Social Monitoring Report

Project Number: 43574-025 December 2018

Period: Inception – June 2018

IND: Major District Roads Improvement Project

Submitted by: Uttar Pradesh Public Works Department

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Semi-annual Social Monitoring Report Inception to June 2018

Loan 3386 –IND Uttar Pradesh Major District Roads Improvement Project

June 2018

Uttar Pradesh Major District Roads Improvement Project Uttar Pradesh Public Works Department 96,Mahatma Gandhi Marg, Lucknow

0

TABLE OF CONTENT DESCRIPTION PAGE NO.

Glossary 2 Project Fact Sheet 3

Section

A Project Introduction & Background 4

B Social Safeguard Categorization 4

C Purpose of the Report 4

D Details of Sub-projects 5

E Institutional Arrangements 7

F Land Acquisition &Resettlement Impacts 7 G Sub-Project (Road) wise Status of Implementation of Resettlement Activities 9

H Cut-off Date 19 I Loss of Common Property Resources (CPR) 19 J Public Consultations& Disclosures 20 K Grievance Redress Mechanism 21 L Compliance status with loan covenants 22 M Conclusion 24

Annexure

1 Sub-project wise Site Visit Photographs 25

2 Translated approved R &R Policy printed by UPPWD 28

3 Constitution of GRC 40

1 GLOSSARY

Compensation: Payment in cash or in kind for an asset or a resource that is acquired or affected by a project at the time the asset needs to be replaced.

Cut-off date: The completion date of the census of project-displaced persons is usually considered the cut-off date. A cut-off date is normally established by the borrower government procedures that establish the eligibility for receiving compensation and resettlement assistance by the project displaced persons. In the absence of such procedures, the borrower/client will establish a cut-off date for eligibility.

Displaced persons: In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihood) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

Entitlement: Resettlement entitlements with respect to a particular eligibility category are the sum total of compensation and other forms of assistance provided to displaced persons in the respective eligibility category.

Host communities: Communities receiving physically displaced persons of a project as resettlers.

Income restoration:Re-establishing productive livelihood of the displaced persons to enable income generation equal to or, if possible, better than that earned by the displaced persons before the resettlement.

Meaningful consultation: A process that (i) begins early in the project preparation stage and is carried out on an ongoing basis throughout the project cycle; (ii) provides timely disclosure of relevant and adequate information that is understandable and readily accessible to affected people; (iii) is undertaken in an atmosphere free of intimidation or coercion; (iv) is gender inclusive and responsive, and tailored to the needs of disadvantaged and vulnerable groups; and (v) enables the incorporation of all relevant views of affected people and other stakeholders into decision making, such as project design, mitigation measures, the sharing of development benefits and opportunities, and implementation issues.

Physical displacement: Relocation, loss of residential land, or loss of shelter as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

Replacement Cost: Replacement cost involves replacing an asset at a cost prevailing at the time of its acquisition. This includes fair market value, transaction costs, interest accrued, transitional and restoration costs, and any other applicable payments, if any. Depreciation of assets and structures should not be taken into account for replacement cost. Where there are no active market conditions, replacement cost is equivalent to delivered cost of all building materials, labour cost for construction, and any transaction or relocation costs.

Relocation assistance: Support provided to persons who are physically displaced by a project. Relocation assistance may include transportation, food, shelter, and social services that are provided to the displaced persons during their relocation. It may also include cash allowances that compensate displaced persons for the inconvenience associated with resettlement and defray the expenses of a transition to a new locale, such as moving expenses and lost work days.

2 Project Fact Sheet

Loan number 3386 - IND

Uttar Pradesh Major District Roads Improvement Project Project (UPMDRIP)

Uttar Pradesh Public Works Department (UPPWD) Executing Agency

Monitoring Period Covered Inception to June 2018

3 Semi-annual Social Monitoring Report

A. Project Introduction and Background 1. Uttar Pradesh is ‘s most populous state with population of about 200 million. The state also has the largest rural population in the country. While the dependence on agriculture is high, the road network is not very well developed: the state has a road network density of about 72 km per 100 sq. km, as against the national average of 107. The Government of Uttar Pradesh (GoUP) has a long-term program to improve the Core Road Network (CRN) and, as part of this program, has received financial assistance from ADB for the Uttar Pradesh Major District Roads Improvement Project (UPMDRIP) – hereinafter referred as ―the Project.‖ The UPMDRIP seeks to upgrade and rehabilitate about eight (8) major district roads (MDR) for a total of 431 km, thereby improving connectivity and fostering inclusive economic growth. The estimated cost of the project is about $428 million, of which $300 million would be financed by ADB as a project loan. The Executing Agency (EA) for the project is Uttar Pradesh Public Works Department (UPPWD). 2. The Project aims to improve the connectivity to the neglected area by improving the road infrastructure and providing connectivity, which will contribute towards the expansion of economic opportunities, hence reducing the interstate disparities within India. The project will also result in improved livelihood and trade opportunities for non-urban population. B. Social Safeguard Categorization 3. The Project is categorized as 'A' for involuntary resettlement (IR) as the Safeguards Policy Statement,(SPS)2009. The project will mainly remain confined within the existing right of way (RoW) that is owned by UPPWD. The Right of Way (RoW) ownership of UPPWD for all road corridors has been verified with the local Land Revenue Records Department and the project does not require private land acquisition. Within the RoW, the corridor of impact (CoI) has been adjusted to ensure that resettlement impacts are minimized. However, the project will still trigger resettlement impacts, mainly resulting from the demolition of external sections of structures (residential and commercial), as well as auxiliary structures belonging to non-titled households (NTH). The identification and verification of affected household reveals that there is no any adverse impact on Indigenous people. Thus, IP category continues to be ‗C‘ during the reporting period.

