UITKOMST COLLIERY PTY LTD:

INTEGRATED WATER & WASTE MANAGEMENT PLAN

SUBMITTED IN SUPPORT OF A WATER USE LICENSE AMENDMENT: 07/V30B/AG/357

FILE NO.: 16/2/7/V301/C/29

DISCLAIMER This report has been prepared by Cabanga Concepts, trading as Cabanga Environmental, with all reasonable skill, care and diligence within the terms of the contract with the client, and taking into account of the resources devoted to it by agreement with the client. We disclaim any responsibility to the client and any other in respect of any matters outside the scope of the project.

This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report, or any part thereof, is made known. Any such parties rely on the report at their own risk.

DOCUMENT CONTROL

Author: J. Barrett (BSc) Signature: Date: 21-04-2017

Approval: K.C.van Rooyen (MSc) Signature: Date: 25-04-2017 Pr.Sci.Nat

UITKOMST COLLIERY: IWWMP

TABLE OF CONTENTS

1. INTRODUCTION ...... 1 1.1 ACTIVITY BACKGROUND...... 1 1.2 APPLICANT DETAILS ...... 1 1.3 REGIONAL & LOCAL SETTING ...... 2 1.4 PROPERTY DESCRIPTION ...... 2 1.5 PURPOSE OF THE IWWMP ...... 3 2. CONCEPTUALISATION OF THE ACTIVITY ...... 8 2.1 DESCRIPTION OF ACTIVITY ...... 8 2.2 EXTENT OF ACTIVITY ...... 8 2.3 KEY ACTIVITY RELATED PROCESSES & PRODUCTS...... 8 2.4 ACTIVITY LIFE DESCRIPTION ...... 9 2.5 ACTIVITY INFRASTRUCTURE DESCRIPTION ...... 11 2.5.1 South Mine ...... 11 2.5.2 Klipspruit Mine ...... 14 2.6 KEY WATER USES & WASTE STREAMS ...... 16 2.7 ORGANISATIONAL STRUCTURE ...... 17 2.8 BUSINESS & CORPORATE POLICIES ...... 17 3. REGULATORY WATER & WASTE MANAGEMENT FRAMEWORK ...... 18 3.1 SUMMARY OF ALL WATER USES ...... 18 3.2 EXISTING LAWFUL WATER USES ...... 24 3.3 RELEVANT EXEMPTIONS ...... 24 3.4 GENERAL AUTHORISATIONS ...... 25 3.5 AMENDMENTS TO EXISTING USES ...... 25 3.6 NEW WATER USES TO BE LICENSED ...... 28 3.7 WASTE MANAGEMENT ACTIVITIES (NEM:WA) & AUTHORISATIONS ...... 29 3.8 OTHER AUTHORISATIONS & REGULATIONS...... 30 4. PRESENT ENVIRONMENTAL SITUATION ...... 31 4.1 CLIMATE ...... 31 4.1.1 Regional Climate ...... 31 4.1.2 Rainfall ...... 31 4.1.3 Evaporation ...... 31 4.2 SURFACE WATER (Letsolo, 2016) ...... 32 4.2.1 Water Management Area (WMA 7) ...... 32 4.2.2 Mean Annual Runoff (MAR) ...... 32 4.2.3 Flood peaks & volumes ...... 33 4.2.4 Surface Water Quality ...... 35

i | P a g e

UITKOMST COLLIERY: IWWMP

4.2.5 Resource Class & River Health ...... 39 4.2.6 Receiving Water Quality Objectives & Reserve ...... 47 4.2.7 Surface water User Survey ...... 48 4.3 SENSITIVE AREAS SURVEY ...... 49 4.4 GROUNDWATER (Future Flow, 2017) ...... 58 4.4.1 Aquifer Characterisation ...... 58 Upper weathered material aquifer: ...... 58 Lower fractured rock aquifer: ...... 59 4.4.2 Hydrocensus ...... 59 4.4.3 Potential Pollution Source Identification ...... 64 4.4.4 Groundwater Model Results: Operational ...... 64 Groundwater contamination: ...... 66 4.4.5 Groundwater Model Results: Long Term Post Operations ...... 71 Recovery of groundwater levels and decant potential: ...... 71 Contaminant migration: ...... 71 4.5 SOCIO-ECONOMIC ENVIRONMENT ...... 75 5. ANALYSIS & CHARACTERISATION OF WATER USE ACTIVITY ...... 77 5.1 SITE DELINEATION FOR CHARACTERIZATION ...... 77 5.2 WATER &WASTE MANAGEMENT ...... 77 5.2.1 Process Water ...... 79 5.2.2 Storm Water ...... 82 5.2.3 Groundwater ...... 83 5.2.4 Potable & Domestic Water Supply ...... 83 5.2.5 Water Balance ...... 84 5.2.6 Waste ...... 86 5.3 OPERATIONAL MANAGEMENT ...... 87 5.4 ORGANISATIONAL STRUCTURE ...... 87 5.5 RESOURCES & COMPETENCE ...... 88 5.6 EDUCATION & TRAINING ...... 88 5.6.1 Training Needs ...... 88 5.6.2 Specialised Skills ...... 88 5.6.3 Review of Training Material ...... 88 5.6.4 Records ...... 89 5.7 INTERNAL & EXTERNAL COMMUNICATION ...... 93 5.8 AWARENESS TRAINING ...... 93 5.9 MONITORING & CONTROL ...... 93 5.9.1 Surface water Monitoring ...... 93 5.9.2 Groundwater Monitoring ...... 95

ii | P a g e

UITKOMST COLLIERY: IWWMP

5.9.3 Biomonitoring...... 96 5.9.4 Waste Monitoring...... 97 5.9.5 Supplementary Monitoring Systems ...... 97 5.10 RISK ASSESSMENT ...... 98 5.11 ISSUES & RESPONSES FROM PUBLIC CONSULTATION PROCESS...... 108 5.12 ASSESSMENT OF LEVEL OF CONFIDENCE OF INFORMATION ...... 112 6. WATER & WASTE MANAGEMENT ...... 112 6.1 WATER & WASTE MANAGEMENT PHILOSOPHY ...... 112 6.2 STRATEGIES ...... 113 6.3 PERFORMANCE OBJECTIVES & GOALS ...... 114 6.3.1 Environmental Objectives and Goals ...... 114 6.3.2 Closure Objectives ...... 114 6.4 MEASURES TO ACHIEVE & SUSTAIN PERFORMANCE OBJECTIVES ...... 114 6.5 OPTION ANALYSES & MOTIVATION FOR IMPLEMENTATION OF PREFERRED OPTIONS 116 6.6 IWWMP ACTION PLAN ...... 116 Immediate to Short-Term Actions: ...... 116 Short-Term Actions: ...... 116 Medium-Term Actions: ...... 116 Long-Term Actions ...... 117 6.7 CONTROL & MONITORING ...... 117 6.8 MONITORING OF CHANGE IN BASELINE ...... 117 6.9 AUDIT & REPORT ON PERFORMANCE MEASURES ...... 117 6.10 AUDIT AND REPORT ON RELEVANT OF IWWMP ACTION PLAN ...... 118 6.3.3 Other Performance Assessments ...... 118 7. CONCLUSION ...... 121 7.1 REGULATORY STATUS OF ACTIVITY ...... 121 7.2 STATEMENT OF WATER USES REQUIRING AUTHORISATION, DISPENSING WITH LICENSING REQUIREMENT & POSSIBLE EXEMPTION FROM REGULATION ...... 125 8. REFERENCES ...... 126

LIST OF TABLES

Table 1: Contact Details ...... 1 Table 2: Property Details ...... 2 Table 3: Project Summary ...... 8 Table 4 Summary of all water uses ...... 19 Table 5: Application for GN704 Exemption ...... 24 Table 6: Summary of existing licensed uses and applicable amendment ...... 25

iii | P a g e

UITKOMST COLLIERY: IWWMP

Table 7: Summary of new water uses to be licensed ...... 28 Table 8: Mean monthly temperature, rainfall and precipitation (Station: Utrecht - V3E004) ... 31 Table 9: Delineated Catchments ...... 32 Table 10: Mean Annual Runoff (MAR) ...... 33 Table 11: Summary of calculations ...... 33 Table 12: Baseline Water Quality Results, November 2015 ...... 37 Table 13: Biomonitoring results (High Flow/Wet Season 2016) ...... 43 Table 14: Biomonitoring results (Low Flow/Dr Season 2016) ...... 45 Table 15: Overview of water availability and use in the Buffalo River Key Area ...... 47 Table 16: Wetland systems occurring in MRA (Hydro Pedo, 2017) ...... 53 Table 17: Hydrocensus results ...... 62 Table 18: Groundwater inflow volumes into the underground mining area ...... 66 Table 19: Demographics (Source: www.localgovernment.co.za) ...... 75 Table 20 MRDS Facility Specifications ...... 82 Table 21: Water Balance ...... 85 Table 22: Proposed waste management strategy on site ...... 86 Table 23: Environmental Awareness Training Requirements ...... 90 Table 24: Risk / Impact Assessment Summary ...... 100 Table 25: Issues & Response Summary ...... 109 Table 26: Measures to Achieve and Sustain Performance Objectives ...... 114 Table 27: Monitoring Plan ...... 118 Table 28 Status of water uses ...... 121

LIST OF FIGURES

Figure 1: Simplified process diagram (SLR, 2015) ...... 9 Figure 2: Current infrastructure at South Mine: Adit 1 (aerial photograph supplied by ESS Survey, April 2017) ...... 13 Figure 3: Proposed layout of Klipspruit Adit 2 (ESS, April 2017) ...... 15 Figure 4: Proposed of Klipspruit Adit 2 in relation to the existing old, PCD (Google Earth, 2016) ...... 16 Figure 5: Uitkomst Colliery BEE Organogram (Source: Pan African Resources PLC) ...... 17 Figure 6: NFEPA Wetland of relevance on site (SANBI, 2015) ...... 40 Figure 7: Quaternary catchment areas and fish support areas of relevance on site (SANBI, 2015) ...... 41 Figure 8: KZN aquatic biodiversity zones of relevance on site (SANBI, 2014) ...... 41 Figure 9: KZN terrestrial biodiversity areas in relation to the mineral boundary ...... 50 Figure 10: Mining Right Area in relation to Important Bird Areas (Harvey, 2017) ...... 52 Figure 11: Depth to groundwater level ...... 60 Figure 12: Topographical vs. groundwater elevation plot ...... 61

iv | P a g e

UITKOMST COLLIERY: IWWMP

Figure 13: Project Conceptualisation and operational hierarchy ...... 78 Figure 14: Existing Uitkomst Adit/Adit 1 Stockpiles ...... 81 Figure 15: Organogram for the implementation of the IWWMP ...... 87

LIST OF APPENDICES

APPENDIX 1: MINING RIGHT ...... 127 APPENDIX 2: CONFIRMATION OF BEE STATUS ...... 127 APPENDIX 3: APPROVED WATER USE LICENSE ...... 127 APPENDIX 4: ENVIRONMENTAL AUTHORISATION ...... 127 APPENDIX 5: SECOND QUARTER WATER MONITORING REPORT ...... 127 APPENDIX 6: WETLAND REPORT ...... 127 APPENDIX 7: AQUATIC BIOMONITORING REPORTS (2016) ...... 127 APPENDIX 8: GROUNDWATER REPORT ...... 127 APPENDIX 9: PROOF OF PUBLIC PARTICIPATION ...... 127 APPENDIX 10: ENGINEERING REPORTS / DESIGNS ...... 127 APPENDIX 11: MASTER PLAN ...... 127 APPENDIX 12: PROOF OF PAYMENT ...... 127 APPENDIX 13: WATER USE LICENSE FORMS ...... 127

v | P a g e

UITKOMST COLLIERY: IWWMP

1. INTRODUCTION

1.1 ACTIVITY BACKGROUND

Uitkomst Colliery has an approved water use license, License No. 07/V30B/AG/357, issued in terms of the National Water Act, Act 36 of 1998 for certain uses associated with its underground mining operations. The license was issued in the name of Brandywine Valley Investments (Pty) Ltd, on the 26 November 2011.

In terms of Point 5 of the Water Use License conditions, the license is valid for a period of ten (10) years, to be reviewed every two (2) years.

This Integrated Water and Waste Management Plan (IWWMP) is being submitted following the biennial review of the existing water use license, and addresses the amendments required to this license. Furthermore, this IWWMP addresses additional water uses associated with the recently acquired Klipspruit reserves.

1.2 APPLICANT DETAILS

Operations commenced at Uitkomst Colliery in 2006 under the ownership of Brandywine Valley Investments (Pty) Ltd.

Blue Falcon 232 Trading (Pty) Ltd acquired Brandywine Valley Investments (Pty) Ltd in April 2015, and applied for a Section102 in terms of the Minerals and Petroleum Resources Development Act, Act 28 of 2002 (MPRDA) to consolidate the mineral rights of Uitkomst Colliery with those of the proposed Klipspruit Mine. Approval of the Section 102 was issued in May 2016 (Mining Right Amendment No.: KZN 30/5/1/2/2/21 MR and 94 MR).

Pan African Resources PLC acquired Blue Falcon 232 Trading (Pty) Ltd taking effective control of the operations on 1 April 2016, and subsequently ceded the mineral rights to its subsidiary Uitkomst Colliery (Pty) Ltd (APPENDIX 1).

Table 1: Contact Details

Name of Applicant Uitkomst Colliery (Pty) Ltd

General Manager Johan Gloy

E-mail [email protected]

Telephone +27 (0) 87 285 1177

+27 (0) 82 857 8842

Fax +27 (0) 86 683 7018

Physical Address Uitkomst Farm, 27 km off R34 from Newcastle to Utrecht, KwaZulu Natal

1 | P a g e

UITKOMST COLLIERY: IWWMP

1.3 REGIONAL & LOCAL SETTING

The Uitkomst Colliery is located approximately 25 km northeast of Newcastle and 24 km northwest of Utrecht, in the Kwa-Zulu Natal Province. The operations fall within the Utrecht Local Municipality of the Amajuba District Municipality (see Plan 1).

The area falls within the Tugela Primary catchment (WMA 7), and underground mining will span across the V32B and V31D quaternary sub catchments (Plan 3). The receiving water bodies are the Kweekspruit and the Doringspruit. Water drains from this area into the Buffels River, which is a tributary of the Tugela River. Drainage is predominantly in a southerly direction.

1.4 PROPERTY DESCRIPTION

The overall mineral area comprises of 11,169.0386 Ha, of which it is anticipated that approximately 1,100 Ha will be affected by underground mining. Plan 2 indicates the extent of the mining right area in relation to the underground mining and Adit areas.

Table 2 summarises those property applicable to the current and proposed water uses only.

Table 2: Property Details

Farm Name & Portion: Property Owner: Title Deed: Extent (Ha): Comment:

Kweekspruit 22 HT Qophumlando T34345/2003 193.4563 Leased by applicant Portion 3 Property Association

Kweekspruit 22 HT Qophumlando T34345/2003 328.0182 Leased by applicant Portion 8 Property Association

Uitkomst 95 HT Qophumlando T34345/2003 701.968 Leased by applicant Portion 5 Property Association

Klipspruit 178 HT Welgedacht T2215/1990 192 Applicant in process Portion 23 Exploration Co. Ltd of purchasing

Rustverwacht 151 HT Welgedacht T29820/1991 188.5148 Undermining only Portion 16 Exploration Co. Ltd

Rustverwacht 151 HT Brandywine Valley T14876/2008 188.5148 Applicant in process Portion 3 Investments (Pty) of purchasing Ltd

Rustverwacht 151 HT Nicolaas Schoeman T23094/1984 378.1332 Undermining only Portion 4 De Jager

Rustverwacht 151 HT Nicolaas Schoeman T23094/1984 24.8394 Undermining only Portion 15 De Jager

Vaalbank 103 HT Vaalbank Trust T16362/1989 517.5222 Undermining only Portion 1

2 | P a g e

UITKOMST COLLIERY: IWWMP

Farm Name & Portion: Property Owner: Title Deed: Extent (Ha): Comment:

Klipspruit 178 HT Vaalbank Trust T1495/1989 214.1330 Undermining only Portion 16

Klipspruit 178 HT National T7470/2011 526.5687 Undermining only Portion 6 Government of

Klipspruit 178 HT National T8962/2011 128.4798 Undermining only Portion 11 Government of South Africa

Klipspruit 178 HT National T8961/2011 57.6954 Undermining only Portion 13 Government of South Africa

Klipspruit 178 HT National T8961/2011 210.9591 Undermining only Portion 14 Government of South Africa

Klipspruit 178 HT National T8961/2011 625.5397 Undermining only Portion 18 Government of South Africa

1.5 PURPOSE OF THE IWWMP

The purpose of the IWWMP is to provide the Department of Water Affairs and Sanitation (DWS) with the necessary information to amend the integrated water use license for the Uitkomst Colliery, to correctly reflect the current and future water uses on site.

The objectives of the IWWMP are to achieve holistic, resource focused water and waste management on site, as well as to achieve compliance with the NWA. It also expands on a monitoring system which will allow early detection of impacts, as well as proposed actions that should be considered should monitoring activities indicate environmental issues.

As monitoring activities proceed and annual audits are conducted, on-site management and monitoring may change. Changes may also occur through new legislation, new technology or improved monitoring or management practices. This will result in the IWWMP becoming an active document which will be regularly updated through the life of the mine.

In summary the IWWMP is:

 A legal requirement;  Takes into consideration: o Legislative requirements, such as GN704; o Environmental requirements such as the water quality guidelines and resource objectives; o Best practices available at the time for implementation and design of management features and water- and waste-related infrastructure and activities; o Uitkomst Colliery’s environmental policies; and o Closure objectives for the site.

3 | P a g e

UITKOMST COLLIERY: IWWMP

The IWWMP outline has been formatted in line with the Regulations regarding the procedural requirements for Water Use License Application and Appeals, published 24 March 2017.

4 | P a g e

Plan 1: Regional Setting

5 | P a g e

Plan 2: Local Setting

6 | P a g e

Plan 3: Quaternary Catchments

7 | P a g e

UITKOMST COLLIERY: IWWMP

2. CONCEPTUALISATION OF THE ACTIVITY

2.1 DESCRIPTION OF ACTIVITY

The project description given below entails a general description of operations for the full life of mine. Table 3 below summarises the project details. Table 3: Project Summary

Mineral: Coal

Status of Project: Brownfields South Mine: Uitkomst Adit Area – active since 2006 Klipspruit Mine – mined historically by Kangra Coal (Pty) Ltd between 1987 - 1991

Mining Method: Underground bord-and-pillar method accessed via a boxcut adit

Resource Estimate: 26 Million tons

Production Rate: 65,000 tons/month

Plant Design 75,000 tons/month Capacity:

Estimated Life of 18 years Mine:

Depth of Mining: Average depth 135 m Gus coal seam varies from 18 – 355 m

2.2 EXTENT OF ACTIVITY

The overall mineral area comprises of 11,169.0386 Ha, of which it is anticipated that approximately 1,100 Ha will be affected by underground mining. Plan 2 indicates the extent of the mining right area in relation to the underground mining and Adit areas.

Infrastructure and surface disturbance will be limited to the Adit areas, with the exception of a 22kv overhead powerline that will run from the Klipspruit Adit to the Uitkomst Adit.

2.3 KEY ACTIVITY RELATED PROCESSES & PRODUCTS

Coal is mined via underground bord-and-pillar methods. Mined coal is conveyed to surface where it is temporarily stockpiled before being fed to the existing plant for processing. The coal is fed to the primary crusher where it is crushed and then transported via conveyor to the screening section in order to achieve the required product specifications. Oversized material is sent to the secondary crushing section. Correctly sized material is then fed to the beneficiation plant.

The beneficiation plant includes a spiral section (-1.5 mm) and a dense medium cyclone section (+1.5 to -40mm). A product screening section provides the different size gradings for the various markets.

8 | P a g e

UITKOMST COLLIERY: IWWMP

The discard from the plant is trucked to the co-disposal facility, while slurry is pumped to surface ponds on the co-disposal facility. The slurry is reclaimed and sold to interested markets where possible. This co-disposal facility is also referred to as the Mine

Residue Disposal Site (MRDS). The figure below depicts a simplified diagram of the key activity processes (SLR, 2015).

Figure 1: Simplified process diagram (SLR, 2015)

2.4 ACTIVITY LIFE DESCRIPTION

The project can be divided into four phases, namely, the construction phase where applicable to new mining areas/infrastructure, the operational phase, decommissioning phase and post closure phase. The activities associated with these phases are listed below

9 | P a g e

UITKOMST COLLIERY: IWWMP

CONSTRUCTION PHASE (APPLICABLE TO KLIPSPRUIT ONLY)

Establishment of construction contractors lay down area

Removal of herbaceous material with soil stripping & stockpiling

Construction of access road

Erection of water management features: Clean & dirty water berms & trenches

Upgrade & extension of existing Pollution Control Dam (PCD)

Installation & use of conservancy tanks

Construction/installation of support services: offices, change house, lamp room, laundry, workshops, washbays, stores, hard park area, access control, security & weighbridge

Construction/installation of diesel & hydrocarbon storage & handling facilities

Waste generation & storage (domestic & industrial)

Installation of light masts

Preparation and construction of boxcut adit & ventilation

Preparation of stockpile area & installation of conveyor

Erection of in-pit infrastructure (sumps and pumps etc.)

OPERATIONAL PHASE

Operation of water management features

Upgrade & repair of Uitkomst PCD and RWD

Utilisation of roads & conveyor lines

Bord & pillar mining

Dewatering and pumping activities

Stockpiling activities

Coal processing (crushing, screening & beneficiation)

Discard & slurry handling

Expansion of Uitkomst MRDS

Ongoing rehabilitation of the MRDS

Utilisation of support services: offices, change house, lamp room, laundry, workshops, washbays, stores, hard park area, access control, security & weighbridge

Diesel & hydrocarbon storage & handling

Sewage handling

Lighting

Storage & handling of explosives

Waste generation & storage (domestic & industrial)

Trucking/transportation of coal

DECOMMISSIONING PHASE

10 | P a g e

UITKOMST COLLIERY: IWWMP

Dismantling, removal & rehabilitation of unnecessary infrastructure

Underground support & sealing of underground mining areas

Backfilling the boxcut adit

Site clean-up; removal of waste & carbonaceous material

Overall rehabilitation of all disturbed areas (ripping, top soiling & seeding)

Capping, profiling & vegetating the MRDS

Restoration of natural drainage patterns as far as possible

Initiation of aftercare & maintenance program

POST CLOSURE

Managing the site for post mining impacts to prevent further pollution

Application for closure certificate

2.5 ACTIVITY INFRASTRUCTURE DESCRIPTION

Uitkomst Colliery can essentially be divided into two sections, namely:

 South Mine; and  Klipspruit Mine The section below details the infrastructure associated with each of these areas.

