f/t >,/+i7Li/C -
DRocumentof The World Bank Public Disclosure Authorized FOR OFJICIJALUSIE ONLY
MICROFICHE COPY 1eport No. 1OO<-(;IS -ype: (SAR) ReportNo. 10071-CS GRAY, DALE/ X32692 / RI2017 / IA4EE
Public Disclosure Authorized STAFF APPRAISAL REPORT
CZECH AND SLOVAK FEDERNALREPUBLIC
POWER AND ENVIRGNNENTAL IMPROVEMENT PROJECT
FEBRUARY21, 1992 Public Disclosure Authorized Public Disclosure Authorized
Energy and Environment Operations Division Central Europe Department Europe and Central Asia Region
This document has a restricted dIsnibution aid may be a*sedby recipients only in the performance of their official duties. Its contents mnaynot otherwise be disclosed without World Bank authorization. CURRENCY EQUIVALENT Currency Unit : Koruna (Kcs) USS1.00 = 28.0 Kcs (September 1991)
WEIGHTS AND MEASURES 1 Megawatt (MW) 1,000 kcilowatts (103 kW) I Gigawatt (GW) = 1,000,000 kilowatts (106 kW) 1 Terawatt (TW) 1 billion kilowatts (109 kW) 1 Megawatt-hour (MWh) 1,000 kilowatt-hours (103 kWh) 1 Gigawatt-hour (GWh) = 1,000,000 kilowatt-hours (106 kWh) 1 Terawatt-hour (TWh) 1 billion kilowatt-hours (109 kWh) 1 Megavolt-ampere (MVA) = 103 kilovolt-Amperes (103 kVA) 1 kilocalorie (kcal) - 3,968 British Thermal Units (btu) 1 Gigacalorie (Gcal) = 1,000,000 kilocalories 1 Joule = 0.24 calories 1 Gigajoule (GJ) - 239,000 kilo-alori.es 1 Petajoule (PJ) = 1015 joule or 34,129 tons of coal equivalent 1 Terajoule (TJ) = 1012 joule or 34.1 tornsof coal equivalent 1 kilogram (kg) = 2.2 pounds (lb) 1 ton (metric ton) = 1,000 kg = 2,205 lb 1 meter (m) = 3.281 feet (ft) 1 cilometer (km) - 1,000 m = 3,281 ft 1 cubic meter (m) - 35.31 ft3
GROSS BEAT VALUES OF FUELS Hard Coal = 25 GJ/Ton = 5,975 kca!/Kg
Lignite - 12 GS/Ton = 2,868 kcal/kg Crude Oil = 11,100 kcal/kg Heavy Fuel Oil = 10,400 kcal/kg Natural Gas = 8,200 kcal/m3
ACRONYMS BCM : Billion Cubic Meters CEZ : Ceske Energeticke Zavody (Czech Power Enterprise) CHP : Combined Heat and Power (plants) CMEA : Council of Mutual Economic Assistance CPP : Czech Gas Company CSFR z Czech and Slovak Federal Republic DH : District Heating EIA : Environmental Impact Assessment ERR : Economic Rate of Return ESP : Electrostatic Precipitators FGD : Flue Gas Desulfurization FME : Federal Ministry of Economy GDP : Gross Domestic Product HOB : Heat Only Boilers ICB : International Competitive Bidding LRMC : Long-Run Marginal Cost mtpy : million tons per year SAL Structural Adjustment Loan SEP Slovensky Energeticky Podnik (Slovak Power Enterprise) SO2 Sulfur Dioxide SPP Slovak Gas Company toe tons of oil equivalent TRANSGAS : Tranzitni Plynovad (Natural Gas Transit Enterprise) UCPTE : Union for the Coordination of Production and Transmission of Electricity VUPEK : Vuzkumny Ustav Palivoeuergetickeho Komplexu (Research Engineering and Consulting Institute)
FISCAL YEAR January 1 - December 31 FOR OFFICIALUSE ONLY
CZECH AND SLOVAK FEDERAL REPUBLIC
POWER AND ENVIRONMENTAL IMPROVEMENT PROJECT
Table of ContentB
Page No.
LOAN AND PROJECT SUMMARY ...... (i)
I INTRODUCTION ...... * 1
II THE ENERGY SECTOR ...... 4 A. Background...... 4 B. Resources and Status of Development ...... 4 C. Energy Balance ...... 7 D. Energy Sector Institutions ...... 8 E. Pricing Issues .1.0...... lo
ZII THE POWER SUBSECTOR ...... 13 A. Overview ...... 13 B. Organization ...... 14 C. Regulatory Framework ...... 16 D. Existing Electric Power Facilities and Operations. . 17 E. Coal Use and Environmental Impacts. .1 F. Electricity Demand and Demand Management .22 G. Electric Power Investment Program .23 H. Electricity Pricing ...... 25 I. Rationale for Bank Involvement .26 J. Bank Activities in the Energy Sector .27
IV THE BORROWER AND THE BENEFICIARIES .28
V THF PROJECT ...... 31 A. Project Objectives and Scope ...... 31 B. Project Description .31 C. Project Cost and Financing Plan .34 D. Project Preparation .35 E. Project Implementation and Construction Schedule . . 36 F. Environmental Considerations .37 G. Procurement ...... 38 H. Disbursements ...... 39 I. Retroactive Financing .40 J. Risks .40
This report is based on the findings of missions which visited the Czech and Slovak Federal Republic in June 1991 and September/October 1991. The mission comprised Messrs. D. Gray (Task Manager), A. Roa (Power Engineer and Procurement Specialist), A. Halildin (Environmental Specialist), K. Jachoutek (Economist), T. Markus (Financial Analyst) and J. Cai (Economist). The report was issued by the Energy and Environment Division (B. Montfort, Division Chief) of the Central Europe Country Department (K. Dervis, Diiector)
This document has a restricted distribution and may be used by recipients only in the performance of their official duties. Its contents may not otherwise be disclosed without World Bank authorization. VI FINANCIALASPECTS ...... 41 A. Accounting and Auditing Framework...... 41 B. Past-FinancialPerformance ...... 41 C. Financial Projections ...... 42
VII ECONOMIC JUSTIFICATION...... 45
VIII AGREEMENTSREACHED AND RECOMMENDATION ...... 49
ANNEXES
Annex 1.1 DocumentsAvailable in the Project File Annex 2.1 Energy Balance 1990 Annex 2.2 Energy Pricing Policy Portion of SAL Annex 2.3 Energy RegulatoryPortion of SAL Annex 3.1 Planned Capacity Retirement Annex 3.2 Planr:d Installationof FGD's and Improved ESP's Annex 3.3 Emission Standardsfor Power Plants and Draft Environmental Regulations Annex 3.4 List of Power Plants Annex 3.5 Damaging Effects of Air Pollutionon Human Health and Forests Annex 3.6 ElectricitySales 1979-89 (MWh) Annex 3.7 CSFR ElectricityConsumption/Forecast 1991-2000 Annex 3.8 Power Sector InvestmentProgram Annex 3.9 Nuclear Power InvestmentProgram Annex 3.10 Average ElectricityTariffs (1989-91) Annex 3.11 ElectricityPricing and Marginal Cost Annex 3.12 Coal Prices and Costs Annex 4.1 CEZ OrganizationalChart Annex 4.2 Draft Terms of Reference for Accounting and FinancialManagement InformationSystems Study Annex 5.1 Detailed Project Cost Annex 5.2 Detailed Cost Estimate for FGD Installationat Prunerov II Annex 5.3 Project ImplementationSchedule Annex 5.4 DisbursementSchedule Annex 6.1 CEZ - Historical Income Statements,1987-1990 Annex 6.2 CEZ - HistoricalBalance Sheets, 1986-1989 Annex 6.3 Notes and Assumptionsfor FinancialProjections Annex 6.4 Table 1: CEZ - ProjectedIncome Statements,1991-1997 Table 2: CEZ - Projected Fund Flow Statement,1991-1997 Table 3: CEZ - ProjectedBalance Sheets Annex 7.1 Power Sector InvestmentOptions with PollutionReduction Annex 7.2 CEZ InvestmentProgram: InternalRate of Return
MAPS IBRD 23371R IBRD 23372R CZECH AND SLOVAK EgErAL REPUBLIC
POWE AND ENVIRONMENTAL I-MENT PROJECT
STAFF APPRAISAL REPORT
Loan and Proi2et Stumma-
BORROWER: Czech Power Enterprise - Ceske Energeticke Zavody (CEZ)
AMOUNT: US$246 million equivalent
TERMS: Fifteen years, including five years of grace.
PROJECT OBJECTIVES: The objectives of the project are to improve power plant efficiency; to reduce air pollution in northern Bohemia, and thereby improve the environment and health of the local population; to modernize the transmission system; and to facilitate interconnection of the (EZ and German power grido. These objectives will be accomplished in the context of overall reform of the energy sector. To this end, the project will: (a) reduce total consumption of pollution-causing lignite through power plant efficiency improvements; (b) curtail power plant SO2 emissions by means of flue gas desulfurization; (c) reduce dust and fly-ash pollution from power plants; (d) increase the reliability, efficiency and economy of the CEZ transmission system; and (e) assist in improving investment planning and corporate management and organization.
PROJECT DESCRIPTION: The proposed project includes: (a) installation of equipment and operational improvements at the Prunerov II power station and other large CEZ power plants to reduce lignite consumption; (b) installation of flue gas desulfurization ecqipment (FGD) at Prunerov II; (c) improvements and equipment for dust collection, i.e., electrostatic precipitators at the worst polluting CEZ power plants; (d) modernization of five 400-kV substations and construction of a short 400-kV transmission line; and (e) ccn,ulting services and staff training. ii -
BENEFITS: The overall result of the project will be a reduced lignite fuel cost in electricity generation, a large reduction of SO2, a substantial reduction of dust and fly-ash, and lower cost, more reliable power exchanges. The total reduct'.on in SO2 from the proposed installations (FGDs and efficiency improvements) will be about 218,000 - 235,000 tons/year. This reduction will not only help to restore the damaged environment in the northern Bohemia region, but also reduce the total amount of S02 in Czechoslovakia to an amount that will, in corbination with other measures, facilitate adherence to the Helsinki-Protocol and pollution reduction commitments.
Savings Zrom plant efficiency investments are lignite fuel savings of US$20 to 40 million/year from a reduction in lignite use of 1.2 to 1.9 million tons/year, and associated reduction of 28,C00 to 45,000 tons/year of SO2.
The net reduction of S02 emissions at Prunerov II is estimated at around 190,000 tons/yr (out of the total 218,000 to 235,000 tons/year of S02 reduced under the project). Based on the total SO2 emission in CSFR recorded in 1989 (2.65 million tons), the installation of FGDs covered by this project component will reduce emissions in CSFR by about 7%, and in relation to the Czech Republic by about 10%. In northern Bohemia, the most polluted region in CSFR, the proposed FGDs will reduce SO2 emissions by about 20%.
She project also includes plant retrofitting with new electrostatic precipitators (ESP) for effective dust control to improve the environment and health of the population. Where the ESPs are rehabilitated or renewed, the emission will be reduced by 75% to 90%. The transmission component will result in a lotwercost and more reliable electricity supply, and will facilitate power exchanges.
RISKS: The main risks associated with the project are: (a) deterioration of CEZ' financial condition as a result of adverse macro-economic developments caused by delays such as major changes in the internal refnrm process; and (b) implementation delays due to CEZ being a first-time borrower. It is reasonable to expect that the government authorities will continue on their present course of political and economic transformation. So far, the stabilization program has been successful with low inflation rates and sound budgetary policy, but certain federal and republic responsibilities are still being worked out. Since the project is entirely within one republic and given tha technical configuration of the system and joint dispatching operations, there are likely to be minimal affects on the project due to changes in inter- republic relationships. Also, CEZ' financial performance is believed to be adequately safeguarded through the proposed covenants. The proposed close supervision of the procurement process is likely to ensure smooth project imp.Lementation. Therefore, the above risks are considered to be manageable.
ESTIMATED PROJECT COST:
KCS Million US$ Million LC FC Total LC FC Total A. PotlutionControl Al. PrunerovII, FGD 3,836.0 3,136.0 6,972.0 137.0 112.0 249.0 A2. DustControl Installations 924.0 756.0 1,680.0 33.0 27.0 60.0 Subtotal 4,760.0 3,892.0 8,652.0 170.0 139.0 309.0 B. EfficiencyImprovement I1.Prunerov II 280.0 140.0 420.0 10.0 5.0 15.0 B2. OtherPower Stations 1,232.0 616.0 1,848.0 44.0 22.0 66.0 Subtotal 1,512.0 756.0 2,268.0 54.0 27.0 81.0 C. TransmissionNetwork Cl. Substations 407.7 642.5 1,050.2 14.6 22.9 37.5 C2. TransmissionLine u,4.1 38.1 102.1 2.3 1.4 3.7 Subtotal 471.7 680.6 1,152.3 16.9 24.3 41.2 D. Training& Consultancy 224.0 187.6 411.6 8.0 6.7 14.7 Base Cost 6,967.7 5,516.2 12,483.9 248.9 197.0 445.9 PhysicalContingencies 696,8 551.6 1,248.4 24.8 19.8 44.6 PriceContingencies * 1,058.0 818.9 1,876.9 37.8 29.2 67.0 ProjectCost 8,722.5 6,886.7 15,609.2 311.5 246.0 557.5 InterestDuring Construction (IDC) 526.4 1,730.4 2,256.8 18.8 61.8 80.6 GRANDTOTAL 9,248.9 8,617.1 17,886.0 330.3 307.8 638.1
...... ExchangeRate: 28.00KCS/US$
* It is assumedthat the exchangerate will reflectthe differentialbetween localand internationalinflation rates iv
FINANCING PLA: Local Foreign Total
IBRD 246.0 246.0 CEZ 311.5 311.5
TOTAL 311.5 246.0 557.5
ESTIMATED DISBU1iSENT: FY93 FY94 FY95 FY96 FY97
Annual 48.1 85.4 74.1 31.3 7.0 CumuLative 48.1 133.5 207.6 239.0 246.0
ECONOMIC RATE OF RETURN: Economic rate of return is greater than 14% on overall power investment; greater than 20% for plant efficiency component. POWERAND ENVIRONMENT IMPROVEME PROJECT
I. ItrJRQDUCTION
1.01 The Czech and Slovak Federal Republic (CSFR) is classified as an upper middle-income courntrywith an estimated per capita income of US$3,460 in 1989 and a population of 15.6 millio.s. CSFR has undertaken a far-reaching economic reform program to move from a rigid cen.rally planned economy to a market economy. Within a stabilization-oriented macro-economic framework, the tranformation program includes trade and exchange reform, large increases in energy prices, liberalization of most non-energy prices, a tightened monetary policy and initiation of a program for rapid privatization of large and small enterprises. The procesb has been complicated by the need to clearly define the responsibilities and authority of the federal government ana the governments of the Republics. The demise of the CMEA trade structure has resulted in much higher prices for imported oil and gas and has drastically reduced exports on many manufactured goods. Manufactured goods production has declined and GDP, which grew at an annual rate of 1.5% in the 1980e, is estimated to have declined by about 35% ini 1991 and expected to decline about 5% in 1992, but to recover thereafter.
1.02 Czechoslovakia's transformation program has two central objectives: (a) rapid transition to a market economy, and (b) restoration of economic growth towards higher standards of living. In order to achieve theae goals, stabilization and structural reform policies are being Implemented at the same time. Unification of the commercial and tourist exchange rates, and price increases for gasoline and industrial energy as well as for transport, were implemented in the second half of 1990. In September 1990, the Government adopted a radical transformation program consisting of a comprehensive set of reform measures including anti-inflationary financial and incomes policies, change of ownership of enterprises, promotion of private sector activities, price and trade liberalization, "internal convertibility" of the currenoy (unrestricted access by enterprises to foreign exchange for current account purposes), and policies of protecting the population groups most vulnerable during the transition process from undue hardship. The program was launched on a broad scale at the beginning of January 1991. It is supported by an IMF standby agreement, and a World Bank Structural Adjustment Loan (SAL) tor US$450 million.
1.03 The CSFR energy sector is character4zed by heavy dependence on domestically produced hard coal and lignite in the industrial, power and residential sectors; severe air pollution problems from use of high sulfur content hard coal and lignite; a unique position as the principal transit country between former USSR and Western Europe for natural gas pipelines but dependence on oil and gas imported from the former USSR; widespread inefficiency in energy consumption related to past misguided industrialization policies and previously subsidized energy prices; recent large increases in administratively determined energy prices whic:,have eliminated financial subsidies in the energy sector (and have resulted in most industrial prices 2-
being at or above economic cost and most residential prices being about half of economic cost); and a pucrly developed regulatory system for n>ural monopolies (natural gas, power and heat).
1.04 Overall demand for energy ls expected to decline as consumers conserve energy in response to the recent sharp increase in energy prices, and also in responae to shifting industrial structure, interfuel substitution, and ways to use fuels ..n a cleaner and more efficient manner. According to Bank and federal government demand projections, energy consumption is projected to decline until the middle of the decade and then begin to climb but, overall, energy demand is expected to be less in 2000 than in 1990. The largeet drop in demand is expected to be in coal consumption while electricity and gas demand are expected to be back near 1990 levels in 2000.
1.05 The government of CSFR has taken a number of bold stepe to reform the economy and the energy sector, sucn as the recent sharp increases in energy prices, which are being complemented by ongoing and planned regulatory and institution reforms. The role of the government and the institutional structure is in the process of being changed from that of exercising absolute control of the economy to one of oversight through a reconstituted regulatory system. This development of a new regulatory system for energy utilities is reflected in the draft federal energy policy paper. This policy paper also proposes that energy utilities be restructured and partially privatized, with the federal and republic governments retaining majority ownership. These proposed reforms of the energy utilities are scheduled to follow the first phase of ownership reform and priv,.ization of large industries planned for the first half of 1992.
1.06 Air pollution from electricity production causes severe health and environmental damage. The power se-tor relies heavily on coal-fired power plants burning low-quality high-sulphur lignite, and represents the largest polluter in CSFR in regard to SO2 and dust (fly-ash or particulate matter). The extensive use of lignite during the last 40 years has resulted in a large environmental damage, which is especially pronounced in the Northern Bohemia region, where large parts of the forests have died and health of the population is declining. Plans for reducing air pollution are based on cleaning up the stack gases from large point sources, improving the plant efficiency, and substituting less polluting fuels, such as natural gas where justified. Proposed amendments to the Air Pollution Act contain emission standards for new and old power plants were approved during 1991.
