File No.P-17024/12/2020-RC

File No. P-17024/12/2020-RC (FMS-369983) Government of Ministry of Rural Development (RC Division) Krishi Bhawan, New Dated 11th May, 2021 To

The Principal Secretary, Panchayati Raj & Rural Development Department, Government of , Multi- Storeyed Building, 3rd Floor, Gate No. 3, Ambedkar Road, - 560001, Karnataka.

Sub: Karnataka State–Proposal cleared under PMGSY-III, Batch I of 2019-20– Revised cost for the proposal under PMGSY-III of 2019-20, Batch-I.

Sir, I am directed to refer to this Ministry’s letter of even number dated 2nd March, 2020 regarding clearance of the project proposal of Karnataka under PMGSY- III, Batch-I of 2019-20 and to say that the project proposals were sanctioned subject to the condition, among others, that the State will verify all the DPRs as per the observation of the Empowered Committee regarding the provisions of CD works, retaining walls, road safety items, etc., and ensure that the corrections have been made in all the DPRs before according technical sanction. The State was further asked to provide the statement showing MoRD sanctioned cost and cost corrected at the time of technical sanction.

2. Based on the compliance report submitted by the State Government, the Ministry hereby accords approval to the revised Value of Project (VoP), the MoRD Share and the State Share of the project sanctioned to the State under PMGSY-III, Batch-I, 2019-20, as per summary given below:-

Items Up-gradation LSBs Total roads Value in Rs Crore 2,094.35 44.63 2,138.98* No. of works 445 26 445 roads 26 LSBs Length in km 3,226.21 1,023.67 m 3,226.21 Km roads 1,023.67 m LSBs Average cost per Km (Rs. In 64.92 4.36/m Lakhs) *MoRD Share: Rs. 1,254.50 Crores State Share: Rs. 884.48 Crores

File No.P-17024/12/2020-RC

3. The OMMAS based road list and district abstract with revised cost are enclosed herewith.

4. All other terms and conditions attached to the clearance of aforesaid project vide this Ministry's letter of even number dated 2nd March, 2020 shall remain the same.

5. This issues with the approval of the Competent Authority. Yours faithfully,

(Lalit Kumar) Deputy Secretary to the Government of India Tel: 011- 23382406 E-mail:- [email protected]

Copy to :- 1. Chief Engineer, KRRDA, 3rd Floor, Anandarao Circle, Bangalore-560009, Karnataka. 2. Director (Technical), NRIDA with a request to ensure compliance on the conditions imposed and bring to Ministry's notice in case of non-compliance on the conditions imposed. 3. Director (P-I), Director (P-II), Director (P-III), Director (F & A), NRIDA, New Delhi. File No.P-17024/12/2020-RC

Signature Not Verified

Digitally signed by LALIT KUMAR Date: 2021.05.12 14:19:18 IST Pradhan Mantri Gram Sadak Yojana

Road List for attachment with Sanction Letter - District Wise Abstract

State : Karnataka Sanction Year : 2019-2020 Batch : 1 Collaboration : Regular PMGSY

Sr.No. District No of Road Length MoRD Cost State Cost (Rs Total Cost Maint. Cost Habs (1000+, 500+, 250+, <250, Total) Works (Kms) / Bridge (Rs Lacs) Lacs) (Rs Lacs) (Rs Lacs) Length (Mtrs) 1 2 3 4 5 6 7 8 9

Road Proposals

1 Bangalore R 15 97.940 3,499.02 2,393.75 5,892.77 547.03 (27 , 53 , 42 , 60 , 182)

2 Bangalore U 14 128.890 6,332.89 4,465.88 10,798.77 795.31 (77 , 51 , 37 , 52 , 217)

3 43 307.395 11,078.37 7,714.93 18,793.30 1,599.44 (116 , 25 , 8 , 0 , 149)

4 1 5.540 205.69 138.15 343.84 32.04 (2 , 1 , 2 , 0 , 5)

5 14 111.520 4,170.43 2,943.72 7,114.15 683.13 (39 , 11 , 9 , 4 , 63)

6 16 106.085 3,185.59 2,255.93 5,441.52 494.79 (51 , 28 , 17 , 7 , 103)

7 Chickballapur 17 157.790 5,083.26 3,474.86 8,558.12 884.06 (40 , 58 , 51 , 44 , 193)

8 Chickmagalur 20 168.635 6,221.90 4,596.34 10,818.24 913.62 (36 , 32 , 42 , 145 , 255)

9 11 69.630 2,479.07 1,685.78 4,164.85 360.44 (31 , 16 , 6 , 8 , 61)

10 Dakshina 12 107.310 5,470.30 4,007.41 9,477.71 653.21 (10 , 23 , 38 , 61 , 132)

11 16 166.864 6,194.71 4,283.12 10,477.83 831.15 (90 , 50 , 31 , 20 , 191)

12 9 77.870 3,295.24 2,298.01 5,593.25 459.94 (40 , 9 , 8 , 1 , 58)

13 Gadag 4 28.400 989.48 692.45 1,681.93 167.09 (11 , 0 , 0 , 0 , 11)

14 25 170.268 6,550.88 4,469.80 11,020.68 961.11 (72 , 25 , 24 , 17 , 138)

15 Hassan 21 116.460 4,988.04 3,642.87 8,630.91 655.35 (41 , 63 , 62 , 139 , 305)

16 Haveri 20 162.790 6,136.26 4,328.85 10,465.11 1,102.30 (75 , 15 , 2 , 2 , 94)

17 Kodagu 12 78.528 3,212.55 2,304.31 5,516.86 486.06 (15 , 13 , 20 , 75 , 123)

18 21 165.225 5,783.07 4,034.23 9,817.30 761.01 (60 , 99 , 73 , 72 , 304)

19 5 36.400 1,294.89 890.99 2,185.88 205.37 (25 , 5 , 1 , 3 , 34)

20 32 189.635 6,801.10 5,024.21 11,825.31 1,039.36 (97 , 61 , 46 , 49 , 253)

21 17 116.506 4,708.59 3,391.94 8,100.53 507.67 (92 , 69 , 36 , 32 , 229)

22 5 42.190 1,851.99 1,272.99 3,124.98 245.81 (16 , 1 , 4 , 12 , 33)

23 Shimoga 22 140.995 5,024.33 3,674.59 8,698.92 811.84 (44 , 37 , 29 , 75 , 185)

24 42 246.806 8,980.28 6,194.61 15,174.89 1,403.38 (113 , 123 , 152 , 275 , 663)

25 5 36.227 1,592.54 1,147.56 2,740.10 186.16 (0 , 4 , 15 , 39 , 58)

26 Uttara Kannada 20 135.075 5,364.39 3,772.16 9,136.55 875.65 (11 , 27 , 51 , 371 , 460)

27 Yadgir 6 55.240 2,280.07 1,560.90 3,840.97 335.60 (25 , 1 , 4 , 0 , 30)

Roads Total 445 3,226.214 1,22,774.93 86,660.34 2,09,435.27 17,997.92 (1256 , 900 , 810 , 1563 , 4529)

Long Span Bridge Proposals

1 Belgaum 1 16.300 50.96 33.97 84.93 0.00 -

2 Davanagere 1 83.000 267.37 178.25 445.62 0.00 -

3 Dharwad 7 229.150 451.87 301.25 753.12 0.00 -

4 Gadag 3 72.720 127.46 84.98 212.44 0.00 -

5 Gulbarga 1 43.500 87.41 58.27 145.68 4.32 -

6 Haveri 3 88.260 138.79 92.53 231.32 0.00 -

7 Tumkur 5 152.540 211.31 140.87 352.18 0.00 -

8 Udupi 4 300.000 1,214.79 813.86 2,028.65 31.25 -

9 Uttara Kannada 1 38.200 125.29 83.53 208.82 0.00 -

Bridges Total 26 1,023.670 2,675.25 1,787.51 4,462.76 35.57 -

Grand Total 471 Total Road 1,25,450.18 88,447.85 2,13,898.03 18,033.49 (1256 , 900 , 810 , 1563 , 4529) Length:3226.214 Kms Total LSB Length:1023.670 Mtrs

Page 1 of 1 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sanction Letter No :369983 Sanction Date : 02/03/2020

State : Karnataka Sanction Year : 2019-2020 Batch : 1 Collaboration : Regular PMGSY Note : All Costs are in Lakhs and Lengths are in Kms.

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Road Proposals

District- Bangalore R

Block-

1 MRL07 MRL07-MDR ( road) Upgarde -- 6.550 3.750 Complete 12 215.53 147.46 362.99 41.21 (2 , 2 , 3 , 2 , 9) to Tellahally agrahara road via Boodihal, Channahally,Chikka Hosahally 2 MRL21 MRL21-NH-207 to Taluk Upgarde Waste Plastics 11.380 3.750 Complete 18 490.16 334.90 825.06 66.99 (3 , 7 , 3 , 0 , 13) Border via, konaginabele, Doddakurubarahally, Varadenahally, Naganayakanahally, 3 MRL09 MRL09-SH 104 to Taluk Upgarde Waste Plastics 3.840 3.750 Complete 10 190.69 130.21 320.90 22.60 (0 , 8 , 1 , 0 , 9) Border via, Kondenahally, Kaggalahally, Jonnahally, Devanayakanahally Block Devanahalli Total 21.770 40 896.38 612.56 1,508.94 130.80 (5 , 17 , 7 , 2 , 31) Block- Doddaballapur

4 MRL06 MRL06-Kondasandra to MDR Upgarde -- 4.400 3.750 Complete 11 166.18 113.59 279.77 25.90 (1 , 2 , 4 , 5 , 12) 22 via Thubagere, Nellugudige, Geddalapalya, Palpaldinne

Page 1 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

5 T02 T02-MDR 7 to MDR 4( KK Upgarde Waste Plastics 13.700 3.750 Complete 29 591.38 404.02 995.40 80.65 (2 , 5 , 10 , 8 , Road) via Nellikuntepalya, 25) Nelkunte, Tanda Nagashettihalli, Cheelanahalli,Tippur, Madeswara, Bomanahalli, Kadabyadarahalli 6 MRL11 MRL11-NH207 to Koluru via Upgarde Waste Plastics 5.030 3.750 Complete 7 186.74 127.58 314.32 29.61 (3 , 3 , 0 , 0 , 6) Thalagavara, Honnagatta Block Doddaballapur Total 23.130 47 944.30 645.19 1,589.49 136.16 (6 , 10 , 14 , 13 , 43) Block- Hosakote

7 MRL24 MRL24-Banamakanahally Upgarde -- 5.960 3.750 Complete 16 195.91 134.06 329.97 22.02 (2 , 2 , 1 , 4 , 9) MDR to Gundrahally via Agasarahally, Marasandrahally, Sathiganahally, Hedakanahally 8 MRL23 MRL23-Kembliganahally to Upgarde -- 6.740 3.750 Complete 20 242.67 166.11 408.78 35.06 (3 , 7 , 1 , 4 , 15) Bavapura via C.T. Gollahally, Malliyappanahally, K- Sathyavara, Channigalapura 9 T02 T02-Upparahalli TO Upgarde Waste Plastics 10.400 3.750 Complete 19 234.41 160.82 395.23 61.22 (6 , 6 , 6 , 3 , 21) Doddakoliga VIA, Muthakadally, Beguru, Kamblipura, Kurubarahally, Sonnadenahally 10 MRL05 MRL05-Doddakoliga MDR TO Upgarde Waste Plastics 6.160 3.750 Complete 16 221.55 151.69 373.24 34.20 (1 , 1 , 0 , 0 , 2) Doddanallurahally MDR VIA, Chikkanallurahally, Beguru , Beemakanahally, Bagalur Block Hosakote Total 29.260 71 894.54 612.67 1,507.21 152.50 (12 , 16 , 8 , 11 , 47)

Page 2 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

11 MRL04 MRL04-NH-4 to Upgarde Waste Plastics 3.740 3.750 Complete 11 166.85 114.18 281.03 22.02 (3 , 1 , 1 , 5 , 10) Honnarayanahalli via T. Begur, Araledibba, Anandhnagar, Thirumalapura, Koneripura, Kempohalli, Madalakote 12 MRL02 MRL02-NH-48 to Taluk Upgarde Waste Plastics 3.600 3.750 Complete 6 117.58 80.60 198.18 21.19 (1 , 2 , 3 , 6 , 12) Border via Gandhigrama, , Lambani thanda, , Thimmegowdana palya, Bolamaranahalli 13 MRL16 MRL16-Dasenahalli Colony Upgarde Waste Plastics 6.210 3.750 Complete 16 193.37 132.55 325.92 34.27 (0 , 3 , 3 , 12 , to Pandupura via Thatte 18) kere, Karimanne, Imechanahally, Imechanahally colony, Devarahatti, Laxmipura 14 MRL22 MRL22- MDR Upgarde -- 3.740 3.750 Complete 10 101.94 69.83 171.77 15.66 (0 , 1 , 5 , 3 , 9) to Arebommanahalli VR Rd Jn via Thottanahalli, Hanumanthapura, Indiranagara, Mahimapura, Gangagowdana palya, Kempapura Agrahara 15 MRL15 MRL15- Upgarde Waste Plastics 6.490 3.750 Complete 19 184.06 126.18 310.24 34.44 (0 , 3 , 1 , 8 , 12) Hanumanthegowdanapalya MDR to Taluk Border via Srinivasapura, Srinivasapura Colony, Hanchipura, Kakkepalya, Kodappanahalli Block Nelamangala Total 23.780 62 763.80 523.33 1,287.13 127.58 (4 , 10 , 13 , 34 , 61)

Page 3 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Bangalore R Total 97.940 220 3,499.02 2,393.75 5,892.77 547.03 (27 , 53 , 42 , 60 , 182) District- Bangalore U

Block-

16 MRL04 MRL04-NH 07 () Upgarde Waste Plastics 7.420 5.500 Complete 9 364.40 249.99 614.39 44.45 (10 , 2 , 0 , 0 , to SH 35 () via 12) Lakshmisagara, Allibommasandra, Guddahatti and Jigala 17 T06 T06-Guddahatti-Jigala Jun Upgarde Waste Plastics 21.500 5.500 Complete 42 1,047.98 733.13 1,781.11 126.54 (8 , 13 , 6 , 3 , to TN Border 30) (Meesaganahalli) Via Yadabvanahalli, Abbianapalya, Vaddarapalya, Manchanahalli, M.Medihalli, Rachamanahalli, Bidaragere, Muthagatti, Hompalaghatta 18 MRL03 MRL03-Hebbagodi to Upgarde Waste Plastics 8.400 5.500 Complete 10 390.61 275.99 666.60 49.43 (6 , 2 , 1 , 0 , 9) Bangalore South Tq Border via Thirupalya, Hulimangala, S Bingipura, and C K Palya

Page 4 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

19 T07 T07-Muthanalluru to TN Upgarde Waste Plastics 16.650 5.500 Complete 17 976.00 683.79 1,659.79 111.83 (6 , 6 , 0 , 4 , 16) Border (Narsapura) Via , Arenuru, Andenahalli, Bilichikkanahalli, Billapura, Adigara Kallahalli, Bidaraguppe SF, Bidaraguppe and Mallenahalli Block Anekal Total 53.970 78 2,778.99 1,942.90 4,721.89 332.25 (30 , 23 , 7 , 7 , 67) Block- Bangalore(E)

20 MRL14 MRL14-MDR ( Byrathi) to Upgarde -- 3.500 5.500 Complete 3 141.94 106.42 248.36 33.55 (3 , 3 , 1 , 1 , 8) MDR ( Angalapura)via Doddagubbi Colony, Doddagubbi. 21 MRL11 MRL11-Kodathi to Sulikunte Upgarde Waste Plastics 4.250 5.500 Complete 12 211.45 152.84 364.29 36.49 (4 , 2 , 1 , 0 , 7) Colony, Colony,Mullur Kachamaranahalli Block Bangalore(E) Total 7.750 15 353.39 259.26 612.65 70.04 (7 , 5 , 2 , 1 , 15) Block- Bangalore(N)

22 MRL06 MRL06-MDR (Dombarahalli) Upgarde -- 4.700 5.500 Complete 4 215.58 154.03 369.61 27.66 (7 , 2 , 6 , 3 , 18) to SH-03 ( Main Road) Via Machohalli, Machohalli JHC, KG Lakkenahalli, NR Pura, Kammasandra and Kadirenahalli

Page 5 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

23 MRL01 MRL01-NH-04 (Kodipalya) to Upgarde -- 4.170 5.500 Complete 4 195.22 139.80 335.02 24.55 (4 , 0 , 2 , 4 , 10) SH-03(Chikka Gollarahatti) via Doddanna Layout, Channayakana Palya, Thippena Halli, Shantinagara, Gangondanahalli, Kachohalli Indira calony and Kachohalli. 24 MRL03 MRL03-Thammrnahalli to Upgarde Waste Plastics 3.800 5.500 Complete 6 187.73 136.97 324.70 19.98 (5 , 1 , 0 , 1 , 7) TR01( Kuduregere) via Soladevanahalli, sasiveghatta. 25 T02 T02- (SH-02) Upgarde Waste Plastics 19.730 5.500 Complete 21 946.28 671.12 1,617.40 116.15 (12 , 15 , 10 , 12 to Nagadasanahalli Via , 49) Ganigarahalli, Kasaghattapura, Mylappanahalli, Madappanahalli, Itgalapura, Adde, Sadenahalli, Adiganahalli and Rajanukunte 26 T01 T01-NH-04 (Makali) to Upgarde Waste Plastics 17.510 5.500 Complete 21 854.24 597.84 1,452.08 103.07 (4 , 3 , 5 , 11 , Kallegowdanapalya Via 23) Balaveeranahalli, Hunnigere, Lakkenahalli, Byregowdanadoddi, Appanappanapalya, Gejjigadahalli, Harokyathanahalli, Kodipalya and Bheereshwaranagara Block Bangalore(N) Total 49.910 56 2,399.05 1,699.76 4,098.81 291.41 (32 , 21 , 23 , 31 , 107)

Page 6 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Bangalore(S)

27 MRL12 MRL12-Tharalu To Upgarde Waste Plastics 6.260 5.500 Complete 15 289.33 205.38 494.71 36.85 (3 , 0 , 2 , 5 , 10) - Bannerughatta Road Via Thataguppe,Alakabelalu And Gutte palya. 28 MRL16 MRL16-Uttari- Thittahalli Upgarde -- 3.500 3.750 Complete 4 107.35 77.12 184.47 20.61 (1 , 2 , 2 , 4 , 9) Road To Kere Choodahalli. Via Dinnepalya,And Chikka nagi palya. 29 MRL11 MRL11-NH 209 (Saluhunise) Upgarde Waste Plastics 7.500 5.500 Complete 16 404.78 281.46 686.24 44.15 (4 , 0 , 1 , 4 , 9) To NH209 main Road Via O B Choodahalli And Vaderahalli. Block Bangalore(S) Total 17.260 35 801.46 563.96 1,365.42 101.61 (8 , 2 , 5 , 13 , 28) District Bangalore U Total 128.890 184 6,332.89 4,465.88 10,798.77 795.31 (77 , 51 , 37 , 52 , 217) District- Belgaum