C. Purpose of the Report 4. The main objective of this monitoring report is to supervise the subproject impacts and to determine whether resettlement goals have been achieved and more importantly whether livelihood and living standards have been at least restored and/or enhanced and suggesting the suitable recommendations for improvement. This report covers resettlement and social safeguard monitoring results to comply with the spirit of ADB policy to ‗enhance stakeholders‘ trust ‗in and ability to engage with ADB, and thereby increase the development impact (of projects) in which disclosure of safeguard monitoring is a prominent aspect.

4 D. Details of subprojects 5. The project involves rehabilitation/reconstruction and widening of eight existing roads totalling 431 kilometres in length. The UPPWD has prepared seven Resettlement Plans (RP) and one Due Diligence Report (DDR) during the processing of the loan with the objective to assist the affected people to improve or at least restore their living standards to the pre-impacted level. The seven RPs capture the involuntary resettlement impacts arising out of the proposed improvements to eight roads spread over 12 districts. The list of subprojects road is provided in table 1 and the index map giving the location of the different sub-projects is presented as Figure 1. Table 1: Details of Sub-projects

Length Contract Physical Sl. Name of Road Safeguards District (KM) Award Progress No. (Sub-project) Category Status (%) Hussainganj – 36 Contract 1.72 1 Hathgaon-Auriya- Fatehpur Awarded on A Alipur Marg 15 Dec 2016 30 Contract 7.38 2 Nanau to Dadau Marg Awarded on A 15 Dec 2016 Muzaffarnagar to Muzaffarnagar 59 Not 3 A Baraut Marg and Baghpat Awarded Haliyapur to 961 Contract 4A-12.36 4 Kurebhar—Belwai Sultanpur Awarded on A 4B-13.34 Marg 15 Dec 2016 Kaptanganj-Hata- 84 Not Gauribazar Marg Deoria and Awarded 5 A and Kaptanganj to Kushinagar Naurangiya Marg Bulandshahar to 36 Not 6 Anoopshahar Bulandshahar Awarded C Marg Mohanlalganj – Lucknow and 54 Not 7 Morava- Unnao Awarded A UnnaoMarg - and 36 Not 8 Marg Kashiram Awarded A Nagar 431 Total length

1 Total road length is 95.628, 0.000 to 49.272 = 49.272 and 56.000 to 102.356 = 46.356 Total = 95.628, rounded off to 96.

5 Figure 1: Location of the roads under the Project

6 E. Institutional Arrangements 6. The implementation of RP is being carried out through a set of institutions at various levels within the implementation framework. The organizations involved – their roles and responsibilities – in the implementation of the plan are described here. (i) Staffing at the EA level:

7. A Chief Engineer (CE) at UPPWD headquarters is responsible for overall implementation of the project who is assisted by the one Project Director (PD). The officer of the level of Executive Engineer has been designated as Safeguards Project Officer (SPO) at the level of Executive Engineer (EE). The SPO will be supported by an outsourced Resettlement Individual Consultant, whose selection process has been completed and is likely to join in the month of July 2018. The Project Implementation Units (PIUs) has been created in Kanpur, Lucknow and Moradabad Divisions and are responsible for the RP implementation at the subproject road level. Each PIU is headed by a Superintending Engineer and supported by an Assistant Safeguards Focal (ASF), responsible for the management of both the environmental and social safeguards at the subproject road level. 8. The EA is supported by the Construction Supervision Consultants (CSC) and Non-governmental organisation (NGO) in implementation of resettlement activities.CSC has mobilised its Resettlement on 27th February 2018. Out the 24 man-months available, around two man- months has been consumed till the end of the reporting period (June 2018). The NGO named Manavadhikar Samajik Manch (MASM) has been engaged to assist in the implementation of all RPs under the UPMDRIP since 3rd October 2018 for tenure of 10 months. The NGO is acting as facilitator and be a link between the PIU and the affected community. EA is ensuring that adequate resources are allocated to the NGO. During the inception mission, the ADB has already provided training to the newly appointed staff in the Environment and Social Cell and PIU focal points. F. Land Acquisition &Resettlement Impacts 9. The project does not involve any acquisition of land and is mainly remained confined within the existing right of way (RoW) that is owned by UPPWD. The Right of Way (RoW) ownership of UPPWD for all road corridors has been verified with the local Land Revenue Records Department and the project does not require any private land acquisition. 10. It is estimated that 934 non-titled households (NTHs) will be affected by the project, for a total number of 7103 affected persons. Only 27 private structures will be severely affected, leading to the physical relocation of its owners. The EA through NGO is conducting the identification and verification survey to verify the final impacts. The owners will receive appropriate compensation and relocation assistance as per the agreedentitlement matrix. A total of eight social safeguards documents were prepared during the processing of UPMDRIP, including seven Resettlement Plans and one Due Diligence Report (DDR). The summary of impacts as per the approved resettlement plans are provided in Table 4.

