M/s Tamilnadu Cements Corporation Ltd. MODIFICATIONS TO THE APPROVED MINING PLAN ALONGWITH PROGRESSIVE MINE CLOSURE PLAN OF ANANDAVADI LIMESTONE MINES

G.O.Ms.No.624 Dated 23.09.1998

EXTENT-110.68.5 HA. TALUK & DISTRICT

(UNDER RULE 12 OF MCDR 1988) Introduction

M/s Tamilnadu Cement Corporation Ltd was incorporated in the year 1962 with the Register of the companies, Chennai, Tamilnadu. Copy of Certificate of incorporation is enclosed as Annexure No - 1

M/s. Tamilnadu Cement Corporation Limited belong to Government of Tamilnadu enterprise is having two cement units, one at Alangulam and another at Ariyalur. The installed capacity of the Ariyalur cement unit is 5 lakh tonnes per annum. It is a modern dry process plant. TANCEM has expanded the capacity of Ariyalur Works from 5 lakh tones per annum to 15 lakh tones per annum by installing the Green field plant and proposed to commission the unit on August 2018. Details of Mining leases held by Tamilnadu Cement Corporation – Ariyalur Unit

Lease Name of the Area in Area in validity G.O.No &Date Status Villages Hectares Acres Period up

to Kallankurichi – Periyanagalur limestone mines. G.O.Ms.344 Deemed Kallankurichi, dated 10.03.2080 240.61.0 594.32 26.04.2001 renewal Khairulabad Under rule Ameenabad. G.O.Ms.456 24 (A)6 of Periyanagalur dated 16.05.1985 MCR 1960 Kallankurichi 194.16.5 479.91 12.11.2005 Khairulabad Ameenabad. G.O.Ms.469 Kurumbanchavadi dated 21.05.1985 66.11.0 163.29 12.11.2005 Khairulabad Ameenabad Total 501.02.0 1237.52

Area in Area in Status Name of the Villages G.O.No &Date Hectares Acres G.O.Ms.624 dated 23.09.1998 110.68.5 273.39 Live Anandavadi

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 1

M/s Tamilnadu Cements Corporation Ltd.

History of Mining Lease: Details of Mining lease:  The mining lease was initially granted for a period of 20 years and approved vide letter no. G.O. (MS) No. 624 dated 23.09.1998, for the period of 30 years.  Subsequently the lease deed was executed on 16.03.2000, and got registered on 13.07.2001 and the period is valid up to 16.03.2030,  As per the section 8 A (5) of new MMDR amendment act 2015, the validity of this lease is deemed to be extended till 16.03.2050.  The copy of G.O. and Mining Lease deed are enclosed as Annexure-2 & Annexure-3 respectively.

DETAILS OF MINE PLAN /SCHEME OF MINING:

S. No. Mining plan / Under MCR or Approval letter No. Date Scheme of Mining MCDR 01 Mining Plan Under Rule 22 (4) of TN/PBR/Lst-MP/916-SZ MCR 1960 dated 18.10.2000. 02 Scheme of Mining Under Rule 12 (3) of TN/PBR/Lst-MS/396-SZ MCDR 1988 dated 06.10.2006 03 Scheme of Mining Under Rule 12 of TN/ALM/LST/MS-662-MDS, MCDR 1988 Dated, 27.04.2012. 04 Scheme of Mining Under Rule 12 of TN/ALM/LST/MS-1300- MCDR 1988 MDS, Dated, 25.01.2016.

 Refer Annexure No – 4 for approval letter of approved Scheme of Mining.

Environmental Clearance from MOEF:  Environmental clearance has been obtained from Ministry of Environment & Forest vide their letter No –No.J-11015/15/99-IA II(M) dated 22.11.1999 over an extent of 110.68.5 Ha for production capacity of 0.26 Million TPA of limestone at village Anandavadi , Sendurai Taluk , Ariyalurl District, Tamilnadu State.  The copy of MoEF clearance letter is enclosed as Annexure No-5.

Reason for Modification

 The applicants already carried out the detailed exploration during the year 1984.  New expansion plant capacity of 1.0 Million ton per annum and expected to commission in the month of august 2018.  The applicant company has proposed to enhance the clinker production from 5.0LTPA to 15.0LTPA. Hence to meet required limestone the applicant company has proposed to enhance

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 2

M/s Tamilnadu Cements Corporation Ltd.

the limestone production from 2.60 Lakhs tons to 15.0 Lakhs tons per annum from 2018-19 to 2020-2021. The Scheme of Mining for G.O.Ms.No. 624, dated 23.09.1998 over an extent of 110.68.5 Ha has been approved by Indian Bureau of Mines under Rule 12(3)of MCDR 1988 for the period 2016-17 to 2020-2021 vide approval No.TN/ALM/LST/MS- 1300 -MDS, dated, 25.01.2016

Hence, the present Modification to the Approved Mining Plan is prepared for the period 2018-19 to 2020-21 Under Rule 17(3) of MCR-2016.

(B.Gangatharan) Qualified Person

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 3

M/s Tamilnadu Cements Corporation Ltd.

MINING LEASE DETAIL SUNDER TANCEM ARIYALUR UNIT

S. G.O.No & Total Area Working/ Location Minerals Status Details N date (in Hec) Non Working

1. 344/ dated 146.45.0 Kallankurichi Limestone Non Working Lease expired on Lr.No and date of 10-03-1980 61.38.0 Ameenabad 26-04-2001. approval of Mining 32.78.5 Kairulabad Renewal application Scheme(For G.O344) 240.61.5 submitted TN/PBR/MS/LST-1257- SZ Dt.19-01-2001. 2. 456/dated 31.70.0 Periyanagalur Limestone Non Working Lease expired on Lr.No and date of 16-05-1985 3.86.0 Ameenabad 12-11-2005. approval of Mining 71.96.5 Kairulabad Renewal application Scheme (For G.O.456) 86.77.0 Kallankurichi submitted TN/PBR/LST-MS-86-SZ 194.16.5 Dt.29-03-2001

3. 469/ dated 10.16.0 Ariyalur Limestone Non Working Lease expired on Lr.No and date of 21-05-1985 8.49.0 Ameenabad 12-11-2005. approval of Mining 32.47.0 Kallankurichi Renewal application Scheme(For G.O. 469) 14.98.0 Kairulabad submitted TN/PBR/LST-MS-86-SZ 66.11.0 Dt.29-03-2001 Lease executed on Lr.No and date of 4. 624/dated 110.68.5 Anandavadi Limestone Working 16.03.2000. approval of Mine Plan 23-09-1998 Valid for50 years. (For G.O.624) TN/TCR/MP/LST-916-SZ Dt.18-10-2000

ALANGULAM UNIT S G.O.No & date Total Area Location Minerals Working/ Status Details N (in Hec) Non o Working 1 871/MMD2 dated 233.99.5 Lakshmipuram Limestone Non - (Renewal application Lr.No and date of . 20-08-1990 176.56.0 Gopalapuram Working submitted) approval of Mine Plan 9.69.5 Vadakarai TN/TNL/MP/L.St-1122------SZ. Dt 10-02-2004 420.25.0 2 595/Ind dated 179.19.5 Alangulam Limestone Non - (Renewal application Lr.No and date of . 03-04-1972 1.63.5 Lakshmipuram Working submitted) approval of Mine Scheme ------TN/VDN/L.St/MS-74/SZ 180.83.0 dated 13-03-2005 3 427/Ind dated 113.50.0 Alangulam Limestone Non - (Renewal application Lr.No and date of . 19-03-1980 57.62.5 Pernaickenpatti Working submitted) approval of Mine Scheme 3.80.5 Duraisamypuram TN/VDN/L.St/MS-74/SZ 76.20.0 Edrikottai dated 13-03-2005 11.51.0 Narayanapuram 6.16.0 Lakshmipuram ------268.80.0 4 729/Ind dated 24.32.5 Pandapalli Limestone Non - (Renewal application Lr.No and date of . 19-07-1980 Working submitted) approval of Mine Scheme TN/TNL/L.St/MS-360/SZ dt 17-05-2006

5 G.O. 3 D.No 4.91.5 Pandapalli Limestone Non - (Renewal application Lr.No and date of . 107/Ind dt 2.64.0 Thenmalai Working submitted) approval of Mine Scheme 11-07-1997 ------TN/TNL/MP/L.St- 149/SZ 7.55.5 dated 18-05-2006. ------

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 4

M/s Tamilnadu Cements Corporation Ltd.

VIRUDHACHALAM UNIT 1 G.O.M.S. 6.61.5 Panikuppam Clay Non (Renewal application Lr.No and date of approval of . No 409/Ind dt Working submitted) Mining Plan (For G.O.2127) 12-10-1993 TN/SA/FC-15-SZ Dt.25-02- 1991. 2 G.O.M.S. 12.30.0 Theranipalayam Clay Non (Renewal application Lr.No and date of approval of . No .198/Ind dt Working submitted) Mining Scheme (For G.O.198) 26-02-1986 TN/TCR/FC/MS-108-MDS dt 04-07-2001.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 5

M/s Tamilnadu Cements Corporation Ltd.

1.0 GENERAL a) a) Name of applicant /lessee/Rule 45 registration no. IBM/7446/2011

Registered Office : M/s. Tamilnadu Cements Corporation Ltd (A Govt. of Tamilnadu Undertaking) 735, Anna Salai, nd L.L.A Building, II Floor, Chennai-600 002, Tamilnadu. Telephone No. : 044 28525461 044 28525471 044 28525230 044 28591735

Telegraph : TANCEM. Fax : 044 28523991 E-mail : [email protected]

Address of authorized : Mrs. D.Sabita, I.A.S, Principal Secretary/Managing Signatory Director/Nominated Owner

Registered Office : M/s. Tamilnadu Cements Corporation Ltd (A Govt. of Tamilnadu Undertaking) Ariyalur Cement Factory, Ariyalur-621 729. , Tamilnadu. Telephone No. : 04329 228531

Telegraph : TANCEM. Fax : 04329 228776 E-mail : [email protected]

Copy of photo identity card of leassee with permanent address proof & certified true copy of the Board resolution is enclosed as annexure-4. List of Board of Directors is enclosed as annexure-5

b) Status of applicant/lessee

 The lessee is a Government of tamilnadu Enterprises, engaged in mining and manufacture of cement.  The company manufactures Portland cement and other various blended cements.  For the purpose of Acts and Rules connected with mining operations Smt Sbita, IAS, has been nominated as the authorized signatory for all the mines coming under M/s Tamilnadu Cements Corporation Ltd.  Board of Directors of the company is enclosed as Annexure No- 6.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 6

M/s Tamilnadu Cements Corporation Ltd.

 A copy of the resolution of Board of Directors nominating the owner is enclosed vide Annexure No- 7.  Photo Id of the authorized signatory is also enclosed as Annexure No – 8.

c) Mineral(s) which is / are included in the prospecting license (For Fresh grant)

N.A d) Mineral(s) which is / are included in the lease deed

LIMESTONE e) Mineral(s) which is the applicant /lessee intends to mine:

LIMESTONE

f) Name of Recognized Person under employed under clause (c) of Sub rule (1) of rule 42 of MCDR, 1988 (Applicable for Scheme of Mining only):

Name : Shri.B.Gangatharan Address : M/s Sai Geo Survey Consultant, 10 A,Palayam Bazaar, Woraiyur , Trichy- 620003. Phone : 0431- 2765071 Fax : Nil Email : [email protected] Mobile No. : 94431-01165, 9788842209 The copy of Qualified Person Education certificate and having of experience in this field is enclosed as annexure-9.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 7

M/s Tamilnadu Cements Corporation Ltd.

2.0 LOCATION AND ACCESSIBILITY a) Lease Details (Existing Mine)

Name of mine : ANANDAVADI LIMESTONE MINES

The mining lease area falls in the Survey of India Topo-sheet no. 58 M/4 and bounded by following co- ordinates

Latitude Longitude

11011’12” – 11011’27” 79010’54” – 79011’56”

Date of grant of lease : 23.09.1998 Period/Expiry : 30 years from 13.07.2001 to 12.07.2031

Period/Expiry Date : This lease period is valid for 30 years and the expiry Date is 16.03.2030 and lease period will be extended up To 31.03.2050 as per Section 8 A (5) of Mines and Minerals (Development and Regulations) Amendment Act 2015. Owner : M/s Tamilnadu Cement Corporation Ltd.

Name of Lessee M/s. Tamilnadu Cements Corporation Ltd Registered Office : (A Govt. of Tamilnadu Undertaking) 735, Anna Salai, L.L.A Building, IInd Floor, Chennai-600 002, Tamilnadu. Telephone No. : 044 28525461 044 28525471 044 28525230 044 28591735 Telegraph : TAMCEM. Fax : 044 28523991 E-mail : [email protected] Address of the Works Tamilnadu Cement Corporation Limited, Ariyalur Cement Works, Ariyalur – 621 729. Ariyalur District, Tamilnadu. Phone 04329 222131, 222132, 222068 Fax 04329 – 222467 Grams TANCEM – ARIYALUR E-Mail [email protected]

Details of lease area with location map (mine)

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 8

M/s Tamilnadu Cements Corporation Ltd.

Forest Non-forest Area (ha) Area (ha) Forest (specify) (i) waste land, (ii) grazing land, NIL (iii) Agriculture land, 110.68.5 (iv)others(specify Dry Land

The details of the S.F.Nos.are shown on authenticated lease sketch and is enclosed as Plate No – 2. Further details of the Survey Nos are enclosed as Annexure No – 2 & 3 Total lease area : 110.68.5 Hectares

District : Ariyalur & State : Tamilnadu

Taluka : Sendurai Village: Anandavadi

Whether the area falls under Coastal Regulation Zone (CRZ)? If yes, details thereof.

No

Existence of public road/railway line, if any nearby and approximate distance .

Road The mining lease area is situated 10 Km from Ariyalur on Ariyalur – Sendurai - Jayankondam road Railway Line Ariyalur railway station is located at a distance of 12 kms from this mine site. Toposheet No. with latitude & longitude of all corner boundary point/pillar

The area of Mining lease falls in Survey of India Toposheet No.58 M/4.

The mining lease area falls in the Villages Longitude Lattitude Survey of India Topo-sheet no. Anandavadi 11011’12” – 79010’54” – 58 M/4 and bounded by following 11011’27” 79011’56” co-ordinates

Details of Latitude and Longitude of the three permanent ground control points situated outside lease area.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 9

M/s Tamilnadu Cements Corporation Ltd.

Ground Control Point: Lat – Long Bearing

GCP - 1 Transformer N 11°11’22.5” E79°10’47.9” 419m NW from GCS -1 Elevation : 101m GCP - 2 Burial Ground N 11°11’12.7” E 79°10’53.3” 98m W from GCS - 1

Elevation : 97m GCP –3 Variattan Koil N 11°11’15.7” E 79°10’54.0” 137m NW from GCS -1 Elevation : 97m Ground Control Station GCS –1 Boundary Pillar Near Burial N 11°11’11.8” E 79°10’56.3” Ground Elevation : 95m GCS –2 Boundary Pillar Near N 11°11’26.8” E 79°10’54.9” Anandavadi to Irumbulikurichi Road Elevation : 99m

Photograph of the lease area and Ground Control Stations – Annexure -11. c) Attach a general location map showing area and access routes. It is preferred that the area be marked on a Survey of India topographical map or a cadastral map or forest map as the case may be. However, if none of these are available, the area may be shown on an administrative map.

Plate No.:1

3.0 DETAILS OF APPROVED MINING PLAN / SCHEME OF MINING (if any)

3.1 Date and reference of earlier approved MP/SOM.

S.No. Mining plan / Under MCR or Approval letter No. Date Scheme of Mining MCDR 01 Mining Plan Under Rule 22 (4) of TN/PBR/Lst-MP/916-SZ MCR 1960 dated 18.10.2000. 02 Scheme of Mining Under Rule 12 (3) of TN/PBR/Lst-MS/396-SZ MCDR 1988 dated 06.10.2006 03 Scheme of Mining Under Rule 12 of TN/ALM/LST/MS-662-MDS, MCDR 1988 Dated, 27.04.2012. 04 Scheme of Mining Under Rule 12 of TN/ALM/LST/MS-1300- MCDR 1988 MDS, Dated, 25.01.2016.

Copy of IBM approval letter is enclosed as annexure no.4.

3.2 Details of last modifications if any (for the previous approved period) of approved MP/SOM, indicating date of approval, reason for modification

NIL

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 10

M/s Tamilnadu Cements Corporation Ltd.

3.3 Give review of earlier approved proposal (if any) in respect of exploration, excavation, reclamation etc.

3.3.1(a):Exploration:

Director of Geology & Mining along with TANCEM carried out systematic exploration of the area in the year 1984-85. By exploratory core & Noncore boreholes were drilled covering almost the entire strike length. The drill holes were drilled regular grid pattern.

The geological mapping was done on the topographic plan, which is the base map, prepared on a scale of 1: 4000, with a contour interval of 1 meter. .

Diamond drill holes and Wagon drill holes were placed at closer intervals (i.e.) 400 M and 200M respectively. The bore holes within the lease area were drilled in grid pattern running NE-SW direction. Geological cross sections were prepared, on a scale of 1: 2000, along -the dip direction, joining the diamond drill holes drilled along the grid line (Please refer Plate-3 & 3a).

The details of drilling, sampling and other exploration done in the area of GO MS 624 are given below.

Quantity of S. No Details of Exploration Grid interval Remarks Work 01 Diamond drilling (a) No. of holes completed 27 400 Mtrs Location of (b) Metreage 845.75 BH /WDH 02 Wagon drilling are shown (a) No. of holes completed 19 400 Mtrs in the 206 Geological (b) Metreage Plan-Plate- 3 03 Total No. of samples 850 collected The exploration of the area reveals the presence of limestone and associated litho units of varying thickness throughout the area.

During the scheme period 2016-17 to 2020-2021, the exploration proposals has been made in the regular grid and will be put in between the earlier bore holes to know the deposit and further enhancement of reserves. As per the discussions had the company officials, at the present period of scheme of mining the company has proposed the total of 20 nos. coring bore holes from the year 2017-18 to 2020-21 at the rate of 5 bore holes in every proposal period as per the UNFC guidelines.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 11

M/s Tamilnadu Cements Corporation Ltd.

