Short Resettlement Plan of LBDC Main Canal (ICB-05)

SRP-ICB-05 April-2013

Islamic Republic of : Loan 2299-PAK: Lower Bari Doab Canal Improvement Project

Prepared by Project Management Unit, Department, for the Government of Pakistan and the Asian Development Bank

i

ACRONYMS AND ABBREVIATIONS

AH Affected Household APs Affected Persons CBO Community Based Organization CCA Culturable Command Area CoI Corridor of Impact Cs Cusec C&W Communication & Works department DCR District Census Report EA Executing Agency EMA External Monitoring Agency FO Farmer Organization GRC Grievance Redress Committee ICS Information and Communication Strategy IP Indigenous People IPDPs Indigenous People Development Plan IPSA Initial Poverty and Social Assessment LAA Land Acquisition Act LARP Land Acquisition and Resettlement Plan LAR Land Acquisition and Resettlement LARF Land Acquisition and Resettlement Framework ESSU Land Acquisition and Resettlement Unit LBDC Lower Bari Doab Canal M&E Monitoring & Evaluation MFF Multi-tranche Financial Facility OFWM On-Farm Water Management O&M Operation and Maintenance PD Project Director PID Punjab Irrigation Department PIADSP Punjab Irrigated Development Sector Project PMU Project Management Unit PRA Participatory Rapid Aapraisal RAC Resettlement Advisory Committee RD Reduced Distance RP Resettlement Plan RoW Right of Way SBEs Small Business Enterprises ToR Terms of Reference

ii

This Social Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgements as to the legal or other status of any territory or area.

iii

TABLE OF CONTENTS 1 INTRODUCTION 1 1.1 Background 1 1.2 Improvements in the Sub-Project Design 1 1.3 Alternative Options for Minimizing the Resettlement Impact 2 1.4 Objectives of the LARP 2 1.5 Resettlement Processing Requirements 2 2 SCOPE OF LAND ACQUISITION AND RESETTLEMENT 6 2.1 Land Occupation and Resettlement 6 2.2 Approach and Methodology 7 2.3 Collection and Review of Secondary Data / Information 7 2.4 Collection of Primary Data 7 2.5 Identification of Affected Persons (APs) by Profession 8 2.5.1 Agriculture (60APs) 8 2.5.2 Tea Stall Owners: (02APs) 8 2.5.3 Laborer: (01AP) 8 2.5.4 Govt. Sector Job (01 AP) 8 2.6 Income of Different Occupation Groups of APs 8 2.7 Impact of Land Occupation on Temporary Basis for Diversions 9 2.8 Impact on Privately Owned Structures 10 2.9 Impact on Community Assets / Structures 11 2.10 Impacts on public Structures/Asset 11 2.11 Impacts on Women Headed Households 11 2.12 Impacts on Private Trees 12 2.13 Impacts on Government Trees 12 2.14 Socio-Economic Characteristics of the APs 12 2.14.1 Population and Family Composition 12 2.14.2 Education and Literacy Level 12 2.14.3 Monthly Income of the Sample Respondents 13 2.14.4 Household Items Availability 13 2.14.5 Available Social Amenities in the Project Area 14 2.14.6 Housing Conditions 14 2.14.7 Women’s Role in Socio-economic Activities 15 2.14.8 Conflict Resolution Mechanism in the Project Area 15 2.15 Asset Valuation 16 i

2.15.1 Standard Rates Adopted For the Assets 16

ii

3 LEGAL AND POLICY BACKGROUND 18 3.1 Pakistan’s Law and Regulations on Land Acquisition and Resettlement 18 3.2 ADB’s Involuntary Resettlement Policy 1995 18 3.3 Comparison of Pakistan’s LAA and ADB Resettlement Policy 1995. 19 3.4 Remedial Measures to Bridge the GAP 19 3.5 Sub-Project Resettlement Principles 19 3.6 Compensation Eligibility and Entitlements 20 3.6.1 Eligibility for Compensation 20 3.6.2 Compensation Entitlements 20 3.6.3 Entitlements Matrix (EM)for ICB-05 20 3.6.4 Memorandum of Understanding (MoU) 21 4 CONSULTATIONAND GRIEVANCE REDRESS PARTICIPATION 22 4.1 Document Disclosure 22 4.2 Consultation with APs 22 4.3 Consultation with Local Women and Community 25 4.4 Consultation with Other Stake Holders 26 5 COMPENSATION, RELOCATION AND INCOME RESTORATION 27 5.1. General 27 5.2. Compensation for Affected Land and Assets 27 5.3. Compensation for Privately Owned Structures 27 5.4. Compensation of vulnerable affected persons 27 5.5. Compensation for Community Owned Structures/Assets 28 5.6. Compensation for Public Structures/Assets 28 5.7. Compensation for Privately Owned Trees 28 5.8. Compensation for Govt.OwnedForestTrees 28 5.8.1 Relocation of Religious Structures 28 6 INSTITUTIONALARRANGEMENTS 29 6.1. Institutional Set up 29 6.2. Irrigation DepartmentPunjab 29 6.3. Local Government 29 6.4. Coordination Initiatives 29 6.5. LAR Steering Committee: 29 6.6. LAR Advisory Committee: 30 6.7. Grievance Redress Committee: 30 6.8. Need for Establishing a Grievance Redress Mechanism 30 iii

6.9. Grievance Redress Procedure 30 6.10. Formation of a Grievance Redress Committee (GRC) 31 6.11. Maintenance of a Social Complaint Register (SCR) 31 6.12. Conflict Resolution Procedure 31 6.13. Training in RP Implementation 32 7 RESETTLEMENT BUDGET AND FINANCING 33 8 IMPLEMENTATION SCHEDULE OF UPDATED OR FINAL LARP 35 8.1. Process of LARP Implementation 36 8.2. Disclosure of LARP and Community Participation 36 9 MONITORING AND EVALUATION 37 9.1. Internal Monitoring and Evaluation 37 9.2. External Monitoring & Evaluation 37 9.2.1 Reporting requirement 37

iv

LIST OF TABLES Table 1.1 Disty/Minors Falling In ICB-05 ...... 1 Table 1.2 Proposed Improvement Works Under ICB-05 ...... 1 Table 2.1: Details Of Proposed Diversions Of ICB-05 ...... 6 Table 2.2: Categories Of Affected Households With Income Status ...... 9 Table 2.3: Detail Of Land To Be Occupied On Temporary ...... 9 Table 2.4: Private Structures Located In CoI Of ICB-05 ...... 10 Table 2.5: Community Owned Assets Structures/Fixtures In CoI ...... 11 Table2.6: Literacy Rate Of The Project Area ...... 12 Table 2.7: Categories Of Sample Households With Income Status ...... 13 Table 2.8: Average Expenditures Of Sample Households ...... 13 Table 3.1: Summary Comparison Of Pakistan’s Laa And Adb Resettlement Policy ...... 19 Table 3.2: Entitlement Matrix (EM) ...... 20 Table 4.1: Summary Of Consultations With Stakeholders And APs ...... 22 Table 5.1: Valuation Of Privately Owned Assets ...... 27 Table 5.2: Valuation Of Affected Community Owned ...... 28 Table 6.1: Conflict Resolution Process At Project Level ...... 32 Table 7.1: Detailed Cost Of LARP Implementation (In Pak. Rs.) ...... 33 Table 8.1: Updated Resettlement Tasks Process ...... 35

LIST OF FIGURE FIGURE 1: LOCATION MAP OF ICB – 05 ...... 4 FIGURE 2: A SAMPLE OF CORRIDOR OF IMPACT (COI) ICB-05 ...... 5

LIST OF ANNEXES Annexure 1: List Of Distributaries And Minors ...... 39 Annexure 2: Inventory Of Structures Of ICB-05 ...... 41 Annexure 3: Details Of Land To Be Occupied On Temporary Basis - ICB-05 ...... 43 Annexure 4: Inventory Of Communitystructures/Fixtures Of ICB-05 ...... 49 Annexure 5: Inventory Of Public Infrastructure Of ICB-05 ...... 50 Annexure 6: Transport Allowance For Affected Household Of ICB-05 ...... 51 Annexure 7: Stake Holders Consultation Meetings With Male Participants ...... 52 Annexure 8: Consultation Meetings With Female Participants ...... 64 Annexure 9: Schduled Contruction Rates Of Building Department ...... 69 Annexure 10: Community Structures/Fixtures ...... 70 Annexure 11: Schduled Contruction Rates Of Building Department ...... 71 Annexure 12: Detail Of Proposed Diversions With Ownership Status Of Land & Earth Work72 Annexure 13: Tree Rates Of Forest Department ...... 76 Annexure 14: Rates Of WAPDA Electric Poles ...... 77

v

Annexure 15: Lar Steering Committee ...... 78 Annexure 16: Lar Advisory Committee ...... 79 Annexure 17: Internal Monitoring Committee ...... 80 Annexure 18: Standard Agreement For Temporary Lease Of Private Land ...... 81 Annexure 19: Corridor Of Impact (COI) ...... 82 Annexure 20: Right of the way (ROW) ...... 88 Annexure 21: Grivence Redress Committee (GRC) ...... 92 Annexure 22: Incme Analysis of The Affected Housesholds ...... 97

LIST OF APPENDIX

Appendix I: Assets Inventory Census Questionnaire ...... 102 Appendix II: Socio-economic and Poverty Assessment Baseline Survey Questionnaire ... 108 Appendix III:Gender Survey ...... 113 Appendix IV: List of Officers/Officials Contacted Regarding Private ...... 116 Appendix V: MOU between project team and affected farmer ...... 117

vi

Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

DEFINITIONS OF TERMS

Affected Household: All members of a household residing under one roof and operating as a single economic unit, and are affected by the Project, or any of its components. It may consist of a single nuclear family or an extended family group.

Affected Person: Any person affected by Project-related changes in use of land, water, natural resources, or income losses.

Compensation: Payment in cash or in kind of the replacement cost of the acquired assets.

Cut-off-date: Shall confirm the date of commencement of census in the specified area.

Entitlement: Range of measures comprising compensation, income restoration, transfer assistance, income substitution, and relocation, which are due to affected people, depending on the nature of their losses, to restore their economic and social base.

Income Restoration: Includes re-establishing income sources and livelihood of the affected persons according to their status.

Involuntary Resettlement: Any resettlement, which does not involve willingness of the persons being adversely affected, but are forced through an instrument of law.

Indigenous People: Refers to “ethnic minorities”, “cultural minorities”, “tribes”, “natives”, “indigenous cultural minorities”, and “aboriginals” whose social or cultural beliefs and practices are distinct from the mainstream society and are, therefore, at greater risk of being disadvantaged in the development process.

Land Acquisition: The process whereby a person is compelled by a government agency to acquire all or part of the land a person owns or possesses to the ownership and possession of the government agency for public purpose in return for compensation.

Market Value: The value of an asset determined by market transaction of similar assets and finally arrived at after negotiations with the owners.It includes transaction costs without the depreciation and deductions for salvaged building material.

Rehabilitation: Compensatory measures provided under the ADB Policy Framework on involuntary resettlement other than payment of the replacement cost of acquired assets.

RoW (Right of Way): In linear projects RoW denotes the area allocated to any canal, distributary, minor, road, gas pipeline or high transmission lines, etc for constructing the main facility, its safeguard, patrolling or any future development. It is generally measured from the center line of the main facility on its either side in equal amounts.

vii

Replacement Cost: “Cost of replacing lost assests and incomes, including cost of transactions”.

Squatters/ Informal Settlers: People who occupy and use land without possessing it or having any legal title, or right to use/possess the land / asset.

Vulnerable: The marginalized or those distinct people who might face the risk of marginalization and suffer disproportionately from resettlement affects, including the women, children, destitute persons, squatters; those with historical or cultural usufruct rights; and landless groups. Generally, people who are below the poverty line are called vulnerable persons, people/ family.

viii

LOCAL TERMS

Pacca - House or building constructed with concrete or bricks Semi-Pacca - House or building constructed with burnt bricks and mud Kacha - House constructed with un-burnt bricks and mud, or temporary wooden poles Tharah - Informal sitting arrangements Khokha - Wooden box used as a stall/business point Adda - Informal sitting arrangements on floor

ix

EXECUTIVE SUMMARY

Introduction i. This Land Acquisition and Resettlement Plan (LARP) of ICB-05 has been prepared by the Project Management Unit (PMU) of Punjab Irrigation Department (PID)-the Project Executing Agency (EA) of the Punjab Irrigated Agriculture Investment Program (PIAIP), funded by Asian Development Bank (ADB) through a Multi-trance Financing Facility (MFF). ii. The LARP has been prepared in accordance with ADB’s Involuntary Resettlement Policy 1995, the Land Acquisition and Resettlement Framework (LARF) of the investmenr program and the applicable national laws and regulations, e.g. Land Acquisition Act 0f 1894, and Punjab Land Acquisition Rules. iii. The data of project impacts and affected persons (APs) has been collected through socio-economic baseline and impact surveys, inventory of project impacts and 100 census of APs, based on the final project design. As LARP illustrates, the project necessitates relocation of religious structures, residential structures and displacement of small business structures. The owners of all such structures are non-titleholders, operating in the right of way (ROW. Average ROW from left side of the canal is about 117 feet including petroling/inspection path and 50 feet on the right side from the centerline of distributories). They will be compensated for their structures and lost incomes/livelihoods, fully in accordance with ADB’s IR principles including current market rate and replacement cost of all affected assets. Before LARP preparation, the EA considered all possible alternative design options to minimize the land acquisition and resettlement impacts. Hence the option selected is with minimum LARP impacts, which are temporary with no permanent land acquisition involved. Furthermore, civilworks activities are also confied within the PID owned ROW on both sides of the canal including distributories and minors. However, construction of diversion channels at 32 locations, outside the ROW, will require temporary occupation of 29.06 acres (232.5 kanals) of private land for a maximum of 3 years using section 35 of LAA. A total of 65 families will be affected by the project impacts. 1894. iv. The owners of all such structures are non-titleholders. In order to avoid or minimize the LAR impacts (if avoidance is not possible), a detailed study of alternative design options was carried out, as per requirements of the ADB. Accordingly, the proposed civil works activities are kept within the available land with the Punjab Irrigation Department (PID), on both sides of the distys/minors, without permananelty acquiring any land. However, at 32 locations, temporary diversion channels will be constructed outside the limits of the available land owned by PID and will require 232.5 Kanal (29.6 acres) privately owned land to be occupied on temporary basis for a period of three (03) years as per provisions of Section-35 of LAA, 1894. v. According to ADB policy, preparation of RP depends upon the degree of severity caused by a project. In case the impacts are severe i.e. >200 persons with > 10%percent income loss, a full RP will be prepared. Full RP is also required if 100 or more affected people are vulnerable indigenous people. In case of less than 200 APs, or a project causing temporary impacts (regardless the number of APs), a short RP will be prepared. In case of ICB 05, a total of 65 families or 425 APs are being affected temporarily, but none is losing 10% or more of income generating resources and no one is being physically dislocated from housing. The APs have multiple sources of incomes and they do not depend on leased land for their livelihoods. The project impacts are temporary and insignificant; therefore, ICB 05 is being placed in catrgory B for involuntary resettlement and C for indigenous peoples as there are no IPs living in and around the project area. Accordingly the PMU has prepared this short resettlement plan which is in line with ADB’s involuntary resettlement policy of 1995 and handbook on good practices. vi. This LARP has been synchronized with construction schedule and will be implemented by the Project Management Unit (PMU). The PMU has already established an

x environment and social safeguards unit (ESSU) within PMU to manage the LARP implementation and monitoring. Further details can be seen in the organizational chart of PMU/ESSU at Figure 1-A.

Sub-project Details vii. The LBDC MainCanal originates from river Ravi at Balloki Barrage, about 75 km south west of . Its total length is 201 km. It is further divided into seven separate International Contract Biddings (ICBs) to facilitate the implementation process under the financial facility. The present LARP relates to ICB-05 sub-project. It mainly comprised of distributaries and minors off taking from the reach of ICB-02 LBDC main canal. It has 85 distributaries and minors. The ICB-05 falls into SahiwalIrrigation division.Total CCA of this package is 610738 acres. Out of which, 467652 acres (77 %) are in sweet zone, while 143086 acres (23 %) fall in brackish zone. In brackish water zone, there are water supply schemes installed through government departments to supply portable water to the communities. There are 1003 outlets irrigating the command area. Layout plan of ICB-05 LBDC Main Canal along with all distributaries/minors is shown in Figure-1. viii. The following works are proposed for ICB-05.

Type of Proposed Work Nos. • Construction of Head Regulators 53 • Replacement of existing Fall Structures 162 • Remodeling of existing Fall Structures 5 • Diversions expected to have temporary occupation of land 32 • New/Replacement of existing DR/VR Bridges 264 • Rehabilitation of Existing Bridges 186 • Reconstruction/Rehabilitation of existing outlets 1003 • Installation of Meter Flume 10 • Washing Points 67 • Cattle Ghats 84

Updated Short Resettlement Plan (LARP) ix. The implementation of this sub-project will cause resettlement impacts like temporary occupation of agriculture land, relocation of religious structures, and displacement of small business structures (Kiosks) and removing of trees for clearance of corridor of impact (CoI. On an average COI on the left side of centre line of distrubutory is 65 feet and 35 feet on the right side of distributor). This is an updated LARP which will be implemented based on the contractors’ construction schedule which is further based on final shop drawings to be prepared by the contractor based on his yearly construction schedule of diversion channels. These activities have been further explained along with timeline in the revised implementation schedule. The LARP has been finalized based on the final land lease price, negotiated and agreed between the PMU and APs (see attached memorandum of understanding-MOUs) and compensation unit rates which are based on current market rates as determined by relevant government departments (see annexes on unit rates). All possible options to avoid or minimize the LAR impacts were studies before finalizing the LARP. In accordance with the design, all civil works activities are kept within the CoI, except the area, where diversions channels are to be made in private land that would be occupied on temporarily on lease basis. Thus, minimum disturbance and displacement is envisaged. x. The resettlement plan has been prepared to address the resettlement issues within the corridor of impact and to compensate the affected persons in order to execute the project activities in a smooth and sustainable manner. The cut-off date for impacts and compensation entitlements has been set at 20th March 2013 and communicated with all the APs during consultations on and signing of MOUs which contain mechanism, negotiated

xi land lease price and timing of payments.The fresh consultation meetings were held during the month of March 2013. xi. Permanent land is not required in this sub-project.There are 42 proposed diversions on 14 disty/minors in ICB-05. However, land will have to be occupied on temporary basis under the provisions of section-35 of LAA 1894; for construction of diversion channels in the private land at 32 locations on nine different distributaries & minors. The ouccpation of land will be for a maximum period of 03 (three) years. Although there are other 10 proposed diversions on fivedifferent distributaries, but these will remain within RoW. xii. The Project will affect 65 households in various occupations. The average size of affected householgs, (AFs) works out to be 6.5 persons. These include farmers, shop keepers, tea stall owners, and laborers. All the APs are either owner of residences, sole business operators and or self cultivators. None of them is tenant. The impacts are temporary and will not cause any livelihood problem as the civil works will be carried out during the canal closure period. During this period all rountine agriculture and/or business activities are stopped anyway, and therefore, project construction work will not cause any loss of income. The details of these APs are as under:- Sr. No Category No of APs APs by Occupation Diversion Affectees 1 Farming 56 Structure Affectees 1 Farming/agriculture related structures 4 2 Shopkeeper 1 3 Small business enterprise; small restaurant/tea stall. 2 4 Govt. Job 1 5 Labor 1 Total 65 xiii. Out of 65 affected households, 56 AFs (376 persons) fall in the farming category and remaining 09 AFs with 45 persons in the non-farming category. There are sevenwomen- headed household werefound in this sub-project. Similarly 15 private structures, 74 electricity poles, 03 telephone poles and01prayer place are identified to come under project impacts. xiv. The socio-economic survey was conducted by selecting a sample of 25 percent APs, as per requirements of the ADB. According to the results of the socio-economic survey, the male to female ratio was 100:118.The number of literate persons worked out as 64 percent of the total study sample. As far as the availability of social amenities were concerned, 100 percent of the respondents reported the availability of electricity, while 88 percent informed that educational facilities of primary schools level are available in their . The availability of health care, telephone, gas and sewerage facilities were reported by 31 %, 13 %, 06 % and 19 % of the respondents, respectively. It was also noted that no one of the affectees was benefiting the facility of water supply.The survey has revealed that the role of women in the socio-economic activities was comparatively better but they havelessrole in decision making relating to farm activities, livestock, sale and purchase of property, social obligations and local representation matters.

Objectives, Policy Framework and Entitlements xv. The LARP is anchored on the philosophy that government development projects must serve the needs of society. To achieve this objective, the PID prepared a LARF and LARP consistent with ADB’s IR policy and Land Acquisiiton Act (LAA) 1894 have been prepared for implementation. The LARP consitans an Entitlement Matrix (EM) based on which the the APs will be compensated. The EM is provided as Table S-1.

xii

Table S-1: Entitlement Matrix

Sr. Type of Loss Entitled People Compensation Entitlements No. 1 Temporary Land Owners • Temporary occupation for Occupation of Land construction of diversion channels on lease basis at negotiated price of Rs.50,000/- acre/year 2 Trees • Non-fruit private trees (wood) are compensated @ Rs.119 X 10 = 1190/- Rs/tree. The wood will be salvaged by the owner. • The compensation for govt. trees based on Punjab Agriculture Department’s formula wherein, the cost for replenishment of 500 trees at one “avenue mile” for five years is Rs. 59,300/-. • The replenishment of govt. trees will be addressed under the EMP, and therefore, no cost is earmarked in the LARP. 3 Residential and All relevant APs • Cash compensation at replacement Business Structures/ costs for affected structure and other assets with full or fixed assets. The replacement value partial losses for Semi-Pakka and Kacha structures are Rs.525 and 310 respectively. • In case of partial impacts, cash assistance to restore remaining structure. • Rs. 5000/- as shifting, wear/ tear and re-installation cost for wooden kiosk and shed. 4 Allowances; All APs (including • Rs. 2,000/AP as shifting allowance Shifting allowance for Informal settlers) for those losing structures. private structures 5 Vulnerability APs below poverty line • One time cash compensation based allowance including women on 3 months income at official (i) 3 women headed headed households and poverty line @ 12,500/month households losing those losing >10% of (rounded figure) more than 10% of income generating income generating resources. land. (ii) 5 women headed • One month’s salary @ official Women headed households poverty line, Rs. 12,500/ rounded households figure 6 Commnity structures Community members • Full costs of structure/ asset at managing the structure replacement cost paid to the community/committee members 7. Unanticipated impacts • In case of any unanticipated impacts during the project implementation, the impacts will be addressed/compensated at replacement costs and in line with the entitlements provided in the approved framework (LARF).

xiii

Consultation and Grievance Redressal Participation xvi. The affected persons were made fully aware through consultative meetings, individual and group discussions and dissemination of the project. APs were consulted at all the 85 distys and minors including 434 males and 101 females. Their concernsin respect of land occupation, valuation of affected assets on current rates, provision of cattle ghats, human crossings, washing points for females, timely payment of compensation, etc.have been considered in the LARP.

Compensation, Relocation and Income Restoration xvii. All affected land, residential, commercial and community structures were considered for compensation as per ADB IR Policy and guidelines on resettlement. In addition to compensation at replacement costs, the allowances for vulnerability and shifting of structures will be provided to the eligible APs.