1.07 The Bank has had, and continues to have, an active role in assisting in the reform of the energy sector. This began with productive dialogue during the discussion of the Country Economic Memorandum in August 1990, followed by draft energy issues papers and policy conditionality under the SAL (on pricing, regulatory framework and least-cost investment planning and medium term environmental action plan). Energy sector issues have been evaluated in detail in the Bank's Energy Sector Review (Report No. 9768-CS, a draft of which was discussed in October 1991 and used as an input into Fe6sral and Republic Energy policy papers). Environmental issues have been evaluated in the Joint Environmental Survey (jointly completed by the Bank, EEC, US AID - 3 - and CSFR authorities - Report No. 9623-CS). Energy projects for the Slovak gas and power enterprises are currently being prepared, whichi include components for power transmission, power station retrofitting, as well as gas transmission, storage and distribution.
1.08 The Power and Environmental Improvement Project will be the first World Bank loan to be made to the CSFR energy sector and one of the largest environmental projects in Bank histccy. It will include funds for upgrading the power sector generation and delivery oystem; equipment which will substantially reduce air pollution, reaulting in improved living conditions and increased health status, specifically in northern Bohemia where the large lignite mines are located; improvement of power plant efficiency, resulting in reduced lignite consumption; improvement of the economic efficiency of the sector; and technical assistance to provide consulting services and training to facilitate sector restructuring. The proposed project will allow CEZ to keep generating expenses low and to defer investments in new generating capacity without further damaging Northern Bohemia's environment, by retrofitt.4ngexisting plants to enable them to continue using low cost lignite fuel in an environmentally safe manner. The total project cost will be $557.5 million including $249 million for the installation of flue gas desulfurization (FGD) equipment at the Prunerov II power plant; $60 million for installation -,'electrostatic precipitators (ESPs) for reduction of particulates in several power plants; $81 million for improvement of plant thermal eificiency; and $41.1 million for rehabilitation and upgrading of the transmission network. It is proposed that the World Bank provide US$246 million, which represents the foreign exchange cost, approximatel.y44% of the total rroject cost. The funds would be useC to finance portions of the cost of FGD equipment, equipment for the transmission network, and for technical assistance.
1.09 The overall environmental impact of the project is very strongly positive with reduction in S02 as well as other a'r pollutants and dust. However, the installation of the FGDs will at the same time, increase the total amount of waste by the generation of gypsum, which is not a hazardous material, will increase by about 30%. This gypsum and waste water from the FGDs can be easily and safely disposed of and are not expected to cause environmental problems. In accordance with the Operational Directive 4.00, Annex A, Environmental Assessment, this project has been ranked at the level B.
1.10 The project was prepared after a pre-appraisal mission in March 1991; an appraisal mission in June 1991; and a post-appraisal mission in September/October 1991. 4-
1. . E ENXR Y
A. gaSkgXound
2.01 The CSFR energy sector was shaped in the past by the centrally planned program which did not reflect rational economic decisions. The industrial sector is dominated by heavy industry and much of the technology used is highly energy inefficient. A major reason for this inefficiency is the fact that energy prices in the past, for induatry and household consumers, were so heavily subsidized that there was no incent4 'e to economize. As a result, the ratio of energy consumption to GDP is . ' higher than in OECD countries. The recent level of energy use in the C. was approximately 0.7 too/US$1000 of GDP, while industrial consimption was approximately 0.6 toe/US$1000 of GDP. This is more than twice the energy intensity in OECD countries. The Federal Government, which sets energy prices, has moved boldly to increase most energy prices and to eliminate the negative "turnover taxes" on energy. Energy price increases between May 1990 and October 1, 1991 have been very large, ranging from 70% (for residential electricity) to 320% (for residential district heat) and have amouuizedto increased costs to consumers (industrial and residential) of about 50 billion Kcs or about 3% of projected 1991 GDP.
B. Resourc-s and Status of Develonment
2.02 The primary source of energy in the CSFR is coal. In 1990 it provided 55% of the gross energy consumption and recoverable reserves could last more than 40 years at current production rates. However, most of the coal is low quality lignite which is highly polluting. The higher quality hard coal contains a high sulfur level which also contributes to the pollution problems. Coal consumption nas been stagnant over the past decade due to low growth of the economy and increased usu of natural gas. Petroleum consumption has declined as _he country moved to limit the petroleum products use to the transportation and chemicals sector and eliminate its use as boiler fuel. Hydroelectricity, which accounts for less than 4% of total electricity production has declined slightly and the remaining undeveloped potential is limited. Nuclear energy has grown rapidly in importance. In 1990, nuclear power supplied 28% of the electricity produced and CSFR's power sector development program includes the completion of two more large nuclear stations. Steam, produced in industrial boilers and power plants, is distributed to industrial consumers and hot water is distributed to residential consumers through pipeline networks in 70 cities.
2.03 Oil and natural gas resources are very limited. Indigenous oil production provides only about 1% of the nation's requirements and natural gas, less than 5%. Almost all of the crude oil and all natural gas imports come from the forner USSR. Prior to 1990 oil from the former USSR had been priced at well below world prices and payments were made in non-convertible rubles and countertrade. The border price for crude oil now being set at international levels. As yet, there have been no restrictions on natural gas imports. Nonetheless, the changes in the CMEA pricing and trading structure have prompted an effort to try to diversify to non-tormer USSR sourcee of both oil and gas imports.
2.04 Coal is the primary indigenous energy resource. Total production in 1990 was 116 million tons, of whickh about 81% was lignite with a heating value of 12-12.3 MJ/kg. (The ljw cost lignite used in the Prunerov plants has a slightly lower heating value of 10.5 MJ/kg.) Minable lignite resources are estimated to be approximately 3700 million tona, equivalent to 47 years requirements at current conaumption rates. Hard coal reserves total 980 million tons or 43 years' supply at current rates of use. Due to environmental and economic limitations, it is anticipated that consumption of domestically produced coal will decline markedJy and bv 2005 it will provide less than 40% of the total energy requirements. The ':oalmining induetry is characterized by a broad range ot mining conditions. There are large mines which supply Prunerov with low cost lignite. Geological conditions are very difficult at some other mines where coal is mined from very thin (20 inch) seams.
2.05 The coal sector is entering a period of transition, moving from a fully protected and regulated environment to a free market economy where performance will be measured by the sector's ability to compete with imported coal and other energy sources. The course of development will be shaped largely by market forces, which will increasingly include internalized environmental costs. But given the negative factors, such as a general stagnation in the economy, higher environmental penalties and substitution of coal by less polluting fuels, it is clear the industry is entering a period of contraction.
2.06 The CSFR consumed a total of 13.4 million tons of oil in 1990, which was almost entirely imported from the former USSR. Prospects for additional domestic production are very limited. The known potentially productive reservoirs are very deep, over 6000 meters, and will require advanced deep drilling technology which is costly and not presently available in the CSFR. Oil imports from the former USSR were reduced by about one-fourth in 1990 and further supply disruptions are possible. The current efforte are to diversify oil supply sources and to expand the delivterysystem and in-country storage. The need to diversify sources of oil as quickly as possible and to provide adequate storage has intensified because the planned increase in deliveries via the Adria pipeline has been disrupted due to political problems in Yugoslavia. Near-term options, which are under consideration, for increasing deliveries from non-former USSR sources are: (a) expansion of the Adria pipeline capacity up to S million tons/year (if disruptions in Adria supply are overcome); (b) construction of products pipelines connecting the Bratislava Slovnaft and Austrian Schwechat refineries; and (c) construction of the Ingolstadt-Litvnov/Kralupy pipeline linking Germany to Czech Republic refineries. In-country storage capacity should also be increased to a level comparable to that of Western European countries, approximately 90 days consumption. -6-
2.07 Natural gas use has grown steadily since the first pipelines from the former USSR were built in the late-1960s. CSFR location is central to the European gas system as the transit pipelines transfer 60 billion cubic meters per year from former USSR gas fields to Western Europe (which comprises about one-third of Western Europe gas imports). In 1990 total CSFR gas consunption was 13.3 billion cubic meters (BCM) of which less than 1 BCM was produced from fields in the CSFR. Because it is environmentally much more acceptable than lignite, natural gas is considered the fuel of choice for most small dispersed indUBtrial, commercial and residential uses. Expansion plans which were established prior to the political changes were based on continuation of past growth rates and it was estimated that by 2000 the total consumption would be approximately 20 BCM. Other demand growth scenarios, which are based on lower anticipated economic growth project demand in the range of 17-18 BCM in 2000. Essentially all of the gas must be imported from the former USSR in the near- and medium-term. As in the case of oil, diversification of supply sources is a priority goal, both to ensure long-term availability and to provide some bargaining leverage in dealings with the former USSR. Discussions have been held with Norwegian, Algerian, and Iranian authorities to assess the longer- term availability of natural gas. In order to meet the growing demand for natural gas as a replacement for low quality coal in industrial and residential applications, the existing supply infrastructure must be strengthened and expanded. As the residential market becomes a larger portion of the total, temperature-sensitive demand will increase and, in order to meet peak demands, storage capacity will have to be expanded.
2.08 The existing level of generating capacity in the power sub-sector appears to be adequate to meet the projected demands through the 1990s. In 1990 the peak demand was about 13,000 Mw. The installed capacity, including al3owances for retirement and conversion of some generating capacity to district heating use, was about 22,000 MW in the same year, but available capacity is much lower. The reserve will be adequate over the near term. After 1995 electricity demand may increase slowly, but under the most realistic assumptions, demand in 2000 is unlikely to exceed 1990 demand. Assuming the stagnation of electric demand, the existing plants remaining after retirement, together with those under const.rlction-- Temelin, 2000 MW and Mochovce, 1760 MW -- should be adequate to mee. demands through the late 1990s. Introduction of free market principles will affect both the demand growth and the optimum program for meeting the projected demands. The long- range sub-sector development plan has not yut been subiected to a rigorcus analysis based on the latest load forecasting and system development simulation methodologies. Over the near term, the sub-sector development program will focus on reduction of pollutants from the coal-burning stations and upgrading of the transmission and distribution systems. A leaSt-cost investment study is underway as part of the existing SAL operation. The study is being financed by the EEC with consultants beginning work in February 1992. .7-
C. _erLy_Žf.J ance
2.09 Overall, energy consumption changed very little from 1980 to 1990, but the entrgy mix shifted from liquid fuels to other energy forms. Oil consumption declined as heavy fuel oil use was substituted by coal and natural gas. Natural gas consumption ine;reasedat an average rate of approximately 4% from 1980 to 1990 as the network to additi.onalcities and towns was expanded. Total electricity consumption increased from 73 TWh in 1980 l:o 85 TWh in 1990. iluclear power increased most rapidly, growing from 6% of electricity production in 1980 to 27% in 1990. Hydroelectricity supplied a very small portion of electricity supply, less than 4%, and has remained relatively constant throughout the decade. Table 2.1 below shows a condensed version of the energy balance. A more detailed energy balance is in hanex 2.1.
Table2.1: CSFRIRn1rRy BalnLe. 1990 (PJ) Coking Total & Hard Brown Total Crude Other Total Natural Town Total Coal/Oil/Gas Coal Coal Coal Oi, Liidq LiAuid __Ga_ Las Gas Energy Production 547.4 1054.41601.8 5.8 0.0 5.6 23.5 23.5 1631.1 Imports 118.5 3.7 122.2 556.1 25.0 581.1 445.7 445.7 1149.0 Exports -68.2 -37.3 -105.5 -22.4 -22.4 -24.3 -24.3 -152.2 Inventory Adj. 1.4 6.2 7.6 20.1 20.1 27.7
Gross Conswup. 599.1 1027.0 1626.1 561.9 2.6 564.5 465.0 0.0 465.0 2655.6 Non-EnergyUse 45.6 257.0 302.6 123.5 123.5 27.2 27.2 453.3 Electric& *ieat 219.2 -739.5958.7 113.4 113.4 11Y.6 11.2 128.8 1200.9 IndustryUse (1) 199.9 22.9 222.8 87.0 87.0 154.5 76.7 231.2 541.0 Construction 0.5 1.8 2.3 3.7 3.7 0.8 0.3 1.1 7.1 AgricuLture 5.4 13.7 19.1 63,7 63.7 13.2 1.6 14.8 97.6 Transportation 1.6 2.7 4.3 106.0 106.0 1.0 0.1 1.1 111.4 Households(2) 33.6 144.1 177.7 8.4 8.4 67.0 11.5 78.5 264.6 Coffercial(3) 38.4 71.9 110.3 40.1 40,1 74.6 7.1 81.7 232.1
(1)Consumption of 1.7Pd of otherfuels not included, (2)Consumption of 10.6PJ of othersolid fuels not included. (3)Consumption of 2.7 Pi of othersolid fuels not included.
Note: Numbersmay not add in thiscondensed table, due to rounding.See Ar.nex 2.1 for the fulldetailed EnergyBalance.
Source: VUPEK,April 1991 -8-
D. Enerav Sector Institutions
2.10 Under the centralized economy of the past 40 ye,rs, a rigid institutional structure was imposed throughout the energy sector. Sector development plans were controlled by the central authority with the primary motivation being to meet pre-established )erformance or production goals. Economic criteria were only considered within the context of overall plans and because of the highly subsidized price structures in the energy sector, they have little meaning in a free market economy. As the nation moves to adapt to the market economy, the institutional structure is also in a state of flux for two reasons. First, as the country moves toward a free market economy, the planning function is being decentralized, so that in the future the enterprises which will rely less on government direction and will increasingly apply conventional economic evaluation criteria when making development plans and investment decisions. To do this, they must adorttnevw accounting methods, adjust costs to reflect international levels and eliminate subsidies. Second, the republics will assume greater authority in energy sector planning while the role of the federal government will be limited to general policy and to those issues affecting both republics. The Ministry for Economic Policy and Development of the Czech Republic will be responsible for sector activities in the republic while the Slovak Ministry of Economy will be responsible for the republic's activities. Proposals are being considered that the natural monopolies in the energy sector, i.e., electricity, natural gas, and district heating services, be subject to a regulatory system which would allow prices to eventually be set based on objective criteria and would ensure that the monopolies do not abuse their monopolistic powers. Options for delegation of authority are being considered whereby each republic would eventually have authority to approve tariffs and conditions of service for each regulated utility.
2.11 The electric sector is comprised of two generating and transmission enterprises, Ceske Energeticke Zavody (CEZ) and Slovensky Energeticky Podnik, (SEP) and 11 distribution utilities. CEZ and SEP, and some of the distribution enterprises will be reorganized as joint stock companies. Options are being considered to sell a minority portion of their shares to private owners while the remaining distribution enterprises are being planned to be operated as autonomous entities wholly owned by the republics or municipal governments.
2.12 The gas sector is primarily concerned with distribution of natural gas but approximately 400,000 customers receive "town gas", a lower heating value gas produced from natura? gas or coal. The town gas systems are being retired and will be essentially eliminated after 1995. The town gas from coal is produced by coa) enterprises but distributed by the gas enterprise. The natural gas sector is comprised of the following principal enterprises:
- The Slovak Gas Enterprise (SPP) receives natural gas from the former USSR via the Brotherhood pipeline and delivers gas to consumers in the Slovak Republic. a- 9 -
The Czech Gas Works (CPP) distributes natural gas in the Czech Republic via six regional centers.
Tranzitni Plynovod (TRANSGAS) is a CPP subsidiary (until the newly formulated plan for formation of a joint stock company is implemented) which delivers gas to CPP and operates the transit gas system from the former USSR border to the delivery points at the Austrian and German borders.
Nafta Gbely is responsible for production of natural gas and oil in the Slovak Republic and operates the Lab natural gas storage field.
2.13 At the beginning of 1990, the coal sector consisted of 21 lignite mines and 9 hard coal mines. The hard coal mines were operated by two enterprises, Ostrava-Karvina (OKD) and Kladno Mining Company (KD). (See Annex 3.12 for mine names and mine regions.) Alternatives for sector restructuring are now under consideration. The principal issue is the extent to which OKD and other companies will be broken into smaller, independent joint stock companies. Several mines, notably the metallurgical (coking) co., mines in the Ostrava region and the underground lignite mines in slovakit and ancillary operations such as construction, manufacture of mining equipment, etc., will be spun off as separate autonomous joint stock companies.
2.14 At present the activities of the oil and chemical industries are the responsibility of the Department of Oil and Chemistry in the CSFR Ministry of Economy. The division of responsibilities with the republic governments has not yet been resolved. The key issue, petroleum product pricing, is the responsibility of the Fede.Lal Price Board in the Ministry of Finance. The state oil concern, CHEMOPETROL has been dissolved with the result that the oil industry is highly fragmented. There are six refining and petrochemical operations, two regional distribution enterprises and two international trading companies. The organizational structure of the oil sub-sector is in transition. The alternatives under discussion include formation of separate joint stock companies to manage the oil pipeline system; the refining operationr; and product marketing. The management and operations of the petrochemicals sector have been very closely integrated with the petroleum sector. These are usually considered to be different types of conmercial operations and this close linkage may make it more difficult to privatize either activity.
2.15 District heating and steam energy play a significant role in the energy sector. In 1990 total consumption was 499 PJ, of which 75% was used by industry; 15% by households; and 10% for other uses. The principal source of heat energy was industry which produced 66% of the total consumed. Combined Heat and Power (CHP) plants and heat-only-boilers (HOB) produced 28%, and 6% was produced by other sources. Major district heating networks have been established in 53 cities in the Czech Republic and 17 in the Slovak Republic. Originally all HOBs connected to the local boiler houses were coal-fired. In the 1960. several HOBs were converted to gai-fired CHP systems but this policy was stopped by the end of the 1960s. Current plans are to replace worn-out units and to contvertpower plants to CHP where appropriate. - 10 -
E. Pricing_Issues
2.16 Policy and Regulation. Under the past centrally planned economy all energy prices were highly distorted when compared to the economin cost of production and delivery. Oil and gas imports from the former USSR were priced much below international levels and were paid for with goods and services valued at arbitrary prices. The lack of meaningful cost accounting methods made it impossible to calculate the true 'economic coat of delivering energy to end-users and government subsidies in the form of negative "turnover" taxes reeulted in a pricing structure which often failed to recover actual costs.
