LITHGOW / BATHURST DISTRICT (Inc. Lithg ow, Bathurst, Orange and Mudgee areas) To Fr Weekly Road Report Western Region 29 October 2018

LITHGOW / BATHURST DISTRICT (Inc. Lithgow, Bathurst, Orange and Mudgee areas)

PRIMARY LOCATION: HILL END ROAD – MR 216 Work type: Narrow bridge sign installation Location: Wallaby Rocks Bridge over Turon River, 5km West of Sofala. Lane closures: Nil. Reduction in speed limits only. Impact: Delays up to 5 minutes can be expected. Speed restrictions: 40, 60, 80 km/h as directed. Working days: Mon to Fri. Working hours: 0700 to 1700 hours. Expected completion: 1 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Manager: Tom Carruthers 0437 631 078

PRIMARY LOCATION: CHIFLEY ROAD – MR516 Work type: Bridge Approaches construction and road realignment. Location: 10Km East of Lithgow at Clarence Lane closures: Intermittent lane closures during working hours. Works to be completed behind steel barriers Impact: Delays up to 10 minutes can be expected. Speed restrictions: 40, 60, km/h as directed. Working days: Mon – Saturday Working hours: 0700 – 1800 hours Mon-Fri - 0700 to 1300 Sat Expected completion: 30 July 2019 Advice / Comments: Please obey all signs and proceed with care. Speed reduction in place after hours. Project Manager: Pat Pina 0429986576

PRIMARY LOCATION: MID WESTERN – HW6 Work type: Heavy patching. Location: 30km West of Bathurst. Lane closures: Intermittent. Impact: Delays up to 10 min can be expected during work hours. Speed restrictions: 40, 60km/h as directed. Working days: Mon to Sat. Working hours: 0700 to 1800 Mon to Fri and 0700 to 1300 Sat. Expected completion: 3 November 2018 Advice / comments: Please obey all signs and proceed with care. Speed reduction in place After Hours. Project Manager: Miles Harrison 0407 047 256

Page 1 of 10

LITHGOW / BATHURST DISTRICT (Inc. Lithgow, Bathurst, Orange and Mudgee areas)

PRIMARY LOCATION: SOFALA ROAD- MR 54 Work type: Heavy patching Location: Various locations between Bathurst heading North and south of , towards Goulburn and Mudgee. Lane closures: One lane closed during working hours Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Sat Working hours: 0700-1800 Expected completion: 23 November 2018 Advice / comments: Please obey all signs and proceed with care. Project Manager Karolina Kosmicki 0428 400 448

PRIMARY LOCATION: O’CONNELL ROAD- MR 253 Work type: Heavy patching Location: Various locations between Bathurst heading to O’Connell Road for about 20km from Great Western Highway. Lane closures: One lane closed during working hours Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Sat Working hours: 0700-1800 Expected completion: 23 November 2018 Advice / comments: Please obey all signs and proceed with care. Project Manager Karolina Kosmicki 0428 400 448

PRIMARY LOCATION: GOOLMA ROAD- MR633 Work type: Pavement Widening Location: 34.78-39.62km from Mudgee Lane closures: One lane closed during working hours Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Sat Working hours: 0700-1800 Expected completion: 22 February 2019 Advice / comments: Please obey all signs and proceed with care. Project Manager Karolina Kosmicki 0428 400 448

PRIMARY LOCATION: – HW7 Work type: Shoulder widening Location: The Rocks, 15km west of Bathurst Lane closures: Reduction in speed limits only. Shoulder closed. Impact: Delays of up to 5 mins can be expected Speed restrictions: 60 km/h as directed. Working days: Mon – Fri Working hours: 0700-1800 hours Expected completion: 28 November 2018 Advice / comments: Please obey all signs and proceed with care. Project Manager Renee Massurit 0437 839 305

Page 2 of 10

DUBBO DISTRICT (Inc. Forbes, Cobar, Coolah, Bourke, Parkes, Walgett & Wellington areas)

PRIMARY LOCATION: MITCHELL HIGHWAY – HW7 Work Type: West Nevertire Shoulder widening and strengthening Location: Approx 11km to18km west of Nevertire (Segment 2565 & 2570) Lane Closures: Intermittent Impact: Delays up to 10 min can be expected during work hours Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Sat Working hours: 0700 to 1800 hours Mon to Fri and 0700 to 1600 Sat Expected completion: 16 November 2018 Advice / Comments: Please obey all signs and proceed with care. Project Manager: Aaron Berry 0439 011 592