2.5.1 South Mine

Operations commenced at the South Mine in 2006, the underground workings are accessed via a boxcut-adit (known as the Uitkomst Adit or Adit 1) cut into the hill slope in a north westerly direction. The adit was constructed into the mountain to allow for access to the Gus coal seam. Topsoil has been removed and stockpiled to the north east of the boxcut. The hards and softs from the boxcut were utilised to construct a platform on the low wall side (south east side) of the boxcut to accommodate the coal processing and load out activities.

The Adit and associated infrastructure area comprises approximately 37 Ha, and includes the following infrastructure (seeFigure 2):

 Box cut and adit;  Soils and spoils stockpiles;  Crushing and Screening plant;  Beneficiation plant;  Product and RoM stockpiles;  MRDS/Co-Disposal Dump;  Settling dams;  RWD;  PCD;  Security, access control and weighbridge;  Offices, workshops and contractors laydown area;  Change houses, lamp room, laundry and ablution facilities;

11 | P a g e

UITKOMST COLLIERY: IWWMP

 Scrap yard and waste storage area; and  Fuel and oil storage area. No additional infrastructure is envisaged for this area. It is however expected that the MRDS will need to be extended in future to cater for the additional life of mine (LoM).

The water management facilities, including the pollution control dam (PCD) and Return Water Dam (RWD) were recently accessed by a registered engineer. The findings of the assessment indicate that the design capacity of the designs are sufficient however, these are heavily silted and need to be cleared out and reinstated to the original capacities (Davel, 2017).

12 | P a g e

UITKOMST COLLIERY: IWWMP

Figure 2: Current infrastructure at South Mine: Adit 1 (aerial photograph supplied by ESS Survey, April 2017)

13 | P a g e

UITKOMST COLLIERY: IWWMP

2.5.2 Klipspruit Mine

The Klipspruit Mine was historically mined, but no infrastructure other than the remnants of an old Pollution Control Dam (PCD) and an Eskom sub-station remain on site.

It is anticipated that the Klipspruit reserves will be accessed via two adits, Adit 2 and Adit 3. See Plan 2 for the position of these in relation to the mining right and underground areas. The position of Adit 3 has been approximated and will be finalised in future on completion of the necessary feasibility studies; as such the mining and operations of Klipspruit Mine will be approached in two phases.

Phase I: Adit 2

It is anticipated that the coal from Adit 2 will be trucked to the South Mine (Uitkomst Adit 1) for processing, using the existing road system. Thus, it is expected that the infrastructure at Adit 2 will be limited to that associated with underground mining only (i.e. no processing) and comprising a total of 21Ha. The following infrastructure is currently envisaged:

 Access road;  Mini substation and overhead lines, including a line running from Adit 2 to Adit1 (see Plan 2);  Box cut and adit;  Soils and spoils stockpiles;  Run of mine stockpiles;  Clean and dirty water management facilities;  Security, access control and weighbridge;  Offices, workshops and contractors laydown area;  Change houses, lamp room, laundry and ablution facilities;  Scrap yard and waste storage area; and  Fuel and oil storage area. Adit 2 and the associated infrastructure will be located within the area previously disturbed and rehabilitated by Kangra Coal (Pty) Ltd, as such it is envisaged that the existing, old PCD can be refurbished for utilisation (see Figure 3).

Phase II: Adit 3

Once the position of Adit 3 is finalised, it is likely that a full scale wash plant and associated infrastructure (MRDS) will be required at the Klipspruit Mine.

Note: Phase II has been excluded from the scope of this IWUL Amendment. A separate water use license will need to be applied for once the position of Adit 3 and associated infrastructure is finalised.

14 | P a g e

Figure 3: Proposed layout of Klipspruit Adit 2 (ESS, April 2017)

15 | P a g e

UITKOMST COLLIERY: IWWMP

Figure 4: Proposed of Klipspruit Adit 2 in relation to the existing old, PCD (Google Earth, 2016)

2.6 KEY WATER USES & WASTE STREAMS

The key water uses are:

 21(a): Taking water from a water resource;  21(b): Storage of water;  21(c): Impeding or diverting the flow of a watercourse;  21(i): Altering the bed, banks, course or characteristics of a watercourse;  21(g): Disposing of a waste in a manner which may detrimentally impact on a water resource; and  21(j): Removing, discharging or disposing of water found underground if it is necessary for the efficient continuation of an activity or for the safety of people. The waste streams generated are:

 General Waste: o Domestic/office waste (incl. paper, plastic, glass); o Uncontaminated PPE; o Food waste; o Uncontaminated building rubble; o Wood; o Scrap metal; and o Old tyres and conveyor belts.  Hazardous waste: o Hydrocarbon waste; o Mine residue;

16 | P a g e

UITKOMST COLLIERY: IWWMP

o Batteries; o Organic compounds and solvents (reagents, chemicals etc.) o WEEE waste (electrical and electronic equipment, cartridges etc.) o Contaminated soils, metals, plastic, rubber and wood; and o Explosives waste.  Sewage.

2.7 ORGANISATIONAL STRUCTURE

Uitkomst Colliery (Pty) Ltd is a subsidiary of Pan African Resources PLC. Uitkomst Colliery is currently in the process of verifying its BEE status; please refer to APPENDIX 2for a letter to this effect. An organogram depicting the organisational and BEE ownership is depicted below in Figure 5.

ORGANOGRAM OF BEE SHAREHOLDING

22,5% PAR Gold Pan African Resources PLC (Pty) Ltd

100%

Pan African Resources Coal Holdings (Pty) Ltd

91%

Mcijo Trust Uitkomst Colliery (Pty) Ltd 5%

2% Uitkomst Colliery Employee Trust BEE effective interest of 29,5% in the 2% Uitkomst Colliery Community Trust Uitkomst Mine

Uitkomst Colliery

4

Figure 5: Uitkomst Colliery BEE Organogram (Source: Pan African Resources PLC)

2.8 BUSINESS & CORPORATE POLICIES

The business and corporate policies have been developed around the internal Safety, Health and Environmental Policy which elaborates on commitments of the company to employees, the environment and resources, and includes constitutional matters such as the right to an environment that is not harmful to an individual and sustainability of environmental resources

17 | P a g e

UITKOMST COLLIERY: IWWMP

for future generations. Generally the policy has been compiled to ensure that Uitkomst Colliery:

 Complies with all relevant laws, regulations, and standards regarding safety, health and the environment.  Constantly monitors and manages the effects of mining in order to prevent pollution, environmental degradation, ill health and damage to property.  Maintains open communication between all employees and affected parties regarding all aspects of the operation.  Employs staff competent in their areas of responsibility regarding safety, health and the environment on all the properties.  Provides staff with the relevant training required to complete their tasks in an environmentally responsible manner through environmental awareness training.  Ensures proper organisational structure, communication procedures and resources are available to staff to allow them to undertake their tasks in an environmentally responsible manner.  Compiles environmental emergency procedures and ensures staff is adequately trained in these procedures to ensure a high level of emergency preparedness for potential on-site emergencies.

3. REGULATORY WATER & WASTE MANAGEMENT FRAMEWORK

3.1 SUMMARY OF ALL WATER USES

The NWA regulates water use within South Africa. In terms of Chapter 4 and Section 22 of the NWA a person may only use water –

 Without a license if that water use is permissible in under Schedule 1; is a continuation of an existing lawful use; or if it falls under the ambit of a General Authorisation.  If the water use is licensed under the NWA.  If the responsible authority has dispensed with a license requirement under subsection (3) of the NWA. Uitkomst Colliery has an approved water use license for certain existing uses on site. See attached, APPENDIX 3 for a copy of the approved license. Changes to the current and future water uses have however since been identified for the operation and as such this IWUL Amendment and IWWMP has been compiled.

The table below summarises all the current and proposed water uses for the operations, and highlights those which require amendments and/or licensing where relevant.

18 | P a g e

Table 4 Summary of all water uses

Ref. Description: S.21 Water Property: Co-ordinates: Maximum Volumes: Use:

1. Abstraction from a borehole for 21(a) Ptn 5 of Uitkomst 95 HT 27˚37’15.81”S 5,000m3/annum domestic & potable use at Uitkomst 30˚07’21.23”E Adit/Adit 1

2. Abstraction of water from Farm Dam 21(a) Ptn 5 of Uitkomst 95 HT 27°36'47.05"S 5,000m3/annum 1 for domestic and mine process use 30°06'59.83"E at Uitkomst Adit/Adit 1

3. Abstraction from a borehole for 21(a) Ptn 23 of Klipspruit 178 27°34'16.76"S 5,000m3/annum domestic & potable use at Klipspruit HT 30°05'16.03"E Adit 2

4. Associated with 21(j) – reuse of 21(a) Ptn 8 of Kweekspruit 22 27°36'04.05"S underground mine water HT 30°08'05.92"E Uitkomst/Adit 1)

989,735 m3/annum 5. Associated with 21(j) – reuse of 21(a) Ptn 23 of Klipspruit 178 27°34'39.43"S underground mine water (Klipspruit HT 30°05'22.73"E Adit 2)

6. Abstraction from a borehole drilled 21(a) Ptn 14 of Klipspruit 178 27°34'5.53"S 180,000 m3/annum into the old Klipspruit workings for use HT 30°05'24.73"E as process water

7. Reservoir 1: Storage of water for 21(b) Ptn 8 of Kweekspruit 22 27°36'09.83"S 5,000m3/annum domestic & potable use Uitkomst HT 30°08'00.35"E Adit/Adit 1 (receives water from

borehole & Farm Dam 1)

8. Reservoir 2: Storage of water for use 21(b) Ptn 8 of Kweekspruit 22 27°36'09.33"S 5,000m3/annum as process water underground HT 30°08'00.64"E (receives water from Farm Dam 1)

19 | P a g e

Ref. Description: S.21 Water Property: Co-ordinates: Maximum Volumes: Use:

9. Uitkomst Adit/Adit 1 & associated 21(c) & (i) Ptn 3 & 8 of Kweekspruit 27°36'04.05"S - infrastructure within a non-perennial 22 HT 30°08'05.92"E and disturbed valley bottom

27°36'13.40"S 30°08'16.99"E

27°36'17.34"S 30°08'22.51"E

10. Klipspruit Adit & associated 21(c) & (i) Ptn 23 of Klipspruit 178 27°34'32.49"S - infrastructure <100m of valley bottom HT 30°05'13.27"E wetland and non-perennial

11. Proposed overhead line <500m of a 21(c) & (i) Ptn 8 of Kweekspruit 22 27°34'11.24"S - wetland HT 30°05'14.62"E Ptn 5 of Uitkomst 95 HT Ptn 3 & 16 Rustverwacht 27°34'12.95"S 151 HT 30°05'21.45"E Ptn 14, 16, & 23 of

Klipspruit 178 HT 27°34'10.38"S

30°05'22.47"E

27°34'12.86"S 30°05'42.40"E

27°34'16.78"S 30°05'45.28"E

20 | P a g e

Ref. Description: S.21 Water Property: Co-ordinates: Maximum Volumes: Use: 27°34'18.56"S 30°05'50.39"E

27°35'28.76"S 30°06'56.47"E

27°35'54.52"S 30°07'56.82"E

27°36'03.79"S 30°08'02.83"E

27°36'04.75"S 30°08'04.96"E

12. Undermining a water resource 21(c) & (i) Ptn 5 of Uitkomst 95 HT - Ptn 6, 11, 13, 14, 16, 18 & 23 of Klipspruit 178 HT Ptn 3,4, 6 &15 Rustverwacht 151 HT Ptn 1 Vaalbank 103 HT

13. RoM Coal stockpile at Uitkomst / Adit 21(g) Ptn 3 of Kweekspruit 22 27°36'03.25"S 1 HT 30°08'08.20"E

14. Coal stockpile area at Uitkomst / Adit 21(g) Ptn 3 of Kweekspruit 22 27°36'03.47"S Combined: 780,000 tons/annum 1 HT 30°08'13.23"E

15. Coal stockpile area at Uitkomst / Adit 21(g) Ptn 3 & 8 of Kweekspruit 27°36'05.41"S 1 22 HT 30°08'10.31"E

21 | P a g e

Ref. Description: S.21 Water Property: Co-ordinates: Maximum Volumes: Use:

16. Coal stockpile area at Uitkomst / Adit 21(g) Ptn 8 of Kweekspruit 22 27°36'08.44"S 1 HT 30°08'07.49"E

17. Coal stockpile area at Uitkomst / Adit 21(g) Ptn 8 of Kweekspruit 22 27°36'14.10"S 1 HT 30°08'04.49"E

18. RoM Coal stockpile area at Klipspruit 21(g) Ptn 23 of Klipspruit 178 27°34'31.19"S Capacity 7,500 m3 Adit 2 HT 30°05'21.16"E

19. Dust suppression at Uitkomst Adit/Adit 21(g) Ptn 3 & 8 of Kweekspruit 27°36'04.52"S 32,400m3/annum 1 22 HT 30°08'08.68"E Ptn 5 of Uitkomst 95 HT 27°36'34.88"S 30°07'57.17"E

27°37'06.93"S 30°06'41.93"E

20 Dust suppression at Klipspruit Adit 2 21(g) Ptn 23 of Klipspruit 178 27°34'31.46"S 32,400m3/annum HT 30°05'07.66"E

27°34'22.28"S 30°05'11.45"E

27°34'23.70"S 30°05'19.91"E

22 | P a g e

Ref. Description: S.21 Water Property: Co-ordinates: Maximum Volumes: Use:

27°34'32.75"S 30°05'22.02"E

21 Pollution Control Dam at Uitkomst 21(g) Ptn 3 & 8 of Kweekspruit 27°36'13.40"S 50,238m3/annum Adit/Adit 1 (currently licensed as RWD 22 HT 30°08'16.99"E A)

22. Return Water Dam at Uitkomst 21(g) Ptn 3 of Kweekspruit 22 27°36'17.34"S 58,808m3/annum Adit/Adit 1 (currently licensed as RWD HT 30°08'22.51"E B)

23. Mine Residue Disposal Site at Uitkomst 21(g) Ptn 8 of Kweekspruit 22 27°36'19.55"S 330,000tons/annum Adit/Adit 1 (currently licensed as HT 30°08'09.10"E Discard Dump)

24. Plant Dam A at Uitkomst Adit/Adit 1 - 21(g) Ptn 3 of Kweekspruit 22 27°36'06.28"S 52,647m3/annum consisting of two compartments HT 30°08'13.43"E (currently licensed as settling pond)

25. Plant Dam B at Uitkomst Adit/Adit 1 21(g) Ptn 3 & 8 of Kweekspruit 27°36'08.39"S 51,4243/annum (currently licensed as pollution control 22 HT 30°08'13.58"E dam)

26. Pollution Control Dam at Klipspruit 21(g) Ptn 23 of Klipspruit 178 27°34'32.49"S 43,854m3/annum Adit 1 HT 30°0513.27"E

27. Dewatering of the underground 21(j) Ptn 8 of Kweekspruit 22 27°36'04.05"S workings at the Uitkomst Adit/Adit 1 HT 30°08'05.92"E 989,735 m3/annum 28. Dewatering of the underground 21(j) Ptn 23 of Klipspruit 178 27°34'39.43"S workings at Klipspruit Adit 2 HT 30°05'22.73"E

23 | P a g e

UITKOMST COLLIERY: IWWMP

3.2 EXISTING LAWFUL WATER USES

According to the NWA, an existing lawful water use is defined as follows:

“32.(1) An existing lawful water use means a water use – (a) Which has taken place at any time during a period of two years immediately before the date of commencement of this Act; or (b) Which has been declared an existing lawful water use under section 33, and which – (i) Was authorised by or under any law which was in force immediately before the date of commencement of this Act; (ii) Is identified as a stream flow reduction activity in section 36(1); or (iii) Is identified as a controlled activity in section 37(1). (2) In the case of – (a) A stream flow reduction activity declared under section 36(1); or (b) A controlled activity declared under section 38, existing lawful water use means a water use which has taken place at any time during a period of two years immediately before the date of the declaration”. The old PCD located at the Klipspruit Adit 2 area is an existing dam, constructed within a non-perennial water course. As this water use(s) was in existence prior to 1998, it must be considered as an existing lawful water use.

3.3 RELEVANT EXEMPTIONS

No exemptions have been granted for the operations to date.

The following exemptions are however being sought from GN704.

Table 5: Application for GN704 Exemption

GN 704 Restrictions: Applicability:

4(a) No person in control of a mine may locate Several wetlands, boreholes and water or place any residue deposit, dam, reservoir, courses occur within and around the mining together with an associated structure or any right area. Where activities have other facility within the 1:100 year floodline or transgressed these, exemption will be within a horizontal distance of 100m from any required. watercourse or estuary, borehole or well, Areas which require exemption include: excluding boreholes or wells drilled specifically  Existing Uitkomst Adit, PCD and RWD are to monitor the pollution of groundwater, or on located within a disturbed valley water-logged ground, or on ground likely to bottom. become water logged, undermined, unstable,  The existing Klipspruit PCD is located or cracked. within a drainage course.  The proposed Klipspruit Adit & associated infrastructure <100m of valley bottom wetland and stream.

24 | P a g e

UITKOMST COLLIERY: IWWMP

GN 704 Restrictions: Applicability:

4(b) No person in control of a mine may except Several wetlands, boreholes and water in relation to a matter contemplated in courses occur within and around the mining Regulation 10, carry on any underground or right area. opencast mining, prospecting or any other Exemption is required for the proposed operation or activity under or within 1:50 year undermining of several wetlands. floodline or within a horizontal distance of 100m Future opencast activities will remain outside from any watercourse or estuary, whichever is the 100m buffer of all wetland areas the greatest. however, where current / past activities have transgressed wetlands exemption will be required. These include:  The existing Uitkomst Adit and infrastructure area is located within disturbed valley bottom.  The proposed Klipspruit Adit & associated infrastructure <100m of valley bottom wetland and stream.

3.4 GENERAL AUTHORISATIONS

Uitkomst Colliery does not currently hold any registered general authorisations.

3.5 AMENDMENTS TO EXISTING USES

Table 6 below summarises the existing, licensed water uses and outlines the amendment required thereto. Please refer to Table 4 for details on the location and capacities.

Table 6: Summary of existing licensed uses and applicable amendment

Ref. S.21 Water Description: Action Currently Requested Use: Required: Authorised: Amendment:

1. 21(a): Taking Abstraction Amend 2,920m3/annum 5,000m3/annum water from a from a borehole volumes & water for domestic & co- 27˚36’13.5”S 27˚37’15.81”S resource potable use at ordinates Uitkomst 30˚07’42.8”E 30˚07’21.23”E Adit/Adit 1

4. 21(a): Taking Associated with Amend 36,000m3/annum 494,867m3/annum water from a 21(j) – reuse of volumes water underground 27˚36’04.05”S resource mine water Uitkomst/ Adit 1 30˚08’05.92”E

13. 21(g): RoM coal Combined Total: Amend Combined Total: Disposal of stockpiles at 360,000

25 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Description: Action Currently Requested Use: Required: Authorised: Amendment: waste in a Uitkomst Volumes tons/annum 780,000 tons/annum manner that Adit/Adit 1 could detrimentally impact on a water course

14. 21(g): Coal stockpile Disposal of at Uitkomst waste in a Adit/Adit 1 manner that could detrimentally impact on a water course

15. 21(g): Coal stockpile Disposal of at Uitkomst waste in a Adit/Adit 1 manner that could detrimentally impact on a water course

16. 21(g): Coal stockpile Disposal of at Uitkomst waste in a Adit/Adit 1 manner that could detrimentally impact on a water course

17. 21(g): Coal stockpile Disposal of at Uitkomst waste in a Adit/Adit 1 manner that could detrimentally impact on a water course

19. 21(g): Dust Amend 24, 090m3/annum 32,400m3/annum Disposal of suppression at volumes waste in a Uitkomst manner that Adit/Adit 1 could detrimentally impact on a

26 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Description: Action Currently Requested Use: Required: Authorised: Amendment: water course

23. 21(g): Mine Residue Amend 83,951m3/annum 330,000tons/annum Disposal of Disposal Site at volumes waste in a Uitkomst manner that Adit/Adit 1 could (currently detrimentally licensed as impact on a Discard Dump) water course

24. 21(g): Plant Dam A at Amend 13,337m3/annum 52,647m3/annum Disposal of Uitkomst throughput waste in a Adit/Adit 1 - volumes manner that consisting of could two detrimentally compartments impact on a (currently water course licensed as settling pond)

25. 21(g): Plant Dam B at Amend 4,149m3/annum 51,4253m3/annum Disposal of Uitkomst throughput waste in a Adit/Adit 1 volumes manner that (currently could licensed as detrimentally pollution control impact on a dam) water course

26. 21(g): Pollution License n/a 43,854m3/annum Disposal of Control Dam at Extension waste in a Klipspruit Adit 1 manner that could detrimentally impact on a water course

27. 21(j): Dewatering of Amend 36,000m3/annum 494,867m3/annum Removing the volumes water from underground Underground workings at the to Continue Uitkomst with Safe Adit/Adit 1 Mining

24. 21(g): Slurry dam Remove n/a n/a Disposal of within boxcut at from water waste in a Uitkomst Adit 1 license manner that

27 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Description: Action Currently Requested Use: Required: Authorised: Amendment: could detrimentally impact on a water course

3.6 NEW WATER USES TO BE LICENSED

Table 7 below summarises the new water uses identified for the operations. Please refer to Table 4 for details on the location and capacities.