2.17 Through its aggressive program to curtail subsidies and raise moBt energy prices to a level at or near their economic cost, the government has reduced or eliminated many of the distortions in the level of average prices for the primary energy sources. As a result of the price increases adopted in 1990 and 1991, the household usere' prices are now closer to the economic cost. It is estimated that, as of October 1, 1991, current residential energy prices amount to approximately the following percentages of the economic cost: heat energy, 25-30%; lignite, 57%; natural gas, 58%; on-peak electricity, 50%. As a result of these increases, the budgetary subsidies to the utilities and enterprises which provide the energy have beehisignificantly reduced and the distortions between residential and industrial prices have been reduced, but not eliminated. AB shown in Table 2.2, the prices to industrial consumers of electricity and natural gas are higher than the economic cost while the prices to residential consumers are below the economic cost.
Table 2.2 COMPARISONOF COrStUMERPRICES ANDECONOMIC COSTS
katio of W.omina! Approximate Price to Price Oct. 1, 1991 Economic Economic Increase Fuels Prices Cost Cost 5/90-10/91
Lignite, Industrial 340 Kcs/T AZ 755 Kcs/T 45% 94% Lignite, Household 600 Kcs/T EL 1053 Kcs/T 57% 200% District Heat, Household 89 Kcs/GJ 300-400 Kcs/GJ 25-30% 320% Natural Gas, Industrial 3350 Kcs/MCM 3100 Kcs/CM 108% 164% Natural gas, Household 2218 Kcs/MCM 3809 Kcs/CM 58% 150% Electricity, Industrial 1.1-1.8 Kcs/Kwh 1.0-1.2 Kcs/Kwh 110-150% 175% Electricity, Residential 0.85 Kcs/Kwh 1.6 Kcs/Kwh 50-60% 70yb/ a/ estimated average price delivered to consumer b/ increased by 70% on October 1, 1991 - 11 -
2.18 Hard coal and lionite pricina. Retail coal prices increased in May 1990 and industrial steam coal and coking coal prices were more than doubled. Over the long term, the objective is to deregulate coal prices and coal users should be allowed to use the least-cost source of coal -- after taking into account environmental costs --- whether it is locally produced or imported. However, during the transition period some special pricing arrangements will be required. For example, the mine-mouth power plants which use lignite cannot easily switch to another fuel. The appropriate price for these consumers lies between the long-run marginal cost of production and the opportunity cost. The real prices of low quality high sulfur coals and lignite used for household heating should be raised in order to promote the shift to more environmentally acceptable fuels.
2.19 Petroleum and products pricing. Petroleum product prices are set at two points: ex-refinery and at the retail level. Prices are based on crude oil prices plus a fixed margin to cover the cost of refining and marketing. The turnover tax at the retail level has been eliminated and replaced with a fixed tax on selected products. The key pricing issues in the petroleum sub- sector will be the extent to which prices are controlled by the government and the refiners' accessibility to world markets. To have a workable system, refiners must have free access to world crude oil and product markets and competition must be established at the retail level. The government is taking first steps in this direction.
2.20 Electricitv price levels. The average industrial tariff, now about $0.04-0.06/kWh, is above the marginal cost, while the low-voltage consumers continue to pay only about 50% to 60% of their marginal cost. The differentials between the tariffs for customers at different voltage levels and in different service categories has been improved with the recent 70% increase in residential electricity tariffs (on October 1, 1991). Tariff structures of individual consumer categories include low-use and high-use tariffs; time-of-day tariffs; and heat storage tariffs which are available for off-peak (night-time) service. On the whole, this structure is suitable for reflecting cost differentials, which will be determined with greater accuracy in the forthcoming least-cost investment study (para. 2.23).
2.21 Natural gas tariffs. Natural gas tariffs are divided into wholesale (bulk) tariffs which apply to large volume consumers, such as electric power plants and industrial users; and retail tariffs which are paid by residential consumers and some small volume customers. Tariffs are not geographically differentiated and the same price is paid by wholesale or retail consumers in all parts of the CSFR. The bulk tariff is a single price for all volumes sold; while the retail tariff is a two-part structure. After the recent industrial price increases, the wholesale tariff iB higher than the retail. tariff even though the cost of service is less. During the second quarter of 1991, the border price of natural gas increased to 2600 Kcs/MCM. To compensate for this increase, the industrial tariff has been increased to 3420 Kcs/MCM. The residential tariff, which had been 890 Kcs/MCM, includes the allowance of a negative turnover tax (subsidy), was increased by 150% on May 1, 1991 but is still less than the border price. - 12 -
2.22 District heatina tariffs. Residential DH heating customers pay for the service under two tariffs: one for space heating which is based on the number of square meters which the user occupies; the second, for domestic hot water which is based on the number of occupants in the dwelling unit. Usually, neither service is metered so the total quantity used by the block of flats is determined at the secondary meter and allocated among all consumers. New metering methods are being proposed. The co-; of district heating at the point of production has been based on the type of fuel used. Theoretically the wholesale price was calculated as the average production cost plus a profit.
2.23 SAL Enerav Conditionality. The Structural Adjustment Loan (SAL) contains conditions which address key macro and sector pricing, as well as regulatory and least-cost investment planning issues, particularly for the power sub-sector. The SAL required the government to increase residential electricity prices and thus reduce the distortion between residential and industrial prices which has led to a miballocation of rescurces (as described in Annex 2.2). In fact, the federal government satisfied this SAL condition by raising residential electricity tariffs by 70%, on October 1, 1991, well ahead of second tranche release. As a condition of the second tranche release, a preliminary least-cost investment study has been prepared, and a suitable pricing structure action plan is being developed, to be implemented over the next two years. Preparatory work and progress on these studies and action plans is being achieved.
2.24 Prior to the third tranche release a Public Utilities Law will be submitted to the Parliament. The law will establish the legal predicate and procedures for economic regulations (including price setting) of enterprises which produce, transport, and distribute electric energy, natural gas, town gas and thermal (heat) energy. The law is expected to define the scope of regulation; and the structure, powers and jurisdiction of the regulating bodies (see Annex 2.3 and Chapter III (Section C) for more details on the regulatory framework). - 13 -
III. THE POWER SUB3-SE9C-R
A. Overview
3.01 Projectionsof decliningeconomic growth over the near term and introductionof energy-efficienttechnology, point to a growing excess of power generation capacity until the mid-1990o,particularly when new generatingplant capacity coming on stream at that time is taken into account. Currentlyreserve margins are adequate so the added capacity will provide an opportunityto retire at least an equivalentamount of capacity in older coal- fired units which are a primary source of air pollution (see Annex 3.1).
3.02 In 1990, 56% of the ele^tric energy war generatedwith coal and 80% of that was from lignite-fueledplants. Very little fuel oil is used for power generation,and that is being phased out as quickly as possible. Natural gas, because of its environmentalbenefits, has been proposed as a growing source of energy for future new power generationwhen needed. Uncertaintiesabout the availabilityof imports and the higher cost, relative to the lignite from the most efficientmines serving mine-mouthpower stations,may limit its use. It may be the most economic fuel in those stations already equipped for gas firing and may be the least-costchoice for inversionepisode control in some locations. Its longer-termrole is still to be defined in the least-cost investmentstudy (para. 2.23). Hydroelectric resourcesare limited but three major hydro plants (two under construction), which together will add 1400 MW of capacity,are scheduledto come into service before 2000.
3.03 The transition to a free market economy, coupled with a greatly changedperspective of environmentalobjectives, could significantlyimpact the sub-sectorinvestment program over the next decade. Any new nuclear plant investmentswill have to be shown to be the least-costoption. Some of the lignite-firedstations are obsolete and inefficient. These will be among the units replaced by the current capacity expansionprogram. But several of the mine-mouth stations have very low fuel costs. They are the stations which have been identifiedas candidatesfor installationof flue gas desulfurizationunits which will reduce the sulfur dioxide emissionsto locally acceptablelevels (see Annex 3.2).
3.04 The developmentof the sub-sectoris also likely to be affectedby recent organizationalchanges and future changes which result from proposed privatizationof some parts, or all, of the sub-sector. Prior to 1990, CEZ and SEP operated as vertically integratedmonopolies in their respective regions. They operated all the generation,transmission and distribution systems as integratednetworks. In 1990, the distributionsystems were restructuredas autonomous organizations. The first steps toward privatizationhave already been announced. It has been proposed that CEZ and SEP, and probably the distributionenterprisee at a later date, be converted to joint stock corporationswhich will offar up to 49% equity participationby the private sector. - 14 -
3.05 Historically, the operations and investment program of the power sub-sector has been closely linked to that of the district heating sub-sector. CEZ and SEP have operated a number of stations which produce both electricity and heat energy (steam and hot water) which were delivered to consumers through district heating pipeline networks.
3.06 The electricity sector is, as with all the other sectors of the economy, affected by the transformation from a centrally planned economy to a more open, market-oriented economy. Certain major issues have, as noted, yet to be clarified. For example, the governments of the two republics, which have taken on new responsibilities, are not yet sufficiently eqx.ipped for the extended tasks of sector regulation; nor is the allocation of responsibilities between the federal government and the republics fully clear. Nevertheless, these issues are being addressed and the overall electricity sector is sufficiently stable and well-defined to implement the proposed project.
3.07 Another large undertaking will be the consequence of the regulation linked to the Air Pollution Act, which become effective in 1991, in that all power plants with a capacity of more than 300 MW must install flue gas desulfurization equipment within a period of 5 years (see Annex 3.3).
B. Organization
3.08 The power sector of Czechoslovakia consists now of the following enterprises:
Czech Republic
(a) CEZ with its Power Generating Companies and the High-Voltage Transmission Network of 400 kV and 220 kV (also see para. 4.02);
(b) Eight independent Power Distribution Companies, as follows:
(i) Prague Power Works (ii) Middle-Bohemian Power Works (iii) South-Bohemian Power Works (iv) West-Bohemian Power Works (v) North-Bohemian Power Works (vi) East-Bohemian Power Works (vii) South-Moravian Power Works (viii) North-Moravian Power Works; and
(c) Research Institutes, CEZ subsidiaries. Among them is a subordinated department in Ceske Budejovice of Energovod, Prague, which has been transformed into Energetik. Ceske Budejovice. - 15 -
(d) Starting January 1, 1991, three District Heating Enterprises which used to be part of CEZ have been separated out and established as independent companies.
Slovak Re ublic
(a) SEP with its Power Generating Companies and the High-Voltage Network of 400 kV and 220 kV;
(b) Three independent Power Distributin Comp nles which also distribute district heating; and
(c) Research Institutese,SEP subsidiaries.
3.09 The latest decision is that the Czech government owns CZZ and that the Slovak government owns SEP. The responsibilities of the federal government are confined to general policy matters. These recent developments may threaten to separate the integrated system into two parts that could lead to uncoordinated development plans. To ensure orderly development of the oector, during negotiations agreement was reached that CEZ will prepare, under jerms of reference satisfactory to the Bank. and furnish to the Bank and the Guarantor not later than October 15.-1992, a draft federal least cost investment program for the period 1993 through 2003, and afford the Bank and the Guarantor a reasonable onnortunity to exchange views with the Borrower on said least cost investment_rogram.
3.10 The distribution companies will build and operate tha transmission lines operating at less than 220 kV and the distribution networks. They will purchase power from CEZ or SEP (with some limited own generation) and resell it to the end-users.
3.11 In the Czech Republic most of the district heating systems are no longer the responsibility of CEZ but are operated as separate enterprises. CEZ is responsible for operation of the CHP stations and transmission of the hot water to local distribution networks. The heat energy is sold to the local District Heating Enterprise at the secondary heat exchanger situated at the local district level. The District Heating Enterprise then resells the energy to the end-users. The regional and municipally owned enterprises are responsible for smaller heat-producing units and distribution to the end- users. In the Slovak Republic, SEP has retained operating responsibility for the district heating systems.
3.12 CEZ and SEP are responsible for construction and operation of all generation and transmission facilities at the 400-kV and 220-kV level. Both companies operate a dispatching center for ensuring the use of the most economic capacity throughout the respective republic. A country-wide dispatching center, superimposed on the republic internal dispatching centers and owned by both companies, ensures the most economic use of capacity on a nationwide basis. - 16 -
C. Reaulatorv Framework
3.13 As in other market economies, there will be a need to regulate the natural monopolies which supply electricity, natural gas and district heating service to ensure that they do not abuse their monopoly position. The Pricing Law provides a legal basis for public utility regulation but specific legislation will be required to establish the jurisdictional scope of the regulating bodies; to define their authority and responsibilities; and to provide a legal foundation for their actions. However, public utility regulatory bodies have not been set up yet. As described in para. 2.24, Annex 2.3 describes the specific SAL conditionality on regulation of public utilities te begin to address these very important issues described in this section. A study, for which the Bank helped draft the terms of reference, of the public utility regulatory framework is being carried out. The study will be financed by the EEC with consultants beginning work in December 1991.
3.14 The four primary objectives of public utility economic regulation under study are:
- All investments in facilities are needed to serve the public interests and will be "used and useful" in public service.
- All expenditures are prudently incurred and are necessary to ensure that the quality of service is maintained.
- The tariffs for each customer category are reasonable and equitable; they promote economic efficiency; and no customer is unfairly discriminated against.
- Utility service is offered to all consumers who can be economically served.
3.15 The present study is evaluating options whereby the functions of the regulatory body would include the approval of tariffs; approval of construction of facilities; and ensuring the protection of the public health and safety. The regulatory body would monitor the activities of the public utilities to ensure that environmental laws and regulations are met. A standard system of financial accounts and periodic reporting procedures should be followed by all regulated public utilities.
3.16 The legal foundation for the institutional structure is planned to be established in the Public Utilities Regulation legislation (submission to Parliament is a condition of SAL third tranche release). Sep4rate &gulatory bodies are presently being considered by the Czech Republic and the Slovak Republic, each to eventually be responsible for tariff approval and other regalatory activities within their respective republics. The draft federal energy policy (prepared in October 1991) calls for development of an independent system for regulating the suppliers of electricity at the federal, republic, and regional level. The Bank has provided guidelines for a structure which would delegate primary responsibilities for tariff approval - 17 -
and regulation to the republics while the federal government would retain responsibility for matters affecting the national interest.
D. Existing Electric Power aaciltiesand Operations
3.17 The CSFR bulk power system is serviced by the two main electric utilities, CEZ and SEP. A small fraction of the generating system belongs to industries whose plant generates for their own consumption and who Bell any surplus to the system. A detailed list of power plants in the Czech and Slovak Republics is shown in Annex 3.4.
3.18 The CEZ generating system comprises plant totalling about 13,350 MW. Of this about 10,170 MW is based on fossil fuels, 1359 MW on hydro, and 1760 MW on nuclear plants. The main coal power plants are concentrated in the North Bohemia region. The hydro component of CEZ comprises plants at Dales4.ce (450 MW), Orlin (364 MW), and other smaller stations below 150 MW each. Although the hydro capacity represents about 10% of total CEZ capacity, its energy contribution is about 2.6%, indicating that hydro plants operate mostly for peaking service. CEZ has also in operation the nuclear power plant Dukovany with 4x440 MW units. This plant, of the VVER 440, model V213, was commissioned in 1983-87. The nuclear capacity, which represents about 13% of total, generates about 21% of electric energy since it is base-loaded.
3.19 The SEP generating system consists of about 5,600 MW of installed capacity. of this, 2,200 MW is generated from fossil fuel plants, 1,655 MW from hydro, and 1,760 MW from nuclear power plants. The major fossil fuel plants are Vojany 1 and 2 and Novaky A and B. At Vojany 1, 6xllO MW units operate on coal while at Vojany 2, 6xllO MW units have been converted to gas- burning boilers. Because of the high fuel cost, these latter units are usually kept in reserve and are only turned on when inversion conditions in northern Bohemia force the operators to shut down some of the worst polluting units in that region. The hydro component comprises a large number of small plantB that make about 8.5% contribution to total generation. The nuclear component consists of the 4x440 MW units (type VVER 440) at Bohunice, that make up about 21.4% of total SEP capacity. These units are base-loaded and contribute about 40% of SEP's total generation.
3.20 In addition to CEZ and SEP, there exist about 2000 MW of industrial own generating capacity in the Czech, and about 800 MW in the Slovak Republic. Their energy contributions to the systems are about 1% in the Czech, and about 9% in the Slovak Republic.
3.21 The CEZ and SEP transmission systems comprise all transmission lines and substations above 110 kV. They are extensive systems that were developed over many years. The 400-kV level was recently introduced to the system and a conversion of the existing 220-kV level to 400/110-kV is proceeding. The country's transmission network has a length of 17,959 km and consists of 4,010 km of 400-kV lines, 2,429 km of 220-kV lines and 11,520 km of 110-kV lines. The 400-kV and 220-kV installations belong to CEZ and SEP, the 110-kV network is considered part of the distribution facilities and belongs to the Power Distribution Companies. - 18 -
3.22 Two nuclear plants are at present under construction: 2xlOOO MW at Temelin in the Czech Republic and 4x440 MW at Mochovce in Slovakia (para. 3.44). Both plants are of Soviet design. Tho Czechoslovak authorities recognize the shortcomings of the Soviet-type reactors and are taking steps to bring the two plants up to Western technology safety standards. As a first step, CEZ has commissioned a detailed safety audit of the Temelin plant by international consultants to define the improvements required to bring the plant in line with Western safety practices. (This study is to be financed under the consultancy and training portion of the proposeciloan.) The Slovak utility, SEP, is expected to carry out a similar exercise in relation to the Mochovce plant. SEP is also preparing a plan to decommission two of the Bohunice units that have been identified as having safety problems. The Czechoslovak authorities had planned earlier additional nuclear capacity: two additional 1000-MW units at Temelin and new power plants at other unidentified sites. These plants are no longer included in the integrated CSFR investment program because of the forecast slow demand growth attributable to changed economic conditions in the country, the clear perception of deficiencies in the Soviet-designed reactors, and the heightened awareness that pressing issues, such as safety upgrade.,,plant decommissioning and radioactive waste disposal: must be given higher priority. Based on the above, it i3 clear that the Czechoslovak authorities are serious about confronting and resolving the complex safety issues of their nuclear power program. In recent years, the Czechoslovak nuclear authorities have been in frequent contact with IAEA to tap the agency'B technical expertise in helping evaluate the safety needs of Temelin and other CSFR nuclear installations. A report on "Pre-operational Safety of the Nuclear Installations - Temelin Nuclear Power Plant" was issued by IAEA in November 1990. The ongoing comprehensive Temelin safety audit (para. 3.44) is in line with the recomnendations of the IAEA report. In addition, the operational safety of Dukovany nuclear power station iB being greatly enhanced through retrofitting with modern, state-of-the-art monitoring and control instrumentation imported from Germany. Moreover, twinning arrangement are being made with Electricite de France (EDF) and German and Spanish nuclear capable utilities in an effort to secure quick transfer of operational and maintenance know-how.
