(I) Basic Information S. No. Item Details 1. Name of the project/s Proposed Expansion of Commercial Building Project, Promoted by M/s Vanchari Hotels Pvt. Ltd. At RIICO Plot No. CC-1,RIICO Industrial Area, Tehsil - , District , . 2. S. No. in the schedule Category „B‟ under item 8(a) of the schedule of Gazette Notification dated September 14th, 2006. 3. Proposed The proposed expansion will involve construction of capacity/area/length/tonnage to new tower. Thus after proposed expansion the project be handled/command area/lease will have total 4 Tower. The area statistics of area/number of wells to be proposed construction is tabulate below:- drilled Details of Proposed Construction S. Particular Existing After Proposed Expansion No. 1. Plot Area 21809.00 Sq. m. 21809.00 Sq. m. 2. Gross Built up Area 18686.13 Sq. m. 51105.10 Sq.m. 3. Permissible Ground 45 % of Plot Area 45 % of Plot Area 4. Coverage (9814.05 Sq. m.) (9814.05 Sq. m.) 5. Utilized Ground 19.26 % of Plot Area 40.95 % of Plot Area Coverage (4200.571 Sq. m.) (8930.671 Sq. m.) 2.00 of Plot Area 2.00 of Plot Area 6. Permissible FAR 43618.00 Sq. m. 43618.00 Sq. m. 0.685 of Plot Area 1.5963 of Plot Area 7. Utilized FAR (14936.982 Sq.m.) 34813.002 Sq. m. 8. Road Width 45 m and 30 m 45 m and 30 m 9. Permissible Height 97.50 m 97.50 m 19.95 m (Terrace Level) 16.75 m (Terrace Level) 10. Achieved Height 24.15 m (Mumty level) 19.75 m (Mumty level)

Total No. of Shops 98 Office, 402 Shops and 98 Office, 914 Shops and 134 11. and Rooms 16 Rooms Rooms

4. New/Expansion/Modernization Expansion project. 5. Existing Capacity / Area etc. Gross Built up Area 18686.13 Sq. m. (98 Office, 402 Shops and 16 Rooms) 6. Category of Project i.e. „A‟ or B „B‟ 7. Does it attract the general No

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 1 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

condition? If yes, please specify 8. Does it attract the specific No condition? If yes, please specify 9. Location Neemrana Plot/Survey/Khasra No. CC-1 Village RIICO Industrial Area Tehsil Neemrana District Alwar State Rajasthan 10. Nearest railway station/airport The proposed site is well connected through a road along with distance in Kms. network from two sides.  Rewari Railway Station is at a distance of about 33.00 km towards NE of proposed site.  Indira Gandhi International Airport is at a distance of at about 94.50 km towards NE of proposed site.  NH-71 B is at about 35.30 Km towards NE side of proposed site.  NH-8 is at about 1.70 Km towards ESE side of proposed site.  SH-14 is at about 12.50 Km towards SSW side of proposed site. 11. Nearest Town, city, District Nearest Town is Neemrana at about 1.80 Km towards Headquarters along with NW of project site. distance in Kms. head quarter I at abour 52.50 Km towards SE of project site. 12. Village Panchayats, Zila Panchayat Samiti Kendra, Main City, Neemrana, Parishad, Municipal Alwar - 301705, Municipal Corporation, U. I. T. Corporation, Local body [Local body] Nagar Vikas Nyas (U.I.T). (complete postal addresses with telephone nos. to be given) 13. Name of the applicant M/s Vanchari Hotels Pvt. Ltd. 14. Registered Address Plot No. CC-2,RIICO Industrial Area, Tehsil - Neemrana, District Alwar, Rajasthan 15. Address for correspondence: Name Mr. Prem Pal Singh Designation (Owner/ Partner/ Authorized Signatory CEO) M/s Vanchari Hotels Pvt. Ltd. Address Plot No. CC-2,RIICO Industrial Area, Tehsil - Neemrana, District Alwar, Rajasthan Pin Code 301705 E-mail [email protected] Telephone No. 0124-4045700