Table 7: Summary of new water uses to be licensed

Ref. S.21 Water Use: Description: Status: Maximum Volume:

2. 21(a): Taking water from Abstraction of water from In use 5,000m3/annum a water resource Farm Dam 1 for domestic and mine process use at Uitkomst Adit/Adit 1

3. 21(a): Taking water from Abstraction from a Proposed 5,000m3/annum a water resource borehole for domestic & potable use at Klipspruit Adit 2

5. 21(a): Taking water from Associated with 21(j) – Proposed 494,867m3/annum a water resource reuse of underground mine water Klipspruit Adit 2

6. 21(a): Taking water from Abstraction from a Proposed 180,000m3/annum a water resource borehole drilled into the old Klipspruit workings for use at process water

7. 21(b): Storage of water Reservoir 1: Storage of In use 5,000m3/annum water for domestic & potable use Uitkomst Adit/Adit 1 (receives water from borehole & Farm Dam 1)

8. 21(b): Storage of water Reservoir 2: Storage of In use 5,000m3/annum water for use as process water underground (receives water from Farm Dam 1)

9. 21(c) & (i): Altering beds Uitkomst Adit/Adit 1 & In use - and Banks or Diverting or associated infrastructure Altering Flow in a within a disturbed valley Watercourse bottom

28 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Use: Description: Status: Maximum Volume:

11. 21(c) & (i): Altering beds Proposed overhead line Proposed - and Banks or Diverting or <500m of a wetland Altering Flow in a Watercourse

12. 21(c) & (i): Altering beds Undermining a water In use - and Banks or Diverting or resource Altering Flow in a Watercourse

18. 21(g): Disposal of waste in RoM and Product coal Proposed Capacity 7,500m3 a stockpiles at Klipspruit Adit manner that could 2 detrimentally impact on a water course

20. 21(g): Disposal of waste in Dust suppression at Proposed 32,400m3/annum a Klipspruit Adit 2 manner that could detrimentally impact on a water course

28. 21(j): Removing water Dewatering of the Proposed 494,867m3/annum from Underground to underground workings at Continue with Safe Klipspruit Adit 2 Mining

3.7 WASTE MANAGEMENT ACTIVITIES (NEM:WA) & AUTHORISATIONS

The National Environmental Management: Waste Act (No. 59 of 2008) (NEM:WA) came into operation on the 1 July 2009. It addresses waste generation, classification and management issues, including recycling of waste.

No waste management licenses in terms of NEM:WA have been applied for or granted to date.

 General, industrial and hazardous waste is and will be disposed of at licensed facility and no landfill facilities have or will be constructed on site. The storage of waste must comply with the relevant requirements or standards determined by the Norms and Standards for the Storage of Waste (Government Gazette 37088, 2013).  The construction of the MRDS was prior to the amendment of the NEM:WA for the inclusion of mine residue, and as such is deemed to be authorized in terms of NEM:WA (refer to the transitional arrangements under the EIA Regulations GN. 982 of 4 December 2014).

29 | P a g e

UITKOMST COLLIERY: IWWMP

3.8 OTHER AUTHORISATIONS & REGULATIONS

The original Environmental Management Programme (EMP) report for Uitkomst Colliery was compiled by Clean Stream in 2004. The EMPr covered the underground bord and pillar mining of Portion 5 of Uitkomst 95 HT; and Portions 3 and 8 of Kweekspruit 22 HT.

1st Amendment: The EMP was amended in 2006 by Digby Wells & Associates for the inclusion of additional surface infrastructure associated with the installation of a beneficiation plant and MRDS.

2nd Amendment: For the inclusion of additional properties (Portion 1 of Uitkomst 95 HT and Portion 3 (of 1) of Rustverwacht 151 HT) compiled by Geoff Silk Civil & Mining Consultants , 2008.

The original EMP for Klipspruit was compiled by GCS (2006) for Kangra Coal. The EMP covered the underground bord and pillar mining of coal on a number of properties to be accessed via three adits, as well as the crushing, screening and washing of coal at a centrally located plant.

The above EMP reports were all submitted and approved by the Department of Mineral Resources (DMR) in terms of the MPRDA. In terms of the transitional arrangements stipulated in NEMAA all EMPs approved in terms of the MPRDA immediately prior to the 8th December 2014 constitute environmental authorization in terms of NEMA. Thus, the original approved EMPs are considered to be environmental authorisation.

In terms of Section 29 of the NEMA EIA Regulations, a Part 1 Amendment was submitted by SLR in April 2015. This Amendment referred to the transfer and consolidation of rights associated with the Section 102 application made in terms of the MPRDA.

The EMP Amendment consolidates and replaces the previous submissions made by Brandywine Valley Investments (Pty) Ltd and Kangra Coal (Pty) Ltd, please refer to APPENDIX 4 for a copy of the approval (environmental authorisation).

30 | P a g e

UITKOMST COLLIERY: IWWMP

4. PRESENT ENVIRONMENTAL SITUATION

4.1 CLIMATE

4.1.1 Regional Climate

The site falls within the Central KwaZulu Natal climate region and receives predominantly summer rainfall. Most rains fall between October and March. Temperatures are mostly moderate in summer, but can reach up to 34°C. Winter is typically dry. Frosts in winter are common, with minimum temperatures from May to August around 0°C or below. Table 6 summarises the climatic data for the area.

Table 8: Mean monthly temperature, rainfall and precipitation (Station: Utrecht - V3E004)

Month Mean Max Temp Mean Min Temp Mean Rainfall Mean Evaporation (ºC) (ºC) (mm) (mm)

January 29.1 16.3 133.1 107.7

February 27.9 15.5 102.7 88.1

March 27.4 14 76.8 108.6

April 24.8 10.3 28.5 97.9

May 22.6 6.2 12.7 82.6

June 20 2.2 14.6 66.0

July 20.7 2.8 5.7 75.0

August 23 5.8 16.4 76.1

September 25.3 9.8 20.3 57.9

October 26.2 12 87.1 106.1

November 27.4 13.8 88.0 79.6

December 29 15.4 104.2 95.7

Annual Value 25.3 10.3 700.1 1041.3

4.1.2 Rainfall

The site has an average annual rainfall of 700.1 mm (Letsolo, 2016). Most rainfall occurs during mid-summer, primarily as thunderstorms.

4.1.3 Evaporation

The site has a mean annual evaporation of approximately 1041.3 mm (Letsolo, 2016).

31 | P a g e

UITKOMST COLLIERY: IWWMP

4.2 SURFACE WATER (Letsolo, 2016)

4.2.1 Water Management Area (WMA 7)

The study area falls within WMA 7 – Thukela. The Thukela WMA lies predominantly in the KwaZulu-Natal province. It is a funnel-shaped catchment, with several tributaries draining from the Drakensberg escarpment towards the Indian Ocean. It is characterised by mountain streams in the upper reaches, where several parks and conservation areas are located, as well as a number of important wetlands and vleis. Rainfall is highest near the mountains and along the coast, and the mean annual precipitation is in the range from 600 mm to 1 500 mm.

Because of the high mean annual runoff and favourable topography, the Thukela basin offers some of the best opportunities for water resources development in South Africa.

4.2.2 Mean Annual Runoff (MAR)

Five (5) site specific catchments were delineated in order to provide site specific storm water management measures (see Plan 4). The delineated catchment areas are summarised as follows:

Table 9: Delineated Catchments

Description Surface Area Hydraulic Change in Significant Water Resource (km2) Length (m) height (m)

Catchment 1 23.64 8864 640 Doringspruit

Catchment 2 7.55 5255 200 Unnamed tributary of the Doringspruit

Catchment 3 34.93 10146 680 Kweekspruit

Catchment 4 23.37 9133 200 Sandspruit

Catchment 5 5.30 1885 80 Unnamed tributary of the Kweekspruit

The MAR for the study area was sourced from the Water Research Commission database (WR2005). Table 10 provides activity based MAR for the 5 catchments in the study area.

32 | P a g e

UITKOMST COLLIERY: IWWMP

Table 10: Mean Annual Runoff (MAR)

Catchment MAR Calculated MAR Description Surface Area (km2) (mm/annum) (m3/annum)

Catchment 1 23.64 44.84 1060018

Catchment 2 7.55 44.84 338542

Catchment 3 34.93 50.58 1766759

Catchment 4 23.37 50.58 1182055

Catchment 5 5.3 50.58 268074

4.2.3 Flood peaks & volumes

Flow through the rivers will be largely dependent on rainfall and therefore occur through summer months. Groundwater reserves from the mountainous areas and escarpment will feed hillslope seeps and may contribute to flow in the perennial streams into the dry winter months. During droughts the systems will remain dry.

The flood calculation outputs are summarized in Table 11 for each of the catchments relevant to the study area.

Table 11: Summary of calculations

1:50 year peak flow 1:100 year peak Description Surface Area (km2) (m3/s) flow (m3/s)

Catchment 1 23.64 245.36 308.68

Catchment 2 7.55 91.90 115.62

Catchment 3 34.93 323.77 407.33

Catchment 4 23.37 173.73 218.57

Catchment 5 5.3 3.46 4.35

33 | P a g e

Plan 4: Effective Catchments

34 | P a g e

UITKOMST COLLIERY: IWWMP

4.2.4 Surface Water Quality

The water quality has been discussed in terms of the baseline data for Klipspruit Mine obtained during the recent assessment conducted by Letsolo and the existing water quality monitoring programme at South Mine (Uitkomst Adit).

Klipspruit Mine:

The Doringspruit is the most significant receiving water body for Klipspruit Mine. The stream was dry during the survey conducted by Letsolo in November 2015, largely due to the drought experienced in South Africa. Therefore no samples could be taken along the stream at points MP A to MP C. A sample was obtained downstream at point MP F, although flow was very low (see Plan 5: Baseline Monitoring Points: Klipspruit Mine).

Samples were also taken at upstream and downstream dams along the Doringspruit, including Dam A, Dam B and Old Mine Catchment Dam. The water quality data obtained for the November 2015 sampling is presented in Table 12.

Dam A, upstream of the proposed site, showed good quality water for parameters tested and no values exceeded DWS or SANS drinking water quality standards.

Dam B, immediately downstream of the proposed Klipspruit Mine, the Old Mine Catchment Dam, which is downstream of Dam B and MP F which is the southernmost sampling point in the Doringspruit all indicated generally good quality water, however Iron exceed DWS drinking water quality standards; however the Iron levels at all three sites were still within SANS drinking water quality standards. The small variation in Iron concentration between Dam A (0.072mg/l), Dam B (0.116mg/l), the Old Mine Catchment Dam (1.14mg/l) and MP F (0.242mg/l) and the stability of Sulphate concentrations and pH between the upstream and downstream sites suggests that the elevated Iron levels are due to the geological nature of the area rather than an anthropogenic impact.

The recorded Iron levels are not expected to cause any health effects and the Doringspruit water quality can be said to be good based on findings from the first sampling.

35 | P a g e

UITKOMST COLLIERY: IWWMP

Plan 5: Baseline Monitoring Points: Klipspruit Mine

36 | P a g e

Table 12: Baseline Water Quality Results, November 2015

Drinking/Domestic Use Irrigation Old Detection Analyses Unit SANS 241-1 DWA Dam A Dam B Mine MP F Limit DWA SAWQTV (2015) SAWQTV Dam pH pH unit n/a 5 - 9.5 6 – 9 6.5 - 8.4 8.2 8.2 8.0 7.7

Electric. Conductivity mS/m 0.1 <150 <70 <40 14.1 13.0 13.7 21.0

Total Dis. Solids mg/L 10 <1000 <450 NS 108 104 116 154

Total Alkalinity mg CaCO3/L 2.477 250 NS NS 56 52 44 88

Calcium mg/L 0.0259 <150 <32 NS 12 10 10 17

Magnesium mg/L 0.009 <70 <30 NS 7 6 7 9

Potassium mg/L 0.018 <50 <50 NS 1.1 1.1 10 17

Sodium mg/L 0.013 <200 <100 <70 8 8 0.1 0.2

Sulphate mg/L 0.04 <500 <200 NS 7 7 4 12

Chloride mg/L 0.423 <300 <100 <100 4 4 6 7

Aluminium mg/L 0.003 <0.3 <0.15 <5 0.100 0.117 0.140 0.410

Copper mg/L 0.001 2 <1 <0.2 <0.010 <0.010 <0.010 <0.010

Iron mg/L 0.003 2 <0.1 <5 0.072 0.116 1.14 0.242

Lead mg/L 0.004 0.01 <0.01 <0.2 <0.010 <0.10 <0.010 <0.010

Manganese mg/L 0.001 0.5 <0.05 <0.02 <0.025 <0.025 <0.025 <0.025

Zinc mg/L 0.002 <5 <3 <1 <0.025 <0.025 <0.025 <0.025

Nitrate (N) mg/L 0.017 <11 <6 NS 0.1 0.1 0.1 0.2

Fluoride mg/L 0.055 <1.5 <1 <2 <0.2 <0.2 <0.2 0.3

37 | P a g e

UITKOMST COLLIERY: IWWMP

South Mine: Uitkomst Adit

Surface water monitoring is currently being undertaken as per the requirements of the approved water use license on a monthly basis. Plan 6 indicates the position of the monitoring points whilst the section below summarises the results for the period September 2016 – March 2017. Please refer to APPENDIX 5 for a copy of the latest water monitoring report for the full results.

All the surface water samples, besides the two Farm Dams and the two river samples (Upstream and Downstream), fall within the dirty water footprint of the Uitkomst Adit and infrastructure area. These dirty water dams are exposed to water that has come into contact with coal and carbonaceous shales and are expected to be polluted. These dirty water management facilities have Conductivity levels, Sodium, Sulphate, Magnesium and Calcium concentrations that exceed the SANS 241 Drinking Water Standards.

The approved water use license for the Colliery imparts water quality limits for the PCD. These limits are so stringent that the up gradient unpolluted water samples do not comply. It must be stressed that the chemical results obtained are as expected for polluted coal water contained in a PCD. It is therefore unrealistic to place water quality limits on a PCD with the purpose of storing dirty water (as required by GN704).

Farm Dam 1 is an up gradient water sample and is not being impacted on by the coal mining activities at the adjacent Uitkomst Colliery. The Sodium and Sulphate concentrations for the month of February were 6.67 and 13.5mg/l, both an improvement when compared to the November sample results. The water, however, not being impacted on by the mining operations contains elevated heavy metals such as Aluminium and Iron. This results in the water being unsuitable for human consumption.

Upstream sampling point is located along the Kweekspruit, up gradient of the plant area. Only the Sulphate concentration exceeded the stringent RQO limit of 7.24mg/l with a concentration of 13.3mg/l in February. This sampling point is not being impacted on by the mining activities.

Downstream sampling point is located along the Kweekspruit, down gradient of the plant area. Water quality, similarly to Upstream does not comply with the RQO limits. Whilst the water is considered of good quality, the water quality in Downstream has marginally deteriorated when compared to Upstream. The February Conductivity level, for example, for the Upstream was 16.6mS/m compared to 24.2 mS/m at Downstream.

Of concern, however, is water sample Farm Dam 2. This is a clean water dam, situated down gradient of the RWDs and MRDS. During the month of September the Sulphate and Sodium concentrations were1067 and 290mg/l. During November these two parameters decreased to 360mg/l and 97.2mg/l. During the second quarter sampling event (January and February), the Sulphate and Sodium concentrations again increased to 851 and 184 mg/l. These results indicated that the down gradient water system is being impacted on by the Colliery’s activities possibly through seepage or poor surface water management. During the month of February the Colliery received over 108mm of rain in short succession. This resulted in the RWD overflowing into Farm Dam 2, hence the elevated concentrations of parameters seen in February. This spill was reported to DWS on the 23rd of February 2017.

38 | P a g e

UITKOMST COLLIERY: IWWMP

Plan 6: Current Surface Water Monitoring Points at South Mine: Uitkomst Adit

4.2.5 Resource Class & River Health

The site is discussed in terms of aquatic sensitivity based on national programmes such as FEPA rivers and wetlands, as well as provincial programmes such aquatic biodiversity and land use decision support (LUDS) plans. This information was obtained from SANBI which has been appointed to manage South Africa’s biodiversity in terms of the National Environmental Management: Biodiversity Act. Furthermore, the biomonitoring results for 2016 (Iggdrasil, 2016) have been included and summarised below.

FEPA wetlands (Figure 6) are scattered throughout the project area. These have been assessed as part of the wetland assessment which is detailed later in the IWWMP. In general, the proposed infrastructure associated with Klipspruit Adit 2 has been planned so as to avoid wetlands and their 100m buffer zones as far as possible. According to NFEPA data, the Doringspruit is classified as a D, the Kweekspruit is classified as a C, the Wasbankspruit is classified as a C and the Slang River situated to the north of the study area is classified as a B (Iggdrasil, 2016). The Slang River drains the northern extent of the mineral boundary, where no surface or underground activities are proposed. This system will be unaffected by mining.

The bulk of the area falls within an upstream catchment management area for fish (Figure 7), however the north eastern portion of the study area is categorised as a FEPA due to the presence of sensitive wetland systems as well as river ecosystems and fish species (Iggdrasil, 2016). This area will remain unaffected by surface infrastructure or underground mining.

According to KZN aquatic biodiversity conservation areas (Figure 8) the mineral boundary is split into areas available for development (north) and areas earmarked for conservation (south). Earmarked areas are prioritised for conservation planning and land use management and will be further assessed in the next 5 years for potential biodiversity

39 | P a g e

UITKOMST COLLIERY: IWWMP management. No conservation areas occur within the mineral boundary. The existing Uitkomst Adit and underground mine areas falls within an area earmarked for conservation.

The Sub Quaternary Reach (SQR) of the Slang River (V31A-02319) indicated that the SQR is regarded as largely natural has a high ecological importance and a very high ecological sensitivity (Iggdrasil, 2016). This system will be unaffected by mining.

The SQR of the Doringspruit (V31D-02387) indicated that the SQR is regarded as largely modified has a moderate ecological importance and a high ecological sensitivity (Iggdrasil, 2016). This is the main receiving water body for the proposed Klipspruit Mine.

The SQR Kweekspruit (V32B-02414) was moderately modified had a high ecological importance and a very high ecological sensitivity (Iggdrasil, 2016). This is the main receiving water body for the proposed Uitkomst Mine.

From an overall aquatic perspective the receiving water bodies on site can be considered as moderately modified but of moderate to high conservation value.

Figure 6: NFEPA Wetland of relevance on site (SANBI, 2015)

40 | P a g e

UITKOMST COLLIERY: IWWMP

Figure 7: Quaternary catchment areas and fish support areas of relevance on site (SANBI, 2015)

Figure 8: KZN aquatic biodiversity zones of relevance on site (SANBI, 2014)

Biomonitoring Results

41 | P a g e

UITKOMST COLLIERY: IWWMP

Aquatic biomonitoring was completed by Iggdrasil during the high and low flow seasons of 2016. However as South Africa was experiencing a severe drought not all sites visited had enough water to complete adequate assessments.

Plan 7 indicates the sites visited during the surveys and Table 13 and 14 summarise the biomonitoring findings. Some correlation was observed with regional data in the sense that the Slang River system indicated highest ecological class. The remaining systems varied between modified to seriously modified ratings for various ecological class ratings, indicating that the systems are more modified than regional data presents.

Plan 7: Baseline Biomonitoring Points (Iggdrasil, 2016)

42 | P a g e

Table 13: Biomonitoring results (High Flow/Wet Season 2016)

Site Description IHAS Score (%) IHAS Class Temp pH EC DO VEGRAI FISHRAI SASS5 Diatom (°C) (mS/m) (%) EC Class EC EC

KLB1 On the Doringspruit, a tributary of the Buffels 67 Acceptable 23 9.00 22.0 52.4 D D/E C N/S River. Shallow slow moving waters over algae covered stones and gravel substrate with marginal vegetation. Some pools with muddy substrates. Surrounded by agricultural land.

KLB2 On the Doringspruit, a tributary of the Buffels 52 Insufficient 22.5 8.32 26.4 67.0 C D/E C B/C River. Shallow slow moving waters over slate sheet bedrock with limited marginal vegetation. Pools between cascading waterfalls with muddy substrate (with 4m waterfall). Surrounded by agricultural land.

KLB3 On Doringspruit tributary. Sites were dry and could not be sampled but should re-evaluate during the next wet season sampling

KLB4

KLB5 On the Kweekspruit, a tributary of the Buffels 55 Insufficient 24.7 9.09 20.6 53.0 C D E-F N/S River. Wide channel with very slow moving waters over bedrock containing many pools or ‘potholes’. Limited marginal vegetation present. Surrounded by agricultural land.

KLB6 On the Kweekspruit, a tributary of the Buffels 46 Insufficient 25.7 7.98 36.2 73.5 C D C C River. Very slow moving waters over sandy and muddy substrate containing few pools; limited marginal vegetation. Narrow channel had much overhanging vegetation with incised riparian banks in some areas.

43 | P a g e

Site Description IHAS Score (%) IHAS Class Temp pH EC DO VEGRAI FISHRAI SASS5 Diatom (°C) (mS/m) (%) EC Class EC EC Surrounded by agricultural land.

KLB7 On an unnamed tributary of the Slang River, 71 Acceptable 23.7 7.5 10.7 85.0 B E D B that flows into the Zaaihoek Dam. Slow flowing water over stones, gravel and sand with pools, runs and riffle areas.

44 | P a g e

Table 14: Biomonitoring results (Low Flow/Dr Season 2016)

Site Description IHAS Score (%) IHAS Class Temp pH EC DO VEGRAI FISHRAI SASS5 Diatom (°C) (mS/m) (%) EC Class EC EC

KLB1 On the Doringspruit, a tributary of 59 Insufficient 18.2 8.39 21.80 81.9 D E C B the Buffels River. Shallow slow moving waters over algae covered stones and gravel substrate with marginal vegetation. Some pools with muddy substrates. Surrounded by agricultural land.

KLB2 On the Doringspruit, a tributary of 52 Insufficient 14.5 8.5 32.4 67.4 C E C B the Buffels River. Shallow slow moving waters over slate sheet bedrock with limited marginal vegetation. Pools between cascading waterfalls with muddy substrate (with 4m waterfall). Surrounded by agricultural land.

KLB3 On Doringspruit tributary. Sites were dry and could not be sampled but should re-evaluate during the next dry season sampling

KLB4

KLB5 On the Kweekspruit, a tributary of 50 Insufficient 11.3 7.96 23.1 71.2 C/D E D B the Buffels River. Wide channel with very slow moving waters over bedrock containing many pools or ‘potholes’. Limited marginal vegetation present. Surrounded by agricultural land.

KLB6 On the Kweekspruit, a tributary of 57 Insufficient 17.3 8.76 36.7 64.0 C E E/F B the Buffels River. Very slow moving waters over

45 | P a g e

Site Description IHAS Score (%) IHAS Class Temp pH EC DO VEGRAI FISHRAI SASS5 Diatom (°C) (mS/m) (%) EC Class EC EC sandy and muddy substrate containing few pools; limited marginal vegetation. Narrow channel had much overhanging vegetation with incised riparian banks in some areas. Surrounded by agricultural land.

