The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

EUROPE AND CENTRAL ASIA | | Water Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2018 | Seq No: 3 | ARCHIVED on 23-Jun-2019 | ISR37799 | Public Disclosure Authorized

Implementing Agencies: FVWRMP PMU under the Agency for Land Reclamation and Irrigation, MINISTRY OF FINANCE, Agency for Land Reclamation and Irrigation

Key Dates

Key Project Dates

Bank Approval Date: 05-Jan-2018 Effectiveness Date: 07-May-2018 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2020 Revised Closing Date: 31-Dec-2020 pdoTable Public Disclosure Authorized Project Development Objectives

Project Development Objective (from Project Appraisal Document) The project development objectives are to help the Government of Tajikistan (i) strengthen the institutional base for irrigation planning and management in the Zarafshon river basin; and (ii) improve the condition and management of irrigation infrastructure in the Zarafshon river basin and adjacent districts in the Syr-Darya basin. The project will increase food availability for rural people in the project area and as such, contribute to the overarching objective of improving food security.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

Components Table

Public Disclosure Authorized Name Rehabilitation of Irrigation Infrastructure:(Cost $11.91 M) Development and Strengthening of Irrigation and Water Resources Management Institutions:(Cost $3.52 M) Project Management:(Cost $1.13 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial

Implementation Status and Key Decisions

Public Disclosure Authorized In the past six months, the project made a substantial progress towards its development objectives with the following results achieved to date: 1. Public works program for small scale irrigation infrastructure rehabilitation. Public works for manual cleaning of small-scale on-farm canals were completed on the territory of four jamoats of Devashtich, 11 jamoats of Pajnakent and 1 jamoat of Ayni. In total 2,662 participants were offered temporary employment resulting in 745 km of small irrigation network cleaned and rehabilitated to the benefit of 22.2 thousand hectares of irrigated land on the territory of these districts. The project will continue its support to low-income households through generation of temporary employment opportunities in Kuhistoni and Ayni districts during the next construction season.

6/23/2019 Page 1 of 7 The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

2. Large-scale irrigation canal rehabilitation program. For implementation of Subcomponent Ib, activities to date had been intensive in most intervention aspects, and corresponding progress had been substantial. Out of 15 planned irrigation system rehabilitation works contracts, 10 had been let, with total contract values corresponding to about 70% of the total planned value of 8.27 million USD. For one of these contracts, corresponding to the cleaning of irrigation canals in district, works were reported as almost 85% complete. Works completion percentages in the order of from 25% to 50% seemed to have been achieved on at least a further 4 of the let contracts, covering irrigation canal, structure and pump station works for several systems in Panjakent and Ayni districts. Meanwhile, for 3 of the 5 remaining planned rehabilitation works contracts, designs and estimates were reported as available for final works scoping and contracts tendering. 3. Institutional support to ALRI: Very little progress was made since the last mission in launching institutional support to the ALRI in Zarafshon basin. The PMU with support of the International Consultant has prepared a draft ToRs for the intended restructuring of the ALRI and further support to turning it into a more sustainable lean irrigation service provider. After several rounds of revisions, the ToRs has been now shared with the Bank for technical review and clearance. Given the very limited timeframe of the project, it is critical to launch this activity in order to be able to introduce critical reforms already during the next season. 4. WUAs strengthening and capacity building. Activities on developing and strengthening WUAs in the project area have been initiated. A local consulting team has been assigned to conduct an initial survey and assessment of existing WUAs in Panjakent, Devashtich and districts. The initial survey and assessment proposed to reduce the existing number of 52 WUAs to 23 WUAs in three selected districts in the Zarafshon basin with the aim at merging small WUAs into larger ones to achieve the economies of scale needed to ensure their financial viability. The restructuring includes: : 25 to 13 WUAs, Devashtich district: 27 to 7 WUAs; and Shahriston district: 3 new WUAs. As one of the tasks under this component, the delineation of irrigation network hydraulic boundaries for WUAs has been initiated and draft schematic maps have been prepared. The training of WUAs has not started yet but is expected to be initiated by July 2019. WUA staff will be trained to cost, manage and supervise maintenance works and to enter into and monitor water service contracts with ALRI. 5. Agriculture productivity. The project is expected to improve irrigation service delivery on approximately 30,000 ha of farm land. Agriculture statistics for the year following the project interventions will need to be collected and analyzed for data triangulation purposes and verification of impact evaluation results. A very tight timeframe has been mandated for implementation of a substantial program of investments envisaged under the project, which also includes a relatively large-scale irrigation system rehabilitation works and an ambitious reform of the institutional set-up of the irrigation sector in the project area. Implementation has been ongoing for one year to date, and the remaining available implementation period duration is 1.5 years only. The Project Implementing Entity is encouraged to immediately launch soft activities envisaged under the project to accelerate the progress towards achieving the PDOs.

