CASTLE HILL WIND FARM
RESOURCE CONSENT APPLICATIONS
August 2011
APPLICATION FOR RESOURCE CONSENT
UNDER SECTION 88 OF THE RESOURCE MANAGEMENT ACT 1991
TO: Manawatu-Wanganui Regional Council
GENESIS POWER LIMITED (trading as “Genesis Energy”), applies for the following resource consents associated with the proposed Castle Hill Wind Farm (“CHWF”) as generally described below, subject to the component location descriptions shown in Schedule One:
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance (including 0.057 ha within rare, threatened or at-risk habitats), including in a Hill Country Erosion Management Area, associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads and construction of new roads (including associated land disturbance, earthworks and vegetation clearance) as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures, in, on, under or over the streambed (including bridges, culverts and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Water Permit – To authorise the take and use of a combined total of up to 531 cubic metres per day of surface water as detailed in this application for construction activities from:
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) is less than the median flow but exceeds 2.04 cubic metres per second.
Water Permit – To authorise the take and use of surface water for construction activities as detailed in this application from:
ii
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N at a rate of up to 1037 cubic metres per day; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N at a rate of up to 1037 cubic metres per day; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N at a rate of up to 2074 cubic metres per day;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) exceeds the median flow.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and the concrete batching plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, within the CHWF Site as detailed in this application and as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate processing plants, as detailed in this application and within the area shown in Figures A1 – A4.
1. The names and addresses of the owners and occupiers of land to which the application relates are listed below:
The application involves a number of separate private landholdings and Council Road Reserve. The name, address and contact details of the owners/occupiers of land to which the resource consent applications relate are listed in Table A1.
2. The location to which these applications relate:
The general area within which the CHWF is located is shown in Figures A1 – 4 and is located approximately 20 kilometres (“km”) northeast of Masterton, 20 km east of Eketahuna and Pahiatua and 15 km west of the Wairarapa Coast north of Castlepoint.
In addition to wind farm activities within the CHWF Site, consent is also sought in relation to works on External Roads generally between Alfredton and the CHWF Site, particularly with respect to enabling over-weight and/or over-dimension vehicles (“OW/OD Vehicles”) to access the CHWF Site. Consent is also sought for water takes, Concrete Batching Plants and a quarry outside the CHWF Site.
iii
The locations to which these activities within the CHWF Site and on the External Roads relate are described in more detail in the Assessment of Environmental Effects (“AEE”) which accompanies this application.
3. A description of the activity to which these applications relate:
3.1 Genesis Energy is proposing to establish and operate the CHWF on privately owned rural land and some road reserve areas in northern Wairarapa. The proposed CHWF comprises up to 286 wind turbines. Development of the CHWF may progress in stages, with the first stage being in the order of up to half the total number of turbines.
3.2 The area within the broader CHWF Site within which wind turbines would be located is referred to as “the Turbine Corridor”. The Turbine Corridor is approximately 3,144 ha and is shown in Figures A1 – A4. The turbines have been grouped into seven “Turbine Clusters” (A to G) for ease of reference. The On-site Construction Footprint will be approximately 861 ha, while the On-site Operational Footprint of the CHWF will be approximately 226 ha.
3.3 Genesis Energy is seeking resource consents that enable a defined maximum size and number of turbines to be built within the Turbine Corridor. The final turbine model(s) to be used for the CHWF and the placement of these turbines within the Turbine Corridor will be confirmed during the detailed design phase of the project. However, they will not total more than 286, and will be no more than 155 m in height (as measured to the rotor tip). The consent sought provides flexibility as to the exact location of turbines and models to be used, while ensuring appropriate environmental outcomes are achieved. Some flexibility in the location of components (other than turbines) outside the Turbine Corridor is also being sought, as identified in Schedule One – Component Location Consenting Approach.
3.4 In defining the Turbine Corridor, and designing the overall CHWF, Genesis Energy has undertaken a comprehensive design and site layout analysis, integrating environmental and engineering considerations to ensure the proposal is appropriately located and that adverse effects are avoided, remedied or mitigated as required by the Resource Management Act 1991.
3.5 The key components during the construction and operation of the CHWF project are outlined below and described in detail in the AEE accompanying this application. Key components include:
Wind turbines (and associated foundations, transformers and platforms) within the Turbine Corridor to generate electricity.
Electrical Balance of Plant (“EBoP”) - Plant includes an Internal Transmission Line, 33kV overhead lines, 33kV underground cables, a Main Substation and Satellite Substation, an optional Switching Station and switch gear huts, along with other associated electrical equipment within the CHWF Site to the point of connection to the External Transmission Line.
Internal Roads constructed within the CHWF Site for transporting wind farm components, materials and personnel within Site and to
iv
allow access around the Site for construction and operational activities.
Permanent operations and maintenance facilities (“O&M facilities”), including site office, workshops, amenities, equipment storage and a wastewater treatment system.
Monitoring masts - up to 16 monitoring masts to collect on-going meteorological information during the operational life of the CHWF.
External Roads, being public roads near the Site that are planned to be used for traffic associated with the construction and operation of the CHWF and by OW/OD Vehicles.
Temporary construction facilities during the construction phase of the CHWF, such as contractor compounds, offices and workshops, amenities and storage facilities.
Water abstraction and retention structures during construction activities.
Quarries to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete batching plants during construction activities.
Excess Fill Areas for placement of excavated material not used in construction.
The project will also involve the upgrading of External Roads (where necessary) on the local road network between the CHWF Site and Alfredton, particularly with respect to enabling OW/OD Vehicles to access the Site.
3.6 Resource Management Act 1991 approvals for the External Transmission Line to connect the CHWF to the national grid are not part of this application and will be sought separately. However, the connection to an External Transmission Line is provided for in this application.
4. The following other resource consents are needed for the proposed activity and have been applied for:
Tararua District Council
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
v
EBoP, including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the External Transmission Line.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, O&M facilities, and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1- A4.
Wellington Regional Council
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
vi
Land Use Consent – To authorise the upgrade of existing External Roads (including associated land disturbance, earthworks and vegetation clearance), as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds for the placement, construction, use and maintenance of structures in, on, under or over the streambed, (including bridges, culverts, cabling and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures in, on, under or over the streambed in a manner that constitutes a permanent reclamation or occupation of the bed, as detailed in this application and within the area shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Water Permit – To authorise the take and use of up to 890 cubic metres per day of surface water from the Tinui River at Taipo, at or about NZTM map reference 1866476E 5477290N as detailed in this application for construction activities.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and Concrete Batching Plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, as detailed in this application and within the CHWF Site as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate crushing plants, as detailed in this application and within the area shown in Figures A1 – A4.
Masterton District Council
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
vii
EBoP, including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the External Transmission Line.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, O&M facilities, and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1 – A4.
5. Lapse Period and Consent Duration
A lapse period of 10 years is requested to enable the development of the proposed CHWF. Accordingly, in terms of section 125 of the Resource Management Act 1991, Genesis Energy requests the date on which the resource consents lapse be specified in any grant of consent as a date no earlier than 10 years from the date of commencement of the consents.
viii
An unlimited duration consent is sought for the District Council Land Use consents and for the Section 13 Regional Council reclamation consents sought.
A duration of 35 years is sought for all the regional resource consents. A duration of 20 years is sought for construction related consents to provide for the implementation of the CWHF through a staged approach.
6. Notification
In accordance with Section 95A(2)(b) of the Resource Management Act 1991, Genesis Energy requests that the applications be publicly notified.
7. The details of the effects arising as a result of the applications, and other matters required to be addressed pursuant to the Fourth Schedule of the Resource Management Act 1991 are attached in accordance with section 88 of the Act.
8. No other information is required to be included in this application by a regional or district plan or regulation.
Dated: 1 August 2011
Genesis Power Limited By its solicitors and authorised agents
Signature: Paul F Majurey Address for Service: C/- Paul F Majurey / T L Hovell Atkins Holm Majurey Limited Level 19, 48 Emily Place PO Box 1585, Shortland Street AUCKLAND 1140
Telephone: (09) 304 0294 Facsimile: (09) 309 1821 Email: [email protected]
i
APPLICATION FOR RESOURCE CONSENT
UNDER SECTION 88 OF THE RESOURCE MANAGEMENT ACT 1991
TO: Wellington Regional Council
GENESIS POWER LIMITED (trading as “Genesis Energy”), applies for the following resource consents associated with the proposed Castle Hill Wind Farm (“CHWF”) as generally described below, subject to the component location descriptions shown in Schedule One:
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads (including associated land disturbance, earthworks and vegetation clearance), as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds for the placement, construction, use and maintenance of structures in, on, under or over the streambed, (including bridges, culverts, cabling and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures in, on, under or over the streambed in a manner that constitutes a permanent reclamation or occupation of the bed, as detailed in this application and within the area shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Water Permit – To authorise the take and use of up to 890 cubic metres per day of surface water from the Tinui River at Taipo, at or about NZTM map reference 1866476E 5477290N as detailed in this application for construction activities.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and Concrete Batching Plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4. ii
Discharge Permit – To authorise the discharge of Excess Fill to land, as detailed in this application and within the CHWF Site as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate crushing plants, as detailed in this application and within the area shown in Figures A1 – A4.
1. The names and addresses of the owners and occupiers of land to which the application relates:
The application involves a number of separate private landholdings and Council Road Reserve. The name, address and contact details of the owners/occupiers of land to which the resource consent applications relate are listed in Table A1.
2. The location to which these applications relate:
The general area within which the CHWF is located is shown in Figures A1 – A4 and is located approximately 20 kilometres (“km”) northeast of Masterton, 20 km east of Eketahuna and Pahiatua and 15 km west of the Wairarapa Coast north of Castlepoint.
In addition to wind farm activities within the CHWF Site, consent is also sought in relation to works on External Roads generally between Alfredton and the CHWF Site, particularly with respect to enabling over-weight and/or over-dimension vehicles (“OW/OD Vehicles”) to access the CHWF Site. Consent is also sought for water takes, Concrete Batching Plants and a quarry outside the CHWF Site.
The specific location of individual activities within the CHWF Site and on the External Roads is described in greater detail in the assessment of environmental effects (“AEE”) which accompanies this application.
3. A description of the activity to which these applications relate:
3.1 Genesis Energy is proposing to establish and operate the CHWF on privately owned rural land and road reserve areas in northern Wairarapa. The proposed CHWF comprises up to 286 wind turbines. Development of the CHWF may progress in stages, with the first stage being in the order of up to half the total number of turbines.
3.2 The area within the broader CHWF Site within which wind turbines would be located is referred to as “the Turbine Corridor”. The Turbine Corridor is approximately 3,144 ha and is shown in Figures A1 – A4. The turbines have been grouped into seven “Turbine Clusters” (A to G) for ease of reference. The On-site Construction Footprint will be approximately 861 ha, while the On-site Operational Footprint of the CHWF will be approximately 226 ha.
3.3 Genesis Energy is seeking resource consents that enable a defined maximum size and number of turbines to be built within the Turbine Corridor. iii
The final turbine model(s) to be used for the CHWF and the placement of these turbines within the Turbine Corridor will be confirmed during the detailed design phase of the project. However, they will not total more than 286, and will be no more than 155 m in height (as measured to the rotor tip). The consent sought provides flexibility as to the exact location of turbines and models to be used, while ensuring appropriate environmental outcomes are achieved. Some flexibility in the location of components (other than turbines) outside the Turbine Corridor is also being sought, as identified in Schedule One – Component Location Table.
3.4 In defining the Turbine Corridor, and designing the overall CHWF, Genesis Energy has undertaken a comprehensive design and site layout analysis, integrating environmental and engineering considerations to ensure the proposal is appropriately located and that adverse effects are avoided, remedied or mitigated as required by the Resource Management Act 1991. . 3.5 The key components during the construction and operation of the CHWF project are outlined below and described in detail in the AEE accompanying this application. Key components include:
Wind turbines (and associated foundations, transformers and platforms) within the Turbine Corridor to generate electricity.
Electrical Balance of Plant (“EBoP”) – Plant includes an Internal Transmission Line, 33kV overhead lines, 33kV underground cables, a Main Substation and Satellite Substation, an optional Switching Station and switch gear huts, along with other associated electrical equipment within the CHWF Site to the point of connection to the External Transmission Line.
Internal Roads constructed within the CHWF Site for transporting wind farm components, materials and personnel within Site and to allow access around the Site for construction and operational activities.
Permanent operations and maintenance facilities (“O&M facilities”), including site office, workshops, amenities, equipment storage and a wastewater treatment system.
Monitoring masts – up to 16 monitoring masts to collect on-going meteorological information during the operational life of the CHWF.
External Roads, being public roads near the Site that are planned to be used for traffic associated with the construction and operation of the CHWF and by OW/OD Vehicles.
Temporary construction facilities during the construction phase of the CHWF, such as contractor compounds, offices and workshops, amenities and storage facilities.
Water abstraction and retention structures during construction activities.
iv
Quarries to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete batching plants during construction activities.
Excess Fill Areas for placement of excavated material not used in construction.
The project will also involve the upgrading of External Roads (where necessary) on the local road network between the CHWF Site and Alfredton, particularly with respect to enabling OW/OD Vehicles to access the Site.
3.6 Resource Management Act 1991 approvals for the External Transmission Line to connect the CHWF to the national grid are not part of this application and will be sought separately. However, the connection to an External Transmission Line is provided for in this application.
4. The following other resource consents are needed for the proposed activity and have been applied for:
Manawatu-Wanganui Regional Council
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance (including 0.057 ha within rare, threatened or at-risk habitats), including in a Hill Country Erosion Management Area, associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads and construction of new roads (including associated land disturbance, earthworks and vegetation clearance) as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures, in, on, under or over the streambed (including bridges, culverts and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Water Permit – To authorise the take and use of a combined total of up to 531 cubic metres per day of surface water as detailed in this application for construction activities from:
v
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) is less than the median flow but exceeds 2.04 cubic metres per second.
Water Permit – To authorise the take and use of surface water for construction activities as detailed in this application from:
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N at a rate of up to 1037 cubic metres per day; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N at a rate of up to 1037 cubic metres per day; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N at a rate of up to 2074 cubic metres per day;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) exceeds the median flow.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and the concrete batching plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, within the CHWF Site as detailed in this application and as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate processing plants, as detailed in this application and within the area shown in Figures A1 – A4.
Tararua District Council
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4. vi
Electrical Balance of Plant (“EBoP”), including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the national grid.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, O&M facilities, and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1- A4.
Masterton District Council
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
vii
EBoP, including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the national grid.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, O&M facilities, and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1- A4.
5. Lapse Period and Consent Duration
A lapse period of 10 years is requested to enable the development of the proposed CHWF. Accordingly, in terms of section 125 of the Resource Management Act 1991, Genesis Energy requests the date on which the resource consents lapse be specified in any grant of consent as a date no earlier than 10 years from the date of commencement of the consents.
viii
An unlimited duration consent is sought for the District Council Land Use consents and for the Section 13 Regional Council reclamation consents sought.
A duration of 35 years is sought for all the regional resource consents. A duration of 20 years is sought for construction related consents to provide for the implementation of the CWHF through a staged approach.
6. Notification
In accordance with Section 95A(2)(b) of the Resource Management Act 1991, Genesis Energy requests that the applications be publicly notified.
7. The details of the effects arising as a result of the applications, and other matters required to be addressed pursuant to the Fourth Schedule of the Resource Management Act 1991 are attached in accordance with section 88 of the Act.
8. No other information is required to be included in this application by a regional or district plan or regulation.
Dated: 1 August 2011
Genesis Power Limited By its solicitors and authorised agents
Signature: Paul F Majurey Address for Service: C/- Paul F Majurey / T L Hovell Atkins Holm Majurey Limited Level 19, 48 Emily Place PO Box 1585, Shortland Street AUCKLAND 1140
Telephone: (09) 304 0294 Facsimile: (09) 309 1821 Email: [email protected]
i
APPLICATION FOR RESOURCE CONSENT
UNDER SECTION 88 OF THE RESOURCE MANAGEMENT ACT 1991
TO: Tararua District Council
GENESIS POWER LIMITED (trading as “Genesis Energy”), applies for the following resource consents associated with the proposed Castle Hill Wind Farm (“CHWF”) as generally described below, subject to the component location descriptions shown in Schedule One:
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
Electrical Balance of Plant (“EBoP”), including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the national grid.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, operations and maintenance facilities (“O&M facilities”), and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
ii
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance (including in an area identified as “Significant groups of trees, vegetation and habitats”) associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1 – A4.
1. The names and addresses of the owners and occupiers of land to which the application relates:
The application involves a number of separate private landholdings and Council Road Reserve. The name, address and contact details of the owners/occupiers of land to which the resource consent applications relate are listed in Table A1.
2. The locations to which these applications relate:
The general area within which the CHWF is located is shown in Figures A1 – A4 and is located approximately 20 kilometres (“km”) northeast of Masterton, 20 km east of Eketahuna and Pahiatua, and 15 km west of the Wairarapa Coast north of Castlepoint.
In addition to wind farm activities within the CHWF Site, consent is also sought in relation to works on External Roads generally between Alfredton and the CHWF Site, particularly with respect to enabling over-weight and/or over-dimension vehicles (“OW/OD Vehicles”) to access the CHWF Site. Consent is also sought for water takes, Concrete Batching Plants and a quarry outside the CHWF Site.
The locations to which these activities within the CHWF Site and on the External Roads relate are described in more detail in the Assessment of Environmental Effects (“AEE”) which accompanies this application.
3. A description of the activity to which these applications relate:
3.1 Genesis Energy is proposing to establish and operate the CHWF on privately-owned rural land and some road reserve areas in northern Wairarapa. The proposed CHWF comprises up to 286 wind turbines. Development of the CHWF may progress in stages, with the first stage being in the order of up to half the total number of turbines.
3.2 The area within the broader CHWF Site within which wind turbines would be located is referred to as “the Turbine Corridor”. The Turbine Corridor is approximately 3,144 ha and is shown in Figures A1 – A4. The turbines have been grouped into seven “Turbine Clusters” (A to G) for ease of reference. iii
The On-site Construction Footprint will be approximately 861 ha, while the On-site Operational Footprint of the CHWF will be approximately 226 ha.
3.3 Genesis Energy is seeking resource consents that enable a defined maximum size and number of turbines to be built within the Turbine Corridor. The final turbine model(s) to be used for the CHWF and the placement of these turbines within the Turbine Corridor will be confirmed during the detailed design phase of the project. However, they will not total more than 286, and will be no more than 155 m in height (as measured to the rotor tip). The consent sought provides flexibility as to the exact location of turbines and models to be used, while ensuring appropriate environmental outcomes are achieved. Some flexibility in the location of components (other than turbines) outside the Turbine Corridor is also being sought, as identified in Schedule One – Component Location Consenting Approach.
3.4 In defining the Turbine Corridor, and designing the overall CHWF, Genesis Energy has undertaken a comprehensive design and site layout analysis, integrating environmental and engineering considerations to ensure the proposal is appropriately located and that adverse effects are avoided, remedied or mitigated as required by the Resource Management Act 1991.
3.5 The key components during the construction and operation of the CHWF project are outlined below and described in detail in the AEE accompanying this application. Key components include:
Wind turbines (and associated foundations, transformers and platforms) within the Turbine Corridor to generate electricity.
EBoP - Plant includes an Internal Transmission Line, 33kV overhead lines, 33kV underground cables, a Main Substation and Satellite Substation, an optional Switching Station and switch gear huts, along with other associated electrical equipment within the CHWF Site to the point of connection to the External Transmission Line.
Internal Roads constructed within the CHWF Site for transporting wind farm components, materials and personnel within Site and to allow access around the Site for construction and operational activities.
Permanent O&M facilities including site office, workshops, amenities, equipment storage and a wastewater treatment system.
Monitoring masts - up to 16 monitoring masts to collect on-going meteorological information during the operational life of the CHWF.
External Roads, being public roads near the Site that are planned to be used for traffic associated with the construction and operation of the CHWF and by OW/OD Vehicles.
Temporary construction facilities during the construction phase of the CHWF, such as contractor compounds, offices and workshops, amenities and storage facilities.
iv
Water abstraction and retention structures during construction activities.
Quarries to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities.
Excess Fill Areas for placement of excavated material not used in construction.
The project will also involve the upgrading of External Roads (where necessary) on the local road network between the CHWF Site and Alfredton, particularly with respect to enabling OW/OD Vehicles to access the Site.
3.6 Resource Management Act 1991 approvals for the External Transmission Line to connect the CHWF to the national grid are not part of this application and will be sought separately. However, the connection to an External Transmission Line is provided for in this application.
4. The following other resource consents are needed for the proposed activity and have been applied for:
Manawatu-Wanganui Regional Council
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance (including 0.057 ha within rare, threatened or at-risk habitats), including in a Hill Country Erosion Management Area, associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads and construction of new roads (including associated land disturbance, earthworks and vegetation clearance) as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures, in, on, under or over the streambed (including bridges, culverts and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
v
Water Permit – To authorise the take and use of a combined total of up to 531 cubic metres per day of surface water as detailed in this application for construction activities from:
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) is less than the median flow but exceeds 2.04 cubic metres per second.
Water Permit – To authorise the take and use of surface water for construction activities as detailed in this application from:
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N at a rate of up to 1037 cubic metres per day; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N at a rate of up to 1037 cubic metres per day; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N at a rate of up to 2074 cubic metres per day;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) exceeds the median flow.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and the concrete batching plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, within the CHWF Site as detailed in this application and as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate processing plants, as detailed in this application and within the area shown in Figures A1 – A4.
Wellington Regional Council
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance associated with the construction, operation, vi
maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads (including associated land disturbance, earthworks and vegetation clearance), as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds for the placement, construction, use and maintenance of structures in, on, under or over the streambed, (including bridges, culverts, cabling and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures in, on, under or over the streambed in a manner that constitutes a permanent reclamation or occupation of the bed, as detailed in this application and within the area shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Water Permit – To authorise the take and use of up to 890 cubic metres per day of surface water from the Tinui River at Taipo, at or about NZTM map reference 1866476E 5477290N as detailed in this application for construction activities.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and Concrete Batching Plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, as detailed in this application and within the CHWF Site as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate crushing plants, as detailed in this application and within the area shown in Figures A1 – A4.
vii
Masterton District Council
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
EBoP, including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the national grid.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, O&M facilities, and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1 – A4.
viii
5. Lapse Period, Consent Duration and Consent Holder
A lapse period of 10 years is requested to enable the development of the proposed CHWF. Accordingly, in terms of section 125 of the Resource Management Act 1991, Genesis Energy requests the date on which the resource consents lapse be specified in any grant of consent as a date no earlier than 10 years from the date of commencement of the consents.
An unlimited duration consent is sought for the District Council Land Use consents and for the Section 13 Regional Council reclamation consents sought.
A duration of 35 years is sought for all the regional resource. A duration of 20 years is sought for construction related consents to provide for the implementation of the CWHF through a staged approach.
Genesis Energy also seeks that the land use consents be granted in the name of Genesis Energy in accordance with s134 of the RMA.
6. Notification
In accordance with Section 95A(2)(b) of the Resource Management Act 1991, Genesis Energy requests that the applications be publicly notified.
7. The details of the effects arising as a result of the applications, and other matters required to be addressed pursuant to the Fourth Schedule of the Resource Management Act 1991 are attached in accordance with section 88 of the Act.
8. No other information is required to be included in this application by a regional or district plan or regulation.
Dated: 1 August 2011 Genesis Power Limited By its solicitors and authorised agents
Signature: Paul F Majurey Address for Service: C/- Paul F Majurey / T L Hovell Atkins Holm Majurey Limited Level 19, 48 Emily Place PO Box 1585, Shortland Street AUCKLAND 1140
Telephone: (09) 304 0294 Facsimile: (09) 309 1821 Email: [email protected] i
APPLICATION FOR RESOURCE CONSENT
UNDER SECTION 88 OF THE RESOURCE MANAGEMENT ACT 1991
TO: Masterton District Council
GENESIS POWER LIMITED (trading as “Genesis Energy”), applies for the following resource consents associated with the proposed Castle Hill Wind Farm (“CHWF”) as generally described below, subject to the component location descriptions shown in Schedule One:
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
Electrical Balance of Plant (“EBoP”), including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the national grid.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, operations and maintenance facilities (“O&M facilities”), and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
ii
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1- A4.
1. The names and addresses of the owners and occupiers of land to which the application relates:
The application involves a number of separate private landholdings and Council Road Reserve. The name, address and contact details of the owners/occupiers of land to which the resource consent applications relate are listed in Table A1.
2. The locations to which these applications relate:
The general area within which the CHWF is located is shown in Figures A1 – A4 and is located approximately 20 kilometres (“km”) northeast of Masterton, 20 km east of Eketahuna and Pahiatua, and 15 km west of the Wairarapa Coast north of Castlepoint.
In addition to wind farm activities within the CHWF Site, consent is also sought in relation to works on External Roads generally between Alfredton and the CHWF Site, particularly with respect to enabling over-weight and/or over-dimension vehicles (“OW/OD Vehicles”) to access the CHWF Site. Consent is also sought for water takes, Concrete Batching Plants and a quarry outside the CHWF Site.
The locations to which these activities within the CHWF Site and on the External Roads relate are described in more detail in the Assessment of Environmental Effects (“AEE”) which accompanies this application.
3. A description of the activity to which these applications relate:
3.1 Genesis Energy is proposing to establish and operate the CHWF on privately owned rural land and some road reserve areas in northern Wairarapa. The CHWF comprises up to 286 wind turbines. Development of the CHWF may progress in stages, with the first stage being in the order of up to half the total number of turbines.
3.2 The area within the broader CHWF Site within which wind turbines would be located is referred to as “the Turbine Corridor”. The Turbine Corridor is approximately 3,144 ha and is shown in Figures A1 – A4. The turbines have been grouped into seven “Turbine Clusters” (A to G) for ease of reference. iii
The On-site Construction Footprint will be approximately 861 ha, while the On-site Operational Footprint of the CHWF will be approximately 226 ha.
3.3 Genesis Energy is seeking resource consents that enable a defined maximum size and number of turbines to be built within the Turbine Corridor. The final turbine model(s) to be used for the CHWF and the placement of these turbines within the Turbine Corridor will be confirmed during the detailed design phase of the project. However, they will not total more than 286, and will be no more than 155 m in height (as measured to the rotor tip). The consent sought provides flexibility as to the exact location of turbines and models to be used, while ensuring appropriate environmental outcomes are achieved. Some flexibility in the location of components (other than turbines) outside the Turbine Corridor is also being sought, as identified in Schedule One – Component Location Consenting Approach.
3.4 In defining the Turbine Corridor, and designing the overall CHWF, Genesis Energy has undertaken a comprehensive design and site layout analysis, integrating environmental and engineering considerations to ensure the proposal is appropriately located and that adverse effects are avoided, remedied or mitigated as required by the Resource Management Act 1991.
3.5 The key components during the construction and operation of the CHWF project are outlined below and described in detail in the AEE accompanying this application. Key components include:
Wind turbines (and associated foundations, transformers and platforms) within the Turbine Corridor to generate electricity.
EBoP - Plant includes an Internal Transmission Line, 33kV overhead lines, 33kV underground cables, a Main Substation and Satellite Substation, an optional Switching Station and switch gear huts, along with other associated electrical equipment within the CHWF Site to the point of connection to the External Transmission Line.
Internal Roads constructed within the CHWF Site for transporting wind farm components, materials and personnel within Site and to allow access around the Site for construction and operational activities.
Permanent O&M facilities including site office, workshops, amenities, equipment storage and a wastewater treatment system.
Monitoring masts - up to 16 monitoring masts to collect on-going meteorological information during the operational life of the CHWF.
External Roads, being public roads near the Site that are planned to be used for traffic associated with the construction and operation of the CHWF and by OW/OD Vehicles.
Temporary construction facilities during the construction phase of the CHWF, such as contractor compounds, offices and workshops, amenities and storage facilities.
iv
Water abstraction and retention structures during construction activities.
Quarries to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities.
Excess Fill Areas for placement of excavated material not used in construction.
The project will also involve the upgrading of External Roads (where necessary) on the local road network between the CHWF Site and Alfredton, particularly with respect to enabling OW/OD Vehicles to access the Site.
3.6 Resource Management Act 1991 approvals for the External Transmission Line to connect the CHWF to the national grid are not part of this application and will be sought separately. However, the connection to an External Transmission Line is provided for in this application.
4. The following other resource consents are needed for the proposed activity and have been applied for:
Manawatu-Wanganui Regional Council
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance (including 0.057 ha within rare, threatened or at-risk habitats), including in a Hill Country Erosion Management Area, associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads and construction of new roads (including associated land disturbance, earthworks and vegetation clearance) as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures, in, on, under or over the streambed (including bridges, culverts and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
v
Water Permit – To authorise the take and use of a combined total of up to 531 cubic metres per day of surface water as detailed in this application for construction activities from:
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) is less than the median flow but exceeds 2.04 cubic metres per second.
Water Permit – To authorise the take and use of surface water for construction activities as detailed in this application from:
a) The Te Hoe Stream at or about NZTM map reference 1846600E 5490500N at a rate of up to 1037 cubic metres per day; and b) The Tiraumea Stream at or about NZTM map reference 1857510E 5498092N at a rate of up to 1037 cubic metres per day; and c) The Tiraumea River at or about NZTM map reference 1842821E 5497910N at a rate of up to 2074 cubic metres per day;
when the Tiraumea River flow at the Regional Council river flow gauge at Ngaturi (NZTM map reference 1847725E 5516240N) exceeds the median flow.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and the concrete batching plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, within the CHWF Site as detailed in this application and as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate processing plants, as detailed in this application and within the area shown in Figures A1 – A4.
vi
Tararua District Council
Land use consent – To authorise the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated structures as detailed in this application and within the areas shown in Figures A1 – A4, including:
Wind turbines (and associated foundations, transformers and platforms) to generate electricity within the Turbine Corridor shown in Figures A1 – A4.
EBoP, including underground cables, overhead lines (33kV and 220kV), transformers, substations (main, satellite and switching station), switchgear and associated structures and equipment for the collection and reticulation of electricity within the CHWF Site as shown in Figures A1 – A4 to the point of connection to the national grid.
Internal Roads providing access to wind turbines, EBoP structures such as Substations, operations and maintenance facilities O&M facilities and connecting to External Roads, within the CHWF Site as shown in Figures A1 – A4.
Permanent O&M facilities including site office, workshops, amenities and a wastewater treatment system within the CHWF Site shown in Figures A1 – A4.
Up to eight wind monitoring masts within the CHWF Site shown in Figures A1 – A4 to collect on-going meteorological information during the operational life of the CHWF.
Construction facilities associated with the CHWF consent activities as shown and described in Figures A1 – A4, including O&M facilities, Contractor Compounds and Lay-bys.
Water abstraction and retention structures during construction activities at the locations shown in Figures A1 – A4.
Quarries at the locations shown in Figures A1 – A4 to obtain aggregate material for road construction and during operation for on-going maintenance of roads and other engineering requirements.
Concrete Batching Plants during construction activities within the area shown in Figures A1 – A4.
Excess Fill Areas for placement of excavated material not used in construction within the CHWF Site shown in Figures A1 – A4.
The upgrading, including associated land disturbance, earthworks and vegetation clearance, of External Roads (where necessary) between the CHWF Site and Alfredton as shown in Figures A1 – A4.
Land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as shown and described in Figures A1- A4.
vii
Wellington Regional Council
Land Use Consent – To authorise land disturbance, earthworks and vegetation clearance associated with the construction, operation, maintenance, replacement and refurbishment of all structures and activities associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Land Use Consent – To authorise the upgrade of existing External Roads (including associated land disturbance, earthworks and vegetation clearance), as detailed in this application and identified in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds for the placement, construction, use and maintenance of structures in, on, under or over the streambed, (including bridges, culverts, cabling and structures) as detailed in this application and at the locations shown in Figures A1 – A4.