7

Table 4: Land Acquisition & Impacts as per the approved RP

-

Type of Impact

-

-

-

-

-

-

-

Diwai Diwai

Morava

-

-

Auriya

Rudrapur Rudrapur

- 81C)

- Belwai

Soron Marg Soron

Dadon Marg Dadon

(82W)

-

-

(MDR25E) (MDR25E)

(MDR

(MDR 45W) (MDR

Alipur Marg Alipur

&Kaptanganj

Chowk (58W) Chowk Marg

Hussainganj Hussainganj

(MDR66E,69 C) (MDR66E,69

Bulandshahar

Muzzaffarnagar Muzzaffarnagar KaptanganjHata

Hathgaon

Baraut Marg(135W) Baraut

Anoopsahar Nanau

Aliganj

Naurangia Marg 031) Marg Naurangia

UnnaoMarg(MDR52C)

Gouribazar

Mohanlalganj Total Kurebhar to Haliyapur 133 Total Persons Affected 0 213 7 918 1182 727 223 2503 7103

Total Households Affected including Tenants 0 32 177 105 170 130 33 329 934

Vulnerable Households 0 3 10 10 25 29 13 80 170 Affected

Severely Affected 27 Households 0 0 0 0 0 15 3 9

Households Affected by 0 0 0 0 0 0 0 0 0 Land Acquisition

Households Affected by 796 Impact on Structures 0 32 148 150 156 120 23 167

Households Fully 0 0 0 0 0 15 3 9 27 Displaced

Households Affected by 672 loss of income 0 8 157 22 91 90 27 277

Households losing 0 0 0 0 0 0 0 0 0 trees/crops

Structures fully affected 0 0 0 0 0 15 3 9 27 (private)

Structures partially 817 affected (private/Public) 0 38 148 106 242 105 20 158

CPRs affected 13 95 36 55 85+(1 57 16 38 396 Govt Building 3 15 7 Religious structures (Include (Include 3 2 (Included 4 6 5 45 affected d in d in in CPR) CPR) CPR)

8 G. Sub-project wise status of implementation of resettlement activities 11. The identification and verification survey has been conducted on the basis of the final design for the five subproject roads by the NGO. The survey revealed that 605 NTHs are likely to be impacted, out of which 339NTHs are as per the approved RPs and 266 NTHs are newly identified while 170 NTHs identified in the RP will be avoided. The changes are due to minor adjustment of alignment within the ROW. Out of 291 CRPs identified in the RP, only 102 will be impacted and 39 CPRs are newly identified. The verification survey for remaining roads will be conducted in the second half of 2018. The preparation of the micro plan is under process (I) Hussainganj –Hathgaon-Auriya- Alipur Marg-MDR‐81C 12. The sub-project road (Figure2) is falling under jurisdiction and starts near the town of Hussain Ganj at Km. 0+000 (Fatehpur Dalmau Road connecting to Raibareli) about 15 km away from district headquarters and ends at Km. 48.600 near Afoi, (Kada Road). The total length of the project road is 48.000 Km. However, the effective length under sub-project will be 36.000 Km, since 12.600 Km of road i.e. from Km 0.000 to Km. 12.600 has already been upgraded by UPPWD.The MDR 81C is also well known as ―Mughal Road‖. Figure2: Hussainganj to Alipur Marg

Contractor M/s Gawar – Jagdish Saran Upgrading of MDR No. 81C Hussainganj- Hathgaon-Alipur Road (Section from km 13.000 to Name of Work km 48.676) (Package No. P01/UPMDRIP/2015-16) in District Fatehpur Length of Road 35.676 km Total Project Cost as per Contract Agreement Rs. 108,62,10,601 Date of contract agreement 15.12.2016

Date of Commencement 21.02.2018

Construction Period 24 Month

Completion Date 20.02.2020

9 13. The Right of Way (RoW) is owned by the State Government and administered by UPPWD. Overall, the RoW varies from 12.067 meters to 41.797 meters. The confirmation of the ownership of the ROW was obtained by verifying the boundaries of the legal RoW and private properties within and near the Corridor of Impact (CoI) with UPPWD‘s records and the revenue department‘s maps. 14. The RP has been prepared for a total length of 36 km. The sub-project road will have significant resettlement impact on 130 NTH, representing 727 persons. Among these, 15 households will be physically relocated due to improvement of the road and 61 CPRs. Out of 61 CRPs, 43 are hand pumps and 18 are community property resources and government properties. 15. The identification and verification survey has been conducted by the NGO in the month of March 2018 on the basis of the final design along with the engineers from CSC and PIU. The survey confirmed that implementation of the subproject does not cause any land acquisition, however, is likely to impact 174 NTHs. Out of which 107 NTHs are as per the approved RP while as 67 NTHs are newly identified. The change is due to minor adjustment of alignment within the ROW. Further, the impact on the remaining 23 NTHs identified in the RP will be avoided. Out of 61 identified in the RP, CPRs only 23 will be impacted. The preparation of the micro plan is under process.

