Status of Languishing Projects in District, Anantang

Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9 I. Jal Shakti :

Jal Shakti (PHE) Division 1 WSS Mamal Jal Shakti (PHE ) 163.00 150.00 119.79 90% Feb.21

Jal Shakti (PHE) Division 2 WSS (Junk of Pipes) Jal Shakti (PHE ) 698.00 491.25 342.878 70% Mar-21 Bijbehara

Jal Shakti (PHE) Division 3 WSS Dardpora Chontihal Watkash Jal Shakti (PHE ) 421.00 416.00 207.797 70% Sep.21 Bijbehara

Jal Shakti (PHE) Division 4 WSS Checki Isheerdas Jal Shakti (PHE ) 299.00 259.00 153.158 60% May-21 Bijbehara

Jal Shakti (PHE) Division 5 WSS Krangsoo Jal Shakti (PHE ) 412.36 381.82 224.79 70% Mar-21 Bijbehara

Jal Shakti (PHE) Division 6 Tailwani Kamad Jal Shakti (PHE ) 375.00 370.00 144.51 60% Mar-22 Bijbehara

Jal Shakti (PHE) Division 7 Khudpora Jal Shakti (PHE ) 130.34 105.34 60.00 80% Mar-21 Bijbehara

Jal Shakti (PHE) Division 8 Durpora Khiram Jal Shakti (PHE ) 140.00 115.00 37.98 75% Jun-21 Bijbehara

Jal Shakti (PHE) Division 9 Bewara Jal Shakti (PHE ) 130.00 92.95 46.552 65% Mar-21 Bijbehara

Jal Shakti (PHE) Division 10 Sheikhpora Mati Jal Shakti (PHE ) 184.24 163.01 28.259 70% Dec-21 Bijbehara

Jal Shakti (PHE) Division 11 Dadoo GB Jal Shakti (PHE ) 150.00 119.02 27.47 95% Jun-21 Bijbehara

Jal Shakti (PHE) Division 12 Jablipora Jal Shakti (PHE ) 500.19 135.69 86.408 95% Mar-21 Bijbehara

Jal Shakti (PHE) Division 13 Seer Ist Jal Shakti (PHE ) 412.36 383.83 192.80 60% Aug-21 Bijbehara

Jal Shakti (PHE) Division 14 Fohar Batpora Jal Shakti (PHE ) 533.34 528.34 205.324 40% Aug-21 Bijbehara

Jal Shakti (PHE) Division 15 Town Jal Shakti (PHE ) 488.17 465.17 100.925 60% Mar-22 Bijbehara

Jal Shakti (PHE) Division 16 Chaklipora Jal Shakti (PHE ) 42.28 29.27 29.27 100% - Bijbehara

Jal Shakti (PHE) Division 17 Andoo Pushroo Jal Shakti (PHE ) 890.37 391.36 104.727 50% Oct-21 Bijbehara Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9

Jal Shakti (PHE) Division 18 High Ground Jal Shakti (PHE ) 371.44 256.81 134.95 50% Oct-21 Bijbehara

Jal Shakti (PHE) Division 19 GB Jal Shakti (PHE ) 205.36 135.36 76.271 30% Jun-21 Bijbehara

Jal Shakti (PHE) Division 20 Indern Gradbader Jal Shakti (PHE ) 255.00 244.00 144.45 70% Aug-21 Bijbehara

Jal Shakti (PHE) Division 21 Laripora Jal Shakti (PHE ) 121.23 72.23 31 90% Mar-21 Bijbehara

Jal Shakti (PHE) Division 22 Arighol Jal Shakti (PHE ) 133.58 70.37 30.63 80% Aug-21 Bijbehara

Jal Shakti (PHE) Division 23 Reshi Mohalla Khandipheri Jal Shakti (PHE ) 943.00 822.09 58.591 25% Mar-22 Bijbehara

Jal Shakti (PHE) Division 24 Gujrat Lehendajan Jal Shakti (PHE ) 385.00 380.00 80.00 70% Jun-21 Bijbehara

Jal Shakti (PHE) Division 25 Shoul Sursuna Jal Shakti (PHE ) 576.11 571.11 60 15% Dec-21 Bijbehara

Jal Shakti (PHE) Division 26 Constt.of impounding reservoir WSS Aug. Bijbehara Jal Shakti (PHE ) 485.00 61.19 0 100% - Bijbehara