E. Coal Use and Environmental Impacts
3.23 The Czechoslovak electr'c power system is heavily dependent on the uae of coal for energy generation. In 1989, 12,347 MW out of a total of 19,227 MW (i.e., 64%) was steam thermal plant burning coal. In terms of generated energy, 50,452 GWh (i.e., 56%) was generated by coal. A small quantity of hard coal with a calorific value of about 24.0 GJ/ ' and an average sulfur content of 0.7% is also used in power. Overall, in 1989, about 40 million tons of lignite and about 3.0 million tons of hard coal were used in power generation.
3.24 Nearly the same amount of lignite, 36 million tons, is used for heat generation all over the country. Of total about 76 million tons, 75% is burned in the northern Bohemia region. Up to now, flue gas desulfurization (FGD) has been tried at two plants in northern Bohemia: Tisova and Tusimice. At Tisova; an ineffective (40% S02 removal rating), second-hand FGD installation - 19 - imported from Germany is in partial operation. TI. Tusimice installation is based on MgO Soviet technology and has never operated satisfactorily. In spite of repeated attempts to make it wcrk, it is unlikely that this FGD will ever be economically operated. In addition to the FGD installations proposed for Prunerov II under the project, CEZ iB retrofitting one of the five 200-MW Pocerady units with modern FGD as part of its ongoing pollution control program (see para. 3.30 and Annex 3.2). At present, therefore, nearly all of the S02, as well as the NOx generated by the lignite, is emitted tc the environment together with large amounts of fly-ash resulting from obsolete electrostatic precipitators (ESPs). The total nationwide emission of S02 is estimated to be 2.67 million tons for the year 1990, of which 1.73 is generated by power plants larger than 5 MW. The emission of NOX is estimated to 1/4 - 1/3 of the sulfur oxides and the emission of fly-ash is calculated to be around 1.15 million tons.
3.25 Following the end of the World War II, the government decided to use the indigenous energy resources, consisting mainly of lignite deposited in the northern part of North Bohemia, to meet the increasing energy demand. The excavation of available lignite increased from about 28 million tons/yr by the year 1950 to more than 100 million tons/yr by the year 1985, and has s4 'ce then dropped to about 76 million tons/yr. To reduce the transportation of the lignite, the power plants were erected close to the mines. The heavy concentration of power plants burning lignite in a very small area has resulted in an envirormentally disastrous situation, with adverse consequences on the local population's health and living conditions. The location of the lart3st S02 emission sources in CSFR (in Annex 3.5) shows the large concentration of power plants in the coal-mine basin in North Bohemia.
3.26 The large increase in the use of lignite of relatively high sulfur content (1.8-2.5%) has resulted in the highest specific emission of S02 /person in Europe, which, for Czechoslovakia, is 179 kg/person. The emission of 502 per capita in the northern Bohemia region is more than 1900 kg/person, which is more than 10 times higher than for the rest of the country. The emission of dust for the whole country is 77 kg/person and in this region 550 kg/person. The environmental impact can be summarized as follows:
- The emission of S02 was 2.67 million tons in 1990. Of this 36.1%, or 0.96 million tons, are gene-ated in northern Bohemia. Expressed as tons per km2 per year the figure, for Czechoslovakia is 22.7 aAld for northern Bohemia, 113.4.
- The emission of 1.15 million tons of dust during 1990, of which 24% or 0.28 million tons are generated ir,northern Bohemia.
- The topographical situation in the mining district in northern Bohemia creates extreme meteorological conditions; e.g., in some towns during the winter season, there is little or no wind for about 50% of the time. This, combined with strong inversion, results in very high concentrations of S02 in the air. In towns like Teplice and Litvinov, concenLrations up to 2600 pg/m3 have been recorded. In the winter of 1988, Teplice had a recorded average concentration 20 -
of over 1000 pg/m3 more than 10% of the time, a level that can cause large hoalth problem, specifically for sensitive persons.
- The effect on the population hae during the last decades resulted in an increased sickneEs and mortality in some population groups in some areas, particularly for men in their economically most productive ages. Contrary to most European countries, the mortality rate for cardio-vascular and oncological deceases has increased, specifically in the mining region. Northern Bohemia has the lowest average life expectancy in CSFR, for both men and women. It also has the highest figures for missed workdays and illnesses of the respiratory system. During inveraion conditions, the air quality becomes so toxic that sick and old people cannot survive. The concentration of S02 in the ambient air reaches, under the worst inversion conditions, lethal levels. Peak pollution during times of atmospheric inversion cause the most severe health problems. In addition to overall reduction of SO2, steps should be taken (e.g., stockpiling and use of high-quality coal) to reduce peak pollution problems. Bv December 31. 1992. CEZ aareed to preyare an action plan. includina targets. satisfactory to the Bank to deal with the remainina peak pollution prcblem. Also the action plan shall include an appropriate monitoring system: and _:EZ and che Bank will annually review (on April 1 of each year. starting April 1. 1994) the results of the monitoring system and the agreed recommendations for improvements will ba implemented.
- According to a survey organized by the U.N. Economic Commission for Europe in 1988, a total of 70.5% of the forests in Czechoslevakia are damaged, of which 5.4% re classified as "dying' and 22% as "medium damaged". The mopt zsuere damage is located in East and North Bohemia and North Moravia, where large areas have been completely deforested and the total figure for damaged, dying and dead forest is between 96-100%. The main reasons are the extremely low pH-value in the soil caused by the deposits of SO2 and the emission of fly-ash. A more detailed review of the health situation and the forest damages in the mining districts is presented in Annex 3.5, which also includes a discussion of ambient air quality in the surroundings of EPK Tusimice (including Prunerov plants).
3.27 The necessity to reduce the air pollution related to S02 and duat emiW.sons is obvious to both the power-generating companies and the environmental authorities in Czechoslovakia.
3.28 The current situat"n gives rise to great concern for the health status and the environmental ..4amagesin CSFR and particularly for northern Bohemia. Total S02 and fly-ash emissions in 1990 were about the same as recorded during 1988. See Table 3.1 belowt - 21
Table 3.1:. 990 ESTIMATED TOTAL POLLUANT EXSSIONS IN CSFR
Particula tes Tons/v6 _ Tons/lyr _i
Czech Republic 2,065,800 77.3 840 300 73.4 of which N. Bohermia 964,080 36.1 275, 071 24.0 Slovak Republic Q605,800Q _2L2.7 304,400 26.6
Total CSFR 2,671,600 100.0 1,144,700 100.0
3.29 The Czech and Slovak Federal Republic authorities are committed to reduce the emission of SO2 and fly-ash. The proposed project is urgently required and is part of a program to retire or retrofit plants in this region.
3.30 CEZ currently has an installed capacity of 10,170 MW, of which 1952 MW would be reduced by retirement of whole plants or certain boilers, and another 4,500-5,000 MW will be equipped with flue gas desulfurizatioll equipment in accordance with the program. The result of the planned program will be that about 19% of the current installed capacity will be retired and about 45-50% will be retrofitted with FGD and other environmental protection equipment. With an expected efficiency of more than 90% SO2 reduction, the program will reduce the SO2 emission from CEZ operated plants by about 50%. The total SO2 from the CEZ operated plants is estimated to be more than 1200 ktons/yr. The program will achieve a reductlon of more than 600 ktona/yr.
3.31 The Bank has reviewed this program, which needs to be confirmed through the ongoing least-cost investment study. Some plants date from the 1950s and the 1960s and will need to be closed down; it is not, therefore, worthwhile to spend large sums on environmental control for such plants. Others are relatively new and burn low-cost lignite and will definitely not be affected by the conclusions of the least-cost study. Prunerov II, the plant included in the project, is one of those plants.
3.32 The FGDs and ESPs at Prunerov 1I, part of the proposed project, will result in a reduction of 190,000 tons of S02 and about 36,000 tons of fly-ash per year. The project will also include measures to improve plant thermal efficiency at Prunerov II and other large CEZ plants to reduce consumption of lignite. Consequently, the emission of SO2 and f3y-ash will be reduced by an additional 28,000 - 45,000 tons of SO2 and around 3,000 tons of fly-ash per year. An a whole, the project will contribute with about 35-40% of the intended SO2 reduction and about 10% of the fly-ash reduction in the heavily polluted northern Bohemia region. - 22 -
F. Electricity Demand and Demand Manageient
3.33 During the ten years 1979-89, electricity demand under the command economy system grew at about 3% per year. The growth rate of small consumers, particularly households, was significantly higher, at about 4.5% per year, while large consumers such as industry, who account for the bulk of electricity consumption, increased their purchases only at about 2.5% p.a., Annex 3.6. As a consequence, by 1989 small consumers had increased their share of total final electricity consumption (excluding electricity consumers within the energy-producing sector) to about 30%, of which almost 20% was accounted for by households. Much of this vigorous growth in the household sector is attributable to the spread of night-storage heating encouraged by low tariffs. The industrial sector retains by far the largest share of electricity consumption: it amounts to about 60% of final consumption, and (together with the energy industry) to almost 70% of electricity delivered to all users.
3.34 Until 1990, industrial electricity use was determined by the output requirements of the planned economy, projected according to input- output relationships. Although the tariff structure was designed rationally to reflect different costs at different times, price was not a tool of demsand management. On the other hand, households responded to the incentive of low off-peak tariffs in the establishment of storage heating: during the 1980s, sales at the low night tariff grew at about 6% p.a. The change in household consumption patterns had a significant effect in many urban locations, and became virible in the daily system load curve by creating new peak times in previously off-peak periods such as winter nights (Annex 3.6). As a result, the load curve has lost its pronounced peaks, and the winter difference between daily minimum and maximum load is about 2,000 MW out of a 13,000 MW peak demand. Seasonality is an important demand feature, and winter demand levels lie about 2,000 MWabove summer ones: on an annual basis, therefore, there is a 4,000 MW difference between the summer minimum and the winter maximum.
3.35 The relatively flat load curve within each season makes it necessary to control the potential shifting of peak periods through more direct means than price alone. Low off-peak tariffs are now associated with remote-control switching-off of appliances such as storage heating, to be triggered at the times when more costly generating plant enters into operation. As tariffs rise over time in real terms, both demand management tools will be effective instruments to flatten tne load curve. Initial evidence in 1991 already indicates that industrial consumers are reacting to the significantly increased industrial tariff levels by shifting some of their consumption to shoulder and off-peak periods.
3.36 Projections for future demand development are based on a radical break with past growth patterns. The transformation of the economy to a market-oriented one implies a strong decline in the output of lheavy industry, and an overall GDP decrease for several years, followed by a gradual economic recovery based on a different industrial structure. Although household - 23 electricity consumption iB expected to show continued growth as residential consumers switch out of poor-quality lignite for home heating, the dominant effect of the economic slowdown and industrial decline is likely to be a slump in overall electricity aales, Annex_3.7. As the pace of the economic decline and revival is uncertain, the power utilities are assuming high and low scenarios of electricity demand development: the high scenario expects a shallow recession, with recovery beginning in 1994. In the low scenario, the recession is deeper. Total electricity consumption in 1995 is projected to still be well below the peak 1989 level, with industry showing a decline in consumption of 15-30%. After 1995, the economic recovery is expected to lead to a renewed power demand growth of about 2% p.a., resulting in a total requirement of 87-100 TWhi in the year 2000, compared to 92 TWh in 1989.
G. Electric Power Investment Proaram
3.3. Investment program scenarios for the borrower, CEZ, outlining their proposed plane in each of the years 1992-2000 are presented in Annex 3.8. Whereas the individual enterprises (CEZ, SEP and the Power Distribution Companies) prepare their investment programs independently, the Federal Ministry of Economy (FME) prepares a strategic development plan for the power sub-sector. This plan integrates the individual plans taking also into cOnsideration broader issues of the expected rate of economic growth in the country, availability of financial resources, management capabilities, and environmental requirements. A thorough optimization of the system investment program will be conducted under the ongoing least-cost investment study.
3.38 For a rational choice of the optimal system development strategy, alternative investment sequences will be carefully costed, using capital and variable costs that reflect international price levels for equipment and fuels, and compared to obtain a least-cost sequence of system investments. This sequence, calculated on a discounted cash flow basis with shadow-priced economic costs, should be consistent with (i) a realistic demand forecast, which takes into account the probable decline of energy-intensive industrial output in the CSFR and the uncertainty involved; (ii) the new pricing regime that will depress demand for electricity and heat; (iii) system operation requirements to meet loads and sales commitments reliably; and (iv) applicable new limits for emissions of pollutants.
3.39 The choice of a least-cost system development sequence for the CEZ/SEP grid will, in turn, influence the decision on the future of the steam coal mining industry, depending on the optimal fuel mix in the system. Rather than starting from a decision to phase out lignite mining (forcing a retirement of coal-fired plant), the analysis should arrive at a conclusion about lignite only after a thorough cost comparison on how to satisfy projected demand under strict environmental requirements.
3.40 In this system optimization exercise, load forecasts will be firmed up using modern methodologies. A least-cost development program which will consider all viable options, including increased end-use efficiency and combined cycle plants using imported natural gas, will be developed with up- to-date analytical tools. Use of imported natural gas for power generation as - 24 - a long-term alternative to expanding nuclear capacity would be explored on economic grounds in line with the acknowledged need for diversification of energy supplies and the need for flexible expansion options to meet uncertain demand.
3.41 The environmental improvement requirements are large, and can be met only gradually, and after examination of the economically optimal way of doing so. Although international agreements call for the reduction of S02 emissions (from the current 1.2 million tons p.a.) by 30% by 1993, even radical measures would reduce 502 output of the power syetem only to just under 1 million tons by 1995. Where economically justifiable, existing coal- fired power stations should be rehabilitated and retrofitted with flue gas desulfurization (FGD) equipment to conform with environmental protection regulations. In this regard, options such as conversion of existing boilers to gas firing and substitution of poor quality local coal with higher quality imported coal (or blended coal) should be explored and compared to the continuing use of lignite. In the case of Prunerov II (the plant selected for the project) these options were explored, and FGD retrofitting is the clear economic choice (para. 7.07). A decision to move to a high share of nuclear generation should only be taken if it is demonstrated to be the least-cost option for reducing emissions and satisfying future demand.
3.42 A related issue is the justification of expanding district heating through the conversion of existing coal-fired power plants to supply bulk heating. Further economic analysis should ascertain the economic merit of the proposed district heating as compared with an increase of natural gas use for production of heat at local boiler plants, or for direct distribution of piped gas to individual residential consumers. To the extent that additional supplies of natural gas become available from the former USSR, Western Europe, etc., this option may well result in a reduced rate of power station conversion and a lower need for additions to district heating capacity during the present decade.
3.43 The total currently planned CEZ investment in the period 1992-2000 is about Kcs 180 billion (US$6.4 billion), with the major categories of investments shown in Annex 3.8. The phasing of the investment depends on (a) the pace of demand development, and (b) the potential for exporting temporary surpluses. Both size of investment program and phasing are subject to confirmation following the ongoing least-cost investment study. Preliminary capacity balance estimates (Annex 3.8) indicate more than adequace capacity margins throughout the 1990s (although the current CEZ definition of "installed capacity" covers significantly more than actually available capacity). In energy (kWh) terms, the margin may be less comfortable. If domestic demand development will take place about midway between the two forecasting scenarios, major new capacity additions such as the Temelin nuclear plant can be delayed by several years, unless firm export contracts for the mid-1990. can be entered into. In the low-demand scenario, a delay of Temelin commissioning may postpone the need for new capacity immediately after the year 2000, thus reducing the CEZ investment expenditure 1992-2000 to about Kcs 165 billion (USS5.9 billion). - 25 -
3.44 Completion of Nuclear Plants. The completion of well advanced nuclear plants is one of the largest parts of the overall investment. Under the CEZ and SEP investment programs, two power plants, one at Temelin (2x1000 MW) and one at Mochovce (4x440 MW) are to be completed (Annex 3.9). The program is examined in terms of incremental expenditures, since the sunk cost can be ignored in economic terms in the situation of a complete re-appraisal of the program. Costs need to be re-estimated due to price and excihange rate distortions in the past, and special arrangements within CMEA. The estimated incremental costs for the Temelin plant are equivalent to a unit price of about US$900-1,000/kW, as the plant is at an advanced stage of implementation, with the first unit 60% and the second unit about 40% complete. The incremental capital cost is higher than the cost of alternative (e.g., gas- fired) capacity, but implies a total cost of only about US¢ 3.2/kWh, well below the gas option. The Mochovce plant consists of 4x440 MW units of Soviet design. Incremental cost for the four units are about Kcs 29 billion, or US$1 billion, which correspond to US5500-600/kW. The plant is at an advanced stage of construction with commissioning possible in 1992-95. A decision to complete the plant is pending. A comprehensive safety audit being carried out by CEZ will help determine the desirability to complete the Temelin plant as originally planned (see para. 3.22).
3.45 Hydro Development. The total share of hydro development represents about 10% of the overall CSFR investment proQram, and about 1-2% of the CEZ program. The plan includes the development of three major hydro plants: Dlouhe Strane, 650 Ml in 1995; Gabcikovo, 2x360 MW in 1993-94; and Zilina, 2x44 MW in 1998-99. It also foresees the development of a number of small hydro plants of a total capacity of 30 MW. The Dlouhe Strane project (600 MW) is well advanced and commissioning is expected in 1995. The Gabcikovo project has been caught in a bitter dispute with Hunaary on environmental grounds but is well advanced on the Slovak side and is likely to be completed in 1995. The remaining planned hydro projects need to be evaluated in the framework of the overall least-cost study to determine the need for this capacity.
H. Electricity Pricing
3.46 The retail electricity tariff structure is complex (see para. 4.07). While the structure of moat tariff categories reflects the costs of supply in different pricing periods, tariff levels until 1990 did not keep up with costs. Tariffs for industrial and other large consumers increased only slowly, and the tariffs for households and other small consumers remained constant in nominal terms since 1981, a decline in real terms. The tariff levels for high-voltage and low-voltage consumers were about equ&l, a feature that did not reflect the cost structure. This distortion worsened in the price adjustments of December 1990 and April 1991, as industrial tariffs were increased by 180%, but residential tariffs were left unchanged. The :.ncreases of residential tariffs in October 1991 by 70% have diminished the gap, but have not yet reversed the distortion: the new industrial tariffs of about US¢ 5/kWh now compare to residential tariffs of about US¢ 3/kwh. See Annex3.10U. - 26 -
3.47 P-aliminary estimates of the long-run marginal cost (LRMC) of electricity supply indicate that high-voltage consumers impose a marginal cost of about USt 4-5/kWh on the system, a level which has been reached by recent tariff increases. on the other hand, household and other small consumers incur an LRMC of about US¢ 6/kWh, a level about double the present tariff. Major tariff increases for umall and low-voltage consumers will be necessary to approach marginal costs even slowly. This issue is being addressed under the SAL pricing action plan (see para. 2.23). Annex 3.11 summarizes the LRMC estimates, and Annex 3.12 illustrates costs and prices of coal.
