The World Bank Report No: ISR5961

Implementation Status & Results Emergency Recovery and Disaster Management (P106449)

Operation Name: Emergency Recovery and Disaster Management (P106449) Project Stage: Implementation Seq.No: 9 Status: ARCHIVED Archive Date: 27-Sep-2011 Country: Bolivia Approval FY: 2008

Public Disclosure Authorized Product Line:IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Emergency Recovery Loan Implementing Agency(ies): Ministry of Planing and Development Key Dates Board Approval Date 20-Dec-2007 Original Closing Date 30-Jun-2011 Planned Mid Term Review Date 29-Oct-2010 Last Archived ISR Date 27-Sep-2011 Public Disclosure Copy Effectiveness Date 11-Dec-2008 Revised Closing Date 30-Jun-2012 Actual Mid Term Review Date 18-Oct-2010

Project Development Objectives Project Development Objective (from Project Appraisal Document) In support of the implementation of the National Plan for Sustainable Rehabilitation and Reconstruction (PRRES), the project will contribute to restore access to basic infrastructure for a portion of the affected population in five target regions, and to strengthen the Government#s ability at the national, sectoral, and municipal levels throughout the country to respond to future disasters. Has the Project Development Objective been changed since Board Approval of the Project?

Public Disclosure Authorized Yes No

Component(s)

Component Name Component Cost Strengthening the National System for Risk Management 2.30 Rehabilitation, Reconstruction, and Small Mitigation Works 14.50

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Public Disclosure Authorized

Implementation Status Overview During a supervision mission conducted between January 9 and January 20, 2012, the GoB reported: (i) a portfolio of 182 subprojects, amounting to approximately US$2.8 million from the credit, have been fully implemented in the departments of Sta. Cruz, Chuquisaca, Cochabamba, Potosi, , Beni, Pando, and Tarija; (ii) a second portfolio of 43 subprojects was being prepared by the GoB for further review; and (iii) corrective measures were being taken in order to reduce the implementation delays associated with Public Disclosure Copy Component 1.

Page 1 of 6 Public Disclosure Authorized The World Bank Report No: ISR5961

The project coordinator, the financial and procurement specialists are key to the successful technical implementation of this project. These responsibilities were reassigned to the Directorate of Administrative Affairs of the Ministry of Planning and Development, as all DRM functions remain within the Ministry under the Vice Ministry of Planning and Coordination.

Delays in project effectiveness and high turnover within the project's ministerial counterparts have resulted in moderate implementation delays, particularly as they pertain to Component 1.

During the next supervision mission, the project team will reassess implementation progress and discuss the next steps to complete the project.

Locations Country First Administrative Division Location Planned Actual

Public Disclosure Copy Bolivia Departamento de Potosi Yocalla

Bolivia Departamento de Potosi

Bolivia Departamento de Potosi Villazon

Bolivia Departamento de Cochabamba Villa Tunari

Bolivia Departamento de Potosi Puna

Bolivia Departamento de Potosi Urmiri

Bolivia Departamento de Potosi Uncia

Bolivia Departamento de Potosi

Bolivia Departamento de Potosi Tomave

Bolivia Departamento de Potosi Tacobamba

Bolivia Departamento de La Paz

Bolivia Departamento de Santa Cruz San Pedro

Bolivia Departamento del Beni San Javier

Bolivia Departamento de Santa Cruz Saipina

Bolivia Departamento de Potosi Ravelo

Bolivia Departamento de Cochabamba Puerto Villarroel

Bolivia Departamento de Santa Cruz Pailon

Public Disclosure Copy Bolivia Departamento de Tarija Padcaya

Bolivia Departamento de Santa Cruz Okinawa Numero Uno

Page 2 of 6 The World Bank Report No: ISR5961

Country First Administrative Division Location Planned Actual Bolivia Departamento de Cochabamba Mizque