Block- Athani

30 MRL10 MRL10- to Kallal Upgarde -- 6.420 3.750 Complete 3 203.00 142.05 345.05 32.60 (8 , 2 , 0 , 0 , 10) via Wadder vasti 31 MRL08 MRL08-Athani to via Upgarde StrataWeb/Geo 12.400 3.750 Complete 9 422.78 292.13 714.91 63.47 (6 , 1 , 0 , 0 , 7) Akalkallu Hulugabali cell 32 MRL17 MRL17-Awarkhod to MDR via Upgarde -- 7.865 3.750 Complete 0 303.71 209.76 513.47 40.76 (3 , 0 , 0 , 0 , 3) Radderhatti Karl tota Block Athani Total 26.685 12 929.49 643.94 1,573.43 136.83 (17 , 3 , 0 , 0 , 20)

Page 7 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Bailahongala

33 MRL09 MRL09-Neelamma Temple- Upgarde Waste Plastics 8.610 3.750 Complete 6 350.87 243.33 594.20 42.22 (4 , 0 , 0 , 0 , 4) Murkibhavi- 34 MRL06 MRL06- T Shigihalli Upgarde -- 6.090 3.750 Complete 8 264.53 185.14 449.67 32.57 (4 , 1 , 0 , 0 , 5) Road 35 MRL38 MRL38-Maradinaglapur Upgarde -- 4.473 3.750 Complete 4 202.58 141.48 344.06 25.57 (3 , 0 , 0 , 0 , 3) Chikkabagewadi 36 MRL39 MRL39- Upgarde -- 9.494 3.750 Complete 4 321.44 223.32 544.76 49.10 (3 , 0 , 0 , 0 , 3) to 37 MRL11 MRL11- to Upgarde -- 4.900 3.750 Complete 0 89.96 64.59 154.55 27.99 (1 , 1 , 0 , 0 , 2) 38 MRL24 MRL24-Ambadgatti Upgarde Cold Mix 5.010 3.750 Complete 6 206.99 144.57 351.56 26.31 (2 , 1 , 0 , 0 , 3) Technology
StrataWeb/Geo cell 39 MRL36 MRL36-Yarguddi Bairnatti Upgarde -- 6.430 3.750 Complete 13 271.98 189.15 461.13 31.90 (2 , 2 , 0 , 0 , 4) Hanumanatti Block Bailahongala Total 45.007 41 1,708.35 1,191.58 2,899.93 235.66 (19 , 5 , 0 , 0 , 24) Block- Belgaum

40 MRL22 MRL22-Hangaraga to Upgarde -- 6.034 3.750 Complete 4 149.22 103.08 252.30 19.20 (2 , 0 , 0 , 0 , 2) 41 MRL01 MRL01-Kurabarahatti- Upgarde -- 5.474 3.750 Complete 7 159.48 110.73 270.21 20.07 (2 , 0 , 1 , 0 , 3) to 42 MRL04 MRL04- to Upgarde -- 4.100 3.750 Complete 4 162.30 112.64 274.94 20.94 (2 , 0 , 0 , 0 , 2)

43 MRL35 MRL35--Budyanur Upgarde -- 5.690 3.750 Complete 3 164.32 114.30 278.62 29.64 (1 , 1 , 1 , 0 , 3) to Karavi Block Belgaum Total 21.298 18 635.32 440.75 1,076.07 89.85 (7 , 1 , 2 , 0 , 10)

Page 8 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Chikkodi

44 MRL08 MRL08-Khadakalat to Upgarde -- 7.120 3.750 Complete 3 180.25 126.59 306.84 38.45 (2 , 1 , 0 , 0 , 3) Gouraimaradi via Chikalwal 45 MRL11 MRL11-Gavan to MN Road Upgarde -- 5.881 3.750 Complete 6 161.81 112.56 274.37 29.08 (3 , 2 , 0 , 0 , 5) (Mahat Godawn) 46 MRL28 MRL28- to Upgarde -- 6.020 3.750 Complete 4 174.26 121.22 295.48 34.39 (2 , 0 , 1 , 0 , 3) Chanaveeranatti via Karagoan 47 MRL13 MRL13- MDR to Kasanal via Upgarde StrataWeb/Geo 8.910 3.750 Complete 4 254.05 176.29 430.34 50.90 (3 , 0 , 0 , 0 , 3) cell Block Chikkodi Total 27.931 17 770.37 536.66 1,307.03 152.82 (10 , 3 , 1 , 0 , 14) Block-

48 MRL19 MRL19- to melvanki Upgarde StrataWeb/Geo 11.600 3.750 Complete 18 497.23 344.00 841.23 64.57 (5 , 0 , 0 , 0 , 5) road via upparahatti cell 49 MRL03 MRL03-Waderahatti Upgarde StrataWeb/Geo 6.435 3.750 Complete 8 275.60 191.63 467.23 35.07 (3 , 0 , 0 , 0 , 3) Road cell 50 MRL23 MRL23- pg Upgarde -- 7.910 3.750 Complete 4 309.35 221.76 531.11 43.71 (4 , 0 , 0 , 0 , 4) badigawad road via duiradundi 51 MRL16 MRL16-FROM KUNDHARAGI Upgarde -- 6.951 3.750 Complete 4 270.57 191.72 462.29 38.87 (6 , 0 , 1 , 0 , 7) TO VIA MALLAPUR SA Block Gokak Total 32.896 34 1,352.75 949.11 2,301.86 182.22 (18 , 0 , 1 , 0 , 19) Block-

52 MRL11 MRL11-Kamatnur to SH via Upgarde -- 7.866 3.750 Complete 9 307.27 213.57 520.84 44.39 (3 , 0 , 0 , 0 , 3) Yelimunnoli, Hanjanatti 53 MRL14 MRL14- to Solapur Upgarde -- 6.539 3.750 Complete 5 212.96 148.65 361.61 29.28 (3 , 0 , 0 , 0 , 3) Via Honnihal

Page 9 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

54 MRL18 MRL18-Chikkalagudda to Upgarde -- 7.433 3.750 Complete 8 258.85 180.43 439.28 42.50 (1 , 2 , 0 , 0 , 3) Anandpur RC via Tudimal Tota, Ullagaddi , 55 MRL25 MRL25-Chilabhavi to Upgarde -- 7.551 3.750 Complete 4 206.50 144.62 351.12 38.05 (2 , 0 , 0 , 0 , 2) Upto MDR Block Hukkeri Total 29.389 26 985.58 687.27 1,672.85 154.22 (9 , 2 , 0 , 0 , 11) Block- Khanapur

56 MRL10 MRL10--Jalaga To Upgarde -- 7.733 3.750 Complete 7 280.27 195.00 475.27 40.11 (2 , 0 , 1 , 0 , 3) 57 MRL03 MRL03- To SH via Upgarde -- 9.820 3.750 Complete 8 296.39 206.27 502.66 48.56 (1 , 1 , 0 , 0 , 2) 58 MRL17 MRL17-Hattargunji- Upgarde -- 5.651 3.750 Complete 6 192.82 134.74 327.56 23.42 (0 , 1 , 2 , 0 , 3) -Dukarwadi To SH 59 MRL16 MRL16--Modekoppa Upgarde -- 6.603 3.750 Complete 10 197.12 136.62 333.74 26.57 (1 , 1 , 0 , 0 , 2) To SH-31 Block Khanapur Total 29.807 31 966.60 672.63 1,639.23 138.66 (4 , 3 , 3 , 0 , 10) Block-

60 MRL23 MRL23- to Upgarde -- 6.616 3.750 Complete 5 214.51 150.01 364.52 33.11 (1 , 2 , 0 , 0 , 3) Ugardharan via tikanal tota 61 MRL03 MRL03-Raibag Ambekdkar Upgarde -- 9.186 3.750 Complete 6 363.77 252.41 616.18 45.97 (3 , 0 , 0 , 0 , 3) nagar to chinchali via Jalapur, 62 MRL07 MRL07-Bykud to Nidgundi Upgarde -- 6.406 3.750 Complete 8 273.46 190.19 463.65 32.11 (2 , 0 , 0 , 0 , 2)

63 MRL04 MRL04-Paramandwadi to Upgarde -- 9.006 3.750 Complete 6 317.68 220.91 538.59 47.56 (2 , 0 , 0 , 0 , 2) koligudd Block Raibag Total 31.214 25 1,169.42 813.52 1,982.94 158.75 (8 , 2 , 0 , 0 , 10)

Page 10 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Ramadurga

64 MRL24 MRL24- to M Upgarde -- 6.000 3.750 Complete 3 241.81 168.39 410.20 30.34 (2 , 0 , 0 , 0 , 2) Chandaragi Road 65 MRL18 MRL18- to SH-14 ( via Upgarde -- 6.663 3.750 Complete 8 250.29 174.39 424.68 36.34 (3 , 1 , 0 , 0 , 4) Kolachi Ghataknur) 66 T03 T03-Chippalakatti to Upgarde StrataWeb/Geo 6.000 3.750 Complete 4 247.41 172.34 419.75 33.52 (2 , 0 , 0 , 0 , 2) cell 67 MRL27 MRL27- to Upgarde -- 11.025 3.750 Complete 6 431.02 298.70 729.72 62.13 (4 , 4 , 1 , 0 , 9) Budnur Road Via Gudagamnal- Panchagaon Road Block Ramadurga Total 29.688 21 1,170.53 813.82 1,984.35 162.33 (11 , 5 , 1 , 0 , 17) Block-

68 T11 T11- to Upgarde -- 5.530 3.750 Complete 4 240.53 167.56 408.09 31.43 (2 , 0 , 0 , 0 , 2)

69 MRL10 MRL10-Dundankoppa to Upgarde -- 5.170 3.750 Complete 3 215.55 150.37 365.92 27.26 (2 , 1 , 0 , 0 , 3) Hosur 70 MRL22 MRL22- to Upgarde -- 12.750 3.750 Complete 4 542.67 375.32 917.99 72.28 (5 , 0 , 0 , 0 , 5) (Via ) 71 MRL20 MRL20-Hanchinal to Upgarde StrataWeb/Geo 5.780 3.750 Complete 4 216.02 149.71 365.73 32.83 (1 , 0 , 0 , 0 , 1) upto Taluka cell Border 72 MRL18 MRL18- to Upgarde -- 4.250 3.750 Complete 2 175.19 122.69 297.88 24.29 (3 , 0 , 0 , 0 , 3) (via Gudamakeri) Block Soundatti Total 33.480 17 1,389.96 965.65 2,355.61 188.09 (13 , 1 , 0 , 0 , 14) District Belgaum Total 307.395 242 11,078.37 7,714.93 18,793.30 1,599.44 (116 , 25 , 8 , 0 , 149) District- Bellary

Page 11 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Hadagali

73 T17 T17-Kattebenur to Upgarde -- 5.540 3.750 Complete 11 205.69 138.15 343.84 32.04 (2 , 1 , 2 , 0 , 5)

Block Hadagali Total 5.540 11 205.69 138.15 343.84 32.04 (2 , 1 , 2 , 0 , 5)

District Bellary Total 5.540 11 205.69 138.15 343.84 32.04 (2 , 1 , 2 , 0 , 5)

District- Bijapur

Block- Bijapur

74 T06 T06- to Kanmuchnal Upgarde -- 13.430 3.750 Complete 33 467.74 327.31 795.05 80.98 (5 , 1 , 0 , 2 , 8) via Harnal Tajpur(H) 75 MRL22 MRL22-Kathijapur to Upgarde -- 5.400 3.750 Complete 11 218.91 153.01 371.92 36.21 (2 , 0 , 0 , 0 , 2) Jumanal Road Block Bijapur Total 18.830 44 686.65 480.32 1,166.97 117.19 (7 , 1 , 0 , 2 , 10) Block- Indi

76 MRL01 MRL01-Masali BK to Tambha Upgarde -- 10.900 3.750 Complete 21 550.51 395.59 946.10 65.79 (4 , 1 , 1 , 0 , 6)

77 T02 T02-Hirebevanur to Padnur Upgarde -- 9.080 3.750 Complete 22 339.31 237.14 576.45 55.31 (5 , 3 , 3 , 0 , 11)

78 MRL07 MRL07-Hirebevanur to Upgarde -- 10.600 3.750 Complete 22 387.69 271.07 658.76 64.23 (2 , 0 , 0 , 0 , 2) Lalsangi 79 MRL06 MRL06-Lingadalli LT1 to Upgarde -- 6.100 3.750 Complete 0 144.82 102.40 247.22 37.78 (2 , 0 , 2 , 0 , 4) 80 MRL10 MRL10-Savalasang to Upgarde StrataWeb/Geo 12.220 3.750 Complete 28 466.06 325.62 791.68 73.67 (3 , 2 , 1 , 2 , 8) Devarnimbaragi cell Block Indi Total 48.900 93 1,888.39 1,331.82 3,220.21 296.78 (16 , 6 , 7 , 2 , 31)

Page 12 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

81 MRL01 MRL01-Tontapur to Alamel Upgarde -- 5.200 3.750 Complete 18 202.43 141.42 343.85 32.10 (2 , 2 , 1 , 0 , 5)

82 MRL04 MRL04-Kerutagi to Kalakeri Upgarde Waste Plastics 5.400 3.750 Complete 7 231.11 169.30 400.41 33.13 (1 , 0 , 0 , 0 , 1)

83 MRL02 MRL02-Kalakeri to Kondaguli Upgarde Waste Plastics 12.370 3.750 Complete 23 494.85 347.36 842.21 74.45 (3 , 2 , 0 , 0 , 5)

84 MRL09 MRL09-Hittanalli to Upgarde -- 5.320 3.750 Complete 7 149.95 105.48 255.43 32.72 (3 , 0 , 0 , 0 , 3) Mulasavalagi 85 MRL10 MRL10-Devarnavadagi to Upgarde -- 4.500 3.750 Complete 4 120.48 84.88 205.36 28.45 (2 , 0 , 0 , 0 , 2) Kumasagi 86 MRL13 MRL13- to Ganihar Upgarde -- 5.100 3.750 Complete 7 179.08 125.42 304.50 31.57 (2 , 0 , 1 , 0 , 3)

87 MRL06 MRL06-Hikkanagutti to Upgarde StrataWeb/Geo 5.900 3.750 Complete 15 217.49 157.72 375.21 36.74 (3 , 0 , 0 , 0 , 3) cell Block Sindagi Total 43.790 81 1,595.39 1,131.58 2,726.97 269.16 (16 , 4 , 2 , 0 , 22) District Bijapur Total 111.520 218 4,170.43 2,943.72 7,114.15 683.13 (39 , 11 , 9 , 4 , 63) District- Chamarajanagar

Block- CR Nagar

88 MRL12 MRL12-Road Junction near Upgarde -- 9.500 3.750 Complete 19 277.21 194.82 472.03 44.66 (7 , 1 , 0 , 0 , 8) Megalahundi To Thammadahalli Via Halepura 89 MRL23 MRL23-Nanjadevanapura to Upgarde -- 6.000 3.750 Complete 11 211.94 152.99 364.93 28.22 (1 , 1 , 0 , 0 , 2) Kalanahundi via Govindavadi (Kalpura) 90 MRL04 MRL04-Junction of Upgarde -- 7.650 3.750 Complete 17 263.23 191.14 454.37 35.99 (5 , 3 , 1 , 1 , 10) Sappainapura and k. mukalli to NH at doddarayapete gate via bhogapura ,Kiragasur Kadahalli

Page 13 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

91 MRL01 MRL01-Santhemarahalli Upgarde Waste Plastics 3.420 3.750 Complete 7 104.99 72.28 177.27 16.09 (6 , 1 , 4 , 0 , 11) MDR Road junction near Heggavadi to SH17 junction at Mariyaladahundi Bus stop 92 MRL19 MRL19-MDR Junction Upgarde -- 5.340 3.750 Complete 14 165.43 113.99 279.42 25.12 (3 , 2 , 1 , 2 , 8) Between Laxmipura and Badagalapura to uganehundi Via Sanegala 93 MRL21 MRL21-Yanagumba to Mdr Upgarde Waste Plastics 4.600 3.750 Complete 7 158.13 108.48 266.61 21.64 (3 , 2 , 0 , 0 , 5) Between Yaraganahalli - Arakalavadi Block CR Nagar Total 36.510 75 1,180.93 833.70 2,014.63 171.72 (25 , 10 , 6 , 3 , 44) Block- Gundlupet

94 MRL03 MRL03-Kamarahalli to Upgarde Waste Plastics 5.005 3.750 Complete 9 172.19 120.09 292.28 23.55 (5 , 0 , 1 , 0 , 6) Halladamadalli 95 MRL01 MRL01-Heggaddahalla To NH Upgarde Waste Plastics 5.780 3.750 Complete 13 217.16 150.13 367.29 27.19 (2 , 1 , 2 , 0 , 5) 212 96 MRL05 MRL05-Shindanapura to Upgarde -- 9.000 3.750 Complete 8 220.78 152.24 373.02 39.98 (4 , 1 , 1 , 0 , 6) Kodasoge (via Mollayanahundi) 97 MRL08 MRL08-SH TO NH Upgarde -- 4.970 3.750 Complete 9 164.32 116.94 281.26 23.38 (2 , 3 , 0 , 0 , 5)

98 MRL19 MRL19-BM Road to Upgarde -- 3.500 3.750 Complete 7 112.61 82.04 194.65 16.46 (4 , 0 , 1 , 0 , 5) Mookahally Block Gundlupet Total 28.255 46 887.06 621.44 1,508.50 130.56 (17 , 5 , 5 , 0 , 27) Block- Kollegala

99 MRL06 MRL06-MM Hills Main Road Upgarde Terrazyme 9.200 3.750 Complete 32 279.77 209.67 489.44 41.51 (3 , 2 , 1 , 0 , 6) to Kothanoor main Road Via
Waste Ikkadalli, Mariyapura Plastics

Page 14 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

100 MRL05 MRL05-Chikkamalapura to Upgarde -- 4.080 3.750 Complete 9 138.23 94.64 232.87 19.19 (2 , 2 , 1 , 0 , 5) Lokkanahally Via Sirgodu 101 MRL03 MRL03-Odeyarapalya to Upgarde -- 9.100 3.750 Complete 16 326.12 225.80 551.92 42.81 (2 , 3 , 2 , 0 , 7) Hunasepalya via Kathekalpadu,Gundimala 102 MRL08 MRL08-Sathegala- Upgarde -- 11.600 3.750 Complete 1 211.18 156.93 368.11 54.57 (1 , 4 , 2 , 3 , 10) Shivanasamudra main road to Shilubepura Block Kollegala Total 33.980 58 955.30 687.03 1,642.33 158.08 (8 , 11 , 6 , 3 , 28) Block-

103 MRL05 MRL05-K.Devarahalli to Upgarde Waste Plastics 7.340 3.750 Complete 10 162.30 113.76 276.06 34.43 (1 , 2 , 0 , 1 , 4) Dasanahundi Block Yelandur Total 7.340 10 162.30 113.76 276.06 34.43 (1 , 2 , 0 , 1 , 4)

District Chamarajanagar Total 106.085 189 3,185.59 2,255.93 5,441.52 494.79 (51 , 28 , 17 , 7 , 103) District- Chickballapur

Block- Bagepalli

104 MRL02 MRL02-Madakavaripalli to Upgarde -- 10.171 3.750 Complete 2 343.47 234.73 578.20 59.44 (2 , 4 , 3 , 6 , 15) Billur 105 T01 T01-Pathapalya to Upgarde Waste Plastics 15.272 3.750 Complete 60 523.58 357.27 880.85 85.72 (4 , 2 , 7 , 8 , 21) Pollanayakanahalli Via Kamsanapalli peddanagurlu Block Bagepalli Total 25.443 62 867.05 592.00 1,459.05 145.16 (6 , 6 , 10 , 14 , 36) Block- Chickballapur

