MONTHLY PROGRESS REPORT UPTO 30.04.2019 DEVELOPMENT PROGRAMME 2018-19 WATER SUPPLY & SANITATION

Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Ongoing Schemes Date of A.A :14-12-2015.Date of T.S: 04-02- 2016.Date of Start: 26-04-2016.Date of 1 1604 R/W/S Scheme Dhamial Rawalpindi 181.407 164.389 5.673 5.673 2.255 2.255 100% 166.644 92% Completion:30-06-2019.Scheme put into operation & handed over to CBO, Only contractor liabilities pending.

Construction of Road/Streets in Village Date of A.A :19-07-2017.Date of T.S: 21-07- Ghoon UC -Beor and Construction of 2 1605 Rawalpindi 8.000 6.000 0.667 0.667 0.000 0.000 0% 6.000 75% 2017.Date of Start: 28-11-2018.Date of Road/Streets & Hand Pumps in UC -Punjar Completion:30-06-2018.Scheme completed & UC -Narar, District Rawalpindi in saving. Date of A.A :19-07-2017.Date of T.S: 21-07- 2017.Date of Start: 29-11-2017.Date of Water Supply Scheme in Kahuta Town 3 1606 Rawalpindi 8.000 2.143 1.952 1.952 1.464 1.464 100% 3.607 45% Completion:30-06-2020.Laying of pipeline Tesil Kahuta, District Rawalpindi completed and made functional, only restoration of cuts is pending which will be done after receiving of balance funds.

Date of A.A :19-07-2017.Date of T.S: 21-07- P/I Tube Well in Latori Syedan & P/I Hand 2017.Date of Start: 29-11-2017.Date of Completion:30-06-2020.Tube Well bore 4 1607 Pumps in Dhok Naka and Village Matore Rawalpindi 5.650 0.120 0.667 0.667 2.834 2.834 100% 2.954 52% completed, Pumping Machinery arranged at UC -Matore, District Rawalpindi site.Demand Notice issued and will be paid after receiving of funds.

A.A Date 03.09.2015. T.S Date Rehabilitation & Augmentation &Ext of 5 1608 43.515 41.514 0.667 0.667 0.500 0.500 100% 42.014 97% 23.09.2015.Date of Start of Scheme water Supply Scheme for Village Dhullian 10.11.2015. Date of Completion of Scheme 30.06.2019.Work is in progress.

Augmentation / Rehabilitation of Water A.A Date 10.09.2016. T.S Date 02.05.2017. Date of Start of Scheme 16.06.2017. Date 6 1609 Supply Scheme Khour Tehsil Pindi Gheb Attock 69.989 12.510 3.333 3.333 2.000 2.000 100% 14.510 21% of Completion of Scheme 30.06.2019. Work District Attock is in progress.

Date of A.A 08.01.2015.Date of T.S 21.01.2015.Date of Start 20.04.2015.Date of completion 30.06.2019.Percolation well, Ground Storage Tank and Rising main completed. Work on the scheme Rehabilitation of Rural water Supply 7 1610 Chakwal 25.000 18.475 2.175 2.175 0.043 0.000 0% 18.475 74% suspended due to loss of water in newly Scheme Sarkalan developed source as some blasting was done by Mining Department. Revised A.A accorded by the DDC on 29.03.2019.Work will be started after T.S & completion of tendering process. Excess funds re- appropriated.

Date of A.A 11.03.2015.Date of T.S 21.01.2015.Date of Start 20.03.2015.Date of Rehabilitation of Rural Water Supply completion 30.06.2019.Work suspended at site due to sever conflicts among the CBO / 8 1611 Scheme Dhoke Khour Tehsil Talagang, Chakwal 1.620 0.719 0.300 0.300 0.000 0.000 #DIV/0! 0.719 44% community members. Community Chakwal. Development Unit trying to resolve the issues. Excessive funds surrendered through re-appropriation.

Scheme shall be completed by 30-06- Extension of water Supply scheme 2020.Balance funds required Rs. 120.008 9 1612 Khewra, Tehsil Pind Dadan Khan, District Jhelum 161.845 28.504 13.333 13.333 0.453 0.453 100% 28.957 18% million.Date of A.A 11-04-2016.Revised A.A Jhelum 31-03-2017.Date of T.S 19-08-2016.Work awarded on 06-02-2017.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Scheme shall be completed by 30-06- Authority to maintain & Regulate Naroomi 2020.Balance funds required Rs. 324.779 10 1613 Dhan water Supply Scheme Tehsil Jhelum 361.446 10.000 26.667 26.667 20.000 20.000 100% 30.000 8% million.Date of A.A 11/2017.Revised A.A 30- P.D.Khan 111-2017. Work award on 16.02.2018.Work in progress Rural Water Supply Scheme Chal No 11 1614 Sargodha 15.000 0.039 3.333 3.333 2.500 2.500 100% 2.539 17% Work in progress. 61/SB Sargodah

Date of AA 15-10-2015 Date of TS 09-11- 2015 Date of award 15.01.2016 Date of Installation of 300 Hand Pumps Noushera completion 30.06.2019 Hand Pump 110/140 12 1615 Khushab 132.000 111.498 1.833 1.833 2.375 2.365 100% 113.863 86% No Bore Submersible Pump 152/160 No. Khushab P/Machinery 152/160 Set G.S Tank 180/160 No. Work is in progress. Latitude 32.489848333333335, Longitude 72.180345

Date of AA 27.08.2016 Date of TS 03-09- 2016 Date of Award 21.01.2017. Date of water Supply Scheme Jhunge Walan of Completion 30.06.2019 T/Well 1/1 No. 13 1616 Khushab 24.058 14.550 3.167 3.167 2.375 2.370 100% 16.920 70% P/House 1/1 No. P/Machinery 1/1 Set UC Khabeki. R/Main 1 1/2"i/d to 4"i/d 26220/31730 Rft Work is in progress. Latitude 32.614153333333334, Longitude 72.28653

Date of AA 27.08.2016 Date of TS 03-09- 2016 Date of Award 24.01.2017 Date of Completion 30.06.2019 Bore Submersible 14 1617 water Supply Scheme Kalial UC Khura. Khushab 25.996 15.996 3.333 3.333 2.500 2.450 98% 18.446 71% Pump 6/6 No. R/Main 1 1/2" to 5"i/d 18605/27116 Rft G.S Tank 1/1 No. work is in progress. Latitude 32.551053333333336, Longitude 72.30362833333334

Date of AA 29.7.2017 Date of TS 04.09.2017 Date of award 14.12.2017 Date Rehabilitation / Improvement of Water of completion 13.12.2019 Tube Well 1 No. 15 1618 Supply Scheme, Khoora UC Khoora, Khushab 12.695 1.998 1.000 1.000 0.750 0.700 93% 2.698 21% Pump House 1 No. Pumping Machinery 1 District Khushab No. Rising Main 3640/19400 Rft Work is in progress. Latitude 32.52835166666667, Longitude 72.21790333333334

Date of A.A. 13-01-2017, Date of T.S. 24-01- 2017, Date of Start of Work. 08-05-2017, Installation of Submersible Water Pumps, 16 1619 Mianwali 50.000 37.423 3.387 3.387 2.540 2.537 100% 39.960 80% Remarks E.R.S=130/144, Trail Bore=6/6, Tehsil Isa Khel District Mianwali. T/Well boring= 61/72, P/Machinery= 61/72, G.S.Tank= 7/72. Work is in progress.Latitude/Longitude: 32.96' / 71.32'

Date of A.A.27-08-2016, Date of T.S.15-10- Provision of Submersible Pumps (UC Bani 2016, Date of Start of Work.03-12-2016, Remarks. E.R.S=35/50, T/Well boring= 17 1620 Afghan, Sawance, Ghundi, Chakrala, Ban Mianwali 49.980 33.415 5.520 5.520 4.140 3.880 94% 37.295 75% 84/110, P/Machinery=84/110, Hafiz Gee, Thamay Wali, Namal) G.S.Tank=0/62-No. Work is in progress.Latitude/Longitude: 32.67' / 71.84'

Date of A.A 25.08.2015 Date of T.S Extension of Sewerage and water Supply, 18 1621 Bhakkar 71.300 38.133 10.934 10.934 11.741 11.741 100% 49.874 70% 11.11.2015 Date of Commencement Mankera. 28.12.2015 Date of completion 30.06.2019 (Latitude 31.3891°/ Longitude 71.4388°) Date of A.A 05-08-2017.Date of T.S.05-09- Construction of PCC in Different Streets in 2017. No. of Beneficiaries = - Surface Drain- 19 1622 Faisalabad 5.000 2.000 1.000 1.000 0.750 0.650 87% 2.650 53% 3600/- Rft, Brick Pavement 12376/10636- UC -64 District Faisalabad CFT, Sullage Carrier 1100/- Rft, Work is in progress. Date of A.A 05-08-2017. Date of T.S.05-09- Construction of PCC in Different Streets in 20 1623 Faisalabad 5.000 1.000 1.333 1.333 1.000 0.995 100% 1.995 40% 2017. No. of Beneficiaries = - Surface Drain- UC -65 District Faisalabad 10490/- Rft, Brick Pavement 655/7206-CFT, PCC 1423/- CFT, Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 05-08-2017.Date of T.S.05-09- Construction of PCC in Different Streets in 2017. No. of Beneficiaries = - Surface Drain- 21 1624 Faisalabad 5.000 2.000 1.000 1.000 0.750 0.746 99% 2.746 55% 5610/1346- Rft, Brick Pavement UC -66 District Faisalabad 13939/2996-CFT, Sullage Carrier 50/50-Rft, Work is in progress. Date of A.A 05-08-2017.Date of T.S.05-09- Construction of PCC in Different Streets in 22 1625 Faisalabad 5.000 1.000 1.333 1.333 1.000 0.870 87% 1.870 37% 2017. No. of Beneficiaries = - Surface Drain- UC -67 District Faisalabad 6920/-Rft, Brick Pavement-11612/8716- CFT, Work is in progress. Date of A.A 05-08-2017.Date of T.S.05-09- Construction of PCC in Different Streets in 2017. No. of Beneficiaries = - Surface Drain- 23 1626 Faisalabad 5.000 1.000 1.333 1.333 1.000 0.972 97% 1.972 39% 3550/205-Rft, Brick Pavement 11830/8255- UC -72 District Faisalabad CFT, Sullage Carrier 1165/-Rft, Work is in progress. Corrigendum for Change of Nomenclature Installation of Water Filetartion Plant in UC-463 to Chak No. 463/GB issued vide Chief Corridination 1(17) RO (ADP ) 24 1627 Chak No.463/GB Teshil Smundri District Faisalabad 3.000 0.000 1.000 1.000 0.000 0.000 #DIV/0! 0.000 0% P&D/2018 dated 20.03.2019 letter send to Faisalabad DDC for AA vide this office No. 1012 dated 28.03.2019.

Date of A.A =21.04.2017. Date of T.S =23.05.2017. No. of Beneficiaries= 8456 Anticipated date of completion= 02.06.2012 Investigation of source= 3/3 • Tube well =3/3-No.• Pump house = 4/4-No.• Pumping Machinery = 5/5-Set • Rising main 6” i/d = 435/700 Rft• 8” i/d =4700/6296 Rft• 10” i/d Rehab: of Rural Water Supply Scheme =485/500- Rf• 12” i/d =492/500- Rft • 14” 25 1628 Faisalabad 87.765 84.043 1.000 1.000 0.750 0.640 85% 84.683 96% i/d= 40907/40200 Rf t • D/System 3” i/d Chak No. 215/RB Tehsil & Distt: Faisalabad =107614/106904 Rft • 4” i/d =13648/ 12295 Rft • 6” i/d =8241/8405 Rft• 8” i/d =1364/ 1400 Rft• Hypo Chlorinator =5/ 5-No • Transmission line =4/4-NO• Boundary wall=1/1-Job • Centrifugal pump =3/3-Set • Ground Storage tank =1/ 1-No • Price variation=3.127/3.722 Million • Work in progress

Date of A.A = 20.10.2016. Date of T.S =24.10.2016(Revised) No. of Beneficiaries= 8581Anticipated date of completion=12.08.2017 Investigation of source=1/1 • Tube well =1/ 1-No. • Pump Rural Water Supply Scheme at Chak 26 1629 Faisalabad 7.955 6.725 1.230 1.230 0.923 0.790 86% 7.515 94% house=1/ 1-No. • Pumping Machinery =1/ 1- No.84/JB Set• Rising main 6” i/d =6264/ 5400 Rft• D/System 3” i/d =2670/3080 Rft • 4” i/d=510/700 Rft • 6” i/d =718/400 Rft• Hypo Chlorinator =1/1-No• OHR 10000 glns =20%/1-No • Transmission line 1-NO •Work in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 20.10.2016 2- Date of T.S 21.10.2016 3- Anticipated date of completion 30.06.2019 4- No. of Beneficiary - 5333 Persons TRIAL BORE = 2/1-Job TUBE-WELLS (0.60-CUSEC) = 2/2-No. PUMP HOUSE (12' X 12') = 2/2-No. RISING MAIN / DISTRIBUTION SYSTEM 6” i/d PVC "B" Class = 23760/23345 Rft 4” i/d PVC "B" Class = 1000/1246 Rft 3” i/d Rehab. of rural water Supply scheme Chak Toba Tek 27 1630 23.943 18.826 1.318 1.318 0.159 0.159 100% 18.985 79% PVC "B" Class = 2000/2757-Rft PUMPING No. 343/GB T.T. Singh Singh MACHINERY 2/2Set OVER-HEAD- RESERVOIR (10,000-GLNS) = 1/1- NoHYPO CHLORINATOR = 2/2-No. BOUNDARY WALL = 1125/1000-Rft Canal CROSSING = 1/1-Job ELECTRIC TRANSMISSION LINE = 3/3-Job OPERATION & MAINTENANCE = 1/0-Job Scheme completed in saving. Balance funds to be released in 4th quarter will be used for O&M.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3- Anticipated date of completion 30.06.2019 4- No. of Beneficiary - 6390 Persons TRIAL BORE = 1/1-Job TUBE-WELLS (0.60-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/10No. RISING MAIN / DISTRIBUTION SYSTEM 8” i/d PVC "B" Class = 25789/16455-Rft 6” i/d PVC "B" Class = 3129/3216-Rft 4” i/d Rural water Supply Scheme Chak Toba Tek PVC "B" Class = 12964/13647-Rft 3” i/d 28 1631 31.298 18.962 3.011 3.011 0.000 0.000 #DIV/0! 18.962 61% PVC "B" Class = 25788/21584-Rft No.674/15/GB Singh PUMPING MACHINERY = 1/1-Set OVER- HEAD-RESERVOIR (10,000-GLNS) = 1/1- No. HYPO CHLORINATOR = 1/1-No. STAFF QUARTER = 1/0-Job BOUNDARY WALL = 1/0-Job RAOD CROSSING = 1/0- Job ELECTRIC TRANSMISSION LINE = 1/1-Job OPERATION & MAINTENANCE = 1/1-Job Scheme completed in saving. Balance funds to be released in 4th quarter will be used for O&M.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3- Anticipated date of completion 30.06.2019 4- No. of Beneficiary - 3561 Persons TRIAL BORE = 1/1-Job TUBE-WELLS (.40-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') =1/1-No. RISING MAIN / DISTRIBUTION SYSTEM 6” i/d PVC "B" Class =230.70/23103-Rft 4” i/d PVC "B" Class = 15650/15077-Rft 3” i/d Rural water Supply Scheme Chak Toba Tek 29 1632 28.057 20.000 2.686 2.686 0.533 0.533 100% 20.533 73% PVC "B" Class = 31320/32693-Rft No.675/16/GB Singh PUMPING MACHINERY =1/1-Set OVER- HEAD-RESERVOIR (10,000-GLNS) =1/1- No. HYPO CHLORINATOR = 1/1-No. STAFF QUARTER = 1/1-Job BOUNDARY WALL = 1/1-Job ELECTRIC TRANSMISSION LINE = 1/1-Job OPERATION & MAINTENANCE = 1/0-Job Scheme completed in saving. Balance funds to be released in 4th quarter will be used for O&M. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3- Anticipated date of completion 30.06.2019 4- No. of Beneficiary - 3381 Persons TRIAL BORE = 1/1-Job TUBE-WELLS (0.50-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/1-No. RISING MAIN / DISTRIBUTION SYSTEM 6” i/d PVC "B" Class = 14692/16286-Rft 4” i/d PVC "B" Class = 13952/13353-Rft 3” i/d Rural water Supply Scheme Chak No.685 Toba Tek 30 1633 21.024 16.243 0.508 0.508 0.000 0.000 #DIV/0! 16.243 77% PVC "B" Class = 1556014678-/Rft 26 GB Singh PUMPING MACHINERY = 1/1-Set OVER- HEAD-RESERVOIR (10,000-GLNS) = 1/1- No.HYPO CHLORINATOR = 1/0-No. STAFF QUARTER = 1/0-Job BOUNDARY WALL = 1/0-Job ELECTRIC TRANSMISSION LINE = 1/0-Job OPERATION & MAINTENANCE = 1/0-Job Scheme completed in saving. Balance funds to be released in 4th quarter will be used for O&M.

1-Date of A.A 10.09.2015 2- Date of T.S 25.02.2016 3- Anticipated date of completion -30.06.2020 4- No. of Beneficiary - 15516 Person Tube-well = 3/3- No. Pump House = 3/3-No. Rising Main / D- Sys 10" i/d PVC = 25500/23318-Rft 8" i/d Rural water Supply Scheme for Chak Toba Tek 31 1634 99.832 74.101 3.333 3.333 2.500 2.488 100% 76.589 77% PVC = 1000/1000-Rft 6" i/d PVC = No.407/JB, 409/JB, 410/JB & 411/JB Singh 30945/28765-Rft 5" i/d PVC = 31050/25730- Rft 4" i/d PVC = 38055/27158-Rft 3" i/d PVC = 61881/47496-Rft Pumping Machinery = 8/8-Set Ground Storage Tank = 2/2-No. Overhed Reservoir = 5/5-No. Boundary Wall = 1000/0 Rft Electric Connection =8/0-Job Work in progress.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3- Anticipated date of completion 30.06.2019 4- No. of Beneficiary - 5867 Persons TRIAL BORE = 1/1-Job TUBE-WELLS (0.60-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/1-No. RISING MAIN / DISTRIBUTION SYSTEM Rural water Supply Scheme, Chak 6” i/d PVC "B" Class = 13265/13265-Rft 4” Toba Tek 32 1635 No.709/GB and 710/GB, Tehsil Kamalia, 18.232 14.000 0.744 0.744 0.186 0.186 100% 14.186 78% i/d PVC "B" Class = 10169/10169-Rft 3” i/d Singh PVC "B" Class = 25833/25833-Rft District Toba Tek Singh PUMPING MACHINERY = 1/1-Set HYPO CHLORINATOR = 1/1-No. STAFF QUARTER = 1/1-Job ELECTRIC TRANSMISSION LINE = 1/1-Job OPERATION & MAINTENANCE = 1/0-Job Scheme completed in saving. Balance funds to be released in 4th quarter will be used for O&M.

1-Date of A.A 20.10.2016 2- Date of T.S 31.10.2016 3-Date of invitation of tenders.13.02.2017 4- Date of Receipt of tenders -15.02.2017 5- Date of completion as per PC-I 30.06.2018 6- Date of work Rural water Supply Scheme, Chak order - 09.03.2017 .7- Anticipated date of Toba Tek 33 1636 No.712/GB and Jamal Pahar, Tehsil 22.981 17.000 1.994 1.994 0.000 0.000 #DIV/0! 17.000 74% completion 30.06.2018 .8- No. of Singh Beneficiary - 3561 Persons 9-Funds Kamalia, District Toba Tek Singh Released by F.D 03.08.2018 & 24.01.2019 10-Re-appropriation of funds(+/-) (-) 11.01.2019 & 15.03.2019. Scheme completed in saving. Balance funds to be released in 4th quarter will be used for O&M. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

1-Date of A.A 06.12.2014 2- Date of T.S 02.03.2015 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary -21302 Person Tube-well = 3/3-No.Pump House = 3/3-No. Rising Main / D-Sys 10" i/d PVC = 28433/28416-Rft8" i/d PVC = 4781/4781-Rft6" i/d PVC = 17272/17136- Rft4" i/d PVC = 40201/39256-Rft.3" i/d PVC water Supply & Sewerage Scheme Rajana Toba Tek 34 1637 179.779 104.999 8.333 8.333 6.250 6.240 100% 111.239 62% =96178/90493-RftPumping Machinery = 5/5- District Toba Tek Singh Singh SetGround Storage Tank = 1/1-NoRCC Sewer 9" i/d 15878/0-Rft12" i/d 3931/48- Rft15" i/d 4334/3202/0-Rft18" i/d 3528/2900- Rft21" i/d 3235/3232-RftForce Main / S.Carrier =3280/0-Rft.Disposal Works = 3/2- No.Surface Drain = 890/0-Rft. Brick Pavement = 3221/0-CftBoundary Wall = 1300/800-Rft.Electric Connection = 8/0-Job Work in progress.

11-Date of A.A 28.12.2015 2- Date of T.S 25.02.2016 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - 37501 Person .Tube-well = 5/5-No. Pump Rural water Supply schemes Chak House= 5/5-No.Rising Main / D-Sys 6" i/d Toba Tek 35 1638 No.285/GB, 383/JB, 390/JB, 380/JB, 90.000 69.965 3.333 3.333 2.500 2.488 100% 72.453 81% PVC= 17705/15632-Rft 5" i/d PVC= Singh 77885/81456-Rft 4" i/d PVC= 46920/45118- 382/JB Feroz and 336/GB, T.T. Singh Rft 3" i/d PVC= 53965/52145-Rft Pumping Machinery= 6/5-Set Ground Storage Tank= 1/1-No. Overhed Reservoir= 5/5-No. Boundary Wall = 2297/2297-Rft Electric Connection = 6/6-JobWork in progress. Installation of 02 No Water Filetration 1-Date of A.A 14.11.2018 2- Date of T.S Plants in Chak no 771/GB & Mouza Akbar Toba Tek 20.11.2018 3- Anticipated date of 36 1639 6.000 0.000 2.000 2.000 2.000 2.000 100% 2.000 33% completion 30.12.2021 4- No. of Beneficiary Sau & UC Jussa tehsil Per Mehal District Singh -3233 Person Filtration Plant = 2/1-No. work Toba Tek Singh in progress. Provision of Water Supply and Drainage 37 1640 Scheme in Village Sher Garh UC Machiwal Gujrat 49.971 0.400 3.333 3.333 2.500 2.500 100% 2.900 6% A.A Date =28.2.2018.work in progress Tehsil & District Gujrat * A.A Date. 25.08.2017* T.S Date. Construction of street / PCC / Soling / Mandi 38 1641 150.000 69.978 3.333 3.333 5.150 5.150 100% 75.128 50% 13.09.2017* Start Date. 06.01.2018* Nallian in various Ucs of District M.B.Din Bahauddin Completion date 05.01.2020Work in progress. Rural water Supply & Drainage Scheme * A.A Date. 19.03.2015* T.S Date. Mandi 39 1642 Village Badshah Pur Tehsil Malikwal District 85.587 75.587 3.333 3.333 2.400 2.400 100% 77.987 91% 02.04.2015* Start Date 22.05.2015.* Bahauddin Completion date 30.06.2019.* Work in M.B.Din progress. * A.A Date. 19.03.2015* T.S Date. Rural water Supply & Drainage Scheme Mandi 40 1643 62.780 57.780 1.667 1.667 0.650 0.650 100% 58.430 93% 02.04.2015* Start Date 22.05.2015.* Village Jayya Tehsil & District M.B.Din Bahauddin Completion date 30.06.2019.* Work in progress. Rural water Supply and drainage Scheme * A.A Date. 28.04.2015* T.S Date. Bhaagowal & Noor Pur Peeran with Mandi 41 1644 50.000 45.000 1.667 1.667 0.450 0.450 100% 45.450 91% 19.05.2015* Start Date 18.06.2015.* adjecent abadies tehsil Mailk waal district Bahauddin Completion date 30.06.2019.* Work in mandi bahuddin progress Installation of 02 tubewells at Tahayat & 42 1645 Lahore 36.878 20.044 5.600 5.600 0.900 0.900 100% 20.944 57% Scheme completed & under operation by Chandrai Village, Green Town, Lahore PHED Scheme completed & under operation by 43 1646 Rural water Supply Scheme Mohlanwal Lahore 53.594 42.378 2.734 2.734 2.051 2.030 99% 44.408 83% PHED Scheme completed & under operation by 44 1647 Rural water Supply Scheme Sundar Lahore 24.475 22.331 0.715 0.715 0.536 0.530 99% 22.861 93% PHED Scheme completed & under operation by 45 1648 Rural water Supply Scheme Village Bath Lahore 39.469 29.475 3.331 3.331 1.611 1.611 100% 31.086 79% PHED Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Scheme put operational and handed over to CBO for O&M but due to damages caused by Sui Gas Department during laying of Rural water Supply Scheme Village Chah 46 1649 Lahore 16.930 12.038 1.308 1.308 0.000 0.000 #DIV/0! 12.038 71% their distribution network in streets, water Tamoli supply network is broken resultantly scheme is temporarily dysfunctional. For rehabilitation funds have been demanded under backup support programme.

Establishment/ Construction of water Supply Scheme at UC 30, 31, 32 wanadala 47 1650 Sheikhupura 152.044 85.000 8.332 8.332 6.249 6.249 100% 91.249 60% Work in Progress dial singh and dhaka nizampura tehsil feroz wala District Sheikhupura

48 1651 Water Supply Scheme Pind burj Attari Sheikhupura 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Work in Progress Rural water Supply and Drainage Scheme 49 1652 Sheikhupura 198.903 72.367 6.667 6.667 5.000 5.000 100% 77.367 39% Work in Progress Javed Nagar, District Sheikhupura Rural water Supply Drainage Scheme Iqbal 50 1653 Sheikhupura 140.161 83.696 3.333 3.333 2.500 2.500 100% 86.196 61% Work in Progress Town District Sheikhupura Rural water Supply Drainage Scheme UC 51 1654 Sheikhupura 95.061 54.999 3.333 3.333 2.500 2.500 100% 57.499 60% Work in Progress Kot Ranjeet Singh Sheikhupura Rural Warter Supply and Drainage P.C.C Funds fully utlized, work stopped due to non- 52 1655 Scheme Tibbi Kamboh, Mochi Pura, Kasur Kasur 199.551 29.782 6.667 6.667 5.000 5.000 100% 34.782 17% availability of funds City. Rural Water Drainage PCC Scheme 53 1656 Bhoojke, Naike & Adjoining Abadies District Kasur 114.522 97.085 5.812 5.812 1.509 1.509 100% 98.594 86% Scheme Completed Kasur. Rural water Supply & Drainage PCC 54 1657 Scheme at Marali Hithar and Adjoining Kasur 97.453 52.295 5.072 5.072 1.324 1.324 100% 53.619 55% Scheme Completed Abadies District Kasur (Revised) Rural water Supply & Drainage Scheme Funds fully utlized, work stopped due to non- 55 1658 Chak No.14 & Ghandhi Otar Tehsil Pattoki Kasur 105.412 84.160 20.000 20.000 15.000 15.000 100% 99.160 94% availability of funds District Kasur. water Supply & Drainage Scheme They Kalay, Basti Balochi, Jhalar Qadir, Jhalar Scheme physically completed, Balance 56 1659 Rehmani, Jhalar Choudhry & Jhalar Kasur 119.701 83.750 3.333 3.333 4.797 4.797 100% 88.547 74% funds are requried to clear the contractor Baglian Wali i/c Tubewell of Rao Tamkeen liabilities District Kasur. Water Supply and Drainage Scheme 57 1660 Gondy Warha, Lambey Jagir, Dhaban, Kasur 82.108 78.345 1.254 1.254 0.000 0.000 #DIV/0! 78.345 95% Work in Progress Sherpur, Lambey Mahtam & Fatey Wala. water Supply & Drainage Scheme Chak Funds fully utlized, work stopped due to non- 58 1661 No.31,32,33 Phullani, Dhoop Sarri & Kasur 199.992 84.797 5.000 5.000 3.750 3.750 100% 88.547 44% availability of funds Saharankey District Kasur Rural water Supply and Drainage PCC 59 1662 Scheme at Mandi Usmanwala and Kasur 158.978 138.348 6.877 6.877 11.579 11.579 100% 149.927 94% Scheme Completed Adjoining Abadies District Kasur. Rural water Supply and Drainage PCC Scheme physically completed, Balance 60 1663 Scheme Hardo Ban Bodla and Adjoining Kasur 99.851 71.924 3.333 3.333 2.500 2.500 100% 74.424 75% funds are requried to clear the contractor Abadies District Kasur. liabilities Rural water Supply and Drainage PCC 61 1664 Scheme Maan Bhamni Wala and Adjoining Kasur 178.985 170.646 2.778 2.778 0.000 0.000 #DIV/0! 170.646 95% Work in Progress Abadies District Kasur. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Rural water Supply and Drainage PCC 62 1665 Scheme Rajuwal and adjoining Abadies Kasur 113.943 111.586 0.786 0.786 0.000 0.000 #DIV/0! 111.586 98% Scheme Completed District Kasur.

Date of A.A 22-04-2017 Date of T.S 29.09.2016 Date of invitation of tenders 25- 05-2017 Date of Receipt of tenders 26-05- 2017 Date of work order 02-06-2017 Date of completion as per PC-I Anticipated date Rural Water Supply & Drainage Scheme, 63 1666 Okara 22.250 5.481 7.252 7.252 3.639 3.625 100% 9.106 41% of completion 30-06-2018Tubewell Boring = Qila Dewan Singh Depaplur, Okara. 2 / 2. NoRising Main Dirtribution System 3" to 8" i/d = 26611 / 40716 RftOHR 20000 Glns 1.NO. 20% completeStaff quarter = 1/ 1 No 80% completeExternal Electrification 1 / 1 Job 20% complete No. of Beneficiary 11550 Person, Work is in progress.

• Date of AA =23.11.2016,• Date of TS =07.12.2016,• No. of Beneficiaries=36267• Date of receipt of tender =07.01.2017,• Date of Work Order =08.02.2017,• Anticipated date of completion 30.06.2019,• Latitude=30.42941166666667• Longitude= 73.04414166666668Tube Well=10/10 No.Pump House=10/10 No.Pumping Machinery=10/10 No. (2 Set Installed 8 Set Arranged)Rising Main & Distribution water Supply Scheme Chak No.120/9.L 64 1667 Sahiwal 105.498 91.699 4.599 4.599 3.449 3.445 100% 95.144 90% System3" i/d PVC Pipe =101773/95762 Kameer. Rft4" i/d PVC Pipe =14336/16039 Rft6" i/d PVC Pipe =4824/8254 Rft8" i/d PVC Pipe =7364/9123 Rft10" i/d PVC Pipe =4532/5449 Rft12" i/d PVC Pipe =1854/1690 Rft14" i/d PVC Pipe =4538/4497 Rft16" i/d PVC Pipe =6481/6517 RftHypo Chlorinator=10/13 SetElectric Connection=2/10 JobOHR 50000 Gln=2/2 No.OHR 100000 Gln=1/1 No.Scheme near to completion and under test operation.

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3. Date of Pre-Qualification: - 4.Date of invitation of tender 04.03.2010 5.Date of Receipt of tenders 06.03.2010 R/W/S/Scheme Gareywala, 65 1668 Multan 70.476 52.661 2.333 2.333 1.750 1.470 84% 54.131 77% 6.Date of work order 14.04.2010 7.Date of Nawabpur,Basti Nau Completion as per PC-l 13.02.2013 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries 51946 Persons. Work is in Progress.

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3. Date of Pre-Qualification: - 4.Date of invitation of tender 06.02.2010 5.Date of Receipt of tenders 08.02.2010 R/W/S/Scheme Raja Pur, Siddiquebad, 66 1669 Multan 77.962 64.018 0.667 0.667 0.500 0.425 85% 64.443 83% 6.Date of work order 14.04.2010 7.Date of Hirwat,Yere Wala Completion as per PC-l 13.02.2013 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries 43334 Persons. Work is in Progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3. Date of Pre-Qualification: - 4.Date of invitation of tender 06.02.2010 5.Date of Receipt of tenders 08.02.2010 6.Date of work order 18.06.2010 7.Date of 67 1670 R/W/S/Scheme Taraggar. Multan 61.140 51.141 3.333 3.333 0.666 0.666 100% 51.807 85% Completion as per PC-l 17.06.2012 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10.No. of beneficiaries 20623 Persons. Work is in Progress.

1. Date of A.A: 17.09.2015 (28.05.2016) 2. Date of T.S: 08.06.2016 3. Date of Pre- Qualification: 11.06.2016 4. Date of Invitation of Tender: 18.07.2016 5. Date of Rural Water Supply & Sewerage Scheme receipt of Tender: 20.07.2016 6. Date of 68 1671 Multan 45.238 41.886 1.000 1.000 0.750 0.670 89% 42.556 94% Award: 22.07.2016 7. Date of Completion Nai Wala as per PC-I: 16.09.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 23.11.2018. 24.01.2019 10. No. of Benificiary=6508 Persons. Work is in progress.

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: 02.11.2016 6. Sewerage Drainage Scheme Qasba 69 1672 Multan 46.177 43.912 1.000 1.000 2.015 2.000 99% 45.912 99% Date of Award: 12.11.2016 7. Date of Jalalpur Khaki Shujabad Completion as per PC-I: 11.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 23.11.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress.

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt of Tender: 15-11-2016 6. Date of Award: 03-12-2016 7. Date of Completion as per PC-I: 31-12-2017 8. 70 1673 water Supply / Sewerage Mouza Rawani. Lodhran 29.450 24.182 1.721 1.721 1.291 1.200 93% 25.382 86% Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 8834 Persons. Work is in Progress. Sewerage portion is under test operation.

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt of Tender: 15-11-2016 6. Rural water Supply Scheme Chak No.12/M Date of Award: 08-12-2016 7. Date of Completion as per PC-I: 31-12-2017 8. 71 1674 & 14/M (East & West) Tehsil Dunyapur, Lodhran 29.922 21.446 2.784 2.784 2.088 2.050 98% 23.496 79% Anticipated Date of Completion: 20-06-2019 District Lodhran 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 6980 Persons. Work is in Progress. Scheme is under test operation. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A. 22-08-2015. 2. Date of T.S. 27-08-2015 Rev. T.S 07-02-2017 3. Date of Pre-Qualification: 4. Date of invitation of tender 01-12-2015 5. Date of Receipt of Rural Water Supply Scheme Quatabpur tenders 02-12-2015 6. Date of work order 16-12-2015. 7. Date of Completion as per 72 1675 Dunyapur, Tehsil Dunyapur, District Lodhran 29.850 9.623 6.742 6.742 0.000 0.000 #DIV/0! 9.623 32% PC-l 21-08-2016 8. Anticipated date of Lohdran completion 30-06-2017 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of beneficiaries 13535 Persons. Scheme completed & under test operation.

1. Date of A.A (Amended) 04.04.2016 2. Date of T.S: 12.04.2016 3. Date of Pre- Qualification: 02.04.2016 4. Date of Invitation of Tender: 21.04.2016 5. Date of Receipt of Tender: 23.04.2016 6. Date of Provision of water Supply Schemes in 73 1676 Khanewal 60.664 47.747 4.306 4.306 3.230 3.230 100% 50.977 84% Work order: 30.04.2016 7. Date of Chak No. 135/10.R, District Khanewal. Completion as per PC-I: 16.09.2017 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11No. of beneficiaries 15048 Persons Work is in progress.

1. Date of A.A (Amended) 17.09.2015 2. Date of T.S: 07.03.2016 3. Date of Pre- Qualification: 02.04.2016 4. Date of Invitation of Tender: 21.04.2016 5. Date of Receipt of Tender: 23.04.2016 6. Date of Provision of Water Supply Schemes in 74 1677 Khanewal 62.211 49.998 1.000 1.000 0.750 0.750 100% 50.748 82% Work order: 30.04.2016 7. Date of Chak No. 136/10.R, District Khanewal. Completion as per PC-I: 29.10.2017 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 23.11.2018 24.01.2019 10. Reason of Slow Moving: _____ 11No. of beneficiaries 12907 Persons Work is in progress.

1. Date of A.A: 04.04.2017. 2. Date of T.S: 10.04.2017 3. Date of Pre-Qualification: 4. Date of Invitation of Tender: 08.05.2017 5. Date of Receipt of Tender: 09.05.2017 6. Rural Sewerage / Drianage scheme chak Date of Work order: 25.11.2017 7. Date of 75 1678 Vehari 18.710 8.742 3.319 3.319 4.149 2.489 60% 11.231 60% Completion as per PC-I: 24.11.2018 8. No. 146/EB and Dalan, District Vehari Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= 20316 Persons Work is in progress.

Provision of water Supply Scheme in Kundi Dera Ghazi 76 1679 50.325 38.936 3.789 3.789 0.242 0.242 100% 39.178 78% "• Date of A.A = 22.08.2015 Wala UC shadan Lund Khan Provision of water Supply Scheme in Dera Ghazi 77 1680 47.463 29.182 5.834 5.834 0.076 0.076 100% 29.258 62% "• Date of A.A = 22.08.2015 Notak Sakhani UC Kala Khan Provision of water Supply Scheme in Dera Ghazi 78 1681 36.579 28.136 2.556 2.556 0.117 0.117 100% 28.253 77% "• Date of A.A = 22.08.2015 Sabzani UC Kala Khan Extension & Augmentation of water Supply Dera Ghazi 79 1682 87.805 77.753 0.333 0.333 0.250 0.245 98% 77.998 89% "• Date of A.A = 16.12.2014 Scheme Sakhi Sarwar Khan Provision of Rural water Supply Scheme Dera Ghazi 80 1683 82.680 59.914 7.577 7.577 5.683 5.569 98% 65.483 79% "• Date of A.A = 23.09.2016 Nutkani, District D.G. Khan Khan water Supply Scheme at Councilor Dera Ghazi 81 1684 25.000 24.000 0.333 0.333 0.250 0.245 98% 24.245 97% "• Date of A.A = 23.09.2016 Muhammad Ali Basti Rojhani Sakhi Sarwar Khan Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Reheblitiation/Extension of Water Supply Scheme Tunga Menhal Phase-II (Basti Dera Ghazi 82 1685 Ouroo, Basti Jora, Basti Rind, Basti Bun 20.000 4.844 5.051 5.051 3.788 3.712 98% 8.556 43% "• Date of A.A = 25.7.2017 Khan Dhola, Basti Gabolan, Basti Manka & Basti Mahool jee) Rehabilitation of Water Supply in Pir Qatal Dera Ghazi 83 1686 10.000 4.998 1.667 1.667 1.250 1.225 98% 6.223 62% "• Date of A.A = 25.7.2017 PP-244 District Dg Khan Khan Rehabilitation of Water Supply in Shehzada Dera Ghazi 84 1687 10.000 4.000 2.000 2.000 1.500 1.470 98% 5.470 55% "• Date of A.A = 25.7.2017 Sultan Town PP-244 District Dg Khan Khan Rehabilitation of Water Supply in Mehboob Dera Ghazi 85 1688 10.000 4.999 1.667 1.667 1.250 1.225 98% 6.224 62% "• Date of A.A = 25.7.2017 Abad PP-244 District Dg Khan Khan Improvement of Rural water Supply 86 1689 Rajanpur 228.679 217.875 3.601 3.601 2.701 2.701 100% 220.576 96% "• Date of A.A = 23.12.2014 Scheme Dajal water Supply Schemes in Mouza Fateh 87 1690 Muzaffargarh 70.000 18.680 4.173 4.173 3.130 3.128 100% 21.808 31% Work is in progress Pur and Ali Pur District Muzaffargarh Date of AA(DDWP) 06.10.2015. Date of TS. Provision of Fund for Restortaion of water 22-02-2016Date of invitation of tenders=28- 01-2016Date of receipt of tenders = 02-03- Supply Scheme in his Constituency District Bahawalnaga 2016Date of award= 30-04-2016Date of 88 1691 Bahwalnagar (i) RWSS Khattan,(ii) RWSS 67.817 49.499 5.339 5.339 1.048 1.048 100% 50.547 75% completion 29-04-2018. Date of receipt of r Jananay wala, (iii) RWSS Ghulab Ali,(iv) funds by F.D. 20.07.2018 & 11.01.2019. Completed & handed over on 31-12-2019. RWSS Bajak & Khamay Wala Excess funds Rs.2.956 million surrendered dated 19.10.2018 & 26-03-2019.

Date of A.A: 22-01-2015. . Date of T.S 26- 01-2015.. Date of work order= 22-05-2015. Date of completion as per agreement= 21- 11-2015.Anticipated date of completion= 09- 02-2016. Scheme Completed in saving and handed over to CBO on 09-02-2016. Contractor liability cleared.. Tube well 0.25 Cusec = 3 Nos/100%. Pump House 12x12 = 3 Nos/ 100%. Pumping Machinery = 3 Set/3 Set. OHT Line = 5 Job/ 5Job. Rising Rehabilitation of Rural water Supply Bahawalnaga Main . 6” Dia PVC Pipe B Class = 29900 89 1692 Scheme Chak No 62 4R Tehsil 38.959 36.550 0.320 0.320 0.240 0.240 100% 36.790 94% Rft/29114 Rft. 6” Dia PVC Pipe C Class = r Haroonabad District Bahawalnagar 19200 Rft/19200 Rft. 6” Dia PVC Pipe D Class = 3280 Rft/3280 Rft. 4” Dia PVC Pipe D Class = 500 Rft/ 417 Rft. Distribution System. 5” Dia PVC Pipe B Class = 6442 Rft/3611 Rft. 4” Dia PVC pipe B Class = 3316Rft./ 3316Rft. 4” Dia PVC pipe D Class = 1500Rft./ 1499Rft. 3” Dia PVC Pipe B Class = 44470Rft/ 44470Rft. GST 20000 Gallons Capacity =2Nos/ 2Nos. Pumping Chamber for G.S.T 2Nos /2Nos. Pumping Machinery for G.S.T = 3 Sets/3 Sets

Date of AA. 08.08.2016.Date of T.S. 21.10.2016.Tender received on 02.11.2016.Date of award. 25.11.2016Date Rehabilitation of rural water Supply of completion 24.11.2017.Anticipated date Bahawalnaga 90 1693 scheme chak no. 69/4-R, 80/1-L & Azafi 39.568 38.934 0.211 0.211 0.054 0.054 100% 38.988 99% of completion 10-03-2018Date of receipt of r funds by F.D. 20.07.2018 & Abadis Chak No. 85/5-R 11.01.2019.Scheme completed & handed over to CBO on 10-03-2018. Excess funds Rs.0.104 million surrendered dated 19.10.2018 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA. 19.08.2016.Date of T.S. 25.10.2016.Date of receipt of tenders= 14- Rehabilitation of Rural water Supply Bahawalnaga 12-2016 Date of award=29-12-2016Date of 91 1694 Schemes Muga Chandna Mirdin Hakim 99.971 53.035 6.667 6.667 5.000 5.000 100% 58.035 58% completion=28-11-2017Anticipated date of r Mirdin Mohib Ali Khazan Singh completion 30-06-2021Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress

Date of AA(DDWP). 18-08-2015 .Date of TS. 06-10-2015.Date of receipt of tenders = 20-10-2015 Date of work order= 04.11.2015. Date of completion as per Rural water Supply Scheme Jand wala and Bahawalnaga agreement= 03.11.16. .Anticipated date of 92 1695 25.000 19.550 1.817 1.817 0.259 0.259 100% 19.809 79% completion 31-12-2018. Date of receipt of Jand wala sani r funds by F.D. 20.07.2018 & 11.01.2019. Scheme Completed in saving & handed over on 31-12-2018. Excess funds Rs.1.104 million surrendered dated 19.10.2018 & 26- 03-2019.

Date of AA (DDSC). 15-10-2015.Date of TS. 22-02-201`6Date of prequalification on 22-03-2016Date of receipt of tenders = 07- 04-2016Date of work awarded Bahawalnaga 93 1696 water Supply Scheme Doonga Boonga 174.252 120.139 6.667 6.667 4.700 4.700 100% 124.839 72% 18.05.2016.Date of completion as per r Agreement: 18.11.2017 .Anticipated date of completion 30-06-2021.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.0.300 million surrender on 26-03- 2019. Work is in progress.

Date of AA. 19.08.2016.. Date of T.S. 25.10.2016. Date of award +19-01-2017. Date of completion+18-12-2017.. Anticipated date of completion 30-06-2021. Funds Rs.2.550 million surrendered through re-appropriation by CE(S), PHED Lahore on 16-04-2019. Work is in progress.. Trial Bore = 5 Nos./100%. Tube Well 0.50 Cusec = 5 Nos./100%.. Pump House 12x12 = 5 Nos./Nil. Pumping Machinery = 5 Set./Nil. Rural water Supply Schemes Mouza Janu Bahawalnaga O.H.T Line = 3 Job/ D.N Paid. 4" Dia PVC 94 1697 Khan Basti Kapooran and kot Ganga Singh 97.808 43.343 6.667 6.667 2.450 2.450 100% 45.793 47% Pipe Class-B = 2932 Rft/2932. 5" Dia PVC r District Bahawalnagar Pipe Class-B = 1372 Rft/1372. 6" Dia PVC Pipe Class-B = 47521 Rft/13700. 8" Dia PVC Pipe Class-B = 37891 Rft/25870. 8” Dia PVC Pipe Class-B = 30 Rft/30. 6” Dia PVC Pipe Class-B = 3955 Rft/Nil. 4" Dia PVC Pipe Class-B = 42885 No./9000. 3" Dia PVC Pipe Class-B = 105998 No./32000. Ground storage Tank = 4 No./Nil. Pumping Chamber = 4 No/ Nil. Pumping Machinery for GST = 4 No / Nil. Maintenance = 4 Job/Nil

Date of AA(DDWP). 06.10.2015. Date of TS. 22-02-2016Date of receipt of tenders = 02-03-2016Date of work order=01-04- water Supply Scheme Noor Sar (New & Bahawalnaga 2016Date of completion as per agreement= 95 1698 72.817 42.617 3.333 3.333 0.200 0.200 100% 42.817 59% 30-10-2017.Anticipated date of completion Old) r 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. funds Rs.2.300 million surrnder on 26-03-2019. Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA. 08.08.2016.Date of T.S. 21.10.2016.Tender received on 02.11.2016.Date of award. 28.11.2016Date of completion 27.11.2017.Anticipated date Rural water Supply scheme chak no. 128/6- Bahawalnaga 96 1699 22.200 20.273 0.536 0.536 0.134 0.134 100% 20.407 92% of completion 14-05-2018Date of receipt of R including all adjoining abadies. r funds by F.D. 20.07.2018 & 11.01.2019. Scheme completed in saving & handed over to CBO for O & M on 14-05-2018 Excess funds Rs.0.268 million surrendered dated 19.10.2018.

1. Date of AA = 15.12.2016 2. Date of TS = 23.12.2016 3.Date of Award of work . 19.05.2017 4.Dated of Released Funds 4. No. of Beneficiaries = 5375 Persons Pump House= 1 NoTube Wells 0.5 Cusic= 1 No 8"i/d B PVC Pipes= 300-Rft6"i/d B PVC Rural water Supply Scheme, Kalowal Pipes= 3508-Rft 4"i/d B PVC Pipes= 4540- 97 1700 Thathi Bala Raja Tehsil Lalian District Chiniot 13.322 6.430 2.297 2.297 1.723 1.550 90% 7.980 60% Rft3"i/d B PVC Pipes= 6050-Rft Pumping Chiniot Machinery= 1 Set.Boundary Wall= 425-Rft Transmission Line= 1 Job.OHR= 1Job.O&M= 1 JobFunds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Progress slow due to site problem. Lat 31.910034 Long 73.0598481

Rehabilitation and Repair of Sewerage Date of A.A : 01-10-2016.Date of T.S: 28-01- 98 1701 Scheme of Housing Scheme , Gujar Khan Rawalpindi 29.980 15.158 3.333 3.333 4.100 4.100 100% 19.258 64% 2017.Date of Start: 27-03-2017.Date of City, Tehsil Gujar Khan, District Rawalpindi Completion:30-06-2020.Work in progress.

Drainage / Sewerage System in Village A.A Date 03.09.2014. T.S Date 29.09.2014. Date of Start of Scheme 16.12.2014. Date 99 1702 Ghourgushti (Phase II), Tehsil Hazro, Attock 88.786 85.975 0.937 0.937 0.703 0.703 100% 86.678 98% of Completion of Scheme 30.06.2019. Work District attock is in progress. A.A Date 01.10.2013. T.S Date 27.01.2014. Drainage and Sanitation scheme in village 100 1703 Attock 44.134 26.243 5.960 5.960 1.490 0.000 0% 26.243 59% Date of Start of Scheme 06.03.2014.Date of Hameed, Tehsil Hazro, District attock Completion of Scheme 30.06.2019.Dispute of land. Construction of Street Pavement in Village A.A Date 23.01.2015. T.S Date 18.04.2015. Date of Start of Scheme 05.06.2015. Date 101 1704 Kalu Kalan (Phase II), (PP 16) Tehsil Hazro Attock 26.227 24.730 1.497 1.497 1.408 1.408 100% 26.138 100% of Completion of Scheme 30.06.2019. Work District attock is in progress.

A.A Date 05.08.2016. T.S Date 15.08.2016. Extension of Rural Drainage Scheme in 102 1705 Attock 60.055 46.834 4.405 4.405 3.304 3.300 100% 50.134 83% Date of Start of Scheme 28.11.2016. Date Villages Haroon, Saleem Khan & Adalzai of Completion of Scheme 30.06.2019. Work is in progress.

A.A Date 12.04.2017.T.S Date 18.04.2017. Rural Drainage Scheme in Villages Chachi, 103 1706 Attock 29.955 20.816 3.046 3.046 2.285 2.285 100% 23.101 77% Date of Start of Scheme 10.06.2017.Date of Saiden, Yasin Completion of Scheme 30.06.2019. Work is in progress.

A.A Date 05.08.2016. T.S Date 09.09.2016. Rural drainage Scheme in Village Mirza 104 1707 Attock 104.909 28.955 6.667 6.667 5.000 5.000 100% 33.955 32% Date of Start of Scheme 16.03.2017. Date Phase2 Tehsil and District attock. of Completion of Scheme 30.06.2019. Work is in progress.

A.A Date 01.04.2016.T.S Date 22.04.2016. Rural drainage scheme in villages 105 1708 Attock 55.840 42.497 4.448 4.448 3.336 3.336 100% 45.833 82% Date of Start of Scheme 30.05.2016. Date Formli,haider Mallah,District attock. of Completion of Scheme 30.06.2019. Work is in progress.

A.A Date 01.04.2016. T.S Date 09.09.2016. Rural drainage scheme in villages Perzai, 106 1709 Attock 29.604 26.725 0.602 0.602 0.882 0.879 100% 27.604 93% Date of Start of Scheme 24.11.2016. Date Muraria, Pandak, District attock of Completion of Scheme 30.06.2019. Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

A.A Date 01.04.2016. T.S Date 20.04.2016. Rural drainage scheme in villages 107 1710 Attock 29.208 28.717 0.491 0.491 0.368 0.368 100% 29.085 100% Date of Start of Scheme 31.05.2016. Date Ramu,Bhadar Khan,District attock of Completion of Scheme 30.06.2019. Work is in progress.

A.A Date 05.08.2016. T.S Date 15.08.2016. Rural drainage scheme in villages, , 108 1711 Attock 55.106 26.472 3.333 3.333 3.670 3.660 100% 30.132 55% Date of Start of Scheme 24.11.2016. Date Khagwani, District attock of Completion of Scheme 30.06.2019. Work is in progress.

Date of A.A 17.09.2015.Date of T.S Const. of Sewerage & Drainage Scheme 109 1712 Chakwal 98.759 47.426 3.333 3.333 7.825 7.820 100% 55.246 56% 08.10.2015.Date of Start 18.03.2016.Date of Kallar Kahar completion 31.12.2019. Work is in progress.Scheme is short funded. Date of A.A 20.04.2017.Date of T.S Rural Drainage Scheme Mangwal District 110 1713 Chakwal 11.000 9.773 0.392 0.392 0.000 0.000 #DIV/0! 9.773 89% 22.04.2017.Date of Start Chakwal 12.06.2017.Scheme completed. Excessive funds re-appropriated. Date of A.A 20.04.2017.Date of T.S Rural Drainage Scheme UC Udherwal 111 1714 Chakwal 14.000 12.424 0.482 0.482 0.000 0.000 #DIV/0! 12.424 89% 22.04.2017.Date of Start District Chakwal 10.06.2017.Scheme completed. Excessive funds re-appropriated. Date of A.A 20.04.2017. Date of T.S Rural Drainage Scheme UC Nara Mogla 112 1715 Chakwal 11.000 9.563 0.476 0.476 0.000 0.000 #DIV/0! 9.563 87% 22.04.2017.Date of Start District Chakwal 08.06.2017.Scheme completed. Excessive funds re-appropriated. Date of A.A 24.08.2016.Date of T.S 113 1716 Sewerage Scheme Lawa, District Chakwal Chakwal 78.169 49.975 3.333 3.333 2.500 2.500 100% 52.475 67% 01.11.2016.Date of Start 23.12.2016.Date of completion 31.12.2019.Work in progress.

Date of A.A 24.08.2016.Date of T.S 01.11.2016.Date of Start 16.01.2017.Date of completion 30.06.2020.Full funds utilized. 114 1717 Rural Drainage Scheme Khanpur Chakwal 150.000 52.462 5.000 5.000 8.416 8.415 100% 60.877 41% Scheme is short funded. Additional funds amounting to Rs.13 Million are requierd to clear contractor liabilities. Date of A.A 16-03-16.Date of T.S 28-03- Improvement/Rehabilitation of Sewerage 2016.Revised T.S 18-10-2017.Date of 115 1718 System in Bilal Town Tehsil & District Jhelum 29.800 27.764 0.676 0.676 0.000 0.000 #DIV/0! 27.764 93% Commencement 07-05-2016.Scheme Jhelum Completed in saving funds are reappropriated to other scheme. Scheme shall be completed by 30-06- Rural drainage scheme Pinanwal, Tehsil 2020.Balance funds required Rs. 76.936 116 1719 Jhelum 100.000 19.985 3.333 3.333 2.500 2.500 100% 22.485 22% million.Date of A.A 26-08-2016.Date of T.S Pind Dadan Khan. 15-12-2016. Work awarded on 02-03-2017. Work in progress.

Date of A.A 27.08.2016, Date of T.S 03.09.2016, Date of Award 06.12.2016, Scheduled date of Completion on 05.12.2017, Date of Commencement, Sewerage scheme Mouza Ahmaday Wala 117 1720 Sargodha 23.426 19.959 1.149 1.149 0.575 0.575 100% 20.534 88% 06.12.2016, Funds released on 30.07.2018, District Sargodha Funds on-lined on 30.07.2018.Sullage Carrier 3250-Rft & Drain 9841-Rft constructed. PCC Slab 18393-Cft & Soling 19458-Cft laid. Work in progress.Latitude/Longitude 31.59°/73.02° Date of A.A 27.08.2016, Date of T.S 03.09.2016, Date of Award 08.12.2016, Scheduled date of Completion on Sewerage/Sullage Carrier for Jalpana/Chak 07.12.2017, Date of Commencement, 118 1721 Sargodha 30.000 20.807 2.795 2.795 2.096 1.969 94% 22.776 76% 08.12.2016, Funds released on 30.07.2018, Muzafarabad/Masar/Sardarpur etc. Funds on-lined on 30.07.2018.Sullage Carrier 12165-Rft & Drain 6240-Rft constructed. P.C.C slab 20390-Cft laid. Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 27.08.2016, Date of T.S 28.10.2016, Date of Award 14.02.2017, Scheduled date of Completion on RSD Scheme Chak No 4 SP Chak No 5 NB 13.02.2018, Date of Commencement, 119 1722 Chak No 7 ML Chak No 65 SB Hujjan Sargodha 105.642 44.397 3.333 3.333 2.500 2.500 100% 46.897 44% 14.02.2017, Funds released on 30.07.2018, District Sargodha Funds on-lined on 30.07.2018.Sullage Carrier 18500-Rft & Drain 8188-Rft constructed. Soling 19544-Cft laid. Work in progress. Date of A.A 27.08.2016, Date of T.S 07.11.2016, Date of Award 10.02.2017, Scheduled date of Completion on Rural Sewerage / Drainage PCC Scheme 09.02.2018, Date of Commencement, 120 1723 Sargodha 100.000 34.967 3.333 3.333 2.500 2.500 100% 37.467 37% 10.02.2017, Funds released on 30.07.2018, for Jhawarian Funds on-lined on 30.07.2018.6661-Rft, Nallah, Drain, 2866-Rft 01- No. collecting tank constructed. PCC slab 27375-Cft laid and Work in progress.

Date of A.A 27.08.2016, Date of T.S 28.10.2016, Date of Award 31.01.2017, Scheduled date of Completion on Rural Sewerage / Drainage Scheme 30.01.2018, Date of Commencement, 121 1724 Sargodha 84.030 28.600 3.333 3.333 2.500 2.500 100% 31.100 37% 31.01.2017, Funds released on 04.08.2017, Bhagtanwala Funds on-lined on 04.08.2017.Drain 9908- Rft & Sullage Carrier 7838-Rft constructed. P.C.C Slab 17860-Cft & Soling 5988-Cft laid. Work in progress. Construction / Rehablitation of streets, Drains , Nullah and Soling at Chak No.20- The nomenclature of scheme has been 122 1725 Sargodha 6.000 0.100 1.000 1.000 0.750 0.000 0% 0.100 2% corrected by the P&D Department on 18-03- Shumali, Chak No.61-Shumali & Village 2019.Funds yet not released. Lak, Tehsil & District Sargodha Date of AA 18.08.2017 Date of TS 11.09.2017 Date of award 22.01.2018 Date of completion 30.06.2020 RCC Sewer 9"i/d Provision of Sewerage System and PCC to 30"i/d 1785 laid +8560 arranged /36021 123 1726 Khushab 92.683 14.299 3.333 3.333 2.500 2.500 100% 16.799 18% Screening Chamber 85% complete Slabs in Village Roda. Collecting Tank 85% Complete PCC Slab 0/38116 Cft Work is in progress. Latitude 32.072514999999996, Longitude 72.10047166666666

Date of A.A.27-05-2016, Date of T.S.19-05- 2017, Date of Start of Work. 10-05-2017, Remarks. E.R.S=3/3, Tube Well=1/1, Pump House=1/1, P/Machinery= Arranged/1, Construction of Rural water Supply R/FMain= 6"i/d G.I Pipe=1150/1200, 4"i/d G.I Pipe= 2250/2250, 3"i/d G.I Pipe= 3012/ 124 1727 Scheme Marmandi Tehsil & District Mianwali 13.500 12.707 0.256 0.256 0.192 0.192 100% 12.899 96% 3020, 2"i/d G.I Pipe=1400/1400, 6"i/d PVC Mianwali Pipe=1960/1900, 3"i/d PVC= 9633/9805, G.S. Tank 20000-Glns=1/1, T/Line= Demand Notice paid to Wapda Connection awaited/1. Work is in progress.Latitude/Longitude: 32.27' / 71.56'

Date of A.A.27-08-2016, Date of T.S.09-12- 2016, Date of Start of Work.03-02-2017, Remarks RCC Sewer=9"i/d= 480- Arrange/20356, 12"i/d=1130-Rft Laid & 992- arranged /12812, 15"i/d= 728-Rft Laid & 630- 125 1728 Sewerage & Sanitation Scheme Daud Khel Mianwali 98.377 19.928 6.667 6.667 5.000 4.998 100% 24.926 25% Arranged /6645, 18"i/d=1850-Rft Laid/3348, 21"i/d=832-Arranged/1768, 24"i/d= 1573/4870, 27"i/d=3841/5505, 33"i/d=2294/3128, S/Carrier=0/200, PCC Slab= 6514 /33597. Work is in progress.Latitude/Longitude: 32.67' / 71.28' Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of A.A.27-08-2016, Date of T.S.06-10- 2016, Date of Start of Work.22-12-2016, Sewerage & Sanitation Scheme Shahbaz Remarks RCC Sewer=9" i/d=15294/33286, 126 1729 Mianwali 95.743 29.964 6.667 6.667 5.000 4.999 100% 34.963 37% 12"i/d= 14502/21045, 15"i/d= 3381/3659, Khel 21"i/d= 766/864, 24"i/d=2253/2445, PCC Slab= 0/62379. Work is in progress.Latitude/Longitude: 32.60' / 71.52

Date of A.A.04-08-2015, Date of T.S.14-09- 2015, Date of Start of Work 16-11-2015, Sewerage / Drainage Scheme Mouch, Remarks RCC Sewer=9" i/d=24628/35130, 127 1730 Mianwali 100.000 46.431 7.856 7.856 7.492 7.461 100% 53.892 54% 12"i/d= 19774/ 12053, 15"i/d= 3476/4564, District Mianwali 18"i/d=5720/4902, 21"i/d= 1608 /1126. Sullage Carrier= 230/2411. Work is in progress.Latitude/Longitude: 32.74' / 71.50'

Date of A.A.27-08-2016, Date of T.S.03-09- 2016, Date of Start of Work 03-12-2016 Remarks RCC Sewer=9" i/d=10551/13484, 128 1731 Sewerage / Drainage Scheme UC Rokhari Mianwali 50.000 22.466 4.476 4.476 3.357 3.355 100% 25.821 52% 12"i/d= 10290/7642, 15"i/d= 5982/6288, 18"i/d=1372/1299, Sullage Carrier= 100/200. Work is in progress.Latitude/Longitude: 32.88' / 71.55'

Date of A.A. 27-08-2016, Date of T.S.09-12- 2016, Date of Start of Work.27-01-2017, Remarks RCC Sewer=9"i/d =2200-Rft Arranged/19157,12"i/d= 6000-Rft Arranged/8786,15"i/d=2539-Rft Laid /2826,18"i/d= 655-Rft Laid /1624, Rural Sewerage Scheme Harnoli Tehsil 21"i/d=1173-Laid /1356 ,24"i/d=1267/1329, 129 1732 Mianwali 94.000 44.953 5.000 35.000 33.750 3.750 11% 48.703 52% 30"i/d=380-Rft Laid/392, Screening Piplan, Mianwali Chamber =1/1, Collecting Tank 20'dia =1/1,Control Room= 1/1,Discharge Sump=0/1, P/Machinery=0/2, S/Carrier=0/1250, S/Drain= 600/4175, PCC Slab=111243 /142412, Culvert=0/1, Electric T/Line =0/1. Work is in progress.Latitude/Longitude: 32.97' / 71.45'

PCC Slab and Sewerage Scheme in Street Date of A.A 27.08.2016 Date of T.S 03.09.2016 Date of Commencement 130 1733 Noon Dager UC Tehsil Kaloor Kot District Bhakkar 48.600 29.681 3.333 3.333 2.500 2.500 100% 32.181 66% 28.11.2016 Date of completion 31.12.2019 Bhakkar (Latitude 32.1575°/ Longitude 71.2696°)

PCC Slab and Sewerage Scheme Shahyan Date of A.A 27.08.2016 Date of T.S 03.09.2016 Date of Commencement 131 1734 Wala U.C Noora Sharif Tehsil Kaloor Kot Bhakkar 30.000 14.397 3.333 3.333 2.500 2.000 80% 16.397 55% 09.11.2016 Date of completion 31.12.2019 District Bhakkar (Latitude 32.0762°/ Longitude 71.6021°)

Date of A.A 10.08.2017 Date of T.S Provision of Sewerage/Drainage/Nali UC 132 1735 Bhakkar 30.000 7.000 3.333 3.333 2.500 2.500 100% 9.500 32% 21.10.2017 Date of Commencement Mullah Wali 03.11.2017 Date of completion 30.06.2020 (Latitude 31.6062°/ Longitude 71.0854°)

Date of A.A 10.08.2017 Date of T.S Provision of Sewerage/Drainage/Nali UC 133 1736 Bhakkar 30.000 10.000 6.667 6.667 5.000 4.480 90% 14.480 48% 21.10.2017 Date of Commencement Peerashab 03.11.2017 Date of completion 30.06.2020 (Latitude 31.6062°/ Longitude 71.0854°)

Sewerage Drainage and PCC Slab and Date of A.A 27.08.2016 Date of T.S 21.10.2016 Date of Commencement 134 1737 Drain in Town Punjgrain Tehsil Darya Khan Bhakkar 100.000 46.648 6.667 6.667 6.820 6.820 100% 53.468 53% 24.11.2016 Date of completion 30.06.2020 District Bhakkar. (Latitude 31.7876°/ Longitude 71.1092°) Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of A.A 27.08.2016 Date of T.S Rural Sewerage Drainage Scheme PCC 135 1738 Bhakkar 49.998 18.599 3.333 3.333 2.500 2.500 100% 21.099 42% 03.09.2016 Date of Commencement Slab and Brick Pavement in Behal City 03.11.2016 Date of completion 30.06.2020 (Latitude 31.4149°/ Longitude 71.0082°)

Date of A.A 27.08.2016 Date of T.S Rural Sewerage Drainage Scheme PCC 136 1739 Bhakkar 39.022 17.991 3.333 3.333 2.500 2.500 100% 20.491 53% 03.09.2016 Date of Commencement Slab and Brick Pavement in Notak City 28.11.2016 Date of completion 30.06.2020 (Latitude 31.4735°/ Longitude 71.0319°)

Date of A.A= 29-08-2017. Date of T.S.=05- 09-2017. No. of Beneficiaries= 3822 Rural drainage Scheme inculding Tuff Tiles Anticipated date of completion=01.01.2018 and Water Supply Lines for left over streets Investigation of source= Drainage • Surface 137 1740 Faisalabad 10.000 5.000 1.667 1.667 1.250 1.080 86% 6.080 61% Drain =623/2450-Rft • Sullage Carrier for Chak No 411/GB darbar Peer Kandhari 1.5x1.5 =1373/1450-Rft • Sullage Carrier tehsil Tandlianwala District Faisalabad 2x2 =0/800-Rft • Tuff tile =16066/ 35000-Sft • Distribution System 3" i/d =6928/ 6100-Rft • Work in progress

Date of A.A =05-08-2017.Date of T.S.=05- 09-2017. No. of Beneficiaries= 6759 Construction of Drainage Nala at Chak .Anticipated date of completion=31.10.2018 138 1741 No. 197/RB Wahga Wala Tehsil Saddar, Faisalabad 3.000 2.000 0.333 0.333 0.250 0.215 86% 2.215 74% .Investigation of source= Drainage. Surface District Faisalabad Drain =0/220 Rft• Sullage Carrier =2500/2629 Rft • Brick Pavment = 0/801 Cft • Work in progress Date of A.A 29-08-2017.Date of T.S.05-09- Construction of Rural Drainage and PCC 2017. No. of Beneficiaries = - Surface Drain- 139 1742 Faisalabad 10.000 1.000 3.000 3.000 2.250 2.005 89% 3.005 30% 1520/-Rft, Brick Pavement 9464/12593- Road , UC 63 District Faisalabad CFT,Sullage Carrier 7200/-Rft, Work is in progress. Date of A.A 29-08-2017.Date of T.S.05-09- Construction of Rural Drainage and PCC 2017. No. of Beneficiaries = - Surface Drain- 140 1743 Faisalabad 10.000 1.000 3.000 3.000 2.250 2.225 99% 3.225 32% 4010/- Rft, Brick Pavement 40539/12070- Road at U.C. 52 District Faisalabad CFT, Sullage Carrier 850/-Rft, Work is in progress. AA Issued on 01-04-2015 date of T.S 18-10- 2016 ( Revised ) Work Order issued on 18- 05-2015.work is in Progress Fund Released on 23-11-2018.& 24-01- 2019.P0pulation=5782-Persons . Trial Bore Rehab: of Rural Water Supply Scheme =2/2 T/Well 0.25-Cusc =2/2-Nos . Pump 141 1744 Chak No. 228/GB Tehsil Sammundari Distt: Faisalabad 21.240 18.698 2.542 2.542 1.907 1.640 86% 20.338 96% House 12x12 =2/2-Nos P/machiewnry =2/2- Faisalabad (Court Case) Sets R/Main 6"i/d =3975/4000-Rft 6" B- Class =8380/8400-Rft D/System 3"i/.d =33916/34290-Rft 4"i.d=6280/6294-Rft 6"i/d =2534/2548-Rft Hypo Chlorinator =1/1 No.E/Transmission Line=2/Jobs .O.H.R 10000-Glns = 1/1 No. AA issued on 16.03.2017 .Date of T.S 31.03.2017 08.06.2017.No. of Beneficiaries Construction of sewerage drain at Chak =10925 RCC Sewer 9'' i/d, 8226/7963-rft, 142 1745 Faisalabad 59.879 42.328 1.000 1.000 0.750 0.640 85% 42.968 72% PCC-57248/11567-cft, Surface Drain- No.469/GB, Samundri, District Faisalabad 11960/-Rft, Brick Pavement 1019/-CFT, Sullage Carrier 1730/500- Rft, ork is in progress. Construction of TST Road (2200 feet) at Chak No. 353/GB Kot Kabir, (Cahk No. 143 1746 Faisalabad 4.000 1.000 1.000 1.000 0.750 0.750 100% 1.750 44% Funds transfer to xen Highway Divison 353/GB to New Abadi) at District Faisalabad. Faisalabad Widening / improvement of at TST Road Funds transfer to xen Highway Divison 144 1747 from 12 feet to 20 feet Chak No.353 to 354 Faisalabad 10.000 4.500 1.000 1.000 0.750 0.750 100% 5.250 53% Faisalabad. at District, Faisalabad AA issued on 15.11.2017. Date of TS. No. Provision of Soling/Drainage at Kannal 145 1748 Faisalabad 2.500 0.479 1.000 1.000 0.750 0.748 100% 1.227 49% of Beneficiaries =9466 .Surface Drain- Awan and Abadies District Faisalabad. 500/250-Rft,Brick Pavement 12249/1929- CFT, Work is in progress.. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of Soling/Drainage at UC No. 50 AA issued on 15.11.2017. Date of TS, No. 146 1749 Faisalabad 2.000 1.000 1.000 1.000 0.750 0.640 85% 1.640 82% of Beneficiaries =3486.Surface Drain-840/- Chak No.144/GB District Faisalabad Rft, Brick Pavement 8627/5507-CFT, Provision of Soling /Drainage at Bhaman AA issued on 15.11.2017. Date of TS, No. of Beneficiaries =9466.Surface Drain- 147 1750 Da Chak and Pathan Da Goth District Faisalabad 2.000 1.000 1.000 1.000 0.750 0.645 86% 1.645 82% 500/250-Rft,Brick Pavement 12249/1929- Faisalabad. CFT, Work is in Progress. Date of A.A 15-11-2017.Date of T.S.22-11- 2017. No. of Baeneficiaries= 4593 Provision of Soling/Drainage Chak 148 1751 Faisalabad 1.000 0.499 0.501 0.501 0.376 0.320 85% 0.819 82% Anticipated Date of Completion=21/11/2018 No.651/2 GB District Faisalabad Surface Drain=2145/1150 Rft.Brick Pavement= 174/2730 Cft.Work is in progress. Date of A.A 15-11-2017.Date of T.S.22-11- Provision of Soling /Drainage at Chak 2017.No. of Baeneficiaries= 5867 Anticipated Date of Completion=21/11/2018 149 1752 No.653/4 GB Abadies Karam Chand and Faisalabad 2.500 0.998 1.502 1.502 1.127 1.123 100% 2.121 85% Surface Drain=2074/2950 Rft.Brick abadi Plots District Faisalabad. Pavement= 9046/6770 Cft.Work is in progress. Date of A.A 15-11-2017.Date of T.S.22-11- Provision of Soling/Drainage Chak 2017.No. of Baeneficiaries= 2518 150 1753 Faisalabad 1.000 0.500 0.500 0.500 0.375 0.319 85% 0.819 82% Anticipated Date of Completion=21/11/2018 No.652/3GB District Faisalabad Surface Drain=0/900Rft.Brick Pavement= 4381/3276 Cft.Work is in progress. Construction of TST Road Jhangar Awan 151 1754 Faisalabad 5.000 1.500 1.000 1.000 0.750 0.750 100% 2.250 45% Funds transfer to xen Highway Divison and Abaedies District, Faisalabad. Faisalabad. Date of A.A 15-11-2017.Date of T.S.22-11- 2017.No. of Baeneficiaries= 4475 Provision of Soling/Drainage Chak 152 1755 Faisalabad 1.000 0.471 0.529 0.529 0.397 0.340 86% 0.811 81% Anticipated Date of Completion=21/11/2018 No.147/GB District Faisalabad Surface Drain=1138/900Rft.Brick Pavement= 2512/3276 Cft.Work is in progress. Date of A.A 15-11-2017.Date of T.S.22-11- 2017. No. of Baeneficiaries= 4990. Provision of Soling /Drainage at Chak Anticipated Date of 153 1756 Faisalabad 2.000 0.500 1.500 1.500 1.125 0.970 86% 1.470 74% Completion=21/11/2018.Surface.Drain=102 No.144/GB District Faisalabad. 6/760Rft. Brick Pavement= 2722/1893 Cft.SULLAGE Carrier= 540/1050 Cft .Work is in progress. Date of A.A 15-11-2017.Date of T.S.22-11- 2017.No. of Baeneficiaries= 5251 Provision of Soling /Drainage at Chak 154 1757 Faisalabad 2.500 0.997 1.503 1.503 1.127 1.123 100% 2.120 85% Anticipated Date of Completion=21/11/2018 No.145/GB District Faisalabad. Surface Drain=145/2900Rft.Brick Pavement= 11394/6734 Cft.Work is in progress. Date of A.A 15-11-2017.Date of T.S.22-11- Provision of Soling/Drainage Chak 2017.No. of Baeneficiaries= 2387 Anticipated Date of Completion=21/11/2018 155 1758 No.459/GB Bhooli de Jhok District Faisalabad 1.500 0.479 1.021 1.021 0.766 0.650 85% 1.129 75% Surface Drain=783/1500 Rft.Brick Faisalabad Pavement= 6367/1274 Cft.Sullage Carrier= 0/550 Rft Work is in progress. Date of A.A 15-11-2017.Date of T.S.22-11- 2017. No. of Baeneficiaries= Provision of Soling/Drainage at UC No. 51 5890.Anticipated Date of 156 1759 Faisalabad 2.500 0.486 1.000 1.000 0.750 0.741 99% 1.227 49% Completion=21/11/2018.Surface Pind Essa Faisalabad Drain=0/1270 Rft.Brick Pavement= 6739/5897 Cft Sullage Carrier= 0/800 Rft.Work is in progress. Date of A.A 15-11-2017.Date of T.S.13-12- Provision of Soling /Drainage at Chak 2017.No. of Baeneficiaries= 6266 157 1760 No.569/Gb Abadi Abdullah Khan District Faisalabad 3.500 0.988 1.000 1.000 0.750 0.750 100% 1.738 50% Anticipated Date of Completion=12/12/2018 faisalabad. Surface Drain=0/3600 Rft.Brick Pavement= 8907/10301 Cft.Work is in progress.

Date of A.A 15-11-2017.Date of T.S.22-11- Provision of Soling /Drainage at 2017.No. of Baeneficiaries= 1628 158 1761 RosheShani Awana and Abadies District Faisalabad 1.000 0.389 0.611 0.611 0.458 0.454 99% 0.843 84% Anticipated Date of Completion=21/11/2018 Faisalabad. Surface Drain=0/900 RftBrick Pavement= 4649/3276 Cft.Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 15-11-2017.Date of T.S.22-11- 2017. No. of Baeneficiaries= 2965 Provision of Soling /Drainage at UC 45 Anticipated Date of 159 1762 Chak No.644/GB Abadi KaluKa Thatha and Faisalabad 2.000 0.475 1.525 1.525 1.144 0.970 85% 1.445 72% Completion=21/11/2018.Surface Saidpur District Faisalabad. Drain=2421/500 Rft.Brick Pavement= 5079/8390 Cft Sulagge Carrier = 0/150 rft.Work is in progress. Date of A.A 15-11-2017.Date of T.S.13-12- 2017. No. of Baeneficiaries= Provision Main Drainage at Chak 160 1763 Faisalabad 1.497 0.994 0.503 0.503 0.377 0.377 100% 1.371 92% 2295Anticipated Date of No.120/GB District Faisalabad. Completion=12/12/2018.Brick Pavement= 6065/6065 Cft .SULLAGE CARRIER= 350/1400 rft Work is in progress.

Date of A.A = 16.03.2017 • Date of TS = 24.03.2017 • No. of Beneficiaries = 22231- Persons • Anticipated date of completion = 30.06.2020 R. C. C. Sewer 9" i/d 1200./3400-Rft. 12" i/d 816/1728-Rft. 15" i/d 612/1686-Rft. 18" i/d 105./759-Rft. 21" i/d 407-Rft. 27" i/d 300./2660-Rft Screening Sewerage / Drainage Scheme Garh Mor, 161 1764 Jhang 81.940 20.000 8.333 8.333 6.250 6.250 100% 26.250 32% Chamber 1-No. Collecting Tank 1/ 2-Nos. Ahmedpur Sial Pumping Chamber 1-No. Pumping Machinery 2-Sets. Diesel Generator and Generator Room 1-No. Out Fall Chamber 1- No. Sullage Carrier 1.5 x 2 1500-Rft. Staff Quarter 1-No. Boundary Wall 735-Rft. Surface Drain 744/47230-Rft. Brick Pavement/PCC 6938/56200-Cft. Work in progress.

1-Date of A.A 20.10.2016 2- Date of T.S 11.11.2016 3- Anticipated date of completion 30.06.2020.4- No. of Beneficiary - 33312 Person RCC SEWER9” i/d = 12972/1500-Rft 12” i/d = 2967/1208-Rft15” i/d = 1193/814-Rft18” i/d = 485/520-Rft21” i/d = 95/24-Rft FORCE MAIN / SULLAGE CARRIERFORCE MAIN16"I/D =7900/0- RftSULLAGE CARRIER ALONG HOTAOR MINOR = 5085/0-RftSUMP WELL (8'X6') = Sewerage Drainage and Street Pavement, 3/0-No.PUMPING CHAMBER (20'DIA) = Toba Tek 162 1765 Sandhilianwali, District Toba Tek Singh 100.000 30.000 3.333 3.333 1.800 1.798 100% 31.798 32% 1/1-NoSCREENING CHAMBER = 1/1- Singh No.COLLECTING TANK= 1/1- Phase I No.PUMPING MACHINERY =2/0- SetINTER CONNECTION =2/0- Job.SURFACE DRAIN (TYPE-I) = 14280/7414-RftSTREET PAVEMENT = 52917/10852-CftBOUNDARY WALL = 400/0-RftSTAFF QUARTER =1/1-No.ROAD CROSSING = 1/0-JobDIESEL GENERATOR WITH GENERATOR ROOM = 1/1-NoELECTRIC TRANSMISSION LINE = 1/0-JobOPERATION & MAINTENANCE CHARGES = 1/0-Job Work in progress.