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 2 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

Fax No. 16. Details of Alternative Sites The Government Body “U. I. T.,” , sanctioned examined, if any. Location of the said land to M/s Stanford Developers for the these sites should be shown on a purpose of Construction of Group Housing at Village.- topo sheet. Gaadpur, Bhiwadi Tehsil-Neemrana, Distt.- Alwar Geographical location of the proposed project is- Latitude - 27°59'11.25"N Longitude - 76°23'24.40"E 17. Interlinked Projects No 18. Whether separate application of Not Applicable interlinked project has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves No approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation) Act, 1980? (b) The Wildlife (Protection) Act, 1972? (c) The C.R.Z Notification, 1991? 22. Whether there is any No Government Order/Policy relevant/relating to the site? 23. Forest land involved (hectares) No 24. Whether there is any litigation No pending against the project and /or land in which the project is proposed to be set up? (a) Name of the court (b) Case No. (c) Orders/directions of the Court, if any and its relevance with the proposed project.

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 3 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S. Information/ Checklist Yes/ Details thereof (with approximate no. confirmation No quantities/rates, wherever possible) with source of information data 1.1 Permanent or temporary change Yes Land use in land use, land cover or The proposed site is in the developing area of topography including increase in Neemrana Tehsil which has mixed land use intensity of land use (with pattern of residential and commercial use. The respect to local land use plan). area is having mixed land use pattern comprising of residential and commercial establishments. There will be minimal change in land use pattern of study area, and thus will not be inconsistent with the existing surroundings.. Yes Land cover Due to human activities, land cover is either directly affected from activity like construction of road-building leading to deforestation or indirectly from water diversion leading to lowering of the water table. The proposed project will not involve any deforestation; only small work of site clearance will be done in which some shrubs and grasses will be removed. It will be balanced by planed landscaping on the site. Excavation of soil will be involved. The total expected quantity of earthwork involved is about 3000 m³.The excavated soil will be balanced within site by back filling. Therefore the changes will be localized and insignificant. No Topography The site is plane and will not involve any leveling activities. The proposed site does not involve any major natural drainage channel of locality therefore no changes in drainage pattern are envisaged. 1.2 Clearance of existing land, No The proposed site is not having any structures vegetation and buildings? and vegetation. List of observed vegetations in study area is enclosed as Annexure XI. It is proposed to plant 167 trees in addition to shrubs. The proposed landscaping and plantation will have positive impact on the M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 4 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

prevailing environment. Details of flora are enclosed as Annexure- XI. 1.3 Creation of new land uses? No The proposed site is located in RIICO Industrial area Neemrana. The Neemrana Tehsil has mixed land use pattern of residential and commercial use. The proposed use of site is for residential. Therefore, the proposed project will not create new land uses that significantly differ from existing land use of locality as per the master plan. 1.4 Pre-construction investigations Yes The soil investigation was carried out. The e.g. bore houses, soil testing? detailed Soil investigation report is enclosed as Annexure No XVII. 1.5 Construction works? Yes The proposed expansion will involve construction of new tower. Thus after proposed expansion the project will have total 4 Tower. The area statistics of proposed construction is tabulate below:- Tower Wise Details Tower Common & No. of Level FAR GBUA Name Circulation Area Existing Towers Tower A G+1 1115.608 1482.408 366.8 Tower B G+2 1166.992 1189.71 224.173 Tower C Basement+G+4 12654.381 15954.01 3299.627 Proposed Tower Basement+ Lower Tower D 19876.02 32478.98 12602.96 Ground +G+4 Total 34813.001 51105.106 16493.56 1.6 Demolition works? No The proposed site is not having any structures which will need demolition. 1.7 Temporary sites used for Yes They will be housed in temporary houses construction works or housing of supported by flush WCs during construction construction workers? period only. 1.8 Above ground buildings, Yes The proposed maximum height of the project will structures or earthworks be 19.95 m upto Terrace Level and 24.15 m upto including linear structures, cut Mumty level. Expected quantity of earth work involved is about 3000 M3. and fill or excavations. 1.9 Underground works including No No tunneling activity is involved. mining or tunneling? 1.10 Reclamation works? No No reclamation works involved 1.11 Dredging? No Not involved 1.12 Offshore structures? No Not applicable