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance Substantial Substantial Substantial Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other ------

Overall Substantial Substantial Substantial

Results

6/23/2019 Page 2 of 7 The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

PDO Indicators by Objectives / Outcomes

Strenghten the institutional base for irrigation planing and management in the project area

IN00721240 ►Proportion of WUAs functioning in accordance with their roles and responsibilites agreed upon in their Charters. (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 40.00 100.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021 The baseline survey determined that only 40 percent of existing WUAs were performing according to their Comments: Charters.The process of restructuring of existing and formation of new WUAs is still ongoing.

IN00721262

►Irrigated area covered by volumetric main system management (Hectare(Ha), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 21,000.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

Improve the condition and management of irrigation infrastructure

IN00721261

►Area served by improved irrigation infrastructure (Hectare(Ha), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 22,221.00 30,000.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721263

►Increased yield for selected cereal and food crops on rehabilitated irrigated land (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 10.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021 The results for this indicator can only be provided after cropping season and completion of rehabilitation Comments: works.

Intermediate Results Indicators by Components

Rehabilitation of Irrigation Infrastructure

IN00721264

►Direct beneficiaries of public works program (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

6/23/2019 Page 3 of 7 The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

Value 0.00 0.00 2,662.00 3,500.00

Date 05-Jan-2017 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721268

Female beneficiaries of public works program (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 790.00 700.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721269

►Length of irrigation canals rehabilitated (Kilometers, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 873.00 1,100.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721271

Length of irrigation canals rehabilitated manually (Kilometers, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 765.00 985.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721272

Length of irrigation canals rehabilitated mechanically (Kilometers, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 108.00 115.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721273

►Major hydraulic control, conveyance and protection structures rehabilitated (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 3.00 115.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721274

Pumping stations (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 2.00 10.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721275

Vertical tubewells (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 28.00

6/23/2019 Page 4 of 7 The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721276

Canal systems and structures (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 58.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721277

Pipeline systems (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 1.00 5.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721278

Flow measurement device sets (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 10.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721279

River bank protection sections (Number, Custom Breakdown)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 4.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721280

►Flow control gates installed/renovated (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 93.00 500.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

Development and Strengthening of Irrigation and Water Resources Management Institutions

IN00721265 ►Proportion of irrigated area covered by GIS-based inventory of irrigation systems and hydraulic structures (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 10.00 55.00 100.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

IN00721267

►ALRI and WUA staff trained in water measurement and volume-based service contracting (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

6/23/2019 Page 5 of 7 The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

Value 0.00 0.00 0.00 100.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

The training of ALRI and WUA staff has not started yet. Comments:

IN00721270

►Irrigated area covered by strengthened Water User Associations (Hectare(Ha), Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 25,000.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

Project Management

IN00721266

►Proportion of grievances registered, relating to delivery of project benefits, that are actually addressed (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 98.00 90.00

Date 05-Jan-2018 20-Dec-2018 19-Jun-2019 30-Mar-2021

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed

P158576 TF-A6507 Effective USD 15.66 15.66 0.00 6.44 9.30 41%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P158576 TF-A6507 Effective 16-Jan-2018 16-Jan-2018 07-May-2018 31-Dec-2020 31-Dec-2020

Cumulative Disbursements

6/23/2019 Page 6 of 7 The World Bank Implementation Status & Results Report Zarafshon Irrigation Rehabilitation and Management Improvement Project (P158576)

Restructuring History

There has been no restructuring to date.

Related Project(s)

There are no related projects.