Bolivia Departamento de Santa Cruz Mineros

Bolivia Departamento de La Paz

Bolivia Departamento del Beni Loreto

Bolivia Departamento de La Paz Departamento de La Paz ✔

Bolivia Departamento de Cochabamba Khuchumuela

Public Disclosure Copy Bolivia Departamento de Santa Cruz General Saavedra

Bolivia Departamento de Potosi

Bolivia Departamento de Potosi

Bolivia Departamento de Santa Cruz Colonia Japonesa San Juan

Bolivia Departamento de Cochabamba Cliza

Bolivia Departamento de Potosi Chaqui

Bolivia Departamento de La Paz

Bolivia Departamento de Potosi Caiza

Bolivia Departamento de Potosi Betanzos

Bolivia Departamento de Potosi Betanzos

Bolivia Departamento de Pando Agua Dulce

Bolivia Departamento de Chuquisaca Culpina

Bolivia Departamento de Chuquisaca Incahuasi

Bolivia Departamento de Chuquisaca Las Carreras

Bolivia Departamento de Chuquisaca Sucre (Capital)

Bolivia Departamento de Chuquisaca Villa Serrano

Bolivia Departamento de Chuquisaca Villa Zudanez (Tacopaya)

Public Disclosure Copy Bolivia Departamento de Chuquisaca Yotala

Bolivia Departamento de Santa Cruz Fernandez Alonso

Page 3 of 6 The World Bank Report No: ISR5961

Bolivia Departamento de Santa Cruz San Carlos

Bolivia Departamento de Santa Cruz El Torno

Bolivia Departamento de Tarija Bermejo

Bolivia Departamento de Santa Cruz San Julian

Bolivia Departamento de Santa Cruz Warnes

Bolivia Departamento de Santa Cruz Yapacani

Bolivia Departamento del Beni San Andres Public Disclosure Copy Bolivia Departamento del Beni Santa Ana

Bolivia Departamento de Chuquisaca Yamparaez

Bolivia Departamento de La Paz Palca

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Number of infrastructure facilities restored and Text Value 0 182 subprojects completed 225 subprojects and 526,548 number of beneficiaries. benefiting 256,428 beneficiaries beneficiaries Date 27-Feb-2009 31-Dec-2011 30-Jun-2012 Comments There is mistake under the previous indicator. It references 570,741 individuals, but in fact there were 170,741 Disaster Risk Management Units established in Text Value 0 3 & 3 9 sectoral and 9 departmental 9 target sectors and 9 departments; staff DRM units established trained; staff of units fully paid by respective Date 27-Feb-2009 01-Jul-2011 30-Jun-2012 entities; submission by all 9 sectors of sectoral risk Mgmt. Comments Progress is being made towards the establishment of 3 sectoral and 3 departmental DRM units.

Public Disclosure Copy Intermediate Results Indicators

Page 4 of 6 The World Bank Report No: ISR5961

Indicator Name Core Unit of Measure Baseline Current End Target Recommendations for a National Risk Text Value 0 0 100% Management System submitted to the MPD for Date 11-Dec-2008 31-Dec-2011 30-Jun-2012 consideration. Comments In progress Percentage of trainees in the 9 target sectors Text Value 0 0 100% obtaining more than 75% in skills tests post Date 11-Dec-2008 31-Dec-2011 30-Jun-2012 training in risk prevention and vulnerability reduction. Comments The e-training will begin in February. Level of acceptance and participation of the Text Value 0% 100% 100% community regarding the works executed. Date 11-Dec-2008 31-Dec-2011 30-Jun-2012 Public Disclosure Copy Comments Level of acceptance for works executed under package 1 & 2. Package 3 is being implemented and requisite surveys will be conducted upon completion. Roads rehabilitated, Rural Kilometers Value 0.00 211.90 100.00 Date 11-Dec-2008 31-Dec-2011 30-Jun-2012 Comments

Data on Financial Performance (as of 26-Mar-2012)

Financial Agreement(s) Key Dates Project Loan No. Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P106449 IDA-43770 Effective 20-Dec-2007 11-Feb-2008 11-Dec-2008 30-Jun-2012 P106449 IDA-44400 Effective 05-Jun-2008 18-Nov-2008 22-Jun-2009 30-Jun-2012

Disbursements (in Millions) Project Loan No. Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P106449 IDA-43770 Effective XDR 8.00 8.00 0.00 2.78 5.22 35.00 P106449 IDA-44400 Effective XDR 2.70 2.70 0.00 1.53 1.17 57.00

Disbursement Graph Public Disclosure Copy

Page 5 of 6 The World Bank Report No: ISR5961 Public Disclosure Copy

Key Decisions Regarding Implementation A follow-up mission has been tentatively scheduled for mid 2012.

Restructuring History There has been no restructuring to date.

Related Projects P109057-Emergency Recovery and Disaster Management Project (AF) Public Disclosure Copy