Land Use Consent – To authorise works in, and associated excavation and disturbance of streambeds, for the placement, construction, use and maintenance of structures in, on, under or over the streambed in a manner that constitutes a permanent reclamation or occupation of the bed, as detailed in this application and within the area shown in Figures A1 – A4.
Water Permit – To authorise the damming and diversion of water (including surface and groundwater) during construction and operational activities, associated with the CHWF consent activities as detailed in this application and shown and described in Figures A1 – A4.
Water Permit – To authorise the take and use of up to 890 cubic metres per day of surface water from the Tinui River at Taipo, at or about NZTM map reference 1866476E 5477290N as detailed in this application for construction activities.
Discharge Permit – To authorise the discharge of stormwater that may contain contaminants to land and surface water during the construction and operation of infrastructure and facilities, associated with the CHWF consent activities as detailed in this application and as shown and described in Figures A1 – A4.
Discharge Permit – To authorise the discharge of stormwater and wash water (from truck bowl wash out and Concrete Batching Plant areas) to land, as detailed in this application and at the locations shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of Excess Fill to land, as detailed in this application and within the CHWF Site as shown in Figures A1 – A4.
Discharge Permit – To authorise the discharge of contaminants to air associated with the operation of Concrete Batching Plants and mobile aggregate crushing plants, as detailed in this application and within the area shown in Figures A1 – A4.
viii
5. Lapse Period, Consent Duration and Consent Holder
A lapse period of 10 years is requested to enable the development of the proposed CHWF. Accordingly, in terms of section 125 of the Resource Management Act 1991, Genesis Energy requests the date on which the resource consents lapse be specified in any grant of consent as a date no earlier than 10 years from the date of commencement of the consents.
An unlimited duration consent is sought for the District Council Land Use consents and for the Section 13 Regional Council reclamation consents sought.
A duration of 35 years is sought for all the regional resource. A duration of 20 years is sought for construction related consents to provide for the implementation of the CWHF through a staged approach.
Genesis Energy also seeks that the land use consents be granted in the name of Genesis Energy in accordance with s134 of the RMA.
6. Notification
In accordance with Section 95A(2)(b) of the Resource Management Act 1991, Genesis Energy requests that the applications be publicly notified.
7. The details of the effects arising as a result of the applications, and other matters required to be addressed pursuant to the Fourth Schedule of the Resource Management Act 1991 are attached in accordance with section 88 of the Act.
8. No other information is required to be included in this application by a regional or district plan or regulation.
Dated: 1 August 2011
Genesis Power Limited By its solicitors and authorised agents
Signature: Paul F Majurey Address for Service: C/- Paul F Majurey / T L Hovell Atkins Holm Majurey Limited Level 19, 48 Emily Place PO Box 1585, Shortland Street AUCKLAND 1140
Telephone: (09) 304 0294 Facsimile: (09) 309 1821 Email: [email protected]
Schedule One – CWHF Component Location Consenting Approach
Component Rationale Location Description Turbines Siting refinement is important to allow for variation in spacing between Turbines to Turbines may not be sited anywhere other than maximise energy output. Spacing varies depending on the size of the Turbine rotor and in the Turbine Corridor. (including Turbine therefore, optimal spacing can only be determined once the final turbine model(s) are Foundations and selected after resource consent acquisition. Four Indicative Turbine Layouts have been Turbine Platforms) established to provide a basis for representative engineering and environmental assessments and to illustrate how different Turbine sizes may be placed within the Turbine Corridor. Turbine Corridor The Turbine Corridor incorporates all areas within the CHWF Site identified for turbine The area and location of the Turbine Corridor is placement. The development and refinement of the Turbine Corridor has incorporated located where indicated in Figures A1 - A4. representative environmental and engineering assessments to avoid, remedy or mitigate adverse environmental effects. Internal Roads Internal Roads have been designed and associated earthworks volumes calculated and Internal Roads are likely to be located where will generally be located where indicated in Figures A1 - A4. However the scope sought indicated in Figures A1 - A4 but may be located (including Lay-bys) within the resource consent will enable the final location of the Internal Roads to be anywhere within the Site, subject to the limits confirmed during the detailed design phase. Further refinement may be required due to presented below: the following: (1) Areas of legally protected habitats (DOC, Technological advances in transporters or components, or construction QEII), and ‘rare’, ‘threatened’ or ‘at-risk’ techniques. This may enable a more efficient route to be taken which may reduce habitats identified under statutory plans will earthworks and/or ecological effects. not be disturbed. (2) Areas of ‘high ecological value’ as defined Unforeseen ground conditions or environmental constraints. in the Ecological Effects Assessment in Unidentified archaeological sites or features. Volume 4 (Section 3) will be avoided, except to the extent already outlined in the The Internal Road design approach is considered appropriate at this Site because of the CHWF Project Figures in Appendix C and large proportion of the Site consisting of low or negligible ecological value. The location of shown in the AEE. Clearance of a limited the Internal Roads will be influenced by the fixed locations of key CHWF infrastructure amount of ‘high ecological value’ (Turbines within the Turbine Corridor and Substations) to which they will provide access. vegetation is described and this quantity will not be exceeded in construction of the CHWF. (3) Clearance of indigenous vegetation will be
Component Rationale Location Description minimised and will not cause the maximum quantity of indigenous vegetation clearance of 66 ha described in the Ecological Effects Assessment in Volume 4 (Section 3) to be exceeded. (4) Watercourse crossings will not vary in location by more than 100 m each side of locations identified in the CHWF Project Figures in Appendix C. (5) Gullies with watercourses will be avoided unless it can be demonstrated that downstream water quality effects are no more than minor. (6) Seepage areas dominated by indigenous species with an area greater than 0.05ha will be avoided. (7) Total CHWF earthworks volumes described in the AEE are not exceeded. Main Substation Two locations have been identified for the Main Substation. The key factors that will The Main Substation will be located at one of determine which location will be most appropriate will be the final size, location and order the two locations shown in Figures A1 - A4. of stages of construction, and the final location of the External Transmission Line. Two alternative locations also provide redundancy in the unlikely event that one location is found to be unsuitable during detailed design. Satellite Substation The location of the Satellite Substation was identified after a thorough assessment of the The location of the Satellite Substation is shown overall Site against a range of suitability criteria, such as area, topography, visibility, in Figures A1 - A4. distance from occupied dwellings, and potential for flood risk, accessibility and ecology. Switching Station The Switching Station location was identified after a thorough assessment of the overall The location of the Switching Station is shown in Site against a range of suitability criteria, such as area, topography, visibility, proximity to Figures A1 - A4. dwellings, potential for flood risk, accessibility, expected proximity to the External Transmission Line connection point and ecology.
Component Rationale Location Description Internal The Internal Transmission Line has been designed to a reasonably high level of certainty The location of the Internal Transmission Line Transmission Line and apart from micro-siting of towers is not expected to change. will be within 50 m of the location indicated in Figures A1 - A4. The location indicated in Figures A1 - A4 shows some alternative arrangements depending on the location of the Main Substation and whether the Switching Station is utilised. The location of the Internal Transmission towers will be within 50m of the locations indicated in Figures A1 - A4, and will be positioned to avoid clearance or trimming of indigenous vegetation to the extent practicable. 33kV overhead lines Wherever practical, the 33kV reticulation system will follow Internal Roads so the These components are likely to be located and underground requirement for variation from the routes indicated will match that of the Internal Roads. where indicated in Figures A1 - A4 but may be cables located anywhere within the Site, subject to the The opportunity arising from refinement, and the degree of constraint applied is as for the following limitations: Internal Roads. 1. Areas of legally protected habitats (DOC, Other EBoP Other EBoP components such as switchgear huts will generally be located near previously QEII) and, ‘rare’, ‘threatened’ or ‘at risk’ listed EBoP components (substations, overhead lines and underground cables) and will habitats identified under statutory plans will vary in their location as these other components do. not be disturbed. Excess Fill Areas On-site Excess Fill Areas have been identified as suitable from both an engineering and 2. Areas of ‘high ecological value’ as defined in environmental perspective. They are located near or adjacent to Internal Roads to the Ecological Effects Assessment in minimise transport of Excess Fill and so may vary in location if Internal Roads relocations Volume 4 (Section 3) will be avoided, except are required. Other variations may be required to achieve engineering or environmental to the extent already outlined in the CHWF improvements and additional Excess Fill Areas may also be identified by the contractor. Project Figures in Appendix C and shown in the AEE. Clearance of a limited amount ‘high Central Laydown Indicative Central Laydown Area locations have been identified to indicate suitable sites ecological value’ vegetation is described and Areas and demonstrate that the requirement to provide Central Laydown Areas can be achieved. this quantity will not be exceeded in Contractor The contractor will identify a suitable location for the Contractor Compound prior to construction of the CHWF. Compounds construction. 3. Clearance of indigenous vegetation will be minimised and will not cause the maximum Operations and The location of O&M facilities will be determined prior to construction depending on the quantity of indigenous vegetation clearance maintenance final size, location and order of stages of construction. of 66 ha described in the Ecological Effects facilities Assessment in Volume 4 (Section 3) to be Quarries Quarries will be established at the locations indicated or additional sites if identified during exceeded. construction.
Component Rationale Location Description Crushing Plant Crushing plant is likely to be located at or near the quarry sites. 4. Gullies with watercourses will be avoided Concrete Batching Concrete Batching Plants will be located either near current construction sites, or near unless it can be demonstrated that Plants material sources such as quarries or water abstraction sites. Indicative locations have downstream water quality effects are no been identified with specific locations to be determined prior to construction. The plants will more than minor. be re-locatable, with only one or two locations operating concurrently at any one time and sites being rehabilitated as soon as the Concrete Batching Plant is relocated. 5. Seepage areas dominated by indigenous species with an area greater than 0.05ha will be avoided. 6. Total CHWF earthworks volumes described in the AEE are not exceeded. 7. Noise standards will be complied with or effects will be appropriately mitigated.
Water abstraction Water abstraction and storage locations have been identified. The location of water abstraction and storage and storage areas facilities is shown in Figures A1 - A4.
Note: Where a component is to be located at a different place from that indicated in Figures A1 - A4, an ecological assessment in accordance with the methodology undertaken for the CHWF Ecological Effects Assessment will be undertaken and information will be provided to Council to confirm that the ecological outcomes associated with the revised location are within the nature and scale of effects described in the AEE.
Route 52
A3
Indicative Internal Road Design Indicative External Road Upgrades Indicative Electrical Balance of Plant Indicative Construc r 80M Internal Road Significant External Road Works Substations !(L Central La t 90M Internal Road Possible External Road Works Optional Switching Station !(B Concrete B yout 100L Internal Road % Bridges on External Roads "J Electrical Switchgear Huts !(Q Quarry Loc yout 110L Internal Road 220kV Internal Transmission Line Towers Quarry and ayout Internal Substation Access Road 220kV Internal Transmission Line Excess Fil ayout Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take _ Water Stor ! !! !! hiatua Road !! Pai Rimu Road !!! !!
!! !!
!
! ! ! !! !! !! ! !! ! !! ! ! ^_ ! ! ! ! !! R !! imu Ro !! ! ! ad ! !!
! ! ! !! !! ! !! !!! ! !!! ! !! !
!! ! ! !
! !! !!
!!!! ! ! !! !! ! ! ! ! !! ! ! ! ! ! ! !! ! ! !! ! ! ^_ W ! a a ihok !! i V a ! lle ! y R oad ! ! ! ! ! ^_ ! ! ! ! !! ! !! !! ! ! !! !! ^_ ! !! 52 ! ! te ! ! o u R !! ! ! ! ! ! ! !!!
!! !
A4
Indicative Internal Road Design Indicative External Road Upgrades Indicative Electrical Balance of Plant Indicative Construc r 80M Internal Road Significant External Road Works Substations !(L Central La t 90M Internal Road Possible External Road Works Optional Switching Station !(B Concrete B yout 100L Internal Road % Bridges on External Roads "J Electrical Switchgear Huts !(Q Quarry Loc yout 110L Internal Road 220kV Internal Transmission Line Towers Quarry and ayout Internal Substation Access Road 220kV Internal Transmission Line Excess Fil ayout Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take _ Water Stor ! ! ! ! ! !!
! ! !! !! ! ! !! ! ! ! ! !! ! ! ! ! !!
! ! ! !
! !!! !! !! ! ! D ! ag ! !! gs ! ! R ! ! ! ! o ! ! ! a ! ! ! d !! ! ! ! ! !! !! ! !! !! ! ^_ ! !! ! ! ! ! ! !! ^_ ! ! ! !!! ! ! ^_1 !! !! ! !! ! ! ! ! !! ! ! ! !! ! ! ! !!! !!
! ! M ! a ! ri ngi Ro !! !! ad ! ! ! ! !! ! ! !! ! !!! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !!! W ! ! a ! ! ir ! ir i !!! R o !! ! a ! d ! ! ! ! ! ! !
Indicative Internal Road Design Indicative External Road Upgrades Indicative Electrical Balance of Plant Indicative Construc r 80M Internal Road Significant External Road Works Substations !(L Central La t 90M Internal Road Possible External Road Works Optional Switching Station !(B Concrete B yout 100L Internal Road % Bridges on External Roads "J Electrical Switchgear Huts !(Q Quarry Loc yout 110L Internal Road 220kV Internal Transmission Line Towers Quarry and ayout Internal Substation Access Road 220kV Internal Transmission Line Excess Fil ayout Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take _ Water Stor ! ! ! ! ! ! ! ! ! ! ! !! ! !! !!! ! ! !! ! ! ! ! ! ! ! ! ! !! ! !
!! !!
! ! !!
^_ ! ! ! !! !!! ! !! !! ! ! !!!!
!! !! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !! !! ! !! ! ! !! ! ! ! ! !! ! ! ! ! ! ! ! !! ! ! ! ! ! ! ! ! ! ! ! !! !! !! !! ! ! d ! ! a ! ! !! o ! ! ! R !! !
a ! ! w
a ! !! n
a ! M ! ^_ ! ! !! !! ! !! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !!! !! ^_ !! !! !!
T inui
Indicative Internal Road Design Indicative External Road Upgrades Indicative Electrical Balance of Plant Indicative Construc r 80M Internal Road Significant External Road Works Substations !(L Central La t 90M Internal Road Possible External Road Works Optional Switching Station !(B Concrete B yout 100L Internal Road % Bridges on External Roads "J Electrical Switchgear Huts !(Q Quarry Loc yout 110L Internal Road 220kV Internal Transmission Line Towers Quarry and ayout Internal Substation Access Road 220kV Internal Transmission Line Excess Fil ayout Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take _ Water Stor
TABLE A1: Castle Hill Wind Farm Landowner Titles and Road Reserves
TARARUA DISTRICT
LO NAMES ON TITLES TITLES TOTAL ID 3 Derek Montgomery Daniell 44D/778 39B/175 44A/466 3 Evelyn Christine Daniell Colin Anthony Garstang
4 Bruce Douglas McKenzie 306/196 44C/317 493/140 743/60 743/61 5 Ian Ronald McKenzie
5 Alan Graham Mitchell 40D/171 1 Wendy Waihuia Mitchell Michael Gordon Lawrence
6 Andrew Eric Falloon 223130 442/68 82281 67638 4 Simon Sinclair McKay
7 Daniel Bryan Edmonds 150214 35C/886 67637 3 Elizabeth June Edmonds Graeme Albert Bayliss
8 Lisa Jane Richardson B2/277 374651 2 Neil John Richardson Graeme Charles Richardson
10 Suzanne Mary Smith 39A/366 475/295 13D/1266 3 Frank Duncan John Smith
11 William Ross White 1 40A/934
12a Elizabeth Esther Billington 13D/1267 41B/226 812/29 3 Allen Charles Billington
12b Waterfall Farm Limited 812/28 13C/254 39A/89 22B/754 4
13 Cyril Graham Shaw 57C/750 1 Gabrielle Anne Sinclair
14 Jeane Louise Burns Fowler 107308 43D/975 528/214 596/111 4 James Fowler LCCA Trustees Limited
TARARUA DISTRICT (cont.)
LO NAMES ON TITLES TITLES TOTAL ID 16a Darztech Limited 37A/509 37A/510 779/75 3
16b Simon Peter France (1/4) 107307 24C/643 57C/749 3 Mark William Freeman (1/4) Darztech Limited (1/2)
17 James Ian Mason 11B/1180 1 Diane Elizabeth Mason Gawith Trustees 2009 Ltd
25 Waimapu Land Developments 673/1 1
29 Otapawa Station Limited 18B/1157 190/221 22C/677 22D/250 32 23C/125 23C/126 240154 248166 248169 248180 25A/289 25A/487 25A/645 25B/116 25C/18 26B/211 26B/899 276/203 29C/17 321/35 326/228 35A/385 39A/90 416/192 446/294 459/3 817/64 959/81 B3/102 E1/1095 E3/268 807/6
30a Michel George Hart 191/14 24C/774 24D/471 24D/472 277/280 322/247 327/214 578/149 616/14 9 Gaylene Ngaire Hart Thomas Joseph Anthony Fouhy
Michael Gorge Hart 223/119 646/91 2 Gaylene Ngaire Hart
31 Te Rimu Station Limited 19D/314 215/238 231/254 231/255 231/256 231/280 23B/766 24B/963 21C/38 25 24C/455 24D/779 24D/781 255/124 255/125 255/128 25A/642 284/85 28620 311/89 311/90 35B/485 35C/550 370/248 465/284 953/99
Legal Road Reserve vested in Tararua District Council: Pahiatua Road; Rimu Road; Route 52; Waihoki Valley Road, Rakaunui Road, Waitawhiti Road, Castle Hill Road, Ngarata Road, Puketawa Road.
MASTERTON DISTRICT
LO NAMES ON TITLES TITLES TOTAL ID 1 Alan John Barton 21D/959 21D/960 597/267 597/268 C2/1383 5 Sally Vivianne Barton
2 Robert Alexander Kyle 15A/1416 15A/1417 15A/205 16D/547 18D/692 5 Robson Blyth King
3 Derek Montgomery Daniell 13D/160 39B/175 44A/466 77/70 966/80 44D/778 6 Evelyn Christine Daniell Colin Anthony Garstang
4 Bruce Douglas McKenzie 743/61 44C/317 2 Ian Ronald McKenzie
5 Alan Graham Mitchell 40D/171 1 Wendy Waihuia Mitchell Michael Gordon Lawrence
6 Andrew Eric Falloon 67638 1 Simon Sinclair McKay
7 Daniel Bryan Edmonds 67637 150214 35C/886 3 Elizabeth June Edmonds Graeme Albert Bayliss
8 Lisa Jane Richardson 374651 B2/227 2 Neil John Richardson Graeme Charles Richardson
10 Suzanne Mary Smith 13D/1266 23A/395 23A/396 41B/334 B1/505 B2/146 39A/366 7 Frank Duncan John Smith
12a Elizabeth Esther Billington 13D/1267 1 Allen Charles Billington
14 Jeane Louise Burns Fowler 840/52 528/214 2 James Fowler LCCA Trustees Limited
24a Robert James Joblin Deborah Jane Joblin 44B/441 Gawith Trustees Limited
MASTERTON DISTRICT (cont.)
LO NAMES ON TITLES TITLES TOTAL ID 24b Deborah Jane Joblin 672/99 9B/1000 832/100 3 Gawith Trustees Limited Gawith Trustees Limited
25 Waimapu Land Developments 672/100 673/1 2
26 Tanglewood Forests Limited 3 15A/1418 15A/203 15A/204
34 Blair Douglas McPhail 40A/961 1 Joanne Ruth McPhail Simon Wellbourne Ogilvie
35 Tirohanga Land Limited 44A/204 1
36 John Robert Canning 490/212 605/255 2 Bridget Diana Canning John William Dalziell
37 Richard James Wylie 473/119 A4/1028 2 John William Kershaw Robert William Maunsell
39 Lindsay Boyd Gribben 16A/492 289/18 16A/379 3 Donald Bruce Todd
43a David William Dalziell 171587 1 Kerry Suzanne Dalziell Graeme Albert Bayliss
43b William David Dalziell 8B/173 8B/174 9D/176 3 Graeme Albert Bayliss David William Dalziell
44 Robert James Cresswell WN56B/481 1 Mangahao Trustees (2006) Limited
Legal Road Reserve vested in Masterton District Council: Alfredton – Tinui Road / Manawa Road, Maringi Road; Route 52; Daggs Road.
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
TABLE OF CONTENTS
Page
1. INTRODUCTION 1
1.1 The Castle Hill Wind Farm Project 1 1.2 Introduction to Genesis Energy 9
1.2.1 Background 9 1.2.2 Approach to Environmental Issues 9
1.3 Resource Consent Requirements 10 1.4 Land Ownership 12 1.5 Written Approvals 12 1.6 Environmental Assessments Undertaken 12 1.7 Structure of this Report 14
2. PROJECT RATIONALE 15
2.1 Introduction 15 2.2 Overview of the New Zealand Electricity Situation 15
2.2.1 Electricity Supply and Demand in New Zealand 15 2.2.2 The Importance of a Secure Electricity Supply 16 2.2.3 Matters Affecting Future Supply Options 17
2.3 Development Approach 20
2.3.1 Wind Resource 20 2.3.2 Suitable Land Availability 21 2.3.3 Distance from Large Population Centres 21 2.3.4 Accessibility 21 2.3.5 Ability to Connect to the National Grid 22 2.3.6 Avoidance of Sensitive Environmental Areas 22
2.4 Summary 22
3. ENVIRONMENTAL SETTING 24
3.1 Social Setting 24 3.2 Cultural Setting 27
3.2.1 Historical Background 27 3.2.2 Archaeology and Heritage 29
3.3 Physical and Ecological Setting 32
3.3.1 General Site Characteristics 32 3.3.2 Landscape 35 3.3.3 Existing Noise Environment 38 3.3.4 Roading and Traffic 42 3.3.5 Surface Water Resources 48
Table of Contents page i
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
3.3.6 Groundwater Resources 63 3.3.7 Terrestrial Ecology 64
3.4 Summary 77
4. PROPOSED DEVELOPMENT 78
4.1 Introduction 78 4.2 CHWF Development Process 78
4.2.1 Introduction 78 4.2.2 Site Selection 78 4.2.3 Concept Studies 80 4.2.4 Preliminary Design and Environmental Assessments 80 4.2.5 Project Design and Assessment of Environmental Effects 81 4.2.6 Alternatives Considered 84
4.3 Project Components 85
4.3.1 Introduction 85 4.3.2 Turbines 86 4.3.3 Electrical Balance of Plant 94 4.3.4 Internal Roads 112 4.3.5 External Roads 118 4.3.6 Permanent Operation and Maintenance Facilities 127 4.3.7 Monitoring Masts 129 4.3.8 Temporary Construction Facilities 130
4.4 Construction Process 140
4.4.1 Construction Methodology 140 4.4.2 Construction Programme and Personnel 140 4.4.3 Construction Materials 141 4.4.4 On-Site Earthwork Activities 142 4.4.5 External Road Earthworks Requirements 146 4.4.6 Erosion and Sediment Control 151 4.4.7 Tree Clearance and Trimming 152 4.4.8 Bulk Fuel Storage and Refuelling 152 4.4.9 Delivery of Turbine Components 152
4.5 Consenting Approach for Location of CHWF Components 154 4.6 Site Reinstatement 159 4.7 Operation and Maintenance Activities 159 4.8 Management Plans 160
5. ASSESSMENT OF ENVIRONMENTAL EFFECTS 161
5.1 Introduction 161 5.2 Socio-economic Effects 161
5.2.1 Electricity-Related Effects 161
Table of Contents page ii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
5.2.2 Economic Effects 162 5.2.3 Recreation and Tourism 164 5.2.4 Summary 168
5.3 Landscape and Visual 169
5.3.1 Introduction 169 5.3.2 Wind Farm Visibility 170 5.3.3 Visibility from Public Viewpoints 175 5.3.4 Visibility from Rural Dwellings 180 5.3.5 Landscape and Visual Effects of the CHWF 182 5.3.6 Summary 193
5.4 Noise Effects 194
5.4.1 Introduction 194 5.4.2 Relevant Noise Standards 194 5.4.3 Construction Noise 196 5.4.4 Operational Noise 203 5.4.5 Summary 215
5.5 Traffic Effects 216
5.5.1 Introduction 216 5.5.2 Construction Traffic Effects 217 5.5.3 Traffic Management 227 5.5.4 Operational Traffic Effects 228 5.5.5 Cumulative Traffic Effects 229 5.5.6 Summary 229
5.6 Potential Effects on Water Resources 230
5.6.1 Introduction 230 5.6.2 Surface Water Effects 231 5.6.3 Groundwater Effects 251 5.6.4 Summary 254
5.7 Ecological Effects 255
5.7.1 Introduction 255 5.7.2 Ecological Vegetation Values 256 5.7.3 Vegetation and Habitat Cover at the CHWF Site 257 5.7.4 Potential Vegetation Clearance 257 5.7.5 Birds 265 5.7.6 Bats 266 5.7.7 Lizards and Frogs 266 5.7.8 Terrestrial Invertebrates 267 5.7.9 Summary 267
5.8 Cultural Effects 267 5.9 Archaeology and Heritage 269
5.9.1 Introduction 269
Table of Contents page iii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
5.9.2 Potential Effects on Archaeological and Heritage Sites 271 5.9.3 Summary 272
5.10 Shadow Flicker and Blade Glint 272
5.10.1 Introduction 272 5.10.2 Shadow Flicker Assessment 273 5.10.3 Effects of Shadow Flicker on External Dwellings 274 5.10.4 Risks to the Public 275 5.10.5 Summary 275
5.11 Radio-communication and Telecommunication Services 276
5.11.1 Introduction 276 5.11.2 Possible Interference Effects 276 5.11.3 Potential Radio Interference Effects of the CHWF 277 5.11.4 Summary 283
5.12 Aviation 284
5.12.1 Introduction 284 5.12.2 Potential Effects on Aviation 284 5.12.3 Summary 286
5.13 Electric and Magnetic Fields 286
5.13.1 Introduction 286 5.13.2 Electric and Magnetic Fields 286 5.13.3 Potential Health Effects of Electric Magnetic Fields 287 5.13.4 Summary 289
5.14 Summary of Environmental Effects 289
6. PROPOSED MONITORING AND MITIGATION 296
6.1 Introduction 296 6.2 Management Plans 296
6.2.1 Overview 296 6.2.2 Environmental Management Plan 296 6.2.3 Supplementary Environmental Management Plans 298
6.3 Construction Activities 299
6.3.1 Earthworks and Sedimentation 299 6.3.2 Construction Traffic 303 6.3.3 Cultural, Archaeological and Heritage 308 6.3.4 Surface and Groundwater Resources 309 6.3.5 Noise 311 6.3.6 Ecology 312
6.4 Operational Activities 315
Table of Contents page iv
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
6.4.1 Landscape and Amenity 315 6.4.2 Telecommunication and Radio-communication Services 316 6.4.3 Aviation 318 6.4.4 Operational Noise 319 6.4.5 Ecology 320
6.5 Proposed Monitoring 320 6.6 Summary 323
7. CONSULTATION 324
7.1 Introduction 324 7.2 The Consultation Process 324
7.2.1 Overview 324 7.2.2 Wider Community Consultation 325 7.2.3 CHWF Landowners 327 7.2.4 Neighbouring Landowners and Residents 328 7.2.5 Tangata Whenua 329 7.2.6 Local Authorities 332 7.2.7 Other Interested or Potentially Affected Parties 335
7.3 Issues Identified in Consultation 342 7.4 Summary 342
8. STATUTORY FRAMEWORK 343
8.1 Resource Management Act 1991 343
8.1.1 Fourth Schedule Requirements 343
8.2 Resource Consent Requirements and Activity Status 347
8.2.1 Introduction 347 8.2.2 Manawatu – Wanganui Regional Council 349 8.2.3 Tararua District Council 357 8.2.4 Wellington Regional Council 360 8.2.5 Masterton District Council 365
8.3 Statutory Planning Documents 369
8.3.1 National Policy Statement for Renewable Electricity Generation 369 8.3.2 National Policy Statement for Freshwater Management 2011 370 8.3.3 Manawatu-Wanganui Regional Council Policy Statement and Plans 371 8.3.4 Tararua District Council Plans 384 8.3.5 Wellington Regional Council Policy Statement and Plans 388 8.3.6 Masterton District Council Plan 397
Table of Contents page v
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
8.4 Section 104 Assessment 401
8.4.1 Introduction 401 8.4.2 Actual and Potential Effects 402 8.4.3 Relevant Provisions of Statutory Planning Documents 404 8.4.4 Other Relevant Matters 407 8.4.5 RMA Part 2 407
9. CONCLUDING STATEMENT 409
10. REFERENCES 410
LIST OF FIGURES
1.1: Location of the CHWF Site. 2
1.2: Layout of the CHWF. 4
1.3(i): Component overview of the CHWF (A1). 5
1.3(ii): Component overview of the CHWF (A2). 6
1.3(iii): Component overview of the CHWF (A3). 7
1.3(iv): Component overview of the CHWF (A4). 8
2.1: Electricity consumption by sector and by region in 2010 (MED, 2011). 16
2.2: Total consumer energy in New Zealand (1990 – 2010) (MED, 2011). 17
3.1: Dwellings located within and near the CHWF Site. 26
3.2: Indicative map showing recorded archaeological sites around the CHWF Site. 30
3.3: Location of potential pa sites in or near the CHWF. 31
3.4: Location of historic woolsheds between Turbine Cluster E and F. 32
3.5: Location of background noise measurement sites. 39
3.6: Background noise at External Dwelling X397. 40
3.7: Background noise at External Dwelling X185. 40
3.8: Background noise at External Dwelling X377. 41
3.9: Background noise at 153 Wairiri Road. 41
Table of Contents page vi
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
3.10: Water quality and aquatic biology sampling sites. 53
3.11: Locations of five-minute bird count and flight path monitoring stations. 68
3.12(i): Example of a Bird Flight Path Monitoring Map for Cluster E at the CHWF Site. CHFP5B had the highest number of observed flight paths - all heights 69
3.12(ii): Example of a Bird Flight Path Monitoring Map for Cluster E at the CHWF Site. CHFP5B had the highest number of observed flight paths - within the potential rotor zone. 70
3.12(iii): Example of a Bird Flight Path Monitoring Map for Cluster D at the CHWF Site. CHFP4B had the lowest number of observed flight paths - all heights. 71
3.12(iv): Example of a Bird Flight Path Monitoring Map for Cluster D at the CHWF Site. CHFP4B had the lowest number of observed flight paths - within the potential rotor zone. 72
3.13: Locations of automated digital bat recorders and bat detections at the CHWF Site. 73
3.14: Location of Artificial Cover Objects (ACOs) and lizards found within the CHWF Site. 75
3.15: Sampling locations for invertebrates within the CHWF Site. 76
4.1: Schematic of Turbine components. 87
4.2: Unmodified Turbine Corridor (green) with four overlying Indicative Turbine Layouts. 88
4.3: Refined Turbine Corridor (green). 89
4.4: Relationship between numbers of Medium and Large Turbines in the Mixed Turbine Configuration. 90
4.5: Schematic Turbine Foundation cross-section. 92
4.6: Schematic layout of a Turbine Platform. 93
4.7: Electrical Balance of Plant Option 1. 97
4.8: Electrical Balance of Plant Option 2. 98
4.9: Schematic Main Substation layout. 101
4.10: Schematic Satellite Substation layout. 102
4.11: Schematic plan view of the optional Switching Station. 103
4.12: Schematic cross-sections for underground cable trench design. 104
Table of Contents page vii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
4.13: Schematic of overhead line to underground cable transition for Internal Road crossings. 105
4.14: Isometric view of multiple 33kV line arrangements. 106
4.15: Isometric view of alternative multiple 33kV line arrangement. 107
4.16: Schematic 33kV double circuit pole design. 107
4.17: Schematic 33kV double circuit pole design. 108
4.18: Schematic 33kV four circuit pole design. 109
4.19: Lattice and monopole 220kV tower structure options. 111
4.20: Representative external Turbine transformer kiosk design. 111
4.21: Representative switchgear hut design. 112
4.22: Schematic Internal Road cross-section design. 117
4.23: Proposed Internal Road water crossings. 119
4.24: Proposed OW/OD Route to the CHWF Site. 123
4.25: Road design on External Roads to Site. 125
4.26: Proposed work requirements and locations of External Road bridges. 126
4.27: Schematic O&M facility layout. 128
4.28: Schematic of Contractor Compound layout. 132
4.29: Location of key civil structures for the CHWF. 133
4.30: Conceptual intake design for the water take structures. 139
4.31: Schematic transport configuration for a nacelle. 153
5.1: Location of visitor settings within 15 km of the CHWF Site. 166
5.2: Modelled sound power level curves for the CHWF noise assessment. 204
5.3: Predicted noise levels of Turbines at External Dwelling X185. 207
5.4: Predicted noise levels of Turbines at External Dwelling X265. 208
5.5: Predicted noise levels of Turbines at External Dwelling X396 and X407. 208
5.6: Predicted noise levels of Turbines at External Dwelling X358. 210
5.7: Predicted noise levels of Turbines at External Dwelling X362. 210
5.8: Predicted noise levels of Turbines at External Dwelling X405. 211
Table of Contents page viii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
5.9: Predicted noise levels of Turbines at External Dwelling X377. 212
5.10: Flow duration curve for Te Hoe Stream showing effect of proposed take on flow frequency. 239
5.11: Flow duration curve for the Tiraumea Stream at Haunui Rd showing effect of proposed take on flow frequency. 241
5.12: Flow duration curve for the Tiraumea River at its confluence with Ihuraua showing effect of proposed take on flow frequency. 243
5.13: Flow duration curve for the Tinui River at Taipo showing the effect of proposed take on flow frequency. 244
5.14: Schematic cross-section – reduced flow at mid-slope features. 253
5.15: All fixed radio linking services operating near the CHWF. 281
5.16: Protection of wide area coverage services. 282
LIST OF PLATES
Plate 3.1: Forestry block of Pinus radiata and pastoral grass in the CHWF Site. 25
Plate 3.2: Example of typical vegetation cover (pastoral grass) in the CHWF Site, with occasional stands of native vegetation and pine forest in the distance. 33
Plate 3.3: Elevated hill country with narrow steep gully slopes and grazed pasture across the CHWF Site from Rangitumau. 36
Plate 3.4: Grazed pasture on hilltops with remnants of indigenous vegetation in gullies (Waitawhiti Road). 36
Plate 3.5: Lowlands and valleys landscape type in the CHWF Site (Manawa Road). 38
Plate 3.6: Stock pond within the CHWF Site formed by blocking a small tributary in the headwaters of the Tiraumea Stream. 49
Plate 4.1: Indicative 80 m lattice wind monitoring mast. 130
Plate 4.2: Typical transporter for a Vestas V80 section of tower. 153
Plate 4.3: Indicative transporter for a Vestas V80 blade. 154
Table of Contents page ix
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
LIST OF TABLES
1.1: Summary of resource consents required from MWRC. 11
1.2: Summary of resource consents required from GWRC. 11
1.3: Summary of resource consents required from TDC. 11
1.4: Summary of resource consents required from MDC. 12
3.1: Radio-communication services operating in the CHWF area (Kordia, 2011). 27
3.2: External Road classifications. 43
3.3: External Road dimensions in the vicinity of the CHWF Site. 44
3.4: Current and forecasted traffic volumes for External Roads near the CHWF Site. 47
3.5: Physical characteristics of the watercourses sampled within and downstream of the CHWF Site (June 2010 and March 2011). 54
3.6: Water quality parameters in watercourses within and downstream of the CHWF Site (June 2010 and March 2011). 57
3.7: Interpretation of MCI, SQMCI and QMCI index values from Stark (1993) (Quality) and Stark and Maxted (2004) (Water Quality). 60
3.8: Vegetation types, relative ecological values, extent and distribution at the CHWF Site. 66
4.1: Outline of the CHWF development process. 79
4.2: Indicative Turbine Layouts. 91
4.3: Indicative Turbine Foundation parameters. 92
4.4: Estimated multiple line lengths. 106
4.5: Internal Road water crossings to access Turbines and substations. 120
4.6: Internal Road water crossings to access Internal Transmission Line towers. 121
4.7: Proposed water abstraction points. 138
4.8: Material requirements for Medium and Large Turbine Layouts. 141
4.9: Maximum earthwork volumes for the Medium Turbine Layout (based on 80M layout). 143
Table of Contents page x
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
4.10: Maximum earthwork volumes for the Large Turbine Layout (based on 100L layout). 144
4.11: Maximum earthwork area by type for the Large Turbine Layout (based on 100L layout). 144
4.12: OW/OD Route earthwork volumes between Alfredton and the CHWF Site. 148
4.13: External Road bridge work descriptions. 149
4.14: External Road bridge work requirements (SH2 to the CHWF Site). 150
4.15 Description of component location extent. 156
4.16: Proposed Site reinstatement. 159
5.1: Location key to 5.1. 165
5.2: Visibility (based on landform screening only) within 10 km of the nearest Turbine. 174
5.3: Public viewpoint visibility of the CHWF. 176
5.4: Rural dwellings located within 5 km of the nearest Turbine. 180
5.5: Rural dwelling visibility within 5 km of the nearest Turbine. 181
5.6: Potential visual effects on dwellings within 5 km of the nearest CHWF Turbine. 185
5.7: Recommended upper noise limits (dBA) for construction work noise received at dwellings in Rural Areas – long-term project duration (NZS6803). 195
5.8: Predicted Turbine Foundation and Platform construction noise levels at nearest External Dwellings. 197
5.9: Construction sound levels at External Dwellings near the Main Substation options. 198
5.10: Construction sound levels at External Dwellings near the Satellite Substation. 198
5.11: Predicted construction traffic noise levels. 200
5.12: Predicted Turbine noise levels at External Dwellings. 205
5.13: Wind farm noise assessment summary at External Dwellings. 206
5.14: Sound levels at External Dwellings near the Main Substation (both options). 213
5.15: Sound levels at External Dwellings near the Satellite Substation. 214
Table of Contents page xi
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
5.16: Forecast peak total contractor vehicle movements – daily, peak hour and mid-day. 222
5.17: Erosion and sediment control risk assessment by Turbine Cluster. 234
5.18: Sediment loads from high risk areas. 235
5.19: Proposed regime for taking water in the Tiraumea Catchment. 238
5.20: Proposed regime for taking water in the Tinui Catchment. 238
5.21: Effects of the proposed water abstraction on key values of Te Hoe Stream. 240
5.22: Effects of the proposed take on key values of Tiraumea Stream at Haunui Rd. 242
5.23: Effects of the proposed take on key values of Tiraumea River at its confluence with Ihuraua. 243
5.24: Effects of the proposed take on key values of the Tinui River at Taipo. 245
5.25: Vegetation and habitat classifications applied at the CHWF Site. 256
5.26: Classifications assigned to vegetation and habitat types at the CHWF Site. 258
5.27: Ecological classifications of vegetation and habitats associated with potential On-site*** total vegetation clearance and potential indigenous vegetation clearance. 260
5.28: Ecological classifications of vegetation and habitats associated with the potential Off-site total vegetation clearance and potential indigenous vegetation clearance at the CHWF Site. 260
5.29: Vegetation and habitat types potentially affected by On-site construction activities for the CHWF. 261
5.30: Vegetation and habitat types potentially affected by Off-site construction activities for the CHWF. 262
5.31: External Dwellings located within the zone of influence. 274
5.32: Exposure to shadow flicker at dwellings within the zone of influence. 274
5.33: Services likely to be interfered with and the level or risk that interference will occur due to the CHWF. 278
8.1: The relevant statutory planning documents for the CHWF. 348
8.2: Summary of resource consents required from MWRC. 349
8.3: Summary of resource consents required from TDC. 357
Table of Contents page xii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
8.4: Summary of resource consents required from GWRC. 360
8.5: Summary of resource consents required from MDC. 365
Table of Contents page xiii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
GLOSSARY
AEE Assessment of Environmental Effects
Areas On-site that may be used to store Turbine components for a sub-set of Turbine locations, or on which construction equipment and Central Laydown Area(s) materials can be placed. This is an alternative option to storing components Off-site or at individual Turbine Platforms.