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 5 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

1.13 Production and manufacturing No Not applicable processes? 1.14 Facilities for storage of goods or Yes Temporary stores or sheds will be constructed for materials? storage of construction materials. 1.15 Facilities for treatment or Yes STP for treatment of sewage. STP treated effluent disposal of solid waste or liquid will be used for gardening and flushing of toilets. effluents? All excess treated water (25.385 KLD) will be discharged in drains maintained by UIT after taking necessary permission from UIT. All solid waste from different sections will be collected in separate bins. The non-organic waste shall be disposed off to authorized vendors. The organic waste will be converted into manure and used within premises for green belt development. 1.16 Facilities for long term housing Yes Cabins for watchmen, gardeners etc and persons of operational workers? engaged in essential services. 1.17 New road, rail or sea traffic No The existing infrastructure is sufficient to catch- during construction or operation? up for the need of such a small project, insignificant increase in traffic for transport of men & material is envisaged. 1.18 New road, rail, air, waterborne or No The proposed project site has well connectivity other transport infrastructure through road; rail and air-transport therefore will including new or altered routes not require any change in existing infrastructure. and stations, ports, airports etc? 1.19 Closure or diversion of existing No No public road or infrastructure is crossing or transport routes or infrastructure within the proposed site. leading to changes in traffic movements? 1.20 New or diverted transmission No No pipeline or transmission line is crossing or lines or pipelines? within the proposed site. 1.21 Impoundment, damming, No The proposed site does not involve any major culverting, realignment or other natural drainage channel of locality therefore no changes to the hydrology of changes in drainage pattern are envisaged. watercourses or aquifers? 1.22 Stream crossings? No The proposed plot is small in size and no natural drain is crossing the plot. 1.23 Abstraction or transfers of water Yes Water will be taken from underground water from ground or surface waters? abstraction. No ground water will be abstracted without obtaining prior NOC from CGWA. An affidavit regarding same is attached as Annexure III. 1.24 Changes in water bodies or the No The excess treated water will discharged in sewer land surface affecting drainage line maintained by UIT after obtaining necessary

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 6 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

or run-off? permission. The proposed site does not involve any major natural drainage channel of locality therefore no such changes were envisaged. 1.25 Transport of personnel or Yes During construction phase material of materials for construction, construction will be transported to site from local operation or decommissioning? market and other sources depending on availability. During operation stage the transportation activities will be due to cars, two wheelers and other vehicles of the residents. 1.26 Long-term dismantling or No Not applicable, as the land is vacant. No decommissioning or restoration structures are present at the site; hence, no works? dismantling, decommissioning or restoration work is required. 1.27 Ongoing activity during No Not applicable decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in Yes During construction phase, there will be inward either temporarily or and outward movement of local labour in the permanently? construction site. However during the post construction phase, there will be regular movement of residents, visitors and other related persons. The Commercial project will house about 4300 persons which will not bring any significant increment in total population of locality. 1.29 Introduction of alien species? No Only the plant/ trees of local species and suitable for the region will be planted. 1.30 Loss of native species or genetic No There are no grown trees on the proposed site, diversity? some shrubs and grasses will be removed. The same will be amply compensated by proposed plantation and landscaping. 1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non- renewable or in short supply): S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 2.1 Land especially undeveloped Yes The proposed site is in developing urban area and or agricultural land (ha) the site has been converted for residential purpose by UIT and allocated to project proponent.