Construction of disposal Sewerage Drainage PCC Scheme Morr Eminabad 163 1766 Gujranwala 199.920 117.216 6.667 6.667 5.000 5.000 100% 122.216 61% Work in progress. Sharqi UC Dhillanwali Tehsil and Distt. Gujranwala Construction of Drains / PCC and 164 1767 Sewerage Scheme at UC Bhikhu Pura, Gujranwala 67.393 17.393 6.667 6.667 5.000 5.000 100% 22.393 33% Work in progress. District Gujranwala Construction of Drains / PCC and 165 1768 Sewerage Scheme at UC Shaheenabad, Gujranwala 64.261 19.260 5.000 5.000 3.750 3.750 100% 23.010 36% Work in progress. District Gujranwala Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) PCC and Sewerage Schemes at Khiali 166 1769 Gujranwala 198.537 153.991 20.000 20.000 21.218 21.218 100% 175.209 88% Bill with Held. Shahpur District Gujranwala. PCC Sewerage Drainage Scheme Disposal 167 1770 UC City Ladhywala Warraich Qila Dedar Gujranwala 149.647 140.598 3.016 3.016 8.262 8.262 100% 148.860 99% work completed Singh Madu Khalil Ghakh Provision of Sewerage Drainage and water 168 1771 Supply scheme in Qila Dedar Singh Gujranwala 196.624 138.865 6.667 6.667 5.000 5.000 100% 143.865 73% Work in progress. Gujranwala Provision of Sewerage, New Disposal & 169 1772 PCC at Kot Qazi & Mudhokhalil, Tehsil Gujranwala 186.266 89.505 30.000 30.000 22.500 22.500 100% 112.005 60% Work in progress. Saddar, Gujranwala Provision of Sewerage, New Disposal & 170 1773 PCC at Ladhay wala Warraich & Mughal Gujranwala 195.240 100.000 30.000 30.000 16.500 16.500 100% 116.500 60% Work in progress. Chak, Tehsil Saddar, Gujranwala Provision of Drainage PCC Facilities at UC 171 1774 Artali Virkan Tehsil Nowshera Virkan Gujranwala 30.000 19.958 3.335 3.335 2.501 2.501 100% 22.459 75% Work in progress. District Gujranwala Provision of Drainage PCC Facilities at UC 172 1775 Baddo Ratta Tehsil Nowshera Virkan Gujranwala 30.000 19.870 3.334 3.334 2.501 2.501 100% 22.371 75% Work in progress. District Gujranwala Provision of Drainage / PCC Schem at UC 173 1776 Gujranwala 77.757 19.999 3.333 3.333 2.500 2.500 100% 22.499 29% Work in progress. Chahal Kalan, District Gujranwala Drainage Sewerage and PCC UC atawa 174 1777 Gujranwala 280.818 151.994 14.117 14.117 10.588 10.588 100% 162.582 58% Work in progress. UC Rakh Kikran Wali PCC and Drainage Facility at 175 1778 Sadoki,Dargahapur and others in Tahsil Gujranwala 158.153 84.945 3.333 3.333 2.500 2.500 100% 87.445 55% Work in progress. Kamoki Provision of PCC/Drainage Sewerage 176 1779 Schemes at UC No 14, 15, 46, 50, 51, 52, Gujranwala 131.295 110.646 6.883 6.883 0.000 0.000 #DIV/0! 110.646 84% Scheme completed 53 Gujranwala Provision of PCC/Drainage/Sewerage 177 1780 Scheme at Municipal Committee, Ghakar Gujranwala 194.226 75.000 20.000 20.000 15.000 15.000 100% 90.000 46% Work in progress. Mandi Const. of disposal Sewerage Drainage PCC Scheme Morr Eminabad Gharbi Audo 178 1781 Gujranwala 178.291 99.864 6.667 6.667 5.000 5.000 100% 104.864 59% Work in progress. Rai UC Maraliwala Tehsil and Distt. Gujranwala Const. of Sewerage Drainage- PPC Soling in UCs Tehsil Noshera Virkan including 179 1782 Gujranwala 467.500 89.888 1.000 1.000 0.750 0.750 100% 90.638 19% Work in progress. UCs No. Wala Jhatan wali & Sahran Chahta Rural Drainage and PCC Scheme at Wandala Virkan Taly Aali Badhay new Abadi Gaibi Lunj Sharif Kolo wala, Matu 180 1783 Gujranwala 50.000 19.997 3.333 3.333 2.500 2.500 100% 22.497 45% Work in progress. Bhanake Al Ditta, Ratta Goraya, Chak Poryan ana Paryan, Karyal Khan and and Adjoining Dera Jattan. Rural Drainage PCC Scheme Kot Nisar 181 1784 Shah Boopara Khurd Dhairr Virkan Bhirri Gujranwala 109.270 46.942 6.667 6.667 5.000 5.000 100% 51.942 48% Work in progress. Shah Rehman Dharoke Sadu Sewerage Scheme Kamoke of Leftover 182 1785 Gujranwala 199.100 65.949 5.000 5.000 3.750 3.750 100% 69.699 35% Work in progress. Area Gujranwala Imrovement of Sewerage, Solling, Drain 183 1786 Gujranwala 103.000 10.000 20.000 20.000 15.000 15.000 100% 25.000 24% Work in progress. Tatley Aali Road Kamokay Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of PCC/Sewerage/Drainage/Solling etc. in 184 1787 Gujranwala 15.000 9.941 1.667 1.667 1.250 1.250 100% 11.191 75% Work in progress. village Chachoke Tehsil Noshera Virkan District Gujranwala Provision of PCC/Drainage Scheme in UC Kalaske, Kot Amar singh, Kot Shaira, Batla 185 1788 Gujranwala 197.800 19.996 30.000 30.000 22.500 22.500 100% 42.496 21% Work in progress. Janda Sigh, Uggu Chak Paponakha, UC 71 Khiyali # 14 MC Qila Didar Singh Provision of Clean Drinking 186 1789 Water/Sewerage Scheme at Ldhay wala Gujranwala 199.779 50.000 30.000 30.000 22.500 22.500 100% 72.500 36% Work in progress. Waraich, Madhu Khalil, Chain Wala etc Provision of Sewerage / Drainage and PCC 187 1790 Gujranwala 40.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 34% Work in progress. facilities Qila didar singh Gujranwala Provision of Sewerage Drainage and PCC 188 1791 Gujranwala 40.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 34% Work in progress. facilities Gakhar City Gujranwala Sewerage and PCC Scheme for Bismillah 189 1792 Colony Wania and Adjacent Area Gujranwala 105.000 96.046 2.985 2.985 2.239 2.239 100% 98.285 94% Bill with held Gujranwala RSD/ PCC Scheme UC Shamsa Dada UC 190 1793 Majju Chak UC Bhoopra Kalan UC Argan Gujranwala 168.000 46.983 3.333 3.333 2.500 2.500 100% 49.483 29% Work in progress. UC Philloke and UC Abidabad Gujranwala Rural Drainage/PCC Scheme in U.C. Garmula Virkan, U.C Budha Goraya, Dogranwala, U.C Phama Sara, Kalsian 191 1794 Gujranwala 109.270 29.914 5.000 5.000 3.750 3.750 100% 33.664 31% Work in progress. Dhutran, Kot Bilal and Madan Chak, Tehsil Nowshera Virkan, Dist. Gujranwala (Revised) Rural Drainage Scheme UC Kot Hassan 192 1795 Hafizabad 98.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 13% A.A. 98.000(M) T.S.98.000 (M) work is in Khan Kassoki Karyala & Allied Abbadies progress. Rural Drainage Scheme UC Chak Chattha A.A. 98.000(M) T.S.98.000 (M) work is in 193 1796 Sabir Kalan Kallian Wala & Allied Abbadies, Hafizabad 98.000 10.000 1.000 1.000 4.084 4.084 100% 14.084 14% progress. District Hafizabad * Org. A.A Date. 03.10.2011* Rev. A.A Drainage/Sewerage and water Supply Mandi 194 1797 102.080 73.238 3.333 3.333 1.600 1.600 100% 74.838 73% Date. 23.02.2013* T.S Date. 18.11.2011* Scheme of Mangat and Rasul Bahauddin Start Date 02.11.201132.706285,73.57570166666666 Construction of street, Drainage and Soling * A.A Date. 09.03.2017* T.S Date. Mandi 195 1798 of Kakka and Kot Jafar, Chak No.18 & 19, 6.500 5.737 0.167 0.167 0.100 0.100 100% 5.837 90% 10.03.2017* Start Date 12.04.2017* Bahauddin Completion date 30.06.2019.* Scheme District M.B.Din completed in saving. Construction of street, Drainage and Soling * A.A Date. 09.03.2017* T.S Date. Mandi 196 1799 of Khizar and Chak No.52, UC Chot 13.000 10.726 0.644 0.644 0.433 0.433 100% 11.159 86% 10.03.2017* Start Date 11.04.2017* Bahauddin Completion date 30.06.2019.* Work in Dheeran, District M.B.Din progress. Provision of Sewerage / Drainage / * A.A Date. 28.01.2015* T.S Date. Mandi 197 1800 Pavement in Halian & Ghanian, Tehsil 50.000 48.643 0.252 0.252 0.189 0.189 100% 48.832 98% 08.02.2015* Start Date 11.04.2015* Bahauddin Completion date 30.06.2019.* Work in Phalia progress.

Provision of Sewerage / Drainage / * A.A Date. 23.09.2016* T.S Date. Pavement in Jano Chak Khurd & Kalan , Mandi 198 1801 75.571 52.495 3.333 3.333 1.050 1.050 100% 53.545 71% 28.10.2016* Start Date 24.12.2016* Basi Khurd & Kalan, Channi Mast, Aado Bahauddin Completion date 30.06.2019.* Work in Sarwani. progress. Provision of Sewerage / Drainage / * A.A Date. 23.09.2016* T.S Date. Mandi 199 1802 Pavement in Narang / Saadullaha Pur / 64.664 50.171 4.824 4.824 1.568 1.568 100% 51.739 80% 28.10.2016* Start Date 24.12.2016* Bahauddin Completion date 30.06.2019.* Work in Khoosor progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Provision of Sewerage / Drainage / * A.A Date. 28.01.2015* T.S Date. Pavement in Sarlay,Lasoori Kalan,Duggal, Mandi 200 1803 50.000 44.765 1.579 1.579 0.394 0.394 100% 45.159 90% 08.02.2015* Start Date 11.04.2015* Phalia (Incl. THQ Hospital), Tehsil Bahauddin Completion date 30.06.2019.* Work in Pahila progress. * A.A Date. 07.09.2015* T.S Date. Rural Sewerage/Drainage scheme village Mandi 201 1804 90.500 79.269 3.744 3.744 2.808 2.808 100% 82.077 91% 10.09.2015* Start Date 17.12.2015* Bosal, Tehsil Malikwal, District M.B. Din Bahauddin Completion date 30.06.2019.* Work in progress. Rrural/Sewerage/Drainage Scheme pindi * A.A Date. 28.07.2017* T.S Date. Mandi 202 1805 Kalu Tehsil Phalian District Mandi 50.000 14.942 11.667 11.667 11.650 11.650 100% 26.592 53% 15.08.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2019* Work in bahauddin progress. * A.A Date. 23.09.2016* T.S Date. Sewerage Drainage Scheme UC Dhok Mandi 203 1806 20.000 19.500 0.166 0.166 0.104 0.104 100% 19.604 98% 24.09.2016* Start Date 23.12.2016.* Kasib Tehsil & District M B Din Bahauddin Completion date 30.06.2019.* Scheme completed in saving. * A.A Date. 23.09.2016* T.S Date. Sewerage & Drainage Scheme U.C Rasul Mandi 204 1807 20.000 19.421 0.184 0.184 0.099 0.099 100% 19.520 98% 24.09.2016* Start Date 21.12.2016.* Tehsil & District M.B.Din. Bahauddin Completion date 30.06.2019.* Scheme completed in saving. * A.A Date. 23.09.2016* T.S Date. Sewerage / Drainage of Village Rerka Mandi 205 1808 41.684 24.326 5.753 5.753 2.815 2.815 100% 27.141 65% 24.09.2016* Start Date 29.12.2016* Mumdana, Tehsil Malikwal Bahauddin Completion date 28.12.2019.* Work in progress Rural Sewerage, Drainage/Soling & PCC * A.A Date. 23.09.2016* T.S Date. Mandi 206 1809 Scheme in Chak No. 20 With Abadies 50.000 45.999 1.334 1.334 0.901 0.901 100% 46.900 94% 24.09.2016* Start Date 19.11.2016* Bahauddin Completion date 30.06.2019.* Work in Tehsil Malikwal Distt. M.B Din progress

Rural Sewerage, Drainage/Soling & PCC * A.A Date. 23.09.2016* T.S Date. Scheme in Villages Main Mandi Mona Mandi 207 1810 53.052 42.556 2.629 2.629 0.272 0.272 100% 42.828 81% 28.10.2016* Start Date 07.02.2017* Depot Pind Makko Tehsil Malilwal District Bahauddin Completion date 30.06.2019* Work in M.B.Din progress Rural Sewerage / Drainage Scheme of * A.A Date. 23.09.2016* T.S Date. Mandi 208 1811 Village Bherowal Tehsil Phalia Distt. Mandi 73.499 29.396 5.000 5.000 3.750 3.750 100% 33.146 45% 28.10.2016* Start Date 24.12.2016* Bahauddin Completion date 30.06.2019.* Work in Bahauddin progress Rural Sewerage / Drainage Scheme of * A.A Date. 23.09.2016* T.S Date. Mandi 209 1812 Village Khai and Bukkan Tehsil & Distt. 74.464 61.888 4.180 4.180 2.685 2.685 100% 64.573 87% 28.10.2016 * Start Date 06.12.2016* Bahauddin Completion date 30.06.2019.* Work in M.B. Din progress Rural Sewerage / Drainage Scheme Village * A.A Date. 07.09.2015* T.S Date. Mandi 210 1813 Kuthiala Sheikhan, Tehsil & District M.B. 55.150 45.574 3.192 3.192 0.979 0.979 100% 46.553 84% 10.09.2015* Start Date 17.12.2015* Bahauddin Completion date 30.06.2019.* Work in DIN progress

Sewerage / Drainage Schemes in Adda * A.A Date. 06.09.2017* T.S Date. Pharainwali, Sandhanwala, Haigerwala, Mandi 211 1814 247.904 79.958 6.667 6.667 1.600 1.600 100% 81.558 33% 24.10.2017* Start Date. 08.01.2018* Murala, Dhall, Dhola, Chhani, Lakhia, Chak Bahauddin Completion date 07.01.2021. Work in No. 38., and Ahdi in District M.B.Din progress. Provision of PCC / Sewerage / Drainage * A.A Date. 28.07.2017* T.S Date. Mandi 212 1815 and allied faiclities in PP-120, District 50.000 28.500 7.167 7.167 6.235 6.235 100% 34.735 69% 15.08.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2019* Work in M.B.Din progress. * A.A Date. 25.08.2017* T.S Date. Sewerage and Drainage scheme of Sahna Mandi 213 1816 100.000 22.099 8.333 8.333 6.950 6.950 100% 29.049 29% 07.09.2017* Start Date. 06.01.2018* and Khanana, District Mandi Baha Ud Din Bahauddin Completion date 05.01.2020. Work in progress. Construction of Brick Pavement PCC Street & Drain / Nullah U.C Mundeke, 214 1817 Ghuinke, Baddokey Cheema, Allomahar, Sialkot 50.000 29.900 1.667 1.667 1.250 1.250 100% 31.150 62% Work in progress. Jamke Cheema, Tehsil Daska District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC, Solling & Drain / Nullah UCs Head Marala, Machrala, Gondal, Bolwanwala , Pindi Punjorian, 215 1818 Sialkot 150.000 34.566 3.333 3.333 2.500 2.500 100% 37.066 25% Work in progress. Kaman Wala Kundan pur, Dallowali, Katchi Maund, Pholkin, Wadhgran Tehsil Sialkot District Sialkot Construction of RCC Sewer & RCC from Zohara Memorial Hospital Chowk to 216 1819 Railway Crossing to Ajmal Garden to Sialkot 175.320 87.576 6.667 6.667 5.000 5.000 100% 92.576 53% Work in progress. Shetab Garha to Adalat Pur road to Nullah Aik, Tehsil & District Sialkot Construction of Sewerage and Drainage 217 1820 Scheme Village Kapooro Wali Tehsil & Sialkot 30.000 24.983 1.667 1.667 1.250 1.250 100% 26.233 87% Work in progress. District Sialkot Provision of PCC / Soling / Nallain /Streets at Baigo wali bsmulla kot marth ,kot muhmmad hussain ,pipli wala ,begowala 218 1821 adda ,bhola musa kotli bawarian, kot kuda Sialkot 80.000 34.470 3.333 23.333 22.500 2.500 11% 36.970 46% Work in progress. yar ,kot qadar daad ,randeer ,bagrian ,chak kupa ,gulab garh, doburji chanda sing ,chowkey ,r Provision of PCC / Soling / Nallain /Streets Schemes at Malkhanwala Bshmula Wan, Pasia, Firdospur, Bangla Nai Abadi, Chak 219 1822 Sialkot 80.000 34.000 3.333 23.333 22.500 2.500 11% 36.500 46% Work in progress. Bassawa, Dhop Sari, Hameed Colony, Mehlowal, Abdullah abad, Dera Roshan Gujjar, Amreekh pura District Sialkot

Provision of PCC / Soling / Nullah / Street Scheme at Khambranwala Bashamula, 220 1823 Dogree, Gorian, Sundar Pur, Bidar, Chak Sialkot 60.000 34.403 3.333 3.333 2.500 2.500 100% 36.903 62% Work in progress. Simanwali etc., Tehsil Sambrial, District Sialkot [LO160068845]. Provision of PCC / Soling / Nullah / Street Scheme at Bakhray Wali Bashamula, 221 1824 Dogranwala, Kathiala, Habibpur etc., Sialkot 55.000 19.960 1.667 1.667 1.250 1.250 100% 21.210 39% Work in progress. Tehsil Sambrial, District Sialkot [LO16006884]. Provision of PCC / Soling / Nullah / Street Scheme at Kulowal Bashamula , Aurtala Sharif, Chak Mughal , Tika , Tambray, 222 1825 Sialkot 100.000 19.980 3.333 3.333 2.500 2.500 100% 22.480 22% Work in progress. Gaghar. Baseer, Jay, Ditowali, Chanigondal, etc., Tehsil Sambrial, District Sialkot Provision of PCC / Soling / Nullah / Street Scheme at Gohad Pur Bashamula, Handlapur, Korpur, Nawan Pind, Nangal, 223 1826 Ghiti Shekan, Kansarour, Tibbi, Arrian, Sialkot 399.852 29.955 3.333 3.333 2.500 2.500 100% 32.455 8% Work in progress. Saleempur, Malkay, Kalan, Malkay Khurd, Olkh Awana etc., Tehsil & District Sialkot [LO16006880]. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Provision of PCC / Soling / Nullah / Street Scheme at Kapurwali, Bashamula Ajjowali, Basant Pur, Dagaray, Malo Chak , Jorian 224 1827 Khurd / Kalan , Sukhnian, Bhindar, Olakh, Sialkot 70.000 19.987 3.333 3.333 2.500 2.500 100% 22.487 32% Work in progress. Saidpur, Jatta,Dusri,Kala Ghumna,Khambranwala, Kansar Pur, Canday Wali etc., Tehsil & D

Provision of PCC / Soling / Nullah / Street Scheme at Jaithi Kay Bashaula, Joluki, Maja Khurd, Haddokay, Kot Deena, Tibbi 225 1828 Sialkot 50.000 19.990 3.333 3.333 2.500 2.500 100% 22.490 45% Work in progress. Inayat Shah, Deera Tibbi Inayat Shah, Deera Tarraran, Dra Gujjran, Dera Arrian, Karan Wali etc.,Teshil & District Sialkot Provision of PCC / Soling / Nullah / Street Scheme at Jassor Wala Bashamula, Chak Gillan Sharki, Chak Gillan Magrabi, 226 1829 Sialkot 50.000 20.000 1.667 1.667 1.250 1.250 100% 21.250 43% Work in progress. Pandorian, Muhammad Pura, Gega, Addowali, Rajjokay etc.,Teshil & District Sialkot Provision of PCC / Soling / Nullah / Street Scheme Roras, Bashamula Mango Behram , Pidian, Kot Bagaa, Chak Maluk, Chak 227 1830 Sialkot 60.000 20.000 1.667 1.667 1.250 1.250 100% 21.250 35% Work in progress. Janta, Dhana Wali Mehad Pur, Dadowali, Manair etc., Tehsil Sambrial, District Sialkot [LO16006879]. Provision of PCC Sewerage Schemes in 228 1831 UC Dhuda Goraya, MaloMahay, Bogray Sialkot 40.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 56% Work in progress. SEO KE District Sialkot Provision of Sewerage and Tuff Tile in Various UCs of District Sialkot, UCs, kotli Behram, Mubarik pura, Miana pura, Model 229 1832 Sialkot 120.000 75.000 3.333 3.333 2.500 2.500 100% 77.500 65% Work in progress. Town, Fateh Garh, Muzafar pur, Haji pura, Ban, Haji pura-II, Imam Sahib, Shahab pura, Pacca Garha, Hamza Ghous. Providing and Laying Tuff Tile RCC Sewer and Construction of Drain /Nullah Mohallah 230 1833 Shahab Pura Bajli Mohallah Darbar Shahab Sialkot 35.000 31.000 1.333 1.333 0.000 0.000 #DIV/0! 31.000 89% Work in progress. Shah U/C. Shahab pura Tehsil & District Sialkot Construction of PCC Street Drain/ Nullah Providing and Laying of RCC Sewer and 231 1834 Tuff Tile U/C Water Works (Silver star road Sialkot 24.400 14.991 3.133 3.133 2.350 2.350 100% 17.341 71% Work in progress. Mohallah Islamia Park) Tehsil & District Sialkot. Construction of PCC Street, Drain/ Nullah Providing and Laying of RCC Sewer and 232 1835 Sialkot 29.500 20.000 3.167 3.167 2.375 2.375 100% 22.375 76% Work in progress. Tuff Tile U/C Duburj Arraian (Moh. Baba Bari, Habib pura) Tehsil & District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC Street, Drain/ Nullah Providing and Laying of RCC Sewer and 233 1836 Sialkot 28.600 19.938 2.867 2.867 2.150 2.150 100% 22.088 77% Work in progress. Tuff Tile U/C Muhammad pura (Nishat park) Tehsil & District Sialkot Construction of PCC Street, Drain/ Nullah Providing and Laying of RCC Sewer and 234 1837 Sialkot 25.500 19.975 1.833 1.833 1.375 1.350 98% 21.325 84% Work in progress. Tuff Tile U/C Water Works (Moh. Pak pura) Tehsil & District Sialkot Providing & Laying of RCC Sewer, Tuff Tile and Construction of Disposal Station Mohallah Water Works to Abbot Road 235 1838 Sialkot 50.000 8.000 5.000 5.000 0.250 0.250 100% 8.250 17% Work in progress. Phatak and along the Railway line to Dara Arrian U/C Water Works, Tehsil & District Sialkot Providing & Laying of RCC Sewer, Tuff Tile and Construction of Disposal Station Nasir 236 1839 Road Prem Nagar Road EIC School to Sialkot 50.000 10.000 5.000 5.000 0.950 0.950 100% 10.950 22% Work in progress. Nullah Bhed U/C Model Town, Tehsil & District Sialkot Providing and Laying of Tuff Tile RCC Sewer and Construction of Drain / Nullah 237 1840 Mohallah Kashmiri Sarray Bhabrian Alamgir Sialkot 32.000 25.933 2.000 2.000 0.700 0.700 100% 26.633 83% Work in progress. Bazar Nikhas U/C. Imam Sahib Tehsil & District Sialkot Provision of PCC/Soling /Nalian/Streets Schemes at Bohalwala Bashamula Chak 238 1841 Kheena, Kotli Nonaan, Kotli Nonaan, Dot Sialkot 80.000 40.500 3.333 18.333 20.067 5.000 25% 45.500 57% Work in progress. Dharan Baddoke Cheema, Kot Bhagat, Jalianwala Ahmadabad District Sialkot Provision of PCC/Soling/nalian/Streets Scehmes at Majra kalan, Chak Ekhtiar, Dingowal, Mahiwal, rakh noshra ,kothy 239 1842 pardansing (islambad)khothay chistian Sialkot 90.000 69.860 3.333 3.333 2.500 2.450 98% 72.310 80% Work in progress. ,Dorarbe Malianwala Jattan & Arrian, Pano attari Hussain Pur, Jamal Pur District Sialkot Provision of PCC/Soling/Nalian/Streets Schemes at Barath Bhoth Bashamula 240 1843 Markiwal, Khorta Syedan, Ballanwala, Sialkot 50.000 29.945 1.667 1.667 1.250 1.250 100% 31.195 62% Work in progress. Machi Khokhar, Gul Bahar Khurd, Gul Bahar Kalan Provision of PCC/Soling/Nalian/Streets Schemes at Chaprar Bashamula Punowal, 241 1844 Sialkot 55.000 29.978 3.333 3.333 2.500 2.500 100% 32.478 59% Work in progress. Najwal, Parwal, Sagarpu, Medhi pur, Bagh pur, Sagri pur etc Provision of PCC/Soling/Nalian/Streets Schemes at Gojra Bashamula Thatha Lathi, 242 1845 Qila Tek Singh, Bhonawali, Phangat, Sialkot 50.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 45% Work in progress. Dheera Sanda, Islam pura, Kotli wala, Kandan Sian Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of PCC/Soling/Nalian/Streets 243 1846 Schemes at Mandran Wala Bashamula Sialkot 75.000 49.601 3.333 3.333 2.500 2.500 100% 52.101 69% Work in progress. Adamkay Cheema, Nai Abadi, Provision of PCC/Soling/Nalian/Streets Schemes at Saidowali Bashamula 244 1847 Hambokay, Kot Mahraj, Merian Pindi, Sialkot 70.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 32% Work in progress. Lalaywali, Easa pur, Khorray, Suraj, Chak Hana etc Provision of PCC/Soling/Nalian/Streets Schemes at Shahuwala Bashamula Balo 245 1848 Sialkot 28.000 19.920 2.667 2.667 2.000 2.000 100% 21.920 78% Work in progress. Chak, Nashtar Abad, Zafarwali, Kamalpur, Manpur etc. Provision of PCC/Soling/nalian/Streets Schemes at Sheeni Bashamula Chaila, 246 1849 Sialkot 90.000 77.698 3.333 3.333 2.500 2.500 100% 80.198 89% Work in progress. bjola, Muljhan, Sagar, punwal ratwal ,chogpur District Sialkot Provision of PCC/Soling/Nalian/Streets Schemes at Verowala Bashamula 247 1850 Wassankay, Magokaman, Nandpur, Baryar, Sialkot 50.000 19.925 3.333 3.333 2.500 2.500 100% 22.425 45% Work in progress. Wan Garthal Umarkey Kalan, Umarkey Khurd, Ahmad abad, Veeramkay etc Const of Streets/drains & PCC in Village 248 1851 Sialkot 60.000 12.990 1.667 1.667 1.250 1.250 100% 14.240 24% Work in progress. Partanwali Const of Streets/drains & PCC in Village 249 1852 Sialkot 65.000 16.490 3.333 3.333 2.500 2.500 100% 18.990 29% Work in progress. Saidpur Kalan Const. of Nullah from Sublime Chowk to 250 1853 Uggoki More to Sahowala Bridge to Sialkot 394.111 244.942 16.667 16.667 12.500 12.500 100% 257.442 65% Work in progress. Syphonof Nullah Aik, Sialkot

251 1854 Const. of PCC Drains / Sewerage Sialkot Sialkot 90.000 62.984 3.333 3.333 7.700 7.700 100% 70.684 79% Work in progress. Provision of Sewerage & PCC Schemes in 252 1855 Pero Chak, Sego Wala, Adha Kanwamlit Sialkot 40.000 19.855 1.667 1.667 1.550 1.550 100% 21.405 54% Work in progress. District Sialkot Provision of Sewerage & PCC Schemes 253 1856 Sialkot 40.000 19.940 1.667 1.667 1.250 1.250 100% 21.190 53% Work in progress. UC Jharah Wala Salhoke, Bharlham Wala Provision of Sewerage / Drainage Scheme 254 1857 at UC Dhodha Tehsil Pasrur District Sialkot Sialkot 165.000 90.000 1.673 51.673 60.557 30.395 50% 120.395 73% Work in progress. (under revision) Date of A.A 25.01.2016, Date of T.S 30.01.2016, Date of Award 25.01.2017, Scheduled date of Completion on Construction of Drains, Soling / PCC and 30.06.2018, Date of Commencement, 255 1858 Sullage Carrier of Ghughiat, District Sialkot 18.164 15.000 1.055 1.055 0.791 0.791 100% 15.791 87% 25.01.2017, Funds released on 30.07.2018, Sargodha Funds on-lined on 30.07.2018.Drain 9620 Rft & Sullage Carrier 112-Rft constructed, PCC 39477-Cft & Soling 37715-Cft laid. Work in progress Construction of PCC / Drain in Dhera 256 1859 Sialkot 50.000 47.970 0.667 0.667 0.500 0.500 100% 48.470 97% Work in progress. Sardha District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC Drain / Tuff Tile Ward No. 1 to 30 Daska Kalan, Daska Kot, U. C Galotian Kalan, Ranganwala, Moseywala, 257 1860 Sialkot 70.000 39.545 3.333 3.333 2.500 2.500 100% 42.045 60% Work in progress. Gaga, Ladhey Bhanbanwal, Thatha, Sukhar Nahar & Bhadeywala, Daska City, District Sialkot. Construction of Drain/Nullah for Diposal of 258 1861 Sewerage at Bhadewal Tehsil Daska Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. District Sialkot Reheblitiation of Sewerage/Drainage 259 1862 Scheme Mitranwali Tehsil Daska District Sialkot 20.000 10.000 3.333 3.333 7.500 7.500 100% 17.500 88% Work in progress. Sialkot Sanitation Schemes in UCs, Gadgore, 260 1863 Khanawali, Alhar, Jassoran, Baddiana and Sialkot 40.000 26.000 4.667 4.667 3.500 3.500 100% 29.500 74% Work in progress. Chawinda, Tehsil Pasrur Construction of PCC Streets, Drains,Tuff 261 1864 tiles and Soling in Adalat Garah, District Sialkot 30.000 14.935 5.000 5.000 3.750 3.750 100% 18.685 62% Work in progress. Sialkot Construction of PCC Streets, Drains,Tuff 262 1865 tiles and Soling in Mahal Kingra & Sialkot 6.000 3.000 1.000 1.000 0.750 0.750 100% 3.750 63% Work in progress. Dhanney, District Sialkot Construction of PCC Streets, Drains,Tuff 263 1866 tiles and Soling in Muzafar Pur, District Sialkot 5.000 2.500 0.833 0.833 0.625 0.625 100% 3.125 63% Work in progress. Sialkot Construction of PCC Streets, Drains,Tuff 264 1867 tiles and Soling in Shatab Garah, District Sialkot 5.000 2.500 0.833 0.833 0.625 0.625 100% 3.125 63% Work in progress. Sialkot Construction of PCC Streets, Drains,Tuff 265 1868 Sialkot 5.000 2.500 0.833 0.833 0.625 0.625 100% 3.125 63% Work in progress. tiles and Soling in Bonkam, District Sialkot

Construction of PCC Streets, Drains,Tuff 266 1869 tiles and Soling in Ganjianwali & Roheel Sialkot 6.000 3.000 1.000 1.000 0.750 0.750 100% 3.750 63% Work in progress. Garah, District Sialkot Construction of PCC streets, Drains,Tuff 267 1870 tiles and Soling in Chak Adil,Chitti Sialkot 10.000 5.000 1.000 1.000 0.834 0.834 100% 5.834 58% Work in progress. Shikhan,Nawan Pind, District Sialkot Construction of PCC Streets, Drains,Tuff 268 1871 tiles and Soling in Murad Pur, District Sialkot 10.000 5.000 1.667 1.667 1.250 1.250 100% 6.250 63% Work in progress. Sialkot Construction of PCC Streets, Drains,Tuff 269 1872 tiles and Soling in Gohad Pur, District Sialkot 10.000 5.000 1.667 1.667 3.283 3.283 100% 8.283 83% Work in progress. Sialkot Construction of PCC Streets, Drains,Tuff 270 1873 Sialkot 5.000 2.500 1.000 1.000 0.750 0.750 100% 3.250 65% Work in progress. tiles and Soling in Dhanwali, District Sialkot

Construction of PCC Streets, Drains,Tuff tiles and Soling in Village Monger to Nehar 271 1874 Sialkot 6.000 3.000 1.000 1.000 0.750 0.750 100% 3.750 63% Work in progress. Upper Chanab & Village Ranjhai to Burj Cheema Link Way, District Sialkot Construction of PCC Streets, Drains,Tuff 272 1875 tiles and Soling in Monger Sofen to Sialkot 7.000 3.500 1.167 1.167 0.875 0.875 100% 4.375 63% Work in progress. Barthanwala, District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC Streets, Drains,Tuff 273 1876 tiles and Soling in Hunter Pura, District Sialkot 5.000 2.500 0.833 0.833 0.625 0.625 100% 3.125 63% Work in progress. Sialkot A.A. dated 23.09.2016 T.S. dated Drainage / PCC scheme for village Gorala 274 1877 Narowal 50.000 34.743 3.333 3.333 2.500 2.476 99% 37.219 74% 24.09.2016 *Start Date 19.11.2016 Maanpur *Completion date 18.05.2018. work in progress. PCC , Soling and Drainage Scheme in A.A. dated 23.09.2016 T.S. dated 24.09.2016 *Start Date 275 1878 Village Babral, Kallah, Mahlo, Sahlo,Tehsil Narowal 41.395 24.992 3.333 3.333 2.500 2.469 99% 27.461 66% 11.01.2017*Completion date Shakargarh, District Narowal 10.01.2018.work in progress. PCC / Soling / Filtration Plant in Village A.A. dated 3.08.17 T.S. date 07.01.2017.02.11.2018*Start Date 276 1879 Noor Kot Manngri and Bagha Madan Narowal 46.000 18.730 1.000 1.000 0.750 0.745 99% 19.475 42% 14.03.2017*Completion date 30.06.2020 Thakrian Pagla, District Narowal. Work in progress. Construction of Nalian, Soling, PCC & Boundary Walls of Graveyard in UCs Nallah, Bua, Melo Salo, Kalah, Mainagty, A.A. dated 23.9.2016. T.S. dated 24.9.2016. 277 1880 Bara Manga, Kot Naina, Bahree, Ikhras Narowal 85.000 49.192 3.333 3.333 2.500 2.471 99% 51.663 61% *Start Date16.06.2017*Completion date Pur, Jalala, Sujowal, Pehgwari, Malik Pur, 15.06.2019.work in progress. Fateh Pur Afghana, Sahari, Ghona, Ghumtala, Kanjror, Lang A.A. dated 03.05.2014T.S. dated 23.05.2014*Start 278 1881 Sewerage scheme for Ghaziwal, Narowal. Narowal 34.648 33.308 0.378 0.378 0.284 0.279 98% 33.587 97% Date18.09.2014*Completion date 17.09.2016 work in progress. Urban / Sewerage / PCC & Tuff Tile A.A Date.23.9.2016.T.S Date*28.10.2016 279 1882 Narowal 174.705 84.160 6.667 6.667 5.000 4.999 100% 89.159 51% Date of start 17.2.2017 Date of completion Scheme Narowal City 30.06.2019. Work in progress. A.A. dated 03.05.2014T.S. dated Sewerage scheme for Oncha Sadawala, 280 1883 Narowal 49.284 47.265 0.611 0.611 0.458 0.451 98% 47.716 97% 23.05.2014*Start Narowal. Date18.09.2014*Completion date 17.09.2016 work in progress. PCC and Drainage Scheme in UC 197 at Physically scheme is completed, balance 281 1884 Lahore 100.082 91.500 2.861 2.861 1.146 1.146 100% 92.646 93% funds are required to clear the contractor's Dhalloki liability. PCC and Drainage Scheme in UC 243 at 282 1885 Lahore 130.989 90.510 6.667 6.667 6.750 6.750 100% 97.260 74% Work stopped due to awaiting funds. attari Saroba Pind Scheme Completed. Funds not yet PCC and Drainage Scheme in UC 246 at 283 1886 Lahore 100.838 100.494 0.344 0.344 0.258 0.258 100% 100.752 100% released. Funds required to clear the Youhanabad contractor's liabilities against Price Variation. PCC and Drainage Scheme in UC 247 at 284 1887 Lahore 201.357 130.000 6.667 6.667 8.250 8.250 100% 138.250 69% Work stopped due to awaiting funds. Kahna Kohna PCC and Drainage Scheme in UC 248 at 285 1888 Lahore 151.603 128.300 7.201 7.201 5.401 5.400 100% 133.700 88% Work stopped due to awaiting funds. Shehzada and Pura Kahna PCC and Drainage Scheme in UC 249 at Physically scheme is completed, balance 286 1889 Lahore 80.384 70.070 3.438 3.438 2.579 2.579 100% 72.649 90% funds are required to clear the contractor's Kamahan liability PCC and Drainage Scheme in UC 252 at Physically scheme is completed, balance 287 1890 Lahore 113.315 106.999 2.105 2.105 0.235 0.235 100% 107.234 95% funds are required to clear the contractor's Pandoki liability PCC and Drainage Scheme in UC 253 at 288 1891 Lahore 120.660 96.245 8.138 8.138 6.004 6.004 100% 102.249 85% Work stopped due to awaiting funds. Suraich PCC and Drainage Scheme in UC 254 Deo 289 1892 Lahore 102.533 83.173 4.187 4.187 5.565 5.565 100% 88.738 87% Work stopped due to awaiting funds. Khurd and Kalan PCC and Drainage Scheme in UC 268 at 290 1893 Lahore 102.003 89.361 4.001 4.001 2.501 2.501 100% 91.862 90% Work stopped due to awaiting funds. Judho Dheer PCC and Drainage Scheme in UC 271 at 291 1894 Lahore 103.300 100.032 1.086 1.086 4.815 4.800 100% 104.832 101% Scheme completed Jia Bhagga and RO Plant at Jia Bhagga Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) PCC and Drainage Scheme in UC191 at Physically scheme is completed, balance 292 1895 Lahore 100.000 92.500 2.500 2.500 1.875 1.875 100% 94.375 94% funds are required to clear the contractor's Gawind liability Construction of PCC Sewerage & 293 1896 Drainage System at UC 262 Shamke Lahore 30.000 18.497 3.833 3.833 2.875 2.870 100% 21.367 71% Work stopped due to awaiting funds. Bhattian, District Lahore Construction of PCC Sewerage & 294 1897 Drainage System at UC 267 Manak, District Lahore 30.000 14.521 5.160 5.160 2.370 2.370 100% 16.891 56% Work stopped due to awaiting funds. Lahore Disposal of Waste Water of Manga Mandi 295 1898 Lahore 161.107 125.649 6.667 6.667 11.463 11.400 99% 137.049 85% Scheme completed and put in to operation, upto River Ravi balance funds are for O&M for 1-Year. PCC and Drainage Scheme in Khananapal Physically scheme is completed, balance 296 1899 Lahore 83.175 72.510 3.555 3.555 2.666 2.666 100% 75.176 90% funds are required to clear the contractor's Kangra Karyal Dhoondy liability. PCC and Drainage Scheme in Nanghar 297 1900 Katcha Tibba Katcha Islampura Halloki Lahore 93.775 81.140 4.212 4.212 0.269 0.269 100% 81.409 87% Scheme completed Sadhuke PCC and Drainage Scheme in UC 145 Physically scheme is completed, balance 298 1901 Lahore 200.014 185.659 4.785 4.785 5.589 5.589 100% 191.248 96% funds are required to clear the contractor's Gajjumatta and Adjoining Abadies. liability. PCC and Drainage Scheme in UC 176 at 299 1902 Lahore 70.128 43.914 8.737 8.737 6.553 6.553 100% 50.467 72% Work stopped due to awaiting funds. Awan Dhaiwa PCC and Drainage Scheme in UC 179 at 300 1903 Lahore 90.000 68.013 7.329 7.329 5.497 5.497 100% 73.510 82% Work stopped due to awaiting funds. Bhaseen PCC and Drainage Scheme in UC 180 at 301 1904 Lahore 155.697 49.805 5.000 5.000 8.750 8.750 100% 58.555 38% Work stopped due to awaiting funds. Minhala PCC and Drainage Scheme in UC 181 at Physically scheme is completed, balance 302 1905 Lahore 45.000 43.000 0.667 0.667 2.600 2.600 100% 45.600 101% funds are required to clear the contractor's Narwar liability. PCC and Drainage Scheme in UC 182 at 303 1906 Lahore 56.817 31.060 8.585 8.585 2.339 2.339 100% 33.399 59% Work stopped due to awaiting funds. Jallo More & Batapur Lahore PCC and Drainage Scheme in UC 190 at 304 1907 Lahore 162.606 50.000 5.000 5.000 4.070 4.070 100% 54.070 33% Work stopped due to awaiting funds. Hadiara PCC and Drainage Scheme in UC 194 at 305 1908 Lahore 101.739 63.707 6.667 6.667 5.600 5.540 99% 69.247 68% Work stopped due to awaiting funds. Liddhar PCC and Drainage Scheme in UC 195 at 306 1909 Lahore 120.468 104.533 5.312 5.312 12.584 12.572 100% 117.105 97% Scheme completed Hair PCC and Drainage Scheme in UC 196 at 307 1910 Lahore 115.347 101.472 1.500 1.500 1.125 1.125 100% 102.597 89% Scheme completed Jaman Provision of Sanitation Facilities including 308 1911 Construction of Lift Station at Tahayat & Lahore 94.210 81.441 4.254 4.254 3.191 3.190 100% 84.631 90% Work stopped due to awaiting funds. Chandrai Village, Lahore Construction of PCC and Drainage at Adda 309 1912 Lahore 30.140 28.294 0.608 0.608 0.106 0.106 100% 28.400 94% Scheme completed Talaab Saral Construction of PCC and Drainage at 310 1913 Lahore 128.380 73.594 3.333 3.333 1.500 1.500 100% 75.094 58% Work stopped due to awaiting funds. Chung Construction of PCC and Drainage at 311 1914 Lahore 74.249 28.893 3.333 3.333 2.500 2.500 100% 31.393 42% Work stopped due to awaiting funds. Khurd Pur Construction of PCC and Drainage at 312 1915 Lahore 199.606 42.995 5.000 5.000 2.050 2.050 100% 45.045 23% Work stopped due to awaiting funds. Manga Mandi Construction of PCC and Drainage at 313 1916 Lahore 52.966 52.184 0.261 0.261 0.756 0.756 100% 52.940 100% Scheme Completed Mohlanwal Construction of PCC and Nallah from 314 1917 Lahore 29.345 18.612 3.577 3.577 2.683 2.683 100% 21.295 73% Work stopped due to awaiting funds. Hadyara Drain to Dulam Village Construction of PCC Sewerage & 315 1918 Drainage System at UC 260 Maraka, Lahore 30.000 12.371 5.876 5.876 0.643 0.643 100% 13.014 43% Work stopped due to awaiting funds. District Lahore Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Up Gradation of Streets PCC Flooring in 316 1919 Asif Town I & II Galaxo Town and Adjoining Lahore 150.678 108.993 6.667 6.667 2.900 2.900 100% 111.893 74% Work stopped due to awaiting funds. abadies Rural Drainage Scheme Kamahan & 317 1920 Lahore 143.277 126.501 5.137 5.137 2.353 2.350 100% 128.851 90% Work stopped due to awaiting funds. Adjoining Abadies Balance work of Sewerage, water Supply 318 1921 and PCC Scheme Town Committtee Kot Sheikhupura 195.462 167.947 3.333 3.333 2.500 2.500 100% 170.447 87% Work in Progress Abdul Malik, District Sheikhupura Const and Rehabilitation of PCC 319 1922 Sewerage Scheme of Ravi Rayan Mannu Sheikhupura 95.313 41.645 3.333 3.333 2.500 2.500 100% 44.145 46% Work in Progress Abad and Nazar Abad (Revised) Construction of Drainage & PCC Scheme 320 1923 Sheikhupura 25.000 20.000 1.667 1.667 1.250 1.250 100% 21.250 85% Work in Progress at Mariam Abad District Sheikhupura

Construction of Drainage & PCC Scheme 321 1924 Sheikhupura 30.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 75% Work in Progress at Mian Ali Dogran District Sheikhupura Construction of Drainage /PCC/Soling 322 1925 Sheikhupura 125.450 49.569 3.333 3.333 2.500 2.500 100% 52.069 42% Work in Progress Scheme at Khanqah Dogran Safdarabad Construction of PCC, Drains, Soling in 323 1926 Sheikhupura 100.000 30.000 3.333 3.333 2.500 2.500 100% 32.500 33% Work in Progress District Sheikhupura Provision of PCC and draniage at 324 1927 Sheikhupura 30.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 75% Work in Progress Manawala Construction of PCC, Drain/Soling & Nullah 325 1928 Sheikhupura 46.000 14.046 3.333 3.333 2.500 2.500 100% 16.546 36% Work in Progress at UC 75, Kakar Gill, District Sheikhupura

Construction of PCC, Drain/Soling & Nullah 326 1929 Sheikhupura 76.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 30% Work in Progress at UC 77, Ajnianwala, District Sheikhupura

Construction of PCC, Drain/Soling & Nullah 327 1930 Sheikhupura 57.000 18.000 3.333 3.333 2.500 2.500 100% 20.500 36% Work in Progress at UC 83, Jatri Kohna, District Sheikhupura

Construction of PCC, Drain/Soling & Nullah 328 1931 Sheikhupura 58.000 27.000 3.333 3.333 2.500 2.500 100% 29.500 51% Work in Progress at UC 84, Makki 460, District Sheikhupura

Construction of PCC, Drain/Soling & Nullah 329 1932 Sheikhupura 40.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 44% Work in Progress at UC 85, Farooqabad, District Sheikhupura Construction of PCC, Drain/Soling & Nullah 330 1933 at UC-97, Ferozwatuan-I, District Sheikhupura 15.000 11.509 1.000 1.000 0.750 0.750 100% 12.259 82% Work in Progress Sheikhupura Construction of PCC, Drain/Soling & Nullah Funds fully utilized, work stopped due to 331 1934 at UC-98, Ferozwatuan-II, District Sheikhupura 15.000 8.138 1.000 1.000 1.144 1.144 100% 9.282 62% non-availability of funds Sheikhupura Construction of Soling / Sewerage & Drainage Scheme at UC Anjianwala, UC Jhabran, UC Kakar Gill, UC Gujiana Nau, UC Kot Sohnda, UC Esserkay, UC Funds fully utilized, work stopped due to 332 1935 Bahalikay, UC Jatri Kohna, UC Sheikhupura 100.000 20.000 3.333 3.333 4.167 4.167 100% 24.167 24% non-availability of funds 85Farooqabad, UC Ghazi Minara, UC Buttar, UC Jhandian Wali, UC Warn, UC Kalokay Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Const. and Rehabilitation of PCC / Funds fully utilized, work stopped due to 333 1936 Sewerage Scheme of City Muridke, District Sheikhupura 96.536 61.500 5.000 5.000 3.750 3.750 100% 65.250 68% non-availability of funds Sheikhupura (Revised) Construction of PCC Tuff Tiles Sewerage Funds fully utilized, work stopped due to 334 1937 Drainage Scheme in PP 163 District Sheikhupura 373.950 131.468 3.333 3.333 2.500 2.500 100% 133.968 36% non-availability of funds Sheikhupura Rural Drainage & PCC Scheme U.C. 335 1938 Sheikhupura 48.000 20.000 1.667 1.667 1.250 1.250 100% 21.250 44% Funds fully utilized, work stopped due to Keelay non-availability of funds Rural Drainage & PCC Scheme U.C. Kot 336 1939 Sheikhupura 45.000 24.000 3.333 3.333 2.500 2.500 100% 26.500 59% Funds fully utilized, work stopped due to Sonda non-availability of funds Rural Drainage & PCC Scheme U.C. 337 1940 Sheikhupura 45.000 24.000 3.333 3.333 2.500 2.500 100% 26.500 59% Funds fully utilized, work stopped due to Muridke non-availability of funds Rural Drainage & PCC Scheme U.C. 338 1941 Sheikhupura 45.000 24.000 1.667 1.667 1.250 1.250 100% 25.250 56% Funds fully utilized, work stopped due to Nookhar non-availability of funds Rural Drainage & PCC Scheme U.C. Sacha 339 1942 Sheikhupura 78.000 24.000 3.333 3.333 2.500 2.500 100% 26.500 34% Funds fully utilized, work stopped due to Souda non-availability of funds Rural Drainage & PCC Scheme UC 340 1943 Sheikhupura 25.000 10.425 4.858 4.858 3.644 3.644 100% 14.069 56% Funds fully utilized, work stopped due to Bhaianwala non-availability of funds Funds fully utilized, work stopped due to 341 1944 Rural Drainage & PCC Scheme UC Ghang Sheikhupura 20.000 16.000 1.333 1.333 1.000 1.000 100% 17.000 85% non-availability of funds

Funds fully utilized, work stopped due to 342 1945 Rural Drainage & PCC Scheme UC Mojoki Sheikhupura 28.000 23.000 1.667 1.667 1.250 1.250 100% 24.250 87% non-availability of funds

Funds fully utilized, work stopped due to 343 1946 Rural Drainage & PCC Scheme UC Warn Sheikhupura 25.000 10.510 4.830 4.830 3.623 3.623 100% 14.133 57% non-availability of funds Rural Drainage & PCC scheme Union 344 1947 Sheikhupura 99.509 30.000 3.333 3.333 2.500 2.500 100% 32.500 33% Funds fully utilized, work stopped due to Council Burj attari, District Sheikhupura non-availability of funds Rural Drainage & PCC scheme Union 345 1948 Sheikhupura 91.385 30.000 3.333 3.333 2.500 2.500 100% 32.500 36% Funds fully utilized, work stopped due to Council Kot Mehmood, District Sheikhupura non-availability of funds Rural Drainage Construction of Street Funds fully utilized, work stopped due to 346 1949 Scheme Chak No 44,45 and Village Jair Sheikhupura 199.486 74.950 3.333 3.333 2.500 2.500 100% 77.450 39% non-availability of funds District Sheikhupura Rural Drainage Construction Of Street Funds fully utilized, work stopped due to 347 1950 Scheme Dograi Gill Qadeem Dograi Gill Sheikhupura 195.462 125.646 3.333 3.333 2.500 2.500 100% 128.146 66% non-availability of funds District Sheikhupura Rural Drainage Scheme UC Chapa Minera 348 1951 Sheikhupura 87.910 54.975 3.333 3.333 2.500 2.500 100% 57.475 65% Funds fully utilized, work stopped due to Sheikhupura non-availability of funds Rural Drainage Scheme UC Chichoki 349 1952 Sheikhupura 85.423 48.694 3.333 3.333 2.500 2.500 100% 51.194 60% Funds fully utilized, work stopped due to Malian Sheikhupura non-availability of funds Rural Drainage Scheme UC Jahamke 350 1953 Sheikhupura 94.134 54.999 3.333 3.333 2.500 2.500 100% 57.499 61% Funds fully utilized, work stopped due to Sheikhupura non-availability of funds Rural Drainage Scheme UC Mallian Kalan 351 1954 Sheikhupura 92.869 50.900 3.333 3.333 2.500 2.500 100% 53.400 58% Funds fully utilized, work stopped due to Sheikhupura non-availability of funds Rural Drainage Scheme Abdullah Pur Kolar Funds fully utilized, work stopped due to 352 1955 Chak No 1/RB Tehsil Safdarabad District Sheikhupura 50.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 25% non-availability of funds Sheikhupura Rural Sewerage Drainage System at Funds fully utilized, work stopped due to 353 1956 Village Kot Pindi Das Tehsil Ferozewala, Sheikhupura 199.993 185.231 4.921 4.921 3.691 3.691 100% 188.922 94% non-availability of funds Distt. Sheikhupura (Revised) Rural Drainage PCC Scheme UC Dhamkey 354 1957 Sheikhupura 199.308 88.690 3.333 3.333 2.500 2.500 100% 91.190 46% Funds fully utilized, work stopped due to Sheikhupura Ferozwala non-availability of funds Rural Drainage PCC Scheme UC Funds fully utilized, work stopped due to 355 1958 Mahmood Kot, Sheikhupura , Sharqpur Sheikhupura 180.146 78.279 3.333 3.333 2.500 2.500 100% 80.779 45% non-availability of funds (Revised) Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Rural Drainage PCC Scheme UC Mandain 356 1959 Sheikhupura 191.008 10.687 3.333 3.333 2.500 2.500 100% 13.187 7% Funds fully utilized, work stopped due to Wala Sheikhupura , Sharqpur (Revised) non-availability of funds Rural Drainage PCC Scheme UC Mhar 357 1960 Sheikhupura 95.862 83.000 4.287 4.287 3.215 3.215 100% 86.215 90% Funds fully utilized, work stopped due to Bhanguwan District Sheikhupura non-availability of funds Rural Drainage PCC Scheme UC Funds fully utilized, work stopped due to 358 1961 Quershian Sheikhupura , Sharqpur Sheikhupura 87.395 66.200 3.333 3.333 2.500 2.500 100% 68.700 79% non-availability of funds (Revised) Rural Drainage PCC Scheme, UC Sehjowal 359 1962 Sheikhupura 93.090 74.136 3.333 3.333 2.500 2.500 100% 76.636 82% Funds fully utilized, work stopped due to District Sheikhupura (Revised) non-availability of funds Rural Drainage PCC Scheme, Wandala Scheme Physically Completed funtional on 360 1963 Dial Shah UC 24 District Sheikhupura Sheikhupura 144.546 142.456 0.697 0.697 0.523 0.523 100% 142.979 99% gravity basis. (Revised) Rural Drainage PCC Tuff Tile Scheme UC 361 1964 Sheikhupura 97.335 72.267 3.333 3.333 2.500 2.500 100% 74.767 77% Funds fully utlized, work stopped due to non- Sharqpur, Sheikhupura availability of funds. Rural drainage scheme at UC Bhadro 362 1965 Sheikhupura 15.110 13.100 0.670 0.670 0.503 0.503 100% 13.603 90% Scheme Completed District Sheikhupura RSD Scheme Faizpur Khurd District 363 1966 Sheikhupura 40.000 16.500 3.333 3.333 2.500 2.500 100% 19.000 48% Funds fully utlized, work stopped due to non- Sheikhupura availability of funds. Rural drainage & Const of streets scheme 364 1967 Sheikhupura 134.768 81.863 3.333 3.333 2.500 2.500 100% 84.363 63% Funds fully utlized, work stopped due to non- UC Khan pur Sheikhupura availability of funds. Rural drainage & Const of streets scheme 365 1968 Sheikhupura 196.571 57.986 3.333 3.333 2.500 2.500 100% 60.486 31% Funds fully utlized, work stopped due to non- UC Mandialy Sheikhupura (Revised) availability of funds. Rural drainage & Const of streets scheme Funds fully utlized, work stopped due to non- 366 1969 UC Qila Sattar Shah Sheikhupura Sheikhupura 182.244 72.431 3.333 3.333 2.500 2.500 100% 74.931 41% availability of funds. (Revised) Rural drainage & Const of streets scheme 367 1970 Sheikhupura 177.038 45.905 3.333 3.333 2.500 2.500 100% 48.405 27% Funds fully utlized, work stopped due to non- Zia abad Sheikhupura (Revised) availability of funds. Rural Drainage & PCC Scheme U.C. 368 1971 Sheikhupura 75.000 25.595 5.000 5.000 3.750 3.750 100% 29.345 39% Funds fully utlized, work stopped due to non- Ajnianwala availability of funds. Funds fully utlized, work stopped due to non- 369 1972 Rural Drainage & PCC Scheme U.C. Buttar Sheikhupura 57.000 39.000 1.667 1.667 1.250 1.250 100% 40.250 71% availability of funds. Rural Drainage & PCC Scheme U.C. 370 1973 Sheikhupura 38.000 25.000 2.667 2.667 2.000 2.000 100% 27.000 71% Funds fully utlized, work stopped due to non- Easerkey availability of funds. Rural Drainage & PCC Scheme U.C. 371 1974 Sheikhupura 55.000 11.629 3.333 3.333 2.500 2.500 100% 14.129 26% Funds fully utlized, work stopped due to non- Gujiana Nu District Sheikhupura availability of funds. Rural Drainage & PCC Scheme U.C. 372 1975 Sheikhupura 35.000 11.629 2.333 2.333 1.750 1.750 100% 13.379 38% Funds fully utlized, work stopped due to non- Harchand availability of funds. Rural Drainage Scheme Chak No 8/RB 373 1976 Sheikhupura 75.000 17.987 3.333 3.333 2.500 2.500 100% 20.487 27% Funds fully utlized, work stopped due to non- Sheikhupura availability of funds. Rural Drainage Scheme Faizpur Khurd IIc 374 1977 Sheikhupura 152.400 74.217 3.333 3.333 2.500 2.500 100% 76.717 50% Funds fully utlized, work stopped due to non- abadis, Tehsil Ferozewala availability of funds. Rural Drainage/PCC Scheme at Moran 375 1978 Sheikhupura 90.000 80.000 0.667 0.667 0.500 0.500 100% 80.500 89% Funds fully utlized, work stopped due to non- Wala District Sheikhupura availability of funds. Rural PCC & Drainage Scheme, UC 376 1979 Sheikhupura 29.000 22.000 2.333 2.333 1.750 1.750 100% 23.750 82% Funds fully utlized, work stopped due to non- Bhaiwala Kalan, District Sheikhupura. availability of funds. Beautification of Sharqpur Sharif, Provision of PCC, Tufftiles, Fountains, Monuments, 377 1980 Sheikhupura 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utlized, work stopped due to non- LED Street lights and construction of roof of availability of funds. Main Bazar Rural Drainage & PCC Scheme UC Mirza 378 1981 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utlized, work stopped due to non- Virkan District Sheikhupura. availability of funds. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Rural Drainage & PCC Scheme UC 379 1982 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utlized, work stopped due to non- Chichoki Mallian District Sheikhupura. availability of funds. Rural Drainage & PCC Scheme Village 380 1983 Sheikhupura 10.000 5.000 1.667 1.667 1.250 1.250 100% 6.250 63% Funds fully utlized, work stopped due to non- Madar District Sheikhupura. availability of funds. Rural Drainage & PCC Scheme UC Funds fully utlized, work stopped due to non- 381 1984 Mohallah Rehman Pura District Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% availability of funds. Sheikhupura. Rural Drainage & PCC Scheme UC kot 382 1985 Sheikhupura 10.000 7.500 0.833 0.833 0.625 0.625 100% 8.125 81% Funds fully utlized, work stopped due to non- Ranjeet District Sheikhupura. availability of funds. Rural Drainage & PCC Scheme UC Kurlkey 383 1986 Sheikhupura 10.000 5.000 1.667 1.667 1.250 1.250 100% 6.250 63% Funds fully utlized, work stopped due to non- District Sheikhupura. availability of funds. Rural Drainage & PCC Scheme UC Mallian 384 1987 Sheikhupura 15.000 7.500 2.500 2.500 1.875 1.875 100% 9.375 63% Funds fully utlized, work stopped due to non- Kalan District Sheikhupura. availability of funds. Rural Water Supply & Drainage Scheme 385 1988 Sheikhupura 95.246 20.000 1.121 1.121 0.841 0.841 100% 20.841 22% Funds fully utlized, work stopped due to non- Murady Kalan, Shiekpura availability of funds. Construction of Sewerage and PCC at Nankana Work stopped due to non availability of 386 1989 195.998 164.782 3.333 3.333 2.500 2.500 100% 167.282 85% funds, Liability of contractor 3.500 million to Bucheki Town. Sahib be paid Provision of Sewerage System at Nankana 387 1990 130.000 61.000 3.333 3.333 2.500 2.500 100% 63.500 49% Funds fully utlized. Work stopped due to Warburton Town Nankana Sahib. Sahib non-availability of funds Provision of Rural Drainage / PCC Scheme Nankana 388 1991 for 16 Nos. of Union Councils in , District 50.000 32.599 3.333 3.333 0.000 0.000 #DIV/0! 32.599 65% Funds reapropriated, due to change of Sahib regime. Sheikhupura PCC and drainage scheme Thieng More 389 1992 Kasur 256.672 89.991 6.667 6.667 5.000 5.000 100% 94.991 37% Funds fully utlized, work stopped due to non- /Illah abad, Tehsil Chunian, District Kasur availability of funds

Construction of Sullage Carrier at Chah 390 1993 Kasur 88.300 36.983 6.667 6.667 5.000 5.000 100% 41.983 48% Funds fully utlized, work stopped due to non- Kalalanwala, Tehsil Pattoki, District Kasur availability of funds

Const. of Soling Nullah, PCC etc. Union Scheme physically completed, Balance 391 1994 Kasur 30.000 27.991 0.669 0.669 0.502 0.502 100% 28.493 95% Funds Required to clear the liability of Council Chirrawan, Tehsil & District Kasur contractor Const. of Soling, Nullah PCC etc. Badian, Funds fully utlized, work stopped due to non- 392 1995 Rai Kalan, Khurd, Baddar Pur and adjoining Kasur 30.000 24.991 1.669 1.669 1.252 1.252 100% 26.243 87% availability of funds abadies, Tehsil Kasur Const. of Soling, Nullah, PCC etc. Katlohi, Scheme physically completed, Balance 393 1996 Wadara and adjoining abadies, Tehsil & Kasur 30.000 24.999 1.667 1.667 1.250 1.250 100% 26.249 87% funds are requried to clear the contractor District Kasur liabilities Construction of PCC and Tuff Tile Funds fully utlized, work stopped due to non- 394 1997 Phoolnagar Phase-II, Tehsil Pattoki, District Kasur 188.416 30.350 10.000 10.000 7.500 7.500 100% 37.850 20% availability of funds Kasur Rural Drainage PCC Brick pavement Schemes Rao Khan wala and Beroon Rao 395 1998 Kasur 77.000 34.995 8.333 8.333 6.250 6.250 100% 41.245 54% Funds fully utlized, work stopped due to non- Khan Wala and Adjoining Abadies Tehsil & availability of funds District Kasur Rural Drainage PCC Scheme Dholan 396 1999 Kasur 114.588 99.662 4.975 4.975 3.731 3.731 100% 103.393 90% Scheme Completed District Kasur. Rural Drainage Scheme Sarhali Kalan & 397 2000 Kasur 94.174 66.977 9.063 9.063 6.797 6.797 100% 73.774 78% Funds fully utlized, work stopped due to non- Adjoining Abadies, Tehsil & District Kasur. availability of funds

Water Supply & Drainage Scheme Nathey Scheme physically completed, Balance 398 2001 Jagir, Lakhankay Abadies, Kamogill, Mega Kasur 101.853 98.860 0.998 0.998 0.749 0.749 100% 99.609 98% funds are requried to clear the contractor Jatt, Sardar Mill & Choudharian Wala. liabilities Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of PCC & drainage Scheme 399 2002 Kasur 99.000 20.000 5.000 5.000 3.750 3.750 100% 23.750 24% Funds fully utlized, work stopped due to non- Habib ababd District Kasur availability of funds Rural Drainage Scheme Baggiana, kamogil 400 2003 Kasur 90.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 25% Funds fully utlized, work stopped due to non- Jahuggian, dhinasing & Baroon Abadies availability of funds Rural Drainage Scheme Nathay Khasla Funds fully utlized, work stopped due to non- 401 2004 Sardar Mill, Garden Adda & Chohdry Jhlar Kasur 90.000 20.000 6.667 6.667 5.000 5.000 100% 25.000 28% availability of funds & dhana Rural Drainage Scheme Khanko more 402 2005 Kasur 95.000 19.995 6.667 6.667 5.000 5.000 100% 24.995 26% Funds fully utlized, work stopped due to non- Chakoki Chak No 04, Madarkhai availability of funds Rural Drainage PCC Scheme Theh Scheme physically completed, Balance 403 2006 Shaikham and Adjoining Abadies District Kasur 97.400 90.282 2.371 2.371 1.778 1.778 100% 92.060 95% funds are requried to clear the contractor Kasur. liabilities Rural Drainage & PCC Scheme Bhamba Funds fully utlized, work stopped due to non- 404 2007 Kalan & Khurd and Adjoining Abadies Kasur 95.000 77.499 5.834 5.834 5.702 5.702 100% 83.201 88% availability of funds District Kasur. Rural Drainage & PCC Scheme Bohar and 405 2008 Kasur 81.000 62.466 6.172 6.172 4.629 4.629 100% 67.095 83% Funds fully utlized, work stopped due to non- Adjoining Abadies District Kasur. availability of funds Rural Drainage & PCC Scheme Mudke UC 406 2009 Kasur 97.014 75.826 6.667 6.667 5.000 5.000 100% 80.826 83% Funds fully utlized, work stopped due to non- District Kasur. availability of funds Rural Drainage Scheme Baroon Raja Jang Funds fully utlized, work stopped due to non- 407 2010 & Adjoining Abadies, Tehsil & District Kasur 99.998 74.698 3.333 3.333 2.500 2.500 100% 77.198 77% availability of funds Kasur. Rural drainage Scheme Hanjray Kalan & Allied Abadies, Khudian, Bhaseen, Dello 408 2011 Kasur 67.952 49.988 5.984 5.984 2.988 2.988 100% 52.976 78% Funds fully utlized, work stopped due to non- Multani, Wander, Jagu Wal Tehsil Pattoki availability of funds District Kasur Rural drainage scheme Hardo Sahari, 409 2012 Kasur 87.235 60.798 20.000 20.000 16.500 16.500 100% 77.298 89% Funds fully utlized, work stopped due to non- District Kasur availability of funds Funds fully utlized, work stopped due to non- 410 2013 Rural Drainage Scheme Qadiwind Kasur 99.677 61.497 5.000 5.000 3.750 3.750 100% 65.247 65% availability of funds Rural Drainage Scheme, Lakhankey, Tehsil 411 2014 Kasur 76.899 67.976 2.974 2.974 1.236 1.236 100% 69.212 90% Work in Progress & District Kasur. Rural PCC & Drainage Scheme Green Kot Scheme physically completed, Balance 412 2015 and Ibrahimabad & Adjoining Abadies Kasur 75.000 64.963 3.343 3.343 2.507 2.507 100% 67.470 90% funds are requried to clear the contractor District Kasur. liabilities Rural PCC & Drainage Scheme Handal and 413 2016 Rawal Jhangar & adjoining abadies District Kasur 69.000 60.768 2.741 2.741 0.685 0.685 100% 61.453 89% Scheme Completed Kasur. Rural PCC & Drainage Scheme Khara and 414 2017 Kasur 50.000 39.406 3.530 3.530 2.648 2.648 100% 42.054 84% Funds fully utlized, work stopped due to non- Wadana & adjoining abadies District Kasur. availability of funds Rural PCC & Drainage Scheme 415 2018 Ramthaman and Matta & adjoining abadies Kasur 74.724 65.000 3.241 3.241 0.000 0.000 #DIV/0! 65.000 87% Scheme Completed District Kasur. Rural PCC & Drainage Scheme Zafarkey Scheme physically completed, Balance 416 2019 and Ghanikey & adjoining abadies District Kasur 50.000 47.306 0.898 0.898 0.674 0.674 100% 47.980 96% funds are requried to clear the contractor Kasur. liabilities Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA 06.03.2017,Date of TS 11.03.2017,Date of Invitation of Tender ,01.05.2017,Date of Receipt of Tender,02.05.2017,Date of work Laying of Tuff Tiles / Sewerage and Sullage Order.10.05.2017,Date of completion As per PC-I.30.06.2018 ,Anticipated date of 417 2020 Carrier in Left Over Streets in Ward No.1 to Okara 47.436 24.999 3.333 3.333 2.100 2.098 100% 27.097 57% completion, 30.06.2019,Rcc Sewer 12" i/d = 50 City Okara 12242 / 10375 Rft15" i/d = 4372 / 5275 Rft24" i/d = 128 / 1870 Rft27" i/d = 0 / 3075 RftTuff Tile 12955 / 12955 Sftsullage Carrier = 1100 / 2215 Rft Projected Population 409924 Person.

Date of AA 23.03.2016, Date of TS 25.03.2016, Date of Invitation of Tender 16.05.2016, Date of Receipt of Tenders 17.05.2016 , ( No Tender Received), Date of Re-Invitation of Tender 11.06.2016, Date Drainage schemes and soling work at UC of Receipt of Tenders,13.06.2016, Date of 418 2021 Okara 28.107 12.598 4.836 4.836 0.000 0.000 0% 12.598 45% work Order 24.06.2016, Date of completion 103 Depalpur District Okara As per PC-I. 18.06.2017, Anticipated date of completion,30.06.2019,Re-Appropreation (- ) 2.400 Projected Population 51130 Person, Work is ini progress.(TPV Awaited) The scope of work has been completed in saving due to compitative rates.

Date of AA 23.03.2016,Date of TS 25.03.2016,Date of Invitation of Tender 16.05.2016,Date of Receipt of Tenders 17.05.2016 ,( No Tender Received),Date of Re-Invitation of Tender 11.06.2016,Date of Drainage Schemes and soling work at UC Receipt of Tenders,13.06.2016,Date of 419 2022 Okara 27.990 21.521 1.080 1.080 0.000 0.000 #DIV/0! 21.521 77% work Order 18.06.2016,Date of completion 105 Depalpur District Okara As per PC-I. 18.06.2017,Anticipated date of completion,30.06.2019,Re-Appropreation (- ) 0.540 Projected Population 51398 Person,Work is ini progress.(TPV Awaited) The scope of work has been completed in saving due to compitative rates.

Date of AA 08.03.2017,Date of TS 20.03.2017,Date of Invitation of Tender 25.05.2017,Date of Receipt of Tenders 26.05.2017,Date of work Order.02.06.2017,Date of completion As per PC-I.31.12.2017,Anticipated date of Rural water Supply & Sewerage Drainage completion, 30-06-2019Tubewell Boring = 1 / 1 NoRising Main Dirtribution System 3" = 420 2023 Scheme, Behlolpur, Tehsil Depalpur, Okara 19.075 18.063 0.326 0.326 0.245 0.163 67% 18.226 96% 14622 / 15171 Rft4" i/d = 738 / 740 Rft6" i/d Okara. = 1126 / 1117 Rft8" i/d = 1217 / 1250 RftOHR 20000 Glns 1 / 1.NO. Staff quarter = 1/ 1 No External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 1464 / 2327 RftBrick Pavement = 18127 / 18127 Cft Sullage Carreir = 228 / 1570 RftProjected Population 24422 Person. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order.02.06.2017, Date of completion As per PC-I.31.12.2017, Rural water Supply & Sewerage Drainage Anticipated date of completion, 30.06.2019,Tubewell Boring = 1 / 1 421 2024 Scheme, Arrora Mian Khan, Tehsil Okara 28.303 22.499 1.934 1.934 3.951 3.877 98% 26.376 93% NoPump House 1 / 1 NoRising Main Depalpur, Okara. Dirtribution System 3" = 36298 / 36298 Rft4" i/d = 20222 / 18707 Rft6" i/d = 4091 / 4320 Rft8" i/d = 1718 / 842 RftOHR 20000 Glns 1 / 1.NO. 90%Staff quarter = 1/ 1 No External Electrification 1 / 1 Job D.N Paid to Wapda Projected Population 24422 Person.

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order 02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, 31.12.2019, Rural water Supply & Sewerage Drainage Tubewell Boring = 1 / 1 NoPump House = 1 / 1 NORising Main Dirtribution System 3" = 422 2025 Scheme, Bhai Rao Key, Tehsil Depalpur, Okara 15.441 11.056 1.460 1.460 0.730 0.730 100% 11.786 76% 12256 / 13904 Rft4" i/d = 2316 / 2316 Rft6" Okara. i/d = 438 / 438 Rft8" i/d = 1217 / 1250 RftOHR 10000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 0 / 3124 RftBrick Pavement = 9913 / 13491 Cft Sullage Carreir = 1524 / 1890 Rft Projected Population 24422 Person.

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender,25.05.2017, Date of Receipt of Tenders, 26.05.2017, Date of work Order.02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, 30.06.2019,Tubewell Boring = 1 Rural water Supply & Sewerage Drainage / 1 NoPump House = 1 / 1 NORising Main 423 2026 Okara 25.728 19.496 2.076 2.076 1.557 1.038 67% 20.534 80% Dirtribution System 3" = 29802 / 29802 Scheme, Bhukan, Tehsil Depalpur, Okara. Rft4" i/d = 4092 / 3726 Rft6" i/d = 3278 / 3201 Rft8" i/d = 1186 / 1186 Rft10" i/d = 0 / 115 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 0 / 1078 RftBrick Pavement = 14740 / 8692 Cft Sullage Carreir = 3378 / 3785 Rft Projected Population 24422 Person.

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order.02.06.2017, Date of completion As per PC-I.31.12.2017, Aniticipated date of completion, 30-06- Rural water Supply & Sewerage Drainage 2019Tubewell Boring = 1 / 1 NoPump House = 1 / 1 NORising Main Dirtribution 424 2027 Scheme, Jhunjh Kalan, Tehsil Depalpur, Okara 25.728 22.607 1.039 1.039 0.779 0.520 67% 23.127 90% System 3" = 21883 / 16712 Rft4" i/d = 3545 Okara. / 3545 Rft6" i/d = 2507 / 2604 Rft8" i/d = 372 / 394 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 3760 / 3760 RftBrick Pavement = 20085 / 23881 Cft Sullage Carreir = 2800 / 3240 Rft Projected Population 24422 Person. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order 02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, 30-06- Rural water Supply & Sewerage Drainage 2019Tubewell Boring = 1 / 1 NoPump 425 2028 Scheme, Kot Shah Mushtaq, Tehsil Okara 22.049 21.029 0.340 0.340 0.255 0.251 98% 21.280 97% House = 1 / 1 NORising Main Dirtribution Depalpur, Okara. System 3" = 17937 / 16042 Rft4" i/d = 576 / 833 Rft6" i/d = 1511 / 1511 RftOHR 10000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 6315 / 6362 RftBrick Pavement = 31044 / 20154 Cft Sullage Carreir = 930 / 2780 Rft Projected Population 24422 Person.

Date of AA- 08.03.2017, Date of TS- 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order.02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, Rural water Supply & Sewerage Drainage 31.12.2019,Tubewell Boring = 1 / 1 NoPump House = 1 / 1 NORising Main 426 2029 Scheme, Lalay Wala, Tehsil Depalpur, Okara 21.017 18.798 0.398 0.398 0.299 0.199 67% 18.997 90% Dirtribution System 3" = 17346 / 17346 Okara. Rft4" i/d = 1554 / 1563 Rft6" i/d = 899 / 908 Rft8" i/d = 986 / 992 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 2675 / 3651 RftBrick Pavement = 18200 / 15103 Cft Sullage Carreir = 750 / 2830 Rft Projected Population 24422 Person.

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order.02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, Rural water Supply & Sewerage Drainage 31.12.2019Tubewell Boring = 1 / 1 NoPump House = 1 / 1 NORising Main Dirtribution 427 2030 Scheme, Phularwa Wazirkey, Tehsil Okara 23.747 18.351 1.797 1.797 1.348 0.896 66% 19.247 81% System 3" = 19028 / 17312 Rft4" i/d = 3537 Depalpur, Okara. / 3539 Rft6" i/d = 1092 / 1092 Rft8" i/d = 2047 / 2055 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 1368 / 3651 RftBrick Pavement = 14796 / 15103 Cft Sullage Carreir = 120 / 2830 Rft Projected Population 24422 Person. Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order 02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, 31.12.2019,Tubewell Boring = 1 / 1 Rural water Supply & Sewerage Drainage NoPump House = 1 / 1 NORising Main 428 2031 Scheme, Shah Pur, Tehsil Depalpur, Okara 19.862 18.978 0.294 0.294 0.221 0.147 67% 19.125 96% Dirtribution System 3" = 28079 / 28079 Okara. Rft4" i/d = 2086 / 2963 Rft6" i/d = 1321 / 1327 Rft8" i/d = 500 / 500 Rft10" i/d = 235 / 235 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 1115 / 2191 RftBrick Pavement = 17494 / 13511 Cft Sullage Carreir = 490 / 2540 Rft Projected Population 24422 Person. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA 08.03.2017, Date of TS 20.03.2017, Date of Invitation of Tender 25.05.2017, Date of Receipt of Tenders 26.05.2017, Date of work Order 02.06.2017, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, 31.12.2019, Rural water Supply & Sewerage Drainage Tubewell Boring = 1 / 1 NoPump House = 1 429 2032 Okara 16.746 14.842 0.633 0.633 0.475 0.317 67% 15.159 91% / 1 NORising Main Dirtribution System 3" = Scheme, Shinwal, Tehsil Depalpur, Okara. 21241 / 21241 Rft4" i/d = 2389 / 2403 Rft6" i/d = 807 / 908 Rft8" i/d = 198 / 992 RftOHR 10000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 1153 / 1890 RftBrick Pavement = 11331 / 7688 Cft Sullage Carreir = 1035 / 1780 Rft Projected Population 24422 Person.

Date of AA 03.08.2016, Date of TS 20.03.2017, Date of Invitation of Tender 11.10.2016, Date of Receipt of Tenders 13.10.2016, Date of work Order 17.11.2016, Date of completion As per PC-I.31.12.2017, Anticipated date of completion, 31.12.2019, Rural water Supply and Drainage Scheme, Tubewell Boring = 1 / 1 NoPump House = 1 430 2033 Okara 20.215 19.350 0.288 0.288 0.216 0.216 100% 19.566 97% / 1 NORising Main Dirtribution System 3" = Jaithpur Depalpur 18625 / 13143 Rft4" i/d = 3540 / 3565 Rft6" i/d = 748 / 748 Rft8" i/d = 245 / 245 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 1545 / 2843 RftBrick Pavement = 26631 / 12516 Cft Sullage Carreir = 450 / 2999 Rft Projected Population 10309 Person

Date of AA 31.08.2016,Date of TS 22.11.2016,Date of Invitation of Tender Rural Drainage Scheme Tuff Tiles PCC 09.12.2016,Date of Receipt of Tenders Sewerage and Soling, 3SP, 43SP, Khurpy 10.12.2016,Date of work 44SP Waltoya Matan Wala Amliya Key Order.05.01.2017,Date of completion As 431 2034 Okara 97.984 95.372 0.868 0.868 0.651 0.433 67% 95.805 98% per PC-I.30.06.2018 ,Anticipated date of Suhag, Nihal Muhar, Mahlo sheikhu, completion, 30.06.2019,Surface Drain Typr - Mahant Darshan Nama Jindida, District I = 38776 / 87983 RftSurface Drain Type -II Okara = 0 / 2025 RftBrick Pavement = 438359 / 438359 CftSullage Carrier = 6260 / 12413 RftProjected Population 24422 Person.

• Date of AA =22.02.2017,• Date of TS =24.02.2017,• No. of Beneficiaries = 66404• Anticipated date of completion 30.06.2020• Latitude=30.64671333333333• Longitude= 73.10561333333334RCC Sewer 9” i/d = 432 2035 Sewerage Scheme in Sahiwal City Sahiwal 27.844 22.271 0.748 0.748 0.561 0.560 100% 22.831 82% 158/825 RftRCC Sewer 12” i/d = 2767/1010 RftRCC Sewer 15” i/d = 2002/870 RftInter Connection=0/2 JobDiesel Generator=1/1 No.Generator Room=1/1 No.Pumping Machinery=3/3 SetWork in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

• Date of AA=10.01.2017,• Date of TS =03.03.2017,• No. of Beneficiaries = 313344• Date of Pre-qualification =11.04.2017 ,• Date of receipt of tender =17.04.2017,• Date of Work Order =15.05.2017,• Anticipated date of completion=30.06.2020• Latitude=30.69253833333333• Longitude= Sewerage Scheme Sahiwal City, City Bund 73.125006666666669" i/d RCC Pipe =1996/26350 Rft12" i/d RCC Pipe 433 2036 Road, LBDC, High Street & Girls College Sahiwal 167.605 74.784 10.000 10.000 7.500 7.000 93% 81.784 49% =9664/4525 Rft15" i/d RCC Pipe Road =5047/9060 Rft18" i/d RCC Pipe =3671/3536 Rft21" i/d RCC Pipe =2343/430 Rft24" i/d RCC Pipe =411/670 Rft27" i/d RCC Pipe =1496/640 Rft30" i/d RCC Pipe =532/475 Rft33" i/d RCC Pipe =1270/1150 Rft36" i/d RCC Pipe =1410/1375 RftStaff Quarter & Complaint Office=0/1 JobInter Connection=0/1 JobPumping Machinery=2/2 SetWork in progress.

Date of A.A= 31.08.2016, Date of T.S= 09.09.2016, Date of Prequalification = 05.01.2017, Date of receipt of tenders = 23.01.2017, Date of work order= 30.01.2017, Date of completion as per PC- 1= 30.06.2018, Date of completion as per agreement= 30.06.2018, No. of beneficiaries= 14050 persons, Funds released by FD = 03.08.2018, Funds online = 13.08.2018, Disposal station completed Provision of Sewerage / Drainage / Street and made functional and handed over to CBO. Latitude longitude 434 2037 Pavements, etc in Chak No. 147/EB Tehsil Pakpattan 72.933 50.997 4.155 4.155 3.116 3.116 100% 54.113 74% 30.296131666666664,73.03730666666667 Arifwala District Pakpattn Surface Drain Type-I= 100 RftBrick Pavement=52148/57170 CftTuff Tile= 0/50600 SftRCC Sewer 9''i/d 10360/10365 Rft 12''i/d 6658/6659 Rft 15''i/d 62180/2180 Rft 18''i/d 460/495 Rft 21'i/d 1460/1460 RftS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Chamber = 1/1NoP/Machinery = 2/2 SetSullage Carrier= 2150/2450 RftBoundry Wall= 650/680 RftStaff Quarter= 1/1 NoExternal Eletrifaction= 1/1 JobWork in progress.

