Social Monitoring Report
Semestral Report June 2016
PRC: Xi’an Urban Road Network Improvement Project
Prepared by Xi’an Municipal Government for People’s Republic of China and the Asian Development Bank.
NOTE
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Xi’an Urban Road Network Improvement Project
External Monitoring and Evaluation Report for RP Implementation (Phase III)
Center for River Engineering Technical Research of Shaanxi Province June 2016
Contents
I. Implementation Schedule of Project ...... 2
II. Impact of Land Acquisition and Demolition ...... 6
III. Monitoring of Land Acquisition and Demolition ...... 13
1. Monitoring scope ...... 13
2.Monitoring method ...... 14
3. Monitoring process ...... 14
4. Monitoring information and data analysis ...... 15
IV. Land Acquisition, Demolition and Resettlement ...... 18
1. Progress of land acquisition ...... 18
2. Progress of house demolition ...... 20
V. Execution of resettlement policy ...... 24
1. Land acquisition ...... 24
2. Housing acquisition ...... 25
3. Other facilities ...... 30
4. Payment of compensation fee ...... 30
VI. Public Participation ...... 32
VII. Conclusions and Suggestions ...... 35
1. Conclusions ...... 35
2. Suggestions ...... 35
Contents of Tables
Table 1 Distribution of the affected areas ...... 7
Table 2Summarization of Update Data and Planning Data of Land Acquisition and Demolition Impact ...... 9
Table 3 Statistics of affected attachments and infrastructures of each subproject ...... 12
Table 4 Questionnaire on basic information of 950 sampled affected households ...... 18
Table 5 Implementation schedule of land acquisition (by the end of December 2015) ...... 19
Table 6 Implementation progress of housing acquisition (up to the end of December 2015) ...... 22
Table 7 Actual implementation standards of land acquisition ...... 24
Table 8 Actual executive standards of housing acquisition ...... 25
Table 9 Compensation standard table for auxiliary facilities ...... 30
Table 10 Information disclosure ...... 32
Table 11 Public participation of relocation and resettlement ...... 33 Contents of Figures
Figure 1 Location plan of road network improvement subproject ...... 2
Figure 2 Fund flow diagram ...... 31
Xi’an Urban Road Network Improvement Project with ADB Loan
External Monitoring Report for RP Implementation Xi’an serves as the capital as well as the political, economic and cultural center of Shaanxi Province. As one of the most important growth poles in West China, Xi’an realized average annual growth rate of population of 1.85% and annual growth rate of GDP of 13.5% from 2000 to 2007. During the period, the annual growth rate for total number of registered vehicles was 12.2%. An effective urban road network is essential for the development of a city and can ensure that all the functions of the city are performed efficiently and social and economic development is facilitated. In recent years, the construction level, service level and operation efficiency of urban infrastructure in Xi’an have been improved greatly, but there are still some problems. For example, the road network is not very efficient, the links among different roads are limited, and some roads have too much traffic; urban entrance and exit have traffic jams, and it is difficult to connect with the expressways; east-west and south-north arterial roads in old urban area are faced with big pressures; there are less pedestrian crossing facilities, and pedestrians, vehicles and non-motor vehicles intermingle in a manner that impacts all three adversely; lack of parking facilities force vehicles to park on the side of the road, exacerbating traffic congestion. To build an efficient, convenient, and environmentally advantageous modern traffic system, perfect urban infrastructure system, and comprehensively improve urban service functions, Xi’an plans to make use of an ADB loan, and attempts to promote the construction and systematic management of urban integrated transportation system by an all-round and overall scheme, thus facilitating the sustainable development of urban economy. The project will build connecting lines for urban road, interchanges, develop bus priority, construct non-motor vehicles roads, improve pedestrian safety, construct comprehensive transportation hub, enhance traffic management, and control traffic emission. In January 2012, Xi’an and ADB signed an agreement on loan of US$ 150 million. In order to better solve the urban traffic problems, relieve traffic jam, improve road safety, enhance the urban carrier function and ensure a rapid, sound and ordered development of the city, Xi’an Municipal People’s Government uses the loan of Asian Development Bank (ADB for short) to initiate the urban road network improvement and public facilities construction project in Xi’an, including (i) road and bridge improvement; (ii) pedestrian safety; (iii) comprehensive transportation facilities; (iv) intelligent transport system (ITS) and safety education for drivers; (v) environment protection enhancement. Besides, the project provides EA/IA with consulting service for project management and capacity building. See Figure 1-1 for the location plan of road network improvement subproject.
