Design-Build Administration Manual January 2014

DESIGN-BUILD

CONTRACT ADMINISTRATION MANUAL

Ministry of Transportation

Design-Build Administration Manual January 2014

Enquiries regarding amendments, suggestions, or comments should be directed to:

Ministry of Transportation Contract Innovations Office, 2nd Floor North Garden City Tower 301 St. Paul Street St. Catharines, Ontario L2R 7R4

Contacts : [email protected] [email protected]

"Ce document hautement spécialisé n’est disponible qu’en anglais, en vertu du règlement 671/92, qui en exempte l’application de la Loi sur les services en français. Pour obtenir de l’aide en français, veuillez communiquer avec le ministère des Transports,877-246-4600.”

Design-Build Administration Manual January 2014

TABLE OF CONTENTS 1.0 INTRODUCTION ...... 1 1.1 PURPOSE OF THE GUIDE ...... 1 1.2 CONFIDENTIALITY ...... 2 1.3 ACRONYMS ...... 2

PART A CONTRACT ADMINISTRATION ...... 5 2.0 GENERAL DESIGN-BUILD ADMINISTRATION ...... 6 2.1 THE OWNERS ROLE ...... 7 2.2 THE DESIGN-BUILDER’S ROLE ...... 7 2.3 CONTRACT PAYMENT ...... 8 2.4 COMMUNICATIONS ...... 8 2.5 SCHEDULE ...... 9 3.0 ADMINISTRATION FOR DESIGN ...... 10 3.1 GENERAL...... 10 3.2 PROJECT SPECIFIC TASKS ...... 10 4.0 ADMINISTRATION FOR CONSTRUCTION ...... 11 4.1 GENERAL...... 11 4.2 CONSTRUCTION ADMINISTRATION START-UP MEETING ...... 12 4.3 CONTRACT AWARD ...... 29 4.4 CONSTRUCTION PRE-START MEETING ...... 29 4.5 NOTIFICATIONS ...... 36 4.6 CONTRACT MEETINGS ...... 37 4.7 COMPLETION DATE ...... 43 4.8 EXPENDITURE CONTROL ...... 44 4.9 ROCK ADMINISTRATION ...... 44 4.10 COMMISSIONING OF HIGHWAYS PRIOR TO OPENING ...... 44 4.11 DOCUMENTATION ...... 44 4.12 CHANGES ...... 48 4.13 MEDIA ENQUIRES ...... 49 4.14 SUBSTANTIAL PERFORMANCE & CONTRACT COMPLETION...... 49 4.15 ASSESSING COMPLIANCE TO THE QUALITY PROCESSES ...... 53 5.0 ADMINISTRATION POST-CONSTRUCTION ...... 55 5.1 CONTRACT CLOSING PROCESS ...... 55 5.2 DESIGN-BUILD CONTRACTOR PERFORMANCE RATING ...... 56 5.3 SUBMISSION OF RECORD DOCUMENTS ...... 56

PART B INSPECTION TASKS ...... 57 6.0 DESIGN-BUILD INSPECTION TASKS - GENERAL ...... 58 7.0 DESIGN-BUILD INSPECTION TASKS - OPS SPECIFICATIONS...... 59 7.1 LEVELS OF INSPECTION ...... 59 7.2 DOCUMENTATION ...... 60 7.3 INDEX OF INSPECTION TASKS ...... 61 8.0 DESIGN-BUILD INSPECTION TASKS - PERFORMANCE SPECIFICATIONS ...... 279 APPENDIX A ...... 295 LIST OF CONTRACT ADMINISTRATION FORMS ...... 295 APPENDIX B ...... 299 ROLE OF THE CA (CA) WITH RESPECT TO QUALITY VERIFICATION ENGINEER (QVE) SERVICES ...... 299 APPENDIX C ...... 301 TECHNICAL STANDARDS AND SPECIFICATIONS...... 301 APPENDIX D ...... 307 DESIGN-BUILD PROJECT MANAGEMENT STRUCTURE ...... 307 APPENDIX E ...... 310 SUBMISSION INSTRUCTION NOTICES AND NOTICE OF NON-CONFORMANCE ...... 310

Design-Build Administration Manual January 2014

APPENDIX F ...... 311 DESIGN-BUILD RECORD DOCUMENTS CHECKLIST ...... 311 APPENDIX G ...... 316 DESIGN-BUILD COMMUNICATION MATRIX ...... 316

Design-Build Administration Manual January 2014

1.0 INTRODUCTION

1.1 PURPOSE OF THE GUIDE

This guide has been prepared to assist in the administration of Design-Build (DB) contracts for highway construction for the Ministry of Transportation, Ontario. It has been developed to provide guidance to Project Leads and Contract Administrators (CA) regarding contract administration duties and the appropriate level of contract oversight for Design-Build contracts.

There are eight key areas to this guide, these are: o Section 1.0–Introduction Part A – Contract Administration o Section 2.0 - General Design-Build Administration o Section 3.0 - Administration for Design o Section 4.0 - Administration for Construction o Section 5.0 - Administration Post-Construction Part B – Inspection Tasks o Section 6.0 - Inspection -General o Section 7.0 - Inspection Tasks for OPS Specifications o Section 8.0 - Inspection Tasks for Performance Specifications

Part A- Contract Administration is divided into sections for general, design, construction and post-construction phases. The phases for design administration and construction administration may overlap depending on the approach to the project by the Design-Builder.

Part B – Inspection Tasks is divided into sections for general, inspection tasks for Work performed using OPS specifications and inspection tasks for Work performed using Performance Specifications.

When a Design-Build contract includes OPS Specifications, Section 7.0 is intended to provide those involved in inspection with a resource to check that the Work is in compliance with Ministry specifications, standards, drawings, policies and procedures. This part of the manual is divided into seven sections or groupings dealing with: Grading, Concrete and Structures, Bituminous, Electrical, ATMS, Traffic Control, and Environmental.

Within Section 8.0 are the inspection tasks for Work that is covered by Performance Specifications. The tasks are intended to provide those involved in inspecting this Work with a resource to ensure that the Design-Builder has complied with all the Contract Documents relating to Work governed by a Performance Specification.

Both sections 7.0 and 8.0 could apply to a Design-Build contract since there is currently a hybrid approach to Design-Build contract specifications that incorporates both types of specifications. As more Performance Specifications become available Section 8.0 will expand and use of Section 7.0 will decrease.

This document is not a complete documentation of the administration process. It is to be read in conjunction with the requirements of the Design-Build Contract Documents, Ministry directives, Memoranda, and pertinent legislation.

1 Design-Build Administration Manual January 2014

1.2 CONFIDENTIALITY

All Design-Builder records are to be treated as confidential documents. Information requests received from subcontractors, suppliers, the media, or by third parties shall be discussed with the Project Lead prior to release.

1.3 ACRONYMS

AASHTO American Association of State Highway Transportation Officials AC Asphalt Cement ACE Area Contracts Engineer ACI American Concrete Institute ADM-R Administration Regional Services AMC Area Maintenance Contract ASAP As Soon As Possible ASTM American Society for Testing and Materials ATMS Advanced Traffic Management Systems AVS Air Void System CA Contract Administrator CAITM Construction Administration and Inspection Task Manual CAN/BAS Canadian Bridge Analysis System CAS Construction Administration System CCAA Construction Contract Administration Agreement (Legal Agreement) C of C Certificate of Conformance CCTV Closed Circuit Television CDED Contract Design Estimating and Documentation CDS Contract Documentation System CIR Cold In-Place CO Change Order CP Cathodic Protection CSA Contract Services Administrator(also means Contract Control Officer) CVOR Commercial Vehicle Operator’s Registration CPR Design-Build Contractor Performance Rating CPRA Contract Payment and Records Assessment DB-EOI Design-Build Expression of Interest DCR Design and Construction Report DFO Department of Fisheries and Oceans DFT Dry Film Thickness DGS Design Graphic System DSLAT Data System Line-up Acceptance Testing DSM Designated Sources for Materials DTE/DCE Data Terminal Equipment / Data Communications Equipment DTM Digital Terrain Model EA Environmental Assessment ENT Electrical Non-Metallic Tubing EPS Expanded Poly Styrene ERS End Result Specification ESA Electrical Safety Association ESD Environmental Screening Document FDS Final Detailed Statement

2 Design-Build Administration Manual January 2014

FOS Filtration Opening Size GPS Global Positioning System GSTPM Guidelines for Sampling and Testing of Pavement Markings HIR Hot In Place Recycling HPC High Performance Concrete LED Light Emitting Diode M Milestone MOE Ministry of the Environment MNR Ministry of Natural Resources MOC Ministry of Culture MSA Material Selection Approval MTO Ministry of Transportation Ontario OGDL Open Graded Drainage Layer OHSA Occupational Health and Safety Act OPP Ontario Provincial Police OPR Operations OPSS Ontario Provincial Standard Specification OSCLIS Ontario Structural Clearance and Load Information System OTM Ontario Traffic Manual PCM Provincial Construction Memo PDA Power Distribution Assembly PGAC Performance Graded Asphalt Cement PH-A Provincial Highways Program Administration PH-CC Provincial Highways Capital Construction PH-D Provincial Highways Design PH-M Provincial Highways Maintenance PHY Provincial Highways PIT Pre-Installation Testing PMD Profile Measuring Device POP Proof of Performance PQP Plan Quantity Payment PMM Provincial Maintenance Memo PVMS Portable Variable Message Sign QA Quality Assurance QAO Quality Assurance Officer QC Quality Control QST Quality and Standards QVE Quality Verification Engineer RAP Reclaimed Asphalt Pavement RFP Request for Proposal RFQ Request for Quotation RHM Recycled Hot Mix ROW Right of Way RSS Retained Soil System SIT System Integration Test SP Special Provision SSPC Steel Structures Painting Council TESR Transportation Environmental Study Report TOC Traffic Operations Centre VDS Vehicle Detection Station VMS Variable Message Sign

3 Design-Build Administration Manual January 2014

VSLAT Video System Line-up Acceptance Testing WHMIS Workplace Hazardous Materials Information System WP Work Project

4 Design-Build Administration Manual January 2014

PART A

CONTRACT ADMINISTRATION

5 Design-Build Administration Manual January 2014

2.0 GENERAL DESIGN-BUILD ADMINISTRATION

The Design-Build contracting approach merges the traditionally separate detail design and construction projects into one contract performed by a single Design-Builder entity. When administering a Design-Build contract, it is important to understand that the Design-Builder has flexibility to design and construct the project within the bounds of the Contract Documents.

For the purposes of this document, the terms “Design-Builder” and “Contractor” have the same meaning and refer to the entity providing the combined design and construction services for the Design-Build contract.

Administering a Design-Build contract involves ensuring that all deliverables are provided as detailed and in conformance with the Contract Documents. The Ministry relies upon the Design- Builder taking professional responsibility for the design and therefore design submissions are not approved by the Ministry.

The nature of the Design-Build contract anticipates involvement from both Regional Engineering and Regional Operations from the outset forming a Project Team. For each project, the responsibility for the administration of the Design-Build contract is to be led by a Project Lead. The Project Lead may change during the course of the Design-Build contract(See “Project Management Structure” in Appendix D). Typically during the phases of contract preparation through procurement the Project Lead will be the Engineering Project Manager. After award of the Contract the Project Lead role typically transfers to the Operations office and may be either the Area Contracts Engineer (ACE) or the Contract Services Administrator (CSA). Although no longer the Project Lead, the Project Manager will still be a key member of the Project Team, especially during the detail design phase. Regardless of which office has the Project Lead role at any given time, the entire Project Team remains involved throughout the project.

While the Project Lead is ultimately responsible for the administration of the Design-Build contract, after award of the Contract a CA will be either assigned (MTO) or retained (Service Provider) to address the day to day administration of the contract.

ACSA will also be assigned to the project. The main role of the CSA is to provide oversight for the CA role, whether that is an “in-house” MTO assignment or a Service Provider. The CSA may also on occasion perform the duties of the CA

The above paragraphs and Appendix D provide some guidance but ultimately it is up to the Regional Managers to establish the structure of the contract administration team and allocate responsibilities based on available resources and requirements of a particular project.

For Design-Build projects, specific project goals are included in the Request for Proposal. When reviewing Design-Builder submissions, in meetings with the Design-Builder and in correspondence, these project goals should form a foundation for project deliverables.

The Design-Builder’s Engineer will now have responsibility for many approvals that were previously undertaken by the CA on behalf of the Ministry. This does not apply however for repair or remedial actions for non-conforming or deficient Work.

6 Design-Build Administration Manual January 2014

2.1 THE OWNERS ROLE

The Ministry shall establish a Project Team responsible for the development, administration and oversight of the Design-Build contract.

The Project Team shall determine the appropriate approach to frequency and detail of reviews and oversight during all phases of the Design-Build contract based on the project type and complexity as well as the type of specifications used. In doing so, the Project Team shall consider the requirements of all Contract Documents (RFP, GC’s, Design-Builder’s proposal, Specification’s, etc). Throughout the various contract phases the Project Team may assess and adjust their approach as necessary in consideration of the Design-Builder’s performance (e.g.: detail of design reviews may be increased if there are issues with non-conformance to the Contract Documents).

The Owner will not approve any design or construction submissions from the Design-Builder but may review them for completeness and to determine conformance to Contract Documents.

2.2 THE DESIGN-BUILDER’S ROLE

In relation to oversight, the Design-Builder’s role on a Design-Build project is to design and construct the project as per and within the constraints of the Contract Documents. The Design- Builder shall work in collaboration with the Owner to communicate scheduling at all phases of the project and to provide access to the Owner’s representatives as required for all required reviews, audits, inspections, sampling and/or collection of performance indicators. Regardless of reviews and oversight by the Owner, the Design-Builder is solely responsible for design adequacy, accuracy, constructability and appropriateness and conformance to all requirements of the Contract Documents.

Project Meetings

The Design-Builder is required to coordinate mandatory pre-start meetings, at Design start-up and Construction start-up, with the CA and the entire Project Team. In addition to the regular agenda (as may be revised for the Design-Build contract model) the following items should be considered for inclusion in either or both the Design Pre-start or Construction Pre-Start meetings: o General reminder that this is a Design-Build contract and that a partnership approach is desired. o High level discussion of the Ministry’s anticipated oversight approach. o Reminder of design submissions required prior to construction o Reiterate that design submissions will NOT be approved by the Ministry – if non- conformances or deficiencies are found in the design the Design-Builder will be required to stop construction until the design is brought into conformance and remediate any Work constructed to that point (at no additional cost to the Ministry). o Discuss communications and how the Design-Builder proposes to keep the Ministry informed on the project status o Discuss Chapter 2 requirements o Discuss requirements of Specifications in Chapter 3 (particular emphasis on Perfs)

It is a requirement of the RFP that the Design-Builder shall arrange, conduct and attend progress meetings. The Project Team shall determine the appropriate frequency of progress meetings during development of the Request for Proposal. The frequency is specified in the

7 Design-Build Administration Manual January 2014

RFP. The Project Management Best Practices provides a good overview of meetings and should be used as a reference for the Project Team to determine the frequency and content of progress meetings. The frequency of meetings held should take into consideration the complexity of the project while also keeping in mind the Design-Builder has sole responsibility for the design.

The Design-Builder is required to provide a meeting agenda five Business Days in advance of meetings. The agenda/content of all meetings should be carefully reviewed by the CA and revised as necessary to ensure it is appropriate to the Design-Build contract model and the Contract Documents.

2.3 CONTRACT PAYMENT

The general payment process currently used for design-bid-build contracts will also apply to Design-Build contracts. The Payment Cover Sheet (PH-CC-881b) and Progress Payment Certificate (PH-CC-882) have been revised for Design-Build contracts.

The main difference in measurement for payment for Design-Build contracts is that the items have been reduced to a maximum of 14 items which are all lump sum payment (see the “Itemized Bid Form” in Appendix B). This is reflected in the Design-Build Progress Payment Certificate. Payment for each lump sum item monthly is based on the percentage completion of the item. The Design-Builder will submit a monthly invoice showing the percent complete for each item. The CA verifies the invoice through field observations and estimates possibly in conjunction with review of the Design-Builders schedule.

The CA shall review the Design-Builder’s Progress Payment Application and check it contains the information as stated in the Contract Documents.

The Design-Builder’s invoice shall be reviewed by the CA for completeness and if accurate recommended for payment. Along with the Invoice Cover Sheet, the Invoice is then forwarded to the CSA and after approval it is forwarded to the Head of Contract Services within five (5) Business Days for processing.

A monthly expenditure forecast report, produced from CAS, shall also be completed by the CA.

2.4 COMMUNICATIONS

The CA shall be the single point of contact to receive all communications from the Design- Builder and provide all responses from the Ministry back to the Design-Builder. The CA shall forward communications received from the Design-Builder to the CSA and/or Project Lead upon receipt. Any responses from the Ministry to the Design-Builder will be forwarded by the CA upon receipt. The Project Lead is responsible to ensure all internal and external stakeholders receive all communications that may impact on their area of responsibility.

It is strongly recommended that the Project Lead, the CSA and the CA develop a communication matrix to assist in ensuring appropriate distribution of all communications (see Appendix G for a sample matrix).

For public relations involving media inquiries the Ministry has sole responsibility. These inquiries should be addressed according to current Ministry protocol. For all other public relation matters

8 Design-Build Administration Manual January 2014

the Design-Builder is the first point of contact. The CA together with other associated Ministry staff are to work collaboratively with the Design-Builder to address issues appropriately and in a timely manner.

2.5 SCHEDULE

The schedule checklist shall be completed by the CA for the originally submitted critical path schedule and forwarded to the CSA and/or Project Lead. The CSA or Project Lead shall review the Design-Builder’s originally submitted (as bid) critical path schedule. Any deficiencies or impracticalities (e.g. operations which appear out of order or questionable production rates) shall be documented and brought to the Design-Builder’s attention.

Any updates to the schedule shall be submitted by the Design-Builder to the CA, both hard copy and electronic version, and reviewed by the CA for practicality, achievability, and conformance to the Contract Documents. Deficient or non-conforming schedules shall be returned to the Design-Builder noting error(s) and requesting a resubmission. The CA shall forward all schedule updates, with their comments, to the CSA.

The CA shall review the Design-Builder’s progress with respect to the schedule. The CA shall review weekly updates of the Design-Builder’s intended work operations, analyse critical path updates received from the Design-Builder and respond to/administer these accordingly. The Design-Builder’s progress shall be monitored throughout the construction period, and action taken as appropriate in the event that the planned schedule is not maintained. The schedule and progress should be reviewed with the Design-Builder at every progress meeting. If the Design-Builder is behind schedule, the progress meeting shall include a discussion of the reasons for delays, determining if any delays are due to MTO, Design-Builder, or other parties, and ensure that it is documented in the minutes of the meeting. The CA shall request an action plan from the Design-Builder detailing how the delays will be addressed.

The CA shall apply information gained from the critical path schedule, to assess in detail any requests for extension of time, and provide detailed recommendations to the CSA with reasons.

The CA may also apply knowledge gained from the critical path schedule to address arising issues, including but not limited to delays, deletions or changes in the work or additional work, potential acceleration, claim negotiations, and/or dispute resolution processes.

9 Design-Build Administration Manual January 2014

3.0 ADMINISTRATION FOR DESIGN

3.1 GENERAL

The CA shall be in regular communication with the Design-Builder to be aware of the progress of the Work.

The CA shall receive any written submission from the Design-Builder documenting the inaccuracy of the Ministry Supplied Information as required in Section2.2 a) of the RFP.

The CA is to receive any submissions by the Design-Builder that may require approval (such as a PHM125) or review. Submissions are forwarded through the CSA to the Project Lead who ensures the appropriate Ministry office(s) receive such submissions and establish and communicate a required timeframe for response(as may be detailed in the Contract Documents). It is very important that such submissions are provided to the appropriate offices as quickly as possible. A communications matrix should be developed by the CA, CSA and Project Lead to set protocols for distribution of submissions.

The CA and the Ministry project team are to review any “Issued for Construction” drawings, and other design submissions required in the RFP, for conformance to the Contract Documents. It should be emphasized the Design-Builder is responsible for the design and ensuring conformance with all Contract Documents. If there are non-conformances, these need to be brought to the Design-Builder’s attention as quickly as possible through a Notice of Non- Conformance issued by the CA. Timeliness of communication is key to achieving project goals and to minimizing conflict in of non-conformance issues. In the event that Work is underway that does not conform to the Contract Documents the CA shall advise the Design- Builder to stop construction on such Work or any Work that may be impacted by the replacement or repair of the non-conforming Work.

The Contract Documents should be followed to ensure adherence to specified submission requirements. Unless a specific time limit for review by the Owner is specified in the Contract Documents, once the design for a component is submitted, the Design-Builder is able to commence that portion of the construction Work immediately. Timely review of submissions will help to minimize conflict in case of non-conformance issues..

A best practice to use for all design submissions is to acknowledge receipt by sending an Instruction Notice (see Appendix E for suggested wording). This approach allows the Design- Builder to proceed with construction unless a review period is otherwise specified in the Contract Documents.

3.2 PROJECT SPECIFIC TASKS

Specific project requirements are detailed under Section2.4 in the RFP.

The CA is to ensure the Design-Builder’s submissions comply with these requirements as well as with the Information Management requirements of PERF 1075.

10 Design-Build Administration Manual January 2014

4.0 ADMINISTRATION FOR CONSTRUCTION

4.1 GENERAL

The CA is responsible to ensure that the Work performed by the Design-Builder conforms to the Contract Documents. Due to the pace of the work and the complexity, specific details for administration, inspection and oversight have been provided in this document to function as tools and guidelines for the CA to help ensure completeness.

Before the Construction phase, a CSA will be assigned to the project either as the CA or to oversee the work of the CA. The CSA (CSA) works closely with the CA and is responsible to keep the Project Lead informed at all times.

The CA may be a Ministry employee or a Service Provider, as defined in the General Conditions. The CA may also have staff to carry out various aspects of their responsibilities.

General Contract Administration Duties During Construction

o Review but do NOT “approve” construction submissions: the CA, and Project Team as appropriate, o Confirm with CSA any special requirements for documenting field observations (who/what/where/when/why/how) of the Design-Builder’s “Alternative Innovative Concepts” (applicable to Design-Build Major only) o Document field observations (who/what/where/when/why/how) of the Design-Builder’s Work relative to Ministry approved Change Orders, Change Proposals and Ministry accepted proposals from the Design-Builder to correct deficient or non-conforming Work o All inspections, sampling, performance assessments and any observed conditions that may affect the performance during the warranty period must be well documented. Documentation, records and samples must be maintained in a secure and safe location up to the end of the warranty period for the Work and until all disputes with the Design- Builder are resolved o Complete the Design-Build Contractor Performance Rating Form B’s every month and review at progress meetings. o Monitor continuity and compliance with Ministry’s commitments with external regulatory agencies between the design and construction stages. o In the case of non-conformances, clearly identify the non-conformance and compile the appropriate documentation (photos, etc.) to explain why the Design-Builder is in non- conformance o Issue Notice of Non-Conformance when warranted and apply appropriate consequences. o Review the Design-Builder’s progress with respect to the submitted/updated CP schedule o Review work completed to verify monthly progress payment requests o Process monthly payments o Complete monthly expenditure forecast reports

11 Design-Build Administration Manual January 2014

General Contract Administration Duties Post-Construction

o Ensure that the Design-Builder’s Engineer confirms completion of the Work in accordance with the Contract Documents. o Document issues/concerns with Contract Documents, including Specifications established for the Design-Build model, and provide feedback to the Contract Innovations Office (CIO) for future document updates. Provide a copy to the Project Manager as well. o Complete Project Construction Report (as per current Head Office Construction Memorandum and as may be revised for Design-Build contract model) o Complete final package as per “Design-Build Record Documents Checklist” PH-CC- 878DB (see Appendix F) – Note that many items on the regular checklist will not be applicable on a Design-Build contract. Other items will be significantly reduced. o Complete Design-Build Contractor Performance Rating documentation Ensure all commitments with external agencies have been met, including reports and any other deliverables associated with agreements, permits and regulations.

CA

4.2 CONSTRUCTION ADMINISTRATION START-UP MEETING

Note to users: This section was drafted for use when a Service Provider is providing CA services through a Contract Administration Agreement. However, it also provides a good start up meeting guide for “in-house” Ministry CA staff. Adjust the content of the meeting to suit the experience of the Ministry assigned CA.

The purpose of the Construction Administration Start-up meeting is to define the roles and responsibilities for Construction Administration. This meeting is attended by the Project Lead and key members of the Project Team as well as the key contract administration staff. The Design-Builder does not attend this meeting. The process for the handling and review of documentation will also be discussed. The Project Lead will arrange and conduct the Construction Administration Start-Up Meeting. The CA will be responsible for the minutes of this meeting.

The following issues should be discussed at the Construction Administration Start-Up Meeting:

4.2.1 Contract Administration Service Provider Quality Control of Services and Deliverables Plan

If the Contract Administration is by a Service Provider, the Service Provider should describe their Quality Control plan and management. Specific attention should be paid to how the CAs non-conformances and deficiencies in contract administration will be addressed.

4.2.2 General

o The CA shall highlight any potential Constructor conflicts and check that the Design- Builder co-ordinates all work with adjacent Contractors, maintenance staff and service crews. Provincial Highways Directive PHY-B-238 Designation of a Constructor o Discuss contract documentation to be copied to MTO. o List of MTO contact names for the contract.

12 Design-Build Administration Manual January 2014

o Discuss/determine location of CA’s field office. o Identify name and location of Ministry designated laboratory. o Discuss internal/external communication protocols and review Regional Policy regarding Media / MPP / General Public Inquiries.

4.2.3 Inspection Tasks

o Ensure the inspection task requirements are carried out as outlined in this manual. o Ensure that all applicable milestone inspections are carried out and documented in the appropriate diaries. o Review staffing levels on the contract ensuring they meet inspection task requirements.

4.2.4 Insurance and Risk Management Issues

Reference: o Provincial Highways Directive PHY-B-103 Claims for Compensation for Personal and Business Losses During Construction

Review Regional Operations Office policy regarding Third Party claims. All claims for compensation for personal and business loss shall be forwarded to the Design-Builder, with a copy to be maintained by the CA. The CA shall obtain copies, and maintain a file of any pertinent accident reports from the appropriate police force.

When the claims are forwarded through Management Board Secretariat’s Insurance and Risk Management Section, theCA shall examine the contract documentation and respond to requests for information. Copies of all correspondence shall be copied to the CSA.

4.2.5 Design-Build Contractor Performance Rating

The Design-Build Contractor Performance Rating shall be carried out in accordance with the associated guidelines and forms that were in effect on the tender opening date of the contract.

4.2.6 Concerns / Expectations on Issues

The CA shall be responsible for:

o Establishing and maintaining appropriate relationships with adjacent property owners, municipalities, other Ministries representatives, the OPP, local politicians, local police and emergency services, school boards, transit authorities, Utility companies, etc. o Providing day-to-day liaison with the Design-Builder o Providing first line interpretations of the Contract Documents to the Design-Builder, consistent with the intent of the Contract Documents o Communicating the Ministry’s decisions to the Design-Builder o Traffic management, lane and ramp notification protocol to be discussed o Informing the CSA/Project Lead of issues which may lead to delays or claims o Administration of progress payments; review the procedures o Checking that the Design-Builder provides deliverables in a timely, accurate manner

13 Design-Build Administration Manual January 2014

o Receiving submissions from the Design-Builder and forwarding them to the Project Lead; − If a submission from the Design-Builder requires Ministry approval, or is for a deficiency or repair, review and forward the submission within two Business Days to the Project Lead with comments (if CA is a Service Provider include the Service Provider Project Manager’s comments in addition) o Tracking, confirming, documenting and reporting that Submissions − Are received within the specified time frame − Consist of the specified number of copies, content and format − Are sealed and signed when specified o Protection of employees; Discuss Health and Safety Plan and potential issues; CA abiding by the Ministry Personal Protective Equipment Guideline o Receiving Design-Builder’s CVORs for equipment on site; review the requirements of the General Conditions for CVORs and the supplying of source materials throughout the duration of the Contract o Carrying out all on-site inspection and associated surveying o Monitoring and reviewing the quality of Design-Builder’s work to confirm that the Design- Builder is discharging its obligations and responsibilities under the Contract Documents. o Maintaining control of the receipt, use and final disposition of all Ministry-supplied materials in accordance with Ministry procedures o Providing written recommendations on situations / issues as deemed necessary by the Ministry o Monitoring construction related environmental permits to check that they are obtained and adhered to o Ensuring the Design-Builder is properly co-ordinating, communicating and consulting with the High Pressure Gas Utility company for excavation and construction near pipelines. Discuss requirements at the Pre-Start Meeting with the Design-Builder. o Monitoring and ensuring compliance with external agencies regulations and any additional commitments specified in the Contract Documents; external agencies include but are not limited to railway authorities, environmental agencies and local Municipalities.

4.2.7 Pre-Construction Photos / Video

The CA shall take a set of pre-construction digital photographs and a video immediately in advance of commencement of construction. This is in order to document existing conditions such as signs, all entrances, side roads, ingress and egress of posted construction entrances, existing structures, electrical plant (e.g. traffic signals, highway lighting, power plants), other authority’s equipment such as hydro, bell, and railways.

4.2.8 Documents Copied to MTO

The following documents shall be provided to the Regional Operations Office: o All Change Orders, reports on delays, minutes of meetings o Instruction Notices to Design-Builder o Schedule updates, and comments back to the Design-Builder. o Extension of time requests o Accidents or claims from the public or property owners o Major issues or delays o Notification of lane closures/lane reductions (faxed at time of initiation/cancellation) o Contract related permits

14 Design-Build Administration Manual January 2014

o Notices of Non-Conformance o General correspondence and e-mail

All documents are to be distributed as indicated on the corresponding form when required.

4.2.9 Material Testing and Sampling

As per Contract Documents, Ministry Directives and Memoranda.

4.2.9.1 Samples for Testing

The CA is responsible for witnessing all Quality Assurance (QA) sampling and for monitoring the Design-Builder’s operation to check that sampling techniques, sample identification and delivery to the appropriate laboratory are in accordance with Contract Documents.

All samples are to be delivered within two (2) Business Days (unless otherwise specified in the Contract Documents), in a testable condition with proper identification (e.g. contract number, date sampled, material type, lot, sublot, contact person, etc.) and WHMIS shall be included with the sample(s) in accordance with applicable Dangerous Goods Legislation. The CA is to review deficiencies in these operations as identified by his staff and the laboratory and take appropriate action if problems arise.

The CA shall maintain a log of QA samples sent to the laboratories. This log shall include the lot numbers, sublot numbers, security seal numbers, witness name, date sampled, date the samples were received by the lab, and the date the test results were received from the lab. The CA is required to evaluate test results in a timely manner.

4.2.9.2 Referee Testing

When referee testing is requested by the Design-Builder, the CA shall notify the appropriate Quality Assurance Office (QAO) in writing within 1 Business Day. Where referee testing of concrete cylinders is requested the CA shall also immediately notify the QA laboratory so that cylinders are not disposed of.

The QAO shall provide the name and contact information for the referee laboratory to the CA.

The CA shall notify the QA laboratory in writing to deliver the samples to the referee laboratory and shall notify the Design-Builder and QAO as to the date of testing.

4.2.9.3 Application of Security Seals

The CA is responsible to properly apply security seals onto sample and keep a log of seals used and for what purpose (for inventory purposes). The CA shall enforce the Quality Control Compliance consequences associated with sub-standard sampling practices by the Design- Builder, including incorrect size sampling. The CA shall retain possession of the bags and seals until after the samples have been taken and all the required paperwork has been filled out and is in/with the sample . Once this is done the container can be placed in the plastic security and the CA/ Inspector can apply the locking seal. If samples are too hot (i.e. PGAC samples) to put in the plastic security bags, the CA shall retain possession of the samples until the bags and seals can be applied.

15 Design-Build Administration Manual January 2014

Security bags and seals shall be used with the following samples:

o Hot Mix Bulk QA and Referee samples o Hot Mix compaction core QA and Referee samples o Hot Mix Thickness Cores o CIR and CREAM Bulk samples o PGAC QA and Referee samples o Granular QA and Referee samples o Aggregate physical properties QA and referee samples o Concrete Pavement Cores o Concrete cores from bridge elements (new with Design-Build concrete specs) o CIR and CREAM compaction slabs

Security bags and seals may be applied to other types of samples, in special circumstances, at the direction of the CSA. However, such situations are expected to be infrequent.

Upon receipt of the test data, the CA shall verify the security seal identification provided with the tests results against those applied in the field.

MTO security bags and seals are supplied by the Regional QA Section. At the end of the Contract, the CA shall account for and return all unused MTO sample bags and security seals to the QA Section.

4.2.9.4 Contact with Laboratories

The CA must provide the laboratory with the pertinent contract details (contract number, WP number, phone and fax numbers and e-mail addresses for CA and for Design-Builder) as well as all pertinent information, which affects testing procedures (hot mix re-compaction temperatures etc.). The CA should clearly indicate what samples are to be tested and the specific tests required. The CA is responsible to check that if samples are to be delivered outside of normal business hours, the testing lab receives at least one (1)Business Days’ notice by the Design-Builder in order to arrange for personnel to receive the samples. For example, for delivery after business hours on Friday evening through Monday morning, the lab should be contacted during business hours on Thursday or earlier.

The CA shall investigate all sample non-conformance identified by the QA Lab, and shall provide written direction to the Design-Builder to resolve the problems(s) in a prompt and efficient manner, on the form provided. The CA is responsible for communicating such instances to the Ministry staff (i.e. CSA, QA Officer) as appropriate, and taking further administrative action as may be required by the Contract Documents.

The CA should liaise directly with the labs on routine matters as required, however, issues related to the performance of the Area and/or MERO Testing Labs (e.g. turn around times and quality of results) or any other related concerns shall be brought to the attention of the Head, Quality Assurance in writing (by e-mail).

Although most QA testing is done by the Area Testing Laboratories, some specialized materials testing is conducted through the MTO Materials Engineering and Research Office (MERO) as listed below. The CA shall meet with the QAO prior to the start of construction to determine which specialized materials testing will be required for the Contract:

16 Design-Build Administration Manual January 2014

Bituminous: Anti-stripping Additive Crack Sealing Quality

Concrete: Portland Cement, Hydraulic Slag or Fly Ash Material Quality Latex Modifier Quality Post Tension Cables Shotcrete Cores Bridge Deck Waterproofing and Protection Board Quality Hot Poured Rubberized Asphalt Joint Seal Quality Expansion Joint Seals Elastomeric/Rotational Bearings Structural Steel Material Quality Metal Wire Galvanizing Traffic Paint Quality (not thickness) Beads Quality Thermoplastic Pavement Markings Field Reacted Polymer Pavement Marking Pre-formed Pavement Marking Tape Stainless Steel Reinforcing Steel

Soils & Aggregates: Geotextile Quality

Foundations: Wick Drains Expanded Polystyrene Geogrids Slag

4.2.9.5 Review of Concrete and Asphalt Mix Designs

The CA shall review all concrete and asphalt mix designs for completeness, making sure all elements of the proposed mix are included in the submissions as per the Contract Documents. The mix design package, including the independent Superpave Mix Design Verification, shall be scanned and saved into a single “PDF” format file and submitted to the Head of QA together with a summary of the review indicating compliance with the Design-Builder’s design and Contract Documents within four (4) Business Days of the design being properly submitted by the Design-Builder. The procedures for processing concrete mix designs are given in HOC #2005-02, Acceptance and Use of Concrete Mix Designs.

4.2.9.6 Review and Submission of Test Results

Where material is to be tested for acceptance, the CA is responsible for determining if the material meets the requirements of the Contract Documents. The role of the lab is only to provide raw data and not determine acceptability.

After review by the CA, copies of test results should also be sent as detailed in the “Guidelines For Test Result Submissions” to the Head of QA (as determined by the Regional Operations

17 Design-Build Administration Manual January 2014

Office). Test results are to be submitted within four (4) Business Days of the results having been submitted to the CA or within four (4) Business Days of the samples being available for testing in cases where the CA is responsible for testing. The Design-Builder shall monitor, record and check that the test result submissions are meeting the required time frames. All test results to be submitted in PDF format.

All submissions must be sent with an appropriate cover letter, identifying the material represented, the acceptability of results, and any actions required by the Design-Builder as a result of not meeting the specification requirements.

For materials that are decisioned using lots and sublots the CA must calculate approximate quantities based on the Design-Builder’s design(since Design-Build projects are Lump Sum bid and exact quantities are not disclosed during tendering) in order to develop a lot and sub-lot system for the purpose of acceptance testing. Prior to the start of construction, the CA and the Design-Builder must establish and agree on lot and sub-lot size. Individual QA test results need only be submitted to the CSA when the results are outside of specified requirements (e.g. low cylinder breaks). These submissions should be accompanied by comments regarding any action that is being taken.

The “Guidelines for Test Result Submissions” has been developed (see below), as an aid to the CA in order to more clearly identify which test results must be submitted to the Ministry. It is a general list that is to be used in conjunction with the Contract Documents and does not include all possible items which may be required to be submitted. If a conflict exists between the list and the Contract Documents, then the Contract Documents take precedence.

4.2.9.7 Year End Summaries

Using the CA’s approximate quantity calculations based on the Design-Builder’s design, Year- end approximate totals of Granular, Concrete, and Bituminous materials are to be submitted by the CA to the Regional Quality Assurance Office in electronic form no later than 30 Days from last placement of the relevant material. For carry-over contracts, approximate running/progress totals shall be submitted at the end of each calendar year (by December 31) for the work completed to that date. The summaries shall include the completion of forms provided by the Ministry for that purpose.

4.2.9.8 Guidelines for Test Result Submissions

ITEMS DETAILS OF SUBMISSIONS Bituminous

Smoothness Sketch of sublot locations and list of approved exempted sublots Summary of results on the Summary Acceptance Forms to be submitted electronically including scallops. This includes profiles taken for sublots re-tested Summary of audit data as specified in the “FIELD GUIDE FOR THE ACCEPTANCE OF HOT MIX AND BRIDGE DECK WATERPROOFING”

Smoothness Sketch of sublot locations and list of exempted sublots indicating By Inertial Profiler stations on both Request for inertial profiler for QA/re-test/referee testing

18 Design-Build Administration Manual January 2014

ITEMS DETAILS OF SUBMISSIONS Summary of IRI results on the Summary Acceptance Forms to be submitted electronically including localized roughness. This includes profiles taken for sublots re-tested Final summary of payment for the entire lot.

Hot Mix Aggregates QA results Physical Properties Referee results if applicable Pavement markings Pavement Marking forms (glass bead application rates, paint thickness, paint quality samples taken and submitted) to be submitted within 30 Days of completion of pavement marking Segregation Listing of areas of segregation including a description of severity as required by the “FIELD GUIDE FOR THE ACCEPTANCE OF HOT MIX AND BRIDGE DECK WATERPROOFING” Miscellaneous QA test results Asphalt Products Referee results if applicable

PGAC Granular sealing Rout and Seal Tack Coat Anti-strip etc Granular Granular O, A, B, QA test results SSM Referee results if applicable Physical Properties Granular O, A, B, If referee testing is invoked, the final spreadsheet including referee SSM data shall also be submitted Production Samples Compaction Checks Monthly summary of QA compaction results and summary of acceptability on PH-CC-011 MTO QA Compaction Summary Sheet Trial Strip/Proctor results and QA/QC correlation results to be submitted upon completion Reinforced Earth All QC data required by the Contract Documents. Walls Miscellaneous Soils QA test results and Aggregates Referee Results if Applicable Products

Geotextiles Seeding etc Concrete & Structural Items Compressive Spreadsheet with acceptance analysis (strength acceptance Strength Results requirements in DBSP1350)to be submitted electronically monthly and upon completion of each lot for each class of concrete. Temperature Records QA audit Cold and Hot weather temperature records after completion of the curing and protection (if applicable) period. Temperature records for HPC after completion of curing (and protection) period. Concrete Aggregates QA results Physical Properties Referee results if applicable

19 Design-Build Administration Manual January 2014

ITEMS DETAILS OF SUBMISSIONS Air Voids in Hardened QA test results; Concrete Referee test results if applicable Tensile Bond Test QA test results Rapid Chloride QA test results Permeability (if Referee test results if applicable applicable to Contract)

Covermeter Survey Completed Survey together with calculated summary (ie. mean, standard dev etc). Make and model of covermeter used to be indicated Waterproofing Copy of Thickness Report and adjustment factor calculations. Material Quality test results for membrane and protection board Half Cell Survey Copy of Half Cell Survey and continuity check form to be submitted to QA and Regional Structural Office (or as indicated by CSA).

Note: Submitted immediately upon completion of field testing and prior to initiation of removals Water test for Copy of form. Copies to include a c/c to the Regional QA section expansion joints (if and the Bridge Office. applicable) Proprietary Products On an as required basis - Name of product - Test data for compressive strength, rapid chloride permeability, shrinkage and tensile bond or as per specification -Type of repair it is being used for. -Design-Builders proposal for use Structural Steel QA/QC data as required by SPs plus Daily Coating Reports and Coating Summary Report and CA Agreement deliverables. Miscellaneous QA Test results Concrete Materials Testing Referee Results if applicable

Portland Cement, Hydraulic Slag / Fly Ash Curing Compounds Admixtures, Air Entraining Expansion Joint Seals Elastomeric Bearings Post Tension Cables Grout results Hot Poured Rubberized Sealant

4.2.9.9 Engineering Materials Field Testing Reference Table

20 Design-Build Administration Manual January 2014

Material Field Test Reference Document(s) This guide and specifications Earth Compaction in the Contract Documents. This guide and specifications Granulars Compaction in the Contract Documents. Review Mix-Design Hot Mix Contract Specifications Documentation Hot-In-Place Recycling Contract Specifications

Cold-In-Place Recycling Contract Specifications

Macrotexture (Sand Patch) Field Guide QA testing of pavement This guide and specifications

smoothness (IRI method) in the Contract Documents. Expanded Asphalt Contract Specifications Guidelines for Conducting Concrete Half Cell Survey Half Cell Surveys Guidelines for Conducting Covermeter Survey Covermeter Surveys Review Mix-Design Contract Specifications Documentation Field Guide For The Bridge Deck Waterproofing Acceptance Of Hot Mix And Thickness Bridge Deck Waterproofing Dowels in Concrete - Pull

Testing QA Audit Check on pavement This guide and specifications Concrete Smoothness (profilograph) in the Contract Documents. Guidelines for Sampling and Miscellaneous Traffic Paint Thickness Testing of Pavement Markings Glass Bead Distribution GSTPM

4.2.10 Quality Assurance Frequency of Monitoring / Audit Checks

o Check that the Design-Builder provides the deliverables as per the Contract Documents in a timely and accurate manner o Review the QVE process

4.2.11 Off-Site Inspection of Structural Items

o Prior to Construction, the CSA in conjunction with the Project Leads shall determine if there are elements requiring off-site inspection. If these off-site inspections are going to be outsourced, adequate work plan requirements shall be included in the specialist’s terms of reference or the Contract Administration Agreement(when all CA services are outsourced). In addition, adequate amount of hours shall be allocated depending on

21 Design-Build Administration Manual January 2014

quantity of material and specification requirements (Examples: Pre-Cast Beams, Structural Steel and Aluminium Sign Supports). o During construction/fabrication, the CSA, or CA in consultation with the CSA, shall decide on the delivery of the CA’s specialty work plan depending on the Design-Builder’s schedule of fabrication and based on the terms and conditions in the CA Agreement.

4.2.12 Geotechnical

Review the Design-Builder’s responsibilities for administering non-commercial pits and quarries and the CA’s responsibilities for monitoring the Design-Builder’s activities. These responsibilities include but are not limited to:

Prior to Construction:

o Review the Aggregate Sources List and confirm the availability of each source proposed by the Design-Builder for use on the Contract. o Review the operational and rehabilitation plans of the Design-Builder prior to them being submitted to the Regional Geotechnical Section for review and approval. o Regional Geotechnical Section will provide two copies of the approved site plan to the CA. One copy is provided to the CA for inspection purposes and one copy is provided to the Design-Builder for direction on operation of the source.

During Construction:

o If the Design-Builder proposes to make an amendment to the approved site plan, the amendment must be reviewed and approved by the Regional Geotechnical Section prior to any operational changes taking place. o The Design-Builder shall simultaneously inform the CA when a request for an amendment is submitted to the Regional Geotechnical Section. o Two copies of this new approved site plan will be forwarded to the CA as above for distribution. By following this process the CA will have the most up to date approved site plan on hand for their daily inspection. Any amendments that are contentious in nature should be relayed to the Design-Builder via an Instruction Notice. o Once the pit and quarry activities have concluded, the CA shall ensure that the Design- Builder has rehabilitated each source as per the approved site plan prior to the Design- Builder leaving the source. o At the conclusion of the contract, or annually on December 31 for multiyear contracts, the CA shall submit to the Regional Geotechnical Section form PH-D-046 Pit and Quarry After Use Report for all sources used on the Contract for both non-commercial and commercial sources. Any tonnages derived from ROW production of aggregates shall also be reported at this time: For Design-Build contracts, the CA must utilize appropriate survey resources to obtain before and after elevations/topography in order to calculate the volumes used by the Design-Builder during the execution of the Work, and confirm/audit design forecasts from the designer; appropriate density values provided by the Regional Geotechnical Section shall be used to convert to tonnages

4.2.13 Electrical

Electrical quality assurance shall include the ongoing and final inspection of, but not limited to the following: o Overhead lines;

22 Design-Build Administration Manual January 2014

o Cathodic protection; o Periodic inspection of highway electrical systems, such as highway lighting, traffic signals, and vehicle detection equipment; o Spot-checking validity of Design-Builder-issued certificates, pre-installation testing, and proof of performance testing. o Electrical quality assurance activities pertaining to Design-Builder electrical maintenance activities shall continue during winter shutdown o Receive and review traffic signal PH-M-125 drawings

4.2.14 Post Pipe Installation Inspections

Quality Assurance of Post Installation Pipe Inspections shall be performed as detailed in 104S02. The inspections shall be carried out by the CA as specified.

o Post installation inspection service to be performed by a certified inspector. Receive list of completed gravity pipe installations from Design-Builder who has certified them as ready for inspection (the Certificate document shall be in a format acceptable to the Ministry and including the details specified in the Contract Documents o Arrange for date or dates that pipe inspection service will be on site to do inspections and notify Design-Builder of inspection dates o Compile inspection results (CA to input into excel spreadsheet available from MTO) o Submit inspection results to Design-Builder o Possible actions afterwards o Design-Builder requests referee inspection (repeats steps 1 through 5 with another inspection firm) Referee requests limited to 1 batch submission – cannot request referee on a refereed inspection; o Confirm replaced or repaired pipes required as a result of inspections o Notify Design-Builder of additional inspections should initial inspection triggers indicate non-satisfactory inspection results(repeats steps 1 through 6) o Notify Design-Builder of more additional pipe inspections(all remaining pipes) should additional inspection triggers indicate non-satisfactory inspection results(repeats steps 1 through 6) o Forward to MTO the CA’s analysis of test/inspection results and acceptance analysis, including consequences, associated with the culvert specifications in the Contract Documents

4.2.15 Environmental

Compliance with the project environmental requirements as noted below are necessary to meet the requirements of environmental statutory duty of environmental due diligence on behalf of the Ministry, including but not restricted to, compliance with the ‘Class Environmental Assessment for Provincial Transportation Facilities’ (2000). Environmental statutory duty is outlined in Section 1.7.3 of the Class EA and environmental protection and monitoring requirements during construction are outlined in Section 4.8 of the Class EA. The penalties for not demonstrating environmental due diligence can be severe, including substantial monetary fines and jail terms.

Specific environmental requirements for administration, including monitoring the Design- Builder’s day-to day operations, and considering any Design-Builder proposals, are provided below. For the purpose of clarity in meeting these requirements or in completing the Environmental Specialty Work-Plan if required, the environmental inspection tasks are detailed

23 Design-Build Administration Manual January 2014

in Part B of this Manual and the project environmental requirements for construction administration are detailed below.

4.2.15.1 Environmental Requirements of Project-Specific Environmental Assessment Process Documentation and Construction Contract Documents

The CA shall review with the CSA all project specific Environmental Requirements.

The CA’s role is to ensure the Design-Builder meets all environmental requirements of the Contract Documents including the Environmental Management PERF 1072 and shall strictly apply the specified consequences during construction and at completion of the Work. In the event of any non-conformances to the environmental requirements in the Contract Documents:

o The Design-Builder shall be notified of consequences and instructed to take appropriate corrective actions; o The Implementation of the corrective actions shall be confirmed; and o Infraction Notices shall be issued in compliance with Ministry policy where corrective measures are not implemented as instructed.

