Resettlement Plan

Document Stage: Draft January 2021

IND: Tamil Nadul Industrial Connectivity Project

Cuddalore to Madapattu Road (SH09)

Prepared by Project Implementation Unit (PIU), Kanyakumari Industrial Corridor, Highways Department, Government of for the Asian Development Bank (ADB)

CURRENCY EQUIVALENTS (as of 7 January 2021)

Currency unit – Indian rupee/s (₹) ₹1.00 = $0. 01367 $1.00 = ₹73.1347

ABBREVIATIONS

ADB – Asian Development Bank AH – Affected Household AP – Affected Person BPL – Below Poverty Line CKICP – Chennai Kanyakumari Industrial Corridor Project DC – District Collector DE – Divisional Engineer (Highways) DH – Displaced Household DP – Displaced Person DRO – District Revenue Officer (Competent Authority for Land Acquisition) GOI – Government of GRC – Grievance Redressal Committee IAY – Indira Awaas Yojana LA – Land Acquisition LARRU – Land Acquisition, Rehabilitation and Resettlement Unit LARRIC – Land Acquisition Rehabilitation and Resettlement Implementation Consultant PD – Project Director PIU – Project implementation Unit PRoW – Proposed Right-of-Way RFCTLARR – The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 R&R – Rehabilitation and Resettlement RF – Resettlement Framework RSO – Resettlement Officer RoW – Right-of-Way RP – Resettlement Plan SC – Scheduled Caste SH – State Highway SPS – Safeguard Policy Statement SoR – Schedule of Rate ST – Scheduled Tribe

NOTE

(i) The fiscal year (FY) of the Government of India ends on 31 March. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY2021 ends on 31 March 2021.

(ii) In this report, "$" refers to US dollars.

This draft resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section on ADB’s website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

TABLE OF CONTENTS

EXECUTIVE SUMMARY ...... i A. Scope of the Project ...... i B. Project Road Description ...... i C. Scope of the Land Acquisition and Resettlement Impacts ...... i D. Information Disclosure, Consultation, and Participation ...... ii E. Legislative Framework, Entitlements, Assistance and Benefits ...... ii F. Grievance Redress Mechanism ...... iii G. Implementation Arrangements ...... iii I. PROJECT DESCRIPTION ...... 1 A. Background ...... 1 B. Cuddalore MadapattuRoad (SH 09) ...... 1 C. Profile of the Project Area...... 3 D. Project Impacts ...... 4 E. Minimizing Involuntary Resettlement ...... 6 F. Impact to Indigenous Peoples ...... 6 II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT ...... 7 A. Introduction ...... 7 B. Scope of Land Acquisition ...... 7 C. Impact on Structures ...... 8 D. Loss of Private Structures ...... 8 E. Magnitude of Impact on Structures ...... 9 F. Loss of Livelihood ...... 9 G. Loss of Trees ...... 10 H. Loss of Common Property Resources ...... 10 III. SOCIO-ECONOMIC INFORMATION PROFILE ...... 11 A. Involuntary Resettlement Impacts ...... 11 B. Methodology Adopted ...... 11 C. Demographic Profile of Project Displaced Households ...... 12 D. Socio-economic Profile ...... 13 E. Key Socio-economic Indicators ...... 18 F. Resettlement Preferences ...... 19 G. Profile of Women Headed Household (WHH) ...... 20 IV. CONSULTATION, PARTICIPATION AND DISCLOSURE ...... 21 A. Consultation in the Project ...... 21 B. Methods of Consultation ...... 21 C. Outcome of the Consultations ...... 22 D. Information Dissemination During Census & Socio -economic Survey Revalidation ..... 23 E. Plan for further Consultation in the Project ...... 25 F. Disclosure ...... 26 V. POLICY AND LEGAL FRAMEWORK ...... 28 A. Background ...... 28 B. National Legislations, Policies and ADB Policy ...... 28 C. Legal and Policy Frameworks of Tamil Nadu...... 29 D. ADB’s Safeguard Policy Statement (SPS), 2009 ...... 29 E. Comparison of Government and ADB Policies ...... 29 F. Involuntary Resettlement Safeguard Principles for the Project ...... 30 G. Valuation of land and assets ...... 30

H. Updating Units of Entitlement ...... 32 I. Rehabilitation and Resettlement Award ...... 32 VI. ENTITLEMENTS, ASSISTANCE AND BENEFITS ...... 33 A. Introduction ...... 33 B. Eligibility Criteria ...... 33 C. Entitlement Matrix ...... 33 VII. RELOCATION OF HOUSING AND SETTLEMENTS ...... 43 A. Physically displaced households ...... 43 B. Physical Relocation Allowances Provided by the Project ...... 43 C. Relocation Strategy ...... 43 D. Physical Relocation Allowances Provided by the Project ...... 44 VIII. INCOME RESTORATION AND REHABILITATION ...... 45 A. Loss of Livelihood in this project ...... 45 B. Entitlements for Loss of Livelihood ...... 45 C. Special Measures to Support Vulnerable Groups ...... 46 D. Income Restoration Measures ...... 46 IX. RESETTLEMENT BUDGET AND FINANCING PLAN ...... 48 A. Introduction ...... 48 B. Compensation ...... 48 C. Assistances ...... 48 D. Compensation for Community Assets and Government Structures ...... 48 E.RP Implementation Cost ...... 48 F. Source of Funding and Fund Flow ...... 49 G. Resettlement Budget Estimates ...... 49 H. Disbursement of Compensation and Assistances ...... 49 X. GRIEVANCE REDRESSAL MECHANISM...... 53 A. Introduction ...... 53 B. Grievance Redressal Committee ...... 53 C. Functions of Local-Level GRC ...... 54 D. Costs ...... 55 XI. INSTITUTIONAL ARRANGEMENT AND IMPLEMENTATION ...... 56 A. Land Acquisition, Rehabilitation and Resettlement Units (LARRU) ...... 56 B. Project Implementation Unit ...... 56 C. Competent Authorities ...... 58 D. LARRIC/Agency for RP Implementation Support ...... 59 E. External Monitoring...... 60 F. Land acquisition and Resettlement process: ...... 60 XII. IMPLEMENTATION SCHEDULE ...... 62 A. Introduction ...... 62 B. Schedule for Project Implementation ...... 62 C. RP Implementation Schedule ...... 62 XIII. MONITORING AND REPORTING ...... 65 A. Introduction ...... 65 B. Internal Monitoring ...... 65 C. External Monitoring ...... 65 D. Indicative Indicators ...... 65 E. Reporting Requirements ...... 67

EXECUTIVE SUMMARY

A. Scope of the Project

1. The has proposed to upgrade its road network under Chennai Kanyakumari Industrial Corridor Project (CKICP) that aims at improving the transport infrastructure, such as connectivity of industrial nodes to ports, urban areas, other nodes and critical hinterland areas, with financial assistance from the Asian Development Bank as Tamil Nadu Industrial Connectivity Project. As part of the current project, the Highways Department of Tamil Nadu has been mandated to undertake improvement and upgradation of various State Highways at different locations in the State under this project.

2. The proposed project will support upgradation and improvement of the identified 16 road projects totalling of about 587.099 km spread across the State.The Project Implementation Unit (PIU) of CKICP of the Highways Department has prepared this Resettlement Plan (RP) for the Cuddalore Madapattu (SH 09) being one of the 16 roads proposed for improvements under CKICP. This RP assesses the involuntary resettlement impacts resulting from the acquisition of private land and impacts on squatters and encroachers occupying the Right of Way (RoW). It outlines mitigation measures in line with ADB's Safeguard Policy Statement, 2009 and Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.

B. Project Road Description

3. The Cuddalore to Madapattu road, involves improvements to 37.360 km of the State Highway- (SH-09). The entire stretch along the existing 2-lane corridor on SH-09, is proposed to be improved toa two-lane corridor with paved shoulders, paver block and drains. This project roadis located in Cuddalore and districts and spreads across Taluks of Panruti, Cuddalore, Ulundurpet.

C. Scope of the Land Acquisition and Resettlement Impacts

4. The objective of this Resettlement Plan (RP) is to assist the affected people to improve or at least restore their living standards to the pre-project level. This RP captures the involuntary resettlement impacts arising out of the proposed improvements to the proposed project road under CKICP. The document describes the magnitude of impact, mitigation measures proposed, method of valuation of land, structures and other assets, eligibility criteria for availing benefits, baseline socio-economic characteristics, entitlements based on type of loss and tenure, the institutional arrangements for delivering the entitlements and the mechanism for resolving grievances and monitoring.

5. The land plan schedules based on the detailed design have been prepared for this project stretch and the number of titleholders based on the revenue records has been captured. The proposed project road will involve the acquisition of 20.3 ha of private land belonging to 270 landowners, the transfer of 0.7113 Ha of government lands.

6. The improvements proposed will cause impact to 748 private structures. The impact to 748 private structures will cause the physical displacement of 38 households, of economic displacement of 23 households, of physical and economic displacement of 2 households and of 12 tenant households and non-significant impact on 685 households. There are 83 landowners ii losing 10 percent and more land who would also face economic displacement. In addition, 81 common property resources will also be affected. In all, the project will cause impact to households 956 comprising of 3804 persons.

7. Out of 748 Private Structure, 63 are significantly affected. Out of 63 significantly affected structures 38 are residential structures and 23 are commercial structures, the 2 are residential cum commercial structures. Out of the total affected structures 36.1% are permanent structures, 21.26% are semi – permanent structures, 25.80% of the structures are temporary in nature and 16.84% are other category structures. The affected structures include 23 owners of business, 09 Commercial tenants.

8. In addition to the 62 affected title holders, 628 encroachers, 58 squatters, 12 tenants also would be affected. In all, the project will cause impact to 956 households comprising of 3804 persons.

D. Information Disclosure, Consultation, and Participation

9. During the census and socio economic survey, focus groups discussions (FGDs) were conducted along the project road in settlements and sections where there were impacts to private assets. All relevant aspects of the road improvement design, land requirements and impact to private property were discussed with the affected communities. Further, consultation meetings with affected persons, owners of commercial establishment along the project road, officials of the district administration and elected members of the local Panchayat were held in six locations.

10. Information will be disseminated to DPs at various stages. Information including magnitude of loss, detailed asset valuations, entitlements and special provisions, grievance procedures, timing of payments, displacement schedule, civil works schedule will be disclosed by the Land Acquisition, Rehabilitation and Resettlement Unit (LARRU) with the assistance from the agency hired for implementing the RP. The translated gist of the EM would provide details of the project, magnitude of impact to land and assets, eligibility and entitlement, institutional arrangement and grievance redressal process. Hardcopies of the gist of the EM in Tamil will be distributed to the DPs by the LARRIC as per the ADB guidelines.

E. Legislative Framework, Entitlements, Assistance and Benefits

11. The entitlements for the Chennai Kanyakumari Industrial Corridor Project (CKICP) is based on national law: The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, State laws and regulations and ADB’s Safeguard Policy Statement (SPS), 2009.

12. For title holders, the date of preliminaryland acquisition notification will be treated as the cut-off date, and for non-title holders, the cut-off date will be the census revalidation date as in this project the original census survey was done in September 2015.The census revalidation has been carried in 17 May 2019. The date of commencement of census revalidation (i.e)17 May 2019 will be the cut-off date for non-titled holders for this Project.

13. The Entitlement Matrix (EM) for the Chennai Kanyakumari Industrial Corridor Project summarizes the types of losses and the corresponding nature and scope of entitlements is in compliance with National/State Laws, in particular the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and Asian iii

Development Bank’s Safeguards Policy Statement, 2009. The total resettlement cost for the project is INR 337.71 million.

F. Grievance Redress Mechanism

14. Grievance Redressal Committee (GRC) will be established at two-levels, one at the Regional level and another at the Project level, to receive, evaluate and facilitate the resolution of affected persons concerns, complaints and grievances.

G. Implementation Arrangements

15. To expedite land acquisition and implement the provisions of the RPs, four regional level Land Acquisition Rehabilitation and Resettlement Units (LARRU) have been constituted and all the four units are operational. This road comes under the jurisdiction of Kanchipuram region LARRU. LARR units are headed by Special District Revenue Officer, Kanchipuram (Spl DRO) and is supported by a Resettlement Officer (RSO), Kanchipuram and Special Tahsildar of Cuddalore.

16. The CKICP Division, Highways Department, Government of Tamil Nadu is the Project Implementation Unit (PIU) and responsible for overall in charge of coordination between the six Divisional Engineers (H) and the four Land Acquisition Rehabilitation and Resettlement Units (LARRU). The PIU is headed by a Project Director (PD) and supported by a Chief Engineer with a full-fledged unit under him. A Special District Revenue Officer (Spl DRO) has been posted at the PIU to coordinate with the 4-LARRU and assist PD, PIU in land acquisition, Rehabilitation and resettlement matters.

17. In view of the significance of resettlement impacts in this project, the monitoring Mechanism for this project will have both monitoring by LARRU and monitoring by an external agency / expert.

I. PROJECT DESCRIPTION

A. Background

1. The Government of Tamil Nadu proposes to upgrade its road network under the Chennai Kanyakumari Industrial Corridor Project (CKICP), which aims at improving the transport infrastructure, such as the connectivity of industrial nodes to ports, urban areas and critical hinterland areas. The Highways Department of Tamil Nadu has been mandated to undertake improvement and upgradation of various State Highways at different locations in the State under this project. The project will improve16 road projects totalling about 587.099 km spread across the State and financed through a loan from the Asian Development Bank (ADB). The project roads proposed under CKICP and their packaging details is given below.

Table 1: List of Projects Proposed under CKICP SNo Road No Road Name Length 1 SH-40-I Tiruchendur to Ambasamudram via Palayamkottai 50.590 2 SH-191 Melur to Tirupattur 30.485 3 SH-63 Thanjavur to Mannargudi 27.585 4 SH-66 Kumbakonam to Mannargudi 14.900 5 SH-64 Kumbakonam to Sirkazhi 36.779 6 SH-23 Mayiladuthurai to Thiruvarur 29.882 7 SH-95 Mohanur–Namakkal–Senthamangalam– Rasipuram 31.500 8 SH-79 Tiruchengode to Erode 11.153 9 SH-142 Thuraiyur to Permabalur 30.057 Omalur to Tiruchengodevia Sankakiri including 10 SH-86 51.715 Tiruchengode Bypass 11 SH-58-I Chengalpattu –Kanchipuram 39.786 12 SH-58-II Kanchipuram to Tiruthani 41.779 13 SH-115 Cheyyur (ECR) to Polur including ECR link 109.273 14 SH-09 Cuddalore to Madapattu 37.360 15 SH-69 Vridhachalam to Ulundurpet 22.855 16 SH-40-II Tiruchendur to Ambasamudram via Palayamkottai 21.400 Total Length 587.099

2. The Project Implementation Unit (PIU) of the Highways Department has prepared this Resettlement Plan (RP) for the Cuddalore to Madapattu (SH 09), being one of the 16 project roads proposed under CKICP. This RP assesses the involuntary resettlement impacts resulting from the acquisition of private land and impacts on squatters and encroachers occupying the Right of Way (RoW). It outlines mitigation measures in line with ADB's Safeguard Policy Statement, 2009 and Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.

B. Cuddalore Madapattu Road (SH 09) 3. The project, Cuddalore Madapattu road, involves improvements to about 37.360 km of the State Highway-09 (SH-09). The existing 2-lane corridor along SH-09 will be improved to a two-lane corridor with pavedshoulders and drains. This project corridor is located in Cuddalore 2 and kallakurichi districts and spreads across Panruti, Cuddalore, Ulundurpet Taluks.The key plan of the project road is presented below.

Figure 1: Key Plan Cuddalore Madapattu Road (SH 09)

4. In rural sections, the proposed cross section design is 23.00m consists of 7.00m carriage way, 2x1.5m paved shoulders, 2x1.00m earthen shoulders, 2x2.00m Utility corridors are 2x1.5m embankment and drain. In urban sections, the cross section design is 16.00m that consists 7.00m carriageway, 2x1.5m paved shoulders, 2x1.5 Utility corridors and 2x1.5 footpath cum drains.

5. The project road connects Cuddalore and Kallakurichi districts. The project road is the shortest route from Cuddalore to Kallakurichi. The start of the project road is Cuddalore which connects famous pilgrim centers for Hindus, Christians and Muslims in Nagapattinam and it attracts the tourist traffic and connects to Pondicherri and Chennai to Trichy (NH 45).

3

Figure 2: Project Road

C. Profile of the Project Area

6. This project corridor is located in Cuddalore and Kallakurichi districts and spreads across the taluks of Panruti and Cuddalore of Cuddalore; Ulundurpet in Kallakurichi District.

7. located in Lattitude 150 5” / 110 11” and 120 35”N Longitude 780 38” and 800 00” of the geographical location. The district has an area of 3703 km. It is bounded on the north by Villupuram District and Kallakurichi district, on the east by the Bay of Bengal, on the northeast by Puducherry district of the union territory Puducherry, on the south by , on the west by and by a small part with .

8. According to 2011 census, Cuddalore district had a population of 2,605,914 with a sex ratio of 987 females for every 1,000 males, much above the national average of 929. A total of 279,950 were under the age of six, constituting 147,644 males and 132,306 females. Scheduled Castes and Scheduled Tribes accounted for 29.32% and .6% of the population respectively. The average literacy of the district was 79%, compared to the national average of 72.99%. The district had a total of 635,578 households. There were a total of 1,169,880 workers, comprising 136,035 cultivators, 325,599 main agricultural labourers, 19,151 in house hold industries, 356,486 other workers, 332,609 marginal workers, 29,135 marginal cultivators, 213,813 marginal agricultural labourers, 12,876 marginal workers in household industries and 76,785 other marginal workers. 4

The district is prone to natural calamities having experienced landfalls of major cyclones formed in the Bay of Bengal region. Apart from the cyclones, 2004 Tsunami caused massive damages to life and property in Cuddalore and its adjacent Nagapattinam district. Cyclone Thane which made landfall here caused major loss to life and property. The district contributes significantly to the Tamil Nadu state production of cashew nut and jack fruit. Thenpennaiyar, Kedilam, Vellar and Manimuthar are the significant rivers of Cuddalore and it have four reservoirs like Wellington, Veeranam, Perumal and Valaja.

9. Kallakurichi is one of the 37 districts which belong to Tamil Nadu state situated on the southern tip of India. The district headquarters is located at Kallakurichi. Kallakurichi district was announced on 8th January 2019 and it came into existence on 26th November 2019 when it was carved out of Villupuram district. It covers 6 taluks namely Kallakurichi, , , Ulundurpet, Thirukovilur and Kalvaraya nmalai. The district comprises the population of 1,682,687. Kallakurichi is an emerging agricultural district. It is also known as "Home of Agriculture". There are over 10 Rice processing units or modern rice (mills) both small and big in this town. Textiles, Jewellery and agricultural feeds are major businesses. The town has two government co-operative sugar mills and one private sugar mill, and one solvent extraction plants. There are many poultry farms in and around Kallakurichi. The name is derived due to the green nature of this village along the banks of the river Gomuki which nourishes the village by its water.

D. Project Impacts

10. The towns and villages along the project road will improve connectivity with the National Highways (NH-45), the section of Chennai to Kanyakumari Industrial Corridor. This will lead to industrial growth along the project road that will result in employment generation. Further, the improvements and designs proposed under this road will improve connectivity for the local community living in the vicinity, to markets, health care facilities, and educational institutions. However, the improvements will involve the acquisition of private land for widening and geometric improvements. Moreover, it will also have impacts on non-titled holders using the Right of Way (ROW).

11. The involuntary resettlement impacts are summarized in Table 2. The proposed project road will involve the acquisition of 20.3 Ha of private land belonging to 270 landowners, the transfer of 0.7113 Ha of government land and will impact 748 private structures. Among these, 38 HHs will lose residence and have to be physically displaced; 23 households economically displaced through loss of shops; 2 households will lose both their residence and shops. A total of 9 commercial tenants will be affected by the project. The number of total affected persons is 3804, of which 1075 are titled APs and 2729 nontitled APs, and 29 Vulnerable Households. A total of 748 structures will be affected and 1613 trees on private land will have to be removed. A total of 81 Common Property Resources (CPRs) like bus shelters and other public infrastructure will be affected. The involuntary resettlement impacts are summarised in Table 2.

5

Table 2: Summary of Involuntary Resettlement Impacts

12. Based on the census survey, amongst 29 vulnerable in significantly affected households, none were women-headed households, 03 disabled households, 19 scheduled caste households, 3 households were below poverty line, none of the minor Children with no support (below 14 years) and 4 households of elderly people. The households available at project site during the survey period only covered in the survey. However, the HHs those who are not staying in the project area will also be surveyed during award enquiry, which is in progress. The vulnerability assessment will be done for all the project affected families/members. Government of Tamil Nadu, government is implementing various welfare schemes for upliftment of vulnerable people of the state. Hence project will provide additional benefits for the affected vulnerable Households as per EM. Non-significantly affected PAFs would be compensated for loss of structure or land affected by the project.

6

Table 3: Impact to Vulnerable Category (mutually exclusive) S.No Number of Vulnerable Category HH impacted 1 Women Headed Household 0 2 Scheduled Caste 19 3 Scheduled tribes 0 4 Below poverty line 3 5 Disabled persons in the Household 3 6 Elderly 4 7 Minor Children with no support (below 14 0 years) Total 29 Source: Census and Social Survey, September to October 2019.

E. Minimizing Involuntary Resettlement 13. Measures were taken to minimise adverse involuntary resettlement impacts by adopting concentric widening in built-up sections and reducing the proposed right-of-way to 13m/16m. The available right-of-way (RoW) was utilised to the maximum, thereby reducing additional land requirements for the proposed widening.

F. Impact to Indigenous Peoples 14. The census and socio-economic survey and consultations conducted along the project road confirm that there are no affected indigenous people.

1 Agricultural landowners who lose 10% or more of their land. 2 Where the impact to asset / structure is less than 10% of the total area, then such impacts are categorized as non- significant impacts as the DP is neither physically nor economically displaced. 3 Amongst significantly affected household.

7

II. SCOPE OF LAND ACQUISITION AND RESETTLEMENT

A. Introduction

15. The project involves improvements to 37.360 km of the Cuddalore to Madapattu (SH 09) two lanes with paved shoulders. The improvement works include geometric improvements, junction improvements, provision of drains and foot paths in built up locations.

B. Scope of Land Acquisition 16. The available right-of-way (RoW) was fully optimized for the proposed improvements. The exact alignment of the RoW was determined using village maps and verified in the field. The highways department confirms that, the existing right of way belongs to highways department and there are no legacy issues in any of the project stretches. In many areas, the existing RoW is not sufficient to meet the design requirements of the cross sections. The private land required for the proposed improvements is 20.3 Ha, comprising of 0.3154 Ha of wet land and 19.9846 Ha of dry land. The private land proposed for acquisition is mostly strips of land. Further, 0.7113 Ha of government land will also be required to be transferred for the proposed improvements. The land plan schedules (LPS) have been prepared and the precise number of titleholders and extent of land lost will be updated once the LPS is completed and the preliminary notification is issued.

Table 4: Category of Land being Acquired S.I. No. Type of Ownership Extent (in hectare) 1 Private Wet 0.3154 2 Private Dry 19.9846 3 Government 0.7113 Total 21.0113 Source: LPS prepared by DPR Consultants, November 2018.

17. The details of the types of private land proposed for acquisition are presented in Table 4 and 5. Table 5: Classification of Loss of Private Land and Impacts SNo Project Component Area in Hectare Wet Dry Govt Total 1 Land along the road for widening 0 11.065 0.7113 11.7763 2 Bypass 0.3154 8.9196 0 9.235 Total 0.3154 19.9846 0.7113 21.0113 Source: LPS prepared by DPR Consultants, November 2018.

18. Extent of land lost and the scale of impact to titleholders is presented in the Table below. Around 69.26% of households (187 HH out of 270 total land affected HH) will lose up to 10% of their land holdings. A total of 30 households will be affected above 10% and 25% impact; 16 HHs above 25% and below 33.3% impact; 15 HHs above 33.3% and below 50% impact; 13 HHs above 50% and below 75% and 09 HHs above 75%. Survey covered all the affected households including the HHs losing only strip of land. During revalidation survey (May 2019) the study team could not contact most of the land only affected households as they are staying away from the project site and no proper contact details are available with the land acquisition offices. However, 8 most of such households would be attending the award enquiry meetings, being conducted by respective land acquisition officer. Census survey/validation is also being done during the award enquiry. All the affected households attending award enquiry will be covered in census survey and assessment will be done. On completion of award enquiries the list of PAHs would be finalized and the same shall be provided in the updated RP. The compensation will be paid as per the entitlement matrix. As per the approved EM, all the land only affected will be eligible for replacement cost and those who are losing livelihood is eligible for Rs 5 lakh in lieu with annuity policy under clause 1(b),2(h) and 3(g).

Table 6: Intensity of Land Impact Number of Affected Percent SNo Scale of Impact Household 1 Up to 10% 187 69.26 2 Above 10% and Below 25% 30 11.11 3 Above 25% and Below 33.3% 16 5.92 4 Above 33.3% and Below 50% 15 5.56 5 Above 50% and Below 75% 13 4.82 6 Above 75% 09 3.33 Total 270 100.00 Source: LPS prepared by DPR Consultants, November 2018. C. Impact on Structures 19. The improvements proposed will cause impact to 748 private structures and 81 common property resources. Further, there are 12 tenants who will be affected. However, only 8.4% (63 out of 748) of the structures are significantly affected and require to be rebuilt, while for the remaining 91.6%, structures will bear non-significant impacts. Among the significantly affected structures, 36.5% of the structures are being used for commercial purpose, 60.32% are used as residences, and 3.18% are used for both residence and commercial purpose.

D. Loss of Private Structures 20. 8.29% of the affected structures are owned by title-holders, 83.96% are owned by encroachers and 7.75-% are owned by squatters and no kiosks found in the entire stretch. The ownership details of the affected private structures are presented in Table 7.

Table 7: Ownership of Private Structures Residential Cum Number of Tenure Residential Commercial Commercial Others Structures Percentage Titled-holders 34 11 7 10 62 8.29 Encroachers 234 244 99 51 628 83.96 Squatters 27 25 4 2 58 7.75 Total 295 280 110 63 748 100.00 Source: Census and Social Survey, May 19- Jan 2020.

9

21. 25.80% structures that are temporary in nature and 21.26% of the structures are semipermanent and 36.10% are permanent structures and others constitute 16.84%. The type of construction of the affected structures is presented in Table 8.

Table 8: Type of Construction of the Affected Structures Type of Structure Number of Structures Percentage Permanent 270 36.10 Semi-permanent 159 21.26 Temporary 193 25.80 Others (CW, lean to roof, toilet, etc) 126 16.84 Total 748 100.00 Source: Census and Social Survey, May 19- Jan 2020.

E. Magnitude of Impact on Structures 22. The project will impact 748 structures and the structures have been assessed for the significance of impact, with loss of less than 10 percent being considered as non-significant and loss of 10 percent and above as significant. Of course, during the RP implementation, a proper assessment on the structure’s viability will be conducted in consultation with its owner to determine whether the house is fully affected – even in case of less than 10% impact by a qualified engineer in consultation with the affected HH. The information in Table 9 will be updated after the completion of the joint verification and on completion of structure valuation.

23. The extent of loss to structure and its use is presented in Table 9. Of 106 HHs affected, 43 HHs will face 10% impact; the extent of loss faced by 7 HHs would be between 10%-20%; for 28 HHs between 20 – 50%; 21 HHs between 50 – 99% and for 7 HH impacted upto 100% impact.

Table 9: Use by Extent of loss to the Affected Structures Residence cum Residence Commercial Commercial Total (No. Impact (No. of HH) (No. Of HH) (No. Of HH) Of HH) Less than 10% 21 13 9 43 ≥ 10% and < 20% 4 2 1 7 ≥20% and < 50% 18 9 1 28 ≥50% and ≤ 99% 11 10 0 21 100% 5 2 0 7 Total 59 36 11 106 Source: Census and Social Survey, May 19- Jan 2020.

F. Loss of Livelihood

24. The Project causes significant impact to 23 commercial establishments and 2 residence cum commercial establishments [Table 10]. Further there are 09 commercial tenants and 83 land owners who would also face economic displacement resulting in total loss of livelihood to about 466 displaced or significantly affected persons (PAPs). The category of impacts causing loss of livelihood is presented Table 10.

10

Table 10: Loss of Livelihood Number of Displaced Number of Displaced Category of Loss Households Persons Owners of Business 25 100 Commercial Tenants 09 36 Employees 00 00 Significantly affected land owners 83 330 Total 117 466 Source: Census and Social Survey, Sep- Oct 2019.

G. Loss of Trees

25. The Project will require removal of 1613 private trees. All other trees getting affected in this project belong to the government and the re-planting of government trees will be done in accordance with the State norms and regulations. Further, the Land Plan Schedule (LPS) prepared will be taken up for scrutiny by the revenue authorities and at that time if there are trees in the land being acquired, they will be compensated in accordance with the provisions contained in the EM.

H. Loss of Common Property Resources 26. The project will affect 81 common property resources. Out of these, 42 are compound walls, government buildings and portion of government buildings, 13 of which will be fully affected. The LARRU, with the support of RP implementation consultant, will consult the trustees of the places of worship, institutions and local Panchayat, will facilitate in the relocation of these places of worship. The common property resource that is getting affected in the project is presented in Table 11.

Table 11: Loss of Community Structures Number of Partially Fully Type of Community Asset Percentage Structures affected affected Place of worship 22 10 12 27.16 Bus stop 17 0 17 20.99 CW, Government buildings, etc 42 29 13 51.85 Total 81 39 42 100.00 Source: Census and Social Survey, Sep- Oct 2019.

11

III. SOCIO-ECONOMIC INFORMATION PROFILE

A. Involuntary Resettlement Impacts

This RP is based on the census and socio-economic survey carried out on 17.05. 2019 based on final and detailed design of the road project. The RP is based on the final engineering design, and the information provided in the RP is based on the preliminary notification. The physical and economic displacement shall be confirmed during award enquiry by the land acquisition officer. RP will be updated on completion of ‘Award Enquiry’ as per land acquisition procedure. The census survey identified 748 households losing their structure and the salient findings are presented in the following sections. Compensation for loss of assets based on the extent and type have been worked out following Entitlement matrix, joint verification and valuation of assets for both physical and economic displacement. The information about the affected persons and compensation will be finalized during award enquiry for both eligible title and non-title holders (including vulnerable households). 27.

B. Methodology Adopted

28. The census survey enumerated all private assets/properties and common property resources within the proposed right-of-way (PRoW) of 16 m in urban sections, 23m in rural sections, and 30m in bypass sections. For every affected household, a pretested structured questionnaire was administered during the census survey. The survey recorded details of: (i) identity of the Project Affected Household (AH); (ii) tenure; and (iii) type, use and extent of loss to the DH.

29. In addition to recording the above information, detailed socio-economic characteristics, including demographic profile of members of the household, standards of living, inventory of physical assets, vulnerability characteristics, indebtedness level, health and sanitation, and ascertaining perceptions about project, resettlement options and compensation, was collected from all main building affected households. All structures were photographed and numbered for reference and record. Details of common property resources within the PRoW were also recorded.

30. The affected households were categorised based on the severity of impact as significant (loss of 10 percent and above of the productive asset or structure) and non-significant (loss of less than 10 percent of the productive asset or structure). The summary of Affected Households and the summary of Affected Common Property Resources are presented in Appendix-1.

31. The census survey identified 748 households and 12 tenants who would be affected and 81 common property resources are affected and required to be relocated or compensated. Of the 748 households, 63 structures are significantly affected households. 38 residential households will have significant impact on their buildings and 23 households on economic displacement, 2 HHs on residential cum commercial structures are covered in socio economic survey. The survey details are analyzed and presented in the following sections. Out of the 63 significantly affected HHs 61 were responded to the survey.

32. Further, as per the land-plan-schedule (LPS) that has been prepared, there are 270 land parcels which would involve at least that many number of landowners who would be losing a strip of their land due to widening or bypass or curve improvement. Among these 270 landowners, 83 landowners will be significantly affected with a loss of 10 percent or more of their land holding 12 and the remaining 187 landowners will face non-significant impact as their loss is less than 10 percent.

33. The RP is based on the final engineering design, the information provided in the RP is based on the preliminary notification. The physical and economic displacement shall be confirmed during award enquiry by the land acquisition officer. RP will be updated on completion of ‘Award Enquiry’ as per land acquisition procedure. Socio economic survey has been conducted for all the physically and economically displaced affected households. The economic displacement of land only affected households can be assessed only during award enquiry. This section of the RP will be updated on completion of award enquiry. The socioeconomic survey was carried out amongst 61 out of 63 significantly affected households (includes both physical and economic displacement) losing either their place of residence or place of business or both; 2 households were not available despite multiple visits. The details are provided in Tables 15 & 17 based on the current survey data. This section of the RP will be updated on completion of award enquiry. The survey details are analyzed and presented in the following sections. In some villages (including Bypasses) few assets were not surveyed, due to non-acceptance providing data and to undertake measurement, hence there will be a chance of increase in number of DPs.

C. Demographic Profile of Project Displaced Households

1. Household by Sex

34. Out of 61 DHs, All 100% of the households are headed by male.

2. Household by Religion

35. The majority of the displaced households in SH 09 are Hindus (91.80%) (56 HHs), followed by Muslims (8.20%) (5 HHs) (Table 12).

Table 12: Household by Religion Religion Number Percentage Hindu 56 91.80 Muslim 5 8.20 Total 61 100.00 Source: Census and Social Survey, Sep- Oct 2019.

3. Household by Social Group

36. Of the 61 displaced HHs, 18 HHs (29.51%) belong to the backward caste category, 18 HHs (29.51%) belonged to the Scheduled Caste category (Table 13). There were 20households most backward caste and none of the households belong to scheduled tribe affected by the project.

Table 13: Household by Social Category Social Category Number Percentage General 5 8.20 Backward caste 18 29.51 Most Backward caste 20 32.78 Scheduled caste 18 29.51 Total 61 100.00 Source: Census and Social Survey, Sep- Oct 2019. 13

4. Household by Size of Family

37. Amongst the 61 DHs, family of size 3 to 4 members constituted to 29.51%, followed by up to 2 members constituting 24.59% (15 HHs), 20 households constituting 32.79% having 5 to 6 members and 8 households have above 6 members (13.11%)(Table 14).

Table 14: Size of the household Size of the Family Number Percentage Up to 2 15 24.59 3 to 4 18 29.51 5 to 6 20 32.79 Above 6 8 13.11 Total 61 100.00 Source: Census and Social Survey, Sep- Oct 2019.

5. Age group of DPs

38. Of the 61 affected households, comprising 247 persons (Men: 128 and Women: 119) will be affected by the road. The majority of them, numbering 73 persons belong to the age group up to 21 years [29.5% (Male 29.7 and female 29.4)], 48 persons belong to the age group of > 21 and ≤ 35 category [19.4% (Men:24 and Women:24)], followed by 35 persons belonging to the age group > 50 and ≤ 65 [14.8% (Men:19 and Women:16)]; 67 persons (Men:32 and Women: 35) belonging to the age group > 35 and ≤ 50 and 24 person among the displaced belonged to the > 65 group (Table 15).

Table 15: Age Group of DPs Male Female Total Age Group Number Percentage Number Percentage Number Percentage Up to 21 38 29.7 35 29.4 73 29.5 > 21 and ≤ 35 24 18.8 24 20.2 48 19.4 > 35 and ≤ 50 32 25.0 35 29.6 67 27.2 > 50 and ≤ 65 19 14.8 16 13.2 35 14.0 Above 65 15 11.7 9 7.6 24 9.8 Total 128 100.00 119 100.00 247 100.00 Source: Census and Social Survey, Sep- Oct 2019.

D. Socio-economic Profile 1. Educational level of DPs

39. The educational level of about 23.5% of the displaced persons is between 9th and 10th Class (27.50% Men and 19.3% Women) constituting to the majority among the displaced. Uneducated constituted 8.9% of the displaced (10 Men and 11 Women). PAPs constitute 15.4% belonging to the categories between 6th and 8th. 14.5% of them have studied up to primary education.

Table 16: Educational level of DPs Educational Male Female Total level Number Percentage Number Percentage Number Percentage Up to 5th 15 11.9 21 16.8 36 14.5 14

Educational Male Female Total level Number Percentage Number Percentage Number Percentage 6th to 8th 19 15.0 19 16.0 38 15.4 9th to 10th 35 27.5 23 19.3 58 23.5 11th and 12th 10 8.1 16 13.4 26 10.5 Diploma 18 13.8 2 1.7 20 7.7 Graduate 17 13.1 19 16.0 36 14.6 Post Graduate 4 3.1 8 6.7 12 4.9 Uneducated 10 7.5 11 10.1 21 8.9 Total 128 100.00 119 100.00 247 100.00 Source: Census and Social Survey, Sep- Oct 2019. 2. Occupation of DPs

40. Amongst 247 PAPs,35.9% of men and 52.1% of women are not in the work force, comprising largely of children, students, elderly, housewives and women who do not work outside home. Among the workforce, majority of the PAFs were engaged as Agricultural Labourers, constitute 19.8% about 1.6% are casual labourers, 5.7% of cultivators, 2% involved in business/trade, about 3.20 each operating petty / tea shops and eatery shops, another 2.8% are either salaried or pensioners, 6.9% are self-employed, With regard to men, 14.1% are agricultural labourers 11.7% are self-employed; 3.2% each operating petty / tea shops and eatery respectively. The table depicts that the majority of the PAPs (43.7%) are in the category of not in workforce as the household members were engaged in education and elderly PAPs .

Table 17: Occupation of DPs S.No Male Female Total Occupation Number Percentage Number Percentage Number Percentage 1 Petty / Tea shop 6 4.7 2 1.7 8 3.2 2 Eatery 7 5.5 1 0.8 8 3.2 3 Repair / Spare part 2 1.6 0 0.0 2 0.8 4 Business/Trade 4 3.1 1 0.8 5 2.0 5 Self employed 15 11.7 2 1.7 17 6.9 6 Salaried/Pension 5 3.9 2 1.7 7 2.8 7 Professional 1 0.8 3 2.5 4 1.6 8 Industrial worker 0 0.0 0 0.0 0 0.0 9 Casual labourer 4 3.1 0 0.0 4 1.6 10 Cultivator 14 10.9 0 0.0 14 5.7 11 Agri labourer 18 14.1 31 25.2 49 19.8 12 Livestock/dairy 0 0.0 0 0.0 0 0.0 13 Unemployed 6 4.7 15 13.4 21 8.5 14 Not in workforce 46 35.9 62 52.1 108 43.7 Total 128 100.00 119 100.00 247 100.00 Source: Census and Social Survey, Sep- Oct 2019.