Sl.No. Year of No. of Bore hole Type Proposed Achieved Proposals depth of BH Depth of BH 1. 2017-18 PBH-1 to PBH-5 Coring 125.0m Nil Total 5 Nos. 125.0m

Reason for deviation: Due to employment / agitation made by land given people and local villagers to the company, there was no production during the year 2016-17 and at the end of year 2017-18 in the month of February second 2018; the company has started mining operation. 3.3.1(b): Mine Development:

Proposed Achieved development development (in tons) (in tons) Year Top Sand Top Sand soil stone/Waste soil stone/Waste 2016-17 Nil 130000 Nil Nil 2017-18 (03.02.2018 to Nil 130000 Nil 13900 31.03.2018) Total Nil 260000 Nil

During scheme mining period, the production was commenced in the year 2016-17 to tune of 260000 tons only. There is no production from this lease due to local social problem by previous land owners and demanding their permanent employment with the company. Due to employment / agitation made by land given people and local villagers to the company, there was no production during the year 2016-17 and at the end of year 2017-18 in the month of February second 2018; the company has started mining operation.

3.3.1C: Exploitation of Mineral:

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 12

M/s Tamilnadu Cements Corporation Ltd.

In the previous approved scheme of mining, the production was projected as 2.60 lakh Tons per annum for five year period from the year 2016-17 to 2020-21.

Proposal Achieved

Production Production Year (in tons) (in tons)

2016-17 260000 Nil 2017-18(03.02.2018 to 260000 58514.56 31.03.2018) Total 520000

It may be seen from above that production could not be achieved as per the targeted production of the previous scheme period year 2016-17 and 2017-18, are due to the following reasons

---Cost of Mining & Transportation ---Administrative issues of M/s. TANCEM due to the local social problem by previous land owners and demanding their permanent employment with the company. Due to employment / agitation made by land given people and local villagers to the company, there was no production during the year 2016-17 and at the end of year 2017-18 in the month of February second 2018; the company has started mining operation. . Actual grade of limestone found during production is as follows.

Blast Sample SiO Al O Fe O CaO /Bench 2 2 3 2 3 I Limestone 10.15 2.97 1.20 44.58 II Limestone 16.4 3.24 2.28 34.30

3.3.1(d): Method of mining: The method of working is opencast (A category fully mechanized) adopting non-conventional method by deploying rock breaker for primary and secondary breaking eliminating drilling and blasting thus adopting eco-friendly mining.

Primary and Secondary Breaking: Mega Rock Breaker of 150 TPH capacity will be deployed for primary breaking and dilution of oversize boulders which will totally eliminate drilling and blasting.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 13

M/s Tamilnadu Cements Corporation Ltd.

Loading and hauling: Excavator will be used for loading the material on to the tippers (hauling units) which will be used for transportation of mineral from the mines to crusher at plant site and for handling the overburden / reject.

Rock breaker will be used for primary breaking wherever required and also for reduction of oversize boulders instead of secondary blasting.

BENCH PARAMETERS:

Bench height - 6m

Bench Width - 8m

Ultimate Pit Slope - 450

Depth of Mining - 21 m maximum up to 80 RL.

Present pit dimension is as follows.

Name of the Pit Length (M) Width (M) Depth (M) RL(M) North pit 180 230 12 85 South pit 100 80 12 85

No Deviation in method of Mining Method

The thickness of topsoil is meager and will be stacked for the purpose of afforestation. The benches shall be sloped at an angle of 45o individual bench in limestone shall also be of 6 m height and the width of the benches shall always be maintained more than the height.

Present pit dimension : 180M (Length) x 230 M (Width) x 12 (Depth)

RL 97.0 M to 85.0 M

Bench parameters. For North pit:

No. Bench Top R.L Bottom R.L Height L x W

I st Bench 100 M 94 M 6.0 M 210 M x 145 M Topsoil & sandstone

II nd Bench 92 M 88 M 6.0 M 100M x 60M

Bench parameters.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 14

M/s Tamilnadu Cements Corporation Ltd.

For South pit:

No. Bench Top R.L Bottom R.L Height L x W

I st Bench 100 M 94 M 6.0 M 100 M x 60M Topsoil & sandstone

II nd Bench 92 M 88 M 6.0 M 80M x 60M

3.3.1(e): Drilling and Blasting:

No drilling and blasting is envisaged during the modifications to the approved mining plan during 2018-19 to 2020-21. 3.3.1(f): Disposal of waste: The nature of top soil is Black cotton soil and has been removed and dumped all along the mine lease boundary for the Afforestation purposes. No sub-grade ore or mineral rejects is generated during the scheme period.

 During the year 2016-17 to year 2017-18 of the plan period, no top soil was proposed. The entire topsoil in the mineable area of the lease area will be removed and will be utilised straight away for afforestation/ green belt purpose.  The mineral reject generated during mining will also be stacked along the western boundary in a separate dump yard.  Dimensions of the waste dump are given below :

Dump Length (m) Width (m) Height (m) Waste Dump-1 100 60 18 Waste Dump-1 80 40 12

3.3.1(g): Environment Management: There is no production from this lease due to local social problem by previous land owners and demanding their permanent employment with the company. During scheme of mining period, impact of mining activities on the environment was very less. The mining operation was started in the year 03.02.2018; subsequently the production was commenced in the year 2018-19 to the tune of 260000 tons only.

During the previous scheme period of mining afforestation proposals were made, however it

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 15

M/s Tamilnadu Cements Corporation Ltd.

could not be achieved since the mining operation was commenced in the year 2018-19, due to the local issues. Proposed Afforestation programme for five years period:

Area Achieved No. of Year Covered Survival Places of Species Saplings (Ha) rate plantation 2016-17 1500 1.00.0 80% Safety zone Eucalyptus & Nil barrier Caurina 2017-18 1500 1.00.0 80% -Do- -Do- Nil Total 3000 2.00.0

Review of Environmental proposals and the status of compilation at the end of the Mining plan period.

SL PROPOSALS AS PER APPROVED POSITION AT THE END OF NO. ITEM SCHEME OF MINING SCHEME OF MINING PERIOD

1 2 3 4 Total quantity of top soil proposed to be Since production was not met that 1. Top soil storage handled is Nil. The existing dumping target. The top soil handled Nil. Proposals were made in the non Topsoil is stored separately on the mineral bearing adjoining to the working designated place so far. There is no pit and in eastern side of the lease area. deviation from the proposal Store it separately for future use in spreading afforestation areas No proposals for reclamation and The mining is not yet reached the 2. Land reclamation and rehabilitation in the approved scheme of basement and the production rehabilitation mining are given, as limestone would achieved during the period is very not be exhausted. meager 0.58 Lakh tonnes.

Proposals were to store topsoil & waste Topsoil, and waste rock sandstone is 3. Waste dump sandstone separately and places were being stacked at the designated management earmarked for the purpose. places separately. No deviation from approved scheme of mining Afforestation programme In the approved mining scheme 7500No Till date eucalyptus & casurina is 4. with precautions for of trees are proposed to cover an area planted about 80.0 Ha having tie up survival and protection of 5.0 Ha. with TNPL. of plantation Periodical environmental monitoring of Periodical environmental monitoring 5. Quality of air. air quality to be conducted. of air quality conducted as per IBM/MoEF norms quarterly The latest environmental monitoring

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 16

M/s Tamilnadu Cements Corporation Ltd.

reports is enclosed as annexure-2

Periodical environmental monitoring of Periodical environmental monitoring 6. Quality of water. Water quality to be conducted. of water quality conducted as per IBM/MoEF norms quarterly

Periodical environmental monitoring of Periodical environmental monitoring 7. Noise level noise level to be conducted. of noise level conducted as per IBM/MoEF norms quarterly

Periodical environmental monitoring of Periodical environmental monitoring 8. Ground vibration. Noise level to be conducted. of Noise level conducted as per IBM/MoEF norms quarterly

Treatment of mine water There was no proposal to treat ground Monitoring and study was made and 9. including surface and or surface water. there will be no toxic effluent that will ground water. be discharged from the mine hence, no treatment of ground and surface water. Re-circulation of treated No proposal in the approved scheme of No re-circulation of treated water 10. water. mining for re-circulation of treated water done. This was not applicable. as there was any need to treat water in the mine.

3.4 : Status of compliance of violations pointed out by IBM.

Indian Bureau of Mines has pointed out following violations under MCDR’ 1988. Compliance position thereof is also discussed below.

Description of Violation Rule Compliance Position Date of No. Compliance The scheme of mining was approved vide letter Rule The applicant company requested no TN/TCR/LST/ Ms/ -396-SZ dated 2(3) time for submission delay vides their 06.10.2006 for G.O.No. 624. letter. The present scheme of mining 02.04.2010 is prepared in view of compliance of

The five year proposals given in the scheme of the above violation. mining has been expired on 31.04.2010. As such the scheme of mining has fallen due for submission. The same has not been submitted for approval to the Regional controller of Mines, Indian Bureau of Mines, Chennai so far

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 17

M/s Tamilnadu Cements Corporation Ltd.

3.5 Indicate and give details of any suspension /closure/ prohibitory order issued by any Government agency under any rule or Court of law . NIL

3.6 In case the MP/SOM is submitted under rules 9 and 10 of the MCDR’88 or under rule 22(6) of the MCR’1960 for approval of modification, specify reason and justification for modification under these rules.

Since the applicant company has proposed to enhance the clinker production, to meet the required limestone the applicant company, the company has proposed to start the expansion plant capacity from 0.5 million tons to 1.50 million tons per annum in the month of August 2018, the company ought to enhance the limestone production from 2.60 lakhs tons to 15.0 lakh tons per annum for the period from 2018-19 to 2020-21. And hence the present modification to the approved mining plan is prepared under 17(3) of MCR 2016.

PART – A

1.0 GEOLOGY AND EXPLORATION:

a) Briefly describe the topography, drainage pattern, vegetation, climate, and rainfall data of the area applied/mining lease area.

Topography

The Anandavadi Limestone mines is located in Anandavadi village, Sendurai Taluk, Ariyalur District. The Anandavadi mine is located 10 Km North East of Ariyalur town. The mines can be reached by a good motorable road on Ariyalur – Sendurai – Jayankondam road and forms part of the survey of India Toposheet No.58M/4. The area has a slope towards south east.

Climate & Rainfall:

In this area the maximum temperature recorded during summer season is 400C and the minimum temperature during the winter season is 250 C. The area is generally dry during summer and is receiving a maximum of 900 cm of rainfall mostly between October and December during the north- east monsoon. Water table in this area is far below 20 meters during monsoonal period and 25 metres in summer. The main crops of the area are cashew and chillies.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 18

M/s Tamilnadu Cements Corporation Ltd. b) Brief descriptions of Regional Geology with reference to location of lease area.

Regional Geology:

The lease area forms part of the Trichy-cretaceous formations, have been studied in detail during the past several decades in view of their Geological and paleontological interest.

The following geological sequence can be made out in this area.

Geological Formations with Lithology Age Geological period Recent and - Alluviam, Kankar, Laterite, etc. Quaternary

Varigated clays with nodules of Palaeocene Niniyur (Danian limestone and marl with occasional boulers of flint and chert.

White friable sandstone and purple Cretaceous Upper clays Ariyalur Loose conglomerates and yellow (Maestrichtian) fossil ferrous limestone, marls and Lower hard limestone clays and sandstone. Calcareous, gritty sandstone, shell Trichinopoly limestone and conglomerate (Turonian to Senonian) sandstone The general trend of the rock formation is NNE – SSW with a low dip of 2 to 5° towards East.

Local / Mine Geology

The local geological sequence.

Arenaceous Limestone and Sandstone

Shell Limestone-1

Arenaceous Line stone and sandstone

Shell Limestone-11

Conglomerate bed.

Arenaceous Limestone and Sandstone

Green Siltstone

Clays

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 19

M/s Tamilnadu Cements Corporation Ltd.

. c) Detailed description of geology of the lease area such as shape and size of the mineral/ore deposit, disposition various litho-units indicating structural features if any etc. (Applicable for Mining Plan for grant & renewal and not for Scheme of Mining/Modifications in the approved mining plan/scheme of Mining).

Not applicable d) (i) Name of prospecting /exploration agency :

(i) Address: Department of Geology and Mining and TANCEM Govt. of Tamilnadu, Guindy, Chennai -32 (ii) E mail : [email protected] and phone no. : 044-28525461 Fax :044-28523991

(iii) Address : M/s. Tamilnadu Cements Corporation Ltd, Anna Salai, Chennai.

e) Details of prospecting/exploration already carried out:

Details of Exploration work:

Director of Geology & Mining along with TANCEM carried out systematic exploration of the area in the year 1984-85. By exploratory core & Non core boreholes were drilled covering almost the entire strike length. The drill holes were drilled regular grid pattern.

Diamond drill holes and Wagon drill holes were placed at closer intervals (i.e.) 400 M and 200M respectively. The bore holes within the lease area were drilled in grid pattern running NE-SW direction. Geological cross sections were prepared, on a scale of 1: 2000, along -the dip direction, joining the diamond drill holes drilled along the grid line.

The details of drilling, sampling and other exploration done in the area of GO MS 624 are given below.

Quantity of Sl.No. Details of Exploration Grid interval Remarks Work 01 Diamond drilling (a) No. of holes completed 27 400 Mtrs Location of (b) Metreage 845.75 BH /WDH 02 Wagon drilling are shown (a) No. of holes completed 19 400 Mtrs in the 206 Geological (b) Metreage Plan-Plate- 3 03 Total No. of samples 850 collected

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 20

M/s Tamilnadu Cements Corporation Ltd.

i) Number of pits and trenches indicating dimensions, spacing etc along and across the strike/ foliation with reference to geological plan.

Details of samples analysis indicating type of sample (surface/sub-surface from pits/trenches/borehole etc) complete chemical analysis for entire strata for all radicals may be undertaken for selected samples from a NABL accredited Laboratory or Government laboratory or equivalent.

Refer litho log Annexure -6a.

IV) Expenditure incurred in various prospecting operations.

Rs.15 Lakhs.

Exploration Proposals:

During the scheme period 2016-17 to 2020-2021, the exploration proposals has been made in the regular grid and will be put in between the earlier bore holes to know the deposit and further enhancement of reserves. As per the discussions had the company officials, at the present period of modifications to the approved mining plan, the company has proposed the total of 15 nos. coring bore holes from the year 2018-19 to 2020-21 at the rate of 5 bore holes in every proposal period as per the UNFC guidelines.

Sl.No. Year of No. of Bore hole Type Proposed Proposals depth of BH 2. 2018-19 PBH-6 to PBH-10 Coring 125.0m 1. 2019-20 PBH-11 to PBH-15 Coring 125.0m 1. 2020-21 PBH-16 to PBH-20 Coring 125.0m Total 15 Nos. 375.0m f) The surface plan of the lease area may be prepared on a scale of 1: 1000 or 1: 2000 with contour interval of maximum of 10 m depending upon the topography and size of the area duly marked by grid lines showing all features indicated under Rule 28(1)(a) of MCDR 1988.

Plate No.4 g) For preparation of geological plan, surface plan prepared on a scale of 1: 1000 or 1: 2000 scale specified under para 1.0 (f) of Part A of the format may be taken as the base plan. The details of exploration already carried out along with supporting data for existence of mineral, locations proposed exploration, various litho units along with structural features, mineralized/ore zone with grade variation if any may be marked on the geological plan along with other features indicated under Rule 28 (1)(b) of MCDR 1988.

Geological Plan Plate No.3:

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 21

M/s Tamilnadu Cements Corporation Ltd. h) Geological sections may be prepared on natural scale of geological plan at suitable interval across the lease area from boundary to boundary.

Geological Cross Section: Plate No.3A

i) Broadly indicate the future programme of exploration with due justification(duly marking on Geological plan year wise location in different colours) taking into consideration the future tentative excavation programme planned in next five years as in table below: -

The Anandavadi limestone deposit can be classified as a simple deposit as given in the CRI(NCBM) guide norms for prospecting, exploration, reserve estimation and technological assessment of cement grade limestone deposits The exploration of the area reveals presence of limestone and associated litho units of varying thickness throughout the area. Considering the available data and the observation of the exposed mine pits by the other companies all around this lease. The additional bore hole has been proposed during this scheme period as given in the page no.22. j) Reserves and Resources as per UNFC with respect to the threshold value notified by IBM may be furnished in a tabular form as given below: (Area explored under different level of exploration may be marked on the geological plan and UNFC code for area considered for different categories of reserve/resources estimation may also be marked on geological cross sections).

Submit a feasibility/pre-feasibility study report along with financial analysis for economic viability of the deposit as specified under the UNFC field guidelines may be incorporated.

Feasibility report Annexure -12. k) Furnish detailed calculation of reserves/resources section wise (When the mine is fully mechanized and deposit is of complex nature with variation of size , shape of mineralized zones, grade due to intrusion within ore zone etc, an attempt may be made to estimate reserves/resources by slice plan method). In case of deposits where underground mining is proposed, reserve/resources may be estimated by level plan method, as applicable, as per the proposed mining parameters.

As per previous Mining Plan Reserve are as follows.

As the deposit is technically feasible and economically viable for mining the total proved reserves

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 22

M/s Tamilnadu Cements Corporation Ltd.

come under UNFC- 111 & 122. After deleting reserve locked up (221) in the safety barrier zone and bench formation,

Reserves as on 31.03.2016.

ABSTRACT Qty UNFC Code Grade Total (in mill. Tons)

High Grade 14903343 14.90 111 Low Grade 3725836 3.73

High Grade 2574149 2.57 221 Low grade 643537 0.64

Total 21846865 21.84

Depletion of Reserves are as follows:

Limestone Year (in MT) 2016-17 Nil 2017-18 58514.56 (From03.02.2018 to 31.03.2018) Total 58514.56

After depletion reserves as on April 2018 are as follows.

ABSTRACT Qty UNFC Code Grade Total (in mill. Tons)

Cement 14848343 14.85 18.58 111 Grade 3725836 3.73

Cement 2574149 2.57 3.21 221 Grade 643537 0.64

Total 21846865 21.84 21.79

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 23

M/s Tamilnadu Cements Corporation Ltd. l) Mineral Reserves/Resources:

Mineral Resources: (Mineral resources may be estimated purely based on level of exploration, with reference to the threshold value of minerals declared by IBM)

Level of Exploration Resources in million tons Grade G1 - Detailed exploration 18.580 Cement G2 - General Exploration 3.210 Cement G3 - Prospecting G4 - Reconnassance

Resources and Reserves within the lease may be arrived after applying results feasibility/pre- feasibility study and economic evaluation of deposit based on various factors such as: a) Mining method, Recovery factor, mining losses, processing loss etc. b) Cut off grade, Ultimate pit depth proposed.

