<<

January 14, 2016

Mr. Steve Walensky Director of Public Works City of Cassville 300 Main Street Cassville, Missouri 65625

Re: WASTEWATER COLLECTION SYSTEM FACILITY PLAN OA PROJECT NO. 014-2994

Dear Mr. Walensky,

We present herewith a copy of the City of Cassville Wastewater Collection System Facility Plan, in accordance with our agreement dated July 31, 2014.

This Facility Plan summarizes our evaluation of the City’s existing wastewater collection system with respect to the development of a comprehensive plan to guide collection system improvements to be pursued by the City over the next several years. Two copies of this report will be sent to MoDNR as part of the Small Community Engineering Assistance Grant requirements.

We appreciate all of the assistance received from officials and employees of the City during the preparation of this Facility Plan.

Sincerely, OLSSON ASSOCIATES

Jerry Jesky, P.E. Senior Engineer

Attachment

550 St. Louis Street TEL 417.890.8802 www.olssonassociates.com Springfield, MO 65806 FAX 417.890.8805

TABLE OF CONTENTS

Page

I. INTRODUCTION ...... 1 A. Purpose ...... 1 B. Scope ...... 1 C. Existing Conditions ...... 1 D. Previous Wastewater System Documentation ...... 3

II. GENERAL INFORMATION AND PLANNING AREA ...... 4 A. Identification ...... 4 B. Planning Area ...... 4 C. Topographic, Geological, Soil, and Climate Characteristics of Planning Area ...... 4

III. PLANNING PERIOD AND POPULATION PROJECTION ...... 6 A. Planning Period ...... 6 B. Population Projection ...... 6

IV. EXISTING FACILITIES ANALYSIS ...... 9 A. Existing Collection System ...... 9 B. Existing Wastewater Treatment Plant (WWTP)...... 12

V. HYDRAULIC CAPACITY EVALUATION ...... 13 A. Water Use and Wastewater Treatment Facility Flow Monitoring ...... 13 B. Wet Weather Flow Projections versus Hydraulic Capacity ...... 25

VI. RECENT CCTV EFFORTS AND IDENTIFIED PROBLEM AREAS ...... 27 A. General ...... 27 B. Observed Collection System Defects ...... 27

VII. PROJECT ALTERNATIVE ANALYSIS ...... 30 A. Repair Alternatives ...... 30 B. Gravity Main Lines ...... 32 C. Service Line Connections ...... 33 D. Manholes ...... 34

VIII. RECOMMENDED PROJECT ALTERNATIVE SUMMARY AND JUSTIFICATION ...... 35 A. Recommended Rehabilitation Alternatives (Years 1-5) ...... 35 B. Private Inflow and Infiltration Abatement (Years 6-10) ...... 36 C. Cost Opinion for Proposed Rehabilitation ...... 37 D. Funding Strategy and Impact on User Fees ...... 39 E. Proposed Rehabilitation Schedule ...... 39 F. Conclusion...... 40

Project 014-2994 i January 2016

Tables

Table III-1 Historical Population Data ...... 7 Table III-2 Projected Population Data ...... 8 Table IV-1 Sanitary Collection System Inventory ...... 9 Table V-1 Estimated Population versus Water Data for 2010 to 2014 ...... 13 Table V-2 Recent Summary of WWTP Effluent Flows and Area Precipitation ...... 14 Table V-3 Dry Weather WWTP Effluent Flows ...... 16 Table V-4 Average Daily Dry Weather Wastewater Effluent per Person ...... 17 Table V-5 Well Water Use & WWTP Outfall Comparison from 2010 to 2014 ...... 18 Table V-6 WWTP Daily Influent and Effluent Flow Data for May 9th – July 23rd, 2015 ...... 20 Table V-7 Flow Data per Capita Comparison ...... 24 Table V-8 Projected WWTP Influent Flow Ranges Based on Dry and Wet Weather per Capita Projections ...... 25 Table V-9 Needed Wet Weather Flow Reductions Over the Planning Period ...... 26 Table VII-1 Sewer Line Inventory for Saturation Zone and Outer Zone ...... 33 Table VII-2 Saturation & Outer Zone Manhole Inventory ...... 34 Table VIII-1 Opinion of Probable Construction Costs for Recommended Improvements ...... 38 Table VIII-2 City of Cassville Current Sewer User Rate Schedule ...... 39

Figures

Figure III-1 Historic and Projected Population ...... 8 Figure V-1 Cassville Well Water Pumped, WWTP Flows, & Rainfall ...... 23

Exhibits

Exhibit 1 Wastewater System Layout Map Exhibit 2 Wastewater System Basin Map Exhibit 3 Wastewater System Saturation Zone Map

Appendices

Appendix A CCTV Review Spreadsheet

Project 014-2994 ii January 2016 City of Cassville, Missouri Wastewater Collection System Facility Plan

I. INTRODUCTION

A. Purpose The purpose of this facility plan is to develop a comprehensive Collection System Evaluation to guide sewer collection system improvements to be pursued by the City of Cassville over the next several years. This facility plan presents an analysis and evaluation of previous wastewater system reports and smoke-testing results, recent sewer line videoing and flow monitoring, Public Works Department maintenance logs, geographical information system (GIS) mapping, and a funding strategy to prioritize and schedule the recommended actions stemming from the evaluation.

B. Scope Preparation of this facility plan included the following steps:

1. Review of the City’s previous wastewater system reports;

2. Review of the City’s sewer system GIS mapping;

3. Review of previous smoke testing results;

4. Review and analysis of recent closed-caption television (CCTV) sewer line videos;

5. Review of recent Public Works Department maintenance logs and activities;

6. Review of City pump station information;

7. Discussion of sewer system issues with Public Works staff, including coordinating additional inspections;

8. Development of a prioritized spreadsheet of recommended improvements based on the review, analysis, and evaluation of the data;

9. Development of cost opinions and a funding strategy for the City to complete the recommended improvements and actions over the next several years.

C. Existing Conditions The City of Cassville’s existing wastewater system consists of a mostly gravity-flow collection system with only one lift station that serves a very small area of the system, and a mechanical wastewater treatment plant (WWTP) with an adjacent overflow lagoon for wet-weather flow storage. The collection system consists of approximately 171,325 feet of gravity mains, 640 manholes, 34 lampholes, and 953 feet of force main from one lift station in the northern portion of the system. The gravity sewer mains range in size from 6” to 24” in diameter.

Project No. 014-2994 1 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

A significant portion of the gravity lines are 8-inch vitrified clay pipe (VCP). Much of the original collection system was constructed prior to 1940, with portions of the original system still in use today. Newer lines have been constructed with conventional polyvinyl chloride (PVC) pipe. The older manholes were constructed with brick and mortar, with newer manholes being pre-cast or poured-in-place concrete.

The mechanical WWTP, located along the northeast edge of town, was initially constructed in 1979 and took the place of the stabilization pond that once served the community. The original stabilization pond now serves as a wet-weather extraneous flow basin. The WWTP, which discharges to Flat Creek in Barry County, currently utilizes an aeration basin with a selector basin and four clarifiers followed by chemical phosphorus removal with disc filtration and then ultraviolet disinfection. For sludge storage, the City uses an aerated sludge holding tank. All of the wastewater that enters the WWTP must be pumped by a main influent lift station (capacity 4.8 MGD) at the head of the plant.

The permitted WWTP design population equivalent is 8,630 with a design flow of 1.1 million gallons per day (MGD). Per the City’s current operating permit, which runs from March 2011 through March 2016, the actual flow through Outfall #001 is listed as 0.925 MGD, and the design sludge production is 115 dry tons/year. Discharge from Outfall #002 associated with the 18-acre stabilization pond is no longer authorized and must be reported as an emergency bypass. Ideally, wet-weather flows that are diverted to the storage pond are only to be stored until treatment capacity is available at the mechanical WWTP.

Several hundred feet of gravity sewer main runs adjacent to Flat Creek, which cuts through the city and is subject to variable creek levels, high groundwater conditions, and flash flooding. Due to the nature of the underlying aquifer, high creek levels during wet-weather events temporarily cause a rise in the regional water table that can last for weeks after the creek floodwaters recede. During these periods of wet-weather and persistent high groundwater levels, the collection system experiences excessive inflow and infiltration (I&I) into the sewer lines, which can lead to surcharging manholes throughout town and very high flows to the WWTP.

The WWTP’s hydraulic capacity is approximately 1.2 MGD. Incoming flow in excess of this capacity is temporarily stored in the adjacent stabilization pond (lagoon) until it can be pumped back through the plant for full treatment. However, because excess flow diversion to the lagoon occurs after the WWTP influent lift station, this flow must be pumped a second time to receive treatment through the plant. During major wet-weather events, the lagoon fills up to capacity and the plant operators must open the discharge valve to release water from the lagoon through Outfall #002.

Under previous operating permits, the City was permitted to discharge from Outfall #002 as long as the effluent quality met the discharge limits for this outfall. However, a 2010 revision to Missouri Department of Natural Resources’ (MoDNR) effluent regulations now prohibits wastewater discharges that bypass secondary treatment. Accordingly, discharge from Outfall #002 is no longer authorized.

Project No. 014-2994 2 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

In March of 2011, the City of Cassville signed a Voluntary Compliance Agreement (VCA) with MoDNR requiring the City to report any future discharges from the lagoon as a “bypass” and to develop a Bypass Elimination Plan (BEP) to outline how the City plans to reduce wet-weather flows and eliminate bypasses from the lagoon. A BEP report was completed in July of 2012 and subsequently submitted to MoDNR for review. The BEP report included a summary of the wastewater system, results from flow-monitoring several locations in the collection system, comparison of dry-weather and wet-weather flow conditions, analysis of lagoon storage capacity, presentation of alternatives for eliminating treatment plant bypasses, proposed collection system upgrades, and a recommended sewer improvements project based on estimated quantities derived from the limited information available. The report was approved for implementation by MoDNR.

The drought conditions experienced in 2012 showed that an increase in collection system piping size was not needed, but rather a reduction in the extraneous I&I flows in the system was warranted. However, the amount of data that was available for evaluation during the development of the BEP report was not sufficient enough to recommend detailed sewer rehabilitation improvements to specific collection system lines. As a result, a collection system rehabilitation schedule that could be associated with a funding strategy was not developed as part of the BEP. Accordingly, this facility plan builds upon the 2012 BEP report by analyzing additional data and establishing specific rehabilitation efforts for collection system lines to be associated with the City’s anticipated rehabilitation budget over the next several years.

D. Previous Wastewater System Documentation The following is a list of previous wastewater documents and analyses that have been reviewed during the preparation of this study.

1. Wastewater Facility Plan (Sprenkle & Associates 2001) 2. Sanitary Sewer Evaluation Survey Smoke Testing (Wade & Associates 2005) 3. Missouri Department of Natural Resources Voluntary Compliance Agreement (MoDNR VCA 2011)

4. Bypass Elimination Plan (Olsson Associates 2012) 5. Manhole Inspections (City of Cassville 2014)

Project No. 014-2994 3 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

II. GENERAL INFORMATION AND PLANNING AREA

A. Identification The name and mailing address of the Publicly Owned Treatment Works (POTW) system continuing authority is:

City of Cassville 300 Main Street Cassville, MO 65738 Mr. Bill Shiveley, Mayor Mr. Steve Walensky, Public Works Director

Mayor Shiveley and Mr. Walensky can be contacted at City Hall, phone number 417.847.4441. The City’s POTW is operated under Missouri State Operating Permit (MOSP) MO-0042579 as part of the National Pollutant Discharge Elimination System (NPDES) and is regulated at the state level by MoDNR, whose central office is located in Jefferson City, Missouri. Regional MoDNR regulatory authority is provided by personnel staffed in the Southwest Regional Office (SWRO) of MoDNR, located in Springfield, Missouri.

B. Planning Area The planning area for this facility plan includes the area served by the City of Cassville’s existing wastewater collection system, shown in Exhibit 1. In general, this area is representative of the City’s incorporated limits, which encompasses approximately 3.22 square miles. Only two (2) notable collection system lines are located outside of the incorporated city limits boundary – one extends north to the Crowder College campus and the other extends northeast to the WWTP. The City currently has no definitive plans to expand its sewer system service area.

With a 2010 United State Census population of 3,266, the City of Cassville acts as a regional hub situated between the larger communities of Joplin, Missouri at forty-five (45) miles (2010 census population of 50,150); Springfield, Missouri at forty-eight (48) miles (2010 census population of 159,498); Rogers, Arkansas at thirty (30) miles (2010 census population of 55,964); and Harrison, Arkansas at fifty-one (51) miles (2010 census population of 12,943). This has resulted in the City having five (5) state highways, a uniquely high number relative to size. These include State Highways 37, 76, 86, 112, and 248.

C. Topographic, Geological, Soil, and Climate Characteristics of Planning Area 1. Topographic Barry County experiences a high elevation of over 1,500 feet USGS along a plateau just west of the service area extending from Washburn to just south of Purdy. The lowest elevation of the county is at the water level of Table Rock Lake, which has a normal surface elevation of 915 feet. The high elevation ridge in the county divides the Missouri River and White River drainage basins, with Cassville being located within the latter. The general slope of the planning area

Project No. 014-2994 4 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

and surrounding land is towards Flat Creek in the center of town where the elevation then drops off towards the northeast as Flat Creek drains into Table Rock Lake.

This unique drainage feature is why Cassville has earned the nickname “The City of Seven Valleys.” Each valley carries with it a significant area of surface water runoff that drains to Flat Creek. Utilizing maps of Barry County creeks, the estimated area of rainwater drainage is approximately forty-five (45) square miles. This large drainage area has contributed to frequent flooding events as the city is built up along and around Flat Creek’s normal flow level. With severe flooding causing the water level in Flat Creek to breach its banks by several feet, a large portion of Cassville has been placed in the Federal Emergency Management Agency’s (FEMA) 100-year floodplain.

2. Geology & Soil The soils and topography in Barry County are influenced to a great extent by many different geologic formations. From the oldest to the youngest, these formations are the Jefferson City- Cotter, Chattanooga, Compton, Pierson, Elsey-Reed Springs, Burlington-Keokuk, Hindsville, Batesville, Fayetteville, and Hale. The formations are mainly composed of limestone rock which greatly contributes to the karst nature of the area. Karst landscapes are created by easily dissolvable , resulting in cracks, caves, fissures, and sinkholes. These open geologic features more easily permit water conveyance, which can lead to high groundwater levels and higher degrees of erosion. The soils in the area are readily excavated for pipelines and are compatible with most commonly used piping materials.

3. Climate Cassville’s service area experiences a moderate climate that is similar to that of the county as a whole. Cassville has a National Climate Data Center recording center operated in cooperation by the National Weather Service and National Oceanic and Atmospheric Administration (station ID #231383). Based off of compiled data from over one hundred years of recordings, Cassville experiences a moderate climate with an average high temperature in summer of 87° F and in winter of 48° F, with a record high of 108° F on August 4, 2011 and a record low of -25° F on December 22, 1916. The City experiences an average yearly rainfall of just under 45 inches, which is well distributed throughout the year.

Project No. 014-2994 5 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

III. PLANNING PERIOD AND POPULATION PROJECTION

A. Planning Period In order to comply with the anticipated schedule associated with the VCA between the City of Cassville and MoDNR, a ten-year planning period was considered in regards to growth, flows, and infrastructure improvements. While this planning period was applied in consideration of developing recommendations, satisfying compliance agreements, and securing the funding needed to meet the objectives of the City’s desired rehabilitation schedule, it is not indicative of the design life of the existing wastewater system or of the improvements recommended. The recommended improvements are expected to have a 50-plus year design life, and are based on the conclusion that existing collection system rehabilitation and compliance with the VCA takes precedence on the planning schedule, rather than long-term population growth and base flow increases.

B. Population Projection Cassville was incorporated in 1846 and is currently listed as a “4th Class” city by Missouri Roster. Unlike many small cities throughout southwest Missouri, Cassville has established itself as a hub of commerce for neighboring communities, thus relieving itself from the dependence on individual businesses. Though employers come and go over the decades, Cassville has shown a resilience to population growth rate variances and has continued to increase in size steadily since 1900. Historical consistency helps increase the accuracy of the growth projections calculated for the 10-year planning period.

Project No. 014-2994 6 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE III-1: HISTORICAL POPULATION DATA

Historical Annual % Year Population Growth

1900 702 1910 781 1.1% 1920 1,002 2.5% 1930 1,016 0.1% 1940 1,214 1.8% 1950 1,441 1.7% 1960 1,451 0.1% 1970 1,910 2.8% 1980 2,091 0.9% 1990 2,371 1.3% 2000 2,890 2.0% 2010 3,266 1.2% Average 1.4%

The yearly growth rates for the entire recorded history from 1900 to 2010 were calculated and averaged to derive the projected growth rate. Additionally, recent data was taken into consideration as factors affecting population can change completely with over a century of data. The two averages calculated out to be very similar, 1.4% for the entire span of data and 1.35% for the recent four (4) census counts. Accordingly, 1.4% annual growth was used to project future populations for the City. A graphic representation of the historical and projected populations can be found in Figure III-1. The projected planning area population for the year 2026 is 4,080.