Date of A.A= 16.03.2017, Date of T.S= 20.03.2017, Date of invitation of tenders=16.05.2017, Date of receipt of tenders = 20.05.2017, Date of work order= 24.05.2017, Date of completion as per PC- 1= 30.06.2018, Date of completion as per agreement= 30.06.2018, No. of beneficiaries= 5749 persons, Funds Provision of Sewerage / Drainage Scheme released by FD = 03.08.2018, Funds online 435 2038 Chak No. 64/EB, Arifwala, District Pakpattan 36.218 26.920 3.099 3.099 2.324 2.324 100% 29.244 81% = 13.08.2018, Latitude longitude Pakpattan. 30.380734999999998,72.92715833333334 Surface Drain Type-I= 0/250 Rft Brick Pavement=37329/56997 CftRCC Sewer 9" i/d 8709/11485 RFt12" i/d 4351/2900 RFt15" i/d 633/410 RFtS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Chamber = 1/1NoP/Machinery = 1/1 SetSullage Carrier= 542/1327 RftBoundry Wall= 0/300 Rft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A= 13.10.2016, Date of T.S= 25.10.2016, Date of invitation of tenders=18.11.2016, Date of receipt of tenders = 10.12.2016, Date of work order= 02.01.2017, Date of completion as per PC- 1= 30.06.2018, Date of completion as per agreement= 30.06.2018, No. of beneficiaries= 14825 persons, Funds released by FD = 03.08.2018 , Funds online = 13.08.2018, Latitude longitude Rural Sewerage/Drainage Scheme 38/EB 436 2039 Pakpattan 32.095 13.986 3.333 3.333 2.500 2.250 90% 16.236 51% 30.40649,73.03111166666666Surface Arifwala Drain Type-I= 0/10113 Rft Brick Pavement=0/36986 CftRCC Sewer 9''i/d 12126/2925 Rft 12''i/d 2880/1240 Rft 15''i/d 775/1860 Rft 18''i/d 390/1263 Rft 21'i/d 1060/250 RftS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Chamber = 1/1NoP/Machinery = 1/2 SetSullage Carrier= 1050/550 RftBoundry Wall= 300/400 RftStaff Quarter= 0/1NoExter/ Electrifaction = 1/1Job Scheme made functional. Work in progress. 1. Date of AA 09.03.2015 (16.05.2016) 2. Date of T.S 15.05.2015 3. Dated of Prequalification __ 4. Date of invitation of tender 24.03.2015 5. Date of Receipt of Rural Drainage Nizam Wala Nawab Pur tenders 25.03.2015 6. Date of work order 437 2040 Multan 19.295 14.295 1.667 1.667 0.000 0.000 #DIV/0! 14.295 74% 29.05.2015 7. Date of Completion as per Road District Multan PC-l 08.03.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries 2768 persons. Scheme completed. 1.Date of AA 09.03.2015 2.Date of T.S 21.04.2015 3.Dated of Prequalification 28.01.2015 4.Date of invitation of tender 27.04.2015 5.Date of Receipt of tenders Rural Drainage Scheme Sewra Chok 02.05.2015 6.Date of work order 02.06.2015 438 2041 Adjoining Abadies Mouza Mubarak Pur Taj Multan 99.890 89.890 3.333 3.333 2.700 2.250 83% 92.140 92% 7.Date of Completion as per PC-l Pur Sandila 08.03.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 46964 persons. Work is in progress 1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: 02.11.2016 6. Sewerage Drainage Scheme Matotli 439 2042 Multan 46.000 35.000 3.667 3.667 2.750 2.725 99% 37.725 82% Date of Award: 10.11.2016 7. Date of Qaiserpur Shujabad Completion as per PC-I: 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress

1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of Prequalification 12.03.2016 4.Date of invitation of tender 07.04.2016 Rural Sewerage Drainage Scheme Chah 5.Date of Receipt of tenders 09.04.2016 6.Date of work order 27.05.2016 7.Date of 440 2043 Rattay wala Mouza Jangal Barirah District Multan 28.800 22.792 1.667 1.667 1.250 1.213 97% 24.005 83% Completion as per PC-l 26.11.2016 8. Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 8253 Persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 27.10.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: 02.11.2016 6. Rural Sewerage Drainage Scheme Mill 441 2044 Multan 87.080 75.000 4.027 4.027 6.428 6.202 96% 81.202 93% Date of Award: 18.11.2016 7. Date of Sadiqabad Completion as per PC-I: 17.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= 23659 Persons. Work is in progress

1.Date of AA 14.11.2009 2.Date of T.S 19.01.2010 3.Dated of Prequalification - 4.Date of invitation of tender 30.01.2010 5.Date of Receipt of tenders 15.03.2010 Rural Sewerage Drainage Scheme Mouza 442 2045 Multan 46.400 41.400 1.667 1.667 1.250 1.249 100% 42.649 92% 6.Date of work order 20.03.2010 7.Date of Jahangirabad Multan Completion as per PC-l 08.03.2013 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 2250 persons. Work is in progress

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 09.11.2016 5. Date of Rural Sewerage Drainage Scheme Pakkay Receipt of Tender: 10.11.2016 6. Date of Award: 16.12.2016 7. Date of Completion 443 2046 Wala Anayat Pur Mahota Tehsil and District Multan 29.930 25.833 1.167 1.167 0.875 0.800 91% 26.633 89% as per PC-I: 15.06.2018 8. Anticipated date Multan of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress

1.Date of AA 12.03.2016 2.Date of T.S 3.Dated of Prequalification 12.03.2016 4.Date of invitation of tender 07.04.2016 Rural Sewerage Drainage Scheme 5.Date of Receipt of tenders 09.04.2016 6.Date of work order 01.06.2016 7.Date of 444 2047 Saddiqabad Hirawat and Yaray wala Multan 22.840 20.937 0.515 0.515 0.386 0.349 90% 21.286 93% Completion as per PC-l 31.11.2016 8. District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 25285 Persons. Work is in progress

1.Date of AA 25.03.2017 2.Date of T.S 01.04.2017 3.Dated of Prequalification - 4.Date of invitation of tender 20.04.2017 5.Date of Receipt of tenders 21.04.2017 Rural Sewerage Scheme Chah Sunna 445 2048 Multan 13.360 8.887 1.490 1.490 1.118 1.115 100% 10.002 75% 6.Date of work order 23.05.2017 7.Date of Wala Multan. Completion as per PC-l 22.07.2017 8. Anticipated date of completion 30.04.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4648 persons. Work is in progress

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: 02.11.2016 6. Date of Award: 10.11.2016 7. Date of 446 2049 Rural Sewerage Schemes Ambala Multan 50.000 44.336 1.714 1.714 1.286 1.285 100% 45.621 91% Completion as per PC-I: 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender 15.05.2017 5. Date of Rural Drainage, Sewerage, Solding and Receipt of tenders 16.05.2017 6. Date of Tuff Tiles Scheme Gardezpur, Dhandho, 447 2050 Multan 7.000 3.635 1.078 1.078 0.000 0.000 #DIV/0! 3.635 52% work order 31.05.2017 7. Date of Bagrain Ghangi, Amanullah Shah Wains & Completion as per PC-l 30.07.2017 8. Anticipated date of completion 30.06.2019 Marha, District Multan 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving.

1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender 15.05.2017 5. Date of Rural Drainage, Sewerage Scheme Mithu Receipt of tenders 16.05.2017 6. Date of work order 31.05.2017 7. Date of 448 2051 Shrqi, Basti Mithu Gharbi, Basti Dad Shah Multan 7.000 3.921 1.012 1.012 0.018 0.018 100% 3.939 56% Completion as per PC-l 30.07.2017 8. Moosa Muqeempur, District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving.

1. Date of AA 11.04.2017 2. Date of T.S - 3. Dated of Prequalification - 4. Date of invitation of tender 15.05.2017 5. Date of Receipt of tenders 16.05.2017 6. Date of Rural Drainage, Sewerage Scheme Basti 449 2052 Multan 6.000 3.464 0.802 0.802 0.000 0.000 0% 3.464 58% work order 31.05.2017 7. Date of Dodwpur, Basti Shahpur, District Multan Completion as per PC-l 30.07.2017 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving.

1. Date of A.A: 27.08.2016 2. Date of T.S: - 3. Date of Pre-Qualification: 30.09.2016 4. Date Invitation of Tender: 01.11.2016 5. Date of Receipt of Tender: 02.11.2016 6. Date of Award: 12.11.2016 7. Date of 450 2053 Rural Sewerage Scheme Basti Laar Multan 50.000 35.000 1.000 1.000 0.750 0.680 91% 35.680 71% Completion as per PC-I: 11.05.2018 8. Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 23.11.2018 24.01.2019 10.No. of Benificiary= Persons. Work is in progress.

1. Date of A.A: 27-08-2016. 2. Date of T.S: 26-09-2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt of Tender: 15-11-2016 6. Sewerage, Tuff Tiles in Remaining Portion Date of Award: 08-12-2016 7. Date of 451 2054 Lodhran 62.170 28.077 6.667 6.667 5.000 4.800 96% 32.877 53% Completion as per PC-I: 31-12-2017 8. of Gaily Wal City. Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 32835 Persons. Work is in Progress.

1. Date of A.A: 27-08-2016. 2. Date of T.S: 19-09-2016 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 14-11-2016 5. Date of Receipt of Tender: 15-11-2016 6. Date of Award: 24-11-2016 7. Date of Tuff Tiles & Sewerage Scheme for 452 2055 Lodhran 45.795 32.717 4.359 4.359 1.112 1.112 100% 33.829 74% Completion as per PC-I: 30-06-2017 8. remaining portion of Gogran City. Anticipated Date of Completion: 23-01-2018 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 16528 Persons. Scheme is functional & handed over to the community. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 27.08.2016 2. Date of T.S: 25.10.2016 3. Date of Pre-Qualification: 22.10.2016 4. Date of Invitation of Tender: 29.11.2016 5. Date of Receipt of Tender: Provision / Laying of Sewer Lines in 05.12.2016 6. Date of Work order: 15.12.2016 7. Date of Completion as per 453 2056 Missing Areas of Khanewal City including Khanewal 100.000 55.895 6.667 6.667 5.000 5.000 100% 60.895 61% PC-I: 30.06.2018 8. Anticipated Date of new and old Azafi Abad completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 379227 Persons Work is in progress.

1. Date of A.A: 25.04.2017 2. Date of T.S: 04.05.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 03.06.2017 5. Date of Receipt of Tender: Provision of Drains, Soling Culverts etc to 05.06.2017 6. Date of Work order: 454 2057 different abadies of PP-212, Tehsil Khanewal 40.000 22.000 6.000 6.000 4.500 4.500 100% 26.500 66% 07.06.2017 7. Date of Completion as per Kabirwala, Khanewal PC-I: 30.06.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 10. Reason of Slow Moving: ------11 No. of beneficiaries 7819 Persons Work in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage Scheme Chak No.88/10-R District 455 2058 Khanewal 10.000 3.000 2.333 2.333 1.750 1.750 100% 4.750 48% 09.11.2017 7. Date of Completion as per Khanewal PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5120 Persons Work is in progress.

1. Date of A.A: 21.02.2017 2. Date of T.S: 25.02.2017 3. Date of Pre-Qualification: 4. Date of Invitation of Tender: 20.05.2017 5. Date of Receipt of Tender: 22.05.2017 6. Provision of Tuff Pavement in Gaggo Mandi Date of Work order: 7. Date of Completion 456 2059 Vehari 49.970 28.688 3.333 3.333 2.500 2.500 100% 31.188 62% as per PC-I: 26.05.2019 8. Anticipated Date / Dharian / Chak No. 187/EB of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of beneficiaries 13005 Persons Work is in progress.

1. Date of A.A: 27-08-2016 2. Date of T.S: 02.09.2016 3. Date of Pre-Qualification: ____ 4. Date Invitation of Tender: 06.12.2016 5. Date of Receipt of Tender: Rehabilitation of Sewerage & Drainage 07.12.2016 6. Date of Award: 22.12.2016 7. 457 2060 Scheme Machiwal, Tehsil and District Vehari 22.396 19.450 0.982 0.982 0.737 0.737 100% 20.187 90% Date of Completion as per PC-I: 21.12.2017 Vehari. 8. Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11 No. of beneficiaries 11435 Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 21.01.2013 2. Date of T.S: 22..01.2013 3. Date of Pre-Qualification: 4. Date Invitation of Tender: 14.02.2013 5. Date of Receipt of Tender: 16.02.2013 6. Execution of Forty (40) Misc. Development Date of Award: 26.02.2013 7. Date of 458 2061 Vehari 27.500 21.681 1.000 1.000 0.750 0.750 100% 22.431 82% Completion as per PC-I: 26.05.2013 8. Schemes in NA-167, District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 23.11.2018 24.01.2019 10. Reason of Slow Moving: - 11. No. of Beneficiary= Persons Work is in progress. Provision of Sewerage & Tuff Tiles for Dajal 459 2062 Rajanpur 120.100 34.990 28.367 28.367 21.275 21.275 100% 56.265 47% "• Date of A.A = 05.11.2016 City Construction of Drain, Brick Pavement 460 2063 Sullage Carrier Culverts, Tuff Tile Rajanpur 29.990 25.694 1.000 1.000 0.000 0.000 #DIV/0! 25.694 86% "• Date of A.A = 17.12.2014 Muhammad Pur Dewan Rajanpur Construction of Drain, Brick Pavement 461 2064 Sullage Carrier Culverts, Tuff Tile Fazilpur Rajanpur 50.000 25.952 1.000 1.000 0.000 0.000 #DIV/0! 25.952 52% "• Date of A.A = 17.12.2014 Rajanpur Comprehensive Sewerage / Drainage / Soling / PCC / Tuff Tile scheme at 462 2065 Muzaffargarh 25.000 22.152 0.949 0.949 0.172 0.172 100% 22.324 89% Scheme completed in saving Sanawan Town, District Muzaffargarh (Remaining Portion) Construction of Drain Brick Pavement, RCC 463 2066 Culverts, VR Bridge and Sullage Carrier in Muzaffargarh 42.270 10.000 10.757 10.757 8.068 8.034 100% 18.034 43% Work is in progress UC Wainse No. 76 Tehsil Jatoi

Construction of Drain Brick Pavement, RCC 464 2067 Culverts, VR Bridge and Sullage Carrier in Muzaffargarh 43.350 10.000 11.117 11.117 8.338 8.307 100% 18.307 42% Work is in progress UC Bairband No. 84 Tehsil Jatoi

Construction of Drain Brick Pavement, RCC 465 2068 Culverts, VR Bridge and Sullage Carrier in Muzaffargarh 43.730 10.000 11.243 11.243 8.432 8.388 99% 18.388 42% Work is in progress UC Kotla Gamoon No. 77 Tehsil Jatoi Sewerage / Drainage Scheme for Rangpur 466 2069 Muzaffargarh 241.100 48.442 56.667 56.667 42.500 33.575 79% 82.017 34% Screening Chamber 02 Nos. Muzaffargarh Rural Sewerage / drainage scheme Shah 467 2070 Muzaffargarh 68.504 63.220 1.000 1.000 6.080 0.000 0% 63.220 92% Scheme completed, liabilities of contractor Jamal cleared Rural Sewerage/Drainage Scheme Dhori 468 2071 Adda & Adoining Abadies Chak No. 426AB Layyah 198.000 63.732 25.010 25.010 18.758 18.748 100% 82.480 42% • Date of AA = 25.10.2014 & 438/TDA (Revised) Rural Drainage/Sewerage & Nallian Mosan Shah, Mongarh, Ahsin & Waddeh wali UC 469 2072 Layyah 30.000 10.000 6.667 6.667 5.000 5.000 100% 15.000 50% • Date of AA = 29.07.2017 Wara Sehran Tehsil Karoor Lal Essen District Layyah Sewerage scheme Chak No. 110/TDA, 470 2073 Layyah 30.000 20.395 3.202 3.202 2.402 2.402 100% 22.797 76% • Date of AA = 22-09-2016 Tehsil Karor, District Layyah Sewerage scheme Chak No. 229/TDA, 471 2074 Layyah 30.000 15.000 5.000 5.000 4.500 3.750 83% 18.750 63% • Date of AA = 22-09-2016 Tehsil Karor, District Layyah Sewerage scheme Chak No. 251/TDA, 472 2075 Layyah 30.000 14.952 5.016 5.016 3.762 3.747 100% 18.699 62% • Date of AA = 22-09-2016 Tehsil Karor, District Layyah Construnction of soling & drain/Nallian in 473 2076 UC Baseera Tehsil Karoor District Layyah Layyah 30.000 17.200 4.267 4.267 3.200 3.200 100% 20.400 68% • Date of AA = 29.07.2017 NA-181 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. Tender received on 14-11-2016 Date of award-03-01-2017 Date of completion=02-12-2017 Anticipated date of completion 31.12.2019.Date of receipt of 474 2077 Construction of Sewerage chak no. 63,DB. Bahawalpur 18.845 14.803 1.340 1.340 1.455 1.450 100% 16.253 86% funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.0.450 million provided through re- appropriation dated 19.10.2018.Work is in progress. Lattitude/Longitude. 29.16558166666667,71.62467333333333

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Tender received on 14-11- Provision of Sewerage / Tuff Tile in Basti 2016 Date of award-03-01-2017 Date of Jhangara Sharqi, Mouza Jhangara Sharqia, 475 2078 Bahawalpur 29.895 26.878 1.003 1.003 1.229 1.229 100% 28.107 94% completion=02-12-2017 Anticipated date of Union Council Bahawalpur Ghalvan, Tehsil completion 31.12.2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Ahmedpur Sharqia, District Bahawalpur. Work is in progress.. Lattitude/Longitude. 29.3978613,71.2032921

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Date of receipt of Tender 14.11.2016. Date of award 30.11.2016. Date of completion 29.10.2017. Anticipated 476 2079 Sewerage & Tuff Tile Jamalpur Bahawalpur 29.526 22.718 2.269 2.269 1.702 1.700 100% 24.418 83% date of completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.. Lattitude/Longitude. 29.76793541572988,72.41130525246263

Date of A.A= 18-08-2015. Date of T.S= 28- 08-2015. Date of receipt of tenders = 08-03- 2016.Date of work order= 18.04.2016..Date of completion as per agreement=17.04.2017.Anticipated date of Sewerage / Drainage Scheme, Chak No. completion = 30.06.2018. Date of receipt of 477 2080 Bahawalpur 29.725 27.964 0.133 0.133 0.000 0.000 #DIV/0! 27.964 94% funds by F.D. 20.07.2018 & 11.01.2019. 110/DB Scheme completed in saving & handed over to CBO on 15-01-2019. Excess funds Rs.0.100 million surrendered through re- appropriation by C.E(S), PHED Lahore dated 17-04-2019. Lattitude/Longitude. 29.078478333333337,71.65292833333334

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Date of receipt of tender 14-11- 2016 Date of award 15-12-2016 Date of completion 14-11-2017 Anticipated date of completion 30-06-2020 Date of receipt of Sewerage Scheme Chak no. 15/Ford wah, 478 2081 Bahawalpur 15.616 8.287 1.855 1.855 0.391 0.390 100% 8.677 56% funds by F.D. 20.07.2018 & 11.01.2019. Tehsil Hasilpur. Funds Rs.0.500 million surrendered vide Chief Engineer(S),PHED Lahore No.72- 78/B(4) dated 10.01.2019. Further funds Rs.0.500 surrendered dated 19-02-2019. Work is in progress.. Lattitude/Longitude. 29.73114900290966,72.61624387465417 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. Date of Receipt of tender 14.11.2016. Date of award 15.12.2016 Date of completion 14.11.2017. Anticipated date of completion 30-06-2020 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. 479 2082 Rural Sewerage Scheme 17/F.W Bahawalpur 25.000 13.450 3.833 3.833 1.075 1.070 100% 14.520 58% Funds Rs.0.800 million surrendered vide Chief Engineer(S),PHED Lahore No.72- 78/B(4) dated 10.01.2019. Further funds Rs.1.00 surrendered dated 19-02-2019. Work is in progress. Lattitude/Longitude. 29.710207236930728,72.58167296648026

Date of AA. 08.08.2016. Date of T.S. 13.10.2016. .Date of Receipt of tender 14.11.2016. Date of award 15.12.2016 Date of completion 14.11.2017/ Anticipated date 480 2083 Rural Sewerage Scheme Basti Chohan Bahawalpur 21.500 10.625 3.510 3.510 2.633 2.500 95% 13.125 61% of completion 30-06-2020 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.79157330468297,72.51960882917047

Date of AA. 21.10.2016.Date of T.S. 26.10.2016.Date of Tender Construction of Sewerage Drainage 12.12.2016Funds released by FD 04-07- Schemes Abadi Jodheka QasimKa Chak Bahawalnaga 2017 & 06-10-2017.Date of receipt of tender 481 2084 99.996 29.990 23.335 38.335 17.501 17.500 100% 47.490 47% 14-12-2016 Date of award 19-01-2017Date Sarkari Bagar Wala Khoo Chavek, Toba r of completion 18-12-2017Anticipated date Balochan Tehsil & Distt. Bahawalnagar of completion 30-06-2020 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of AA. 15-10-2015 Date of TS. 22-02- 2016Prequalification of the contractor=22- 03-2016Date of invitation of tenders=24-03- 2016Date of receipt of tenders = 07-04- 2016Date of award= 30-04-2016.Date of completion as per agreement=29-04- 2018.Expected date of completion 30-06- Sewererage and Drainage Scheme Maroot Bahawalnaga 482 2085 120.980 52.857 22.665 22.665 19.222 19.222 100% 72.079 60% 2020Date of receipt of funds by F.D. Tehsil Fortabbas District Bahawalnagar r 20.07.2018 & 11.01.2019. Funds Rs.2.223 million provided through reappropriation dated 19-02-2019. The Scheme is partially functioning and handed over to the user committee on 27-02-2019.The balance work will be completed as well as the balance funds received from the Government

Date of AA. 08.02.2011.Date of T.S. 08.02.2011.Date of award. 11.03.2011Date Comprehensive Urban / Draiange Bahawalnaga 483 2086 72.683 69.236 1.000 1.000 1.000 0.500 50% 69.736 96% of completion 30.06.2012.Funds released Sewerage Scheme Doonga Boonga r by FD on 12-11-2018 & 11.01.2019 .Scheme completed & handed over to MC on 30-06-2014. Liability cleared

"Date of AA(DDWP)=28-10-2016. Date of T.S. 13.02.2017. Tenders received on 13-03- 2017 . Date of work awarded .25-04-2017. Provision of water Supply /Sewerage Rahim Yar Date of completion 24-04-2019. Anticipated 484 2087 scheme for MC Tranda Saway Khan, Tehsil 121.000 32.590 29.466 29.466 22.100 22.070 100% 54.660 45% date of completion 30-06-2020. Date of Khan & District RYK receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 28.487481666666667 / 70.40674666666668 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of A.A= 26-02-2016. Date of T.S= 05- 05-2016. Date of prequalification. 03-08- 2016. .Date of tender received on 10-10- 2016. Date of award= 16-11-2016. Date of completion= 15-04-2018. Anticipated date Construction of Sewerage Open Drain in Rahim Yar 485 2088 97.240 52.148 14.698 34.698 12.520 12.475 100% 64.623 66% of completion 30-06-2020. Date of receipt of Chachran Sharif Khan funds by F.D. 20.07.2018 & 11.01.2019. Funds amounting to Rs.1.496 million provided by Chief Engineer(S), PHED Lahore on 13-03-2019. Work is in progress. Latitude / longitude 28.870943333333337 / 70.45938500000001

Date of AA =17-09-2016. Date of TS=23-11- 2016. Prequalification of contractors 05-01- 2017. Date op receipt of Tenders 06-02- 2017. Date of work awarded 17.03.2017. Urban water Supply / Sewerage Scheme Rahim Yar 486 2089 121.750 49.980 23.917 23.917 17.938 17.411 97% 67.391 55% Date of completion 16.09.2018. Anticipated for City Tranda Muhammad Pannah Khan date of completion 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 29.100585000000002 / 70.91535166666667

"Date of AA. 24.10.2016. Date of T.S. 29.11.2016. Tenders received on 16-01- 2017. Date of work awarded 08-02-2017. Sewerage & Tuff tiles in UC 36, 37, 38, 40, Rahim Yar Date of completion 07-08-2017. Anticipated 487 2090 35.000 20.000 1.000 1.000 0.750 0.710 95% 20.710 59% date of completion 30-06-2020. Funds 41, 42 and 71 under Rahim Yar Khan Khan released by FD on 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.51231833333333 / 70.22775666666666

Date of A.A= 30-12-2015. Date of RAA= 23- 09-2016. Date of T.S. 30.09.2016. Date of prequalification= 03-08-2016. Date of tender= 21-10-2016. Date of work Sewerage Scheme R.Y.Khan City with awarded=19-12-2016. Date of Treatment Plant-Construction of Rahim Yar completion=18-05-2017. Anticipated date of 488 2091 481.825 421.239 2.000 2.000 1.500 1.450 97% 422.689 88% completion 08-10-2018. Funds released by Intermediate Pumping Station Near Niazi Khan FD on 11.01.2019. The scheme is Colony & Installation of Force Main completed and functional. Libility of Contractor is yet to be cleared. Estimate submitted to P&D Department Lahore for revised A.A. Latitude / longitude 28.395944999999998 / 70.31435666666667

1. Date of AA = 20.10.2016 2. Date of TS = 25.10.2016 3.Date of Award of work 17.12.2016 4.Dated of Released Funds 5. No. of Beneficiaries = 1891 Provision of Sewerage in Chak No 141JB Persons.Surface Drain/Type- I= 29834- 489 2092 Chiniot 31.350 25.000 2.117 2.117 1.588 1.525 96% 26.525 85% RftBrick Pavement / PCC= 45918- Khokhran Tehsil & District Chiniot Rft.Sullage Carrier= 6029-Rft.Funds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat,31.580018 Long, 72.8859062 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of AA = 19.09.2017 2. Date of TS = 25.10.2017 3. Date of Work Order = 09.12.2017 4.Dated of Released Funds 03.11.2017 18" i/d Sewer= 2129-Rft.24" i/d Sewer= 2078-Rft.27" i/d Sewer= 2857- Rft30" i/d Sewer= 45-Rft36" i/d Sewer= Sewerage Scheme, PCC Slab Soling in 490 2093 Chiniot 77.000 20.363 8.333 8.333 6.250 6.250 100% 26.613 35% 5307-RftScreening Chember= 1 Bhowana city Chiniot NoCollecting Tanks= 1 NoPumping Chember= 1 No.Pumping Machinery= 1 SetSullage Carrier= 200-Rft Boundary Wall= 1 NoFunds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat, 31.552235 Long, 72.650012 Bulk water Supply Project from River 491 2094 Rawalpindi 4,254.770 1,068.566 1.000 1.000 0.250 0.000 0% 1068.566 25% Work in Progress. Jhelum to Murree Date of A.A :01-01-2016.Date of T.S: 04-02- 2016.Date of Start: 15-04-2016.Date of Completion:30-06-2021.In last PDWP water Supply Scheme Fazaiya Housing meeting a committee of member water, 492 2095 Rawalpindi 373.073 338.322 11.584 11.584 5.792 5.792 100% 344.114 92% member infrastructure & Secretary HUD & Colony Turnol Tehsil & District Rawalpindi PHE was constituted to ascertain availability of sufficient water down stream of shahpur dam for this scheme whose report is submitted to P&D. Improvement of Water Supply System in 493 2096 Murree under PPP Rehabilitate, Operate Rawalpindi 24.500 14.500 3.333 3.333 0.000 0.000 #DIV/0! 14.500 59% Funds Released by FD on 31st July 2018. and Transfer (ROT Mode). A.A Date 21.10.2014. T.S Date 10.11.2014. Installation of water Supply scheme for 494 2097 Attock 469.913 400.994 10.000 10.000 7.500 7.500 100% 408.494 87% Date of Start of Scheme 22.01.2015. Date residents of attock of Completion of Scheme 30.06.2019.Work is in progress. Date of A.A 17.09.2015.Date of T.S Rehabilitation of Urban water Supply 495 2098 Chakwal 73.390 61.987 3.801 3.801 2.851 2.851 100% 64.838 88% 12.10.2015.Date of Start 11.02.2016. Date Scheme Kallar Kahar District Chakwal of completion 30.06.2019.Full funds utilized. Scheme is short funded. Date of A.A 17.09.2015.Date of T.S 07.10.2015.Date of Start 26.01.2016.Date of 496 2099 Est. of W.S. Scheme Talagang Chakwal 94.580 82.608 3.931 3.931 2.948 2.948 100% 85.556 90% completion 30.06.2019.Full funds utilized. Scheme is short funded.

Date of A.A 03.04.2014.Date of T.S 16.04.2014.Date of Start 30.05.2014.Date of completion 30.06.2021.Phase-I of the scheme has been completed.2 Cusec water from Khai Dam is being supplied to M.C water Supply Scheme Chakwal Based on Chakwal since 01-2018. The amended A.A 497 2100 Chakwal 1,018.160 341.465 33.333 33.333 2.488 0.969 39% 342.434 34% has been submitted in P&D for according Khai Dam approval. The tendering process of Phase-II will be started after getting amended approval.The expenditure in F.Y 2018-19 will only be possible after getting ammended approval. Funds proposed for reappropriation.

Installation of 02 no. of Tubewells in choa Date of A.A 21.11.2017.Date of T.S 498 2101 Chakwal 18.460 17.730 0.730 0.730 0.548 0.548 100% 18.278 99% 23.11.2017.Date of Start 12.01.2018.Date of Saiden Shah, District Chakwal completion 30.06.2018.Scheme completed.

"Scheme shall be completed by 30-06- Water Suplly Scheme based on Naroomi 2020.Balance funds required Rs. 7.919 499 2102 Jhelum 298.854 286.982 3.953 3.953 0.865 0.865 100% 287.847 96% million.A.A: 10-04-14.T.S: 16-4-14 .Date of Dhan Spring Phase II Commencement 24-10-2014.Work is in Progress. Scheme is partially operational Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Completion is Lying of water Supply Pipelines in D Block 30.06.2018, Date of Commencement, 500 2103 Old Satellite Town & Millat Abad Sargodha Sargodha 5.386 4.139 0.416 0.416 0.312 0.312 100% 4.451 83% 22.02.2017, Funds released on 30.07.2018, City Funds on-lined on 30.07.2018.R/Main / D- System 9395-Rft laid. P.C.C Slab 3128-Cft laid. RCC Sewer 12" i/d 531-Rft laid. Work in progress.

Date of A.A 28.02.2014, Date of T.S 30.04.2014, Date of Award 28.06.2014, Scheduled date of Completion is 30.06.2017, Date of Commencement, 28.06.2014, Funds released on 30.07.2018, Augmentation of water Supply Scheme Funds on-lined on 30.07.2018.21-No. tube wells completed out of provision 22-No. 21- 501 2104 Sargodha based on Canal water Supply Sargodha 268.210 197.713 16.667 16.667 12.500 11.312 90% 209.025 78% No. Pump Houses 90% completed out of Sargodha Phase I provision 22-No. 31-Sets of Pumping machinery arranged. R/Main / D-System 122534-Rft laid out of provision 122534-Rft. 5-No. GSTs 90% completed out of 05-No. 05-No. Staff Quarter 85% completed. Work in progress.

"Date of A.A 11.08.2015, Date of T.S 14.10.2015, Date of Award 16.01.2016, Scheduled date of Completion on 30.06.2017, Date of Commencement, 16.01.2016, Funds released on 30.07.2018, water Supply Scheme for Farooq Colony, 502 2105 Sargodha 98.971 65.957 6.667 6.667 5.000 5.000 100% 70.957 72% Funds on-lined on 30.07.2018.06-No. trial Imtiazabad Abad Sargodha City bore, tube well bore & pump house completed out of provision 06-No. 08-Sets of Pumping machinery arranged. R/Main / D-System 49652-Rft laid out of provision 112510-Rft. 02-No. GSTs 90% completed. Work in progress. Date of A.A 08.10.2009 Date of T.S 05.11.2009 Date of award 05.12.2009 Date Comprehensive Urban water Supply and of completion 30.06.2019 Scheme is 503 2106 Khushab 358.444 342.647 5.261 5.261 1.946 1.945 100% 344.592 96% functional and handed over to Municipal Sewerage Scheme Khushab City Committee Khushab. Latitude 32.305058333333335, Longitude 72.42525333333333 Date of A.A 08.10.2009 Date of T.S 05.11.2009 Date of award 11.08.2010 Date of completion 30.6.2019 All 10 No. Tubewell with pump house, pumping Comprehensiver Urban water Supply and 504 2107 Khushab 586.987 462.440 33.333 33.333 26.000 26.000 100% 488.440 83% machinary and GST 800000 Gln completed. Sewereage Scheme Jauharabad Work of laying of water supply pipe line is in Progress. All 3 Nos disposal works completed and functional. Work lying lataral sewer is in progress. Latitude 32.2959665, Longitude 72.4152732 Date of AA 27.08.2016 Date of TS 01.11.2016 Date of award 06.02.2017 Date Replacement of Old water Supply Pipeline of Completion 30.06.2020 Pump House 4/5 505 2108 Khushab 90.000 21.943 3.333 3.333 2.500 2.500 100% 24.443 27% P/Machinery 4/4 D/System 3"i/d to 6"i/d in Jauharabad. 101159/280407 Rft Work is in progress. Latitude 32.28155, Longitude 72.27786166666667

Date of AA 27.08.2016 Date of TS 01.11.2016 Date of award 06.02.2017 Date Replacement of Old water Supply Pipeline of Completion. 30.06.2020 T/Well 3/3 No. 506 2109 Khushab 130.000 44.202 16.667 16.667 12.500 12.490 100% 56.692 44% Pump House 2/3 No. P/Machinery 3/5 Set in Khushab City. D/System 3"i/d to 12"i/d 131522/257978 Rft Work is in progress. Latitude 32.29495166666666, Longitude 72.33265 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Revised Date of A.A. 16-01-2014 Date of Revised T.S.08-08-2014, Date of 2nd Revised A.A. 04-11-2015, Date of 2nd Revised T.S.10-12-2015, Date of Start of Work.03-12-2009, Remarks. Tube- Well=8/8, Pump House= 8/8, Pumping Machinery=9/9, Rising Feeding Main=12"i/d A.C= 921/940, 10" i/d A.C= 11959 /11960, 8" i/d PVC=26535 /26541, 6"i/d PVC= Comprehensive water Supply Sewerage 507 2110 Mianwali 494.444 462.274 6.667 6.667 1.005 1.005 100% 463.279 94% 30244 /30591,4"i/d PVC= 40592/40583, Scheme Mianwali 3"i/d PVC= 137262/137106, OHR = 3/3, Chlorinator = 8/8, T/Line 5/8, RCC Sewer=42"i/d= 480/480, 36"i/d =8385/8385, 30"i/d =2159/2159, 27"i/d= 8694/8694, 24"i/d=12415 /12415, 21"i/d= 14020/14020, 18"i/d= 23255/23357, 15"i/d= 28803 /29337, 12"i/d=137955 /137918, 9"i/d=31456/31456, Sullage Carrier=8500/8500, Oxidation Pond=2/2.Scheme almost completed.Latitude/Longitude:32.60'/71.52'

Date of A.A. 11-08-2015, Date of T.S. 15-08- 2015, Date of Start of Work 28-10-2015, Remarks. Rising Main=4"i/d PVC= Water Supply Scheme Iskandarabad, 1960/1960, D/System=4"i/d G.I= 0/50, 3"i/d 508 2111 Mianwali 4.498 1.509 0.996 0.996 0.024 0.024 100% 1.533 34% PVC=6000/6000, 4"i/d PVC= 400/400, 6"i/d District Mianwali. PVC 1900/1900, O.H.R=1/1 , Repair of P/Machinery, R/F Main old=1/1. Scheme completed in saving.Latitude/Longitude: 32.66' / 71.51'

1-Date of A.A 16.10.2014 2- Date of T.S 28.11.2014 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary - 298364 Person TRIAL BORES = 8/8-Job TUBE-WELLS (2.00-CUSEC) = 8/8-No. PUMP HOUSE (12' X 12') = 8/8-No. RISING MAIN / DISTRIBUTION SYSTEM 16” i/d AC "B" Class = 700/220-Rft 14” i/d PVC "B" Class = 351/370-Rft 12” i/d PVC "B" Class = 3,010/3568-Rft 10” i/d PVC "B" Comprehensive water Supply Scheme Toba Tek 509 2112 426.211 307.725 25.000 25.000 18.750 18.750 100% 326.475 77% Class = 9,395/8598-Rft 8” i/d PVC "B" Class Kamalia City Singh = 47,834/50634-Rft 6” i/d PVC "B" Class = 115,776-/132424Rft 4” i/d PVC "B" Class = 47,515/57557-Rft 3” i/d PVC "B" Class = 523,064/354020-Rft PUMPING MACHINERY = 8/8-SetOVER HEAD RESERVOIR (5-LAC GLNS) = 2/1-No 90%.HYPO CHLORINATOR = 8/7- No.SUIGAS, PTCL-LINE & ROAD CROSSING = 3/ -Job STAFF QUARTER = 1/1-No.ELECTRIC TRANSMISSION LINE = 8/8-Job.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

1-Date of A.A 01.01.2016 2- Date of T.S 30.03.2016 3-Anticipated date of completion 30.06.20219- No. of Beneficiary - 393651 Person Survey Investigation = 1-JobTrial Bore = 15/15-No.Test-Well = 1/1-No. Tube- Well = 15/15-No.Pump House = 16/0- No.R/Collector Main & D/Sys. 20" i/d 19500/ 0 -Rft18" i/d 1950/ 0- Rft16" i/d 1000/ 0- Urban water Supply Scheme Gojra Phase Toba Tek Rft12" i/d 16136/ 1004- Rft10" i/d 510 2113 532.942 125.000 33.333 183.333 25.000 24.900 100% 149.900 28% 14800/3174- Rft.8" i/d 29196/4957- Rft6" i/d II Singh 29768/5225- Rft.4" i/d 41405/2000- Rft. 3" i/d 180244/70000- Rft.Pumping Machinery = 30/14-Set.Ground Storage Tank = 6/4- No..Hypo Chlorinator =14/0-No..Over Head Reservoir = 5/3-No. Boundary Walls = 6000/409-RftSingle Room Staff Quarter = 6/0 No.Railway,Road,Suigas Cro. = 9/0- JobTransmission Line = 30/0-Job.Work in progress.

1-Date of A.A 23.10.2017 2- Date of T.S 17.11.2017. 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary Provision of Brick Pavements, Drains, Tuff - Person BRICK PAVEMENT = 798875/500047-Cft Resoling = Tiles, Water Supply, Play Grounds, Public Toba Tek 394153/224869-Sft Tuff Tiles = 511 2114 Parks, etc., in the Rural and Urban Areas of 245.000 120.000 16.667 16.667 12.500 12.489 100% 132.489 54% 15151/15153-Sft SURFACE DRAIN (TYPE- Singh Tehsil Kamalia and Tehsil Pir Mehal District I) = 82748/25906-Rft Sullage Carrier = 13833/5266-Rft Water Supply Pipe line 6" T.T. Singh i/d PVC= 5889/5889-Rft 5" i/d PVC= 16674/16674-Rft 4" i/d PVC= 9058/9058-Rft 3" i/d PVC= 22809/20304-Rft Oxidation Pond = 1/1-No. Work in progress. A.A Date =5.9.2014.T/Well installed=4 Nos.functional= 3 Nos .PVC Pipe Provision of water Supply and Drainage 512 2115 Gujrat 197.050 138.416 10.000 10.000 7.500 7.500 100% 145.916 74% Laid=171574 Rft.PCC= 165574 Cft. Scheme for Dinga City Distt Gujrat. S.C=7719 Rft. Soling=6069 sft, Tuff paver=19570 sft.1 No OHR 50000 Gln completed.Work in porgress. A.A Date =10.02.2009. 17 Nos Tube wells are functional and Handed over to M.C Construction of water Supply System Gujrat .3 Nos OHR's are functional. 763906 513 2116 Gujrat 742.379 487.503 33.333 33.333 4.000 4.000 100% 491.503 66% Rft pipes laid & functional.House Gujrat Connection= 2155 Nos. 2 Nos contracts out of 3 Nos are rescinded while 1 No has been reinstated. A.A Date =23.9.2014.T/Well installed= 3 Extension of Urban water Supply and Nos Functional= 2 Nos.PVC Pipe 514 2117 drainage scheme Azafi Abadies in Kharian Gujrat 122.416 79.911 5.000 5.000 3.750 3.750 100% 83.661 68% Laid=36194 Rft.PCC=104022 Cft. City S.C=5986 Rft.Tuff Paver= 74392 Sft Work in porgress. A.A Date =23.9.2014.T/Well installed= 2 Extension of Urban water Supply and 515 2118 Gujrat 159.603 122.667 8.432 8.432 11.324 11.324 100% 133.991 84% Nos.PVC Pipe Laid=80483 Rft.PCC= drainage scheme Sarai Alamgir City. 328408 Cft. S.C=550 Rft. Type-I= 30570 Rft.Work in porgress. water Supply & Sewerage Scheme in PP 516 2119 Gujrat 47.981 22.984 8.332 8.332 6.249 6.249 100% 29.233 61% Drain Type-I=23952 Rft. PCC. 1:2:4=91393 114 Cft.Work in progress. water Supply scheme Lalamusa and Rural A.A Date =23.02.2017.3 T/Well 517 2120 Gujrat 197.321 40.000 5.000 5.000 3.750 3.750 100% 43.750 22% installed.Pipe 8"=400 Rft, 4"=2000 Rft, Areas 3'=1000 rft. Work in porgress. Improvement / Extension of Urban water * A.A Date. 25.03.2016* T.S Date. Mandi 518 2121 Supply Sewerage & Drainage Scheme 345.995 114.976 16.667 16.667 14.670 14.670 100% 129.646 37% 29.03.2016* Start Date 24.04.2016* Bahauddin Completion date 23.04.2019.* Work in M.B.Din City progress. Improvement / Extension of Urban water * A.A Date. 07.01.2016* T.S Date. Mandi 519 2122 Supply Sewerage & Drainage Scheme 197.956 102.347 5.000 5.000 3.750 3.750 100% 106.097 54% 15.01.2016.* Start Date 01.03.2016* Bahauddin Completion date 28.02.2019.* Work in Malikwal City progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) * A.A Date. 07.09.2015* T.S Date. water Supply Scheme Chot Dhirian, Mandi 520 2123 75.000 64.263 3.333 3.333 1.000 1.000 100% 65.263 87% 10.09.2015* Start Date 17.12.2015.* M.B.Din Bahauddin Completion date 30.06.2019.* Work in progress A.A Date.30.9.2014 T.S Rehabilitation / Augmentation of Urban 521 2124 Narowal 185.411 98.401 13.333 13.333 3.733 3.729 100% 102.130 55% Date.10.11.2014*Start Date water Supply Scheme Narowal City 23.12.2014*Completion date 22.06.2016 .Work in progress. Urban water Supply Scheme Kahna Scheme in nearing completion, 2-Nos. Tube 522 2125 Lahore 199.405 126.661 6.667 6.667 5.000 4.975 100% 131.636 66% wells are put operational. Balance funds are Phase I and II required to complete the scheme. Provision of Open water Supply Scheme 523 2126 Sheikhupura 175.524 125.000 3.333 3.333 2.500 2.500 100% 127.500 73% Work in Progress Ferozwala 524 2127 Urban water Supply Scheme Muridkey Sheikhupura 450.000 219.000 16.667 16.667 12.500 12.500 100% 231.500 51% Work in Progress

525 2128 water Supply Scheme Chunian Amended Kasur 228.855 220.454 2.672 2.672 0.866 0.866 100% 221.320 97% Work in Progress Urban water Supply and Sewerage/ 526 2129 Kasur 475.472 468.331 2.380 2.380 0.296 0.296 100% 468.627 99% Work in Progress Drainage Scheme Phool Nagar water Supply, Drainage & PCC Scheme Scheme physically completed, Balance 527 2130 Kasur 176.173 172.172 1.334 1.334 1.001 1.001 100% 173.173 98% funds are requried to clear the contractor Outside Khudian District Kasur liabilities

Date of A.A (Revised) 22.01.2013, Date of T.S (Revised) 28.01.2013, Date of Prequalification 11.09.2012, Date of invitation of tenders 16.02.2013, Date of Receipt of tenders 16.02.2013, Date of work Extension / Improvement of water Supply order 21.02.2013, Date of completion as per 528 2131 Okara 864.000 701.498 26.667 26.667 20.000 13.334 67% 714.832 83% PC-I 13.05.2015, Anticipated date of Scheme Southern City, Okara. completion 30.06.2019, No. of Beneficiary - 69380 Person,Tubewell Boring = 26 / 26. NoRising Main = 53684 /54510 RftDirtribution System 3" to 24" i/d = 346341 / 370936 (PVC Pipe) RftDirtribution System 3" to 24" i/d = 10013

1. Date of AA 05.12.2016 2. Date of T.S - 3. Provision and Installation of six (06) Water Dated of Prequalification - 4. Date of invitation of tender 01.02.2017 5. Date of Purification Plants at Matotli Qaisarpur, Receipt of tenders 03.02.2017 6. Date of Shah Mosa Shah Pipulwala, Basti Mahram 529 2132 Multan 10.722 4.461 2.087 2.087 0.486 0.486 100% 4.947 46% work order 11.02.2017 7. Date of Rukn Hatti, Chak No.13- Faiz, Chak Completion as per PC-l 10.06.2017 8. Anticipated date of completion 30.06.2019 Sardarpur & Basti Nawan Shehar, Tehsil 9. Date of released of funds 03.08.2018. Shujabad, District Multan 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving.

1. Date of A.A: 17.09.2015 2. Date of T.S: 09.11.2015. 3. Date of Pre-Qualification: 18.01.2016 4. Date of Invitation of Tender: 16.02.2016 5. Date of Receipt of Tender: Rehabilitation of water Supply and 17.02-2016 6. Date of Work order: 530 2133 Khanewal 106.963 68.841 6.667 6.667 5.000 5.000 100% 73.841 69% 05.03.2016 7. Date of Completion as per Sewerage Schemes in Tulamba City. PC-I: 16-09-2017 8. Anticipated Date of completion: 30-06-2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11 No. of beneficiaries 53394Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

1. Date of A.A: 05.09.2014 2. Date of T.S: 28.10.2014 3. Date of Pre-Qualification: 18.12.2014 4. Date of Invitation of Tender: 19.01.2015 5. Date of Receipt of Tender: Urban water Supply & Sewerage Scheme 20.01.2015 6. Date of Work order: 18-02- 531 2134 Khanewal 191.232 147.091 14.714 14.714 11.036 11.036 100% 158.127 83% 2015 7. Date of Completion as per PC-I: 04- Khanewal City 09-2016 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 358569 Persons Work is in progress.

1. Date of A.A: 11.01.2016. 2. Date of T.S: 25.02.2016 3. Date of Pre-Qualification: 11.04.2015 4. Date of Invitation of Tender: 24.03.2016 5. Date of Receipt of Tender: Comprehensive water Supply & Sewerage 02.04.2016 6. Date of Work order. 532 2135 Vehari 99.982 78.470 6.970 6.970 5.228 5.228 100% 83.698 84% 14.04.2016 7. Date of Completion as per Scheme for Luddan City District Vehari. PC-I: 10.01.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary 20316 Persons Work is in progress.

1. Date of A.A: 11.04.2016. 2. Date of T.S: 29.04.2016. 3. Date of Pre-Qualification: 11.04.2015. 4. Date of Invitation of Tender: 18.05.2016. 5. Date of Receipt of Tender: 28.05.2016. 6. Date of Award: 15.06.2016 G- Comprehensive water Supply & Sewerage 533 2136 Vehari 332.198 308.130 8.000 8.000 6.000 6.000 100% 314.130 95% I. 17.06.2016 G-II 7. Date of Completion as Scheme for Vehari city. per PC-I: 14.06.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11. No. of Beneficiary= 140193 Persons Work is in progress. Comprehensive water Supply Scheme Dera Ghazi 534 2137 195.973 149.673 15.433 15.433 8.075 8.075 100% 157.748 80% • Date of A.A = 12.12.2014 Taunsa Sharif Khan Rehabilitaion of Urban water Supply Dera Ghazi 535 2138 257.064 243.790 4.397 4.397 3.298 1.154 35% 244.944 95% • Date of A.A =01.04.2015 Scheme Fort Minroe Khan Comprehensive Extension/Rehab. of Urban 536 2139 water Supply Scheme Rojhan and adjoining Rajanpur 49.569 25.000 8.190 8.190 6.143 6.143 100% 31.143 63% "• Date of A.A = 22.09.2016 abadies Enhancement of Supply of Water for 537 2140 Rajanpur 30.000 20.000 3.333 3.333 4.000 2.500 63% 22.500 75% "• Date of A.A = 22.09.2016 Rojhan City District Rajanpur Urban water Supply 538 2141 Muzaffargarh 419.689 398.484 4.110 4.110 3.083 2.054 67% 400.538 95% Work is in progress Scheme,Muzaffargarh(Ammended) (PSDP) Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA :29-11-2006.Date of TS :08-01- 2007.Date of RAA: 17-04-2014. Date of RTS. 17-04-2014.Date of receipt of tender.14-02-2007. Date of work order: 17- 03-2007.Date of completion as per agreement 16-03-2008.Funds Rs.1.200 million surrendered vide Chief Engineer(S),PHED Lahore No.72-78/B(4) dated 10.01.2019. Further funds Rs.0.500 million surrendered dated 19-02-2019 Three out of four portions are completed and handed over to TMA on 30-04-2014. Rehabilitation and Agumentation of water Balance Distribution system of Model Town- 539 2142 Bahawalpur 282.533 254.014 3.805 3.805 0.379 0.379 100% 254.393 90% B, karna basti and trust colony are under Supply Scheme, Bahawalpur test operation. G.I pipe 3” i/d 22680 Rft is pending as the people of intercity has refused. only house connections are to be installed after completion of successful testing/operation. Lattitude/Longitude. T/W No. 18 9.443500000000004,71.66939333333333 T/W No. 17, 29.44337833333333,71.67107333333334 T/W No. 16- 29.442918333333335,71.67257500000001 T/W No. 16,29.442918333333335,71.672575000000

Date of AA(DDWP)=24-10-2016. Date of TS=19-01-2017. Prequalification of the contractors=05-01-2017. Date of receipt of tender 27-02-2017 Date of award=03-03- 2017 Date of completion. 02-03-2018. Expected date of completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. .Work is in progress. Lattitude/Longitude. 29.727565655484796,72.48690473847091 540 2143 Urban water Supply Scheme for Hasilpur Bahawalpur 100.000 76.466 7.844 7.844 5.883 5.875 100% 82.341 82% T/W No. 02 29.72820817027241,72.48784761875868 T/W No. 03 29.728445671498775,72.4881225451827 T/W No. 04 29.728479282930493,72.48819404281676 T/W No. 05 29.72939576022327,72.48927555978298 T/W No. 06 29.7295211115852,72.4894735403359

Date of AA. 08.08.2016.Date of T.S. 27.09.2016.Date of receipt of tender water Supply Scheme of Chak Sarkari and 02.11.2016.Date of award. 30.11.2016Date Bahawalnaga 541 2144 Adjoining Abadies Tehsil Minchinabad 10.827 9.283 1.544 1.544 1.158 1.158 100% 10.441 96% of completion 29.07.2017.Anticipated date r of completion 31-12-2018Funds released by District Bahawalnagar FD on 12-11-2018 & 11.01.2019.Scheme completed and handed over to CBO on 31- 12-2018

Date of AA 09.03.2010.Date of T.S 13.03.2010.Date of award 14.05.2010.Date of completion 13.05.2011.Scheme Water Supply Scheme Doonga Boonga, Bahawalnaga remained unfunded during 2011-12.Funds 542 2145 11.168 0.915 3.418 3.418 0.891 0.891 100% 1.806 16% released on 20-07-2018 & 11.01.2019. District Bahawalnagar. r Scheme completed and functional & handed over ot On 30-06-2012 . Excess funds Rs.1.673 million surrendered dated 19.10.2018. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA 11.08.2009.Date of T.S 31.10.2009Date of award 13.01.2010.Date of completion 30.06.2014.Scheme remained unfunded during 2014.15.Date of Replacement & Up-Gradation of Urban Bahawalnaga 543 2146 214.155 211.310 0.947 0.947 0.441 0.441 100% 211.751 99% receipt of funds by F.D. 20.07.2018 & Water Supply Scheme Bahawalnagr r 11.01.2019. Scheme completed in saving & handed over to MC, Bahawalnagar on 30- 06-2015. Liabiity cleared. Excess funds Rs.0.269 million surrendered dated 19.10.2018

A.A issued on 12-05-2014. Date of T.S. 26- 05-2014. Date of prequalification=21-07- 2014. Date of receipt of tenders = 22-12- 2014. Date of work order= 03-01-2015. water Supply Scheme Sadiqabad, Tehsil Rahim Yar Date of completion as per agreement 02-01- 544 2147 692.527 454.150 67.779 97.779 50.834 48.290 95% 502.440 73% 2018. Anticipated date of completion 30-06- Sadiqabad, District R.Y. Khan. Khan 2020. No. of beneficiaries=405864 persons. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 28.38298666666667 / 69.98409333333333

"Date of A.A. 05.08.2017. Date of T.S. 09.08.2017. Date of receipt of Tender: Urban Water Supply Scheme Bismillah 07.09.2017. Date of award: 31.10.2017. Rahim Yar 545 2148 Town, Thalli Road, Near Madrassa Kulyat 30.000 9.949 6.667 6.667 5.000 4.966 99% 14.915 50% Date of completion: 31.1.2018. Anticipated Khan date of completion 30-06-2020. Date of ul Islam City Rahim Yaar Khan receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 28.500068333333335 / 70.304225

Date of AA 18.08.2015. Date of T.S 14.09.2015. Date of award 07.01.2016. Date of completion 30.06.2016. Scheme remained unfunded during 2016-17. Date of Const. of Water Supply Scheme Tranda Rahim Yar 546 2149 2.610 0.603 0.669 0.669 0.252 0.252 100% 0.855 33% receipt of funds by F.D. 20.07.2018 & Sway, R.Y.Khan. Khan 11.01.2019. Scheme completed in saving 2017-18. Excess funds Rs. 0.250 million surrendered on 23.10.2018. Latitude / longitude 28.48231333333333 / 70.40598666666666

Urban Sewerage / Drainage & PCC for A.A Date 09.01.2016. T.S Date 22.01.2016.Date of Start of Scheme 547 2150 Fateh Jang City, Tehsil Fateh Jhang, Attock 99.948 80.231 5.341 5.341 5.006 4.996 100% 85.227 85% 09.03.2016. Date of Completion of Scheme District attock. 30.06.2019.Work is in progress.

Urban Sewerage / drainage scheme for A.A Date 28.08.2014. T.S Date 01.09.2014. Date of Start of Scheme 26.01.2015. Date 548 2151 Hassan Abdal City, Hassan Abdal, District Attock 195.317 167.071 8.336 8.336 7.232 7.232 100% 174.303 89% of Completion of Scheme 30.06.2019.Work attock is in progress. Date of A.A 29.03.2016 (2nd Rev).Date of Providing / laying of Sewerage, T.S 24.01.2019 (3rd Rev).Date of Start Construction / Rehabilitation of storm water 549 2152 Chakwal 239.300 225.507 2.429 2.429 1.822 1.822 100% 227.329 95% 21.02.2014.Date of completion channel in Choa Saiden Shah District 30.06.2019.Scheme almost completed only contractor liabilities are to be clear for which Chakwal (Phase-I) (3rd Revised) additional funds are required. Date of A.A 22.01.2015 (3rd Rev).Date of T.S 06.02.2015.Date of Start 550 2153 Urban Sewerage Scheme, Talagang City. Chakwal 99.667 80.853 5.067 5.067 2.800 2.800 100% 83.653 84% 13.04.2015.Date of completion 30.06.2019.Work is in progress. Scheme shall be completed by 30-06- Construction of Sewerage and Drianage 2020.Balance funds required Rs. 8.377 551 2154 Jhelum 30.000 17.456 4.167 4.167 3.125 3.125 100% 20.581 69% million.Date of A.A 26-08-2016.Date of T.S Scheme Sohawa City 30-09-2016.Work awarded on 24-01- 2017.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Scheme shall be completed by 30-06- 2020.Balance funds required Rs.124.157 million.Date of A.A .14-09-2009.Date of Revise A.A 29-03-2016.Date of T.S 24-10- 2009.Date of Revis T.S 31-05-2016.Date of Commencement 17-08-2016.Date of Completion 15-08-2018.Scheme has been Urban Sewerage Scheme Jhelum with Revised and Administratively approved 552 2155 Jhelum 539.592 382.102 33.333 33.333 25.000 25.000 100% 407.102 75% vide. No.SO(PH-S)9-16/2015 (Jhelum).dt: Treatment Plant District Jhelum 29.03.2016. Work awarded in 2009 to 4 (Four) Groups. They have gone in litigation against recovery effected on the recommendations of CMIT. Work is held up by them since July 2014. Work to be done as per revised scope of work Revised Estimate allotted on 17-08-2016. Work on lift station & R.C.C pipe 12" i/d in progress.

Date of A.A 25.06.2009, Revised Date of A.A 31.01.2014, 2nd Revised Date of A.A 19.09.2016, Date of T.S 29.06.2009, Date of 2nd Revised T.S 30.09.2016, Date of Award 24.11.2009 & 04.12.2009, Scheduled date Comprehensive Urban Sewerage Scheme 553 2156 Sargodha 232.641 216.687 4.972 4.972 1.757 1.649 94% 218.336 94% of Completion on 12.2010, Revised date of Bhalwal Colonies Completion 30.06.2018, Date of Commencement, 24.11.2009 & 04.12.2009, Funds released on 30.07.2018, Funds on- lined on 30.07.2018.Scheme completed in saving, operational and handed over to Municipal Committee Bhalwal.

Date of A.A 27.08.2016, Date of Revised A.A 15.06.2017, Date of T.S 10.10.2016, Date of Award 16.11.2016, Scheduled date Rehabilitation of Sewerage Scheme Kot of Completion is 15.11.2017, Date of 554 2157 Sargodha 152.397 32.809 3.333 3.333 0.893 0.059 7% 32.868 22% Commencement, 16.11.2016, Funds Momin District Sargodha released on 30.07.2018, Funds on-lined on 30.07.2018.Drain Type-I, II & III 6877-Rft, constructed. The work is held up due to dispute of land of disposal station.

Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Completion is Construction of Sewerage PCC Soling 555 2158 Sargodha 5.177 4.283 0.298 0.298 0.224 0.224 100% 4.507 87% 30.06.2018, Date of Commencement, Resoling Bashir Colony Sargodha City 22.02.2017, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.RCC Sewer 12" to 24" i/d 1845-Rft laid, PCC Slab 2257- Cft laid. Work in progress

Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Scheduled date of Completion is Costruction of Sewerage / PCC / soling / 30.06.2018, Date of Commencement, 556 2159 Sullage Carrier Mulsim Town, Usman Park, Sargodha 5.927 4.376 0.500 0.500 0.375 0.375 100% 4.751 80% 22.02.2017, Funds released on 30.07.2018, Shiraz Park, Funds on-lined on 30.07.2018.Sullage Carrier 1653-Rft constructed Soling 1639- Cft laid. RCC Sewer 12" i/d 961-Rft laid Work in progress

Date of A.A 27.08.2016, Date of T.S 04.09.2016, Date of Award 22.02.2017, Construction of Sewerage PCC Soling in Scheduled date of Completion is 30.06.2018, Date of Commencement, 557 2160 Nawab Colony Aziz Colony and Ghani Park Sargodha 5.430 4.789 0.214 0.214 0.161 0.161 100% 4.950 91% 22.02.2017, Funds released on 30.07.2018, Sargodha City Funds on-lined on 30.07.2018.RCC Sewer 12" i/d 1504-Rft laid, PCC Slab 11550-Cft laid. Work in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 27.08.2016, Date of T.S 28.10.2016, Date of Award 14.02.2017, Scheduled date of Completion on 13.02.2018, Date of Commencement, Urban Drainage / PCC Flooring Scheme 14.02.2017, Funds released on 30.07.2018, 558 2161 Sargodha 93.181 35.964 5.000 5.000 3.750 3.750 100% 39.714 43% Funds on-lined on 30.07.2018.01-No. Miani District Sargodha Collecting tank completed, Sullage Carrier 23424-Rft & Drain 3129-Rft constructed. P.C.C 35971-Cft & Tuff Tile 22857-Sft laid. 03-No. Culvert completed. Work in progress.

Date of A.A 09.06.2015, Date of T.S 17.06.2015, Date of Award 31.07.2015, Urban Sewerage Scheme for (Islam Pura, Scheduled date of Completion is Zafar Colony, Qartaba Town, Jauhar 30.07.2017, Date of Commencement, 31.07.2015, Funds released on 30.07.2018, Colony, Sultan Town, Shirazi park, Mujhid Funds on-lined on 30.07.2018.02-No. 559 2162 Colony, Ali Town, Gilwala Including Sargodha 389.887 213.660 16.667 16.667 12.500 12.500 100% 226.160 58% screening chamber, collecting tank, Adjacent Colonies) & Abadies of (Yousaf pumping chamber 90% completed. 08-Sets Pumping Machinery out of 14-sets & 02- park, Aziz Colony, Bashir Colony, Nawab Sets Generator arranged at site. RCC Colony Sewer 1958-Rft laid. RCC Box Channel 9139-Rft constructed. Work in progress.Latitude/Longitude32.06°/72.42°

Date of A.A 25.08.2015, Date of T.S 14.10.2015, Date of Award 15.01.2016, Scheduled date of Completion on Sewerage and Drainage Scheme at Chak 30.06.2017, Date of Commencement, 560 2163 No.60 Shamali Khizarabad Ghosia Mehria Sargodha 60.000 49.976 3.334 3.334 2.501 2.501 100% 52.477 87% 15.01.2016, Funds released on 30.07.2018, Colony Funds on-lined on 30.07.2018.Drain 35186- Rft & Sullage carrier 8212-Rft constructed, Soling 4484-Cft & PCC Slab 121392-Cft laid. work in progress.

Date of A.A 02.01.2018, Date of T.S 13.02.2018, Date of Award 20.03.2018, Rural Drainage Scheme U.C Bhabra, U.C Scheduled date of Completion on Halal Pur, U.C Takhat Hazara and 561 2164 Sargodha 10.000 4.985 1.667 1.667 1.250 1.104 88% 6.089 61% 30.06.2019, Date of Commencement, Adjoining Abadies Tehsil Kot Momin District 20.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.Drain 192-Rft Sargodha constructed. P.C.C slab 6751-Cft & Soling 17594-Cft laid. Work in progress.

Date of A.A 02.01.2018, Date of T.S Rural Drainage Scheme U.C Mouzamabd, 13.02.2018, Date of Award 24.03.2018, U.C Jalla Makhdoom, U.C Mateela Scheduled date of Completion on 562 2165 Sargodha 10.000 5.000 1.667 1.667 1.251 1.061 85% 6.061 61% 30.06.2019, Date of Commencement, including Adjoining Abadies Tehsil Kot 24.03.2018, Funds released on 30.07.2018, Momin District Sargodha Funds on-lined on 30.07.2018.Soling 25462- Cft laid. Work in progress.

Date of A.A 02.01.2018, Date of T.S 13.02.2018, Date of Award 17.03.2018, Rural Drainage Scheme U.C Ghula Pur, Scheduled date of Completion on U.C Chak No.11/SB, U.C Garhi Kala and 563 2166 Sargodha 10.000 4.989 1.667 1.667 1.250 1.250 100% 6.239 62% 30.06.2019, Date of Commencement, Adjoining Abadies Tehsil Kot Momin District 17.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.Drain 1934- Sargodha Rft & Sullage Carrier 769-Rft constructed. Soling 17938-Cft laid. Work in progress. Date of A.A 02.01.2018, Date of T.S 13.02.2018, Date of Award 20.03.2018, Rural Drainage Scheme U.C Mela, U.C Scheduled date of Completion on Naseer Pur Kalan, U.C Mustafa Abad and 564 2167 Sargodha 10.000 4.957 1.667 1.667 1.250 1.159 93% 6.116 61% 30.06.2019, Date of Commencement, Adjoining Abadies Tehsil Kot Momin District 20.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.Drain 352-Rft Sargodha constructed. Soling 27162-Cft laid. Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 02.01.2018, Date of T.S Rural Drainage Scheme U.C Dodha, U.C 13.02.2018, Date of Award 20.03.2018, Gurna, U.C Jan Muhammad Wala, U.C Scheduled date of Completion on 30.06.2019, Date of Commencement, 565 2168 Laksian, U.C Miana Kot and Adjoining Sargodha 10.000 4.989 1.667 1.667 1.251 1.143 91% 6.132 61% 20.03.2018, Funds released on 30.07.2018, Abadies Tehsil Kot Momin District Funds on-lined on 30.07.2018.Drain 376-Rft Sargodha constructed. Soling 25284-Cft laid. Work in progress. Date of A.A 02.01.2018, Date of T.S 13.02.2018, Date of Award 20.03.2018, Rural Drainage Scheme U.C Bucha Kalan, Scheduled date of Completion on U.C Wan Miana, U.C Midh Ranjha and 566 2169 Sargodha 10.000 4.984 1.667 1.667 1.250 1.155 92% 6.139 61% 30.06.2019, Date of Commencement, Adjoining Abadies Tehsil Kot Momin District 20.03.2018, Funds released on 30.07.2018, Funds on-lined on 30.07.2018.Drain 1295- Sargodha Rft constructed. Soling 25849-Cft laid. Work in progress.

Date of A.A. 05-09-2014, Date of T.S.03-10- 2014, Date of Start of Work,08-11-2014, , Remarks. RCC Sewer=9" i/d=13629 /15205, 12"i/d= 3959/4960, 15"i/d= 8201/8695, 18"i/d= 3678/3675, 21"i/d=184/200, 24"i/d= 485/500, 27"i/d= 585/600, 30"i/d= 1106/1250, 33"i/d= Urban Sewerage / Drainag Scheme, Kamar 3232/3330, Screening Chamber=1/1, 567 2170 Mianwali 190.611 117.953 16.667 16.667 12.500 12.500 100% 130.453 68% Collecting Tank 25'dia= 2/2, Mushani, Mianwali. P/Machinery=4/4, Suction Delivery=1/1, Discharge Sump=1/1, Generator Room=1/1, Staff Quarter=1/1, Generator Set=1/1, Boundary Wall=1/1, S/Carrier= 3120/4675, Out fall Structure=0/1, S/Drain= 17845/51760, PCC Slab= 202010/294164, Electric T/Line=0/1. Work is in progress.Latitude/Longitude:32.94' / 71.49'

Provision of PCC Slab and Sewerage Date of A.A 27.08.2016 Date of T.S 30.09.2016 Date of Commencement 568 2171 Scheme in Municipal Committee Dullay Bhakkar 68.340 48.098 3.333 3.333 2.500 2.500 100% 50.598 74% 28.11.2016 Date of completion 30.06.2020 wala (Latitude 31.8427°/ Longitude 71.4359°)

Date of A.A 15.08.2017 Date of Amended A.A 16.12.2017 Date of T.S 07.02.2018 Date of commencement 24.03.2018 Date of Urban Sewerage/Drainage scheme, PCC 569 2172 Bhakkar 833.933 39.633 50.000 50.000 37.500 33.675 90% 73.308 9% completion 30.06.2021 Work at Disposal Slab & Brick Pavement in Bhakkar City Station is in progress. Payment for land acquisition has been made.Target will be acheived in the coming month.(Latitude 31.6062°/ Longitude 71.0854°)

Date of A.A 20-10-2016. Date of T.S.31-10- 2016. No. of Beneficiaries = 69568 Anticipated date of completion = Investigation of Source= RCC Sewer 9'' i/d 12040 /11963-Rft, 12'' 4335/2227-Rft,15'' i/d 3440/3186-Rft, 18'' i/d 2475/2013 Rft, 21'' i/d Provision of Sewerage in Tandlianwala City 140/210-Rft, 24'' i/d 1705/2670-Rft, 27'' i/d 570 2173 Faisalabad 100.000 69.988 9.366 9.366 7.025 5.960 85% 75.948 76% 2145/1983-Rft, 30'' i/d 1055/1053-Rft,(1). District Faisalabad Phase 1 Screening Chamber-1/1(2). Collecting Tank- 2/2 (3). Pumping Chamber-1/1 (4). Pumping Machinery-2/2 (5). Ductile pipe for Suction and Delivery-450/449 (6) Discharge Pump-1/1 (7). Sullage Carrier-2200/2235 Rft (8). Boundry Wall-200/-Rft (9). Staff Qurter-2/- Work is in progress.

Construction of Carpet Road (2200 feet) at 571 2174 Faisalabad 4.000 1.000 1.000 1.000 0.750 0.750 100% 1.750 44% Funds transfer to xen Highway Divison Chak No. 353/GB, District Faisalabad Faisalabad. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Boundary Wall of at Funds transfer to xen Building Divison 572 2175 Football Ground at Chak No.144/GB District Faisalabad 1.500 0.500 1.000 1.000 0.750 0.750 100% 1.250 83% Faisalabad. Faisalabad. Construction of Boundary Wall of Funds transfer to xen Building Divison 573 2176 Graveyard at Chak No. 630/GB Abadi Faisalabad 2.099 0.500 1.000 1.000 0.750 0.750 100% 1.250 60% Faisalabad. Rairoo, District Faisalabad. Date of A.A 15-11-2017.Date of T.S.13-12- Provision of Soling /Drainage at Chak 2017. No. of Baeneficiaries= 4654 Anticipated Date of Completion=12/12/2018 574 2177 No.568/GB Abadi Ahmad Khan District Faisalabad 2.000 0.485 1.515 1.515 1.136 1.131 100% 1.616 81% Surface Drain=35/1750 Rft Brick Faisalabad. Pavement= 8044/6671 Cft Work is in progress. Date of A.A 15-11-2017.Date of T.S.13-12- Provision of Soling /Drainage at Abadi 2017. No. of Baeneficiaries= 6266 575 2178 Faisalabad 3.000 0.997 1.000 1.000 0.000 0.000 #DIV/0! 0.997 33% Anticipated Date of Completion=12/12/2018 Bahadur Khan District Faisalabad. Surface Drain=0/4140 Rft Brick Pavement= 5166/6770 Cft Work is in progress. Date of A.A 15-11-2017.Date of T.S.13-12- 2017. No. of Baeneficiaries= Provision of Soling /Drainage at UC- 51 576 2179 Faisalabad 1.000 0.499 0.501 0.501 0.376 0.373 99% 0.872 87% 3566Anticipated Date of District Faisalabad. Completion=12/12/2018.Surface Drain=819/290 Rft.Sullage Carrier= 645/800 Rft. Work is in progress. Construction of TST Road 12 feet wide4 at 577 2180 Faisalabad 5.000 1.000 1.000 1.000 0.750 0.750 100% 1.750 35% Funds transferred to XEN High Way Abadi Hayyat Ullah, District Faisalabad. Division FSD.

Date of A.A 15-11-2017. Date of T.S.13-12- 2017. No. of Baeneficiaries= 5788 Provision Main Drainage at UC 35 Chak 578 2181 Faisalabad 5.000 0.998 1.000 1.000 0.750 0.746 99% 1.744 35% Anticipated Date of Completion=12/12/2018 No.119/GB, District Faisalabad. Surface Drain=913/0 Rft Sullage Carrier= 891/4625 Rft Brick Pavement= 1882/0 Cft Work is in progress. Repair of Road (4400 feet) 01-KM at Bhagi Funds transfer to xen Highway Divison 579 2182 Dhal to Purana Wasiran, District Faisalabad 3.000 0.600 1.000 1.000 0.750 0.750 100% 1.350 45% Faisalabad. Faisalabad. Construction of TST Road at Chak 580 2183 Faisalabad 6.000 1.000 1.000 1.000 0.750 0.750 100% 1.750 29% Funds transfer to xen Highway Divison No.119/GB, District Faisalabad. Faisalabad. Rehabilitation / Carpeting of Road (Length 4.00 KM) at Lahore Road Pull Sal to 581 2184 Faisalabad 21.715 5.000 1.000 1.000 0.750 0.750 100% 5.750 26% Funds transfer to xen Highway Divison Dulchian Road to Daand Gali, District Faisalabad. Faisalabad.

Date of A.A = 20.10.2016 • Date of TS = 24.11.2016 • No. of Beneficiaries = 24422- Persons • Anticipated date of completion = 30.06.2020 'R. C. C. Sewer 9" i/d 5308 /26072-Rft. 12" i/d 1000/ 4896-Rft. 15" i/d 672/2920-Rft. 18" i/d 611/1960-Rft. 21" i/d 79/246-Rft. 27" i/d 512./1726-Rft Screening Comprehensive Sewerage/ Drainage 582 2185 Jhang 100.000 30.000 6.667 6.667 5.000 5.000 100% 35.000 35% Chamber 1-No. Collecting Tank 1-No. / 2- scheme AP Sial (Urban) Nos. Pumping Chamber 1-No. Pumping Machinery 5-Sets. Diesel Generator and Generator Room 1-No. Out Fall Chamber 1- No. Sullage Carrier 1.5 x 2 2500-Rft. Staff Quarter 1-No. Boundary Wall 735-Rft. Surface Drain 5805-Rft. Sullage Carrier 1.5 x 1.5 450-Rft. Brick Pavement/PCC 78513- Cft. Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. of Beneficiaries = 19434- Construction of Sewerage, PCC Slab, Persons • Anticipated date of completion = 30.06.2020 R.C.C Sewer 352-Rft. Surface 583 2186 Drain & Soling at Ward NO. 1,2,3,4,5&6 Jhang 6.000 4.000 0.667 0.667 0.500 0.500 100% 4.500 75% Drain 3516-Rft. /3675-Rft. Brick Pavement and adjoining abadies urban area Jhang 1638-Cft. Sullage Carrier 144-Rft. PCC 12818-Sft / 52694-Sft. Road Culvert 1-No./ 1-No. Work in progress. Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. of Beneficiaries = 17707- Construction of Sewerage, PCC Slab, Persons • Anticipated date of completion = Drain & Soling at Ward NO. 13,14,15,16,17 584 2187 Jhang 6.000 3.900 0.667 0.667 0.500 0.500 100% 4.400 73% 30.06.2020 R.C.C Sewer 336-Rft. Surface & 18 and adjoining abadies urban area Drain 2861/3675-Rft. Brick Pavement 1638- Cft. Sullage Carrier 144-Rft. PCC Jhang 13572/52694-Sft. Road Culvert 1/1-No. Work in progress. Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. of Beneficiaries = 19400- Construction of Sewerage, PCC Slab, Persons • Anticipated date of completion = Drain & Soling at Ward NO. 19,20,21,22,23 585 2188 Jhang 6.000 4.000 0.667 0.667 0.500 0.500 100% 4.500 75% 30.06.2020 R.C.C Sewer 376-Rft. Surface & 24 and adjoining abadies urban area Drain 1273/2280-Rft. Brick Pavement 1274- Cft. Sullage Carrier 190-Rft. PCC Jhang 12528/59188-Sft. Road Culvert 1/1-No. Work in progress. Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. of Beneficiaries = 18583- Construction of Sewerage, PCC Slab, Persons • Anticipated date of completion = Drain & Soling at Ward NO. 25,26,27,28,29 586 2189 Jhang 6.000 3.998 0.667 0.667 0.500 0.500 100% 4.498 75% 30.06.2020 R.C.C Sewer 368/368-Rft. & 30 and adjoining abadies urban area Surface Drain 1810/2400-Rft. Brick Pavement 1238-Cft. Sullage Carrier 220- Jhang Rft. PCC 13474/59035-Sft. Road Culvert 1/1-No. Work in progress. Date of A.A 25.03.2017 Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. Construction of Sewerage, PCC Slab, of Beneficiaries = 17702-Persons • Drain & Soling at Ward NO. 31,32,33,34,35 Anticipated date of completion = 30.06.2020 587 2190 Jhang 6.000 3.993 0.667 0.667 0.500 0.500 100% 4.493 75% R.C.C Sewer 352-Rft. Surface Drain & 36 and adjoining abadies urban area 1825/2130-Rft. Brick Pavement 1456-Cft. Jhang Sullage Carrier 1460/155-Rft. PCC 14479/60636-Sft. Road Culvert 1/1-No. Work in progress. Date of A.A 25.03.2017 Date of T.S 28.03.2017 Date of Invitation of tenders Construction of Sewerage, PCC Slab, 18.04.2017. Date of Receipt of tender Drain & Soling at Ward NO. 20.04.2017 Date of work order 07.09.2017 588 2191 Jhang 7.000 5.000 0.667 0.667 0.500 0.500 100% 5.500 79% Date of Completion As per PC-I 19.10.2018 37,38,39,40,41,42, & 43 and adjoining Anticipated date of completion. 06.07.2018 abadies urban area Jhang No of Baneficiary 13260-Persons Agreement Amount 6.191-Million Work is in progress.

Date of A.A 25.03.2017 • Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. Construction of Sewerage, PCC Slab, of Beneficiaries = 19867-Persons • Drain & Soling at Ward NO. 589 2192 Jhang 7.000 4.963 0.667 0.667 0.500 0.500 100% 5.463 78% Anticipated date of completion = 30.06.2020 44,45,46,47,48,49, & 50 and adjoining R.C.C Sewer 296-Rft. Surface Drain 416/2700-Rft. Brick Pavement 1019-Cft. abadies urban area Jhang Sullage Carrier 238-Rft. PCC 21024/73040- Sft. Road Culvert 1-No. Work in progress.

• Date of A.A = 25.03.2017 • Date of TS = 28.03.2017 • No. of Beneficiaries = 17491- Construction of Sewerage, PCC Slab, Persons • Anticipated date of completion = 590 2193 Drain & Soling at Ward NO. 7,8,9,10,11&12 Jhang 6.000 3.906 0.667 0.667 0.500 0.500 100% 4.406 73% 30.06.2020R.C.C Sewer 320-Rft. Surface and adjoining abadies urban area Jhang Drain 3278/2100-Rft.Brick Pavement 1456- Cft.Sullage Carrier 324-Rft.PCC9368/59272- Sft.Road Culvert1/1-No.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

1-Date of A.A 12.11.2015 2- Date of T.S 25.02.2016 3- Anticipated date of completion 30.06.2021 4- No. of Beneficiary - 306625 Person.RCC SEWER 9” i/d = 45464/23024-Rft12"i/d = 9883/11102-Rft 15"i/d = 6563/2189-Rft 18"i/d = 3920/2321- Rft 21"i/d =2180/835-Rft 24"i/d = 2465/1219- Extension Rehabilitation of Urban Toba Tek 591 2194 488.756 239.700 33.333 33.333 25.000 24.900 100% 264.600 54% Rft 27"i/d = 1226/1266-Rft36"i/d = 194/ -Rft Sewerage Scheme Karnalia City Phase II Singh FORCE MAIN 28/9788"i/d = 11200-Rft FORCE MAIN 24"i/d = 7800/7635-Rft FORCE MAIN 20"i/d = 700/829-Rft SUMP WELL (SIZE 8'X6') = 7/4-No. REPAIR OF EXISTNG DISPOSAL WORKS = 1/0 - JobDIESEL GENERATOR WITH ROOM = 3/3-No. 90%PUMPING MACHINERY =6/6- Set. Work in progress.

11-Date of A.A 12.11.2015 2- Date of T.S 26.02.2016 3-Date of Prequalification - 07.03.2015 4-Date of invitation of tenders 18.03.2016 5- Date of Receipt of tenders 26.03.2016 6- Date of work odder - Extension/Rehabilitation of Urban Toba Tek 592 2195 400.000 224.900 16.667 16.667 12.500 12.500 100% 237.400 59% 18.04.2016 7- Date of completion as per PC- Sewerage Scheme Gojra Singh I 11.11.2018 8- Anticipated date of completion 11.11.20189- No. of Beneficiary - 393651 Person .10-Funds Released by F.D 03.08.2018 & 24.01.2019. 11-Re- appropriation of funds(+/-) Work in progress.

1-Date of A.A 16.10.2014 2- Date of T.S 03.12.2014 3-Date of Prequalification 08.12.2014 4-Date of invitation of tenders 08.12.2014 5- Date of Receipt of tenders 23.12.2014 6- Date of work order Urban Sewerage and Drainage Scheme Pir Toba Tek 593 2196 290.000 230.000 6.667 6.667 7.380 7.380 100% 237.380 82% 31.12.2014 7- Date of Completion as per Mehal Singh PC-I 15.10.2017.8- Anticipated date of completion 30.12.2018 .9- No. of Beneficiary - 139496 Person .10-Funds Released by F.D 03.08.2018 1& 24.01.2019 11-Re-appropriation of funds(+/-) (+) 15.03.2019 Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3- Anticipated date of Improvement of Street / Roads of Rajana Toba Tek completion 30.06.2020.4- No. of Beneficiary 594 2197 25.000 7.939 1.667 1.667 1.250 1.249 100% 9.188 37% - Person .Brick Pavemen =16722/10346- Town, District T.T Singh Singh Cft.Resoling= 117030/22142-Sft RCC Sewer (9" & 12") = 9818/4459-Rft Surface Drain 50/0-Cft Work in progress. 1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017 3- Anticipated date of Provision of Laying Tuff Tile, Sewerage and Toba Tek completion 30.06.2020Tuff Tile 595 2198 150.000 75.000 8.333 8.333 6.250 6.244 100% 81.244 54% 969180/502842-Sft Rcc Sewer (12" & 9") = Nullahs in Gojra, District T.T.Singh Singh 10484/7924-Rft Surface Drain = 4240/600- Rft Sullage Carrier = 600/0-Rft Work in progress. Construction of Sewerage Drainage Tuff 596 2199 Gujranwala 208.986 25.000 3.333 3.333 2.500 2.500 100% 27.500 13% Work in progress. tiles in Noshera Virkan Const of Sewerage Drainage PCC Scheme 597 2200 Gujranwala 120.754 84.455 5.306 5.306 3.980 3.980 100% 88.435 73% Work in progress. Sodhra Talwara Tehsil Wazirabad Provision of Sewerage & water Supply 598 2201 Scheme at Ghakhar & Ladhaywala, District Gujranwala 199.871 130.786 30.000 30.000 22.500 22.500 100% 153.286 77% Work in progress. Gujranwala (Revised) Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Sewerage / Drainage & PCC / RCC 599 2202 Scheme at Rahwali including Adjoining Gujranwala 392.400 100.600 20.000 20.000 28.526 28.526 100% 129.126 33% Work in progress. Abadies etc, Gujranwala. Provision of Drainage / PCC Scheme at 600 2203 Tehsil Noshera Virkan & UC Sharan Kalan, Gujranwala 77.000 16.846 3.333 3.333 2.500 2.500 100% 19.346 25% Work in progress. District Gujrnawala Provision of Sanitation / Drainage in City 601 2204 Hafizabad 167.781 109.933 10.000 10.000 6.300 6.300 100% 116.233 69% A.A 167.781 Date 04/04/2016 T.S. 167.77 Pindi Bhattian date 16-05-2016 work in progress.

The work was alloted to the contractor on dt: 26-11-2016 and contractor started the work at site .A.A 141.240 Date 06/09/2016 T.S. 142.374 date 30-09-2016 Drain 140910 Provision of Sanitation facilities in City Rft, Sullage Carrier /storm water 602 2205 Hafizabad 141.332 129.643 3.796 3.796 2.847 2.830 99% 132.473 94% 1.5x1.5=2225 Rft 2.0x2.0=1350 Rft Sukhike Mandi 2.0x2.5=2350 Rft 3.0x3.0=5878 Rft Tuff tile 60mm thick=17292 Sft 80mm thick =3200 Sft Brick Pavement/Soling = 37645 Cft, PCC 3" thick= 69726 Cft,4" thcik=56945 Cft,thick=82872 Cft, work in progress.

The work was alloted to the contractor on dt: 26-11-2016 and contractor started the work at site .A.A 141.240 Date 06/09/2016 T.S. 142.374 date 30-09-2016 Drain 140910 Rft, Sullage Carrier /storm water 603 2206 Urban Drainage Scheme Jalapur Bhattian Hafizabad 96.640 84.870 3.884 3.884 1.913 1.913 100% 86.783 90% 1.5x1.5=2225 Rft 2.0x2.0=1350 Rft 2.0x2.5=2350 Rft 3.0x3.0=5878 Rft Tuff tile 60mm thick=17292 Sft 80mm thick =3200 Sft Brick Pavement/Soling = 37645 Cft, PCC 3" thick= 69726 Cft,4" thcik=56945 Cft,thick=82872 Cft, work in progress.