Cut-off grade

The Mining Lease area is located in the state of Tamil nadu the threshold value and cut off grade of limestone as per circular 3/2010 of IBM (Indian Bureau of Mines) is given below:

Limiting Values CaO% MgO% SiO2 Threshold values 35.00 4.00 18.00 Cut Off Grades 35.00 1.00 18.00

Keeping in view the exploitation of limestone for the manufacture of cement, the process parameters of LSF (Lime Saturation Factor), SM (Silica Modulus) and AM (Alumina Modulus) should also be satisfied from the material being fed to the plant. The expected range of the as above parameters is as follows:

Parameters Range

LSF 0-85 – 1.10 SM 2.20 – 2.80 AM 1.20 – 2.50 From the grade of limestone given above it can be observed that the limestone from this leasehold satisfied all the requisite parameters required for manufacture of cement.

Grade control:

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 24

M/s Tamilnadu Cements Corporation Ltd.

As per the norms prescribed by NCBM (National council for Cement and Building Materials) the broad chemical specifications of cement grade ROM limestone are as follows:

CaO%

Acceptable range for manufacture of OPC 44-52

Limiting values taking into consideration Min. 40 type of cements, scope of beneficiation and blending

Thus, limestone with at least 44% CaO is required in the ROM for manufacture of cement and limestone above 40% CaO can be used if beneficiation is provided or higher grade limestone is available which can be blended to upgrade the lower grade limestone upto 44% CaO. The quality of available high grade ore in Anandavadi limestone is of 47.5% CaO content and having less Fe2 O3 & MgO, and this can be blended well with the Kallankurichi deposit limestone materials which are having high Fe2 O3 and less SiO2. The present blending technique and raw mix design is given below. During the enhancement of limestone production and Cement capacity of plant, the blending technique and raw mix design will be modified according to the available grade of limestone and limestone from new mining leases in future.

Grade of Limestone:

The limestone is yellow color fine to medium grain bedded in nature and fossiliferous. The marl is pale yellow and powder in nature overlained by red soil. The purity of limestone is about 70 to 80% TCO3 with little MgCO3. The SiO2 content is ranging from 10-18% in the entire mining area.

The variation in the chemical behavior of this limestone & marl is summarized below

SiO2 (%) Al2O3 (%) Fe2O3 (%) CaO (%) SO3 (%)

Red soil 18.0 - 40.0- 43.0 10.0-13.0 13.0-15.0 10.0-13.0 20.0 Kankar / 10.0-18.0 3.0-4.0 3.0-4.5 43.0- 0.3 – 0.5 Blendable 45.0

Limestone Marl 25.0-35.0 5.0-7.0 5.5-8.0 35.0- 0.4-0.6 37.0

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 25

M/s Tamilnadu CementsChemistry Corporation Ltd. Average Thick Physical Rock type ness characteristics SiO2 Al2O3 Fe2O3 CaO LSF (in m) Top Soil Loose, friable 0.0-0.5 42.76 12.94 14.19 18.78 13.00 Red soil & absorbent Soft yellowish clay OB 5.0-8.0 27.50 8.77 9.55 12.50 6.25 soil Kankar / Yellow medium Bedded 10.18 2.97 3.20 44.58 130.80 grained fossiliferous Limestone 10.0-15.0 Loose pale yellow Marl 21.08 6.33 5.85 35.42 52.12 friable Bottom Conglomeratic Below 15.0 Greyish yellow coarse 41.61 15.81 19.96 14.84 10.00 - sandstone grained

Raw Mix Design:

% of Name of the mine Sio Fe O CaO MgO Contribution 2 2 3 G.O.No.344 25 9.4 4.0 46.3 0.6 G.O.No.456 1 6.5 3.6 48.0 0.5 G.O.No.469 15 16.4 4.6 40.3 1.0 G.O.No.624 60 11.80 0.75 47.5 1.50 Clay (Additive) 04 59.5 7.0 5.0 1.5

c) Mineral/ ore blocked dues to benches, barriers, pillars, road, railway, river, nala, reservoir, electric line and other statutory barriers etc, under forest, sanctuaries etc. where necessary permissions are not available.

As the deposit is technically pre feasible and economically viable for mining the total proved reserves come under UNFC- 111 & 122. After deleting reserve locked up (221) in the safety barrier zone and bench formation,

GEOLOGICAL AXIS:

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 26

M/s Tamilnadu Cements Corporation Ltd.

Refer Feasibility Report: Annexure -12

FEASIBILITY AXIS:-

Refer Feasibility Report: Annexure -12

ECONOMIC AXES:

Refer Feasibility Report: Annexure -12

Based on the above and the Economic axis has been fulfilled all the aspects of UNFC classification, the limestone reserves of the Anandavadi limestone deposit can be categorized “111“.

Refer Feasibility Report Annexure:12

Insitu Reserves of Anandavadi Limestone Mine (As on 01.04.2018):

UNFC Code Quantity in Grade million tons A. Total Mineral Reserve 111 18.58 Cement Proved Mineral Reserve 121 and 122 Probable mineral Reserve B. Total Remaining Resources Feasibility mineral Resource 211 Prefeasibility mineral resource 221 and 222, 3.21 Cement Measured mineral resource 331 Indicated mineral resource 332 Inferred mineral resource 333 Reconnaissance mineral resource 334 Total Reserves + Resources 21.79 Cement

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 27

M/s Tamilnadu Cements Corporation Ltd.

2.0 MINING

A. OPEN CAST MINING: a) Briefly describe the existing as well as proposed method for excavation with all design parameters indicating on plans /sections.

 The method of working is opencast mining considering various technical parameters like surface topography, continuation of limestone deposit, quality variations, geo-technical aspects, required rate of production etc.,  The method of working is opencast fully mechanized adopting non-conventional method by developing rock breaker for primary and secondary breaking eliminating drilling and blasting thus adopting eco-friendly mining.  It is proposed to work this deposit by adopting 6.0 m bench height. The width of working benches will be 8.0m  The ultimate pit slope of the pit is 450  The ramp gradient shall be kept minimum of 1 in 16.

The Following are the steps involved for winning limestone.

Primary and Secondary Breaking: Mega Rock Breaker of 150 TPH capacity will be deployed for primary breaking and dilution of oversize boulders which will totally eliminate drilling and blasting.

Loading and hauling: Excavator will be used for loading the material on to the tippers (hauling units) which will be used for transportation of mineral from the mines to crusher at plant site and for handling the overburden / reject.

Rock breaker will be used for primary breaking wherever required and also for reduction of oversize boulders instead of secondary blasting.

BENCH PARAMETERS:

Bench height - 6m Bench Width - 8m Ultimate Pit Slope - 450 Depth of Mining - 21 m maximum up to 80 RL.

Operating cost: a) Mining (Wages , purchase cost , Explosives) b) Over head cost (Stores, spares, electricity ) Rs.240.85

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 28

M/s Tamilnadu Cements Corporation Ltd.

c) Depreciation, Royalty d) Transportation Rs. 85.80 e) NMET Rs. 16.00 f) DMF Rs. 24.00

Total Rs.366.65 Limestone cost/t Rs.366.65/T

b) Indicate year-wise tentative Excavation in Cubic Meters indicating development, ROM, pit wise as in table below. Following table shows year wise development and estimated production figures for this plan period. I. Insitu Tentative Excavation

Year Pit No. Total tentative Top Soil OB/SB/IB ROM (Cu m) Total ROM/ Excavation (Cu m) (Cum) waste Waste cum Ore Mineral (Cum) Ratio cum reject (Cum) 1 2 3 4 5 6 7 8 9 2018-19 North pit 450000 Nil 150000 300000 Nil 150000 1:0.50 South Pit 675000 225000 450000 225000 Total 1125000 375000 750000 375000 2019-20 North pit 450000 Nil 150000 300000 Nil 150000 1:0.50 South Pit 675000 225000 450000 225000 Total 1125000 375000 750000 375000 2020-21 North pit 450000 Nil 150000 300000 Nil 150000 1:0.50 South Pit 675000 225000 450000 225000 Total 1125000 375000 750000 375000 Total 3375000 1125000 2250000 Nil 1125000

Bulk Density of Limestone=2.0, Waste rock (Sandstone) =2.0

Detailed calculation of Year wise production table with size of pit, level of working and with bench parameters is enclosed as annexure 13.

Quality of Reject / Waste generated during the development:

Chemistry Average Thick Physical Rock type ness characteristics SiO2 Al2O3 Fe2O3 CaO LSF (in m) Top Soil Loose, friable 0.0-0.50 42.76 12.94 14.19 18.78 13.00 Red soil & absorbent Soft yellowish clay OB / Interstitial 0.50-8.0 soil and interstitial 27.50 8.77 9.55 12.50 6.25 reject materials reject

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 29

M/s Tamilnadu Cements Corporation Ltd.

II. Dump re handling (for the purpose of recovery of mineral): Estimated available material (Cum)

No dump re handling

Dump identification/ Year wise Estimated recovery of Reject no handling saleable material (Cum) (Cum) (Cum) *

Nil Nil Nil Nil c) Enclose Individual year wise development plans and sections showing pit layouts, dumps, stacks of mineral reject, if any, etc in case of 'A' category mines. Refer Plate No. 6A to 6C) d) Describe briefly giving salient features of the proposed method of working indicating Category of mine.  The method of working is opencast mining considering various technical parameters like surface topography, continuation of limestone deposit, quality variations, geo-technical aspects, required rate of production etc.,  The method of working is opencast (A Category fully mechanized) adopting non- conventional method by deploying rock breaker for primary and secondary breaking eliminating drilling and blasting thus adopting eco-friendly mining.  It is proposed to work this deposit by adopting 4.0 m bench height. The width of working benches will be 6.0m  The ultimate pit slope of the pit is 450  The ramp gradient shall be kept minimum of 1 in 16. The main work comprises of overburden removal, using rock breaker for mining kankar & limestone.

The Following are the steps involved for winning limestone.

Primary and Secondary Breaking: Mega Rock Breaker of 150 TPH capacity will be deployed for primary breaking and dilution of oversize boulders which will totally eliminate drilling and blasting.

Loading and hauling: Excavator will be used for loading the material on to the tippers (hauling units) which will be used for transportation of mineral from the mines to crusher at plant site and for handling the overburden / reject.

Rock breaker will be used for primary breaking wherever required and also for reduction of oversize boulders instead of secondary blasting.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 30

M/s Tamilnadu Cements Corporation Ltd.

BENCH PARAMETERS:

Bench height - 6m

Bench Width - 8m

Ultimate Pit Slope - 450

Depth of Mining - 14 m maximum up to 80 RL.

e) Describe briefly the layout of mine workings, pit road layout, the layout of faces and sites for disposal of overburden/waste along with ground preparation prior to disposal of waste, reject etc. A reference to the plans and sections may be given. UPL or ultimate size of the pit is to be shown for identification of the suitable dumping site.

Present Pit dimension as follows: For North pit:

No. Bench Top R.L Bottom R.L Height L x W

I st Bench 100 M 94 M 6.0 M 210 M x 145 M Topsoil & sandstone

II nd Bench 92 M 88 M 6.0 M 100M x 60M

For South pit:

No. Bench Top R.L Bottom R.L Height L x W

I st Bench 100 M 94 M 6.0 M 100 M x 60M Topsoil & sandstone

II nd Bench 92 M 88 M 6.0 M 80M x 60M

A sump is being developed in the Eastern side of the pit to collect the surface water. Presently in view of supplying raw material to the cement field, yearly production from this mine is proposed to adopt A category fully mechanized method of mining. The nature of top soil is Black cotton soil and the same has been removed and dumped all along the mine lease boundary. No sub-grade ore or mineral rejects is generated during the modifications to the approved mining plan period. Refer plate No: 6A to 6C f) Conceptual Mine planning up to the end of lease period taking into consideration the present available reserves and resources describing the excavation, recovery of ROM, Disposal of

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 31

M/s Tamilnadu Cements Corporation Ltd. waste, back filling of voids, reclamation and rehabilitation showing on a plan with few relevant sections.

Refer Plate No.8 The following factors have been considered for arriving at the ultimate pit limits. Ultimate pit limit has been determined based on the mineral economics and quality of limestone from the bore hole data. The ultimate size of the pit is ------ha.

This ultimate pit limit is marked on the Geological plan and conceptual plan.

Ultimate pit Dimension : Leaving safety barriers on all sides as per rules, the rest of the lease area will be worked out. Ultimate pit limit has been determined and demarcated on surface plan and geological plan

Ultimate Pit size

No. of Pit Length Width Height Pit slope Benches North 850 M 430 M 4 25M 450 South 1100 M 700 M 3 25M 450

The total excavated area shall be around 60.685Ha at the end of mining operations. It is proposed to convert part of the mined out area as an artificial pond to store rainwater and the remaining by back filling with rejects (sandstone). The area is arid and has a low rainfall about 900mm/yr. Therefore the water stored from rainfall could be used as reservoir in the locality helping the neighboring villagers. The reservoir will have an enough potential to store water. The water in the reservoir thus located shall improve bore well irrigation.

The undisturbed virgin lease area along the mining lease boundary shall be utilized for agricultural purposes by developing the area with eucalyptus and causurina plants with co ordination of Forest department and TNPL. This work shall be done after the cessation of mining operations.

This aspect has been considered in detail. Accordingly conceptual mining plan is drawn. There is adequate space for dumping waste rock. After the mine reaches the ultimate depth waste stacked in the ear marked location will be spread as top capping in the reclaimed area to improve the growth of vegetation.

The total quantity of top soil black cotton soil material has been stacked all along the mining lease boundary and in the eisting top soil dump location area earmarked in the plated no. 6A to 6C

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 32

M/s Tamilnadu Cements Corporation Ltd.

As the mining has not yet reached the ultimate pit limit, there is no proposal for reclamation during this modification period. Mineable reserve and anticipated life of the mines: The proved mineral reserves are 18.58 Mil.T of limestone, having the proposed exploitation fo mineral of 1.5 million tons per annum, the life of the mine will come around 12.38 years, say 13 years. Hence the life of mine is 13 years only with respect to the proposed production rate.. However the life of the mining may be extended in future depending upon the availability of other fresh leases. B. UNDERGROUND MINING Not Applicable ix) Extent of mechanization Describe briefly with calculation for adequacy and type of machinery and equipment proposed to be used in different activities of drilling, material handling in development and stope, hauling, hoisting to surface, surface transportation and any other operation.

Justification of Mining for Mining Machinery Requirements.  The method of working is opencast mining considering various technical parameters like surface topography, continuation of limestone deposit, quality variation, geo- technical aspects, required rate of production etc.,  It is proposed to work this deposit by adopting 6.0m bench height . the width of working benches will also be 6m.  The ultimate pit slope of bench is kept at 45%  The ramp gradient shall be kept minimum of 1 in 16.

EXTENT OF MECHANISATION:

For the proposed production of 1.50 MTPA)

Production per day : 1500000/300 = 5000 TPD

(1) Primary Breaker

(1) Primary Breaker

Nos Bucket Capacity in TPH Make 04 150 TPH Atlas Copco

Proposed production per day : 5000 t

Number of shifts = 2

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 33

M/s Tamilnadu Cements Corporation Ltd.

Effective working hours = 6

Output per hour = 150 TPH

Output per machine per shift = 900 TPD

No of Machines required = 1

Considering 80% as availability 1 rock breakers are sufficient to handle the production.

However one more rock breaker will be kept as standby.

(2) Loading equipment (Production and development)

Type Nos. Bucket capacity in Make H.P Cu.m Excavator 04 1.9 Tata 198 Hitachi Excavating Parametres:

C = Bucket Capacity = 1.90 m3

F = Bucket fill factor = 0.85

S = Swell Factor (at 25% swell) = 0.8 t = Time cycle per pass at 900 swing = 20 sec e = Overall efficiency for three working shift = 0.80

T = Seconds per hour = 3600 n = Number of working shifts/day = One h = hours per shift = 8

W = Working days in a year = 300

A = Availability of machine = 0.35

U = Utilization factor = 0.80 b) Rate of Production

Output / Shovel/ hour = (C * F * S * T)/ (t) 1.5 * 0.85 * 0.80 * 3600 / 20

= 183.6 m3 say 184 m3

Output/ Shovel/ Year = 184*h*n*w*e*A*U

= 184*8*1*300*0.80*0.85*0.80

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 34

M/s Tamilnadu Cements Corporation Ltd.

= 240230 or 480460 or 4.80 Lac Tones. c) Number of Excavators

Quantity of material to be handled per day : 7500 Tones

No.of working days : 300 days

Maximum handling of material required = 2250000 tones.

Number of excavator (Shovels) required = 4 no.

Four machine is just sufficient to handled both production and development. However one more machine will be kept as standby.

(3) Haulage and transport equipment

(a) Haulage within the mining lease-hold.

Type Nos. Bucket capacity in Make H.P Cu.m Tippers 33 20 T AMV/TATRA/MAN 112 The company has proposed to set up the mobile screening plant for the production of 500Tons per day.

Hauling units for Production:

Quantity to be handled – T/day : 7500T No.of Shifts per day : 2 Capacity of tipper : 20T Distance of handling : 28 kms (to and fro distance) Total quantity of ore handled by tipper / hr : 20 T Effective working hours : 6 Total quantity of ore handled by Tipper / shift : 150 T No.of Tippers required : 33 No.of spare tippers : 7 Total no of tippers : 40

List of Mining Machineries The Miscellaneous equipments like Explosive van, water tanker and jeeps are provided for effective workings.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 35

M/s Tamilnadu Cements Corporation Ltd.

S.No Name of Machinery Nos T/Hr Capacity Model H.P Mobile Screening 1 500 To be Installed Plant 1 Excavator 2 200 2.2 Tata Hitachi 200 Excavator 2 300 2 Rock break 2 150 TPH - Atlas Copco 3 Tippers ( Production) 24 480 20 T AMV / TATRA / MAN 4 Jeeps 1 - - Mahindra - 5 Water Sprinkler 1 - 4000 Its Tractor with tanker - mounted 3. MINE DRAINAGE a) Minimum and maximum depth of water table based on observations from nearby wells and water bodies .

Ground water is the main source in this area, apart from rain in the monsoon period. The water table is intersected 30 to 35 meters from the surface

b) Indicate maximum and minimum depth of Workings.

Minimum depth of mine working is 21 m and maximum depth 25m c) Quantity and quality of water likely to be encountered, the pumping arrangements and places where the mine water is finally proposed to be discharged .

The main source of ground water in the area is rainfall. The average rainfall per year in the area is 900mm. At the end of the plan period of excavated area, the water encountered in the mine shall be collected in a sump which shall be at a level lower then the actual mine floor and the collected water sump shall be utilized for spraying on the haul roads and for plantation. The resident water shall be pumped out in to a channel to the nearby pond. d) Describe regional and local drainage pattern. Also indicate annual rain fall, catchments area, and likely quantity of rain water to flow through the lease area, arrangement for arresting solid wash off etc.