CHWF Castle Hill Wind Farm.
Owners of the land on which the wind farm will be built. CHWF CHWF Landowners Landowners have signed agreements with Genesis Energy.
CHWF Site or Site The area of land defined by the land titles covered by agreements.
CHWF Landowner Dwellings within the CHWF Site. Dwellings
A facility required for making concrete. Likely to include a concrete Concrete Batching Plant mixer, cement silos, sand and aggregate stockpiles, water storage tanks and storage areas for equipment and tools.
Construction Traffic External Roads used for non-OW/OD construction traffic. Routes
Centre for construction management and workshop based activities Contractor Compound consisting of offices, workshops, storage, parking and amenities.
All electrical structures and equipment related to the collection and reticulation of electrical power around CHWF and required to connect Electrical Balance of Plant the CHWF to the External Transmission Line. Plant includes (EBoP) underground cables, overhead reticulation lines, transformers, substations and switchgear.
Excavated material (excluding top soil) that is incorporated into engineered earthworks such as road fills, Turbine Platforms and Engineered Fill Central Laydown Areas. Placement and treatment of the Engineered Fill is designed to meet construction requirements for such aspects as drainage, strength and stability.
Soil removed from the ground which is either not suitable or not Excess Fill needed as Engineered Fill.
Excess Fill Areas Areas for disposal of Excess Fill.
External Dwellings Dwellings external to the CHWF Site.
Public roads that are planned to be used for traffic associated with the External Roads construction and operation of the CHWF and including roads used by Over-weight and Over-dimension Vehicles.
Glossary page i
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
External Transmission The electricity transmission line which connects CHWF to the Line Transpower national grid.
Turbine layouts that have been created to represent the range of possible Turbine layouts:
80M – a Turbine layout consisting of 286 Medium Turbines based on a Turbine with an 80m rotor diameter.
90M – a Turbine layout consisting of 262 Medium Turbines based Indicative Turbine Layouts on a Turbine with a 90m rotor diameter.
100L – a Turbine layout consisting of 242 Large Turbines based on a Turbine with a 100m rotor diameter.
110L – a Turbine layout consisting of 186 Large Turbines based on a Turbine with a 110m rotor diameter.
Roads that will be constructed within the CHWF Site for transporting Internal Roads wind farm components and materials within the Site and to allow access around the Site for construction and operational activities.
Internal Transmission The 220kV electricity transmission line that is On-site and connects Line the Main Substation to the Satellite Substation.
Internal Transmission The deviation of the Internal Transmission Line to connect it to the Line Deviation Switching Station.
Large Turbine Any Turbine configuration that consists only of Large Turbines with a Configuration maximum quantity of 242 Turbines.
Turbines that have a maximum tip height greater than 135 m but no Large Turbines greater than 155 m.
A passing bay which provides a means for heavy vehicles to pass Lay-by each other in Internal Roads.
The larger of the two substations, located in the southern region of the Main Substation wind farm.
Medium Turbine Any Turbine configuration that consists only of Medium Turbines with Configuration a maximum quantity of 286 Turbines.
Medium Turbines Turbines that have a maximum tip height of 135 m.
Any Turbine configuration that consists of a mixture of Large Turbines Mixed Turbine and Medium Turbines with a maximum quantity of Turbines limited by Configuration the proportion of Medium and Large Turbines.
Off-site Anywhere outside the CHWF Site.
Glossary page ii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
On-site Anywhere within the CHWF Site.
The area of ground covered by all permanent and temporary wind On-Site Construction farm components. This includes extents of all cuts and fills during Footprint construction.
The area of ground covered by all permanent or semi-permanent On-Site Operational components. Semi-permanent are those components that are primarily Footprint used for construction, but may occasionally be used during operation of the wind farm. They will not be actively rehabilitated.
OW/OD Over-weight and/or over-dimension.
OW/OD Route External Roads used for OW/OD Vehicles.
Any vehicle with a gross mass in excess of 40 tonnes and/or over 20 OW/OD Vehicles metres in length, 2.5 m in width and 4.25 m in height.
The top layer of material on the Internal Road that forms a surface that Road Pavement is designed specifically for traffic to regularly pass over it.
The smaller of the two substations, located in the northern region of Satellite Substation the wind farm.
Provides an optional connection point for the External Transmission Switching Station Line to connect to the Internal Transmission Line as an alternative to connecting at the Main Substation.
Wind Turbine generators consisting of foundations, tower, nacelle and Turbines rotor, and including all equipment for, and associated with the generation of electricity from wind.
Turbine Clusters Grouping of Turbines for ease of reference.
Turbine Corridor The area of the CHWF Site in which wind Turbines can be located.
The underground foundation upon which each Turbine is based and Turbine Foundations which keeps the Turbine upright and stable.
An engineered flat area beside the Turbine that will be used for laying out and assembling Turbine components and as a hard standing area Turbine Platform for construction equipment and vehicles, particularly the construction crane.
Entrances to the CHWF Site where External Roads meet Internal Wind Farm Access Points Roads.
Glossary page iii
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
1. INTRODUCTION 1.1 The Castle Hill Wind Farm Project
Genesis Power Limited (trading as “Genesis Energy”) is proposing to establish and operate the Castle Hill Wind Farm (“CHWF”) on privately1 owned rural land in northern Wairarapa. The CHWF involves up to 286 wind Turbines with a potential nominal capacity of up to 860MW of renewable electricity generation. The electricity produced is potentially equivalent to that consumed each year by up to 370,0002 average New Zealand households.
The CHWF Site (where agreements have been negotiated with landowners) covers some 30,000 ha and is located approximately 20 kilometres (“km”) northeast of Masterton, 20 km east of Eketahuna and Pahiatua and 15 km west of the Wairarapa Coast north of Castlepoint (see Figure 1.1). The CHWF Site is located in a remote area that is relatively sparsely populated. The closest settlements are Tiraumea, Alfredton, Bideford, Tinui, Pongaroa, Makuri and Mauriceville.
The area that has been selected for Turbine placement is referred to as the “Turbine Corridor”. The Turbine Corridor covers approximately 3,144 ha and is shown in Figure 1.2. The Turbines have been grouped into seven “Turbine Clusters” (A to G) for ease of reference. The On-site Construction Footprint will be approximately 861 ha, while the On-site Operational Footprint of the CHWF will be approximately 226 ha.
In designing the CHWF, Genesis Energy has undertaken a comprehensive design and site layout analysis, considering environmental values and engineering practicalities, to ensure the proposal is appropriately located and that it avoids, remedies or mitigates adverse effects as required by the Resource Management Act 1991 (“RMA”).
The key project components and features of the CHWF are described in detail in Section 4 of this document, and include:
Turbines: Wind Turbine generators consisting of foundations, tower, nacelle and rotor, and including all equipment for, and associated with the generation of electricity from wind.
Turbine Corridor: 3,144 ha identified as suitable for Turbine placement. Turbines will be located within this corridor.
Turbines: Up to 286 Medium Turbines (maximum tip height 135 m) or up to 242 Large Turbines (maximum tip height greater than 135 m but no greater than 155 m) or a mixture of Medium and Large Turbines installed within the Turbine Corridor. The maximum number of Turbines for the CHWF is 286.
Internal Roads: roads constructed within the CHWF Site for transporting wind farm components, materials and personnel within the Site and to allow access around the Site for construction and operational activities.
1 Where External Roads dissect the CHWF Site, the road reserve only forms part of the CHWF Site where works are required in those areas. 2 Calculated on 3,000 GWh divided by the average annual residential consumer consumption of 8,100 kWh in 2010 (Concept Consulting, 2011).
Introduction Section 1 – page 1
Legend NAPIER HASTINGS " CHWF Site "
PalmerstonCouncil North Boundary City "WANGANUI
Pahiatua "MASTERTON
"WELLINGTON
Makuri Manawatu-Wanganui Region Tararua District Pongaroa
Tiraumea Eketahuna
Alfredton
Mauriceville
Mataikona
Masterton District Wellington Region Bideford
Tinui
Castlepoint
048122 W-CHL-GE-001 Kms
Figure 1.1: Location of the CHWF Site. Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Operations infrastructure e.g. operations and maintenance facilities (“O&M facilities”).
Electrical Balance of Plant (“EBoP”): all electrical structures and equipment related to the collection and reticulation of electrical power around the CHWF to the point of connection to the External Transmission Line. Plant includes an Internal Transmission Line, 33kV overhead lines, 33kV underground cables, a Main Substation and Satellite Substation, an optional Switching Station and switch gear huts, along with other associated electrical equipment.
Monitoring masts: up to 16 monitoring masts to collect on-going meteorological information during the operational life of the CHWF.
External Roads: public roads near the Site that are planned to be used for traffic associated with the construction and operation of the CHWF and by Over-weight and Over-dimension Vehicles (“OW/OD Vehicles”).
Temporary construction infrastructure: components required for construction of the CHWF, including Concrete Batching Plants, Central Laydown Areas, Excess Fill Areas, Contractor Compound, quarrying3 and crushing facilities, and water storage and abstraction facilities.
The layout of the CHWF is shown in Figure 1.2, and in more detail in Figures 1.3(i) to 1.3(iv).
Genesis Energy is in discussions with Transpower in respect to the External Transmission to connect the CHWF to the national grid. RMA approvals for the External Transmission Line are not part of this application and will be sought separately from these resource consent applications.
This document is an Assessment of Environmental Effects (“AEE”) supporting the resource consent applications for the construction, operation and maintenance of the CHWF as required under the RMA. It addresses all matters required by the Fourth Schedule of the RMA as summarised in Section 8 of this document. A glossary of specific terms used is provided at the beginning of this document. These terms are capitalised when used in the remainder of this document.
A Construction and Operations Management Report (“COMR”) has been prepared to support this application and is attached to this document in Appendix A (Volume 2).
3 Some quarry sites may remain in service during the operational phase of the CWHF.
Introduction Section 1 – page 3
Legend G Wind monitoring masts (existing) Turbine Corridor Turbine Cluster (A-G) CHWF Site Electrial Balance of Plant )"1 Main Substation option 1 )"2 Main Substation option 2 )"3 Satellite Substation )"4 Switching Station (optional) Internal Transmission Line (220kV) A Internal Transmission Line Deviation Internal Roads Turbine access Substation access Internal Transmission Line tower access
B
D C
E G
F
02461 W-CHL-LY-001 Kms
Figure 1.2: Layout of the CHWF. " P a Va l le y R o Valley Road a ne d
"
"
"
"
Route 52 "
" "
"
Alfr " e " d
t o n R o a d " "
"" " "" " "" " " "
egend
Council Boundary Indicative Turbine Layout Indicative Internal Road Design Electrical Balance of Plant Indicative Construction Areas CHWF Site ! 80M Turbine Layout 80M Internal Road Substations !(L Laydown Areas Turbine Corridor ! 90M Turbine Layout 90M Internal Road Optional Switching Station !(B Concrete Batching Plant Turbine Cluster (A-G) ! "J Electrical Switchgear Huts 100L Turbine Layout 100L Internal Road !(Q " Quarry Locations External Dwellings ! 110L Turbine Layout 110L Internal Road 220kV Internal Transmission Line Towers " Quarry and Crushing Fac CHWF Landowner Dwellings Internal Substation Access Road 220kV Internal Transmission Line Excess Fill Areas Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take Points ^_ Internal Road Water Course Crossings 33kV Overhead Internal Electrical Lines Water Storage Areas Transport Route 33kV Underground Interal Electrical Cables NtAtiitA " " "
"
""
" " ! !! A " !! A !! PaihiatuaR Road imu Road !!! !! " !! A !! !
! ! ! !! !
! A !! ! " !! " ! !! ! ! ^_ ! ! ! ! !! R !! imu Ro !! ! ! ad ! !! " " " ! A ! ! ! ! ! " !! " " !! " !!! ! " " " !!! ! !! ! "
" " " !! " A " ! " ! " ! "
! !!
!! A
B
! " " !!! ! ! !! "" !! ! ! " ! ! B !! ! ! ! ! ! !!! ! B !! ! ! ^_ W ! a a ihok !! i V a ! " lle ! y R oad ! ! " ! ! ^_ " ! ! ! "
! !! "
! " ! B !! !! " " " ! ! " " " !! ! ! !! ! B ^_ ! ! 52 ! ! e t " ! ! " o u R !! ! ! ! ! ! " ! " !!!
!! B !
egend
Council Boundary Indicative Turbine Layout Indicative Internal Road Design Electrical Balance of Plant Indicative Construction Areas CHWF Site ! 80M Turbine Layout 80M Internal Road Substations !(L Laydown Areas Turbine Corridor ! 90M Turbine Layout 90M Internal Road Optional Switching Station !(B Concrete Batching Plant Turbine Cluster (A-G) ! "J Electrical Switchgear Huts 100L Turbine Layout 100L Internal Road !(Q " Quarry Locations External Dwellings ! 110L Turbine Layout 110L Internal Road 220kV Internal Transmission Line Towers " Quarry and Crushing Fac CHWF Landowner Dwellings Internal Substation Access Road 220kV Internal Transmission Line Excess Fill Areas Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take Points ^_ Internal Road Water Course Crossings 33kV Overhead Internal Electrical Lines Water Storage Areas Transport Route 33kV Underground Interal Electrical Cables NtAtiitA " " "
" D
"
" " "
"
" D ! ! " ! ! " ! !! " " " ! " " " ! !! !! ! ! " !! ! ! ! ! !! ! ! ! ! !!
G ! ! " D ! ! " " ! !!! " ! !!
! ! ! D Da ! !! gg ! ! s ! R ! ! ! ! o ! ! ! a ! ! ! d !! ! ! ! !! ! """ ! ! " G !! !! ! ^_ ! !! ! ^_ ! ! ! ! !! ! ! ! !!! ! E ! 1^_ !!
!! ! G !! !
! !
! !! D ! ! ! !! ! ! ! !!! !! "
! ! M ! ar ing E i R !! "o G !! " ad ! ! ! ! !! ! !
!! ! !!! G ! " !
! ! " ! E ! ! ! ! ! " ! ! ! " ! ! ! " "" !!! W ! ! a ! ! ir ! ir i !!! R o
!! ! a G ! d !
! ! ! G " ! ! ! " " "
" "" "
Glendonald Road """ " "" " "
egend
Council Boundary Indicative Turbine Layout Indicative Internal Road Design Electrical Balance of Plant Indicative Construction Areas CHWF Site ! 80M Turbine Layout 80M Internal Road Substations !(L Laydown Areas Turbine Corridor ! 90M Turbine Layout 90M Internal Road Optional Switching Station !(B Concrete Batching Plant Turbine Cluster (A-G) ! "J Electrical Switchgear Huts 100L Turbine Layout 100L Internal Road !(Q " Quarry Locations External Dwellings ! 110L Turbine Layout 110L Internal Road 220kV Internal Transmission Line Towers " Quarry and Crushing Fac CHWF Landowner Dwellings Internal Substation Access Road 220kV Internal Transmission Line Excess Fill Areas Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take Points ^_ Internal Road Water Course Crossings 33kV Overhead Internal Electrical Lines Water Storage Areas Transport Route 33kV Underground Interal Electrical Cables NtAtiitA D C
! ! C ! ! ! ! ! ! ! ! ! !! ! !! !!! ! ! !! ! ! ! ! ! "
! ! ! ! !! C ! ! " " "
!! " !! " "
! ! !!
^_ ! C
! D C ! !! !!! ! !! !! !
! !!
!! " C
"
"
E "
!! !! " ! ! ! ! ! ! ! F ! ! ! ! "" ! " " ! ! !! !! ! !! ! ! " F !! ! " " E ! ! ! !! ! ! ! ! ! ! ! !! ! ! " ! ! ! ! ! ! " ! ! ! !! !! !! !! ! !
d " ! !
a ! E ! ! ! o ! ! !
R " !! ! F a ! !
w F
a ! !! n
a ! M ! ^_ ! ! ! !!! " " ! " !! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !!! !!
"" "^_ !! !! !!
" "
F F "
"
" " Tinui
" " "
" " " " "
egend
Council Boundary Indicative Turbine Layout Indicative Internal Road Design Electrical Balance of Plant Indicative Construction Areas CHWF Site ! 80M Turbine Layout 80M Internal Road Substations !(L Laydown Areas Turbine Corridor ! 90M Turbine Layout 90M Internal Road Optional Switching Station !(B Concrete Batching Plant Turbine Cluster (A-G) ! "J Electrical Switchgear Huts 100L Turbine Layout 100L Internal Road !(Q " Quarry Locations External Dwellings ! 110L Turbine Layout 110L Internal Road 220kV Internal Transmission Line Towers " Quarry and Crushing Fac CHWF Landowner Dwellings Internal Substation Access Road 220kV Internal Transmission Line Excess Fill Areas Internal Transmission Line Access Road Optional Internal Transmission Line Deviation !(W Water Take Points ^_ Internal Road Water Course Crossings 33kV Overhead Internal Electrical Lines Water Storage Areas Transport Route 33kV Underground Interal Electrical Cables NtAtiitA Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
1.2 Introduction to Genesis Energy 1.2.1 Background Genesis Energy was established as a State Owned Enterprise on 1 April 1999, following the Government’s split of the Electricity Corporation of New Zealand. Genesis Energy has a diverse portfolio of renewable and thermal electricity generation assets including hydro, thermal and wind generation plants, and is one of the largest electricity generators in the country, supplying an average of approximately 20% of electricity generation per year over the last five years.
Genesis Energy has generation assets with a combined nominal generation capacity of approximately 2,140MW. The generation assets currently comprise:
The Huntly Power Station, which is the largest thermal generation asset base in New Zealand, incorporating four coal fired units, an open cycle gas Turbine and a combined cycle gas Turbine unit.
Three hydro generation schemes, being the Tongariro Power Scheme (central North Island), Waikaremoana Hydro Scheme (Hawke’s Bay), and Tekapo A and B Hydro Stations (Canterbury).
The Hau Nui Wind Farm in southern Wairarapa.
Genesis Energy generates electricity for sale to the wholesale market and to meet the needs of its retail customers. Genesis Energy, and its subsidiary Energy Online, combined hold the largest share of the retail market at 43% (MED, 2011), and has a retail customer base of approximately 655,000 electricity and gas customers. Genesis Energy is also an equity partner in the Kupe joint venture, which owns the Kupe Gas Project in Taranaki.
1.2.2 Approach to Environmental Issues Genesis Energy operates under the State Owned Enterprises Act 1986 that, amongst other things, requires Genesis Energy to operate its assets in the same manner as a commercial business, and act as a good corporate citizen. To achieve this, Genesis Energy seeks to make the best use of the resources available to it, while working alongside its communities and looking after the environment in which it operates.
Genesis Energy’s approach to environmental management is expressed in a suite of “Environmental Values”. These values state the company’s intention and principles in relation to its overall environmental performance. Genesis Energy’s Environmental Values state the company will:
Act with integrity at all times.
Foster close relationships with the community and stakeholders, so that their views can be incorporated into the environmental decision-making processes.
Acknowledge that our activities affect both the environment and the communities within which we operate.
Introduction Section 1 – page 9
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Respect the role of tangata whenua as kaitiaki of the natural resources and taonga within their rohe.
Investigate to better understand the nature of the environmental effects – and share this information with the community and stakeholders.
Seek environmental improvements in all aspects of our business.
Genesis Energy understands that all aspects of its business can impact on the environment, and that in order to reduce that impact it must:
Identify those who have responsibility for environmental management.
Identify and document all environmental effects associated with its activities.
Identify environmental objectives and develop associated work programmes to address the environmental effects of the activities undertaken.
Regularly review how well the company environmental values are being implemented, whether objectives are being met and which areas require corrective action.
Report publicly on environmental performance.
To achieve these objectives, Genesis Energy operates an Environmental Management System (“EMS”) which utilises a number of different business systems to manage the company’s effects and requirements for environmental management across all Genesis Energy projects and operational sites. The EMS provides the necessary controls and instructions to achieve the company’s commitment to environmental excellence and requirement to comply with all environmental legislation. The EMS applies to all activities involving the use of natural and physical resources and the environment, from the conceptual stage of any project through to normal operational activities of Genesis Energy.
Genesis Energy also has a comprehensive whole of company Climate Change Strategy to address the company’s impact on climate change, both through its activities and emissions, and through the activities of customers and stakeholders. As part of this strategy, Genesis Energy is committed to developing renewable energy in New Zealand while contributing to New Zealand’s long-term energy supply, and international and national climate change obligations.
1.3 Resource Consent Requirements
This application seeks all necessary resource consents required from the Manawatu- Wanganui Regional Council (“MWRC”), Greater Wellington Regional Council (“GWRC”), Tararua District Council (“TDC”) and Masterton District Council (“MDC”), for the construction, operation, maintenance, replacement and refurbishment of the CHWF and associated infrastructure.
A full description of the resource consents required is provided in Part A of this document and a description of the relevant rules is provided in Section 8. Tables 1.1 to 1.4 summarise the resource consents sought from each council.
Introduction Section 1 – page 10
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 1.1: Summary of resource consents required from MWRC.
Consent Type Activity Activity Status Land disturbance, earthworks and vegetation Land use Discretionary clearance Upgrade of existing External Roads and Land use Discretionary construction of new roads Land use Work in streambeds (structures) Discretionary Damming and diversion of surface water and Water permit Discretionary groundwater Water permit Water take and use Discretionary Discharge permit Disposal of excess fill to land Discretionary Discharge permit Discharge contaminants to air Discretionary Discharge permit Discharge stormwater to land and water Discretionary Discharge stormwater and wash water to Discharge permit Discretionary land
Table 1.2: Summary of resource consents required from GWRC.
Consent Type Activity Activity Status Land disturbance, earthworks and vegetation Land use Restricted discretionary clearance Upgrade of existing External Roads and Land use Restricted discretionary construction of new roads Land use Work in streambeds (structures) Discretionary Land use Work in streambeds (reclamation) Discretionary Damming and diversion of surface water and Water permit Discretionary groundwater Water permit Water take and use Discretionary Discharge permit Disposal of excess fill to land Discretionary Discharge permit Discharge contaminants to air Discretionary Discharge permit Discharge stormwater to land and water Discretionary Discharge stormwater and wash water to Discharge permit Discretionary land
Table 1.3: Summary of resource consents required from TDC.
Consent Type Activity Activity Status Construction, operation, maintenance, Land use replacement and refurbishment of a wind Discretionary farm and associated structures*
* Genesis Energy was granted resource consent RM090034 in March 2009 for up to eight monitoring masts within the CHWF Site, and intends to relinquish this consent if these applications are granted.
Introduction Section 1 – page 11
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 1.4: Summary of resource consents required from MDC.
Consent Type Activity Activity Status Construction, operation, maintenance, Land use replacement and refurbishment of a wind Discretionary farm and associated structures.*
* Genesis Energy was granted resource consent 20090407 in April 2009 for up to eight monitoring masts within the CHWF Site and intends to relinquish this consent if these applications are granted.
Genesis Energy seeks resource consent for an unlimited period for all land use consents and for the Section 13 Regional Council reclamation consents. A duration of 35 years is sought for all other the regional council resource consents. A lapse period of 10 years is sought to enable the development of the CHWF, while a duration of 20 years is sought for construction related consents to provide for the implementation of the CWHF through a staged construction approach.
Genesis Energy also seeks that the land use consents be granted in the name of Genesis Energy in accordance with s134 of the RMA.
1.4 Land Ownership
The CHWF will be located on land covering a number of land titles under the ownership of various parties (referred to as “CHWF Landowners”) for which agreements have been entered into for the development of the CHWF, and Council Road Reserve. Table A1 of the resource consent applications provides the legal descriptions for the properties that comprise the CHWF Site. Copies of the relevant Certificates of Title are available upon request.