1
Figure 1 Location plan of road network improvement subproject Only subprojects 1 and 3 in the project involve resettlement. The resettlement plan was formulated in 2011. In September 2012, the project implementation agency determined the first batch of subprojects (east section of Kunming Road, Zhuhong Road-North 2nd Ring Interchange, Zhuhong Road-Fengcheng 4th Road Interchange, Hongmiaopo Interchange, and Xinghuo Road Interchange) and finished their primary design schemes. In March 2013, the resettlement plan was updated in accordance with the primary design and the updated plan was approved by ADB in September 2013 (hereinafter referred to as “the updated resettlement report for the first batch of subprojects”). In April 2014, the project implementation agency determined the preliminary design scheme for Fengcheng 8th Road-Taihua Road Interchange subproject, and the resettlement plan was updated based on the preliminary design. The updated plan was obtained by ADB in Decemebr 2014 (hereinafter referred to as “updated resettlement plan for Fengcheng 8th Road-Taihua Road”). In April 2014, the project implementation agency determined the preliminary design scheme for Dazhai Road subproject and the updated resettlement plan of Dazhai Road was approved by ADB in November 2015. In September 2015, the project implementation agency determined the preliminary design scheme for Keji 2nd Road subproject. ADB approved the updated resettlement plan of Keji 2nd Road in May 2016.
I. Implementation Schedule of Project 1. The overall implementation schedule for road & bridge improvement subprojects is as below: (1) Kunming Road: Design change of road. In the original design, Kunming Road, after extension, would cover the polluted river channel. Based on the modified design, however, a river-crossing bridge that will become a part of expressway corridor in Xi’an will be constructed. The feasibility research on
2 expressway corridor has been approved by the municipal government. Due to design change and delay of implementation, Xi’an Urban and Rural Construction Commission and Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. will make use of the government funds to construct roads. By the end of June 2016, the land acquisition and demolition work was not started. (2) Zhuhong Road-North 2nd Ring Interchange: The original design scheme involves the demolition for Community of Sinohydro Corporation Engineering Bureau 15, but based on the evaluation of social stability risks required by Xi’an Municipal People’s Government, only 89% of residents agree to the removal, failing to meet the requirement (95%). Hence, west-north cloverleaf with left-hand turns in the original design is changed into a west-north directional ramp with left-hand turns, avoiding the demolition for Community of Sinohydro Corporation Engineering Bureau 15. Currently, all of the land occupied by the project is allocated state-owned land1. The demolition problem of a public toilet left during the inspection of ADB delegation in September 2014 was completely solved in the end of May 20152. In June 2016, the principal part of the interchange was completed and the interchange has been open to traffic in the north and south direction. (3) Zhuhong Road-Fengcheng 4th Road Interchange: According to the updated resettlement report for the first batch of subprojects, Zhuhong Road-Fengcheng 4th Road Interchange involves no land acquisition and demolition. But the migration of some trees and water supply pipeline network are involved, which has been finished. Besides, the invitation of tender for civil engineering has been accomplished, and construction conditions are possessed. The project is being implemented in accordance with the schedule, main works for bridge of mainline have been completed and marked line and lighting engineering is under construction. The main bridge was open to traffic on May 26, 2016. (4) Hongmiaopo Interchange: The northeast, northwest and southwest corners of Hongmiaopo Interchange involve no land acquisition. 104 households in Fangxin Community of Fangxin Group under the jurisdiction of State-owned Supervision and Administration Commission of Xi’an People’s Government will be affected by the southeast part of the project. On December 17, 2015, Xi’an Qujiang Daming Palace Heritage Site Area Preservation and Development Office held the demonstration meeting of compensation scheme for housing acquisition of Hongmiaopo interchange project. The acquisition announcement for Hongmiaopo interchange project Announcement of Xi’an Municipal People’s Government on Determining Housing Acquisition (Shi Fang Zheng Gao Zi [2016] No.1) was obtained on March 22, 2016. Currently, the asset value evaluation for 88 affected households has been accomplished, and the initial resettlement agreement has been signed with 25 affected households. For the rest households, asset value evaluation and negotiation of signing resettlement agreement are being conducted. The enclosure formalities for main part of the interchange project have been handled and construction has been started. And rainwater pumping station and pipeline are under construction. The pipeline migration and structural construction of main maintenance poles will be conducted with enclosure in case of hazy weather.