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 7 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

2.2 Water (expected source & Yes  During construction phase water requirement competing users) unit: KLD will be 16.00 KLD which will be met from authorized water suppliers.  During post construction phase daily water requirement will be about 217.939 KLD.  94.193 KLD- Fresh water from ground water abstraction after obtaining NOC from CGWA  123.745 KLD- Recycled water from STP. 2.3 Minerals (MT) No - 2.4 Construction material – stone, Yes The construction will involve use of Stone, Stone aggregates, and /soil Grit, Sand, bricks and timber. (expected source-MT) The Stone and Stone grit is available from various queries operative around Bhiwadi City. Details are enclosed as Annexure XXI. 2.5 Forests and timber (source – Yes Timber will be obtained from authorized local MT). timber merchant. 2.6 Energy including electricity During construction phase : 20 KW and fuels (source, competing Yes During operation phase: 3003 KW users) Unit: fuel (MT), energy The power will be received from JVVNL at 11 (MW) KV supply voltage, it will be stepped down to 0.433 KV through three transformers each of 1600 kVA rating To supplement above during power failure, it is proposed to provide Four D.G. Set, one of 250 kVA and500 kVA, two DG sets each of capacity 1000 kVA. 2.7 Any other natural resources Yes Solar energy will be utilized for lighting of (use appropriate standard common areas and solar water heaters for units) providing hot water to residents.

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S. No Information/checklist Yes Details thereof (with approximate confirmation /No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, No The proposed project will not use any hazardous which are hazardous (as per material. Hazardous material in proposed project MSIHC rules) to human health will be generated only as used lubricating oil from or the environment (flora, DG Set which can cause health hazard. This used fauna, and water supplies) oil will be sold to authorized recyclers. 3.2 Changes in occurrence of No The project is of a building construction. The waste disease or affect disease water as well as MSW is proposed to be disposed vectors (e.g. insect or water of in appropriate manner therefore the project will

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 8 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

borne diseases) not lead to change in occurrence of diseases or affect disease vectors. 3.3 Affect the welfare of people Yes The urban cities including Jaipur are suffering from e.g. by changing living shortage of adequate and hygienic living conditions? conditions. This has resulted in mushrooming of unauthorized Colonies which lacks basic amenities. The proposed project will provide all basic amenities and hygienic and comfortable living conditions. 3.4 Vulnerable groups of people No There are a number of Schools, Colleges, Hospitals who could be affected by the etc but it is a small group housing project and will project e.g. hospital patients, not affect vulnerable group of people. children, the elderly etc., 3.5 Any other causes No -

4. Production of solid wastes during construction or operation or decommissioning (MT/month) S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine No Not applicable. wastes 4.2 Municipal waste (domestic Yes According to the building construction manual and commercial wastes) of MoE&F the rate of waste generation in residential building is 0.41 Kg/day/person. In the Residential Section of project, Out of total domestic waste 60 % will be wet garbage and rest (40 %) will be dry garbage. The solid waste so generated will be first segregated as plastic, glass, paper and other waste separately and disposed off as per MSW Rules, 2000 and amended Rules, 2008. Generation of Waste From Commercial Section = 60%(0.41 X 4300) = 1057.80 kg/day Wet Garbage @ 40% Total Waste Generated = 423.12 kg/day Dry waste @60% Total Waste Generated = 634.68 Kg/day

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 9 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

Management of Solid Waste during Operation Phase:-  Collection and Segregation of waste I. A door to door collection system will be provided for collection of domestic waste in colored bins from the different blocks. II. For waste collection, adequate number of colored bins (Green and Blue & dark grey bins– Separate for Bio-degradable and Non Bio-degradable) are proposed to be provided at the strategic locations of the area. III. Litter bin will also be provided in open areas like parks etc.  Handling of Waste: Recyclable wastes I. Grass Recycling – The cropped grass will be spread on the green area. It will act as manure after decomposition. II. The saleable waste like paper, plastic, metals etc segregated during collection will be sold off to recyclables.  Disposal Non-recyclable wastes will be disposed through Govt. approved agency. Hence, the Municipal Solid Waste Management will be conducted as per the guidelines of Municipal Solid Wastes (Management and Handling) Rules, 2000 amended up to date). A Solid waste management Scheme is depicted in the following figure for the project:-