1.5 Written Approvals
Section 104(3)(a)(ii) of the RMA requires that when considering a resource consent application, a Consent Authority must not have regard to the effect on any person who has given RMA written approval to the application in accordance with section 95E of the RMA. For the CHWF resource consent applications RMA written approvals are being provided by CHWF Landowners and residents of all CHWF Landowner Dwellings, and by the owner and occupier of 161 Gandys Road (also known as Rakaunui Road). Effects on these properties are not considered further in this assessment.
1.6 Environmental Assessments Undertaken
A series of environmental assessments have been undertaken through the preliminary and project design phases of the CHWF development process. Through each phase, environmental values and engineering practicalities have been integrated to ensure that appropriate environmental outcomes are achieved.
The environmental assessments undertaken are provided in Volumes 3, 4 and 5 of this document, and include:
Introduction Section 1 – page 12
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Castle Hill Wind Farm – Electricity-Related Effects Assessment, Concept Consulting Group Limited, July 2011.
Castle Hill Wind Farm – Economic Impact Assessment, BERL Economics, July 2011.
Castle Hill Wind Farm – Recreation and Tourism Effects Assessment, Rob Greenway & Associates, July 2011.
Castle Hill Wind Farm – Landscape and Visual Effects Assessment, Boffa Miskell Ltd, July 2011.
Castle Hill Wind Farm – Noise Effects Assessment, Marshall Day Acoustics, July 2011.
Castle Hill Wind Farm – Transportation Effects Assessment, Traffic Design Group, July 2011.
Castle Hill Wind Farm – Shadow Flicker Effects Assessment, Boffa Miskell Ltd, July 2011.
Castle Hill Wind Farm – Water Supply Assessment, Pattle Delamore Partners Ltd, July 2011.
Castle Hill Wind Farm – Hydrology Effects Assessment, Pattle Delamore Partners Ltd, July 2011.
Castle Hill Wind Farm – Groundwater Effects Assessment, Pattle Delamore Partners Ltd, July 2011.
Castle Hill Wind Farm – Aquatic Ecology Effects Assessment, Ryder Consulting Limited, July 2011.
Castle Hill Wind Farm – Ecological Effects Assessment, Wildland Consultants, July 2011.
Castle Hill Wind Farm – Cultural Impact Assessment - Rangit ne o Wairarapa Inc, July 2011.
Castle Hill Wind Farm – Cultural Values Assessment - Rangit ne o Tamaki Nui A Rua, in preparation.
Castle Hill Wind Farm – Cultural Impact Assessment - Ngati Kahungunu ki Wairarapa, July 2011.
Castle Hill Wind Farm – Cultural Impact Assessment - Kahungunu ki Tamaki Nui a Rua, in preparation.
Castle Hill Wind Farm – Archaeological Effects Assessment, Clough and Associates Ltd, July 2011.
Introduction Section 1 – page 13
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Castle Hill Wind Farm – Radio Services Effects Assessment, Kordia, July 2011.
Castle Hill Wind Farm – Health Effects Assessment, Enviromedix Limited, June 2011.
1.7 Structure of this Report
This AEE comprises 10 sections (including this introduction) as follows:
Section 1 This introduction provides an overview of the CHWF project, introduces Genesis Energy (the applicant) and the company’s approach to environmental issues, outlines the resource consent requirements, land ownership, written approvals and sets out the structure of the report.
Section 2 Sets out the overall rationale for the project and outlines the development approach for selecting the CHWF Site.
Section 3 Provides a description of the environmental setting of the CHWF Site, including the social, cultural, physical and ecological setting.
Section 4 Describes the CHWF project in detail, including the CHWF development process, alternatives considered, key project components, construction process and site reinstatement. The approaches to be used for managing effects of the activity are also outlined.
Section 5 Provides an assessment of environmental effects associated with the CHWF, including socio-economic effects, and effects on landscape and visual, noise, traffic, surface water and groundwater resources, ecology, cultural effects, archaeology and heritage, shadow flicker and blade glint, radio-communication and telecommunications services, aviation and electric and magnetic fields.
Section 6 Sets out the proposed monitoring and mitigation that will be undertaken, and outlines the management plans for the project.
Section 7 Describes the consultation undertaken with relevant stakeholders, potentially affected parties and interest groups.
Section 8 Describes relevant RMA matters, and the district and regional planning framework for assessing the resource consent applications required for the CHWF.
Section 9 Provides a concluding statement in relation to the overall assessment of environmental effects.
Section 10 Provides a list of references.
Introduction Section 1 – page 14
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
2. PROJECT RATIONALE 2.1 Introduction
The provision of a secure and reliable electricity supply to New Zealanders is a constant challenge being faced by the electricity generation industry as a whole. Overall, as long-term demand for electricity continues to increase, additional electricity generation facilities need to be built. At the same time, there is a strong direction from central Government to provide more electricity generation from renewable sources. These key factors provide the overarching rationale for the CHWF.
2.2 Overview of the New Zealand Electricity Situation 2.2.1 Electricity Supply and Demand in New Zealand Electricity supply in New Zealand comes from both renewable and non-renewable sources. In 2010, renewable generation accounted for approximately 79% of total generation, and comprised: hydro (56%), geothermal (13%), wind (4%), and co- generation (6%) (MED, 2011). Non-renewable sources include gas (18%) and coal (3%), which make up the balance of electricity supply.
Residential electricity consumption accounts for approximately 34% of total demand, with commercial (24%) and basic metals (17%) being the other major consumers. The balance of electricity consumption in New Zealand is by primary industries, food processing, wood, pulp and paper processing/printing, and other industrial uses (25%). Almost 66% of electricity demand is based in the North Island, with Auckland and Northland consuming approximately 28% of the total electricity supplied. Figure 2.1 shows the breakdown of consumption by sector and by region in New Zealand in 2010.
Historically, electricity demand in New Zealand has generally increased by approximately 1.8% per annum over the last 15 years4 (MED, 2011), and despite trends towards more efficient use, electricity demand is forecast to continue growing, with up to 8,900 GWh per annum of new generation required by 2020.
Forecasting by the Electricity Authority and the Ministry of Economic Development (“MED”) predicts that demand for electricity will continue to grow, albeit at slightly lower rates than observed in the past, and that new sources of supply will be required (Concept Consulting, 2011). A number of new projects either are under construction or expected to commence construction soon. However, these projects are only expected to add around 230MW (capable of supplying approximately 1,700 GWh/year) of new generation by 2014. A range of other projects have resource consents, but no decisions to proceed have been made and many projects are on hold. There is a risk that many consented projects will not proceed at all as a result of economic factors or availability of fuel. There is a need for new generation projects to ensure that the combined supply meets the expectations for demand growth for this period and beyond.
4 Demand fell slightly in 2008 as a result of electricity savings (arising from a public conservation campaign during a period of extreme low hydro inflows) and fell again in 2009 following equipment failure at the Rio-Tinto Aluminum Smelter at Tiwai Point. However, demand rebounded relatively strongly in 2010.
Project Rationale Section 2 – page 15
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 2.1: Electricity consumption by sector and by region in 2010 (MED, 2011).
The annual energy contribution of the CHWF is expected to be between 1,500 GWh and 3,000 GWh per annum. A project the size of the CHWF will provide a significant contribution to meeting the additional requirements for generation, and will make a material contribution to meeting projected demand growth.
Genesis Energy considers that it is critical that the supply of electricity matches demand, and given the steady increase in demand, and shortage of committed generation projects, there is a need for more generation.
2.2.2 The Importance of a Secure Electricity Supply Electricity is an essential input for modern lifestyles, and for commercial and industrial activity. As illustrated in Figure 2.2, electricity generally accounts for a quarter of annual end-use energy consumption in New Zealand, second only to oil (which includes transportation fuels) among sources of delivered energy. Industrial, commercial and domestic activities are all dependent on electricity, including manufacturing, retail, health services, transportation, lighting, water supply and wastewater treatment and disposal. Accordingly, electricity plays a vital role in New Zealand society. As is highlighted during power outages (for example, during storm
Project Rationale Section 2 – page 16
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects events, accidents, maintenance requirements, or other emergency situations), a secure supply of electricity is critical for economic and social well-being.
600
500
400
300 PJ per annum 200
100
0
Oil Gas Coal Geothermal Direct Use Other Renewables Electricity
Figure 2.2: Total consumer energy in New Zealand (1990 – 2010) (MED, 2011).
2.2.3 Matters Affecting Future Supply Options Overall Policy Framework
Reducing greenhouse gases and sustainably meeting energy needs through the increased use of renewable energy have been cornerstone priorities for central Government over a number of years. This commitment to renewable energy is clearly established through:
The National Policy Statement for Renewable Electricity Generation 2011 which took effect in May 2011. The overarching objective of the National Policy Statement for Renewable Electricity Generation is:5
“To recognise the national significance of renewable electricity generation activities by providing for the development, operation, maintenance and upgrading of new and existing renewable electricity generation activities, such that the proportion of New Zealand’s electricity generated from renewable energy sources increases to a level that meets or exceeds the New Zealand Government’s national target for renewable electricity generation.”
5 New Zealand Government National Policy Statement for Renewable Electricity Generation 2011, pg 4.
Project Rationale Section 2 – page 17
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The 2003 Sustainable Development Programme of Action, of which a principal component is the development of additional renewable generation capacity.
The Resource Management (Energy and Climate Change) Amendment Act (2004), which recognises the importance of renewable energy to New Zealand’s climate change response, and requires that particular regard be given to its importance when making decisions under the RMA.
New Zealand has signed the United Nations Framework Convention on Climate Change (often referred to as the “Kyoto Protocol”) committing the country to reducing greenhouse gas emission levels. The Government has recently gazetted (31 March 2011) a 2050 target for greenhouse gas emissions to be 50% below the level they were at in 1990. This has implications for non-renewable electricity generation, particularly as the Emissions Trading Scheme (“ETS”) has increased the operating costs associated with thermal generation.
The Draft New Zealand Energy Efficiency and Conservation Strategy (MED, 2010), which identifies increasing renewable generation capacity as being central to addressing New Zealand’s main energy challenges. These challenges include, responding to the risks of climate change by reducing greenhouse gas emissions associated with the production and use of energy, and delivering clean, secure, affordable energy, while treating the environment responsibly. The 2010 draft is consistent with the Government's proposed primary statement of energy policy set out in the 2007 New Zealand Energy Strategy.
It is clear from this overall policy framework that a clear policy preference for renewable generation will remain in the foreseeable future. This is endorsed in the preamble to the National Policy Statement for Renewable Electricity Generation, which states:6
“In considering the risks and opportunities associated with various electricity futures, central government has reaffirmed the strategic target that 90 per cent of electricity generated in New Zealand should be derived from renewable energy sources by 2025 (based on delivered electricity in an average hydrological year) providing this does not affect security of supply.”
Local authorities are required to give effect to provisions for renewable energy generation in regional policy statements, and regional and district plans made under the RMA. A number of regional and local authorities (including MWRC, GWRC, TDC and MDC) have provided for renewable energy development and use within their own planning provisions. Renewable energy policy at the regional and local level in respect to the CHWF is addressed in Section 8 of this AEE.
6 New Zealand Government National Policy Statement for Renewable Electricity Generation 2011, pg 3.
Project Rationale Section 2 – page 18
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Generation Options
There is a range of possible generation options available to increase future electricity supply, including wind, hydro, gas-fired, geothermal, coal, and new generation options such as solar, wave and tidal.
New Zealand is recognised as having a world class wind resource, because of the country’s geographic position spanning the “Roaring Forties” latitudes (Concept Consulting, 2011). While wind generation has grown substantially in the last 15 years, it is still relatively new to New Zealand and makes up a small proportion of total electricity supply (just under 4% in 2010) (MED, 2011).
Over the last 15 years larger scale electricity generation developments in New Zealand have typically been gas-fired, however the outlook for gas supply in New Zealand has changed significantly, especially since gas production from the Maui gas field has declined.
For other options, such as hydroelectricity generation which currently provides the majority of New Zealand’s electricity supply, there is potential for further development, however, the opportunity for new large scale hydroelectricity projects is limited.
Some options, such as geothermal generation, can only occur at a commercial scale where significant geothermal resources are located, such as in close proximity to the North Island’s central plateau.
The technical performance of all generation types has improved, particularly so for some technologies. Over the last 10-15 years there have been major advances in gas- fired Turbines and wind Turbines, with sizeable efficiency, reliability and cost improvements being achieved. Meanwhile, it will be some time before emerging renewable generation options, such as utility scale solar, are commercially viable in New Zealand. Technologies that may have greater commercial potential in future include wave and tidal power, with resource consents having recently been granted for a tidal project in the Kaipara Harbour.
The CHWF Project
Genesis Energy operates a diverse portfolio of renewable and non-renewable electricity generation assets. In terms of future planning, Genesis Energy considers both renewable and non-renewable generation options are required to meet the increasing demand for electricity while contributing to security of supply. Genesis Energy is also committed to contributing to New Zealand’s climate change obligations. Taking into account electricity supply and demand requirements, security of supply, overall policy framework and generation options for meeting future requirements, wind generation is likely to form a more significant part of future electricity generation in New Zealand than it does now.
While the other generation options outlined above will play a role in providing electricity in New Zealand, the CHWF as proposed by Genesis Energy, will make a material contribution to meeting projected demand growth and to enabling the generation of 90% of electricity needs from renewable sources. The CHWF is consistent with the Government’s overall policy framework to secure energy supply with the development
Project Rationale Section 2 – page 19
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects of renewable electricity generation projects, and aligns with the Government’s policy towards reducing climate changing greenhouse gas emissions.
Currently, wind generation contributes less than 4% of national electricity generation. The CHWF will help reduce security of supply risks by providing further diversification in electricity generation supply.
2.3 Development Approach
Genesis Energy has used both traditional methods and advanced modelling techniques to identify potential wind farms sites around New Zealand, and as a result identified the area to the east of Pahiatua and Eketahuna as being suitable for wind farm development.
In selecting any site for further investigation and the development of a wind farm, several technical matters need to be considered. While every potential location for a wind farm has its unique challenges, it is generally accepted that a site which has the following general attributes will be a suitable candidate for wind generation at a commercial scale:
Availability of a good wind resource (typically an average wind speed greater than 8 m/s, preferably with low turbulence);
Availability of land suitable for the construction of Turbines;
Distant from large population centres;
Practical access for transporting equipment and materials to the site;
Ability to connect to the national grid; and
Avoids sensitive environmental areas such as outstanding natural features and landscapes, and protected areas.
Genesis Energy considered each of these matters in selecting the CHWF Site and the development of the CHWF project. Each matter is described further below.
2.3.1 Wind Resource Areas with wind speeds sufficient for commercial wind farm projects in New Zealand are found in a number of locations, including the Wellington and Wairarapa Regions, although the air turbulence at some sites means that they are less suited to Turbines than others. The CHWF Site was first identified by Genesis Energy in early 2008 as a result of a national site screening assessment using spatial modelling tools to identify likely areas of higher wind speeds, and where turbulence factors also favoured wind generation.
In 2008, an initial assessment of the area identified by the wind modelling work was undertaken, incorporating more specific desktop studies of wind modelling and terrain, along with site visits to assess the potential for development of a wind farm in the area.
Project Rationale Section 2 – page 20
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
This initial desktop study led to implementation of a more detailed wind monitoring assessment of the Site commencing in 2009.
The preliminary assessment for the CHWF project was supported by wind monitoring across the Site using data from six 80 m monitoring masts associated recording equipment installed across the Site by Genesis Energy in 2009 (see Figure 1.2) and Light Detection and Ranging (“LiDAR”) surveys (a ground based method of wind monitoring that can be correlated with the monitoring mast data). The wind measurements have been used to understand site specific wind conditions. Subsequent modeling and analysis has enabled identification of potential Turbine models and areas for Turbine placement, as well as an estimation of potential net energy production.
A large proportion of the proposed Turbine sites have an average wind speed of more than 9 m/s, and some over 10 m/s, meaning that the wind resource across the Site arguably represents one of the best wind energy resources in the world for wind energy generation. The wind speed and conditions at the CHWF Site predominantly fit within International Electrotechnical Commission (“IEC”) Class IA parameters7.
2.3.2 Suitable Land Availability The CHWF Site consists of a series of predominantly north-west facing ridgelines, suitably aligned to the wind resource. The landforms are elevated, but not dominant, over the surrounding area.
Overall, the topography of the area allows for practical access to be developed for construction purposes, and is suitable for Turbine placement. Some geotechnical features, such as localised land instability, were identified in preliminary assessment work and have been incorporated into technical studies and design work. These features of the Site can be readily managed through appropriate engineering design and construction techniques.
2.3.3 Distance from Large Population Centres The CHWF Site is located in a remote area that is relatively sparsely populated. The surrounding area is rural in nature, comprising land used for primary production. There are no large population centres located close to the Site. Masterton (population 18,000), Pahiatua (population 2,600) and Eketahuna (population 460) are the larger townships located within 30 km of the CHWF Site (see Figure 1.1). Six small rural settlements are located in or around the Site, including, Tinui, Pongaroa, Makuri, Alfredton, Tiraumea, and Bideford. Combined, these small rural settlements have a population base of approximately 500 people (Statistics New Zealand, 2006).
2.3.4 Accessibility The Turbine components to be used for the CHWF (i.e. blades, tower sections and nacelle) are currently manufactured overseas and will need to be shipped to New Zealand. A suitable OW/OD Route has been identified to transport these components from the Port of Napier, for the most part via a major arterial route (State Highway 2
7 The IEC identifies a range of wind Turbine classes based on the wind resource, with Class IA being the highest wind speed class.
Project Rationale Section 2 – page 21
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
(“SH2”)) to the Site, while routes from other ports may also be suitable. Other External Roads in the vicinity of the CHWF are suitable for Site access for Heavy Commercial Vehicles (“HCV’s”) and other construction traffic, although may require some upgrading (such as curve straightening, widening or sealing).
Internal Roads on private land will also be required to access the Turbine locations within the Site. Where possible, existing farm access tracks will be used, although such tracks will need to be upgraded (including widening, sealing and/or strengthening in some places), to enable transportation of the Turbine components to the required locations within the Site.
Overall, appropriate access to the CHWF Site can be achieved in a relatively straightforward manner. Section 4.3.5 of this document provides specific detail relating to Site access.
2.3.5 Ability to Connect to the National Grid The electricity generated by the CHWF can be connected to the national grid at an appropriate location. A 220kV External Transmission Line, potentially up to 70 km long, is required for this connection. It is likely that the CHWF will connect to the national grid at the Transpower 220kV line near Bunnythorpe, although the details of the External Transmission Line have not yet been finalised and are subject to discussions with Transpower. This connection feeds electricity into the central North Island region.
2.3.6 Avoidance of Sensitive Environmental Areas The CHWF Site and immediate surrounds are not identified in the GWRC, MWRC, TDC or MDC planning documents as being within or part of an outstanding natural feature or landscape. The nearest identified outstanding natural feature or landscape to the Site is the Puketoi Range in the Tararua District. The skyline of the Puketoi Range when viewed from the west has been identified as the key visual/scenic characteristic of this range. Tinui Taipos, which is located some 7.5 km to the south of the CHWF Site, is also identified as an outstanding natural feature in the Combined Wairarapa District Plan 2011 (“Combined Plan”).
Most of the CHWF Site is covered with exotic pasture used for pastoral farming, although there is some remnant indigenous vegetation at the Site. There are five DOC (“DOC”) administered reserves located within 2 km of the CHWF Site, and 19 Queen Elizabeth II (“QEII”) Open Space covenants located within or close to the CHWF Site. These areas are not located within the construction area for the CHWF and will continue to be avoided through careful project design.8 Further description of the CHWF design process is provided in Section 4 of this document.
2.4 Summary
There is a clear need for additional generation capacity in New Zealand. The need is particularly acute for capacity of the kind that is renewable, not impacted by
8 A survey anomaly has been identified at QEII covenant (5/07/635) on Castle Hill Road. This is currently being resolved between Genesis Energy, QEII and MDC.
Project Rationale Section 2 – page 22
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects hydrological conditions, is not dependent on the availability of additional gas supplies, does not have high greenhouse gas emissions, and contributes to a secure supply through diversification of generation plant. Development of wind generation options is ideally suited to meet these requirements. The CHWF clearly falls within this framework and will provide a material contribution to meeting projected demand growth.
The excellent wind resource available at the CHWF Site, in combination with suitable topography for access and construction purposes, location in a remote area that is relative sparsely populated, ability to connect to the national grid, and the relative scarcity of environmentally sensitive sites within, or in close proximity to the Site, means that the CHWF Site provides an appropriate opportunity for development of a wind farm. This is supported by environmental assessments indicating no significant impediments to the granting of resource consents (detailed in Section 5 of this document). Overall, the CHWF Site is an appropriate location for a wind farm.
Project Rationale Section 2 – page 23
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
3. ENVIRONMENTAL SETTING
This section of the AEE sets out the background environmental setting of the CHWF. The local environment is outlined in terms of the social, cultural, physical and ecological characteristics of the area. This describes the environmental context in which the actual, potential and cumulative effects that may occur as a result of the CHWF can be assessed. These effects are discussed in detail in Section 5 of this document.
3.1 Social Setting
The CHWF is located in the south-east of the Tararua District and the north-east of the Masterton District in the northern Wairarapa, within the Manawatu-Wanganui and Greater Wellington Regions respectively (see Figure 1.1). Tararua District has a population of 17,344 and Masterton District has a population of 22,822 (BERL, 2011). Both districts have relatively static populations. Over the last 10 years (2000 to 2010) the population in Masterton District has grown at 0.1% per annum whereas, in Tararua District, the population has declined by 0.5% per annum.
Masterton District comprises one large town (Masterton, population 18,000) which is the largest town in the Wairarapa, and a large rural area which stretches from the Tararua Ranges in the west to the Pacific Ocean in the east. Masterton is a service centre for the District’s agricultural sector, although other business, retail and population services are prevalent within the town. Masterton is the largest township located within 30 km of the CHWF Site.
Tararua District comprises a number of small urban settlements with Dannevirke (population 5,500) the main centre for the District. Other urban centres include Norsewood, Woodville, Pahiatua and Eketahuna. Pahiatua (population 2,600) and Eketahuna (population 460) are nearest to the CHWF Site, located approximately 20 km to the west on SH2 (see Figure 1.1) (Statistics New Zealand, 2006). These settlements are considered to be service centres for the wider agricultural sector, and include businesses associated with primary production, schools, healthcare facilities and wholesale/retail activity.
Both the Masterton and Tararua Districts are characterised by agriculture-based primary production, with the Primary sector accounting for almost a quarter of total employment across both Districts combined. More than two thirds of workers in the primary sector come from the Tararua District. Masterton District has a more balanced economy, comprising employment from a range of sectors. About 95% of Tararua District’s 400,000 ha is farmed, with sheep, beef and dairy the main types of farming. These represent 90% of all holdings and account for 99% of total stock units. Forestry is a growing industry with more than 13,000 ha planted in Pinus radiata, however pastoral farming continues to be the main economic activity.
The second largest sector for employment in the combined Tararua and Masterton Districts is wholesale and retail sector (21% of employment) followed by the manufacturing sector (9% of employment) (BERL, 2011). Accommodation, cafes and restaurants account for 4% of total employment.
The CHWF Site is located in a remote and relatively sparsely populated area of the Tararua and Masterton Districts. The Site and surrounding area is rural in nature with
Environmental Setting Section 3 – page 24
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects extensive pasture areas. The land has been significantly modified and is currently used for agricultural activities. The predominant land use is pastoral farming (sheep and cattle) while several forestry blocks (predominantly Pinus radiata) are located in the south of the Site (see Plate 3.1).
Plate 3.1: Forestry block of Pinus radiata and pastoral grass in the CHWF Site.
Farm dwellings and other associated farm buildings and structures are distributed within and around the CHWF Site (see Figure 3.1). Nearby rural settlements include Tiraumea (2 km to the north), Alfredton (9 km to the west), Bideford (5fivekm to the south), Tinui (9 km to the south-east), and Pongaroa (9 km to the north-east) (see Figure 1.2). These rural settlements mainly provide rural population-based services, including schools, community halls, public domains, churches, convenience stores and golf courses.
The coastline is located approximately 13 km to the east of the Site and includes a number of small settlements that comprise both permanent and holiday homes. The population in settlements such as Castlepoint and Akitio increase significantly over the summer holiday period due to holidaymakers.
The area surrounding the CHWF Site has relatively low use in respect to recreation and tourism activities, and is generally considered remote. A limited number of adventure operations have been established as destinations in themselves. The main tourism and recreational activities in the vicinity of the CHWF are small-scale, such as back-packers, gardens and motorcycle tours, and are often a diversification of farming activities.
Few destinations are associated with any specific landscape feature except Castlepoint, which is located over 15 km from the CHWF Site. There is no landscape setting that serves as a visitor attraction in itself.
Environmental Setting Section 3 – page 25
Legend CHWF Site " CHWF Landowner Dwellings " External Dwellings " """ " " Turbine Corridor "" "" " 2km from Turbine Corridor """ " " " " " " 5km from Turbine Corridor " "" "" " Indicative Internal Roads " " "" 209 " " "" " " " " " " 397 " " " " " "" " " " " " "" 249 247 "" " 252 248 "" """ " " 255 256 " " "" " "400 " 258 " " " " " " 190 " " " ""189 " 188 " " "" " " " " 396 " 263" 186 """ " "" "" "" " " " " 265 407 " " " " " " 402 " "" " " "" " "" " "" " " " "" 403 " " " " "" " 167 " " " "" 168 " " " " 170 171 " " " 409 408" " " 185 " " " " "" "" "" " " " " " " " " 380 "" " " "" " 391 " " " " " " 378 " " " "" 377 379 " " " " " 392 " " " " " " "" """ " "" " " "" " " " " " " " 321 "" " " " " " 361" """ 359" " " " " " " 358 360 """ 405 "" " " 362 " " " " " "" " " " " " " " " " "" " "" " "" " "" " " " " " " " "" " " " " """ " " "" " " " " " "" " " "" " " " " " " " """ "" " " " """ " " " " "
03691.5 km
Figure 3.1: Dwellings located within and near the CHWF Site. Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Radio-communication and Telecommunication
A number of radio-communication and telecommunication services operate in and around the CHWF Site, including broadcast analogue and digital television and radio, fixed radio linking, aeronautical RADAR, land mobile VHF, cellular services and licensed and unlicensed broadband wireless access services. Table 3.1 provides a summary of the types of services that operate in and around the CHWF Site.
Table 3.1: Radio-communication services operating in the CHWF area (Kordia, 2011).
Type of service Services present in and around the CHWF Site Analogue terrestrial Residential dwellings that may have analogue television are located television throughout, and in close proximity to, the Site. The total number of analogue television receptions is not known, and similar assessments have found that at least 50% of rural dwellings receive digital satellite services (e.g. Sky, Freeview or TiVO). Fixed radio linking There are numerous fixed radio link services operating within the general vicinity of the CHWF, although only four pass through the Site. Telecom New Zealand Ltd and Juken New Zealand Ltd hold licenses for links which pass through the Site. Wide area These include broadband wireless, cellular, and emergency services. coverage services Four licensed mobile repeater services are operating within the CHWF Site. RADAR and The nearest aeronautical radio service is 9 km southwest of the Site at Aeronautical Radio Rangitumau. The nearest aeronautical RADAR service is over 35 km northwest of the Site at Ballance. AM/FM broadcast AM/FM radio broadcasts are received throughout the Site and radio surrounding area.
Aviation
The nearest airports to the CHWF Site that provide scheduled international or domestic flight services are Palmerston North International Airport, located to the north of Palmerston North, and Masterton Airport (Hood Aerodrome) located to the south of Masterton. These airfields are located approximately 50 km and 25 km from the Site respectively.
Aerial topdressing is commonly used in the wider area for the application of fertiliser, given that the hilly terrain restricts the application by land-based methods to flatter areas. A number of private airstrips are scattered throughout the wider area, which are primarily used for topdressing operations.
3.2 Cultural Setting 3.2.1 Historical Background Ngati Kahungunu and Rangit ne are the two iwi who Genesis Energy understand hold mana whenua in the Wairarapa Region. In geographical terms, Ngati Kahungunu has the second largest tribal rohe in New Zealand, extending from the Wharerata Ranges
Environmental Setting Section 3 – page 27
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects in northern Hawke’s Bay down to Cape Palliser (the southern-most tip of the North Island)9.
Ngati Kahungunu is organised into six taiwhenua groupings, namely: Wairoa; Whanganui a Orutu; Heretaunga; Tamatea; Tamaki Nui A Rua and Wairarapa. Each taiwhenua is governed by local elected marae / hapu representatives. The CHWF Site falls within the Wairarapa and Tamaki Nui A Rua taiwhenua areas.
For Rangit ne, the Wairarapa forms part of a wider homeland that includes the Manawatu and Horowhenua Regions. There are four takiwa (branches) of Rangitaane based in the Manawatu, Tararua, Wairau and Wairarapa areas. Although the four takiwa are representative of the same tribe they all remain autonomous in their own areas and are distinct in the development of their respective hapu and areas of mana whenua. The land blocks which cover the majority of the CHWF Site are known as the Castlepoint blocks, and were once covered in lowland forest stretching from the Mangamauku River (an upper tributary of the Tukituki) to Kopuaranga, just north of Masterton and east to the Puketoi Range. This forest was known as Te Tapere-nui-a- Whatonga (Forty and Seventy Mile Bush) and was important to Rangit ne for spiritual and physical sustenance (Rangit ne o Wairarapa Inc, 2011). Today there is a small remnant of this forest left approximately 20 km to the west of the CHWF Site, known as Pukaha (Mount Bruce).
Rangit ne consider the area of Te-Tapere-nui-a-Whatonga is considered to be a site of significance as it was utilised it as a pataka (food store) and therefore was a vital part of Rangit ne existence. Many waahi tapu sites have been found by local farmers and from the writings of Keith Cairns (Rangit ne o Wairarapa Inc, 2011). These sites have been listed with the New Zealand Archaeological Association (“NZAA”) and are not located within or near the CWHF Site.
Consultation with Ngati Kahungunu and Rangit ne representatives has been undertaken by Genesis Energy (see Section 7.2.5), more specifically with the following:
Rangit ne o Wairarapa;
Ngati Kahungunu ki Wairarapa;
Rangit ne o Tamaki Nui A Rua; and
Kahungunu ki Tamaki Nui A Rua.
Cultural Impact Assessments (“CIA’s”) have been prepared by Rangit ne o Wairarapa and Ngati Kahungunu ki Wairarapa, and is currently being prepared by Kahungunu ki Tamaki Nui A Rua, while a Cultural Values Assessment (“CVA”) is being prepared by Rangit ne o Tamaki Nui A Rua. The two CIA’s and two letters provided by Kahungunu ki Tamaki Nui A Rua and Rangit ne o Tamaki Nui A Rua in respect to the CIA and CVA they are preparing respectively, are provided in Volume 4 (Section 4) of this document.
9 http://www.kahungunu.iwi.nz/index2.html
Environmental Setting Section 3 – page 28
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
3.2.2 Archaeology and Heritage Archaeological sites in the wider Wairarapa area are generally concentrated on the east coast, with small clusters of archaeological sites around the Akitio and Owahanga Rivers, and between the Mataikona River and Castlepoint, as shown in Figure 3.2.
Recorded archaeological sites are generally middens, earth ovens and potential habitation terraces, with a number of pa sites and occupation terraces located near river mouths. Other features that have historically been found in the coastal area include moa bones, charcoal, jewellery, fish hooks, stone tools and human remains, reflecting a mixture of permanent and seasonal settlement.
A detailed archaeological assessment of the CHWF Site has been undertaken by Clough and Associates (2011), including both a desktop analysis and field surveys. The Archaeological Effects Assessment is provided in Volume 4 (Section 5) of this document. The assessment did not purport to interpret the cultural significance of any sites; rather to identify the sites and describe their characteristics and features.
