FORM 1

FOR

PROPOSED CONSCTRUCTION PROJECT (28727.17 SQ. M)

BY

DEV REALITIES AT REVENUE SURVEY NO. 56/P1, MADHAPAR, TALUKA , DIST: RAJKOT

1

APPENDIX I

(See paragraph – 6)

FORM 1

(I) Basic Information Sr. No. Item Details 1 Name of the project/s Proposed Residential Building 2 S. No. In the schedule 8 (a) 3 Proposed Proposed Residential Building capacity/area/length/tonnage to be Total Built up Area: 28727.17 Sq. m. handled/command area/lease FSI Area: 22610.48 Sq. m area/number of wells to be drilled Please refer Annexure - I 4 New/Expansion/Modernization New 5 Existing Capacity/Area etc. 8409.45 Sq. m 6 Category of Project i.e. ‘A’ or ‘B’ ‘B’ 7 Does it attract the general No condition? If yes, please specify 8 Does it attract the specific No condition? If yes, please specify 9 Location Plot/Survey/Khasra No. Revenue Survey No. 56/P1, Madhapar, Taluka Rajkot, Dist: Rajkot Village Madhapar Tehsil Rajkot State 10 Nearest railway station / air port Railway Station: Junction – 5 km along with distance in kms. Airport : Rajkot – 5.5 km 11 Nearest Town, city, District Rajkot – The proposed project is within the limit Headquarters along with distance of the Rajkot Urban Development Authority in kms (RUDA) 12 Village Panchayats, Zilla Parishad, Shri Chimanbhai Patel Vikas Bhavan, Municipal Corporation, Local body Post Box No.238, Road, (complete postal addresses with Rajkot Gujarat, telephone nos. to be given) Ph: 0281-2476874 Email: [email protected] 13 Name of applicant Dev Realities 14 Registered Address Revenue Survey No. 56/P1, Madhapar, Taluka Rajkot, Dist: Rajkot 15 Address for correspondence Name Mr. Nayanbhai Gangani

2

Designation (Owner/Partner/CEO) Partner Address Revenue Survey No. 56/P1, Madhapar, Taluka Rajkot, Dist: Rajkot Pin Code 360005 E-mail [email protected] Telephone No. (M)+91 9924099995 Fax No. -- 16 Details of Alternative Sites No examined, if any. Location of this site should be shown on a topo sheet. 17 Interlinked Projects No 18 Whether separate application of - interlinked project has been submitted? 19 If yes, date of submission - 20 If no, reason - 21 Whether the proposal involves No approval/clearance under: if yes, details of the same and their status to be given. (a) The Forest (Conservation Act, 1980? (b) The Wildlife (Protection) Act, 1972? © The C.R.Z Notification, 1991? 22 Whether there is any Government No Order/Policy relevant/relating to the site? 23 Forest land involved (hectare) None 24 Whether there is any litigation None pending against the project and/ or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Orders/direction of the Court, if any and its relevance with the proposed project.

3

(II) Activity

1. Construction, operation or decommissioning of project involving action, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Sr. No. Information /checklist confirmation YES/NO Details thereof (with approximate quantities/rate, wherever possible) with source of information data 1.1 Permanent or temporary change in land No The proposed project is use, land cover or topography including developed at Madhapar under increase in intensity of local land use plan) Rajkot Urban Development Authority, (RUDA) with construction of Residential building having 180 Flats.