15

3. Income of Household

41. The pattern of monthly family income range of DHs was as follows: 4.9% of the DHs earned between Rs.1501-6188; 49.2% between Rs.6,189 to 10,000; about 18.0% between Rs.10,000 to 15,000; and 16.4% above Rs.20,000.

42. Those earning below Rs.1477/- per capita per month (for the average family size of 4.3) will be treated as belonging to below poverty line as per Dr.C. Rangarajan Committee's revised methodology for measurement of poverty*. The average monthly family income of DPs was reported as Rs.7326.

(*The state specific poverty line for rural Tamil Nadu for the year 2011-12, as per Dr. C. Rangarajan committee's (constituted by Planning Commission of India) revised methodology for measurement of poverty, is Rs.1081.94 per capita per month. The same has been updated to September 2015 based on CPIRL and accordingly BPL families have been identified. The BPL cut-off income is Rs.1,477/- per capita per month for September 2015).

Table 18: Monthly Household Income of DHs Monthly Family Income Range Number Percentage Up to 1,500 0 0.0 1,501 to 6,188 3 4.9 6,189 to 10,000 30 49.2 10,001 to 15,000 11 18.0 15,001 to 20,000 5 8.2 >20,000 10 16.4 Not disclosed 2 3.3 Total 61 100.00 The average monthly family income is Rs. 10591 Source: Census and Social Survey, Sep- Oct 2019.

4. Indebtedness of Household

43. Among 61 displaced households, 7 HHs (11.48%) had borrowed from banking institutions, and 13 (21.31%) from money lenders. 41 HH (67.21%) had not made any borrowings.

Table 19: Indebtedness of DHs Indebtedness Number Percentage Banking Institutions 7 11.48 Money Lenders 13 21.31 None 41 67.21 Total 61 100 Source: Census and Social Survey, Sep- Oct 2019.

44. Among those who had borrowed from banks, 04 HHs have borrowed a sum above above a sum of Rs.1,00,000.

16

Table 20: Extent of Loan taken - Bank Amount Borrowed Number Percentage ≤ 10,000 > 10,000 and ≤ 25,000 2 28.57 > 25,000 and ≤ 50,000 > 50,000 and ≤ 1,00,000 1 14.29 > 1,00,000 4 57.14 Source: Census and Social Survey, Sep- Oct 2019.

45. With regard to the purpose of borrowings from the bank, 57.14% (04 HHs) reported that they had borrowed for purpose of house construction; and another 28.57% (02 HHs) for education and 14.29% (01 HHs) of the households agriculture.

Table 21: Purpose of Loan - Bank Borrower Number Percentage Agriculture 1 14.29 Business investment Medical expenses Wedding / Family function House Construction / Repair 4 57.14 Educational Loan 2 28.57 Others Total 07 100.0 Source: Census and Social Survey, Sep- Oct 2019.

46. Among those who had borrowed from money lenders, 8 households had borrowed sums ranging above Rs. 1,00,000 and three households > 25,000 and ≤ 50,000.

Table 22: Extent of Loan taken - Money Lenders Amount Borrowed Number Percentage ≤ 10,000 > 10,000 and ≤ 25,000 2 15.38 > 25,000 and ≤ 50,000 3 23.08 > 50,000 and ≤ 1,00,000 > 1,00,000 8 61.54 Total 13 100.00 Source: Census and Social Survey, Sep-Oct 2019.

47. Thirteen households had borrowed from money lenders, of them one households for business (7.69%) and five for construction and repairing of their houses (38.46%).

Table 23: Purpose of Loan - Money Lenders Borrower Number Percentage Agriculture Business investment 1 7.69 House Construction / Repair 5 38.46 Others 7 53.85 Total 13 100.00 Source: Census and Social Survey, Sep- Oct 2019. 17

5. Health and Sanitation

48. Four households surveyed on the project road reported of having taken treatment, of them 2 from government hospitals and two households form private hospitals for ailments for the past one year.

Table 24: Place of Treatment Place of treatment Number Percentage Government Hospital 2 50.00 Private Clinic 2 50.00 Traditional healing 0 0 Medical shop 0 0 Treatment not taken 0 0 Total 4 100.00 Source: Census and Social Survey, Sep- Oct 2019

49. Most of the DHs (90.16%) reported that they were aware of HIV/AIDS and 9.84% (6 HHs) reporting not being aware of HIV/AIDS.

Table 25: Awareness to HIV/AIDS Awareness Number Percentage Aware 55 90.16 Not aware 06 9.84 Total 61 100.00 Source: Census and Social Survey, Sep- Oct 2019. 50. Among those who were aware of HIV/AIDS, 90.16% reported that they are aware on how it spreads and 90.16% had knowledge about its prevention methods.

Table 26: Level of HIV/AIDS Awareness Number Percentage Awareness to mode of 55 HIV AIDS spread 90.16 Awareness to prevention 55 methods 90.16 Source: Census and Social Survey, Sep- Oct 2019.

51. 81.82% percent of DPs reported that the source of information about HIV/AIDs was television broadcasting. 7.27% of them theough print media and 3.64% each through campaign by the Government and NGO.

Table 27: Source of HIV/AIDS Information Source Number Percentage Print Media 4 7.27 Radio 0 0.00 Television 45 81.82 Govt Campaign 2 3.64 NGO Campaign 2 3.64 18

Source Number Percentage Not disclosed 2 3.64 Total 55 100.00 Source: Census and Social Survey, Sep- Oct 2019.

52. Regarding child delivery, 68.85% reported that the last delivery of child in their household took place in Government Hospital and 11.48% in Private Hospital.

Table 28: Child Delivery Number Percentage Government Hospital 42 68.85 Private Hospital 07 11.48 Midwife at Home Village elder at Home No response 12 19.67 Total 61 100.00 Source: Census and Social Survey, Sep- Oct 2019.

6. Impact to Vulnerable HH

53. The vulnerability amongst the significantly impacted DHs account for 29 households. Among the vulnerable none was women headed households, three disabled persons in the household (10.34%) and 19 scheduled caste household (65.52%), 03 of them are below poverty line and four for them were ederly persons. All BPL families were included as vulnerable category and presented in the RP. However, the number of vulnerable households would be finalized during award enquiry and explained in Para no. 27. The vulnerable status of significantly impacted DHs in the project, which is mutually exclusive in the order of priority as presented in Table 29. The actual number shall be finalized during the Award Enquiry. The status of being landless will be confirmed through Village Administrative Officer (VAO) during Award Enquiry and the table revised accordingly.

Table 29: Vulnerable (mutually exclusive) Vulnerability Type Number of HH impacted Percentage Women Headed Household 0 0.00 Scheduled Caste 19 65.52 Scheduled tribes 0 0.00 Below poverty line 3 10.34 Disabled persons in the 3 10.34 Household Elderly 4 13.79 Minor Children with no 0 0.00 support (below 14 years) Total Vulnerable 29 100.00 Source: Census and Social Survey, Sep- Oct 2019.

E. Key Socio-economic Indicators

54. The key socio-economic indicators established based on the census and socioeconomic survey carried out amongst the AHs in September to October 2019 are presented below. These 19 indicators would form the baseline indicators that would be compared with the evaluation carried out by the independent external evaluation agency.

Table 30: Key Socio-economic Indicators S.No Indicator Unit Value/Figure a) Income (N =61) 1 Monthly family income (Rs) Average 10591 2 Number of earners Average 1.70 b) Business establishment Significant Impact Nos. 23 b) Housing/Shop Characteristics (N=61) 4 Permanent % 36.10 5 Semi-permanent % 21.26 6 Temporary % 25.80 c) Standard of Living 7 Owned % 39.34 8 Squatter % 60.66 9 Having separate kitchen % 88.20 10 Having separate toilet % 86.34 11 Having separate bath % 85.71 12 Houses electrified % 94.41 13 Access to piped water supply (HSC/PT) % 69.57 14 LPG as fuel for cooking % 90.68 c) Family Characteristics

15 Family size Average 3.98 16 Women headed household % 0 Source: Census and Social Survey, Sep- Oct 2019.

F. Resettlement Preferences 52. The DHs were asked to indicate their choice in resettlement and Rehabilitation option of self-managed - cash assistance or project supported housing/livelihood assistance. The majority 65.57% preferred cash assistance, followed by 27.87% being undecided. 17 PAPs did not decide to where to relocate.

Table 31: Resettlement Preferences Preference Number Percentage Self-managed - Cash assistance 40 65.57 Project assisted - House / shop 04 6.56 Undecided 17 27.87 Total 61 100.00 Source: Census and Social Survey, Sep- Oct 2019.

Table 32: Project Assisted House/Shop - Location Preferences Preference Number Percentage Same settlement 04 100.0 20

Any where 0 0 Undecided 0 0 Total 04 100 Source: Census and Social Survey, Sep- Oct 2019.

53. All 04 households did opt for house/shop wanted to reside in the same settlement.

G. Profile of Women Headed Household (WHH)

54. The Project do not impact on WHHs.

21

IV. CONSULTATION, PARTICIPATION AND DISCLOSURE

A. Consultation in the Project 55. In order to engage with the community and enhance public understanding about the Project and address the concerns and issues pertaining to compensation, Rehabilitation and resettlement, individual interviews, focus group discussions (FGD) and meetings were undertaken amongst the various sections of Affected Persons (APs) and other stakeholders. These consultations were undertaken during the census and socio-economic survey that was carried out as part of the detailed project report (DPR) for the Project. The opinions of the APs, stakeholders and their perceptions were obtained during these consultations. The consultations with the APs and other stakeholders will continue throughout the RP implementation period.

B. Methods of Consultation

56. Consultations and discussions were held during the census and socio-economic survey with project affected persons (APs), project beneficiaries, officials of the Highways Department, the implementing agency, the officials of the Revenue Department and the elected members of the local self-government.

57. During the census and socio-economic survey consultations were held with affected households, commercial establishment owners along the Project road, officials of the district administration and elected members of the local Panchayat. In order to hear and address the concerns of women, women were encouraged to participate and express their concern during consultations. The consultation methods are detailed in the following table.

Table 33: Consultation Methods Stakeholders Consultation Method Affected Persons Census and Socio-economic Survey Affected Persons Focus Group Discussions Local Communities Focus Group Discussions Local Body Elected Members Individual interview, discussion Highways and Revenue Department Officials Individual meeting/interview, discussion APs and General Public Consultation Meetings

58. During the census and socio economic survey, 2public meetings and 2 FGDs were conducted in Kondur, Kollumangudi, Thuriapadi and Kottapattu villages in the project road, giving priority to settlements and sections where impacts to private assets and property are most significant. Consultations addressed all relevant aspects of the proposed road design, details of the private and public land required and impact to private property. Consultation meetings were attended by the affected persons, owners of commercial establishment along the subproject road, officials of the district administration and elected members of the local panchayat.

Table 34: Place of Consultation and Number of Participants Number of SNo Place Date participants 1 Kondur 12.02.2016 60 2 Semakottai 12.02.2016 139 3 Thruraipadi 23.08.2019 14 22

4 Kottakuppam 23.08.2019 17

Details of NTH Award Enquiry

No. of participants S.No Place Date Male Female Total Govt High School- 1 Semakottai 29.07.2020 44 18 62 2 PDO Office- Annagramam 10.08.2020 41 32 73 Govt High School- 3 Semakottai 21.08.2020 55 49 104 Govt Primary School- 4 Madapattu 24.09.2020 60 45 105

C. Outcome of the Consultations

59. People were aware about the improvements proposed for the road Projects but were not aware about specific details of the PRoW, shift in centreline and the method of valuation for land and building, payment of compensation and other Rehabilitation and resettlement measures. The salient points of the consultations are summarised in the following Table 38. Dissemination of Entitlement matrix through printed material in the vernacular language (Tamil) were distributed to all PAFs and clarifications regarding their doubts were also explained by LARRIC. Signed attendance are being prepared and samples are attached in the RP as Appendix 2.

Table 35: Summary of Consultation Outcome

Design change / Mitigation measures proposed / Concern Explanation Wherever bypasses are inevitable, roads would be Would bypasses be planned crossing planned in the agricultural lands after providing agricultural lands appropriate compensation to the land owner Whole building has been measured to calculate the Why the whole structure was measured, extent of affected portions. If the whole building is would you acquire whole house for the affected, full length and breadth of the building is project? measured. Whether only numbered assets would be affected? Yes Compensation will be given the body/Committee. School buildings and other Government What would you do for the CPRs structures will be reconstructed How will we know the affected portion of the Revenue/Highways/RP implementation agency would structure? inform the PAPs Can we start constructing buildings in our land Need to confirm the officials whether the land is getting near project area affected by the project Facilities like bus shelters, rest rooms, pavements, What are all the facilities provided through drains etc would be provided. Officers such as this project and to whom should we Divisional engineers, DROs could be approached for approach? grievances. For any grievances, would you give us toll Not planned for toll free number, grievance free contact number petitions can be sent to the respective officers 23

Design change / Mitigation measures proposed / Concern Explanation Whether the project be stopped if government changes No, project will be continued Compensation will be informed during resettlement What would be compensation for the tenants implementation What would be the width of the road from the 8 meters in the built up area and 11.5 meter in rural centre line? area Appropriate compensation will be given by valuing with Where will we go if our house is affected? the current schedule of rate without depreciation. Whether the compensation be sufficient for our affected structures? Yes. What will you do for the electric post, overhead Posts and water tanks will be replaced in appropriate water tanks etc locations. Mr.Srinisvasan, of Keelkavrapattu asked whether electric line and drainage pipe in the All utilities like waterline, EB line, lamp post etc., will existing road will be demolished due to this be shifted appropriately without hindering regular widening development supply Public asked when this project work will be started. Project will be started immediately after LA and R&R compled Public have expressed that there are frequent accidents occur in the existing road; Proper sign boards and safety features like speed limit hence widening of road with speed control signs and major hurdles like sharp curves would be would help reducing accidents. realigned Public asked whether accident prone area in sharp curves having poor visibility. Whether Poor geometry location and accident prone area are curves are improved or not identified and improved to the standards to avoid accident and achieve design speed also. Once the alignment finalization. Land acquisition Public expressed that how can they find process will start based on final alignment. Notification whether their building or land is falling within will be published for affected lands as per land the widening boundary. acquisition act.

D. Information Dissemination During Census & Socio -economic Survey Revalidation 60. In Cuddalore to Manappattu road (SH 09), census survey was started in May 2019 by LARRIC. The officers of field implementation unit and LARR unit were attended the revalidation activity. The PAPs were briefed about the project, entitlement matrix, tentative timeline of project implementation etc., during census revalidation. All the assets (buildings/structures) falling within the proposed ROW based on the final design were numbered in blue colour. The snapshots of the activity are shown below.

24

Award Enquiry and Group Discussions

25

E. Plan for further Consultation in the Project

61. The extent and level of involvement of stakeholders at various stages of the project from design stage and through the RP implementation will open up the line of communication between the various stakeholders and the project implementing authorities, thereby aiding the process of resolving conflicts at the early stages of the project rather than letting it escalate into conflicts resulting in implementation delays and cost overrun. Participation of the local community in decision-making will help mitigate adverse impacts.

62. Further, successful implementation of the RP is directly related to the degree of involvement of those affected by the Project road. Consultations with DPs will be conducted regularly during the RP implementation. The Land Acquisition, Rehabilitation and Resettlement Unit (LARRU), the jurisdictional DE (H), and the RP implementing support LARRIC will be responsible for conducting these consultations. The proposed consultation plan will include the following. i) In case of any change in the project design, the DPs and other stakeholders will be consulted regarding the factors that necessitate the change, efforts taken to minimize resettlement impacts and mitigation measures available. ii) The LARRU, with the assistance of the LARRIC, will carry out information dissemination sessions in the project area. iii) During the implementation of the RP, the LARRIC will organize public meetings, and will appraise the communities about the schedule/progress in the RP and civil works implementation, including awareness regarding road safety and HIV AIDS prevention. iv) Consultations and focus group discussions will be conducted with vulnerable groups like women headed households, ST and SC to ensure that the vulnerable groups understand the process and that their needs are specifically taken into consideration.

63. A Public Consultation and Disclosure Plan will be finalised by the PIU in consultation with the Project LARRU as per the tentative schedule given in the following table.

26

Table 36: Public Consultation and Disclosure Plan

Activity Task Period Agencies Remarks Screening of Project Identifying built-up September DPR and stakeholder sections and assessment Completed 2015 Consultants Identification of likely impact Identifying DPs and collected socioeconomic Census and information on DP’s. DPR Socioeconomic Carrying out consultations September2015 Completed Consultants survey to capture issues and concerns of people and incorporate in the design. Revalidation of Revalidation of Census Census and and Socio-economic May - LARRU/LARRIC Completed Socioeconomic survey and updating RP November 2019 survey Publish list of affected Public Notification for As per lands/sites in a local December 2019 LARRU LA State Act newspaper Web disclosure RP posted on Highways November 2020 PIU / ADB oftheRP and ADB website Carryout consultations with DPs on significance After RP is RP disclosure LARRU / of impact, entitlement, December 2020 approved meetings LARRIC implementation by PIU arrangement and GRC Project commencement Project information Jurisdictional DE details and scheduling of December 2020 Dissemination / LARRIC civil works Throughout RP implementation and formal Consultation with Throughout RP LARRU / consultation meetings to DPs implementation LARRIC be held at least once in every quarter Internal and external monitoring reports will be Dissemination of uploaded in the website of Throughout RP PIU monitoring reports Highways along with implementation corrective actions taken, if any. Summary of complaints Dissemination of GRC received and action taken Throughout RP PIU actions will be uploaded in the implementation website of Highways

F. Disclosure 64. The RP will be disclosed by the PIU and ADB upon its review and approval, and uploaded in the CKICP website along with a summary version with the entitlement matrix translated in local language. The translated summary of the EM would provide details of the eligibility and entitlement, institutional arrangement and grievance redressal process. Hardcopies of the EM summary in and distributed to all the PAPs and same is available at the office of the PIU, jurisdictional DE, LARRU and distributed to the DPs by the LARRIC. PAPs were 27 explained about the compensation during house visits by LARRIC staff and in the public disclosure and award enquiry meetings.

65. Information will be disseminated to DPs at various stages. Information including magnitude of loss, detailed asset valuations, entitlements and special provisions, grievance procedures, timing of payments, displacement schedule, civil works schedule will be disclosed by the LARRU with assistance from the LARRIC hired for assisting in RP implementation and this will be done through public consultation. Entitlement booklets have been issued to PAFs and other stakeholders of the project, hence, accessing to booklet becomes much easier.

66. Hard copies of the full resettlement plan will also be made available at: (i) the offices of the LARRU; (ii) office of the District Collectors; (iii) Taluk Offices; and (iv) Offices of the Panchayat / Union / Municipality / Corporation, as soon as the plans are available.

67. Electronic version of the RP will be placed on the official website of the project. In addition, all safeguard documents including the list of eligible DPs will be made available in the website throughout the life of the project. 28

V. POLICY AND LEGAL FRAMEWORK

A. Background

68. The Chennai Kanyakumari Industrial Corridor Project (CKICP) has prepared an Entitlement Matrix (EM) to mitigate the involuntary resettlement impacts that can arise in this project and is line with the EM of the Second Tamil Nadu Road Sector Project (TNRSP-II) which is currently being implemented. The EM complies with the provisions of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR), State Laws and Policies and the ADB Safeguards Policy Statement, 2009 (SPS)).

B. National Legislations, Policies and ADB Policy

69. The entitlements for the Chennai Kanyakumari Industrial Corridor Project (CKICP) is based on national law: The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, State laws and regulations and the ADB’s Safeguard Policy Statement (SPS), 2009.

70. The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (RFCTLARR) Act, 2013, provides for a transparent process and just and fair compensation to the affected families whose land is acquired or proposed to be acquired or are affected by such acquisition and provides for Rehabilitation and resettlement assistance of the affected families. The basic principle of the RFCTLARR Act is to ensure that the cumulative outcome of compulsory land acquisition should be such that, the affected persons become partners in development, leading to an improvement in the standard of living after acquisition. This act came into effect on January 01, 2014 and the Land Acquisition Act, 1894 stands repealed.

71. The Land Acquisition Officer while determining the market value of the land has to consider the higher value of the land arrived at by 3-methods of valuation viz: (i) market value as per Indian Stamp Act, 1899 for the registration of sale deed or agreements to sell, in the area where land is situated; or (ii) average sale price for similar type of land, situated in the nearest village or nearest vicinity area, ascertained from the highest 50% of sale deeds of the preceding 3 years; or (iii) consented amount paid for PPPs or private companies. In case of rural areas, the market value of land so determined is multiplied by a factor, as per the GO Ms No. 300 of Revenue and Disaster Management (LA-I1(1)) dated 21.09.2017. A solatium of 100% is payable on the market value of land multiplied by the factor and all immovable properties or assets, trees and plants.

Relevance: In this project, land will be acquired invoking the Tamil Nadu Highways Act, 2001 and compensation, rehabilitation and resettlement will be determined in accordance with the provisions of the Right to Fair Compensation and Transparency in

Land Acquisition, Rehabilitation and Resettlement Act, 2013 (RFCTLARR). To enable use of TN Highways Act, Sec 105A was inserted in the RFCTLARR Act through an amendment.

72. A Resettlement and Rehabilitation award detailing the entitlements to be provided as per the Second Schedule of Act is passed by the Land Acquisition Officer after getting approval from the Project Director. Possession of land can be taken only after payment of compensation and 29

Rehabilitation and resettlement entitlements as detailed in Second Schedule. The details of amenities to be provided in a resettlement site is detailed in the Third Schedule. C. Legal and Policy Frameworks of Tamil Nadu

73. The legislations and policy concerning the land acquisition and resettlement for road project includes (i) Tamil Nadu Highways Act, 2001 and (ii) The Tamil Nadu Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Rules, 2017 (iii) GO Ms No. 300 of Revenue and Disaster Management (LA-I(1)) dated 21.09.2017. The factor by which the market value of land shall be multiplied in case the project is situated in rural areas in accordance with Section 26(2) of RFCTLARR Act read with the provisions contained in Serial Number 2 of the First Schedule of RFCTLARR Act has been notified vide this government order. The multiplication factor of 1.25 for projects that are within 30km from the urban area, a factor of 1.5 for projects beyond 30km and within 50km and a factor of 2.0 for projects beyond 50km.

D. ADB’s Safeguard Policy Statement (SPS), 2009

74. The ADB’s Safeguard Policy Statement (SPS) 2009 describes the policy objective, its scope and triggers and principles of (i) environmental safeguards; (ii) involuntary resettlement safeguards; and (iii) indigenous people’s safeguards. The objectives of involuntary resettlement safeguards are: (i) avoid involuntary resettlement where possible; (ii) if avoidance is not possible, minimize involuntary resettlement by exploring project and design alternatives; (iii) enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and (iv) improve the standards of living of the displaced poor and other vulnerable groups.

75. The involuntary resettlement safeguards policy covers physical displacement (relocation, loss of residential land, or loss of shelter) and economic displacement (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of; (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary.

76. The three important elements of involuntary resettlement safeguards are: (i) compensation at replacement cost for lost assets, livelihood, and income prior to displacement; (ii) assistance for relocation, including provision of relocation sites with appropriate facilities and services; and (iii) assistance for Rehabilitation to enhance, or at least restore, the livelihoods of all displaced persons relative to pre-project levels and to improve the standard of living of displaced poor and other vulnerable groups.

77. Replacement cost is defined as(i) fair market value; (ii) transaction costs; (iii) interest accrued, (iv) transitional and restoration costs; and (v) other applicable payments, if any.

E. Comparison of Government and ADB Policies

78. Overall, the new Act now bridges the gaps between the GoI policy and ADB's SPS, 2009. In particular, the Act requires social impact assessments for projects involving land acquisition, although it sets a minimum threshold of 3 years for affected non-titled holders for this provision to apply, while this is not required in the SPS. The Act also expands compensation coverage by a solatium of 100 percent of all compensation amounts. Overall, the RFCTLARR Act, 2013 brings the value of compensations for land and structures higher than replacement cost, which is the 30 principle on which compensations are calculated under SPS. The Act furthermore is in line with ADB requirement that compensation be paid prior to project taking possession of any land.

79. The outstanding differences between the government and ADB policy is the establishment of a cut-off date for compensation or entitlements to non-title holders. The RFCTLARR Act, 2013 specifies that only non-titleholders residing on any land for the preceding three years or more will be entitled for compensation and assistance as per this Act. This gap as been bridged by incorporating the cut-off date for non-titleholders will be the start date of census survey which is provided in the Resettlement Plan. Moreover, unlike SPS the new Land Act does not have special provisions for vulnerable households but only for scheduled castes and scheduled tribes. Special measures for vulnerable households have been included in this RP.

80. A significant development in Government statute is the notification of ‘The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013’, which has repealed the Land Acquisition Act of 1894 (as amended in 1984). This Act decreases significantly the gap between the LA Act 1894 and ADB’s SPS. The Act also provides for value of structures, trees, plants, or standing crops affected to be compensated at market value along with a solatium of 100 percent. The Act furthermore meets ADB requirement as Section 38(1) of RFCTLARR Act mandates payment of compensation and Rehabilitation and resettlement entitlements prior to project taking possession of the land.

F. Involuntary Resettlement Safeguard Principles for the Project (i) Based on the above analysis of the government provisions and ADB policy, the following resettlement principles have been adopted for this Project: (ii) land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative sub-project designs; (iii) where unavoidable, time-bound resettlement plans (RPs) will be prepared and APs will be assisted in improving or at least regaining their pre-program standard of living; (iv) consultation with APs on compensation, disclosure of resettlement information to APs, and participation of APs in planning and implementing sub-projects will beensured; (v) vulnerable and severely affected households will be provided special assistance; (vi) payment of compensation to APs including non-titled persons (e.g., informal dwellers/squatters, and encroachers) for acquired assets at replacement rates; (vii) payment of compensation and resettlement assistance prior to the contractor taking physical acquisition of the land and prior to the commencement of any construction activities; (viii) provision of income restoration and Rehabilitation; (ix) Establishment of appropriate grievance redressal Mechanism.

G. Valuation of land and assets 1. Compensation for Land 81. Land will be acquired in accordance with provisions of State Laws while determining the compensation for land, the Land Acquisition Officer (LAO) will be guided by the provisions of Sec 26, Sec 27, Sec 28, Sec 29 and Sec 30 of RFCTLARR Act, 2013. The compensation includes, the multiplying factor1 of 1.25-2.00 times on the land value being the higher of the guideline value

1 As per G.O.Ms. No 300 of Revenue and Disaster Management (LA-I(1)) dated 21.09.2017. 31 or average of higher 50% of sale deed rates for the preceding 3 years or any rates consented for PPP or private projects. In addition, 100% solatium will be added. This calculation meets the replacement cost requirement of SPS. The project will provide 25% of the total amount for those who accepted for negotiated purchase, in addition to the compensation as per RFCTLARR act 2013,vide G.O.(D).No.195, Highways and Minor Ports (HS2) Department, Dated: 26.11.2019.

82. Where land owners refuse to accept the compensation or where there is a dispute to the title of the property, the Spl DRO will remit such amount with the LARR authority and in all other cases, where compensation cannot be paid, the compensation amount will be kept in an interest bearing account with the project for a period of three years and paid to land owners as and when they come forward to accept the compensation.

2. Compensation for Structures 83. All affected households losing structures, regardless of legal title, will be paid compensation equivalent to the replacement cost of the structure, or in the case of titledholders, compensations based on PWD rates in the area plus 100% solatium according to the RFCTLARR Act 2013. Replacement cost is the rate determined based on the prevailing scheduled of rates, updated by a panel of competent engineers every year. If the RFCTLARR Act 2013 rates are higher than replacement cost, they will be maintained for the project. If these rates are lower than replacement cost, then replacement cost for the structure will be provided to titled-holders also. In addition, physically displaced titled and non-titled holders will receive additional resettlement and subsistence allowances. All PAPs irrespective of their title will be compensated based on the Entitlement Matrix (EM).

84. Compensation for properties belonging to the community or common places of worship will be provided to enable construction of the same at new places through the department owning it or the local self-governing bodies like Village Panchayath/Village council or the trust/body managing the places of worship, in accordance with the modalities determined by such bodies to ensure correct use of the amount of compensation. Further, all compensation and assistance will be paid to DPs at least 1 month prior to displacement or dispossession of assets.

85. Upon payment of compensation, the APs will be given 1-month time to take away the materials salvaged from their dismantled houses or shops or other building, and no charges will be levied upon them for the same. A notice to that effect will be issued intimating that APs can take away the materials so salvaged within 30 days of receipt of compensation; or otherwise, the structure would be demolished and material disposed of by the project authority without giving any further notice.

3. Compensation for Trees

86. Compensation for trees will be based on their market value. Loss of timber trees, compensation for fruit bearing trees, perennial trees, loss of crops, will be compensated at their replacement cost for titled-holders either compensated as replacement cost or as per the rates assessed by the Departments of Forest or Horticulture or Agriculture along with 100% solatium in line with the provision of RFCTLARR Act 2013, whichever is higher. For non-title holders compensation for fruit bearing trees will be paid without solatium (as per EM). The replacement cost of fruit trees will take into account the productive life of the tree. Prior to taking possession of the land or assets attached to the land, the compensation will be fully paid and APs will have the opportunity to harvest crops/trees within 1-month from the date of payment of compensation.

32

H. Updating Units of Entitlement 87. All units of entitlement and assistances will be revised by PIU, based on Consumer Price Index for Agricultural Labourers (CPIAL) and communicated to all LARRU for making payment as per the revised rates. The unit rates contained in the EM of this RP will be applicable until March 31, 2019. The updating will be done annually in the month of March and will become effective from the 1st day of April of that year. The unit rates will not be downgraded and the rate increased will be communicated to ADB.

I. Rehabilitation and Resettlement Award 88. The Spl DRO, LARRU will pass a separate Rehabilitation and Resettlement Award after getting approval from the Project Director, listing the names of displaced persons and their entitlements in accordance with approved EM for this project. The same will be displayed in prominent places such as the office of the local body concerned, office of the DE, Highways, LAARU and individual awards will be issued to the APs.

33

VI. ENTITLEMENTS, ASSISTANCE AND BENEFITS

A. Introduction

89. The project will have two types of affected persons i.e.: (i) persons with formal legal rights to land lost in its entirety or in part; and (ii) persons who have neither formal legal rights nor recognized or recognizable claims to such land. The involuntary resettlement requirements apply to both these types of affected persons.

B. Eligibility Criteria

90. In accordance with the involuntary resettlement policy principles of this project, the affected persons falling in any of the following three categories will be eligible for compensation and resettlement assistance: (i) those who have formal legal rights to land lost in its entirety or in part (title holders / pattadars); (ii) those who lost the land they occupy in its entirety or in part and have no formal legal rights to such land, but who Have claims to such lands that are recognized or recognizable under national/state laws (forest dwellers); and (iii) those who lost the land they occupy in its entirety or in part and Have neither formal legal rights nor recognized or recognizable claims to such land (non-titled holders such as squatters and encroachers).

91. Cut-off Date: For title holders, the date of preliminary notification of intended acquisition as per the provisions of State Laws will be treated as the cut-off date.

92. The cut-off date for census survey for non-titled holders was March and May 2015 and the implementation of the RP was delayed for around four years. LAARIC has undertaken a census and socio economic data on 14 April, 2019 and the cut-off date for eligibility and entitlement of non-titled holders will be the start date of the census survey by LARRIC. This updated survey will record all non-title holders affected by the project. The cut-off date for nontitle holders will be maintained as start date of the census to avoid new occupants in the EROW. Video coverage has also been done to capture all the structures and PAPs within the corridor of impact on the cut-off date.

93. There will be adequate notification and dissemination of the cut-off date and measures will be taken to prevent encroachments/squatting after the cut-off date is established. Non-title holders who settle in the affected areas after the cut-off datewill not be eligible for compensation. They however will be given sufficient advance notice (60 days) to vacate the premises and dismantle affected structures prior to project implementation. The project will recognize both licensed and non-licensed vendors, and titled and non-titled households.

C. Entitlement Matrix (i) The Entitlement Matrix (EM) for the Chennai Kanyakumari Industrial Corridor Project summarises the types of losses and the corresponding nature and scope of entitlements and is in compliance with National/State Laws, in particular the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and the Requirements II on Involuntary Resettlement of the Safeguard Policy Statement of the Asian Development Bank, 2009. The 34

entitlement matrix presents the entitlements corresponding to the tenure of the affected persons in the following order: Impact to private property (title holders) consisting of: (i) loss of private land; (ii) loss of private residential structure; (iii) loss of private commercial structure; (iv) loss of private other structures; (v) impact to tenants (residential / commercial / agricultural) of title holders; and (vi) impact to trees, standing crops, etc; (i) Impact to Non-title holders consisting of: (i) impact to squatters; and (ii) impact to encroachers; (ii) Loss of employment to agricultural and non-agricultural workers/employees; (iii) Additional assistance to vulnerable affected persons; and (iv) Unforeseen impacts

94. The following is the approved entitlement matrix for the project (the EM has been approved Vide letter No. Highways and Minor Ports (HS2) Departments, Secretariat Chennai- 9, letter (D) No. 280/HS2/2018-1 dated 13.11.2018).

Table 37:: Entitlement Matrix SNo Impact Category Entitlements Implementation Guidelines

Section I. TITLE HOLDERS - Loss of Private Property 1 Loss of Land a Compensation for land Land will be acquired upon payment (agricultural, of compensation as per the homestead, provisions of RFCTLARR Act, 2013 commercial or otherwise) Compensation rates will be,

Higher of (i) market value as per Indian Stamp Act, 1899 for the registration of sale deed or agreements to sell, in the area where land is situated; or (ii) average sale price for similar type of land, situated in the nearest village or nearest vicinity area ascertained from the highest 50% of sale deeds of the preceding 3 years; or (iii) consented amount paid for PPPs or private companies

The market value in Rural areas shall be multiplied by a factor as notified by GoTN2.

Plus 100% solatium and 12% additional market value from date of 15(2) notification to award.

2 G.O.(Ms) No.300, Revenue &Disaster Management (LA-I(1)), dated 20.09.2017. [Factor by which the market value to be multiplied based on the distance of the Project Area from Urban Areas is as follows: Within 30 Kilometres - by 1.25, Beyond 30 Kilometres and within 50 Kilometres - by 1.50 and Beyond 50 Kilometres - by 2.00] 35

Title holders whose land is severed, will have the option of surrendering the severed portion of the remaining unviable land3 b Agricultural landowners Any affected family4 whose livelihood whose primary source of is primarily dependent (loses one livelihood is lost due to the third of the annual family income due land acquired will be to the acquisition of the said entitled for Rs.5,00,000 as agricultural land) on the agricultural onetime payment in lieu of land acquired alone will be treated annuity policy as livelihood lost, will be entitled for Rs. 5,00,000/- as onetime payment in lieu of annuity policy

Registered tenants in private land, registered tenant cultivators in HR&CE land and registered Bhoodan Land occupiers, who loses 1/3rd of annual family income due to the acquisition of the said agricultural land will also be eligible to receive this entitlement, provided they had submitted a self- sworn affidavit that they have been tenants for 3-years prior to the date of notification.

2 Loss of residential In addition to Replacement cost is the rate structure Compensation for land and determined based on the prevailing Assistances listed above schedule of rates updated by the under S.No.1 panel of competent engineers every a year. Cash compensation at replacement cost with In case of partly affected house,

100% solatium. manufactory or other building, as per Section 94 (1), the whole structure may be acquired, if the owner so desires

The affected person has the option of surrendering the full house or the building when the impact is partial. In the event of the affected person not wanting to surrender the remaining portion of the building, she/he may be asked to provide her/his decision inwriting to the jurisdictional Special DRO. In the event the person has opted to surrender the full house or the building, when the impact is partial, the whole building has to be demolished by the affected person without fail, failing which, the whole building will be demolished by the

3 Inserted vide amendment GO (D) No.174 of Highways and Minor Ports (HN2) Department dated 25.07.2017 4 Family is defined as per section 3(m) of RFCTLARR Act 2013. 36

department at the risk and cost of the affected person5.

b Right to salvage affected materials without cost

c One-time assistance of Rs.25,000 for each affected family of an artisan or self-employed and who has to relocate.

d An alternative house as Stamp duty and registration charges per IAY specifications in will be borne by the project in case rural areas and a of new houses or sites. constructed house/flat of minimum 50 sq.m. in Patta will be issued in the name of urban areas or cash in lieu the wife/women7 of the household of house if opted (the cash in lieu of house will be Rs.1,20,000/-6 in line with GoI IAY standards in rural areas and Rs.1,50,000 in case of urban areas), for those who have to relocate. e One time transitional / subsistence allowance of Rs.36,000 for affected households who require to relocate due to the project

f Shifting assistance of Rs.50,000 for those who have to relocate g One-time Resettlement Allowance of Rs.50,000 for those who have to relocate h Residential structure Any affected family whose livelihood owners, who are deriving is primarily dependent (loses rental income from the onethird of the annual family income affected structure in the due to the acquisitionof the said land acquired and whose residential structure) on the rental livelihood is lost will be income from the acquired residential entitled for Rs. 5,00,000/- building will be treated as livelihood as onetime payment in lieu lost, will be entitled for Rs. 5,00,000/- of annuity policy as onetime payment in lieu of annuity policy

5 Inserted vide amendment GO (D) No.174 of Highways and Minor Ports (HN2) Department dated 25.07.2017 6 Revised in accordance with GoI revised norms for PMAY-G (restructured IAY) vide GoTN amendment GO (D) No.174 ofHighways and Minor Ports (HN2) Department dated 25.07.2017 7 In accordance with GO Ms.No.1763 of Revenue Department dated 19.11.1987 37

3 Loss of In addition to Replacement cost is the rate Commercial Compensation for land and determined based on the prevailing structure Assistances listed above schedule of rates updated by the under S.No.1 panel of competent engineers every a year

Cash Compensation at replacement cost with In case of partly affected house,

100% solatium. manufactory or other building, as per

Section 94 (1), the whole structure may be acquired, if the owner so desires

The affected person has the option of surrendering the full house or the building when the impact is partial. In the event of the affected person not wanting to surrender the remaining portion of the building, she/he may be asked to provide her/his decision inwriting to the jurisdictional Special DRO. In the event the person has opted to surrender the full house or the building, when the impact is partial, the whole building has to be demolished by the affected person without fail, failing which, the whole building will be demolished by the department at the risk and cost of the affected person8.

b Right to salvage affected materials without cost c One-time grant of If the business owner is different Rs.25,000 for loss of from the structure owner, the trade/self-employment for onetime grant for loss of the business owner trade/selfemployment, will be paid to the business owner. d One-time transitional livelihood and subsistence allowance of Rs.36,000 for affected households who require to relocate due to the project

e Shifting assistance of Rs.50,000 for those who have to relocate

8 Inserted vide amendment GO (D) No.174 of Highways and Minor Ports (HN2) Department dated 25.07.2017 38

f One-time Resettlement Allowance of Rs.50,000 for those who have to relocate g Commercial structure Any affected family, whose livelihood owners, who are deriving is primarily dependent (loses onethird business income and/or of the annual family income due to rental income from the loss of business operation carried out affected structure on the from the acquired commercial land acquired, and whose structure) on the business income primary source of derived from the acquired livelihood is lost due to the commercial structure will be treated land acquired will be as livelihood lost. entitled for Rs.5,00,000/- as onetime payment in lieu Any affected family, whose livelihood of annuity policy. is primarily dependent (loses onethird of the annual family income due to loss of the acquired commercial structure) on the rental income derived from the acquired commercial structure will be treated as livelihood lost.

