The Medupi Power Plant Project of Eskom

Total Page:16

File Type:pdf, Size:1020Kb

The Medupi Power Plant Project of Eskom AFRICAN DEVELOPMENT BANK EXECUTIVE SUMMARY Of SOUTH AFRICA: ENVIRONMENTAL IMPACT ASSESSMENT FOR THE MEDUPI POWER PLANT PROJECT OF ESKOM 1 July 2009 Table of Contents Page No. 1. Introduction 3 2. Project description 3 3. Policy legal and administrative framework 4 4. The need and justification of the project 5 5. Project Alternatives 6 6. Description of the Project Environment 7 7. Potential Impacts and Mitigation Measures 10 8. Public Consultations and Disclosure 15 9. Environmental management and monitoring plans 16 10. Environmental enhancement & Complementary Initiatives 18 11. Conclusion 20 12. References 20 2 1. Introduction In order to meet the objectives as set out in the South African Energy Policy as well as to meet developmental and socio-economic objectives in South Africa, the country needs to optimally use the available energy resources. Eskom is required to respond to the longer term growing electricity demand of approximately 3% per annum. The construction of a Medupi coal-fired power station in the Lephalale (previously Ellisras) area was identified as the most favored feasible option for the first new power station, that is proposed to operate at an installed capacity of approximately 4,800 MW. The following presents a summary of the ESIA of the MEDUPI power station project. Its contents include: i) Project Description, (ii) Policy Legal and Administrative framework, (iii) The need and justification of the Project, (iv) Project Alternatives, (v) Description of the Project Environment, (vi) Potential Impacts and Mitigation, (vii) Public Consultations and Disclosure, (viii) Environmental & Social Management and Monitoring plans (ix) Environmental Enhancement & Complementary Initiatives, (x) Conclusion and (xi) References. 2. Project Description The Power Station is proposed to ultimately have a maximum installed capacity of up to 4800 MW (6 x 800 MW units). The power plant and associated plant (terrace area) would require an area of approximately 700 ha, and an additional estimated 500 - 1000 ha would be required for ancillary services, including ash disposal facilities (alternate ash disposal options are, however, currently being investigated). The proposed power station will utilize a range of technologies pertaining to cooling, combustion and pollution abatement. The proposed power station will be a dry-cooled station. The use of dry-cooled technology is necessitated as a result of South Africa being a water scarce country and limited water availability in the area. The power station would be a zero liquid effluent discharge station, particulate emissions will be less than 50mg/Sm3 and due to the relatively low sulphur content of the coal and local air quality sulfur dioxide emissions will not have a significant impact on health. The plant will be Flue Gas Desulphurization (FGD) ready, a decision and timing for retrofitting the power station with FGD will be based on ambient air quality monitoring results, South African regulations including proposed emission limits and water availability. The power station will source coal from the local coalfields, and it would be delivered to the power station via conveyor belts. The coal to Medupi will be supplied through a brownfields expansion of Grootegeluk mine with mining from the existing opencast pit continuing at an accelerated rate. The coal beneficiation process will be handled via two new dense medium facilities (Grootegeluk 7 and Grootegeluk 8 beneficiation plants) which will be constructed at the mine. The Environmental Impact Assessment for the coal mine and transmission lines have been completed in separate EIA processes1. 1 The ESIA for the Transmission lines (not part of the project) is a separate process and has been completed and received the approval of the Department of Environment and Tourism (DEAT). 