Ground water is the main source in this area, apart from rain in the monsoon period. The water table is intersected 40 to 45 meters from the surface. The ground water will be collected in the sump for the deposition of solid particles. Once the suspended particles are deposited it will be pumped out for domestic purpose, dust suppression system, gardening and Afforestation purpose. The excess water only will be pumped out to the nalla /closer water bodies – pond after the deposition of solid particles. There are no toxic elements found in the sump water.

The water table is found at a depth of 30 metres in rainy season and at 35m in dry season. To cope up with storm water and seepage water, an energy efficient electrical pump of 20H.P capacity will be installed and the discharge will be let-out in the nallah/Pond.

Garland drains will be made all along the periphery of dumpsites to prevent the water carrying the

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 36

M/s Tamilnadu Cements Corporation Ltd. wash-offs from the dumps and topsoil yard entering into the mines. The water collected in the garland drains will flow towards a settling tank formed near by the dumpsite. The water will be allowed to settle the wash offs from the dumps in the settling tank and pure & clear water will be utilized for afforestation purposes and for wetting of haul roads to arrest the dust generation.

Average rainfall in this area during Northeast Monsoon is around 900 mm.

4.0 STACKING OF MINERAL REJECT /SUB GRADE MATERIAL AND DISPOSAL OF WASTE a) Indicate briefly the nature and quantity of top soil, overburden / waste and Mineral Reject to be disposed off. The mining lease area is covered by Red soil of 0.0 to o.50 Mtrs. thickness. The test results of soil samples collected from this area prove that the soil cover over is suitable for agriculture and for afforestation purpose. The chemical composition of top soil and waste rock as follows.

Nature and Quality of Top soil There will be no handling of Topsoil & overburden during the scheme period. The top soil of very meager quantity encountered will be temporarily stacked along the mining lease boundary and consumed parallely for the afforestation purposes. The waste generated during the mining operations is topsoil & waste rock sandstone. The nature of the waste is sandstone. The chemical composition of waste is as follows.

LOI SiO2 Al2O3 Fe2O3 CaO MgO 13.80 59.50 11.70 7.20 5.20 1.30

The Topsoil removed during the year 2000-01 to 2010-11 around 1.12 lakh Tons is dumped in the existing dumpyard given in the eastern side of the lease area. During the last scheme fperiod no top soil and waste has been generated due to the quality and technical constriants of the deposit.

GENERATION OF WASTE IN THIS SCHEME PERIOD

Topsoil Waste rock / (sandstone) YEAR (in Metric tons.) In Metric tons)

2018-19 750000

2019-20 750000

2020-21 750000

Total 2250000

.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 37

M/s Tamilnadu Cements Corporation Ltd.

The total quantity of about 2250000 tons of reject / waste will be generated during the proposed production of limestone in this modification period. This quantity will be stacked in the existing dump yard as well as in the proposed dump yard with in the mining lease area. The location of existing and proposed dump yards is shown in the plate No.3, 4 & 6. b) The proposed dumping ground within the lease area be proved for presence or absence of mineral and be outside the UPL unless simultaneous backfilling is proposed or purely temporary dumping for a short period is proposed in mineralized area with technical constraints & justification.

Dumping will be done in advancing method. During the last Eleven-year plan 1.12 lakh tons of Top soil / waste rock has been removed and has been stacked in the existing dump in non mineral bearing area earmarked in the lease hold area and top soil has been utilized for stacking in the safety barrier zone all along the mining lease boundary for Afforestation purpose. The total quantity of about 2250000 tons of waste will be generated during the proposed production of limestone in this modification to the approved mining plan period. This quantity will be stacked in the existing dump yard as well as in the proposed dump yard with in the mining lease area. The location of existing and proposed dump yards is shown in the plate No.3 & 5 to 9.

c) Attach a note indicating the manner of disposal of waste, configuration and sequence of year wise build up of dumps along with the proposals for protective measures.

Dumping will be done in advancing method. During the last Eleven-year plan 1.12 lakh tons of Top soil / waste rock has been removed and has been stacked in the existing dump in non mineral bearing area earmarked in the lease hold area and top soil has been utilized for stacking in the safety barrier zone all along the mining lease boundary for Afforestation purpose. Location of Dump:

The overburden and the interstitial rejects are disposed by dumping them in the dump yards. The reject dump yards are located in the barren, non-mineral bearing areas in the mining lease area. The dump yards have been planned and formed in such a manner so as to facilitate safe and convenient dumping operations as per the guidelines give by IBM.

The angle of repose of the dump yard is 450. The proposed dumps are located within the distance of about 100 to 200 mts from the respective working mines. The proposed dumps are shown in the year

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 38

M/s Tamilnadu Cements Corporation Ltd. wise production and development plan (Plate No. 6A to 6C).

Maximum Spread and Height of Dumps:

The total quantity of Top soil / waste rock of about 1.12 Lakh Ton ( 75000 M3) generated during the last 11 years period and it was used concurrently for the afforestation purpose and the remaining quantity is stacked temporarily in the dump yard and Safety Zone.

Existing top soil / waste rock Dump Configuration along the periphery.

Dump Length (m) Width (m) Height (m) Waste Dump-1 100 60 18 Waste Dump-1 80 40 12

Proposed Top soil and waste dump configurations are shown in the year wise and developmental plans and sections in plate nos. 6A to 6C.

Stabilization and vegetation of dumps During the previous years of operation, the quantity of topsoil / waste rock dumped is meager and with minimum height of 1 metre to 1.5 metre there will not be possibility for slope instability. Hence the question of vegetation of dumps does not arise. Moreover, the dumped topsoil during mining operation will be removed and used for afforestation purposes.

Measures to control erosion / sedimentation There is no any major nallahs nearby the workings. So there will not be any problem regarding erosion. Moreover there is no major dumps, which may be exposed to erosion, and hence no sedimentation also. If at all the water course filled with sediments, it will be cleared every year after monsoon. Only the surface wafer, which is a source of erosion, is diverted by forming the bunds.

5.0 USE OF MINERAL AND MINERAL REJECT The following are to be furnished in the interest of mineral conservation. a) Describe briefly the requirement of end-use industry specifically in terms of physical and chemical composition.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 39

M/s Tamilnadu Cements Corporation Ltd.

The entire mineral mined will be used for the manufacture of different types of cements in the our own captive cement plant located at Ariyalur, and District along with limestone received from other leases. The limestone mined from all of captive limestone mines will be utilized for the cement manufacturing only. Raw mix parameters required to be maintained for the manufacture of cement is as follows, The variation in the chemical behavior of this limestone is summarized below.

Minerals Sio2 (%) Al2O3 (%) Fe2O3 (%) CaO (%)

Limestone 8.0 - 13.0 2.70 -4.50 1.80 -3.50 42.0 -47.0

Grade control:

As per the norms prescribed by NCBM (National council for Cement and Building Materials) the broad chemical specifications of cement grade ROM limestone are as follows:

Basically the qualities of raw mix parameters are controlled on the basis of the LSF, SM & AM. Depending upon the quality of coal used in the plant the quality of the ROM will vary in terms of LSF between 90 to 100 The quality of limestone from various leases in varies in composition because of inherent geological characteristics. Based on the available average analysis of limestone from different leases the M/s. Tamilnadu cement Corporation Limited has to mine the limestone from this Mine lease area in the above rate to meet out the required raw mix parameters, Plant capacity of the Ariyalur Works. : 1.5 million tons / annum

Requirement of Limestone : 2.5 Million tons /annum

Limestone from G.O.624 : 1.5 million tons / annum

Balance quantity of limestone will meet from other limestone mines.

Raw Mix Design:

% of Name of the mine Sio Fe O CaO MgO Contribution 2 2 3 G.O.No.344 25 9.4 4.0 46.3 0.6

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 40

M/s Tamilnadu Cements Corporation Ltd.

G.O.No.456 41 6.5 3.6 48.0 0.5 G.O.No.469 15 16.4 4.6 40.3 1.0 G.O.No.624 15 11.80 0.75 47.5 1.50 Clay (Additive) 04 59.5 7.0 5.0 1.5

b) Give brief requirement of intermediate industries involved in up gradation of mineral before its end-use. The entire limestone is used for own cement manufacturing purpose and the end product is cement c) Give detail requirements for other industries, captive consumption, export, associated industrial use etc.

The mined out limestone will be exclusively for captive use in the company’s cement plant. d) Indicate precise physical and chemical specification stipulated by buyers .

The mineral limestone to be raised from this mine shall be solely for captive use for the manufacture of cement. The limestone is not for sale nor shall it be exported e) Give details of processes adopted to upgrade the ROM to suit the user requirements.

The limestone is of cement grade and no sub-grade mineral is encountered. Hence, the company will consume it in it’s own cement plant.

6.0 PROCESSING OF ROM AND MINERAL REJECT a) If processing / beneficiation of the ROM or Mineral Reject is planned to be conducted, briefly describe nature of processing / beneficiation. This may indicate size and grade of feed material and concentrate (finished marketable product), recovery etc.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 41

M/s Tamilnadu Cements Corporation Ltd.

No processing or beneficiation of the ore or mineral mined is planned to be conducted on site or adjacent to the extraction areas. The mined material shall be loaded and transported to the crusher located at the plant. Apart from crushing no processing or beneficiation of the mineral is involved. b) Give a material balance chart with a flow sheet or schematic diagram of the processing procedure indicating feed, product, recovery, and its grade at each stage of processing.

No processing or beneficiation of the ore c) Explain the disposal method for tailings or reject from the processing plant.

No processing or beneficiation of the mineral is involved. d) Quantity and quality of tailings /reject proposed to be disposed, size and capacity of tailing pond, toxic effect of such tailings, if any, with process adopted to neutralize any such effect before their disposal and dealing of excess water from the tailings dam.

No processing or beneficiation of the mineral is involved. e) Specify quantity and type of chemicals if any to be used in the processing plant.

No processing / beneficiation is proposed to be conducted, therefore, no chemical(s) shall be used f) Specify quantity and type of chemicals to be stored on site / plant.

No chemicals shall be stored at site / plant g) Indicate quantity (cum per day) of water required for mining and processing and sources of supply of water, disposal of water and extent of recycling Water balance chart may be given.

No water shall be required for processing. Water shall be required in mining for dust suppression at faces and on the haul roads, cleaning and washing of HEME and plantation. Apart from the above water shall also be required for drinking and cleaning purposes. The estimated quantum of water requirement shall be to the tune of 40 m3/day. Ground water pumped out through tube wells and as the mine develops the water accumulated in the dump shall be utilized to meet the above requirement.

No waste water is likely to be generated from the mines. Only water used under high pressure for cleaning of HEME in the workshop can be guided and passed into the green belt. The water used for spraying the mine face or haul road shall either absorbed by the ground or get evaporated. Thus no recycling of water in the mines is foreseen.

7.0 OTHER a) Site services:-

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 42

M/s Tamilnadu Cements Corporation Ltd.

The site services include (a) mines office, (b)rest shelter,(c) first aid center, (d)store room, water tank, public convenience, water-man-shed Road – for adjacent mines and factory Drinking water- Bore wells are dug to cater the need of the drinking water ,Telephone line etc.

All the above structures is of semi-permanent / temporary in nature. b) Employment potential:

Employment potential of Anandavadi Mines

The anticipated employment, likely to be generated, is given in the table below. It includes managerial & supervisory staff directly employed by the company and skilled, semi skilled workers through contractual.

Manpower calculation for Anandavadi Limestone Mines No. of Persons Sl.No. Operations required per day 1 Mines Manager 1 Asst.Mines Manager cum Mining 2 2 Engineer 3 Geologist 1 4 Mech.Engineer 1 5 Mines Foreman 2 Sub-total 7 9 H.E.O 8

10 Drivers 18

11 Mechanic 2

12 Helpers, Mazdoors 3

13 Clerk 1 14 Un Skilled 2 Sub-total 34 Grand total 41

Therefore, total strength of workforce in the mine is = 41 (Direct-7& Indirect-34)

Additional Requirement:

Transportation of Limestone. The following additional contractual man power required for handling of limestone apart from above departmental manpower. . Tarus Drivers : 35 Nos (Skilled) Spotters & Helpers : 02 Nos (UN Skilled)

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 43

M/s Tamilnadu Cements Corporation Ltd.

ORGANISATION CHART FOR MINING DEPARTMENT

Managing Director

General Manager- Tech

Deputy General Manager – Tech/Unit Head

Manager (Mines)

Dy. Manager (Mines)

Asst. Manager Asst. Manager Sr. Asst. Manager Mines Mines Mines / Asst. Manager

Sr.Foreman (Mines) Sr.Foreman (Mines) Asst. Manager Surveyor Geologist

Geologist

8.0 PROGRESSIVE MINE CLOSURE PLAN UNDER RULE 23 OF MCDR’2017

8.1 Environment Base line information: Attach a note on the status of baseline

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 44

M/s Tamilnadu Cements Corporation Ltd.

Information with regard to the following.

Hence environmental impact due to limestone production up to 15.0 lakh tons / annum during the forthcoming years, M/S Tamilnadu Cement Corporation Ltd has engaged an environmental consultant for seasonal monitoring. The company has appointed the environmental consultant for preparing the EIA report for the enhanced quantity of 15.0 lakhs tons per annum of limestone. The .copy of work order issued to environmental consultant for preparing EIA / MOEF report is enclosed as Annexure-.14.

Existing land use pattern indicating the area already degraded due to quarrying, dumping processing plant, workshop, township etc., in a tabular form.

(i) Land-use pattern:

Present Land use pattern.

As on date No Details (in Ha.)

1 Area under mining 3.045 2 Storage of topsoil 0.500 3 Overburden/dump 1.000 4 Mineral storage 0.000 5 Infrastructure 0.150

6 Road 0.200 7 Railways 0.000 8 Green belt 25.000 9 Tailing pond 0.000

10 Effluent treatment plant 0.000 11 Mineral separation plant 0.000 12 Township 0.000 13 Unused virgin land 80.790 Grand Total 110.685

(ii) Water regime

The Nallah is passing across the lease area and flowing from NNE to SW of the lease area. It drains the area and joins the local water body in the south and western portion of the ML area. The Nallah is not perennial. It is dry during the major part of the year but is subject to occasional flash floods.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 45

M/s Tamilnadu Cements Corporation Ltd.

The ground water table is about 30 to 35 metres below the ground during the summer and it raises during rainy season.

(iii) Flora & Fauna:

Flora: The area adjacent to the mining lease is occupied by vegetation and other species. In the buffer-zone area of five kilometers, we find neem, babul etc., on bunds. Natural vegetation like grasses and wild shrubs grow during the monsoon, which is useful for grazing and in the summer, they dry out. Density of flora will be around 100 trees / hectare.

Fauna: The fauna that is obtained within the buffer zone are common varieties like foxes, jackals, mongoose and rats etc. In the amphibian and reptile category monitor lizard, cobra, viper, krait, chameleons are found. The insects are honey bee, wasp, beetle, termites, bugs, mosquitoes, scorpion, red ants etc.

The fauna found in the area are of common variety and thus no endangered species are found in the study area.

Base line data generation for air, noise level, ground vibration will be discussed in detail after the completion of one season monitoring. Presently the various environmental parameters are discussed based on the available data.

(iv) Quality of air:

Generally the dust level in the air is kept within the limit. The maximum concentration of air pollutants at different- stations during the study indicates that the highest 24 hour concentration of S P.M. was 260.6mg/m3 at TAI Station (Anandavadi village) and well within the CPCB limits .

3 The maximum 24 hour concentration of SO2 was 7.6 mg/m at station TA4 (Sendurai) and is well within the prescribed limits of CPCB (80mg/m3).

3 Similarly the maximum 24 hour concentration of NOX was 16.8 mg/m at station TA2 (Maruvathur) and is well within the prescribed CPCB limits (120 mg/m3).

Hence there will not be any bad impact on Air quality by mining, to the entire life of the mine.

In case of source samples, the SPM level recorded has been a maximum of 1659.6.50 micrograms /m3 near haulage road (source sample) requiring suitable management measures. The CO level in the ambient air samples was found to be below detecting level.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 46

M/s Tamilnadu Cements Corporation Ltd.

A summary of ambient quality monitoring results for 24 hours average concentration are given below:

Sl. Sampling station TSPM PM10 So2 NOx HC CO No µg/m3 µg/m3 µg/m3 µg/m3 ppm Ppm A1 Mining lease area-1 132.9 38.8 8.1 11.6 <1 <1 A2 Mining lease area-2 129.6 34.9 6.9 10.0 <1 <1 A3 Near Pit-3 132.9 38.5 7.9 11.1 <1 <1 A4 Venkataramanapuram 90.3 24.8 5.9 8.6 <1 <1 A5 Ottakoil 91.8 23.3 5.9 7.0 <1 <1 A6 Kallankurichi 90.4 25.8 5.9 7.9 <1 <1 A7 Kadugur 88.9 23.4 5.8 8.0 <1 <1 A8 Kovilankudikadu 91.3 25.8 5.8 8.1 <1 <1 A9 Chinnanagalur 105.0 26.6 6.0 8.2 <1 <1 A10 Reddipalayam 96.3 25.6 6.0 7.8 <1 <1

(v) Noise level:

Noise level is kept under check. Adequate measures will be taken up to control the noise level and also to provide appliances to the operators to avoid noise pollution if any.

The maximum and average of this noise levels in the 0 - 3 KM zone are 90 dB(A) and 74 dB(A) respectively. Whereas in 3-8 KM zone the same have been reported to be 71 dB(A) and 52 dB(A) respectively. In the 8-10 KM zone the maximum noise level recorded is 68 dB(A) and the average is 51 dB(A).

Hence there will not be any damage risk for hearing loss, by the mining activities, upto the mine life period.

Location of the Noise Level survey.

Sl. Sampling station Day Leq Night Leq No dB(A) dB(A) A1 Mining lease area-1 49.8 41.5 A2 Mining lease area-2 48.0 44.6 A3 Near Pit-3 50.3 45.8 A4 Venkataramanapuram 49.5 44.3 A5 Ottakoil 50.1 45.0 A6 Kallankurichi 48.7 43.5 A7 Kadugur 50.2 41.9 A8 Kovilankudikadu 48.0 41.0 A9 Chinnanagalur 48.3 42.3 A10 Reddipalayam 47.6 40.6

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 47

M/s Tamilnadu Cements Corporation Ltd.

To reduce the noise level efforts will be made by proper maintenance schedule, placement of compressors away from the workers. However, in addition to this, earmuffs are also being provided to the workers to prevent them from the noisy environment.

(vi)Ground vibrations:

Three number of blasts have been conducted at source area from close distances and found that the peak particle velocities were found to be less than 3mm / sec. The readings are taken from the blast site at different distance in the three blasts. During the first blast, around 600 kgs of explosives were blasted with a charge per delay of 202 kgs, the PPV value was measured at a distance of 500m from the blasting site, which showed a value of 1.5 mm/sec. During the second and third blast, the ppv values were measured at a distance of 150m and 75m respectively, in which we recorded a PPV value of 1.5 and 2.9 mm/sec.