Project No. 014-2994 7 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE III-2: PROJECTED POPULATION DATA

Annual Projected Year % Population Growth

2016 3,550 1.4% 2017 3,600 1.4% 2018 3,650 1.4% 2019 3,701 1.4% 2020 3,753 1.4% 2021 3,806 1.4% 2022 3,859 1.4% 2023 3,913 1.4% 2024 3,968 1.4% 2025 4,023 1.4% 2026 4,080 1.4%

FIGURE III-1: HISTORIC AND PROJECTED POPULATION

5000

4500 2035 Projected Population = 4623 4000 Historical

Projected 3500

3000

2500

2000 Population

1500

1000

500

0 1880 1900 1920 1940 1960 1980 2000 2020 2040 2060 Year

Project No. 014-2994 8 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

IV. EXISTING FACILITIES ANALYSIS

A. Existing Collection System

1. Collection System Description and Inventory The sanitary sewer collection system for Cassville primarily consists of VCP and PVC gravity lines, along with one force main from the Sherwood Forest lift station. The system is divided into seven basins based on geographical and man-made barriers. Each basin has an identification letter associated with it and, in the case of Cassville, so also does the main trunk line, which serves as the interceptor sewer to convey wastewater to the WWTP. The basin identifications are arbitrarily labelled “A” through “G”, with Basin G being the main trunk line running form the newest industrial developments in the southwest to the treatment plant in the northeast portion of the service area. The Sherwood Forest lift station and associated force main are located within Basin B in the northwest portion of the City. In total, the service area has approximately 171,325 linear feet of gravity line and 953 of force main. Providing access to the sewer lines are approximately 640 manholes and 34 lampholes, which the City has incorporated into a sewer system GIS. A map of the service area can be found in Exhibit 1 and a map of the basins can be found in Exhibit 2. The following is an inventory of the collection system by basin based on current mapping data:

TABLE IV-1: SANITARY COLLECTION SYSTEM INVENTORY

Basin Approximate Approximate Sewer Length ID # of Manholes Gravity Force Main A 146 40,431 0 B 113 28,934 953 C 50 15,040 0 D 70 15,384 0 E 102 29,647 0 F 61 16,691 0 G 98 25,198 0 TOTAL 640 171,325 953

2. Previous Collection System Evaluation and Findings

a. General Inflow and Infiltration Findings by Public Works Staff The effects of system deficiencies are most visible at the Cassville WWTP during and following heavy rain events. As the ground becomes saturated, defects in the collection system allow rainwater to enter in the form of inflow and infiltration – also known as “I&I”. Inflow is the rainwater that enters the system directly from point sources, such as missing manhole lids, building sump pumps, or downspouts connected to the sanitary sewer collection system. Infiltration occurs when groundwater enters through leaking joints, cracked pipes, or deteriorated manholes in the collection system.

Project No. 014-2994 9 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

Most all sanitary sewer systems experience I&I to some degree, and management programs should be adopted and routinely implemented to mitigate the costs associated with conveying and treating high wet-weather flows. Major cost concerns include additional wear on pumps and other mechanics, cost of operation of pumps and treatment plant equipment/chemicals, overflow cleanup, and the necessary system upgrades to handle large flow rates. While the 2001 Wastewater Facility Plan by Sprenkle & Associates noted that collection system defects existed and I&I was high, this plan focused on increasing treatment capacity and capability rather than on reducing I&I in the collection system.

Through their recent sewer line cleaning and televising efforts, Cassville Public Works staff have found numerous defects throughout the collection system, almost entirely in the older areas of the system that have clay sewer lines. Unfortunately, these areas also tend to be in the lower elevations of the service area and along Flat Creek, and are thus subject to highly saturated ground conditions.

b. Smoke Testing In 2005, the City of Cassville contracted Wade & Associates, Inc. (acquired by CH2M Hill in 2007) to conduct smoke testing on the sanitary sewer system. This testing involves using fans located on adjacent manholes to push smoke into the lines; where the smoke can find a leak in the system, a plume will arise, which can be marked for later repair. These defects are broken into two sectors based on ownership – public and private. Public defects include issues with sewer mains and manholes, while private defects include sources located from the service connection up to and inside the home.

In total, Wade & Associates was able to test 518 line segments for a total of approximately 135,000 linear feet. Work crews were able to located 191 defects in the sanitary sewers, primarily in the private sector, which accounted for 166 of these defects. Furthermore, the largest single cause of defect was found to be service laterals, with 106 occurrences. Unfortunately, due to a lack of funding, the City has been unable to take action in resolving the private sector issues, other than replacing a few cleanout caps around town.

c. 2011 Flow Monitoring In 2011, Olsson Associates performed a wastewater system study to develop a Bypass Elimination Plan (BEP) for Cassville. This plan established action steps for the City in accordance with a signed Voluntary Compliance Agreement (VCA) with MoDNR. The VCA was necessary as previous permit requirements that allowed for discharges from the lagoon (Outfall #002) were eliminated, since bypassing secondary (biological) treatment was no longer allowed. Included in the BEP was flow monitoring, collection system capacity analysis, WWTP capacity analysis, and recommendations to address I&I.

Project No. 014-2994 10 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

Flow monitoring for the BEP consisted of temporary installation of six (6) flow meters from April to July of 2011. The meters were placed in manholes above the flow, using Doppler radar to measure surface velocity and ultrasonic pulse echo to measure depth, from which the instantaneous flow rate was able to be calculated every fifteen (15) minutes. Over the course of the study numerous rain events and dry periods allowed for a sampling of the systems response to various conditions allowing for both base line and heavy use models. Most notably was that the treatment plant received a peak inflow rate of 4.24 million gallons per day (MGD) and twenty (20) consecutive days with inflow greater than the WWTP design maximum of 1.1 MGD. Frequent discharge from the Outfall #002 was required to prevent the lagoon from spilling over.

During the flow monitoring period, several incidents of sanitary sewer overflows (SSOs) occurred throughout the system. SSOs result from collection system flow exceeding the pipe capacity, resulting in discharges from available relief points, which include but are not limited to manholes, cleanouts, cracked pipes, and loose joints.

Also presented in the BEP report were several alternatives to provide additional capacity and rehabilitation to the collection system to help mitigate the need for discharging from Outfall #002. The BEP was finalized and submitted to MoDNR in 2012. However, the drought conditions experienced throughout 2012 showed that an increase in collection system piping size to the WWTP was not necessary; but rather a concentrated effort on reducing wet-weather I&I flows through rehabilitation of the collection system was needed.

d. Manhole Inspections In 2014, the City of Cassville began a standardized method of evaluating manholes in the collection system by means of structure location, composition, and condition. The inspections included sixty-nine (69) manholes from across the service area and revealed the structures to be in generally good condition. Seventeen (17) defects were identified from the evaluations, the majority resulting from deteriorated brick or block structural materials. Joints are the most common source of infiltration and older masonry manholes have vastly higher total joint lengths between structural members than precast concrete. Additional defects included a defective lid, signs of surcharge, and manhole steps in poor condition. Copies of the inspection reports are on-file with the City.

e. 2015 Flow Monitoring In 2015, WWTP influent flow monitoring was conducted between May 8th and July 23rd by placing a single flow meter (ISCO LaserFlow) in the manhole just upstream of the WWTP influent pump station. This monitoring period coincided with an uncommonly wet summer in which multiple heavy rainfall events occurred. A summary of the data collected can be found in Table V-6 with associated analysis discussed in Section V.

Project No. 014-2994 11 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

B. Existing Wastewater Treatment Plant (WWTP) Cassville operates a single WWTP approximately half a mile northeast of city proper on Farm Road 1120 (also known as Partridge Dr.). The current WWTP operator is Steve Henderson, certified Level A (#2842). The plant was upgraded in 2003 to a permitted design flow of 1.1 MGD. Influent enters the WWTP through a twenty-four inch (24”) PVC pipe where flows are screened for debris. Flows enter the WWTP through an influent pump station, providing the necessary initial head to allow flows to gravity flow through the plant. When flows are projected to top 1.2 MGD, a weir located along the influent channel that receives the pumped influent flow can be adjusted to divert incoming flows greater than 1.2 MGD to the lagoon and prevent flooding within the mechanical plant. The excess flow (>1.2 MGD) is diverted to an 18-acre storage basin that once served as the main treatment lagoon for the service area before the mechanical treatment plant was constructed. During wet-weather periods that result in sustained incoming flow diversion to the lagoon that consumes the available storage capacity, a valve can be opened to discharge from the lagoon at Outfall #002, directly to Flat Creek, to avoid overtopping the lagoon berms. Since there is no flow meter on the lagoon influent or effluent structures, no direct means of measuring the volume diverted or discharged is available.

The mechanical plant currently includes the following components: • 24” PVC influent line from plant entrance to headworks • Screening • 4.8 MGD influent pump station • Flow control structure (diversion weir) and influent flow meter (to mechanical plant) • Cyclone grit removal • Anaerobic selector basin to facilitate biological phosphorus removal • 1,000,000-gallon aeration basin • Liquid alum feed system • 4 – 24’ diameter clarifiers (2.17 MGD capacity at 1,200 gpd/sf) • 2 – Kruger disc filters (rated for 2.17 MGD each) • UV disinfection – 2.17 MGD design flow • Parshall flume/ultrasonic effluent flow meter • 400,000-gallon aerated sludge digester

The 2010 discharge requirement revisions by MoDNR necessitate that all wastewater treatment facilities treat sewage with secondary, biological processes before discharging to receiving streams. Without a means of measuring discharge volumes from Outfall #002, it is not possible to accurately calculate the additional treatment capacity needed at the WWTP to handle anticipated wet-weather flows. From the information proved by plant staff, a maximum discharge volume from Outfall #002 is noted as 594,000 gallons per day for occasions in which the lagoon is discharging all day. The typical procedure is for the diversion weir from the plant to the lagoon to be set ahead of time, in anticipation of rain, so the plant does not take on more than a 1.2 MGD flow through the mechanical processes.

Project No. 014-2994 12 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

V. HYDRAULIC CAPACITY EVALUATION

A. Water Use and Wastewater Treatment Facility Flow Monitoring To better determine the effects that I&I is having on the system, water usage from the city’s groundwater wells was compared to wastewater flow measurements to quantify the volume of water entering the sewer system that is over and above the volume expected due to normal customer use. Three sources of information were analyzed to determine the level of I&I reduction necessary to mitigate the need for discharges from Outfall #002 – 1) historical information regarding daily drinking water and wastewater volumes, 2) WWTP influent flow rates during the recent 2015 flow monitoring, and 3) WWTP flow monitoring rates measured in 2011. From a comparison of flow rates from historical dry-weather periods, customer water usage, and recent influent monitoring, it is possible to establish an estimated I&I volume for the wastewater system during wet-weather events and devise a level of necessary mitigation.

First, information was analyzed for five full calendar years of 2010 to 2014 regarding the water volume pumped from the City-operated drinking water wells, the water volume billed to customers, and the wastewater volume discharged from the WWTP. For comparison, the water pumped from the wells was used as the basis for water placed into the sanitary sewers as metered water billings do not always reflect accurate usage. Tabulated information regarding well water pumped and water billing can be found below in Table V-1.

TABLE V-1: ESTIMATED POPULATION VERSUS WATER DATA FOR 2010 TO 2014 Estimated Historic & Water Pumped Metered Water Sold Population Year Projected Using 1.4% Calculated Calculated Population Yearly Total Yearly Total Growth Rate GPD/person GPD/person 2010 3,266 191,394,000 161 107,534,735 90 2011 3,312 183,819,000 152 110,402,624 91 2012 3,358 174,151,700 142 104,812,545 86 2013 3,405 164,828,312 133 105,841,626 85 2014 3,453 173,183,000 137 107,446,771 85 Average 145 87

Due to the large discrepancy between well water pumped and water sold to customers, an average of the two was taken as a probable volume placed into the sewers. This was assumed as the cause of the variance could not be readily determined and a review of the water system is quite extensive, which is not within the scope of this wastewater plan. The average of the two water categories above calculates out to be roughly 116 GPD per person.

For comparison with the average water usage for the service area, the average WWTP effluent volume was calculated to determine daily system wastewater flows. Effluent data is collected daily from the WWTP as the treated water passes through a Parshall flume monitored by an ultrasonic meter. Additionally, precipitation levels measured from a rain gauge located at the WWTP were also analyzed. A summary of the recorded information for 2010 through 2014 is provided below in Table V-2.

Project No. 014-2994 13 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-2: RECENT SUMMARY OF WWTP EFFLUENT FLOWS AND AREA PRECIPITATION.

Wastewater Effluent Flows Outfall #001 Outfall #002 Outfall Total Year Month Daily Avg Daily Max Daily Avg Daily Avg Rainfall (GPD) (GPD) (GPD) (GPD) Jan 851,032 1,096,000 126,935 977,968 2.60 Feb 889,000 1,080,000 119,321 1,008,321 1.78 Mar 973,032 1,175,000 294,613 1,267,645 3.60 Apr 884,300 1,102,000 189,767 1,074,067 2.72 May 964,467 1,104,000 270,600 1,235,067 6.39 Jun 841,129 1,102,000 69,065 910,194 2.99 2010 Jul 819,806 1,108,000 0 819,806 3.89 Aug 741,806 940,000 0 741,806 1.09 Sep 815,467 1,070,000 59,400 874,867 7.86 Oct 678,452 821,000 0 678,452 1.10 Nov 707,533 1,134,000 0 707,533 1.83 Dec 618,839 760,000 0 618,839 0.54 Avg 815,405 1,041,000 94,142 909,547 36.39 Jan 380,806 502,000 0 380,806 0.62 Feb 466,964 658,000 0 466,964 6.05 Mar 555,387 746,000 0 555,387 3.99 Apr 653,867 989,000 184,800 838,667 13.03 May 908,467 1,020,000 412,900 1,321,367 8.06 Jun 682,355 957,000 181,226 863,581 1.95 2011 Jul 545,677 670,000 0 545,677 0.88 Aug 579,387 1,024,000 0 579,387 3.82 Sep 618,500 998,000 0 618,500 7.81 Oct 507,742 736,000 0 507,742 2.93 Nov 597,533 836,000 59,400 656,933 6.57 Dec 666,129 1,168,000 38,323 704,452 2.86 Avg 596,901 858,667 73,054 669,955 58.57 Jan 582,226 678,000 0 582,226 1.18 Feb 577,655 744,000 0 577,655 2.15 Mar 715,742 999,000 135,742 851,484 4.46 2012 Apr 629,567 802,000 0 629,567 4.12 May 558,167 729,000 0 558,167 1.18 Jun 471,129 726,000 0 471,129 1.45 Continued on next page

Project No. 014-2994 14 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-2 (CONT’D): RECENT SUMMARY OF WWTP EFF. FLOWS AND AREA PRECIPITATION Wastewater Effluent Flows Outfall #001 Outfall #002 Outfall Total Year Month Daily Avg Daily Avg Daily Avg Daily Avg Rainfall (GPD) (GPD) (GPD) (GPD) Jul 443,710 494,000 0 443,710 1.35 Aug 452,516 594,000 0 452,516 3.65 Sep 454,000 641,000 0 454,000 3.82 2012 Oct 483,806 623,000 0 483,806 3.50 Nov 474,467 670,000 0 474,467 0.86 Dec 569,742 1,095,000 0 569,742 2.14 Avg 534,394 732,917 11,312 545,706 29.86 Jan 543,226 655,000 0 543,226 5.09 Feb 562,214 798,000 0 562,214 2.38 Mar 694,032 872,000 0 694,032 4.61 Apr 893,133 1,090,000 136,133 1,029,267 6.07 May 920,967 1,112,000 107,267 1,028,233 8.82 Jun 786,903 1,028,000 180,032 966,935 0.85 2013 Jul 615,355 1,026,000 0 615,355 8.19 Aug 873,548 1,113,000 274,258 1,147,806 5.35 Sep 586,567 791,000 0 586,567 4.48 Oct 691,516 904,000 0 691,516 5.01 Nov 755,967 1,051,000 0 755,967 1.87 Dec 630,935 891,000 0 630,935 2.15 Avg 712,864 944,250 58,141 771,005 54.87 Jan 755,516 1,595,000 0 755,516 0.85 Feb 669,107 875,000 0 669,107 0.04 Mar 640,613 943,000 0 640,613 1.59 Apr 624,300 959,000 0 624,300 2.29 May 600,833 867,000 0 600,833 3.38 Jun 669,129 867,000 0 669,129 6.67 2014 Jul 536,323 695,000 0 536,323 2.35 Aug 546,871 778,000 0 546,871 3.24 Sep 696,667 972,000 0 696,667 4.19 Oct 819,613 1,101,000 0 819,613 10.37 Nov 682,367 930,000 0 682,367 2.19 Dec 697,645 871,000 0 697,645 2.60 Avg 661,582 954,417 0 661,582 39.76 60-month Average 664,229 906,250 47,330 711,559 43.89

Project No. 014-2994 15 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

As shown in Table V-2, over the recent 60-month period, the average effluent flow from the mechanical WWTP is approximately 0.66 MGD, and a peak single day treated flow of 1.6 MGD was recorded. However, peak WWTP flow values are limited by the fact there is no means of measuring volumes diverted to the lagoon. A maximum value of 594,000 gallons is listed as volume discharged from Outfall #002 into Flat Creek.

Precipitation values are included in Table V-2 to correlate rainfall with increases in sanitary sewer flows. Most notably are periods of heavy precipitation such as April and May of 2011. A total rainfall of over twenty inches (20”) of rain fell during that two-month period, nearly half of the average yearly precipitation for the area, during which the WWTP saw large increases in flow volumes. It should be noted that precipitation events may have occurred at the beginning or ending of a month, so though a high rainfall level was recorded for a particular time period, the effects may have been experienced during the following month. Thus, adjacent months should be considered when evaluating the effect I&I has on the system.

Dry periods also give perspective on the effect rainfall has on treatment plant flows as the plant saw its lowest ratio of wastewater-to-water in January of 2011, when that month and the previous month totaled only slightly over one inch of precipitation. During this time, but not exclusively for this period only, the system actually registered lower volumes at the plant than water pumped from the wells. This was evidenced throughout much of 2012 when the area experienced a significant prolonged drought. It also indicates the wastewater collection system is likely losing flow to the surrounding soil through defects in the system.

Though the recorded WWTP effluent data (Outfall #001) do not fully portray the effects of wet- weather events due to the lack of diverted flow and Outfall #002 data, it is possible to utilize the flows during prolonged dry periods to establish a baseline for dry-weather system flows. Accordingly, data was evaluated for the five months with the lowest average monthly effluent and is summarized below in Table V-3. The result is that recent dry-weather sewer flows can be approximated as 440,000 GPD.

