51st Meeting of the Central Sanctioning and Monitoring Committee (CSMC) Pradhan Mantri Awas Yojana, Housing For All – Urban

PMAY(U),

7th August, 2020 PROGRESS OF PMAY (U)

Indicators Current Status (No.) ▪ Cities Approved 27 (Twenty Seven) Yes (Round 1 in 2016-17 ) ▪ Demand Survey Completed Round 2 in progress (10 ULBs completed) 46,360 (Round 1) ▪ Total Demand 20,000 (Round 2 - estimated) ▪ Whether HFAPoA Submitted Yes. ▪ Whether AIP Submitted In process ▪ Whether HFAPoA & AIP entered in MIS Yes at ULB’s level

▪ SLTC/CLTC staffs approved vs. placed 4/5 SLTC Experts in place. 12/14 CLTC Experts in place

▪ Target of DUs in 2020-21 25,417 State Share in the form exemption of Registration Fee and ▪ State Budgetary Provision for PMAY (U) Stamp Duties. Pradhan Mantri Awas Yojana (PMAY-U), Manipur

Agenda 1 Curtailment of 579 beneficiaries under BLC(New) component of PMAY(U), Housing for All in respect of Manipur Curtailment of beneficiaries under BLC(New).

v A total of 579 beneficiaries under 10 BLC(New) projects of PMAY(U), Manipur needs to be curtailed. v Curtailment necessitated due to non-starting of construction by the beneficiaries. v SLNA and ULBs have repeatedly tried to persuade the beneficiaries to start construction of houses through reminders, notifications, awareness programs and field visits. v If curtailed, the above 10 BLC(new) projects will have 100% grounding. v Curtailment of the beneficiaries is already approved by the SLSMC. Project-wise beneficiaries to be curtailed.

Beneficiaries Date of approval No. City Name Project Code Project Name to be curtailed by SLSMC Project for Construction of New Houses under Beneficiary Led Construction 1 14801477014N0 24 vertical of PMAY-HFA Urban for Heirok Nagar Panchayat(7C14801477002179) Project for Construction of New Houses under BLC vertical of PMAY-HFA for 2 14801493014N0 67 Jiribam Municipal Council(7C14801493000850) Project for construction of new houses under BLC vertical of PMAY-HFU for 3 Khunou 14801483014N0 4 Municipal Council(7C14801483000931) Project for construction of new houses under BLC vertical of PMAY HFA for 4 14801492014N0 26 ( West) Lilong Nagar Panchayat IW(7C14801492000933) Project for construction of New Houses under BLC vertical of PMAY-HFA Urban 5 14801488014N0 43 for Samurou Nagar Panchayat(7C14801488002180) 27.06.2020 Project for Construction of New Houses under BLC vertical of PMAY-HFA Urban 6 Sikhong Sekmai 14801480014N0 25 for Shikhong Sekmai Municipal Council(7C14801480003556) Project for for New Houses under BLC Vertical of 7 Sugnu 14801482014N0 40 PMAY(7C14801482000846) Thongkhong Laxmi Project for Construction of New Houses under BLC vertical of PMAY Urban for 8 14801490014N0 82 Bazar Thongkhong Laxmi Bazar Municipal council (7C14801490003885) Project for Construction of New houses under BLC vertical of PMAY HFA for 9 14801479014N0 266 Thoubal Municipal Council(7C14801479000934) Project for Construction of New Houses under BLC Vertical of PMAY-HFA at 10 Wangjing 14801478014N0 2 16.09.2019 Wangjing Lamding MC(7C14801478000921) TOTAL 579 Comparison sheet of projects.

Project Central Beneficiary Total Transge Details Male Female Gen SC ST OBC Cost Share Share DUs nder

Before 26184.83 15445.50 10739.23 10297 3644 6652 1 5317 756 77 4147 10 BLC(New) Curtailment Projects, PMAY(U) Manipur After 24690.33 14577.00 10113.33 9718 3452 6265 1 4979 748 66 3925 Curtailment Comparison sheet of projects.

