GMR Business Park (Site A) M/s GMR International Airport Limited SURVEY NOS. 99/1 and 169, MAMIDIPALLI, SAROOR NAGAR,

1. FORM I 2. FORM I A

Submitted By Studies & Documentation by M/s GMR Hyderabad International Airport Limited M/s Team Labs and Consultants 5th Floor, GMR Aero Towers, RGI Airport (An ISO Certified Organization) Shamshabad, Hyderabad - 500409 B-115 -117 & 509, Annapurna Block, Phone: 040-6739 4000 Aditya Enclave, , Hyderabad- 500 038 Phone: 91-040-23748555/616 Fax : 91-040-23748666 e-mail: [email protected]

SUBMITTED TO STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY GOVERNMENT OF APPENDIX I

(See paragraph – 6) FORM 1 S.No Item Details 1 GMR Business Park (Site A) by M/s GMR Name of the Project/s Hyderabad International Airport Limited 2 S.No. in the Schedule B category 3 Proposed capacity/area/length/ Annexure I tonnage to be handled/command area/lease area/number of wells to be Expected cost of the project: INR 318.79 Cr drilled 4 New/Expansion/Modernization New 5 Existing Capacity/Area etc. NA 6 Category of Project i.e. 'A' or 'B' B category 7 Does it attract the general condition? If yes, please specify No 8 Does it attract the Specific condition? If yes, please specify. No 9 The proposed GMR Business Park (Site A) will be located within the existing Rajiv Gandhi International Airport Campus, Shamshabad, Hyderabad. The location map and study area map (10 km radius) of the Location project site are enclosed Plot/Survey/Khasra No. Survey no. 99/1, 169 Village Mamidipalli Tehsil Saroor Nagar District Ranga Reddy District State Telangana 10 Nearest railway station/airport along Umda Nagar Railway Station at a distance with distance in kms. of 5.2 km 11 Nearest Town, City, District Headquarters Hyderabad at a distance of 20 km along with distance in kms. 12 Village Panchayats, Zilla Parishad, Hyderabad Airport Development Authority Municipal Corporation, Local body (complete postal address with telephone nos. to be given) 13 Name of the Applicant Mr. Sourabh Jain 14 Registered Address M/s GMR Hyderabad International Airport Limited 5th Floor, GMR Aero Towers, RGI Airport, Shamshabad, Hyderabad - 500409 15 M/s GMR Hyderabad International Airport Limited Address for Correspondence: 5th Floor, GMR Aero Towers, RGI Airport, Shamshabad, Hyderabad - 500409

FI - 1 S.No Item Details Name Mr. Sourabh Jain Designation (Owner/Partner/CEO) Head Aerospace & Airport City Business M/s GMR Hyderabad International Airport Limited 5th Floor, GMR Aero Towers, RGI Airport, Address Shamshabad, Hyderabad - 500409 Pin Code 500 409 E-mail [email protected] Telephone Number 040-6676 4000 Fax No. 040-6646 2626 16 Details of alternative Sites examined, if Village-District-State any. Location of these sites should be NA shown on a topo sheet. 17 Interlinked Projects No 18 Whether separate application of interlinked project has been submitted? No 19 If yes, date of submission NA 20 If no, reason NA 21 Whether the proposal involves No approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z Notification, 1991? 22 Whether there is any Government The existing airport land falls under the Order/Policy relevant/relating to the Notified Area Committee’s jurisdiction. site? GO 287 (HADA Master Plan) 23 Forest land involved (hectares) No 24 Whether there is any location pending No against the project and /or land in which the project is propose to be set up? (a) Name of the Court (b) Case No (c) Orders/directions of the Court, if any and its relevance with the proposed project.

FI - 2 (I) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Details thereof (with approximate quantities /rates, S.No. Information/Checklist confirmation wherever possible) with source Yes/No of information data 1.1 Permanent or temporary change in Yes The proposed project will be land use, land cover or topography implemented within the existing including increase in intensity of land Airport area only. use (with respect to local land use Entire land required is under the plan) Possession of RGIA. No new land Acquisition is involved. Hence, no changes in land use or Land cover. 1.2 Clearance of existing land, vegetation No The land is barren containing and buildings? mainly shrubs and bushes. The same shall be cleared. 1.3 Creation of new land uses? No The land use is GMR Business Park (Site A) land use associated with Airport. 1.4 Pre-construction investigations e.g. No - bore houses, soil testing? 1.5 Construction works? Yes The project is a construction project of Commercial Office Building. 1.6 Demolition works? No - 1.7 Temporary sites used for construction Yes Labour force will be provided works or housing of construction with temporary accommodation workers? within the site. 1.8 Above ground buildings, structures or Yes Built up Area: Annexure I earthworks including linear structures, Cut and Fill quantity: Annexure II cut and fill or excavations 1.9 Underground works including mining or No tunneling? 1.10 Reclamation works? No 1.11 Dredging? No 1.12 Offshore structures? No 1.13 Production and manufacturing No Commercial Office building processes? construction project 1.14 Facilities for storage of goods or Yes Construction materials like materials? cement, steel, sand, paints, aggregate etc shall be stored on site. The cement and paints are stored indoor, while the

FI - 3 Details thereof (with approximate quantities /rates, S.No. Information/Checklist confirmation wherever possible) with source Yes/No of information data remaining materials are stored outdoors. 1.15 Facilities for treatment or disposal of Yes The sewage generated from the solid waste or liquid effluents? domestic uses will be treated in the dedicated Sewage Treatment Plant. The treated sewage shall be completely reused for landscaping / flushing. The water balance, water recycling quantities and the design details of sewage treatment plant are presented in Annexure –III. Solid waste shall be treated at the existing facility of RGIA. The capacity of the existing SWM facility is being expanded and the solid waste from the Project shall be accommodated within that capacity. All the biodegradable waste will be composted. Recyclable waste will be segregated and sold. The solid waste management plan is enclosed in Annexure – IV. 1.16 Facilities for long term housing of No Required labour shall be drawn operational workers? from neighboring areas/ villages. 1.17 New road, rail or sea traffic during No Not Envisaged construction or operation? 1.18 New road, rail, air waterborne or other No Not Envisaged transport infrastructure including new or altered routes and stations, ports, airports etc? 1.19 Closure or diversion of existing No Not required transport routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission lines or No Not required pipelines? 1.21 Impoundment, damming, culverting, No All existing local drainage realignment or other changes to the features shall be considered hydrology of watercourses or while designing the storm water

FI - 4 Details thereof (with approximate quantities /rates, S.No. Information/Checklist confirmation wherever possible) with source Yes/No of information data aquifers? collection and disposal system so that there won’t be any impact on the natural regime 1.22 Stream crossings? No

1.23 Abstraction or transfers of water form No ground or surface waters? 1.24 Changes in water bodies or the land No No significant changes in the surface affecting drainage or run-off? water bodies or land surface. Storm water drains shall be sufficiently designed to take the surface water increased flows due to the new land use pattern. 1.25 Transport of personnel or materials for Yes Trucks shall be used for construction, operation or transporting the materials. decommissioning? 1.26 Long-term dismantling or No decommissioning or restoration works? 1.27 Ongoing activity during No decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either No No influx of people is envisaged temporarily or permanently? although during construction stage temporary labour will be working at the construction site.

1.29 Introduction of alien species? No

1.30 Loss of native species or genetic No diversity? 1.31 Any other actions? No

FI - 5 2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Details thereof (with approximate quantities /rates, S.No. Information/checklist confirmation Yes/No wherever possible) with source of information data

2.1 Land especially undeveloped or Yes Undeveloped land of 4.69 agricultural land (ha) hectares

2.2 Water (expected source & competing Yes Source will be from existing users) unit: KLD Airport water supply system which subsequently getting water from HMWSSB. (517.5 KLD) 2.3 Minerals (MT) No

2.4 Construction material – stone, aggregates, Yes Annexure – V: Lead distances of sand / soil (expected source – MT) construction materials. Annexure – VI: Quantity of construction material requirement. 2.5 Forests and timber (source – MT) Yes Local authorized Suppliers

2.6 Energy including electricity and fuels Yes DG sets and construction (source, competing users) Unit: fuel (MT), equipment shall be used during energy (MW) construction, which shall use mainly HSD as fuel. The energy requirement during occupation is presented in Annexure – VII. DG sets (1500 kVA X 3 nos. 1250 KVA x 2 nos. 750 KVA x 6 nos.) shall be used during occupation in the event of power shut down. 2.7 Any other natural resources (use No appropriate standard units)

FI - 6 3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Details thereof (with approximate quantities/rates, S.No. Information/Checklist confirmation Yes/No wherever possible) with source of information data 3.1 Use of substances or materials, which are No General building materials used hazardous (as per MSIHC rules) to human are Paints, adhesive etc. health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or affect No disease vectors (e.g. insect or water borne diseases) 3.3 Affect the welfare of people e.g. by Yes The project will give changing living conditions? employment to 11500 people. The population in surrounding area will get benefited due to job opportunities (direct & indirect) during construction & operational phase. Since, this is not a polluting industry; no adverse impact on health is envisaged. 3.4 Vulnerable groups of people who could No be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No

FI - 7 4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Details thereof (with approximate quantities/rates, wherever S.No. Information/Checklist confirmation Yes/No possible) with source of information data 4.1 Spoil, overburden or mine wastes No

