SECTORWISE DETAIL OF CENTRAL PROJECTS
Atomic Energy BHAVINI LIMITED
SN Project Name DOA Cost Original Cost Anti. EXPenditure 1 PROTOTYPE FAST BREEDER REACTOR 9/2003 3492.00 5677.00 2049.67 (BHAVINI, 500 MWE)
NUCLEAR POWER CORPORATION OF INDIA LIMITED
SN Project Name DOA Cost Original Cost Anti. EXPenditure 2 KUDANKULAM APP (NPCIL) 12/2001 13171.00 13171.00 12446.00
Civil Aviation AIRPORT AUTHORITY OF INDIA LIMITED
SN Project Name DOA Cost Original Cost Anti. EXPenditure 3 CONST. NEW TERMINAL BIDG. MADURAI 4/2007 84.00 84.92 42.27
4 STREN. and EXTN. OF RUNWAY at Trichy 3/2003 25.93 25.93 21.48
5 SITC NEW INTEGRATED ATS SYSTEM CHENNAI 8/2007 69.60 69.60 0.00 AIRPORT
6 Construction of 4 Nos. Night Parking 10/2007 29.45 29.45 10.90 stands for B-747 Aircraft at Chennai Airport
7 Expansion & Modification of Existing 10/2007 78.00 78.00 3.75 Terminal building at Coimbatore
8 C/O INTEGERATED CARGO COMPLEX(PH-III) 8/2008 144.94 144.94 21.86 AT CHENNAI AIRPORT
9 D/O OF TERMINAL BLDG. AND PAVEMENT 1/2008 535.00 535.00 143.97 WORKS AT CHENNAI AIRPORT
10 D/O KAMARAJ DOMESTIC TER-PH-II & EXP. 8/2008 1273.00 1273.00 255.24 ANNA INT. TER BLDG
11 Expansion of Apron for additional 9/2007 41.51 41.51 0.00 Parking bays & construction of part- parallel taxiway at coimbatore
Coal NEYVELI LIGNITE CORPORATION SN Project Name DOA Cost Original Cost Anti. EXPenditure 12 TUTICORIN THERMAL POWER PROJECT 5/2008 4904.54 4904.54 502.63
SECTORWISE DETAIL OF CENTRAL PROJECTS
13 TPS-II EXPANSION (1470MW TO 1970MW) 10/2004 2030.78 2453.57 1873.08 (NLC)
14 EXPANSION OF TPS-II 10/2004 2030.78 2453.57 1873.08
15 EXPANSION OF MINE-II 10/2004 2161.28 2295.93 1715.76
Petroleum HINDUSTAN PETROLEUM CORPORATION LIMITED SN Project Name DOA Cost Original Cost Anti. EXPenditure 16 CONSTRUCTION OF NEW TERMINAL AT ENNORE 1/2008 224.00 224.00 35.28 CHENNAI
Power POWER GRID CORPORATION OF INDIA LIMITED
SN Project Name DOA Cost Original Cost Anti. EXPenditure 17 TRANSMISSION SYSTEM ASSOCIATED WITH 5/2008 90.26 90.26 57.61 CHENNAI NTPC-TNEB JV TPS
18 NEYVELI TS-II TRANSIMISSION SYSTEM 1/2005 691.83 913.33 706.05 (PGCIL)
19 KUNADANKULAM-APP TRANS. SYSTEM (PGCIL) 5/2005 1779.29 1896.65 1465.48
20 SYSTEM STRENGTHENING - VII OF SOUTHERN 5/2005 279.30 340.14 282.50 REGION (PGCIL)
Railways LINE DOUBLING
SN Project Name DOA Cost Original Cost Anti. EXPenditure 21 KANKANADI PANAMBUR T.N 4/2006 70.00 70.00 0.23
22 PATTABIRAM-ARAKKONAM,SR 4/2002 71.94 124.00 151.76
METROPOLITAN RAPID TRANSPORT PROJECTS
SN Project Name DOA Cost Original Cost Anti. EXPenditure 23 EXT. OF MRTS FROM VELACHERY TO STN. 4/2006 415.59 495.74 53.06 THOMAS
RAIL VIKAS NIGAM LTD.