The CA is encouraged to consult any and all available environmental assessment process documentation that is available for further information on the environmental provisions contained in the Contract Documents and their purposes.

4.2.15.2 Project Environmental Protection / Mitigation / Compensation Measures

The CA shall assess the effectiveness of project environmental protection, mitigation and compensation measures as included in the Contract Documents to determine that:

o Protection / Mitigation / Compensation measures are: – In place as required; – Appropriate to the protection / mitigation / compensation required; – Functioning properly and maintained as specified; and – Removed where required at the end of construction.

o Operations, equipment and materials are:

– On-site where they are permitted; – On-site when they are permitted; and – Occurring and / or being used or applied as permitted.

4.2.15.3 Formal Environmental Approvals and Timing Constraints

The construction shall be monitored by the CA to determine compliance with project-specific environmental permits / approvals (e.g. federal Navigable Waters Protection Act permits and Fisheries Act authorizations).

24 Design-Build Administration Manual January 2014

4.2.15.4 Environmental Documentation Requirements

There are a number of environmental documentation requirements that the CA is responsible for, that require completion and submission of the following, during or after construction:

o CA / Inspector’s Environmental Diary o Detailed Specialty Reports (under Environmental Specialty Work Plan, if applicable) o Class EA Process Monitoring Questionnaire for Contract Administration Staff’

“Summary of Environmental Concerns and Commitments” Table

The CA shall use the blank spaces provided in the ‘Summary of Environmental Concerns and Commitments’ table, to document the Design-Builder’s compliance with the environmental provisions of the Contract Documents as summarized in the table. This table shall be updated on a regular basis, as this is a living document.

Upon construction completion, the completed Summary table, along with the ‘Environmental Synopsis’ provided by the Design-Builder, will be used to report on how well environmental assessment commitments were met through compliance with, and the effectiveness of, the environmental provisions in the Contract Documents. As such, confirmation that this table has been completed is part of the Contract Closing Process section of this Manual.

CA / Inspector’s Environmental Diary

A separate Environmental Diary shall be maintained to record the following: o The Design-Builder’s compliance / conformance and non-compliance / non-conformance with environmental timing constraints and action taken to address them, as well as related communications with agencies; o The Design-Builder’s environmental protection measures and their effectiveness, including successes, deficiencies, instructions given and results of corrective actions taken; o Spills or other environmental incidents that the Design-Builder is responsible for, including, but not restricted to details about when the incident took place, actions taken or intended to be taken by the Design-Builder regarding the incident such as containment of spills, notifications made to proper authorities, actions taken to clean up and restore the environment to pre-incident conditions, investigations, charges, stop work orders and remedial instructions by regulatory agencies, and environmental complaints by the public. A copy of the Incident Notification Form (PH-CC-818) that the Design-Builder is required to submit to the Ministry within 48 hours of the incident should also be kept with these notes in the diary. o The discovery of existing environmental conditions such as archaeological finds and materials suspected of being contaminated including all relevant details as to what was found and actions taken by the Design-Builder to notify the CA and/or the Ministry and secure the site for investigation.

Class EA Process Monitoring Questionnaire for Contract Administration Staff

The information used to complete the ‘MTO Class EA Process Monitoring Questionnaire for Construction Administration Staff’ shall be completed from, but not limited to: investigations / charges, stop work orders, remedial instructions from regulatory agencies, and public complaints as documented in the Environmental Diary. Two copies of the completed

25 Design-Build Administration Manual January 2014

questionnaire shall be provided to the Ministry including one that shall be submitted to the MTO Environmental Planner for the project (see form for more details).

4.2.15.5 Environmental Notifications

The CA shall make the following Environmental Notifications to the Ministry immediately after the Design-Builder notifies the CA.

o In the event that the Design-Builder notifies the CA in accordance with section GC 3.07.05 of the General Conditions of Contract, that it is suspected that an archaeological find, such as building remains, hardware, accumulations of bones or other human remains, pottery, or arrowheads has been encountered during construction, the CA shall notify the CSA and the MTO Environmental Planner. At the direction of the CSA, the Service Provider CA shall engage a licensed Archaeologist to visit the site to assess and verify the find and determine a course of action. The Archaeologist on-site will also be responsible for contacting other appropriate authorities, including the Police, Ministry of Culture and the Ministry of Government Services, if they determine that human and/or archaeological remains have been encountered.

o In the event that the Design-Builder notifies the CA in accordance with OPSS 180 that materials suspected of being contaminated (e.g. stained or odorous soil, oily sheen on water in an excavation) have been encountered during construction, the CA shall notify the CSA and the MTO Environmental Planner. At the direction of the CSA, the Service Provider CA shall engage an environmental specialist, who specializes in contaminated property identification and management, visit the site to investigate and determine a course of action. The environmental specialist will also be responsible for contacting MOE as deemed necessary in consultation with MTO.

o In the event that the Design-Builder notifies the CA that a Species at Risk has been encountered during construction in accordance with section GC 3.07.06 of the General Conditions of Contract, the CA shall notify the CSA and the MTO Environmental Planner. At the direction of the CSA, the Service Provider CA shall engage an environmental specialist, who is qualified to identify Species at Risk, visit the site to verify the species and determine a course of action. The environmental specialist will also be responsible for contacting MNR as deemed necessary in consultation with MTO.

4.2.16 Traffic Management and Public Information Services

The CA shall check that all Traffic Management and Public Information Services and Deliverables in the Contract Documents or required by law are complied with (including the requirements of the Traffic and Mobility PERF 1077 and Information Management PERF 1075). To determine compliance with the traffic control plan requirements of the Contract Documents the CA shall:

Prior to work starting: o Instruct the Design-Builder to provide a copy of their health and safety policy and program, which includes the traffic control plan for the Contract, to the CA at the pre- start meeting o Assess the Design-Builder’s Traffic Control Plan, to check that all requirements of the Contract Documents including, but not limited to, those in the Ontario Traffic Manual (OTM) Book 7 Temporary Conditions, the Ontario Traffic Manual (OTM) Book 7

26 Design-Build Administration Manual January 2014

Temporary Conditions (Field Edition), the Occupational Health and Safety Act and any specific traffic control requirements of the Contract Documents are complied with and provide satisfactory levels of safety for workers and motorists;

During construction:

Monitor the traffic control measures implemented by the Design-Builder to determine that the actual measures are consistent with those shown in the Traffic Control Plan and Contract Documents, and that the measures provide satisfactory levels of safety for workers and motorists.

The minimum frequency of this monitoring for the first 24-hour period any traffic control measures are in place, shall be:

o Once during the period immediately following the installation of the measures; o Once during the period one half hour before sun rise; o Once during the day-light period; o Once during the period one half hour after sun set; and o Once during the night time (dark period).

The minimum frequency for this monitoring, after the initial 24-hours, shall be such that:

o At least two (2) of the above noted daytime periods are monitored each 24-hours, and; o Each period has been monitored twice during the normal work week; and o Each period has been monitored twice during the weekend period. o Assess the effectiveness of the traffic control measures used by the Design-Builder, during the first 24-hour monitoring periods each time a new traffic control set up is placed or after any alteration to an existing set up, to determine that: o The traffic control measures implemented by the Design-Builder are what is needed; in place when needed; positioned where needed; and are working as required; o Operations, equipment and materials are only where they are permitted; occurring/operating/placed when they are permitted; and are doing what is permitted; deficiencies are corrected when they are needed by using what is needed; and doing it where it is needed; o Notify the Design-Builder of any deficiencies identified in the traffic control measures, instructing the Design-Builder to take appropriate corrective measures and confirming and reporting the results of the corrective measures; o Provide a copy of the Design-Builder’s traffic control signing diary, to the Ministry, on each Monday or day following a holiday for the preceding week or more frequently if requested by the Ministry; o Check that Design-Builder’s site supervisor performs traffic control/lane closure notifications including co-ordinating traffic management and public communications with other roadway work in the vicinity of the project; o Provide notification to local media and the Ministry of any potential traffic delays, and on termination of the delay or associated activity, the CA is to immediately notify the Project Lead of instances that involve fatalities or serious injuries; o Maintain adequate Public Traffic Staging Records including review of proposed staging plans sufficient to document and support all actions taken; o Maintain adequate Public Notification Records sufficient to track all notifications;

27 Design-Build Administration Manual January 2014

o Providing a record of traffic accidents, public notifications and complaints that occur in the work zone, in all cases, a copy of all documentation is to be provided to the Ministry within the same Business Day as the traffic incident occurs; o Videotape haul road conditions prior to use by the Design-Builder; and o Perform all traffic control related tasks listed in the Contract Administration and Inspection Task Manual. o Monitor the Design-Builder’s operations for compliance with Ministry safety policies concerning the provision of safe passage for the travelling public.

In all cases, any communication between the Design-Builder and/or the Contract Administration staff and/or the Ministry shall be by verbal and written means, and a copy of all documentation is to be provided to the Ministry within the same Business Day as the communication occurs.

4.2.17 MTO Roles

o CSA – approvals, mediation, check compliance with Contract Administration Agreement, monitor CA’s performance and report to Operations office. Monitor service provider’s conformance to the construction Contract Administration Agreement, provide procedural information, and provide contact names for various offices in the region. o Quality Assurance – advisors, information resources (including maintenance coordinators and electrical coordinators), provides technical expertise to senior Operations and Design-Builder field staff through the CSA. o Project Leads – approvals, continuity of design and construction

4.2.18 Contract Administrator’s Performance Appraisal

o Review the Performance Evaluation form. o Random checks to monitor CA’s performance and adherence to the agreement, Services and Deliverables and records (select date for initial review). o A Contract Payment and Records Assessment may be performed on payment records and documentation after Contract Completion. When recommended in the CPRA Report, the CA Appraisal will be reviewed for potential adjustment of the rating.

4.2.19 Well Investigations The CA is to check the applicable reference documents (including Directive OPR-C-002 (21/05/2004), and to ensure that:

o Design-Builder reviews/adheres to the requirements in the Contract and the environmental assessment process documentation. o Design-Builder follows the “Guidelines For Drinking Well Water Sampling And Testing In Ministry of Transportation Activities”.

4.2.20 Project Construction Report

o Maintain documentation during construction to assist in preparation of the project construction report. o Follow format of most current Head Office Construction Memorandum for Project Construction Report

28 Design-Build Administration Manual January 2014

4.3 CONTRACT AWARD

Reference: o Provincial Highways PHY-B-152 Commencement of Work by a Contractor

The “Designation of Construction Zone” Form shall be completed and submitted by the Project Lead before the start of construction.

4.4 CONSTRUCTION PRE-START MEETING

The Construction Pre-Start meeting is held before the start of any construction work.

The Design-Builder shall chair the meeting and arrange for the minutes to be taken and distributed. However, the CA shall ensure important items are discussed during the meeting as per this guide. The agenda provided by the Design-Builder should be reviewed in advance by the CA to ensure all appropriate items outlined in this guide are covered. CONTRACT NO.: LOCATION: DATE: PLACE:

The CA should ensure the following representatives have been invited by the Design-Builder:

NOTIFIED ATTENDANCE ADMINISTRATIVE REPRESENTATIVES Yes No Yes No CSA Construction Contract Administration Project Manager (if CA by Service Provider) Project Lead (Planning and Design Project Manager) Project Lead (Operations, Area Contracts Engineer) Head of Operational Services Representative (local patrol, sign shop, electrical, etc.) Ministry of Labour Head, Regional Quality Assurance Road User Safety Regional Environmental Section Regional Structural Section Foundations Office Regional Electrical Section Regional Geotechnical Section Regional Traffic Section Regional Advanced Traffic Management Section Ontario Provincial Police

29 Design-Build Administration Manual January 2014

Regional/Municipal Police External Environmental Agencies (MOE, MNR, Conservation

Authority, DFO, etc.) The following should be notified if applicable to the Work: Emergency Services (Fire Response, Ambulance, etc.) Local Traffic Authorities Local Transit Authorities Municipality Road Superintendent Railway Representative MTO Property Office (if limited interest, or other) Health and Safety Representative Regional Construction Administration Office (to be notified) Utilities (Please identify) Others (Please identify)

The following information should be obtained/reviewed through the meeting:

Administration and Staffing

A-1 Identify Design-Builder’s Site Representative and alternates with signing authority.

A-2 Identify the location of the Design-Builder’s field office and yard.

A-4 Identify the location of the CA’s field office.

A-5 Assemble the emergency 24-hour phone numbers: Ministry (CSA and Project Lead) and the Design-Builder (minimum two (2) representatives). Copies of the emergency name, position and phone numbers to be sent to the Regional Construction Office, O.P.P., Regional or Municipal Police, MTO or AMC Patrol, Area Office and/or Radio Room/COMPASS Centre with contract number and location.

Ministry of Labour

L-1 Address any concerns identified by the Ministry of Labour.

Road User Safety (RUS)

Discuss Weighing and Overloading Issues

D-1 Outline that the Design-Builder is responsible for any overloading that occurs on the Contract, and that the Ministry RUS Section will monitor compliance.

D-2 Indicate that the CA will notify RUS when overloading is suspected.

30 Design-Build Administration Manual January 2014

D-3 Request the haul routes proposed by the Design-Builder and outline the Design- Builder’s responsibilities (load limits, responsibilities of Design-Builder, local by-laws, etc.)

D-4 Address any concerns of Drivers & Vehicles

D-5 Discuss CVOR General Condition 7.06.01

Area/Regional Operations

O-1 Review and discuss concerns of Operations Office (maintenance)

Environmental

E-4 Ask the Design-Builder to identify any area that they plan to disturb outside the specified limits of the Work (access, storage, disposal, work yard, etc.). Remind the Design-Builder that the selection and use of any such areas must comply with Environmental laws as well as environmental assessment and environmental permit / approval requirements / commitments.

E-5 Review the key environmental requirements of the Contract Documents. Advise the Design-Builder that, with respect to statutory environmental requirements and prohibitions, they are responsible for providing environmental protection measures that are required solely because of the choices made by the Design-Builder with respect to construction means, methods, techniques, sequences and procedures.

E-6 Remind the Design-Builder that applicable environmental forms in the Contract Documents or provided by the CA must be completed and submitted to the CA with regard to the following: o Use of sites for disposal or storage of “disposable fill” (per OPSS 180); o Shipment of hazardous waste (MOE Reg. 347 Waste Manifests); o Use of air-cooled blast furnace slag as granular material; o Incident Management Form to document spills and other environmental emergencies (PH-CC-818): and o Fisheries Act Authorization – Oversight, Monitoring and Documentation (MTO SP199F58) o Copy of applicable contract related permits (such as water taking)

E-7 Remind the Design-Builder that applicable environmental timing constraints must be complied with as specified in the Design-Builder’s Environmental Plan, and the contract specifications (including PERFs) and “Summary of Environmental Concerns and Commitments” Table. The following list is a guide and the CA must review specifics to the Contract Documents:

o Maximum time between removal of original vegetative surface cover and placement of final cover; o Timing requirements for replacement of straw bales in sediment barriers and flow checks; o Requirement to check that temporary erosion control measures are in effective working order prior to forecast storm events and following a storm event; o Fisheries timing constraints; o Control of construction noise in noise sensitive areas;

31 Design-Build Administration Manual January 2014

o Migratory Birds Act / timing constraints and requirements for netting, if required

E-8 Request submission of any environmental drawings or plans that are required by the Contract Documents, including Design-Builder proposals for dewatering procedures or in water work. Explain the review process and the time required for any approvals.

E-9 Identify the designated inspector who will monitor environmental protection/ mitigation and maintain an environmental diary.

E-10 Obtain Design-Builder’s contact names, positions and telephone numbers for the following: o The Design-Builder staff to be notified for follow-up of any environmental accidents/incidents/problems both during the Work and during periodic/ seasonal shut- downs; o The Design-Builder staff person ultimately responsible for meeting statutory environmental duty in the event that regulatory agencies wish to pursue any problems: and o If required by the Contract, the name and firm of the qualified Fisheries Contracts Specialist.

E-11 Identify the requirements of the MTO General Conditions of Contract with respect to Incident Management Under Legislation Protecting the Environment and Natural Resources.

Traffic

T-1 Review the Design-Builder’s responsibilities with respect to traffic, staging, detours, traffic control, maintenance of traffic, signing as per Ontario Traffic Manual (OTM) Book 7 Temporary Conditions, Freeway Detour Signing Guidelines, safety precautions, and special provisions (e.g. Traffic and Mobility Management PERF 1077, Traffic Control Signing, Hours for Lane Closures, Maintenance of a Traffic Control Diary, etc.).

T-2 Review PHM125 Drawings.

T-3 The Design-Builder team shall have performed bridge clearance verification during the development of its design. The specified minimum clearances (horizontal and vertical; protocol for advising about clearances) must be maintained in accordance with the Contract Documents, including the Design-Builder’s Issued for Construction Drawings. Any vertical clearance of less than 4.5m must have been identified by the Design-Builder during the design and the Regional Structural Section and RUS and Manager of Regional Operations notified. The Pre-construction bridge clearances for each lane and for shoulders must be verified by the CA, shared with the Design-Builder and forwarded to Regional Structural Section prior to Construction. The Design- Builder must provide an opportunity for the CA to obtain the verification measurements.

T-4 Make the Design-Builder aware of their duties with respect to construction and traffic safety, and to abide by the Occupational Health and Safety Act.

T-5 Review with the Design-Builder any reduced speed zones to be in effect (if applicable) and confirm submission of required documentation;

T-6 Review the concerns of any other interested agencies.

32 Design-Build Administration Manual January 2014

T-7 Facilitate the advance notification of closures, detours, etc. to be provided to emergency services, municipalities, transit authorities, etc.

Quality Assurance

QA-1 Discuss the requirements for properly managing non-conformances to QC Performance Measures and the consequences of major and minor deviations.

QA-2 (Pre-paving meeting)

QA-3 (Pre-placing meeting for concrete)

QA-4 Advise the Design-Builder that all structures are to be inspected by the Regional Structural Section a minimum of three (3) weeks prior to opening to traffic, with the exact time determined by construction field staff with the Design-Builder’s assistance.

QA-5 Advise the Design-Builder the name and location of the QA lab including the applicable advance notification of sample delivery (e.g. 24 hrs)

Structural / Foundations

S/F-1 N/A

S/F-2 Check on Regional Structural Office requirement for notification of oversize load restrictions through structures including clearance restrictions (Form OSCLIS.xls in applicable regions).

S/F-3 Discuss schedule of off-site inspections for structural components.

Geotechnical

GT-1 N/A.

GT-2 N/A

GT-3 Advise the Design-Builder of legislative responsibilities and Ministry process for operating non-commercial pits and quarries.

GT-4 Review disposal areas to confirm volumes and environmental suitability.

General

G-1 Submissions required from the Design-Builder: o Sub-Contractor’s forms: Consent to Sublet (PH-CC-742); o Design-Builder’s work schedule and weekly work schedules, or acknowledgement of critical path schedule in writing; o List of material sources for all materials supplied by the Design-Builder, including suppliers for concrete, hot-mix, granular materials and manufactured products, including approved Designated Sources for Material (DSM) references;

33 Design-Build Administration Manual January 2014

o Current Workplace Hazardous Materials Information System (WHMIS) documentation and Material Safety Data Sheets for designated materials must be submitted to the CA prior to the commencement of construction; o Samples for testing in appropriate affixed with complete and accurate identification labels and WHMIS labels. Check that labelling and placarding of goods under the Transportation of Dangerous Goods Act is carried out; o Concrete and Asphalt mix designs including supporting documentation, to be reviewed as per the Contract Documents(CA’s review is different in PERFs: verify that all elements listed in the submission requirements are provided, not an approval); o Permits required (pit or quarry permits for aggregates and borrow, environmental permits/approvals, forest resources licence prior to harvesting trees within a crown land pit or quarry boundary); o Other submissions required by the terms of the Contract Documents.

G-2 Review by Design-Builder of Design-Builder’s design package (Issued for Construction Drawings, special provisions, specifications, etc.):discuss any provisions, unique problems, Ministry commitments and constraints to the Contract; o Instructions from the CA must be adhered to in all cases. Disregarding verbal instruction will result in written notices, and could ultimately result in an Infraction Report being issued.

G-3 Remind the Design-Builder that contract layout is to be done by the Design-Builder. The Design-Builder team shall, in conjunction with the CA: o Review requirements of special provisions and any new initiatives; o The Design-Builder shall have verified of the location and number of co-ordinate bars, benchmarks and alignment ties during the design phase. (Hand over horizontal and vertical control sheets must have been produced). The CA must request any Pre- engineering survey data that was developed by the Design-Builder; o Review requirements for submission of Record Drawings data and drawings (red-line revisions) for the Contract. Digital files for contract drawings should be generated/available by the Design-Builder for this purpose; Replacement of layout (property bars, benchmarks, etc.) destroyed by the Design-Builder will be the responsibility of the Design-Builder; o Review milestone field review requirements and submission procedures; o Remind the Design-Builder of their responsibility to carry out a pre-blast survey.

G-4 Utility Work (Special Provisions) o Remind that the Design-Builder is responsible for obtaining stake-out of existing Utilities; o Remind the Design-Builder to provide proper notification to Utilities, in advance of any Work affecting their plant; o Remind the Design-Builder to abide by the O.H.S.A. (Constructor Issue); o Review compliance with Operational Constraints relating to Utilities. o For excavation and construction near pipelines, co-ordinate, communicate and consult with the High Pressure Gas Utility company.

G-5 Property o Remind the Design-Builder to review any property restrictions, expropriations, easements, clearances or restrictions, and Permission to Enter agreements. Review the terms of each property agreement (if applicable).

34 Design-Build Administration Manual January 2014

G-6 Railways o Receive proper notification from the Design-Builder in order to make arrangements with railway officials; o Confirm that appropriate insurance requirements are in place as per special provisions or the railway requirements; o Check that the Design-Builder advises the railway authority when working within the railway right-of-way.

G-7 Contract Meetings o To be held at regular intervals, determine schedule.

G-8 Correspondence o All Contract correspondence must flow through the CA.

G-9 Changes in the Work o Check that the Design-Builder advises of any change in the Work under the terms of the Contract Documents. The Design-Builder is not required to proceed with the change in the Work until a Change Order has been issued. The Change Order will establish the method of payment. Utilize the appropriate method of payment for Design-Build contract as per the General Conditions in the Contract. The following methods should be used as method of payment when possible:

– Revised tender prices, or by negotiated unit price (for a new item) – Lump sum; – Time and Material a) Equipment rates will be as per OPSS 127 unless otherwise approved by the Project Lead. The Design-Builder shall supply an equipment list with sufficient detail to establish 127 rates; b) No labour premium payment (e.g. overtime, shift premium) will be made without prior approval of the CSA/ACE (Construction Project Lead); c) Time and Material Summary For Payment, and all supporting invoices, etc. are to be forwarded to the CA for verification prior to invoicing for payment.

o The Design-Builder may apply for an extension of time in accordance with the MTO General Conditions of Contract regardless of the method of payment.

G-10 Work Directive Discuss process for issuing a Work Directive when there is a dispute as to whether a Change Order should be issued.

G-11 Progress Payments Discuss and confirm the payment process and approach.

G-12 Damage to Permanent or Temporary Installations Review MTO Provincial Highways Directive PHY-B-102. Advise the Design-Builder of the safety and legal aspects of installations.

G-13 Claims by Motorists, Property Owners, etc. Advise that all claims during the construction period will be forwarded to the Design-Builder.

35 Design-Build Administration Manual January 2014

G-14 During the construction season the Design-Builder is responsible for maintenance of the highway infrastructure within the construction zone as per the General Conditions of Contract. Form PH-CC-771 Turnover Agreement shall be filled out in order to transfer the responsibility. A minimum of 5 Business Days prior to anticipated transfer date the CA, Design-Builder and representative of MTO maintenance shall perform a pre-turnover field inspection. The pre- turnover field inspection shall identify deficiencies within the right-of-way and timeframe for correction.

Note: The transfer of the Roadway maintenance does not relieve the Design-Builder from the responsibility of the Work he has performed. The Contract may require the Design-Builder to perform routine and non-routine maintenance activities on electrical systems (i.e. traffic signals and highway lighting) during a shutdown

G-15 Substantial Performance and Contract Completion Review MTO General Conditions of Contract. The Design-Builder shall provide notice to the CA at substantial performance.

G-16 Design-Build Contractor Performance Rating Report • Review the process for compiling the report and the impacts of assessments. • Determine what work is to be performed under OPSS and what work is to be performed under PERF specifications. • Determine with Design-Builder the percentage split for appropriate rating categories (ie OPSS work and PERF work percentage weightings). • Form B’s review process.

G-17 N/A

G-18 Infraction Report Discuss current process for issuing and receiving an Infraction Report with emphasis on impacts.

G-19 Documents to be provided to the Design-Builder by the CA, when not published on Ministry’s website (including standard forms related to the contract).

4.5 NOTIFICATIONS

4.5.1 Notifications Prior to Construction

Before construction begins, the Design-Builder shall give written notice to all property owners and businesses within the limits of the Contract. The notice shall indicate that construction is about to begin and should identify the Design-Builder, the Design-Builder’s representative and a telephone number, a general description of the work, the anticipated completion date, and the name and office telephone number of the CA.

The Design-Builder shall keep all appropriate agencies apprised of any construction activity that may have an impact on their daily operations, with copy to the CA, including: – Schools – Utilities – O.P.P. – Municipal/Regional Police Forces – Fire – Ambulance – Transit Authorities – Municipalities

36 Design-Build Administration Manual January 2014

– Maintenance Patrols/Operations – Ministry of Natural Resources – Department of Fisheries and Oceans – Conservation Authority – Others as required

4.5.2 Notifications During Construction

Applicable notifications are to be provided by the Design-Builder to the CA as per Regional protocols, requirements of the Contract Documents, or as requested by the Ministry including traffic and lane closure reports / notifications, and any information required for weekly updates for Travellers website (in order to assist travelling through construction zone).

4.5.3 Traffic Control / Lane Closure Notification

References: o Design-Builder’s traffic control and management plan, and design details; o Ontario Traffic Manual (OTM) Book 7 Temporary Conditions o NSSP – Traffic Control Signing o Ontario Traffic Manual (OTM) Book 7 Temporary Conditions (Field Edition) o Regional Protocols for lane and ramp closure notification o Regional Protocols for OSCLIS (Ontario Structural Clearance and Load Information System)

The Design-Builder shall ensure, and the CA shall check, that the Design-Builder maintains and updates a Traffic Signing Diary as required. The CA shall check that all traffic control, staging, detours and lane closures by the Design-Builder follow Ontario Traffic Manual (OTM) Book 7 Temporary Conditions and the Design-Builder’s design and traffic control and management plan.

The Design-Builder shall ensure, and CA shall check, that appropriate Traffic Control Lane Closure Notifications are submitted in accordance with Regional Protocols, whenever lane restrictions will be in place either on a permanent or temporary basis.

4.6 CONTRACT MEETINGS

The CA shall be in attendance at all Contract meetings.

The Design-Builder shall arrange, conduct and attend Contract meetings. The Project Team shall determine the appropriate frequency of progress meetings, as well as what “Special Meetings” may be required, during development of the Request for Proposal. The frequency and meeting types are specified in the RFP. The frequency of meetings held should take into consideration the complexity of the project while also keeping in mind the Design-Builder has sole responsibility for the design.

The Design-Builder is required to provide a meeting agenda five Business Days in advance of the meeting and forward copies to all meeting invitees, including the CA, CSA and Project Lead. The agenda/content of all meetings should be carefully reviewed by the CA, and revisions sent to the Design-Builder as necessary, to ensure it is appropriate to the Design-Build contract model and the Contract Documents. The Project Management Best Practices provides a good

37 Design-Build Administration Manual January 2014 overview of meetings and should be used as a reference for the CA to determine the appropriateness of the content of progress meetings in addition to the details provided below.

4.6.1 Contract Progress Meetings

CACSA

In general, the following items should be discussed at all progress meetings:

o Review the minutes of the previous meeting o MTO or Design-Builder concerns, which have not been resolved on a day-to-day basis o Safety and environmental issues o Adherence to the Quality Control performance measures (non-conformances, deviations) o Quality Assurance issues o Project status to date / planned activities / critical path updates o Review the Design-Build Contractor Performance Rating report, Form B’s. o Claims/change orders/negotiations o Safety-traffic control/accidents/MOL concerns/OPP o New business/Design-Builder issues/Ministry issues

The minutes of meetings are an important contract document. It should be strongly recommended the Design-Builder seek agreement with the minute records and include a statement at the start of each meeting that the contents and wording of the previous minutes of meeting be accepted as written. Any amendments (i.e. errors, omissions and additional comments) are to be noted. If there are discussions pertaining to items in the previous minutes, these are to be discussed under “New Business” with reference to the previous minutes’ number, e.g. Item No. 2, Site Meeting No. 6, Date.

The minutes should also include the following information:

o Meeting Number # o Contract Number o “Action By” column (beside each item) o Date/Time and Location of the meeting o Invited Guests / In Attendance or not o Name of the person chairing the meeting o Time that the meeting adjourned o Date / Time and Location of the next meeting to be held o Name of the person compiling the minutes o Cc all present / copy to file

4.6.2 Special Meetings

o Traffic meetings to discuss major changes in operations (staging, detours, night closures, etc.) are to be held prior to any change. o Pre Soils Meeting to discuss any unique requirements for use of earth materials. Also clarify disposal and erosion and sediment control requirements.

38 Design-Build Administration Manual January 2014

o It may be beneficial to hold a separate Pre-Work Environmental Meeting with MNR and/or DFO, the Environmental Planner, and the CCA Environmental Monitor for any in- water, or de-watering work in the project. o Any other meetings that are deemed necessary such as Emergency Services and Seasonal Shutdown shall be held and minutes taken and distributed. o Post Construction Meeting (lessons learned) should be organized and chaired by the Design-Builder; MTO Project Leads, the CSA and CA shall be in attendance. o Pre-Placement Meeting for Concrete (see below) o Pre-Paving Meeting (see below) o Pre-Work Meeting for Electrical (see below)

4.6.2.1 Pre-Placement Meeting for Concrete

At the pre-start meeting, SP DB 1350 or applicable specifications included in the Contract Documents should be reviewed and requirements for acceptance testing should be determined (including lot and sub-lot size per each concrete class).

Pre-placement meetings are good industry practice. It is recommended to hold one prior to any significant concrete operation on the Contract.

The purpose of this meeting is to review Design-Builder’s quality control management plan related to concrete work, and placement details prior to the concrete placement event.

The minutes of this meeting are to be recorded and documented with copies to all invitees, (with copies to the CA and CSA, as a minimum).

Topics:

o Review of quality control performance measures. Establish persons in charge from the Design-Builder’s QC team o Date and time of placement o Review status of falsework and foundation certification, and dry run o Expected duration of placement Concrete mix details and supply; back up plant o Testing procedures including acceptance/rejection of loads o Curing of cylinders o Retarders, super plasticizer when included in the design by the Design-Builder o Weather forecast o Hot/Cold weather protection/precautions: Status of Design-Builder’s submissions o Surface finishing requirements in specifications o Curing requirements as per specifications o Review requirements for post-placement sampling and testing as per Contract Documents o For bridge decks: discuss plan, dry run, locations of possible construction joints if unforeseen issues arise (Design-Builder’s team to determine this location). o General

39 Design-Build Administration Manual January 2014

4.6.2.2 Pre-Paving Meeting

At the pre-start meeting, the Asphalt Pavement PERFs and/or applicable specifications included in the Contract should be reviewed. Also, consequences for non-conformances and requirements for acceptance testing should be reviewed.

A pre-paving meeting is good practice and it is recommended prior to any significant paving operations on the Contract. The lot testing and acceptance procedures should be established and reviewed with the Design-Builder.

The purpose of Pre-Paving meeting is to review the specifications in the Contract and to address issues identified leading to the significant paving production. The minutes of this meeting are to be recorded and documented with copies to all invitees, (copies to the CA and CSA, as a minimum).

Topics:

o Review status of all mix design submissions o Review of specifications in the Contract o Review of quality control performance measures o Review plans, Traffic Control, Scheduling, etc. o Request that all paperwork is in order prior to commencement o Review sketch of sublots to be measured by PMD, areas to be exempt from surface smoothness measurements/penalties and all other additional measurements required (e.g. existing surface beneath single lifts) o Discuss Design-Builder’s duties to facilitate smoothness measurements o Discuss any new technologies that may be used on Contract.

4.6.2.3 Pre-work Meeting for Electrical

At the pre-start meeting, applicable electrical specifications included in the Contract should be reviewed, with careful attention to the requirements associated with signal activation and PHM 125 (which must have been transferred by the Design-Builder to the Issued for Construction drawings)

Depending on contract size and amount of electrical installations, a pre-work electrical meeting is recommended prior to any significant electrical operations on the Contract.

A pre-start meeting shall be arranged prior to the installation of any electrical material or equipment on the Contract.

The purpose of this meeting is to review construction and maintenance requirements for the new and existing electrical plant.

The minutes of the meeting are to be recorded and documented with copies to all in attendance (copies to CA, CSA and MTO Electrical Coordinator, as a minimum).

40 Design-Build Administration Manual January 2014

Topics:

o Review all applicable specifications in the Contract o Review Contract Document requirements for the Design-Builder to maintain existing electrical systems o Review condition of existing electrical plant o Review coordination needs with MTO electrical coordinators, local municipalities and power supply authorities o Review locates and clearances (overhead and underground), and methods to warn sub-contractors, equipment operators. Consequences if lines are hit by the Design- Builder) o Signal Activation Contract Document requirements and PHM 125

For scheduling resources, the CA and MTO electrical staff shall be notified of the start of the electrical work, and thereafter shall be notified as soon as possible on any changes to the schedule of electrical work.

4.6.3 Pre-Seasonal Shutdown / Final Inspection Meeting

The CA shall organize and chair the Pre-Seasonal Shutdown/Final Inspection Meeting.

Topics:

o Review the Ministry’s protocol concerning the “Seasonal Shutdown and Working in Free Time” period, depending on the requirements of the Contract Documents. o Review the Design-Builder’s updated Critical Path Schedule at each Pre-Seasonal Shutdown Meeting, which must identify what work will be completed to allow the safe passage of the travelling public during the seasonal shutdown. o Review the applicable portions of the construction season shutdown period checklist (Note to CA: if there are any outstanding issues, this is an appropriate time to address them.) o Review the applicable “seasonal shutdown period” requirements in the Contract Documents o Review and discuss any concerns of Operations/Maintenance that should be added to this agenda and provide to the Design-Builder to be sent out to all invitees prior to the scheduled meeting. o Review traffic staging revision submission and approval requirements. o Request any haul routes proposed by the Design-Builder during this period are reviewed by the CA noting load limits and local by-laws may differ from Design-Builder’s design assumptions. o Review the Design-Builder’s responsibilities with respect to traffic, staging, detours, traffic control, maintenance of traffic, signing as per Ontario Traffic Manual (OTM) Book 7 Temporary Conditions, Freeway Detour Signing Guidelines, safety precautions, and Contract Documents(e.g. PERFs, Traffic Control Signing, Hours for Lane Closures, Maintenance of a Traffic Control Diary, etc.). o The specified minimum clearances (horizontal and vertical; protocol for advising about clearances) must be maintained in accordance with the Issued for Construction drawings and Contract Documents. o Review the Design-Builder duties with respect to construction and traffic safety.

41 Design-Build Administration Manual January 2014

o Remind the Design-Builder of any reduced speed zones to be in effect (if applicable). o Review the concerns of any other interested agencies. o Facilitate the advance notification of closures, detours, etc. to be provided to emergency services, municipalities, transit authorities, etc. o Damage to Permanent or Temporary Installations o Review MTO Provincial Highways Directive PHY-B-102. Advise the Design-Builder of the safety and legal aspects of installations. o All claims by Motorists, Property Owners, etc during the construction period must be brought to the attention of the CA. o Substantial Performance and Contract Completion: − Review the General Conditions of Contract. Two weeks advance notice for final inspection should be provided to the CA in writing. o Remind the Design-Builder that applicable environmental timing constraints must be complied with, as follows: – Obtain Design-Builder’s contact names, positions and telephone numbers – The Design-Builder staff to be notified for follow-up of any environmental accidents/incidents/problems both during the Work and during periodic/ seasonal shutdowns. – Facilitate the advance notification of closures, detours, etc. to be provided to emergency services, municipalities, transit authorities, etc. o Advise the Design-Builder that all structures are to be inspected by the Regional Structural Section prior to opening to traffic, with the exact time determined by the CA with the Design-Builder’s assistance: coordination is needed between the CA and Design-Builder to organize the inspection so that it happens a minimum of three (3) weeks prior to opening to traffic, therefore, the structural office will need to be kept informed about status of work. o Discuss the responsibility of the Design-Builder concerning proposed staging changes etc o Remind the Design-Builder about adhering to the submission of updated Critical Path Schedules (GC 7.01.07) o Remind everyone that all contract correspondence must flow through the CA. o Anything unusual in this project, which should be covered by additional clarification. o Does the staging comply with the seasonal shutdown requirements listed in the Contract Documents? o Review staging approach to ensure conformance with the Contract Documents (including the applicable seasonal shutdown typical cross etc.) and considerthe applicable construction and maintenance related concerns such as: – MH and CB’s be reset to shut down pavement elevations – Provisions for drainage must be made – During the seasonal shut down/working in free-time period all lanes must be restored to Contract Document requirements – Address all pavement markings (temporary and permanent) including appropriate obliteration – Address temporary and permanent signals etc. (if applicable) – Can the Work be constructed with the staging provided – Have all the safety-related components been addressed (such as TCB, SBGR) – Address all structure-related issues – Does the proposal/shutdown plan incorporate the turnarounds for emergency vehicles o Develop a static deficiency list, which incorporates any seasonal shutdown related situations/problems, which will be reviewed at all pre-seasonal shutdown meetings

42 Design-Build Administration Manual January 2014

(noting by the time the scheduled shutdown nears all deficiencies must be established by the various offices involved in order for the CA team to administrate an orderly and timely turnover.) o Can all structural lanes be restored prior to seasonal shutdown. o Notification of winter work to applicable media-related (such as the Regional Radio etc.) o Discuss the Design-Builder’s intentions concerning Seasonal Shutdown and Free Time work. o Discuss the removal of construction signs (if applicable) o Prior to the scheduled shut down/working in free time each section submit their static list of deficiencies and concerns: (noting the Design-Builder is always encouraged to work in free time or accelerate, when allowed in the Contract, which can end up in a stage that may not accommodate the minimum winter configurations. The CA must bring this type of situation to the attention of the CSA well in advance of the scheduled shutdown date.) o Prior to any turnover (whether a “seasonal shut down” for a carry over or a “final inspection” for Contract Completion ) the CA must notify the applicable Ministry representatives (including a drive through with the CSA/Design-Builder/CA/ operations representatives) o Has a final inspection type meeting been held with the construction / maintenance Design-Builder/operations/ACE/CSA prior to the actual turn over or opening of the road/ lane etc. (whether final inspection or seasonal shut down) checking that everyone’s concerns have been addressed each Section /Department should inspect the contract and submit a “static list” within two Business Days to the CA o Has the Turnover Agreement form ( PH-CC-771) been sent to the appropriate MTO offices for Ministry accepting responsibility for the road (at the Contract Completion/winter shutdown or spring start up) o Have all work zone accesses being addressed? o Any constructor or Utility issues? o Have MTO operational offices representatives reviewed their specific interests? o Review the Design-Builder’s traffic control and workers protection plan to check that they are up to date reflecting any necessary changes to address the seasonal shutdown or working in free time period. o Has a contingency plan been developed to address unexpected situations (such as an early snow fall or winter)?

4.7 COMPLETION DATE

References: o MTO General Conditions of Contract o Provincial Construction Memorandum PCM #2007-02

The CA shall become familiar with and administer the Contract Document requirements regarding contract completion dates, and liquidated damages, if applicable. These requirements should be reviewed during the Pre-Start Meeting.

The Design-Builder must request an Extension of Time in accordance with the MTO General Conditions of Contract. The CA shall receive and evaluate the Design-Builder’s requests for extension of time, and provide a comprehensive written report with recommendations to the Ministry (within an agreed upon time frame). The request and Design-Builder recommendations shall be reviewed with the CSA. The MTO Regional Operations Office will grant approval or disapproval of Design-Builder requests for extension of time. When the Design-Builder has submitted PH-CC-775 Extension of Time Request and Approval or PH-CC-750 Request for

43 Design-Build Administration Manual January 2014

Clarification disagreeing with the response to an extension of time request, the amount of liquidated damages shall be calculated but not deducted. The MTO Regional Operations Office will advise the CA of the outcome and instructions for application of damages when applicable.

4.8 EXPENDITURE CONTROL

The CA shall use the Construction Administration System (CAS) supplied by the Ministry of Transportation for the production and tracking of change orders.

The CA will be responsible for submitting a hard copy of an accurate expenditure forecast on a monthly basis along with the recommended Progress Payment. All changes shall be listed and an accurate detailed explanation is required for each change. The CAS database must be submitted at the same time electronically to the Regional Operations Office.

The Contract Information Form in CAS must be updated monthly to include an updated contract completion date, all estimated expenditures for the current fiscal year (April 1st – March 31st) as well as carryover expenditures for the next fiscal year (if any).

4.9 ROCK ADMINISTRATION

Administration of rock excavation and embankment construction shall be as per the Contract Documents. Depending on the specific Contract Document requirements, the CSA shall ensure that Contract Administration Agreement contains appropriately specified sub-plan, qualified survey staff and level to perform the quality assurance and audit checks required to protect the Ministry’s interests.

4.10 COMMISSIONING OF HIGHWAYS PRIOR TO OPENING

o The Project Lead and CAshall be familiar with the current protocol for Commissioning new sections of Highway prior to opening. o Provide notification to the CSA and ensure that all items on the Commissioning Checklist are completed in accordance with the Ministry’s latest guidelines.

4.11 DOCUMENTATION

4.11.1 Documentation of Contract Activities

Design-Build projects generally generate a lot less paperwork: more specifically, there are no, or minimal, weight tickets or measurements to support payment. However, the CA and technical support staff shall provide sufficient documentation of all contract activities. It is essential that an accurate and detailed description of contract operations be maintained to assist in the preparation of the final documentation package, and in dealing with claims and Change Orders.

4.11.1.1 CA’s Diary

The CA’s Diary shall be properly titled, noting the Contract Number, the Region, and the Location. The name and address of the CA keeping the Diary shall be placed on the personnel page, as well as a complete listing of all personnel assigned to the Contract.

Daily entries must be made in the CA’s Diary by the CA or his representative in his absence.

44 Design-Build Administration Manual January 2014

The minimum documentation requirements are as follows:

o Index (for any significant issues, claims, etc.) o Date o Weather conditions; recording frequency should increase when conditions are near critical thresholds (i.e. low temperature, precipitation) o General progress of the work, especially at the beginning and ending of important phases, and an account of any difficulties encountered by the Design-Builder including achievement of milestones and whether notification was made to the CSA or Project Lead o Record of labour, materials, equipment, activity and location whenever there is the potential for a change in the Contract or the Design-Builder has raised the potential for a change in the Contract. o Monitor if controlling operation is maintained as per the Design-Builder’s Critical Path and discuss changes with Design-Builder. o Design-Builder’s claims or complaints o Verbal and written instructions given to the Design-Builder o Record of events that could have an effect on the Design-Builder’s production and possibly require shut down on the Design-Builder’s part o Any significant event that occurs on the Contract and an assessment of the potential impacts o Dates of the relocation of Utilities and all pertinent data regarding the effects such relocation has on the Design-Builder’s use of equipment o All discussions, complaints, concerns, etc. or dealings with property owners (e.g. date of physical acquisition of property) o All discussions or dealings with municipalities, other ministries, Utilities, third parties, etc. o Record of any grade or alignment changes together with the rationale for and acceptance of the change o Deviations from plans, profiles, specifications, special provisions along with the rationale for acceptance of the change o Any decisions or recommendations made by MTO officials must be recorded, including the date, subject, decisions and final results. A copy of this record shall be promptly sent to the CSA for information and / or for forwarding to appropriate individuals o Irregularities in any item during construction o Any changes in the work, including additions and deletions, identification of the compensation mechanism, including references and appropriate justification o Reference to Change Orders o Data required for reconciliation of Daily Work Records o Record all accidents within the Contract limits, and on operations connected with the Contract (i.e. set up of closures or traffic queues resulting from closures, etc.) o Maintain a record of environmental incidents, including, but not restricted to when the incident took place, actions taken or intended to be taken by the Design-Builder regarding the incident such as containment of spills, notifications made to proper authorities, actions taken to clean up and restore the environment to pre-incident conditions, investigations, charges, stop work orders and remedial instructions by regulatory agencies, environmental complaints by the public. o The condition of haul roads before and after construction, including appropriate documentation (i.e. photographs) o Explanations for incompleteness of any field records

45 Design-Build Administration Manual January 2014

o Record of non-compliance / non-conformance with environmental timing constraints and action taken to address, and communications with MTO and agencies o Record of non-compliance / non-conformance with any Performance Specification and action taken to address, and resulting communications with MTO and agencies o Report Information shall be recorded in the Diary for the preparation of the Project Construction Report. All peculiarities as they occur such as design and construction problems, and their solutions, quality assurance problems, etc. must be documented

4.11.1.2 Inspector’s Diary

The Inspector shall maintain accurate and detailed description of contract operations relative to the Design-Builder’s activities for work governed by OPS specifications.

Design-Builder’s activities will be recorded in the Inspector’s Diary by actual times when CA staff are present and by the best practical estimate of times when CA staff are not present, (i.e. the estimated times will be based on the Design-Builder’s statements or a realistic appraisal of production rates, etc). Any abnormalities or explanations will be noted in the remarks column of the records.

A separate Inspector’s Diary must be kept for Grade, Structures, Bituminous, Electrical, Environmental, and other items in consultation with the Project Lead.

The Inspector’s attendance time on the operation will be recorded above his signature.

The minimum documentation requirements are as follows:

o The Inspector’s Diary shall be titled noting the Region, Contract Number, Highway Number and Location, and the name of the Design-Builder o Date o Weather conditions; recording frequency should increase when conditions are near critical thresholds (i.e. low temperature, precipitation) o Design-Builder’s hours of work o General progress of the work,where the Design-Builder is working and what he is doing, especially at the beginning and ending of important phases, and an account of any difficulties encountered by the Design-Builder including achievement of milestones o Record of labour, materials, equipment, activity and location whenever there is the potential for a change in the Contract or the Design-Builder has raised the potential for a change in the Contract. o Separate Time and Materials Records are maintained in the case of a Change Order, Additional Work or Claim situation o Visits to the contract of MTO officials, and any specific instructions they may have given. o Instructions given to the Design-Builder o Design-Builder’s claims or complaints o All discussions and dealings with property owners o Work performed on the contract by public Utilities, noting start and completion of the work o Stoppage of work by the Design-Builder for any reasons with full description of why contract was shut down o Maintain a record of incidents including but not restricted to when the incident took place, actions taken or intended to be taken by the Design-Builder regarding the incident such as containment of spills, notifications made to proper authorities, actions taken to

46 Design-Build Administration Manual January 2014

clean up and restore the environment to pre-incident conditions, investigations, charges, stop work orders and remedial instructions by regulatory agencies, environmental complaints by the public o Record of non-compliance / non-conformance with environmental timing constraints and action taken to address, and communications with MTO and agencies o Inspection activities and verification results

4.11.1.3 Diaries (CA and Inspector’s) Submissions

Diaries (CA and Inspector’s) must be hardbound books with numbered pages. There shall be duplicate, perforated and carbonized pages for daily entries to allow for easy removal of a copy for distribution.

The original copy of the diaries must be submitted to the CA’s Field Office on a daily basis, and forwarded to the CSA on a weekly basis. The second (bound) hard copy of the diary sheets shall be kept at the CA’s Field Office for submission with the Final Record Documents. The CA shall also retain a third hard copy of the diary sheets in a secure, separate location.

4.11.1.4 Documentation of Service Provider CA Activities

On a daily basis, the CA shall make available to the Ministry, sufficient documentation to determine that they are satisfying their obligations under the Construction Administration Agreement and the Design-Build Contract Administration Manual requirements. Inspection tasks and time spent on each should be referenced in the Inspector’s Diaries.