Institutional Framework xviii. An efficient coordination mechanism has been established as envisaged in the LARF to ensure coordination among various concerned agencies/ departments for the successful implementation of the LARP. Three committees “viz.” LAR Steering Committee, LAR Advisory Committee and Grievance Redressal Committees are established.

Resettlement Budget xix. The final resettlement budget is PK Rs. 13.56 million ($ 0.14 million). Table 7.1 provides further details. This includes cost of land lease price/acre for 3 years, cost of structures, trees, M&E cost and allowances.

Implementation Schedule xx. The implementation will be commencing following the ADB’s approval of the LARP. The implementation will follow the schedule (table 8.1) that contains timed LAR activities synchronized with procurement/construction schedule.

Monitoring and Evaluation xxi. Both, internal & external monitoring and evaluation of LARP implementation will be conducted according to the project activity schedule. The PMU/ESSU will carry out internal monitoring of the LARP while external monitoring will be undertaken by external monitoring agent/firm, hored by PMU for this purpose. The monthly internal and quarterly external monitoring reports will be provided to ADB for review/approval.

xiv

Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

1 INTRODUCTION

1.1 Background 1. The Punjab Irrigated Agriculture Investment Program (PIAIP) is a Multi-tranche Financial Facility (MFF) to be financed by the ADB. The Program includes several tranches each covering one sector-like Project. The Tranche-1 of the Program will finance the physical and organizational rehabilitation and up-gradation (R&U) of the Lower Bari Doab Canal (LBDC) irrigation systemlocated in Punjabprovince of Pakistan. The tranche is subdivided into two sub-components: (i) Rehabilitation and Upgradation (R&U) of the Balloki Barrage and ancillary infrastructure; and (ii) R&U of the LBDC network including (a) R&U of the MainCanal and (b) R&U of the distribution system. 2. The LBDC Main Canal originates from river Ravi at Balloki Barrage, about 75 km south west of Lahore. Its total length is 201 km. It is further divided into seven separate International Contract Biddings (ICBs) to facilitate the implementation process under the financial facility. The ICB-02 (MainCanal) starts from RD 227+454 to 526+00, ICB-03 (MainCanal) from RD 526+00 to 660+700. 3. The ICB-05 comprises all distys/minors off take from ICB-02. It falls into irrigation division of . There are 85 distributaries and minors under this package. The number of distributaries and minors with their length falling in respective irrigation divisions are summarized in Table 1.1 and details are presented in Annexure-1. There are 1003 outlets irrigating the command area. The CCA under ICB-05 is 610738 acres. Out of these, 467652 acres (77%) fall in sweet zone, while 143086 acres (23%) fall in brackish zone. In brackish water zone, there are water supply schemes installed through government departments to supply portable water to the communities. Layout plan of ICB-05 is shown in Figure-1. Table 1.1: Disty/Minors under ICB 05 Sr. # Irrigation Division Disty/Minor Total Length (Miles) 1 Sahiwal Division 85 478.66 Total 85 478.66 4. This LARP has been synchronized with the construction schedule and will be implemented by the Project Management Unit (PMU) working at Lahore to implement the Project. The PMU has established an environment and social safeguards unit (ESSU) within the PMU, which will manage the LARP implementation incouding LARP updating (if and when required), implementation; disbursement of payments to the APs, consultations and grievance redress aspects in particular, and internal monitoring of LARP. The organizational chart (fig 1-A) provides further details about ESSU and its staff.

1.2 Improvements in the Sub-Project Design 5. Table 1.2 below provides civil works activities, based on the final project design. Table 1.2: Civil works activities Type of Proposed Work Nos. • Construction of Head Regulators 53 • Construction of Head Regulators/corss regulators 06 • Replacement of existing Fall Structures 162 • Remodeling of existing Fall Structures 05 • Diversions 42 • New/Replacement of existing DR/VR Bridges 264 • Rehabilitation of Existing Bridges 186 • Reconstruction/Rehabilitation of existing outlets 1003 • Installation of Meter Flume 10 • Washing Points and cattle ghats 67/84

1

6. All civil works activities will remain within the CoI and, where required within the PID owned existing right of way (RoW), except diversions at different places of the distributaries that fall in the private land.

1.3 Alternative Options for Minimizing the Resettlement Impact 7. The follloiwng project alternatives were considered to (i) avoid, or (ii) minimize land acquisition and resettlement impacts: i. Take Full RoW as Work Area Limit (Right of Way) 8. The first alternative was to consider the available RoW of the distributaries/ channels as work area limit for the execution of improvement works.The width of RoW is different at various disturabutaries and minors. Normally it ranges from 25ftto 45ft. from the center line on either side. According to the preliminary survey of the RoW, the RoW was noticed encroached at different locations by locals. Adoption of this option could cause considerable resettlement impacts resulting in large scale disturbance in social networks and socioeconomic and farming activities in the area, further involving huge cost of LAR. ii. Reduce Work Area Limits to CoI (Corridor of Impact) 9. Keeping in view the above situation and to minimize the resettlement impacts of the proposed interventions, discussions were made with the design engineers and it was decided that instead of taking entire RoW, the work area limits should be considered for the assessment of resettlement impacts, Fig-2.Normally it ranges from 15 to 25 feet for minor and for distributor it is 65 feet on right and 35 feet on left side. As the RoW varies from channel to channel depending upon the discharge of the channel, bed width and type of civil work.The width of CoI also varies at right and left sides of the channel. This approach has helped to minimiz the resettlement related impacts to a significant extent on a number of distributaries and minors. Additionally, most of the works are proposed specifically to be carried out during closure periods. However where necessary; diversions are proposed to ensure regular water supplies. This will ensure un-interrupted water availability for irrigation and other community uses from the system. 10. The option (ii) above has been adopted in the project design and the assessment of the LAR impacts has been made according to the final design. The CoI approach helped to avoid the use of whole RoWand resultedin saving of significant number of structures, fixtures and trees without interrupting construction activities.

1.4 Objectives of the LARP 11. The purpose of preparation of the LARP is to ensure that the identified affected persons (APs) are compensated in a fair, timely and transparent manner in accordance with existing laws of Pakistan and the requirements of the ADB’s IR policy and approved land acquisition and resettlement frameowkr (LARF). The LARP is prepared based on the finalized technical / engineering design and following the guidenlines of ADB’s IR policy 1995 and LARF approved for the Lower Bari Doab Canal Improvement Project (LBDCIP).

1.5 Resettlement Processing Requirements 12. Based on the provisions of the RF, the following resettlement-related conditions are to be satisfied for the implementation of this sub-project: i. Condition to Contract Awards Signing: 13. The LARP has been prepared on the basis of final detailed engineering design, assessment of related impacts and approval by ADB. ii. Condition to Initiation of Civil Works Implementation: 14. The initiation of civil works of the project is contingent upon full payment of land

2 compensation and all assets including strucrues and allowances as provided in the entitlement matrix. Notice to proceed to civilworks is contingent upon confirmation of payments and LARP implementation by external monitor through external monitoring report.

1.6 Layout of LARP 15. The layout as suggested in the ADB approved RF for Tranche-1 sub-projects, has been adopted in the preparation of the present document, as follows. • Introduction • Scope of land acquisition and resettlement • Objectives, policy framework and entitlements • Consultation and participation in grievance redress • Compensation, relocation and income restoration • Institutional framework • Resettlement budget and financing • Implementation schedule • Monitoring and evaluation.

3

Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

FIGURE 1: LOCATION MAP OF ICB – 05

4 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

FIGURE 2: A SAMPLE OF CORRIDOR OF IMPACT (COI) ICB-05

5 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

2 SCOPE OF LAND ACQUISITION AND RESETTLEMENT

2.1 Land Occupation and Resettlement 16. Permanent land acquisition is not involved in this sub-project. However, private land will need to be occupied on temporary basis for diversions at 32 locations on different Distributaries/minors. All civil works will be accomplished on the distys and minors within the contract period of (03) three years (09 May, 2012 to 27June, 2015) as per implementation Schedule provided in Table 8.2. So a total of 232.5 kanals (29.36 acres) of private agriculture land will be temporarily used for 3 years. Section 35 of land acquisition act of 1894 will be used this purpose. All the land is owner cultivated and no tenants or employees have been reported. The detail of diversions is presented in Table 2.1. Although, there are 10 other diversions on five different distributaries of ICB-05, but the construction activities on these distributaries is confined within the PID owned existing ROW and LAR issues are not involved in these areas. Table 2.1: Details of Proposed Diversions Land Sr. ROW (ft) Branch/Disty/Minor RD Diversion Ownership No. (Left Right Side Status 1 4R Jhilwala Disty 2+050 55 40 Right Private 2 4R Jhilwala Disty 8+200 55 40 Left Private 3 5L Gamber Disty 1+420 200 55 Right Government 4 9L Disty 34+136 65 50 Right Private 5 9L Disty 81+400 70 55 Left Private 6 9L Disty 93+000 70 55 Left Private 7 9L Disty 113+084 65 50 Left Private 8 9L Disty 117+515 65 50 Right Private 9 9L Disty 127+420 65 50 Left Private 10 9L Disty 137+825 60 45 Left Private 11 9L Disty 142+570 60 45 Left Private 12 9L Disty 148+700 75 60 Left Government 13 1L/9L Pandatwala Disty 11+974 - 45 Right Private 14 1L/9L Pandatwala Disty 16+457 - 45 Right Private 15 1L/9L Pandatwala Disty 23+529 - - Right Government 16 Bahab Disty 4+865 80 60 Right Private 17 11L Dadfatiana Disty 15+200 65 60 Right Private 18 11L Dadfatiana Disty 24+500 60 55 Right Private 19 11L Dadfatiana Disty 33+300 60 50 Left Private 20 11L Dadfatiana Disty 36+590 60 50 Left Private 21 11L Dadfatiana Disty 42+500 50 35 Left Private 22 11L Dadfatiana Disty 47+250 50 35 Left Private 23 11L Dadfatiana Disty 52+725 50 - Left Private 24 11L Dadfatiana Disty 59+200 35 30 Left Private 25 12L Disty 20+350 80 65 Left Government 26 12L Chichawatni Disty 25+200 80 65 Right Private 27 12L Chichawatni Disty 46+930 70 55 Closure 28 12L Chichawatni Disty 50+350 70 55 Right Private 29 12L Chichawatni Disty 54+700 70 55 Left Private 30 12L Chichawatni Disty 85+000 65 50 Right Government 31 12L Chichawatni Disty 98+200 60 45 Left Private

6 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Branch/Disty/Minor RD ROW (ft) Diversion Land 32 12L Chichawatni Disty 110+500 60 45 Left Government 33 12L Chichawatni Disty 121+200 85 70 Right Government 34 12L Chichawatni Disty 122+300 85 70 Right Government 35 1R/12L Minor 30+970 55 40 Right Private 36 1R/12L Minor 38+385 55 40 Right Private 37 1R/12L Minor 72+000 45 40 Right Private 38 1R/12L Minor 76+411 40 35 Right Private 39 14L Disty 5+000 65 50 Left Government 40 14L Disty 9+500 70 55 Right Private 41 14L Disty 27+950 60 45 Right Private 42 14L Disty 39+900 60 45 Right Private

2.2 Approach and Methodology 17. The assessment of the project impacts has been made by adopting a well defined approach and methodology. The envisaged approach is based on the identification of resettlement impacts according to the final design of the project, and is explained as follows.

2.3 Collection and Review of Secondary Data / Information 18. Available data/ information relating to the sub-project were collected from the project documents, concerned offices of Local Government and Revenue Department of Okara and Sahiwal districts. The Census Reports for these districts were also consulted. Relevant information was gathered from the publications of Agriculture Department, Forest Department, Fisheries Department, etc.

2.4 Collection of Primary Data 19. In addition to collecting the data/ informationfrom the secondary sources, surveys were also conducted to collect data / information from the real field settings by using the pre- structured questionnaires. The questionnaires for Census Survey of the APs, Socio-economic Survey and Gender Survey are provided as appendix I, II and III, respectively. 20. Census Survey of the APs within the CoI, on 100 % basis, was carried out. The survey aimed to register and document the number and status of people likely to be physically displaced or affected otherwise as a result of the project; and therefore, entitled to compensation. The first census survey of APs was undertaken in May 2011, and accordingly 28 May 2011 was fixed as the cut-off date for project impacts and entitlements and compensation. Fresh consultations were carried ut with APs for the purpose of updating/finalizing the LARP in March 2013, and a fresh cut-off date was fixed as 20 March 2013 after completing the consutlaitons with APs. Cut-off date was announced publicly during individual consultations as well as group discussions and community was informed that anybody moving into the RoW and CoI after this date will not be considered as entitled to any compensation. 21. A sample survey in the project corridor was carried out. The purpose was to develop a socio-economic baseline of the affected people. The number of identified affected households in ICB-05 comes up to 65. Out of these, 56 are farmers (land affectees) and 09 belong to non-farming (structures affectees) community. ADB guidelines require that 20-25 percent APs should be taken as sample for socioeconomic study. However, keeping in view the data size of universe of the study and to have a representative socioeconomic profile of the APs and project corridor, 25 percent of the AF (16 AFs) were taken as sample for socioe-conomic survey. The farming and non farming respondents were taken proportionate by applying the stratified sampling techniquefor equal representation of each category. Thus, 13 respondents from farming group and 03 from non-farming group were selected at

7 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP) random. The farming group will be affected onlydue to temporary occupation of private land for the construction of diversions. The non farming affectees are scattered in ICB-05 on different distributaries. 22. Consultations were made with the stakeholders and general public. Consultative meetings and scoping sessions were held at different places within the project corridor to collect the views and concerns of the public on the proposed development works. The concerns raised by the stakeholders were considered in the LARP. The main objectives of the consultation process were: i. To provide a platform to the stakeholders, to voice concerns or suggestions to the Project team; ii. To develop a collective sense of ownership by the stakeholders for the activities of the Project team; and iii. To announce cut-off date for entitlement of compensations under the project.

2.5 Identification of Affected Persons (APs) by Profession 23. Any person, whose land, asset / structure, source of income or access to resources is likely to be affected by the project works, is defined as AP. These include the untitled enchroachers (owners of structures and fixtures) situated along bank of the irrigation channels. The data has indicated that 65such households fall in the CoI. The number of AP members comes to 421 with average HH size of 6.5 persons. The details of these APs with regard to various occupation categories is given as below:

2.5.1 Agriculture (60 APs) 24. The 56 APs under this occupation will be affected due to temporary land occupation for diversions at 32 locations, while 04 APs will loose their structures. A temporary yet insignificant impact on their source of income is envisaged. 25. The structures falling in this category will be partially disturbed. However the livelihood will not be affected during the project activities as they will continue their business in the vicinity.

2.5.2 Tea Stall Owners: (02 APs) 26. The APs under this occupation has constructed kacha structures in the designated CoI of 5-L/9-L distys. At RD 9+200 as shown in Annexure-2. They will be displaced due to construction of temporary diversion at this location.They intend to temporairy shift their businessesnearby in the RoW.

2.5.3 Laborer: (01 AP) 27. The AP under this occupation group have constructed residential structure and shed within the CoI. The encroached kacha boundary wall and shed of the AP will be affected due to diversion. However the main residential structure will not be affected.The AP is located on 1-L/3-L/9-L at RD 1+300.The AP is woman headed household.There will be no affect on her livelihood. Anyway, special attention will be paid during construction period.

2.5.4 Govt. Sector Job (01 AP) 28. The AP will be affected under this catagory. He is a bank employee. His boundary wall of a farm house will be affected at RD 10 of disty. He will be compensated as per ADB policy.

2.5.5 Income of Different Occupation Groups of APs 29. The income status of the APs is provided in Table 2.2 and the individual level details

8 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

are given in Annexure -2. Table 2.2: Categories of Affected Households with Income Status Avg. Total Average Avg. Monthly No. Monthly Monthly Monthly Sr. No. of Income/ Occupation of Income Income Income/non # APs. Farming AFs of APs of AP Farming AP AP (Rs.) (Rs) (Rs.) (Rs.) Land Affectees 1 Farmers(Large) 9 78 678,000 75,333 75,333 0 2 Farmers(Small) 47 298 2,096,809 44,613 44,613 0 Sub-Total 56 376 2,774,809 49,550 49,550 0 Structure Affectees 1 Farming 4 25 42,800 10700 0 10,700 2 Shopkeeper 1 7 14,400 14400 0 14,400 3 Hotel/tea stall 2 9 12,500 6250 0 6,250 4 Govt. Servant 1 1 30,000 30000 0 30,000 5 Labor 1 3 3,500 3500 0 3,500 Sub-Total 9 45 103200 11467 49,550 11467 Total 65 421

2.6 Impact of Land Occupation on Temporary Basis for Diversions 30. Private land will be occupied on temporary basis at 32 locations on nine distributaries for three year, as per provision of section 35 of LAA 1894. The identified resettlement impacts are shown in the Annexure-12. Total area to be occupied for diversions is 232.5 kanals (29.10 acres). 31. The land has been demarcated for diversion work as per final design and record of identification of each site documented. All diversions require “borrow material”. The dump soil of excavated material will be adjusted with in the temporarily occupied private land without affecting any adjoining area of farmers.The calculation based on the design is provided in Annexure-12. The ownership of farmers was determiend by the concerned canal and Revenue patwaries. The details of land to be occupied for each diversion are provided in Table 2.3. Table 2.3: Details of Land to be Occupied on Temporary Basis for Diversions Area Sr. No. Location Canal Side Nos. of APs Kanal---marla 4-R Jhilwala 1 2+050 R 5---2 03 2 8+200 L 4---11 01 9-L Ganjibar 3 34+136 R 16---0 03 4 81+400 L 6----0 01 5 93+000 L 5----0 01 6 113+084 L 5----0 03 7 117+515 R 5----0 02 8 127+420 L 3----0 02 9 137+825 L 2---10 01 10 142+570 L 2---10 01

9 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

1L/9L Pandatwala Disty 11 11+974 R 13---8 02 12 16+457 R 10---0 02 11-L Dad Fatiana Distributary 13 15+200 R 8---0 02 14 24+500 R 4---1 02 15 33-300 L 4---0 02 16 36+590 L 4---0 02 17 42+500 L 3--0 02 18 47+250 L 4---2 01 19 52+725 L 1---0 01 20 59+200 L 5----4 01 12-L Chichawatni Disty 21 25+200 R 4----0 01 22 50+350 R 12---0 01 23 54+700 L 1---0 01 24 98+200 L 6---0 03 1R/12L Minor 25 30+970 R 8---0 01 26 38+385 R 8----0 02 27 72+000 R 11----7 04 28 76+411 R 15---16 02 14-L Disty 29 9+500 R 16---0 01 30 27+950 R 19---10 02 31 39+900 R 16 ---0 01 Wahab Disty 32 4+865 R 3---0 02 Total 232. 5 (29.1 acres) 56

2.7 Impact on Privately Owned Structures 32. Different types of privately owned structures such as commercial, residential and animal shed will be affected due to project works. Besides, some moveable business structures like wooden kiosks will come under project impactson temporary basis. The data of different types of affected structures is given in Table 2.4 Table 2.4: Private Structures located in CoI/ROW Sr. No. Details of Type of S. Pacca Katcha Structures Loss (T/P) No. Area (Sq.ft.) No. Area (Sq.ft.) Commercial Structures 1 Shed T 2 393 2 Patio/Bench T 2 44 - - 3 Wooden Shed T 1 - - - Sub Total 3442 393 Residential Structures 4 B. Wall T 1 20 5 384 5 Shed T 2 259 6 Kitchen T - - 1 99 7 Room T - - 1 270 Sub Total 1209 1012 Total 4 64 11 1405

10 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

2.8 Impact on Community Assets / Structures 33. The community structures, affected by the project works, are listed in Table 2.5 and details are provided in Annex-4 .The committees are formed to shift/reconstruct these structures through allocated budget in the RP.The undertaking from these committees are provided in Annexures 15 & 16. Table 2.5: Community owned Structures in COI/RoW Sr. Details of Nos. of Area RD Location Structure/Asset No. Structures Structures (Sq.ft) Prayer 9-L, Rehmat 1 5+300 Prayer Place 1 169 Place Colony) Jamia Masjid Toilets 3 60 2 Mosque 14+500 Faradia Ablution Place 1 48

Floor 1 180 Total 6 457

2.9 Impacts on public Structures/Asset 34. There are 74 electric and 3 telepoles of PTCL, 3 transformers and PTCL poles and one lined watercourse falls in the CoI (Annex-5) of these sub project.These structures/assets will be compensated through the relevant department.

2.10 Impacts on Vulnerable Women Headed Households 35. There are seven vulnerable women headed households losing land to the project temporarily. The loss of land varies from 5% to 100%. Details provided in the table below, show that 3 women (sr. # 1, 2 & 5 of table 2.6) are losing more than 10% their productive land income generating. They will be paid vulnerability allowance equal to 3 months of inflation adjusted official poverty line (OPL) of Rs. 12,500/month (rounded figure). This allowance will be in addition to the negotiated land lease price per acre (Rs. 50,000/acre/year) per year for 3 years. All remaining 4 women households (including the 2 structures owner women) will receive vulnerability allowance equal to one month’s OPL salary of Rs. 12,500/- This will be paid over and above the land lease compensation. The details of these women affectees are as under: Table 2.6: Vulnerbale Women Headed households Sr. Type of Extent No. Location APs Name affected of loss Remarks Asset/Structure (% age) 1 9-L (RD 34) Majeedan Temp.land for 50% Of the total 6 kanals Bibi diversion she possesses, 3 kanals will be lost to the projectr for 3 years. 2 9-L (RD93) Hameedan Same as above 27% She has large land Bibi holdings in other area. 3 9-L (RD117) Najma Same as above 5% Perveen She has 12 acres of (Waseem land Minor) 4 11-L (RD59) Manzooran Same as above 3% She has 25 acres of Bibi land

11 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

5 1-R/12-L Bashiran Same as above 100% She has only two (RD71) Bibi kanals(Unavoidable case) 6 2-L / Wahab Ameeran Only boundary 5% Due to lining of Minor (RD3) Bibi wall and shed 7 1-L/3-L/9-L Asmat Bibi Only boundary 5% Same as above (RD2) wall and shed

2.11 Impacts on Private Trees 36. About 71 non-fruit trees, owned by one farmer, are falling in the CoI at diversion site RD 71+871 of 1-R/12-L. The AP will be compensated according to the compensatory policy of the Forest department as in Annexure-13

2.12 Impacts on Government Trees 37. The 13678 forest trees owned by the Punjab Forest department fall in the CoI. Forest department will undertake replenishment of the trees program with cost provide by PMU and allocated in the envornmental management plan (EMP). For this purpose, the budget is allocated in the EMP.

2.13 Socio-Economic Characteristics of the APs 38. The analysis is based on the findings of socio-economic survey of the APs as per ADB requirements discussed in Section 2.4 above. A sample of 25 % of the total number of APs was taken for socio-economic study. The study aimed at to assess the present condition of the APs and to appraise the project impacts ontheir livelihoods. The information on demographic characteristics, education, health, occupations, sources of income, pattern of household expenditures, etc. was collected.

2.13.1 Population and Family Composition 39. According to the results of the socio-economic survey, the total population of the APs comes up to 85 persons comprising 46 males and 39 females. Out of these, the APs from farming group were 11 males and 28 females, whereas 11 male and 11 female were from non farming group.Out of this, children below 10 years of age are 16, comprising 09 male and 07 females. These are 04 males and 03 females in farming group, while 05 male and 04 female are found in non farming group. The sex ratio was found as 100:118. The average family size of the sample respondents’ was 5.3.