Ground vibrations were measured near the mine site at different directions at the time of blasting and readings were found to be very less.All the mining area is isolated, and no residential structures are nearby. Due to ground vibrations while blasting, nearby dwellings will not be affected because of very low particle velocity.

Protective measures for ground vibrations / airblast

Ground vibration is an important consideration, so that public should not be affected. The following measures are taken to minimize ground vibrations and air blast by blasting.

1. A delay interval of 25 milliseconds, between holes is maintained using delay detonators. 2. Individual delays for each hole is used with card relays.

3. We will minimize the use of detonating fuse within the hole and other portions will be covered with drill cuttings and there will not be air blast.

4. Peak particle velocity will be kept very low, by using non-el-system as a special case.

5. For larger blasts, sequential timer will be used in the blasting operations to avoid noise and vibration.

6. Proper spacing and burden is maintained according to the bench heights to control blasting with low particle velocity and low noise.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 48

M/s Tamilnadu Cements Corporation Ltd.

7. Adequate care is taken to minimize the ground vibration by proper selection and usage of explosive depending upon the strata to be blasted.

However, displacement due to blasting was measured using a vibration meter at a distance of 500 m from the mine and the displacement noticed was only 0.2 micron which is very minimal which will not cause any damage.

Monitoring Locations and Methodology

Water samples from surface water source and ground water sources were collected from identified locations as per details given in following table in sterilized plastic cans to assess the existing water quality of the study area twice during the study period. The samples were analyzed for physical, chemical and bacteriological parameters as per the bureau of India Standards IS:10500 specifications, However, additional parameters like chemical and Bio chemical Oxygen Demand, Total suspended solids, Oil & Grease, and Ferric and Ferrous ion were also analyzed. The samples were analyzed as per standard procedure / method given in IS : 3025 (different parts) and standard method for examination of water and waste water ED 20, published jointly by APHA,WWA and WPCF.

Detail of water sampling locations

S.I. Location Sample Arial Distance Direction Type and No. No. from mines From Mines Sources of (KM) water 1 Kallankurichi PW1 SW 4 Bore Well 2 Periyanagalur PW2 0 0 Mine Water 3 Kairullbad PW3 NE 4.7 Bore Well 4 Amenabad PW4 SE 1.75 Bore Well

Results and observations

The detailed physico- chemical characteristics of surface and ground water samples collected within the study area are presented in Annexure –8 and described hereunder.

Ground Water

pH values varied between 7.12 to 8.10 while turbidity ranged from 2.3 to 3.5 NTU. Dissolved solids varied between152.359 mg/l and 1995 701 mg/l and total hardness varied from 160.0 to 295.7

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 49

M/s Tamilnadu Cements Corporation Ltd.

mg/l. Chloride values varied between 29.9 mg/l and 4956 mg/l. Calcium values varied between 54.5 mg/l and 75.2 mg/l and Magnesium values varied between 27.4 mg/l and 32.6 mg/l. Sulphate values varied from 28.7 to 480 mg/l and Nitrate values varied from 0.4 to 1.7 mg/l. Cyanide has been observed as nil while Arsenic, Cadmium, Lead, Copper, Chromium, Selenium and Zinc have been observed below detection limit.

Surface Water

pH values varied between 7.64 to 8.0 while turbidity ranged from 8.8 to 9.5 NTU. Dissolved Solids varied between 338 mg/l and 542 mg/l while total suspended solids varied from 31.7 to 36.7. Total hardness varied from 235.1 to 295.3 mg/l. Chloride values varied between 18.2 mg/l to 25.1 mg/l. Calcium values varied between 71.5 mg/l to 77.2 mg/l and Magnesium values varied between 32.6mg/l and 33.6 mg/l. Sulphate values varied from 27.6 to34.8 mg/l and Nitrate values varied from 0.4 to 1.7 mg/l and Nitrate values varied from 1.1 to 1.3 mg/l. Cyanide has been observed as nil while Arsenic, Cadmium, Lead, Copper, Chromium, Selenium and Zinc have been observed below detection limit. MPN Coliform (per 100 ml) values have been observed within limit.

From the above results, the prescribed limit of IS 10500, it is found that ground water of the study area is fit for drinking purposes as alternate source.

There would not be any toxic effluent from mine hence there in no need for any treatment of water from mine.

Control measures to be adopted are

The peripheral bunds will help that soils is not carried away by storm water. Stabilization of bund slope to prevent erosion and this shall be done by providing dense plantation along the bund slopes.

During dewatering operations the pumped out water will be let out in the nearby natural courses.

(viii) Climatic conditions

A meteorological station was set up in all three season to collect micro meteorological data for the area.

The average annual rain fall in this area is about 900 mm. The area receives maximum rainfall during N.E. Monsoon (i.e.) between October to December and precipitation also occur during S.W. monsoon between July and September.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 50

M/s Tamilnadu Cements Corporation Ltd.

The rains are not generally heavy enough to hamper mining operations for more than one or two days at a time. Ho disastrous floods have been recorded in this area. The maximum temperature in summer months is 40° C. In the winter months (December to February) the minimum ternperature would be about 300 C. Cyclone and storms are rare in this area. The main wind directions are as follows. Winds are mainly from directions between North and North East from November to February. In March winds are mostly from directions North East and South East, to the morning and afternoon they are either Northerly to North Easterly or Southerly to South Easterly. During April to October winds blow mostly from directions between South and South Western in the morning, in the afternoons they are between South West and South East.

The area is well outside the known earthquake belt of the country and no earthquakes or sympathetic shocks have been reported since historical times.

(ix) Human settlements:

The mining lease area is surrounded by few small villages. The main occupation of the people in this part is agriculture. The lands in these areas are very fertile. Besides agriculture there are no major industries. .Rehabilitation Within the Mine lease area, there is no a village or human settlement. Hence there is no question of any evacuation and resettlement of people elsewhere. . Socio Economic Studies It is well known fact, that industrialization will affect directly or indirectly the life styles, social structure and economics of the persons who are living in the region. A study of the existing baseline date on these aspects will help to force the impact of mining in future. For this study the area has been divided into 2 zones namely core and buffer, while the 5KMs belt around the mine lease area constituted the core zone the area up to 10 Kms distance from the periphery of the lease has been considered as buffer zone. Baseline data and socioeconomic environment in the core and buffer zone were combined from the senses. The data covers various constituents such as demo graphs, literacy, employment, land classification, availability of educational, medical and communication facilities etc.

DEMOGRAPHIC PROFILE Village Population Distance Direction Sendurai 4637 1.4 Km SW Maruvattur 2761 3.1 Km SE Periakurichi 3253 3.9 Km NE

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 51

M/s Tamilnadu Cements Corporation Ltd.

Nakkambadi 2679 2.6 Km NW Vanjinapuram 2798 3.0 Km NW Public Buildings, Places and Monuments: There are no historical places of interest monuments, pilgrimage centers around the Mining lease area.

Sanctuary is located in the vicinity of leasehold.

No Sanctuary is located in the vicinity of leasehold.

8.2 Impact Assessment: Attach an Environmental Impact Assessment Statement describing the impact of mining and beneficiation on environment on the following:

ENVIRONMENT IMPACT ASSESSMENT STATEMENT

The environmental impact due to the enhancement of limestone production up to 15.0 lakhs tons per Annum during the proposed modification period has been taken in to considerations while preparing impact assessment statement.

Due to the increase in the cement production from 5 lakhs to 15 lakhs tons, the company has engaged the EIA consultant for the enhanced proposed production of limestone from this G.O. 624 will be 15.0 lakhs tons per annum. The address of the EIA consultant who prepares the EIA report for the MOEF clearance is as follows, M/s Mantec Consultants Pvt. Ltd, D-35 & 36, sector-6, Noida, Pin- 201 301 India. Tel: +91 1412751801/802/803, Fax: 2751806 E-Mail: [email protected] url: www.cegindia.com

The copy of work order issued to EIA consultant is enclosed as annexure no.15, the same after completion will be submitted to IBM.

ENVIRONMENT IMPACT ASSESSMENT STATEMENT:

i) LAND ENVIRONMENT:

Land use pattern after five years

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 52

M/s Tamilnadu Cements Corporation Ltd.

As on At end of At the end date (in scheme of life of the No Details Ha.) period (in mines (in Ha.) Ha.) 1 Area under mining 3.045 7.045 60.685 2 Storage of topsoil 0.500 0.500 0.000

3 Overburden/dump 1.000 2.900 0.000 4 Mineral storage 0.000 0.000 0.000 5 Infrastructure 0.150 0.200 1.000 6 Road 0.200 0.500 0.500 7 Railways 0.000 0.000 0.000 8 Green belt 25.000 27.500 48.500 9 Tailing pond 0.000 0.000 0.000 10 Effluent treatment plant 0.000 0.000 0.000 11 Mineral separation plant 0.000 0.000 0.000 12 Township 0.000 0.000 0.000 13 Unused Virgin lands 80.790 72.040 0.000 Grand Total 110.685 106.685 110.685 a) Land and Land Subsidence:

Any mining operation is likely to alter the already existing topography. Scheduled reclamation of the mined out areas will eventually represent a better landscape with even topography, which would be amenable for farming etc. b) Aesthetic Environment and Tourist Spots (if any)

The Mining lease area neither endowed with environmentally aesthetic attributes not is an attractive place for tourists. c) Soil and Land use Pattern

Opencast mechanized mining operations in this area would not cause discernible changes in the soil characteristics since mining operations will not result in any kind of toxic effluents nor would there be any solid waste generation.

The existing land use pattern is mainly cultivation for rotational/seasonal crop harvest. In the M.L. area, most of the area is agricultural land and the remaining part comprises of grazing lands and scrub jungle. Most of the plants are armed with spines and hooks. The prevailing land use pattern in the post-mining period would not altogether get altered. Novel and extensive schemes of afforestation will be implemented so as to minimize the effect of current land use. d) Agriculture

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 53

M/s Tamilnadu Cements Corporation Ltd.

The proposed mining methods will not cause any harm to the agricultural field in the surroundings.

With the commencement of mining operations employment (both direct and indirect) opportunities will inherently force a change in the occupational structure partially. Consequently with increased economic status, modernized agricultural practices would be adopted which will result in not only better crop yield, but also reduce the pressure on particular operation.

Additionally, the wastelands and fallow lands upon mining and suitable reclamation will result in beneficial rehabilitation of the derelict lands. Emphasis will be on restoration of mined out lands to agricultural practices. e) Forest

The Mining lease area does not include any forest area. f) Flora and Fauna

The area under mining lease is not a habitat for wild life or bird sanctuary etc. Therefore mining would not cause any effect on existing flora and fauna. There is no rare/endangered species of flora in the area. Mining operations will not involve any felling of trees etc. as most of the area selected for mine working is devoid of trees/plants etc. There is no wild life sanctuary in the vicinity of mining lease area. So no rare/endangered or wild species is likely to be affected by the mining project.

AIR:

A number of activities have an impact of ambient air quality of the area. These includes industries,

domestic fuel consumption, traffic emission etc. Major pollutants are SPM, Nox and So2. The main

source of air pollutant in SPM is mining activities. The generation of Nox and So2 results obtained are well within the limits prescribed by CPCB for areas meant for industrial use.

Air pollution impact analysis is of prime concern. Dust is a particulate contaminant suspended in the atmosphere. The upper size limit of dust particles is governed by gravitational effects. While the distinction between the respirable and non respirable dust is scientifically valid it is clear that both sizes can impair lung functions when inhaled over a time.

Deployment of diesel powered equipment for mining may produce emissions that are known to be hazardous, viz unburnt hydrocarbons, oxides of nitrogen, particulates, phynols, aldehydes, oxides

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 54

M/s Tamilnadu Cements Corporation Ltd.

of sulphur, trace elements, smoke and hydrocarbons. These pollutants are known to cause respiratory ailments.

Use of protective equipments to reduce the exposure of personnel to excessive concentrations of dust, dust suppressive techniques along haul tracks and drilling sites are practiced to minimize negative impacts.

Ambient air quality Monitoring was carried out for summer season (April, May and June). The parameters selected for analyzing ambient air quality status were Respirable Particulate Matter

(RPM), Suspended Particulate Matter (SPM) Oxides of Nitrogen (Nox), Sulphur diaoxide (SO2). A summary of ambient quality monitoring results for 24 hours average concentration are given below:

Locations Values SPM RPM SO2 NOx µg/m3 µg/m3 µg/m3 µg/m3 Anandavadi Min 67.60 33.740 7.00 6.00 lease site Max 74.20 41.30 12.00 10.00 Mean 71.57 38.98 9.63 8.13

Control Measures for Air Quality / Dust Suppression The main activities for air pollution are drilling, Blasting, loading, unloading, transportation and heavy duty mobile equipments. Suppression measures like water spraying along haul road, roadside plantation to provide canopy of foliage and regular use of water ejecting system to dampen and control the dust during the course of drilling will be undertaken.

The proposed measures to control air quality within the limits are detailed below,

Mobile equipments Dust emanated due to the movement of equipments is generally suppressed by the following ways:

Surfacing of internal roads.

Dust suppression by water sprays Dust generated in the mines will be suppressed by sprinkling water on haul roads with the help of mobile water tanker with sprinkling arrangement. As there is not much of water seepage and accumulation in the pits, permanent pipe line connection for spraying water on haul road for dust suppression cannot be carried out immediately. However your advice & suggestion will be

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 55

M/s Tamilnadu Cements Corporation Ltd.

considered in future.

Rows of trees would be planted ii) WATER ENVIRONMENT:

a) Surface Water:

The Nallah is passing across the lease area and flowing from NNE to SW of the lease area. It drains the area and joins the local water body in the south and western portion of the ML area. The Nallah is not perennial. It is dry during the major part of the year but is subject to occasional flash floods.

The ground water table is about 15 to 20 metres below the ground during the summer and it raises during rainy season.

b) Ground Water

Ground water is the main source in this area, apart from rain in the monsoon period. The water table is intersected 15 to 20 meters the surface. The ground water will be collected in the sump for the deposition of solid particles. Once the suspended particles are deposited it will be pumped out for domestic purpose, dust suppression system, gardening and Afforestation purpose. The excess water only will be pumped out to the nalla /closer water bodies – pond after the deposition of solid particles. There are no toxic elements found in the sump water.

The water table is found at a depth of 15metres in rainy season and at 20m in dry season. To cope up with storm water and seepage water, an energy efficient electrical pump of 20H.P capacity will be installed and the discharge will be let-out in the nallah/Pond. Garland drains will be made all along the periphery of dumpsites to prevent the water carrying the wash-offs from the dumps and topsoil yard entering into the mines. The water collected in the garland drains will flow towards a settling tank formed near by the dumpsite. The water will be allowed to settle the wash offs from the dumps in the settling tank and pure & clear water will be utilized for afforestation purposes and for wetting of haul roads to arrest the dust generation. (v) Noise level: Noise level is kept under check. Adequate measures will be taken up to control the noise level and also to provide appliances to the operators to avoid noise pollution if any.

The maximum and average of this noise levels in the 0 - 3 KM zone are 90 dB(A) and 74 dB(A) respectively. Whereas in 3-8 KM zone the same have been reported to be 71 dB(A) and 52 dB(A)

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 56

M/s Tamilnadu Cements Corporation Ltd.

respectively. In the 8-10 KM zone the maximum noise level recorded is 68 dB(A) and the average is 51 dB(A).

Hence there will not be any damage risk for hearing loss, by the mining activities, upto the mine life period.

Location of the Noise Level survey.

Sl. Sampling station Period Day Leq Night Leq No dB(A) dB(A) A1 Mining lease area-1 Nov-10 49.8 41.5 A2 Mining lease area-2 Nov-10 48.0 44.6 A3 Near Pit-3 Nov-10 50.3 45.8 A4 Venkataramanapuram Nov-10 49.5 44.3 A5 Ottakoil Nov-10 50.1 45.0 A6 Kallankurichi Nov-10 48.7 43.5 A7 Kadugur Nov-10 50.2 41.9 A8 Kovilankudikadu Nov-10 48.0 41.0 A9 Chinnanagalur Nov-10 48.3 42.3 A10 Reddipalayam Nov-10 47.6 40.6

To reduce the noise level efforts will be made by proper maintenance schedule, placement of compressors away from the workers. However, in addition to this, earmuffs are also being provided to the workers to prevent them from the noisy environment.

(vi)Ground vibrations:

Three number of blasts have been conducted at source area from close distances and found that the peak particle velocities were found to be less than 3mm / sec. The readings are taken from the blast site at different distance in the three blasts. During the first blast, around 600 kgs of explosives were blasted with a charge per delay of 202 kgs, the PPV value was measured at a distance of 500m from the blasting site, which showed a value of 1.5 mm/sec. During the second and third blast, the ppv values were measured at a distance of 150m and 75m respectively, in which we recorded a PPV value of 1.5 and 2.9 mm/sec.

As such there is no need to go for 30 readings to be taken, as the values in either in the village or in the close vicinity do not warrant such an exercise.

Monitoring Locations and Methodology

Water samples from surface water source and ground water sources were collected from identified locations as per details given in following table in sterilized plastic cans to assess the existing

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 57

M/s Tamilnadu Cements Corporation Ltd.

water quality of the study area twice during the study period. The samples were analyzed for physical, chemical and bacteriological parameters as per the bureau of India Standards IS:10500 specifications, However, additional parameters like chemical and Bio chemical Oxygen Demand, Total suspended solids, Oil & Grease, and Ferric and Ferrous ion were also analyzed. The samples were analyzed as per standard procedure / method given in IS : 3025 (different parts) and standard method for examination of water and waste water ED 20, published jointly by APHA,WWA and WPCF.