1 By the end of December 2015, the certificate for state-owned land use right is still being handled. 2 In April 2015, Daxing Reconstruction Office in Weiyang District signed an agreement with Jintao Company, and in the end of May 2015, the demolition was finished. A new toilet with the same area as before is built at the place 800m away from the original site for Jintao Company to use. Besides, RMB 15,000 Yuan is provided as subsidy for relocation. The original contract is still effective. 3
(5) Xinghuo Road Interchange: 11 households in Fenghe Village at west side of Xinghuo Road will be affected, and land acquisition and demolition of the households will be included in the urban village reconstruction plan for over 1,700 households in Fenghe Village, but the reconstruction work has made no breakthrough. seven enterprises and public institutions and 147 residents in Railway Community at east side of Xinghuo Road will be affected, and after negotiation with Housing Management Department of Xi’an Railway Bureau for many times, The evaluation on Xitie Bachelor Apartment and Xitie Residential Building has been finished at present, and the evaluation on all non-residential houses (7 enterprises and public institutions and 15 stores facing the street) has been completed. So far, the agreement on acquisition compensation has been signed with 5 households (two for units and three for stores); the doors and windows of five stores facing the street have been demolished. It is difficult to come to an agreement with the Bureau of Railway Management on the affected railway maintenance buildings at the west side of the construction site. POM will change the project design to avoid the influence on the west part of construction site. Currently, auxiliary road and rainwater pipeline under the auxiliary road at west side to south of Xinghuo Road and West Ziqiang Road have been constructed. Traffic dispersion line 134m long and 4.5m wide for west auxiliary road at Xinghuo Road (Fenghe Road-East Xinghuo Lane), D 3,000mm pipeline 206m long for moat water-break engineering, D 4,000mm pipeline of 188m, Φ600 maintenance piles for moat water-break, and 18 Φ800 maintenance piles for main works have been completed. (6) Fengcheng 8th Road-Taihua Road Interchange: Main resettlement activities for the subproject include information manual provision, mobilization meeting, policy publicity, as well as detailed measurement and investigation by Land and Resources Bureau and real estate evaluation company from January to June 2015. Contract on the interchange engineering was signed with Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. on November 16, 2015 and filed by Xi’an Urban and Rural Construction Commission on November 19. By the end of December 2015, the land acquisition and demolition agreement for Fengcheng 8th Road-Taihua Road Interchange subproject was signed, By May 20, 2016, the houses at the southeast corner of the interchange was demolished, with demolished area of about 5,926m2; garbage at the site was collected, and funds of RMB 9.367 million Yuan was paid. However, garbage of 60,000-70,000m3 within the red line of road at the northeast corner was not collected. There are 57 stores, with building area of about 5,000m2 and now the demolition office has organized and convoked a removal and relocation meeting. The northwest corner involves one green square, and three two-storied buildings, with building area of 5,000m2, which involves no resettlement. (7) Dazhai Road: The resettlement plan of Dazhai Road has been updated and reported to ADB and approved. By December 30, 2015, the collective land involved in Yanta District project was rented by the Administrative Committee of Yuhua Industrial Park. The Administrative Committee of Yuhua Industrial Park is negotiating with Erfuzhuang Village and Minqizhai Village, and attempts to completely acquire the collective land in the two villages through urban village reconstruction. Then the village collection and peasant households will be compensated according to the price of land acquisition. In November 2014, the implementation plan on Urban Village Reconstruction of Erfuzhuang Village was reported to Xi’an Urban Village Reconstruction Office from