106 MRL06 MRL06-NH-234 To Upgarde -- 6.637 3.750 Complete 25 236.38 161.10 397.48 36.38 (4 , 7 , 2 , 1 , 14) Bannikuppe Via Mannarapura

Page 15 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

107 MRL08 MRL08-Gundlagurki Cross To Upgarde Waste Plastics 9.552 3.750 Complete 13 297.26 203.28 500.54 52.77 (5 , 3 , 6 , 1 , 15) Dibbur Via Akkalathimmanahalli, Devastanahosahalli, Soppahalli, Puradagadde 108 MRL04 MRL04-NH-7 To Kethenahalli Upgarde -- 6.876 3.750 Complete 14 238.00 162.35 400.35 38.26 (0 , 2 , 4 , 6 , 12) MDR Via Kalukunte Ittapanahalli And Mogalaguppe Gollahalli 109 MRL10 MRL10-NH-234 To Upgarde -- 5.782 3.750 Complete 8 203.35 138.61 341.96 31.33 (1 , 4 , 0 , 2 , 7) Kandakkanahalli Via Yennur Kadirenahalli Block Chickballapur Total 28.847 60 974.99 665.34 1,640.33 158.74 (10 , 16 , 12 , 10 , 48) Block- Chinthamani

110 MRL14 MRL14-Kachihalli to Upgarde -- 8.500 3.750 Complete 13 262.96 179.75 442.71 45.95 (2 , 3 , 3 , 2 , 10) Vishwanathapura via Chikkapura Anur 111 MRL06 MRL06-MDR Near Upgarde -- 5.500 3.750 Complete 13 173.63 118.87 292.50 29.63 (1 , 3 , 0 , 0 , 4) Borgamakalahalli To Mylapura Via Bommekallu 112 MRL13 MRL13-Chinnasandra To BC Upgarde Waste Plastics 14.540 3.750 Complete 24 456.18 311.91 768.09 82.34 (2 , 4 , 1 , 1 , 8) Road Via Nayindrahalli Colony Block Chinthamani Total 28.540 50 892.77 610.53 1,503.30 157.92 (5 , 10 , 4 , 3 , 22) Block- Gowribidanur

113 MRL02 MRL02-Alkapura gate To SH- Upgarde -- 4.207 3.750 Complete 15 127.62 87.39 215.01 24.58 (2 , 3 , 7 , 0 , 12) 94 Via Alkapura, Doddahanumenahalli, Bhumenahalli

Page 16 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

114 MRL12 MRL12-Manchenahalli Upgarde -- 13.211 3.750 Complete 39 415.67 284.27 699.94 74.19 (3 , 5 , 0 , 1 , 9) Thondebavi Road To near Beeramangala via Channabyranahalli, Rayarekalahalli, Bajjeranagenahalli, Mavinakayalahalli, Arkunda 115 MRL07 MRL07-SH(Near Upgarde Waste Plastics 8.950 3.750 Complete 25 289.85 198.10 487.95 51.00 (2 , 7 , 2 , 1 , 12) Gollachinnenahalli) To Anegambarayaswamy Temple Via Narasapura Gullaganjihalli Dasarenahalli Block Gowribidanur Total 26.368 79 833.14 569.76 1,402.90 149.77 (7 , 15 , 9 , 2 , 33) Block- Gudibanda

116 T01 T01-MDR to Paragodu via Upgarde Waste Plastics 15.424 3.750 Complete 45 487.24 333.16 820.40 86.99 (5 , 6 , 2 , 5 , 18) Bathalahalli, Dapparthi, Gavikuntahalli, Adinaraganahalli, , Bagepalli Taluk Yandrakayalapalli, Devireddypalli 117 MRL04 MRL04-From NH to B.B.Road Upgarde -- 9.668 3.750 Complete 48 305.38 208.91 514.29 55.89 (3 , 3 , 4 , 4 , 14) via Yarralakkenahalli, Bhogenahalli, Thirumani, Katenahalli, Mittemari Road Block Gudibanda Total 25.092 93 792.62 542.07 1,334.69 142.88 (8 , 9 , 6 , 9 , 32) Block-

118 MRL01 MRL01- Taluk border Upgarde -- 5.500 3.750 Complete 13 171.75 117.32 289.07 27.34 (2 , 0 , 2 , 0 , 4) (Ibasapura) to KG Road via Sugaturu, , J.Kurabarahalli

Page 17 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

119 MRL05 MRL05-Ganjikunte SH to Upgarde -- 6.000 3.750 Complete 15 183.94 126.06 310.00 32.95 (1 , 0 , 3 , 4 , 8) Pollakuntahalli (MDR) via Doddabadragatta, Chikkabandragatta, Hakkipikki Calony, Poolakuntla halli. 120 MRL08 MRL08-Korlaparthi to Upgarde Waste Plastics 12.000 3.750 Complete 13 367.00 251.78 618.78 69.30 (1 , 2 , 5 , 2 , 10) T.Venkatapura via Kommasandra, Kariyappanahalli Block Sidlaghatta Total 23.500 41 722.69 495.16 1,217.85 129.59 (4 , 2 , 10 , 6 , 22) District Chickballapur Total 157.790 385 5,083.26 3,474.86 8,558.12 884.06 (40 , 58 , 51 , 44 , 193) District- Chickmagalur

Block- Chickmagalur

121 MRL07 MRL07-Bypass NH to B T Upgarde -- 5.490 3.750 Complete 19 221.44 182.83 404.27 33.02 (3 , 2 , 2 , 2 , 9) road Malledevarahalli MDR via Nettekerehalli 122 T05 T05-Hiremagalur to Belur Upgarde -- 3.480 3.750 Complete 14 152.12 126.27 278.39 18.43 (1 , 2 , 1 , 3 , 7) Taluk border 123 MRL20 MRL20-Amble to Thiruguna Upgarde Waste Plastics 10.970 3.750 Complete 30 487.03 356.81 843.84 62.73 (1 , 3 , 2 , 6 , 12) via Kadrimidri 124 MRL25 MRL25-Hukkunda to K M Upgarde -- 7.520 3.750 Complete 29 340.83 244.02 584.85 42.65 (3 , 1 , 4 , 2 , 10) road via Yarehalli Block Chickmagalur Total 27.460 92 1,201.42 909.93 2,111.35 156.83 (8 , 8 , 9 , 13 , 38) Block- Kadur

125 MRL01 MRL01-Singatagere To Upgarde -- 7.600 3.750 Complete 25 206.42 160.03 366.45 37.53 (3 , 0 , 1 , 7 , 11) Keresanthe

Page 18 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

126 MRL16 MRL16-Channapura Upgarde -- 8.600 3.750 Complete 27 349.30 260.82 610.12 42.47 (2 , 1 , 4 , 3 , 10) Giribommanahalli MDR to Sokke Peelapura SH via Hadagalu 127 MRL03 MRL03- to NH-206 Upgarde -- 6.300 3.750 Complete 50 213.13 150.87 364.00 31.12 (1 , 1 , 0 , 5 , 7) via Lakshmisagara 128 T04 T04- taluk border to Upgarde -- 12.000 3.750 Complete 37 357.22 265.15 622.37 59.21 (5 , 0 , 1 , 1 , 7) via Asandi Block Kadur Total 34.500 139 1,126.07 836.87 1,962.94 170.33 (11 , 2 , 6 , 16 , 35) Block-

129 MRL33 MRL33- to Nooji via Upgarde -- 11.225 3.750 Complete 39 496.85 364.85 861.70 55.78 (2 , 1 , 4 , 13 , SK Megal 20) 130 MRL20 MRL20-Bettadamane Upgarde -- 9.700 3.750 Complete 34 380.40 281.28 661.68 53.36 (0 , 2 , 4 , 11 , Devarunda road MDR to 17) Kirugunda via Kajjehalli 131 MRL34 MRL34-Bankenahalli to Upgarde -- 8.600 3.750 Complete 35 360.32 263.29 623.61 47.29 (1 , 1 , 1 , 1 , 4) Phalguni via Kudihalli and Yerkal Block Mudigere Total 29.525 108 1,237.57 909.42 2,146.99 156.43 (3 , 4 , 9 , 25 , 41) Block-

132 MRL11 MRL11-Chinnakudige to Upgarde -- 5.500 3.750 Complete 14 215.21 151.36 366.57 31.94 (0 , 1 , 0 , 22 , Bangavani - Vagade Via 23) Bettagere Kelakoppa 133 MRL19 MRL19-Bangavani to Upgarde -- 6.300 3.750 Complete 15 193.94 137.05 330.99 31.06 (0 , 1 , 3 , 10 , Kudregundi - Chikkagrahara 14) Via Kasana Gundvani road

Page 19 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

134 T05 T05-BH Kaimara to Upgarde -- 14.480 3.750 Complete 25 166.18 119.48 285.66 84.77 (0 , 0 , 2 , 32 , Nagaramakki Via Edagere 34) Hallibailu Gubbiga Kuguvally Block Narasimharajapura Total 26.280 54 575.33 407.89 983.22 147.77 (0 , 2 , 5 , 64 , 71) Block-

135 MRL23 MRL23-SH Meegina Kallu To Upgarde -- 8.710 3.750 Complete 24 416.15 298.87 715.02 55.60 (0 , 0 , 2 , 20 , Devalekoppa via Heggadde, 22) Hosakoppa, Magalabailu, Hadlukopp Block Sringeri Total 8.710 24 416.15 298.87 715.02 55.60 (0 , 0 , 2 , 20 , 22) Block- Tarikere

136 MRL12 MRL12-Kortikere to Upgarde -- 10.890 3.750 Complete 19 405.23 303.87 709.10 59.49 (4 , 3 , 4 , 1 , 12) Rangapura road Via Sokke Shanuboganahalli Kudlur 137 MRL06 MRL06-Gulladamane to Upgarde Cold Mix 7.920 3.750 Complete 15 314.57 234.85 549.42 44.01 (3 , 6 , 3 , 4 , 16) Tarikere - road Technology Via 138 MRL08 MRL08- Belenahally to Upgarde -- 5.710 3.750 Complete 10 238.60 183.80 422.40 31.39 (2 , 4 , 1 , 1 , 8) Siddarahalli Via Jodikodihalli Duggalapura Seethapura kaval 139 MRL07 MRL07-Shivani RS to Upgarde Cement 6.570 3.750 Complete 5 339.69 241.26 580.95 30.05 (5 , 1 , 1 , 0 , 7) Bukkambudi - Shivani Road Stabilization 140 MRL19 MRL19-Hosalli Tandya to Upgarde -- 11.070 3.750 Complete 16 367.27 269.58 636.85 61.72 (0 , 2 , 2 , 1 , 5) Ajjampura - Bu Block Tarikere Total 42.160 65 1,665.36 1,233.36 2,898.72 226.66 (14 , 16 , 11 , 7 , 48)

Page 20 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Chickmagalur Total 168.635 482 6,221.90 4,596.34 10,818.24 913.62 (36 , 32 , 42 , 145 , 255) District- Chitradurga

Block-

141 MRL18 MRL18-Somaguddu to Upgarde Waste Plastics 10.600 3.750 Complete 29 466.88 315.02 781.90 54.88 (4 , 4 , 0 , 2 , 10) Budnahatti via Imampura, Gorlakatte, Veeradimmanahalli, Budnahatti Lambanihatti 142 MRL19 MRL19-Maradihatti to Andra Upgarde Waste Plastics 5.230 3.750 Complete 20 269.35 183.63 452.98 27.08 (2 , 0 , 0 , 2 , 4) border via Kyadigunte, Siddeshwaranadurga, Siddeshwaranadurga gollarahatti 143 MRL26 MRL26-Siddapura to Upgarde -- 3.210 3.750 Complete 6 148.12 100.99 249.11 16.61 (4 , 0 , 0 , 0 , 4) Somaguddu via Laxmipura Block Challakere Total 19.040 55 884.35 599.64 1,483.99 98.57 (10 , 4 , 0 , 4 , 18) Block-

144 MRL11 MRL11-NH-4 to Beerenahalli Upgarde -- 13.150 3.750 Complete 3 246.20 167.42 413.62 68.08 (4 , 1 , 0 , 1 , 6) via Yaradakatte, Metikurke, Sooragondanahalli, Tavandi, Katanahatti Block Hiriyur Total 13.150 3 246.20 167.42 413.62 68.08 (4 , 1 , 0 , 1 , 6)

Block- Holalkere

145 MRL17 MRL17-Andanur Gollarahatti Upgarde Terrazyme 6.250 3.750 Complete 8 206.14 140.70 346.84 32.35 (7 , 2 , 2 , 1 , 12) to Ganjigatte Lambanihatti via Andanur, Ingaladahalli, Bandebommenahalli, B.B. Halli Vaddarhatty, Ganjigatte

Page 21 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

146 MRL25 MRL25-Shivaganga to Upgarde Waste Plastics 3.850 3.750 Complete 11 138.20 94.24 232.44 19.93 (3 , 2 , 1 , 0 , 6) Thodaranahal via Chitrahalli 147 MRL20 MRL20-Talya to NH-13 Upgarde -- 5.820 3.750 Complete 10 196.96 134.39 331.35 30.13 (2 , 2 , 1 , 1 , 6) (Kudineerakatte) via Sirapanahalli, Hunasepanche, Sihineerakatte, Kudineerakatte Block Holalkere Total 15.920 29 541.30 369.33 910.63 82.41 (12 , 6 , 4 , 2 , 24) Block-

148 MRL29 MRL29-Ahamad Nagara to Upgarde Waste Plastics 6.350 3.750 Complete 9 265.28 181.09 446.37 32.87 (0 , 2 , 0 , 1 , 3) vai Adrikatte, Marabhagatta 149 MRL20 MRL20-Jankal- Upgarde Waste Plastics 4.500 3.750 Complete 11 183.74 125.43 309.17 23.29 (2 , 2 , 2 , 0 , 6) Akkithimmaiahnahatty (MDR) to Sodarnal via Devapura, Honnenahalli, Hunavinadu Block Hosadurga Total 10.850 20 449.02 306.52 755.54 56.16 (2 , 4 , 2 , 1 , 9)

Block- Molakalmur

150 MRL05 MRL05-Tumkurlahalli to Upgarde -- 4.850 3.750 Complete 9 167.39 114.20 281.59 25.10 (2 , 0 , 0 , 0 , 2) via Marammanahalli 151 MRL11 MRL11-Chikumthi to Upgarde -- 5.820 3.750 Complete 12 190.81 128.67 319.48 30.12 (1 , 1 , 0 , 0 , 2) Yarapothajogihalli via Tumakurlahalli Block Molakalmur Total 10.670 21 358.20 242.87 601.07 55.22 (3 , 1 , 0 , 0 , 4)

District Chitradurga Total 69.630 128 2,479.07 1,685.78 4,164.85 360.44 (31 , 16 , 6 , 8 , 61)

Page 22 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District-

Block- Bantwal

152 MRL05 MRL05-Kanyana to Upgarde -- 6.130 3.750 Complete 42 328.72 240.93 569.65 35.91 (0 , 3 , 6 , 2 , 11) Nekkarekadu ST Colony 153 MRL01 MRL01-Golthamajalu to Upgarde -- 11.160 5.500 Complete 60 726.94 521.39 1,248.33 68.45 (5 , 5 , 7 , 2 , 19) Manchikatte Road (SH) 154 MRL03 MRL03-Ira Thalithabettu To Upgarde Cold Mix 6.825 3.750 Complete 40 340.47 249.25 589.72 39.98 (1 , 2 , 1 , 2 , 6) Cheluru Technology 155 MRL02 MRL02-Bolpade to Madara Upgarde Waste Plastics 9.620 3.750 Complete 51 430.37 345.67 776.04 49.05 (0 , 1 , 4 , 1 , 6) mule Block Bantwal Total 33.735 193 1,826.50 1,357.24 3,183.74 193.40 (6 , 11 , 18 , 7 , 42) Block- Belthangadi

156 MRL10 MRL10-Parappu to Adrupral Upgarde -- 5.050 3.750 Complete 26 247.34 180.46 427.80 30.93 (1 , 0 , 1 , 7 , 9) Road 157 MRL07 MRL07-MDR Bejadaddi to Upgarde Cold Mix 10.465 3.750 Complete 49 502.26 361.70 863.96 64.08 (0 , 4 , 3 , 7 , 14) Parpikallu Technology 158 MRL03 MRL03- Laila to Kotikatte Upgarde Waste Plastics 7.450 3.750 Complete 42 377.99 275.93 653.92 45.62 (0 , 3 , 1 , 8 , 12) Road 159 T02 T02- Ujire - Kuppetti Road Upgarde -- 24.750 5.500 Complete 102 1,296.83 955.66 2,252.49 163.76 (0 , 1 , 4 , 8 , 13)

Block Belthangadi Total 47.715 219 2,424.42 1,773.75 4,198.17 304.39 (1 , 8 , 9 , 30 , 48) Block-

160 MRL17 MRL17-Munchigudde to Upgarde -- 5.400 3.750 Complete 24 286.15 208.77 494.92 27.61 (0 , 0 , 2 , 5 , 7) Niddodi Road Block Mangalore Total 5.400 24 286.15 208.77 494.92 27.61 (0 , 0 , 2 , 5 , 7)

Page 23 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Puttur

161 MRL04 MRL04-BAREPADY- Upgarde -- 6.520 3.750 Complete 30 252.55 176.24 428.79 40.64 (1 , 1 , 1 , 1 , 4) PALLATHARU-KUNKYA (PERUVAJE) 162 MRL18 MRL18-KAKKUR-ANADKA- Upgarde -- 7.190 3.750 Complete 45 355.37 261.31 616.68 44.04 (0 , 0 , 2 , 15 , KARNAPADY 17) Block Puttur Total 13.710 75 607.92 437.55 1,045.47 84.68 (1 , 1 , 3 , 16 , 21) Block- Sulya

163 MRL18 MRL18-PERAL-AJJAVRA- Upgarde -- 6.750 3.750 Complete 40 325.31 230.11 555.42 43.13 (2 , 3 , 6 , 3 , 14) NARKODU Block Sulya Total 6.750 40 325.31 230.11 555.42 43.13 (2 , 3 , 6 , 3 , 14) District Dakshina Kannada Total 107.310 551 5,470.30 4,007.41 9,477.71 653.21 (10 , 23 , 38 , 61 , 132) District- Davanagere

Block- Chennagiri

164 T05 T05-SH near Chikkulikere to Upgarde Terrazyme 4.315 3.750 Complete 12 146.25 106.94 253.19 16.51 (2 , 2 , 0 , 0 , 4) MDR near Gulihalli via
Waste Ajjihalli, Mudigere, Plastics Thimalapura 165 T01 T01-SH near Honnebagi to Upgarde -- 3.864 3.750 Complete 17 156.43 108.11 264.54 18.51 (2 , 1 , 0 , 0 , 3) Joldhal via Gandhinagara, Malligere, Hanumanthanagara, Shivajinagara, Hosahalli