Solid waste Management Scheme during Operational Phase

Solid Waste

Biodegradable Waste Non Biodegradable Waste

Non- Recyclable Waste Recyclable Waste

Segregation during Waste Collection

Green Bins Dark Gray Bins Blue Bins

Sold to Respective Recyclers/Buyers Remaining

Final Disposal through Municipal Corporation of City 4.3 Hazardous wastes (as per Yes Used lubricating oil from DG Set will be Hazardous waste Management generated during construction of the building. Rules) Waste oil will be properly stored and sold to authorized recyclers.

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 10 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

4.4 Other industrial process No Not applicable as the proposed project is of wastes construction and will not involve any industrial activity. 4.5 Surplus product No Not applicable , Commercial Building Project 4.6 Sewage sludge or other sludge Yes Dried sludge from STP will be used as manure from effluent treatment for plants after treatment. 4.7 Construction or demolition Yes Construction wastes will be used for road wastes construction. 4.8 Redundant machinery or No All machinery after construction will be equipment removed from site. 4.9 Contaminated soils or other No No such material envisaged materials 4.10 Agricultural wastes No Not applicable 4.11 Other solid wastes No Not applicable

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S.No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 5.1 Emissions from combustion Yes The only point source of pollution will be four of fossil fuels from stationary D.G. Set, one of 250kVA and500 kVA, two DG or mobile sources sets each of capacity 1000 kVA. The emissions will be discharged through vent of proper height. D.G Set will conform to emission limits as prescribed under E P Act- 1986 and having acoustic arrangement as per EP Act- 1986. The D.G Set will carry „Type approval Certificate‟. 5.2 Emissions from production No - processes 5.3 Emissions from materials Yes Dust will be generated during transportation and handling including storage or unloading of material. The measures to minimize transport the effects are given in Environmental Management Plan. 5.4 Emissions from construction Yes The measures to minimize the effects are given in activities including plant and Environmental Management Plan. equipment 5.5 Dust or odours from handling Yes The measures to minimize the effects are given in of materials including Environmental Management Plan. construction materials, sewage and waste. 5.6 Emissions from incineration No No such operations are envisaged. No burning of of waste waste will be practiced. 5.7 Emissions from burning of No Waste would be collected and handed over to the waste in open air (e.g. slash authorized vendor and biodegradable waste will

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 11 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

materials, construction debris) be converted into manure by Organic Waste Converter. 5.8 Emissions from any other No - sources

6. Generation of Noise and Vibration, and Emissions of Light and Heat: S. No. Information/Checklist Yes/No Details thereof (with approximate confirmation quantities/rates, wherever possible) with source of information data with source of information data 6.1 From operation of equipment Yes but Noise generated by equipment will be e.g. engines, ventilation plant, negligible nominal. The measures to minimize the crushers effects are given in Environmental Management Plan. 6.2 From industrial or similar No It is a construction project. processes 6.3 From construction or Yes But insignificant to result in any adverse demolition effect on environment. 6.4 From blasting or piling No Not involved

6.5 From construction or Yes During construction phase the noise will be operational traffic generated from movement of vehicles, earthwork, concrete mixer etc. 6.6 From lighting or cooling No Silent generators will be used. systems 6.7 From any other sources No -

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 7.1 From handling storage, use or Yes Used lubricating oil from D.G Set will be spillage of hazardous properly stored and sold to authorized recyclers. materials 7.2 From discharge of sewage or Yes The Sewage generated will be treated and other effluents to water or the handled properly to minimize the impact. land (expected made and During construction phase septic tank soak pit place of discharge) system would be provided and during operation phase STP would be provided. 7.3 By deposition of pollutants No The only source of air pollution will be Four D.G. emitted to air into the land or set, one of 250kVA and500 kVA, two DG sets into water each of capacity 1000 kVA, which would have