There is little recorded physical/archaeological evidence of Maori occupation inland (west) of the CHWF Site in the Wairarapa Valley between the Masterton and Pahiatua Basins, some 25 km from the CHWF Site. It is likely that the area was visited and used by Maori in the past to gather resources, or they may have travelled through the area en route to other areas, even though there is little surviving evidence of such activities. Evidence of late 19th century and early 20th century European logging and farming activities are more common elements in the inland hill country of the CHWF Site.
No known or recorded archaeological sites on the NZAA database are located within, or in the immediate vicinity of, the CHWF Site.
Clough and Associates (2011) reviewed background literature and archaeological reports relevant to the area, including a summary of the archaeology of the Wairarapa Region incorporating a number of unpublished sources (such as unconfirmed information obtained from landowners in the Wairarapa Valley in the 1960’s) (McFadgen, 2003). This unconfirmed information indicated two possible pa sites are located in and near the CHWF Site, as shown in Figure 3.3.
Environmental Setting Section 3 – page 29
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.2: Indicative map showing recorded archaeological sites around the CHWF Site.
Environmental Setting Section 3 – page 30
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.3: Location of potential pa sites in or near the CHWF.
The northern possible pa site is located approximately 2 km west and north of Turbine Cluster B and C respectively, and outside the Site. The southern possible pa site is located in the middle of Turbine Cluster E. A ground search of both potential pa sites did not locate any evidence of these features. In consultation with Ngati Kahungunu and Rangit ne (see Section 7.2.5), and as outlined in the two CIA’s completed, no evidence has been found in respect to these pa sites, or any other sites of cultural significance located within the CHWF Site. Most waahi tapu sites are situated close to sources of food along the coastline or beside rivers and streams (Rangit ne o Wairarapa Inc., 2011).
No other archaeological sites were identified during the field surveys.
Most heritage features in the area are located more than 5 km from the CHWF Site. Two historic woolsheds (Annedale Station Woolshed and the Manawa Station Woolshed) are identified as ‘Heritage Items’ in Appendix 1.7 of the Combined Plan. Annedale Station Woolshed is located on Annedale Road and Manawa Station Woolshed is on Manawa Road outside the south-eastern part of the CHWF Site (see Figure 3.4). Neither buildings are located near the Turbine Corridor or other CHWF infrastructure. Manawa Station Woolshed is on the OW/OD Route but will not be affected by OW/OD Vehicles during the construction of the CHWF. No other known historical features are located within or in close vicinity to the CHWF Site.
Environmental Setting Section 3 – page 31
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.4: Location of historic woolsheds between Turbine Cluster E and F.
3.3 Physical and Ecological Setting 3.3.1 General Site Characteristics As outlined in Section 3.1, the CHWF Site is located in a rural area characterised by undulating hill country, steep hills predisposed to erosion and a distinctive valley network that extends throughout the wider area. The hills follow a pronounced north- east/south-west alignment running parallel to the Tararua Range which is located approximately 40 km to the west of the Site.
The distant Tararua Range to the west, which forms part of the North Island axial ranges, along with the Puketoi and Waewaepa Ranges to the east, dominate the wider landscape. These visually prominent ranges are characterised by high elevations (between 700 – 900 m above sea level (“asl”)) and are relatively unmodified. The elevation of the CHWF Site is less prominent, being between 400 – 500 m asl. To the east, the coast is approximately 13 km from the CHWF Site at its closest point. The topography of the CHWF Site varies from broad pasture dominated hilltops with occasional stands of pine trees (see Plate 3.2) to narrow steep gully systems that dissect the Site and contain patches of remnant or regenerating indigenous vegetation.
Environmental Setting Section 3 – page 32
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Plate 3.2: Example of typical vegetation cover (pastoral grass) in the CHWF Site, with occasional stands of native vegetation and pine forest in the distance.
The area experiences warm summers and moderate winters, and droughts may occur in spring and summer. Average annual rainfall is 1,137 mm at the Castle Hill Road gauge (located between Turbine Clusters D and F), and 1,263 mm at the Alfredton gauge (west of the CHWF Site). Regional hydrological monitoring sites are shown in Figure B1 of Appendix B (Volume 2).
Six wind anemometer monitoring masts were erected by Genesis Energy across the Site in 2009 to measure wind speed and other meteorological conditions. As outlined in Section 2.3.1, monitoring of the wind resource using masts and LiDAR has confirmed that there is an excellent wind resource in most parts of the Site. Air temperatures recorded at the top of the monitoring masts are mild, ranging from -1.1°C to 26°C.
Geology
The two main groups of geological units in the CHWF area, as shown on Figures B2 and B3 of Appendix B (Volume 2), are:
Generally weak (soft) Tertiary age mudstone, siltstone and sandstone – this unit varies from massive mudstone/siltstone to well bedded sandstone and siltstone, with more competent sandstone and some fossiliferous sandstone and shell limestone beds.
Environmental Setting Section 3 – page 33
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Stronger greywacke-type rocks – this unit comprises fractured sandstone and alternating sandstone and siltstone, with locally fossiliferous mudstone. This occurs along the main north-south ridgeline in the south-west of the CHWF Site.
Alluvial valley-floor and terrace deposits being gravel dominated with minor to interbedded sand and silt are present but comprise a minor part of the geology of the Site. Highly permeable limestone rock is present outside the CHWF Site to the north- west, but within the CHWF Site no limestone deposits have been recorded during site investigations by Pattle Delamore Partners (“PDP”) (2011b). Any limestone that may be present will occur as minor beds and fossiliferous/calcareous rock within mudstone and sandstone dominated units.
The main soil types (top 1 m of soil) within the CHWF Site include:
Brown soils – relatively stable with a well developed particle structure, located across most of the Site; and
Pallic soils – weak structure with low permeability, occurs in the southern part of Turbine Cluster A, most of Turbine Cluster B, and small parts of Turbine Clusters C and D. Pallic soils are susceptible to erosion because of their high potential for slaking and dispersion.
These hill and steepland soils vary in depth and drought properties according to the parent material. They have low to moderate natural fertility, variable water holding capacity and can be prone to erosion.
The typical grain size of soils (sand, silt, clay or loam – a mix of all three) across the Site is shown in Figure B4 of Appendix B (Volume 2). Soils across the Site include:
Silt, or silt over sand – Turbine Cluster A and parts of Turbine Clusters B, C, D, E and G.
Loam, loam over sand - Turbine Cluster F and parts of Turbine Clusters C, D, E and G.
Loam over clay – covering parts of Turbine Clusters B and C.
The dominant forms of erosion across the Site are soil slippage (Turbine Clusters A, B and G) and earth flows (Turbine Clusters B, C, D and E), and to a lesser extent slumping (Turbine Cluster F) and tunnel gully erosion (parts of Turbine Clusters D, E and G). Erosion severity is “slight” over much of Turbine Clusters B, D, E and G, while there are areas of “negligible”, “moderate” and “severe” erosion severity in Turbine Clusters A, C, E and F.
The CHWF Site is an agricultural setting, therefore there is the possibility of old offal pits, sheep dip sites, rubbish pits, metals and other contaminants from pesticide/fertiliser use, spills of fuel or other contaminants from storage tanks, effluent pits, and/or asbestos in buried building materials being located within the Site. However, during the various environmental assessments and consultation with CHWF Landowners undertaken for this application, no evidence of contaminated land was identified.
Environmental Setting Section 3 – page 34
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
3.3.2 Landscape Landscape Context
As noted previously, the CHWF Site and immediate surrounds are not identified in the GWRC, MWRC, TDC or MDC planning documents as being within, or part of, an outstanding natural feature or landscape. The nearest outstanding landscape is the Puketoi Range in the Tararua District, located to the north-west of the CHWF Site.
The CHWF is located in an area of extensively faulted, tilted and uplifted hill country, that extends along the east coast of the lower North Island, from Hawke’s Bay in the north to Cape Palliser in the south. This hill country follows a pronounced north-east, south-west axis that parallels the Tararua and the Rimutaka Ranges to the west. The combination of rapid uplift of the underlying materials and softer rocks has resulted in a landscape characterised by shattered and often steep hills.
The CHWF is located on a mix of elevated hill country dissected by narrow steep gully systems subject to erosion (see Plate 3.3). The slopes are dominated by grazed pasture, with hilltops relatively bare of woody vegetation, except for smaller areas of exotic plantation forestry and limited remnant or regenerating native vegetation, as shown in Plate 3.4. Some common pest plant species such as gorse are also present. The hills provide a distant landscape backdrop from low elevation positions in the surrounding valleys.
The open and expansive rural character of the landscape contains a series of smaller, well defined landscapes associated with the valley network that extends throughout the area. In terms of rural character, the CHWF Site is a well managed rural working landscape typical of the northern Wairarapa hill country.
In order to place the CHWF in its wider landscape setting, landscapes defined in the Wairarapa Landscape Study were used to interpolate and extend the character areas into the adjoining Tararua District (Boffa Miskell, 2011a). In the context of the wider landscape setting defined in the Wairarapa Landscape Study10 (Boffa Miskell, 2010), the CHWF is located within an area exhibiting four different and distinctive landscape types (see Figure B5, Appendix B, Volume 2), including:
Ranges.
Hill country.
Lowlands and valleys.
Coastal hill country.
These landscape types are detailed further below. The CHWF is confined and contained exclusively within the inland hill country.
10 Currently being undertaken by GWRC, MDC, Carterton District Council and South Wairarapa District Council.
Environmental Setting Section 3 – page 35
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Plate 3.3: Elevated hill country with narrow steep gully slopes and grazed pasture across the CHWF Site from Rangitumau.
Plate 3.4: Grazed pasture on hilltops with remnants of indigenous vegetation in gullies (Waitawhiti Road).
Environmental Setting Section 3 – page 36
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Ranges
The Tararua Range is predominantly covered in native forest and forms part of the North Island axial ranges. Together with the Puketoi and Waewaepa Ranges to the east, these are distinctive and prominent landforms within the District. The ranges are relatively undeveloped or settled, with substantial areas of indigenous vegetation.
Hill Country
The hill country landscape type in which the CHWF is located, generally aligns north- east/south-west and extends 70 km from the northern end of the Puketoi Range to near Bideford in the south. The hills form the foothills of the Puketoi Range for about half their extent to the north. The southern end of the foothills separates the catchments of the Tararua and Masterton Districts. The hill country is higher in elevation than the adjoining valley and lowland hill systems to the north, west and east, ranging in height to between 200 m and 500 m asl. Hill country is characterised by a network of steep sided gullies and valleys, often containing remnant or regenerating native vegetation (see Plate 3.3). Pastoral farming is the dominant land use, although large areas of exotic forestry and smaller areas of regenerating native and exotic vegetation are also present in the southern part of the CHWF Site.
Lowlands and Valleys
This landscape type is characterised by flat valley floors enclosed by low hills. The elevation ranges between 150 m asl in the valley floors to 350 m asl at the hill tops. Grazed pasture dominates the slopes and hilltops that are relatively bare of trees (with the exception of woodlot and production forest areas). Within the flat valley floors pastoral activity is also evident as well as public roads, farmsteads, houses and small rural settlements (see Plate 3.5).
Coastal Hill Country
The steep, rugged, dissected coastal hills are a continuation of the coastal hills to the south on the Wairarapa coast, and run parallel to the coast separating the inland valley systems from the coast. Several inland catchments drain to the coast, via steep sided winding river valleys, with narrow river flood plains. Extensive grazing is the predominant land use within the coastal hill country, with some areas of exotic pine forest south of the TDC/MDC boundary.
Environmental Setting Section 3 – page 37
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Plate 3.5: Lowlands and valleys landscape type in the CHWF Site (Manawa Road).
3.3.3 Existing Noise Environment The CHWF Site is rural in character and does not have significant industrial noise sources. The noise environment is dominated by rural production activities and natural sounds typical of a rural environment, with some traffic noise from nearby roads.
The existing noise environment in the vicinity of the CHWF was established using the method recommended by New Zealand Standard 6808:2010 “Acoustics – Wind farm noise” (“NZS6808”), as detailed in the Noise Effects Assessment (Marshall Day Acoustics, 2011) provided in Volume 3 (Section 5) to this AEE. NZS6808 recognises that noise limits in respect to operational Turbines are dependent on the existing background noise environment, and therefore provides specific methods that reflect the ambient noise environment as a function of wind conditions.
In accordance with NZS6808, background sound level measurements were taken at “noise sensitive”11 locations where the sound level of the CHWF is predicted to exceed 35dBA sometimes under certain conditions. The locations where background noise measurements have been taken are shown on Figure 3.5. Noise predictions from several Turbine Layouts and associated Turbine models were used to define the 35dBA noise contour (discussed further in Section 5.4). Field measurements of background noise were taken at 10 minute intervals over several periods of two – three weeks each in 2010 (both day and night).
11 “Noise Sensitive Locations” are defined in NZS6808 as locations where noise sensitive activities occur, associated with a habitable space or education space in a building not on the wind farm site.
Environmental Setting Section 3 – page 38
Legend CHWF Site Turbine Corridor " CHWF Landowner Dwellings " External Dwellings 397 "
258 "
190 "
265 "
403 "
171 " 185 "
377 379 " "
"1024 Manawa Road
"153 Wairiri Road
02461 km
Figure 3.5: Location of background noise measurement sites. Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The background noise data has been correlated with estimated wind speed for the same period at the nearest indicative Turbine location. Examples of background noise measurements from four representative sites are shown in Figures 3.6 to 3.9.
y = 0.00022973x4 0.01322014x3 + 0.20813030x2 + 0.86459842x + 18.20248885 60 R² = 0.78507141
50
40
30
20 Monitored LA90 (10min) (dB) 10
0 0 5 10 15 20 25
Wind farm wind speed at hub height (m/s)
Figure 3.6: Background noise at External Dwelling X397.
The existing background noise level at higher wind speeds at residence X397 (see Figure 3.6) is dominated by wind noise in local and distant trees, and by occasional household activity and traffic on Rimu Road.
4 3 2 60 y = 0.00011118x 0.00309689x 0.07702823x + 3.70925894x + 10.00767257 R² = 0.74536235
50
40
30
20 Monitored LA90 (10min) (dB) 10
0 0 5 10 15 20 25
Wind farm wind speed at hub height (m/s)
Figure 3.7: Background noise at External Dwelling X185.
Environmental Setting Section 3 – page 40
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
As shown on Figure 3.7, the existing background noise level at X185 is dominated by wind noise in local and distant trees. Little farming activity noise was observed.
60 y = 0.00055434x4 0.02894140x3 + 0.50300188x2 1.83272995x + 24.84146632 R² = 0.66007859 50
40
30
20 Monitored LA90 (10min) (dB) 10
0 0 5 10 15 20 25
Wind farm wind speed at hub height (m/s)
Figure 3.8: Background noise at External Dwelling X377.
The existing background noise level at residence X377 (see Figure 3.8) is dominated by wind noise in local and distant trees at elevated wind speeds, and during daytime hours may include noise from farming activities. Logging operations in adjacent forestry land occurred during these measurements, and this activity commences early in the morning during the nominal night-time period.
60 y = 0.00037399x4 0.01994083x3 + 0.36383654x2 1.54656237x + 26.97650190 R² = 0.31759783 50
40
30
20 Monitored LA90 (10min) (dB) 10
0 0 5 10 15 20 25
Wind farm wind speed at hub height (m/s)
Figure 3.9: Background noise at 153 Wairiri Road.
Environmental Setting Section 3 – page 41
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The existing background noise level at 153 Wairiri Road (see Figure 3.9) is dominated by wind noise in local and distant trees, and potentially a very low level contribution from distant watercourses during the winter month when measurements were taken. During daytime hours farm activity noise, including stock and dogs, as well as birds contributed to the noise environment. Logging operations in adjacent forestry land occurred during these measurements, and this activity commences early in the morning during the nominal night-time period.
Overall, the existing environment of the CHWF Site is rural in character, with small settlements and no significant industrial activity. The background noise levels measured indicate a typical rural environment, with relatively low traffic noise at night, but generally experiencing elevated noise levels during the day from rural farm activities (including stock and dogs), wind noise through local and distant trees, and birds. At all times wind speed influences noise levels, with no areas significantly shielded from wind noise.
3.3.4 Roading and Traffic The location of the CHWF Site in the road network, External Road classifications, and the existing traffic environment is outlined below, and described in more detail in the Transportation Effects Assessment (Traffic Design Group (“TDG”) (2011)) provided in Volume 3 (Section 6) of this document.
Location in the Road Network
Turbines and other imported equipment are proposed to be transported to the CHWF Site from the Port of Napier along the OW/OD Route detailed in Section 4.3.1, although other ports have been assessed and are suitable. Napier is the closest suitable port to the CHWF and is connected to the Site by a major arterial route (State Highway 50(A) and then State Highway 2). The OW/OD Route then uses local roads to the CHWF Site. Construction traffic (such as vehicles for transporting dump trucks, bulldozers, excavators, loaders, and construction personnel) will utilise the OW/OD Route as well as the Construction Traffic Route to access the Site.
External Road Classification
External Roads are classified in the TDC and MDC within the road heirachy defined in the relevant District plans as follows:
Strategic or Primary arterials – state highways and major bypass routes, the backbone of the network, linking the Wairarapa with the rest of the country.
District arterials (MDC) and Secondary (District) Arterials (TDC) – key District roads of considerable importance to the local economy, linking communities within and between parts of the Districts.
Collector roads – roads or routes within or between population centres and activity areas that collect traffic from local roads and feed through to arterial routes.
Environmental Setting Section 3 – page 42
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Local roads – predominantly provide access to properties.
External Roads that will provide access for construction and operational traffic from their origin to the CHWF are classified as District / Secondary (District) Arterial, Collector Roads or Local Roads, as outlined in Table 3.2.
Table 3.2: External Road classifications.
District Road Name Classification Route 52 Secondary (District) Arterial Alfredton Road Secondary (District) Arterial Hamua Rongomai Road Local Pahiatua Road Secondary (District) Arterial Tararua Castle Hill Road Collector Kaitawa Road Collector Mangaone Valley Road Collector Waitawhiti Road Local Waihoki Valley Road Local Rakaunui Road / Gandys Road Local Rimu Road Local Ngarata Road Local Haunui Road Local Puketawa Road Local Daggs Road Local Wairiri Road Local Maringi Road Local Whangaehu Valley Road District Arterial Masterton Te Ore Ore Road District Arterial Te Ore Ore Bideford Road Collector Manawa Road Collector Masterton-Castle Point Road Secondary (District) Arterial Alfredton-Tinui Road Local
External Roads that will provide access to the CHWF Site have varying carriageway widths, as detailed in Table 3.3. The Secondary (District) Arterial and Collector roads are sealed two lane carriageways generally between 4 m to 6.5 m wide. Closer to the CHWF Site many of the External Roads become unsealed, more winding, with steeper grades and narrower carriageway widths.
Environmental Setting Section 3 – page 43
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.3: External Road dimensions in the vicinity of the CHWF Site.
Road Carriageway Widths (m) Length to External Road Name District Carriageway Site Typical Minimum Typical Access Maximum (km) Route 52 Tararua Sealed 26 (9.0) 4.2 6.6 5.7 - 5.8 Sealed / Rimu Road Tararua 4.3 3.0 4.5 3.0 – 3.5 Unsealed Pahiatua Road Tararua Sealed 1.0 5.1 7.5 5.1 – 7.0 Rakanui Road / Gandys Tararua Unsealed 1.35 3.0 3.9 3.0 – 3.2 Road Sealed / Castle Hill Road Tararua 14.5 3.3 6.0 4.0 - 5.0 Unsealed Sealed / Daggs Road Tararua 4.3 4.0 6.2 4.0 - 4.5 Unsealed Sealed / Daggs Road Masterton 2.0 4.0 4.4 4.0 - 4.4 Unsealed Alfredton Road Tararua Sealed 17.0 3.9 7.4 6.1 Sealed / Haunui Road Tararua 5.4 3.0 5.4 4.6 Unsealed Sealed / Waihoki Valley Road Tararua 2.0 3.2 5.4 3.2 Unsealed Sealed / Waitawhiti Road Tararua 11.6 3.6 6.0 4.8 Unsealed Kaitawa Road Tararua Sealed 5.3 5.1 6.6 5.7 Mangaone Valley Road Tararua Sealed 23.1 5.0 7.8 5.5 - 6.3 Ngarata Road Tararua Unsealed 2.8 4.0 6.0 4.0 – 5.0 Puketawa Road Tararua Unsealed 1.0 3.0 5.0 3.5 – 4.5 Sealed / Wairiri Road Masterton 8.6 4.0 4.5 4.0 Unsealed Maringi Road Masterton Unsealed 9.7 3.6 4.3 3.6 - 4.0 Whangaehu Valley Road Masterton Sealed 19.6 5.6 7.1 5.6 - 6.0 Sealed / Manawa Road Masterton 12.5 4.7 6.3 4.7 - 5.3 Unsealed Masterton-Castlepoint Masterton Sealed 41.6 4.0 7.3 6.5 Road Alfredton-Tinui Road Masterton Unsealed 12.5 4.0 4.8 4.0 Te Ore Ore Road Masterton Sealed 2.3 7.0 14.0 7.0 -14.0 Te Ore Ore Bideford Road Masterton Sealed 23.2 5.3 7.1 5.3 - 6.3
Traffic Activity External Roads
A range of uses and activities occur on External Roads, including:
Personal access and local resident travel;
School bus travel;
Environmental Setting Section 3 – page 44
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Stock movement along or across the carriageway;
Recreational walking and exercise (due to no footpaths);
Emergency vehicle access to farm properties;
Logging truck movements;
Tourist, campervan and touring motorcycle movements, particularly on Route 52;
Equestrian movements;
Seasonal variations such as stock sales and fertiliser supplies to farms; and
Specific events such as motorsport rallies and cycle touring.
Some of these events and activities, such as specific events, are generally planned and co-ordinated with the relevant local authority, while other activities are recurring (school bus travel) or variable (for example, tourist and stock movements). Logging and forestry activities occur sporadically throughout the year, similarly school bus travel, road closures, events and cycle activities are important local activities and are described further below.
Logging Truck Movements
A considerable area of exotic forest is located to the south-east of the CHWF Site. Forest harvesting is a year round activity, with peak periods driven by export demand. Castle Hill Road is a key transportation route in relation to logging truck movements. While logging trucks are known to move in both directions along Castle Hill Road, the most common approach involves empty trucks entering the Site from the west, collecting a load and travelling east to Masterton via the Masterton-Castlepoint Road.
Forecasting of logging activity in the Wellington Region (predominantly the eastern areas) shows a predicted three to four fold increase over the next 10 years. Accordingly, the number of logging trucks using External Roads near the CHWF Site is expected to increase.
School Bus Travel
A small, but important component of the overall daily traffic volumes on External Roads (including SH2) is school bus traffic and local resident trips connecting with the school bus. Typical pick-up times are 7.30 am to 9.00 am and drop-off times are between 2.30 pm and 4.30 pm. Closer to the CHWF Site a school bus service operates from Alfredton, along Daggs Road, Castle Hill Road and Route 52, and occasionally along other External Roads.
In addition to the school bus movements, school children often wait at the side of the road, or are delivered to a common access point on the bus routes to be collected. At these collection points there is often a collection of parents with their children parked on the road side. This can at times constrain access for the short duration of their stay.
Environmental Setting Section 3 – page 45
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Road Closures, Events and Cyclic Activities
Road closures due to Council and community organised events, such as cycle races, occur periodically in the area. Events which occur on the External Roads to the CHWF Site include motor vehicle road races (the “Dunlop Targa” and the National Rally Championship “Rally Wairarapa”), and the “Trust House Cycle Classic”. The Dunlop Targa and Rally Wairarapa events involve road closures around the CHWF Site.
In addition to these main events, trail rides and horse treks occur on an ad hoc basis, and traffic control is limited to advance warning signage.
Other cyclic activities relate to the farming operations in the CHWF area, and add seasonal traffic (truck) demands onto External Roads, such as stock movement along or across roadways, ram sales and mustering (November), lamb sales (February), and fertilising activities (autumn and spring).
Traffic Volumes on External Roads
State Highway traffic volumes are detailed in the Transportation Effects Assessment provided in Volume 3 (Section 6) of this document, and External Road traffic volumes are summarised below.
Table 3.4 summarises current traffic volumes (vehicles per day (“vpd”) and vehicles per hour (“vph”)) on External Roads to the CHWF Site (sourced from TDC and MDC records), and forecast traffic volumes for 2021 (based on projected growth rates for traffic in the NZTA Economic Evaluation Manual (“EMM”). As shown in Table 3.4, District roads such as Route 52, Alfredton Road, Castle Hill Road, Kaitawa Road, Te Ore Ore Road, Te Ore Ore Bideford Road, Masterton-Castlepoint Road and Whangaehu Valley Road, have average daily traffic flows greater than 100 vpd on sections closest to the State Highway network. All other External Roads generally carry flows under 100 vpd, with some of these roads being less than an equivalent two- lane road. Peak hour traffic volumes account for approximately 10% of daily traffic.
Forecasted traffic growth rates to 2021 for External Roads are based on EEM annual percentage arithmetic traffic growth rates for the Manawatu-Wanganui and Wellington Regions of 2%. If traffic volumes increase at a rate equivalent to those on the more urbanised arterials and State Highways, some links such as Te Ore Ore Road show some potential for a significant increase. However, construction traffic associated with the CHWF will not use this section of External Road, therefore the potential effects of traffic growth on External Roads is not relevant to the CHWF.
Traffic stream compositions obtained from NZTA, TDC and MDC show compositions vary throughout the day. Cars typically make up 75 – 85% of vehicle composition, while light commercial vehicles make up another 10%. HCV’s generally account for between 5 – 10% of the traffic mix. This is typical of other similar rural environments.
Environmental Setting Section 3 – page 46
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.4: Current and forecasted traffic volumes for External Roads near the CHWF Site.
Traffic Volume 2021 Last Forecasted Peak District Road Daily Count Traffic Hour (vpd) Year Volumes (vph) (vpd) Alfredton Road 40 – 490 4 – 49 2009 58 - 619 Castle Hill Road 40 – 150 4 – 15 2007 55 - 188 Daggs Road 30 – 40 3 – 4 2005 36 - 50 Tararua Kaitawa Road 320 – 550 32 – 55 2008 435 - 692 Mangaone Valley Road 50 – 200 5 – 20 2010 58 - 297 Route 52 65 – 300 7 – 30 2010 88 - 368 Waihoki Valley Road 10 – 30 1 – 3 2001 9 - 41 Wairiri Road 15 – 50 2 – 5 2005 19 - 65 Maringi Road 30 3 2005 10 - 30 Alfredton-Tinui Road 20 2 2005 10 - 19 Manawa Road 60 – 120 6 – 12 2006 117 - 156 Masterton-Castlepoint Masterton 130 – 2,000 13 – 200 2007 173 - 2411 Road Te Ore Ore Bideford 120 – 7,500 12 – 75 2006 506 - 1422 Road Te Ore Ore Road 3,000 – 7,600 30 – 76 2006 3,600 – 9,120 Whangaehu Valley Road 100 – 200 10 – 20 2004 120 - 240
Local Road Safety Data
The NZTA Crash Analysis System was used to assess the road safety history for the likely transport routes to the CHWF Site. The spatial distribution of intersection and mid-block crashes between Pahiatua and Masterton shows that the Masterton- Castlepoint Road has had the highest number (24) of crashes in the last five years. Other roads with comparatively notable crash records are Whangaehu Valley Road (five) and Alfredton Road (four).
All 24 crashes on Masterton-Castlepoint Road occurred on mid-block (between intersections) sections between Te Ore Ore Road and Manawa Road, with the principal factor being speeds too high for the conditions. Road environment condition was also cited as a contributing factor for a high proportion of the crashes, with 88% of injury crashes being single vehicle crashes.
The five crashes on Whangaehu Valley Road occurred on mid-block sections and four of the five were associated with turning manoeuvres. This road is typically a higher speed section of road and is windy in some parts. All crashes on Alfredton Road were single vehicle crashes relating to the road environment condition.
Environmental Setting Section 3 – page 47
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Overall, the safety data shows that both individual driver behaviour and road environment conditions are contributing factors to accidents that have occurred on External Roads in the area.
3.3.5 Surface Water Resources The hydrology of the CHWF Site is detailed in the Water Supply Assessment (PDP 2011(c)) and the Hydrology Effects Assessment (PDP 2011(b)) (Volume 3, Sections 7 and 8 respectively). The aquatic environment is detailed in the Aquatic Ecology Effects Assessment (Ryder Consulting 2011) provided in Volume 4 (Section 2) of this document. These assessments are summarised below.
Hydrology
The CHWF Site is primarily located within the Upper Tiraumea and Owahanga Catchments to the north, and the Tauweru and Whareama Catchments to the south, as shown in Figure B6 of Appendix B (Volume 2). A small part of the Site is located within the Mataikona Catchment in the east.
Watercourses generally begin as small intermittent streams in the upper portions of the CHWF Site and drain hill gullies. In valley floors and low-lying areas near the road network, smaller streams combine to form larger streams and rivers, which mostly have permanent flow. Three of the main rivers drain in an easterly direction (Owahanga River, Mataikona River and Whareama River), while the Tiraumea River and the Ihuraua River (including the Te Hoe Stream tributary) drain to the north and west (see Figure B1, Appendix B, Volume 2). The Tauweru River originates in the middle of the Site and drains to the south-west, eventually entering the Ruamahanga River upstream of Martinborough. The numerous small watercourses within the Site are mostly unfenced from stock, and some have been dammed or ponded to form stock water ponds and provide water in dry periods, as shown in Plate 3.6.
Natural wetlands at the Site are small and degraded, with little or no indigenous wetland vegetation. A total of five natural wetlands were observed at the Site, but none will be affected by the development and are therefore not discussed further in this document.
Stream flow gauging was undertaken by PDP (2011(c)) in December 2010 to obtain an indication of flow in different streams across the Site and to broadly identify potential water abstraction sites during the construction of the CHWF. Rainfall at the Castle Hill Rd gauge in the month preceding the gauging was low (second lowest rainfall for November on record). Stream flow gauging results found:
Flows of about 40 L/s in the Tiraumea River at Haunui Rd.
Flows in the Te Hoe Stream Catchment were less than 3 L/s at Ngarata Rd, but increased downstream as the catchment received more flow from tertiary sandstone/mudstone areas rather than greywacke.
Flows within the Whareama Catchment above Tinui township were greater in the Tinui River than the Whareama River.
Environmental Setting Section 3 – page 48
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Plate 3.6: Stock pond within the CHWF Site formed by blocking a small tributary in the headwaters of the Tiraumea Stream.
Further gauging was undertaken in March 2011. The flow at the Ngaturi gauge was approximately 2.6 m3/s during the gauging (compared to a Mean Annual Low Flow (“MALF”) of 2.38 m3/s). The second round of gauging identified the following:
About 90% of flow at Ngaturi during the gauging came from the Makuri sub- catchment (Makuri River was approximately 2.33 m3/s).
The upper Tiraumea had higher flow than the Ihuraua/Te Hoe (flows at the confluence of the Ihuraua and the Tiraumea were 11 L/s and 167 L/s respectively and flows further up the Tiraumea at Haunui Rd were about 30 L/s).
Flows within the Te Hoe Stream were small (negligible flow at Ngarata Rd, and 4 L/s at Route 52).
Flows in the upper part of the Tauweru were about 11 L/s, but were approximately the same downstream at Mangareia Rd.
There was no significant flow in the upper parts of the Ihuraua or Mangareia and a small amount of flow (approximately 5 - 10 L/s) in the Mangaiti Stream.
The 4 L/s flow at Te Hoe Stream at Route 52 is less than the calculated MALF of 8.9 L/s at Alfredton (and also the MALFs for the Tiraumea at Haunui Rd and Ihuraua confluence). Inspection of the Te Hoe synthetic flow record generated by MWRC indicated that there were a number of occasions when the estimated flow was less than the MALF - the second gauging is therefore consistent with the synthetic record. Review of the record also identified that the summer of 2007/2008 represented one of
Environmental Setting Section 3 – page 49
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects the lowest – this is used as an example of potential effects of the proposed water abstraction discussed in Section 5.6.2.