Page 24 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

166 T03 T03-MDR near Upgarde Terrazyme 12.260 3.750 Complete 43 414.95 300.42 715.37 52.83 (3 , 0 , 2 , 0 , 5) Agarbannihatti to MDR near Kondadahalli via Hosabannihatti, Bulsagara, Kagathur, Ramagondanahalli Block Chennagiri Total 20.439 72 717.63 515.47 1,233.10 87.85 (7 , 3 , 2 , 0 , 12) Block- Davanagere

167 T18 T18- to Kandgal Upgarde Terrazyme 22.620 3.750 Complete 41 819.99 546.66 1,366.65 121.90 (16 , 7 , 5 , 5 , via ,kalur attigere
Waste 33) and Plastics gopnal,kashipura,mallakere 168 T17 T17-Turchagatta to Upgarde Waste Plastics 7.300 3.750 Complete 5 274.02 182.68 456.70 39.34 (9 , 9 , 0 , 3 , 21) Anagodu via Chandrnahalli,Kurki, Bullapura Block Davanagere Total 29.920 46 1,094.01 729.34 1,823.35 161.24 (25 , 16 , 5 , 8 , 54) Block- Harapanahalli

169 T12 T12-Chirastahalli to Ittigudi Upgarde Terrazyme 10.300 3.750 Complete 29 458.21 305.48 763.69 53.06 (7 , 1 , 2 , 2 , 12) Via G Dadapura ,Alagilwada
Waste Plastics 170 T04 T04-H H Road to H H road Upgarde Terrazyme 17.820 3.750 Complete 24 640.12 426.75 1,066.87 91.81 (8 , 2 , 7 , 3 , 20) Via
Waste Gowrihalli,Almarasikere,Ma Plastics dalgere.Kerekanahallithand a,Kannayakanahalli Block Harapanahalli Total 28.120 53 1,098.33 732.23 1,830.56 144.87 (15 , 3 , 9 , 5 , 32)

Page 25 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Harihara

171 T09 T09-SH-25 to NH 4 via Upgarde Terrazyme 13.552 3.750 Complete 42 501.16 367.78 868.94 65.25 (10 , 3 , 0 , 2 , Mahajenahally,Hanagavadi,B
Waste 15) elludi,Bannikodu,Satyanaray Plastics ana camp,Hale kundwada 172 T01 T01-MDR(Govinahole) to Upgarde -- 12.935 3.750 Complete 25 433.85 323.71 757.56 64.61 (2 , 0 , 1 , 0 , 3) SH25( shimoga Road) Via G T Katte, Kokkanur camp Vaderabasapura camp,Dibbadahalli,Komaran ahalli,Chikkamukthenahalli, Koppa Block Harihara Total 26.487 67 935.01 691.49 1,626.50 129.86 (12 , 3 , 1 , 2 , 18) Block-

173 T04 T04-KK Road to Upgarde Terrazyme 9.045 3.750 Complete 57 347.63 242.98 590.61 44.52 (2 , 0 , 2 , 0 , 4) Kanchugaranahalli via
Waste Mavinakote,Hanumanahalli, Plastics Channenahalli 174 T07 T07-Haralahalli to Upgarde Terrazyme 11.650 3.750 Complete 25 430.05 294.35 724.40 58.19 (4 , 0 , 2 , 0 , 6) Nelahonne Thanda via
Waste Bannikodu,Kulambi,Yarehall Plastics i,Kundur,Nelahonne Andhra Camp,Nelahonne 175 T02 T02- to Upgarde -- 5.675 3.750 Complete 8 206.78 150.94 357.72 27.94 (3 , 2 , 1 , 1 , 7) Mussenahal via Kudrekonda,salabalu,ganjin ahalli,Chatnihalli,Yeramada camp

Page 26 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

176 T03 T03-Hirematha to Upgarde -- 7.438 3.750 Complete 19 255.77 186.66 442.43 36.56 (3 , 1 , 0 , 0 , 4) Holemadapura via Malldevarakatte ,Sunkadakatte,diddaguru,Bi daragadde Block Honnali Total 33.808 109 1,240.23 874.93 2,115.16 167.21 (12 , 3 , 5 , 1 , 21) Block- Jagalur

177 MRL06 MRL06-Kasturipura to Upgarde Terrazyme 10.780 3.750 Complete 25 400.75 267.16 667.91 55.34 (7 , 10 , 3 , 1 , Petekanakuppr-
Waste 21) chikkamanahatti road via Plastics kasturipura, Bullane halli ,Rasthemachikere , Giddanakatte,Kanakuppe 178 T20 T20-Rangapura to Upgarde Terrazyme 11.670 3.750 Complete 9 444.74 296.50 741.24 55.94 (7 , 9 , 3 , 2 , 21) Donnehalli via Hanumantha
Waste pura Plastics ,Goguddu,Hosakannakatte,K annakatte,Bangarakkanagud da,Siddamanahalli,Hosahatt i, 179 T10 T10-Asagodu to Gode via Upgarde Terrazyme 5.640 3.750 Complete 11 264.01 176.00 440.01 28.85 (5 , 3 , 3 , 1 , 12) A.Vadarahatti,Diddigi,Urlak
Waste atte,Tarehalli Plastics Block Jagalur Total 28.090 45 1,109.50 739.66 1,849.16 140.13 (19 , 22 , 9 , 4 , 54) District Davanagere Total 166.864 392 6,194.71 4,283.12 10,477.83 831.15 (90 , 50 , 31 , 20 , 191) District- Dharwad

Page 27 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Dharwad

180 MRL02 MRL02-Mangudi to via Upgarde Terrazyme 5.660 3.750 Complete 20 287.07 200.90 487.97 32.72 (6 , 0 , 0 , 0 , 6) Benkanakatti 181 MRL04 MRL04-NH Near to Upgarde -- 12.540 3.750 Complete 33 553.37 387.27 940.64 77.22 (12 , 1 , 2 , 1 , MDR Tadkod- via 16) Belur--- -Dubbanamaradi Block Dharwad Total 18.200 53 840.44 588.17 1,428.61 109.94 (18 , 1 , 2 , 1 , 22) Block-

182 MRL01 MRL01- to Upgarde -- 4.750 3.750 Complete 8 203.92 136.68 340.60 27.70 (2 , 0 , 0 , 0 , 2) kundagol taluk border via Noolvi 183 MRL07 MRL07-NH near Varur to NH- Upgarde -- 7.620 3.750 Complete 12 356.19 238.69 594.88 44.83 (2 , 1 , 0 , 0 , 3) 4 near Agadi via Aralikatti Block Hubli Total 12.370 20 560.11 375.37 935.48 72.53 (4 , 1 , 0 , 0 , 5)

Block- Kalghatgi

184 MRL03 MRL03-Kuruvinakoppa to Upgarde Waste Plastics 5.550 3.750 Complete 10 209.35 146.50 355.85 32.52 (3 , 0 , 0 , 0 , 3) MDR near 185 MRL20 MRL20-Shivanapur to Upgarde -- 10.680 3.750 Complete 22 407.47 284.75 692.22 63.75 (7 , 4 , 1 , 0 , 12) Nelliharvi via Mukkal Aralihonda 186 MRL19 MRL19-Dhulikoppa to Upgarde -- 4.970 3.750 Complete 6 202.37 141.63 344.00 28.75 (2 , 1 , 1 , 0 , 4) -Hesarambi MDR 187 MRL21 MRL21- to Upgarde -- 4.200 3.750 Complete 11 170.36 128.18 298.54 25.42 (1 , 2 , 4 , 0 , 7) Sachhidanandanagar via Suilkatti and Maslikatti Block Kalghatgi Total 25.400 49 989.55 701.06 1,690.61 150.44 (13 , 7 , 6 , 0 , 26)

Page 28 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Navalgund

188 MRL03 MRL03- to Upgarde Waste Plastics 21.900 3.750 Complete 41 905.14 633.41 1,538.55 127.03 (5 , 0 , 0 , 0 , 5) via Block Navalgund Total 21.900 41 905.14 633.41 1,538.55 127.03 (5 , 0 , 0 , 0 , 5)

District Dharwad Total 77.870 163 3,295.24 2,298.01 5,593.25 459.94 (40 , 9 , 8 , 1 , 58) District- Gadag

Block- Gadag

189 MRL11 MRL11-Mulagund to Upgarde -- 5.330 3.750 Complete 15 188.35 131.82 320.17 31.91 (3 , 0 , 0 , 0 , 3) Kurthkoti 190 MRL31 MRL31-Kurtakotti to Antur- Upgarde -- 6.730 3.750 Complete 25 206.48 144.49 350.97 40.31 (2 , 0 , 0 , 0 , 2) Bentur Block Gadag Total 12.060 40 394.83 276.31 671.14 72.22 (5 , 0 , 0 , 0 , 5)

Block-

191 MRL11 MRL11-Konchigeri to Upgarde -- 7.160 3.750 Complete 34 290.32 203.17 493.49 41.86 (2 , 0 , 0 , 0 , 2) via Budhihal 192 MRL10 MRL10-Doddur thanda to Upgarde -- 9.180 3.750 Complete 26 304.33 212.97 517.30 53.01 (4 , 0 , 0 , 0 , 4) MDR via Suvarnagiri and suranagi Block Shirhatti Total 16.340 60 594.65 416.14 1,010.79 94.87 (6 , 0 , 0 , 0 , 6)

District Gadag Total 28.400 100 989.48 692.45 1,681.93 167.09 (11 , 0 , 0 , 0 , 11) District- Gulbarga

Page 29 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Afzalpur

193 MRL01 MRL01-Afzalpur to Upgarde Waste Plastics 6.130 3.750 Complete 4 239.91 164.79 404.70 33.92 (5 , 2 , 2 , 0 , 9) Bandarwad Via Anoor Devalghangapur 194 MRL21 MRL21- B to Kadani Upgarde -- 9.220 3.750 Complete 13 374.66 257.32 631.98 54.32 (3 , 1 , 1 , 0 , 5) Via Hawanoor 195 MRL12 MRL12- B to Athnoor Upgarde -- 5.000 3.750 Complete 8 197.25 135.50 332.75 29.22 (3 , 0 , 0 , 0 , 3)

196 MRL19 MRL19-Diksanga K to Karajgi Upgarde -- 8.035 3.750 Complete 9 295.00 202.66 497.66 47.17 (3 , 0 , 0 , 1 , 4) Via Karajgi Tanda Block Afzalpur Total 28.385 34 1,106.82 760.27 1,867.09 164.63 (14 , 3 , 3 , 1 , 21) Block- Aland

197 MRL09 MRL09-Dhangapur to Upgarde -- 5.010 5.500 Complete 13 331.41 224.34 555.75 29.49 (4 , 0 , 0 , 0 , 4) Nimbarga via Battarga 198 MRL01 MRL01-Kinnisultan To Upgarde Waste Plastics 4.703 3.750 Complete 3 194.75 131.22 325.97 23.24 (3 , 0 , 0 , 0 , 3)

199 MRL22 MRL22-Ladchincholi to Upgarde -- 7.890 3.750 Complete 8 268.06 180.58 448.64 45.81 (2 , 1 , 1 , 0 , 4) Dharmwadi via kadganchi 200 MRL06 MRL06-Tadkal to Jambga (R) Upgarde -- 5.860 3.750 Complete 10 210.87 142.85 353.72 34.52 (2 , 0 , 0 , 0 , 2)

201 MRL04 MRL04-Sunthnoor cross to Upgarde -- 8.606 3.750 Complete 4 251.93 170.85 422.78 50.70 (2 , 0 , 0 , 1 , 3) nimbarga via suntnoor dharmwadi basawanthwadi nibarga tanda Block Aland Total 32.069 38 1,257.02 849.84 2,106.86 183.77 (13 , 1 , 1 , 1 , 16) Block-

202 MRL17 MRL17-Chandankera (SH125) Upgarde Waste Plastics 12.780 5.500 Complete 16 732.34 498.95 1,231.29 66.11 (3 , 7 , 6 , 6 , 22) to Ainapur (SH75) via kotga khanapoor

Page 30 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

203 MRL16 MRL16-Seri cross to tq Upgarde -- 6.820 3.750 Complete 16 311.11 212.00 523.11 35.27 (1 , 3 , 3 , 7 , 14) border via Junglipeer tanda cross Gundappa Gudi Tanda 204 MRL09 MRL09-Ainapur to Upgarde -- 5.790 3.750 Complete 32 290.88 197.92 488.80 29.95 (3 , 0 , 2 , 2 , 7) Chiimmanchod tanda cross Via Benkepalli Block Chincholi Total 25.390 64 1,334.33 908.87 2,243.20 131.33 (7 , 10 , 11 , 15 , 43) Block- Gulbarga

205 MRL23 MRL23-Antapnal to Jevanagi Upgarde -- 5.488 3.750 Complete 5 162.14 111.10 273.24 26.01 (3 , 2 , 1 , 0 , 6) via Bhunyar 206 MRL13 MRL13-Kadani Cross to Upgarde -- 6.227 3.750 Complete 7 229.71 155.02 384.73 36.28 (3 , 0 , 1 , 0 , 4) Kawalga B Via Kadani, Minijagi 207 MRL17 MRL17-Astaga Cross to Upgarde -- 6.281 3.750 Complete 5 260.22 178.90 439.12 34.82 (4 , 0 , 0 , 0 , 4) Via Bhimalli 208 MRL30 MRL30-Kamalapur to Limbu Upgarde Waste Plastics 10.568 3.750 Complete 5 279.06 191.47 470.53 61.55 (3 , 0 , 2 , 0 , 5) Tanda via Monu Naik Tanda Dinsi K tanda,Dinsi k Block Gulbarga Total 28.564 22 931.13 636.49 1,567.62 158.67 (13 , 2 , 4 , 0 , 19) Block- Jewargi

209 MRL23 MRL23-Kallur K to Balwandgi Upgarde -- 5.145 3.750 Complete 16 168.97 116.14 285.11 30.63 (4 , 0 , 0 , 0 , 4)

210 MRL06 MRL06-Hipparaga SN to Upgarde -- 5.600 3.750 Complete 16 183.46 126.11 309.57 31.73 (2 , 2 , 0 , 0 , 4) Mandewal Cross 211 MRL10 MRL10-Kurnalli to Mayoor Upgarde -- 4.770 3.750 Complete 4 145.75 100.23 245.98 27.69 (1 , 0 , 0 , 0 , 1) Via Mandewal 212 MRL11 MRL11-Ranjanagi to MDR Via Upgarde Waste Plastics 8.505 3.750 Complete 8 282.77 194.37 477.14 48.20 (5 , 1 , 2 , 0 , 8) Halgattaragi

Page 31 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

213 MRL12 MRL12-Harnur to Upgarde -- 6.100 3.750 Complete 16 195.82 133.69 329.51 34.57 (2 , 0 , 0 , 0 , 2)

214 MRL21 MRL21-Yalwar to Satkhed Upgarde -- 5.785 3.750 Complete 16 179.68 122.43 302.11 34.35 (4 , 0 , 1 , 0 , 5) via somnathhalli Block Jewargi Total 35.905 76 1,156.45 792.97 1,949.42 207.18 (18 , 3 , 3 , 0 , 24) Block-

215 MRL09 MRL09-SH 122 to Upgarde Waste Plastics 5.910 3.750 Complete 15 232.58 158.48 391.06 34.20 (3 , 2 , 1 , 0 , 6) Chittkanpalli Via Munkampalli 216 MRL19 MRL19-Gundahalli To Upgarde -- 6.270 3.750 Complete 12 221.17 150.71 371.88 36.33 (1 , 3 , 1 , 0 , 5) Main Road (SH 15) Via Mushtahalli 217 MRL20 MRL20- To SH 122 Near Upgarde -- 7.775 3.750 Complete 15 311.38 212.18 523.56 45.02 (3 , 1 , 0 , 0 , 4) Ranjol Via Imdapur Block Sedam Total 19.955 42 765.13 521.37 1,286.50 115.54 (7 , 6 , 2 , 0 , 15) District Gulbarga Total 170.268 276 6,550.88 4,469.80 11,020.68 961.11 (72 , 25 , 24 , 17 , 138) District- Hassan

Block-

218 T12 T12-B.M road to A.B Road Upgarde Waste Plastics 3.900 3.750 Complete 11 171.89 124.92 296.81 22.03 (2 , 2 , 4 , 11 , via Bellur, Murdur, 19) 219 T10 T10-Kudidale to Kadlur Upgarde -- 9.800 3.750 Complete 11 477.08 351.69 828.77 57.34 (4 , 0 , 4 , 7 , 15) Koodige 220 MRL17 MRL17-Alur Biccodu Road Upgarde -- 6.100 3.750 Complete 16 294.66 213.61 508.27 34.34 (1 , 1 , 2 , 13 , via Chikkanagalu to join 17) C.Hosahalli

Page 32 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

221 MRL09 MRL09- to NH-75 via Upgarde Coir 5.810 3.750 Complete 12 266.59 195.77 462.36 33.07 (0 , 1 , 3 , 5 , 9) Nidanur, J.Honnavally Technology Block Alur Total 25.610 50 1,210.22 885.99 2,096.21 146.78 (7 , 4 , 13 , 36 , 60) Block- Arakalgud

222 MRL01 MRL01- Devrahalli to Upgarde Waste Plastics 4.230 3.750 Complete 8 177.02 134.82 311.84 24.06 (1 , 7 , 4 , 2 , 14) Ganganalu via Hullangala 223 MRL16 MRL16-Kollangi to Upgarde Coir 6.610 3.750 Complete 14 305.29 224.08 529.37 37.40 (2 , 4 , 3 , 4 , 13) Chowragalli via Masavathuru Technology 224 MRL19 MRL19-Shambhunathapura Upgarde -- 5.630 3.750 Complete 13 264.86 193.30 458.16 30.44 (2 , 6 , 5 , 4 , 17) to Cholenahalli Via Chowdenahalli, Ankanayakanahalli, 225 MRL20 MRL20-Konapura to SH-8 Upgarde -- 3.000 3.750 Complete 9 144.31 109.50 253.81 16.09 (1 , 2 , 4 , 9 , 16) (CNS road) via Mudigere Block Arakalgud Total 19.470 44 891.48 661.70 1,553.18 107.99 (6 , 19 , 16 , 19 , 60) Block- Arasikere

226 MRL20 MRL20-Kolagunda to Upgarde -- 4.160 3.750 Complete 7 133.43 100.87 234.30 22.30 (2 , 3 , 1 , 2 , 8) Melinahosahalli 227 T04 T04-Jenukal siddapura to Upgarde -- 7.935 3.750 Complete 22 307.78 220.53 528.31 43.56 (1 , 1 , 2 , 10 , MDR near via 14) Bevinahalli 228 MRL05 MRL05-MDR near Upgarde Waste Plastics 4.050 3.750 Complete 8 146.98 118.06 265.04 21.82 (2 , 4 , 3 , 11 , Thondiganahalli to MDR 20) near via Shanegere Thippaghatta Block Arasikere Total 16.145 37 588.19 439.46 1,027.65 87.68 (5 , 8 , 6 , 23 , 42)

Page 33 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Belur

229 MRL01 MRL01-Venkatipete to join Upgarde Cold Mix 8.275 3.750 Complete 9 284.95 199.21 484.16 50.66 (1 , 2 , 7 , 19 , Dolanamane Via Technology 29) Arehallii,Heggadihalli 230 T01 T01-Mathgighatta to Upgarde -- 5.100 3.750 Complete 5 190.91 135.22 326.13 31.10 (1 , 4 , 1 , 9 , 15) Hirihalli Via Suranayakanahalli Block Belur Total 13.375 14 475.86 334.43 810.29 81.76 (2 , 6 , 8 , 28 , 44) Block-

