STATUS AS ON 30.04.2019 INDIRAMMA FLOOD FLOW CANAL

Indiramma Flood Flow canal envisages diversion of flood water from Sri Ram Sagar reservoir through the flood flow canal which would be stored in two reservoirs viz., Mid Manair Reservoir and Gouravelly Reservoir to provide irrigation facilities to 93,587 Ha in Rajanna Sircilla, , Siddipet, Urban, Jangaon, Jagtiyal & Peddapally districts of . The project was accorded investment clearance for Rs. 1331.3083 Crore by Planning Commission vide No. 2(322)/03-WR, dated 08.12.2005. The project was included under AIBP during FY 2005-06 and it is being monitored by M & A Dte, CWC, Hyderabad. The latest revised estimated cost of the project is Rs. 5940.09 crore which was approved during 128th TAC meeting held on 29-02-2016.

1. PROJECT COMPONENTS • Head Regulator of IFFC at the foreshore of Sri Ram Sagar Project Dam across . • IFFC of length 125.03km connecting SRSP dam to MMR with a design discharge capacity of 623.00 cumec. • Formation of MMR with gross storage capacity of 732.60 MCM and Live storage of 572.93 MCM upstream of existing Lower Manair Dam. • Left Bank canal (4249 ha) and Right Bank Canal (28129 ha) from MMR to irrigate 32,376 ha annually. • Single stage Lift (102.00m) cum gravity Canal from MMR to Gouravelly reservoir. • Formation of Gouravelly Reservoir having gross storage of 39.92 MCM. • Three irrigation canals from Gouavelly reservoir to irrigate an ayacut of 48,561 ha annually. • An ayacut of 12,648 ha annually is proposed under micro-irrigation with Ground Water in Kharif season. 2. BENEFITS a) Irrigation Potential (Ha) : 93587 CCA (Ha): 132000 b) Annual Irrigation (Ha) : 102000 c) Drinking Water Supply MCM : 3.7 Irrigation Demand (MCM): 335.4

3. Physical & Financial progress as on Apr 2019 A.PHYSICAL: i) Head works : 90% ii) Main canal : 80% iii) Branch canal : 57% iv) Distributary : 0% v) Minors : 0% vi) Lift : 76% vii) Irrigation Potential created upto Apr 2019 : 1214 Balance IP to be created: 92,373

B.FINANCIAL: i) Approved Cost (Rs. Cr.) : 1331.308 Works: 1215.911 AIBP: 788.1915 ii) Latest Revised Cost (Rs. Cr.) : 5940.09 Works: 5488.17 AIBP: 5037.125 iii) Expenditure upto March, 2018 (on AIBP) (Rs. Cr.) : 4248.23 iv) Expenditure during 2018-19 (Rs. Cr.) : 82.57 v) Cumulative expenditure upto Apr 2019 (on AIBP) (Rs. Cr.) : 4330.8 vi) Balance Cost (on AIBP)(Rs. Cr.) : 706.33 vii) Budget outlay for the year 2018-19 : 495.92

4. Progress during 2018-19 Physical (%) Financial (%) Irrigation Potential Ha Land Acquisition Ha 0.00 1.64 0 0

5. Target Date completion: Dec-19

6. FTPC Status The latest cost of project Rs. 5940.09 Cr was approved during 128th TAC Meeting held on 29.02.2016. FTP Clearance is not required.

7. CA DETAILS i) Eligible CA as on 01.04.2016 as per new PMKSY guidelines (Rs. Cr.) : 0 ii) CA released during 2016-17 (Rs. Cr.) : 0 iii) CA released during 2017-18 (Rs. Cr.) : 0 Not elligible as per cabinet note calculation. Central Share matching with State iv) CA released during 2018-19 (Rs. Cr.) : 0 share was already released. v) Balance CA to be released (Rs. Cr.) : 0

8. CADWM DETAILS: Target date of Completion Mar-20 Status of Inclusion under the CADWM scheme: Included Area Proposed (Ha) Central Share (Rs. Cr.) State Share (Rs. Cr.) Total cost of CAD works (Rs. Cr.) CA released in 17-18 Rs. cr CA released in 18-19 Rs. cr 90298 48.212 47.904 97.239 3.0694 0.00 CADWM CA Proposal for 2018-19: CA of Rs. 3.06 crore for FY 2017-18 was released by NABARD vide letter dated 10.12.2018. Proposal for 2018-19 not received yet

9. ISSUES • Mid Manair Reservoir – Main canal of 3Km, out of 85Km and Distributaries of 206Km, out of 265Km to be taken up. • Gouravelly Reservoir – 3 irrigation canals: Main canal 32Km out of 82Km and Distributaries of 497Km, out of 590Km to be taken up. • Land Acquisition: 1883 Ha land to be acquired out of 13725Ha. • R & R: Mid Manair Reservoir – 5 villages, out of 11 villages to be shifted. Gouravelly Reservoir – Total 4 villages to be shifted.