A third round of gauging was undertaken in April 2011 (following rainfall of approximately 40 mm on the 22 and 23 March 2011). No rainfall had occurred for five days prior to the gauging. Flows at all sites had increased since the March 2011 gauging, with flows from tertiary mudstone catchments increasingly proportionally more.
Stream baseflows are limited by low seepage rates from groundwater resources. Specific discharge rates range from as low as 0.04 L/s/km2 (for the Te Hoe Stream) to 0.8 L/s/km2 (for the Tiraumea Stream just above the confluence with the Ihuraua River) in March 2011 (PDP, 2011b).
Information obtained from National Institute of Water and Atmosphere’s (“NIWA”) New Zealand wide GIS model of annual suspended sediment yields across the Site is summarised in Figure B7 of Appendix B (Volume 2). As shown in Figure B7, most of the Turbine Corridor within Turbine Clusters C, E, G and parts of Turbine Clusters D and A has suspended sediment yields of 10 – 500 t/km2/year. Most of Turbine Cluster B has yields of 500 – 2000 t/km2/year, while Turbine Cluster F and the northern part of Turbine Cluster D have yields of 2000 – 5000 t/km2/year. It is noted that the Wairarapa has some of the highest sediment yields in the country. As a comparison, the flatter parts of the Auckland Region have yields of 10 - 50 t/km2/year and the Hunua Ranges 200 – 500 t/km2/year.
Domestic water within the Site is generally sourced from rainwater tanks and springs, while stock water is supplied primarily from stock water ponds or the occasional stream take. No recorded consented surface water takes occur within 5 km of the Turbine Corridor in the MWRC area, while two consented water takes occur within about 12 km of the Site. Two consented takes occur approximately 3 km east of Cluster F in GWRC jurisdiction (PDP, 2011b).
The Operative and Proposed Tararua District Plan (“Operative TDP” and “Proposed TDP”) identify rivers as regionally significant natural features and/or are protected by water conservation notices. None of these rivers are located within the CHWF Site.
Appendix 1.9 of the Combined Plan identifies significant water bodies in the Masterton District that includes reaches of the Tauweru River (downstream of the Tauweru Bridge) and the Whareama River (seaward side of the Coastal Marine Area boundary). Both of these reaches are over 20 km downstream of the CHWF Site.
Appendix 1 of the Proposed Wellington Regional Policy Statement (“Proposed WRPS”) (2010) identifies the following rivers and lakes with reaches in the CHWF Site to have the following values requiring protection:
Ruamahanga River below, and including, the Kopuaranga confluence - habitat for six or more indigenous fish species.
Tauweru River - habitat for six or more12 indigenous fish species.
12 Records for only five indigenous fish species.
Environmental Setting Section 3 – page 50
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Whareama River Catchment - habitat for threatened indigenous fish species; habitat for six or more indigenous fish species; habitat for threatened indigenous fish species (one record of giant kokopu outside the CHWF Site); and inanga spawning habitat (outside of the CHWF Site).
Mataikona River - habitat for six or more indigenous fish species; and inanga spawning habitat (outside of the CHWF Site).
Rivers on the true left bank of the Mataikona River between the Pakowhai River and easting 2785345 and northing 6046718 - high percentage of indigenous vegetation cover (area of tidal influence outside the CHWF Site).
Rivers on the true right bank of the Mataikona River between easting 2784611 and northing 6046207 and the coast - high percentage of indigenous vegetation cover (area of tidal influence outside the CHWF Site).
While the Proposed WRPS identifies that the Tauweru, Whareama, and Mataikona Rivers meet one or more criteria relating to rivers with significant indigenous ecosystems, these features primarily relate to river reaches outside the CHWF Site.
The Regional Freshwater Plan for the Wellington Region (1999) (“Regional Freshwater Plan”) identifies:
Water Bodies with Nationally Threatened Indigenous Fish Recorded in the Catchment (Appendix 3).
Water Bodies with Important Trout Habitat (including spawning areas) - Water Quality to be Managed for Fishery and Fish Spawning Purposes (Appendix 4).
Water Bodies with Regionally Important Amenity and Recreational Values - Water Quality to be Managed for Contact Recreation Purposes (Appendix 5).
Water Bodies with Water Quality to be Managed for Water Supply Purposes (Appendix 6).
Water Bodies with Water Quality Identified as Needing Enhancement (Appendix 7).
No waterways within the CHWF Site are identified in the above appendices of the Regional Freshwater Plan.
Within MWRC jurisdiction, the northern part of the CHWF Site is located within the Owha 1 and Mana 7a Management Zones of the MWRC Proposed One Plan (“One Plan”). Schedule D lists the values associated with the various water management. All watercourses within the CHWF Site are identified as having the values listed in Schedule AB of the One Plan, including life-supporting capacity, aesthetics, contact recreation, mauri, industrial abstraction, irrigation, stockwater, existing infrastructure and capacity to assimilate pollution. One watercourse (Tiraumea River from Alfredton to its source) within the CHWF Site is identified as having site/reach specific recreational values (Other Trout Fishery). This value indicates that the trout fishery is neither outstanding nor regionally significant.
Environmental Setting Section 3 – page 51
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Water Quality
Water quality monitoring was undertaken in watercourses at 27 sites in winter (June 2010) and 32 sites in summer (March 2011) within and downstream of the CHWF Site at the locations shown in Figure 3.10. Flow in the Tauweru River during the June 2010 sampling ranged from 7 – 18 cumecs, while during the March 2011 sampling was 0.3 – 0.7 cumecs, and at times was below the ‘low flow’ warning level of 0.4 cumecs on the GWRC flow website13.
Sites were chosen to be representative of habitats throughout the CHWF, and included several sites within most of the Turbine Clusters (see Figure 3.10). Topographical maps and CHWF layouts were overlain with a river environment classification (“REC”) system to identify where Internal Roads may cross watercourses, as detailed further in the COMR (Volume 1, Appendix A) and the Hydrology Effects Assessment (Volume 3, Section 8). Sampling sites included proposed watercourse crossing points and downstream sites (including outside the CHWF Site), and covered the range of aquatic habitats, from headwaters with minimal depth and flow, to downstream rivers. Survey methods are described in detail in the Aquatic Ecology Effects Assessment (Ryder Consulting 2011) provided in Volume 4 (Section 2) of this document.
The physical characteristics of the watercourses sampled are summarised in Table 3.5.
Fifteen sites were soft-bottomed streams, seven were hard-bottomed streams and 10 streams included sections of both soft and hard substrates. Overall, waterways were generally small and narrow, with width of streams ranging from 0.5 - 8 m (16 sites had a width of 3 m or less) during winter flows, and water depths ranging from <0.05 m (one site) to more than 1 m (nine sites had a water depth of <0.5 cm). During summer flows, some of the waterways that had been sampled during the winter were either completely dry, or consisted of disconnected pools. All other waterways had reduced flows.
Grass was the most commonly encountered riparian vegetation (17 sample sites), with ‘grass/indigenous trees’ (seven sites), ‘grass/exotic trees’ (three sites), ‘grass/indigenous trees/exotic trees’ (three sites), and ‘indigenous shrubs’ (two sites) also present. This reflects the predominantly pastoral land use in the area. Most (25) sites were unfenced. Slumping of the bank was noted for some of the waterways.
Survey sites in the Wellington Region were assessed against the relevant GWRC water quality guidelines. These guidelines are derived from the Australian and New Zealand Environment and Conservation Council (“ANZECC”), Agriculture and Resource Management Council of Australia and New Zealand (“ARMCANZ”) default trigger values for aquatic ecosystems. The ‘trigger values’ are intended to be compared with median values at a site, rather than one-off measurements, however they still provide a useful indication of the existing water quality in the CHWF area. Water quality results for the relevant management zones in the MWRC Region were assessed against the targets for those zones set out in Schedule D of the One Plan for the MWRC Region.
Water quality parameters measured in watercourses within and downstream of the CHWF Site are presented in Table 3.6. Overall, water quality is generally good when sampled during winter flow conditions, although it was lower in some watercourses during reduced flows in summer. Most parameters measured were within the relevant
13 http://www.gw.govt.nz/rivers-and-streams-2/
Environmental Setting Section 3 – page 52
Legend CHWF Site Turbine Cluster (A-G) Council Boundary Catchment Sampling Sites
3 A
4
5 6 1 29 2 B 28
8 30 9 7 10 11 14 13 2021 D C 32 31
15
2223
E F 2627 G 18 17 25 16 24
19
02461 km Figure 3.10: Water quality and aquatic biology sampling sites. Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.5: Physical characteristics of the watercourses sampled within and downstream of the CHWF Site (June 2010 and March 2011).
Sediment depth Dominant Elevation Width (m) Depth (cm) Site Catchment Watercourse Substrate (cm) riparian Fenced (m) June Mar June Mar June Mar vegetation 1 Owahanga River Waihoki Stream tributary 280 hard 0.5-1.5 0.1-1.0 5-50 1-50 8 1-17 grass/native trees no 2 Owahanga River Waihoki Stream 260 soft/hard 2-3 0.2-3 120 80 10 1-13 grass yes 3 Owahanga River Managatiti Stream 120 soft/hard 6-8 4-8 >100* 20->100* NM** 5->25* grass no 4 Tiraumea Stream Tiraumea Stream tributary one 300 soft 0.5-1 0.5-1 10-120 0-100 17 2-30 grass/native trees no 5 Tiraumea Stream Tiraumea Stream 194 soft 2-2.5 0.8-1.5 120 10-40 5 5-15 grass no 6 Tiraumea Stream Tiraumea Stream tributary two 270 soft/hard 1-2 20-2 15-100 5-80 5 5 grass no 7 Tiraumea Stream Waitawhiti Stream tributary one 272 soft 3-4 0 <5 0 5 grass no 8 Tiraumea Stream Waitawhiti Stream tributary two 260 soft 0.5-1.5 0.5-1.5 30->100 0->100 8 1-30 grass no 9 Tiraumea Stream Waitawhiti Stream 225 soft 1.5-4 0.5-4 60->100 20->100* 10 2-30 grass no 10 Ihuraua River Ponui Stream 160 soft/hard 3-4 1-4 50->100* 3-80 NM** 2-45 grass/exotic trees yes 11 Ihuraua River Te Hoe Stream tributary one 287 soft 0.5-1 0 20-30 0 15 grass no 12 Ihuraua River Te Hoe Stream tributary two 284 soft 0.5-1 0 10-40 0 5 grass no 13 Ihuraua River Te Hoe Stream tributary three 280 hard 2-4 0-2 10-50 3-40 4 9 grass/native trees no 14 Ihuraua River Te Hoe Stream 200 hard 3-4 0.2-3 10-40 3-44 4 4 grass no grass/native 15 Tauweru River Tauweru River middle 260 soft/hard 1.5-3.5 1-2.5 30->100* 7->100* 10 0-70 no trees/exotic trees 16 Tauweru River Tauweru River tributary 216 hard 0.5-1 0 5-20 0 8 grass/native trees no 17 Tauweru River Tauweru River downstream 200 hard 5-6 1.5-5 10-100 5-60 4 0-50 grass/native trees yes 18 Tauweru River Wainuiomapu Stream 180 hard 4-6 0.2-6 20-100 5-60 5 30 grass no 19 Tauweru River Managareia Stream 133 soft/hard 2-3 0.5-3 >100* >100* NM** 11 grass no
* Water depth exceeded 100cm and conditions did not allow maximum water depth to be measured safely. ** NM - not measured, the water depth was too great to allow sediment depth to be measured safely. *** Although not fenced stock access is limited by the steep sided banks. There is some evidence of stock access but is minimal.
Environmental Setting Section 3 – page 54
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.5: Physical characteristics of the watercourses sampled within and downstream of the CHWF Site (June 2010 and March 2011) (cont).
Sediment depth Elevation Width (m) Depth (cm) Dominant riparian Site Catchment Watercourse Substrate (cm) Fenced (m) vegetation June Mar June Mar June Mar 20 Whareama River Axehandle Stream tributary 277 soft 0.5-1.5 0 <5 0 20 grass no 21 Whareama River Axehandle Stream 222 hard 1-2 0 10-25 0 8 grass/exotic trees yes 22 Whareama River Whareama River tributary one 160 soft 1-1.5 0.1-1.5 15-50 1-31 15 20 grass/native trees no 23 Whareama River Whareama River tributary two 142 soft 0.5-1 0.2-1 5-20 1-40 10 30 grass/native trees no 24 Whareama River Whareama River tributary three 80 soft 1-3 1-3 50->100* 1->100* 5 10 grass yes 25 Whareama River Whareama River 79 soft/hard 3-5 1.5-4 >100* 7->100* 20 0-20 grass no 26 Whareama River Tinui River tributary 160 soft 1-3 1-3 20-200 0->100* 30 40 grass no 27 Whareama River Tinui River 140 soft 4-6 4-6 >100* >100* NM** 30 grass no Waitawhiti Stream tributary grass/native 28 Tiraumea Stream 327 soft - 0.1-1 - 1-20 - 0-70 no three shrub/exotic shrub grass/native 29 Tiraumea Stream Waitawhiti Stream upstream 331 soft - 0.1-1 - 1-120 - 0-25 no shrub/exotic shrub 30 Tiraumea Stream Waitawhiti Stream tributary four 226 soft/hard - 0.2-2 - 3-60 - 0-15 grass/exotic trees no 31 Tauweru River Tauweru River tributary two 271 soft/hard - 0.01-1 - 1-15 - 0-20 native shrub yes*** 32 Tauweru River Tauweru River upstream 270 soft/hard - 1-2 - 4-80 - 0-20 native shrub yes***
* Water depth exceeded 100cm and conditions did not allow maximum water depth to be measured safely. ** NM - not measured, the water depth was too great to allow sediment depth to be measured safely. *** Although not fenced stock access is limited by the steep sided banks. There is some evidence of stock access but is minimal.
Environmental Setting Section 3 – page 55
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
GWRC and MWRC water quality guidelines in winter however, guidelines were exceeded at some sites in summer.
In MWRC, water quality parameters in tributaries of the Owahanga River catchment were within the One Plan target levels in June 2010, with the exception of turbidity in the Mangatiti Stream. In March 2011, dissolved oxygen levels breached guideline levels at two sites. Clarity guidelines were not met at one of the three sites in March 2011. Dissolved oxygen saturation and pH levels at five sites in the Tiraumea Stream Catchment were all within the One Plan target levels in both June 2010 and March 2011. However, at one site in March 2011 dissolved oxygen levels were very low and breached guidelines. Clarity guidelines were not met at six of the eight sites sampled in March 2011. Streams in the Ihuraua River catchment were within the guidelines in June 2010, with the exception of the Te Hoe Stream tributary where pH levels were slightly outside the recommended range. This site and a second tributary site (site 12) were dry in March 2011. At the remaining three sites dissolved oxygen breached guideline levels.
Within GWRC, turbidity levels at all sites in the Tauweru River Catchment exceeded the guidance level of 5.6 NTU during the winter survey, however turbidity may have been elevated due to winter flow conditions at the time the samples were collected. During summer sampling, all sites but one (site 32), met the guideline turbidity level. Dissolved oxygen saturation and pH levels at all sites were within GWRC guideline levels in both June 2010 and March 2011, except at the Mangareia Stream (Site 19) where dissolved oxygen saturation was only 20% in March 2011. This low level was due to the minimal flow and the presence of aquatic plant mats, which can led to oxygen depletion. At all seven sites measured in the Whareama River Catchment, dissolved oxygen saturation and pH levels were within guideline levels in June 2010, however in March 2011, two sites were dry and dissolved oxygen was below guideline levels at all but one of the remaining sites. Conductivity measurements at most sites in the Whareama River were higher than those recorded in other catchments. Values at all sites exceeded 347μS/cm and ranged up to 877μS/cm in March 2011. High conductivity levels were also recorded for this catchment by GWRC in 2008 – 2009.
Aquatic Ecology at the Proposed Water Abstraction Points
As outlined in Section 1 and detailed further in Section 4.3.8, Genesis Energy proposes to abstract water during the construction period from four surface water abstraction points in reasonable proximity to the Site. The proposed water abstraction sites are Te Hoe Stream, Tiraumea Stream at Haunui Rd, Tiraumea River at the confluence with Ihuraua, and Tinui River at Taipo. The aquatic environment at each of these water take sites is outlined below.
Te Hoe Stream (WS1)
Te Hoe Stream is a tributary of Tiraumea Stream. The stream has unfenced grassed riparian areas at the proposed abstraction site. Aquatic communities were sampled in Te Hoe Stream approximately 1.5 km upstream of the proposed abstraction site in June 2010 and March 2011, and macroinvertebrate communities were found to be indicative of ‘fair’ to ‘excellent’ quality habitat. Water quality was good in June 2010, with high dissolved oxygen levels of 89%, and low conductivity (92S/cm), total suspended solids (<5g/m2) and turbidity levels (4.6NTU). In March 2001 there was.
Environmental Setting Section 3 – page 56
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.6: Water quality parameters in watercourses within and downstream of the CHWF Site (June 2010 and March 2011).
Total Temperature Dissolved Dissolved Conductivity Turbidity Clarity o suspended pH Site Catchment Watercourse ( C) oxygen (%) oxygen (mg/L) (S/cm) 2 (NTU) (m) solids (g/m ) June Mar June Mar June Mar June Mar June Mar June Mar June Mar Mar Manawatu Wanganui Region 1 Owahanga River Waihoki Stream tributary 6.5 14.2 86.7 61.5 10.66 6.30 135.1 260.5 <10 4 7.1 1.94 7.5 7.19 2.6 2 Owahanga River Waihoki Stream 7.5 16.3 81.3 20.9 9.72 2.17 121.5 280.8 <5 <5 7.9 5.62 7.52 7.15 0.7 3 Owahanga River Managatiti Stream 7.2 20.6 93.2 116.0 11.26 10.41 167.3 328.8 56 <3 49.7 1.52 8.04 8.59 1.6 Tiraumea Stream tributary 4 Tiraumea Stream 6.5 16.1 91.6 73.9 11.25 7.26 63 210.2 <5 <5 4.2 6.58 7.88 7.55 0.8 one 5 Tiraumea Stream Tiraumea Stream 7.0 17.0 94.2 86.5 11.44 8.37 114.4 296.2 39 <4 24.7 4.87 7.78 7.80 1.4 Tiraumea Stream tributary 6 Tiraumea Stream 7.8 15.7 90.7 72.6 10.78 7.20 105.8 325.9 <5 <3 4.5 2.02 7.74 7.89 2.0 two Waitawhiti Stream tributary 7 Tiraumea Stream ------one Waitawhiti Stream tributary 8 Tiraumea Stream 6.5 14.8 89.9 73.9 11.05 7.14 110.1 296.2 6 <5 10.2 1.88 7.34 7.75 0.8 two 9 Tiraumea Stream Waitawhiti Stream 7.5 17.2 94.8 76.2 11.36 7.34 130 345.4 9 8 9.2 2.07 7.64 7.67 1.0 10 Ihuraua River Ponui Stream 7.7 15.8 83.6 58.8 9.96 5.82 147.1 333.3 7 <3 9.4 1.23 7.52 7.36 1.9 Te Hoe Stream tributary 11 Ihuraua River 9.0 - 74.4 - 8.6 - 98.9 - 12 - 13.5 - 6.90 - - one Te Hoe Stream tributary 12 Ihuraua River 9.6 - 90.1 - 10.27 - 78.1 - 6 - 6.1 - 7.22 - - two 13 Ihuraua River Te Hoe Stream tributary 8.5 15.4 90.3 65.4 10.54 6.54 89.5 164.8 <5 5 8.1 2.37 7.40 7.01 - three 14 Ihuraua River Te Hoe Stream 7.1 18.8 89.2 66.7 10.79 6.20 91.9 314.9 <5 <3 4.6 0.44 7.69 7.17 6.1 Wellington Region 15 Tauweru River Tauweru River upstream 7.8 16.8 90 97 10.85 9.39 107.7 256.0 5 5 7.6 2.35 7.63 7.98 1.8 16 Tauweru River Tauweru River tributary 8.1 - 94 - 11.13 - 87 - 6 - 9.7 - 7.90 - - Tauweru River 17 Tauweru River 8 17.5 95.5 96.7 11.3 9.25 118.9 281.8 7 <3 8.6 0.95 7.90 8.03 2.2 downstream 18 Tauweru River Wainuiomapu Stream 8.8 21.9 92.5 133.0 10.74 11.72 100.6 295.7 8 <3 9.01 0.54 7.87 8.98 4.2
- Site not sampled either due to insufficient water flow or was a new site in March 2011 -- Exceed Council water quality guidelines
Environmental Setting Section 3 – page 57
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.6: Water quality parameters in watercourses within and downstream of the CHWF Site (June 2010 and March 2011) (cont.)
Total Temperature Dissolved Dissolved Conductivity Turbidity Clarity o suspended pH Site Catchment Watercourse ( C) oxygen (%) oxygen (mg/L) (S/cm) 2 (NTU) (m) solids (g/m ) June Mar June Mar June Mar June Mar June Mar June Mar June Mar Mar 19 Tauweru River Managareia Stream 8.1 15.7 91.9 20.0 10.84 1.99 131.5 219.8 14 <3 12.1 1.97 7.90 7.15 - Axehandle Stream 20 Whareama River ------tributary 21 Whareama River Axehandle Stream 7.8 - 89.2 - 10.64 - 114.7 - 11 - 12.8 - 8.04 - - Whareama River tributary 22 Whareama River 8 15.3 90.6 65.7 10.72 6.55 141.8 488.1 6 7 12.2 4.13 7.48 7.91 1.1 one Whareama River tributary 23 Whareama River 8.2 15.1 88.3 76.3 10.35 7.52 210 533 11 17 12.9 12.5 7.75 8.04 0.5 two Whareama River tributary 24 Whareama River 9.2 16.2 91.9 17.7 10.55 1.71 369.5 535 56 10 48.3 3.08 7.94 7.59 1.3 three 25 Whareama River Whareama River 7.9 17.6 91.9 65.3 10.92 6.26 292 877 138 <5 122.0 2.56 8.01 7.76 1.3 26 Whareama River Tinui River tributary 6.4 19.3 86.2 127.6 10.63 11.41 231 352.9 9 <3 11.0 2.78 7.90 8.05 - 27 Whareama River Tinui River 7.1 16.4 83.2 64.1 10.06 6.28 193.5 347.3 10 <3 11.6 2.18 7.72 7.65 1.2 Manawatu Wanganui Region Waitawhiti Stream tributary 28 Tiraumea Stream - 13.4 - 13.5 - 1.39 - 171.0 - 14 - 4.25 - 7.21 0.5 three Waitawhiti Stream 29 Tiraumea Stream - 15.6 - 71.0 - 7.14 - 203.2 - <3 - 2.25 - 7.39 1.0 upstream Waitawhiti Stream tributary 30 Tiraumea Stream - 20.5 - 118.7 - 10.69 - 286.9 - 8 - 2.42 - 8.66 2.0 four Wellington Region Tauweru River tributary 31 Tauweru River - 13.5 - 85.7 - 8.90 - 227.4 - 5 - 5.05 - 7.66 - two
32 Tauweru River Tauweru River upstream - 13.4 - 83.9 - 8.75 - 230.2 - 10 - 6.13 - 7.81 1.3
- Site not sampled either due to insufficient water flow or was a new site in March 2011 -- Exceed Council water quality guidelines
Environmental Setting Section 3 – page 58
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects minimal flow and dissolved oxygen saturation was lower (67%) and conductivity higher (315 S/cm). Cran’s and upland bully, shortfin eel, and freshwater crayfish have been recorded in the Te Hoe Stream Catchment
Tiraumea Stream at Haunui Road (WS3)
The proposed abstraction site is located in the upper reaches of Tiraumea Stream. Aquatic communities at this site were indicative of ‘poor’ to ‘fair’ quality habitat. The stream is not fenced and the dominant riparian vegetation is grass. Recent water quality monitoring in January 2011 indicates that Tiraumea Stream has high total suspended solids of 551 g/m2 and high turbidity levels of 280NTU. Shortfin eel, longfin eel and freshwater crayfish have been recorded at the proposed abstraction site, and Cran’s bully and brown trout have been recorded further downstream.
Tiraumea River at Confluence with Ihuraua (WSB)
At the proposed abstraction site, the Tiraumea River is soft-bottomed and the channel is unfenced, with exotic trees and grass dominating the riparian vegetation. In March 2011 the river had a low flow (167 L/s), however dissolved oxygen levels were good (87%). Water quality was similar to that at the Tiraumea Stream at Haunui Road site upstream, although conductivity was higher (370S/cm). At a higher flow (419 L/s) in April 2011 water quality was similar to March 2011, although water temperature had decreased (from 17 to 12oC) and turbidity increased (from 2.6 to 9.1NTU). Macroinvertebrate communities were not sampled at the site, however the habitat is similar to that at the Tiraumea Stream at Haunui Road site upstream and therefore are likely to be indicative of ‘poor’ to ‘fair’ quality habitat. Brown trout, Cran’s bully, longfin eel, shortfin eel, upland bully and freshwater crayfish have been recorded in the Tiraumea River Catchment.
Tinui River at Taipo (WS5)
The proposed abstraction site is located approximately 16 km upstream of the Whareama River confluence. The river at the site has a cobble and boulder dominated bed, although there are areas of fine sediment deposition within this. The river channel is unfenced with the dominant riparian vegetation composed of rank grass and exotic trees. Recent water quality monitoring in March 2011 indicated that the water temperature was moderately high (16ºC), dissolved oxygen levels were slightly low (70%), and conductivity was high (565 S/cm). Macroinvertebrate communities were sampled at the site in January 2011 and found to be indicative of ‘fair’ to ‘good’ habitat quality. In terms of other fauna, inanga, Cran’s bully, longfin and shortfin eel have been recorded in the vicinity of the proposed abstraction site.
Aquatic Ecology Within and Downstream of the CHWF Site
Periphyton
Many watercourses within the CHWF Site are soft-bottomed and not suitable for periphyton growth. Three of the four sites where periphyton biomass samples were taken had biomass less than the Ministry for the Environment (“MfE”) (2000)
Environmental Setting Section 3 – page 59
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects guidelines. At the fourth site biomass exceeded the standard by a considerable margin in March 2011. At most sites diatom mat algae rather than filamentous algae were dominant. Although visible periphyton cover was present at a greater number of sites in March 2011 than June 2010, cover was generally low with the greatest cover occurring in pools with very little flow.
Macroinvertebrates
Macroinvertebrates were sampled at each site, taxonomic richness (number of species present) was calculated and community health was assessed by determining the presence and abundance of pollution sensitive taxa Ephemeroptera (mayflies), Plecoptera (stone flies) and Trichoptera (caddis flies) (“EPT”). In addition, the Macroinvertebrate Community Index (“MCI”) (Stark 1985) and the Quantitative Macroinvertebrate Community Index (“QMCI”) (Stark 1993) or Semi-Quantitative Macroinvertebrate Community Index (“SQMCI”) values were calculated. The MCI, QMCI and SQMCI are biotic indices based on indicator scores assigned to each taxon that reflects their sensitivity to poor environmental conditions. The MCI is based on presence/absence data whilst the QMCI/SQMCI has an abundance component.
MCI scores range from 0 – 200, with low scores indicating poor water quality, while high scores indicate a healthy stream with excellent water quality. SQMCI and QMCI are variants of the MCI, with scores ranging from 1 – 10, where <4 indicates probable severe pollution, and >6 indicates clean water. The relationship of MCI, SQMCI and QMCI scores to water quality is shown in Table 3.7.
Table 3.7: Interpretation of MCI, SQMCI and QMCI index values from Stark (1993) (Quality) and Stark and Maxted (2004) (Water Quality).
Quality Water Quality MCI SQMCI/QMCI
Excellent Clean water >120 >6.0
Good Doubtful quality or possible mild pollution 100 – 119 5.0 – 6.0
Fair Probable moderate pollution 80 – 99 4.0 – 4.99
Poor Probable severe enrichment <80 <4.0
MWRC standards in the One Plan for macroinvertebrate communities in both the Owha 1 and Mana 7a Management Zones is an MCI score of greater than 100. There are no guidelines for the GWRC Region.
Macroinvertebrate community indices (SQMCI/QMCI) indicating ‘fair’ to ‘poor’ quality aquatic habitats were recorded at 19 sites sampled within or downstream of the CHWF during winter, and indices indicating ‘good’ to ‘excellent’ quality habitat at eight sites. Macroinvertebrate community indices were generally lower in summer, with most (73%) being indicative of ‘fair’ to ‘poor’ quality aquatic habitats.
Freshwater crayfish (koura) were detected in some of the streams draining the CHWF Site. Koura populations are regarded as undergoing gradual decline (Hitchmough et al. 2007).
Environmental Setting Section 3 – page 60
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The macroinvertebrate community in streams draining the CHWF Site is summarised below:
Owahanga River Catchment – taxonomic richness ranged from 14 – 20 taxa, with 31 – 58% of these pollution-sensitive EPT taxa in June 2010, reducing to 7 - 50% EPT taxa in March 2011. Community indices ranged from ‘poor’ to ‘fair’ quality habitat at two sites and were below (site 2) and just above (site 3) the MWRC guideline of 100, to ‘good’ to ‘excellent’ at the hard- bottomed Waihoki Stream tributary. Macroinvertebrate communities at all sites were dominated by Potamopyrgus snails in June 2010.
Tiraumea Stream sub-catchment to the Tiraumea River – taxonomic richness ranged from 5 – 21 taxa, with low EPT scores recorded at all but two sites (< 44%). SQMCI scores at most sites were indicative of ‘poor’ to ‘fair’ quality habitat and below the MWRC MCI guideline. Macroinvertebrate communities were generally dominated by either Potamopyrgus snails or Oligochaeta worms, although two of the new sites sampled in March 2011 were dominated by mayfly species, and were indicative of ‘good’ quality habitat and met the MWRC MCI guideline.
Ihuraua River sub-catchment to the Tiraumea River – taxonomic richness ranged from 5 – 22 taxa, with the lowest taxa recorded in Te Hoe Stream Tributary 1 (where five taxa were collected and none were EPT taxa). SQMCI/QCMI scores were mostly indicative of ’poor’ to ‘fair’ quality habitat and below the MWRC MCI guideline, with the exception of the Te Hoe Stream site (site 14), which was indicative of ‘excellent’ quality habitat in June 2010, however this had declined to ‘fair’ in March 2011. Macroinvertebrate communities at all five sites in March 2011 were dominated by Potamopyrgus snails or Oligochaete worms.
Tauweru River Catchment – three of the five sites in June 2011 had macroinvertebrate communities dominated by Deleatidium mayflies, however in March 2011 habitat quality had declined and only one site continued to be dominated by mayflies. Taxonomic richness ranged from 11 – 24 taxa, of which 0 – 54% were EPT taxa. Community indices at the mayfly dominated sites declined from being indicative of ‘good’ to ‘excellent’ habitat quality in June 2011, to being indicative of ‘poor’ to ‘good’ habitat quality in March 2011. Two additional sites were sampled in the headwaters of the catchment in March 2011 (Sites 31 and 32). Both had macroinvertebrate communities dominated by mayflies, and were indicative of ‘good’ to ‘excellent’ habitat quality.
Whareama River Catchment – taxonomic richness ranged from 7 – 16 taxa. Two of the eight sites (sites 21 and 22), sampled in the Whareama River catchment were dominated by Deleatidium mayflies in June 2010 and community indices at these sites were indicative of ‘good’ to ‘excellent’ quality habitat. However, habitat quality had declined to ‘poor’ at site 22 in March 2011, and site 21 was dry, as was its tributary (site 20). Community indices were indicative of ‘good’ quality habitat in both June 2010 and March 2011 at the Whareama River tributary two site. The remaining five sites had communities dominated by Potamopyrgus snails or Oligochaete worms, with communities indicative of ‘poor’ or ‘fair’ quality habitat.