231 MRL08 MRL08-Anathi to Thimlapura Upgarde -- 5.590 3.750 Complete 8 136.41 98.16 234.57 31.30 (4 , 5 , 2 , 3 , 14) vai- B.Byrapura 232 MRL04 MRL04-Sorehalli to Bekka Upgarde Terrazyme 5.590 3.750 Complete 15 267.76 187.28 455.04 29.35 (3 , 3 , 2 , 3 , 11) via- Parama, B.Honnenahalli , Shivapura Block Channarayapatna Total 11.180 23 404.17 285.44 689.61 60.65 (7 , 8 , 4 , 6 , 25) Block- Hassan

233 MRL02 MRL02-B T Koppalu to Upgarde White Topping 5.300 3.750 Complete 11 265.76 190.98 456.74 29.02 (7 , 4 , 2 , 3 , 16) Salagame road via Yadiyur 234 MRL01 MRL01-Gyarahalli to Upgarde -- 5.220 3.750 Complete 12 253.04 183.37 436.41 28.60 (0 , 4 , 3 , 7 , 14) Hachagondanahalli via Tejur 235 MRL14 MRL14-HN Pura TQ Border Upgarde Waste Plastics 4.000 3.750 Complete 13 196.42 144.28 340.70 21.89 (2 , 4 , 4 , 5 , 15) To Markuli Road Jn (Via Muthige , ) 236 MRL34 MRL34-MDR to MDR via Upgarde -- 7.100 3.750 Complete 13 295.11 217.89 513.00 39.90 (1 , 2 , 3 , 7 , 13) Hosur, , Bellikopplu, Mallanayakanahalli, Bandihalli

Page 34 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

237 MRL37 MRL37-SH near Hoovinahalli Upgarde Coir 5.910 3.750 Complete 9 216.88 160.11 376.99 32.67 (2 , 4 , 3 , 1 , 10) to Kuppalli via Haralahalli Technology
Waste Plastics
White Topping Block Hassan Total 27.530 58 1,227.21 896.63 2,123.84 152.08 (12 , 18 , 15 , 23 , 68) Block- Sakaleshpur

238 MRL18 MRL18-Hebbasale to Donigal Upgarde -- 3.150 3.750 Complete 7 190.91 139.22 330.13 18.41 (2 , 0 , 0 , 4 , 6) (NH) via H colony, Adangudda, Devihalli Block Sakaleshpur Total 3.150 7 190.91 139.22 330.13 18.41 (2 , 0 , 0 , 4 , 6)

District Hassan Total 116.460 233 4,988.04 3,642.87 8,630.91 655.35 (41 , 63 , 62 , 139 , 305) District- Haveri

Block- Byadgi

239 MRL04 MRL04-Sudambi to join MDR Upgarde None 8.710 3.750 Complete 31 445.24 314.04 759.28 50.97 (5 , 1 , 1 , 0 , 7) via Chikkalli, , Siddapur, Dasankoppa 240 MRL09 MRL09-Dummihal to join SH Upgarde None 9.700 3.750 Complete 22 347.64 245.36 593.00 57.29 (5 , 1 , 0 , 0 , 6) near via Sudambi, Hireanaji, Dhullikoppa 241 MRL05 MRL05- to Upgarde Waste Plastics 13.830 3.750 Complete 31 539.42 380.66 920.08 81.91 (4 , 0 , 0 , 0 , 4) Chikkanaji via Kummur, , Dhullikoppa Block Byadgi Total 32.240 84 1,332.30 940.06 2,272.36 190.17 (14 , 2 , 1 , 0 , 17)

Page 35 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

242 MRL07 MRL07-Naregal to Upgarde -- 6.690 3.750 Complete 15 268.26 189.50 457.76 39.10 (4 , 2 , 0 , 0 , 6) Sankrikoppa via Kodiyallapur 243 MRL08 MRL08-Vardi to tp join MDR Upgarde -- 5.050 3.750 Complete 7 227.88 160.79 388.67 29.56 (1 , 0 , 0 , 0 , 1) via Shankrikoppa 244 MRL01 MRL01-Uppanshi to join SH Upgarde -- 11.370 3.750 Complete 30 413.66 292.77 706.43 137.13 (7 , 2 , 0 , 0 , 9) near Adur via Byagawadi,, tavaragoppa, Hirehullal Block Hangal Total 23.110 52 909.80 643.06 1,552.86 205.79 (12 , 4 , 0 , 0 , 16) Block- Haveri

245 MRL02 MRL02- to Marol via Upgarde Terrazyme 11.610 3.750 Complete 20 353.14 248.90 602.04 140.45 (6 , 1 , 0 , 0 , 7) Negalur ,Kodabal 246 MRL01 MRL01- to MDR Upgarde -- 6.530 3.750 Complete 26 298.76 210.41 509.17 36.54 (2 , 1 , 0 , 0 , 3) (Guttal-Havanur Road) 247 MRL17 MRL17-Negalur to Upgarde Waste Plastics 11.850 3.750 Complete 30 489.01 344.96 833.97 68.53 (2 , 0 , 0 , 0 , 2) Kanchargatti road (MDR) via Guttal Block Haveri Total 29.990 76 1,140.91 804.27 1,945.18 245.52 (10 , 2 , 0 , 0 , 12) Block- Ranibennur

248 MRL01 MRL01-Kamadod to Upgarde -- 3.900 3.750 Complete 9 138.11 97.36 235.47 43.61 (4 , 0 , 0 , 0 , 4) (Halageri-Dandagihalli Road) via ,Antaravalli 249 MRL02 MRL02-Itagi to Yalabadagi Upgarde -- 5.980 3.750 Complete 17 176.34 123.69 300.03 34.47 (5 , 1 , 0 , 1 , 7) via Manakur, Nandhihalli 250 T02 T02-Halaageri to Upgarde Waste Plastics 3.900 3.750 Complete 12 119.09 83.95 203.04 22.12 (4 , 0 , 0 , 0 , 4) Dandagihalli via Aladakati, , Konantali

Page 36 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

251 MRL06 MRL06-Ankasapura to Upgarde -- 6.540 3.750 Complete 14 163.21 115.06 278.27 26.20 (4 , 0 , 1 , 0 , 5) Huvinamaradi via ,Karuri, Hullikatti 252 T01 T01- to Somalapura via Upgarde -- 4.600 3.750 Complete 14 119.35 84.13 203.48 26.20 (5 , 1 , 0 , 0 , 6) Rahutaanakatti, Medleri Block Ranibennur Total 24.920 66 716.10 504.19 1,220.29 152.60 (22 , 2 , 1 , 1 , 26) Block- Savanur

253 MRL03 MRL03-Shirabadagi cross to Upgarde Terrazyme 7.800 3.750 Complete 19 320.01 225.62 545.63 45.66 (4 , 0 , 0 , 0 , 4) Chillur badni via
Waste Plastics 254 MRL07 MRL07-Ichangi to Suranageri Upgarde -- 7.530 3.750 Complete 14 274.99 194.08 469.07 44.53 (3 , 1 , 0 , 0 , 4) via Hesarur , Siddapur 255 MRL10 MRL10- to Upgarde -- 8.490 3.750 Complete 12 283.85 200.11 483.96 48.87 (3 , 1 , 0 , 0 , 4) Basavanakoppa via Hesarur, Block Savanur Total 23.820 45 878.85 619.81 1,498.66 139.06 (10 , 2 , 0 , 0 , 12) Block- Shiggoan

256 MRL06 MRL06-Kyalakonda to Madali Upgarde -- 9.110 3.750 Complete 21 394.32 278.21 672.53 53.83 (4 , 0 , 0 , 0 , 4) via ,Hulasogi,Chikkbend igeri,Supagatti 257 MRL13 MRL13-Artala to Upgarde Waste Plastics 7.370 3.750 Complete 18 254.90 180.10 435.00 43.19 (2 , 0 , 0 , 1 , 3) cross via Yattinahalli , Makapura 258 MRL10 MRL10- to Shiapura Upgarde Terrazyme 12.230 3.750 Complete 24 509.08 359.15 868.23 72.14 (1 , 3 , 0 , 0 , 4) via Hottur,Kurshapur Block Shiggoan Total 28.710 63 1,158.30 817.46 1,975.76 169.16 (7 , 3 , 0 , 1 , 11)

Page 37 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Haveri Total 162.790 386 6,136.26 4,328.85 10,465.11 1,102.30 (75 , 15 , 2 , 2 , 94) District- Kodagu

Block-

259 MRL16 MRL16-Balamuri to Upgarde -- 5.590 3.750 Complete 33 224.37 161.27 385.64 33.01 (1 , 0 , 2 , 9 , 12) Hodavada School area via Vatakadu ,Hoddur 260 MRL07 MRL07-Bengur to Kopatti Upgarde -- 7.890 3.750 Complete 37 293.60 208.44 502.04 47.01 (1 , 3 , 3 , 5 , 12)

261 MRL11 MRL11-Bavali to SH Upgarde -- 5.610 3.750 Complete 33 217.82 156.85 374.67 32.88 (0 , 1 , 1 , 10 , (Nariyanda) 12) Block Madikeri Total 19.090 103 735.79 526.55 1,262.34 112.89 (2 , 4 , 6 , 24 , 36) Block- Somavarpet

262 MRL15 MRL15-Suntikoppa Ayyappa Upgarde -- 6.640 3.750 Complete 42 306.01 226.46 532.47 34.61 (3 , 0 , 2 , 3 , 8) Temple to Nakoor Via Kanbailu Bychanalii , Nakoor Shirangala 263 MRL17 MRL17-Andagove to Upgarde Waste Plastics 6.380 3.750 Complete 37 281.04 200.22 481.26 36.70 (2 , 2 , 1 , 0 , 5) Kambibane Via Metnahalla 264 MRL05 MRL05-Sunti to Gondallii Upgarde Waste Plastics 5.282 3.750 Complete 25 174.32 130.17 304.49 28.15 (0 , 1 , 2 , 4 , 7) (Via Basavanakoppa,Shanthveri, Gondalli) 265 MRL14 MRL14-Karkalli to Upgarde -- 5.990 3.750 Complete 27 255.56 182.85 438.41 30.84 (2 , 3 , 1 , 1 , 7) Kushalnagar SH 266 MRL19 MRL19-1st Kudlur to Handli Upgarde -- 5.900 3.750 Complete 25 229.86 165.01 394.87 36.02 (0 , 1 , 4 , 4 , 9)

Block Somavarpet Total 30.192 156 1,246.79 904.70 2,151.49 166.32 (7 , 7 , 10 , 12 , 36)

Page 38 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Virajpet

267 MRL42 MRL42-Hudikeri to Upgarde -- 5.916 3.750 Complete 42 249.17 178.42 427.59 45.18 (3 , 0 , 0 , 5 , 8) Bettachuki Via Bellur 268 MRL40 MRL40-K M Kolli to Kumtoor Upgarde -- 6.730 3.750 Complete 36 286.12 203.45 489.57 46.56 (1 , 0 , 1 , 12 , Via K.Badaga, Kallambala 14) 269 MRL20 MRL20-C.H.Temple to Upgarde -- 7.700 3.750 Complete 47 383.27 269.34 652.61 53.56 (0 , 0 , 2 , 8 , 10) Balapanakere Via Haligattu,Seetha Colony, Chinivada,Begur 270 MRL19 MRL19-Nangala to Upgarde Waste Plastics 8.900 3.750 Complete 36 311.41 221.85 533.26 61.55 (2 , 2 , 1 , 14 , Bittangala - Kongana road( 19) Via Kotheri,Podakeri, V.Badaga,Kuttandi ) Block Virajpet Total 29.246 161 1,229.97 873.05 2,103.02 206.85 (6 , 2 , 4 , 39 , 51) District Kodagu Total 78.528 420 3,212.55 2,304.31 5,516.86 486.06 (15 , 13 , 20 , 75 , 123) District- Kolar

Block- Bangarpet

271 MRL10 MRL10-Nayakarahalli To Upgarde -- 12.390 3.750 Complete 31 448.41 314.45 762.86 53.07 (10 , 14 , 7 , 4 , Hudukula - Sulikunte 35) 272 T09 T09-RR Road to mothakpalli Upgarde -- 11.380 3.750 Complete 21 409.99 287.30 697.29 57.65 (3 , 6 , 7 , 6 , 22) via doddagondahalli, yethur,nakkanahalli,dalavai hosahalli 273 MRL03 MRL03-Dinnur to Upgarde Waste Plastics 9.970 3.750 Complete 20 371.27 260.04 631.31 47.36 (3 , 4 , 9 , 4 , 20) road

Page 39 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

274 T14 T14-Parandahalli MDR to Upgarde -- 6.430 3.750 Complete 14 215.42 151.97 367.39 20.34 (3 , 4 , 4 , 6 , 17) baluvanahalli Via Anatharamapura,Muddegow danahalli,Jangamanahalli,M majara kottur 275 T10 T10-KGF-Kuppam SH To Upgarde -- 7.060 3.750 Complete 14 220.69 155.52 376.21 30.20 (0 , 5 , 2 , 8 , 15) Kyasamballi Via Parandahalli,Puttepalli,Kam bampalli,Chaldiganahalli,Be eranakuppa,Nachandlahalli, Buchepalli,Madivala Block Bangarpet Total 47.230 100 1,665.78 1,169.28 2,835.06 208.62 (19 , 33 , 29 , 28 , 109) Block- Kolar

276 T09 T09-Vemagal to Upgarde -- 8.325 3.750 Complete 14 321.86 224.06 545.92 43.59 (3 , 7 , 2 , 3 , 15) (MDR) 277 T11 T11-NH-4 to Vokkaleri via Upgarde Waste Plastics 5.570 3.750 Complete 10 176.43 124.42 300.85 25.11 (4 , 7 , 3 , 3 , 17) Gajaladinne,chatrakodihalli ,beglibenajenahalli,cholagh atta,jangalahalli,muduvathi ,nernahalli,shettiganahalli,s hettikothnuru 278 T19 T19-NH-4 TO manighatta Upgarde -- 16.580 3.750 Complete 40 519.32 366.01 885.33 77.41 (8 , 14 , 6 , 6 , MDR Via 34) vardenahalli,chadumanahall i,kalhastipura,shillangere, vadagur ,kembodi,iragasandra, parehosahalli Block Kolar Total 30.475 64 1,017.61 714.49 1,732.10 146.12 (15 , 28 , 11 , 12 , 66)

Page 40 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

279 MRL09 MRL09-Kolar Taluk Border to Upgarde -- 8.852 3.750 Complete 26 348.05 237.95 586.00 31.15 (4 , 8 , 1 , 3 , 16) Yalavaguli 280 MRL22 MRL22-Doddamale -Tekal Upgarde Waste Plastics 6.595 3.750 Complete 18 228.55 156.41 384.96 31.97 (2 , 1 , 2 , 4 , 9) road to 281 MRL04 MRL04-Kolar Malur Hosur Upgarde Waste Plastics 3.526 3.750 Complete 8 186.10 127.17 313.27 17.86 (3 , 1 , 1 , 2 , 7) Road to M Sonnahalli 282 MRL11 MRL11- to Upgarde -- 6.941 3.750 Complete 14 199.48 136.66 336.14 34.80 (1 , 4 , 1 , 2 , 8) Anikarahalli Road 283 MRL16 MRL16-Hunisikote to Taluk Upgarde -- 5.205 3.750 Complete 17 157.49 107.85 265.34 24.31 (1 , 0 , 4 , 1 , 6) Border via Ullerahalli,Veerakatpura Block Malur Total 31.119 83 1,119.67 766.04 1,885.71 140.09 (11 , 14 , 9 , 12 , 46) Block-

284 T11 T11-Alangur - Machanahalli Upgarde -- 5.058 3.750 Complete 18 199.19 136.22 335.41 20.33 (0 , 4 , 3 , 2 , 9) road to NH-234 285 T16 T16-Pethandlahalli to Upgarde -- 5.803 3.750 Complete 18 210.64 144.10 354.74 24.58 (2 , 2 , 1 , 2 , 7) Gudipally road 286 MRL08 MRL08-Harapanayakanahalli Upgarde -- 7.360 3.750 Complete 16 226.41 158.65 385.06 35.73 (1 , 4 , 4 , 3 , 12) Cross to Agara 287 T06 T06-Koladevi road to Upgarde Waste Plastics 5.970 3.750 Complete 10 194.02 136.72 330.74 32.57 (3 , 0 , 0 , 2 , 5) Kurudamale road 288 T08 T08- to NH-234 Upgarde Nano 6.000 3.750 Complete 7 220.33 155.10 375.43 28.63 (2 , 3 , 2 , 2 , 9) Technology Block Mulbagal Total 30.191 69 1,050.59 730.79 1,781.38 141.84 (8 , 13 , 10 , 11 , 42)

Page 41 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Srinivasapura

289 MRL06 MRL06-GBK Road to Upgarde Waste Plastics 5.160 3.750 Complete 17 231.29 161.65 392.94 25.54 (3 , 3 , 8 , 2 , 16) Byraganapalli - Yadaganapalli Road via Pathagowanpalli,G Reddivaripalli, Agrahara Thoragonigadda 290 T15 T15-SP Road to LP Road via Upgarde Nano 9.570 3.750 Complete 21 297.10 209.47 506.57 44.48 (2 , 3 , 5 , 7 , 17) Kornahalli, Pataballapalli, Technology Tantharlapalli, Chennapalli, Bachivaripalli, Ganganagaripalli 291 MRL01 MRL01- Jonnapalli- Upgarde -- 11.480 3.750 Complete 25 401.03 282.52 683.55 54.33 (2 , 5 , 1 , 0 , 8) Digavapalli mdr Road to Hodli mdr via Dimbala, Champalli,devalapalli Block Srinivasapura Total 26.210 63 929.42 653.64 1,583.06 124.35 (7 , 11 , 14 , 9 , 41) District Kolar Total 165.225 379 5,783.07 4,034.23 9,817.30 761.01 (60 , 99 , 73 , 72 , 304) District- Koppal

Block- Gangavathi

292 MRL24 MRL24-Hirekeda to Navali- Upgarde -- 5.300 3.750 Complete 15 197.39 135.49 332.88 30.53 (1 , 2 , 0 , 1 , 4) Kanakageri Road 293 MRL14 MRL14-Naganakal to Laxmi Upgarde -- 10.060 3.750 Complete 18 381.32 263.45 644.77 54.73 (6 , 0 , 1 , 1 , 8) camp, via Hulkihal, Hulkihal Camp, Chellur Camp 294 MRL25 MRL25-Navali to Jeeral Upgarde -- 8.410 3.750 Complete 12 165.08 115.43 280.51 50.08 (6 , 1 , 0 , 1 , 8)

Block Gangavathi Total 23.770 45 743.79 514.37 1,258.16 135.35 (13 , 3 , 1 , 3 , 20)

Page 42 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Kustagi

295 MRL26 MRL26-Jagir to Upgarde -- 5.190 3.750 Complete 11 202.43 139.17 341.60 28.19 (6 , 1 , 0 , 0 , 7) Kadival Vai Pattalachinti Block Kustagi Total 5.190 11 202.43 139.17 341.60 28.19 (6 , 1 , 0 , 0 , 7)