Acid mine drainage, if any

No acid mine drainage

Socio-economics

Educational Facilities:- Tamil medium state board higher secondary school and an English medium matriculation school are available at Ariyalur to cater the need of the education to employee’s children and the other villager’s children living in and around the factory and mines. Scholarship facilities for employee’s children as well as to the school toppers are given for pursuing higher education. Hospital: The hospital is located at Ariyalur and at Kadugur in a well-constructed building. Medical treatments including supply of specialist care, medicines are given to the employees and other persons living in and around the mines and factory at free of cost E.C.G facility is also provided in the dispensary. Phone facilities will be arranged in the mines to contact the Doctors and the Hospital round the clock. Ambulance has also been provided which can be summoned immediately over phone. Staffs are provided in the dispensary round the clock to attend to the emergency cases. Health care facilities: Regularly health camps are organized at our dispensary to cater to the need of the persons living in and around the mines area and factory area at free of cost. Specialist from various health fields like eye, cardiac care, diabetes, ortho etc are called from Ariyalur, Trichy & Perambalur hospitals to give specialized health care to the people. For the welfare of the children of the employees and villagers living around mines and factory, vaccination camps are regularly organized at our dispensary. Drinking water facility: Bore wells are dug in the villages in and around the mines at our company’s cost to cater to the

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 58

M/s Tamilnadu Cements Corporation Ltd.

need of the villagers for drinking water. For the nearby villages, sintex water tanks are kept in prominent locations which are filled up daily with drinking water supplied through a water tanker from the factory. The lakes in and in around villages are deepened with our mine machineries regularly every year just before the onset of monsoon season in order to accumulate and store the rain water in the lakes for the use of villagers for their domestic purposes. Road & Bridges constructions: For the villages in around the mines and factory permanent roads laying works are taken from time to time by the company. Children’s park: A park for the children of employees residing in the colony will be provided with a good lawn and sliding board and other playing mutes. Quality of life: The standard of living of the villagers has drastically improved as most of them are employed in the factory or in the mines. Because of this they are able to provide good education to their children and improve their quality of life. Most of the employees who are presently employed in the mines and factory are the third generation in the family working for the factory and mines continuously. Indirect employment opportunities are created for the local people living in around the mines area motivating them by giving suitable contractual jobs like transportation of limestone from mines to factory, Afforestation work at mines etc. Community centre: Community center is constructed at our colony premises to organize marriage functions and other traditional rituals of our mine employee’s family and other villagers at a nominal rate. Temple renovation work: Company is taking utmost interest & contributing in renovating the existing temples in around the mines area and factory at company’s cost enabling the villagers to celebrate their temple functions every in a grand manner. The management grants donations to various temples for conducting scheduled annual poojas.

Rainwater harvesting: Recently our company has initiated the rain water harvesting practices inside our company and colony premises to store the rainwater and effectively use the same during the summer season. Occupational Health and Safety

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 59

M/s Tamilnadu Cements Corporation Ltd.

As regards occupational health and safety are concerned, the employed staff would be provided with adequate safety implements and also be periodically trained in the VT programmes to observe and use them. Strict vigil would be maintained as is our usual practice for observance of safety aspects in working atmosphere. Health of workers is of primary concern in our organization. Regular medical checkup for the workers will be conducted as per statutory requirements.

Public Buildings, Places and Monuments:

There are no historical places of interest monuments, pilgrimage centers around the Mining lease area.

Review of Environmental proposals and the status of compilation at the end of the plan period.

PROPOSALS FOR PROPOSALS AS PER POSITION AT THE END SL NEXT THREE YEARS APPROVED SCHEME OF SCHEME OF NO. ITEM MODIFICATION OF MINING MINING PERIOD PERIOD

1 2 3 4 5 Total quantity of top soil Since production was No generation of top soil 1. Top soil storage proposed to be handled not met that target. The is proposed. is 2.31 Lakh tons. top soil handled upto the Dumping Proposals 31st march 2011 is 1.25 were made in the Lakh tones. Topsoil is mineral bearing stored separately on the adjoining to the working designated place so far. pit. Store it separately There is no deviation for future use in from the proposal spreading afforestation areas No proposals for The mining is not yet The mine will not be 2. Land reclamation and reached the basement exhausted of limestone in reclamation and rehabilitation in the and the production the next five years so no rehabilitation approved scheme of achieved during the reclamation or ,as limestone would not period is very meager rehabilitation of full or part be exhausted. 2.60 Lakh tonnes. of the quarry is proposed.

Proposals were to store Topsoil, and waste rock 22.5 Lakh tones off 3. Waste dump topsoil & waste sandstone is being sandstone envisaged management sandstone separately stored at the designated during this period will be and places were places separately. No stacked separately at ear earmarked for the deviation from approved marked locations.. purpose. scheme of mining Afforestation In the approved mining Till date eucalyptus & It is proposed to plant 4. programme with scheme 3880 No of casurina is planted over about 4500 nos. of trees precautions for trees are proposed to 2.0 Ha at the rate of in five years at the rate of survival and cover an area of 4.15 1500 Trees / ha along 1500 trees per year along protection of Ha.. the water body the boundary and waste plantation boundary. dump yard. Area covered will around 02.50 Ha.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 60

M/s Tamilnadu Cements Corporation Ltd.

Periodical Periodical environmental Periodical environmental 5. Quality of air. environmental monitoring of air quality monitoring of air quality monitoring of air quality conducted as per conducted as per to be conducted. IBM/MoEF norms IBM/MoEF norms quarterly quarterly and the same to The latest environmental be continued monitoring reports is enclosed as annexure-2

Periodical Periodical environmental Periodical environmental 6. Quality of water. environmental monitoring of water monitoring of water monitoring of Water quality conducted as per quality conducted as per quality to be conducted. IBM/MoEF norms IBM/MoEF norms quarterly quarterly and the same to be continued Periodical Periodical environmental Periodical environmental 7. Noise level environmental monitoring of noise level monitoring of Noise level monitoring of noise conducted as per conducted as per level to be conducted. IBM/MoEF norms IBM/MoEF norms quarterly quarterly and the same to be continued Periodical Periodical environmental Periodical environmental 8. Ground environmental monitoring of Noise level monitoring of Noise level vibration. monitoring of Noise conducted as per conducted as per level to be conducted. IBM/MoEF norms IBM/MoEF norms quarterly quarterly and the same to be continued Treatment of There was no proposal Monitoring and study There will be no toxic 9. mine water to treat ground or was made and there will effluent that will be including surface water. be no toxic effluent that discharged from the mine surface and will be discharged from hence, no treatment of ground water. the mine hence, no ground and surface water treatment of ground and is proposed. surface water. Re-circulation of No proposal in the No re-circulation of Not applicable as no toxic 10. treated water. approved scheme of treated water done. This effluent is going to be mining for re-circulation was not applicable. produced or discharged of treated water as from the mine. there was no need to treat water in the mine.

Presently the company has registered the ONLINE application to TNPCB for the above quarterly Monitoring study of Air, Water, and Noise during the scheme period. TNPCB will do the monitoring study as per the date of registration and priority basis. After the completion of quarterly monitoring study the same will be submitted to IBM for reference. The copy of EMP report and TNPCB consent letter is enclosed as annexure no.14.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 61

M/s Tamilnadu Cements Corporation Ltd.

8.3 Progressive reclamation Plan:

In the preceding chapter, an attempt was made to assess the likely impact on the environment due to various mining activities. This chapter describes the scheme for environmental management, the proposed abatement measures to minimize the likely environmental degradation that may be caused due to the mining operations at proposed Mining Project.

Considering the scale and methodology of mining operations in the project area as discussed earlier, no significant environmental degradation is expected. The micro level eco system and socio economic setup of the villages is likely to improve. Environmental control measures and techniques are discussed below to mitigate any adverse effect owing to the mining activities.

8.3.1. Mined-Out Land:

The total excavated area shall be around 60.685 Ha at the end of mining operations. It is proposed to convert the mined out area as an artificial pond to store rainwater and as well as part of the area will be refilled and subsequently afforested. The area is arid and has a low about 900mm/yr. Therefore the water stored from rainfall could be used as reservoir in the locality helping the neighboring villagers. The reservoir will have an enough potential to store water. The water in the reservoir thus located shall improve bore well irrigation.

The undisturbed virgin lease area along the mining lease boundary shall be utilized for agricultural purposes by developing the area with guava, straw berry, fig fruit plants etc. This work shall be done after the cessation of mining operations.

Justification Artificial Pond to Store Rain Water: The sub-surface of the area is composed of hard rocky strata. So the rainwater is not directly and effectively absorbed into the ground. Since no major water resources / reservoirs / lakes / ponds etc, are present in the area, if we fully reclaim the mined out pits we would completely loose the entire rainwater instead of being harvested in the mined out pits thereby increasing the level of the water table in the area will get increased.

The undisturbed virgin lease area along the mining lease boundary shall be utilized for agricultural purposes by developing the area with guava, straw berry, fig fruit plants etc. This work shall be done after the cessation of mining operations.

Therefore, by proposing to utilize the mined out pits as water reservoirs, after entire mining operations gets completed, we would be able to serve the following purposes:

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 62

M/s Tamilnadu Cements Corporation Ltd.

1) Sustain the water resources for the drought prone area of local villages. 2) Increase the level of water table in the adjacent area. 3) To meet the drinking water requirement of local villagers. 4) To afforestate the non-mining leases areas (earmarked for afforestation) with the Stored water from these pits.

Therefore, considering the above facts, we propose not to reclaim the mined out pits after entire mining is completed instead we would utilize them as water reservoirs which would be the need of the prevailing hydrological atmosphere in the mining lease area.

Post Mining after cessation of mining activities

As on At end of At the end date (in scheme of life of No Details Ha.) period (in the mines Ha.) (in Ha.) 1 Area under mining 3.045 7.045 60.685 2 Storage of topsoil 0.500 0.500 0.000 3 Overburden/dump 1.000 2.900 0.000 4 Mineral storage 0.000 0.000 0.000

5 Infrastructure 0.150 0.200 1.000 6 Road 0.200 0.500 0.500 7 Railways 0.000 0.000 0.000 8 Green belt 25.000 27.500 48.500 9 Tailing pond 0.000 0.000 0.000 10 Effluent treatment plant 0.000 0.000 0.000 11 Mineral separation plant 0.000 0.000 0.000

12 Township 0.000 0.000 0.000 13 Unused Virgin lands 80.790 72.040 0.000 Grand Total 110.685 110.685 110.685

8.3.2 Topsoil Management:

During the three year modification period no topsoil will be generated and it will be in meager quantity will be stacked all along the safety barriers of the lease area, and it will be utilized for the afforestation purposes.separately in the 50M safety zone area along the odai. The average thickness of the top soil is varying in thickness 1 to 0.5M in the mining lease area for mining. The upper layer of top soil, which is oxidized and contains organic matter will be stripped and used for spreading over the slopes of the peripheral bund to facilitate revegetation and also for tree plantation over areas beyond the peripheral bund. Excess quantity of top soil remaining will be stacked separately in a dump yard for the above stated purpose. The slopes of the dumpsites

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 63

M/s Tamilnadu Cements Corporation Ltd.

will be terraced with grasses, legumes etc to arrest soil crossing to a great extent. The soil from this dump yard and shall be rehandle and spread over the backfilled areas, once backfilling of the mines out area commences.

During the modification period to plant about 1500 Nos. of saplings all along the boundary to cover an area of 2.50.0 Ha and the survival rate of plantation is only 80%.

Existing Afforestation details as follows:

Existing afforestation

The non mined areas of the lease are afforested by planting saplings of casurina and Eucalyptus. Afforestation is completed within the mining lease area. The existing afforestation within the lease area is as follows.

Area in No. of Name of Expected rate Location Hectares plants species of survival

Along the water course and in the non Eucalyptus and 25.00 15,000 80% mining area by Forest Casurina dept. and by TNPL

This afforestation work is done with the co-ordination of Forest Department. After the contract period is over the trees will be cut by the above department and again the non mining areas will become virgin.

Proposed Afforestation programme for three years modification period:

Area No. of Year Covered Survival Places of Species Saplings (Ha) rate plantation 2018-19 1500 0.833 80% Safety zone Eucalyptus & barrier Caurina 2019-20 1500 0.833 80% -Do- -Do- 2020-21 1500 0.834 80% -Do- -Do- Total 7500 2.50.0

Environmental Plan is enclosed. Refer Plate No. 7

8.3.3 Tailings Dam Management.

As such there is no beneficiation plant for processing of the mineral and hence there is no

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 64

M/s Tamilnadu Cements Corporation Ltd.

Disposal of waste/ tailing from the mine is envisaged. 8.3.4 Acid mine drainage, if any and its mitigative measures.

No acid mine drainage

8.3.5 Surface subsidence mitigation measures through backfilling of mine voids or by any other means and its monitoring mechanism.

The information on protective measures for reclamation and rehabilitation works year wise may be provided as per the following table.

SUMMARY OF YEARWISE PROPOSAL FOR ITEM NO. 8.3

Lime stone deposit was not exhausted and the quarry has not reached ultimate depth. So question does not arise for reclamation and rehabilitation.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 65

Scheme of Mining of Anandavadi Limestone Mines

YEARLY PROPOSAL FOR ITEM NO. 8.3 OF PMCP FOR THE III YEAR (2018-19) FOR ANANDAVADI LIMESTONE MINES OVER AN EXTENT OF 110.685 HA. Items Details Proposed Actual Remarks Area afforested (ha) Nil No of saplings planted Nil Dump Cumulative no of plants Nil management Cost including watch and care during the Nil

year Area available for rehabilitation (ha) Nil Afforestation done(ha) Nil Management No of saplings planted in the year Nil of worked out Cumulative no of plants Nil benches Any other method of rehabilitation (specify) Nil Cost including watch and care during the Nil year Void available for Backfilling (L x B x D) pit Nil Reclamation wise /stope wise and Rehabilitation Void filled by waste /tailings Nil by Afforestaion on the backfilled area Nil backfilling Rehabilitation by making water reservoir Nil Any other means (specify) Nil Rehabilitation Area available (ha) Nil of waste land Area rehabilitated Nil within lease Method of rehabilitation-By afforestation Nil Ambient Air Quality Water Quality Rs. Noise level 250,000/- Ground vibration Others 0.833 (1500 (specify) saplings) Green belt along mine periphery/Virgin area cost likely to (Ha) be incurred – Rs. 75000 Total Rs. 325000

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 67

Scheme of Mining of Anandavadi Limestone Mines

YEARLY PROPOSAL FOR ITEM NO. 8.3 OF PMCP FOR THE IV YEAR (2019-20) FOR ANANDAVADI LIMESTONE MINES OVER AN EXTENT OF 110.685 HA. Items Details Proposed Actual Remarks Area afforested (ha) Nil No of saplings planted Nil Dump Cumulative no of plants Nil management Cost including watch and care during the Nil

year Area available for rehabilitation (ha) Nil Afforestation done(ha) Nil Management No of saplings planted in the year Nil of worked out Cumulative no of plants Nil benches Any other method of rehabilitation (specify) Nil Cost including watch and care during the Nil year Void available for Backfilling (L x B x D) pit Nil Reclamation wise /stope wise and Rehabilitation Void filled by waste /tailings Nil by Afforestaion on the backfilled area Nil backfilling Rehabilitation by making water reservoir Nil Any other means (specify) Nil Rehabilitation Area available (ha) Nil of waste land Area rehabilitated Nil within lease Method of rehabilitation-By afforestation Nil Ambient Air Quality Water Quality Rs. Noise level 250,000/- Ground vibration Others 0.833 (1500 (specify) saplings) Green belt along mine periphery/Virgin area cost likely to (Ha) be incurred – Rs. 75000 Total Rs. 325000

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 68

Scheme of Mining of Anandavadi Limestone Mines

YEARLY PROPOSAL FOR ITEM NO. 8.3 OF PMCP FOR THE V YEAR(2020-21) FOR ANANDAVADI LIMESTONE MINES OVER AN EXTENT OF 110.685 HA. Items Details Proposed Actual Remarks Area afforested (ha) Nil No of saplings planted Nil Dump Cumulative no of plants Nil management Cost including watch and care during the Nil

year Area available for rehabilitation (ha) Nil Afforestation done(ha) Nil Management No of saplings planted in the year Nil of worked out Cumulative no of plants Nil benches Any other method of rehabilitation (specify) Nil Cost including watch and care during the Nil year Void available for Backfilling (L x B x D) pit Nil Reclamation wise /stope wise and Rehabilitation Void filled by waste /tailings Nil by Afforestaion on the backfilled area Nil backfilling Rehabilitation by making water reservoir Nil Any other means (specify) Nil Rehabilitation Area available (ha) Nil of waste land Area rehabilitated Nil within lease Method of rehabilitation-By afforestation Nil Ambient Air Quality Water Quality Rs. Noise level 250,000/- Ground vibration Others 0.834 (1500 (specify) saplings) Green belt along mine periphery/Virgin area cost likely to (Ha) be incurred – Rs. 75000 Total Rs. 325000

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 69

Scheme of Mining of Anandavadi Limestone Mines

8.4 Disaster Management and Risk Assessment:

The objective of onsite disaster management plan for the captive mine is to be a state of perceptual readiness through training, development to immediately control and arrest any emergency situation so as to avert a full fledged disaster and the consequence of human and property damage and in the event of a disaster still occurring, to manage the same so that the risk of the damage consequences to life and property is minimized

M/s Tamilnadu Cement Corporation Limited has formulated a disaster management plan for Emergency Preparedness & Responses.

The salient features are elaborated as below:

. Emergency response Organization . Communication System . Action on the site . Facilities available at site.

Emergency Response organization

Following officers of the mines will be responsible for co ordination in case of emergency situated in any section of the mine.

Person Name Contact No. Responsibility

Head of the department Mr.K.Senthil kumar 9943844086 Site Controller

Section In charge Mr.T. Santhakumar 9047872442 Accident Controller/ Communication officer Employee who gives the first Mr.K.Senthil kumar 9943844086 Primary Controller information about the accident/ Shift in charge P & A Dep’t. (HOD) Mr.Balachandar 8056902430 Liaison officer

Key Personnel and their responsibility: Site Controller

The head of the department have overall responsibility for controlling the incident/accident and directing the personnel.

. To prepare full proof plan for control of accident like, landslides, subsidence flood and other natural calamities

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 70

Scheme of Mining of Anandavadi Limestone Mines

. To inform statutory bodies of the State and central Government. . To inform communication officer about the emergency, control centre and assembly point. . To provide all assistance and call for Fire Squad, Security Officer and other services required for removing/control of danger. . To ensure that all necessary personnel to be assemble at assembly point. Accident Controller/Section In charge

. Mock rehearsal of plan prepared for accident. . To withdraw men/machines from the affected area with priority for safety of personnel, minimize damage to the machines, environment and loss of material. . To act as accident controller to all the later arrived. . To make a report based on the facts and figure and submit to the Site Controller Primary Controller/ Shift in charge

. To inform the Accident Controller / shift in charge from the nearest means of communication about the location and the nature of accident.

. To assist in clearing any obstruction in relief of accident.

. To carry out all instructions of accident controller.

Capability of Lessee: Following facilities are available at Mines.

. Public addressing system

. Telephones/ Mobile handsets

. Runners/messenger

. Emergency alarm

. Fire fighting equipments & accessories with trained manpower

. Full fledge dispensary

. Training centre

. Fire tender, Ambulance

Facilities available out side

Government Hospital at Ariyalur, Kadugur & Sendurai are available.

