INTEGRATED IRRIGATION AND AGRICULTURE TRANSFORMATION PROJECT

Public Disclosure Authorized Procurement Methods

Procurement Approaches and Methods Thresholds (US$ Equivalent) Open international (goods, IT, and non- >3 million consulting services) Open national (goods, IT, and non- >100,000 and up to 3 million consulting services) National request for quotation Up to 100,000 (goods/works) Open international (works) >40 million Open national (works) >100,000 and up to 40 million Direct selection No threshold; For goods/works/non-consulting services: According to paragraphs 6.8–6.10 of the Regulations; Public Disclosure Authorized For consultants: According to paragraphs 7.13– 7.15 of the Regulations Framework Agreements For goods, works, and non-consulting services: According to paragraphs 6.57–6.59 of the Regulations Shortlist of national consultants Up to 800,000 1. Procurement prior-review thresholds based on the Moderate rating. The World Bank requires its prior review of the following types of contract:

(a) Works: All contracts more than US$15 million equivalent (b) Goods and IT: All contracts more than US$4 million equivalent (c) Non-consulting services: All contracts more than US$4 million equivalent

Public Disclosure Authorized (d) Consultants: All contracts more than US$2 million equivalent for firms and US$400,000 equivalent for individuals (e) Direct selection: Justification of DS for all contracts more than US$100,000 equivalent

2. National procurement procedure conditions. National competition for the procurement of goods, works, and non-consulting services will be within the thresholds and will comply with the Procurement Provisions of paragraphs 5.3–5.6 of Section V of the Regulations and the following additional provisions:

(a) Only the model bidding documents agreed with the World Bank (as amended from time to time) will be used for bidding. (b) At least 30 days before the deadline for submission of bids, invitations to bid will be advertised in at least one widely circulated national daily newspaper,

Public Disclosure Authorized or on a widely-used website or electronic portal with free national and international access inan abridged version of the advertisement published in a widely circulated national daily, giving details of the electronic portal where the full invitation to bid can be downloaded. (c) No preference will be accorded to any bidder for price or for other terms when competing with foreign bidders, state-owned enterprises, small-scale enterprises, or enterprises from a given state. (d) Extension of bid validity will not be allowed for contracts subject to World Bank prior review without prior World Bank concurrence (i) for the first request for an extension longer than four weeks and (ii) for all subsequent requests for extension whatever the length; concurrence will be considered only in cases of force majeure and other circumstances beyond the control of the purchaser employer. (e) There will be no re-bidding of contracts subject to World Bank prior review without prior World Bank concurrence. In this project, bids will not be rejected for being outside a predetermined range of prices. (f) To improve the efficiency and transparency of small-value purchases in WB- financed projects, the Bank has agreed to allow the following uses of Government e-Marketplace (GeM): (i) in lieu of shopping, up to US$30,000 in catalog mode; (ii) in lieu of shopping, up to US$100,000 if there are at least three suppliers for the item on GeM and the purchaser uses the GeM Request for Quotation feature (mini-competition) to discover the final price; (iii) in both cases, borrowers will record their assessment that the price is reasonable, and (iv) GeM is not to be used in lieu of National Competitive Bidding. (g) No negotiations are to be conducted even with the lowest evaluated responsive bidders.

Domestic preference. Domestic preference will be applied in evaluating bids in accordance with Annex VI of the Regulations. PROCUREMENT : AP Integrated Irrigation & Agriculture Transformation Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2020-09-28 Revised Plan Date(s): (comma delineated, leave blank if none)2021-01-06 Project ID: P160463 GPN Date: Project Name: AP Integrated Irrigation & Agriculture Transformation Project Loan / Credit No: IBRD / 89100 Executing Agency(ies):Irrigation Circle,

WORKS Activity Reference No. / Estimated Actual Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification High SEA/SH Procurement Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Contract Description Component Review Type Method Market Approach Amount Amount Document / and Recommendation Signed Contract No. Process (Y/N) Risk Document Type Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Completion (US$) (US$) Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned

IN-ICKURAPIIATP-186946- CW-RFB / Rehabilitation of Nelathalamarri Tank Component A: Improving Under Single Stage - One 2022-07- (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 78,527.61 52,520.95 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 Envelope 05 Nelathalamarri Village in Efficiency ion Devanakonda Mandal in Kurnool District Under APIIATP

IN-ICKURAPIIATP-187100- CW-RFB / Rehabilitation of Thangadencha MI Tank Component A: Improving Under Single Stage - One 2022-07- (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 99,693.25 68,537.06 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 Envelope 05 Thangadencha Village in Efficiency ion Jupadubunglow Mandal in Kurnool District Under APIIATP