(II) Nanau to Dadau Marg (MDR-82W)

16. The sub-project road (Figure3) Nanau to Dadon section of MDR82W starts near Nanau village forming a T intersection with NH-91 at Km. 0.000 and ends at Km. 30.000 near Dadau. The project passes through the district of Aligarh for a total length of 30.000 Km. Figure 3: Nanau to Dadau Marg

Contractor M/s PNC Infratech. Ltd. Name of Work Upgradation of MDR No. 82W Nanau-Dadau Marg (Section from km 0.000 to km 30.000) (Package No. P02/UPMDRIP/2015-16) in District Aligarh Length of Road 30 km

10 Contract Agreement no. 99/UPMDRIP/2016-17 dated 15.12.16 Total Project Cost as per Contract Agreement Rs. 119,94,79,308 Date of Bid submission 06.04.2016 Date of contract agreement 15.12.2016 Date of Commencement 08.11.2017 Construction Period 24 Months Completion Date 07.11.2019

17. This subproject involves reconstruction and widening of the 30 km long road corridor. Nanau- Dadau Marg (MDR-82W), of a total length of 30 km. The sub-project road will have minor resettlement impact on 177 households including 29 tenants, representing 1337 persons. No household will be physically relocated. The Right of Way (RoW) is owned by the State Government and administered by UPPWD. Overall, the RoW varies from 12 mtrs to 42 mtrs. The confirmation of the ownership of the ROW was obtained by verifying the boundaries of the legal RoW and private properties within and in the vicinity of the Corridor of Impact (CoI) with UPPWD‘s records and the Land Revenue Department‘s maps. The verification of census, survey and land records confirm that the project does not involve private land acquisition. 18. In order to minimize resettlement impacts, the RoW has been minimized to the corridor of impact of 12 meters in urban areas and14 meters in rural areas. In some very congested areas such as Chharra and Dadau, the COI has been restricted to eight meters. In RP 36 common property resources are identified, most of which are handpumps(29),one well, one clinic,one hospital, two temple boundry, one police chowki and one bus stop. After verification 12 CPRs have been verified, those are two temple boundaries, one well, the boundary walls of one hospital, others two and two government properties are partially affected (one police chowki and one bus stop). 19. After verification by the NGO, 257 structures have been Identified and verified. Out of 257, 108 HH verified which were already identified in RP and 149 are new identified HH. There are 69 HH which were identified in RP but will not be affected as per proposed ROW. Preparation of Micro plan is under process.

(III) Muzaffarnagar to Baraut Marg (MDR-135W) 20. The sub-project road (Figure 4) starts near the town of Muzaffarnagar at Km. 3.000 and ends at Km. 62.000 near Baraut town. The project passes through the two districts of Muzaffarnagar and Baghpat for a total length of 59.000 Km. The contract for the subproject is yet to be awarded.

11 Figure 4: Muzaffarnagar to Baraut Marg

R&R Impacts as Per RP

Total Persons Affected 213 Total Households Affected including Tenants 32 Vulnerable Households Affected 3 Severely Affected Households 0 Households Affected by Land Acquisition 0 Households Affected by Impact on Structures 32 Households Fully Displaced 0 Households Affected by loss of income 8 Households losing trees/crops 0 Structures fully affected(private) 0 Structures partially affected (private) 38 CPRs affected 95 Religious structures affected 3

21. After verification by the NGO, 46 structures have been verified. Out of 46, 32 HH verified which were already identified in RP and 14 are newly identified HH. Identification and verification had been completed by NGO and report is to be submitted shortly.

12

(IV) Haliyapur to Kurebhar—Belwai Marg (MDR66E,69 C) 22. The sub-project road (Figure 5) Haliyapur to Kurebhar section of MDR-66E and MDR-69C starts near Haliypur village at Km. 0.000 and ends at Km. 102.356 near Belwai. The project passes through the district Sultanpur for a total length 96.000 Km (Km 0.000 to 49.272 and Km 56.000 to 102.356). Figure 5: Haliyapur to Kurebhar Marg

Contractor M/s APCO InfratechPvt. Ltd Upgrading of MDR No. 66E Haliyapur-Kudebhar Road Name of Work (km 0+000 to 49+272) (Package No. P04A/UPMDRIP/2015-16) in Dist. Sultanpur and Length of Road 49.272 km+46.356 Km Contract Agreement no. 96/UPMDRIP/2016-17 dated 15.12.2016 Total Project Cost as per Contract Rs. 174,63,77,995+ Rs. 156,31,54,772 agreement Date of contract agreement 15.12.2016 Date of Commencement 03.10.2017 Construction Period 24 months Completion Date 02.10.2019