4 Loss of other a Cash Compensation for Replacement cost is the rate structure the structure at determined based on the prevailing replacement cost with schedule of rates updated by the 100% solatium. panel of competent engineers every year

b One-time assistance of Rs.25,000 to all households who lose cattle shed

c Right to salvage material without cost 5 Impact to tenants 5.1 a Residential (residential / 1-month notice to vacate commercial the rental premises /agricultural) b Rental allowance at Rs.3,000 per month in rural areas and Rs.4,000 per month in urban areas, for six months c Shifting assistance of Rs.10,000 5.2 a Commercial 1-month notice to vacate the rental premises 39

b Rental allowance at Rs.4,000 per month in rural areas and Rs.6,000 per month in urban areas, for six months

c Shifting assistance of Rs.10,000 d Commercial tenants will receive the one-time grant of Rs.25,000 for loss of trade/self-employment provided under 3(c) above in lieu to the owner

5.3 a Agricultural Tenants In case of agricultural tenants advance notice to harvest crops or compensation for lost crop at market value of the yield determined by the Agricultural Department

6 Impact to trees, a Three months (90 days) standing crops, advance notification for the other properties, harvesting of standing perennial and non- crops (or) lump sum equal perennial crops: to the market value of the yield of the standing crop

lost determined by the Agricultural Department

b Compensation for trees based on timber value at market price to be determined by the Forest Department for timber trees and for other trees (perennial and fruit trees) by the Agriculture/ Horticultural Department, which includes value of productive life of fruit trees, with 100% solatium

c Loss of other properties such as irrigation wells will be compensated at replacement cost with 100% solatium. Section II. Additional Assistance for Women (Title and Nontitle holders) 40

7 Loss of Land / a Reimbursement of stamp The property should be purchased in house / shop duty and registration the name of a women in the charges, for purchase of household and registered either in property out of the her name or jointly with one or more compensation/R&R member of the household. The assistance. registration shall be done within

3years from LA award/R&R award.

Section III. NON TITLE HOLDERS - Impact to squatters / Encroachers

8 Impact to 8.1 a Loss of House Replacement cost is the rate Squatters Compensation at determined based on the prevailing replacement cost. schedule of rates updated by the panel of competent engineers every year. b Right to salvage the affected materials without cost c House construction grant of Rs.70,000 for all those who have to relocate and who do not have another house.

Additional house site grant of Rs.50,000 to those who do not have a house site, d One-time subsistence allowance of Rs.18,000 e Shifting assistance of Rs.10,000 8.2 a Loss of shop Replacement cost is the rate Compensation at determined based on the prevailing replacement cost schedule of rates updated by the panel of competent engineers every year b Right to salvage the affected materials without cost c One-time rehabilitation grant of Rs.20,000 for reconstruction of affected shop d One-time subsistence allowance of Rs.18,000 for loss of business income e Shifting assistance of Rs.10,000 41

8.3 Loss of Kiosk One-time rehabilitation grant of Rs.18,000 for Kiosks affected significantly and having to relocate 8.4 Loss of other structure Replacement cost is the rate a Compensation at determined based on the prevailing replacement cost schedule of rates updated by the panel of competent engineers every b Right to salvage material year without cost 8.5 a Cultivation 2-month notice to harvest standing crops or market value of compensation for standing crops b Fruit bearing trees Market value of compensation for fruit bearing trees 9 Impact to 9.1 a Cultivation Replacement cost for the loss of Encroachers 2-month notice to harvest standing crops will be decided by the standing crops or market Spl. DRO in consultation with the value of compensation for Agriculture or Horticulture standing crops, if notice is Department. not given.

b Fruit bearing trees Market value of compensation for fruit bearing trees 9.2 a Structure 1-month notice to demolish the encroached structure b Compensation at Replacement cost is the rate replacement cost for the determined based on the prevailing affected portion of the schedule of rates updated by the structure panel of competent engineers every year. c Right to salvage material without cost Section IV. Loss of other Livelihood Opportunities 10 Loss of a Subsistence allowance Only agricultural or non-agricultural employment in equivalent to minimum labourers who are in fulltime / agricultural or non- agricultural wages for 3 permanent employment of the agricultural months landowner, or full-time employees of activities or other the affected business, will be eligible wage workers for this assistance. Seasonal agricultural labourers will not be entitled for this assistance.

Section V. Impact to Vulnerable affected Persons 42

SNo Impact Category Entitlements Implementation Guidelines

11 Vulnerable a Training for skill One adult member of the vulnerable Households9 development to one households whose livelihood is member of each vulnerable affected, will be entitled for skill households. development.

This assistance includes The LARRU with support from the cost of training and LARRIC will identify the number of

financial assistance for eligible vulnerable persons based on

travel/conveyance and the 100% census of the displaced food. persons and will conduct training

b One-time assistance of need assessment in consultations Rs.8,000 for physically with the displaced persons so as to displaced residential and develop appropriate training economically programmes suitable to the skill and displacedcommercial the region. vulnerable households. Suitable trainers or local resources c Displaced Vulnerable will be identified by LARRU and households will be linked to LARRIC in consultation with local the government welfare training institutes. schemes, if found eligible and not having availed the scheme benefit till date.

Section VI. Unforeseen Impacts Unforeseen impacts encountered during implementation will be addressed in accordance with the principles of RFCTLARR Act and ADB’s Safeguards Policy Statement.

Foot Note: The replacement cost principles are confirmed to be achieved by implementing the RFCTLARR Act 2013. In addition to the compensation as per PFCTLARR Act 2013, CKICP will provide 25% of the total amount for those who accepted for negotiated purchase.

95. Compensation for land and structure, in accordance with the eligibility and entitlement, will be paid prior to physical and economic displacement. One-time rehabilitation assistances and shifting assistances paid as cash will also be disbursed prior to physical and economic displacement. However, any long-term rehabilitation measures like training for skill development and annuity for life, if any, will continue for a longer period and such rehabilitation measures will not be a bar to commence civil works.

9 Vulnerable Group includes but is not limited to the following categories; (i) DPs falling under Below Poverty Line (BPL), (ii) landless people (iii) persons who belongs to Scheduled Caste (SC) and Scheduled Tribes (ST), (iv) women headed households (v), children (PAPs upto 14 years have been considered as children) and elderly people (PAP over 60 years of age have ben considered as elderly people in the project (viii) including orphans and destitute and Physically and mentally challenged /disabled people. 43

VII. RELOCATION OF HOUSING AND SETTLEMENTS

A. Physically displaced households

96. Among all the surveyed 748, affected households, 38 will require physical relocation as their residential structure will no longer be viable. As per the census survey, all the PAPs have opted for cash compensation. All the displaced families will get one-month time to relocate to a new location on receipt of total compensation. Time extension for relocation can also be granted on a case to case based on the situation. RP will be updated on completion of ‘Award Enquiry’ as per land acquisition procedure.

B. Physical Relocation Allowances Provided by the Project

97. addition to the replacement cost of structure, any affected household who is physically displaced from his/her residence structure as a result of the project will receive the following relocation allowances. Landless residential squatters will get house site grant (for purchasing house site). All residential squatters will be validated by the respective Village Administrative Office. All residential squatters are eligible for house construction grant as per Entitlement Matrix.

Table 38. Relocation assistance for physically displaced (in addition to replacement cost for structure)

Titled-holders No. Non-titled holders No.HH HH

● An alternative house as per IAY 19 ● House construction grant 19 specifications in rural areas and a constructed of Rs.70,000 for all those who house/flat of minimum 50 sq.m. in urban areas have to relocate and who do not or cash in lieu of house if opted (the cash in lieu have another house. of house will be Rs.1,20,000/-10 in line with GoI IAY standards in rural areas and Rs.1,50,000 in ● Additional house site grant case of urban areas), for those who have to of Rs.50,000 to those who do not relocate. have a house site,

● Subsistence grant of Rs. 36,000 for 19 ● Subsistence grant of Rs. 19 titledholders 18,000 for non-titled holders

● Rs. 50,000 Resettlement grant 19 ● N/A ● Rs.50,000 Shifting assistance 19 ● Shifting assistance of 19 Rs.10,000

C. Relocation Strategy 98. The residential displaced titleholder households are entitled for a built houses or cash in lieu of house in addition to compensation at replacement cost and other R&R assistances.

10 Revised in accordance with GoI revised norms for PMAY-G (restructured IAY) vide GoTN amendment GO (D) No.174 of Highways and Minor Ports (HN2) Department dated 25.07.2017 44

D. Physical Relocation Allowances Provided by the Project

99. As part of the implementation activity, the LARRU with the help of the RP implementation support LARRIC will consult each and every DPs to obtain their choice based on the options available to them. If any of the displaced family finds difficulty in self resettlement, LARRIC shall facilitate those PAPs to resettle in coordination with LARRU, including provision of individual house sites. This project does not expect development of resettlement sites for residential displaced households.

45

VIII. INCOME RESTORATION AND REHABILITATION A. Loss of Livelihood in this project

100. The project road will cause the loss of livelihood of 117 households, Details are summarized in below table.

Table 39: Loss of Livelihood Type of livelihood impact (Sub title – Loss of Structures) No. HH No. HH losing commercial structures or rent from commercial structures 23 No. HH losing commercial cum residential structures 2 No. tenants losing rented commercial structures 9 No. employees of affected commercial structures 00 No. of titled-holders losing agricultural land 83 Total 117

B. Entitlements for Loss of Livelihood

101. This resettlement plan includes measures to improve or at least restore income and livelihood of affected persons to pre-project levels. The entitlement matrix includes the following measures for the temporary or permanent loss of livelihood:

Table 40: Entitlement for Loss of Livelihood Category of Impact Number Provisions of APs Agricultural landowners whose 10* Rs.5,00,000 as onetime payment in lieu of primary source of livelihood is lost annuity policy due to the land acquired (Reduction in income) Titleholder: losing commercial 6 Rs.5,00,000 as onetime payment in lieu of structures or rent from commercial annuity policy structures One-time grant of Rs.25,000 for loss of trade/self-employment for the business owner One-time transitional livelihood and subsistence allowance of Rs.36,000 for affected households who require to relocate due to the project Shifting assistance of Rs.50,000 for those who have to relocate One-time Resettlement Allowance of Rs.50,000 for those who have to relocate Squatter: loss of commercial 17 One-time subsistence allowance of Building Rs.18,000 for loss of business income Shifting assistance of Rs.10,000 46

One-time rehabilitation grant of Rs.20,000 for reconstruction of affected shop Tenants: Loss of business 09 Rental allowance at Rs.4,000 per month in rural areas and Rs.6,000 per month in Category of Impact Number Provisions of APs urban areas, for six months

Shifting assistance of Rs.10,000

one time grant of Rs.25,000 for loss of trade/self-employment Employees: Loss of Income 0 Subsistence allowance equivalent to minimum agricultural wages for 3 months Number will be confirmed after award enquiry. 102. Effort will be made by the LARRU with the support of the LARRIC to assist the DP in their effort to restore their income. If the DP so desires, the R&R assistances can be utilised to deliver suitable income restoration activities in order to leverage on the existing skills of the DP.

C. Special Measures to Support Vulnerable Groups

(i) As per the Census Survey 29 vulnerable households are affected by the Project road. (ii) The following special assistance measures will be provided to physically displaced vulnerable households: (iii) 29 HH will be eligible to participate to the income improvement program (see description below). All vulnerable HHs based on footnote 8 of the Entitlement Matrix shall be assessed. All vulnerable HHs are getting assistance from various ongoing government schemes (Attached as Appendix. 7). The project has provided additional assistance of Rs.8000/- and training assistance to significantly affected HHs.

D. Income Restoration Measures 103. The entitlement proposed under this project (CKICP) has adequate provisions for restoration of livelihood of the affected persons. Wherever feasible and if the DP so desires, income restoration schemes will be identified and implemented by the LARRU with the assistance of the implementing LARRIC.

104. Towards this the DP will be guided and assisted by the LARRU with the support of the LARRIC, in effectively using the compensation and R&R assistances towards establishing an income generating activity and re-establishing the shop/kiosk or utilising the amount for buying land or taking land on lease. The compensation for land and assets and the R&R assistances arrived at in accordance with the provisions of the RFCTLARR Act are adequate to restore the income levels. Further, the subsistence allowance and cash in lieu of annuity policy are aimed at providing long term support to the affected households and will ensure that the income levels are restored. Further, efforts will be made to provide employment to the DPs during the 47 construction phase by facilitating their engagement by the civil works contractor. The LARRU in consultation with the jurisdictional DE, should ensure that local people and in particular the willing DPs are engaged by the contractor in suitable civil work as stipulated in the contract.

105. Further, the LARRU with the assistance of the implementing LARRIC will make the training need assessment and will impart training to the eligible DPs, in particular to the vulnerable DPs, for income restoration and skill up-gradation as necessary. 48

IX. RESETTLEMENT BUDGET AND FINANCING PLAN

A. Introduction 106. The resettlement cost estimate for the project include compensation for private land determined in accordance with RFCTLARR Act and by adopting the multiplying factor adopted in accordance with the State specific multiplication factor[1]. Budgetary provisions have been made for the compensation for structure at replacement cost without depreciation, resettlement and rehabilitation assistances to titleholders in accordance with the RFCTLARR Act and to nontitleholders in accordance with the provisions of the EMof CKICP and the cost of RP implementation, including the cost of resolving grievances. The total resettlement cost for the project is INR. 337.71 million. The major heads of budget items are listed below. [1]G.O.Ms. No 300 of Revenue and Disaster Management (LA-I(1)) dated 21.09.2017

B. Compensation

107. Private Land: The compensation for private land has been calculated as an average of replacement cost of land in rural and semi-urban area adjoining the road corridor. The replacement cost was gathered during census survey in discussion with local community and the elected local body representatives and compared with guideline value from the registration department. For budgetary purposes, the replacement cost for land has been taken as Rs.347 per sq.m. being the average rate for rural land from the guideline value. The multiplying factor as per State rules is 1.25, being the maximum that can be applied to any land parcel, and is based on the distance from the nearest urban centre. With a 100% solatium and 25% additional value the land cost works out to be Rs.1084 sq.m.

108. Structure: The compensation for structures have been arrived at based on prevailing (year 2018 -19) market rate (the rate shall be updated every year by a panel of engineers in public works department, Govt of Tamil Nadu) for building works, material and labour. Rate fixed for each category along with the quantity is given in Table 44. However, at the time of disbursement of the compensation, the competent authority will value each structure to arrive at the replacement cost as per the current rate. The solatium of 100% on structure rate is adopted for titleholders.

C. Assistances

109. All other unit rates are as per the minimum provisions contained in RFCTLARR Act and as per the approved EM. For budgeting purposes, the onetime grant of Rs.5,00,000 has been provided for significantly impacted titleholders who would lose one-third of their family income.

D. Compensation for Community Assets and Government Structures

110. The unit cost for the place of worship will budgeted as a lumpsum Rs.3,00,000 to cover the cost of reconstruction. However, the actual cost will be assessed by the Highways Engineer at the time of implementation.

E. RP Implementation Cost

111. The cost of hiring LARRIC for assisting LARRU in RP implementation has been provided with a budget of Rs.73,00,000, for intermittent inputs and the RP implementation is expected to 49 be completed in 24 months including disbursement of compensation and Rehabilitation and resettlement assistance for land acquired under RFCTLARR Act. A budgetary cost for external monitoring and evaluation has also been envisaged, as this Project is a Category-A for IR, a budgetary provision of Rs.21,00,000 has been made available for hiring of a consultant for the same. The budgetary provision for meeting administrative expenses is included as part of the project cost. A lumpsum provision of Rs.5,00,000 towards grievance redressal Mechanism related expenses has been budgeted. Further, a lump sum provision of Rs.50,000 to meet disclosure expenses and a lump sum provision of Rs.2,00,000/- for staff training, in particular the LARRU and LARRIC staff involved in RP implementation, has also been budgeted.

F. Source of Funding and Fund Flow 112. The Government will provide adequate budget for all land acquisition compensations, R&R assistances and RP implementation costs from the counterpart funding. The funds as estimated in the budget for a financial year and additional fund required based on revised estimates, shall be available at the disposal of the jurisdictional Divisional Engineer (Highways)at the beginning of the financial year and from whom LARRU will draw the required funds. The PD, Chennai Kanyakumari Industrial Corridor Project (CKICP), Highways Department being the EA for this project, will provide necessary funds for compensation for land and structure and the cost of resettlement assistance in a timely manner to the jurisdictional Divisional Engineer (Highways). The DE(H) will ensure timely availability of funds with the LARRU for smooth implementation of the RP. The LARRIC under the LARRU will facilitate disbursements, but the responsibility of ensuring full and timely payment to displaced persons will be that of LARRU.

G. Resettlement Budget Estimates 113. The budget for this project is based on data and information collected during census and socio-economic surveys conducted during April - August 2019. The unit rates for structure has been worked out from the PWD plinth area rates for 2018-19. The total budget for LA, RR and implementation cost is estimated at INR 337.71 million. A detailed budget estimate for the Project is given along with item wise cost break-up in the following table.

H. Disbursement of Compensation and Assistances 114. In order to ensure that: (i) the DP need not make frequent visits to his/her bank for depositing the physical paper instruments; (ii) s/he need not apprehend loss of instrument and fraudulent encashment; and (iii) the delay in realization of proceeds after receipt of paper instrument is obviated, all disbursement of compensation for land and structure and R&R assistances shall be done only through Electronic Clearing Service (ECS) Mechanism and charges for ECS, if any, will be borne by LARRU. If the DPs destination branch does not have the facility to receive ECS (Credit), then the disbursement shall be done through respective lead banks’ IFSC (Indian Financial System Code). Payment through account payee cheques will be made only if payment trough ECS is not possible and no cash payment will be made.

115. The LARRIC and LARRU, while collecting bank particulars from the APs, will also check with the respective bank branches if the branch has ECS (Credit) Mechanism, and if not, details of lead bank offering the facility will be collected to facilitate ECS transfer. Wherever new accounts are to be opened, preference will be given to bank’s having ECS (Credit) facility. The LARRIC will check the type of APs bank account and help the AP to convert the bank account to a regular savings bank account, if it is of Jan Dhan type, to enable receive compensation, 50

Rehabilitation and resettlement assistances. The bank account particulars of the AP as part of the micro plan will be submitted to the jurisdictional Resettlement Officer (RSO) for disbursement.

Table 41: Budget Estimate Amount Item No Item Input Unit Rate Quantity (in INR) 1 Compensation Land Cost (Multiplying Factor 1.25 and 1.1 Solatium 100%) 25% Additional Sq.m 1084 203000 220052000 compensation

Temporary Structures and Solatium 100% 1.2 (Titleholder) Sq.m 8310 324.38 2695597.8 Semi-permanent Structures and 1.3 Solatium 100% (Titleholder) Sq.m 7970 270.19 2153414.3 Permanent Structures and Solatium 100% 1.4 (Titleholder) Sq.m 11670 1192.5 13916475 Temporary Structures without 1.5 Solatium (Non-Titleholder) Sq.m 4155 3493.2 14514246 Semi-permanent Structures without 1.6 Solatium (Non-Titleholder) Sq.m 3985 281.68 1122494.8 Permanent Structures without 1.7 Solatium (Non-Titleholder) Sq.m 5835 14.625 85336.875 1.8 Private well and Solatium 100% Units 1000000 2 2000000 1.9 Loss of trees with 100% solatium LS 1613 4000000 Subtotal Compensation (A) 260539564.8 2 R&R Assistance One time grant for land owners & loss of 2.1 income (commercial building) One Time 500000 10 5000000 One time resettlement allowance for Major 2.2 Owner Res / Com One Time 50000 63 3150000 Subsistence allowance for Major Res / 2.3 Com Owners One Time 36000 63 2268000 2.4 Shifting allowance major owners One time 50000 63 3150000 Alternate house for Major Impacted Owner 2.5 Residences (R) One Time 120000 10 1200000 Alternate house for Major Impacted Owner 2.6 Residences (U) One Time 150000 9 1350000 One time assistance for cattle shed (Major 2.7 Owner) One Time 25000 2 50000 51

One time assistance for loss of trade / self- 2.8 employment (Major One Time 25000 25 625000 owner/tenant)

Rental allowance for Res tenants - Rural 2.9 (Major) One Time 18000 1 18000 Rental allowance for Res tenants - Urban 2.1 (Major) One Time 24000 2 48000 Rental allowance for Commercial/ 2.11 Res+Comm tenants - Rural (Major) One Time 24000 3 72000 Rental allowance for Commercial/ 2.12 Res+Comm tenants - Urban (Major) One Time 36000 6 216000 2.13 Shifting allowance major Tenants One Time 10000 12 120000 Housing and site grant to Residential 2.14 squatters (Major) One Time 120000 19 2280000 Rehabilitation grant for Comm 2.15 squatters One Time 20000 18 360000 Subsistence allowance for Res/Com 2.16 Squatters (Major) One Time 18000 37 666000 Shifting assistance for 2.17 squatters (Major) One Time 10000 37 370000 Subsistence allowance for employees 2.18 (Major) One Time 20160 0 0 2.19 Subsistene allowance for Kiosk (Major) One Time 18000 0 0 2.2 Vulnerable Household assistance One Time 8000 29 232000 2.21 Training for Vulnerable household One Time 5,000 29 145000 Subtotal R&R Assistance (B) 21320000 3 Community Assets 4.1 Bus Shelter * Unit 0 17 0 4.2 Bore well * Unit 0 0 0 4.3 Handpump 0 0 0 4.4 Water Tank Syntex 0 0 0 4.5 Pump House 0 0 0 4.6 Canal Shutter 0 0 0 4.7 Open well 0 0 0 4.8 Statue 300000 0 0 4.9 Memorial 300000 0 0 4.1 School 300000 0 0 4.11 Places of Worship Unit 300000 22 6600000 52

4.12 Other and government buildings Unit 200000 42 8400000 Subtotal Community Assets (C) 81 15000000 4 Administrative Expenses 4.1 Training for staff LS - 200000 4.2 NGO for RP Implementation LS - 7300000 4.3 Monitoring and Evaluation consultants LS - 2100000 4.4 GRC Expenses LS - 500000 4.5 Disclosure LS - 50000 Subtotal Administrative expenses (D) 10150000

Total (INR) (A+B+C+D) 307009564.8

Contingency @ 10% 30700956.48 Total (In INR) 337710521.3 Total in Million INR 337.71

Note The Structure cost is based on the valuation given by the HD The CPR relocation cost is based on the local market rates, based on discussion with local people during survey The R&R Assistance derived based on the Entitlement Matrix of CKICP

53

X. GRIEVANCE REDRESSAL MECHANISM A. Introduction 116. A project-specific grievance redress Mechanism (GRM) will be established to receive, evaluate and facilitate the resolution of affected people’s concerns, complaints and grievances about the social and environmental performance at different levels of the project. The GRM will aim to provide a time-bound and transparent Mechanism to voice and resolve social and environmental concerns linked to the project. The project-specific GRM is not intended to bypass the government’s own redress process, rather it is intended to address affected people's concerns and complaints promptly, making it readily accessible to all segments of the affected people and is scaled to the risks and impacts of the project. The PAPs are free to approach the judicial system at any time.

B. Grievance Redressal Committee 117. The Grievance Redressal Mechanism (GRM) will be composed of two Grievance Redress Committees (GRCs), one at the Project level (Project-Level GRC), and the other at the local level (local-level GRC). The GRCs’ role is to receive, evaluate and facilitate the resolution of affected persons concerns, complaints and grievances. The GRM will provide an opportunity to the PAPs to have their grievances redressed prior to approaching the State level LARR Authority11, constituted by Government of Tamil Nadu in accordance with Section 51(1) of the RFCTLARR Act, 2013. The GRM is aimed to provide a trusted way to voice and resolve concerns linked to the project, and to be an effective way to address affected person’s concerns without allowing it to escalate resulting in delays in project implementation.

118. The GRM will continue to function, for the benefit of the APs, during the entire life of the project including the defects liability period. The response time prescribed for the GRCs would be three weeks. Since the entire resettlement component of the project has to be completed before the construction starts, to resolve the pending grievances, the GRC, at regional level, will meet at least once every month in the first year of the RP implementation and once in three months thereafter. Other than disputes relating to ownership rights and apportionment issues on which the LARR Authority has jurisdiction, the GRCs will review grievances involving eligibility, valuation, all resettlement and Rehabilitation benefits, relocation and payment of assistances. Grievances received by the Special DRO, LARRU will be resolved at his/her level, if possible, else it will be placed before the GRC.

119. Local-level: The local levels GRCs will function out of Thanjavurand Thiruvarur Districts. The 4-member local GRCs will be chaired by (i) a retired District Revenue Officer (DRO) or equivalent rank officer, the (ii) Divisional Engineer, Highways, CKICP acting as its member secretary and a (iii)Revenue Divisional Officer of division concerned iv) local person of repute and standing in the society, nominated by the Project Director, CKICP based on the recommendations made by the respective District Collector. Grievances/concerns can be lodged directly to the DE,, Highways, CKICPor submitted to the LARRIC/agency appointed for implementation support, either in person or through post or through email.

120. Project-Level GRC: The Project Director, CKICP, Highways Department will be the appellate authority who will be supported by the Superintending Engineer, PIU. The grievance redressal procedure is shown in the following figure.

11 G.O.(Ms) No.305, Revenue & Disaster Management (LA-I(1)), dated 20th September 2017. 54

Figure 3: Grievance Redressal Process

C. Functions of Local-Level GRC 121. The main functions of the GRCs will be:

(i) To provide support to PAPs on problems arising out of eligibility for entitlements and R&R assistance as per the Entitlement Matrix; (ii) To record the grievances of the PAPs, categorize and prioritize the grievance that needs to be resolved by the GRC and solve them within 3 weeks; (iii) To inform the PIU (and Project-Level GRC) regarding serious cases within one week; and (iv) To report to the aggrieved parties about the developments regarding their grievances and decisions of the PIU, within 3weeks.

122. The GRC should meet at least once a month in the respective office of the jurisdictional Divisional Engineer (H). Petitions received from APs of any concerns or complaints or grievances should be taken up in the GRC. The member secretary should maintain a register of all petitions received with details of date of receipt of the petition, date of hearing, if any, date when it was considered by the committee, along with nature of complaint/concern, action taken and date of communication sent to petitioner. Communication, in writing should be sent to the aggrieved person about the date, time and venue of the GRC sitting and make it known that s/he is entitled for personal hearing and that representation through proxy will not be entertained. Communication will also be sent through implementation support LARRICso as to ensure that the petitioner is informed about the date of GRC sitting.

55

123. Copies of petitions received 1-week prior to the committee’s sitting should be sent to Chairman and the member along with an explanatory note from appropriate authority and/or RP implementation support LARRIC, as the case may be, to enable the Chairman and member to scrutinize the petitions in detail. Petitions received in the week of the committee’s sitting, shall be taken up during the sitting and resolved.

124. Decision of the committee will be final unless an appeal is preferred with the Project Director, PIU. If the committee is unable to arrive at a decision through consensus, the matter will be referred to the appellate authority with a note on the opinion of the committee members. The complaint/concern will be redressed in three week time and written communication should be sent to the complainant about the decision taken.

125. The RP implementation support LARRIC will assist displaced persons in registering their grievances and being heard. The complaint / grievance will be redressed in 3weeks time and written communication will be sent to the complainant. A complaint register will be maintained at Jurisdictional Des office (member secretary of GRC)/LARRU/PIU level with details of complaint lodged, date of personal hearing, action taken and date of communication sent to complainant. If the complainant is still not satisfied s/he can approach the appellate authority and/or the jurisdictional LARR Authority. The complainant can access the appropriate LARR Authority at any time and not necessarily go through the GRC.

D. Costs 126. All costs involved in resolving the complaints (meetings, consultations, communication and reporting / information dissemination) will be borne by the Project.

56

XI. INSTITUTIONAL ARRANGEMENT AND IMPLEMENTATION

A. Land Acquisition, Rehabilitation and Resettlement Units (LARRU)

127. To expedite land acquisition and implement the provisions of the road-project RPs, one Land Acquisition and Rehabilitation and Resettlement Unit (LARRU) at the PIU Head Quarters, Chennai and four LARRU Field Units have been formed for carrying out land acquisition and RP implementation. four regional levels Land Acquisition Rehabilitation and Resettlement Units (LARRU) have been constituted. These units will be headed by a Special District Revenue Officers (Spl DRO) and will be supported by a Resettlement Officer (RSO)and Tahsildars for support in land acquisition. A separate Government Order12 has been issued nominating Spl DRO as competent authority under TNH Act for land acquisition and award pronouncement. The Project Director, CKICP will be overall in charge of land acquisition and R&R implementation and will coordinate with the four Spl DROs in RP implementation and LA. The Chief Engineer, working under the Project Director, will be supported by domain experts in the areas of land acquisition and Social Development/R&R. The Chief Engineer will report to the Project Director. These units will be entrusted with responsibilities of implementation of the RP involving: (i) acquisition of land and assets; (ii) payment of compensation for land and assets; (iii) disbursement of resettlement assistances including development of resettlement sites. The LARRU in each region will be supported with clerical staff. The members of these units, their roles, responsibilities and functions are outlined below.

B. Project Implementation Unit 128. The office of the Project Director, CKICP,Chennai, Highways Department, Government of Tamil Nadu will be the Project Implementation Unit (PIU) and will be overall in charge of coordination between the six Division Engineers (H) and the four Special DROs (LA).The PIU will be headed by the Project Director and supported by the Chief Engineer with a full-fledged unit under him. A Special District Revenue Officer (Spl DRO), Resettlement Officer (RSO) have been posted at the PIU to coordinate with the 4-LARRU and assist PD, PIU in land acquisition, rehabilitation and resettlement matters.

Table 42: Administrative Roles and Financial Powers of LARRU

Officers Roles and Powers

Project Director Overall in charge of LA and R&R Reporting to Asian Development Bank on progress and submission of quarterly progress report Approve payment to LARRIC / external monitoring agency According financial approval for all payments pertaining to LA and R&R Approval of the R and R entitlements for TH and NTH Obtaining necessary budgetary allocation from GoTN Decision on the report of Spl DRO of claims for inclusion as APs

Chief Engineer, Overall responsible for LA and R&R implementation. CKICP Monitoring the progress of LA and R&R activities and reporting to Project Director

12 GO (MS) No.99 Highways and Minor Port (HF1) Department dated 01.09.2014 (enclosed as Appendix-III) 57

Officers Roles and Powers

Special District Competent authority for LA under TNHA 2001 Revenue Approve valuation of land and structure as per RFCTLARR 2013 Officer(s) Hear objections vide Sec 15(2), determine compensation amount in agreement with DP vide Sec 19(2) or in case of disagreement vide Sec 19(3), hear APs on the compensation amount vide Sec 19(5), refer disagreement on compensation to LARR Authority for adjudication vide Sec 20 and apportionment issues vide Sec 21(2) Pronounce award for compensation of land and structures as per TNHA 2001 Financial powers of up to Rs.10 crores Above Rs.10 crores, will obtain CLA permission and pass award Liaison with District Administration to update the land records and notify the guideline values. . Monitor the progress of LA carried out by Special Tahsildar Co-ordinate the implementation of R&R activities through resettlement officer, field staff, highway, forest, agricultural department, horticulture department and revenue officials Approval of Individual Entitlement Plan (micro plan) prepared for implementing RP. Monitor the progress of resettlement activities carried out by the LARRIC. Certify work of LARRIC for payment to PD, PIU Hold fortnightly meetings on RP implementation and report to the PD, CKICP through CE, CKICP Liaison with district administration and line departments to dovetail Aps with government schemes. Monitor the progress of Resettlement Site development and liaison with district administration and line departments for providing necessary amenities and facilities Participate in meetings to facilitate LA and R&R activities Review of Monthly and Quarterly reports Issue milestone wise encumbrance free certificate to concerned field DE(H), CKICP for commencement of civil works Authorise bank for disbursement of compensation and resettlement assistances to APs through ECS Review report submitted by RSO on claims for inclusion as DPs and forward to CE, CKICP with recommendations.

Resettlement Responsible for the implementation of R&R activities through field staff, highway, Officer (RSO) forest, agricultural department, horticulture department and revenue officials Review of individual entitlement plans prepared for implementing RP and submit to DRO for approval. Identify suitable land for Resettlement in coordination with District administration and initiate alienation/acquisition process Supervise the LARRIC involved in RP implementation Assist DRO in disbursement of compensation and resettlement assistances

Holding periodical consultations with the affected people on implementation of LA and R&R activities with the support of the LARRIC. Prepare monthly physical and financial progress reports Update payment of compensation, disbursement of resettlement assistances, Aps socio-economic data in the database with the support of the LARRIC Verify claims for inclusion as Aps and submit report to Spl DRO for onward transmission to CE, CKICP

58

Officers Roles and Powers

Superintending Undertake internal monitoring of RP implementation based on monthly progress Engineer report submitted by LARRU and submit report to PD, CKICP Divisional Coordinate with line department and ensure relocation of utilities, in particular Engineer water supply, prior to civil works Coordinate with forest department and revenue officials for tree cutting in RoW Valuation of Structures Conduct GRC meetings Undertaken the reconstruction of affected common facilities including temples. Issue clearance to contractor to commence civil works after obtaining milestone wise clearance from LARRU Tahsildar(s) Approve sub-division sketch, award statement and valuation statement Approve valuation of assets, trees and crops submitted by concerned department officials Assist RSO in identifying suitable land for Resettlement in coordination with District administration and initiate alienation/acquisition process Coordinate with district administration and line departments and provide necessary amenities and facilities in the resettlement site Coordinate the relocation of Aps to resettlement site Oversee the relocation / shifting of CPRs Submit milestone wise encumbrance free certification to DRO Issue of identity cards to the Aps Surveyor(s) Verify LPS prepared by DPR consultants and carryout necessary corrections after survey and measurement Prepare sub-division sketch, statement for award and valuation statement for LA After LA award, coordinate with concerned Revenue officials and carryout changes in revenue record After LA, provide corrected FMB sketch and updated RoW details to concerned Highway Divisional office Issuance of LA notifications to Aps and other stakeholders MIS Specialist Maintain and update AP data Update periodically disbursement of compensation and assistances Generate information and data for monthly and quarterly progress reporting Revenue Assisting in the field verification for LA and R&R activities Coordinate and Inspector monitor the service of LA notice . Collection of sales statistics, guide line value from SR office Coordination to collect tree value from forest, agriculture and horticulture department. Obtaining NOC from HR&CE and land reforms departments Coordinate between various departments

Land Records Works relating to scrutinyofsub division records Draughts Man Preparation of eye value sketch for PV proposal Coordinate with sub inspector of survey in preparing enjoyment sketch before award enquiry Activities related to post award

C. Competent Authorities 129. The implementation of land acquisition and resettlement impacts will require approvals and clearance at various stages. The following officers will act as competent authorities for certain key activities. 59

Table 43: Competent Authority for Approvals Approvals Required Competent Authority Approval for LA awards Special DRO, CKICP Approval for LA awards exceeding Rs10 Crore Commissioner of Land Administration Approval of RPs including Budget provisions Project Director, CKICP Changes in Policy provisions, entitlements Empowered Committee, CKICP Unit rate updation of entitle matrix Project Director, CKICP Staff requirements, Consultants/LARRICs Project Director, CKICP Appointments Approval for issue of ID cards Special DRO, CKICP Approval of R&R Assistance Project Director, CKICP Disbursement of R&R Assistance Special DRO, CKICP Approval for structure valuation Divisional Engineer (H), CKICP Approval for shifting and relocation of community Special DRO, CKICP assets Approval of Resettlement sites, House site, Issue of Special DRO, CKICP titles etc. Resolution of disputes GRC / LARR Authority Committee formed by the Project Director, consisting of the Chief Engineer, Implementation Guidelines Superintending Engineer and Spl. District Revenue Officer.

D. LARRIC/Agency for RP Implementation Support 130. The implementation of the R&R provisions will be carried out by LARRU with the support of LARRICs who have had experience in similar development projects. The LARRICs to be engaged will have proven experience in carrying out resettlement and rehabilitation activities and community development and consultations in projects of similar nature in Tamil Nadu.

131. The LARRIC will play a key role in the implementation of the RP. Their tasks will include the final verification of DPs, consultations, establishment of support mechanisms and facilitate the delivery of the rehabilitation assistances as per the RP provisions and to ensure that the DPs receive all the entitlements as per the R&R policy of the project.

132. Key activities of the LARRIC in relation to resettlement planning and implementation include: (i) assist LARRU in verification and updating, if required, the detailed census and socioeconomic survey of displaced persons carried out during DPR preparation based on detailed design, and verify the identity of below poverty line, female-headed, and other vulnerable households affected by land acquisition and involuntary resettlement and issue ID cards; (ii) prepare micro plan and get vetted by LARRU; (iii) facilitate the process of disbursement of compensation to the DPs – coordinating with the LARRU and informing the displaced persons of the compensation disbursement process and timeline; (iv) assist DPs in opening bank accounts explaining the implications, the rules and the obligations in having a bank account, process of disbursement adopted by CKICP and how s/he can access the resources s/he is entitled to; (v) assist the DPs in ensuring a smooth transition (during the part or full relocation of the affected persons), helping them to take salvaged materials and shift; (vi) in consultation with the DPs, inform the LARRU about the shifting dates agreed with DPs in writing and the arrangements they desire with respect to their entitlements; (vii) organize training programs to the vulnerable for income restoration; (viii) conduct meaningful consultations throughout the RP implementation and ensure disclosure of resettlement plans in an accessible manner to the 60 displaced persons; (ix) assist DPs in grievance redressal process; (x) assist LARRUs in keeping detailed records of progress and establish monitoring and reporting system of RP implementation; and (xi) act as the information resource center for community interaction with the project and maintain liaison between community, contractors and project management and implementing units during the execution of the works. Terms of reference for the recruitment of a LARRIC/agency for RP implementation support is given in Appendix-5.