Before and After Curtailment

No. City Name Project Code Beneficiary Project Cost Central Share Total DU Male Female Trans Gen SC ST OBC Share 559.44 333.00 226.44 222 37 185 0 12 0 0 210 1 Heirok 14801477014N0 498.96 297.00 201.96 198 33 165 0 9 0 0 189

994.76 523.50 471.26 349 177 172 0 232 10 39 68 2 Jiribam 14801493014N0 803.7 423 380.7 282 134 148 0 184 8 33 57

Kakching 1905.12 1134.00 771.12 756 380 376 0 2 658 0 96 3 14801483014N0 Khunou 1895.04 1128.00 767.04 752 377 375 0 2 654 0 96

Lilong 3039.12 1809.00 1230.12 1206 471 734 1 1134 0 1 71 4 14801492014N0 (Imphal West) 2973.60 1770.00 1203.6 1180 459 720 1 1111 0 1 68

3114.72 1854.00 1260.70 1236 485 751 0 703 1 2 530 5 Samurou 14801488014N0 3006.36 1789.5 1216.86 1193 466 727 0 663 1 2 527 Comparison sheet of projects. (Contd.) Before and After Curtailment

No. City Name Project Code Beneficiary Project Cost Central Share Total DU Male Female Trans Gen SC ST OBC Share

Sikhong 1849.68 1101.00 748.60 734 338 396 0 644 0 0 90 6 14801480014N0 Sekmai 1786.68 1063.50 723.18 709 327 382 0 619 0 0 90

1045.95 550.50 495.45 367 234 133 0 352 0 1 14 7 Sugnu 14801482014N0 931.95 490.5 441.45 327 210 117 0 315 0 0 12

Thongkhong 4508.28 2683.50 1824.78 1789 858 931 0 177 0 33 1579 8 14801490014N0 Laxmi Bazar 4301.64 2560.5 1741.14 1707 812 895 0 173 0 29 1505 7376.04 4390.50 2985.54 2927 300 2627 0 1447 87 1 1392 9 Thoubal 14801479014N0 6705.72 3991.50 2714.22 2661 271 2390 0 1291 85 1 1284

1791.72 1066.50 725.22 711 364 347 0 614 0 0 97 10 Wangjing 14801478014N0 1786.68 1063.5 723.18 709 363 346 0 612 0 0 97 Curtailment of beneficiaries under BLC(New).

Publicity for Curtailment at ULBs Curtailment of beneficiaries under BLC(New).

Notifications for Curtailment Pradhan Mantri Awas Yojana (PMAY-U), Manipur

Agenda 2 Proposals for 10 (Ten) New BLC (New) Projects of Manipur under PMAY(U), Housing for All PROGRESS OF PMAY (U)

❖ To facilitate smooth transfer of title of land to the female head of the household or entering the name of the spouse of the male head of the household as co-pattadar for availing the benefits of PMAY-HFA(U), the State Govt. has exempted the following fees/ charges:

(i) Stamp duty of 3% (ii) Registration fee of 1% and , (iii) Tax of 1% on registration of deeds for transfer of land. STATUS OF MANDATORY CONDITIONS

Mandatory conditions Current Status

Achieved. Provision made in sub-para(ii) of para (6) of The Manipur Land Revenue and Land Reforms ▪Dispensing the need for separate Non (Diversion of Land), RULES, 2014 issued, vide Agricultural (NA) Permission notification No.2/1/2014-R(Act/Rule) dated 9th July, 2014

Achieved. Provision for Earmarking of at least 20-25% of developed land in all housing projects (both Public ▪Prepare/amend their Master Plans &Private Agencies) for EWS / LIG Categories was made earmarking land for Affordable Housing vide Notification No. 7/122/2008-MAHUD dated 28.06.2008

▪Single-window, time bound clearance for Achieved. Single-window clearance as per para 3 (Chapter -II) of the Imphal Municipal Council Building layout approval and building permissions Bye Laws-2013 STATUS OF MANDATORY CONDITIONS (Contd.)