4.2 Municipal waste (domestic and or Yes 3450 kg/day commercial wastes)

4.3 Hazardous wastes (as per Hazardous Yes Used oil: 400 l/year Waste Management Rules) Used Batteries: 25 nos. /year

4.4 Other industrial process wastes No

4.5 Surplus product No

4.6 Sewage sludge or other sludge from Yes 25 kg/day sludge from STP shall be effluent treatment reused as manure. 4.7 Construction or demolition wastes Yes Construction waste shall be disposed to authorized scrap dealers of respective products 4.8 Redundant machinery or equipment No

4.9 Contaminated soils or other materials No

4.10 Agricultural wastes No

4.11 Other solid wastes No

FI - 8 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)

Details thereof (with approximate S.No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data 5.1 Emissions from combustion of fossil fuels No from stationary or mobile sources 5.2 Emissions from production processes No Vehicular transport is the other source of emission. 5.3 Emissions from materials handling including No storage or transport 5.4 Emissions from construction activities Yes Construction equipment including plant and equipment and DG sets which mainly use HSD, as fuel shall generate emissions. Fugitive Dust will be generated during construction period. Dust suppression system (mobile water sprayers) would be provided all around the construction site to suppress/reduce the dust generation. 5.5 Dust or odours from handling of materials Yes Dust from construction including construction materials, sewage activities is envisaged and and waste will be handled as mentioned above. There will be no odour causing sources 5.6 Emissions from incineration of waste No

5.7 Emissions from burning of waste in open air No (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No

FI - 9 6. Generation of Noise and Vibration, and Emissions of Light and Heat:

Details thereof (with approximate quantities/rates, S.No. Information/Checklist confirmation Yes/No wherever possible) with source of information data with source of information data 6.1 From operation of equipment e.g. Yes Construction activity and the engines, ventilation plant, crushers construction equipment are the main sources of noise and vibration during construction. There are no major sources of noise during occupation phase. The equipment noise levels will be below 85 dB(A). Acoustic enclosures will be provided as applicable. 6.2 From industrial or similar processes No

6.3 From construction or demolition Yes Noise levels in the range of 80- 105 dB (A) will be generated during construction activities. Workers will be provided with protective equipment such as Earmuffs etc. 6.4 From blasting or piling No No blasting activity envisaged.

6.5 From construction or operational traffic NO Traffic envisaged for construction will not be significant and hence will not increase the noise levels. During operation time, the traffic envisaged is more from the Airport and not from the city, hence increase in noise levels is not envisaged. 6.6 From lighting or cooling systems Yes The noise level due to operation of chiller plant will be less than 85 dB (A). 6.7 From any other sources No

FI - 10 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Details thereof (with approximate quantities/rates, S.No. Yes/No wherever possible) with source Information/Checklist confirmation of information data 7.1 From handling, storage, use or spillage No Used batteries and waste oil shall of hazardous materials be stored separately.

7.2 From discharge of sewage or other No Sewage shall be treated effluents to water or the land appropriately to conform to (expected mode and place of regulatory standards and used in discharge) greenbelt.

7.3 By deposition of pollutants emitted to No The project shall not emit air into the land or into water substantial quantities of pollutants to have an impact on the air quality. 7.4 From any other sources No

7.5 Is there a risk of long term build up of No pollutants in the environment from these sources?

FI - 11 8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Details thereof (with approximate quantities/ rates, Information/Checklist confirmation Yes/No wherever possible) with source S.No. of information data

8.1 From explosions, spillages, fires etc from No Precautionary measures shall be storage, handling, use or production of adopted. Fire plan shall be put hazardous substances in place before occupation of the property. 8.2 From any other causes No

8.3 Could the project be affected by natural No The site is located at a higher disasters causing environmental damage elevation and the seismic zone (e.g. floods, earthquakes, landslides, for the project area is Zone II, cloudburst etc)? which is considered safe.

FI - 12 9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Details thereof (with approximate quantities/rates, S. No. Information/Checklist confirmation Yes/No wherever possible) with source of information data 9.1 Lead to development of supporting.

Lities, ancillary development or development Stimulated by the project which could Yes have impact on the environment e.g.:

• Supporting infrastructure (roads, power Yes supply, waste or waste water treatment, etc.) No

• Housing development No

• Extractive industries No

• Supply industries

• Other

9.2 Lead to after-use of the site, which could No have an impact on the environment 9.3 Set a precedent for later developments Yes The surrounding areas shall develop as commercial areas.

9.4 Have cumulative effects due to proximity No to other existing or planned projects with similar effects

FI - 13 (II) Environmental Sensitivity

Aerial distance (within 15 km.) S.No. Areas Name/ Proposed project location Identity boundary 1 Areas protected under international No conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or sensitive for Yes Nehru Zoological Park - ecological reasons - Wetlands, watercourses 12.5 KM N or other water bodies, coastal zone, Chilkur National Park - 17 biospheres, mountains, forests Km, NW Musa River - 13.5 km NW Himayat Sagar – 10.0 km - 10.5 km N Rawiral Cheruvu - 6.4 km SE Umdasagar – 6.4 km, N 3 Areas used by protected, important or Yes Chilkur National Park - 17 sensitive species of flora or fauna for KM, NW breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine or underground Yes Musa River - 13.5 km NW waters Himayat Sagar –10.0 km

5 State, National boundaries No

6 Routes or facilities used by the public for Yes National Highway, NH-7 - access to recreation or other tourist, pilgrim 3.2 km, NW areas Railway line - 2.8 km, W Srisailam State Highway – 4.5 km, E 7 Defense installations Yes Defense Research Laboratory - 10 km, NE Research Center Imarat - 3.8 km, E National Police Academy - 8 km, N 8 Densely populated or built-up area Yes Shamshabad town - 5.0 km, W

9 Areas occupied by sensitive man-made land No uses (hospitals, schools, places of worship, community facilities) 10 Areas containing important, high quality or Yes Umdasagr - 3.5 km, N

FI - 14 Aerial distance (within 15 km.) S.No. Areas Name/ Proposed project location Identity boundary scarce resources Musa River - 13.5 km NW (Ground water resources, surface resources, Himayat Sagar – 10 km forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or No environmental damage. (Those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard which No could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

FI - 15 (III).Proposed Terms of Reference for EIS studies Scope of Work of EIS

“...The EIS shall cover the following:

Description of the proposed project The first task:” Description of the proposed project” forms a vital component of the Environmental Impact Statement (EIS) as it provides the basis for evaluating the likely causes of Environmental Impacts. Land use issues dictate the significance of land loss/change. It is essential that the key components of the project shall be clearly determined as far as possible at this stage.

Assessment of Environmental Impacts Based upon the results from the review of existing information, field visits, site data collection and consultation, for each component of environment (physical, biological and socio economic) the positive, negative, direct and indirect, temporary and permanent impact s will be evaluated along with an indication of the degree of impact, i.e., whether the impact is significant, moderate, minor or negligible.

Environment Management Plan and Mitigation Plan For each significant negative impact identified, specialist shall work closely with the engineering team/technical consultants to suggest practicable measures to avoid or mitigate the impact. Suggestions for compensation shall be given where there is no other alternative course of action.

The mitigation of environmental impacts will be by three mechanisms. =>Introduction of mitigation features through the engineering practices. =>Implementation of environmental controls during construction and operation. =>Legislative control involving compliance with Indian environmental laws.

The Environmental management plan shall include an estimate of capital and recurring costs of mitigation measures and will identify the parties and institutional framework for implementation.

Monitoring Plan Having identified the significant environmental impact that are likely to arise as a result of the construction of Commercial Office building project, the project team shall specify what monitoring is required during the various phases of the project cycle.

The monitoring plan will identify parameters and frequency of monitoring and responsible organization

FI - 16 FI - 17 Annexure-I

Built up Area Statement No. of Total Site Built up area (m2) Land Use 2 floors Area (m ) Parking Office Total Existing (Obtained Building Permit Order) Tower - 1 G + 5 3702 18370 18370 Proposed Tower - 2 B + G + 6 3451 6168 18465 24633 Tower - 3 B + G + 6 7143 13026 39471 52497 Tower - 4 B + G + 6 3093 6293 19070 25363 Tower - 5 B + G + 6 3093 6293 19070 25363 Green area 7502 Road area 9817 Open area 2879 Surface Parking 6175 Total 46855 31780 114446 146226

A - 1 Annexure-II

Cut & Fill Quantities Qty. of fill Qty of cut Surplus fill Surplus cut S. No. Area (m3) (m3) (m3) (m3) 1 Site 70283 117138 ------46855

A - 2 Annexure-III

Water Requirement of the Project Total No. of Water requirement Total Water Description Persons lpcd* Requirement in KLD Office 11500 45 517.5 Total 11500 517.5 * Water requirement as per NBC

Water Savings Proposed Water Effective Water Treated water Description No. of Persons Requirement Requirement in Reuse KLD in KLD KLD Office 11500 517.5 230.0 287.5 Total 11500 517.5 230.0 287.5

The effective water consumption is reduced by 230.0 kl/day and the requirement will be in the order of 287.5 kl/day.

Water Balance during occupation stage Input KL/Day Output KL/Day Domestic water 287.5 HVAC Chillers 181.0 Treated waste water for Recycled water 230.0 Recycle 230.0 Water requirement for green belt during non monsoon 3.0 Losses approx 20% 103.5 Total 517.5 Total 517.5

The water used is about 517.5 KL/day would generate 414.0 KL/day of wastewater which has to be treated for reuse.