E. External Monitoring 133. A third-party monitoring agency will be recruited to monitor and evaluate the implementation of all the resettlement plans of the Tamil Nadu Industrial Corridor Improvement Project. The objectives of the external monitoring are to:

(i) Assess the implementation progress of RP as per the RPF provisions and processes and its compliance with ADB’s Safeguard Policy Statement (SPS) 2009.; (ii) Monitor the schedules and the implementation targets; (iii) Evaluate whether the objectives and outcomes of RP are met the project roads.The External Monitoring Team will have at least 1 team leader, 3 key experts and several field staff.

F. Land acquisition and Resettlement process: 1. Rehabilitation and Resettlement Award

134. In accordance with the provisions of the RFCTLARR Act [Sec31(1)], the competent authority will pass a Rehabilitation and Resettlement (R&R) Award. All the affected titleholders who are eligible for R&R assistance will be notified along with details of eligible assistance as per the provisions of RFCTLARR Act. Initially a draft list will be notified by giving minimum of 15 days’ time inviting objections, if any, regarding discrepancies on the nature and quantum of assistance. The final list will be notified after taking into account the objections, if any. Similarly, the list of those affected non- title holders will also be notified along with the details of R&R assistance and a separate R&R award enquiry will be conducted for the non-titleholders.

2. Micro plan

135. The implementation support LARRIC will prepare the draft micro plan, village wise for the project road detailing the type of loss, tenure of the AP, vulnerability status and the entitlements as per the provisions of the Entitlement Matrix (EM) and beneficiary bank details. The draft micro plan will be disclosed in the jurisdictional village panchayat where the APs are living/having business, and 7-days after the disclosure, the R&R award enquiry will be held by the jurisdictional Special District Revenue Officer Spl DRO).

136. Based on the R&R award enquiry outcome, the LARRIC will submit the final micro plan to RSO, LARRU for verification and onward transmission to Project Director, PIU through the Spl DRO, LARRU. The Project Director, PIU, after scrutiny of the micro plan will accord approval for the disbursement of the R&R entitlements.

61

3. R&R Award Process

137. The Spl DRO, LARRU will hold R&R award enquiry in the project area and will send prior intimation to all concerned APs through the jurisdictional Village administrative Officer (VAOs) and the LARRIC.

138. During the R&R award enquiry, each AP will be informed about the type of loss and tenure as recorded during census and socio-economic survey and verified subsequently, and the entitlements due to the AP as per the provisions contained in the EM. All the APs will be given an opportunity to be heard and concerns if any, will be addressed. The R&R proceedings will be recorded and copy of the R&R award will be issued to the AP then and there.

G. Establishment of a Management Information System (MIS)

133. A well-designed MIS will be created and will be maintained at PIU and LARRU level. The MIS will be supported with approved software and will be used for maintaining the APs baseline socio-economic characteristics, developing pre-defined reports, algorithms and calculations based on the available data and updating tables/fields for finding compensation and assistances, tracking the land acquisition and resettlement progress. The individual entitlements, compensation calculations, structure valuation, etc. will be updated using MIS software. In addition, land acquisition notices, identity cards will also be generated thorough MIS. All quires will be generated and the baseline data will also be maintained and updated as needed. The data and information required for periodical progress reports will be generated using MIS database. The required computer terminals and software will be established at LARRU level in order to feed the data to be maintained in the web with backup at PIU.

H. Capacity Building of PIU/LARRU

134. The staff of LARRU, LARRIC and the staff of PIU, who are involved in LA and R&R will require to be familiar with land acquisition procedures and ADB Social Safeguards policy requirements. In order to build the capacity of the LARRU and the PIU, an orientation and training in resettlement management at the beginning of the project will be undertaken. The training activities will focus on issues concerning (i) principles and procedures of land acquisition, (ii) public consultation and participation, (iii) entitlements and compensation disbursement mechanisms, (iv) Grievance redressal, and (v) monitoring of resettlement operation.

62

XII. IMPLEMENTATION SCHEDULE A. Introduction 135. Resettlement activities will be coordinated with the timing of civil works. The required coordination has contractual implications, and will be considered in procurement and bidding schedules, award of contracts, and release of cleared sections to project contractors. The project will provide adequate notification, counseling and assistance to affected people through the RP implementing agencies/LARRICs so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation.

136. The RP implementing agencies/LARRICs staff will provide project LA and R&R related information to the PAPs, provide details of entitlements and procedures for getting compensations and availing R&R assistance. The agencies/LARRICs will also provide assistance in updating the RP particularly with PAP and their asset details, facilitating issue of ID cards, opening of bank accounts, facilitate implementation of livelihood and income restoration program, coordinate with other various agencies, conduct awareness program for HIV/AIDS, health and hygiene, road safety, gender and human trafficking. All other activities related to implementation and land acquisition will be undertaken simultaneously.

B. Schedule for Project Implementation

137. The proposed RP implementation activities are divided into three broad phases viz. project preparation phase, RP implementation phase, and monitoring and reporting phase, and the activities envisaged in each phase is discussed below.

138. Project Preparation Phase: The activities to be performed in this phase include: (i) the formation and staffing of the LARRUs; (ii) submission of the RP to ADB for approval; (iii) the appointment of the RP implementation LARRIC/agency; and (iv) the establishment of GRCs. The information dissemination and stakeholder consultations will commence in this stage and continue untill the end of the project.

139. RP Implementation Phase: In this phase, the key activities to be carried out include: (i) joint verification; (ii) valuation of structures; (iii) LA notification; (iv) preparation of micro plan; (v) LA and R&R award enquiry; (vi) approval of final micro plan; (vii) identification and development of resettlement site; (viii) payment of compensation for land and structure; (ix) payment of other Rehabilitation assistances; (x) relocation of DPs to resettlement site; and (xi) issuing site clearance certificate to enable commencement of civil works.

140. Monitoring and Reporting PHase: Internal monitoring will commence as soon as RP implementation begins and continue till end of RP implementation. External monitoring will also commence from the beginning of RP implementation.

C. RP Implementation Schedule 141. An implementation schedule for land acquisition, payment of compensation and resettlement and Rehabilitation activities in the project including various sub tasks and time line matching with civil work schedule is provided in the work plan. The following are the key implementation activities that are presented in the work plan. a) Updating of RP based on design changes, if any b) Approval of RP and Disclosure c) Appointment of LARRICs and External Monitoring consultants 63

d) Constitution and notification of GRCs e) LA Notification f) Verification of APs and Notification of AP list g) Obtaining options for resettlement and choice of resettlement site location h) MIS in operational for tracking LA and R&R Implementation progress i) Structure Valuation j) Disclosure of Microplan (list of eligible APs and their entitlements) k) Issue of Identity cards l) R&R Award including assistance for non-title holders m) Relocation of CPRs n) Payment of R&R assistance o) Allotment of house sites or development of Resettlement sites p) Shifting of DPs of alternative resettlement sites q) LA Award and disbursement of compensation r) R&R Award including assistance for title holders s) Certification of payment of LA and R&R assistance for first milestone t) Certification of payment of LA and R&R assistance for second milestone u) Impact Evaluation

142. Coordination with Civil Works: The land acquisition and resettlement implementation will be cocoordinated with the timing of procurement and commencement of civil works. The required co-ordination has contractual implications, and will be linked to procurement and bidding schedules, award of contracts, and release of encumbrance free land to the contractors. The project will provide adequate notification, counselling and assistance to APs so that they are able to move or give up their assets without undue hardship before commencement of civil works and after receiving the compensation and R&R assistances.

143. The relocation of common property resources will be linked to handing over of encumbrance free land to the contractors. The handing over of land to the contractor will be organised in two sections. Sections having no IR impact and non-significant impacts will be in the first-milestone and will be handing over after signing of the contract and by the financial closure date, and the rest within one year/one and half years of contract signing as spelled out in the respective civil work contracts.

64

RP Implementation Work Plan

65

XIII. MONITORING AND REPORTING

A. Introduction

144. The objective of monitoring is to provide the PIU and LARRU with an effective tool for assessing Rehabilitation progress, identifying potential difficulties and problems areas and provide an early warning system for areas that need correction. Continuous supervision and periodic monitoring are an integral part of successful implementation. Monitoring is a warning system for project managers and a channel for the APs to express their needs and reactions to the programme.

B. Internal Monitoring 145. The Land Acquisition, Rehabilitation and Resettlement Unit (LARRU) will carry out concurrent monitoring of RP implementation through the RSO, LARRU and prepare monthly and quarterly progress report in terms of physical and financial progress. In addition, the monitoring process will also look into: the communication and reactions of APs; use of grievance procedures; information dissemination to APs on benefits; and implementation time table. The monthly internal monitoring reports based on the outcome of consultations and feedback with displaced people who have received assistance and compensation and review of progress of other implementation activates including complains/concerns/issues raised by the APs, will be submitted to PIU by the end of 1st week of the subsequent calendar month. The progress report will be reviewed by the CE, PIU and comments if any, will be communicated to LARRU for immediate action.

146. A copy of the quarterly report will be made available to ADB. In view the significance of resettlement impacts, the monitoring Mechanism for this project will Have both monitoring by LARRU and monitoring by an external agency / expert.

C. External Monitoring

147. An external monitoring agency will be recruited by the EA under ADB financing. The team will be composed of a team leader experienced in resettlement and land acquisition, and three key experts, in additional to support and field staff. The external monitoring will include but not limited to: (i) assess the RPs’ implementation and compliance with ADB’s Safeguard Policy Statement (2009); (ii) review and verify the monitoring reports prepared by LARRU; (iii) monitor the work carried out by LARRIC and provide training and guidance on implementation; (vi) review the grievance redressal Mechanism and report on its working; (v) mid-term impact assessment through sample surveys amongst displaced persons for midterm corrective action; (vi) consultation with APs, officials, community leaders for preparing review report; (vii) assess the resettlement efficiency, effectiveness and efficiency of LARRU, impact and sustainability, and drawing lessons for future resettlement policy formulation and planning. Some of the important task of external monitoring is the feedback of the APs who receives compensation and assistance and also alerts on the risks, non-compliances and early warnings in the implementing.

D. Indicative Indicators

148. Indicators will be developed for internal monitoring and external monitoring purposes and integrated in the MIS. The Table 47 below shows indicative indicators for monitoring.

66

Table 44: Indicative Indicators for Monitoring

Monitoring Issues Monitoring Indicators Budget and time frame ● Have all resettlement staff been appointed and mobilized for field and office work on schedule? ● Have capacity building and training activities been completed on schedule? ● Are resettlement implementation activities being achieved according to agreed implementation plan? ● Are funds for resettlement being allocated to resettlement agencies on time? have resettlementofficesreceivedthescheduled funds? ● Have funds been disbursed according to RF? ● Has the land been made encumbrance-free and handed over to the contract or in time for project implementation? Delivery of entitlements ● Have all affected persons received entitlements according to numbers and categories of loss set out in the entitlement matrix? ● How many affected households have relocated and built their new structures at new locations? ● Are income and livelihood restoration activities being implemented as planned? have affected businesses received entitlements? ● Have the community structures (e.g. mosque, club, etc.) been compensated and rebuilt at new sites? ● Have all processes been documented? ● Are there discrepancies between the estimated number of affected persons as per the RP/RP addendum and actual numbers ● Share of CCL disbursement vs total TH affected ● SHare of TH who have received “top ups” ● Share of TH who have received entitlement benefits ● Share of NTH who have been compensated market value for loss of structure, tree or crops ● Share of NTH who have received entitlement benefits Relocation assistance ● Has LARRIC prepared a list of alternative places to rent/buy? ● Have affected households benefitted from support of LARRIC to find alternative place to rent/buy? If so, how many and what services were provided? Consultation, grievances, ● Have resettlement information brochures/leaf lets been prepared and special issues and distributed? have consultations taken place as scheduled, including meetings, groups, and community activities? ● Have any affected persons used the grievance redress procedures? What grievances were raised? What were the outcomes? ● Have conflicts been resolved? ● Have grievances and resolutions been documented? have any cases been taken to court? Resettlement ● What changes have occurred in patterns of occupation compared Benefit/Impacts to the pre-project situation? 67

Monitoring Issues Monitoring Indicators ● What changes have occurred in income, expenditure and livelihood patterns compared to pre-project situation? ● How many physically displaced households have relocated? Where are they relocated (i.e. remaining plot of land, newly purchased plot, rented plot/structure) ● How many household have purchased plot? ● What was compensations/resettlement benefits spent on? ● Have the participants of the livelihood training program used their new skills? What was the seed grant spent on?

E. Reporting Requirements 149. The following reports will be prepared and submitted to the PIU, EA or project team at the Asian Development Bank.

Table 45: Reporting Requirements

Type of Report Submitted Content Frequency Responsibility to RP update Provide the updated list of Till the end of LARRIC / PIU/EA/ADB affected persons after the joint Project PIU/LARRMC verification survey Addendum(s) Detail the land acquisition and To be prepared LARRIC/PIU/ PIU/EA/ADB resettlement impacts, when either LARRMC socioeconomic survey of conditions affected persons, mitigation and below is met: (i) Rehabilitation measures, for sections of budgetary requirements and project timeline for implementation where design is not final (ii) for unforeseen activities with resettlement impacts Monthly Progress on land acquisition and Monthly LARRIC/ PIU progress report resettlement activities, progress LARRMC on indicators, results, issues affecting performance, constraints, variation from RP (if any) and reason for the same and corrections recommended

Semi-annual Progress on land acquisition and Semiannually PIU ADB resettlement resettlement activities, monitoring indicators, variations if any report with explanation and outcome, recommended corrective actions.. External Progress on land acquisition and Semiannually External Monitor PIU/EA/ADB monitoring resettlement activities, report indicators, variations if any with 68

Type of Report Submitted Content Frequency Responsibility to explanation and outcome, affected person’s satisfaction with process, compliance with ADB’s SPS, corrective actions recommended Resettlement Overall narrative of the land Once PIU ADB completion acquisition and resettlement report process, outputs and outcomes of indicators from baseline, key variations/changes, lessons learned Resettlement Overall assessment of the land Once External Monitor PIU/EA/ADB evaluation acquisition and resettlement report process, compliance with ADB’s SPS, indicators achievement when compared to baseline, lessons learned

69

Appendix 1: Summary of APs and CPR

Summary of Private Structures Sl. Village Asset Name of Chai Side Use of Type of Tenure Overall No name No. Head of nage structure structure Impact Household /property 1 Kondur(ct KOL-01 Mathiyazh 3.02 LEFT Commerc Temporar Squatter Significa ) agan ial y nt 2 Kondur(ct KOR-01 Abdul 3.03 RIG Commerc Temporar Encroach Non-sig ) Rahman HT ial y er 4 Kondur(ct KOR-02 Ganeshan 3.04 RIG Residenti C.W Encroach Non-sig ) HT al er 3 Kondur(ct KOR-03 Srinivasan 3.07 RIG Resi + Temporar Encroach Non-sig ) HT Commerc y er ial 5 Kondur(ct KOR-04 NATARAJA 3.1 RIG Commerc Temporar Encroach Non-sig ) N HT ial y er 6 Kondur(ct KOR-05 3.12 RIG Others C.W Encroach Non-sig ) HT er 7 Kondur(ct KOL-02 ANBARASA 3.12 LEFT Commerc Temporar Encroach Non-sig ) N ial y er 8 Kondur(ct KOL-03 Murugaiya 3.13 LEFT Resi + Temporar Encroach Non-sig ) n Commerc y er ial 9 Kondur(ct KOR-06 3.13 RIG Commerc Temporar Encroach Non-sig ) HT ial y er 10 Kondur(ct KOL-04 Ramu 3.15 LEFT Residenti Others Encroach Non-sig ) al er 11 Kondur(ct KOL-05 Selvaraj 3.15 LEFT Residenti Others Encroach Non-sig ) al er 12 Kondur(ct KOL-06 Gunasekar 3.15 LEFT Residenti Others Encroach Non-sig ) an al er 13 Kondur(ct KOR-07 3.16 RIG Others C.W Encroach Non-sig ) HT er 14 Kondur(ct KOL-07 Rathi 3.16 LEFT Residenti Temporar Encroach Non-sig ) al y er 15 Kondur(ct KOL-08 Kuttiyandi 3.17 LEFT Others Temporar Encroach Non-sig ) y er 16 Kondur(ct KOL-09 Sivagami 3.17 LEFT Residenti Temporar Encroach Non-sig ) al y er 17 Kondur(ct KOR-08 3.18 RIG Others C.W Encroach Non-sig ) HT er 18 Kondur(ct KOR-09 Babu 3.2 RIG Resi + Temporar Encroach Non-sig ) Shanthi HT Commerc y er ial 19 Kondur(ct) KOL-10 NISHANTHI 3.215 LEFT Residential Others Encroacher Non-sig 20 Kondur(ct KOL10 EZHILMAR 3.21 LEFT Residenti SemiPermane Encroach Non-sig ) A AN 5 al nt er 21 Kondur(ct KOR-10 Subburayal 3.22 RIG Commerc Temporar Encroach Non-sig ) u HT ial y er 22 Kondur(ct KOR-11 Andal 3.23 RIG Resi + Temporar Encroach Non-sig ) HT Commerc y er ial 23 Kondur(ct KOR-12 3.24 RIG Commerc C.W Encroach Non-sig ) HT ial er 70

24 Kondur(ct KOL-13 3.25 LEFT Residenti C.W Encroach Non-sig ) al er 25 Kondur(ct KOL-14 Kandhasa 3.29 LEFT Commerc Temporar Encroach Non-sig ) my ial y er 26 Kondur(ct KOL-15 3.31 LEFT Resi + Permane Encroach Non-sig ) Commerc nt er ial 27 Kondur(ct KOL-16 Sridhar 3.32 LEFT Commerc C.W Encroach Non-sig ) ial er 28 Kondur(ct KOL-17 Mugundha 3.33 LEFT Commerc Temporar Encroach Non-sig ) n ial y er 29 Kondur(ct KOR-15 3.36 RIG Others C.W Encroach Non-sig ) HT er 30 Kondur(ct KOR-16 3.36 RIG Others C.W Encroach Non-sig ) HT er 31 Kondur(ct KOL-18 3.36 LEFT Commerc Temporar Encroach Non-sig ) ial y er 32 Kondur(ct KOL-19 Isakkimuth 3.37 LEFT Resi + Permane Encroach Non-sig ) u A 5 Commerc nt er ial 33 Kondur(ct KOL-20 Manohara 3.38 LEFT Resi + Permane Encroach Non-sig ) n 5 Commerc nt er ial 34 Kondur(ct KOL-22 Rajendran 3.41 LEFT Resi + Permane Encroach Non-sig ) Commerc nt er ial 35 Kondur(ct KOL-24 3.45 LEFT Commerc SemiPermane Encroach Non-sig ) ial nt er 36 Kondur(ct KOL-25 SIVALINGA 3.46 LEFT Resi + Permane Encroach Non-sig ) M K Commerc nt er ial 37 Kondur(ct KOL-27 3.5 LEFT Resi + Temporar Encroach Non-sig ) Commercial y er 38 Kondur(ct KOR-22 RAJENDIR 3.53 RIG Commerc Temporar Encroach Non-sig ) AN K HT ial y er

39 Kondur(ct KOL-31 MUTHUKU 3.56 LEFT Commerc Temporar Encroach Non-sig ) MARAN K ial y er

40 Kondur(ct KOR-23 MUJIBUR 3.56 RIG Commerc Temporar Encroach Non-sig ) RAHMAN HT ial y er

41 Kondur(ct KOL-32 PURUSOT 3.6 LEFT Others C.W Encroach Non-sig ) H AMMAN er

42 Kondur(ct KOR-28 DEVARAJA 3.74 RIG Commerc C.W Encroach Non-sig ) N HT ial er

43 Tottapatt u TTL-01 3.82 LEFT Others C.W Encroach Non-sig er

44 Tottapatt u TTR-01 3.9 RIG Others C.W Encroach Non-sig HT er

45 Tottapatt u TTR-02 3.95 RIG Others C.W Encroach Non-sig HT er 71

46 Tottapatt u TTR-05 JAYAPRAK 4.03 RIG Commerc C.W Encroach Non-sig ASH HT ial er

47 Tottapatt u TTR-06 PAVANAN 4.09 RIG Commerc Temporar Encroach Non-sig HT ial y er

48 Tottapatt u TTR-07 4.12 RIG Commerc C.W Encroach Non-sig HT ial er

49 Tottapatt u TTR-11 4.5 RIG Others C.W Encroach Non-sig HT er

50 Tottapatt u TTL-03 NITHIYAN 4.56 LEFT Commerc C.W Encroach Non-sig ANDHAM ial er

51 Tottapatt u TTR-12 4.58 RIG Others C.W Encroach Non-sig HT er

52 Tottapatt u TTR-13 4.8 RIG Others C.W Encroach Non-sig HT er

53 Tottapatt u TTL-04 KALAIYAR 4.83 LEFT Commerc SemiPermane Squatter Significa ASI ial nt nt

54 Tottapatt u TTL-07 LAKSHMI 4.9 LEFT Commerc C.W Encroach Non-sig ial er

55 Tottapatt u TTR-15 JAYARAM 4.92 RIG Commerc C.W Encroach Non-sig HT ial er

56 Tottapatt u TTR-18 Baskaran 5.02 RIG Residenti C.W Encroach Non-sig HT al er

57 Tottapatt u TTR-19 Kannan 5.03 RIG Residenti C.W Encroach Non-sig HT al er

58 Tottapatt u TTR-20 Sobana 5.05 RIG Residenti Permane Encroach Non-sig HT al nt er

59 Tottapatt u TTR-21 Sundari 5.06 RIG Residenti C.W Encroach Non-sig HT al er 60 Tottapatt u TTR-22 Rajendhra 5.08 RIG Residenti SemiPermane Encroach Non-sig n HT al nt er 61 Tottapatt u TTR-23 KAMALA L 5.09 RIG Residenti SemiPermane Encroach Non-sig HT al nt er 62 Tottapatt u TTR-24 Venugopal 5.1 RIG Residenti C.W Encroach Non-sig HT al er 63 Tottapatt u TTR-25 Rajesh 5.11 RIG Residenti Permane Encroach Non-sig HT al nt er 64 Tottapatt u TTR-26 GANESAN 5.13 RIG Resi + Permane Encroach Non-sig HT Commerc nt er ial 65 Tottapatt u TTR-27 Saravanan 5.13 RIG Residenti Permane Encroach Non-sig 5 HT al nt er 66 Tottapatt u TTR-30 5.15 RIG Others C.W Encroach Non-sig HT er 67 Tottapatt u TTR-33 Rajasekara 5.31 RIG Residenti Permane Encroach Non-sig n HT al nt er 72

68 Tottapatt u TTR-34 MURUGAN 5.32 RIG Commerc Permane Encroach Non-sig HT ial nt er 69 Tottapatt u TTR- THULASIR 5.4 RIG Residenti C.W Encroach Non-sig 34A AMAN HT al er 70 Tottapatt u TTR-35 Ramu 5.4 RIG Residenti Temporar Encroach Non-sig HT al y er 71 Varakkal VKR-2 N.RAMAC 5.60 RIG Residenti SemiPermane Encroach Non-sig pattu HANDRAN 5 HT al nt er 72 Varakkal VKR-3 M.KIRESI 5.60 RIG Residenti Permane Owner Non-sig pattu 7 HT al nt 73 Senjikum SL-01 Arul 5.64 LEFT Resi + Permane Encroach Non-sig arapuram Commerc nt er ial 74 Varakkal VKR-5 SEKAR 5.64 RIG Residenti Permane Encroach Non-sig pattu 5 HT al nt er 75 Senjikum SL-02 Sebagavalli 5.66 LEFT Residenti Permane Encroach Non-sig arapuram al nt er 76 Tottapatt u TTR-41 5.68 RIG Others C.W Encroach Non-sig HT er 77 Senjikum SL-04, Marimuth 5.68 LEFT Residenti SemiPermane Encroach Non-sig arapuram 05 u al nt er 78 Senjikum SL-6A Palanisam 5.7 LEFT Others C.W Encroach Non-sig arapuram y er 79 Senjikum SL-9A Ramesh 5.71 LEFT Resi + C.W Encroach Non-sig arapuram Commerc er ial 80 Senjikum SL-09 Babu 5.72 LEFT Resi + Temporar Encroach Non-sig arapuram Commerc y er ial 81 Senjikum SR-01 Bhavani 5.72 RIG Commerc Temporar Encroach Non-sig arapuram HT ial y er 82 Senjikum SL-10 Suresh 5.72 LEFT Resi + Temporar Encroach Non-sig arapuram Commerc y er ial 83 Senjikum SR-02 KIRUBAKA 5.73 RIG Residenti Temporar Encroach Non-sig arapuram RAN HT al y er 84 Senjikum SR-03 VIJI 5.73 RIG Residenti Temporar Encroach Non-sig arapuram HT al y er 85 Senjikum SL-11 Sankar 5.73 LEFT Resi + Temporar Encroach Non-sig arapuram Commerc y er ial 86 Senjikum SR-04 SARAVAN 5.74 RIG Residenti Permane Encroach Non-sig arapuram AN 5 HT al nt er 87 Senjikum SR-05 BUVANES 5.75 RIG Residenti Permane Encroach Non-sig arapuram H WARI HT al nt er 88 Senjikum SR-06 Thirugnan 5.75 RIG Resi + Permane Encroach Non-sig arapuram asamband 5 HT Commerc nt er ham ial 89 Senjikum SR-07 RAMALING 5.76 RIG Resi + Permane Encroach Non-sig arapuram AM D 5 HT Commerc nt er ial 90 Senjikum SL-15 Dhatchina 5.78 LEFT Residenti Temporar Encroach Non-sig arapuram moorthy al y er 91 Senjikum SL-14 VIJAYA 5.78 LEFT Residenti Permane Encroach Non-sig arapuram al nt er 73

92 Senjikum SL-16 Thangaras 5.79 LEFT Resi + Temporar Encroach Non-sig arapuram u Commerc y er ial 93 Senjikum SL-17 Dhanabal 5.8 LEFT Resi + Temporar Encroach Non-sig arapuram Commerc y er ial 94 Senjikum SL-18 Nallatham 5.80 LEFT Residenti Permane Encroach Non-sig arapuram bi 5 al nt er 95 Senjikum SL-19 SELVI 5.81 LEFT Residenti Temporar Encroach Non-sig arapuram al y er 96 Senjikum SL-20 RAJESHW 5.82 LEFT Residenti Permane Encroach Non-sig arapuram A al nt er RI 97 Senjikum SL-22 Srinivasan 5.86 LEFT Commerc SemiPermane Encroach Non-sig arapuram ial nt er 98 Senjikum SR-11 Rajendran 5.93 RIG Commerc C.W Encroach Non-sig arapuram HT ial er 99 Senjikum SL-26 Vasugi 5.96 LEFT Resi + Temporar Encroach Non-sig arapuram Commerc y er ial 10 Senjikum SR-12 PURUSOT 5.98 RIG Others C.W Encroach Non-sig 0 arapuram H AMMAN HT er 10 Senjikum SL-27 5.98 LEFT Commerc Temporar Encroach Non-sig 1 arapuram ial y er 10 Senjikum SL-28 DHAMOTH 5.99 LEFT Commerc Temporar Encroach Non-sig 2 arapuram ARAN S ial y er 10 Senjikum SR-13 VITHYA 6 RIG Resi + Temporar Encroach Non-sig 3 arapuram HT Commerc y er ial 10 Senjikum SL-30 CHITRA 6.03 LEFT Resi + Temporar Encroach Non-sig 4 arapuram Commerc y er ial 10 Senjikum SL-31 6.03 LEFT Commerc Temporar Encroach Non-sig 5 arapuram ial y er 10 Senjikum SL-32 6.06 LEFT Others C.W Encroach Non-sig 6 arapuram er 10 Senjikum SL-33 AMEER 6.16 LEFT Resi + Temporar Encroach Non-sig 7 arapuram SULDAN Commerc y er ial 10 Senjikum SL-34 6.18 LEFT Commerc Permane Encroach Non-sig 8 arapuram ial nt er 10 Senjikum SR-15 6.32 RIG Others C.W Encroach Non-sig 9 arapuram HT er 11 Senjikum SL-35 SAKTHIVE 6.32 LEFT Commerc C.W Encroach Non-sig 0 arapuram L ial er 11 Senjikum SL-36 RAVI G 6.35 LEFT Commerc Temporar Encroach Non-sig 1 arapuram ial y er 11 Senjikum SL-37 TAMILARA 6.38 LEFT Commerc SemiPermane Encroach Non-sig 2 arapuram SAN K ial nt er 11 Varakkal VKL-1 PERUMAL 6.41 LEFT Residenti SemiPermane Encroach Non-sig 3 pattu al nt er 114 Varakkal VKL-2 6.42 LEFT Residential Semi- Permane Encroach Non-sig pattu nt er 11 Varakkal VKR-1 K.CHANDR 6.42 RIG Others C.W Encroach Non-sig 5 pattu A HT er 74

11 Varakkal VKL-3 ANAND.S 6.49 LEFT Residenti Permane Encroach Non-sig 6 pattu al nt er 11 Varakkal VKL-4 PARAMASI 6.52 LEFT Residenti C.W Owner Non-sig 7 pattu VAM.K al 11 Varakkal VKL-5 G.RAVI 6.53 LEFT Commerc SemiPermane Encroach Non-sig 8 pattu ial nt er 11 Varakkal VKL-6 UDHAYAK 6.58 LEFT Residenti SemiPermane Encroach Non-sig 9 pattu UMAR.I al nt er 12 Varakkal VKR-6 6.68 RIG Residenti SemiPermane Encroach Non-sig 0 pattu 5 HT al nt er 12 Varakkal VKR-7 7.05 RIG Residenti Temporar Encroach Non-sig 1 pattu HT al y er 12 Varakkal VKR-8 NARAYAN 7.07 RIG Commerc SemiPermane Encroach Non-sig 2 pattu AN HT ial nt er 12 Varakkal VKR-9 VANI 7.08 RIG Residenti SemiPermane Encroach Non-sig 3 pattu 1 HT al nt er 12 Varakkal VKR-10 7.12 RIG Others Temporar Encroach Non-sig 4 pattu HT y er 12 Karamani KMR-1 KIRIJA 7.74 LEFT Residenti SemiPermane Squatter Significa 5 kuppam al nt nt 12 Varakkal KMR-3 SANTHY 7.77 RIG Residenti Permane Encroach Non-sig 6 pattu HT al nt er 12 Karamani KMR-4 SAKTHIVE 7.78 RIG Resi + SemiPermane Squatter Non-sig 7 kuppam L HT Commerc nt ial 12 Karamani KMR-5 SUMATHI 7.78 RIG Resi + SemiPermane Encroach Non-sig 8 kuppam 5 HT Commerc nt er ial 12 Karamani KMR-8 N.JAYAMO 7.8 RIG Resi + Temporary Encroach Non-sig 9 kuppam ORTHI HT Commerc er ial 13 Karamani KMR-9 KATHAYI 7.81 RIG Residenti Temporary Squatter Significa 0 kuppam HT al nt 131 Karamani KMR- 8.32 RIGH Residential Permanent Encroacher Non-sig kuppam 12 T 13 Karamani KMR- M.RAMALI 8.37 RIG Commerc Permane Owner Non-sig 2 kuppam 13 NGAM HT ial nt 13 Karamani KMR- NATARAJA 8.4 RIG Residenti Temporary Encroach Non-sig 3 kuppam 14 N HT al y er 13 Nellikupp NKL-01 B. 9.1 LEFT Resi + Permane Encroach Non-sig 4 am PRAPAVAT Commerc nt er HI ial 13 Nellikupp NKL-02 9.12 LEFT Residenti C.W Encroach Non-sig 5 am al er 13 Nellikupp NKL-03 J. 9.14 LEFT Residenti SemiPermane Encroach Non-sig 6 am KOTHISWA al nt er RARAO 13 Nellikupp NKR-01 G. 9.14 RIG Residenti Permane Encroach Non-sig 7 am RAMANI 5 HT al nt er 13 Nellikupp NKR-02 S. 9.15 RIG Commerc Temporar Encroach Non-sig 8 am JAYAMALA 5 HT ial y er 13 Nellikupp NKR-03 R. 9.16 RIG Residenti C.W Encroach Non-sig 9 am DURGABAI HT al er 14 Nellikupp NKR-04 S. KUMAR 9.16 RIG Resi + Temporar Encroach Non-sig 0 am 5 HT Commerc y er 75

ial 14 Nellikupp NKR-05 JAWAHAR 9.17 RIG Resi + Permane Encroach Non-sig 1 am SINGH 5 HT Commerc nt er ial 14 Nellikupp NKR-06 P. 9.18 RIG Residenti Permane Encroach Non-sig 2 am SUMATHI HT al nt er 14 Nellikupp NKR-07 T. 9.18 RIG Residenti C.W Encroach Non-sig 3 am DHANDAP 5 HT al er ANI 14 Nellikupp NKR-08 V. 9.2 RIG Resi + Permane Encroach Non-sig 4 am PADMINI HT Commerc nt er ial 14 Nellikupp NKL-4 K. 9.21 LEFT Commerc Temporar Encroach Non-sig 5 am LAKSHMI ial y er 14 Nellikupp NKR-09 R. 9.21 RIG Residenti SemiPermane Encroach Non-sig 6 am LOGANAT 5 HT al nt er H SINGH 14 Nellikupp NKR-10 S. RAJA 9.22 RIG Residenti Temporar Encroach Non-sig 7 am HT al y er 14 Nellikupp NKR-11 K. 9.24 RIG Residenti Temporar Encroach Non-sig 8 am RAJENDRA HT al y er N 14 Nellikupp NKR-12 9.33 RIG Others C.W Encroach Non-sig 9 am 5 HT er 15 Nellikupp NKR-13 R. 9.35 RIG Resi + Temporar Encroach Non-sig 0 am MANGALA HT Commerc y er ME ial 15 Nellikupp NKR-14 9.43 RIG Residenti Permane Encroach Non-sig 1 am HT al nt er 15 Nellikupp NKR-15 9.44 RIG Residenti Permane Encroach Non-sig 2 am HT al nt er 15 Nellikupp NKR-16 R. 9.5 RIG Commerc Temporar Encroach Non-sig 3 am MURUGAI HT ial y er YAN 15 Nellikupp NKL-06 M. 9.52 LEFT Residenti Permane Encroach Non-sig 4 am JAMBULIN al nt er GAM 15 Nellikupp NKL-05 9.52 LEFT Residenti Others Encroach Non-sig 5 am al er 15 Nellikupp NKL-07 V. 9.54 LEFT Residenti C.W Encroach Non-sig 6 am VEERAMM 5 al er AL 15 Nellikupp NKL-08 K. 9.84 LEFT Commerc Permane Encroach Non-sig 7 am THIYAGAR ial nt er AJAN 15 Nellikupp NKL-09 9.86 LEFT Commerc Temporar Encroach Non-sig 8 am ial y er 15 Nellikupp NKL-10 A. MUTHU 9.91 LEFT Resi + Others Encroach Non-sig 9 am Commerc er ial 16 Nellikupp NKL-11 PRABAKAR 9.93 LEFT Resi + Temporar Encroach Non-sig 0 am AN Commerc y er ial 16 Nellikupp NKL-12 9.93 LEFT Residenti Temporar Encroach Non-sig 1 am 5 al y er 76

16 Nellikupp NKL-13 R. 9.93 LEFT Residenti Permane Encroach Non-sig 2 am MANOKAR 5 al nt er AN 16 Nellikupp NKL-14 M. 9.94 LEFT Residenti C.W Encroach Non-sig 3 am MOHAME al er D ZUNAITH 16 Nellikupp NKL-15 9.94 LEFT Residenti C.W Encroach Non-sig 4 am 5 al er 16 Nellikupp NKL-16 9.95 LEFT Commerc Permane Encroach Non-sig 5 am 5 ial nt er 16 Nellikupp NKL-17 9.97 LEFT Residenti Permane Encroach Non-sig 6 am al nt er 167 Nellikuppa NKL-18 9.975 LEFT Commercial Temporary Encroacher Non-sign m 16 Nellikupp NKR-71 D.MOORT 10 RIG Resi + Permane Encroach Non-sig 8 am HY HT Commerc nt er ial 16 Nellikupp NKL-19 BHATHAV 10.0 LEFT Residenti Permane Encroach Non-sig 9 am ACHALAM 05 al nt er 17 Nellikupp NKL-20 P. 10.0 LEFT Residenti Permane Encroach Non-sig 0 am PATHMAN 1 al nt er ATHAN 17 Nellikupp NKR-17 DHAKSHN 10.0 RIG Residenti SemiPermane Encroach Non-sig 1 am AMOORTH 1 HT al nt er Y 17 Nellikupp NKL-21 R. 10.0 LEFT Residenti Permane Encroach Non-sig 2 am MANGALA 23 al nt er ME 17 Nellikupp NKR-18 M. 10.0 Righ Residenti Permane Encroach Non-sig 3 am VENGATES 5 t al nt er AN 17 Nellikupp NKR-19 SHEK 10.0 Righ Commerc SemiPermane Encroach Non-sig 4 am MOHIDEE 72 t ial nt er N 17 Nellikupp NKR-20 10.0 Righ Residenti SemiPermane Encroach Non-sig 5 am 85 t al nt er 17 Nellikupp NKR-21 M. 10.1 Righ Residenti Permane Encroach Non-sig 6 am HILARNISH 03 t al nt er A 17 Nellikupp NKL-22 10 Left Residenti C.W Encroach Non-sig 7 am al er 17 Nellikupp NKR-22 L. 10.1 Righ Residenti SemiPermane Encroach Non-sig 8 am GANESAN 1 t al nt er 17 Nellikupp NKR-23 S. 10.1 Righ Residenti C.W Encroach Non-sig 9 am SIVAGANA 2 t al er GI 18 Nellikupp NKL-23 10.1 Left Residenti C.W Encroach Non-sig 0 am 4 al er 18 Nellikupp NKL-24 10.1 Left Residenti Permane Encroach Non-sig 1 am 4 al nt er 18 Nellikupp NKR-24 10.1 Righ Commerc Permane Encroach Non-sig 2 am 5 t ial nt er 18 Nellikupp NKL-25 S. 10.1 Left Residenti SemiPermane Encroach Non-sig 3 am VARATHAR 55 al nt er AJAN 77