2.13.2 Education and Literacy Level 40. Out of 85 persons, the number of literates comes to 54, which are 64 percent of the sample population. Out of the total literate, the persons having primary level of education are 27 percent. The respondents with middle level education are 12 percent, while 18 percent are matriculate. Educational level of intermediate was 01 percent, while 04 percent are graduates and 02 percent are post graduate. The information in respect of education and literacy level of the sample population is provided in Table 2.7. Table 2.7: Literacy Rate in Project area Literacy Rate of the Project Corridor Sr.No Educational Level Number %age 1 Primary 23 27 2 Middle 10 12 3 Matric 15 18 4 Intermediate 1 1

12 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

5 Graduate 3 4 6 Post graduate 2 2 Total Educated 54 64 7 Illiterate (propotion of total population) 23 27 8 Children (propotion of total population) 8 9 Total 85 100

2.13.3 Monthly Income of the Sample Respondents 41. The analysis indicates that the main occupations of the sample population were found as farming, hotel/tea stall, labor, butcher, barbar, mechanic, servicemen and shop keepers. The category wise information in respect of income of the respondents is provided in Table 2.8. The detail of income analysis is provided in Annexure-22. Table 2.8: Categories of sample Households with Income Status Profession of the Total Monthly Average Monthly Sr. No. No. of APs Respondents Income (Rs.) Income Per AP (Rs) 1 Farming Group 13 318006 24462 2 Non Farming Group 03 33500 11167 Table 2.9: Average Expenditure of Sample households Sr. Description of Total exp/month Avr. Total exp. Avr No. Expenditure (13 farming exp/month) Nonfarming exp/month families) 3families 1 Food items 92450 7111 14400 4800 2 Non food items 24800 1908 3700 1234 3 Utilities 44300 3408 4300 1434 4 Health care 24917 1917 1167 389 Other expenses 5 (cloths,shoes, 17917 1378 2875 958 function etc) Total 204384 15722 26442 8814 42. According to the income and expenditure analysis as provided in Tables 2.8 and 2.9 above, the average monthly income of the sample APs of farming and non-farming community is Rs. 318,006/ and Rs. 33,500/ respectively. The corresponding expenses of the same respondent’s category come out Rs.204,384/ and 26,442/ respectively. 2.13.4 Household Items Availability 43. The data/ information relating to the availability of various household items indicate socio-economic condition of the respondents. It also reflects the necessity and affordability of the people to accomplish their social needs. The information collected from the sample respondents is provided in Table 2.10. Table 2.10: Comparison of Households Possessing Economic Assets

Farming(13) Non Farming(03) Sr. Items No. Possessions Possessions Nos. Households % Nos. Households % 1 Refrigerator 10 10 77 1 1 33 2 Television 11 11 85 1 1 33 Washing 3 7 7 54 0 0 0 Machine 4 Electric Fan 46 13 100 5 3 100 5 Electric Iron 13 13 100 0 0 0

13 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sewing 6 7 7 54 1 1 33 Machine 7 Bicycle 8 8 62 2 2 67 8 Motor Cycle 9 9 69 1 1 33 9 Mobile 14 13 100 2 2 67 Electric Water 10 12 12 92 0 0 0 Pump 11 Hand Pump 1 1 8 3 3 100 Electric 2 2 15 0 0 0 12 Madhani

44. The data indicates that the expenditure on food and non-food items of farming group comes to about 57%, compared with 68% of non farming respondents. Whereas the expense on utilities and health care of farming and non farming respondents were reported 32 percent and 20 percent respectively. The miscellaneous expense on cloth, shoes and other social activities were reported as 09 percent from farming and 11 percent from non farming respondents. The farming families prefer to spend their savings to purchase livestock, agricultural tools and land. Whereas the non farming community faces financial constraints due to lack of work opportunities. 45. The information provided in Table 2.10 showssocio-economic conditions of both categories. The refrigerator, TV and motor cycles are being used by 45 to 60 percent of the farming group. It is concluded that the farmers with comparatively large land holdings are leading better life as compared with small farmers and the non-farming group. 2.13.5 Available Social Amenities in the Project Area 46. The results of the socio-economic survey reveal that electricity was available in the project areato 100 percent of the respondents.The 100 percent were dis-satisfied with the quality of services. Education facility was available in the area to 88 percent of the respondents. Out of them, 86 percent were satisfied with the quality of services, while 14 percent showed their dissatisfaction. Availability of sewerage/ drainage facility was reported by19 percent of the respondents and with 100 % satisfaction level relating to the quality of services provided. Basic Health Unit facility was available to 31 percent of the interviewed APs and they showed 60 percent satisfaction.Other amenities like gas and telephone was partially available in the project corridor. None of the respondents reported the availability of water supply scheme, because the fresh groundwater is sweet.The information in respect of access to social amenities and their quality of services is given in Table 2.11. Table 2.11: Availability of Social Amenities & Satisfaction Level of Respondents Available Satisfaction Level (%) Sr. No Facility Non Available Not Availabale Satisfactory Satisfactory 1 Electricity 100 0 0 100 2 Sui Gas 6 94 100 0 3 Water Supply 0 100 0 100 4 Telephone 13 87 100 0 5 Sewerage 19 81 100 0 6 BHU 31 69 60 40 7 School 88 12 86 14

2.13.6 Housing Conditions 47. To collect information on housing conditions in the project area, houses were categorized as pacca, semi-pacca and kacha. The house / structure in Pacca category is constructed with concrete or bricksusing concrete slabes for the roof and cemented floor,

14 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

whereas in semi-pacca category, the construction is made with burnt bricks and mud using girder,T-iron and tiles for the roof and burnt bricks fitting on the floor. The kacha house is constructed with un-burnt bricks and mud, or temporary wooden planks with thatched roof and floor with kacha surface ground. The information about the housing conditions of the respondents reflects that 85 percent of the respondents live in semi-pacca houses followed by 10 percent living in kacha houses.Only five percent large farming community is living in pacca house. 2.13.7 Women’s Role in Socio-economic Activities 48. The female are more than half (51%) of the total population in Pakistan. Subsequently, gender survey was carried out in the project area to differentiate social and economic roles between women and men. The respondent’s women were belonged to all walks of life like farming, school teachers and health attendants etc. The distribution of the female respondents is the Table 2.12. Table 2.12: Women Respondents Sr. # Location No. of Respondents 1 5-AR Distributary 12 2 5-L Distributary 14 3 2-L / Wahab Minor 9 4 12-L Distributary 15 5 1-R / 12-L Minor 5 6 2-L / 9-L Minor 17 7 7-AR Distributary 21 8 11-L Distributary 8 Total 101 49. The survey revealed that the participation level of women in various socio-economic activities is generally high (100 percent) in case of household activities including child caring as compared to their involvement in farming activities, livestock rearing, sale/purchase of property. Their involvement was assessed as 74, 70 and 22 percent respectively. Regardless of this that they are an integral part of Pakistan’s rural society their literacy rate is only 31% of the total. Table 2.13 Women’s Role in Routine Activities Physical Decision Sr. #. Item Participation (%) Making (%) 1 Household Activities 100 100 2 Child Caring 100 100 3 Farm / Crop Activities 74 20 4 Livestock Rearing 70 17 5 Sale & Purchase of Property 22 18 50. Women of the area were playing active roles in household activities, which includes cooking, washing, dusting/cleaning, carrying of fodder for livestock, bringing potable water for household consumption and child caring. They were also actively participating in farming activities such as hoeing, harvesting, picking, grain storage and making dung cakes for fuel purposes. The detailed summary of consultation meetings with the women respondents regarding their concerns/issues/suggestions is provided in annexure-8.In general the the women supported the project execution, as they perceived that it was beneficial to their livelihoods. 2.13.8 Conflict Resolution Mechanism in the Project Area 51. Generally, local disputes are settled through Panchayat. Panchayat is an informal but well organized conflict resolving mechanism exists in the project area.This system has also been regularized in the prevailing local bodies system. Yet most of the conflicts and disputes

15 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP) are being settled through panchayat. According to the Panchayat mechanism, the influential of the area, a community representative, local religious leader and villageNumberdar play their role to resolve the reported dispute / conflict with mutual consensus, after hearing the parties. If any of the party is not satisfied with the decision of the Punchayat, then they are free to lodge complaint to police station or court of law. Generally, the people prefer to settle their disputes through the Panchayat to avoid enmity, wastage of time and resourcesy.

2.14 Asset Valuation 52. For non-land assets including structures of different types, the unit compensation rates were finalized after consulting composite schdule rates of Communication and Works Department for the year 2011-12. Also, a valuation survey was undertaken by the field engineers and resettlement team for calculating the unit rates. Asset valuation was made in consultation with the community/ affected people at current market rates. The rates of different items were also collected from government contractors for construction of Pakka, Semi-Pakka and Kacha rooms for comparison / verification purpose. Using these data, the unit rate used for the valuation of affected structures was adjusted to meet the level of replacement costs. (Annex-12.1 to 12.5, 15).

2.14.1 Standard Rates Adopted For the Assets 53. The following procedures/ methods were used for the assessment of unit compensation values of different items/ assets located within the CoI as standard for valuation of assets as given in Table 2.14. Compensaiton Rates • Private land has been temporarily leased for 3 years at a neogitated price of Rs. 50,000/per acre/per year. This price is 43% higher than the prevailing lease price of Rs. 30,000/ to 35,000/acre in the area. The reason for allowing a higher compensation rate is to ensure that all APs are compensated according to ADB’s IR policy requirement of replacement cost, further enabling them to restore or improve their livelihoods with this compensation amount even higher than replacement costs. • Residential and commercial structures are valued at (2011/12) replacement value/cost based on cost of materials, type of construction, labor, transport and other construction costs.

Allowance • Shifting allowance will be provided to the APs shifting of affected structures; private and community structures. • Vulnerability allowance will be provided to vulnerable/women headed households. Table 2.14: Unit Rates Quantity Type of Sr. Unit Rate Description Unit Measur Construct # Nos. (Rs. /sq.ft.) -ement -ion A. Compensation unit rate for temporary occupation of land Agricultur 1 Private land acre 29.36 50,000/acre e land B. Compensatioin unit rates for private structures

2 Residential & Commercial 1 270 Kacha 310

Sqft 3 Cattle Shed and Sheds 4 652 Kacha 150

4 Patio/Bench 2 44 S. Pacca 110

16 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

1 20 S. Pacca 110 5 Walls / Boundary Walls 5 384 Kacha 80

6 Kitchen 1 99 Kacha 110

7 Kiosk Nos 1 - wooden 5000 C. Govt. Owned Structures/Assets Shifting cost of N Electric Pole 66,458 electric ples os 8 Transformer Shifting N Transformer 10,000 Cost os D. Community Owned Structures/Assets Prayer place and 3 60 S.Pacca 325 toilets S Open yeard/floor for 9 q.f 1 180 S.Pacca 110 praying t Ablution Place 1 48 S.Pacca 325 Prayer place 1 169 S.Pacca 175 E. Trees Private and Forest 10 Private (71) Nos) Timber Wood

F. Government / Forest Trees 11 Govt.Tree Nos Included in EMP

17 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

3 LEGAL AND POLICY BACKGROUND

3.1 Pakistan’s Law and Regulations on Land Acquisition and Resettlement 54. The Land Acquisition Act (LAA) of 1894 is used to regulate land acquisition for public purposeon permanent or temporary basis in Pakistan. It is a provincial law. According to the provisions of LAA, land is valued on the last 3-5 years average of registered land sale rates by the Revenue Department. Due to under-valuation of land, current market rates are now frequently applied by the Revenue Department, plus 15% Compulsory Acquisition Surcharge as provided in the LAA. Based on the LAA only legal owners and tenants registered with the Land Revenue Department or possessing formal lease agreements, are eligible to compensation. Users of Rights of Way (ROW) are not considered "affected" by project activities under this law and thus not entitled to any mitigation measure, compensation, or livelihood support. Also, there is no legal obligation to provide title-less land users, unregistered tenants, squatters or encroachers for rehabilitation either in form of house-for- house or land-for-land replacement, or in form of cash. 55. The LAA also does not automatically mandate for specific rehabilitation/assistance provisions benefiting the poor, vulnerable groups, or severely affected APs, nor does it automatically provide for income/livelihood losses or resettlement expenses rehabilitation. Though, often this is done; it is the responsibility of affected persons to apply for benefits, rather than the responsibility of the project proponent to automatically provide them. However, exceptions to the rule can be explained by the fact that the law is not rigid and is broadly interpreted at the provincial level depending on operational requirements, local needs, and socio-economic circumstances. Recourse is often taken to adhoc arrangements, agreements and understandings for resettlement in difficult situations. 56. Despite all its weaknesses, the LAA of 1894 is the only applicable law, where land is required permanently or temporarily. In this sub-project, most of the civil works will be carried out in the CoI or within the ROW. Land will be required for diversions on different distributaries on lease basis at local prevailing market rates and with the consent of land owners. The clause 35 of LAA 1894 isapplicable for temporary land acquisition in this sub- project.

3.2 ADB’s Involuntary Resettlement Policy 2009 57. The ADB Policy on Involuntary Resettlement is based on the following principles:

• Involuntary resettlement is to be avoided or at least minimized. • Compensation will ensure the maintenance of the APs’ pre-project standardsof living. • APs should be fully informed and consulted on LAR compensation options. • APs’ socio-cultural institutions should be supported/used as much as possible. • Compensation will be made without gender bias. • Lack of formal legal land title will not be a hindrance to compensation/ rehabilitation. • Particular attention should be paid to households headed by women and other vulnerable groupsand appropriate assistance should be provided to help them improve their status. • LAR should be conceived and executed as a part of the project, and the full costs of compensation should be included in project costs and benefits. • Compensation and resettlement subsidies will be fully provided prior to clearance of right of way/ ground leveling and demolition.

18 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

3.3 Comparison of Pakistan’s LAA and ADB’s IR Policy 1995. 58. Differences between Pakistan’s Law and ADB IR policy are outlined in Table 3.1 below: Table 3.1: Summary of Comparison of Pakistan’s LAA and ADB’s IR Policy Pakistan’s Land Acquisition Act, 1894 ADB’ Involuntary Resettlement Policy 1995 Land compensation only for titled Lack of title should not be a bar to landowners or holders of customary rights. compensation and/or rehabilitation. Crop losses compensation provided only Crop losses compensation provided to to registered landowners and landowners and sharecrop/lease tenants sharecrop/lease tenants. whether registered or not Land valuation based on the median Land valuation based on current market registered land transfer rate over the rate/replacement value previous 3 years. Disputes, complaints and grievances are Land Acquisition Collector (LAC) is the resolved informally through community only pre-litigation final authority to decide participation in the Grievance Redress disputes and address complaints regarding Committees (GRC), Local governments, and quantification and assessment of - and/or local-level community based compensation for the affected assets organizations (CBOs) The decisions regarding land acquisition Information related to quantification and and compensations to be paid are costing of land, structures and other assets, published in the official Gazette and entitlements, and amounts of compensation notified in convenient places so that the and financial assistance are to be disclosed people affected get aware of the same to the affected persons prior to appraisal. No provision for income/livelihood The ADB policy requires rehabilitation for rehabilitation measure, allowances for income/livelihood, for severe losses, and for severely affected APs and vulnerable expenses incurred by the APs during the groups, or resettlement expenses relocation process.

3.4 Remedial Measures to Bridge the GAP 59. Pakistan’s law (LAA) neither provides compensation or assistance to non-titleholders nor does it consider for rehabilitation of the livelihoods of those affected by the project. Project specific resettlement issues have been addressed to assist non-titleholder persons and bridge the gap between existing practice and the main guidelines of the ADB IR Policy of 1995. To clarify these issues and reconcile eventual gaps between Pakistan’s Law and ADB IR Policy, the EA prepared a Resettlement Framework for the Project, ensuring compensation at replacement cost of all items, the rehabilitation of informal settlers, and the provision of r allowances for APs that may be dislocated, suffer business losses, or may be affected.

3.5 Sub-Project Resettlement Principles 60. This LARP is anchored on the philosophy that government development projects must serve the needs of society. The basic principles and guidelines of resettlement include the following: • All APs are equally eligible for compensation and rehabilitation assistance, irrespective of their land ownership status. • The compensation packages shall reflect replacement costs of all assets affected; land, structures/fixtures, businesses, trees and crops and relocation costs for all the losses.

19 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

• The APs would be compensated according to the provisions of ADB approved RF, and IR policy principles and procedures, • Compensation and resettlement will be satisfactorily completed before contractors are mobilized. • APs will be systematically informed and consulted about the sub-project and RP will be made available in local language () to the affected persons and other stakeholders. • The consultative process shall include not only those affected but all the stakeholders.

3.6 Compensation Eligibility and Entitlements

3.6.1 Eligibility for Compensation 61. Compensation eligibility is determined on the basis of the cut-off-date, which is the date of completion of census survey, i.e. 20 March 2013-the date of completion of fresh consultations and preparation of MOUs. People settling in the affected areas after this cut- off-date, will not considered for compensation. They however, will be given sufficient advance notice (at least one month) to vacate the encroached area prior to commencing the construcitobn work.

3.6.2 Compensation Entitlements 62. Entitlement provisions for APs losing land, residential and business structures, sources of income, etc. will include compensation for the loss of structures at replacement cost basis. In addition, they will be also paid transportation allowance for shifting of their affected structures. Table 3.2: Allowances to be paid Entitled HHs Sr. No Description Unit Unit/Rate(Rs.) (No.) 1 Shifting Allowance Rs/AHH 9(Annex-6) 2,000/AP 2 Vulnerable Allowance Rs/AHH 12,500 (OPL)

3.6.3 Entitlements Matrix (EM) 63. Resettlement tasks under this sub-project will be implemented according to the compensation eligibility and Entitlements Matrix (EM) in accordance with the provisions of the ADB approved LARFfor LBDCIP. The EM is provided in Table 3.3. Table 3.2: Entitlement Matrix (EM) Type of Loss Entitled People Compensation Entitlements Temporary Acquisition Land Owners Negotiated land lease price @ Rs. 50,000/acre/year of Land for 3 years. Private Trees Owners/tenants Fruit trees: compensation to reflect income replacement as assessed by Agriculture department based on market value of annual produce, projected for number of years the tree can potentially produce fruit. Non-Fruit trees: will be compensated at a cost equivalent to market price of fuel wood available from each tree based on the unit rates as provided by the Forest Department.

20 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Trees (government) The cost has been calculated in light of the notification No.SOFT (EXT) VII-4/200 dated 5.11.2008, of the Punjab Forest Department, wherein, the cost for replenishment of 500 trees at one Avenue. Mile for five years is Rs. 59,300/- The replenishment cost at the rate of Rs 119/tree (59300/500) will be paid to the APs. The uprooting and replenishment of govt. trees will be addressed in the EMP. Residential and All relevant APs Cash compensation at replacement costs basis for Business Structures/ affected structure and other fixed assets. assets with full or In case of partial impacts, full cash assistance to partial losses restore remaining structure.

Rs. 5000/- as wear and tear cost for wooden kiosk

and shed.

Allowances: All APs (including One time paid an amount of Rs. 2,000/= as shifting Shifting allowance for Informal settlers) allowance. private structures whose structure are affected

Vulnerability APs below poverty One time cash compensation based on 3 months allowance line including income at official poverty line @ 12,500/month (i) 3 women headed women headed households losing households and more than 10% of those losing >10% income generating of income land. generating (ii) 5 women headed resources. One month’s salary @ official poverty line, Rs. households 12,500/ rounded figure. Shifitng allowance for Representative of Full costs of structure/ asset at replacement basis. cumminuty/ religious the Managing structures. body of the affected asset

Unanticipated impacts In case of any unanticipated impacts during the project implementation, the impacts will be addressed/compensated at replacement costs and in line with the entitlements provided in the approved framework (LARF).

3.6.4 Memorandum of Understanding (MoU) 64. A Memorandum of Understanding is signed between the APs and PMU (ESSU representative) with mutual agreement on rate of land lease and terms and conditions for the lease of land and compensation for the construction of a temporary diversion channel (Copy of MoU is appendix as V). A formal agreement will be signed and compensation amount will be paid to the AP before initiation of civil work activities which is expected in April, 2013. PMU will provide addendum to the approved LARP on final lease and payment deeds based on construction schedule as mentioned in the implementation schedule.

21 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

4 CONSULTATIONAND GRIEVANCE REDRESS PARTICIPATION 65. During impact assessment, frequent consultative meetings, and focus group discussions were conducted with the community and stakeholders “viz a viz” ID, PIDA, Local Government Representatives, Local Welfare Societies and community representatives. During these meetings the project objectives were explained to the participants. Their concerns and suggestions were documented and taken care of to enhance the project acceptability. Mostly their concerns were related to the assessment and payment of compensation for their lost assets. During field visits series of public consultations and scoping sessions were carried out at various locations on ICB-05. Fresh consultations were also carried out in March 2013, in which land lease price and other related matters were discussed. The main objectives of the consultations included: • Introduction of the LBDCIP; • Rapport building with the local people and APs; • Assessment of the impacts of sub-project and their mitigation; • Introduction of ADB funding and involuntary resettlement policy to the stakeholders; • Compensation, entitlements and disbursement policy; and • Explanation of monitoring and evaluation process of the implementation of this RP.

4.1 Document Disclosure 66. The summary of this LARP will be translated into Urdu and will be disclosed to the APs at PIU and respective offices of Sub Divisional Officers Sahiwal Division, after ADB approval. The RP in English will also be made available in the offices of Superintendent Engineer (SE) LBDC Circle and Executive Engineer of relevant Division. An information brochure in Urdu summarizing important information about affected assets valuation, entitlements, compensation rates, complaint procedure, and payment andcompensation provisions will be sent to all APs.