3 All Eskom's existing operational coal-fired power stations utilize pulverized fuel technology (PF). The specific technology employed in the Medupi power plant would be super critical boilers which would heat water to produce steam within a pressure and temperature range of 24-30 MPa and 5380C – 6000C respectively. The plant will be dry cooled and installed with low NOx burners and pulse jet fabric filters. The proposed power station would be similar to the existing Matimba Power Station in terms of operation, design and dimensions. The power station structure would be approximately 130 m high and approximately 500 m wide. The required stacks would be approximately 220 m in height. Direct-cooling technology will be applied; hence no cooling towers will be constructed. Other related infrastructure would include a coal stockpile, conveyor belts, and an ash dump, with infrastructure such as transmission lines being planned to integrate the station into the national electricity grid. Annex 1 illustrates the plant location while Annex 2 shows the plant layout. 3. Policy, legal and administrative framework According to AfDB environmental and social assessment procedures, this project is assigned Category 1. The ESIA conforms to the Environmental and Social Assessment Procedures (ESAP, 2001) of the African Development Bank and the World Bank 1998 Pollution Prevention and Abatement Handbook (PPAH, 1998). In terms of the Environmental and Social Impact Assessment (ESIA) Regulations published in terms of the Environment Conservation Act (No 73 of 1989), Eskom Holdings Limited requires authorization from the National Department of Environmental Affairs and Tourism (DEAT) in consultation with the Limpopo Department of Economic Development, Environment and Tourism (LDEDET) for the undertaking of the proposed project. In order to obtain authorization for this project, comprehensive, independent environmental studies have been undertaken in accordance with the ESIA Regulations. An ESIA process for the proposed coal-fired power station and ancillary infrastructure has been undertaken in accordance with the requirements of all relevant South African legislation including inter alia, those of: • Environment Conservation Act (No 73 of 1989); • National Environmental Management Act (No 107 of 1998); • National Water Act (No 36 of 1998); • National Heritage Resources Act (No 25 of 1999); • Occupational Health and Safety Act (No 85 of 93); • Atmospheric Pollution Prevention Act (No 45 of 1965); • National Environmental Management: Air Quality Act 39 of 2004; • White Paper on Energy Policy, GN 3007, 17/12/1998; • South Africa had its Long Term Mitigation Strategy (LTMS) on Climate Change approved by the South African cabinet in 2008; • The March 2009 Climate Change Summit laid the foundation for a participatory process to shape the way South Africans respond to climate change following; • The South African government has started drafting its policy framework for climate change; 4 • White Paper on Integrated Pollution and Waste Management for South Africa (January 2000); and • National Waste Management Strategy documents (October 1999). It is noted that Provisional ambient air quality limits for South Africa were published in Schedule 2 of the National Environmental Management: Air Quality Act. Draft ambient air quality standards which will replace the provisional limits were published for public comment in March 2009, and should be legislated later in 2009. South African ambient air quality limits are similar to those in the EU and the WHO Guidelines The environmental studies (Ref 1,2, and 3)followed a two-phased approach in accordance with the ESIA Regulations published in terms of the Environment Conservation Act (No 73 of 1989) i.e.: • Phase 1: Environmental Scoping Study • Phase 2: Environmental Impact Assessment (EIA) No fatal flaws were identified since the impacts can be mitigated to acceptable levels. The DEAT has granted to Eskom the Record of Decision (ROD) which is like an environmental permit. 4. The Need and Justification for the Proposed Project Policy Considerations and Strategic Planning The South African Energy Policy, published in December 1998 by the Department of Minerals and Energy (DME) identifies five key objectives, namely: • Increasing access to affordable energy services; • Improving energy sector governance; • Stimulating economic development; • Managing energy-related environmental impacts; and • Securing supply through diversity. In order to meet these objectives and the developmental and socio-economic objectives in South Africa, the country needs to optimally use the available energy resources. The South African Government, through