Mandatory conditions Current Status

Achieved. The Municipal Councils and Nagar ▪ Adopt the approach of deemed building permission Panchayats shall prepare 3 to 4 model plans, and layout approval on the basis of pre-approved lay conforming to codal provisions. Beneficiaries can select outs and building plans. a model of his/ her choice.

▪ Amend or legislate existing rent laws on the lines of State has consented to the proposed Draft Model the Model Tenancy Act. Tenancy Act, 2019.

Achieved. There is no system of Floor Area Ratio (FAR) ▪ Additional Floor Area Ratio (FAR)/Floor Space / Floor space Index (FSI) prescribed in the State. Index (FSI)/ Transferable Development Rights Development controls of buildings are based on front, (TDR) and relaxed density norms. back, side setbacks and permissible height of the area only. INTERFACE WITH MIS

Indicators Current Status (No.) ▪Survey entry made (%) 38,826 (91%)

▪Projects approved: 27 towns (BLC- New) ▪Projects entered (7A/B/C/D) 7C

▪DUs approved under BLC 42,651

▪Beneficiaries attached 36,763 (86%)

▪Houses geo-tagged 31,801 (75%)

▪Total fund transferred through DBT (Rs. Lakhs) 17,812.90

▪National Electronic Funds Transfer (NEFT) - Rs. 17,812.90 Lakhs through PFMS/ DBT in ▪PFMS/ DBT AADHAR linked accounts of beneficiaries. ▪Aadhar Payment Bridge (APB) DBT to Aadhar linked A/c only. PROGRESS OF PROJECTS

Work Grounded / In Progress Houses Verticals Tendered order Completed Approved Issued Started Foundation Lintel Roof Total

▪ ISSR

▪ AHP

▪ BLC (N) 42,651 NA NA 3,342 10,862 6,791 2,329 23,324 2,940

▪ BLC (E)

▪ Total 42,651 NA NA 3,342 10,862 6,791 2,329 23,324 2,940

▪ CLSS GLIMPSES OF PROGRESS GLIMPSES OF PROGRESS GLIMPSES OF PROGRESS PROJECT PROPOSAL BRIEF

Remarks Verticals ISSR AHP BLC (New) BLC (E) (NP=Nagar Panchayat; MC=Municipal Council) Heirok NP, Jiribam MC, Kakching Khunou MC, Lilong No. of Projects (IW) MC, Samurou MC, Shikhong Sekmai MC, Sugnu ▪ 10 (Ten) MC, Thongkhong Laxmi MC, Thoubal MC & Wangjing Lamding MC ▪No. of DUs 7906 ▪Project Cost (Rs. Lakhs) 19,946.22 ▪Central Share (Rs. Lakhs) 11,859.00 ▪State Share -- ▪ULB Share -- ▪Beneficiary Share (Rs. Lakhs) 8087.22

Completion Verticals Per Unit Cost Central Share State Share ULB Share Benf. Share Time

▪ BLC (New) Rs. 2.52 lakhs Rs. 1.50 lakhs Nil Nil Rs. 1.02 lakhs 18 Months PROJECT PROPOSAL BRIEF

Checklist Status (Y/N) ▪Layout plan (as per NBC norms) Attached Yes ▪SLAC/SLSMC approval/Minutes submitted Yes ▪Land title status (encumbrance free) Yes ▪Beneficiary list (BLC) submitted Yes ▪No. of Beneficiaries with Aadhar ID 7,906 ▪No. of Beneficiaries with other Unique ID …… If any account is not AADHAR seeded, it ▪No. of Aadhar seeded Bank accounts will be linked before release of subsidy. ▪Status of physical & social infrastructure From State Govt. Normal Schemes ▪Implementation plan/Completion period 18 months from fund release ▪Beneficiary consent sought Yes HFA (U): Activities at State Level

❖ After the demand survey forms for BLC component in the prescribed format are collected, these are scrutinized by a panel of Officers.