KLB7 On an unnamed tributary of the 73 Acceptable 14.3 7.81 11.3 85.1 B E B B Slang River, that flows into the Zaaihoek Dam. Slow flowing water over stones, gravel and sand with pools, runs and riffle areas.

46 | P a g e

UITKOMST COLLIERY: IWWMP

4.2.6 Receiving Water Quality Objectives & Reserve

The following has been extracted from the DWAF report (2004) on water availability in the Thukela Water Management Area. The Buffalo River includes the towns of Dundee, Newcastle, , Utrecht and . The main storage dams in the Buffalo catchment are:

 Ntshingwayo Dam (previously known as Chelmsford Dam) which has a capacity of 199 million m3. The dam was built to supply water to the town of Newcastle, Eskom’s thermal power station and irrigation farmers downstream. Releases are sometimes made to dilute factory spillages that end up in the river system.  Zaaihoek Dam, which was has capacity of 193 million m3. Zaaihoek Dam is on the Slang River, a tributary of the Buffalo River, and is used to transfer water to the Vaal system and the Majuba Power Station. Zaaihoek Dam can also supply downstream requirements by releasing water into the Slang River.

The MAR of the Buffalo Key Area is 884 million m3/a. The gross available surface water in the Buffalo River based on current development levels is estimated at between 173 million m3/a and 205 million m3/a depending on where in the catchment the water is utilised. Most of this yield is derived from dams discussed above. The occasional surplus in the Zaaihoek Dam was not made available in water quantity calculations.

Table 15: Overview of water availability and use in the Buffalo River Key Area

Resource Category Water available/requirement at a 1:50 year assurance (million m3/a)

At outlet of Key Area At Ntshingwayo Dam

Gross surface water resource 205 173

Subtract : Ecological Reserve 33 33

Invasive alien plants 4 4

Dryland sugarcane 0 0

Net surface water resource 168 136

Groundwater resource 6 6

Return flows 32 32

Total local yield 206 174

Transfer In 0 0

Grand Total 206 174

Irrigation 50

Urban 24

Rural 9

Industrial 12

Afforestation 1

47 | P a g e

UITKOMST COLLIERY: IWWMP

Resource Category Water available/requirement at a 1:50 year assurance (million m3/a)

At outlet of Key Area At Ntshingwayo Dam

Total local requirements 96

Transfers Out 55

Grand Total 151

Balance 55 23

There are significant return flows from irrigation, the urban and commercial centres as well as the mining and industrial activities in the catchment; the return-flow volumes being similar to that of the requirements of the ecological Reserve.

Irrigation is the dominant water use. The urban, rural and mining/industrial requirements are also significant, largely due to the development in and around Newcastle.

There is surplus water available in the Buffalo River Key Area that can be allocated without affecting the reserve allocation. Priority must be given to redressing of inequities and poverty eradication. Allocations must however be dealt with cautiously and the location of the surplus identified before making allocations. New allocations should not be made upstream of the Zaaihoek or Ntshingwayo dams unless accompanied by the provision of additional yield through the construction of farm dams.

The upper Buffalo River is the most severely impacted from a water quality perspective within the Thukela WMA. Acid mine drainage from numerous old coal mines and industrial pollution from the Newcastle area and the Ngagane River area, requires special intervention. Water quality in the length of the Buffalo River has been described by the Regional Office as being very poor.

It appears that RQO’s for the catchment have not been specifically set. The mine-related contamination is however dealt with in this IWWMP as this would be relevant to the development and includes:

 Addressing impacts associated with mining-related impacts, specifically decant water and AMD formation.  Addressing salt- and contaminant-loading into the Buffalo River Catchment.

4.2.7 Surface water User Survey

Water requirements in the Buffalo River Key Area are largely for irrigation followed by urban, mining/industrial and rural requirements. The area has a total demand of approximately 96m3/a, around 55m3/a is released from the catchment and availability in the catchment is estimated at 206m3/a. The catchment has a surplus of 55m3/a (DWAF, 2004). It must be stressed that the reserve has not specifically been included within the DWAF (2004) report.

Groundwater is the primary water source. Surface water use around the mine on the mine portions is primarily from springs that occur in the area and farm dams fed in part by springs

48 | P a g e

UITKOMST COLLIERY: IWWMP and rainfall. This water is used for domestic purposes as well as agricultural use in stock watering

4.3 SENSITIVE AREAS SURVEY

The overall mining right area is largely natural to semi-natural vegetation used for grazing purposes. Smaller portions have been transformed for crops or specific grazing lands, possibly for milk-cows. It has been found that most of the tracts of lower-lying grasslands are ‘managed’, i.e. regularly burnt and possibly ploughed to some degree in the past, and species assemblages vary according to management actions. Most of the region around the Klipspruit Adit 2 is at best semi-natural, where old mining activities have been abolished and the area revegetated.

An established road system exists to the Uitkomst and Klipspruit Adits off the R34 between Newcastle and Utrecht. Several Eskom lines traverse the study area, with a substation close to the planned new Klipspruit Adit. As mentioned above, the Uitkomst Adit 1 is fully operational, with pollution control dams, ore stockpile area, mine residue disposal sites and all related mine infrastructure.

No formally protected areas occur on site, although large areas have been incorporated into the National Protected Expansion Areas.

No other threatened ecosystems occur on site.

The vegetation types on and in close proximity of the study area as described in Mucina and Rutherford (2006) are the KwaZulu Natal Highland Thornveld (Gs6); the Wakkerstroom Montane Grassland (Gs7); and the Income Sandy Grassland (Gm14) (Dimela, 2016). None of the vegetation units are listed as threatened.

According to Mucina and Rutherford (2006), the KwaZulu Natal Highland Thornveld vegetation type is relevant to the main infrastructure areas and underground mining areas. Contrary to this, when comparing species assemblages on the ground, the largest part of the study area appears to be covered with Wakkerstroom Montane Grassland, especially the central plateau and boulder ridges, or it is at least a very strong transition to this vegetation type. Its landscapes is comprised of low mountains and undulating plains, covered mostly by short montane grasslands (Dimela, 2016).

The EKZN Wildlife Minset database shows that portions of the mining right area are classified as Critical Biodiversity Areas (Figure 9) (EKZNW 2010). Note that the Adit and infrastructure areas do not fall within any of these areas. CBA1 priority areas are associated with the northern extent of the mineral area where no surface or underground activities are proposed. Portions of the southern half of the properties overlay areas that are classified as ‘Critical Biodiversity Priority Area (Type 3 Optimal).

This new infrastructure will be close to the western extent of the historical Klipspruit mine workings, and placed on either secondary vegetation or habitats of relatively low species diversity and accordingly low sensitivity (see (Dimela, 2017).

49 | P a g e

Figure 9: KZN terrestrial biodiversity areas in relation to the mineral boundary

50 | P a g e

UITKOMST COLLIERY: IWWMP

Plan 8: Vegetation Association mapped for the study area (Dimela, 2017)

Plan 9: Vegetation Sensitivity mapped for the study (Dimela, 2017)

51 | P a g e

UITKOMST COLLIERY: IWWMP

The mining right area falls within the extreme southern portion of the Grasslands IBA (IBA No SA020) (Figure 9). The IBA extends from Newcastle and Utrecht in the south to Amersfoort in the north. It is considered a very valuable IBA and supports bird populations that meet all three categories, and is most notable for holding particularly important populations of several highly threatened species. However, the areas and species of most importance mostly occur away from the study site, particularly around the towns of Wakkerstroom, Memel and Volksrust (Marnewick et al 2015, Taylor et al 2015). Nevertheless, a number of sensitive species do occur and are likely to occur within the mining right area. Three Red Data species, White-bellied Korhaan, Southern Bald Ibis and Blue Crane were recorded on site during the 2016 survey and are likely to be regular within the mining right area (Harvey, 2017).

Figure 10: Mining Right Area in relation to Important Bird Areas (Harvey, 2017)

The mining right area is characterised by many wetlands including five hydrogeomorphic (HGM) units, namely: hillslopes seeps, hillslope seeps linked to stream channel, valley bottom without channel, valley bottom with channel and pan wetlands. Please refer to the Wetland/Riparian Assessment Report for full details (Hydro Pedo, 2017; APPENDIX 6). The wetland systems within the overall mining right are were categorised according to their HGM state(s) as well as being significantly disturbed or not. Thus, 10 grouped wetland systems were identified (Table 16).

52 | P a g e

UITKOMST COLLIERY: IWWMP

Due to surrounding land uses and activities including construction of roads, abstraction of surface and borehole water, farming of livestock, agricultural activities and mining, many of these wetlands have been greatly impacted upon and are in a disturbed state. According to the assessment, “the geomorphology of these wetlands is mostly intact, while the vegetation component is the most modified. The absence of major infrastructure, large dams, and year-around irrigation sustains the hydrological function of the wetlands in the study area. The vegetation is mostly affected due to the removal of natural communities through the establishment of dams, the presence of erosion channels and gullies, and agricultural activities within the wetland boundary.” (HydroPedo, 2017).

Table 16: Wetland systems occurring in MRA (Hydro Pedo, 2017)

Wetland Disturbed / HGM types included in system Undisturbed

A Undisturbed Hillslope seeps of single and multiple HGM units

B Disturbed Hillslope seeps of single and multiple HGM units

C Disturbed Hillslope seep with excavated eye

D Undisturbed Hillslope seep linked to a stream channel

E Disturbed Hillslope seep linked to a stream channel

F Undisturbed1 Hillslope seep on very steep topography

G Undisturbed Valley bottom wetland with channel

H Disturbed Valley bottom wetland with channel

I Undisturbed Valley bottom wetland without channel

J Undisturbed Pans

Note: HGM units are abbreviated on maps according to the following: C: channeled; VB: valley bottom; HS: hillslope seep; P: pan; d: disturbed.

The mean Present Ecological Status (PES) of the wetlands in the study area was assessed to be C: Moderately modified. Furthermore, the overall Ecological Importance and Sensitivity (EIS) of the wetlands in the study area is regarded as B: High, which are wetlands that are considered to be ecologically important and sensitive, where the biodiversity of these wetlands may be sensitive to flow and habitat modifications and they play a role in moderating the quality and quantity of water of major rivers.

1 Assumed, as not distinguished in specialist report

53 | P a g e

Plan 10: Wetland delineation of the overall Mining Right Area by Hydro Pedo (2017)

54 | P a g e

UITKOMST COLLIERY: IWWMP

Only a proportion of the assessed wetlands will be affected by the proposed surface and underground activities (Plan 11). The wetlands affected by the two surface infrastructure areas and underground mine plan are summarised in the sub-sections below.

Underground Mine Areas:

The underground mine plan is overlain on surface by some wetlands, dominated by two channeled valley bottom systems that drain into the Doringspruit (Plan 11). The wetland system in the north-western area consists of a combination of wetland type G and H (Table 16), being undisturbed and disturbed channeled valley bottom wetlands with an overall combined PES of C/D – Moderately to Largely modified. The central wetland system is characterised as type H, being a disturbed channeled valley bottom wetland system, with an overall combined PES of E – Seriously modified (Hydro Pedo, 2017).

These wetlands are largely fed by surface water from seasonal rainfall and the base flow from the upper weathered aquifer, which ranges from 5 to 20 mbgl. The underground mining ranges from a minimum depth of 18mbgl to a maximum of 350mbgl. The mining is largely occurring deeper than 100m, which has no interaction with surface water reserves (Future Flow, 2017). These areas of the underground mining are thus not expected to interact directly with the surface and shallow sub-surface hydrogeological processes significantly (Future Flow, 2017).

However, the area where the mining is within 20 to 100mbgl has the potential to negatively affect the upper weather aquifer and the surface wetland systems. The shallowest area of the coal seam is associated with the adit and this is where the largest impact could be. The impact to the wetland could be related to dewatering during operations and negative impacts on water quality post-mining.

It is important to note that the leach test results do not show significant acid generating potential, which lowers the potential negative water quality impacts the underground mining could have on the surface water resources (Future Flow, 2017).

55 | P a g e

Plan 11: Wetlands as delineated by Hydro Pedo (2017) in relation to the underground mine plan, and 22 kV powerline

56 | P a g e

UITKOMST COLLIERY: IWWMP

Adit & Infrastructure Areas:

The Uitkomst Adit and associated infrastructure was constructed in a non-perennial stream and hillslope seep (Plan 12). The disturbed hillslope seep has been determined to be a ‘Type C’ wetland as per Table 16. This wetland has been assessed to have a PES of F – Critically modified (Hydro Pedo, 2017). The wetlands feed into a valley bottom wetland downslope (east) and these systems are identified broadly as wetland Type H, being disturbed valley bottom wetlands with a channel. These wetlands have been assessed to have a mean PES of E – Seriously Modified (Hydro Pedo, 2017).

Plan 12: Uitkomst Adit 1 and affected wetlands as delineated by Hydro Pedo (2017)

The proposed Klipspruit Adit 2 is not planned to be constructed within any delineated wetlands. This area has already been disturbed by previous mining and has been assessed to no longer function naturally within the hydrological landscape (Hydro Pedo, 2017). This infers that there will be no significant direct impact to wetlands as this area is already impacted upon.

However, this area is within 100m of a valley bottom wetland and stream associated with the Doringspruit. This wetland system consists of a combination of wetland type G and H (Plan 12), being undisturbed and disturbed valley bottom wetlands with a channel respectively. The overall combined PES of this system has been determined to be C/D – Moderately to Largely modified.

The proposed route of the overhead powerline has avoided wetlands as far as possible as no pylons are placed in wetlands; however some pylons and cables will be within 100m of the identified wetlands.

57 | P a g e

UITKOMST COLLIERY: IWWMP

Plan 13: Proposed Klipspruit Adit infrastructure and surrounding wetlands as delineated by Hydro Pedo (2017)

4.4 GROUNDWATER (Future Flow, 2017)

The section below is extracted from the Geohydrological Study completed by Future Flow in 2016, revised in 2017. Please refer to APPENDIX 8 for a copy of the full report. 4.4.1 Aquifer Characterisation

Two aquifers occur in the area. These two aquifers are associated with a) the upper weathered material, and b) the underlying competent and fractured rock material.

Upper weathered material aquifer:

The upper aquifer forms due to the vertical infiltration of recharging rainfall through the weathered material being retarded by the lower permeability of the underlying competent rock material. Groundwater collecting above the weather / unweathered material contact migrates down gradient along the contact to lower lying areas.

Aquifer thickness data was available from the monitoring borehole drilling results. The recorded data shows that the upper aquifer has an average thickness of approximately 12 m, and can range between 5 and 20 m in thickness. These minimum and maximum values are not absolute values for the entire study area. Lesser thicknesses can occur from the competent hard rock outcropping in places throughout the high lying area.

It is considered that effectively between 1 and 3 % of the mean annual rainfall eventually reaches the groundwater table in the form of recharge to the aquifers (Grobbelaar, Usher,

58 | P a g e

UITKOMST COLLIERY: IWWMP

Cruywagen, de Necker, & Hodgson, 2004). Typical transmissivity values for this aquifer range between 0.1 and 2 m2/day.

The borehole yields in this aquifer are seasonally variable due to the strong dependence on rainfall recharge. Generally, it can be said that the yields of this aquifer during the rainy season can be around 1 to 3 L/s while sustainable yields will decrease markedly during the dry season. In some areas this aquifer will be laid completely dry during the dry season.

The groundwater quality in undisturbed areas is good due to the dynamic recharge from rainfall. This aquifer is, however, more likely to be affected by contaminant sources situated on surface.

Based on the combined effect of the relatively shallow nature of the weathered zone, where a number of areas have the competent rock outcropping on site, and the dependence on recharge from rainfall, it can be said that this aquifer is expected to show significant seasonal fluctuations.

Lower fractured rock aquifer:

Although the lower permeability of the unweathered rock material will retard vertical infiltration of groundwater, a percentage of the water in the upper aquifer will recharge the lower aquifer. Direct recharge from rainfall can occur where the fractured, competent rock outcrops. In areas where the stream bases of the non-perennial rivers are located directly on top of the competent rock the aquifer can be directly recharged from the surface stream.

The competent rock is subjected to fracturing associated with tectonic movements that took place during intrusion of dolerite dykes and sills into the older Karoo aged sandstone and shale sediments. Groundwater flows in the lower aquifer are associated with the secondary fracturing in the competent rock and as such will be along discrete pathways associated with the fractures. Faults and fractures in the sandstone and shale can be a significant source of groundwater depending on whether the fractures have been filled with secondary mineralisation.

The aquifers present in the area are classified as minor aquifer, but of high importance to the local landowners as it is their sole source of water for domestic and agricultural (stock watering and irrigation) purposes.

4.4.2 Hydrocensus

A hydrocensus was undertaken on the 2nd of February 2016 to identify and document groundwater users in the region. An additional two monitoring boreholes were drilled in the project area. In total 15 boreholes were located in the field.

The results of the hydrocensus are summarised in Table 17 and shown graphically Figure 11Figure 12. From this it can be seen that the depth to groundwater level ranges between artesian and 20.29 mbgl. Boreholes BH9 and BH10 were not accessible and the depth to groundwater level could not be measured. The depth to groundwater level at the point “Fountain” is assumed to be 0 m.

The water level measured in borehole “De Jager” appears to be anomalously deep compared to other boreholes in the area and is possibly due to the borehole being pumped shortly before the water level was measured. Borehole “Community” that is located close by

59 | P a g e

UITKOMST COLLIERY: IWWMP shows a water level of 7.50 mbgl which is in line with the other groundwater levels measured in the area.

In addition, the depth to groundwater level in borehole “BH11” is also anomalously low at 20.29 m. The reason for this is not known.

In areas where there are no large scale external impacts on the groundwater environment, such as the lowering of groundwater level through dewatering, and where the geology and aquifer interactions are not excessively complex it is expected that the groundwater level contours will reflect topographical contours, although at a moderated gradient.

Plotting groundwater level elevation versus topographical elevation for this project area yields a 99 % correlation as shown in Figure 12. This is a very high correlation between the groundwater level elevation and topographical elevation, however only nine groundwater levels which were obtained from the hydrocensus were used and there is limited information available in the study area. From this it is concluded that the groundwater levels generally mimic topography in the areas where the boreholes are located.

Figure 11: Depth to groundwater level

60 | P a g e

UITKOMST COLLIERY: IWWMP

Figure 12: Topographical vs. groundwater elevation plot

61 | P a g e

Table 17: Hydrocensus results

Easting Northing Elevation Water level BH Owner WGS84, LO31 WGS84, LO31 mamsl mbgl mamsl

BH1 -84 851.4 -3 055 016 1 264.64 6.39 1 258.25 Uitkomst Colliery – monitoring borehole

BH2 -84 615.4 -3 054 842 1 265.47 11.91 1 253.56 Uitkomst Colliery – monitoring borehole

BH3 -85 304.1 -3 053 107 1 311.07 5.79 1 305.28 Uitkomst Colliery – monitoring borehole

BH4 -86 943.4 -3 055 172 1 300.24 8.21 1 292.03 Uitkomst Colliery – monitoring borehole

BH5 -88 250.4 -3 055 798 1 286.59 7.33 1 279.26 Uitkomst Colliery – monitoring borehole

BH6 -88 005.4 -3 055 078 1 322.01 6.93 1 315.08 Uitkomst Colliery – monitoring borehole

BH7 -86 048.7 -3 052 873 1 376.90 - - Uitkomst Colliery – monitoring borehole

BH8 -88 430.4 -3 051 945 1 376.51 - - Uitkomst Colliery – monitoring borehole

BH9 -86 772.4 -3 051 594 1 430.96 - - Uitkomst Colliery – monitoring borehole

BH10 -86 929.4 -3 051 115 1 373.66 - - Uitkomst Colliery – monitoring borehole

BH11 -83 582.4 -3 052 662 1 271.46 20.29 1 251.17 Uitkomst Colliery – monitoring borehole

BH12 -90 229.4 -3 054 796 1 292.14 1.33 1 290.81 Uitkomst Colliery – monitoring borehole

Fountain -85 347.1 -3 051 741 1 316.11 0 1 316.11 Fountain – privately owned

Landman -90 053.8 -3 053 690 1 323.93 4.04 1 319.89 Johan Landman – private borehole

Community -87 196.3 -3 048 633 1 501.27 7.50 1 493.77 Community – private borehole

DeJager -87 196.4 -3 048 424 1 501.57 20.01 1 481.56 Nick de Jager – private borehole

New BH3 -85 287.7 -3 055 531 1 264.03 3.46 1 260.57 Uitkomst Colliery – monitoring borehole

Klip 1 -87 767.5 -3 051 999 1 400.41 10.66 1 389.75 Klipspruit Colliery – monitoring borehole

Klip 2 -89 890.4 -3 052 793 1 286.51 0 1 286.51 Klipspruit Colliery – monitoring borehole

62 | P a g e

Plan 14: Hydrocensus Points

63 | P a g e

UITKOMST COLLIERY: IWWMP

4.4.3 Potential Pollution Source Identification

Pollution Sources on Site:

The underground mine area, MRDS, overburden and topsoil stockpile areas, process water dams and settling dams act as potential sources of contamination to the aquifers. For the purpose of this discussion it is assumed that good housekeeping such as storage of potentially hazardous material will be within properly constructed and lined or paved areas. Oil traps will be sized, operated and maintained to contain all discarded oil from working areas etc.

Leach testing and the results can be used to determine the potential source concentrations. From the leach testing it can be seen that all the samples comply with the IFC effluent guidelines. Therefore, it was decided to apply a generic approach during the impact assessment modelling. The results can then be applied to any contaminants that may be identified.

A value of 100 is assigned to the pollution source areas; in this case the underground mine area, mine residue, overburden and topsoil stockpile areas, process water dams and settling dams. In effect this represents 100 % of the starting concentration of any contamination. The plume distribution then represents the percentage of starting concentration that will be measured at a specific point. For example should the plume at a specific point indicate a value of 50, it indicates that the element concentration at the point and time is expected to be 50 % of the initial source concentration.

4.4.4 Groundwater Model Results: Operational

Groundwater level drawdown:

The mine floor elevations are below the general groundwater level thus causing groundwater flows into the underground mining area from the surrounding aquifers during operations.

