Initial Environment Examination

Project Number: 44427-013 May 2018 (Addendum)

IND: State Road Sector Project Subproject : -Kachche (Antagarh) Road - Upgradation of 2 Lane to 4 Lane at three stretches under “Rajnandgoan Kachche” of Package-8

Submitted by

Public Works Department, Government of Chattisgarh,

This report has been submitted to ADB by the Public Works Department, Government of Chattisgarh, Raipur and is made publicly available in accordance with ADB’s Public Communications Policy (2011). It does not necessarily reflect the views of ADB. This report is an addendum to the IEE report posted in January 2013 available on https://www.adb.org/projects/documents/chhattisgarh-state-road-sector-project-rajnandgaon- kachche-antagarh-road-subproject-iee. This addendum to initial environment examination report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Addendum Initial Environmental Examination

Rajnandgaon -Kachche (Antagarh) Road Subproject (Upgradation of 2 Lane to 4 Lane at three stretches under “Rajnandgoan Kachche” of Package-8)

Loan Number: 2981-IND May 2018

IND: Chhattisgarh State Road Sector Project

Prepared by: Public Works Department, Government of Chhattisgarh for the Asian Development Bank.

The addendum initial environmental examination is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature

1

Contents

A. INTRODUCTION ...... 1 B. APPLICABLE ENVIRONMENTAL POLICIES AND OTHER LEGISLATIONS ...... 5 C. SUB-PROJECT DESCRIPTION ...... 5 D. APPROACH FOR ADDENDUM PREPRATION ...... 8 E. DESCRIPTION OF ENVIRONMENT ...... 8 F. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ...... 9 G. ENVIRONMENTAL MANAGEMENT ...... 10 H. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN ...... 11 I. GRIEVANCE REDRESS MECHANISM ...... 11 J. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE ...... 12 K. FIELD-BASED ENVIRONMENTAL DUE DILIGENCE ...... 12 L. CONCLUSION ...... 14

2

List of Tables

Table 1 - Details of Packages Under Group A Group B and Group C ...... 2 Table 2 - Package Wise Details of ADB Approved IEE Reports ...... 3 Table 3 - Details of Packages under Rajnandgaon-Kachche (SH-5)…...... 4 Table 4 - Change of scope from two to four lane in Package-8 ...... 6 Table 5 - Environmental Features Along the Sections ...... 8 Table 6 - Details of Tree Cutting ...... 10 Table 7 - Details of Payment to Forest Department ...... 10

List of Figures

Figure 1 - Project Location Map ...... 4 Figure 2 – Location map on google map from Km 1.800 to Km 4.500 at Rajnanadgaon...... 6 Figure 3 - Location map on google map from Km 35.000 to Km 36.600 at Dondi-Lohara …...... 7 Figure 4 – Location map on google map from Km 73.100 to Km 74.100 at Dondi ……………………..7 Figure 5 - Approved Typical Cross section for 4 Lane ...... 8 Figure 6 - Public Consultation at Dondi Lohara………...... 12 Figure 7 - Public Consultation at Dondi Town ...... 12

List of Annexures

Annexure I Rapid Environmental Assessment (REA) Checklist Annexure II Attendance Sheet of Public Consultation Annexure III Environmental Management Plan Annexure IV Environmental Monitoring Plan Annexure V Grevienece Readdressal Mechanishm Annexure VI Tree Cutting Permission (Package 8) Annexure VII Photographs of Field Visit

List of Acronyms

3 ADB Asian Development Bank CGPWD Chhattisgarh Public Works Department Ch. Chainage CSC Construction Supervision Consultant CSRSDP Chhattisgarh State Roads Sector

Development Project CSRSP Chhattisgarh State Road Sector Project CTE Consent to Establish Cum Cubic meter DFO Divisional Forest Officer DPR Detailed Project Report EA Executing Agency EARF Environmental Assessment and Review Framework EHS Environment Health Safety EMP Environmental Management Plan GoCG Government of Chhattisgarh GPS Global Positioning System GRC Grievance Redressal Cell GRM Grievance Redress Mechanism HIV/AIDS Human Immunodeficiency Virus/ Acquired Immune Deficiency Syndrome HMP Hot Mix Plant IEE Initial Environmental Examination IRC Indian Road Congress JV Joint Venture Km Kilometre LHS Left Hand Side M.T. Metric Tonne MDR Major District Road MoEF&CC Ministry of Environment Forest & Climate Change MoRTH Ministry of Road Transport Highways PIU Project Implementation Unit PM10 Particulate Matter < 10 micron PM2.5 Particulate Matter < 2.5 micron PUC Pollution Under Control PWD Public Works Department RF Resettlement Framework RHS Right Hand Side ROW Right of Way RMC Ready Mix Concrete SH State Highway SPCB State Pollution Control Board SPS ADB Safeguard Policy Statement, 2009

4

A INTRODUCTION 1. Roads are the main mode of transportation in Chhattisgarh. National highways (NH6, NH16 and NH78) provide good east-west connections with neighbouring states, and NH43 and NH200 provide the main north-south connection between Raipur, Bilaspur and . However, the remaining roads in Chhattisgarh are mostly in poor conditions, and not passable in the monsoon season. This is especially true for roads in southern and northern Chhattisgarh, where most of the tribal people live. The total road length in Chhattisgarh is about 36,000 km with the road density less than 30 km per 100 km2 against the national average of 100 km per 100 km2. To improve state roads, Chhattisgarh Public Works Department (CGPWD) in 2002–2003, prepared a 10-Year Master Plan for Road Sector Development (MPRSD) for the years 2003 to 2012. MPRSD aims to (i) promote development of six main road corridors, (ii) remove capacity bottlenecks from the network to better connect rural areas, and (iii) support socioeconomic development by improving road access and connectivity among growth centres. Based on MPRSD, Government of Chhattisgarh prepared and approved a priority investment program for improvement (rehabilitation, strengthening and widening) of about 5,000 km of state roads at an estimated cost of about Rs 105 billion ($2 billion). CGPWD has improved many roads through Government funds and support from funding agencies including 1249 Km roads with the help of ADB.

2. The Government of Chhattisgarh (GoCG) plans to improve the state road network under Chhattisgarh State Roads Sector Development Project (CSRSDP) with the assistance of Asian Development Bank and for that has applied a loan through Government of from the Asian Development Bank (ADB) for the improvement of about 916 kms state roads in Chhattisgarh. This road up-gradation and rehabilitation project will improve transport efficiency of the State road network which will contribute to expansion of economic opportunities and poverty reduction.

3. The Chhattisgarh Public Works Department (CGPWD), Government of Chhattisgarh is the Executing Agency (EA) for the project. The nineteen project roads have been divided into three Groups (Group A, B &C). The Consultancy services have been engaged for advisory and construction supervision, institutional strengthening, social rehabilitation and resettlement, environmental mitigation and road safety measures. The construction supervision consultancy works have been awarded to following agencies 4. This project comprises of widening and strengthening of state highways and major district roads. Under Group B roads, there are 8 packages (Package-1 to 6) of about 273.30km, under Group B roads, there are 8 packages (Package-7 & 8, Package-10 to 15) about 390.36 km and under Group-C roads, there are 4 packages (Packages -16 to 19) comprising of 191.944 km road network. The details of road package, name of the road and length under each package are given in table 1.

1

Table 1- Details of Package Under Group A , B and C S. Length Package Name of the Road District No. (km) Group –A 1. Package 1 Raipur – Bhaisa (SH-9) 36.50 Raipur Raipur & Baloda 2. Package 2 Bhaisa – (SH-9) 35.58 Bazar 3. Package 3 Nandghat – Baloda Bazar (SH-10) 42.19 Baloda Bazar 4. Package 4 Baloda Bazar - Gidhori (SH- 9) 49.04 Baloda Bazar 5. Package 5 Simga – Arang(Gullu) (SH- 20) 57.15 Raipur Raipur & 6. Package 6 Arang (Gullu) – Kurud (SH-20 / MDR) 52.84 Total Length of Project Road in Group –A (in KM) 273.30 Group –B 7. Package 7 Raipur-Urla-Patharidih-Berla-Kodwa (MDR) 48.03 Raipur and Package 8 and 8. Rajnandgaon- Kachche (SH-5) 77.13 Rajnandgaon 9. Package 10 Chandukuri Maro Umariya (MDR) 68.27 Bemetra Package 11 Rohanda-Foratari-Atariya- 10. 39.25 Rajandgaon (MDR) Package 12 Khairagarh - Donagargarh - Tumadlbod Kabirdham 11. 53.31 (MDR) 12. Package 13 Balod -Dhamtari (MDR) 30.67 Kabirdham 13. Package 14 Anda-Funda (MDR) 32.73 Durg and Balod 14. Package 15 Bodla-Traegaon-Daldali (MDR) 40.97 Balod Total Length of Project Road in Group –B (in KM) 390.36 Group –C 15. Package 16 Sheorinarayan – Birra – Champa (SH-9) 51.798 Janjgir-Champa Package 17 Bilaspur & 16. Ratanpur - Kota-Lormi (SH-10) 50.200 Mungeli Package 18 Lormi – Pandariya & Mungeli– Lormi with Mungeli & 17. 37.007 Mungeli bypass (SH-10/MDR) Kabirdham Package 19 Jairamnagar – Masturi – Malhar – Jondhara - Bilaspur & Baloda 18. 52.939 Lawan (MDR) Bazar Total Length of Project Road in Group –C (in KM) 191.944 Project Road Under Implementation in Group-A,B &C (in KM) 855.604