❖ Also, the demand survey forms are checked with the Socio- Economic Caste Census (SECC) data, 2011.

❖ In the case of discrepancy with SECC data, a team of SLTC/CLTC undertook ‘field verification’ to finalize the draft beneficiaries. HFA (U): Activities at State Level (Contd.)

Notice in local Newspaper, inviting cases of left-outs / omission ACTIVITIES FOR NEW PROPOSALS

Field Verification by Official Team: ACTIVITIES FOR NEW PROPOSALS

Field Verification by Official Team: BEST PRACTICE / INNOVATION

▪ Best practice to be shared: To disseminate activities of HFA (U), certain IEC activities were implemented by SLNA and ULBs v Tree Plantation: Every BLC houses under the project are encouraged to develop an environment of cohesive and sustainable living by planting trees in front of their completed house.

v Awareness on best practices of healthy and hygienic living, Rain water harvesting and energy conservation were carried out through events such as painting competition, Street plays etc. and adopted by the Beneficiaries.

v Under Angikaar – A campaign for Change Management, a thorough door to door assessment visits were made to spread awareness among the beneficiaries for convergence of other schemes with PMAY(U), Housing for All.

v Source segregation: All the beneficiaries under PMAY (U) are provided two bins for segregation of waste at their homes. It is mandatory for every beneficiaries to segregate their waste at source. In some ULBs, feeding food waste to fishery, poultry, piggery farms are practiced. Encouraged in other ULBs also. BEST PRACTICE / INNOVATION

AWARENESS PROGRAM STREET PLAY

STREET PLAY DOOR TO DOOR AWARENESS BEST PRACTICE / INNOVATION

ROOF-TOP RAIN-WATER HARVESTING DISTRIBUTION OF THREE BINS TO THE BENEFICIARIES FOR SOURCE SEGREGATION

TREE PLANTATION DISTRIBUTION OF SAPLINGS TO BENEFICIARIES BEST PRACTICE / INNOVATION

AWARENESS PROGRAM ON IMPORTANCE OF SOURCE DISTRIBUTION OF BINS TO THE BENEFICIARIES FOR SEGREGATION SOURCE SEGREGATION BEST PRACTICE / INNOVATION

PAINTING COMPETITION Thank You! BEST PRACTICE / INNOVATION Registration Fee & Stamp Duty Exemption Orders: DETAILED COST BREAK-UP

Total Total No. Total Central Total Project Beneficiary 1st Instalment of Share (@Rs. Sl. No Name of town cost (Col. 3 x share (Col. 3- (40% of Col. 4) in Beneficia 1.50 lakhs per Rs. 2.52 lakhs) Col. 4) in Rs. Rs. Lakhs ries benef.) lakhs 0 1 2 3 4 5 6 1 Heirok NP 293 738.36 439.50 298.86 175.80

2 Jiribam MC 70 199.50 105.00 94.50 42.00

3 Kakching Khunou MC 1054 2656.08 1581.00 1075.08 632.40 4 Lilong (IW) MC 756 1905.12 1134.00 771.12 453.60 5 Samurou MC 956 2409.12 1434.00 975.12 573.60

6 Shikhong Sekmai MC 800 2016.00 1200.00 816.00 480.00 7 Sugnu MC 385 970.20 577.50 392.70 231.00

8 Thongkhong Laxmi MC 940 2368.80 1410.00 958.80 564.00

9 Thoubal MC 1520 3830.40 2280.00 1550.40 912.00 10 Wangjing Lamding MC 1132 2852.64 1698.00 1154.64 679.20 Total 7,906 19,946.22 11,859.00 8,087.22 4,743.60 Layout plan (as per NBC norms)