4.11.1.5 Documentation/Certification

Documentation requirements related to inspection have not been specifically identified within the individual tasks in Part B of this manual. It is the responsibility of the CA to require that all documentation specified by the Contract Documents is available or has been received and/or approved at the time and in the specified manner. These documents include but are not limited to the following:

o Certificates of component o Certificate of conformance o Stamped drawings o Proposals o Material certificates and material data sheets o Facilities and personnel certificates o Electrical service manuals o Proposed Aggregate Permit / Wayside Permit Applications

4.11.2 Instruction Notice to Design-Builder

Instruction Notices to the Design-Builder shall be issued to document concerns and deviations or non-conformances, clarify requirements of the Contract, communicate information, and transmit documentation. Instruction Notices shall be signed by the CA and the Design-Builder to acknowledge receipt of the Notice. Examples for the use of Instruction Notices to the Design- Builder include, but are not limited to, the following:

47 Design-Build Administration Manual January 2014

o Changes in the Work o Acknowledge receipt of complete submission (Complete means thatit has all the elements listed in the specification). The CA does not approve Design-Builder’s design submissions unless related to remedial work or Change proposals, and as specified in the Contract Documents. o Transmittal of documents o Safety issues o Non-conformance to the Contract Documents o Warnings o Suspension of work, stop work order issued by MTO or its agents o Specific Instructions from the Ministry

4.11.3 Design-Builder’s Infraction Report

Reference: o Procedures for Processing the Design-Builder’s Infraction Report

The CA shall prepare the Design-Builder’s Warning of Infraction Report/Infraction Report upon discussion with the CSA and Project Lead, and shall attach appropriate documentation. The completed Warning of Infraction Report/Infraction Report shall be forwarded to the CSA. The Project Lead shall attend any meetings with the Design-Builder to discuss the issuance of the Warning of Infraction Report or the Infraction Report.

4.12 CHANGES

References: o MTO DELEGATION OF AUTHORITY FRAMEWORK (DELEGATION OF AUTHORITY for the MINISTRY OF TRANSPORTATION) o MTO General Conditions of Contract o Construction Change Order Manual

4.12.1 Change Orders

All information on Change Orders can now be found in the Construction Change Order Manual.

4.12.2 Clarification and Claims

References: o MTO General Conditions of Contract GC 3.14 o HOC #2006-02 Administration of Claim Settlements

Check that the Clarification and Claims process and timeframes for resolutions are documented and the Contract Documents are adhered to. The CA must notify the CSA and Project Lead of a potential Claim situation. It is the Design-Builder’s responsibility to maintain Daily Work Records in support of their (potential) Claim. The CA shall prepare a report on the details of the claim for the CSA. The Project Lead shall liaise with the CSA to provide input into the negotiations and facilitate the satisfactory resolution of Clarification and Claims.

The CA shall as a minimum: o Receive all written Request for Clarifications, Daily Work Records, and other supporting information/documentation.

48 Design-Build Administration Manual January 2014

o Check that Design-Builder’s Request for Clarification submission fully complies with Contract Document requirements both for content and time o Check that the Design-Builder submits Daily Work Records in accordance with the Contract o Monitor and record Design-Builder work activities (manpower, materials and equipment) for work affected by (or likely to be affected by) the Claim. o The Daily Work Records shall be signed each day of work by both the Design-Builder's representative and the CA. The CA will note disagreements on the Daily Work Record prior to signing and return a copy to the Design-Builder. o Provide a detailed analysis and review based on the Contract Documents and all pertinent information related to the Clarification and Claims. o Complete the Clarification and Claims Summary Form (PH-CC-751) for all Request for Clarifications. o Provide final written response to the Design-Builder’s request for clarification as soon as possible within the Contract Document timelines. o In the event a Claim is elevated to the Regional level, the CA shall review the Design- Builder’s Notice of Claim submitted to the Region and provide written response to the Region on any significant discrepancies from the information provided at the field level, within 5 Business Days.

4.12.2.1 Clarification and Claim Settlements on Active Contracts

Request for Clarifications determined to be a change to the Contract shall be processed as a Change Order.

In the event that a Regional or Head Office level settlement is reached, and the contract is still on going, Regional or Head Office Claims staff will forward the claim settlement details to the CSA and CA for payment processing. The CA will enter all relevant data into the CAS using the category for “claims settlements” under Other Payment Adjustments – No Change Order.

4.13 MEDIA ENQUIRES

The Project Lead must handle all media enquiries as per applicable Regional protocol.

4.14 SUBSTANTIAL PERFORMANCE &CONTRACT COMPLETION

References: o Provincial Highways Directive PHY-B-241 Construction Lien Act o MTO General Conditions of Contract

The Design-Builder must request Substantial Performance and/or Certificate of Contract Completion in writing and provide a two week notice to the CA to make arrangements for the Final Completion Meeting.

The CA shall participate in joint inspections of the work with representatives of the Design- Builder and the Ministry, following receipt of a written request from the Design-Builder, for the purpose of establishing the date of substantial performance of the work and/or the date of completion of the Work.

49 Design-Build Administration Manual January 2014

4.14.1 Certificate of Substantial Performance

References o GC 8.02.04.05 Certificate of Substantial Performance

The CA shall monitor the progress and financial status of the contract and shall generate the Certificate of Substantial Performance at such time when the requirements of Substantial Performance have been met and will be signed by the CA to be forwarded to the Regional Operations Office. The CA will submit their calculations to support the eligibility for the Substantial Performance as identified in the MTO General Conditions of Contract and should also include a deficiency list for any outstanding work.

The Substantial Performance shall be processed in accordance with the appropriate Contract Documents. The CA must also identify set-offs to the contract for incomplete and deficient work.

Once all of the above has been addressed, the certificate can be issued to the Design-Builder for publication.

4.14.2 Certification of Sub-Contractor Completion

References o GC 8.02.04.07 Certification of Sub-Contractor Completion

Before the Work has reached the stage of substantial performance, the Design-Builder may notify the CA that a subcontract is completed satisfactorily and ask that the CA certify the completion of the subcontract. The purpose of this request is to allow for the holdback, on the subcontracted items that have been completed, to be released. The CA should follow the process as outlined in the MTO General Conditions of Contract.

4.14.3 Certificate of Contract Completion

References o General Conditions of Contract

The Completion Checklist shall be generated by the CA and reviewed with the CSA prior to the Completion Meeting. All deficiencies in the Work should be noted and reviewed with the CSA and the Design-Builder for rectification. The Project Lead/CSA will notify the Regional Contracts Office of the completion date and a Certificate of Completion will be issued and signed by the Payment Certifier. The General Warranty period begins after the date of Contract Completion as set out in the Contract Completion Certificate. Item-specific warranties begin as specified in the Contract Documents. Completion should not be certified until all Work in the field is complete.

50 Design-Build Administration Manual January 2014

CONTRACT COMPLETION CHECKLIST (*Denotes items to be completed prior to Completion of the Work)

ACTION REQUIRED ACTION TAKEN COMMENTS

Request for Completion from Design-Builder in writing * (including Substantial Performance with proof of advertising). Notify CSA two (2) weeks prior to anticipated Contract * Completion and arrange meeting to review contract. Notify Head, Quality Assurance Section two (2) weeks * prior to anticipated Contract Completion. Notify Head Operational Services/Maintenance Coordinator/Area Maintenance Contractor representative, two (2) weeks prior to anticipated * Contract Completion. Arrange field review with Maintenance Coordinator/AMC representative to determine deficiencies. Notify Regional Structural Section two (2) weeks prior * to anticipated Contract Completion. * Notify Regional Environmental Office. Verify the Design-Builder has notified permit-issuing agency for rehabilitation of pits or quarries under wayside permits or aggregate permits and has * completed Compliance Report as per document “Procedures for Administration of Mineral Aggregate Extraction on MTO Contracts” Notify: Municipal Officials * Railway Officials Utilities Other Interested Parties * Complete Structural Clearance Report.

* Review status of completion date.

* Develop deficiency list.

* Review deficiency list with CSA. Meet with the Design-Builder to resolve outstanding * deficiencies. Check that the Design-Builder replaces any property * and/or horizontal and vertical bars damaged or removed during construction. Prepare/obtain a list of outstanding: * Change Orders Intents to Claim

51 Design-Build Administration Manual January 2014

Infraction Reports Test Results Cost Sharing/Recoverables Releases for disposal areas, pits, etc. All certifications Review the status of: * Permanent signs Pavement markings * Notify Regional Electrical Section

Notify MTO Electrical Coordinator

* Notify Advanced Traffic Management Section Verify Design-Builder has completed a report

regarding Management of Materials (OPSS 180) Contract Completion Meeting. Review Design-Builder’s Record Drawings for completeness and as per requirements of Contract Documents

52 Design-Build Administration Manual January 2014

4.15 ASSESSING COMPLIANCE TO THE QUALITY PROCESSES

4.15.1 General

References: o Appendix B o SP 199S53

The CA will:

o Ensure all contract administration staff are aware of the Special Provision “Performance Requirement – Quality Processes”, and their roles and responsibilities for monitoring compliance, assessing deviations and preparing monthly summary reports for submission to the Ministry o Review certifications by the manufacturers, suppliers and Design-Builder’s authorised personnel to check proper wording and submissions including timeliness, test results and proper seals and signatures where required.

Note: Review of QVE services including Certifications of Conformance and Interim Inspections is covered in Appendix B.

o Receive and review Non-Conformance Reports (NCR) from the Design-Builder to determine if they are complete, accurate and have been submitted in accordance with the Contract Documents. If not, the CA will notify the Design-Builder in writing requesting correction and resubmission and consideration shall be given to assessment of a deviation.

In addition, the CA will review the proposed corrective action to determine its appropriateness. This decision will be made with consideration given to the effect of the proposed corrective action on the quality of the end product. If the corrective action is unusual or precedent setting, it is essential that the CA provides recommendations and obtains input from the appropriate Ministry personnel.

o Monitor the Design-Builder’s operations and clearly document the Design-Builder’s compliance, during construction and within 30 Days after the date of certification of the completion of the Work (i.e. “Work” as defined in the MTO General Conditions of Contract). The CA shall identify all non-conformances. o Within 3 Business Days of identifying a non-conformance or receiving a NCR from the Design-Builder, notify the Design-Builder in writing using form PH-CC-862 Status of Non-Conformance that the non-conformance is; – Not a deviation, or – A deviation including the reason for the deviation, or – Under review with the Ministry. o Where the Status of Non-Conformance classification is not obvious or may be precedent setting, obtain Ministry involvement. The CA will forward Non-Conformance Report if the Design-Builder identified the non-conformance, Status of Non-Conformance form, any other information related to the deviation and recommendations. The CA will submit this to the Ministry’s CSA and Regional Quality Control Advisor within 2 Business Days of the deviation occurring.

53 Design-Build Administration Manual January 2014

o When the CA issues Status of Non-Conformance to the Design-Builder indicating “under review with the Ministry”, the CA will issue an Instruction Notice indicating the results of the review within 3 Business Days of receiving the results of the Ministry review. The Instruction Notice will inform the Design-Builder that the non-conformance is; – a deviation including the reason for the deviation; and its severity (minor/major) – not a deviation o For each non-conformance, review the requirements of the Contract Documents that resulted in the non-conformance to identify any requirements the Design-Builder must still complete. If the Design-Builder does not complete the requirements within 3 Business Days of receiving the Status of non-Conformance, the CA shall issue an Instruction Notice to the Design-Builder for the requirements that must still be completed. The deviation will not be waived regardless of the Design-Builder’s compliance with the instruction. If the Design-Builder does not comply with the instruction, the CA shall consult with the Ministry to determine other appropriate administrative action. o Record all Non-Conformances and deviations from the QC requirements (using the form PH-CC-861 Monthly Summary of Processes Non-Conformance) and submit to the Ministry as per the distribution list on a monthly basis o Recommend initiation of, or act upon recommendations to initiate the Ministry’s infraction process if Design-Builder’s QC non-compliance warrants such action. o Respond to routine Ministry reports including but not limited to QAO inspection reports, CSA’s Contract Administration Performance Reports that pertain to the CA’s QC monitoring.

4.15.2 Non-Conformances Administration for PERF Specifications

The CA shall enforce the Contract Document requirements related to Non-Conformances with the performance measures specified in the PERFs and their associated consequences. The CA is required to identify the Non-Conformance and notify the Design-Builder within the timeframes specified.

Closely related to this, the CA shall keep track of the consequences applied since they will affect the Design-Build Contractor Performance Rating.

54 Design-Build Administration Manual January 2014

5.0 ADMINISTRATION POST-CONSTRUCTION

5.1 CONTRACT CLOSING PROCESS

The CA shall complete the Contract Closing Checklist as follows:

ACTION REQUIRED COMMENTS

Fill out Certificate of Contract Completion form

Complete Design-Build Contractor Performance Rating

Forward Certificate of Completion form, and Design-Build

Contractor Performance Rating to the CSA Identify Contract Work under Warranty with Expiration Time Frame as per the Contract Documents (Including all actual site seeding and landscape planting dates) Send 3 copies of electrical record drawings, electrical shop drawings and service manuals to the Electrical Coordinator Send record of GPS coordinates readings (electronic copy) for ATMS field components to ATMS contact

Submit Project Construction Report to CSA Submit Pit & Quarry After Use Report PH-D-46-02-01 (commercial, wayside and permit sources) completed by the Design-Builder Material Summaries, estimated/as available, in a Digital

Format Acceptable to the Ministry Submit Disposal Site Permits & Property Owner Clearance

Certificates completed by the Design-Builder Submit completed MTO Class EA Process Monitoring

Questionnaire Submit Summary of Environmental Concerns and

Commitments Table completed by the Design-Builder

Submit Record Documents Package

Provide to the Design-Builder the Final Estimate Quantity and Cost Sheet (Ph-cc-829).

Submit Final Detailed Statement (FDS) to CSA

Substantial Performance Form and proof of advertisement

55 Design-Build Administration Manual January 2014

Final CAS should be reconciled to payments and provided

to MTO at the hand over meeting.

List of any known outstanding issues

5.2 DESIGN-BUILDCONTRACTOR PERFORMANCE RATING

Reference: o Design-Build Contractor Performance Rating (and the associated Design-Build Contractor Performance Rating Guideline)

The final document (rating and form B’s) where applicable must include clear, complete and factual information to support the rating given with references to diary sheets, minutes of meetings or other record document.

The CA shall prepare the Design-Build Contractor Performance Rating documents as per the Ministry Guidelines, for Ministry approval (Reviewed by CSA / recommended by Project Lead / confirmed by RCE).

5.3 SUBMISSION OF RECORD DOCUMENTS

5.3.1 RECORD DRAWINGS The CA shall review the Record Drawings submitted by the Design-Builder to verify compliance with requirements of the Contract Documents. The CA shall submit the Design-Builders Record Drawings to the Ministry with the final records package.

5.3.2 PROJECT CONSTRUCTION REPORT

Reference: o Project Construction Report Completion (most current Ministry guidelines)

The CA shall prepare the Project Construction Report within 60 Days of completion of the Certificate of Completion (or as otherwise agreed to by the Ministry). The Region will prepare Part A and distribute the report. For Design-Build projects, the CA will assist the Project Leads during the completion of a Data Collection sheet that basically includes a summary of the financial numbers for the project.

56 Design-Build Administration Manual January 2014

PART B

INSPECTION TASKS

57 Design-Build Administration Manual January 2014

6.0 DESIGN-BUILD INSPECTION TASKS - GENERAL

The Project Team will determine the appropriate frequency and detail of oversight and reviews during the construction phase based on the project type, complexity and type of specifications used. Ideally Design-Build contracts would be fully Performance based. Until Performance Specifications are available for all elements of a project it will be necessary to have a blended or hybrid approach to specifications. The Contract Documents have been written to incorporate Performance Specifications into the contract where available. In all other cases traditional Ontario Provincial Standard (OPS) Specifications and Drawings are to be used (subject to Design-Builder requests for substitutions). Accordingly, different oversight approaches are required for each. This manual identifies the oversight approach for those work elements subject to Performance Specifications (Section 8.0) and a different oversight approach more in line with traditional practices for OPS specifications (Section 7.0).

For OPS specifications, the measurement for payment and unit price components are not applicable to Design-Build contracts. As such the oversight associated with unit payment is no longer required. As well, in most cases, bonus/penalty or price adjustment language has been removed. Inspections to ensure quality and conformance in accordance with the OPS specifications and drawings are still required. Likewise Quality Assurance testing for material quality remains, although the material is deemed to be only acceptable or rejected.

When determining the appropriate frequency and detail of oversight and reviews the project team shall keep in mind the Design-Builder is solely responsible for the quality of work and conformance to all requirements of the Contract Documents. It is also important to remember that the Design-Builder’s submitted proposal forms part of the Contract Documents.

58 Design-Build Administration Manual January 2014

7.0 DESIGN-BUILDINSPECTION TASKS - OPS SPECIFICATIONS

7.1 LEVELS OF INSPECTION

The following tables identify the required level of inspection noted at the bottom of each inspection task.

Table 1 LEVEL OF INSPECTION MINIMUM FREQUENCY

A1 Continuous

B1 Twice Per Day

C1 Once Per Day

D1 Every Other Day

E1 Once Per Week

Table 2 LEVEL OF INSPECTION TIME ON SITE 100% of the time the Design-Builder is on site carrying out A2 that task 75% of the time the Design-Builder is on site per day carrying B2 out that task 50% of the time the Design-Builder is on site per day carrying C2 out that task 25% of the time the Design-Builder is on site per day carrying D2 out that task 10% of the time the Design-Builder is on site per day carrying E2 out that task F2 10% of the time Design-Builder is on site carrying out that task

Some tasks may consist of a combination of the above two (2) tables, with a statement to define the inspection effort. For example: o Level of Inspection – C1/E2 means that CA (or designee) shall be on site to inspect an operation once per day and inspect 10% of the day’s production.

Where practical, for tasks that require less than full time inspection, the required time shall be interspersed throughout the day. (i.e. for a task requiring a 25% time commitment, the inspection should not occupy the first quarter of the day, with no further inspection for the rest of the day).

59 Design-Build Administration Manual January 2014

The required levels of inspection are specified as minimums. If the Design-Builder is not performing well, or test results are continually poor, then the level of inspection may need to be increased to a higher level in order to check that the Design-Builder provides a quality end product. This situation must be reported to the CSA.

In conjunction with the inspection tasks outlined in this manual, the CA shall provide qualified personnel to inspect all work (including all non-civil related tasks such as electrical) as required to verify and document non-compliance to the Design-Builder’s Quality Control Management Plan.

Any inspection activity identified as a milestone requires a CA (or designee) on site to inspect and document an operation(s) at predetermined critical phases (milestones). Subsequent work on an operation shall not proceed until the milestone inspection is complete including corrective action if required. A milestone may be at an intermediate stage or at the final inspection stage.

A “milestone” is the component of the Work that is critical, prior to continuing with the remainder of the operation or the next operation.

All milestone inspections must be carried out and documented regardless of the levels of inspection specified. Obtain photographs of Milestone Inspections where practical (i.e. pile splices).

Milestones are indicated with an “M” beside the activity.

7.2 DOCUMENTATION

o Documentation requirements related to inspection have not been specifically identified within the individual tasks in Section 7 of this manual. Various tasks state to verify operations and dimensions. Any findings shall be documented in the Inspector’s Diaries. o Various tasks state “Check”. All information / findings noted from that “Check” shall also be documented in the diary. o Refer to Section 4.11.1.2 Inspector’s Diary of this manual.

60 Design-Build Administration Manual January 2014

7.3 INDEX OF INSPECTION TASKS GRADING AND DRAINAGE ...... 65 TASK GD 1 – CLEARING, CLOSE CUTTING, AND GRUBBING ...... 65 TASK GD 2 – BOULDER CLEAN-UP ...... 66 TASK GD 3 – STRIPPING ...... 67 TASK GD 4 – SWAMP TREATMENT ...... 68 TASK GD 5 – EARTH CUT...... 70 TASK GD 6 – EARTH EMBANKMENT ...... 71 TASK GD 7 – ROCK CUT ...... 73 TASK GD 8 – ROCK EMBANKMENT ...... 75 TASK GD 9 – TRANSITION TREATMENTS IN ROCK OR EARTH ...... 76 TASK GD 10 – FROST HEAVE TREATMENT ...... 77 TASK GD 11 – BASE AND SUBBASE...... 78 TASK GD 12 – RESTORING ROADWAY SURFACES ...... 79 TASK GD 13 – GRADE AND COMPACTION ...... 80 TASK GD 13 – GRADE AND COMPACTION ...... 81 TASK GD 14 – BORROW PITS AND QUARRIES ...... 82 TASK GD 15 – WAYSIDE PERMIT, AGGREGATE PERMIT, AND LETTER OF APPROVAL PITS AND QUARRIES ...... 83 TASK GD 17 – DITCHING ...... 84 TASK GD 18 – SUBDRAINS ...... 85 TASK GD 19 – EXCAVATION FOR CULVERTS ...... 87 TASK GD 20 – BACKFILLING FOR CULVERTS ...... 89 TASK GD 21 – SEWER IN TRENCH ...... 91 TASK GD 22 – SEWER TUNNEL / JACK AND BORE ...... 93 TASK GD 23 – WATERMAIN IN TRENCH ...... 95 TASK GD 24 – MANHOLES, CATCHBASINS, AND DITCH INLETS ...... 97 TASK GD 25 – GEOTEXTILE ...... 98 TASK GD 26 – GRANULAR BLANKET ...... 99 TASK GD 27 – RIP RAP ...... 100 TASK GD 28 – GABIONS ...... 101 TASK GD 29 – TOPSOIL ...... 102 TASK GD 30 – SODDING ...... 103 TASK GD 31 – SEED AND COVER ...... 104 TASK GD 32 – FENCE ...... 105 TASK GD 33 – GUIDE RAIL ...... 107 TASK GD 34 – ECCENTRIC LOADER BARRIER AND EXTRUDERS ...... 109 TASK GD 35 – TEMPORARY CONCRETE BARRIER (RELOCATION) ...... 111 TASK GD 36 – INERTIAL BARRIER MODULE ...... 112 TASK GD 37 – CRASH/CUSHION ATTENUATING TERMINAL BARRIER ...... 113 TASK GD 38 – TREND END TREATMENT BARRIER ...... 115 TASK GD 39 – GUIDE RAIL ENERGY ABSORBING TERMINAL BARRIER ...... 116 TASK GD 40 – CONNETICUT IMPACT ATTENUATION SYSTEM BARRIER ...... 117 TASK GD 41 – NOISE BARRIER ...... 119

61 Design-Build Administration Manual January 2014

TASK GD 42 – SURCHARGING ...... 120 TASK GD 43 – HAUL ROADS ...... 121 TASK GD 44 – WICK DRAINS ...... 122 TASK GD 45 – TREE AND SHRUB PLANTING ...... 123 TASK GD 46 – GROUND MOUNTED SIGN PLACEMENT ...... 124 TASK GD 47 – COMMERCIAL VEHICLE INSPECTION FACILITY ...... 126 TASK GD 48 – CONTROL STRIP ...... 127 CONCRETE AND STRUCTURES ...... 128 TASK CS 1 – CONCRETE PLACEMENT, CONSOLIDATION, FINISHING, AND CURING ...... 128 CONCRETE AND STRUCTURES ...... 130 TASK CS 1 – CONCRETE PLACEMENT, CONSOLIDATION, FINISHING, AND CURING ...... 130 TASK CS 3 – TREMIE CONCRETE ...... 133 TASK CS 4 – CURB AND GUTTER ...... 134 TASK CS 5 – CONCRETE SIDEWALK...... 135 TASK CS 6 – CONCRETE BARRIER WALLS ...... 136 TASK CS 7 – CONCRETE BASE AND PAVEMENT ...... 137 TASK CS 8 – CONCRETE BASE AND PAVEMENT – FULL DEPTH REPAIR ...... 140 TASK CS 9 – CONCRETE BASE AND PAVEMENT – FULL DEPTH REPAIR (FAST TRACK) ...... 142 TASK CS 10 – CONCRETE BASE AND PAVEMENT – PARTIAL DEPTH REPAIR ...... 143 TASK CS 11 – STRUCTURE REHABILITATION – REMOVAL OF WATERPROOFING SYSTEM FROM DECK SURFACE ...... 145 TASK CS 12 – STRUCTURE REHABILITATION – CONCRETE REMOVALS ...... 146 TASK CS 13 – STRUCTURE REHABILITATION – SURFACE PREPARATION ...... 150 TASK CS 14 – STRUCTURE REHABILITATION – NORMAL CONCRETE OVERLAY ...... 151 TASK CS 15 – STRUCTURE REHABILITATION - CATHODIC PROTECTION - ANODE MESH SYSTEM AND CONCRETE OVERLAY ...... 154 TASK CS 16 – STRUCTURE REHABILITATION – SILICA FUME CONCRETE OVERLAY ...... 155 TASK CS 17 – STRUCTURE REHABILITATION - LATEX-MODIFIED CONCRETE OVERLAY ...... 156 TASK CS 18 – STRUCTURE REHABILITATION – CONCRETE PATCHES ...... 157 TASK CS 19 – STRUCTURE REHABILITATION – CONCRETE REFACING ...... 159 TASK CS 20 – APPLICATION OF SILICA FUME OR NORMAL SHOTCRETE ...... 161 TASK CS 21 – STRUCTURE EXCAVATION ...... 163 TASK CS 22 – COFFERDAMS, SHEET PILING, TIE BACKS, AND ROADWAY PROTECTION ...... 165 TASK CS 23 – UNWATERING ...... 167 TASK CS 24 – PILING ...... 169 TASK CS 25 – CAISSON FOUNDATIONS ...... 171 TASK CS 26 – STRUCTURE BACKFILLING ...... 173 TASK CS 27 – FORMWORK ...... 174 TASK CS 28 – FALSEWORK ...... 175 TASK CS 29 – INSTALLATION OF BEARINGS ...... 176 TASK CS 30 – STRUCTURAL STEEL BEAM ERECTION ...... 177 TASK CS 31 – REINFORCING STEEL PLACEMENT ...... 178 TASK CS 32 – PRESTRESSING SYSTEMS ...... 179 TASK CS 33 – STRESSING OPERATION ...... 180

62 Design-Build Administration Manual January 2014

TASK CS 34 – GROUTING OF POST-TENSIONING DUCTS ...... 181 TASK CS 35 – BRIDGE DECK WATERPROOFING ...... 183 TASK CS 36 – PRESTRESSED CONCRETE MEMBERS (NORMAL AND HIGH PERFORMANCE CONCRETE) ...... 185 TASK CS 37 – INSTALLATION OF EXPANSION JOINTS ...... 186 TASK CS 38 – TEMPORARY MODULAR BRIDGES...... 188 TASK CS 39 – STRUCTURAL STEEL COATING ...... 189 TASK CS 40 – STEEL PARAPET RAILING ...... 191 TASK CS 41 – OVERHEAD SIGN PLACEMENT ...... 192 TASK CS 42 – RETAINED SOIL SYSTEMS ...... 193 TASK CS 43 – ABRASIVE BLAST CLEANING OF CONCRETE SURFACES AND REINFORCING STEEL ...... 195 TASK CS 44 – LIGHTWEIGHT FILL MATERIALS ...... 196 TASK CS 45 – PRECAST CONCRETE CULVERTS ...... 198 TASK CS 46 – DOWELS IN CONCRETE ...... 200 TASK CS 47 – STEEL BREAKAWAY SIGN PLACEMENT ...... 201 TASK CS 48 – TIMBER BREAKAWAY SIGN PLACEMENT ...... 202 TASK CS 49 – DOWELS INTO BEDROCK ...... 203 TASK CS 50 – FOUNDTION INSTRUMENTATION FOR MONITORING SETTLEMENTS, PORE PRESSURES, LATERAL DISPLACEMENTS ...... 204 TASK CS 51 – MASS CONCRETE ON BEDROCK ...... 205 BITUMINOUS ...... 206 TASK BIT 1 – GRANULAR SEALING ...... 206 TASK BIT 2 – RECLAIMING ASPHALT PAVEMENT ...... 207 TASK BIT 3 – HOT MIX PAVING ...... 208 TASK BIT 4 – CUT AND FILL GROOVES ...... 210 TASK BIT 5 – ROUTING AND SEALING CRACKS ...... 211 TASK BIT 6 – TACK COAT ...... 213 TASK BIT 7 – PAVEMENT MARKING ...... 214 TASK BIT 8 – SURFACE TREATMENT ...... 215 TASK BIT 9 – HOT-IN-PLACE RECYCLING (HIR) ...... 216 TASK BIT 10 – COLD-IN-PLACE RECYCLING (CIR) ...... 217 TASK BIT 11 – IN-PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR ...... 218 TASK BIT 13 – SURFACE SMOOTHNESS MEASUREMENTS INTERIAL PROFILER ...... 219 TASK BIT 14 – EXPANDED ASPHALT STABILIZATION ...... 222 TASK BIT 15 – OPEN GRADED DRAINAGE LAYER ...... 224 TASK BIT 16 – ROUTING AND SEALING CRACKS ...... 225 ELECTRICAL ...... 226 TASK E/AMTS 1 – ELECTRICAL CHAMBERS ...... 226 ELECTRICAL AND ATMS ...... 227 TASK E/AMTS 2 – UNDERGROUND DUCTS ...... 227 TASK E 10 – POLE FOUNDATIONS AND POLE ERECTION ...... 229 TASK E 11 – GROUNDING ...... 231 TASK E 12 – CABLE INSTALLATION ...... 232

63 Design-Build Administration Manual January 2014

TASK E 13 – LUMINAIRES ...... 234 TASK E 14 – POWER SUPPLY EQUIPMENT ...... 235 TASK E 15 – TRAFFIC SIGNAL EQUIPMENT ...... 236 TASK E 16 – TRAFFIC ACTUATION AND DETECTION EQUIPMENT ...... 237 TASK E 17 – HIGH MAST LIGHTING ...... 239 TASK E 18 – SIGNAL ACTIVATION (TEMPORARY AND PERMANMENT INSTALLATION) ...... 241 TASK ATMS 20 – ATMS ELECTRICAL CABLE INSTALLATION...... 243 TASK ATMS 21 – GROUNDING ...... 244 TASK ATMS 22 – POWER SUPPLY EQUIPMENT ...... 245 TASK ATMS 23 – CLOSED CIRCUIT TELEVISION (CCTV) POLES AND MAINTENANCE SITES ...... 246 TASK ATMS 24 – COMMUNICATION CABLE INSTALLATION ...... 248 TASK ATMS 25 – DATA TRANSMISSION EQUIPMENT INSTALLATION ...... 249 TASK ATMS 26 – VIDEO TRANSMISSION / DISPLAY EQUIPMENT INSTALLATION ...... 250 TASK ATMS 27 – CAMERA EQUIPMENT INSTALLATION ...... 251 TASK ATMS 28 – VEHICLE DETECTION EQUIPMENT INSTALLATION ...... 252 TASK ATMS 29 – CABINET AND CONTROLLER INSTALLATION ...... 254 TASK ATMS 30 – VARIABLE MESSAGE SIGN (VMS) INSTALLATION ...... 256 TASK ATMS 31 – SYSTEM INTEGRATION TEST (SIT) VERIFICATION ...... 258 TASK ATMS 32 – PORTABLE VARIABLE MESSAGE SIGN (PVMS) INSTALLATION ...... 259 TASK ATMS 33 – PORTABLE VARIABLE MESSAGE SIGN (PVMS) INSTALLATION ...... 261 TASK ATMS 34 – NON-INTRUSIVE TRAFFIC SENSOR INSTALLATION ...... 263 TASK ATMS 35 – DOME CAMERA INSTALLATION...... 264 TASK ATMS 36 – CAMERA RAISING AND LOWERING DEVICE INSTALLATION ...... 265 TASK ATMS 37 – WIRELESS COMMUNICATION SYSTEMS INSTALLATION ...... 267 TRAFFIC CONTROL ...... 268 TASK TC 1 – GENERAL ...... 268 TASK ENV 2 – USE OF WASTE PRODUCTS / MATERIALS IN THE WORK...... 270 TASK ENV 3 – MANAGEMENT AND DISPOSAL OF EXCESS MATERIALS ...... 271 TASK ENV 4 – WORK IN, ADJACENT TO, AND OVER WATERBODIES ...... 272 TASK ENV 5 – WORK IN AND ADJACENT TO AREAS OF TREES NOT DESIGNATED FOR REMOVAL ...... 273 TASK ENV 6 – CONTROL OF DUST FROM THE WORK ...... 274 TASK ENV 7 – TEMPORARY EROSION AND SEDIMENTATION CONTROL ...... 275 TASK ENV 8 – INCIDENT MANAGEMENT ...... 277 TASK ENV 9 – FISHERIES ACT AUTHORIZATION IMPLEMENTATION AND MONITORING ...... 278

64 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 1

CLEARING, CLOSE CUTTING, AND GRUBBING

Task # Activity

GD 1.1 Check for proper installation of tree barrier protection prior to clearing, close cutting or grubbing activities.

GD 1.2 Check that clearing activities occur during permitted timing windows, if specified by the Contract Documents to avoid nesting periods of migratory birds (e.g. May 1st to August 1st).

GD 1.3 M Check that all clearing, close cutting and grubbing debris is removed and managed as per the Contract Documents.

GD 1.4 Check that clearing, close cutting and grubbing is carried out to the limits given.

GD 1.5 Check that Grubbing is performed as specified (stumps, roots, embedded logs, debris, and secondary growth) and stripping depths are as indicated in the Contract Documents.

LEVEL OF INSPECTION – B1/E2

65 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 2

BOULDER CLEAN-UP

Task # Activity

GD 2.1 Record location of disposal sites.

LEVEL OF INSPECTION – B1/E2

66 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 3

STRIPPING

Task # Activity

GD 3.1 M Confirm stripping is completed in accordance with the construction sub-grade report widths and that proper depth of stripping is achieved.

GD 3.2 M Check required amount of stripped organic material is stockpiled for topsoil as specified prior to disposal of surplus material. Record the location of the stockpile sites.

GD 3.3 Check that erosion control measures are in place and functioning properly prior to stripping.

GD 3.4 Check that topsoil piles are positioned away from waterbodies.

GD 3.5 Check that sheetflow from stockpiles is intercepted using silt fence, straw bale or barriers.

LEVEL OF INSPECTION – B1/D2

67 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 4

SWAMP TREATMENT

Task # Activity

GD 4.1 Floating the road. M (i) Check during construction that the integrity of the mat material is maintained. M (ii) Check that no rock fill is in contact with the root mat. (iii) Check that care is taken in locating ditching and that root material is not disturbed. (iv) Beware of culverts being inserted below the root mat. (v) Swamp waves shall not be excavated or otherwise disturbed. M (vi) Confirm each layer is built using an outside to inside sequence by keeping the outer one third portions of the layer a least 30 metres ahead of the centre portion (vii) Check that if geotextiles are used that they are placed in accordance with the specifications (viii) Check that the rate of embankment construction is carried out as per Special Provisions (time, pore pressure dissipation levels, etc.) (ix) If berms are being constructed check that that the berm is constructed appropriately during the construction of the embankment (x) Check that culverts are installed with specified articulation and or camber.

GD 4.2 Excavation M (i) Survey and record the limits and depth of the excavation and compare them to the design limits. M (ii) Check that during excavation, material removed is managed as specified in the Contract Documents. M (iv) Check that excavation of displaced materials and backfilling is carried out simultaneously, and in such a way as to displace the muskeg and produce a mud wave (displacement method). M (vi) If excavated material is being used for, or blended for use as topsoil, then check that the required amount of excavated organic material is stockpiled for topsoil as specified prior to disposal of surplus material. Record location of stockpile site. M (vii) Check that backfill materials are as specified in the Contract Documents and are compacted to the target density.

68 Design-Build Administration Manual January 2014

GD 4.3 Surcharging – See Task GD 42 (i) Check construction staging and verify embankment and surcharge is constructed in accordance with staging details. (ii) Check that surcharge is placed to the geometry shown on the contract drawings. M (iii) Check that proper surcharge material is used and placed to height and limits specified in the Contract Documents. Check that surcharge is removed only after required time period, settlement, or pore water pressure is achieved.

LEVEL OF INSPECTION – A2

69 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 5

EARTH CUT

Task # Activity

GD 5.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 5.2 M Check suitability of cut material for use as fill in other locations.

GD 5.3 M Watch for any seepage areas in earth cuts, and provide for appropriate treatments as required. Check that any advanced dewatering scheme to facilitate the excavation is carried out.

GD 5.4 M Check that treatment of frost susceptible soil area is completed as specified in the Contract Documents. Ensure that the disposition of material from each earth cut area is recorded.

GD 5.6 Check for proper crown and that adequate drainage is maintained.

GD 5.7 Check that the excavation is carried out to the requirements of the Contract Documents.

GD 5.8 M Verify and record that grading tolerances are correctly applied and all slopes conform to the acceptance .

GD 5.9 Check that longitudinal and transverse transition treatments (cut to fill, fill to fill) are constructed correctly.

GD 5.10 Check that soil sloughing is avoided and controlled during excavation procedure.

GD 5.11 M Check that toe drains, slope drains and / or interceptor ditches are properly constructed.

GD 5.12 M Record starting and ending dates of various earth operations for conformance with timing constraints.

GD 5.14 Check that boulders on excavated slopes are removed in accordance with the specifications.

LEVEL OF INSPECTION – D2

70 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 6

EARTH EMBANKMENT

Task # Activity

GD 6.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 6.2 Check that any organic or deleterious material is sub-excavated prior to embankment construction.

GD 6.3 M Check that special embankment foundation and benching is carried out as specified in the Contract Documents.

GD 6.4 M Check Design-Builder’s required quality control tests to determine if target density is obtained.

GD 6.5 Inspect embankment construction to check that the specified depth of layers are maintained, that oversize and frozen material is not used, that material is not placed on frozen ground or on ice or snow, and that the cross fall is adequate for drainage.

GD 6.6 Check that boulders are placed in accordance with the specifications.

GD 6.7 If a berm is required; check that it is constructed before the main fill is built to a level higher than the berm.

GD 6.8 If a surcharge is used, see task GD 42.

GD 6.9 M Verify and record that grading tolerances are correctly applied and all slopes conform to the acceptance envelope prior to placement of subbase material.

GD 6.10 M Check that fill is placed and compacted according to the specifications – layer compaction or modified layer compaction.

GD 6.11 Check that appropriate construction procedure is conducted for side hill or sloping sections.

GD 6.12 For embankments over soft ground, check that rate of embankment construction is carried out as per Special Provisions.

GD 6.13 Check that all field test results and information are received within 2 Business Days following completion of a lot.

71 Design-Build Administration Manual January 2014

LEVEL OF INSPECTION – D2

72 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 7 A

ROCK EXCAVATION

Task # Activity

GD 7.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action. GD 7.2 Check that the Design-Builder has removed all stumps, roots, vegetation and soil overlaying rock to be excavated to the width specified on the construction subgrade report.

GD 7.3 M Check that overburden is excavated from each transition treatment area prior to blasting.

GD 7.4 Check that removal of overburden and earth is carried out sufficiently in advance to permit surveying of original rock cross-sections.

GD 7.5 Check that disposal of overburden material is as specified. Check that disposal sites are positioned away from waterbodies. Check that sheetflow from disposal is intercepted using silt fence, straw bale or sandbag barriers.

GD 7.6 M Check that blasting design, blasting permit, and pre-construction survey have been submitted.

GD 7.8 Check qualifications of the Blasting Designer.

GD 7.9 M Check that proper notifications are provided to the appropriate authorities. Check that appropriate notification is conducted prior to blasting.

GD 7.10 M Check that all safety precautions are observed prior to blasting, including the sounding of audible warning device before and after blasting as required. Check that protective measures to control fugitive flyrock, as specified, are used around private properties and/or Utility locations.

GD 7.11 Check that noise, vibration and dust levels are controlled as required.

GD 7.12 M Check that a “Trial Blast” for drilling and blasting is carried out to verify the blasting design in general.

GD 7.13 Check that drilling depth is sufficient to provide the required shatter and extra depth shatter is specified.

73 Design-Build Administration Manual January 2014

GD 7.14 M Check that extra depth shatter is verified and drilling depths recorded. Check that drilling pattern is as per the blasting design.

GD 7.15 Check that drilling pattern is as per the blasting design. Record type and amount of explosive material used. Record drilling depths, limits and pattern.

GD 7.16 M Check that there is effective drainage to ditches and transition treatments by confirming that no undrained pockets are left in the road bed or ditches.

GD 7.17 During and after scaling inspect rock face for potential rockfall hazard and discuss any concerns with the CSA. Check that any special rockfall hazard designs have been properly implemented, as indicated in the Contract Documents.

GD 7.19 M Document the disposition of all rock excavation material showing how cut is excavated, type of equipment used, where it is being disposed including the equipment involved and the time and duration of the work.

GD 7.20 Check that a post construction survey is carried out by the Design-Builder

GD 7.21 M Verify and record that grading tolerances are correctly applied and all excavations conform to the acceptance envelope.

GD 7.22 Coordinate with Rock Engineering Specialist (if applicable) to inspect rock face locations such as foundations founded on a rock ledge to determine rock mass stabilization.

GD 7.23 Check that blasting monitoring equipment, procedure and recording is conducted as specified.

GD 7.24 Check Design-Builder’s construction blasting records / blasting reports.

LEVEL OF INSPECTION – A2

74 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 8

ROCK EMBANKMENT

Task # Activity

GD 8.1 M Check that rock fill is built in accordance with SP206S03, unless otherwise specified in the Contract Documents.

GD 8.3 Check that rock fill is not placed on frozen soil.

GD 8.4 If rock fill is used to displace soft underlying materials, the centre should be kept ahead of the sides or one side on sidehill organic displacement.

GD 8.5 Check equipment type and size, number of passes, and lift thickness for the compaction of rock embankment.

GD 8.6 M Check that shale embankment materials are spread and compacted in uniform layers as specified in the Contract Documents.

GD 8.7 Check that large particle sizes are within specified size restriction and are properly positioned within the rockfill embankment.

GD 8.8 Check that chinking is carried out to fill surface voids.

GD 8.9 Check that approved procedures are followed for surcharge loading. See Task GD 42.

GD 8.10 M Verify and record that grading tolerances are correctly applied and all fill slopes conform to the acceptance envelope.

GD 8.11 M Record daily, the construction of Rock Fill (location of source of material used, final disposition of the material, the equipment involved, and the time and duration of the work).

GD 8.12 Check that direction of Rock fill placement is such that mud waves are displaced away from the embankment.

LEVEL OF INSPECTION – C-2

75 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 9

TRANSITION TREATMENTS IN ROCK OR EARTH

Task # Activity

GD 9.1 M Verify and record that proper transition treatment is carried out during initial construction period, before fill placement interferes with the excavation. Verify and record that grading tolerances are correctly applied and all slopes conform to the acceptance envelope prior to backfilling. Backfill as specified in the Contract Documents.

GD 9.2 Check that transition has positive drainage.

LEVEL OF INSPECTION – D2

76 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 10

FROST HEAVE TREATMENT

Task # Activity

GD 10.1M Check that material supplied by the Design-Builder is sampled as required. Check that the polystyrene complies with environmental specifications.

GD 10.3 M Record that frost susceptible soils are removed and replaced with acceptable material to the specified grades, lengths and tolerances. Adjust grades and limits depending on extent of frost susceptible soils. Verify transition between frost treatment and normal grading sections is constructed properly.

GD 10.4 Check to that the Design-Builder has provided adequate drainage from treated area.

GD 10.5 Check expanded polystyrene is installed as follows: (i) Check that the sheets are properly placed with regards to tight and staggered joints; (ii) Check that sheets are secured to prepared surface; and (iii) Check that backfill is placed by dumping, spread and compacted in one lift, free of oversized material and is of sufficient depth to protect the polystyrene.

GD 10.6 M Check that backfill materials are compacted to the target density.

LEVEL OF INSPECTION – B2

77 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 11

BASE AND SUBBASE

Task # Activity

GD 11.1 Check for any evidence of contamination from subgrade pumping into subbase and have the Design-Builder take appropriate corrective action.

GD 11.2 M Check that quality assurance samples are obtained for testing as specified in the Contract Documents. Conduct visual inspection of material for contamination, including clay balls, clay coated particles or foreign material. Where contamination is observed or suspected take appropriate action.

GD 11.3 M Check that subbase and base materials comply as specified in the Contract Documents. Check that no Blast Furnace Slag material is being place in the base and sub base. Check Design-Builder’s compaction density readings to see that all the work falls within the specified tolerances.

GD 11.5M Verify and record horizontal and vertical grading tolerances prior to the placement of the next type of material or pavement.

GD 11.6 M Check that material control, distribution and weighing conform to the Contract Documents.

GD 11.7 Check that all field test results and information are received within 2 Business Days following completion of a lot.

GD 11.8 Check that all field test results and information are received prior to placement of Hot Mixed Asphalt (HMA).

LEVEL OF INSPECTION – D2

78 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 12

RESTORING ROADWAY SURFACES

Task # Activity

GD 12.1 M Check that all deleterious material is removed from grade prior to restoration.

GD 12.1 Check that the restored roadway surface is compacted to the target density.

GD 12.2 M Check the Design-Builder’s crossfall on the restored roadway surface for correctness prior to placement of the next type of material or pavement.

LEVEL OF INSPECTION – E2

79 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 13 A

GRADE

Task # Activity

GD 13.1 M A monitoring checking frequency of a minimum of 25% per day (but not limited to), is required to be recorded for all of Design-Builder’s quality control grade checks to verify the Design-Builder’s ability to ensure that the grades and cross sections are within the specified tolerances. When one half of the Design-Builder’s quality control operation has been successfully completed the monitoring frequency may be reduced to a minimum (but not limited to) of 5%, with the approval of the CSA.

Quality Assurance checks for subgrade and granulars (prior to the placement of the next type of material or pavement) shall include the record of station, actual elevation and offset. This information is to be recorded at the specified intervals in a separate field book. The CA survey work will be separate and independent from the Design- Builder’s Quality Control surveys.

During the grade check, the width of placement should be checked and recorded, and when the horizontal tolerances are exceeded, elevations and distances must be recorded.

LEVEL OF INSPECTION – D2

80 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 13 B

COMPACTION

Task # Activity

GD 13.1 M A testing frequency of a minimum of 25% per day or per Design- Builder’s current testing amounts (but not limited to), is required to be recorded for all of Design-Builder’s quality control testing requirements to verify the Design-Builder’s ability to control compaction. This is to be done on an ongoing base.

When one half of the Design-Builder’s quality control operation has been successfully completed the physical testing frequency may be reduced to a minimum (but not limited to) of 5%, with the approval of the CSA

LEVEL OF INSPECTION – D2

81 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 14

BORROW PITS AND QUARRIES

Task # Activity

GD 14.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 14.2 Check that the pit or quarry is worked to the approved line and grade and appropriate measurements are taken to support payment.

GD 14.4 Check that stripping material does not contaminate the borrow.

GD 14.5 M Check that the operation of the pit or quarry is carried out in accordance with the Aggregate Sources List, site plan and permit / Letter of Approval. If the Design-Builder does not operate in accordance with the site plan and/or the site plan standards and operational requirements, notify the Design-Builder by Instruction Notice and notify the CSA immediately.

GD 14.6 M Check that the rehabilitation of the pit or quarry, at the completion of the job, is in accordance with the site plan.

LEVEL OF INSPECTION – C1

82 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 15

WAYSIDE PERMIT, AGGREGATE PERMIT, AND LETTER OF APPROVAL PITS AND QUARRIES

Task # Activity

GD 15.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 15.2 Check that required stripping is carried out and all unsuitable material is removed from the pit or quarry face. Visually inspect for seams of unsuitable material in pit or quarry face during extraction.

GD 15.3 M Check that the operation of the pit or quarry is carried out in accordance with the site plan and Aggregate / Wayside Permit / Letter of Approval. If the Design-Builder does not operate in accordance with the site plan standards and / or the operational requirements, notify the Design-Builder by Instruction Notice and notify the CSA immediately.

GD 15.4 M Check that the rehabilitation of the pit or quarry, at the completion of the job, is in accordance with the site plan.

LEVEL OF INSPECTION – C1

83 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 17

DITCHING

Task # Activity

GD 17.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 17.2 M Check that ditch grading tolerances are correctly applied and all slopes conform to acceptance envelope.

GD 17.3 Check that suitable material excavated from ditches is utilized in fill areas.

GD 17.4 Check that unsuitable material is managed as specified in the Contract Documents.

GD 17.5 M Check for positive drainage from field tiles.

LEVEL OF INSPECTION – E2

84 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 18

SUBDRAINS

Task # Activity

GD 18.1 M Check specified size of pipe, including filter material. Check that all the delivered material is stored properly and verify that it is being supplied from the approved list that was submitted by the Design- Builder at the commencement of the contract.

GD 18.3 Check that perforations are placed down when their purpose is to collect water and they are bedded in free draining filter material. Check that pipes without perforations are used when their purpose is to transport water.

GD 18.4 Check that couplings are suitable for and compatible with the class and type of pipe and installed correctly.

GD 18.5 M Check that granular materials comply with the specifications and are compacted to the target density.

GD 18.6 If impervious clay cap is required, check that cap is properly built.