SEWAGE TREATMENT PLANT Treatment plant for treating sewage in the project site has been proposed for a capacity of 500 m3/day. The Sewage Treatment flow chart is shown in below figure.

Sewage treatment plant based on Fluidized Aerobic Bio Reactor (FAB) technology The raw sewage will be collected in a collection sump and pumped to mechanical bar screen chamber for removal of large floating matter followed by grit removal in Grit Chamber. The raw sewage will then be collected in an equalization tank for homogenization of hydraulic load. The tank contents will be kept in suspension by means of course bubble serration through pipe grid. The equalization tank, with air flow indicator for continuous monitoring of air supply to the tank in order to avoid septic conditions, will be covered from top (RCC or FRP) to avoid nuisance. The equalized effluent will then be pumped to two Fluidized Aerobic Bio Reactors (FAB) in series where A - 3 BOD/COD reduction can be achieved by virtue of aerobic microbial activities. The oxygen required will be supplied through coarse air bubble diffusers. The bio-solids formed in the biological process will be separated in the down stream Tube Settler. The clear supernatant will gravitate to the chlorine contact tank where sodium hypochlorite will be dosed for disinfection of treated water prior to disposal.

Fluidized Aerobic Bio Reactor (FAB) Conventional effluent treatment plants are large sized, power intensive and require a lot of monitoring. Scarcity of open space and rising land a power costs have forced the industries to look out for space saving, compact and efficient treatment options. This has led to the development attached growth processes where the bio mass is retained within the aeration tank obviating the need for recycle. These plants are not only compact but also user friendly. The endeavor to have a continuously operating, no-clogging biofilm reactor with no need for back washing, low head-loss and high specific biofilm surface area culminated in the most advanced technology of aerobic biological fluidized bed treatment where the biofilm (biomass) grows on small carrier elements that move along with the water in the reactor. The movement is normally caused by aeration in the aerobic version of the reactor.

The reactor combines all the advantages and best features of Trickling filters, Rotating biological contractors, activated sludge process and submerged fixed film reactors while eliminating the drawbacks of these systems. The plants are more compact and more energy efficient.

The Fluidized Aerobic Bio Reactor (FAB) consists of a tank in any shape filled up with small carrier elements. The elements are made up of special grade PVC or polypropylene of controlled density (shown in plate). For media of specific gravity 0.92-0.96 the overall density could be expected to increase up to 9.5% when full of biomass such that they can fluidize using an aeration device. A biofilm develops on the elements, which move along the effluent in the reactor. The movement within the reactor is generated by providing aeration with the help of diffusers placed at the bottom of the reactor. Then thin biofilm on the elements enables the bacteria to act upon the biodegradable matter in the effluent and reduce the BOD/COD content in the presence of oxygen available from the air that is used for fluidization.

Characteristics of Waste water Parameter Quantity in mg/l PH 6 – 7 Total Suspended Solids 400 – 600 BOD 200 – 300 COD 450 – 500

Design of the unit Basic data Flow : 414 KLD Capacity : 500 m3 Peak factor : 3.5

A - 4 Peak flow Q peak : 1750 m3/day Influent BOD : 200 mg/lit Influent Suspended Solids : 200 mg/lit Influent COD : 350 mg/lit Effluent BOD : 30 mg/lit Effluent COD : 200 mg/lit Effluent Suspended Solids : 100 mg/lit

1. Bar Screen Chamber Average flow : 0.0054 m3/sec Peak factor : 3.5 Peak flow : 0.019 m3/sec Velocity at peak flow : 0.75 m/Sec Effective area of screen Required At average flow : 0.017 m2 At Peak flow : 0.024 m2 Provide Effective area of screen : 0.024 m2 Considering the bar of dia. 10 mm(w) and clear spacing of 20 mm (b) Overall area required : 0.036 m2 Considering screen depth as : 0.5 m Number of clear spacing : 1.8 Number of bars : 2 Consider 4 Nos. Hence Provide 5 bars Provide a screen of 0.5 m X 0.5 m at an inclination of sin 600. In a screen channel of one meter (1 m) length.

2. Grit Chamber : The flow from the bar screen chamber is let into the Grit Chamber of minimum 2 hours capacity. This tank is provided to even out the flow variation, and to provide a continuous feed into the secondary biological treatment units. Peak flow Q : 0.019 m3/sec Providing a flow through velocity of 0.30 m/sec Cross sectional area of Channel : 0.07 m2 Surface area of channel : 1.4 m2 Assuming depth d : 0.2 m Width of channel : 0.3 m (say 0.3m) Length of channel : 4.3 m (say 4.3 m) Provide two channels each of 0.2 m wide and 4.3 m long with depth of waste water 0.2 m.

3. Equalization tank: The flow from the bar screen chamber is let into the equalization tank of minimum 2hours capacity. This tank is provided to even out the flow variation, and to provide a continuous feed into the secondary biological treatment units. Average flow : 20.8 m3/hr Peak factor : 3.5 Peak flow : 72.91 m3/hr

A - 5 Hydraulic retention tank = 2 hrs at Peak flow Hence required volume of the tank : 145 m3 Provide tank of Capacity : 145 m3 Assuming depth : 5 m Area : 29 m2 Assuming length to width ratio (1:1) ; l=b length of the tank : 5.2 m width of the tank : 5.2 m Air required for agitation : 0.01 m3/ m2 min Total air required : 79.75 m3/hr Air blower required : 100 m3/hr @ 3.8 mwc Effluent transfer pump : 19.58 m3/hr @ 8 mwc

4. Fluidized Aerobic Bio Reactor (FAB): The polypropylene media have been provided with a specific surface area of 350 – 520 m2 /m3. This allows micro-organisms to get attached and biomass concentration can be increased to four folds as compared to Activated Sludge Process. This enables to consider higher Organic loading rates.

The micro-organisms attached to media are kept in a fluid state thereby maintaining the CSTR (continuous Stirrer tank reactor) regime as well as two tanks are provided in series making the plug – flow system. This will enhance the efficiencies and have the merits of both CSTR and plug-flow regimes. Organic loading rate : 3.2 kg BOD/ m3 d Organic load : 94 kg/day Volume of the tank : 29.3 m3 Assume the depth : 5 m No. of tanks in series : 2 Size of the tank : 2.6 m dia. x 5.0 SWD Specific gravity of media : 0.92 to 0.96 Specific surface area of media : 350 – 520 m2 /m3 Media filling : 30 – 50 % of tank volume Oxygen required : 2 kg / kg BOD Oxygen in air : 23% Specific gravity of air @ 30 deg. : 1.65 Aeration : Coarse bubble Oxygen transfer efficiency : 12% Air required : 116.6 m3/hr Air blower required : 150 m3/hr @ 6.5 m wc

5.Tube settler Surface loading rate : 48 m2 /m3 d Surface area required : 9.8 m2 3.0 m x 6.0 m x 2.7 m SWD With Tank size : 55 deg. hopper bottom Tube Modules : 3.0m x 6.0 m x 0.6 m ht. Tube inclination : 60 deg.

A - 6 Settling area for 60 deg slope : 11 m2 /m3 Cross sectional area of tubes : 120 mm x 44 mm Hexagonal Hydraulic radius : 1/61 cm (1.5 cm) Shape factor : 0.6 – 0.7 for media settleable solids

6. Pre Filtration tank The flow from the each individual settling tank i.e., the supernatant liquid is let into the respective Pre-Filtration Tank, which has a minimum 1.5 hours holding capacity. This tank is provided to hold the treated effluent and give an even flow to the pressure sand filter. Average flow : 20.8 m3/hr Peak factor : 2 m3/hr Peak flow : 41.6 m3/hr Provide min 1.5 hours holding capacity. Hence required volume of the tank : 62.5 m3

7. Pressure Sand Filter: Vertical down flow type with graded/sand bed under drain plate with polysterene strains. Flow : 500 m3/day Rate of filtration assumed as : 10 m3/m2/hr Requirement of treated water for usage in 20 hrs : 23.5 m3/hr Dia. of filter of 1 nos. : 1767 mm Provide pressure sand filter of 1800 mm dia. and 2100 mm HOS with sand as media layer, under drain pipe, laterals face piping etc for each stream.

8. Activated Carbon Filter: Vertical down flow type with graded/sand bed under drain plate with polysterene strains. Flow : 500 m3/day Rate of filtration assumed as : 10 m3/m2/hr Requirement of treated water for usage in 20 hrs : 23.5 m3/hr Dia of filter of 1 nos. : 1767 mm Provide Activated Carbon filter of 1700 mm dia with granular Activated carbon as media and 2100 mm HOS with sand as media layer, under drain pipe, laterals face piping etc for each stream.