Urban Sewerage / Drianage Scheme 604 2207 Eastern Side Ghari Awan & Allied Abadies Hafizabad 219.535 141.081 10.000 10.000 7.500 7.400 99% 148.481 68% work in progress. Hafizabad City R.A.A Date =3.05.2017R.T.S date=29.9.2017.1 Nos Screening Chamber, 1 Nos Collecting Tank 20' Dia 6set Construction of Two Pumps Station at Old Machinery, Force main pipe i/d Dia 10"=50 605 2208 Gujrat 108.440 66.578 13.928 13.928 10.446 10.446 100% 77.024 71% Rft,12"=100 Rft, 16"=3300 Rft, 18"=400 Rft G.T.Road Drain Gujrat. Drain type-I=2862 Rft Sullage Carrier= 2500 Rft RCC Sewer 15'=300 Rft,18"=346 Rft, 24"=1664 Rft PCC=7568 Cft .work in progress * A.A Date. 09.10.2014* T.S Date. Sewerage & water Supply Tank for Bhiki Mandi 606 2209 116.314 90.745 8.522 8.522 6.292 6.292 100% 97.037 83% 22.12.2014 * Start Date 16.02.2015* Sharif Bahauddin Completion date 30.06.2019.* Work in progress. * A.A Date. 06.01.2016* T.S Date. Sewerage / Drainage Scheme Malikwal Mandi 607 2210 237.200 62.105 8.333 8.333 4.850 4.850 100% 66.955 28% 15.01.2016* Start Date 11.03.2016* City, Distt.M.B.Din Bahauddin Completion date 10.03.2019.* Work in progress. Urban Sewerage/ Drainage PCC and Tuff * A.A Date. 06.09.2017* T.S Date. Mandi 608 2211 Tiles in City Phalia Tehsil Phalia District 270.500 27.095 10.000 10.000 7.370 7.370 100% 34.465 13% 24.10.2017* Start Date. 07.01.2018* Bahauddin Completion date 06.01.2021.Work in M.B.Din progress. Provision of Sewerage/PCC Streets/ * A.A Date. 25.08.2017* T.S Date. Mandi 609 2212 Drain/Tuff Tiles/Park and Janazgah District 75.000 55.000 6.667 6.667 5.000 5.000 100% 60.000 80% 06.09.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2020* Work in M.B.Din progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of PCC / Soling / Nullah / Street Scheme at Adalat Garah Bashamula, 610 2213 Muzaffarpura, Dhanay, phabarainawala, Sialkot 200.000 25.000 3.333 3.333 2.500 2.498 100% 27.498 14% Work in progress. Gujayanwala, Ravail pura, Stabgary, Burj / Butter etc.,Teshil & District Sialkot Provision of Sewerage Drainage and and 611 2214 Sialkot 100.000 30.000 3.333 23.333 22.500 2.500 11% 32.500 33% Work in progress. Tuff Tile at Daska City Construction of Street PCC / Tufff Tiles 612 2215 Drains & Nullah Fazal Pura & adjoining Sialkot 80.000 49.845 3.333 3.333 2.500 2.500 100% 52.345 65% Work in progress. Streets Sambrial City Construction of Street PCC / Tufff Tiles 613 2216 Drains & Nullah in Mandi Samrial and old Sialkot 80.000 44.945 3.333 3.333 2.500 2.475 99% 47.420 59% Work in progress. Sambrial Tehsil Sambrial Construction of Street PCC/Tuff Tiles 614 2217 Drains & Nullah in Mohallah Rasoolpur & Sialkot 80.000 44.992 3.333 3.333 2.500 2.500 100% 47.492 59% Work in progress. More Sambrial, Tehsil Sambrial Construction of Streets (Drains, PCC) 615 2218 Mohallah Sharif Pur, Habib Pura, Bashir Sialkot 90.000 49.918 3.333 3.333 3.700 3.700 100% 53.618 60% Work in progress. Pura, Nazir Abad Colony and others. Construction of Urban Drainage Scheme 616 2219 Sialkot 99.827 24.992 3.333 3.333 2.500 2.450 98% 27.442 27% Work in progress. Pasrur City, Tehsil Pasrur, District Sialkot. Construction of Nallah Around Road from Uggoki to Rai Pur Abba Baigowala Ganda 617 2220 Sialkot 199.826 69.726 5.000 5.000 3.750 3.750 100% 73.476 37% Work in progress. Nallah Railway Station etc. Tehsil Sambrial ,District Sialkot Removal of ponds / construction of Pull and 618 2221 establishment of Park at Moza Bahlor Sialkot 36.043 20.643 5.133 5.133 0.000 0.000 #DIV/0! 20.643 57% Scheme Completed Tehsil Pasrur, District Sialkot. Const of PCC / Tuff tiles of City Package *Date of A.A 9.4.2016*Date of T.S 619 2222 Narowal 69.569 49.569 6.667 6.667 4.500 4.469 99% 54.038 78% 19.4.2016*Start Date 09.6.2016*Completion Zafarwal City date 08.12.2017.Work in progress. Sewerage scheme for Talwandi Bhindran, A.A Date.3.5.2014 T.S Date.23.5.2014 620 2223 Narowal 109.876 105.797 1.360 1.360 1.020 0.999 98% 106.796 97% *Start Date 25.08.2014*Completion date Narowal. 30.06.2019.Work in progress. Provision of clean drinking water Sewerage Physically scheme is completed, balance 621 2224 system PCC and allied facilities in Chung Lahore 200.742 171.650 9.697 9.697 11.073 11.073 100% 182.723 91% funds are required to clear the contractor's Mohlanwal Manak liability. Provision of clean drinking water, Sewerage system, PCC and allied facilities Physically scheme is completed, balance 622 2225 Lahore 200.012 171.650 9.454 9.454 7.091 7.091 100% 178.741 89% funds are required to clear the contractor's in Babo Mehar Town, Lidhar, Bedian Road liability. and adjoining abadies Provision of clean drinking water, 623 2226 Sewerage system, PCC and allied facilities Lahore 509.268 219.523 26.667 26.667 20.000 20.000 100% 239.523 47% Work stopped due to awaiting funds. in Jallo More, Batapur PCC and drainage Scheme in UC 117 624 2227 Lahore 202.567 128.019 5.000 5.000 3.750 3.750 100% 131.769 65% Work stopped due to awaiting funds. Mansoora Lahore. Construction of PCC, Nallah at Maraka UC- 122, Shamke Bhattian, Chahram & mal, Physically scheme is completed, balance 625 2228 Lahore 24.200 7.634 5.522 5.522 0.000 0.000 0% 7.634 32% funds are required to clear the contractor's Manga Mandi Sunder, Kot Fateh liability. Muahammad Athul, District Lahore Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC Sewerage & Drainage 626 2229 System at UC-272 Raiwind Kalan & UC- Lahore 8.000 5.581 0.806 0.806 0.202 0.000 0% 5.581 70% scheme completed 273 Raiwind City, District Lahore Katcha Storm / Sullage Water Channel in 627 2230 Sheikhupura 199.813 139.520 5.000 5.000 3.750 3.750 100% 143.270 72% Work in Progress District Sheikhupura Provision of Sewerage Scheme Burjwala, 628 2231 Saleem Kot, Housing Colony, City Sheikhupura 174.527 165.000 3.176 3.176 2.382 2.382 100% 167.382 96% Work in Progress Sheikhupura Provision of Sewerage system in mohllah 629 2232 Sheikhupura 157.452 155.000 0.817 0.817 0.613 0.613 100% 155.613 99% Work in Progress ghareeb abad etc City Sheikhupura Provision of Open water Supply Scheme 630 2233 Sheikhupura 199.210 82.664 3.333 3.333 2.500 2.500 100% 85.164 43% Work in Progress Ferozwala. Provision Of Sewerage and PCC Scheme 631 2234 Pir Bahar Shah, Qazi Park Ramgarah & Sheikhupura 175.000 95.000 3.333 3.333 2.500 2.500 100% 97.500 56% Work in Progress Purana Shehar City Sheikhupura Urban Sewerage / Drainage Scheme 632 2235 Sheikhupura 183.441 89.027 3.333 3.333 2.500 2.500 100% 91.527 50% Work in Progress Sharqpur Seikhupura , Sharqpur Urban Sewerage Scheme Ferozwala New 633 2236 Sheikhupura 199.330 184.330 5.000 5.000 3.750 3.750 100% 188.080 94% Work in Progress Sewer Lines District Sheikhupura Urban Drainage & PCC Scheme Northn 634 2237 Sheikhupura 96.319 48.319 5.000 20.000 3.750 3.750 100% 52.069 54% Work in Progress Side of Railway Track City Sheikhupra Providing and laying of sewerage at 635 2238 Ghaloria Colony Farooq Nagar Shah Sheikhupura 97.683 47.683 5.000 5.000 3.750 3.750 100% 51.433 53% Work in Progress Colony District Sheikhupura Execution of Sanitation Sector Nankana 636 2239 Development scheme Shah Kot City District 50.000 23.600 3.333 3.333 2.800 2.800 100% 26.400 53% Funds fully utlized. work stopped due to non- Sahib availability of funds Nankana Sahib Const. of Storm Water Channel / Ext. & Nankana 637 2240 Improvement Urban Sewerage / Drainage 119.138 99.756 6.461 6.461 1.926 1.926 100% 101.682 85% Funds fully utlized. work stopped due to non- Sahib availability of funds Scheme Shahkot Phase-II Augmentation / Rehabilitation of Urban Nankana Work stopped due to non availability of 638 2241 264.253 130.000 5.000 5.000 3.750 3.750 100% 133.750 51% enough funds, Liability of contractor 1.700 Sewerage Scheme, Nankana Sahib Sahib million to be paid Construction of Sullage Carrier for Ultimate Funds fully utlized, work stopped due to non- 639 2242 Disposal of Phoolnagar City, Tehsil Pattoki, Kasur 337.971 18.614 20.000 20.000 18.941 18.941 100% 37.555 11% availability of funds District Kasur Provision of Sewerage & Drainage System Scheme physically completed, Balance 640 2243 Kasur 99.011 76.401 20.000 20.000 16.520 16.520 100% 92.921 94% funds are requried to clear the contractor in Chunian City, Kasur liabilities Urban Drainage Scheme Kasur city District 641 2244 Kasur 99.827 34.999 20.000 20.000 16.389 16.389 100% 51.388 51% Funds fully utlized, work stopped due to non- kasur availability of funds Urban Drainage, PCC & Brick Pavement Scheme physically completed, Balance 642 2245 Kasur 457.681 407.681 16.667 16.667 12.500 12.500 100% 420.181 92% funds are requried to clear the contractor scheme Kasur city District Kasur liabilities Urban PCC & Drainage Scheme Kot Radha 643 2246 Kasur 112.887 104.597 2.758 2.758 0.690 0.690 100% 105.287 93% Scheme Completed Kishan District Kasur. Urban Sewerage Drainage Scheme, Pattoki 644 2247 Kasur 680.017 657.032 6.294 6.294 0.546 0.546 100% 657.578 97% Work in Progress (Revised) Sewerage Drainage Scheme Kangan Pur 645 2248 Kasur 161.161 122.346 3.333 3.333 2.500 2.500 100% 124.846 77% Funds fully utlized, work stopped due to non- District Kasur. availability of funds Drainage P.C.C. & Brick pavement in 646 2249 Kasur 246.400 196.400 16.667 16.667 0.811 0.811 100% 197.211 80% Scheme Completed Mustafabad, Kasur. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA 03.03.2014, Date of TS 05.03.2014, Date of Pre- qualification.05.05.2014, Date of Receipt of Tenders,20.05.2014, Date of work Order. 30.05.2014, Date of completion As per PC- I. 30.06.2016, Anticipated date of completion.30.06.2019, Projected Complete Repair and renovation of Population 66950 Person,RCC Sewer 30" Sewerage system including PCC, Drains, =3208 / 3210 Rft27" i/d = 925 / 975 Rft24" 647 2250 Okara 184.048 172.023 4.006 4.006 3.005 1.926 64% 173.949 95% i/d = 1243 / 1244 Rft21" i/d = 820 / 823 water channels, soling, tuff tiles etc. in M.C. Rft18" i/d = 4742 / 5023 Rft15" i/d = 2373 / Mandi Ahmed Abad, District Okara. 3986 Rft12" i/d = 3687 / 5093 Rft9" i/d = 19452 Rft / 20830 RftPumping Machenry = 3 /3 SetStaff Qarter = 1 /1 JobStorm Water Channel = 9250 / 12500 SftTuff Tile 80mm = 123037 /218200 sftTuff Tile 60mm = 28509 / 48050 sftStreet Lights = 240 240 No.D.I Pipe 10" i/d = 389 /400 Rft Sullage Carreir = 585 / 1400 Rft

Date of AA 02.04.2014, Date of TS 14.04.2014, Date of Pre- qualification.10.04.2014, Date of Invitation of Tender 05.05.2014, Date of Receipt of Tenders 05.05.2014, Date of work Order 13.05.2014, Date of completion As per PC- I. 30.06.2016., Anticipated date of completion,30.06.2019,Rcc Sewer 48" i/d = Construction of Sewerage Scheme Renala 648 2251 Okara 327.480 296.423 10.352 10.352 7.764 5.198 67% 301.621 92% 33100Rft/33100 Rft42" i/d = 1900Rft/1900 Khurd City, District Okara Rft36" i/d = 2990 Rft/ 3034 Rft30" i/d = 635 Rft/ 635 Rft24" i/d = 1390 Rft/ 1390 Rft21" i/d = 540 Rft/ 540 Rft18" i/d = 2102 Rft / 3340 Rft15" i/d = 7307 Rft/ 7307 Rft12" i/d = 23750 Rft/ 23750 Rft9" i/d = 4184 Rft / 10334 RftSullage carrier (5x4) = 106 Rft /800 Rft Protection Wall = 200 Rft / 200 Rft Projected Population 119573 Person, Release of Funds 02.08.2017.

Date of AA 09.04.2010 ( Original), Date of Revised AA 31.10.2014 , Date of TS 18.08.2010 (Phase -I), Date of Revised TS 05.03.2015 , Date of Pre- qualification,20.03.2015, Date of Invitation of Tender 09.05.2015, Date of Receipt of Tenders 10.05.2015, Date of work Order 20.06.2011 & 03.09.2015, Date of completion As per Revised PC-I. 31.12.2017, Anticipated date of completion,30.06.2019,Rcc Sewer 48" i/d = Sewerage Scheme Depal Pur City District 649 2252 Okara 300.355 269.408 3.620 3.620 1.815 1.815 100% 271.223 90% 7519 Rft/ 7535 Rft42" i/d = 6056 Rft/1900 Okara Rft36" i/d = 1912 Rft/ 1927 Rft33" i/d = 1478 Rft/ 1519 Rft30" i/d = 1141 Rft/ 1257 Rft27" i/d = 4161 Rft/ 4169 Rft24" i/d = 4273 Rft/ 4853 Rft21" i/d = 2641 Rft/ 5015 Rft18" i/d = 4434 Rft / 5941 Rft15" i/d = 8637 Rft/ 9648 Rft12" i/d = 7600 Rft/ 12940 Rft9" i/d = 31923 Rft / 51553 RftSullage carrier (4x3) = 3283 Rft / 5820 Rft 3x3' = 2940 / 5155 Rft2x2" = 4000 / 4000 Rft External Electrification l = 2 / 2 JobComplaint Cell = 1 /1 NOStaff Quarter = 2 /2No Projected Population 229210 Person, Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA 16.05.2014, Date of TS 28.06.2014, Date of Pre-qualification 17.06.2014, Date of Invitation of Tender 30.06.2014, Date of Receipt of Tenders 30.06.2014, Date of work Order 17.09.2014, Date of completion As per PC-I.14.09.2016 , Anticipated date of completion,30.06.2019,Screening Chamber = 1 / 1No.collecting Tank 25' i/d = 1/1 No. Sewerage Scheme Shergarh Renala Khurd 650 2253 Okara 99.224 94.810 1.424 1.424 0.718 0.718 100% 95.528 96% completePumping chamber 25' i/d = 1/1No Okara completePumping Machenry 4 cusec = 2/2 set completeBoundry Wall = 600 / 600 RftSurface Drain 20940 / 16725 RftSullage Carrier 3x3' = 2178 / 2500 RftRcc Sewer 24" i/d = 1157 Rft/ 1925 Rft21" i/d = 1722 Rft/ 2136 Rft18" i/d = 1357 Rft / 1940 Rft15" i/d = 2480 Rft/ 2480 Rft12" i/d = 5400 Rft/ 5400 Rft9" i/d = 37868 Rft / 41775 RftExternal electrufication 1 /1 Job Projected Population 26497 Person.

Date of A.A 30-11-2017 Date of T.S 24-01- 2018 Date of Prequalification 13-09-2017 Date of invitation of tenders 22-02-2018 Date of Receipt of tenders 22-02-2018 Date Extension, Improvement Complete Repair, of work order 22-03-2018 Date of Renovation of Sewerage and and Water completion as per PC-I 22-03-2021 Supply System alongwith Provision of Anticipated date of completion 30-06-2021 651 2254 Okara 398.910 59.545 6.667 6.667 3.600 3.587 100% 63.132 16% No. of Beneficiary 47415 PersonScreening Strom Water Channels, Street Lights and Chamber = 0 / 1No.collecting Tank 20' i/d = Tuff Tiles in Hujrah Shah Muqeem, District 0/1 No. Pumping chamber 20' i/d = 0/1No Okara Pumping Machenry 2 cusec = 0/3 set completeBoundry Wall = 0 /4600 RftSullage Carrier = 0 / 200 RftRcc Sewer 21" i/d = 0 Rft/ 5655 Rft18" i/d = 5817 Rft / 6681 Rft15" i/d = 0 Rft/ 8349 Rft12" i/d = 5870 Rft/ 1356

• Date of AA =13.10.2016 ,• Date of TS =07.12.2016,• No. of Beneficiaries = 24113• Date of Pre-qualification= 08.02.2017,• Date of receipt of tender =18.02.2017 ,• Date of Work Order =22.03.2017 ,• Anticipated date of completion 30.06.2020,• Latitude=30.6340758• Longitude= 72.87130189" i/d RCC Sewer Pipe =4767/17796 Rft12" i/d RCC Sewer Pipe =1835/2117 Rft15" i/d RCC Sewer Pipe Rehabilitation/Augmentation of Sewerage =1206/2945 Rft18" i/d RCC Sewer Pipe 652 2255 Sahiwal 78.583 56.389 7.398 12.398 5.549 5.545 100% 61.934 79% =3730/3665 Rft21" i/d RCC Sewer Pipe System at Harrappa City =1467/1240 Rft24" i/d RCC Sewer Pipe =1191/1180 Rft27" i/d RCC Sewer Pipe =598/795 Rft30" i/d RCC Sewer Pipe =2031/1950 Rft33" i/d RCC Sewer Pipe =653/715 RftScreening Chamber 8' x 20'= 1/1 No.Collecting Tank 25' i/d=2/2 No.Pumping Chamber 20' i/d=1/1 No.Over Head Transmission Line=0/1 JobInter Connection=0.5/1 JobBoundary Wall=0/290 RftPumping Machinery 5 Cusec 50 BHP=0/2 SetWork in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 11.04.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Provision / Rehablitation / Improvement of 5.Date of Receipt of tenders 18.10.2017 water Supply in Urban U/Cs-12 & 13 and 653 2256 Multan 6.000 4.000 0.667 0.667 0.000 0.000 #DIV/0! 4.000 67% 6.Date of work order 06.11.2017 7.Date of Construction of Drain, Tuff Tiles, Sewerage Completion as per PC-l 05.05.2018 8. Anticipated date of completion 30.06.2019 in Urban U/Cs-23,24,26 & 41 Multan City 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4648 persons. Scheme completed.

1. Date of A.A. 15.01.2014 (21.04.2016) 2. Date of T.S. 22.01.2014 (05.08.2016) 3. Date of Prequalification 27.01.2014 4. Date of Invitation of Tender 12.02.2014 5. Date of Extension of Urban Sewerage Scheme Receipt of Tenders 24.02.2014 6. Date of 654 2257 Multan 196.830 158.627 12.289 12.289 9.217 8.300 90% 166.927 85% work order 10.03.2014/18.11.2016 7. Date Jalalpur Pirwala, District Multan (Revised) of Completion as per PC-l 14.01.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. No. of beneficiaries= 170275 persons. Work is in progress.

1. Date of AA 26.08.2014. 2. Date of T.S 15.10.2014. 3. Dated of Prequalification 11.08.2014. 4. Date of invitation of tender 23.10.2014. 5. Date of Receipt of tenders 24.10.2014. 6. Date of work order Sewerage Water Disposal from North 655 2258 Multan 145.222 118.112 8.989 8.989 0.000 0.000 #DIV/0! 118.112 81% 08.11.2014. 7. Date of Completion as per South Shujabad City Multan PC-l 25.08.2016 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018. 24.01.2019 10. No. of beneficiaries=111527 persons. Scheme completed in saving and handed over to TMA Shujabad.

1. Date of A.A: 12.02.2015 2. Date of T.S: 05.03.2015. 3. Date of Pre-Qualification: 11.08.2014. 4. Date of Invitation of Tender: 23.10.2014. 5. Date of Receipt of Tender: 24.10.2014 6. Date of Work order: Rehabilitation / extension of Sewerage / 656 2259 Khanewal 306.616 254.224 17.464 17.464 13.098 12.388 95% 266.612 87% 05.11.2014 7. Date of Completion as per drainage system of Mian Channu City PC-I: 25.08.2016 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 200428 Persons Work is in progress.

1. Date of A.A: 27.08.2016 2. Date of T.S: 25.10.2016 3. Date of Pre-Qualification: 26.10.2016 4. Date of Invitation of Tender: 03.12.2016 5. Date of Receipt of Tender: 05.12.2016 6. Date of Work order: Revamping of Jahanian Sewerage System, 657 2260 Khanewal 199.359 97.866 16.667 16.667 12.500 12.500 100% 110.366 55% 15.12.2016 7. Date of Completion as per Jahanian PC-I: 30.09.2019 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 65206Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 18.11.2017 2. Date of T.S: 08.12.2017 3. Date of Pre-Qualification: 06.09.2017 4. Date of Invitation of Tender: 30.01.2018 5. Date of Receipt of Tender: 31.01.2018 6. Date of Work order: Provision of Urban sewerage Scheme at 658 2261 Khanewal 99.676 49.676 10.000 10.000 7.500 7.500 100% 57.176 57% 10.02.2018 7. Date of Completion as per Kabirwala City, District Khanewal. PC-I: 31.03.2019 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 56299 Persons Work is in progress.

1. Date of A.A: 29.12.2014. 2. Date of T.S: 12.03.2015 3. Date of Pre-Qualification: 13.03.2015 4. Date of Invitation of Tender: 10.04.2015 5. Date of receipt of Tender: Provision of drainage / Sewerage, soling & 11.04.2015 6. Date of Award: 20.04.2015 7. 659 2262 water Supply in Municipal Area of Burewala Vehari 358.775 233.686 16.667 16.667 12.500 12.500 100% 246.186 69% Date of Completion as per PI: 28.12.2016 8. City. Anticipated Date of Complion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiaries 226016 Persons. Work is in progress.

Comprehensive Sewerage / Drainage Dera Ghazi 660 2263 Scheme Taunsa Sharif including Tuff Tilling 485.406 214.529 33.333 33.333 27.200 9.000 33% 223.529 46% "• Date of A.A = 12.02.2015 Khan of Streets -InActive Construction of Nali Soling in UC Basti Jaam, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Dera Ghazi 661 2264 Ara Jafar, Construction Of Nali 21.500 10.747 3.583 3.583 2.687 2.633 98% 13.380 62% "• Date of A.A = 04.10.2017 Khan Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Kotla Ahmad Khan, District D.G. Khan. Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas Muza Chak Masso U/C Nawan Shumali, Construction Dera Ghazi 662 2265 6.000 2.973 1.000 1.000 0.750 0.743 99% 3.716 62% "• Date of A.A = 04.10.2017 Of Nali Soling,Tough Tiles Khan Drainage,Culverts And Qulabas U/C Jakhar Imam Shah, District D.G. Khan. Construction Of Nali Soling,Tough Tiles Dera Ghazi 663 2266 Drainage,Culverts And Qulabas U/C Haji 9.000 4.442 1.500 1.500 1.125 1.114 99% 5.556 62% "• Date of A.A = 04.10.2017 Khan Kamand, District D.G. Khan. 10930 Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Khan Pur Janobi, Construction Of Nali Dera Ghazi 664 2267 Soling,Tough Tiles Drainage,Culverts And 33.700 16.843 5.617 5.617 4.213 4.129 98% 20.972 62% "• Date of A.A = 04.10.2017 Khan Qulabas U/C Nawan Shumali, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C N Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Aali Wala, Construction Of Nali Soling,Tough Dera Ghazi 665 2268 Tiles Drainage,Culverts And Qulabas U/C 52.000 25.955 8.667 8.667 6.500 6.435 99% 32.390 62% "• Date of A.A = 04.10.2017 Khan Jalbani, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Basti Malana, Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Tibbi Kharak, Construction Of Nali Soling,Tough Dera Ghazi 666 2269 Tiles Drainage,Culverts And Qulabas U/C 130.000 64.993 6.000 6.000 4.500 4.410 98% 69.403 53% "• Date of A.A = 04.10.2017 Khan Chabri Zareen, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Kot, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Darahma, Construction Of Nali Dera Ghazi 667 2270 Soling,Tough Tiles Drainage,Culverts And 29.000 14.485 4.833 4.833 3.625 3.589 99% 18.074 62% "• Date of A.A = 04.10.2017 Khan Qulabas U/C Samina, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Chorahatta, Dist Construction of Nali Soling V/C Aliwala C/O Fateh Muhammad Bazgir, Construction of Dera Ghazi 668 2271 Nali Soling, Tuff Tiles, Drainage, Culverts 10.000 4.978 1.667 1.667 1.250 1.238 99% 6.216 62% "• Date of A.A = 04.10.2017 Khan and Qulabas U/C Mana Ahmadani, District D.G. Khan. Construction of Nali Soling, Tuff Tiles, Dera Ghazi 669 2272 Drainage, Culverts and Qulabas U/C Notak 11.000 5.474 1.833 1.833 1.375 1.348 98% 6.822 62% "• Date of A.A = 04.10.2017 Khan Mahmeed, District D.G. Khan. Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Darkhast Jamal Khan Darmiani, Dera Ghazi 670 2273 Construction Of Nali Soling,Tough Tiles 10.000 5.000 1.667 1.667 1.250 1.238 99% 6.238 62% "• Date of A.A = 04.10.2017 Khan Drainage,Culverts And Qulabas U/C Darkhast Jamal Khan Janobi, Construction Of Nali Soling,Tough Tiles Drainage,

Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Jhoke Utra, Construction Of Nali Soling,Tough Dera Ghazi 671 2274 Tiles Drainage,Culverts And Qulabas U/C 47.500 23.731 3.333 3.333 2.500 2.450 98% 26.181 55% "• Date of A.A = 04.10.2017 Khan Hazara, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Haider Quresh Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C Khan Pur Janobi, Construction Of Nali Dera Ghazi 672 2275 Soling,Tough Tiles Drainage,Culverts And 40.000 20.000 1.000 1.000 3.334 2.809 84% 22.809 57% "• Date of A.A = 04.10.2017 Khan Qulabas U/C Nawan Shumali, Construction Of Nali Soling,Tough Tiles Drainage,Culverts And Qulabas U/C N Construction of Urban Sewerage Drainage 673 2276 Earth filling brick pavement and Tuff Tile Rajanpur 61.369 55.200 1.000 1.000 0.750 0.750 100% 55.950 91% " Date of A.A = 24.4.2015 scheme for Rojhan Urban drinage/Sewerage/tuff tile scheme in Jampur City (replacement of outlived sewer 674 2277 Rajanpur 365.753 195.169 33.333 33.333 25.000 25.000 100% 220.169 60% "• Date of A.A = 23.12.2014 and new sewer system in Faisal Colony, Shah Jamal Colony and Tattar Wala) Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Rural Drainage Sewerage PCC and Tuff 675 2278 Tile flooring Rajan Pur City and Adjoining Rajanpur 40.500 25.600 4.967 4.967 3.725 3.725 100% 29.325 72% "• Date of A.A = 24.4.2015 Abadies UC Rajan Pur Construction of drain, brick pavement 676 2279 sullage carrier culverts & tuff tile flooring Rajanpur 50.000 25.000 8.333 8.333 6.250 6.250 100% 31.250 63% "• Date of A.A = 17.12.2014 scheme of fazilpur tehsil & district rajanpur Open Drainage & Tuff Tile Scheme in 677 2280 Muzaffargarh 49.850 32.404 5.815 5.815 4.361 4.361 100% 36.765 74% Work is in progress Remaining Portion of Kot Addu City Sewerage System for Recep Tayyip Part-I completed. Application for Evaluation 678 2281 Erdogan Hospital Muzaffargarh Expansion Muzaffargarh 191.449 78.700 1.000 1.000 0.750 0.000 0% 78.700 41% are submitted to consultant. Project Comprehensive Sewerage Scheme 679 2282 Layyah 199.995 105.377 16.667 16.667 12.500 12.473 100% 117.850 59% • Date of AA = 22-09-2016 alongwith Tuff Tiles in City Chowk Azam Urban Sewerage / Drainage Scheme 680 2283 Layyah 147.290 138.871 1.000 1.000 0.000 0.500 #DIV/0! 139.371 95% "• Date of AA(Original) = 10-09-2007 Chowk Azam 681 2284 Urban Sewerage Scheme for Kot Sultan Layyah 191.440 152.935 6.667 6.667 5.000 5.000 100% 157.935 82% • Date of AA = 24-02-2009

Date of AA :26-02-2014 Date of TS :05-03- 2014. Date of RAA=12-05-2016 Date of pre- qualification: 07-03-2014. Date of receipt of tenders. 02-04-2014 Date of work order :29- Sewer Line from Bahawalpur Victoria 04-2014. Date of completion as per 682 2285 Hospital to Disposal Lal Bagh Tehsil & Bahawalpur 172.906 139.513 11.131 11.131 8.348 8.114 97% 147.627 85% agreement:28.04.2016. Anticipated date of District Bahawalpur. completion=30-06-2020 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Restoration work is in progress. Lattitude/Longitude. 29.390331666666665,71.67951666666666

Date of A.A 04.05.2016 Date of T.S 26-05- 2016 Date Awarded 11.06.2016. Date of completion 11-09-2017 Funds released by FD 20.07.2018 & 11.01.2019.Work Sewerage / Tuff Tile in Choti Karana Tehsil completed & functional during 2017-2018. 683 2286 Bahawalpur 1.288 0.883 0.135 0.135 0.000 0.000 #DIV/0! 0.883 69% Liability of the contractor cleared.Excess & District Bahawalpur. funds Rs. 0.068 million surrendered dated 19.10.2018. Further funds Rs.0.033 million surrendered dated 19-02-2019. Lattitude/Longitude. 29.411988333333337,71.68345666666667

Date of AA 19.03.2015 Date of T.S 18.04.2015. Date of award 18.05.2015. Date of completion 17.09.2015. Expected date of completion 30-06-2017. Funds released by FD 20.07.2018 & Construction of Tuff Tile in Main Street 11.01.2019Scheme remained unfunded during 2016-2017. Remaining work has 684 2287 Gillani City Uch Sharif Tehsil Ahmed Pur Bahawalpur 3.089 0.801 0.763 0.763 0.000 0.000 #DIV/0! 0.801 26% been executed/completed by Local East, Bahawalpur. Government due to which funds not required. Excess funds Rs. 0.0382 million surrendered dated 19.10.2018.Further funds Rs.0.119 million surrendered dated 19-02-2019. Lattitude/Longitude. 29.2365403,71.0627274 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA: 11.01.2014Date of TS: 17.01.2014Date of RTS 23-11-2016Date of pre-qualification: 28.02.2014.Date of receipt of tenders = 19-03-2014Date of work Laying of Tuff Paver and provision of water Bahawalnaga order=11.04.2014.Date of completion as 685 2288 70.000 49.812 4.922 4.922 3.692 3.692 100% 53.504 76% per agreement=10.04.16.Anticipated date of Supply Pipelines in City Bahawalnagar. r completion=30-06-2020Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019.Original scope of work is completed. Revised scope of work is in progress.

Date of AA = 29-09-2016(DDSC).Date of T.S. 08.02.2017Funds released by FD= 04- 07-2017 Prequalification of the contractor Provision of Sewerage Scheme Zone A Bahawalnaga 686 2289 399.587 138.058 50.000 50.000 50.000 50.000 100% 188.058 47% 26-01-2017 Tender received on 22.03.2017 with Tuff Paver at Bahawalnagar r Date of work awarded.03-05-2017. Date of completion 02-05-2019. Date of receipt of funds by F.D. 20.07.2018 and 19-12-2018. Work is in Progress

Date of A.A 25.05.2014 . Date of T.S. 21-07- 2014.Date of Prequalification. 21-07- 2014Date of receipt of tenders =12-08- 2014Date of work order= 16-09-2014.Date of completion as per agreement= 15.09.2017.Anticipated date of completion = Sewerage Scheme Chishtian City Uplift Bahawalnaga 687 2290 916.110 672.765 33.333 33.333 25.000 25.000 100% 697.765 76% 30.06.2021. .No. of beneficiaries=342309 Package Chishtian r persons. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Scheme partially completed and handed over to MC Chishtian on 28-02-2018. The balance work of sewer 12" dia is in progress. Funds Rs 210 Million are required to complete the scheme

Date of A.A(PDWP) 19-01-2017. Date of T.S 16.02.2017. Prequalification of the contractor 15.03.2017. Date of receipt of tender:- 03.04.2017. Date of award Rahim Yar 688 2291 Mega Sewerage Scheme Liaqatpur City 500.000 49.996 66.667 66.667 50.000 49.355 99% 99.351 20% 24.07.2017 Date of completion. 23-07- Khan 2019.Anticipated date of completion 30-06- 2020.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 28.93957833333333 / 70.95657833333333

Date of AA. 23-09-2014. Date of TS.. 27-11- 2014. Date of prequalification. 08-12-2014. Date of receipt of tenders = 31-12-2014. Date of work order=10-2-15. Date of Request for provision of Sewerage Scheme Rahim Yar 689 2292 199.970 160.769 13.063 13.063 9.797 9.295 95% 170.064 85% completion as per agreement 09-8-16. of Feroza Town, Tehsil Liaqat Pur Khan Anticipated date of completion 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 28.766561666666668 / 70.80993166666667 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA. 09-10-2014. Date of TS. 21-11- 2014. Rev: TS 28.10.2016. Date of prequalification. 08-12-2014. Date of receipt of tenders = 31-12-2014. Date of work order= 10-01-2015. Date of completion as per agreement= 09-01-2016.Anticipated Rahim Yar date of completion=30-06-2018. Scheme 690 2293 Rehabilitation of Sewerage City Sadiqabad 70.326 52.373 5.984 5.984 0.192 0.192 100% 52.565 75% completd in saving. Date of receipt of funds Khan by F.D. 20.07.2018. Funds not required during 2018-2019. Excess funds amounting to Rs.1.496 million released by F.D on 11.01.2019 is surrender by Chief Engineer(S), PHED Lahore on 13-03-2019. Latitude / longitude 28.300515000000004 / 70.10846

Date of AA 19-12-2017. Date of T.S 15-02- 2018. Tenders received on 13-03-2018. Date of award 18.04.2018. Date of completion 12.04.2019. Anticipated date of Laying of Soling, Water Supply, Sewerage Rahim Yar 691 2294 40.000 19.958 6.667 6.667 5.800 5.502 95% 25.460 64% completion 17-04-2020. Date of receipt of Line and Tuff Tiles in City Sadiq Abad. Khan funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.0.800 million provided through re- appropriation. Work is in progress. Latitude / longitude 28.287063333333336 / 70.12249833333334

"Date of AA 19-12-2017.Date of T.S 15-02- 2018. Date of receipt of tenders 13-03-2018 . Date of work awarded 30-03-2018. Date of Laying of Soling, Water Supply, Sewerage Rahim Yar completion 29-06-2018. Anticipated date of 692 2295 Line and Tuff Tiles in Rural Area Tehsil 35.000 17.468 5.833 5.833 4.375 4.308 98% 21.776 62% completion 30-06-2020. Date of receipt of Khan Sadiq Abad. funds by F.D. 20.07.2018 & 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.28630333333333 / 70.18586166666667

Date of AA 19-12-2017. Date of T.S 16-02- 2018. Date of receipt of tenders 13-03-2018 . Date of work awarded 07-04-2018. Date of Laying of Soling, Water Supply, Sewerage Rahim Yar completion 06-06-2018. Anticipated date of 693 2296 Line and Tuff Tiles in Chak No. 148/P 8.000 3.984 1.333 1.333 1.000 0.989 99% 4.973 62% completion 30-06-2020. Date of receipt of Khan Tehsil Sadiq Abad. funds by F.D. 20.07.2018 & 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.279065 70.21711499999999

Date of AA 19-12-2017. Date of T.S 16-02- 2018. Tenders received on 13-03-2018. Dated of award 11.05.2018. Date of Construction of Sewerage Line and Soling Rahim Yar completion 26.06.2018. Anticipated date of 694 2297 5.000 2.471 0.833 0.833 0.625 0.625 100% 3.096 62% completion 30-06-2020. Date of receipt of Wahid Bux Mahar Tehsil Sadiq Abad. Khan funds by F.D. 20.07.2018 & 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.289573333333337 / 70.05784999999999 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA =05.03.2014. Date of TS=05.03.2014. Date of work awarded 14.04.2014.. Date of completion 13.04.2016.. Scheme completed. Liability of the contractor Rs. 20.00 Million is yet to be cleared. . RCC Pipe 9" i/d = =8996 Rft/100%. RCC Pipe 12" i/d = =23039 Rehabilitation / Augmentation of Sewerage Rahim Yar Rft/100%. RCC Pipe 15" i/d = =20402 695 2298 scheme Khan Pur city Phase-II District 452.844 432.844 2.000 2.000 0.700 0.700 100% 433.544 96% Rft/100%. RCC Pipe 18" i/d = =5936 Khan Rahim Yar Khan Rft/5936 Rft. RCC Pipe 21" i/d = =1775 Rft/1744 Rft. RCC Pipe 24" i/d = =3240 Rft/3470 Rft. RCC Pipe 27" i/d = =3860 Rft/3692 Rft. RCC Pipe 30" i/d = =2930 Rft/2867 Rft. RCC Pipe 36" i/d = =7090 Rft/7090 Rft. RCC Pipe 42" i/d = =2764 Rft/2778 Rft. RCC Pipe 54" i/d = =4710 Rft/4800 Rft.

1. Date of AA =02.05.2016 2. Date of TS = 19.08.2016 . 3. Date of work order= 22.10.2016. 4. Date of Completion as per PC-I = 3 Ye.5. Anticipated Date of Comp = 30.06.2019 6. No. of Beneficiaries= 116058.9"i/d Sewer= 251672-Rft12" i/d Sewer= 96403-Rft15" i/d Sewer= 10210- Rft18" i/d Sewer= 6494-Rft21" i/d Sewer= 7076-Rft24" i/d Sewer= 4772-Rft 27" i/d Comprehensive Sewerage scheme Chenab 696 2299 Chiniot 719.952 164.999 66.667 66.667 49.500 49.080 99% 214.079 30% Sewer= 1645-Rft30" i/d Sewer= 1120-Rft Nagar Chiniot 33" i/d Sewer= 1145-Rft36" i/d Sewer= 2794-Rft 42" i/d Sewer= 2100-Rft48" i/d Sewer= 4450-Rft Screening Chember= 2 NoCollecting Tanks= 4 No Pump House= 2 NoPumping Machinery= 7 Sets Staff Quarter= 2 NoDeisel Genrator= 1 Job Genrator Room= 1 NoFunds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat,31.7583760 Long, 72.9165266

1. Date of AA=15.09.2014. 2. Date of TS =28.11.2014 3. Date of Pre-qualification =06.12.2014 4. Date of inviting Tenders=20.12.2014 5. Date receipt of Tenders= 20.12.2014 6. Date of work order= 01.01.2015 7.Date of Completion as per PC-I =2 Year 8. No. of Beneficiaries 94630 12" i/d Sewer= 42174-Rft15" i/d Sewer= 989-Rft18" i/d Sewer= 3843-Rft21" New urban Sewerage scheme for Mohallah i/d Sewer= 1264-Rft24" i/d Sewer= 3963- Rft33" i/d Sewer= 2164-Rft36" i/d Sewer= 697 2300 Fateh Abad Rashida Osmanaabad paris Chiniot 199.694 103.971 16.667 16.667 16.500 16.340 99% 120.311 60% 868-Rft42" i/d Sewer= 1832-RftScreening road Moazam Shah Shahbaal Chember= 1 NoCollecting Tanks= 2 NoPumping Chember= 1 NoPumping Machinery= 4 SetsSullage Carrier = 200- RftPCC= 55476-CftSullage Carrier= 5100- Rft Staff Quarter= 3 NoDiesel Genrator 200 KVA + Genrator Room= 1 SetBoundary Wall= 1 NoFunds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat, 31.7339017 Long, 72.96676

1. Date of AA = 02.08.2017 .2. Date of TS = 26.08.2017 3.Date of Award of work Soling / Drain, Pulian Hajiabad, Muradwala, 31.10.2017 Surface Drain / Type - I= 1422- 698 2301 Sabowala,Colony, Sabowala, District Chiniot 4.998 0.800 1.000 1.000 0.750 0.750 100% 1.550 31% RftBrick Pavement / PCC= 15921-Rft Chiniot PCC= 2440-RftSullage Carrier= 310-Rft Work completed. Lat, 31.7604821 Long, 72.7525140 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of AA = 02.08.2017 2. Date of TS = 26.08.2017 3.Date of Award of work Construction of PCC / Soling / Drain, in 699 2302 Chiniot 10.000 9.410 0.590 0.590 0.443 0.443 100% 9.853 99% 31.10.2017 Surface Drain / Type - I= 2080- Town Committee Lalian, District Chiniot Rft.Brick Pavement / PCC= 1618-Rft.PCC= 3084-RftWork completed. Lat ,31.8169755 Long, 72.8073035

1. Date of AA = 24.12.2012 2. Date of TS = 29.10.2013 (Revised) 3.Date of Award of work 31.01.2013. 9"i/d Sewer= 37826- Rft12" I/d Sewer= 70160-Rft 15" i/d Sewer= 5613-Rft18" i/d Sewer= 6207-Rft21" i/d Sewer= 832-Rft24" i/d Sewer= 1635-Rft27" Extension Rehabilitation Sewerage Scheme 700 2303 Chiniot 212.366 209.621 1.000 1.000 0.750 0.750 100% 210.371 99% i/d Sewer= 1891-Rft33" i/d Sewer= 1768-Rft Chiniot City. 36" i/d Sewer= 3129-Rft42" i/d Sewer= 2674-RftScreening Chember= 1 NoCollecting Tanks= 2 No.Pump House= 1 NoPumping Machinery= 4 Sets Staff Quarter= 2 NoDeisel Genrator= 1 JobGenrator Room= 1 jobWork completed. Lat,31.711686 Long, 73.0087417

1. Date of AA = 02.08.2017 2. Date of TS = Construction of PCC / Soling / Drain,Pullian 26.08.2017 3.Date of Award of work 31.10.2017 Surface Drain / Type - I= 3339- 701 2304 Mouza Colony Mohammad Wala, Chiniot 4.000 2.539 1.461 1.461 1.096 1.096 100% 3.635 91% Rft Brick Pavement / PCC= 15038-Rft Muhammad Wala, Mamola, District Chiniot Sullage Carrier= 69-Rft Work completed. Lat 31.7001077 Long, 72.5813857

1. Date of AA = 31.07.2015 2. Date of TS = 27.08.2015 3.Date of Award of work 31.10.2015. Surface Drain / Type - I= 6902- Construction of Sewerage Disposal Harsa 702 2305 Chiniot 28.493 22.230 1.000 1.000 0.750 0.570 76% 22.800 80% Rft Brick Pavement / PCC= 36610- Sheikh Lahore road Chiniot RftSullage Carrier= 8890-RftSullage Pump / Chember= 1 Set Work completed. Liability of the contractor is pending. Lat, 31.78955 Long, 73.13034 1. Date of AA = 02.08.2017 2. Date of TS = 26.08.2017 3.Date of Award of work Construction of PCC / Soling / Drain,Mouza 703 2306 Chiniot 4.000 2.957 1.043 1.043 0.782 0.782 100% 3.739 93% 31.10.2017 Drain Type - I= 2692-RftBrick Burj Babal , District Chiniot Pavement= 7069-Rft PCC= 4612-RftWork completed. Lat, 31.7480446 Long, 72,882683 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs / UC 26.08.2017 3.Date of Award of work 31.10.2017 Drain Type - I= 2275-RftBrick 704 2307 No.35 Tehsil Bhowana District Chiniot in Chiniot 5.000 4.729 0.271 0.271 0.203 0.203 100% 4.932 99% Pavement= 22668-Rft Sullage Carrier= 109- PP-76, Chiniot Rft. Work completed. Lat 31.439965 Long, 72.6951 1. Date of AA = 02.08.2017 2. Date of TS = 26.08.2017 3.Date of Award of work Soling / Drains / Culverts / PCC Slabs / Mc 705 2308 Chiniot 10.000 7.409 1.000 1.000 0.750 0.750 100% 8.159 82% 31.10.2017 Drain Type - I= 6468-RftBrick Bhowana District Chiniot in PP-76, Chiniot Pavement= 34202-Rft Sullage Carrier= 888- Rft.Work completed. Lat 31.5484067 Long, 72.6319317 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs /Uc 26.08.2017 3.Date of Award of work 31.10.2017 Drain Type - I= 2997-Rft Brick 706 2309 No.34 Tehsil Bhowana District Chiniot PP- Chiniot 4.000 3.804 0.196 0.196 0.147 0.147 100% 3.951 99% Pavement= 11807-Rft Sullage Carrier= 144- 76, Chiniot Rft Work completed. Lat, 31.4605917 Long ,72.722835 1. Date of AA = 02.08.2017 2. Date of TS = Soling / Drains / Culverts / PCC Slabs / UC 26.08.2017 3.Date of Award of work 31.10.2017 Drain Type - I= 1855-Rft Brick 707 2310 No.33 Tehsil Bhowana District Chiniot in Chiniot 5.000 2.669 1.000 1.000 0.750 0.750 100% 3.419 68% Pavement= 19065-Rft Sullage Carrier= 877- PP-76, Chiniot Rft Work completed. Lat 31.4177022 Long, 72.6826651 Capacity Strenghthening of Design Cell of 708 2311 Punjab 180.278 62.397 8.333 8.333 35.850 35.850 100% 98.247 54% Work In Progress HUD&PHED for project Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Residential Buildings at 709 2312 Lahore Head Quarter for officers BS 16 to Punjab 277.000 81.706 10.000 10.000 7.500 7.500 100% 89.206 32% In Progress BS 18 PHED Improvement and Extension of the Water 710 2313 Punjab 260.000 19.590 50.000 50.000 0.000 0.000 #DIV/0! 19.590 8% In Progress Testing Laboratories Phase I Renovation of PHED Head Quarter 711 2314 Punjab 95.000 38.500 0.833 0.833 0.625 0.625 100% 39.125 41% In Progress Building. Establishment of Management Information 712 2315 System and Monitoring & Evaluation (MIS & Punjab 175.000 30.000 11.667 11.667 19.250 19.250 100% 49.250 28% In Progress ME) For Capacity Building Establishment of PMU for WASH (Water, 713 2316 Punjab 35.000 4.200 3.267 3.267 6.850 6.000 88% 10.200 29% In Progress Sanitataion & Hygiene) Establishment of regional design cell at 714 2317 Punjab 19.043 1.443 3.333 3.333 0.900 0.000 0% 1.443 8% In Progress each civil division / Circle level Preparation of Water Quality Survey & 715 2318 Sewerage Master Plan/Development Plan Punjab 18.235 12.435 1.650 1.650 1.238 1.238 100% 13.673 75% In Progress of Districts, Tehsil and Urban Area 716 2319 Survey & investigation of water source Punjab 9.436 0.456 2.993 2.993 0.845 0.400 47% 0.856 9% In Progress Third Party Validation for Quality Control of 717 2320 Punjab 39.847 2.301 4.182 4.182 3.137 2.091 67% 4.392 11% In Progress the New Initiatives through out Punjab Upgradation / Strengthening of Existing 718 2321 Punjab 390.000 93.500 50.000 50.000 37.500 36.500 97% 130.000 33% In Progress Laboratories at District Head Quarter Multi Sectoral Nutrition Strategy for WASH 719 2322 Including Water Supply, Sanitation, Punjab 1,013.037 100.000 166.667 166.667 125.000 109.701 88% 209.701 21% Work in Progress Hygiene, Waste Water Rehabilitation of 662 dysfunctional Rural 720 2323 Punjab 8,195.950 0.480 333.333 333.333 200.000 0.000 0% 0.480 0% Work in Progress Water Supply Schemes Combined PC-II of Water Quality Survey, Identification of outlived pipes, outsourcing of water Supply schemes, Rationalization 721 2324 Punjab 327.683 30.600 33.333 33.333 25.000 24.667 99% 55.267 17% In Progress of staff in WASAs, MC & PHED and pre qualification of contractors and manufacturers Rehabilitation of need based (identified 722 2325 through TPV) Dysfunctional Rural water Punjab 1,146.048 707.664 66.667 66.667 50.000 42.285 85% 749.949 65% In Progress Supply Schemes Scaling up Approach for Total 723 2326 Punjab 399.705 287.317 16.667 16.667 8.500 7.500 88% 294.817 74% In Progress Sanitation (PATS) in Punjab (ODF) Date of A.A= 05.08.2017. Date of T.S.=05- 10-2017. No. of Beneficiaries= UC Construction of PCC in Different Streets in 724 2327 Faisalabad 5.000 3.808 1.192 1.192 0.894 0.780 87% 4.588 92% Anticipated date of completion=01.04.2018 UC -77 District Faisalabad Investigation of source= Drainage • Surface Drain =3053/2669 Rft • PCC =11204/10666 Cft • Work in progress Construction of Gallian Nallian PCC Soling 725 2328 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Dheer Bain Construction of Gallian Nallian PCC Soling 726 2329 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Kotli Nawab Construction of Gallian Nallian PCC Soling 727 2330 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Wando Construction of Gallian Nallian PCC Soling 728 2331 Gujranwala 10.000 4.807 1.667 1.667 0.000 0.000 #DIV/0! 4.807 48% Scheme completed. and Tuff Tile in UC Kali Suba Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Gallian Nallian PCC Soling 729 2332 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Sohawa Dhalwan

Construction of Gallian Nallian PCC Soling 730 2333 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Nangal Dona Singh Construction of Gallian Nallian PCC Soling 731 2334 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Gona Osar Construction of Streets and Drainage at 732 2335 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.1 District Gujranwala Construction of Streets and Drainage at 733 2336 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.2, District Gujranwala Construction of Streets and Drainage at 734 2337 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.3, District Gujranwala Construction of Streets and Drainage at 735 2338 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.4, District Gujranwala Construction of Streets and Drainage at 736 2339 Gujranwala 5.650 3.150 0.833 0.833 0.000 0.000 #DIV/0! 3.150 56% Scheme completed. Ward No.5, District Gujranwala Construction of Streets and Drainage at 737 2340 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.6, District Gujranwala Construction of Streets and Drainage at 738 2341 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.7, District Gujranwala Construction of Streets and Drainage at 739 2342 Gujranwala 5.000 2.500 0.833 0.833 0.000 0.000 #DIV/0! 2.500 50% Scheme completed. Ward No.8, District Gujranwala Provision of PCC / Sewerage / Drainage / 740 2343 Soling etc. in Village Jajoki, Teshil Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. Nowsehra Virkan, District Gujranwala Rehabilitatin Improvement of Streets in 741 2344 Village Pir Kot Tehsil Wazirabad, District Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. Gujrnawala Construction of PCC, Sewerage/Drains at 742 2345 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. UC 63 District Gujranwala Construction of Gallian Nallian PCC Soling 743 2346 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Nadala Sindhowan

Construction of Gallian Nallian PCC Soling 744 2347 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Mandiala Tabsa

Construction of Gallian Nallian PCC Soling 745 2348 Gujranwala 10.000 5.000 1.667 1.667 0.000 0.000 #DIV/0! 5.000 50% Scheme completed. and Tuff Tile in UC Chak Ram Daas Construction of PCC Tuff Tile & Draiange at 746 2349 Railway Road, Salamat Pura, Kamoki, Gujranwala 6.755 3.930 0.942 0.942 0.000 0.000 #DIV/0! 3.930 58% Scheme completed. District Gujranwala Construction of PCC & Drainage at Street Nos.13,14,15,16,17 and St. Masjid-E- 747 2350 Gujranwala 40.000 10.000 1.126 1.126 0.000 0.000 #DIV/0! 10.000 25% Scheme completed. Shuhda, Ahl-E-Hadith, Tibba Muhammad Nagar, Kamoki, District Gujranwala

Installation of Water Filteration Plant at Scheme proposed for deletion from ADP as 748 2351 Lahore 5.350 2.833 0.839 0.839 0.000 0.000 #DIV/0! 2.833 53% Filtration Plant has already been installed in Village Class Marri Lahore. village Class Mari during F.Y 2017-18. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Scheme proposed for deletion from ADP as Installation of Water Filteration Plant at 749 2352 Lahore 5.350 0.886 1.488 1.488 0.000 0.000 0% 0.886 17% Filtration Plant has already been installed in Village Gallian Khuda Bakhsh Lahore. village Gallian Khuda Bakhsh under IPOR Package NA-130 during F.Y 2017-18.

Scheme proposed for deletion from ADP, as due to change in political scenario, 750 2353 Installation of filteration Plant Naseebabad Lahore 5.350 0.950 1.466 1.466 0.000 0.000 #DIV/0! 0.950 18% conflict with community, site is not available for installation of filtration plant. Construction of PCC, Soling, Drain and Nallah in Chak No. 11, 8, 7, 6, 18, 16, 15, Nankana 751 2354 30.000 15.000 3.333 3.333 0.867 0.867 100% 15.867 53% Funds fully utlized. Work stopped due to 14 GB and Chak No 01 (Khoti Wala) Nizam Sahib non-availability of funds. Pura District nankanasahib 1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Water Supply Dera Dogran Bhutta Colony Date of Award: 10-02-2018 7. Date of 752 2355 Lodhran 39.263 9.986 9.754 9.754 10.159 10.145 100% 20.131 51% Completion as per PC-I: 28-02-2018 8. Rukn Deen Pur, District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 3821 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Water Supply Scheme Kotli Wajjwah, Date of Award: 07-02-2018 7. Date of 753 2356 Lodhran 37.175 9.977 9.058 9.058 6.794 6.716 99% 16.693 45% Completion as per PC-I : 28-02-2018 8. District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 5367 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Water Supply Scheme Haifzaabad Date of Award: 06-02-2018 7. Date of 754 2357 Dunyapur Gharbi Remainig Portion Lodhran 49.805 9.900 13.268 13.268 14.322 14.157 99% 24.057 48% Completion as per PC-I: 28-02-2018 8. Dunyapur Sharqi, District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 4731 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Water Supply Scheme in Chak No.359/Wb Date of Award: 06-02-2018 7. Date of 755 2358 Lodhran 19.309 9.896 3.103 3.103 2.327 2.200 95% 12.096 63% Completion as per PC-I: 28-02-2018 8. District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 4235 Persons. Work is in Progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Date of Award: 10-02-2018 7. Date of Water Supply Scheme in Chak No.358/Wb 756 2359 Lodhran 26.334 9.992 5.445 5.445 4.084 3.800 93% 13.792 52% Completion as per PC-I: 28-02-2018 8. District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 4881 Persons. Work is in Progress. Scheme is under test operation.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Water Supply Scheme in Chak No.311/Wb Date of Award: 30-03-2018 7. Date of 757 2360 Lodhran 36.605 9.855 8.868 8.868 6.651 6.500 98% 16.355 45% Completion as per PC- I: 28-02-2018 8. District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 2996 Persons. Work is in Progress.

1. Date of A.A: 04-12-2017. 2. Date of T.S: 06-12-2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 03-01-2018 5. Date of Receipt of Tender: 04-01-2018 6. Water Supply Scheme in Chak No.13/M Date of Award: 10-02-2018 7. Date of 758 2361 Lodhran 28.934 9.927 6.311 6.311 4.733 4.500 95% 14.427 50% Completion as per PC-I: 28-02-2018 8. District Lodhran Anticipated Date of Completion: 20-06-2019 9.Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: 11.No. of Benificiary 1934 Persons. Work is in Progress. Construction of Nali Soling Tuff Tile & Dera Ghazi 759 2362 7.000 2.000 1.000 1.000 0.750 0.735 98% 2.735 39% "• Date of A.A = 13.1.17 Culverts UC Shero Dasti Dg Khan Khan Construction of Nali Soling Tuff Tiles,, Dera Ghazi 760 2363 Drainage, Culverts and Qulabas U/Cjhoke 10.000 2.000 1.000 1.000 0.750 0.000 0% 2.000 20% • Date of A.A = 13.1.17 Khan Ultra, D.G Khan Rehabilitation of Water Supply in Fareed Dera Ghazi 761 2364 10.000 7.000 1.000 1.000 0.750 0.735 98% 7.735 77% "• Date of A.A = 25.7.2017 Abad PP-244 District Dg Khan Khan Rehabilitation of Water Supply in Gharib Dera Ghazi 762 2365 10.000 5.000 1.000 1.000 0.750 0.735 98% 5.735 57% "• Date of A.A = 25.7.2017 Abad PP-244 District Dg Khan Khan Rehabilitation of 10 Rural Water Supply Date of A.A :19-07-2017.Date of T.S: 21-07- 763 2366 Schemes Tehsil Murree & Kotli Sattian, Rawalpindi 34.830 9.787 3.333 3.333 1.677 1.677 100% 11.464 33% 2017.Date of Start: 19-07-2017.Date of District Rawalpindi Completion:30-06-2021.Work in progress Const. of 02 Nos. Filtration Plants in each Ward of Chaklala Cantt Ward No.5 to 10& Date of A.A :05-09-2017.Date of T.S: 07-09- 764 2367 Rawalpindi 50.000 19.500 4.667 4.667 2.334 2.334 100% 21.834 44% 2017.Date of Start: 29-11-2017.Date of Const. of 0.2 MG capacity UGT at Sarwar Completion:30-06-2020.Work in progress. Park LalKurti, District Rawalpindi

Const. of Bridge / Drain at Rawal Town, Tench Road/Adra Bridge/ Kacha Stop Date of A.A :05-09-2017.Date of T.S: 07-09- 765 2368 Rawalpindi 50.000 20.000 6.667 6.667 11.285 11.285 100% 31.285 63% 2017.Date of Start: 29-11-2017.Date of under Railway Track/Aliabad/Dk. Banaras/ Completion:30-06-2020.Work in progress Ahmadabad, District Rawalpindi Const. of Road / Sewerage at each Ward No.1 to 10 of Rawalpindi Cantt and Ward Date of A.A :05-09-2017.Date of T.S: 07-09- 766 2369 Rawalpindi 50.000 20.909 6.667 6.667 7.500 7.500 100% 28.409 57% 2017.Date of Start: 29-11-2017.Date of No.5 to 10 & Minority Member, District Completion:30-06-2021.Work in progress. Rawalpindi Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A :16-09-2017.Date of T.S: 06-10- Construction of streets in UCs PP-03 2017.Date of Start: 16-11-2017.Date of 767 2370 including Gujar Khan City, District Rawalpindi 150.000 35.897 6.667 6.667 10.329 10.329 100% 46.226 31% Completion:30-06-2021.Work is in Rawalpindi progress, contractor liability of about 10.00 Million is pending. Laying of 4’’ Dia Water Supply Pipe Line Date of A.A :05-09-2017.Date of T.S: 07-09- 2017.Date of Start: 18-11-2017.Date of 768 2371 Ward No,1 to Ward No,10 Rawalpindi Rawalpindi 40.000 10.000 10.000 10.000 7.500 7.500 100% 17.500 44% Completion:30-06-2020.Restoration of Cantonment Board ., District Rawalpindi dismentalled PCC streets is in progress.

Const. of 02 Nos. Filtration Plants in each Ward of Rawalpindi Cantt Ward No.1 to 10 Date of A.A :05-09-2017.Date of T.S: 07-09- 769 2372 Rawalpindi 50.000 20.000 10.000 10.000 7.500 7.500 100% 27.500 55% 2017.Date of Start: 29-11-2017.Date of and Const. of 0.2 MG capacity UGT at Dk. Completion:30-06-2020.Work is in progress Gujran Ward No.10, District Rawalpindi

Date of A.A :05-09-2017.Date of T.S: 07-09- Construction of Under Ground Water Tank 2017.Date of Start: 28-11-2017.Date of 770 2373 Rawalpindi Cantonment Board, District Rawalpindi 25.000 21.156 1.114 1.114 0.836 0.836 100% 21.992 88% Completion:30-06-2020.Only electric Rawalpindi connection pending rest of physical work completed. Date of A.A :19-07-2017.Date of T.S: 21-07- Water Supply Scheme at Dhala, District 771 2374 Rawalpindi 10.200 5.000 1.733 1.733 1.300 1.300 100% 6.300 62% 2017.Date of Start: 29-11-2017.Date of Rawalpindi Completion:30-06-2020.Work is in progress. Construction of PCC link road Wasla to Dhoke Bhattian, length=2.00 Km UC Sui Date of A.A :19-07-2017.Date of T.S: 21-07- 772 2375 Rawalpindi 12.815 5.000 2.605 2.605 3.351 3.351 100% 8.351 65% 2017.Date of Start: 02-12-2017.Date of Chemian, Tehsil Gujar Khan, District Completion:30-06-2020.Work is in progress Rawalpindi Construction of PCC link road Sattal to Date of A.A :19-07-2017.Date of T.S: 21-07- Sabah Sher and Dhoke Phugoo, 2017.Date of Start: 29-11-2017.Date of 773 2376 Rawalpindi 12.881 5.000 2.627 2.627 0.302 0.000 0% 5.000 39% Completion:30-06-2020.Funds re- length=2.00 Km, Tehsil Gujar Khan, District appropriated to other schemes due to its Rawalpindi meager allocation.

Construction of PCC road Dhoke Khumbail, Date of A.A :19-07-2017.Date of T.S: 21-07- 774 2377 Phase-I, length=1.5 Km, UC Sui Chemian, Rawalpindi 10.569 5.000 1.856 1.856 0.533 0.533 100% 5.533 52% 2017.Date of Start: 02-12-2017.Date of Tehsil Gujar Khan, District Rawalpindi Completion:30-06-2020.Work is in progress

Date of A.A :19-07-2017.Date of T.S: 21-07- Constt. Of PCC link Road Mohri Barsal uc 775 2378 Rawalpindi 14.000 8.969 1.677 1.677 2.656 2.655 100% 11.624 83% 2017.Date of Start: 25-11-2017.Date of Jero Ratial., District Rawalpindi Completion:30-06-2019.Scheme physically completed only contractor liability pending.

Constt. Of PCC link Road Paka Khanpur Date of A.A :19-07-2017.Date of T.S: 21-07- 776 2379 Rawalpindi 14.000 4.917 3.000 3.000 0.750 0.750 100% 5.667 40% 2017.Date of Start: 02-12-2017.Date of UC Bhadana., District Rawalpindi Completion:30-06-2020.Work is in progress

Constt. Of PCC link Road Dhoke Rajgan Date of A.A :19-07-2017.Date of T.S: 21-07- 777 2380 Rawalpindi 12.000 5.000 2.333 2.333 1.750 1.750 100% 6.750 56% 2017.Date of Start: 29-11-2017.Date of UC Qazian., District Rawalpindi Completion:30-06-2020.Work is in progress

Constt. Of PCC link Road Dhoke fateh Date of A.A :19-07-2017.Date of T.S: 21-07- 778 2381 Rawalpindi 11.000 4.500 2.000 2.000 1.500 1.500 100% 6.000 55% 2017.Date of Start: 29-11-2017.Date of Paharian UC Qazian., District Rawalpindi Completion:30-06-2020.Work is in progress Constt. Of PCC link Road Dhoke Channi Date of A.A :19-07-2017.Date of T.S: 21-07- 2017.Date of Start: 29-11-2017.Date of 779 2382 Dakhali Sohawa Mirzian, Islam Pura Jabbar Rawalpindi 11.000 5.000 2.000 2.000 1.500 1.500 100% 6.500 59% Completion:30-06-2020.Work is in / Bewal., District Rawalpindi progress.

Construction of PCC link road Jhawan to Date of A.A :19-07-2017.Date of T.S: 21-07- 780 2383 Kountrila UC Kountrila, length=1.70 Km, Rawalpindi 10.530 4.773 1.843 1.843 1.243 1.243 100% 6.016 57% 2017.Date of Start: 29-11-2017.Date of Tehsil Gujar Khan, District Rawalpindi Completion:30-06-2020.Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC link road Kanyal to Date of A.A :19-07-2017.Date of T.S: 21-07- Dhoke Jeaven, length=1.70 Km UC Mohra 2017.Date of Start: 29-11-2017.Date of 781 2384 Rawalpindi 10.170 4.995 1.723 1.723 0.000 0.000 #DIV/0! 4.995 49% Completion:30-06-2020.Funds re- Noori, Tehsil Gujar Khan, District appropriated to other schemes due to its Rawalpindi meager allocation. A.A Date 02.08.2017. T.S Date Drainage scheme at Noorpur and Lundi, 782 2385 Attock 26.139 9.977 5.380 5.380 2.650 2.648 100% 12.625 48% 13.09.2017.Date of Start of Scheme Tehsil Hazro, District Attock 29.01.2018 . Date of Completion of Scheme 30.06.19. Work is in progress. A.A Date 02.08.2017.T.S Date Drainage scheme at Khudlathi and 783 2386 Attock 28.306 9.977 6.102 6.102 4.577 4.571 100% 14.548 51% 13.09.2017.Date of Start of Scheme Sarwana, Tehsil Hazro, District Attock 07.12.2017.Date of Completion of Scheme 30.06.19. Work is in progress. A.A Date 02.08.2017. T.S Date 13.09.2017 . Drainage scheme at Musa and Sherani, 784 2387 Attock 26.931 14.976 3.977 3.977 2.983 2.983 100% 17.959 67% Date of Start of Scheme 27.11.2017. Date Tehsil Hazro, District Attock of Completion of Scheme30.06.19. Work is in progress. A.A Date 02.08.2017. T.S Date 13.09.2017 . Rural drainage scheme in village 785 2388 Attock 32.394 9.980 3.333 3.333 2.500 2.500 100% 12.480 39% Date of Start of Scheme 09.12.2017. Date Shakardara Phase-II, District Attock of Completion of Scheme 30.06.2019. Work is in progress.

Rural draiange scheme in village A.A Date 02.08.2017. T.S Date 13.09.2017.Date of Start of Scheme 786 2389 Ghourgushti Phase-II, Tehsil Hazro, District Attock 19.313 9.914 3.104 3.104 2.328 2.325 100% 12.239 63% 09.12.2017.Date of Completion of Scheme Attock 30.06.2019.Work is in progress. Construction of PCC road from Kohat road A.A Date 02.08.2017. T.S Date 13.09.2017. Date of Start of Scheme 06.12.2017. Date 787 2390 Bhandar to Dhok Sanakhi UC Langar Attock 28.500 9.979 6.167 6.167 4.625 4.624 100% 14.603 51% of Completion of Scheme 30.06.19. Work is Tehsil Jand District Attock in progress. Water Supply scheme of village Ferozwali A.A Date 02.08.2017. T.S Date 13.09.2017 . Date of Start of Scheme 10.01.2018. Date 788 2391 UC Gareebwal Tehsil District Attock 22.500 7.961 4.833 4.833 3.625 3.625 100% 11.586 51% of Completion of Scheme 30.06.2019.Work Attock is in progress.

A.A Date 16.09.2017. T.S Date 11.10.2017 Drainage / sewerage scheme in village 789 2392 Attock 61.838 25.999 3.333 3.333 2.500 2.500 100% 28.499 46% .Date of Start of Scheme 06.11.2017. Date , Daman, Jalalia, District Attock of Completion of Scheme 30.06.2019. work is in progress.

A.A Date 16.09.2017. T.S Date 10.10.2017. Drainage / sewerage scheme in village 790 2393 Attock 54.788 19.972 3.333 3.333 3.500 3.500 100% 23.472 43% Date of Start of Scheme 09.12.2017.Date of Shadi Khan Phase-II, District Attock Completion of Scheme 30.06.2019.Work is in progress.

A.A Date 02.08.2017. T.S Date 13.09.2017 . Drainage / Sewerage System in village 791 2394 Attock 15.450 9.346 1.817 1.817 1.363 1.360 100% 10.706 69% Date of Start of Scheme 29.11.2017.Date of , Tehsil Hazro, District Attock Completion of Scheme 30.06.2019.Work is in progress.

Rural drainage scheme and water supply Date of A.A 31.07.2017.Date of T.S 792 2395 Oudherwal and Mohallah Islam Pura Chakwal 18.000 10.000 2.667 2.667 2.600 2.600 100% 12.600 70% 08.08.2017.Date of Start 18.10.2017.Date of Chakwal completion 30.06.2019.Work is in progress. Date of A.A 31.07.2017.Date of T.S Rural drainage scheme and Water Supply 793 2396 Chakwal 24.000 10.000 4.667 4.667 5.031 5.031 100% 15.031 63% 08.08.2017.Date of Start 18.10.2017.date of in UC Dub, District Chakwal completion 30.06.2019.Full funds utilized. Scheme is short funded. Urban sewerage and drainage scheme in Date of A.A 31.07.2017.Date of T.S 08.08.2017.Date of Start 19.10.2017. Date 794 2397 Chakwal City, Ward No.1 to Ward No.12, Chakwal 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% of completion 30.06.2020.Full funds utilized. District Chakwal Scheme is short funded. Urban Drainage & Sewerage scheme of Date of A.A 31.07.2017.Date of T.S 08.08.2017.Date of Start 19.10.2017.Date of 795 2398 Chakwal City from Ward No.13 to Ward Chakwal 30.000 16.000 4.667 4.667 14.000 13.998 100% 29.998 100% completion 30.06.2019.Allocated funds No.23, District Chakwal were utilized.

Urban Drainage & Sewerage scheme of Date of A.A 31.07.2017.Date of T.S 796 2399 Chakwal City from Ward No.28 to Ward Chakwal 30.000 9.970 3.333 3.333 2.500 2.500 100% 12.470 42% 08.08.2017.Date of Start 19.10.2017.Date of No.37, District Chakwal completion 30.06.2020.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Rural drainage scheme and retaining wall Date of A.A 31.07.2017.Date of T.S 797 2400 and Cause Way in MC Bhaun, District Chakwal 27.000 13.000 4.667 4.667 7.000 6.998 100% 19.998 74% 08.08.2017.Date of Start 23.10.2017.Date of Chakwal completion 30.06.2019.Work in progress. Rural Drainage Scheme and Retaining wall Date of A.A 31.07.2017.Date of T.S 798 2401 and Cause way in UC Mureed, District Chakwal 25.000 13.999 3.667 3.667 2.750 2.745 100% 16.744 67% 08.08.2017.Date of Start 25.10.2017.Date of Chakwal completion 30.06.2019.Work in progress. Rural Drainage Scheme and Retaining wall Date of A.A 31.07.2017.Date of T.S 799 2402 and Cause way in UC Jand Awan, District Chakwal 20.000 9.997 3.333 3.333 2.500 2.500 100% 12.497 62% 08.08.2017.Date of Start 26.10.2017.Date of Chakwal completion 30.06.2019.Work in progress. Rural drainage and water supply village Date of A.A 31.07.2017.Date of T.S 800 2403 Chakwal 20.000 10.000 3.333 3.333 0.969 0.969 100% 10.969 55% 08.08.2017.Date of Start 26.10.2017.Date of Tatral, District Chakwal completion 30.06.2019.Work is in progress.

Rural Drainage scheme and Retaining wall Date of A.A 31.07.2017.Date of T.S 801 2404 Chakwal 17.000 9.996 2.333 2.333 1.150 1.150 100% 11.146 66% 08.08.2017.Date of Start 26.10.2017 .Date in UC Mulhal Mughllan, District Chakwal of completion 30.06.2019.Work in progress.

Rural draiange scheme & Retaining wall Date of A.A 31.07.2017.Date of T.S 802 2405 and causeway in UC Chak Umara, District Chakwal 13.000 8.000 1.667 1.667 3.750 3.333 89% 11.333 87% 08.08.2017.Date of Start 26.10.2017.Date of Chakwal completion 30.06.2019.Work is in progress. Rural drainage scheme UC -Jaswal, Tehsil Date of A.A 31.07.2017.Date of T.S 803 2406 Chakwal 20.000 9.997 3.333 3.333 1.900 1.900 100% 11.897 59% 08.08.2017.Date of Start 26.10.2017.Date of & District Chakwal completion 30.06.2019.Work is in progress.

Rural drainage scheme Nichandi & Dhapai, Date of A.A 31.07.2017.Date of T.S 804 2407 Chakwal 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% 08.08.2017.Date of Start 27.10.2017.Date of Tehsil & District Chakwal completion 30.06.2019.Work in progress.

Construction of PCC, Streets, Drain & Date of A.A 09.08.2017.Date of T.S 805 2408 Chakwal 147.248 29.998 3.333 3.333 2.500 2.495 100% 32.493 22% 02.10.2017.Date of Start 17.11.2017. Date Water Supply at Talagang, District Chakwal of completion 30.06.2020.Work in progress.

Construction of PCC, Streets, Drain & Date of A.A 09.08.2017.Date of T.S 806 2409 Water Supply at Tehsil Lawa PP-23, District Chakwal 98.166 24.920 3.333 3.333 2.500 2.499 100% 27.419 28% 08.08.2017.Date of Start 21.11.2017.Date of Chakwal completion 30.06.2020.Work in progress. Restoration / Flood Rains Damages vented causeway on Dhermond to Dk. Fateh Shah Date of A.A 31.07.2017.Date of T.S 08.08.2017.Date of Start 27.10.2017.Date of 807 2410 Road, Vented causeway Darot & street / Chakwal 14.239 10.000 1.413 1.413 0.707 0.707 100% 10.707 75% completion 30.06.2019.Scheme completed. drains village Wanhar, Tehsil Talagang, Excess funds re-appropriated. District Chakwal Scheme shall be completed by 30-06- Provision of sewerage at Ward No.36 2020.Balance funds required Rs. 8.187 808 2411 Jhelum 15.000 4.480 2.333 2.333 1.750 1.750 100% 6.230 42% million.A.A Date 27-07-2017.T.S Date 09-08- Tehsil & District Jhelum, District Jehlum 2017.Date of Work Award 09-09-2017.Work in progress. Scheme shall be completed by 30-06- Provision of Sewerage system at UC Kotla 2020.Balance funds required Rs. 10.000 809 2412 Jhelum 30.000 10.000 3.333 3.333 9.185 9.185 100% 19.185 64% million.A.A Date 27-07-2017.T.S date 09-08- Faqeer, Tehsil & District Jhelum 2017.Date of Work Award 09-09-2017.Work in progress Provision of Water Supply at Pind Sawika, "Scheme shall be completed by 30-06- 810 2413 Jhelum 15.000 7.988 2.333 2.333 0.750 0.750 100% 8.738 58% 2020.Balance funds required Rs. 4.679 Tehsil & District Jhelum million.A.A Date 27-07-2017 Provision of Water supply at village Kundal, "Scheme shall be completed by 30-06- 811 2414 Jhelum 21.747 9.941 3.916 3.916 9.406 9.406 100% 19.347 89% 2020.Balance funds required Rs. 1.421 District Jhelum million.A.A Date 27-07-2017 Water supply scheme at Chak No.165 812 2415 Sargodha 10.673 4.947 1.891 1.891 1.418 1.411 100% 6.358 60% Work in progress. Shumali, Sillanwali, District Sargodha Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 813 2416 Sargodha 20.000 9.979 3.333 3.333 2.500 2.209 88% 12.188 61% Work in progress. in Chak No 45/SB Tehsil and District Sargodha Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 814 2417 Sargodha 20.000 9.977 3.333 3.333 2.500 2.226 89% 12.203 61% Work in progress. in Chak No 46/Sb tehsil and District Sargodha Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 815 2418 Sargodha 20.003 9.920 3.334 3.334 2.501 2.344 94% 12.264 61% Work in progress. in Chak No 107/Sb Tehsil and District Sargodha Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 816 2419 Sargodha 10.004 6.036 1.323 1.323 0.993 0.993 100% 7.029 70% Work in progress.Latitude/ in Chak No 85/NB tehsil and District Longitude32.02°/72.36° Sargodha Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 817 2420 Sargodha 10.008 4.972 1.669 1.669 1.252 1.118 89% 6.090 61% Work in progress. in Chak No 84/NB Tehsil and District Sargodha Water supply scheme at Chak No.129 818 2421 Sargodha 23.594 7.000 4.531 4.531 3.398 3.364 99% 10.364 44% Work in progress. Janobi, Sillanwali, District Sargodha Water supply scheme at Chak No.119 819 2422 Sargodha 17.002 10.000 2.334 2.334 1.751 1.671 95% 11.671 69% Work in progress. Janobi, Sillanwali, District Sargodha Water supply scheme at Chak No.111/107 820 2423 Sargodha 17.193 10.000 2.398 2.398 1.799 1.624 90% 11.624 68% Work in progress. Shumali, Sillanwali, District Sargodha Water supply scheme at Chak No.140 821 2424 Sargodha 12.961 5.997 2.320 2.320 1.740 1.672 96% 7.669 59% Work in progress. Janobi, Sillanwali, District Sargodha Construction of Drain / PCC / Soling / 822 2425 Sullage Carrier at Midh Pergana Islam Pure Sargodha 16.130 10.000 2.043 2.043 1.532 1.456 95% 11.456 71% Work in progress. More, Tehsil Bhera. District Sargodha

Construction of PCC / Soling / Sewerage / 823 2426 Nullah Dera Abdul Sattar jhamat Chak No. Sargodha 20.000 9.972 3.333 3.333 2.500 2.411 96% 12.383 62% Work in progress. 19 Shumali L= 2800 Feet, District Sargodha Construction of PCC / Soling / Sewerage / Chabar Balooka Dera Mehar Muhammad 824 2427 Akhtar Lak and PCC / Soling Mehar Qadir Sargodha 20.000 10.000 3.333 3.333 2.500 2.226 89% 12.226 61% Work in progress. Yat Lak, UC Sakisar Baar, District Sargodha Constructio of Soling / Sewerage / PCC, Dera Jaat via Mehar Shahid Akram Lak, 825 2428 Ghulam Ahmed Kamrana, Ahmed Yaar Sargodha 20.000 10.000 3.333 3.333 2.500 2.361 94% 12.361 62% Work in progress. Gondal, Haji Muhammad Sher, UC Mardi Lak, District Sargodha Construction of Soling / PCC / Nullah / Dera Mahar Nasar Hayat Lak and Soling Lak More to Bonga Minhas Colony, Dera Jaat 826 2429 Sargodha 20.000 10.000 3.333 3.333 2.500 2.213 89% 12.213 61% Work in progress. Mahar Muhammad Bakhsh Lak, Mahar Abdul Rehamn Lak, Salah Muhammad Sipra, UC Lak More, District Sargodha Construction of Soling / PCC / UC Chak No. 827 2430 Sargodha 20.000 9.978 3.333 3.333 2.500 2.500 100% 12.478 62% Work in progress. 58 Shumali, District Sargodha Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construciton of Soling Dera Jaat Badle Wala and PCC / Sewerage and repair of 828 2431 Sargodha 20.000 10.000 3.333 3.333 2.500 2.490 100% 12.490 62% Work in progress. road Chak No. 53 Shumali, District Sargodha Rural Drainage scheme for Chak No 9/SB, 829 2432 Sargodha 29.294 11.100 3.333 3.333 2.500 2.241 90% 13.341 46% Work in progress. District Sargodha Rural Drainage scheme for Chak No.18/SB 830 2433 Sargodha 25.885 13.609 3.333 3.333 2.500 2.500 100% 16.109 62% Work in progress. & Colonies, District Sargodha Rural Drainage scheme Chak No.2/NB, 831 2434 Sargodha 30.261 9.966 3.333 3.333 2.500 2.352 94% 12.318 41% Work in progress. District Sargodha Rural Drainage Scheme Abdal, District 832 2435 Sargodha 25.667 10.885 3.333 3.333 2.500 2.500 100% 13.385 52% Work in progress. Sargodha Construciton of Drainage / Soling, Adjoining 833 2436 Abadies of Mouza Ahmaday wala, District Sargodha 15.000 5.000 3.333 3.333 2.500 2.219 89% 7.219 48% Work in progress. Sargodha Rural drainage scheme UC No.64, 834 2437 Sargodha 19.991 8.500 3.330 3.330 2.498 2.301 92% 10.801 54% Work in progress. Dharema, Sargodha, District Sargodha Rural drainage scheme UC No.77, 835 2438 Sargodha 19.927 9.995 3.309 3.309 2.482 2.132 86% 12.127 61% Work in progress. Hyderabaad Town, District Sargodha Rural drainage scheme UC No.76, Chak 836 2439 Sargodha 19.955 10.000 3.318 3.318 2.489 2.462 99% 12.462 62% Work in progress. No.71/NB, District Sargodha Rural drainage scheme UC No.74, Chak 837 2440 Sargodha 19.987 10.000 3.329 3.329 2.497 2.222 89% 12.222 61% Work in progress. No.79/NB, District Sargodha Drainage scheme at Chak No.132/136, 838 2441 Sargodha 29.657 11.993 3.333 3.333 2.500 2.494 100% 14.487 49% Work in progress. Janobi, Sillanwali, District Sargodha Drainage scheme at Chak No.125/129 839 2442 Sargodha 32.611 10.000 3.333 3.333 2.500 2.500 100% 12.500 38% Work in progress. Shumali, Sillanwali, District Sargodha Drainage scheme at Chak No.128/130 840 2443 Sargodha 33.563 12.999 3.333 3.333 2.500 2.252 90% 15.251 45% Work in progress. Janobi, Sillanwali, District Sargodha Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 841 2444 Sargodha 15.000 10.000 1.667 1.667 1.251 1.211 97% 11.211 75% Work in progress. in Chak No 23-ASB Tehsil and District Sargodha. Construction of road Drain / Soling / Re- Soling / PCC / Tuff Pavers / Sullage Carrier 842 2445 Sargodha 15.002 10.000 1.667 1.667 1.251 1.114 89% 11.114 74% Work in progress. in Chak No 73/SB Tehsil and District Sargodha Urban Sewerage & Drainage Scheme in 843 2446 Sargodha 50.000 19.981 3.333 3.333 2.500 2.500 100% 22.481 45% Work in progress. M.C-04 Sargodha City. Urban Sewerage & Drainage Scheme in 844 2447 Sargodha 40.000 19.788 3.333 3.333 2.500 2.500 100% 22.288 56% Work in progress. M.C-19 Sargodha City. Urban Sewerage & Drainage Scheme in 845 2448 Cantonment Ward No. 01 to 05 Sargodha Sargodha 50.000 20.675 3.333 3.333 2.500 2.500 100% 23.175 46% Work in progress. City. Urban Sewerage & Drainage Scheme in 846 2449 Cantonment Ward No. 06 to 10 Sargodha Sargodha 50.000 21.099 3.333 3.333 2.500 2.500 100% 23.599 47% Work in progress. City. Urban Sewerage & Drainage Scheme / Water Supply Pipeline including Disposal 847 2450 Sargodha 50.000 19.917 3.333 3.333 2.500 2.448 98% 22.365 45% Work in progress. Station Gillwala and Tiwana Park Sargodha City. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Urban Sewerage & Drainage Scheme / Water Supply Pipeline including Disposal 848 2451 Station M.C No. 07 Street No. 01, 02, 03, Sargodha 50.000 22.600 3.333 3.333 2.500 2.240 90% 24.840 50% Work in progress. 04 & 05 to Rehman Pura Chowk via Pistool Marka Gali Sargodha City. Urban Sewerage & Drainage Scheme / 849 2452 Water Supply Pipeline in M.C No. 08 Sargodha 40.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 56% Work in progress. Sargodha City. Urban Sewerage & Drainage Scheme / Water Supply Pipeline including Renovation 850 2453 Sargodha 45.000 19.996 3.333 3.333 2.500 2.500 100% 22.496 50% Work in progress. of Disposal Station Eid Gah M.C No. 09 Sargodha City. Urban Sewerage & Drainage Scheme / 851 2454 Water Supply Pipeline M.C No. 11 & M.C Sargodha 50.000 21.260 3.333 3.333 2.500 2.290 92% 23.550 47% Work in progress. No. 13 Sargodha City Urban Sewerage & Drainage Scheme / Water Supply Pipeline including Disposal 852 2455 Sargodha 50.000 13.000 3.333 3.333 2.500 2.500 100% 15.500 31% Work in progress. Station Iqbal Colony and at Girls Degree College to Block No. 16 Sargodha City

Urban Sewerage & Drainage Scheme / Water Supply Pipeline Madina Town, New 853 2456 Madina Town, Muhammadi Colony Sargodha 50.000 20.309 3.333 3.333 2.500 2.500 100% 22.809 46% Work in progress. including Disposal Station and Main Water Works Chowk / Road Sargodha City.