GD 18.7 M Check that proper connection to manholes, catchbasins, and ditch inlets (grouting and grade) are made.

GD 18.8 Check that each outlet location is marked with an approved marker and is visible from the driving portion of the roadway.

GD 18.9 Check that outlet and collector pipers are not crushed during backfilling operations.

GD 18.10 Check that outlet and collector pipes are placed to required slope and grade to provide gravity flow.

GD 18.11 Check that rodent grates are installed securely and quickly after subdrain installation.

GD 18.12 M Check that the trenches are excavated to the width, grade and alignment specified in the Contract Documents.

GD 18.13 Check for trench stability during excavation.

GD 18.14 Check that pipe bedding and backfilling is conducted as specified.

85 Design-Build Administration Manual January 2014

GD 18.15 Check that inspection report is completed by the Design-Builder for the excavation, bedding and backfilling.

GD 18.16 Check that a non-woven geotextile is used to wrap the trench when 19 mm clear stone is specified as backfill.

GD 18.17 M Check that video camera inspection is conducted as specified.

LEVEL OF INSPECTION – D2

86 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 19

EXCAVATION FOR CULVERTS

Task # Activity

GD 19.1 Verify and record that all fisheries-related environmental mitigation measures have been installed and are functioning properly prior to the start of excavation.

GD 19.2 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 19.3 M Check that the dewatering and flow passage arrangements comply with restrictions / provisions specified in the Contract Documents.

GD 19.4 M Check that unwatering is not causing erosion of soil at the outlet and other environmental concerns (i.e. muddy water discharge). Check that the Design-Builder has the standby equipment (pumps, hose, etc.) on site as required in the environmental submission. Check that the Design-Builder has obtained a Permit to Take Water in accordance with Special Provision 100S59.

GD 19.5 Check that dust and debris from construction operations is not entering a watercourse or Environmentally Sensitive Area.

GD 19.6 Confirm that any other relevant environmental constraints have been addressed.

GD 19.7 Check that the founding soil is sound and undisturbed. Check that all loosened, soft, organic and deleterious material and boulders at the foundation base are removed and replaced with suitable, compacted granular material or mass concrete.

GD 19.8 Investigate pipe relocation to avoid cutting the organic mat when the embankment rides the swamp.

GD 19.9 M Confirm and record limits of excavation (width and depth) to determine if they conform to Contract Documents. Confirm and record limits of frost tapers at shoulderline and centreline. Confirm that the specified taper slope continues until it intersects subgrade / bottom of roadbed granular. If the crossing is identified as a watercourse in the Contract Documents, limit disturbance beyond the end of the culverts.

87 Design-Build Administration Manual January 2014

GD 19.10 For crossings identified as watercourses in the Contract Documents, survey existing streambed elevation prior to construction to determine if the new culvert depth is at or below the exiting streambed elevation (i.e. a minimum 300mm depression unless otherwise specified in the Contract Documents) to create low flow channel.

GD 19.11 Check for signs of basal heave due to unbalanced hydrostatic head conditions.

GD 19.12 Check for working slabs / working pads.

GD 19.13 Check that any temporary protection scheme to facilitate the excavation and construction of the culvert is carried out.

LEVEL OF INSPECTION – C2

88 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 20

BACKFILLING FOR CULVERTS

Task # Activity

GD 20.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 20.2 M Check all the delivered material to verify that it is as specified in the Contract Documents.

GD 20.3 Check that all pipes are correct class and reject those that are damaged and cannot be repaired.

GD 20.4 Check that advanced dewatering is conducted as required to prevent soil sloughing, basal heave and boiling. Check that excavations are free of water at all times.

GD 20.5 M Check that alignment, invert and designed widths are adhered to, as loading on pipe is partially dependent on trench widths.

GD 20.6 M Check that dewatering is not causing erosion of soil at the outlet and other environmental concerns (i.e. muddy water discharge). Check that the Design-Builder has the standby equipment (pumps, hose, etc.) on site as required in the environmental submission.

GD 20.7 Check the foundation for transition from firm to soft material, high points, soft spots, stones or boulders under culvert; general foundation problems due to unstable soil conditions, prior to placing bedding or embedment material.

GD 20.8 M Check that backfilling materials are sampled as required, comply with the specifications, and are compacted to the target density. Check that the proper compacted lift thickness is as specified. (Elevation not to exceed existing streambed elevation.)

GD 20.9 If required, check that upstream end of the pipe is embedded and material is properly compacted to prevent seepage.

GD 20.10 M Check that the bedding and the backfilling materials are placed in the dry, and as specified in the Contract Documents.

GD 20.11 Check that backfilling is compacted under the haunches.

89 Design-Build Administration Manual January 2014

GD 20.12 Check that proper gaskets and couplers are used. Check that all gaskets and joints are tight. Check for proper camber. Where applicable, check that joints are lapped in direction of flow.

GD 20.13 Check that pipes and connections are kept clean and free of foreign material.

GD 20.14 Check that the strutting requirements are met when required.

GD 20.15 Check that backfilling is brought up evenly on both sides of the pipe at the same time.

GD 20.16 Check that compaction equipment does not impose excessive vibrations on structure.

GD 20.17 Check that specified depth of cover is placed before heavy equipment is allowed over culvert location.

GD 20.18 Check that oversize particles are removed.

GD 20.19 M Record trench widths, type of bedding and type of backfilling.

GD 20.20 For crossings identified as watercourses in the Contract Documents, survey existing streambed elevation if not provided in the Contract Documents to check that the new culvert depth does not exceed the exiting streambed elevation (i.e. a minimum 300mm depression unless otherwise specified in the Contract Documents) to maintain low flow channel.

GD 20.22 M Check that post installation inspection is done in accordance with Special Provision 104S02.

LEVEL OF INSPECTION – D2

90 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 21

SEWER IN TRENCH

Task # Activity

GD 21.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 21.2 M Check all the delivered material to verify that it is as specified in the Contract Documents.

GD 21.3 Check that all pipes are correct class and reject those that are damaged and cannot be repaired.

GD 21.4 Check that advanced dewatering is conducted as required to prevent soil sloughing, basal heave and boiling. Check that excavations are free of water at all times.

GD 21.5 M Check that alignment, invert and designed widths are adhered to.

GD 21.6 Check that unwatering is not causing erosion of soil at the outlet and other environmental concerns (i.e. muddy water discharge). Check that the Design-Builder has the standby equipment (pumps, hose, etc.) on site as required in the environmental submission.

GD 21.7 Check the foundation for transition from firm to soft material, high points, soft spots, stones or boulders under culvert; general foundation problems due to unstable soil conditions, prior to placing bedding or embedment material.

GD 21.8 M Check that backfilling materials are sampled as required, comply with the specifications, and are compacted to the target density. Check that the proper compacted lift thickness is as specified. (Elevation not to exceed existing streambed elevation.)

GD 21.9 M Check that the bedding and the backfilling materials are placed in the dry, and as specified in the Contract Documents.

GD 21.10 Check that backfilling is compacted under the haunches.

GD 21.11 Check that proper gaskets and couplers are used. Check that all gaskets and joints are tight. Check for proper camber. Where applicable, check that joints are lapped in direction of flow.

91 Design-Build Administration Manual January 2014

GD 21.12 Check that pipes and connections are kept clean and free of foreign material.

GD 21.13 Check that the strutting requirements are met when required.

GD 21.14 Check that backfilling is brought up evenly on both sides of the pipe at the same time.

GD 21.15 Check that compaction equipment does not impose excessive vibrations on structure.

GD 21.16 Check that specified depth of cover is placed before heavy equipment is allowed over sewer location.

GD 21.17 Check that oversize particles are removed.

GD 21.18 M Record trench widths, type of bedding and type of backfilling.

GD 21.19 M Check that post installation inspection is done in accordance with Special Provision 104S03.

LEVEL OF INSPECTION – D2

92 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 22

SEWER TUNNEL / JACK AND BORE

Task # Activity

GD 22.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 22.2 Check that sufficient indicators are set up and maintained to detect and monitor any movements within and outside the tunnel.

GD 22.3 Check that techniques employed meet the specification.

GD 22.4 M Check that alignment and grade are maintained.

GD 22.5 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 22.6 Check that permanent liners are supplied and installed.

GD 22.7 Check and verify the soil spoil.

GD 22.8 Check that grouting materials are properly supplied and placed.

GD 22.9 Report all ground movements, failures, seepage zones and changes in soil conditions to the CSA.

GD 22.10 Check that appropriate dewatering is conducted to avoid soil cave-in and sloughing during the tunnelling.

GD 22.11 Check to verify any obstructions attributable to boulders and cobbles.

GD 22.13 Check that excavation shafts and shoring systems are stable.

GD 22.14 Check that stamped working drawings are submitted.

GD 22.15 Check for Tunnel Portal Work Plan.

GD 22.16 Check for Primary Support plans, including materials, connection details and method of installation.

93 Design-Build Administration Manual January 2014

GD 22.17 Check for Tunnel Excavation Work Plan including sequence, dimensions, methods, provisions for controlling line and grade, ventilation and muck handling methods.

GD 22.18 Check Secondary Liner materials, installation.

GD 22.19 Check criteria for assessment of Roadway subsidence.

GD 22.20 Check that instrument monitoring is installed as per the Contract Documents.

LEVEL OF INSPECTION – C2

94 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 23

WATERMAIN IN TRENCH

Task # Activity

GD 23.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 23.2 Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 23.3 Check that excavations are free of water at all times.

GD 23.4 M Check that alignment and designed widths are adhered to as loading on pipe is partially dependent on trench widths.

GD 23.5 Check that specified bedding is used and constructed as per the Contract Documents.

GD 23.6 M Check that watermain is placed in trench to depth as specified in the Contract Documents for frost penetration.

GD 23.7 Check that all pipes are correct type and class.

GD 23.8 During progress of work check that pipes, connections and appurtenances are kept clean and free of foreign material.

GD 23.9 Check that all pipe ends are lubricated with material recommended by the pipe manufacturer prior to installation.

GD 23.10 Check that fabricated bends are used when changes in line or grade are required.

GD 23.11 Check that any connections, caps and bends are provided with thrust blocks and wedges.

GD 23.12 M Check that backfill materials are as specified in the Contract Documents and the required compaction checks are made.

GD 23.13 Check that backfill is brought up evenly on both sides of the pipe at the same time.

95 Design-Build Administration Manual January 2014

GD 23.14 Check that oversize particles are removed.

GD 23.15 Check that appropriate equipment is used for compaction until the specified depth of cover over the pipe is achieved.

GD 23.16 M Observe all appropriate testing for approvals.

GD 23.17 Check that top of pipe elevations are recorded.

GD 23.18 Check that measurements of bends, ties, connections, etc. are recorded.

GD 23.19 M Check that watermains are flushed and disinfected as specified.

GD 23.20 Check that the founding soil is sound and undisturbed.

LEVEL OF INSPECTION – C2

96 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 24

MANHOLES, CATCHBASINS, AND DITCH INLETS

Task # Activity

GD 24.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 24.2 Check type, alignment, offset and grades of manholes, catchbasins and ditch inlets.

GD 24.3 M Check correct positioning and installation of ladder rungs and safety grates.

GD 24.4 Visually check all materials used for quality and/or damage (Pre-Cast); i.e. honeycombing, cracks, voids, surface defects, etc.

GD 24.5 M Check that, backfill materials are as specified in the Contract Documents and are compacted to the target density.

GD 24.6 M Check that poured in place manholes, catchbasins and ditch inlets conform to the Contract Documents.

GD 24.7 Check that the frustum is located and constructed properly.

GD 24.8 Check for the correct placement of reinforcing steel.

GD 24.9 Check that specified compaction is obtained under pipes entering or exiting manholes, catchbasins and ditch inlets.

GD 24.10 Check for proper placement of weep-holes.

GD 24.11 Check for proper placement of pipe subdrain outlet in structures.

GD 24.12 M Check that manholes, catchbasins and ditch inlets are cleaned out. Check that excess materials from the work are stored and disposed of as specified in the Contract Documents Check that honeycombed areas are parged and the grates and pipes are grouted upon completion.

LEVEL OF INSPECTION – E2

97 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 25

GEOTEXTILE

Task # Activity

GD 25.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 25.2 Check that material supplied by the Design-Builder is sampled as required and forwarded for testing.

GD 25.3 M Check that each roll to be used has a tag showing product name and number and it meets the design requirements (woven or non-woven, Class I or Class II, F.O.S.).

GD 25.4 Check that the geotextile is contained in opaque (light blocking) wrapping.

GD 25.5 Check installation area for removal of sharp objects that may puncture the geotextile.

GD 25.6 Check that the proper overlap has been maintained during installation.

GD 25.7 Check that the geotextile is not exposed to sunlight for more than three Business Days.

GD 25.8 Check that drop height for material placed onto it is less that 1 metre to prevent damage of geotextile.

GD 25.9 Check that sufficient geotextile is placed on the ditch sides to prevent erosion of the sides of the ditch.

GD 25.10 Check that all materials contaminated or damaged during installation are either replaced or repaired so that the geotextile will perform as intended.

LEVEL OF INSPECTION – E2

98 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 26

GRANULAR BLANKET

Task # Activity

GD 25.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 26.1 M Check that erosion and sediment control schemes are in place and functioning. Examine with the Design-Builder to determine if additional erosion control measures or additional locations may be required.

GD 26.2 Check that granular materials comply with the specifications.

GD 26.3 M Check that slope to receive blanket is properly prepared. Excavate beyond finished surface such that the granular blanket will fit the theoretical cut slope line.

GD 26.4 Check that granular blanket is placed as excavation progresses and completion of the blanket coincides with completion of the cut.

GD 26.5 Check construction of interceptor ditches.

GD 26.6 Check the placement of any subdrains below the ditch line.

GD 26.7 Check that care is taken in placement to minimize segregation, especially if placed under water.

GD 26.8 Check that thickness and evenness of placement will provide a stable free draining slope material.

LEVEL OF INSPECTION – E2

99 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 27

RIP RAP

Task # Activity

GD 27.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 27.2 Check that rip rap material is as specified in the Contract Documents.

GD 27.3 Check that rip rap has an adequate foundation.

GD 27.4 M When placed on slopes, check that rip rap is countersunk into the surface of the slope.

GD 27.5 Check that rip rap is placed in a manner that will not tear or otherwise damage the geotextile.

GD 27.6 Check that rip rap is placed in accordance with any applicable timing restrictions.

GD 27.7 Check that the rip rap when placed on a slope is placed at the toe first and progresses up the slope.

LEVEL OF INSPECTION – C1/E2

100 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 28

GABIONS

Task # Activity

GD 28.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 28.2 Check that the water table level is managed as specified in the Contract Documents.

GD 28.3 If working in the water, check that work is isolated from the water as specified. Check that timing restrictions are adhered to, as specified.

GD 28.4M Confirm that any other relevant environmental constraints have been addressed.

GD 28.5 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 28.6 M Check that the founding soil is sound and undisturbed.

GD 28.7 Check that bed is uniform, trimmed, not frozen and consolidated and check for the need of scour protection.

GD 28.8 M Check that gabions are installed to the lines and grades as specified in the Contract Documents.

GD 28.9 Check proper assembly, positioning and tying.

GD 28.10 Check that gabions are placed in tension prior to filling to achieve proper alignment and compaction.

GD 28.11 Check that transverse and vertical joints between gabions are staggered.

GD 28.12 Verify the quality, size and proper placement of the stone.

GD 28.13 Check that the front face is hand packed to minimize voids.

LEVEL OF INSPECTION – C1/E2

101 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 29

TOPSOIL

Task # Activity

GD 29.2 Check that topsoil stockpiles are positioned away from waterbodies.

GD 29.3 M Check that erosion and sediment control schemes are in place and functioning. Examine with the Design-Builder to determine if additional erosion control measures or additional locations may be required.

GD 29.4 M Check that the quality of the native, imported, or blended topsoil meets Contract Document requirements including the submission of applicable test results.

GD 29.5 Check that topsoil is not used for filling depressions or wasted.

GD 29.6 M Check that topsoil is spread uniformly to the depth specified.

LEVEL OF INSPECTION – B1/E2

102 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 30

SODDING

Task # Activity

GD 30.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 30.2 M Check that surface preparation of the areas designated for sodding has been completed prior to sodding.

GD 30.3 Check application of fertilizer.

GD 30.4 Check placement of sod ensuring that placement is as specified.

GD 30.5 Check that the performance measures are met. If not, perform required activity under “Failure to Meet Performance Measures” section of the specification.

LEVEL OF INSPECTION – E2

103 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 31

SEED AND COVER

Task # Activity

GD 31.1 M Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action. . GD 31.2 Check that Certificate of Seed Analysis is provided by Design-Builder 24 hours prior to application of seed. Review Certificate of Analysis for compliance with specification

GD 31.3 M Check that the surface preparation of areas to be seeded has been prepared in accordance with the specification.

GD 31.4 Check that the Design-Builder does not apply seed and cover under adverse weather conditions as stated in the specification.

GD 31.5 Check that the Design-Builder has laid out all locations for various seed mixes and different cover types.

GD 31.6 M Check that the specified cover is applied as a separate operation immediately after the application of seed, fertilizer and water.

GD 31.7 M Follow the inspection intervals and check that the performance measures are met. If not, perform required activity under “Failure to Meet Performance Measures” section of the specification.

LEVEL OF INSPECTION – E2

104 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 32

FENCE

Task # Activity

GD 32.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 32.2 Check that preservative treated wood is identified with certification marks authorized by the Canadian Wood Preservers Bureau.

GD 32.3 Check the preservative treated wood to determine if the splits and checks are within specified limits.

GD 32.4 Check that all posts and rails are fabricated from galvanized steel pipe for chain link fence.

GD 32.5 M Check that fence is placed in accordance with the requirements of the property agreements and Contract Documents.

GD 32.6 Check that fence posts are the specified length.

GD 32.7 Check that all end, corner, anchor, line, straining and gate posts are properly installed with regard to depth, alignment, and spacing.

GD 32.8 Check all bracings are correctly installed.

GD 32.9 Check that loose material in the bottom of the posthole is tamped or removed prior to placing the posts.

GD 32.10 Check that all posts are vertical with the large end down and that the backfill is properly tamped.

GD 32.11 Check that steel wire for chain link fence fabric conforms to the requirements of the Contract Documents.

GD 32.12 Check that all fittings and accessories for chain link fences are galvanized.

GD 32.13 Check that all gates for chain link fence open approximately 180 degrees and that the gates for highway fence open into the owner’s land and close by gravity.

GD 32.14 Check that all fences are maintained throughout the duration of the contract.

105 Design-Build Administration Manual January 2014

GD 32.15 Check that concrete footings are constructed properly with regards to forming and placement of concrete.

GD 32.16 Check that all abraded and damaged surfaces are repaired and coated with approved zinc pigmented paint.

LEVEL OF INSPECTION – E1

106 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 33

GUIDE RAIL

Task # Activity

GD 33.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 33.2 Check that all preservative treated wood is identified with certification marks authorized by the Canadian Wood Preservers Bureau.

GD 33.3 Check a minimum of 10% of the guide rail during installation and record any deficiencies.

I. Check that cable guide rail is never located behind a curb.

II. Check the guide posts to determine if the splits and checks are within specified limits.

III. Check that guide rail is erected at the specified location and offset.

IV. Check that guide posts are the specified length.

V. Check that loose material in the bottom of the post hole is tamped or removed prior to placing the posts.

VI. Check that anchor blocks are constructed properly with regards to forming and placement of concrete.

VII. CA to review guiderail layout as per Contract Documents.

GD 33.4 M Complete a detailed inspection of 25 % of the guide rail recording any deficiencies.

I. Check that all posts are vertical and that the backfill is properly tamped.

II. Check the guide posts for cracks and splits.

III. Check that stretching, stapling and splicing is completed.

IV. Check that posts are cut off correctly, chamfered and tops treated and mounting height is correct.

107 Design-Build Administration Manual January 2014

V. Check that the steel beam mounting height is correct.

VI. Check that Steel Beam guide rail in the vicinity of concrete surfaces is bolted to these surfaces.

VII. Confirm placement of reflectorized strips.

VIII. Check that the Steel Beam guide rail elements are overlapped in the direction of adjacent traffic flow.

IX. Check that where the steel beam guide rail is behind the curb, the offset is less that 250mm.

X. Check that all bolts, washers and nuts are placed and affixed securely to all plates, angles, posts and steel rail, as required.

LEVEL OF INSPECTION – B1/D2

108 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 34

ECCENTRIC LOADER BARRIER AND EXTRUDERS

Task # Activity

GD 34.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 34.2 Check that all preservative treated wood is identified with certification marks authorized by the Canadian Wood Preservers Bureau.

GD 34.3 Check the first two end treatments during installation and record any deficiencies. When deficiencies are identified, inspection frequencies may be increased with the approval of the CSA.

I. Check the preservative treated wood to determine if the splits and checks are within specified limits.

II. Check that guide rail is erected at the proper locations.

III. Check that guide rail posts are the specified length.

IV. Check that anchor posts, breakaway posts and offset blocks are properly installed with regards to depth, alignment and spacing. Check the holes drilled at the front of the posts are in the direction of traffic.

V. Check foundation tubes and soils bearing plates are properly installed.

VI. Check that loose material in the bottom of the posthole is tamped or removed prior to placing the posts.

VII. Check that foreslope crossfall is graded properly to allow proper end treatment installation and positive drainage.

GD 34.4 M Complete a detailed inspection of 25% of the end treatments recording any deficiencies.

I. Check that all posts are vertical and that the backfill is properly tamped.

II. Check in the area 3m wide and 30m long behind the end treatment that the ground is not steeper than 4:1 and is

109 Design-Build Administration Manual January 2014

traversable (protrusions, rip rap, etc. size below 75mm are acceptable).

III. Check that the strut between foundation tubes at post one and two is attached properly.

IV. Check that channels are installed at proper locations, elevations, and are terminated as required.

V. Check that the steel beam mounting height is correct.

VI. Check that cable is snug and the breakaway holes are the proper size and location.

VII. Check that corrugated steel loader section is installed properly and all loader assembly installation details are adhered to.

VIII. Check that posts are cut off correctly, corner post (No. 1) is chamfered and all tops treated.

IX. Check that guide rail cable is properly attached with clamps to steel beam, as required.

X. Check that all bolts, washers and nuts are placed and affixed securely to all plates, angles, posts and steel rail, as required.

GD 34.5 M Check that Certification of the Installation of Safety Item forms are received from the Design-Builder as per the Contract Documents.

LEVEL OF INSPECTION – E1

110 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 35

TEMPORARY CONCRETE BARRIER INSTALLATION AND RELOCATION

Task # Activity

GD 35.1 M Check that barriers meet physical requirements as specified in the Contract Documents including approved manufacturer.

GD 35.2 Check for any defects in the barrier after installation.

GD 35.3 Check that the AI connector is always inserted in the channel end of adjacent unit.

GD 35.4 M Check that placement, end treatments and offsets are as specified in the Contract Documents.

GD 35.5 During construction, periodically check for any misaligned or damaged barrier. Check that replacement or repair is carried out as required.

GD 35.6 Check that removal or relocation is carried out as specified in the Contract Documents.

GD 35.7 M Check that Certification of Temporary Precast Concrete Barrier Installations forms are received from the Design-Builder as per the Contract Documents.

LEVEL OF INSPECTION – E2

111 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 36

INERTIAL BARRIER MODULE

Task # Activity

GD 36.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 36.2 Check that sand/salt mixture is mixed at the approved rate.

GD 36.3 Check that module is assembled correctly, precisely in the configuration required and at the location as specified in the Contract Documents.

GD 36.4 Check that module is set firmly in a vertical position and filled correctly.

LEVEL OF INSPECTION – E1

112 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 37

CRASH/CUSHION ATTENUATING TERMINAL BARRIER

Task # Activity

GD 37.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 37.2 Check that all preservative treated wood is identified with certification marks authorized by the Canadian Wood Preservers Bureau.

GD 37.3 Check the first two end treatments during installation and record any deficiencies. When deficiencies are identified, inspection frequencies may be increased with the approval of the CSA.

I. Inspect the preservative treated wood to determine if the splits and checks are within specified limits.

II. Check that guide rail is erected at the proper locations.

III. Check that guide posts are the specified length.

IV. Check that steel posts are properly installed with regards to depth, alignment and spacing.

V. Check that loose material in the bottom of the posthole is tamped or removed prior to placing the posts.

GD 37.4 M Complete a detailed inspection of 25% of the end treatments recording any deficiencies.

I. Check that all posts are vertical and that the backfill is properly tamped.

II. Check that channels are installed at proper locations, elevations and are terminated as specified in the Contract Documents.

III. Check that the steel beam mounting height is correct.

IV. Check that spacer channel is installed properly and all connection details for posts 1 through 6 are adhered to.

V. Check that anchor cable is installed at the correct height.

VI. Check that guide rail is properly attached as required.

113 Design-Build Administration Manual January 2014

VII. Check that all bolts, washers and nuts are placed and affixed securely to all plates, angles, posts and steel rail as required.

GD 37.5 M Check that Certification of the Installation of Safety Item forms are received from the Design-Builder as per the Contract Documents.

LEVEL OF INSPECTION – E1

114 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 38

TREND END TREATMENT BARRIER

Task # Activity

GD 38.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 38.2 Check the first two end treatments during installation and record any deficiencies. When deficiencies are identified, inspection frequencies may be increased with the approval of the CSA.

I. Check that granular is placed to required length and width prior to forming concrete pad. II. Check that reinforcing steel is installed as specified in the Contract Documents. III. Check that posts are specified length prior to affixing to concrete pad. IV. Check that plastic sand/salt filled containers are installed correctly. V. Check that anchor block is constructed properly with regards to forming and placement of concrete.

GD 38.3M Complete a detailed inspection of 25% of the end treatments recording any deficiencies.

I. Check that restraining cable is properly attached to post and anchor block. II. Check that the steel beam mounting height is correct. III. Check that all bolts, washers and nuts are placed and affixed securely to all plates, angles, posts and steel rail, as required. IV. Check that in the area 4 metres wide behind the end treatment that the ground is not steeper than 4:1 and is traversable. (Protrusions, rip rap, anchor block, etc. size below 75mm are acceptable).

GD 38.4 M Check that Certification of the Installation of Safety Item forms are received from the Design-Builder as per the Contract Documents.

LEVEL OF INSPECTION – E1

115 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 39

GUIDE RAIL ENERGY ABSORBING TERMINAL BARRIER

Task # Activity

GD 39.1 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 39.2 Check the first two end treatments during installation and record any deficiencies. When deficiencies are identified, inspection frequencies may be increased with the approval of the CSA.

I. Check that the minimum number of bays are constructed to suit design speed.

II. Check that the length of the concrete pad constructed matches the design number of bays.

GD 39.3 M Complete a detailed inspection of 25% of the end treatments recording any deficiencies.

I. Check that the restraining cable is installed when a permanent system has four or more bays or a temporary system has six bays.

II. Check that delineator posts are installed where median hazards exist.

III. Check that reflectorized markers are mounted 45 degrees to centreline of median on both sides of delineator posts.

IV. Check that the thrie beam fender panel height is correct.

V. Check that all bolts, washers and nuts are placed and affixed securely to all plates, angles, posts and steel rail as required.

VI. Check where two way traffic is present that a deflector panel is attached to the system and back of concrete wall or barrier, to shield against wrong-way hits.

GD 39.4 M Check that Certification of the Installation of Safety Item forms are received from the Design-Builder as per the Contract Documents.

LEVEL OF INSPECTION – E1

116 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 40

CONNETICUT IMPACT ATTENUATION SYSTEM BARRIER

Task # Activity

GD 40.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 40.2 Check the first two end treatments during installation and record any deficiencies. When deficiencies are identified, inspection frequencies may be increased with the approval of the CSA.

I. Check that concrete pad and backwall are constructed as specified in the Contract Documents.

II. Check that granular pad constructed is a minimum 150mm in depth and compacted.

III. Check that asphaltic concrete pad constructed as specified in the Contract Documents.

GD 40.3 M Complete a detailed inspection of 25% of the end treatments recording any deficiencies.

I. Check that cylinders A through N are positioned correctly in relation to each other by measuring wall thickness of cylinder.

II. Check that the system is placed along the designed centreline.

III. Check that the are supplied and attached to the cylinders with a chain.

IV. Check that the portable (temporary) backwall is supplied when specified in the Contract Documents.

V. Check that all bolts, washers and nuts are placed and affixed securely to all plates, angles, posts and steel rail, as required.

VI. Check that the back row of cylinders is bolted to the backwall as specified in the Contract Documents.

GD 40.4 M Check that Certification of the Installation of Safety Item forms are received from the Design-Builder as per the Contract Documents.

117 Design-Build Administration Manual January 2014

LEVEL OF INSPECTION – E1

118 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 41

NOISE BARRIER

Task # Activity

GD 41.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

GD 41.2 M Check that grading and berm construction is completed as required in the contract drawings prior to footing construction.

GD 41.3 Check that barrier for tree protection is in place as specified prior to commencement.

GD 41.4 Check that all loose material is removed from the bottom of the postholes or is compacted prior to post installation.

GD 41.5 Check that posts are installed to the proper alignment and depth.

GD 41.6 Check that earth and granular material comply with specification and are compacted to the target density.

GD 41.7 Check that each panel is installed in its proper location in the noise barrier system.

GD 41.8 Check bottom panels to determine that no voids are visible, required minor grading is carried out and installation matches ground profile.

GD 41.9 Check that tree pruning is carried out correctly and kept to a minimum.

GD 41.10 M Check that barrier is constructed within the tolerances of the lines and grades as specified in the Contract Documents.

GD 41.11 Check all galvanized surfaces to determine that any abrasions are cleaned and painted with the required paint.

GD 41.12 Check that all side fences are reconnected in accordance with Contract Documents.

GD 41.13 Check the testing of the mounting bolts when attached to retaining walls to determine that specified torque has been applied.

GD 41.14 Check that all drainage requirements have been implemented.

LEVEL OF INSPECTION – E2

119 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 42

SURCHARGING

Task # Activity

GD 42.1 Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

GD 42.2 M Check that surcharge is built and removed to the requirements shown in the Contract Documents. Check that surcharge is removed only after required settlement is achieved, the specified time has elapsed, or the required pore water pressure has been achieved.

LEVEL OF INSPECTION – E2

120 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 43

HAUL ROADS

Task # Activity

GD 43.1 M Inspect and review haul road prior to construction use with CSA, Design-Builder and local road officials.

GD 43.2 Obtain photographs or videos are taken prior to haul road being used.

GD 43.3 Check that haul road is upgraded, as required, prior to use.

GD 43.4 Check that Design-Builder adheres to load limits on existing structures and/or township roads.

GD 43.5 Periodically inspect haul road and to determine if safe conditions exist.

GD 43.6 In the case of a Design-Builder constructed haul road, check that erosion and sediment control schemes are in place and functioning. Determine if additional erosion control measures, or additional locations may be required.

GD 43.7 Check that Design-Builder maintains haul road throughout the duration of contract, as required.

GD 43.8 M Inspect haul road upon completion of the contract to determine what repairs are required.

GD 43.9 M Check that Design-Builder restores haul road to a safe condition.

LEVEL OF INSPECTION – E1

121 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 44

WICK DRAINS

Task # Activity

GD 44.1 Check qualifications of specialized subDesign-Builder.

GD 44.2 Check that the wick drain satisfies the physical and mechanical properties specified.

GD 44.3 Check that sample of wick drain is submitted prior to construction.

GD 44.4 Check that the wick drain is properly stored and protected from sunlight, dirt, dust, mud, debris and any other detrimental substances.

GD 44.5 Check the appropriate equipment is used to install the wick drains.

GD 44.6 Check if pre-augering is required.

GD 44.7 M Check that material supplied by the Design-Builder is sampled as required and forwarded for testing.

GD 44.8 Check that the installation procedure submission requirement is satisfied.

GD 44.9 Check that trial drains are installed.

GD 44.10 Check layout of drains.

GD 44.11 Check plumbness of drains

GD 44.12 Check cut-off of drains

GD 44.13 Check method for drain installation when obstructions are encountered.

GD 44.14 Check Tip Elevations

GD 44.15 Check for artesian flows

LEVEL OF INSPECTION – C2

122 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 45

TREE AND SHRUB PLANTING

Task # Activity

GD 45.1 M Check prior to delivery that the specified plantings are per design requirements including that species are suitable for the zone specified on applicable landscape planting plan.

GD 45.2 Check the location of all landscape plantings before planting.

GD 45.3 Check that all planting occur within the specified operational time constraints.

GD 45.4 Check that planting operation has met all applicable Contract Document requirements.

GD 45.5 M After planting check and verify all sizes, materials and locations are supplied according to the specifications.

GD 45.6 W Check that the end results meets the provisions of the maintenance and warranty requirements including winter protection of conifers. Follow the inspection interval specified in the NSSP.

LEVEL OF INSPECTION – E2

123 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 46

GROUND MOUNTED SIGN PLACEMENT

Task # Activity

GD 46.1 Record location of those signs, which are not identified in the Contract Documents as requiring replacement, relocation or removal (i.e. existing signs which should be in original location at the end of the contract). Record sign’s condition and take a picture.

GD 46.2 Verify that Design-Builder is properly storing signs, which have been removed for construction activities, to be reinstalled at the end of the contract. (Signs should be removed from posts and stored neatly)

GD 46.3 M Within 2 weeks of sign pickup by Design-Builder, verify that all signs have been received and that their sizes and messages are correct. Report sign errors to CCO, as soon as possible, to facilitate their timely replacement.

GD 46.4 Verify that new signs are being stored in a proper manner (i.e. off the ground and protected from the elements).

GD 46.5 Check that each sign installation is at its designated location and lateral offset, and placed to the proper depth. Record the reason for field adjustment ( Utilities, public complaint, conflict with another sign or object).

GD 46.6 Verify that metal posts are galvanized and that wood posts are pressure- treated as per relevant OPSS’s.

GD 46.7 Check that the sign support is correct size and type. Check that posts are plumb and oriented to approaching traffic. Check that steel posts are not bent and that wood posts are not cracked, twisted or warped significantly.

GD 46.8 Check that correct sign message is mounted on the support. Verify sequence of sign boards on support with contract drawings. Verify that sign is mounted level and to the height listed in the Sign Work Tables. Check that sign has not been damaged during installation.

GD 46.9 Verify that all sign and support removals have been completed. Check that all materials (signs and posts) have been removed from site.

GD 46.10 Check that sign is not obstructed by another sign or object. This is especially important for signs such as Stop, Stop Ahead and Checkerboards

124 Design-Build Administration Manual January 2014

GD 46.11 Check that new sign installation in the vicinity of an intersection does not restrict the view of approaching highway traffic from the intersecting road.

GD 46.12 M Check that constructed unit is as per design requirements.

GD 46.13 Check that applicable submissions are received by Design-Builder.

LEVEL OF INSPECTION – E2

125 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 47

COMMERCIAL VEHICLE INSPECTION FACILITY

Task # Activity

GD 47.1 M Check that the Design-Builder has obtained required permits prior to proceeding with associated work.

GD 47.2 Maintain a separate Inspector’s diary to clearly document the progress of all work at the facility including, but not limited to, the following operations; demolition, excavation, foundation, septic systems, structural steel, building construction, HVAC, electrical, plumbing, site services, weigh scales, finishes and related site works.

GD 47.3 M Check the construction conforms to the Contract Documents, Ontario Building Code, municipal bylaws and associated regulations.

GD 47.4 M Check that delivered material is in compliance with the Contract Documents.

GD 47.5 M Check that inspections required of the local building authority are carried out and documented prior to proceeding with subsequent work.

GD 47.6 Perform joint inspections of the work with the Design-Builder, building inspectors and Ministry staff.

GD 47.7 Receive shop drawings, proposals and other Design-Builder submissions providing applicable recommendations .

GD 47.8 M Prepare deficiency lists and check that all defects in the work are corrected.

GD 47.9Provide required sampling and testing as per Contract Documents

LEVEL OF INSPECTION – C1/D2

126 Design-Build Administration Manual January 2014

GRADING AND DRAINAGE – TASK GD 48

COMPACTION CONTROL STRIP

Task # Activity

GD 48.1 Check that a new control strip is established at the time of initial use of each source, when there is a perceptive change in the appearance and/or gradation of materials, at least once per calendar year on all carry-over contracts, after each 10 QC lots of material have been completed for earth and after each 25 QC lots of material have been completed for granulars (base, subbase and select subgrade applications only).

GD 48.2 Check that a suitable location has been selected for the control strip.

GD 48.3 Check that all required laboratory test results have been received prior to construction of the control strip.

GD 48.4 Check that the type of compaction equipment to be used is suited to the material to be compacted, the degree of compaction required and space available.

GD 48.5 Check that the target density of the control strip is determined at a field moisture content within the allowable tolerances.

LEVEL OF INSPECTION – A2

127 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 1

CONCRETE MATERIAL, PRODUCTION AND TESTING

Task # Activity

CS 1.1 Obtain Form A portion of the concrete mix design along with the supporting documentation at least 14 Days prior to placement of concrete and review it to determine if it meets the Contract Document requirements. Check that the concrete plant supplier is certified. Check that all materials are from approved lists and meet the requirements of the Contract Documents. Issue written confirmation that the concrete mix design submission meets the Contract Document requirements or advise the Design-Builder of any requirements that have not been met.

CS 1.2 Check that the required quality assurance samples of water, admixtures, and cementing materials are taken and delivered to the appropriate laboratories.

CS 1.3 Identify which method of acceptance will be used for compressive strength. For acceptance method A, determine lot and sublot sizes and generate random numbers

CS 1.4 Check that the technician performing the testing of plastic concrete is certified by A.C.I. or C.S.A.

CS 1.5 M Check concrete delivery tickets are checked for correct class of concrete, mix design number and batching time, and record the discharge time, and other information required by the Contract Documents. Check that the Design-Builder records the amount of any material added after batching, rejection of a load or part thereof, time truck arrived on site and the time when the truck finished discharging.

CS 1.6 Check that plastic concrete is sampled and tested according to the Contract Documents. Identify to the Design-Builder concrete loads from which performance cylinders, or other cylinders for information purposes, are to be cast as the loads arrive on site.

CS 1.7 Check that test cylinders are handled, cured and transported as per C.S.A. and/or Contract Documents.

CS 1.8 Check that appropriate curing regime is used for curing of concrete.

CS 1.9 Check that the required quality assurance samples of curing compound, as applicable, are taken and delivered to the testing laboratory.

CS 1.10 Obtain submission for “Plastic Concrete Test Results” after each day’s work. The submission shall include copies of delivery tickets for each load of

128 Design-Build Administration Manual January 2014

concrete and a summary of testing, adjustments, rejections, as specified in the Contract Documents.

CS 1.11 Obtain submissions for “Cylinder Curing Records” at the completion of the field curing period.

CS 1.12 Determine the quantity of concrete in lots using the dimensions in the Contract Documents, for the purpose of calculating payment adjustment for air void system and rapid chloride permeability.

CS 1.13 Identify random locations for coring specimens for AVS and RCP.

CS 1.14 Forward compressive strength, AVS and RCP test results and add payment adjustment information to the Design-Builder as the results become available. For compressive strength forward analysis of results at a minimum of monthly intervals.

CS 1.15 Check appropriateness of material selected to fill in core holes.

CS 1.16 Obtain the Design-Builder’s written intent to invoke compressive strength, AVS or RCP referee testing within 5 Business Days of the Design-Builder receiving the test results for the sublot or lot, as applicable.

LEVEL OF INSPECTION – A1

129 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 2

CONCRETE STRUCTURES

Use this task in conjunction with CS 1

Task # Activity

CS 2.1 Obtain submission for “Bridge Deck Placement Plan”, when applicable, a minimum of one week prior to the commencement of placing concrete in bridge decks.

CS 2.2 Obtain submission for “Temperature Control Plans” for concrete subject to cold weather, high performance concrete, bridge decks and large concrete components where the smallest dimension is 1.5 m and verify that they meet the Contract Document requirements for control of temperature and temperature difference.

CS 2.3 Check that the “Notification of Placement of Structural Concrete” form letter is issued, prior to each placing operation and that the form is signed by the Design-Builder.

CS 2.4 Check that the data logger temperature records and records of any action taken to maintain control of temperature and temperature difference are submitted at the end of each working day during the temperature monitoring period.

CS 2.6 Obtain information related to curing compound application specified in the Contract Documents, at least one week prior to the application.

CS 2.7 Review details of “pre-placement” meeting regularly for compliance.

CS 2.8 Check that deck finishing equipment is as specified in the Contract Documents.

CS 2.9 Check that deck finisher dry run is conducted.

CS 2.10 Check transferring systems (concrete pumps, belts, runways, etc.).

CS 2.11 Check that curing materials and, in cold weather, all protection materials have been delivered to the site before any concrete is placed.

CS 2.12 Check that the thermocouples for temperature and temperature difference control are installed as per the Design-Builder’s plan.

CS 2.13 Check that the concrete and concrete testing is in accordance with CS 1.

130 Design-Build Administration Manual January 2014

CS 2.14 Check that placement operations are as specified in the Contract Documents.

CS 2.15 Check that vibratory equipment is in good operating condition and meets specification requirements.

CS 2.16 Check for adequate consolidation and proper use of vibrators.

CS 2.17 Check that finishing of plastic concrete is as specified in the Contract Documents.

CS 2.18 Check that finished concrete is within tolerances specified in the Contract Documents.

CS 2.19 Check that specified curing is carried out. For HPC check structure decks, approach slabs, curbs and sidewalks, to check that fog mist is applied continuously from the time concrete is deposited in the deck until it is covered with burlap. Check that burlap is prevented from freezing during cold weather.

CS 2.20 Check that temperature control requirements for cold weather, bridge deck and large concrete components are carried out as specified in the Contract Documents, where applicable.

CS 2.21 Take random readings of thermocouples installed in bridge deck and substructure and compare to the datalogger temperature records submitted by the Design-Builder, to verify thermocouple function and readings.

CS 2.22 M Carry out the covermeter survey on the top surface of decks (including medians and sidewalks) and front face of concrete barrier/parapet walls. Results are to be submitted to the Quality Assurance Section electronically within 4 Business Days of completing the survey.

CS 2.23 Check that cracks are identified, documented and a proposal for remedial action submitted for review and acceptance.

CS 2.25 Give or deny permission to waterproof following completion of a bridge deck repair based on verification that the repair has been completed satisfactorily and the deck has dried for three (3) Days.

CS 2.26 Accept components with formed and unformed surfaces based on verification that the cracks in the completed work were treated as required by the specification.

131 Design-Build Administration Manual January 2014

LEVEL OF INSPECTION – A1 – B1 / E2 during curing operation and after the initial set

132 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 3

TREMIE CONCRETE Use this task in conjunction with CS 1 and CS 2

Task # Activity

CS 3.1 Check that erosion and sediment control schemes are in place and functioning prior to placement of Tremie concrete.

CS 3.2 Check that unwatering is not carried out prior to when it is specified in the Contract Documents.

CS 3.3 M Check that unwatering is not causing erosion of soil at the outlet and other environmental concerns (i.e. muddy water discharge). Check that the Design-Builder has the standby equipment (pumps, hoses, filter bags, etc.) on site as required in the environmental submission. Check that the Design-Builder has obtained a Permit to Take Water in accordance with Special Provision 100S59 before unwatering is carried out.

CS 3.4 Check that placement operations are as specified.

CS 3.5 Check that concrete material, production and testing is in accordance with CS 1 and that placement, consolidation, finishing and curing operations are in accordance with CS2.

CS 3.6 Check elevation at which the placement is terminated.

CS 3.7 M Check proper removals, cleaning and soundness of top surface prior to placing additional concrete.

CS 3.8 Check that the formed enclosure meets water tightness specified in the Design-Builder’s submission, when placement is required next to a watercourse.

LEVEL OF INSPECTION – A1

133 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 4

CURB AND GUTTER Use this task in conjunction with CS 1

Task # Activity

CS 4.1 Check that proper type of curb is constructed as per the Contract Documents.

CS 4.2 Check for proper alignment, grade and proper granular base preparation.

CS 4.3 Check for proper positioning of joints.

CS 4.4 Check for proper positioning of manhole frames and grates.

CS 4.5 Check that concrete material, production and testing are in accordance with CS 1.

CS 4.6 Check that placement, consolidation, finishing and curing operations are as specified in the Contract Documents..

CS 4.7 Check for proper drop curb at entrances and at Traffic Signal locations.

LEVEL OF INSPECTION – E2 – A-1 During concrete placement

134 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 5

CONCRETE SIDEWALK Use this task in conjunction with CS 1

Task # Activity

CS 5.1 Check for proper alignment, grade, granular base preparation and extra thickness at entrances.

CS 5.2 Check for proper positioning of construction joints and expansion joints.

CS 5.3 Check that concrete material, production and testing are in accordance with CS 1.

CS 5.3 Check that placement, consolidation finishing and curing operations are as specified in the Contract Documents.

CS 5.4 Check that a chase is installed on structures where a chase is specified in the Contract Documents.

LEVEL OF INSPECTION – E2 – A-1 During concrete placement

135 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 6

CONCRETE BARRIER WALLS Use this task in conjunction with CS 1and CS2

Task # Activity

CS 6.1 Check that the method of construction is as specified in the Contract Documents

CS 6.2 Conventional Wooden or Steel Form Method (i) Check for correct alignment, grade and granular base preparation. (ii) Check for correct joint detail and spacing. (iii) Check that the inside face of formwork is clean and in good order, to produce a smooth cast face. (iv) Check that the barrier wall forms are adequately restrained to prevent uplift. (v) Check that railing mounts / anchorages are correctly installed (Location, elevation, flushness, and anchor bolt protrusion is adequate for rails) (vi) Check that concrete material, production and testing is in accordance with CS 1. (vii) Check that concrete placement, consolidation and finishing operations are as specified in CS2. (viii) Check that specified curing requirements are carried out. (ix) Check for surface tolerances and cracking.

CS 6.3 Extruded Method (Not allowed on bridge decks) (i) Check for correct alignment, grade and granular base preparation. (ii) Check that specified percentage of air is being maintained. (iii) Check that construction joints, isolation joints and contraction joints are constructed as per the Contract Documents. (iv) Check that specified curing requirements are met. (v) Check for surface tolerances and cracking. (vii) Check that the E.R.S. requirements have been met where applicable.

CS 6.4 Pre-Cast (Not allowed on bridge decks) (i) Check that the foundation is prepared for acceptance of pre-cast units. (ii) Check that pre-cast units are as specified and are supplied from the approved list. (iii) Check for correct installation of interlocking devices and check that no damaged units are installed. (iv) Check for correct alignment and grade.

LEVEL OF INSPECTION – B1/D2

136 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 7

CONCRETE BASE AND PAVEMENT Use this task in conjunction with CS 1

Task # Activity

CS 7.1 Obtain a plan detailing curing and protection when concrete is placed in cold weather conditions. Check that the plan includes the method by which in-place minimum concrete temperatures are maintained.

CS 7.2 Obtain Form A portion of the concrete mix design along with the supporting documentation at least 14 Days prior to placement of concrete and review it to determine if it meets the Contract Document requirements. Check to that the Regional Quality Assurance Section has received Form B of the concrete mix design from the concrete supplier prior to placement of concrete.

CS 7.3 Check that all the delivered material is supplied from the approved list and is properly stored, sampled and tested.

CS 7.4 Issue written confirmation that the concrete mix design submission meets the Contract Document requirements or advise the Design-Builder of any requirements that have not been met.

CS 7.5 Check that the tie bars and dowel bars are the proper length and diameter. Check that the tie bars and dowel bars are properly stored on- site and the amount of damage to the epoxy coated. Reject any bars not meeting the Contract Document requirements.

CS 7.6 Check for proper alignment, grade and base preparation.

CS 7.7 Check that the dowel bars are entirely coated with bond breaker prior to installing them.

CS 7.8 Check that the dowel bars and tie bars are placed and remain in the specified location. Check that load transfer devices are placed on the proper skew and staked in place. Check that the spacer wires are cut on the load transfer devices prior to placing concrete. Check that the location of the dowel bars are visibly marked on the side of the concrete for joint cutting.

CS 7.9 Check the temperature of the existing surface to receive the concrete, to determine that it is not above 35ºC or below 5ºC. Check the air temperature to determine that it is not below 0ºC or above 32ºC prior to or during the concrete placing operation.

137 Design-Build Administration Manual January 2014

CS 7.10 Load transfer devices should be checked following paving operations to determine that they have not been moved.

CS 7.11 Check that concrete placement, consolidation, finishing and curing operations are in accordance with the Contract Documents.

CS 7.12 Check that the specified trial run of the paving equipment is made when specified. After the first day’s production, check cut-out to determine that the position and alignment of the dowel bars is according to the Contract Document requirements. Check that repair is according to the Contract Documents.