The 3D numerical groundwater flow model was used to simulate the development of the drawdown cone over time in the vicinity of the underground mine area. The provided mine plan that indicates a nine year life of mine for the operations was used.

Numerical modelling shows that during the life of operations the groundwater flow directions in the vicinity of the underground mine will be directed toward the mine area. This is due to mine dewatering causing the groundwater levels to be drawn down to the mine floor elevations.

The maximum drawdown in the groundwater level from pre-mining levels in the upper weathered aquifer is negligible and calculated at less than 1 m. The maximum drawdown is calculated at 250 m for the lower fractured aquifers (Plan 15).

The direct impact of the mine dewatering on the fractured rock aquifer, within which the mining area is located, is greater than the impact on the weathered material aquifer which lies more than 100 metres above the underground workings and is to some extent disconnected from the impact of the mine dewatering by the semi-impermeable sandstone

64 | P a g e

UITKOMST COLLIERY: IWWMP and shale that overlies the mining area and separates the mine from the weathered material aquifer.

The drawdown in groundwater level and the associated cone of depression will develop over time in the fractured rock aquifer as the mining progresses. In the fractured rock aquifer the zone of influence of the groundwater level drawdown extends up to 1 400 m west and 1 100 m north and south of the mining area.

The springs located on the plateau and the escarpment are dependent on the upper weathered aquifer which is reliant on recharge from rainfall. Based on the disconnect between the deeper lying underground mine, and the shallow aquifer that feed the springs that occur on the plateau and escarpment as described above, the impact from mine dewatering on the springs on the escarpment is calculated to be minimal (<1%) because mining occurs within the fractured rock aquifer which will experience the greatest impact. The exception will be around the Klipspruit access point (proposed Adit 2) which will be directly connected to the upper weathered aquifer. The zone of influence of the impact on the groundwater levels in the weathered material aquifer is expected to be less than 500 m in extent.

Plan 15 shows that six of the hydrocensus boreholes (BH8, Klip1, Klip2, Landman, Community and de Jager) will be impacted by the groundwater level drawdown in the area. The maximum drawdown in groundwater level in each of the boreholes during the life of operations is calculated at:

 BH8: 40.7 m;  Klip1: 37.1 m;  Klip2: 3.7 m;  Landman: 1.9 m;  Community: 12.8 m and  De Jager: 12.8 m. Three of these boreholes are monitoring boreholes and are not used by private landowners for water supply. Three of these boreholes (Landman, Community and de Jager) are privately owned and used for water supply purposes, however the boreholes are located in the weathered material aquifer which shows an extent of disconnect with the fractured rock aquifer where the underground workings and associated dewatering will take place.

Groundwater inflows into the underground mine

Groundwater inflows volumes into the mine area over 9 years were calculated using the 3-D numerical groundwater flow model. The obtained results are summarised in Table 18.

65 | P a g e

UITKOMST COLLIERY: IWWMP

Table 18: Groundwater inflow volumes into the underground mining area

Year Expected groundwater inflow volume (m3/day)

1 3 510

2 3 870

3 4 840

4 6 400

5 7 385

6 8 275

7 8 930

8 9 490

9 8 365

The groundwater inflow volumes into the underground mining area are expected to range between 3 510 and 9 490 m3/day. The groundwater inflow volumes decrease slightly during the final year of mining.

The high inflow volume is due to the mining area expanding into areas where the host geology is not dewatered yet and water is released from storage, thus keeping the inflow volumes relatively high. During the last year of life of mine less statured rock is broken and the inflows decrease.

The flow model only takes average yearly values such as average annual recharge from rainfall into consideration. Therefore, no seasonality is included in the calculations. However, it is not expected that the fractured rock aquifer will show significant seasonal changes.

Groundwater contamination:

The pollution source areas (underground mine area, mine residue, overburden and topsoil stockpile areas, process water dams and settling dams) are located on the western and south eastern perimeter of the existing Uitkomst Adit area outside the zone of influence of the groundwater level drawdown cone; therefore it can be expected that contamination will migrate away from these sources during the operational phase. Similarly, the overburden and RoM stockpile area at the proposed Adit 2 fall outside the groundwater level drawdown cone and contamination is expected to migrate away from these point sources.

It must be noted however that leach test results show that the leach qualities are expected to comply with the LCT0 quality guidelines. Therefore, it can be said that the impact on the groundwater quality of any seepage that originates from the mining area will not exceed water quality guideline requirements. This should be kept in mind when interpreting the pollution plumes shown in Plan 16 and Plan 17 as well as the discussion below.

66 | P a g e

UITKOMST COLLIERY: IWWMP

The contaminant plumes are calculated to migrate 400 m and 1 000 m down gradient from the western and south eastern areas respectively. The wetland and three monitoring boreholes (BH1, BH20 and New BH3) will be impacted by seepage migration away from the potential pollution sources.

Contaminant migration away from the overburden and RoM stockpiles at the Adit 2 are expected to migrate approximately 300 m down gradient. Contamination is expected to reach the Doringspruit west of Adit 2K.

During the operational life of mine the mining area will be dewatered. This will cause the groundwater flow directions around the mining area to be directed towards the mine. Due to this, little to no contamination is expected to migrate away from the mining area during the life of mine.

Contamination that does escape the mining area is expected to migrate downgradient slightly as shown in Plan 17. It is not expected that streams in the area will be impacted significantly (>1 %) based on the fact that:

 The contaminant migration will be along the fractured rock aquifer with no direct discharge into the streams; and  Leach test results show the leachate that forms in the underground mine is expected to be of relatively good quality and all elements comply with LCT0 quality guidelines.

67 | P a g e

Plan 15: Groundwater Level Drawdown (Operational)

68 | P a g e

Plan 16: Contamination Plume – Upper Weather Aquifer (Operational)

69 | P a g e

Plan 17: Contamination Plume – Lower Fractured Aquifer (Operational)

70 | P a g e

UITKOMST COLLIERY: IWWMP

4.4.5 Groundwater Model Results: Long Term Post Operations

Recovery of groundwater levels and decant potential:

In the post operational environment groundwater levels and flow patterns in the area will recover to near pre-operational levels. The time required for recovery of the groundwater levels to near pre-operational levels in the study area will be dependent on a number of factors:

 There will be inflows into the underground mine from the surrounding aquifers. The inflow rate will depend to a large extent on the groundwater flow gradient between the groundwater level in the surrounding aquifers and the water level in the underground mine; and  Recharge from rainfall into the underground mine has been shown to range around 1 % of the mean annual rainfall (Grobbelaar, Usher, Cruywagen, de Necker, & Hodgson, 2004). This will contribute to the flooding of the underground mine. The rate of rise of the water level in the underground mining area can be calculated:

As described above the inflows into the underground mine areas will depend on inflows from the surrounding aquifers. The mining area is measured to be approximately 8.61 km2 (8.61×106 m2). Using an average void space of 70 % of the underground mining area with the pillars in place, the mining area of 8.61×106 m2 and an average seam thickness of 1.5 m, it can be calculated that approximately 9 040 500 m3 of void space has to be filled.

Inflows from the surrounding aquifers were calculated to be between 3 510 and 9 490 m3/day. The inflows are partly controlled by the groundwater flow gradient with increasing flow associated with higher flow gradients. The inflows will reduce over time as the water level in the underground mine area rise and the flow gradient decreases due to the reduced vertical difference between the surrounding regional groundwater levels and the water level in the underground mine. For the purpose of this discussion an average of 6 000 m3/ day is used.

From the above it is calculated that recovery of the groundwater levels will take 1 506 days or approximately 4.1 years.

At no point is the coal seam floor elevation above that of the surface elevation at the mine entrance. Therefore, no decant is expected.

Contaminant migration:

The groundwater levels in the mining areas will recover due to the mine dewatering stopping. The recovering groundwater levels will lead to a re-establishment of groundwater flow patterns away from the mining area. This will allow for contaminant migration away from the mining area in a down gradient direction.

The expected contaminant plume at 50 and 100 years after closure is shown in Plan 18Plan 19 respectively. From this it can be seen that the contaminant plume development is expected to follow topography and migrate 1 000 m west toward the Dorpspruit and 2 000 m east towards the Kweekspruit.

71 | P a g e

UITKOMST COLLIERY: IWWMP

Leach test results show that the leach qualities are expected to comply with the LCT0 quality guidelines. Therefore, it can be said that the impact on the groundwater quality of any seepage that originate from the mining area will not exceed water quality guideline requirements. This should be kept in mind when interpreting the pollution plumes shown in Plan 18 and Plan 19.

72 | P a g e

Plan 18: Contaminant Plume 50 years post closure – Lower Fractured Aquifer

73 | P a g e

Plan 19: Contaminant Plume 100 years post closure – Lower Fractured Aquifer

74 | P a g e

UITKOMST COLLIERY: IWWMP

4.5 SOCIO-ECONOMIC ENVIRONMENT

Uitkomst Colliery is situated under the jurisdiction of the eMadlangeni (Utrecht) Local Municipality (KZN253) within the Amajuba District Municipality, in the KwaZulu Natal Province. Table 19 below summarises the demographics for the Local Municipality.

Table 19: Demographics (Source: www.localgovernment.co.za)

2016 2011

Population 36 869 34 442

Age Structure

Population under 15 38.6% 35.9%

Population 15 to 64 57.6% 59.1%

Population over 65 3.8% 5.1%

Dependency Ratio

Per 100 (15-64) 73.6 69.3

Sex Ratio

Males per 100 females 92.6 103.1

Population Growth

Per annum 1.55% n/a

Labour Market

Unemployment rate (official) n/a 37.6%

Youth unemployment rate (official) 15-34 n/a 46.4%

Education (aged 20 +)

No schooling 10.7% 14.9%

Matric 26.6% 20.1%

Higher education 8.1% 5.0%

Household Dynamics

Households 6 667 6 252

Average household size 5.5 5.2

Female headed households 45.3% 38.8%

Formal dwellings 67.4% 58.3%

Housing owned 79.5% 41.8%

75 | P a g e

UITKOMST COLLIERY: IWWMP

2016 2011

Household Services

Flush toilet connected to sewerage 32.7% 28.5%

Weekly refuse removal 29.4% 24.2%

Piped water inside dwelling 25.0% 27.0%

Electricity for lighting 57.2% 48.5%

76 | P a g e

UITKOMST COLLIERY: IWWMP

5. ANALYSIS & CHARACTERISATION OF WATER USE ACTIVITY

5.1 SITE DELINEATION FOR CHARACTERIZATION

The main delineated areas that have been considered are detailed in Figure 13. Each area is also linked to summary key activity processes, the main relevant infrastructure and key water uses.

5.2 WATER &WASTE MANAGEMENT

Each of the key processes and associated water uses have:

 Firstly been characterised under the four main key areas essential to IWWMP formulation (storm water, process water, groundwater and waste); and  Secondly, been elaborated regarding the process description and how the water use/waste handling relates to that process and how it will be managed.

77 | P a g e

Mine areas: South Mine Klipspruit

Operational areas:

Adit 1 / Uitkomst Adit 2

Key activity processes:  Underground mining  Underground mining  Material stockpiles  Material stockpiles  Coal processing  Operational, administrative & infrastructure support  Mine residue disposal  Operational, administrative & infrastructure support

Supporting Infrastructure:  Boxcut adit & sump  Boxcut adit & sump  All underground infrastructure incl. ventilation  All underground infrastructure incl. ventilation  Coal stockpiles  Coal stockpiles  Crusher, screener & beneficiation plant  Access roads & coal transport  Access roads & coal transport  Mine offices  Mine offices  Workshop & Wash bays  Workshop & Wash bays  Contractor’s yard  Contractor’s yard  Lamp room ,change house & Laundry  Laboratory  Conservancy tanks for sewage handling  Lamp room ,change house & Laundry  Water Storage Reservoirs & Jojo tanks  Conservancy tanks for sewage handling  Waste Storage Areas  Water Storage Reservoirs & Jojo Tanks  PCD  Waste Storage Areas  MRDS  Plant Dams  RWD  PCD

Water uses:  21(a): reuse of underground water (associated with 21j dewatering activity)  21(a): reuse of underground water (associated with 21j dewatering activity)  21(a): abstraction of water from borehole for potable use  21(a): abstraction of water from borehole for potable use  21(b): storage of water with reservoirs  21(a): abstraction of water from the old Kangra workings  21(c & i): Uitkomst Adit/Adit 1 & associated infrastructure within a disturbed valley  21(c & i): Klipspruit Adit 2 and associated infrastructure <100m from a non-perennial bottom stream  21(c & i): Undermining a streams & wetland  21(c & i): Undermining streams & wetlands  21(g): MRDS, RWD, PCD, Plant water dams, coal stockpile, and dust suppression  21(c & i): Overhead powerline <500m of a wetland  21(j): Dewatering of underground mine  21(g): PCD, coal stockpile, and dust suppression  21(j): Dewatering of underground mine

Figure 13: Project Conceptualisation and operational hierarchy

78 | P a g e

UITKOMST COLLIERY: IWWMP

5.2.1 Process Water

Water will be recycled on site as far as possible and dirty water will be prioritized for process needs (use in the process plant or for use underground). The process plant uses approximately 3,250m3 of water / day.

Dirty Water Dams:

There are four existing dirty water dams at Uitkomst Adit/Adit 1 and one existing dam at the proposed Klipspruit Adit 2 area.

 Plant Water Dam A & Plant water Dam B: Receives water from the RWD. Fines are settled out and water is then fed to the plant for processing.  Uitkomst PCD: The PCD has been designed to contain runoff from the processing and infrastructure area during a 1:50 year flood event. PCD water will be pumped to the RWD for water balance maintenance. Recent investigations indicate that this dam is heavily silted and must be cleaned out to its original capacity.  Uitkomst RWD: will contain all dirty water runoff from the MRDS facility, as well as supernatant water pumped from slurry penstocks and seepage from the slurry collected from the under drainage at the MRDS facility. May also receive water from the PCD for water balance maintenance. Recent investigations indicate that this dam is heavily silted and must be cleaned out to its original capacity. Water will be pumped from the RWD to the Plant Dams for use in the plant. Water will also be abstracted from this dam for dust suppression.  Klipspruit PCD: It is proposed that the existing PCD (Plate 1) be upgraded. The PCD extension has been designed to cater for a 1:50 year flood event with a 0.80m freeboard (capacity of 5,000m3). The dam will receive runoff water from the Klipspruit dirty footprint area as well as water from the underground workings. This water will be used for dust suppression. Please refer to APPENDIX 10 for the applicable engineering drawings.

Dust Suppression:

Water for dust suppression will be sourced from the Uitkomst RWD and the Klipspruit PCD. Dust suppression. Water sourced from these dams for dust suppression will only be used within the dirty footprint of the mine, to prevent contamination of clean areas with dirty water.

For dust suppression over clean areas, water will be sourced from Farm Dam 1.

79 | P a g e

UITKOMST COLLIERY: IWWMP

Plate 1: Existing Klipspruit PCD

Coal Stockpiling:

RoM and product stockpiles exist at the Uitkomst Adit/Adit 1 area and have been licensed. The overall capacity has however since increased and must be amended (see Figure 14 below for the individual stockpiles areas and maximum storage capacity at the Adit 1 area). The cumulative, maximum coal storage capacity at Uitkomst Adit 1 is 103,510m3.

RoM coal from the Klipspruit underground will be temporarily stockpiled on surface at Adit 2 (maximum capacity estimated at 7,500m3) before being trucked to the existing Uitkomst plant area for processing.

All the coal stockpile areas will be compacted and made as impermeable as possible; and slightly sloped to drain water into the PCDs or sump.

80 | P a g e

UITKOMST COLLIERY: IWWMP

Figure 14: Existing Uitkomst Adit/Adit 1 Stockpiles

81 | P a g e

UITKOMST COLLIERY: IWWMP

Mine Residue Disposal Site (MRDS):

The existing MRDS is operated as a co-disposal facility i.e. coarse discard at the perimeter and slurry placed to the inside. The MRDS will in future need to be expanded up the mountain slope to meet the additional capacity requirements as such the MRDS has been re-designed (see APPENDIX 10).

The MRDS has under drainage to collect seepage from the slurry. Installation of sub surface drainage will also be required in the future expansion areas. This seepage collection system would be installed below the coarse discard section of the waste facility assisting with structural stability and environmental protection. This drain would consist of 2.0m wide fin drains, collection and outfall pipes. All seepage would be collected at designate outfall locations in manholes. The manholes are linked with a 250 OD UPVC collection pipe. Seepage water will flow under gravity to the RWD.

The existing slurry compartments are equipped with a concrete intake tower slotted to one side, to allow for slurry and water level control. Normal operation requires the placement of planks in the slot to control water decant. This method allows for the settlement of solids and decanting of water only, if correctly implemented. It is however proposed that the slurry placement be in such a way that the low point is always at the penstock intake. This can be achieved with the extension of the slurry delivery system to the inside perimeter of the discard facility (Davel, 2017).

Discard placement must be completed systematically in layers and along the wall, providing in order to provide for the necessary freeboard in the slurry pond. Continuous compaction of the discard must be undertaken to prevent spontaneous combustion.

The cut off trench is designed to collect runoff from the co-disposal facility and drains to the RWD.

Table 20 MRDS Facility Specifications

Description: Quantum:

Extension Slurry Volume 384,000m3

Extension Discard Volume 355,556m3

Highest point from NGL (Final) 25m

Existing Footprint Area 13.2 Ha

Final Footprint Area 18 Ha

5.2.2 Storm Water

In general storm water management and drainage infrastructure onsite accommodates a 1:50 year storm event as required by legislation. Clean and dirty water will be separated and dirty water channeled into dirty water containment facilities. Clean water will be diverted around various dirty footprints by means of channels and berms to the natural environment. Please refer to APPENDIX 10 for the engineering designs specifying the dimensions and location of the storm water drains.

82 | P a g e

UITKOMST COLLIERY: IWWMP

5.2.3 Groundwater

Dewatering activities will be carried out on site to allow for the safe continuation of mining. Electric pumps will be utilised to dewater the underground workings, and dispose of mine affected water into the boxcut sump prior for re-use. Water will be recycled as follows:

 Water will be pumped to the underground for any necessary water requirements associated with underground dust suppression and drilling.  Excess water will be stored underground within mined out sections.  Water will be pumped to the mine dams for plant make-up water or dust suppression where required. During the operational phase the maximum drawdown in the groundwater level from pre- mining levels in the upper weathered aquifer is negligible and calculated at less than 1 m. The maximum drawdown is calculated at 250 m for the lower fractured aquifers.

The direct impact of the mine dewatering on the fractured rock aquifer, within which the mining area is located, is greater than the impact on the weathered material aquifer which lies more than 100 metres above the underground workings and is to some extent disconnected from the impact of the mine dewatering by the semi-impermeable sandstone and shale that overlies the mining area and separates the mine from the weathered material aquifer.

The drawdown in groundwater level and the associated cone of depression will develop over time in the fractured rock aquifer as the mining progresses. The zone of influence of the groundwater level drawdown extends up to 1 400 m west and 1 100 m north and south of the mining area (Future Flow, 2017).

5.2.4 Potable & Domestic Water Supply

Water for potable and domestic use is sourced from two boreholes (1 at Klipspruit and 1 at Uitkomst), as well as the nearby Farm Dam.

 At Uitkomst Adit 1: water is pumped to two prefabricated reservoir tanks (each with a capacity of 250m3 - see Plate 2). From here it is circulated to a number of Jojo tanks for use within the change house, offices, ablutions and laundry.  At Klipspruit Adit 2: water will be pumped from the borehole to Jojo tanks for use within the change house, offices, ablutions and laundry.

83 | P a g e

UITKOMST COLLIERY: IWWMP

Plate 3: Photograph of Reservoir Tank(s) on site

5.2.5 Water Balance

Currently the mine is water deficient. However the groundwater model predicts that as mining progresses underground, an inflow of between 3 510 and 9 490 m3/day is expected, and thus in the long run a surplus expected. Excess water will remain underground and pumped into mined out compartments / workings. The table below summarises the expected water balance for the operations.

84 | P a g e

Table 21: Water Balance

FACILITY: WATER IN: m3/annum WATER OUT: m3/annum BALANCE:

Co-disposal Rainfall 84 012.00 Retained in material 25 203.60

Runoff to RWD 58 808.40

SUB-TOTAL: 84 012.00 SUB-TOTAL: 84 012.00 -

Plant & Stockpile Rainfall 70 010.00 Retained in material 20 302.90 Area Plant Dam A 49 707.10

SUB-TOTAL: 70 010.00 SUB-TOTAL: 70 010.00 -

Plant Dam A Rainfall 2 940.40 Evaporation 4 373.50

Runoff from Plant & Stockpile Area 49 707.10 To Plant Dam B 48 274.00

SUB-TOTAL: 52 647.50 SUB-TOTAL: 52 647.50 -

Plant Dam B Rainfall 3 150.50 Evaporation 4 685.90

Plant Dam A 48 274.00 To Uitkomst PCD 46 738.60

SUB-TOTAL: 51 424.50 SUB-TOTAL: 51 424.50 -

Uitkomst PCD Rainfall 3 500.00 Evaporation 520.70

Plant Dam B 46 738.60 Plant Feed 49 717.90

SUB-TOTAL: 50 238.60 SUB-TOTAL: 50 238.60 -

RWD Rainfall 4 550.70 Evaporation 6 768.50

Co-disposal 58 808.40 Dust Suppression @ Uitkomst 32 400.00

Plant Feed 26 408.40

SUB-TOTAL: 58 808.40 SUB-TOTAL: 58 808.40 -

Klipspruit PCD Rainfall 7 701.10 Evaporation 11 454.30

Runoff from stockpile & infrastructure area 10 291.50 Dust Suppression @ Klipspruit 32 400.00

Underground 25 861.70

SUB-TOTAL: 43 854.30 SUB-TOTAL: 43 854.30 -

Plant Feed RWD 26 408.40 Process Plant Requirements 1 170 000.00

Uitkomst PCD 49 717.90

Dewatering 913 873.70

Old Klipspruit Workings Borehole 180 000.00

SUB-TOTAL: 1 170 000.00 SUB-TOTAL: 1 170 000.00 -

Domestic & Potable Use Farm Dam 1 5 000.00 Offices & Change Houses 7 200.00

Borehole 1 5 000.00 Laundry 7 800.00

Borehole 2 5 000.00

SUB-TOTAL: 15 000.00 SUB-TOTAL: 15 000.00

Dewatering Groundwater inflow 1 281 150.00 Underground Processes 50 000.00

Plant Feed 913 873.70

Klipspruit PCD 25 861.70

SUB-TOTAL: 1 281 150.00 SUB-TOTAL: 989 735.40 291 414.60

85 | P a g e

UITKOMST COLLIERY: IWWMP

5.2.6 Waste

Waste generation on site will be minimal and will generally be limited to general domestic waste, sewage, scrap metal and used hydrocarbons. Table 22 below highlights main waste streams and waste handling and treatment.