the Department of Minerals and Energy (DME), the National Electricity Regulator (NER) and Eskom are required to address what can be done to meet these electricity needs both in the short- and long- term. Growth in electricity demand and reduction in surplus capacity The demand for electricity in South Africa has grown, on average, at more than 4% up until 2008, with a concomitant reduction in the surplus generating capacity. The DME, NERSA and Eskom planning processes all indicate that South Africa will require an additional 5 000 MW of electricity within the next 5 years, with this consisting of both base load electricity generating capacity and peaking electricity generating capacity. The processes also indicate that new base load capacity will be required by approximately 2010. In 2004, the South African Cabinet took the decision that Eskom will build approximately 70% of the new capacity required in South Africa. The balance is expected to come from Independent Power Producers (IPPs). 5 For base load capacity,
Recommended publications
  • The Case of Kusile FINAL
    THE EXTERNAL COST OF COAL -FIRED POWER GENERATION: The case of Kusile Prepared by: • Business Enterprises at University of Pretoria (Pty(Pty)) LLtLtdtdd Prepared for: • Greenpeace Africa and Greenpeace International DATE: 29 September 2011 PO Box 14679 Hatfield 0028 University of Pretoria Main Campus, Prospect Street, Hatfield, Graduate Centre, Ground Floor, Entrance 1.82 T: +27 (12) 420 4245 F: +27 (12) 362 5270 TABLE OF CONTENTS 1. Introduction 5 2. Background, problem statement and study limitations 7 3. The externality cost of coal-fired power generation: a sectoral overview 9 3.1 Health 9 3.2 Climate change 11 3.3 Water 13 3.4 Mining 15 4. Results 17 5. Conclusion 19 6. References 21 NOTE: For access to the annexes listed below, please refer to the Greenpeace Africa website: www.greenpeaceafrica.org Annex 0 (Background): Coal and coal-fired power generation in South Africa Annex 1: The health costs of coal-fired power generation in South Africa Annex 2: Climate change: the opportunity cost of Medupi and Kusile power stations Annex 3: Estimating the opportunity cost of water for the Kusile and Medupi coal-fired electricity power plants in South Africa Annex 4: The external costs of coal mining: the case of collieries supplying Kusile power station ACKNOWLEDGEMENTS The authors gratefully acknowledge comments provided by the Greenpeace Africa and Greenpeace International review teams, and by four workshop panellists, Prof Jane Olwoch, Prof Kuku Voyi, Prof Ban Farrell and Mr Meiring du Plessis. This research was financially supported
    [Show full text]
  • Energy and Water
    ENERGY AND WATER 137 Pocket Guide to South Africa 2011/12 ENERGY AND WATER Energy use in South Africa is characterised by a high level of dependence on cheap and abundantly available coal. South Africa imports a large amount of crude oil. A limited quantity of natural gas is also available. The Department of Energy’s Energy Policy is based on the following key objectives: • ensuring energy security • achieving universal access and transforming the energy sector • regulating the energy sector • effective and efficient service delivery • optimal use of energy resources • ensuring sustainable development • promoting corporate governance. Integrated Resource Plan (IRP) The IRP lays the foundation for the country’s energy mix up to 2030, and seeks to find an appropriate balance between the expectations of different stakeholders considering a number of key constraints and risks, including: • reducing carbon emissions • new technology uncertainties such as costs, operability and lead time to build • water usage • localisation and job creation • southern African regional development and integration • security of supply. The IRP provides for a diversified energy mix, in terms of new generation capacity, that will comprise: • coal at 14% (government’s view is that there is a future for coal in the energy mix, and that it should continue research and development to find ways to clean the country’s abundant coal resources) • nuclear at 22,6% • open-cycle gas turbine at 9,2% and closed-cycle gas turbine at 5,6% • renewable energy carriers, which include hydro at 6,1%, wind at 19,7%, concentrated solar power at 2,4% and photovoltaic at 19,7%.