CS 7.13 When fixed form pavers are used, check that hand held vibrators are used properly to supplement consolidation.

CS 7.14 Check that specified finishing and texturing procedures are adhered to. Check the width, centres and depth of grooves to determine that they meet the Contract Document requirements.

CS 7.15 Check that timing of form removal is as specified and any honeycombed areas are properly repaired.

CS 7.16 Check that the joints are the correct type and are cut at the proper location.

CS 7.17 Check that the initial sawcut is made to the depth specified in the Contract Documents. Check that this initial sawcut is done within the constraints specified in the Contract Documents, without damaging the concrete surface.

CS 7.18 Inspect hardened concrete surface for cracks outside of the joints and to determine that it is within surface tolerance.

CS 7.19 M Check that traffic is not permitted on the concrete pavement/base until the concrete has attained a compressive strength of 20 MPa.

CS 7.20 Check that Quality Assurance cores are obtained and delivered to the designated laboratory.

CS 7.21 Calculate the Percent Within Limits for the criteria of strength and thickness.

CS 7.22 Check that the profile measuring device (PMD) meets the Contract Document requirements and that it has been correlated with the Owner’s PMD.

138 Design-Build Administration Manual January 2014

CS 7.23 Check that the measuring of the concrete surface for roughness is carried out as per the Contract Documents in the presence of the CA.

CS 7.24 M Check profile traces and check that scallops are ground prior to sealing joints, where specified.

CS 7.25 Calculate the Percent Within Limits for the criteria of surface roughness.

CS 7.26 Check that the Work has an effluent containment system in place.

CS 7.27 Check that reservoir cuts are made to specified widths and depths.

CS 7.28 Check that the reservoir cuts are immediately flushed with water to remove slurry as per the Contract Document requirements.

CS 7.29 Check that all the joint faces are abrasive blast cleaned according to the Contract Documents immediately prior to joint sealing and are blown clean and dry.

CS 7.30 Check that reservoir cuts are sealed according to the Contract Document requirements.

LEVEL OF INSPECTION – A1 / A2

139 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 8

CONCRETE BASE AND PAVEMENT – FULL DEPTH REPAIR

Task # Activity

CS 8.1 Obtain Form A portion of the concrete mix design along with the supporting documentation at least 14 Days prior to placement of concrete and review it to determine that it meets the Contract Document requirements. Check that the Regional Quality Assurance Section has received Form B of the concrete mix design from the concrete supplier prior to placement of concrete.

CS 8.2 Issue written confirmation that the concrete mix design submission meets the Contract Document requirements or advise the Design-Builder of any requirements that have not been met.

CS 8.3 M Obtain documentation certifying that the superplasticizer meets the special provision requirements.

CS 8.4 M Obtain the Design-Builder’s linear shrinkage test results within 40 Days of the mix design submission and forward a copy to the Quality Assurance Section and a copy to the Concrete Section.

CS 8.5 M Check that all supporting test data is not more than 12 months old from the date the concrete mix design was submitted.

CS 8.6 M Obtain the Design-Builders details of the method of concrete removal at least two weeks prior to start of any work and check that it is according to the special provision.

CS 8.7 Obtain and review submissions for Cold and Hot Weather Concrete.

CS 8.8 Check that removal limits shown in the contract drawings are appropriate to existing field conditions.

CS 8.9 Check that the saw cuts are full depth.

CS 8.10 Check Design-Builder is using proper equipment to remove the concrete slabs.

CS 8.11 Check that the concrete removal operation does not damage the subbase or adjacent concrete surfaces. If the subbase is disturbed, check that disturbed material is removed.

140 Design-Build Administration Manual January 2014

CS 8.12 Check that the dowels, tie bars and load transfer devices are placed as specified in the Contract Documents.

CS 8.13 Check that gang drills are used to drill holes for dowel bars.

CS 8.14 Check that all dowel bars are completely encased by epoxy for the full depth of the hole and that a grout retention disk is attached.

CS 8.15 Check preparation work, concrete placement, consolidation, finishing and curing procedures are according to the Contract Documents.

CS 8.16 Check that the technician performing the testing of plastic concrete is certified by A.C.I. or C.S.A.

CS 8.17 Check concrete delivery tickets for correct class of concrete, mix design number and batching time.

CS 8.18 Check that the concrete is sampled and tested in accordance with the special provision.

CS 8.19 Check the completed work for any of the defects listed in the special provision. Check that surface of the concrete meets the surface tolerances stated in the special provision.

CS 8.20 Calculate the Percent Within Limit for the 28-Day compressive strength.

CS 8.21 Check that the Work has an effluent containment system in place.

CS 8.22 Submit all supporting documentation to the Quality Assurance within 4 Business Days of receiving results.

LEVEL OF INSPECTION – A2 until Design-Builder demonstrates satisfactory performance of operation then reducing to E2.

141 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 9

CONCRETE BASE AND PAVEMENT – FULL DEPTH REPAIR (FAST TRACK) Use this task in conjunction with CS 8

Task # Activity

CS 9.1 Obtain fast track repair submission at the time of the mix design submission and verify that it meets the requirements of the special provision for both the Autogenous Method and the Maturity Method.

CS 9.2 Review and approve or reject Design-Builder’s proposed location for the trial area, if location is not designated in the Contract Documents.

CS 9.3 Check the Design-Builder’s ability to adequately complete the trial repair area within the time frame of the closure as defined in the Contract Documents.

CS 9.4 Check repair trial area for deficiencies such as poor finish and cracks.

CS 9.5 Check that the Design-Builder has verified the calibration charts.

CS 9.6 M Give or deny permission to proceed with repairs to the Work.

CS 9.7 Check that mid-lane longitudinal joints are as per the special provision.

CS 9.8 Check that autogenous cylinders are made and tested according to the special provision.

CS 9.9 Check that the Design-Builder has installed 2 thermocouple wires for early strength determination in the final full depth repair area for each closure according to the special provision.

LEVEL OF INSPECTION – A1

142 Design-Build Administration Manual January 2014

CONCRETE & STRUCTURES - TASK CS 10

CONCRETE BASE AND PAVEMENT – PARTIAL DEPTH REPAIR

Task # Activity

CS 10.1 Obtain Form A portion of the concrete mix design along with the supporting documentation at least 14 Days prior to placement of concrete and review it to determine that it meets the Contract Document requirements. Check that the Regional Quality Assurance Section has received Form B of the concrete mix design from the concrete supplier prior to placement of concrete.

CS 10.2 Issue written confirmation that the concrete mix design submission meets the Contract Document requirements or advise the Design-Builder of any requirements that have not been met.

CS 10.3 M Obtain documentation certifying that the superplasticizer meets the special provision.

CS 10.4 Obtain the Design-Builder’s linear shrinkage test results within 40 Days of the time the mix design submission and forward a copy to the Quality Assurance Section and a copy to the Concrete Section.

CS 10.5 Check that all supporting test data is not more than 12 months old from the date the concrete mix design was submitted.

CS 10.6 Obtain the Design-Builders details of the method of concrete removal at least two weeks prior to start of any work and check that it is according to the special provision.

CS 10.7 If the Design-Builder submits a proposal to use a proprietary product instead of concrete, check if material is on the Ministry’s approval list and that the dimension of the repair area(s) are less than 300 mm.

CS 10.8 Delineate the limits of the areas to be repaired.

CS 10.9 Check that the perimeter of the repair area is sawcut vertically to a depth of 25 mm.

CS 10.10 Check that concrete removals are carried out using a chipping hammer to a minimum depth of 50 mm and up to a maximum depth of one-third the thickness of the existing concrete slab.

143 Design-Build Administration Manual January 2014

CS 10.11 Check that preparation work, prior to placing concrete is carried out according to the Contract Documents. (ie. Abrasive blast cleaning, pre- wetting and application of bonding agent)

CS 10.12 Check that joints are formed in the repair area, where the repair includes an existing pavement joint or working crack. Check joints are formed according to the Contract Documents.

CS 10.13 Check concrete placement, consolidation, finishing and curing procedures are according to the Contract Documents.

CS 10.14 Check the work for any of the defects listed in the special provision.

CS 10.15 Calculate the Percent Within Limit for the 28-Day compressive strength.

CS 10.16 Submit all supporting documentation to the Quality Assurance Section within 4 Business Days of receiving results.

LEVEL OF INSPECTION – A1

144 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 11

STRUCTURE REHABILITATION – REMOVAL OF WATERPROOFING SYSTEM FROM DECK SURFACE (For deck to be subsequently rehabilitated by patch / waterproofing and paving)

Task # Activity

CS 11.1 M Check that all old waterproofing membrane is completely removed from the concrete surface without any damage to the existing surface of the deck. Identify any damage to the deck surface due to removal operation of waterproofing and all repairs and remedial work that needs to be carried out prior to waterproofing.

CS 11.2 Check that all repairs and remedial work to the concrete deck have been completed.

CS 11.3 Check that dust and debris from exposed work, and from construction operations such as concrete cutting / grinding, abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Significant Area.

LEVEL OF INSPECTION – D2

145 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 12

STRUCTURE REHABILITATION – CONCRETE REMOVALS

Task # Activity

CS 12.1 Obtain from the Design-Builder an identification of equipment and manufacturer’s published specification for concrete removals.

CS 12.2 Obtain Working Drawings for “Concrete Removal – Structural Component” and “Concrete Removal – Complete Deck” at least one week prior to the commencement of the concrete removals and verify that it meets the Contract Document requirements and that it has been sealed and signed by the Design Engineer and Design Check Engineer.

CS 12.3 M Obtain a Certificate of Conformance upon completion of the designated concrete removal for each structural component and / or the complete deck as per requirements of the Contract Documents.

CS 12.4 Obtain notification from the Design-Builder 24 hours prior to the commencement of the scarifying operation.

CS 12.5 Upon receipt of written notification from the Design-Builder to carry out all applicable concrete survey(s), check that all work requirements identified in the Contract Documents have been completed by the Design-Builder prior to commencing concrete surveys.

CS 12.6 Notify the Quality Assurance Section and the Regional Structural Section as soon as the Design-Builder submits notification to commence with the concrete surveys.

CS 12.7 Carry out a covermeter survey (if applicable) for all asphalt covered decks after the first pass of the scarifying equipment where concrete removals from the top surface of the deck are specified. Grid points shall be the same as the ones on the corrosion potential survey, where specified. Plot readings on a separate drawing other than the concrete removal survey drawing.

CS 12.8 Carry out, as per the Contract Document requirement, the following concrete removal surveys as part of determining and demarcating the actual location and extent of removals: • Visual and Delamination Survey– Identify areas of scaling, honeycombing and delaminated concrete. • Corrosion Potential Survey (Half-Cell) (if applicable) – where concrete is to be removed based on corrosion potential criteria when specified in

146 Design-Build Administration Manual January 2014

the Contract Documents. Grid points shall be the same as the ones for the original bridge deck condition survey.

CS 12.9 Carry out concrete removal survey(s) for the soffit when Type B or localized full depth removals in the deck are specified in the Contract Documents.

CS 12.10 Determine full depth localized removal areas in the deck by performing the following: • Complete the concrete removal surveys on both the top surface of the deck and the soffit. • Superimpose both the concrete removal surveys on the original bridge deck condition survey.

CS 12.11 Determining areas of removal on structures where the existing concrete overlay will not be completely removed by performing the following: • Complete the concrete removal survey(s) on the top surface of the overlay. • Complete a second delamination survey on the top surface of the original deck within the removal area, after the concrete has been removed. • Demarcate removal areas where the concrete is delaminated in the second survey.

CS 12.12 Superimpose all concrete removal surveys on original bridge deck condition surveys. Clearly identify all delaminations and actively corroding areas in different colours.

CS 12.13 M Immediately after completion of surveys, deliver coloured copies of the covermeter survey and the concrete removal survey(s), along with revised estimated quantities, to the Regional Structural Section for review and approval.

CS 12.14 M After permission to remove concrete and/or further direction has been received from the Regional Structural Section; the CA shall square off and clearly identify all removal areas with spray paint.

CS 12.15 M Provide the Design-Builder with written permission to proceed with the concrete removals.

CS 12.16 Demarcate all areas of exposed reinforcing steel prior to scarifying operation. For scarifying greater than 10 mm, demarcate areas of low cover.

CS 12.17 Check weight of equipment does not exceed the limit specified.

147 Design-Build Administration Manual January 2014

CS 12.18 Check portion of the structure to be scarified and depth of scarifying are according to the Contract Documents.

CS 12.19 Check portion of curb face, barrier wall or parapet wall which will be covered by an overlay is roughened according to the Contract Documents.

CS 12.20 Check that concrete removal is being done correctly and as specified in the Contract Documents. (ie. Hammer size and strokes, size and weight of equipment, location and depth of removals, staging of removal and strength of adjacent new concrete)

CS 12.21 M After concrete removals are completed, check within the demarcated areas and along the perimeter for soundness of concrete and delamination to determine if additional removals are required.

CS 12.22 Notify the Quality Assurance Section and Regional Structural Section if the concrete is delaminated beyond 25 mm of the 1st layer of reinforcing steel; or if the Design-Builder has removed concrete more than the specified depth.

CS 12.23 Check existing reinforcing steel, post-tensioned cables, adjacent concrete, hardware and components to remain in place are not damaged during concrete removal. Check that existing concrete to remain in place has not been contaminated.

CS 12.24 Check reinforcing steel to remain in place for bar loss and heavy rust. Notify the Regional Structural Section if bar loss is greater than 20 % or heavy rust exists in any location.

CS 12.25 Check that the Design-Builder does not damage the top flange of steel girders. If damage does take place, all relevant details, including size and location of the damage shall be documented and reported to the Regional Structural Section within 48 hours.

CS 12.26 For full depth removal with full depth sawcut construction joint, check that the sawcut surfaces are roughened.

148 Design-Build Administration Manual January 2014

CS 12.28 Check that dust and debris from exposed work, and from construction operations such as concrete cutting / grinding, abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Significant Area.

CS 12.29 Check that environmental protection enclosures or containment systems are in place and functioning.

LEVEL OF INSPECTION – B1

149 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 13

STRUCTURE REHABILITATION - SURFACE PREPARATION

Task # ACTIVITY

CS 13.1 Check surface of deck to determine whether extra work is required (i.e. to correct scaling).

CS 13.2 M Check that surface preparation is as specified in the Contract Documents.

CS 13.3 Check that dust and debris from exposed work, and from construction operations such as concrete cutting / grinding, abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Significant Area.

LEVEL OF INSPECTION - D2

150 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 14

STRUCTURE REHABILITATION – NORMAL CONCRETE OVERLAY Use this task in conjunction with CS 1 and CS 2

Task # Activity

CS 14.1 Check that concrete material, production and testing is in accordance with CS1.

CS 14.2 Obtain documentation certifying that the superplasticizer meets the requirements of the special provision.

CS 14.3 Obtain the Design-Builder’s linear shrinkage test results within 40 Days of the mix design submission and forward to the Quality Assurance Section within 4 Business Days of receiving results.

CS 14.4 Check that all supporting test data is not more than 12 months old from the date the concrete mix design was submitted.

CS 14.5 Check that the screed rails have been installed outside the area to be waterproofed.

CS 14.6 M Check that the Design-Builder’s trial run has been completed before each placing operation and determine that the minimum thickness of the overlay can be achieved.

CS 14.7 M Check that the Design-Builder has verified that the screed rails and finishing machine have been set to allow the thickness of the overlay to meet the requirements of the Contract Documents before proceeding with the placement of the overlay.

CS 14.8 M Check that all full depth patches have been repaired prior to placing the overlay, unless otherwise specified in the Contract Documents.

CS 14.9 M Check that concrete for all partial depth removal areas in the deck are placed at the same time as the overlay.

CS 14.10 Check that overlay is not placed adjacent to any new concrete less than 48 hours old. If the ambient air temperature falls below 10° C within the first 48 hours after placement of concrete, the 48hour time requirement is extended to 96 hours.

CS 14.11 Check the temperature of the air and existing concrete surface to receive the overlay, to determine that it meets Contract Document requirements prior to and during concrete operations

151 Design-Build Administration Manual January 2014

CS 14.12 If the air temperature drops below 5ºC during curing, check that cold weather protection is provided according to the specifications.

CS 14.13 Check equipment and runways for the concrete transporting equipment to check that they are not supported by reinforcing steel.

CS 14.14 Check that only the finishing machine and buggies used to place concrete are allowed on the abrasive blast cleaned portions of the deck. No other vehicles or equipment, including concrete ready mix trucks shall be permitted.

CS 14.15 Check that heavy vehicles such as concrete ready mix trucks or dump trucks are not permitted on the deck where concrete removal has taken place.

CS 14.16 Check that concrete surface and reinforcing steel have been abrasive blast cleaned according to CS 43.

CS 14.17 Check that removal of all dust and loose material is carried out by oil-free compressed air.

CS 14.18 Check that the prepared surface is maintained in a wet condition for six hours prior to placing concrete.

CS 14.19 Check that excess water is removed by oil-free compressed air immediately prior to application of bonding agent.

CS 14.20 Check that areas of reinforcing steel and prepared concrete surface are protected from oil leaks and dropping grout or concrete from placing equipment.

CS 14.21 Check that all vertical and horizontal surfaces against which the overlay will be placed receive a thorough, even coating of bonding grout, with no excess left in place.

CS 14.22 Check that the application of grout is such that the brushed material does not become dry before it is covered with overlay concrete. Check that bonding grout, which is not used within 30 minutes after mixing, is discarded.

CS 14.23 Check that concrete placement, consolidation, finishing and curing procedures are in accordance with CS 2unless specified otherwise in the Contract Documents.

152 Design-Build Administration Manual January 2014

CS 14.24 Check that the overlay is cured with burlap and water regardless of ambient temperature. Check that the burlap is maintained in a continuously wet condition throughout the curing period by means of a soaker hose. The soaker hoses shall be placed on the burlap prior to placing the moisture barrier.

CS 14.25 Check that the burlap is prevented from freezing during cold weather.

CS 14.26 Obtain temperature-monitoring data to check that the concrete temperature does not fall below 10ºC within 7 Days following concrete placement.

CS 14.27 Check that the construction joints are placed as specified in the Contract Documents.

CS 14.28 Define the lots and determine core locations for air void system and tensile bond strength test.

CS 14.29 Check that the tensile bond strength cores and air void system cores are carried out as per the Contract Document requirements. Check that the core holes have been filled according to the Contract Document requirements.

CS 14.30 Obtain and review tensile bond strength results within 4 Business Days of testing and forward the results to the Quality Assurance Section.

CS 14.31 Check the overlay for any areas of debonding, honeycombed areas or cracks.

CS 14.32 Obtain and verify Design-Builder’s crack inspection report and review Design-Builder’s crack treatment proposal if applicable.

CS 14.33 Check that permission to waterproof is not issued until cracks are treated (if applicable) and the deck is air dried for three Days.

LEVEL OF INSPECTION – A1

153 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 15

STRUCTURE REHABILITATION – CATHODICPROTECTION - ANODE MESH SYSTEMAND CONCRETE OVERLAY Use this task in conjunction with CS 1 and CS 14

Task # Activity

CS 15.1 M Check that all delivered material, equipment and cabinets are supplied from the approved list in the Contract Documents.

CS 15.2 Review all required submissions for conformance with Contract Documents.

CS 15.3 Check that one copy of all required submissions is forwarded to Bridge Office.

CS 15.4 Check that all patch repair has been completed in accordance with Contract Documents before any wiring, reference cells and anode mesh is placed.

CS 15.5 Check that the top surface of all patched areas has been scarified or roughened in accordance with Contract Documents before anode mesh is placed.

CS 15.6 Check that all saw cuts for wiring and reference cells installation are within the specified tolerance for depth, width and locations, and are properly filled with specified material afterwards without any voids.

CS 15.7 Check placement and anchoring of anode mesh, welding of distribution bars, and verify tests for short circuits between anode mesh, rebars and other metallic appurtenances.

CS 15.8 Check that concrete material, production and testing is in accordance with CS1.

CS 15.9 Check that all electrical equipment, including CP cabinets, junction , etc. is properly located as specified in the Contract Documents.

CS 15.10 M Check that the acceptance testing is performed in accordance with the Contract Documents; review the acceptance testing report.

LEVEL OF INSPECTION – C2

154 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 16

STRUCTURE REHABILITATION – SILICA FUMECONCRETE OVERLAY Use this task in conjunction with CS 1, CS 2 and CS 14

Task # Activity

CS 16.1 Verify that the concrete mix and materials meet the requirements of the Special Provision for rapid chloride permeability at 28 Days.

CS 16.2 Check that the trial run procedures are in accordance with CS14 and thatthe Design-Builder has demonstrated their ability to fog mist using the same equipment to be used for the overlay.

CS 16.3 Check that fog mist is applied continuously from the time of screeding until concrete is covered with burlap.

CS 16.4 Define the lots and determine core locations for air void system, tensile bond strength and rapid chloride permeability test.

CS 16.5 Obtain and review rapid chloride permeability results within 4 Business Days of testing and forward the results to the Quality Assurance Section.

CS 16.6 Check that dust and debris from exposed work, and from construction operations such as concrete cutting / grinding, abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Significant Area.

LEVEL OF INSPECTION – A1

155 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 17

STRUCTURE REHABILITATION -LATEX-MODIFIED CONCRETE OVERLAY

Task # Activity

CS 17.1 M Check that all the delivered material is being supplied from the approved list and stored properly. Check that material supplied by the Design-Builder is sampled and tested as specified in the Contract Documents.

CS 17.2 M Check that fine and coarse aggregate (enough for each stage) are stockpiled at the site three weeks prior to placing concrete. Sample as per Contract Document requirements and deliver to designated lab for mix design purposes. Check that sufficient latex modifier to complete each stage is delivered at least seven (7) Days prior to placing concrete.

CS 17.3 M Check that concrete mix design is available prior to the material discharge test on the mixing unit.

CS 17.4 Check that the aggregate discharge test and the test for flow rate of latex modifier are carried out as specified in the Contract Documents.

CS 17.5 M Check that Design-Builder carries out a yield test as specified in the Contract Documents. Check dimensions of yield and verify that data is being recorded accurately.

CS 17.6 Check that the trial run procedures are in accordance with CS 14.

CS 17.7 Check that the placement and quality assurance procedures are in accordance with CS 14 unless otherwise specified in the Contract Documents.

LEVEL OF INSPECTION – A1

156 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 18

STRUCTURE REHABILITATION – CONCRETE PATCHES Use this task in conjunction with CS 1, CS 2 and CS 14

Task # Activity

CS 18.1 Obtain documentation certifying that the superplasticizer meets the requirements of the special provision.

CS 18.2 Obtain the Design-Builder’s linear shrinkage test results within 40 Days of the mix design submission and forward to the Quality Assurance Section.

CS 18.3 Check that all supporting test data is not more than 12 months old from the date the concrete mix design was submitted.

CS 18.4 For FORM AND PUMP placement method, obtain and review the Design- Builder’s proposal at least one week prior to commencement of the work. Check that the proposal includes methodology and equipment to be used for this construction contract and that it is signed and sealed by a Professional Engineer.

CS 18.5 For FORM AND PUMP placement method, check that the pump is a positive displacement type pump and that it is capable of delivering adequate volumes of concrete to maintain a continuous placement.

CS 18.6 Check the temperature of the air and existing concrete surface to receive the patches, to ensure it meets Contract Document requirements prior to and during concrete operation.

CS 18.7 Check equipment and runways, vehicles for the concrete transporting/transferring equipment to ensure they are not supported by reinforcing steel.

CS 18.8 Check removal of all dust and loose material is carried out by oil-free compressed air.

CS 18.9 Check that the concrete surface and reinforcing steel have been abrasive blast cleaned according to CS 43. CS 18.10 Check that the prepared surface is maintained in a wet condition for six hours prior to placing concrete.

CS 18.11 Check excess water is removed by oil-free compressed air immediately prior to application of bonding grout.

157 Design-Build Administration Manual January 2014

CS 18.12 Check that thermocouple wires have been installed in the concrete for cold weather protection as specified in the Special Provision.

CS 18.13 M Review Design-Builder’s temperature records daily for cold weather protection (if applicable).

CS 18.14 Check that prior to seasonal shut down, all patches are completed in all areas of concrete removal.

CS 18.15 Check that no construction vehicles, equipment or traffic, with the exception of sawcutting equipment be permitted on the finished surface of the patches until the curing period has elapsed and a minimum of 80% of the specified compressive strength has been attained.

CS 18.16 Define the lots and determine core locations for air void system and tensile bond strength test.

CS 18.17 Check that the tensile bond strength testing is carried out as per the Contract Documents. Obtain and review tensile bond strength within four (4) Business Days of testing and forward the results to the Quality Assurance Section.

CS 18.18 Check that the core holes have been filled according to the Contract Documents.

CS 18.19 Check patches for any areas of debonding, honeycombed areas or cracks.

CS 18.20 Obtain and verify Design-Builder’s crack inspection report, review Design- Builder’s crack treatment proposal if applicable.

CS 18.21 Check that permission to waterproof is not issued until the cracks are treated (if applicable) and the patches in the deck are dried for three (3) Days.

CS 18.22 Obtain and review Design-Builder’s air void system test results within three (3) weeks of concrete placement and forward the results to the Quality Assurance Section.

LEVEL OF INSPECTION – A1 – B2 During placement

158 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 19

STRUCTURE REHABILITATION – CONCRETE REFACING Use this task in conjunction with CS 1, CS 2 and CS 18

Task # Activity

CS 19.1 Check that the welded steel wire fabric is welded galvanized steel and conforms to CSA G 30.5.

CS 19.2 Check that the anchors for the attachment of the wire fabric to the concrete surface are galvanized in conformance with the Contract Document requirements.

CS 19.3 Check that the anchors are of adequate length and strength to resist a pull-out force of 1.0 kN.

CS 19.4 Check that the wire fabric is installed after the concrete surface and exposed reinforcing steel in the repair area have been abrasive blast cleaned. Check that the wire fabric is installed in accordance with the Special Provision in the locations shown on contract drawings using spacers and anchors.

CS 19.5 Check that the wire fabric is kept clean of any contamination.

CS 19.6 Check that concrete material, production and testing is in accordance with CS 1. Check that submissions, concrete placement, finishing, curing, and quality assurance procedures are in accordance with CS 18 unless specified otherwise elsewhere in the Contract Documents.

CS 19.7 Check that the surface of the existing concrete is roughened according to the Contract Document requirements.

CS 19.8 Check that burlap and water is applied immediately to the top of all exposed concrete surfaces, within 2 to 4 m from the finishing operation. Check that burlap is kept continuously wet by means of a soaker hose placed along the top of the component being refaced. Check that the soaker is placed immediately after the concrete has set without causing fines to wash out.

CS 19.09 Check that the forms are removed according to the Contract Document requirements and that the concrete is cured as specified in the Special Provision.

159 Design-Build Administration Manual January 2014

CS 19.10 Check that dust and debris from exposed work, and from construction operations such as concrete cutting / grinding, abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Significant Area. Check that environmental protection enclosures or containment systems are in place and functioning.

LEVEL OF INSPECTION – C2

160 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 20

APPLICATION OF SILICA FUME OR NORMAL SHOTCRETE

Task # Activity

CS 20.1 Check that environmental protection enclosures or containment systems are in place and functioning prior to silica fume or shotcrete application.

CS 20.2 During silica fume or shotcrete application check that dust and debris from exposed work, and from construction operations such as concrete cutting / grinding, abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Sensitive Area.

CS 20.3 Obtain mix proportions and the name of the supplier of the prebagged shotcrete mix for approval at least one week prior to the application of shotcrete.

CS 20.4 Obtain with the mix design submissions all the supporting documents in accordance with the Contract Documents.

CS 20.5 Check that all supporting test data is not more than 12 months old from the date the mix design was submitted.

CS 20.6 Check shotcrete equipment submission is in accordance with the Contract Documents.

CS 20.7 M Check that the nozzle operator is certified.

CS 20.8 Obtain and check the curing submission which includes equipment and procedures to be used one week prior to the commencement of the application of shotcrete.

CS 20.9 Check where applicable, cold weather protection and hot weather shotcreting descriptions are in accordance with the Contract Documents.

CS 20.10 Check that the shotcrete material supplied meets the Contract Document requirements and that it is properly stored.

CS 20.11 Check Date of Manufacture to determine that has not expired.

161 Design-Build Administration Manual January 2014

CS 20.12 M Check that the following items meet specified requirements: (i) Shotcrete mixing equipment; (ii) Removal of concrete, abrasive blasting, placement of steel wire fabric and protection of adjacent surfaces; (iii) Pre-wetting of repair areas; (iv) Mix proportions of material delivered to site; (v) Application of shotcrete; (vi) Temperature before, during and after application of shotcrete.

CS 20.13 M Check that shotcrete is cured in accordance with the Contract Documents.

CS 20.14 M Sound for deficiencies in the repair areas.

CS 20.15 Randomly select locations for testing of compressive strength, tensile bond and rapid chloride permeability. Check for cracks that require remedial action.

CS 20.16 Obtain and review test results for compressive strength, tensile bond and rapid chloride permeability and forward results to the Quality Assurance Section within 4 Business Days of receiving them.

LEVEL OF INSPECTION – C2

162 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 21

STRUCTURE EXCAVATION

Task # Activity

CS 21.1 M Check that preconstruction survey of property and structures that may be affected by the work is submitted.

CS 21.2 M Check that protection schemes are constructed as per working drawings

CS 21.3 Check that erosion and sediment control schemes (and coffer dams if required) are in place and functioning prior to structure excavation such that the watercourse is isolated from the work area. Determine if additional erosion control measures, or additional locations may be required. Confirm that any other relevant environmental constraints have been addressed.

CS 21.4 Check that advanced unwatering is conducted as required to prevent soil sloughing, basal heave and boiling.

CS 21.5 Check that unwatering is not causing erosion of the soil at the outlet and other environmental concerns (e.g. muddy water discharge). Check that the Design-Builder has the standby equipment (pumps, hoses, sediment bags, etc.) on site as required in the environmental submission. Check that the unwatering / flow passage system complies with the Contract Documents, including any accepted Design-Builder’s proposals, and that the system is not causing sedimentation of the watercourse downstream of the work site.

CS 21.6 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

CS 21.7 Check the geometry of temporary slopes to facilitate excavation. Check that all footing excavations conform to size, shape, line, elevations and grades as specified in the Contract Documents.

CS 21.8 Check that loosened material, soft material, boulders and other deleterious material at the foundation base are removed and replaced with suitable compacted material or mass concrete. Check that any stockpiling of excavated material is done in an area that is isolated from any watercourses such that entry of sediment to watercourses is prevented.

163 Design-Build Administration Manual January 2014

CS 21.9 Record the depth, length, width, type of material used, and how it was placed, when the Design-Builder uses a working slab.

CS 21.10 Check that any adjacent Utility / structure is not affected or undermined by the footing excavation.

CS 21.11 Check that the founding soil is protected and preserved.

CS 21.12 Check that protection schemes are constructed as per working drawings.

CS 21.13 Check that excavation for frost tapers are carried out according to specifications.

CS 21.14 Check that any staged construction (excavation, backfilling sequence restrictions) is conducted.

LEVEL OF INSPECTION – E2

164 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 22

COFFERDAMS, SHEET PILING, TIE BACKSAND ROADWAY PROTECTION

Task # Activity

CS 22.1 Check length and condition of all materials delivered to the site.

CS 22.2 Check that a pre-construction site condition survey has been carried out as required.

CS 22.3 Check that the Design-Builder’s scheme is as specified in the Contract Documents or accepted proposal.

CS 22.4 M Verify that working drawings are submitted to the CA.

CS 22.5 Verify submissions bear the seal and signature of a design engineer and a design-checking engineer.

CS 22.6 Check that the information specified to be shown on the construction drawings has been included.

CS 22.7 Check that the Design-Builder’s scheme is as specified in the Contract Documents for length.

CS 22.8 Check that all elements of the unwatering / flow passage system (e.g. coffer dams) are properly staged / installed to prevent any discharge of sediment to the watercourse.

CS 22.9 Check the alignment, depth and layout of the protection scheme.

CS 22.10 Check that any vibratory equipment to facilitate the installation does not disturb native soil nor exiting Utilities / structures.

CS 22.11 Check that anchor testing equipment and procedure is as specified in the Contract Documents.

CS 22.12 Check that the Design-Builder monitors the completed scheme for movement.

CS 22.13 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

CS 22.14 Check that soil loss is not occurring during installation behind the shoring during excavation.

165 Design-Build Administration Manual January 2014

CS 22.15 Check that the corrosion protection has been provided as specified.

CS 22.16 Check that a record of each anchor hole excavation is submitted.

CS 22.17 Check that the quality of grout is being tested as specified.

CS 22.18 Check that the roadway protection / excavation sequence is properly executed.

CS 22.19 Verify Removal requirements for Temporary Roadway Protection.

LEVEL OF INSPECTION – E2

166 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 23

UNWATERING

Task # Activity

CS 23.1 Check that erosion and sediment control schemes are in place and functioning prior to the start of unwatering such that the watercourse is isolated from the work area and unwatering activities. Determine if additional erosion control measures or additional locations may be required.

CS 23.2 Check that the unwatering and flow passage systems required by the Contract Documents are in place and functional before disturbing the work area.

CS 23.3M Check that environmental special provisions and / or Design-Builder proposals for unwatering are adhered to.

CS 23.4 Check operation of unwatering system.

CS 23.5 Check that groundwater drawdown levels are as designed and the ‘natural flow’ of the watercourse is maintained. Check that the Design-Builder is monitoring as specified in the Contract Documents.

CS 23.7 Check that pump inlet is not submerged in mud and is properly screened to prevent fish ingestion.

CS 23.8 Check that discharge is being managed as per Contract Document requirements.

CS 23.9 Check that unwatering is not causing erosion of soil at the outlet and other environmental concerns (e.g. muddy water discharge). Check that the Design-Builder has the standby equipment (pumps, hoses, filter bags, etc.) on site as required in the environmental submission.

CS 23.10 M Check that the Design-Builder’s unwatering scheme is not causing loss of materials under adjacent founding elements or backfill.

CS 23.11 Check that unwatering system is not removed until the backfilling is brought up to grade and the work area is cleared of any debris or construction materials that could be washed downstream.

CS 23.12 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

167 Design-Build Administration Manual January 2014

LEVEL OF INSPECTION – B1/E2

168 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 24

PILING Use this task in conjunction with CS 1

Task # Activity

CS 24.1 Check that erosion and sediment control schemes are in place and functioning. If the control measures are not functioning or are insufficient the Design-Builder must be requested to review and take action.

CS 24.2 M Record and verify the pile type, length, condition of the pile splices and driving shoes and length to cut off. Verify straightness of piles.

CS 24.3 Check that all the delivered material is supplied from the approved list, and handled and stored so as to prevent damage to the piles.

CS 24.4 M Check that the correct value of imported steel has been declared on the “Statement of Imported Content” form. Collect all mill certificates (test results should be from Canadian testing facilities). Check that mill certificates satisfy the requirements in general and specifically for imported steel.

CS 24.5 M Check that pile driving equipment conforms to specified requirements. Monitor hammer performance.

CS 24.6 Check that the end treatments are correctly applied (i.e. shoes, Oslo Points, Bearing Points, collars, etc.).

CS 24.7 M Check that pile installation sequence is as per submission, and that layout of piles conforms to Contract Document requirements.

CS 24.8 Check that vertical and batter alignment of pile meets specified requirements.

CS 24.9 M Verify that piles are not overdriven and hence damaged during installation.

CS 24.10 M Check that welder is certified. Check that welding of splicing conforms to specified requirements, and that pile splices are carried out properly.

CS 24.11 Check that pile set and refusal criteria are satisfied. Check that actual tip elevation corresponds to design founding stratum.

CS 24.12 Check that the piles are cut off as specified.

169 Design-Build Administration Manual January 2014

CS 24.13 Check that retapping / redriving requirements are being satisfied.

CS 24.14 Check the Design-Builder’s pile driving records.

CS 24.15 Check that noise control restrictions have been complied with.

CS 24.16 M Check that the piles are installed to the specified tolerances.

CS 24.17 For piles driven to refusal, check that the appropriate Dynamic Formula is used in accordance with the Contract Documents..

CS 24.18 Check that piles are not driven adjacent to fresh concrete as specified in the Pile Driving Restrictions and Requirements in the Piling Special Provision.

CS 24.19 M When driving piles to a set, contact Foundations Office immediately if ultimate axial resistance of pile is not achieved. Check that the Design-Builder doesn’t drive pile beyond design tip elevation without consultation with Foundations Office.

CS 24.20 When retapping piles, check that piles are retapped at the previous set.

CS 24.21 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – A1

170 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 25

CAISSON FOUNDATIONS Use this task in conjunction with CS 1

Task # Activity

CS 25.1 Check type, length and condition of caisson liners.

CS 25.2 M Check that welder is certified.

CS 25.3 M Check that installation equipment is as specified in the Contract Documents.

CS 25.4 Check that erosion and sediment control schemes are in place and functioning. Determine if additional erosion control measures or additional locations may be required.

CS 25.5 Check that caisson is drilled to design tip elevation.

CS 25.6 Check that penetration and cut off are in accordance with design data.

CS 25.7 Check that sidewall and basal stability is maintained during the caisson foundation installation.

CS 25.8 M Check that caissons are cleaned out prior to placing reinforcing steel and concrete.

CS 25.9 Check the Design-Builder’s cleaned out material containment location. Check that containment locations are placed away from watercourses and that erosion and sediment control measures are in place and functioning around them.

CS 25.10 Check that slurry properties are being tested and verified as per Contract Document requirements.

CS 25.11 Check that reinforcement steel is being properly placed as per Contract Document requirements.

CS 25.12 Check that vertical and batter alignment of caisson are as specified in the Contract Documents.

CS 25.13 Check that rock socketted caissons are installed to the appropriate depth, tip elevation and geometry.

171 Design-Build Administration Manual January 2014

CS 25.14 Check that any temporary slurry does not negatively impact shaft resistance design requirements. Temporary slurry needs to be adequately flushed.

CS 25.15 Check that concrete is placed within the specified time period following cleaning and inspection of caisson base.

CS 25.16 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – B2

172 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 26

STRUCTURE BACKFILLING

Task # Activity

CS 26.1 Check that erosion and sediment control schemes are in place and functioning. Determine if additional erosion control measures or additional locations may be required.

CS 26.2 M Check that the structure excavation limits are verified and recorded prior to commencement of backfilling operations.

CS 26.3 M Check that the concrete has reached the required percentage of the design strength prior to backfilling.

CS 26.4 Check that subdrains are placed as specified in the Contract Documents.

CS 26.5 Check that proper procedures are used for weep holes and perforated pipe installation.

CS 26.6 Check that backfill is placed as specified in the Contract Documents, and that all backfill materials are free of waste.

CS 26.7 M Check that appropriate compaction procedure and sequence is used, and that appropriate compaction equipment is used in restricted areas. Check that appropriate compaction testing is being conducted

CS 26.8 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – C2

173 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 27

FORMWORK

Task # Activity

CS 27.1 Check that dimensions of forms are as specified in the Contract Documents.

CS 27.2 Check that form release oil is applied to the forms before the installation of reinforcing steel.

CS 27.3 Check forms (several times) for alignment and possible deformation, during concrete placement.

CS 27.4 M Check that the Certificate of Conformance is supplied andreviewed as per the requirements of the Contract Documents.

LEVEL OF INSPECTION – E2

174 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 28

FALSEWORK

Task # Activity

CS 28.2 M Check that stamped falsework drawings are on site. Check installed falsework against stamped working drawings prior to pour. CS 28.1 Check that the founding soil is prepared.

CS 28.2 Check that any foundation bearing pad is properly placed and compacted.

CS 28.3 Monitor falsework (several times) during concrete placement operation for deflection and settlement.

CS 28.4 M Check that the required concrete strength has been reached prior to removing falsework.

CS 28.5 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – E2

175 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 29

INSTALLATION OF BEARINGS

Task # Activity

CS 29.1 M Check that the Adjustment of Bearing drawings are supplied and reviewed as per the time requirements of the Contract Documents.

CS 29.2 Check that all the delivered material is being supplied from the approved list and properly stored.

CS 29.3 Check and record from elastomeric bearings, the size, name of manufacturer, part number and date of manufacture and also check that the bearing is not on the list of defective bearings put out by the Concrete Section.

CS 29.4 When specified, randomly select and then have the Design-Builder ship the sample bearing(s) for testing as specified.

CS 29.5 Check that surface and bedding of bearing seats are within tolerances and meet the requirements of the applicable specifications.

CS 29.6 Check that each bearing is installed at the correct location, elevation, and is properly aligned as specified in the Contract Documents.

CS 29.7 Check for removal of any shipping device or restraints from bearings as specified in the Contract Documents and/or shop drawings.

CS 29.8 M Upon completion of the structure, visually inspect the bearings to determine that they have full and uniform bearing at top and bottom, and that bearing components are not out of position.

CS 29.9 Check the timing and procedure for jacking and re-alignment of bearings.

CS 29.10 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – D2

176 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 30

STRUCTURAL STEEL BEAM ERECTION

Task # Activity

CS 30.1 M Check that the steel is supplied from a designated source and that the correct value of imported steel has been declared on the “Statement of Imported Content” form.

CS 30.2 M Check that the stamped erection drawings are on site.

CS 30.3 Check that beams have not been damaged and are set to the specified alignment and seated properly.

CS 30.4 M Collect steel mill certificates (coupon tags) and store on file in site office.

CS 30.5 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – D2 – A-2 during erection

177 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 31

REINFORCING STEEL PLACEMENT

Task # Activity

CS 31.1 Check reinforcing steel schedule and drawings.

CS 31.2 Check for proper site storage and handling.

CS 31.3 M Check mill certificates to determine that the steel is supplied from a designated source.

CS 31.5 Obtain a sample of stainless steel rebar as per the Contract Documents.

CS 31.6 Check that the correct grade and size of steel has been placed in accordance with the Contract Documents.

CS 31.7 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – E2

178 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 32

PRESTRESSING SYSTEMS

Task # Activity

CS 32.1 Check type, size and condition of prestressing materials delivered to the site.

CS 32.2 Check for proper site storage of prestressing materials.

CS 32.3 Check that material supplied by the Design-Builder is sampled and tested as required.

CS 32.4 Check installation of prestressing sheaths, support cables, and anchorages.

CS 32.5 Check the elevation and alignment of cable sheaths.

CS 32.6 Check that cable sheaths are secured firmly in place.

CS 32.7 Check that grout vent hoses are installed at all the proper locations.

CS 32.8 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – B2

179 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 33

STRESSING OPERATION

Task # Activity

CS 33.1 M Check that stressing working drawings are on site.

CS 33.2 Check that the correct calibration tests have been carried out by an approved authority in the last six months.

CS 33.3 M Check that void hold-downs are released prior to stressing.

CS 33.4 M Check that concrete is up to specified strength prior to stressing.

CS 33.5 Check that cables are stressed in proper sequence.

CS 33.6 Check that cables are marked and measured and that elongation, gauge pressure and slip are recorded.

CS 33.7 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – C2

180 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 34

GROUTING OF POST-TENSIONING DUCTS

Task # Activity

CS 34.1 M Prior to the grouting operations, check that the test batch has been mixed in the presence of the Quality Verification Engineer and that the quality of the grout meets the specified requirements.

CS 34.2 After completion of post-tensioning operation, obtain the Design-Builder’s records of elongation, calibrated jacking pressure readings, slippages and strand bandages.

CS 34.3 Verify that the Quality Verification Engineer carries out Interim Inspection of post-tensioning system, witnesses stressing and issues written permission to the Design-Builder to proceed with grouting. Check that grouting does not proceed until the permission is given.

CS 34.4 Check that ducts are blown out with oil free air and, when required, with water.

CS 34.5 Check that all vent tubes are free from blockage.

CS 34.6 Check that dry grout mix components meet the Contract Document requirements.

CS 34.7 Check that the concrete temperature of the deck is as specified in the Contract Documents.

CS 34.8 Check the mixer and pump. Check that pressure gauge at pump or intake, water measures, and timer are accurate.

CS 34.10 Check that grouting is carried out within the specified time limits of tensioning and receipt of permission to grout.

CS 34.11 Check that the grout is being tested and meets the specified requirements.

CS 34.12 Identify batch (es) of grout from which grout cubes for determination of compressive strength will be made.

CS 34.13 Check that grout cubes are taken for testing and delivered as required to the specified testing facility.

CS 34.14 Check that grouting operation is continuous and hoses are topped-up prior to tying off as specified in the Contract Documents.

181 Design-Build Administration Manual January 2014

CS 34.15 Check Design-Builder’s placing schedule such that placement of sidewalks, curbs, median curbs, etc., is done after the grouting of post tension grout tubes.

CS 34.16 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – A1

182 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 35

BRIDGE DECK WATERPROOFING

Task # Activity

CS 35.1 M Check that the deck meets the requirement for surface tolerance and surface finish of the Contract Document requirements.

CS 35.2 Identify all repairs and remedial work that needs to be carried out prior to waterproofing including texture surfaces, sawcut grooves and scaling.

CS 35.3 Check that all repairs and remedial work to the concrete deck have been completed.

CS 35.4 M Check that the air and concrete surface temperature are 5°C or higher.

CS 35.5 Check that Design-Builder performing the waterproofing is approved.

CS 35.6 M Permission is given to Design-Builder to proceed after verifying that the deck surface, face of the curbs and barrier walls were completely treated by abrasive blast cleaning to expose sound, laitance-free concrete.

CS 35.7 Check that no traffic, other than the construction equipment directly associated with the waterproofing operation, is allowed on the abrasive blast cleaned deck.

CS 35.8 Check that tack coat is applied uniformly at the required rate when the concrete is surface dry and clean.

CS 35.9 Check that the Design-Builder takes adequate protective measures to mask concrete and prevent over-spray of tack coat materials onto adjacent concrete surfaces (curb face, barrier wall, abutments, columns, etc.) to prevent waterproofing material from entering a watercourse.

CS 35.10 M Check that all delivered materials are from an approved source.

CS 35.11 Check that tack coat is cured completely and free of any surface moisture and dirt before waterproofing membrane is applied.

CS 35.12 Check that the mixing kettle is completely empty prior to commencement of melting cakes of asphalt membrane.

183 Design-Build Administration Manual January 2014

CS 35.13 Check that temperature of waterproofing membrane at time of placing is as specified and that the temperature does not exceed the safe heating temperature at any time during the waterproofing operation.

CS 35.14 Check for correct placement of membrane reinforcement over joints. Check for correct placing of protection boards. Check proper lapping of waterproofing at construction joint and staging boundaries.

CS 35.15 Upon completion of each lot, measure and record membrane thickness following the procedure in the “Field Guide for the Acceptance of Hot Mix and Bridge Deck Waterproofing”.

CS 35.16 M Compute payment adjustment factor and have the Design-Builder sign form PH-CC-129 A prior to paving. Submit the “Waterproofing Membrane Thickness Report” to the Quality Assurance Section within 4 Business Days of completing it.

CS 35.17 Check that all test results have been received and price adjustments calculated and applied as appropriate.

CS 35.18 Check that asphalt drainage tubes are open.

CS 35.19 Check tack coating of protection boards just prior to paving.

LEVEL OF INSPECTION – B2

184 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 36

PRESTRESSED CONCRETE MEMBERS (NORMAL AND HIGH PERFORMANCECONCRETE)

Task # Activity

CS 36.1 M Check that submissions are as per the Contract Document requirements.

CS 36.2 Obtain Form A portion of the concrete mix design along with the supporting documentation at least 14 Days prior to placement of concrete and review it to determine that it meets the Contract Document requirements. Check that the Regional Quality Assurance Section has received Form B portion of the concrete mix design from the concrete supplier prior to placement of concrete.

CS 36.3 Issue written confirmation that the concrete mix design submission meets the Contract Document requirements or advise the Design-Builder of any requirements that have not been met.

CS 36.4 Check that the members are fabricated at a plant certified according to the Contract Document requirements.

CS 36.5 M Check that the stamped erection drawings are on site.

CS 36.6 M Check that members are fabricated, delivered and erected as per the Contract Documents.

CS 36.7 Check that members meet the dimensional tolerances of the Contract Documents and they are free of any defects.

CS 36.8 Obtain and review test results for compressive strength, air voids and rapid chloride permeability.

CS 36.9 Check that the members are temporarily braced immediately after erection.

CS 36.10 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – D2

185 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 37

INSTALLATION OF EXPANSION JOINTS Use this task in conjunction with CS 1

Task # Activity

CS 37.1 Check that no damage occurs during handling.

CS 37.2 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. Check that material supplied by the Design-Builder is sampled as required. Check for proper storage of the joints.