The construction will be done is conformity with the requirement of GDCR Norms. 1.2 Clearance of existing land, vegetation and No - buildings? 1.3 Creation of new land use? No - 1.4 Pre-construction investigation e.g. bore Yes The soil analysis report has been house, soil testing? carried out before construction. 1.5 Construction work No -

1.6 Demolition works? No - 1.7 Temporary sites used for construction No - works or housing of construction works? 1.8 Above ground building, structures or earth Yes Total Built Up Area for the works including liner structures, cut and ill proposed building is 28727.17 or excavations Sq. m

These building are residential building as per GDCR Norms. 1.9 Underground works including mining or No - tunneling? 1.10 Reclamation works? No - 1.11 Dredging? No - 1.12 Offshore structures? No - 1.13 Production and manufacturing processes? No It is a construction and building project. 4

1.14 Facilities for storage of goods or materials? Yes Construction materials like steel, cement, sand, bricks etc will be procured from local market and will be temporarily stored at site. 1.15 Facility for treatment or disposal of solid Yes Wastewater waste or liquid effluent? Project proponent will install STP of 200 KLD with dual pumping system and treated water will be used for flushing and gardening. Please refer Annexure II

Solid waste: The total solid waste generated during the operation phase will be collected, Segregated & treated onsite by waste to compost machine. 1.16 Facility for long term housing of operational No - workers? 1.17 New road, rail or sea traffic during Yes Road traffic will increase due to construction or operation? the various construction activities and also in the operation phase because of increased population due to proposed project. 1.18 New road rail. Air waterborne or other No - transport infrastructure including new or altered routes and station, ports airport etc. 1.19 Closure or diversion of existing transport No - routes or infrastructure leading to changes in traffic movements? 1.20 New or diverted transmission lines or No - pipelines? 1.21 Impoundment, damming. Culver ting. Yes RUDA water supply line and Realignment or other changes to the onsite treated water is the hydrology of watercourses or aquifers? source of water during operation phase. 1.22 Stream crossing? No - 1.23 Abstraction or transfer of water from No During operation phase the ground or surface waters? whole water requirement will be met through RUDA water

5

supply and treated water. 3 Nos. of percolation well will be constructed for the ground water recharging as per the GDCR Norms. 1.24 Changes in water bodies or the land The project involves Surface affecting drainage or run-off? construction of paved areas and hence the quantity of runoff will increase due to infiltration. This Yes runoff will be collected through a well – designed surface water drain and will be used for recharging aquifers. 1.25 Transport of personnel or material for Transportation of construction construction, operation or Yes material will be by truck. Decommissioning? 1.26 Long-term dismantling, decommissioning, No - or restoration works? 1.27 Ongoing activity during decommissioning No - which could have an impact on the environment? 1.28 Influx of people to an area in either No - temporarily or permanently? 1.29 Introduction of alien species? No - 1.30 Loss of native species or genetic diversity? No - 1.31 Any other actions? No -

2. Use of Natural resources for construction or operation of the project (such as land, water material or energy any resources which are non-renewable or in short supply): Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data 2.1 Land especially undeveloped or agricultural land No The project will be (ha) constructed in within plot area of 8409.45 sqm which is undeveloped land at present. 2.2 Water (expected source & competing users) Yes During operation phase the whole water requirement will be met through RUDA

6

water supply line and onsite treated water.

Please refer Annexure II for water consumption. 2.3 Minerals No - 2.4 Construction material-stone, aggregates, No - and/soil (expected source-MT) 2.5 Forests and timber (sources MT) No Wood will be used for the furniture. 2.6 Energy including electricity and fuels (source, Yes The project would required competing users) Units. Fuel (MT) energy (MW) about 600 KW electric power during operation phase which is sourced from PGVCL 2.7 Any other natural resources (appropriate No - standards units)

3. Uses, Storage, Transport, Handling or production of substances or materials, which could be harmful to production to human health or the environment or raise concern about actual or perceived risks to human health Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data 3.1 Use of substances or materials, which are No - hazardous (as per MSIHC rules) to human health or the environment (flora fauna and water supplies) 3.2 Changes in occurrence of diseases of affect No - disease vectors (e.g. insect or water borne disease) 3.3 After the welfare of people (e.g. by Yes During operation phase, changing living condition? direct – indirect employment will be generated which will uplift the socio – economic of the area. 3.4 Vulnerable groups of people who could be No - affected by the projects e.g. hospital patients, children, the elderly etc. 3.5 Any other cause No -

7

4. Production of solid waste during construction or operation or decommissioning MT/month): Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data 4.1 Spoil, overburden or mine waste No - 4.2 Municipal waste (domestic and or Yes The Municipal solid waste commercial wastes) generated during operation phase will consist of: Organic Waste: Waste vegetable and food

Inorganic waste: Papers, cartons, thermocol, plastic, polythene bags, glasses etc. The solid waste generated will be approximately 540 kg/day.