I. Rationale for Bank Involvement
3.48 The Bank's overall objectives in Czechoslovakia are to support the transformation to a market economy, increase efficiency, and improve the environment. The SAL supports these objectives, as does this first Bank investment project. The Bank's objectives in energy and environment is to introduce principles of efficiency and economy that were not used in past years under a centrally controlled economy; to reduce pollution and improve public health; to rationalize the investment program under conditions of decreasing or flat demand; to introduce financial profitability, accountability, financial autonomy, and responsibility; to raise the level of cr,ability at the management and technical levels by introducing modern methodologies and technologies; to support government privatization plans; and to diversify and increase reliability of energy supplies. This project supports these objectives, and in particular, the immediate need to rehabilitate and modernize power plants by using technologies that improve efficiency on the very poor environmental situation in northern Bohemia, which is causing Berious health problems in the local population and severe environmental degradation. Also, the transmission component of the project facilitates exchanges of electricity with neighboring countries, thereby satisfying Bank objectives by bringing higher reliability and lower cost to the interconnected system of Central Europe.
3.49 The general movement toward market oriented economiks is expected to affect the energy sector in much the same way as other areas of trade and technology exchange. Currently, the CEE countries have a significant dependence on imports of energy from the Soviet Union. While this dependency is most significant in terms of raw energy, in the form of coal, oil and gas, there is a considerable dependency upon the Soviet Union for electricity imports. This is reflected in the numerous ties, at 750,400- and 220-kV, from the southern Soviet system to Bulgaria, Czechoslovakia, Hungary, Romania, and Poland. Ties from the west, on the other hand, are limited to one HVDC tie between Austria and Czechoslovakia and several AC ties to electrically isolated areas. While limited cooperation already takes place between the CEE and Western European (UCPTE) electrical systems, the political climate now allows a more comprehensive assessment and consideration of a greater degree of interconnection along with associated benefits to all parties. The CEE countries (especially Hungary, Czechoslovakia and Poland) are in a geographically strategic position relative to an increase in electrical energy traIe between themselves, the former USSR and the western systems. Consequently, the strengthening of interconnections, specifically to the West, - 27 - could have a considsrable and positive impact on health in both the CEE countries and the Southern former USSR energy sector. This could make a significant contribution to the continuing success of the reform processes. Furthermore, the opportunities for wheeling are a potential source of foreign exchange, albeit possibly in kind. A pre-requisite of strengthened transmission ties to UCPTE is that of improved power quality and reliability in the CEE systems. This is the near-term challenge; one of modernizing the central and eastern European supply to the point where large-scale cooperation with the weBtern systems will be practicable. A comprehensive study on East- West electric power interconnection and trade has been proposed by the Bank and others under the auspices of the Central and Eastern Europe Network for Regional Energy (CEENERGY).
J. Bank Activities in the Energy ector
3.50 The Bank is in a unique position, based on experience elsewhere, to assist CSFR develop a comprehensive energy strategy. To this end, the Bank began its involvement in the energy sector in August 1990 (as described in para. 1.08) and has discussed and reviewed with the government the Bank's report on thf CSFR Energy Sector, Report No. 9768-CS (Gray Cover finalized in January 1992). Moreover, the Bank can play a catalytic role in helping CSFR integrate its energy system with those of Western Europe and in attracting private sector participation. The Czech and Slovak Federal Republic rejoined the Bretton Woods institutions in September 1990. The first operation from these institutions was the 14-month IMF standby of SDR 620 million and financing under the CCFF for SDR 484 million. A Structural Adjustment Loan of US$450 million was also approved in 1990. Energy policy conditionality, relating to energy pricing and regulatory policy, is a prominent part of the SAL. Several energy studies have been agreed upon by the government, and are planned to go ahead under grant financing. These include: (a) Comprehensive Energy Study, (b) Regulatory and Institutional Reform of Power and Gas Sub- sector, (c) Least-Cost Power Expansion Plan, and Long-Run Marginal Cost, (d) Coal Sub-sector Restructuring, and (e) Gas and Oil Storage.
3.51 This proposed project is the first energy (and first investment) project for CSFR, but it is seen as the first of a number of operations in this sector covering both the Czech and Slovak Republics. The proposed project comprises a number of high-priority investments, mainly environmental in nature, that are ready to go ahead at this time. Other investment proposals, notably projects in the gas sub-sector and for the Slovak power sector, are under preparation. These will be brought forward as soon as they are ready. The coal and petroleum sub-sect.rs may be the focus of future energy loans, but certain questions must be first resolved, regarding the implementation procedures under the Large Scale Privatization Law and feasibility studies to resolve technical, environmental and other cyuestions. - 28
IV. THB ORROWER
4.01 The Borrower for the proposed Bank loan will be Czech Power Enterprise (CEZ). The objectives, functions, organization and managemenit of the borrower are summarized below.
4.02 Before July 1, 1990 CEZ was solely responsible for the supply of public electricity throughout Czech Republic. CEZ was also responsible for supplying district heating in Prague and northern Bohemia. In addition, the CEZ corporate organization also included related research, manufacturing and construction activities. After July 1, 1990 CEZ statutory responsibilities were altered to include mainly construction and operation of power plants and 400-kV and 220-kV transmission lines and substations. Sub-transmission, distribution activities and district heating were transferred to separate independent enterprises with the exception of three co-generation power plants which continue to supply district heating.
4.03 CEZ, an independent state-owned enterprise, has wide autonomy in its operational, financial and managerial decisions. Its management is free to hire and fire personnel, to approve annual budget and investment plans, and to decide on imports and on domestic borrowing. The supervising agency of CEZ is the Department of Electricity in the Ministry of Economic and Development of the Czech Republic; while it does not interfere witn the company's day-to-day operation, it appoints the General Director. It also approves the year end accounts and, should needs arise, acts as mediator in disputes between CEZ and other energy enterprises such as distribution companies. In addition, the ministry reserves the right to approve CEZ's foreign borrowings.
4.04 By the end of 1991, CEZ staff numbered just over 31,000. If the restructuring and privatization program including the separation of CEZ's non- electric generation activities will be implemented over next 3-4 years, then the number of employees will be reduced to about 20,000. CEZ is currently managed by a General Director assisted by four Deputy Directors, one each for Generation and Transmission; Development; Economics and Trade; and Personnel and Social Development. The present organization chart of CEZ is shown in Annex 4.1. While CEZ's staff can carry out their tasks competently and efficiently in the technical field, there is a definite need for improvement in the field of corporate policy development, financial management, planning, accounting, and personnel administration (including remuneration policies). The need for improvements in these fields can be traced directly to the absence of a market economy and lack of business-oriented management during the previous decades.
4.05 Until recently, in CSFR, financial information was neither kept nor disclosed on the basis of generally accepted accounting standards; basic information derived from conceptually different accounting systems which have been in existence in the country for decades. While a substantial amount of information was collected according to the requirements of various local, state, or federal regulations, there has been less emphasis on developing a basis for management decisions; for budget preparation and control; for general performance analysis, and those of cost and profit centers; for financial planning; and for fund flow and working capital management. In addition, as accounting and financial functions are spread among various units - 29 - within CEZ, coordination botween these units need to be otrengthened within a framework of comprehensive corporate plan. Also, internal audit is limited both in scope and content, and needs considerable strengthening (also see paras. 6.01 and 6.02). Recognizing this need, the management of CEZ has agreed that an appropriate action program should be undertaken to improve the accounting and financial management system. Conceptual Terms of Reference (Annex 4.2) have been agreed upon and the work will be undertaken in three phases with the assistance of consultants acceptable to the Bank. Phase I will include a diagnostic study with the objective of identifying and recommending necessary actions for appropriate changes in the organization of accounting and management functions, and of improving the accountina and financial management information system. In Phase 1I the recommendations will be reviewed with the Bank and, for the agreed recommendations, an implementation plan will be prepared and will include the necessary training and human resource development program. Phase III will be the actual implementation of the agreed program. In particular, the work would cover: general and cost accounting; capital and operating budgets; budget control and analysis; development of coot and profit centers; short- and medium-term financial planning; revenue and expenditure forecasts; cashflow and working capital management; project evaluation; fixed assets management; and internal audit and control. To address these areas, during loan negotiations. agreement was reached that CEZ will carry out a diagnostic studv to: (a) identify, evaluate and recommend measures to strengthen the companv's financial manaaement caDabilitv including imRrovements to the Management Information System and staff training: (b) develop an action plan for the implementation of the recommended measures and present this plan not later than March 31. 1993 for Bank review and comments: and (c) thereafter, taking into account Bank comments. commence implementing the Plan. In addition. it was agreed that not later than January 1. 1993. CEZ will establish an internal audit section with oraanization. human and financial resources and terms of reference, all accentable to the Bank.
4.06 Most of the electricity that CEZ generates is sold to distribution companies and SEP on the basis of annually negotiated contracts. The annual contracts set the bulk tariffs, inter alia, on the basis of the demand, production costs, production mix, and investment needs.
4.07 Retail tariffs of electricity in CSFR are controlled by the federal government. The structure is complex and includes about 30 categories, many with multi-part characters. Tariffs generally are designed to provide signals to consumers about different costs incurred at different periods of operation, distinguishing between peak, shoulder and off-peak periods. These periods are defined in terms of time of day as well as the seaeon to coincide with the plant merit order in the load duration curve. Due both to changes in the market during the last few years and to lack of appropriate tariff actions, some of the tariff categories may not correspond to the cost differences incurred. Also, tariff levels may not have kept up with costs and increasing distortions developed between residential and industrial tariffs. The need to diminish the distortion and to update the tariff structure to bring it in line with costs is evident. A Tariff and Marginal Cout Study, together with an Action Program to implement the findings of the study, is to be undertaken under the SAL (para. 2.23). 30 -
4.08 With the current contractual arrangements, the distribution companies retain about 20%-30% of the total retail revenues and about 70%-80% is received by the generating and transmission company, CEZ. In order to safeguard the financial viability of CEZ aareement was reached drina loan neaotiationB that CEZ will: (i) furnish to the Bank. not later than November 1 each year,the terms and conditions on which it pro oses to supl.l electricity to the distribution companies and to larae consumers and which are desianed to achieve optimal utilization of CEZ's supplv fucilities: (ii) aive the Bank reasonable o=portunity to exchange views regarding the mentioned terms and conditions: and-Liii) take all the necessary measures within its nower, to conclude sunplv contracts with the distribution companies and with the large consumers. takina into account the Bank's comments. Also, during loan negotiations agreement was reached with the Federal Government that it will take all measures, as mav be required within its power to enable CEZ to carry out the project and to comply with its other obligations under the Loan Aareement. - 31 -
V. THE PROJECT
A. Proiect Obiective and ScoDe
5.01 The objectivesof the project are to improvepower plant efficiency;to reduce air pollution in northern Bohemia, and thereby improve the environmentand health of the local population;to modernize the transmissionsystem; and to facilitate interconnectionof the CEZ and German power grids. These objectiveswill be accomplishedin the context of overall reform of the energy sector. To this end, the project will: (a) reduce total consumptionof pollution-causinglignite through power plant efficiency improvements;(b) curtail power plant SO2 emissionsby means of flue gas desulfurization;(c) reduce dust and fly-ash pollution from power plants; (d) increase the reliability,efficiency, and economy of the CEZ transmission system; and te) assist in improviniginvestment planning and corporate management and organization.
B. Project Description
5.02 The proposed project includes: (a) installationof equipmentand operationalimprovements at Prunerov II power station and other large CEZ power plants to reduce lignite consumption;(b) installationof flue gas desulfurizationequipment (FGD) at Prunerov II; (c) improvementsand equipment for dust collection,i.e., electrostaticprecipitators at the worst polluting CEZ power plants; (d) modernizationof five 400-kV substationsand constructionof a short 400-kV transmissionline; and (e) consultingservices and staff training. The componentsof the project are described in more detail below (and their location is shown in Maps IBRD 23371R and 23372R):
(i) Plant EfficiencyImprovement
5.03 Through a recent study on "NecessaryMeasures for Future Mitigation of SO2 Emissions"from the power plants in CSFR, it has been establishedthat by means of small changes in operatingpractices and installationof measuring devices, it is possible to increase the plants' thermal efficiency and thereby reduce both the consumptionof lignite and the emission of SO2. CEZ has already started a program for this purpose. A calculationmade for the larger units, between 100-500 MW, shows that the lignite savings could be estimatedat 1.2 to 1.9 million tons/year.
5.04 The measures mentioned above will be supportedunder the project by additional actions that are also aimed, directly or indirectly,cr control pollution,namely: (i) the addition of equipment to measure the actual oxygen content in the flue gases by installationof measuring devices; (ii) the reduction of the air pre-heaterleakage by improved mainteranceand by applying an improved central sealing system; (iii) the sealing of boilers, flue gas ducts and the ESP casing; (iv) the training and educationof the power plant staff; (v) the installationof fine grinding and pre-drying equipment for the lignite; (vi) the optimizationof the start-up and shut-down operation;and (vii) improvementof net heat rate of the power station through reduced internalpower consumption. (The current CEZ program for environmentalimprovement does include installationof DENOX system, exchange to low-NO,burners.) The costs associatedwith items (i)-(iii)and (v)-(vii) - 32 -
are included under this subcomponent of the project. See Annex 5.3. Item (iL) will be included in subcomponent D - Training and Consulting (see Table 5.1). The project will provide special monitoring equipment and training both in CSFR and abroad for staff responsible for maintenance and operation of the power plants included in the project.
(ii) Flue Gae Desulfurization
5.05 Out of a total capacity of about 3790 MW planned by CEZ for retrofitting by 1999 (see para. 3.03) the project will finance a total of about 1050 MW at Prunerov II with state-of-the-art, high removal efficiency FGD systems (wet-limestone process). According to an independent consultant's report (referred to in para. 5.03), Prunerov II will achieve the lowest cost/ton of SO2 removal, lower than the rest of the plants in the FGD program, and is, therefore, being given the highest priority.
5.06 Prunerov II is the largest single source of SO2 emissions in CSFR. The fuel used at Prunerov II is lignite of low calorific value (10.5 GJ/ton) and high average sulfur content (1.7%). FGD retrofitting of Prunerov II is the least-cost option to meet the CSFR emission mitigation targets (para. 7.07).
5.07 At Prunerov II, five units rated 210 MW each will be retrofitted with wet limestone FGD. The net reduction of S02 emissions at Prunerov II is estimated at around 190,000 tons/yr. Based on the total S02 emission in CSFR recorded in 1990 (2.67 million tons), the installation of FGD covered by this project component will reduce emissions in CSFR by about 7%, and in relation to the Czech Republic by about 10%. In Northern Bohemia,the most polluted region in CSFR, the proposed FGD will reduce SO2 emissions by about 20%.
(iii) Dust Control
5.08 The project also includes plant retrofitting with new electrostatic precipitators (ESP) for effective dust control. This retrofitting will be done at power plants and combined heat and power (CHP) plants, which are not currently scheduled for retrofitting with FGD systems, as the FGD systems will indirectly reduce the fly-ash to an acceptable level. A total of about 1650 MW would be rehabilitated at the worst polluting units. Through this project component, dust emissions will be .-uced from 400-450 mg/Nm3 to 50-100 mg/Nm3 (milligrams per cubic meter of dry gases at normal conditions of temperature and pressure).
5.09 The project will finance ESP retrofitting of the following plants:
Pocerady Unit 1,2 and 6 3*200 MW Ledvice I 1 1*200 " Trebovice K13-14 2*161 " Prerov Kl-3 3* 82.5" Krnov " K3-5 3* 33.6' Olomouc K3-4 2* 42 " Frydec-Mistek " K1-2 2* 51 " - 33 -
(iv) Transmission System Improvement
5.10 An important part of CSFR's energy development program is strengthening of interconnections with neighboring countries to enhance electricity trade. Following the introduction of 400-kV high voltage transmission, CEZ is in the process of gradually eliminating the 220-kV network and enhancing its interconnections with neighboring countries. Given the reunification of Germany, the alternating current (AC) connection to the former East Germany will be discontinued, and a new interconnection will be established to Bavaria through an alternating current-to-direct current (AC/DC), back-to-back conversion station. The new interconnection will be the second tie-line to the UCPTE network. Along with the existing interconnection through Austria, it will facilitate further power exchanges, lower the cost of service, increase reliability of supply, and help establish a unified and competitive European market for electricity. Through this compcnent, the project will finance:
(a) construction of a 13.6 km sece.ionof 400-kV, double circuit transmission line, to loop the existing Chrast-Temelin line into the Prestice substation; and
(b) modernization of five existing substations to reduce losses. The work includes installation of new 3¢O-MVA, 400/110-kV power transformers and associate- switchgear and protection and control equipment at each of the following substations: Prestice, Sokolnice, Prosenice, Cechy Stred, ard Bezdecin.
(v) Train!.np& Consultancy
5.11 Although technical training at CEZ is extensive with a number of training schools, the level of training has not been kept abreast of the technological developments in industrialized nations. Therefore, training is needed in mode-n techniques of plant operation, maintenance, fuel eourcing, and purchasing. Training in modern finance, commercial, and planning techniques would require special emphasis owing to their long absence from CSFR under a centrally planned economy. Such training will be supported under the project. The project also includes about 35 manmontha of consultancy services to assist CEZ in carrying out a comprehensive safety audit at Temelin nuclear power station, under constructior - 34 -
C. Project_Cost and Financinc Plan
5.12 The total estimated cost, excluding initerestduring construction (IDC), is ITS $557.5 million equivalent (Kcs 15,609.2 million) as shown in Table 5.1.