Table 22: Proposed waste management strategy on site

Waste type Waste treatment

Domestic and office Locally collected in bins and transferred to skips for disposal at the municipal waste waste site. Recycling will be done as far as possible with regards to paper, glass, tins/cans, plastics, batteries and computer equipment, and inflorescent lights.

Sewage Conservancy tanks are and will continue to be utilized. Sewage will be removed from site by contractors and disposed of at a licensed facility for treatment.

Mine Water Water will be extracted to ensure the safe continuation of mining. This water will be used for underground mining related processes such as drilling. Excess water from these pits will be pumped to the surface, where it will be utilized for dust suppression or within the beneficiation plant.

Mine Residue & Slurry and discard will we disposed of onto the co-disposal facility (MRDS) as per Carbonaceous engineer designs and standard operating procedures. Supernatant water from Waste the superficial slurry pond will be piped off to the RWD.

Used hydrocarbon These will be collected in drums and stored within an adequately sized bunded waste area, constructed to SABS standards. The waste will be collected and removed from site by a reputable contractor and disposed of at a suitably licensed facility.

Old tyres, conveyor These will be collected and temporarily stored in an allotted area in the scrap belts yard for recycling by a reputable contractor.

Scrap metal

Old machinery

Building rubble Minimal building rubble will be removed from site and disposed of by the contractor. Where the material is safe to use for filling of final voids, then this will be done.

Sewage will report to prefabricated conservancy tanks, emptied on a regular basis by a reputable contractor for disposal at a licensed sewage works. Currently nine (9) conservancy tanks exist at the Uitkomst infrastructure area, each with a maximum capacity of 5m3. It is currently envisage that six (6) conservancy tanks will be installed at the Klipspruit Adit 2.

86 | P a g e

UITKOMST COLLIERY: IWWMP

Plate 4: Example of conservancy tank (Source: www.rainharvest.co.za)

5.3 OPERATIONAL MANAGEMENT

Uitkomst Colliery employs sub-contractors to conduct the underground mining. These contractors will be trained and have signed obligation with regard to environmental management. The persons responsible for the implementation of the IWWMP are indicated in the figure below:

General Manager Johan Gloy

Mine Manager Steven Taylor

SHEQ Manager Pieter Kruger

Figure 15: Organogram for the implementation of the IWWMP

5.4 ORGANISATIONAL STRUCTURE

The organisational structure for the company and the mine has been included under Section 2.7 above.

87 | P a g e

UITKOMST COLLIERY: IWWMP

5.5 RESOURCES & COMPETENCE

Uitkomst Colliery will ensure that all staff/contractors hired for any positions that may become available will have the relevant experience and knowledge to conduct their tasks in accordance with best practices and in an environmentally responsible manner. All staff and contractors which become involved in the mine will also undergo the relevant environmental awareness training required for them to proceed with their tasks without infringing on the accepted environmental management plan and integrated water and waste management plan.

The management of the mine will fall under the ambit of the General Manager, assisted by the Mine Manager, and the SHEQ Manager.

The financial provision for the project has been conducted as part of the NEMA process and submitted to the Department of Mineral Resources (DMR), and the necessary guarantees for rehabilitation secured.

Uitkomst Colliery also has access to environmental and engineering consultants and various specialists to assist where required.

5.6 EDUCATION & TRAINING

One of the responsibilities of the SHEQ is to adopt a Safety, Health, Environment and Quality awareness and training procedure that includes all employees.

Training will also address the specific measures and actions as listed in the EMP and IWWMP.

5.6.1 Training Needs

A training needs analysis is performed through all levels of the organization including those within the administration, plant and mining worker sectors. Each of the categories / levels of the organization have different responsibilities and roles, accordingly different knowledge requirements are applicable. These are summarised in the Table 23. After the training needs have been identified, it is the responsibility of the SHEQ Manager to ensure that personnel attend the relevant identified training.

5.6.2 Specialised Skills

The Training Department in conjunction with the SHE Manager are responsible for ensuring job specific training for personnel performing tasks, which can cause significant environmental and social impacts (e.g. receipt of bulk hazardous chemicals/fuel, hazardous materials handling, responding to emergency situations etc.). The Mine Manager with the assistance of the SHE Manager must identify relevant personnel and training courses.

5.6.3 Review of Training Material

Effectiveness of the environmental management training will be done by the management through task observations and during internal and external audits. All training material for presentation to personnel and contractors will be reviewed annually to ensure consistency with organisational requirements and best practice guidelines. In addition to this, annual monitoring reports, audit results and all incident reports will be reviewed; any short comings

88 | P a g e

UITKOMST COLLIERY: IWWMP and non-compliancy will be highlighted and management measures incorporated or improved upon within the training material.

5.6.4 Records

Records from the implementation of this environmental awareness training will be kept and controlled in accordance with the SHEQ Management System Control of Records Procedure, which is required to be implemented so as to provide evidence of conformity and effective operation of the relevant requirements of the SHEQ management system.

89 | P a g e

Table 23: Environmental Awareness Training Requirements

Occupation Environmental Required Knowledge And Input: Training Required: Interval: Category Management Responsibility / Role:

Senior Managing the Social Understanding the purpose of the SEAMS and SHE Management System General in-house, Once off Management & Environmental Knowledge of the significant impacts as described in the EIA/EMP during management training including Assessment & the construction and operational phases Process Management System Knowledge of the commitments made in the EMP relevant to the Managers and (SEAMS), and the construction and operational phases Head of Safety, Health & Department Environmental (SHE) Setting and reviewing the mine’s Environmental objectives Management System Directing the SEAMS and SHE management system, and monitoring their progress

Accessing the legal register and searching for details Training on the legal Once off Emergency preparedness and response register

Environmental Managing the SEAMS Understanding the purpose of the SEAMS and SHE Management System General in-house, Once off Management and the SHE Knowledge of the significant impacts as described in the EIA/EMP during management training Representative, Management System the construction and operational phases SHE Officer & Monitoring and Knowledge of the commitments made in the EMP relevant to the Internal Auditor auditing construction and operational phases Directing the SEAMS and SHE management system, and monitoring their progress

Current knowledge of South African regulatory requirements, best Training on the legal Once off practice guidelines and applicable legislation register

Emergency preparedness and response Meetings and Talk Topics Continuous Knowledge in spill management, stockpile management, discard management, water management and waste management Knowledge of the relevant Operational procedures, Emergency Response Plans and Incident reporting

Knowledge of the SABS standards and other relevant legislation Training on the SABS Annual regarding the correct storage of chemicals standards and other legislation

Knowledge of auditing techniques and report writing Auditor training Annual

90 | P a g e

Occupation Environmental Required Knowledge And Input: Training Required: Interval: Category Management Responsibility / Role:

Section Implementation and Understanding the purpose of the SEAMS and SHE Management System General in-house, Once off Managers & daily management of Knowledge of the relevant department’s significant impacts as management training Section the SEAMS and the described in the EIA/EMP during the construction and operational phases Engineers SHE Management Actively implementing actions to achieve SEAMS Management Plans System and Environmental Objectives.

Knowledge in stockpile management, discard management, water Meetings and talk topics Continuous management and waste management Knowledge of the relevant Operational procedures, Emergency Response Plans and Incident reporting Knowledge in the correct storage of chemicals

Engineering Implementation and Understanding the purpose of the SEAMS and SHE Management System General in-house, Once off HOD & General daily management of Knowledge of the relevant department’s significant impacts as management training Engineering the SEAMS and the described in the EIA/EMP during the construction and operational phases Supervisor SHE Management Actively implementing actions to achieve SEAMS Management Plans System and Environmental Objectives.

Knowledge in spill management and waste management Meetings and talk topics Continuous Knowledge of the relevant Operational procedures, Emergency Response Plans and Incident reporting Knowledge in the correct storage of chemicals

Mine Captain Implementation and Understanding the purpose of the SEAMS and SHE Management System General in-house, Once off & General daily management of Knowledge of the relevant department’s significant impacts as management training Engineering the SEAMS and the described in the EIA/EMP during the construction and operational phases Supervisors SHE Management Actively implementing actions to achieve SEAMS Management Plans System and Environmental Objectives.

Knowledge in spill management and waste management Meetings and talk topics Continuous Knowledge of the relevant Operational procedures, Emergency Response Plans and Incident reporting Knowledge in the correct storage and handling of chemicals Understanding the requirements for not polluting the environment

91 | P a g e

Occupation Environmental Required Knowledge And Input: Training Required: Interval: Category Management Responsibility / Role:

Supervisors, General Understanding the purpose of the SEAMS and SHE Management System General in-house, Once off Shift Boss & Environmental Knowledge of the relevant department’s significant impacts as management training Forman Awareness and job described in the EIA/EMP during the construction and operational phases specific impacts Knowledge of the relevant Operational procedures, Emergency Response Plans and Incident reporting Knowledge in spill management and waste management Understanding the requirements for not polluting the environment

Operators, General General Awareness of aim and purpose of the SEAMS and SHE Environmental Annual tradespersons Environmental Management System Awareness Training & Floor Awareness and job Understanding the SEAMS Management Plan relevant to their operations Employees specific impacts Understanding the requirements for not polluting the environment General understanding of the relevant Operational procedures, Emergency Response Plans and Incident reporting

General General General Awareness of aim and purpose of the SEAMS and SHE Environmental Annual Administration Environmental Management System Awareness Training Staff Awareness and job Understanding the SEAMS Management Plan relevant to their operations specific impacts Understanding the requirements for not polluting the environment General understanding of the relevant Operational procedures, Emergency Response Plans and Incident reporting

Security General General Awareness of aim and purpose of the SEAMS and SHE Environmental Annual Environmental Management System Awareness Training Awareness and job Understanding the requirements for not polluting the environment specific impacts

92 | P a g e

UITKOMST COLLIERY: IWWMP

5.7 INTERNAL & EXTERNAL COMMUNICATION

The SHEQ Manager will be responsible for overall implementation of the IWWMP and EMP. All issues relating to the environment will be either directly inspected by the SHEQ Manager or appointed individual. The Mine Manager will be trained in the necessary environmental aspects pertaining to the EMP and IWWMP and will be in direct daily contact with the SHEQ Manager regarding any monitoring and inspections.

At least biennial (every two years) meetings with I&APs. Uitkomst Colliery will also establish a complaints registers at the Security Office where I&APs can lodge their complaints directly. These registers will be checked by SHEQ Manager daily and issues attended to as soon as possible. The register will indicate the I&AP’s details, his complaints, signature of the site/environmental officer who read the issue, date of attending to the issue and manner in which the issue was addressed.

5.8 AWARENESS TRAINING

Through the on-site environmental training, I&AP communication and liaison between communities, a general awareness will be created between all parties. As part of environmental awareness, meetings will be scheduled with various staff at appropriate time intervals (usually weekly) to discuss any general issues or allow for transfer of information. This can also be conducted by means of posters communicating major issues identified on site placed at gathering points in various appropriate languages.

5.9 MONITORING & CONTROL

5.9.1 Surface water Monitoring

 The surface water quality will be monitored on a monthly basis.  The existing monitoring programme must be updated to include the points indicated in Plan 20.  The following chemical parameters are recommended for the analysis (any additional elements included in the IWUL will also be included): o Total Dissolved Solids / Electrical Conductivity; pH; Alkalinity; Carbonates; Magnesium; Calcium; Sodium; Potassium; Sulphate; Chloride; Fluoride; Iron; Manganese; and Aluminium.  All samples will be submitted to an accredited laboratory for analysis.  Quarterly and annual reports will be compiled and submitted to the mine management and to DWS.

93 | P a g e

Plan 20: Proposed Surface water monitoring programme

94 | P a g e

UITKOMST COLLIERY: IWWMP

5.9.2 Groundwater Monitoring

 The existing groundwater monitoring programme must be updated to include: o Hydrocensus points around the mine areas: BH1, BH2, BH3, BH4, BH5, BH6, BH11, BH12, Fountain, Landman, Community, DeJager, New BH3, Klip1 and Klip2  The groundwater quality will be monitored on a quarterly basis, at which time the levels will also be dipped.  All monitoring boreholes must be demarcated and protected to prevent damage or tampering.  The following chemical parameters are recommended for the analysis (any additional elements included in the IWUL will also be included): o Total Dissolved Solids / Electrical Conductivity; pH level; Alkalinity; Carbonates; Magnesium; Calcium; Sodium; Potassium; Sulphate; Chloride; Fluoride; Iron; Manganese; and Aluminium.  All samples will be submitted to an accredited laboratory for analysis.  Reports will be submitted to DWS quarterly and annually.  The groundwater model will be updated every two years and the monitoring programme will be reviewed after this period and amended as necessary. Any changes will be submitted to DWS.

Plan 21: Proposed Groundwater Monitoring Programme

95 | P a g e

UITKOMST COLLIERY: IWWMP

5.9.3 Biomonitoring

Biomonitoring is currently undertaken as per the requirements of the approved water use license. With the inclusion of the Klipspruit reserves it is recommended that the biomonitoring programme be updated as follows:

Plan 22: Proposed biomonitoring points (KLB3 and KLB4 may be excluded if sites are not appropriate for biomonitoring and may be replaced with other sites)

Note: Sites KLB3 and KLB4 must be revisited to determine their appropriateness to include in the overall biomonitoring programme.

The following stressor, habitat and response indicators will be evaluated and will be included in the biomonitoring report:

 In situ water quality assessment and determination of water quality variables of concern, where available.  Identification of prevailing existing impacts.  Habitat assessment, utilizing the Invertebrate Habitat Assessment Systems (IHAS).  Macro invertebrate assessment, including the generation of reference conditions and determination of Present Ecological State utilizing the South African Scoring System Version 5 (SASS5) and the Macro-Invertebrate Response Assessment Index (MIRAI).  Diatom assessment at sites KLB2, KLB6 and KLB7.

96 | P a g e

UITKOMST COLLIERY: IWWMP

5.9.4 Waste Monitoring

 The dirty water dams and associated dirty water management features must be regularly (weekly) inspected to ensure these are functioning optimally. Signs of erosion, spillages, and leaks will be investigated and repaired if observed. The capacities and freeboard will be maintained in all dams. Silt build-up and any obstructions will be cleared from dams, silt traps and diversion channels/trenches. Deposition cleared from dirty water infrastructure will be disposed of onto the MRDS.  The Mine Manager and SHEQ Manager will inspect the MRDS facility at least weekly to ensure activities are being undertaken in line with standard operating procedures and engineered designs and plans.  The SHEQ Manager will inspect the conservancy tank areas and portable toilet facilities at least weekly to ensure that no sewage leaks / spills are occurring and ensure sites are clean. The SHEQ Manager will also ensure that these are emptied / serviced by a reputable contractor on a regular basis. Records of all sewage removal will be kept in a detailed waste manifest register and waste certificates will be obtained from the disposal contractor.  The SHEQ Manager will inspect areas at least monthly for illegally dumped waste and will ensure domestic waste bins/skips are ideally placed and ensure that all contractors and staff collect waste and dispose of waste into these skips or bins.  The SHEQ Manager will inspect the bunded areas and associated oil traps weekly and after rainfalls to ensure taps are closed, oil traps are not over-flowing and bunded areas are not flooded.

5.9.5 Supplementary Monitoring Systems

As sedimentation can result in impacts to surface water bodies and wetlands, soil management principals must be applied on site. Furthermore, some alien invasive species are known to have detrimental effects on water resources and stream characteristics. Therefore the following monitoring is recommended and considered part of water management.

 Any rehabilitated areas, such as the sides of the MRDS facility, and soil stockpiles will be monitored for soil quality and depth on an annual basis and recommendations made by the specialist pedologist, including the fertilization requirements, will be implemented on site.  Surface area of underground mining areas will be monitored for any potential subsidence which will be rehabilitated if noted.  The site will be monitored for alien invasive species on a 6 monthly basis (more frequently for herbaceous species) and an ecologically sensitive alien invasive eradication programme will be implemented on site.  Any rehabilitated areas and soil berms and stockpiles will be surveyed visually for erosion vegetation cover on a monthly basis and any areas of failed germination or poor vegetation cover will be re-assessed and re-seeded. Consideration will be given to hand planting of seedling plugs if germination continues to be low in an area. Erosion control measures, such as gabions, will be implemented on persistently eroded areas or where erosion is severe.

97 | P a g e

UITKOMST COLLIERY: IWWMP

5.10 RISK ASSESSMENT

A summary risk assessment is included below in Table 24. Please refer to the geohydrological and wetland studies attached as appendices for detailed impact assessment for the operations.

The methodology used to assess the risks/impacts associated with the project is as follows:

The methodology used by Cabanga Concepts is as follows:

The status of the impact

Status Description

Positive: a benefit to the holistic environment

Negative: a cost to the holistic environment

Neutral: no cost or benefit

The duration of the impact

Score Duration Description 1 Short term Less than 2 years 2 Short to medium term 2 – 5 years 3 Medium term 6 – 25 years 4 Long term 26 – 45 years 5 Permanent 46 years or more The extent of the impact

Score Extent Description

1 Site specific Within the site boundary

2 Local Affects immediate surrounding areas

3 Regional Extends substantially beyond the site boundary

4 Provincial Extends to almost entire province or larger region

5 National Affects country or possibly world

The reversibility of the impact

Score Reversibility Description

1 Completely reversible Reverses with minimal rehabilitation & negligible residual affects

3 Reversible Requires mitigation and rehabilitation to ensure reversibility

5 Irreversible Cannot be rehabilitated completely/rehabilitation not viable

The affect (severe or beneficial) of the impact

Score Severe/beneficial effect Description

1 Slight Little effect - negligible disturbance/benefit

2 Slight to moderate Effects observable - environmental impacts reversible with time

98 | P a g e

UITKOMST COLLIERY: IWWMP

3 Moderate Effects observable - impacts reversible with rehabilitation

4 Moderate to high Extensive effects - irreversible alteration to the environment

5 High Extensive permanent effects with irreversible alteration

The probability of the impact

Score Rating Description

1 Unlikely Less than 15% sure of an impact occurring

2 Possible Between 15% and 40% sure of an impact occurring

3 Probable Between 40% and 60% sure that the impact will occur

4 Highly Probable Between 60% and 85% sure that the impact will occur

5 Definite Over 85% sure that the impact will occur

The Consequence = Severity + Spatial Scale + Duration + Reversibility.

The Significance = Consequence x Probability.

The Significance rating is described as follows:

Score out of 100 Significance

1 to 20 Low

21 to 40 Moderate to Low

41 to 60 Moderate

61 to 80 Moderate to high

81 to 100 High

99 | P a g e

Table 24: Risk / Impact Assessment Summary

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post Aspect: Topography and associated drainage characteristics

Alteration in Uitkomst upgrade. Neg 3 1 3 3 10 5 50 Soil berm placement should consider remediation of 1 1 3 3 8 5 40 topographical Klipspruit construction. other impacts, such as utilising berms to divert clean nature. Operation & storm water runoff or shielding visual impacts where decommissioning possible. Utilise existing roads where possible. Rehabilitate all disturbed areas when they are no longer needed, including contouring areas properly to ensure no pooling of water on site. Demarcate the activity area as small as possible and maintain all activities within designated areas. Maintain topsoil berms at no more than 2m, subsoil stockpiles at no more than 6m and overburden stockpiles at no more than 10m.

Subsidence will alter Operation; Neg 2 1 3 3 9 1 9 Rehabilitate any surface subsidence noted over areas 1 1 3 3 8 1 8 surface decommissioning & of underground mining by filling and levelling areas. topographical closure Complete pre-mining topographical surveys to aid in nature of the area monitoring for potential subsidence.

Coal stockpiles have Uitkomst upgrade. Neg 2 1 1 1 5 5 25 Demarcate stockpile areas and strip soil from these 1 1 1 1 4 4 16 and will continue to Operation & areas and compact and line base as per engineered alter the decommissioning designs. topographical Stockpile heights must not exceed 3m for coal nature of the site. stockpiles. Move coal stockpiles on a first-in-first-out basis to reduce extent of coal stockpile areas. Coal stockpile and handling must be in designated areas only.

Extension of the Uitkomst upgrade. Neg 1 1 3 1 6 5 30 Strictly apply engineered designs and standard 1 1 3 1 6 5 30 dump will result in Operation operating procedures to mine residue handling and additional disposal and the upgrade of the co-disposal facility. topographical impact.

Eradication of voids Decommissioning & Pos 3 1 5 1 10 5 50 Treatment options for decant and contamination plume 3 1 5 1 10 5 50 & stockpiles during closure. Rehabilitate will be finalised if required and may require retaining rehabilitation phase. any areas no longer dams on site to contain and treat decant. Replacement of needed during Rehabilitate all disturbed areas and complete shaping material and operations. and capping of the MRDS facility. Topsoil and vegetate profiling. all areas.

100 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post Aspect: Soil and associated land capability (Focussing on erosion impacts which could lead to sedimentation of downstream environment)

Erosion and loss of Uitkomst upgrade. Neg 3 1 2 3 9 5 45 Utilise existing roads where possible and implement 2 1 2 3 8 5 40 topsoil Klipspruit construction. adequate drainage and erosion control on new roads. Operation & As far as possible, plan soil stripping activities in the dry decommissioning season. Demarcate the activity area as small as possible and maintain all activities within designated areas. Divert storm water runoff away from areas with high erosion potential. Incorporate measures to reduce the flow velocity of storm water runoff, specifically over compacted areas and roads. Incorporate erosion control measures where erosion is severe or persistent. Demarcate stockpile areas and strip the topsoil from stockpile areas. Topsoil stockpiled as perimeter berms must not exceed 2 m. Subsoil stockpiles must not exceed 6 m in height. All stockpiles must have an outer slope of approximately 1 V: 3 H (to limit the potential for erosion of the outer pile face). Construct top and toe perimeter berms on topsoil and subsoil stockpiles. Seed all stockpiles - Seeding must be completed within seven (7) days of stockpiling.