Urban Sewerage & Drainage Scheme / 854 2457 Water Supply Pipeline M.C No. 22 with Sargodha 50.000 21.488 3.333 3.333 2.500 2.500 100% 23.988 48% Work in progress. Road Election Commission Sargodha City. Urban Sewerage & Drainage Scheme / 855 2458 Water Supply Pipeline M.C No. 20 M.C No. Sargodha 40.000 19.969 3.333 3.333 2.500 2.268 91% 22.237 56% Work in progress. 21 Sargodha City. Urban Sewerage & Drainage Scheme / Water Supply Pipeline Hameed Town, 856 2459 Society Colony including Renovation of Sargodha 45.000 19.994 3.333 3.333 2.500 2.238 90% 22.232 49% Work in progress. Main Disposal Works Sillanwali Road Sargodha City. Urban Sewerage & Drainage Scheme in 857 2460 Sargodha 50.000 24.739 3.333 3.333 2.500 2.500 100% 27.239 54% Work in progress. M.C-01 Sargodha City. Urban Sewerage & Drainage Scheme in 858 2461 Sargodha 30.000 14.684 3.333 3.333 2.500 2.386 95% 17.070 57% Work in progress. M.C-02 Sargodha City. Urban Sewerage & Drainage Scheme in 859 2462 Sargodha 30.000 9.580 3.333 3.333 2.500 2.250 90% 11.830 39% Work in progress. M.C-03 Sargodha City. Rehabilitation water supply scheme Bhera 860 2463 Sargodha 80.000 33.978 3.333 3.333 4.472 4.472 100% 38.450 48% Work in progress. Town, District SargodhaPhase-I Urban Water Supply Scheme Distribution System Factory Area, Essa Nagar, 861 2464 Istaqlalabad, Hameed Town, Corporation Sargodha 30.000 14.911 3.333 3.333 2.500 2.281 91% 17.192 57% Work in progress. Town, Society Colony and Nallah including Slab Karkhana Bazar Sargodha City. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Additional Water Supply pipeline in Cheema Colony, Kalyar Town, Rehmat 862 2465 Sargodha 30.000 15.000 3.333 3.333 2.500 2.249 90% 17.249 57% Work in progress. Park, Pir Muhammad Colony & Adjoining Colonies Sargodha City. Rehabilitation of Water Supply Scheme 863 2466 Sargodha 50.000 20.000 3.333 3.333 2.500 2.268 91% 22.268 45% Work in progress. New Satellite Town Sargodha City Providing / Fixing Ultra Filtration Plants U.F 864 2467 / R.O in Wards / M.Cs in PP-34 Sargodha Sargodha 40.000 25.000 3.333 3.333 2.500 2.303 92% 27.303 68% Work in progress. City 10-No. Up-gradation of Disposal Works in New Satellite Town & Ghani Park and laying of 865 2468 Sargodha 48.000 27.221 3.333 3.333 2.500 2.500 100% 29.721 62% Work in progress. Distribution System in New Satellite Town & adjoining abadies Sargodha City Water supply scheme at Sobaga, 866 2469 Sargodha 23.195 9.943 3.333 3.333 2.500 2.343 94% 12.286 53% Work in progress. Sillanwali, District Sargodha Construction of PCC Tuff Tiles / Tuff Pever road Liaqat Shaheed road to Merydal School & Suger Mil road to Lalazar Colony 867 2470 Sargodha 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. road & Merydal School to Sail Nallah & Pathan Wala road, Street Masjid Wali, Bhalwal, District Sargodha Construciton of Sewerage Scheme, Tehsil 868 2471 Sargodha 50.000 29.250 3.333 3.333 2.500 2.500 100% 31.750 64% Work in progress. Sahiwal, District Sargodha Construciton of Sewerage Scheme 869 2472 Sargodha 50.000 20.000 3.333 3.333 2.500 2.153 86% 22.153 44% Work in progress. Farooqa, District Sargodha Construciton of Sewerage Scheme Vijh, 870 2473 Sargodha 30.000 8.200 3.333 3.333 2.500 2.248 90% 10.448 35% Work in progress. Tehsil Sahiwal, District Sargodha Construciton of Sewerage Scheme 871 2474 Sargodha 40.000 14.992 3.333 3.333 4.807 4.793 100% 19.785 49% Work in progress. Nehong, Tehsil Sahiwal, District Sargodha

Date of AA 29.7.2017 Date of T.S 04.09.2017 Date of award 09.12.2017 Date of completion 30.06.2019 Tube Well 1 No. Extension of Rural Water Supply Scheme, 872 2475 Khushab 24.530 9.979 4.843 4.843 3.632 3.630 100% 13.609 55% Pump House 1 No. Rising Main Malwal, District Khushab 11000/18000 Rft D/System 6000/6070Rft Work is in progress. Latitude 32.489601666666665, Longitude 72.33234333333333

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of award 23.12.2017 Date of Provision of 100 Hand Pumps at Mahar 873 2476 Khushab 30.000 9.991 3.333 3.333 2.500 2.500 100% 12.491 42% completion 30.06.2020 Hand Pump 25/34 Area, District Khushab District Khushab Nos. Bore with submersible pump 16/29 Nos. G.S Tank 500 Glns 5/29 Nos. Latitude 32.37667833333333, Longitude 71.895465

Date of AA 29.07.2017 Date of TS 04.9.2017 Date of award 18.12.2017 Date Extension / Improvement of Water Supply of completion 30.06.2020 Tube Well 1 No. 874 2477 Scheme, Kuradhi UC Uchhali, District Khushab 21.225 3.000 3.333 3.333 2.500 2.500 100% 5.500 26% Pump House 1 No. Pumping Machinery 1 Khushab No. Rising Main 3240/28525 Rft Work is in progress. Latitude 32.55372, Longitude 72.05391333333334

Date of AA 29.07.2017 Date of TS Rehabilitation / Improvement of Water 05.09.2017 .2015 Date of award 08.01.2018 Date of completion 30.06.2019 Rising Main 875 2478 Supply Scheme, Fateh Pur Maira UC Khushab 12.400 5.595 2.133 2.133 1.600 1.595 100% 7.190 58% 10750/11500 Rft D/System 0/2355 Rft Work Gunjial Shumali, District Khushab is in progress. Latitude 32.4330485, Longitude 71.9206826 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA 29.07.2017 Date of TS 05.09.2017 Date of award 23.12.2017 Date Rehabilitation of Water Supply Scheme, of completion 30.06.2020 Tube Well 1 No. 876 2479 Khushab 25.000 9.999 3.333 3.333 2.500 2.500 100% 12.499 50% Pump House 1 No. Pumping Machinery 1 Warcha UC Warcha, District Khushab No. Rising Main 11880/17875 Rft D/System 0/1320 Rft Work is in progress. Latitude 32.40596, Longitude 71.93284833333334

Date of Rev. AA13.06.2018 Date of TS 22.06.2018 Date of award 16.12.2017 Date Rehabilitation of Water Supply Scheme, of completion 30.06.2020 Tube Well 1 No. 877 2480 Khushab 15.230 8.750 1.743 1.743 1.307 1.307 100% 10.057 66% Pump House 1 No. Pumping Machinery 1 Kufri UC Kufri, District Khushab No. Rising Main 7300/9860 Rft Work is in progress. Latitude 32.545386666666666, Longitude 72.09819333333333

Date of AA 29.07.2017 Date of TS 4.9.2017 Date of award 11.12.2017 Date of Construciton of Water Supply Scheme of completion 30.06.2020 Tube Well 6/6 Set. 878 2481 Rehman Colony MC Hadhali, District Khushab 30.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 58% Pumping Machinery 6 Nos. Rising Main Khushab 52422/52696 Rft Work is in porgress. Latitude 32.27144833333333, Longitude 72.251625

Date of AA 29.07.2017 Date of TS 4.9.2017 Date of award 11.12.2017 Date of Construciton of Water Supply Scheme of completion 30.06.2019 Tube Well 6 Nos. 879 2482 Zaman Colony MC Hadhali, District Khushab 30.000 15.999 4.667 4.667 3.500 3.440 98% 19.439 65% Pumping Machinery 6/6 Set. Rising Main Khushab 56500/60400 Rft Work is in progress . Latitude 32.27241166666667, Longitude 72.25867333333333 Date of AA 16.10.2017 Date of TS 21.11.2017 Date of award 04.01.2018 Date Provision of sewerage scheme Roda, of completion 30.06.2020 RCC Sewer 880 2483 Khushab 100.000 23.486 3.333 3.333 2.500 2.440 98% 25.926 26% 0/1500 Rft. PCC Slab 47342/293128 Cft District Khushab Work is in progress. Latitude 32.07192833333333, Longitude 72.09581333333334 Date of AA 29.07.2017 Date of TS 5.9.2017 Date of award 08.12.2017 Date of Provision of Drainage System in MC Mitha completion 30.06.2020 PCC Slab 881 2484 Khushab 49.900 14.997 3.333 3.333 2.500 2.450 98% 17.447 35% 67376/89202 Cft Surface Drain 0/19550 Rft Tiwana, District Khushab Sullage Carrier 0/10715 Rft Work is in progress. Latitude 32.250818333333335, Longitude 72.11242999999999

Date of AA 29.07.2017 Date of TS 5.9.2017 Date of award 08.12.2017 Date of Provision of Drainage System in MC completion 30.06.2020 RCC Sewer 882 2485 Khushab 49.831 16.993 3.333 3.333 2.500 2.460 98% 19.453 39% 6322/18305 Rft PCC Slab 43952/76862 Cft QuaidaAbad, District Khushab Surface Drain 0/3000 Rft work is in progrss. Latitude 32.34438, Longitude 71.87972833333333 Date of AA 29.07.2017 Date of TS 05.09.2017 Date of award 09.12.2017 Date Provision of Drainage System in UC Ukhli 883 2486 Khushab 18.025 9.998 2.675 2.675 2.006 2.000 100% 11.998 67% of completion 30.06.2019 PCC Slab Mohla, District Khushab 35774/54740 Cft work is in progress. Latitude 32.25557, Longitude 71.97306666666667 Date of AA 29.07.2017 Date of TS 04.09.2017 Date of award 09.12.2017 Date Construction of Drainage / Sewerage of completion 30.06.2020 RCC Sewer 884 2487 scheme, Rehman Colony, MC Hadhali, Khushab 32.000 9.999 3.333 3.333 2.500 2.460 98% 12.459 39% 7320/8700 Rft PCC Slab 13559/39304 Cft District Khushab Surface Drain 4401/6000 Rft Work is in progress. Latitude 32.25693833333333, Longitude 72.26121333333334 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA 29.07.2017 Date of TS 04.09.2017 Date of award 09.12.2017 Date Construction of Drainage / Sewerage of completion 30.06.2020 PCC Slab 885 2488 scheme, Zaman Colony, MC Hadhali, Khushab 30.000 10.000 3.333 3.333 2.500 2.496 100% 12.496 42% 27284/27284 Cft Surface Drain 513/5000 District Khushab Rft Sullage Carrier 1800/15540 Rft Work is in progress. Latitude 32.26454666666667, Longitude 72.26207833333333

Date of AA 29.7.2017 Date of TS 05.09.2017 Date of award 07.12.2017 Date Construction of PCC Derajat, UC Uttra, 886 2489 Khushab 20.000 9.998 3.333 3.333 2.500 2.460 98% 12.458 62% of completion 30.06.2019 PCC Slab District Khushab 54107/66532 Cft Surface Drain 0/1470 Rft Work is in progress. Latitude 32.31797166666667, Longitude 71.909465

Date of AA 29.07.2017 Date of TS 05.09.2017 Date of award 11.12.2017 Date Construction of PCC Slab, UC Gunjial, 887 2490 Khushab 30.000 9.929 3.333 3.333 2.500 2.446 98% 12.375 41% of completion 30.06.2020 RCC Sewer District Khushab 0/860 Rft Surface Drain 0/5000 Rft PCC Slab 33651/63069 Cft Work is in progrss. Latitude 32.34786, Longitude 71.89001

Date of AA 29.7.2017 Date of TS 05.09.2018 Date of award 11.12.2017 Date Construction of PCC Slab, UC 14 MB, 888 2491 Khushab 20.000 10.000 3.333 3.333 2.500 2.448 98% 12.448 62% of completion 30.06.2019 PCC Slab District Khushab 42293/66326 Cft Surface Drain 900/1600 Rft Work is in progress. Latitude 32.164885, Longitude 71.880985

Date of AA 16.10.2017 Date of TS 21.11.2017 Date of award 28.03.2018 Date Construction of Sewerage in, MC Mitha of completion 30.06.2020 PCC Slab 889 2492 Khushab 100.000 15.490 3.333 3.333 2.500 2.500 100% 17.990 18% 36505/78190 Cft Surface Drain 5662/18230 Twana, District Khushab Rft Sullage Carrier 400/29400 Rft work is in progress. Latitude 32.252444999999994, Longitude 72.10074833333333

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Remarks.RCC Pipe Sewer 9"i/d=1800- Arranged/2957, 12"i/d=2000- Provision of Sewerage and Sanitation at Arranged/2878, 15"i/d=109-Rft Laid & 750- Arranged/1175, 18"i/d=1043-Rft Laid/828, 890 2493 village Dhoranka City, UC Namal, District Mianwali 20.000 1.996 3.333 3.333 2.500 2.495 100% 4.491 22% 21"i/d= 921-Rft Laid/978, 24"i/d=511/942, Mianwali Surface Drain=0/430, PCC Slab=0/9035, Sullage Carrier (1.25'x1.5')=0/100, (1.50'x2')=0/500, (2.50'x4')=0/1400. Work is in progress.Latitude/Longitude: 32.95' / 71.55'

Date of A.A. 18-08-2017, Date of T.S. 13-11- 2017, Date of Start of Work 19-01-2018, Remarks. RCC Sewer=9" i/d=0/6890, 12"i/d= 482-Laid & 5214-Arranged/23310, 15"i/d= 6416-Arranged /6595, 18"i/d=2536- Provision of Integrated Sewerage Scheme Arranged/2590, 21"i/d=0/150, 24"i/d=700- 891 2494 Mianwali 75.000 11.995 3.333 3.333 4.918 4.918 100% 16.913 23% Rft Laid & 900-Arranged/1635, 27"i/d=1697 for Wan Bhachran Town, District Mianwali /1690, 30"i/d=1745/1740, 33"i/d=407/510, Surface Drain= 0/460, PCC Slab= 19714/98880, Sullage Carrier= 0/500, 0/150, Screening Chamber=0/1, P/Machinery=0/1, T/Line=0/1. Work is in progress.Latitude/Longitude:32.91' / 71.54' Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Remarks.RCC Pipe Sewer 9"i/d=0/980, Provision of Sewerage and Sanitation at 12"i/d=0/2532, 15"i/d=0/1418, 18"i/d=0/930, 892 2495 Mianwali 20.000 12.997 2.333 2.333 1.750 1.748 100% 14.745 74% Surface Drain=0/1040, PCC Slab= 62796 UC Mari, District Mianwali /28106, Sullage Carrier (1.25'x1.5')=0/430, (1.50'x2') =0/1850, (2.50'x4') =0/100 Work is in progress.Latitude/Longitude: 32.63' / 71.26'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Remarks.RCC Pipe Sewer 12"i/d=372- Provision of Sewerage and Sanitation at 893 2496 Mianwali 20.000 12.495 2.500 2.500 1.875 1.875 100% 14.370 72% Arranged/ 2393, 15"i/d=0/868, 18"i/d=0/636, UC Kalon Wala, District Mianwali Surface Drain=700/4535, Sullage Carrier=0/955, PCC Slab= 51624/33241, Brick Pavement=0/51000. Work is in progress.Latitude/Longitude: 32.90' / 71.24'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017-, Date of Start of Work 29-10-2017, Provision of Sewerage and Sanitation at Remarks. RCC Pipe Sewer 12"i/d=0/536, 894 2497 UC Manda Khel / Jalal Pur, District Mianwali 20.000 12.495 2.500 2.500 1.875 1.770 94% 14.265 71% 24"i/d=0/257, Surface Drain=491/3130, Mianwali Sullage Carrier=350/850, PCC Slab= 47720/56009. Work is in progress.Latitude/Longitude: 32.96' / 71.54'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Installation of Submersible Pumps in PP-43 895 2498 Mianwali 50.000 21.998 3.333 3.333 2.500 2.115 85% 24.113 48% Remarks. ERS=116/116, Trial Bore=06/11, , District Mianwali Tube Well = 28/58, Pumping Machinery= 28/58, G.S.Tank 500-Glns=0/58. Work is in progress.Latitude/Longitude: 32.85' / 71.56'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, PCC Slab / Drainage Scheme UC Kot 896 2499 Mianwali 20.000 12.499 2.500 2.500 1.875 1.874 100% 14.373 72% Remarks. PCC Slab= 53864/ 59483, Chandna, Tehsil Isa Khel, District Mianwali Surface Drain=1630/2900, Sullage Carrier=0/350 Work is in progress.Latitude/Longitude: 32.59' / 71.75'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Remarks. RCC Pipe Sewer 12"i/d= 785/1284, 24"i/d =280/330, Surface Drain= Urban sewerage drainage scheme Isa 897 2500 Mianwali 20.000 9.999 3.333 3.333 2.500 2.498 100% 12.497 62% 1261/4540, Sullage Carrier= 835/1335, Khel, District Mianwali PCC Slab= 25570/28996, Tuff Tiles= 3238 /3564, Replacement of Rising Main 8"i/d PE=2000/3335, 6"i/d PVC=0/60, 4"i/d PVC = 0/60, 3"i/d PVC= 0/660. Work is in progress.Latitude/Longitude:32.96' / 71.32'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, PCC Slab at U.C Khaglanwala, District Remarks. PCC Slab=44695 /53023, 898 2501 Mianwali 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Surface Drain=984/9255, Sullage Mianwali Carrier=150/150, RCC Sewer 12" = 318/335. Work is in progress.Latitude/Longitude: 32.90' / 71.24'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Remarks. PCC Slab= 52443 /63118, 899 2502 PCC Slab at U.C Vanjari, District Mianwali Mianwali 20.000 9.999 3.333 3.333 2.500 2.490 100% 12.489 62% Surface Drain=0/1055, Sullage Carrier=0/120. Work is in progress.Latitude/Longitude: 32.84' / 71.34' Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017. Remarks. PCC Slab= 41949/59804, 900 2503 PCC Slab at U.C Chapri, District Mianwali Mianwali 20.000 9.998 3.333 3.333 2.500 2.298 92% 12.296 61% Surface Drain= 0/4235, Sullage Carrier=0/600. Work is in progress.Latitude/Longitude: 32.84' / 71.21'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017 Date of Start of Work 29-10-2017, PCC Slab at U.C Paka Kamar Mushani, Remarks. RCC Pipe Sewer 12"i/d= 862 901 2504 Mianwali 20.000 6.999 3.333 3.333 2.500 2.490 100% 9.489 47% /1530, Surface Drain=0/1720, Sullage District Mianwali Carrier=400/400, PCC Slab=46458/57767. Work is in progress.Latitude/Longitude: 32.92' / 71.48'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Construction of PCC Slab & Drain Kala 902 2505 Mianwali 15.250 6.999 2.750 2.750 2.063 1.898 92% 8.897 58% Remarks. Surface Drain=0/7230, Sullage Bagh Lari Adda, District Mianwali Carrier=0/100, PCC Slab=24252/35699, Tuff Tiles=0/15800. Work is in progress.Latitude/Longitude: 32.40' / 71.68'

Date of A.A. 01-08-2017, (Rev)Date of T.S.08-03-2018, Date of Start of Work 29- 10-2017, Remarks. RCC Pipe Sewer 9"i/d= Sewerage and Sanitation for Paki Shah 0/938, 12"i/d=590/4320, 15"i/d=1314/1276, 903 2506 Mianwali 30.000 9.991 3.333 3.333 2.500 2.344 94% 12.335 41% 18"i/d= 2504/3950, 21"i/d=1812/1664, Mardan District Mianwali 24"i/d=1291/2062, Surface Drain=0/120, PCC Slab= 0/4600, Sullage Carrier= 350/1060. Work is in progress.Latitude/Longitude: 32.69' / 71.86'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, Remarks.RCC Pipe Sewer PCC Slab / Drainage Scheme UC vanjari, 904 2507 Mianwali 20.000 9.994 3.333 3.333 2.500 2.498 100% 12.492 62% 12"i/d=2062/2595, 15"i/d=480- Tehsil Isa Khel, District Mianwali Arranged/480, Surface Drain=0/4535, Sullage Carrier=0/955, PCC Slab= 35812/44680. Work is in progress.Latitude/Longitude: 32.71' / 71.26'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, PCC Slab / Drainage Scheme UC Pacca Remarks. RCC Pipe Sewer 12"i/d= 905 2508 Kama Mushani, Tehsil Isa Khel, District Mianwali 40.000 20.000 6.667 6.667 5.000 4.990 100% 24.990 62% 2550/2785, 15"i/d=0/660, Surface Mianwali Drain=0/1270, Sullage Carrier=0/350, PCC Slab= 85719/107505 Work is in progress.Latitude/Longitude: 32.84' / 71'.38'

Date of A.A. 01-08-2017, Date of T.S. 08-08- 2017, Date of Start of Work 29-10-2017, PCC Slab / Drainage Scheme UC Sultan 906 2509 Mianwali 20.000 9.996 3.333 3.333 2.500 2.490 100% 12.486 62% Remarks. PCC Slab= 42686/59297, Khel, Thesil Isa Khel, District Mianwali Surface Drain 0/5945, Sullage Carrier=0/200 Work is in progress.Latitude/Longitude: 32.88' / 71.29' Construction of Sewerage / Drainage Date of A.A 10.08.2017 Date of T.S scheme i/c PCC Pavement in Street village 13.09.2017 Date of Commencement 907 2510 Bhakkar 64.920 10.000 3.333 3.333 2.500 2.500 100% 12.500 19% 08.12.2017 Date of completion Hussasin Shah, Tehsil Darya Khan District 30.06.2020(Latitude 31.7876°/ Longitude Bhakkar 71.1092°) Construction of sullage carrier, surface drain, brick pavement, PCC Slab, RCC Date of A.A 10.08.2017 Date of T.S 18.08.2017 Date of Commencement 908 2511 Sewer and Disposal Station in Sara-e- Bhakkar 48.600 10.500 3.333 3.333 2.500 2.500 100% 13.000 27% 31.10.2017 Date of completion 30.06.2020 Mohajir, Chak No.250/TDA, District (Latitude 31.5020°/ Longitude 71.2369°) Bhakkar. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of sullage carrier, surface Date of A.A 10.08.2017 Date of T.S drain, brick pavement, PCC Slab, RCC 18.08.2017 Date of Commencement 909 2512 Bhakkar 48.600 15.500 3.333 3.333 2.500 2.500 100% 18.000 37% 02.11.2017 Date of completion Sewer and Disposal Station in Chak 30.06.2020(Latitude 31.5020°/ Longitude No.67/ML, District Bhakkar. 71.2369°)

Construction of sullage carrier, surface Date of A.A 10.08.2017 Date of T.S drain, brick pavement, PCC Slab, RCC 910 2513 Bhakkar 47.255 18.000 3.333 3.333 2.500 2.500 100% 20.500 43% 18.08.2017 Date of Commencement Sewer and Disposal Station in Sara-e- 31.10.2017 Date of completion 30.06.2020 Mohajir Chak No.71/ML, District Bhakkar. (Latitude 31.6333°/ Longitude 71.0666°)

Construction of sullage carrier, surface Date of A.A 10.08.2017 Date of T.S drain, brick pavement, PCC Slab, RCC 911 2514 Bhakkar 49.833 18.000 3.333 3.333 2.500 2.267 91% 20.267 41% 18.08.2017 Date of Commencement Sewer and Disposal Station at Adda Jahan 31.10.2017 Date of completion 30.06.2020 Khan, Chak No.45/TDA, District Bhakkar. (Latitude 31.6062°/ Longitude 71.0854°)

Date of A.A 10.08.2017 Date of T.S Rural sewerage, drainage, PCC Slab / brick 06.11.2017 Date of Commencement 912 2515 pavement scheme in UC Katchi Shahani, Bhakkar 57.023 17.500 3.333 3.333 1.700 1.700 100% 19.200 34% 31.10.2017 Date of completion Tehsil & District Bhakkar 30.06.2020(Latitude 31.63855°/Longitude 71.00538°) Rural sewerage, drainage, PCC Slab / brick Date of A.A 10.08.2017Date of T.S 06.11.2017 Date of Commencement 913 2516 pavement scheme in UC Sial, Tehsil & Bhakkar 59.573 20.000 3.333 3.333 2.500 2.500 100% 22.500 38% 13.12.2017 Date of completion 30.06.2020 District Bhakkar (Latitude 31.63855°/ Longitude 71.00538°)

PCC Slab/ Sewerage / Tuff tiles / RCC / "Date of A.A 10.08.2017 Date of T.S Pullian / and soling scheme UC Fazal, UC 914 2517 Bhakkar 30.000 10.000 6.667 6.667 5.000 5.000 100% 15.000 50% 18.18.2017 Date of Commencement Chak No. 40/ML UC Chak No. 63/DB, Tshil 31.10.2017 Date of completion 30.06.2019 Kallur Kot, District Bhakkar (Latitude 32.0762°/ Longitude 71.6021°) PCC Slab/ Sewerage / Tuff tiles / RCC / Date of A.A 10.08.2017 Date of T.S Pullian / and soling scheme UC Dali 18.08.2017 Date of Commencement 915 2518 Namdar UC Ghulaman No.1, UC Bhakkar 40.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 44% 31.10.2017 Date of completion Ghulaman No.2, Tehsil Kallur Kot, District 30.06.2020(Latitude 32.1575°/ Longitude 71.2696°) Bhakkar

PCC Slab/ Sewerage / Tuff tiles / RCC / Date of A.A 10.08.2017 Date of T.S Pullian / and soling scheme UC Haitthu, UC 916 2519 Bhakkar 50.000 18.000 3.333 3.333 2.500 2.500 100% 20.500 41% 18.08.2017 Date of Commencement Kalul, UC Maibal, UC Kanjan and UC Noon 31.10.2017 Date of completion 30.06.2020 Dagar, Tehsil Kallur Kot, District Bhakkar (Latitude 32.1575°/ Longitude 71.2696°)

Provision of PCC Pavement / Slab, Date of A.A 10.08.2017 Date of T.S Sewerage, Culverts and Soling in UC 18.08.2017 Date of Commencement 917 2520 Bhakkar 46.563 23.500 3.333 3.333 1.700 1.700 100% 25.200 54% 31.10.2017 Date of completion Khaawar kala, Majoka, Lak Kalan, tehsil 30.06.2020(Latitude 31.7945°/ Longitude Darya Khan District Bhakkar 71.1079°) Provision of PCC Pavement / Slab, Sewerage, Culverts and Soling in UC Date of A.A 10.08.2017 Date of T.S 18.08.2017 Date of Commencement 918 2521 Dullaywala Rural, Jhammat Shumali, Bhakkar 46.904 20.000 3.333 3.333 2.500 2.500 100% 22.500 48% 31.10.2017 Date of completion 30.06.2020 Barranga, Tehsil Darya Khan District (Latitude 31.8427°/ Longitude 71.4359°) Bhakkar

Provision of PCC Pavement / Slab, Date of A.A 10.08.2017 Date of T.S Sewerage, Culverts and Soling in UC 919 2522 Bhakkar 36.304 15.000 3.333 3.333 1.780 1.780 100% 16.780 46% 18.08.2017 Date of Commencement Daggar Qureshi, Wahwara, Barkatwala, 31.10.2017 Date of completion 30.06.2020 Tehsil Darya Khan District Bhakkar. (Latitude 31.7876°/ Longitude 71.1092°)

Provision of PCC Pavement / Slab, "Date of A.A10.08.2017 Date of T.S Sewerage, Culverts and Soling in UC 920 2523 Bhakkar 49.827 10.000 3.333 3.333 1.160 1.160 100% 11.160 22% 18.08.2017 Date of Commencement Angra Daggar, Chak No 6/TDA, Gadai 31.10.2017 Date of completion 30.06.2020 Tehsil Darya Khan District Bhakkar. (Latitude 31.7876°/Longitude 71.1092°) Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Provision of PCC Pavement / Slab, Date of A.A 10.08.2017 Date of T.S Sewerage, Culverts and Soling in UC 921 2524 Bhakkar 32.268 10.000 3.333 3.333 2.500 2.500 100% 12.500 39% 18.08.2017 Date of Commencement Punjigrain Daggar and Nasheb, Tehsil 31.10.2017 Date of completion 30.06.2020 Darya Khan District Bhakkar. (Latitude 31.7876°/ Longitude 71.1092°)

Construction of Sewerage / Drainage Date of A.A 10.08.2017 Date of T.S scheme i/c PCC Pavement in Street village 922 2525 Bhakkar 15.040 8.495 2.180 2.180 1.635 1.635 100% 10.130 67% 18.08.2017 Date of Commencement Sukha Shah, Tehsil Darya Khan District 03.11.2017 Date of completion 30.06.2019 Bhakkar (Latitude 31.7876°/ Longitude 71.1092°) Date of A.A 10.08.2017 Date of T.S Construction of Sewerage / Drainage 18.18.2017 Date of Commencement 923 2526 scheme Baranga Tehsil Darya Khan, Bhakkar 49.760 15.000 3.333 3.333 2.500 2.500 100% 17.500 35% 02.11.2017 Date of completion District Bhakkar 30.06.2020(Latitude 31.8427°/ Longitude 71.4359°) Construction of Sewerage / Drainage Date of A.A 10.08.2017 Date of T.S scheme i/c PCC Pavement in Street village 18.18.2017Date of Commencement 924 2527 Bhakkar 27.650 10.000 3.333 3.333 2.500 2.500 100% 12.500 45% 31.10.2017 Date of completion Londi Nasheeb, Tehsil Darya Khan, District 30.06.2020(Latitude 31.7876°/Longitude Bhakkar 71.1092°) Date of A.A 10.08.2017 Date of T.S Rural Drainage scheme UC Goharwala and 925 2528 Bhakkar 28.345 15.000 4.448 4.448 3.336 3.336 100% 18.336 65% 18.08.2017 Date of Commencement Khansar., District Bhakkar 03.11.2017 Date of completion 30.06.2019 (Latitude 31.6617°/Longitude 71.3290°)

Construction of sewerage / Drainage Date of A.A 10.08.2017 Date of T.S 18.08.2017 Date of Commencement 926 2529 scheme in Chak No. 49/TDA Tehsil and Bhakkar 36.766 10.000 3.333 3.333 2.500 2.500 100% 12.500 34% 02.11.2017 Date of completion 30.06.2020 District Bhakkar (Latitude 31.5526°/ Longitude 71.1716°)

Construction of sewerage / Drainage Date of A.A 10.08.2017 Date of T.S 18.08.2017 Date of Commencement 927 2530 scheme in Chak No. 47/TDA Tehsil and Bhakkar 45.685 5.000 3.333 3.333 2.500 2.500 100% 7.500 16% 02.11.2017 Date of completion 30.06.2020 District Bhakkar (Latitude 31.5526°/ Longitude 71.1716°)

Extension of Sewerage / Drainage Scheme Date of A.A 10.08.2017 Date of T.S and PCC pavement in left over streets 928 2531 Bhakkar 50.000 22.499 3.333 3.333 2.500 2.500 100% 24.999 50% 18.08.2017 Date of Commencement Darya Khan City, Tehsil Darya Khan District 31.10.2017 Date of completion 30.06.2020 Bhakkar. (Latitude 31.7876°/ Longitude 71.1092°) Date of A.A 10.08.2017 Date of T.S Sewerage scheme Kotla Jam, Tehsil & 929 2532 Bhakkar 48.611 4.000 3.333 3.333 2.200 2.125 97% 6.125 13% 18.08.2017 Date of Commencement District Bhakkar 31.10.2017 Date of completion 30.06.2020 (Latitude 31.7002°/ Longitude 71.0943°)

PCC Slab and Sewerage scheme MC Date of A.A 10.08.2017 Date of T.S 18.08.2017 Date of Commencement 930 2533 jandanwala, Tehsil Kallut Kot, District Bhakkar 30.000 10.000 3.333 3.333 1.100 1.100 100% 11.100 37% 31.10.2017 Date of completion 30.06.2020 Bhakkar (Latitude 32.0762°/ Longitude 71.6021°)

Date of A.A 10.08.2017 Date of T.S PCC Slab and Sewerage scheme MC 931 2534 Bhakkar 50.000 21.500 3.333 3.333 2.500 2.500 100% 24.000 48% 18.08.2017 Date of Commencement Kallut Kot, District Bhakkar 31.10.2017 Date of completion 30.06.2020 (Latitude 32.1575°/ Longitude 71.2696°)

Date of A.A =29-09-2017. Date of T.S=.05- 09-2017. No. of Beneficiaries= UC Construction of PCC, Soling & drains Anticipated date of completion=01.01.2018 schemes in Chak No.409 GB, 420 GB, 410 932 2535 Faisalabad 15.500 10.000 1.833 1.833 1.375 1.170 85% 11.170 72% Investigation of source= Drainage • Surface GB, 405 GB, 407 GB, 424 GB District Drain =3284/ 11570 Rft • Sullage Carrier =1100/1100 Rft • Brick Pavment Faisalabad =40807/46426 Cft • PCC =0/4620 Cft • Work in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A =29-09-2017. Date of T.S.=05- 09-2017. No. of Beneficiaries= UC Construction of PCC, Soling & drains Anticipated date of completion=01.01.2018 schemes in Chak No. 430 GB, 422GB, 423 933 2536 Faisalabad 12.500 7.000 1.833 1.833 1.375 1.371 100% 8.371 67% Investigation of source= Drainage • Surface GB, 427 GB, 428 GB, 425 GB, 404 GB Drain =4801/10440 Rft • Sullage Carrier =700/1780 Rft • Brick Pavment District Faisalabad =39238/33084 Cft • PCC =3408/2373 Cft • Work in progress

Construction of PCC, soling & drainage and Date of A.A= 29-09-2017. Date of T.S.=16- 09-2017. No. of Beneficiaries= Anticipated boundary walls of graveyards in Pindi date of completion=01.01.2018 934 2537 Sheikh Musa, Mobarik Pura, Chak No.451 Faisalabad 17.000 5.889 2.333 2.333 1.750 1.744 100% 7.633 45% Investigation of source= Drainage • Surface GB, 429 GB, 400 GB, 408 GB & Nazir Drain =4809/14000 Rft • Sullage Carrier =0/ 600 Rft • Brick Pavment =29625/ 550574 Colony District Faisalabad Cft • PCC =0/2601 Cft • Work in progress

Date of A.A 04-12-2017. Date of T.S.15-03- 2018. No. of Baeneficiaries= 392511 Rural Drainage Scheme of Villages in NA- Anticipated Date of Completion=14/03/2019 935 2538 Faisalabad 150.000 39.926 6.667 6.667 5.000 4.965 99% 44.891 30% Surface Drain=16517 /117720 Rft Sullage 76 Carrier = 3264/22650 Rft Brick Pavement= 132589/309254 Cft PCC= 23419/38740 Cft Work is in progress.

Date of A.A 29-08-2017. Date of T.S.19-01- 2018. No. of Baeneficiaries= 16837 Construction of Rural Drainage and PCC Anticipated Date of Completion=18/01/2019 936 2539 Faisalabad 15.000 5.000 3.333 3.333 2.500 2.190 88% 7.190 48% Surface Drain=0 /11680 Rft Sullage Carrier Road UC 30, 194/RB, District Faisalabad = 1885/2325 Rft Brick Pavement= 8456/12849 Cft PCC= 11018/15069 Cft Work is in progress.

Date of A.A 29-08-2017. Date of T.S.19-01- 2018. No. of Baeneficiaries= 13375 Construction of Rural Drainage and PCC Anticipated Date of Completion=18/01/2019 937 2540 Faisalabad 15.000 5.000 3.333 3.333 2.500 2.140 86% 7.140 48% Surface Drain=2198 /15950 Rft Sullage Road ,UC 60 District Faisalabad Carrier = 1285/3300 Rft Brick Pavement= 12451/24898 Cft PCC= 0/0 Cft Work is in progress.

Date of A.A 05-08-2017. Date of T.S.19-01- 2018. No. of Baeneficiaries= 21874 Construction of Rural Drainage and PCC 938 2541 Faisalabad 15.000 5.000 3.333 3.333 2.500 2.120 85% 7.120 47% Anticipated Date of Completion=18/01/2019 Road , UC 71 District Faisalabad Surface Drain=0 /8170 Rft Sullage Carrier = 0/5100 Rft Brick Pavement= 27260/33888 Cft PCC= 0/0 Cft Work is in progress.

Date of A.A 05-08-2017. Date of T.S.19-01- 2018. No. of Baeneficiaries= 13060 Construction of Rural Drainage and PCC Anticipated Date of Completion=18/01/2019 939 2542 Faisalabad 15.000 3.495 2.667 2.667 2.000 1.700 85% 5.195 35% Surface Drain=412 /13200 Rft Sullage Road at U.C. 62 District Faisalabad Carrier = 355/3700 Rft Brick Pavement= 15244/29994 Cft PCC= 0/0 Cft Work is in progress.

Date of A.A 29-08-2017. Date of T.S.19-01- 2018. No. of Baeneficiaries= 17639 Construction of Rural Drainage and PCC Anticipated Date of Completion=18/01/2019 940 2543 Faisalabad 15.000 2.049 1.667 1.667 1.250 1.100 88% 3.149 21% Surface Drain=0 /14490 Rft Sullage Carrier Road at U.C. 65 District Faisalabad = 0/1200 Rft Brick Pavement= 4331/27955 Cft PCC= 6118/6447 Cft Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 29-08-2017. Date of T.S.19-01- 2018. No. of Baeneficiaries= 16249 Construction of Rural Drainage and PCC Anticipated Date of Completion=18/01/2019 941 2544 Faisalabad 15.000 4.928 1.667 1.667 1.250 1.070 86% 5.998 40% Surface Drain=705 /9060 Rft Sullage Road at U.C. 67 District Faisalabad Carrier = 0/7250 Rft Brick Pavement= 25321/19292 Cft PCC= 0/0 Cft Work is in progress.

Date of A.A= 27-10-2017. Date of T.S.=28- 10-2017. No. of Beneficiaries= UC Anticipated date of completion=01.01.2018 Provision of Sewerage/ Drainage Facilities Investigation of source= Drainage • Surface 942 2545 in PP-57, District Faisalabad Faisalabad 50.000 19.297 3.333 3.333 2.500 2.115 85% 21.412 43% Drain I &II =13171/35121 -Rft • Sullage Carrier 1.5x2 =3500/2900-Rft • Sullage Carrier 2x2 =0/ 6000-Rft • Brick Pavment =60922/ 117428 Cft • PCC =1985/5421 Cft • Work in progress

Date of A.A 29-08-2017. Date of T.S.05-09- 2017. Work order issued on 19-01-2018. Work is in progress. Funds released on 03.08.2018 & 24.1.19. Population = RCC Rural Drainage Scheme for Muncipal 943 2546 Faisalabad 49.888 29.937 3.333 3.333 2.500 2.453 98% 32.390 65% Sewer 9"i/d. =1933/6975-Rft 12"i/d committee Samundri District Faisalabad =392/828-Rft S/Drain Tuype-I =5148/19518- Rft Type-II =0/660-Rft B/Pavement =79831/62288-Cft Resoling =0/15186-Cft PCC =32103/27989 Cft S/Carrier =1823/6690-Rft

Date of A.A 29-08-2017. Date of T.S.05-09- 2017. Work order issued on 19-01-2018. Work is in progress. Funds released on Rural Drainage Scheme for Samundri 944 2547 Faisalabad 50.000 20.000 3.333 3.333 2.500 2.120 85% 22.120 44% 03.08.2018 & 24.1.19. S/Drain Type-I District Faisalabad =20873/41050-Rft Type-II =2665/6005-Rft B/Pavement =62250/122471-Cft Resoling=12132/72491-Cft Sullage Carrier=0/50-Rft

Date of A.A =29-08-2017. Date of T.S.=05- 09-2017. No. of Beneficiaries= 31650 Rural Drainage Scheme at Chak No. Anticipated date of completion=31.10.2018 Investigation of source= Drainage • Surface 945 2548 263/RB, Dijkot Town Committee Tehsil Faisalabad 30.000 10.000 3.333 3.333 2.500 2.115 85% 12.115 40% Drain I & II =1121/27552 Rft • Sullage ,District Faisalabad Carrier =1700/1740 Rft • Brick Pavment =52593/74008 Cft • PCC =333/10268 Cft • Work in progress

AA Issued on 05-08-2017date of T.S 16-09- 2017 .Work Order issued on 31-10- 2017work is in Progress .Fund Released on 03-08-2018 & 24-01-2019 Population =8811- Rural Water Supply Scheme chak No. Persons T/Well 0.50 Cusec= 2/2 No Pump 946 2549 203\GB Tehsil Samundari District Faisalabad 23.880 10.000 4.627 4.627 3.470 3.470 100% 13.470 56% House 12x12 = 0/2 No Pump Machinery = Faisalabad 0/2 Set Rising Main 8"/id = 14945/19950 Rft 6"/id =0/500 Rft Distribotion system 3"/id =12115/11870 Rft 4"/id = 1749/1650 Rft 6"/id = 3100/3310 Rft Electric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No.

AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018& 24-01-2019 Population =7103- Rural Water supply Scheme chak no. Persons T/Well 0.25 Cusec= 2/2 No Pump 947 2550 199\GB Tehsil Samundari District Faisalabad 13.434 10.000 1.145 1.145 0.859 0.859 100% 10.859 81% House 12x12 = 15%/2 No Pump Machinery Faisalabad = 2/2 Set Rising Main 6"/id = 7870/7950 Rft 4"id = 840/700 Rft Distribotion system 3"/id =8095/8220 Rft 4"/id = 2670/2750 Rft 6"/id = 515/550 RftElectric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018& 24-01-2019 Population =7103- Rural Water supply Scheme chak no. Persons T/Well 0.50 Cusec= 1/1 No Pump 948 2551 208\GB Tehsil Samundari District Faisalabad 20.359 10.000 3.453 3.453 2.590 2.225 86% 12.225 60% House 12x12 = 1/- NoPump Machinery = 1/- Faisalabad Set Rising Main 6"/id = 29340/21745 Rft6"d- class =-/1940 Rft Distribotion system 3"/id =6505/- Rft 4"/id = 1100/- Rft 6"/id = 1100/- Rft Electric trasmitin = 1/- -JobHypo chlorinator = 1/- No.

Date of A.A 02-10-2017. Date of T.S.01-03- 2018. No. of Baeneficiaries= 173265 Anticipated Date of Completion=28/2/2019 PCC / Seewrage etc. Scheme Jaranwala 949 2552 Faisalabad 100.000 20.877 6.667 6.667 5.000 4.225 85% 25.102 25% Surface Drain=5561 /40860 Rft Sullage City in NA-76 Carrier = 0/4500 Rft Brick Pavement= 0/21258 Cft pcc= 57403/168268 Cft RCC SEWER 9"-12"= 1861/2550 Rft Work is in progress.

Date of A.A= 09-10-2017. Date of T.S.=02- Provision of Solling / Nalian / Drainage in 11-2017. No. of Beneficiaries= Anticipated Tandlianwala City , Mamu kanjan City, UC's date of completion= 01.06.2018 76,77,78,79,80,81,82,83,84,85,86,87, 88, Investigation of source= drainage • Surface 950 2553 Faisalabad 126.000 24.631 6.667 6.667 5.000 5.000 100% 29.631 24% Drain I &II =11504/74758-Rft • Sullage 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, Carrier 1.5x2 =1080/12040-Rft • Sullage 100, 101, 102, 103, 104, Tehsil Carrier 2x2 =1150/2430-Rft • Brick Pavment Tandlianwala District Faisalabad =108388/419393 Cft • PCC =4415/ 27167 Cft • Work in progress

AA Issued on 05-08-2017 date of T.S 16-09- 2017. Work Order issued on 31-10-2017 work is in Progress . Fund Released on 03- 08-2018 & 24-01-2019 Population=3941- Rural Water supply Scheme chak no. Persons Tube Well = 2/2 NoPump House 951 2554 209\GB Tehsil Samundari District Faisalabad 19.412 10.000 3.137 3.137 2.353 2.080 88% 12.080 62% 12x12 = 0/2 No Pump Machinery = 2/2 Set. Faisalabad Rising Main 6"/id = 15845/20650 Rft 4"id = 0/500 Rft. Distribotion system 3"/id =3875/6685 Rft 4"/id = 0/1100 Rft 6"/id = 1025/1100 Rft .Electric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No.

AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018 & 24-01-2019 Population=4706- Rural Water supply Scheme chak no. Persons Tube Well 0.25 Cusec= 2/2 No Pump House 12x12 = 0/2 No Pump 952 2555 212\GB Tehsil Samundari District Faisalabad 12.439 10.000 0.813 0.813 0.610 0.520 85% 10.520 85% Machinery = 2/2 Set Rising Main 6"/id = Faisalabad 5260/4150 Rft 4"id = 0/600 Rft Distribotion system 3"/id =11940/12120 Rft 4"/id = 3955/3300 Rft 6"/id = 1030/1200 Rft Electric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No.

AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018 & 24-01-2019 Population=3597- Rural Water supply Scheme chak no. Persons Tube Well 0.50 - Cusec= 1/1 No 953 2556 207\GB Tehsil Samundari District Faisalabad 26.341 10.000 3.333 3.333 2.500 2.125 85% 12.125 46% Pump House 12x12 = 0/1 No Pump Faisalabad Machinery = 0/1Set Rising Main 6"/id = 22532/30170 Rft Distribotion system 3"/id =0/15005 Rft 4"/id = 0/2100 Rft 6"/id = 0/550 Rft Electric trasmitin = 0/1 -Job Hypo chlorinator = 0/1- No. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018 & 24-01-2019 Population=5424- Rural Water supply Scheme chak no. Persons Tube Well = 2/2 No Pump House 954 2557 211\GB Tehsil Samundari District Faisalabad 11.338 6.000 1.779 1.779 1.334 1.130 85% 7.130 63% 12x12 = 0/2 No Pump Machinery = 2/2 Set Faisalabad Rising Main 6"/id = 2325/2750 Rft 4"id = 0/600 Rft Distribotion system 3"/id =7050/10320 Rft 4"/id = 0/2550 Rft 6"/id = 0/1100 Rft Electric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No.

AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018 & 24-01-2019 Population=5261- Rural Water supply Scheme chak no. Persons Tube Well = 2/2 No Pump House 955 2558 202\GB Tehsil Samundari District Faisalabad 12.378 6.000 2.126 2.126 1.595 1.360 85% 7.360 59% 12x12 = 0/2 No Pump Machinery = 2/2 Set Faisalabad Rising Main 6"/id = 3930/5450 Rft 4"id = 0/600 Rft Distribotion system 3"/id =4675/8250 Rft 4"/id = 0/3195 Rft 6"/id = 0/1100 Rft Electric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No.

AA Issued on 05-08-2017 date of T.S 16-09- 2017 Work Order issued on 31-10-2017 work is in Progress Fund Released on 03- 08-2018& 24-01-2019 Population =7103- Rural Water supply Scheme chak no. Persons T/Well 0.25 Cusec= 2/2 No Pump 956 2559 200\GB Tehsil Samundari District Faisalabad 11.850 6.000 1.950 1.950 1.463 1.250 85% 7.250 61% House 12x12 = 15%/2 No Pump Machinery Faisalabad = 2/2 Set Rising Main 6"/id = 7870/7950 Rft 4"id = 840/700 Rft Distribotion system 3"/id =8095/8220 Rft 4"/id = 2670/2750 Rft 6"/id = 515/550 Rft Electric trasmitin = 0/2 -Job Hypo chlorinator = 0/2- No.

Date of A.A =05-08-2017. Date of T.S. =16- 09-2017. No. of Beneficiaries= 9305 . Anticipated date of completion=31.10.2018.Investigation of source=2/2• Tube well =2/ 2-No.• Pump Construction of Soling, Nallian, Pullian, house=0/ 2-No.• Pumping Machinery =0/2- Set• Intermediate Station=0/ 1-Set• Rising 957 2560 Nallah and Water Supply at Chak No. 5 GB Faisalabad 37.222 15.000 3.333 3.333 2.500 2.125 85% 17.125 46% main 6” i/d =400/ 500 Rft• 8” i/d Kamal Pur UC 168 in District Faisalabad =24639/28500 Rft• D/System 3” i/d=0/21080 Rft• 4” i/d =0/3240 Rft • 6” i/d =0/ 1490 Rft• 8” i/d =0/ 1360 Rft• Hypo Chlorinator =0/ 2-No• Staff Quarter=0/ 1- No• Transmission line=0/3-NO• Sullage Carrier = 0/466-Rft • Work in progress

Date of A.A =05-08-2017.Date of T.S.=16- 09-2017. No. of Beneficiaries= 7029. Anticipated date of completion=31.10.2018.Investigation of source=2/2• Tube well=2/2-No.• Pump Construction of Soling, Nallian, Pullian, house =2/2-No.• Pumping Machinery=0/ 2- Set• Rising main 6” i/d=701/500 Rft• 8” 958 2561 Nallah and Water Supply at Chak No. 52 Faisalabad 22.692 10.000 4.231 4.231 3.173 2.890 91% 12.890 57% i/d=3975/6200 Rft• D/System 3” GB malal Pur UC 166 in District Faisalabad i/d=19588/22410 Rft• 4” i/d=3487/ 4300 Rft• 6” i/d=2604/2450 Rft• 8” i/d=0/710 Rft• Hypo Chlorinator=0/ 2-No• OHR =0/1-No• Transmission line=0/ 2-NO• Surface Drain=0/ 500 Rft • Brick Pavment =0/ 2730 Rft • Work in progress

AA issued on 05.08.2017. Date of T.S 16.09.2017 Work order issued on Construction of PCC different streets UC-4 959 2562 Faisalabad 40.000 18.000 1.000 1.000 0.750 0.700 93% 18.700 47% 23.11.2018. Work is in progress. Funds UC-6 UC-7 UC-8 in District Faisalabad released on 12.06.2018 & 24.1.19. Drain Type 1 14370/1550 Rft ,PCC 97445 Cft/27950 Cft, No of beneficiaries 45830 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) AA issued on 05.08.2017. Date of T.S 16.09.2017 Work order issued on 13.06.2018. Work is in progress. Funds Construction of PCC different streets UC-9 960 2563 Faisalabad 30.000 15.000 1.000 1.000 0.750 0.650 87% 15.650 52% released on 23.11.2018 & 24.1.19. Drain UC-10 UC-11UC-12 in District Faisalabad Type 1 8812 Rft/1860 Rft,Brick Pavement 74565 Cft/ 26126Cft Sullage Carrier(1.5'X2') 230Rft/Nil No of Beneficiaries 45830 Persons AA issued on 05.08.2017. Date of T.S 16.09.2017 Work order issued on Construction of PCC different streets UC- 12.06.2018. Work is in progress. Funds 961 2564 Faisalabad 20.000 10.000 1.000 1.000 0.750 0.650 87% 10.650 53% released on 23.11.2018 & 24.1.19. Drain 14 UC-15 UC-17 in District Faisalabad Type 17540Rft/850Rft, PCC 47119Cft/21170Cft No of Benificiaries 16638 Persons Date of A.A =02-10-2017. Date of T.S.=01- 11-2017. No. of Beneficiaries= Abadies , Construction of PCC Streets in District 962 2565 Faisalabad 75.000 25.000 6.667 6.667 5.000 4.225 85% 29.225 39% town Anticipated date of Faisalabad completion=08.02.2019 Investigation of source=PCC . PCC in Streets =79365/202570-Cft • Work in progress Date of A.A 05-08-2017. Date of T.S.31-10- 2017. No. of Baeneficiaries= 22250 Anticipated Date of Completion=30/10/2018 Sewerage Sheme in 240GB and additional 963 2566 Faisalabad 30.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 75% Surface Drain=10244 /21790 Rft Sullage Abadies Carrier = 0/1650 Rft Brick Pavement= 0/23514 Cft pcc= 59003/27622 Cft RCC SEWER 9"-12"= 0/2890 Rft Work is in progress.

Date of A.A 05-08-2017. Date of T.S.31-10- 2017. No. of Baeneficiaries= 136293 Provision of PCC / Sewerage / Drainage / Anticipated Date of Completion=30/10/2018 964 2567 Tuff Tile and etc in PP-53, District Faisalabad 50.000 25.000 3.333 3.333 2.500 2.498 100% 27.498 55% Surface Drain=6614 /31160 Rft Sullage Faisalabad Carrier = 2341/11530 Rft Brick Pavement= 102207/129431 Cft PCC= 7065/2119 Cft Work is in progress.

Date of A.A 19-09-2017.Date of T.S.20-11- 2017. No. of Beneficiaries= 8- Villages.Anticipated date of completion=01.02.2019.Investigation of source= 10/10 •Tube well=10/10-No.• Pump house=50%/ 10-No.• Pumping Machinery Water Supply Schemes in Constitutency 965 2568 Faisalabad 122.000 35.000 6.667 6.667 5.000 4.270 85% 39.270 32% =10/10-Set• Intermediate Station =0/ 1-Set• NA-80, District Faisalabad Rising main 6” i/d=28310/42850 Rft• 8” i/d =9507/10500 Rft• D/System 3” i/d =14531/ 168655 Rft• 4” i/d =2851/12585 Rft • 6” i/d =992/3760 Rft• 8” i/d=5313/6000 Rft• Hypo Chlorinator =0/10-No• Staff Quarter =50%/6- No• Transmission line =0/11-NO • Work in progress

Date of A.A 02-10-2017. Date of T.S.17-11- Provision of Installation of New Water Plant 2017. No. of Beneficiaries= Town 966 2569 Faisalabad 75.000 34.862 6.667 6.667 5.000 4.290 86% 39.152 52% Anticipated date of completion=03.03.2019 in District Faisalabad Investigation of source= • RO Water filtration Plant =8/13-No. • Work in progress

Date of A.A = 01.08.2017 • Date of TS = 06.09.2017 • No. of Beneficiaries = 17763- Soling / Drains / Culverts / PCC Slabs / UC Persons • Anticipated date of completion = 967 2570 Jhang 13.000 6.996 2.000 2.000 1.500 1.500 100% 8.496 65% 30.06.2020.Surface Drain 1664/1970- No.1 to UC No.8 Tehsil & District Jhang Rft.Brick Pavement 46658/70223-Cft Sullage Carrier 590-Rft Road Culverts 4- Nos.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A = 01.08.2017 • Date of TS = 06.09.2017 • No. of Beneficiaries = 5194- Persons • Anticipated date of completion = Drainage Scheme Chak no. 479/JB District 968 2571 Jhang 16.749 6.991 3.250 3.250 2.438 2.438 100% 9.429 56% 30.06.2020Surface Drain 9921/24270- Jhang. Rft.Brick Pavement 15683/33780- CftOxidation Pond 1-No.Sullage Carrier 1416/2000-Rft.Road Culvert 3/4-Nos.Work in progress. Date of A.A = 01.08.2017.Date of TS = 06.09.2017.No. of Beneficiaries = 6314- Drainage Scheme Chak no. 482/JB District Persons.Anticipated date of completion = 969 2572 Jhang 20.489 4.982 3.333 3.333 2.500 2.500 100% 7.482 37% 30.06.2020.Surface Drain 5307/22630- Jhang. Rft.Brick Pavement 28889/61281- Cft.Sullage Carrier 100/2100-Rft.Work in progress. Date of A.A = 01.08.2017 • Date of TS = 06.09.2017 • No. of Beneficiaries = 13184- Drainage Scheme Chak no. 493/JB District Persons • Anticipated date of completion = 970 2573 Jhang 30.614 11.999 3.333 3.333 2.500 2.500 100% 14.499 47% 30.06.2020Surface Drain 7238/35720- Jhang. RftSullage Carrier 6556/7623-Rft Brick Pavement 23443/65010-Cft Pond 1- No.Work in progress.

Date of A.A = 01.08.2017 • Date of TS = 06.09.2017 • No. of Beneficiaries = 12796- Construction of Soling, Drains, PCC and Persons • Anticipated date of completion = 971 2574 Sullage at Sammunduana, Tehsil Ahmad Jhang 14.354 9.855 1.451 1.451 1.088 1.088 100% 10.943 76% 30.06.2020.Surface Drain 6092/11151- Pur Sial District Jhang. Rft.Sullage Carrier 1450/4550-Rft.Brick Pavement 39491/7462-Cft .PCC 5077/18298-Cft Work in progress.

Date of A.A = 01.08.2017 • Date of TS = 13.09.2017.No. of Beneficiaries = 438230- Rural Drainage Scheme at Different Persons Anticipated date of completion = 972 2575 Jhang 40.000 19.996 3.333 3.333 2.500 2.500 100% 22.496 56% 30.06.2020.Surface Drain 364/8785-Rft Villages, 18 Hazari, in District Jhang Brick Pavement 123667/212319-Cft Sullage Carrier 44/1880-Rft P.C.C.1000-Sft.Road Culverts 1-No. Work in progress. Date of A.A = 01.08.2017 Date of TS = 13.09.2017 • No. of Beneficiaries = 3992- Water Supply Scheme Chak No. 412 Persons • Anticipated date of completion = Cheemia Wali, Tehsil Shorkot, District 30.06.2020.Survey & Investigation Trail Boring 2/2-Job.Tube Well 0.50 Cusec 2/2- 973 2576 Jhang and Construction of Tank for Water Jhang 20.303 9.990 3.434 3.434 2.576 2.576 100% 12.566 62% Nos.Pump House 2/2-Nos.Pumping Supply Scheme Chak No. 412 Cheemia Machinery2-Set Hypoclorinator 2-SetRising Wali. Main 18402/16800Rft.DistributionSystem16668/2 3345-Rft.Work in progress.

Date of A.A = 01.08.2017 • Date of TS = 13.09.2017 • No. of Beneficiaries = 4504- Persons • Anticipated date of completion = Provision of Water Supply at Chak No. 498 30.06.2020Survey & Investigation Trail 974 2577 Jhang 22.000 9.993 4.000 4.000 3.000 3.000 100% 12.993 59% Boring 2/2-Job.Tube Well 0.50 Cusec 2/2- Tehsil Shorkot, District Jhang. Nos.Pump House 2/2-Nos. Pumping Machinery 2-Set Hypoclorinator 2-Set Rising Main 8757/16600-Rft Distribution System40216/45300-Rft Work in progress.

Date of A.A = 01.08.2017 • Date of TS = 06.09.2017 • No. of Beneficiaries = 18520- Provision of Sewerage & drainage At UC- 975 2578 Jhang 15.000 6.899 2.667 2.667 2.000 2.000 100% 8.899 59% Persons • Anticipated date of completion = 46 Rustam Sargana Tehsil shorkot. 30.06.2020Surface Drain 8602/13055- RftBrick Pavement 22316/47538-CftSullage Carrier 600/1500-RftWork in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A = 19.09.2017 • Date of TS = 09.10..2017 • No. of Beneficiaries = 37324- Persons • Anticipated date of completion = Sewerage / Drainage Scheme for Tehsil 30.06.2021.R. C. C. Sewer 9" i/d 976 2579 Headquartar Ahmad Pur Sial District Jhang Jhang 100.000 39.962 6.667 6.667 5.000 5.000 100% 44.962 45% 6102/12921-Rft.12" I/d 954/2638-Rft 15" i/d Phase-2. 612/4200-Rft.Surface Drain 575-Rft.Sullage Carrier 1000-Rft Tuff Tile119506/492100-Sft Brick Pavement 4409/4732-Cft Work in progress. Date of A.A = 19.09.2017 • Date of TS = 28.09.2017 • No. of Beneficiaries = 32735- Hazrat Peer Abdur rehman Sewerage Persons • Anticipated date of completion = 977 2580 Jhang 70.000 24.580 6.667 6.667 5.000 5.000 100% 29.580 42% 30.06.2020 Surface Drain 12760/52690-Rft Scheme District Jhang. Sullage Carrier 7390/14830-Rft Brick Pavement/PCC 38516/98514-Cft Work in progress. Date of A.A = 18.10.2017 Date of TS = 31.10.2017.No. of Beneficiaries = 438230- Provision of 16 nos. Water Filtration Plants 978 2581 Jhang 40.000 0.600 3.333 3.333 2.500 2.500 100% 3.100 8% Persons Anticipated date of completion = in Tehsil 18 Hazari, District Jhang. 30.06.2021Ultra Filtration Plant 1/12- Nos.Reverse Osmosis Plant 2-Nos.Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary Provision of Drainage and Soling and Toba Tek - Person Surface Drain = 11002/4614-Rft 979 2582 Replacement / new Water Supply Pipelines 13.000 7.465 1.833 1.833 1.375 1.371 100% 8.836 68% Brick pavement = 11866/0-Cft Sullage Singh in UC 18 District T.T. Singh. Carrier = 1425/875-Rft Rising Main & D/System 6" i/d PVC 4073/3000-Rft 4" i/d PVC 6800/3300-Rft 3" i/d PVC 17801/17751- Rft Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - Provision of Drainage and Soling and Toba Tek Person Trial Bore = 1/1-No. Tube-Well 1/1- 980 2583 Replacement / new Water Supply Pipelines 12.500 6.225 2.083 2.083 1.562 1.560 100% 7.785 62% No.Pump House = 1/1-No.Rising Main & Singh in UC 34 District T.T. Singh. D/System 4"i/d 3500/3500-RftPumping Machinery = 1/1-Set.Hypo Chlorinator = 1/0- No. Transmission Line 1/0-Job Construction of Road 4789/4500-Rft Work in progress.

1-Date of A.A 28.09.2017 2- Date of T.S 19.10.2017 3- Anticipated date of completion 30.06.2021 4- No. of Beneficiary - Person Brick Pavment = 640246/269668- Cft Resoling = 115,06,630/415218-Sft Road Pavement = 298,135/194558-Sft Surface Laying of Soling, Resoling, Drain, Repair of Toba Tek Drain = 665,997/22415-Rft PCC, = 981 2584 Roads and Piplelines Water and Sewerage 315.000 65.000 3.333 3.333 2.500 2.499 100% 67.499 21% 27,726/8298-Cft Tuff Tiles, = 19904/17130- Singh in District T.T.Singh. Sft Sullage Carrier = 22,400/1526-Rft RCC Sewer (9"-21") = 6,208/2044-Rft Water Supply Pipe = 30,526/26554-Rft Boundary Wall = 7026/0-Cft Tube-well = 2/2-No. Pump House = 2/0-No. Pumping Machinery = 1/1-Set Transmission Line = 1/0-Job Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3- Anticipated date of completion 30.06.2021 4- No. of Beneficiary Laying of PCC, Tuff Tiles, Soling and - Person Brick Pavement = 67,214/27353- Resoling, Drain, Repair of Roads and Toba Tek 982 2585 85.000 34.899 1.000 1.000 1.667 1.666 100% 36.565 43% Cft Resoling = 7456534933-Sft Surface Pipelines of water and Sewerage in District Singh Drain = 310/0-Rft PCC, Tuff Tiles, = 181552/69773-Cft RCC Sewer (9"-21") = T.T.Singh. 9604/ 2266-Rft Water Supply Pipe = 8916/3888-Rft Boundary Wall = 140/0-Rft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3- Anticipated date of Rehablitation of Rural Water Supply completion 30.06.2021 4- No. of Beneficiary 7006 Person Tube-well = 9/7-No. Pump Scheme Chak # 148/ GB, 149/GB, 151/GB House = 9/0-No. Rising Main / D-Sys 6:i/d ,153/GB, Balgn, 294/JB, 350/GB, Rural Toba Tek 983 2586 185.086 40.000 3.333 3.333 2.500 2.490 100% 42.490 23% PVC = 145515/44173-Rft 5:i/d PVC = Water Supply Scheme Chak # 258/GB Singh 17600/0-Rft 4:i/d PVC = 113980/19570-Rft 3:i/d PVC = 103560/41235-Rft Pumping Noor Mahal and 292/GB Bara Rasla in Machinery = 11/11-Set Ground Storage District T.T.Singh. Tank = 2/0-No. Overhed Reservoir = 1/0- No. Electric Connection =11/0-Job Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S 20.10.2017 3- Anticipated date of completion 30.06.2021 4- No. of Beneficiary -4383 Person Trial Bore 13/13-No. Tube- well = 13/13-No. Pump House =14/10-No. Rehabalitation of Rural Water Supply Rising Main / D-Sys 10" i/d PVC Scheme Chak # 402/JB Virkan348/GB Toba Tek 984 2587 178.792 68.399 3.333 3.333 3.000 2.986 100% 71.385 40% 30500/30429-Rft 8" i/d PVC1000/0-Rft 6" i/d Bajra, 296/GB, 297/GB, 299/GB, 290/GB, Singh PVC 73585/34242-Rft 5" i/d PVC 28400/6500-Rft 4" i/d PVC 101470/13896- 349/GB, and 351/GB in District T.T.Singh. Rft 3" i/d PVC 98258/7287-Rft Pumping Machinery = 17/17-Set Ground Storage Tank = 1/1-No. Overhed Reservoir = 1/0- No. Electric Connection 18/0-Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary -3360 Person Trial Bore = 3/3 No Tube-well Water Supply Scheme in Chak no. 374/JB, Toba Tek = 3/3-No. Pump House = 3/3No. Rising 985 2588 35.000 11.964 3.333 3.333 2.500 2.491 100% 14.455 41% Main / D-Sys 6" i/d PVC = 11180/10958-Rft 387/JB, 385/JB, District T.T.Singh. Singh 5" i/d PVC = 12000/12004-Rft 4" i/d PVC = 37930/16333-Rft 3" i/d PVC = 35370/4534- Rft Pumping Machinery = 3/0-Set Electric Transmission Line 3/0-Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 1- Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary Drainage/Soling and Water Supply and -3360 Person Trial Bore = 3/3 No Tube-well Toba Tek 986 2589 Road Repair UC No. 26 in District 12.000 6.000 2.000 2.000 1.500 1.494 100% 7.494 62% = 3/3-No. Pump House = 3/3No. Rising Singh Main / D-Sys 6" i/d PVC = 11180/10958-Rft T.T.Singh. 5" i/d PVC = 12000/12004-Rft 4" i/d PVC = 37930/16333-Rft 3" i/d PVC = 35370/4534- Rft Pumping Machinery = 3/0-Set Electric Transmission Line 3/0-Job Work in progress.

11-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary Drainage/Soling and Water Supply and Toba Tek - Person Brick Pavement = 28639/17365- 987 2590 Road Repair UC No. 28 in District 12.000 5.956 2.000 2.000 1.500 1.499 100% 7.455 62% Cft Resoling = 27371/18142-Sft Surface Singh T.T.Singh. Drain = 738/365-Rft Sullage Carrier = 1865/1365-Rft RCC Sewer 12" i/d 888/0-Rft Repair of Road = 19000/0-Sft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 12.08.2017 2- Date of T.S 12.08.2017 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - Drainage/Soling and Water Supply and Toba Tek Person Brick Pavement = 8259/6621-Cft 988 2591 Road Repair UC No. 32 in District 12.000 6.000 2.000 2.000 1.500 1.500 100% 7.500 63% Resoling = 880/0-SftSurface Drain = 1060/0- Singh T.T.Singh. RftSullage Carrier = 500/0-Rft Water Supply Pipe = 2270/2270-Rft RCC Sewer Pipe = 3277/2493-Rft PCC Flooring = 4217/4217-Cft Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S Drainage/Soling and Water Supply and 12.08.2017 3- Anticipated date of Toba Tek 989 2592 Road Repair UC No. 30 in District 12.000 5.984 2.000 2.000 1.500 1.500 100% 7.484 62% completion 30.06.20204- No. of Beneficiary - Singh Person Brick Pavement = 9621/8584Cft T.T.Singh. Sullage Carrier = 6422/4722-Rft Road Pavement = 55900/0-Rft Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary -5847 Person TRIAL BORES = 2/2-No. TUBE-WELLS = 3/3-No. PUMP HOUSES (SIZES 12'X12') = 4/0-No. RISING MAIN & Rural Water Supply Scheme Chak No. DISTRIBUTION SYSTEM 12”i/d PVC Pipe 321/GB Khumanwala Tehsil Pirmahal "B" Class = 100/0-Rft 8”i/d PVC Pipe "B" Class = 500/0-Rft 6”i/d PVC Pipe "B" Class District Toba Tek Singh, Chak No. 700/42 Toba Tek = 27730/22621-Rft 4”i/d PVC Pipe "B" 990 2593 GB Pir Kadhiana – Christian Colony Tehsil 49.970 17.999 5.000 5.000 3.750 3.742 100% 21.741 44% Class = 13955/21499-Rft 3”i/d PVC Pipe Singh Pirmahal District Toba Tek Singh, Chak No. "B" Class = 28734/26770-Rft PUMPING MACHINERIES = 5/0-No. HYPO 294/GB azafi abadi Tehsil & District Toba CHLORINATORS = 4/0-No. BOUNDARY Tek Singh. WALL = 400/0-Rft STAFF QUARTER = 1/0- No. OVER HEAD RESERVOIR (10,000- GLNS) = 1/0-No. RCC GST (50,000-Glns) = 1/0-No. ROAD CROSSING = 1/0-No. ELECTRIC TRANSMISSION LINES = 5/0- No.. OPERATION & MAINTENANCE COST = 3/0-No. Work in progress.

1-Date of A.A 19.09.2017 2- Date of T.S Rehabilitation of Rural Water Supply 20.10.2017 3- Anticipated date of Scheme Chak No. 301/GB azafi abadi – completion 30.06.2020 4- No. of Beneficiary - Person Trial Bore 3/3 Tube-well = 3/3-No. New Chak Tehsil & District Toba Tek Singh, Toba Tek Pump House = 4/2-No. Rising Main / D-Sys 991 2594 Chak No. 303/GB azafi abadi Tehsil & 72.396 20.000 3.333 3.333 2.500 2.490 100% 22.490 31% 6" i/d PVC = 36150/22771-Rft 5" i/d PVC = Singh District Toba Tek Singh, Chak No. 333/GB, 38120/5419-Rft 4" i/d PVC = 23705/7009- Rft 3" i/d PVC = 21235/11803-Rft Pumping District Toba Tek Singh, Chak No. 341/GB Machinery = 8/2-Set Ground Storage Tank Tehsil & District = 2/0-No. Electric Connection = 18/0-Job Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary - 13647 Person TRIAL BORE = 1/1-No. TUBE-WELLS (0.35-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/1-No. RISING MAIN / DISTRIBUTION SYSTEM 8” i/d PVC "B" Class = 5100/5100-Rft 6” i/d Extension / Rehabilitation Rural Water Toba Tek PVC "B" Class = 9000/9114-Rft 4” i/d PVC 992 2595 Supply Scheme Chak No.325 and 326/ GB, 24.600 19.000 1.867 1.867 0.600 0.600 100% 19.600 80% "B" Class = 1600/0-Rft 3” i/d PVC "B" Class Singh District T.T Singh. = 8010/8592-Rft PUMPING MACHINERY ( For Tube Well) FOR GST 325/GB = 1/0-Set FOR GST 326/GB = 1/0-Set RCC GROUND STORAGE TANK (100000-Glns) =1/1-No STAFF QUARTER = 1/0-No. BOUNDARY WALL = 600/0-Rft ELECTRIC TRANSMISSION LINE = 3/0-Job OPERATION & MAINTENANCE = 1/0-Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary - 4716 Person TRIAL BORE = 1/1-No. TUBE-WELLS (0.40-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/1-No. RISING MAIN / DISTRIBUTION SYSTEM = 1-No. 6” i/d PVC "B" Class = 19000/18207- Rural Water Supply Scheme Chak No. Toba Tek 993 2596 21.500 15.000 2.167 2.167 2.425 2.424 100% 17.424 81% Rft 4” i/d PVC "B" Class = 8960/8752-Rft 3” 671/12-GBDistrict T.T. Singh. Singh i/d PVC "B" Class = 2725/9262-Rft PUMPING MACHINERY =1/1-Set HYPO CHLORINATOR = 1/1-No. OVER HEAD RESERVOIR (10000-Glns) = 1/1-No. BOUNDARY WALL = 290/0-Rft STAFF QUARTER = 1/1-No. ROAD CROSSING = 2/0-Job ELECTRIC TRANSMISSION LINE = 1/0-Job OPERATION & MAINTENANCE = 1/0-Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary -5309 Person TRIAL BORE = 1/1-No. TUBE- WELLS (0.50-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/0-No. RISING MAIN / DISTRIBUTION SYSTEM 6” i/d PVC "B" Rural Water Supply Scheme Chak Toba Tek 994 2597 15.400 7.000 2.800 2.800 0.795 0.794 100% 7.794 51% Class = 7530/5121-Rft 4” i/d PVC "B" Class No.711/GB District T.T. Singh. Singh = 5800/7070-Rft 3” i/d PVC "B" Class = 13685/7289-Rft PUMPING MACHINERY = 1/0-Set HYPO CHLORINATOR = 1/0-No. OVER HEAD RESERVOIR (10000-Glns) = 1/0-No.STAFF QUARTER = 1/0-No. ELECTRIC TRANSMISSION LINE = 1/0- Job OPERATION & MAINTENANCE = 1/0- Job Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary - 8625 Person TRIAL BORE = 1/1-No. TUBE-WELLS (0.75-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/1-No. RISING MAIN / DISTRIBUTION SYSTEM 8” i/d PVC "B" Class = 18150/18171-Rft 6” Rural Water Supply Scheme Chak Toba Tek i/d PVC "B" Class = 2760/0-Rft 4” i/d PVC 995 2598 29.500 10.000 3.333 3.333 2.500 2.488 100% 12.488 42% "B" Class = 11060/0-Rft 3” i/d PVC "B" No.662/3-GB District T.T. Singh. Singh Class = 21500/0-Rft PUMPING MACHINERY = 1/0-Set HYPO CHLORINATOR = 1/0-No. OVER HEAD RESERVOIR (20,000-GLNS) = 1/0- No.BOUNDARY WALL = 600/0-Rft STAFF QUARTER = 1/1-No. ROAD CROSSING = 1/0-Job ELECTRIC TRANSMISSION LINE = 1/0-Job OPERATION & MAINTENANCE = 1/0-Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.2020 4- No. of Beneficiary - 6164 Person TRIAL BORE = 1/1-No. TUBE-WELLS (0.50-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1-No. RISING MAIN / DISTRIBUTION SYSTEM 6” i/d PVC "B" Class = 17261/13874-Rft 4” i/d Rural Water Supply Scheme Chak Toba Tek 996 2599 27.300 11.998 5.100 5.100 3.825 3.823 100% 15.821 58% PVC "B" Class = 13706/9156-Rft 3” i/d PVC No706/GB. District T.T. Singh Singh "B" Class = 17374/13219-Rft PUMPING MACHINERY = 1/0-Set HYPO CHLORINATOR = 1/0-No. OVER HEAD RESERVOIR (10000-Glns) = 1-/0- No.BOUNDARY WALL = 880/500-Rft STAFF QUARTER = 1/1-No. ELECTRIC TRANSMISSION LINE = 1/0-Job OPERATION & MAINTENANCE = 1/0Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - 11853 Person TRIAL BORE = 1/1-No. TUBE-WELLS (0.85-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/0-No. RISING MAIN / DISTRIBUTION SYSTEM 8” i/d PVC "B" Class = 3400/4052-Rft 6” i/d Rural Water Supply Scheme Chak Toba Tek 997 2600 24.750 17.000 2.583 2.583 1.937 1.933 100% 18.933 76% PVC "B" Class = 8353/7694-Rft 4” i/d PVC No.720/GB District T.T. Singh. Singh "B" Class = 11798/13733-Rft 3” i/d PVC "B" Class = 28359/22923-Rft PUMPING MACHINERY = 1/0-Set HYPO CHLORINATOR = 1/0-No. OVER HEAD RESERVOIR (20,000-GLNS) = 1/1- No.STAFF QUARTER = 1/1-No. ELECTRIC TRANSMISSION LINE 1/0-Job OPERATION & MAINTENANCE 1/0-Job Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - 8765 Person TRIAL BORE = 1/1-No. TUBE- WELLS (0.75-CUSEC) = 1/1-No. PUMP HOUSE (12' X 12') = 1/1-No. RISING MAIN / DISTRIBUTION SYSTEM 8” i/d PVC "B" Class = 4600/4400-Rft 6” i/d PVC "B" Class Rural Water Supply Scheme Chak Toba Tek 998 2601 25.700 14.799 3.633 3.633 2.725 2.720 100% 17.519 68% = 10699/10572-Rft 5” i/d PVC "B" Class = No.721/GB District T.T. Singh. Singh 1000/1000-Rft 4” i/d PVC "B" Class = 9643/9780-Rft 3” i/d PVC "B" Class = 23541/16013-Rft PUMPING MACHINERY = 1/0-Set HYPO CHLORINATOR = 1/0-No. OVER HEAD RESERVOIR (20,000-GLNS) = 1/1-No.STAFF QUARTER = 1/0-No. ELECTRIC TRANSMISSION LINE = 1/0- Job OPERATION & MAINTENANCE = 1/0- Job Work in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3-Date of Prequalification 4- Date of invitation of tenders 5- Date of Receipt of tenders 6- Date of work order Rural Water Supply Scheme Chak Toba Tek 31.10.2017 7- Date of completion as per PC- 999 2602 23.500 13.999 3.167 3.167 0.885 0.881 100% 14.880 63% I 8- Anticipated date of completion 9- No. of No.722/GB District T.T. Singh Singh Beneficiary -6826 Person 10-Funds Released by F.D 03.08.2018 & 24.01.2019 - 11-Re-appropriation of funds (+/-) (-) 11.01.2019. Work in progress. Latitude:- 30.395791 Longitude:-72.301784

1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - Water Supply Scheme Chak No. 317/JB .. Person Trial Bore = 1/1-JobTube-well = Toba Tek 1000 2603 and Installation of Filtration Plant in Chak 24.587 10.000 4.862 4.862 3.647 3.631 100% 13.631 55% 1/1-No. Pump House = 1/1-No.Rising Main Singh / D-Sys 6"i/d PVC = 26460/26285-Rft 4"i/d No.401/JB District T.T.Singh PVC = 14300/11716-Rft 3"i/d PVC = 12150/11680-Rft Pumping Machinery = 1/1- Set Filteration Plant = 1/0-No.Electric Connection = 3/0-JobWork in progress.

1-Date of A.A 12.01.2018 2- Date of T.S 13.01.2018 3- Anticipated date of Rehabilitation / Improvemnet of Rural Toba Tek completion 30.06.2020 4- No. of Beneficiary 1001 2604 Draiange Scheme Chak no. 402/GB Virkan 35.000 3.999 1.667 1.667 1.250 1.245 100% 5.244 15% -.. Person Brick Pavement = 65420/17860- Singh Tehsil and District T.T.Singh Cft Resoling = 90750/0-SftSurface Drain = 26125/0-RftSullage Carrier = 8700/3241- RftWork in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of Provision of Soling / Re-Soling Nali / completion 30.06.2020 4- No. of Beneficiary Toba Tek 1002 2605 Sewerage / PCC and Tuff Tile Schemes in 20.000 9.998 3.333 3.333 2.500 2.488 100% 12.486 62% - Person Tuff Tiles = 89381/58224-Sft Brick Singh Pavement = 2366/0Cft Surface Drain = City Kamalia In District T.T.Singh 420/0-Rft RCC Sewer 9" i/d = 957/175-Rft 12" i/d = 1012/0-Rft 15" i/d =312/302-Rft 18" i/d = 1115/1091-RftWork in progress.