TABLE V-3: DRY WEATHER WWTP EFFLUENT FLOWS

Precipitation Average WWTP Year Month (inches) Effluent (GPD)

2011 Jan 0.62 380,806 2011 Feb 6.05 466,964 2012 July 1.35 443,710 2012 Aug 3.65 452,416 2012 Sep 3.82 454,000 Average 3.10 439,579

Project No. 014-2994 16 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

From the dry-weather flow volumes shown in Table V-3, the average flow of wastewater discharged by the WWTP per person during dry periods can be calculated based on the population estimates shown in Table V-1. These calculations are summarized in Table V-4, and result in an average daily dry-weather wastewater flow of 132 GPD/person.

TABLE V-4: AVERAGE DAILY DRY WEATHER WASTEWATER EFFLUENT PER PERSON

Estimated Average WWTP Average Daily WW Year Month Population Effluent (GPD) Flow (GPD/person)

2011 Jan 3,312 380,806 115 2011 Feb 3,312 466,964 141 2012 July 3,358 443,710 132 2012 Aug 3,358 452,416 135 2012 Sep 3,358 454,000 135 Average 132

Drinking water usage between 2010 and 2014 was also considered. From the collected data, the Percent Wastewater (discharged by Outfall #001 and #002) versus Water Usage (pumped by the wells) was calculated to represent the volume of wastewater being discharged every month compared to the amount of well water pumped into the drinking water system. Results of the wastewater-to-water comparison are presented in Table V-5. The total monthly rainfall received at the WWTP is also included in the table for perspective on wet-weather conditions.

Project No. 014-2994 17 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-5: WELL WATER USE AND WWTP OUTFALL COMPARISON FROM 2010 TO 2014 Average Percent Combined Average Daily Wastewater vs Outfall Well Water Precipitation Year Month Water Discharge Pumped (GPD) (inches) Pumpage (GPD) Jan 977,968 648,581 2.60 151% Feb 1,008,321 606,607 1.78 166% Mar 1,267,645 560,742 3.60 226% Apr 1,074,067 532,333 2.72 202% May 1,235,067 557,100 6.39 222% Jun 910,194 520,935 2.99 175% 2010 Jul 819,806 577,903 3.89 142% Aug 741,806 594,581 1.09 125% Sep 874,867 457,767 7.86 191% Oct 678,452 428,323 1.10 158% Nov 707,533 396,200 1.83 179% Dec 618,839 414,323 0.54 149% Total 909,547 524,367 36.39 173% Jan 380,806 476,555 0.62 80% Feb 466,964 391,986 6.05 119% Mar 555,387 352,717 3.99 157% Apr 838,667 388,552 13.03 216% May 1,321,367 389,638 8.06 339% Jun 863,581 437,857 1.95 197% 2011 Jul 545,677 481,870 0.88 113% Aug 579,387 430,242 3.82 135% Sep 618,500 436,414 7.81 142% Oct 507,742 375,655 2.93 135% Nov 656,933 353,290 6.57 186% Dec 704,452 319,222 2.86 221% Total 669,955 362,567 58.57 185% Jan 582,226 348,508 1.18 167% Feb 577,655 355,318 2.15 163% Mar 851,484 333,121 4.46 256% 2012 Apr 629,567 326,758 4.12 193% May 558,167 387,176 1.18 144% Jun 471,129 443,227 1.45 106% Continued on next page

Project No. 014-2994 18 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-5 (CONT’D): WELL WATER PUMPAGE AND WWTP OUTFALL COMPARISON FROM 2010 TO 2014 Average Percent Combined Average Daily Wastewater vs Outfall Well Water Precipitation Year Month Water Discharge Pumped (GPD) (inches) Pumpage (GPD) Jul 443,710 468,598 1.35 95% Aug 452,516 475,412 3.65 95% Sep 454,000 432,834 3.82 105% 2012 Oct 483,806 432,079 3.50 112% Nov 474,467 379,852 0.86 125% Dec 569,742 342,394 2.14 166% Total 545,706 395,195 29.86 138% Jan 543,226 336,363 5.09 161% Feb 562,214 355,896 2.38 158% Mar 694,032 318,675 4.61 218% Apr 1,029,267 342,724 6.07 300% May 1,028,233 364,679 8.82 282% Jun 966,935 376,096 0.85 257% 2013 Jul 615,355 420,037 8.19 147% Aug 1,147,806 403,774 5.35 284% Sep 586,567 419,012 4.48 140% Oct 691,516 362,440 5.01 191% Nov 755,967 378,035 1.87 200% Dec 630,935 370,864 2.15 170% Total 771,005 370,779 54.87 208% Jan 755,516 373,019 0.85 203% Feb 669,107 409,985 0.04 163% Mar 640,613 375,780 1.59 170% Apr 624,300 384,320 2.29 162% May 600,833 390,314 3.38 154% Jun 669,129 411,041 6.67 163% 2014 Jul 536,323 419,728 2.35 128% Aug 546,871 423,795 3.24 129% Sep 696,667 382,169 4.19 182% Oct 819,613 378,323 10.37 217% Nov 682,367 341,617 2.19 200% Dec 697,645 324,206 2.60 215% Total 661,582 384,424 39.76 172% Average 711,559 378,241 43.89 188%

Project No. 014-2994 19 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

Though the data in Table V-5 provide a good correlation between precipitation events and increases or decreases in wastewater handled by the treatment system, it is not possible to determine the true volumes of water being conveyed to the WWTP due to the unrecorded flow diversion to the lagoon. To better determine influent wastewater flow rates, and in preparation for this Master Plan as well as the 2012 BEP, the City installed a temporary flow meter in the influent line to the WWTP. Between May 9th and July 23rd of 2015, real time readings were logged by an ISCO LaserFlow meter for velocity, depth, and flow rate, every fifteen (15) minutes. This information, in accompaniment with Outfall #001 data, allows for an estimation of the wastewater volumes entering the lagoon.

For comparison with recent WWTP incoming flow, the data summarized in Table V-6 includes the tabulated daily influent flow volumes calculated from 15-minute readings, along with daily precipitation values, well water pumped, the calculated (estimated) lagoon influent flow, and the recorded lagoon effluent flow for each day during the 2015 influent flow monitoring period.

TABLE V-6: WWTP DAILY INFLUENT AND EFFLUENT FLOW DATA FOR MAY 9 – JULY 23, 2015. Estimated Recorded Well Water WWTP WWTP Precipitation Lagoon Lagoon Date Pumped Influent Effluent (inches) Influent Effluent (gallons) (ISCO) (gallons) (gallons) (gallons) 5/9/15 0.63 591,603 1,238,513 904,000 334,513 594,000 5/10/15 0.52 405,254 1,208,238 932,000 276,238 594,000 5/11/15 0 381,214 1,609,137 981,000 628,137 173,000 5/12/15 0 434,336 1,289,892 973,000 316,892 0 5/13/15 0.16 459,402 1,168,215 945,000 223,215 0 5/14/15 0.03 472,044 1,102,281 959,000 143,281 0 5/15/15 0.25 730,682 1,030,230 861,000 169,230 0 5/16/15 1.1 474,374 958,592 867,000 91,592 0 5/17/15 0 536,412 1,673,181 910,000 763,181 0 5/18/15 0.03 383,686 1,344,834 1,012,000 332,834 0 5/19/15 0 609,613 1,196,801 725,000 471,801 0 5/20/15 0.51 455,841 1,316,235 806,000 510,235 0 5/21/15 0 455,434 1,147,919 828,000 319,919 0 5/22/15 2.5 499,250 1,039,419 887,000 152,419 0 5/23/15 1.35 496,930 1,038,528 840,000 198,528 0 5/24/15 1.9 619,395 1,939,952 865,000 1,074,952 0 5/25/15 0.2 283,071 2,437,446 884,000 1,553,446 0 5/26/15 0.16 549,457 2,127,981 860,000 1,267,981 284,000 5/27/15 0 477,059 1,954,046 871,000 1,083,046 594,000 5/28/15 0.37 499,853 1,800,387 920,000 880,387 594,000 5/29/15 1.5 511,789 1,889,757 940,000 949,757 594,000 5/30/15 0 411,099 2,848,050 1,060,000 1,788,050 594,000 Continued on next page

Project No. 014-2994 20 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-6 (CONT’D): WWTP DAILY INFLUENT AND EFFLUENT FLOW DATA FOR MAY 9th – JULY 23rd, 2015 Estimated Recorded Well Water WWTP WWTP Precipitation Lagoon Lagoon Date Pumped Influent Effluent (inches) Influent Effluent (gallons) (ISCO) (gallons) (gallons) (gallons) 5/31/15 0 454,913 2,826,705 1,491,000 1,335,705 594,000 6/1/15 0 459,626 2,512,751 989,000 1,523,751 0 6/2/15 0 662,991 2,258,933 968,000 1,290,933 0 6/3/15 0 296,385 2,094,371 957,000 1,137,371 0 6/4/15 0 547,919 1,956,831 937,000 1,019,831 0 6/5/15 0 472,085 1,804,766 950,000 854,766 0 6/6/15 0 548,003 1,625,141 993,000 632,141 0 6/7/15 0 461,203 1,454,304 979,000 475,304 0 6/8/15 0 489,374 1,279,640 919,000 360,640 0 6/9/15 0 549,503 1,194,075 881,000 313,075 0 6/10/15 0 551,096 1,099,586 921,000 178,586 0 6/11/15 0 571,072 1,092,956 888,000 204,956 0 6/12/15 0.03 537,906 1,107,492 932,000 175,492 0 6/13/15 0.79 603,956 1,168,683 851,000 317,683 0 6/14/15 0.36 616,092 1,211,579 1,016,000 195,579 0 6/15/15 1.03 329,560 1,543,418 969,000 574,418 396,000 6/16/15 0.82 419,793 1,445,711 1,027,000 418,711 594,000 6/17/15 0.71 461,999 1,584,128 1,022,000 562,128 594,000 6/18/15 3.8 465,738 2,300,334 1,043,000 1,257,334 594,000 6/19/15 0 492,916 3,608,493 1,012,000 2,596,493 594,000 6/20/15 0 460,362 3,053,100 1,034,000 2,019,100 594,000 6/21/15 0 495,912 2,782,248 1,047,000 1,735,248 594,000 6/22/15 0 472,154 2,359,986 1,045,000 1,314,986 594,000 6/23/15 0 546,615 2,080,392 1,037,000 1,043,392 594,000 6/24/15 0 473,853 1,949,763 1,040,000 909,763 594,000 6/25/15 0 536,052 1,864,962 964,000 900,962 594,000 6/26/15 1.1 514,281 1,926,978 933,000 993,978 594,000 6/27/15 0 424,811 1,857,876 927,000 930,876 594,000 6/28/15 0 531,590 1,678,776 937,000 741,776 594,000 6/29/15 0 406,612 1,593,111 954,000 639,111 198,000 6/30/15 0 493,061 1,498,416 1,003,000 495,416 0 7/1/15 0.03 599,284 1,471,793 1,012,000 459,793 0 7/2/15 0.44 514,092 1,447,083 992,000 455,083 0 7/3/15 0.23 499,621 1,398,356 936,000 462,356 0 7/4/15 0.2 493,733 1,292,445 1,002,000 290,445 0 7/5/15 0 485,998 1,154,235 1,001,000 153,235 0 Continued on next page

Project No. 014-2994 21 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-6 (CONT’D): WWTP DAILY INFLUENT AND EFFLUENT FLOW DATA FOR MAY 9th – JULY 23rd, 2015 Estimated Recorded Well Water WWTP WWTP Precipitation Lagoon Lagoon Date Pumped Influent Effluent (inches) Influent Effluent (gallons) (ISCO) (gallons) (gallons) (gallons) 7/6/15 0.04 456,662 1,087,566 1,016,000 71,566 0 7/7/15 4.27 639,663 2,648,637 1,009,000 1,639,637 371,000 7/8/15 0.49 331,157 3,128,255 1,167,000 1,961,255 594,000 7/9/15 2.6 489,343 3,206,936 1,003,000 2,203,936 594,000 7/10/15 0 444,212 3,082,359 1,021,000 2,061,359 594,000 7/11/15 0 425,760 2,785,719 1,027,000 1,758,719 594,000 7/12/15 0 461,261 2,569,952 1,022,000 1,547,952 594,000 7/13/15 0 511,428 2,213,456 1,021,000 1,192,456 594,000 7/14/15 0 508,616 2,085,314 1,019,000 1,066,314 594,000 7/15/15 0 547,598 1,965,630 974,000 991,630 594,000 7/16/15 0 475,216 1,917,441 1,177,000 740,441 594,000 7/17/15 0 559,614 1,866,117 1,032,000 834,117 408,000 7/18/15 0 628,868 1,807,809 1,062,000 745,809 0 7/19/15 0 472,564 1,738,242 1,055,000 683,242 0 7/20/15 3 481,076 1,805,771 1,032,000 773,771 0 7/21/15 0.67 488,889 2,299,401 1,080,000 1,219,401 594,000 7/22/15 0.34 481,969 2,213,853 1,017,000 1,196,853 594,000 7/23/15 0.02 576,017 2,108,897 1,068,000 1,040,897 594,000 Average: 0.42 495,498 1,821,979 976,855 845,124 274,184 Maximum: 4.27 730,682 3,608,493 1,491,000 2,117,493 594,000 Minimum: 0.00 283,071 958,592 725,000 233,592 0

Rain events, like that which occurred on July 7th, demonstrate the delayed process in which the groundwater table affects the sanitary system. Though the highest rainfall occurred on July 7th, the highest volume discharged by the WWTP was on July 8th, the highest volume measured in the influent line was on July 9th, and Outfall #002 discharged for eight days after the rain stopped on July 10th. The average influent recorded was slightly over 1.8 MGD, well above the WWTP design capacity.

The blue highlighted cells of recorded WWTP Influent represent the thirty (30) consecutive days of highest flows from which to determine an average wet-weather influent flow rate of 2.13 MGD, which is nearly double the WWTP’s design capacity. During this 30-day wet period between June 18th and July 17th, on only one day (July 6th) did the plant influent meter record a lower volume than the design WWTP capacity of 1.1 MGD.

A graphical comparison of the tabular information presented in the above table is shown in Figure V-1 below, which shows how vastly different the well water pumped, WWTP influent, and

Project No. 014-2994 22 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

WWTP/lagoon effluent flows can be during wet-weather periods. The prolonged stretches of high influent flow after the rain has stopped are indicative of a severe infiltration problem rather than an inflow problem. The initial rehabilitation efforts, therefore, should concentrate on remedies to curb infiltration in the sewer mains.

FIGURE V-1: CASSVILLE WELL WATER PUMPED, WWTP FLOWS, AND RAINFALL.

During the 2015 influent flow monitoring, a maximum total day flow of 3.6 million gallons was recorded on June 19th. Instantaneous flows to the plant exceeded 4 MGD for short durations. The rain event that lead to the maximum flow during the monitoring period actually took place from June 12th to the 18th, over which time 7.5” of rain were recorded. With the data showing that even after the rain stopped on June 18th, influent levels continued to remain near or above 2.0 MGD until the next rain event on June 26th is an indication of just how much flow is related to infiltration rather than inflow. Had inflow been more of a factor, peak WWTP influent flows would occur very soon after the rainfall starts and then dissipate quickly once the precipitation event ends. A rain event of similar size to the June 2015 event was also experienced during the flow monitoring period in 2011, in preparation for the BEP report. For the 2011 rain event, a maximum day flow of 3.45 MGD was experienced. Comparisons of wet-weather flow volumes to population are summarized in Table V-7.

Project No. 014-2994 23 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-7: FLOW DATA PER CAPITA COMPARISON

Flow Flow Per Estimated Year Event Description Rate Person Population (MGD) (GPD/person)

2011-2012 Historical WWTP Effluent Dry-Month Flow 3,340 0.44 132 2011 WWTP Influent Monitoring Max Day Flow 3,312 3.45 1,042 2015 WWTP Influent Monitoring Max Day Flow 3,501 3.60 1,028 2015 WWTP Influent Monitoring Wet-Month Flow 3,501 2.10 608

Table V-7 demonstrates the wide fluctuation in flows experienced at the WWTP during dry and wet periods and provides data that is useful in determining an I&I reduction level for Cassville to work toward. The maximum day flow rates during the two monitoring periods (2011 and 2015) are also included in Table V-7 to show the recent consistency in max-day influent flows, but the dry- and wet-month flow rates listed establish the current extremes the WWTP can expect to experience in upcoming years. It is worth mentioning that the unsurcharged, full-flow capacity of the 24-inch sewer interceptor line leading to the WWTP is approximately 5 MGD, assuming minimum slope conditions.

The estimated range of WWTP influent flow rates for the projected service area populations was based on both dry-weather and wet-weather conditions. Table V-8 shows projected influent flows based on the per capita Historical WWTP Effluent Dry-Month Flow (132 GPD/person) and the per capita WWTP Influent Monitoring Wet-Month Flow (608 GPD/person) shown in Table V- 7 throughout the 10-year planning period. While the projected dry-weather flows are easily within the 1.2 MGD hydraulic capacity of the WWTP, the wet-weather flows need immediate mitigation in order to avoid filling up the lagoon and ultimately discharging from Outfall #002.