PRIMARY LOCATION: – HW17 Work Type: Godwins Lane Rehabilitation – Culvert Works and Side Track Location: Approx 25kms north of Dubbo on the Newell Highway Lane Closures: No lane closure. Impact: No delays expected Speed restrictions: 60 km/h Working days: Mon to Fri Working hours: 0700 to 1800 Expected completion: 2 November 2018 Advice / Comments: Please obey all signs and proceed with care Project Manager: Geoff Collison 0428 980 385

PRIMARY LOCATION: MITCHELL HIGHWAY – HW7 Work Type: Improvement for New Solar Farm Access Location: Approx 1.0 km west of Nevertire Lane Closures: Intermittent Impact: Delays up to 10 min can be expected during work hours Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Sat Working hours: 0700 to 1800 hours Mon to Fri and 0700 to 17.00 Sat Expected completion: 30 November 2018 Advice / Comments: Please obey all signs and proceed with care. Project Manager: Siva Chandrasorupan – 0427 662 062

PRIMARY LOCATION: PAYTENS BRIDGE ROAD – LR1570003 Work type: Timber Bridge Rehab. Location: Paytens Bridge, Lachlan River at Collett’s Crossing. Lane closures: One Lane Bridge. Restricted lane width of 3.1m on bridge until further notice. Portable Traffic Lights in operation during working hours. Impact: Over width vehicles should detour via Casuarina Drive and Gooloogong, and allow about 20 minutes additional travel time. Speed restrictions: 40km/h on approach and 20km/h across bridge Working days: Mon – Fri. Working hours: 0700 – 1700 hours. Expected completion: 9 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Manager: Kaushalya Perera 0419 755 999

Page 3 of 10

DUBBO DISTRICT (Inc. Forbes, Cobar, Coolah, Bourke, Parkes, Walgett & Wellington areas)

PRIMARY LOCATION: – HW12 Work type: Routine Bridge Maintenance – Bridge Scour repair Location: Marjorie Walford Bridge, Bridge over Namoi River, Walgett. Lane closures: Intermittent lane closures during working hours. Impact: Delays up to 5 minutes can be expected. Speed restrictions: 40 km/h as directed. Working days: Mon – Friday Working hours: 0700 – 1800 hours Expected completion: 1 November 2018 Advice / Comments: Please obey all signs and proceed with care. Project Manager: Tom Carruthers 0437 631 078

PRIMARY LOCATION: – MR56 Work type: Bridge Maintenance and conversion to single lane traffic Location: Iron Bridge, Reymond Street/Lachlan Valley Way, Forbes. Lane closures: Nil. Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Friday Working hours: 0700-1700 Expected completion: May 2019 Advice / comments: Please obey all signs and proceed with care. Project Manager Thomas Carruthers 0437 631 078

PRIMARY LOCATION: MID WESTERN HIGHWAY – HW6 Work type: Bridge works. Location: 64km west of Grenfell. Lane closures: Side track in operation. Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Sun Working hours: 24 hours Expected completion: 20 February 2019 Advice / comments: Please obey all signs and proceed with care. Project Manager Renee Massurit 0437 839 305

PRIMARY LOCATION: MITCHELL HIGHWAY – HW7 Work type: Pavement Reconstruction Location: 3 – 8 km East of Nyngan Lane closures: One lane closed during working hours. Impact: Delays up to 5 minutes can be expected. Speed restrictions: 40, 60, 80 km/h as directed. Working days: Mon – Saturday Working hours: 0700 – 1800 hours Expected completion: 8 December 2018 Advice / Comments: Please obey all signs and proceed with care. Project Manager: Sam Brown 0427 907 390

Page 4 of 10

DUBBO DISTRICT (Inc. Forbes, Cobar, Coolah, Bourke, Parkes, Walgett & Wellington areas)

PRIMARY LOCATION: THE – MR377 Work type: Heavy Patching Location: Various locations between The Monument and Eugowra Lane closures: One lane closed during working hours Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Sat Working hours: 0700-1800 Expected completion: 02 November 2018 Advice / comments: Please obey all signs and proceed with care. Project Manager Jacob Ward 0419 883 429