5. As required by ADB’s Safeguard Policy Statement 2009 (SPS 2009), an environmental assessment and review framework (EARF) was prepared and approved in 2012 to provide guidance on environmental

2

screening, assessment, institutional arrangements, and procedures to be followed, where components were not yet been fully defined and locations not identified. The EARF ensures that succeeding tranches comply with SPS 2009 and the applicable national laws and regulations

6. The initial environmental examination was carried out for all the subprojects falling under group A, group B and group C and the details of ADB approved IEE reports against each package are provided in table 2 below Table 2 - Package Wise Details of ADB Approved IEE Reports (Chhattisgarh State Road Sector Project)

ADB Approved IEE Report S. No. Package Name of the Road

1. Package 1 Raipur – Bhaisa (SH-9) Raipur to Balodabazar (SH-9); January 2013 2. Package 2 Bhaisa – Baloda Bazar (SH-9) 3. Package 3 Nandghat – Baloda Bazar (SH-10) Nandghat-Gidhoury (SH-10) July 2012 4. Package 4 Baloda Bazar - Gidhori (SH- 9) 5. Package 5 Simga – Arang(Gullu) (SH- 20) Simga-Kurud (SH-20); July 2012 6. Package 6 Arang (Gullu) – Kurud (SH-20 / MDR)

7. Package 7 Raipur-Urla-Patharidih-Berla-Kodwa (MDR) Raipur-Urla-Belra-Kodwa Road; January 2013 Package 8 Rajnandgaon Kachche 8. Rajnandgaon- Kachche (SH-5) (Antagarh) Road; January 2013 9. Package 10 Chandukuri Maro Umariya (MDR) Chandkhuri-Maro-Umariya Road; January 2013 Package 11 Rohanda-Foratari-Atariya-Khairagarh Dhamda -Khairagarh Road; 10. (MDR) January 2013 Package 12 Khairagarh - Donagargarh - Khairagarh-Tumdibod Road; 11. Tumadlbod (MDR) January 2013 12. Package 13 Balod -Dhamtari (MDR) Balod – Dhamtari Road; January 2013 13. Package 14 Anda-Funda (MDR) Anda-Funda Road; January 2013 14. Package 15 Bodla-Traegaon-Daldali (MDR) Badola-Daldali Road; January 2013 Package 16 Shivrinarayan-Birra-Champa 15. Sheorinarayan – Birra – Champa (SH-9) Road; January 2013 16. Package 17 Ratanpur - Kota-Lormi (SH-10) Ratanpur-Kota-Lormi-Pandaria- Mungeli Road; January 2013 Package 18 Lormi – Pandariya & Mungeli– Lormi with 17. Mungeli bypass (SH-10/MDR) Package 19 Jairamnagar – Masturi-Lawan Jairamnagar – Masturi – Malhar – Jondhara 18. Road; January 2013 - Lawan (MDR)

3

7. The ADB approved IEE report “Rajnandgaon- Kachche (SH-5)” approved in January 2013 cover one package i.e. package 8. During implementation stage change in scope of work was undertaken in package 8 from the original provided scope of work as per ADB approved IEE report. The detail of in the package ‘The details of in this package ‘Rajnandgaon- Kachche (SH-5)” is provided in table 3 while project location Map is given in figure 1. Table 3 - Details of Packages under Rajnandgaon- Kachhe (SH-5) Road

S. No Package Name of Package Length (Km) Location 1 8 Rajnandgaon- Kachche (SH-5) Road 77.13 Rajnandgaon

Figure 1 - Project Location Map

4

8. This report is addendum to the ADB-approved IEE report prepared for Rajnandgaon- Kachhe (SH-5) Road)”. The addendum to IEE report has been prepared due to change of scope from two lanes to four lanes at three different sections of under this package 8 9. This addendum to IEE report would capture information on the environmental consequences associated with change of scope. This report will also cover the field based environmental due diligence studies to ascertain presence of any residual environmental impacts since the sub-project was implemented without undertaking environmental assessments and suggest specific remedial measures, if any to address such residual impacts B. APPLICABLE ENVIRONMENTAL POLICIES AND OTHER LEGISLATIONS

10. As per the Ministry of Environment, Forest and Climate Change, GoI, vide its Notification No.S.O. 1533 dated 14-09- 2006 and its subsequent amendment, the environmental clearance is not applicable under the sub-project. Aside from SPS 2009, the project needs to comply with the requirements provided by the GoI acts, rules, notifications, standards, and policies and other state level guidelines that apply to the project. The relevant regulations and other legislations are given in chapter 2 of ADB approved IEE report, January 2013 are applicable for this subproject.

C. SUB-PROJECT DESCRIPTION

11. The project activities involve widening of existing roads to 2 – lane carriageway, within available ROW. The Rajnandgaoh Kacheche Road is 77.13 Km long. The road widening activities primarily will comprise of raising the embankment at certain locations and its stabilisation including construction of retaining wall if required especially near water bodies, overlay on the existing carriageway, junction improvement, and construction of minor bridges, culvert and RCC drain in built-up section. 12. The project road section of Rajnandgaon - Kachche Road is part of SH-5 and starts from Km 0.000 on SH-5 (at Union Chowk on NH-6 at Km 340.700) in Rajnandgaon and ends at Km 80.725 on SH-5 (border of & ). Total length of the project road was 80.725 Km. However, length from Km 0.000 to Km 1.800 and Km 60.200 & 62.000 has been excluded from the scope. Therefore, widening and up-gradation have been proposed for 77.13 km length. The project road from at three different section such as from (i) Km 1.800 to Km 4.500 at Ranjnandgaon city; (ii) km 35.000 to km 36.600 at Dondi Lohara; and (iii) km 73.100 to km 74.100 at Dondi will be four lane within available RoW. The road traverses through Rajanadgaon district and newly formed Balod district of Chhattisgarh State. Nodal towns on the stretches are Rajnandgoan, Acholi, Lohara, Dalli Rajahara and Dondi towns . 13. During the implementation stage the widening of road was undertaken for 4 lane carriageways instead of 2-lane (as provided in ADB approved IEE report) at three locations. The 4-lane carriageway included 14.0 m wide road with 7 m width of each lane, 1.0 meter median and 1.3 m of drainage on both sides. The hard shoulder varies from 1.6m to 2.5m depending on the available RoW and the works have been completed within the existing RoW.

5

14. This addendum to ADB-approved IEE report has been prepared due to widening of road to four lanes instead of two lane (provided in scope of work as per approved IEE) at three stretches of Rajnandgaon- Kachhe (SH-5)” Road . The details are given in table 4: Table 4 - Change of scope from two to four lane in Package-8 Location Name Chainage ( KM) Length (Km) S.No

1 Rajnandgaon City Km 1.800 to Km 4.500 2.700 2 Dondi Lohara Km 35.000 to Km 36.600 1.600 3 Dondi Km 73.100 to Km 74.100 1.000 Total Length of 4-lane Stretches 5.3 Km

15. The location maps prepared in google map Rajnandgaon city from Km 1.800 to Km 4.500, Dondi Lohara from Km 35.000 to Km 36.600 and Dondi from Km 73.100 to Km 74.100 are given in figure 2, figure 3 and figure 4 respectively. The typical cross-section for four lanes at three sections is given in figure 5. 16. The works have been completed at all three sections of four lane alignments.