The reusable waste will be sold off. The non recyclers solid waste generated will be collected, Segregated & treated onsite by waste to compost machine. 4.3 Hazardous waste (as per Hazardous waste No - Management rules) 4.4 Other industrial process waste No - 4.5 Surplus project No - 4.6 Sewage sludge or other sludge from Yes Sewage sludge generated from effluent treatment STP will be used as manure after composting. 4.7 Construction or demolition waste No - 4.8 Redundant machinery or equipment No - 4.9 Contaminated soils or other materials No - 4.10 Agriculture waste No - 4.11 Other solid waste No -

8

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr): Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data 5.1 Emissions from combustion of fossil fuels No - from stationary or mobile sources 5.2 Emission from production processes No - 5.3 Emissions from materials handling No - including storage or transport rules) 5.4 Emissions from construction activities No - including plants and equipment 5.5 Dust or orders from handling of materials There will be formation of dust including construction materials, sewage during loading/unloading and Yes and waste handling of construction material. 5.6 Emissions from incineration of waste No - 5.7 Emission from burning of waste in open No - air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No -

6. Generation of Noise, vibration, Emissions of Lights and Heat. Sr.No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data 6.1 From operation of equipment e.g. No - engines, ventilation plant, crushers. 6.2 From Industrial or similar processes No - 6.3 From construction or demolition No - 6.4 From blasting or piling No - 6.5 From construction or operational traffic Yes During operational activities noise will be generated due to traffic but there will not be any significant increase in the noise due to the proposed project. 6.6 From lighting or cooling system No - 6.7 From any other sources No -

9

7. Risk of accidents during construction or operation of the Project, which could affect human or the environment. Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data 7.1 From handling, storage, use or spillage of No - hazardous materials 7.2 From discharge of sewage or other There will not be any chances of effluents to water or the land (expected No land/water contamination from mode and place of discharge) sewage. 7.3 By deposition of pollutants emitted to air, No - into the land or into water 7.4 From any other source No - 7.5 Is there a risk of long term build up of No All EMS components shall run pollutants in the environment from these round the clock. sources?

8. Risk of accidents during construction or operation of the project, which could affect human of the environment Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, Wherever possible) with source of information data 8.1 From explosions, spillages, handling, use No - or production of hazardous substances 8.2 From any other causes No - 8.3 Could the project be affected by natural Yes Project area is categorized in disasters causing environmental damage the Seismic Zone III which is (e.g. floods, earthquakes, landsides, classified as having a fairly cloudburst etc.)? medium probability of earthquake shocks.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality. Sr. No. Information/checklist confirmation Yes/No Details there of (with approximate quantities/rates, 10

Wherever possible) with source of information data 9.1 Lead to development of supporting Yes This is a building and facility ancillary development or construction project which will development stimulated by the project lead to the further which could have impact on the development of surrounding environment e.g. area.  Supporting infrastructure (roads, power supply, wastewater treatment, etc.  Housing development  Supply industry Others 9.2 Lead to after-use of the site, which could No - have impact on the environment. 9.3 Set a precedent for later development No - 9.4 Have cumulative effects due to proximity No - to other existing or planned project with similar effects.