9.Final Treated Water Holding Tank It is always preferred to provide one final holding tank of minimum one day holding capacity, so that the treated effluents can be stored and used back for gardening or other tertiary purposes. Capacity: 500 m3

A - 7 10. Sludge Filter Press: The biomass in the aeration tank stabilizes BOD in wastewater by consuming the organic matter in the wastewater. The metabolic activity results in growth of the biomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank has been provided with filter press for dewatering sludge. The filtrate drains off through the media, which is again let into equalization tank. The dewatered sludge is collected in trays, which can be used as manure in the garden. No. of plates : 24 Size of plates : 600 mm X 600 mm Plate moc (material of construction) : PP (poly propline) Type of operation : Hydraulic Power pack capacity : 2 HP

The biomass in the aeration tank stabilizes BOD in wastewater by consuming the organic matter in the wastewater. The metabolic activity results in growth of the biomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank has been provided with filter press for dewatering sludge. The filtrate drains off through the media, which is again let into equalization tank. The dewatered sludge is collected in trays, which can be used as manure in the garden.

Characteristics of Treated Waste water Parameter Quantity in mg/l pH 6.5-9 Total Suspended Solids <50 BOD 20 COD 50

Disposal of Treated Wastewater: The treated water shall be used for toilet flushing and for green belt development for the greening of site. Hence the recycled water is utilized completely and is considered as a zero discharge.

A - 8 22 Pump (1W+1S) Filter Feed Filter To Reuse To TANK WATER PSF CLARIFIED ACF Overflow UV TREATED WATER TANK TUBE Settlers TANK SLUDGE HOLDING Sludge system Disposal Sludge dewatering Sludge FAB REACTOR FAB (Package unit) (Package SEWAGE TREATMENT PLANT TREATMENT SEWAGE EQT TANK FLUIDIZED AEROBIC BIO REACTOR TECHNOLOGY (FAB) TECHNOLOGY BIOREACTOR AEROBIC FLUIDIZED Screen/ Grit Screen/ Chamber Bar Raw Sewage Raw

A - 9 Annexure-IV

SOLID WASTE MANAGEMENT PLAN SOLID WASTE MANAGEMENT PLAN

Segregation at Source

Biodegradable Non-Biodegradable Domestic e - Waste waste Waste Hazardous Wastes

Maintenance Maintenance Maintenance Maintenance Department Department Department Department Main Collection Main Collection Main Collection point/Segregation point/Segregation point/Segregation Storage Area Point Point Point

Existing RGIA Existing RGIA Existing RGIA Existing RGIA Facility Facility Facility Facility

A - 10 Annexure-V

Lead Distance for Construction Materials Lead Distance S.No Material Source (Km) Sand ROBOSAND and or Krishna or Godavari river bed areas 1 200 – 340 permitted by Govt. of Telangana 2 Aggregate With in the site 0 – 5 3 Cement Manufacturing units 100 – 150 4 Reinforcement Steel SAIL/TATA god owns 5-10 Bricks Local suppliers/ 5 50 Manufacturers 6 Plumbing Material Local suppliers 2 – 9 7 Electrical Material Local Suppliers 2 – 8 8 Sanitary Material Local suppliers 2 – 8 Flooring and 9 Manufacturers 50– 110 Pavement Tiles 10 Paints Local Manufacturers 10 – 30 11 Ready Mix Concrete Local Batch Plants 3 - 7

A - 11 Annexure-VI

Material Consumption for Project (Approximate) Ready Reinfor BUA per Aggre Block Mix Cement Sand Water cement Land Use unit in gate (Nos.) Concrete (bags) (m3) (m3) steel (m2) (m3) x 1000 (m3) (MT) Total BUA 146226 59953 135990 57028 6288 35387 16962 3363 Total 146226 59953 135990 57028 6288 35387 16962 3363

A - 12 Annexure-VII

Energy Consumption Statement Total area Power allocated Total Power S.No Description in m2 in watts per m2 required in (KW) Office & 1 114446 60.00 6866.76 Common area Total 6866.76

Maximum demand in kw at 0.6 diversity factor 4120.1 Consumption of power for 12 hours per day 49440.7 Maximum demand in kw at 0.1 diversity factor 686.7 Consumption of power for 12 hours per day 8240.1 Total consumption of power per day 57680.8 KW Total consumption of power per year 210.5 Lakh Units

Energy Saving by using copper wound transformers for Comm. Power loss using CU. wound transformer 1.20%

Savings in power loss using CU wound transformer 2.5 Lakh Units

Energy Saving by using HF Ballast Power loss using conventional ballast 25% Power loss using HF ballast 14% Savings in power loss using HF ballast 11%

Power Total Total Power allocated S.No Description area in required in in watts m2 (KW) per m2 1 Parking 31780 3.00 95.34 2 Common Area 34334 5.00 171.67 Total 267.01

Maximum demand in kw at 0.8 diversity factor 213.6 Consumption of power for 12 hours per day 2563.3 Maximum demand in kw at 0.2 diversity factor 53.4 Consumption of power for 12 hours per day 640.8 Total consumption of power per day 3204.1 KW Total consumption of power per year 11.7 Lakh Units Savings in power loss using HF ballast 1.3 Lakh Units

A - 13 Electrical Power savings using CFL/T5 for lighting Savings in power Using CFL/T5 as against Fluorescent Lamps 30%

Power Total Power Total area S.No Description allocated in required in in m2 watts per m2 (KW) 1 Parking 31780 3.00 95.34 2 Common Area 34334 5.00 171.67 Total 267.01

Maximum demand in kw at 0.8 diversity factor 213.6 Consumption of power for 12 hours per day 2563.3 Maximum demand in kw at 0.2 diversity factor 53.4 Consumption of power for 12 hours per day 640.8 Total consumption of power per day 3204.1 KW Total consumption of power per year 11.7 Lakh Units Savings in power using CFL 3.5 Lakh Units

Electrical Power savings using Solar Power for External lighting Power Total Power Total area S.No Description allocated in required in in m2 watts per m2 (KW) 1 External Lighting 10.00 Total 10.00

Maximum demand in kw at 1.0 diversity factor 10.0 Consumption of power for 6 hours per day 60.0 Maximum demand in kw at 0.5 diversity factor 5.0 Consumption of power for 6 hours per day 30.0 Total consumption of power per day 90.0 KW Total consumption of power per year 0.33 Lakh Units Savings in power using Solar Power 0.33 Lakh Units

A - 14 Electrical Power savings using water Cooled Chillers Savings in power by using Water Cooled Chillers as against Air cooled Chiller 40%

Total Power Total Power S.No Description area in allocated in required in m2 watts per m2 (KW) 1 Commercial Office 114446 25.00 2861.15 Total 2861.15

Maximum demand in kw at 0.6 diversity factor 1716.7 Consumption of power for 12 hours per day 20600.3 Maximum demand in kw at 0.1 diversity factor 286.1 Consumption of power for 12 hours per day 3433.4 Total consumption of power per day 24033.7 KW Total consumption of power per year 87.7 Lakh Units Savings in power using water Cooled Chillers and heat 35.09 recovery wheel Lakh Units

Total Saving Savings in lakh Savings in S.No Description kwh units percentage 1 With Cu wound Transformer 2.5 1.2 2 with HF Ballast 1.3 0.01 3 With CFL 3.5 1.7 4 With Water Cooled Chillers 35.1 16.7 5 With Solar Power for External lighting 0.3 0.2 6 Total Saving 42.7 20.3 7 Total Consumption 210.5

A - 15 Annexure-VIII

Details of DG Set emissions Temp. of Pollutant Emission Name of Height Dia Exhaust Velocity Concentration (g/sec) Stack m m Gases m/sec PM SO NO (OC) 2 X 1500 KVA 8.0 0.6 675 12.5 0.005 0.012 0.015 (3 Nos.) 1250 KVA 7.5 0.5 563 12.5 0.004 0.1 0.13 (2 Nos.) 750 KVA 5.5 0.3 338 10.5 0.002 0.06 0.08 (6 nos.)

A - 16 APPENDIX II (See paragraph 6) FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity): Location Plan enclosed. 1.1. Will the existing land use gets significantly altered from the project that is not consistent with the surroundings? (Proposed land use must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority are submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters).

The site area is a classified Commercial zone of Hyderabad Airport Development Authority of Hyderabad. The location plan is enclosed.

1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.

Area Statement for the proposed Building No. of Total Site Built up area (m2) Land Use 2 floors Area (m ) Parking Office Total Existing (Obtained Building Permit Order) Tower - 1 G + 5 3702 18370 18370 Proposed Tower - 2 B + G + 6 3451 6168 18465 24633 Tower - 3 B + G + 6 7143 13026 39471 52497 Tower - 4 B + G + 6 3093 6293 19070 25363 Tower - 5 B + G + 6 3093 6293 19070 25363 Green area 7502 Road area 9817 Open area 2879 Surface Parking 6175 Total 46855 31780 114446 146226

F1A - 1 Water Requirement of the Project Total No. of Water requirement Total Water Description Persons lpcd* Requirement in KLD Office 11500 45 517.5 Total 11500 517.5 * Water requirement as per NBC

Water Savings Proposed Water Effective Water Treated water Description No. of Persons Requirement Requirement in Reuse KLD in KLD KLD Office 11500 517.5 230.0 287.5 Total 11500 517.5 230.0 287.5

The effective water consumption is reduced by 230.0 kl/day and the requirement will be in the order of 287.5 kl/day. The water balance of the project during occupation stage is tabulated below.

Water Balance during occupation stage Input KL/Day Output KL/Day Domestic water 287.5 HVAC Chillers 181.0 Treated waste water for Recycled water 230.0 Recycle 230.0 Water requirement for green belt during non monsoon 3.0 Losses approx 20% 103.5 Total 517.5 Total 517.5

The water used in the order of 517.5 KL/day would generate 414 KL/day of wastewater which has to be treated for reuse and remaining unused excess treated water will be used for roadside plantation.