Project No. 014-2994 24 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-8: PROJECTED WWTP INFLUENT FLOW RANGES BASED ON DRY AND WET WEATHER PER CAPITA PROJECTIONS

Population Projected WWTP Influent (MGD) Year (from Dry-Weather Flow Wet-Weather Flow Table III-2) (132 GPD/Person) (608 GPD/Person) 2016 3,550 0.47 2.16 2017 3,600 0.48 2.19 2018 3,650 0.48 2.22 2019 3,701 0.49 2.25 2020 3,753 0.50 2.28 2021 3,806 0.50 2.31 2022 3,859 0.51 2.35 2023 3,913 0.52 2.38 2024 3,968 0.52 2.41 2025 4,023 0.53 2.45 2026 4,080 0.54 2.48

B. Wet Weather Flow Projections versus Hydraulic Capacity With an understanding of the current wet-weather flows experienced by Cassville’s collection system, the needed level of extraneous flow reduction can be quantified in order to eliminate discharges from Outfall #002 without having to increase WWTP capacity. Table V-9 tabulates the available treatment capacity flow per capita based on the existing WWTP hydraulic capacity (1.2 MGD) and the projected populations, and compares this capacity with the current per capita wet-weather flow to determine the level of flow reduction needed to stay within the capacity of the existing WWTP. As expected, as the population increases during the planning period, there is less capacity per capita available in the existing WWTP, and as an average, Cassville should strive to achieve a 50% reduction in wet-weather flows to allow future flows to stay within the treatment plant’s hydraulic capacity.

Project No. 014-2994 25 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE V-9: NEEDED WET WEATHER FLOW REDUCTIONS OVER THE PLANNING PERIOD

Available Flow Per Current Wet- Population Person Based on Percent Weather Flow Difference Year Plant Capacity of Reduction (from Per Person (GPD) 1.2 MGD Needed Table III-2) (GPD/person) (GPD/person) 2016 3,550 338 608 270 44% 2017 3,600 333 608 275 45% 2018 3,650 329 608 279 46% 2019 3,701 324 608 284 47% 2020 3,753 320 608 288 47% 2021 3,806 315 608 293 48% 2022 3,859 311 608 297 49% 2023 3,913 307 608 301 50% 2024 3,968 302 608 306 50% 2025 4,023 298 608 310 51% 2026 4,080 294 608 314 52% Average 48%

In consideration of the conclusions drawn from the recent and historical data analyzed, which include Cassville’s wet-weather conditions stem more from the effects of infiltration rather than direct inflow, and that a 50% reduction in wet-weather flows is needed, specific wastewater system evaluations and recommendations can be developed. The following section summarizes recent collection system investigations performed and the resulting system defects identified.

Project No. 014-2994 26 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

VI. RECENT CCTV EFFORTS AND IDENTIFIED PROBLEM AREAS

A. General The City of Cassville owns a sewer line jetter and a closed-circuit television (CCTV) camera and has dedicated two (2) full time employees to perform sewer line cleaning and operate the camera to inspect the sewer lines. As part of the investigative efforts associated with this Collection System Facility Plan, the City has recently inspected almost all clay sewer mains within the collection system, which are primarily located around the older sections of the City and in the vicinity of Flat Creek. DVDs of the inspections were presented to Olsson Associates for evaluation of lines, determination of defects, and prioritization of repairs. An evaluation of each DVD was logged in a spreadsheet with noted defects, start and finish manhole, pipe size and material, flow direction, and debris settling, and length of sewer line. The full spreadsheet can be found in Appendix A.

B. Observed Collection System Defects The following is a listing and description of the defects noted during the evaluation of the Cassville sanitary sewer collection system CCTV videos:

1. Cracked Joint – Perhaps the most common defect noted in the system, this is a crack originating from the joint between two pipes. The crack could be listed as minor, otherwise known as “hairline”, to major, which would indicate a large open crack with a visible gap. The crack can run radially around the pipe or parallel along the pipe.

2. Cracked Pipe – Though these cracks can also originate from the joint of the pipe, the distinction was made that the primary damage has occurred further along the pipe section. This was also applied to cracks that acted along multiple pipe sections as though the joint were not an obstacle and the damage continues from one pipe to the next.

3. Broken Pipe – Cracks in pipes can continue until sections of pipe become separated, allowing for the section to break away or fall out of place. This defect is noted if the cracked pipe has resulted in a hole. Minor broken pipes may be noted if the bell section of a pipe end has broken away, revealing easy access for groundwater. Severely broken pipes may include several square inches of missing pipe, with the surrounding material exposed.

4. Roots in Pipe/Lateral/Joint/Crack – This is also a common defect found in Cassville’s system. This defect refers to tree roots that have penetrated the system through an opening or joint in the system. Minor roots may be as small as blades of grass, indicating a small gap in a joint or separation along a crack; or major as some root curtains and root balls restrict flow by blocking a significant percentage of the pipe area, which can lead to line backups, SSOs, and debris settling, as well as prevent inspection completion.

5. Offset Joint – Joint separation and offsetting is common in older clay systems as joint seals fail and both piping and manholes settle. Gaps in joints allow flow to pass in and out of the pipe which can washout or erode surrounding material. The remaining void allows the pipe

Project No. 014-2994 27 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

to further settle, increasing the size of the gap or creating minor to moderate flow backups. Typical minor joint offsets are most easily noted when the CCTV camera jumps over joints. Major offsets allow visual inspection of the surrounding pipe material.

6. Inflow and Infiltration – Inflow is not typically noted as it would require televising during a rain event, which would impede inspection of the line due to high flow levels. Infiltration is more readily visible as raised groundwater levels may take many days to drop after a heavy rainfall event, allowing for greater opportunity to discover. Minor infiltration may be clear water dripping from a pipe joint and measured in fractions of a gallon per hour, or major infiltration appearing as a running faucet from a crack measured in gallons per minute. Varying degrees of infiltration were noted coming from several service lateral connections, cracks, joints, and manholes.

7. Settled Solids – Settled solids typically take the form of silty-sand material as well as other organic material that has fallen to the bottom of the pipe to restrict flow. These occur when pipe flows do not reach a scouring velocity, typically considered a minimum of two feet-per- second (2 fps). Minor settled solids were noted if the flow was low enough to visibly see the solids not clearing from the bottom of the pipe. Major settled solids occurred as a result of severely restricted flow from a blockage or pipe sag.

8. Debris – This includes a vast array of material located in the pipe that may restrict flow or even create an ever-increasing dam. A rock, small piece of pipe, or stuck bathroom tissue would be noted as minor. In a pipe not able to reach the necessary scour velocity, a small rock may accumulate floating bathroom tissue, baby wipes, hygiene products, trash, or other material, causing flow backups that can be several feet long. Large debris can also cause issues even if cleared from the collection system as the materials listed above can shorten pump impeller life and, occasionally, block impellers from spinning. Multiple municipalities have filed complaints with companies that produce “Flushable Wipes” and some have gone so far as to file legal action as this label is wrong. The flushable wipes do not break down as readily as bathroom tissue and rapidly accumulate at any snag point.

9. Broken Invert – Some manholes in the inspections were noted to have broken inverts, or a half-pipe section at the bottom of the manhole. A minor break would have been noted if the invert was cracked, while a major break was noted if a section of the concrete invert or clay pipe material along the invert was missing.

10. Grease – Typically, grease is flushed away with the flow as emulsifiers, such as soap and laundry detergent, keep the grease suspended until treatment. However, users that flush high volumes of grease – be it a restaurant with no or a poorly-functioning grease trap or a resident that improperly disposes of it after cooking – can cause grease deposits that can restrict flow in service laterals to the point of complete blockage and/or create buildup in system lines that restrict flow and result in settled solids upstream. The City does utilize a degreaser when needed and has a monthly grease trap program.

Project No. 014-2994 28 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

Review of the City’s sanitary sewer video logs provided insight into the condition of the system and the steps to be performed to alleviate the issues. In general, many of the clay pipes located throughout the older areas of the City exhibited cracks, root intrusion, grease and debris build- up, as well as joint offsets. Where appropriate, the defects were described as slight, minor, moderate, major, heavy, etc. to indicate the severity of the issue. Though visual I&I was not documented frequently, the potential for I&I is still evident, as video inspections benefit from dry- weather conditions in order to reduce the volume of water in the system, thus providing better visibility of the pipes. Pipes with flow depths over forty percent (40%) are considered too full to perform a proper visual evaluation.

Project No. 014-2994 29 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

VII. PROJECT ALTERNATIVE ANALYSIS

A. Repair Alternatives In addition to the wording used to describe the severity of the defects observed through review of the CCTV video, each sewer line segment was assigned a “Priority” number from one through five (1 – 5), with five (5) being the highest priority for correction. Many minor defects do not require restoration at this time, but were noted for monitoring in future evaluations. Ten potential sewer rehabilitation techniques were considered for appropriate application, implementation, and cost in order to recommend the best-value alternative for the line segment deficiencies observed. A listing of the rehabilitation techniques is as follows:

1. Open-Cut Replacement – This involves the replacement of the entire sewer line segment by means of excavation. This is typically the most costly alternative as the method is very invasive, oftentimes requires bypass pumping, and can require restoration of other infrastructure such as streets, sidewalks, curb and gutter, utility poles, and driveways.

2. Open-Cut Point Repair – This method is applied to a small section of pipe in need of replacement. Commonly, this involves excavating and repairing a small section of collapsed line or severely offset joints in areas where there will be minimal above-ground disturbance.

3. Cut Protruding Tap – Occasionally a service connection will have protruded into the main pipeline which causes an obstacle for the CCTV camera and restricts the flow. Correction requires use of a rotating circular cutting tool at the end of a jetting hose to saw through the tap, leaving the lateral connection more flush with the main pipeline wall.

4. Cured-In-Place Pipe (CIPP) – This trenchless method of rehabilitation requires the use of large, specialized equipment and material that is traditionally not cost effective for direct purchase by a city, but rather lends itself to contracting with a specialized company for installation. The process begins by cleaning the line segment before an equipment truck parks on each manhole at either end. One truck contains a “liner” of inside-out pipe fabric that is impregnated with a hardening resin. The liner is inflated into the line, inverting into the proper orientation as it travels through the line. Once the liner is in place, the crew begins curing the resin by attaching a steam blower to one end. The steam heats the resin, causing the new liner to harden. The service connections associated with the host pipe are then re-instated with a robotic saw that cuts a hole in the cured liner at the exact location of each service connection. Since CIPP liners do not adhere tightly to the host pipe walls, groundwater that enters the host pipe can still track along the outside of the liner and will eventually enter the liner through the hole associated with the re-instated service connections. To avoid this, it is oftentimes prudent to also install a cured-in-place lateral connection repair (LCR) at each service connection after the CIPP process is complete.

5. Cured-In-Place Lateral Connection Repair (LCR) – Similar in concept to the CIPP liner, but using different trenchless installation equipment and a 100%-solids hardening resin, this rehabilitation technique installs a short T-shaped liner in the main line at the location of the

Project No. 014-2994 30 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

service connection and inverts a portion of the liner about 12”-18” up into the service lateral. The resin binds the LCR liner to the CIPP liner and the adjacent service connection piping well enough to resist significant infiltration into the service connection point as a result of water tracking along the host pipe. Similarly, a bad service line connection (cracked, offset joint, etc.) with a structurally-sound sewer main can also permit groundwater and root intrusion, and would only require a short LCR liner to remedy, regardless of whether the sewer main was CIPP-lined. Trenchless sewer rehabilitation companies can also install longer lengths of lateral liners if damage to the service lateral is extensive.

6. Cured-in-Place Pipe End Seal – Cured-in-place pipe end seals are used to trenchlessly repair the sewer main’s connection to a manhole. These are installed at the main-to- manhole interface, extend a couple feet into the sewer main, and utilize a 100%-solids bonding resin just like the LCRs.

7. Cured-In-Place Point Liner (CIP Point Liner) – This method of trenchless, cured-in-place liner utilizes equipment already owned by the City of Cassville, thus drastically reducing costs compared to contracting out. A CIP Point Liner is a short section, typically 4’-6’ long, that utilizes a 100%-solids resin to adhere to the walls of the host pipe to repair short- spanning defects. CIP point liners can be used in series to rehabilitate longer cracks or breaks, averting the cost of a full manhole-to-manhole CIPP liner.

8. Manhole Relining – Relining a manhole can be achieved by different methods, but the most cost effective means at this time is by grouting. With grouting, a crewman will enter the manhole and trowel a waterproof grout onto the entire interior surface of the manhole; from the invert to the lid. Proper installation has effectively eliminated manhole leaks without the need for specialized equipment for liners or epoxies, or for full manhole replacement.

9. Joint Inspection and Grouting – This trenchless sewer rehabilitation method is an alternative to CIPP-lining and is also being used in several cities throughout Missouri. To implement this technique, the sewer lines are first cleaned to provide a smooth surface for pressure testing. The key piece of equipment used for this method is a pressure-testing and grout- filling cylinder that just fits inside the sewer line. On both ends of the cylinder is a rubber plug that inflates to seal the joint section being tested. If the joint fails a pressure test, grout can be injected through the cylinder, into the joint, and out into the substrate to fill any void space just outside the pipe to seal . The grout sets quickly to allow the equipment to proceed to the next section for testing and repair.

10. Lateral Connection Grout Repair – As with sewer main joint testing and grouting, lateral connection grout repair uses specialized equipment to first pressure test and then grout- repair, as needed, lateral connections to the sewer main. This technique allows for the filling of broken connections, cracked lateral pipes (to the extent of the equipment), and failed gasket seals. The equipment is slightly different from the sewer main joint cylinder in that a testing and grouting liner is first inflated into the service lateral to create a pressure- testing seal and provide a mold for grouting, if necessary.

Project No. 014-2994 31 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

B. Gravity Main Lines The City of Cassville CCTV-videoed nearly 300 VCP gravity lines, from which 264 defects were identified. Such a high percentage of defects to inspections reveals the need for significant rehabilitation and a prioritized plan of action to implement the repairs. As each line of CCTV video was reviewed, consideration was placed on the importance of addressing the deficiencies observed and a priority number from one to five (1-5) was given; with five (5) being the most severe. The highest-priority lines exhibited a need for near-term attention as the defect is currently preventing proper system operation. A common example would be roots or debris blocking over half of the cross-sectional area of a sewer line, causing backups during normal flow conditions. Generally, most of the high-priority issues can be temporarily addressed with heavy-duty line cleaning, and then follow-up with CCTV inspection to determine which rehabilitation method to implement thereafter.

Following the high-priority cleaning and re-inspection, a plan to systematically rehabilitate the next priority gravity lines can be implemented. Development of the rehabilitation plan recommended in this report first involved the determination of which areas are most likely to experience I&I in the system, with an emphasis on the areas most subject to infiltration. Though a crack may be larger in one pipe than another, location of the pipe should be taken into account when determining repair benefits.

Accordingly, it appears the City can achieve its greatest value for wet-weather flow reduction by concentrating initial rehabilitation efforts on the low-lying areas of the collection system that lie along the floodplain associated with Flat Creek and its tributaries. To this end, a “Saturation Zone” was identified within the service area, where the highest levels of infiltration are likely to occur. Topographic contour lines, floodplain maps, and the location of gravity sewer lines were used to delineate the Saturation Zone, in which to concentrate the next-highest priority of rehabilitation efforts. Within the Saturation Zone, sewer lines are likely to remain in contact with the shallow groundwater table for days or weeks after a rain event, allowing persistent infiltration through defects in the piping and associated manholes. A map of the Saturation Zone can be found in Exhibit 3.

The Saturation Zone primarily includes areas within and along the Flat Creek floodplain, consisting of a total gravity-line length of nearly 100,000 feet. A summary of the system within the Saturation Zone and the remaining Outer Zone can be found in Table VII-1. All of the lines associated with the area serviced by the Sherwood Forest Pump Station are in the Outer Zone.

Project No. 014-2994 32 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE VII-1: SEWER LINE INVENTORY FOR SATURATION ZONE AND OUTER ZONE

Approximate Sewer Lengths Basin Gravity ID Force Saturation Zone Outer Zone Total Main A 20,848 19,583 40,431 0 B 11,911 17,024 28,934 953 C 6,145 8,895 15,040 0 D 4,233 11,151 15,384 0 E 22,670 6,977 29,647 0 F 2,553 14,138 16,691 0 G 24,066 1,132 25,198 0 TOTAL 92,426 78,899 171,325 953

After developing the CCTV review records, specific rehabilitation efforts were itemized within the Saturation Zone and the Outer Zone. However, with the wide-array of defects identified through review of the CCTV videos, as well as an understanding of the impact infiltration has on the observed wet-weather flows in Cassville, a repair strategy of joint and service connection pressure-testing and grouting is recommended to address the broadest range of issues expected in the Saturation Zone. Implementing a plan to test the gravity lines within the Saturation Zone will also provide additional inspection details regarding defect repairs which are not applicable to grouting. As the joint testing is conducted, more severe defects can be noted while completing the line inspections that were initially hindered due to blockages. Though some defects will require various degrees of additional attention, a broad-stroke action of joint- testing and grouting is expected to address the majority of gravity line defects in the Saturation Zone, and provide the greatest value for the City’s rehabilitation investment.

C. Service Line Connections Three primary methods of addressing defective service line connections have been noted in the CCTV inspection report: 1) cured-in-place lateral connection repair (LCR), 2) pressure-testing and grouting, and 3) open-cut repair. Additionally, some connections appear to have been abandoned and can be removed as sources of I&I by installing a CIP point liner. As gravity line joint pressure-testing and grouting is implemented, the City should concurrently pressure-test and grout service connections.

Beyond the service connection, correcting defective service lines have been an issue for municipalities for decades as I&I sources are rarely addressed beyond the connection point, which typically extends onto private property. Some attempts have been made previously with smoke testing and building inspections to locate defects, but property owners are generally not inclined to participate in rehabilitation programs.

Project No. 014-2994 33 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

More recently, MoDNR and municipalities have been teaming up to provide funding for repairs through grants that offset customer rate increases. With this method, the State, City, and customers shoulder a share of the financial responsibility to perform repairs on a completely voluntary basis. Every property owner is given multiple opportunities for an inspection team to locate any possible source of I&I beyond the connection to the sewer main. Sources of I&I are addressed through a third party plumber that has agreed upon a fee schedule of each issue. The property owner is not contractually obligated at any time to continue with the program and any grievances are alleviated as soon as possible. No direct cost is associated to the property owner, though they receive services they may not have been financially capable of providing themselves. The City sees the reduction in system loading during wet-weather conditions along with a reduction in treatment costs as volumes decrease. The City also benefits from reduced sanitary sewer overflows and an increase in the useful life duration of the existing WWTP capacity.