    [Show full text]
  • New Build News
    New BuildNews Issue 4 January 2008 Introduction This is a monthly update on Eskom's current new build projects. This includes both power station and transmission line projects. For further details, please email [email protected] Project Update Ankerlig Open Cycle Gas Turbine Station Location: Atlantis, Industrial Area, north of Cape Town This station has been in full commercial operation since 25 June 2007 - four units rated at 148 MW each are now being operated by Eskom's Generation Division. The total output for both OCGT stations is 1 036MW - 592 MW at Ankerlig and 444 MW at Gourikwa. The building of five additional units of 150 MW each at Ankerlig started on 8 August 2007. The team has completed the groundwork for the high-voltage yard and the base for the one fuel tank. The construction team is currently completing drains, building a base for the second fuel tank and installing power for the construction site. Gourikwa Open Cycle Gas Turbine Station Location: Petro SA area, west of Mossel Bay The first sod was turned on 24 January 2006, and the station has been in full commercial operation since 8 June 2007 - three units rated at 148 MW each are now being operated by Eskom's Generation Division. The second phase involves the building of two more 150 MW Units. Earthworks started on 24 September 2007. Construction has started on the new The ground and terrace work for the high-voltage yard, terrace level and drainage has units at Gourikwa power station started. Medupi power station Location: To the west of Lephalale, Limpopo Province This is a coal fired power plant project comprising of 6 units rated in total at 4 788MW installed capacity.
    [Show full text]
  • Transmission Ten-Year Development Plan 2013-2022 Transmission Ten-Year Plan 2013 – 2022 > FOREWORD by GROUP EXECUTIVE
    Transmission Ten-Year Development Plan 2013-2022 Transmission Ten-Year Plan 2013 – 2022 > FOREWORD BY GROUP EXECUTIVE “I would also like to take this opportunity to thank the team that has worked and continues to work on the development of these plans.” A reliable electricity supply of acceptable quality is essential for the developed by Eskom and IPPs must be connected to the network. economic development of South Africa. It is also a prerequisite The first two phases of preferred bidders for the Department for socio-economic development, as it paves the way to access to of Energy’s REFIT renewable energy programme (wind, solar education, improved nutrition and health care, and jobs, amongst photovoltaic, solar thermal, etc.) have been announced to help others. The transmission system plays a vital role in the delivery meet South Africa’s commitment to reduce carbon emissions. of a reliable, high quality electricity supply throughout South Africa Thirdly, new loads need to be connected to the network. and the region, by delivering electricity in bulk to load centres The provision of a reliable electricity supply, which will enable South and very large end-users. From there, the distribution networks Africa to meet its economic growth targets, requires significant owned by Eskom and municipalities deliver electricity to end-users. capital investment, which is ultimately funded by electricity The transmission system needs to be well-maintained to deliver a consumers through the tariff. There is a need for stakeholders reliable supply of electricity, and it also needs to be strengthened to understand what is required to ensure a reliable and secure to meet changing customer needs.
    [Show full text]
  • Spatial Transformation: Are Intermediate Cities Different? South African Cities Network: Johannesburg
    CENTRE FOR DEVELOPMENT SUPPORT SENTRUM VIR ONTWIKKELINGSTEUN ACKNOWLEDGEMENTS Lead authors: Lochner Marais (University of the Free State) Danie Du Plessis (Stellenbosch University) Case study authors: Drakenstein: Ronnie Donaldson (Stellenbosch University) King Sabata Dalindyebo: Esethu Ndzamela (Nelson Mandela University) and Anton De Wit (Nelson Mandela University Lephalale: Kgosi Mocwagae (University of the Free State) Matjhabeng: Stuart Denoon-Stevens (University of the Free State) Mahikeng: Verna Nel (University of the Free State) and James Drummond (North West University) Mbombela: Maléne Campbell (University of the Free State) Msunduzi: Thuli Mphambukeli (University of the Free State) Polokwane: Gemey Abrahams (independent consultant) Rustenburg: John Ntema (University of South Africa) Sol Plaatje: Thomas Stewart (University of the Free State) Stellenbosch: Danie Du Plessis (Stellenbosch University) Manager: Geci Karuri-Sebina Editing by Write to the Point Design by Ink Design Photo Credits: Page 2: JDA/SACN Page 16: Edna Peres/SACN Pages 18, 45, 47, 57, 58: Steve Karallis/JDA/SACN Page 44: JDA/SACN Page 48: Tanya Zack/SACN Page 64: JDA/SACN Suggested citation: SACN. 2017. Spatial Transformation: Are Intermediate Cities Different? South African Cities Network: Johannesburg. Available online at www.sacities.net ISBN: 978-0-6399131-0-0 © 2017 by South African Cities Network. Spatial Transformation: Are Intermediate Cities Different? is made available under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License. To view a copy of this license, visit http://creativecommons.org/licenses/by-nc-sa/4.0/. 2 SPATIAL TRANSFORMATION: ARE INTERMEDIATE CITIES DIFFERENT? Foreword As a network whose primary stakeholders are the largest cities, the South African Cities Network (SACN) typically focuses its activities on the “big” end of the urban spectrum (essentially, mainly the metropolitan municipalities).