Connectivity: The project will be spread over an area of 4.69 hectares in Survey Nos. 99/1, 169, Mamidipalli, Saroor Nagar, Ranga Reddy District within the existing Rajiv Gandhi International airport area. The proposed project will be implemented within the existing Airport area only. The site is surrounded by open lands in all the directions. The connectivity to the site is by an 18 m wide road in north direction and further connects to main access road of RGIA connecting NH-7 & Sri Sailam Highway. The nearest railway station is the Umda Nagar Railway Station located at a distance of 5.2 km.

F1A - 2 Energy Consumption Statement Power Total Power Total area in S.No Description allocated in required in m2 watts per m2 (KW) Office & 1 114446 60.00 6866.76 Common area Total 6866.76

Maximum demand in kw at 0.6 diversity factor 4120.1 Consumption of power for 12 hours per day 49440.7 Maximum demand in kw at 0.1 diversity factor 686.7 Consumption of power for 12 hours per day 8240.1 Total consumption of power per day 57680.8 KW Total consumption of power per year 210.5 Lakh Units

Energy Saving by using copper wound transformers for Comm. Power loss using CU. wound transformer 1.20%

Savings in power loss using CU wound transformer 2.5 Lakh Units

Energy Saving by using HF Ballast Power loss using conventional ballast 25% Power loss using HF ballast 14% Savings in power loss using HF ballast 11%

Total Power Total Power S.No Description area in allocated in required in m2 watts per m2 (KW) 1 Parking 31780 3.00 95.34 2 Common Area 34334 5.00 171.67 Total 267.01

Maximum demand in kw at 0.8 diversity factor 213.6 Consumption of power for 12 hours per day 2563.3 Maximum demand in kw at 0.2 diversity factor 53.4 Consumption of power for 12 hours per day 640.8 Total consumption of power per day 3204.1 KW Total consumption of power per year 11.7 Lakh Units Savings in power loss using HF ballast 1.3 Lakh Units

F1A - 3 Electrical Power savings using CFL/T5 for lighting Savings in power Using CFL/T5 as against Fluorescent Lamps 30%

Power Total Power Total area S.No Description allocated in required in in m2 watts per m2 (KW) 1 Parking 31780 3.00 95.34 2 Common Area 34334 5.00 171.67 Total 267.01

Maximum demand in kw at 0.8 diversity factor 213.6 Consumption of power for 12 hours per day 2563.3 Maximum demand in kw at 0.2 diversity factor 53.4 Consumption of power for 12 hours per day 640.8 Total consumption of power per day 3204.1 KW Total consumption of power per year 11.7 Lakh Units Savings in power using CFL 3.5 Lakh Units

Electrical Power savings using Solar Power for External lighting Power Total Power Total area S.No Description allocated in required in in m2 watts per m2 (KW) 1 External Lighting 10.0 Total 10.0

Maximum demand in kw at 1.0 diversity factor 10.0 Consumption of power for 6 hours per day 60.0 Maximum demand in kw at 0.5 diversity factor 5.0 Consumption of power for 6 hours per day 30.0 Total consumption of power per day 90.0 KW Total consumption of power per year 0.33 Lakh Units Savings in power using Solar Power 0.33 Lakh Units

F1A - 4 Electrical Power savings using water Cooled Chillers Savings in power by using Water Cooled Chillers as against Air cooled Chiller 40%

Total Power Total Power S.No Description area in allocated in required in m2 watts per m2 (KW) 1 Commercial Office 114446 25.00 2861.15 Total 2861.15 Maximum demand in kw at 0.6 diversity factor 1716.7 Consumption of power for 12 hours per day 20600.3 Maximum demand in kw at 0.1 diversity factor 286.1 Consumption of power for 12 hours per day 3433.4 Total consumption of power per day 24033.7 KW Total consumption of power per year 87.7 Lakh Units Savings in power using water Cooled Chillers and heat 35.09 recovery wheel Lakh Units

Total Saving Savings in lakh Savings in S.No Description kwh units percentage 1 With Cu wound Transformer 2.5 1.2 2 with HF Ballast 1.3 0.01 3 With CFL 3.5 1.7 4 With Water Cooled Chillers 35.1 16.7 5 With Solar Power for External lighting 0.3 0.2 6 Total Saving 42.7 20.3 7 Total Consumption 210.5

Amenities Proposed Amenity Nos. or Description Sewage Treatment Plant 1 Garbage Collection Bin 1 DG Set 1500 kVA X 3 nos. 1250 KVA x 2 nos. 750 KVA x 6 nos. Green area 7502.0 m2

Parking Space Provision of the Project Floor 4-Wheeler 2-Wheeler Tower 1 & 2 429 128 Tower 3 542 160 Tower 4 & 5 432 141 Total 1403 429

F1A - 5 1.3. What is the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing land use, and disturbance to the local ecology). No major impact on the local ecology is anticipated.

1.4. Will there are any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, Seismicity etc may be given). a. Soil type: clayey or clay loam b. Slope analysis c. Vulnerability to Subsidence: No subsidence is anticipated in Deccan trap areas. d. Seismicity: The site area is classified as Zone II.

1.5. Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site) No, the site area is 4.69 hectares only and does not form part of any major drainage.

1.6. What are the quantities of earthwork involved in the construction activity cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.) Cut and fill activity is involved. The site is uneven with rolling terrain. Earth Work Quantities Qty. of fill Qty of cut Surplus fill Surplus cut S. No. Area (m3) (m3) (m3) (m3) 1 Site 70283 117138 ------46855 The excess cut material in the order of 46855 m3 will be used for construction of roads within the site.

1.7 Give details regarding water supply, waste handling etc during the construction period. The water requirement during construction phase is about 20 KLD and will be met from the Airport Water Supply System. Construction debris like cement, sand, RCC, Aggregate, steel etc. are the waste generated during construction and these waste materials are used for road development.

1.8. Will the low-lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity) NO

1.9. Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal). Construction Debris The construction debris consists of various types of materials. The construction debris will consists empty containers of adhesives, thinners, paints and petroleum products and same will be sold to authorize recycling agencies. The other wastes contain

F1A - 6 recyclable debris like iron and other metal, glass, plastics, cartons of paper, wood etc. which will be sent for reuse/recycle. The waste percentage will be in the order of 2%. Construction debris containing bricks and demolished RCC will be used for land filling in the place of sub grade.

2. WATER ENVIRONMENT 2.1. Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. Water Requirement of the Project Total No. of Water requirement Total Water Description Persons lpcd* Requirement in KLD Office 11500 45 517.5 Total 11500 517.5 * Water requirement as per NBC

Water Savings Proposed Water Effective Water Treated water Description No. of Persons Requirement Requirement in Reuse KLD in KLD KLD Office 11500 517.5 230.0 287.5 Total 11500 517.5 230.0 287.5 The effective water consumption is reduced by 230.0 kl/day and the requirement will be in the order of 287.5 kl/day. The water balance of the project during occupation stage is tabulated below.

Water Balance during occupation stage Input KL/Day Output KL/Day Domestic water 287.5 HVAC Chillers 181.0 Treated waste water for Recycled water 230.0 Recycle 230.0 Water requirement for green belt during non monsoon 3.0 Losses approx 20% 103.5 Total 517.5 Total 517.5

The water used in the order of 517.5 KL/day would generate 414 KL/day of wastewater which has to be treated for reuse and remaining unused excess treated water will be used for roadside plantation or used for construction of other buildings /given to other developers.

2.2 What is the capacity (dependable flow or yield) of the proposed source of water? The fresh water requirement for the proposed project will be met from RGIA water supply system.

F1A - 7 2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality) The quality of the water would conform to the standards as per IS: 10500. The water sourced from GHIAL water supply will be treated to conform to the BIS standards.

2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage)

Water Savings Proposed Water Effective Water Treated water Description No. of Persons Requirement Requirement in Reuse KLD in KLD KLD Office 11500 517.5 230.0 287.5 Total 11500 517.5 230.0 287.5 The effective water consumption is reduced by 230.0 kl/day and the requirement will be in the order of 287.5 kl/day.

2.5. Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption) NO

2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity)

Characteristics of Waste water Parameter Quantity in mg/l PH 6 – 7 Total Suspended Solids 400 – 600 BOD 200 – 300 COD 450 – 500

2.7. Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Rain water harvesting facilities like recharge pits, bio swales, rain gardens shall be developed apart from roof top rainwater harvesting. Roof top rain water shall be reused for landscaping.

F1A - 8 Rainwater Harvesting: The quantity of rainwater, which can be harvested, depends upon the annual rainfall, the area of the plot (catchment area) and soil characteristics. The amount of water infiltrated into soil varies with the condition of soil surface and the moisture content of the soil at the time of rainfall. The total amount of water infiltered depends on the infiltration opportunity time, which depends mainly on the slope of the land and the field structure like contour bunds, terraces and other structures, which tend to hold the runoff water over long periods on the land surface. Roof top water shall be used for domestic purpose/landscaping after filtration and disinfection.

2.8. What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long-term basis? Would it aggravate the problems of flooding or water logging in any way? The impact of project on physiography is a function of the rocky terrain of the area. The project area has a plain land and the design stage deliberations have ensured that the major contours are not disturbed.