4.2 Consultation with APs 67. The consultation process was initiated by holding a consultative meeting with the stakeholders on the following distributaies and minors. The participants in consultations included the APs, farmers, businessmen/ shopkeepers and laborers. Scoping sessions werealso held with the APs. The concerns and issues raised by the participants are similar as in the previous packages because of same project activities, communities and the area. The summary of public consultations is given in Table 4.1and details are provided in Annexure-3. Table 4.1: Summary of Consultations Sr. No. Name of Channel Date Participants 1 5L Gamber DY 20,21-12-10 14 2 1R/5L Kator wala MR 10 3 1L/1R/5L Sub MR 23,24-12-10

4 2R/5L Pakhi MR 5 1L/2R/5L Sub MR 6 2L/2R/5L Sub MR 26-12-10 12 7 3R/5L MR 8 4R Jhil wala DY 9 1L/4R Naubahar MR 27,28-12-10 7 10 1R/4R MR 11 2R/4R MR 12 3R/4R MR 29-12-10 & 03-1-11 10

22 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No. Name of Channel Date Participants 13 5R Yousaf wala DY 14 5AR DY 15 2-L/1-L/9-L Minor 16 1L/9L MR 17,19,-01-11 8 17 1L/1L/9L Sub MR 18 2L/1L/9L Sub MR 19 9-L disty 2-2-11 to 4-2-11

20 2L/1L/9L Sub MR 38

21 1R/1L/9L Sub MR 7-2-11 to 8-2-11 22 2L/9L MR 23 1L/2L/9L Sub MR 24 1R/9L Bara MR 9-2-11 to 11-2-11 12 25 3L/9L MR 26 1L/3L/9L Sub MR 27 2R/9L MR 28 4L/9L MR 22,23-2-11 10 29 1R/4L/9L Sub MR 30 5L/9L MR 31 3R/9L MR 32 4R/9L MR 24-2-11 8 33 5R/9L MR 34 6R Sahiwal DY 35 1R/6R MR 1-3-11 to 2-3-11 16 36 2L/6R MR 37 6CR DY 4-3-11 10 38 6BR DY 39 Bahab DY 40 1L/Bahab MR 5-3-11 & 13-3-11 14 41 2L/Bahab MR 42 1L/2L Bahab Sub MR 43 6AR DY 44 9AL DY 14,15-3-11 12 45 6DR DY 46 10L Harappa DY 16-3-11 6 47 11L Dad Fatiana DY 17,18-3-11 30 48 1L/11L MR 49 1R/11L MR 19,20-3-11 14 50 2L/11L MR 51 3L/11L MR 52 7R Bakerke DY 53 1R/7R MR 54 2R/7R MR 21,22-3-11 20 55 1R/2R/7R Sub MR 56 7AR DY 57 12AL DY 25-5-11 8 58 12L DY 26-5-11 to 28-5-11 30 59 1R/12L MR 29-5-11 14 60 1R/1R/12L Sub MR 8-6-11 8 61 2R/1R/12L Sub MR 62 1L/12L MR 63 2L/12L MR 64 3L/12L MR 10,13-6-11 14 65 1L/3L/12L Sub MR 66 1R/3L/12L Sub MR 67 2R/12L MR 14,15-6-11 20 68 3R/12L MR

23 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No. Name of Channel Date Participants 69 4R/12L MR 70 7AR/I DY 71 13L DY 72 7BR DY 16,17-6-11 16 73 7CR DY 74 13AL DY 75 14L DY 20,22,24-6-11 30 76 2R/14L MR 77 3R/14L MR 30-6-11 12 78 1L/14L MR 79 2L/14L MR 80 14AL DY 81 7DR DY 12-7-11 13 82 7ER DY 83 1R/7ER MR 13-7-11 10 84 14BL 1st DY 85 14BL 2nd DY 29-7-11 8 Total 434 68. The outcome of the consultations indicated that in general, people were aware of the proposed project and were of the view that the improvement of LBDC and its related irrigation distribution network will make a positive impact on the incomes of the small/ poor farmers and the overall economy of the area.The major socio-economic concerns and issues raised by the community are discussed as under. 69. Concern Raised: Restricted mobility of common people on the bank of channel during the construction was feared by some participants.

70. Proposed Mitigation: Alternative routes have been provided at the construction sites for the free mobility of the people and their livestock.

71. Concern Raised: Some farmers highlighted their concern about water logging and seepage due to canal diversion.

72. Proposed Mitigation: The engineering team briefed them that proper compaction and stone pitching along the diversion has been provided in the design of the sub- project to stop any adverse effect on their lands and structures.

73. Concern Raised: After compleltion of the project, who will restore the land acquired by the project?

74. Proposed Mitigation: They were assured that as per agreement the contractor is bound to restore and rehabilitate the occupied lands.

75. Concern Raised: What about the mode of payment of the leased land?

76. Proposed Mitigation: The payment will be made in full to the owners prior to the start of civil works as per provisions of the RP. No work will be started if the payments are not made.

77. Concern Raised: People inquired whether they would get jobs in the project.

78. Proposed Mitigation: They were told that according to the clauses 6.1, in the contract documents the contractor will employ the un-skilled labour(male and female) from the localarea, as far as possible.

24 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

79. Concern Raised: Compensation, resettlement/ relocation to the APs should be made prior to the execution of the project.

80. Proposed Mitigation: The APs were assured that the RF approved by the ADB clearly describes that all the payments to the APs should be cleared before the start of civil works.

81. Concern Raised: Cattle ghats and washing places at existing locations or even at new locations should be provided.

82. Proposed Mitigation: The APs wereexplainedthat walk through surveys with FOs/KPs in association of PMU/PIU were carried out to incorporate the community demands in the designand 84 cattle ghats, 67 washing placesand 96 human crossing at suitable locations have been provided in the design.

83. Concern Raised: Non-availability of irrigation water during the execution of civil works on ICB-05 was feared by majority of APs. They were of the view that civil works should be carried out during canal closure period or diversions should be made to ensure regular irrigation supplies.

84. Proposed Mitigation: The APs were explained that as far as possible, the project works will be carried out during closure of channel. In addition, diversions at different 42 locations have been provided to ensure the un-intruppted channel flows.

85. Concern Raised: The religious places like mosque shouldbe protected and reconstructed in case of any loss to these structures.

86. Proposed Mitigation: The people were ensured that in line with the ADB policy, all efforts have been adopted to avoid/ protect any such place if falling in the CoI. However, if it is un-avoidable, then a structure of the same dimensions will be constructed on replacement cost basis at a proper location in the nearby vicinity.

4.3 Consultation with Local Women and Community 87. Consultations, sessions with the local women were also held. Female sociologist conducted these consultations along with their male counterparts. The women of the area were keen interested in participating in the consultations. They included housewives, students, and head of households, widows, school teachers and farm workers. The majority of them were illiterate or functional literate. Most of them belonged to poor families living in small houses / katcha houses. They showed the following issues and concerns, associated with this sub-project. 88. Most of the women suggested that some ponds along the channels near the villages should be constructed for washing clothes and crockery, bathing their children as well as for other similar activities. 89. Risk of safety, security and privacy will be increased due to outsiders working during construction work on the channel. 90. For most of the concerns / issues raised by the women, adequate provisions have been made in the design like provision of 67spots for washing of clothes/ bathing their kids and 84cattle ghats. 91. The issues raised by stakeholders / APs regarding temporary negative impacts on the incomes of their spouses have been adequately addressed and incorporated in the RP and proper compensation and income restoration strategy as explained in Section 4.2 has been provided.

25 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

4.4 Consultation with Other Stake Holders 92. Consultations, sessions with other stake holders including Government Officials from relevant Government Departments (Irrigation, Forest, Revenue, Buildings and Agriculture) were also held. During the consultations, issues pertaining to the encroachments in the RoW, removal of trees, and impact assessment were discussed. 93. In the , a few NGOs exist mostly for emergency events like accidents and floods.There are some Community Organizations (COs), formal and informal, playing their roles for the well being of the people. These, however have no capacity and experience in the resettlement planning and implementation of RPs. In the project area, the following COsare working with their specific objectives. Name of Sr. Role In RP Community Objective No. Implementation Organization Punjab Rural To assist poor families through small loans to No role in RP 1 Support Program improve their livelehood. implementation (PRSP) To provide first aid in emergenecy and No role in RP 2 Eidhi incidental events like accident, fire and implementation mishapes. APO Welfare socity for providing educational and No role in RP 3 (Active Help health assistance to improve quality of lives of implementation Organization) margional people. It is functioning purely under political shedow. No role in RP 5 Kissan Wing No broad vision to improve farmars socio - implementation economic conditions. Farmer Yes,during 6 Currently formed through PIDA. Organization (FO) project activities To provide free catering & tents at the time of death and funeral to poor families. Al-Madina Welfare No role in RP 7 To provide cash assistance to the poor families Trust implementation for their daughters marriages. Financial and social support to poor parents. Social Welfare To support the poor people in providing No role in RP 8 Society medicines implementation National No role in RP Comission for implementation 9 Human Promotion of adult education Development (NCHD) National Education To provide free basic education to poor No role in RP 10 Foundation (NEF) families implementation To provide microfinance to low income wage KASHF No role in RP 11 earners for become prosperous and to alleviate Foundation implementation poverty. To strengthen the economic base of low- No role in RP 12 Kushali Bank Income populace across Pakistan by improving implementation their accessibility to financial services.

26 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

5 COMPENSATION, RELOCATION AND INCOME RESTORATION

5.1. General 94. This section deals with the compensations for affected land, structures and assets that have been identified during the Census Survey as per provisions of the EM. The RP focuses on providing compensations for the lost assets and suggests measures to restore their livelihoods at least to former living standards of the APs.

5.2. Compensation for Affected Land and Assets 95. Privateland will be occupied on temporary basis at 32 (thirty two) locations for diversions, as per provision of section 35 of LAA 1894. The land will be occupied for the period of 03 yearsfrom 56 farmers. The proposed land is cultivated.Total area to be acquired for diversions is 232.5 kanals (about 29.10 acres). The negotiations with the owners of the land were made as per provisions of the LAA, 1894 and a lease rate of Rs.50,000/acre per year was agreed, based on current market rates.

5.3. Compensation for Privately Owned Structures 96. The privately owned affected structures include (i) residential, (ii) commercial (iii) wooden kiosks (khokha) and sheds. The kacha, semi pacca and pacca structures have been evaluated separately.The number of such affected structures and assets comes to 15.The replacement value of these structures have been assessed for compensation on an average unit rate per sq. ft.based on current local material rates, consultation with the affected persons (Section 4.2 of the RP) verified by the C&W department, Sahiwal. The detail of compensation to various types of structures is provided in Table 5.1 Table 5.1: Valuation of Private Assets Details of No. of Area Unit Rate Sr. No. Total Cost (Rs.) Structures Structures (Sq. ft.) (Rs. /sq. ft.) Residential/Commercial Structures 1 a)Room Kacha 1 270 310 83,700 b)Cattle Sheds, Sheds etc 2 Kacha 4 652 150 97,800 c )Patio/Bench 3 S.Pacca 2 44 110 4,840 d)Walls / Boundary Walls 4 S.Pacca 1 20 110 2,200 Kacha 5 384 80 30,720 e)Kitchen 5 Kacha 1 99 110 10,890 f)Other Structures 6 Kiosk(Khokha) 1 0 5,000 5,000 Total: 15 1469 - 235,150

5.4. Compensation of vulnerable affected persons 97. There are 7 women headed households considered as vulnerable in the project area. They will be provided a vulnerability allowance for 1 – 3 months based on OPL of Rs. 12,500/month.

27 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

5.5. Compensation for Community Owned Structures/Assets 98. The affected community structures / assets include one prayer place, one ablution place (annexure-4). No other community structures like community centre, schools and archaeological monuments, etc. fall within the CoI. The extent of loss to the community structures is compensated adequately.It is proposed to construct the affected structures and fixtures at replacement cost basis for which a provision of Rs. 84,475/= has been made in the resettlement budget, as detailed in Table 5.2. Table 5.2: Valuation of Affected Community structures Unit Total Sr. Details of Nos. of Area Rate Estimated Structure/Asset Cost No. Structures Structures (Sq.ft) (Sq. Cost(Rs.) (Rs.) ft) Prayer 1 Prayer Place 1 169 175 29575 29,575 Place Toilets 3 60 325 19500 2 Mosque Ablution Place 1 48 325 15600 54,900 Floor 1 180 110 19800 Total 6 457 - 84475 84,475

5.6. Compensation for Public Structures/Assets 99. The survey has revealed that 74 electric poles, 03 transformers and 03 PTCL poles are being affected (Annex-5) in this sub-project. These structures/assets will be compensated through the relevant departments. A provision of Rs.66,458/- per as relocation cost of electric pole,Rs.10000/- per relocation cost of PTCL pole and shifting charges of transformer @ Rs.10,000/= per unit has been provided in the resettlement budget amounting to Rs.58,55,142/-. Rate is based on demand notice of WAPDA as provided vide Annexure- 14.

5.7. Compensation for Privately Owned Trees 100. A total of 71 privately owned non fruit trees have been identified in the CoIof 1-R/12-L minor.Non-fruit private trees (wood) are compensated @ Rs.119 X 10 = 1190/- Rs. per tree with salvaging the tree wood. The cost has been calculated in light of the notification no. SOFT(EXT)VII-4/200 dated 5.11.2008, of the Punjab Forest Department, wherein, the cost for replenishment of 01 Ave. Mile at 10x10 spacing for five years has been determined as Rs. 59,300/-Therefore, the cost for replenishment of one tree comes up to 59300/500 = 119 Rs. A detail of the estimated compensatory plantation cost is explained in section2.16.

5.8. Compensation for Govt.OwnedForestTrees 101. The replenishment cost for the government owned trees falling in the desiganated CoI will be paid to the Punjab Forest Department.The ForestDepartment will carryout replenishment of these trees.The Compensatory budget is allocated in the EMP.

5.8.1 Relocation of Religious Structures 102. Oneprayer placeon9-L Ganjibar disty at RD 5+200 will be affected during project works. A structure related to prayer place at RD 14+500 of the same disty will also be affected. Undertakings to relocate/reconstruct the structures have been obtained from committees, who maintain these structures.

28 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

6 INSTITUTIONALARRANGEMENTS

6.1. Institutional Set up 103. The following institutional arrangement has ben set up within PMU to manage the LAR iactivities including the prearation, updation, implementation and monitoring of resettlement plan: • Irrigation Department (ID), Government of Punjab as project proponent, • Project Management Unit (PMU) as implementation agency, • Local Government (Revenue department) as identification and verification of land/assets

104. The detailed responsibilities of each Departments\Agencies involved in the resettlement process are given below.

6.2. Irrigation DepartmentPunjab 105. ID through its Project Management Unit (PMU) has overall responsibility for the implementation and financing of all resettlement tasks as cross-agency coordinator. The PMU will execute the project through the Project Implementation Unit (PIU), tasked with day- to-day sub-project activities. Within the PMU, resettlement tasks will be managed by Land Acquisition and Resettlement Unit (ESSU), which will organize the resettlement tasks, internally monitor LARP preparation and its implementation (including surveys, asset valuation and public consultation), resettlement related cross-agency coordination and LARP approval. In implementation of these tasks, the ESSU will get specific technical assistance from: 106. A Resettlement Specialists Team under the PMU Support Consultants, which will assist in resettlement planning, implementation, internal M&E and training of PMU staff in accordance with the provisions of ADB approved RF; 107. An Independent Agency for external monitoring hired by the PMU to conduct periodic monitoring and evaluation as the third (external) party validation for monitoring of resettlement activities.

6.3. Local Government 108. Local Government has its jurisdiction for land administration, valuation and other resettlement related activities. Since permanent or temporary land acquisition will involve in sub projects, therefore, active involvement of District Revenue Department is essential in identification, is required. A number of other supporting officials, most notably the Patwari, (the land record keeper) will carry out specific roles such as title identification and verification in the resettlement process.

6.4. Coordination Initiatives 109. A number of provincial departments and agencies have been identified for the effective, smooth and timely completion of different activities for the successful implementation of the project. In order to ensure proper coordination between various implementing agencies, the following three coordination committees would play their respective role in a synchronized manner, as required under RF of the sub project.

6.5. LAR Steering Committee: 110. LAR Steering Committee at Provincial level is established on 12th December, 2009 vide notificationNo.SO (Evl) IRRI/1-22/2006-II, attached as Annexure-15. This Committee is

29 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP) proposed to meet periodically to ensure the proper and timely formation of the Advisory Committees in the Project Area at District level.

6.6. LAR Advisory Committee: 111. The Committee is formed at District level in the project area. The aim of this set up is to provide coordination mode for RP preparation and its implementation in a timely manner. The LAR Advisory Committees for Sahiwal and Okara Districts are formed vide No.PD (LBDCIP) LAR/2193-B-Dated-1st January 2010 shown as Annexure-16.

6.7. Grievance Redress Committee: 112. The GRC will facilitate the process of resolving the issues and complaints of the APs. The Deputy Director (Community Relations), ESSU-PMU will be focal person and responsible for co-ordination between the members of GRC and the complainant. He shall make all arrangements to convene meetings of the committee and compile the record of each meeting. The GRC will convene its meetings on as and when required basis, or upon receipt of the grievance complaint as detailed in the Grievance Resolution Mechanism. Such meetings will be convened either in the office of the Chairperson of GRC, or in the offices of the PIUs at Sahiwal. 113. The establishment of GRC is under process. It shall comprise of members from ESSU, XEN/SDO, DO (Revenue) and a representative of APs. The GRC is not a regular body requiring specified premises for office. However, space at PIU office as well as logistics support will be provided to the GRC. Thus, special budget for establishment of the office of the GRC will not be required. The expanses of the ex-officio members of the GRC incurred to attend such meetings will be reimbursed as payment of Traveling and Daily Allowances to the attending members from the contingencies provided in the resettlement budget.

6.8. Need for Establishing a Grievance Redress Mechanism 114. LAR relating issues are identified in the RP and mitigation measures are suggested to address these issues vide ofEntitlement Matrix (EM). However, in spite of best efforts, there is every chance that the individuals / communities affected by the project are dissatisfied with the measures adopted and they look forward some platform for the resolution of their grievances. Some of the grievances that may arise are listed as follows: • Name of the AP is missing from the list, • Losses (such as damage to crops/ assets) not identified correctly, • Inadequate or inappropriate assessment of compensation., • Improper distribution of compensation in case of joint ownership • Dispute on ownership of the affected asset • Problems in the relocation of infrastructure • Delays in the payment of the compensation • Owners’ reluctance to allow commencement of works on their affected property before payment of compensation • Any other issues arising during the project implementation. 115. In order to ensure the timely and successful implementation of provisions of LARP a Grievance Redress Mechanism (GRM) has been established, as per guidelines of the ADB. The objective of GRM is to address the grievances of the aggrieved at the root level. The GRM allows an AP to appeal against any decision, practice or activity, he disagrees with. Thus, the main objective of the GRM would be to mediate conflict and cut down on lengthy litigation, which often delays such infrastructure projects.

6.9. Grievance Redress Procedure 116. The following modus operandi of the GRM has been envisaged for its efficient and

30 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP) effective functioning.

6.10. Formation of a Grievance Redress Committee (GRC) 117. The formation of a Grievance Redress Committee (GRC) at sub-project levelis underprocess, which will be a part of institutional arrangement for successful implementation of the project.

6.11. Maintenance of a Social Complaint Register (SCR) 118. The Dy. Director- PIU, assisted by the Assistant Director-PIU will maintain the Social Complaint Register (SCR) at the work sites to document all complaints received from the local communities. The information recorded in the Register will include date of the complaint, particulars of the complainant, description of the grievance, actions to be taken, the person responsible to take the action, movement of the document (forwarded to whom / which Committee), follow up requirements and the target date for the implementation of the mitigation measure. The register will also record the actual measures taken to mitigate these concerns. All complaints received in writing or received verbally will be (written), properly recorded and documented.

6.12. Conflict Resolution Procedure 119. The PD, PMU has the overall responsibility for ensuring compliance with the LARP provisions for satisfactory project implementation through ESSU. The PD, PMU will be supported by the Dy. Director (Community Relations), PMU; in turn assisted by the Dy. Director and Assistant Director, Project Implementation Unit (PIU) stationed at project site office to attend matters relating to resettlement. 120. The DD-PIU will be the initiating authority to address the issues. He will be bound to resolve the issue within 7 days in accordance of the provisions of the RP and will inform the complainant. However, if in some cases, policy matters are involved, the case will be referred to the appropriate authority or committee appointed by the Project to decide the matter. 121. If complainant is not satisfied with his decision / action, the DD-PIU will refer the case to GRC. The complainant will be kept associated with the proceedings of the GRC. The GRC will take a decision within 15 days and will intimate the decision to the complainant. In case some response on the complaint is not received within 21 days of the lodging of the complaint, the complainant may send a reminder to the GRC with 07 days notice to take legal remedial measures. 122. In case of complainant’s disagreement with the decision of the GRC, the DD (CR) as Chairman of the Committee will send the case to PD, PMU through Director, ESSU-PMU. The Director, ESSU will submit the case to PD, PMU with his observations on the matter and will respond back within 07 days of the receipt of case in the PD office. 123. In case of such eventualities, all affected persons will be exempted from legal and administrative fees made / paid / incurred pursuant to the grievance redress procedures. The conflict resolution process at project level is provided in Table 6.1.

31 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Table 6.1: Conflict Resolutaiotn Process at Project level

Responsible Stage Action Location Complaint Resolution Period Body

PD Office / Complaint is Dy. Director, 07 days from the date of 1. received and Project Site registration (if not settled then PIU registered Office Stage – 2)

Passed on to Within 15 days 2. Grievance Redress At project site GRC (if not settled then Stage – 3) Committee 07 days from the date of PD, PMU, Dy. Director (CR) receipt of case in the PD through Referred to PD, PMU ESSU-PMU (as office. If AP is not agreed with 3. Director by the GRC the chairman of the mitigation / decision (E&SSG) GRC) provided, he has the option to ESSU-PMU go to court of law.

6.13. Training in RP Implementation 124. Orientation to specific project activity is pre-requisite requirement. It facilitates to have similar approach for the participants and stakeholders including EA, PMU, local government and Consultants. For this purpose, one week training program is planned to all relevant officials of Local Government, ESSU/PIUS, -and the Consultants. The training will be provided by the Resettlement Specialist (PMU). The training session should have the following topics to be covered: (i) Resettlement Parameters • Elements of resettlement • Principal of resettlement • Mechanism of resettlement • Implementation of resettlement

(ii) Principles and procedures of land acquisition • ADB policy on Land acquisition, • Assessment and measurement of temporary/permanent land acquisition, • Identification of owners of private land/ assets,

(iii) Entitlements, Compensation and Disbursement Mechanism on, • Assets to be affected • Valuation of assets • Preparation of Entitlement Matrix • Compensation of the affected assets

(iv) Dispute Resolution and Redressing Grievances of APs • Type of dispute, which may arise • Mechanism to categories these disputes • Mechanism to resolve these disputes • Final undertaking of APs

32 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

7 RESETTLEMENT BUDGET AND FINANCING 125. As shown in Table 7.1, the total budget for resettlement activities comes to as Pak Rs.13.56 million (US$ 0.14 million).The replacement cost of assets/structures is based on current market price determined by the LBDC Design Consultants. The PID will set aside and provide this amount in an efficient and timely manner during the course of the project. Table 7.1: Total Cost of LAR and related Activities Description of Sr. No. Units/qty Cost in Rs. Reference Affected Items A. Compensations a) Residential /Commercial Structures 1 Rooms 1 83,700 Table 5.1 Cattle Sheds/ 2 4 97,800 Table 5.1 Sheds 3 Patio/bench 2 4,840 Table 5.1 Walls / Boundary 4 6 32,920 Table 5.1 Walls 7 Kiosk 1 5,000 Table 5.1 8 Kitchen 1 10,890 Table 5.1 Sub Total (a) : 235,150 15 b) Land for Lease and Private Trees 9 Land Lease Acre 4,474,675 Annex-3 Trees Private 10 Nos 84,490 (71x1190) Land occupation 11 217,969 Charges @ % 5 Sub Total (b) : 4,777,134 c) Allowances Transport 12 9 18,000 Annex -6 Allowance Vulnerablity 13 Allownce Women below OPL & losing >10% of 13a provductive land-3 3x3 112,500/ months salary @ OPL of 12,500/ Women headed households-1 13b 4 50,000/ months salary @ OPL of Rs. 12,500/ Sub Total (c) : 180,500/ d) Community/Public Structures 13 Mosque 1 54,900 Table 5.3 14 Prayer Place 1 29,575 Table 5.3 15 Electric Pole 74 4,947,892 Annexure-5 16 Telephone Poles 2 20,000 Annexure-5 17 Watercuorse 1 887,250 Annexure-5 Sub Total (d) : 5,939,617 Sub Total (A) = {Total(a)+(b)+(c)+(d)}: 11,132,401

33 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

B. Training & Monitoring 18 Field Staff Training Lump sum 100,000 Monitoring & 19 Lump sum 1,000,000 Evaluation Sub Total (B) : 1,100,000 Total (A+B) : 12,232,401 C. Contingencies LARP Implementation Charges @ 1 20 120,699 percent of (A+B) 21 Contingencies @10per cent of (A+B) 1,206,990 Sub Total (C) : 1,327,689 One US$ = Pak Rs. 97 Total Cost Rs : 13,560,090 US$ 0.14 million

34 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

8 IMPLEMENTATION SCHEDULE OF UPDATED LARP 126. After ADB approves the final LARP, the PMU will start implementing the plan according to LAR activities, timed and synchronized with construction schedule. The contractor shall carryout his civil works synchronizsed with the RP implementation schedule in concurrence with ADB. Final MOUs have been signed with all APs identified based on final engineering design. However, land lease and compensation agreements will be signed with final list of APs to be confirmed after the contractor makes the shops drawing and construction schedule available to the PMU. The PMU will then sign lease agreements with final APs and make them the payments. ADB will be informed about final list of Aps and lease agreements through the addendums, as and when required, and notice ot proceed to to civil works will only be issued after confirmation of payments to the APs by external monitor. The PMU will provide to ADB both (i) addendums, and (ii) external monitoring report of the implementation of LARP. After the fresh cut-off-date of 20 March 2013, if PMU finds that new encroachers or squatters have entered into the CoI, the PID/PMU will send notices to such encroachers to vacate the space within 30 days, after which PMU will clear the land from all incumberances and hand over the land to the contractor for civil works. No compensation will be given to such enroachers/squatters, although they will be allowed to salvage the material, if any. LAR activities and implementation schedule is explained in the table below: Table 8.1: Updated LARP implementation Schedule Sr. No. Action Responsibility Timeline Memorandum of understanding on land lease 1. PMU/ESSU Done conditions signed with APs Lease agreements and payment of Based on contractors compensation to the APs to be finalized 2. PMU/ESSU construction schedule, based on contractor’s construction schedule as mentioned in MOUs and shop drawings. 3. Internal monitoring report PMU/ESSU 30 April 2013 4. External monitoring PMU/EMA 30 June 2013 Section by section/distributory by 5. Handing over of sites PMU distributor. Reference MOU 6. Contractor mobilization PMU Feb 2013 Section by section/ distributory by 7. Construction Schdule PMU distributor. Reference MOU 8. GRC establishment, notification PMU Notified 9 Submission of updated final LARP ESSU 31 March 2013 10. ADB approval. ADB 5 April 2013 Translation and Disclosure of LARP, 11. ESSU 20 April 2013 Uploaded at ADB & Govt. websites Section by section/distributory by 12. Compensation Disbursement ESSU/PIU distributor. Reference MOU Distribution of Relocation Notices / 13. Demolishing / Relocation of Affected ESSU As above Structures / Assets etc. 14. Complaints and Grievance PMU, ESSU Continous Process LARP Iemplemented and internal monitoring 15 PMU/ESSU Section by section report provided to ADB

35 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No. Action Responsibility Timeline 16. Confirmation by EMA EMA Section by section

8.1. Process of LARP Implementation 127. The LARP will be implemented by PMU through Land and Resettlement Unit (ESSU). The ESSU will be assisted by the PIUs, representatives of APs and PMU Support Consultants. The ESSU will keep the APs informed about the sub-project activities, compensation and assistance package duly approved by the IA and ADB. APs will also be involved in the grievance redress to review and resolve any dispute concerning compensation and other resettlement issues. The whole process shall be monitored and evaluated by a third party throughout the implementations cycle. Table 8.2 provides timeframe (Activity Schedule Chart) for implementation of LARP. 128. Keeping in view the number of affected structures and extent & magnitude of losses, a 30 days’ advance notice seems sufficient to allow APs to shift/ remove their belongings. All activities will be completed in accordance with the resettlement tasks process.