1-Date of A.A 19.09.2017 2- Date of T.S Soling Drainage Khalla Nalli and Pullian in 12.10.2017 3- Anticipated date of UC 57, 58, 59, 60, 61, 62, 63, 66, 68, Chak Toba Tek completion 30.06.20204- No. of Beneficiary - 1003 2606 60.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 38% Person Brick Pavement = 207333/91611- No. 735/GB in Tehsil Kamalia District Singh Cft.Resoling = 177605/39215-Sft Surface T.T.Singh Drain = 17489/4206-Rft Sullage Carrier = 5013/1600-Rft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of Tuff Tile PCC Soling / Drainage / Sewerage Toba Tek completion 30.06.2020 4- No. of Beneficiary 1004 2607 in Kamalia City Tehsil Kamalia District 40.000 13.662 1.667 1.667 1.250 1.244 100% 14.906 37% - Person Tuff Tiles = 181668/83276-Sft Singh T.T.Singh Brick Pavement = 11807/3790-Cft Surface Drain Type-I = 11190/934Rft RCC Sewer = 1968/1599-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of Tuff Tile PCC Soling / Re-soling Drainag, Toba Tek 1005 2608 40.000 14.999 1.667 1.667 1.250 1.250 100% 16.249 41% completion 30.06.2020 4- No. of Beneficiary Sewerage etc for Kamalia City Singh - Person Tuff Tiles = 226549/154900-Sft Surface Drain Type-I = 5560/2248-Rft PCC Sewer = 1675/1675-Cft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Construction of PCC / Tuff 30.08.2017 3- Anticipated date of Toba Tek 1006 2609 tile/Soling/Resoling Pirmahal City in District 25.000 10.000 5.000 5.000 3.750 3.740 100% 13.740 55% completion 30.06.2020 4- No. of Beneficiary Singh - Person Tuff Tiles = 161836/77503-Sft T.Tsingh Brick Pavement = 1660/0 Rftt Surface Drain Type-I = 34/200-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 .3- Anticipated date of completion 30.06.20204- No. of Beneficiary - Person .Surface Drain = 9656/0-Rft Brick pavement = 32851/0-Cft Sullage Carrier = Provision of Drainage and Soling and Toba Tek 2300/0-Rft Trial Bore = 2/2-No.Tube-Well = 1007 2610 Replacement / new Water Supply Pipelines 32.000 12.000 1.667 1.667 1.250 1.244 100% 13.244 41% 2/2-No. Pump House = 2/0-No.Rising Main Singh in UC 17 District T.T. Singh. & D/System 6" i/d PVC 20967/20700-Rft 4" i/d PVC 6500/5500-Rft.3" i/d PVC 8040/8040-RftPumping Machinery = 2/0- SerHypo Chlorinator = 1/0-No.Boundray Wall = 664/0-Rft.Transmission Line = 2/0- JobWork in progress.

1-Date of A.A 12.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of Provision of Tuff Paver and Drains in Toba Tek completion 30.06.20204- No. of Beneficiary - 1008 2611 40.000 15.000 1.667 1.667 9.451 9.451 100% 24.451 61% Person Tuff Tiles = 145767/81528Sft Brick Kamalia City, District T.T.Singh Singh Pavement 7939/1364-Cft Surface Drain Type-I = 8670/1044-Rft RCC Sewer 9"i/d 2848/206-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of Provision of Tuff Paver and Drains in Pir Toba Tek completion 30.06.20204- No. of Beneficiary - 1009 2612 40.000 15.000 1.667 1.667 0.483 0.482 100% 15.482 39% Person Tuff Tiles = 274005/112510-Sft Mahal City, District T.T.Singh. Singh Brick Pavement =1635/1635-Cft Resoling = 640/640-SftSurface Drain Type-I = 737/737- Rft.Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of Provision of Drainage and Soling and Toba Tek completion 30.06.20204- No. of Beneficiary - 1010 2613 Replacement / new Water Supply Pipelines 15.000 7.500 2.500 2.500 1.875 1.866 100% 9.366 62% Person Surface Drain = 1047/0-RftBrick Singh in UC 14 District T.T. Singh. pavement = 53057/37274-Cft.Sullage Carrier = 3146/809-Rft.Water Supply pipe line = 15365/3718-Rft.Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 03.08.2017 2- Date of T.S 30.08.2017 3- Anticipated date of completion 30.06.20204- No. of Beneficiary - Person Surface Drain = 2150/0-Rft Brick pavement = 25102/20518-Cft Sullage Provision of Drainage and Soling and Toba Tek Carrier = 3141/396-Rft Trial Bore = 1/1- 1011 2614 Replacement / new Water Supply Pipelines 31.000 20.000 3.333 3.333 2.500 2.493 100% 22.493 73% No.Tube-Well = 1/1-No. Pump House = 1/0- Singh in UC 15 District T.T. Singh. No.Rising Main & D/System 6" i/d PVC 28580/28000-Rft 4" i/d PVC 6315/5808- Rft3" i/d PVC 17380/13917-RftPumping Machinery = 1/0-Set.Hypo Chlorinator = 1/0- No. Transmission Line = 1/0-Job.Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Provision of Drainage and Soling and 30.08.2017 3- Anticipated date of Toba Tek 1012 2615 Replacement / new Water Supply Pipelines 13.000 7.500 1.833 1.833 1.375 1.373 100% 8.873 68% completion 30.06.2020.4- No. of Beneficiary Singh -Person Surface Drain = 14414/7570-Rft in UC 16 District T.T. Singh. Brick pavement = 29946/19104-Cft Sullage Carrier = 955/693-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1013 2616 Chak No. 672/13 GB & azafi abadi in 3.000 1.455 0.500 0.500 0.375 0.374 100% 1.829 61% completion 30.06.20204- No. of Beneficiary - Singh Person .Brick Pavement = 11051/3279-Cft District T.Tsingh Resoling = 14040/11310-Sft Surface Drain Type-I = 1121/1121-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1014 2617 Chak No. 673/14/GB Harisabad & azafi 3.000 1.422 0.500 0.500 0.375 0.373 99% 1.795 60% completion 30.06.2020 4- No. of Beneficiary Singh - Person Brick Pavement = 8487/6279-Cft abadi in District T.Tsingh Resoling = 12530/9880-Sft Surface Drain Type-I = 1964/629-Rft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1015 2618 Chak No. 675/16/GB & azafi abadi in 3.000 1.500 0.500 0.500 0.375 0.375 100% 1.875 63% completion 30.06.2020 4- No. of Beneficiary Singh District T.Tsingh - Person Brick Pavement = 16519/9050-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1016 2619 Chak No. 676/17/GB & azafi abadi in 3.000 1.498 0.500 0.500 0.375 0.375 100% 1.873 62% completion 30.06.2020 4- No. of Beneficiary Singh District T.Tsingh - Person Brick Pavement = 16125/8177-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1017 2620 Mouza Shahpur & azafi abadi in District 3.000 1.000 0.667 0.667 0.500 0.498 100% 1.498 50% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 17115/-6988-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1018 2621 Mouza Nakrari & azafi abadi in District 3.000 0.997 0.667 0.667 0.500 0.499 100% 1.496 50% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 17119/5896-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1019 2622 Mouza Bub & azafi abadi in District 2.500 0.952 1.548 1.548 1.161 1.159 100% 2.111 84% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 17865-Cft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 19.09.2017 2- Date of T.S 19.10.2017 3- Anticipated date of completion 30.06.20214- No. of Beneficiary - Person Brick Pavement = 441306/294291- Cft.Resoling = 897720/255791-Sft Surface Provision of Sewerage / Drainage / Tuff Toba Tek Drain = 53187/7229-Rft Sullage Carrier = 1020 2623 199.924 99.996 5.000 5.000 3.750 3.750 100% 103.746 52% 19220/6300-Rft RCC Sewer (9"-24") = Tiles etc in District T.T.Singh. Singh 6770/6981-Rft Water Supply Pipe = 6" i/d PVC 9900/1175-Rft4" i/d PVC 23360/18470- Rft 3" i/d PVC 35350/37169-Rft Overhead Reservoir = 1/0-No. Boundary Wall 7805/900-Rft P/Machinery 1/0-Set.Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S 12.08.2017 3- Anticipated date of Rural Drainage/Brick Pavement/Resoling Toba Tek 1021 2624 3.000 1.500 0.500 0.500 0.375 0.374 100% 1.874 62% completion 30.06.2020 4- No. of Beneficiary Plot-A & azafi abadi in District T.Tsingh Singh - Person Brick Pavement = 13939-Cft Surface Drain Type-I = 250-Rft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1022 2625 Chak No. 718/GB & azafi abadi in District 3.000 1.499 0.500 0.500 0.375 0.375 100% 1.874 62% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 18059/8296-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1023 2626 Chak No. 719/GB & azafi abadi in District 3.000 1.500 0.500 0.500 0.375 0.375 100% 1.875 63% completion 30.06.2020 4- No. of Beneficiary Singh - Person Brick Pavement = 9661/7294-Cft T.Tsingh Resoling = 1500/1500-Sft Surface Drain Type-I = 926/776-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1024 2627 Chak No. 720/GB & azafi abadi in District 3.000 1.478 0.500 0.500 0.375 0.375 100% 1.853 62% completion 30.06.2020 4- No. of Beneficiary Singh - Person Brick Pavement = 10347-Cft T.Tsingh Resoling = 5500-Sft Surface Drain Type-I = 2550-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1025 2628 Chak No. 722/GB & azafi abadi in District 3.000 1.500 0.500 0.500 0.375 0.375 100% 1.875 63% completion 30.06.2020 4- No. of Beneficiary Singh - Person Brick Pavement = 13251/7737-Cft T.Tsingh Resoling = 1500/0-Sft Surface Drain 1676/0- Rft Work in progress. 1-Date of A.A 12.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1026 2629 Chak No. 741/GB & azafi abadi in District 3.000 1.020 0.500 0.500 0.375 0.374 100% 1.394 46% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 17784/3998-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1027 2630 Chak No. 747/GB & azafi abadi in District 3.000 0.595 0.500 0.500 0.375 0.375 100% 0.970 32% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 17840/6065-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1028 2631 Chak No. 757/GB & azafi abadi in District 2.500 1.204 0.417 0.417 0.313 0.313 100% 1.517 61% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 12725-Cft Rosoling = 5000-Sft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1029 2632 Chak No. 759/GB & azafi abadi in District 3.000 1.500 0.500 0.500 0.375 0.375 100% 1.875 63% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 17523/9487-Cft Work in progress. 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1030 2633 Chak No. 760/GB & azafi abadi in District 2.500 1.250 0.417 0.417 0.313 0.313 100% 1.563 63% completion 30.06.2020 4- No. of Beneficiary Singh T.Tsingh - Person Brick Pavement = 12599/7662-Cft Rosoling = 5500/0-Sft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1031 2634 Chak No. 764/GB & azafi abadi in District 3.000 1.500 0.500 0.500 0.375 0.374 100% 1.874 62% completion 30.06.2020 4- No. of Beneficiary Singh - Person Brick Pavement = 10839/7000-Cft T.Tsingh Resoling = 4420/4420-Sft Surface Drain 2128/1978-Rft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling Toba Tek 12.08.2017 3- Anticipated date of 1032 2635 Chak No. 660/1/GB & azafi abadi in District 3.000 1.500 0.500 0.500 0.375 0.375 100% 1.875 63% completion 30.06.20204- No. of Beneficiary - Singh T.Tsingh Person Brick Pavement = 16275/9266-Cft Resoling = 7720/9867-Sft Work in progress.

1-Date of A.A 03.08.2017 2- Date of T.S Rural Drainage/Brick Pavement/Resoling 12.08.2017 3- Anticipated date of Toba Tek 1033 2636 Mouza Inayat Shah & azafi abadi in District 3.000 1.500 0.500 0.500 0.375 0.374 100% 1.874 62% completion 30.06.20204- No. of Beneficiary - Singh Person .Brick Pavement = 13074/9226-Cft T.Tsingh Resoling = 9867/9867-Sft Surface Drain Type-I = 855/50-Rft Work in progress. Constructoin of Drains PCC / RCC in UC 1034 2637 Qila Mian Singh Uggu Chak District Gujranwala 50.000 13.000 5.000 5.000 3.750 3.750 100% 16.750 34% Work in progress. Gujranwala Sewerage PCC Drainage in UC Wahndo / 1035 2638 Gujranwala 60.000 19.991 6.667 6.667 5.000 5.000 100% 24.991 42% Work in progress. UC Chak Ramdas in District Gujranwala Construction of PCC and Sewerage at Y- Block Peoples Colony, X-Block Behari 1036 2639 Colony, Shadman Town, Green Town Gujranwala 20.000 9.999 3.333 3.333 2.500 2.500 100% 12.499 62% Work in progress. Ahsan Town, Hassan Town District Gujranwala Construction of PCC and Sewerage at Kot Abdullah, Kangni Wala, Rana Colony, 1037 2640 Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Saddique Colony, Nabi Pura, Illama Iqbal Town in District Gujranwala Provision of Sewerage, PCC, Street, Drain, 1038 2641 Tuff Tile, Water Supply in City Wazirabad, Gujranwala 200.000 75.000 3.333 3.333 2.500 2.500 100% 77.500 39% Work in progress. Sodra, District Gujranwala Drainage and PCC Soling in UCs Nokhar, 1039 2642 Pheloke, Udowali, in Saharan Chatha Gujranwala 88.947 19.901 3.333 3.333 2.500 2.500 100% 22.401 25% Work in progress. District Gujranwala Drainage and PCC Soling in UCs Noi wala, 1040 2643 Jattan wali, Bheri Shah Rehman, Jhallan in Gujranwala 89.034 17.820 3.333 3.333 2.500 2.500 100% 20.320 23% Work in progress. District Gujranwala Drainage and PCC Soling in UCs Phama 1041 2644 Sara, Arghan, Chak Chaudhary, Kot Ladha, Gujranwala 89.776 20.000 3.333 3.333 2.500 2.500 100% 22.500 25% Work in progress. in District Gujranwla Construction of PCC Streets and Drainage in Botala Sharam Singh / Akbarian, Sansera Goraya and Muslim Chack, Attawa, Therri Sansi and Chand da Qila, Kotli Dianat Raye and Sheray wala, 1042 2645 Gujranwala 50.000 20.000 30.000 30.000 22.500 22.500 100% 42.500 85% Bill with Held Nangray Dadan, Dera Bhaghat Singh and Dera Hakam Singh, Chddiala Kalan and Khurd, Murali wala and Khuwasra, Dhillian wali, Chianwall, Kot Shera and Sahnaya wala Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC and Sewerage at sarfaraz Colony, Hashimi Colony, Gulshan 1043 2646 Gujranwala 40.000 15.000 1.667 1.667 1.250 1.250 100% 16.250 41% Work in progress. Adeel, Mumtaz Colony, Karmabad District Gujranwala Construction of PCC and Sewerage at Asghar Colony, Salamat Pura, Allah 1044 2647 Gujranwala 40.000 15.000 1.667 1.667 1.250 1.250 100% 16.250 41% Work in progress. Bukhsh Colony, Nawaz Colony, Faisal Colony District Gujranwala Construction of PCC and Sewerage at Jinnah Colony, Rehman Colony, Ali Pura, 1045 2648 Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Bukhari Colony, Sanat Road, Jamia Muhammadiya District Gujranwala Construction of PCC and Sewerage at Rasheed Colony, Ismail Pura, Abdullah 1046 2649 Gujranwala 20.000 9.999 3.333 3.333 2.500 2.500 100% 12.499 62% Work in progress. Colony, W Block Peoples Colony District Gujranwala Construction of PCC and Sewerage at Z- 1047 2650 Block Peoples Colony, X-Block Peoples Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Colony District Gujranwala Construction of PCC and Sewerage at Chamra Mandi, Wahdat Colony, Chaman 1048 2651 Gujranwala 20.000 9.910 3.333 3.333 2.500 2.500 100% 12.410 62% Work in progress. Shah Road, Taj Colony, Arfat Colony, Ferozwala Road in District Gujranwala Construction of PCC and Sewerage at Arfat 1049 2652 Colony, Islam Pura, Haidry Road in District Gujranwala 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. Gujranwala Construction of PCC and Sewerage at 1050 2653 Mujahid Pura, Camp No. 4, Saithy Palaza, Gujranwala 15.000 9.999 1.667 1.667 1.250 1.250 100% 11.249 75% Work in progress. Faisal Colony, in District Gujranwala Construction of PCC and Sewerage at Galla Ghulam Thakedar Wala, Galla Mehar 1051 2654 Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Noor Wala, Islam Pura, Muslim Road in District Gujranwala Drainage and PCC at UC, 31,40,46 at 1052 2655 Gujranwala 150.000 29.998 5.000 5.000 3.750 3.750 100% 33.748 22% Work in progress. District Gujranwala Construction of PCC/ Tuff Tile, Drainage 1053 2656 and Allied Facilities etc in NA-96, District Gujranwala 50.000 29.987 3.333 3.333 2.500 2.500 100% 32.487 65% Work in progress. Gujranwala Construction of PCC, Sewerage/Drains at 1054 2657 Gujranwala 25.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 55% Work in progress. UC 48 District Gujranwala Construction of PCC, Sewerage/Drains at 1055 2658 Gujranwala 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. UC 49 District Gujranwala Construction of PCC, Sewerage/Drains at 1056 2659 Gujranwala 15.000 9.948 1.667 1.667 1.250 1.250 100% 11.198 75% Work in progress. UC 50 District Gujranwala Construction of PCC, Sewerage/Drains at 1057 2660 Gujranwala 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. UC 51 District Gujranwala Construction of PCC, Sewerage/Drains at 1058 2661 Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. UC 52 District Gujranwala Construction of PCC, Sewerage/Drains at 1059 2662 Gujranwala 20.000 9.920 3.333 3.333 2.500 2.500 100% 12.420 62% Work in progress. UC 53 District Gujranwala Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC, Sewerage/Drains at 1060 2663 Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. UC 54 District Gujranwala Construction of PCC, Sewerage/Drains at 1061 2664 Gujranwala 20.000 9.982 3.333 3.333 2.500 2.500 100% 12.482 62% Work in progress. UC 57 District Gujranwala Construction of PCC, Sewerage/Drains at 1062 2665 Gujranwala 25.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 55% Work in progress. UC 58 District Gujranwala Construction of PCC, Sewerage/Drains at 1063 2666 Gujranwala 20.000 9.954 3.333 3.333 2.500 2.500 100% 12.454 62% Work in progress. UC 59 District Gujranwala Construction of PCC, Sewerage/Drains at 1064 2667 Gujranwala 25.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 55% Work in progress. UC 60 District Gujranwala Construction of PCC, Sewerage/Drains at 1065 2668 Gujranwala 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. UC 62 District Gujranwala Provision of Sewerage, Drainage and PCC 1066 2669 Scheme UC Aroop, UC Butteranwali, Gujranwala 200.000 40.000 3.333 3.333 2.500 2.500 100% 42.500 21% Work in progress. District Gujranwala, Phase-I

Provision of Sewerage, Drainage and PCC 1067 2670 Scheme for Area Rahwali Sharqi, Kot Gujranwala 100.000 30.000 3.333 3.333 2.500 2.500 100% 32.500 33% Work in progress. Shahan And Trigri District Gujranwala Construction of PCC/RCC/Drainage at 1068 2671 Gujranwala 30.000 7.992 20.000 20.000 15.000 15.000 100% 22.992 77% Work in progress. Shaheenabad, Gujranwala Construction of PCC/RCC/Drainage at 1069 2672 Gujranwala 50.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 35% Work in progress. Pasban Colony, Gujranwala Construction of PCC/RCC/Drainage at 1070 2673 Gujranwala 50.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 35% Work in progress. Samnabad, Gujranwala Construction of PCC/RCC/Drainage at 1071 2674 Gujranwala 30.000 7.000 3.333 3.333 2.500 2.500 100% 9.500 32% Work in progress. Gondalwala, Gujranwala Construction of PCC/RCC/Drainage at 1072 2675 Gujranwala 30.000 7.989 3.333 3.333 2.500 2.500 100% 10.489 35% Work in progress. Aminpur, Gujranwala Construction of PCC/RCC/Drainage at 1073 2676 Gujranwala 30.000 8.000 3.333 3.333 2.500 2.500 100% 10.500 35% Work in progress. Badoki Gusaian, Gujranwala Construction of PCC/RCC/Drainage at 1074 2677 Gujranwala 30.000 8.000 3.333 3.333 2.500 2.500 100% 10.500 35% Work in progress. Dingranwali, Gujranwala Provision of PCC / Sewerage schemes 1075 2678 near Bypass Surrounding Abadies of Gujranwala 190.600 40.000 30.000 30.000 22.500 22.500 100% 62.500 33% Work in progress. Timber Market, District Gujranwala Constructoin of Drains PCC / RCC in UC 1076 2679 Kalaskay, Banka, Ladheywala Cheema Gujranwala 50.000 13.000 5.000 5.000 3.750 3.750 100% 16.750 34% Work in progress. District Gujranwala Construction of Drains, PCC/RCC and 1077 2680 Sullage Carrier in Villages of U.C Chianwali Gujranwala 30.000 9.848 8.333 8.333 6.250 6.250 100% 16.098 54% Work in progress. in District Gujranwala Construction of Drains, PCC/RCC and 1078 2681 Sullage Carrier in Villages of U.C Gujranwala 30.000 9.970 20.000 20.000 15.000 15.000 100% 24.970 83% Bill with Held Ladhaywala Goraya in District Gujranwala Sewerage PCC Drainage in UC Malkay / 1079 2682 UC Mari Thakran / UC Ghoma in District Gujranwala 80.000 23.483 5.000 5.000 3.750 3.750 100% 27.233 34% Work in progress. Gujranwala Sewerage PCC Drainage in UC Talwandi 1080 2683 Gujranwala 60.000 29.963 5.000 5.000 3.750 3.750 100% 33.713 56% Work in progress. MK / UC Jandiala in District Gujranwala Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Water Supply / PCC / Drainage Facility in 1081 2684 Sodhrar Town, Tehsil Wazirabad, District Gujranwala 134.586 18.000 20.000 20.000 26.218 26.218 100% 44.218 33% Work in progress. Gujranwala Construction of Streets and Drainage at UC 1082 2685 Gujranwala 30.000 9.975 3.333 3.333 2.500 2.500 100% 12.475 42% Work in progress. Marri Thakran, District Gujranwala Construction of Streets and Drainage at UC 1083 2686 Gujranwala 30.000 9.972 3.333 3.333 2.500 2.500 100% 12.472 42% Work in progress. Akbar Ghanoke, District Gujranwala Construction of Streets and Drainage at UC 1084 2687 Gujranwala 30.000 9.988 3.333 3.333 2.500 2.500 100% 12.488 42% Work in progress. Ghaniya District Gujranwala Construction of Streets and Drainage at UC 1085 2688 Gujranwala 30.000 9.947 3.333 3.333 2.500 2.500 100% 12.447 41% Work in progress. Guna Aur District Gujranwala Construction of Streets and Drainage at UC 1086 2689 Gujranwala 30.000 9.997 6.667 6.667 5.000 5.000 100% 14.997 50% Work in progress. Ghoma/Harpoki District Gujranwala Construction of Streets and Drainage at UC 1087 2690 Gujranwala 30.000 9.958 3.333 3.333 2.500 2.500 100% 12.458 42% Work in progress. Machrala District Gujranwala Construction of Streets and Drainage at UC 1088 2691 Gujranwala 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Work in progress. Sadoki District Gujranwala Provision of Clean Water Facility in NA-95, 1089 2692 Gujranwala 200.000 66.995 5.000 5.000 3.750 3.750 100% 70.745 35% Work in progress. District Gujranwala Constructoin of Drains PCC / RCC in UC 1090 2693 Gujranwala 32.000 12.500 1.667 1.667 1.250 1.250 100% 13.750 43% Work in progress. Botal Jhanda Singh District Gujranwala Sewerage PCC Drainage in UC Mokhal / 1091 2694 UC Nadala / UC Feroz wala in District Gujranwala 80.000 23.412 3.333 3.333 2.500 2.500 100% 25.912 32% Work in progress. Gujranwala Sewerage PCC Drainage in UC Nangal 1092 2695 Gujranwala 80.000 23.345 3.333 3.333 2.500 2.500 100% 25.845 32% Work in progress. Dona / UC Machrala in District Gujranwala Sewerage PCC Drainage in UC Sohawa / 1093 2696 Gujranwala 60.000 19.898 3.333 3.333 2.500 2.500 100% 22.398 37% Work in progress. UC Kali Suba in District Gujranwala Sewerage PCC Drainage in UC Sadhoki / 1094 2697 UC Gunaur / UC Mandiala Tega in District Gujranwala 80.000 23.473 5.000 5.000 3.750 3.750 100% 27.223 34% Work in progress. Gujranwala Construction of Drains,PCC Sullage Carrier 1095 2698 UC Budha Graya Tehsil Nowshera Virkan Gujranwala 20.000 9.953 3.333 3.333 2.500 2.500 100% 12.453 62% Work in progress. District Gujranwala Construction of Drains,PCC Sullage Carrier 1096 2699 UC Boopra Kalan Tehsil Nowshera Virkan Gujranwala 20.000 9.897 3.333 3.333 2.500 2.500 100% 12.397 62% Work in progress. District Gujranwala Construction of Drains,PCC Sullage Carrier 1097 2700 UC Tatlay Aali Tehsil Nowshera Virkan Gujranwala 20.000 9.999 3.333 3.333 2.500 2.500 100% 12.499 62% Work in progress. District Gujranwala Construction of Drains,PCC Sullage Carrier 1098 2701 UC Matto Bbajme Tehsil Nowshera Virkan Gujranwala 20.000 9.858 3.333 3.333 2.500 2.500 100% 12.358 62% Work in progress. District Gujranwala Construction of Drains,PCC Sullage Carrier 1099 2702 UC Karyl Kalan Tehsil Nowshera Virkan Gujranwala 20.000 9.997 3.333 3.333 2.500 2.500 100% 12.497 62% Work in progress. District Gujranwala Provision of PCC / Sewerage / Drainage 1100 2703 /Tuff Tiles and allied facilities etc. in NA- Gujranwala 100.000 28.000 5.000 5.000 3.750 3.750 100% 31.750 32% Work in progress. 101, District Gujranwala Provision of Water Filtration Plant / A.A.30.860 (M) T.S. 30.860 (M) work is in 1101 2704 Drainage System Chak Chatha U/C no. 15, Hafizabad 30.860 10.000 3.333 3.333 2.500 2.450 98% 12.450 40% progress. District Hafizabad Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Constrcutinn of Drain / Nallah / PCC / Soling Bateray, Kotli Amir Singh, 1102 2705 Hafizabad 50.000 19.999 3.333 3.333 2.500 2.500 100% 22.499 45% A.A. 50.000 (M)T.S. 50.000 (M) work is in Kallairwala, Muradian U/C Sagar Khan, no. progress. 12, District Hafizabad Constrcutinn of Drain / Nallah / PCC / 1103 2706 Hafizabad 50.000 20.000 3.333 3.333 2.500 2.480 99% 22.480 45% A.A. 50.000 (M) T.S. 50.000 (M) work is in Soling U/C No. 5, District Hafizabad progress. Constrcutinn of Drain / Nallah / PCC / 1104 2707 Hafizabad 50.000 19.810 3.333 3.333 4.167 4.166 100% 23.976 48% A.A. 50.000 (M) T.S. 50.000 (M) work is in Soling U/C No. 14, District Hafizabad progress. Constrcutinn of Drain / Nallah / PCC / A.A. 50.000 (M) T.S. 50.000 (M) work is in 1105 2708 Soling and Sewer in village Vanike Tarar Hafizabad 50.000 20.000 3.333 3.333 2.500 2.450 98% 22.450 45% progress. U/C No. 3, District Hafizabad Rural Drainage Scheme Herdo Sagar, A.A. 25.002 (M) T.S. 25.002 (M) work is in 1106 2709 Dhnoi Dogran, Praim Kot, Batairay, Wingay Hafizabad 25.005 10.000 5.002 5.002 2.352 2.250 96% 12.250 49% progress. and Bashmolajat District Hafizabad Rural Drainage Scheme Dhunni, Jaidkey, Chak Chatha, Dahranwali, Thatha, Kharian, 1107 2710 Hafizabad 25.002 9.999 5.001 5.001 3.751 3.650 97% 13.649 55% A.A. 25.002 (M) T.S.25.002 (M) work is in Peer Koot and Bashmolajat District progress. Hafizabad Construction of Streets Drains PCC/ Soling A.A. 20.000 (M) T.S. 20.000 (M)work is in 1108 2711 and Nallah In Vilaage Kassesy District Hafizabad 20.000 10.000 3.333 3.333 4.000 4.000 100% 14.000 70% progress. Hafizabad Construction of Streets Drains PCC/ Soling A.A. 20.000 (M) T.S. 20.000 (M) work is in 1109 2712 and Nalla In Village Tibba Shah Balol Hafizabad 20.000 9.925 3.333 3.333 2.500 2.500 100% 12.425 62% progress. District Hafizabad Construction of Streets Drains PCC/ Soling A.A. 20.000 (M)T.S.20.000 (M) work is in 1110 2713 and Nallah In Village Kot Khush hall District Hafizabad 20.000 9.978 3.333 3.333 2.500 2.459 98% 12.437 62% progress. Hafizabad Construction of Streets Drains PCC/ Soling A.A. 25.000 (M) T.S. 25.000 (M) work is in 1111 2714 and Nallah In Village Tali Goraya and Jasso Hafizabad 25.000 9.763 5.000 5.000 3.750 3.660 98% 13.423 54% progress. ke District Hafizabad Construction of Streets Drains PCC/ Soling A.A. 20.000 (M) T.S. 20.000 (M) work in 1112 2715 and Nallah In Village Narowal Dera Jaat Hafizabad 20.000 10.000 3.333 3.333 2.500 2.450 98% 12.450 62% progress. District Hafizabad Construction of Streets Drains PCC/ Soling A.A. 15.000 (M) T.S. 15.000 (M) work is in 1113 2716 and Nallah In Village Chak No. 474 District Hafizabad 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% progress. Hafizabad Construction of Streets Drains PCC/ Soling A.A. 15.000 (M) T.S. 15.000 (M) work is in 1114 2717 and Nallah In Village Matay Ke District Hafizabad 15.000 9.719 1.667 1.667 0.750 0.730 97% 10.449 70% progress. Hafizabad Construction of Streets Drains PCC/ Soling A.A. 15.000 (M) T.S.15.000 (M) work is in 1115 2718 and Nallah In Village Badr Ali District Hafizabad 15.000 9.942 1.667 1.667 1.250 1.200 96% 11.142 74% progress. Hafizabad Construction of Streets Drains PCC/ Soling A.A. 15.000 (M) T.S.15.000 (M) work is in 1116 2719 and Nallah In Village Mustafa Abad District Hafizabad 15.000 9.959 1.667 1.667 2.284 2.242 98% 12.201 81% progress. Hafizabad Provision of Water Filtration Plant / A.A. 36.585 (M) T.S.36.585 (M) work is in 1117 2720 Drainage System Kolo Tarar U/C no. 8, Hafizabad 36.585 11.209 3.333 3.333 2.500 2.500 100% 13.709 37% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 31.854 (M) T.S.31.854 (M) work is in 1118 2721 Drainage System Kot Said Muhammad U/C Hafizabad 31.854 11.999 3.333 3.333 2.500 2.452 98% 14.451 45% progress. No. 1, District Hafizabad Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of Water Filtration Plant / A.A. 27.539 (M) T.S.27.539 (M) work is in 1119 2722 Drainage System, Kot Ishaq U/C No. 2, Hafizabad 27.539 13.000 4.846 4.846 3.635 3.610 99% 16.610 60% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 61.830 (M) T.S.61.830 (M) work is in 1120 2723 Drainage System Vanike Tarar U/C No. 3, Hafizabad 61.830 20.000 6.667 6.667 5.000 4.912 98% 24.912 40% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 38.225 (M) T.S.38.225 (M) work is in 1121 2724 Drainage System Alaudinkey U/C no. 4, Hafizabad 38.225 15.920 3.333 3.333 2.500 2.451 98% 18.371 48% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 33.136(M) T.S.33.136 (M) work is in 1122 2725 Drainage System Sooianwala U/C No. 5, Hafizabad 33.136 11.907 3.333 3.333 2.500 2.450 98% 14.357 43% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 31.145(M) T.S.31.145 (M) work is in 1123 2726 Drainage SystemRamke Chatha U/C no. 6, Hafizabad 31.145 12.000 3.333 3.333 2.500 2.500 100% 14.500 47% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 42.320(M) T.S.42.320 (M) work is in 1124 2727 Drainage System Dhiranke Lalke U/C no. 7, Hafizabad 42.320 20.000 3.333 3.333 2.500 2.500 100% 22.500 53% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 32.850(M) T.S.32.850 (M) work is in 1125 2728 Drainage System Sandhwan Tarar U/C no. Hafizabad 32.850 12.000 3.333 3.333 2.500 2.450 98% 14.450 44% progress. 9, District Hafizabad Provision of Water Filtration Plant / A.A. 30.049(M) T.S.30.049 (M) work is in 1126 2729 Drainage System Pind Bawray U/C no. 10, Hafizabad 30.049 10.000 3.333 3.333 2.500 2.450 98% 12.450 41% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 32.850(M) T.S.32.850 (M) work is in 1127 2730 Drainage System Sagar Kalan U/C No. 12, Hafizabad 28.414 10.000 6.138 6.138 4.604 4.500 98% 14.500 51% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 34.675(M) T.S.34.675 (M) work is in 1128 2731 Drainage System Dhunni U/C No. 14, Hafizabad 34.675 11.996 3.333 3.333 0.833 0.820 98% 12.816 37% progress. District Hafizabad Provision of Water Filtration Plant / A.A.29.334(M) T.S.29.334 (M) work is in 1129 2732 Drainage System Kalianwala U/C no. 11, Hafizabad 29.334 12.000 5.778 5.778 2.684 2.580 96% 14.580 50% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 28.045(M) T.S.28.045(M) work is in 1130 2733 Drainage System Karyala U/C no. 19, Hafizabad 28.045 12.000 5.348 5.348 7.061 7.061 100% 19.061 68% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 34.935(M) T.S.34.935 (M) work is in 1131 2734 Drainage System kassoke U/C no. 20, Hafizabad 34.935 12.000 3.333 3.333 2.500 2.450 98% 14.450 41% progress. District Hafizabad Provision of Water Filtration Plant / A.A. 27.257(M) T.S.27.257 (M) work is in 1132 2735 Drainage System Vinni U/C no. 16, District Hafizabad 27.257 10.000 5.752 5.752 4.314 4.313 100% 14.313 53% progress. Hafizabad Provision of Water Filtration Plant / A.A. 29.376(M) T.S.29.376 (M) work is in 1133 2736 Drainage System Solangi Awan U/C no. 17, Hafizabad 29.376 10.000 3.333 3.333 2.500 2.450 98% 12.450 42% progress. District Hafizabad Provision of Water Filtration Plant / 1134 2737 Hafizabad 47.862 19.864 3.333 3.333 2.500 2.500 100% 22.364 47% A.A. 47.862(M) T.S.47.862 (M) work is in Drainage System Kot Nakka progress. Provision of Water Filtration Plant / 1135 2738 Hafizabad 29.486 9.971 3.333 3.333 2.500 2.451 98% 12.422 42% A.A. 29.486(M) T.S.29.486 (M) work is in Drainage System Khana Bhattian progress. Provision of Water Filtration Plant / 1136 2739 Hafizabad 35.920 14.993 3.333 3.333 2.500 2.500 100% 17.493 49% A.A. 35.920(M) T.S.35.920 (M) work is in Drainage System Thata Jhaid Amirwala progress. Provision of Water Filtration Plant / 1137 2740 Hafizabad 32.026 11.910 3.333 3.333 2.500 2.500 100% 14.410 45% A.A. 32.026(M) T.S.32.026 (M) work is in Drainage System North progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of Water Filtration Plant / 1138 2741 Hafizabad 53.655 20.000 3.333 3.333 2.500 2.500 100% 22.500 42% A.A. 53.655(M) T.S.53.655 (M) work is in Drainage System Kot Sarwer progress. Provision of Water Filtration Plant / 1139 2742 Hafizabad 25.650 10.000 5.217 5.217 3.913 3.913 100% 13.913 54% A.A. 25.650(M) T.S.25.650 (M) work is in Drainage System Mowan Bhattian progress. Provision of Water Filtration Plant / A.A. 30.000(M) T.S.30.000 (M) work is in 1140 2743 Drainage System Jalal Pur Bhattian in Hafizabad 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% progress. District Hafizabad Construction of PCC Street/ Drain, Soling A.A Date =28.7.2017.Drain Type-I=6937 1141 2744 and Nullah in UC Fatta Band Tehsil Kharian Gujrat 20.027 10.000 3.342 3.342 2.507 2.507 100% 12.507 62% Rft. PCC. 1:2:4=1000 Cft.Soling= 2741sft District Gujrat .Work in progress. Construction of PCC Street/ Drain, Soling and Nullah in U.C's Mirza Tahir, Nona Wali, Bumali, Kolian Shah Hussain, Jora A.A Date =28.8.2017.Drain Type-I=6359 1142 2745 Kamana, Haji Muhammad, Sikaryali, Gujrat 69.000 19.985 3.333 3.333 2.500 2.500 100% 22.485 33% Rft. PCC. 1:2:4=43123 Cft.Soling= 8900 Chakori Bhailwal, Warraichanwala, sft.Nullah 2x2=400 Rft.Work in progress. Nagranwala, Ali Chak, Kulewa, Taplyala, Chak Pind in Tehsil Kharian

Provisino of Sewerage / Drainage / Soling A.A Date =28.8.2017.Drain Type-I=4629 1143 2746 etc in Various UC's in PP-113, District Gujrat 50.000 25.000 1.667 1.667 1.250 1.250 100% 26.250 53% Rft. PCC. 1:2:4=46666 Cft.Soling= 15646 Gujrat sft .Nullah 2'x2'=100.Work in progress.

Exten: Construction of PCC Street / Drain, A.A Date =28.8.2017.1 Nos T/Well installed. Soling, Nullah and Eten: of Water Supply 1144 2747 Gujrat 81.151 22.000 3.333 3.333 2.500 2.500 100% 24.500 30% Pipe 6"=10384 Rft, 4"=5678 Rft, 3'=14560 Scheme Fath Bhand Tehsil Kharian District rft. Soling=34508 sft, Nullah 2'x2'=1019 Rft. Gujrat Work in porgress. Rural Water Supply and Drainage Scheme 1 Nos T/Well installed.PVC Pipe of dias 3" 1145 2748 Gujrat 30.000 9.748 3.333 3.333 2.500 2.500 100% 12.248 41% =18613 Rft,4"= 5789 Rft,6"= 3074 Rft.PCC Morala Tehsil Kharian District Gujrat 6581 Cft. Work in porgress.

Construction of PCC Street / Drain, Soling and Nullah in U.C Gunjah, Thekarian Matwanawala, Miana Chak, Punjan A.A Date =28.8.2017.Drain Type-I=9351 1146 2749 Khasana, Khawaspur, Bhaddhar, Kotla Gujrat 60.990 20.000 3.333 3.333 2.500 2.500 100% 22.500 37% Rft. PCC. 1:2:4=41644 Cft.Soling= 17354 Qasim Khan, Chakor Sher Ghazi, Deona sft .Tuff paver=4727. Work in progress. Mandi, 1 & 2 Dinga, Addowal, Saroki, Machiana in Tehsil Kharian Distric

Construction of PCC Street / Drain, Soling A.A Date =28.7.2017.Drain Type-I= 1919 1147 2750 and Nullah in U.C 1 to 4 Lalamusa City Gujrat 18.400 10.000 2.800 2.800 2.100 2.100 100% 12.100 66% Rft. PCC. 1:2:4=18061 Cft .Tuff Tehsil Kharian District Gujrat paver=16112. Work in progress.

Construction of PCC Street/ Drain, Soling and Nullah in Bagrianwala, Baho Ghaseet A.A Date =28.7.2017.Drain Type-I=8360 1148 2751 Gujrat 27.604 15.000 3.333 3.333 2.500 2.500 100% 17.500 63% Rft. PCC. 1:2:4=28683 Cft.Work in Pur, Sheikh Sukha, Sabowal, Amra Kalan, progress. Chak Jani in Tehsil Kharian District Gujrat

Provision of Streets and Drains in UC's Chak Sada, Mandhiyala, Thatha Musa, Chopala, Bharaj, Thim Ke, Manju Chak, A.A Date =28.8.2017.Drain Type-I=11013 1149 2752 Gujrat 60.000 22.000 3.333 3.333 5.000 5.000 100% 27.000 45% Rft. PCC. 1:2:4=52777 Cft.Sullage Ikhlas Garh, Fateh Pur, Daulta Nagar, Alam Carriar=1470 Rft.Work in progress. Garh, Doga, Chachian, Jaura Jalalpur and Dhuma Malka District Gujrat Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Sewerage Scheme Jail Chowk to Bhimber A.A Date =17.3.2018. construction of 1150 2753 Gujrat 249.994 49.952 3.333 3.333 2.500 2.500 100% 52.452 21% pumping chamber and collecting Tank is in Nullah, Gujrat City District Gujrat progress. Construction of Nallahs in city Sarai Alamgir 1151 2754 Gujrat 82.600 22.195 3.333 3.333 1.580 1.580 100% 23.775 29% PCC.1:2:4=63409 Cft. S.C= 1200 Rft. Work District Gujrat in progress. Provision of Sewerage / Drainage and A.A Date =29.12.2017.Drain Type-I= 17586 Rft. PCC. 1:2:4=98231Cft.Tuff paver= 1152 2755 streets / Tuff Tiles etc in various UCs, Gujrat 480.000 44.979 6.667 6.667 19.420 19.420 100% 64.399 13% 54208 sft .Nullah 1.5'x1.5'= 1829.RCC District Gujrat pavement=13580.5 cft.Work in progress. Sewerage / Drainage / PCC & Brick Pavement Scheme in villages Adda

PharIanwall, HaIgher * A.A Date. 28.07.2017* T.S Date. Khurd,Haslanwala,pindl Kalu,Loha Tibba Mandi 1153 2756 30.000 11.977 3.333 3.333 4.500 4.500 100% 16.477 55% 15.08.2017* Start Date. 06.01.2018* ,Chak Jano Khurd, Thatha Hast, Luk, Bahauddin Completion date 05.01.2019* Work in Thatha Pheray, Rajoa, Baghanwala,kot progress. Sattar Duborji, Kotli Qazl, Sandanwala, Charranwala a Sewerage / Drainage / PCC & Brick Pavement Scheme in villages kailu, tuggal, channi syedian, Ratoo, bahri, Chak Kamal, * A.A Date. 28.07.2017* T.S Date. Mandi 1154 2757 Melu Mahi Gheran, Aghroa, Kotha Bhola, 30.000 9.021 3.333 3.333 2.500 2.500 100% 11.521 38% 15.08.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2019* Work in Maseetwali Komokay, Chak Mitha, progress. Heigherwala, Kot Phollay shah, Chak Zahir, Bahu, Manga, Arzani, S Construction of Street Drains, Soling and

PCC in Village Gajjan, Slianman, Kot * A.A Date. 28.07.2017* T.S Date. Hamid Shah, Jhanda Chohan, Rasul Pur, Mandi 1155 2758 23.000 8.494 4.333 4.333 3.250 3.250 100% 11.744 51% 15.08.2017* Start Date. 06.01.2018* Chicheranwali, Bhinder Kalan, Bhinder Bahauddin Completion date 05.01.2019* Work in Khurd, Chakora, Thatha Alia and Thatha progress. Naik District M B Din Construction of Street Drains, Soling and PCC in Village Bhagat, Thathi Mureed * A.A Date. 28.07.2017* T.S Date. Mandi 1156 2759 Sahnpal, Channi Sahnpal, Ranaml, Sharif 26.500 14.991 3.833 3.833 3.275 3.275 100% 18.266 69% 15.08.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2019* Work in Channi Mahram, Qila Attar Singh, Ghagoki progress. and Sarang District M B Din Construction of Street Drains, Soling and PCC in Village Narrang, Saad Ullah Pur, * A.A Date. 28.07.2017* T.S Date. Mandi 1157 2760 Kot Pejo, Karamawala, Dhudra, Long 26.000 9.541 5.333 5.333 5.290 5.290 100% 14.831 57% 15.08.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2019* Work in Charrhkey, Khoosar and Pindi Dotharan progress. District M B Din Construction of Street Drains, Soling and PCC in Village Dhaul, Kotly Khurd, Khiyyan, * A.A Date. 28.07.2017* T.S Date. Mandi 1158 2761 Chak Jano New Abadies, Addu Sarwani, 31.500 9.595 7.167 7.167 9.725 9.725 100% 19.320 61% 15.08.2017* Start Date. 06.01.2018* Bahauddin Completion date 05.01.2019* Work in Sheikh Alipur, Ransikey, Pahrianwali, progress. Sainthal and saida Saghar District M B Din Construction of PCC / Drainage, UC 1159 2762 Sialkot 20.000 10.000 3.333 3.333 3.783 3.783 100% 13.783 69% Work in progress. Chobara District Sialkot Construction of PCC / Drainage, US Kingra 1160 2763 Sialkot 20.000 10.000 3.333 3.333 1.000 1.000 100% 11.000 55% Work in progress. District Sialkot Construction of PCC / Drainage, UC Dogri 1161 2764 Sialkot 15.000 7.500 2.500 2.500 1.875 1.875 100% 9.375 63% Work in progress. District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC / Drainage, UC 1162 2765 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Balagan District Sialkot Construction of PCC / Drainage, UC 1163 2766 Sialkot 20.000 10.000 3.333 3.333 1.500 1.500 100% 11.500 58% Work in progress. Malipur District Sialkot Construction of PCC / Drainage, UC 1164 2767 Sialkot 20.000 9.100 3.333 3.333 1.300 1.300 100% 10.400 52% Work in progress. Talawandi, District Sialkot Construction of PCC / Drainage, UC 1165 2768 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Chacharwali District Sialkot Construction of PCC / Drainage, UC 1166 2769 Sialkot 20.000 10.000 3.333 3.333 0.200 0.200 100% 10.200 51% Work in progress. Klasswala, District Sialkot Construction of PCC / Drainage, UC 1167 2770 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Jodhala, District Sialkot Construction of PCC, Street Drain/ Nullah Village Kundan Pur Bashmola Tahthi 1168 2771 Sialkot 48.000 18.000 3.333 3.333 2.500 2.500 100% 20.500 43% Work in progress. Minderwal, Chan, Khany Chak, Kajlewal, Mahal Tajer, Ossomata and Khurra

Construction of PCC, Street Drain/ Nullah Village Chakrala Bashmula Machrala, 1169 2772 Sialkot 49.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 46% Work in progress. Nandpurn Rang Khokhran, Lalian, Gaiat, Bahadur and Madina Town. Construction of PCC, Streets Drains, Tuff 1170 2773 Tiles and Soling in UC Marakiwall in District Sialkot 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. Sialkot. Construction of PCC, Streets Drains, Tuff 1171 2774 Tiles and Soling in UC Berth in District Sialkot 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. Sialkot Construction of PCC, Streets Drains, Tuff 1172 2775 Tiles and Soling in UC Booth in District Sialkot 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. Sialkot Construction of PCC, Streets Drains, Tuff 1173 2776 Tiles and Soling in UC Machranal in District Sialkot 12.000 9.000 1.000 1.000 0.750 0.750 100% 9.750 81% Work in progress. Sialkot Construction of Streets / Drain / Nullah / 1174 2777 Soling / Tuff Tiles / PCC at UC Dhilum Sialkot 25.000 8.000 1.667 1.667 1.250 1.250 100% 9.250 37% Work in progress. Balagon, District Sialkot Construction of Streets / Drain / Nullah / Soling / Tuff Tiles / PCC at Fardaus Pura, 1175 2778 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Nand Garh, Wan, Dhoop Sarri, Kotli Miani, Malkhanwala, District Sialkot Construction of Streets / Drain / Nullah / 1176 2779 Soling / Tuff Tiles / PCC at UC Bhopalwala Sialkot 50.000 19.399 3.333 3.333 2.500 2.500 100% 21.899 44% Work in progress. Tehsil Sambrial, District Sialkot Construction of Streets / Drain / Nullah / 1177 2780 Soling / Tuff Tiles / PCC at UC Alleali, Sialkot 20.000 7.000 1.667 1.667 1.250 1.250 100% 8.250 41% Work in progress. District Sialkot Construction of Streets / Drain / Nullah / Soling / Tuff Tiles / PCC at Villages Mundair 1178 2781 Sialkot 25.000 8.000 1.667 1.667 1.250 1.250 100% 9.250 37% Work in progress. Syedian, Mundair Khothay, Roras, Sohowala, Kharolian etc., District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Streets / Drain / Nullah / 1179 2782 Soling / Tuff Tiles / PCC at UC Berowala Sialkot 40.000 12.000 3.333 3.333 2.500 2.500 100% 14.500 36% Work in progress. Tehsil Daska, District Sialkot Construction of Streets / Drain / Nullah / 1180 2783 Soling / Tuff Tiles / PCC at UC Bagowala , Sialkot 20.000 7.000 1.667 1.667 1.250 1.250 100% 8.250 41% Work in progress. District Sialkot Construction of Streets / Drain / Nullah / 1181 2784 Soling / Tuff Tiles / PCC at UC Ghuinke, Sialkot 149.892 20.000 3.333 3.333 2.500 2.500 100% 22.500 15% Work in progress. District Sialkot Construction of Streets / Drain / Nullah / 1182 2785 Soling / Tuff Tiles / PCC at UC Bharokey, Sialkot 40.000 12.000 3.333 3.333 2.500 2.500 100% 14.500 36% Work in progress. District Sialkot Construction of sewerage, Nallah, PCC at 1183 2786 Sialkot 20.000 11.000 3.000 3.000 2.250 2.250 100% 13.250 66% Work in progress. UC Prochak and Alo Mahr District Sialkot.

Construction of Streets / Sewerage / Tuff 1184 2787 Sialkot 100.000 29.967 3.333 23.333 22.500 2.500 11% 32.467 32% Work in progress. Tile/ PCC/ Soling in Rural UC's of NA-113

Construction of PCC, Soling / Drains in 1185 2788 Sialkot 20.000 10.000 3.333 10.000 9.167 2.500 27% 12.500 63% Work in progress. Villages of UC in Ghutalian District Sialkot Construction of PCC, Soling / Drains in 1186 2789 Villages of UC in Chichar wali District Sialkot 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. Sialkot Construction of PCC, Soling / Drains in 1187 2790 Villages of UC in Pejoke Qila Kalarwala Sialkot 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. District Sialkot Construction of Streets, Nullah, PCC, Soling at villages Jasso Wali Pun, Sahn Gill, pajokay, Mehmand Wali, Rata jathool, 1188 2791 Baso Panu, alawal Pur, Loharan Wali, Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Jhangi Shah Khaki, Jhans, Sodian, Bhuda, Peera Baryar, Charwind, Deehr, Bhojo, Alkry, Kala Pahar,

Construction of PCC, Soling / Drains in 1189 2792 Sialkot 25.000 12.000 1.667 1.667 1.250 1.250 100% 13.250 53% Work in progress. Villages of UC Sokan Wind District Sialkot

Construction of Streets, Drains PCC/ Soling / Tuff Tiles in Villages of UC's Kanwanlit, Adamkey Cheema, Raja Gamman, 1190 2793 Sialkot 120.000 45.000 3.333 3.333 2.500 2.500 100% 47.500 40% Work in progress. Galotian Kalan, Galotian Khurd, Goindkey, Banbanwala, Bharokey and Mitranwali Tehsil Daska District Sialkot Constructon of Streets / Drain / Nullah / 1191 2794 Soling at UC, Moongar, Baqarpur, Pindi Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Khokharn etc., District Sialkot Constructon of Streets / Drain / Nullah / 1192 2795 Soling at, UC Kapoor Wali and Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Khamberwala District Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Constructon of Streets / Drain / Nullah / 1193 2796 Soling at Village Satab Garah, Butter, Sialkot 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Work in progress. Dhanney, Ganjaniwali etc. District Sialkot Construction of Street / Swerage / Tuff Tile 1194 2797 Sialkot 50.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 45% Work in progress. ETC in City Daska District Sialkot Construction of PCC/Streets/Nalian at U.C. 1195 2798 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Syedanwali District Sialkot Construction of PCC/Streets/Nalian at 1196 2799 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. U.C.Pargpur District Sialkot Construction of PCC/Streets/Nalian at U.C. 1197 2800 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Vario District Sialkot Construction of PCC/Streets/Nalian at U.C 1198 2801 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Rasoolpur Balian District Sialkot Providing & Laying of Tuff Tile PCC and 1199 2802 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Drainge Lines in UC Kotli Barham Providing & Laying of Tuff Tile PCC and 1200 2803 Sialkot 30.000 15.000 1.667 1.667 1.250 1.250 100% 16.250 54% Work in progress. Drainge Lines in UC Paka Garh Providing & Laying of Tuff Tile PCC and 1201 2804 Sialkot 30.000 15.000 1.667 1.667 1.250 1.250 100% 16.250 54% Work in progress. Drainge Lines in UC Maina Pura Providing & Laying of Tuff Tile PCC and 1202 2805 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Drainge Lines in UC Muzafar Pur Providing & Laying of Tuff Tile PCC and 1203 2806 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Drainge Lines in UC Fathegarh Providing & Laying of Tuff Tile PCC and 1204 2807 Sialkot 20.000 9.995 3.333 3.333 2.500 2.500 100% 12.495 62% Work in progress. Drainge Lines in UC Haji Pura Ban Providing & Laying of Tuff Tile PCC and 1205 2808 Sialkot 20.000 9.986 3.333 3.333 0.200 0.200 100% 10.186 51% Work in progress. Drainge Lines in UC Imam Saheb Providing & Laying of Tuff Tile PCC and 1206 2809 Sialkot 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work in progress. Drainge Lines in UC Mubarik Pura Provision of PCC / Sewerage / Tuff Tiles / 1207 2810 Drainage and allied facilities in PP-122, Sialkot 100.000 44.992 3.333 3.333 2.500 2.500 100% 47.492 47% Work in progress. District Sialkot Provision of PCC / Sewerage / Tuff Tiles / 1208 2811 Drainage and allied facilities in PP-123, Sialkot 199.950 100.000 3.333 3.333 2.500 2.500 100% 102.500 51% Work in progress. District Sialkot Construction of PCC, Street Drain/ Nullah Village Jallian Wala Bashamula Moma 1209 2812 Sialkot 47.000 18.000 3.333 3.333 2.500 2.500 100% 20.500 44% Work in progress. Khurd, Kalan Virkan, Dulchikay, Lodhary Dogranwala and Rai Pur. Construction of PCC, Street Drain/ Nullah Village Ghari Gondal Bashmula Ahmal Pur, 1210 2813 Sialkot 47.000 17.936 1.667 1.667 1.250 1.250 100% 19.186 41% Work in progress. Sarhall, Hadali, Minal Pathan, Bazpur and Romal Juttan. Construction of PCC, Street Drain/ Nullah 1211 2814 Village Baghwal Awan Bashmula Harar, Sialkot 46.000 17.956 5.000 5.000 1.350 1.350 100% 19.306 42% Work in progress. Noul, Dumbola and Dogran. Construction of sewerage, Nallah, PCC at 1212 2815 UC Jaranwala and Barthanwala, District Sialkot 20.000 11.000 3.000 3.000 2.250 2.250 100% 13.250 66% Work in progress. Sialkot Construction of sewerage, Nallah, PCC at 1213 2816 UC Salhokay and Bhuda Gorya, District Sialkot 20.000 10.938 3.000 3.000 2.250 2.250 100% 13.188 66% Work in progress. Sialkot Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of sewerage, Nallah, PCC at 1214 2817 UC Mundekay Gorya and Malomay, District Sialkot 20.000 11.000 3.000 3.000 2.250 2.250 100% 13.250 66% Work in progress. Sialkot Construction of sewerage, Nallah, PCC at 1215 2818 Sialkot 20.000 11.000 3.000 3.000 2.250 2.250 100% 13.250 66% Work in progress. UC Boghray and Seo Ke, District Sialkot.

Construction of sewerage, Nallah, PCC at 1216 2819 Sialkot 20.000 12.000 2.667 2.667 2.000 2.000 100% 14.000 70% Work in progress. UC Adha and Sehjo Kala District Sialkot. Construction of sewerage, Nallah, PCC at 1217 2820 UC Ghuainkey and Badoke Cheema, Sialkot 15.000 9.941 1.667 1.667 1.250 1.250 100% 11.191 75% Work in progress. District Sialkot. Construction of sewerage, Nallah, PCC at 1218 2821 UC Jamkay Cheema and Kanwanliq, Sialkot 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Work in progress. District Sialkot. Construction Street Drain PCC / and Nullah 1219 2822 Sialkot 20.000 10.000 3.333 3.333 4.534 4.534 100% 14.534 73% Work in progress. U/C Jaithke Construction of Street Drain PCC / and 1220 2823 Sialkot 20.000 9.920 3.333 3.333 2.500 2.500 100% 12.420 62% Work in progress. Nullah U/C Kopra Providing & Laying of Tuff Tile PCC and 1221 2824 Sialkot 40.000 14.963 3.333 3.333 3.500 3.500 100% 18.463 46% Work in progress. Drainge Lines in UC Dalowali Providing & Laying of Tuff Tile PCC and 1222 2825 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Drainge Lines in UC Talwara Providing & Laying of Tuff Tile PCC and 1223 2826 Sialkot 20.000 9.968 3.333 3.333 2.500 2.500 100% 12.468 62% Work in progress. Drainge Lines in UC Pindi Arian Providing & Laying of Tuff Tile PCC and 1224 2827 Sialkot 30.000 9.920 1.667 1.667 1.250 1.250 100% 11.170 37% Work in progress. Drainge Lines in UC Hamza Ghous Providing & Laying of Tuff Tile PCC and 1225 2828 Sialkot 20.000 9.987 3.333 3.333 2.500 2.500 100% 12.487 62% Work in progress. Drainge Lines in UC Naika Pura Providing & Laying of Tuff Tile PCC and 1226 2829 Sialkot 20.000 9.937 3.333 3.333 2.500 2.500 100% 12.437 62% Work in progress. Drainge Lines in UC Duborji Arian Providing & Laying of Tuff Tile PCC and 1227 2830 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Drainge Lines in UC Ahmed Pura Providing & Laying of Tuff Tile PCC and 1228 2831 Sialkot 20.000 9.970 3.333 3.333 2.500 2.500 100% 12.470 62% Work in progress. Drainge Lines in UC Pura Hiran Providing & Laying of Tuff Tile PCC and 1229 2832 Sialkot 40.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 44% Work in progress. Drainge Lines in UC Rangpura Providing & Laying of Tuff Tile PCC and 1230 2833 Sialkot 20.000 9.700 3.333 3.333 2.500 2.500 100% 12.200 61% Work in progress. Drainge Lines in UC Islam Abad Construction of Street Drain PCC/ and 1231 2834 Sialkot 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Work in progress. Nullah UC Majra Kalan Construction of Street Drain PCC / and 1232 2835 Sialkot 20.000 10.000 3.333 3.333 7.500 7.500 100% 17.500 88% Work in progress. Nullah U/C Village Srankey Construction of Street Drain PCC/ and 1233 2836 Sialkot 80.000 30.000 1.667 1.667 1.250 1.250 100% 31.250 39% Work in progress. Nullah U/C’s Verowala, Halewai, Habibpur Construction of sewerage, PCC, Tuff Tile, 1234 2837 Sialkot 50.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 45% Work in progress. District Sialkot Construction of PCC & Drains in Village 1235 2838 Sialkot 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Work in progress. Chobara U/C Chobara District Sialkot Construction of Drainage System, PCC and A.A. dated 07.08.2017T.S. dated 08.08.2017*Start Date 1236 2839 Brick Pavement in Villages of UC Rupo Narowal 12.000 4.993 2.000 2.000 1.250 1.225 98% 6.218 52% 28.09.2017*Completion date 27.03.2018 Chak Tehsil Zafarwal District Narowal work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated 07.01.2017 *Start Date 27.10.2017 1237 2840 Datewal, Mangolay, Hallowal, Dhrug Miana Narowal 30.000 12.308 3.333 3.333 2.500 2.496 100% 14.804 49% *Completion date 26.04.2018. work in and Ghota Fateh Garh District Narowal progress.

Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated 12.08.2017 *Start Date 27.10.2017 1238 2841 Talwandi Bhindran, Giddan, Niddokay, Kot Narowal 30.000 9.960 3.333 3.333 2.500 2.493 100% 12.453 42% *Completion date 26.04.2018. Work in Lakha Singh and Domala, District Narowal progress.

Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated Khan Kassa, Dongian, Bubak Murali, 1239 2842 Narowal 30.000 9.871 3.333 3.333 2.500 2.481 99% 12.352 41% 12.08.2017 *Start Date 26.09.2017 Sadowala Uncha and Falezpur District *Completion date 25.03.2018. Work in Narowal progress. Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated 07.01.2017 *Start Date 26.09.2017 1240 2843 Ahmadabad, Depokey, Jestiwala, Uncha, Narowal 30.000 9.940 3.333 3.333 2.500 2.493 100% 12.433 41% *Completion date 25.03.2018 Work in Lala and Nonar, District Narowal progress. Provision of Drains/Soling and PCC in UCs, "A.A. dated 03.08.2017 T.S. dated 12.08.2017 *Start Date 27.10.2017 1241 2844 Mehlu Wala, Dhamthal, Langarkay, Tapiala Narowal 30.000 9.940 3.333 3.333 2.500 2.491 100% 12.431 41% *Completion date 26.04.2018. Work in and Sankhtara District Narowal progress. Provision of PCC/Streets/Nalian at Bado Malihi, Chandarkay, Ransiwal, Manak, "A.A. dated 19.10.17 T.S. dated 27.10.2017*Start Date 13.12.2017 1242 2845 Qayampur, Agrian, Pungarian, Salukay, Narowal 130.000 34.991 6.667 6.667 5.000 4.987 100% 39.978 31% *Completion date 12.12.2019 Work in Dawod, Chundowal, Klass Gorya, progress. Muhammad Rana Wala District Narowal

Provision of Tuff Tile from Zafarwal bypass "A.A Date.03.08.2017 T.S Date*18.09.2017 1243 2846 Narowal 22.000 9.965 4.000 4.000 3.000 2.997 100% 12.962 59% Start Date 28.09.2017*Completion date to Chowk Ghas Mandi, District Narowal 27.03.2018. Work in progress.

Construction of Drainage System, PCC and A.A. dated 03.08.17 T.S. dated 08.08.2017*Start Date 1244 2847 Brick Pavement in Villages of Jandiala Narowal 15.000 4.993 3.333 3.333 2.250 2.201 98% 7.194 48% 18.10.2017*Completion date 17.04.2018 Tehsil Zafarwal District Narowal Work in progress

Provision of PCC / Sewerage / Drainage "A.A. dated 03.08.17 T.S. dated 08.08.2017 1245 2848 Narowal 25.000 9.812 1.667 1.667 1.250 1.245 100% 11.057 44% *Start Date 27.10.2017 *Completion date etc. in PP-133, District Narowal 26.10.2018. Work in progress. PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1246 2849 Lahore 50.000 38.992 3.667 3.667 6.090 6.090 100% 45.082 90% funds are required to clear the contractor's UC-273, Raiwind City, Lhr liability. PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1247 2850 Lahore 50.000 39.986 3.333 3.333 2.500 2.500 100% 42.486 85% funds are required to clear the contractor's UC-112, Mustafa Town, liability. Provision of PCC & Drainage Facilities in 1248 2851 Lahore 50.000 40.000 3.333 3.333 0.027 0.027 100% 40.027 80% Scheme completed Attari & allied abadies. Provision of PCC & Drainage Facilities in Work stopped due to Court Case. Stay 1249 2852 Youhanabad, Dhullu Kalan & Khurd & allied Lahore 50.000 39.987 3.333 3.333 2.260 0.035 2% 40.022 80% order vacated on 29.4.2019, now work will abadies. be commenced. Provision of PCC & Drainage Facilities in 1250 2853 Lahore 50.000 40.000 3.333 3.333 0.027 0.027 100% 40.027 80% Scheme completed Gajjumatta & allied abadies. Provision of PCC & Drainage Facilities in 1251 2854 Lahore 50.000 40.000 3.333 3.333 0.100 0.100 100% 40.100 80% Scheme completed Bhallar & allied abadies. Provision of PCC & Drainage Facilities in 1252 2855 Lahore 50.000 40.000 3.333 3.333 0.030 0.030 100% 40.030 80% Scheme completed Dhalloki & allied abadies. Provision of PCC & Drainage Facilities in 1253 2856 Lahore 50.000 40.000 3.333 3.333 0.900 0.900 100% 40.900 82% Scheme completed Jhulkey & allied abadies. Provision of PCC & Drainage Facilities in 1254 2857 Lahore 50.000 40.000 3.333 3.333 1.640 1.640 100% 41.640 83% Scheme Completed Jaman and Gawind & allied abadies. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of PCC & Drainage Facilities in 1255 2858 Lahore 50.000 40.000 3.333 3.333 0.070 0.070 100% 40.070 80% Scheme completed Shahzada & allied abadies. Provision of PCC & Drainage Facilities in 1256 2859 Lahore 50.000 40.000 3.333 3.333 0.050 0.050 100% 40.050 80% Scheme completed Jia Bhagga & allied abadies. Provision of PCC & Drainage Facilities in 1257 2860 Lahore 50.000 40.000 3.333 3.333 0.027 0.027 100% 40.027 80% Scheme completed Pandoki & allied abadies. Provision of PCC & Drainage Facilities in 1258 2861 Lahore 73.000 54.100 3.333 3.333 0.080 0.080 100% 54.180 74% Scheme completed Hair & allied abadies. Construction of Sewerage and Disposal 1259 2862 Lahore 50.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 45% Work stopped due to awaiting funds. Manawan Sky Land & Abadies Construction of PCC/Sewerage and Link 1260 2863 Lahore 50.000 34.992 5.000 5.000 3.750 3.750 100% 38.742 77% Work stopped due to awaiting funds. Streets UC-147 Lahore. Construction of PCC/Sewerage and Link 1261 2864 Lahore 50.000 39.992 3.333 3.333 2.500 2.500 100% 42.492 85% Work stopped due to awaiting funds. Streets UC-148 Lahore. Construction of PCC/Sewerage and Link Physically scheme is completed, balance 1262 2865 Lahore 50.000 39.992 3.333 3.333 2.500 2.500 100% 42.492 85% funds are required to clear the contractor's Streets UC-149 Lahore. liability. Construction of PCC/Sewerage and Link 1263 2866 Lahore 50.000 39.992 3.333 3.333 2.300 2.300 100% 42.292 85% Work stopped due to awaiting funds. Streets UC-150 Lahore. Construction of PCC/Sewerage and Link 1264 2867 Lahore 50.000 39.538 3.333 3.333 2.400 2.400 100% 41.938 84% Work stopped due to awaiting funds. Streets UC-151 Lahore. Construction of PCC/Sewerage and Link 1265 2868 Lahore 50.000 39.992 3.333 3.333 2.500 2.500 100% 42.492 85% Work stopped due to awaiting funds. Streets UC-152 Lahore. Construction of PCC/Sewerage and Link 1266 2869 Lahore 50.000 29.984 3.333 3.333 2.500 2.500 100% 32.484 65% Work stopped due to awaiting funds. Streets UC-174 Lahore. Construction of PCC/Sewerage and Link 1267 2870 Lahore 50.000 39.991 3.333 3.333 2.500 2.500 100% 42.491 85% Work stopped due to awaiting funds. Streets UC-175 Lahore. Construction of PCC/Sewerage and Link 1268 2871 Lahore 50.000 39.991 3.333 3.333 2.500 2.500 100% 42.491 85% Work stopped due to awaiting funds. Streets UC-183 Lahore. Construction of PCC/Sewerage and Link 1269 2872 Lahore 50.000 34.968 5.000 5.000 3.750 3.750 100% 38.718 77% Work stopped due to awaiting funds. Streets UC-108 Lahore. Construction of PCC/Sewerage and Link 1270 2873 Lahore 100.000 75.000 5.000 5.000 3.750 3.750 100% 78.750 79% Scheme completed physically, funds are Streets Bhangali Lahore. required to clear the contractor liabilities. PCC & Drainage & Sewerage System at 1271 2874 Lahore 50.000 39.977 3.333 3.333 2.500 2.500 100% 42.477 85% Work stopped due to awaiting funds. UC-110, Niaz Baig Lahore PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1272 2875 Lahore 50.000 39.273 3.573 3.573 3.130 3.130 100% 42.403 85% funds are required to clear the contractor's UC-111, Hunjarwal, Lahore liability. PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1273 2876 Lahore 50.000 39.493 3.500 3.500 2.625 2.625 100% 42.118 84% funds are required to clear the contractor's UC-109, Margzaar Colony, Lahore. liability. PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1274 2877 Lahore 50.000 45.000 1.667 1.667 2.250 2.250 100% 47.250 95% funds are required to clear the contractor's UC-117, Shahpur Kanjran, Lahore. liability. PCC & Drainage & Sewerage System at 1275 2878 Lahore 50.000 29.989 1.667 1.667 1.050 1.050 100% 31.039 62% Work stopped due to awaiting funds. UC-262, Shamke Bhattian, Lahore. PCC & Drainage & Sewerage System at 1276 2879 Lahore 50.000 31.995 1.667 1.667 6.250 6.250 100% 38.245 76% Work stopped due to awaiting funds. UC-255, Sattu Kattla, Lahore PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1277 2880 Lahore 50.000 39.556 3.333 3.333 4.000 4.000 100% 43.556 87% funds are required to clear the contractor's UC-256, Ali Raza Abad, Lahore liability. PCC & Drainage & Sewerage System at Physically scheme is completed, balance 1278 2881 Lahore 50.000 40.000 3.333 3.333 10.000 10.000 100% 50.000 100% funds are required to clear the contractor's UC-272, Raiwind Kalan, Lahore liability. Provision of PCC & Drainage in Streets UC- 1279 2882 Lahore 50.000 39.800 3.333 3.333 1.666 1.666 100% 41.466 83% Work stopped due to awaiting funds. 176 Awan Dhai Wala Lahore. Provision of PCC & Drainage in Streets UC- Physically scheme is completed, balance 1280 2883 Lahore 50.000 39.620 3.333 3.333 2.262 2.262 100% 41.882 84% funds are required to clear the contractor's 190 Hadiara Lahore. liability. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Provision of PCC & Drainage in Streets UC- 1281 2884 Lahore 50.000 39.599 3.333 3.333 4.372 4.372 100% 43.971 88% Work stopped due to awaiting funds. 180 Minhala Kallan Lahore. Provision of PCC & Drainage in Streets UC- 1282 2885 Lahore 50.000 39.977 3.333 3.333 1.700 1.700 100% 41.677 83% Work stopped due to awaiting funds. 181 Wahga Lahore. Provision of PCC & Drainage in Streets UC- 1283 2886 Lahore 50.000 40.000 3.333 3.333 0.037 0.037 100% 40.037 80% Scheme completed 194 Lidhar Lahore. Provision of clean drinking water, sewerage system, PCC and allied facilities in Manga 1284 2887 Lahore 300.000 137.599 8.333 8.333 6.250 6.250 100% 143.849 48% Work stopped due to awaiting funds. Mandi, Raiwind Village and adjoining Abadies. Construction of PCC, Soling, Drain & Nallah Funds fully utilized, work stopped due to 1285 2888 at Tibbi Humbo, UC 64, District Sheikhupura 15.000 2.500 1.667 1.667 1.250 1.250 100% 3.750 25% non-availability of funds Sheikhupura Provision of PCC, Drain, Soling, Nallah & Funds fully utilized, work stopped due to 1286 2889 culvert at UC 87 Farooqabad , District Sheikhupura 20.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 56% non-availability of funds Sheikhupura Provision of PCC, Drain, Soling, Nallah & 1287 2890 Sheikhupura 20.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 56% Funds fully utilized, work stopped due to culvert at UC Ghung, District Sheikhupura non-availability of funds Provision of PCC, Drain, Soling, Nallah & Funds fully utilized, work stopped due to 1288 2891 culvert at UC Nokhar Nau, District Sheikhupura 20.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 56% non-availability of funds Sheikhupura Provision of PCC, Drain, Soling, Nallah & Funds fully utilized, work stopped due to 1289 2892 culvert at UC Sucha Sauda, District Sheikhupura 20.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 56% non-availability of funds Sheikhupura Provision of PCC, Drain, Soling, Nallah & 1290 2893 Sheikhupura 20.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 56% Funds fully utilized, work stopped due to culvert at UC Hardev, District Sheikhupura non-availability of funds

Construction of soling, PCC, Drain & Nallah 1291 2894 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to UC Mojoki Mallian, District Sheikhupura non-availability of funds

Construction of soling, PCC, Drain & Nallah 1292 2895 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to UC Jhamkay, District Sheikhupura non-availability of funds Construction of soling, PCC, Drain & Nallah 1293 2896 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to UC Kalokay, District Sheikhupura non-availability of funds Construction of soling, PCC, Drain & Nallah Funds fully utilized, work stopped due to 1294 2897 UC Rakh Hiran Minara District Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% non-availability of funds Sheikhupura Construction of soling, PCC, Drain & Nallah 1295 2898 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to UC Ghang District Sheikhupura non-availability of funds Construction of soling, PCC, Drain & Nallah Funds fully utilized, work stopped due to 1296 2899 UC Warn Dera Bhikhi Ana District Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% non-availability of funds Sheikhupura Rural drainage & PCC Scheme UC 1297 2900 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to Jhabran, District Sheikhupura non-availability of funds Rural drainage & PCC Scheme UC Ghazi 1298 2901 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to Minara, District Sheikhupura, non-availability of funds Rural drainage & PCC Scheme UC Hardev, 1299 2902 Sheikhupura 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utilized, work stopped due to District Sheikhupura non-availability of funds Construction of PCC, Drain / Soling & Funds fully utilized, work stopped due to 1300 2903 Nallah at UC Kakar Gill, District Sheikhupura 11.000 5.000 2.000 2.000 1.500 1.500 100% 6.500 59% non-availability of funds Sheikhupura Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC, Drain / Soling & Funds fully utilized, work stopped due to 1301 2904 Nallah at UC 83 Jatri Kohna, District Sheikhupura 14.000 5.000 3.000 3.000 2.250 2.250 100% 7.250 52% non-availability of funds Sheikhupura Construction of PCC, Drain / Soling & Funds fully utilized, work stopped due to 1302 2905 Nallah at UC 79 Harchand, District Sheikhupura 12.000 5.000 2.333 2.333 1.750 1.750 100% 6.750 56% non-availability of funds Sheikhupura Construction of PCC, Drain / Soling & Funds fully utilized, work stopped due to 1303 2906 Nallah at UC 81 Sucha Sauda, District Sheikhupura 16.000 5.000 3.667 3.667 2.750 2.750 100% 7.750 48% non-availability of funds Sheikhupura Construction of PCC, Drain / Soling & Funds fully utilized, work stopped due to 1304 2907 Nallah at UC 80 Esherke, District Sheikhupura 14.000 5.000 3.000 3.000 2.250 2.250 100% 7.250 52% non-availability of funds Sheikhupura Construction of PCC, Drain / Soling & Nallah at UC-85, 86 & 87 Farooqabad City 1305 2908 Sheikhupura 55.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 41% Funds fully utilized, work stopped due to & Muridke village UC-70, District non-availability of funds Sheikhupura Construction of PCC, Drain, Soling & Nallah 1306 2909 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utilized, work stopped due to Kala Khatai UC-9, District Sheikhupura non-availability of funds

Construction of PCC, Drain, Soling & Nallah 1307 2910 Sheikhupura 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utilized, work stopped due to Khatiala Virkan UC-18, District Sheikhupura non-availability of funds Construction of PCC, Drain, Soling & Nallah Funds fully utilized, work stopped due to 1308 2911 Sheikhupura Bedad UC-15, District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura Construction of PCC, Drain, Soling & Nallah Funds fully utilized, work stopped due to 1309 2912 Nangal Kaswala UC-14, District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura Construction of PCC, Drain, Soling & Nallah 1310 2913 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utilized, work stopped due to Dharor Muslim UC-13, District Sheikhupura non-availability of funds

Construction of PCC, Drain, Soling & Nallah 1311 2914 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utilized, work stopped due to Ahdian UC-7, District Sheikhupura non-availability of funds

Construction of PCC, Drain, Soling & Nallah 1312 2915 Sheikhupura 12.000 5.000 2.333 2.333 1.750 1.750 100% 6.750 56% Funds fully utilized, work stopped due to Lambray UC-10, District Sheikhupura non-availability of funds Construction of PCC, Drain, Soling & Nallah Funds fully utilized, work stopped due to 1313 2916 Nangal Sahdan UC-11, District Sheikhupura 20.000 5.000 1.667 1.667 1.250 1.250 100% 6.250 31% non-availability of funds Sheikhupura Rural Drainage and Construction of Streets 1314 2917 Sheikhupura 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utilized, work stopped due to Scheme at UC Barth District Sheikhupura. non-availability of funds Rural Drainage and Construction of Streets Funds fully utilized, work stopped due to 1315 2918 Scheme at UC Chak No.22 District Sheikhupura 30.000 19.000 3.667 3.667 2.750 2.750 100% 21.750 73% non-availability of funds Sheikhupura. Rural Drainage and Construction of Streets Funds fully utilized, work stopped due to 1316 2919 Scheme at UC Faizpur Khurd District Sheikhupura 35.000 19.000 1.667 1.667 1.250 1.250 100% 20.250 58% non-availability of funds Sheikhupura. Rural Drainage and Construction of Streets Funds fully utilized, work stopped due to 1317 2920 Scheme at UC Luban Wala District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Rural Drainage and Construction of Streets Funds fully utilized, work stopped due to 1318 2921 Scheme at UC Faizpur Kalan District Sheikhupura 30.000 19.000 3.667 3.667 2.750 2.750 100% 21.750 73% non-availability of funds Sheikhupura. Rural Drainage and Construction of Streets Funds fully utilized, work stopped due to 1319 2922 Scheme at UC Buraj Attari District Sheikhupura 25.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 45% non-availability of funds Sheikhupura. Rural Drainage and Construction of Streets Funds fully utilized, work stopped due to 1320 2923 Scheme at UC Moran Wala District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura. Rural Drainage and Construction of Streets 1321 2924 Scheme at UC Rana Bhati District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Scheme Completed Sheikhupura. Rural Drainage and Construction of Streets Scheme at UC Kashmir Town/Rana Town/ 1322 2925 Sheikhupura 50.000 1.750 3.333 3.333 2.500 2.500 100% 4.250 9% Funds fully utilized, work stopped due to Galkxy Block/ Kot Hadayat/ Haider Road non-availability of funds District Sheikhupura. Rural Drainage and PCC at villages Samolana, Mada Treda, Pherianwala, Funds fully utilized, work stopped due to 1323 2926 Khanni, Jalalpur, Nizampura, Kukripur, Sheikhupura 30.000 15.000 1.667 1.667 1.250 1.250 100% 16.250 54% non-availability of funds Sikhanwala, Jogiwala and adjoinging abdies, District Sheikhupura Construction of PCC, Drains and Nallah at 1324 2927 Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utilized, work stopped due to UC-37 Chak 575 GB District Sheikhupura non-availability of funds

Construction of Rural Draiange PCC & Tuff 1325 2928 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utilized, work stopped due to tiles scheme UC 27, District Sheikhupura non-availability of funds

Construction of Rural Draiange PCC & Tuff 1326 2929 Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utilized, work stopped due to tiles scheme UC 28, District Sheikhupura non-availability of funds

Construction of Rural Draiange PCC & Tuff 1327 2930 Sheikhupura 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Funds fully utilized, work stopped due to tiles scheme UC 29, District Sheikhupura non-availability of funds

Construction of Rural Draiange PCC & Tuff 1328 2931 Sheikhupura 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% Funds fully utilized, work stopped due to tiles scheme UC 30, District Sheikhupura non-availability of funds Construction of Rural drainage PCC & Tuff Funds fully utilized, work stopped due to 1329 2932 tiles scheme UC Rana Bhatti, District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura Construction of Rural drainage PCC & Tuff Funds fully utilized, work stopped due to 1330 2933 tiles scheme UC Mandianwala, District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura Construction of Rural drainage PCC & Tuff Funds fully utilized, work stopped due to 1331 2934 tiles scheme UC Dhamkay, District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura Construction of Rural drainage PCC & Tuff Funds fully utilized, work stopped due to 1332 2935 tiles scheme UC Chak No.22, District Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% non-availability of funds Sheikhupura Urban Drainage and Sewerage Scheme 1333 2936 Sheikhupura 220.000 30.000 1.000 1.000 0.750 0.750 100% 30.750 14% Funds fully utilized, work stopped due to Narang Mandi, District Sheikhupura non-availability of funds Urban Sewerage, Drainage & PCC Scheme Funds fully utilized, work stopped due to 1334 2937 MC Ferozewala, Tehsil Ferozewala, District Sheikhupura 160.000 20.000 5.000 5.000 3.750 3.750 100% 23.750 15% non-availability of funds Sheikhupura Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC, Drain & Nallah 1335 2938 Sheikhupura 100.000 25.000 3.333 3.333 2.500 2.500 100% 27.500 28% Funds fully utilized, work stopped due to Muridke City, District Sheikhupura non-availability of funds Construction of PCC, Drain & Nallah 1336 2939 Sheikhupura 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utilized, work stopped due to Narang City, District Sheikhupura non-availability of funds Sewerage Disposal Station Completed, Demand Notice Paid, Fully funds utilized, Provision of water supply and sewerage / workstopped due to non availability of 1337 2940 Sheikhupura 450.000 17.500 16.667 31.667 12.500 12.500 100% 30.000 7% funds, balance funds are requierd to clear drainage scheme city Sheikhupura the contractors liability, water supply portion not yet started due to non availability of funds. Urban Sewerage, Drainage & PCC Scheme Funds fully utilized, work stopped due to 1338 2941 MC Kot Adbul Malik, Tehsil Ferozewala, Sheikhupura 140.000 15.000 3.333 3.333 2.500 2.500 100% 17.500 13% non-availability of funds. District Sheikhupura Urban Sewerage, Drainage & PCC Scheme Funds fully utilized, work stopped due to 1339 2942 UC Momin Pura, Tehsil Ferozewala, District Sheikhupura 20.000 5.427 4.858 4.858 3.644 3.644 100% 9.071 45% non-availability of funds. Sheikhupura Urban Sewerage, Drainage & PCC Scheme Funds fully utilized, work stopped due to 1340 2943 UC Shamkay, Tehsil Ferozewala, District Sheikhupura 100.000 9.254 3.535 3.535 2.651 2.651 100% 11.905 12% non-availability of funds. Sheikhupura Urban Sewerage, Drainage & PCC Scheme 1341 2944 UC Qilla Sattar Shah, Tehsil Muridkay, Sheikhupura 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Scheme Completed District Sheikhupura Provision of PCC and Tuff Tiles in City 1342 2945 Sheikhupura 180.000 140.000 3.333 3.333 2.500 2.500 100% 142.500 79% Funds fully utilized, work stopped due to Sheikhupura PP-167, District Sheikhupura non-availability of funds.