    [Show full text]
  • Written Statement of Mxolisi Mgojo, the Chief Executive Officer Of
    1 PUBLIC ENTERPRISES PORTFOLIO COMMITTEE INQUIRY INTO ESKOM, TRANSNET AND DENEL WRITTEN STATEMENT OF MXOLISI MGOJO, THE CHIEF EXECUTIVE OFFICER OF EXXARO RESOURCES LIMITED INTRODUCTION ...................................................................................................... 2 COST-PLUS MINES VERSUS COMMERCIAL MINES .......................................... 5 THE SO-CALLED “PRE-PAYMENT” FOR COAL ................................................. 9 PREJUDICE TO EXXARO’S COST-PLUS MINES AND MAFUBE ..................... 11 Introduction ........................................................................................................... 11 Arnot mine ............................................................................................................. 12 Eskom’s failure to fund land acquisition ................................................................. 12 Non-funding of operational capital at Arnot ............................................................ 14 The termination of Arnot’s CSA .............................................................................. 15 Conclusion of the Arnot matters ............................................................................. 19 Mafube mine.......................................................................................................... 19 Matla mine ............................................................................................................. 21 Non-funding of capital of R1.8 billion for mine 1 ...................................................
    [Show full text]
  • International Bank for Reconstruction and Development International Development Association
    International Bank for Reconstruction and Development International Development Association INSP/64977-ZA MANAGEMENT REPORT AND RECOMMENDATION IN RESPONSE TO THE INSPECTION PANEL INVESTIGATION REPORT SOUTH AFRICA ESKOM INVESTMENT SUPPORT PROJECT (IBRD LOAN NO. 78620-ZA) March 2, 2012 MANAGEMENT REPORT AND RECOMMENDATION IN RESPONSE TO THE INSPECTION PANEL INVESTIGATION REPORT OF THE SOUTH AFRICA ESKOM INVESTMENT SUPPORT PROJECT (IBRD LOAN NO. 78620-ZA) Pursuant to paragraph 23 of the Resolution Establishing the Inspection Panel (IBRD Resolution 93-10 and IDA Resolution 93-6), attached for consideration by Executive Directors is Management’s Report and Recommendation in response to the findings set out in the Investigation Report No. 64977-ZA dated November 21, 2011, of the Inspection Panel on the captioned Project (Eskom Investment Support Project, IBRD Loan No. 78620-ZA). MANAGEMENT REPORT AND RECOMMENDATION IN RESPONSE TO THE INSPECTION PANEL INVESTIGATION REPORT NO. 64977-ZA SOUTH AFRICA ESKOM INVESTMENT SUPPORT PROJECT (IBRD LOAN NO. 74920-ZA) CONTENTS Abbreviations and Acronyms ............................................................................................ iv Executive Summary ............................................................................................................ v I. Introduction ............................................................................................................. 1 II. The Project .............................................................................................................