8.2. LARP Disclosure of LARP and Community Participation 129. This LARP will be translated in Urdu and will be disclosed to the APs at relevant PIU and Union Council offices immediately after the ADB approval. The LARP in English will be posted on the ADB website after the EA endorsement. A primer in both English and Urdu summarizing compensation provisions will be sent to all APs. Besides, a formal mode of communication as transpired above informal modes like oral communication and simple notes as well as display charts bearing important information about affected assets valuation, compensation rates, complaint procedure, payment and civil work schedule etc will be used for the disclosure of the LARP. 130. Moreover, this LARP will be made available to the Local / District Government of Sahiwal as well as PID field office Sahiwal as an official public document. ESSU with the help of PMU Support - Consultants will undertake public disclosure of this LARP all along this sub-project corridor of impact considering the following main objectives: • Inform and explain the entitlement policy and various options to the (APs) prior to payment, compensation and other financial assistance; • Socially prepare the affected persons, particularly house-owners and small business owner operators for removal / relocation; • Help counter rumors and prevent un-necessary distress; • Bring clarity on issues that might be raised by the affected persons, including the affected households and small business owners about their entitlements and benefits; • Solicit and help the APs and encourage their participation in LARP implementation; • Attempt to ensure that vulnerable groups understand the process and their needs are specifically taken into consideration. • The participation of APs is also ensured in the LARP implementation through their involvement in various local committees such as Grievances Redress Committee (GRC). The PID field office and ESSU will establish and continuously maintain interaction with the APs and community to identify problems to undertake remedial / corrective actions.

36 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

9 MONITORING AND EVALUATION 131. Resettlement tasks under this sub-project are subjected to both internal and external monitoring. Internal monitoring will be conducted by the already established Internal Monitoring Cell (IMC) comprising of staff from ESSU and resettlement experts from PMU Support Consultants. The external monitoring and evaluation has been assigned to an Independent Monitoring Specialist who is responsible for EME of this LARP.

9.1. Internal Monitoring and Evaluation 132. Internal monitoring will be carried out routinely by the PMU-LBDCIP. An Internal monitoring and Evaluation Committee has been constituted Vide Notification No.PMU/LBDCIP/IPD/DSG-LAR/0016, dated March 22,2011 as Annexed-17.Indicators set for the internal monitoring are those relating to process and immediate outputs and results. This information will be collected directly from the field and reported monthly to the PMU to assess the progress and results of this LARP implementation, and to adjust the work program, if necessary. The monthly reports will be consolidated quarterly in the standard supervision reports to ADB. Specific monitoring will be: • Information campaign and consultation with APs; • Extent of requirement for clearing the ROW and CoI; • Payment / Compensation for affected structures and other assets; • Payment against loss of income; and • Income restoration activities.

9.2. External Monitoring & Evaluation 133. The project includes provision for external monitoring and evaluation of the implementation of the subproject resettlement plans by an Independent Monitoring Agency (IMA) or individual. For this purpose, an Independent Monitoring Specialist has been inducted.

9.3. Reporting requirement 134. The Independent Monitor will submit quarterly or 6 monthly (as agreed with EA) monitoring reports as per his agreement to PMU for its record and onward submission to ADB. The language of the reports will be English. Illustrations, if necessary, will be provided as part of the reports.

37 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

ANNEXURES

38 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

ANNEXURE 1: LIST OF DISTRIBUTARIES AND MINORS

Length Sr. No. Name of Channel Parent Channel Off Take RD (Miles) Sahiwal Division 1 5L Gamber DY LBDC 257+509 17.74 2 1R/5L Kator wala MR 5L Disty 22+765 11.64 3 1L/1R/5L Sub MR 1R/5-L 41+685 1.14 4 2R/5L Pakhi MR 5L Disty 29+846 11.3 5 1L/2R/5L Sub MR 2R/5-L 23+000 2.9 6 2L/2R/5L Sub MR 2R/5-L 46+940 2.27 7 3R/5L MR 5L Disty 37+000 2.4 8 4R Jhil wala DY LBDC 258+144 13.59 9 1L/4R Naubahar MR 4R Disty 1+920 5.29 10 1R/4R MR 4R Disty 29+675 1.79 11 2R/4R MR 4R Disty 40+000 1.24 12 3R/4R MR 4R Disty 64+500 2.2 13 5R Yousaf wala DY LBDC 285+200 5.04 14 5AR DY LBDC 314+995 1.32 LBDC 322+254 0.65 15 9L DY 9L Disty 3+250 46.57 16 1L/9L MR 9L Disty 3+280 17 17 1L/1L/9L Sub MR 1L/9-L 11+774 1.94 18 2L/1L/9L Sub MR 1L/9-L 23+329 7.79 19 1L/2L/1L/9L Sub MR 2L/1L/9-L 11+076 1.4 20 2L/2L/1L/9L Sub MR 2L/1L/9-L 25+300 2.54 21 1R/1L/9L Sub MR 1L/9-L 28+406 0.89 22 2L/9L MR 9-L Disty 33+085 17.52 23 1L/2L/9L Sub MR 2L/9-L 23+500 2.86 24 1R/9L Bara MR 9-L Disty 53+410 1.42 25 3L/9L MR 9-L Disty 80+472 9.42 26 1L/3L/9L Sub MR 3L/9-L Minor 9+710 1.29 27 2R/9L MR 9-L Disty 104+457 4.17 28 4L/9L MR 9-L Disty 110+500 7.32 29 1R/4L/9L Sub MR 4L/9L Minor 11+500 3.08 30 5L/9L MR 9-L Disty 137+000 5.82 31 3R/9L MR 9-L Disty 138+597 2.5 32 4R/9L MR 9-L Disty 184+550 3.6 33 5R/9L MR 9-L Disty 212+350 1.76 34 6R Sahiwal DY LBDC 328+554 6.9 35 1R/6R MR 6-R Disty 4+090 4.44 36 2L/6R MR 6-R Disty 11+175 4.24 37 6CR DY LBDC 363+000 1.11 38 6BR DY LBDC 366+000 1.63 39 Wahab DY LBDC 387+700 21.21 40 1L/Wahab MR BAPab Disty 16+304 2.3 41 2L/Wahab MR BAPab Disty 38+304 6.36 42 1L/2L Wahab Sub MR 2L/BAPab Minor 20+555 0.8 43 6AR DY LBDC 387+800 2.3 44 9AL DY LBDC 387+847 1.7 45 6DR DY LBDC 402+250 1.6 46 10L Harappa DY LBDC 405+705 4.02

39 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Length Sr. No. Name of Channel Parent Channel Off Take RD (Miles) 47 11L Dad Fatiana DY LBDC 428+772 21.18 48 1L/11L MR 11-L Disty 3+265 1.21 49 1R/11L MR 11-L Disty 52+185 2.34 50 2L/11L MR 11-L Disty 64+280 2.71 51 3L/11L MR 11-L Disty 72+800 2.62 52 7R Bakerke DY LBDC 429+705 5.03 53 1R/7R MR 7-R Disty 2+450 2.12 54 2R/7R MR 7-R Disty 12+176 5.56 55 1R/2R/7R Sub MR 2R/7-R Minor 3+650 4 56 7AR DY LBDC 450+050 7.01 57 12AL DY LBDC 450+304 4.03 58 12L DY LBDC 450+500 39.3 59 1R/12L MR 12-L Disty 20+051 20.1 60 1R/1R/12L Sub MR 1R/12-L Minor 24+780 8.04 61 2R/1R/12L Sub MR 1R/12-L Minor 71+871 1.89 62 1L/12L MR 12-L Disty 46+430 2.5 63 2L/12L MR 12-L Disty 70+336 1.92 64 3L/12L MR 12-L Disty 84+403 13.73 65 1L/3L/12L Sub MR 3L/12-L 15+380 2.16 66 1R/3L/12L Sub MR 3L/12-L 33+000 1.02 67 2R/12L MR 12-L Disty 97+714 6.74 68 3R/12L MR 12-L Disty 147+520 6.68 69 4R/12L MR 12-L Disty 170+700 2.05 70 7AR/I DY LBDC 482+995 0.27 71 13L DY LBDC 483+500 6.85 72 7BR DY LBDC 488+000 2.05 73 7CR DY LBDC 513+243 0.21 74 13AL DY LBDC 513+733 0.41 75 14L DY LBDC 526+965 22.73 76 2R/14L MR 14-L Disty 18+393 2.73 77 3R/14L MR 14-L Disty 24+846 6.5 78 1L/14L MR 14-L Disty 71+246 5.85 79 2L/14L MR 14-L Disty 81+158 3.85 80 14AL DY LBDC 527+000 1.66 81 7DR DY LBDC 527+216 3.21 82 7ER DY LBDC 540+180 4.15 83 1R/7ER MR 7-ER Disty 9+160 0.69 84 14BL 1st DY LBDC 542+000 0.99 85 14BL 2nd DY LBDC 542+000 2.06

40 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 2: INVENTORY OF STRUCTURES OF ICB-05 Extent Total Monthly CoI RoW Area Vulnerable ID Sr. Canal Affected HHs Structure of Structure Structure Cost of RD Location Occupation Income Unit Estimated Allowanc No No Side Person Size Category Loss Affected Type Area Affected (Rs.) L R L R W L Rate Cost e (%) (sq.ft) Structures 4-R Jhilwala Distributary

Khokha Wooden Khalil 5,000 Ahmad

1 1 32+000 Adda 64/4R LS s/o 7 Shopkeeper 14,400 Commercial <10% 27 17 50 35 Patio S.Pacca 4 8 32 9,840 110 3,520 Bashir

Ahmad Bench S.Pacca 2 6 12 110 1,320

Mamora Kitchen Kacha 9 11 99 110 10,890 2 2 43+000 68/4R RS s/o 10 Farming 15,800 Residential <10% 22 43 50 35 23,290

Wahab B.wall Kacha 155 155 80 12,400 Sub Total 17 30200 33130 33130 3R/5L Minor Shahbaz Ahmad

3 1 4+904 58/5L RS s/o 4 Farming 9,000 Residential <10% 20 27 30 25 B.Wall Kacha 0 0 80 6,400 6,400 24,000 80 Shamas Din Sub Total 4 9,000 80 6,400 6,400 0 Bahab Distributary 0

M.Arif Room Kacha 15 18 270 310 83,700 4 30 Tulla Bulla RS s/o Allah 8 Farming 13,000 Residential <10% 20 46 60 39 87,700 0

Ditta B.Wall Kacha 50 80 4,000 Sub Total 8 13,000 320 87,700 87,700 0 2L/Bahab Minor 0 Ameeran Shed Kacha 15 13 195 Bibi w/o 150 29,250 5 1 2+600 Dera Zarein RS 4 Farming 5,000 Residential <10% 20 17 50 28 35,170 24,000 Sultan B.Wall Kacha 0 0 74 (Late) 80 5,920 Sub Total 4 5,000 269 35,170 35,170 0

0 1-L/3L/9L Sub Minor

Shed Kacha 8 8 64 Asmat 150 9,600 Bibi w/o 6 1 1+300 139/9L RS Hafiz 3 Labor 3,500 Residential <10% 18 22 50 35 11,600 24,000 M.Din B.Wall Kacha 25 25 (Late) 80 2,000

Sub Total 3 3,500 89 11,600 11,600 0 0

5-L/9L Minor 0

41 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

M.Haroon

7 1 9+200 161/9L RS s/o 6 Tea Stall 6,500 Commercial <10% 19 34 30 35 Shed Kacha 13 13 169 25,350 24,000 150 25,350 M.Rafique

Ghulam Adda Shabbir 8 2 9+200 RS 3 Tea Stall 6,000 Commercial <10% 19 34 30 35 Shed Kacha 14 16 224 33,600 24,000 162/9L s/o Bashir 150 33,600 Ahmad

Sub Total 9 12,500 393 58,950 58,950 0

10-L Harrapa Distributary 0 Malik Tariq Aziz Govt. 9 1 10+000 LS 1 30,000 Dera <10% 38 15 50 35 Wall S.Pacca 0 20 20 2,200 0 s/o Abdul Job 110 2,200 Aziz

Sub Total 1 30,000 20 2,200 0 2,200 Grand Total 46 103,200 1,469 235,150 235,150 120,000

42 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 3: DETAILS OF LAND TO BE OCCUPIED ON TEMPORARY BASIS - ICB-05

Compensa Affected Area Leas tion of S Ca Total Estim Estimat House Month e Trees Estima r. Locatio nal Cate Area ated ed Total RD Name of AP hold ly Rate/ ted N n Sid gory (Kan Equa Affec Lease Lease Cost Size Incom Equ Kanal Typ Cost of o. e als) Mar l to ted for 1 for three e (Rs.) Kanal al to per e of Tota Trees la Kana Area Years Years Acre year Tre l l % e Tem Mumtaz Hussain p. 1 2+050 54/4-R RS 4 8 2 3 2.15 0.27 26.88 s/o Ahmad Khan 12,000 Land 6,250 13,438 40,313 - - - 40,313 Acq. Tem Allah Yar s/o p. 2 2+050 54/4-R RS 10 8 2 12 2.60 0.33 32.50 Manzoor Ali 10,000 Land 6,250 16,250 48,750 - - - 48,750 Acq. Tem Manik Khan s/o p. 3 2+050 54/4-R RS 6 12 0 7 0.35 0.04 2.92 Waryam 15,500 Land 6,250 2,188 6,563 - - - 6,563 Acq. Tem Ilam Din s/o Noor 4 8+200 55/4-R LS 9 p. 44 4 11 4.55 0.57 10.34 Muhammad 34,560 6,250 28,438 85,313 - - - 85,313 Land

9-L Ganjibar

Tem M.Afzal s/o Khushi p. 5 34+136 136/9L RS 3 64 7 0 7 0.88 10.94 Mohammad 37,650 Land 6,250 43,750 131,250 - - - 131,250 Acq. Tem Zulifaqar Ali s/o p. 6 34+136 136/9L RS 4 12 6 0 6 0.75 50.00 Sardar Mohammad 12,500 Land 6,250 37,500 112,500 - - - 112,500 Acq. Tem Majeedan Bibi w/o p. 7 34+136 136/9L RS 2 14 3 0 3 0.38 21.43 M.Aslam 9,500 Land 6,250 18,750 56,250 - - - 56,250 Acq. Tem M. Akram etc s/o M. p. 8 81+400 142/9-L LS 7 21 6 0 6 0.75 28.57 Ibrahim 8,000 Land 6,250 37,500 112,500 - - - 112,500 Acq.

43 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Tem Hameedan Bibi w/o p. 9 93+000 144/9-L LS 6 18 5 0 5 0.63 27.78 Zahoor Ahmad 65,000 Land 6,250 31,250 93,750 - - - 93,750 Acq. Tem 1 113+08 Azmat Ali s/o Fateh p. 146/9-L LS 2 24 1 10 1.5 0.19 6.25 0 4 Muhammad 10,250 Land 6,250 9,375 28,125 - - - 28,125 Acq. Tem 1 113+08 M. Anwar s/o M. p. 146/9-L LS 4 22 3 0 3 0.38 13.64 1 4 Shafi 25,000 Land 6,250 18,750 56,250 - - - 56,250 Acq. Tem 1 113+08 M. Ramzan s/o p. 146/9-L LS 6 8 0 10 0.5 0.06 6.25 2 4 M. Jhanda 4,350 Land 6,250 3,125 9,375 - - - 9,375 Acq. Muhammad Tem 1 117+51 175/9-L RS Waseem s/o M. 3 p. 84 4 10 4.50 0.56 5.36 3 5 35,000 6,250 28,125 84,375 - - - 84,375 Ameen Land Tem 1 117+51 Bashir Ahmad s/o 175/9-L RS 6 p. 40 0 10 0.50 0.06 1.25 4 5 M. Abdullah 16,530 6,250 3,125 9,375 - - - 9,375 Land Tem 1 127+42 Muahammad Yasin 161/9-L LS 6 p. 56 2 10 2.50 0.31 4.46 5 0 s/o Ghulam Dastgir 47,000 6,250 15,625 46,875 - - - 46,875 Land Tem 1 127+42 Amanat Ali etc s/o 161/9-L LS 9 p. 108 0 10 0.50 0.06 0.46 6 0 Muhammad Din 69,000 6,250 3,125 9,375 - - - 9,375 Land Tariq Mehmood s/o Tem 1 137+82 162-9L LS Ch. Muhammad 5 p. 30 2 10 2.50 0.31 8.33 7 5 19,640 6,250 15,625 46,875 - - - 46,875 Shafi Land Javaid Mumtaz s/o Tem 1 142+57 162/9-L LS Muhammad 4 p. 64 2 10 2.50 0.31 3.91 8 0 36,000 6,250 15,625 46,875 - - - 46,875 Mumtaz Akhtar Land

1L/9L Pandatwala Disty

Muhammad Yousaf Tem 1 11+974 93/9L RS s/o Ahmad (Punnu 5 p. 12 9 0 9.00 1.13 75.00 9 11,500 6,250 56,250 168,750 - - - 199,557 s/o Samanda) Land

Tem 2 Pir Muhammad s/o 11+974 93/9L RS 12 243,00 p. 296 4 8 4.40 0.55 1.49 0 Sardar Ameer Ali 6,250 27,500 82,500 - - - 82,500 0 Land

44 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Tem 2 16+457 99/9L RS Bashir/Hoot 10 p. 72 6 0 6.00 0.75 8.33 1 33,400 6,250 37,500 112,500 - - - 112,500 Land Tem 2 Abdul Rasheed s/o 16+457 99/9L RS 5 p. 4.4 4 0 4.00 0.50 90.91 2 Muhammad Munshi 18,560 6,250 25,000 75,000 - - - 75,000 Land

11-L Dad Fatiana Distributary

Tem 2 Muzaffar Hussain 15+200 9/11-L RS 6 p. 84 4 0 4.00 0.50 4.76 3 s/o Jalal Din 81,000 6,250 25,000 75,000 - - - 75,000 Land Tem 2 Ghulam Qadir s/o 15+200 9/11-L RS 7 p. 24 4 0 4.00 0.50 16.67 4 Sharafat Ali 17,000 6,250 25,000 75,000 - - - 75,000 Land Tem 2 Manzoor Qadir s/o 24+500 9/11-L RS 3 p. 24 1 0 1.00 0.13 4.17 5 Mehmood Ali 15,073 6,250 6,250 18,750 - - - 18,750 Land Tem 2 Ghulam Ali s/o 24+500 9/11-L RS 5 p. 24 3 10 3.50 0.44 14.58 6 Nazir Ahmad 11,700 6,250 21,875 65,625 - - - 65,625 Land Tem 2 Des Mohammad 33-300 8/11-L LS 8 p. 20 0 10 0.50 0.06 2.50 7 s/o Ahmad Din 22,860 6,250 3,125 9,375 - - - 9,375 Land Naseem Vincent Tem 2 33+300 8/11-L LS Masih s/o Rehmat 3 p. 8.8 3 10 3.50 0.44 39.77 8 24,236 6,250 21,875 65,625 - - - 65,625 Masih Land Tem 2 Malik Lal Khan s/o 36+590 8/11-L LS 6 p. 100 3 0 3.00 0.38 3.00 9 Rang Ali 89,400 6,250 18,750 56,250 - - - 56,250 Land Tem 3 Naseem Hassan 36+590 8/11-L LS 5 p. 36 1 0 1.00 0.13 2.78 0 s/o Khuda Bux 63,000 6,250 6,250 18,750 - - - 18,750 Land Tem 3 Ejaz Ahmad s/o 42+500 12/11-L LS 16 p. 56 2 0 2.00 0.25 3.57 1 Wali Mohammad 80,000 6,250 12,500 37,500 - - - 37,500 Land Tem 3 Allah Ditta s/o Fazal 42+500 12/11-L LS 4 p. 32 1 0 1.00 0.13 3.13 2 Ahmad 18,000 6,250 6,250 18,750 - - - 18,750 Land Tem 3 M.Khurshid s/o 47+250 13/11-L LS 7 p. 80 4 2 4.10 0.51 5.13 3 M.Din 45,000 6,250 25,625 76,875 - - - 76,875 Land Tem 3 M.Asif s/o Ghulam 52+725 13/11-L LS 4 p. 28 1 0 1.00 0.13 3.57 4 Dastgir 26,000 6,250 6,250 18,750 - - - 18,750 Land