Block- Yelburga

296 MRL02 MRL02-Mandalagera (MDR) Upgarde -- 7.440 3.750 Complete 20 348.67 237.45 586.12 41.83 (6 , 1 , 0 , 0 , 7) to Yerihanchihal Via Block Yelburga Total 7.440 20 348.67 237.45 586.12 41.83 (6 , 1 , 0 , 0 , 7)

District Koppal Total 36.400 76 1,294.89 890.99 2,185.88 205.37 (25 , 5 , 1 , 3 , 34) District- Mandya

Block- Krishnarajapet

297 T14 T14-Maragonahally gate to Upgarde Terrazyme 6.020 3.750 Complete 22 234.45 175.63 410.08 32.77 (3 , 1 , 3 , 3 , 10) join madapura road via
Waste Maragonahally, Plastics Govindanahally, Govindanahally koppalu, 298 T02 T02-Mandagere to Upgarde Terrazyme 8.900 3.750 Complete 41 343.37 248.77 592.14 47.71 (2 , 3 , 4 , 0 , 9) Angaramuddanahally -
Waste Gubbahally road Via Plastics Gaddehosuru, Mudalakoppalu, Allenahally, Kyathanahally, Beekanahally 299 T18 T18-krishnapura to Upgarde Terrazyme 4.600 3.750 Complete 19 156.06 114.84 270.90 25.49 (3 , 1 , 0 , 3 , 7) panduvapura railway station
Waste SH road Plastics

Page 43 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

300 T22 T22-Sharahally to K R Pet - Upgarde -- 3.570 3.750 Complete 38 103.62 84.11 187.73 20.71 (2 , 2 , 0 , 2 , 6) road Via Chikkaharanahally, Chikkaharanahally colony, Jothanapura 301 T17 T17-Gandinagara to join Upgarde -- 6.620 3.750 Complete 25 230.55 168.29 398.84 36.77 (2 , 1 , 2 , 2 , 7) Kodimaranahally -Kundur road Via Settahally,chikalale, Hirikalale Block Krishnarajapet Total 29.710 145 1,068.05 791.64 1,859.69 163.45 (12 , 8 , 9 , 10 , 39) Block- Maddur

302 MRL18 MRL18-Ajjahalli to Upgarde Waste Plastics 5.170 3.750 Complete 22 218.81 161.00 379.81 23.62 (8 , 0 , 2 , 1 , 11) Nagarakere via Gurudevarahalli,Upparadod di,Sompura 303 MRL14 MRL14-Taluk Border to Upgarde -- 5.120 3.750 Complete 22 202.51 145.92 348.43 28.34 (3 , 0 , 0 , 1 , 4) Bidarahosahalli via Yaladahalli 304 T08 T08-Chapuradoddi to Upgarde -- 6.770 3.750 Complete 25 225.01 166.17 391.18 37.89 (6 , 2 , 3 , 5 , 16) Huragalavadi via Belthur,Hombalegowdanado ddi,Guligowdanadoddi,Kere megaladoddi,Konsale Garibe Site,Konsaledoddi,D Hosahalli 305 MRL25 MRL25- Bandihalli Upgarde Terrazyme 4.000 3.750 Complete 17 144.67 107.08 251.75 22.10 (2 , 4 , 1 , 2 , 9) MDR to Nidasale via Avasaradahalli,Kundanakupp e,Harakanahalli

Page 44 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

306 T06 T06-Borapura to Maddur Bus Upgarde -- 9.690 3.750 Complete 25 282.89 198.94 481.83 53.35 (5 , 2 , 2 , 2 , 11) Stand via Sadolalu, KMF Colony, Basavanapura, Gejjalagere, Mabbalagere Block Maddur Total 30.750 111 1,073.89 779.11 1,853.00 165.30 (24 , 8 , 8 , 11 , 51) Block-

307 MRL55 MRL55-Gulgatta to Upgarde -- 4.820 3.750 Complete 25 199.34 145.04 344.38 27.27 (3 , 2 , 2 , 0 , 7) Amrutheshwaranahalli Colony via Kandegala 308 MRL01 MRL01-BM road To Upgarde Terrazyme 5.220 3.750 Complete 25 177.68 128.12 305.80 30.29 (5 , 3 , 2 , 0 , 10) Uppanahalli Via 309 MRL19 MRL19-Ravani to Upgarde -- 4.050 3.750 Complete 17 119.33 83.72 203.05 23.50 (4 , 0 , 2 , 1 , 7) Kalyanikoppalu 310 T03 T03-NH 209 to Linganapura Upgarde -- 4.525 3.750 Complete 15 189.16 145.63 334.79 25.65 (8 , 2 , 1 , 0 , 11) via aladahalli,Kamsagara 311 MRL32 MRL32-NH 209 to Upgarde Terrazyme 6.190 3.750 Complete 25 230.19 165.65 395.84 34.35 (8 , 0 , 0 , 0 , 8) Dadamahalli via Chennipura,Hullegala 312 MRL26 MRL26-Gowdagere to Hadli Upgarde Waste Plastics 3.820 3.750 Complete 15 130.11 108.60 238.71 20.76 (3 , 1 , 0 , 0 , 4)

Block Malavalli Total 28.625 122 1,045.81 776.76 1,822.57 161.82 (31 , 8 , 7 , 1 , 47) Block- Mandya

313 T03 T03-Maranahalli to Goravale Upgarde -- 7.950 3.750 Complete 38 305.79 225.22 531.01 41.30 (5 , 1 , 1 , 0 , 7) via M Kebbahalli, Shivali, Gorvale

Page 45 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

314 MRL07 MRL07-Karadikoppalu to Upgarde Waste Plastics 3.455 3.750 Complete 20 99.33 73.66 172.99 20.05 (1 , 1 , 1 , 2 , 5) Doddagarudanahalli via Hampapura, Upparakanahalli 315 MRL04 MRL04-Bettahally to Upgarde -- 5.760 3.750 Complete 32 237.03 177.79 414.82 31.89 (4 , 1 , 1 , 0 , 6) Mallaghatta via M Honnenahally 316 T07 T07- to Mandya Upgarde -- 4.825 3.750 Complete 25 144.04 104.72 248.76 27.00 (5 , 2 , 1 , 0 , 8) Kowdle road via Shivara, Siddegowdanadoddi 317 MRL13 MRL13-Karadikoppalu to Upgarde Terrazyme 5.035 3.750 Complete 25 162.49 114.78 277.27 27.54 (1 , 0 , 0 , 0 , 1) Mandya Nagamangala road via Bilidegalu Block Mandya Total 27.025 140 948.68 696.17 1,644.85 147.78 (16 , 5 , 4 , 2 , 27) Block- Nagamangala

318 MRL16 MRL16-Bindiganavile toH Upgarde Terrazyme 8.490 3.750 Complete 34 324.79 242.92 567.71 44.96 (2 , 2 , 1 , 8 , 13) Kyathanahally via B
Waste Mallenahally,Aghalayakoppa Plastics lu,H Bhuvanahally. 319 MRL01 MRL01-Kadenahally Road to Upgarde -- 5.750 3.750 Complete 32 190.66 137.28 327.94 31.50 (0 , 4 , 4 , 4 , 12) Doddabalua MDR Via Naragalu 320 MRL03 MRL03-Halthi to Upgarde -- 5.905 3.750 Complete 32 235.31 172.45 407.76 33.06 (0 , 1 , 3 , 7 , 11) Gollarahatti Via Kendanahally,Veerasandra,K rishnapura,Chikkajata. 321 MRL06 MRL06-Doddabala to S Upgarde Terrazyme 7.620 3.750 Complete 32 273.29 202.86 476.15 41.69 (0 , 2 , 2 , 4 , 8) Channapura via Chikkenahally, P Neralekere,Kadenahally. Block Nagamangala Total 27.765 130 1,024.05 755.51 1,779.56 151.21 (2 , 9 , 10 , 23 , 44)

Page 46 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Pandavapura

322 MRL05 MRL05-Hulkere to Upgarde Terrazyme 7.510 3.750 Complete 32 284.51 207.51 492.02 39.77 (3 , 4 , 1 , 0 , 8) J.Mallenahally via Chagashettahally,M.Bettahal ly,Shyadanahally. 323 T01 T01-Hiremarali to Upgarde -- 11.390 3.750 Complete 32 375.62 286.47 662.09 62.90 (4 , 7 , 1 , 0 , 12) Meenagara Via Ganadahosur,Anuvalu,Madar ahalli. 324 MRL03 MRL03-Madenahally to Upgarde Terrazyme 5.210 3.750 Complete 27 212.27 158.67 370.94 28.05 (1 , 2 , 2 , 1 , 6) Naranapura via
Waste Balaghatta,B.Kodagahally Plastics Block Pandavapura Total 24.110 91 872.40 652.65 1,525.05 130.72 (8 , 13 , 4 , 1 , 26) Block- Srirangapatna

325 MRL21 MRL21-Kodiyala to Kalakere Upgarde -- 6.330 3.750 Complete 36 237.50 174.47 411.97 35.27 (1 , 3 , 1 , 1 , 6) via Doddaharohalli, Chikkaharohalli,Bannahalli, Bettahalli 326 MRL02 MRL02-T.M Hosur to Taluk Upgarde Terrazyme 5.760 3.750 Complete 34 179.47 131.11 310.58 31.61 (1 , 4 , 0 , 0 , 5) Border via
Waste Gowdahalli,Gangur,siddapur Plastics a 327 MRL13 MRL13-Kalkere to Taluk Upgarde Terrazyme 5.120 3.750 Complete 17 165.52 124.64 290.16 27.85 (1 , 0 , 3 , 0 , 4) Boundary via AK Koppalu, Gammanahalli, Devaraguddanakoppalu 328 MRL12 MRL12- to KRS via Upgarde -- 4.440 3.750 Complete 25 185.73 142.15 327.88 24.35 (1 , 3 , 0 , 0 , 4) Majjigepura, Hongalli Block Srirangapatna Total 21.650 112 768.22 572.37 1,340.59 119.08 (4 , 10 , 4 , 1 , 19)

Page 47 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Mandya Total 189.635 851 6,801.10 5,024.21 11,825.31 1,039.36 (97 , 61 , 46 , 49 , 253) District- Mysore

Block-

329 MRL02 MRL02-Manuganahally to Upgarde -- 6.730 3.750 Complete 18 245.63 178.85 424.48 30.99 (3 , 7 , 2 , 2 , 14) Gaddige road via Belaganahally, Haropura 330 MRL07 MRL07-Kalasur to Hegganur Upgarde Waste Plastics 5.335 3.750 Complete 11 216.76 154.48 371.24 23.10 (2 , 7 , 2 , 3 , 14) road via Thelugumasahalli 331 T01 T01-MM Road to Upgarde -- 12.036 3.750 Complete 26 469.92 348.52 818.44 53.78 (4 , 4 , 4 , 6 , 18) via Mallahalli Bachegowdanahalli 332 MRL19 MRL19-H B Road to Upgarde StrataWeb/Geo 5.825 3.750 Complete 11 213.71 153.71 367.42 25.60 (3 , 3 , 1 , 3 , 10) Bommalapura via cell
Waste Plastics Block Heggadadevanakote Total 29.926 66 1,146.02 835.57 1,981.59 133.46 (12 , 21 , 9 , 14 , 56) Block- Hunsur

333 MRL03 MRL03-Kallahalli to Upgarde Waste Plastics 6.770 3.750 Complete 27 273.70 194.08 467.78 30.77 (8 , 4 , 4 , 0 , 16) Kothegala via Thammadahalli 334 MRL20 MRL20-Biligere-Mailamburu Upgarde -- 7.460 3.750 Complete 25 353.60 256.42 610.02 32.73 (8 , 4 , 0 , 1 , 13) Road to Jabagere via kallikoppalu, manchabayanahalli 335 MRL40 MRL40-Uddur Road to Upgarde -- 6.155 3.750 Complete 15 270.09 195.16 465.25 23.52 (4 , 5 , 2 , 0 , 11) Uyigowdanahally via Bannikuppe, Doddegowdanakoppalu

Page 48 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

336 MRL02 MRL02-Hosakoppalu near to Upgarde Waste Plastics 9.960 3.750 Complete 14 372.37 265.36 637.73 44.14 (1 , 3 , 0 , 1 , 5) BM Road via Habbanakuppe, Kothegala, Yamagumbha Block Hunsur Total 30.345 81 1,269.76 911.01 2,180.77 131.16 (21 , 16 , 6 , 2 , 45) Block- Krishnarajanagar

337 MRL29 MRL29-Haliyur-Ankanahalli Upgarde Waste Plastics 9.050 3.750 Complete 21 384.86 274.55 659.41 37.82 (9 , 5 , 2 , 1 , 17) Road To Kesturkopllu Via Chikkakopplu Kuppe 338 MRL16 MRL16-SH57 To Kalyanpura Upgarde Waste Plastics 5.180 3.750 Complete 17 209.72 153.06 362.78 19.82 (13 , 4 , 0 , 2 , via Gandhanalahhy 19) 339 MRL04 MRL04-Kesturu-Kesturugate Upgarde -- 5.000 3.750 Complete 11 186.98 138.41 325.39 21.55 (3 , 0 , 1 , 1 , 5) Road to Kaveri river Via Kesturkopplu 340 MRL14 MRL14-SH57 To Taluk Border Upgarde StrataWeb/Geo 4.490 3.750 Complete 10 178.34 127.63 305.97 20.41 (2 , 2 , 0 , 0 , 4) Via Kanchikere cell Maragowdanahally 341 MRL26 MRL26-Salukopplu To KR Upgarde -- 4.270 3.750 Complete 10 157.60 115.77 273.37 18.98 (6 , 2 , 3 , 2 , 13) Nagara Taluk Border Via Doddakopplu Kulmehosur Block Krishnarajanagar Total 27.990 69 1,117.50 809.42 1,926.92 118.57 (33 , 13 , 6 , 6 , 58) Block- Periyapatna

342 MRL04 MRL04-Bettadakaval to Upgarde StrataWeb/Geo 9.420 3.750 Complete 24 374.56 265.88 640.44 43.17 (9 , 6 , 6 , 2 , 23) Kelaganahalli via Kudkur cell
Waste Plastics

Page 49 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

343 MRL05 MRL05-P.Basavanahalli to MB Upgarde Waste Plastics 6.440 3.750 Complete 18 234.42 165.75 400.17 30.42 (5 , 5 , 4 , 2 , 16) Road-Thirumalapura Road Via Thirumalapura, Chikkahonur,Gariguddakaval ,Handiguddakaval 344 MRL21 MRL21-SH(Hunsur-Virajpet) Upgarde StrataWeb/Geo 4.770 3.750 Complete 8 225.36 164.25 389.61 17.33 (5 , 3 , 0 , 4 , 12) to Habtoor kopplu via cell Malangi,Mummadikaval SC Kolony 345 MRL02 MRL02-Ayarabedu to MB Upgarde -- 7.615 3.750 Complete 11 340.97 240.07 581.04 33.56 (7 , 5 , 5 , 2 , 19) Road via Koralahosahalli Naviloor Alanahalli kopplu Block Periyapatna Total 28.245 61 1,175.31 835.95 2,011.26 124.48 (26 , 19 , 15 , 10 , 70) District Mysore Total 116.506 277 4,708.59 3,391.94 8,100.53 507.67 (92 , 69 , 36 , 32 , 229) District- Raichur

Block- Deodurga

346 MRL06 MRL06-SH link road to Upgarde Waste Plastics 7.600 3.750 Complete 4 307.39 205.04 512.43 43.55 (2 , 0 , 2 , 8 , 12) rekhalmardi via mallapurdoddi , , bagerdoddi 347 MRL04 MRL04-MDR to taluk border Upgarde Waste Plastics 7.410 3.750 Complete 12 322.93 220.87 543.80 34.86 (1 , 0 , 0 , 0 , 1) G road via Block Deodurga Total 15.010 16 630.32 425.91 1,056.23 78.41 (3 , 0 , 2 , 8 , 13) Block-

348 MRL13 MRL13-Santekallur to Upgarde -- 5.080 3.750 Complete 8 170.44 113.62 284.06 29.48 (2 , 0 , 0 , 0 , 2) Maraldinni Block Lingasugur Total 5.080 8 170.44 113.62 284.06 29.48 (2 , 0 , 0 , 0 , 2)

Page 50 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

349 MRL05 MRL05-Bhagwat Camp to Upgarde -- 9.970 3.750 Complete 56 448.96 321.74 770.70 54.11 (4 , 1 , 2 , 3 , 10) Nico Camp via Bagalwada Block Manvi Total 9.970 56 448.96 321.74 770.70 54.11 (4 , 1 , 2 , 3 , 10) Block- Raichur

350 MRL04 MRL04- to Jalinenchi Upgarde Waste Plastics 12.130 3.750 Complete 33 602.27 411.72 1,013.99 83.81 (7 , 0 , 0 , 1 , 8) via gadhar and kamalapur Block Raichur Total 12.130 33 602.27 411.72 1,013.99 83.81 (7 , 0 , 0 , 1 , 8)

District Raichur Total 42.190 113 1,851.99 1,272.99 3,124.98 245.81 (16 , 1 , 4 , 12 , 33) District- Shimoga

Block- Bhadravathi

351 T16 T16-SH-65(seetharampura) Upgarde Waste Plastics 5.150 3.750 Complete 24 198.38 148.29 346.67 28.16 (3 , 2 , 2 , 0 , 7) to thallikatte via seetharampura old grama taana, kumarinarayanapura 352 MRL17 MRL17-Veerapura (SH-65) to Upgarde -- 5.040 3.750 Complete 17 193.67 146.85 340.52 27.56 (4 , 1 , 3 , 3 , 11) Kachagondanahalli via , jayanagara, 353 MRL22 MRL22-NH-13(Yedehalli) to Upgarde Terrazyme 6.170 3.750 Complete 30 182.19 139.33 321.52 33.74 (2 , 2 , 0 , 1 , 5) keerebeeranahalli via chandanakere, aratholalu, vaddarahatti, aratholalu Block Bhadravathi Total 16.360 71 574.24 434.47 1,008.71 89.46 (9 , 5 , 5 , 4 , 23)

Page 51 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Hosanagar

354 MRL26 MRL26-Shirugolli to Upgarde -- 8.130 3.750 Complete 17 296.43 216.31 512.74 46.31 (0 , 0 , 2 , 11 , Heddaripura via Kalluru 13) 355 MRL23 MRL23-Balehalli SH to SH 77 Upgarde -- 5.760 3.750 Complete 12 216.14 161.62 377.76 32.83 (0 , 0 , 0 , 10 , (Brahmeshwara rd) 10) 356 MRL09 MRL09-Pujaridimba to Upgarde Terrazyme 5.160 3.750 Complete 11 195.34 149.52 344.86 29.39 (0 , 0 , 2 , 3 , 5) Gouturu, Block Hosanagar Total 19.050 40 707.91 527.45 1,235.36 108.53 (0 , 0 , 4 , 24 , 28) Block- Shikaripur