Soil replacement Decommissioning and Pos 4 1 3 1 9 5 45 Rehabilitation must be on-going at the MRDS facility. 4 1 3 1 9 5 45 and amelioration into early closure. The utilizable soil (150 mm) removed during the during rehabilitation. Rehabilitate any construction phases shall be redistributed in a manner areas no longer that achieves an approximate uniform stable thickness needed during consistent with the approved post-mining land use operations. (grazing), and will attain a free draining surface profile. Fertilization and amelioration of rehabilitated areas will be undertaken as per soil fertility assessments. Seedbed preparation must be undertaken using agricultural equipment. Seeding must be undertaken in accordance with a vegetation specialist’s recommendations. Restriction of vehicle movement over rehabilitated areas and do not allow any grazing for the first two years. Rehabilitation model and plan must be implemented and take into account topographical surveys.

101 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post

Aspect: Surface Water

Increased runoff and Uitkomst upgrade. Neg 4 2 3 3 12 4 48 Apply soil management measures as stipulated above. 2 2 2 3 9 2 18 associated potential Klipspruit construction. Rehabilitate all disturbed areas as soon as they are no silt-loading and Operation & longer required. contamination of decommissioning Revegetate all bare soils. downstream water Establish storm water control measures before any other bodies and activities commence to ensure clean and dirty water associated separation and dirty water containment. This must be in wetlands. line with the engineered designs. This will include upslope berms to divert clean water around the site of activity into natural drainage lines and downstream (and internal as needed) channels to drain dirty water from the active footprint to suitably designed, containment dams. Dirt y water dams and trenches to be constructed and lined as per the engineering designs. Road surfaces must be compacted in order to increase stability. Sheet runoff from cleared areas, paved surfaces and access roads needs to be curtailed by installing flow dissipaters where rapid flow of diverted clean storm water runoff occurs as necessary. Install silt traps / flow dissipaters if necessary to trap silt in highly silt-laden runoff. 100m buffer zones / 1:100 year flood lines will be demarcated as no-go areas until authorisations under NWA have been obtained where necessary.

Downstream water Uitkomst upgrade. Neg 1 2 3 1 7 5 35 Necessary measure to contain dirty water runoff in line 1 2 3 1 7 5 35 quantity of Operation & with NWA's GN704. catchment reduced. decommissioning

102 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post Contamination of Uitkomst upgrade. Neg 3 2 3 3 11 4 44 Inspect, maintain and repair all water management 2 1 2 3 8 2 16 surface water Klipspruit construction. features. features as result of Operation & Follow emergency response plan for spills and ensure mine water spills or decommissioning quick access to sandbags for emergency spills. irresponsible Keep back-up pumps and pipes on site. handling of coal or Coal spillages must be regularly cleared and replaced coal spillages. to designated areas. Ensure water separation and dirty water containment on site as per GN704 requirements, constructed in line with engineered designs. Ensure all dirty water containment facilities are adequately sized, designed and constructed. All dams will be constructed and lined as per designs and managed with a 0.8m freeboard. All pollution control facilities must be managed in such a way as to ensure that storage and surge capacity is available if a rainfall event occurs. Coal stockpile and handling must be in designated dirty water areas with appropriate base and must form part of the dirty water footprint. Trucks must not be overloaded and should be covered with tarpaulin.

Containment of Uitkomst upgrade. Pos 5 2 3 1 11 4 44 None. 5 2 3 1 11 4 44 contaminated Klipspruit construction. water. Operation & decommissioning

Potential Operation Neg 4 2 3 3 12 3 36 Oil from oil traps will be removed to used hydrocarbon 2 1 3 3 9 2 18 contamination of drums for removal from site by a reputable hydrocarbon soils with waste contractor. indiscriminate use of Spill kits must be available on site and personnel trained materials on site. to utilise these to clear spills. All vehicles / machinery on site will be up-to-date with their service and maintenance plans. The use of persistently leaky equipment will be discontinued until repairs are made. Equipment will not be parked over bare ground; where unavoidable, drip trays will be placed under the equipment to collect potential leaks. Ensure action and emergency response plans are in place for all hydrocarbon spills. Bunding / concrete flooring or enclosed containers and oil traps must be constructed in areas for hydrocarbon storage and transfer and in workshop areas where diesel-driven equipment is serviced. Bunds in workshop and washbays will drain to an oil trap. No chemicals will be stored in areas exposed to rain and wind. Chemicals will be stored as per requirements of the MSDS.

103 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post Wet and dry chemicals, reducing and oxidising agents, will be stored separately. Wet chemicals will be stored over drip trays. Cement will be stored under cover and will be handled over protective sheeting.

Generation of coal Operation Neg 5 2 3 3 13 4 52 Coal spillages and coal in non-designated areas must 2 1 3 1 7 2 14 dust could be cleared and removed to coal stockpile areas. contaminate water Coal stockpile and handling must be in designated bodies in areas with compacted base and must form part of the neighbouring areas. dirty water footprint. Manage dust through water carts or sprinklers. Trucks must not be overloaded and must be covered with tarpaulin.

Irresponsible use of Operation Neg 4 3 3 1 11 3 33 Inspection of ALL water features for leaks and 2 2 1 1 6 3 18 water and water immediate repair wastage. Saving water initiatives will be included in environmental awareness training. Utilise water on site responsibly. Record all water usage on site.

Potential Operation; Neg 5 2 3 1 11 4 44 Upgrade the Uitkomst facility as per engineered designs 3 2 2 1 8 3 24 contamination of decommissioning & and operate and maintain the MRDS facility as per downstream water closure standard operating procedures, including adequate and wetlands. base drainage to prevent seepage to groundwater and surface runoff management and containment to prevent contaminated runoff to downstream environment. Inspect and repair the MRDS facility and associated water management features regularly. Discard from the plant will be transported to the MRDS facility for disposal. Slurry will be pumped to the MRDS facility directly from the plant and back-up pumps and pipelines will be available on site to replace any malfunctioning equipment. MRDS facility will be managed as a dirty water area, as will all slurry pipelines. Pipelines should be designed to allow for easy shut off and replacement should pipelines

104 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post spill and should be within the dirty water management area. On rehabilitation the MRDS facility will receive final coaly materials cleared from surfaces which will be compacted on surface; the dump will be shaped, capped and revegetated. The RWD will remain in place to contain runoff and seepage. RWD will be upgraded in line with engineered designs and operated with 0.8m freeboard.

Potential for sewage Operation Neg 2 2 2 1 7 4 28 Inspect and repair all aspects of the potable water and 1 2 1 1 5 2 10 spills sewage reticulation as needed, including any plumbing associated with the bathrooms and toilets. Ensure registered contractor is utilised for removal of sewage from site and obtain disposal certificates from contractor to ensure cradle-to-grave management of sewage. . Commence and maintain a waste manifest on site and include records on sewage disposal. Occasional bacterial assessment of potable water.

Potential Operation Neg 3 1 2 1 7 4 28 Inspect and clear all litter and waste. 2 1 2 1 6 2 12 contamination of Commence and maintain a waste manifest on site and surface water with include records on sewage disposal. indiscriminately Waste should be recycled as far as possible and dumped waste. sold/given to interested contractors. Waste will be stored according to the Norms and Standards for Storage of Waste. Recyclable waste should not be stored for excessive periods. Refuse bins will be placed around site to collect waste for separation, recycling and disposal.

Free drainage Decommissioning and Pos 4 1 5 1 11 4 44 Rehabilitation must be on-going. 4 1 3 1 9 4 36 restored to area. into early closure. The utilizable soil (150 mm) removed during the Poor drainage if Rehabilitate any construction phases shall be redistributed in a manner area is not areas no longer that achieves an approximate uniform stable thickness adequately needed during consistent with the approved post-mining land use rehabilitated. operations. (grazing), and will attain a free draining surface profile. Fertilization and amelioration of rehabilitated areas will be undertaken as per soil fertility assessments. Seedbed preparation must be undertaken using agricultural equipment. Seeding must be undertaken in accordance with a vegetation specialist’s recommendations. Restriction of vehicle movement over rehabilitated areas and do not allow any grazing for the first two years.

105 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post Rehabilitation model and plan must be implemented and take into account topographical surveys.

Aspect: Groundwater

Impacts on Operation Neg 3 2 2 3 10 5 50 Monitor groundwater levels. 2 1 2 3 8 5 40 groundwater Monitor for surface subsidence. Rehabilitate and surface quantity due to subsidence noted over areas of underground mining by dewatering. filling and levelling areas. Seal off individual high yielding inflow zones intercepted during mining.

Impacts on surface Operation Neg 2 2 5 5 14 5 70 Monitor groundwater levels. water and wetlands Monitor stream flow volumes. due to active Implement appropriate safety factors. dewatering.

Impacts on surface Operation; Neg 1 2 2 5 10 5 50 Upgrade the Uitkomst facility as per engineered designs 1 1 2 5 9 3 27 quality due to poor decommissioning & and operate and maintain the MRDS facility as per quality seepage closure standard operating procedures, including adequate from pollution source base drainage to prevent seepage to groundwater and areas. surface runoff management and containment to prevent contaminated runoff to downstream environment. Inspect and repair the MRDS facility and associated water management features regularly. Discard from the plant will be transported to the MRDS facility for disposal. Slurry will be pumped to the MRDS facility directly from the plant and back-up pumps and pipelines will be available on site to replace any malfunctioning equipment. MRDS facility will be managed as a dirty water area, as will all slurry pipelines. Pipelines should be designed to allow for easy shut off and replacement should pipelines spill and should be within the dirty water management area. On rehabilitation the MRDS facility will receive final coaly materials cleared from surfaces which will be compacted on surface; the dump will be shaped, capped and revegetated. The RWD will remain in place to contain runoff and seepage. RWD will be upgraded in line with engineered designs and operated with 0.8m freeboard.

106 | P a g e

Applicable Mine

Impact Mitigation

Phase

mitigation)

mitigation) -

-

STATUS Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (pre Magnitude Extent Duration Reversibility CONSEQUENCE PROBABILITY SIGNIFICANCE (post Impacts on Operation; Neg 2 1 5 5 13 5 65 Upgrade the Uitkomst facility as per engineered designs 2 1 5 5 13 4 52 groundwater quality decommissioning & and operate and maintain the MRDS facility as per due to poor quality closure standard operating procedures, including adequate seepage from the base drainage to prevent seepage to groundwater and mining area. surface runoff management and containment to prevent contaminated runoff to downstream environment. Inspect and repair the MRDS facility and associated water management features regularly. Discard from the plant will be transported to the MRDS facility for disposal. Slurry will be pumped to the MRDS facility directly from the plant and back-up pumps and pipelines will be available on site to replace any malfunctioning equipment. MRDS facility will be managed as a dirty water area, as will all slurry pipelines. Pipelines should be designed to allow for easy shut off and replacement should pipelines spill and should be within the dirty water management area. On rehabilitation the MRDS facility will receive final coaly materials cleared from surfaces which will be compacted on surface; the dump will be shaped, capped and revegetated. The RWD will remain in place to contain runoff and seepage. RWD will be upgraded in line with engineered designs and operated with 0.8m freeboard.

Recovery of Decommissioning, Pos 4 3 5 3 15 5 75 No remediation necessary - positive impact groundwater level Closure after dewatering has stopped

107 | P a g e

UITKOMST COLLIERY: IWWMP

5.11 ISSUES & RESPONSES FROM PUBLIC CONSULTATION PROCESS

A public participation process (PPP) was undertaken between December 2015 and February 2016 for the IWULA process. During this process advertisements were placed in the local newspapers; posters were erected on and around site; and background information documents were circulated to surrounding landowners and users. Please refer to APPENDIX 9 for proof of public participation.

The table below summarises the issues and responses from the process.

108 | P a g e

Table 25: Issues & Response Summary

Interested and Affected Issue raised & Date Received EAPs response to issues the applicant Parties List the names of persons consulted in this column, and Mark with an X where those who must be consulted were in fact consulted.

Johan Landman – 02-12- Is not necessarily happy with Uitkomst Mine and is Noted. Specialist will contact Mr Landman prior to site Vaalbank Trust 2015 concerned about water loss and quality in the visits. Numerous specialist studies will be undertaken to future. Asked that the specialist please contact assess possible water quality decreases and loss. Vaalbank Ptn 1, 4 & 5 him prior to arriving on site. Klipspruit Ptn 4, 5 & 16

Willem van Rensburg - 03-12- Please can the specialists contact him prior to Noted, specialists will contact Mr van Rensburg prior to Jericho 400 Ptn RE 2015 arriving at site? site visits.

Johan de Beer – 03-12- Wants to know if the mine will be mining under his It is unclear at this stage, this farm was included in the Rusverwacht 151 Ptn 12 & 14 2015 farm. mining right, however the mine wishes to progress towards the old Klipspruit area, which is away from his

farm.

Conrad Cloete – 03-12- Please can the specialists contact him prior to Noted, specialists will contact Mr Cloete prior to site Altemooi Plaas 2015 arriving at site? visits. Rusverwacht 151 Ptn 11

Nick de Jager – 04-12- Is not necessarily happy with mining and the Noted. Numerous specialist studies will be undertaken Rusverwacht Trust 2015 impacts on groundwater. The specialists must to assess possible water quality decreases and loss. phone and come and see him prior to arriving on Specialists will contact Mr Cloete, the farm manager, Rusverwacht Ptn 1, 2, 4, 5, 6, site. prior to site visits. 7, 8, 9, 13 & 15 The mine has since come to an agreement with him. Jericho A Ptn 1, 3, 5 & 6 Jericho Ptn 2 & 3

James Alexander de Jager – 30-12- Is concerned that the mine will affect his water. The mine is undertaking numerous specialist studies Rusverwacht 151 Ptn 6 2015 He stated that his water is already being including ground and surface water. This will be affected. assessed as part of the process.

109 | P a g e

Interested and Affected Issue raised & Date Received EAPs response to issues the applicant Parties List the names of persons consulted in this column, and Mark with an X where those who must be consulted were in fact consulted.

Kobus Schoeman – 02-12- He is leasing land on Vaalbank from Mr Landman, Cabanga will assist in sending him some contact Kalk Krans 313 Ptn 1 2015 wants to lease some of the mine land. Please can details. we put him in contact with someone?

Fanie van Schalkwyk – 03-12- He is managing all of the Saidy Farming farms; Noted, specialists will contact Mr van Schalkwyk prior to Saidy Farming 2015 please can the specialist contact him prior to site visits. arriving at site. Uitkomst 95 Ptn 1, 2 & 4 Kweekspruit 22 Ptn 1

Andre Smit – 04-12- Has no concern with the mine. Is worried about The relevant contact details for authorities at Water Wasbank 149 Ptn 1, 8 & 17 2015 the two dams that have recently been built by Affairs will be forwarded to Mr Smit. This information surrounding farmers. This is going to have must be forwarded to DWS and they will investigate if detrimental effects on the water downstream. If necessary. there is a flood, these dams will break and will cause massive problems. Any assistance with the matter is appreciated.

December Nkosi – 02-12- Wants the mine to come and prospect his farm. Noted. The mine will be informed. Explained that the Uitkomst 95 Ptn 3 2015 mine would need a prospecting right which would take a long time to obtain. Zandspruit 2 Ptn 2

Nelisiwe Ndlozi – 02-12- Wants a job with the mine. It is unclear at this stage if jobs will be available, Uitkomst 95 Ptn 4 2015 however all CV’s can be forwarded to Cabanga for consideration.

Baron Brummer – 02-12- Works for Mr Landman who owns the farm, he Mr Landman was contacted and has been informed. Vaalbank 103 Ptn 1 & 2 2015 must be contacted.

Lindiwe Nkosi – 02-12- The land is state owned, they have no water, and Noted. Rural Development has been informed. Watervaal 157 Ptn 2 2015 can the mine please speak to Cllr Gama to assist.

110 | P a g e

Interested and Affected Issue raised & Date Received EAPs response to issues the applicant Parties List the names of persons consulted in this column, and Mark with an X where those who must be consulted were in fact consulted. No other concerns.

George Viviers – 03-12- No concerns. Complained about other farmers in Noted. Kweekspruit 22 Ptn 4 & 5 2015 the area building dams which will restrict water downstream. Wasbank 149 Ptn 4 & 7

Mrs Jonker – 11-01- Stated that her farm (Waterval Ptn 18) was Noted. This has been corrected. Waterval 157 Ptn 18 2016 incorrectly ladled in the BID as state owned land and it needs to be corrected. This farm is owned by a trust (Waterval Trust).

Cllr M.A Gama – 02-12- Wants to know if a meeting with the mine can be Cabanga will assist in arranging a meeting. Ward 4 Utrecht Municipality 2015 arranged to discuss old outstanding issues.

Thembisile Mudau – 02-12- When will the mine start? Will there be any jobs? It is unclear at this stage if jobs will be available as it is Engodini Community 2015 Must consult with Cllr Gama, he will discuss likely that the mine will use the existing labour force, everything with the community. however all CV’s can be forwarded to Cabanga for Klipspruit 178 Ptn 6 & 18 consideration. Cllr Gama was contacted and has been informed.

Daniel Msibi – 03-12- No concerns. Please can the specialists contact Noted. Specialists will contact Mr Msibi prior to site visits. Chairman Qophumlando 2015 him prior to arriving at site? He is main point of Community Association contact as representative of community.

Andrew Batho – 07-12- Requested to be registered as an I&AP for the Mr Batho was registered and will be kept informed Afzelia Environmental 2015 project and be kept informed. throughout the process. Consultants

Vusi Patrick – 07-01- Is looking for employment with the mine. Requested that he send his CV so this can be Utrecht Resident 2016 forwarded to the mine for consideration.

111 | P a g e

UITKOMST COLLIERY: IWWMP

5.12 ASSESSMENT OF LEVEL OF CONFIDENCE OF INFORMATION

All specialist studies are conducted to certain levels of confidence, and in all instances known methodologies have been used and confidence levels are generally high. This means that in most cases the situation described in is accurate at high certainty levels, but there exists a low probability that some issues have not been identified during the studies. Such situations cannot be avoided simply due to the nature of field work and have therefore not been further discussed. Furthermore, statistical analyses and mathematical models are merely tools which assist the researcher in assessing field observations and have innate assumptions which can reduce objectivity of the results obtained. This is not seen as a major flaw but should always be considered when assessing results.

6. WATER & WASTE MANAGEMENT

6.1 WATER & WASTE MANAGEMENT PHILOSOPHY

Uitkomst Colliery’s philosophies can be summarised as follows:

 The attitude towards the mine project as a whole will be to: o Primarily pre-empt impacts and prevent the realisation of these impacts - PREVENTION. o To ensure that activities which are expected to impact on the environment are undertaken and controlled in such a way so as to minimise their impacts – MODIFY and/or CONTROL. Specific strategies include: . To ensure systems are in place for immediate and adequate treatment and/or rectification of any significant impacts that may occur due to the proposed activity – REMEDY. . To ensure the operation and rehabilitation is commenced and conducted in such a way so as to have minimal impact on the water resources and ensure post closure objectives are considered right from the onset to ensure these are attained at closure.  Additional philosophies relating to storm water management on site will be to: o Prevent unnecessary decreases to the downstream water quantity and quality. o Prevent the clean storm water runoff from upstream locations outside the activity footprint from entering the activity footprint. o Ensure that all dirty water within the footprint is contained within the area and no deliberate discharge of dirty water to the environment takes place.  Additional philosophies relating to process water management on site will be to: o Ensure that all dirty water within the footprint is contained within the area to reduce ensure maximum containment of mine water to reduce the need for make-up water. o On-site water is recycled as far as possible and prevents water wastage.  Additional philosophies relating to groundwater management on site will be to: o Prevent unnecessary water supply disruption to surrounding groundwater users. o Contain dirty groundwater that develops due to mining activities.

112 | P a g e

UITKOMST COLLIERY: IWWMP

o Contain and/or treat any potential plume or decant that may arise after mining.  Additional philosophies relating to waste and hazardous material management on site will be to: o Conduct hazardous material handling and storage in an environmentally conscious manner at all times on site. o Ensure a cradle-to-grave philosophy regarding any waste generated on site. o Create awareness of the creation, reuse and final disposal of waste and ensure all is conducted in an environmentally responsible manner. 6.2 STRATEGIES

Strategies that will be employed to ensure the above philosophies can be attained are discussed below. General strategies include:

 Prevent, modify, remedy, control and/or stop any action, activity or process which causes pollution or environmental degradation.  Prevent, contain and/or remedy the cause of pollution or degradation and migration of pollutants.  Comply with any prescribed legislation, management standards and/or practices.  Ensure responsible, thoughtful and well planned execution of activities on site.  Ensure that formal response procedures are in place for various potential environmental emergencies.  Good house-keeping practices.  Contain dirty water on site, and limit the dirty footprint to as small an area as possible.  Ensuring the storm water management plan is implemented on site prior to new activities taking place on site.  Recycling water on site as far as possible on site.  Recording water abstraction and dewatering and recycling water on site in order to reduce the need for abstraction of water from clean water resources for make-up water.  Disposing of waste responsibly.  Storing waste on site responsibly and for as short a duration as possible.  Recycling waste as far as possible.  Ensuring all contractors dispose of waste responsibly and that all certification for disposal of waste from the proposed mine is in obtained from the contractors.  Establish and maintain a waste manifest.  Implementing an adequate monitoring programme and schedule as detailed in this IWWMP to: o Ensure that mitigation and management measure are effective. o Allow quick detection of potential impacts/risks, which in turn will allow for quick response to issue/impacts. o Allow quick implementation of proposed action plans as set out in this IWWMP. o Reduce duration of any potential negative impacts.  Ensuring quick access to necessary specialists to assist with any environmental issues to ensure the best possible action can be taken speedily.  Ensure post closure objectives are considered right from the onset and throughout operations to ensure these are attained at closure.