Jal Shakti (PHE) Division 27 WSS Kehribal Rambirpora Jal Shakti (PHE ) 3587.50 3291.39 0 50% Not Accorded Bijbehara

Jal Shakti (PHE) Division 28 WSS Batpora Bijbehara Jal Shakti (PHE ) 280.00 112.25 20 50% Jun-21 Bijbehara

Jal Shakti (PHE) Division 29 Qammer Thamankote Jal Shakti (PHE ) 65.00 20.00 20.00 100% -

Jal Shakti (PHE) Division 30 Aug. Dooru Town Jal Shakti (PHE ) 567.00 302.50 160.79 70% Apr-21 Qazigund

Jal Shakti (PHE) Division 31 Dudwugan Jal Shakti (PHE ) 52.00 18.50 7.12 100% - Qazigund

Jal Shakti (PHE) Division 32 Sadiwara Lift Jal Shakti (PHE ) 226.15 54.95 20.00 100% - Qazigund

Jal Shakti (PHE) Division 33 Wavthura Ardbal Jal Shakti (PHE ) 216.00 135.33 17.00 60% Aug.-21 Qazigund

Jal Shakti (PHE) Division 34 Aug. Lift Jal Shakti (PHE ) 355.13 285.33 80.79 65% Aug-21 Qazigund

Jal Shakti (PHE) Division 35 Hiller Shahabad Jal Shakti (PHE ) 460.00 254.11 183.73 90% May-21 Qazigund Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9

Jal Shakti (PHE) Division 36 Aug. Agnoo Jal Shakti (PHE ) 187.00 68.69 17.38 70% Mar-21 Qazigund

Jal Shakti (PHE) Division 37 Ziyarat Shareef Mantipora Jal Shakti (PHE ) 286.00 88.00 10.00 40% Jun-21 Qazigund

Jal Shakti (PHE) Division 38 Bragam Jal Shakti (PHE ) 74.00 23.48 17.50 100% - Qazigund

Jal Shakti (PHE) Division 39 Ziarat Sharief Chohan Jal Shakti (PHE ) 87.00 40.00 30.04 100% - Qazigund

Jal Shakti (PHE) Division 40 Reshipora Gawas Jal Shakti (PHE ) 77.00 25.32 10.00 100% - Qazigund

Jal Shakti (PHE) Division 41 Gujjar Basti Checki Drabihall Jal Shakti (PHE ) 139.15 47.59 34.16 100% - Qazigund

Jal Shakti (PHE) Division 42 Kokagund Jal Shakti (PHE ) 80.00 10.67 8.52 100% - Qazigund

Jal Shakti (PHE) Division 43 Panzoo lift Jal Shakti (PHE ) 114.00 20.69 20.00 100% - Qazigund

Jal Shakti (PHE) Division 44 Lalan Ganoor Jal Shakti (PHE ) 200.00 87.87 34.00 45% Jul-21 Qazigund

Jal Shakti (PHE) Division 45 Shagadwani Zamalgam Jal Shakti (PHE ) 336.70 331.70 66.00 55% Jul-21 Qazigund

Jal Shakti (PHE) Division 46 Mujmandoo Sheikhpora Jal Shakti (PHE ) 326.32 326.32 50.00 55% Aug-21 Qazigund

Jal Shakti (PHE) Division 47 Add. OHT Gassipora Jal Shakti (PHE ) 115.00 52.60 45.36 100% - Qazigund

Jal Shakti (PHE) Division 48 Zadoora Jal Shakti (PHE ) 215.00 14.87 8.25 100% - Qazigund

Jal Shakti (PHE) Division 49 Chirhama Bongam Jal Shakti (PHE ) 277.00 56.96 27.96 100% - Qazigund

Jal Shakti (PHE) Division 50 Aug. Qazigund Town Jal Shakti (PHE ) 522.34 282.38 110.16 70% Oct-21 Qazigund

Jal Shakti (PHE) Division 51 Divisional Office Building at Qazigund Jal Shakti (PHE ) 267.42 138.51 78.55 70% Jun-21 Qazigund

Jal Shakti (PHE) Division 52 New Colony Sadoora Jal Shakti (PHE ) 235.26 120.72 82.03 70% June.-21 Qazigund

