-Pangasinan-La Union Expressway Under Construction Connects SCTEX in Tarlac to Pangasinan to La Union Project type Expressway Length 89 km Cost US$ 488 million Source of funds PPP, solicited Proponent San Miguel Infrastructure Start of Construction 2010 Status Partially operational

Target completion June 2019 Photo Source: BusinessWorld Developments Project Description: • August 2018 - San Miguel Infrastructure has submitted a PPP The 11-km extension from Pozzorubio, Pangasinan to proposal to extend the expressway by 59 km to San Juan, La Rosario, La Union to the existing 78-km Tarlac-Pangasinan-La Union. Union expressway is the final section of the expressway that • December 2017 – Partial operations to Pozzorubio, Pangasinan connects SCTEX in Concepcion, Tarlac to Pangasinan and • December 2014 – Partial operations to Urdaneta, Pangasinan La Union. began • November 2013 – Partial operations to Tarlac City • January 2010 – Phase 1 construction began

Updated on November 15, 2018

NLEX Harbor Link Segment 8.1: Completed Connects Segment 8.1 to MacArthur Highway Project type Expressway NLEX Segment 8.1 Length 3 km <- NLEX Segment 9 Cost PhP 2 billion

Source of funds PPP NLEX Proponent Metro Pacific Start of Construction April 2009 Status Operational

Date of completion June 2010 Photo Source: NLEX Developments Project Description: • June 2010 – Project Completion NLEX Segment 8.1, or the NLEX- Link, is the • April 2009 – Groundbreaking ceremony first segment of the 27-km NLEX Harbor Link that connects Mindanao Ave. in to the SMART Connect Interchange of NLEX.

Updated on December 12, 2018

NLEX Harbor Link Segment 8.2: Under Construction Connects NLEX to Commonwealth Project type Expressway Length 8 km Cost PhP 7 billion Source of funds PPP Proponent Metro Pacific Start of Construction Q1 2019 Status Active

Target completion Q2 2021 Photo Source: DPWH Developments Project Description: NLEX Segment 8.2 is the fourth and final segment of the 27- km NLEX-Harbor Link project to be constructed. The four- lane road will connect NLEX, from Segment 8.1, to Commonwealth Ave.

Updated on December 11, 2018

NLEX Harbor Link Segment 9: Completed Connects Segment 8.1 to MacArthur Highway NAIA 3 Project type Expressway Length 2 km Cost PhP 2 billion Source of funds PPP Proponent Metro Pacific Start of Construction April 2013 Status Operational

Date of completion March 2015 Photo Source: BusinessWorld Developments Project Description: • March 2015 – Segment opened to the public NLEX Segment 9, or the NLEX Karuhtan Link, is the second • April 2013 – Groundbreaking Ceremony segment of the 27-km NLEX Harbor Link that connects MacArthur Highway to the SMART Connect Interchange.

Updated on December 10, 2018

NLEX Harbor Link Segment 10: Under Construction Connects McArthur Highway to R10 NAIA 3 Project type Expressway Length 6 km Cost PhP 16 billion Source of funds PPP Proponent Metro Pacific Start of Construction 2014 Status Active

Target completion December 2019 Photo Source: BusinessWorld Developments Project Description: • December 2019 – Target completion of project NLEX Segment 10, the third segment of the 27-km NLEX • December 2018 – Target completion until C3 Road Interchange Harbor Link Project, is a four lane, 6 km elevated expressway • November 25, 2018 – 86% Completed that connects McArthur Highway at the end of NLEX • October 2018 – Completion of ROW Acquisition Segment 9 to R10 Road, the main road used for trucks • May 2014 – Start of Construction coming from the North and South Ports of .

Video footage of construcon progress as of Dec 2018 Updated on December 10, 2018

NLEX – SLEX Connector Road Under Development Connects Skyway Stage 3 to C3 in Project type Expressway Length 8 km Cost US$ 466 million Source of funds PPP Proponent Metro Pacific Start of Construction May 2019 Status Active

Target completion Q2 2021 Photo Source: DPWH Developments Project Description: • 2018: Undergoing ROW acquisition The NLEX – SLEX Connector Road is an elevated 8-km, 4- • September 2017: Detailed engineering design completed lane toll road extending from NLEX southward from the the • September 2016: Project awarded end of Segment 10 in C3 Road, Caloocan City to Skyway • December 2015: NEDA Board Approval Stage 3 at Sta. Mesa, Manila. The road will cut travel time • May 2010: Approved by DOTC from SLEX to NLEX from 2 hours to just 20 minutes and benefit • 2010: Proposal submitted by Metro Pacific at least 35,000 vehicles per day.

Updated on February 14, 2019

C5 Expressway Under Development Connects Cavitex to NLEX over C5 road NAIA 3 Project type Expressway Length 27 km Cost PhP 93 billion Source of funds PPP, unsolicited Proponent Metro Pacific Target Construction TBD Status Active

Target completion TBD Photo Source: MPTC Developments Project Description: • May 9, 2018 – DPWH confirmed completeness of proposal The C5 Expressway is a 27 km, all-elevated expressway, • August 2017 – MPIC submitted unsolicited proposal to DPWH which will be built above the existing C5 road and connect NLEX Segment 8.2 to Cavitex-C5 South Link. It is divided into two phases: (1) Cavitex-C5 South Link to Pasig Blvd. and (2) Pasig Blvd. to NLEX Segment 8.2. The expressway will cut travel time from end-to-end of C5 from two hours to 30 minutes. Updated on February 20, 2019

Metro Manila Skyway Stage 3: Under Construction Buendia Avenue to Balintawak, Quezon City Project type Expressway Length 15 km Cost PhP 37 billion Source of funds PPP Proponent San Miguel Infrastructure Start of Construction February 2014 Status Active - 46% Completed