SN Project Name DOA Cost Original Cost Anti. EXPenditure SECTORWISE DETAIL OF CENTRAL PROJECTS
24 TAHANJAVUR-VILLUPURAM GAUGE CONVERSION 10/2001 223.00 425.90 556.93 (G.C)(SR)
SIGNALLING & TELECOMMUNICATIONS
SN Project Name DOA Cost Original Cost Anti. EXPenditure 25 MADRAS BEACH GUMMUND.AWS 3/2000 6.45 53.54 46.19
SOUTHERN RAILWAY
SN Project Name DOA Cost Original Cost Anti. EXPenditure 26 KARUR-SALEM(NL),SR 2/1997 155.55 613.00 61.86
27 TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC) 9/1995 100.00 548.96 374.06
28 MAYLADUTHURAI-THIRUVARUR-KARAIKUDI- 9/2007 404.19 711.15 36.81 THIRU 'PONDI'-AGASTHAMPALLI
29 TINDIVANAM-GINGEE-TIRUVANNAMALAI (NL) 9/2006 125.00 227.40 11.01
30 ATTIPATTU- KORUKUPET,SR 4/1999 40.10 71.00 99.98
31 CHENNAI-BEACH-ATTIPATTU 4/2003 50.23 50.23 0.16
32 CHENNAI- KURUKKUPET 4/2003 59.57 85.70 0.44
33 TIDIVANAM-NAGARI (NL) 9/2006 456.00 582.83 22.05
34 DINDIGUL-POLLACHI-PALGHAT-POLLACHI AND 9/2006 343.17 639.00 158.61 COIMBATORE
35 VILLUPURAM-KATPADI (GC)(SR) 2/2000 175.00 502.14 453.51
WORKSHOPS & PRODUCTION UNIT
SN Project Name DOA Cost Original Cost Anti. EXPenditure 36 INTEGRAL COACH -PAINTING FACILITIES 3/2001 26.55 33.21 29.25
37 AUGMENTATION OF SPRING MANU. FCC 7/2004 34.66 37.96 0.80
SECTORWISE DETAIL OF CENTRAL PROJECTS
38 ICFAUG.OF FACILITIES FOR 3/2002 45.32 49.41 26.84
Road Transport & Highways DEPT OF ROAD TRANSPORT & HIGHWAYS SN Project Name DOA Cost Original Cost Anti. EXPenditure 39 KARUR TO KANGAYAM T.N 2/2006 63.01 63.01 143.66
40 KANGYAM TO COIMBATORE T.N 2/2006 79.52 79.52 106.80
NATIONAL HIGHWAYS AUTHORITY OF INDIA
SN Project Name DOA Cost Original Cost Anti. EXPenditure 41 THUMPIPADI - SALEM PH-1 4/2000 82.49 82.49 109.55
42 THOPURGHAT - THUMPIPADI 12/2003 92.54 92.54 94.59
43 CHENNAI-ENNORE EXPRESS WAY 4/2000 45.29 0.00 60.61
44 TRICHY - DINDIGUAL NH-45 3/2005 576.00 576.00 172.90
45 MADURAI -KANNIAKUMARI SEC. (NS-42/TN) 12/2003 507.49 507.49 301.37 NH-7, KM.120 TO KM.160
46 MADURAI -KANIAKUMARI SECTION (NS-41/TN) 12/2003 323.36 323.36 189.80 NH-7,KM.80 TO KM.120
47 PADALUR-TRICHY, NH-45 3/2005 320.00 320.00 636.10
48 THANJAUR-TRICHY,NH-67(NHAI) 3/2005 280.00 280.00 533.50
49 TOVARAMKURCHI-MADURAI,NH45B (NHAI) 4/2000 263.00 263.00 317.74
50 IMPROVEMENT OF ACCESS OF GQ WITHIN 12/2003 210.00 210.00 579.82 CHENNAI CITY(NHAI) OTHERS
51 CHENNAI BYPASS (NHAI) OTHERS, NH-45, 4 12/2003 480.00 480.00 760.60 AND 5
52 KANYAKUMARI-PANAGUDI (NS CORR. PH-II) 1/2004 120.00 120.00 84.51 (KM 203-233.60), NH-7
SECTORWISE DETAIL OF CENTRAL PROJECTS
53 TRICHY BYPASS END TO TOVARAMKURCHI (NH- 3/2005 261.00 261.00 286.29 45B)(NHAI)
54 MADURAI-ARUPKOTTAI-TUTICORIN, KM.138.8 3/2005 629.00 629.00 749.60 TO KM.264.5, NH-45 B
55 SALEM TO KERALA BORDER SEC(TN6), 12/2003 469.80 469.80 665.80 KM.203.96 NH7 TO KM 53 NH47
56 SALEM - U / UNDRUPET(BOT -1/TN-06) NH - 3/2005 941.00 941.00 266.60 68
57 TRICHY - KORUR NH-67 3/2005 516.00 516.00 213.30
58 PONDICHERY - TINDIVANAU NH-66 3/2005 285.00 285.00 204.60
PLANING COMMISSION
SN Project Name DOA Cost Original Cost Anti. EXPenditure 59 CHENNAI ENNORE EXPRESS WAY T.N 4/2000 76.76 0.00 0.00
Shipping & Ports PORT TRUST
SN Project Name DOA Cost Original Cost Anti. EXPenditure 60 CONSTRUCTION OF BERTH NO. 9 7/2006 40.00 44.57 34.08
61 PROVISION OF 10-15 NW WIND MILL 2/2005 75.00 44.67 0.00 OPERATED POWER GENERATOR
62 PROCUREMENT OF 7 NO. 15 ROPE CRANES 3/1998 26.00 26.00 14.67
63 REPL.7 NOS. WHARF CRANE 3/1998 64.00 60.00 29.64
64 SETHUSAMUDRAM SHIP CHANNEL PROJECT 6/2005 2427.40 2427.40 809.61
SCIL
SN Project Name DOA Cost Original Cost Anti. EXPenditure 65 ENNORE MANALI EXPRESS WAY,F/O SPECIAL 10/2002 150.00 309.00 23.26 PURPOSE VEHICLE (SPV)
Steel STEEL AUTHORITY OF INDIA LIMITED (SAIL) SECTORWISE DETAIL OF CENTRAL PROJECTS
SN Project Name DOA Cost Original Cost Anti. EXPenditure 66 EXPANSION OF SALEM STEEL PLANT 1/2008 1902.00 1902.00 1134.00
Telecommunications BHARAT SANCHAR NIGAM LIMITED
SN Project Name DOA Cost Original Cost Anti. EXPenditure 67 CONSTRUCTION OF ADMIN. BUILDING AT 9/2006 95.67 95.67 8.89 GREAMS RAOD, CHEENAI
68 GSM EQUIPMENT OF 1006280 LINES IN 6/2008 409.21 483.54 470.24 TAMILNADU PH-4.5