Environmental Setting Section 3 – page 61
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Fish
Freshwater fish communities recorded within and immediately downstream of the CHWF Site were not diverse, with only seven species recorded. Six of these species are native and one introduced (brown trout). Of the six native species, only four species (Cran’s bully, longfin eel, shortfin eel and upland bully) were commonly recorded throughout the CHWF Site. The other two native species, common bully and inanga, were recorded less frequently.
Longfin eel and inanga have a conservation ranking of ‘declining’ under the DOC’s threat ranking system, whilst the other species are not regarded as threatened (Allibone et al. 2010). Inanga are diadromous (requiring access to the sea to complete their life cycle) so are less likely to be found in those streams in the CHWF Site that are a long distance from the sea and at higher altitudes. Longfin eel and shortfin eel are also diadromous, however they have superior climbing abilities and are known to penetrate further inland.
Four additional diadromous fish species now classified as ‘declining (redfin, torrentfish,, lamprey (‘data poor’), and giant k kopu (‘partial decline’) have been identified in the downstream reaches of the Owahanga, Mataikona and Whareama River Catchments according to the New Zealand Freshwater Fish Database. All records of these species were within 20 km of the east coast and at elevations of 20 m asl or lower. Some of these species, such as redfin bully, torrentfish and lamprey, are known to penetrate inland and may be present in watercourses within the CHWF Site. However, none were found during sampling and habitat for redfin bully and torrentfish is limited so it is likely that only lamprey could be present within the Site.
Several existing road culverts and some natural waterfalls in the CHWF Site would present a barrier to the upstream passage of some fish species.
Summary
Most watercourses within and downstream of the CHWF Site have no special features with respect to water quality and aquatic communities. This is not unexpected given the over-riding pattern of agricultural land use, general lack of riparian protection, and the steep and erosion-prone, soft-sedimentary land type, which typically result in modified water quality environments, including high levels of sediment run-off.
No watercourses within the CHWF Site are identified as regionally significant natural features and/or are protected by water conservation notices in the Operative or Proposed TDP, or Appendices to the Regional Freshwater Plan for the GWRC. Some rivers and lakes with reaches in the CHWF Site are identified in the Proposed WRPS as having values requiring protection, although most identified values are outside the CHWF Site.
Most watercourses are soft-bottomed, with active slumping and erosion of banks and sediment deposition in beds. All of the watercourses surveyed were flowing when sampled in June 2010, however during the March 2011 sampling, some were ephemeral, having dry channels or consisting of a series of unconnected pools during summer. Water quality was generally good when sampled during winter flow conditions, although it was lower in most watercourses during reduced flows in
Environmental Setting Section 3 – page 62
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects summer. Conductivity and turbidity levels were generally higher in larger, lower elevation watercourses than in smaller streams at higher elevations.
Macroinvertebrate communities were, in general, more diverse and of higher quality in the few hard-bottomed watercourses. Macroinvertebrate communities in soft-bottomed watercourses were generally indicative of ‘poor’ to ‘fair’ quality habitat. Fish communities were not diverse, with seven species recorded in the general area, and only four species commonly recorded. There is no angling opportunity in the headwaters of watercourses within the CHWF Site and relatively little opportunity in larger tributaries in the valley floors. Trout fishery in the general area has not been identified as either outstanding or regionally significant.
3.3.6 Groundwater Resources PDP (2011(a)) has assessed the groundwater resource in the CHWF area using stream baseflows and groundwater information (e.g. seepage distribution) obtained during a field survey in February 2011, shallow (<15 m deep) subsurface drilling (undertaken by Aurecon), and information received from CHWF Landowners on groundwater on their property (for example, spring locations and presence of bores). The Groundwater Effects Assessment is provided in Volume 4 (Section 1) of this document, and is summarised below and in Section 5.6.3.
There are no recorded drillholes or consented groundwater takes within 5 km of the Turbine Corridor in the MWRC Region. The nearest consented groundwater take in the GWRC Region is located approximately 3 km from the Turbine Corridor.
No CHWF Landowners have a functional groundwater bore on their property. A number of springs are located on CHWF Landowner properties throughout the CHWF Site (see Figure B2 of Appendix B, Volume 2) and some of these springs are used as a water supply source.
The springs are located in both Tertiary mudstone and sandstone, and greywacke rock types. Seepages are numerous, widespread and present at a full range of slope positions, from the ridge crest down to near the valley floor.
Most CHWF Landowners identified dams/ponds on their properties that provide water supply for stock drinking purposes. The dams/ponds are located in a variety of positions on the slope, ranging from near the ridge crest to near the valley bottom.
Depth to Groundwater
With the exception of one test-pit, no groundwater has been encountered in any of the subsurface drilling carried out by Aurecon. This is expected because the investigations have been relatively shallow (<20 m deep) and focussed on Turbine Foundations and aggregate resources which are typically in elevated locations, for example on ridgelines. The investigations have been located in both the Tertiary and greywacke rock types.
Groundwater was encountered at a depth of 2.5 m in silty sand in a test-pit in Turbine Cluster F, and probably indicates a perched aquifer at this location. The lack of measured groundwater level information available does not materially affect the findings of the PDP (2011(a)) assessment as the assessment focuses on the
Environmental Setting Section 3 – page 63
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects groundwater-surface water interaction part of the groundwater system, therefore depth to groundwater information based on hydrogeological principals are sufficient.
Groundwater Recharge and Discharge
Stream baseflow rates (flow after a prolonged dry period) in the CHWF Site are very low and indicate groundwater recharge rates of approximately 0.1 – 2% of rainfall. These rates are low in the spectrum of recharge rates but are generally consistent with what would be expected for the rock types present in the CHWF Site. Only a very small proportion of rainfall recharges groundwater, the vast majority runs over the surface into streams or is lost due to evapo-transpiration.
Groundwater Flow and Groundwater – Surface Water Interactions
The main rock types in the CHWF Site are the Tertiary rocks and greywacke, both of which are sufficiently fine grained, consolidated or cemented, that groundwater flow through the rock is limited to open cracks (joints). The hydraulic conductivity of the rocks is typically low because joints are generally not open, particularly at depth. The low hydraulic conductivity for the rock types is consistent with the low groundwater recharge values outlined above.
Even though the overall rockmass has low hydraulic conductivity, subtle variations form zones of preferred groundwater flow and zones of negligible groundwater flow. Zones in the rock where there is preferred groundwater flow include jointed sandstone (Tertiary and greywacke) and closely fractured zones near faults. Zones with negligible groundwater flow include Tertiary mudstone, sparsely jointed areas and fault zone clays.
Multi-layered groundwater systems are typical because both preferred groundwater flow zones and negligible flow zones are present in the rockmass. In these groundwater systems:
Only a portion of rainfall recharge infiltrates through the multi-layered rockmass to reach deep groundwater which feeds stream baseflow;
The remaining portion of rainfall recharge is forced to flow at shallow depth eventually discharging to the surface at mid-slope positions (where it evaporates); and
Seepages occur at a range of slope positions.
Overall, the available information indicates that some form of the multi-layered/multi- zoned groundwater system applies to the majority of catchments in the Study Area. The uniform groundwater system may apply to parts of catchments but is unlikely to apply to whole catchments due to geological variability.
3.3.7 Terrestrial Ecology The baseline ecological values of the CHWF Site have been assessed by Wildland Consultants (2011), including both a desktop analysis and field surveys. The
Environmental Setting Section 3 – page 64
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Ecological Effects Assessment is provided in Volume 4 (Section 3) of this document and is summarised below.
Ecological Context
The CHWF Site is located primarily within the Eastern Wairarapa Ecological District, which forms part of the Eastern Wairarapa Ecological Region. A small section in the north-west of the Site is located in the Puketoi Ecological District of the Pahiatua Ecological Region.
The Eastern Wairarapa Ecological District extends from the coastline to inland hill country that includes the steep-sided Taipo Hills. Most of the natural vegetation in the ecological district was cleared for farming in the 19th and early 20th Century. As a result, today most of the District is farmed with the other main land use being plantation forestry. Patches of remnant indigenous vegetation are dominated by manuka and/or kanuka cover. A small area of black beech forest is present. Hard beech occurs locally on Mt Rewa in Ngaumu Forest and at Castlepoint, small areas of podocarp forest, and more extensive areas of secondary forest without podocarps, beech species or tawa also occur within the District.
The Puketoi Ecological District is located inland and comprises low ranges and dissected hills mostly over 300 m asl. Most of this district is also farmed and hence vegetation is dominated by high-producing exotic grassland, with remnant indigenous vegetation comprising less than 10% cover in that district.
Vegetation and Habitat Types
Twenty-nine vegetation and habitat types have been identified at the Site (including External Roads). These include 19 indigenous habitat types and 10 exotic or human- made habitat types grouped within 12 broad vegetation and habitat structural classes as shown in Table 3.8. Small “natural wetlands with some indigenous vegetation” have been identified within the Site, but will not be affected by the development and are therefore not discussed further in this report. Vegetation types present within the Site and along External Roads are shown on the maps in the Ecology Effects Assessment in Volume 4 (Section 3) to this document.
Table 3.8 shows the relative extent and general distribution of each vegetation type. In relation to distribution within the Site, ‘widespread’ means that a type occurs widely throughout the Site (and/or in the vicinity of External Roads) while ‘local’ indicates that it occurs in only one or a few locations. Table 3.8 also shows the relative ecological value that has been assigned to each vegetation type.
Vascular Plant Species
A total of 209 vascular plant taxa - 141 indigenous and 68 exotic - have been recorded during the field surveys. The indigenous vascular plant assemblage recorded is not diverse, and is typical of the habitats surveyed, i.e. predominantly pasture with scattered grazed indigenous scrub and shrubland remnants. Most habitats are grazed by stock and browsing pest animals, which has degraded the indigenous vegetation remnants and reduced the diversity of indigenous plants.
Environmental Setting Section 3 – page 65
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Table 3.8: Vegetation types, relative ecological values, extent and distribution at the CHWF Site.
Vegetation Structural Class/ Ecological Indigeno Code Distribution Vegetation Type14 Value us Indigenous Forest High Yes Podocarp/broadleaved forest 1.2.1 High Local Yes Tawa forest 1.2.2 High Local Yes Kamahi forest 1.2.3 High Local Yes Mixed broadleaved forest 1.2.4 High Local Yes Manuka-kanuka forest 1.3 High Local Yes Indigenous Treeland High Yes Broadleaved treeland 2.2 High Local Yes Manuka-kanuka treeland 2.3 Moderate Local Yes Podocarp treeland 2.4 Moderate Local Yes Indigenous Scrub Moderate Yes Manuka-kanuka scrub 3.1 Moderate Widespread Yes Mixed broadleaved scrub 3.4 Moderate Widespread Yes Manuka-kanuka scrub mixed 3.5 Moderate Widespread Yes broadleaved scrub Indigenous Shrubland Yes Manuka-kanuka/pasture grass shrubland 4.1 Low Widespread Yes Manuka-kanuka shrubland 4.2 Low Local Yes tauhinu/pasture grass shrubland Tauhinu/pasture grass shrubland 4.3 Low Local Yes Mixed broadleaved shrubs/pasture grass 4.4 Low Widespread Yes shrubland Manuka-kanuka shrubland mixed 4.5 Low Widespread Yes broadleaved shrubland Rock Outcrops Yes Rock outcrops (indigenous) 5.1 High Local Yes Road cuttings (exotic) 5.2 Low Local No Wetland Yes Natural wetland with some indigenous 6.2 Moderate Local Yes species (indigenous) Stock ponds (artificial - exotic) 6.4 Negligible Widespread No Rivers Yes Rivers with indigenous riparian vegetation 7.1 High Local Yes (indigenous) Rivers without indigenous vegetation 7.2 Moderate Local No (exotic) Exotic Forest No Exotic forest/indigenous understory 8.1 Negligible Widespread No Exotic forest or shelter belts 8.2 Negligible Widespread No Exotic Scrub and Shrubland No Gorse-broom scrub 9.1 Negligible Widespread No Gorse-broom/pasture grass shrubland 9.2 Negligible Widespread No Exotic Pasture No Pasture grassland 10.1 Negligible Widespread No Buildings No Buildings 11.1 Negligible Widespread No Roads No Roads 12.1 Negligible Widespread No
14 This includes vegetation types and habitat types such as rock outcrops, which may not have a cover of indigenous vegetation.
Environmental Setting Section 3 – page 66
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Threatened and Uncommon Species
Prior to the field surveys undertaken for this project, the following ‘At Risk’ or ‘regionally rare’ species were known to be present within or close to the Site or External Roads (threat rankings are from de Lange et al. 2009 or Sawyer 2004):
Within the Site: - wood rose (Dactylanthus taylorii; Threatened-Nationally Vulnerable). Known sites will not be affected.
Habitats adjacent to External Roads: - Teucridium parviflorum (At Risk-Declining); - Coprosma pedicellata (At Risk-Declining); - White mistletoe (Tupeia antarctica; At Risk-Declining); - Dwarf (leafless) mistletoe (Korthalsella linksayi; regionally threatened- sparse).
None of these species were found within habitats to be affected by development of the CHWF, or any other ‘Threatened’, ‘At Risk’, regionally rare, or uncommon plant species.
Pest Plants
Eleven pest plant taxa listed in Regional Pest Management Strategies (Horizons Regional Council 2007 and Greater Wellington Regional Council 2009) were recorded during field visits, or have been reported within or near the Site.
Birds
Systematic surveys were undertaken across the Site, between January 2010 and March 2011, encompassing a full suite of seasons, and two complete spring-summer periods. Systematic surveys undertaken between 20 January 2010 and 11 March 2011 included monthly five-minute bird counts at 90 standardised recording sites across the Site at the locations shown in Figure 3.11, and systematic observations and recording of bird ‘flight paths’ across ridges where turbines are to be placed as shown in Figures 3.12(i) to 3.12(iv). Recording of many incidental observations of species also occurred from October 2009 until March 2011.
Fifty-five bird species - 33 indigenous and 22 introduced - were recorded during field surveys and incidental observations at the Site. A total of 19,053 birds from 42 species were observed during formal monitoring. More than three-quarters (77.4%) of all birds recorded during formal surveys at the Site have been introduced species.
Bats
Long-tailed bats were detected at 15 sites in Turbine Clusters A, D, E, and G, with repeat detections at 11 sites (Figure 3.13). No bats were detected at Cluster B (four survey sites), C (one survey site), or F (one survey site). The largest number of long- tailed bat detections (nearly 70% of total detections) occurred in the lower parts of Patitapu Bush, which is well outside of the area to be affected by construction works.
Environmental Setting Section 3 – page 67
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.11: Locations of five-minute bird count and flight path monitoring stations.
Environmental Setting Section 3 – page 68
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.12(i): Example of a Bird Flight Path Monitoring Map for Cluster E at the CHWF Site. CHFP5B had the highest number of observed flight paths - all heights
Environmental Setting Section 3 – page 69
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.12(ii): Example of a Bird Flight Path Monitoring Map for Cluster E at the CHWF Site. CHFP5B had the highest number of observed flight paths - within the potential rotor zone.
Environmental Setting Section 3 – page 70
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.12(iii): Example of a Bird Flight Path Monitoring Map for Cluster D at the CHWF Site. CHFP4B had the lowest number of observed flight paths - all heights.
Environmental Setting Section 3 – page 71
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.12(iv): Example of a Bird Flight Path Monitoring Map for Cluster D at the CHWF Site. CHFP4B had the lowest number of observed flight paths - within the potential rotor zone.
Environmental Setting Section 3 – page 72
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.13: Locations of automated digital bat recorders and bat detections at the CHWF Site.
Environmental Setting Section 3 – page 73 Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Long-tailed bats are likely to be present in suitable habitat elsewhere within and adjacent to the site, and may forage across much of the Site.
Lizards and Frogs
Common skink, common gecko, southern North Island forest gecko, and the introduced southern bell frog have been recorded at the Site during field surveys (Table 13) and shown in Figure 3.14. These species are all classified as ‘Not Threatened’. Lizards have been found in rock outcrops, scrub, and shrubland habitats throughout the Site. Southern bell frogs have been heard in stock ponds in Clusters A, C, D, and G.
Terrestrial Invertebrates
An initial literature review revealed that no threatened invertebrate species were known from the Site. A field survey was subsequently undertaken using pitfall sampling and demonstrated that a diverse invertebrate assemblage is present at the Site. The results are shown in Figure 3.15. Invertebrates were typical of the habitats present.
Introduced Mammals
Nineteen pest animal species have been recorded at the Site, including ten species listed in the Greater Wellington Regional Pest Management Strategy (2009) and/or the Manawatu-Wanganui Regional Pest Management Strategy (2009).
Summary
Vegetation and habitats within the CHWF Site and along External Road margins have been mapped and described in detail and include 29 types (19 indigenous, ten exotic), in 12 broad classes. Each vegetation type has been assessed to determine its relative ecological value, based on composition and structure. These types have been classified as being of High, Moderate, or Low ecological value. Most of the Site is considered to have very limited ecological value, or low ecological value. The CHWF has been designed to avoid areas with formal legal protection DOC protected areas and QEII covenants). Vegetation types that could trigger provisions in the Horizons One Plan and/or District Plans were also identified and have been avoided where practicable. Much of the remaining indigenous vegetation at the Site is in a secondary successional state, being dominated by manuka and or kanuka. Overall, a limited diversity of indigenous vascular plants is known from the Site.
Field surveys were undertaken for birds, bats, lizards, and terrestrial invertebrates. Various bird, bat, lizard, and invertebrate species are known to be present, but only limited numbers of ‘Threatened’ or ‘At Risk’ species are present. The terrestrial invertebrate community is distinct in indigenous and exotic (pasture) vegetation types and several new species (not an unusual occurrence) and infrequently collected indigenous species were found.
Environmental Setting Section 3 – page 74 Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.14: Location of Artificial Cover Objects (ACOs) and lizards found within the CHWF Site.
Environmental Setting Section 3 – page 75 Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 3.15: Sampling locations for invertebrates within the CHWF Site.
Environmental Setting Section 3 – page 76 Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
3.4 Summary
The CHWF Site is located in a remote and relatively sparsely populated area of the Tararua and Masterton Districts. Both the Masterton and Tararua Districts are characterised by agriculture-based primary production. The Site and surrounding area is rural in nature, significantly modified, currently used for agricultural activities and is generally remote.
It is likely that the CHWF Site and surrounds was visited and used by Maori in the past to gather resources, or they may have travelled through the Site en route to other areas. However, no known or recorded archaeological sites are located within, or in the general vicinity of, the CHWF Site. Archaeological sites in the wider Wairarapa area are generally concentrated on the eastern coast.
The CHWF Site and immediate surrounds are not identified as being within or part of an outstanding natural feature or landscape in the relevant planning documents. The vegetation is dominated by grazed pasture, with hill tops relatively bare of vegetation other than exotic grasses, except for smaller areas of exotic plantation forestry and remnant or regenerating native vegetation in gullies. The noise environment is dominated by rural production activities and natural sounds typical of a rural environment, with some traffic noise from nearby roads.
The CHWF Site is primarily located within the Upper Tiraumea and Tauweru Catchments. Small intermittent streams originate in the upper slopes and combine to form larger perennial streams and rivers in the valley floors and low lying areas. No features of special ecological significance have been identified in the watercourses which drain the CHWF Site. This may be due primarily to the dominance of agricultural activities at the Site, the general lack of riparian protection and sediment run-off from land in the area. Overall, water quality was generally good during winter flow conditions although it declined in some watercourses during reduced summer flows.
Terrestrial vegetation within and around the CHWF Site has been highly modified through significant changes and intensification of land use due to rural uses, including farming and forestry. Forested areas of ecological significance are typically limited to isolated fragments. As a result, the plant and animal communities are dominated by exotic species across much of the Site.
Environmental Setting Section 3 – page 77 Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
4. PROPOSED DEVELOPMENT 4.1 Introduction
The development of the CHWF project has followed an iterative process, from the early stages of site selection through concept studies and preliminary environmental effects assessment phases, to detailed environmental assessments and increasingly definitive project design. During the development process, findings from environmental and engineering assessments, and feedback from stakeholders and the wider community, have been considered. As a result, incremental refinements to project design have been made to ensure that the locations of project components are appropriate and that adverse effects are appropriately avoided, remedied or mitigated.
This section of the AEE outlines the development process undertaken for the CHWF and alternatives considered. The key project components, proposed construction process and Site reinstatement are outlined, as well as an introduction to the proposed resource consent Environmental Management Plan (“EMP”) and Supplementary Environmental Management Plans (“SEMPs”).
4.2 CHWF Development Process 4.2.1 Introduction Genesis Energy has undertaken a comprehensive development process for the CHWF over the last four years which has culminated in this resource consent application. Refinement of the design has occurred throughout the process to take into account environmental aspects, engineering requirements, site characteristics and wind resource.
Refinement of the design will continue through to construction of the CHWF. This will enable selection of the appropriate Turbine for the Site at the time of construction, and will enable site specific environmental and engineering/constructability factors identified during the detailed design phase to be addressed prior to construction commencing. The final design for the CHWF will be confirmed after the Turbine model is selected after resource consents have been obtained, but will be within the parameters of the resource consents granted. When implementing the CHWF project, Genesis Energy will ensure that final designs fit within the overall location and extent of effects described in the AEE and authorised by the resource consents granted. It will ensure that the nature and scale of the effects associated with the final design are no greater than the authorised adverse effects.
The CHWF development process is outlined in Table 4.1 and detailed further below.
4.2.2 Site Selection To identify an appropriate location for a wind farm development, Genesis Energy undertook a national site screening assessment. The assessment utilised mesoscale and spatial modelling tools to identify areas within New Zealand which experience favourable wind speeds, are likely to have suitable terrain for wind farm construction, and to avoid sites of known environmental sensitivity. Incorporated into the spatial modelling were factors such as wind speed, terrain slope and elevation, proximity of intervening land forms, population, known ecological and landscape features, and
Proposed Development Section 4 – page 78
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects transmission and roading infrastructure. The development approach undertaken in selecting a site is detailed in Section 2.3 of this document. As a result of this process, an area located approximately 20 km east of Pahiatua and Eketahuna was identified as having the required attributes for a wind farm. This led to the identification of what is now referred to as the CHWF Site.
Table 4.1: Outline of the CHWF development process.
Phase Key Activities Nationwide search of possible wind development sites using spatial and mesoscale wind modelling tools Site Selection Focus on sites of high wind (2007- 2008) Avoid areas that are known to have environmental sensitivity, those close to residential areas or of established ecological or national significance
Initial CHWF layout Concept Studies RMA planning and high level environmental assessments (2008 – 2009) Land access secured
Preliminary Wind monitoring and energy assessments Design and Environmental Constructability assessments Assessments Preparation and refinement of alternative Turbine layouts (2009) Preliminary environmental assessments Further development of project design, including development and Project Design refinement of the Turbine Corridor and Assessment of Environmental Engineering to support assessment of environmental effects Effects Detailed environmental assessments (2010- 2011) Ongoing incorporation of environmental assessment findings and feedback from consultation with stakeholders into project design Lodge Resource Consent Project definition finalised Applications Resource consent applications lodged (2011)
Detailed design Development of detailed specifications for tendering and procurement of components and works (before construction) Detailed design prior to construction Finalisation and approval of the resource consent EMP and SEMPs Implementation of the resource consent EMP and SEMPs Final Design Design finalisation and modifications during construction (during construction) Monitoring of construction activities and environmental effects with modifications to design and the resource consent EMP and SEMPs if required.
Proposed Development Section 4 – page 79
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
4.2.3 Concept Studies The second phase in the CHWF development process involved feasibility studies to assess the suitability of the Site for a wind farm development. An initial Turbine layout was developed and high level environmental assessments and RMA planning assessments were undertaken to assess potential environmental sensitivities associated with the Site. Landowner access was also secured with CHWF Landowners to enable more detailed investigation of the Site.
4.2.4 Preliminary Design and Environmental Assessments Preliminary environmental assessments were undertaken during the third phase of the development process to develop a better understanding of the Site’s features and characteristics and to identify any potential environmental sensitivities, or construction constraints. More detailed wind monitoring was also carried out during this phase.
Preliminary environmental assessments included ecology, landscape and visual amenity effects, potential noise implications and transportation issues. A number of potential environmental sensitivities were identified during these preliminary assessments, and were incorporated into the project design. The studies did not identify any significant environmental impediments to the development of the project at the Site.
A constructability assessment was undertaken by Aurecon to determine the construction constraints at the Site. This assessment included an extensive survey across potential Turbine locations to ascertain the suitability of the Site for Turbine placement. The constructability assessment concluded that construction of a wind farm on the Site was technically feasible.
Detailed wind resource analysis was undertaken to further understand the wind resource at the CHWF Site. Ongoing wind data was collected from six wind monitoring masts that were installed across the Site between April and December 200915. LIDAR equipment has also been used to collect wind data from around the Site to supplement the monitoring mast data. This has been analysed with mesoscale wind modelling outputs and information collected from long-term weather stations, particularly the weather station at Castlepoint. The detailed wind resource assessments based on this data confirmed that the CHWF Site has a highly suitable wind resource for wind generation.
Assessments of Turbine technology and wind conditions at the Site were used to identify the Turbines that are likely to be available and suitable for installation at the CHWF Site. From this, a range of Turbine specifications were identified to represent the range of Turbines that may be available and appropriate for the Site, both now and in the future. Four Indicative Turbine Layouts were developed to represent this range of Turbines and specifications, and these in turn have been used to define the Turbine Corridor and for further engineering and environmental assessments.
15 Genesis Energy has installed six 80 m monitoring masts and associated recording equipment in accordance with existing resource consents RM090034 (TDC) and 20090407 (MDC). These masts have been used to study site specific wind conditions for determining Turbine locations, to provide an estimate of the potential electricity production of the CHWF Site, and will enable ongoing optimisation of Turbine output.
Proposed Development Section 4 – page 80
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
4.2.5 Project Design and Assessment of Environmental Effects The project design and assessment of environmental effects phase of the CHWF development process included engineering and environmental assessments to inform and refine the overall project design. The environmental effects assessments are summarised in Section 5 of this document and provided in Volumes 3, 4 and 5.
Consultation with key stakeholders and the wider community, as detailed further in Section 7 of this document, has also been an integral part of the CHWF development process. Feedback obtained during consultation has been used to refine the project design.
The design process for the CHWF has been iterative with the design upon which environmental assessments have been based being refined by the findings of the assessments. Placement of infrastructure has been located to avoid and minimise potential effects where practicable. Further description of how the environmental assessments influenced the design of the CHWF is outlined below. Engineering considerations that were taken into account and influenced the design of the CHWF are described in the COMR provided in Appendix A (Volume 2).
Recreation and Tourism
The Recreation and Tourism Effects Assessment concluded that with traffic management, road improvements and mitigation measures the effects on recreation and tourism will at, most, be no more than minor. No specific design modifications were required. Refer to Section 5.2.3 for a summary of recreation and tourism effects and Volume 3 (Section 3) for the Recreation and Tourism Effects Assessment.
Landscape and Visual
The position of the CHWF infrastructure was considered with respect to achieving an appropriate fit with the surrounding landscape. From site selection and throughout the development process and project design phase of the CHWF, an important landscape objective has been to achieve a high degree of visual and landscape integration and in doing so, avoiding and minimising potential landscape and visual effects. To disguise or attempt to “hide” the CHWF is not practical. Likewise, to highlight and make the CHWF the major focal point in the landscape was not sought. What has been achieved has been an integrated outcome where the visibility of the Turbines and their associated infrastructure have been carefully considered, as have the potential effects on views, rural character and visual amenity of the area in general and rural dwellings in particular.
Substations, the Internal Transmission Line and 33kV overhead lines have been sited to minimise visibility. Low visibility was one of the criteria considered when selecting Substation sites, and the Internal Transmission Line and 33kV lines have been situated off ridge lines and away from public viewpoints and dwellings where practicable.
Refer to Section 5.3 for a summary of the landscape and visual effects, and Volume 3 (Section 4) and Volume 5 for the Landscape and Visual Effects Assessment.
Proposed Development Section 4 – page 81
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Noise
During design predicted noise emissions informed the location and siting of infrastructure by ensuring that all relevant noise standards could be met. Predicted construction noise effects comply with the relevant standards at all External Dwellings therefore no design modifications were required. Predicted operational noise effects comply with the limits set out in the wind Turbine noise standard (NZS6808:2010) at all External Dwellings. At External Dwellings where the predicted noise level is close to the wind Turbine noise standard limit the Turbine Corridor has been reduced to prevent any Turbines being located closer to the dwelling than that assessed. Refer to Section 5.4 for a summary of noise effects and Volume 3 (Section 5) for the Noise Effects Assessment.
Transportation
The transportation effects assessment determined that with appropriate management measures, traffic effects associated with construction and operation of the CHWF would be acceptable. No requirements for modification of the CHWF design to minimise effects were identified. Castle Hill Road was selected as the OW/OD Route to the eastern side of the CHWF rather than upgrading Daggs Road, Wairiri Road and Maringi Road to reduce earthworks relating to External Road upgrades. Refer to Section 5.5 for a summary of transportation effects and Volume 3 (Section 6) for the Transportation Effects Assessment.
Hydrology
A key factor considered in identifying potential sites for buildings such as the Main and Satellite Substations, and the Switching Station, was the potential for flood risk. Buildings have been sited away from potential flood areas as far as practicable and have been designed to avoid and manage effects of flooding. Turbines and associated Turbine infrastructure are primarily located on ridgelines so there is no flood risk associated with these components. Refer to Section 5.6.2 for a summary of the hydrology effects and Volume 3 (Section 8) for the Hydrology Effects Assessment.
Groundwater
The groundwater assessment determined that with mitigation measures the effects of the CHWF on groundwater would be no more than minor therefore no specific design modifications were required. Refer to Section 5.6.3 for a summary of groundwater effects and Volume 4 (Section 1) for the Groundwater Effects Assessment.
Aquatic Ecology
All CHWF infrastructure has been positioned and designed to avoid or minimise clearance of vegetation around watercourses and seepage areas dominated by high value indigenous species. Avoiding and minimising this vegetation clearance will allow a buffer to be maintained at watercourses where practical thereby reducing potential effects from adjacent earthworks disturbance and sediment discharges. The location of water crossings was also reviewed to take into account the relative ecological values
Proposed Development Section 4 – page 82
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects of the waterways On-site. No requirements for modification of the location and design of watercourse crossings were identified. Specific design of erosion and sediment control measures will be completed once the CHWF design is finalised as described in the COMR and the Hydrology Effects Assessment. Refer to Section 5.6.2 for a summary of aquatic ecology effects and Volume 4 (Section 2) for the Aquatic Ecology Effects Assessment.
Terrestrial Ecology
Wherever possible and practicable, CHWF infrastructure has been located in vegetation dominated by exotic species, such as pasture, and early successional manuka and/or tauhinu shrubland of low ecological value. All CHWF infrastructure was positioned and designed to avoid legally-protected areas (DOC and QEII administered land), to avoid or minimise clearance of high ecological value vegetation types such as podocarp/broadleaved forest, tawa forest, and kamahi forest and to minimise clearance of manuka-kanuka forest, and broadleaved treeland. All legally protected areas were removed from the Turbine Corridor as were areas of high ecological value wherever practicable. Refer to Section 5.7 for a summary of the ecological effects assessment and Volume 4 (Section 3) for the Ecology Effects Assessment.
Archaeology
The archaeology assessment determined that the CHWF Site had no known sites of archaeological significance and the potential for discovery of unidentified archaeological is low. No specific design modifications were required. Refer to Section 5.9 for a summary of archaeology effects and Volume 4 (Section 5) for the Archaeological Effects Assessment.
Shadow Flicker
The shadow flicker assessment determined that shadow flicker effects on External Dwellings would be within international guidelines therefore no specific design modifications were required. Refer to Section 5.10 for a summary of shadow flicker effects and Volume 4 (Section 6) for the Shadow Flicker Effects Assessment.