23. The Resettlement Plan (RP) for the sub-project road Haliyapur-Kurebhar Marg (MDR-66E and 69C), of a total length of 96 km has been prepared. The sub-project road will have minor resettlement impacts on 170 households, representing 1182 persons. No household will be physically relocated nor lose 10% or more of their productive assets. Technical and engineering constraints as well as social impacts were major concerns during the exploration of various alternative alignments. Overall, the project is designed to limit civil works in congested areas to pavement improvement and avoid impacting sensitive sites altogether. The Right of Way (RoW) is owned by the State Government and administered by UPPWD. Overall, the RoW varies from 12.43 mtrs to 32.81 mtrs. The confirmation of the ownership of the ROW was obtained by verifying the boundaries of the legal RoW and private properties within and in the vicinity of the Corridor of Impact (CoI) with UPPWD‘s records and the

13 revenue department‘s maps. The verification of census, survey and land records confirm that the project does not involve private land acquisition. However, there will impact on 170 households (156 non-title holder owners all of whom identified as encroachers and 14 tenants), representing a total of 1182 persons. 24. In RP 85 CPRs which includes 68 are hand pumps, 15 religious structures (mostly boundary walls, old permanent structures) a well, school boundary and Government properties (PWD office) 25. After verification34 CPRs consisting of 21 religious structures (mostly boundary walls),two well, two shrines, two boundary wall of outbuildings ,five platform and two school boundary are also affected due to this subproject. The COI has been reduced to avoid impacting sensitive structures. 26. After verification by the NGO, 128 HHs have been verified. Out of 128, 92 HHs verified which were already identified in RP and 36 HHs are newly identified. Further, 78 HHs were identified in RP but will not be affected as per proposed ROW. 27. Micro plan of 0+000 to 34+500 verified from RP has been submitted and approved by the Chief Engineer.Micro planfor the remaining part of the road is under preparation and will be completed by October 2018..

(V) Kaptanganj-Hata-GauribazarMarg and Kaptanganj to Naurangiya Marg (MDR-25E & ODR-31) 28. The sub-project road (Figure 6) Naurangiya to Kaptainganj to Varhaaj Marg falls under the districts of Deoria and Kushinagar and combination of two roads MDR-025 E and ODR -031. The total length of both the road section is 84.000 km. The contract for the road subproject is yet to be awarded.

Figure6: Kaptanganj-Hata-GauribazarMarg and Kaptanganj to Naurangiya Marg

The approved RP for the subproject envisages impact on 105 NTHs and 55 CPRs. The identification and verification survey has not yet started. NGO assured that survey will be completed by August 2018.

Upgrading of Kaptanganj-Hata-Gauribazar and Name of Road Kaptanganj to Naurangiya (MDR-25E & ODR-24)

Length of Road 84 Km

Contractor Not Awarded R&R Impacts as Per RP(Identification and Verification Process yet to be completed by NGO)

14 Total Persons Affected 918 Total Households Affected including 105 Tenants Vulnerable Households Affected 10 Severely Affected Households 0 Households Affected by Land Acquisition 0 Households Affected by Impact on 150 Structures Households Fully Displaced 0 Households Affected by loss of income 22 Households losing trees/crops 0 Structures fully affected(private) 0 Structures partially affected (private) 106 CPRs affected 55 Religious structures affected 7

(VI) Bulandshahar to Anoopshahar MargMDR-58W)

29. The sub-project road (Figure7) is located in . The road starts from Jatwai village (Km.20.000) to Debai chowk (Km. 56.000). The total length of the project road is 36.000 Kms. The existing carriageway configuration is two lanes with earthen shoulders having the width of carriageway vary between 5.50 m and 7.30 m. The road was upgraded in 2014 and the existing pavement condition is good to fair.

Figure7: Bulandshahar to Anoopshahar Marg

Upgrading of Bulandshahar to Anoopshahar Name of Road Marg(MDR-58W)

Length of Road 36 Km

Contractor Not Awarded R&R Impacts as Per DDR (Identification and Verification Process yet to be completed by NGO) CPRs affected 13 Religious structures affected 3

15 (VII) Mohanlalganj –Morava-Unnao Marg (MDR-52C)

30. The project road (figure 8) Mohanlalganj-Unnao section of MDR52C starts near Mohanlalganj town forming a T intersection of NH-24B at Km. 0.000 and end at Km. 54.00 near Taura village. The project passes through the districts of Lucknow and Unnao for a total length of 54.000 Km. The contract for the road subproject is yet to be awarded.

Figure8: Mohanlalganj to Morava Unnao Marg

The approved RP for the subproject envisages impact on 33 NTHs including 13 tenants and 22 CPRs. The identification and verification survey is yet to be started.

(VII) Aliganj-Soron Marg (MDR-45W)

31. The sub-project road (Figure9) Aliganj-Soron section of MDR45W starts at mile stone 26.087 near village and ends at Km 61.592 near Soron village. The project passes through the district of Kashganj for a total length of 36.000 Km.