45 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Tem 3 Manzoorn Begum 59+200 18/11-L LS 7 120,00 p. 200 5 4 5.20 0.65 2.60 5 w/o Faiz Meeran 6,250 32,500 97,500 - - - 97,500 0 Land

12-L Chichawatni Disty

Muhammad Riaz Tem 3 25+200 38/12-L RS s/o Khusi 6 400,00 p. 72 4 0 4.00 0.50 5.56 6 6,250 25,000 75,000 - - - 75,000 Muhammad 0 Land Tem 3 Muhammad Ikram 50+350 42/12-L RS 6 p. 208 12 0 12.00 1.50 5.77 7 Cheema 80,000 6,250 75,000 225,000 - - - 225,000 Land Tem 3 Muhammad Afzal 54+700 44/12-L LS 7 p. 100 1 0 1.00 0.13 1.00 8 s/o Abdullah 50,000 6,250 6,250 18,750 - - - 18,750 Land Deh Tem 3 Anayat Babu s/o Ali 98+200 Kameea LS 9 218,30 p. 100 1 10 1.50 0.19 1.50 9 Ahmad 6,250 9,375 28,125 - - - 28,125 n 0 Land Deh Tem 4 Muhammad Yousaf 98+200 Kameea LS 5 p. 56 1 10 1.50 0.19 2.68 0 s/o Raj Muhammad 35,000 6,250 9,375 28,125 - - - 28,125 n Land Deh Tem 4 Baqir Ali s/o Noor 98+200 Kameea LS 8 p. 16.8 3 0 3.00 0.38 17.86 1 Muhammad 40,000 6,250 18,750 56,250 - - - 56,250 n Land

1R/12L Minor

Tem 4 M. Maqsood Khan 30+970 110/12-L RS 7 p. 12.5 8 0 8.00 1.00 64.00 2 s/o M. Iqbal Khan 14,000 6,250 50,000 150,000 - - - 150,000 Land Tem 4 Rana Javaid s/o 38+385 111/12-L RS 8 p. 16 5 0 5.00 0.63 31.25 3 Rana Riaz 10,000 6,250 31,250 93,750 - - - 93,750 Land

Tem 4 Faqeer Muhammad 38+385 111/12-L RS 8 p. 36 3 0 3.00 0.38 8.33 4 s/o Delawar Gujjar 20,000 6,250 18,750 56,250 - - - 56,250 Land

Non Tem 4 Muhammad Afzal - 72+000 101/12-L RS 6 p. 4.6 2 0 2.00 0.25 43.48 121,990 5 s/o Manzoor 7,200 6,250 12,500 37,500 Fruit 71 84,490 Land Tree s

46 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Tem 4 Jan Muhammad s/o 72+000 101/12-L RS 5 p. 18.5 5 7 5.35 0.67 28.92 6 Dilbar 7,800 6,250 33,438 100,313 - - - 100,313 Land Tem 4 Bashir Ahmad s/o 72+000 101/12-L RS 11 p. 3.4 2 0 2.00 0.25 58.82 7 Bootay Khan 8,400 6,250 12,500 37,500 - - - 37,500 Land *24,000 Tem 4 Bashrian Bibi d/o 100.0 + 72+000 101/12-L RS 11 p. 2 2 0 2.00 0.25 8 Bootay Khan 8,400 0 6,250 12,500 37,500 - - - 37,500 Land =61,500 Tem 4 Ghulam Mustafa 76+411 101/12-L RS 17 p. 208 6 9 6.45 0.81 3.10 9 s/o M. Nawaz 93,500 6,250 40,313 120,938 - - - 120,938 Land Muhammad Akram Tem 5 76+411 101/12-L RS s/o Muhammad 8 129,00 p. 203 9 7 9.35 1.17 4.61 0 6,250 58,438 175,313 - - - 175,313 Sher 0 Land

14-L Kassowal Disty

Tem 5 Din Muhammd s/o 9+500 3/14-L RS 10 p. 72 16 0 16.00 2.00 22.22 100,00 1 Sher Muhammad 50,000 6,250 300,000 - - - 300,000 Land 0 Tem 5 Ali Muhammad s/o 27+650 9/14-L RS 10 p. 56 16 8 16.40 2.05 29.29 102,50 2 Kamoon 30,000 6,250 307,500 - - - 307,500 Land 0 Tem 5 Muhammad Irshad 27+950 9/14-L RS 9 p. 15 3 2 3.10 0.39 20.67 3 s/o Rehmat Ali 15,000 6,250 19,375 58,125 - - - 58,125 Land Tem 5 Noor Muhammad 39+900 14/14-L RS 6 p. 136 16 0 16.00 2.00 11.76 100,00 4 Fazil Khokhar 95,000 6,250 300,000 - - - 300,000 Land 0 Wahab

Disty Tem 5 Bashir Ahmad s/o 4+865 100 WM RS 4 p. 78 2 0 2.00 0.25 2.56 5 Allah Ditta Jutt 26,000 6,250 12,500 37,500 - - - 37,500 Land Muhammad Afzal Tem 5 4+865 100WM RS etc s/o Ghulam 6 p. 78 1 0 1.00 0.13 1.28 6 50,000 6,250 6,250 18,750 - - - 18,750 Sarwar Jutt Land

Total 29.0625 4,383,375 2774809 1453125 376 222 210 232.5 0 4359375 - 71 84490

47 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

48 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 4: INVENTORY OF COMMUNITYSTRUCTURES/FIXTURES OF ICB-05 Location Area Sr Detail Struct Total Struct Are Un Est. . of ure Affecte Villag Si ure a it Cost N RD Struct Affecte W L d Cost e de Type (Sq Co (Rs.) o. ure d (Rs.) . ft) st 9-L Ganjibar Oppo site Rehm Prayer Prayer 1 1 1 5+300 L Pacca 169 at Place Place 3 3 175 29,575 29,575 Colon y Three 1 Pacca 5 60 Toilets 2 325 19,500 Jamia 14+50 2 R Masjid 0 Ablution Pacca 6 8 48 54,900 Faradia 325 15,600 3 Floor Pacca 6 180 0 110 19,800 Total 457 84,475 84,475

49 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 5: INVENTORY OF PUBLIC INFRASTRUCTURE OF ICB-05 Location Number of Item Sr. Detail of Ownersh Unit Type Righ Total Cost (Rs.) No. RD Structure ip Rate Left t 1L/4R Jhilwala 1 5+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 2 5+600 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 3 6+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 4 12+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 1R/5L Adda 1 5 to 6 Qadir Electric Pole Cement WAPDA 0 6 6 66,458 398,748 Abad 2 18+000 Electric Pole Cement WAPDA 1 0 1 66,458 66,458 3 19+000 Telephone pole Steel PTCL 1 0 1 10,000 10,000 4 20 Electric Pole Steel WAPDA 1 1 2 66,458 132,916 Abadi 3 32+500 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 Nargana 4 37+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 5-L Gamber 1 23+000 Electric Pole Cement WAPDA 1 1 2 66,458 132,916 2 24+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 3 36+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 4 48+000 Electric Pole Cement WAPDA 0 1 1 66,458 66,458 2R/5L 57/5L 1 4+000 Electric Pole Steel WAPDA 0 1 1 66,458 66,458 Abadi Rao 2 19+000 Telephone pole Steel PTCL 0 1 1 10,000 10,000 6-R Sahiwal Distributary 1 5+000 Electric Pole Cement WAPDA 1 1 2 66,458 132,916 Electric 2 6+000 Cement WAPDA 6 1 7 66,458 475,206 Pole+transformer 3 7+000 Electric pole Cement WAPDA 6 0 6 66,458 398,748 4 8+000 Electric Pole Cement WAPDA 3 0 3 66,458 199,374 5 9+000 Electric Pole Cement WAPDA 6 0 6 66,458 398,748 6 10+000 Electric Pole Cement WAPDA 7 0 7 66,458 465,206 7 11+000 Electric Pole Cement WAPDA 9 0 9 66,458 598,122 Electric Cement WAPDA 4 1 5 66,458 342,290 8 12+000 Pole/transformer Telephone pole Steel PTCL 0 1 1 10,000 10,000 9 13+000 Electric Pole Cement WAPDA 2 0 2 66,458 132,916 1R/6R Minor 1 1+500 82/6R Electric Pole Cement WAPDA 0 1 1 66,458 66,458 2 2+000 82/6R Electric Pole Cement WAPDA 1 2 3 66,458 199,374 17+00 Electric 3 Cement WAPDA 2 2 66,458 132,916 0 Pole+transformer 12-L 887,25 1 84 51/12-L Watercourse Cement OFWM 0 0 887,250 0 Total 51 26 77 58,55,142 Note: Transformers are not included in the total numbers, but cost of shifting is included.

50 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 6: TRANSPORT ALLOWANCE FOR AFFECTED HOUSEHOLD OF ICB-05

Transport Sr. Canal Monthly RD Location Affected Person Occupation Allowance No. Side Income (Rs.) (Rs.) Adda Khalil Ahmad s/o 1 32+000 L Shopkeeper 14400 2000 64/4R Bashir Ahmad Mamora s/o 2 43+000 68/4R R Agriculture 15800 2000 Wahab Shahbaz Ahmad 3 4+904 58/5L R Agriculture 9000 2000 s/o Shamas Din Tulla M.Arif s/o Allah 4 30 R Agriculture 13000 2000 Bulla Ditta Dara Ameeran Bibi w/o 5 2+600 R Agriculture 5000 2000 Zarein Sultan (Late) Asmat Bibi w/o 6 1+300 139/9L R Hafiz M.Din Labor 3500 2000 (Late) M.Haroon s/o 7 9+200 161/9L R Hotel 6500 2000 M.Rafique Adda Ghulam Shabbir 8 9+200 R Hotel 6000 2000 162/9L s/o Bashir Ahmad Malik Tariq Aziz Govt. 9 10+000 L 30000 2000 s/o Abdul Aziz Servant Total 103,200 18,000

51 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 7: STAKE HOLDERS CONSULTATION MEETINGS WITH MALE PARTICIPANTS

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Alam Sher The lease M. Amin rent will be Hamid Ali What will be the mode of paid prior to M. Munawar payment of the lease? start of civil Muhammad Shafique works Muhammad Yousaf Sharif Masih As per Ashiq Hussain contract We have already agreement Sajid Ali s/o Ashiq Hussain experienced, that the ,the Abdur Rasheed s/o M. contractor never restore Contractor is Lateef land to its original bound to Muhammad Asghar s/o condition. It will very restore the Habib Ahmad difficult for us to restore it. occupied Munir Ahmad s/o M. Sadiq land M. Sadique s/o Mushtaq The lease Ahmad rent will be Rana Abdul Sattar s/o What will be the mode of paid prior to Mehdi Khan payment? start of civil Abdul Hameed s/o works Muhamma Yousaf Shahid Mehmood s/o M. Amin 5-L Nasir Khan s/o Muhammad 1 Gamber Khan

Naimat Ali s/o Khushi Muhammad Payments Sadiq Ali s/o Ghulam In the past, we have seen will be made Muhammad that the government / for any Muhammad Lateef s/o contractor use farmer’s soil services as Jamal Din without permission and per contract Muhammad Jameel s/o donot pay for it. agreement M.Sadique Muhammad Akram s/o M. Shafi Jangbaz s/o Hamayat Khan Basharat Ali s/o Mubarak Ali Muhammad Iqbal s/o M. As per Shafi approved Imtaiz Ali rate of the Jaffar Ali Forest Muhammad Asif What will be about privat department, Haider Ali Sipra trees? compensatio n per tree will be paid Allah Ditta along with salvage of

52 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . the tree. ASif Khan The EMP Muhammad Arshad s/o bounds the Abdul Rasheed contractor to The upper layer of the soil store the is very fertile. How it will be fertile layer ensured to save it? Liaquat Ali to restore the fertility of the land. Ijaz Hussain Alam Sher s/o Nizam Din Shahbaz Ahmad s/o Shams Priority is to We have small businesses. Din minimize the Government should try to Liquat Ali s/o Muhammad losses of the avoid removing. Hussain APs. Ameer Hamza Abul Rehman Sajjad Hussain s/o Mukhtar The ADB Ahmad policy aims M.Ashiq s/o M. Sharif to minimize M. Hassan s/o Bohna resettlement Khalid s/o Manzoor Ahmad issues. The Muhammad Asif s/o M. structures Aslam would be M.Ali s/o Khan M shifted on M. Arshad s/o Faqeer temporary Muhammad Due to dislocation, our basis for the Taj Muhammad s/o Sher business will be disturbed period of Muhammad causing adverse effects on construction Amanat Ali s/o Chirag Ali our livelihoods. activities on 2 1R/5-L Muhammad Shaban s/o the particular M.Shafi section.It will Pir Muhammd s/o Ghulam help to Muhammad minimize the Muhammad Khalid losses. Muhammad Shahbaz Muhammad Nadeem s/o M.Ali Abid Ali Dogar Akbar Ali Social Muhammad Ashraf s/o structures Wazeer Ahmad like Muhammad Kabil s/o M. footbridges, Azmat Is there any facility be cattle Ghats Ghulam Hussain provided to the community and Muhmmad Rafique s/o M. under this project? clothwashing Ilyas points for Muhammad Yasin s/o Jalal women are Din being Shakeel s/o Saif ur provided.

53 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Rehmad Muhammad Javeed s/o Ahmad Bux Bashir s/o Din Muhammad Muhammad Yousaf s/o M. Sadique Muhmmad Luqman s/o Sultan Ali Ishaq s/o Bashir Sultan s/o Jumma Khan Muhammad Rafique s/o Ahmad Din M. Hussain s/o Ghulam Muhammad Muhammad Yousaf s/o M. Sadique Zakir Hussain s/o Jan Khan Muhammad Iqbal s/o M. Hussain Noor Muhammad s/o Ramzan Abdul Ramzan s/o Muhammad Amin Malik Liaquat Ali s/o Bashir Ahmad Malik Nukre Khan s/o The Qasim Ali Compensation should be compensatio Muhammad Rustam s/o given timely to the n will be paid Waryam Affectees. prior to start Abdul Razaq s/o Bashir of works. Ahmed Muhammad Shahbaz s/o Bashir Ahmad Haq Nawaz s/o Nukra Khan 3 2-R/5L Muhammad Aslam s/o M. Amin Zahoor Ahmad s/o Muhammad Khan Muhammad Ashraf s/o M. Alam Sher The Project Zahir Hussain s/o The tail enders do not get objective is Muhammad Jalal water according to their to improve Mushtaq Ahmad s/o Noor allocated share. The water Muhammad design engineers should conveyance Allah Ditta s/o Muhammad make it possible to provide efficiency Ramzan water to tail enders. benefiting to Manzoor Ahmad s/o Ahmad tailenders. Ali Noor Muhammad s/o M.Ramzan

54 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . M.Amin s/o Noor Muhammad Muhammad Abbas s/o M. Akram Muhammad Latief s/o Noor Hasan Muhammad Ashraf s/o Ilm Din Muhammad Yousaf s/o Abdur Rasheed Zulifquar Ali s/o Ramzan Khan

Ali Sher s/o Muhammad Rehabilitatio The banks of the channels Ramzan n of these are very weak. Is their any Aashiq Hussain s/o channels will provision for the Muhammad Yousaf strengthen improvement of these Allah Ditta s/o Abdur Razaq the banks. banks? Sardar s/o Bashar

M. Raqfique s/o Abdul Rehman Atta Muhammad s/o Noor Din Shahamad Ali s/o Sohail 4 2-L/2-R/5L Jahangir s/o Hamid Iqbal s/o Sultan M. Gulzar s/o Shah Muhammad Kashif Masih Noor Muhammad s/o Ghulam Hussain Muhammad Asif s/o M. The Hanif contractor 6-R 6-R distributary is passing M. Sajid s/o Ghulam has 5 Sahiwal through the city area. How Muhammad submitted Disty it Sardar Ali s/o Ali the traffic Will be ensured to make Muhammad plan in EMP smooth traffic flow as in Muhammad Hanif s/o Wazir for smooth routine? Ali traffic Hameed Ahmad s/o Riaz mobility Ahmad Ch. Ishtiaq Hussain Zaman Amin s/o Haji Sultan Ali Maher Ali Sher Zafar Ali 2-L/9L 6 Azhar Iqbal Minor The labour camps should Muhammad Faisal Nadeen be far away from the Dilbar Ahmad As per settled area. Muhammad Yasin contract Balouch Khan agreement,

55 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Azhar Khan the labour Noor Ahmad camp will be Naseer Ahmad estabilished Manzoor Hussain ateast 500 Noor Mehram meters away Ali Bahadar from the Noor Muhammad settled area. Muhammad Saeed Shaukat Ali Muhammad Nawaz Muhammad Asif Muhammad Abbas Rana Mohsin According to Khadim Hussain ADB policy, Abdul Ghafoor the local M. Shafiq s/o Gulzar The local people should people will Ahmad prefer for labour job. be given Abdul Razaq s/o Ziadat han chance on Maher Muhammad s/o G. priority basis Abbas especially for Muammad Nawaz Kharl un skilled Maher Manzoor Ahmad jobs Malik Tanveer Afzal s/o Nizam Ali Mudsar Saeed Khan A joint Muhammad Akhtar s/o walkthrough Sawab Gull survey with Abdul Majeed s/o Barkat Ali FOs, PIDA Sarwar Masih s/o Dolti and design Masih Consultants Suhail Asif s/o M. Mehar Government should has been Din provide cattleghats and conducted VRBs under the project. and social structures are Muhammad Nawaz s/o M. incorporated Sardar in the design 9-L 7 on need Gunjibar basis. Sarfraz /Mehar Din M. Afzal s/o Khushi Muhammad Zulifqar Ali s/o Sardar Under the Muhammad Is the government has any project, ten Anwar s/o Azmat Ali policy to implant trees trees against Muhammad Akram s/o M. along the channel? one uprooted Akram tree will be M. Anwar s/o Muhammad planted. Shafi Ramzan s/o Jhanda

56 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Muhammad Bashir s/o Abdullah Muhammad Yasin s/o Ghulam Dastgir Suhail Waris s/o Muhammad Iqbal Tariq Mehmood s/o M. Shafi Arain Javeed Mumtaz s/o M. Mumtaz Akbar Noul Naseer Ahmad s/o M.

Habib Khan Ahmad Yar s/o Nazar Ahmad Kahlid Saleem s/o Rasheed Ahmad Kazim Ali s/o Wali M

57 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Muhammad Asif there any other facility be FOs / Muhammad Asif s/o Faiz given to the community? Community Meeran demanded Amjad Ali s/o Muhammad facility like Akram cattle ghats, M. Mohsin s/o Muzaffar footbridges Hussain and washing Anwaar Ahmad places for Ghulam Hussain women are Mukahtar Ahmad s/o M. provided in Sardar the design. Atta Muhi ud Din Mumtaz Hussain s/o Ahmad Khan Shahamand Ali Yes, the The banks condition of the banks of the Rao Muhammad Ayub Khan distributary and minors are canal and in poor condition. Is there distributary Muhammad Saeed Khan any provision under this will be Maher Muhammad Iqbal project to improve their improved Khalid condition? under this Muhammad Hussain project. Bashir Ahmad Zafar Iqbal Khan 4-R Maher Tufail Muhammad A 12 Jhilwala Abid Farooq comprehansi Muhammad Ashraf s/o ve M.Shafi walkthrough Riaz Ahmad survey with Muhammad Rafique With the passage of time, PID, PIDA, Rustam Ali the areas have become Consultant Muhammad Zaman Kham populated. So the and FOs has Qasim Ali government should provide been Allah Yar s/o Manzoor Ali foorbridges and bridges on completed. Manik Khan s/o Waryam “where needed” basis. So, the Ilm Din s/o Noor social Muhammad structures are provided Rana Liaquat under this project Rana Akhtar Hussain Muhammad Saleem As per 11-L Dad Mujhiana contract The government should Rana Pernaiz Hussain agreement, refill the diversion land the Rana Shabir Hussain 13 after the completion of the contractor is Fatiana Rana Maqsood Hussain project. bound to Rana Abdul Sattar restore the Rana Shafi Muhammad affected land Rana Niamat Ali after Shah Muhammad completion (Numberdar) the work. Shakeel Ahmad

58 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Tanveer Ahmad Muhammad Yousaf Thinking Muzaffar Hussain s/o Jalal orientation is Din there Ghulam Qadir s/o Sharafat through Ali Is there any policy to give disclosure of Manzoor Qadir s/o technical trainings to the RP.But Mehmood Ali affectees under this there is no Ghulam Ali s/o Nazir project? provision to Ahmad impart any Des Muhammad Dogar s/o training for Ahmad Din the project Naseem Vincent s/o affectees Rehmat Masih Malik Lal Khan Rang Ali Naseem ul Hassan s/o The FO Khuda Bux forum can be Ijaz Ahmad s/o Wali used for ths Muhammad purpose. FO Allah Ditta s/o Fazal Ahmad should give Khursheed Ahmad s/o Water scarcity is basic an Muhammad Din problem of the area. application to Muhammad Asad s/o Government should the SE for Ghulam Dastgir increase wate of the this purpose. Noor Muhi Udin s/o Faiz distributary. He is Meeran competent Sheraz Akhtar authority to Imran Nasir increase Atif Mehmood water Raja Wajid Nawaz allowance. Imtaiz Hussain Maqsood Ahmad Muhammad Mustafa This activity Khan Faiz Rehman is already Nasir Iqbal being under Muhammad Ibrar this project. Hafiz Bashir Ahmad The project Government should make Javeed Iqbal component model farm to teach Muhammad Nawaz five(OFWM) modern agriculture to Mhammad Amin is setting farming community of the Muhammad Yasin demonstratio area under this project. Safdar Mehmood n field for to This method can mobilize mobilize the Nazar Muhammad farmers to adopt and use people of the Younis Masih new agriculture techniques. Malik Javeed area to use Ali Ahmad new water Rana Muhammad Fiaz safety Joya techniques Muhammad Yasin Dogar such as drip Muhammad Ashraf irrigation etc.