D. Manholes Also located within the Saturation Zone are approximately 300 manholes. Though manhole condition was difficult to determine based on the low light provided by the CCTV sewer line camera, several manholes were noted to have defects, including but not limited to: infiltration, broken inverts, and visible sunlight through structure. An inventory of the system manholes within the Saturation Zone and Outer Zone is provided by individual basin below in Table VII-2.

TABLE VII-2: SATURATION AND OUTER ZONE MANHOLE INVENTORY

Approximate Number of Manholes Basin Saturation Outer ID Total Zone Zone

A 70 76 146 B 38 75 113 C 30 20 50 D 22 48 70 E 77 25 102 F 16 45 61 G 90 8 98 TOTAL 343 297 640

The City has already begun a manhole inspection program, with a total of sixty-nine inspected thus far. Continuing this program with a focus on the Saturation Zone will provide a means of prioritizing manhole rehabilitation so immediate needs can be addressed in the short-term. A modest schedule of manhole rehabilitation of thirty-five (35) manholes per year for the next ten years is recommended to address issues associated with I&I at the manholes.

Project No. 014-2994 34 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

VIII. RECOMMENDED PROJECT ALTERNATIVE SUMMARY AND JUSTIFICATION

A. Recommended Rehabilitation Alternatives (Years 1-5) Based on the observed deficiencies, pipe material, and topographic features, division of the collection system into the areas within and outside of a delineated “Saturation Zone” is recommended to guide the systematic rehabilitation of Cassville’s collection system. Approximate gravity sewer line lengths were compiled in Table VII-2 for both inside and outside the Saturation Zone. City staff have stated that two 5-year plans are desired to accomplish the recommended sewer rehabilitation on both the public and private portions of the sewer system. The following plans of action summarize the recommended rehabilitation efforts for years 1-5 and years 6-10.

1. Within the Saturation Zone The oldest parts of the City are located within close proximity to Flat Creek and its many tributaries, as access to water was paramount before the founding of Cassville. This has resulted in the aging system suffering the greatest negative effects in sewer collection lines located within flood plains, areas with shallow groundwater levels, and soil with high water retention times. The Saturation Zone was established to provide a basis for initial repairs that will achieve the greatest results toward reducing wet-weather infiltration.

Some of the gravity lines within the Saturation Zone are recommended to have specific repairs made, as determined through CCTV review; such repairs include both open-cut and trenchless point repairs as well as CIPP-lining of entire lines where the frequency and severity of defects necessitates full-pipe rehabilitation. For the remainder of the pipe located within the Saturation Zone, a systematic approach of pressure-testing and grout-filling of pipeline joints and service connections is recommended. This proposed rehabilitation will address the majority of issues discovered in the CCTV inspections as well as locate joint defects not previously detectable.

In addition, a systematic manhole rehabilitation program will provide further I&I reduction as many of the CCTV-reviewed manholes are constructed of concrete or brick masonry with deteriorated grout joints. Relining the manhole involves covering the entire interior surface with grout or epoxy to alleviate I&I. This rehabilitation effort is proposed for the entire system in order to address manhole deficiencies both inside and outside the Saturation Zone.

2. Outside Saturation Zone As stated above, a system-wide manhole rehabilitation program to address deficient structures is recommended. It is likely the majority of manholes are located within the Saturation Zone due to the age of the system in that area, but structures throughout the collection system should be investigated for deficiencies that are allowing I&I.

Project No. 014-2994 35 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

Due to the presence of VCP sewer lines outside of the Saturation Zone, some of the gravity lines reviewed for the project in the Outer Zone have also been recommended for repairs such as CIPP-lining, CIP point repairs, and LCRs, as well as open-cut repairs and additional cleaning and televising. Though these recommended sites of rehabilitation are located outside of the Saturation Zone, they have a high priority for corrective action.

B. Private Inflow and Infiltration Abatement (Years 6-10) Implementation of a program to inspect and evaluate the private connections to the wastewater collection system beyond the typical reach of the municipality can be beneficial to the homeowner, the City, and the state. A combined effort by all parties has been successfully implemented in other municipalities where previous efforts that put the burden of corrective action solely upon the private landowner have failed. Once a properly-funded program for private I&I abatement is established – and an emphasis by the City that the issues to be corrected are a community problem, not just a private owner problem – home and business owners are likely to be much more willing to cooperate for the common benefit.

The recommended method for implementing a private I&I abatement program begins with an estimated budget based on an expected number of repairs and an average cost per repair. Estimates for the number of repairs can be based on a number of factors – including the size of the area to be rehabilitated, the number of connections within the rehabilitation area, any previous inspection data, the required level of reduction, and the level of repair desired. Perhaps the most important, but least considered, is the level of repair desired. For this, the cost of the individual repair can vary greatly – for example, repairing a broken cleanout lid can included replacing the cover for less than $25 or be as involved as riser replacement and a vault enclosure costing over $250. The new cleanout lid will remove the opening as a source of I&I, but the vault enclosure will prevent the cleanout from being broken again.

The involvement of professional plumbers throughout the implementation process will aid in establishing a cost for repairs. Providing an opportunity for multiple plumbing companies to discuss a fixed rate structure for the project will help in establishing a project budget as well as a list of contractors for when the City is ready to institute repairs. The City directly contracting the repairs with a fixed price schedule has the benefits of ensuring specific criteria are met by the plumber such as experience, licensing, and bonding; work is performed to the standards established at the onset of the program; work is distributed fairly; and final payment is not made until completion of the repairs.

Buildings within the selected private rehabilitation area should be inspected by no less than two individuals trained to inspect plumbing fixtures and determine compliance. Assuring owners of the voluntary nature of the program and emphasizing the specific target of the evaluation has shown to result in greatly higher inspection rates and fewer conflicts with distrusting individuals. Additionally, every effort to inform the citizens in the area through newspaper notifications, public information meetings, radio and television outlets, and mailed or door-hung fliers provides reassurance of the legitimacy of the program. Periodic statistical updates regarding number of inspections and repairs will further assist with public awareness.

Project No. 014-2994 36 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

Once an inspection is performed and a deficiency is detected, the property owner should be given the opportunity to choose from the list of pre-selected plumbers prior to the City choosing. The plumber would be compensated the pre-agreed cost of the repair upon completion and final inspection by the city’s inspectors.

Planning for private I&I abatement should involve consideration of the successes and failures of other programs as well as an introspective look at the municipality’s own capabilities and limitations. For this Facility Plan, the cost of a private I&I abatement program was estimated from recent data collected for the City of Springfield, Missouri private I&I abatement program. In general, about one-third of the establishments inspected required some form of corrective action. In consideration of the labor cost for inspections and follow-up evaluations after repairs, in addition to the cost of the repairs themselves, the average cost of the program can be estimated at about $3,000 per establishment in which a deficiency was identified. This average amount also covers the cost of inspecting facilities in which a defect is not identified.

For Cassville, with about 1,500 sewer connections, a preliminary budget of $1,500,000 should be considered for a private I&I abatement program based on one-third of the sewer connections needing a $3,000 average investment. It may be advantageous for the City to take an approach similar to the public-side sewer system rehabilitation and concentrate initially on establishments in the Saturation Zone, where approximately half of the sewer connections are affected. However, since this area is the oldest part of town, the percentage of facilities with defects may be higher than 33%.

C. Cost Opinion for Proposed Rehabilitation An opinion of probable construction cost has been developed for the recommended collection system rehabilitation items for Cassville. No capital improvements involving the WWTP are being recommended in this report. The most significant and highest-priority improvements recommended involve pressure-testing and grouting sewer main joints and service connections within the Saturation Zone and addressing the critical issues noted during review of the recent CCTV videos. Following this initial effort and subsequent wet-weather flow analysis to determine the I&I reduction achieved through the improvements, a private I&I abatement program should be implemented.

Table VIII-1 presents an opinion of probable construction cost for each item of collection system rehabilitation recommended and compiles a total project cost in consideration of the non- construction costs associated with completing all of the proposed improvements as one project, should the City choose this route for budgeting and funding purposes. If complete-project funding cannot be procured, the rehabilitation can be completed incrementally as city funds allow, as each item works toward resolving one or more of the deficiencies identified. The unit costs associated with the rehabilitation efforts include consideration of the associated incidental items such as piping, pressure-testing, grouting, CIPP preparation, pipe bedding, and cleanup. The cost opinion presented in Table VIII-1 is based on available knowledge of the current bidding climate and is subject to change.

Project No. 014-2994 37 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

TABLE VIII-1: OPINION OF PROBABLE PROJECT COSTS FOR RECOMMENDED IMPROVEMENTS

Item Est. Item Description – Construction Costs Units Unit Price Price Extension No. Quantity

1 Bonding, Insurance, Mobilization (5%) LS 1 $ 130,000.00 $ 130,000.00

2 Open-Cut Point Repair EA 25 $ 3,500.00 $ 87,500.00

3 Cured-in-Place Pipe (Manhole-to-Manhole) LF 4,000 $ 25.00 $ 100,000.00

4 Cured-in-Place Lateral Connection Repair EA 50 $ 1,600.00 $ 80,000.00

5 Cured-in-Place Pipe End Seal EA 4 $ 500.00 $ 2,000.00

6 Pressure Test and Grout Joints LF 93,000 $ 17.00 $ 1,581,000.00

7 Pressure Test and Grout Lateral Connections EA 600 $ 400.00 $ 240,000.00

8 Clean and CCTV LF 45,000 $ 2.25 $ 101,250.00

9 Cut Protruding Tap/Gasket EA 20 $ 300.00 $ 6,000.00

10 Cured-in-Place Sectional Repair EA 113 $ 600.00 $ 67,800.00

11 Manhole Re-lining EA 343 $ 1,000.00 $ 343,000.00

12 Gravity Sewer Line Relocation/Replacement LF 1,000 $ 70.00 $ 70,000.00

13 New Manhole, Complete EA 10 $ 3,000.00 $ 30,000.00

14 Private I&I Abatement Program EA 500 $ 3,000.00 $ 1,500,000.00

Construction Cost Subtotal: $ 4,338,550.00

Item Est. Item Description – Non-construction Costs Units Unit Price Price Extension No. Quantity

15 Contingency (15%) LS 1 $ 650,450.00 $ 650,450.00

16 Legal & Administration (2%) LS 1 $ 86,000.00 $ 86,000.00

17 Review/Prioritization of New CCTV Videos LS 1 $ 50,000.00 $ 50,000.00

18 Engineering Design (5%) LS 1 $ 217,000.00 $ 217,000.00

19 Bidding and Construction Admin. (2%) LS 1 $ 86,000.00 $ 86,000.00

Non-Construction Cost Subtotal: $ 1,089,450.00

Opinion of Total Project Cost: $ 5,428,000.00

Project No. 014-2994 38 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

D. Funding Strategy and Impact on User Fees

Current residential sewer user rates are structured around per-month water usage volumes and charged under a single billing category for all sewer customers (residential, commercial, industrial, etc.). A base connection rate is applied regardless of volume used, with an additional cost, fractionally applied, calculated on each 1,000 gallons of metered water use. A summary of the City’s current billing rate structure effective as of February, 2015 is show in Table VIII-2.

TABLE VIII-2: CITY OF CASSVILLE CURRENT SEWER USER RATE SCHEDULE

Single Billing Billing Fee Category

Base Rate, Regardless of Volume $ 8.44

Cost per 1,000 gallons of Water Usage $ 6.67

Example Cost for 5,000 Gallons $ 41.79

Other revenues for the wastewater system include various account setup fees and late payment charges. The City should consider increasing the impact fee for new sewer connections, which currently consists of a $50 permit and inspection fee along with reimbursing the City its cost for the connection saddle materials. Impact fees should be assessed to bring equity between existing and new customers. By establishing and collecting cost-based impact fees, the City assures that “growth pays for growth” and existing utility customers will not have to shoulder an undue portion of the financial impact associated with new developments.

In consideration of the $5.4 million total project cost shown in Table VIII-1, if the entirety of this investment were to be financed through an increase in user rates, the monthly debt service per sewer connection would be approximately $22/month based on 1,600 connections and a 20- year loan term at 4.5% interest. With an existing monthly sewer bill of $41.79 based on 5,000 gallons of water use, the City may be able to position itself for some grant funding to complement the loan amount. Alternative funding sources and loan terms would of course alter the ultimate impact to user fees. Additionally, staging the project investment to first complete the public-side improvements before taking on the private I&I abatement program would allow the increase in sewer rates to be spread out over several years.

E. Proposed Rehabilitation Schedule

Based on the two 5-year plans outlined in this section and the associated financial impact and funding strategy needed to complete the recommendations, the following schedule is proposed for the City’s consideration:  January 2016 – Submit this report to MoDNR to fulfill the requirements of the Department’s Small Community Engineering Assistance Grant;

Project No. 014-2994 39 January 2016

City of Cassville, Missouri Wastewater Collection System Facility Plan

 Spring 2016 – Obtain 5-year time extension on VCA;

 Spring 2016 to Winter 2017 – City-performed rehabilitation and additional investigation with regards to stormwater impact on sanitary sewer flows;

 Spring 2017 – Hold bond election for sewer improvements funding, install permanent flow meter immediately upstream of WWTP influent lift station;

 Summer 2017 to Winter 2018 – Pending passage of bond election or other funding source, design sewer rehabilitation improvements;

 Spring 2018 to Winter 2020 – Construct sewer rehabilitation improvements;

 Spring 2020 – Conduct flow monitoring to measure impact of completed sewer rehabilitation improvements on I&I reduction, develop/finalize private I&I abatement program;

 Summer 2020 to Fall 2024 – Administer private I&I abatement program, obtain 5-year time extension on VCA, if needed;

 Spring 2025 – Conduct flow monitoring to measure impact of I&I reduction based on completed repairs/rehabilitation.

F. Conclusion

This facility plan presents a comprehensive Collection System Evaluation with recommended improvements to be completed over the next several years. The City requests that this evaluation and associated action plan replace the 2012 BEP submitted and approved over three years ago. During the last three years, a substantial amount of additional data was collected and analyzed to develop a more appropriate and specific strategy toward mitigating peak and prolonged wet-weather flows that could result in discharges from Outfall #002. This facility plan represents the City of Cassville’s new 5-year plan, and includes an additional five years of anticipated efforts to ensure the City is fulfilling its due diligence to eliminate bypasses from Outfall #002. Accordingly, the City respectfully requests the Department’s approval of the recommended plan of action and associated schedule over the next several years, and the replacement of the existing BEP with this facility plan.

Project No. 014-2994 40 January 2016

APPENDIX A CCTV Review Spreadsheet From DVD Chpt Month Year To MH LF Comments MH

Clay, low flow, good condition/joints w good joints until 125', then flow 100 1 74 73 8" backs up, broken pipe at 132' - video ends at 132'. GIS has 277'.

Point Repair at 132', video rest of line.

Clay, good condition/joints, some sags, pipe half full in areas, conn. @ 100 2,3 359 404 280 8" 101', minor cracks at 112', conn. with lots of roots @ 113', conn. @ 115', flow gets very low @ 125', conn. @ 212'.

Mainly just a couple of sags, MH404 looks good.

Cracked pipe at MH457, grease at top of pipe, pipe/joints good, minor offsets, some sags, minor cracked joints, conn. @ 28'., broken pipe @ 100 4,5 457 456 132 8" 31'-35', cracked pipe @ 102'-105', cracked pipe from 119'-125', minor crack/sag @ 127'.

Point Repair at 102'-105', 119'-125'.

8" clay that transitions to 8" PVC @ 13', then has a bend at 105'. Looks 100 6 457 ?? ? like thin-wall PVC and is deflected. Not sure on where this ends.

Discuss w/ City

Evidence of half-full, grease, minor crack @19', crack at 24', low flow, sags, pipe/joints good, PVC pt. rpr. @57'-65', sag downstream of PVC 100 7 422 40 438 8" to 83', minor crack at 100', sag & conn. & grease at 103', video ended at 105'.

Determine issue at 103'.

Starts with MH40?Clay, going downstream, to MH44 maybe? Minor 100 8 40? 44? 298 8" crack at 11', lots of grease buildup, a few long sags. Video stops at 125'.

Determine pipe location, consider replacing at constant slope.

"Rest of Sapp St." Starts at 342', clay. Very little flow, good pipe/joints. 102 1 43? 42? 306 8" Conn. w roots @ 394', conn. w roots/grease @ 410', conn. @ 487', conn. w roots @ 538', conn. @ 567', line ends @ 590' MH42.

No repairs needed, just jet out roots from conns.

"Trout Farm patch job". Not sure on location, appears to be a casing, 102 2 81? 82? 252? ? high-flow service connection or break at 35'.

More video of high-flow "break/conn." Transition to another pipe matl at 102 3 81? 82? 252? ? 49'. Trial patch???

Page 1 of 56 From DVD Chpt Month Year To MH LF Comments MH

102 4 81? 82? 252? ? "Trout Farm Patch Job Day 2". Prior to patch over high flow area.

"Trout Farm Patch Job Day 2" Shows city-applied CIP patch btwn 38'- 102 5 81? 82? 252? ? 40', effectively stopping leak. Another patch installed downstream???

"Sherwood Forest", PVC, very low flow, grease-stained pipe at 90'-95', 105 1 381 394 303 8" conn. @ 93', 115', 187', grease staining at 185'-189', conn. @ 203', again more grease, MH394 looks OK.

No repairs needed. Just keep cleaned of grease (low flow).

"Forest Cir", 20' PVC sticks, low flow, some settling, 6" service comes in 105 2 324 ?? 403 8" at 83', end at MH??unnumbered??

107 1 04/22/13 ?? ?? ?? ? "19th St." Half-full pipe, roots, stagnant water.

Short, unlabeled video.

Clay, very low flow, good pipe/joints, conn. @ 33', couple of capped 107 2 ?? ?? 204 8" factory taps (good cond.), conn. @ 57', 163', good pipe, but lots of roots in downstream MH#??