113 | P a g e

UITKOMST COLLIERY: IWWMP

 Ensure strategies are in place to compensate for any water losses to registered water users. 6.3 PERFORMANCE OBJECTIVES & GOALS

6.3.1 Environmental Objectives and Goals

Environmental objectives are:

 Protect the biophysical environment as far as possible o Minimise impacts to the biophysical environment. o Ensure relevant legislation in terms of NEMA and Conservation of Agricultural Resources Act are applied on site including but not limited to alien invasive management and protection of ecologically sensitive species and environments.  Protect the water resources in the area. o Ensure clean and dirty water separation systems are established on site from the onset. o Use water responsibly and recycle water as much as possible. o Ensure relevant legislation regarding the NWA are applied on site.  Ensure atmospheric pollution is to a minimum: o Manage dust generation. o Ensure all pollutants are within levels stipulated in the National Air Quality Act. o Complete the NAEIS registration and continue annual reporting to the site as required.  Ensure an adequate rehabilitation plan is followed to allow for adequate rehabilitation to a prescribed land use which will be grazing. 6.3.2 Closure Objectives

The overall closure objectives are:

 To ensure that all impacts incurred during the operational phase are mitigated and that these are reduced over time, and that these mitigation measures are in line with best practices (existing at the time);  To minimise the impacts on the local community;  To ensure that as little poor quality water as possible decants from the mining areas;  To rehabilitate the areas as soon as possible;  To return the land to that of at least the pre-mining use which will be grazing land capability;  To ensure that residual impacts after closure of the mine are minimal; and  Apply for a closure certificate.

6.4 MEASURES TO ACHIEVE & SUSTAIN PERFORMANCE OBJECTIVES

Measures to achieve and sustain the abovementioned objectives are listed in Table 22 below, along with the responsible persons and timeframes for implementation.

Table 26: Measures to Achieve and Sustain Performance Objectives

Objective: Measure:

Protect the biophysical Place spill kits at all active areas

114 | P a g e

UITKOMST COLLIERY: IWWMP

Objective: Measure: environment as far as possible All activity areas will be properly demarcated and all activity will remain within the designated area.

Ensure emergency preparedness in terms of spills, water leaks and fires.

Protect natural water All sensitive areas (nearby wetlands and drainage areas) will be demarcated resources as no-go areas and no activity will take place within these areas until authorisation is obtained to do so.

Ensure all potentially contaminating materials (hydrocarbons, chemicals, cement, etc.) and all wastes are stored within designated areas and stored in terms of national standards and regulations.

Clean and dirty water Compile a detailed storm water management plan; delineate all clean and separation dirty water areas on the mine plan.

Construct and maintain clean water diversion berms and trenches in line with GN704. Construct and maintain dirty water collection trenches in line with GN704. Construct and maintain dirty water dams in line with GN704 requirements.

Ensure sufficient capacity in all water management facilities

Install flow dissipaters, silt traps and / or erosion control measures.

Ensure discard and slurry disposal is being conducted as per SOPs and engineered design for the MRDS.

Use water responsibly Update water balance annually and recycle water as Install flow meters on all abstraction points far as possible Record water usage volumes

Prevent erosion Install flow dissipaters, silt traps and / or erosion control measures.

Install and maintain top and toe perimeter berms on all soil stockpiles.

Legally compliant Colour code waste skips / bins according to waste type waste disposal Compile and implement a waste manifest

Ensure adequate Compile a mine rehabilitation and closure plan rehabilitation and Ensure soil samples are taken at rehabilitated areas to determine soil fertility return the land to grazing land capability.

Ensure that residual Update the geohydrological / groundwater study on a regular basis impacts after closure of the mine are minimal and appropriately managed, specifically poor quality decant.

Ensure legal Surface and ground water quality monitoring compliance (provincial Bio-monitoring & national legislation) Conduct Regular inspections & audits

115 | P a g e

UITKOMST COLLIERY: IWWMP

6.5 OPTION ANALYSES & MOTIVATION FOR IMPLEMENTATION OF PREFERRED OPTIONS

Uitkomst Colliery is an operational mine, as such alternatives were not considered.

6.6 IWWMP ACTION PLAN

The management strategy and monitoring plan in the IWWMP has been devised for each phase of mining. Where necessary some measures must continue on into the next phase. Also indicated in the monitoring and action plan is the frequency at which monitoring/inspection is to be conducted, and the person/individual responsible for ensuring these monitoring/inspection activities are properly carried out (either carry these out personally or delegate to another individual who will report back to the responsible person). Therefore the above management strategy and monitoring plan already addresses the short-term, medium-term and long-term actions that will need to be considered in the form of a management plan for the construction and upgrade phase (immediate to short-term action), operations (short to medium-term actions that must be implemented over the next 1-2 years), decommissioning and post closure (long-term actions) phases of mining. A very brief summary is provided below.

Immediate to Short-Term Actions:

Immediate actions necessary are related to environmental authorisations and other authorisations related to the mining activities. Regarding the environmental authorisations the following will be necessary:

 Ensure IWUL is amended/granted by DWS.  Ensure all the monitoring programmes are implemented immediately and conducted at stipulated frequencies for the life of mine.  Ensure all activities comply with GN704 unless relevant exemptions are granted by DWS.  Ensure the management measures and performance assessment is applied as per this document.  Ensure the monitoring programme as indicated in this document is applied.

Short-Term Actions:

 Ensure the relevant EMPr and IWUL audits are scheduled and carried out and submitted to the authorities.  Ensure the management measures and performance assessment is applied as per this document.  Ensure the monitoring programme as indicated in this document is applied.

Medium-Term Actions:

 Ensure the management measures and performance assessment is applied as per this document.  Ensure the monitoring programme as indicated in this document is applied.  Ensure the relevant compliance audits are carried out and submitted to the authorities.

116 | P a g e

UITKOMST COLLIERY: IWWMP

 Ensure that the preferred option for decant management is largely drafted.  Ensure the final rehabilitation plan is drafted.

Long-Term Actions

 Ensure the management measures and performance assessment is applied as per this document.  Ensure the monitoring programme as indicated in this document is applied.  Ensure the relevant compliance audits are carried out and submitted to the authorities.  Ensure closure applications are finalized and submitted.

6.7 CONTROL & MONITORING

The monitoring and audit reports discussed below will all be integral to the compilation of the annually updated IWWMP, which will essentially be composed of this IWWMP with updates to reflect any changes in activities on site, address any new management strategies that need to be incorporated as indicated through monitoring and audit reports and generally allow for the IWWMP to become a living document which can be updated with new technologies and new alternative management measures and best practices.

In addition, inspection and monitoring logs will be kept on site in terms of the general monitoring and inspection requirements indicated in Table 6. These logs must be made available to auditors and therefore be kept on site.

6.8 MONITORING OF CHANGE IN BASELINE

The baseline information has been reported for groundwater, surface water and aquatic Biomonitoring within the various license applications. The monitoring plan as elaborated within this IWWMP as well as the various EMP reports will continue and be upgraded when necessary. Monitoring data will be compared to the baseline data.

6.9 AUDIT & REPORT ON PERFORMANCE MEASURES

The monitoring plan has been established to determine if the performance objectives are being met through the implementation of the management strategies. Water quality and bio-monitoring reports will be compiled annually for submission to DWS. These reports will relate findings and trends related to the latest monitoring data in relation to past monitoring findings. If monitoring activities suggest that issues on site exist, then these monitoring reports should further identify the source and make recommendations to update management strategies in order to rectify or reduce these impacts.

An internal audit should be carried out by the person responsible for the implementation of the IWWMP to ensure that the general monitoring and inspection activities as indicated in Table 6 are adhered to and that appropriate and immediate action is taken to address any issues observed. This general monitoring plan will also assist in ensuring that the environmental

117 | P a g e

UITKOMST COLLIERY: IWWMP performance objectives are attained and should therefore form part of the audit process on general performance.

6.10 AUDIT AND REPORT ON RELEVANT OF IWWMP ACTION PLAN

An annual audit will be compiled by a suitably qualified, external party on the conditions of the IWUL and should also include an audit of activities against GN704. The conditions proposed by DWS within the IWUL and the requirements of GN704 will be critical to attaining performance objectives.

The IWUL and GN704 audit will compare activities on site and determine the status of thereof. These should be identified as compliant or non-compliant, and recommendations made to rectify any non-compliance identified.

Further, the IWWMP and associated monitoring programmes should be reviewed annually and updated where relevant.

6.3.3 Other Performance Assessments

 All information as required by the various Government Departments should be captured and be readily available for submission when required. Therefore all monitoring data, inspections, incidences and remedial actions taken must be recorded and logged and be at the disposal of authorities during site visits.  A monitoring/inspection and action log will be maintained on site which will record date of inspection, any evidence of non-compliance observed with regard to the EMP and IWUL, all issues observed during inspections or through monitoring data, and all remediation actions taken. This log will be part of the public domain and be available to authorities during site visits.  A complaints register will be maintained on site and operated in much the same as the incident log as discussed above.  An annual performance assessment (different timeframe may be stipulated by authorities which will then be relevant) will be conducted by an external consultant throughout the life of mine as required by the NEMA. This is conducted to assess the adequacy and compliance of the EMP, and the relevant legislation. This report will comply with the format as set out in NEMA’s EIA regulations and will be submitted to the DMR.  The Quantum of the Financial Provision will be reviewed on an annual basis, and submitted to the DMR. Table 27: Monitoring Plan

Frequency of Functional requirements for Action Plans Responsible monitoring & monitoring person reporting

Continuous Water metering and Any large spikes on water use must be SHEQ recording followed up and source determined. May Manager indicate leaks on site.

Daily Inspect site for coal spillages All coal spillages on roads will be cleared SHEQ and all coal stockpile areas and the coal deposited on product Manager and ensure coal is regularly stockpiles.

118 | P a g e

UITKOMST COLLIERY: IWWMP

Frequency of Functional requirements for Action Plans Responsible monitoring & monitoring person reporting removed from site and in designated areas

Daily & After Inspect all concrete Taps/valves must always be closed and only SHEQ Rainfall bunded areas for opened under controlled circumstances. Manager hydrocarbon leaks and Operators must be properly trained to water accumulation. ensure these areas are managed properly. Water released from bunded areas will pass through oil traps and into the dirty water system. All water released after a flood event should be retained within the dirty water and recycled as far as possible. Water should be passed through oil traps prior to release into dirty water system to prevent oily residue build up in water.

Daily during Ensure activity is Cease all activity in undesignated areas Mine construction proceeding in demarcated and rehabilitate. If required, report activity Manager and then areas only and ensure any to the relevant authority. Monthly cement handling is over designated areas.

Weekly Inspection of all storm water All leaks identified will be repaired SHEQ management features, immediately. Silt build-up in water Manager potable water management facilities / dams will be infrastructure, pipelines, cleared and deposited in soil stockpiles if pumps and dams, clean or in residue deposits at the mine if dirty.

Weekly Inspection of all service and Schedule services and calibration as Mine maintenance needed. Manager plans/logbooks to ensure maintenance is scheduled in time.

Weekly Inspect co-disposal facility Ensure design parameters and rehabilitation Mine development and mine plans for the co disposal dump are applied. Manager & residue handling and Consult specialist engineers if required. SHEQ disposal Manager

Monthly Surface water quality Continue with surface water monitoring SHEQ monitoring programme. Manager All water related activities and actions within this table will be assessed if impaired quality is observed. Specialists will be consulted if required.

Monthly Dust monitoring Continue with dust monitoring programme. SHEQ Increase dust suppression when and where Manager necessary.

119 | P a g e

UITKOMST COLLIERY: IWWMP

Frequency of Functional requirements for Action Plans Responsible monitoring & monitoring person reporting

Monthly Visual inspections for Maintain a cradle to grave philosophy of SHEQ littering and illegally waste generated at site. Waste generated Manager dumped waste on site should be recycled as far as possible and sold/given to interested contractors. Recyclable waste should not be stored on site for excessive periods to reduced risk of environmental contamination. Refuse bins will be placed around site to collect all non- recyclable waste for disposal at the municipality.

Monthly (may Eradicate and control alien If aliens are observed on site then these will SHEQ vary invasive species be removed, preferably using mechanical Manager depending on methods before consideration to chemical species) methods. Plants will be removed when not seeding if possible.

Monthly visual Inspect surface overlying Ensure adequate safety standards are set SHEQ inspections underground mine and with regards to board-and-pillar mining. Manager ensure no surface cracks or Inspect areas of underground mining and subsidence rehabilitate any subsidence or sinkholes according to acceptable standards. Fill and rehabilitate all cracks and sinkholes with compacted overburden and covering with topsoil.

Monthly visual Monitor site for erosion and If pooling is observed then these areas will SHEQ inspections & pooling be filled and graded or entire area will be Manager After rainfall graded if drainage is insufficient. Repair all erosion on site using contour berms or gabions. Consult specialist if required. Disc or rip all compacted soils depending on degree of compaction and rehabilitate area. Apply erosion control measures to persistently eroded or severely eroded sites.

Quarterly Groundwater monitoring All water related activities and actions within SHEQ this table will be assessed if impaired quality Manager is observed. Specialists will be consulted if required.

Annual Topographical surveys Compare to baseline surveys and update Surveyor rehabilitation model accordingly.

Annual Soil surveys Contract soil specialist to assess soils and SHEQ implement recommendations Manager

Annual Test integrity of concrete Any lining which needs to be repaired will Mine bunding, coal stockpiling be attended to immediately with the Manager & layer and lining of dams assistance of specialists if required. SHEQ and co-disposal facility, Manager

Annual Complete alien invasive Contract registered alien invasive specialist SHEQ species surveys and follow- as soon as it is legally required and Manager

120 | P a g e

UITKOMST COLLIERY: IWWMP

Frequency of Functional requirements for Action Plans Responsible monitoring & monitoring person reporting up surveys implement recommendations

Biannual Biomonitoring Contract specialist and implement SHEQ recommendations Manager

7. CONCLUSION

7.1 REGULATORY STATUS OF ACTIVITY

The table below summarises the water uses identified for the operations and the regulatory status thereof. Table 28 Status of water uses

Ref. S.21 Water Use: Description: Currently Status: Action Required: Licensed:

1. 21(a): Taking water Abstraction from a Yes Existing Amend volumes & from a water resource borehole for domestic & co-ordinates potable use at Uitkomst Adit/Adit 1

2. 21(a): Taking water Abstraction of water No Existing New license from a water resource from Farm Dam 1 for required domestic and mine process use at Uitkomst Adit/Adit 1

3. 21(a): Taking water Abstraction from a No Proposed New license from a water resource borehole for domestic & required potable use at Klipspruit Adit 2

4. 21(a): Taking water Associated with 21(j) – Yes Existing Amend volumes from a water resource reuse of underground mine water Uitkomst/ Adit 1

5. 21(a): Taking water Associated with 21(j) – No Proposed New license from a water resource reuse of underground required mine water Klipspruit Adit 2

6. 21(a): Taking water Abstraction from a No Proposed New license from a water resource borehole drilled into the required old Klipspruit workings for use at process water

7. 21(b): Storage of water Reservoir 1: Storage of No Existing New license water for domestic & required potable use Uitkomst Adit/Adit 1 (receives water from borehole &

121 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Use: Description: Currently Status: Action Required: Licensed: Farm Dam 1)

8. 21(b): Storage of water Reservoir 2: Storage of No Existing New license water for use as process required water underground (receives water from Farm Dam 1)

9. 21(c) & (i): Altering Uitkomst Adit/Adit 1 & No Existing New license beds and Banks or associated infrastructure required Diverting or Altering within a disturbed valley Flow in a Watercourse bottom

10. 21(c) & (i): Altering The proposed Klipspruit Pre-1998 Existing Include in license beds and Banks or Adit & associated Existing Diverting or Altering infrastructure <100m of Lawful Flow in a Watercourse valley bottom wetland Use and stream.

11. 21(c) & (i): Altering Proposed overhead line No Proposed New license beds and Banks or <500m of a wetland required Diverting or Altering Flow in a Watercourse

12. 21(c) & (i): Altering Undermining a water No Existing New license beds and Banks or resource required Diverting or Altering Flow in a Watercourse

13. 21(g): Disposal of waste RoM coal stockpiles at in a Uitkomst Adit/Adit 1 manner that could detrimentally impact on a water course

14. 21(g): Disposal of waste Coal stockpile at in a Uitkomst Adit/Adit 1 manner that could detrimentally impact on a water course

15. 21(g): Disposal of waste Coal stockpile at Yes Existing Amend volumes in a Uitkomst Adit/Adit 1 manner that could detrimentally impact on a water course

16. 21(g): Disposal of waste Coal stockpile at in a Uitkomst Adit/Adit 1 manner that could detrimentally impact on a water course

17. 21(g): Disposal of waste Coal stockpile at in a Uitkomst Adit/Adit 1

122 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Use: Description: Currently Status: Action Required: Licensed: manner that could detrimentally impact on a water course

18. 21(g): Disposal of waste RoM and Product coal No Proposed New license in a stockpiles at Klipspruit required manner that could Adit 2 detrimentally impact on a water course

19. 21(g): Disposal of waste Dust suppression at Yes Existing Include in license in a Uitkomst Adit/Adit 1 Amend capacity to manner that could include extension detrimentally impact on a water course

20. 21(g): Disposal of waste Dust suppression at No Proposed New license in a Klipspruit Adit 2 required manner that could detrimentally impact on a water course

21. 21(g): Disposal of waste Pollution Control Dam at Yes Existing None. in a Uitkomst Adit/Adit 1 manner that could (currently licensed as detrimentally impact RWD A) on a water course

22. 21(g): Disposal of waste Return Water Dam at Yes Existing None. in a Uitkomst Adit/Adit 1 manner that could (currently licensed as detrimentally impact RWD B) on a water course

23. 21(g): Disposal of waste Mine Residue Disposal Yes Existing Amend volumes & in a Site at Uitkomst Adit/Adit capacity manner that could 1 (currently licensed as detrimentally impact Discard Dump) on a water course

24. 21(g): Disposal of waste Plant Dam A at Uitkomst Yes Existing Amend throughput in a Adit/Adit 1 - consisting of volumes manner that could two compartments detrimentally impact (currently licensed as on a water course settling pond)

25. 21(g): Disposal of waste Plant Dam B at Uitkomst Yes Existing Amend throughput in a Adit/Adit 1 (currently volumes manner that could licensed as pollution detrimentally impact control dam) on a water course

26. 21(g): Disposal of waste Pollution Control Dam at Pre-1998 Existing Amend throughput

123 | P a g e

UITKOMST COLLIERY: IWWMP

Ref. S.21 Water Use: Description: Currently Status: Action Required: Licensed: in a Klipspruit Adit 1 Existing volumes manner that could Lawful detrimentally impact Use on a water course

27. 21(j): Removing water Dewatering of the Yes Existing Amend volumes from Underground to underground workings Continue with Safe at the Uitkomst Adit/Adit Mining 1

28. 21(j): Removing water Dewatering of the No Proposed New license from Underground to underground workings required Continue with Safe at Klipspruit Adit 2 Mining

24. 21(g): Disposal of waste Slurry dam at Uitkomst Yes n/a Remove from water in a Adit/Adit 1 license manner that could detrimentally impact on a water course

124 | P a g e

UITKOMST COLLIERY: IWWMP

7.2 STATEMENT OF WATER USES REQUIRING AUTHORISATION, DISPENSING WITH LICENSING REQUIREMENT & POSSIBLE EXEMPTION FROM REGULATION

The following additional / future water use activities have been identified on site, and require licensing in terms of the NWA:

 21(a) Taking water from a water resource;  21(c) Impeding or diverting the flow of water in a water course;  21(i) Altering the beds, banks, course or characteristics of a water course;  21(g) Disposing of waste in a manner which may detrimentally impact on a water resource;  21(j) Removing, discharging or disposing of water found underground if it is necessary for the efficient continuation of an activity or for the safety of people. In addition, a number of water uses require exemption from GN R. 704; these are indicated in Section 3.3 of this report.

125 | P a g e

UITKOMST COLLIERY: IWWMP

8. REFERENCES

Cabanga Concepts, 2007 revised 2010: Integrated Water Use License Application and Technical Document for Uitkomst Colliery.

Cabanga Concepts, 2012: Integrated Water and Waste Management Plan for Uitkomst Colliery.

Cabanga Environmental, 2017: Second Quarter Water Monitoring Report.

Cabanga Environmental, 2017: Uitkomst Colliery (Pty) Ltd, Uitkomst and Klipspruit Adits, Summary of all Wetland Impacts for the Application of a Water Use License Application.

Clean Stream Environmental Service, 2004: Uitkomst Colliery Environmental Management Programme Report.

Digby Wells and Associates, 2006: Environmental Impact Assessment and Environmental Management plan for Uitkomst Colliery.

Dimela Eco Consulting, 2016 revised 2017: Uitkomst Colliery (Pty) Ltd, Vegetation Impact Assessment Report.

eMandlangeni Local Municipality Demographics, date unknown: available at http://www.localgovernment.co.za/locals/view/68/eMadlangeni-Local- Municipality#service-delivery last accessed 26 April 2017.

Future Flow Groundwater and Project Management, 2017: Uitkomst Colliery, Groundwater WULA Study.

Geoff Silk Civil and Mining Consultants, 2009: Uitkomst Colliery Extension, MPRDA Section 102 Application.

Groundwater Consulting Services, 2006: Kangra Coal (Pty) Ltd, Klipspruit Colliery, Environmental Management Programme.

Groundwater Consulting Services (, 2006: Uitkomst Colliery, Coal Discard Disposal Facility Conceptual Design and Pollution Control Dam Detailed Design.

Harvey Ecological, 2016 revised 2017: Fauna Biodiversity Assessment for the Proposed Klipspruit Mine Extension Development, Newcastle Area, KwaZulu-Natal.

Hydro-Pedo Consulting, 2017: Wetland/Riparian Delineation and Functional Assessment.

Letsolo Water and Engineering Services, 2016 revised 2017: Klipspruit and Uitkomst Adits, Hydrological Impact Assessment (Revision 2).

SLR Consulting, 2015: Environmental Impact Assessment and Environmental Management Programme Consolidation for Klipspruit and Uitkomst Collieries.

126 | P a g e

UITKOMST COLLIERY: IWWMP

APPENDIX 1: MINING RIGHT APPENDIX 2: CONFIRMATION OF BEE STATUS APPENDIX 3: APPROVED WATER USE LICENSE APPENDIX 4: ENVIRONMENTAL AUTHORISATION APPENDIX 5: SECOND QUARTER WATER MONITORING REPORT

APPENDIX 6: WETLAND REPORT APPENDIX 7: AQUATIC BIOMONITORING REPORTS (2016) APPENDIX 8: GROUNDWATER REPORT APPENDIX 9: PROOF OF PUBLIC PARTICIPATION APPENDIX 10: ENGINEERING REPORTS / DESIGNS

APPENDIX 11: MASTER PLAN APPENDIX 12: PROOF OF PAYMENT

APPENDIX 13: WATER USE LICENSE FORMS

127 | P a g e