Figure 9: Aliganj-Soron Marg

16

Name of Road Upgrading of Aliganj-Soron section of MDR45W

Length of Road 36 KM

Contractor Not Awarded R&R Impacts as per the approved RP

Total Persons Affected 2503 Total Households Affected including 329 Tenants Vulnerable Households Affected 80 9 Severely Affected Households Households Affected by Land Acquisition 0 Households Affected by Impact on 167 Structures Households Fully Displaced 9

277 Households Affected by loss of income Households losing trees/crops 0

Structures fully affected(private) 9

Structures partially affected (private) 158 CPRs affected 38

5 Religious structures affected

32. The Photographs of sub-project sites are appended as ―Annexure– 1‖.The details of resettlement impacts as per RPs in comparison to Identification and verification survey is presented in Table 5.

Table 5: Details of Resettlement Impacts as per RP vis a vis I&V Sl. As Per RP As Per Final I&V2 No. Non-Title CPRs Total Non-Title CPRs Total Name of Sub-project Holders Holders (NTHs) (NTHs) 1 Hussainganj to Alipur Marg 130 57 191 174 22 196

2 Nanau to Dadau Marg 177 36 213 257 12 269 3 Muzaffarnagar to Baraut Marg 32 95 124 46 17 63 4 Haliyapur to Kurebhar Marg 170 86 256 128 34 162 5 Kaptanganj-Hata-GauribazarMarg and Kaptanganj to Naurangiya 63 55 118 - - - Marg 6 Bulandshahar to Anoopshahar 0 13 17 Marg 13 0 17 7 Mohanlalganj to Morava Unnao - 33 16 - Marg 55 - 8 Aliganj-Soron Marg 329 38 367 - - - Total 934 396 1337 605 102 707

The details as available from identification and verification census done by NGO are presented in Table 6.

2 I&V are not started for sl no.5,7 and 8 at the reporting period.

17

Table 6: Identification and Verification of APs (NON-TITLE HOLDERS)

Sl. Total Number of APs included Total Remarks No. number of new APs in RP list but Name of Sub-project APs verified identified not affected as per RP within COI list 1 Hussainganj to Alipur I & V Marg 107 67 23 174 submitted on 25.04.2018 2 Nanau to Dadau Marg I & V 108 149 69 257 submitted on 02.05.2018 3 Muzaffarnagar to I & V done, Baraut Marg 32 14 - 46 data entry in progress Haliyapur to Kurebhar I & V 4 Marg 92 36 78 128 submitted on 23.01.2018 5 Kaptanganj-Hata- Gauribazar Marg and Not started 63 - - Kaptanganj to Naurangiya Marg 6 Bulandshahar to Anoopshahar Marg 0 0 0 0 I&V done. No NTH found 7 Mohanlalganj to Not started 33 - - Morava Unnao Marg 8 Aliganj-Soron Marg 329 - - Not started 9 Total 764 266 170 605

The status of Micro Plan preparation as on 30.06.2018 is presented in Table 7. Table 7: Status of Micro Plans

Sl. Non-Title CPRs Total Remarks Name of Sub- No. Holders project (NTHs)

1 Hussainganj to Alipur Under progress 174 22 196 Marg

2 Nanau to Dadau Under progress 257 12 268 Marg

3 Muzaffarnagar to Micro Plan is to be ------Baraut Marg prepared

Haliyapur to Partly Submitted 3 4 128 34 153 Kurebhar Marg

5 Kaptanganj-Hata- Micro Plan is to be Gauribazar Marg and prepared ------Kaptanganj to Naurangiya Marg

3Micro Plan and Identity/entitlement card for verified APs from RP chainage Km 0+00 to Km 34+500 submitted and approved.

18 6 Bulandshahar to Micro Plan is to be -- In Progress -- Anoopshahar Marg prepared 7 Mohanlalganj to Micro Plan is to be ------Morava Unnao Marg prepared

8 Aliganj-Soron Marg Micro Plan is to be ------prepared

9 Total 559 68 617

The number of Vulnerable NTHs in 3 Sub-projects for which I & V are prepared is presented in Table 8.

Table 8: Vulnerable NTHs (In 4 Sub-projects for which I & V completed)

Sl. Total number of NTHs Vulnerable NTHs Name of Sub-project No. 1 Hussainganj to Alipur Marg 174 12 2 Nanau to Dadau Marg 257 6 3 Haliyapur to Kurebhar Marg 128 39 4 Muzaffarnagar to Baraut Marg 46 3 Total 605 60

H. Cut-off Date 33.The cut-off date for the subproject is the date of completion of census survey and in case of land acquisition the date issuance of notification under The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 will serve as cut-off date those having legal title. Table 9: Package wise cut-off dates Sl. Name of Sub-project Cut -off Date No. 1 Hussainganj to Alipur Marg 4thMarch 2015

2 Nanau to Dadau Marg 18thMarch 2015 3 Muzaffarnagar to Baraut Marg 18th February 2015 4 Haliyapur to Kurebhar Marg 31st March 2015 Kaptanganj-Hata-Gauribazar Marg and Kaptanganj to 24th April and 26th April 5 Naurangiya Marg 2015 DDR/survey 16-18th March 6 Bulandshahar to Anoopshahar Marg 2015 7 Mohanlalganj to Morava Unnao Marg 4th June 2015 16th June 2015 8 Aliganj-Soron Marg

I. Loss of Common Property Resources (CPR) 34. There are 256 CPR properties which will be affected in the 8 sub-project roads and they are of different categories. The list of CPRs affected in the sub-project roads are presented in the table 10 below.