PRIMARY LOCATION: PARK ST – MR245 Work type: Crack Sealing Location: Millthorpe, between Blake St and Church St Lane closures: One lane closed during working hours Impact: Delays of up to 5 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Tue Working hours: 0700-1800 Expected completion: 30 October 2018 Advice / comments: Please obey all signs and proceed with care. Project Manager Jacob Ward 0419 883 429

PRIMARY LOCATION: HENRY PARKES WAY – MR61 Work type: Sealing works. Location: Dennison St, Condobolin Lane closures: One lane closed during working hours Impact: Delays of up to 10 mins can be expected Speed restrictions: 40 km/h as directed. Working days: Mon – Fri Working hours: 0700-1800 hours Expected completion: 2 November 2018 Advice / comments: Please obey all signs and proceed with care. Project Manager Renee Massurit 0437 839 305

Page 5 of 10

NARRABRI DISTRICT (Inc. Coonabarabran, Moree, Narrabri and areas)

PRIMARY LOCATION: NEWELL HIGHWAY – HW17 Work type: Wallaroy Overtaking Lanes Location: 31.25 – 34.60 km North of Gilgandra Lane closures: One lane during work hours Impact: Delay up to 10 mins can be expected Speed restrictions: 40, 60, 80 km as directed Working days: Mon to Fri Working hours: 0700 to 1700 hours Expected completion: February 2019 Advice/Comments: Please obey all signs and proceed with care Project Manager: Bradley Edwards 0428 646 683

PRIMARY LOCATION: – HW11 Work type: Nombi Fill Embankments Location: 48 - 49km East of Coonabarabran Lane closures: Both lanes open Impact: Delay up to 5 mins can be expected Speed restrictions: 60, 80 km as directed Working days: Mon to Fri Working hours: 0700 to 1700 hours Expected completion: February 2019 Advice/Comments: Please obey all signs and proceed with care Project Manager: Bradley Edwards 0428 646 683

PRIMARY LOCATION: OXLEY HIGHWAY – HW11 Work type: Concrete repairs, drainage improvements Location: B3523 12.1km west of Mullaley Unnamed culvert Lane closures: One lane during work hours Impact: Delay up to 10 mins can be expected Speed restrictions: 40, 60, 80 km as directed Working days: Mon to Fri Working hours: 0700 to 1700 hours Expected completion: 1 November 2018 Advice/Comments: Please obey all signs and proceed with care Project Manager: Thomas Carruthers 0437 631 078

PRIMARY LOCATION: NEWELL HIGHWAY-HW17 Work Type: Foxes Lane Rehabilitation Location: 55.4km to 60.9km North of Moree Lane Closures: Both Lanes Open Impact: Delays up to 5 min may be expected Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Fri Working hours: 0700 to 1800 hours Mon to Fri Expected completion: April 2019 Advice/Comments: Please obey all signs and proceed with care Project Engineer Kiran Sapkota 0429 268 671

Page 6 of 10

BROKEN HILL DISTRICT (Inc. , Tibooburra, and areas)

PRIMARY LOCATION: – HW8 Work type: Intersection improvement for new Caravan Park & Resort at Mt.Gipps. Location: Approximately 15km east of Broken Hill Lane closures: One lane will be closed with 24 hours traffic lights in operation. Impact: Delays up to 5 -10 minutes can be expected. Speed restrictions: 40, 60 km/h as directed. Working days: Mon – Friday Working hours: 0700 – 1800 hours Expected completion: 30 December 2018 Advice / Comments: Please obey all signs and proceed with care. Project Manager: Siva Chandrasorupan – 0427 662 062

PRIMARY LOCATION: BARRIER HIGHWAY –HW8 Work type: Musheroo Reshape – Culvert Head / Wing Walls extension Location: Various locations between 137km to 148km west of Cobar. Lane closures: None. Impact: Minor delays expected. Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Fri. Working hours: 0700 to 1800 hours. Expected completion: 29 March 2019. Advice / Comments: Detour through temporary unsealed side track (10m wide) with associated connecting ramps to highway are in place. Please obey all signs and proceed with care. Project Manager: Sunil Thapa 0476 809 547