CS 37.3 M Check that field splices in steel components are located and welded as per shop drawings and are performed by a certified welder.

CS 37.4 Check that the dimensions of the block-out to receive the joint assembly are in accordance with the contract drawings and standard drawings.

CS 37.5 Check that the block-out area to receive the joint is abrasive blast cleaned, without damaging the epoxy coated steel.

CS 37.6 Check that all debris in the block-out has been removed and the area is coated with a cement paste prior to placing concrete.

CS 37.7 M Check that the proper gap or “j” dimension of the unit has been established prior to placing concrete, and check that the constant gap is achieved throughout the total length.

CS 37.8 M Check that clamping angles or channels are removed as specified in the Contract Documents.

Cs 37.9 Check that holes left from removal of clamping angles or channels are cleaned and grouted with approved epoxy.

CS 37.10 Check for concrete blockages in the expansion joint opening.

CS 37.11 Check that seal is properly installed with no damage, wrinkles or splices.

CS 37.12 Check that sliding plates on sidewalk, curbs and median have been installed properly with regards to the direction of traffic.

CS 37.13 Check that formwork including styrofoam has been removed below expansion joint assembly between deck and ballast wall.

186 Design-Build Administration Manual January 2014

CS 37.14 Check for cracks in the concrete adjacent to the expansion joint.

CS 37.15 Check that end dam concrete has been cured for a minimum of 7 Days and has reached 25 MPa prior to epoxy injection.

CS 37.16 M Check that traffic is not allowed on the deck joint assembly until the epoxy injection has been completed and cured, and clamping bars are installed for Type A expansion joints.

CS 37.17 Check that the injection method is in accordance with the Contract Documents and injected by the supplier of the expansion joint system, or an agent approved by the supplier.

CS 37.18 M Sound the steel armour for voids. If voids are detected, check that proper procedures are taken to fill the voids.

CS 37.19 M Check that a water test has been carried out.

CS 37.20 Check that all waste material (Styrofoam) is disposed of as per the Contract Documents.

CS 37.21 M Check that the Certificate of Conformance is supplied and reviewed for each task and as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – C2

187 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 38

TEMPORARY MODULAR BRIDGES

Task # Activity

CS 38.1 Check that erosion and sediment control schemes are in place and functioning prior to start of modular bridge installation. Determine if additional erosion control measures, or additional locations may be required.

CS 38.2 Check that all environmental constraints have been complied with (fisheries approvals, work on the banks, etc.) prior to installation.

CS 38.3 M Visually check foundations as per Contract Documents.

CS 38.4 Check that layout and elevations of the launching and construction rollers have been approved. Check that founding elements, cribs, and footings are located as per plan.

CS 38.5 M Check that all bracing bolts, chord bolts and transom clamps remain fully tightened.

CS 38.6 Check that base plates and bearings are free of debris.

CS 38.7 Inspect base plates and cribs for settlement.

CS 38.8 Visually check timber for soundness and specified requirements.

CS 38.9 Check material control is as specified in the Contract Documents.

LEVEL OF INSPECTION – E2

188 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 39

STRUCTURAL STEEL COATING

Task # Activity

CS 39.1 Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

CS 39.2 Check that material supplied by the Design-Builder is sampled as required.

CS 39.3 Check that all requirements of manufacturers product data sheets are met.

CS 39.4 Check that individual coating products used in the coating system come from the same manufacturer and are compatible.

CS 39.5 Check that environmental operations including enclosure systems, negative pressure, management including sampling, testing, storage, documentation / manifesting, transportation and disposal of spent blast medium and removed coating material are as specified in Contract Documents and/or Design-Builder’s approved proposal. Check that a copy of all test results and manifests are provided to the MTO Environmental Planner – .

CS 39.6 M Check that surface preparation is carried out as specified in the Contract Documents and meets the specified SSPC standard.

CS 39.7 Check sample(s) of spent blast medium is obtained as specified in the Contract Documents.

CS 39.8 M Check that coating of structural steel follows cleaning within the time as specified in the Contract Documents.

CS 39.9 Check air temperature and dew point restrictions.

CS 39.10 Check that the coat application is carried out as specified in the Contract Documents.

CS 39.11 Check that the dry film thickness gauge and any DFT gauge utilized by the Design-Builder are calibrated to SSPC PA-2 and any special provision requirements. Only type 2 gauges are to be used.

CS 39.12 M Check that each coat meets the dry film thickness requirements. Test frequencies and acceptance to be in accordance with SSPC PA-2, including the requirements in Appendix 3 for girder structures.

189 Design-Build Administration Manual January 2014

Acceptance of multiple coats will be based on the cumulative minimum and maximum requirements after each coat application. Deficiencies to be corrected before acceptance and proceeding with subsequent coat.

CS 39.13 Check that all blast abrasive, dust and other debris are removed from the steel surface and each coating surface prior to the application of the subsequent coat.

CS 39.14 Complete Daily Inspection Report Forms PH-CC-782A and/or PH-CC- 782B each day and Summary Form PH-CC-783 after the completion of the work on each structure.

CS 39.15 Check condition of galvanized components during installation. Check that repairs are as specified in the Contract Documents.

CS 39.16 M Check that the Service Provider or sub-consultant inspecting the structural steel coating holds the appropriate certifications.

LEVEL OF INSPECTION – A1

190 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 40

STEEL PARAPET RAILING

Task # Activity

CS 40.1 M Check type, size, length and condition of materials (including protective ) delivered to the site. Check that all the delivered material is being supplied from the approved list and is properly stored.

CS 40.2 M Check that installation is as specified in the Contract Documents.

CS 40.3 Check the condition of completed posts and rails. Check that damaged areas are properly repaired.

CS 40.4 M Check that the Certificate of Conformance is supplied and reviewed for each task and as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – E2

191 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 41

OVERHEAD SIGN PLACEMENT Use this task in conjunction with CS 1

Task # Activity

CS 41.1 Check that erosion and sediment control schemes are in place and functioning prior to start of overhead sign placement. Determine if additional erosion control measures, or additional locations may be required.

CS 41.2 M Check that the foundations for the overhead signs are installed to the depth, size and procedures specified in the Contract Documents.

CS 41.3 Check footings with regards to “as constructed” elevations and type, plumbness of footing, alignment between two founding elements and the distance between the two founding elements (C/C footings).

CS 41.4 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

CS 41.6 M Check overhead sign structure to determine that installation is in accordance with the contract drawings and shop drawings.

CS 41.7 M Check that correct sign message is mounted on the support.

CS 41.8 M Check full bearing of all base plates.

CS 41.9 Check that sign structure is installed facing in the proper direction and that the required number of sign clamps have been supplied.

CS 41.10 Check for cracking of erected sign structure.

CS 41.11 Check that exposed anchorage threads do not exceed 3 diameters.

CS 41.12 Check the top of footing for surface finish and levelness.

CS 41.13 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – E2

192 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 42

RETAINED SOIL SYSTEMS

Task # Activity

CS 42.1 M Check that all submissions bear the seal and signature of the Design Engineer and the Design Check Engineer.

CS 42.2 M Check that the Design-Builder has selected a RSS designated as A (Accepted) or DE (Demonstration) on the DSM List that meets the specified Contract Document requirements.

CS 42.3 M Check that the Design-Builder has a copy of the stamped working drawings on site at all times.

CS 42.4 M Check that the working drawings include at least the following:

• All design, fabrication and construction drawings and specifications for the RSS • Details of all excavation, unwatering, drainage and backfilling required to construct the RSS, including type and source of associated backfill • Details at joints and connections to other structures where shown in the Contract Drawings • Details of all protection systems • Statement of bearing resistance required by the RSS foundation, and the bearing resistance provided in accordance with the CHBDC • Statement of satisfactory internal and external stability • All design, fabrication and construction drawings and specifications for traffic barriers and base, and finishing caps, where applicable • Details of how all relevant Operational Constraints and Environmental Constraints, as specified in the Contract Documents, will be adhered to • A copy of the Approved Product Drawings covering material and construction details.

CS 42.5 M Forward one set of the stamped working drawings to the Pavement and Foundation Section, Ministry of Transportation, Downsview, for information purposes

CS 42.6 Check that all loose, softened, deleterious material at the founding elevation of the RSS is removed.

193 Design-Build Administration Manual January 2014

CS 42.7 M Check that foundation preparation is carried out as per the contract drawings and documents.

CS 42.8 M Check that the backfill type is as indicated on the working drawings and that the Design-Builder is placing the backfill as per the manufacturers recommendations, working drawings and Contract Documents.

CS 41.10 Check that concrete barrier is not part of the lump sum item.

CS 41. 11 Check excavation limits in backfill zone.

CS 42.12 M Check alignment such as stations, lines and grades, cross-sections, verify levelling pad elevation and other constraints as specified in the Contract Drawings.

CS 42.13 M Check for Out-of-Tolerance Geometry, Performance and Aesthetics Conditions / Deficiencies as per working drawing requirements.

For walls: visible distress in wall, differential settlement, tilting or rotating facing elements, bulging, panel / block contact resulting in spalling or chipping, wall facing out of vertical (plumb) or horizontal alignment.

For slopes: lack of vegetation, sloughing, lack of erosion protection, maximum slope angle exceeds that specified in Contract Documents.

CS 42.14 M Check that Warranty requirements are satisfied.

CS 42.15 M Check that the Certificates of Conformance are supplied and reviewed in a timely manner to correspond with the intervals that meet the specified Contract Document requirements.

LEVEL OF INSPECTION – A2

194 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 43

ABRASIVE BLAST CLEANING OF CONCRETE SURFACES AND REINFORCING STEEL

Task # Activity

CS 43.1 Check that Environmental containment systems are in place and functioning prior to start of abrasive blast cleaning.

CS 43.2 M Check that concrete surface and reinforcing steel are abrasive blast cleaned according to the Contract Documents.

CS 43.3 Check that dust and debris from exposed work, and from abrasive blast cleaning of concrete and steel, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Sensitive Area.

CS 43.4 M Check that the subsequent concrete is placed within the time limit specified in the Contract Documents.

CS 43.5 M Verify Contract Document requirement for removal of epoxy coating from existing epoxy coated reinforcing steel.

CS 43.6 Check that all new epoxy coated reinforcing steel in the vicinity of the abrasive blast cleaning is protected.

LEVEL OF INSPECTION – C2

195 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 44

LIGHTWEIGHT FILL MATERIALS

Task # Activity

SLAG

CS 44.1 M Check that the Design-Builder has submitted the Certificates of Conformance for the material properties prior to placement.

CS 44.2 Check that the Design-Builder submits Quality Control Test Results.

CS 44.3 M Check that the Design-Builder has retained a laboratory accepted by the MTO to conduct testing of the physical, mechanical and chemical properties of the material.

CS 44.4 Check that the trial area is properly constructed.

CS 44.5 Check that the insitu unit weight requirements and overcrushing restrictions are satisfied during the trial and also during construction.

CS 44.6 Check that the Design-Builder’s compaction equipment and procedure satisfies the requirements of the specification.

CS 44.7 M Check that the Design-Builder has submitted Certificate of Conformance stating that the material satisfies the requirements of the specification, and the work has been carried out in general conformance with the Contract Documents.

Expanded Poly Styrene

CS 44.8 Check that the shop drawings are reviewed, signed and sealed by the Quality Verification Engineer prior to commencement of work.

CS 44.9 Check that the materials satisfy the requirements of the Special Provisions.

CS 44.10 Check that foundation excavation and preparation is conducted to remove any loosened or deleterious materials.

CS 44.11 Check that the levelling pad is properly placed and compacted.

CS 44.12 Check that the EPS are properly installed.

CS 44.13 M Check that the EPS blocks are properly covered with .

196 Design-Build Administration Manual January 2014

CS 44.14 Check that the concrete slab is properly constructed on top of the EPS blocks.

CS 44.15 Check that side slope material is placed without damage to the blocks.

CS 44.16 M Check that a final Certificate of Conformance signed and sealed by the Quality Verification Engineer is submitted.

LEVEL OF INSPECTION – C2

197 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 45

PRECAST CONCRETE CULVERTS

Task # Activity

CS 45.1 M Check the manufacturer is on the Ministry’s approved list. .

CS 45.2 M Check that applicable Contract Document required submissions are received and reviewed prior to fabrication.

CS 45.3 Check maximum concrete strength specified on contract drawings is provided on submitted shop drawings.

CS 45.4 M Check dimensions of units as arriving on site until consistency of units is confirmed checking every third unit from there on prior to any installation operations. Reject any units that do not meet the dimension tolerances outlined in Contract Documents.

CS 45.5 Check that all environmental and dewatering schemes are in place and working in an acceptable manner.

CS 45.6 Check the condition, limits and elevation etc., of subgrade has been approved prior to and placement of granular base material.

CS 45.7 Check granular base limits, material meets Contract Document requirements. .

CS 45.8 Confirm bedding materials, elevations and levelness.

CS 45.9 Check that apron walls are aligned properly and applicable grout is installed as per Contract Document requirements

CS 45.10 M Check the installation of the units are as per Contract Document requirements (shop drawings and manufacturer’s recommendations).

CS 45.11 M If gaps are larger than specified the Design-Builder should not proceed with the installation of the remainder of the units until an acceptable proposed solution has been received.

CS 45.12 Check gasket or seals have been installed as per the Contract Document requirements and that gaps do not exceed the specified requirements.

CS 45.13 Confirm streambed substrate as per the Contract Documents.

198 Design-Build Administration Manual January 2014

CS 45.14 M Check that structure excavation limits have been verified and recorded prior to backfilling operations.

CS 45.15 Check that are external joint requirements, recesses, lifting lugs and holes are filled as per Contract Document requirements prior to backfilling.

CS 45.16 Check that the backfilling operation and material etc., meet Contract Document requirements. (see applicable backfilling to structures inspection task)

CS 45.17 Check that applicable post tensioning is per Contract Document requirements (see applicable post tension inspection task).

CS 45.18 M Check that all applicable Certificates of Conformance including installation are submitted as per the Contract Documents and reviewed.

LEVEL OF INSPECTION – C2 during placement of the units – C1 during non-placement operations

199 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 46

DOWELS IN CONCRETE

Task # Activity

CS 46.1M For all dowels, not limited to those selected for testing, check that concrete in the vicinity of the dowel location is sound and free of cracks.

CS 46.2 Schedule dowel pull testing with the independent laboratory and check that the testing is completed within 5 Business Days of Design-Builder notice.

CS 46.3 Review equipment calibration documentation and that calibration test data is not more than 12 months old.

CS 46.4 M Check that dowel being used is on the Ministry’s approved designated sources list.

CS 46.5 Select dowels for in-situ testing.

CS 46.6 Select location for Proof of Process Installation when in-situ testing cannot be done.

CS 46.7 M Check that the hole drilled is correct size, depth and free of all dust, debris and water prior to placing the applicable bonding material.

CS 46.8 Check that all applicable manufacturer’s recommendations and written instructions are adhered to.

CS 46.9 Check that the gel time of dowel adhesive is long enough to allow proper dowel installation.

CS 46.10 Check that dowels are maintained in the proper position during the setting period and that excess epoxy is removed.

CS 46.11 Check that pull-testing is completed as specified in the Contract Documents.

LEVEL OF INSPECTION – C1/D2

200 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 47

STEEL BREAKAWAY SIGN PLACEMENT

Task # Activity

CS 47.1 M Check that support is laid out at the correct station and offset.

CS 47.2 M Check that designed footing elevations match the as constructed grade (footings shall be level with surrounding grade). Report deviations to designer for correction prior to installation.

CS 47.3 M Check that support parts are supplied by a designated source. Verify that all support parts are new.

CS 47.4 Check that support is constructed according to contract drawings and relevant Special Provisions.

CS 47.5 Check that all hardware is in place and that the hardware is secure.

CS 47.6 Check that correct sign is mounted on the support. Check that the sign is not damaged during installation.

CS 47.7 Check that the support footings or disturbed ground – the result of installation activities – do not obstruct drainage.

CS 47.8 M Check that foundations for the breakaway signs are installed to the depth, size and procedures specified in the contract drawings.

CS 47.9 M Check that applicable submissions are received.

LEVEL OF INSPECTION – E2

201 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 48

TIMBER BREAKAWAY SIGN PLACEMENT

Task # Activity

CS 48.1 M Check that support is laid out at the correct station and offset. The offset is measured relative to edge of pavement, which is the nearest pavement lane edge line.

CS 48.2 M Check that support is constructed according to contract drawings and requirements. Check that the posts are plumb in both directions. Verify that all cut and drilled surfaces have been treated with wood preservative.

CS 48.3 Check that correct sign is mounted on the support. Check that the sign is level and has not been damaged during installation.

CS 48.4 Check that the support footings or disturbed ground – the result of installation activities – do not obstruct drainage.

CS 48.5 Check that all hardware is in place and that the hardware is secure.

CS 48.6 M Check that applicable submissions are received.

LEVEL OF INSPECTION – E2

202 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 49

DOWELS INTO BEDROCK

Task # Activity

CS 49.1 Check the hole is drilled to correct size, depth and cleaned prior to placement of dowel.

CS 49.2 Check dowel size.

CS 49.3 M Verify that cementitious non shrinking grout is used to fill the annular space.

CS 49.4 Check that dowels are maintained in the proper position during the setting period.

CS 49.5 M Verify that the dowel pull out tests are conducted in accordance with the specifications.

LEVEL OF INSPECTION – E2

203 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 50

FOUNDTION INSTRUMENTATION FOR MONITORING SETTLEMENTS, PORE PRESSURES, LATERAL DISPLACEMENTS

Task # Activity

CS 50.1 M Check that instrumentation supply is per the contract drawings and specifications.

CS 50.2 M Check that the installation is per the contract drawings and specifications. Check that the sequence of installation is per the contract drawings and specifications.

CS 50.3 M Check that baseline readings are obtained in accordance with the Contract Document specifications.

CS 50.4 M Check that the required installation data, readout units and other is transferred to the Monitoring Service Provider as per the contract drawings and specifications.

LEVEL OF INSPECTION – E2

204 Design-Build Administration Manual January 2014

CONCRETE AND STRUCTURES – TASK CS 51

MASS CONCRETE ON BEDROCK Use this task in conjunction with CS 1

Task # Activity

CS 51.1 Check that any dewatering is carried out prior to mass concrete placement

CS 51.2 M Check that the surface of the founding rock is exposed, cleaned and any loose or fractured parts removed so that rock is exposed. Check that the mass concrete is placed on the exposed cleaned sound founding rock surface as per the contract drawings and documents.

CS 51.3 Check that that the minimum thickness of mass concrete is achieved.

LEVEL OF INSPECTION – E2

205 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 1

GRANULAR SEALING

Task # Activity

BIT 1.1 M Check that areas to be sealed are shaped and dampened before sealing.

BIT 1.2 M Check that granular is not frozen, air temperature is above minimum, wind does not cause drifting off designated area in contract and precipitation is not imminent.

BIT 1.3 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

BIT 1.4 M Check that material supplied by the Design-Builder is sampled and tested as required.

BIT 1.5 Check environmental constraints before applying sealant.

BIT 1.6 M Check for proper rate and method of application and uniform coating.

LEVEL OF INSPECTION – D2

206 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 2

RECLAIMING ASPHALT PAVEMENT

Task # Activity

BIT 2.1 M Check that random samples of Reclaimed Asphalt Pavement (RAP) to be used in Recycled Hot Mix (RHM) have been taken after processing.

BIT 2.2 M Check that reclaiming is carried out to design width to essentially the same station before shutdown each day and properly ramped.

BIT 2.3 Check that there is no contamination with granular shoulder and granular base material when RAP is to be used in RHM.

BIT 2.4 Partial Pavement Removal (i) Check for correct crossfall, depth and surface texture during milling; (ii) Record reclaimed asphalt removal rate (m²/hr); (iii) Check that the milled surface is broomed and inspected, and that areas of asphalt rich dust are removed.

BIT 2.5 Full Depth Removal (i) Check that granular is restored to specified requirements following pavement removal; (ii) Check and record depths of removal.

LEVEL OF INSPECTION – B1/D2

207 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 3

HOT MIX PAVING

Task # Activity

BIT 3.1 Check proper joint construction including location of longitudinal joints, preparation, tack coating and compaction.

BIT 3.2 Check that paving is carried out to design width to approximately the same station, with ramping as specified in the Contract Documents prior to shutdown each day, including edge ramping.

BIT 3.3 Check the condition of substrata (compaction, etc.) ahead of paving operation. Confirm surface to be paved is unfrozen, clean, dry and free of standing water.

BIT 3.4 Check sequence of paving operations including, but not limited to, paving intersections, tapers, ramps, bridge decks and all staging plans.

BIT 3.5 M Check placement of hot mix including alignment, crossfall, surface tolerance, width, smoothness, depth of asphalt mat using the area covered and applicable BRD for the mix (kg/m²) or other applicable contract related field checks (such as for the m² payment method).

BIT 3.6 M Check that the distribution rates of premium surface courses are revised to account for the mass multiplier factors.

BIT 3.7 Check that air temperature at the surface of the road is above the minimum specified in the Contract Documents (if applicable) to permit paving.

BIT 3.8 Check that temperature of mix delivered to the site does not exceed the maximum discharge temperature allowed in the Contract Document (if applicable).

BIT 3.9 M Visually inspect mix placed for dragging, segregation and other visual defects prior to covering with another lift and / or stage changes.

BIT 3.10 Check paving in echelon operation to determine that the specified distance (if applicable) between pavers is maintained.

BIT 3.11 M Check and witness that all required samples are taken at correct (random) locations and tonnages.

BIT 3.12 Check that equipment does not impact/damage areas beyond shoulder.

208 Design-Build Administration Manual January 2014

BIT 3.13 M Check for proper reinstatement of sample locations (plates and cores) on a daily basis.

LEVEL OF INSPECTION – A2

209 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 4

CUT AND FILL GROOVES

Task # Activity

BIT 4.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

BIT 4.2 M Check that material supplied by the Design-Builder is sampled and tested as specified in the Contract Documents.

BIT 4.3 M Check that existing pavement joints are marked to determine that the new groove is located precisely over the existing joints.

BIT 4.4 Check that the grooves are cleaned and dried immediately prior to pouring the joint sealing compound.

BIT 4.5 Check that grooves are cut and filled as soon as possible after paving, as specified in the Contract Documents.

LEVEL OF INSPECTION – B1/D2

210 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 5

ROUTING AND SEALING CRACKS

Task # Activity

WITH WARRANTY

BIT 5.1 W Document non-compliance with Contract Document requirements.

WITHOUT WARRANY

BIT 5.2 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

BIT 5.3 M Check that the material supplied by the Design-Builder is sampled and tested as required and batch numbers are recorded as specified in the Contract Documents.

BIT 5.4 M Check that cracks as specified in the Contract Documents are routed to the specified width and depth and that the rout is centered on the crack.

BIT 5.5 M Check that all routed and unrouted cracks are blown clean and dry using hot compressed air lance before sealing commences.

BIT 5.6 Check that dust and debris from exposed work, and from routing and sealing operations, does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential / commercial / institutional properties, and is not entering a watercourse or Environmentally Sensitive Area.

BIT 5.7 Check that sealing material is heated within the manufacturers recommended range and is being continuously agitated.

BIT 5.8 Check that sealing material is applied immediately after cleaning and drying.

BIT 5.9 Check that cracks are filled with sealant as specified in the Contract Documents and that no spillage occurs.

BIT 5.10 Check that debris, including excess sealing material, is removed from routed area and adjacent pavement.

211 Design-Build Administration Manual January 2014

BIT 5.11 Check that completed cracks are dusted with a suitable bond breaker before exposing to traffic.

LEVEL OF INSPECTION – C1/E2 with warranty – B1/C2 without warranty

212 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 6

TACK COAT

Task # Activity

BIT 6.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

BIT 6.2 Check that existing pavement is dry and clean before applying tack coat.

BIT 6.3 M Check that proper rate of application and coverage is used if specified in Contract Documents.

BIT 6.4 M Check that tack coat has cured to the desired level before placing hot mix pavement.

BIT 6.5 M Check that traffic is not allowed on the tack coated area before paving.

BIT 6.6 M Check that all required samples are taken and delivered as specified in the Contract Documents.

LEVEL OF INSPECTION – B1/D2

213 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 7

PAVEMENT MARKING

Task # Activity

BIT 7.1 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. Check that the material supplied by the Design-Builder is sampled and tested as specified in the Contract Documents.

BIT 7.2 Check that air temperature, pavement temperature and surface condition requirements are met.

BIT 7.3 Check that the locations of the markings applied are as specified in the Contract Documents.

BIT 7.4 Check that the surface is dry and free of loose and/or foreign material.

BIT 7.5 Temporary and Permanent Tape (i) Check for correct spacing and application; (ii) Check that only butt splices are used; (iii) Check that specified tamping has been carried out; (iv) Check that material is stored as specified.

BIT 7.6 M Pavement Marking (i) Check that zone painting is completed on any temporary driving surface prior to opening to traffic; (ii) Check zone painting has a well defined edge, free from waviness, uniformly dimensioned and shaded with no splatter or overspray; (iii) Check for correct material application temperature; (iv) Check that glass beads are applied uniformly prior to the paint drying; (v) Check that the pavement markings and materialsare applied as specified in the Contract Documents; (vi) Check that the glass beads are applied as specified in the Contract Documents; (vii) Conduct a bond/adhesion test on durable marking materials (for thermoplastic and field reacted polymeric: (viii) A monitoring frequency of a minimum of 25%, but not limited to, is required to be performed and recorded to determine that the Design-Builder has properly applied sight distance requirements as specified.

LEVEL OF INSPECTION – B1/D2

214 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 8

SURFACE TREATMENT

Task # Activity

WITH WARRANTY

BIT 8.1 W Document non-compliance with the Contract Document requirements.

WITHOUT WARRANTY

BIT 8.2 Check the condition of the grade for compaction, profile, potholes, grade failure repair and brooming, etc.

BIT 8.3 M Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. Check that material supplied by the Design-Builder is sampled and tested as specified in the Contract Documents.

BIT 8.4 Check that quality and aggregate gradation tests have been done in accordance with the current Ministry test method.

BIT 8.5 Check the adequacy of the following: 1) Binder and aggregate distribution and application 2) Width of application 3) Emulsion temperature 4) Air temperature 5) Centreline and transverse joints 6) Rolling operation 7) Brooming off of excess aggregates

BIT 8.6 Check that material is confined to the area specified in the Contract Documents.

BIT 8.7 M Check that all test results are received and price adjustments are calculated and applied as applicable.

LEVEL OF INSPECTION – D1/E2 – With warranty – B1/C2– Without warranty

215 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 9

HOT–IN–PLACE RECYCLING (HIR)

Task # Activity

BIT 9.1 M Check that the Mix Design and material submissions meet the requirements as specified in the Contract Documents. Check that the material supplied by the Design-Builder is sampled and tested as specified in the Contract Documents.

BIT 9.2 M Check the pavement is prepared as specified in the Contract Documents.

BIT 9.3 Check that HIR scarification depth tests are carried out and are acceptable as specified in the Contract Documents.

BIT 9.4 (i) Check that there is no direct flame in contact with the pavement; (ii) Check that there is no charring of the pavement occurring; (iii) Check that the fine aggregate added is dry and uniform; (iv) Check that there is no excess smoke; (v) Check that the mix temperature meets the requirements as specified in the Contract Documents; (vi) Visually inspect the mat appearance for uniform mixing, no segregation flushing or lumps; (vii) Check that longitudinal and transverse joints are constructed as specified in the Contract Documents; (viii) Check the ring test to determine depth of HIR. (ix) Check for white aggregate (broken stones) produced by scarification. (Shows proof of insufficient heating which results in cold milling.)

BIT 9.5 M Check that HIR is sampled and tested as specified in the Contract Documents.

BIT 9.6 Check that the smoke emission level does not endanger traffic safety.

LEVEL OF INSPECTION – A2

216 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 10

COLD–IN–PLACE RECYCLING (CIR)

Task # Activity

BIT 10.1 M Check that the Mix Design and material submissions meet the requirements specified in the Contract Documents.

BIT 10.2 M Check that all the delivered material is supplied from the approved list submitted by the Design-Builder at the commencement of the contract.

BIT 10.3 Check that pavement is prepared as specified in the Contract Documents.

BIT 10.4 Check that the ambient temperature meets the requirements as specified in the Contract Documents.

BIT 10.5 Check that the pavement is reclaimed, to full design width, as specified in the Contract Documents.

BIT 10.6 Check that the CIR material has been mixed properly, contains no oversize particles and that the processed material is not slumping.

BIT 10.7 Check that compaction is carried out as specified in the Contract Documents.

BIT 10.8 M Check that CIR material is sampled and tested as specified in the Contract Documents.

BIT 10.9 M Check that traffic is restricted as specified in the Contract Documents.

BIT 10.10 M Check that CIR pavement meets requirements as specified in the Contract Documents prior to placement of the wearing surface.

BIT 10.11 Check that the wearing surface is placed within the time restriction specified in the Contract Documents.

LEVEL OF INSPECTION – A-2

217 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 11

IN–PLACE FULL DEPTH RECLAMATION OF BITUMINOUS PAVEMENT AND UNDERLYING GRANULAR

Task # Activity

BIT 11.1 M Check that the in–place materials are processed to the depths, widths and gradation as specified in the Contract Documents.

BIT 11.2 Check that the composition of the blended material is as specified in the Contract Documents.

BIT 11.3 Check that oversized material has been removed or reprocessed as specified in the Contract Documents.

BIT 11.4 M Check that operational constraints are carried out as specified in the Contract Documents.

BIT 11.5 M Check that surface shaping and compaction is as specified in the Contract Documents.

LEVEL OF INSPECTION – B2/D2

218 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 12

SURFACE SMOOTHNESS MEASUREMENTS USING AN INERTIAL PROFILER

Task # Activity

BIT 13.1 Prepare a sublot sketch that identifies all of the sublots which must be measured and those sublots which are exempted along with stations. Check that the sublots are consecutively numbered, that no two sublots have the same sublot number and that the proposed reference lines and offsets are indicated on the sketch. Provide the sketch to the Design- Builder for review at the pre-pave meeting or within 5 Business Days after the meeting. Receive and review any proposed sublot exemptions as requested by the Design-Builder prior to the start of surface course paving and provide a response to the Design-Builder.

BIT 13.2 Submit a request to the Owner to provide an inertial profiler for QA/Referee acceptance testing or to re-measure a repaired sublot. Such request is to be prepared within 1 Business Day after the CA receives the Design-Builder’s written notice indicating that the Design-Builder has clearly marked out the sublots and removed any debris from the pavement the Design-Builder Administrator shall coordinate the approved high speed profiler firm (Profiler Operators) with a qualified Profile Measurement Devices (PMD) to complete smoothness measurements.

BIT 13.3 Obtain from the profiler operator a copy of the correlation certificate. Record the make and serial number of the inertial profiler.

BIT 13.4 Prior to the commencement of any surface smoothness measurements each day, observe while the profiler operator is doing the “block test”, the “bounce test”, and the distance calibration. All such checks will be done in accordance with the instructions of the manufacturer of the inertial profiler or LS-296. Provide a copy of the sublot sketch to the profiler operator and identify the sublots that are intended for measurement that day including respective stations and exempted sublots. Agree to and record the reference line(s) and offsets that the profiler should use.

BIT 13.5 When the profiler operator is conducting the measurements check that the measurements are being done in accordance with the requirements stated in the Contract Documents. In the event the profiler operator deems that the results for one or more sublots within a particular run are invalid, review operator’s reasoning and decide on whether or not to allow the profiler to repeat that run. Keep a record of the discussions.

219 Design-Build Administration Manual January 2014

BIT 13.6 Make sure that the profiler operator has provided one electronic copy of the raw data files on CD using proper file names and format stated in LS- 296 including a list of “lead-ins” and “lead-outs” for each file.

BIT 13.7 Make sure that, within 4 Business Days after each set of measurements, the profiler operator has provided all the electronic filtered files, the Microsoft Excel 2003 spreadsheet file(s) containing all IRI measurements and the locations and values of all localized roughness in both wheel paths, for each run of each sublot. Calculate the adjustment factors for each sublot based on the data provided by the inertial profiler.

BIT 13.8A Within 5 Business Days after each set of measurements: Provide to the Bituminous Section, the Regional Quality Assurance Section, and the Design-Builder one CD containing: a) all of the unfiltered electronic data files for the measurements that were generated by the inertial profiler for each profile run; b) a BIT 13.7. Make sure that, within four (4) Business Days after each set of inertial profiler measurements have been completed for sublots designated by the CA, the Profiler Operator shall provide copies of the following to the CA:

a) All of the unfiltered data files that are generated by the Inertial Profiler in ppf or erd format that can be read by ®ProVAL on CD’s or sent electronically by E-mail for use by IBM-compatible PC’s; b) All of the filtered data files generated by ProVAL in ppf or erd format on CD’s or sent electronically by E-mail for use by IBM-compatible PC’s;A hard copy or electronic summary of the longitudinal reference lines and offsets as well as the “lead-in” and “lead-out” distances that were used for each profile run;c) Microsoft Excel 2003 spreadsheet file(s) containing all IRI measurements, the resulting adjustment factors, and the locations and values of all localized roughness in both wheel paths, for each run of each sublot, in accordance with LS-296; d) areas of special conditions, such as superelevations or curves, any additional information such as joints or major intersections, and any areas that are being measured but will be exempt from surface smoothness- related price reductions/repairs. c) A hard copy or electronic summary of the “lead-in” distances that the inertial profiler required, prior to the start of the first sublot being measured in each run; d) An electronic copy of the ProVAL reports showing all applicable IRI and the locations and magnitudes of all localized roughness determinations for each profile run that was carried out; e) Microsoft Excel spreadsheet files of the summaries of all IRI measurements for both wheel paths as well as the locations and magnitudes of all localized roughness for every run of each sublot,

220 Design-Build Administration Manual January 2014

measured on the Contract, using the methods given in LS-296. The information shall be reported on the Excel form provided by MTO. f) All test results shall be accompanied by a transmittal letter to the CA, under the signature of the Vendors Project Manager for this assignment, verifying the limits measured and indicating that the data analysis have been verified and the submitted results are in compliance with the requirements of the RFT, LS-296, and the current version of the specification.

BIT 13.8B Within 4 Business Days after each set of measurements forward all information to the Design-Builder, MTO Quality Assurance and Bituminous Section.

Provide to the Bituminous Section and the Regional Quality Assurance Section: a) One CD containing all of the filtered electronic data files; b) A written confirmation indicating that the inertial profiler has completed the measurements and all the required electronic data and spreadsheets have been submitted to the CA.

BIT 13.9 Arrange to have any repaired sublots re-measured by a QA inertial profiler, obtain the data, calculate the pay factors, fill out the Excel spreadsheets, and submit the files to the Bituminous Section, Regional Quality Assurance Section, and the Design-Builder.

BIT 13.10 Calculate pay factors and determine the overall price adjustment for the surface course.

BIT 13.11 Produce a written report containing a summary of the QA/Referee data with reasons for any areas which were exempt from measurements and/or penalties, a summary and all decisions regarding rejectablesublots and localized roughness and a summary of the tolerance measurements which were carried out in areas that were either not measured by PMD or were measured by PMD but were exempt from penalties.

LEVEL OF INSPECTION – C2

221 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 13

EXPANDED ASPHALT STABILIZATION

Task # Activity

BIT 14.1 M Check that the Mix Design and material submissions meet the requirements as specified in the Contract Documents. Check that all the delivered material is supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

BIT 14.2 Check that oversize material has been removed or reprocessed as specified in the Contract Documents.

BIT 14.3 M Check that an acceptable trial section is completed as specified in the Contract Documents.

BIT 14.4 Monitor and record materials including any corrective aggregate incorporated in the mix.

BIT 14.5 Check that the system of nozzles provides a uniform application of expanded asphalt.

BIT 14.6 M Check that the material is sampled and tested as specified in the Contract Documents.

BIT 14.7 Check and record thickness measurements at the frequencies specified in the Contract Documents.

BIT 14.8 Check that compaction is in accordance with the requirements of the Contract Documents.

BIT 14.9 Check that the finished surface has a uniform texture, is free of surface dust defects and meets the profile and cross-section specified in the Contract Documents.

BIT 14.10 M Check that the material meets the requirements (dry, wet and tensile strength ratio, thickness, compaction, surface tolerance) specified in the Contract Documents prior to placing the wearing surface.

BIT 14.11 M Check that the reclaiming and / or stabilizing is completed across the full width of pavement prior to the closing down of operations each day.

222 Design-Build Administration Manual January 2014

BIT 14.12 M Check all vertical clearances from top of asphalt to the bottom of beam at the edge of all lanes.

BIT 14.13 M Check and record applied rate of expanded asphalt to determine that the design rate is met at the end of each day’s operation.

LEVEL OF INSPECTION – A1

223 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 14

OPEN GRADED DRAINAGE LAYER

Task # Activity

BIT 15.1 M Check that material submissions meet the requirements specified in the Contract Documents. Check that equipment to be used meets the requirements specified in the Contract Documents.

BIT 15.2 Check that environmental conditions are met as specified in the Contract Documents.

BIT 15.3 M Check that the drainage system is operational prior to placing the OGDL.

BIT 15.4 M Check that an acceptable trial section is completed as specified in the Contract Documents.

BIT 15.5 M Check that the material is sampled and tested as specified in the Contract Documents.

BIT 15.6 Check that that Portland cement treated OGDL is cured as specified in the Contract Documents.

BIT 15.7 Check that traffic is restricted as specified in the Contract Documents.

BIT 15.8 Check that the wearing course is placed over the OGDL within the time restrictions specified in the Contract Documents.

LEVEL OF INSPECTION – B1/C2

224 Design-Build Administration Manual January 2014

BITUMINOUS – TASK BIT 15

FULL DEPTH ASPHALT CRACK REPAIR

Task # Activity

BIT 16.1 Check that cracks, as specified in the Contract Documents, are removed to the specified width and depth and are centered on the crack.

BIT 16.2 M Check the condition of the underlying granular material to verify that it is shaped to the proper cross fall, compacted, unfrozen, cleaned of all loose, broken and foreign materials, dry and free of standing water.

BIT 16.3 Check that hot mix placed meets the requirements of the Contract Documents.

BIT 16.4 M Check for proper construction including tack coating of all vertical faces, placement of hot mix and compaction. Confirm that the lift thickness of mix placed does not exceed the maximum allowable lift thickness as stated in the Contract Documents.

BIT 16.5 Check that the ambient temperature at the surface of the road is above the minimum specified in the Contract Documents to permit paving.

BIT 16.6 Check that the temperature of the mix delivered to the site does not exceed the maximum discharge temperature allowed. Confirm the temperature of the mix does not fall below the minimum temperature allowable for placement.

BIT 16.7 M Check and witness that all samples required in the Contract Documents, are taken at correct (random) locations and tonnages. Confirm proper reinstatement of sample locations (plates and cores) on a daily basis.

BIT 16.8 Check that equipment does not damage areas beyond the shoulder.

BIT 16.9 Check that debris, including excess material, is removed from the repair area and adjacent pavement.

LEVEL OF INSPECTION – A2

225 Design-Build Administration Manual January 2014

ELECTRICAL AND ATMS – TASK E/ATMS 1

ELECTRICAL AND ATMS CHAMBERS

Task # Activity

E/ATMS 1.1 M Check all delivered material to verify that it is in accordance with the Contract Documents. Record all non-conformance items and provide recommendations.

E/ATMS 1.2 Check that the type, alignment, offset, station, elevation relative to final grade, and depth of maintenance holes and hand holes conforms to the Contract Document requirements.

E/ATMS 1.3 M Check that the number of concrete adjustment units conforms to Contract Document requirements.

E/ATMS 1.4 Check that the correct number of sleeves and openings are installed. Check for correct positioning, alignment and installation of: ladder rungs, pulling irons, duct sleeves, drainage pipe, and frames and covers.

E/ATMS 1.5 M Check that drainage installation has been completed as specified in the Contract Documents.

E/ATMS 1.6 M Check that the backfill materials are as specified in the Contract Documents and are compacted to the target density.

E/ATMS 1.7 Check that rigid ducts entering maintenance holes are installed with standard end bells placed flush with the face of the inside wall of the unit.

E/ATMS 1.8 Check that ATMS communications ducts entering chambers are installed such that they extend 150mm beyond the face of the inside wall of the unit.

E/ATMS 1.9 M Check that frames and covers are connected to the system ground.

E/ATMS 1.10 M Check that frames and covers are free of debris and that drain openings are clear.

E/ATMS 1.11 M Obtain GPS readings for chambers.

LEVEL OF INSPECTION – C1 /D2

226 Design-Build Administration Manual January 2014

ELECTRICAL AND ATMS – TASK E/ATMS 2

UNDERGROUND DUCTS

Task # Activity

E/ATMS 2.1 M Check all delivered material to verify that it is in accordance with the Contract Documents. Record all non-conformance items and provide recommendations.

E/ATMS 2.2 M Check that excavation for the duct and/or duct bank conforms to the specified dimensions.

E/ATMS 2.3 Check that the depth of ducts conforms to Contract Document requirements.

E/ATMS 2.4 M Check that wobble joints are installed as specified in the Contract Documents.

E/ATMS 2.5 Check that the correct size, type, colour and number of ducts are being installed.

E/ATMS 2.6 M Check that backfill materials are as specified in the Contract Documents and are compacted to the target density.

E/ATMS 2.7 Check that surface mounted duct has been installed in accordance with the manufacturer’s recommendations and the contract drawings

E/ATMS 2.8 M Where Electrical Non-Metallic Tubing (ENT) is used; check that it has been installed in accordance with the manufacturer’s recommendations.

E/ATMS 2.9 Check that marker tape and cable bricks have been installed as specified in the Contract Documents.

E/ATMS 2.10 M Check that ducts are free of debris.

227 Design-Build Administration Manual January 2014

E/ATMS 2.11 M Check that all unused ducts are plugged with plastic plugs and have fishwire installed.

E/ATMS 2.12 M Check that ducts for underpass luminaires consist of non- metallic liquid tight conduit and connectors.

LEVEL OF INSPECTION – A1 for communication ducts, C1/D2 for all other ducts

228 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 10

POLE FOUNDATIONS AND POLE ERECTION

Task # Activity

E 10.1 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

E 10.2 Check that the Design-Builder augers holes to the specified dimensions for poles and footings.

E 10.3 M Check that the foundations are constructed according to the Contract Documents.

E 10.4 Visually check all poles for dents, cracks, scratches, paint chipping, and any other obvious imperfections.

E 10.5 Check that the Design-Builder properly stores, erects and supports the poles in accordance with the manufacturer’s recommendations and the Contract Document constraints.

E 10.6 Check that the pole orientation and handhole orientation are as specified in the Contract Documents.

E 10.7 M Check that the orientation and elevation of each and every frangible base is as specified in the Contract Documents. Perform 100% inspection of frangible bases.

E 10.8 M Check that pole foundations and poles are installed to the correct elevation, station, offset, and vertically aligned, as specified in the Contract Documents.

E 10.9 M Check that the local grading around the pole foundations is completed as specified in the Contract Documents.

E 10.10 M Check that the distance between the pole bases and the pole footings are according to the Contract Documents.

229 Design-Build Administration Manual January 2014

E 10.11 M Check that all formwork is removed.

E 10.12 M Obtain GPS readings for all lighting poles.

LEVEL OF INSPECTION – C1 / D2

230 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 11

GROUNDING

Task # Activity

E 11.1 M Check all delivered material to verify that it is in accordance with the Contract Documents. Record all non-conformance items and provide recommendations.

E 11.2 Check that insulation ground wire is of correct colour and type, as specified in the Contract Documents.

E 11.3 M Check that the specified ground electrodes are used and that the type, quantity, dimensions, and locations of ground electrodes are according to the Contract Documents.

E 11.4 M Check that all ground connectors are Canadian Standards Association (CSA) approved, and are of the size and type specified in the Contract Documents.

E 11.5 M Check that all inaccessible ground connections are installed as specified in the Contract Documents.

E 11.6 M Check that the Design-Builder conducts the resistance to ground tests. Check that the Design-Builder ensures that the grounding system complies with the requirements of the Electrical Safety Authority (ESA) and is in conformance with the Contract Documents.

E 11.7 M Check that the traffic signal grounding system is in conformance with the Contract Documents.

E 11.8 M Check that all metal components throughout the contract are grounded according to the Ontario Electrical Safety Code.

E 11.9 Check that the system ground is continuous throughout.

E 11.10 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – D2

231 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 12

CABLE INSTALLATION

Task # Activity

E 12.1 M Check all delivered material to verify that it is in accordance with the Contract Documents. Record all non-conformance items and provide recommendations.

E 12.2 M Check that the size, type and colour of cables are as specified in the Contract Documents.

E 12.3 M Check that all communication cable on-reel tests have been completed successfully, immediately following delivery and prior to any communication cable installation work.

E 12.4 M Check that the Design-Builder pulls cables through the ducts without exceeding the maximum pulling tension recommended by the manufacturer and without underground splices. Check that sufficient cable lubricant is used during the pulling operation.

E 12.5 Where direct buried cable is installed, check that marker tape and cable bricks are installed as specified in the Contract Documents.

E 12.6 M For Low Voltage Systems and Extra Low Voltage Systems, check that the Design-Builder performs continuity and resistance to ground tests, as specified in the Contract Documents.

E 12.7 Check that all splices and terminations conform as specified in the Contract Documents.

E 12.8 M Check that all continuity and attenuation tests on all connectorized links are as specified in the Contract Documents.

E 12.9 M For High Voltage Systems, check that the Design-Builder performs all testing required by the local authorities and all tests specified in the Contract Documents.

E 12.10 Check that all ducts terminating in traffic signal control cabinets, power supply cabinets, and/or distribution assemblies with wiring installed are sealed.

232 Design-Build Administration Manual January 2014

E 12.11 Check that all unused ducts are plugged with plastic plugs and have fishwire installed.

E 12.12 M Check that coils and slack cable is provided as specified in the Contract Documents.

LEVEL OF INSPECTION – C1/C2

233 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 13

LUMINAIRES

Task # Activity

E 13.1 Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. ` E 13.2 Check that the luminaires delivered have the correct lamp, socket position, photometrics, ballast, and that they are dated.

E 13.3 M Check that luminaires are installed and aligned correctly.

E 13.4 M Check that luminaire shields, refractors, and reflectors are installed and aligned correctly.

E 13.5 M Check that all luminaires and associated hardware and materials are visually checked for cracks, dents and other damage.

E 13.6 M Once all of the luminaires have been installed, perform an aerial inspection on a minimum of 5 percent of the conventional (non-high mast) luminaires.

E 13.7 M Check that all luminaires operate properly when the system is energized.

E 13.8 M Check that the luminaire “burn-in” period meets requirements as specified in the Contract Documents.

E 13.9 Check that fuses are of the correct amperage and type.

LEVEL OF INSPECTION – E2

234 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 14

POWER SUPPLY EQUIPMENT

Task # Activity

E 14.1 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

E 14.2 M Check that the Design-Builder has obtained the Electrical Safety Authority (ESA) of approval prior to installation of the power supply.

E 14.3 Check the equipment for obvious defects or damage.

E 14.4 Check that the equipment is as specified, paying special attention to the ratings for voltage and amperage.

E 14.5 M Check that the specified grounding is completed

E 14.6 Where applicable, check that the power supply is mounted at the correct height, using the specified brackets.

E 14.7 M Check that the Design-Builder has tested the cables and the grounding system in accordance with the Contract Documents.

E 14.8 M Check that the photoelectric controllers are installed and oriented correctly.

E 14.9 M Check that the component layout conforms to the approved shop drawings.

E 14.10 M Check that the Design-Builder has obtained a connection authorization from the Electrical Safety Authority (ESA) prior to energization.

E 14.11 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

E 14.12 M Obtain GPS readings for power supply cabinets and distribution assemblies.

LEVEL OF INSPECTION – E2

235 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 15

TRAFFIC SIGNAL EQUIPMENT

Task # Activity

E 15.1 Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

E 15.2 M Receive manufacturer’s certificate for pre-installation testing of equipment.

E 15.3 M Check that the PH-M-125 (legal approval form) is received prior to signal equipment (both permanent and temporary) being activated.

E 15.4 Check that the signal heads and brackets are the correct size and type.

E 15.5 Check that the lamps or the LED modules are the correct wattage and are installed correctly.

E 15.6 Check the orientation and mounting heights of traffic signal heads.

E 15.7 Check that test results for loops conform to the Contract Document requirements.

E 15.8 Check that all actuation devices operate properly.

E 15.9 M Once all of the signal displays have been installed, perform an aerial inspection on a minimum of 2 non-pedestrian signal heads per intersection.

E 15.10 M Check that the Design-Builder has tested all traffic signal control equipment, demonstrated that it is fully operational and that it conforms to the requirements as specified in the Contract Documents.