Radio Services
The radio services effects assessment determined that there is potential for effects on some radio services. These are being addressed through consultation with the operators and any remaining risks will be addressed through micro-siting of Turbines within the Turbine Corridor during detailed design. Refer to Section 5.11 for a summary of radio services effects and Volume 4 (Section 7) for the Radio Services Effects Assessment.
Health Effects
The health effects assessment determined that there would be no effects as long as the design standards (International Commission for Non-ionising Radiation Protection
Proposed Development Section 4 – page 83
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
(“ICNIRP”) Guidelines 2010) which the EBoP was designed to comply with, continued to be met. As the ICNIRP Guidelines were incorporated early in the design stage, no later design modifications were required. Refer to Section 5.13 for a summary of the health effects assessment and Volume 4 (Section 8) for the Health Effects Assessment.
4.2.6 Alternatives Considered Alternative Generation Options
A number of factors were considered by Genesis Energy in deciding to proceed with a wind farm development in this locality. As outlined in Section 2.2.3, Genesis Energy operates a diverse portfolio of renewable and non-renewable generation that assists in meeting demand while contributing to a secure electricity supply to New Zealand. New Zealand has a world class wind resource, and in line with national energy policies, Genesis Energy considers that renewable generation, and wind generation in particular, will be an increasingly important component of the overall electricity generation mix.
Alternative Sites
Section 2.3 outlines the development approach undertaken by Genesis Energy in deciding to proceed with the CHWF at the identified Site. A range of matters were considered in selecting this Site, including the suitability of the wind resource, land availability, site access, proximity to the national grid, RMA planning considerations and potential environmental effects. The site selection process commenced at a nationwide level, where 14 regions were selected for more detailed study, including (amongst others), Southland/southern Otago, northern Northland, south Waikato, southern Taranaki and southern Hawke’s Bay/Wairarapa. The wind resource for each of these regions was modelled and potential sites narrowed down taking various site attributes and constraints into consideration. From this, the Wairarapa area was considered for further assessment and the Castle Hill Site was ultimately identified as being appropriate for a wind farm development.
Alternative Turbines and Site Layout
The development process undertaken for the CHWF, including how the location and layout of the Turbines, Turbine Corridor, EBoP, Internal Roads and other structures have been defined is outlined above. Any Turbine used for the CHWF will have to fit within the parameters of the Turbine Corridor and Turbine height limits. The Turbine Corridor enables a range of Turbine models to be considered for any specific location, provided that the resource consent conditions are satisfied. The specific Turbine model will be selected as part of the detailed design phase. As part of the detailed design phase, once the Turbine model(s) has been selected, final Turbine layout within the Turbine Corridor will be determined.
Alternative Access
A key consideration with any wind farm development is the access and delivery of wind farm components, and ancillary materials during the construction phase. Given the
Proposed Development Section 4 – page 84
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
OW/OD loads associated with the delivery of wind farm components, a number of alternative delivery routes to the CHWF Site have been considered, including alternative:
Delivery port options for wind farm components; and
Access for the delivery of Turbine components, including rail, air and barge.
The final selection of the delivery port will be confirmed in the detailed design. Alternative options for the delivery of Turbine components to the Site were assessed but have not been considered further due to practical limitations accessing the Site, requirement for double-handling of Turbine components, capacity to transport the required loads and other logistical constraints. Irrespective of which delivery port is utilised, the effects on local roads remains essentially the same.
4.3 Project Components 4.3.1 Introduction This section of the AEE sets out the main project components and features of the CHWF. Components are shown in the CHWF Project Maps in Appendix C (Volume 2) and include:
Turbines: plant consisting of foundations, tower, nacelle and rotor for conversion of wind energy into electricity.
A Turbine Corridor: 3,144 ha identified as suitable for Turbine placement. Turbines will be located within this corridor.
Turbine Clusters: groupings of Turbines for ease of reference.
Turbine Configurations: up to 286 Medium Turbines (maximum tip height 135 m) or up to 242 Large Turbines (maximum tip height greater than 135 m but no greater than 155 m) or a mixture of Medium and Large Turbines installed within the Turbine Corridor.
Internal Roads: roads constructed within the CHWF Site for transporting wind farm components, materials and personnel within Site and to allow access around the Site for construction and operational activities.
EBoP: all electrical structures and equipment related to the collection and reticulation of electrical power around CHWF to the point of connection to the External Transmission Line. EBoP includes an Internal Transmission Line, 33kV overhead lines, 33kV underground cables, a Main Substation and Satellite Substation, an optional Switching Station and switch gear huts along with other associated electrical equipment.
External Roads: Public roads near the Site that are planned to be used for traffic associated with the construction and operation of the CHWF and by Over-weight and Over-dimension Vehicles.
Earthworks associated with the construction and maintenance of the CHWF.
Proposed Development Section 4 – page 85
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Temporary construction infrastructure: components required for construction of the CHWF including Concrete Batching Plants, Central Laydown Areas, Excess Fill Areas, Contractor Compounds, quarrying and crushing facilities and water storage and abstraction facilities.
Operations infrastructure e.g. operations and maintenance buildings.
Turbines and other imported equipment are likely to be transported from the Port of Napier. This is the closest suitable port to the CHWF and is connected to the Site by a major arterial route (SH 50(A) and then SH 2). Other ports being considered are Centre Port and Port Taranaki. The final selection of the delivery port will be confirmed through discussions with the ports prior to detailed design. Genesis Energy is not seeking resource consent as part of this application, for any upgrading of External Roads that may be required between the chosen Port and Alfredton. Where resource consents are required for the works on External Roads for this section of the route, they will be sought through a separate resource consent application process.
4.3.2 Turbines As outlined, Genesis Energy is seeking resource consents for the construction and operation of the CHWF that provides some flexibility in terms of the Turbine model and size selected, and location within the Turbine Corridor. The actual Turbines will be selected during the detailed design phase of the project.
Turbine Components
Irrespective of the Turbine model selected, each Turbine will comprise several main components, as shown in Figure 4.1 and described below.
Tower
The supporting structure will be a steel or concrete tower fitted with an internal ladder or lift. The dimensions will be dependent on the Turbine model selected. To facilitate their production and transport, the towers will be manufactured in sections which will be assembled at each Turbine location. If a steel tower design is selected, there will typically be up to five sections to transport and assemble on Site. Should concrete towers be used, a larger number of sections are expected (for example approximately 16 individual sections) which may be prefabricated and transported to the Site in sections or fabricated on-site.
Rotor
The rotor consists of three Turbine blades and a hub, and is attached to the shaft which drives the generator in the nacelle. The blades are generally constructed of fibreglass and the hub generally of steel. Motors within the nacelle are used to turn the nacelle to face into the wind and to adjust the pitch of the Turbine blades to maximise energy production.
Proposed Development Section 4 – page 86
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Blade
Hub Nacelle
Rotor Diameter
Tower Height
Hub Height
Tip Tower Height Turbine Kiosk/transformer
Turbine Foundation
Figure 4.1: Schematic of Turbine components.
Nacelle
The nacelle is the housing mounted on top of the tower that generally encloses a gearbox, generator, transformer, motors, brakes, electronic components, wiring, and hydraulic and lubricating oil systems and to which the rotor is attached. The nacelle is usually constructed of steel and fibreglass. Weather monitoring equipment located on top of the nacelle will provide data on wind speed and direction for the automatic operation of the Turbine.
Transformer
Turbine transformers are required to transform Turbine generator voltage for reticulation and may be located inside the Turbine nacelle, tower base, or adjacent to the Turbine on separate foundations.
Proposed Development Section 4 – page 87
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Turbine Corridor
Genesis Energy anticipates that a number of Turbine models will be commercially available at the time of tendering for the construction of the CHWF. In order to allow for optimisation in Turbine placement (for commercial, environmental and constructability reasons), Genesis Energy is seeking resource consent for a Turbine Corridor enabling a range of Turbines to be considered. The Turbine Corridor covers an area of 3,144 ha and incorporates all areas within the CHWF Site that have been selected for Turbine placement (see Figure 1.2). Turbines may be sited anywhere within the Turbine Corridor and may not be located outside the Turbine Corridor.
The area and location of the Turbine Corridor is shown in Figures 1.2 and 1.3(i) to 1.3(iv), and in the CHWF Project Maps (Appendix C, Volume 2).
The proposed Turbine Corridor has incorporated environmental and engineering assessments to avoid and/or minimise environmental effects. Firstly, the Turbine Corridor was created by overlaying the four Indicative Turbine Layouts on each other (as shown in the example in Figure 4.2). A buffer of 200 m was applied around each Turbine location with the resulting shape (the initial Turbine Corridor) then being examined and adjusted to ensure that all areas within the Site suitable for Turbine placement were included. The Turbine Corridor approach allows for optimisation of the placement of different sized Turbines and the use of a range of Turbine specifications.
Figure 4.2: Unmodified Turbine Corridor (green) with four overlying Indicative Turbine Layouts.
Environmental sensitivities and engineering constraints were then assessed in detail as shown in the example in Figure 4.3. Areas where legal or statutory plans limit disturbance, such as reserves, QEII Open Space Covenants and DOC land were identified and removed from the Turbine Corridor. The Turbine locations in the Indicative Turbine Layouts were adjusted to avoid or minimise other environmental effects as described in Section 4.2.5 above.
Proposed Development Section 4 – page 88
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 4.3: Refined Turbine Corridor (green).
As part of the detailed design phase, once the final Turbine models have been selected, Turbines will be micro-sited within the Turbine Corridor, with the Turbine model selected dictating the spacing required between the individual Turbines and therefore the total number of Turbines to be installed. Typically Turbine spacing is between 2.5 to four times the Turbine rotor diameter if Turbines are arranged across the predominant wind direction, and five to 12 times the Turbine rotor diameter in the downwind direction. Terrain, wind conditions, Turbine model characteristics and environmental factors will determine the final Turbine locations. The Turbine layout to be used will be defined prior to construction, and construction layout plans will be provided to Council.
Turbine Sizes
Genesis Energy has undertaken an assessment of available Turbines and potential suppliers to identify a range of Turbines suitable for installation at the CHWF. Two Turbine size ranges have been established to capture the range of sizes available:
Medium Turbines have a maximum tip height of 135 m; and
Large Turbines have a maximum tip height greater than 135 m but not more than 155 m.
Turbine Configurations
The size range of suitable Turbines determines the number of Turbines which can be installed. As the rotor diameter of the Turbines increases, the space required between the Turbines also increases to avoid energy loss from wake and other effects. This
Proposed Development Section 4 – page 89
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects means the optimal quantity and positioning of the Turbines changes from one Turbine model to the next.
The following three Turbine configurations have been established to define the maximum number of Turbines in the Turbine Corridor:
Medium Turbine Configuration - comprises only Medium Turbines up to a maximum quantity of 286 Turbines.
Large Turbine Configuration – comprises only Large Turbines up to a maximum quantity of 242 Turbines.
Mixed Turbine Configuration - comprises a mixture of Medium and Large Turbines with the maximum quantity of Turbines of each size determined according to the graph shown in Figure 4.4. This mixture of Medium and Large Turbines is described by the following equation:
NM + NL 1 286 242
where NM is the number of Medium Turbines and NL is the number of Large Turbines in the Mixed Turbine Configuration.
Relationship Between Medium and Large Turbine Numbers 300
250
200
150 Number of Large Turbines 100
50
0 0 50 100 150 200 250 300 350 Number of Medium Turbines
Figure 4.4: Relationship between numbers of Medium and Large Turbines in the Mixed Turbine Configuration.
The Mixed Turbine Configuration has been included as there is the potential for different types of Turbines to be used within the Turbine Corridor, due to the variance in the wind resource across the CHWF Site. In addition, there may be different
Proposed Development Section 4 – page 90
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Turbines available for supply at different stages of development. However, the variation between Turbines will be minimised where practicable, for example while the size may differ, very large Turbines will not be utilised next to much smaller Turbines. To minimise visual effects, Turbines will be off-white in colour and will have three blades. Tubular (not lattice) towers will be used.
Turbine Layouts
Four Indicative Turbine Layouts (two Medium Turbine Layouts and two Large Turbine Layouts) have been developed to represent the range of possible Turbine sizes that could be developed at the CHWF Site, and to allow environmental assessment where a specific layout is required. The layouts are based on different rotor diameter sizes to demonstrate the different Turbine spacing that could occur within the Turbine Corridor. The parameters of these layouts are provided in Table 4.2.
Table 4.2: Indicative Turbine Layouts.
Medium Turbine Layouts Large Turbine Layouts Indicative Turbine Layout Name 80M 90M 100L 110L Indicative Rotor Diameter (m) 80 90 100 110 (may vary up or down) Indicative Hub Height (m) 90 90 100 100 (may vary up or down)
Number of Turbines 286 262 242 186
Maximum tip height (m) 135 135 155 155
Turbine placement for these layouts was determined by:
Suitability of terrain for Turbine construction.
Quality of the wind resource across the Site - this affects which locations are selected but will also dictate the type of wind Turbine that can be used at a particular site.
Spacing required between Turbines to minimise wake effects from one Turbine to another (generally determined by a Turbines rotor size).
Turbine Clusters
As outlined in Section 1.1 and shown in Figure 1.2, the Turbines have been grouped into seven Turbine Clusters (A to G) for ease of reference. The Turbine Clusters are primarily based on geographical location, and do not represent proposed project staging or a construction programme.
Proposed Development Section 4 – page 91
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Turbine Numbering
Turbines are numbered according to the following format:
Layout Name – Turbine Cluster Letter - Turbine Number.
For example, Turbine 5-80-A-016 is Turbine 16 belonging to Turbine Cluster A of revision 5 of the 80M layout.
Turbine Foundations
Turbine Foundations will be regular shaped concrete pads (likely to be circular or octagonal), and constructed from reinforced concrete. The design of each Turbine Foundation will differ depending on Turbine type, geotechnical conditions at each site, earthquake loading conditions and wind loading conditions, and will be determined during the detailed design phase. Indicative Turbine Foundation design parameters for the Medium and Large Turbine options are summarised in Table 4.3.
Table 4.3: Indicative Turbine Foundation parameters.
Turbine Foundation Reinforcing Steel Concrete Foundation Type Diameter (m) (tonnes) (m3) Depth (m) Medium Up to 18 40 – 50 465 – 520 2.0 – 5.0 Large Up to 21 50 – 65 580 – 710 2.0 – 5.0
Piled foundations may be used in areas of site instability or where weaker soils are present. This requirement will be confirmed once final Turbine locations are determined during the detailed design phase. All Turbine Foundations will be covered with excavated soil and will not be visible after construction. Figure 4.5 provides a schematic cross-section of a Turbine Foundation.
Figure 4.5: Schematic Turbine Foundation cross-section.
Proposed Development Section 4 – page 92
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Turbine Platforms
Each Turbine will have a flat construction platform located adjacent to the Turbine Foundation, to provide a working space for crane operations and for lay-out and assembly of Turbine components. All Turbine Platforms will be located within the Turbine Corridor, and are unlikely to extend out further than 60 m from final Turbine locations.
The Turbine Platform for both the Medium and Large Turbines will be approximately 50 m long and 28 m wide (1,400 m²). However, the specific geometry of each Turbine Platform will be optimised on a case by case basis during the detailed design phase prior to construction, to take into account the local terrain. Where local conditions dictate the need for a smaller Turbine Platform, the size will be reduced to a minimum area of 800 m² for a Medium Turbine and 1,250 m² for a Large Turbine, however a smaller size may be less practical and give rise to construction delays. Figure 4.6 shows a schematic of a Turbine Platform layout.
Figure 4.6: Schematic layout of a Turbine Platform.
The Turbine Platform site will be excavated to a level surface and covered with a layer of compacted gravel. Where appropriate, a stormwater retention system will be established around the perimeter of the Turbine Platform for the duration of the construction period. Post construction, the platform will not be actively rehabilitated but may naturally re-vegetate. This allows for the Turbine Platform to be retained should it be required for future operations and maintenance activities.
Turbine Lighting for Aviation Purposes
Aviation safety and standards in New Zealand are the responsibility of the Civil Aviation Authority (“CAA”). Under Part 77 of the Civil Aviation Rules, anyone proposing a structure that will extend more than 60 m in height above the ground level at its site must notify the Director of Civil Aviation of the proposed structure at least 90 days before it is erected. Under Rule 77.19, any structure exceeding 120 m in height above the ground level at its site is considered a hazard in navigable airspace, and conditions or limitations may be imposed for marking or lighting the structure.
Proposed Development Section 4 – page 93
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
With respect to wind farms, the CAA has specific guidelines regarding the lighting and identification of wind Turbines and meteorological masts, and will make a determination on a case-by-case basis as to the lighting requirements. As a minimum, the following conditions and limitations are likely to be included in all determinations by the CAA:
Selected individual Turbines at wind farms with Turbines over 60 m high will be required to have lighting.
The highest Turbines, those at the extremities of the Site, and other Turbines around the perimeter of the Site will be lit. The spacing between lit Turbines will not exceed 1 1,850 m.
Lighting will be medium intensity red as defined in Rule Part 77, Appendix B10 (i.e. an effective intensity of not less than 1,600 candela of red light, and will flash between 20 and 60 times per minute).
The obstruction lights shall be located on or above the top of the nacelle, shall be visible from all directions, and may be shielded below the horizontal plane.
Obstruction lights at intermediate levels will not be required.
The painting of Turbines with obstruction marking will not be required.
All wind farms will be depicted on aeronautical charts (CAA, 2006).
With respect to the CHWF, permanent lights will only be installed on Turbines and wind monitoring masts where required to meet CAA requirements, to minimise lighting in the surrounding area. As a minimum, it is expected that there will be a requirement for lighting to be installed on Turbines around the perimeter of the Site, along with some Turbines within each of the Turbine Clusters.
Genesis Energy has discussed the proposal with the CAA in relation to their requirements, and no specific requirements (other than as noted above) have been identified. The CAA will be formally notified of the project details at the detailed design stage of the project and will be provided with a final Turbine layout. This will enable an assessment to be undertaken at that time to determine the specific lighting and other aviation safety requirements.
4.3.3 Electrical Balance of Plant The EBoP is comprised of all electrical plant on the Site connecting the Turbines to the External Transmission Line. There are two options for the EBoP design (referred to as EBoP Option 1 and EBoP Option 2), as shown in Figures 4.7 and 4.8.
The difference in the EBoP Options relates to the two location options for the Main Substation as the final selection of the Main Substation location will determine the location of various EBoP components. Figures 4.7 and 4.8 show the indicative location of all EBoP components and illustrate how the EBoP component locations vary depending on which Main Substation location is selected.
Proposed Development Section 4 – page 94
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The main components of the EBoP include:
Main Substation (two options proposed);
Satellite Substation;
33kV underground cables (double and single circuit);
33kV overhead lines (double and single circuit);
Internal Transmission Line;
Optional Switching Station and Internal Transmission Line Deviation;
Electrical switchgear huts; and
Other components (e.g. earthing / communications).
Each of these components is described in more detail below.
While some flexibility in the footprint of the substations is sought, the layout of the EBoP is not expected to change significantly from that described below and shown in Figures 4.7 and 4.8, regardless of whether a Medium or Large Turbine Configuration is selected.
Location Description for EBoP Components
The EBoP are likely to be located where indicated in the CHWF Project Maps in Appendix C (Volume 2) but may be located anywhere subject to the following limitations:
Main Substations: located at one of the two locations shown in the CHWF Project Maps in Appendix C.
The location of the Satellite Substation is shown in the CHWF Project Maps in Appendix C.
The location of the Switching Station is shown in the CHWF Project Maps in Appendix C.
The location of the Internal Transmission Line will be within 50m of the location indicated in the CHWF Project Maps in Appendix C.
The location of the Internal Transmission towers will be within 50m of the locations indicated in the CHWF Project Maps in Appendix C and will be positioned to avoid clearance or trimming of indigenous vegetation to the extent practicable.
33kV Overhead Lines, Underground Cables and other EBoP components are likely to be located where indicated in the CHWF Project Maps in Appendix C
Proposed Development Section 4 – page 95
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
but may be located anywhere within the Site, subject to the following limitations:
1. Areas of legally protected habitats (DOC, QEII) and, ‘rare’, ‘threatened’ or ‘at risk’ habitats identified under statutory plans will not be disturbed.
2. Areas of ‘high ecological value’ as defined in the Ecological Effects Assessment in Volume 4 (Section 3) will be avoided, except to the extent already outlined in the CHWF Project Figures in Appendix C and shown in the AEE. Clearance of a limited amount ‘high ecological value’ vegetation is described and this quantity will not be exceeded in construction of the CHWF.
3. Clearance of indigenous vegetation will be minimised and will not cause the maximum quantity of indigenous vegetation clearance of 66ha described in the Ecological Effects Assessment in Volume 4 (Section 3) to be exceeded.
4. Gullies with watercourses will be avoided unless it can be demonstrated that downstream water quality effects are no more than minor.
5. Seepage areas dominated by indigenous species with an area greater than 0.05ha will be avoided.
6. Total CHWF earthworks volumes described in the AEE are not exceeded.
7. Noise standards will be complied with or effects will be appropriately mitigated.
Main Substation and Satellite Substation
Main and Satellite Substation sites have been identified according to the following criteria:
Large, flat area central to the surrounding wind Turbines;
Suitable access for heavy vehicles;
Distant from occupied dwellings;
Consideration of visual impacts from overhead lines and the building;
Potential for flood risk;
Proximity to trees and potential sources of flying debris; and
Sheltered from the wind.
From a number of sites of sufficient size, two sites for the Main Substation and one site for the Satellite Substation were identified.
Proposed Development Section 4 – page 96 bles !100 ouble circuit !100 ngle circuit 2 !100 d, double circuit A !100 !100 100 !100 ! d, single circut !100 !100 3 !100 !100 sion Line (220kV) !100 !100 !100 !100 !100 sion Line Deviation !100 !100 sion Line towers 4 !100 100 ! !100 !100 !100
! 5 !100 !100 !100 !100 !100 !100 !100 Satellite Substation !100 6 !100 !100 !100 !100 !100 B 7 !100 !100 !100 !100 !100
!100 !100
!100 9 !100 !100
!100 100 !100 !100 ! !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !00 Optional Switching Station 12 !100 13 !100 !100 !100 !100 !100 100 100 !100 100 100 ! 100 ! !100 !100 ! ! ! !100 !100 10!100 !100 !100 D C !100 !100 !100 !100 !100 !100 !100 !100 !100 11 100 !100 ! !100 !100 14 15 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 16 !100 !100 !100 !100 !100 !100 !100 !100 100 !100 ! !100 !100 !100 !100 18 !100 100 100 !100 21 ! ! 17 !100 !100 !100 !100 !100 !100 25 !100 !100 100 100 ! 100!100 ! !100 !100 ! !100 100 100 !100 ! 100 !100 !100 ! !100 ! !100 !100 !100 !100 !100 23!100 !100 !100 100 !100 100 100 ! E 100 20 !100 ! ! ! 100 !100 100 !100 ! !100 !100 !100 ! !100 !100 26 !100 100 100 100 !100 ! !100 !100 !100 ! !100 ! !100 100 !100 !100 ! F !100 27 !100 !100 100 !100 !100 ! 100 19 !100 22!100 ! G 100 100 ! ! !100 100 !100 !100 ! !100 !100 !10 !0 !100 !100 !100 !100 !100 24 !100 !100 28 !100 !100 !100!100 !0
!0 d, double circuit ! d, single circuit !100 ound, double circuit 2 A !100 !100 100 100 ! ound, single circuit !100 ! !100 3 !100 mission Line (220kV) !100 !100 !100 !100 mission Line Deviation !100 !100 100 ! !100 mission Line towers 4 !100 !100 !100 !100 !100
!100 ! !100 !100 !100 !100 Satellite Substation 6 !100 !100 !1 !100 !10 B 7 !100 !100 !100 !100 !100
!100 !100
!100 100 9 !100 !
!100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !00 Optional Switching Station 12 !100 13 !100 !100 !100 !100 !100 10 100 !100 !100 !100 100 ! 100 !100 !100 ! ! !100 !100 !100 !100 D !100 100 C ! !100 !100 !100 !100 !100 !100 !100 !100 100 11 !100 100 14 ! !100 ! 15 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 !100 16 !100 !100 !100 !100 !100 !100 !100 !100 100 !100 ! !100 !100 !100 !100 18 !100 100 100 !100 17 ! ! !100 !100 !100 !100 !100 !100 !100 !100 21 25 100 100 ! 100 100 !100 ! ! ! !100 100 100 !100 ! 1 100 !100 ! 100 ! !100! 100 100 ! !100 100 !100 ! ! !100 !10 ! !100 !100 23 100 !100 !100 E!100 20 ! !100 !100 !100 !100 !100 !100 !100 !100 !100 26 100 100 ! !100 ! !100 !100 !100 !100 !100 !100 100 100 !100 ! ! F !1 !100 27 !100 !100 !100 22 !100 19 !100 !100 100 !100 24 ! !100 !100 !100 !100 !100 !100 !100 !100 !00 !100 !100 !100 !100 !100 !100 !0 Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The Main Substation is located in the southern region of the Site connecting about two- thirds of the Turbine circuits directly, and the Satellite Substation located in the northern region of the Site. The Main Substation will be located at one of the two locations shown in Figures 4.7 and 4.8. Of these two options for the Main Substation, one will be selected during the detailed design phase of the project depending on which part of the CHWF is first developed, and the final location of the External Transmission Line. Alternative locations also provide redundancy in the unlikely event that one location is found to be unsuitable.
The Satellite Substation has one location (see Figures 4.7 and 4.8), but two alternative pad sites have been provided for. No significant alterations to the EBoP layout are required for either of the pad sites.
The Main Substation may contain the following components:
33kV to 220kV transformers;
Circuit breakers and switchgear;
Switchgear/control/relay building;
Static Var compensation equipment building;
Overhead gantries and buses;
Oil interceptor tanks;
Communication equipment;
Services building;
Car park; and
Perimeter fence.
The purpose of the substations is to receive the output (33kV) from the Turbines, convert this to the 220kV voltage required for transmission to the national grid, provide a safe, controllable and compliant connection to the External Transmission Line, and to provide other required electrical function.
A control room will be sited at each substation and will typically contain electrical and some wind farm control instrumentation, electrical and communications equipment, routine maintenance equipment and stores, a small work area and staff amenities. An auxiliary services building may also be located at the substation site, which will contain switchyard control equipment and batteries.
The final size and configurations of the substations will be influenced by the level of system security chosen and as an outcome of the detailed design. Generally, the level of system security required depends on the size of the wind farm, the type of wind Turbine model selected, grid requirements and operations, and the potential value of lost generation in the event of plant failure. These factors are subject to change as the CHWF is developed, therefore three potential security system levels for the CHWF project have been developed (outlined in the COMR attached as Appendix A).
Proposed Development Section 4 – page 99
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
For the Main Substation, the maximum external dimensions will be 230 m x 174 m (4 ha), while the Satellite Substation will have maximum external dimensions of 125 m x 125 m (1.6 ha).
The substations will be connected to the Internal Transmission Line via termination towers (approximately 26 m high), while the maximum height of the substation is not expected to exceed approximately 20 m. Buildings within each Substation site are not expected to exceed 9 m. The indicative layout of the Main and Satellite Substations are shown in Figures 4.9 and 4.10 respectively.
Switching Station
A centrally located Switching Station has been developed as an alternative point of connection of the CHWF to the External Transmission Line. Potential sites for the Switching Station were identified taking into account the following:
Ease of access;
Topography;
Earthwork volumes required;
Visibility;
Proximity to dwellings and other buildings;
Risk of flooding;
Expected proximity to the External Transmission Line connection point;
Wind load; and
Location in respect to the Internal Transmission Line.
The Switching Station will be located at the location shown in Figures 4.7 and 4.8.
The Switching Station collects the high voltage (220kV) outputs from both the Main and Satellite Substation, and directs this output to the national grid via the External Transmission Line. The main function of the Switching Station is to connect / disconnect the substations from the External Transmission Line.
The optional Switching Station may contain the following main components:
HV circuit breakers and switchgear;
An optional 33kV to 220kV transformer;
Switchgear/control/relay building;
Proposed Development Section 4 – page 100
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 4.9: Schematic Main Substation layout.
Proposed Development Section 4 – page 101
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Figure 4.10: Schematic Satellite Substation layout.
Overhead gantries and buses;
Oil interceptor tanks (if required for optional transformer);
Communication equipment;
Car park; and
Perimeter fence.
The Switching Station has an expected footprint of approximately 140 m x 106 m, while equipment within the site will have an expected height of up to 25 m. Figure 4.11 provides an indicative plan of the Switching Station.
Proposed Development Section 4 – page 102
Genesis Energy – Castle Hill Wind Farm [Assessment of Environmental Effects]
Figure 4.11: Schematic plan view of the optional Switching Station.
Underground Cables
Turbines are grouped into electrical circuits. Turbines within circuits will be connected by 33kV underground cables typically buried in a trench beneath (or adjacent to) Internal Roads to minimise earthworks and disturbance. A combination of underground
Proposed Development Section 4 – page 103
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects cables and overhead lines will be used to connect these circuits to centrally located substations.
Several cables may be buried in the same trench or in multiple trenches along the same route. Site specific conditions and electrical loads will determine how the cables are laid and the type of cable used. Figure 4.12 shows two typical cross-sections for underground cabling. The maximum length of all underground cable is estimated to range from 160 km to 180 km, depending on the location of the Main Substation, with all but approximately 10km located under or adjacent to Internal Roads.
Figure 4.12: Schematic cross-sections for underground cable trench design.
Proposed Development Section 4 – page 104
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
Where possible, bedding and backfill material will be sourced from Site (for example excavated material), however it is possible that imported material like sand or crusher dust may be required as bedding material to achieve required thermal resistivity characteristics. This will be confirmed during the detailed design phase. Design and management measures for underground cables is described in more detail in the COMR attached as Appendix A (Volume 2).
Where underground cables are required to traverse a stream, this will be achieved either by directional drilling (from each side of the stream), or through the use of a cable bridge. An indicative sketch of a cable bridge can be found in Appendix A of the COMR. The COMR is attached as Appendix A (Volume 2) to this document.
Overhead Lines
Due to the size of the CHWF, 33kV overhead lines will be required to link the electrical circuit groups to the Main and Satellite Substations.
Overhead line routes will, where practicable, follow existing farm tracks or Internal Roads for ease of installation, monitoring and maintenance. In some sections (for example, close to residential dwellings, due to physical constraints, or where routes cross Internal Roads required for crane movements, the overhead line will convert to underground cabling (see Figure 4.13).
Figure 4.13: Schematic of overhead line to underground cable transition for Internal Road crossings.
To minimise the spread of overhead lines across the Site, and thereby minimise their associated effects, the design of the 33kV reticulation system has sought to bring lines together to follow the same route where possible. This means that in some places, generally as 33kV lines get closer to the substations, more than one set of overhead lines will run in parallel. Table 4.4 provides an estimate of the length of various multiple lines according to estimates based on the current design, and Figures 4.14 and 4.15 show a range of multiple line arrangements. These may vary when detailed design is undertaken. The proposed overhead line routes are shown in Figures 4.7 and 4.8.
Proposed Development Section 4 – page 105
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects
The overhead lines will be supported by a combination of different pole structures. Three representative types of pole structures similar to what will be used for the CHWF are shown in Figures 4.16, 4.17 and 4.18.
Table 4.4: Estimated multiple line lengths.
EBoP Option 1 EBoP Option 2 Length of Total Length of Length of Lines Total Length of Lines Running Individual Running in Individual Lines in Parallel (km) Lines (km) Parallel (km) (km) 1 pole lines 18.2 18.2 35.7 35.7 2 pole lines 17.4 34.8 16.6 33.1 3 pole lines 10.4 31.2 2.6 7.8 4 pole lines 2.3 9.3 1.5 6.1 TOTAL 48.3 93.5 56.4 82.7
Figure 4.14: Isometric view of multiple 33kV line arrangements.
Proposed Development Section 4 – page 106
Genesis Energy – Castle Hill Wind Farm Assessment of Environmental Effects