Figure 2: Location map on Google from Km 1+800 to Km 4+500 at Rajnandgaon City

6

Figure 3 – Location map on Google from Km 35+000 to Km 36+600 at Dondi Lohara

Figure 4 – Location map on Google from Km 73+100 to Km 74+100 at Dondi

7

Figure 5 - Approved Typical Cross section for 4 Lane2

D. APPROACH FOR ADDENDUM PREPRATION

17. The Addendum to ADB-approved IEE report (January 2013) has been prepared based on field visits, carrying out discussion with field staffs and the officials of executing agency (EA) conducted during project implementation stage. The information gathered during site visit has been used to update the Rapid Environmental Assessment (REA) Checklist (Annexure I), which assisted in screening, categorization of sub-project and anticipating potential impacts on environment due to construction of sub-project E. DESCRIPTION OF ENVIRONMENT 18. The sub-project is located in district Rajnanadgaon. The descriptions of environment for this district have been captured in Chapter 3.0 (Description of Environment) of ADB approved IEE report prepared in January 2013, which adequately capture the environmental setting in the district and may be referred. The testing of environmental parameters such as ambient air quality, ambient noise levels and water quality have been conducted package wise under the project covered in different environmental monitoring reports. The environmental features along the sections from Km 1.800 to Km 4.500, from Km 35.000 to Km 36.600 and from Km 73.100 to Km 74.100 has been collected from site and given in the table 5. Table 5 - Environmental Features Along the Sections S. No Environmental Features Status Remarks, if any 1 Forest section Not involved No impact anticipated 2 Number of trees available No tree is present at No impact anticipated location where the scope of work is changed. The work is being carried out under existing Row. No additional tree cutting is

8

S. No Environmental Features Status Remarks, if any involved due to change of scope. 3 Tree to be cut due to change of No additional tree cutting No impact anticipated scope is involved 4 Water bodies such as pond, river No water bodies are No impact anticipated present along the sections where the scope of work is changed. However, small village ponds are present alongside the overall stretch of road. No impact is anticipated on village ponds due to change in scope of work. 5 Environmental sensitive features such No school, college and No impact anticipated as school, college, hospitals hospital are present nearby the sections where the scope of work is changed. However educational institutions and hospitals are present alongside the overall stretch of road. Safety measures are being taken to avoid any hindrance to educational institutions and hospitals as given in EMP 6 Archaeological site, monument, Not involved No impact anticipated cultural heritage and temple

F. POTENTIAL ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

19. The preparation of this addendum is accordance to specified criteria provided in the Environmental Assessment Review Framework (EARF). These criteria were used for identify in the potential environmental impacts due to the sub-project in ADB-approved IEE report under the Chapter 5. The REA checklist prepared for the sub-project forms the basis for assessment of potential environmental impacts and suggesting mitigation measures

20. No additional environmental impacts are anticipated due to widening of road from 2 lane (as per scope provided in ADB approved IEE report) to 4 lane (Changed scope of work). The change in scope of work does not involve any additional tree cutting, structure damage, impact on water bodies and environmental sensitive area. The upgradation of road is being undertaken within the existing RoW thus no land acquisition is required. Thus, the no additional mitigation measures are suggested

21. The roads under package 8 Rajnandgaon- Kachche (SH-5) Road not pass through any forest land. However, to up-grades the roads tree cutting is inevitable. During implementation stage, a total of

9

3495 trees of which total 3495 trees may need to be cut in actual within ROW in this Package. The number of trees impacted for upgradation to 4 lane remains same as for 2 lane, as there are no additional trees cutting involved due to change in scope of work. The details of trees required to be cut under package 8 is provided in table 6 and permission obtained from competent authority for package 8 is provided in Annexure VI.

22. The tree cutting required for widening of road to 2 lane road and 4 lane road remained same as no additional tree cutting was required for widening of road to 4 lane. This to clarify that the widening of road to 4 lane is done within the existing RoW and no land acquisition is involved

Table 6 - Details of Tree Cutting Package Permission Obtained from Actual No. of No. of Trees Cut Balance No. of No. Collector for cutting of Trees Trees to be Cut As on 31th March Trees to be cut 2018 8 3495 3495 3495 0

23. For each tree to be cut for the road widening, the concerned authority in their permission letters have imposed condition that 10 times the trees should be planted preferable near to the existing roads as compensatory plantation. The details of payment made to State Forest Department under each package for tree cutting and compensatory plantations are provided in table No.7

Table 7 - Details of Payment to Forest Department

Package Payments Done to Forest Department Forest Division No. As on 30TH March 2018 (Rs. in Lacs) For Cutting of Trees Compensatory Plantation

8 56.58 27.35 DFO Balod Sub Total 56.58 27.35

24. The change in scope of work will not change the environmental category of the project i.e. Category -B as no additional environmental impact is anticipated. Moreover, the widening of road from 2 to 4 lane is within the RoW of existing road. The potential environmental impacts anticipated remains same and are specifically capture in Section 4.0 of ADB-approved IEE report, which is also valid during widening of road to 4 lane.

G. ENVIRONMENTAL MANAGEMENT

25. The ADB-approved IEE report has suggested appropriate measures to mitigate impacts associated with construction activities. An Environmental Management Plan (Annexure III) has been prepared for the project that discusses the anticipated impacts, monitoring requirements, and development of mitigation measures with respect to the following stages: (i) Pre-Construction, (ii) Construction, and (iii) Operation and Maintenance. The environmental management plan was made part of contract agreement for contractor’s mandatory compliance to EMP.

26. The impacts associated with the sub-project are mainly due to activities during construction stage. As no additional environmental impacts are anticipated due to the change in scope of work. Thus, the Environmental Management Plan prepared for the project is adequate to mitigate the impacts due to sub-project.

10

H. INSTITUTIONAL REQUIREMENTS AND ENVIRONMENTAL MONITORING PLAN

27. Chhattisgarh State Roads Sector Development Project (CSRSDP) has taken up civil works for road up-gradation and rehabilitation, Consultancy services have been engaged for advisory and construction supervision, institutional strengthening, social rehabilitation and resettlement, environmental mitigation and road safety measures.

28. The Government of Chhattisgarh (GoCG) plans to improve the state road network under Chhattisgarh State Roads Sector Development Project (CSRSDP) with the assistance of Asian Development Bank. The Chhattisgarh Public Works Department (CGPWD), Government of Chhattisgarh is the Executing Agency (EA) for the project

29. The Consultancy services for Construction Supervision for the project roads to be developed are divided into three Groups (Group A, Group B and Group C). The Chhattisgarh Public Works Department has employed Egis International In JV with Egis India Consulting Engineering Pvt. Ltd.to undertake Consultancy services for Construction Supervision of Rehabilitation and Upgrading of Group “B” Road (Contract Package 7 to 15) Contract Agreement No.10 of 2014-2015, Durg Dated 28.02.2015. The objectives of the Consultancy services are to ensure that high quality construction is achieved and to ensure that all work is carried out in full compliance with the Environmental Safeguard, Social Safeguard, Engineering design, technical specifications and other documents as well as promoting technology transfer by employment of local/PWD staff and on the job training.

30. The Road Specific Environment Management Plan has been formulated which consists of a set of mitigation measures; monitoring and institutional measures applicable to design, construction and operation stages of the project and roles and responsibilities of various parties. The upgradation of environmental management plan is not required due to change of scope and no additional environmental implications are anticipated. Thus, the EMP present in the ADB-approved IEE report has been implemented by the civil contractors.

31. In order to comply to requirements of Environmental Monitoring Plan (EMoP) as provided in Contract Agreement an external environmental monitoring agency M/s Anacon Laboratories Pvt. Ltd. (NABET Accredited & MoEF&CC approved Laboratory) has been hired by the Civil Contractors for their respective packages to carry out the environmental monitoring with regards to ambient air quality, water quality, soil quality and noise levels during the construction period.

32. The environmental monitoring for ambient air quality, water quality, soil quality and noise levels have been conducted during construction phase and test results along with analysis are covered in subsequent semi-annual environmental monitoring reports.

I. GRIEVANCE REDRESS MECHANISM

33. Rajnandgaon-Kachche (SH-5) Road falls under . Grievance Redressal Committee (GRC) has been formed this project district. The details are provided in Annexure V.

11

34. Grievance Redress Committee (GRC) set up at district level monitors grievances arising during implementation for each package under area of its jurisdictions. The GRC determines the merit of each grievance, and resolve grievances within an outer time limit of three months of receiving the complaint. The Affected Persons has the right to refer the grievances to appropriate courts of law if not satisfied with the redress at any stage of the process. The set up GRC has the system of records keeping, contact details of complainant date of the complaint received, nature of grievance etc. if any for the ongoing project and taking the necessary action against the complaint.

35. Till date no grievance has been reported with respect to environmental issues in this package 8 (Rajnandgaon – Kachche).

J. PUBLIC CONSULTATION AND INFORMATION DISCLOSURE 36. Public Consultation (PC) meetings with local people residing along the road have been conducted at all three locations such as Rajnanadgaon city, Dondi Lohara and Dondi. The photographs collected during PC at Dondi Lohara and Dondi are given in Figure 6 and 7 respectively. 37. The meeting aims to address associated environmental implications due to proposed project. The sample attendance sheet of public consultation at Dondi and Dondi-Lohara are provided in Annexure II. The discussions during the consultation are as follows:

 General issues related to safety, accident and traffic control and dust emission has raised by the local community which contractor has proposed in their action plan to follow during construction.