    [Show full text]
  • Waterberg-Bojanala Priority Area Air Quality Management Plan: Threat Assessment
    Part 2 Waterberg-Bojanala Priority Area Air Quality Management Plan: Threat Assessment This report has been produced for the Department of Environmental Affairs by uMoya-NILU Consulting (Pty) Ltd. The authors are Mark Zunckel, Atham Raghunandan, Sarisha Perumal, Yegeshni Moodley and Benton Pillay. No part of the report may be reproduced in any manner without written permission from the Department of Environmental Affairs. This document should be cited as follows: Department of Environmental Affairs (DEA), 2014: Waterberg-Bojanala Priority Area Air Quality Management Plan: Threat Assessment, December 2014. ii EXECUTIVE SUMMARY The Minister of Water and Environmental affairs declared the Waterberg–Bojanala Priority Area (WBPA) on 15 June 2012 as the third National Priority Area (DEA, 2012a). The WBPA includes the Waterberg District Municipality (WDM) in the Limpopo Province and parts of the Bojanala Platinum District Municipality (BPDM) in the North West Province, and borders on Botswana. The WDM and Botswana have significant coal reserves that are largely unexploited with the Matimba Power Station and Morupule Power Station currently in operation. As a result, ambient air quality is relatively good. The National Development Plan 2030 (National Planning Commission, 2012), acknowledges that the lack of stable power to meet the energy demands is an impediment to economic growth in the region, proposing Strategic Infrastructure Projects (SIPs) to accelerated growth and development in the WDM. In addition, the Government of Botswana requires that the energy sector be augmented through the development of new coal-fired power plant generation capacity. The energy-based development initiatives in South Africa and Botswana pose a threat to the current state of ambient air quality in the region.
    [Show full text]
  • 2. DESCRIPTION of the PROPOSED PROJECT In
    Environmental Scoping Report for the proposed establishment of a New Coal-Fired Power Station in the Lephalale Area, Limpopo Province 2. DESCRIPTION OF THE PROPOSED PROJECT In order to be able to adequately provide for the growing electricity demand, Eskom propose to construct a new power station with a maximum capacity of 4 800 MegaWatts (MW) in the Lephalale area in the vicinity of the existing Matimba Power Station. Currently the project name for the new proposed power station is Matimba B, but the name will be changed should the project be approved. The power station will be coal-fired, and source coal from local coalfields. 2.1 The Proposed Matimba B Power Station Matimba B Power Station is proposed to ultimately have a maximum installed capacity of up to 4800 MW, but the first phase to be constructed and operated will be approximately half that installed capacity. The exact output will depend on the specification of the equipment installed and the ambient operating conditions. The footprint of the proposed new power station is still to be determined through final engineering and design, but has been indicated by Eskom that the new facility will be similar in size (ground footprint) to the existing Matimba Power Station. The power plant and associated plant (terrace area) would require an area of approximately 700 ha, and an additional approximate 500 - 1000 ha would be required for ancillary services, including ashing facilities (alternate ash disposal options are, however, currently being investigated). It is envisaged that the proposed power station will utilise a range of technologies pertaining to cooling, combustion and pollution abatement.
    [Show full text]
  • Literature Review: Public Health and Ecological Effects of Substances Emitted to Air from Power Plants Documents Published 2013-2020
    REPORT Literature Review: Public Health and Ecological Effects of Substances Emitted to Air from Power Plants Documents Published 2013-2020 Submitted to: Katie Duffett, Project Manager, Clean Air Strategic Alliance 9915-108 Street NW, 1400 Edmonton, Alberta T5K 2G8 Submitted by: Golder Associates Ltd. Suite 200 - 2920 Virtual Way, Vancouver, British Columbia, V5M 0C4, Canada +1 604 296 4200 20397046-001-R-Rev0 18 March 2021 Classification: Protected A 18 March 2021 20397046-001-R-Rev0 Distribution List 1 e-copy Clean Air Strategic Alliance - Health and Environmental Assessment Task Group (HEAT Group) 1 e-copy Golder Associates Ltd. i Classification: Protected A 18 March 2021 20397046-001-R-Rev0 Executive Summary Golder Associates Ltd. (Golder) was retained by the Clean Air Strategic Alliance (CASA) to conduct a literature review on the public health and ecological effects of substances known to be emitted into the air from electricity generation using various resource types (e.g., coal, biomass, fuel oil, waste) from power plants (not limited to stack emissions). The objective of the literature review was to identify new information published from 2013 to 2020 to aid the 2018 Five-Year Review of the 2003 Emissions Management Framework for Alberta Electricity Sector. Golder conducted a search of white and grey literature for the literature review. White literature included primary peer-reviewed journal articles while grey literature included literature published by provincial, federal, and international organizations. Relevant articles were scored using the ‘Checklist for assessing the quality of quantitative studies' (herein referred to as the “Checklist”) developed at the Alberta Heritage Foundation for Medical Research1.