59 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Muhammad Abdullah Malik Khalid Hayat Malik Ghaznafar Malik Rab Nawaz Haq Nawaz s/o Bakhtawar Allah Dtta s/o Muhammad Yousaf Sarfraz s/o Haq Nawaz M. Luqman s/o Ghulam Sarwar Muhammad Ilyas s/o Ghulam Sarwar On Farm Riaz Ahmad Water scarcity is the major Water M. Riaz s/o Khushi problem of the area. Management Muhammad Actullay the water is involved in Faqeer Muhammad management is very poor. this Hammad u Nasr s/o M. People are not aware how project.The Ikram Cheema and how much water concerned Razi ul Kareem Cheema should be use for their officials will Altaf Hussain crops. Government should 12-L play their Muhammad Ikram start awareness programe 14 Chichawat role in this Muhammad Afzal s/o for this purpose. ni regard. Abdullah Anayat Babu s/o Ali Ahmad M. Yousaf s/o Raj Muhammad Baqir Ali s/o Noor Muhammad Azhar Mehmood s/o Nazeer Ahmad Ch Muhammad Haneef No, this is Muhammad Sarfraz not in our Zafar Iqbal mendate to Can mogha size be Jalil Gill increase or increased under this Muhammad Iqbal decrese project? Muhammad Idress Mogha size Muhammad Imran Faqeer under this Anwar Ahmad project M. Maqsood Khan s/o M. How it will be ensured, that Project aims Iqbal Khan the affected people retain to Rana Javeed Ahmad s/o their economic status to its compensate Riaz Ahmad real position ? the APs as Faqeer Muhammad s/o per ADB 1R/12-L Dilawar Ali policy.The 15 Muhammad Afzal s/o policy Manzoor Ahmad provides M. Ramzan s/o M. Shafi adequate Dilbar assistance to Bashir Ahmad s/o Bootay the APs not Khan to be worse

60 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Ghulam Mustafa s/o off. M.Nawaz M. Akram s/o Muhammad Sher Ch. Tahir Hussain Mazhar Farooq Malijk Manzoor Ali Ayyub Shahzad Muhammad Riaz Zafar Iqbal Allah Ditta Cheema Ch. Muhammad Aslam Ch. Muhammad Akram Wazeer Ahmad The civil Tahir Gujjar works on Abdul Razaq s/o Khan minor will be carried out Muhammad This is small minor; it can during Muhammad Ramzan s/o M. be rehabiliated during closure or Sadique closure. We are running through 16 3L/12-L Safdar Ali Nazeer Ahmad our businesses for the last parallel M. Idrees s/o Faqeer many years, government diversion Muhammad should avoid to dislocate without any Ghulam Haider s/o Asmat us. ullah water Tariq Bhatti interruption and business Ahmad Ali disturbance Muhammad Arif s/o Allah Ditta Bashir Ahmad s/o Allah Ditta Muhammad Amjad s/o We will use Ghulam Sarwar As you know that Wahab that Maher Muhammad Amin distributary is passing engineering Maher Sher Muhammad through thickly populated techniques Bahab 17 Usman Shah Khaga area, how it will be which will Disty Muhammad Mukhtar Kathia rehabilitated without ensure to Muhammad Ibrahim Watto disturbing the local minize level Muhammad Yousaf community. of Abdul Lateef disturbance Naseer Malah Dr. Sher Muhammad Ghulam Muhammad Toraiz Khan Muhammad Ramzan The Dr. Zahoor provision for 2L/Wahab is a small minor, Shameer Khan the lining of 18 2L/Bahab it should be completely Maqsood Ahmad 2L/Wahab lined under this project. Muhammad Bashir s/o has already M.Khan been made

61 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Lal Khan s/o Torej Khan under this Naseer s/o Muhammad project. Riaz Hussain Amjad Hussain Khan Muhammad In some places, the Bashir Ahmad moghas are not on their As per Hasan Sher original place, for some project Ali Sher places these moghas are provision, all Tauqeer Ahmad at high level and for some the moghas Muhammad Iqbal places they are at low level will reset to Muhammad Yar from thir original place. Is their original Muhammad Aslam there any provision to set level. Muhammad shafique them to their original level? 7-R 19 Muhammad Din Bakerke Muhammad Tariq Ghulam Qadir The banks Abdul Majeed The banks of the of the Nazeer Ahmad distributary are eroded, distributary Zafar Iqbal when there is full supply of system will Muhammad Akhtar irrigation water , the water be Ghulam Qadir causes overtopping and strengthened Abid Hussain makes loss to surrounding under this Muhammad Yar crops. These banks project to Khan Muhammad should be strengthened control under this project. breching of Habib Khan distributary. Muhammad Yar s/o Ramzan It is a small sub minor, is it Lining is Saeed Ahmad s/o Rehmat 20 1R/2R/7R possible to line under the proposed in Ullah project? the design Riaz s/o Rehmat Ullah Rehmat Ullah s/o Ramzan Mukatar Hussain Yes, 5-R Abdul Razaq Yousafwala 5-R 5-R is a small distributary, Muhammad Ramzan Gill will be 21 Yousafwal is it possible to line under Mudassar Iqbal completely a the project? Muhammad Ashiq lined under Muhammad Sharif this project. Muhammad Ghous Dial Basharat Ali 10-L is a small distributary, It will be 10-L 22 Niaz Ahmad is it possible to line under lined under Harrapa Malik Tariq Aziz s/o Abdul the project? the project. Aziz Kamran Ashraf Government should make This activity Muhammad Ibrahim model farm to teach is already Maqbool Ahmad modern agriculture to being under 23 7-ER Muhammad Ijaz farming community of the this project. Ghulam Sabir area under this project. The project Abid Hussain This method can mobilize component Muhammad Asif farmers to adopt and use five(OFWM)

62 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. Views/Concerns/Suggest No Location Respondents Response ions . Noor Muhammad new agriculture techniques is setting Gulzar Ahmad demonstratio Muhammad Akram n field for to Sardar Muhammad mobilize the Abdul Qadir people of the Nazir Ahmad area to use Bashir Ahmad new water Muhammad Ali safety Muhammad Boota techniques such as drip Noor Muhammad irrigation etc. Ghulam Qadir s/o Sultan Muhammad Javeed Under hydel power Zulifqar s/o Shahamand project,surve Din Muhammad s/o Sher Government should y is in 14-L Muhammad implant power project on process to 24 Kassowal Ali Muhammad s/o Kamoon this distributary to provide qualify the Berhoomt electricity to surrounding site. Anyway villages. Muhammad Irshad s/o this is not Rehmat Ali related to Noor Muhammad s/o this project. Muhammad Fazil Ghulam Rasool The banks of Sayed Zile Hussain Shah The banks of the the Muhammad Iqbal Lak distributary are eroded, distributary when there is full supply of system will Ghulam Mustafa irrigation water , the water be 25 9-AL Aftab uz Zaman causes overtopping and strengthened Dilawar Sher makes loss to surrounding under this crops. These banks project to should be strengthened control Saleem Khalid under this project. breching of distributary.

63 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 8: CONSULTATION MEETINGS WITH FEMALE PARTICIPANTS Sr. No of Name of Locatio Views/Concerns/Suggesti No Participan Responden Response n ons . ts ts Muneeran The majority of women Sociologist responded Bibi showed their keen interest that all women land Razia Bibi to actively participate in owners can participate Sakina Bibi Farmer Organization (FO) in election to be a Naseem Bibi activities. member of Farmer Sageeran Organization. Bibi 5-AR Ghulam Bibi 1 12 Disty Hafeezan Bibi Fahma Bibi Nargis Bibi Respondents showed their Provision has already Naziran Bibi interest for improvement been made in design for Sajda Bibi and widening of village road the widening and Asia Bibi bridge in their respective improvement of said village. bridge. Gulan Bibi The majority of the women The question is wd/o Talib demanded that a vocational irrelevant to the project. Hussain training institute be However the FO could Musarat Bibi established. utilize its role to d/o Bahawal establish such Sher vocational training Begum Bibi centers at the village w/o Falak level to promote income Sher generation activities Naiz Bibi During consultation the among women of the w/o Jaffar women also demanded for area. 5-L Bashiran the provision of cattle ghat 2 14 Disty Bibi w/o and VRB along the channel Sociologist explained Sadiq near settlements. that rehabilitation for the Perveen Bibi existing VRB has Anwar Bibi already been included in Ameeran the engineering design Bibi but the section of tail Amna Bibi end is quite narrow, so Zubeda Bibi the provision of cattle Salma Bibi ghat is not possible. Ghazala Bibi Sharifan Bibi Zarina Bibi Fakhar Bibi Women inquired whether The problem will be w/o the silt and breaching resolved after the M.Aslam problem of the channel completion of lining for Noor Fatima would be resolved after the the 2-L/ wahab minor w/o Liaqat project implementation. under this project. Ali Doda Naseem Bibi Respondents queried the Construction staff will be Sahoo w/o Noor issue of polluted instructed to use the 3 2-L / 9 Hassan environment due to dust water sprinklers during Wahab Zara Bibi and excessive machinery the construction stage Minor w/o Noor noises made during and any radio / tape Hasan construction activities on recorders will not be Sughran site. allowed to play loudly as Bibi w/o bound by the EMP. Ghulam Abbas

64 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No of Name of Locatio Views/Concerns/Suggesti No Participan Responden Response n ons . ts ts Ghulam Sakina w/o Bahawal Sher Rani Bibi w/o Shaban Bhag Bari Bibi d/o Mehmood Zahida Bibi The movements of women, As per the contract w/o Charag children and elderly people agreement, the Din should not be restricted due contractor will be bound Zobia Bibi to project employees at the to keep his labor force w/o Allah campsite. away from local Din settlements and they will Safia Bibi not be allowed to enter w/o Jameel the settlements without Din Compensation should be local representative. Abida given in a timely manner to Perveen w/o the affectees. They were assured that M. Anwar compensation will be Sajda given to the affectees Andleeb d/o prior to the start of M. Aslam Local people of the project project activities as per Sameea area should be given equal ADB policy. Andleeb d/o labor opportunities during M.Aslam the construction stage. As per the EMP contract Nasreen agreement, preference Akhtar d/o will be given to local M. Anwar people within the area 12-L / Nazia d/o for unskilled jobs and 4 Disty 15 M.Asghar child labor will not be Shamshad permitted. w/o Sajid Safia Bibi w/o Wazir Ali Farkhanda Naz d/o Abdul Razaq Sajda Bibi wd/o Safdar Safai Bibi w/o Ghulam Mustafa Samina Khalil w/o Khalil Ahmed Khursheed Bibi w/o Faqeer Ahmed 1-R / Naziran Bibi The chances of children The contractor is 5 12-L 5 d/o M.Anwar being involved in on site expected to announce Minor Azra Bano accidents, due to machinery their activity schedule

65 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No of Name of Locatio Views/Concerns/Suggesti No Participan Responden Response n ons . ts ts w/o M. / equipments failure should and mobilization of Mansha be prevented by taking machinery/equipments Imtiaz Bibi appropriate measures and construction staff to w/o M. during civil works. control such incidences. Akram Amna Bibi wd/o M. Akram Niaz Begum wd/o M. Bashir Samina w/o There should be a well A Social Frame work Razaq defined and clear Agreement (SFA) will be Anwar Bibi mechanism to monitor the signed between the w/o Ahmed ongoing project activities Irrigation department Irshad Bibi through the local and villager’s committee w/o Ameen community. of each distributary Rehana Bibi command area to w/o Malik monitor the project Tanvir activities. Naseem The women’s farming Akhtar w/o community in the tail end of They were informed that Mehboob the reach demanded the the Zahida Bibi remodeling of existing reconstruction/rehabilitat w/o Ashiq outlets, in order to receive ion Hussain the irrigation water in its full of existing outlets will be Sajda Bibi capacity. carried out using the w/o Talib same parameters as Hussain approved by the Sarwar Bibi irrigation department. w/o Sultan For the remodeling of Ahmed The women showed their outlets, farmers should 6 Shehnaz interest for the consult the canal SE Bibi w/o environmental improvement Sahiwal. 2-L / 9-L 17 Abdul Sttar measures, through the re- Noor Bibi plantation of trees along The tree plantation plan w/o Nasir channel banks. will be prepared along Nasreen the banks in consultation Akhtar w/o with the Forest Zaheer department. According Zubeda Bibi to the EMP, re- w/o plantation will be M.Shabir ensured at a minimum Riaz Bibi ratio of five trees for w/o Ahmed each felled tree. Saeed Irshad Bibi w/o Falak Sher Sahi Bibi w/o Sarwar Ghulam Fatima w/o Ziadat Khan Bashiran Bibi w/o Ameer Din

66 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No of Name of Locatio Views/Concerns/Suggesti No Participan Responden Response n ons . ts ts Niaz Bibi Participants reported that Sociologist responded wd/o water scarcity has become that under this project, Jahangir a big concern for the all channels will be Murad Bibi farmers. Their farm income rehabilitated in order to wd/o Qasim has been affected and in improve water Perveen return they also have to conveyance efficiency. Akhtar wd/o bear the cost of high fuel M.Ameen prices. Nasreen The respondents were Akhtar wd/o Apart from the rehabilitation clearly informed by the M.Aslam process, will their water sociologist that there will Ilam Bibi courses be lined under this be no such activity in the wd/o project? project’s scope of works. M.Shafique The main objective is Kaniz Bibi the improvement of the w/o Allah LBDC system. Ditta Bashiran Labor camps should be far As per contract Bibi w/o away from any residential agreement, the M.Akram areas due to security contractor will be Muneeran issues. restricted to establish Bibi d/o Dost labor camps Muhammad approximately 500 Shagufta meters away from any w/o Zaffar They asked for information settlement. Hussain regarding project Sakina Bibi activities/civil works to be They were ensured that w/o Allah displayed within a suitable people will be informed 7 7-AR 21 Ditta timeframe for their in advance, through sign

Shehnaz convenience. board displays at Bibi w/o construction sites and Itmad public routes. Hussain Nisha Bibi w/o M.Akram Faiz Batool w/o Ghulam Badsha Najma d/o Akram Tasneem Akhtar w/o Izhar Hussain Nasreen Bibi d/o M.Anayat Naziran Bibi w/o M.Anwar Saima d/o M.Akram Ameena Bibi wd/o Faiz Meer Nazia Bibi

67 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Sr. No of Name of Locatio Views/Concerns/Suggesti No Participan Responden Response n ons . ts ts w/o M.Jamil Irshad Bibi wd/o M.Sharif

Azra Bibi Excavation material must be Excavation material will w/o disposed off away from the be dumped within the M.Ashraf residential area. RoW as per Azra Bibi environmental policy. w/o M.Aslam Muniran Bibi w/o Gulab They inquired whether IPs & Yes, it is included in the Rana NIPs would be improved. project mandate to Karam Bibi improve the IPs & NIPs. 8 w/o Ghulam 11-L 8 Nabi

Sobia Muneer d/o M.Muneer Bashiran Bibi w/o Sharif Hanifan Bibi w/o M.Sadiq Shazia w/o Ramzan

68 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 9: Schduled Contruction Rates of Building Department

69 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 10: Community Structures/Fixtures

70 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 11: Schduled Contruction Rates of Building Department

71 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 12: Detail of Proposed Diversions with Ownership Status of Land & Earth Work ROW Diversion Total Cut Fill Sr. Old RD New RD Ownership Length of Distributry Quantity Quantity Remaks No. (Existing) (Proposed) Left Right Yes/No Side Status Diversion 3 3 (ft ) (ft ) (ft) BORROW

1 4R Jhilwala 1+920 2+050 55 40 Yes Right Private 460 MATERIAL 247.18 109,618.20 Disty REQUIRED BORROW

2 4R Jhilwala 8+000 8+200 55 40 Yes Left Private 440 MATERIAL 1,396.00 67,650.99 Disty REQUIRED BORROW

3 5L Gamber 1+311 1+420 200 55 Yes Right Government 610 MATERIAL 30.00 19,475.70 Disty REQUIRED BORROW

4 33+636 34+136 65 50 Yes Right Private 710 MATERIAL 688.06 143,826.33 9L Disty REQUIRED BORROW

5 81+100 81+400 70 55 Yes Left Private 650 89064.94 MATERIAL 7,936.71 9L Disty REQUIRED BORROW

6 92+500 93+000 70 55 Yes Left Private 630 MATERIAL 8,003.08 79,291.98 9L Disty REQUIRED BORROW

7 112+784 113+084 65 50 Yes Left Private 560 MATERIAL 1,134.97 117,663.51 9L Disty REQUIRED BORROW

8 117+215 117+515 65 50 Yes Right Private 560 MATERIAL 6,460.37 99,477.07 9L Disty REQUIRED BORROW

9 127+120 127+420 65 50 Yes Left Private 550 MATERIAL 9,260.91 29,456.50 9L Disty REQUIRED BORROW

10 137+626 137+825 60 45 Yes Left Private 520 MATERIAL 16,232.43 37,315.71 9L Disty REQUIRED BORROW

11 142+370 142+570 60 45 Yes Left Private 520 MATERIAL 2,437.15 53,440.75 9L Disty REQUIRED 12 9L Disty 148+500 148+700 75 60 Yes Left Government 520 BORROW 72 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

3,564.31 37,296.72 MATERIAL REQUIRED 1L/9L BORROW

13 Pandatwala 11+774 11+974 - 45 Yes Right Private 560 MATERIAL 7,840.52 8,753.44 Disty REQUIRED 1L/9L BORROW

14 Pandatwala 16+257 16+457 - 45 Yes Right Private 550 MATERIAL 3,700.97 18,688.13 Disty REQUIRED 1L/9L BORROW

15 Pandatwala 23+329 23+529 - - Yes Right Government 480 MATERIAL 1,078.19 26,564.48 Disty REQUIRED SPOIL TO BE 16 4+665 4+865 80 60 Yes Right Private 510 Bahab Disty 19,212.88 17,070.75 STOCKED IN ROW 11L BORROW

17 Dadfatiana 14+772 15+200 65 60 Yes Right Private 560 MATERIAL 13,798.12 22,388.59 Disty REQUIRED 11L BORROW

18 Dadfatiana 24+240 24+500 60 55 Yes Right Private 540 MATERIAL 9,155.90 29,427.56 Disty REQUIRED 11L BORROW

19 Dadfatiana 33+000 33+300 60 50 Yes Left Private 540 MATERIAL 12,595.93 40,570.75 Disty REQUIRED 11L SPOIL TO BE 20 Dadfatiana 36+390 36+590 60 50 Yes Left Private 520 32,311.78 23,493.95 STOCKED IN ROW Disty 11L BORROW

21 Dadfatiana 42+333 42+500 50 35 Yes Left Private 520 MATERIAL 8,651.71 65,136.58 Disty REQUIRED 11L BORROW

22 Dadfatiana 47+050 47+250 50 35 Yes Left Private 510 MATERIAL 484.74 65,868.38 Disty REQUIRED 11L BORROW

23 Dadfatiana 52+525 52+725 50 - Yes Left Private 490 MATERIAL 5,841.20 84,275.48 Disty REQUIRED 11L BORROW

24 Dadfatiana 59+044 59+200 35 30 Yes Left Private 480 MATERIAL 9,243.96 53,440.13 Disty REQUIRED 12L SPOIL TO BE 25 Chichawatni 20+000 20+350 80 65 Yes Left Government 700 12480.67 16,506.19 STOCKED IN ROW Disty

73 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

12L BORROW

26 Chichawatni 24+700 25+200 80 65 Yes Right Private 680 MATERIAL 2,539.52 56,857.03 Disty REQUIRED 12L BORROW

27 Chichawatni 46+430 46+930 70 55 No - Closure 680 MATERIAL 1,821.81 7,456.64 Disty REQUIRED 12L BORROW

28 Chichawatni 49+850 50+350 70 55 Yes Right Private 670 MATERIAL 203.91 13,437.35 Disty REQUIRED 12L BORROW 29 Chichawatni 54+202 54+700 70 55 Yes Left Private 660 310.1583101 28015.29454 MATERIAL Disty REQUIRED 12L BORROW 30 Chichawatni 84+720 85+000 65 50 Yes Right Government 590 4166.603208 26094.09608 MATERIAL Disty REQUIRED 12L BORROW 31 Chichawatni 97+714 98+200 60 45 Yes Left Private 550 10913.94976 21508.22425 MATERIAL Disty REQUIRED 12L SPOIL TO BE 32 Chichawatni 110+200 110+500 60 45 Yes Left Government 530 5808.468583 3701.622678 STOCKED IN ROW Disty 12L BORROW 33 Chichawatni 121+000 121+300 85 70 Yes Right Government 530 4827.652375 9100.433733 MATERIAL Disty REQUIRED 12L BORROW 34 Chichawatni 122+000 122+300 85 70 Yes Right Government 490 9698.820028 20265.68326 MATERIAL Disty REQUIRED BORROW 35 30+670 30+970 55 40 Yes Right Private 520 16049.62851 24231.69958 MATERIAL 1R/12L Minor REQUIRED BORROW 36 38+085 38+385 55 40 Yes Right Private 520 6650.145986 20603.3046 MATERIAL 1R/12L Minor REQUIRED SPOIL TO BE 37 71+871 72+000 45 40 Yes Right Private 290 11826.64391 8087.951607 1R/12L Minor STOCKED IN ROW SPOIL TO BE 38 76+311 76+411 40 35 Yes Right Private 280 18675.4256 5372.909315 1R/12L Minor STOCKED IN ROW BORROW 39 4+500 5+000 65 50 Yes Left Government 600 806.2821625 6518.732143 MATERIAL 14L Disty REQUIRED

74 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

BORROW 40 9+007 9+500 70 55 Yes Right Private 590 0 85080.28051 MATERIAL 14L Disty REQUIRED BORROW 41 27+650 27+950 60 45 Yes Right Private 550 54008.12617 149894.8778 MATERIAL 14L Disty REQUIRED BORROW 42 39+600 39+900 60 45 Yes Right Private 520 16070.13246 22200.3022 MATERIAL 14L Disty REQUIRED

75 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 13: Tree Rates of Forest Department

76 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 14: Rates of WAPDA Electric Poles

77 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 15: LAR Steering Committee

78 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 16: LAR Advisory Committee

79 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 17: Internal Monitoring Committee

80 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 18: AGREEMENT FOR TEMPORARY LEASE OF PRIVATE LAND

81 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 19: Corridor of Impact (COI)

82 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

83 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

84 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

85 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

86 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

87 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 20: Right of the way (ROW)

88 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

89 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

90 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

91 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 21: Grivence Redress Committee (GRC)

Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Annexure 22: Incme Analysis of The Affected Housesholds

Monthly Income Total Occupation (Rs.) Monthly Sr. Relationship Income No. Name of AP with H.H Main Secondary Main Secondary (Rs.) 4-R Jhilwala 1 1 2 3300 3000 Mumtaz Hussain 2 14 1 12,000 s/o Ahmad Khan 3 2 3000 3 2 2700 1 1 2 5500 4500 2 Allah Yar s/o 2 2 10,000 Manzoor Ali 2 2 2 1 11 5500 2 14 Manik Khan s/o 3 23 3 15,500 Waryam 3 9 10000 4 14 4 14 1 1 19560 2 23 3 16 15000 Ilam Din s/o Noor 4 21 14 34,560 Muhammad 22 12 22 12 19 12 9-L Ganjibar M.Afzal s/o 1 1 29650 5 Khushi 2 14 37,650 Mohammad 3 10 8000 Zulifaqar Ali s/o 1 1 24 8000 4500 6 Sardar 2 12,500 Mohammad 3 1 1 11 6000 1500 Majeedan Bibi 7 9,500 w/o M.Aslam 4 11 2000 1 1 8000 2 14 M. Akram etc s/o 3 12 8 8,000 M. Ibrahim 3 24 4 12 6 23 1 1 30000 Hameedan Bibi 2 14 9 w/o Zahoor 65,000 3 9 35000 Ahmad 21 10 Azmat Ali s/o 1 1 10250 10,250

93 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Fateh 2 14 Muhammad 1 22 1 25000 M. Anwar s/o 2 14 11 25,000 M. Shafi 3 12 3 12 1 1 4350 3 1 M. Ramzan s/o 12 4 14 4,350 M. Jhanda 19 12 19 12 1 1 35000 Najma Parveen 13 35,000 w/o M. Ameen 23 1 1 16530 Bashir Ahmad s/o 14 2 14 16,530 M. Abdullah 3 12 1 9 27000 20000 Muahammad 2 14 15 Yasin s/o Ghulam 47,000 3 12 Dastgir 6 23 1 1 55000 2 14 5 23 6000 Suhail Waris s/o 16 6 23 69,000 Muhammad Iqbal 7 8 8000 7 12 7 12 1 1 19640 Tariq Mehmood 2 14 17 s/o Ch. 3 12 19,640 Muhammad Shafi 3 12 3 12 1 9 1 25000 11000 Javaid Mumtaz 18 s/o Muhammad 2 14 36,000 Mumtaz Akhtar 3 12 1L/9L Pandatwala Disty 1 10 1 8500 3000 Muhammad 6 14 19 Yousaf s/o 2 14 11,500 Ahmad Ali 7 8 14 1 1 8 135000 50000 2 14 3 9 30000 Pir Muhammad 3 9 28000 20 s/o Sardar Ameer 243,000 3 1 Ali 21 14 21 14 21 14