Inspect and determine repairs needed at MH.

Same Ch. 2, unsure on MH#, clay, very low flow, solids have settled 107 2 ?? ?? 295 8" (too flat), good pipe/joints, no connections. Downstream MH looks good, unlabeled on video.

Keep clean or look at re-laying at steeper slope.

107 3 ?? ?? 8" Short, unlabeled video. Camera submerged.

Short, unlabeled video. Downstream MH looks OK, there is another inlet 1074 ????408" pipe to MH, minor debris in MH.

No repairs needed.

Clay, conn. @ 5' w some roots, conn. @ 6' w roots, slightly damaged 107 5 ?? ?? 8" factory tap at 7', very low flow, settled solids, video shows rodding service @ 6'.

Page 2 of 56 From DVD Chpt Month Year To MH LF Comments MH

Clay, fast low flow, good pipe/joints, slight sag @ 82', conn. @ 107' w slight sag, small crack w roots at 133', roots in some joints, conn. @ 107 6 ?? ?? 395 8" 288'-w good flow, downstream MH good except maybe damage on bottom - check.

Check downstream MH bottom for damage, infiltration.

Same chapter, continue down line, sag in pipe first 45', about half full w stagnant water, some grease build up, couple of slight sags, good 107 6 ?? ?? 376 8" pipe/joints, line has good flow (~1/4 full), conn. @ 306', downstream MH OK, has additional inlet pipes.

No repairs, keep clean of grease, settled solids.

107 7 318 317? 8" Clay, very low flow, settled debris, slight roots in joints, short video.

See Ch. 8 below.

Video'd again, debris cleaned out, still roots in joints, very low flow (stagnant, flat pipe), slight offset joint at 48' (PVC pipe repair), conn. @ 107 8 318 317? 355+ 8" 123', 140', 159', 182', 272', settled debris @ 355' (pipe may be unbelled here), inspection stopped @ 355' (not end of line).

Finish videoing line, thus far, no obvious repairs, keep clean of grease, settled solids.

"Hwy 248", clay, VERY low flow, flat pipe, good pipe/joints, downstream 108 1 267 8" MH looks good (block, unnumbered).

"Hwy 248", clay, very low flow, flat pipe, good pipe/joints, good 108 2 133 8" downstream block MH (unnumbered), straight-thru.

"Hwy 248", same chapter, continue downstream, flat pipe, good clean pipe/joints, slight sag at 20'-50', also at 70'-100', small crack at 137', conn. @ 210', minor cracks and compress pipe at 212'-216', also at 108 2 8" 223' (all minor though), slight sag @ 280'-290', minor crack @ 312', slight sag @ 337'-350', conn. @ 343', slight sag @ 363'-378' (settled solids), video ends @ 387'.

Nothing too significant, keep clean of settled solids.

"Hwy 248", clay, VERY low flow, good pipe/joints, conn. @ 33', 65', 108 3 153 297 373 8" 200'. Downstream block MH looks good, holes in lid, straight-thru piping.

No repairs, just keep clean of settled solids.

"Hwy 248", same chapter, continue to downstream pipe, inspection 108 3 297 298 ?? 8" ended at 47' (not end of pipe).

No repairs, just keep clean of settled solids.

Page 3 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Hwy 248", clay, very low flow, CCTV upstream, good pipe/joints, a few 108 4 396 8" slight sags, nothing significant, minor pipe break @ 258', no conn., straight thru downstream block MH.

Consider CIP pt. rpr. @ 258'.

"Hwy 248", clay, low flow, flat slope, good pipe/joints, few minor sags, conn. 125', major infiltration 181'. PVC repair around 187'-197', grease 108 5 ?? ?? 384 8" build up downstream of 300', conn. w/roots 373', downstream block MH looks fine, holes in lid.

Patch over I&I @ 181', keep clean of settled solids.

"W 15th to W 14th", clay, minor broken pipe within 5', very low flow, flat pipe, good pipe/joints, some grease, conn. @ 150' w/lots of grease, very 108 6 ?? ?? 216 8" minor roots in joints, conn. @ 205'. DS block MH looks fine, straight- thru.

Degrease lateral at 150', keep clean.

"W 15th to W 14th", clay, same chapter-continue down line, conn. w/minor roots @ 2', good pipe/joints, very minor roots in joints, very low 108 6 ?? ?? 118+ 8" flow, minor broken pipe @ 43', roots in joints at 92'&98' should be cut out. Inspection ended at 98' (not end of pipe).

Consider CIP pt. rpr. @ 43', cut roots, keep clean.

"L1 SP", clay, conn. <5', settled debris/gravel, low flow, flat, good pipe/joints, evidence of 3/4 pipe flow, conn. @ 71', 83', 145', 195', 108 7 ?? ?? 410 8" significant flow from service at 206' - inspect; conn. @ 229', 269', 270', sig. sag from 360'-400' due to piled up debris at 400'.

Clean debris out, routinely clean. Inspect service at 206'.

"13th to Vine", clay, low flow, CCTV upstream, good pipe/joints, 6" conn. @ 63', grease in line, inflitration in joint @ 91', conn. @ 140', 108 8 337 464 245 8" minor crack @ 189', upstream block MH appears OK but has minor infiltration at bottom; straight through piping.

Keep clean, patch over infiltration @ 91', grout MH 464 to seal out infiltration.

"13th St. to Wildwood Dr", clay, CCTV downstream, good pipe/joints, low flow, conn. @ 37' w/infiltration, minor crack @ 84', sig. crack @ 108 9 337 338 255 8" 103', grease along bottom, block MH338 has daylight coming through corbel, signs of water from top.

LCR @ 37', keep clean, patch cracks @ 84'&103', repair MH338.

Downstream to drop MH, in clay, low flow, good velocity, good 109 1 338 ?? 368 8" pipe/joints, some grease build-up. Evidence of half full. Joint crack at 145'. Conn. @ 203'.

Consider Pt. Rpr. at 145', keep clean of settled solids and grease.

Page 4 of 56 From DVD Chpt Month Year To MH LF Comments MH

Very low flow, upstream, grease, flat slope, good pipe/joints (20' PVC?). 109 2 ?? ?? 360+ ?? No conns. Video did not reach end of line.

No repairs needed, just keep clean of settled solids and grease.

Clay, downstream, very flat, settled solids/grease, good pipe/joints, 1093 ???????? evidence of grease on crown of pipe.

See chapter 4 below.

5' Clay, downstream, very flat, settled solids/grease, good pipe/joints, 1094 ???????? evidence of grease on crown of pipe.

No repairs needed so far, finish clean/video, keep clean of settled solids and grease.

Downstream, low/fast flow, good pipe/joints, 5' clay, clean, clay conn. @ 46', roots/grease in conn. @ 75', very minor roots in joints, conn. 109 5 404 ?? 174+ 8" w/roots/grease at 102', lots of roots @ conn. @ 174'. Video ends at 174' before end of of line.

Clean conn. @ 75', 102', and 174', finish clean/video.

Clay, low flow, very flat/stagnant, upstream, some grease, clay conn. @ 109 6 202+ 8" 104', 198'. A couple hangling gaskets.

No repairs needed, finish clean/video, keep clean of settled solids and grease.

Clay, very low flow, very flat/stagnant, clay conn. @ 47', some grease, slight sag @ 50'. A couple hangling gaskets. Slight sag at 100'-110', 109 7 ?? EOL?? 144 8" Roots in joint at 112', slight sag at 130', PVC @ 138', with PVC conn. @ 142' and 143', PVC to upstream EOL MH @ 144'.

No repairs needed, just clean out to remove settled solids and grease.

109 8 103 8" PVC, very low flow, light grease/solids. PVC conn. @ 104'.

No repairs needed, just keep clean of settled solids and grease.

Clay, downstream, slight sag at 10'-28', evidence of less than half flow, sag at 35'-45', good/clean pipe/joints, sag at 60-67', clay conn. @ 125'- 109 9 ?? ?? 8" camera didn't stop, need to look at this again, add'l slight sags in pipe, signif. I&I at 182' - need to fix. Video ended at 183', at infil. pt.

CITY HAS DONE THIS: Fix leaking joint at 182' (CIP Pt. Rpr.), keep clean of settled solids.

Same as Ch. 9, clay, downstream, low flow with occassional slight sags, 109 10 ?? ?? 8" went by conn. @ 125', City applied patch at 182', no more infiltration..

CITY FIXED INFILTRATION AT 182'.

"New spot on 248 need fixed". Short, unmarked video, going 109 11 ?? ?? 8" downstream, infil. @ 29'.

Pipe has very low flow, but infiltration @ 29'.

Page 5 of 56 From DVD Chpt Month Year To MH LF Comments MH

109 12 ?? ?? 8" "Day we fixed pipe to line up". Short, unmarked video. Infil. @ 29'.

Pipe has very low flow, but infiltration @ 29'.

109 13 ?? ?? 8" "Second patch job on 248". Video of patch applied at 28'.

CITY FIXED INFILTRATION AT 29'.

DVD titled "Mill St. MH #) Last Two Films"; "L1 SP", clay, 5' sticks, CCTV downstream, good pipe/joints, little grease, decent flow, good slope, PVC conn. @ 108'?, slight sag at 170'-185', bell crack at 205' ??? 1 ?? ?? 297 ?? (maybe pt rpr), slight sag at 258'-290'? MH at 297', kept videoing downstream, DS MH looks good, brick cone, next segment-sag at 310'- 345', clay conn. at 353'; video stops here. Pipes show evidence of half full at times.

Potential CIP Pt. Rpr. at 205', nothing significant.

DVD titled "Mill St. MH #) Last Two Films"; "L1 SP", clay, 5' sticks, CCTV downstream, good pipe/joints, very little grease, relatively low ??? 2 ?? ?? 201+ ?? flow, good slope, a couple hanging gaskets, clay conn. @ 105', cracked bell at 132' (pt rpr), minor roots in some joints, sig. roots at 201', video stops here.

CIP Pt Rpr at 132', cut roots at 201', clean out roots every few years.

"L1 SP", Clay, CCTV upstream, low flow, good slope, some grease, ??? 3 ?? ?? 349 ?? good pipe/joints, a couple slight sags, evidence of half full or less, good DS block MH, flow from right and upstream.

No repairs needed, just clean out to remove grease.

"L1 SP", Submerged at beginning, clay, stagnant flow, CCTV upstream, pipe half full til 48', then signf. Sag at 50'-140', thin wall PVC service at 82', PVC conn. @ 140', sig. sag at 154'-240', sig. sag at 257'-353' ??? 4 ?? ?? ?? (slope get steeper), clay conn. @ 294', US MH @ 370', pipes in all four directions (retrofit bypass?), MH bottom submerged slightly, block MH in good shape. Pipe/joints decent.

Look into add'l piping in US MH, re-construct to remove sags?

"L1 SP", Clay, stagnant flow, ~third full, settled solids, sag for first 40', still stagnant, very low flow with add'l slight sags, messy hammer-tap at ??? 5 ?? ?? ?? 74', dig up and replace if active (may not be though), or pipe-over if inactive, PVC conn. @ 97', DS block MH good (ring may not be fully supported, flow from upstream.

Repair conn. @ 74'. Keep clean of settled solids, or re-lay to maintain slope.

Page 6 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Mill St. to 14th St.", clay, stagnant flow for 20', ~quarter full, then low flow at decent slope, CCTV upstream, slight sags with settled solids, good pipe/joints, clay conn. @ 68', minor roots at 78'/105'/108'/110'/117', clay conn. w/roots 108', clay conn. @ 142', PVC ??? 6 ?? ?? ?? conn. @ 146', clay conn. @ 206', clay conn. @ 221' (could use LCR), PVC conn. @ 263', PVC conn. @ 347', clay conn. @ 355', clay conn. @ 367', clay conn. @ 388', clay conn. @ 406', very low flow despite conns. (inactive?), rough looking lateral service, 464', brick MH with very rough bottom @ 468', upstream pipe (no flow), MH lid with holes,.

Clean out minor roots, settled solids, check active conns., reline US MH, replace lid.

"Mill St going toward Church", clay conn. @ 9', piece of broken pipe @ 7', clay conn. @ 19', very low stagnant flow, clay conn. @ 35', grease in ??? 7 ?? ?? ?? line, clay conn. @ 19', clay conn. @ 35', settled solids in line, sag "@ 40'-57'(root/grease ball), clay conn. @ 53' w/grease, line heavy with grease, root/grease ball at 57',

Clean to remove root/grease ball, settled solids, finish CCTV.

"Luney Dr in Field"; clay pipe, CCTV upstream, roots in joint at 24', sig. ??? 1 313 315 roots @ 29'-40' - needs cleaning and lined over, surrounding pipe in good shape.

Clean out roots, plan to CIP at least btwn 28'-40'.

"Luney Dr in Field"; CCTV downstream (reverse setup??), clay, roots in ??? 2 ??? ??? several joints, low flow, decent velocity, cracked pipe at 62', little grease roots blocking at 112'.

Due to root prevalence and pipe damage, CIPP entire pipe.

??? 3 ??? ??? 200 "Luney Dr in Field"; short video, clay, roots in joints.

Reline (CIPP).

"Luney Dr in Field"; clay, CCTV upstream, very low flow, good velocity, mostly good/clean pipe/joints, but roots in joints, esp. @ 27' (broken at ??? 4 ??? ??? joint, upward flow of water), sig. joint offset b/c of roots at 81' (grout?), video ends at 82'.

Patch pipe at 27'. Patch or grout offset at 81', finish clean&CCTV of line.

"Luney Dr in Field"; clay, CCTV downstream, good/clean pipe/joints, ??? 5 315 313 very low flow, good velocity, minor roots in joints until 151' - major root blockage.

Jet out root ball at 151', finish CCTVing line. Plan to patch/grout over root intrusion.

Page 7 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Kathy Dr" DVD; L1 SP, clay, CCTV upstream, very low flow, clean pipe, good pipe/joints, 5' sticks, clay/thinPVC conn. @ 55', US MH @ 148', flow from upstream and right (lateral service?), settled solids in ??? 1 402 401 MH bottom. CCTV continues upstream to next segment, still good, clean, very low flow. PVC conn. with roots at 207' (55'). PVC conn. @ 274' (122'); sig. roots at 290' at clay conn., need LCR. Roots also present at ~300'. Video ends at 290'.

Clean roots out of conn. @ 207' (55') and at 290', install LCRs both locations or dig up and repair. Clean out other roots in pipe, finish CCTVing.

??? 2 402 403 Still in MH402 going east, short video (1:28).

Clean debris in line, check for blockages.

MH400 going south; grease and roots/debris (rocks/wood, etc.), ??? 3 400 401 evidence of full pipe flow/blockage, need to clean out.

Clean line of roots/debris, CCTV.

CCTV upstream, PVC pipe repair 12'-25', then clay, clay conn. @ 40', ??? 4 417 416? maybe a conn. @ 196?, very low flow, good velocity, a few settled solids, block MH @ 201' looks good, upstream flow at an angle to left.

No repairs, just keep clean of settled solids.

US brick MH, Large diameter line?, roots near beginning and collapsed pipe (no debris though), grease/debris build up, very low flow, PVC conn. @ 17', back-to-back clay conn. @ 26', clay conn. from above @ ??? 5 ??? ??? 28'?? (protruding some), more collapsed pipe at 30', slight sag at 36'- 44', CCTV downstream, settled debris, pipe is curved, some pipe debris in line, entire line not videoed, camera got caught up in pipe.

This line needs to be investigated more, may need to be replaced.

Clay, CCTV upstream, very, very low flow, good pipe/joints, some small ??? 6 408 ??? settled debris/grease, clay conn. @ 130', grease/root blockage at 278', need to remove.

Need to remove grease/root blockage at 278'.

Clay, <1/3 full, stagnant water, grease build up, debris blocking pipe at ??? 7 520 ??? 14', short 28 sec. video.

Clean debris out of line.

Still in MH520, CCTV downstream, stagnant water, couple of signif. ??? 8 520 494? Sags, pipe is sometimes full, grease build-up and debris/minor roots, debris prevented videoing entire line.

Evaluate as part of big picture for basin.

Page 8 of 56 From DVD Chpt Month Year To MH LF Comments MH

"11th and County Farm Rd"; CCTV downstream, clay, some grease buildup, cracked pipe at 16', pipe about 1/3 full, flat slope initially, then better cracked pipe at 21', pipe has changing slopes, good velocity 2014 1 422 40 when slope is there; PVC line repair at 54'-60' (grease sticks to PVC Reline too), then a sag in pipe from 60' to 80' with grease build up and minor bell cracking; pipe flattens out at 95', results in full pipe (may be blockage downstream), video ends at 98'.

Evaluate as part of big picture for basin.

"11th and Presley" Reverse setup, CCTV upstream, pipe starts 1/3 -1/2 2014 full for first 25' or so; clay with some grease, consistent 1/4-1/3 full of 2 40 422 Reline stagnant water, unsubmerged at 83', just fast low flow (many vertical pipe delections), back to submerged by 95' til end of video at 167'.

Evaluate as part of big picture for basin.

"11th and Presley", CCTV downstream, clay, cracked pipe at 9', grease 2014 34044 buildup, settled debris at 27' (~1/3 full), too much debris, video ends at Reline 29'.

Clean pipe of debris, finish CCTV.

"10th and Townsend", Clay, CCTV upstream, low flow, stagnant, some 2014 4 49 50 117 settled solids, some grease, flat slope, block MH at 117', low flow area Reline of system, looks OK, active line to right, inactive? line straight ahead.

Keep clean of settled solids and grease. Consider plugging inactive line in MH50.

"10th and Townsend"; greasy lateral near MH, very low flow, some settled solids, grease, clay conn. @ 20', roots in clay conn. @ 53', high 2014 54947 flow in lateral service @ 12o'clock @ 56'; clay conn. @ 98', conn. with Reline roots and grease at 100', conn. with roots @101'? Large mass of roots/grease at 113'. Video ends at 113'.