    [Show full text]
  • Renewable Energy Choices and Their Water Requirements in South Africa
    Journal of Energy in Southern Africa 26(4): 80–92 DOI: http://dx.doi.org/10.17159/2413-3051/2014/v25i4a2241 Renewable energy choices and their water requirements in South Africa Debbie Sparks Amos Madhlopa Samantha Keen Mascha Moorlach Anthony Dane Pieter Krog Thuli Dlamini Energy Research Centre, University of Cape Town, Cape Town, South Africa Abstract tive of this study was to investigate and review South Africa is an arid country, where water supply renewable energy choices and water requirements is often obtained from a distant source. There is in South Africa. Data were acquired through a com- increasing pressure on the limited water resources bination of a desktop study and expert interviews. due to economic and population growth, with a Water withdrawal and consumption levels at a given concomitant increase in the energy requirement for stage of energy production were investigated. Most water production. This problem will be exacerbated of the data was collected from secondary sources. by the onset of climate change. Recently, there have Results show that there is limited data on all aspects been concerns about negative impacts arising from of water usage in the production chain of energy, the exploitation of energy resources. In particular, accounting in part for the significant variations in the burning of fossil fuels is significantly contributing the values of water intensity that are reported in the to climate change through the emission of carbon literature. It is vital to take into account all aspects of dioxide, a major greenhouse gas. In addition, fossil the energy life cycle to enable isolation of stages fuels are being depleted, and contributing to where significant amounts of water are used.
    [Show full text]
  • Mercury Emissions from South Africa's Coal-Fired Power Stations
    Mercury emissions from South Africa’s coal-fired power stations Belinda L. Garnham*1 and Kristy E. Langerman1 1Eskom Holdings SOC Limited, Megawatt Park, 1Maxwell Drive, Sunninghill, Sandton, [email protected], [email protected] Received: 8 August 2016 - Reviewed: 3 October 2016 - Accepted: 2 November 2016 http://dx.doi.org/10.17159/2410-972X/2016/v26n2a8 Abstract Mercury is a persistent and toxic substance that can be bio-accumulated in the food chain. Natural and anthropogenic sources con- tribute to the mercury emitted in the atmosphere. Eskom’s coal-fired power stations in South Africa contributed just under 93% of the total electricity produced in 2015 (Eskom 2016). Trace amounts of mercury can be found in coal, mostly combined with sulphur, and can be released into the atmosphere upon combustion. Coal-fired electricity generation plants are the highest contributors to mer- cury emissions in South Africa. A major factor affecting the amount of mercury emitted into the atmosphere is the type and efficiency of emission abatement equipment at a power station. Eskom employs particulate emission control technology at all its coal-fired power stations, and new power stations will also have sulphur dioxide abatement technology. A co-beneficial reduction of mercury emissions exists as a result of emission control technology. The amount of mercury emitted from each of Eskom’s coal-fired power stations is calculated, based on the amount of coal burnt and the mercury content in the coal. Emission Reduction Factors (ERF’s) from two sources are taken into consideration to reflect the co-benefit received from the emission control technologies at the stations.
    [Show full text]