184 Nellikuppa NKR-25 R RAMKUM 10.15 Right Commercial Permanent Encroacher Non-sig m AR. 5 18 Nellikupp NKR- M. 10.1 Righ Commerc Permane Encroach Non-sig 5 am 26 LALITHA 6 t ial nt er

18 Nellikupp NKR- LOGANAY 10.1 Righ Commerc SemiPermane Encroach Non-sig 6 am 27 AGAM 7 t ial nt er

18 Nellikupp NKL-26 R. 10.1 Left Commerc Permane Encroach Non-sig 7 am UMASHAN 77 ial nt er KAR

18 Nellikupp NKL-27 P. 10.1 Left Residenti SemiPermane Encroach Non-sig 8 am GANESAN 8 al nt er

18 Nellikupp NKL-28 K. 10.1 Left Residenti Permane Encroach Non-sig 9 am VIJAYALAK 8 al nt er SHMI

19 Nellikupp NKR- LOGANAY 10.1 Righ Commerc Permane Encroach Non-sig 0 am 28 AGAM 85 t ial nt er

19 Nellikupp NKR- LOGANAY 10.1 Righ Commerc SemiPermane Encroach Non-sig 1 am 29 AGAM 89 t ial nt er

19 Nellikupp NKL-29 K. 10.1 Left Residenti Permane Encroach Non-sig 2 am MALLIGA 9 al nt er

19 Nellikupp NKR- K. 10.2 Righ Commerc Permane Encroach Non-sig 3 am 31 KAMALAK 25 t ial nt er ANNAN

19 Nellikupp NKR- P. 10.2 Righ Commerc Permane Encroach Non-sig 4 am 32 RAMALING 3 t ial nt er AM

19 Nellikupp NKR- A. RANI 10.2 Righ Commerc Permane Encroach Non-sig 5 am 33 4 t ial nt er

19 Nellikupp NKL-30 S. 10.2 Left Residenti SemiPermane Encroach Non-sig 6 am RUKUMAN 5 al nt er I

19 Nellikupp NKL-31 V. 10.2 Left Residenti Temporar Encroach Non-sig 7 am PARAMES 58 al y er HWARI

19 Nellikupp NKL-32 G. 10.2 Left Residenti Permane Encroach Non-sig 8 am SIVASHAN 65 al nt er KAR

19 Nellikupp NKL-33 10.2 Left Resi + Permane Encroach Non-sig 9 am 7 Commerc nt er ial 78

200 Nellikuppa NKL-34 10.27 Left Resi Permane nt Encroacher Non-sig m 5 Commerc ial+ 20 Nellikupp NKL-35 P. DEVAGI 10.2 Left Commerc SemiPermane Encroach Non-sig 1 am 8 ial nt er

20 Nellikupp NKL-36 KUPPU 10.2 Left Commerc SemiPermane Encroach Non-sig 2 am RAMAN 85 ial nt er

20 Nellikupp NKL-37 J. PARI 10.2 Left Commerc SemiPermane Encroach Non-sig 3 am 9 ial nt er

20 Nellikupp NKR- v. 10.3 Righ Commerc Permane Encroach Non-sig 4 am 34 NATARAJA 1 t ial nt er N

20 Nellikupp NKR- 10.3 Righ Others C.W Encroach Non-sig 5 am 35 15 t er

20 Nellikupp NKR- P. 10.3 Righ Commerc Permane Encroach Non-sig 6 am 36 RAMALING 23 t ial nt er AM

20 Nellikupp NKR- 10.3 Righ Commerc Temporar Encroach Non-sig 7 am 37 26 t ial y er

20 Nellikupp NKR- S. 10.3 Righ Commerc Permane Encroach Non-sig 8 am 38 SELVARAJ 32 t ial nt er

20 Nellikupp NKR- G. R. 10.3 Righ Resi + Permane Encroach Non-sig 9 am 39 AMUTHA 7 t Commerc nt er ial

21 Nellikupp NKR- K. THULASI 10.3 Righ Commerc Permane Encroach Non-sig 0 am 40 PRINDHA 8 t ial nt er

21 Nellikupp NKR- P. 10.3 Righ Commerc Permane Encroach Non-sig 1 am 41 RAMALING 83 t ial nt er AM

21 Nellikupp NKR- P. 10.3 Righ Commerc Permane Encroach Non-sig 2 am 42 RAMALING 85 t ial nt er AM

21 Nellikupp NKR- RENGANA 10.3 Righ Commerc SemiPermane Encroach Non-sig 3 am 43 THAN 88 t ial nt er

21 Nellikupp NKR- 10.4 Righ Commerc C.W Encroach Non-sig 4 am 44 05 t ial er

21 Nellikupp NKR- ALIRUL 10.4 Righ Commerc Permane Encroach Non-sig 5 am 45 JAMAL 1 t ial nt er

21 Nellikupp NKR- AKBAR 10.4 Righ Commerc Permane Encroach Non-sig 6 am 46 HUSSAIN 26 t ial nt er 79

217 Nellikuppa NKR- 10.44 Right Commercial C.W Encroacher Non-sig m 47 21 Nellikupp am NKR- 10.4 Righ Commerc Permane Encroach Non-sig 8 48 45 t ial nt er

21 Nellikupp am NKR- 10.4 Righ Residenti Permane Encroach Non-sig 9 49 6 t al nt er

22 Nellikupp am NKL-38 HABIBUR 10.4 Left Resi + Permane Encroach Non-sig 0 RAHMAN 6 Commerc nt er ial

22 Nellikupp am NKL-39 10.4 LEFT Residenti C.W Encroach Non-sig 1 7 al er

22 Nellikupp am NKL-40 10.4 LEFT Residenti SemiPermane Encroach Non-sig 2 75 al nt er

22 Nellikupp am NKR- 10.5 RIG Commerc Permane Encroach Non-sig 3 50 15 HT ial nt er

22 Nellikupp am NKR- T. BASKAR 10.5 RIG Commerc Permane Encroach Non-sig 4 51 2 HT ial nt er

22 Nellikupp am NKR- 10.5 RIG Commerc Temporar Encroach Non-sig 5 53 45 HT ial y er

22 Nellikupp am NKR- MOHAME 10.5 RIG Commerc Permane Encroach Non-sig 6 52 D HANEEF 45 HT ial nt er

22 Nellikupp am NKR- N. 10.5 RIG Residenti Permane Encroach Non-sig 7 54 MURUGAN 7 HT al nt er

22 Nellikupp am NKL-41 10.6 LEFT Commerc Permane Encroach Non-sig 8 ial nt er

22 Nellikupp am NKL-42 10.6 LEFT Resi + Temporar Encroach Non-sig 9 05 Commerc y er ial

23 Nellikupp am NKL-43 A. 10.6 LEFT Commerc Temporar Encroach Non-sig 0 HA 1 ial y er JA MOIDEEN 23 Nellikupp am NKR- M. 10.6 RIG Residenti SemiPermane Encroach Non-sig 1 55 MOHAME 2 HT al nt er D ABI

23 Nellikupp am NKL-44 HAMEEDH 10.6 LEFT Residenti C.W Encroach Non-sig 2 UMA 4 al er

23 Nellikupp am NKR- JAYNUL 10.6 RIG Commerc Temporar Encroach Non-sig 3 56 PUDEN 45 HT ial y er

23 Nellikupp am NKL-45 A. ADAM 10.6 LEFT Residenti C.W Encroach Non-sig 4 SHAFFI 5 al er

23 Nellikupp am NKR- JUNITHA 10.6 RIG Residenti Permane Encroach Non-sig 5 57 BEGUM 5 HT al nt er 80

23 Nellikupp am NKR- 10.6 RIG Residenti Permane Encroach Non-sig 6 58 55 HT al nt er

23 Nellikupp am NKL-46 NAZEERHA 10.6 LEFT Resi + Permane Encroach Non-sig 7 MED 6 Commercial nt er

23 Nellikupp NKL-47 Krishnamo 10.6 LEFT Residenti C.W Encroach Non-sig 8 am orthy 65 al er

23 Nellikupp NKR- NAWAZ 10.6 RIG Residenti C.W Encroach Non-sig 9 am 59 BEGUM 7 HT al er

24 Nellikupp NKL-48 ABDULRAS 10.6 LEFT Commerc Temporar Encroach Non-sig 0 am EDKHAN 7 ial y er

24 Nellikupp NKL-49 A. 10.6 LEFT Commerc SemiPermane Encroach Non-sig 1 am MOHAME 8 ial nt er D THAHEED

24 Nellikupp NKL-50 HATHEEJA 10.6 LEFT Resi + Permane Encroach Non-sig 2 am BEEVI 95 Commerc nt er ial

24 Nellikupp NKL-51 RABIYUNIS 10.7 LEFT Resi + C.W Encroach Non-sig 3 am SA Commerc er ial

24 Nellikupp NKR- REGINA 10.7 RIG Commerc Permane Encroach Non-sig 4 am 60 BEGUM 1 HT ial nt er

24 Nellikupp NKR- 10.7 RIG Residenti Permane Encroach Non-sig 5 am 61 15 HT al nt er

24 Nellikupp NKL-52 10.7 LEFT Residenti SemiPermane Encroach Non-sig 6 am 15 al nt er

24 Nellikupp NKR- 10.7 RIG Commerc Temporar Encroach Non-sig 7 am 62 17 HT ial y er

24 Nellikupp NKL-53 10.7 LEFT Residenti Permane Encroach Non-sig 8 am 25 al nt er

24 Nellikupp NKL-54 KOLANCHI 10.7 LEFT Commerc Permane Encroach Non-sig 9 am YAPPAN 27 ial nt er

25 Nellikupp NKL-55 10.7 LEFT Commerc Permane Encroach Non-sig 0 am 35 ial nt er

25 Nellikupp NKR- GAYATHRI 10.7 RIG Commerc Permane Encroach Non-sig 1 am 63 4 HT ial nt er

25 Nellikupp NKL-56 ZAHIRABY 10.7 RIG Commerc Permane Encroach Non-sig 2 am 4 HT ial nt er

25 Nellikupp NKR- 10.7 RIG Commerc Permane Encroach Non-sig 3 am 64 4 HT ial nt er

25 Nellikupp NKL-57 10.7 LEFT Commerc Permane Encroach Non-sig 4 am 5 ial nt er 81

25 Nellikupp NKR- 10.7 RIG Commerc Others Encroach Non-sig 5 am 65 57 HT ial er

25 Nellikupp NKL-58 PURUSOT 10.7 LEFT Resi + SemiPermane Encroach Non-sig 6 am H AMMAN 6 Commerc nt er ial

Nellikupp am NKR-66 10.7 RIG Commerc Permane Encroach Non-sig 25 6 HT ial nt er 7 25 Nellikupp am NKR-67 MOHAME 10.7 RIG Commerc Permane Encroach Non-sig 8 D ISMAIL 83 HT ial nt er

25 Nellikupp am NKL-59 10.7 LEFT Commerc Temporar Encroach Non-sig 9 9 ial y er

26 Nellikupp am NKL-60 S.KRISHN 10.8 LEFT Commerc Temporar Encroach Non-sig 0 A MURTHY ial y er

26 Nellikupp am NKL- ANANTHA 10.8 LEFT Commerc Temporar Encroach Non-sig 1 61.1 N 2 ial y er

26 Nellikupp am NKL-61 S.KRISHN 10.8 LEFT Commerc Temporar Encroach Non-sig 2 A MURTHY 2 ial y er

26 Nellikupp am NKR-68 JAINULAB 10.8 RIG Resi + Permane Encroach Non-sig 3 UDEEN 2 HT Commerc nt er ial

26 Nellikupp am NKR-69 NAGARAJ 10.8 RIG Commerc Permane Encroach Non-sig 4 A 22 HT ial nt er N.B 26 Nellikupp am NKR-72 10.8 RIG Commerc Permane Encroach Non-sig 5 3 HT ial nt er

26 Nellikupp am NKL-62 K.VIJAYA 10.8 LEFT Commerc Permane Encroach Non-sig 6 4 ial nt er

26 Nellikupp am NKL-63 MEGARUN 10.8 LEFT Commerc Permane Encroach Non-sig 7 NISHA 5 ial nt er

26 Nellikupp am NKL-64 REVATHI 10.8 LEFT Commerc Temporar Encroach Non-sig 8 55 ial y er

26 Nellikupp am NKR-73 HAJAMOID 10.8 RIG Commerc Permane Encroach Non-sig 9 EEN.A.R 55 HT ial nt er

27 Nellikupp am NKR-74 MOHAME 10.8 RIG Commerc Permane Encroach Non-sig 0 D ISMAIL 6 HT ial nt er

27 Nellikupp am NKL-65 BABAJOH 10.8 LEFT Commerc Temporar Encroach Non-sig 1 N 65 ial y er

27 Nellikupp am NKR-75 ABDUL 10.8 RIG Commerc SemiPermane Encroach Non-sig 2 JALEEL 65 HT ial nt er

27 Nellikupp am NKR-76 ABUSALI 10.8 RIG Commerc Temporar Encroach Non-sig 3 7 HT ial y er 82

27 Nellikupp am NKR-77 SETHURA 10.8 RIG Commerc SemiPermane Encroach Non-sig 4 MAN 75 HT ial nt er

27 Nellikupp am NKR77 DILIPCHA 10.8 Righ Resi + SemiPermane Encroach Non-sig 5 A N 75 t Commerc nt er D.J ial

27 Nellikupp am NKL-66 10.8 LEFT Commerc Permane Encroach Non-sig 6 85 ial nt er

27 Nellikupp am NKL-67 MOHAMA 10.8 LEFT Commerc Permane Encroach Non-sig 7 D ISMAIL 85 ial nt er

27 Nellikupp am NKR-78 Ujara 10.9 RIG Commerc SemiPermane Encroach Non-sig 8 Beham 05 HT ial nt er

27 Nellikupp am NKR-79 Juneetha 10.9 Commerc Permane Encroach Non-sig 9 Beham 07 ial nt er

28 Nellikupp am NKL-68 10.9 LEFT Commerc Permane Encroach Non-sig 0 15 ial nt er

28 Nellikupp am NKR-80 Santhosh 10.9 RIG Commerc Permane Encroach Non-sig 1 m 15 HT ial nt er ull 28 Nellikupp am NKR-81 Prakashm 10.9 Commerc Permane Encroach Non-sig 2 a 18 ial nt er l 28 Nellikupp am NKR-82 10.9 RIG Resi + Permane Encroach Non-sig 3 27 HT Commerc nt er ial

28 Nellikupp am NKL-69 10.9 LEFT Resi + Permane Encroach Non-sig 4 35 Commerc nt er ial

28 Nellikupp am NKL-70 V.Vengade 10.9 LEFT Commerc Permane Encroach Non-sig 5 san 4 ial nt er

28 Nellikupp am NKR-83 10.9 Resi + Permane Encroach Non-sig 6 4 Commerc nt er ial

28 Nellikupp am NKL-71 10.9 Commerc Permane Encroach Non-sig 7 5 ial nt er

28 Nellikupp am NKL-72 Akbar 10.9 LEFT Commerc Others Encroach Non-sig 8 Hussain 55 ial er

28 Nellikupp am NKL-77 10.9 LEEF Residenti Permane Encroach Non-sig 9 55 T al nt er

29 Nellikupp am NKL-73 10.9 LEFT Resi + Permane Encroach Non-sig 0 8 Commerc nt er ial 83

29 Nellikupp am NKR-84 10.9 RIG Resi + Permane Encroach Non-sig 1 8 HT Commerc nt er ial

29 Nellikupp am NKL-74 Shaik 10.9 Commerc Permane Encroach Non-sig 2 Beevi M Y 85 ial nt er

29 Nellikupp am NKR-85 Seralathan 10.9 RIG Commerc Permane Encroach Non-sig 3 9 HT ial nt er

29 Nellikupp am NKL-75 M.Ayyanar 10.9 LEFT Commerc Permane Encroach Non-sig 4 9 ial nt er

29 Nellikupp am NKL-76 10.9 LEEF Resi + Permane Encroach Non-sig 5 93 T Commercial nt er

29 Nellikupp am NKR-86 10.9 RIG Residenti Permane Encroach Non-sig 6 95 HT al nt er

29 Nellikupp am NKL-78 10.9 LEFT Residenti Permane Encroach Non-sig 7 97 al nt er

29 Nellikupp am NKL-79 CHOKKAL 11 LEFT Commerc Permane Encroach Non-sig 8 I NGAM ial nt er

29 Nellikupp am NKR-87 11 RIG Commerc Permane Encroach Non-sig 9 HT ial nt er

30 Nellikupp am NKR-88 11.0 RIG Residenti Temporar Encroach Non-sig 0 04 HT al y er

30 Nellikupp am NKR-89 KASI 11.0 RIG Commerc SemiPermane Encroach Non-sig 1 ANANDHA 15 HT ial nt er N

30 Nellikupp am NKL-81 11.0 LEFT Residenti Permane Encroach Non-sig 2 2 al nt er

30 Nellikupp am NKR-90 11.0 RIG Commerc Temporar Encroach Non-sig 3 27 HT ial y er

30 Nellikupp am NKR-91 11.0 LEFT Commerc Permane Encroach Non-sig 4 4 ial nt er

30 Nellikupp am NKR-92 11.0 RIG Resi + Permane Encroach Non-sig 5 43 HT Commerc nt er ial

30 Nellikupp am NKR-93 BALASUB 11.0 RIG Commerc Permane Encroach Non-sig 6 R 52 HT ial nt er AMANIAN. K 30 Nellikupp am NKR-94 SURESH 11.0 RIG Commerc Permane Encroach Non-sig 7 MULL 6 HT ial nt er CHORDIA

30 Nellikupp am NKR-95 TAMILSEL 11.0 Righ Commerc SemiPermane Encroach Non-sig 8 V 7 t ial nt er I 84

30 Nellikupp am NKR-96 MANIKAN 11.0 Righ Commerc Permane Encroach Non-sig 9 DAN 7 t ial nt er

31 Nellikupp am NKR-97 MUNIYAM 11.0 Righ Commerc SemiPermane Encroach Non-sig 0 MAL 77 t ial nt er

31 Nellikupp am NKL-82 11.1 LEFT Residenti Permane Encroach Non-sig 1 05 al nt er

31 Nellikupp am NKR-99 MALIK 11.1 Righ Commerc SemiPermane Encroach Non-sig 2 M.H 23 t ial nt er

31 Nellikupp am NKL-83 ABDUL 11.1 LEFT Commerc Permane Encroach Non-sig 3 HAMEED 3 ial nt er

31 Nellikuppam NKL-84 BALAKRIS 11.13 LEFT Commerci Permanent Encroacher Non-sig 4 HNAN 8 al 31 Nellikupp am NKL-85 BAHARAT 11.1 LEFT Commerc Temporar Encroach Non-sig 5 H 5 ial y er

31 Nellikupp am NKL-86 11.1 LEFT Residenti SemiPermane Encroach Non-sig 6 7 al nt er

31 Nellikupp am NKL-87 R.MURALI 11.1 LEFT Commerc Permane Encroach Non-sig 7 DHARAN 8 ial nt er

31 Nellikupp am NKL-88 A.KRISHN 11.1 LEFT Resi + Permane Encroach Non-sig 8 A 9 Commerc nt er MOORTHY ial

31 Nellikupp am NKR10 G.SAKTHI 11.2 RIG Commerc Permane Encroach Non-sig 9 0 V HT ial nt er EL 32 Nellikupp am NKR10 R.SUJATH 11.2 RIG Commerc Permane Encroach Non-sig 0 1 A DEVI 05 HT ial nt er

32 Nellikupp am NKL-89 11.2 LEFT Commerc Temporar Encroach Non-sig 1 1 ial y er

32 Nellikupp am NKR10 M.PRAKSH 11.2 RIG Commerc Permane Encroach Non-sig 2 2 CHAND 15 HT ial nt er

32 Nellikupp am NKL-90 SANJEEVI 11.2 LEFT Commerc Permane Encroach Non-sig 3 2 ial nt er

32 Nellikupp am NKL-91 R.SELVAM 11.2 LEFT Commerc Temporar Encroacher Non-sig 4 ANI 65 ial y er

32 Nellikupp am NKL-92 11.2 LEFT Resi + Permane Encroach Non-sig 5 8 Commerc nt er ial

32 Nellikupp am NKR10 11.2 RIG Commerc Permane Encroach Non-sig 6 4 85 HT ial nt er

32 Nellikupp am NKL-93 A.ROHAYA 11.2 LEFT Residenti C.W Encroach Non-sig 7 BEE 9 al er 85

32 Nellikupp am NKL-94 MOHAME 11.3 LEFT Commerc Permane Encroach Non-sig 8 D ZUNAITH ial nt er

32 Nellikupp am NKR10 11.3 RIG Residenti Permane Encroach Non-sig 9 5 1 HT al nt er

33 Nellikupp am NKL-95 SHANMUG 11.3 LEFT Commerc Permane Encroach Non-sig 0 AM 1 ial nt er

33 Nellikupp am NKL-96 11.3 LEFT Residenti Permane Encroach Non-sig 1 2 al nt er

33 Nellikupp am NKL-97 ANNASUG 11.3 LEFT Resi + Temporar Encroach Non-sig 2 ANTHA 25 Commerc y er MERCY ial

33 Nellikupp am NKR10 11.3 RIG Resi + Permane Encroach Non-sig 3 6 4 HT Commerc nt er ial

33 Nellikuppam NKL-98 DURAISAM 11.34 LEFT Commerci Permanent Encroacher Non-sig 4 Y al 33 Nellikupp am NKR10 N.PRAPAT 11.3 RIG Residenti Permane Encroach Non-sig 5 7 H 45 HT al nt er

33 Nellikupp am NKL-99 11.3 LEFT Residenti Permane Encroach Non-sig 6 6 al nt er

33 Nellikupp am NKR10 SIKKANTH 11.3 RIG Resi + Permane Encroach Non-sig 7 8 ER BASHA 6 HT Commerc nt er ial

33 Nellikupp am NKR10 G.SUSILA 11.3 RIG Residenti SemiPermane Encroach Non-sig 8 9 7 HT al nt er

33 Nellikupp am NKL- HASAN ALI 11.3 LEFT Commerc SemiPermane Encroach Non-sig 9 100 9 ial nt er

34 Nellikupp am NKL- JAHEER 11.4 LEFT Commerc Temporar Encroach Non-sig 0 101 HUSSAIN ial y er

34 Nellikupp am MKL102 KAMALAB 11.4 LEFT Commerc Temporar Encroach Non-sig 1 UBAKKAR 15 ial y er

34 Nellikupp am NKR11 PAKKIRI 11.4 RIG Commerc Permane Encroach Non-sig 2 0 MOHAME 2 HT ial nt er D

34 Nellikupp am NKR11 SHAMSUD 11.4 RIG Commerc Temporar Encroach Non-sig 3 1 EEN.M 3 HT ial y er

34 Nellikupp am NKL- ASHRAF 11.4 LEFT Commerc Permane Encroach Non-sig 4 103 ALI 3 ial nt er

34 Nellikupp am NKR11 11.4 RIG Resi + Permane Encroach Non-sig 5 2 4 HT Commerc nt er ial 86

34 Nellikupp am NKL- 11.4 LEFT Residenti Temporar Encroach Non-sig 6 105 5 al y er

34 Nellikupp am NKR11 MAHESHK 11.4 RIG Commerc SemiPermane Encroach Non-sig 7 3 UMAR 55 HT ial nt er

34 Nellikupp am NKR11 ABDUL 11.4 RIG Commerc Permane Owner Non-sig 8 4 RAZAK.A 6 HT ial nt

34 Nellikupp am NKL- SAMSUDE 11.4 LEFT Commerc Temporar Encroach Non-sig 9 106 EN.S 6 ial y er

35 Nellikupp am NKR11 S.VIJAYAL 11.4 RIG Commerc Permane Owner Significa 0 5 AKSHMI 65 HT ial nt nt

35 Nellikupp am NKL- 11.4 LEFT Commerc Temporar Encroach Non-sig 1 107 65 ial y er

35 Nellikupp am NKL- HABEEBU 11.4 LEFT Commerc Others Encroach Non-sig 2 108 R 65 ial er RAHMAN 35 Nellikupp am NKL- IYYAPPAN 11.4 LEFT Commerc Others Encroach Non-sig 3 109 7 ial er

35 Nellikupp am NKR11 11.4 RIG Resi + Permane Encroach Non-sig 4 6 7 HT Commerc nt er ial

35 Nellikupp am NKL- MUNAVAR 11.4 LEFT Commerc Others Encroach Non-sig 5 110 ALI 75 ial er

35 Nellikupp am NKR11 PATHMAN 11.4 RIG Commerc Permane Encroach Non-sig 6 7 ABAN 75 HT ial nt er

35 Nellikupp am NKL- 11.4 LEFT Commerc SemiPermane Encroach Non-sig 7 111 85 ial nt er

35 Nellikupp am NKL- PRABHU. 11.4 LEFT Commerc Permane Encroach Non-sig 8 112 M 95 ial nt er

35 Nellikupp am NKL- MUSTAFA. 11.4 LEFT Commerc SemiPermane Encroach Non-sig 9 113 D 95 ial nt er

36 Nellikupp am NKR12 ABDUL 11.4 RIG Commerc Permane Encroach Non-sig 0 0 MUTHALIP 97 HT ial nt er .A

36 Nellikupp am NKL- M.JAYARA 11.5 LEFT Commerc Temporar Squatter Significa 1 115 MAN ial y nt

36 Nellikupp am NKR12 11.5 RIG Residenti Temporar Squatter Non-sig 2 1 HT al y

36 Nellikupp am NKL- KASINATH 11.5 LEFT Commerc Permane Encroach Non-sig 3 114 AN ial nt er

36 Nellikupp am NKL- RAJAKUM 11.5 LEFT Commerc Others Encroach Non-sig 4 114A ARI ial er 87

36 Nellikupp am NKR12 RAJALAKS 11.5 RIG Commerc Permane Encroach Non-sig 5 2 HMI.R 2 HT ial nt er

36 Nellikupp am NKL- K.MANI 11.5 LEFT Commerc Temporar Squatter Non-sig 6 116 45 ial y

36 Nellikupp am NKR12 SAHABUD 11.5 RIG Residenti Permane Encroach Non-sig 7 3 E 6 HT al nt er EN.A 36 Nellikupp am NKR12 ZAHIRABY 11.5 RIG Residenti Permane Encroach Non-sig 8 4 7 HT al nt er

36 Nellikupp am NKL- 11.5 LEFT Residenti SemiPermane Encroach Non-sig 9 117 7 al nt er

37 Nellikupp am NKR12 11.5 RIG Residenti C.W Encroach Non-sig 0 5 9 HT al er

37 Nellikupp am NKL- S.UMAMA 11.6 LEFT Commerc Permane Encroach Non-sig 1 118 HESHWAR ial nt er I 37 Nellikupp am NKR11 V.SUSEND 11.6 RIG Commerc Permane Encroach Non-sig 2 8 HIRAN HT ial nt er

37 Nellikuppam NKR- PALANI.D 11.60 RIGH Residential Permanent Owner Non-sig 3 126 5 T 37 Nellikupp am NKL- GOPU 11.6 LEFT Residenti Permane Encroach Non-sig 4 119 15 al nt er

37 Nellikupp am NKR11 A.ABDULM 11.6 RIG Commerc Permane Encroach Non-sig 5 9 UNAFF 15 HT ial nt er

37 Nellikupp am NKR12 K.MUTHU 11.6 RIG Resi + Permane Encroach Non-sig 6 7 RAMAN 15 HT Commerc nt er ial

37 Nellikupp am NKR12 MAHESHK 11.6 RIG Resi + Permane Encroach Non-sig 7 8 UMAR 2 HT Commerc nt er ial

37 Nellikupp am NKR12 NANDHAG 11.6 RIG Resi + Permane Encroach Non-sig 8 9 OPAL 25 HT Commerc nt er ial

37 Nellikupp am NKR13 D.KRISHN 11.6 RIG Resi + Permane Encroach Non-sig 9 0 A GOPAL 3 HT Commerc nt er ial

38 Nellikupp am NKR13 SUBRAMA 11.6 RIG Commerc Permane Owner Non-sig 0 1 NIYAN.A 4 HT ial nt

38 Nellikupp am NKL- VENKATE 11.6 LEFT Commerc SemiPermane Encroach Non-sig 1 120 S 5 ial nt er AN.B

38 Nellikupp am NKL- PRABHAV 11.6 LEFT Commerc Permane Encroach Non-sig 2 121 ATHI 7 ial nt er 88

38 Nellikupp am NKL- N.K.SEER 11.6 LEFT Commerc Temporar Encroach Non-sig 3 122 A LAN 8 ial y er

38 Nellikupp am NKR13 T.RAVI 11.6 RIG Residenti SemiPermane Encroach Non-sig 4 2 8 HT al nt er

38 Nellikupp am NKR13 VIJAYALA 11.6 RIG Residenti Temporar Encroach Non-sig 5 3 K SHMI 85 HT al y er

38 Nellikupp am NKR13 ARUNKUM 11.7 RIG Resi + Temporar Encroach Non-sig 6 4 AR 4 HT Commerc y er ial

38 Nellikupp am NKR13 MAHADEV 11.7 RIG Commerc Permane Encroach Non-sig 7 5 AN.S 7 HT ial nt er

38 Nellikupp am NKR13 AASIAMM 11.7 RIG Commerc Permane Encroach Non-sig 8 6 A.M 8 HT ial nt er

38 Nellikupp am NKR13 JABARULL 11.8 RIG Residenti Permane Encroach Non-sig 9 7 A.A HT al nt er

39 Nellikupp am NKR13 RAMESHB 11.8 RIG Commerc Permane Encroach Non-sig 0 8 ABU 1 HT ial nt er

39 Nellikupp am NKR13 MYMUNA. 11.8 RIG Resi + SemiPermane Encroach Non-sig 1 9 D 15 HT Commerc nt er ial

39 Nellikupp am NKR14 BAVANI.S 11.8 RIG Residenti Temporar Encroach Non-sig 2 0 8 HT al y er

39 Nellikupp am NKL- ARUN 11.8 LEFT Residenti Temporar Encroach Non-sig 3 123 9 al y er

39 Nellikupp am NKL- D.SATHYA 11.9 LEFT Residenti Temporar Encroach Non-sig 4 124 NARAYAN al y er AN

39 Nellikupp am NKR14 SARAVAN 11.9 RIG Commerc Temporar Encroach Non-sig 5 1 AN.P 1 HT ial y er

39 Nellikupp am NKR14 T.KARTHIK 11.9 RIG Commerc Temporar Encroach Non-sig 6 2 25 HT ial y er

39 Nellikupp am NKR14 SUGUMAR 11.9 RIG Resi + Temporar Encroach Non-sig 7 3 3 HT Commerc y er ial

39 Keelkavar KKR-01 17.2 Righ Others Permane Encroach Non-sig 8 apattu 23 t nt er

39 Keelkavar KKL-01 Thandapan 17.5 Left Others SemiPermane Encroach Non-sig 9 apattu i R 23 nt er

40 Keelkavar KKL-02 Sankaran 17.5 Left Commerc Others Encroach Non-sig 0 apattu 4 ial er 89

40 Keelkavar KKR-02 Rajangam 17.5 Righ Residenti C.W Encroach Non-sig 1 apattu 43 t al er

40 Keelkavar KKR-03 Sankar M 17.5 Righ Residenti C.W Encroach Non-sig 2 apattu 63 t al er

40 Keelkavar KKR-04 Krishnamo 17.7 Righ Others Others Encroach Non-sig 3 apattu orthy 8 t er

40 Keelkavar KKR-05 Vasudevan 17.8 Righ Commerc SemiPermane Encroach Non-sig 4 apattu 4 t ial nt er

40 Keelkavar KKR-06 Mangai 17.9 Righ Commerc SemiPermane Encroach Non-sig 5 apattu 6 t ial nt er

40 Keelkavar KKL-03 SENTHILN 18.0 Left Commerc Permane Encroach Non-sig 6 apattu ATHAN 23 ial nt er

40 Keelkavar KKL-3 A RANGANA 18.0 Left Residenti Permane Encroach Non-sig 7 apattu THAN 25 al nt er

40 Keelkavar KKR-07 Adi 18.1 Righ Others Others Encroach Non-sig 8 apattu Narayanan 2 t er

40 Keelkavar KKR-9A 18.1 Righ Others C.W Encroach Non-sig 9 apattu 83 t er

41 Keelkavar KKR- Narayanan 18.2 Righ Residenti SemiPermane Encroach Non-sig 0 apattu 8&9 4 t al nt er

41 Keelkavar KKL-5 Dastakeer 18.4 Left Commerc Others Encroach Non-sig 1 apattu 03 ial er

41 Keelkavar KKR-10 Thirumalai 18.4 Righ Commerc Temporar Squatter Significa 2 apattu J 65 t ial y nt

41 Keelkavar KKL-07 Chinnapon 18.5 Left Commerc Temporar Squatter Significa 3 apattu nu 03 ial y nt

41 Keelkavar KKL- Jeganatha 18.5 Left Commerc Temporar Encroach Non-sig 4 apattu 8&9 n 23 ial y er

41 Keelkavar KKL-10 Sathanand 18.5 Left Resi + Permane Encroach Non-sig 5 apattu am 25 Commerc nt er ial

41 Keelkavar KKL-11 Sivanesan 18.5 Left Resi + Permane Encroach Non-sig 6 apattu G 4 Commerc nt er ial

41 Keelkavar KKL-13 Nagapoosa 18.5 Left Others C.W Encroach Non-sig 7 apattu nam 63 er

41 Keelkavar KKL- GUNASEK 18.5 Left Commerc SemiPermane Encroach Non-sig 8 apattu 13A A 83 ial nt er R 90

41 Keelkavar KKL-14 Selvi 18.6 Left Commerc SemiPermane Encroach Non-sig 9 apattu 23 ial nt er

42 Keelkavar KKL-15 JEYAKUM 18.6 Left Commerc Others Encroach Non-sig 0 apattu A 43 ial er R 42 Keelkavar KKL-16 Tamilarasi 18.6 Left Commerc Others Encroach Non-sig 1 apattu 5 ial er

42 Keelkavar KKL-17 Manavalan 18.6 Left Residenti Temporar Squatter Significa 2 apattu T 75 al y nt

42 Keelkavar KKL-18 Elayaraja T 18.6 Left Residenti Temporar Squatter Significa 3 apattu 83 al y nt

42 Keelkavar KKL-19 Deivasiga 18.6 Left Residenti Temporar Squatter Significa 4 apattu mani 95 al y nt

42 Keelkavar KKR-11 Padmanab 18.7 Righ Residenti Temporar Squatter Significa 5 apattu an 55 t al y nt

42 Keelkavar KKL-20 Nagappan 18.7 Left Residenti SemiPermane Squatter Significa 6 apattu 83 al nt nt

42 Keelkavar KKR-12 Nagamuth 18.7 Righ Residenti Temporar Squatter Significa 7 apattu u 83 t al y nt

42 Keelkavar KKL-21 Gajendiran 18.7 Left Commerc SemiPermane Encroach Non-sig 8 apattu 93 ial nt er

42 Nellikupp am NKR-70 ANSARI 18.8 RIG Commerc Permane Encroach Non-sig 9 25 HT ial nt er

43 Keelkavar KKL-22 Amutha 18.8 Left Commerc Temporar Squatter Non-sig 0 apattu 43 ial y

43 Keelkavar KKR-13 Babu 18.8 Righ Residenti Temporar Squatter Significa 1 apattu 63 t al y nt

43 Keelkavar KKL- Sukumar G 18.8 Left Others Temporar Encroach Non-sig 2 apattu 22A 63 y er

43 Keelkavar KKR14 Muthulaks 18.8 Righ Commerc SemiPermane Encroach Non-sig 3 apattu A hmi 73 t ial nt er

43 Keelkavar KKL-23 DHANALA 18.8 Left Residenti Temporar Encroach Non-sig 4 apattu KSHMI 73 al y er

43 Keelkavar KKR-14 Selvi 18.8 Righ Residenti SemiPermane Squatter Significa 5 apattu 83 t al nt nt

43 Keelkavar KKL-24 Dhatchina 18.8 Left Resi + Permane Encroach Non-sig 6 apattu moorthy 83 Commerc nt er ial 91

43 Keelkavar KKR-15 Muthukum 18.9 Righ Residenti SemiPermane Encroach Non-sig 7 apattu aran 03 t al nt er

43 Keelkavar KKR-17 19.1 Righ Others C.W Encroach Non-sig 8 apattu 43 t er

43 Keelkavar KKL- 19.2 Left Others C.W Encroach Non-sig 9 apattu 25A 03 er

44 Keelkavar KKL-25 19.2 Left Others Temporar Encroach Non-sig 0 apattu 5 y er

44 Keelkavar KKL-26 19.2 Left Others C.W Encroach Non-sig 1 apattu 84 er

44 Melkavar MKR-01 Jayabharat 19.6 Righ Residenti Permane Encroach Non-sig 2 apattu hi 04 t al nt er

44 Melkavar MKR-02 Elamaran 19.6 Righ Residenti Others Encroach Non-sig 3 apattu 35 t al er

44 Melkavar MKR-03 19.7 Righ Others Others Squatter Non-sig 4 apattu 44 t

44 Melkavar MKR-04 Subramani 19.7 Righ Others C.W Encroach Non-sig 5 apattu 64 t er

44 Melkavar MKL-03 Arumugam 19.7 Left Commerc Temporar Squatter Significa 6 apattu 84 ial y nt

44 Melkavar MKR-5 19.8 Righ Commerc SemiPermane Encroach Non-sig 7 apattu 24 t ial nt er

44 Melkavar MKR-06 KUPERA 19.9 Righ Residenti Permane Encroach Non-sig 8 apattu SELVAM 65 t al nt er

44 Melkavar MKR- BALAKRIS 19.98 Right Residential Permanent Encroacher Non-sig 9 apattu 7&8 HNAN 5 45 Panruti PTL-1 V. 20.3 LEFT Commerc Permane Squatter Significa 0 ARULDOS 25 ial nt nt S 45 Panruti PTL-4 20.5 LEFT Others C.W Encroach Non-sig 1 2 er