Clean out settled solids/roots/grease, finish CCTV. Clean roots from conn. @ 20', 100'; investigate high flow at 56'. Plan on LCRs.

"Old Exeter Rd"; cracks near MH456; clay, CCTV upstream; low flow 2014 with good velocity; broken pipe joint at 24', grease along top of pipe 6 456 457 126 Reline (flows full often), crack along bottom at 88'; broken pipe bell at 94'; MH 457 coated in grease-has surcharged, MH lid has holes.

End seal near MH 456; CIP pt rpr at 24', determine cause of full pipe flow; consider CIP Pt. Rpr @ 88'; CIP Pt. Rpr. @ 94'

2014 7 "Empty Title"; NO VIDEO Reline

N/A

Page 9 of 56 From DVD Chpt Month Year To MH LF Comments MH

"10th & Fair St."; MH25 going west, clay (5'), CCTV upstream, grease buildup, decent velocity despite some stagnant flow, 1/2 full from Creek 1 07/17/13 25 9 160+ backup; pipe has been full, grease on crown, some settled solids, not Xings sure on integrity of bottom of pipe-could be bad at 128'; video ends at 160'.

Clean of grease/solids, plug upstream and video to determine condition of bottom of pipe, source of backups.

"Still at 10th & Fair St"; clay (5'), CCTV downstream, good velocity, pipe Creek 1/4-1/2 full, grease along crown, DS block MH @ 256', straight thru 2 07/17/13 ??? ??? 355'+ Xings piping, continue CCTV downstream, lots of grease, clay conn. @ 310', video ends at 355'.

Clean of grease/solids, plug upstream and video to determine condition of bottom of pipe, source of backups.

"City Park to Fair St"; CCTV downstream, ~1/3-1/2 full, slow moving Creek 3 07/17/13 172 ??? 186 water, grease, clay and PVC, evidence of full pipe, areas coated in Xings grease, DS block MH @ 186', straight thru.

Clean of grease/solids, plug upstream and video to determine condition of bottom of pipe, source of backups.

Creek "Still in City Park"; pipe coated in grease, PVC, about 1/2 full, slow 4 07/17/13 ??? ??? 203'+ Xings moving, has been full, video ends at 203' @ grease/root ball.

Clean grease/roots at 203', finish CCTV, determine cause of backup/stagnant flow.

"Going to Fox Ridge"; CCTV upstream, very low flow, 5' clay, little grease, good pipe/joints, no evidence of surcharge, very slight sags with Creek 5 07/17/13 418 501 192 low velocity, pipe change at 103' (crossing?) 20' steel?, back to clay at Xings 157', some settled solids, US MH @ 192', US flow from slight right, also from left (PVC), good block MH 501.

No repairs needed.

Creek "Rocky Edmondson Park"; CCTV downstream, clay, coated in grease, 6 07/17/13 340 69 48'+ Xings low flow, settled solids/debris, esp. @ 48' where video ends.

Clean of debris/solids, finish CCTV.

"248 Hwy"; CCTV downstream, clay, good pipe/joints, little grease, no evidence of frequent surcharge (but likely has occurred), clay conn. @ 126' (>4"?, active), active infiltration @ 183' (same spot fixed in other Creek 7 07/17/13 298 190 video?), city's patch at 190', active infiltration @ 193' and @ 197', pipe Xings is flat from 200' on, settled solids, slow velocity, up to 1/2 full, slope picks up again at 225', pipe change at 226'-368' (crossing?, 20' steel?), root mass at clay conn. @ 374', video ends @ 375'.

Clean root mass at 374', fix active infiltration at 183', 193', 197'.

Page 10 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Along Greenway to Picnic"; CCTV upstream, PVC, stagnant flow, up to 1/2 full, pipe has surcharged, settled solids, goes to steel casing @ 43', still flat, settled solids, back to PVC @ 96', still flat w/settled solids, Creek 8 07/17/13 159 160 166 evidence of full pipe, at 134' solids less noticable, flow very low and no Xings solids (washed down?), still evidence of full pipe, settled solids at 160', US MH @ 166' with settled solids, flow from upstream only, no footage of inside MH.

Clean of settled solids, check pipe slope btwn MHs. Evaluate as part of big picture.

"Along Greenway to Hwy 112"; Still in MH159, CCTV upstream, PVC, stagnant flow, up to 1/2 full, pipe has surcharged, settled solids, goes to Creek 9 07/17/13 159 193 348 steel casing @ 58'-75', still flat, settled solids, back to PVC @ 75', still Xings flat w/settled solids, evidence of full pipe, 1/2 full stagnant, grease, US MH @ 348', flow from slight right, good precast MH.

Clean of settled solids, check pipe slope btwn MHs. Evaluate as part of big picture.

"Trout Farm"; CCTV downstream, in casing?, good flow/velocity, high flow from hole in pipe @ 42', grease, evidence of full pipe, slope lessens Creek and pipe is 1/2 full at 100'-130', still flat, ~1/3 full, lots of grease on pipe 10 07/17/13 ??? ??? 267'+ Xings crown, pipe 1/3-1/2 full remainder of video, video ends at DS block MH coated in grease @ 246', video contiues downstream, becomes clay in MH and continues clay to end of video @ 267'.

Fix hole in pipe, clean of grease, settled solids.

Creek 11 07/17/13 ??? ??? N/A "Trout Farm 2"; video of hole in pipe at 42'. Xings

Fix hole in pipe.

15inch "15-inch main & over by shop by creek" DVD, "15 Inch": short 12 1 03/07/12 17 15" main second video

N/A

"15-inch main & over by shop by creek" DVD, "L1 SP": CCTV downstream, clay, ~1/4-1/2 full, clay, rapid velocity, evidence of infrequent full pipe, only grease along bottom, active clay conn. @ 44', 15inch 2 03/07/12 17 16 357'+ 15" crack in pipe @ 120' and 148', is there major infil. from underneath?, main conc. MH at 244' (bolted?), continue video downstream, still 1/4-1/3 full, good velocity, clay, good pipe/joints, maybe settled debris, little grease, video ends at 357'.

Evaluate as part of big picture for basin.

"15-inch main & over by shop by creek" DVD, "L1 SP": video starts as same as chapter 2 (MH17-16), from MH 16-15 distance counter reset to 15inch 3 03/07/12 16 15 138'+ 15" zero, video shows 1/4-1/2 full pipe, good clay pipe, video concentrates main on pipe wall btwn 75'-138' (not sure why, settled solids?), video ends at 138'.

Evaluate as part of big picture for basin.

Page 11 of 56 From DVD Chpt Month Year To MH LF Comments MH

"15-inch main & over by shop by creek" DVD, "L1 SP": video starts at 15inch MH (16??), continues downstream, good pipe/joints, only grease on 4 03/07/12 16? 15? 15" main bottom, pipe 1/5-1/2 full, again checking pipe wall, not sure what intent is-trying to dislodge settled solids?

Evaluate as part of big picture for basin.

15inch "15-inch main & over by shop by creek" DVD, "L1 SP": clay, video of 5 03/07/12 20 ??? 15" main pipe wall, nothing to conclude.

Evaluate as part of big picture for basin.

"15-inch main & over by shop by creek" DVD, "L1 SP": ~1/3 full, good 15inch rapid flow, coated (grease?) clay pipe (5'), minor crack @ 34', grease 6 03/07/12 20 19 15" main along flow line, rapid flow, crack on crown at 153', camera stuck-debris or offset joint at 158'?, video ends at 174' (n pipe).

CIP Pt. Rpr. @ 153', evaluate as part of big picture for basin. Is rapid flow expected here or part of infiltration? Finish CCTVing.

"15-inch main & over by shop by creek" DVD, "L1 SP": CCTV downstream, ~1/4-1/2 full, good velocity, lots of grease along pipe 15inch 7 03/07/12 ??? ??? 213 15" crown, clay conn. @ 49', good pipe/joints, camera submerged (>1/2 full) main from 70'-213' where it reaches DS block MH which looks OK. Camera then tries to focus on something downstream, not sure what it is.

Evaluate as part of big picture for basin.

"15-inch main & over by shop by creek" DVD, "L1 SP": CCTV downstream, clay, grease, settled debris, much of video is of pipe wall 15inch close-up, shows grease coating-nothing can be discerned about pipe 8 03/07/12 14 13 15" main integrity though, camera also submerged much of the way, reaches clay conn. @ 358' (grease), reaches DS MH at 397' (camera submerged), camera continues DS (still submerged) to 442' where video ends.

Clean of settled solids, check pipe slope btwn MHs. Evaluate as part of big picture.

"15-inch main & over by shop by creek" DVD, "Over by Shop Going 15inch Under Creek": in MH D001C, clay, mostly submerged video of pipe 9 03/02/12 D001C ??? 15" main wall, minor crack at 54', root mass at 83' - blocking pipe! Inspection ends at 83'.

Clear out root mass at 83'!

"15-inch main & over by shop by creek" DVD, "Off 10th St. in Yard": Still 15inch 10 03/07/12 D001C D001B 15" in MH D001C going towards D001B, clay, grease on crown, flow 1/4- main 1/3 full, camera submerged at 20' til end of video at 34'.

Need to clean and re-video.

Page 12 of 56 From DVD Chpt Month Year To MH LF Comments MH

"15-inch main & over by shop by creek" DVD, "Over by Bridge Toward Plant": CCTV downstream, MH9 towards creek, ~1/4 full, CCTV downstream, steel casing pipe under creek?, good velocity, hole in pipe at 41' (as shown in previous videos), camera submerged ~100', grease 15inch 11 03/07/12 9 5 244 15" all along pipe, camera unsubmerged at 125', back to ~1/4 full, lots of main grease, pipe ~ 1/2 full at 225' (flatter slope), reach DS MH @ 244', grease and debris, evident of surcharge in MH, MH lid has 3 holes, video continues downstream, still lots of grease (esp. @ 260'), back to clay pipe, video ends at 265'.

Hole in pipe has been fixed by City crews. Plug upstream and clean & video with no sewer flow to find other areas of infiltration.

"All of Sherwood Forest", VERY low flow, PVC, conn. @ 45', 159', 273' 111 1 01/19/15 371 372 274'+ 8" (grease), some grease in line, camera gets hung up on grease at 274', video ends.

No repairs needed, just keep clean of settled solids and grease.

274'+ "Sherwood Forest"; Assume in same line, conn. @ 143', grease, DS MH 111 2 01/19/15 371 372 8" 146? @ 146', some debris at end of line, newer precast MH.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, very low flow, conn. @ 5', 21' (grease), video 111 3 01/19/15 392? 8" ends in pipe at 101'.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, very low flow, DS, some settled solids, conn. 111 4 01/19/15 391 381 345 8" @ 52' (grease), 125', 227', 262' (grease), precast MH @ 345', some settled solids, good MH.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, very low flow, DS, conn. @ 83', 142' (grease), 111 5 01/19/15 380 381 239 8" 237' (grease), grease/debris clog in line at MH, 239', video ends at MH entrance.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; Numbering doesn't match up with GIS, PVC some 111 6 01/19/15 379 378 273 8" settled solids, flat pipe, conn. @ 115', 172' (grease in line), 194' (grease in line), reach DS MH 273', precast, looks good.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, low flow, very flat pipe, settled solids, conn. @ 40' (grease), 145' (lots of grease), 159' (lots of grease), grease caked up 111 7 01/19/15 378 377 295 8" on line in spots, conn. @ 288' (grease), precast MH @ 295', settled debris.

No repairs needed, just keep clean of settled solids and grease.

Page 13 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Sherwood Forest"; PVC, DS, very low flow, some grease buildup, 111 8 01/19/15 377 376 249 8" settled solids, conn. @ 121', DS precast MH @ 249'.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, US video, low flow, some grease buildup, pipe has some deformity, settled solids; conn. @ 63', water rushing in from 111 9 01/19/15 373 372 294 8" connection at 183', US precast MH @ 294'. Heavy grease build up at 193' due to conn. @ 198'.

What is source of heavy flow at 183'? No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, DS, low flow, some grease buildup, settled 111 10 01/19/15 373 374 224 8" solids, conn. @ 120' with heavy grease, DS precast MH @ 224'.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, US, low flow, some grease buildup, settled 111 11 01/19/15 375 374 157 8" solids, conn. @ 145', US precast MH @ 157', some settled solids.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, US, low flow, some grease buildup, settled 111 12 01/19/15 375 376 146 8" solids, conn. @ 139' w grease, US precast MH @ 146', some settled solids.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, US, low flow, some grease buildup, settled 111 13 01/19/15 375 395 8" solids, conn. @ 109', 123'; US precast MH @ 234'.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, DS, low flow, little grease buildup, settled 111 14 01/19/15 381 394 302 8" solids, conn. @ 94', 115', 187', 203'; DS precast MH @ 302'.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, DS, very low flow, conn. @ 100'; DS precast 111 15 01/19/15 393 394 256 8" MH @ 256'.

No repairs needed, just keep clean of settled solids and grease.

"Sherwood Forest"; PVC, DS, low flow, grease buildup, settled solids; 111 16 01/19/15 394 395 54 8" DS precast MH @ 54' (drop MH).

No repairs needed, just keep clean of settled solids and grease.

Page 14 of 56 From DVD Chpt Month Year To MH LF Comments MH

"County Farm Rd"; PVC, U.S., evidence of half-full, greasy, some 112 1 01/19/15 367 369 233 8" settled solids, conn. @98', 99', 230', U.S. MH @ 233', board/debris in MH, precast MH has inside drop.

No repairs needed, just remove debris in MH 369 and keep clean of settled solids and grease.

"All of Eagle Nest"; PVC. U.S., very low flow, some grease, conn. @ 53', 112 2 01/19/15 367 368 413 8" 144', 160', 216' with lots of grease, 236', 283', 302', 353', 372', 408', 409', precast MH @ 413'.

Very low flow despite several services? No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; PVC, U.S., greasy, evidence of half-full, very low 112 3 01/19/15 367 366 43 8" flow, settled solids, precast MH @ 43'.

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; PVC, U.S., very low flow, dirty pipe, precast MH @ 112 4 01/19/15 365 366 44 8" 44'.

No repairs needed, just keep clean of settled solids and grease.

"Billy Dr"; clay, D.S., very low flow, quite clean, good pipe/joints, D.S. 112 5 01/19/15 362 361 309 8" MH at 309', block/brick.

No repairs needed, no connections.

"From Billy Dr to Carole"; D.S., clay, very low flow, settled solids, greasy, very minor roots in a few joints, minor cracks in a couple joints, 112 6 01/19/15 360 359 170 8" very flat pipe, no connections, block/brick MH at 170', could get better sealing ring/lid.

No repairs needed, may want to replace MH 359 ring/lid for better seal. Keep clean of settled solids and grease.

"Carole Trying to Go to CFRD"; U.S., clay, flat pipe, stagnant water, evidence of over half-full, grease, major sag in pipe near MH 359; clay 112 7 01/19/15 359 364 254 8" conn. @ 77', PVC? conn. @ 87', transition to steel pipe at 87'- MH@254' (shallow block MH 364).

See if it makes sense to replace pipe D.S. of steel piping to remove sag. Keep clean of grease/solids.

"Carole Trying to Go to CFRD"; Continue U.S. to MH 363, clay, conn. @ 6', PVC conn. @ 14', clay conn. @ 78', conn. @ 122' with grease, 112 7 01/19/15 364 363 310 8" conn. @ 212' with cracked pipe surrounding (hammer tap), offset clay conn. @ 226' with roots, PVC conn. @ 305', U.S. block/brick MH at 310', grease/settled solids in U.S. pipe.

Consider LCR at 212', open-cut repair of conn. at 226', clean settled solids in MH 363 upstream pipe.

Page 15 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Carole St Going Toward Kathy Dr"; clay pipe, D.S., sag in first 20' near MH 359, evident of over half-full, greasy, settled solids, clay conn. @ 100', conn. @ roots @ 112', significant flow through connection at 113' 112 8 01/20/15 359 404 276 8" (broken under creek or just washing machine discharge due to suds??), sag and grease at 150'-160', stagnant flow, several sags, grease along walls, clay conn. @ 210', D.S. MH @ 276', block/brick, good shape, may need new lid/ring?

Determine source of flow and resolve flow coming in at 113'. Determine reason for backups, keep clean of settled solids and grease. Does it make sense to replace this line? Consider new ring/lid for MH404.

"Billy Dr"; clay, U.S., clay conn. @ 12', slight sag 20'-40', good pipe but 112 9 01/21/15 360 361 173 8" minor crack at 87', debris @ 99' (root from joint @ 102'), root curtain @ 108'.

Remove roots near 100', install CIP Section point repair. Remove root curtain at 108', make repairs as needed.

"Billy Dr"; reverse setup, going D.S. to MH360, clay conn. @ 10' 112 10 01/21/15 361 360 173 8" w/grease/solids, conn. @ 17' w/roots, minor roots in several joints, roots @ 39' and 59', PVC conn. @ 63', back to root curtain at 65'.

Consider CIPPing entire line, LCR at 17'.

"County Farm Going Kathy Dr"; clay, U.S., low flow, some settled solids, 112 11 01/22/15 408 407 124 8" good pipe/joints, grease, no connections, U.S. block/brick MH @ 124'.

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; clay, D.S., some grease, low fast flow, good 112 12 01/22/15 408 409 309 8" pipe/joints, evidence of fuller pipe, some deteriorated gaskets, PVC conn. @ 233', D.S. precast MH @ 309'.

Determine reasons for any surcharges, no specific repairs needed on this pipe.

"Country Farm Rd"; clay, DS, some grease, low fast flow, loose pipe 114 1 01/27/15 409 416 394 8" joints, evidence of full pipe, minor crack @ 55', PVC conn. @ 204' & 337', DS precast MH @ 394'

No repairs needed, just keep clean of settled solids and grease.