Figure 6 - Public Consultation at Dondi –Lohara Figure 7 - Public Consultation at Dondi

38. The addendum to IEE report shall be disclosed and made available to the public. K. FIELD-BASED ENVIRONMENTAL DUE DILIGENCE 39. This chapter ascertains presence of any residual environmental impacts due to implementation of works at three locations i.e. Rajnandgaon-Kachche (SH-5) 5.3 km {Rajnanadgaon 2.700 km (Km 1.800 to Km 4.500), Dondi Lohara 1.600km (Km 35.000 to Km 36.600) and Dondi 1.000 km (Km 73+100 to Km 74+100)} where scope of work is changed from the original provided scope and suggests appropriate, time-bound corrective measures to address those residual environmental impacts, if any. The photographs of field visit are provided in Annexure VII.

12

40. The various aspects that would be considered for such field-based environmental due diligence are elaborated below: (a) Confirmation of EMP in contractor’s contract agreement: EMP is made part of contractor’s contractor agreement and the contractor’s compliance to EMP is being monitored by carrying out field visits from time to time during the project implementation. The change of scope in package-8 has not resulted in any addition environmental implication. No environmental sensitive area, structures, water bodies and trees are present in the area where the road is being upgraded from 2 lane to 4 lane. Moreover, the upgradation of road is being undertaken in the e xisting RoW. Thus, the upgradation of EMP is not required due to change of scope. (b) Compliance status during pre-construction and construction stage of the sub-project(s): Environmental Management Plan is made part of contractor’s contract agreement and contractor is mandate to comply with the environmental implications provided in the EMP. (c) Status of statutory permission applicable for the sub-project(s), if any: No additional statutory permission is required due to change of scope in package 8. The applicable statutory permissions such as (i) consent to establish and operate of construction plants; (ii) permission to withdrawal of construction water from surface and ground water sources; (iii) quarry lease deed and quarry license from state department of mines and geology; (iv) labor licenses and associated insurance policy/workmen compensation; and (v) permission of storage handling and transport of hazardous material have been obtained by the respective civil contractors. The civil contractors have also renewed the required statutory permissions for the sub-project. (d) Status on implementation of environmental mitigation measures, if any and testing of environmental parameters of ambient air quality and ambient noise levels along the sub- projects as per agreed monitoring plan, if any: environmental monitoring for ambient air quality, water quality and ambient noise level have been carried out as per given ADB-approved environmental monitoring plan (Refer Annexure IV). All the test results are within permissible limits and no impacts on air quality, water quality and ambient noise levels are anticipated due to change of scope under package-8. (e) (e) Residual environmental impacts, if any with appropriate, time-bound corrective measures: The civil contactors are reminded from time to time, to follow the environmental management plan and the mitigation measures as per EMP. No environmental impact has been noticed. Thus, no added corrective measure is required/suggested. (f) Public consultations during project implementation stages: Public consultation is being carried out as a part of continuous participation of public in the proposed project during the implementation stage. The details of public consultations carried out for the changed scope of subproject are provided in Chapter J of this addendum to IEE report. The public consultations being carried out during project implementation stage are also being updated in the subsequent semi-annual environmental monitoring reports. (g) Status of grievances, if any, received due to implementation of the sub-projects: The grievance redressal committee are setup in all the concern districts (Annexure V). The details of GRC are provided in Chapter I of this addendum to IEE report. No grievance related to environmental issue for any subproject is recorded.

13

(h) Conclusions: No major environmental impact is predicted due to the change in scope of subproject. L. CONCLUSION 41. This addendum to IEE report is based upon the environmental assessment and review framework (EARF) which is consistent with the ADB’s Safeguard Policy Statement (SPS) 2009. The subproject is classified as category “B” for environmental and does not require further environmental impact assessment. The ADB-approved EMP prepared for the project is valid and the same is recommended for adoption during implementation stage

14

Annexure – I Rapid Environmental Assessment Checklist

ROADS AND HIGHWAYS Instructions (i) The project team completes this checklist to support the environmental classification of a project. It is to be attached to the environmental categorization form and submitted to the Environment and Safeguards Division (RSES), for endorsement by Director, RSES and for approval by the Chief Compliance Officer.

(ii) This checklist focuses on environmental issues and concerns. To ensure that social dimensions are adequately considered, refer also to ADB's (a) checklists on involuntary resettlement and Indigenous Peoples; (b) poverty reduction handbook; (c) staff guide to consultation and participation; and (d) gender checklists.

(iii) Answer the questions assuming the “without mitigation” case. The purpose is to identify potential impacts. Use the “remarks” section to discuss any anticipated mitigation measures.

Country / Project Title: India : Chhattisgarh State Road Sector Project: Subproject – Rajnandgaon – Kachche (SH-5) Road (Chhattisgarh)

Sector Division: Transport Sector Screening questions Yes No Remarks A. Project Siting Is the project area adjacent to or within any of the following environmentally sensitive areas? Cultural heritage site X No archaeologically protected monument or cultural heritage site in located within the road ROW or even within 5 Km distance from the road. Though, few religious structures like temple are located close to the roads. Protected Area X No protected area is located close to roads and nearby (assessment made upto 10 Km ) area. Wetland X No protected or classified wet land is located close to the roads. Few village ponds though are located close to the project road. Mangrove X Project road is not located in coastal areas. Estuarine X No Estuarine is located in the project area. Buffer zone of protected area X No such area is located in the project vicinity. Special area for protecting biodiversity X No such area is located in the project vicinity. B. Potential Environmental Impacts Encroachment on historical/cultural areas; X The topography of proposed project road is

15

Screening questions Yes No Remarks disfiguration of landscape by road mainly plain. There is no encroachment of embankments, cuts, fills, and quarries? historical places in this stretch. Since road widening being confined to available ROW, no change in landscape is expected. Earth material will be sourced from pre identified areas (located within 25 to 30 Km from the road) and with the consent of landowner. All borrow areas being suitably rehabilitated.

No such impact is envisaged because of changed scope of subproject. Encroachment on precious ecology (e.g. X There is no National Parks, Wild Life Sensitive or protected areas)? Sanctuaries or any other similar eco- sensitive areas in and around the project area. Alteration of surface water hydrology of X The proposed change in scope of work waterways crossed by roads, resulting in (construction of four lane divided increased sediment in streams affected by carriageway in 5.3 km length) are not increased soil erosion at construction site? crossing through any Rivers and small drains. No addition impact is anticipated due to changed scope of subproject. Deterioration of surface water quality due to X Adequate sanitary facilities including silt runoff and sanitary wastes from worker- sewage treatment facilities being provided based camps and chemicals used in at construction camp, which being set-up construction? away from habitat and water bodies. No harmful ingredients are likely being used in the construction activities. As such, no impact on surface water quality is anticipated due to construction.

No such additional impact is envisaged because of changed scope of subproject. Increased local air pollution due to rock X Localised air pollution level is likely being crushing, cutting and filling works, and increased for short duration during chemicals from asphalt processing? construction period due to construction vehicle movement and asphalt processing. The asphalt mixing plant (hot mix plant) has been located away from habituated areas with adequately high stack for effective dispersion of likely emissions. Dust separation measures like spraying of water on unpaved vehicle movement areas being proposed to minimise the dust generation.

The changed scope of subproject does not result in any additional impact

16

Screening questions Yes No Remarks Risks and vulnerabilities related to X Workers may get exposed to dust and occupational health and safety due to noise during construction activities. physical, chemical, biological, and However the exposure levels being for radiological hazards during project short and insignificant. Workers have been construction and operation? provided PPEs to minimise such exposure and associated harmful occupational health effects.

Traffic on the road is expected little high and as such, no occupational health hazard is anticipated during operation phase. The impact due to changed scope of work will remain same as earlier. Noise and vibration due to blasting and X No Blasting is involved. No significant noise other civil works? generation is expected during construction activities except normal construction equipment operational noise.

All stationary noise making sources equipment like DG set, compressors being installed with acoustic enclosures.

No such additional impact is envisaged because of changed scope of subproject. Dislocation or involuntary resettlement of Yes The project road being widened within people existing RoW to two lane to four lane at three locations . About 175 families may affected, this will confirm after finalization of micro plan by EA. This aspect being addressed as per approved entitlement matrix. Dislocation and compulsory resettlement of Yes Only part of the structure is affected, .all of people living in right-of-way? them will received the assistance as per approved entitlement matrix

Disproportionate impacts on the poor, X No such impact is being anticipated. women and children, Indigenous Peoples or other vulnerable groups? Other social concerns relating to X No such social concern is being expected. inconveniences in living conditions in the Concern may arise during construction project areas that may trigger cases of stage due to increase in ambient air upper respiratory problems and stress? pollution levels, which is expected being localised and temporary in nature. This aspect being effectively controlled with the proposed dust suppression and other mitigation measures. As such people at large are supportive of project.

No such additional impact is envisaged

17

Screening questions Yes No Remarks because of changed scope of subproject Hazardous driving conditions where X Hazardous driving condition may arise construction interferes with existing roads? around bridge construction areas and at locations of road interface with non-project roads. To minimized the impact suitable traffic management plan being designed and implemented by the contractor to prevent any hazardous driving condition in above situations.