Construction of PCC, Drains and Nallah at 1343 2946 Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utilized, work stopped due to UC-57 Jevanpura, District Sheikhupura non-availability of funds. Construction of PCC, Drains and Nallah at 1344 2947 Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utilized, work stopped due to UC-58 Kadlathi, District Sheikhupura non-availability of funds. Construction of PCC, Drains and Nallah at 1345 2948 Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utilized, work stopped due to UC-80 Khariyanwala. District Sheikhupura non-availability of funds. Construction of PCC, Drains and Nallah at 1346 2949 Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utilized, work stopped due to UC-81 Bhikhi. District Sheikhupura non-availability of funds. Construction of PCC, Drains and Nallah at 1347 2950 Sheikhupura 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utilized, work stopped due to UC-82 Tibbi Hambo. District Sheikhupura non-availability of funds. Construction of sewerage, drains, tuff tiles, PCC & LED Street lights at Wandala Dial 1348 2951 Sheikhupura 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utilized, work stopped due to Shah & Dhaka Nizam Pura, District non-availability of funds. Sheikhupura Construction of drain / soling / PCC / Nullah and Pulyat at vilalge Rato Ana, Kot Ghulam Nankana 1349 2952 29.500 10.000 3.333 3.333 1.667 1.667 100% 11.667 40% Funds fully utlized. Work stopped due to Rasool and village Sheedi Kot UC Kot Sahib non-availability of funds. Hussain Khan, District Nankana Sahib Construction of PCC / Soling & Nallah at Nankana 1350 2953 30.000 10.000 3.333 3.333 6.900 6.900 100% 16.900 56% Funds fully utlized. Work stopped due to UC Buchoke Pur Distirct Nankana Sahib Sahib non-availability of funds. Construction of Drain / Nullah / Culverts / PCC and Soling at UC Kari Wala i/c Nankana 1351 2954 15.000 10.000 1.667 1.667 0.024 0.024 100% 10.024 67% Funds fully utlized. Work stopped due to Mashmoola Jat, Tehsil Shah Kot, District Sahib non-availability of funds. Nankana Sahib Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of drain / soling / PCC / Nullah and Pulyat at village Nathowala 180/RB, Nankana 1352 2955 Chak No.181/RB, Kari Wala and Chak 29.700 10.000 3.333 3.333 1.200 1.200 100% 11.200 38% Funds fully utlized. Work stopped due to Sahib non-availability of funds. No.182/RB, UC Nathowala, District Nankana Sahib Construction of drain / soling / PCC / Nullah and Pulyat at village Chak No.184/RB Kot Nankana 1353 2956 29.300 10.000 3.333 3.333 2.500 2.500 100% 12.500 43% Funds fully utlized. Work stopped due to Nizam Din and Chak No.186/RB Ghandran Sahib non-availability of funds. UC Kot Nizam Din, District Nankana Sahib Construction of Drain / Soling / Nallah at Nankana 1354 2957 UC Saleem Pur Pakka, District Nankana 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Sahib Construction of Drain / Soling / Nallah at Nankana 1355 2958 30.000 10.000 3.333 3.333 7.480 7.480 100% 17.480 58% Funds fully utlized. Work stopped due to UC Mangtanwala, District Nankana Sahib Sahib non-availability of funds. Construction of Drain / Soling / Nallah at Nankana 1356 2959 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utlized. Work stopped due to UC Chachke Gill, District Nankana Sahib Sahib non-availability of funds. Construction of Drain / Soling / Nallah at Nankana 1357 2960 30.000 10.000 3.333 3.333 3.000 3.000 100% 13.000 43% Funds fully utlized. Work stopped due to UC Haft Madar, District Nankana Sahib Sahib non-availability of funds. Construction of Drain / Soling / Nallah in left Nankana 1358 2961 over area of UC Ganaish Pur, District 30.000 10.000 3.333 3.333 4.100 4.100 100% 14.100 47% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Nankana Sahib Construction of Drain / Soling / Nallah in left Nankana 1359 2962 over area of UC Jawahar Pur, Distirct 40.000 13.000 3.333 3.333 1.100 1.100 100% 14.100 35% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Nankana Sahib Construction of Drain / Soling / Nallah in left Nankana 1360 2963 over area of UC Jogaykot, Distirct Nankana 30.000 10.000 3.333 3.333 1.100 1.100 100% 11.100 37% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Sahib Construction of Drain / Soling / Nullah at Nankana 1361 2964 15.000 10.000 1.667 1.667 1.100 1.100 100% 11.100 74% Funds fully utlized. Work stopped due to UC jalal Nau, District Nankana Sahib Sahib non-availability of funds. Construction of Drain / Soling / Nullah at Village Balaqian, Dodhay, Chora, Mat Nankana 1362 2965 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Funds fully utlized. Work stopped due to Kalayian and Dharian, District Nanakana Sahib non-availability of funds. Sahib Provision of sewerage, PCC & Nullah at Nankana 1363 2966 Mouza Khiyaray Kalan, Tehsil & District 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Nankana Sahib Provision of water supply sanitation and Nankana 1364 2967 drainage facilities at Chak No.168/RB 112.768 23.200 3.333 3.333 6.400 6.400 100% 29.600 26% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Machar Wali District Nankana Sahib Construction of Nullah / Drain and PCC at Bucheki City and at Chak No.22/75, Chak Nankana 1365 2968 No.18/71, Chak No.16/69, Chak No.641 50.000 40.000 3.333 3.333 0.000 0.000 #DIV/0! 40.000 80% Scheme Completed. Sahib Bohty Wala, Lurka Jangly, District Nankana Sahib Construction of PCC / Drain / Nullah at Burala, Maddo Ladoana, Juggian Nolan, Warra Narain Singh, Jahana Nool, Peeray Nankana 1366 2969 30.000 13.000 3.333 3.333 0.567 0.567 100% 13.567 45% Funds fully utlized. Work stopped due to Wali, Chak Wattowan, Nodhan, Sikhanwali, Sahib non-availability of funds. Kawanwali, Nizam Pura, Baghoor, District Nankana Sahib Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Soling, Drains & PCC at village Nathowala, Nizampura, Nodha, Nankana 1367 2970 50.000 33.000 3.333 3.333 3.950 3.950 100% 36.950 74% Funds fully utlized. Work stopped due to Fareedabad, Kheokay Bhattian, Madu, Sahib non-availability of funds. Purana Syed wala , District Nankana Sahib Construction of PCC, Soling & Nullah at UC Machrala i/c Bhagor, Wakeel Wala, Nankana 1368 2971 30.000 10.000 3.333 3.333 3.700 3.700 100% 13.700 46% Funds fully utlized. Work stopped due to Adampura & Dolatpura, Distirct Nankana Sahib non-availability of funds. Sahib Construction of PCC, Soling & Nullah at UC Nankana 1369 2972 Mustafaabad / Jislani, Distirct Nankana 25.000 10.000 3.333 3.333 2.250 2.250 100% 12.250 49% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Sahib Construction of PCC, Soling & Nullah at UC Nankana 1370 2973 25.000 10.000 3.333 3.333 0.850 0.850 100% 10.850 43% Funds fully utlized. Work stopped due to Meeranpur, Distirct Nankana Sahib Sahib non-availability of funds. Construction of PCC, Drains and Nallah at Nankana 1371 2974 UC-51 Khiarraey Kalan District Nankana 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Sahib. Construction of PCC, Drains and Nallah at Nankana 1372 2975 UC-52 Chokian Wala District Nankana 15.000 5.000 3.333 3.333 0.950 0.950 100% 5.950 40% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Sahib. Construction of PCC, Nallah, Drains at Nankana 1373 2976 50.000 40.000 3.333 3.333 0.000 0.000 #DIV/0! 40.000 80% Scheme Completed. Syed Wala, District Nankana Sahib Sahib Construction of PCC, Drains and Nallah at Nankana 1374 2977 15.000 5.000 3.333 3.333 0.145 0.145 100% 5.145 34% Funds fully utlized. Work stopped due to UC-48 Rehanwala District Nankana Sahib. Sahib non-availability of funds.

Construction of PCC, Drains and Nallah at Nankana 1375 2978 15.000 5.000 3.333 3.333 4.000 4.000 100% 9.000 60% Funds fully utlized. Work stopped due to UC-36 Mashrala District Nankana Sahib. Sahib non-availability of funds.

Construction of PCC, Drains and Nallah at Nankana 1376 2979 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Funds fully utlized. Work stopped due to UC-39 Meeranpur District Nankana Sahib. Sahib non-availability of funds.

Construction of PCC, Drains and Nallah at Nankana 1377 2980 15.000 5.000 3.333 3.333 3.400 3.400 100% 8.400 56% Funds fully utlized. Work stopped due to UC-50 Ganaishpur District Nankana Sahib. Sahib non-availability of funds.

Construction of PCC, Drains and Nallah at Nankana 1378 2981 15.000 5.000 3.333 3.333 5.870 5.870 100% 10.870 72% Funds fully utlized. Work stopped due to UC-38 Warbutton District Nankana Sahib. Sahib non-availability of funds. Construction of PCC, Drains and Nallah at Nankana 1379 2982 UC-40 Shareen Jhangaar District 15.000 5.000 3.333 3.333 4.500 4.500 100% 9.500 63% Funds fully utlized. Work stopped due to Sahib non-availability of funds. Sheikhupura Rural Drainage PCC Brick pavement Funds fully utlized, work stopped due to non- 1380 2983 Schemes Beroon Mustafa Abad and Kasur 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% availability of funds Adjoining Abadies, Tehsil & District Kasur Rural Drainage PCC Brick pavement Funds fully utlized, work stopped due to non- 1381 2984 Schemes Weghal and Adjoining Abadies, Kasur 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% availability of funds Tehsil & District Kasur

Rural Drainage PCC Brick pavement Scheme physically completed, Balance 1382 2985 Schemes Badar Pur, Ray, Badian and Kasur 15.000 4.966 3.333 3.333 2.500 2.500 100% 7.466 50% funds are requried to clear the contractor Adjoining Abadies, Tehsil & District Kasur liabilities Rural Drainage PCC Brick pavement Funds fully utlized, work stopped due to non- 1383 2986 Schemes Matta and Adjoining Abadies, Kasur 20.000 9.957 3.333 3.333 2.500 2.500 100% 12.457 62% availability of funds Tehsil & District Kasur Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Rural Drainage PCC Brick pavement Funds fully utlized, work stopped due to non- 1384 2987 Schemes Khara and Adjoining Abadies, Kasur 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% availability of funds Tehsil & District Kasur Const. of Soling Drains, PCC, Culverts U.C 1385 2988 Kasur 30.000 11.467 1.667 1.667 3.620 3.620 100% 15.087 50% Funds fully utlized, work stopped due to non- Handal, Tehsil KRK, District Kasur availability of funds Rural drainage scheme U.C Bhedian, 1386 2989 Kasur 30.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 38% Funds fully utlized, work stopped due to non- District Kasur availability of funds Rural drainage scheme U.C Sheikhum, 1387 2990 Kasur 25.000 9.993 5.000 5.000 3.750 3.750 100% 13.743 55% Funds fully utlized, work stopped due to non- District Kasur availability of funds Rural drainage scheme U.C Fathe Pur, Scheme physically completed, Balance 1388 2991 Kasur 30.000 9.981 1.967 1.967 1.475 1.475 100% 11.456 38% funds are requried to clear the contractor District Kasur liabilities Rural drainage scheme U.C Hussain Khan 1389 2992 Kasur 30.000 10.000 6.667 6.667 6.000 6.000 100% 16.000 53% Funds fully utlized, work stopped due to non- Wala, District Kasur availability of funds Construction of Sewerage / Drainage / PCC Funds fully utlized, work stopped due to non- 1390 2993 Scheme Kot Radha Kishan City, District Kasur 199.860 34.999 20.000 20.000 26.303 26.303 100% 61.302 31% availability of funds Kasur Construction of Soling, Nallah, PCC & 1391 2994 Kasur 15.000 4.992 3.333 3.333 2.500 2.500 100% 7.492 50% Funds fully utlized, work stopped due to non- Drain at Satoki, District Kasur. availability of funds Construction of Soling, Nallah, PCC & Funds fully utlized, work stopped due to non- 1392 2995 Drain at UC Cheena Arla and Nathoki, Kasur 15.000 4.996 3.333 3.333 2.500 2.500 100% 7.496 50% availability of funds District Kasur Construction of Soling, Nallah, PCC & 1393 2996 Kasur 15.000 4.980 3.333 3.333 2.500 2.500 100% 7.480 50% Funds fully utlized, work stopped due to non- Drain at UC Pemar, District Kasur availability of funds Construction of soling / drains / PCC roads 1394 2997 Kasur 3.000 2.500 0.167 0.167 0.125 0.125 100% 2.625 88% Scheme Completed in Chak No.38, District Kasur Construction of soling / drains / PCC roads Scheme physically completed, Balance 1395 2998 in village Chugian & Marathiwala, District Kasur 3.000 2.457 0.167 0.167 0.475 0.475 100% 2.932 98% funds are requried to clear the contractor Kasur liabilities Construction of soling / drains / PCC roads Scheme physically completed, Balance 1396 2999 Kasur 3.000 2.500 0.167 0.167 0.125 0.125 100% 2.625 88% funds are requried to clear the contractor in village Chaku , District Kasur liabilities Construction of Urban Sewerage, Drainage, Funds fully utlized, work stopped due to non- 1397 3000 PCC Scheme Khudian Phase-II, District Kasur 360.000 35.000 10.090 10.090 7.568 7.568 100% 42.568 12% availability of funds Kasur Construction of Urban Sewerage, Drainage, 1398 3001 Kasur 150.026 29.977 5.000 5.000 3.750 3.750 100% 33.727 22% Funds fully utlized, work stopped due to non- PCC Scheme, Kanganpur, District Kasur availability of funds Urban Water supply scheme, Kasur City, 1399 3002 Kasur 70.526 20.000 5.000 5.000 3.750 3.750 100% 23.750 34% Funds fully utlized, work stopped due to non- District Kasur availability of funds Construction of drain, PCC, Tuff Tile, Culverts, Sullage Carrier and Brick Funds fully utlized, work stopped due to non- 1400 3003 Pavement Sheikham, Kacha Pakka, Kasur 144.500 27.996 5.000 5.000 3.750 3.750 100% 31.746 22% availability of funds Padhana, Bath Kalan and Tara Garh, Tehsil Pattoki, District Kasur Construction of drain, PCC, Tuff Tile, Culverts, Sullage Carrier and Brick Funds fully utlized, work stopped due to non- 1401 3004 Pavement Balloki, Sandhu Kalan, Sarai Kasur 149.000 28.000 5.000 5.000 3.750 3.750 100% 31.750 21% availability of funds Mughal, Beharwal and Bhonikey, Tehsil Pattoki, District Kasur Rehabilitation & Re-construction of sullage Scheme physically completed, Balance 1402 3005 Kasur 10.451 7.000 1.150 1.150 2.363 2.363 100% 9.363 90% funds are requried to clear the contractor carrier at Waan Adhan, District Kasur liabilities Construction of Drain, Brick Pavement & Funds fully utlized, work stopped due to non- 1403 3006 PCC in Ghummankey and adjoining Kasur 69.298 20.000 20.000 20.000 15.000 15.000 100% 35.000 51% availability of funds abadies, Tehsil Pattoki, District Kasur Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Drain, Brick Pavement & Funds fully utlized, work stopped due to non- 1404 3007 PCC in Bonga Balochan and adjoining Kasur 66.879 20.000 20.000 20.000 15.195 15.195 100% 35.195 53% availability of funds abadies, Tehsil Pattoki, District Kasur Construction of Drainage, Brick Pavement, PCC and Sullage Carrier Scheme in Blair, 1405 3008 Kasur 50.000 18.000 3.333 3.333 2.500 2.500 100% 20.500 41% Funds fully utlized, work stopped due to non- Masradass i/c adjoining abadies, Tehsil availability of funds Pattoki, District Kasur Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 26.09.2017, Date of Receipt of tenders 27.09.2017, Date of work order ,12.10.2017 Rural Sewerage / Drainage Scheme Chak Date of completion as per PC-I ,30.06.2018 1406 3009 Okara 14.330 9.993 1.000 1.000 0.500 0.500 100% 10.493 73% Anticipated date of completion No.18/GD, District Okara ,30.06.2018Surface Drain = 0 / 848 RftBrick Pavment = 12761 / 15548 CftSullage Carrier 1.5x1.5' = 8250 / 4730 RftSullage Carrier 2x2' = 498 / 498 RftTuff tile = 21330 / 21330 Rft No. of Beneficiary - 9878 Person, Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019,Tubewell Boring = 1 / 1 Rural Water Supply & Drainage Scheme, 1407 3010 Okara 20.840 9.992 3.613 3.613 4.810 4.810 100% 14.802 71% NoPump House = 1 / 1 NORising Main Sahbay Wala, Depal Pur Dirtribution System 3" = 13932 / 14162 Rft4" i/d = 2886 / 3072 Rft6" i/d = 1097 / 1150 Rft8" i/d = 1091 / 1055 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 128 / 1270 RftBrick Pavement = 1087 / 10083 Cft Sullage Carreir = 0 / 287 Rft No. of Beneficiary - 9822 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019,Tubewell Boring = 1 / 1 Rural Water Supply & Drainage Scheme, 1408 3011 Okara 20.510 7.993 4.170 4.170 2.278 1.849 81% 9.842 48% NoPump House = 1 / 1 NORising Main Bhakho Shah, Depal Pur Dirtribution System 3" = 13932 / 14162 Rft4" i/d = 5400 / 5488 Rft6" i/d = 2600 / 2666 Rft8" i/d = 1200 / 1231 Rft10" i/d = 200 / 200 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 0 / 2868 RftBrick Pavement = 0 / 11743 Cft Sullage Carreir = 0 / 1666 Rft No. of Beneficiary - 6316 Person, Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019,Tubewell Boring = 1 / 1 Rural Water Supply & Drainage Scheme, 1409 3012 Okara 20.325 7.992 4.108 4.108 0.014 0.013 93% 8.005 39% NoPump House = 1 / 1 NORising Main Dhool Choor, Depal Pur Dirtribution System 3" = 20000 / 23174 Rft4" i/d = 0 / 2210 Rft6" i/d = 0 / 1350 Rft8" i/d = 0 / 860 Rft10" i/d = 200 / 200 RftOHR 20000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 0 / 1121 RftBrick Pavement = 0 / 3479 Cft Sullage Carreir = 0 / 437 Rft No. of Beneficiary - 9804 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019,Tubewell Boring = 1 / 1 Rural Water Supply & Drainage Scheme, 1410 3013 Okara 19.930 9.991 3.310 3.310 0.883 0.859 97% 10.850 54% NoPump House = 1 / 1 NORising Main Aman Wala, Depal Pur Dirtribution System 3" = 13977 / 15780 Rft4" i/d = 2904 / 2904 Rft6" i/d = 736 / 736 Rft8" i/d = 0 / 0 Rft10" i/d = 0 / 0 RftOHR 10000 Glns 1 / 1.NO. 90%External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 474 / 1855 RftBrick Pavement = 1700 / 9660 Cft Sullage Carreir = 318 / 2843 Rft No. of Beneficiary - 4246 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, 1411 3014 Okara 17.400 7.987 3.133 3.133 2.350 1.523 65% 9.510 55% Tubewell Boring = 1 / 1 NoPump House = 1 Dhol Gehla, Depal Pur / 1 NORising Main Dirtribution System 3" = 15423 / 15423 Rft4" i/d = 2216 / 2295 Rft6" i/d = 0 / 100 RftOHR 10000 Glns 1 / 1.NO. External Electrification 1 / 1 Job D.N Paid to Wapda Surface Drain = 0 / 2697 RftBrick Pavement = 0 / 9817 Cft Sullage Carreir = 0 / 275 Rft No. of Beneficiary 3302 Person Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion Rural Water Supply & Drainage Scheme, 30.06.2019,Tubewell Boring = 1 / 1 1412 3015 Okara 17.190 7.500 3.230 3.230 2.423 1.060 44% 8.560 50% NoPump House = 1 / 1 NORising Main Mehro Kalan, Depal Pur Dirtribution System 3" = 27487 / 27487 Rft4" i/d = 1722 / 1722 Rft6" i/d = 1108 / 1135 Rft8" i/d = 0 / 100 RftOHR 10000 Glns 1 / 1.NO. 70.%External Electrification 0 / 1 Surface Drain = 0 / 700 RftBrick Pavement = 0 / 2548 Cft Sullage Carreir = 0 / 0 Rft No. of Beneficiary 6277 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, ubewell Boring = 1 / 1 NoPump House = 1 / 1413 3016 Okara 17.660 9.972 2.553 2.553 1.915 1.262 66% 11.234 64% 1 NORising Main Dirtribution System 3" = Somian Bholon, Depal Pur 16772 / 19520 Rft4" i/d = 1236 / 1360 Rft6" i/d = 1869 / 1855 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 1 / 1.NO. 45.%External Electrification 0 / 1 Surface Drain = 0 / 1172 RftBrick Pavement = 13952 / 8729 Cft Sullage Carreir = 0 / 1195 Rft No. of Beneficiary 3678 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion Rural Water Supply & Drainage Scheme, 30.06.2019,ubewell Boring = 1 / 1 NoPump 1414 3017 Okara 15.520 9.991 1.840 1.840 1.380 0.920 67% 10.911 70% House = 1 / 1 NORising Main Dirtribution Roori, Depal Pur System 3" = 13404 / 15671 Rft4" i/d = 5974 / 5974 Rft6" i/d = 933 / 945 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 1 / 1.NO. 75.%External Electrification 0 / 1 Surface Drain = 0 / 1002 RftBrick Pavement = 1929 / 3847 Cft Sullage Carreir = 0 / 1170 Rft No. of Beneficiary 3005 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, ubewell Boring = 1 / 1 NoPump House = 1 / 1415 3018 Okara 17.900 7.912 3.300 3.300 1.625 1.613 99% 9.525 53% 1 NORising Main Dirtribution System 3" = Mali Singh, Depal Pur 13316 / 13393 Rft4" i/d = 1665 / 1740 Rft6" i/d = 840 / 865 Rft8" i/d = 0 / 100 RftOHR 10000 Glns 1 / 1.NO. 45.%External Electrification 0 / 1 Surface Drain = 0 / 2745 RftBrick Pavement = 10514 / 20089 Cft Sullage Carreir = 120 / 815 Rft No. of Beneficiary 3813 Person Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion Rural Water Supply & Drainage Scheme, 30.06.2019,ubewell Boring = 1 / 1 NoPump 1416 3019 Okara 25.790 9.970 5.263 5.263 3.947 2.916 74% 12.886 50% House = 1 / 1 NORising Main Dirtribution Khan Bahadar, Depal Pur System 3" = 18131 / 17637 Rft4" i/d = 1126 / 1120 Rft6" i/d = 2205 / 2212 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 1 / 1.NO. 90.%External Electrification 1 / 1 Surface Drain =1699 / 4487 RftBrick Pavement = 6705 / 44428 Cft Sullage Carreir = 0 / 680 Rft No. of Beneficiary 5319 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 07-12- 2017 Date of Receipt of tenders 08-12-2017 Date of work order 14-12-2017 Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, 1417 3020 Okara 22.970 4.992 5.990 5.990 2.382 2.234 94% 7.226 31% Tubewell Boring = 1 / 1 NoPump House = 1 Kalia Ibrahim, Depal Pur / 1 NORising Main Dirtribution System 3" = 6097 / 9952 Rft4" i/d = 1304 / 525 Rft6" i/d = 2108 / 1725 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. Staff qurter = 1/80%External Electrification 0 / 1 Surface Drain = 0 / 3813 RftBrick Pavement = 0 / 35872 Cft Sullage Carreir = 0 / 1630 Rft No. of Beneficiary 2866 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, A nticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, 1418 3021 Okara 19.710 10.000 3.237 3.237 1.619 1.615 100% 11.615 59% Tubewell Boring = 1 / 1 NoPump House = 1 Shamaskay, Depal Pur / 1 NORising Main Dirtribution System 3" = 6097 / 9952 Rft4" i/d = 1304 / 525 Rft6" i/d = 2108 / 1725 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. Staff qurter = 1/80%External Electrification 0 / 1 Surface Drain = 0 / 3813 RftBrick Pavement = 0 / 35872 Cft Sullage Carreir = 0 / 1630 Rft No. of Beneficiary 2619 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion Rural Water Supply & Drainage Scheme, 30.06.2019,Tubewell Boring = 1 / 1 1419 3022 Okara 22.450 9.995 4.150 4.150 1.363 1.363 100% 11.358 51% NoPump House = 1 / 1 NORising Main Subhan Shah, Depal Pur Dirtribution System 3" = 14902 / 11175 Rft4" i/d = 5154 / 5370 Rft6" i/d = 1375 / 2900 Rft8" i/d = 0 / 100 RftOHR 10000 Glns 1 / 1.NO. 75 %Staff qurter = 1/1External Electrification 0 / 1 Surface Drain = 0 / 3771 RftBrick Pavement = 0 / 21418 Cft Sullage Carreir = 0 / 1198 Rft No. of Beneficiary 5870 Person Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019,Tubewell Boring = 1 / 1 Rural Water Supply & Drainage Scheme, 1420 3023 Okara 21.110 9.999 3.703 3.703 1.827 1.827 100% 11.826 56% NoPump House = 1 / 1 NORising Main Bothana, Depal Pur Dirtribution System 3" = 23340 / 23130 Rft4" i/d = 1093 / 1745 Rft6" i/d = 3399 / 3774 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. Staff qurter = 0/1External Electrification 0 / 1 Surface Drain = 804 / 1532 RftBrick Pavement = 3570 / 12740 Cft Sullage Carreir = 780 / 1076 Rft No. of Beneficiary 5652 Person Work is in progress. Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, Tubewell Boring = 1 / 1 NoPump House = 1 1421 3024 Okara 21.510 11.000 3.503 3.503 1.752 1.752 100% 12.752 59% / 1 NORising Main Dirtribution System 3" = Sahniwal, Depal Pur 21019 / 21040 Rft4" i/d = 1782 / 1790 Rft6" i/d = 1375 / 1385 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. 75 %Staff qurter = 1/1External Electrification 1 / 1 Surface Drain = 0 / 7352 RftBrick Pavement = 0 / 19112 Cft Sullage Carreir = 0 / 800 Rft No. of Beneficiary 4724 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion Rural Water Supply & Drainage Scheme, 30.06.2019,Tubewell Boring = 1 / 1 1422 3025 Okara 17.270 9.993 2.423 2.423 1.217 1.163 96% 11.156 65% NoPump House = 1 / 1 NORising Main Chak no. 7/D Rakh Dharma, Depal Pur Dirtribution System 3" = 8837 / 8837 Rft4" i/d = 1092 / 1177 Rft6" i/d = 597 / 655 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. Staff qurter = 1/80%External Electrification 0 / 1 Surface Drain = 0 / 3389 RftBrick Pavement = 0 / 13635 Cft Sullage Carreir = 0 / 1125 Rft No. of Beneficiary - 3781 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 07-12- 2017 Date of Receipt of tenders 08-12-2017 Date of work order 12-12-2017 Date of completion as per PC-I 30.06.2018, Anticipated date of completion Rural Water Supply & Drainage Scheme, 30.06.2019,Tubewell Boring = 1 / 1 1423 3026 Okara 18.500 9.992 2.833 2.833 1.425 1.413 99% 11.405 62% NoPump House = 1 / 1 NORising Main Kandowal Sarai, Depal Pur Dirtribution System 3" = 20251 / 21521 Rft4" i/d = 3661 / 3775 Rft6" i/d = 2228 / 1085 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. Staff qurter = 0/1External Electrification 0 / 1 Surface Drain = 0 / 1581 RftBrick Pavement = 0 / 5534 Cft Sullage Carreir = 0 / 356 Rft No. of Beneficiary - 6281 Person, Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, Tubewell Boring = 1 / 1 NoPump House = 1 1424 3027 Okara 18.330 9.997 2.777 2.777 1.383 1.383 100% 11.380 62% / 1 NORising Main Dirtribution System 3" = Chak no. 19/D, Depal Pur 27910 / 27910 Rft4" i/d = 2052 / 2052 Rft6" i/d = 0 / 375 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. 20%Staff qurter = 1/1External Electrification 0 / 1 Surface Drain = 0 / 965 RftBrick Pavement = 0 / 9752 Cft Sullage Carreir = 0 / 979 Rft No. of Beneficiary - 4604 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019,Tubewell Boring = 1 / 1 Rural Water Supply & Drainage Scheme, 1425 3028 Okara 21.320 9.998 3.773 3.773 1.880 1.792 95% 11.790 55% NoPump House = 1 / 1 NORising Main Sarai Amar Singh, Depal Pur Dirtribution System 3" = 12085 / 5528 Rft4" i/d = 4147 / 1098 Rft6" i/d = 1567 / 1567 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. 20%Staff qurter = 1/1External Electrification 1 / 1 Surface Drain = 953 / 3575 RftBrick Pavement = 1216/ 31321 Cft Sullage Carreir = 1020 / 1476 Rft No. of Beneficiary - 6642 Person, Work is in progress. Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018,, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, Tubewell Boring = 1 / 1 NoPump House = 1 1426 3029 Okara 21.650 9.999 3.883 3.883 1.912 1.907 100% 11.906 55% / 1 NORising Main Dirtribution System 3" = Chak Kamboh, Depal Pur 14159 / 14159 Rft4" i/d = 3106 / 3106 Rft6" i/d = 2108 / 1725 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 0 / 1.NO. Staff qurter = 181External Electrification 1 / 1 Surface Drain = 0 / 4097 RftBrick Pavement = 0 / 24297 Cft Sullage Carreir = 0 / 1300 Rft No. of Beneficiary - 5441 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 10.10.2017, Date of Receipt of tenders 11.10.2017, Date of work order 16-11-2017, Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, Tubewell Boring = 1 / 1 NoPump House = 1 1427 3030 Okara 19.930 9.986 3.310 3.310 2.483 1.645 66% 11.631 58% / 1 NORising Main Dirtribution System 3" = Doola Mustakim , Depal Pur 5472 / 10675 Rft4" i/d = 993 / 993 Rft6" i/d = 651 / 685 Rft8" i/d = 0 / 0 RftOHR 10000 Glns 1 / 1.NO. Staff qurter = 1/1External Electrification 0 / 1 Surface Drain = 1319 / 1399 RftBrick Pavement = 6785 / 29848 Cft Sullage Carreir = 390 / 863 Rft No. of Beneficiary - 3942 Person, Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 07-12- 2017 Date of Receipt of tenders 08-12-2017 Date of work order 14-12-2017 Date of completion as per PC-I 30.06.2018, Anticipated date of completion 30.06.2019, Rural Water Supply & Drainage Scheme, Tubewell Boring = 1 / 1 NoPump House = 1 1428 3031 Okara 21.580 9.992 3.860 3.860 1.895 1.874 99% 11.866 55% / 1 NORising Main Dirtribution System 3" = Bonga Saleh, Depal Pur 13866 / 13866 Rft4" i/d = 2114 / 2497 Rft6" i/d = 1397 / 1940 Rft8" i/d = 324 / 320 RftOHR 10000 Glns 1 / 1.NO. 75%Staff qurter = 1/1External Electrification 0 / 1 Surface Drain = 0 / 1900 RftBrick Pavement = 0 / 18546 Cft Sullage Carreir = 0 / 800 Rft No. of Beneficiary - 7909 Person, Work is in progress.

Date of A.A 11.08.2017, Date of T.S 15.08.2017, Date of Prequalification 13-09- 2017, Date of invitation of tenders 08.10.2017, Date of Receipt of tenders Construction of Drain, Brick Pavement, 09.10.2017, Date of work order 18-11-2017, Date of completion as per PC-I 1429 3032 Sullage Carrier, Tuff Tile, PCC in District Okara 64.454 7.800 3.333 3.333 2.500 0.735 29% 8.535 13% 30.06.2019,Surface Drain = 14370 / 28529 Okara Chak no. 38-GD RftBrick Pavment = 0 / 2129 CftSullage Carrier 1.25x1.25' = 3180 / 2210 RftSullage Carrier 1.5 x1.5' = 4500 / 5430 RftTuff tile = 0 / 412364 Rft No. of Beneficiary -14313 Person, Work is in progress.

Date of A.A 26.07.2017, Date of T.S 31-07- 2017, Date of Prequalification 13-09-2017, Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order ,07-02-2018 Date of Construction of Drain, Brick Pavement, completion as per PC-I 30.06.2018, 1430 3033 Sullage Carrier, Tuff Tile, PCC in District Okara 25.000 9.999 3.333 3.333 1.000 1.000 100% 10.999 44% Anticipated date of completion 30.06.2019, Okara Chak no. 4/GD Surface Drain = 7138 / 30202 RftBrick Pavment = 8281 / 10792 CftSullage Carrier 1.5x1.5' = 4417 / 6924 RftSullage Carrier 2x2' = 2225 / 1430 RftSullage Carrier 1.5x2' = 545 / 1572 RftTuff tile = 0 / 1200 Rft No. of Beneficiary - 10018 Person,

Date of A.A 26.07.2017, Date of T.S 31-07- 2017, Date of Prequalification ,13.09.2017 Date of invitation of tenders 18-12-.2017, Date of Receipt of tenders 19-12-2017, Soling / Sewerage and Drainage of Chak Date of work order 19-01-2018 Date of 1431 3034 Okara 20.000 9.999 3.333 3.333 0.600 0.600 100% 10.599 53% completion as per PC-I , Anticipated date of No. 53/2L, 54/2L, 55/2L, District Okara completion, 30-06-2019Rcc Sewer 9" i.d 2/ 200 Rft12" i/d = 6268 /6268Rft15" i/d = 0 /500 Rft Surface Drain 3308 / 4011 RftBrick Pavement = 22089 / 59015 CftNo. of Beneficiary - 51657 Person,

Date of A.A 08.08.2017, Date of T.S 10.08.2017 Date of Prequalification ,13.09.2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order 31-09-2017 Provision of Soling and Drainage Scheme 1432 3035 Okara 14.000 6.986 2.333 2.333 0.250 0.250 100% 7.236 52% Date of completion as per PC-I , Anticipated at U.C. No.42/3R, District Okara date of completion , 30-06-2019Surface Drain = 832 / 4835 RftBrick Pavment = 15680 / 38328 CftSullage Carrier 1.5x1.5' = 0 / 1830 RftSullage Carrier 2x2' = 1502 / 2310 Rft No. of Beneficiary - 49251 Person, Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 26.07.2017, Date of T.S 02-08- 2017 Date of Prequalification ,13.09.2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order 12-12-2017 Date of Provision of Soling and Drainage Scheme 1433 3036 Okara 20.000 10.000 3.333 3.333 1.435 1.435 100% 11.435 57% completion as per PC-I , Anticipated date of at U.C. No.35/2RA, District Okara completion, 30-06-2019Surface Drain = 10715 / 12170 RftBrick Pavment = 34749 / 34749 CftSullage Carrier 1.5x1.5' = 0 / 4730 RftSullage Carrier 2x2' = 200 / 250 RftTuff tile = 19744 / 19900 Rft No. of Beneficiary - 33832 Person,

Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification ,13.09.2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders Provision of Tuff Tiles Soling, PCC, and 28.10.2017, Date of work order 20-11-2017 Date of completion as per PC-I , Anticipated 1434 3037 Drainage Schemes at Haveli Lakha and Okara 48.940 18.295 3.333 3.333 1.667 1.660 100% 19.955 41% date of completion, 30-06-2019Surface Adjoining Abadies Drain = 4492/12391 Rftsullage cArrier 520 / 1500 RftBrickpavement = 36780 / 55993 CftTuff Tile 60mm = 104435 /213520 sft80mm =- 0/ 32480 Sft No. of Beneficiary 42300 Person, Work is in progress.

Date of A.A 11.08.2017, Date of T.S 27.09.2017, Date of Prequalification 19-09- Installation of LED Street Light 120/W, 2017 Date of invitation of tenders 03.11.2017, Date of Receipt of tenders 50/W including Pools, Construction of 03.11.2017, Date of work order 09-11-2017 1435 3038 Sullage Carrier / sewerage & Construction Okara 74.312 38.998 3.333 3.333 1.667 1.667 100% 40.665 55% Date of completion as per PC-I , Anticipated of Tuff Paver different places at Okara City date of completion, 30-06-2019Rcc Sewer 12" i/d = 2624 / 7971 Rft15" i/d = 920 / 920 approx. District Okara RftTuff Tile 290214 / 484291 Sftsullage Carrier = 377 / 1685 Rft No. of Beneficiary 215982 Person Work is in progress.

Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders Construction of Tuff Tiles / Sewerage and 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order 17-11-2017 1436 3039 Drainage of Ward no. 1 to 50, District Okara 40.000 14.957 3.333 3.333 1.667 1.667 100% 16.624 42% Date of completion as per PC-I , 30-06- Okara 2018 Anticipated date of completion, 30-06- 2019Rcc Sewer 12" i/d = 3992 /3992 Rft15" i/d = 0/ 600 RftTuff Tile = 118114 / 302217 Sfr No. of Beneficiary -640401 Person, Date of A.A 26.07.2017, Date of T.S 01.08.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders City Package Renala Khurd Tuff Tile and 28.10.2017, Date of work order 07-11-2017 1437 3040 Sewerage Androon City Gilyat Renala Okara 35.000 15.584 3.333 3.333 2.500 1.667 67% 17.251 49% Date of completion as per PC-I 30-06-2018 Khurd In District Okara Anticipated date of completion, 30-06- 2019Rcc Sewer 12" i/d = 2530 / 4144 Rft15" i/d = 1855 / 2196 RftTuff Tile 118529 / 253039 Sft No. of Beneficiary - 64595 Person, Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders Sewerage Scheme at Mohallah Shakoor 28.10.2017, Date of work order 18-11-2017 1438 3041 Abad, Mohallah Eid Gah, Mohallah Masjid Okara 49.934 22.496 3.333 3.333 1.670 1.665 100% 24.161 48% Date of completion as per PC-I ,30-06-2018 Basharat, Akhter Town, Haveli Lakha, City. Anticipated date of completion, 30-06- 2019Rcc sewer 9" = 6252 /18115 Rft12" i/d = 3955 / 7145 Rft15" i/d = 2848 / 2855 Rft18" i/d 3331 / 6100 Rft No. of Beneficiary - Person, Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 28-09-2017 Date of T.S 16-11- 2017 Date of Prequalification 18-11-2017 Date of invitation of tenders 13-12-2017 Date of Receipt of tenders, 13-12-2017 Date of work order 23-12-2017 Date of completion as per PC-I 23-12-2020 Anticipated date of completion, 30-06- 2020Re-Appropreation (+)5.990Tubewell 1439 3042 Water supply Schemes for NA-145 Okara 300.000 74.642 20.000 20.000 51.997 51.997 100% 126.639 42% Boring = 9 / 18. NoRising Main Dirtribution System 3" to 10" i/d = 260150 / 452139 RftPumopin gMachenery = 1 / 18 setGround Storage Tank 10000 Gln to 20000 Gln = 3 / 5 JobsPumin gMachenry ( GST) = 0 / 5 setOHR = 3 / 9 JobsExternal Electrification 0 / 18 Jobs No. of Beneficiary 900043 Person,

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders Construction of Drain, Brick Pavement, 27.10.2017, Date of Receipt of tenders 1440 3043 Sullage Carrier, Tuff Tile, PCC in District Okara 23.299 11.494 3.333 3.333 1.670 1.669 100% 13.163 56% 28.10.2017, Date of work order 25-01-2018 Okara:in Mouza Jaboka Date of completion as per PC-I ,25-01-2019 Anticipated date of completion, 30-06-2019 Tuff Tile 60mm = 108693 /181814 Sft No. of Beneficiary - 14607 Person, Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order 25-01-2018 Construction of Drain, Brick Pavement, Date of completion as per PC-I 25-01-2019 1441 3044 Sullage Carrier, Tuff Tile, PCC in District Okara 49.895 17.413 3.333 3.333 1.714 1.713 100% 19.126 38% Anticipated date of completion, 30-06- Okara Mouza Lasharian 2019Surface Drain = 7864 / 5120 RftRaising of Drain = 0 / 15514 RftBrick Pavment = 55116 / 13468 CftSullage Carrier 1.5x2' = 8622 / 14275 RftTuff tile = 0 / 214362 Rft No. of Beneficiary - 17695 Person, Date of A.A 26.07.2017, Date of T.S 02.08.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 18-12- .2017, Date of Receipt of tenders 19- 12.2017, Date of work order 19-01-2018 Construction of Drain, Brick Pavement, Date of completion as per PC-I 19-01-2019 1442 3045 Sullage Carrier, Tuff Tile, PCC in District Okara 26.331 4.996 3.333 3.333 2.300 1.705 74% 6.701 25% Anticipated date of completion, 30-06- Okara Mouza Kohla 2019Surface Drain = 1531 / 1531 RftBrick Pavment = 29631 / 12427 CftSullage Carrier 1.5x1.5' = 996 / 1600 RftSullage Carrier 2x2' = 0 / 3065 RftSullage Carrier 1.5x2' = 0 / 1300 RftTuff tile = 0 / 101722 Rft No. of Beneficiary - 21476 Person,

Date of A.A 26.07.2017, Date of T.S 31.07.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order 18-11-2017 Construction of Drain, Brick Pavement, Date of completion as per PC-I 30-06-2018 Anticipated date of completion, 30-06- 1443 3046 Sullage Carrier, Tuff Tile, PCC in District Okara 18.346 13.991 1.282 1.282 4.462 4.460 100% 18.451 101% 2019Surface Drain = 8320 / 18155 RftBrick Okara Mouza Bama Bala Pavment = 29673 / 29673 CftSullage Carrier 1.5x1.5' = 300 / 500 RftSullage Carrier 2x2' = 0 / 1850 RftSullage Carrier 1.5x2' = 0 / 830 RftTuff tile = 44126 / 61755 Rft No. of Beneficiary - 12896 Person, Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 08.08.2017, Date of T.S 12.08.2017, Date of Prequalification 13-09- 2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date of work order 23-12-2017 Construction of Drain, Brick Pavement, Date of completion as per PC-I 30-06-2018 1444 3047 Sullage Carrier, Tuff Tile, PCC in District Okara 27.702 14.999 4.234 4.234 2.126 2.059 97% 17.058 62% Anticipated date of completion, 30-06-2019 Okara Mouza Maroula Sharif Surface Drain = 6559 / 10340 RftBrick Pavment = 41058 / 18728 CftSullage Carrier 1.5x1.5' = 500 / 630 RftSullage Carrier 2x2' = 4200 / 5400 RftTuff tile = 18484 / 91248 Rft No. of Beneficiary - 09561 Person, Date of A.A 12-09-2017 Date of T.S 16-09- 2017 Date of Prequalification 13-09-2017 Date of invitation of tenders 27.10.2017, Date of Receipt of tenders 28.10.2017, Date Provision of Drainage, Sewerage and Tuff of work order 20-11-2017 Date of completion as per PC-I 30-06-2018 1445 3048 Till Scheme at Civil Area Okara Cantt, Okara 20.000 5.377 4.833 4.833 3.625 2.467 68% 7.844 39% Anticipated date of completion, 30-06-2019 District Okara Surface Drain = 216/2400 RftBrick Pavement = 0/1310 CftTuff Tile 80121 / 144749 SftCullage carrier 1.5x1.5' = 0/ 250 Rft No. of Beneficiary 98441 Person, Work is in progress. Date of A.A Date of T.S Date of Prequalification Date of invitation of tenders Date of Receipt of tenders Date of work order Date of completion as per PC-I Providing of Tuff Tile & Sewerage / Anticipated date of completion, Surface Drain = 742 / 745 RftBrick Pavement = 1446 3049 Drainage in Basirpur and Mandi Ahmad Okara 26.398 9.999 3.333 3.333 1.994 0.000 0% 9.999 38% 54568 / 54610 Cftsullage carrier = 2101240 Abad Town, District Okara RftTuff Tile 60mm 29892 / 115395 Sft80mm = 0 / 18720 SftRcc sewer 9" = 0 / 394 Rft12" i/d = 0 / 763 Rft15" i/d = 0 / 906 Rft No. of Beneficiary Person, Work is in progress.

• Date of AA =06.12.2017,• Date of TS =15.12.2017,• No. of Beneficiaries=296264• Date of receipt of tender =28.03.2018 ,• Work order =18.04.2018 ,• Date of completion as per PC-1=30.06.2020,• Latitude=30.659053333333336• Longitude= 73.09937166666667 PCC Flooring=128250/435118 Sft9" i/d RCC Water Supply / Sewerage / Filtration Plants Sewer Pipe =0/1641 Rft12" i/d RCC Sewer 1447 3050 Sahiwal 150.000 34.996 16.667 16.667 12.500 12.000 96% 46.996 31% Pipe =5431/16790 Rft15" i/d RCC Sewer in 13 UCs of PP-221, Sahiwal Pipe =1475/147 RftTuff Tile= 37257/80224Surface Drain=0/9719 RftBrick Pavement=9358/90308 CftSullage Carrier= 0/4549 RftFiltration Plant=1/2 No.Tube Well=0/1 No.Pump House=0/1 No.Pumping Machinery=0/1 No. 3" i/d PVC Pipe =1081/9555 Rft4" i/d PVC Pipe =0/5175 Rft6" i/d PVC Pipe =0/3135 RftWork in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

• Date of AA =19.08.2017,• Date of TS =28.08.2017,• No. of Beneficiaries=12986• Date of Work Order =23.12.2017 ,• Anticipated date of completion =31.12.2019 • Latitude=30.624000000000002• Longitude= 73.137905Tube Well=1/1 Water Supply Scheme for Chak No. 78/5L 1448 3051 Sahiwal 30.000 10.000 6.667 6.667 5.425 5.400 100% 15.400 51% No.Pump House=1/1 No.Pumping Sahiwal Machinery=0/1 No.Rising Main & Distribution System3" i/d PVC Pipe =16404/16435 Rft4" i/d PVC Pipe =2344/2345 Rft6" i/d PVC Pipe =2680/2690 Rft8" i/d PVC Pipe =15345/31000 RftHypo Chlorinator=1/1 No. Electric Connection=0/1 JobWork in progress.

• Date of AA =01.08.2017 ,• Date of TS =03.08.2017 ,• No. of Beneficiaries=12829• Date of receipt of tender= 20.11.2017 ,• Date of Work Order =02.12.2017 ,• Anticipated date of completion 31.12.2019 (i) Latitude=30.4355676Longitude= 72.5957931(ii) Construction of Drain / Soling Sewerage Latitude=30.449426666666668Longitude= 1449 3052 Nala Chak no. 50/12L, 105/12L, 106/12/L, Sahiwal 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% 72.61357166666667(iii) District Sahiwal Latitude=30.435455Longitude= 72.59181833333334Drain Type I =900/4280 RftDrain Type II=0/290 RftBrick Pavement=12620/9057 CftSullage Carrier= 3632/1010 RftPumping Machinery=0/1 No. 9" i/d RCC Sewer Pipe =0/796 Rft12" i/d RCC Sewer Pipe =0/547 Rft15" i/d RCC Sewer Pipe =0/525 RftWork in progress.

• Date of AA =01.08.2017,• Date of TS =07.08.2017,• No. of Beneficiaries=19812• Date of receipt of tender= 09.11.2017 ,• Date of Work Order =24.11.2017 ,• Anticipated date of completion=31.12.2019 Work in progress.(i) Latitude=30.541561666666666Longitude= 72.497995(ii) Latitude=30.52711Longitude= Construction of Drain / Soling Sewerage 72.47944833333332(iii) 1450 3053 Nala Chak no.38/14L,39/14L/40/14L, Sahiwal 15.000 4.998 3.333 3.333 2.500 2.500 100% 7.498 50% Latitude=30.522551666666665Longitude= 41/14L , District Sahiwal 72.45642666666666(iv) Latitude=30.514016666666667Longitude= 72.46911166666668Drain Type I =1940/12877 RftDrain Type II=0/511 RftBrick Pavement=25510/20048 CftSullage Carrier= 75/3822 Rft9" i/d RCC Sewer Pipe =0/966 Rft12" i/d RCC Sewer Pipe =317/414 Rft15" i/d RCC Sewer Pipe =0/506 RftWork in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) • Date of AA= 01.08.2017 ,• Date of TS =07.08.2017,• No. of Beneficiaries=32294• Date of receipt of tenders =09.11.2017 ,• Date of Work Order=24.11.2017 , Anticipated date of completion =31.12.2019, (i) Latitude=30.5231118Longitude= Construction of Drain / Soling Sewerage 72.6729522(ii) 1451 3054 Nala Chak no. 40/12L, 109/12L, Ghulshan Sahiwal 15.000 4.977 3.333 3.333 2.500 2.500 100% 7.477 50% Latitude=30.5071041Longitude= Colony, District Sahiwal 72.675686Drain Type I =0/4080 RftDrain Type II=0/510 RftBrick Pavement=13746/20991 CftSullage Carrier= 0/2635 Rft9" i/d RCC Sewer Pipe =0/1556 Rft12" i/d RCC Sewer Pipe =3118/1472 Rft15" i/d RCC Sewer Pipe =674/630 RftWork in progress.

• Date of AA= 01.08.2017 ,• Date of TS =03.08.2017,• No. of Beneficiaries=18907• Date of receipt of tender= 20.11.2017 ,• Date of Work Order =02.12.2017 ,• Anticipated date of completion= 31.12.2019 (i) Latitude=30.481318333333334Longitude= 72.54414(ii) Construction of Drain / Soling Sewerage Latitude=30.48190833333333Longitude= 1452 3055 Nala Chak no. 118/12L, 117/12L, Ada Sahiwal 15.000 7.488 2.500 2.500 1.875 1.875 100% 9.363 62% 72.55744333333334(iii) Kassowal, District Sahiwal Latitude=30.485188333333333Longitude= 72.52961Drain Type I =1887/3248 RftDrain Type II=0/300 RftBrick Pavement=12926/8183 CftSullage Carrier= 397/770 RftPumping Machinery=1/1 Set9" i/d RCC Sewer Pipe =0/133 Rft12" i/d RCC Sewer Pipe =0/596 Rft15" i/d RCC Sewer Pipe =0/962 RftDisposal Works=1/1 jobWork in progress.

• Date of AA= 01.08.2017,• Date of TS =07.08.2017,• No. of Beneficiaries=20033• Date of receipt of tender= 09.11.2017,• Date of Work Order =24.11.2017,• Anticipated date of completion=31.12.2019 (i) Latitude=30.56351833333333Longitude= 72.52921666666666(ii) Contruction of Drain / Soling Sewerage Latitude=30.562821666666665Longitude= Nala Chak no. 119/7DR, 120/7ER, 72.50334333333333(iii) 1453 3056 Sahiwal 15.000 7.495 2.500 2.500 1.875 1.875 100% 9.370 62% Latitude=30.555803333333333Longitude= 121/7ER, 122/7ER, 117/7DR, District 72.48784333333333(iv) Sahiwal Latitude=30.560103333333338Longitude= 72.47178000000001Drain Type I =1285/8648 RftDrain Type II=0/210 RftBrick Pavement=41708/24674 CftSullage Carrier= 1430/390 Rft9" i/d RCC Sewer Pipe =0/1748 Rft12" i/d RCC Sewer Pipe =0/1380 Rft15" i/d RCC Sewer Pipe =0/552RftWork in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

• Date of AA =01.08.2017,• Date of TS =07.08.2017 ,• No. of Beneficiaries=16395• Date of receipt of tender= 09.11.2017,• Date of Work Order =24.11.2017,• Anticipated date of completion =31.12.2019 , (i) Latitude=30.556Longitude= 72.62021833333333(ii) Construction of Drain / Soling Sewerage Latitude=30.562929999999998Longitude= 1454 3057 Nala Chak no. 114/7R, 115/7CR, 116/7CR Sahiwal 15.000 7.499 2.500 2.500 1.875 1.870 100% 9.369 62% 72.59232833333334(iii) Sahwa, Dharma, District Sahiwal Latitude=30.548438333333333Longitude= 72.56176833333333Drain Type I =3381/7927 RftDrain Type II=0/1510 RftBrick Pavement=32350/35956 CftSullage Carrier= 2475/1510 Rft9" i/d RCC Sewer Pipe =0/414 Rft12" i/d RCC Sewer Pipe =0/368 Rft15" i/d RCC Sewer Pipe =0/782 RftWork in progress.

• Date of AA =01.08.2017 ,• Date of TS =08.08.2017 ,• No. of Beneficiaries=16395• Date of receipt of tender= 09.11.2017 ,• Date of Work Order =02.12.2017,• Construction of Drain / Soling Sewerage Anticipated date of completion =31.12.2019 Nala Chak no. 112/7r, 113/7r, Purani (i) Latitude=30.5645837Longitude= 1455 3058 Sahiwal 15.000 7.497 2.500 2.500 1.875 1.875 100% 9.372 62% 72.6858502(ii) Chichawatni, Sheikh Tayyab, District Latitude=30.569916666666668Longitude= Sahiwal 72.68709833333334Drain Type I =692/12600 RftDrain Type II=0/4560 RftBrick Pavement=11748/30970 CftSullage Carrier= 1878/2175 RftWork in progress.

• Date of AA =01.08.2017,• Date of TS =05.09.2017 ,• No. of Beneficiaries=5833• Date of receipt of tender= 11.09.2017,• Date Installation of Filtration Plant at 60/5L in of Work Order =31.10.2017, • Date of 1456 3059 Sahiwal 3.000 1.500 0.500 0.500 0.250 0.250 100% 1.750 58% Completion=30.06.2019 ,• District Sahiwal Latitude=30.62474333333333• Longitude= 73.26869833333333 Plant Room=1/1 Job RO Filtration Plant=1/1 No. Scheme completed.

• Date of AA =01.08.2017,• Date of TS =05.09.2017 ,• No. of Beneficiaries=2106• Date of receipt of tender= 11.09.2017,• Date Installation of Filtration Plant at 79/5R in of Work Order= 31.10.2017, • Date of 1457 3060 Sahiwal 3.000 1.500 0.500 0.500 0.075 0.072 96% 1.572 52% Completion =30.06.2019 , • District Sahiwal Latitude=30.69822• Longitude= 73.15358333333333Plant Room=1/1 JobRO Filtration Plant=1/1 No.Scheme completed in saving.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 23.09.2017, Funds released by FD = 03.08.2018, Funds online = 13.08.2018, Latitude longitude 30.385195,73.36082333333334 Inv. Of Rural Water Supply Scheme ChakNo. Source= 1/1 JobTube Well = 1/1 No.Pump 1458 3061 Pakpattan 31.190 9.000 7.397 7.397 5.548 5.548 100% 14.548 47% House= 1/1 No.House 20/SP Tehsil and District Pakpattan Connection=945/0Pumping Machinery= 1/1 SetR/Main &D/System = 3" i/d PVC= 31211/31211 Rft4" i/d PVC= 5085/5085 Rft6" i/d PVC= 1470/1470 Rft8" i/d PVC= 2135/2135 RftExternal Electrification= 1/1 JobHypo Chlorinator= 1/1 No.OHR 20000 G=1/1 No.Boundry Wall= 400/400 RftStaff Quarter= 1/1 No. Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 31.10.2017, Funds released by FD = 03.08.2018, Funds online = 13.08.2018, Latitude longitude 30.37893166666667,73.49669166666666 Rural Water Supply Scheme Kumari Wala Inv. Of Source= 1/1 JobTube Well = 1/1 1459 3062 Pakpattan 34.670 14.978 5.223 5.223 3.917 3.917 100% 18.895 54% No.Pump House= 1/1 No.House Tehsil and District Pakpattan Connection=822/822Pumping Machinery= 1/1 SetR/Main &D/System = 3" i/d PVC= 28690/33567 Rft4" i/d PVC= 8905/13477 Rft6" i/d PVC= 1820/1537 Rft8" i/d PVC= 180/180 RftExternal Electrification= 1/1 JobHypo Chlorinator= 1/1 No.OHR 20000 G=1/1 No.Boundry Wall= 400/400 RftStaff Quarter= 1/1 No. Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 23.09.2017, Funds released by FD = 03.08.2018 Funds online = 13.08.2018, Latitude longitude 30.51861666666667,73.39435166666667 Rural Water Supply Scheme Chak No. Inv. Of Source= 1/1 JobTube Well = 1/1 1460 3063 Pakpattan 32.440 8.700 7.813 7.813 5.860 5.860 100% 14.560 45% No.Pump House= 1/1 No.House 67/D Tehsil and District Pakpattan Connection=1105/0Pumping Machinery= 1/1 SetR/Main &D/System = 3" i/d PVC= 43950/27381 Rft4" i/d PVC= 2745/2324 Rft6" i/d PVC= 1374/1371 Rft8" i/d PVC= 1910/1794 RftExternal Electrification= 1/1 JobHypo Chlorinator= 1/0 No.OHR 20000 G=1/1 No.Boundry Wall= 400/400 RftStaff Quarter= 1/1 No. Work in progress.

Date of A.A= 01.08.2017. Date of T.S= 04.08.2017. Date of receipt of tenders = 24.08.2017. Date of work order= 18.09.2017. Funds released by FD = 03.08.2018 Funds online = 13.08.2018, Latitude longitude 30.470286666666667,73.34706166666666 Inv. Of Source= 1/1 JobTube Well = 1/1 Rural Water Supply Scheme Dhupai Tehsil 1461 3064 Pakpattan 29.980 16.000 4.660 4.660 3.495 3.495 100% 19.495 65% No.Pump House= 1/1 No.House and District Pakpattan Connection=1105/0Pumping Machinery= 1/0 SetR/Main &D/System = 3" i/d PVC= 19785/19258 Rft4" i/d PVC= 2425/1553 Rft6" i/d PVC= 1580/1401 Rft8" i/d PVC= 1910/1794 RftExternal Electrification= 1/0 JobHypo Chlorinator= 1/0 No.OHR 20000 G=1/1 No.Boundry Wall= 250/0 RftStaff Quarter= 1/0 No.Complaint Cell= 1 No./1 No. Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 31.10.2017, Funds released by FD = 03.08.2018 Funds online = 13.08.2018, Latitude longitude 30.12597333333333,73.00135666666667In Rural Water Supply Scheme Chak No. 1462 3065 Pakpattan 19.978 10.000 3.326 3.326 2.495 2.495 100% 12.495 63% v. Of Source= 1/1 JobTube Well = 1/1 29/KB in District Pakpattan NoPump House= 1/1 NoPumping Machinery= 1/1 SetR/Main &D/System = 3" i/d PVC= 40836/39006 Rft4" i/d PVC= 7967/8164 Rft6" i/d PVC= 1040/1110 RftExternal Electrufction= 1/1 JobHypo Chlorinator+ 0/1NoOHR 20000 G=1/1 NoBoundry Wall= 540/300 RftStaff Quarter= 1/1No Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 31.10.2017, Funds released by FD = 03.08.2018 Funds online = 13.08.2018, Latitude longitude 30.189791666666665,72.96276166666667I Rural Water Supply Scheme Chak No. nv. Of Source= 1/1 JobTube Well = 1/1 1463 3066 Pakpattan 29.412 8.000 7.137 7.137 5.353 5.353 100% 13.353 45% NoPump House= 1/1 NoPumping 111/EB in District Pakpattan Machinery= 1/1 SetR/Main &D/System 3" i/d PVC= 53094/53862 Rft4" i/d PVC= 4164/6040 Rft6" i/d PVC= 1256/5237 Rft8" i/d PVC= 0/426 Rft10" i/d PVC= 0/400 RftExternal Electrufction= 1/1 JobHypo Chlorinator+ 1/1NoOHR 10000 G=1/1 NoBoundry Wall= 0/200 Rft Work in progress. Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 23.09.2017, Funds released by FD = Rural Drainage Scheme Chak No. 74/D 1464 3067 Pakpattan 27.671 15.000 4.224 4.224 3.168 3.168 100% 18.168 66% 03.08.2018 Funds online = 13.08.2018, Tehsil and District Pakpattan Latitude longitude 30.189791666666665,72.96276166666667 Surface Drain Type-I=27415/4635 RftBrick Pavement=70482/60496 CftPacca Sullage Carrier=3925/10258 Rft Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 31.10.2017, Funds released by FD = Rural Drainage Scheme 8/EB Tehsil and 1465 3068 Pakpattan 23.979 13.979 3.333 3.333 2.500 2.500 100% 16.479 69% 03.08.2018 Funds online = 13.08.2018, District Pakpattn Latitude longitude 30.541859999999996,73.26302833333332 Surface Drain Type-I=18744/12412 RftBrick Pavement=67031/73954 CftPacca Sullage Carrier=3210/5306 Rft Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 23.09.2017, Funds released by FD = Rural Drainage Scheme 90/D Tehsil and 1466 3069 Pakpattan 29.303 19.000 3.434 3.434 2.576 2.576 100% 21.576 74% 03.08.2018 Funds online = 13.08.2018, District Pakpattan Latitude longitud e 30.48664666666667,73.13716500000001S urface Drain Type-I=22286/10306 RftBrick Pavement=70980/73995 CftPacca Sullage Carrier=5512/5579 Rft Work in progress. Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Date of receipt of tenders = 21.10.2017, Date of work order= 13.11.2017, Funds released by FD = Rural Drainage scheme in Various UCs of 03.08.2018, Funds online = 13.08.2018, 1467 3070 Pakpattan 74.312 25.000 8.333 8.333 6.250 6.250 100% 31.250 42% Latitude longitu de PP-228 District Pakpattan 30.321273333333338,73.37348 Surface Drain Type-I=21600/0 RftBrick Pavement=256286/146692 CftPacca Sullage Carrier=15406/5012 Rft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Date of receipt of tenders = 21.10.2017, Date of work order= 13.11.2017, Funds released by FD = Provision of Sewerage/ Tuff Tile / PCC / 03.08.2018 Funds online = 15.08.2018, Latitude longitude 1468 3071 Soling / Nallian in Various UC's of PP-228 Pakpattan 74.312 25.000 16.437 16.437 12.328 12.328 100% 37.328 50% 30.361086666666665,73.36713833333333 in District Pakpattan Surface Drain Type-I=1190/0 RftBrick Pavement=44028/7098 CftP.C.C=8391/0 RftTuff Pavers=451973/203791 SftR.C.C Sewer 9"i/d =210/18 Rft12"i/d=10985/7252 Rft15"i/d=328/0 Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 31.10.2017, Funds released by FD = 03.08.2018 Funds online = 13.08.2018, Latitude longitude 30.093911666666667,72.977715Surface Rural Sewerage / Drainage Scheme 1469 3072 Pakpattan 37.413 6.000 10.471 10.471 7.853 7.853 100% 13.853 37% Drain Type-I= 1403/15302 Rft Type II= Jamman Shah in District Pakpattan 0/310 RftBrick Pavement=20089/51463 CftRCC Sewer 9'' 0/736Rft 12'' i/d= 1713/1184 RftS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Machinery = 2/2 SetSullage Carrier1x1'= 5924/3050 RftSullage Carrier1.5x1.5'= 3180/7500 RftSullage Carrier2x2'= 788/1100 RftOxidation Pond= 2/2 No Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 23.09.2017, Funds released by FD = 03.08.2018, Funds online = 13.08.2018, Rural Sewerage / Drainage Scheme Chak Latitude longitude 1470 3073 Pakpattan 31.582 20.000 1.304 1.304 0.978 0.978 100% 20.978 66% 30.147768333333335,72.97831Surface No. 123/EB in District Pakpattan Drain Type-I= 100 Rft Brick Pavement=24934 CftRCC Sewer 9'' -15" = 18840 RftS/Chamber = 1 NoC/Tank = 1 NoP/Chamber = 1NoP/Machinery = 2 SetSullage Carrier= 2472 RftBoundry Wall= 390 Rft Work in progress.

Date of A.A= 01.08.2017, Date of T.S= 04.08.2017, Date of receipt of tenders = 24.08.2017, Date of work order= 23.09.2017, Funds released by FD = 03.08.2018, Funds online = 13.08.2018, Latitude longitude 30.241041666666668,72.93208833333333 Rural Sewerage / Drainage Scheme Chak 1471 3074 Pakpattan 36.230 27.376 2.610 2.610 1.958 1.958 100% 29.334 81% Surface Drain Type-I= 0/100 Rft Brick No.211/EB in District Pakpattan Pavement=24934/24934 CftRCC Sewer 9" i/d RCC Sewer 13064/14189 RFt12" i/d RCC Sewer 4968/5260 RFt15" i/d RCC Sewer 795/799 RFtS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Chamber = 1/1NoP/Machinery = 2/2 SetSullage Carrier= 2472/2472 RftBoundry Wall= 390/390 Rft Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Amended A.A issued on 27.01.2018.Tender received on 07.02.2018 and Additional performance security received on 13.02.2018 and Work order issued on 17.02.2018. Funds released by FD = 03.08.2018 Funds online = 13.08.2018, Latitude longitude 30.29019,73.00874166666668Surface Provision of Drainage/ Sewerage Schemes Drain Type-I= 0/15000 Rft Type II= 0/1500 at Chak No. 161/E.B and Union Council RftBrick Pavement=15975/31708 CftRCC 1472 3075 Pakpattan 35.785 12.976 6.762 6.762 5.072 3.381 67% 16.357 46% Sewer 9" i/d RCC Sewer 0/5289 RFt12" i/d NO.35 (Headquarters 13/EB) Tehsil RCC Sewer 0/612 RFt15" i/d RCC Sewer Arifwala District Pakpattan 0/845 RFt18" i/d RCC Sewer 0/801 RFtS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Chamber = 1/1NoP/Machinery = 0/2 SetSullage Carrier= 6540/16920 RftBoundry Wall= 0/300 Rft Work in progress. Contractor liability amounting to Rs.2.500 million stands. The case submitted to P&D Department Lahore for correction of project code.

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Date of receipt of tenders = 21.10.2017, Date of work order= 13.11.2017, Funds released by FD = Provision of PCC / Sewerage / Drainage / 03.08.2018 Funds online = 15.08.2018, 1473 3076 Pakpattan 150.000 33.142 8.333 8.333 6.250 6.250 100% 39.392 26% Latitude longitude Tuff tiles etc. in PP-227, District Pakpattan 30.366035000000004,73.41742666666667 Surface Drain Type-I=47371/11895 RftBrick Pavement=538576/189777 CftPacca Sullage Carrier=12476/1242 Rft Work in progress.

Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Date of receipt of tenders = 21.10.2017, Date of work order= 13.11.2017, Funds released by FD = 03.08.2018 Funds online = 15.08.2018, Provision of PCC / Sewerage / Drainage / 1474 3077 Pakpattan 148.624 34.998 16.667 16.667 12.500 12.500 100% 47.498 32% Latitude longitude Tuff tiles etc. in NA-165, District Pakpattan 30.35083666666667,73.37556666666666S urface Drain Type-I=30707/2898 RftBrick Pavement=481247/252154 CftPacca Sullage Carrier=12407/4845 RftTuff Pavers=184831/15239 SftR.C.C Sewer 12"i/d =6532/0 Rft Work in progress. Date of A.A= 24.08.2017, Date of T.S= 12.10.2017, Date of receipt of tenders = 21.10.2017, Date of work order= 13.11.2017, Funds released by FD = 03.08.2018 Funds online = 15.08.2018, Latitude longitude Provision of PCC / Sewerage / Drainage / 30.35083666666667,73.37556666666666ur 1475 3078 Pakpattan 148.624 31.997 8.333 8.333 6.250 6.250 100% 38.247 26% face Drain Type-I= 1388/60742 Rft Type Tuff Tiles etc. in PP-231 II=0/520 RftBrick Pavement=145930/494717 CftRCC Sewer 9'' 856/2820 Rft 15" i/d 0/500 RftS/Chamber = 1/1 NoC/Tank = 1/1 NoP/Chamber = 1/1NoP/Machinery = 4/4 SetSullage Carrier= 4500/16982 RftOxi/ Pondl= 0/2 No Work in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Water Supply and Drainage Scheme 05.12.2017 6.Date of work order 10.01.2018 1476 3079 Basti Nazak Nagar, Tehsil Jalapur Pirwala, Multan 49.180 14.982 11.393 11.393 8.545 7.650 90% 22.632 46% 7.Date of Completion as per PC-l District Multan 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4578 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Basti 05.12.2017 6.Date of work order 22.12.2017 1477 3080 Bahadur Pur Tehsil Jalalpur Pirwala District Multan 48.970 14.960 11.323 11.323 8.492 8.459 100% 23.419 48% 7.Date of Completion as per PC-l Multan 21.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Shujat 1478 3081 Multan 49.070 15.000 11.357 11.357 8.518 8.514 100% 23.514 48% 05.12.2017 6.Date of work order 23.12.2017 Pur Tehsil Jalalpur Pirwala District Multan 7.Date of Completion as per PC-l 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries - persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Water Supply Scheme Chak No.55/M 1479 3082 Multan 14.000 4.947 3.000 3.000 2.250 2.250 100% 7.197 51% 6.Date of work order 03.11.2017 7.Date of and 56/M District Multan Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4572 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Water Supply Scheme Chak No.71, 1480 3083 Multan 21.000 9.834 3.667 3.667 2.750 2.569 93% 12.403 59% 6.Date of work order 27.11.2017 7.Date of 72 & 73/M District Multan Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6354 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Water Supply Scheme Chak No.76, 1481 3084 Multan 21.000 9.949 3.667 3.667 2.750 2.564 93% 12.513 60% 6.Date of work order 27.11.2017 7.Date of 77 and 78/M District Multan Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4687 persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Water Supply Scheme Chak No.79, 1482 3085 Multan 21.000 9.853 3.667 3.667 2.750 2.500 91% 12.353 59% 6.Date of work order 27.11.2017 7.Date of 80 & 81/M District Multan Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6554 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Rural Water Supply Scheme Mouza Obvra 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 03.11.2017 7.Date of 1483 3086 Shumali Saray Khara and Jungle Ameer Multan 14.000 6.840 2.333 2.333 1.750 1.580 90% 8.420 60% Completion as per PC-l 02.05.2018 8. Hussain District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12354 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Basti Nandla 05.12.2017 6.Date of work order 19.01.2018 1484 3087 Multan 45.000 14.990 3.333 3.333 2.500 2.491 100% 17.481 39% 7.Date of Completion as per PC-l North & South District Multan 18.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11358 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Adda band 05.12.2017 6.Date of work order 01.01.2018 1485 3088 Bosan, Roye Hatti & Mattay Hatti District Multan 40.600 9.919 3.333 3.333 2.500 2.250 90% 12.169 30% 7.Date of Completion as per PC-l Multan 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13474 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Sewerage Scheme Ghousabad, 1486 3089 Multan 37.000 8.690 3.333 3.333 2.500 2.270 91% 10.960 30% 6.Date of work order 29.12.2017 7.Date of District Multan Completion as per PC-l 28.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 14879 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage / Sewerage Scheme Chah 1487 3090 Multan 14.970 9.995 1.657 1.657 3.343 1.120 34% 11.115 74% 6.Date of work order 23.12.2017 7.Date of Bananwala District Multan Completion as per PC-l 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 9476 persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Taj Pur Sandila, 05.12.2017 6.Date of work order 29.12.2017 1488 3091 Dhareeban Thahti Sandila Faiz Town UC Multan 49.980 14.980 3.333 3.333 2.500 2.488 100% 17.468 35% 7.Date of Completion as per PC-l 95 Tehshil & District Multan 28.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4658 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Sewerage Scheme Qasim Bela, Basti 1489 3092 Multan 32.410 13.975 3.333 3.333 2.500 2.270 91% 16.245 50% 6.Date of work order 28.12.2017 7.Date of Langrial Tehsil and District Multan Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4789 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Mouza Ajwani / 05.12.2017 6.Date of work order 05.01.2018 1490 3093 Multan 96.500 29.998 3.333 3.333 2.500 2.498 100% 32.496 34% 7.Date of Completion as per PC-l Sharif District Multan 04.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6589 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage, Soling and Tuff Tile 05.12.2017 6.Date of work order 17.01.2018 1491 3094 Scheme in Union Council Bagrian District Multan 50.000 19.949 3.333 3.333 2.500 2.500 100% 22.449 45% 7.Date of Completion as per PC-l Multan 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage, Soling and Tuff Tile 05.12.2017 6.Date of work order 27.12.2017 1492 3095 Scheme in Union Council Hilal Wajah Multan 50.000 19.973 3.333 3.333 2.500 2.489 100% 22.462 45% 7.Date of Completion as per PC-l District Multan 26.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage, Soling and Tuff Tile 05.12.2017 6.Date of work order 23.12.2017 1493 3096 Scheme in Union Council Gardez Pur Multan 50.000 19.981 3.333 3.333 2.500 2.500 100% 22.481 45% 7.Date of Completion as per PC-l District Multan 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Kotla 05.12.2017 6.Date of work order 28.12.2017 1494 3097 Multan 50.000 20.000 3.333 3.333 2.500 2.500 100% 22.500 45% 7.Date of Completion as per PC-l Chakar Jalalpur Pirwala District Multan 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4587 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage / Sewerage Scheme Basti 1495 3098 Multan 30.000 9.850 3.333 3.333 2.500 2.500 100% 12.350 41% 6.Date of work order 10.11.2017 7.Date of Mithu Gharbi District Multan Completion as per PC-l 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13254 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage / Sewerage Scheme 1496 3099 Multan 33.000 11.974 3.333 3.333 2.500 2.490 100% 14.464 44% 6.Date of work order 21.12.2017 7.Date of Muqeempur District Multan Completion as per PC-l 20.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13546 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage / Sewerage Scheme 1497 3100 Multan 39.000 11.994 3.333 3.333 2.500 2.487 99% 14.481 37% 6.Date of work order 10.01.2018 7.Date of Munshi Wala District Multan Completion as per PC-l 09.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12144 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage / Sewerage Scheme Lal 1498 3101 Multan 25.000 9.931 3.333 3.333 2.500 2.250 90% 12.181 49% 6.Date of work order 11.12.2017 7.Date of Wah District Multan Completion as per PC-l 10.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 14456 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage / Sewerage Scheme Obara 1499 3102 Multan 30.000 11.699 3.333 3.333 2.500 2.500 100% 14.199 47% 6.Date of work order 10.11.2017 7.Date of Shumali District Multan Completion as per PC-l 09.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11243 persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Drainage / Sewerage Scheme Jagoo 05.12.2017 6.Date of work order 01.02.2018 1500 3103 Multan 50.000 9.976 3.333 3.333 2.500 2.250 90% 12.226 24% 7.Date of Completion as per PC-l Wala District Multan 30.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 3547 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Sewerage / Drainage Scheme Kotla 1501 3104 Multan 20.000 9.990 3.333 3.333 2.500 2.500 100% 12.490 62% 6.Date of work order 28.12.2017 7.Date of Abdul Fateh District Multan Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 6547 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Rural Drainage Scheme Basti Kothy Wala, 5.Date of Receipt of tenders 18.10.2017 New Kothy Wala, Basti Utar Wali and 1502 3105 Multan 30.000 9.994 3.333 3.333 2.500 2.500 100% 12.494 42% 6.Date of work order 19.02.2018 7.Date of Haroo Wala Mouza Kothy Wala District Completion as per PC-l 18.08.2018 8. Anticipated date of completion 30.06.2019 Multan 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries - persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage Scheme UC 18/MR, District 1503 3106 Multan 26.000 9.521 3.333 3.333 2.500 2.270 91% 11.791 45% 6.Date of work order 28.01.2018 7.Date of Multan Completion as per PC-l 27.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries - persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Water Supply Scheme Mouza Matotli 1504 3107 Multan 14.000 6.962 2.333 2.333 1.750 1.750 100% 8.712 62% 6.Date of work order 03.11.2017 7.Date of and Qaiser Pur District Multan Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 10452 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Water Supply Scheme Mouza Sha 1505 3108 Multan 14.000 6.942 2.333 2.333 1.750 1.588 91% 8.530 61% 6.Date of work order 03.11.2017 7.Date of Musa and Muqeem Pur District Multan Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11365 persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Rural Water Supply Scheme Mouza Adu 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 14.12.2017 7.Date of 1506 3109 Wali, Inayat Pur, Mochi Panhuwah, Basti Multan 21.000 9.849 3.667 3.667 2.750 2.750 100% 12.599 60% Completion as per PC-l 13.06.2018 8. Bairar District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 9878 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Rural Water Supply Scheme Mouza Obvra 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 03.11.2017 7.Date of 1507 3110 Janubi, Basti Lang and Nauraja Bhutta Multan 15.000 6.844 2.667 2.667 2.000 1.904 95% 8.748 58% Completion as per PC-l 02.05.2018 8. District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 7458 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage/ Drainage scheme Katcha 05.12.2017 6.Date of work order 13.01.2018 1508 3111 Talla, ict Munirabad, Kot Shehbaz Pull 18- Multan 44.530 15.000 9.843 9.843 7.382 7.370 100% 22.370 50% 7.Date of Completion as per PC-l Kassi Bhdhla Road Tehsil & district Multan 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 11354 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme 18-Kassi 05.12.2017 6.Date of work order 28.12.2017 1509 3112 Ghareeb Abad and Adjoining Abadies UC Multan 44.470 14.956 9.823 9.823 7.367 6.700 91% 21.656 49% 7.Date of Completion as per PC-l Jhok Lashkar Pur District Multan 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4687 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Rural Sewerage Scheme Asghar Pur and 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 23.12.2017 7.Date of 1510 3113 Munir Abad, UC Jhok Lashkar Pur District Multan 15.000 10.000 1.667 1.667 1.250 1.125 90% 11.125 74% Completion as per PC-l 22.05.2018 8. Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 4589 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage Scheme UC Kot Rab 1511 3114 Multan 15.000 10.000 1.667 1.667 1.250 1.248 100% 11.248 75% 6.Date of work order 14.12.2017 7.Date of Nawaz, UC 120 District Multan Completion as per PC-l 13.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage Scheme UC 123 Jalal Abad 1512 3115 Multan 15.000 9.962 1.667 1.667 1.250 1.222 98% 11.184 75% 6.Date of work order 28.12.2017 7.Date of Shumali District Multan Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage Scheme UC 131 Chatha 1513 3116 Multan 20.000 9.997 3.333 3.333 2.500 2.500 100% 12.497 62% 6.Date of work order 03.11.2017 7.Date of District Multan Completion as per PC-l 02.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage Scheme UC 134 Kiri Tamak 1514 3117 Multan 20.000 9.910 3.333 3.333 2.500 2.368 95% 12.278 61% 6.Date of work order 21.11.2017 7.Date of District Multan Completion as per PC-l 20.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Sewerage Scheme Basti Beat Wala 1515 3118 Multan 11.540 4.982 2.180 2.180 1.635 1.500 92% 6.482 56% 6.Date of work order 28.12.2017 7.Date of Ajwain Sharif Tehsil & District Multan Completion as per PC-l 27.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries= 12358 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Tiab Masood Pur, 05.12.2017 6.Date of work order 23.12.2017 1516 3119 Multan 33.470 12.346 3.333 3.333 2.500 2.487 99% 14.833 44% 7.Date of Completion as per PC-l Tehsil & District Multan 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =14356 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Sewerage Scheme Sharif Pura New 1517 3120 Multan 38.080 10.625 3.333 3.333 2.700 2.500 93% 13.125 34% 6.Date of work order 19.01.2018 7.Date of Shalimar Tehsil & District Multan Completion as per PC-l 18.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =10358 persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Rural Sewerage Scheme Gareen Town 05.12.2017 6.Date of work order 14.02.2018 1518 3121 Multan 41.960 7.499 3.333 3.333 2.500 2.500 100% 9.999 24% 7.Date of Completion as per PC-l Deen Pur & Jarran Wala District Multan 13.08.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =12548 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Sewerage Scheme Zakaria Town Phase-III 1519 3122 Multan 16.500 9.908 2.167 2.167 1.625 1.618 100% 11.526 70% 6.Date of work order 27.11.2017 7.Date of District Multan Completion as per PC-l 26.05.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =14225 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Main Sewerage Line for Farrukh Town & 05.12.2017 6.Date of work order 04.01.2018 1520 3123 Multan 49.990 25.000 3.333 3.333 2.500 2.492 100% 27.492 55% 7.Date of Completion as per PC-l Raja Pur, District Multan 03.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =11658 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 14.12.2017 7.Date of 1521 3124 Water Purification Plants 10 District Multan Multan 20.000 9.940 3.333 3.333 2.500 2.270 91% 12.210 61% Completion as per PC-l 13.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries =14212 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 5.Date of Receipt of tenders 18.10.2017 Rural Drainage Scheme UC-Khan Pur 1522 3125 Multan 13.000 9.967 1.000 1.000 0.750 0.680 91% 10.647 82% 6.Date of work order 30.01.2018 7.Date of maral, District Multan Completion as per PC-l 29.07.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries = persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Funds for drain/sewerage and soling for UC 05.12.2017 6.Date of work order 05.01.2018 1523 3126 Multan 80.000 26.735 3.333 3.333 8.884 8.825 99% 35.560 44% 7.Date of Completion as per PC-l 95 & 96 City Shujabad. District Multan 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries= 5587 persons. Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Funds for drain/sewerage, soling from Raja 05.12.2017 6.Date of work order 23.12.2017 1524 3127 Multan 40.000 16.976 3.333 3.333 2.500 2.498 100% 19.474 49% 7.Date of Completion as per PC-l Ram, Bagrain and Shahpur. District Multan 22.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries= 6987 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S Rural Sewerage and Drainage Scheme, 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Tuff Tile Pavement in Basti Ado Wali, Basti 5.Date of Receipt of tenders 18.10.2017 Adam Wali, Basti Dhando, Basti Hayat Pur, 1525 3128 Multan 28.000 14.999 4.333 4.333 3.250 2.950 91% 17.949 64% 6.Date of work order 21.11.2017 7.Date of Basti Balocha, Wach Sandela, Basti Ali Pur Completion as per PC-l 20.05.2019 8. Anticipated date of completion 30.06.2019 Sadat and Basti Gull Wala UC Ali Pur 9. Date of released of funds 03.08.2018 Sadat District Multan 24.01.2019 10.No. of beneficiaries =15325 persons. Work is in progress

Rural Sewerage and Drainage Scheme, 1.Date of AA 03.08.2017 2.Date of T.S Tuff Tile Pavement in Basti Brar, Basti 08.08.2017 3.Dated of Prequalification - Pathan Wala, Basti Ahmad Wali, Basti 4.Date of invitation of tender 27.09.2017 Daya, Basti Barzawah, Basti Lohar, Basti 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 29.11.2017 7.Date of 1526 3129 Inayat Pur, Basti Sial, Basti Saif Ullah Shah, Multan 30.000 9.972 6.667 6.667 5.000 4.520 90% 14.492 48% Completion as per PC-l 28.05.2019 8. Basti Gakhar, Basti Bagh Arain Wali, Basti Anticipated date of completion 30.06.2019 Miani, Basti Ranojha, Basti Saich Wali, 9. Date of released of funds 30.08.2018 24.01.2019 10.No. of beneficiaries 16358 Basti Deewan Wali and Basti Mochian Wali persons. Work is in progress UC Inayat Pur District Multan

1.Date of AA 03.08.2017 2.Date of T.S Rural Sewerage and Drainage Scheme, 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Tuff Tile Pavement in Basti Radal Pur, Basti 5.Date of Receipt of tenders 18.10.2017 Lutaf Pur, Chak Numberabad, Molvi Wala, 1527 3130 Multan 30.000 9.800 3.333 3.333 2.500 2.250 90% 12.050 40% 6.Date of work order 28.12.2017 7.Date of Basti Cut Wala, Tibbi Qasian, Basti Completion as per PC-l 27.06.2019 8. Anticipated date of completion 30.06.2019 Balochan Wala UC Radal Pur District 9. Date of released of funds 30.08.2018 Multan 24.01.2019 10.No. of beneficiaries 14325 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - Rural Sewerage and Drainage Scheme, 4.Date of invitation of tender 27.09.2017 Tuff Tile Pavement in Basti Mari Noon, 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 28.12.2017 7.Date of 1528 3131 Basti Godar, Basti Dogran, Basti Khokhran, Multan 30.000 11.997 3.333 3.333 2.500 2.270 91% 14.267 48% Completion as per PC-l 27.05.2018 8. Basti Ghous Pur UC Mari Noon District Anticipated date of completion 30.06.2019 Multan 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12442 persons. Work is in progress

1.Date of AA 03.08.2017 2.Date of T.S 09.09.2017 3.Dated of Prequalification - Rough Cost Estimates for replacement of 4.Date of invitation of tender 27.09.2017 Old Sewer Lines at Muhalla Sharif Pura UC 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 20.11.2017 7.Date of 1529 3132 65 Piran Ghaib II in Sub Division New Multan 12.450 8.334 0.817 0.817 0.613 0.550 90% 8.884 71% Completion as per PC-l 19.05.2018 8. Multan Sewerage Central Division WASA Anticipated date of completion 30.06.2019 Multan 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 13225 persons. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Dated of Prequalification - 4.Date of invitation of tender 27.09.2017 Ext. of Rual Drainage / Sewerage Scheme 5.Date of Receipt of tenders 18.10.2017 6.Date of work order 22.11.2017 7.Date of 1530 3133 Chah Muhammad Hussain wala & Multan 29.510 12.478 3.333 3.333 2.500 2.270 91% 14.748 50% Completion as per PC-l 21.05.2018 8. Adjoining Ababdies District Multan Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 12455 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders Scheme / Drainage Scheme Kotli Nijabat 05.12.2017 6.Date of work order 05.01.2018 1531 3134 Multan 69.500 21.924 3.333 3.333 2.500 2.500 100% 24.424 35% 7.Date of Completion as per PC-l District Multan 30.06.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 15654 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders 05.12.2017 6.Date of work order 03.03.2018 1532 3135 Sewerage System in UC-90 District Multan Multan 65.000 4.958 3.333 3.333 2.500 2.250 90% 7.208 11% 7.Date of Completion as per PC-l 02.08.2018 8. Anticipated date of completion 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 9876 persons. Work is in progress 1.Date of AA 03.08.2017 2.Date of T.S 08.08.2017 3.Date of Prequalification 28.08.2017 4.Date of invitation of tender 02.12.2017 5.Date of Receipt of tenders 05.12.2017 6.Date of work order 20.02.2018 1533 3136 Sewerage System in UC-82 District Multan Multan 65.000 22.996 3.333 3.333 2.500 2.500 100% 25.496 39% 7.Date of Completion as per PC-l 19.02.2020 8. Anticipated date of completion 30.06.2020 9. Date of released of funds 03.08.2018 24.01.2019 10.No. of beneficiaries 15775 persons. Work is in progress 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2018 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme Chak No.7/9-R 1534 3137 Khanewal 12.000 6.000 2.000 2.000 1.500 1.500 100% 7.500 63% 24.10.2017 7. Date of Completion as per District Khanewal PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6340 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Construction of Drainage Scheme Chak 1535 3138 Khanewal 12.000 2.000 3.333 3.333 2.500 2.500 100% 4.500 38% 09.11.2017 7. Date of Completion as per No.93/10-R District Khanewal PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5788Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme Chak No.92/10-R 1536 3139 Khanewal 18.000 10.000 2.667 2.667 2.000 2.000 100% 12.000 67% 09.12.2017 7. Date of Completion as per District Khanewal PC-I: (8) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 8140 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme UC No. 48 Tehsil 1537 3140 Khanewal 11.000 5.000 2.000 2.000 1.500 1.500 100% 6.500 59% 24.10.2017 7. Date of Completion as per Mian Channu PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 8265 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme UC No. 51 Tehsil 1538 3141 Khanewal 12.000 6.000 2.000 2.000 1.500 1.421 95% 7.421 62% 09.12.2017 7. Date of Completion as per Mian Channu PC-I: (5) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6568 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme UC No. 55 Tehsil 1539 3142 Khanewal 12.000 7.000 1.667 1.667 1.966 1.783 91% 8.783 73% 24.10.2017 7. Date of Completion as per Mian Channu PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 65619 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme UC No. 56 Tehsil 1540 3143 Khanewal 11.000 6.000 1.667 1.667 1.250 1.250 100% 7.250 66% 17.11.2017 7. Date of Completion as per Mian Channu PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5790 Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme UC No. 62 Tehsil 1541 3144 Khanewal 12.000 6.000 2.000 2.000 1.500 1.500 100% 7.500 63% 24.10.2017 7. Date of Completion as per Mian Channu PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 5689 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Rural Drainage Scheme Chak No.134/16-L 1542 3145 Khanewal 12.000 6.000 2.000 2.000 1.500 1.500 100% 7.500 63% 24.10.2017 7. Date of Completion as per and Adjoining Abadies Tehsil Mian Channu PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6132 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: Rural Drainage Scheme Chak No 20/8-BR, 29.09.2017 6. Date of Work order: 24.10.2017 7. Date of Completion as per 1543 3146 1/8-R, 2/8-R, 3/8-R, 4/8-R and Adjoining Khanewal 12.000 7.000 1.667 1.667 1.250 1.250 100% 8.250 69% PC-I: (6) months 8. Anticipated Date of Abadies Tehsil Mian Channu completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 6443 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling 122/15-L District 1544 3147 Khanewal 3.000 2.385 0.167 0.167 0.016 0.016 100% 2.401 80% 24.10.2017 7. Date of Completion as per Khanewal PC-I: (6) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1936 Persons Scheme Completed in saving.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling 53/15-L District 1545 3148 Khanewal 3.000 2.500 0.167 0.167 0.000 0.000 #DIV/0! 2.500 83% 24.10.2017 7. Date of Completion as per Khanewal PC-I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1876 Persons Scheme Completed in saving. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling 58/15-L District 1546 3149 Khanewal 3.000 2.500 0.167 0.167 0.005 0.005 100% 2.505 84% 24.10.2017 7. Date of Completion as per Khanewal PC-I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1916 Persons Scheme completed in saving.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling 117/15-L District 1547 3150 Khanewal 3.000 2.500 0.167 0.167 0.000 0.000 #DIV/0! 2.500 83% 19.10.2017 7. Date of Completion as per Khanewal PC-I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 2065 Persons Scheme Completed in Saving.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling 42/15-L District 1548 3151 Khanewal 3.000 2.500 0.167 0.167 0.005 0.005 100% 2.505 84% 24.10.2017 7. Date of Completion as per Khanewal PC-I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1837 Persons Scheme Completed in Saving.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling 135/16-L District 1549 3152 Khanewal 3.000 2.500 0.167 0.167 0.125 0.125 100% 2.625 88% 24.10.2017 7. Date of Completion as per Khanewal PC-I: (5) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1926 Persons Work is in Progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling Pakka Haji Majeed 1550 3153 Khanewal 3.000 1.700 0.433 0.433 0.325 0.325 100% 2.025 68% 24.10.2017 7. Date of Completion as per District Khanewal PC-I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1966 Persons Work is in Progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 26.07.2017 2. Date of T.S: 20.09.2017 3. Date of Pre-Qualification: 05.09.2017 4. Date of Invitation of Tender: 09.11.2017 5. Date of Receipt of Tender: Rehabilitation of Sewerage Scheme 11.11.2017 6. Date of Work order: 23.11.2017 7. Date of Completion as per 1551 3154 Tulamba City in missed area Tehsil Mian Khanewal 49.990 15.000 3.333 3.333 2.500 2.500 100% 17.500 35% PC-I: (12)months 8. Anticipated Date of Channu completion: 31.12.2019 9. Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 2690 Persons Work is in progress.