19

Table 10: Identification and Verification of Common Property Resources (CPR)

Total No. of Numbe CPRs Total Remarks CPRs r of included in (Affecte Sl. verified as new RAP list but d) Name of Sub-project No. per RP list CPRs not affected identifi within COI ed I & V submitted 1 Hussainganj to Alipur 16 6 45 22 on 25.04.2018 Marg 2 Nanau to Dadau Marg I & V submitted 06 6 30 12 on 02.05.2018 Muzaffarnagar to Baraut I & V done, 3 Marg 17 - 78 17 data entry in progress 4 Haliyapur to Kurebhar I & V submitted Marg 17 17 69 34 on 23.01.2018 Kaptanganj-Hata- Gauribazar Marg and Not Started 5 - - - - Kaptanganj to Naurangiya Marg Bulandshahar to Anoop Draft I & V 6 Sahar Marg 7 10 6 17 submitted on 24.05.2018 7 Mohanlalganj to Morava Not Started Unnao Marg - - - - Aliganj-Soron Marg Not Started 8 - - - -

9 Total 63 39 228 102

J. Public Consultations and Disclosures 35. In order to be closely associated with the community and enhance the public understandings of the project and address the issues pertaining to resettlement, various sections of affected persons (AP) and other stakeholders are being regularly consulted through focus group discussions (FGD), meetings and individual interviews during the implementation of the project. Besides the informal as well formal consultations with the UPPWD Officers are being regularly conducted by the NGO and CSC‘s Social Development Specialist during the implementation of the Project. The opinions of the stakeholders and their perceptions are regularly being obtained, discussed with the concerned authorities and resolved during these consultations. 36. The people were aware about the improvements to the existing road but were not well informed about the final alignment and proposed ROW of the project at the implementation stage. The APs welcomed the idea of road improvement and requested for the suitable compensation for their losses of various kinds. TheAPs assured full support to the project. The UPPWD printed the translated R&R policy in local language (Hindi) and NGO distributed that summary R&R policy to APs for proper disclosure about the compensation. This document (attached as ―Annexure -2‖) includes a

20 summary of the scope of the project, details of eligibility and entitlements and contact details of the EA and PIU. 37.The details of public consultations such as attendance sheet and minuets of meetings are not provided by NGO during the reporting period and they were instructed to provide the details in coming monthly and quarterly reports along with the relevant documents. There were 20 public consultations carried out during the reporting period as below and it is being done regularly to make the implementation more interactive and user-friendly and hence more transparent. Table11: Public Consultations

Name of Sub-project Number of Consultations Hussainganj to Alipur Marg 3 Nanau to Dadau Marg 6

Muzaffarnagar to Baraut Marg 1

Haliyapur to Kurebhar Marg 10 Kaptanganj-Hata-Gauribazar Marg and Kaptanganj to 1 Naurangiya Marg Bulandshahar to Anoopshahar Marg 1 Mohanlalganj to Morava Unnao Marg 1 Aliganj-Soron Marg 1 Total 20

Coordination Meetings with NGO, PIU officials, contractors and CSC

Number of meetings held 18

K. Grievance Redress Mechanism 38.A project-specific grievance redress mechanism (GRM) has been established to receive, evaluate and facilitate the resolution of displaced people‘s concerns, complaints and grievances about the social and environmental performance at the level of the Project. The GRM‘saim is to provide a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project. The project-specific GRM is not intended to bypass the government‘s own redress process, rather it is intended to address displaced people's concerns and complaints promptly, making it readily accessible to all segments of the displaced people and is scaled to the risks and impacts of the project. The APs are free to access the court system at any time. 39.The UPPWD up to end of this monitoring period has not received any grievance. In case any grievance is received by the project, the process detailed out in the resettlement framework will be followed in its resolution. At the field level the GRC‘s have already been formed for all the 3 Circles (Lucknow/Kanpur/Moradabad) as below. (i) On 04.10.2017 as amended from time to time for Lucknow vide letter nos.1206/900(1)/ADB/WBYC/17 dated 04.10.2017 and 676/901-WBYC-ADB/2018 dated 17.04.2018;

21 (ii) On 25.09.2017 as amended from time to time for Moradabad vide letter nos. 351/1com-WBPC/17 dated 25.09.2017 and 844/4Cm-WBPC/17 dated 30.10.2017; (iii) On 27.10.2017 as amended from time to time for Kanpur vide letter nos. 579/1M- WBPCK/17 dated 27.10.2017 and 149/IC(1)-WBPCK/2018 dated 09.04.2018.Few relevant copies of Office Orders are attached as ―Annexure -3‖.At the state level the GRC has also been formed first on 31.07.2015 and then on 14.09.2017 as amended from time to time vide letter nos. 543/2-01/UPADB/CEWB/2014 dated 31.07.2015 and 1186/2-19/UPADB/CEWB/2014 dated 14.09.2017. The GRC‘s are amended from time to time due to transfer of concerned officials and change in nominations of CSC representatives. L. Compliance status with the social safeguards covenants as stipulated in the loan agreement

