PROCUREMENT PLAN Date: July 21, 2011 (updated as of January 18, 2012) : ADDITIONAL FINANCING OF IRRIGATION REHABILITATION EMERGENCY PROJECT (IBRD Loan#8106-AM) a) CIVIL WORKS Review By No. of Method of Bank Actual Contract Price in Contractor/ Country of Expected Bid- Contract Completion # Description/ Location Packages Invitation Date Start Date Contract ref # Procurement (Prior/ Contract Currency registration Opening Date Signing Date Date /Lots Post) Public Disclosure Authorized 1. WORKS FOR REHABILITATION OF PRIMARY AND ON-FARM IRRIGATION CANALS Rehabilitation of Mkhchyan canal IREP/AF/NCB/CW- 1 DM35+20-DM74+43 and Dvin canal NCB Prior 1 335,962,419 AMD Dorozhnik LLC (NKR) 23-Sep-11 24-Oct-11 16-Dec-11 25-Dec-11 30-Apr-13 11/001 DM7+69-DM38+08 Rehabilitation of Arzni Shamiram canal IREP/AF/NCB/CW- 2 DM105+35-DM281+50 (I-st stage NCB Prior 1 798,178,056 AMD Sahakyanshin CJSC (RA) 23-Sep-11 24-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13 11/002 canal) Rehabilitation of Arzni Shamiram canal IREP/AF/NCB/CW- 3 DM179+60-DM447+91 (II-nd stage NCB Post 1 719,813,400 AMD Khachhar LLC (RA) 24-Sep-11 25-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13 11/003 canal)

JV of Egvardshin OJSC- Rehabilitation of Arzni canal branch IREP/AF/NCB/CW- 4 NCB Post 1 1,179,723,760 AMD Dorozhnik LLC, 1-Oct-11 31-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13 DM27+57-DM124+00 11/004 (RA/NKR) Public Disclosure Authorized

Rehabilitation of right branch of Kasakh canal DM9+14-DM41+42 and left IREP/AF/NCB/CW- 5 NCB Post 1 440,000,007 AMD Agat-777 LLC (RA) 24-Sep-11 25-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13 branch of Kasakh canal DM34+09- 11/005 DM65+00

Rehabilitation of Lower Hrazdan canals JV of Arpa Sevan OJSC - DM112+00-DM160+40 (I-st stage), IREP/AF/NCB/CW- 6 NCB Post 1 869,999,425 AMD SHMSH-23 OJSC 29-Sep-11 27-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13 DM24+22-DM86+60 (II-nd stage) and 11/006 (RA/RA) Shah-Aru canal DM30+74-DM47+86

Rehabilitation of Shirak main canal DM13+40-DM24+04; Distributor 26 IREP/AF/NCB/CW- 7 NCB Post 1 674,922,925 AMD Spitak-1 OJSC (RA) 24-Sep-11 25-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13

Public Disclosure Authorized canal at DM91+64-DM169+84 and 11/007 Nalband canal DM141+22-DM183+73

Rehabilitation of right branch of Talin main canal DM102+46-DM165+07 and Bagramyanshin OJSC IREP/AF/NCB/CW- 8 NCB Post 1 410,435,050 AMD 29-Sep-11 27-Oct-11 15-Dec-11 25-Dec-11 30-Apr-13 "Mayr Aru" canal DM0+00- (RA) 11/008 DM31+86 Public Disclosure Authorized Rehabilitation of tertiary irrigation networks in Baghramyan, Miasnikyan, , , Bagaran, Vanand, JV of SADE JSC - Blesk Ervandashat, communities of IREP/AF/NCB/CW- 9 NCB Post 1 863,888,452 AMD LLC (France/ 14-Oct-11 11-Nov-11 21-Dec-11 20-Jan-12 30-Apr-13 Talin I/S, , Hatsik, Noravan 11/009 Russia) communities in I/S and community under command of Lower-Hrazdan system.

Rehabilitation oftertiary irrigation networks in Jrashen community of Nalband I/S, , Martuni, IREP/AF/NCB/CW- 10 NCB Post 1 649,206,111 AMD Dorozhnik LLC (NKR) 14-Oct-11 11-Nov-11 16-Dec-11 20-Jan-12 30-Apr-13 Dzoragjugh, , 11/010 communities of Sevan I/S and Meghrashen community of Shirak I/S.

b) Consulting Services

Review by Expected Adverti- Selection Bank Number of Actual Contract Price in Consultant / country of Proposal Contract Completion # Description sement for Start Date Contract ref # Method Prior/ Contracts Contract Currency registration Submission Signing Date Date EOI Date Post Date 2. CONSULTANTS` SERVICES

Technical and quality supervision over JV of CES-YSUAC IREP/AF/QCBS/ 1 QCBS Prior 1 704,472 USD 27-Aug-11 29-Nov-11 21-Dec-11 25-Dec-11 30-Apr-13 rehabilitation of primary canals (Germany/RA) SW-11/001

Technical and quality supervision over JV of CES-YSUAC IREP/AF/QCBS/ 2 QCBS Prior 1 191,904 USD 27-Aug-11 30-Nov-11 16-Jan-12 20-Jan-12 30-Apr-13 rehabilitation of on-farm irrigation (Germany/RA) SW-11/002 network canals

The Procurement procedures has not started 1-Feb-12 15-Apr-12 25-May-12 1-Jun-12 1-Dec-12 IREP/AF/QCBS/ 3 Study of the Meghri gravity scheme QCBS Prior 1 yet SW-11/003

15-Oct-11 15-Dec-11 25-Jan-12 1-Feb-12 30-Jun-13 Audit of WUAs and WSAs (for calendar The Procurement procedures has already IREP/AF/LCS/SW- 4 LCS Prior 1 started 11/001Aud years 2011-2012) 3-Nov-11 18-Jan-12

The Procurement procedures has not started 15-Oct-11 15-Dec-11 25-Jan-12 1-Feb-12 30-Jun-13 IREP/AF/LCS/SW- 5 Audit of Project (2011-2013) LCS Post 1 yet 11/002Aud