SECTORWISE DETAIL OF CENTRAL PROJECTS

Atomic Energy BHAVINI LIMITED

SN Project Name DOA Cost Original Cost Anti. EXPenditure 1 PROTOTYPE FAST 9/2003 3492.00 5677.00 2049.67 (BHAVINI, 500 MWE)

NUCLEAR POWER CORPORATION OF INDIA LIMITED

SN Project Name DOA Cost Original Cost Anti. EXPenditure 2 KUDANKULAM APP (NPCIL) 12/2001 13171.00 13171.00 12446.00

Civil Aviation AIRPORT AUTHORITY OF INDIA LIMITED

SN Project Name DOA Cost Original Cost Anti. EXPenditure 3 CONST. NEW TERMINAL BIDG. MADURAI 4/2007 84.00 84.92 42.27

4 STREN. and EXTN. OF RUNWAY at Trichy 3/2003 25.93 25.93 21.48

5 SITC NEW INTEGRATED ATS SYSTEM 8/2007 69.60 69.60 0.00 AIRPORT

6 Construction of 4 Nos. Night Parking 10/2007 29.45 29.45 10.90 stands for B-747 Aircraft at Chennai Airport

7 Expansion & Modification of Existing 10/2007 78.00 78.00 3.75 Terminal building at Coimbatore

8 C/O INTEGERATED CARGO COMPLEX(PH-III) 8/2008 144.94 144.94 21.86 AT CHENNAI AIRPORT

9 D/O OF TERMINAL BLDG. AND PAVEMENT 1/2008 535.00 535.00 143.97 WORKS AT CHENNAI AIRPORT

10 D/O KAMARAJ DOMESTIC TER-PH-II & EXP. 8/2008 1273.00 1273.00 255.24 ANNA INT. TER BLDG

11 Expansion of Apron for additional 9/2007 41.51 41.51 0.00 Parking bays & construction of part- parallel taxiway at coimbatore

Coal NEYVELI LIGNITE CORPORATION SN Project Name DOA Cost Original Cost Anti. EXPenditure 12 TUTICORIN THERMAL POWER PROJECT 5/2008 4904.54 4904.54 502.63

SECTORWISE DETAIL OF CENTRAL PROJECTS

13 TPS-II EXPANSION (1470MW TO 1970MW) 10/2004 2030.78 2453.57 1873.08 (NLC)

14 EXPANSION OF TPS-II 10/2004 2030.78 2453.57 1873.08

15 EXPANSION OF MINE-II 10/2004 2161.28 2295.93 1715.76

Petroleum CORPORATION LIMITED SN Project Name DOA Cost Original Cost Anti. EXPenditure 16 CONSTRUCTION OF NEW TERMINAL AT ENNORE 1/2008 224.00 224.00 35.28 CHENNAI

Power POWER GRID CORPORATION OF INDIA LIMITED

SN Project Name DOA Cost Original Cost Anti. EXPenditure 17 TRANSMISSION SYSTEM ASSOCIATED WITH 5/2008 90.26 90.26 57.61 CHENNAI NTPC-TNEB JV TPS

18 NEYVELI TS-II TRANSIMISSION SYSTEM 1/2005 691.83 913.33 706.05 (PGCIL)

19 KUNADANKULAM-APP TRANS. SYSTEM (PGCIL) 5/2005 1779.29 1896.65 1465.48

20 SYSTEM STRENGTHENING - VII OF SOUTHERN 5/2005 279.30 340.14 282.50 REGION (PGCIL)

Railways LINE DOUBLING

SN Project Name DOA Cost Original Cost Anti. EXPenditure 21 KANKANADI PANAMBUR T.N 4/2006 70.00 70.00 0.23

22 PATTABIRAM-ARAKKONAM,SR 4/2002 71.94 124.00 151.76

METROPOLITAN RAPID TRANSPORT PROJECTS

SN Project Name DOA Cost Original Cost Anti. EXPenditure 23 EXT. OF MRTS FROM VELACHERY TO STN. 4/2006 415.59 495.74 53.06 THOMAS

RAIL VIKAS NIGAM LTD.

SN Project Name DOA Cost Original Cost Anti. EXPenditure SECTORWISE DETAIL OF CENTRAL PROJECTS

24 TAHANJAVUR-VILLUPURAM GAUGE CONVERSION 10/2001 223.00 425.90 556.93 (G.C)(SR)

SIGNALLING & TELECOMMUNICATIONS

SN Project Name DOA Cost Original Cost Anti. EXPenditure 25 MADRAS BEACH GUMMUND.AWS 3/2000 6.45 53.54 46.19

SOUTHERN RAILWAY

SN Project Name DOA Cost Original Cost Anti. EXPenditure 26 KARUR-SALEM(NL),SR 2/1997 155.55 613.00 61.86

27 TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC) 9/1995 100.00 548.96 374.06

28 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI- 9/2007 404.19 711.15 36.81 THIRU 'PONDI'-AGASTHAMPALLI