Jal Shakti (PHE) Division 53 Rajard Doniwani Jal Shakti (PHE ) 181.00 114.32 58.55 90% Feb-21 Qazigund Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9

Jal Shakti (PHE) Division 54 Levdoora Kuchipora Jal Shakti (PHE ) 214.16 154.67 123.60 80% Mar-21 Qazigund 19188.50 13689.93 4070.02 II. R&B :

Construction of 2 x 20 M span girder Bridge over 1 R&B Department R&B 261.85 123.04 101.94 100% - Nallah Gowaran near Syedpora Kharati Vailoo

Construction of 1x30 Mtr Span Steel Trussed bridge over Nallah Aripath in Km 10th of Gopalpora 2 R&B Department R&B 190.00 68.00 54.57 100% - Tailwani Issue Wangam road (Balwat Bridge)

Construction 3x25 Mtr span steel girder bridge over 3 R&B Department R&B 550.51 384.68 222.00 80% Jun-21 Bringi on Sagam Kandiwara road

Construction 2x25 Mtrs span steel girder bridge over 4 R&B Department R&B 268.31 236.31 18.41 40% May-21 nallah Aripath at Noonwani

Construction of 2 x25 mtr span steel girder bridge 5 R&B Department R&B 232.00 46.00 33.48 100% - over Nallah Bringi at Village Poru Goihard

6 Construction/Upgradation of Ohe Kantigund R&B Department R&B 170.42 93.40 93.06 100% -

7 Improvements of Ohe Piasan road R&B Department R&B 144.10 89.21 83.63 100% -

8 Construction of road from Sunbari to Hill Bund R&B Department R&B 68.90 53.99 46.84 100% -

9 Improvement of Chakilpora Thimran road R&B Department R&B 165.00 73.04 63.21 100% -

Upgradation/Strengthening of Larnoo Draway road 10 R&B Department R&B 124.10 40.96 40.96 100% - including link

Construction of road from to Damhal via 11 R&B Department R&B 244.95 79.72 50.78 100% - Hardpora

12 Construction of road from Shangus to Andoo road R&B Department R&B 198.15 144.15 142.69 100% - Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9

13 Construction of road from Kadpora road R&B Department R&B 243.36 216.91 65.04 80% Jun-21

Construction of road from Goriwan to Gohihard via 14 R&B Department R&B 103.13 78.15 15.17 60% May-21 Wandevalgam

Construction of road from interior road at 15 R&B Department R&B 222.48 207.89 107.48 65% Jun-21 Boontooru

Upgradation of link road from High School Gohan 16 R&B Department R&B 153.00 147.90 78.20 65% Jun-21 to Malmarg

17 Upgradation of Mohripora Kandiwara Soaf road R&B Department R&B 555.81 365.10 255.27 90% May-21

Construction of road from Ranipora Rakhi Brah 18 R&B Department R&B 430.02 303.89 253.33 100% - Deethu Sonach road

19 Upgradation of interior raods at Watnard R&B Department R&B 150.07 141.46 0.00 70% May-21

20 Construction of Khull Brah Kralgund road R&B Department R&B 117.46 111.06 67.21 100% -

21 Construction of Brah Dawoodpora Road R&B Department R&B 134.10 114.10 56.80 100% -

22 Construction of Arhama Badasgam road R&B Department R&B 127.88 71.63 67.28 100% -

Construction of 1x37 Mtr span girder bridge at 23 R&B Department R&B 137.37 69.30 60.654 100% - Lalipora to Khanland. (balance cost) Construction of 2x30 Mtr span bridge at Badasgam 24 R&B Department R&B 531.00 225.27 167.287 100% - A to Badsagam B over Bud khul Nallah.

Construction of 2x30 mtr span steel girder foot 25 R&B Department R&B 314.09 155.62 116.829 100% - bridge at Sadoora Chopan Mohalla.

Construction of 3x30m Span steel girder bridge at 26 R&B Department R&B 504.41 302.10 302.10 100% - Nowpora Keeri Lonepora on Nallah Sandran.

Construction of 2x30m Span steel girder bridge at 27 R&B Department R&B 551.00 322.95 270.00 85% .March-21 Bonagund Zamalgam on nallah Sandran. Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9

Construction of 3x20m Span steel girder bridge at 28 R&B Department R&B 524.00 94.70 13.26 97% May, 21 Reshipora Hergawas on nallah sandran.