E 15.11 M Check that traffic signal operation conforms to the timing plan and operational parameters set by the Regional Traffic Section.

E 15.12 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – E2

236 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E 16

TRAFFIC ACTUATION AND DETECTION EQUIPMENT

Task # Activity

E 16.1 M Check all delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

E 16.2 M Check that the equipment has passed pre-installation testing prior to any installation work.

E 16.3 Check that sealant is the approved type and rated for the temperature at which time the installation is taking place.

E 16.4 Check that loop layout and installation are in conformance with the Contract Documents. Check that the loops are installed with the size, winding direction, number of turns and type of cable specified.

E 16.5 M Check that the Design-Builder has accurately laid out the loops. The position (centred within the lane), dimensions and spacing to upstream or downstream loops are critical. Check that the Design- Builder applies special treatment (neoprene tubing) to sawcut slots that cross pavement irregularities and that the corners have been rounded as detailed in the Contract Documents.

E 16.6 Check that the loop cable end at the splice point which progresses clockwise is clearly identified, such as being marked with multiple bands of electrical vinyl tape which also indicate the loop number (loop number four (4) requires four (4) bands of tape, etc.).

E 16.7 Check that the saw cut slot depth is as required and has been cleaned and thoroughly dried as specified in the Contract Documents.

E 16.8 Check that the black conductor of the extra low voltage cable is consistently connected to the clockwise winding of the loop lead cable.

E 16.9 Check backing rods are the correct length, diameter and are spaced as required in the Contract Documents.

E 16.10 For Traffic Counting Stations, check that post, accessories (reflector / chain etc.) and handhole sizes, type and orientation is as specified in the Contract Documents.

237 Design-Build Administration Manual January 2014

E 16.11 Check that the metallic shield of extra-low voltage cables are cut off cleanly and left unconnected in the resin loop splice.

E 16.12 M Verify all loop splices and determine that they are encased in a resin splice with the splices positioned to obtain a minimum coverage of 6mm of resin around each splice.

E 16.13 Check that initially, the sensitivity switches of amplifiers are set to Level 4. Fine-tuning of the sensitivity switches will be adjusted during the physical car counting process.

E 16.14 Check that the High (FH) Low (FL) frequency switches of amplifiers alternate on each channel.

E 16.15 M Check that the Design-Builder tests the loop with a “megger” and with an inductance meter and submits the measured values for verification.

E 16.16 M Verify that the loop is operating as specified in the Contract Documents.

E 16.17 M Check that the Certificate of Conformance (if required) is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – C1/C2

238 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E17

HIGH MAST LIGHTING

Task # Activity

E 17.1 Check all the delivered material to verify that it is being supplied from the approved list that was submitted by the Design-Builder at the commencement of the contract.

E 17.2 M Check that the supply erection drawings and procedures have been received prior to the commencement of the assembly of any high mast poles.

E 17.3 M Check that the high mast equipment training certificates for the Design-Builder’s employees have been received prior to the commencement of construction of any high mast poles.

E 17.4 M Check that the shop drawings (poles, anchorage assemblies and raising/lowering equipment) have been received prior to the commencement of any high mast poles.

E 17.5 M Check that the distance from the top of the high mast pole footing to the bottom of the bottom levelling nuts is according to the Contract Documents.

E 17.6 Inspect the high mast lighting luminaires in accordance with Task E6.

E 17.7 M Check that all high mast lighting equipment and materials are in place and are visually checked for cracks, dents and other damage.

E 17.8 M Check that the Design-Builder has tested all high mast lighting equipment, particularly the raising and lowering equipment, demonstrated that it is fully operational, and that it conforms to the requirements as specified in the Contract Documents.

E 17.9 M Check that the certificate of conformance has been received, and any required documentation concerning the galvanizing and paint coating of the high mast lighting equipment.

239 Design-Build Administration Manual January 2014

E 17.10 Check that the fuses are of the correct amperage and type.

E 17.11 M Check that shielding is correctly in place and providing required light transmission cut off prior to the burn-in test.

LEVEL OF INSPECTION – F2

240 Design-Build Administration Manual January 2014

ELECTRICAL – TASK E18

SIGNAL ACTIVATION (TEMPORARY AND PERMANEMT INSTALLATION)

Task # Activity

E 18.1 M Check the Design-Builder has an approved signed copy of the applicable PHM 125 documents.

E 18.2 Check offset from E/P or back of curb to front face of pole base is as per Contract Documents .

E 18.3 Check grading requirements are as per Ministry related documents.

E 18.4 Check that pedestrian push buttons are accessible and approaches are level.

E 18.5 Check that pole bases (if adjusted during the construction) that the arm lengths are per Contract Document requirements.

E18.6 Primary Heads must be positioned in the centre of the through lane.

E 18.7 Check if heads are obstructed by any site objects. If any concerns contact the designer for recommendation.

E 18.8 Check appropriate signage has been installed and is per Contract Documents.

E 18.9 Check that Pre-Marking of the Stop Bars, Crosswalks and dropped curbs are in the correct locations (per PHM 125 and Ministry Standards).

E 18.10 For temporary installations – Check site specific conditions at the time of installation math PHM 125 drawing.

E 18.11 For temporary installations – Check TCB is placed as per the PHM 125 and that it meets Ministry standards.

E 18.12 M Check that the mandatory pre-activation meeting is held in advance of signal activation (if applicable) and all required personnel have been invited.

E 18.13 Check if the pedestrian push buttons are being activated one at a time to determine that they are functioning properly.

E 18.14 M Confirm the phases and turning movements to determine adequate time is being allotted to each phase as intended.

241 Design-Build Administration Manual January 2014

DAY OF ACTIVATION

E 18.15 Check that all applicable people are present (which includes Police, Traffic Section representative, Prime Design-Builder representative, Electrical Co-ordinator, CSA and CA Electrical Inspector)

E 18.16 Check if the corners of the loops are marked with non-permanent paint on top lift of pavement if cut into the binder.

E 18.17 M Police must control traffic through the intersection until signals are activated, including during the flash out of the signals,

E 1818 Check if the pavement markings are being installed as per Contract Document requirements.

E 18.19 Check if pedestrian push buttons are being activated one at a time to determine that they are functioning properly.

E 18.20 M Confirm the phases and turning movements to determine adequate time is being allotted to each phase as intended (this should be at the pre-activation meeting).

E 18.21 M Record any requests for changes to timing and / or any other adjustment made. (This should be at the pre-activation meeting).

LEVEL OF INSPECTION – A2 / A1

242 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 20

ATMS ELECTRICAL CABLE INSTALLATION

Task # Activity

ATMS 20.1 M Check all delivered material to verify that it is being supplied from the approved material selection approval (MSA) list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 20.2 M Check that the size, type and colour of cables are as specified in the Contract Documents.

ATMS 20.3 M Check that the Design-Builder pulls cables through the ducts without exceeding the maximum pulling tension recommended by the manufacturer and without underground splices. Check that sufficient cable lubricant is used during the pulling operation.

ATMS 20.4 M For Low Voltage Systems and Extra Low Voltage Systems, check that the Design-Builder performs continuity and resistance to ground tests, as specified in the Contract Documents.

ATMS 20.5 Check that all splices and terminations conform as specified in the Contract Documents.

ATMS 20.6 Check that all ducts terminating in ATMS cabinets, and/or power supply cabinets with wiring installed are sealed.

ATMS 20.7 Check that all unused ducts are plugged with plastic plugs and have fishwire installed.

ATMS 20.8 M Check that coils and slack cable is provided as specified in the Contract Documents.

LEVEL OF INSPECTION – C1/C2

243 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 21

GROUNDING

Task # Activity

ATMS 21.1 M Check all delivered material to verify that it is in accordance with the Contract Documents. Record all non-conformance items and provide recommendations. ATMS 21.2 Check that insulation ground wire is of correct colour and type, as specified in the Contract Documents.

ATMS 21.3 M Check that the specified ground electrodes are used and that the type, quantity, dimensions, and locations of ground electrodes are according to the Contract Documents.

ATMS 21.4 M Check that all ground connectors are Canadian Standards Association (CSA) approved, and are of the size and type specified in the Contract Documents.

ATMS 21.5 M Check that all inaccessible ground connections are installed as specified in the Contract Documents.

ATMS 21.6 M Check that the Design-Builder conducts the resistance to ground tests. Check that the Design-Builder determines that the grounding system complies with the requirements of the Electrical Safety Authority (ESA) and is in conformance with the Contract Documents.

ATMS 21.7 M Check that all metal components throughout the contract are grounded according to the Ontario Electrical Safety Code.

ATMS 21.8 Check that the system ground is continuous throughout.

ATMS 21.9 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

LEVEL OF INSPECTION – D2

244 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 22

POWER SUPPLY EQUIPMENT

Task # Activity

ATMS 22.1 M Check all delivered material to verify that it is being supplied from the approved material selection approval (MSA) list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations. ATMS 22.2 M Check that the Design-Builder has obtained the Electrical Safety Authority (ESA) label of approval prior to installation of the power supply.

ATMS 22.3 Check the equipment for obvious defects or damage.

ATMS 22.4 Check that the equipment is as specified, paying special attention to the ratings for voltage and amperage.

ATMS 22.5 M Check that the specified grounding and/or bonding is completed.

ATMS 22.6 Check that the power supply is mounted at the correct height, using the specified brackets.

ATMS 22.7 M Check that the Design-Builder has tested the cables and the grounding system in accordance with the Contract Documents.

ATMS 22.8 M Check that the Certificate of Conformance is supplied and reviewed as per the time requirements of the Contract Documents.

ATMS 22.9 M Obtain GPS readings for ATMS power supply equipment.

LEVEL OF INSPECTION – E2

245 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 23

CLOSED CIRCUIT TELEVISION (CCTV) POLESAND MAINTENANCE SITES

Task # Activity

ATMS 23.1 M Check all delivered material to verify that it is being supplied from the approved material selection approval (MSA) list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 23.2 Check that the Design-Builder augers holes to the specified dimensions for poles and foundations

ATMS 23.3 M Check that the foundations are constructed according to the Contract Documents.

ATMS 23.4 Visually check all poles for dents, cracks, scratches, and any other obvious imperfections.

ATMS 23.5 Check that the Design-Builder properly stores, erects and supports the poles in accordance with the manufacturer’s recommendations and the contract constraints.

ATMS 23.6 Check that the pole orientation and handhole orientation are as specified in the Contract Documents.

ATMS 23.7 M Check that pole foundations and poles are installed to the correct elevation, station, offset, and vertically aligned, as specified in the Contract Documents.

ATMS 23.8 M Check that the local grading around the pole foundations is completed as specified in the Contract Documents.

ATMS 23.9 Check that the opening for the maintenance site is not less than 5.0 m and has the proper taper back to the edge of pavement.

ATMS 23.10 M Check the installation of the subdrain as specified in the Contract Documents.

ATMS 23.11 M Check that the Design-Builder compacts the fill materials of the maintenance site to the target density.

ATMS 23.12 M Obtain GPS readings for camera poles.

246 Design-Build Administration Manual January 2014

LEVEL OF INSPECTION – C1/D2

247 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 24

COMMUNICATION CABLE INSTALLATION

Task # Activity

ATMS 24.1 M Check all delivered material to verify that it is being supplied from the approved material selection approval (MSA) list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 24.2 M Check that the size, type and colour of cables are as specified in the Contract Documents.

ATMS 24.3 M Check that all communication cable on-reel tests have been completed successfully, immediately following delivery and prior to any communication cable installation work.

ATMS 24.4 Check that a generous amount of cable lubricant is applied during the installation.

ATMS 24.5 Check that communication cable is installed according to all the constraints of the Contract Documents and that none of the dynamic characteristics of the cable are exceeded to prevent damage.

ATMS 24.6 M Check that all continuity and attenuation tests on all connectorized links as per the Proof of Performance (POP) and the Contract Documents are performed successfully.

ATMS 24.7 Check that all unused ducts are plugged with plastic plugs and have fishwire installed. Check that used communication ducts are plugged with duct sealing compound.

ATMS 24.8 M Check that coils and slack cable in maintenance chambers are provided as specified in the Contract Documents (typically at bridge crossings, and upstream and downstream of communication pedestals).

ATMS 24.9 M Check that all cables are labelled according to the Contract Documents.

LEVEL OF INSPECTION – C1/D2

248 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 25

DATA TRANSMISSION EQUIPMENT INSTALLATION

Task # Activity

ATMS 25.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 25.2 M Check that the equipment has passed Pre–Installation Testing (PIT) as required prior to any installation work.

ATMS 25.3 Check that the field and traffic operations centre (TOC) equipment is installed and secured in the cabinets’ designated reserved space as per the contract drawings.

ATMS 25.4 Check that all cables are neatly trained together within the cabinet when routed along the same path and supported along the rails of the equipment rack and that no maximum bending radii have been exceeded.

ATMS 25.5 Check that the equipment is connected to the proper power distribution assembly (PDA) receptacle reserved for the communication equipment.

ATMS 25.6 Check that the proper data terminal equipment/data communications equipment (DTE/DCE) to DTE/DCE data interface cable is installed to match the type of controller equipment.

ATMS 25.7 M Check that all data interface equipment has successfully passed Proof of Performance (POP) testing prior to commencing data system line-up acceptance testing (DSLAT) testing and that DSLAT testing is completed successfully.

ATMS 25.8 M Check that the data communications documentation being supplied meets the Contract Document requirements.

LEVEL OF INSPECTION – C1/D2

249 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 26

VIDEO TRANSMISSION / DISPLAYEQUIPMENT INSTALLATION

Task # Activity

ATMS 26.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 26.2 M Check that the equipment has passed Pre–Installation Testing (PIT) as required prior to any installation work.

ATMS 26.3 Check that the field and traffic operations centre (TOC) equipment is installed and secured in the cabinets’ designated reserved space as per the Contract Drawings.

ATMS 26.4 Check that all cables are neatly trained together within the cabinet when routed along the same path and supported along the rails of the equipment rack and that no maximum bending radii have been exceeded.

ATMS 26.5 Check that the equipment is connected to the proper power distribution assembly (PDA) receptacle reserved for the video transmission / display equipment.

ATMS 26.6 M Check that all video transmission / display equipment has successfully passed Proof of Performance (POP) testing prior to commencing video system line-up acceptance testing (VSLAT) testing and that VSLAT testing is completed successfully.

LEVEL OF INSPECTION – C1/C2

250 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 27

CAMERA EQUIPMENT INSTALLATION

Task # Activity

ATMS 27.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 27.2 M Check that the equipment has passed Pre–Installation Testing (PIT) as required prior to any installation work.

ATMS 27.3 Check that the entire pole top is grounded according to the contract drawings.

ATMS 27.4 Check that the field equipment is installed and secured in the cabinets’ designated reserved space as per the contract drawings.

ATMS 27.5 Check that all cables are neatly trained together within the cabinet when routed along the same path and supported along the rails of the equipment rack and that no maximum bending radii have been exceeded.

ATMS 27.6 Check that the equipment is connected to the proper power distribution assembly (PDA) receptacle reserved for the camera equipment.

ATMS 27.7 Check that the pan/tilt range stops are field adjusted with the assistance and guidance of advanced traffic management systems (ATMS).

ATMS 27.8 M Check that all camera equipment has successfully passed Proof of Performance (POP) testing.

ATMS 27.9 M Obtain GPS readings for ATMS camera equipment.

LEVEL OF INSPECTION – C1/D2

251 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 28

VEHICLE DETECTION EQUIPMENT INSTALLATION

Task # Activity

ATMS 28.1 M Check all delivered material to verify that it is being supplied from the approved material selection approval (MSA) list that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 28.2 M Check that the equipment has passed pre-installation testing prior to any installation work.

ATMS 28.3 Check that sealant is the approved type and rated for the temperature at which time the installation is taking place.

ATMS 28.4 Check that loop layout and installation are in conformance with the Contract Documents. Check that the loops are installed with the size, winding direction, number of turns and type of cable specified.

ATMS 28.5 M Check that the Design-Builder has accurately laid out the loops. The position (centred within the lane), dimensions and spacing to upstream or downstream loops are critical. Check that the Design-Builder applies special treatment (neoprene tubing) to sawcut slots that cross pavement irregularities and that the corners have been rounded as detailed in the Contract Documents.

ATMS 28.6 Check that the loop cable end at the splice point which progresses clockwise is clearly identified, such as being marked with multiple bands of electrical vinyl tape which also indicate the loop number (loop number four (4) requires four (4) bands of tape, etc.).

ATMS 28.7 Check that the saw cut slot depth is as required and has been cleaned and thoroughly dried as specified in the Contract Documents.

ATMS 28.8 Check that the black conductor of the extra low voltage cable is consistently connected to the clockwise winding of the loop lead cable.

ATMS 28.9 Check backing rods are the correct length, diameter and are spaced as required in the Contract Documents.

252 Design-Build Administration Manual January 2014

ATMS 28.10 Check that the metallic shield of extra-low voltage cables are cut off cleanly and left unconnected in the resin loop splice.

ATMS 28.11 M Verify all loop splices and determine that they are encased in a resin splice with the splices positioned to obtain a minimum coverage of 6mm of resin around each splice.

ATMS 28.12 Check that each detector station is identified with a nameplate on the inside wall of the splice point.

ATMS 28.13 Check that the loop location is accurately marked with a cut cross on each curb.

ATMS 28.14 Check that the operating mode of all connected detector amplifiers is set to presence (PR) mode.

ATMS 28.15 Check that initially, the sensitivity switches of amplifiers are set to Level 4. Fine-tuning of the sensitivity switches will be adjusted during the physical car counting process.

ATMS 28.16 Check that the High (FH) Low (FL) frequency switches of amplifiers alternate on each channel.

ATMS 28.17 M Check that the Design-Builder tests the loop with a “megger” and with an inductance meter and submits the measured values for verification.

ATMS 28.18 M Verify that the loop is operating as specified in the Contract Documents.

ATMS 28.19 M Check that the Certificate of Conformance (if required) is supplied and reviewed as per the time requirements of the Contract Documents.

ATMS 28.20 M Check that all vehicle detection station (VDS) equipment has successfully passed Proof of Performance (POP) testing.

ATMS 28.21 M Obtain GPS readings for VDS loop station.

LEVEL OF INSPECTION – C1/C2

253 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 29

CABINET AND CONTROLLER INSTALLATION

Task # Activity

ATMS 29.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by the Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 29.2 M Check that the equipment has passed Pre–Installation Testing (PIT) as required prior to any installation work.

ATMS 29.3 Check that all concrete cabinet pads are installed to the correct elevation, station and offset, as specified in the Contract Documents.

ATMS 29.4 Check that all conduits for the concrete cabinet pads are installed to the proper dimensions.

ATMS 29.5 Check that all conduits into the cabinets are identified as to their purpose.

ATMS 29.6 Check that all unused conduits into a cabinet have a fishwire installed and are plugged with plastic plugs, used conduits should be sealed.

ATMS 29.7 Check that the cabinet is installed with the door orientation specified in the Contract Drawings.

ATMS 29.8 Check that the proper 12 character laminated phenolic identification nameplate is installed on the cabinet so as to be visible when approaching along the highway.

ATMS 29.9 Check that the cabinet ground bus is connected to the system ground at the power supply ground termination.

ATMS 29.10 Check that the loop input wires (extra low voltage cables) are labelled and terminated at the I/J file according to the contract drawings.

ATMS 29.11 Check the controller is plugged into the proper outlet of the cabinet power distribution assembly (PDA).

254 Design-Build Administration Manual January 2014

ATMS 29.12 Check the controller is left with the power switch in the “on” position.

ATMS 29.13 M Check that all controller and cabinet equipment has successfully passed Proof of Performance (POP) testing.

ATMS 29.14 M Obtain GPS readings for cabinet.

LEVEL OF INSPECTION – C1/E2

255 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 30

VARIABLE MESSAGE SIGN (VMS) INSTALLATION

Task # Activity

ATMS 30.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by Design-Builder at the commencement of the contract. Record all non-conformance items and provide recommendations.

ATMS 30.2 M Check that the equipment has passed Pre–Installation Testing (PIT) as required prior to any installation work.

ATMS 30.3 Check that the structural support truss is grounded according to the contract drawings.

ATMS 30.4 Check that the field equipment is installed and secured in the cabinets’ designated reserved space as per the contract drawings.

ATMS 30.5 Check that all cables are neatly trained together within the cabinet when routed along the same path and supported along the rails of the equipment rack and that no maximum bending radii have been exceeded.

ATMS 30.6 Check that the VMS is positioned on the truss as per the contract drawings.

ATMS 30.7 Check that the Design-Builder has all tools tied off while working on the structure and that all Operation Constraints for traffic control from the Contract Documents have been followed.

ATMS 30.8 Check that all support clamps are secured prior to removing the crane support.

ATMS 30.9 Check that the VMS is installed with the tile angle recommended within the Contract Documents.

ATMS 30.10 Check that all access doors are anchored and/or secured properly.

ATMS 30.11 Check that all attachment bolts and/or nuts are tightened to the recommended manufacturer’s torque.

ATMS 30.12 M Check that all VMS equipment has passed Proof of Performance (POP).

256 Design-Build Administration Manual January 2014

ATMS 30.13 M Obtain GPS readings for Variable Message Signs

LEVEL OF INSPECTION – C1/D2

257 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 31

SYSTEM INTEGRATION TEST (SIT) VERIFICATION

Task # Activity

ATMS 31.1 M Check that all equipment installed in the Contract has successfully completed its Pre- Installation Test (PIT) and / or Proof of Performance (POP) testing prior to commencing with SIT.

ATMS 31.2 M Check that the Design-Builder tests in the following chronological order: . Complete all equipment and subsystem tests required in the Contract Documents; . Test each subsystem independently on the communication subsystem; . Test each subsystem independently through the communications subsystem with the head end control device in the traffic operations centre (TOC); . Add subsystems one at a time and monitor the head end performance at the TOC; . Fail safe testing of all subsystems one at a time and monitor the lead end performance at the TOC

ATMS 31.3 M Check that the Design-Builder follows the approved SIT test procedures.

ATMS 31.4 M Check that all tests are successfully completed and all results (PIT, POP and Stage 1 of SIT) are submitted for verification.

ATMS 31.5 M Check that a notification to start the 14 day burn-in test is submitted 5 Business Days in advance, before the commencement of the test.

ATMS 31.6 M Check daily that the Event and Error Logs of the Compass System during the 14 day burn-in test are error free and to notify the Design-Builder promptly if there are any errors.

LEVEL OF INSPECTION – A1/A2

258 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 32

PORTABLE VARIABLE MESSAGE SIGN (PVMS) INSTALLATION - FIXED SUPPORT

Task # Activity

ATMS 32.1 M Check all the delivered material to verify that it is being supplied from the approved material selection (MSA) that was submitted by the Design-Builder at the commencement of the contract.

ATMS 32.2 M Check that the equipment has passed Pre-Installation Testing (PIT) as required prior to any installation work.

ATMS 32.3 Check that the PVMS support structure is grounded according to the contract drawings.

ATMS 32.4 Check that the PVMS is positioned on the support structure as per the contract drawings.

ATMS 32.5 Check that the PVMS is positioned with the angle recommended within the contract drawings.

ATMS 32.6 Check that all attachment bolts and / or nuts are tightened to the recommended manufacturer’s torque.

ATMS 32.7 Check installation PVMS controller cabinet including mounting on the structure, locking mechanism and that equipment inside is securely mounted.

ATMS 32.8 Check the mounting and position of the solar panel and battery pack, if applicable.

ATMS 32.9 Check power supply connection to sign, if applicable.

ATMS 15.10 Check communications link (e.g. telephone, fibre, etc.) to the sign, if applicable.

ATMS 32.11M Check that the communication mode has been set for remote control (e.g. cellular communication), if applicable. Test to determine there is proper control from a COMPASS Traffic Operations Centre or Radio Room.

ATMS 32.12 M Check that all PVMS equipment has passed Proof of Performance (POP).

259 Design-Build Administration Manual January 2014

ATMS 32.13 M Obtain GPS readings for Portable Variable Message Sign.

LEVEL OF INSPECTION – C1/D2

260 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 33

PORTABLE VARIABLE MESSAGE SIGN (PVMS) INSTALLATION - PORTABLE (TRAILER MOUNTED)

Task # Activity

ATMS 33.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by Design-Builder at the commencement of the contract.

ATMS 33.2 M Check that the equipment has passed Pre-Installation Testing (PIT) as required prior to any installation work.

ATMS 33.3 Check that the PVMS trailer is stabilized and levelled.

ATMS 33.4 Check that that the PVMS trailer assembly includes wheel locks to maintain security of the PCMS.

ATMS 33.5 Check that the PVMS sign display is accurately aligned towards traffic.

ATMS 33.6 Check that the PVMS is locked into secure position to prevent rotation and lowering of the sign while in display mode.

ATMS 33.7 Check that the solar panel is locked into the appropriate position on the top of the sign case by using the independent locking mechanism.

ATMS 33.8 Check that the solar panel is installed facing a true South.

ATMS 33.9 Check that all attachment bolts and / or nuts are tightened to the recommended manufacturer’s torque.

ATMS 33.10 Check that the PVMS controller cabinet and equipment inside is securely mounted.

ATMS 33.11 Check battery pack is secured and connected.

ATMS 33.12 Check that communication link to the sign has been activated.

ATMS 33.13 Check for presence of non-skid finish on fenders.

ATMS 33.14 M Check that all PVMS equipment has passed Proof of Performance (POP).

261 Design-Build Administration Manual January 2014

ATMS 33.15 M Obtain GPS readings for PVMS for initial installation and each relocation required in the Contract Documents. The GPS coordinates shall be provided to COMPASS Operations by email within 2 hours of the PVMS installation.

ATMS 33.16 M For PVMS used for traffic management during construction contract, provide PVMS operation data in the traffic signage diary. The record shall include PVMS display content, status of operation, location and direction of the PVMS face. Provide the message content to COMPASS Operations daily.

LEVEL OF INSPECTION – C1/D2

262 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 34

NON - INTRUSIVE TRAFFIC SENSOR INSTALLATION

Task # Activity

ATMS 34.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by Design-Builder at the commencement of the contract.

ATMS 34.2 M Check that the equipment has passed Pre-Installation Testing (PIT) as required prior to any installation work.

ATMS 34.3 Check that the Design-Builder has accurately mounted the unit according to manufacturer’s installation guidelines for parameters including the mounting height, set-back position (side-fire configuration), tilt angle, etc.

ATMS 34.4 Check that a traffic sensor unit is aimed properly to the travel lanes based on whether it is configured for side-fire or forward-looking mode. Check that each detection footprint is contained within one lane.

ATMS 34.5 Check that sensor communications and power cables are continuous between the surge suppressor units and the cabinet and connected correctly at the sensor unit, surge suppressors and to ATC unit inside the cabinet. Verify grounding of the surge suppression and cable.

ATMS 34.6 Check that the external power supplies, grounding and RF equipment are connected as per Contract Document requirements and manufacturer installation guidelines.

ATMS 34.7 Check that the sensor unit is properly calibrated at the site by using manufacturer PC software. Confirm that data is received at the COMPASS Traffic Operations Centre.

ATMS 34.8 M Check if additional calibration table is required later in the contract to reflect lane configuration dictated by staging. Note approximate schedule.

ATMS 34.9 M Check that all sensor equipment has passed Proof of Performance (POP).

LEVEL OF INSPECTION – C1/D2

263 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 35

DOME CAMERA INSTALLATION

Task # Activity

ATMS 35.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by Design-Builder at the commencement of the contract.

ATMS 35.2 M Check that the equipment has passed Pre-Installation Testing (PIT) as required prior to any installation work.

ATMS 35.3 Check that the pole top is grounded according to the contract drawings.

ATMS 35.4 Check that the wiring between the camera and cabinet has been installed continuous with no intermediate splices.

ATMS 35.5 Check that cable strain relief is provided for the power and communication cables.

ATMS 35.6 Check that all cables are neatly trained together within the cabinet when routed along the same path and supported along the rails of the equipment rack and that no maximum bending radii have been exceeded.

ATMS 35.7 Check that the camera pole does not obstruct the desired camera field review.

ATMS 35.8 Check blanking preset, if applicable.

ATMS 35.9 Check that equipment is connected to the proper power distribution assembly (PDA) receptacle reserved for the camera equipment

ATMS 35.10 Check by visual inspection of the image at TOC that the stainless steel straps for the camera arm are sufficiently tightened and that the dome is free of dirt.

ATMS 35.11 M Check that all Dome Camera equipment has passed Proof of Performance (POP).

ATMS 35.12 M Obtain GPS readings for dome camera.

LEVEL OF INSPECTION – C1/D2

264 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 36

CAMERA RAISING AND LOWERING DEVICE INSTALLATION

Task # Activity

ATMS 36.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by Design-Builder at the commencement of the contract.

ATMS 36.2 M Check that the equipment has passed Pre-Installation Testing (PIT) as required prior to any installation work.

ATMS 36.3 Check that camera pole is free from external damage from transportation to the site.

ATMS 36.4 Check that camera pole is placed as per Contract Document specifications and that underground ducts connect properly to the pole.

ATMS 36.5 Verify that pole is installed plumb.

ATMS 36.6 Check that the straps for the pole mounted fitter with pulley housing and mounting bracket are tightened securely.

ATMS 36.7 Check that the arm is positioned as per Contract Document specifications.

ATMS 36.8 Check that the arm is installed at the height specified in Contract Document specifications.

ATMS 36.9 Check that power and communication cables are continuous from cabinet to the camera.

ATMS 36.10 Check that power and communications cables and suspension cable have sufficient length to allow lowering of the camera to ground level.

ATMS 36.11 Check that the winch is rust free and installed securely.

ATMS 36.12 M Check to see the raising/lowering device can be operated using both (a) an electrically-powered and (b) hand-operated device.

265 Design-Build Administration Manual January 2014

ATMS 36.13 M Check that all Camera Raising and Lowering Device equipment has passed Proof of Performance (POP).

ATMS 36.14 M Obtain GPS readings for Camera Raising and Lowering Device.

LEVEL OF INSPECTION – C1 / D2

266 Design-Build Administration Manual January 2014

ATMS – TASK ATMS 37

WIRELESS COMMUNICATION SYSTEM INSTALLATION

Task # Activity

ATMS 37.1 M Check all the delivered material to verify that it is being supplied from the approved material selection approval (MSA) that was submitted by Design-Builder at the commencement of the contract.

ATMS 37.2 M Check that the equipment passed Pre-Installation Testing (PIT) as required prior to any installation work.

ATMS 37.3 Check that the field equipment is installed and secured on the structure (e.g. transmitter and receiver poles / towers) as per the contract drawings.

ATMS 37.4 Check that all cables are supplied continuous with no intermediate splices from cabinet to pole top.

ATMS 37.5 Check that cable connectors match equipment and are securely installed on the cables.

ATMS 37.6 Check that Check that all cables are neatly trained together within the cabinet when routed along the same path and supported along the rails of the equipment rack and that no maximum bending radii have been exceeded.

ATMS 37.7 Check that equipment is connected to the proper power distribution assembly (PDA) receptacle reserved for the communication equipment.

ATMS 37.8 Check that transmit and receive antennas are properly aligned towards each other.

ATMS 37.9 M Check that all wireless communication links equipment has passed Proof of Performance (POP).

ATMS 37.10 M Obtain GPS reading foe wireless communications system.

LEVEL OF INSPECTION – C1 / C2

267 Design-Build Administration Manual January 2014

TRAFFIC CONTROL – TASK TC 1

GENERAL

Task # Activity

TC 1.1 M Check that Design-Builder has submitted an applicable site specific Workers Protection Plan and Traffic Control Plan.

TC 1.2 Review the Approved Signing Requirements with the Design-Builder.

TC 1.3 Record Design-Builder’s contact person(s) responsible for traffic control and the Traffic Control Signing diary.

TC 1.4 Check that the construction zone designation is in place before speed limit signs are changed or the construction zone begins / ends signs are installed.

TC 1.5 Check that layout of signs is in accordance with Ontario Traffic Manual Book 7 Temporary Conditions or as modified by the Regional Traffic Office.

TC 1.6 M Check that Design-Builder’s initial sign placements (by station, offset and height above pavement) and all revisions are clearly documented in the Traffic Control Signing diary.

TC 1.7 Check that all signs and traffic control devices are properly maintained, and in good working order, (i.e. flashers, etc.), and that temporary traffic signals are working properly with no long delays.

TC 1.8 Check that signs and traffic control devices are retro-reflective, clean, legible and in good working order.

TC 1.9 Check for the removal of temporary signs when they are no longer required.

TC 1.10 M Check that (on a regular basis) the Design-Builder records each stage change or sign change in the Traffic Control Signing diary.

TC 1.11 M If an accident occurs check that the Design-Builder has documented all traffic control devices, signing, time of inspection and any other pertinent information including measurements, photos and police accident reports.

TC 1.12 M Check that all lane closure protocol is adhered to as per the requirements of the Contract Documents.

268 Design-Build Administration Manual January 2014

LEVEL OF INSPECTION – A1

NOTE: This task shall be performed by all staff on the contract on an “ongoing” basis. It shall be performed at the initial installation of the traffic stage and every change throughout the life of the contract.

269 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 1

USE OF WASTE PRODUCTS / MATERIALS IN THE WORK

Task # Activity

ENV 1.1 M Check that waste product dust suppressants meet the material and construction requirements of the Contract Documents, e.g. MOE approved dust suppressant.

ENV 1.2 M Check that any use/placement of reclaimed/excess concrete, asphalt pavement, etc. as aggregate, embankment material, slope flattening material, engineered fill within the ROW or other fill is in compliance with the material and construction requirements of the Contract Documents.

ENV 1.3 M Check that standard forms regarding use of blast furnace slag in the work are submitted 3 weeks prior to any use of the material.

ENV 1.4 M Check that any use/placement of blast furnace slag as aggregate, embankment material, slope flattening material or fill is in compliance with the material and construction requirements of the Contract Documents.

LEVEL OF INSPECTION – C1

270 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 2

MANAGEMENT AND DISPOSAL OF EXCESS MATERIALS

Task # Activity

ENV 2.1 M Check that sampling, testing, storage, documentation / manifesting, transportation and disposal of excess materials that is hazardous waste is conducted in accordance with the Contract Documents. A copy of all test results and waste manifests are provided to the MTO Environmental Planner – Waste Management.

ENV 2.2 M Check that standard forms regarding the management of excess material are submitted prior to management of excess material off site.

ENV 2.3 M Check that areas are pre-cleared prior to excess material placement and contour graded and seeded and mulched after placement.

ENV 2.4 Record the locations of management areas and sources of excess material being managed.

ENV 2.5 M Check compliance with conditions on management of disposed fill and materials stockpiled inside the R.O.W., on Ministry property and on third party properties covered with letters of agreement.

LEVEL OF INSPECTION – C1

271 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 3

WORK IN, ADJACENT TO, AND OVER WATERBODIES

Task # Activity

ENV 3.1 Check that sediment and other deleterious material are prevented from reaching watercourses, and other water bodies.

ENV 3.2 Check that entry of equipment and construction materials to watercourses and waterbodies, and undertaking of any work, is limited to that specified in the Contract Documents and environmental documentation, and as may be authorized through environmental permits/approvals.

ENV 3.3 Check that work specified in the watercourses/waterbodies and their banks is in compliance with that specified in the Contract Documents and environmental documentation, and as may be authorized through environmental permits/approvals.

ENV 3.4 Check that temporary water passage systems, temporary waterbody crossings, cofferdams and turbidity curtains are installed, maintained and removed in compliance with Contract Document requirements.

ENV 3.5 Check that disturbance/damage to watercourse/waterbody beds, banks and bank vegetation is limited to that specified in the Contract Documents and environmental documentation, and as may be authorized through environmental permits/approvals.

ENV 3.6 Check for compliance with the time constraints specified in the Contract Documents relative to work in and adjacent to watercourses.

ENV 3.7 Check that re-grading and restoration measures are undertaken as specified in the Contract Documents that the erosion/sedimentation control schemes are in place and functioning. Determine if additional erosion control measures, or additional locations may be required.

LEVEL OF INSPECTION – C1 – A1 During critical operations (i. e. in-water work, beginning and ending of dewatering and unwatering operations. Except where a Fisheries Contracts Specialist has been hired to oversee the work under a DFO Fisheries Act Authorization.

272 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 4

WORK IN AND ADJACENT TO AREAS OF TREESNOT DESIGNATED FOR REMOVAL

Task # Activity

ENV 4.1 Check that sediment and other deleterious material are prevented from reaching areas of trees not designated for removal.

ENV 4.2 Check that the specified limits of grading are not exceeded in and adjacent to areas of trees not designated for removal, and that damage/removal of trees is limited to that specified in the Contract Documents and environmental documentation.

ENV 4.3 Check that entry of equipment, construction materials and excess materials to areas of trees not designated for removal is limited to that specified in the Contract Documents and environmental documentation.

ENV 4.4 Check that tree barrier protection is in place prior to commencement of construction activities.

ENV 4.5 Check for proper placement and maintenance of barrier for tree protection.

ENV 4.6 Check for any damage to trees, and have them repaired / replaced as specified in the Contract Documents.

LEVEL OF INSPECTION – C1

273 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 5

CONTROL OF DUST FROM THE WORK

Task # Activity

ENV 5.1 Check that dust from exposed work, and from construction operations such as grading, concrete cutting/grinding, abrasive blast cleaning of concrete and steel, and road sweeping does not cause a nuisance to pedestrian and vehicular traffic within the ROW, adjacent residential/commercial/institutional properties, and is not entering a watercourse or Environmentally Significant Area.

LEVEL OF INSPECTION – A1

NOTE: This task shall be performed by all staff on the contract on an “ongoing” basis.

274 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 6

TEMPORARY EROSION AND SEDIMENTATION CONTROL

Task # Activity

ENV 6.1 M Check that sediment barriers, flow checks, sediment traps, turbidity curtains and cofferdams are installed where and when they are specified in the Contract Documents, or as specified in the Design- Builder’s proposals, or are adjusted when installed, according to site conditions and staging activities.

ENV 6.2 Check that construction of temporary erosion and sedimentation control measures complies with Contract Document requirements.

ENV 6.3 Check that temporary erosion and sedimentation control measures are maintained and replaced as specified in the Contract Documents. Check that contingency supplies where specified in the Contract Documents, such as straw bale flow checks, erosion control blanket, stakes, rock and silt fence are on site for the purposes of maintenance or repair of erosion and sediment control measures.

ENV 6.4 Check that accumulated sediment is cleaned out from temporary erosion and sedimentation control measures as specified in the Contract Documents, and that temporary erosion and sedimentation control measures are checked for effective working condition prior to forecasted major storm events, and subsequent to storm events.

ENV 6.5 Check that sediment discharges to watercourses and other sensitive areas are removed in consultation with environmental staff.

ENV 6.6 Check that temporary erosion and sedimentation control measures are removed as specified in the Contract Documents, and in a manner that prevents sediment escape.

ENV 6.7 Check for compliance with time constraints on the maximum period between removal of original vegetative surface cover and placement of final specified surface cover. Check that such compliance also provides for compliance with the cut-off dates for seed and cover specified in the Contract Documents.

ENV 6.8 Check that the Design-Builder installs any additional erosion and sedimentation control measures that are necessary solely because of preferred construction means, methods, techniques, sequences and procedures selected by the Design-Builder.

275 Design-Build Administration Manual January 2014

ENV 6.9 Check that the Design-Builder installs any additional erosion and sedimentation control measures that were not anticipated during design, but are required because of site conditions.

LEVEL OF INSPECTION – C1 during installation – C1 prior to forecasted major storm events – C1 following significant storm events – E1 for routine maintenance, unless maintenance / repairs are required upon inspection and after significant storm events

276 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 7

INCIDENT MANAGEMENT (As required by clause GC7.13.03 of the MTO General Conditions of Contract)

Task # Activity

ENV 7.1 Check that any spill, discharge, emission, release or escape of a material, pollutant, contaminant, deleterious substance or dangerous good as a result of an incident under the control of the Design- Builder or as a result of the Design-Builder’s operations, is immediately contained.

ENV7.2 Check that the Design-Builder undertakes immediate notification of the spill / environmental incident to the proper authorities (SP199F34). If the Design-Builder is unable or unwilling to make the required notifications, or there is any doubt that they have been made, the CA shall make the immediate notifications on behalf of the Design-Builder.

ENV 7.3 Check that the Design-Builder undertakes cleanup and restoration of the environment to pre-spill / environmental incident conditions.

ENV 7.4 Check that the Design-Builder completes the Incident Notification Form (PH-CC-818) within 48 hours of the incident.

LEVEL OF INSPECTION - A1 Upon notification by the Design-Builder of an incident as required by MTO GC 7.13.03, or upon direct discovery by the CA

277 Design-Build Administration Manual January 2014

ENVIRONMENTAL – TASK ENV 8

FISHERIES ACT AUTHORIZATION IMPLEMENTATION AND MONITORING

(As required by SP199F58 - Fisheries Act Authorization Compliance – Oversight, Monitoring and Documentation)

Task # Activity

ENV 8.1 Verify that the Fisheries Contracts Specialist (and Fisheries Assessment Specialist, if required) is registered in the appropriate Specialty on RAQS, as posted under “Contract Attachments” in the Owner’s Contract Business Management System for the contract.

ENV 8.2 Liaise with Fisheries Contract Specialist regarding Fisheries Act Authorization requirements of the contract.

ENV 8.3 Check that the Fisheries Contracts Specialist is on-site to determine that the proper installation, functioning and decommissioning (as appropriate) of all compensation and mitigation measures referred to in the Fisheries Act Authorization.

ENV 8.4 Check that the Fisheries Contracts Specialist – Monitoring Documentation is completed and submitted on time as required. The CA shall send unmodified copies of each of the Monitoring Documents to the MTO Regional Environmental Office/Section, within 2 Business Days of receipt from the Design-Builder, and to the Department of Fisheries and Oceans as per conditions of the Authorization.

ENV 8.5 Review Monitoring Documentation and take appropriate follow-up action for issues of non-compliance, including working with the Fisheries Contracts Specialist towards appropriate remediation.

LEVEL OF INSPECTION – C1

278 Design-Build Administration Manual January 2014

8.0 DESIGN-BUILD INSPECTION TASKS - PERFORMANCE SPECIFICATIONS

This section of the Administration Manual is still under development; detail is provided only on administration/oversight of a few of the available Performance Specifications (Perf).

In general, the oversight required for that Work covered by a Performance Specification is significantly less than traditional levels of oversight for Work covered by an OPSS. The CA, CSA and Project Lead are strongly encouraged to review in detail all Perfs included in the Contract Documents and plan the oversight process for each one.

Each Perf provides details of the Design-Builder’s responsibilities and the required performance of the Work. To guide the CA there are detailed performance measurement criteria including performance indicators, measurement procedures and requirements for repair/replacement of non-conforming work. The Perfs also provide detail on the consequences to be applied for non- conformance to the performance requirements. Non-conformances are administered by the CA.

279 Design-Build Administration Manual January 2014

Performance Specification for Environmental Management – PERF 1072

PRE- CONSTRUCTION

Item Performance Element Oversight Method/Comments 1072 Environmental Check /ensure EMS meets all requirements as outlined Management System under PERF 1072.04.01.02 1072 Permits and Approvals Check/ensure copies of all permits and approvals obtained by Design-Builder are submitted to CA prior to construction. 1072 Check/ensure a letter of confirmation is submitted to the CA that assures that all Class Environmental Assessment commitments and requirements of permits and approvals have been met.

DURING CONSTRUCTION

Item Performance Element Oversight Method/Comments 1072 Temporary Erosion Check daily that erosion and sediment control measures Sedimentation Control (silt fence and straw bales etc.) are in place and functioning as per the Design-Builder’s Environmental Plan 1072 SARS Mitigation Check weekly that measures are in place for the protection Measures of any species at risk. 1072 Timing Restrictions Check that all timing requirements are adhered to. 1072 Temporary Water Check that sheet piling/cofferdams/turbidity curtains for the Passage systems purpose of dewatering, have been installed and maintained as per Contract Document requirements. 1072 Dust Control Check daily that dust from exposed work is being addressed by the Design-Builder.

COMPLETION OF CONSTRUCTION

Item Performance Element Oversight Method/Comments 1072 Environmental Review Work and check to ensure all final mitigation Management measures have been met 1072 Check that the Design-Builder has submitted a letter that assures all environmental management features ( as per table 1 in the RFP) have been met.

LEVEL OF INSPECTION –

280 Design-Build Administration Manual January 2014

Performance Specification for Information Management – PERF 1075

PRE- CONSTRUCTION

Item Performance Element Oversight Method/Comments 1075

DURING CONSTRUCTION

Item Performance Element Oversight Method/Comments 1075

COMPLETION OF CONSTRUCTION

Item Performance Element Oversight Method/Comments 1075

LEVEL OF INSPECTION –

281 Design-Build Administration Manual January 2014

Performance Specification for Traffic and Mobility Management – PERF 1077

PRE CONSTRUCTION

Item Performance Element Oversight Method/Comments 1077.1 Designation of Check /ensure Design-Builder submits a signed Construction Zone construction zone (regulatory) speed reduction form requesting a posted speed reduction on the contract, and forward to the regional office for approved signatures. 1077.2 Traffic Management To be submitted prior to construction by the Design-Builder Plan that outlines the overall traffic management strategy for all the work performed under the contract ( be available upon request within 24 hours and on site when workers are present) Reference list under PERF 1077.04.02

DURING CONSTRUCTION

Item Performance Element Oversight Method/Comments 1077.3 Temporary Condition Check daily that all long duration temporary condition Signs signs are installed and maintained as per OTM Book 7 ( reference typical TL -1 TL-3) 1077.4 Contract Identification Check signs are installed 5 Business Days prior to Signs (TC-81,s) construction 1077.5 Temporary Advance Check signs are installed 5 Business Days prior to any Information Signs (TC- lane closures 64,s) 1077.6 Advisory Speed Signs Check daily, signs are in place within the construction zone as per Book 7 and Design-Builders TMP 1077.7 Design-Builders Sign Check weekly that the Design-Builder is maintaining a sign Dairy diary as per GC 7.01.05 1077.8 Open Excavations Check daily that there are no open excavations adjacent to a lane carrying traffic overnight and on non working days. 1077.9 Excavations (Frost Check daily that any excavation within 4 m of lanes Heaves etc) carrying traffic is backfilled at night up to profile grade prior to shutdown 1077.10 Equipment/Material Check daily no equipment or material is stored within 4m of the travelled portion of the roadway at shutdown. 1077.11 Traffic Hazards Check daily that anything that the CA in his/her opinion constitutes a traffic hazard is removed immediately by the Design-Builder. 1077.12 Maximum Allowable Check twice /week by means of a simple drive through, to Travel Time check/ensure the Design-Builder is meeting MATT as (MATT) outlined in Table 1 of PERF. 1077.13 Consequences for Non Apply consequences for each particular feature as outlined conformance in Table 3 of PERF as per occurrence.

LEVEL OF INSPECTION –

282 Design-Build Administration Manual January 2014

Performance Specification for Design and Reconstruction and Rehabilitation of Pavement Structure – PERF 2272

PRE CONSTRUCTION

Item Performance Element Oversight Method / Comments 2272.1 Pavement Design Report Review submitted PDR to ensure it meets including Certification is Contract Document requirements submitted to CA 5 Business Days prior to start of any in place processing. 2272.2 Mix design is submitted 1 Review submitted mix design to ensure it meets Business Day prior to start of Contract Document requirements paving

DURING CONSTRUCTION

Item Performance Element Oversight Method / Comments 2272.3 Ensure Design-Builder takes Randomly established sample locations to samples of material according to submit to Design-Builder Table E. 2272.4 Vertical & horizontal grade Review submitted grade checks checks are submitted to CA within 2 Business Days of each grade check 2272.5 Design-Builder submits signed Review submitted form PH-CC-820 “Certification and certified templates or form of Grade Elevation/Cross fall) (PH-CC-820) “Certification of Grade Elevation/Crossfall” to the CA 2272.6 Check that each HMA course; the Upon receipt of Certification of Grade minimum width (paved lane, Randomly check a point every 2km throughout shoulder etc.) shall be the design the contract limits width. 2272.7 Check final cross fall of all paved Upon receipt of Certification of Grade for final surfaces shall not vary plus or surface asphalt. minus 0.33% from design cross Randomly check cross-fall at tangent areas fall. throughout contract limits Check super elevation at all curves throughout the contract limits 2272.8 Check the finish surface Upon completion of all surface paving, randomly pavement is within the 120mm check centreline profile every km throughout the permitted grade raise. contract limits. 2272.9 Check that the final surface area Upon completion of all paving, review the is 100% free of all surface contract limits and visually check for distresses. distresses Immediately notify Design-Builder by instruction notice if distresses are found that potentially could impact the safety of the travelling public. 2272.10 Check for Smoothness Upon completion of all paving, randomly check

283 Design-Build Administration Manual January 2014

throughout contract limits an area every km throughout the contract limits, using a 3 m long straight edge, ensuring that when placed anywhere on the binder or surface course in any direction, there shall not be a gap between the bottom of the straight edge and the surface of the binder or surface course greater than 6 mm. Document areas that are in non- conformance and notify Design-Builder through instruction notice 2272.11 Check material types and Review QA/QC sample results. On site visual thickness observations. Check Longitudinal Joints in Upon completion of all paving, check surface course meet Contract Longitudinal joint is set up as per OPSS 313 and Document requirements follows demarcation between driving lanes, tapers etc. as indicated in the Contract Documents.