TABLE5.1 CZECHOSLOV'AKIA POWERAND ENVIRONMENTALIMPROVEMENT PROJECT
SUMMARYPROJECT COST (October1591 constant prices)
KCS Mitlion USS Million --.-.-...---.-...... -...... LC FC Total LC FC Total A. PollutionControl Al. Prunerov11, FPD 3,836.0 3,136.0 6,972.0 137.0 112.0 249.0 A2. DustControl Instaltations 924.0 756.0 1,680.0 33.0 27.0 60.0 ------...... Subtotal 4,760.0 3,892.0 8,652.0 170.0 139.0 309.0 ...... - - -- ...... B. EfficiencyImprovement 81. Prunerov11 280.0 140.0 420.0 10.0 5.0 15.0 B2.Other Power Stations 1,232.0 616.0 1,848.0 44.0 22.0 66.0 ---- ...... Subtotal 1,512.0 756.0 2,268.0 54.0 27.0 81.0 ...... C. TransmissionNetwork
Cl. Substations 407.7 642.5 1,050.2 14.6 22.9 37.5 C2. TransmissionLine 64.1 38.1 102.1 2.3 1.4 3.7 ...... Subtotal 471.7 680.6 1,152.3 16.9 24.3 41.2 D...... D. Training& Consultancy 224.0 187.6 411.6 8.0 6.7 14.7 ~~~~~...... ------...... BaseCost 6,967.7 5,516.2 12,483.9 248.9 197.0 445.9 PhysicalContingencies 696.8 551.6 1,248.4 24.3 19.8 44.6 PriceContingencies * 1,058.0 818.9 1,876.9 37.8 29.2 67.0 ...... ProjectCost 8,722.5 6,886.7 15,609.2 311.5 246.0 557.5
c===r=: ======c M=_== = = z_M==_.. ==_ .. :=n_==_= InterestDuring Construction (IDC) 526.4 1,730.4 2,256.8 18.8 61.8 80.6 ...... GRANDTOTAL 9,248.9 8,617.1 17,886.0 330.3 307.8 638.1
...... ExchangeRate: 25.00KCS/USS
* It is asssumedthat theexchange rate will reficctthe differential between localand internationalinflation rates. - 35 -
5.13 Nearly 70% of project costs are for actions directly related to the environment -- reduction of S02 emissions and control of dust. US$249.0 million are for the FGD installations, yielding an estimated unit cost of about US$237 per inBtalled kW. This unit cost is reasonable for high- efficiency S02 removal installations, based on recent experiencing in CSFR and neighboring countries. The cost of ESP and transmission and substation equipment was estimated on th& basis of recent procurement of similar types of equipment in CSFR. Physical contingencies were estinated at 10%. Price contingencies are based on the assumption of a 4.9% escalation of foreign costs in 1991-95 and 3.7% thereafter. The escalation of local costs was assumed to be 34.4% in 1991, 8.8% in 1992, 6.7% in 1993, 4.4% in 1994, 3.8% in 1995, and 3.4% in 1996. Detailed project costs are given in Annex 5.1 and a break-down of the cost of the FGD installations is given in Annex 5.2.
5.14 The proposed Bank loan of USi246 million would finance 100 % of the foreign exchange cost of the project, i.e., 44% of the total cost. Interest during construction, taxes and duties, and any other local costs would be financed through CEZ internal cash generation and local loans.
Table 5.2 Project Financing Plan/1 (Us $ Millions)
Local Foreign Total
Proposed Bank Loan - 246.0 246.0 CEZ 311.5 - 311.5
Total 311.5 246.0 557.5
/1 excluding interest during construction.
5.15 The loan would be made directly to CEZ for fifteen years, including five years of grace. The loan would be guaranteed by the federal government. CEZ would bear the foreign exchange risk.
D. Proiect Prenaration
5.16 The technical and economic preparation of the various components of the project have been advanced to a satisfactory degree, although not all components are at the same level of preparation. The FGD components have been prepared by local consultants (Chemopro4ekt) and the bidding documents have been largely completed. Bidding documents are scheduled for distribution to interested bidders atarting in early 1992. In addition, an experienced consultant was recruited by the Bank to study the overall FGD program and to recommend a long-term leact-cost strategy for sulfur removal based on efficiervcyand rccnomny (occ para. 5.03). fliureport wan nubmittvd irnJuly 1991 and is part of the project file. The plants to be retrofitted with ESPn - 36 - under the project have been identified(see para. 5.09). The transmissionand substation componenthas been preparedby local consultants (Energovod)to an advanced degree of detail. Projectpreparation is, for the most part, satisfactory;no delays are anticipatedstemming from the lack of adequate project preparation.
E. Proiect Implementationand CgpLtXugjILn Schedule
5.17 The preparationof des.gn and rrocurementpackages for most project components is well advanced. An implementationschedule has been establishedfor each componentand subcomponent,according to which all componentswill be completedby the end of 1996. The schedule allows for anticipateddelays in the procurementprocess that may be experiencedowing to the novelty of Bank proceduresfor Czechoslovakauthorities. The preparation of bidding documentshas started; thus, CEZ would be in a position to sign a contract shortly after loan-signing. The FGD-technologymust be imported,and it is foreseen that foreign companieswill be responsiblefor implementation. However, the skilled and experiencedlocal manufacturingindustries will probably do all site preparationand constructionof parts of the equipment. Similarly,Czechoslovak companies have already establishedcooperation with foreign companies to produce ESPs under license. Therefore, significantlocal contributionto this component is expected. Although the pressure to install FGD systems is high, ample allowancefor the necessaryprocedures and possible delays in constructiontime has been made. Similarly,the implementation schedule for the transmissionand substationscomponents are staggeredfrom 1992 to 1996 to accommodateboth the availabilityof financialand human resources and the electric power system growth. The followingcontract packages are planned for the principalproject components:
FGDs
A single responsibilityturnkey contract covering engineering design, project management and coordination,and supply, erection and commissioning. A two-stepbidding procedure will be followed.
TransmissionLine
Supply contracts for: ;_eltowers, conductors and hardware, shied wire, and insulators.
Ubsta-tions
Supply contractsfor the five substationsin the project.
Plant Efficiency Imorovement
Supply contractsfor this componentwill be mostly plant specific and will be developedas each plant is identifiedand evaluated. - 37 -
The project is scheduledfor completionby December 31, 1996. The loan closing date is expected to be June 30,1997. A summary implementation schedule is shown in Annex 53.
5.18 The supervision"f constructionof the proposed project would be performed by CEZ through Chemoprojektand Energovod. CEZ, Chemoprojektand Energovod are adequatelystaffed with experiencedpersonnel in project constructionsupervisioni and management. The mission reviewed the capabilitiesof CEZ, Chemoprojektand Energovodand found them satisfactory.
5.19 The novelty of procuring equipmentunder Bank guidelinesposes a special challenge to CEZ and may be critical in project implementation. The technical specificationsof the proposed equipmentare well known to CEZ from past experienceand no difficultyis anticipatedin preparing the needed documentation.
F. EnvironmentalConsiderations
5.20 The project will undoubtedlybring about a substantialimprovement of the environmentin the northern Bohemia region, which is regarded as one of the most polluted regions in the world and part of the so-calledBlack Triangle. As such, the overall impact of the project will be strongly positive. In accordanceto the Bank's OperationalDirective 4.00, Annex 4, "EnvironmentalAssessment," this project has been ranked as level B, taking into account the project'spositive impact on the environment.
5.21 The total environmentalbenefit from the proposed installations would be a reductionof about 218,000 - 235,000 tons/yr of S02 and about 36,000 tons/yr of fly-ash. Dependingon the specificmeteorological conditions in the area where the power plants are located, the positive effect from this reductionwould be effectiveeven during the worst inversion incidents. Since the emissionsoccur at specific spots, the project will have considerablelocal impact and be of the greatest importancefor the improvementof the environmentand living conditions.
5.22 The additionalamount of waste generatedby the FGDs at Prunerov II is calculated to be about 30% of the current waste volume. Taking into account that the additionalwaste consistsmainly of gypsum (CaSO4), which is not regarded as hazardous, the disposal problem will be hardly affected by the proposed FGD and ESP installations. The additionalfly-ash from the more efficientESPs is estimatedat about 0.2-0.3% of the current ash amount collected,which is a minimal incrementalimpact. As a result of Decree No. 166 issued by the Czech Republic GovernmentMay 15, 1991, the ash must be disposed of from 1997 in the mined out excavatedarea of the open pit-mine DNT Nastup and in a way that the ground water resources are protected from further contaminationfronm the ash. In the meantime, the ash and gypsun will be used to stabilize existing ash-pondsby mixing the ash with the overburden. The coal-mine organization(DNT) has officiallyagreed to the disposal of a mixture of ash, waste water and gypsum to stabilize the overburdendeposits, st arting from t1ue very beg,inning of operation of the FGD syrtem nt Prnnerov II. - 38
5.23 The existing water supply is ample enough to support the installationof planned FGDs at Prunerov II without crowding out other users. The wastewater dischargefrom the FGD system is not expected to create any environmentalproblems since the transportof the ash is performed hydraulicallyand the water dischargefrom the FGD plant will be used as make- up water for the ash-transportsystem.
G. Procurement
5.24 A concertedeffort is being made to familiarizeCEZ with the Bank's procurementprocedures and Sample Bidding Documents,copies of which have been provided to CEZ. A prc-urementseminar was conductedin Prague in the week of April 8, 1991. It was well attendedby CEZ and other potential borrowers. Follow-up seminars are planned early in the procurementprocess.
5.25 All works, equipmentand materials to be financed from the Bank loan proceeds would be procured in accordancewith the Bank's "Guidelinesfor Procurementof Equipment." Goods manufacturedin Czechoslovakiaprocured under InternationalCompetitive Bidding (ICB),would receive a preference in bid evaluationof 15% of the CIF price or the prevailing custom duty applicableto non-exempt importers,whichever is less, provided they can prove that the value added to the product in Czechoslovakiaexceeds 20% of ex- factorybid price. All ICE bidding packages estimatedto cost $250,000 equivalent or more would be subject to the Bank's prior review of procurement documentation. Other contractswould be subject to ex-post review in accordancewith the guidelines. Consultingservices to be financed from the loan proceeds would be procured in accordancewith the Bank's "Guidelinesfor the Use of Consultants." All documentsrelating to procurementof consulting services would be subject to the Bank's prior review.
5.26 Procurementarrangements are slimmarizedin Table 5.3. ICB would be used for the FGD packages (US$311.3million), dust control installations (US$75.0million), transmissionline (US$4.5million), substations (US$46.9 million), and most of the contractsfor plant efficiencyimprovement (US$101.3 million). For items of a proprietarynature or where compatibilitywith installedequipment is required,direct contractingwould be applied. Internationalshopping, based on at least three price quotationsfrom at least two countries,would be used for items of small value and having an estimated value of up to US $200,000 equivalenteach, with an aggregate limit of US$10 million. Installationservices for dust control equipmentand the transmissionline and substations,and plant efficiencyimprovements would be provided locally and would not be financedby the Bank. - 39
TabLe5.3 ProcurementArr/ngements
------(USSMilt-io. ICB/2 Other Total 1. FGD Facilities 311.3 311.3 (139.8) (139.8) 2. Dust ControtInstallations 75.0 75.0 (33.7) (33.7) 3. EfficiencyImprovement 76.3 25.0 101.3 (21.3) (12.5) (33.7) 4. TransmissionLine 4.5 4.5 (1.8) (1.8) 5. Substations 46.9 46.9 (28.6) (28.6) 6. Consultingand Training 18.5 18.5 (8.4) (8.4)
Sub-Total 514.0 43.5 557.5 (Bank) (225.1) (20.9) (246.0)
...... /1 The figuresin parenthesesare the respectiveamounts which would be financedby the Benk. /2 ICB: InternationalCompetitive Bidding /3 Other: Other ProcurementArrangements (International Shopping, Negotiated Contract, Consultation, etc.)
H. Disbursements
5.27 The proceeds of the loan would finance up to 100 percent of the eligible direct foreign expenditures for goods, works, services and training, as well as up to 100 percent of the eligible ex-factory costs of locally procured goods. Disbursements would be against Statement of Expenditures for eligible expenditures under equipment and material contracts valued at US$200,000 or less. Supporting documentation for these expenditures would be retained by CEZ for at least one year after receipt by the bank of the audit reports for the year in which the last disbursement was made. The documentation would be audited by independent auditors and be made available for review by bank staff upon request. The annual audits would include a separate opinion on this disbursement made under the Special Account (SA) and Statements o4 Expenditure (SOE) procedure. All other expenditures would be fully documen'ed.
5.28 To facilitate disbursements, it is proposed that the borrower establish, maintain and operate, under terms and conditions satisfactory to the Bank, a USDollar (or any freely convertible currency) denominated SA. The amount deposited would represent about four months of projected Bank expenditures (US$16 million). The depository bank and currency of the Special Account will be communicated to the Bank for its approval before opening the account. The Special Account will be replenished on a timely basis not to exceed every four months or when the balance of the SA is half the initial - 40 - deposit, whichever occurs first. Documentation for replenishment of the SA would follow the same procedure as in para. 5.27. In addition, monthly bank statements would accompany replenishment requests. The minimum size replenishment request acceptable to the Bank will be about 10 percent of the initial deposit. Modalities concerning the use of SOEs and SAB were agreed to at negotiations.
5.29 A detailed disbursements schedule is provided in Annex 5.4. The Bank's disbursement profiles do not include FGD projects, and disbursement experience with CSFR is limited.
I. Retroactive Financing
5.30 Up to US$0.750 million of the loan proceeds would be disbursed for retroactive financing of the Temelin Nuclear Power Plant Audit Study. Work on the study started in July 1991 and is being carried out by CEZ with the help of foreign consultants. This provision will allow CEZ to make disbursements for the study and apply for reimbursement as soon as the loan becomes effective.
J. Risks
5.31 The main risks associated with the project are: (a) deterioration of CEZ' financial condition as a result of adverse macro-economic developments caused by delays such as major changes in the internal reform process; and (b) implementation delays due to CEZ being a first-time borrower. It is reasonable to expect that the government authorities will continue on their present course of political and economic transformation. So far, the stabilization program has been successful with low inflation rates and sound budgetary policy, but certain federal and republic responsibilities are still being worked out. Since the project is entirely within one republic and given the technical configuration of the electro power system and joint dispatching operations, there are likely to be minimal effects on the project due to changes in inter-republic relationships. Also, CEZ' financial performance is believed to be adequately safeguarded through the proposed covenants (para. 8.01). The proposed close supervision of the procurement process is likely to ensure smooth project implementation. Therefore, the above risks are considered to be manageable. - 41 -
VI. FEIANCIALLASECTS
A. Accountina and Auditina Framework
6.01 Due to the characteristicsof the centrallyplanned economic system, in the past, accounting in Czechoslovakiadiffered significantlyfrom internationallyaccepted norms. By and large, accountingpractices havs aimed more at external reporting for statisticaland regulatorypurposes rather than on providing financialinformation for decision-making,which is required from the management of commercially-orientedenterprises. Consequentlymanagers and staff of the various enterpriseswere not adequatelytrained and experiencedin generally accepted accountingmethods and, more important,in financialmanagement. Internal auditing was more of a verificationprocess, restrictedto checking the use of approvedbudgets and complianceswith regulations. Financial and managementaudits by outside, independent auditors,the type found in most of the market economies,did not exist. Even the verificationof complianceswith regulatoryrequirements, usually was carried out by "peer" audit type of process or by special investigations carried out by appointeesof the Ministry of Finance or other line ministries.
6.02 Both the federal and the state governmentshave recognizedthat internationalstandards in accountingand auditing legislations,institutions and practices are vital for meeting the objectivesof the country'seconomic reform. Gradual improvementsare being introducedthrough establishing compulsoryaudit requirements. Parallel with this, basicallyto support the government'sprivatization program, the companiesare being gradually requestedto and trained to disclose financialinformation by use of generally accepted accountingprinciples. The balance sheets, income statementsand other financialreports of a growing number of companiesare now based on the generally accepted accountingprinciples. Financial informationis increasinglybeing adapted to Western practiceswith the aim of improving commercial control, betteringcommercial performance, and increasing usefulnese for outside investorsas well as for internalmanagement. Also, the increasingnumber of accountingfirms of internationalrepute, which are preaentlyopening offices in the countrywith trained accountantsand providing on-the-jobtraining to local professionals,are also instrumentalin the introductionof internationallyaccepted accounting systems.
B. Pe-t FinancialPerformance
6.03 During the last two years, drastic organizationalchanges were introducedin the power sector,re-grouping the production,transmission and distributionfunctions, and changing the hierarchial-relationsof the various entities considerably. one of the effects of the changes was that the enterprises'activity profiles were altered, largely destroying the possibilityof historic comparisonsof physical institutional,or financial performances. This, combined with the frequent changes in evolutionin the accountingpractices, makes it extremelydifficult, if not impossible,to reconstructhistorical financial statementsof the power enterprisestor meaningful comparisonsor as basis for projections. Even if this could be done, the usefulnessof such informationfor analyzingcurrent and future performanceswould be substantiallymitigated by the fact that the entire centrallyplanned economy of the country is changing to that of a market - 42 - economy. The consequent structural changes will have drastLc impact, for example, on the demand for energy, rendering the historical data for projections largely meaningless.
6.04 Due to the organizational and structural changes in the economy referred to above, the pre-1991 financial information has little relevance for developing an analysis for future financial performance or for providing direct comparisons. Nevertheless, an overview of the pre-1991 financial situation is presented in the following paragraph, details are in Annexes 6.1 and 6.2.
6.05 Historically, CEZ was the largest electricity supplier in the country. Electricity oaleB during the last three years were about 52.6 GWh per annum, providing over 90% of CEZ's operating revenues. Between 1987 and 1990, the company's operating revenues increased by 23% from 24.5 billion KcB to 30.2 billion Kcs; while during the same period, operating expenses increased by 32% from 19 billion KCB in 1987 to 25 billion Kcs in 1990. Between 1987 and 1990, annual net operating incomes varied between 5.0 to 5.7 billion Kcs and CEZ' annual profits (after income tax) were between 1.1 to 1.7 billion Kcs, representing about 5 to 7% of the total revenues. Historically, the borrowings of CEZ were modest; the company did not inherit any substantial long-term financial debt from earlier years. The debt/equity ratios, between 1987 and 1990 were around 20:80; the sizeable investment programs were largely financed from internally generated funds and capital contributions. However, the reported operating results are somewhat misleading. Since 1962, the fixed assets of CEZ have not been revalued on an appropriate techno/commercial basis. Consequently, the asset values in the balance sheets are non-representative and the annual depreciation costs charged against the operating revenues are too low to permit the companies to accumulate sufficient funds for replacing the assets at the end of their useful life. Therefore, durina loan neaotiations, aareement was reached with CEZ that the company's fixed assets will be revalued by June 30. 1994 and that the revaluation will be in accordance with methods satisfactory to the Bank.