As per Risk Assessment studies, the possibility of “Offsite” emergency situation are ruled out

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 71

Scheme of Mining of Anandavadi Limestone Mines

as proposed mine is not likely to pose any offsite emergency and hence does not call for any preparation of an off-site emergency plan. Further the residential quarters and living area are far from the mine. However, considering extreme situation, District authority including police would be informed about any offsite emergency if situation arises.

8.5 Care and maintenance during temporary discontinuance: An emergency plan for the situation of temporary discontinuance due to court order or due to statutory requirements or any other unforeseen circumstances may indicate measures of care, maintenance and monitoring of status of discontinued mining operations expected to re-open in near future.

When the mine is temporarily discontinuance due to any unforeseen circumstances the following care and maintenance shall be carried out: -

. Notice to be served to the all concerned authority . The mining pit area shall be covered by temporary fencing . All access roads / openings to the pit/face shall be closed by parapet wall as per rule. . Warning shall be display on “Notice Board” at appropriate places . Security personnel shall be posted at every danger point. . No unauthorized person shall be allowed to enter into the mine without prior permission of the management. . All men and machinery shall be withdrawn from the mine and shall be kept in a compact and safe place. . All safety precautions shall be taken care off as per rule.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 72

Scheme of Mining of Anandavadi Limestone Mines

8.6 Financial Assurance:

Table indicating the Breakup of areas in the Mining lease for calculation of Financial assurance. ( as per circular 4/2006)

Sl. Head Area put on Additional Total Area Net area No use at start of requirement (In Ha.) considered as considered Scheme of during plan fully reclaimed for Mining period & rehabilitated calculation (in Ha.) (In Ha.) (in Ha.) (in Ha.) A B C = A+B D E=C- D 1 Area under mining 3.045 4.000 7.045 0.000 7.045

2 Storage for topsoil 0.000 0.500 0.000 0.500 0.500 3 Waste dump 0.000 1.000 1.900 2.900 2.900 4 Mineral storage 0.000 0.000 0.000 0.000 0.000

5 Infrastructure 0.150 0.050 0.200 0.000 0.200

6 Road 0.200 0.300 0.500 0.000 0.500

7 Railways 0.000 0.000 0.000 0.000 0.000

8 Tailing pond 0.000 0.000 0.000 0.000 0.000

9 Effluent treatment 0.000 0.000 0.000 0.000 0.000 plant 10 Mineral separation 0.000 0.000 0.000 0.000 0.000 plant 11 Township 0.000 0.000 0.000 0.000 0.000

12 Others to specify 25.000 2.500 27.500 0.000 27.500 Green belt Grand Total 29.895 8.750 38.645 38.645

Area put to use for mining & allied services is about 38.645 Ha. for the modification period. As per Rule 23(1) of MCDR 2017 an amount of Rs 1,15,93,500/-(Rupees One Crore Fifteen Lakhs Ninety three thousand Five hundred only) @ Rs. 300000 per Ha. for “A” category mines will be furnished after obtaining clearance from the Regional controller of mines.

The financial assurance in the form of Bank guarantee for the amount of Rs.9,66,125/- has been submitted to IBM as per BG: No. The copy of BG is enclosed as annexure no.16.

The remaining amount of 1,06,27,375/- will be submitted after obtaining clearance from regional Controller of Mines, Chennai.

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 73

Scheme of Mining of Anandavadi Limestone Mines

The details of Bank Guarantee are given below:

Sl. Bank Guarantee No. & date Amount Validity No (in Rs.)

1 BG No.

18.02.2016

2 BG No.

Total

(B.Gangatharan) Qualified Person

Modifications to the Approved Mining Plan of Anandavadi Limestone Mines (G.O.624, Ext.110.68.5Ha.) 74

N

318 GCP-1 E 79' 10' 47.9" / N 11'11'22.5" /101.0 SE 419 M FROM BP-33 302 GCP-2 E 79' 10' 53.3" / N 11'11'12.7" / 97.0 E 98M FROM BP-33 362 GCP-3 E 79' 10' 54.0" / N 11'11'15.7" / 97.0 SE 137M FROM BP-33 BP-33 E 79' 10' 56.3" / N 11'11'11.8" / 95.0 NEAR BURIAL GROUND 361 303 307 BP-1 E 79' 10' 54.9" / N 11'11'26.8" / 99.0 ON THE IRUMBULIKURICHI ROAD BP-3 304 419 363 429 369 BP-4

360 420 423 364 306

104m BP-2 305 370 365 359 312 104m BP-5

422 357 368 354 BP-6 313 358 326 366 BP-7 371 BP-8 BP-9 BP-1 353 356 322 367

421 325 314 351 355 326 Koppatti Kovil 352 BP-10 346 GCP-1 345 BP-37 323 BP-36

350 327 321 324 372 320 BP-11 SE 419 M FROM BP-33 BP-14 BP-12 BP-13 BP-35 BP-34 349 328 319 Vathikaruppu kovil 347 GCP-3

344 330 315 Mariamman Kovil GCP-2 348 SE 137M FROM BP-33 FROM 137M SE 318 BP-15 317 340 BP-17

E 98M FROM BP-33 FROM 98M E BP-16 341 331 BP-33 378 343 333

342 334 316 329 383 332 339 335 BP-32 382

BP-19 BP-18 336 BP-31 337 384 766 338 Sellapaudayar kuttai

385 764 743 765 742 BP-30 BP-29 744 763 750 INDEX

BP-20 MIING LEASE BOUNDARY 762 751 767 ROAD 745 746 747 KULAM / KUTTAI CART TRACK

+ ODAI 769 + + + BURIAL GROUND 741 + 749 Anandavadi Colony area 761 768 748 752 733 BP-28

753

BP-25 734 760 BP-21

BP-27 733 BP-26

759 754 PLATE NO:2 Applicant:

755 TAMILNADU CEMENTS CORPORATION LTD., BP-24 770 ARIYALUR WORKS

757 756 ANANDAVADI LIMESTONE MINES 758 GO.No.624, dt.23.09.98 BP-23 LEASE PLAN

BP-22 Certified that "the plans & sections are prepared based on lease map authenticated by state Govt."

B.GANGATHARAN Qualified Person Scale 1:2000 SAI GEOSURVEY CONSULTANT N 2000 N TO IRUMBILIKURICHI

AGD-25 107.00 GCP-1 E 79' 10' 47.9" / N 11'11'22.5" /101.0 S33° E - 419 M FROM BP-33 GCP-2 E 79' 10' 53.3" / N 11'11'12.7" / 97.0 N21°W-62M FROM BP-33

GCP-3 E 79' 10' 54.0" / N 11'11'15.7" / 97.0 N15°W-148M FROM BP-33 CHOLANKURICHI TO

BP-33 E 79' 10' 56.3" / N 11'11'11.8" / 95.0 NEAR BURIAL GROUND AGD-24 BP-1 E 79' 10' 54.9" / N 11'11'26.8" / 99.0 ON THE IRUMBULIKURICHI ROAD 105.745

BP-3 N 1800

AGD-23 104.090

104m ADTH-5 104m BP-4 102.990 100m AGD-18 105.550 BP-2

102m AGD-22 N 1600 103.175 ADTH-4 BP-5 102.095

AGD-17 101.445 AGD-21 BP-6 102.450 BP-7

102m ADTH-3 BP-8 98m BP-1 101.40 BP-9 101.5

KOVIL AGD-16 Pit No. 1 100.2 100.735 N 1400 AGD-20 99.5 102m 100.180 94.5 BM 99.2 ADTH-2 OFFICE

156m, S84° W 100.34 99.0 BP-10 98.1 TO IRUMBILIKURICHI 100.2 94.5 93.5 AGD-1A GCP-1 BP-37 88.5 87.5 AGD-15 102.700 98.710 BP-36 96.0 100.0 ADTH-10 419m, S33° E BP-11 100m 99.35 94.5 96m 100m Haul Road 99.2 96.0 102.1 ADTH-1 99.200 AGD-14

N 1200 BP-12 AGD-11 104 100.595 BP-13 BP-14 BP-34 98.0 BP-35 DUMP 91.0 ADTH-9 KOVIL 98m 106 85.0 98m

GCP-3148m, N15° W AGD-13 Pit No. 2 97.060 AGD-10 99.405

97.2 90.5 94m 84.5 96m GCP-2

62m, N21° W + + + + + + 96m + + 90 + ADTH-8 BP-15 AGD-12 96.0 N 1000 BP-33 95.00 98.970 BP-17 BP-16 BP-32 102m

ADTH-7 ADTH-15 99.810 94.60 AGD-8 96.080 94m

BP-31

N 800 ADTH-14 BP-19 BP-18100m 92m ADTH-6 98.60 91.50 AGD-7 98m 94.225 IDAYANKULAM

94m ADTH-13 97.650 BP-30 BP-29 INDEX 92m AGD-9 AGD-5 96.915 93.095 MIING LEASE BOUNDARY 96m QUARRY N 600 ADTH-12 96m CONTOUR LINE 95.840 BP-20 ROAD HAUL ROAD AGD-4 97.080 KULAM / KUTTAI

AGD DIAMOND DRILL HOLE

ADTH-19 GCP GROUND CONTROL POINT 93.33 CART TRACK ADTH-11 93.90 ODAI AGD-3 + + + BURIAL GROUND N 400 96.220 + + BP-28 WELL ADTH-18 ACTIVE TOP SOIL DUMP YARD 94.620 94m LIMESTONE OUTCROP

Eqalyptus plants by TNPL AGD-2 BP-21 94.225 Buildings

ADTH-17 BP-27 BP-25 94.450 BP-26 N 200

PLATE NO:3 Applicant:

TAMILNADU CEMENTS CORPORATION LTD.,

92m ARIYALUR WORKS 0 20 40 60 80 100 200 300 400 500 AGD-6 Scale 1:2000 BP-24 92.415 ADTH-16 ANANDAVADI LIMESTONE MINES 92m 92.520 GO.No.624, dt.23.09.98 SURFACE PLAN

Certified that "the plans & sections are prepared based on lease map authenticated by state Govt." N 0 BP-23 E 0 E 200 E 400 E 600 AGD-1 E 800 E 1000 91.350 BP-22 B.GANGATHARAN Qualified Person Date of survey 05.04.18 Scale 1:2000 SAI GEOSURVEY CONSULTANT N 2000 A' N TO IRUMBILIKURICHI

AGD-25 107.00 GCP-1 E 79' 10' 47.9" / N 11'11'22.5" /101.0 S33° E - 419 M FROM BP-33 GCP-2 E 79' 10' 53.3" / N 11'11'12.7" / 97.0 N21°W-62M FROM BP-33

GCP-3 E 79' 10' 54.0" / N 11'11'15.7" / 97.0 N15°W-148M FROM BP-33 CHOLANKURICHI TO

BP-33 E 79' 10' 56.3" / N 11'11'11.8" / 95.0 NEAR BURIAL GROUND AGD-24 BP-1 E 79' 10' 54.9" / N 11'11'26.8" / 99.0 ON THE IRUMBULIKURICHI ROAD 105.745

BP-3 N 1800

AGD-23 104.090 C' 104m

ADTH-5 AGD-18 104m BP-4 102.990 B' 100m 105.550

BP-2

102m AGD-22 N 1600 103.175 ADTH-4 BP-5 102.095

AGD-17 101.445 PBH-1 AGD-21 BP-6 102.450 DUMP YARD BP-7

102m ADTH-3 BP-8 98m BP-1 KOVIL BP-9 101.5

Pit No. 1 AGD-16 100.2 100.735 N 1400 AGD-20 99.5 102m 100.180 94.5

TO IRUMBILIKURICHI 99.2 ADTH-2 OFFICE PBH-3

100.34 99.0 BP-10 E' AGD-1A 93.5 98.1 D' A 100.2 94.5 GCP-1 BP-37 88.5 87.5 AGD-15 102.700 98.710 BP-36 96.0 100.0 ADTH-10 BP-11 100m 99.35 94.5 54.7342 96m 100m Haul Road 99.2 96.0 102.1 ADTH-1 99.200 AGD-14 AGD-11 100.595 B N 1200 BP-12 104 BP-13 BP-14 BP-35 BP-34 98.0 ADTH-9 DUMP 91.0 98m 97.20106 KOVIL 85.0 GCP-3 98m AGD-13 96m 97.060 5° AGD-10 DUMP YARD 99.405

97.2 90.5 94m 84.5 GCP-2 Pit No. 2

+ + + + + + + + 96m 90 + BP-33 ADTH-8 BP-15 AGD-12 96.0 AGD-9 N 1000 95.00 98.970 PBH-8 97.82 F' BP-17 BP-16 C BP-32 PBH-6 102m PBH-9 PBH-7 ADTH-7 ADTH-15 5° 99.810 94.60 AGD-8 96.080 94m

BP-31 PBH-10

N 800 ADTH-14 BP-19 BP-18100m 92m ADTH-6 98.60 91.50 AGD-7 98m 94.225 IDAYANKULAM

D PBH-11 G' 94m ADTH-13 97.650 BP-30 BP-29 INDEX 92m AGD-6 PBH-14 93.095 AGD-5 MIING LEASE BOUNDARY 96.91596m E QUARRY N 600 PBH-12 ADTH-12 96m CONTOUR LINE 5° 95.840 BP-20 ROAD H' HAUL ROAD AGD-4 PBH-15 97.080 KULAM / KUTTAI

AGD DIAMOND DRILL HOLE PBH-13 ADTH-19 PBH PROPOSED BORE HOLE 93.33 CART TRACK ADTH-11 93.90 ODAI PBH-16 AGD-3 + + + BURIAL GROUND N 400 96.220 + + BP-28 GCP GROUND CONTROL POINT ADTH-18 5° DIP & STRIKE F 94.620 94m PBH-18 ACTIVE TOP SOIL DUMP YARD

PROPOSED DUMP YARD AGD-2 BP-21 94.225 ULTIMATE PIT LIMIT

LIMESTONE OUTCROP

ADTH-17 INTERSTITIAL REJECTS BP-25 PBH-17 94.450 BP-27 G PBH-19 LIMESTONE WITH MARL BP-26 5° Eqalyptus plants by TNPL N 200

PLATE NO: 4 Applicant:

I' TAMILNADU CEMENTS CORPORATION LTD.,

92m ARIYALUR WORKS 0 20 40 60 80 100 200 300 400 500 AGD-26 Scale 1:2000 BP-24 92.415 ADTH-16 ANANDAVADI LIMESTONE MINES 92m 92.520 GO.No.624, dt.23.09.98 PBH-20 H GEOLOGICAL PLAN

Certified that "the plans & sections are prepared N 0 BP-23 based on lease map authenticated by state Govt." E 0 E 200 E 400 E 600 AGD-1 E 800 E 1000 91.350 BP-22 B.GANGATHARAN I Qualified Person Date of survey 05.04.18 Scale 1:2000 SAI GEOSURVEY CONSULTANT 748.1403

N Section along AGD - 19 to AGD - 25 Section along ADTH -1 to ADTH - 4 UPL A' UPL AGD-25 AGD-24 107.10 107.0 AGD-23 105.74 A 104.10 AGD-22 AGD-21 103.75 102.0 AGD-20 102.50 AGD-19 101.7 B' 99.64 100.0 100.0 B ADTH-4 UPL ADTH-3 PBH-1 102.10 102.0 102.0 ADTH-2 Existing Pit 96.0 96.0 101.40 ADTH-1 100.14 UPL 95.0 95.0 100.0 100.0 99.5 PBH-2 94.0 94.0 93.0 93.0 92.0 A 92.0 96.0 96.0 95.0 95.0 SST 94.0 94.0 88.0 88.0 93.0 93.0 92.0 92.0

84.0 84.0 10.40 88.0 88.0 22.60 80.0 80.0 84.0 84.0 16.50 76.0 76.0 20.0 80.0 80.0

72.0 30.10 34.0 72.0 24.00 76.0 31.0 76.0 30.50 30.0 0.0 200 400 600 34.20 68.0 68.0 INDEX ( 221 ) ( 221 )

64.0 64.0 ( 111 ) MINING LEASE BOUNDARY 60.0 60.0 0.0 200 400 600 800 1000 1200

( 221 ) ( 221 ) ULTIMATE PIT LIMIT

( 111 )

TOP SOIL C C' 102.0 Section along AGD -12 to AGD -18 102.0 Section along ADTH -6 to ADTH - 9 & ADTH - 2 LIMESTONE WITH MARL 102.0 102.0

106.0 AGD-18 106.0 105.05 104.0 104.0 SANDSTONE AGD-17 102.0 AGD-16 101.45 102.0 UPL UPL 100.7 100.0 100.0 AGD-14 AGD-15 PBH-3 ADTH-15 AGD-13 98.6 98.40 D' EXISTING CORE DRILL BH PBH-4 AGD-12 97.40 PBH-5 D 96.0 96.0 96.57 ADTH-2 95.0 95.0 102.0 102.0 94.0 94.0 PBH-9 93.0 93.0 100.0 ADTH-9 100.0 PROPOSED CORE DRILL BH 92.0 92.0 97.20 ADTH-7 ADTH-8 96.0 94.60 PBH-6 95.0 96.0 88.0 88.0 95.0 95.0 94.0 ADTH-6 94.0 93.0 91.90 93.0 92.0 92.0 84.0 84.0

88.0 88.0 VERTICAL- 1CM = 5 M 80.0 80.0 84.0 84.0 HORIZONTAL - 1CM = 50 M 76.0 76.0

80.0 14.0 80.0 72.0 72.0

76.0 76.0 68.0 32.65 68.0 20.40 31.00 36.50 29.50 31.00 16.5 30.65 72.0 72.0 64.0 64.0 30.0 63.0 63.0 62.0 62.0 30.0 61.0 61.0 68.0 68.0

59.0 59.0

57.0 57.0 64.0 64.0 41.60 0.0 200 400 600 800 55.0 55.0

( 221 ) 0.0 200 400 600 800 1000 1200 ( 221 )

( 111 ) ( 111 ) ( 221 ) ( 221 ) 538.8625 Section along AGD-6 to AGD-11 & AGD-11A Section along ADTH - 11 to ADTH - 15 Area available for mining after leaving safety distance E E'

AGD-11A 102.0 102.70 102.0 AGD-11 F F' 100.0 ( 50.0 m Safety zone barrier ) AGD-10 100.59 100.0 AGD-9 99.04 PBH-8 97.82 AGD-8 102.0 102.0 96.0 AGD-7 96.08 96.0 95.0 PBH-7 95.0 ADTH-15 94.25 100.0 PBH-9 100.0 94.0 AGD-6 94.0 ADTH-14 99.81 ADTH-13 PBH-10 93.0 93.095 93.0 98.60 97.65 PBH-11 92.0 92.0 2.0000 ADTH-12 95.84 PBH-12 96.0 ADTH-11 96.0 95.0 93.90PBH-13 95.0 94.0 94.0 88.0 88.0 93.0 93.0 92.0 92.0

84.0 84.0 88.0 88.0

80.0 80.0 8.00 84.0 84.0 13.00 15.00 76.0 76.0 15.00 17.00 80.0 80.0

72.0 72.0 76.0 76.0 0.0 200 400 600 800 68.0 68.0 30.90 31.00 30.10 ( 221 ) ( 221 )

64.0 30.10 64.0 ( 111 ) 63.0 63.0 30.50 62.0 38.70 62.0 61.0 32.0 61.0

59.0 59.0 0.0 200 400 600 800 1000 1200

( 221 ) ( 221 )

( 111 )

Section along AGD - 1 to AGD - 26 Section along AGD - 2 to AGD - 5 I I' PLATE NO: 5 G 102.0 102.0 G' 100.0 100.0 Section along ADTH - 16 to ADTH - 19 Applicant: 102.0 102.0

100.0 100.0 96.0 96.0 95.0 95.0 AGD-4 AGD-5 AGD-1 AGD-26 AGD-3 97.08 94.0 94.0 PBH-15 PBH-14 96.915 93.0 92.45 93.0 TAMILNADU CEMENTS CORPORATION LTD., 96.0 AGD-2 96.220 96.0 PBH-20 H H' 95.0 94.225 PBH-16 95.0 92.0 91.35 92.0 94.0 94.0 93.0 93.0 102.0 102.0 92.0 92.0 88.0 88.0 100.0 100.0 ARIYALUR WORKS.

