Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged, and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer Mr Byron Lovell

Road Name Parish Extent of Works Current Status

Programmed 1st November A228 Colts Hill Capel Crittenden Road to B2017 2019

A268 Rye Road Sandhurst Lomas Lane to Rosemullion To be programmed early 2020

Travel Lodge Hotel to Church A264 Mount Ephraim Tunbridge Wells To be programmed early 2020 Road

Eridge Road Roundabout to To be programmed early 2020 A26 Eridge Road Tunbridge Wells Pedestrian Crossing (Summervale Rd)

Junction with Hanover Rd to To be programmed from April A26 Grovesnor Road Tunbridge Wells A26 St Johns Rd 2020

Surface Treatments – Contact Officer Mr Jonathan Dean

Micro Surfacing

Road Name Parish Extent of Works Current Status

A262 Road Various From East of Goudhurst to Complete Biddenden

J/w Benhall Mill Road to Forest Road Tunbridge Wells Bayham Road (Joint with Complete 2018 SD)

Maidstone Road to Queen Lucks Lane Paddock Wood Street (Leave out level Completed crossing)

From the junction with the A21 A264 Road Tunbridge Wells Access roundabout (Tesco Completed end) to the junction with Kingswood Road.

Mascalls Park Rd to "Kings To be re-programmed. Date to Maidstone Road Paddock Wood Barn" (Joint with last year's be confirmed micro surfacing)

50m west of Petteridge Lane ("Myrtle Cottage") to Brenchley Road Crook Road (Opposite Completed

Brenchley Memorial Hall)

Clayhill Road B2169 Furnace Lane to A21 Completed Lamberhurst Quarter

A268 Queen Street, Bodiam Road Sandhurst Sandhurst to KCC Completed the boundary with East Sussex ("THE MILL HOUSE") Crittenden Road and From A228 Colts Hill to Chestnut Lane Capel / Maidstone Road, Matfield Completed

KCC Boundary (East end of Bayham Road Tunbridge Wells Tunbridge Wells Completed Crematorium) to Forest Road

Blackhurst Lane Tunbridge Wells Between Sandown Park and Completed Academy entrance

In front of Hospice and near Maidstone Road Pembury To be re-programmed. Date to the school. be confirmed Penshurst Hill to 50m past Barden Road Speldhurst Completed Furzefields

Lower Green Road to Etherington Hill Speldhurst Gateway To be re-programmed. Date to be confirmed Mount Pleasant Road bend Clayhill Road Lamberhurst past "Snaggs Well Cottages" Completed to end of trees

Hawkhurst Delmonden Lane to A268 MA. Completed North Hill Road

Cromwell Road Tunbridge Wells Whole Length To be re-programmed. Date to be confirmed

End of HFS j/w Standen Cranbrook Street ("Weald House") to Completed Mill Street and Sponden Lane ("Sponden Sponden Lane Oast")

Surface Dressing

Road Name Parish Extent of Works Current Status

A228 Pembury Northern Pembury From Maidstone Road to Completed Bypass Pembury Road

Cranbrook / Headcorn Road/Green Lane Completed Staplehurst Road Staplehurst to Park Wood Lane.

Footway Improvement - Contact Officer Mr Neil Tree

Showfields Road Tunbridge Road Entire Length Completed (Footway Protection)

College Drive Tunbridge Wells Entire Length Completed (Footway Protection)

Concord Close Tunbridge Wells Entire Length Completed (Footway Protection)