45 Panruti PTL-6 J. 20.6 LEFT Residenti C.W Encroach Non-sig 2 AMUTHA 2 al er

45 Panruti PTL-7 20.6 LEFT Residenti Permane Encroach Non-sig 3 25 al nt er

45 Panruti PTL-8 P. 20.6 LEFT Residenti Permane Encroach Non-sig 4 BALAMUR 45 al nt er UGAN

45 Panruti PTR-2 J. 20.6 RIG Commerc Permane Encroach Non-sig 5 S 45 HT ial nt er HALK ANSARI 92

45 Panruti PTL-9 K. 20.6 LEFT Residenti SemiPermane Encroach Non-sig 6 JAYABAL 55 al nt er A N

45 Panruti PTL-10 K. 20.6 LEFT Residenti Permane Encroach Non-sig 7 MAHALIN 65 al nt er GAM

45 Panruti PTL-11 K. 20.6 LEFT Residenti Temporar Encroach Non-sig 8 VEERAMA 7 al y er NI

45 Panruti PTR-2.A 20.6 RIG Others Others Encroach Non-sig 9 7 HT er

46 Panruti PTL-12 M. 20.6 LEFT Residenti SemiPermane Encroach Non-sig 0 RAMACHA 8 al nt er NDIRAN

46 Panruti PTL-13 R. 20.6 LEFT Residenti Temporar Encroach Non-sig 1 RAMAMO 85 al y er ORTHY

46 Panruti PTR-03 R. 20.7 RIG Others Others Encroach Non-sig 2 ABDULSA 25 HT er MATKAN

46 Panapakk am KPR-01 Cheran 22.6 Righ Residenti Permane Owner Significa 3 7 t al nt nt

46 Panapakk am KPL-01 Nagapillai 22.6 Left Commerc Permane Owner Significa 4 7 ial nt nt

46 Panapakk am KPR-02 Jeyasanka 22.6 Righ Resi + Permane Owner Significa 5 r 7 t Commerc nt nt ial

46 Panapakk am KPL- Sundhar 22.7 Left Others Others Owner Non-sig 6 02&KPR 7 -03

46 Panapakkam KPR-04 Sekar V 22.94 Left Residential Permanent Owner Significa 7 nt 46 Panapakk am KPL-04 Jeyamala 22.9 Left Residenti Permane Owner Significa 8 4 al nt nt 46 Panapakk am KPR-06 Tamilmani 23.9 Righ Others Others Owner Non-sig 9 2 t 47 Panapakk am PPL-A 24.4 Left Others Others Owner Non-sig 0 7 47 Panapakk am PPR-A Manikand 24.7 Righ Others Temporar Owner Non-sig 1 an 6 t y 47 Panapakk am PPR-B 25 Righ Others Others Owner Non-sig 2 t 47 Panapakk am PPR-01 Rajalaksh 25.2 Righ Residenti Temporar Squatter Significa 3 mi t al y nt 47 Panapakk am PPL-01 Karupayi 25.2 Left Residenti Temporar Squatter Significa 4 al y nt 93

47 Panapakk am PPR-02 Rajendiran 25.2 Righ Residenti SemiPermane Squatter Significa 5 t al nt nt 47 Thurapad TPR-A & Murugan 25.6 Righ Others Others Owner Non-sig 6 i TPL-A 5 t 47 Thurapad TPR-B Dr. 26.1 Righ Others Others Owner Non-sig 7 i Govindhar 4 t ajan 47 Thurapad TPL-B Ganesan 26.1 Left Others Others Owner Non-sig 8 i 4 47 Thurapad TPL-01 Kaliyamma 26.2 Left Residenti Permane Owner Significa 9 i l 1 al nt nt 48 Thurapad TPL-02 Selvarasu 26.2 Left Residenti SemiPermane Owner Significa 0 i 2 al nt nt 48 Thurapad TPL-3 & Navammal 26.2 Left Residenti SemiPermane Owner Significa 1 i 4 2 al nt nt 48 Thurapad TPL-05 Meera 26.2 Left Residenti SemiPermane Owner Significa 2 i 3 al nt nt 48 Thurapad TPL-06 Sakthivel 26.2 Left Residenti Permane Owner Significa 3 i 8 al nt nt 48 Thurapad TPR-01 Jeya 26.2 Righ Residenti Permane Owner Significa 4 i 8 t al nt nt 48 Thurapad TPR-02 Shankar 26.2 Righ Residenti Permane Owner Non-sig 5 i 8 t al nt 48 Thurapad TPL-07 Salma 26.3 Left Residenti SemiPermane Owner Significa 6 i 2 al nt nt 48 Thurapad TPR-03 Sudhakar 26.3 Righ Residenti Others Owner Non-sig 7 i 2 t al

48 Thurapad TPL-08 Sedhuram 26.3 Left Residenti Permane Owner Significa 8 i an 3 al nt nt

48 Thurapad TPR-04 Jeyalaksh 26.3 Righ Commerc Permane Owner Significa 9 i mi 3 t ial nt nt

49 Thurapad TPR-05 Muralidhar 26.3 Righ Residenti Permane Owner Significa 0 i an 4 t al nt nt

49 Kotlampa KTPL- Kuppusam 26.8 Left Residenti Temporar Owner Significa 1 kkam 05 y 1 al y nt

49 Kotlampa KTPL- Sriraman 26.8 Left Commerc Permane Owner Significa 2 kkam 08 1 ial nt nt

49 Kotlampa KTPL- Ravi S 26.8 Left Commerc Permane Owner Significa 3 kkam 09 1 ial nt nt

49 Kotlampa KTPL- Rajendiran 26.8 Left Residenti Temporar Owner Significa 4 kkam 12 S 1 al y nt

49 Kotlampa KTPL- Pitchai 26.8 Left Residenti Permane Owner Non-sig 5 kkam 06 1 al nt

49 Kotlampa KTPL- Kamala 26.8 Left Commerc SemiPermane Owner Non-sig 6 kkam 07 1 ial nt 94

49 Kotlampa KTPL- Ragothma 26.8 Left Residenti Temporar Owner Non-sig 7 kkam 11 n R 1 al y

49 Kotlampa KTPL- Sivakumar 26.8 Left Residenti Temporar Owner Non-sig 8 kkam 10 1 al y

49 Kotlampa KTPL- Lakshmi 26.8 Left Residenti Temporar Owner Significa 9 kkam 04 4 al y nt

50 Kotlampa KTPL- Selvam 26.8 Left Residenti SemiPermane Owner Significa 0 kkam 03 4 al nt nt

50 Kotlampa KTPL- Babu 26.8 Left Residenti Permane Owner Significa 1 kkam 01 5 al nt nt

50 Kotlampa KTPL- Akbar ali 26.8 Left Residenti Permane Owner Non-sig 2 kkam 02 azad 6 al nt

50 Kotlampa KTPL-2 Abdul 26.8 Left Residenti Others Owner Significa 3 kkam A Rahim 7 al nt

50 Anguchet MPR-1 Arumugam 28.9 Righ Commerc Permane Encroach Non-sig 4 typalaya m 38 t ial nt er

50 Anguchet MPR-2 Ramesh A 28.9 Righ Resi + Permane Encroach Non-sig 5 typalaya m 58 t Commerc nt er ial

50 Anguchet MPR-4 Rajendiran 28.9 Righ Resi + Semi- Encroach Non-sig 6 typalayam B 78 t Commerci Permanent er al 50 Anguchet MPR-3 Murugan 28.9 Righ Commerc SemiPermane Owner Significa 7 typalaya m 9 t ial nt nt

50 Anguchet MPR-5 Durai 29 Righ Residenti SemiPermane Encroach Non-sig 8 typalaya m t al nt er

50 Semakott SKR-29 M.THIRUV 30.8 Righ Others SemiPermane Encroach Non-sig 9 ai ASAGAMA 99 t nt er NI 51 Semakott SKL-39 M. 30.9 Left Residenti SemiPermane Encroach Non-sig 0 ai RAJESWA 19 al nt er R I 51 Semakott SKR-30 T. 30.9 Righ Residenti SemiPermane Encroach Non-sig 1 ai RAJATHI 19 t al nt er

51 Semakott SKL-40 M. 30.9 Left Residenti Others Encroach Non-sig 2 ai CHELLAIY 19 al er A N 51 Semakott SKR-32 E. 30.9 Righ Residenti Permane Encroach Non-sig 3 ai KANNAN 25 t al nt er

51 Semakott SKL-41 U. SEKAR 30.9 Left Residenti Temporar Encroach Non-sig 4 ai 25 al y er 95

51 Semakott SKL-42 J. SANTHA 30.9 Righ Residenti SemiPermane Squatter Non-sig 5 ai 5 t al nt

51 Semakott SKL-43 M. 30.9 Left Residenti Others Encroach Non-sig 6 ai KUTHAN 5 al er

51 Semakott SKR-37 S. 31.0 Righ Resi + SemiPermane Encroach Non-sig 7 ai SARATHA 2 t Commerc nt er MPAL ial 51 Semakott SKR-38 K. 31.0 Righ Resi + Permane Encroach Non-sig 8 ai RAGHUKU 25 t Commerc nt er MAR ial 51 Semakott SKL-44 K. PALANI 31.0 Left Residenti Others Encroach Non-sig 9 ai 3 al er

52 Semakott SKR-40 K. 31.0 Righ Resi + SemiPermane Encroach Non-sig 0 ai RAMESH 55 t Commerc nt er ial 52 Semakott SKR-41 R. VASU 31.0 Righ Residenti Permane Encroach Non-sig 1 ai 6 t al nt er

52 Semakott SKR-42 R. 31.0 Righ Residenti SemiPermane Owner Non-sig 2 ai VELAYUTH 65 t al nt AM 52 Semakottai SKR-43 K. 31.08 Righ R Permanent Owner Non-sig 3 SURESH esi + Commerc ial 52 Semakott SKR-44 A. 31.0 Righ Resi + Permane Owner Non-sig 4 ai HAIRUNNI 9 t Commerc nt SA ial

52 Semakott SKR-45 G. 31.1 Righ Residenti Permane Owner Non-sig 5 ai BALAKRIS 1 t al nt H NAN

52 Semakott SKL-45 K. 31.1 Left Residenti Temporar Squatter Significa 6 ai SELVARAJ 2 al y nt

52 Semakott SKR-46 M. 31.1 Righ Commerc SemiPermane Encroach Non-sig 7 ai SIVARMA 2 t ial nt er N

52 Semakott SKR-48 A. 31.1 Righ Residenti SemiPermane Encroach Non-sig 8 ai KAJINIMO 6 t al nt er HAMED

52 Semakott SKR-49 C. 31.2 Righ Others C.W Owner Non-sig 9 ai ALAVUDE t E N 53 Semakott SKR- 31.2 Righ Others Others Encroach Non-sig 0 ai 49A t er

53 Semakott SKR-50 P. AKBAR 31.2 Righ Residenti Temporar Encroach Non-sig 1 ai ALLI 4 t al y er 96

53 Semakott SKL-46 M. 31.2 Left Residenti Temporar Squatter Non-sig 2 ai ANJAMMA 5 al y L

53 Semakott SKR-51 B. 31.2 Righ Residenti C.W Encroach Non-sig 3 ai MEERASA 6 t al er BATSHA

53 Semakott SKL-47 KANNAPA 31.2 Left Residenti Temporar Squatter Significa 4 ai N 8 al y nt

53 Semakott SKR-52 R. 31.2 Righ Commerc Temporar Squatter Non-sig 5 ai LAKSHMI 8 t ial y

53 Semakott SKL-48 K. RANI 31.2 Left Others Temporar Squatter Non-sig 6 ai 9 y

53 Semakott SKR-54 E. 31.3 Righ Residenti SemiPermane Owner Non-sig 7 ai SHAMSUD 1 t al nt EEN

53 Semakott SKL-49 R. VASUKI 31.3 Left Residenti Temporar Encroach Non-sig 8 ai 2 al y er

53 Semakott SKR-56 V. MOHAN 31.3 Righ Residenti Temporar Owner Non-sig 9 ai RAJ 4 t al y

54 Semakott SKL-50 S. 31.4 Left Resi + Others Encroach Non-sig 0 ai PALANIVE Commercial er L 54 Semakott SKR-57 K. 31.4 Righ Residenti SemiPermane Squatter Non-sig 1 ai PARAMES 2 t al nt HVARI

54 Semakott SKR-58 T. 31.4 Righ Residenti SemiPermane Encroach Non-sig 2 ai RAGOTHA 5 t al nt er MMAN

54 Semakott SKL-52 D. 31.4 Left Commerc SemiPermane Encroach Non-sig 3 ai GUNASEK 85 ial nt er A R 54 Semakott SKR-60 A. 31.5 Righ Residenti Temporar Squatter Non-sig 4 ai KOLANJI t al y

54 Semakott SKL-53 D. 31.5 Left Commerc SemiPermane Encroach Non-sig 5 ai KATHIRVE ial nt er L

54 Semakott SKL-55 BALU.K 31.6 Left Resi + Permane Owner Non-sig 6 ai Commerc nt ial

54 Semakott SKL- BALU.K 31.6 Left Resi + Permane Owner Non-sig 7 ai 55A Commerc nt ial 97

54 Semakott SKR-66 GNANASA 31.6 Righ Commerc Temporar Encroach Non-sig 8 ai MBANDA 2 t ial y er M

54 Semakott SKR-68 P. 31.6 Righ Commerc Temporar Squatter Non-sig 9 ai SANTHAN 5 t ial y AM

55 Semakott SKR-69 GNANASE 31.6 Righ Residenti SemiPermane Owner Non-sig 0 ai K ARAN 8 t al nt

55 Semakott SKR-71 R. 31.7 Righ Resi + Permane Owner Non-sig 1 ai RAMAMO t Commerc nt ORTHY ial

55 Semakott SKR-72 G. 31.7 Righ Commerc SemiPermane Encroach Non-sig 2 ai SELVARAJ 5 t ial nt er

55 Semakott SKL-60 PERUMAL 31.7 Left Commerc SemiPermane Encroach Non-sig 3 ai 6 ial nt er

55 Semakott SKL-61 A. 31.8 Left Commerc SemiPermane Squatter Significa 4 ai PALANIAM 8 ial nt nt MAL

55 Semakott SKR-76 M. 32.0 Righ Commerc SemiPermane Encroach Non-sig 5 ai KESAVAN 2 t ial nt er

55 Thiruvam TVR-01 Kalaiyarasi 32.8 Righ Commerc Permane Encroach Non-sig 6 ur 8 t ial nt er

55 Thiruvam TVR-02 Murugavel 33.0 Righ Residenti Permane Encroach Non-sig 7 ur 55 t al nt er

55 Thiruvam TVR-04 Padmavat 33.0 Righ Residenti SemiPermane Encroach Non-sig 8 ur hi 85 t al nt er

55 Thiruvam TVR-05 Muralidhar 33.1 Righ Resi + SemiPermane Encroach Non-sig 9 ur an t Commerc nt er ial

56 Thiruvam TVL-06 Ramalinga 33.1 Left Commerc Temporar Squatter Non-sig 0 ur m 08 ial y

56 Thiruvam TVR-06 Ezhumalai 33.1 Righ Commerc Temporar Encroach Non-sig 1 ur 08 t ial y er

56 Thiruvam TVR-07 Vanitha S 33.1 Righ Commerc Temporar Squatter Non-sig 2 ur 45 t ial y

56 Thiruvam TVL-07 Sekar 33.1 Left Others Temporar Encroach Non-sig 3 ur 45 y er

56 Thiruvam TVR-08 Ramachan 33.1 Righ Commerc Temporar Squatter Non-sig 4 ur diran 46 t ial y 98

56 Thiruvam TVR-09 Kaliyaperu 33.1 Righ Commerc SemiPermane Squatter Non-sig 5 ur mal 5 t ial nt

56 Thiruvam TVR-11 Appasamy 33.1 Righ Commerc SemiPermane Encroach Non-sig 6 ur 9 t ial nt er

56 Thiruvam TVR-12 Malaiyapp 33.1 Righ Residenti Permane Owner Non-sig 7 ur an 97 t al nt

56 Thiruvam TVR-13 Sellappan 33.2 Righ Residenti Temporar Encroach Non-sig 8 ur t al y er

56 Thiruvam TVR-14 Saranya 33.2 Righ Resi + SemiPermane Encroach Non-sig 9 ur 08 t Commerc nt er ial

57 Thiruvam TVR-15 Vetrivel 33.2 Righ Resi + Permane Owner Non-sig 0 ur 2 t Commerc nt ial

57 Thiruvam TVR-16 Gopalakris 33.2 Righ Commerc SemiPermane Owner Non-sig 1 ur hnan 8 t ial nt

57 Panapakk am KPL-3 RAJENDR 33.8 LEFT Residenti Permane Owner Significa 2 A 2 al nt nt N.S 57 Thiruvam TVL- 34.3 LEFT Residenti SemiPermane Encroach Non-sig 3 ur 11.1 7 al nt er

57 Thiruvam TVL- 34.3 Left Residenti SemiPermane Encroach Non-sig 4 ur 11.2 7 al nt er

57 Thiruvam TVL-11 34.3 Left Residenti Permane Encroach Non-sig 5 ur 7 al nt er

57 Veeraper VPL-39 MUTHUKR 34.5 Left Commerc SemiPermane Encroach Non-sig 6 umanallu ISHNAN 68 ial nt er r

57 Veeraper VPL-40 T. 34.6 Left Others C.W Encroach Non-sig 7 umanallu SRIDHARA 3 er r N

57 Veeraper VPL-41 T. 34.6 Left Residenti Permane Encroach Non-sig 8 umanallu RAMAMO 38 al nt er r ORTHY

57 Veeraper VPR-57 PAZHANIY 34.7 Righ Residenti C.W Encroach Non-sig 9 umanallu AMMAL 75 t al er r 99

58 Veeraper VPR-56 S. 34.7 Righ Residenti C.W Encroach Non-sig 0 umanallu RAVICHAN 8 t al er r DRAN

58 Veeraper VPR-58 SADHASIV 34.8 Righ Residenti C.W Encroach Non-sig 1 umanallu AM t al er r

58 Veeraper VPR-59 SUGUMAR 34.8 Righ Residenti C.W Encroach Non-sig 2 umanallu 12 t al er r

58 Veeraper VPR-60 R. BALU 34.8 Righ Residenti C.W Encroach Non-sig 3 umanallu 2 t al er r

58 Veeraper VPL-42 34.8 Left Others Temporar Encroach Non-sig 4 umanallu 29 y er r

58 Veeraper VPR-61 34.8 Righ Residenti C.W Encroach Non-sig 5 umanallu 6 t al er r

58 Veeraper VPR-62 VALARMA 34.9 Righ Resi + SemiPermane Encroach Non-sig 6 umanallu THI 28 t Commerc nt er r ial

58 Veeraper VPR-01 35.3 Righ Others Others Encroach Non-sig 7 umanallu t er r

58 Veeraper VPL-01 Kumar 35.6 Left Commerc SemiPermane Encroach Non-sig 8 umanallu 9 ial nt er r

58 Veeraper VPL-43 36.2 Left Resi + Permane Encroach Non-sig 9 umanallu 5 Commerc nt er r ial

59 Veeraper VPR-03 Manivel 36.2 Righ Others Temporar Encroach Non-sig 0 umanallu 71 t y er r

59 Veeraper VPL-2A N. BABU 36.2 Left Residenti Permane Encroach Non-sig 1 umanallu 89 al nt er r

59 Veeraper VPL-02 Ravi S 36.3 Left Residenti Permane Encroach Non-sig 2 umanallu al nt er r

59 Veeraper VPR-05 Dhandapa 36.3 Righ Residenti Permane Encroach Non-sig 3 umanallu ni N 4 t al nt er r 100

59 Veeraper VPL-03 Veeran 36.3 Left Resi + SemiPermane Encroach Non-sig 4 umanallu 44 Commerc nt er r ial

59 Veeraper VPR-06 Anjali devi 36.3 Righ Resi + SemiPermane Encroach Non-sig 5 umanallu 65 t Commerc nt er r ial

59 Veeraper VPR-07 Subramani 36.3 Righ Residenti Permane Encroach Non-sig 6 umanallu yan 9 t al nt er r

59 Veeraper VPR-11 Deivasiga 36.4 Righ Residenti SemiPermane Encroach Non-sig 7 umanallu mani 34 t al nt er r

59 Veeraper VPR-12 Sarasulaks 36.4 Righ Residenti Temporar Encroach Non-sig 8 umanallu hmi 39 t al y er r

59 Veeraper VPL-04 Durairaj L 36.4 Left Commerc Permane Encroach Non-sig 9 umanallu 41 ial nt er r

60 Veeraper VPR-13 Ramalinga 36.4 Righ Residenti Permane Encroach Non-sig 0 umanallu m 55 t al nt er r

60 Veeraper VPL-06 Thavuttam 36.5 Left Residenti SemiPermane Squatter Significa 1 umanallu mal 25 al nt nt r

60 Veeraper VPR-15 Kaliyan 36.5 Righ Commerc Temporar Encroach Non-sig 2 umanallu 63 t ial y er r

60 Veeraper VPL-07 Alamelu 36.5 Left Commerc Temporar Squatter Significa 3 umanallur 78 ial y nt

60 Veeraper VPL-08 Arumugam 36.5 Left Commerc Temporar Squatter Significa 4 umanallu 8 ial y nt r

60 Veeraper VPL-09 Angalam 36.5 Left Commerc Temporar Squatter Significa 5 umanallu 85 ial y nt r

60 Veeraper VPL-10 Suresh 36.6 Left Commerc Permane Encroach Non-sig 6 umanallu ial nt er r

60 Veeraper VPR-17 Suburayal 36.6 Righ Resi + SemiPermane Encroach Non-sig 7 umanallu u t Commerc nt er r ial

60 Veeraper VPL-11 Sanjeevi 36.6 Left Commerc SemiPermane Encroach Non-sig 8 umanallu 12 ial nt er r 101

60 Veeraper VPR-18 Sankar 36.6 Righ Commerc SemiPermane Squatter Significa 9 umanallu 38 t ial nt nt r

61 Veeraper VPR-19 Arumugam 36.6 Righ Commerc SemiPermane Encroach Non-sig 0 umanallu 53 t ial nt er r

61 Veeraper VPL-14 Nagammal 36.6 Left Resi + Permane Encroach Non-sig 1 umanallu 53 Commerc nt er r ial

61 Veeraper VPL-15 Natrajan 36.6 Righ Commerc Permane Encroach Non-sig 2 umanallu 62 t ial nt er r

61 Veeraper VPR-20 Sarasu 36.6 Righ Commerc SemiPermane Encroach Non-sig 3 umanallu 62 t ial nt er r

61 Veeraper VPR-21 Thandapa 36.6 Righ Commerc SemiPermane Encroach Non-sig 4 umanallu n 65 t ial nt er r i

61 Veeraper VPL-16 Balachandi 36.6 Left Commerc Permane Encroach Non-sig 5 umanallu ran 85 ial nt er r

61 Veeraper VPL-17 Santhikant 36.6 Left Commerc Permane Encroach Non-sig 6 umanallu han 91 ial nt er r

61 Veeraper VPL-18 Maragadh 36.6 Left Commerc Permane Encroach Non-sig 7 umanallu avalli 93 ial nt er r

61 Veeraper VPR-22 Ramu D 36.6 Righ Commerc Semi- Encroach Non-sig 8 umanallur 93 t ial Permannte er

61 Veeraper VPL-19 Loganatha 36.6 Left Commerc Permane Encroach Non-sig 9 umanallu n 97 ial nt er r

62 Veeraper VPR-23 Muthaiyan 36.7 Righ Commerc Temporar Squatter Significa 0 umanallu 02 t ial y nt r

62 Veeraper VPL-20 Rukmani 36.7 Left Commerc Temporar Encroach Non-sig 1 umanallu 15 ial y er r

62 Veeraper VPL-21 Vimala 36.7 Left Resi + Permane Encroach Non-sig 2 umanallu 2 Commerc nt er r ial

62 Veeraper VPL-23 Suresh 36.7 Left Commerc Temporar Squatter Significa 3 umanallu 35 ial y nt r 102

62 Veeraper VPR-25 Ramalinga 36.7 Righ Resi + Permane Encroach Non-sig 4 umanallu m 37 t Commerc nt er r ial

62 Veeraper VPL-24 Mani 36.7 Left Commerc Permane Encroach Non-sig 5 umanallu 44 ial nt er r

62 Veeraper VPR-26 Iyyappan S 36.7 Righ Commerc Temporar Encroach Non-sig 6 umanallu 47 t ial y er r

62 Veeraper VPL-22 Prema S 36.7 Left Resi + Permane Encroach Non-sig 7 umanallu 5 Commerc nt er r ial

62 Veeraper VPR-27 Subrayalu 36.7 Righ Commerc Permane Encroach Non-sig 8 umanallu 53 t ial nt er r

62 Veeraper VPL-25 Selvaraj 36.7 Left Commerc Temporar Encroach Non-sig 9 umanallu 56 ial y er r

63 Veeraper VPL-26 Mohan 36.7 Left Commerc Temporar Encroach Non-sig 0 umanallu 6 ial y er r

63 Veeraper VPR-28 Manikand 36.7 Righ Resi + Permane Encroach Non-sig 1 umanallu an 62 t Commerc nt er r ial

63 Veeraper VPR-30 Venkatajal 36.7 Righ Commerc Permane Encroach Non-sig 2 umanallu apathy 91 t ial nt er r

63 Veeraper VPL-32 Krishnaven 36.8 Left Residenti Temporar Encroach Non-sig 3 umanallur i 17 al y er

Veeraper VPR-33 Nadarajan 36.8 Righ Commerc Permane Encroach Non-sig 63 umanallu 2 t ial nt er r 4 63 Veeraper VPL-33 Veeramani 36.8 Left Commerc Temporar Squatter Significa 5 umanallu 37 ial y nt r

63 Veeraper VPL-35 Meena 36.8 Left Residenti Temporar Encroach Non-sig 6 umanallu 5 al y er r

63 Veeraper VPR-37 Manisanka 36.9 Righ Resi + Permane Encroach Non-sig 7 umanallu r A t Commerc nt er r ial

63 Veeraper VPL-36 Fatima 36.9 Left Resi + SemiPermane Encroach Non-sig 8 umanallu Beevi 02 Commerc nt er r ial 103

63 Veeraper VPL-37 Vilvamani I 36.9 Left Commerc Others Encroach Non-sig 9 umanallu 2 ial er r

64 Veeraper VPR-41 Lakshmi 36.9 Righ Residenti Permane Encroach Non-sig 0 umanallu 4 t al nt er r

64 Veeraper VPR-42 Ramu 36.9 Righ Residenti SemiPermane Encroach Non-sig 1 umanallu 5 t al nt er r

64 Veeraper VPR-43 Jothy S 36.9 Righ Resi + Permane Encroach Non-sig 2 umanallu 61 t Commerc nt er r ial

64 Veeraper VPL-38 Indhra 36.9 Left Residenti SemiPermane Encroach Non-sig 3 umanallu 93 al nt er r

64 Veeraper VPR-48 Palani N 37.0 Righ Residenti Permane Encroach Non-sig 4 umanallu 13 t al nt er r

64 Veeraper VPR55 37.7 Righ Residenti C.W Encroach Non-sig 5 umanallu A 83 t al er r

64 Paravana PNR-01 Ayyanar V 38.8 Righ Commerc Temporar Squatter Significa 6 ndhal 73 t ial y nt

64 Paravana PNR-02 Kaliyaperu 39.4 Righ Residenti Temporar Encroach Non-sig 7 ndhal mal 8 t al y er

64 Paravana PNL-01 Ayyanar M 39.4 Left Residenti Temporar Squatter Significa 8 ndhal 95 al y nt

64 Paravana PNL-02 Moorthy 39.7 Left Residenti Temporar Encroach Non-sig 9 ndhal 14 al y er

65 Paravana PNL-03 Subramani 39.7 Left Residenti SemiPermane Squatter Non-sig 0 ndhal yan M 35 al nt

65 Paravana PNL-04 Pitchai 39.7 Left Residenti Temporar Encroach Non-sig 1 ndhal 6 al y er

65 Paravana PNR-03 Kaliyan G 39.7 Righ Residenti Temporar Squatter Significa 2 ndhal 73 t al y nt

65 Paravana PNL-05 Ravi R 39.9 Left Residenti SemiPermane Squatter Significa 3 ndhal 07 al nt nt

65 Paravana PNL-06 Subramani 39.9 Left Resi + SemiPermane Squatter Significa 4 ndhal R 18 Commerc nt nt ial

65 Kanthala vadi KVR-01 Muniyam 39.9 Righ Residenti Permane Encroach Non-sig 5 mal 6 t al nt er 104

65 Kanthala vadi KVL-01 Anthayi 39.9 Left Residenti Temporar Encroach Non-sig 6 68 al y er

65 Kanthala vadi KVL-02 Veerapathi 39.9 Left Residenti Temporar Encroach Non-sig 7 ran 75 al y er

65 Kanthala vadi KVL-03 Jeyasankar 39.9 Left Resi + SemiPermane Encroach Non-sig 8 85 Commerc nt er ial

65 Kanthala vadi KVL-04 Ganagamb 39.9 Left Residenti Temporar Encroach Non-sig 9 aram 9 al y er

66 Kanthala vadi KVR-02 Palani K 40.0 Righ Residenti Temporar Encroach Non-sig 0 6 t al y er

66 Kanthala vadi KVL-12 Anjaladevi 40.0 Left Others Temporar Encroach Non-sig 1 S 63 y er

66 Kanthala vadi KVR-03 Durai @ 40.0 Righ Residenti Temporar Encroach Non-sig 2 Arumugam 68 t al y er

66 Kanthala vadi KVR-05 Arumugam 40.0 Righ Residenti Temporar Encroach Non-sig 3 88 t al y er

66 Kanthala vadi KVR-06 Tamilselvi 40.0 Righ Residenti Temporar Encroach Non-sig 4 94 t al y er

66 Kanthala vadi KVR-07 Manikand 40.1 Righ Residenti Temporar Encroach Non-sig 5 an 12 t al y er

66 Kanthala vadi KVR-08 R K 40.1 Righ Residenti Temporar Encroach Non-sig 6 Murugan 23 t al y er

66 Kanthala vadi KVR-09 Sasikumar 40.1 Righ Residenti Permane Encroach Non-sig 7 S 33 t al nt er

66 Kanthala vadi KVR-10 Mahalinga 40.2 Righ Residenti Permane Encroach Non-sig 8 m 38 t al nt er

66 Kanthala vadi KVR-11 Subramani 40.2 Righ Residenti Temporar Encroach Non-sig 9 53 t al y er

67 Kanthala vadi KVL-15 Jayaraman 40.2 Left Residenti Temporar Encroach Non-sig 0 A 73 al y er

67 Kanthala vadi KVL-15 Sudharsan 40.2 Left Others Others Encroach Non-sig 1 B an 88 er

67 Kanthala vadi KVR-15 Subramani 40.3 Righ Residenti Permane Encroach Non-sig 2 yan 31 t al nt er

67 Kanthala vadi KVR-17 Rekha 40.3 Righ Residenti Temporar Squatter Non-sig 3 4 t al y

67 Kanthala vadi KVR-16 Ranjitha 40.3 Righ Residenti Others Encroach Non-sig 4 4 t al er

67 Kanthala vadi KVL-16 Ramalinga 40.3 Left Residenti Permane Encroach Non-sig 5 m 6 al nt er

67 Kanthala vadi KVL-18 Desinghu 40.4 Left Residenti Permane Encroach Non-sig 6 15 al nt er 105

67 Kanthala vadi KVL- Arumugam 40.4 Left Residenti Permane Encroach Non-sig 7 19&20 2 al nt er

67 Kanthala vadi KVR-20 Sundhara 40.4 Righ Residenti Permane Encroach Non-sig 8 moorthy 4 t al nt er

67 Kanthala vadi KVL-22 Gothandap 40.4 Left Residenti Permane Encroach Non-sig 9 ani 4 al nt er

68 Kanthala vadi KVR-21 Muthulaks 40.4 Righ Residenti Temporar Encroach Non-sig 0 hmi 5 t al y er

68 Kanthala vadi KVR-22 Vijaya D 40.4 Righ Residenti C.W Encroach Non-sig 1 68 t al er

68 Kanthala vadi KVR-24 Rajamani 40.4 Righ Residenti Permane Encroach Non-sig 2 85 t al nt er

68 Kanthala vadi KVR-26 Panchalai 40.4 Righ Residenti Permane Encroach Non-sig 3 98 t al nt er

68 Madapatt MDL-1 MURUGA 40.5 Left Residenti Permane Encroach Non-sig 4 u N 33 al nt er

68 Madapatt MDL-4 THIRISAN 40.5 Left Resi + Temporar Encroach Non-sig 5 u G 6 Commerc y er U ial

68 Madapatt MDL-5 DURAI 40.5 Left Residenti SemiPermane Encroach Non-sig 6 u 7 al nt er

68 Seethano MDR-1 RAJENDIR 40.5 Righ Residenti Temporar Encroach Non-sig 7 or AN 8 t al y er

68 Madapatt MDR-2 MOORTH 40.5 Righ Residenti Temporar Encroach Non-sig 8 u Y 8 t al y er

68 Madapatt MDL-9 CHENNAD 40.6 Left Others Temporar Encroach Non-sig 9 u URAI 2 y er

69 MDR-5 MANIKAN 40.6 Righ Residenti C.W Encroach Non-sig 0 DAN 7 t al er

69 Kedilam MDL-10 ASHWINI 40.7 Left Others Tempor Encroach Non-sig 1 92 ar er y 69 Madapatt MDL-11 KAMSALA 40.7 Left Residenti SemiPer Encroach Non-sig 2 u 92 al mane er nt

69 Madapatt MDL-12 GNANAM 40.8 Left Residenti C.W Encroach Non-sig 3 u OORTHY 1 al er

69 Serthanal MDR-6 PITCHAIK 40.9 Righ Commerc SemiPer Encroach Non-sig 4 lur A RN 93 t ial mane er nt

69 Madapatt MDR-7 GANDHI 41.0 Righ Commerc SemiPer Encroach Non-sig 5 u 18 t ial mane er nt 106

69 Madapatt MDR-8 KALAISEL 41.1 Righ Residenti SemiPer Encroach Non-sig 6 u V 2 t al mane er I nt

69 Madapatt MDL-14 MUTHAIY 41.1 Left Others Others Encroach Non-sig 7 u A 25 er N 69 Madapatt MDR-9 HYDER 41.1 Righ Residenti Perman Encroach Non-sig 8 u ALI 33 t al e er nt 69 Madapatt MDR-10 VENGADA 41.1 Righ Residenti SemiPer Encroach Non-sig 9 u CHALAM 5 t al mane er nt

70 Madapatt MDR-12 KESAVAN 41.1 Righ Resi + SemiPer Encroach Non-sig 0 u 78 t Commerc mane er ial nt

70 Madapatt MDR-13 MURUGA 41.1 Righ Others Tempor Encroach Non-sig 1 u N 93 t ar er y 70 Madapatt MDR-17 ARUMUG 41.2 Righ Residenti SemiPer Encroach Non-sig 2 u A 42 t al mane er M nt

70 Madapatt MDL-17 M. 41.2 Left Residenti Tempor Encroach Non-sig 3 u MANIKAN 92 al ar er DAN y

70 Madapatt MDL-18 B. 41.2 Left Residenti Tempor Encroach Non-sig 4 u AYYANAR 92 al ar er y 70 Madapatt MDL- M. KABIL 41.3 Left Commerc C.W Encroach Non-sig 5 u 19&21 13 ial er

70 Madapatt MDL-20 S. VALLI 41.3 Left Commerc Perman Encroach Non-sig 6 u 16 ial e er nt 70 Madapatt MDR-25 SATHASIV 41.3 Righ Resi + SemiPer Squatter Non-sig 7 u AM 27 t Commerc mane ial nt

70 Madapattu MDR-20 G. 41.32 Righ Commercial Tempor Encroacher Non-sig 8 ELUMALAI 8 ary 70 Madapatt MDR-22 RAMALIN 41.3 Righ Residenti Temporar Encroach Non-sig 9 u G AM 5 t al y er

71 Madapatt MDR-24 PACHAIYA 41.3 Righ Resi + Temporar Squatter Non-sig 0 u MMAL 6 t Commerc y ial

71 Madapatt MDL-22 NATARAJ 41.3 Left Residenti Temporar Encroach Non-sig 1 u A 65 al y er N 107

71 Madapatt MDR-26 RAMAR 41.3 Righ Residenti SemiPermane Encroach Non-sig 2 u 82 t al nt er

71 Madapatt MDR-27 G.ARUMU 41.3 Righ Residenti Permane Encroach Non-sig 3 u GAM 83 t al nt er

71 Madapatt MDR-28 41.3 Righ Residenti SemiPermane Encroach Non-sig 4 u 98 t al nt er

71 Madapatt MDR-29 RAJENTHI 41.4 Righ Residenti Temporar Encroach Non-sig 5 u R AN.K 11 t al y er

71 Madapatt MDL-23 SIVAKUMA 41.4 Left Commerc SemiPermane Encroach Non-sig 6 u R 2 ial nt er

71 Madapatt MDR-30 SANMUGA 41.4 Righ Residenti Permane Encroach Non-sig 7 u SUNDARA 25 t al nt er M

71 Madapatt MDL-24 KRISHNA 41.4 Left Resi + SemiPermane Encroach Non-sig 8 u M 3 Commerc nt er OORTHY ial

71 Madapatt MDL-25 SIRINIVAS 41.4 Left Commerc SemiPermane Encroach Non-sig 9 u AN 3 ial nt er

72 Madapatt MDR-31 KUPPU 41.4 Righ Residenti Permane Encroach Non-sig 0 u 38 t al nt er

72 Madapatt MDR-32 RANI.K 41.4 Righ Residenti Temporar Encroach Non-sig 1 u 4 t al y er

72 Madapatt MDL-26 ELUMALAI 41.4 Left Resi + SemiPermane Encroach Non-sig 2 u 4 Commerc nt er ial

72 Madapatt MDL-27 CHINNASA 41.4 Left Commerc Temporar Squatter Significa 3 u MY 44 ial y nt

72 Madapatt MDL-28 CHANDRA 41.4 Left Resi + Temporar Encroach Non-sig 4 u 6 Commerc y er ial

72 Madapatt MDR-33 L. 41.4 Righ Resi + SemiPermane Encroach Non-sig 5 u ARUNAGI 62 t Commerc nt er R ial I 72 Madapatt MDL-29 PRABAKA 41.4 Left Commerc SemiPermane Encroach Non-sig 6 u R AMN 64 ial nt er