1. Date of A.A: 26.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: ------4. Date of Invitation of Tender: 28.09.2017 5. Date of Receipt of Tender: 29.09.2017 6. Date of Work order: Drainage & Soling Chak No.8-9/8-AR 1552 3155 Khanewal 3.000 2.500 0.167 0.167 0.008 0.008 100% 2.508 84% 24.10.2017 7. Date of Completion as per District Khanewal PC-I: (3) months 8. Anticipated Date of completion: 30.06.2019 9. Date of released of funds 03-08-2018 24.01.2019 10. Reason of Slow Moving: ------11 No. of beneficiaries 1896 Persons Scheme Completed in Saving.

1. Date of A.A: 19.08.2017 2. Date of T.S: Constructino of Soling, Drains, Sullage 22.09.2017 3. Date of Pre-Qualification: Carrier, RCC Culverts in Union Councils 05.09.2017 4. Date of Invitation of Tender: 09.11.2017 5. Date of Receipt of Tender: Salar Wahan, Thull Najeeb, Man Kot, Chak 11.11.2017 6. Date of Work order: Norang Shah, Boota Singh, Mari Sahu 1553 3156 Khanewal 199.990 72.900 16.667 16.667 12.500 12.500 100% 85.400 43% 26.12.2017 7. Date of Completion as per Ibrahim Pur, Mubarak Pur, 5-Kassi, Mula PC-I: 31.12.2018 8. Anticipated Date of completion: 30.06.2019 9. Date of released Pur, Nabi Pur, Chak Haider Abad & Monga of funds 03-08-2018 24.01.2019 10. Reason Wala Tehsil Kabirwala in PP-213 District of Slow Moving: ------11 No. of Khanewal beneficiaries 11356 Persons Work is in Progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Water Supply Scheme Chak No.126/WB, Date of Award: 11.12.2017 7. Date of 1554 3157 Vehari 28.966 9.995 6.322 6.322 4.742 4.742 100% 14.737 51% Completion as per PC-I: 10.12.2018 8. 128/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ------11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rehabiliation of Water Supply Scheme Date of Award: 25.11.2017 7. Date of 1555 3158 Vehari 15.000 7.443 1.667 1.667 1.250 1.250 100% 8.693 58% Completion as per PC-I: 24.11.2018 8. Chak No.96/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Provision of Water Supply / Filtration Plants Date of Award: 25.11.2017 7. Date of 1556 3159 & Sewerage Scheme Chak No.233/EB Vehari 17.639 3.877 2.546 2.546 1.910 1.910 100% 5.787 33% Completion as per PC-I: 24.11.2018 8. District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Provision of Water Supply / Filtration Plants Date of Award: 25.11.2017 7. Date of 1557 3160 & Sewerage Scheme Chak No.249/EB Vehari 24.842 5.246 4.947 4.947 3.710 3.710 100% 8.956 36% Completion as per PC-I: 24.11.2018 8. District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Provision of Water Supply / Filtration Plants Date of Award: 25.11.2017 7. Date of 1558 3161 & Sewerage Scheme Chak No.251/EB Vehari 23.451 6.682 4.484 4.484 3.363 3.363 100% 10.045 43% Completion as per PC-I: 24.11.2018 8. District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Provision of Water Supply / Filtration Plants Date of Award: 25.11.2017 7. Date of 1559 3162 & Sewerage Scheme Chak No.243/EB Vehari 20.663 3.934 3.554 3.554 2.666 2.666 100% 6.600 32% Completion as per PC-I: 24.11.2018 8. District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ----- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Sewerage / Drainage & Water Supply Date of Award: 25.11.2017 7. Date of 1560 3163 Vehari 31.617 9.998 3.333 3.333 2.500 2.500 100% 12.498 40% Completion as per PC-I: 24.11.2018 8. Scheme Chak No.65/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Construction of Water Filtration Plants 16- Date Invitation of Tender: 23.10.2017 5. No in Chak No.05/WB, 18/WB, 22/WB, Date of Receipt of Tender: 24.10.2017 6. 65/WB, 59/WB, 93/WB, 97/WB, 56/Wb, Date of Award: 25.11.2017 7. Date of 1561 3164 Vehari 48.000 13.853 11.000 11.000 8.250 8.250 100% 22.103 46% Completion as per PC-I: 24.11.2018 8. 34/WB, Pull-48, Pull Mohsin Shah, 63/WB, Anticipated Date of Completion: 30.06.2019 24/WB, 26/WB, Noor Shah Melsi, Shittab 9.Date of released of funds 03.08.2018 Garh Melsi. 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Water Supply Scheme 176/WB Date of Award: 20.11.2017 7. Date of 1562 3165 Vehari 25.171 9.833 5.057 5.057 3.793 3.793 100% 13.626 54% Completion as per PC-I: 19.11.2018 8. Baghbanpura District Vehari Anticipated Date of Completion: 30.06.2019. 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Water Supply Scheme Chak Date of Award: 22.11.2017 7. Date of 1563 3166 Vehari 16.073 9.999 2.024 2.024 1.518 1.518 100% 11.517 72% Completion as per PC-I: 19.11.2018 8. No.182/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: --- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Water Supply Scheme Chak Date of Award: 25.11.2017 7. Date of 1564 3167 Vehari 28.673 9.991 6.224 6.224 4.668 4.668 100% 14.659 51% Completion as per PC-I: 24.11.2018 8. No.184/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Water Supply Scheme Chak Date of Award: 20.11.2017 7. Date of 1565 3168 Vehari 18.426 10.000 2.809 2.809 2.107 2.107 100% 12.107 66% Completion as per PC-I: 19.11.2018 8. No.161/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Water Supply Scheme Chak Date of Award: 20.11.2017 7. Date of 1566 3169 Vehari 31.485 9.960 7.162 7.162 5.372 5.372 100% 15.332 49% Completion as per PC-I: 19.11.2018 8. No.163/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 23.10.2017 5. Date of Receipt of Tender: 24.10.2017 6. Rural Water Supply Scheme Chak Date of Award: 20.11.2017 7. Date of 1567 3170 Vehari 17.583 9.978 2.528 2.528 1.896 1.896 100% 11.874 68% Completion as per PC-I: 19.11.2018 8. No.159/WB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: --- 11. No. of Beneficiary= Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 21.08.2017 2. Date of T.S: 19.10.2017 3. Date of Pre-Qualification: 27.10.2017 4. Date Invitation of Tender: 29.11.2017 5. Date of Receipt of Tender: Rural Water Supply Scheme Chak 30.11.2017 6. Date of Award: 27.12.2017 7. 1568 3171 No.50/WB Dahlu Hari Chand and 52 Sharqi Vehari 123.590 34.755 16.667 16.667 12.500 12.500 100% 47.255 38% Date of Completion as per PC-I: 26.12.2019 District Vehari 8. Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: --- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Sewerage Schemes Chak No.5/WB, Date of Award: 25.11.2017 7. Date of 1569 3172 Vehari 40.000 8.323 3.333 3.333 2.500 2.500 100% 10.823 27% Completion as per PC-I: 24.11.2018 8. 24/WB, 88/ WB and 90/WB. District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Drainage Sewer Scheme Chak No.110/WB Date of Award: 25.11.2017 7. Date of 1570 3173 Vehari 20.000 9.999 3.333 3.333 2.500 2.500 100% 12.499 62% Completion as per PC-I: 24.11.2018 8. District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling, Drainage & Culverts Date of Award: 25.11.2017 7. Date of 1571 3174 Vehari 15.000 6.917 2.500 2.500 1.875 1.875 100% 8.792 59% Completion as per PC-I: 24.11.2018 8. UC 46-173/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling, Drainage & Culverts Date of Award: 25.11.2017 7. Date of 1572 3175 Vehari 15.000 7.165 2.500 2.500 1.875 1.875 100% 9.040 60% Completion as per PC-I: 24.11.2018 8. UC 53-275/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: - 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Date of Construction of Soling, Drainage & Culverts 1573 3176 Vehari 15.000 9.807 1.667 1.667 1.250 1.250 100% 11.057 74% Award: 25.11.2017 7. Date of Completion UC 40-128/EB District Vehari as per PC-I: 24.11.2018 8. Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: NIL 11. No. of Beneficiary= Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling, Drainage & Culverts Date of Award: 25.11.2017 7. Date of 1574 3177 Vehari 15.000 9.967 1.667 1.667 1.250 1.250 100% 11.217 75% Completion as per PC-I: 24.11.2018 8. UC 44-199/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling, Drainage & Culverts Date of Award: 25.11.2017 7. Date of 1575 3178 Vehari 15.000 7.499 2.500 2.500 1.875 1.875 100% 9.374 62% Completion as per PC-I: 24.11.2018 8. UC 45-175/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling , Drainage & Date of Award: 25.11.2017 7. Date of 1576 3179 Vehari 25.000 12.285 4.167 4.167 3.125 3.125 100% 15.410 62% Completion as per PC-I: 26.11.2018 8. Culverts UC49-233/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling , Drainage & Date of Award: 25.11.2017 7. Date of 1577 3180 Vehari 25.000 12.500 4.167 4.167 3.125 3.125 100% 15.625 63% Completion as per PC-I: 24.11.2018 8. Culverts UC47-215/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 07.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Construction of Soling , Drainage & Date of Award: 25.11.2017 7. Date of 1578 3181 Vehari 15.000 12.499 0.833 0.833 0.625 0.625 100% 13.124 87% Completion as per PC-I: 24.11.2018 8. Culverts UC48-187/EB District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of Receipt of Tender: 28.10.2017 6. Rural Sewerage / Drainage Scheme Chak Date of Award: 25.11.2017 7. Date of 1579 3182 Vehari 15.000 6.915 2.667 2.667 2.000 2.000 100% 8.915 59% Completion as per PC-I: 24.11.2018 8. No. 57/WB Tehsil & District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of A.A: 31.07.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: - 4. Date Invitation of Tender: 26.10.2017 5. Date of receipt of tender: 28.10.2017 6. Rural Sewerage / Drainage Scheme Chak Date of Award: 25.11.2017 7. Date of 1580 3183 Vehari 16.000 7.999 2.667 2.667 2.000 2.000 100% 9.999 62% Completion as per PC-I: 24.11.2018 8. No. 53/WB Tehsil & District Vehari Anticipated Date of Completion: 30.06.2019 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress.

1. Date of A.A: 06.09.2017. 2. Date of T.S: 08.08.2017 3. Date of Pre-Qualification: 27.10.2017 4. Date Invitation of Tender: 29.11.2017 5. Date of receipt of tender: Rehabilitation and Extension of Water 30.11.2017 6. Date of Award: 19.01.2018 7. 1581 3184 Supply & Sewerage Schemes Mailsi and Vehari 279.804 74.459 33.333 33.333 25.000 25.000 100% 99.459 36% Date of Completion as per PC-I: 18.01.2021 Adjoining Abadies. District Vehari 8. Anticipated Date of Completion: 18.01.2021 9.Date of released of funds 03.08.2018 24.01.2019 10. Reason of Slow Moving: ---- 11. No. of Beneficiary= Persons Work is in progress. Construction of Nali Soling Tuff Tile & Dera Ghazi 1582 3185 Culverts UC Kot Mubarak, Shero Satal and 11.500 4.955 2.167 2.167 1.625 1.593 98% 6.548 57% "• Date of A.A = 13.1.17 Khan Yaroo DG Khan Construction of Nali Soling Culverts and Dera Ghazi 1583 3186 20.000 9.975 3.333 3.333 2.500 2.475 99% 12.450 62% "• Date of A.A = 13.1.17 Tuff Tile U/C Palgah Chak NO.3 DG Khan Khan Construction of Nali Soling & Culverts UC Dera Ghazi 1584 3187 13.000 6.999 2.000 2.000 1.500 1.470 98% 8.469 65% "• Date of A.A = 13.1.17 Dagar Chitt. DG Khan Khan Construction of Nali Soling Tuff Tile of Basti Dera Ghazi 1585 3188 14.000 6.643 2.333 2.333 1.750 1.733 99% 8.376 60% "• Date of A.A = 13.1.17 Foja and Darkhast Jamal Janubi DG Khan Khan Construction of Nali Soling Tuff Tiles in UC Dera Ghazi 1586 3189 13.610 6.617 2.203 2.203 1.652 1.635 99% 8.252 61% "• Date of A.A = 13.1.17 Basti Malana DG Khan Khan Construction of Sewerage Nali Soling & Dera Ghazi 1587 3190 11.000 4.986 2.000 2.000 1.500 1.470 98% 6.456 59% "• Date of A.A = 13.1.17 Culverts / Bridge UC Khakhi. DG Khan Khan Construction of Nali Soling Tuff Tile & Dera Ghazi 1588 3191 12.000 4.985 2.333 2.333 1.750 1.715 98% 6.700 56% "• Date of A.A = 13.1.17 Culverts UC Kala DG Khan Khan Construction of Nali Soling Tuff Tile & Dera Ghazi 1589 3192 14.000 6.000 2.667 2.667 2.000 1.960 98% 7.960 57% "• Date of A.A = 13.1.17 Culverts UC Shadan Lund DG Khan Khan Construction of Nali / Drainage Tuff Tile Dera Ghazi 1590 3193 40.000 14.264 8.333 8.333 6.250 6.125 98% 20.389 51% "• Date of A.A = 13.1.17 Choti City and Colonies DG Khan Khan Water Supply Scheme City Choti Zereen Dera Ghazi 1591 3194 50.000 14.999 11.667 11.667 8.750 8.663 99% 23.662 47% "• Date of A.A = 25.7.2017 District DG Khan Khan Rehabilitation and Augmentation of Water Dera Ghazi 1592 3195 30.000 4.999 3.333 3.333 2.500 2.450 98% 7.449 25% "• Date of A.A = 25.7.2017 Supply Scheme of Choti Zareen Khan Rural Water Supply Scheme Nutkani Dera Ghazi 1593 3196 80.000 29.999 10.000 10.000 7.500 7.350 98% 37.349 47% "• Date of A.A = 16.09.2017 District DG Khan Khan Construction of PCC Drainage / Tuff Tile in Dera Ghazi 1594 3197 155.000 26.295 33.333 33.333 25.000 24.750 99% 51.045 33% "• Date of A.A = 16.09.2017 NA-171 DG Khan Khan Rehabilitation of Water Supply in Block Dera Ghazi 1595 3198 20.000 9.964 3.333 3.333 2.500 2.450 98% 12.414 62% "• Date of A.A = 25.7.2017 Churatta District DG Khan Khan Rehabilitation of Water Supply in Union Dera Ghazi 1596 3199 20.000 9.999 3.333 3.333 2.500 2.450 98% 12.449 62% "• Date of A.A = 25.7.2017 Gaddai District DG Khan Khan Construction of Nali Soling Tuff Tiles & Dera Ghazi 1597 3200 3.000 2.354 0.167 0.167 0.125 0.124 99% 2.478 83% "• Date of A.A = 25.7.2017 Culverts UC Shero Satai DG Khan Khan Construction of Nali Soling Culverts Dera Ghazi 1598 3201 3.000 2.438 0.167 0.167 0.125 0.123 98% 2.561 85% "• Date of A.A = 25.7.2017 Jhok,Uttra DG Khan Khan Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Nali Soling in Jukharr Imam Dera Ghazi 1599 3202 3.000 2.474 0.167 0.167 0.125 0.123 98% 2.597 87% "• Date of A.A = 25.7.2017 & Sherru Qasbas Khan Sewerage and Tuff Tiles in PP-244 District Dera Ghazi 1600 3203 90.000 49.000 6.667 6.667 15.000 14.850 99% 63.850 71% "• Date of A.A = 16.09.2017 DG Khan Khan Rehabilitation of Rural Water Supply 1601 3204 Scheme in Thul Sirak & Thul Jaman Tehsil Rajanpur 15.000 10.000 1.667 1.667 1.250 1.250 100% 11.250 75% "• Date of A.A = 09.01.2018 Jampur, District Rajanpur. Provision of Sewerage & Tuff Tile Kot Tahir 1602 3205 Rajanpur 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% "• Date of A.A = 04.08.2017. City District Rajanpur Installation of 1000 Nos. Deep Hand Pumps 1603 3206 Rajanpur 35.000 12.000 7.667 7.667 5.750 5.750 100% 17.750 51% "• Date of A.A = 04.08.2017. at Pachad Area, District Rajanpur. Rehabilitation of water supply in scheme 1604 3207 Rajanpur 16.000 8.000 2.667 2.667 2.000 2.000 100% 10.000 63% "• Date of A.A = 04.08.2017. Basti Tuski in District Rajan Pur Water supply scheme in Veeni Khosa to 1605 3208 Hajoo Via Basti Riaz hambae UC-Wah Rajanpur 13.000 5.993 2.333 2.333 1.750 1.750 100% 7.743 60% "• Date of A.A = 04.08.2017. Lashari in District Rajanpur

1606 3209 Deep Hand Pump in Pachad Area 200No Rajanpur 50.000 16.000 11.333 11.333 8.500 8.500 100% 24.500 49% "• Date of A.A = 04.08.2017. Rural drainage / sewerage, PCC & Tuff Tile 1607 3210 Flooring Rajanpur City of left over area Rajanpur 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% "• Date of A.A = 04.08.2017. District Rajanpur Construction of Tuff Tile, Soling, Sewerage, 1608 3211 Rajanpur 25.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 55% "• Date of A.A = 04.08.2017. Drainage and Street etc Rajan Pur City Construction of Street, Soling, Sewerage, 1609 3212 Drainage, Tuff tiles in District Rajan Pur Rajanpur 25.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 55% "• Date of A.A = 04.08.2017. City Provision of Sewerage & Tuff Tile at Basti 1610 3213 Cheena, Basti Talai Wala U/C Kot Janu. Rajanpur 30.000 10.000 6.667 6.667 5.000 5.000 100% 15.000 50% "• Date of A.A = 04.08.2017. Disrict Rajan Pur Provision of Sewerage & Tuff Tile Noshera 1611 3214 Rajanpur 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% "• Date of A.A = 04.08.2017. Gharbi. Disrict Rajan Pur Provision of Sewerage and Tuff Tile Kotla 1612 3215 Rajanpur 30.000 9.990 6.667 6.667 5.000 5.000 100% 14.990 50% "• Date of A.A = 04.08.2017. Mughlan. Disrict Rajan Pur Construction of Soling and Drain UC Jhugi 1613 3216 Muzaffargarh 20.000 10.000 3.333 3.333 2.500 2.490 100% 12.490 62% Work is in progress Wala District Muzaffargarh Construction of Soling, Tuff Tiles & Drain 1614 3217 Muzaffargarh 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% Work is in progress UC Seetpur District Muzaffargarh Provision of Soling Tuff Tiles & Drains in 1615 3218 Union Council Alludewall, District Muzaffargarh 20.000 10.000 3.333 3.333 2.500 2.498 100% 12.498 62% Work is in progress Muzaffargarh (Revised) Construction of Soling Tuff Tiles & Drains in 1616 3219 Union Council Meeran Pur, District Muzaffargarh 20.000 10.000 3.333 3.333 2.500 2.491 100% 12.491 62% Work is in progress Muzaffargarh (Revised) Construction of Soling Tuff Tiles & Drains in 1617 3220 Union Council Usman Koria, District Muzaffargarh 20.000 10.000 3.333 3.333 2.500 2.495 100% 12.495 62% Work is in progress Muzaffargarh (Revised) Construction of PCC/ Drainage and Tuff 1618 3221 Muzaffargarh 90.000 25.000 6.667 6.667 5.000 4.990 100% 29.990 33% Work is in progress Tiles District Muzaffargarh Provision of Tuff Tile, Sewerage and Drainage in Urban Area Municipal 1619 3222 Muzaffargarh 40.000 10.000 30.000 30.000 17.960 17.948 100% 27.948 70% Work is in progress Committee Chowk Sarwar Shaheed District Muzaffargarh Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of Soling and Driange work in 1620 3223 UC-Dammar Wala and Kotla Gmaoon, Muzaffargarh 25.000 10.000 5.000 5.000 3.750 3.735 100% 13.735 55% "• Date of AA 31.7.2017 District Muzaffargarh Construction of Soling and Driange work in 1621 3224 Calor Wali Qadir Pur and Damar Wali, Muzaffargarh 25.000 10.000 5.000 5.000 3.750 3.725 99% 13.725 55% Work is in progress District Muzaffargarh Construction of Soling and Driange work in 1622 3225 Janda Wali Aluda Wali and Mahal Khakhi, Muzaffargarh 15.000 7.000 2.667 2.667 2.000 2.000 100% 9.000 60% Work is in progress District Muzaffargarh Const: of Soling Drain Tuff Tile VR Bridges 1623 3226 Muzaffargarh 30.000 10.000 6.667 6.667 5.000 5.000 100% 15.000 50% Work is in progress UC Kotla Gamon District Muzaffargarh

Const: of Soling Drain Tuff Tile VR Bridges 1624 3227 Muzaffargarh 30.000 10.000 6.667 6.667 5.000 4.990 100% 14.990 50% Work is in progress UC Kotla Lal Shah District Muzaffargarh

Const: of Soling Drain Tuff Tile VR Bridges 1625 3228 Muzaffargarh 30.000 13.250 3.333 3.333 2.500 2.500 100% 15.750 53% Work is in progress UC Shehr Sultan District Muzaffargarh Const: of Soling Drain Tuff Tile VR Bridges 1626 3229 Muzaffargarh 30.000 10.000 6.667 6.667 5.000 4.990 100% 14.990 50% Work is in progress UC Vains District Muzaffargarh Const: of Soling Drain Tuff Tile VR Bridges 1627 3230 Muzaffargarh 30.000 10.000 6.667 6.667 5.000 4.990 100% 14.990 50% Work is in progress UC Jhalarin District Muzaffargarh

Const: of Soling Drain Tuff Tile VR Bridges 1628 3231 Muzaffargarh 30.000 10.000 6.667 6.667 5.000 4.990 100% 14.990 50% Work is in progress UC Bair Bund District Muzaffargarh

Const: of Soling Drain Tuff Tile VR Bridges 1629 3232 Muzaffargarh 30.000 10.000 6.667 6.667 5.000 4.980 100% 14.980 50% Work is in progress UC Binda Ishaq District Muzaffargarh Drainange / Soling / Tuff Tile / Culverts Gul 1630 3233 Wala, Khanpur Fazil Kalroo District Muzaffargarh 30.000 10.000 6.667 6.667 5.000 5.000 100% 15.000 50% Work is in progress Muzaffargarh Construction of Soling and Driange work in 1631 3234 UC-Vains and Basti Arif Wala, District Muzaffargarh 15.000 5.000 3.333 3.333 2.500 2.500 100% 7.500 50% Work is in progress Muzaffargarh Construction of Soling and Driange work in 1632 3235 Jatoi, Rampur, Nichrani, Baber, Azam Khan Muzaffargarh 15.000 7.000 2.667 2.667 2.000 2.000 100% 9.000 60% Work is in progress and Kasir Gazlani, District Muzaffargarh Construction of Soling and Driange work in 1633 3236 Rohilan Wali, Binday Wali and Khakhi, Muzaffargarh 15.000 7.000 2.667 2.667 2.000 1.990 100% 8.990 60% Work is in progress District Muzaffargarh Construction of Soling and Driange work in 1634 3237 Miyan Sawar Mochi Wala Ganga and Muzaffargarh 15.000 7.000 2.667 2.667 2.000 1.990 100% 8.990 60% Work is in progress Khakhi, District Muzaffargarh Construction of Soling and Driange work in 1635 3238 Baily Wala and Bait Umar Draz and Bindi Muzaffargarh 15.000 7.000 2.667 2.667 2.000 1.990 100% 8.990 60% Wokr is in progress Pitafi, District Muzaffargarh Cosntruction of Soling / Drainage and 1636 3239 Culverts Tuff Tiles Municipal Committee Muzaffargarh 20.000 9.000 3.333 3.333 2.500 2.500 100% 11.500 58% Work is in progress Daira Deen Panah District Muzaffargarh Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Drainage / Soling / UC Thath Gurmani, U/C Gurmani Sharqi, U/C Sheikh Umar, U/C 1637 3240 Muzaffargarh 100.000 33.500 6.667 6.667 5.000 5.000 100% 38.500 39% Work is in progress Daya Jokha Sharqi, U/C Gujrat U/C Allud District Muzaffargarh Muzaffargarh City Sewerage Scheme 1638 3241 Soling / Drainage, Tuff Tiles District Muzaffargarh 50.000 20.000 3.333 3.333 2.500 1.667 67% 21.667 43% Work is in progress Muzaffargarh Construction of Soling / Drainage Tuff Tiles 1639 3242 Union Council Taleri Doaba District Muzaffargarh 30.000 10.000 3.333 3.333 2.500 1.667 67% 11.667 39% Work is in progress Muzaffargarh Construction of Soling / Drainage Tuff Tiles 1640 3243 Union Council Bhutta Pur District Muzaffargarh 30.000 10.000 3.333 3.333 2.500 1.640 66% 11.640 39% Work is in progress Muzaffargarh Drainage / Soling / Tuff Tiles / Culverts K.D Qurehi, Gulqaim Mastoi, Budh, Wanpitafi, 1641 3244 Muzaffargarh 50.000 20.000 3.333 3.333 2.500 2.497 100% 22.497 45% Work is in progress Sharif Chujra, Ali Dah, Dawna, Mehmood Kot District Muzaffargarh

Construction of Soling / Drainage Tuff Tile Culverts sullage Carrier Pull Pullet PPC Allied Work etc Qureshi Aabwala Rahim Ali 1642 3245 Muzaffargarh 60.000 20.000 3.333 3.333 2.500 2.488 100% 22.488 37% Work is in progress Mulan Walidad Mazhay wala Tibbi Godar Chowk Sanwai Syed Hassan Shah Bakhsh Wala Jada Chandai District Muzaffargarh Const: of Soling/ Sewerage Drain UC Jhanday Wali UC Manikpur UC Darien UC 1643 3246 Muzaffargarh 30.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 42% Work is in progress Shahjamal UC Alludeywali District Muzaffargarh Construction of PCC/Drainage and Tuff Tile 1644 3247 Muzaffargarh 65.000 25.000 6.667 6.667 5.000 5.000 100% 30.000 46% Work is in progress in NA179 and PP-258 District Muzaffargarh Construction of Tuff Tile Drainge Sewerage 1645 3248 Soling PCC Slab and different work PP-262 Layyah 100.000 35.000 6.667 6.667 5.000 5.000 100% 40.000 40% • Date of AA = 15.08.2017 District Layyah Construction of Tuff Tile Drainage 1646 3249 Sewerage Soling PCC Slab and different Layyah 120.000 30.000 10.000 10.000 7.500 7.500 100% 37.500 31% • Date of AA = 15.08.2017 work PP-263 District Layyah Construction of Tuff Tile Drainage 1647 3250 Sewerage Soling PCC Slab and different Layyah 100.000 30.000 16.667 16.667 12.500 12.500 100% 42.500 43% • Date of AA = 15.08.2017 work PP-264 District Layyah Comprehensive sewerage / Drainage 1648 3251 scheme along with tuff Tile in Choubara city Layyah 100.000 30.000 23.333 23.333 17.500 17.500 100% 47.500 48% • Date of AA = 15.08.2017 District Layyah.

1649 3252 Swerage Drainge / Tuff Tiles for Layyah city Layyah 300.000 75.000 50.000 50.000 37.500 37.500 100% 112.500 38% • Date of AA = 06.09.2017 Construction of Sewerage/Drains and Administrative Approval issued on dated. 08- 1650 3253 Laying of Tuff Tiles/Soling in UC, Sirishta Layyah 143.137 10.000 21.297 21.297 15.973 15.964 100% 25.964 18% 01-2018. Thal District Layyah Rural Sewerage/ Drainage / Brick Pavement / Tuff Tiles in Union Council 164- 1651 3254 Layyah 20.000 10.000 3.333 3.333 2.500 2.500 100% 12.500 63% • Date of AA = 29.07.2017 A / TDA and Adjoining Abadies Tehsil District Layyah Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of tender; 12-10-2017. Date of award:-26-10-2017. Date of completion. 25- 10-2018. Anticipated date of completion 31- Const. of Road, Sewerage & tuff Tile Chak 1652 3255 Bahawalpur 11.889 5.990 1.963 1.963 1.472 1.472 100% 7.462 63% 12-2019 Date of receipt of funds by F.D. No.5/BC District Bahawalpur 20.07.2018 & 11.01.2019. Full funds have been utilized upto 12-03-2019. Work has been stopped by the contractor due to non availability of funds. Lattitude/Longitude. 29.40036,71.82009

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 12-10-2017. Rehabilitation of water supply schemes in Date of award:-31-10-2017. Date of completion. 30.07.2018. Anticipated date of 1653 3256 Chak no.5/DNB Tehsil Yazman District Bahawalpur 20.488 9.994 3.496 3.496 2.622 2.590 99% 12.584 61% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. . Work is in progress. Lattitude/Longitude. 29.105988333333336,71.50697

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 23-10-2017. Rehabilitation of water supply schemes in Date of award:-31-10-2017. Date of completion. 30.07.2018. Anticipated date of 1654 3257 Chak no.14/DNB Tehsil Yazman District Bahawalpur 20.802 14.939 1.934 1.934 1.451 1.450 100% 16.389 79% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.107975000000003,71.54872999999999

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 23-10-2017. Rehabilitation of water supply schemes in Date of award:-31-10-2017. Date of completion. 30.07.2018. Anticipated date of 1655 3258 Chak no.76/DNB Tehsil Yazman District Bahawalpur 17.490 8.396 2.497 2.497 1.873 1.838 98% 10.234 59% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. . Work is in progress.. Lattitude/Longitude. 29.035675,71.30850166666667

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 23-10-2017. Date of award:-31-10-2017. Date of Rehabilitation of water supply schemes in completion. 30.07.2018. Anticipated date of completion 31-12-2019 Date of receipt of 1656 3259 Chak no.24/DNB Tehsil Yazman District Bahawalpur 21.552 9.997 3.851 3.851 2.888 2.827 98% 12.824 60% funds by F.D. 20.07.2018 & 11.01.2019. Bahawalpur Work is in progress. Lattitude/Longitude. 29.063098333333333,71.38126166666666 T/W No. 01 29.063766666666666,71.38213999999999

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 23-10-2017. Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of completion 31-12-2019 Date of receipt of Rehabilitation of water supply schemes in funds by F.D. 20.07.2018 & 11.01.2019. 1657 3260 Chak No.44/DB Tehsil Yazman, District Bahawalpur 46.980 25.000 3.333 3.333 2.600 2.550 98% 27.550 59% Funds Rs.0.100 million provided through re- Bahawalpur. appropriation by C.E(S), PHED Lahore dated 17-04-2019.Work in progress. Lattitude/Longitude. 29.219614999999997,71.87149166666667 T/W No. 01 29.217738333333333,71.871525 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 23-10-2017. Rehabilitation of water supply schemes in Date of award:-31-10-2017. Date of completion. 30.07.2018. Anticipated date of 1658 3261 Chak No.143/DB Tehsil Yazman, District Bahawalpur 22.680 14.996 2.560 2.560 1.920 1.920 100% 16.916 75% completion 31-12-2019 Date of receipt of Bahawalpur. funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.102473333333332,71.61088166666667

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of tender; 23-10-2017. Date of award:-31-10-2017. Date of completion. 30- Water Supply Scheme in Chak No.115/DB 1659 3262 Bahawalpur 20.000 9.928 3.333 3.333 2.500 2.500 100% 12.428 62% 07-2018. Anticipated date of completion 31- Kachi Tehsil Yazman District Bahawalpur. 12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.102950000000003,71.612615

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 23-10-2017. Date of award:-31-10-2017. Date of completion. 30.07.2018. Anticipated date of 1660 3263 Water Supply scheme of Chak No.114/DNB Bahawalpur 18.000 8.698 2.667 2.667 2.000 1.956 98% 10.654 59% completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.103966666666665,71.49491666666667

Date of AA = 27-07-2017. Date of T.S 29.09.2017. Date of receipt of tender: 12-10- 2017. Date of award: 31.10.2017. Date of Const. of Road, Sewerage & Tuff Tile Basti 1661 3264 Bahawalpur 15.000 5.954 3.000 3.000 2.250 2.216 98% 8.170 54% completion: 30.07.2018 Anticipated date of Hansarah District Bahawalpur completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.382105000000003,71.67586

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. P/L of Sewerage and Tuff Tile Basti Inayati Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of 1662 3265 Tehsil Khairpur Tamewali District Bahawalpur 29.000 14.991 4.667 4.667 3.500 3.450 99% 18.441 64% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.7016969230026,72.33235208317637

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 12-10-2017. P/L of Sewerage and Tuff Tile Basti Bohran Date of award:-31-10-2017. Date of completion. 30.07.2018. Anticipated date of 1663 3266 Tehsil Khairpur Tamewali District Bahawalpur 15.300 4.974 3.433 3.433 2.873 2.850 99% 7.824 51% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.58046417683363,72.22700958140194

Date of AA= 08.08.2017 Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Date of award:-31-10-2017. Date of Sewerage/Drainage/Tuff Tiles/ Sullage in completion. 30.01.2019. Anticipated date of 1664 3267 189/Murad adjoining Abadies District Bahawalpur 22.000 9.999 4.000 4.000 3.000 2.976 99% 12.975 59% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. . Work is in progress.. Lattitude=29.476535455724164, Longitude=72.64597366437899 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA= 08.08.2017 Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of 1665 3268 147/Murad and adjoining Abadies District Bahawalpur 35.000 9.990 3.333 3.333 2.500 2.494 100% 12.484 36% completion 30-06-2020 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.58238823827911,72.66389583140555

Date of AA= 08.08.2017 Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of 1666 3269 179/Murad and adjoining Abadies District Bahawalpur 35.100 14.341 3.333 3.333 2.500 2.495 100% 16.836 48% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. . Work is in progress. Lattitude/Longitude. 29.542312600115025,72.7619708207658

Date of AA= 08.08.2017 Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Sewerage/Drainage/Tuff Tiles/ Sullage in Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of 1667 3270 160/Murad Adjoining Abadies, District Bahawalpur 35.100 14.999 3.333 3.333 2.500 2.496 100% 17.495 50% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.51783779140611,72.63583342260145

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Date of award:-31-10-2017. Date of Const. of Sewarage & Tuff Tile Basti Kori 1668 3271 Bahawalpur 20.000 9.989 3.333 3.333 2.500 2.400 96% 12.389 62% completion. 30.07.2018. Anticipated date of Wala, Hoot Wala District Bahawalpur completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.35623666666667,71.68510333333333

Date of AA= 27-07-2017. Date of T.S= 31.07-2017 Date of tender; 12-10-2017. Rehabilitation of Sewerage Date of award:-26-10-2017. Date of completion. 25-09-2018. Anticipated date of 1669 3272 Scheme/Drainage and Tuff Tiles City Noor Bahawalpur 12.086 8.999 1.029 1.029 0.772 0.772 100% 9.771 81% completion 31-12-2019 Date of receipt of Pur Noranga District Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.222853333333333,71.43270333333334

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. P/L Sewerage /Tuff Tile City Hathaiji Mouza Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of 1670 3273 Hathaiji Tehsil Ahmadpur East District Bahawalpur 50.000 19.998 10.000 10.000 7.500 7.481 100% 27.479 55% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.3343687,71.2397529 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of AA= 27-07-2017. Date of T.S=09-08- 2017 Date of receipt of tender: 16-10-2017. Date of award:-31-10-2017. Date of P/L Sewerage /Tuff Tile Mubrakpur City 1671 3274 Bahawalpur 40.000 6.903 3.333 3.333 2.500 2.498 100% 9.401 24% completion. 30.01.2019. Anticipated date of Tehsil Ahmadpur East District Bahawalpur completion 30-06-2020 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.254193,71.3697326

Date of A.A (DDSC). 28-09-2017. Date of T.S. 17-10-2017. Prequalification completed on 06-11-2017. Date of receipt of tender from Prequalified contractors on 05-12- 2017 .Date of award. 26-12-2017 Date of Rehabilitation of Sewerage, City Yazman completion. 25-12-2020. Date of receipt of 1672 3275 Bahawalpur 300.000 59.999 33.333 33.333 25.000 25.000 100% 84.999 28% funds by F.D. 20.07.2018 & 11.01.2019. District Bahawalpur Work is in progress. Design of cradle required to be changed due to fluctuation in water table as the change of site of disposal. Revised administrative approval is required. Lattitude/Longitude. 29.110216666666663,71.74209333333333

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Date of award:-31-10-2017. Date of Sewerage Scheme Chak No.86/DB District 1673 3276 Bahawalpur 19.359 8.000 3.786 3.786 2.840 2.819 99% 10.819 56% completion. 30.07.2018. Anticipated date of Bahawalpur completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. . Work is in progress.. Lattitude/Longitude. 29.117099999999997,71.82421

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 16-10-2017. Date of award:-31-10-2017. Date of Sewerage Scheme Chak No.53/DB District 1674 3277 Bahawalpur 20.588 8.999 3.863 3.863 2.897 2.850 98% 11.849 58% completion. 30.07.2018. Anticipated date of Bahawalpur completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.16089833333333,71.74869833333334

Date of AA= 27-07-2017. Date of T.S=08-08- 2017 Date of receipt of tender: 12-10-2017. Date of award:-31-10-2017. Date of Sewerage Scheme Chak No.68/DB District 1675 3278 Bahawalpur 16.397 4.998 3.799 3.799 2.849 2.800 98% 7.798 48% completion. 30.07.2018. Anticipated date of Bahawalpur completion 31-12-2019 Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.206916666666665,71.91308000000001

Date of AA= 27-07-2017. Date of T.S=09-08- 2017 Date of receipt of tender: 16-10-2017. Provision of Tuff Tile & Sanitation Scheme Date of award:-31-10-2017. Date of completion. 30.01.2019. Anticipated date of 1676 3279 in Hatiji Tehsil Ahmadpur East Ditrict Bahawalpur 40.000 14.995 3.333 3.333 2.500 2.500 100% 17.495 44% completion 31-12-2019 Date of receipt of Bahawalpur funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Lattitude/Longitude. 29.3275377,71.2855532 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- Provision of Water supply Chak No. 202- Bahawalnaga 2017.Date of work award. 22-09-2017Date 1677 3280 206/M, 128-132/M, 133-134/M, 176/M, 50.000 14.992 6.667 6.667 5.000 5.000 100% 19.992 40% of completion. 31-12-2018.Anticipation date r 60/4/R District Bahawalnagar of completion 30-06-2020Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress

Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- Provision and laying of water supply Bahawalnaga 2017.Date of work award. 22-09-2017Date 1678 3281 schemes Chak No.53/F alongwith allied 25.000 10.000 5.000 5.000 3.750 3.750 100% 13.750 55% of completion. 31-12-2018.Anticipation date r basties District Bahawalnagar of compltion.30-06-2020Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- Rehabilitation of water supply schemes Bahawalnaga 2017.Date of work award. 22-09-2017Date 1679 3282 Chak No.45/F Jattan wali District 15.000 9.984 1.667 1.667 1.250 1.250 100% 11.234 75% of completion. 30-09-2018.Anticipation date r Bahawalnagar of completion 30-06-2020Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017.Date of T.S. Rehabilitation of Rural Water Supply 08-08-2017Date of receipt of tender. 11-09- Scheme Chak No. 82/5-R &138-139/6-R Bahawalnaga 2017.Date of work award. 22-09-2017Date 1680 3283 40.000 14.997 8.333 8.333 6.250 6.200 99% 21.197 53% of completion. 31-12-2018.Anticipated date Including All Adjoining Abadies Tehsil r of completion 30-06-2020Date of receipt of Haroonabad District Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A(DDC) 03-08-2017.Date of T.S. Rehabilitation of Rural Water Supply 08-08-2017Date of receipt of tender. 11-09- Scheme Chak No. 53/4-R & 137/6-R Bahawalnaga 2017.Date of work award. 22-09-2017Date 1681 3284 44.000 15.652 9.447 9.447 7.085 7.000 99% 22.652 51% of completion. 31-12-2018.Anticipated date Including All Adjoining Abadies Tehsil r of completion 30-06-2020.Date of receipt of Haroonabad District Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress

Rural Water Supply Scheme/ Sewerage/ Date of A.A 09-08-2017. Date of T.S. Drainage scheme Sri Ram Pura, Khair 12.10.2017. prequalification of the contractors. 31.10.2017. Date of receipt of Shah, Bhaluka, Puna, Habibka, Allah Buksh Bahawalnaga Tender from prequalified contractors on 16- 1682 3285 Lalika, Bunga Machi Murad Wala, Musa 80.000 34.980 8.333 43.333 6.250 6.250 100% 41.230 52% 11-2017 .Date of award. 30-12-2017.Date r Bhota Jhulan Arrain, Sanateka, Jurana of completion. 29-12-2018.Anticipated date of completion 30-06-2020. Date of receipt of Basti, Kup Quraishian, Chak Jodheka, funds by F.D. 20.07.2018 & 11.01.2019. Bhaluka, Chakmadrass, Distr Work is in progress.

Date of A.A 09-08-2017. Date of T.S. Construction of Soling / Water Supply in 12.10.2017. prequalification of the contractors completed on 31.10.2017. Date Union Councils Islam Pura, Fateh Kot, of receipt of tender. 16-11-2017 .Date of Malik Pura, Sawae Wala, Muhammad Pur, Bahawalnaga 1683 3286 100.000 29.963 10.000 10.000 10.000 9.900 99% 39.863 40% work awarded. 11-12-2017.Date of Koryanwala, Denan, Sondha, Gulaab Ali, r completion. 10-12-2018.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Barah Sajwad Khan, Teko Raam, Donga Funds Rs.2.500 million provided through re- Bonga District Bahawalnagar appropriation dated 26-03-2019. Work is in progress. Date of A.A 03-08-2017. Date of T.S 08-08- 2017. Date of receipt of tender 11-09- 2017.Date of work awarded Rural Water supply scheme of Khiraaj Pura Bahawalnaga 1684 3287 15.000 6.996 2.667 2.667 2.000 2.000 100% 8.996 60% 31.10.2017.Date of completion and Goband Pur District Bahawalnagar r 30.10.2018.Anticipated date of completion 30-06-2020.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A 03-08-2017. Date of T.S 08-08- 2017. Date of receipt of tender received Rural Water supply scheme of Maakhe Bahawalnaga 27.11.2017.Date of work awarded. 30-11- 1685 3288 wali, Mohan Pura, Jeeto, Jhugyan District 15.000 6.960 2.667 2.667 2.000 2.000 100% 8.960 60% 2017Date of completion 29-12-2018 r Bahawalnagar Anticipated date of completion 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A 03-08-2017. Date of T.S 08-08- 2017. Date of receipt of tender 11-09- 2017.Date of work awarded Rural water supply scheme of Taalya and Bahawalnaga 1686 3289 15.000 6.886 2.667 2.667 2.000 2.000 100% 8.886 59% 31.10.2017.Date of completion Dhaban District Bahawalnagar r 30.10.2018.Anticipated date of completion 30-06-2020.Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(DDC) 03-08-2017.Date of T.S. Rehabilitation of Rural Water Supply 08-08-2017Date of receipt of tender. 11-09- Scheme Chak No. 143/6-R including all Bahawalnaga 2017.Date of work award. 22-09-2017Date 1687 3290 28.807 9.944 6.269 6.269 4.702 4.700 100% 14.644 51% of completion. 31-12-2018.Anticipated date Adjoining Abadies Tehsil Haroonabad r of completion 30-06-2020. Date of receipt of District Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress

Date of A.A 03-08-2017.Date of T.S. 08.08.2017. .Date of receipt of tender 11-11- Rural Water Supply Scheme Chak No. Bahawalnaga 2017.Date of work award. 16-11- 1688 3291 196/HB Tehsil Fortabbas District 25.000 9.999 5.000 5.000 3.750 3.750 100% 13.749 55% 2017.Anticipated date of completion 30-06- r Bahawalnagar 2020. Date of completion 15-11-2018Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress

Date of A.A(DDC) 03-08-2017.Date of T.S. Rehabilitation of Rural Water Supply 08-08-2017Date of receipt of tender. 11-09- Scheme Chak No. 70/4-R & 84/5-R Bahawalnaga 2017.Date of work award. 22-09-2017Date 1689 3292 50.000 19.949 10.000 10.000 7.500 7.500 100% 27.449 55% of completion. 31-12-2018.Anticipated date Including All Adjoining Abadies Tehsil r of completion 30-06-2020. Date of receipt of Haroonabad District Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress

Date of A.A(DDC) 03-08-2017.Date of T.S. Rural Water Supply Scheme Chak No. 08-08-2017Date of receipt of tender. 11-09- 237,238,239/9R & 239/HB Including All Bahawalnaga 2017.Date of work award. 02-10-2017Date 1690 3293 40.000 14.999 8.333 8.333 6.250 6.250 100% 21.249 53% of completion. 31-12-2018.Anticipated date Adjoining Abadies Tehsil Fortabbas. District r of completion 30-06-2020. Date of receipt of Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A 03-08-2017. Date of T.S 08-08- 2017.Date of tender receipt 11-09- Construction of Sewer Lines and Tuff Tiles 2017.Date of award 31.10.2017Date of Bahawalnaga 1691 3294 in City Area Haroonabad Tehsil 18.000 9.990 2.667 2.667 1.400 1.400 100% 11.390 63% completion 31.10.2018.Date of receipt of r funds by F.D. 20.07.2018 & 11.01.2019. Haroonabad District Bahawalnagar Work is in progress. Rs.0.600 million surrendered due to site dispute on dated 19.10.2018. Date of A.A. 09-08-2017.Date of T.S. Construction of Tuff Paverment urban area 04.10.2017. Tender received on 10-01- Bahawalnaga 1692 3295 City Chistian Ward No.1 to 36 District 100.000 29.999 16.667 16.667 12.500 12.500 100% 42.499 42% 2018Date of award: 23.01.2018.Date of r completion 30.06.2019Date of receipt of Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- Provision of Soling, Drainage system, Bahawalnaga 2017.Date of work award. 02-10-2017Date 1693 3296 Erection of Tuff Tiles in Mandi Sadiq Gunj 44.000 16.998 3.333 3.333 2.500 2.500 100% 19.498 44% of completion. 31-12-2018.Anticipated date r city. District Bahawalnagar of completion 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- 2017.Date of work award. 28-10-2017Date Provision of Soling, Drainage System, Bahawalnaga of completion. 31-12-2018.Anticipated date 1694 3297 Erection of Tuff Tiles in Macloed Gunj city. 50.000 19.985 3.333 3.333 6.550 6.550 100% 26.535 53% of completion 30-06-2020. Date of receipt of r District Bahawalnagart funds by F.D. 20.07.2018 & 11.01.2019. Funds Rs.4.05 million provided through re- appropriation dated 26-03-2019 & 16-04- 2019. Work is in progress.

Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- Provision of Soling, Drainage System Bahawalnaga 2017.Date of work award. 28-10-2017Date 1695 3298 Erection of Tuff Tiles in Madhaniwal District 21.000 9.996 3.667 3.667 2.750 2.750 100% 12.746 61% of completion. 31-12-2018.Anticipated date r Bahawalnagar of completion 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A 03-08-2017. Date of T.S 08-08- 2017. Date of Tender receipt 11-09- Provision of Soling, Drainage System, 2017.Date of award 31.10.2017.Date of Bahawalnaga 1696 3299 Erection of Tuff Tiles in Hasil Sarrhu. 45.000 21.853 3.333 3.333 8.424 8.422 100% 30.275 67% completion 30.01.2019.Date of receipt of r funds by F.D. 20.07.2018 & 11.01.2019. District Bahawalnagar Work is in progress. Rs.5.924 million provided through re-appropriation dated 19.10.2018. Date of A.A 03-08-2017. Date of T.S 05.08.2017. Date of tender receipt 11-09- Provision of Soling, Tuff Tile, Drainage in Bahawalnaga 2017.Date of award 31.10.2017Date of 1697 3300 Mouza Muharram Cheena. District 12.000 9.998 0.667 0.667 0.500 0.500 100% 10.498 87% completion 30.10.2018.Anticipated date of r Bahawalnagar completion 30-06-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress Date of A.A(DDC) 03-08-2017.Date of T.S. 08-08-2017Date of receipt of tender. 11-09- Provision of Soling, Tuff Tile, Drainage in Bahawalnaga 2017.Date of work award. 02-10-2017Date 1698 3301 21.000 9.999 3.667 3.667 2.750 2.750 100% 12.749 61% of completion. 31-12-2018.Anticipated date Mouza Hassanwala. District Bahawalnagar r of completion 30-06-2020. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress.

Date of A.A 09-08-2017. Date of T.S. Sewerage / drainage scheme Sri Ram 12.10.2017. prequalification of the Pura, Khair Shah, Bhaluka, Puna, Habibka, contractors. 31.10.2017. Date of receipt of Allah buksh Lalika, Bunga Machi Murad Bahawalnaga Tender from prequalified contractors on 16- 1699 3302 150.000 43.484 6.667 6.667 5.000 5.000 100% 48.484 32% 11-2017 Date of award. 30-12-2017Date of wala, Musa Bhota Jhulan Arrain, Sanateka, r completion 29-03-2019.Anticipated date of Jattu wal Deen Pure, Chak Hotyana and completion 30-06-2021Date of receipt of Jurana Hafizabad District Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Date of A.A 09-08-2017. Date of T.S 06-11- Providing and laying sewerage schemes 2017Date of receipt of tender: 10-01- Bahawalnaga 1700 3303 Chak No.98/F, Bakhshan Khan, Chak 54/F, 100.000 29.859 10.000 10.000 7.500 7.500 100% 37.359 37% 2018Date of award: 23.01.2018Date of r completion 30.06.2019Date of receipt of 105/F, 10/FW, 174/M District Bahawalnagar funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

The scheme Provision of Soiling, Tuff Tile, Drainage in Mouza Muharram Cheena District Bahawalnagar reflected in ADP- 2017-18 was substituted by Standing Committee of the Cabinet on Finance & Development in its meeting held on 20-09- Provision of Soling, Drainage System 2017 as proposed by Mian Fida Hussain Watto EX-MPA PP-277 and minutes of Eraction of Tutt Tiles in Bahawalnaga meeting issued vide S&GAD No.SO(CAB- 1701 3304 BhainiSikandarJassoka and 3.000 2.500 0.167 0.167 0.209 0.125 60% 2.625 88% II)1-2/2017(Fin-170) dated 06-10-2017. r MouzaShamonJassoka Tehsil Scheme approved on 02-11-2017 by DDC. Work awarded on 29-12-2017 but work not Minchanabad District Bahawalnagar started due to non availability of funds during 2017-2018. Now funds have been released by FD on 12-11-2018 & 11.01.2019. Date of completion dated 28-03- 2018. Anticipated dated of competition 30- 06-2020 Amended A.A is issued from DC, office on 11-12-2018. Work in progress.

Scheme approved on 02-11-2017 by DDC. Provision of Soling Drainage System Tender received on 27-11-2017 .Date of receipt of funds by FD.05-03-2018. Date of Erection of Tuff Tile in Moti Pur, Qadir Pur, award. 29-12-2017. Date of completion 26- Munshi Other, Basti Shah Bharamka, Bahawalnaga 1702 3305 15.000 9.999 1.667 1.667 0.900 0.899 100% 10.898 73% 06-2018. Anticipated date of completion. 30- Manzoor Kot, Chak Saroo, Chak Saroo, r 06.2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Scheme Chak Tehsil Minchanabad District completed in saving. Excess funds Bahawalnagar Rs.0.350 million surrendered dated 19.10.2018

Date of A.A(DDC) 03-08-2017. Date of T.S. 08-08-2017. Date of receipt of tender.12-09- 2017.Date of work award. 22-09-2017.Date Construction of Sewer Lines and Tuff Tiles of completion. 21-12-2018.Anticipated date Bahawalnaga 1703 3306 in Faqir Wali Tehsil Haroonabad District 40.000 14.367 3.333 3.333 5.000 5.000 100% 19.367 48% of completion 30-06-2020. Date of receipt of r funds by F.D. 20.07.2018 & 11.01.2019. Bahawalnagar Funds Rs.2.500 million Provided through re- appropriation vide Chief Engineer(S),PHED Lahore No.72-78/B(4) dated 10.01.2019.Work is in progress.

Date of A.A. 05.08.2017. Date of T.S. 09.08.2017. Date of receipt of Tender: 07.09.2017. Date of award: 31.10.2017. Constuction PCC Draiinge / Soling in NA- Rahim Yar Date of completion: 30-04-2019. Anticipated 1704 3307 40.013 12.987 3.333 3.333 2.500 2.398 96% 15.385 38% date of completion 30-06-2019. Date of 193 District Rahim Yar Khan Khan receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.40483166666667 / 70.31396166666667

"Date of A.A. 05.08.2017. Date of T.S. 09.08.2017. Date of receipt of Tender: 07.09.2017. Date of award: 31.10.2017. Construction of laying Sewerage, Water Rahim Yar Date of completion: 30.10.2019. Anticipated 1705 3308 Supply & Tuff Tiles City Sadiqabad District 30.000 26.419 1.192 1.192 0.894 0.894 100% 27.313 91% date of completion 30-06-2020. Date of Khan Rahim Yar Khan receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.278135 / 70.12561333333333

Date of A.A. 09-08-2017. Date of T.S 26-10- 2017. Date of receipt of Tenders from prequalified contractors 27-12-2017. Date Mega Sewerage Scheme Roads & Tuff Tile Rahim Yar 1706 3309 100.000 14.996 16.667 36.667 12.500 12.447 100% 27.443 27% of award 21-02-2018. Date of completion 20- Kotsamaba Khan 10-2019. Date of receipt of funds by F.D. 20.07.2018 & 11.01.2019. Work is in progress. Latitude / longitude 28.548231666666666 / 70.463665 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age)

Date of A.A. 05.08.2017. Date of T.S. 09.08.2017. Date of receipt of Tender: Providing / Lying of Tuff Tiles Both Sides of 07.09.2017. Date of award: 31.10.2017. Road from Attock Petrolium to Chowk Din Rahim Yar Date of completion: 30.10.2018. Anticipated 1707 3310 31.500 9.999 3.333 3.333 2.500 2.486 99% 12.485 40% date of completion 30-06-2020. Date of Pur Sharif Length: 1.50 KM District Rahim Khan receipt of funds by F.D. 20.07.2018 & Yar Khan 11.01.2019. Work stopped by the contractor due to want of funds. Latitude / longitude 28.654911666666667 / 70.65899666666665

1. Date of AA = 02.08.2017 2. Date of TS = 26.08.2017 3.Date of Award of work 31.10.2017 4.Dated of Released Funds 30.10.2017 Drain Type - I= 11525-Rft.Brick Rural Drainage Scheme / PCC Slab For 1708 3311 Chiniot 29.995 7.498 3.333 3.333 2.500 2.500 100% 9.998 33% Pavement= 57358-RftP.C.C= 16595- Mouza Rao Bagh Tehsil and Distt. Chiniot RftSullage Carrier= 7017-Rft.Funds Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat,31.7383884 Long ,73.0290784 Construction of PCC / Soling / Drainage / 1. Date of AA = 02.08.2017 2. Date of TS = Street and Tuff Tiles in Mohallah Adda 28.08.2017 3.Date of Award of work 31.10.2017 4.Dated of Released Funds Road Haidry Chowk Lalian, Baldia Road Al 30.10.2017 .Drain Type - I= 1260-Rft Brick 1709 3312 Qaim Medical Store Afzal Bhatti Mehar Chiniot 14.993 10.000 1.664 1.664 1.248 1.248 100% 11.248 75% Pavement= 35964-Cft. Funds Released Sikandar Lali Chowk, Gala Mandi Paka upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in Bazar Abadi Bil Muqabil Baldiya office Aqab progress. Lat 31.8266451 Long, Abadi Police 72.8033615 1. Date of AA = 02.08.2017 2. Date of TS = Construction of PCC / Soling / Drainage / 28.08.2017 3.Date of Award of work Street and Tuff Tiles in Mohallah Afzal 31.10.2017 4.Dated of Released Funds Bhatti Doctor Bashir Road Heli Chowk 30.10.2017 12" i/d Sewer= 220-Rft 15" i/d Sewer= 2227-Rft Tuff Tile= 121717-Sft 1710 3313 Laliyan, beli Chowk Laliyan, Beli Chowk to Chiniot 23.000 8.496 4.333 4.333 3.250 3.150 97% 11.646 51% Sullage Carrier= 2000-Rft Funds Released soling/ Sheikh Muhammad Hussain Airan on 03.08.2018 by the Chief Engineer Store Jhang Road via Hujra Mor, Beli/ (South) PHED Lahore and work is in Hujra Road to progress. Lat 31.8224577. Long, 72.8118424

Construction of PCC / Soling / Drainage / 1. Date of AA = 02.08.2017 2. Date of TS = Street and Tuff Tiles in Mohallah 28.08.2017 3.Date of Award of work Ahmadabad Chowk Bazar Kocha Bandi 31.10.2017 4.Dated of Released Funds 30.10.2017 Tuff Tile= 108364-Sft Sullage 1711 3314 Ward no. 10, Chongi no. 5 to Jamia Chiniot 17.907 10.000 2.636 2.636 1.977 1.977 100% 11.977 67% Carrier= 1347-Rft Funds Released upto Mosque Chowk Bangla Road,Bangla Road 24.01.2019 by the Chief Engineer (South) to Chowk Bazar, Kot Muhammad Yar- PHED Lahore and work is in progress. Lat Nawab Chowk Aqeeb Baldiya Office Mo 31.8254211 Long, 8049794

Construction of PCC / Soling / Drainage / Street and Tuff Tiles in Mohallah Jamiya 1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Mosque Bangla Road Nawab Chowk Imtiaz 31.10.2017 Drain Type-I= 544-Rft Sullage 1712 3315 Lali Chowk, Old Eid gah Changran - Chiniot 26.900 4.938 3.333 3.333 2.500 2.300 92% 7.238 27% Carrier= 185254-Rft Funds Released upto Qadirabad Wark No 3, Ghulam Mustafabad 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat Ward no 4, Dera Mehar Imtiaz Lali to 31.8237691 Long, 72.8001537 Haidery Chowk Police

1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Construction of PCC / Soling / Drainage / 31.10.2017 12" i/d RCC Sewer= 1974-Rft Street and Tuff Tiles in Mohallah Allah 15" i/d RCC Sewer= 633-Rft 24" i/d RCC Sewer= 1067-Rft Tuff Tile= 107867-Sft 1713 3316 Chowk to Sargodha Road, Station Noorpur Chiniot 25.500 4.420 3.333 3.333 2.500 2.500 100% 6.920 27% Sullage Carrier= 2000-Rft Funds Released Ward no. 2, Ward no. 5 Laliyan, Tariqabad upto 24.01.2019 by the Chief Engineer Ward no. 6 Lalian (South) PHED Lahore and work is in progress. Lat 31.8263464 Long, 72.7997993 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) Construction of PCC / Soling / Drainage / 1. Date of AA = 02.08.2017 2. Date of TS = Street and Tuff Tiles in Mohallah Jamia 28.08.2017 3.Date of Award of work 31.10.2017 24" i/d RCC Sewer= 550-Rft 27" Mosque ward no 7 Laliyan, Imtia Town New i/d RCC Sewer= 3991-Rft Drain Type-I= 1714 3317 Eidgah Umerabad ward no. 11 Phase I, Chiniot 21.499 4.850 3.333 3.333 2.500 2.500 100% 7.350 34% 3318-Rft Tuff Tile= 4290-Rft Sullage Imtiaz Town New Eidgah Umerabad ward Carrier= 4841-Rft Funds Released upto 24.01.2019 by the Chief Engineer (South) no 11 Phase II, including Bangla Road to PHED Lahore and work is in progress. Lat Pir Qatbi Shah 31.8469 Long, 72.79282

1. Date of AA = 02.08.2017 2. Date of TS = Construction of PCC / Soling / Drainage / 28.08.2017 3.Date of Award of work Street and Tuff Tiles in Mohallah Dars 31.10.2017 Drain Type - I= 8241-Rft Brick Colony Bashir Colony Jaly Dar Dakhli Pavement= 38407-Cft P.C.C= 7829-Cft Sullage Carrier= 2570-Rft Funds Released 1715 3318 Laliyan, Miana Thatha Zahoor Colony Chiniot 15.500 4.663 3.500 3.500 1.625 1.500 92% 6.163 40% upto 24.01.2019 by the Chief Engineer Dakhli Laliyan, Mouza oilywala Hujra Hujra (South) PHED Lahore. Work is in Progrees. Colony Abadi near Petrol Pump Dakhli Progress slow due to site problem. Target Laliyan,Mouza Bhais progress will be achieved in coming month. Lat 31.8302425 Long, 72.8125039

Construction of PCC / Soling / Drainage / 1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Street and Tuff Tiles in Mohallah Pulliyan 31.10.2017 Funds Released upto Abadi Rana Colony Soling remaining 1716 3319 Chiniot 31.100 2.850 3.333 3.333 1.500 1.425 95% 4.275 14% 24.01.2019 by the Chief Engineer (South) Portion sargodha road to Rana Colony PHED Lahore. Work stopped by the contractor and Notice issued from this office Dakhli Laliyan, Soling, Mouza Wala, Mouza as well as S.E PHE Circle Faisalabad Thathi Bala Raja, Mouza Kalu wal. Office to the contractor for restart the work.

1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Construction of PCC / Soling / Drainage / 31.10.2017 Drain Type - I= 19723-Rft Brick Pavement= 69030-Cft PCC= 14798-Cft Tuff Street and Tuff Tiles Pullian Mouza Ahmad Tile= 20329-Sft Sullage Carrier= 3101-Rft 1717 3320 Nagar, Carpet City Ladhiyan Phase-I, Chiniot 32.000 9.816 3.333 3.333 2.500 2.385 95% 12.201 38% Funds Released upto 24.01.2019 by the Carpet City Ladhiyan Phase-II, and Chief Engineer (South) PHED Lahore. Work is in Progrees. Progress slow due to alongwith Road Mouza Changarwala. site problem. Target progress will be achieved in coming month. Lat 31.7851137 Long, 72.8899466 1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work 31.10.2017 9" i/d Sewer= 1542-Rft 12" i/d P/L Tuff Tile, Sewer Line PCC and Street Sewer= 3311-Rft Drain Type - I= 1645-Rft Lights in Mohallah Rehmanabad, 1718 3321 Chiniot 40.827 8.900 3.333 3.333 2.500 2.500 100% 11.400 28% PCC= 16470-Cft Tuff Tile= 81142-Sft Karamabad, Moqeet Town and Sagheer Sullage Carrier= 11739-Rft Funds Released upto 24.01.2019 by the Chief Engineer Colony in Tehsil and District Chiniot (South) PHED Lahore and work is in progress. Lat 31.7176689 Long, 72.9887384 1. Date of AA = 02.08.2017 .2. Date of TS = Provision 28.08.2017 3.Date of Award of work Drainage/Sewerage/Nallah/PCC/Tuff Tile 31.10.2017 .Drain Type - I.Brick Pavement. 1719 3322 Chiniot 49.988 10.000 3.333 3.333 2.500 2.250 90% 12.250 25% P.C.C. Tuff Tile.Sullage Carrier. Funds /Brick Pavement including all allied works of Released upto 24.01.2019 by the Chief UC 11, District Chiniot Engineer (South) PHED Lahore and work is in progress. Lat, 31.7676' Long, 73.06908

1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Provision 31.10.2017 .Drain Type - I= 22445-Rft Brick Drainage/Sewerage/Nallah/PCC/Tuff Tile Pavement= 94002-Cft.P.C.C= 5435-Cft Tuff 1720 3323 Chiniot 49.990 14.200 3.333 3.333 2.500 2.500 100% 16.700 33% Tile= 48000-Sft.Sullage Carrier= 9179-Rft /Brick Pavement including all allied works of Funds Released upto 24.01.2019 by the UC 12, District Chiniot Chief Engineer (South) PHED Lahore and work is in progress. Lat,31.7935933 Long, 73.185715 Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) 1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Provision 31.10.2017 .Drain Type - I= 16449-Rft Brick Drainage/Sewerage/Nallah/PCC/Tuff Tile Pavement= 115347-Cft.P.C.C=13250-Cft 1721 3324 Chiniot 49.982 15.000 3.333 3.333 2.500 2.500 100% 17.500 35% Tuff Tile= 40820-Sft.Sullage Carrier= 8270- /Brick Pavement including all allied works of Rft Funds Released upto 24.01.2019 by the UC 13, District Chiniot Chief Engineer (South) PHED Lahore and work is in progress. Lat 31.6358245 Long, 73.0228783

1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Provision 31.10.2017 .Drain Type - I= 33201-Rft.Brick Drainage/Sewerage/Nallah/PCC/Tuff Tile Pavement= 94459-Cft.P.C.C= 1771-Cft.Tuff 1722 3325 Chiniot 49.982 13.000 3.333 3.333 2.500 2.400 96% 15.400 31% Tile= 84000-Sft.Sullage Carrier= 3408- /Brick Pavement including all allied works of Rft.Funds Released upto 24.01.2019 by the UC 14, District Chiniot Chief Engineer (South) PHED Lahore and work is in progress. Lat,31.6536834 Long, 73.0709479

1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work Provision 31.10.2017.Drain Type - I= 21145-Rft.Brick Drainage/Sewerage/Nallah/PCC/Tuff Tile Pavement= 64387-Sft.PCC= 22116- 1723 3326 Chiniot 49.986 20.000 5.000 5.000 3.250 3.120 96% 23.120 46% Cft.Boundary Wall= 60500-Sft.Sullage /Brick Pavement including all allied works of Carrier= 9356-Rft.Funds Released upto UC 15, District Chiniot 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is in progress. Lat 31.7421417 Long, 73.015255 1. Date of AA = 02.08.2017 2. Date of TS = 28.08.2017 3.Date of Award of work 31.10.2017 .Drain Type - I= 25945-RftBrick Provision Pavement= 146874-Cft.Sullage Carrier= Drainage/Sewerage/Nallah/PCC/Tuff Tile 1724 3327 Chiniot 49.990 10.000 5.000 5.000 2.750 2.750 100% 12.750 26% 9337-RftBoundary Wall= 1400-Rft.Funds /Brick Pavement including all allied works of Released upto 24.01.2019 by the Chief Engineer (South) PHED Lahore and work is UC 21, District Chiniot in progress. Progress slow due to site problem. Lat, 31.6127186 Long, 72.7273481 1. Date of AA = 02.08.2017.2. Date of TS = 28.08.2017 3.Date of Award of work Provision 31.10.2017.Drain Type - I= 26088-Rft Brick Drainage/Sewerage/Nallah/PCC/Tuff Tile Pavement= 171905-Cft.Sullage Carrier= 1725 3328 Chiniot 49.980 15.000 5.000 5.000 3.750 3.750 100% 18.750 38% 2206-Rft.Boundary Wall= 220-Rft Tuff Tile= /Brick Pavement including all allied works of 2150-Sft .Funds Released upto 24.01.2019 UC 22, District Chiniot by the Chief Engineer (South) PHED Lahore and work is in progress. Lat, 31.59843 Long 72.7149817 1725 Total Ongoing 126362.993 59312.981 8408.757 8895.424 6473.326 5946.786 92% 65259.767 52% New Schemes 1-Date of A.A 07.12.2018 2- Date of T.S 12.12.2018 3- Anticipated date of completion 30.06.2021 4- No. of Beneficiary Reheblitiation of Rural Water Supply Scheme -4536-Person Pacca Water Course = 200- 1 3329 Toba Tek Singh 28.997 0.000 2.000 2.000 0.000 0.000 #DIV/0! 0.000 0% 394/JB Tehsil & Distt Toba Tek Singh Rft Water Works = 1-Job Water Supply Pipe = 32990-Rft Pumping Machinery = 2- Set Tender received on 09.01.2019 funds demanded on 22.01.2019. Rural water supply scheme Saho Chak, Badi Pur & 2 3330 Gurdanpur U/C Ghurri Tehsil & District Sialkot Sialkot 27.900 0.000 1.000 1.000 1.000 1.000 100% 1.000 4% Tender under process (Court Direction) Rural Drainage Sewerage Scheme of UC Rasulpur 3 3331 Sialkot 5.000 0.000 1.000 1.000 0.000 0.000 #DIV/0! 0.000 0% Tender under process Bhallian Rough Cost Estimate / PC-I prepared by Construction of Sewerage System & Rehabilitation the consultant has been submitted to Chief Rahim Yar Engineer South PHE Department. However 4 3332 of Roads, Municipal Committee Zahir Pir Tehsil 357.877 0.000 5.000 5.000 0.000 0.000 #DIV/0! 0.000 0% Khan clearnce of the scheme form LG & CD Khanpur, Distric R.Y.Khan Department is still awaited. Latitude / longitude -NiL Physical %age Total Revised Funds progress till Sr. GS. No. Approved Exp Upto Provision for Funds utilization Accummulative Name of Scheme District allocation for utilized current Remarks No. New Cost June 2018 2018-19 Released on release exp: till 2018-19 till 30.04.2019 month 30.04.2019 30.04.2019 (%age) The Scheme has been dropped. HUD & Construction of Waste Water Treatment Plant at PHE Department has desired to substitution 5 3333 Mianwali 468.000 0.000 5.000 3.000 0.000 0.000 #DIV/0! 0.000 0% Mianwali. the scheme namely revamping of S/D scheme Mianwali Sewerage Drianage Scheme in 05 No. colonies of Scheme approved by DDWP on 6 3334 chak No. 79/NB including desilting of exisitng Sargodha 69.638 0.000 5.000 3.000 0.000 0.000 #DIV/0! 0.000 0% 15.04.2019. Approval letter is awaited sewer lines, Sargodha (Court Direction) PC-I / Estimate has prepared. Process of Rehabilitaion / Improvement Sewerage system MOU from MC Jhang is under process in 7 3335 Jhang 700.000 0.000 5.000 3.000 0.000 0.000 #DIV/0! 0.000 0% Jhang, Phase-I Committee constituted by Secretary, LG & CD. Sewerage / Drianage scheme adjacent abadies of Estimate returned back by DDWP with 8 3336 Lahore 150.000 0.000 2.500 2.500 0.000 0.000 #DIV/0! 0.000 0% ada Mohlanwal certain. Water, Sanitation and Hygiene (WASH) Programme under stunting reduction programme in Un Approved. PC-I submitted to Planning 9 3337 Punjab 3,086.564 0.000 8.743 8.743 0.000 0.000 #DIV/0! 0.000 0% 11 Districts of Multan, Bahawalpur and D.G.Khan Commission for its placement in ECNEC. Civil Divisions

Feasibility Study for provision of surface water and Un Approved. PC-II submitted in P&D 10 3338 Punjab 200.000 0.000 5.000 5.000 0.000 0.000 #DIV/0! 0.000 0% treatment of waste water across Punjab Department. Un-Approved. Underprocess in Pronvincial 11 3339 Funding for Clearance of liablities Punjab 40.000 0.000 40.000 30.000 0.000 0.000 #DIV/0! 0.000 0% Cabinet Public Awareness Campaign and strengthening of 12 3340 communicty development & communication unit of Punjab 100.000 0.000 5.000 3.000 0.000 0.000 #DIV/0! 0.000 0% Un Approved. PC-I has been prepared. PHED 13 3341 Clean Water for Healthy Life Punjab 5,000.000 0.000 5000.000 4998.000 0.000 0.000 #DIV/0! 0.000 0% - 14 3342 Rural sewerage & drainage schemes Punjab 3,500.000 0.000 2000.000 0.000 0.000 0.000 #DIV/0! 0.000 0% - Water Quality testing Labortary at Township Un Approved. Concept paper has been 15 3343 Punjab 395.000 0.000 1.000 1.000 0.000 0.000 #DIV/0! 0.000 0% Lahore (PPP Mode) submitted in PPP Cell. Establishment of Project Support Unit for Clean 16 3344 Punjab 500.000 0.000 5.000 5.000 0.000 0.000 #DIV/0! 0.000 0% Un Approved. Water for Healthy Life Insaaf Program for Water Supply and Sanitation in 17 3345 Punjab 5,000.000 0.000 5000.000 3820.000 0.000 0.000 #DIV/0! 0.000 0% - Rural Areas 17 Total New 19628.976 0.000 12091.243 8891.243 1.000 1.000 100.00% 1.000 0% 1742 Total Ongoing + New 145991.969 59312.981 20500.000 17786.667 6474.326 5947.786 92% 65260.767 45%