Up-gradation of Mandipora Changoo Chinar 29 R&B Department R&B 345.69 299.19 91.47 40% Apr-21 links.(4.00 Kms)

30 Up-gradation of Town. R&B Department R&B 548.59 437.31 0% Dec-21

Construction of 1x25 Mtr Span RCC Steel Girder 31 R&B R&B Division Khanabal 167.06 67.56 76.56 100% - bridge between Guree and keripora Bijbehara.

Construction of overhead Pedestrain Crossing at 32 R&B R&B Division Khanabal 150.00 79.00 79.00 100% - Biejbehara on NH.

Construction of 1x15 Mtr Span Steel Girder bridge 33 at Hanjipora Guree on Km. 1st of Guree Aader R&B R&B Division Khanabal 150.00 101.00 175.00 68% Feb-21 Seepan road.

Construction of Suspension Foot Bridge over River 34 R&B R&B Division Khanabal 383.00 318.00 191.00 50% Jul-21 Jehlum at Padshahi Bagh Bijbehara

Construction of 1X10 Mtr Span Steel Girder bridge 35 R&B R&B Division Khanabal 173.09 159.09 127.00 80% Mar-21 over Katoo Satkipoora Nallah at Katoo village.

Construction of Steel Trussed Jeepable Bridge at 36 R&B R&B Division Khanabal 295.00 285.00 229.75 100% - Bangidar .

Construction of overhead Foot Bridge from 37 R&B R&B Division Khanabal 132.00 127.00 95.00 85% Feb-21 Amusement Park to Golf Course at .

Construction of Seer Numbal Bridge including 38 R&B R&B Division Khanabal 569.08 569.08 0.00 0% Mar-22 approaches on either side

39 Mini Secretariat Bijbehara R&B R&B Division Khanabal 362.08 159.58 202.50 90% Mar-21

Total 10693.06 6962.34 4114.76 Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9 III. Housing & Urban Development Department. CONSTRUCTION OF COMMUNITY HALL AT 1 ULB, R&B 68.00 46.00 44.50 100% - ASHAJIPORA

3 SRTC SHOPPING COMPLEX ANTNATNAG ULB, Kashmir R&B 1926.00 1142.00 1296.00 70% -

RASOOL MIR MEMORIAL HALL, DOORU 2 ULB, Kashmir R&B 196.3400 78.7700 97% Mar-21 VERINAG Drainage Scheme old Town Bijbehara Phase II 4 H&UDD R&B 684.58 443.44 55% Mar-21 Including Old Bus Adda 5 Drainage Scheme Mattan H&UDD R&B 496.37 476.75 `26% Jul-21 Total 3371.29 2186.96 1340.50 IV. Health: 1 NTPHC Aishmuqam (JKPHC) Health JKPHC 188.000 168.000 80.00 45% June.-21 2 NTPHC Kehribal(JKPHC) Health JKPHC 188.000 168.000 94.00 45% May-21 3 NTPHC (JKPHC) Health JKPHC 226.970 18.420 226.79 100% - 4 NTPHC Hiller(JKPHC) Health JKPHC 188.000 168.000 150.00 80% Apr-21 5 NTPHC Karawa Rampora(JKPHC) Health JKPHC 188.000 173.000 140.00 80% Apr-21 6 PHC at Watnard(JKPHC) Health JKPHC 379.880 375.000 180.00 45% Jun-21 7 PHC Kandiwara(JKHB) Health JKHB 250.000 220.000 36.20 37% Oct-21 8 Construction of NTPHC at Hatigam Health JKHB 188.000 178.000 48.50 15% Dec-21 9 PHC SADIWARA Health JKHB 285.000 112.640 72.50 85% Apr-21

10 NTPHC Nanil(SICOP) Health SICOP 189.700 154.480 154.48 95% Apr-21

Total 2271.550 1735.540 1182.470 V. Sports Council:

Development of sports complex at Nilandrusu 1 J&K Sports council J&K Sports council 1179.00 1179.00 300.00 40% Nov-21 Bijbehara Anantnag.

2 Upgradation of play field at Marhama Bijbehara J&K Sports council J&K Sports council 83.00 83.00 33.20 52% Apr-21

3 Upgradation of play field at Munjhara Bijbehara J&K Sports council J&K Sports council 81.00 81.00 38.40 62% Apr-21

Development of oplay field at Panzmulla Anantnag 4 J&K Sports council J&K Sports council 19.00 19.00 19.00 100% - by way of earth work and filling. Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9

Development of play field at by way of 5 J&K Sports council J&K Sports council 7.00 7.00 4.90 100% - levelling.