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 12 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

vent of proper height. Beside the DG set will be housed in acoustic enclosure as per prevailing rules. 7.4 From any other sources No - 7.5 Is there a risk of long term No Not envisaged. build up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S. No. Information/checklist Yes/ Details thereof (with approximate confirmation No quantities/rates, wherever possible) with source of information data 8.1 From explosions, spillages, No These operations are not involved. fires from storage, handling, use or production of hazardous substances 8.2 From any other causes No - 8.3 Could the project be affected Yes The site is located in the seismic zone-III, which by natural disasters causing is the zone of moderate seismic intensity, as per environmental damage (e.g. the seismic zoning map of India given in BIS floods, earthquakes, code IS: 1893(Part 1)-2002.As such there is no landsides, cloudburst etc)? history of such disasters in the area till now. Proper safety measures as per Disaster Management Plan will be adopted to face such incidents.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality. S. No. Information/checklist Yes/ Details thereof with approximate confirmation No quantities/rates, wherever possible) with source of information data

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 13 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

9.1 Lead to development of The proposed site is located near RIICO supporting cities, ancillary Industrial Area Neemrana. The area has well development or development developed infrastructure and provision of proper stimulated by the project basic amenities. which could have impact on the environment e.g.:  Supporting infrastructure This is a small project and will not exert any (Roads, power supply, waste No significant negative impact. or waste water treatment etc.)  Housing development  Extractive industries  Supply industries  Other 9.2 Lead to after-use of the site, No This is a construction project. which could have an impact on environment 9.3 Set a precedent for later No The project will be developed strictly as per UIT developments bye laws. 9.4 Have cumulative effects due No It is a construction project and will be used for to proximity to other existing non polluting activities with full civic facilities or planned projects with like water supply, sewage treatment and similar effects. ventilation etc.

(III) Environmental Sensitivity S. No. Areas Name/Identity Aerial distance (within 15 km.) Proposed project location boundary 1 Areas protected under No No such areas exist. international conventions, national or local legislation for their ecological, landscape, cultural or other related value 2 Areas which are Tankri PF 12.50 Km towards NNE of project site. important or sensitive Kiratsingpura PF 5.50 Km towards South of project site. for ecological reasons Barud PF 6.50 Km towards SSW of project site. –Wetlands, Kolila PF 7.50 Km towards SSW of project site. watercourses or other Nimrana PF 0.80 Km towards NW of project site. water bodies, coastal Kanti PF 13.60 Km towards NW of project site. zone, biospheres, Humzapur PF 7.60 Km towards South of project site. mountains, forests Banganga River 10.80 Km towards SE of project site. Sabi River 8.40 Km towards SE of project site. 3 Areas used by No No such areas exist.