72 Madapatt MDR-34 ELUMALAI 41.4 Righ Commerc SemiPermane Encroach Non-sig 7 u 7 t ial nt er 108

72 Madapatt MDL-31 S. 41.4 Left Commerc Others Encroach Non-sig 8 u GOVINDR 7 ial er A J 72 Madapatt MDL-30 RAJADUR 41.4 Left Commerc SemiPermane Encroach Non-sig 9 u A 73 ial nt er I

73 Madapatt MDR-35 T. 41.4 Righ Resi + Permane Encroach Non-sig 0 u NADARAJ 78 t Commerc nt er A ial N 73 Madapatt MDR-36 GANDHI 41.4 Righ Resi + SemiPermane Encroach Non-sig 1 u 81 t Commerc nt er ial

73 Madapatt MDR-37 PARISHA 41.4 Righ Commerc SemiPermane Encroach Non-sig 2 u BEGAM 85 t ial nt er

73 Madapatt MDR-38 SARANYA 41.4 Righ Commerc SemiPermane Encroach Non-sig 3 u 91 t ial nt er

73 Madapatt MDR-39 PALANI 41.4 Righ Commerc SemiPermane Encroach Non-sig 4 u 98 t ial nt er

73 Madapatt MDR-40 MURUGE 41.5 Righ Commerc SemiPermane Encroach Non-sig 5 u S t ial nt er AN

73 Madapatt MDL-33 RAJANGA 41.5 Left Commerc SemiPermane Encroach Non-sig 6 u M ial nt er

73 Madapatt MDR-42 RAJAMAN 41.5 Righ Commerc Permane Encroach Non-sig 7 u I 1 t ial nt er

73 Madapatt MDL-34 VIJAYAN 41.5 Left Commerc Temporar Encroach Non-sig 8 u 1 ial y er

73 Madapatt MDL-35 SUDHAKA 41.5 Left Commerc SemiPermane Encroach Non-sig 9 u R 13 ial nt er

74 Madapatt MDR- GANDHI 41.5 Righ Commerc SemiPermane Encroach Non-sig 0 u 43,44 16 t ial nt er

741 Madapatt MDL-36 GANDHI 41.52 Right Commercial Semi- Permane Encroacher Non-sig u 5 nt 74 Madapatt MDL-37 41.5 Righ Residenti Temporar Encroach Non-sig 2 u 25 t al y er 74 Madapatt MDR-41 RAJAMAN 41.5 Righ Commerc SemiPermane Encroach Non-sig 3 u I 44 t ial nt er 74 Semakott SKL-54 D. 31.5 Left Residenti SemiPermane Encroach Non-sig nt 109

4 ai KATHIRVE OO al er L 74 Veeraper VPL-38A karpagam Left Residenti Temporar Squatter Non-sig 5 umanallu al y r 74 Nellikupp NKR103 DR.MURA RIG Residenti Permane Encroach Non-sig 6 am L HT al nt er ITHARAN 74 Varakkal VKR-4 ARUMUG RIG Residenti C.W Encroach Non-sig 7 pattu A HT al er M 74 Panapakk KPR-5 Righ Others Temporar Owner Non-sig 8 am t y 1 Varakkal KMR- N.HARIDO 7.79 RIG Commerc SemiPermane Tenant Non-sig pattu 2.1 SS HT ial nt 2 Keelkavar KKR- Jesudass 18.8 Righ Commerc SemiPermane S/E Non-sig apattu 14A.1 73 t ial nt Tenant 3 Kotlampa KTPL- Murugesa 26.8 Left Residenti Temporar Tenant Non-sig kkam 11.1 n 1 al y 4 Kotlampa KTPL- Padmanab 26.8 Left Commerc SemiPermane Tenant Non-sig kkam 07.1 an 1 ial nt 5 Kotlampa KTPL- Dhanasek 26.8 Left Commerc Permane Tenant Non-sig kkam 08.1 a ran 1 ial nt 6 Kotlampa KTPL- Dhayalan 26.8 Left Commerc Permane Tenant Non-sig kkam 08.2 1 ial nt 7 Kotlampa KTPL- Sugumar V 26.8 Left Commerc Permane Tenant Non-sig kkam 09.1 1 ial nt 8 Kotlampa KTPL- Thulasinga 26.8 Left Commerc Permane Tenant Non-sig kkam 09.2 m P 1 ial nt 9 Kotlampa KTPL- Seenivasa 26.8 Left Residenti Temporar Tenant Non-sig kkam 04.1 n 4 al y 10 Semakott SKR- R. 31.0 Righ Commerc SemiPermane Tenant Non-sig ai 42.1 VELAYUT 65 t ial nt H AM 11 Semakott SKR69.1 M. 31.68 Rigth Residential Semi- Permane Tenant Non-sig ai - KIRUBAK nt A RAN 12 Nellikupp NKR-98 MAHEND 11.0. Righ Commerc SemiPermane Tenant Non-sig am R 97 t ial nt AN

Affected Common Property Resources Asset Type of S.No No Side Chainage Name of Village Affected Portion Structure

KOL- Tamil Nadu Cooperative 1 CPR-01 Left 3.02 Kondur Marketing Office Temporary

KOL- 2 CPR-02 Left 3.08 Kondur TANFED Petrol Bunk Temporary 110

KOL- Panchayat Primary 3 CPR-03 Left 3.2 Kondur school Permanent

KOL- Sri Muthumariyamman 4 CPR-04 Left 3.23 Kondur Koil Permanent

KOL- 5 CPR-05 Left 3.37 Kondur Kondur Bus Stop Permanent

KOL- Tamil Nadu Thoweed 6 CPR-06 Left 3.4 Kondur Jamath-Community hall Permanent

TTL- 7 CPR-01 Left 4.6 Thottapattu Amman temple Temporary

TTR- 8 CPR-01 Right 4.9 Thottapattu Bus stop Permanent

TTL- 9 CPR-02 Left 5 Thottapattu TNEB-Compound wall Temporary

TTR- Sri Kariya sithi 10 CPR-02 Right 5.21 Thottapattu Anjeneyar Temple Permanent

TTL- Sri Muthalu Vali amman 11 CPR-03 Left 5.27 Thottapattu koil Permanent

SL- Sri Kumaraguru 12 CPR01 Left 5.82 Senjikumarapuram Parameshwarar Koil Permanent

SR- 13 CPR01 Right 5.9 Senjikumarapuram Bus stop Permanent

KKL- 14 CPR-01 Left 18 Keelkavarapattu Bus stop Permanent

KKR- 15 CPR-01 Right 18.73 Keelkavarapattu bus stop-Annagiramam Permanent

KKR- 16 CPR-02 Right 18.73 Keelkavarapattu Compound wall Temporary

KKL- 17 CPR-02 Left 18.74 Keelkavarapattu Amman temple Temporary

KKR- Annagiramam 18 CPR-03 Right 18.78 Keelkavarapattu Panchayat Union office Temporary

KKR- Annagiramam BDO 19 CPR-04 Right 18.97 Keelkavarapattu office Temporary

KKL- Annagiramam BDO 20 CPR-03 Left 19.08 Keelkavarapattu office Temporary

KKL- Keelkavarapattu bus 21 CPR-04 Left 19.23 Keelkavarapattu stop Permanent

MKL- Pathirakali amman 22 CPR-01 Left 19.72 Melkavarapattu Statue Permanent

MKR- Sri Angalaparameshwari 23 CPR-01 Right 19.75 Melkavarapattu Temple Permanent 111

MKR- Melkavarapattu bus 24 CPR-02 Right 19.95 Melkavarapattu stop Permanent

MKL- Pathirakali amman Semi- 25 CPR-02 Left 19.95 Melkavarapattu Statue Permanent

MKL- Melkavarapattu bus 26 CPR-03 Left 19.97 Melkavarapattu stop Permanent

PTR- 27 CPR-01 Right 20.5 Housing Board Housing board Permanent

PTL- 28 CPR-01 Left 20.5 Housing Board Housing board Permanent

PTL- 29 CPR-02 Left 20.87 Muthumariamman koil Permanent

KPR- 30 CPR-01 Right 22.85 Kanisapakkam OHT tank Permanent

KPL- 31 CPR-01 Left 22.85 Kanisapakkam Sump Temporary

KPL- 32 CPR-02 Left 22.85 Kanisapakkam Pump house Permanent

KPL- 33 CPR-03 Left 23.13 Kanisapakkam Vaikal Amman Temple Temporary

TPL- 34 CPR-01 Left 25.76 Thorapadi Iyyanar koil Permanent

KTPL- Kurai Theertha 35 CPR-01 Left 26.84 Kotlampakkam mariyamman koil Permanent

MPR- 36 CPR-01 Right 28.92 Manapakkam Manapakkam bus stop Permanent

SKR- 37 CPR-01 Right 30.58 Semakottai Semakottai bus stop Permanent

SKR- Semi- 38 CPR-02 Right 30.58 Semakottai School parking area Permanent

SKL- 39 CPR-01 Left 30.69 Semakottai Bore well Temporary

SKL- 40 CPR-02 Left 30.71 Semakottai anganwadi Permanent

SKR- 41 CPR-03 Right 30.77 Semakottai Govt School Permanent

SKR- 42 CPR-04 Right 30.78 Semakottai Pump house Permanent

SKL- 43 CPR-03 Left 30.88 Semakottai Hand pump Temporary

SKL- 44 CPR-04 Left 30.98 Semakottai TV Room Permanent 112

SKL- Sri Balasubramaniyan 45 CPR-05 Left 30.98 Semakottai Koil Permanent

SKL- 46 CPR-06 Left 30.98 Semakottai Pump house Permanent

SKR- 47 CPR-05 Right 30.98 Semakottai Semakottai bus stop Permanent

SKL- 48 CPR-07 Left 31.12 Semakottai OHT tank Permanent

SKL- 49 CPR-08 Left 31.44 Semakottai Compound wall Temporary

SKR- 50 CPR-06 Right 31.75 Semakottai bus stop Permanent

SKL- 51 CPR-09 Left 31.8 Semakottai Sree Iyyanarappan koil Permanent

TVL- 52 CPR-01 Left 32.85 Thiruvamoor Putru koil Temporary

TVL- 53 CPR-02 Left 32.86 Thiruvamoor bus stop Permanent

TVR- 54 CPR-01 Right 33.12 Thiruvamoor Syntex tank Temporary

TVL- 55 CPR-03 Left 33.16 Thiruvamoor bus stop Permanent

VPR- 56 CPR-01 Right 35.25 Veeraperumanallur Pump house Permanent

VPL- 57 CPR-01 Left 35.29 Veeraperumanallur Pump house Permanent

VPL- 58 CPR-02 Left 36.14 Veeraperumanallur temple Permanent

VPR- 59 CPR-02 Right 36.54 Veeraperumanallur RCC building Permanent

VPR- 60 CPR-03 Right 36.56 Veeraperumanallur Syntex tank Temporary

VPL- 61 CPR-03 Left 36.56 Veeraperumanallur Ration shop Permanent

VPR- Old primary health 62 CPR-04 Right 36.6 Veeraperumanallur centre Permanent

VPL- Semi- 63 CPR-04 Left 36.62 Veeraperumanallur Permanent

VPR- 64 CPR-05 Right 36.74 Veeraperumanallur bus stop Permanent

VPR- 65 CPR-06 Right 36.74 Veeraperumanallur koil Temporary 113

PNL- 66 CPR-01 Left 38.82 Paravanenthal Permanent

PNL- 67 CPR-02 Left 38.875 Paravanenthal Bus stop Permanent

PNL- Hand pump, Undiyal, 68 CPR-03 Left 38.9 Paravanenthal Statue Temporary

PNL- 69 CPR-04 Left 39.5 Paravanenthal Syntex tank Temporary

PNL- 70 CPR-05 Left 39.5 Paravanenthal koil shed Temporary

KVL- 71 CPR-01 Left 40.18 Kandhalavadi Syntex tank Temporary

KVL- 72 CPR-02 Left 40.19 Kandhalavadi Pump house Permanent

KVL- 73 CPR-03 Left 40.3 Kandhalavadi Pump house Permanent

KVL- 74 CPR-04 Left 40.5 Kandhalavadi temple Permanent

KVL- 75 CPR-05 Left 40.5 Kandhalavadi bus stop Permanent

KVL- 76 CPR-06 Left 40.5 Kandhalavadi anganwadi Permanent

KVL- 77 CPR-07 Left 40.5 Kandhalavadi Ration shop Permanent

MDL- 78 CPR-01 Left 40.64 Madapattu Pump house Permanent

MDR- 79 CPR-01 Right 41.32 Madapattu Syntex tank Temporary

MDR- 80 CPR-02 Right 41.54 Madapattu OHT tank Permanent

Anguchettypalayam 81 Right 29.35 I Beedam Temporary

Appendix 1 114

Appendix 2: Participants in Consultation

Appendix 1 115

116 Appendix 1

Appendix 1 117

118 Appendix 1

Appendix 1 119

120 Appendix 1

121 Appendix 3

Appendix 3: Comparison between ADB IR Policy Requirements and RFCTLARR Act 2013 with Gap filling measures

Asian Development Bank’s Involuntary RFCTLARR Remarks and provisions in Measures to bridge S.No Resettlement Act 2013 RFCTLARR Act 2013 the Gap Policy Requirement

Policy Objectives

1 Avoid involuntary Social Impact assessment (SIA) resettlement (IR) should include: (i) whether the wherever feasible extent of land proposed for acquisition is the absolute bare minimum extent needed for the ✔ project; (ii) whether land acquisition at an alternate place has been considered and found not feasible [Ref: Section 4 sub-section 4(d) and 4(e)]

2 If IR is unavoidable, The principles of the minimise involuntary project address this resettlement by requirement. x exploring viable alternate project design 3 DPs should be The cumulative outcome of - assisted in their compulsory acquisition should be efforts to enhance or that affected persons become at least restore the partners in development leading to livelihoods of all an improvement in their post ✔ displaced persons in acquisition social and economic status and for matters connected real terms to therewith or incidental thereto preproject levels [Ref: Preamble of the RFCTLARR ACT]

Scope of Application

4 Involuntary In the definition of affected family, it acquisition of land includes ‘a family whose land or ✔ other immovable property has been acquired’ [Ref: Section 3 sub-section c (i)] 122 Appendix 3

5 Involuntary In the definition of affected family restriction of land in includes ‘family whose primary use or on access to source of livelihood for three years legally designated prior to the acquisition of the land parks and protected ✔ is dependent on forests or water areas. bodies and includes gatherers of forest produce, hunters, fisher folk and boatmen and such livelihood is affected due to acquisition of land’ [Ref: Section 3 sub-section c (vi)] Eligibility Criteria

6 Those who have In the definition of affected family, it formal legal rights to includes ‘a family whose land or land lost in its ✔ other immovable property has been entirety or in part acquired’ [Ref: Section 3 sub-section c (i)] 7 Those who do not In the definition of affected family, it have formal legal includes ‘the Scheduled Tribes and rights to land lost but other traditional forest dwellers who who have a claim to have lost any of their forest rights such land that are recognised under the Scheduled recognized or Tribes and Other Traditional Forest recognizable under Dwellers (Recognition of Forest Rights) Act, 2006 due to acquisition national laws of land’; and also includes ‘a ✔ member of the family who has been assigned land by the State Government or the Central Government under any of its schemes and such land is under acquisition’. [Ref: Section 3 sub-section c(iii) and (v)]

8 Those who have In the RP, under neither formal legal eligibility criteria, this rights nor recognised x is addressed. or recognizable claim to land lost 9 Persons who In the RP, the cut-off encroach on the area date has been after the cut-off date defined. are not entitled to compensation or any x other form of resettlement assistance. Appendix 3 123

Policy Princples

10 Carry out meaningful Whenever a SIA is required, the consultations with appropriate Government shall affected persons, ensure that a public hearing is held host communities at the affected area, after giving and concerned adequate publicity about the date, ✔ nongovernment time and venue for the public originations hearing, to ascertain the views of the affected families to be recorded and included in the SIA Report. [Ref: Section 5] 11 Establish a For the purpose of providing The RP provides for grievance redress speedy disposal of disputes a regional level GRC Mechanism to relating to land acquisition. to resolve grievances receive and facilitate compensation, Rehabilitation and in the First Level and resolution ofthe resettlement, establish, by the appellate affected persons’ notification. one or more Authorities authority at Project ✔ concerns. to be known as "the Land level as the Second Acquisition, Rehabilitation and Level of grievance Resettlement Authority" resolution [Ref: Section 51 sub-section 1] Mechanism, prior to referring/approaching the LARR authority 12 Preference to Land for land is recommended in Land for land option, landbased irrigation projects and in projects if feasible, is provided resettlement where SC/ST is involved equivalent in the EM. If not strategies for ✔ land. feasible, then cash displaced persons [Ref: Second Schedule S.No.2] compensation at whose livelihoods replacement cost has are land-based. been provided 124 Appendix 3

13 Provide physically The Rehabilitation and and economically Resettlement Award shall include displaced persons all of the following:...... (c) with needed particulars of house site and house assistance, including to be allotted, in case of displaced the following: (i) if families; (d) particulars of land there is relocation, allotted to the displaced families; secured tenure to (e) particulars of one time relocation land, subsistence allowance and better housing at transportation allowance in case of resettlement sites displaced families;...... with comparable [Ref: Section 31 sub-section 2(c), access to (d) and (e)] employment and production opportunities, integration of resettled persons ✔ economically and socially into their host communities, and extension of project benefits to host communities; (ii) transitional support and development assistance, such as land development, credit facilities, training, or employment opportunities; and (iii) civic infrastructure and community services, as required. 14 Improve the The act provides for special Special provision for standards of living of provisions and assistance for vulnerable have the displaced poor scheduled caste and scheduled been provided in and other vulnerable tribe in scheduled area. Entitlement matrix. groups, including [Ref: Section 41] women, to at least Further the act recognizes widows, national minimum ✔ (partly) divorcees and women deserted by standards families as separate families [Ref: Section sub-section (m)] The act does not recognize other vulnerable category and also SC/ST from non-scheduled areas. Appendix 3 125

15 Develop procedures Not explicitly stated Provided for in the in a transparent, RP consistent, and equitable manner if x actuation is through negotiated settlement. 16 Prepare a The Act provides for the resettlement plan preparation of Rehabilitation and elaborating on Resettlement Scheme including displaced persons time line for implementation entitlements, the [Ref: Section 16 - sub-section 2] income and livelihood restoration strategy, institutional ✔ arrangements, monitoring and reporting framework, budget and timebound implementation schedule 17 Disclose a draft The appropriate Government shall resettlement plan, ensure that the Social Impact including Assessment study report and the documentation of the Social Impact Management Plan, consultation process are prepared and made available in in a timely manner, the local language to the before project Panchayat, Municipality or appraisal, in an Municipal Corporation, as the case accessible place and ✔ may be, and the offices of the a form and District Collector, the SubDivisional language(s) Magistrate and the Tehsil, and shall understandable to be published in the affected areas, affected persons and in such manner as may be other stakeholders. prescribed, and uploaded on the Disclose the final website of the appropriate resettlement plan Government. 126 Appendix 3

and its updates to [Ref: Section 6 sub-section 1] affected persons and other stakeholders Further the commissioner shall cause the approved Rehabilitation and Resettlement Scheme to be made available in the local language to the Panchayat, Municipality or Municipal Corporation. As the case may be, and the offices of the district collector, the Sub-Divisional Magistrate and Teshil, and shall be published in affected areas, in such manner as may be prescribed and uploaded on the website of the appropriate Government [Ref: Section 18] 18 Pay compensation The Collector shall take possession The RP stipulated and provide other of land after ensuring that full that all compensation resettlement entitle payment of compensation as well and assistance will before physical or as Rehabilitation and resettlement be paid to APs at economic entitlements are paid or tendered least 1 month prior to displacement. to the entitled persons within a displacement or period of three months for the Implant the dispossession of compensation and a period of six resettlement plan assets under close ✔ months for monetary part of Rehabilitation and resettlement supervision entitlements listed in the Second throughout project Schedule commencing from the implementation date of the award made under section 30. [Ref: Section 38 - sub-section 1]

19 Monitoring and The Central Government may, The RP provides for assess resettlement whenever necessary for national or internal and external outcomes, their inter-state projects, constitute a monitoring of impacts on the National Monitoring Committee for LA,R&R standard of living of reviewing and monitoring the displaced persons, implementation of Rehabilitation and whether the and resettlement schemes or plans objectives of the under this Act. resettlement plan ✔ [Ref: Section 48 - sub-section 1] Have been achieved by taking into account the baseline conditions and the results of resettlement monitoring. Disclose monitoring reports.

127 Appendix 4

Appendix 4: Outline Semi-Annual Social Monitoring Report

Sample Outline of RP Monitoring Report

Following requirements of the ADB Safeguard Policy Statement (2009) and the Operations Manual section on safe guard policy (OMF1), borrowers/clients are required to establish and maintain procedures to monitor the status of implementation of safeguard plans and ensure progress is made toward the desired outcomes. For projects categorized as AorB in Involuntary Resettlement and/or Indigenous People, the Borrowers/clients are required to submit semi annual monitoring reports for ADB review. The level of detail and comprehensiveness of a monitoring reportis commensurate with the complexity and significance of social safeguards impacts (IR and IP) and with the current status of project implementation phase. The RP monitoring report may include the following elements:

A. Executive Summary: This section provides a concise statement of project scope and impacts, key findings and recommended actions (as applicable). B. Background of the Monitoring Report: This section provides: (i) Background/context of the monitoring report which includes information on the project project components, safeguards categorizations and general scope of the social safeguards impacts; (ii) Information on the implementation progress of the project activities, scope of monitoring report and requirements, methodology used, reporting period; (iii) Changes in project scope, if any.

C. Scope of Impacts: This section outlines the detail of (i) Scale andscopesoftheprojectimpactsoninvoluntaryresettlementsorindigenouspeopleas identified in the approved RP/IPP, (ii) Adjusted safeguard measures due to changes in project scope, if applicable (iii) Vulnerability status of the affected people, (iv) Entitlements matrix and other Rehabilitation measures, as applicable, as described in the approved final RP(s) /IPP(s).

D. Status of RP/IPP Implementation: This section provides detail and progress for the implementation of the RP/IPP. This includes various activities and institutional arrangements required prior the finalization and implementation of the RP/IPP. This section should have descriptions on:

(i) Institutional Arrangement and Capacity: This section describes the actual implementation or any adjustment made to the institutional arrangement for implementing and managing the social safeguards issues. This includes the establishment of safeguards unit/ team and appointment of staff in the EA/IA; implementation of the GRM and its committee; supervision 128 Appendix 4 and coordination between institutions involved in the management and monitoring of safeguards issues, the roles of LARRIC and women’s groups in the monitoring and implementation of the plan, if any; budget/fund availability for implementing the GRM, RP/IPP; adequacy of EA/IA capacity to manage safeguards issues; updated RP/IPP implementation schedule, etc. (ii) Compensation and Rehabilitation: This section describes the process and progress of the implementation of the land acquisition and resettlement (LAR) and/or indigenous people (IP) impacts mitigation activities as determined in the RP. This includes payment of the affected assets compensation, allowances, loss of incomes, etc. to the entitled persons; provisions of other types of entitlement as described in the matrix and implementation of livelihood Rehabilitation activities as determined in the plan. Quantitative as well as qualitative results of the monitoring parameters, should be provided. (e.g., adequacy of compensation rates and timeliness of payments, adequacy and timeliness of IR Rehabilitation measures including preparation of the replacement housing sites, house reconstruction, livelihood support measures, and training, etc.). Any discrepancies that may occur from the approved RP/IPP during the implementation should be explained. (iii) Disclosure and public consultation: This section describes public disclosure and consultations activities during the project’s implementation as agreed in the plan. This includes final consultations with APs during RP finalization after the completion of detail design and final DMS survey; the numbers of activities conducted; issues raised during consultations and responses provided by the project team, implementing LARRICs, project supervision consultants, contractors; project reports posted on website, etc. (iv) Grievance Redress Mechanism (GRM): This section described the implementation of project GRM as design in the approved RP/IPP. The monitoring and evaluation include its readiness, effectiveness, procedures, complaints receive, timeliness to resolve issues/ complaints and adequacy of resources provided to solve the complaints. Special attentions should be given if there are complaints received from the affected people or communities.

E. Summary Monitoring Results and Key Findings: This section describes the summary and key findings of the monitoring activities. The results are compared against previously established benchmarks and compliance status or resolutions/follow up of previously identified issues. It also compared against the objectives of safeguards or desired outcomes (e.g. IR impacts avoided or minimized; livelihood restored or enhanced).

F. Compliance Status: This section summarizes the compliance status of the project activities with the loan covenants, ADB SPS (2009) on SR2.

G. Follow up Actions, Recommendation and Disclosure: This section describes recommendations and further actions or items to focus on for the remaining monitoring period. If noncompliance or any major gaps identified, include the recommendation of corrective action plan. It also includes lesson learned for improvement for future safeguards monitoring activities. Disclosure dates of the monitoring report to the affected communities should also be included and, as needed, a time-bound summary table for required actions.

H. Appendices: (i) List of Affected Persons and Entitlements (ii) Summary of the survey results(from the external monitor) Appendix 4 129

(iii) Copies of AP’s certification of payment (signed by the APs) (iv) Summary of minutes of meetings during public consultations (v) Summary of complaints received and solution status (vi) Photographs of the affected areas, consultation meetings, housing reconstruction activities etc.

130 Appendix 5

APPENDIX 5: TERMS OF REFERENCE (TOR) FOR THE LARRIC/AGENCY TO ASSIST LARRU IN RESETTLEMENT PLAN IMPLEMENTATION

A. Project Background

1. Government of Tamil Nadu (GoTN) is implementing the Chennai – Kanyakumari Industrial Corridor Project (CKICP) that aims at improving 15 State Highways to a length of about 655 km.

2. The roads taken up under CKICP are proposed to be implemented in 9 packages under Engineering, Procurement Construction contract (EPC). The proposed improvements include widening and strengthening of some existing two-lane roads to two-lane with paved shoulders/ four lane, provision of drainage facility, road furniture and accessories. The project roads traverse across 18 Districts.

3. A Resettlement Plan (RP) for each EPC road stretches is being prepared separately based on census and baseline socio-economic surveys conducted in the field. The RP describes: (i) the project components that cause involuntary resettlement; (ii) initial inventory of losses and socio economic characteristics of the affected people; (iii) an entitlement matrix (i.e. R&R policy); (iv) a methodology for the valuation of assets;(iv) institutional and implementation arrangements required to mitigate adverse impacts; and (v) budget and time line for RP implementation.

4. One R&R Monitoring Unit at the PIU Head Quarters, Chennai and four Land Acquisition and Rehabilitation and Resettlement Field Units (LARRU) are being formed for carrying out private land acquisition and RP implementation. Chennai – Kanyakumari Industrial Corridor Project (CKICP) is the implementing agency of the project. Chennai – Kanyakumari Industrial Corridor Project (CKICP) proposes to appoint a consultant/ LARRIC experienced in carrying out such rehabilitation and resettlement activities at the grass root level to assist the PIU in RP implementation works.

5. The list of road stretches taken up for improvement under CKICP is tabulated below. The tentative extent of LA and the number of PAP is also indicated.

Table A50: Road stretches taken up for improvement Total LA PAP Package Sl. No. Road Length (in (in Ha) (*tentative) No. km) 1 Tiruchendur to Ambasamudram via Palayamkottai (SH 40) 74.9 21.7930 400 2 Melur to Karakikudi via Tirupattur, Kundrakudi(SH 191 & SH 191A) 46.9 8.0057 300 3 Thanjavur to Mannargudi(SH 63) 27.59 9.9116 350

4 Kumbakonam to Mannargudy (SH 66) 34.26 6.1396 850 CKIC/ 5 Kumbakonam to Sirkazhi(SH 64) 38.07 30.0350 2500 LARRIC/01 6 Mayiladuthurai to Thiruvarur (SH 23) 31.28 36.0450 900 7 Kumbakonam to Sirkazhi (SH 64) Junction (SH 9) 40.6 108.4000 700

Total 293.6 220.3299 6000 Appendix 5 131

Total LA (in Ha) PAP Package Sl. No. Road Length (in (*tentative) No. km) 1 Mohanur – Namakkal – Senthamangalam-Rasipuram Road (SH95) 46.44 59.2970 500 2 Tiruchengode to Erode(SH 79) 10.27 12.2900 800

3 Thuraiyur to Perambalur(SH 142) 31.49 14.8370 300

Omalur to Tiruchengode via Sankakiri including 4 Tiruchengode Bypass (SH 86) 54.8 92.0470 1900

5 Chengalpattu – Kanchipuram Road (SH 47.31 62.7440 800 58) (60/037-107/350) CKIC/ 6 Chengelpet to Kancheepuram (SH 58) (30/0 - 39.75 26.9770 700 LARRIC/02 60/037) 7 Cheyyur (ECR) to Polur(SH115) including ECR link 110 19.5350 300 8 Virudhachalam to (SH 69) 20.88 10.9240 700

Total 360.94 298.6510 6000

*PAP details given as above are tentative and exact numbers shall be decided based on final verification survey by the implementation consultants. No variation cost will be allowed upto 10% increase or decrease in number of PAPs.

B. Objectives of the Assignment

6. CKICP is recruiting RP implementing Consultants/LARRIC. The overall objective of the consultancy services is to assist the PIU in the updation& implementation of RPs for the Project Roads and shall be responsible for the following in accordance with the RP.

7. The consultants / LARRIC should Under Supervision of LARRU, CKICP, verify Project Affected Persons (PAPs) list and inventory of loss of assets. Submission of Microplans containing complete details of PAPs eligible and ineligible to receive R&R assistance, to the LARRU.

8. Under CKICP supervision, establish and maintain a Computerized Management Information System (CMIS) with details of all information related to the inventory of lost assets, completely collected PAP information, impact on community assets, PAP payments and relocation progress.

9. Support LARRU, CKICP in identifying the resettlement sites in consultation with PAPs

10. Support LARRU, CKICP in disbursement of compensations and relocation of affected community assets in close consultation with PAPs and in publishing of Microplans containing details of both eligible and ineligible PAPs to receive R&R entitlements

11. Assist PAPs in getting employment with contractors, for those interested, based on the skill of the PAPs. Identification of vulnerable PAPs/family members who can be provided with skill based training to improve their livelihood and employment opportunities 12. Helping PAPs in collecting their documentation as needed for receiving compensation and assistance, with LARRU and GRC.

132 Appendix 5

13. Assisting PAPs in opening bank accounts, getting their benefits from the bank, attending the queries raised by the bank or IT department with respect to the compensation of LA & RR.

14. Disseminate project impacts and information on Entitlement Matrix (R&R Policy).

15. Conduct regular consultations with PAPs and ensure participation of women.

16. Supporting Project Implementation Unit (PIU) in social responsibilities of the subproject, such as compliance with labour laws and international core labour standards (i.e. prohibition of child labour, forced labour, no discrimination).

17. Conduct community awareness program for road safety for communities along all project roads, with the location and number of such programmes being identified by LARRU.

18. Conduct awareness program for HIV/AIDs, Health and Hygiene in worksites/labour camps.

19. Collect data and submit progress reports on a monthly and quarterly basis for PIEto monitor the progress of RP implementation and other social responsibilities.

20. Assist CKICP-LARR unit in sucessfull implementation of RP

C. Scope of Work

1. Supporting the PIU, LARRUs, FIU

21. Working in co-ordination with the Resettlement Officer (RSO) in the LARRU; and assist the RSO in carrying out the implementation of the RP for each road in the package.

22. Conduct verification survey of PAPs (titled and non-titled), of the inventory of lost assets and impacts on community structures based on actual limitations of works.

23. Consultant/LARRIC shall verify the information already contained in the RP and the individual losses of the PAPs. They should validate the data provided in the RP and report to CKICP –LARRU (PIU & FIU) on changes required, if any, along with documentary evidence.

24. Update the census survey and socio-economic survey records and collect additional information required for the preparation of the micro plan and for disbursement.

25. Preparing error free micro plan one in English and one in Tamil based on the field verified data separately for non-titleholders and titleholders as per the approved Entitlement

26. Matrix (R&R Policy). The microplans should be submitted for all PAPs who are found to be eligible and ineligible for R&R assistance, after confirmation through joint verification

27. Assisting the RSO in disclosure of microplans in Tamil & English version for both eligible and ineligible PAPs, in the offices of Town Panchayat / Village Panchayat and Village Administrative Officers office, conducting R&R award enquiries conducting public meetings, information campaigns during the RP implementation and give full information to the affected community. Prepare one-page leaflets with key impacts and entitlements and contact information for questions/grievances in English and Tamil to distribute to PAPs and post notices in key Appendix 5 133 locations. Prepare brochure detailing all entitlements as per the Entitlement Matrix/R&R Policy in English and Tamil with project contact information.

2. Disclosing and disseminating the RP to PAPs

28. Under the supervision and guidance of CKICP, establish and maintain a Computerized Management Information System (CMIS) with information of all affected titled and non-titled persons, with appropriate km location, with inventory of losses as per the Entitlement Matrix/R&R Policy, information on affected community structures and information of payment and relocation progress.

29. Provide data, maintain data and generate reports of the information that PIU will require in the management of the data base of the PAPs. Maintenance will also include updating of data, correction of data and ensuring that error free data are submitted in Micro plans.

30. Assist CKICP-LARR Unit in providing training to PAPs, wherever required during the implementation of RP.

31. During or after LA award enquiry, the consultant / LARRIC should prepare census survey records for all title holders and socio-economic survey record wherever required, and enter the same in the web application. The consultant/LARRIC must monitor the payment progress of title- holders and reflect this in monitoring system that identifies location of title-holders on a linear, kilometre basis. Ensure CMIS contains information on vulnerable PAPs as prescribed in the RP. Assist the LARRU in disclosure of microplans of Title-

32. Holders both eligible and ineligible in the offices of Town Panchayat / Village Panchayat and Village Administrative Officers office

33. Based on the verification and update of the census and socio economic survey data and additional particulars collected for the preparation of the micro plan and for disbursement, the Consultant/LARRICs should update all the above particulars(viz. Data from all parts of the application/format) in the CMIS/web application.

34. Take photograph of the PAP & assets and upload the same in the CMIS/web application for generating identity cards and for identifying the assets.

35. Support in the timely distribution of identity and entitlement cards.

36. Assist the LARRU in award enquiry by providing necessary particulars. Assist the

37. LARRU in identification of absentee PAPs.

38. Assist LARRU - CKICP in payment of compensation / Assistance to non titled- holders.

39. Submit monthly and quarterly progress report to the RSO including both physical and financial progress in RP implementation. The report should also cover implementation issues, summary of grievances and summary of consultations.

40. Assist LARRU, CKICP and the PAPs in documenting grievances received and resolution of Grievance Redressal Committees.

134 Appendix 5

41. Assist LARRU, CKICP in conducting regular consultations with PAPs and ensuring women participation.

42. Prepare monthly action plans with targets in consultation with the RSO and LARRU.

3. Assistance to PAPs

43. The Consultants/LARRICs shall establish rapport with PAPs, consult and provide information to them about the respective entitlements as proposed under the RP, and

44. distribute Identity Cards to the eligible PAPs of the Roads. The identity card should include a photograph of the PAPs with address generated from web.

45. During the verification of the eligible PAPs, the Consultants/LARRICs shall ensure that each of the PAPs are contacted and consulted either in groups or individually. The Consultants/LARRICs shall specially ensure consultation with women from the affected families especially women headed households. Conduct Focus-Group Discussions with women to ensure their regular consultations. Documenting of all consultations to be done.

46. The Consultants/LARRICs shall develop rapport between the PAPs and the Project Authority, particularly the RSO. This will be achieved through regular interactions with both the RSO and the PAPs. Meetings with the RSO will be held at least fortnightly, and consultation meetings with the PAPs will be held monthly, during the entire duration of the assignment. All consultation meetings and decisions taken shall be documented by the Consultants/LARRIC.

47. The Consultants/LARRICs shall display the list of eligible and ineligible PAPs in prominent public places in villages and Panchayat offices.

48. Participatory methods should be adopted in assessing the needs of the PAPs of the roads, especially with regard to the vulnerable groups of PAPs / Selection of family members of vulnerable groups for skill development training. The methods of contact may include village level meetings, gender participation through group’s interactions, and individual meetings and interactions.

49. The Consultants/LARRICs shall explain to the PAPs of the roads, the provisions of the policy and the entitlements under the RP. This shall include communication to the roadside squatters and encroachers about the need for the timely shifting, the timeframe for disbursement of their entitlement.

50. Assist the PAPs (Titled and Non-Titled) in collecting the proper documentation to obtain their awards (in case of titled affected person) and other entitlements (in case of titled and non- titled affected persons).Helping PAPs in documentation as needed for receiving compensation and assistance.

51. Obtaining of options and choices of displaced PAP’s in particular from those eligible for house site and housing assistance and record the same.

52. Based on the options and choices obtained and assessment of major impacted residential / commercial PAPs, assess the requirement of resettlement site, its location in consultation with RSO and assist LARRU in identifying the resettlement sites in consultation with displaced PAP’s.

Appendix 5 135

53. The Consultants/LARRICs shall disseminate information to the PAPs of the roads, on the possible consequences of the project on the communities’ livelihood systems and the options available, so that they do not remain ignorant.

54. The Consultants/LARRICs shall assist the PAPs in opening bank accounts explaining the implications, the rules and the obligations of a joint account and how she/he can access the resources she/he is entitled to.

55. Assist PAPs in getting employment with contractors, for those interested, based on the skill of the PAPs.

56. The Consultants/ LARRICs shall facilitate the PAPs in finding suitable economic investment options and help them in regaining the losses of land and other productive assets. 57. Assisting the PAPs in redressing their grievances through the GRCs;

58. The Consultants/LARRICs shall make the PAPs aware of the existence of Grievance Redressal Committee (GRCs) the process involved in submitting a representation and timeline for resolving grievances.

59. This will also include assisting PAPs in submitting their petitions and sufficient evidence to Grievance Redressal Cell, in coordination with LARRU.

60. Accompanying and Representing the PAPs at the Grievance Committee Meetings.

61. The Consultants/LARRICs shall help the PAPs in lodging their grievances and also in clearing their doubts about the procedure as well as the context of the GRC award.

62. To accompany the PAPs to the GRC meeting on the decided date, help the PAPs to express his/her grievance and again inform the PAPs of the decisions taken by the GRC within 3 days of receiving a copy of the decision from the GRC.

4. Other/ General responsibilities:

63. In all of these, the Consultants/ LARRIC’s shall consider women as a special focus group, and deal with them with care and sympathy.