Target completion 2019 Photo Source: Peri Developments Project Description: • February 7, 2018: Sevilla bridge was closed for renovation in The last stage of the Skyway is a 15-km 6-lane preparation for the Skyway Stage 3 construction. elevated toll road connecting SLEX to Balintawak in Quezon • June 5, 2018: Meralco completes relocation works on Skyway City and NLEX, passing through Central Metro Manila Area. Stage 3 construction sites. Its completion is expected to relieve traffic on EDSA. • July 21, 2018: An exit ramp leading to Java St., Makati has been temporarily opened. • September 19, 2018: To give way to the construction, the bridge Drone video footage of construcon progress as of Sept 2018 connecting San Juan and Manila has been closed for demolition. Updated on October 19, 2018 Batasan Interchange Metro Manila Skyway ß NLEX C5 - Katipunan Stage 4: Under Construction Interchange Tumana Interchange Connects Skyway to Batasang Pambansa Complex Project type Expressway Marcos Highway Interchange

Length 34 km Interchange Cost PhP 45 billion Source of funds PPP C5 – Diego Silang Proponent San Miguel Interchange Start of Construction April 2018 C6 – SLEX-FTI Interchange Status Active Interchange Target completion April 2021 Photo Source: DPWH Project Description: Developments • April 2018 – Start of construction of Section 1 (1A – Skyway to FTI / Skyway Stage 4 (Southeast Metro Manila Expressway) is a 34 1B – FTI to C5/Diego Silang) km toll expressway. It will cross eastern Manila and part of • January 2018 – Groundbreaking , beginning at the future SLEX-FTI interchange in Taguig • June 2016 – Issuance of Notice to Proceed near the existing Skyway, and ending in the Batasang • August 2014 – Approval of Supplemental Toll Operations Pambansa Complex in Quezon City. Agreement by Office of the President

Updated on February 18, 2019

NAIA Expressway Phase II Completed Connects CAVITEX to NAIA Project type Expressway Length 8 km Cost US$ 361 million Source of funds PPP, solicited Proponent San Miguel Infrastructure Start of Construction January 2014 Status Operational

Date Completed June 2017 Photo Source: Mark Villar Official FB page Developments Project Description: • June 2, 2017 – NAIAX fully opened to motorists • December 28, 2016 – Access ramps to CAVITEX opened Phase II of the NAIA Expressway (NAIAX) completes • September 22, 2016 – Macapagal Blvd to NAIA Terminals 1 and 2 the 12 km NAIAX system that connects Skyway and segment opened to all motorists • January 2, 2016 – Construction of Phase II begins CAVITEX to the Ninoy Aquino International Airport • May 30, 2012 – NAIAX Phase II approved by NEDA Board terminals and PAGCOR Entertainment City • May 2009 – Phase 1 of NAIAX completed

Updated on November 9, 2018

CAVITEX – C5 South Link Expressway Under Construction Connects CAVITEX to SLEX and C5 NAIA 3 Project type Expressway Length 8 km Cost PhP 10 billion Source of funds PPP Proponent Metro Pacific Start of Construction 2016 Status Active

Target completion Q1 2020 Photo Source: BusinessWorld Developments Project Description: • March 2019 – Target start of operations for first three out of the four The east-west CAVITEX-C5 South Link connects major segments districts in the Makati and Taguig area to Cavite, Las Pinas, • October 25, 2018 – 52% Construction completed of Segment 3A-1 and Paranaque and will service an estimated 45,000 (Merville to SLEX/C5 Road) vehicles per day. • May 2016 – Groundbreaking ceremony

Video footage of construcon progress as of Oct 2018 December 10 December 10, 2018

Cavite-Laguna Expressway (CALAX) Under Construction Connects CAVITEX in Cavite to SLEX in Laguna Project type Expressway Length 45 km Cost PhP 36 billion Source of funds PPP, solicited Proponent Metro Pacific Start of Construction 2017 Status Active

Target completion June 2021 Photo Source: Metro Pacific Investments Corp. Project Description: Developments The Cavite-Laguna Expressway or CALAX connects CAVITEX in Kawit, • August 2018 – 18.83% of Laguna segment completed Cavite to SLEX in Mamplasan, Laguna and is expected to reduce • June 2017 – Groundbreaking ceremony travel time from Cavite to Laguna by 45 minutes. • June 2015 – Notice of award for Metro Pacific

• November 2013 – NEDA Board approval There will be 9 exits: Kawit, Open Canal, Governor’s Drive, Silang • August 2013 – ICC approval West, Silang East, and Sta. Rosa-Tagaytay in Cavite and Laguna Boulevard, Laguna Technopark, and Mamplasan in Laguna.

Video of CALAX construction as of Oct. 2018 Updated on October 29, 2018

Cavite-Tagaytay-Batangas Expressway Under Development Connects Cavite and Laguna to Batangas NAIA 3 Project type Expressway Length 50 km Cost PhP 22 billion Source of funds PPP, unsolicited Proponent Metro Pacific Target Construction 2019 Status Active

Target completion Q2 2022 Photo Source: MPTC Developments Project Description: • Q2 2019 - Target date for Swiss Challenge The Cavite-Tagaytay-Batangas Expressway or CTBex • July 2018 – DPWH awarded original proponent status (OPS) to connects CALAX at Silang, Cavite to Nasugbu, Batangas Metro Pacific Tollways South Corporation and decongests the Tagaytay area. Once completed, CTBex will cut travel time from Dasmarinas City, Cavite to Nasugbu, Batangas to 44 minutes, while Sta. Rosa, Laguna to Tagaytay City will take 46 minutes.

Updated on December 10, 2018