POST CONSTRUCTION

Item Performance Element Oversight Method / Comments 2272.12 Check Design-Builder installs Check the accuracy of each 500m segment sign 500m segment signs, as per placement by using an odometer check. Contract Document requirements. Check Steel post and metal sign conforms to OPSS 2007 and OPSS 2001 Performance Requirements at Ensure Performance Requirements are met as Contract Completion per Table G in the PERF. 2272.13 Performance Requirements Ensure Performance Requirements are met as During the Warranty Period per Table H in PERF

LEVEL OF INSPECTION –

284 Design-Build Administration Manual January 2014

Performance Specification for Design and Construction of Pavement Markings – PERF 2273

. Item Performance Element Oversight Method / Comments 2273.1 Short Term Pavement Check /ensure these markings if needed are Markings in place and are painted, for each occurrence 2273.2 Pavement Markings and Randomly check markings and symbols are Symbols in the location as identified in the Contract Documents. 2273.3 Pavement Markings and Randomly check markings are clearly Symbols visible, legible and conform to OTM Book 11 2273.4 Pavement Markings and Randomly check line edges are straight and Symbols true with no severe splatter overspray or tracking of material 2273.5 Pavement Markings and Upon completion of the placement of all final Symbols pavement markings review the Contract Document with the regional pavement coordinator to check the minimum performance requirements have been achieved, as detailed in Table 3 of the PERF.

LEVEL OF INSPECTION –

285 Design-Build Administration Manual January 2014

Performance Specification for Design and Construction of Unpaved Shoulders – PERF 2277

LEVEL OF INSPECTION –

286 Design-Build Administration Manual January 2014

Performance Specification for Design and Construction of Pavement Structure Replacement – PERF 2282

LEVEL OF INSPECTION –

287 Design-Build Administration Manual January 2014

Performance Specification for Design and Construction of Hot Mix Asphalt Partial Depth and Hot Mix Asphalt Full Depth Repair – PERF 2292

LEVEL OF INSPECTION –

288 Design-Build Administration Manual January 2014

Performance Specification for Design and Construction of Structural Culverts – PERF 3271

LEVEL OF INSPECTION –

289 Design-Build Administration Manual January 2014

Performance Specification for Design and Construction of Deck Joint Assemblies, Preformed Seals, Joint Fillers, Joint Seals, Joint Sealing Compounds and Waterstops – PERF 3273

LEVEL OF INSPECTION –

290 Design-Build Administration Manual January 2014

PERFORMANCE SPECIFICATION FOR DESIGN AND CONSTRUCTION OF NON- STRUCTURAL CULVERTS – PERF 4271

DURING CONSTRUCTION . Item Performance Element Oversight Method/Comments 4271.1 Pipe Material Selection Check pipe selection complies with MTO Pipe Gravity Design regarding culvert material requirements (eg. Steel, Concrete, High Density Polyethylene, PVC) 4271.2 Pipe Material Code Check randomly 25% new pipe installations that the designed pipe material code is being followed including the new designed diameter and length, as per quantity sheets 4271.3 New Culvert Installation randomly check 25% of new pipe installations (random checks should focus on culverts in deep fills) are being installed at the designed location, elevation, alignment as the existing culvert with minor adjustments for erosion to meet current conditions.

4271.4 New Culvert Installation randomly check 25% of the new culverts are being installed at designed trench widths with proper fill/bedding materials, frost tapers where site conditions warrant etc.

4271.5 Dewatering/Unwatering Randomly check 25% of the new culverts to ensure where dewatering measures are required they are carried out as per the Contract Document requirements.

POST CONSTRUCTION

Item Performance Element Oversight Method/Comments 4271.6 Constructed Culvert Inventory check/ ensure Constructed Culvert Inventory Database Database is submitted to the Ministry 5 Business Days before the start of a main inspection window.

4271.7 Pipe Condition Status Ministry to perform post installation inspections on 25% of the total number of culverts installed (locations will be at the Ministries discretion.) to determine if culverts meet Pipe Condition Status.

291 Design-Build Administration Manual January 2014

4271.8 Post Installation Inspection Notify the Design-Builder 5 Business Days prior to the start date of the post installation inspections 4271.9 Post Installation Inspection Check that the pipe culverts identified for inspection have been cleaned and flushed out by the Design-Builder at least 2 Business Days prior to the inspection. 4271.10 Post Installation Inspection Schedule arrangements with a qualified Inspection firm to Check for scour , slope erosion, settlement/distortion/heaving, , shape and joints at selected pipe locations (25% of culverts installed) to ensure the features meet performance requirements. 4271.11 Ensure pipes after inspection that do not have an acceptable PCS, are replaced or repaired. 4271.12 Scour, Slope Erosion, Ensure Design-Builder corrects within 15 Settlement/Distortion/Heaving Business Days of receiving notice from the Ministry. 4271.13 Pipe Condition Status Ensure repair methods are performed as outlined assessed with a “Repair” PCS in Table 3 of PERF.

LEVEL OF INSPECTION –

292 Design-Build Administration Manual January 2014

PERFORMANCE SPECIFICATION FOR DESIGN AND CONSTRUCTION OF STRUCTURAL CULVERTS – PERF 3271

LEVEL OF INSPECTION –

293 Design-Build Administration Manual January 2014

PERFORMANCE SPECIFICATION FOR DESIGN AND CONSTRUCTION OF CABLE GUIDE RAIL, STEEL BEAM GUIDE RAIL AND STEEL BEAM ATTENUATING TERMINAL SYSTEMS– PERF 4201

. Item Performance Element Oversight Method/Comments 4201.1 Cable Guide Rail Check 25% of CGR installed meets Contract Document requirements. (refer to CAITM) 4201.2 Steel Beam Guide Rail Check all SBGR installed meets Contract Document requirements (refer to CAITM) 4202.3 Steel Beam Energy Attenuating Check all End Treatments installed meets Systems Contract Document requirements (refer to CAITM)

LEVEL OF INSPECTION –

294 Design-Build Administration Manual January 2014

APPENDIX A

LIST OF CONTRACT ADMINISTRATION FORMS

CONTRACT ADMINISTRATION FORMS LIST ADM-R-44 RECORD OF EXPANSION JOINT - WATER TESTING PH-A-106 LIST OF MATERIALS FROM DESIGNATED SOURCES PH-CC-009 FIELD COMPACTION REPORT (NUCLEAR GUAGE) PH-CC-010 ONE POINT PROCTOR TEST PH-CC-106 BITUMINOUS ROAD INSPECTOR'S DAILY REPORT PH-CC-117 COLD WEATHER CONCRETING RECORD TEMPERATURE PH-CC-129A WATERPROOFING MEMBRANE THICKNESS REPORT PH-CC-130 DETERMINING PAYMENT PER SHIPMENT OF EMULSIFIED ASPHALTS PH-CC-131 DETERMING THE PERCENTAGE ADJUSTMENT FOR EMULSIFIED ASPHALTS PH-CC-132 DETERMINING THE PERCENTAGE ADJUSTMENT FOR EMULSIFIED ASPHALT PRIMERS PH-CC-133 DETERMINING THE PERCENTAGE ADJUSTMENT FOR LIQUID ASPHALTS PH-CC-134 DETERMINING THE PERCENTAGE ADJUSTMENT FOR POLYMER MODIFIED EMULSIFIED ASPHALTS PH-CC-139 BITUMINOUS SAMPLE IDENTIFICATION PH-CC-247 HOT MIX – ACCEPTANCE TEST RESULT FOR RECOVERED PENETRATION PH-CC-255 HOT MIX – COMPACTION ACCEPTANCE AND PRICE ADJUSTMENT SHEET PH-CC-322 CONCRETE CONSTRUCTION REPORT PH-CC-340 FIELD SAMPLE DATA SHEET - CONCRETE PH-CC-349 BITUMINOUS MATERIAL (PRODUCT SAMPLE FORM) PH-CC-360 PAVEMENT MARKING SAMPLE DATA MATERIALS ENGINEERING & RESEARCH OFFICE CONCRETE SECTION PH-CC-427 BRIDGE DECK COVERMETER SURVEY PH-CC-430 STRUCTURAL COATING SAMPLE DATA MATERIALS ENGINEERING & RESEARCH OFFICE CONCRETE SECTION PH-CC-433A CONCRETE MIX DESIGN SUBMISSION FORM A PH-CC-433B CONCRETE MIX DESIGN SUBMISSION FORM B PH-CC-443 GEOTEXTILE TESTING REQUEST PH-CC-448a AGGREGATE TEST DATA – CONCRETE (Physical Properties – Fine Aggregate) PH-CC-448b AGGREGATE TEST DATA – CONCRETE (Physical Properties – Coarse Aggregate) PH-CC-449a AGGREGATE TEST DATA – HOT MIX ASPHALT (Physical Properties – Fine Aggregate) PH-CC-449b AGGREGATE TEST DATA – HOT MIX ASPHALT (Physical Properties – Coarse Aggregate) PH-CC-449c AGGREGATE TEST DATA – HOT MIX ASPHALT (Superpave – Consensus Properties) PH-CC-450a AGGREGATE TEST DATA – GRANULAR (PHYSICAL PROPERTIES) PH-CC-450b AGGREGATE TEST DATA – GRANULAR (PRODUCTION PROPERTIES) PH-CC-451 AGGREGATE TEST DATA – SURFACE TREATMENT (Physical Properties) PH-CC-455 QA GRANULAR SUMMARY PH-CC-700 PERMISSION TO START WORK PH-CC-703 SCALE ACCURACY INSPECTION PH-CC-708 DAILY REPORT GLASS BEAD APPLICATION RATE PH-CC-709 INSTRUCTION NOTICE TO DESIGN-BUILDERS PH-CC-711 SUMMARY REPORT PAVEMENT MARKINGS

295 Design-Build Administration Manual January 2014

PH-CC-712 RECONCILLIATION OF MTO SUPPLIED MATERIALS PH-CC-713 DAILY REPORT PAVEMENT MARKINGS PH-CC-716 SUMMARY QUANTITY SHEETS PH-CC-719 COVER FORM FOR MATERIAL WEIGH TICKETS PH-CC-721 RECORD OF SCALE AND WEIGHING INSPECTION PH-CC-725 TAX CHANGE STATEMENT PH-CC-730 SUMMARY FOR ITEM PH-CC-731 FINAL PAYMENT QUANTITY PH-CC-732 MATERIAL CONTROL LEDGER, CONTRACT MATERIALS PH-CC-735 CROSS SECTION TEMPLATE (SUB - GRADE) PH-CC-736 NOTIFICATION OF PLACEMENT OF STRUCTURAL CONCRETE PH-CC-742 CONSENT TO SUBLET PH-CC-744 FUEL CONSUMPTION LISTING SUBDESIGN-BUILDER PH-CC-745 FUEL CONSUMPTION TRACKING SUBDESIGN-BUILDER PH-CC-750 REQUEST FOR CLARIFICATION PH-CC-754 DAILY WORK RECORD PH-CC-763 STATEMENT OF RECORD OF WORKING DAYS PH-CC-765 CONTRACT MATERIAL DELIVERY SCHEDULE PH-CC-771 TURNOVER AGREEMENT PH-CC-775 EXTENSION OF TIME REQUEST AND APPROVAL FORM PH-CC-782 DAILY REPORT STRUCTURAL STEEL COATING PH-CC-783 SUMMARY REPORT STRUCTURAL STEEL COATING PH-CC-796 TIME & MATERIAL SUMMARY FOR PAYMENT PH-CC-797 CERTIFICATE OF COMPLETION OF SUBCONTRACT PH-CC-798 STATUTORY DECLARATION OF COMPLETION OF SUBCONTRACT PH-CC-799 CERTIFICATE OF SUBSTANTIAL PERFORMANCE PH-CC-800 CLAIM FOR LIEN PH-CC-801 RELEASE OF LIEN PH-CC-802 RELEASE FROM WARRANTY CERTIFICATE PH-CC-811 CERTIFICATION OF THE COMPONENT PH-CC-817 APPLICATION FOR SUBSTANTIAL PERFORMANCE / CONTRACT COMPLETION PH-CC-818 INCIDENT NOTIFICATION FORM PH-CC-819 ACTUAL PAYROLL BURDEN PH-CC-820 CERTIFICATION OF GRADE ELEVATION / CROSSFALL PH-CC-822 CERTIFICATE OF CONFORMANCE PH-CC-822CPD CERTIFICATE OF THE PAVEMENT DESIGN AND THE PAVEMENT DESIGN REPORT PH-CC-822IMC CERTIFICATE OF INDEPENDENT CHECK OF MIX DESIGN PH-CC-822PIC CERTIFACTION OF INSTALLATION OF PIPE CULVERTS PH-CC-822PCC POST CONSTRUCTION CERTIFICATE PH-CC-823 ADVANCE PAYMENT FOR GRANULAR PH-CC-825 LETTER OF APPROVAL (LAND OWNER AGREEMENT) PH-CC-828 CHANGE PROPOSALS DURING CONSTRUCTION PH-CC-829 FINAL ESTIMATE QUANTITES AND COST SHEET PH-CC-830 CONTRACT VALUE REPORT FOR SUBDESIGN-BUILDER’S PH-CC-831 DESIGNATION AND INSPECTION OF HAUL ROADS PH-CC-832 DESIGN-BUILDER'S INFRACTION REPORT PH-CC-833 WARNING OF INFRACTION REPORT PH-CC-834 MEMORANDUM RE: MAJOR ITEM OVERRUN/UNDERRUN

296 Design-Build Administration Manual January 2014

PH-CC-837 RELEASE OF PIT AREAS & WASTE SITES ON CROWN LAND PH-CC-838 PRELIMINARY DESIGN-BUILDER SCHEDULE CHECKLIST PH-CC-839 MTO CLASS EA MONITORING QUESTIONNAIRE FOR CONTRACT ADMINISTRATION STAFF PH-CC-840 REGIONAL ROAD REPORT PH-CC-841 WARRANTIES PH-CC-842 INSP., TESTING AND SAMPLING OF DESIGNATED SOURCE MATERIAL PH-CC-843 NUCLEAR MOISTURE / DENSITY, GAUGE INSPECTION WORKSHEET (QC) PH-CC-844 PRICE ADJUSTMENT FOR CONCRETE PH-CC-845 DAILY CONCRETE LOAD TEST RESULTS PH-CC-846 HOT MIX COMPACTION CORE SAMPLE LOCATION PH-CC-847 HOT MIX SUMMARY PH-CC-848 HOT MIX / CONCRETE SMOOTHNESS ACCEPTANCE & PRICE ADJUSTMENT SHEET PH-CC-849 DETERMINATION OF SCARIFICATION DEPTH FOR HOT-IN-PLACE RECYCLING PH-CC-850 CHANGE ORDER - ADDITIONAL WORK PH-CC-851 CHANGE ORDER - CHANGE IN THE WORK, EXTRA WORK PH-CC-852 TIME AND MATERIAL BAR GRAPH PH-CC-854 CHANGE ORDER APPROVAL AND COST ESTIMATE PH-CC-856 PRICE AGREEMENT FOR CHANGE IN THE WORK, EXTRA WORK OR ADDITIONAL WORK PH-CC-857 WORK DIRECTIVE PH-CC-859 NON-CONFORMANCE REPORT PH-CC-861 MONTHLY SUMMARY OF QUALITY PROCESS NON-CONFORMANCES PH-CC-862 STATUS OF NON-CONFORMANCE PH-CC-863 ANNUAL DECLARATION: MTO MINIMUM QUALITY MANAGEMENT SYSTEM PH-CC-863M ANNUAL DECLARATION FOR A COMPANY WITH SUBSIDIARIES: MTO MINIMUM QUALITY MANAGEMENT SYSTEM PH-CC-864 ANNUAL DECLARATION: ISO 9001 QUALITY MANAGEMENT STANDARD PH-CC-866 APPLICATION FOR FIELD ADJUSTMENT TO JMF PH-CC-867 MACROTEXTURE RATIO CALCULATION FORM PH-CC-868 HOT MIX QC/QA COMPARISON AND PAY FACTOR CALCULATION PH-CC-870 LIFT THICKNESS MEASUREMENT RECORDING FORM PH-CC-871 FORM A: CONCRETE COVER METER CALIBRATION REPORT & FORM B: REPORT ON LIFT THICKNESS AS DETERMINED FROM CONCRETE COVERMETER READINGS PH-CC-872 SAMPLE LETTER TO DESIGN-BUILDER - Re: Design-Builder Mix Designation as required by SP for Acceptance of Hot Mix by End Result Specification PH-CC-873 SAMPLE LETTER TO DESIGN-BUILDER (Version 1.0) Re: Notice of (General/Mid- Lane) Segregation PH-CC-874 HOT MIX - SMOOTHNESS ACCEPTANCE AND PRICE ADJUSTMENT SHEET PH-CC-875 VISUAL ASSESSMENT OF HOT MIX DEFICIENCES PH-CC-876 CERTIFICATION OF TEMPORARY CONCRETE BARRIER INSTALLATIONS PH-CC-877 CERTIFICATION OF THE INSTALLATION OF SAFETY ITEMS PH-CC-878 RECORD DOCUMENTS CHECKLIST PH-CC-879 CERTIFICATION OF ELECTRICAL CHAMBER INSTALLATIONS PH-CC-880 CONTRACT CONTROL OFFICER REPORT PH-CC-880CAPR CONTRACT ADMINISTRATION PERFORMANCE REPORT PH-CC-881 PAYMENT COVER SHEET PH-CC-890 CERTIFICATE OF CONTRACT COMPLETION

297 Design-Build Administration Manual January 2014

PH-D-046 PIT AND QUARRY AFTER USE REPORT PH-D-10 AGGREGATE SAMPLE DATA SHEET PH-D-1A GRANULAR A GRADATION COMPUTATION ACCEPTANCE & PAYMENT ADJUSTMENT SHEET PH-D-1B GRANULAR B TYPES I, II & III GRADATION COMPUTATION ACCEPTANCE & PAYMENT ADJUSTMENT SHEET PH-D-1M GRANULAR M GRADATION COMPUTATION ACCEPTANCE & PAYMENT ADJUSTMENT SHEET PH-D-1O GRANULAR O GRADATION COMPUTATION ACCEPTANCE & PAYMENT ADJUSTMENT SHEET PH-D-1SSM SSM GRADATION COMPUTATION ACCEPTANCE & PAYMENT ADJUSTMENT SHEET PH-D-205 BRIDGE CONSTRUCTION PILE DRIVING RECORD PH-D-352 MISCELLANEOUS DETAIL SHEET PH-D-359 INVOICE OF PLANS, PROFILES, NOTES, ETC. PH-M-002 SURFACE TREATMENT DAILY REPORT PH-M-101 DESIGNATION OF CONSTRUCTION ZONE

Forms can be downloaded from RAQS

298

APPENDIX B

ROLE OF THE CONTRACT ADMINISTRATOR WITH RESPECT TO QUALITY VERIFICATION ENGINEER (QVE) SERVICES

PRINCIPLES

The CA shall monitor the performance of the Design-Builder (and by extension the QVE) by verifying the Design-Builder’s processes, rather than assessing the quality of the Work. The CA shall conduct random assessments to determine whether or not the QVE services, including the issuing of Certificates of Conformance (CofC’s), are in general conformance with the Contract Documents. It is important that the CA not assume any responsibility for the QVE services or the quality of the Work.

CA SERVICES

The CA shall provide the following services, as a minimum:

Construction

. Receiving CofC’s for Construction; . Confirming, documenting and reporting that CofC’s: - Are received within the specified time frame - Consist of the specified content and format (defined in SP199S48) - Are sealed and signed by the QVE . Requesting a copy of the QVE’s written permission to proceed after an Interim Inspection on a random basis on the % of work specified in the Contract Administration and Inspection Task Manual or when there is justifiable concern that the work covered by the Interim Inspection does not comply with the Contract Documents; . Confirming, documenting and reporting that QVE’s written permission to proceed after an Interim Inspection: - Is received within the specified time frame and - The work complies with the Contract Documents . Conducting random assessments of the Work; This activity includes conducting a random assessment on the % of work specified in the this guide for that item, random assessment of fabricated components when received on site, and immediately advising MTO Operations staff (CSA) if the as- constructed work differs from the description in the CofC; . Facilitating speedy consideration of Design-Builder proposals for Amendments to Contract Documents in cases of non-conformance.

QVE Performance Monitoring Report

. The CA shall submit a QVE monitoring report to the Regional Contracts Office at the same time the Design-Build Contractor Performance Rating report is submitted;

299

. The report is not an audit of the construction work but the results of an audit of the Certificates of Conformance (CofC), permissions to proceed and the Design- Builder’s processes; . The monitoring shall include: – Has the Design-Builder complied with the Special Provision for QVE Services and the Quality Control Compliance Incentive Special Provision? – Has the QVE been on-site when required by the Contract Documents, or at the fabrication plant (if applicable)? – What procedures did the QVE perform? – Did the QVE perform all the procedures required by the applicable SP? . The report shall include: – Contract item/specification; – Component monitored; – Location of component monitored; – Details of their monitoring procedures; – Date/time of monitoring.

300

APPENDIX C

TECHNICAL STANDARDS AND SPECIFICATIONS

Document Distributor MTO Library Website Abbreviation and Symbols Manual Publications Ontario MTO Library Website AutoCAD Drawings – Structural Library Publications Ontario MTO Library Website AutoCAD Standards Guide Publications Ontario MTO Library Website Bailey Bridge Manual Publications Ontario MTO Library Website Bridge Clearance and Load Restriction Manual Publications Ontario MTO Library Website Canadian Bridge Analysis System (CANBAS) Publications Ontario MTO Library Website Canadian Bridge Analysis System (CANBAS) Examples Manual Publications Ontario Canadian Bridge Analysis System (CANBAS) Input Instruction MTO Library Website Manual Publications Ontario MTO Library Website Canadian Highway Bridge Design Code Publications Ontario Canadian Portland Cement Association “Thickness Design for Canadian Portland Cement Concrete Highways and Street Pavements” Association MTO Library Website Cathodic Protection Manual for Concrete Bridges Publications Ontario Class Environmental Assessment for Provincial Transportation MTO Website Facilities (2000) Publications Ontario MTO Library Website Commercial Site Access Policy and Standards Manual Publications Ontario MTO Library Website Commercial Vehicle Survey Customized Report Publications Ontario MTO Library Website Concrete Culvert Design and Detailing Manual Publications Ontario MTO Library Website Construction Administration and Inspection Task Manual Publications Ontario MTO Library Website Construction Change Order Manual Publications Ontario MTO – Regional Contracts Construction Contract Administration Regional Memoranda Office Design-Builder Performance and Selection System, Design- Builder Reviews and Design-Builder Infraction Reports – Process MTO Website Guide Design-Builder Quality Control (QC) Plan – Process Procedures MTO Website Guide

301

MTO – Regional Contracts Design-Build Contractor Performance Rating Guideline Office MTO Library Website Contract Design Estimating and Documentation Manual Publications Ontario MTO Library Website Corridor Control and Permit Procedures Manual Publications Ontario MTO Library Website Designated Sources for Materials Publications Ontario MTO Library Website DGS Design Graphic System User Manual Publications Ontario MTO Library Website Drainage Management Manual – Volumes 1,2,3 and 4 Publications Ontario MTO Library Website Electrical Engineering Manual Volume 1 – Electrical Design Publications Ontario MTO Library Website Electrical Engineering Manual Volume 2 – Electrical Maintenance Publications Ontario MTO Library Website Electrical Engineering Manual Volume 3 – C.D.E.D. Publications Ontario MTO Library Website Electrical Engineering Manual Volume 4 – ATMS C.D.E.D. Publications Ontario Environmental Guide for Contaminated Property Identification and MTO Website Management Publications Ontario Environmental Guide for Built Heritage and Cultural Heritage MTO Website Landscapes Publications Ontario

Environmental Guide for Erosion and Sediment Control During MTO Website Construction of Highway Projects Publications Ontario MTO Website Environmental Guide for Fish Habitat Publications Ontario MTO Website Environmental Noise Guide for Noise Publications Ontario MTO Website Environmental Guide for Patrol Yard Design Publications Ontario MTO Website Environmental Guide for Wildlife in the Oak Ridges Moraine Publications Ontario MTO Library Website Environmental Guidelines for Structural Steel Coating Publications Ontario Environmental Protection Requirements for Transportation MTO Website Planning and Highway Design, Construction, Operations and Publications Ontario Maintenance MTO Website Environmental Reference for Contract Preparation Publications Ontario MTO Website Environmental Reference for Highway Design Publications Ontario Exceptions to the Canadian Highway Bridge Design Code MTO Bridge Office CAN/CSA – S6-00-Sign Support Inspection Guidelines

302

MTO Website Environmental Standards and Practices User Guide Publications Ontario Field Guide for the Acceptance of Hot Mix and Bridge Deck MTO Library Website Waterproofing Publications Ontario Flexible Link Slab for Steel Girder Bridges MTO Bridge Office MTO Library Website Formwork and Falsework Manual Publications Ontario MTO Library Website Geometric Design Standards for Ontario Highways – Metric Publications Ontario Guideline for the Design of Snowmobile Bridges MTO Bridge Office Guidelines For Drinking Well Water Sampling and Testing In MTO Website Ministry of Transportation Activities Publications Ontario Design and Construction Design and Construction Standards Office Bulletins / Memos Standards Office MTO Library Website Highway Engineering Standards Drawings: Structural Publications Ontario MTO Library Website Highway Equipment Standards Manual Publications Ontario MTO Library Website Inspector’s Diary Publications Ontario MTO Library Website Integral Abutment Bridges Publications Ontario MTO Website Interim Guide to Environmental Assessment: Co-ordinating Environmental Policy and Provincial and Federal Legislative Requirements Standards Section MTO Library Website King’s Highway Guide Signing Policy Manual Publications Ontario MTO Library Website Laboratory Testing Manual (MTO) Publications Ontario MTO Library Website Maintenance Manual Publications Ontario MTO – Environmental Management of Excess Materials in Road Construction and Policy and Standards Maintenance Protocol Section (905-704-2104) MTO – Materials Manual for Condition Rating of Flexible Pavements (SP-024) Engineering and Research Office MTO – Materials Manual for Condition Rating of Rigid Pavements (SP-005) Engineering and Research Office MTO Library Website Manual of Standard Short Span Steel Bridges Publications Ontario MTO – Materials Mix Design Method for Recycled Hot Mix Engineering and Research Office

303

MTO Website Environmental Policy and MTO Class EA Process Monitoring Program (Sept. 2000) Standards Section (905- 704-2104) MTO/DFO/MNR Protocol for Protecting Fish and Fish Habitat on MTO Website Provincial Transportation Undertakings (2006) Publications Ontario MTO/MOE Memorandum of Understanding on Permits to Take MTO Website Water (2006) Publications Ontario MTO Website MTO Environmental Glossary Publications Ontario MTO Library Website MTO General Conditions of Contract Publications Ontario MTO Library Website MTO Soil Classification Manual Publications Ontario MTO Library Website Ontario Bikeways: Planning/Design Guidelines Publications Ontario

rd MTO Library Website Ontario Highway Bridge Design Code (3 Edition, 1991) Publications Ontario MTO Library Website Ontario Highway Traffic Volumes 1988 – 2002 Publications Ontario OPS Specifications for Roads and Municipal Services, Volume 1, MTO Library Website General Conditions of Contract and Specifications for Publications Ontario Construction (Division 1 to 9) OPS Specifications for Roads and Municipal Services, Volume 2, MTO Library Website Specifications for Material Publications Ontario OPS Specifications for Roads and Municipal Services, Volume 3, MTO Library Website Drawings for Roads, Barriers, Drainage, Sanitary Sewers, Water- Publications Ontario Mains, and Structures OPS Specifications for Roads and Municipal Services, Volume 4, MTO Library Website Drawings for Electrical Work Publications Ontario MTO Library Website Ontario Structure Inspection Manual Publications Ontario MTO Library Website Ontario Traffic Manual (OTM) Book 5 Regulatory Signs Publications Ontario MTO Library Website Ontario Traffic Manual (OTM) Book 6 Warning Signs Publications Ontario MTO Library Website Ontario Traffic Manual (OTM) Book 7 Temporary Conditions Publications Ontario Ontario Traffic Manual (OTM) Book 7 Temporary Conditions (Field MTO Library Website Edition) Publications Ontario MTO Library Website Ontario Traffic Manual (OTM) Book 11 Markings and Delineation Publications Ontario MTO Library Website Ontario Traffic Manual (OTM) Book 12 Traffic Signals Publications Ontario MTO Library Website Ontario Traffic Signal Control Equipment Specifications Publications Ontario Overcoating – Technical Assessment of Existing Coatings of Steel MTO – Bridge Office Bridges for Overcoating 304

MTO Library Website Pavement Design and Rehabilitation Manual Publications Ontario MTO Library Website Pesticides Spray Manual Publications Ontario MTO Library Website Pile Load and Extraction Tests, 1954 – 1992 Publications Ontario MTO Library Website Post - Tensioned Decks Publications Ontario Pre-stressed Concrete Manual for Quality Assurance of Bridges MTO Library Website During Construction Publications Ontario MTO Library Website Prioritized Contract Content Guidelines Publications Ontario Procedures for the Design of High Mast Pole Foundations MTO – Bridge Office MTO – Materials Procedures for Administration of Mineral Aggregate Extraction on Engineering and Research MTO Contracts Office MTO – Regional Contracts Progress and Final Payment Guidelines (July 2003) Office Property Request Manual MTO – Property Section MTO Library Website Provincial Highways Distance Table Publications Ontario MTO Library Website Remote Airport Lighting Manual Publications Ontario MTO Library Website Roadside Safety Manual Publications Ontario Seeding And Cover Quality Assurance Visual Inspection Field MTO Library Website Guide Publications Ontario MTO Library Website Short Span Steel Bridges Publications Ontario MTO Library Website Sign Support Manual Publications Ontario Standard Ministry Forms related to Construction Contract MTO - Regional Contracts Administration Services Office MTO Library Website Standards for Engineering Surveys, Version 2.0 Publications Ontario MTO Library Website Structural Financial Analysis Manual Publications Ontario MTO Library Website Structural Manual Publications Ontario MTO Library Website Structural Steel Coating Manual Publications Ontario MTO Library Website Structure Rehabilitation Manual Publications Ontario MTO Library Website Survey Book Publications Ontario

305

MTO Library Website Surveys and Plans Manual (Volume 1–3) Publications Ontario Traffic Control Signal Timing and Capacity Analysis for Signalized MTO – Traffic Office Intersections 1993 AASHTO Guide for the Design of Pavement Structures for AASHTO Rigid and Flexible Pavements MTO - Regional Contracts Applicable Ministry Directives and Regional Memoranda Office Central Region Operation Constraints Non-Standard SP’s MTO – Central Region Northwestern Region Geotechnical Investigation Minimum MTO – Northwestern Requirements, Version 1 Region Geotechnical Office Northwestern Region Geotechnical Pavements Design Thickness MTO – Northwestern Chart Region Geotechnical Office MTO – Northwestern Northwestern Region L:/ Drive Files Region P & D MTO – Regional Contracts Guidelines for Conducting ½ Cell Survey & Covermeter Survey Office Stormwater Management Requirement for Land Development MTO – Drainage Proposals Management Website MTO – Drainage Evaluation of Drainage Management Software Management Website

306

APPENDIX D

DESIGN-BUILD PROJECT MANAGEMENT STRUCTURE

In order to effectively develop, advertise and award a Design-Build contract, there needs to be a well-developed Project Management Structure.

For each Design-Build project, a Project Team shall be established to develop and deliver the project from start to finish. The Primary Project Lead role will be shared between the Engineering Project Manager (EPM) and the ACE as outlined in the table below. The Project Lead will be supported by a multi-disciplinary team, as with a traditional project.

Individual Project Team members will be need to be engaged in most aspects of project delivery i.e. RFP preparation, procurement of the Design-Builder and contract administration/oversight (design and construction). As the ministry gains experience with the Design-Build model, the number of members may be reduced. However, in the interim, representation by all functional offices involved in a particular project, as is typically done in traditional project delivery, is recommended. It is also recommended that Project Team members be individually selected based on their ability and desire to implement a new model for contract delivery and oversight.

For continuity purposes, it is imperative to maintain the same Project Team members throughout the life of the project.

Although some Project Team members may only be required on a part-time basis, it is imperative for the success of the project that the Primary Project Lead has the necessary commitment from Project Team members to contribute fully when required, and the authority to utilize their services effectively.

Specific roles and responsibilities for the Primary Project Lead, Associate Project Lead and Project Team members may change through the life of the project. As such, the table below describes the different phases of a Design-Build project along with the roles and responsibilities of each member.

307

DESIGN-BUILD PROJECT MANAGEMENT STRUCTURE Evaluation/Award Post Award Document Development During Advertising During Warranty (see Note 2) (During Design/Construction) Engineering Primary Project Lead Primary Project Lead Primary Project Lead Associate Lead Associate Lead Project • Prepares project scope as per SCR • In cooperation with • In cooperation with the • Attends project meetings with Design-Builder • Addresses design related issues Manager (EPM) • Prepares DB ready Prelim Design the ACE, coordinates ACE coordinates the • Reviews design submissions arising during warranty period package/report for inclusion in DB-EOI and/or responses to bid evaluation process and • Transmits all correspondence to Design- through ACE (see Note 1) RFP enquiries documentation with Builder through ACE • Forms Project Team as per traditional • Work with CMO support from the • Addresses design related issues raised by design/contract development and obtains input (Estimating Office) on Technical Advisors Design-Builder from regional technical offices (Technical preparation of the • Provides support to CA Advisors) and/or Head Office as required Official Estimate • Liaises with Program Planning • Prepares DB-EOI/RFP (with support from CIO) • Coordinates the preparation of the risk assessment (with support from CIO) • Coordinates Regional review • Coordinates executive review • Prepares regions estimate • Submits package to CMO (via CRO) for advertising • Manages issues • Provides internal reports as required CSA/ACE Associate Lead Associate Lead Associate Lead Primary Project Lead (CA) Primary Project Lead (CA) (see Note 3) • Provides input to SCR • Assists the EPM In • Assists the EPM in the • Coordinates meetings with the Design-Builder • Coordinates project warranty • Supports the EPM in establishing the Project responding to bid evaluation process. • Coordinates all project correspondence, reviews and associated Team enquiries payments, conformance issues documentation • Participates in the RFP development • Assists the EPM in • Coordinates field reviews • Coordinates meetings with the • Participates in the risk assessment process preparation of the • Coordinates project acceptance Design-Builder as needed • Develops Working Day estimate Official Estimate • Prepares performance report (rating) • Assists with design review • Provides feedback to EPM regarding design submission • Co-ordinates access to site during proposal preparation stage of project

308

Regional • Provide input to SCRProvide support to the • Assist the EPM in • Participate in the • Provide technical support during contract • Provide technical support during Functional EPM in developing the technical requirements responding to bid evaluation process • May assist with milestone inspections warranty Offices for the project enquiries • Assist with design reviews (see Note 4) • Participate in the RFP development • Provide support to CA • Participate in Technical Review • Participate in executive review

During Evaluation/Award Post Award Document Development During Warranty Advertising (see Note 2) (During Design/Construction) Field Monitors • May provide support to the EPM in developing • Assists the EPM In • Attends progressmeetings with Design-Builder • Performs warranty reviews (CSA, CSI and the technical requirements for the project responding to bid • Provides field monitoring activities (focus on QAO) enquiries safety, environment and milestone • Will provide varying levels of support to the inspections) EPM in developing the technical requirements • Assesses adherence to performance for the project (QAO may play a larger requirements (gathers performance indicators, advisory role at this stage) tracks non-conformances) • Assists with preparation of performance report (rating) • Assists with design review • Provides or supports Contract Administration Field • Advise CA of non-conformances Assistance during the warranty period as (see Note 5.) identified during routine maintenance administrative duties Head Office • Provide support to EPM with development or • Provide support to • May provide technical • May provide technical support during contract • May provide technical support Functional review of technical provisions for project- EPM in preparation of expertise to the (HSB-MERO) during warranty period (HSB- Offices (HSB, specific issues (HSB-MERO) the Owner’s Estimate evaluation team (HSB- MERO) CMO, MERO) (CMO-Estimating MERO) Office) • Provide Bid Evaluation and award support (CMO-Estimating Office) Contract • Assists EPM with development and review of • Assists the EPM In • Participates in the • Provide support/advise throughout contract as • Provide support/advice throughout Innovations DB-EOI/RFP documents (including Risk responding to bid evaluation process needed. warranty period as needed Office Allocation Table for DB Major) enquiries • Support for identifying appropriate specifications for RFP

Notes: 1. Depending on the scope of work and at the discretion of the Region, the EPM could be from Planning and Design or Regional Structural Section 2. Award Process to follow current practice provided by Contract Management Office 3. ACE or CSA as the lead will be at the Region’s discretion. 4. Typically applies to functional engineering offices, Environmental section, Geotechnical,.... 5. Typically Maintenance Superintendent and/or Maintenance Coordinators

309

APPENDIX E

SUBMISSION INSTRUCTION NOTICES AND NOTICE OF NON-CONFORMANCE

Instruction Notice acknowledging receipt of submissions from the Design-Builder;

Suggested wording:

“The Ministry is in receipt of your submission for. A non-conformance has been identified and a Notice of Non-Conformance is attached.. The Ministry will not be approving the design submission since, as identified in the Contract Documents, the Design- Builder is solely responsible for design adequacy, accuracy, constructability, appropriateness regarding environmental requirements and conformance to all requirements of the Work.”

For submissions with a specified review time by the Ministry: send an additional Instruction Notice once the review is complete. Suggested wording:

“The Ministry has reviewed your submission forfor conformance to the Contract Documents. A non-conformance has been identified and a Notice of Non- Conformance is attached.. The Ministry will not be approving the design submission since, as identified in the Contract Documents, the Design-Builder is solely responsible for design adequacy, accuracy, constructability, appropriateness regarding environmental requirements and conformance to all requirements of the Work”

For submissions that have been determined by the Ministry to be in non-conformance: Include the “non-conformance” statement in the appropriate Instruction Notice above and issue a Notice of Non-Conformance. Suggested wording to be included in the Notice of Non- Conformance:

“In the opinion of the Ministry the submission foris not in conformance to requirements of the Work for the following reasons: As identified in the Contract Documents, the Design-Builder is solely responsible for design adequacy, accuracy, constructability, appropriateness regarding environmental requirements and conformance to all requirements of the Work. When, in the opinion of the Ministry, the design submissions are not in conformance, or contain significant errors, the Design-Builder will be required to correct the Work so that it conforms to the Contract Documents. The Design- builder shall stop construction of the Work that is not in conformance with the Contract Documents or any Work which may impede the correction of Work that is not in conformance with the Contract Documents, until such time as the Design-Builder corrects the Work so that it conforms to the Contract Documents at no cost to the Ministry.”

310

APPENDIX F

DESIGN-BUILD RECORD DOCUMENTS CHECKLIST

Contract Number

Items that are “greyed out” are deemed as not required for the Design-Build model however each should be assessed by the Project Team, including QAO, for applicability to a specific contract.

The Record Documents include, but are not limited to the following documentation:

Please check if included in final package, or comment on reason it is not included √ File # Documentation Record Documents Checklist to CCO Records of Services and Deliverables, according to the Construction Administration Agreement Records of inspections and verifications of Design-Builder’s work including QVE certificates Releases (Property Owners, Pits, etc.) Intents to Claim and related documentation Project Construction Report (to be prepared within 60 Days of completion of the construction contract) Design-Build Contractor Performance Rating (hard copy plus digital) Record Drawings N/A Design Package Evaluation (Hard copy and digital) Contract Drawings (complete package of Issued For Construction Drawings submitted by the Design-Builder) Contract Documents (including RFP, all addenda, Proposal, Agreement) Final Payment Certificate (including Design-Builder invoice in hard copy and digital format) N/A Itemized list of Breakdown Quantities with Payment References N/A Final Estimate Quantities and Cost Sheet Correspondence Folders (related to the contract) Minutes of all Meetings Instruction Notices (signed hard copies) All Field Books and pre-engineering notes (grade checks, field measured items showing all dimensions, original rock sections, roadway signs) (with index describing contents in detail) Contract Administrator’s Diaries Inspectors Diaries Design-Builder’s Traffic Signing Diary Traffic Accident Records including Police Reports N/A Survey Party Diary N/A Contract Signing Diary acknowledging granular and borrow deductions N/A Item summaries, summary quantity and detail sheets for all non PQP & Adjusted PQP Items that require calculations (including references to supporting field notes and all calculations for advanced payments)

311

List of Personnel on site, their position titles and dates of employment List of Field Books, Cross Section Rolls and Diaries, including a brief description of their content N/A Numbered Cross Section Rolls with tags, design rolls with construction revisions, topsoil piles, original rock after overburden removed and borrow pit rolls N/A Statement of Record of Working Days (with signatures) All Required Certificates (QVE, Certification of Components & Conformance, etc.) All Digital Files (CAS, Design-Build ,CPR, etc.) Shop Drawings Design-Builder’s Master Equipment List Extension of Time Request/Approval Change Proposal Documentation Substantial Performance Certificate Copy of Certificate of Completion List of Warranty Inspection Dates (include all actual site seeding and landscape planting dates) List of Outstanding Issues (claims, negotiations, etc.) Design-Builders Schedule (critical path) N/A CA’s Completed Design-Builder QC Checklist Deficiency Lists Summary of QC Major/Minor Deviations Service Providers Contract Administration QC Plan for CA Services (including Monitoring / Auditing Records (Only if Service Provider CA) QAO and CAP Reports N/A All Correlation Documentation N/A All Bonus/Reduction Calculations (e.g. completion incentives, lane rentals, A+B, waterproofing, covermeter, etc.) All Physical Test Results –QA All Acceptance Test Results (e.g. covermeter survey, waterproofing, line painting, geotextile, granular sealing, etc.) Electrical Service Manuals Illumination and Traffic Signals Quality Records Verified traffic signal PH-M-125’s ATMS inspection and testing records Specialty Work Quality Records New Product Quality Records Final half-cell and delamination survey records from Design-Builder and verification records by CA (including other structural as constructed related documentation as requested) Environmental Quality Assurance Records (diary for environmental quality control during construction, and the Design-Builder’s performance relative to same) Detailed Environmental Speciality Reports (e.g. fisheries, snakes, etc) MTO Class Environmental Assessment (EA) Process Monitoring Questionnaire

312

Excess Materials Disposal Agreements and Releases submitted by Design-Builder. Complete ‘Summary of Environmental Concerns and Commitments’ table Copies of all environmental approvals, permits and authorizations obtained by the Design-Builder for the work, including those that were initially obtained by the ministry and amended during construction by the issuing agency, or issued by the agency in the Design-Builder's name after contract award Environmental Monitoring Reports if any N/A Complete package of design calculations and revisions for all PQP items Invoice of Plans, Profiles, Notes, etc. (i.e. Packing Slip or Transmittal Record) List of benchmarks before and after construction (including restoration of destroyed monuments) from Design-Builder N/A Sketches of grids N/A Construction Grading Report and revisions or templates complete with recorded verification limits (signed by the inspector) N/A Notice to Design-Builder to review final quantities (Regional Construction Office) Truck Register CVORS N/A Scale Accuracy Inspections N/A Daily Truck Tares Overload Reports N/A Daily Summaries N/A Up-to-date Summaries N/A Cancelled Loads Report N/A All Weigh Tickets Change Orders (signed change orders, price agreements, invoices, estimates daily work records, justification for the change, documentation, etc.) Compaction Reports -QA One Point Proctor Tests (or control strip records) Gradations -QA (factor calculations for DB CPR) Grade certifications by Design-Builder and QA Grade Checks N/A Template Sheets/Grading Reports N/A All Earth and Rock Quantity Calculations (field adjusted volume reports, HDS files, boulders, etc.) N/A Muskeg Excavation Cross-Sections N/A Underfill Stripping Measurements (including calculation adjustments) Pit and Quarry After-Use Report (for all applicable commercial, wayside and permit sources) NEW – Summary Report of Total Aggregate Use (includes aggregate produced from ROW rock cuts, qty of material produced from reclamation processes, qty of recycled materials used in pavement/structure elements) Report form under development – Nov 2011 N/A Rock Blasting Reports (include drilling patterns)

313

Asphalt Mix Designs All QA Tests Miscellaneous Items Quality Assurance/Acceptance Records Records documenting how property related commitments and construction concerns have been addressed Material adjustment factor calculations based on QA test results (for DB CPR purposes) N/A Distribution Checks A/C QA Test Results N/A A/C Indexing Calculation N/A A/C for bidding purposes calculation N/A Hot Mix Summaries – hard copy and digital (copies should also be forwarded to Bituminous Office) Concrete Mix Design N/A Concrete Batch Records Compressive Strength Test Results for acceptance and DB CPR Compressive Strength (adjustment factor calculations for DB CPR) Hardened Air Void Tests (adjustment factor calculations for DB CPR) Notification of Placement of Structural Concrete All other related test results and documentation List of borrow pits, waste disposal areas and the related release forms Design-Builder’s Consent to Sublet List of Subcontractors Company Compliance Records complying with the statute and regulations regarding use and transportation of nuclear density gauges. Photographic and Video Records • Provide full video record (both directions) of construction zone at one week intervals: • Provide photographic records of the following (but not limited to) significant incidents/accidents, potential claim or delay situations, signing configurations/changes, unusual or critical field operations, or other situations as appropriate at the discretion of the CA; • All records are to accurately record the date and time they were recorded; • Photographic records relating to accidents, claims, or potential legal action are to be of conventional (not digital) nature; • Records of complex matters are to be accompanied by a narrative or diary reference that clarifies the situation.

314

Submitted By: Position:

Service Provider Name:

Reviewed By (Ministry CSA):

Date:

Received in Office (date): Received By:

Distribution: 1) Area Contract Engineer 2) Contract Administrator 3) Head Contract Services

315

APPENDIX G

DESIGN-BUILD COMMUNICATION MATRIX

It is strongly recommended that the Project Lead, the CSA and the CA develop a communication matrix to assist in ensuring appropriate distribution of all communications.Attached below is a sample of a communication matrix that could be used. Note this is a sample only and should be customized specifically to each Design-Build project. (NOTE: A communication matrix template based on the sample below is available on the CIO SharePoint site at: https://intra.sse.gov.on.ca/mto/PHM/ho/cmob/cio/Pages/Design-Build.aspx)

316

Design-Build Communications Matrix Contract: DB-20XX-XXXX Project Title: Distribution 1 1 1 Stakeholders Primary Contact Group MTO Regional Functional Offices Utilities Other

Communication

2

Originator

Type Builder

Gas OPP DFO MNR MOE Hydro Traffic Traffic Railway Contract Contract Engineer Engineer Geotech/ Structural Foundations Environment Administrator Administrator Municipalities Design - AreaContracts ProjectManager Contract Services Quality Assurance Regional Contracts Management Office Contract Services Design-Builder Schedule Design-Builder √ √ √ √ √ Updates Design submissions Design-Builder √ √ √ √ √ √ √ √ √ required in RFP PHM125 Design-Builder √ √ √ √ Meeting Agendas/Minutes Design-Builder √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ √ Monthly Invoice Design-Builder √ Payment Certificate and Contract Supporting √ √ √ Administrator Documentation Project Construction Contract √ √ √ √ Report Administrator Instruction Notice/ Notice Contract √ √ √ √ √ of Non-Conformance Administrator

√ = First point of contact for submission √ = Mandatory Distribution List √= Distribute as appropriate relative to submission content NOTES: 1. Distribution list (headings) should be customized to be project specific (e.g. CP Rail, Union Gas, City of London could be more specific Stakeholders for a project) 2. Communication Type list should be customized for your specific project (e.g. you may want to break down the “Design Submissions” into more specific categories such as “Foundation design submissions”, “Structural design submissions”, “Electrical design submissions” etc.). Use your RFP and the DB Contract Admin Manual to complete an appropriate listing of items (or groupings of item types) for your project.

317