No such additional impact is envisaged because of changed scope of subproject

Poor sanitation and solid waste disposal in X Proper provisions for sanitation (sewage construction camps and work sites, and treatment), health care (drinking water possible transmission of communicable supply and periodic health check-ups) and diseases from workers to local populations? solid waste disposal (through composting) facilities being made at each construction camp.

Awareness being created amongst the workers about hygiene and health protection. Creation of temporary breeding habitats for X No such condition is being anticipated. mosquito vectors of disease? Further each borrow area will be rehabilitated as per pre agreed used and rehabilitation plan.

No such additional impact is envisaged because of changed scope of subproject Accident risks associated with increased X Adequate safety measures being adopted vehicular traffic, leading to accidental spills to avoid accidents during construction and of toxic materials and loss of life? will be operation stages. Measures, like signage, speed control, crash barriers will be taken close to sensitive locations if required Increased noise and air pollution resulting X Increase in noise and air pollution is little from traffic volume? being expected during construction phase but it has been confined within few meters of either side of the road. Adequate mitigation measures being adopted to minimise the same. During operation phase, vehicular traffic will be the main source of air and noise pollution. Improved road conditions, extensive plantation including multi-layered plantation along the road will reduce the noise and air pollution impact.

18

Screening questions Yes No Remarks No such additional impact is envisaged because of changed scope of subproject Increased risk of water pollution from oil, X This possibility is minimal but cannot be grease and fuel spills, and other materials ruled out. Controlled construction activities from vehicles using the road? and proper drainage system being reduced this possibility.

Provision is made for adequate signage and crash barriers near water bodies, which will minimise the possibilities of accidental water pollution.

No such additional impact is envisaged because of changed scope of subproject Social conflicts if workers from other X Most of the workers being hired locally. regions or countries are hired? Large population influx during project X Most of the workers being hired locally. construction and operation that causes One construction camp has been increased burden on social infrastructure established in this package with expected and services (such as water supply and workers population of only 50-60. This is sanitation systems)? unlikely to cause any significant burden on social infrastructure and services. Risks to community health and safety due X The construction material (aggregate from to the transport, storage, and use and/or approved quarries, borrow earth, bitumen) disposal of materials such as explosives, being sourced from nearby and approved fuel and other chemicals during sources. No explosive or chemicals is construction and operation? being used. Bitumen waste if any generated during construction being either recycled or disposed-off in controlled manner. Community safety risks due to both X No such impacts are anticipated. accidental and natural causes, especially Adequate awareness being created where the structural elements or amongst people and workers through components of the project are accessible to information disclosure, safety signage and members of the affected community or public consultation about safety aspects. where their failure could result in injury to the community throughout project construction, operation and decommissioning.

Based on above assessment no additional environmental impact is anticipated and the project is categorized as ‘B’

19

Annexure II Attendance Sheet of Public Consultation

20

21

Annexure III

Environmental Management Plan for Rajnandgaon – Kachche (SH-5) Road

(The requirement related to ‘Precautions for Safeguarding Environment” detailed at Section 111 of Technical Specifications and Sub-clause 4.18 of PCCB ( pre-conditions for contract bidding) shall be read in conjunction with the measures given below. All the requirement detailed at section 111 and sub clause 4.18 and as given below are to be implemented.)

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n A. Design and Pre - Construction Stage 1. Design Considerations Legislative approvals Considering the proposed Legislative As identified in Part of Activity 1 to 3 PIU, PWD project activities the following requirements DPR for the construction concerned legislative approvals shall be location of costs Nodal officer of required in advance: respective activity. PWD and activity 4 & 5 1. Obtain permission from contractor forest or district authorities as applicable for cutting of trees

2. Obtain concurrence from Gram Panchyats for shifting or demolition of community structure 3. Obtain permission from concerned authorities for shifting of utilities ( like electric pole, telephone lines, hand pumps) 4. Obtain connect to establish Hot Mix plant, batching plant (if

22

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n required), quarry operation if new quarry to be opened, and setting up construction 5. Obtain permission for withdrawal of ground water as applicable Utility Relocation Utilities relocation will be Design As per widening Included in Design PIU PWD reasonably completed before requirement plan construction Consultant construction starts and without cost affecting any essential supplies to settlements like water supply.. Shifting of Community structures, like, Design As per widening Included in Design PIU PWD Community Structure religious structures will be requirement plan construction Consultant shifted appropriately, if cost required. Climate Change and No climate Change induced Local Forest Rule Within RoW or on Covered in Through Forest PIU PWD Removal of vulnerability anticipated. Govt. Land EMP Department trees Approximately 3495 trees may need to be cut within 16m ROW for up-gradation of the project road before the commencement of construction with prior Clarence from the Forest Department/District Authorities as applicable.

Compensatory afforestation: Ten trees will be planted for each tree felled as per

23

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n regulatory compliance. Geometric adjustment to reduce tree cutting.

Removal of The project road does not Design Within RoW Included in Construction PIU PWD Structures and require land acquisition Only requirement construction Agencies, PIU/ acquisition of land few non title holders are cost PWD affected. They will be removed as per the project’s Rehabilitation and Resettlement plan prepared separately Widening Option and Selection of widening option Design All habitat areas Included in Design PIU PWD Pavement design (left aligned, right aligned or requirement throughout the construction Consultant and inadequate centric widening) to be decided alignment cost drainage provisions based on the least cutting of in habitat areas tree, minimum loss of structure and embankment design considerations.

Selection of suitable pavement design in settlement areas considering alignment level and drainage requirements.

Raise road level as feasible, above the nearby areas with provision of adequate side drains to evacuate the rain water and domestic discharges (drained by settlements

24

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n occasionally) to prevent damage to road and rain water entry to habitats’ houses.

Provision of adequate no of cross drainage structures based on drainage pattern shall be made to maintain natural flow of rain water across the road. Safety along the Adequate safety provisions like Design Crash barriers are Included in Design PIU PWD proposed alignment crash barriers at accident requirement proposed at construction Consultant prone areas, rumble strips in sensitive locations cost habitat areas to regulate like school, medical speed, retro-reflective warning centers, along the sign boards nears school, project corridor hospital, religious places (Preferably PCC boards with Rumble strips are retro- reflective paints to avoid proposed at the all its theft) shall be made. the settlements and crossing points

2. Natural Hazards Protection from Adoption of relevant IS codes for IRC:34 Throughout the Project Design PIU PWD damage from design embankment/structures Recommendations stretch especially preparation Consultant Earthquake suitable to withstand earthquake for road bridge structures and of highest magnitude in construction in construction moderate earthquake intensity waterlogged area costs Cost Zone ( Seismic Zone II level as and IRC: 75 and per Indian classification). MoRT&H guidelines for

25

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Design of High Embankments B. Construction Stage 3. Climate and Air Quality Local Weather Additional Plantation on river Kyoto Protocol, Road Side Design CSC / PIU conditions banks, borrow areas and Environmental Plantations in Consultant and PWD sensitive locations to increase Protection Act, the ratio of Contractor the green cover and improve the 1986; The Air 1:10 ( costs aesthetics (Prevention and highlight in the Control of following table) Pollution) Act, 1981 Included in Design CSC / PIU + construction Consultant and PWD Dust Generation Transport, of loose and fine IRC and costs Contractor CSC / PIU due to construction materials through covered MORT&H Throughout project PWD activities and vehicles and paved roads to the Specifications for corridor, mainly at transport, storage extent feasible . Road and Bridge haulage roads, and handling of works earthwork, construction Loading and unloading of Air (P and CP) construction sites, materials construction materials shall be Act 1974 and loading areas, made at designated locations in Central Motor and storage areas, project area with provisions of Vehicle transport route. water fogging around these Act 1988 locations

Storage areas to be located downwind of the habitation area.

Water spraying on earthworks, unpaved haulage roads and other dust prone areas.

26

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Provision of PPEs to workers. Emission from Regular maintenance of Asphalt mixing Included in Contractor CSC/ CSC / vehicle, equipment machinery and equipment. plants, crushers, construction PIU PWD and machinery DG sets locations costs Hot Mix Plant shall have a bag filter and be located at least 1 km downwind of the human settlement. Included in monitoring cost Batching, plant (if required) and crushers at downwind (0.5km) direction from the nearest settlement. Hot mix plant to be fitted with adequate stack height. Obtain consent to establish (NOC) from PCB before setting up these plants.

Only crushers licensed by the PCB shall be used

DG sets with stacks of adequate height and use of low sulphur diesel as fuel.