Yanta District Urban Village Reconstruction Office. All 4 residential houses and most enterprises and public institutions involved in the project have been demolished, and seedlings have been moved. Shaanxi Jianxin Doors & Windows Factory still has a leftover problem. Due to the time-based effect of evaluation report, the previous evaluation report for the factory has lost its efficacy, and the implementation agency reevaluates it. The latest evaluation report has come out and negotiation on demolition agreement is being conducted with enterprises. The Administrative Committee of Yuhua Industrial Park spent RMB 800,000 Yuan on installing self-help water supply machine in Erfuzhuang Village on December 2014, so as to solve the water supply problem of Erfuzhuang after the demolition of water tower. As for Zhongbaozi Village of Lianhu District involved in the project, the enclave has not been acquired, and the financial problem has been solved; the four enterprises of Heping Industrial Park involved have reached verbal agreement that they will dismantle the buildings within the red line of road, and will not affect construction entry, which provides a guarantee for the on-site construction. (8) Keji 2nd Road: The preliminary design of Keji 2nd Road project was completed in September 2015, ADB approved the updated resettlement plan of Keji 2nd Road in May 2016.. Land in the section of Dingjiaqiao Village has been provided after the urban village reconstruction, and by the end of 2015, building demolition and garbage collection in the section were completed; an agreement on the land acquisition and demolition for the section of Xi’an International University has been reached with Xi’an International University and village collective, and the compensation agreement has been signed, and building (structure) demolition on the ground has been started since November 14, 2015. Currently, the land acquisition work meeting of Xiaoyanzhuang Village was held on January 11, 2016, and the matters on land acquisition are being discussed; demolition involves 29 households in the section of Xiaoyanzhuang Village, and after the land acquisition, homestead of 29 households will be demolished first; an agreement on the land acquisition and demolition of Fenghui Apartment in Yuhuazhai Village was signed with the owner and village collective in September 2014, building demolition and garbage collection have been finished; an agreement on the land of Bodi School has been signed with the owner and village collective, and seedlings have been migrated; a consensus on the land acquisition and demolition in Yuahua Industrial Park has been reached with Ruier Kang Container Plant, Sirui and Gaorui, compensation agreement for demolition has been signed with three enterprises, relocation involving workshop equipment has been completed, handover formalities for vacant room have been handled, demolition has been started, and building demolition and garbage collection have been accomplished, meeting the road construction requirements; it was agreed in urban village reconstruction in the end of 2013 that the land in Yingfazhai Village was reserved by the government. Tomb and nursery stock migration has been finished, but the certificate for state-owned land use right has not been obtained; the agreement on collective land acquisition involved in Yuhuazhai section was signed in the middle of June 2016. 2. Multimodal Interchange Facilities (MIF) subproject covers four comprehensive traffic hubs (Xi’an North Railway Station, Xi’an National Civil Aerospace Industrial Base, Yuhuazhai and International Trade & Logistics Park), five multistory parking garages, and five CNG Stations (included in four comprehensive traffic hubs, with the addition of Mujiangwang CNG Station). The overall implementation schedule is as below: 5