357 MRL24 MRL24-SH-57 Near Upgarde -- 10.800 3.750 Complete 13 297.31 203.76 501.07 65.32 (5 , 1 , 0 , 3 , 9) Bhadrapura to Mudrahalli Via Gama, Isuru, Hunasekoppa 358 MRL04 MRL04-Huliginakoppa- Upgarde -- 3.700 3.750 Complete 3 116.03 83.76 199.79 22.37 (1 , 1 , 1 , 2 , 5) Koratigere MDR to Hakkali Via Channavasaprasanna Temple, Hosamuthagi 359 MRL18 MRL18-Biliki(MDR) to Upgarde Waste Plastics 6.115 3.750 Complete 11 205.66 141.96 347.62 36.99 (3 , 1 , 1 , 2 , 7) Siddihalli Via Kadethinahalli 360 MRL03 MRL03-SH near Upgarde Terrazyme 8.950 3.750 Complete 5 254.59 175.03 429.62 54.13 (4 , 2 , 0 , 1 , 7) Huluginakoppa to Kadenandhihalli Via Huluginakoppa, Muthagi, Bidarakoppa, Sadapura Block Shikaripur Total 29.565 32 873.59 604.51 1,478.10 178.81 (13 , 5 , 2 , 8 , 28)

Page 52 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Shimoga

361 MRL10 MRL10-NH-13 near Gajanur Upgarde -- 7.620 3.750 Complete 41 283.00 207.91 490.91 41.63 (1 , 4 , 3 , 3 , 11) to Shimoga-Hai Hole road via , Tattikere and Basavapura 362 T02 T02-MDR (near Koralahalli) Upgarde Terrazyme 4.570 3.750 Complete 17 147.73 117.50 265.23 25.00 (1 , 2 , 1 , 4 , 8) to MDR-5 via Kachinakatte and Yaraganal 363 MRL07 MRL07-NH-13 near Javalli to Upgarde Waste Plastics 5.610 3.750 Complete 29 158.68 124.09 282.77 30.60 (1 , 5 , 0 , 2 , 8) Kudli via Hoysanahalli and Abraghatta 364 T08 T08-SH near Upgarde -- 6.590 3.750 Complete 32 323.91 236.69 560.60 36.02 (4 , 2 , 1 , 0 , 7) Channamumbapura to MDR via Basavagangur and Kalgagangur Block Shimoga Total 24.390 119 913.32 686.19 1,599.51 133.25 (7 , 13 , 5 , 9 , 34) Block- Soraba

365 MRL03 MRL03-Kamanavalli MDR Upgarde -- 8.900 3.750 Complete 16 315.21 223.89 539.10 50.80 (9 , 4 , 3 , 2 , 18) Cross to Gondi Taluk Border via Chikachowthi, Jogerkere, Vadddigere, Hurulli, Toruvanda 366 MRL14 MRL14-Vidyanagara to Upgarde Terrazyme 4.130 3.750 Complete 10 140.96 103.67 244.63 24.98 (1 , 2 , 2 , 5 , 10) Bennuru via Horabailu, Mannetti Cross 367 MRL04 MRL04-Kodikoppa MDR to Upgarde -- 11.440 3.750 Complete 15 368.78 257.86 626.64 67.98 (2 , 3 , 1 , 4 , 10) Kathuvalli Via Thimmapura, Bendekatte,Tudnuru, Hasavi, Siddihalli, Maddikumari

Page 53 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

368 MRL07 MRL07-Malalikoppa to SH Upgarde Waste Plastics 6.650 3.750 Complete 12 206.84 149.30 356.14 39.01 (3 , 3 , 3 , 3 , 12) Via Chitturu, Kavadi Block Soraba Total 31.120 53 1,031.79 734.72 1,766.51 182.77 (15 , 12 , 9 , 14 , 50) Block- Thirthahalli

369 T05 T05-NH (KALMANE VIA Upgarde Waste Plastics 6.020 3.750 Complete 35 310.16 224.24 534.40 36.44 (0 , 0 , 2 , 4 , 6) HANSA TO MEGARAVALLI )NH 370 T10 T10-SH SHANKRALLI VIA Upgarde Waste Plastics 4.230 3.750 Complete 9 182.69 139.49 322.18 24.12 (0 , 1 , 1 , 4 , 6) HORABYLU TO SH KONANNDUR 371 MRL04 MRL04-MDR( MELIGE TO Upgarde -- 3.450 3.750 Complete 7 173.98 132.35 306.33 19.67 (0 , 1 , 0 , 1 , 2) HORABYLU VIA KELAKERE 372 T01 T01-MDR MRUGAVADHE TO Upgarde Terrazyme 6.810 3.750 Complete 14 256.65 191.17 447.82 38.79 (0 , 0 , 1 , 7 , 8) MUNDUVALLI MDR Block Thirthahalli Total 20.510 65 923.48 687.25 1,610.73 119.02 (0 , 2 , 4 , 16 , 22) District Shimoga Total 140.995 380 5,024.33 3,674.59 8,698.92 811.84 (44 , 37 , 29 , 75 , 185) District- Tumkur

Block- C.N.Halli

373 MRL12 MRL12-NH150 to SH47 Via Upgarde Cold Mix 3.230 3.750 Complete 30 132.89 95.57 228.46 19.02 (3 , 4 , 6 , 5 , 18) Amanikere, Y S Technology Playa, Baradele Palya And Thammadihalli 374 MRL02 MRL02-Huliyar-Anekatte Upgarde -- 6.880 3.750 Complete 58 314.24 224.11 538.35 40.54 (3 , 5 , 1 , 5 , 14) Road to NH234 Via Thimmalapura, Hosahalli palya and Hosahalli

Page 54 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

375 MRL09 MRL09-Kuppur to Upgarde -- 6.110 3.750 Complete 58 236.93 168.71 405.64 36.00 (1 , 5 , 7 , 19 , Ankasandra via 32) Machasandra, Abbujihalli, Bevihalli Gate, Bevinahalli 376 T01 T01-Shettikere to NH150A Upgarde Waste Plastics 12.636 3.750 Complete 117 557.41 398.29 955.70 73.87 (2 , 5 , 13 , 20 , Via Hosapalya , 40) Kallubhavipalya ,Gantiganapalya, Thippanapalya, Chunganahalli,Masthayyana palya and Malgondanahallli Block C.N.Halli Total 28.856 263 1,241.47 886.68 2,128.15 169.43 (9 , 19 , 27 , 49 , 104) Block-

377 MRL23 MRL23-SH-03 to KMT Road Upgarde -- 3.030 3.750 Complete 7 118.39 81.22 199.61 15.45 (1 , 6 , 6 , 6 , 19) via Mannurthimmanahalli,Hanu manthapura,Alalasandra,Ker eyagalahalli 378 T04 T04-Gargadoddi - Voddagere Upgarde -- 4.990 3.750 Complete 7 165.43 113.57 279.00 24.73 (3 , 3 , 3 , 7 , 16) Thanda road to SH-03 via yattujenahalli,jantacolony,p uttammanapalya, 379 MRL20 MRL20-Koratagere- Upgarde Waste Plastics 5.930 3.750 Complete 11 180.01 123.73 303.74 33.94 (1 , 4 , 4 , 3 , 12) Kyamenahalli Road to Madavara via Bajjanahalli 380 T03 T03-Kathinagenahalli to Upgarde -- 5.430 3.750 Complete 8 167.28 114.91 282.19 31.08 (1 , 3 , 2 , 4 , 10) koratagere-Madhugiri taluk border via Chilagonahalli, yadagere,kalkere,Gubalgutt e

Page 55 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

381 T05 T05-Byrenahalli-Thondebavi Upgarde -- 4.230 3.750 Complete 8 152.39 104.61 257.00 24.21 (2 , 2 , 5 , 7 , 16) Road to Siddlingayannapalya via Moraji school,Hosapalya, Thanda,Hakkipikki colony Block Koratagere Total 23.610 41 783.50 538.04 1,321.54 129.41 (8 , 18 , 20 , 27 , 73) Block- Kunigal

382 MRL15 MRL15-Ujjani Upgarde -- 5.610 3.750 Complete 10 229.61 156.46 386.07 33.07 (5 , 0 , 1 , 5 , 11) Road to SH-33 via Anathihalli and Rajendrapura 383 MRL10 MRL10- to NH-48 via Upgarde -- 3.900 3.750 Complete 4 140.83 95.98 236.81 22.98 (6 , 4 , 3 , 11 , Alkere and 24) Kallanayakanahalli 384 MRL09 MRL09-NH-48 (Arasarapalya) Upgarde -- 5.920 3.750 Complete 8 234.08 159.50 393.58 34.88 (4 , 4 , 2 , 6 , 16) to Hucchanabhavi Road via Mavinakatte and Nelathanahalli 385 MRL08 MRL08-Chowdanakuppe - Upgarde -- 3.807 3.750 Complete 3 123.38 86.03 209.41 22.44 (4 , 0 , 2 , 6 , 12) Tavarekere SH to Bestarapalya via Ankanahalli and R.Byadarahalli 386 MRL14 MRL14- to Upgarde -- 3.810 3.750 Complete 3 141.70 96.55 238.25 22.45 (2 , 0 , 1 , 3 , 6) Doddakoppalu via Byranayakanahalli 387 MRL17 MRL17-Shettibidu to Upgarde Waste Plastics 5.322 3.750 Complete 6 203.75 143.85 347.60 31.36 (1 , 1 , 0 , 5 , 7) Venkatareddipalya via Hosur Block Kunigal Total 28.369 34 1,073.35 738.37 1,811.72 167.18 (22 , 9 , 9 , 36 , 76)

Page 56 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Madhugiri

388 MRL33 MRL33-Polenahally to Upgarde -- 7.010 3.750 Complete 18 255.55 175.44 430.99 40.12 (3 , 3 , 3 , 4 , 13) Thippapaura via Sundekunte 389 MRL11 MRL11-MDR-09 to SH-159 Via Upgarde -- 5.110 3.750 Complete 19 199.04 136.61 335.65 29.25 (0 , 4 , 3 , 5 , 12) Bramsamudra 390 MRL20 MRL20-MDR-55 to Upgarde -- 5.240 3.750 Complete 18 210.65 144.54 355.19 29.99 (1 , 2 , 2 , 0 , 5) Bittanakurke via Achenahalli,Kambadahalli. 391 MRL35 MRL35-Veeropagondanahalli Upgarde Waste Plastics 5.970 3.750 Complete 10 176.35 121.15 297.50 34.17 (5 , 4 , 4 , 4 , 17) to Dabbegatta Via K. Gollarahatti ,Bittanakurke 392 MRL30 MRL30- MDR-35 to Upgarde Waste Plastics 5.990 3.750 Complete 24 202.35 138.95 341.30 34.28 (2 , 2 , 4 , 4 , 12) Marithimmanahalli to via venkatapura ,Banavenahalli, jadegondanahalli. Block Madhugiri Total 29.320 89 1,043.94 716.69 1,760.63 167.81 (11 , 15 , 16 , 17 , 59) Block- Pavagada

393 MRL10 MRL10-Hosadurga cross to Upgarde Waste Plastics 5.690 3.750 Complete 10 179.54 123.10 302.64 33.50 (4 , 2 , 0 , 7 , 13) SH-03 via potaganahalli, chikkahalli AKC 394 T16 T16-Y.N Hosakote- Upgarde -- 7.100 3.750 Complete 11 214.79 147.55 362.34 37.09 (3 , 2 , 2 , 1 , 8) Bestrahalli Road to A.P Border via Siddapura,Jalodu, chikkajalodu 395 MRL07 MRL07-Bellibatlu to Upgarde -- 9.230 3.750 Complete 15 314.43 210.48 524.91 54.33 (5 , 4 , 6 , 8 , 23) chikkathimmanahatti via thimlapura,nidagallu,devray anaroppa.

Page 57 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

396 MRL09 MRL09-Y.N Hosakote to SH- Upgarde -- 8.130 3.750 Complete 12 203.23 139.79 343.02 47.86 (2 , 1 , 2 , 1 , 6) 03 via R.D Roppa,Dalavaihalli,Bheeman akunte, Block Pavagada Total 30.150 48 911.99 620.92 1,532.91 172.78 (14 , 9 , 10 , 17 , 50) Block- Sira

397 MRL05 MRL05-Dwaranakunte to S.A Upgarde -- 5.190 3.750 Complete 13 209.79 143.95 353.74 29.70 (9 , 1 , 2 , 1 , 13) Road via Nidhaghatta 398 MRL16 MRL16-Doddagulla to Upgarde -- 6.690 3.750 Complete 14 196.58 135.11 331.69 37.95 (5 , 4 , 6 , 3 , 18) Bangalow via Kallipalya,Ganganahalli gollarahatti 399 MRL18 MRL18-SH-84 to Upgarde Waste Plastics 9.540 3.750 Complete 23 382.18 262.24 644.42 54.60 (4 , 2 , 2 , 6 , 14) Chikkagrahara via yaramadanahally,punajihally ,Malanahally 400 MRL01 MRL01-NH-234 to Upgarde -- 5.100 3.750 Complete 15 183.46 125.94 309.40 27.47 (2 , 1 , 0 , 4 , 7) Ramalingapura-Sakshihalli MDR via Balapura,Durgowanahatti Block Sira Total 26.520 65 972.01 667.24 1,639.25 149.72 (20 , 8 , 10 , 14 , 52) Block-

401 MRL14 MRL14-YT Road to SH 47 Via Upgarde -- 5.570 3.750 Complete 40 237.96 162.58 400.54 32.77 (4 , 4 , 1 , 4 , 13) Honnenahally, Bochihally, Sugur, and Mathigatta

Page 58 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

402 MRL05 MRL05-NH 206 to Upgarde -- 5.750 3.750 Complete 18 196.59 134.36 330.95 33.83 (1 , 6 , 7 , 13 , Kotigehally Via Kuppuru, 27) Shettihally, Ballekatte, Uppinahally and Ginikikere. 403 MRL16 MRL16-Bommenahally to Upgarde Cold Mix 4.890 3.750 Complete 4 150.40 102.80 253.20 28.76 (1 , 1 , 4 , 14 , Halkurki via Technology 20) Kalammanagudda, Bommenahally L.Thandya, Lambanitandya, Thandya,and Muddenahalli. H 404 MRL02 MRL02-Eachnur to Karadi Upgarde -- 6.660 3.750 Complete 35 297.17 203.03 500.20 39.17 (1 , 9 , 8 , 5 , 23) Via Karadalu Sante Maidana, Kondlighatta,and Mallipatana 405 MRL27 MRL27-Kasavanahally to Upgarde -- 5.730 3.750 Complete 28 231.79 158.36 390.15 33.71 (2 , 1 , 6 , 8 , 17) MDR Via H Janatha Colony, and Hullenahalli Block Tiptur Total 28.600 125 1,113.91 761.13 1,875.04 168.24 (9 , 21 , 26 , 44 , 100) Block- Tumkur

406 MRL20 MRL20-NHS Road- Upgarde -- 3.768 3.750 Complete 10 145.43 99.41 244.84 16.63 (3 , 1 , 3 , 5 , 12) Cross ViaKurgunda,Vardnahali,Kali palya 407 MRL27 MRL27-Bugudanahalli to NH- Upgarde Waste Plastics 6.565 3.750 Complete 14 241.99 165.59 407.58 34.27 (5 , 6 , 1 , 6 , 18) 206 via Mudigere, Doddanaravangala and Peramanahalli 408 MRL13 MRL13-Chikkathotlukere to Upgarde -- 5.512 3.750 Complete 13 188.35 128.83 317.18 25.93 (2 , 4 , 3 , 9 , 18) SH33 via Bommanahalli, Beladhara, Ahobalagrahara and M.Gollahalli

Page 59 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

409 MRL11 MRL11-Machagondanahalli Upgarde -- 3.970 3.750 Complete 1 136.57 93.48 230.05 22.68 (2 , 2 , 2 , 5 , 11) to Pandithanahalli Hand Post via Kesaramadu and K.Palasandra 410 MRL01 MRL01-Kumkumanahalli to Upgarde -- 9.678 3.750 Complete 8 370.12 253.21 623.33 53.30 (2 , 3 , 3 , 5 , 13) Bellavi via , Mudigere, Ballapura, Singrihalli Block Tumkur Total 29.493 46 1,082.46 740.52 1,822.98 152.81 (14 , 16 , 12 , 30 , 72) Block-

411 MRL19 MRL19-Taluk border to Upgarde -- 3.720 3.750 Complete 23 132.58 92.59 225.17 21.42 (2 , 0 , 7 , 13 , NH150A via Thore 22) mavinahalli and Bhuvanalli 412 MRL17 MRL17-VR 252 (Nagalapura Upgarde Waste Plastics 6.110 3.750 Complete 31 229.13 155.69 384.82 35.17 (2 , 5 , 4 , 6 , 17) road) to NH150 A via Beediganahalli 413 MRL10 MRL10-Sarigehalli to Upgarde Cold Mix 6.808 3.750 Complete 31 235.22 164.91 400.13 39.19 (0 , 2 , 6 , 12 , Harenahalli- Kallur Road Technology 20) MDR via Hattihalli and Muslim colony 414 MRL07 MRL07-NH 150A near Upgarde -- 5.250 3.750 Complete 30 160.72 111.84 272.56 30.22 (2 , 1 , 5 , 10 , to Neergunda 18) via Venkatapura. Block Turuvekere Total 21.888 115 757.65 525.02 1,282.67 126.00 (6 , 8 , 22 , 41 , 77) District Tumkur Total 246.806 826 8,980.28 6,194.61 15,174.89 1,403.38 (113 , 123 , 152 , 275 , 663) District- Udupi

Page 60 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

415 MRL13 MRL13-Mulladka to Upgarde -- 6.140 3.750 Complete 28 272.61 194.81 467.42 31.65 (0 , 0 , 5 , 8 , 13) Kanjarkatta road 416 MRL20 MRL20-Banglegudde to Upgarde Cold Mix 8.220 3.750 Complete 31 330.57 238.85 569.42 43.06 (0 , 1 , 3 , 10 , Battahole road Technology 14) 417 MRL08 MRL08-Uddapalke to Upgarde -- 10.000 3.750 Complete 26 453.95 325.03 778.98 48.90 (0 , 0 , 5 , 9 , 14) Malanthaguttu road via Pelathaje Block Karkala Total 24.360 85 1,057.13 758.69 1,815.82 123.61 (0 , 1 , 13 , 27 , 41) Block- Kundapura

418 MRL13 MRL13-Albady proper, Upgarde Cold Mix 4.197 3.750 Complete 26 226.76 165.56 392.32 21.33 (0 , 2 , 1 , 1 , 4) Maruru to Kodabailu road Technology 419 MRL27 MRL27-Salkodu to Upgarde -- 7.670 3.750 Complete 22 308.65 223.31 531.96 41.22 (0 , 1 , 1 , 11 , Moodabage via mardi road 13) Block Kundapura Total 11.867 48 535.41 388.87 924.28 62.55 (0 , 3 , 2 , 12 , 17) District Udupi Total 36.227 133 1,592.54 1,147.56 2,740.10 186.16 (0 , 4 , 15 , 39 , 58) District- Uttara Kannada

Block- Ankola

420 MRL16 MRL16-Taribail to Agragone Upgarde -- 8.270 3.750 Complete 28 215.27 151.57 366.84 49.38 (0 , 2 , 7 , 18 , Joog via Bolkunte, 27) Sagadgeri , Bailkeri, Hegre , Totadkeri, Adigone. Block Ankola Total 8.270 28 215.27 151.57 366.84 49.38 (0 , 2 , 7 , 18 , 27)