29 TINDIVANAM-GINGEE-TIRUVANNAMALAI (NL) 9/2006 125.00 227.40 11.01

30 ATTIPATTU- KORUKUPET,SR 4/1999 40.10 71.00 99.98

31 CHENNAI-BEACH-ATTIPATTU 4/2003 50.23 50.23 0.16

32 CHENNAI- KURUKKUPET 4/2003 59.57 85.70 0.44

33 TIDIVANAM-NAGARI (NL) 9/2006 456.00 582.83 22.05

34 DINDIGUL-POLLACHI-PALGHAT-POLLACHI AND 9/2006 343.17 639.00 158.61 COIMBATORE

35 VILLUPURAM-KATPADI (GC)(SR) 2/2000 175.00 502.14 453.51

WORKSHOPS & PRODUCTION UNIT

SN Project Name DOA Cost Original Cost Anti. EXPenditure 36 INTEGRAL COACH -PAINTING FACILITIES 3/2001 26.55 33.21 29.25

37 AUGMENTATION OF SPRING MANU. FCC 7/2004 34.66 37.96 0.80

SECTORWISE DETAIL OF CENTRAL PROJECTS

38 ICFAUG.OF FACILITIES FOR 3/2002 45.32 49.41 26.84

Road Transport & Highways DEPT OF ROAD TRANSPORT & HIGHWAYS SN Project Name DOA Cost Original Cost Anti. EXPenditure 39 KARUR TO KANGAYAM T.N 2/2006 63.01 63.01 143.66

40 KANGYAM TO COIMBATORE T.N 2/2006 79.52 79.52 106.80

NATIONAL HIGHWAYS AUTHORITY OF INDIA

SN Project Name DOA Cost Original Cost Anti. EXPenditure 41 THUMPIPADI - SALEM PH-1 4/2000 82.49 82.49 109.55

42 THOPURGHAT - THUMPIPADI 12/2003 92.54 92.54 94.59

43 CHENNAI-ENNORE EXPRESS WAY 4/2000 45.29 0.00 60.61

44 TRICHY - DINDIGUAL NH-45 3/2005 576.00 576.00 172.90

45 MADURAI -KANNIAKUMARI SEC. (NS-42/TN) 12/2003 507.49 507.49 301.37 NH-7, KM.120 TO KM.160

46 MADURAI -KANIAKUMARI SECTION (NS-41/TN) 12/2003 323.36 323.36 189.80 NH-7,KM.80 TO KM.120

47 PADALUR-TRICHY, NH-45 3/2005 320.00 320.00 636.10

48 THANJAUR-TRICHY,NH-67(NHAI) 3/2005 280.00 280.00 533.50

49 TOVARAMKURCHI-MADURAI,NH45B (NHAI) 4/2000 263.00 263.00 317.74

50 IMPROVEMENT OF ACCESS OF GQ WITHIN 12/2003 210.00 210.00 579.82 CHENNAI CITY(NHAI) OTHERS

51 CHENNAI BYPASS (NHAI) OTHERS, NH-45, 4 12/2003 480.00 480.00 760.60 AND 5

52 KANYAKUMARI-PANAGUDI (NS CORR. PH-II) 1/2004 120.00 120.00 84.51 (KM 203-233.60), NH-7

SECTORWISE DETAIL OF CENTRAL PROJECTS

53 TRICHY BYPASS END TO TOVARAMKURCHI (NH- 3/2005 261.00 261.00 286.29 45B)(NHAI)

54 MADURAI-ARUPKOTTAI-TUTICORIN, KM.138.8 3/2005 629.00 629.00 749.60 TO KM.264.5, NH-45 B

55 SALEM TO KERALA BORDER SEC(TN6), 12/2003 469.80 469.80 665.80 KM.203.96 NH7 TO KM 53 NH47

56 SALEM - U / UNDRUPET(BOT -1/TN-06) NH - 3/2005 941.00 941.00 266.60 68

57 TRICHY - KORUR NH-67 3/2005 516.00 516.00 213.30

58 PONDICHERY - TINDIVANAU NH-66 3/2005 285.00 285.00 204.60

PLANING COMMISSION

SN Project Name DOA Cost Original Cost Anti. EXPenditure 59 CHENNAI ENNORE EXPRESS WAY T.N 4/2000 76.76 0.00 0.00

Shipping & Ports PORT TRUST

SN Project Name DOA Cost Original Cost Anti. EXPenditure 60 CONSTRUCTION OF BERTH NO. 9 7/2006 40.00 44.57 34.08

61 PROVISION OF 10-15 NW WIND MILL 2/2005 75.00 44.67 0.00 OPERATED POWER GENERATOR

62 PROCUREMENT OF 7 NO. 15 ROPE CRANES 3/1998 26.00 26.00 14.67

63 REPL.7 NOS. WHARF CRANE 3/1998 64.00 60.00 29.64

64 SETHUSAMUDRAM SHIP CHANNEL PROJECT 6/2005 2427.40 2427.40 809.61

SCIL

SN Project Name DOA Cost Original Cost Anti. EXPenditure 65 ENNORE MANALI EXPRESS WAY,F/O SPECIAL 10/2002 150.00 309.00 23.26 PURPOSE VEHICLE (SPV)

Steel LIMITED (SAIL) SECTORWISE DETAIL OF CENTRAL PROJECTS

SN Project Name DOA Cost Original Cost Anti. EXPenditure 66 EXPANSION OF 1/2008 1902.00 1902.00 1134.00

Telecommunications BHARAT SANCHAR NIGAM LIMITED

SN Project Name DOA Cost Original Cost Anti. EXPenditure 67 CONSTRUCTION OF ADMIN. BUILDING AT 9/2006 95.67 95.67 8.89 GREAMS RAOD, CHEENAI

68 GSM EQUIPMENT OF 1006280 LINES IN 6/2008 409.21 483.54 470.24 TAMILNADU PH-4.5