(1) Four comprehensive traffic hubs: The land for Bus Parking Lot of Xi’an North Railway Station was handed over to Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. in December 2014. So far, Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. has obtained written decision on state-owned construction land allocation as well as the approval from land resources department, Acquisition of road and greenbelt land has been completed. and construction land use permit is being handled, and the certificate for land use right has not been obtained. Yuhuazhai Transfer Station has been canceled. Xi’an Urban and Rural Construction Commission and Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. proposed to build another traffic hub in the west of Xi’an. However, by the end of June 2016, the place was not determined. The site selection of Xi’an National Civil Aerospace Industrial Base has been confirmed. The area of land acquired is reconfirmed to be 45 mu. Publicity was conducted by meeting, information inquiry, etc. was conducted to the affected persons in July 2015. The information includes basic information of project, project progress, housing demolition, compensation standard and removal for other facilities, appeal treatment mechanism, etc. By the end of January 2016, work was finished for the land acquisition and demolition of the project including: 1. signing of Land Acquisition Agreement; 2. work content of bidding agency (100%), and design bidding prepared to be started. 3. the draft due diligence report on project land acquisition and demolition has been completed.4. Preliminary design is being done. The next step is to rapidly complete the compensation for ground attachment, rapidly clean the site, and strive to complete all land acquisition as soon as possible. The design schedule and land occupation for traffic hub of Xi’an International Trade & Logistics Park have not been determined yet. (2) Five multistory garages: By the end of June 2016, the site selection of five multistory garages has not been determined. In view of the difficulty in acquiring land within the 2nd Ring Road, Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. suggests that the subproject should be cancelled. (3) Gas and CNG CNG Station: The original site of Mujiangwang CNG Station fails to meet the business demand, however, by the end of June 2016, an alternative site was not found. Therefore, Xi’an Urban Infrastructure Construction Investment Group Co., Ltd. suggests that the subproject should be cancelled.
II. Impact of Land Acquisition and Demolition Xi’an Urban Road Network Improvement Project with ADB Loan belongs to urban road and infrastructure construction project, and road & bridge improvement subprojects cover Keji 2nd Road, Dazhai Road, Kunming Road, Zhuhong Road-Fengcheng 4th Road Interchange, Zhuhong Road-North 2nd Ring Interchange, Hongmiaopo Interchange, Xinghuo Road Interchange, Fengcheng 8th Road-Beichen Avenue Interchange, Fengcheng 8th Road-Taihua Road Interchange; comprehensive traffic subprojects include Bus Parking Lot of Xi’an North Railway Station, CAIB Bus Parking Lot, Yuhuazhi Transfer Station, Transfer Station of Xi’an International Trade & Logistics Park, Yuhuazhai Parking Lot, Bus Parking Lot of International Trade & Logistics Park, Multistorey Parking Garage of Xizhan Community, Ring Road-Taihua Road Multistorey Parking Garage, Xianning Road-Dongguannan Street Multistorey Parking Garage, Mujiangwang CNG Station, CNG Station of CAIB Bus Parking Lot,
6
CNG Station of Xi’an North Railway Station, Yuhuazhai CNG Station, and CNG Station of Xi’an International Trade & Logistics Park. After formulating the preliminary design scheme for the project, the project implementation agency updated the original resettlement plan (draft) correspondingly and investigated the impact of land acquisition and demolition based on the preliminary design scheme. The affected areas cover three economic and technological development zones, six subdistrict offices and two industrial parks in five administrative districts in Xi’an (Weiyang District, Lianhu District, Chang’an District, Yanta District, Baqiao District), as well as Xi’an International Trade & Logistics Park, Daming Palace Preservation and Renovation Office, and Daxing Reconstruction Office in Weiyang District. After implementation of the project, the project implementation agency makes an inventory of and registers the number and type of affected objects.
1. Affected districts The affected districts include Weiyang District, Lianhu District, Chang’an District, Yanta District, and Baqiao District in Xi’an. See Table 1 for details.