Page 61 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Bhatkal

421 MRL23 MRL23-Murudeshwar Upgarde Waste Plastics 6.780 3.750 Complete 17 282.71 198.22 480.93 39.83 (1 , 7 , 5 , 17 , Harikantrakeri to NH-66 30) Neeragadde Crossing NH-66 Yedabadru Muragoli Kalika Temple Via Tudalli Village 422 MRL21 MRL21-Bhatkal -Sagar SH Upgarde -- 11.090 3.750 Complete 36 345.06 243.28 588.34 65.56 (0 , 1 , 2 , 46 , Murukodi to Hudir village 49) Primary school Via Hudeel , Gandalagi , Murkodikeri,Marathikeri Block Bhatkal Total 17.870 53 627.77 441.50 1,069.27 105.39 (1 , 8 , 7 , 63 , 79) Block-

423 MRL16 MRL16-Golehalli to Upgarde Waste Plastics 5.870 3.750 Complete 8 236.93 180.17 417.10 36.93 (2 , 4 , 0 , 3 , 9) Banasgeri via Joganakoppa 424 MRL19 MRL19-Pala mangalwad to Upgarde Terrazyme 6.320 3.750 Complete 12 238.55 166.95 405.50 41.13 (2 , 1 , 0 , 2 , 5) Hunsawad village via Malawad Block Haliyal Total 12.190 20 475.48 347.12 822.60 78.06 (4 , 5 , 0 , 5 , 14) Block- Honnavara

425 MRL32 MRL32-MDR Basti to Hesige Upgarde -- 7.300 3.750 Complete 27 280.06 196.13 476.19 45.13 (0 , 0 , 0 , 27 , via neeragai , jinbail , 27) Bettanakeri , Kulgaar , Heggar 426 MRL24 MRL24-NH-206 to Kembal , Upgarde Waste Plastics 6.700 3.750 Complete 19 250.17 175.29 425.46 40.89 (0 , 0 , 2 , 23 , Halli Gatte Road 25) Block Honnavara Total 14.000 46 530.23 371.43 901.66 86.02 (0 , 0 , 2 , 50 , 52)

Page 62 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Joida/ Supa)

427 MRL18 MRL18-Godshet to Tellolli Upgarde -- 6.160 3.750 Complete 22 264.05 184.79 448.84 39.28 (0 , 0 , 0 , 11 , via Kumbarwada 11) Block Joida/ Supa) Total 6.160 22 264.05 184.79 448.84 39.28 (0 , 0 , 0 , 11 , 11) Block- Karwar

428 MRL05 MRL05-Devalmakki to Upgarde -- 6.200 3.750 Complete 23 189.65 133.27 322.92 37.37 (0 , 0 , 7 , 6 , 13) Soregadde Siddarameshwar temple Via SH-6, Konkangadde,Shirve Block Karwar Total 6.200 23 189.65 133.27 322.92 37.37 (0 , 0 , 7 , 6 , 13) Block- Kumta

429 MRL01 MRL01-SH 48 to SH 48 via Upgarde -- 5.230 3.750 Complete 14 189.01 132.55 321.56 32.21 (0 , 2 , 6 , 8 , 16) Hegle,Goudgalkoppa,Gowdr ukeri,Bachkanda,Kelaginkeri ,Kelaginkoppa Block Kumta Total 5.230 14 189.01 132.55 321.56 32.21 (0 , 2 , 6 , 8 , 16) Block- Mundagod

430 MRL25 MRL25-GUNJAVATHI TO Upgarde Waste Plastics 8.500 3.750 Complete 29 442.52 309.80 752.32 55.73 (1 , 1 , 0 , 3 , 5) UMMACHAGI-KATUR ROAD (MDR) 431 MRL18 MRL18-Tenkal cross(MDR) to Upgarde Terrazyme 5.740 3.750 Complete 19 240.21 168.50 408.71 36.94 (0 , 0 , 1 , 2 , 3) (Mavinakatta)taluka Boundary VIA Ummachagi Block Mundagod Total 14.240 48 682.73 478.30 1,161.03 92.67 (1 , 1 , 1 , 5 , 8)

Page 63 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Siddapura

432 MRL05 MRL05-Hale Bedkani to Upgarde Waste Plastics 5.980 3.750 Complete 27 260.78 180.79 441.57 40.52 (1 , 3 , 4 , 41 , Halageri-Adukatta 49) (MDR)Road via Kumbarakuli, Sunkatti, Sullurkeri 433 MRL02 MRL02-Guntekodlu to Upgarde Waste Plastics 9.100 3.750 Complete 47 399.73 281.99 681.72 63.01 (0 , 1 , 7 , 25 , Siddapura-Talaguppa road 33) via Mandagalale, Nipli, Arendur 434 MRL08 MRL08-Mensi -Vandane road Upgarde Waste Plastics 4.660 3.750 Complete 39 254.57 177.71 432.28 30.98 (0 , 0 , 2 , 25 , to Kudegod via Jigalemane, 27) Karibal, Anagal 435 MRL07 MRL07-Koppanakeri to NH Upgarde Waste Plastics 5.200 3.750 Complete 31 214.05 152.20 366.25 35.97 (0 , 0 , 1 , 9 , 10) via Algod, Tulakalmane cross, Kodagibaile crooss, Mandagalale, Hemtemane Block Siddapura Total 24.940 144 1,129.13 792.69 1,921.82 170.48 (1 , 4 , 14 , 100 , 119) Block- Sirsi

436 MRL26 MRL26-Dasanakoppa to Upgarde Waste Plastics 10.350 3.750 Complete 35 442.10 306.01 748.11 82.39 (3 , 5 , 4 , 19 , Kandraji via Danaganahalli, 31) Kotekoppa, Ummadi, Bankanal 437 MRL02 MRL02-Ganeshnagar to Upgarde Waste Plastics 3.115 3.750 Complete 11 68.02 47.34 115.36 22.56 (1 , 0 , 3 , 31 , Neeranalli Via Andalli 35) Block Sirsi Total 13.465 46 510.12 353.35 863.47 104.95 (4 , 5 , 7 , 50 , 66) Block- Yellapura

438 MRL08 MRL08-Kumbri to Upgarde Waste Plastics 6.520 3.750 Complete 16 274.01 191.80 465.81 41.30 (0 , 0 , 0 , 40 , Upaleshwar 40)

Page 64 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

439 MRL96 MRL96-Tukadbail to Hulagod Upgarde Waste Plastics 5.990 3.750 Complete 18 276.94 193.80 470.74 38.54 (0 , 0 , 0 , 15 , Via Jogabhattarkeri 15) Block Yellapura Total 12.510 34 550.95 385.60 936.55 79.84 (0 , 0 , 0 , 55 , 55) District Uttara Kannada Total 135.075 478 5,364.39 3,772.16 9,136.55 875.65 (11 , 27 , 51 , 371 , 460) District- Yadgir

Block- Shahpur

440 MRL01 MRL01-Haranagera to Upgarde Waste Plastics 13.630 3.750 Complete 17 491.74 342.34 834.08 82.92 (6 , 0 , 0 , 0 , 6) Maddaraki Via Gogi(P) 441 MRL03 MRL03-SH-16 to Hoskera Via Upgarde -- 8.350 3.750 Complete 21 329.00 224.20 553.20 50.34 (5 , 1 , 0 , 0 , 6) Rabbanalli Karkalli Rajapur 442 MRL02 MRL02- to Sagar Upgarde -- 8.000 3.750 Complete 16 309.51 210.92 520.43 48.67 (2 , 0 , 2 , 0 , 4)

Block Shahpur Total 29.980 54 1,130.25 777.46 1,907.71 181.93 (13 , 1 , 2 , 0 , 16) Block-

443 MRL01 MRL01-Kudlagi to Mudnoor K Upgarde -- 8.140 3.750 Complete 18 378.04 257.60 635.64 49.52 (4 , 0 , 2 , 0 , 6)

444 MRL13 MRL13-Budihal To Bapparga Upgarde Waste Plastics 7.630 3.750 Complete 13 295.79 201.55 497.34 46.42 (4 , 0 , 0 , 0 , 4) Via Horatti 445 MRL03 MRL03-Pet Ammapur to Upgarde -- 9.490 3.750 Complete 20 475.99 324.29 800.28 57.73 (4 , 0 , 0 , 0 , 4) Godrihal Road VIa Jaibenchi Chigrihal Block Shorapur Total 25.260 51 1,149.82 783.44 1,933.26 153.67 (12 , 0 , 2 , 0 , 14) District Yadgir Total 55.240 105 2,280.07 1,560.90 3,840.97 335.60 (25 , 1 , 4 , 0 , 30)

Page 65 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Road Proposals Total 3,226.214 8,198 1,22,774.93 86,660.34 2,09,435.27 17,997.92 (1256 , 900 , 810 , 1563 , 4529) Long Span Bridge Proposals

District- Belgaum

Block- Bailahongala

446 - Construction of Box culvert Upgarde -- 16.300 0.000 Complete 0 50.96 33.97 84.93 0.00 (0 , 0 , 0 , 0 , 0) at Ch 0.290km on Mugabasav Budihal road Block Bailahongala Total 16.300 0 50.96 33.97 84.93 0.00 (0 , 0 , 0 , 0 , 0)

District Belgaum Total 16.300 0 50.96 33.97 84.93 0.00 (0 , 0 , 0 , 0 , 0)

District- Davanagere

Block- Davanagere

447 - Construction of Box Culvert Upgarde -- 83.000 0.000 Complete 0 267.37 178.25 445.62 0.00 (0 , 0 , 0 , 0 , 0) across Sagale Halla on Kandagallu to Mayakonda Road at 1.02 km Block Davanagere Total 83.000 0 267.37 178.25 445.62 0.00 (0 , 0 , 0 , 0 , 0)

District Davanagere Total 83.000 0 267.37 178.25 445.62 0.00 (0 , 0 , 0 , 0 , 0)

District- Dharwad

Block- Dharwad

448 - Construction of box culvert Upgarde -- 32.750 0.000 Complete 0 84.51 56.34 140.85 0.00 (0 , 0 , 0 , 0 , 0) at Ch 5.34 km in MRL-04 NH Near Heggeri to MDR Tadkod-Garag via Belur-ko Block Dharwad Total 32.750 0 84.51 56.34 140.85 0.00 (0 , 0 , 0 , 0 , 0)

Page 66 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block-

449 - Constr of Box culvert at Upgarde -- 18.150 0.000 Complete 0 40.81 27.20 68.01 0.00 (0 , 0 , 0 , 0 , 0) 8.16km in MRL 12-Kalas to Pashupatihal 450 - Constr of Box culvert at Ch Upgarde -- 47.350 0.000 Complete 0 67.18 44.79 111.97 0.00 (0 , 0 , 0 , 0 , 0) 1.86 in MRL06 to join hanchinal road via kubhihal 451 - Const of Box culvert at Upgarde -- 19.400 0.000 Complete 0 35.93 23.96 59.89 0.00 (0 , 0 , 0 , 0 , 0) 2.79km in MRL16-Ingalgi to Kamadolli via Tarlghatta 452 - Constr of Box culvert at Upgarde -- 50.650 0.000 Complete 0 70.03 46.69 116.72 0.00 (0 , 0 , 0 , 0 , 0) 3.60 Km in MRL06-Yaliwal to join Kamadolli hanchinal road via kubhihal Block Kundgol Total 135.550 0 213.95 142.64 356.59 0.00 (0 , 0 , 0 , 0 , 0)

Block- Navalgund

453 - Const of Box culvert at Upgarde -- 39.800 0.000 Complete 0 104.49 69.66 174.15 0.00 (0 , 0 , 0 , 0 , 0) 2.42Km in MRL02-Annigeri SH to Bhadrapur road 454 - Const of Box culvert at 1.42 Upgarde -- 21.050 0.000 Complete 0 48.92 32.61 81.53 0.00 (0 , 0 , 0 , 0 , 0) km in MRL02-Annigeri SH to Bhadrapur Block Navalgund Total 60.850 0 153.41 102.27 255.68 0.00 (0 , 0 , 0 , 0 , 0)

District Dharwad Total 229.150 0 451.87 301.25 753.12 0.00 (0 , 0 , 0 , 0 , 0)

District- Gadag

Page 67 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Gadag

455 - Kurthkoti to Antur-Bentur Upgarde -- 21.630 0.000 Complete 0 55.65 37.10 92.75 0.00 (0 , 0 , 0 , 0 , 0) Bridge Block Gadag Total 21.630 0 55.65 37.10 92.75 0.00 (0 , 0 , 0 , 0 , 0)

Block- Shirhatti

456 - Konchigeri HLC Upgarde -- 24.660 0.000 Complete 0 19.31 12.87 32.18 0.00 (0 , 0 , 0 , 0 , 0)

457 - Konchigeri Box culvert Upgarde -- 26.430 0.000 Complete 0 52.51 35.00 87.51 0.00 (0 , 0 , 0 , 0 , 0)

Block Shirhatti Total 51.090 0 71.81 47.88 119.69 0.00 (0 , 0 , 0 , 0 , 0)

District Gadag Total 72.720 0 127.46 84.98 212.44 0.00 (0 , 0 , 0 , 0 , 0)

District- Gulbarga

Block- Chittapur

458 - Construction of Long Span Upgarde -- 43.500 0.000 Complete 0 87.41 58.27 145.68 4.32 (0 , 0 , 0 , 0 , 0) Bridge to Road From to Tarkashpet Via Sugur(N) Block Chittapur Total 43.500 0 87.41 58.27 145.68 4.32 (0 , 0 , 0 , 0 , 0)

District Gulbarga Total 43.500 0 87.41 58.27 145.68 4.32 (0 , 0 , 0 , 0 , 0)

District- Haveri

Block- Haveri

459 - HAVANUR BRIDGE Upgarde -- 26.550 0.000 Complete 0 38.73 25.82 64.55 0.00 (0 , 0 , 0 , 0 , 0)

Block Haveri Total 26.550 0 38.73 25.82 64.55 0.00 (0 , 0 , 0 , 0 , 0)

Page 68 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Hirekerur

460 - Guddadamadapur Bridge Upgarde -- 21.430 0.000 Complete 0 54.58 36.39 90.97 0.00 (0 , 0 , 0 , 0 , 0)

Block Hirekerur Total 21.430 0 54.58 36.39 90.97 0.00 (0 , 0 , 0 , 0 , 0)

Block- Savanur

461 - Ichangi Bridge Upgarde -- 40.280 0.000 Complete 0 45.48 30.32 75.80 0.00 (0 , 0 , 0 , 0 , 0)

Block Savanur Total 40.280 0 45.48 30.32 75.80 0.00 (0 , 0 , 0 , 0 , 0)

District Haveri Total 88.260 0 138.79 92.53 231.32 0.00 (0 , 0 , 0 , 0 , 0)

District- Tumkur

Block- C.N.Halli

462 - Construction of LongSpan Upgarde -- 53.140 0.000 Complete 0 57.00 38.00 95.00 0.00 (0 , 0 , 0 , 0 , 0) Bridge to the Road Huliyar- Anekatte Road to NH234 Via Thimmalapura 463 - Contruction of Longspan Upgarde -- 42.000 0.000 Complete 0 64.20 42.80 107.00 0.00 (0 , 0 , 0 , 0 , 0) Bridge at ch. 6.75 km to the road Thammadihalli to Anksandra Via Abbujihalli 464 - Contruction of Longspan Upgarde -- 24.000 0.000 Complete 0 49.80 33.20 83.00 0.00 (0 , 0 , 0 , 0 , 0) Bridge at ch. 0.74 km to the road Thammadihalli to Anksandra Via Abbujihalli Block C.N.Halli Total 119.140 0 171.00 114.00 285.00 0.00 (0 , 0 , 0 , 0 , 0)

Page 69 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Block- Turuvekere

465 - CONSTRUCTION OF BOX Upgarde -- 16.700 0.000 Complete 0 20.15 13.44 33.59 0.00 (0 , 0 , 0 , 0 , 0) TYPE BRIDGE AT CH 60M OF ROAD JOINING HAMPLAPURA MDR TO TALUK BORDER VIA 466 - CONSTRUCTION OF BOX Upgarde -- 16.700 0.000 Complete 0 20.15 13.44 33.59 0.00 (0 , 0 , 0 , 0 , 0) TYPE BRIDGE AT CH1530M OF ROAD JOINING HAMPLAPURA MDR TO TALUK BORDRVIA SAMPIGE Block Turuvekere Total 33.400 0 40.31 26.87 67.18 0.00 (0 , 0 , 0 , 0 , 0)

District Tumkur Total 152.540 0 211.31 140.87 352.18 0.00 (0 , 0 , 0 , 0 , 0)

District- Udupi

Block- Karkala

467 - Mudrady to Uppala Bridge Upgarde -- 55.000 0.000 Complete 0 233.57 159.71 393.28 5.72 (0 , 0 , 0 , 0 , 0)

Block Karkala Total 55.000 0 233.57 159.71 393.28 5.72 (0 , 0 , 0 , 0 , 0)

Block- Kundapura

468 - Maruru Bridge Upgarde -- 120.000 0.000 Complete 0 477.90 318.60 796.50 12.50 (0 , 0 , 0 , 0 , 0)

469 - Kuntuhole Bridge Upgarde -- 30.000 0.000 Complete 0 121.72 81.15 202.87 3.13 (0 , 0 , 0 , 0 , 0)

Block Kundapura Total 150.000 0 599.62 399.75 999.37 15.63 (0 , 0 , 0 , 0 , 0)

Block- Udupi

470 - Kunthalanagara Bridge Upgarde -- 95.000 0.000 Complete 0 381.60 254.40 636.00 9.90 (0 , 0 , 0 , 0 , 0)

Block Udupi Total 95.000 0 381.60 254.40 636.00 9.90 (0 , 0 , 0 , 0 , 0)

Page 70 of 71 Generated On : 12/05/2021 11:35 AM Pradhan Mantri Gram Sadak Yojana Road List for attachment with Sanction Letter

Sr. Core Name of Road / Bridge Category New Road (Kms) / Carriage Stage Const. CD Work MoRD Cost State Cost Total Cost Maint. Cost Habs (1000+, Network No. (N/U) Technology Bridge (Mtrs) Way Width (Nos) (Rs Lacs) (Including (Including (Rs Lacs) 500+, 250+, Length Additional Additional <250, Total) State Share) State Share) (Rs Lacs) (Rs Lacs) 1 2 3 4 5 6 7 8 9 10 11 12 13 14

District Udupi Total 300.000 0 1,214.79 813.86 2,028.65 31.25 (0 , 0 , 0 , 0 , 0)

District- Uttara Kannada

Block- Haliyal

471 - Construction of Bridge at Ch Upgarde -- 38.200 0.000 Complete 0 125.29 83.53 208.82 0.00 (0 , 0 , 0 , 0 , 0) 5.30 km Block Haliyal Total 38.200 0 125.29 83.53 208.82 0.00 (0 , 0 , 0 , 0 , 0)

District Uttara Kannada Total 38.200 0 125.29 83.53 208.82 0.00 (0 , 0 , 0 , 0 , 0)

Long Span Bridge Proposals Total 1,023.670 0 2,675.25 1,787.51 4,462.76 35.57 (0 , 0 , 0 , 0 , 0)

Grand Total Total Road Length:3226.214 Kms 8,198 1,25,450.18 88,447.85 2,13,898.03 18,033.49 (1256 , 900 , Total LSB Length:1023.670 Mtrs 810 , 1563 , 4529)

Page 71 of 71 Generated On : 12/05/2021 11:35 AM