Use LPG as fuel at construction camps

Undertake periodic ambient air quality monitoring as per EMOP 4 . Noise

27

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Noise from Provision is made for installing Legal requirement The school, Cost for Contractor CSC / PIU construction need base noise barrier near Noise Pollution hospitals are away Plantation PWD vehicle, equipment sensitive locations like hospitals, (Regulation and from the road, already and machinery. schools. Control) Rules, therefore, at the indicated 2000 and time of above. All equipment shall be fitted with amendments construction of Rest part of silencers and will be properly thereof road supervision construction maintained to minimize its + consultant will costs operational noise. Clause No 501.8.6. evaluate the need MoRT&H to noise barriers. Stationary noise making Specifications for equipment shall be placed along Road and Bridge uninhabited stretches. works

The timing for construction Monitoring activities shall be regulated such Cost as that all noise generating indicated In construction activities happen EMoP. after school hours.

Construction must not take place at night to avoid disturbance to community.

The provision of temporary noise barrier (Barricading) shall be made near identified sensitive locations or near the noise source during construction.

Plantation along the boundary

28

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n wall using appropriate species shall be made at start of construction itself.

Protection devices (ear plugs or ear muffs) shall be provided to the workers operating near high noise generating machines

Noise measurements as per EMoP should be carried out to ensure the effectiveness of mitigation measures and develop a mechanism to record and respond to complaints on noise

Noise monitoring as per EMoP. 5. Land and Soil Land use Change The top soil from the productive Project Throughout the Included in Contractor CSC / PIU and Loss of land shall be preserved and requirement project section and construction PWD productive/top soil reused for plantation purposes borrow areas cost as top cover of embankment slope for growing vegetation to protect soil erosion.

The land taken on lease for access road and construction camp shall be is restored back to its original land use before handing it over back to land

29

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n owner. Slope protection Bank protection measures shall IRC: 56 -1974 At high Construction Design CSC / PIU and Soil erosion be taken at erosion prone areas. recommended embankment area cost consultant and PWD due to construction The protection measures may practice for Contractor, activities, include use of geo-textiles treatment of earthwork, and cut matting, bio ( vegetative) - embankment and fill turfing slopes for erosion control Side slopes of the embankment Clause No. 306 shall not be steeper than 2H:1V. and 305.2.2 Provision of side drain to guide MoRT&H the water to natural outfalls. In Specifications for rural stretches, longitudinal side Road and Bridge drains shall be intercepted by works Guidelines drains serving as outlet channels IX for Soil erosion to reduce the erosion.

Soil spread on slopes for permanent disposal shall be buttressed at the toe by retaining walls.

Turfing of embankment slopes shall be done along the stretch. Stone pitching wherever necessary.

Shrubs and grasses shall be planted in loose soil area.

Soil erosion shall be visually

30

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n checked on slopes and high embankment areas. In case soil erosion is found, suitable measures shall be taken to control the soil erosion further including bio-turfing

While planning or executing excavations the Contractor will take all adequate precautions against soil erosion as per MoRT&H 306.

Soil erosion at The earth stockpiles to be At earth stockpiles Construction Contractor CSC / PIU earth stockpiles provided with gentle slopes to cost PWD prevent soil erosion and stock piles to be located downwind.. Borrow areas Non-productive, barren lands, IRC Guidelines Borrow sites Construction Contractor CSC / PIU wasteland shall be used for (No. IRC:10-1961) location. cost PWD borrowing earth with the on borrow areas necessary permissions/ selection and consents. amount to be extracted Borrow areas should not be located on cultivable lands For quarries except in the situations where (Environmental land owners desires to level the Protection Act and land. The top soil shall be Rules, 1986; Water preserved and depth shall be Act, Air Act) restricted to the desired level + Clause No.

31

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n and the slop shall not be steeper 305.2.2 MoRT&H than 25%. Specifications for Road and Bridge Borrow areas shall be sited works away from inhabited areas. To Guidelines V for the extent possible, Borrow Areas Management To the extent borrow areas shall be sited away from inhabited areas.

Borrow areas shall be leveled with salvaged material or other filling materials which do not pose contamination of soil. Else, it shall be converted into fishpond in consultation with fishery department and land owner/community. Rehabilitation of the borrow areas as per Guidelines for redevelopment of Borrow Areas. Quarry Operations Aggregates will be sourced from Clause No. 111.3 existing licensed quarries. MoRT&H Copies of consent/ approval / Specifications for rehabilitation plan for a new Road and Bridge quarry or use of existing source works Guidelines will be submitted to EO, PIU. VI for Quarry Areas Management The contractor will develop a Quarry Redevelopment plan, as

32

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n per the Mining Rules of the state and submit a copy of the approval to EA if new quarries are to be opened. Compaction of soil Construction vehicles, Design Parking areas, Included in Contractor CSC / PIU and impact on machinery, and equipment to be requirement Haulage roads and construction PWD quarry haul roads stationed in the designated construction yards. cost due to movement of ROW to avoid compaction. vehicles and equipment Approach roads/haulage roads shall be designed along the barren and hard soil area to reduce the compaction.

Transportation of quarry material to the dumping site through heavy vehicles shall be done through existing major roads to the extent possible to restrict wear and tear to the village/minor roads.

Land taken for construction camp and other temporary facility shall be restored to its original conditions. Contamination Fuel and lubricants shall be Design Fuelling station, Monitoring Contractor CSC / PIU of soil and stored at the predefined storage requirement construction sites, Cost Included PWD construction waste location away from drainage and construction in EMoP management channels. The storage area shall camps and be paved with gentle slope to a disposal location.

33

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n corner and connected with a chamber to collect any spills of the oils

Construction vehicles and equipment will be maintained and refueled in such a fashion that oil/diesel spillage does not contaminate the soil.

All efforts shall be made to minimize the waste generation. Unavoidable waste shall be stored at the designated place prior to disposal. To avoid soil contamination at the wash-down and re-fuelling areas, “oil interceptors” shall be provided. Oil and grease spill and oil soaked materials are to be collected and stored in labeled containers (Labelled: WASTE OIL; and hazardous sign be displayed) and sold off to SPCB/ MoEF authorized Waste Oil Recycler

Septic tank or mobile toilets fitted with anaerobic treatment facility shall be provided at construction camp.

34

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n

Domestic solid waste at construction camp shall be segregated into biodegradable and non-biodegradable waste. The non-biodegradable and recyclable waste shall be sold off.

Efforts shall be made that biodegradable waste shall be composted in the mechanized and movable composter by the contractor. Non bio-degradable and non saleable waste shall be disposed off to authorized land fill site.

All excavated materials from roadway, shoulders, drains, cross drainage should be used for backfilling embankments, filling pits, and landscaping.

Unusable debris material should be suitably disposed off at pre designated disposal locations, with approval of the concerned authority.

Unproductive/wastelands shall

35

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n be selected for dumping sites. Away from residential areas and located at least 1KM downwind side of these locations, Dumping sites shall not be close to water body and contaminate any water sources, rivers. Dumping sites should have adequate capacity equal to the amount of debris generated. Public perception and consent from the village Panchayats about the location of debris disposal site shall be obtained before finalizing the location.

The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MoRT&H guidelines should be followed.

Soil quality monitoring shall be carried out as per EMoP.

6. Water Resources Construction water Requisite permission as Clause No. 1010 Throughout the Included in Contractor CSC / PIU applicable shall be obtained for EP Project section construction PWD abstraction of groundwater. Act 1986 MoRT&H cost

36

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Specifications for The contractor shall make Road and Bridge arrangements for water required works for construction without affecting the water availability and supply to nearby communities.

Water intensive activities shall not be undertaken during summer season.

Provisions shall be made to connect road side drains with exiting nearby ponds.

37

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Alteration in Existing drainage system to be Design Near all drainage Included in Contractor CSC / PIU surface water maintained and further requirement, channels, river construction PWD hydrology due to enhanced. Clause No 501.8.6. crossings etc. cost embankment MoRT&H Adequate cross drainage Specifications for structures shall be provided. Road and Bridge. Additional balancing culverts IRC SP 42 and 50 shall be provided in flood prone for design of areas. surface and subsurface The embankment height shall be designed consistent with the existing topography of the region and shall be higher than the HFL.

Elaborate drainage system shall be provided to drain the storm water from the roadway and embankment and to ensure minimum disturbance to natural drainage of surface and subsurface water of the area.

Surface runoff from the main road and embankment slopes shall be discharged through longitudinal drains, designed for adequate cross section, and the outfalls.

No construction material will be stored or disposed near any water body except for reusing it 38 for enhancement measures such

as embankment raising.

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Siltation in water Embankment slopes to be Design Near Shivnath Included in Contractor CSC / PIU bodies due to modified suitably to restrict the requirement , River and construction PWD construction soil debris entering water bodies. Clause No 501.8.6. Kharkhara River cost activities/ Provision of Silt fencing shall be MoRT&H bodies, earthwork made at water bodies. Specifications for embankment Road and Bridge slopes. Silt/sediment should be collected works and stockpiled for possible reuse (CP and CP) as surfacing of slopes where and worldwide best they have to be re-vegetated. practices

Earthworks and stone works to be prevented from impeding natural flow of rivers, streams and existing drainage system.