Table 1 Distribution of the affected areas Subdistrict office/ Economic and Category Type No. Engineering name County/district technological development zone
1 Keji 2nd Road Yanta District XHTZ
Yuhua Industrial Yanta District, 2 Dazhai Road Park, Heping Lianhu District Industrial Park Road East section of Yuhuazhai Subdistrict 3 Lianhu District Kunming Road Office
West section of Yuhuazhai Subdistrict 4 Lianhu District Kunming Road Office Zhuhong Xi’an Economic & 5 Road-Fengcheng 4th Weiyang District Technological Road Interchange Development Zone Xi’an Economic & Road & bridge Technological improvement Development Zone, subproject (Xi’an Zhuhong Road-North Weiyang Palace 6 nd Weiyang District Municipal Public 2 Ring Interchange Subdistrict Office, Utility Bureau) Daxing Reconstruction Office in Weiyang District Daming Palace Interchange Hongmiaopo Weiyang District, Preservation and 7 Interchange Lianhu District Renovation Office, Daxing New District Daming Palace Xinghuo Road Weiyang District, Preservation and 8 Interchange Lianhu District Renovation Office, Daxing New District Fengcheng 8th Tanjia Subdistrict 9 Road-Beichen Avenue Weiyang District Office Interchange Fengcheng 8th Tanjia Subdistrict 10 Road-Taihua Road Weiyang District Office Interchange 7
Subdistrict office/ Economic and Category Type No. Engineering name County/district technological development zone Xi’an Economic & Bus Parking Lot of Xi’an 11 Weiyang District Technological North Railway Station Development Zone Economic & Bus parking Technological lot CAIB Bus Parking Lot Development Zone of 12 Chang’an District Xi’an National Civil Aerospace Industrial Base Yuhuazhai Transfer 13 Yanta District Yuhua Industrial Park Station Metro transfer hub Transfer Station of Xi’an International 14 Xi’an International Baqiao District Trade & Logistics Trade & Logistics Park Park Yuhuazhai Bus Parking 15 Yanta District Yuhua Industrial Park Lot Bus Parking Lot of Xi’an Xi’an International Multimodal 16 International Trade & Baqiao District Trade & Logistics Interchange Logistics Park Park Facilities (MIF) Urban Multistorey Parking subproject (Xi’an Yuhuazhai Subdistrict multistory 17 Garage of Xizhan Lianhu District Urban Office parking Community Infrastructure garage Ring Road-Taihua Construction Taihua Subdistrict 18 Road Multistorey Xincheng District Investment Group Office Co., Ltd.) Parking Garage Xianning Road-Dongguannan Dongguannan 19 Beilin District Street Multistorey Subdistrict Office Parking Garage Mujiangwang CNG Hongqi Subdistrict 20 Baqiao District Station Office
CNG Station of CAIB 21 Chang’an District Xi’an National CAIB Bus Parking Lot Xi’an Economic & CNG Station of Xi’an CNG Station 22 Weiyang District Technological North Railway Station Development Zone Yuhuazhai Subdistrict 23 Yuhuazhai CNG Station Yanta District Office CNG Station of Xi’an Xi’an International 24 International Trade & Baqiao District Trade & Logistics Logistics Park Park
8
2. Type and Category of the Impact
Table 2 Summarization of Update Data and Planning Data of Land Acquisition and Demolition Impact Residential housing Enterprises and institutes Land Updated resettlement plan Updated resettlement acquisition in plan Category Type No. Project name the updated Households Area m2 Amount Area m2 resettlement plan ha)
1 Keji 2th Road 17.18 74 87,849.48 6 63,863.45 2 Dazhai Road 9.2 29 14,930.13 15 37,004.56 13.34 0 2 71,000 Road 3 East Section of Kunming Road
4 West Section of Kunming Road
0 0 0 0 0 Zhuhong Road –-Fengcheng 4th Road 5 Road and Interchange interchange 3 improvement 0 0 1 11,719 Zhuhong Road- North 2nd Ring Road subproject(MPU 6 0.67 A) Interchange
Interchange 0.52 0 0 1 7,855 7 Hongmiaopo Interchange
4 1.33 0 0 5 0 8 Xinghuo Road Interchange 0
10 Not yet been updated Not yet been updated 9 Fengcheng 8th Road - Beichen Road