94 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

1 1 33400 2 14 4 12 21 Bashir s/o Hoot 4 12 33,400 4 12 4 12 4 12 1 1 2560 Abdul Rasheed 2 14 22 s/o Muhammad 3 4 6000 18,560 Munshi 3 4 10000 4 14 11-L Dad Fatiana Distributary 1 16 66000 15000 Muzaffar Hussain 2 14 23 81,000 s/o Jalal Din 3 1 21 14 1 1 2 13000 4000 Ghulam Qadir s/o 24 2 14 17,000 Sharafat Ali 6 23 1 1 15073 Manzoor Qadir 25 2 14 15,073 s/o Mehmood Ali 2 14 1 1 11 5700 6000 Ghulam Ali s/o 6 14 26 11,700 Nazir Ahmad 8 12 7 12 1 1 12860 2 14 1 1 Des Mohammad 4 14 27 22,860 s/o Ahmad Din 3 10 10000 4 14 3 1 4 14 Naseem Vincent 1 23 1 11400 2100 28 Masih s/o Rehmat 2 23 10736 24,236 Masih 3 25 1 1 8 77400 12000 2 14 Malik Lal Khan 29 4 12 89,400 s/o Rang Ali 4 12 3 12 1 10 1 55000 8000 2 14 Naseem Hassan 30 3 12 63,000 s/o Khuda Bux 3 12 4 31 Ejaz Ahmad s/o 1 1 15000 80,000

95 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Wali Mohammad 2 14 3 1 15000 3 22 25000 3 22 25000 3 1 3 1 3 1 21 14 21 14 21 14 21 14 21 14 1 1 18000 Allah Ditta s/o 2 14 32 18,000 Fazal Ahmad 3 1 3 12 1 1 45000 2 14 M.Khurshid s/o 3 1 33 45,000 M.Din 21 14 22 12 22 12 1 1 16000 M.Asif s/o 6 14 34 26,000 Ghulam Dastgir 7 11 10000 11 14 1 1 120000 6 23 Noor Muhi Ud Din 35 3 1 120,000 s/o Faiz Meeran 3 1 20 14 12-L Chichawatni Disty 1 22 300000 214 3 3 100000 312 Muhammad Riaz s/o Khusi 414 36 Muhammad 19 14 400,000 1 1 23 35000 25000 Muhammad Ikram 3 1 20000 37 Cheema 19 14 80,000 1 1 50000 214 31 312 312 Muhammad Afzal 312 38 s/o Abdullah 814 50,000 39 Anayat Babu s/o 1 1 208300 218,300

96 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Ali Ahmad 214 3 8 10000 21 14 19 12 412 1 1 35000 214 312 Muhammad Yousaf s/o Raj 412 40 Muhammad 412 35,000 1 1 16 5000 15000 214 3 22 20000 21 14 414 412 Baqir Ali s/o Noor 412 41 Muhammad 412 40,000 1R/12L Minor 1 1 7000 7 1 7000 M. Maqsood 15 14 42 Khan s/o M. Iqbal 12 12 14,000 Khan 15 14 15 14 12 12 1 1 10000 Rana Javaid s/o 43 2 14 10,000 Rana Riaz 6 23 1 1 12000 2 14 3 1 8000 Faqeer 4 14 44 Muhammad s/o 20,000 Delawar Gujjar 4 14 4 14 3 12 3 12 1 1 11 1200 6000 Muhammad Afzal 2 14 45 7,200 s/o Manzoor 5 23 6 23 1 1 7800 Jan Muhammad 46 2 14 7,800 s/o Dilbar 6 23 1 1 11 1700 3000 6 23 Bashir Ahmad s/o 8 1 700 47 8,400 Bootay Khan 2 14 3 11 3000 4 14

97 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

1 1 14 700 6 23 Bashrian Bibi d/o 7 1 11 1700 3000 48 8,400 Bootay Khan 11 14 12 11 3000 15 14 1 23 1 12000 40000 2 14 5 23 5500 6 23 7 1 25000 11 14 Ghulam Mustafa 15 14 49 93,500 s/o M. Nawaz 12 12 15 14 12 12 7 10 11000 11 14 15 12 11 12 1 1 80000 2 14 3 1 35000 Muhammad 3 9 14000 50 Akram s/o 129,000 Muhammad Sher 3 12 3 12 4 14 4 12 14-L Kassowal Disty 1 1 50000 2 14 3 1 19 14 Din Muhammd 19 14 51 s/o Sher 50,000 Muhammad 19 14 19 12 22 12 19 14 22 12 1 1 30000 2 14 3 1 Ali Muhammad 52 3 1 30,000 s/o Kamoon 3 1 21 14 21 14 1 1 15000 Muhammad 2 14 53 Irshad s/o 15,000 Rehmat Ali 4 14 4 14

98 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

3 12 3 12 3 12 3 12 1 23 25000 55000 2 14 Noor Muhammad 54 3 10 10000 95,000 Fazil Khokhar 19 14 4 10 5000 Wahab Disty 1 1 20000 Bashir Ahmad s/o 2 14 55 26,000 Allah Ditta Jutt 4 8 6000 3 Muhammad 1 1 20000 Amjad etc s/o 56 50,000 Ghulam Sarwar 1 23 Jutt 2 14 22 30000 Total 2,774,809

99 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

APPENDIX

100 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Appendix I: Assets Inventory Census Questionnaire

LOWERBARIDOABCANAL IMPROVEMENT PROJECT Environment and Social Assessment Study Assets Inventory Census Questionnaire 1. LOCATION 1.1 Name of Canal/Distry /Minor: ______1.2 RD:______2. IDENTIFICATION 2.1 Name of Affected Person: ______2.2 Father’s Name: ______2.3Respondent NIC No: ______

2.4 Permanent Address of the Respondent: Village:______Sub-Village______Town______Tehsil______District:______Contact No.______2.5 Category of Respondent: (Tick relevant)

1 ResidentLand Owner 2 AbsenteeLand 3 Tenant Owner 4 Business Owner Operator 5 Business Tenant 6 Encroacher Operator 7 Squatter 8 Other (Specify)______

2.6 Demographic Profile of Respondent: (Children up to 10 yrs (#): M___, FM ___=T______)

Name of Income from Relationshi Sex Educatio Business/ Business/ Sr. Age Health p with Male=1 n Occupation (See Occupation (Rs. No (Yrs. Conditio Respondent (See Codes) /Annum) . Female= ) n (See codes) 2 Codes) Mai Secondar Mai Secondar n y n y 1 SELF 2 3 4 5 *Other Rent from property, remittances, net sale of items during a year, net income from agriculture etc.

102 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Demographic Codes: a).Relationship: 1=Self, 2=Wife, 3=Son, 4=Daughter, 5=Father, 6=Mother, 7=Brother, 8=Sister, 9=Grand Father, 10=Grand Mother, 11=Sister in Law, 12=Nephew, 13=Father-in-Law, 14=Mother-in-Law, 15=Niece, 16Uncle, 17Aunty, 18. Son, 19. Daughter, 20 S. in Law, 21D. in Law, 22 Other______23.Other______b).Sex: 1=Male, 2=Female c).Education: 1= Primary 2= Middle 3= Metric, 4= Intermediate, 5= Graduate, 6= Post Graduate, 7=Law, 8=Engineer, 9=MBBS, 10=Technical Diploma, 11=Dars-e-Nizami, 12=Can Read Quran, 13= Can Insert Signatures, 14= Illiterate d).Occupations: 1=Agriculturist, 2=Shopkeeper, 3= Hotel, 4= Mechanic,5=Barber,6=Butcher,7=Cobbler,8= Business,9= Govt. Servant, 10=Private Servant, 11=Labor, 12=Student, 13=House- Maid,14= House Wife,15=Advocate, 16=Livestock/Dairy, 17=Fishing, 18=Driver, 19=Health Related, 20=Teaching,21=Entertainer, 22=Gone Abroad, 23=Retired/Old,24=Other______25=Other______e). Health: 1= Good, 2= Average, 3= Poor

3. DETAIL OF AFFECTED PROPERTY 3.1 Type of Affected Property (a) Land (b) Structure (c) Land & Structure 3.2 Offset from the Outer Edge of Existing RoW ______Ft. 3.3 Located At (RS / LS) ______3.4 In case of affected land provide following details:

TotalLand Owned Affected Land Type of Land (Kanals) Width Length (with in and outside this village) (ft.) (ft.) a) Agriculture b) Commercial c) Residential d) Grazing Land e) ForestLand f) Wasteland g) Others (specify)

3.5 If Structure, Specify Category of Structure: (Tick Relevant) (a).Commercial______(b).Residential______(c). Dera______

3.6 Information about Commercial Structures: Ownership Documents: (Yes)______(No)______

103 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Type of Structure Affected Size (ft.) Estimated Year of Structure (codes) Structures(ft.) Cost (Rs.) Construction H W L Roof Wall Floor (WxL) Shop Khokha Adda

3.7 Information About Residential Structure: Ownership Documents: (Yes)______(No)______Similar Size (ft) Type of Structure Affected Sr. Estimate Year of Const. Structur Structure No d Cost Constructio Cost at e Roo Wal Floo s (sq. ft) . H W L (Rs.) n Presen f l r (WxL) t (Rs.) Living 1 Rooms Kitchen 1 Bathroom 1 / Latrine Shed 1 (Animal) Boundary 1 Wall Hand 1 Pump

Types of Structures (codes)

Walls: 1= Bricks + Cement + Cement Plaster 2=Bricks+Mud+Mud Plaster 4= Mud Masonry Roofs: 1= RCC 2= RBC 3=Tiles+T.Irons+Girders 4= Tiles+Wooden Planks 5= Asbestos/ Iron Sheets 6=Mud+Wood 7= Mud +Thatched Floors: 1= Mosaic 2= Concrete with Plaster 3= Bricks+Cement 4= Mud 3.8 Ownership of Land/ Structure 3.8.1 Have legal Documents Yes: No: 3.8.2 Have Informal Documents Yes: No: 3.8.3 Inherited Yes: No: 3.8.4 Possession Only Yes: No:

104 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Details about Shareholders, if any: Relationship Document Sr. Share in Name with Available No. % age Respondent (Yes/No) 1. 2. 3. 4. 5.

3.9 Employee Description: How many employees do you have? ______Nos. Averag Stay At Site Family Composition Sr. Name of Nature of e With No Employe Employme Monthl Alon Mal Femal Childre Tota Famil . e nt y Wage e e e n l y (Rs.) 1 2 3 4 5 3.10 Details about Affected Crops: Sr. Crops Area Production Total Qnty. Price No. Marla Kanal (Kgs) Costs Sold (Rs./40Kgs) (Rs.) (Kgs) 1. 2. 3. 4. 5.

3.12 Details about other Affected Assets: Type of Asset No. Value (Rs.) When Purchased / Installed (No. of Yrs.) Peter Engine Hand Pump/Donkey Pump Electric Motor Tube Well Lined Watercourse Other (specify) 3.13 Detail of Affected Trees: Sr. Description Privately Owned Government No. No. Value Age No. Age (Yrs) (Rs.) (Yrs) 1 Shade Trees a. Shesham b. Popular c. Eucalyptus d. Kikar

105 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

e. Bakian f. Other 2 Fruit Trees a. Ma- b. Orange/Kino c. Lemon d. Guava e. Pomegranate f. Other 4. COMPENSATION PREFERENCES 4.1 Do you have some other place to move? (Yes)______(No) ______4.2 In case of Yes: a) How far away from this place? ______(km) (b) Do you own this place?(Yes)___ (No)____

4.3 In case of No, what kind of assistance you expect from the Project? Type of Assistance / Compensation In Lieu of Cash Compensation (Tick) Land Structure Construction

5. IN CASE OF TENANT 5.1 Name of Owner: ______Name of Occupation / Business ______Av. Monthly Income (Rs.) ______Av. Monthly Rent (Rs.) ______5.2 Type of Tenancy (a) Residential (b) Commercial (c) AgricultureLand 5.3 For how long you are at tenancy: ______Month ______Year 5.4 Have you made any investment: (Yes)______(No) ______5.5 If yes, Provide following details:

Size (ft) Estimated Year of Cost for Similar Structure W L Cost (Rs.) Construction Replacement (Rs.) House (Rooms) Shop Khokha Other (specify)

6. COMMENTS / OBSERVATIONS 6.1 General Remarks of the Respondents: ______6.3 Pressing Needs of the Respondent:

106 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

______6.4 General Observations of Interviewers: ______

Name of Interviewer ______Dated______

107 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Appendix II: Socio-economic and Poverty Assessment Baseline Survey Questionnaire

Form/case#______LOWERBARIDOABCANAL IMPROVEMENT PROJECT SOCIO-ECONOMIC AND POVERTY ASSESSMENT BASE LINE SURVEY

1. IDENTIFICATION 1.1: Name ofRespondent______1.2: Father’sName______1.3: Respondent NIC No: ______1.4: Permanent Address of the Respondent: Village: ______Town ______Tehsil ______District: ______1.5 Located At: Head / Middle / Tail (of the Distributary / Minor) 1.6 Category of Respondent: (Tick relevant) 1 ResidentLand Owner 2 AbsenteeLand Owner 3 Tenant 4 Business Owner 5 Business Tenant Operator 6 Encroacher Operator 7 Squatter 8 Other 9 Specify)______

1.7 Demographic Profile of Respondent (Children up to 10 yrs (#): M___, FM ___=T______) Name of Income from Relationship Sex Education Business/ Business/ Sr. with Age Health Male=1 (See Occupation (See Occupation (Rs. / No. Respondent (Yrs.) Condition Female=2 Codes) Codes) Annum) (See codes) Main Secondary Main Secondary 1 SELF 2 3 *Other: Rent from property, remittances, net sale of items during a year, net income from agriculture etc. Demographic Codes: a).Relationship: 1=Self, 2=Wife, 3=Son, 4=Daughter, 5=Father, 6=Mother, 7=Brother, 8=Sister, 9=Grand Father, 10=Grand Mother,11=Sister in Law, 12=Nephew, 13=Father-in-Law, 14=Mother-in-Law, 15=Niece, 16Uncle, 17Aunty, 18. Son, 19. Daughter, 20 S. in Law,21D. in Law, 22 Other______23.Other______b).Sex: 1=Male, 2=Female c).Education: 1= Primary 2= Middle 3= Metric, 4= Intermediate, 5= Graduate, 6= Post Graduate, 7=Law, 8=Engineer, 9=MBBS, 10=Technical Diploma, 11=Dars-e-Nizami, 12=Can Read Quran, 13= Can Insert Signatures, 14= Illiterate d).Occupations: 1=Agriculturist, 2=Shopkeeper, 3= Hotel, 4=Mechanic,5=Barber,6=Butcher,7=Cobbler,8= Business,9= Govt. Servant, 10=Private Servant, 11=Labor, 12=Student, 13=House- Maid,14= House Wife,15=Advocate, 16=Livestock/Dairy, 17=Fishing, 18=Driver, 19=Health Related, 20=Teaching,21=Entertainer, 22=Gone Abroad, 23=Retired/Old,24=Other______5=Other______

108 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP) e). Health: 1= Good, 2= Average, 3= Poor

2. LANGUAGE SPOKEN______3. Agricultural Implements Sr. Year of Items Nos. Present Value No. Purchase 1 Tractor 2 Fodder Cutter 3 Sowing Machine/Drill 4 Harvesting Machine 5 Thresher 6 Sprinkler 7 Spray Pump 8 Land Leveler 9 Scrapper 10 Others

3.1: LAND UTILIZATION Land Acres Kanal Marla a. Total Area owned b. Total Cultivated Area • Area Under Rabi ( winter)

Crops • Area Under Kharif (summer)

Crops c. Uncultivated Area • Area Under Trees • Area Under Farm Structure • Waste land

3.2: Cropping Pattern, Yield and Cost Area Sown Total Price Production costs Code Crops (Rs/40kg) Acres Kanal (Kgs) incurred

(Rs.) 1 2 3 Cotton 4 5 Millets 6 7 Fodder (kharif) 8 Vegetables(kharif) 9 Barley 10 11 Oilseed 12 Fodder (Rabi) 13 Vegetables(Rabi) 14 Orchards 15 Other

109 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

3.3: Source of Irrigation 1. Canal 2. Tube well 3. Canal + Tube well 4. Lift Irrigation 5. Barani 6. Other 3.4: Prevalent Land Rate (Rs. Per kanal) Residential______Grazing Land______Cultivated______Waste Land______Cultivable Waste______Other______3.5: Land Rent (Rs./ Year) ______3.6: Tube well Water (Rs./Hr.)______3.8 CanalWater (Rs. /Turn/Hr.)______

4.POSSESSION OF HOUSEHOLD ITEMS Item No Value(Rs.) Item No Value(Rs.) Refrigerator Van/Pickup Deep Freezer Gas Cylinder Television VCR Washing Machine Dish Antenna Electric Fan Telephone/PTCL Electric Iron Mobile Electric Madhani Geyser Sewing Machine Air Conditioner Radio/Tape Recorder Electric Water Pump Bicycle Computer Motor Cycle/Scooter Air Cooler Car Other

5. AVERAGE MONTHLY EXPENDITURE ON FOOD AND NON- FOOD ITEMS (RS.)

Food Items Expenses Non-Food Items Expenses Meat Bath Soap Ghee Washing Soap Sugar Gas Cylinder Flour Fuel Wood Legumes Kerosene Oil Vegetables Other Species Tea Leaves Others

5.1: Av. Monthly Bills (Rs.) Electricity ______Telephone______Water______Education______5.2: Expenditure on clothes and shoes during last year (Rs.)______5.3: Occasional expenses during last year (Rs.)______

110 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

5.4: Annual Expenditure on Health Care (Rs.)______6. HOUSING CONDITIONS 6.1 Total Area of the House:______Kanal ______Marla 6.2 Year of Construction______6.3 Present Value of the House (Rs.)______6.4 Type of Structure a) Kacha______b) Pacca______c) Semi-Pacca______6.5 Structure Details Type of Structure No. of Rooms Type Living rooms Animal shed/room Other shed / Kitchen Bathroom (Separate / Attached) Latrine -Open -Flush 7. ACCESS TO SOCIAL AMENITIES (TICK) Non- Social Amenities Available Satisfactory No Access Satisfactory Electricity Gas Water Supply Telephone Sewerage/Drainage BHU School

8. LIVESTOCK INVENTORY Livestock No. Present Value (Rs.) Buffaloes Cows Horse Donkey Camel Sheep/Goat Poultry 9. WOMEN’S PARTICIPATION AND ROLE IN DIFFERENT HOUSEHOLD ACTIVITIES 9.1: Participation and Decision Making (Tick): Participation Decision Making Activities Extent (%) Extent (%) Household activities Child caring Farm/Crop activities Livestock rearing Sale & Purchase of properties Social obligations (marriage, birthday & other

functions) Local representation (councilor/political

111 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

gathering)

9.2: Education and Earning Status Av. Employment Relationship Sr. Education Name of Monthly 1=Employees with the Age No. Level Institute Income 2=Household Respondent (Rs.) Activities 1 2 3

9.3: PERCEPTIONS OF RESPONDENTS FOR ACTION ASSOCIATED WITH THE PROJECT Possible impacts/effects of the Project 1 Increase 2 Decrease Employment opportunities Industrial Development Opportunities Living standard Unemployment Income generating activities Electricity Supply Quality Mobility (Access to Resources) Other specify 10. Does any NGO Exist in your Area? Yes______No______If yes, Name of - :______Are you member of this- ______Are you member of this - ______Role of - :______11. General Remarks of the Respondents ______12. General Observations of Interviewers ______

Name of Interviewer: ______Dated:______

112 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

ID#______

Appendix III:Gender Survey

LOWERBARIDOABCANAL IMPROVEMENT PROJECT (LBDCIP) LBDC COMPONENT

1. LOCATION

1.1: Name of Canal/Distry /Minor: ______1.2: RD______

2. IDENTIFICATION

2.1: Name of Affected Person: ______2.2: Father’s Name ______

2.3: Permanent Address of the Respondent:

Village/Town:______Tehsil______District: ______

3. Education and Earning Status

Relationshi Av. Sr. Age Age Marita Occupation p with Educatio Monthly No l Respondent (Yrs. (Yrs. n Mai Secondar Income(Rs. . ) ) Status (See codes) n y ) 1 SELF 2 3 4 5 6 7 Demographic Codes: a) Occupations: 1=House Wife, 2=House-Maid, 3=Shopkeeper 4=Private Servant, 5=General Labor, 6=Livestock, 7=Health Related, 8=Teaching, 9=Other______b) Relationship: 1=Wife, 2=Daughter, 3=Mother, 4=Sister, 5=Grand Mother, 6=Sister in Law, , 7=Daughter in Law, 8=Mother-in-Law, 9=Niece, 10=Aunty, 11. Other, c) Marital Status: 1= Single 2= Married

113 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

4. Participation and Decision Making (Tick): Decision Participation Activities Making Extent (%) Extent (%) Household activities Child caring Farm/Crop activities Livestock rearing Sale & Purchase of properties Social obligations (marriage, birthday & other

functions) Local representation (councilor/political gathering)

5. What is source of Water for your domestic use?

5.1: Public Water Supply______5.2: Hand Pump/Electric Motor______

5.3: River/ Canal Water______5.4: Any other______

6. What are the pressing needs of the women of the area?

6.1: During Construction:- ______

6.2: AfterConstruction:______

7. Is there Association/Organization exist in this Area?

(i) Yes______(ii) No______

7.1: If yes, Name of NGO:______

114 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

7.2: Area of Interest: ______

8. In your opinion, should this project be implemented here? ______

9. General Observations of Interviewer: ______

Name of Interviewer: ______Dated: ______

115 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Appendix IV: List of Officers/Officials Contacted Regarding Private Land Occupation for Diversions ICB-05 Sr. Name Designation Contact No No. 1 Rashid Qureshi SDO, 9-L Gunjibar 0322-8752580 2 Rao Athar Ali SDO, Chichawatni 0332-4910138 3 Amin Lateef ullah SDO, Sahiwal 0300-9699455 4 Muhammad Ishaq Overseer, 9-L Gunjibar 0300-8752580 5 Shahid Rafique Ziladar 03016525729 6 M. Shareef Ziladar - 7 Khalid Mehmood Ziladar - 8 M. Younas Patwari 0344-6689905 9 M. Ali Blouch Patwari 0307-6929128 10 Shoukat Shah Patwari 0301-6524368 11 Rana Munir Ahmad Patwari 0300-6904479 12 M. Saleem Office Clerk, 9-L Gunjibar 03016533480 13 Liaquat Ali Patwari 0300-7832130 14 Narshad Ali Patwari 0345-7478178 15 Nazeer Ahmad Patwari 0347-6353729 16 Arshad Butt Patwari 0303-7998389 17 M. Rasheed Patwari 0345-7470584 18 Abdul Hameed Patwari 0300-7832763 19 Ghulam Hussain Patwari 0300-6936956

116 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

Appendix V: MOU between project team and affected farmer

117 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

118 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

119 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

120 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

121 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

122 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

123 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

124 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

125 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

126 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

127 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

128 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

129 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

130 Updated Land Acquisition and Resettlement Plan, ICB 05 Lower Bari Doab Cana Improvement Project PIAIP)

131