Provision of retaining wall is made along the road for the ponds located next to the road to prevent soil erosion and siltation of pond

Deterioration in No vehicles or equipment should The Water Water bodies, Construction Contractor CSC / PIU Surface water be parked or refueled near (Prevention and refueling stations, cost PWD quality due to water-bodies, so as to avoid Control of construction leakage from contamination from fuel and Pollution) Act, 1974 camps. Monitoring cost vehicles and lubricants. and amendments as indicated in equipment. thereof. EMoP Oil and grease traps and fuelling platforms to be provided at re- fuelling locations.

39

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n

All chemicals and oil shall be stored away from water and on concreted platform with catchment pit for spills collection.

All equipment operators, drivers, and warehouse personnel will be trained in immediate response for spill containment and eventual cleanup. Readily available, simple to understand and preferably written in the local language emergency response procedure, including reporting, will be provided by the contractors

Construction camp to be sited away from water bodies.

Wastes must be collected, stored and taken to approve disposal site only.

Water quality shall be monitored periodically. 7. Flora and Fauna Vegetation loss Suitable modifications in design Forest Throughout project Indicated Forest CSC / PIU due to site to minimize tree cutting. Conservation Act corridor above Department for PWD preparation and 1980 tree cutting

40

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n construction Roadside trees to be removed + and activities and with prior approval of competent IRC SP: 21 and compensatory Plantation Strategy authority. IRC SP:66 tree plantation. Rest contractor Compensatory plantation at 1:10 basis with local forest department.

Provision of LPG in construction camp as fuel source to avoid tree cutting, if possible.

Additional plantation near river banks to check erosion (not possible during construction stage).

In the event of design changes during the construction stages additional assessments including the possibility to save trees shall be made by the EA . Road side Plantation Strategy as per IRC specifications including manuring.

Control use of pesticides/manure 8. Construction Camps Impact associated All camps should maintain Design Both construction Included in Contractor CSC / PIU with location minimum distance from following: Requirement camps construction PWD

41

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n # 1000 m from habitation cost # 500 m from water bodies

42

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n worker’s Health in The location, layout and basic The Building and All construction Part of the Contractor CSC / PIU construction camp facility provision of each labor Other Construction camps Contract PWD camp will be submitted to CSC workers prior to their construction. The (Regulation of construction shall commence Employment and only after approval of CSC Conditions of concurrence Service) Act 1996 and The contractor will maintain The Water necessary living accommodation (Prevention and and ancillary facilities in Control of functional and hygienic manner Pollution) Act, 1974 as approved by the EA. and amendments thereof Preventive medical care to be provided to workers.

Disposal of solid waste on regular basis at identified locations.

The Contractor will take all precautions to protect the workers from insect and pest to reduce the risk to health. This includes the use of insecticides which should comply with local regulations.

No alcoholic liquor or prohibited drugs will be imported to, sell, give, barter to the workers of host community. 43

Provision of day crèche for children

Limited recreation and sporting Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n 9. Management of Construction Waste/Dismantled Debris Selection of Unproductive/wastelands shall Design At all Dumping Part of the Contractor. CSC / PIU Dumping Sites be selected for dumping sites. Requirement and Sites contract PWD Away from residential areas and MoRT&H water bodies guidelines

Dumping sites have adequate capacity equal to the amount of debris generated.

Public perception and consent from the village Panchayats has to be obtained before finalizing the location.

44

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Reuse and The existing bitumen surface disposal of shall be utilized for paving of construction and cross roads, access roads, and dismantled waste paving works in construction sites and camps, temporary traffic diversions, and haulage routes.

All excavated materials from roadway, shoulders, verges, drains, cross drainage will be used for backfilling embankments, filling pits, and landscaping.

Unusable debris material should be suitably disposed off at pre- designated disposal locations, with approval of the concerned authority. The bituminous wastes shall be disposed in secure landfill sites only in environmentally accepted manner. For removal of debris, wastes and its disposal MORT&H guidelines should be followed.

Unusable and surplus materials, as determined by the Project Engineer, will be removed and disposed off-site. 45

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n 10. Accessibility, Traffic Management, Accident and Safety Risks Design Temporary traffic diversion shall Design Throughout the Project Contractor CSC / PIU requirement and be planned by the contractor and requirement and project corridor preparation PWD Traffic Planning approved by the CSC IRC SP:55 especially at and During intersections. construction Construction Stage The traffic control plans shall cost contain details of diversions; traffic safety arrangements during construction; safety measures for nighttime traffic and precautions for transportation of hazardous materials. Traffic control plans shall be prepared in line with requirements of IRC’s SP 55 document’.

The Contractor will ensure that the diversion/detour is always maintained in running condition, particularly during the monsoon to avoid disruption to traffic flow. On stretches where it is not possible to pass the traffic on the part width of existing carriageway, temporary paved diversions will be constructed.

The contractor shall inform local community of changes to traffic routes, and pedestrian access

46

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n arrangements with assistance from CSC and Nodal officer concerned

Use of adequate signage to ensure traffic management and safety. Conduct of regular safety audit on safety measures. Pedestrians, All measures for the safety of Design Near habitation on Included in Contractor in CSC / PIU animal and traffic during construction viz. requirement and both sides of construction consultation PWD Vehicular signs, markings, flags, lights and IRC: SP: 27 -1984 schools, temples, cost. with Forest movement, flagmen as proposed in the Report hospitals, department Traffic Control Plan/Drawings Containing construction sites, and PIU shall be taken. Recommendati haulage roads, ons of IRC diversion sites. Temporary access and diversion, Regional with proper drainage facilities. Workshops on Access facility to the schools Highway located adjacent to the highway. Safety IRC:SP: 32 -1988 Accident risk from Contractors to adopt and Road Safety Construction sites Included in Obligation of CSC / PIU construction maintain safe working practices. for Children (5- construction Contractor PWD activities Usage of fluorescent and retro- 12 Years Old) cost reflective signage, in local IRC:SP: 44 -1994 language at the construction Highway sites Safety Code IRC: SP: 55 -2001 Training to workers on safety Guidelines for procedures and precautions. Safety in Construction Provision of PPEs to workers. Zones

47

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n The Building and Provision of a readily available other first aid unit including an Construction adequate supply of dressing workers Act materials. Ensure ready access 1996 and Cess to ambulance, nursing staff, and Act of 1996 doctor when needed. Factories Act 1948 The contractor will not employ any person below the age of 14 years for any work and no woman will be employed on the work of painting with products containing lead in any form.

Clear demarcation of areas for restricted accesses to avoid accidents. 11. Common Property Resources and other Utilities Damage to Ensure that no construction Environment Throughout the Construction Contractor CSC / PIU Common Property material dumped close to the Protection corridor cost PWD Resources and such facilities and all precautions Requirement Utilities are taken such that no damage happen to any of common property resources and utilities. Access to common The area shall be barricaded for Environment Throughout the Construction Contractor CSC / PIU property resources safety prospective. It shall be Protection corridor cost PWD ensured that access to these Requirement area ensure for people to visit such places. 12. Enhancement Measures

48

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Environmental Enhancement of tree plantations Environmental Throughout the Construction Contractor CSC / PIU enhancement near likely to be relocated Enhancement as corridor cost PWD along the corridor community structures/ part of project landscaping etc. requirement

Enhancement/rehabilitation of borrow areas etc. 13. Contractor Demobilization Clean-up Contractor will prepare site Project Throughout the ---- Contractor CSC / PIU Operations, restoration plans, which will be requirement Corridor and PWD Restoration and approved by the CSC. The borrow areas Rehabilitation cleanup and restoration operations are to be implemented by the contractor prior to demobilization.

All construction zones including river-beds, culverts, road-side areas, camps, hot mix plant sites, crushers, batching plant sites and any other area used/affected by the project will be left clean and tidy, at the contractor's expense, to the satisfaction of the Environmental officer. All the opened borrow areas will be rehabilitated and CSC will certify in this regard. B. Operation Stage 1. Climate and Air quality Air pollution due to Roadside tree plantations shall Environmental Throughout the Indicated In CSC / PIU PWD

49

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n due to vehicular be maintained. Protection Act, Corridor EMoP movement Regular maintenance of the road 1986; The Air will be done to ensure good (Prevention and surface condition Control of Pollution) Act, 1981 Ambient air quality monitoring shall be carried out as per EMoP. If monitored parameters are above the prescribed limit, suitable control measures must be taken.

Road signs shall be provided reminding the motorist to properly maintain their vehicles to economize on fuel consumption and protect the environment. 2 Noise Environment Noise due to Effective traffic management and Noise Pollution In all settlement Included in CSC / PIU PWD movement of traffic good riding conditions shall be (Regulation and areas additional maintained to reduce the noise Control) Rules, plantation cost. level throughout the stretch and 2000 and speed limitation and honking amendments restrictions may be enforced thereof near sensitive locations.