C. Financial Projections
6.06 One of the objectives of the project is to safeguard the financial stability of CEZ while ensuring appropriate power-generating capacity. In the past, the cost of investment programs and inflationary or real cost increases were not necessarily concurrent with appropriate adjustments in retail and bulk tariffs. The lack of cost recovery often led to undesirable reliance on government funds in the forms of operational subsidies or non-economical investment support. Any undesirable reliance on government funds should be avoided in the future by assuring adequate operating margins and cash generating capacity for CEZ. The financial targets (para. 6.10) aim to ensure this. - 43 -
6.07 Based upon the projected power generation, transmission and distribution levels for the next 7 years, financial forecasts were prepared in constant (1991) values. The projections reflect future operations including those associated with the proposed project as well as with other action plans, investment programs, and renewals, all aiming at capacity and efficiency improvements. In order to assess the extent of fund generation and the various actions that may be needed to ensure the financial stability of the company, the projected revenues are based on October 1991 tariffs plus future adjustments that the government is preparing to introduce in 1993. Costs, while varying with the power generating mix and with the level of projected supply, are also based on 1991 values. The sensitivity of the forecast performance to changes in costs and revenues have been tested (para. 6.11). A summary of the forecast assumptions is in Annex 6.3.
6.08 Between 1992 and 1998 the operating revenues of CEZ are expected to grow by some 31% from 49 billion Kcs to 64 billion Kcs. The bulk of the revenues would derive from supplying electricity: 93% of it to the distribution companies, 3% to SEP, the Slovakian Power Company, about 1% to large industrial and commercial customers, and about 3% for export. The importance of the sale of heat will remain constant, between 3%-4% of total operating revenues during the next seven years.
6.09 Operating expenses are expected to increase by 46% or 12.4 billion Kcs between 1992 and 1998. The largest single cost item will remain the cost of fuel, representing some 39% of the 1998 operating costs. Depreciation, while increasing from 13% of the 1992 operatinigcosts to 21% in 1998, iB Still considered to be too low as fixed assets have not been revalued since 1962. Due to its fairly modest past borrowings the company's interest payments will remain relatively low, representing no more than 12% of the 1998 net income. Corporate tax payments are forecasted at 56% of the net operating income or about 18% of the operating revenues. Taking into account both the operating and non-operating revenues and expenses, taxes and other obligatory payments, CEZ, during the forecast period will have regular net profits in the order of 8 to 11 billion KCB. As for its liquidity, between 1992 and 1998, CEZ is expected to generate regularly from its operation funds at a level of about 50% of its total revenues or on the average, about 60% of its investment requirements. Detailed projected financial statements are shown in Annex 6.4.
6.10 From the point of view of operation, the forecast profitability is considered satisfactory. Also on account of the proposed project and CEZ's investment program, the forecasted (internal) cash generation is sufficient. Nevertheless, to ensure the timely availability of funds and to provide a cushion for possible delays in future revenue adjustments to offset cost increases and to ensure the company's continued financial stability, durinq negotiations, aareement was reached that CEZ will take all steps necessary to maintain (i) annual ratios of cash operating costs to operating revenues not more than 0.6 from 1992: (ii) from 1992. internally Qenerated annual cash surpluses not less than 40% of the (3 vears movina averaael canital expenditure incurred and : (iii) debt service coverace (internally aenerated cash surpluses in relation to servicino lona term borrowina) not lower than - 44 -
.0 in 1992 through 1994. 3.5 in 1995 and 2.2 in 1996 and thereafter. The progress towards achievina the annual taraets mentioned (i) and (ii) above will be monitored on a semi-annual basis and if it ap eared that using a combination of actual and prolected data the achievement of the annual taroets would lag, CEZ would immediatelv take all recessarv remedial actions to ensure achievement of the annual targets. I addition. agreement was reached that CEZ will forward to the Bank each year, not later than 5 months after the end of its financial year. annual financial statements audited by independent auditors acceptable to the Bank together with the auditor's report on. inter alia. la) the financial statements: (b) the operation of all accounts including the Special Account and Statements of Expenditure (SOEs): and (c) the eligibility of withdrawals made on the basis of SOEs for reimbursement by the Bank. Also. aoreement was reached that CEZ will forward to the Bank every year, by March 31. its investment program together with the financing plan covering the next five years.
6.11 The major financial risk that could adversely affect CEZ' capability to support the proposed project and maintain its financial viability could be adverse macro-economic conditions. For example, if due to economic recessions the distribution companies would have difficulties in collecting revenues from their customers and therefore, in turn, to pay CEZ in a timely manner for the electricity purchased, or if due to inflation the real values of the contractual bulk tariffs would erode or adjustments to maintain the revenue levels in real terms would be delayed and/or be insufficient to match cost increases, CEZ' financial strength would be eroded. For example, a 10% increase in cash operating costs would reduce annual profits by about 7%. To offset such a negative impact, revenues would have to be increased by about 5%. Similarly, if revenues from electricity were to be about 10% lower than forecasted, without commensurate cost reductions, profits would be reduced by about 20%. - 45 -
VII. ECONOMIC JUSTIFICATION
7.01 All project components are justified as the lowest cost option to meet the required objectives. The Prunerov II plant will be utilized ae an integral part of CEZ base-load generation and will be required under all foreseeable demand scenarios. None of the project components is an investment in expansion of system generation. Moreover, the preliminary CEZ overall investment program, which includes proposed investments under the project, yields an overall internal rate of return of 13% to 17%, under low and high demand scenarios, respectively. A consultant's report "Necessary Measures for Future Mitigation of SO2 Emissions," July 1991, confirmed the selection of Prunerov II and benefits of plant efficiency improvements.
7.02 Desulfurization and Dust Control Investments. As described in Chapter III, the environmental conditions in northern Bohemia are very poor, resulting in severe impact on the local population's health and expected life span, causing severe degradation of forests, acidification of water bodies and streams, and economic losses to agriculture. It is clear that some measures must be taken to improve the existing conditions quickly. Air pollution in Notthern Bohemia is a localized problem caused mainly by the large concentration of power plants burning local, low cost, high sulfur lignite. Least-cost analysis demonstrates that retrofitting with FGDs at Prunerov II is the lowest cost, most practical and timely solution as alternative options are clearly more expensive, as described in the following paragraphs.
7.03 The available options to achieve an externally mandated objective of emission reductions while maintaining power supply in line with projected demand are: (i) shutting down of a number of heavily polluting plants and replacing the supply by electricity imports into the CEZ system; (ii) switching the operation of the existing boilers to gas, a cleaner fuel; (iii) switching to low-sulfur imported coal for at least the periods of severe atmospheric inversion conditions; and (iv) retrofitting suitable plants with flue-gas desulfurization equipment. Annex 7.1 summarizes the comparative costs of all the system options.
7.04 Option (i) is already being partially implemented to alleviate atmospheric pollution during the worst atmospheric inversions, utilizing the gas-fired Vojany plant in eastern Slovakia to make up the shortfall. However, to go further and shut down major facilities immediately would deprive the system of needed capacity that could not be removed without decreasing the reliability or service and increasing the imports of electricity that are estimated to be more costly (close to US¢ 5/kWh compared to about US¢ 4- 4.6/kWh for lignite in general, including the cost of environmental safeguards and about US¢ 2.8-3.8/kWh at Prunerov II). The new CEZ nuclear capacity, now scheduled to come on-line gradually in the years 1995-1998 at a cost of about US¢ 3.2/kWh, will enable the retirement of some old, polluting units that are not scheduled for retrofitting.
7.05 Option (ii), i.e., switching to gas, would entail shutting the boilers for a period necessary for retrofitting. This would incur Additional capital cost for the boiler modifications and additional safety facilities, and would depend on adequate oupplies of gas. These would depend, in turn, on the construction of new transmission facilities and on secure, long-term - 46 - contracts for the supply of gas. The preliminary analysiS indicates that the economic incremental cost of continued generation from lignite including FGD retrofitting at about ¢4.0-4.6/kWh iB well below the incremental supply cost from new gas-based combined cycle plant at similar load factors (¢6-8/kWh) and somewhat below tl.e cost range of supply from converted plants. In addition, the gas-based cost does not include gas transmission investments: the lignite/FGD option appears clearly preferable at this time.
7.06 Option (iii) must depend on the availability of imported coal with a low sulfur content. Assuming that it would be possible to obtain coal with a sulfur content below 1%, this option will still require the installation of FGD equipment to meet the target of 400 mg/Nm3 dry gas as an emission level. (Without FGD, the use of available low sulfur coal ^would result in emissions of > 2000 mg/m3). In addition, provisions would have to be made for transporting large quantities of coal to the power plants now burning lignite from nearby mines via dedicated transportation systems. The cost of generation based on imported low-sulfur coal at about 44.1-5.2/kWh, plus the necessary transport investments, would be higher than the cost of lignite including the investment cost after FGD retrofitting.
7.07 In conclusion, the FGD retrofitting of 1,050 MW lignite-fired capacity at Prunerov II (at about US$240/kW) is the least-cost, practical, and timely solution to the pressing need for quick improvement to air quality conditions in that region and a major step in a program of reducing air pollution. The present value of investment and recurrent CostB of the retrofit is significantly lower than that of the import alternative, even at a power import price lower than that currently available from the former USSR. By the same token, it is lower in cost than the options of using low-sulfur coal, or of converting to natural gas. As the LRMC of lignite supply to Prunerov lies well below the weighted average LRMC of lignite in northern Bohemian mines, the incremental unit cost of maintaining generation of Prunerov after retrofitting is only about US¢ 2.8-3.8/kWh (,Anpex7.1). Thus, this solution takes advantage of the low cost domestic lignite produced from mines adjacent to the Prunerov plant.
7.08 The project will retrofit several power plants with ESPB for effective dust control (para. 5.09). The reduction in dust emission will be 75% to 90% (see para. 5.08) which iB clearly justified to improve health and improve the environment. Annex 3.5 documents tne severe health problems from dust, which will be improved following installation of ESPs.
7.09 Plant Efficiency Improvements. Simple cust benefit calculations demonstrate that investments of US$81 million for plant efficiency improvements would achieve lignite savings of 1.2 to 1.9 million tons/year (para. 5.03), which is equal to about US$20 to 40 million/year in fuel cost savings. This results in internal rates of return greater tnan 20% for this component. - 47 -
7.10 Transmission and Distribution. The project components for transmission and distribution constitute needed extensions and reinforcements to an existing system that, in ivostcases, allows little flexibility of choice. The configuration of the existing system requires the addition of transformer stations and high-voltage transmission and subtransmission lines to increase system reliability and flexibility for optimal dispatch, and to reconfigure the transmission network for new capacity location and links to Western Europe.
7.11 A CEZ least-cost analysis of the optimal high-voltage transmission investment strategy has established that it is more advantageous to replace the aging 220-kV system by direct transformation from 400-kV to 110-kV. Assuming the same projected system load for the alternative strategies of (i) reinforcement and rehabilitation of the 220-kV system, and (ii) replacement of the 220-Kv system by 400/lln-kV, all demand scenarios yield a lower present value for the replacement alternative. The substation and transmission line components of the proposed project are part of this strategy.
7.12 Internal Rate of Return on Preliminary CEZ Investment Program. Given the need for retaining retrofitted thermal capac;.ty,the preliminary 10- year investment program of CEZ for 1991-2000 was evaluated to estimate the internal rate of return on the overall investment program.
7.13 Investment expenditures, operating Costs, and fuel costs are expressed in terms of international costs or border price equivalents. Distorted domeatic cost figures have been re-estimated to approximate international cost levels, while maintaining the real cost differentials such as labor costs. Benefits are defined as (i) the sales to consumers that are made possible b; replacing or rehabilitating old generating capacity, by retrofitting remaining lignite capacity with FGD, and by maintaining transmission and distribution capacity, and (ii) net fuel savings from the capacity replacement and from the replacement of heat-only boilers by repowered combined heat and power facilities. Essentially, new nuclear capacity now in an advanced state of implementation is seen as replacing old nuclear and lignite-fired units that are being retired (see para. 3.44 and Annex 3.9). The remaining thermal units are assumed as being rehabilitated, converted to CHP, and retrofitted with flue gas desulfurization, if justified.
7.14 The individual components of the proposed project are integral parto of the larger power sector investment program. The CEZ program, in its preliminary optimized form as evaluated above (para. 3.43, base case investment scenario), hae an internal rate of return of about 14%, based on tariff levels as proxies for program benefits (_nex 7.2). Sales to consumero are valued at the 1992 tariff levels averaging about KCs 1.34/kWh (US04.8/kWh). The preliminary program, relyii.gon retirement of old thermal plant, retrofitting remaining thermal plant with environmental safeguards, conversions to combined heat and power operations, and completing the Temelin nuclear plant in the mid-1990s, appears sound. In addition, the analysis indicates that tariff levels are adequate to re+Covci2 .n :ciiiit.ai ivllntVdwent in the 1990s. If the high-investment scenario is imblmnbA, hut dcitnnd - 48 -
development unexpectedly follows the low demand scenario (see para. 3.36), the overinvestment in new and rehabilitated capacity during the early years depresses the internal rate of return of the program to about 13%. The risk of overinvestment, therefore, is not great enough to render the overall program infeasible. If a pronounced and sustained low-demand scenario would become likely, the CEZ strategy would be to delay some of the lumpy investment packages, such as the completion of new nuclear capacity. A delay of the investment in Temelin completion, either for financial reason6 or as reaction to slower demand growth, would increase the IRR to about 15-17% (Annex 7.2). In either case, however, there is no question that the retrofitted Prunero, II plant would be retained in the future. The components of the proposed project appear in all scenarios as parts of the optimized system investment program. The agreed leapt-cost investment study will form the basis for a firm optimized long-term investment program. - 49 -
VIII. AGREEMENTS REACHED AND RECOMMENDATION
8.01 During negotiations the following agreements were reacled:
(i) with the Federal Government that it:
will take all measures, as may be required within its power, to enable CEZ to carry out the project and to comply with its obligations under the Loan Agreement (para 4.08);
(ii) with CEZ that it:
(a) will prepare, under terms of reference satisfactory to the Bank, anid furnieh to the Bank and the Guarantor not later than October 15, 1992, a draft federal least cost investrmentprogram for the period 1993 through 2003; and afford the Bank and the Guarantor a reasonable opportunity Xo exchange views with the Borrower on said least cost investment program (para. 3.09);
(b) will prepare an action plan satisfactory to the Bank, by December 31, 1992, to deal with the remaining peak pollution problem. The action plan shall incltudean appropriate monitoring system. CEZ and the Bank will annually review by April 1 of each year, starting from April 1, 1994, the results of the monitoring system and the agreed recommendations for improvements will be implemented (para. 3.26);
(c) will carry out a diagnostic study to: identify, evaluate and recommend measures to strengthen the Company'B financial management capability; develop an action plan for implementation of the recommended measures and preaent thiB plan not later than March 31, 1993 for Bank review and comments; and thereafter taking into account the Bank's comments commence implementing the plan (para 4.05);
(d) will establish by January 1, 1993, an Internal Audit Section with organization resources and terms of reference all acceptable to the Bank (para 4.05);
(e) will furnish to the Bank by November 1 each year the proposed terms and conditions designed to achieve optimal utilization of CEZ's supply facilities for supplying electricity to distribution companies and large consumers; give the opportunity to the Bank to exchange views regard3ng these termm and conditions; and tamk the necessary measures within its power to conclude the supply contracts taking into account the Bank's comments (para 4.08); - 50 -
(f) will revalue CEZ's fixed assets by June 30, 1994 (para 6.05);
(g) will take all steps necessary to maintain annual ratios of cash operating costs to operating revenues not more than 0.6 after 1992; internally generate annual cash surpluses of not less than 40% of the capital expenditures after 1992; debt service coverage not lower than 5.0 in 1992 through 1994, 3.5 in 1995 and 2.2 in 1996 and thereafter (para 6.10);
(h) will forward to the Bank each year, not later than five months after the end of the financial year, annual financial statements audited by independent auditors (para. 6.10); and
(i) will forward to the Bank for review by March 31 each year the investment program along with the financial plan covering the next five years (para. 6.10).
8.02 With the above agreements, the project would constitute a suitable basis for a Bank loan of US$246 million equivalent to CEZ, under terms and conditions applicable for CSFR, with the guarantee of the Czech and Slovak Federal Republic. - 51 -
Annex 1.1 Page 1 of 2
CZECH AND SLOVAK FEDERAL,REPUBLIC
POWER AND ENVIRONMENTALTMPROVEMENT_PROJECT
Documents Available in the Project File
1. CzechoslovakElectric Power System and East-West Interconnection, February 1991.
2. CSFR Study of Nuclear and Coal-firedExperience and ProjectedCosts of ElectricityGeneration, May 1990.
3 Report on Flue Gas DesulfurizationProgram, January 1991.
4. Scenarios for Demand Forecasts,January, 1991.
5. Proposal for Short-TermSimulation of the CEZ GenerationSystem, November, 1990.
6. Brochures of CEZ Power Plants.
7. StatisticalTables for CEZ and SEP for the year 1980-1990.
8. Report on the Instrumentationand Control of the Tenelin Nuclear Power Plant. 1UV, January, 1991.
9. The Environinent:in Czechoslovakia,Dcpartment of the EnvironmentState Commission for ScieniceTechnology anled Investments, Prague, lMay3.990.
10. Report onithe InstruLientation and Conitrol of the TeimelinNuclear Power Plant. Colenco, January, 1991.
11. Descriptiull of the Bollunicu Nuleaclr 'olwer llnillt.
12. Clharter of the Czecho!;lovak Atomic Energy Comnmi5;!Jionl.
13. Preoperational Safety of the Nuiclear Installations - Temelin Nuclear Power Plantt. IAEA November 1990.
1/4. Necessary Measures for Future Mitigation of S02 Emissionls in CzechoslovakiA, STYAG AG, Essen, Germany, Jul.y 1991.
15. F'sIh111t\ Stt'd' trpnrrni . - 52 -
Annex 1.1 Page 2 of 2
16. Project Cost Estimate and ConstructionSchedule TransmissionLines and Substations.
17. FeasibilityStudy on Czech TransmissionGrid PerformanceWithin Next Ten Years, CEZ, September1991.
18. About the Intended Project in the CSFR 420-kV Power TransmissionSystem, CEZ/Energovod,September 26, 1991
19. Study on Power Plants EPF Tusimice Influenceon S02 and Fly-ash Emissions in the Region. Energy Project, Prague,July 1991.