40. The compliance status of social safeguards loan covenants as stipulated in the loan agreement is given in Table 12.

Table12: Status of compliance with social safeguards loan covenants

Item Description Status of complianc e/ Remarks Schedule Conditions for Award of Contract' Commencement of Work Complied 4 The Borrower shall ensure or cause the EA to ensure that no with. Para No. 6 Works contract is awarded which involves impacts on indigenous peoples or involuntary resettlement impacts until the EA has prepared and submitted to ADB the final RP based on the Project's detailed design, and obtained ADB's clearance of such RP. Schedule Resettlement Being 5 The Borrower shall ensure or cause the EA to ensure that all land Complied Para No. 5 and all rights-of-way required for the Project, and all Project with. facilities are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with (i) all applicable laws and regulations of the Borrower and the State relating to land acquisition and involuntary resettlement; (ii) the Involuntary Resettlement Safeguards; and (iii) all measures and requirements set forth in the RP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report. Schedule Without limiting the application of the Involuntary Resettlement Being 5 Safeguards or the RP, the Borrower shall ensure or cause the EA Complied Para No. 6 to ensure that no physical or economic displacement takes place in with. connection with the Project until: (a) compensation and other entitlements have been provided to affected people in accordance with the RP; and (b) a comprehensive income and livelihood restoration program has been established in accordance with the RP. Schedule Human and Financial Resources to Implement Safeguards Being 5 Requirements Complied Para No.8 The Borrower shall make available or cause the EA to make with. available necessary budgetary and human resources to fully implement the EMP and the RP.

22 Item Description Status of complianc e/ Remarks Schedule Safeguards — Related Provisions in Bidding Documents and Being 5 Works Contracts Complied Para No.9 The Borrower shall ensure or cause the EA to ensure that all with. bidding documents and contracts for Works contain provisions that require contractors to: comply with the measures relevant to the contractor set forth in the IEE, the EMP, and the RP (to the extent they concern impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report; make available a budget for all such environmental and social measures; provide the EA with a written notice of any unanticipated environmental, resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the RP; adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction; and reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project; Condition upon the completion of construction. Schedule Safeguards Monitoring and Reporting Being 5 The Borrower shall ensure or cause the EA to ensure the following: Complied Para submit Safeguards Monitoring Reports semi-annually for with. No.10 Involuntary Resettlement Safeguards and Indigenous Peoples Safeguards and annually for Environmental Safeguards to ADB and disclose relevant information from such reports to affected persons promptly upon submission; if any unanticipated environmental and/or social risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, and the RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; no later than 3 months from award of the first Works contract, engage or cause to be engaged qualified and experienced external experts or qualified nongovernmental organizations under a selection process and terms of reference acceptable to ADB, to verify information produced through the Project monitoring process, and facilitate the carrying out of any verification activities by such external experts; and Report any actual or potential breach of compliance with the measures and requirements set forth in the EMP or the RP promptly after becoming aware of the breach.

23 M. Conclusion

41. The UPPWD confirms that no civil works has commenced in the affected section where the non-titled households are affected. The civil work will be started only after the full disbursement of compensation and other assistance to displaced persons as per the agreed entitlement matrix of the RP. After preparation of micro-plans and verification surveys the appropriate payment of compensation to the AP‘s will be taken up as per the approved R & R policy and Resettlement Plans will be updated accordingly.

24 Annexure-1 SUB-PROJECT WISE SITE VISIT PHOTOGRAPHS MDR-66E (Haliyapur to Kurebhar Road) – District- Sultanpur

Project Road Starting Point at CPR close to existing road at Village- Haliyapur (Haliyapur to Belwai Ainpur, District- Sultanpur Road)

Statue of Late Shri IndraBhadra Singh The two CPRs at Village- Bajhana at Dhanpatganj Market (Nearest from existing road)

Initial Consultation with local peoples at Project Road End Point at Bibiganj Rahul Nagar Market Market (Belwai)

25 MDR-81C (Hussainganj to Alipur Marg) – District- Fatehpur

Project Road Starting Point at CPR close to existing road at Village- Hussainganj Market (District- KandhaiKaPurwa, District- Fatehpur) Fatehpur

Location of Mawai Market on existing road Project Road condition with existing Mile project (Hussainganj to Alipur Marg) Sonte towards Hathgaon Town

Location of Chilbila Market on existing road Project Road End Point at Alipur Market project (Hussainganj to Alipur Marg) (District- Fatehpur)

26 MDR-82W (Nanau to Dadau Road) – District- Aligarh

Project Road Starting Point at Nanau Project Road Starting Point at Nanau (Nanau to (Nanau to Dadau Road) - 1 Dadau Road) - 2

CPR (Shiv Ji Temple) close to existing road Sachin Brick Field Office at Village-Pilkhana at AzadpurChauraha

CPR Ma Bhagwati Temple close to existing Project Road End Point at Dadau road at Village- Sikandarpur

Annexure - 2

31

32

33

34

35

36

37

38

39

40 Annexure-3

41

42

43

44

45

46

47