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 14 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4 Inland, coastal, marine Banganga River 10.80 Km towards SE of project site. or underground waters Sabi River 8.40 Km towards SE of project site. 5 State, National Yes Rajasthan–Haryana interstate boundary boundaries at a distance of 8.50 km towards NE from the proposed project site. 6 Routes or facilities SH-14 12.50 Km towards SSW side of used by the public for proposed site. access to recreation or NH-8 1.70 Km towards ESE side of proposed other tourist, pilgrim site. areas 7 Defense installations - - 8 Densely populated or Village Jonaicha kalan 5.60 Km towards NNE of project site. built-up area Village Kutina 10.80 Km towards NNE of project site. Village Giglana 13.50 Km towards North of project site. Village Rajgarh 13.20 Km towards NNE of project site. Village Tankari 13.80 Km towards NE of project site. Village Khandora 10.10 Km towards NE of project site. Village Mohanpura 13.00 Km towards NE of project site. Village Gugal Kota 8.50 Km towards NE of project site. Village Shajahanpur 5.60 Km towards ENE of project site. Town Neemrana 3.20 Km towards NW of project site. Village Mirzapur 8.80 Km towards NE of project site. Village Janaksingpura 1.50 Km towards ESE of project site. Village Bahror Jat 3.60 Km towards SE of project site. Village Kankara Barud 11.70Km towards SSW of project site. Village Sodawas 14.10 Km towards SSW of project site. Village Madhosingura 1.50 Km towards South of project site. Village Gondla 13.50 Km towards WSW of project site. Town Shivpuri 2.50 Km towards West of project site. Village Dosod 10.00 Km towards WNW of project site Village Majrikhurd 6.00 Km towards WNW of project site. Village Kanti Khas 9.50 Km towards NW of project site. Village Kheri 8.50 Km towards NW of project site. Village Majro 5.50 Km towards NW of project site. Village Madhan 12.00 Km towards NNW of project site. Village Gilot 7.50 Km towards North of project site. 9 Areas occupied by Health Care Facility/Hospitals Facilities sensitive man-made Dispensary at Giglana 12.50 Km towards North of project site. land uses (hospitals, Veterinary Hospital at 12.00 Km towards NNW of project site.

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 15 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

schools, places of Madhan worship, community Hospital & Veterinary 3.20 Km towards NW of project site. facilities) hospital at Neemrana Dispensary at Kutina 10.80 Km towards NNE of project site. Dispensary at Kanti Khas 9.50 Km towards NW of project site. Hospital at Shajahanpur 5.60 Km towards ENE of project site. Worship & Community Facilities Temple Post office & At Neemrana 3.20 Km towards NW of Police Station project site. Post office & Temple At Shajahanpur 5.60 Km towards ENE of project site. Post Office At Bahror Jat 3.60 Km towards SE of project site. Post Office & police At Village Kankara Barud 11.70 Km Station towards SSW of project site. School and Educational Facilities Govt. School At Neemrana 3.20 Km towards NW of project site.

Govt. School At Shajahanpur 4.00 Km towards ENE of project site. Govt. School At Bahror Jat 6.60 Km towards SE of project site. Govt. School At Village Kankara Barud 11.70 Km towards SSW of project site. Primary School At Village Janaksingpura 1.50 Km towards ESE of project site. Rajkiya Ucchya At Shivpuri 2.50 Km towards West of Madhyamik School project site. 10 Areas containing Banganga River 10.80 Km towards SE of project site. important, high quality or scare resources (ground water Sabi River 8.40 Km towards SE of project site. resources, surface resources, forestry, agriculture, fisheries, tourism minerals) 11 Areas already No Project is located in the RIICO subjected to pollution Industrial Area Neemrana. or environmental damage.(those where existing legal

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 16 EIA Consultant

Form 1-Proposed Expansion of Commercial Building

environmental standards are exceeded) 12 Areas susceptible to No Neemrana is located in semi-arid natural hazard which region and there is no history of floods could cause the project or land slide. Soil in Alwar is generally to present sandy and cohesion less; mildly sloping environmental hence there is no threat of subsidence. problems The site is located in the seismic zone- (earthquakes, III, which is the zone of moderate subsidence, landslides, seismic intensity, as per the seismic erosion, flooding or zoning map of India given in BIS code extreme or adverse IS: 1893(Part 1)-2002.As such there is climatic conditions) no history of such disasters in the area till now. Map of India showing seismic zones of India is enclosed as Annexure- XIX.

(b) “I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.”

Date: Place: Mr. Prem Pal Singh ( Authorized Signatory ) M/s Vanchari Hotels Pvt. Ltd. Plot No. CC-2, RIICO Industrial Area, Tehsil -Neemrana, District Alwar, Rajasthan

M/s Vanchari Hotels Pvt. Ltd. TEAM Institute of Science & Technology Pvt. Ltd.

Authorized Signatory 17 EIA Consultant