F1A - 9 The project will have a positive impact on the soils and soil quality as project will have landscaping and the soils will be protected due to conservation. During the occupation stage, compaction will not occur, and the compaction if any will be restricted to road ROW. And the road ROW compaction cannot be said to be an impact of the operation stage as the pavement itself is a function of compacted base and sub base. Storm water drains and cross drainage structures will ensure no impact of increased run off. The project activity will be provided with a Sewage Treatment Plant to treat the domestic wastewater and necessary infrastructure will be provided for the safe disposal of domestic wastes to protect the water bodies.

2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any) There will not be any tapping of ground water.

2.10. What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts) Construction activity will take up only during non-monsoon season. There are no major drains in the site. All material dumps shall be located away from the natural drains. Storm water drains shall be constructed before the construction of the building.

2.11. How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels) Storm water drains: Storm water drains will be provided all over the proposed site to meet the expected increase in the runoff during rainy season due to the impervious nature of the roads and other paved areas. The site is uneven and it is proposed to maintain the levels as much as possible, hence storm water outlets from the site are anticipated. The expected runoff is calculated for the design of the storm water management plan is presented in following table

Rainwater pipes shall be designed for rainfall intensity of 40mm/hour from terrace floor to be harvested by storm water sumps adjacent to each building, excess disposed to external storm water lateral drain running adjacent to the periphery of the campus. The storm water drain has been proposed taking into consideration the site profile (contour).

CALCULATION FOR STORM WATER DRAIN: Quantity of storm water: (a) Without project (business as usual) : Area of Catchment, ‘A’ : 4.6855 Ha Run off Coefficient, ‘C’ : 0.6 Maximum intensity of rainfall, ‘I’ : 40 mm/hr Therefore Q : 0.312 m3/sec

F1A - 10 (b) With project: : Area for catchment for roof and road : 3.030 Ha Area of Catchment, ‘A’ : 3.030 Ha Run off Coefficient, ‘C’ : 0.9 Maximum intensity of rainfall, ‘I’ : 40 mm/hr Therefore Q = : 0.303 m3/sec Area for catchment for open areas : 1.656 Ha Run off Coefficient, ‘C’ : 0.6 Maximum intensity of rainfall, ‘I’ : 40 mm/hr Therefore Q = : 0.110 m3/sec Total Discharge : 0.413 m3/sec But, Discharge, Q = A/V : Where, : A= Area of the Drain, : V= Max. Permissible Velocity : 6 m/sec for concrete drain Area of drain, ‘A’ = Q/V : 0.069 m2 Taking depth of drain as 0.6 m at the starting point : 0.6 Width of drain = Area/depth = 0.115 m 115 mm

Storm Water Calculation Land Use Area in Vol./hr Vol./hr Difference Remarks Hectares (KL) after (KL) before in develo Develo Discharge pment pment (KL) C=0.8 C=0.6 Stored in 2 sumps of Roof 2.05 655.4 491.6 163.9 capacity 100 m3 each & Area used for domestic utility Road 0.98 314.1 235.6 78.5 Harvested in about 30 Area nos. of RWHS of size Open 1.66 198.7* 397.3 -198.7 1.5m X 1.5m X 2.0m Area TOTAL 4.69 43.7 *C=0.3 after development of greenery

2.12. Will the deployment of construction laborers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation) No. Temporary toilet facilities shall be provided and the same shall be connected to septic tank followed by soak pit.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal)

F1A - 11 PROCESS DESCRIPTION: The raw sewage will be collected in a collection sump and pumped to mechanical bar screen chamber for removal of large floating matter followed by grit removal in Grit Chamber. The raw sewage will then be collected in an equalization tank for homogenization of hydraulic load. The tank contents will be kept in suspension by means of course bubble serration through pipe grid. The equalization tank, with air flow indicator for continuous monitoring of air supply to the tank in order to avoid septic conditions, will be covered from top (RCC or FRP) to avoid nuisance. The equalized effluent will then be pumped to two Fluidized Aerobic Bio Reactors (FAB) in series where BOD/COD reduction can be achieved by virtue of aerobic microbial activities. The oxygen required will be supplied through coarse air bubble diffusers. The bio-solids formed in the biological process will be separated in the down stream Tube Settler. The clear supernatant will gravitate to the chlorine contact tank where sodium hypochlorite will be dosed for disinfection of treated water prior to disposal.

The biological sludge generated in the FAB and settled in the tube settlers will be collected in a sludge sump and then pumped to sludge drying bed for de watering. The dried sludge will then be disposed off suitably as manure. The schematics of the process are shown. The two main components of the treatment system viz. The FAB reactor and tube settler are described in the following sections.

Fluidized Aerobic Bio Reactor (FAB) Conventional effluent treatment plants are large sized, power intensive and require a lot of monitoring. Scarcity of open space and rising land a power costs have forced the industries to look our for space saving, compact and efficient treatment options. This has led to the development attached growth processes where the bio mass is retained within the aeration tank obviating the need for recycle. These plants are not only compact but also user friendly. The endeavor to have a continuously operating, no- clogging biofilm reactor with no need for back washing, low head-loss and high specific biofilm surface area culminated in the most advanced technology of aerobic biological fluidized bed treatment where the biofilm (biomass) grows on small carrier elements that move along with the water in the reactor. The movement is normally caused by aeration in the aerobic version of the reactor.

The reactor combines all the advantages and best features of Trickling filters, Rotating biological contractors, activated sludge process and submerged fixed film reactors while eliminating the drawbacks of these systems. The plants are more compact and more energy efficient.

The Fluidized Aerobic Bio Reactor (FAB) consists of a tank in any shape filled up with small carrier elements. The elements are made up of special grade PVC or polypropylene of controlled density (shown in plate). For media of specific gravity 0.92- 0.96 the overall density could be expected to increase up to 9.5% when full of biomass such that they can fluidize using an aeration device. A biofilm develops on the elements, which move along the effluent in the reactor. The movement within the reactor is generated by providing aeration with the help of diffusers placed at the bottom of the reactor. Then thin biofilm on the elements enables the bacteria to act

F1A - 12 upon the biodegradable matter in the effluent and reduce the BOD/COD content in the presence of oxygen available from the air that is used for fluidization.

Characteristics of Waste water Parameter Quantity in mg/l PH 6 – 7 Total Suspended Solids 400 – 600 BOD 200 – 300 COD 450 – 500

Design of the unit Basic data Flow : 414 KLD Capacity : 500 m3 Peak factor : 3.5 Peak flow Q peak : 1750 m3/day Influent BOD : 200 mg/lit Influent Suspended Solids : 200 mg/lit Influent COD : 350 mg/lit Effluent BOD : 30 mg/lit Effluent COD : 200 mg/lit Effluent Suspended Solids : 100 mg/lit

1. Bar Screen Chamber Average flow : 0.0054 m3/sec Peak factor : 3.5 Peak flow : 0.019 m3/sec Velocity at peak flow : 0.75 m/Sec Effective area of screen Required At average flow : 0.017 m2 At Peak flow : 0.024 m2 Provide Effective area of screen : 0.024 m2 Considering the bar of dia. 10 mm(w) and clear spacing of 20 mm (b) Overall area required : 0.036 m2 Considering screen depth as : 0.5 m Number of clear spacing : 1.8 Number of bars : 2 Consider 4 Nos. Hence Provide 5 bars Provide a screen of 0.5 m X 0.5 m at an inclination of sin 600. In a screen channel of one meter (1 m) length.

2. Grit Chamber : The flow from the bar screen chamber is let into the Grit Chamber of minimum 2 hours capacity. This tank is provided to even out the flow variation, and to provide a continuous feed into the secondary biological treatment units. Peak flow Q : 0.019 m3/sec Providing a flow through velocity of 0.30 m/sec

F1A - 13 Cross sectional area of Channel : 0.07 m2 Surface area of channel : 1.4 m2 Assuming depth d : 0.2 m Width of channel : 0.3 m (say 0.3m) Length of channel : 4.3 m (say 4.3 m) Provide two channels each of 0.2 m wide and 4.3 m long with depth of waste water 0.2 m.

3. Equalization tank: The flow from the bar screen chamber is let into the equalization tank of minimum 2hours capacity. This tank is provided to even out the flow variation, and to provide a continuous feed into the secondary biological treatment units. Average flow : 20.8 m3/hr Peak factor : 3.5 Peak flow : 72.91 m3/hr Hydraulic retention tank = 2 hrs at Peak flow Hence required volume of the tank : 145 m3 Provide tank of Capacity : 145 m3 Assuming depth : 5 m Area : 29 m2 Assuming length to width ratio (1:1) ; l=b length of the tank : 5.2 m width of the tank : 5.2 m Air required for agitation : 0.01 m3/ m2 min Total air required : 79.75 m3/hr Air blower required : 100 m3/hr @ 3.8 mwc Effluent transfer pump : 19.58 m3/hr @ 8 mwc

4. Fluidized Aerobic Bio Reactor (FAB): The polypropylene media have been provided with a specific surface area of 350 – 520 m2 /m3. This allows micro-organisms to get attached and biomass concentration can be increased to four folds as compared to Activated Sludge Process. This enables to consider higher Organic loading rates.