IN-ICKURAPIIATP-187108- CW-RFB / Rehabilitation of Peddacheruvu and Ramagiri Component A: Improving Under Tank Cascade No.16 in Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 105,674.85 74,320.48 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 Nallachelimala and Envelope 05 Efficiency ion Nallagundla Village in Tuggali Mandal in Kurnool District Under APIIATP

IN-ICKURAPIIATP-187111- CW-RFB / Rehabilitation of Jilledubudakala and Component A: Improving Under Karivemula MI Tank Cascade Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 292,331.29 207,786.76 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 No.06 in Jilledubudakala and Envelope 05 Efficiency ion Karivemula Villages in Devanakonda Mandal in Kurnool District Under APIIATP

IN-ICKURAPIIATP-187114- CW-RFB / Rehabilitation of Component A: Improving Under Hythakhan Tank Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 122,546.01 89,841.94 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 (Independent) in Uppalapadu Envelope 05 Efficiency ion Village in Owk Mandal in Kurnool District Under APIIATP

IN-ICKURAPIIATP-188427- CW-RFB / Rehabilitation of Component A: Improving Under Muthukur MI Tank Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 207,515.34 148,571.29 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 (Independent) in Muthukur Envelope 05 Efficiency ion village in Aspari Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-192031- CW-RFB / Rehabilitation of Uricheruvu ( Pathikonda MI Component A: Improving Under Single Stage - One 2022-07- Tank) (Independent) in IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 85,429.45 65,099.27 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 Envelope 05 Pathikonda village in Efficiency ion Pathikonda Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-192033- CW-RFB / Rehabilitation of Component A: Improving Under Chinnahothur MI Tank Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 114,877.30 81,508.89 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 (Independent) in Envelope 05 Efficiency ion Chinnahothur village in Aspari Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-192036- CW-RFB / Rehabilitation of Component A: Improving Under Bilehal MI Tank (Independent) Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 130,904.91 97,949.07 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 in Bilehal village in Halhavarvi Envelope 05 Efficiency ion Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-192039- CW-RFB / Rehabilitation of Challavanka MI Tank Component A: Improving Under Single Stage - One 2022-07- (Independent) in Hebbatam IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 124,539.88 90,633.89 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 Envelope 05 village in Holagunda Mandal Efficiency ion in Kurnool District under APIIATP

IN-ICKURAPIIATP-192041- CW-RFB / Rehabilitation of Component A: Improving Under Chintakaunta MI Tank Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 160,122.70 115,455.49 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 (Independent) in Chintakaunta Envelope 05 Efficiency ion village in Halhavarvi Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-192044- CW-RFB / Rehabilitation of Saranala Vanka MI Tank (Maha Component A: Improving Yogi Laksmamma cheruvu) Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 113,803.68 0.00 Canceled 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-12-01 2021-01-05 (Independent) in Pedda Envelope 05 Efficiency Harivanam village in Mandal in Kurnool District under APIIATP

Page 1 IN-ICKURAPIIATP-192046- CW-RFB / Rehabilitation of Component A: Improving Under Pedda Cheruvu MI Tank Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 80,521.47 55,884.32 Implementat 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-11-12 2020-12-01 2020-12-09 2021-01-05 (Independent) in Isvi village in Envelope 05 Efficiency ion Adoni Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-193110- CW-RFB / Rehabilitation of Component A: Improving Udumulapadu MI Tank Single Stage - One 2022-07- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 148,619.63 0.00 Canceled 2020-10-07 2020-10-07 2020-10-12 2020-11-11 2020-12-01 2021-01-05 (Independent) in Envelope 05 Efficiency Udumulapadu village in Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-210563- CW-RFB / Rehabilitation of Component A: Improving Pending Udumulapadu MI Tank Single Stage - One 2022-09- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 148,619.63 0.00 Implementat 2021-01-21 2021-01-25 2021-03-03 2021-03-07 2021-03-19 (Independent) in Envelope 16 Efficiency ion Udumulapadu village in Dhone Mandal in Kurnool District under APIIATP

IN-ICKURAPIIATP-210570- CW-RFB / Rehabilitation of Saranala Vanka MI Tank (Maha Component A: Improving Pending Yogi Laksmamma cheruvu) Single Stage - One 2022-09- IBRD / 89100 Irrigated Agriculture Post Request for Bids Open - National 113,803.68 0.00 Implementat 2021-01-21 2021-01-25 2021-03-03 2021-03-07 2021-03-19 (Independent) in Pedda Envelope 16 Efficiency ion Harivanam village in Adoni Mandal in Kurnool District under APIIATP

GOODS Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

NON CONSULTING SERVICES Activity Reference No. / Draft Bidding Bid Evaluation Report Loan / Credit Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents as Proposal Submission / Description Component Review Type Method Market Approach Document / and Recommendation Signed Contract Contract Completion No. Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation Issued Opening / Minutes Justification for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Contract Type Estimated Actual Amount Draft Negotiated Description Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

Page 2