11

(II) Environmental Sensitivity Sr.No. Areas Name/I Aerial distance (with 15 km) dentity proposed project location boundary 1. Areas protected under international - conventions, national or local legislation No for their ecological landscape, cultural or other related value 2 Areas which are important or sensitive - for ecological reasons –Wetlands, waster No courses or other water bodies coastal zone, biospheres, mountains, forests 3 Areas used by protected, important or - sensitive species of flora or fauna for No breeding, nesting foraging, resting, over wintering, migration. 4 Inland, coastal, marine or underground Nyari Dam @ 19 km Yes waters 5 States, National boundaries No - 6 Routes or facilities used by the public for access to recreation or other tourist, No Public transportation pilgrim areas] 7 Defense installations No - 8 Densely populated or built-up area Project is situated in well Yes developed area of Madhapar, Rajkot 9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of Yes - worship, community facilities) 10 Areas containing important, high quality - or scarce resources (ground water No resources, surface resource, forestry, agriculture, fisheries tourism, minerals) 11 Areas already subjected to pollution or - environmental damage (Those where No existing legal environmental standards are exceeded.) 12 Areas susceptible to natural hazard which - could cause the project to present environmental problems.(earthquakes, No subsidence, landslides, erosion, flooding or extreme or adverse climates condition)

12

III) Proposed Terms of Reference for EIA studies:

As per the EIA Notification, 14th September 2006 of MoEF, New Delhi, no EIA required as the built up area is < 1,50,000/- Sq. m. even though it will be conducted as the TOR issued by SEAC.

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.”

Date: 15/12/2018 Signature of the applicant

Place: Rajkot (Project Proponent / Authorized Signatory)

Name: Nayanbhai Gangani Full Address: Revenue Survey No. 56/P1, Madhapar, Taluka Rajkot, Dist: Rajkot

13

ANNEXURE – I AREA STATEMENT

Plot Area 8409.45 Sq. m Built up Area 28727.17 Sq. m Built up Area, FSI 22610.48 Sq. m Nos. of Blocks 5 buildings Nos. of Flats 3 BHK 144 Flats 4 BHK 36 Flats

14

ANNEXURE – II

WATER AND WASTEWATER DETAILS

 Water and Wastewater Details (CONSTRUCTION PHASE)  Source: Local Tanker Supply

Water Wastewater Sr. Purpose Consumption Generation Remarks No. (KL/day) (KL/day) Wastewater Domestic will be 80% 1 40 workers x 30 Lit/day = 2.1 KL/day 1.2 0.96 of the

requirement 2 Construction and Sprinkling Acitivities 20 - - Total 21.2 0.96 -

Mode of Disposal: Domestic wastewater generation is disposed off in soak pit.

 Water and Wastewater Details (OPERATION PHASE)  Source: RUDA and Recycled from STP

Fresh Water Treated water Wastewater Sr. Purpose Consumption consumption Generation No. (KL/day) (KL/day) (KL/day) Domestic 1 180 units (3&4BHK) x 6 person/unit x 97 65 129.6 150 Lit/day/person = 162 KL/day 2 Greenbelt - 6.0 - Total 97 71.0 129.6

Total water consumption: 168 kld (Fresh 97 kld & Treated 71 kld)

Mode of disposal:  Sewage to be generated will be treated in the proposed onsite STP. Treated sewage will be reused for gardening and flushing purpose within premises and remaining quantity of sewage will be discharged into the underground drainage line of Rajkot Urban Development (RUDA).  Capacity of proposed STP will be 200 kld  STP Technology: STP with MBBR technology.  Treated water will be reused for gardening and flushing purpose.  Quantity of treated water to be reused: Gardening (KL/day): 6.0, Flushing (KL/day): 65.0 15

 Dual plumbing system will be provided for reuse of treated water in flushing system

16

ANNEXURE – III

 Municipal Solid Waste Generation (CONSTRUCTION PHASE)

Sr. No. Description Quantity (kg/day) 1 Domestic (40 worker x 500 gm/person/day) 20 Total 20

 Municipal Solid Waste Generation (OERATION PHASE)

Sr. No. Description Quantity (kg/day) Domestic 1 180 Units (3&4BHK) x 6 person/unit x 500 540 gm/person/day = 540 kg/day Total 540

17

ANNEXURE – IV

KEY PLAN

18