The micro-organisms attached to media are kept in a fluid state thereby maintaining the CSTR (continuous Stirrer tank reactor) regime as well as two tanks are provided in series making the plug – flow system. This will enhance the efficiencies and have the merits of both CSTR and plug-flow regimes. Organic loading rate : 3.2 kg BOD/ m3 d Organic load : 94 kg/day Volume of the tank : 29.3 m3 Assume the depth : 5 m No. of tanks in series : 2 Size of the tank : 2.6 m dia. x 5.0 SWD Specific gravity of media : 0.92 to 0.96 Specific surface area of media : 350 – 520 m2 /m3 Media filling : 30 – 50 % of tank volume

F1A - 14 Oxygen required : 2 kg / kg BOD Oxygen in air : 23% Specific gravity of air @ 30 deg. : 1.65 Aeration : Coarse bubble Oxygen transfer efficiency : 12% Air required : 116.6 m3/hr Air blower required : 150 m3/hr @ 6.5 m wc

5.Tube settler Surface loading rate : 48 m2 /m3 d Surface area required : 9.8 m2 3.0 m x 6.0 m x 2.7 m SWD With Tank size : 55 deg. hopper bottom Tube Modules : 3.0m x 6.0 m x 0.6 m ht. Tube inclination : 60 deg. Settling area for 60 deg slope : 11 m2 /m3 Cross sectional area of tubes : 120 mm x 44 mm Hexagonal Hydraulic radius : 1/61 cm (1.5 cm) Shape factor : 0.6 – 0.7 for media settleable solids

6. Pre Filtration tank The flow from the each individual settling tank i.e., the supernatant liquid is let into the respective Pre-Filtration Tank, which has a minimum 1.5 hours holding capacity. This tank is provided to hold the treated effluent and give an even flow to the pressure sand filter. Average flow : 20.8 m3/hr Peak factor : 2 m3/hr Peak flow : 41.6 m3/hr Provide min 1.5 hours holding capacity. Hence required volume of the tank : 62.5 m3 7. Pressure Sand Filter: Vertical down flow type with graded/sand bed under drain plate with polysterene strains. Flow : 500 m3/day Rate of filtration assumed as : 10 m3/m2/hr Requirement of treated water for usage in 20 hrs : 23.5 m3/hr Dia. of filter of 1 nos. : 1767 mm Provide pressure sand filter of 1800 mm dia. and 2100 mm HOS with sand as media layer, under drain pipe, laterals face piping etc for each stream. 8. Activated Carbon Filter: Vertical down flow type with graded/sand bed under drain plate with polysterene strains. Flow : 500 m3/day Rate of filtration assumed as : 10 m3/m2/hr Requirement of treated water for usage in 20 hrs : 23.5 m3/hr Dia of filter of 1 nos. : 1767 mm Provide Activated Carbon filter of 1700 mm dia with granular Activated carbon as

F1A - 15 media and 2100 mm HOS with sand as media layer, under drain pipe, laterals face piping etc for each stream.

9.Final Treated Water Holding Tank It is always preferred to provide one final holding tank of minimum one day holding capacity, so that the treated effluents can be stored and used back for gardening or other tertiary purposes. Capacity: 500 m3

10. Sludge Filter Press: The biomass in the aeration tank stabilizes BOD in wastewater by consuming the organic matter in the wastewater. The metabolic activity results in growth of the biomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank has been provided with filter press for dewatering sludge. The filtrate drains off through the media, which is again let into equalization tank. The dewatered sludge is collected in trays, which can be used as manure in the garden. No. of plates : 24 Size of plates : 600 mm X 600 mm Plate moc (material of construction) : PP (poly propline) Type of operation : Hydraulic Power pack capacity : 2 HP

The biomass in the aeration tank stabilizes BOD in wastewater by consuming the organic matter in the wastewater. The metabolic activity results in growth of the biomass population in the Fluidized Aerobic Bio Reactor (FAB). Sludge holding tank has been provided with filter press for dewatering sludge. The filtrate drains off through the media, which is again let into equalization tank. The dewatered sludge is collected in trays, which can be used as manure in the garden.

Characteristics of Treated Waste water Parameter Quantity in mg/l pH 6.5-9 Total Suspended Solids <50 BOD 20 COD 50 Disposal of Treated Wastewater: The treated water shall be used for toilet flushing and for green belt development for the greening of site. Hence the recycled water is utilized completely and is considered as a zero discharge.

F1A - 16 22 Pump (1W+1S) Filter Feed Filter To Reuse To TANK WATER PSF CLARIFIED ACF Overflow UV TREATED WATER TANK TUBE Settlers TANK SLUDGE HOLDING Sludge system Disposal Sludge dewatering Sludge FAB REACTOR FAB (Package unit) (Package SEWAGE TREATMENT PLANT TREATMENT SEWAGE EQT TANK FLUIDIZED AEROBIC BIO REACTOR TECHNOLOGY (FAB) TECHNOLOGY BIOREACTOR AEROBIC FLUIDIZED Screen/ Grit Screen/ Chamber Bar Raw Sewage Raw

F1A - 17 2.14 Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use.

The piping for landscaping shall generally be in HDPE, detailing of which would depend on the finally approved landscape design. Pumping requirements of landscaping would also likewise depend on the landscaping design, and shall generally be centralized and operated from the STP with timer, using Drip/Pressurized sprinkler systems.

A separate flushing water line will be proposed to each toilet in the building to recycle the treated sewage.

3. VEGETATION

3.1. Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with its unique features, if any) -NA-

3.2. Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project) No. The site area has no major trees and is covered mainly with shrubs.

3.3.What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale). The landscape area is 7502.0 m2. The plantation list is presented in the following table

S. No Plant Name 1 Anthocephalus Chinensis/ cadamba 2 Roystonea Regia 3 Tabebuia Rosea 4 Bauhinea Blakeana 5 Lagerstroemia Speciosa 6 Delonix Regia 7 Cassia Spectabilis 8 Alstonia Scholaris 9 Tabebuia Chrysantha/ argentea 10 Kigelia Pinnata 11 Fillicium Decipens 12 Mimusops Elengi 13 Ficus Benjamina 14 Alstonia Scholaris 15 Cassia Fictula

F1A - 18 4. FAUNA 4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details. NO

4.2. Any direct or indirect impacts on the avifauna of the area? Provide details. No major impact envisaged.

4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna. NA

5. AIR ENVIRONMENT 5.1. Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions) NA

5.2. What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters. Sources of dust during Construction Activity Vehicle and Equipment Use Exposed Areas Contractor Activities Vehicle and equipment Areas of exposed soil that entering and leaving the have been cleared and Land clearing and grubbing project site grubbed Areas of exposed soil that Vehicle and equipment Earthwork including soil have been excavated, movement and use within the compaction, rough grading filled, compacted, or project site and final grading. graded Materials handling, including Temporary parking lots and Vehicle and equipment material stockpiling, transfer staging areas storage and service areas and processing Material processing areas Onsite Construction traffic Batch dropping and dumping and transfer points Conveyor transfer and Construction roads stacking Bare ground areas of Material transferring construction site Milling and screening Spilled materials operations Demolition and debris Construction stockpiles disposal Soil and debris piles Tilling

F1A - 19 OCCUPATION STAGE No dust generation is envisaged during the occupation stage as the surrounding area will have greenery and all roads shall be paved and all slopes and embankments shall be turfed as per best engineering practices.

5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

Parking Space Provision of the Project Floor 4-Wheeler 2-Wheeler Tower 1 & 2 429 128 Tower 3 542 160 Tower 4 & 5 432 141 Total 1403 429 Circulation drawing enclosed.

5.4. Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category. NA

5.5. Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above. There will be increase in the traffic volumes due to proposed project. However, this impact will not be felt much due to wider approach roads having adequate number of carriageways and footpaths. These roads will be adequate to handle the traffic volumes during the operation of the project.

5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details. NA

6. AESTHETICS 6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents? NO

6.2. Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account? No adverse impacts are anticipated 6.3. Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out. The layout plan is on the basis of Development norms prescribed by Notified Area Committee for RGI Airport Campus.

F1A - 20 6.4. Are there any anthropological or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

-NO- 7. SOCIO-ECONOMIC ASPECTS 7.1. Will the proposal result in any changes to the demographic structure of local population? Provide the details.

During construction phase, this project will provide temporary employment to many unskilled and semi-skilled laborers in nearby villages. This project will also help in generation of indirect employment to those people who render their services for the personnel directly working in the project.

The direct and indirect employment generation by this project will be a positive socio- economic development in the surroundings of the project area. The socioeconomic development in the region will lead to enhancement of quality of life of people in the region.

7.2 Give details of the existing social infrastructure around the proposed project. Bus Stops: 1.3 km from site Railway Station: 5.2 km from site Airport: Adjacent to site

7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed? NO

8. BUILDING MATERIALS 8.1. May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency)

Ready Reinfor BUA per Aggre Block Mix Cement Sand Water cement Land Use unit in gate (Nos) x Concrete (bags) (m3) (m3) steel (m2) (m3) 1000 (m3) (MT) Total BUA 146226 59953 135990 57028 6288 35387 16962 3363 Total 146226 59953 135990 57028 6288 35387 16962 3363

The proposed project does not involve the use of building materials with high- embodied energy.

F1A - 21 8.2. Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts? All materials shall be transported during non peak hours. .

8.3. Are recycled materials used in roads and structures? State the extent of savings achieved? There are no recycled materials to use in roads and structures.