20. Study of Justificationusing FGD units at Power Plants in the North Bohemia - Part 1 Fuel Research Institute,Prague, July 1991.
21. Air Pollutionin Northern Bohemia, Fuel Research Institute,Usti n.l., April 1991.
22. The Report on the EnvironmentStatus and its Impact on the Health Status of Teplied District Inhabitants,Ebrforum and In&:tpendentExperts Commission,Teplice, January 1990.
23. Environmentand Health in Czeclhoslovakia,Department of Health Care and Epidemorlogy,Vancouver, November 1990. CZECH AND SLOVAK ._JERAL REPUBLIC POWERAND ENVIRONMENTALIMPROVEMENT PROJECT
ENERGYBALANCE - YEAR 1990 UNIT:PJ
CRUDE NATURALHEAT& ELECTRI TOTAL ENERGY HARDCOAL UGNIE OIL GASOUNEDIESEL FUELOIL GAS STEAM OIlY i Notes (1) (2) (3) (4)
PRODUCnON 547.4 1096.1 5.9 23.5 11.5 104.0 1788.4 630A # IMPORTS l18.5 3.7 556.1 8.7 8.5 7.8 445.7 0.0 86.4 1235.4 430A -EXPORTS -68.2 -37.3 -0.7 -11.6 -10.1 -24.3 0.0 -41.9 -194.1 -7f STOCKCHANGES 1.4 6.2 20.1 0.0 0.0 27.7 1O
NETTO TRANSFORMATION 599.1 1068.7 562.0 8.0 -3.1 -2.3 465.0 11.5 148.5 2857.4 1OO
ENCA-Y R . A
ELECTRCITY AND HEAT -219.2 -764.6 -113.4 -79.0 503.0 165.0 -508.2 NON-ENERGYUSES -123.5 -11.2 -3.7 -138.4 u TRANSFORMATIONINDUSTRY -57.0 -28.6 -562.0 67.7 163.7 310.0 4.4 -101.8 LOSSES -37.0 -8.6 -11.8 -35.0 -92.4 UNACCOUNTEDDIFFERENCE -6.5 37.8 -25.4 5.9
INET TO CONSUMPTICN 279.4 275.5 0.0 75.7 160.6 70.8 408.4 499.0 253.1 2022.5 1
FINALCONSUMPTMON
INDUSTRY 199.9 24.6 0.0 6.0 36.0 45.1 231.1 373.8 145.5 1062.0 53% METALLURGICAL 172.9 3.7 0.2 0.3 16.3 84.0 46.0 28.2 351.6 170A NON-FERROUSMETALS 0.9 0.8 7.1 6.1 6.7 21.6 1 CHEMICAL 2.3 0.3 0.6 0.3 2.7 46.1 90.3 24.4 167.0 8A OTHERS 23.8 20.6 5.2 35.4 25.3 93.9 231.4 86.2 521.8 26A CONSTRUCTION 0.5 1.8 0.0 2.3 1.3 1.1 6.7 2.1 15.8 19 AGRiCULTURE 5.4 15.4 3.5 50.5 9.7 14.8 8.4 16.3 124.0 6 TRANSPORT 1.6 27 521 53.0 1.0 1.1 4.0 12.5 128.0 > DOMESTIC. 33.6 154.7 5.0 3.4 0.0 78.5 72.4 47.9 395.5 COMMERCiAL 38.4 74.6 9.1 15.3 15.7 81.6 33.8 28.7 297.2 15
Notes: . (1) Includescoking coal (2) Includespeat and other solid residualfuels (3) Includes LPG (4) Includeslubricants and other non-energeticcomponents AiNNEX2.1 - 54 Page 2 of 2
CZECHOSLOVAKIA Energy Consumption (1990) in PJ
Brown Coal
551 ¢Gw
HIard Coal Conicuruct. su 11 547 By Energy Source By C:onsumer
1 PJ = 34,130 tce = 18,451 toe - 55 -
Annex 2.2 Page 1 of 2
CZECH AND SLOVAK FEDERAL REPUJBLIC
POWER AND ENVIRONMENTALIMPROVEMENT PROJECT
Energy Pricing Policy Portion of SAL
1. An integral part of becoming an efficientmarket economy is letting energy prices reflect the costs of energy. Czechoslovakia'seconomy is two to three times more energy-intensivethan Western European economies, due to (a) low energy prices and central energy allocations;(b) the emphasis on physical targets and the lack of market incentivesto improve efficiency; (c) the emphasis on heavy industries;and (d) the use of outdated equipment. Inefficientenergy use and the heavy reliance on high-sulphurcoal and lignite have also been major pollutioncauses, especiallyin Northern Bohemia. Many ..sidential energy prices are too low, and the structureof energy prices is distorted, strongly influencedby the low CMEA prices. Virtually the entire petroleumand natural gas needs and about 7 percent of electricityneeds have been met through imports from the USSR under bilateral arrangements.
2. Pricing Policies. The Government'smedium-term goal is (a) to deregulateall prices for oil, oil products and coal, and allow free imports and exports of these products; and (b) to establishan autonomousregulatory process for utilities (electricity,heat, and natural gas), whereby tariffs will be set equal to economic costs. Tariffs for tradeables (e.g., coal) will be set equal to internationalprices plus transportation,storage and distributioncosts, with automaticpass through of changes in international prices; and tariffs for non-tradeablegoods and services (e.g., electricity and heat) will be set equal to long run marginal costs (includingproduction/ generation,transportation/transmission, and distributioncosts), passing through changes in input fuel prices based on an automaticfuel adjustment clause. All energy products shall be subject to the Value Added Tax (VAT) when it is established Additional consumptiontaxes on transport fuels will remain in place. The Government is also consideringto charge additional environmentaltaxes on coal, and possibly on some other fuels (e.g., gasoline, diesel, and fuel oil). All environmentalcosts related to the production, transportationand distributionof energy shall be borne entirely by the enterprisescausing the damage, and be covered by tariffs and prices whenever they are regulated. During an initialtransition period prices and tariffs will be progressivelyadjusted towards economic cost levels. Increases shall be made in such a way that the relative structureof prices for different types of consumers reflect the relative structureof estimatedeconomic costs to avoid inefficientinter-fuel substitution. - 56 -
Annex 2.2 Page 2 of 2
3. Progress to date. Prices for oil and petroleumproducts were increasedin July, October, and December 1990, reaching the equivalentof US$30 per barrel of crude oil at the then prevailingexchange rate of Kcs 24 per US$1. Import price changes for oil and oil products will be passed through on a monthly basis. Bi-annualrevisions of transport and distribution costs, to take into account inflationand other cost changes, will enable the Government to adjust these prices as appropriate. Taxes were changed from an ad-valorem (330 percent over previous prices) to a specific rate, so as to have stable government revenue and to limit the increase in consumer prices to the increase in ex-refineryprices. Taxes are high by internationalstandards and produce nearly 5 percent of GDP in budgetarv revenue. At the current exchange rate of Kcs28 per US$1, ex-refineryprices are equivalentto US$26 per barrel; should internationalprices continue to decline, the Government may be advised to increase taxes slightly.
4. Followingthe energy price increasesin December 1990, most energy sales to industry are now close to their economic cost, with the exception of heat. Fuel coal (steam coal and lignite)prices for industry were increased by 50 percent to levels around 60-80 percent of equivalent international (border)prices. Electricityand natural gas tariffs for industrywere increasedby 53 percent and 143 percent, respectively. In March 1991, the Governmentand the Bank conductedjointly a preliminaryreview of estimated long-run marginal costs of electricitysupply. It was found that electricity tariffs for industry (and other large high-voltagecustomers) and for householdsamounted to about 90 percent and 50 percent of estimated LRMC respectively. The Government increasedindustrial electricity prices in April 1991, which will raise high-voltageprices to about 100-130 percent of estimated LRMC. This is the reverse of the efficientpricing structurethat would be indicatedby LRMC.
5. Action to be taken and supportedunder the SAL for Energy Pricing. Prior to the second tranche release, significantsteps towards the preparation of a least-costinvestment program for the electricpower sector were completed. On the basis of this study a suitable pricing study will be developed. Average tariffs for industrialcustomers will be at least equal to their calculated long-runmarginal cost. Tariffs for household consumerswire increasedby about 70% as compared to May 1990 price levels.1 These changes result in a narrowing of the distortionsbetween industrialand household tariffs.
1 The price was increasedby 70% on October 1, 1991. - 57 - ANNEX 2,l3
CZECH AND SLOVAK FEDERAL REPUBLIC
POWERAND ENVIRONMENTALIMPROVEMENT PROJECT
Energy Regulatory Portion of SAL
Action to be taken and supportedunder SAL for regulationof utilities. Utilities in charge of supplyingelectricity, heat, and natural gas to consumers enjoy natural monopolisticpowers and thus require some type of governmentalsupervision, though not operationalcontrol. A system of "economicregulation" shall be put into place, whereby the companies' financialsoundness and operationalautonomy will be assured, but at the same time preserving the qualit) of serviceprovided and the rights of consumers. Health, safety, and environmentalimpact shall also be regulated through this system. The governmentwill prepare and review with the Bank a plan of action for establishingregulatory institutions, processes and methods for the power, heat and gas. A Public Utilities Law would establishthe legal predicateand procedures for economic regulationsof enterpriseswhich produce, transport, and distribute electric energy, natural gas, town gas and thermal (heat) energy. The law would define the scope of regulation;the procedures for implementingthe legislation;and the structure,powers and jurisdictionof the regulatingbodias. The draft law, after review with the Bank, will be submitted to Parliamentprior to third tranche release. Their first assignmentwill be the adoption of a code of regulations,that would define the procedures to be used to establishand update tariffs and to monitor operationsof the regulatedutilities, as well as the system of accounts and reports to be used by such enterprises. The regulating agencieswill also codify regulationsfor the protectionof public health, safety, and the environment. - 58 -ANNEX 3,1
CZECH AND SLOVAK FEDERAL REPUBLIC
POWER At'D ENVIRONMENTALIMPROVEMENT PROJECT
CEZ Planned Capacitv Retirement (MW)
1991 1992 1993 1994 1995 1996 1997
Prunerov I lx11o lx11O
Tisova lx103 1x103
Tusimice I 1x11O Ix110 1xl1O 1xl1O 2x110
Ledvics II 2x110
Oslavany 21+50
Hodonin 1x50 1x50
Melnik I 1x55 1x55
Tisova I 1x54 1x54
Trebovi ce 1x50
Opatovice lx55
Malesice II 1x50
Ledvice 1 1x90
Forici 1x55
TOTAL 394 323 110 160 379 364 485
Source: CEZ - 59- ANNEX 3.2
CZECH AND SLOVAK FEDERAL REPUBLIC
POWER AND ENVIRONMENTALIMPROVEMENT PROJECT
CEZ Planned Installationof FGDs and Improved ESPs
Plannedinstallation of FGDs and inmprovedESPe
1991 1992 1993 1994 1995 1996 1997 1998
PrunerovI *------FGD 4xI10 __n PrunerovII /1 *------FGD 5x210 ------* TusimiceII /2 *------FGD 4x200 ------* Pocerady/3 ------FGD 4x200 + ESP 3x200 ------* Molnick III * FGD lx500 ------* Melnik II *------4xllO ------* Ledvice 4 II * FGD+ ESP lx200 ------* TisovsJ *------FGD lxllO + 2x50 ------* Chvaletic- 4x200 ------* Detmarovice *---- 4x20O ------* Opatovice 6x55---* Bodonin *----2x55 ------* iorici -- 7X55------Other minor - ----
Total capacity equipped with FGDs: ,720 HE
Although Prunerov II FGDs are amply justified, the overall plan is subject to the results of the ongoing Least Cost Development Study.
During the former communist government, decision was made to install FGDs equipment at the PPs Pocerady and Tusimice II. In the latter case, an unproved technologybased on the Magnesite process was installed by the Soviets. They had based the technology on a system aeveloped in the US; but due to the Soviet intervention in Afghanistan, the transfer of technology from the US was stopped. The result was that the installed system at PP Tusimice II never worked, and today the equipment is regarded to be unable to operate. In the case of Pocerady, the first unit is just under constructionand is supposed to be in operation during 1993 based on the wet-limestondprocess. At the plant Tisova, a FGD system based on dry injection of limestone is under construction. In this case, the plant was chosen by the German utility that transferred surplus FGD equipment to CEZ as a gift.
/1 Part of the proposed project.
/2 Partially equipped with MgO2 FGD based on Soviet technology,not yet operational.
/3 FGD for 200-MW under construction.
/4 Partially equipped with low effectiveness (40% SO? removal), seLnd-hand FGD imported from Germany.
Source: CEZ - 60 -
ANNEX 3.3 Page 1 of 5
CZECH AND SLOVAK FEDERAL REPUBLIC
POWER AND ENVIRONMENTAL. IMPROVEMENT PROJECT
Emission Standards for Coal Fired PowAr and Heating Plants and Draft Environmental Regulations
In an amendment to the Air Pollution Act the following standards are regulated. The amendment has been effective since October 1, 1992.
Plant size SO2 NOX CO Fly-ash (dust)
3 3 3 3 a 300 MWt * 500 mg/Nm 650 mg/Nm 250 mg/Nm 100 mg/Nm
50 - 300 MWt **1700 " 650 " 250 " 100
5 - 50 MWt 2500 650 " N.A. 150 2- 5 MWt N.A. N.A. N.A. N.A.
The obtained concentration after mitigation measures should be minimum 15% of basic value.
** The obtained concentration after mitigation measures should be minimum 30% of basic value.
The standards are mandatory for new plants and old plante will obtain a grace period of 5 years. A translation of the regulations concerning emissions from coal fired power and heating plants are enclosed on the pages 2-5. -61- ANNEX 3.3 Page 2 of 5 1. SPCIFIC LIMITS FOR EMISSION 1.1 Production p1hdte Cal energy by means oi luel combustion - eower and healtinc Ilants The maximum amount of emissions discharged into atmosphere during luel combustion in energetic, company's and municipai power and heat plants in order to produce steam, heat and electrical energy is determined by emission limits given under this paragraph. D)uring fuel combustion in order to produce steam, heat or eiectrical energy in power and heat plants the emission limits for contaminants selected according to paragraph 2.2 do not apply. When other types of solid or liquid fuel than fossil fuel and fuel derived (bituminous coal, brown coal, lignite, coke, wood, luel oil and heating oil) are burned in boilers installed in energetic, company's and municipal power and heat plants, the limits for emission from refuse incinerating plant must be observed (see paragraph 3.19).
1.1.1 Combustion of solid luels 1.1.1.1 Limits for solid particle emissions on new plants - Orn boilers running on solid fuels having a heat performance over 5u MW tne weight concentration oi solid particles in the waste gas must not exceed 100 mg/mB. - On boilers running on solid fuels and having a heaL output in the range from 2 to 50 MW the weight concentration must not exceed 250 mg/m9.
1.1.1.2 Limits for sulphur dioxide emissions on new plants - On boilers running on solid fuels having a heat output over 300 MW.r the weight concentration of sulphur dioxide in the waste gas must not exceed 500 mg/m 3. If this value cannot be achieved without waste gas desulphurization, the emission of sulphur dioxLde must be reduced to a level that will not be higher thar. 15% of the ir.itial level. On boilers running on solid fuels and having a heat output ir. the ranoe arom 50 to 3u'J MWT¶,the weight concentration of sulphur dioxide in the waste gas must not exceed 1700 mg/ma. If this value cannot be achieved without waste gaH desulphurization, the sulphur dioxide emiseion must be reduced to a level that will not be higher than 30 of initial level. - On boilers running on solid fuels and lhaving a heat output in the range from 5 to 50 MW.V the sulphur dioxide weight concentration in the waste gas must not exceed 2500 mg/m 3 . - In case of failure of the equipment to limit the emissions the combustion equipment can be operated only if the failure period does not exceed 96 continuous hours and 360 hours in total during a calendar year.
1.1.1.3 Limits for oxides of nitrogen emissions on new plantu on boilers ru;lning on solid fuelB having a heat output over 5 MW the concentration of oxides of nitrogen recalculated to nitrogren dioxide NO2 in the waste gaR must not exceed 650 mg/m. - 62 - ANNEX3.3 Page 3 of 5
1.1.1.4 Limits for carbon monoxiide emissions Or, boiiers runrn,.ng on solid fuels and having a heat output over 50 MW, the concentratior, of carbon monoxide in the waste gas must not exceed 2bO m9/rm3 .
1.1.1.5 L.imitrs for organic compoundl emissions on ne-w plants 1f bark. wood and wooden waste are b,urned in an equiPment havinar a heat ouitput over and includino 2 MW, the organic compounci errission, expressed as concentratior, oi hydrocarborn C in the waste gas murzt not. exceed E50 mg/rin, .
1.1.1.6 General conditions lir- equiprment operation - All the limits for emissions, stated under Paragraph 1..1., apply Ior concentrations recalculated to dr- gas under normal conditions: 101.32 kPa and uo' and for oxygen volume ol 6s% ir, the waste gas. If only wooder, waste is burned the concer.trations are recalculated tc tne oxygen volume of 11'.' irn thie waste cras.
1.1.1.7 Limits Icr emi!sions orn current, plantF Equipment whict is currently an oPeration rc-lorE this edict bccomes efilective, muct ae oPerates an such way that all emissions are minimizecd ar.a within . 'ear- aitei this ecjicT becomcs C-l1CCtikE thc. Jimits giiver; lnde- Paracirarzh 1.1.1 ol thii edict must be observed. The atmosrphere protc-ct)on chec1.c nuthorit. r,as trho right to lix individual errission liI, its ior individual courceo ioi a limitecd period. - II 7 years aIter the date oi eIlectivenor,o oI thirs cdict an equipment would not be operated more tharn 13000 hours, the indivicual c-mircion limits will bc dc-tormined rby the .atinolohere protecto.on chc-cX authority baLsed or, application of kocrce ci the equirmcnt tsour;. of Pollution).
:..1.2 Liquid fuel cornbuutiori 1.1.2.1 Limits lor colid particle emisCiors oi, nro-wpliar.ti;
- rn boalerr rur,ning or, iquoad luelc navir.cz theat output cuer 50 M1WrthL w¢,,inht concrnttration ol cuoid pzarticlcc it, the wartc- gaG musut not c-xcec-d tIJ rimg/rn'-. Or, boi loer- running on ii quid lucel nava r,c a h1eat out put in the rangc from , to 'O MWTrthc- Wfeitht concentratiorn ir. thf waite gaf: must not c>coccd 101) i,0 , .