3 Enterprise in the resettlement plan updated in 2013 refers to the demolition of residential area of Sinohydro Corporation Engineering Bureau 15 Co., Ltd. However, in the risk assessment of social stability required by Xi’an Municipal People’s Government, only 89% of the residents agreed the demolition, which fails to meet the requirement of 95%. Therefore, the original left-turn cloverleaf ring road from west to north is changed as left-turn directional ring road from west to north, so as to avoid the demolition for resident area of Sinohydro Corporation Engineering Bureau 15 Co., Ltd. 4 Interchange involves 11 residences in Fenghe Village, but the data of which are absent from the resettlement plan updated in 2013. 5 Xinghuo Road Interchange involves the demolition of several enterprises and public institutions as well as shops, but the data of which are absent from the resettlement plan updated in 2013. 9
Land Residential housing Enterprises and institutes acquisition in Updated resettlement plan Updated resettlement Category Type No. Project name the updated plan resettlement Households Area m2 Amount Area m2 plan ha) 5.633 0 2 4,960 Fengcheng 8th Road - Taihua Road 10 Interchange
6.67 Not yet been updated Not yet been updated 11 Xi’an North Railway Station Bus Parking Lot of Bus parking lot 12 Bus parking lot of XCAIB Bus Parking Lot 6.67
Yuhuazhai Comprehensive Transfer Station 13 3.33 Metro (some station in the west part of Xi’an city) transfer junction Comprehensive Xi'an International Trade & Logistics 14 3.33 transportation Park Synthetic Transfer Junction Station facilities subproject (Xi’an Urban 15 Yuhuazhai Bus Parking Lot 0.53 Infrastructure Construction Xi'an International Trade & Logistics Park Bus Investment 16 0 Group Co., Ltd.) Parking Lot
Urban 17 Xizhan Community Multistory Parking Garage 0 multistory parking garage Ring Road - Taihua Road Multistory Parking 18 0.53 Garage
Xianning Road - Dongguan Nanjie Multistory 19 0.53 Parking Garage
10
Land Residential housing Enterprises and institutes acquisition in Updated resettlement plan Updated resettlement Category Type No. Project name the updated plan resettlement Households Area m2 Amount Area m2 plan ha)
20 Mujiangwang CNG Station 0.55
21 XCAIB CNG Station 0.55
CNG 22 Xi’An North Railway Station CNG Station 0.55 station
23 Yuhuazhai CNG Station 0.55
Xi'an International Trade & Logistics Park CNG 24 0.55 Station
Total 82.213 xx xx xx Note: The final scheme of Xinghuo Road is not confirmed, and the above data is acquired through previous design survey. Note: The affected area of Xinghuo interchange belongs to urban village reconstruction scope; if the reconstruction starts first,, the land demanded by the project is allocated by urban village reconstruction office. Note: The new increased lands of subprojects are all state owned land.
11
The project implementation agency will be responsible for compensating and recovering the ground attachments and infrastructure according to the replacement price. The ground attachments demolished in each subproject include 3,024 mature trees, 6,069 young trees, 1,860 fencing, two toilets, and 14,860 m2 lawn. Besides, the affected special facilities include 20,105 meters electric wire, 14,490 meters telecommunication wire, 240 power poles, 1,093 meters communication optical cables, 31 transformers, 14 high-voltage towers, 13,667 water pipes, 1 overpass, 2 emergency communication stations, and 227 street lamps. See Table-3 for details, the data in the brackets is the original data of the resettlement plan.
Table 3 Statistics of affected attachments and infrastructures of each subproject
West Section Zhuhon Zhuhon Fengch Fengch of Keji Dazhai g Road XCAI g Road eng 8th eng 8th 2nd Road - B - North Road - Road - Road (Yanhua U Kunmin Fengch Hongmia Xinghuo Bus Item 2nd Ring Beichen Taihua (West n Road - Total nit g Road eng 4th opo Road Parki Road Road Road 3rd Ring West 3rd Road ng Intercha Intercha Intercha Road- Ring Intercha Lot nge nge nge Zhangb Road) nge a North Road 3,00 0)27 50 180 3,03 Mature trees — 20 6 55 40 — 0 8 159 446 4 2,030 5,03 4,30 400 30 20 0) 21 6,06 Young trees — 300 500 0 0 344 38 26 21 80 9 1,300 3,460 161 200 1,86 Fencing M — — 50 — — — 50 0 — 220 0 1,540
Toilet — — — — 0)1 — 1 0 — 4 1 — 2