88.0 88.0 84.0 84.0 96.0 ADTH-17 ADTH-18 96.0 95.0 94.45 PBH-19 94.260 PBH-18 ADTH-19 95.0 94.0 93.30 94.0 ADTH-16 84.0 84.0 93.0 93.0 80.0 80.0 92.0 92.52 92.0 ANANDAVADI LIMESTONE MINES

80.0 SST 80.0 76.0 76.0 88.0 88.0 GO.No.624, dt.23.09.98

76.0 76.0 72.0 72.0 84.0 84.0

12.0 72.0 72.0 10.0 GEOLOGICAL SECTIONS 68.0 68.0 80.0 80.0 SST

68.0 68.0 64.0 64.0 76.0 76.0 18.0 Certified that "the plans & sections are prepared 17.00 30.20 30.25 64.0 64.0 60.0 60.0 72.0 72.0 based on lease map authenticated by state Govt." 31.0 30.60

60.0 60.0 56.0 56.0 68.0 68.0 0.0 200 400 600

( 221 ) ( 221 ) 38.45 52.0 38.0 52.0 64.0 64.0 B.GANGATHARAN ( 111 ) 48.0 48.0 60.0 60.0 Qualified Person 0.0 200 0.0 200 400 600

( 221 ) ( 221 ) ( 111 ) ( 221 ) ( 111 ) ( 221 ) SAI GEO SURVEY CONSULTANT N 2000 N

C C' 102.0 102.0 TO IRUMBILIKURICHI 102.0 Section along C - C' 102.0 106.0 106.0

104.0 104.0

102.0 102.0 MLB UPL UPL 100.0 100.0 AGD-25 96.0 96.0 95.0 95.0 94.0 94.0 93.0 93.0 92.0 92.0 107.00

88.0 88.0

84.0 84.0

80.0 80.0

76.0 76.0

72.0 72.0 TO CHOLANKURICHI TO

68.0 68.0

64.0 64.0 63.0 63.0 62.0 62.0 61.0 61.0

59.0 59.0

57.0 57.0 55.0 55.0 AGD-24 0.0 200 400 600 800 1000 1200 105.745

BP-3

N 1800 B' MLB B MLB UPL UPL 102.0 102.0 100.0 100.0

96.0 96.0 95.0 95.0 94.0 94.0 93.0 93.0 92.0 92.0

88.0 88.0

84.0 84.0

80.0 80.0

76.0 76.0 0.0 200 400 600 C'

Section along B - B' 104m

104m BP-4 B' 100m

BP-2

102m

N 1600 BP-5

BP-6 BP-7

102m BP-8 98m BP-1 KOVIL BP-9 101.5

Pit No. 1 100.2 N 1400 99.5 102m

94.5

TO IRUMBILIKURICHI 99.2

OFFICE

99.0 BP-10 93.5 100.2 94.5 98.1 BP-37 88.5 87.5 BP-36 96.0 100.0

100m BP-11 94.5 96m 100m Haul Road 99.2 96.0 102.1

N 1200 BP-12 104 BP-13 BP-14 BP-34 98.0 BP-35 DUMP 91.0 98m 106 85.0 Proposed Dumping area B 98m

96m

97.2 90.5 94m 84.5

+ + + + + + + + 96m 90 + BP-33 BP-15 96.0 N 1000 BP-17 BP-16 C BP-32 102m

94m

BP-31

N 800 BP-19 BP-18100m 92m 98m

IDAYANKULAM

94m

BP-30 BP-29 INDEX 92m MIING LEASE BOUNDARY 96m QUARRY N 600 96m CONTOUR LINE BP-20 ROAD HAUL ROAD

KULAM / KUTTAI

CART TRACK

ODAI

+ + + + + BURIAL GROUND LIMESTONE N 400 BP-28 DIP & STRIKE

94m DUMP YARD ULTIMATE PIT LIMIT

BP-21 2018- 19 Year Programme

Proposed Dumping Area

BP-27 BP-25 BP-26

N 200

PLATE NO: 6 Applicant:

TAMILNADU CEMENTS CORPORATION LTD., ARIYALUR WORKS 0 20 40 60 80 100 200 300 400 500 92m Scale 1:2000 BP-24 ANANDAVADI LIMESTONE MINES 92m GO.No.624, dt.23.09.98 YEARLY DEVELOPMENT & PRODUCTION PLAN FOR 2018-19 Certified that "the plans & sections are prepared based on lease map authenticated by state Govt." N 0 BP-23 E 0 E 200 E 400 E 600 E 800 E 1000 BP-22 B.GANGATHARAN Qualified Person Scale 1:2000 SAI GEOSURVEY CONSULTANT N 2000 A' N

C C' 102.0 Section along C - C' 102.0 TO IRUMBILIKURICHI 102.0 102.0

106.0 106.0

104.0 104.0

102.0 102.0 MLB UPL UPL 100.0 100.0 AGD-25 96.0 96.0 95.0 95.0 94.0 94.0 93.0 93.0 92.0 92.0 107.00

88.0 88.0

84.0 84.0

80.0 80.0

76.0 76.0

72.0 72.0 TO CHOLANKURICHI TO

68.0 68.0

64.0 64.0 63.0 63.0 62.0 62.0 61.0 61.0

59.0 59.0

57.0 57.0 55.0 55.0 AGD-24 0.0 200 400 600 800 1000 1200 105.745

Section along D - D' BP-3 D' D MLB UPL UPL MLB N 1800 102.0 102.0 100.0 100.0

96.0 96.0 95.0 95.0 94.0 94.0 93.0 93.0 92.0 92.0

88.0 88.0

84.0 84.0

80.0 80.0

76.0 76.0 20.40

72.0 72.0 30.0

30.0 C' 68.0 68.0

64.0 64.0 0.0 200 400 600 800 104m

104m BP-4 100m

BP-2

102m

N 1600 BP-5

BP-6 BP-7

102m BP-8 98m BP-1 BP-9

100 N 1400 102m 91.5

84.5

84.5

TO IRUMBILIKURICHI 91.5 100.2

OFFICE

A BP-10 D' 90.5

BP-37 83.5 99 BP-36 96.0 100.0 100m BP-11 96m 100m Haul Road 96.0 102.1

N 1200 BP-12 104 BP-13 BP-14

97.0 BP-34 88.5

BP-35 81.5 DUMP 98m 106 Proposed Dumping area 98m

96m 81.5 88.5 97.2 94m

+ + + + + + + + 96m + BP-33 BP-15

N 1000 BP-17 BP-16 C BP-32 102m

94m

BP-31

N 800 BP-19 BP-18100m 92m 98m Proposed Dumping area IDAYANKULAM

D

94m

BP-30 BP-29 INDEX 92m MIING LEASE BOUNDARY 96m QUARRY N 600 96m CONTOUR LINE BP-20 ROAD HAUL ROAD

KULAM / KUTTAI

CART TRACK

ODAI

+ + + + + BURIAL GROUND LIMESTONE N 400 BP-28 DIP & STRIKE

94m DUMP YARD ULTIMATE PIT LIMIT

BP-21 2019- 20 Year Programme

Proposed Dumping Area

BP-27 BP-25 BP-26 N 200

PLATE NO: 7 Applicant:

TAMILNADU CEMENTS CORPORATION LTD., ARIYALUR WORKS 0 20 40 60 80 100 200 300 400 500 92m Scale 1:2000 BP-24 ANANDAVADI LIMESTONE MINES 92m GO.No.624, dt.23.09.98 YEARLY DEVELOPMENT & PRODUCTION PLAN FOR 2019-20 Certified that "the plans & sections are prepared based on lease map authenticated by state Govt." N 0 BP-23 E 0 E 200 E 400 E 600 E 800 E 1000 BP-22 B.GANGATHARAN Qualified Person Scale 1:2000 SAI GEOSURVEY CONSULTANT N 2000 A' N TO IRUMBILIKURICHI

AGD-25 107.00 Section along F - F'

F F' MLB UPL MLB UPL 102.0 102.0

100.0 100.0

96.0 96.0

95.0 95.0 94.0 94.0 CHOLANKURICHI TO 93.0 93.0 92.0 92.0

88.0 88.0

84.0 84.0

80.0 80.0 AGD-24

76.0 76.0 0.0 200 400 600 800 105.745 ( 221 ) ( 221 )

( 111 )

BP-3 N 1800

104m

104m BP-4 100m

BP-2

102m

N 1600 BP-5

BP-6 BP-7

102m BP-8 98m BP-1 BP-9

100 N 1400 102m 91.5 84.5

84.5 79

91.5

TO IRUMBILIKURICHI 82.5 100.2

OFFICE

A BP-10 90.5 83.5

BP-37 76.5 99 BP-36 96.0 100.0 100m BP-11 96m 100m 96.0 102.1

N 1200 BP-12 104 BP-13 BP-14

97.0 BP-35 BP-34 88.5 81.5 DUMP

74.5 98m 106 Proposed Dumping area 98m

96m

81.5 79.5 97.2 88.5 94m

+ + + + + + + + 96m + BP-33 BP-15

N 1000 F' BP-17 BP-16

94 BP-32 78.5 85.5 102m

94m

75.5

BP-31 82.5

91 N 800 BP-19 BP-18100m 92m 98m Proposed Dumping area IDAYANKULAM

94m

BP-30 BP-29 INDEX 92m MIING LEASE BOUNDARY 96m QUARRY N 600 96m CONTOUR LINE BP-20 ROAD HAUL ROAD

KULAM / KUTTAI

CART TRACK

ODAI

+ + + + + BURIAL GROUND LIMESTONE N 400 BP-28 DIP & STRIKE

F 94m DUMP YARD ULTIMATE PIT LIMIT

BP-21 2020- 21 Year Programme

Proposed Dumping Area

BP-27 BP-25 BP-26

N 200

PLATE NO: 8 Applicant:

TAMILNADU CEMENTS CORPORATION LTD., ARIYALUR WORKS 0 20 40 60 80 100 200 300 400 500 92m Scale 1:2000 BP-24 ANANDAVADI LIMESTONE MINES 92m GO.No.624, dt.23.09.98 YEARLY DEVELOPMENT & PRODUCTION PLAN FOR 2020-21 Certified that "the plans & sections are prepared based on lease map authenticated by state Govt." N 0 BP-23 E 0 E 200 E 400 E 600 E 800 E 1000 BP-22 B.GANGATHARAN Qualified Person Scale 1:2000 SAI GEOSURVEY CONSULTANT N

WASTE DRY LAND

N 2000

TO IRUMBILIKURICHI TO CHOLANKURICHI TO

N 1800 WIND DIRECTION

104m

104m 100m

WASTE DRY LAND WASTE DRY LAND

102m

N 1600

SW 102m 98m

KOVIL 101.5

Pit No. 1 100.2 N 1400 99.5 102m 99.0 94.5

TO IRUMBILIKURICHI 99.2

OFFICE 99.0

100.2 94.5 93.5 98.1 GCP-1 88.5 87.5

96.0 100.0

100m 94.5 96m 100m 99.2 96.0 102.1 500 M N 1200 104

98.0 DUMP 91.0 98m 106 KOVIL 85.0 98m INDEX GCP-3 97.0 96m

97.2 90.5 94m

84.5 MIING LEASE BOUNDARY GCP-2

+ + + + + BURIAL GROUND + + + 96m 90 96m CONTOUR LINE +

96.0 N 1000 ROAD 500 M 102m HAUL ROAD

KULAM / KUTTAI 94m CART TRACK N 800 100m 92m 60M RADIUS 98m ODAI IDAYANKULAM + + + BURIAL GROUND 94m + +

92m DUMP YARD

WASTE DRY LAND

96m N 600 ULTIMATE PIT LIMIT

60 M ZONE AREA

500 M ZONE AREA Eaucalyptus plants by TNPL

N 400 Vegetation area within 60m 94m

RESERVED FOREST LAND

WASTE DRY LAND Village Population Distance Direction 60M RADIUS

Sendurai 1.4 km SW N 200 4637 Maruvattur 2761 3.1 km SE NE Periakurichi 3253 3.9 km NE 92m Nakkambadi 2679 2.6 km NW 92m Vanjinapuram 2798 3.0 km NW

N 0 E 0 E 200 E 400 E 600 E 800 E 1000

WIND DIRECTION

PLATE NO:9 Applicant: TAMILNADU CEMENTS CORPORATION LTD., ARIYALUR WORKS WASTE DRY LAND ANANDAVADI LIMESTONE MINES GO.No.624, dt.23.09.98

ENVIRONMENT PLAN

Certified that "the plans & sections are prepared based on lease map authenticated by state Govt."

B.GANGATHARAN RQP/MAS/120/98-A Scale 1:5000 SAI GEOSURVEY CONSULTANT N 2000 A' N TO IRUMBILIKURICHI

AGD-25

107.00 TO CHOLANKURICHI TO

AGD-24 105.745

BP-3 N 1800

104m

104m BP-4 100m

BP-2

102m

N 1600 BP-5

BP-6 BP-7

102m BP-8 98m BP-1 BP-9

100 N 1400 102m 91.5

84.5

84.5 79

91.5

TO IRUMBILIKURICHI 82.5 100.2 OFFICE

A BP-10

90.5 83.5

BP-37 76.5 99 BP-36 96.0 100.0 100m BP-11 96m 100m 96.0 102.1

N 1200 BP-12 104 BP-13 BP-14 97.0 BP-35 BP-34 88.5 81.5 DUMP

74.5 98m 106 Proposed Dumping area 98m

96m 81.5 79.5

97.2 88.5 94m

+ + + + + + + + 96m + BP-33 BP-15

N 1000 BP-17 BP-16

94 BP-32 78.5 85.5 102m

94m

75.5

BP-31 82.5

91 N 800 BP-19 BP-18100m 92m 98m Proposed Dumping area IDAYANKULAM

94m

BP-30 BP-29 INDEX 92m MIING LEASE BOUNDARY 96m QUARRY N 600 96m CONTOUR LINE BP-20 ROAD HAUL ROAD

KULAM / KUTTAI

CART TRACK

ODAI

+ + + + + BURIAL GROUND LIMESTONE N 400 BP-28 DIP & STRIKE

94m DUMP YARD ULTIMATE PIT LIMIT

5th YEAR PIT LIMIT BP-21 GREENBELT DEVELOPMENT AREA Proposed Dumping Area

BP-27 BP-25 BP-26

N 200

PLATE NO: 10 Applicant:

TAMILNADU CEMENTS CORPORATION LTD., ARIYALUR WORKS 0 20 40 60 80 100 200 300 400 500 92m Scale 1:2000 BP-24 ANANDAVADI LIMESTONE MINES 92m GO.No.624, dt.23.09.98

FINANCIAL AREA ASSURANC PLAN

Certified that "the plans & sections are prepared based on lease map authenticated by state Govt." N 0 BP-23 E 0 E 200 E 400 E 600 E 800 E 1000 BP-22 B.GANGATHARAN Qualified Person Scale 1:2000 SAI GEOSURVEY CONSULTANT N 2000 N

TO IRUMBILIKURICHI TO CHOLANKURICHI TO

N 1800

104m B'

104m 100m

WASTE DRY LAND 102m WASTE DRY LAND

N 1600

PIT LIMIT AT THE END OF LIFE OF MINE

102m 5TH YEAR PIT LIMIT 98m

KOVIL

N 1400 102m

TO IRUMBILIKURICHI A A' OFFICE

100m 100m

99.1

ACTIVE TOP SOIL DUMP 100 x 25 x 3m

N 1200 99.4

98m KOVIL

Y' 98m 97.0 PROPOSED WASTE DUMP

94m

+ + + + + + + + 96m + PIT LIMIT AT THE END OF LIFE OF MINE

N 1000

102m

94m

N 800 100m 92m

B 98m PROPOSED WASTE DUMP IDAYANKULAM

PROPOSED WASTE DUMP

INDEX

MIING LEASE BOUNDARY 92m QUARRY

96m 96m CONTOUR LINE N 600 ROAD HAUL ROAD

KULAM / KUTTAI X X' CART TRACK ODAI

+ + + + + BURIAL GROUND

WASTE DRY LAND ULTIMATE PIT LIMIT

GREEN BELT DEVELOPMENT AREA

ACTIVE TOP SOIL DUMP YARD N 400 PROPOSED WASTE DUMP YARD

SANDSTONE 94m

RESERVED FOREST LAND

N 200

92m 92m

N 0 21.6759 E 0 E 200 E 400 E 600 E 800 E 1000 PLATE NO:11 37.0254 Applicant: TAMILNADU CEMENTS CORPORATION LTD., Y ARIYALUR WORKS UPL WEST ML EAST

X SECTION ALONG X -X' ML X' UPL ANANDAVADI LIMESTONE MINES 100 100 95 95 GO.No.624, dt.23.09.98 85 85

75 75

65 65 55 55 CONCEPTUAL PLAN & SECTIONS

Certified that "the plans & sections are prepared SOUTH NORTH

UPL based on lease map authenticated by state Govt." ML ML

Y UPL Y' UPL Proposed Waste dump UPL 100 SECTION ALONG Y -Y' 100 95 95

85 85 75 75 B.GANGATHARAN 65 65

55 55 Qualified Person Scale 1:2000 SAI GEOSURVEY CONSULTANT