Extention of play field at Pahalgam Anantnag by way of earth work in cutting and filling,dismantling 6 of existing fencing and damaged building and J&K Sports council J&K Sports council 19.00 19.00 18.00 100% - construction of chain link fencing around the extended

Development of play field by way of chain link 7 J&K Sports council J&K Sports council 32.00 31.00 28.60 95% Mar-21 fencing at Shangus Nowgam.

Development of play field at Wularhama Pahalgam 8 Anantnag by way of Earth work in cutting and J&K Sports council J&K Sports council 36.00 36.00 36.00 100% - filling.

9 Lighting of Mehandi kadal stadium. J&K Sports council J&K Sports council 75.00 75.00 75.00 100% -

10 Lighting of seer hamdan play field J&K Sports council J&K Sports council 75.00 75.00 75.00 100% -

Construction of new sports stadium at chandrigam 11 J&K Sports council J&K Sports council 212.00 200.00 80.00 55% May-21 Pahalgam.

Total 1818.000 1805.000 708.100 VI. Education:

Construction of Additional Accommodation to HSS 1 Education R&B 99.19 29.19 86.36 100% - Nanil Anantnag

Const. of 08 Roomed Double Storey Building at HS 2 Education R&B 78.19 48.19 61.98 90% Feb.21 Lukhbhawan Doru Shangus Engg. Wing of Education 3 Education 80.46 54.12 45.00 90% Feb.21 (KGBV Model II) Department. Construction of 09 Roomed Building (Section II) at Engg. Wing of Education 4 Education 85.55 55.55 70.00 100% - Govt. Girls High School Doru Department. Const. of 06 Roomed Building at MS Hunumapora Engg. Wing of Education 5 Education 45.65 35.65 37.30 100% - Zone Srigufwara Department. Providing of Water Supply to 207 uncovered schools 6 Education PHE Department 188.56 - of Anantnag Total 389.040 411.260 300.640 Estimated ApprovedCost by Name of the Name of the Executing work done Present Status Target date of S. No Name of the languishing project Cost JKIDFC under LP department Agency ₹ in lakhs (%age) completion ₹ in lakhs ₹ in lakhs

1 2 3 4 5 6 7 8 9 VII. a. PDD - KPDCL:

Ending March 1 Providing of Reliable Power Supply to Pahalgam KPDCL KPDCL STD Bijbehara 576.2 285.7 0 70% 2021

System Improvement Scheme in Dooru KPDCL ED 2 KPDCL 371.13 171.1 349.46 100% - Constituency. Anantnag Segregation of 11KV Larnoo feeder from R/Stn 3 KPDCL KPDCL 19.5 9 0 100% - Dandipora 4 Segregation of 11KV Hiller feeder. KPDCL KPDCL 8.16 13.5 0 0% Feb.21

Segregation of 11KV Essential feeder from R/Stn 5 KPDCL KPDCL 7.53 7.53 0 100% - Sangam

6 Segregation of 11KV Salia feeder from R/Stn Salia KPDCL KPDCL 0 4.1 0 100% -

Segregation of 11KV Ashmuqam feeder from R/Stn 7 KPDCL KPDCL 0 4.1 0 100% - Ashmuqam Total 982.520 495.030 349.460 b. J&K Power Transmission Corporation Ltd J&K Power Relocation of Tower No. 50 (SZ+6) of 220 KV(DC) J&K Power Transmission 1 Transmission 130.37 105.37 105.37 100% - KPTL Corporation Ltd Corporation Ltd c. T&LD - II Renovation/Modernization and augmentation of 130 1 T&LD-II T&LD-II 311.99 311.99 95% Feb.21 MVA Grid Station Wanpoo Total 1424.880 912.390 454.830 VIII. I&C: District Industries 1 Industrial Estate Mehmoodabad Dooru Centre SICOP 964.00 492.00 99.51 90% Mar-22 Anantnag Office Building of Assistant Director Handicrafts 2 Handicrafts SICOP 192.73 62.000 - 100% - Office Anantnag Total 1156.730 554.000 99.510 G.Total 41295.570 28752.450 12620.290