64. The Consultants/LARRICs shall assist the project authorities in ensuring a smooth transition (during the part or full relocation of the PAPs), helping the PAPs to take salvaged materials and shift. In close consultation with the PAPs, the Consultants/ LARRICs shall inform the RSO about the shifting dates agreed with the PAPs in writing and the arrangements desired by the PAPs with respect to their entitlements.

65. The Consultants/LARRICs shall record the Grievance and bring it to the notice of the GRCs within seven days of receipt of the grievance from the PAPs, suggest multiple solutions, if possible, and deliberate on the same in the GRC meeting along with the PAPs concerned.

66. Carry out Public consultation on regular interval, consult major impacted at least once in a month and document the discussions and outcome.

67. Should organize meetings and appraise the communities about the schedule / progress of civil works. 136 Appendix 5

68. In additional to counselling and providing information to PAPs, the Consultants/ LARRICs will carry out periodic consultation with PAPs and other stakeholders.

69. All the consultations should be documented and if possible, photographs and attendance sheets should be compiled along with the list of participants and a summary of the consultation and outcome.

70. The RP includes provision for internal monitoring by PIU and quarterly, mid-term monitoring and evaluation by external agency. The Consultants/LARRICs involved n the implementation of the RP of the roads will be required to supply all information, documents to the PIU, Project Monitoring Consultant and external monitoring consultants.

71. Help LARRU, CKICP in identifying the resettlement sites in consultation with PAPs .

72. Help LARRU, CKICP in relocation of affected community assets in close consultation with PAPs.

73. Any other tasks in realising the objective.

74. Assisting the PIU with the Project’s other Social Responsibilities.

75. To assist the PIU in ensuring that the EPC Concessionaire comply with the applicable labour laws (including prohibition of child labour, bonded labour and gender requirements) as contained in the EPC Agreement.

76. To assist the PIU in ensuring compliance with safety, health and hygiene norms, and the conduct HIV/AIDS and Human Trafficking awareness/prevention campaigns for the labourers.

77. The Consultants/LARRICs shall assist the PIU to implement Community Road Safety awareness measures, including collaboration with the line agencies. These programmes should be a minimum of six in number per road and ensure it targets vulnerable groups (i.e. professional drivers, schoolchildren, etc.).

D. Reporting and Documentation

78. The Consultants/LARRICs selected for the assignments of the roads shall submit the following reports in the frequency indicated.

79. Submit an inception report within three weeks; in signing up of the contract including a work plan for the whole contract period, staffing and personnel deployment plan, and a withdrawal plan at the end of the period of contract. The withdrawal plan shall be detailed and reflect how the PAPs will maintain the assets created and transferred to the PAPs.

80. Prepare monthly progress reports to be submitted to the Special DRO (LA), that details weekly progress and work charts as against the scheduled timeframe of RP implementation.

81. Prepare and submit quarterly reports on a regular basis, to be submitted to PIU, CKICP.

Appendix 5 137

82. Submit a completion report at the end of the contract period summarizing the actions taken during the project, the methods and personnel used to carry out the assignment, a summary of support/ assistance given to the PAPs and lessons learnt and best practices.

83. Record minutes of all meetings and include in the respective reports.

84. Four copies of each report shall be submitted to PIU, CKICP together with one soft copy of each report in the CD.

E. Deliverables and Timeline

85. It is estimated that the LARRICs/Consultants services will be required for about 24 months to undertake the assignment of facilitating the implementation of the RP. The time schedule for completion of key tasks is given below.

Table A51: Key tasks and time for completion Sl.No Task Description Time for completion 1 Inception Report At the end of the 2nd week after commencement of services

2 Joint verification with CKICP Field team of the PAPs, and Priority roads, at the end of the 45 Providing required inputs for updating the Resettlement days and 75 days for other roads Plan for the Priority roads and Other roads as per the after commencement of services. requirement of ADB

Issue of identity card and submission of corrected data, if At the end of the 4th month after 3. any, including proposal for replacement and up gradation commencement of services of community assets, Collecting Additional and /or missing census survey records of PAPs (to be collected only after due approval of such cases by RSO in writing) including profiles of DP in such survey along with additional particulars required for preparation of micro plan for eligible and ineligible PAPS for R&R and disbursement, and updating the same in web application 4 Assist in identification of resettlement site and At the end of the 6th month after development of the same commencement of services 5 Monthly Progress Report /Quarterly Progress Report At the end of each month covering the activities in the scope of works and /quarter corresponding deliverables 6 Facilitating disbursement of the entitlements for 25% of At the end of the 6th month after total PAPs for whom micro plan is submitted and commencement of services compensation disbursed coinciding with the milestone fixed by CKIC 7 Disbursement of the entitlements for another 25% of total At the end of the 9th month after PAPs for whom micro plan is submitted and commencement of services compensation disbursed coinciding with the milestone fixed by CKIC 8 Disbursement of the entitlements for another 25% of total At the end of the 12th month PAPs for whom micro plan is submitted and after commencement of services compensation disbursed coinciding with the milestone fixed by CKIC 138 Appendix 5

Sl.No Task Description Time for completion 9 Facilitate PAPs to relocate to resettlement site At the end of the 14th month after commencement of services 10 Disbursement of the entitlements for remaining 25% of At the end of the 15th month total PAPs for whom micro plan is submitted and after commencement of services compensation disbursed coinciding with the milestone fixed by CKIC 11 Draft Final Report summarizing the action taken and other One month before the service / resettlement works to be fulfilled by the LARRIC 23rd month after commencement of services 12 Final report summarizing the action taken and other At the end of the service / 24th resettlement works to be fulfilled by the LARRIC month after commencement of services incorporating suggestions of CKICP on the draft report.

F. Payment Schedule

86. The payment will be made on successful completion of key tasks is given below. Based on the recommendations of the DRO (LA), CKIC, the Divisional Engineer (H), CKIC will make payment to the Consultant/ LARRIC.

Table A52: Milestone Payments % payment Sl. No Task Description 1 Inception report & Mobilisation of all staff. . The particulars of all staff 10% mobilized must be furnished to concerned LARRU and the same w.r.t availability of personnel at the proposed office premise will be verified and approved by the Special DRO concerned. 2 Joint verification of the PAPs, and Providing required inputs for updating 7.5% the Resettlement Plan for the Priority roads

3 Joint verification of the PAPs, and Providing required inputs for updating 7.5% the Resettlement Plan for the Other roads

4 Issue of identity card and submission of corrected data, if any, including proposal for replacement and upgradation of community assets 5% Additional and /or missing census survey records of PAPs (to be collected only after due approval of such cases by RSO in writing) including profiles of DP in such survey and updating / entering all additional information in the web application

5 Disbursement of the entitlements for 30% of total eligible PAPs (unique) for 15% whom micro plan is submitted and compensation disbursed.

6 Disbursement of the entitlements for 30% of total eligible PAPs 15% (Unique) for whom micro plan is submitted and compensation disbursed. Appendix 5 139

7 Disbursement of the entitlements for remaining 40% of total eligible 15% PAPs (Unique) for whom micro plan is submitted and compensation disbursed. 8 Approval of draft Final Report 15% 9 Approval of final report 10% **Unique –Multiple Entitlement to a PAP, shall be treated as one PAP only.

87. Penalty: The payment of R&R Implementation Consultant will be reduced in case of any fake / irrelevant / totally not connected person being identified as PAP and included in the micro plan submitted to the LARRU at double the rate of loss made to the Government. The above clause is also applicable if entitlement amount is not calculated in accordance with RPF and the actual eligibility of the PAP concerned, and higher amount is recommended when the actual entitlement is lower.

88. Invoices should be raised periodically and should be vetted with the concernedLARR Unit of FIU Data, Services and Facilities to be provided by the Client

89. The PIU will provide to the Consultants/ LARRICs the copies of the RP of the roads and list of PAPs with their profile along with Census survey records, the strip plan of final design, set- out table indicating the corridor-of-impact and right-of-way with respect to existing centreline and any other relevant reports/ data prepared by the DPR consultant of the roads.

90. All facilities required in the performance of the assignment, including office space, office stationery, transportation and accommodation for staff of the Consultant/ LARRIC, etc., shall be arranged by the Consultant/ LARRIC itself.

91. The Consultant/LARRIC should have an office in the town of the concerned Special District Revenue officer (LA) or approved location (One for each DRO) to have better co- ordination.

G. LARRIC/ Consultant Team

92. The Consultant/LARRICs teams should consist of the staff pattern as listed in Section 9. The core team should have a combined professional experience in the areas of social mobilization, community development, land acquisition and resettlement, census and socio economic surveys and participatory planning and consultations. Atleast one key staff and 1 field staff should be women. One field Staff should be employed for every 200 major impacts.

H. List of Key Positions

93. The suggested Key staff pattern for each LARRIC/ consultant for executing the work in the field is as below:

140 Appendix 5

Table A53: Key Staff Sl. No. of No. Key Professional Persons Experience 1 Team Leader / Project 1 (One) PG in social science/ psychology with a minimum of 15years Coordinator experience and 10 years in RR implementation and (Input - continuous) proficient in Tamil and English, and should not be a team lead for more than two projects. PG in social science/ psychology with a minimum of 10years experience and 8 years in RR implementation and proficient in Tamil and English. The experts on full time basis should relocate and mandatorily reside near the stretch of road under acquisition and in the District where major acquisition

takes place pertaining to the road. Experience in engaging with communities, managing involuntary resettlement activities and land acquisition projects in India at the field R&R Experts level. Capacity to understand legal issues involved in land 2 (Input - continuous) 4(Four) inheritance/mutation, engaging with community and support APs in collecting documentation. Experience in supervising field staff and dealing with grievances. PG in social science/ psychology with a minimum of 10 years experience and 8 years in RR implementation and proficient in Tamil and English. Experience in carrying out skill needs assessment and implementing livelihood improvement programs including HIV/AIDS and Human Social Improvement Trafficking awareness/promotion campaigns, community 3 Specialist 1(One) (Input - Intermittent) Road safety awareness programme based on liaising with existing governmental or non- governmental training initiatives Sub Key Staff Graduate with knowledge and experience in community *Based on consultation census and socio-economic surveys and 1 Field Staff the package proficient in Tamil. The field staff should relocate and mandatorily reside near the stretch of road under acquisition and in the area assigned to the field staff. Graduate with knowledge and experience in system *Based on management, data collection and entry. Working 2 Data entry specialist the package experience and knowledge of software that are commonly used in India, ideally managing CMIS for resettlement projects *Based on Graduate with knowledge and experience in census and 3 Enumerators the package socio-economic surveys and proficient in Tamil.

*Sufficient Sub-key staff are to be engaged based on the number of PAPs to complete the field works within the prescribed time frame given in clause 5 of the TOR

141 Appendix 6

Appendix 5: Various Welfare Schemes being Implemented by the Government of Tamil Nadu for Vulnerable Community

Schemes for Backward Class and Most Backward Class BC/MBC https://www.tn.gov.in/scheme/beneficiary_wise/5 1. District level prizes public examination 10th standard and 12th standard 2. Free education scheme 3. Free education scholarship for professional courses (engineering, medical, agriculture, veterinary and law) 4. Free education scholarship for three year diploma (polytechnic courses) 5. Perarignar anna memorial award 6. Postmatric scholarship are sanctioned from 11th standard to research level as per the rates prescribed in the scholarship notitification 7. Pre-matric scholarship scheme 8. Prize schemes to the students state level prizes 9. Scheme for meritorious students to pursue higher secondary education in the best schools of tamilnadu

Farmers https://www.tn.gov.in/scheme/beneficiary_wise/14 1. Agmark grading 2. Agricultural mechanisation programme 3. Agricultural producers cooperative marketing society 4. Agriculture input subsidy where crop loss is 50 percent and above 5. Agriculture technology management agency - training of farmers 6. Application of gypsum in ground nut 7. Application of zinc sulphate in rice growing areas 8. Biological control of crop pests 9. Bio- mass planting activities - (as per forest schedule of rates) 10. Cluster development 11. Coconut palm insurance scheme 12. Command area development and water management programme 13. Compact block demonstration 14. Composting of farm waste through pleurotus 15. Construction of house 16. Consumer durables 17. Credit linked subsidy for establishment of pack house 18. Crop loans sugarcane 19. Crop yield competition 20. Dap foliar spray in pulses 21. Dap spraying 22. Demonstration of agricultural machinery and implements 23. Demonstrations - (regular activities) 142 Appendix 6

24. Development of agriculture clusters 25. Distribution of agricultural implements - (additional activities) 26. Distribution of agricultural implements - (regular activities) 27. Distribution of biofertilisers 28. Distribution of bio pesticides 29. Distribution of blue green algae 30. Distribution of certified seeds 31. Distribution of certified seeds of maize 32. Distribution of certified seeds - oil seeds 33. Distribution of foundation / certified seeds of paddy, millets, pulses, and oilseeds 34. Distribution of gypsum 35. Distribution of gypsum - oil seeds 36. Distribution of manually operated plant protection equipment 37. Distribution of micro nutrient mixture 38. Distribution of minikits at free of cost 39. Distribution of nuclear poly hedrosis virus 40. Distribution of rhizobium 41. Distribution of rhizobium packets - oilseeds 42. Distribution of soil health card 43. Farmers hub (kisan bhavan) 44. Farmers interest group (fig)

45. Farmers training 46. Farmers training centres ( ftc ) 47. Farm production system and micro enterprises - sponsored by state govt 48. Focus technology revisiting crop demonstrations - (additional activities) 49. For registered medical practioners and engineering graduates 50. For two wheelers 51. House extension, renovation 52. Immediate payment to farmers at regulated markets 53. Infrastructure subsidy for privately developed industrial estates. 54. Initiatives for nutritional security through intensive millets promotion (insimp) 55. Inm demonstrations – (additional activities) 56. Inm demonstrations - (regular activities) 57. Integrated development of pulses village 58. Integrated farming in coconut holding for productivity improvement 59. Integrated horticulture development scheme(scp)-sc/st 60. Integrated pest management demonstration cum training 61. Intensification of redgram cultivation through demonstration 62. Jewel loan 63. Land development scheme 64. Livelihood activities for asset less persons-2012 65. Livelihood activities for asset less persons - sponsored by state govt 66. Loan on title deeds 67. Members children educational loan 68. Micro nutrient spray Appendix 6 143

69. Mini mission ii – technology mission on cotton 70. Minor irrigation scheme 71. Mobilization of different farmers groups including farmers’ interest groups, commodity interest groups and farmer co-operatives etc., 72. Modified national agricultural insurance scheme 73. National agricultural insurance scheme - crop insurance 74. National agriculture development programme 75. National agriculture development programme - hi-tech productivity enhancement programme 76. National bamboo mission 77. National horticulture mission 78. Oil palm area expansion (opae) 79. Organic certification 80. Organizing block demonstration 81. Organizing block demonstration on polythene mulch technology in groundnut 82. Organizing block demonstration through department and also through tnau 83. Organizing demonstrations 84. Organizing field days and kisan gosthis 85. Organizing integrated pest management demonstration 86. Organizing integrated pest management demonstration- oil seeds 87. Pipes carrying water from source to field 88. Pipes carrying water from source to field - pulses ispom 89. Pledge loan to farmers 90. Pledge loan to traders 91. Popularizing system of rice intensification technology on cluster basis 92. Precision farming 93. Price preference for micro and small enterprises in government purchases 94. Primary cooperative agriculture and rural development bank - for animal husbandry 95. Primary cooperative agriculture and rural development bank - for fishing boats (catamarans) 96. Primary cooperative agriculture and rural development bank - for handloom and other non-farm sector activities 97. Primary cooperative agriculture and rural development bank - for horticulture 98. Primary cooperative agriculture and rural development bank - for inland fishing 99. Primary cooperative agriculture and rural development bank - for minor irrigation 100. Primary cooperative agriculture and rural development bank - for plantation (tea) 101. Primary cooperative agriculture and rural development bank - for poultry development 102. Primary cooperative agriculture and rural development bank - for power tiller

144 Appendix 6

103. Primary cooperative agriculture and rural development bank - for sericulture in irrigated area. 104. Primary cooperative agriculture and rural development bank - for tractor purchase 105. Primary cooperative agriculture and rural development bank - jewel loans 106. Oduce pledge loan 107. Production and distribution of green manure seeds 108. Production of certified seeds 109. Production of certified seeds of maize 110. Production of foundation and certified seeds 111. Production of foundation seeds 112. Professional courses 113. Purchase of passenger bus, mini lorry, car, jeep 114. Purchase preference for micro and small enterprises on government purchases 115. Quality paddy seed distribution 116. Rain water harvesting and runoff management programme 117. Reclamation of saline and alkaline soil 118. Revamped micro credit 119. Salary loan for government employee 120. Scheme for artificial recharge to ground water 121. Seed certification 122. Seed multiplication scheme of paddy, millets, pulses and oilseeds 123. Seed multiplication scheme of paddy, millets, pulses, oilseeds and cotton 124. Seed quality control 125. Seed testing 126. Seed village programme - (additional activities) 127. Seed village programme - (regular activities) 128. Self help group 129. Sericulture - catalytic development programme - bivoltine training to farmers 130. Sericulture - catalytic development programme - construction of separate rearing house 131. Sericulture - catalytic development programme - establishment of chawkie rearing center 132. Sericulture - catalytic development programme - installation of drip irrigation system 133. Sericulture - catalytic development programme - installation of multiend reeling 134. Sericulture - catalytic development programme - procurement of improved rearing appliances 135. Sericulture - catalytic development programme - supply of quality disinfectants 136. Sericulture - hill area development programme (hadp) - construction of separate rearing house 137. Sericulture - hill area development programme (hadp) - plantation incentive 138. Sericulture - hill area development programme (hadp) - procurement of improved rearing appliances 139. Sericulture - western ghats development programme -wgdp - construction of separate rearing house 140. Sericulture - western ghats development programme -wgdp - procurement of improved rearing appliances 141. Site purchase 142. Soil and water conservation under hill area development programme Appendix 6 145

143. Soil and water conservation under western ghats development programme 144. Soil and water samples analysis 145. Soil conservation in tribal areas under integrated tribal development programme 146. Sprinkler irrigation, drip irrigation, laying pipe lines 147. Ssi unit 148. Supply of coconut seedlings 149. Tamil nadu farmers development and welfare scheme 150. Tamil nadu - irrigated agriculture modernization and water bodies restoration and management (tn-iamwarm) 151. Technology business incubators in the fields like automobile, machine tools, food processing etc. In msme sector 152. Three days training on seed production technology 153. Training of farmers on pulses production technologies 154. Training to farmers 155. Under integrated scheme for maize 156. Under integrated scheme for oilpalm 157. Under integrated scheme for oilseeds, oilpalm and maize (isopom) 158. Urban cooperative banks - house construction 159. Urban cooperative banks - jewel loans 160. Urban cooperative banks - purchase of two wheelers, t.v., fridge, house hold articles articles 161. Urban cooperative banks - renovation and repairs 162. Vermicomposting of agricultural waste 163. Visit of contract farming farmers to the research stations in karnataka 164. Waiver of earnest money deposit for participation in tenders 165. Weather based crop insurance scheme (wbcis) 166. Western ghats development programme -wgdp - plantation incentive

Handloom Weavers https://www.tn.gov.in/scheme/beneficiary_wise/13

1. Awarding Scholarships under the M.G.R. Handloom Weavers Welfare Trust 2. Co-operative Handloom Weavers’ Family Pension Scheme 3. Co-operative Handloom Weavers’ Old Age Pension Scheme 4. Development Schemes - Free Power Supply to Handloom and Powerloom Weavers 5. Development Schemes - Free Supply of Dhothies and Sarees Scheme 6. Development Schemes - Rebate Subsidy Scheme 7. Handlooms and Textiles Department - Important Activities Prescribed In The TamilNadu Co-Operative Socieites Act,1983 8. Handlooms and Textiles Department - Institutions Under The Control Of The Department And Their Activities - Co-operative Spinning Mills 146 Appendix 6

9. Handlooms and Textiles Department - Institutions Under The Control Of The Department And Their Activities - Tamilnadu Co-operative Spinning Mills Federation Limited (TANSPIN), Chennai 10. Handlooms and Textiles Department -Institutions Under The Control Of The Department And Their Activities - Tamilnadu Co-operative Textile Processing Mills Limited, Erode 11. Handlooms and Textiles Department - Institutions Under The Control Of The Department And Their Activities - Tamilnadu Handloom Development Corporation Limited, Chennai 12. Handlooms and Textiles Department - Institutions Under The Control Of The Department And Their Activities - Tamilnadu Textile Corporation Limited, 13. Handlooms and Textiles Department - Institutions Under The Control Of The Department And Their Activities - Tamilnadu Zari Limited, Kancheepuram 14. Handlooms and Textiles Department - Payment of scholarship to students of Indian Institute of Handloom Technology, Salem 15. Handlooms and Textiles Department - Payment of scholarship under Shiksha Sahayog Yojana 16. Handlooms and Textiles Department - Prize Award Scheme for the Best Exporters 17. Handlooms and Textiles Department - Scheme for integrated textile parks(SITP) 18. Handlooms and Textiles Department - Scheme for integrated textile parks(SITP) Under the Scheme for setting up of Integrated Textile Parks 19. Handlooms and Textiles Department - Technology Upgradation Fund Scheme (TUFS) 20. Health Insurance Scheme for Weavers 21. Institutions Under The Control Of The Department And Their Activities - Tamilnadu Handloom Weavers Co-operative Society Limited (Co-optex),Chennai 22. Integrated Handlooms Development Scheme - Cluster Development Programme. 23. Integrated Handlooms Development Scheme - Group approach for development of Handlooms. 24. Mahathma Gandhi Bunkar Bima Yojana Scheme (Insurance Scheme for Handloom Weavers)

Manufacturers https://www.tn.gov.in/scheme/beneficiary_wise/16

1. Additional capital subsidy for women, SC / ST, differently abled and transgender entrepreneurs 2. Additional capital subsidy to promote cleaner and environment friendly technologies 3. Application for sanction of subsidy for the purchase of Generator Set 4. Application for Special Capital (Investment) Subsidy 5. Application for State Capital Subsidy 6. Capital subsidy - For Incentive 7. Capital subsidy - For Subsidy 8. Employment intensive subsidy 9. Generator subsidy 10. Low Tension power tariff subsidy 11. Mini Tool Rooms Appendix 6 147

12. Rebate on Stamp duty and registration charges for Privately Developed Industrial Estates 13. Rebate/ Reimbursement of Stamp duty & Registration charges for Micro and Small Enterprises 14. Reimbursement of hall rent for conducting exhibition by MSME Association 15. Reservation for Micro Enterprises in TANSIDCO Industrial Estates 16. Reservation for Micro , Small and Medium Enterprises in SIPCOT Industrial Estates 17. Skill Development Training Schemes and Skill Upgradation Training Schemes 18. Special capital subsidy for thrust sector enterprises 19. Stamp duty exemption on mortgaged and pledged documents

20. Subsidy on the assessed Value Added Tax (VAT) 21. Subsidy on the cost of Patent Registration in India or abroad 22. Subsidy on the cost of Trade Mark Registration in India or abroad 23. Technology Development Fund for evolving cleaner and / or energy efficient or IT enabled technologies for Micro, Small & Medium Manufacturing Sector. 24. Term loan obtained for ISO Certification/R&D under NSICTANSIDCO Consortium 25. Term loan obtained for Technology upgradation / modernisation schemes 26. Term loan obtained under Credit Guarantee Fund Trust Scheme 27. Term loan obtained under NEF scheme of TIIC (Renamed as Micro/Small Enterprises Funding Scheme) 28. Unemployed Youth Employment Generation Programme (UYEGP)

Pregnant Women https://www.tn.gov.in/scheme/beneficiary_wise/2

1. Assistance for delivery of a child 2. Assistance for miscarriage or termination of pregnancy 3. District central cooperative banks and through its branches - for maternity loan through self help groups 4. Maternity loan through self help group 5. Nutrition - integrated child development services scheme 6. Urban cooperative banks - loan for maternity loan through self help groups

SC/ST https://www.tn.gov.in/scheme/beneficiary_wise/6

1. Abolition of Bonded Labour System 2. Admission of Adi Dravidar / Tribal students in plusone at reputed schools. 3. All India Service Examinations like I.A.S., I.P.S., I.R.S., etc. 4. Animal Husbandry 5. Annal Gandhi Memorial Award 6. Assistance for Funeral Rites 7. Burial Ground - Provision of Burial Grounds and pathway to Burial Grounds 8. Chief Minister Merit Award- Given Rs.3000/- per annum for 5 years 9. Community Halls 10. Construction of free houses for tribals 148 Appendix 6

11. Development of Agricultural lands 12. District Collector s Discretionery Fund 13. District Level award for XII std 14. District Level award for X std 15. Dr.Ambedkar National merit Scholarship 16. Drinking Water facility - Provision of drinking water facilities to AD and Tribal Habitations 17. Exemption of Examination Fees / Application Fees / Registration Fees 18. Exemption of Special fees and Examination Fees to the Post Graduate Girl students. 19. Exemption of Special Fees and Examination Fees to the Under Graduate students 20. Exemption of Tuition Fees 21. Government of India Post-Matric Scholarship Scheme 22. Government of India Pre-Matric Scholarship Scheme for the children of those engaged in unclean occupation 23. Higher Education Special Scholarship 24. Hill area development programme. 25. Housing and other schemes 26. Housing and other Schemes - Encroachments will be regularised for issue of pattas 27. Housing Scheme 28. Individual entrepreneur development scheme 29. Insurance scheme to the primitive tribal (janasree beema yojana scheme) 30. Land Development Scheme 31. ink road - link roads are provided connecting the ad/tribal habitation with the main roads / villages 32. Merit-cum-Means Award 33. Note Books 34. NSKFDC 35. NSLRS 36. Overseas Scholarship 37. Providing interest free loan to tribals, provision of essential articles at reasonable price and marketing the minor forest produces to ensure better returns to the tribals through lamp societies. 38. Provision of link road facilities to the tribal village connecting with plains or main villages 39. Provision of Minor Irrigation 40. Provision of street lights to Tribal habitations. 41. Schemes of Tribal Welfare Department 42. Sericulture scheme 43. Special Assistance to Law Graduates 44. Special Fee concession 45. Special incentives to girl students 46. Special Prize Money scheme 47. State Government’s Special Post-Matric Scholarship (beyond X Std.) 48. State level Toppers Award 49. State level Toppers award for X Standard 50. Subamathi Self Help Group 51. Subject toppers award (25 Subjects) 52. Subject toppers award (5 Subjects) Appendix 6 149

53. Supply of 10 Beehives at free of cost for collecting honey Students https://www.tn.gov.in/scheme/beneficiary_wise/8 1. Adi Dravidar and Tribal Welfare Department -Hostels - Special Guides 2. Adi Dravidar and Tribal Welfare Department -Incentive / Award of Prizes - District Level Prize plus2 Examination Rs.3000/- 10th Std First prize Rs.1000/- Second Prize Rs.500/- Third Prize Rs.300/. 3. Adi Dravidar and Tribal Welfare Department -Incentive / Award of Prizes - For each subjects (c) plus2 Examination Rs.2000/- (d)10th Std Examination Rs.1000/- 4. Adi Dravidar and Tribal Welfare Department -Scholarship - Free Education upto 12th Std. to all i.e. tuition fee will not be collected and the amount will be reimbursed by Government. 5. Adi Dravidar and Tribal Welfare Department -Scholarship - Public Examination fee for 10th and 12th Std. 6. Adi Dravidar and Tribal Welfare Department - Stationary - Text Books 7. Annal Gandhi Memorial Award - Two (One Boy and One Girl) Hindu AD Students in each district who have secured first rank in the 12th Std Public Examinations and continue their studies. 8. Assistance for Education 9. Awards to Bright Students 10. Book bank - books will be purchased for medical/ engineering/ law / m.b.a./veterinary / agri. and polytechnic/courses and placed in the library. 11. Book Bank - Books will be purchased for Medical/ Engineering/ Law / M.B.A./Veterinary / Agri. and Polytechnic / courses and placed in the Library. 12. Chief minister’s award - joint sports development centre 13. Chief minister’s award - joint sports development centre - kit and sports equipments 14. Chief minister’s award - national service scheme 15. Chief minister’s award - national service scheme for special camping 16. Chief minister’s award -sports school hostel 17. Chief minister s merit award 18. Development schemes - scheme of free supply of uniforms to school children 19. Directorate of non formal and adult education - continuing education programme 20. Distribution of free house site patta 21. Educational scholarship - educational scholarship to children of servicemen / exservicemen, sri lankan and other refugees. 22. Educational scholarship to children of scavengers / sweepers - educational scholarship to children of scavengers / sweepers 23. Educational scholarship to school students - adi dravida, tribal, most backward denotified communities. Backward communities welfare scholarship 24. Examination fees - from 2007-08 academic year onwards tamil medium students are exempted from payment of examination fees. 25. Food grant 26. Free bus pass - providing free bus pass to students 27. Free education (degree) 28. Free education - granting of admission fees, registration fees to ads / tribals / ad converted to christianity girls students who join degree, post graduate degree, professional courses 150 Appendix 6

29. Free education polytechnic 30. Free education professional courses 31. Free education - special fee and examination fee to students studying in b.a., b.sc., b.com., other degree courses and girl students of p.g. Courses. 32. Free education - special fee and examination fee to students studying in b.a., b.sc., b.com., other degree courses and girl students of p.g. Courses. Special fee and examination fee to students studyi 33. Free supply of bicycles 34. Grant-cum-loan scheme for small and medium farmers 35. Grant of states overseas scholarship - scholarship to ad/tribal students pursuing higher studies in abroad. 36. Grants to perform funeral rites 37. Higher education special scholarship scheme 38. Hostels - free boarding and lodging to student studying upto 12th standard 39. Hostels - mats and bed sheets 40. Hostels - uniforms 41. Ias/ips civil service examination training 42. Incentive / award of prizes - state level (a) plus2 public examination rs. 25,000/(b)10th public examination rs. 10,000/- 43. Incentives scheme for rural girl students (mbc /dnc only) 44. Individual term loan scheme 45. Integrated education for the disabled children ( iedc) - to enable the disabled children to mingle freely with normal children without barriers. 46. Ob oriented training - 2.2 typewriting and shorthand 47. Loans for transport sector 48. Maintenance charges - dayscholars 49. Maintenance charges - hostellers 50. Merit cum means award - conditions and prize amounts for grant of this award are as per the gandhi memorial award. This award is meant for tirbals and adi dravidar converted to christianity. 51. Merit-cum-means scholarships to minority students 52. Milch animal loan schemes 53. National cadet crops - scholarships 54. Nutrition - puratchi thalaivar mgr nutritious meal programme 55. Post matric scholarship 56. Postmatric scholarship - all compulsorily payable fees, exam fees and maintenance charges payable to schools and colleges are sanctioned as scholarship. 57. Post matric scholarships to minority students 58. Pre matric scholarships 59. Schemes of bc, mbc, dept - stationery - free supply of text books 60. Schemes of bc, mbc, dept - stationery - note books 61. Chemes of bc, mbc, dept - stationery - supply of slates 62. Scholarship - assistance to the children of those engaged in unclean occupations Appendix 6 151

63. Scholarship - beyond 12th std. Students studying in govt. / govt. Aided institutions are exempted from payment of tuition fees. The amount will be reimbursed to the head of the institution by govt. 64. Scholarship - granting of special fee 65. Special incentive scheme for encouraging girls education 66. Special prize money award - grant of one time award to the graduates and post graduate and professional courses. 67. Stationery - special guides (question and answer) 68. Stationery - uniforms 69. Supply of free bicycles 70. Supply of iron box 71. Supply of sewing machines

72. Tamil nadu agricultural labourers agriculturalists social security and welfare scheme 2006 - educational assistance to children of whose father / mother died (or) permanently incapacitated in accidents. 73. Tamil nadu agricultural labourers agriculturalists social security and welfare scheme 2006 - provision of education scholarship to the children of agricultural labourers who have passed 10th and 12th standards 74. Text books from 1st to 12th std bc mbc dnc 75. Tuition fees for english medium students 76. Welfare schemes of the school education department - distribution of free text books 77. Welfare schemes of the school education department - distribution of free uniforms 78. Welfare schemes of the school education department - free text book - supply of free text books 79. Welfare schemes of the school education department - free uniform - supply of free uniform 80. Welfare schemes of the school education department - incentive to girls students 81. Welfare schemes of the school education department - parent teacher association - parent teacher association 82. Welfare schemes of the school education department - supply of free bicycles 83. Welfare schemes of the school education department - talent examination - national talent exam

Unemployed https://www.tn.gov.in/scheme/beneficiary_wise/7 1. Afforestation schemes providing incentives and providing employment to Tribals in Forest Operation. 2. Assistance to Lawyers for Starting their Practice 3. Award of Rs.20,000/- to Best Writers 4. Employment opportunities to Educated Tribal Youths 5. Issue of tools and appliances - sewing machines/carpentry things to the iti holders. (iron boxes will be supplied those who undertook ironing as a trade) 6. Land Purchase Scheme 7. Training in basket making, tailoring etc. for the women 8. Vocational Guidance center are functioning at Udhagamandalam to the guidance of Tribal youths for employment purpose 152 Appendix 6

9. Vocational Training Programme 10. Welfare Schemes of the School Education Department - National Institute of Open Schooling (NIOS)

Minorities https://www.tn.gov.in/scheme/beneficiary_wise/9

1. Urban Cooperative Banks - Loan for economically backward class citizen TABCEDCO / TAMCO, loan given to public belonging to Backward class, MBC and minorities at lower rate of interest. 2. Welfare Schemes of the School Education Department - Project for Residual Illiteracy (PRI) 3. Welfare Schemes of the School Education Department - Special Literacy Proramme for Women

Physically Challenged [Differently abled] https://www.tn.gov.in/scheme/beneficiary_wise/4

1. Appointment of guardians to special categories of disabled persons under the national trust act, 1999 2. Artificial limbs 3. Assistance for corrective surgery for polio and spinal cord injured persons 4. Assistance to law graduates 5. Award for the visually handicapped students 6. Award for the visually handicapped students of x standard rank holders district level 7. Award for the visually handicapped students of x standard rank holders state level 8. Braille watches 9. Calipers and crutches 10. Diploma in medical laboratory technology training 11. Early intervention centre for infant and young children with hearing impairment 12. Early intervention centre for the mentally retarded children 13. Free computer training course 14. Free supply of braille books 15. Free travel concession to the disabled persons in state owned transport corporation buses 16. Free travel concession to the hearing impaired and locomotor disabled persons in state owned transport corporation buses 17. Free travel concession to the mentally retarded persons in state owned transport corporation buses 18. Free travel concession to the visually handicapped / orthopeadically handicapped persons in state owned transport corporation buses 19. Goggles and folding sticks 20. Government care camp, melpakkam 21. Government institute for the mentally challenged 22. Government institute for the mentally challenged, chennai Appendix 6 153

23. Government rehabilitation homes 24. Hearing aids and solar re-chargeable batteries 25. Homes for the mentally retarded above the age of 14 years 26. Loan assistance from national handicapped finance and development corporation (nhfdc) 27. Maintenance allowance to mentally retarded persons 28. Maintenance allowance to severely disabled persons 29. Marriage assistance to normal person marrying orthopaedically handicapped person 30. Marriage assistance to normal person marrying speech and hearing impaired person 31. Marriage assistance to normal persons marrying visually handicapped persons 32. Modular functional artificial limbs (modular transtibial prosthesis) 33. Motorised cycles (invalid carriage) 34. National identity card for the disabled persons 35. Physiotherapy exercise 36. Pre school for young hearing impaired children 37. Readers allowance to visually handicapped persons 38. Registration of complaints under persons with disabilities act, 1995 39. Rehabilitation of the disabled - distribution of pre-recorded cassettes and tape recorders to visually handicapped 40. Rehabilitation of the disabled - readers allowance to visually handicapped persons 41. Rehabilitation of the disabled -reservation of teaching posts in educational institutions for visually handicapped 42. Rehabilitation of the disabled - scholarship 43. Rehabilitation of the disabled scholarship - for degree course 44. Rehabilitation of the disabled - starting of degree courses for the hearing impaired students 45. Reservation of jobs in government departments / government undertakings 46. Reservation of non teaching posts in educational institutions for speech and hearing impaired persons 47. Scholarship - for the age of 12 to 14 48. Scholarship - for the age of 6 to 11 49. Scribe assistance 50. Secondary grade teachers training institute for the visually and orthopaedically handicapped persons (diploma in teacher education) 51. Self employment 52. Special education 53. Training to the adult blind women 54. Training to the speech and hearing impaired (male) 55. Training to the visually handicapped (male) 56. Tricycles 57. Unemployment allowance to the visually handicapped 58. Wheel chairs

Social Welfare and Nutritious Meal Programme Department https://www.tn.gov.in/scheme/department_wise/30 1. Accident relief scheme 2. Adoption 154 Appendix 6

3. Annai theresa ninaivu orphan girls marriage assistance scheme 4. Appointment of guardians to special categories of disabled persons under the national trust act, 1999 5. Assistance for corrective surgery for polio and spinal cord injured persons 6. Assistance to law graduates 7. Award for the visually handicapped students 8. Award for the visually handicapped students of xii standard rank holders district level 9. Award for the visually handicapped students of x standard rank holders district level 10. Award for the visually handicapped students of x standard rank holders state level 11. Destitute agricultural labourer pension scheme 12. Destitute physically handicapped pension scheme 13. Destitute widow pension scheme 14. Diploma in medical laboratory technology training 15. Distress relief scheme 16. Dr. Dharmambal ammaiyar ninaivu widow remarriage scheme 17. Dr.muthulakshmi reddy ninaivu intercaste scheme 18. Early intervention centre for infant and young children with hearing impairment 19. Early intervention centre for the mentally retarded children 20. E.v.r. Maniammaiyar ninaivu poor widow daughter’s marriage assistance scheme 21. Free computer training course 22. Free supply of text books and note books to widows children 23. Moovalur ramamirtham ammaiyar ninaivu marriage assistance scheme 24. National identity card for the disabled persons 25. Nutrition - integrated child development services scheme 26. Nutrition - puratchi thalaivar mgr nutritious meal programme 27. Old age home 28. Protection of women from domestic violence 29. Sathiyavani muthu ammaiyar ninaivu free supply of sewing machine scheme 30. Sathya ammaiyar ninaivu goverment orphanages 31. Schemes of social welfare and nutritious meal programme. Annapurna scheme 32. Schemes of social welfare and nutritious meal programme destitute deserted wives pension scheme 33. Self employment 34. Sivagami ammaiyar memorial girl child protection scheme 35. Working women’s hostel