The effectiveness of the multilayered plantation should be monitored.

50

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n 3. Land and Soil Soil erosion at Periodic checking to be carried to Project At bridge locations Included in CSC / PIU PWD embankment assess the effectiveness of the requirement and embankment Operation/ during heavy rain stabilization measures viz. slopes and other Maintenance fall. turfing, stone pitching, river probable soil cost training structures etc. erosion areas. Soil erosion at Visual monitoring and inspection Project At bridge locations Included in CSC / PIU PWD borrow areas of soil erosion at borrow areas, requirement and embankment Operation/ quarries (if closed and slopes and other Maintenance rehabilitated), embankments and probable soil cost other places expected to be erosion areas. affected, will be carried out once in every six months as suggested in monitoring plan. 4. Water Resources Contamination of Monitoring of surface water Near drains Indicated in CSC / PIU PWD surface water bodies /natural streams EMoP quality due to leakage of oil Siltation Regular visual checks shall be made to observe any incidence of blockade of drains/culverts. Regular checks shall be made for soil erosion and turfing conditions of river training structures for its effective maintenance. . . 5. Flora and Fauna Vegetation Planted trees, shrubs, and Forest Throughout the Indicated in CSC / PIU PWD grasses to be properly Conservation Act corridor Monitoring cost maintained. 1980 in EMoP

51

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n

The tree survivalist audit to be conducted at least once in a year to assess the effectiveness

6. Flooding/ inundation Road inundation Field Unit will ensure that all Project operation In settlement area Overall CSC/PIU CSC / PIU PWD due to choking of drains (side drains and all cross requirement Operation cost drainage channels drainages) are periodically cleared especially before monsoon season to facilitate the quick passage of rainwater and avoid flooding. 7. Right-of-Way Maintenance Accident Risk due The construction site shall be Project Throughout the Included in CSC / PIU PWD to uncontrolled kept completely clear of requirement Project route operation/ growth of vegetation. Maintenance vegetation cost Regular maintenance of plantation

Invasive plant not to be planted near the road.

Controlled use of herbicide/pesticide

The designated ROW shall be maintained free of any encroachment. 8. Accidents and Safety

52

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n Accident risks Traffic control measures, IRC:SP:55 Throughout the Included in CSC / PIU PWD associated with including speed limits, will be Project route operation/ traffic movement. enforced strictly. Maintenance cost Further encroachment and squatting within the ROW will be prevented.

Monitor/ensure that all safety provisions included in design and construction phase are properly maintained

Transport of Preparation of spill prevention Throughout the Included in CSC / PIU PWD Dangerous Goods and control and emergency project stretch operation/ preparedness and responsive Maintenance plans based on an analysis of cost. hazards, implementation of presentation and control measures. 9. Monitoring Operation Performance Monitoring Monitor the operational Throughout the Included in CSC / PIU PWD Operation performance of the mitigation/ corridor EMoP Performance enhancement measures carried out as a part of the project

The indicators selected for monitoring include the survival rate of trees; utility of enhancement provision, status of rehabilitation of borrow areas, Air

53

Environmental Remedial Measures Reference to Approximate Mitigation Institutional Responsibility Aspect/Impact Laws /Guidelines Location Cost Implementatio Supervision n quality, water quality, noise levels, soil quality, drainage pattern. The monitoring and reporting to be carried out as per EMoP

Source: ADB approved IEE report, Rajnandgaon-kachche (SH – 5) subproject Note: The changed scope of project has not resulted in any additional environmental implications thus the earlier proposed environmental management plan can be utilized and upgradation of EMP is not required.

54

Annexure IV

Environmental Monitoring Plan for the Project Road

Package- 8 Rajnandgaon- Kachche (SH-5) Road

Environmental Duration / Project stage Parameter Standards Locations Implementation Supervision Component Frequency Air Construction SPM, SO2, Minimal National Wherever the Stack Emission Contractor through a PIU, Supervision Phase NOx, CO, HC Standards contractor decides Monitoring approved monitoring Consultant, PWD to locate the Hot agency Mix Plant PM2.5, PM10, National Stretch of the road Continuous 24- Contractor through a PIU, Supervision SO2, NOx and Ambient Quality where construction hourly, twice a approved monitoring Consultant, PWD CO Standards in progress site week once during agency preferably at Hardi, Construction Acholi, Lohara, Phase Dalli Rajahara and Dondi Operation PM2.5, PM10, National At Hardi, Acholi, Continuous 24- PIU, PWD PWD Phase SO2, NOx and Ambient Quality Lohara, Dalli hourly, twice a CO Standards Rajahara and week once in Dondi year for 2 years Water Quality Construction pH, TDS, TSS, As Water quality At Hardi, Acholi, Once during the Contractor through a PIU, Supervision Stage Oil & Grease standards Lohara, Dalli Construction approved monitoring Consultant, PWD (IS 10500) Rajahara and Phase agency Dondi Operation pH, TDS, TSS, As Water quality At Hardi, Acholi, End of summer PIU, PWD PWD Phase Oil & Grease standards Lohara, Dalli before the onset (IS 10500) Rajahara and on monsoon Dondi every year for 2 years

55

Environmental Duration / Project stage Parameter Standards Locations Implementation Supervision Component Frequency Noise and Construction Noise Level in As per National Hardi, Acholi, One day hourly Contractor through a PIU, Supervision Vibration Phase dB (A) Noise standards Lohara and Dalli measurement, approved monitoring Consultant, PWD Rajahara, Dondi once in six agency months once during the Construction Phase Operation Noise Level in As per National At Hardi, Acholi, One day hourly PIU, PWD PIU, Supervision Phase dB (A) Noise Lohara, Dalli measurement, Consultant, PWD standards. Rajahara and Dondi Soil Erosion Construction Soil erosion -- On slops and After precipitation PIU, PWD PIU, Supervision Phase embankment Consultant, PWD Operation Soil erosion -- On slops and After precipitation PIU, PWD PIU, Supervision Phase embankment Consultant, PWD Road Side Construction Monitoring of As laid out in the Entire stretch of During felling of Forest Dept. PIU, PWD Plantation Phase trees felling detailed design project road trees for project Operation Survival rate of The survival rate Entire stretch of Every year for 3 PWD, Forest Dept. PWD Phase trees success should be at project road years of re-plantation least 70% below which re- plantation shall be done.

Source: ADB approved IEE report, Rajnandgaon- Kachche (SH-5) Road

56

Cost of Environmental Monitoring Plan Component Stage Item Parameters Unit Cost Quantity Total Cost  Monitoring at hot mix plant locations Stack emission 6,000/- Two time during construction 12000 approved by the Supervision monitoring of SPM, phase Consultant SO2, NOx, CO, HC and VOC Construction  Monitoring at construction site in PM2.5, PM10, SO2, 4000/- Continuous 24 - hourly, twice a 240000 Air tandem with construction work NOx and CO week twice in each season preferably at Hardi, Acholi, Lohara, during construction Dalli Rajahara and Dondi Operation  Ambient Air Quality monitoring at PM2.5, PM10, SO2, 4000/- 5 locations, 24, hourly 240000 preferably at Hardi, Acholi, Lohara, NOx and CO monitoring twice a week every Dalli Rajahara and Dondi season for 2 years At Hardi, Acholi, Lohara, Dalli Rajahara Pre-monsoon and post 100000 Construction and Dondi As per IS 10500 5,000/- monsoon season for two years Water At Hardi, Acholi, Lohara, Dalli Rajahara Pre-monsoon and post 100000 Operation and Dondi As per IS 10500 5,000/- monsoon season for two years At equipment yards Day and Night Leq 2,000/- As and when necessary 26000 Construction Noise Monitoring at 5 Construction Site Day and Night Leq 2,000/- As and when necessary 30000 Noise Operation Noise Monitoring at 5 Construction Site Day and Night Leq 2,000/- Once in every year for two years 20000 including Hardi, Acholi, Lohara, Dalli Rajahara and Dondi Soil Construction At productive land abutting traffic detours No. of Samples 6,000/- Max. of 5 locations for each of 2 60000 and traffic diversions, to be identified by years the Supervision Consultant Operation Supervision of expert to check the soil LS 15000 5 visits during rains 50000 erosion Green Belt Construction Along the stretch Lump sum 50000 50000 Operation At locations of compensatory plantation Lump sum 50000 50000 Total 978000

Source: ADB approved IEE report, Rajnandgaon- Kachhe (SH-5) Road Note: The changed scope of project has not resulted in any additional environmental implications thus the earlier proposed environmental monitoring plan can be utilized and upgradation of EMP is not required

57

. Annexure V

Grievance Redress Committee – District Balod & Rajnandgaon

58

59

Annexure VI

Permission for Tree Cutting (Package -8)

60

61

62

63

Annexure VII

Photographs of Field Visit

Package-8 Dondi Package-8 Rajnanadgaon

Package- 8 no any additional tree cutting

64