PRIMARY LOCATION: OLD ROAD – LR18 Work type: Patch grading. Location: South of Lake Tandou Lane closures: Nil. Impact: Nil. Speed restrictions: Nil. Working days: Mon to Fri. Working hours: 0600 to 1800 hours. Expected completion: 2 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor: Neville Monaghan 0429 394 612

PRIMARY LOCATION: HENRY ROBERTS ROAD – LR15 Work type: Roads to Recovery works. Location: Various locations east of Pulgamurtie Lane closures: Nil. Impact: Minor delays expected. Speed restrictions: 40, 60, 80 km/h as directed. Working days: Mon to Fri. Working hours: 0600 to 1800 hours. Expected completion: 30 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Neville Monaghan 0429 394 612

Page 7 of 10

BROKEN HILL DISTRICT (Inc. Broken Hill, Tibooburra, Wilcannia and areas)

PRIMARY LOCATION: SILVER CITY HIGHWAY – HW22 Work type: Road construction Location: Warratta Creek, 300km to 308km north of Broken Hill Lane closures: Traffic lights and side tracks will be in operation. Impact: Nil Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Fri. Working hours: 0600 to 1800 hours. Expected completion: 20 December 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Louis Kanu 0476 801 596

PRIMARY LOCATION: MUTAWINTJI NP TO WHITE CLIFFS RD – RR428 Work type: Roads to Recovery works. Location: Various locations near Henry Roberts Rd Lane closures: Nil. Impact: Minor delays expected. Speed restrictions: 40, 60, 80 km/h as directed. Working days: Mon to Fri. Working hours: 0600 to 1800 hours. Expected completion: 30 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Neville Monaghan 0429 394 612

PRIMARY LOCATION: SILVER CITY HIGHWAY – HW22 Work type: Resealing Location: 85km North of Broken Hill Lane closures: Stop/slow traffic. Wait times up to 10 min at times. Impact: Approximate 10 Minute wait time Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Sat. Working hours: 0600 to 1800 hours Mon to Fri and 0700 to 1700 on Sat.. Expected completion: 2 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Brett Gould 0428 778 944

PRIMARY LOCATION: SILVER CITY HIGHWAY – HW22 Work type: Resealing Location: 210km North of Broken Hill Lane closures: Stop/slow traffic. Wait times up to 10 min at times. Impact: Approximate 10 Minute wait time Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Sat. Working hours: 0600 to 1800 hours Mon to Fri and 0700 to 1700 on Sat.. Expected completion: 2 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Brett Gould 0428 778 944

Page 8 of 10

BROKEN HILL DISTRICT (Inc. Broken Hill, Tibooburra, Wilcannia and areas)

PRIMARY LOCATION: SILVER CITY HIGHWAY – HW22 Work type: Resealing Location: Tibooburra town limits Lane closures: Stop/slow traffic. Wait times up to 10 min at times. Impact: Approximate 10 Minute wait time Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Sat. Working hours: 0600 to 1800 hours Mon to Fri and 0700 to 1700 on Sat. Expected completion: 2 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Brett Gould 0428 778 944

PRIMARY LOCATION: CAMERONS CORNER – UR08 Work type: Resealing Location: 0 to 85kms West of Tibooburra Lane closures: Stop/slow traffic. Wait times up to 10 min at times. Impact: Approximate 10 Minute wait time Speed restrictions: 40, 60, 80 km/h as directed Working days: Mon to Sat. Working hours: 0600 to 1800 hours Mon to Fri and 0700 to 1700 on Sat. Expected completion: 2 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor Brett Gould 0428 778 944

PRIMARY LOCATION: SILVER CITY HIGHWAY – HW22 Work type: Sealed maintenance works Location: South of Broken Hill, near Popiltah Lake Lane closures: Nil. Impact: Nil. Speed restrictions: Nil. Working days: Mon to Fri. Working hours: 0600 to 1800 hours. Expected completion: 2 November 2018. Advice / Comments: Please obey all signs and proceed with care. Project Supervisor: Kevin Bath 0429 346 432

Page 9 of 10

Exercise caution when travelling

through worksites. Police enforce roadwork speed limits.

NEXT REPORT AVAILABLE Monday 5 November 2018