8.4. Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project.

Solid waste is segregated at source and then conveyed to the Solid Waste Management facility at RGIA. Biodegradable waste is composted and used as manure and the non biodegradable waste will be given to authorized recyclers.

SOLIDSOLID WASTE WASTE MANAGE MANAGEMENTMENT PLANPLAN

Segregation at Source

Biodegradable Non-Biodegradable Domestic e - Waste waste Waste Hazardous Wastes

Maintenance Maintenance Maintenance Maintenance Department Department Department Department Main Collection Main Collection Main Collection point/Segregation point/Segregation point/Segregation Storage Area Point Point Point

Existing RGIA Existing RGIA Existing RGIA Existing RGIA Facility Facility Facility Facility

9. ENERGY CONSERVATION

9.1. Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?

F1A - 22 LOCAL BODIES Energy Consumption Statement Power Total Power Total area in S.No Description allocated in required in m2 watts per m2 (KW) Office & 1 114446 60.00 6866.76 Common area Total 6866.76

Maximum demand in kw at 0.6 diversity factor 4120.1 Consumption of power for 12 hours per day 49440.7 Maximum demand in kw at 0.1 diversity factor 686.7 Consumption of power for 12 hours per day 8240.1 Total consumption of power per day 57680.8 KW Total consumption of power per year 210.5 Lakh Units

Energy Saving by using copper wound transformers for Comm. Power loss using CU. wound transformer 1.20%

Savings in power loss using CU wound transformer 2.5 Lakh Units

Energy Saving by using HF Ballast Power loss using conventional ballast 25% Power loss using HF ballast 14% Savings in power loss using HF ballast 11%

Total Power Total Power S.No Description area in allocated in required in m2 watts per m2 (KW) 1 Parking 31780 3.00 95.34 2 Common Area 34334 5.00 171.67 Total 267.01

Maximum demand in kw at 0.8 diversity factor 213.6 Consumption of power for 12 hours per day 2563.3 Maximum demand in kw at 0.2 diversity factor 53.4 Consumption of power for 12 hours per day 640.8 Total consumption of power per day 3204.1 KW Total consumption of power per year 11.7 Lakh Units Savings in power loss using HF ballast 1.3 Lakh Units

F1A - 23 Electrical Power savings using CFL/T5 for lighting Savings in power Using CFL/T5 as against Fluorescent Lamps 30%

Power Total Power Total area S.No Description allocated in required in in m2 watts per m2 (KW) 1 Parking 31780 3.00 95.34 2 Common Area 34334 5.00 171.67 Total 267.01

Maximum demand in kw at 0.8 diversity factor 213.6 Consumption of power for 12 hours per day 2563.3 Maximum demand in kw at 0.2 diversity factor 53.4 Consumption of power for 12 hours per day 640.8 Total consumption of power per day 3204.1 KW Total consumption of power per year 11.7 Lakh Units Savings in power using CFL 3.5 Lakh Units

Electrical Power savings using Solar Power for External lighting Power Total Power Total area S.No Description allocated in required in in m2 watts per m2 (KW) 1 External Lighting 10.0 Total 10.0

Maximum demand in kw at 1.0 diversity factor 10.0 Consumption of power for 6 hours per day 60.0 Maximum demand in kw at 0.5 diversity factor 5.0 Consumption of power for 6 hours per day 30.0 Total consumption of power per day 90.0 KW Total consumption of power per year 0.33 Lakh Units Savings in power using Solar Power 0.33 Lakh Units

F1A - 24 Electrical Power savings using water Cooled Chillers Savings in power by using Water Cooled Chillers as against Air cooled Chiller 40%

Total Power Total Power S.No Description area in allocated in required in m2 watts per m2 (KW) 1 Commercial Office 114446 25.00 2861.15 Total 2861.15 Maximum demand in kw at 0.6 diversity factor 1716.7 Consumption of power for 12 hours per day 20600.3 Maximum demand in kw at 0.1 diversity factor 286.1 Consumption of power for 12 hours per day 3433.4 Total consumption of power per day 24033.7 KW Total consumption of power per year 87.7 Lakh Units Savings in power using water Cooled Chillers and heat 35.09 recovery wheel Lakh Units

Total Saving Savings in lakh Savings in S.No Description kwh units percentage 1 With Cu wound Transformer 2.5 1.2 2 with HF Ballast 1.3 0.01 3 With CFL 3.5 1.7 4 With Water Cooled Chillers 35.1 16.7 5 With Solar Power for External lighting 0.3 0.2 6 Total Saving 42.7 20.3 7 Total Consumption 210.5

9.2. What type of, and capacity of, power back-up to you plan to provide?

Details of DG Set emissions Temp. of Pollutant Emission Name of Height Dia Exhaust Velocity Concentration (g/sec) Stack m m Gases m/sec PM SO NO (OC) 2 X 1500 KVA 8.0 0.6 675 12.5 0.005 0.012 0.015 (3 Nos.) 1250 KVA 7.5 0.5 563 12.5 0.004 0.1 0.13 (2 Nos.) 750 KVA 5.5 0.3 338 10.5 0.002 0.06 0.08 (6 nos.)

F1A - 25 9.3. What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation? The façade is not made of glass and the glass requirement is only for windows. The glass characteristics are presented below: Characteristics of Glass utilized Normal Anti-firing type Non- Seethrough(SE) SE NS seethrough(NS) Nominal thickness 6 8 10 6 10 9.8 9.8 Out glass FL3 FL4 FL5 G3 G5 PWN 6.8 GWN 6.8 Structure vacuum 0.2 0.2 0.2 0.2 0.2 0.2 0.2 In glass Low-E 3 Low-E 4 Low-E 5 Low-E 3 Low-E 3 Low-E 3 Low-E 3 TL(%) 75.5 74.6 73.8 75.5 73.8 72.4 72.4 Visible RL(%) 15.9 15.8 15.6 15.9 15.6 16.8 16.8 TS(%) 62.6 60.1 57.8 62.6 57.8 56.9 56.9 Solar RS(%) 14.1 13.6 13.2 14.1 13.2 14.2 14.2 AS(%) 23.3 26.3 29.0 23.3 29.0 28.9 28.9 Solar heat gain 0.76 0.74 0.72 0.69 0.66 0.69 0.63 (W/m2K) 1.5 1.5 1.5 1.5 1.5 1.5 1.5 Thermal (kcal/m2hr insulation 1.3 1.3 1.3 1.3 1.3 1.3 1.3 C) Sound reduction 30 30 30 30 30 35 35 (JIS grade) Maximum size(mm) 2,400 x 1,350 1,800 x1,200 L M Minimum size(mm) 350 x 200 350 x 200 350 x 200

9.4. What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project.  All window openings is provided with chajjas depth as specified by the design standards (around 300mm)  Use of Large fenestrations in buildings reduces the use of mechanical light energy during daytime thereby reducing the energy consumption.

9.5. Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details. Solar power shall be used for external lightning (street lightning, landscape etc.).

9.6. Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

Yes. The buildings are aligned accordingly to maximize the shading.

F1A - 26 9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications. Building Materials The building materials chosen for the blocks are as per the recommendations of the climatic standards.  To achieve the maximum energy value, a balance between the availability of building materials locally and skilled labourers is achieved.  Burnt brickwork with fly ash for the walling and plastering reduces the thermal penetration by 20-30%. Colour of Facades  The colour choice for the building uses a maximum of white surface (nearly 84%). This increases the solar reflectivity factor.  Emittance factor for white surfaces is around 90% compared to coloured surface (20-60%)  16% of wall area uses earthen colours and this space has longer thermal storage in the walls. This creates a comfortable temperature at nights due to the thicker walls designed.  Heat absorbance of the brick used for building is around 50%.  The roof of the units (if not covered with terrace garden) is painted white to have a maximum reflectivity.  The R-factor (resistance factor) for the roof with brickbats and white painted is nearly 40% more as compared to the recommended standards.

9.8. What are the likely effects of the building activity in altering the microclimates? Provide a self-assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

-NA- 9.9. What are the thermal characteristics of the building envelope? (a) Roof; (b) External walls; and (c) Fenestration? Give details of the material used and the U- values or the R-values of the individual components.

S.NO. COMPONENTS U – VALUE (W/m2K) 1 Walls 2.44 2 Roofs 3.35 3 Floors 1.13 4 Windows 5.67 5 Glass < 3.0

F1A - 27 9.10. What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans. - NA - GMR Business Park (Site A) construction project - GMR Hyderabad International Airport Limited has envisaged Commercial office Buildings (GMR Business Park) in 5 Towers within RGIA.

9.11. If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics. -NA-

9.12. What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration. 4 A changes = 4.

9.13. To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used. -Nil-

10. ENVIRONMENT MANAGEMENT PLAN The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire. Furnished in EIS/EMP report.

F1A - 28 GMR Business Park (Site A) M/s GMR Hyderabad International Airport Limited SURVEY NOS. 99/1 and 169, MAMIDIPALLI, SAROOR NAGAR, RANGA REDDY DISTRICT

Studies and Documentation by: Team Labs and Consultants (An ISO Certified Organization) B-115 -117 & 509, Annapurna Block, Aditya Enclave, Ameerpet, Hyderabad- 500 038 Phone: 91-040-23748555/23748616 Fax : 91-040-23748666 e-mail: [email protected]