"Country Farm Rd"; clay, US, moderate grease, low fast flow, clay conn. 114 2 01/27/15 417 416 291 8" @ 108', joint seperation @ 288', multiple gaskets falling from joints, US precast MH 416 @ 291'

CIP Point Liner to repair joint seperation at 288'. Inspect top of manhole for possible gaps.

Page 16 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Country Farm Rd"; clay, US, some grease, low fast flow, evidence of full pipe, offset joint @ 11', PVC pipe from 11' to 27', clay conn. @ 40' 114 3 01/27/15 417 ??? 201 8" not in use or collapsed, US concrete masonry block with precast chimney MH @ 201'

Evaluate usage of connection of 40' to determine if lateral repairs are needed.

"Country Farm Rd"; clay, DS, moderate grease, variable flow rates due 114 4 01/27/15 417 418 349 8" to grades, evidence of 2/3 full pipe, DS precast MH @ 349'

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd to Array St"; clay, US, moderate grease, low fast flow, evidence of full pipe, gasket falling out of joint @ 163', PVC pipe from 114 5 01/27/15 418 500 193 8" 104' to 157', US concrete masonry block MH 500 @ 193', US MH notation on video does not match map

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; clay, DS, moderate grease, low fast flow, evidence of half full pipe, clay conn. w/roots up in lateral @ 106' (private side), 114 6 01/27/15 418 ??? 393 8" cracked pipe with roots @ 132'/281', roots in joint @ 147'/152'/208'/313'/322'/328', lightly cracked pipe @ 251', clay conn. w/roots @ 287', DS concrete masonry block MH @ 393'

Clean line and reinspect to determine extent of damage of cracks. CIP Point Repair at 132'.

"County Farm Rd from Wayne Rd to 14th St", clay, Continued DS, 114 6 01/27/15 ??? ??? 379 8" moderate grease, high flow level and moderate flow rate, clay conn. @ 309', sag in line @ 774', DS MH @ 379'

No repairs needed, just keep clean of settled solids and grease.

"Oakhill Dr", clay, US, light to moderate grease, no current flow, evidence of 1/8 full pipe, clay conn. @ 54', 152', & 220', clay conn. with 114 7 01/27/15 35 36 230 8" grease @ 130' & 203', US concrete masonry block MH 36 @ 230', video MH numbers do not match map

No repairs needed, just keep clean of settled solids and grease.

"Oakhill Dr", clay, US, light grease, low flow level with moderate rate, evidence of half full pipe, clay conn. with minor grease @ 29'/241', roots 114 8 01/27/15 35 34 298 8" in joint @ 64'/69'/74'/276', cracked pipe w/roots & 79', clay conn. @ 130', clay conn. w/moderate roots @ 292', US concrete masonry blocks @ 298', flow direction does not match map

No repairs needed, clean to remove roots and regularly check to monitor root growth.

"Oakhill Dr", clay, DS, light grease, low fast flow, evidence of half full pipe, minor cracked joint @ 11'/16', clay conn. w/minor crack @ 96', DS 114 9 01/27/15 35 37 120 8" concrete masonry block MH 37 @ 120', video MH notation does not match map

No repairs needed, just keep clean of settled solids and grease.

Page 17 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Oakhill Dr", clay, DS, variable flow level and rate due to sags, evidence of 1/3 pipe high flow level, minor roots in joint @ 100'/110'/156', PVC 114 10 01/27/15 37 38 301 8" conn. @ 160'/203', cracked pipe w/moderate roots from 258' to 263', minor cracked pipe from 278' to 280', DS concrete masonry block MH @ 301', MH 38 not on map

Clean roots and install CIP Point Liner at 258' to 263' and 278' to 280' to resolve pipe crack.

"Oakhill Dr", clay, Continued DS, light grease, low fast flow, evidence of half full pipe, clay conn. w/moderate grease @ 28', clay conn. @ 114 10 01/27/15 38 ??? 293 8" 129'/231', cracked pipe w/moderate roots @ 186', minor broken pipe w/moderate roots @ 191', unknown DS concrete masonry block MH @ 293'

Clean line and install CIP Point Liner from 186' to 195' to resolve pipe cracks.

"Oakhill Dr", clay, US, no grease, low flow w/moderate rate, evidence of half full pipe, clay conn. @ 64', 165', 237', & 288', clay conn. 115 1 01/29/15 32 33 295 8" w/moderate grease @ 113', US concrete masonry block MH 33 @ 295', map indicates MH 32 & 33 do not connect

No repairs needed, just keep clean of settled solids and grease.

"Oakhill Dr", clay, DS, low fast flow, evidence of full pipe, light grease, 115 2 01/29/15 32 31 297 8" clay conn. @ 5', DS concrete masonry block MH 31 w/drop in line

No repairs needed, just keep clean of settled solids and grease.

"W 14th St", clay, US, low flow w/moderate rate, light grease, evidence of higher flow level, moderate roots in joint w/minor cracked pipe @ 115 3 01/29/15 ??? ??? 240 8" 120', minor roots in joint @ 149', clay conn. @ 150', minor cracked pipe @ 219', US concrete masonry block MH has moderate root presence

Clean line and reinspect to determine extent of damage of cracks. Reline up stream manhole.

115 4 01/29/15 ??? ??? 8" No identifying notation, clay, debris is blocking inspection @ 7'

Clean and reinspect line.

"W 14th St"; clay, DS, 1/3 full line w/low rate, light grease, evidence of 115 5 01/29/15 ??? ??? 37 8" full pipe, debris @ 36' causing flow backup, DS concrete masonry block MH @ 37'

No repairs needed, just keep clean of settled solids and grease.

"Country Farm Rd to W 14th St"; clay, US, light grease, low flow 115 6 01/29/15 419 ??? 197 8" w/moderate rate, evidence of 3/4 full pipe, clay conn. @ 147', US precast MH @ 197'

No repairs needed, just keep clean of settled solids and grease.

Page 18 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Country Farm Rd to W 14th St"; clay, US, light grease, low fast flow, 115 6 01/29/15 ??? ??? 193 8" evidence of full pipe, clay conn. @ 15', US concrete masonry block MH @ 193'

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; clay, DS, moderate grease, low fast flow, evidence 115 7 01/29/15 419 ??? 286 8" of half full pipe, clay conn. @ 44' & 204', retrofit DS precast MH @ 286'

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; clay, DS, moderate grease, 1/4 depth fast flow, 115 7 01/29/15 ??? 421 195 8" evidence of 3/4 full pipe, clay conn. @ 81'/193', DS precast MH @ 195'

No repairs needed, just keep clean of settled solids and grease.

"County Farm Rd"; clay, DS, moderate grease, varying flow depth & 115 7 01/29/15 421 ??? 8" rate due to mutliple sags, evidence of full pipe, inspection ends @ capped service conn.

No repairs needed, just keep clean of settled solids and grease. Monitor future inspections to ensure stability of sags.

"County Farm Rd"; clay, US, light grease, varying flow depth & rate due 115 8 01/29/15 422 421 8" to multiple sags, inspection ends @ capped service conn.

No repairs needed, just keep clean of settled solids and grease. Monitor future inspections to ensure stability of sags.

"W 14th St"; clay, US, heavy grease, varying flow depth & rate due to 115 9 01/29/15 30 ??? 364 8" multiple sags, evidence of full pipe, clay conn. @ 83'/294', PVC conn. @138', US concrete masonry block MH with heavy debris

Clean deposits in upstream manhole. Review location of line and manholes with City. No obvious repairs required.

"W 14th St"; clay, DS, heavy grease, quarter full line w/slow flow, 115 10 01/29/15 30 29 8" inspection ends @ 7' due to heavy debris in line, MH notation on video does not match map

Clean line and reinspect.

"W 14th St"; clay, US, heavy grease, low fast flow, evidence of full pipe, 115 11 01/29/15 29 30 8" heavy debris in pipe, clay conn. @ 51', inspection ends @ 52' due to rock in line, MH notation on video does not match map

Clean line and reinspect.

Page 19 of 56 From DVD Chpt Month Year To MH LF Comments MH

"W 14th St"; clay, US, light grease, low fast flow, evidence of higher flow level, light roots in joint @ 13' & 23', moderate roots in joint @ 28'/33', 115 12 01/29/15 29 ??? 8" clay conn. w/heavy grease @ 21', Inspection ends @ 34' due to heavy root blockage

Clean line and reinspect. CIP Point Repair from 22' to 33'.

"W 14th St"; clay, DS, heavy grease, 1/3 full pipe w/slow flow rate, evidence of full pipe, Inspection ends @ 32' due to heavy grease & 115 13 01/29/15 29 258 8" debris buildup, map indicates MH 28 is located between MH 29 & 258

Clean line and reinspect. Maps indicate downstream manhole should be 28.

"Presley Ave"; clay, DS, light grease, very low & slow flow, light roots in 115 14 01/29/15 350 351 220 8" joint @ 41'/46', heavy roots in joint @ 51', Inspection ends @ 51' due to heavy roots

Clean line and reinspect. Probably CIP Point Liner at 51'.

"Presley Ave"; clay, US, light grease, low fast flow, debris settled in pipe, many offset joints, PVC conn. @ 25'/130', moderately offset joints @ 61'/76'/81'/92'/111'/121'/126', conn. w/heavy grease @ 117', light 115 15 01/29/15 351 350 220 8" roots in joint @ 56'/156', cracked pipe from 128' to 131' & 134' to 136', offset joint w/light roots @ 160', offset joint w/heavy roots @ 169', Inspection ends @ 169' due to heavy root blockage

Clean line and reinspect. CIP Point Liner from 128' to 131' (with service reinstatement), 134' to 136', and 169'.

"Presley Ave"; clay, US, light grease, low fast flow, 30+ offset joints, clay conn. @ 95'/98'/112'/162'/235'/289'/330', offset joints w/minor roots @ 249'/254'/259'/264'/274', PVC conn. @ 277', minor cracked & offset 115 16 01/29/15 351 352 337 8" joint @ 289', light roots in joints @ 309'/313'/318'/329', moderate cracked pipe from 330' to 331', US precast concrete w/brick corbel MH 352 Several offset joints, test and grout seal as needed. CIP Point Liner from 330' to 331' (varify activity of lateral at 330' before re- establishing).

"Presley Ave"; clay, DS, light grease, low fast flow, minor roots in joints @ 35'/156', offset joints @ 41'/56', clay conn. w/major blockage @ 114', PVC conn. @ 116', minor pipe crack from 116' to 119', heavy offset & 116 1 01/29/15 351 ??? 8" cracked joint @ 150', moderate roots in lightly cracked joint @165', minor roots in moderately cracked joint @ 185', heavy roots in joint @ 199', Inspection ends @ 199' due to heavy roots

Clean line and reinspect. Confirm usage of connection at 114'. CIP Point Repair at 150', 164', 185', and 199'.

"Presley Ave"; clay, DS, light grease, low slow flow, debris settled in pipe, PVC conn. @ 7'/34'/139'/266', clay conn. @ 17', offset joint @ 48'/112'/264'/343', roots in joint @ 116 2 01/29/15 353 354 369 8" 123'/160'/165'/174'/180'/184'/189'/195'/205'/209'/239'/334', clay conn. w/heavy roots @ 169', cracked pipe w/moderate roots @169', PVC conn. w/moderate grease @336', DS precast w/brick corbel MH 354 @ 369'

Clean line and CIPP to resolve issues.

Page 20 of 56 From DVD Chpt Month Year To MH LF Comments MH

"15th St"; clay, DS, some grease, low slow flow, evidence of 3/4 full pipe, multiple offset joints, clay conn. @ 44'/119', minor roots in joint @ 55'/60'/70'/95'/99'/105'/130'/140', cracked joint @ 65', clay conn. 116 3 01/30/15 354 355 177 8" w/heavy grease @ 67', PVC conn. @ 127', moderately offset joint @ 175', moderately cracked pipe @ 177', DS precast w/brick corbel MH 355 @ 177'

Clean line regularly to control roots. CIP Point Repair at 127'. Pipe End Seal at manhole 355 (try to resolve offset at 175' with end seal).

"15th St"; clay, DS, some grease, low slow flow, multiple offset joints, roots in joint @ 148'/169'/178'/208', moderate roots in joint @ 174', clay 116 4 01/30/15 355 ??? 216 8" conn. w/heavy grease @ 151', clay conn. w/minor roots in joint @ 205', moderately offset joint @ 214', cracked pipe @ 216', DS precast manhole w/brick corbel MH @ 216'

Clean line and inspect regularly to control roots and monitor cracks. CIP Lateral connection at 205'.

"15th St"; clay, DS, moderate grease, low fast flow, evidence of 3/4 full pipe, clay conn. w/roots & crack @ 3', roots in joint @ 116 4 01/30/15 ??? ??? 8" 3'/38'/48'/52'/58'/63'/68'/73'/78'/88'/93', offset joint w/moderately cracked pipe @ 43', Inspection ends @ 93' due to root intrusion

Clean line and reinspect. Probably CIPP entire line.

"Ivey St"; clay, DS, some grease, low fast flow, evidence of 3/4 full pipe, multiple offset joints, clay conn. w/heavy grease @ 5', roots in joint @ 7'/81'/86'/96'/127'/146', cracked pipe @ 27', moderately cracked pipe 116 5 01/30/15 356 258 8" from 36' to 37', PVC conn. @ 67', moderate roots in joint @ 91'/141', clay conn. w/heavy roots @ 114', cracked joint w/heavy roots @ 136'/138', heavy roots in joint @ 151', Inspection ends @ 152' due to root blockage

Clean line and reinspect. CIP Point Liner from 36' to 37' and probable additional CIP Point Liner at 151'.

"14th St"; clay, US, heavy grease, low fast flow, evidence of full pipe, multiple offset joints, 6" clay conn. @ 56', heavy debris deposits, 116 6 01/30/15 28 29 8" moderate offset joint @ 71', roots in joint w/heavy grease @ 155', heavy grease deposit @ 160'/165', Inspection ends @ 169' due to heavy root and grease blockage

Clean line and reinspect. Probably CIP Point Repair at 71' and 169'.

"14th St"; clay, DS, heavy grease, third to half full flow with moderate rate, evidence of full pipe, heavy debris deposits, depth of flow 116 7 01/30/15 28 258 8" preventing proper inspection, Inspection ends @ 88' due to large debris deposit

Clean line and reinspect.

"14th St"; clay, US, heavy grease, quarter full, evidence of full pipe, 116 8 01/30/15 258 28 8" multiple offset joints, offset joint w/heavy debris @ 86', Inspection ends @ 95' due to heavy debris deposit

Clean line and reinspect.

Page 21 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Ivey St"; clay, DS, some grease, low fast flow, camera does not move & 117 1 02/02/15 258 259 8" line is not inspected

No recommendations.

"Ivey St"; clay, DS, moderate grease, low fast flow, evidence of full pipe, offset joint @ 13'/19'/24'/54'/99', PVC conn. @ 66', clay conn. @ 101', 117 2 02/02/15 258 259 8" cracked pipe joint @ 74', clay conn. @ 101' is protruding into line preventing further inspection

Cut tap and reinspect.

"Ivey St"; clay, US, moderate grease, low fast flow, evidence of full pipe, multiple offset joints, heavy offset joint @ 12', PVC conn. @ 25', PVC 117 3 02/03/15 259 258 8" conn. w/medium grease @ 52', clay conn. @ 123' is protruding into line preventing further inspection

See also Disc 117 Chapter 2. CIP Point Repair at 12'.

"Ivey St"; clay, DS, moderate grease, low fast flow, evidence of full pipe, mutliple offset joints, cracked joint w/roots @ 32', PVC conn. @ 68', clay 117 4 02/03/15 259 260 8" conn. @ 145'/153', minor roots in joint @ 156', clay conn. w/moderate roots @ 172', clay conn. w/heavy roots and possible break in pipe @ 201', Inspection ends @ 201' due to root blockage

Clean line and reinspect. CIP Point Repair at 32'. CIP Lateral Connection Repair at 172' and 201'.

"Ivey St"; clay, US, moderate grease, low fast flow, evidence of higher 117 5 02/03/15 260 259 8" flow, Inspection ends @ 10' due to root blockage

See also Disc 117 Chapter 4. Clean line and reinspect to ensure full line is evaluated.

"Ivey St"; clay, DS, moderate grease, low fast flow, evidence of higher flow, clay conn. @ 29'/32'/39'/90'/208', heavy debris deposits after 110', sag from 110' to 130', clay conn. w/moderate grease @ 151'/155', clay 117 6 02/03/15 260 261 313 8" conn. w/light grease @ 215', clay conn. w/debris @ 242', clay conn. w/roots in joint @ 260'/304', clay conn. w/rags @ 309', DS precast MH 261 w/moderately broken invert

Clean line to eleviate debris. Repair invert in MH 261.

"Ivey St"; clay, DS, moderate grease, low fast flow, evidence of nearly full pipe, clay conn. @ 52'/220'/278', clay conn. w/grease @ 105'/158'/170', large debris deposits, clay conn. w/heavy grease @ 117 6 02/03/15 261 71 (46?) 314 8" 193', minor roots in joint @ 198', clay conn. w/gasket falling out @ 233', DS masonry brick MH 71 w/evidence of surcharge @ 314', MH notation on map does not match video

Clean and regularly reinspect to ensure deposits are removed. Determine activity of connection at 193', possibly clogged. Cut protruding gasket at 233'.

Page 22 of 56 From DVD Chpt Month Year To MH LF Comments MH

"13th St"; clay, US, some grease, variable low flow depth to 1/4 full, 117 7 02/03/15 262 ??? 8" evidence of nearly full pipe, clay conn. @ 23'/39'/60', offset joint @ 26', Inspection ends @ 60' due to lateral protruding into line

Cut tap and reinspect.

"13th St"; clay, DS, some grease, low slow flow, evidence of over half full pipe, clay conn. w/grease @ 20'/197', clay conn. @ 23'/132'/199'/224', clay conn. w/cracked pipe @ 57', clay conn. w/grease causing heavy buildup in line @ 130', heavy deposits, 117 8 02/03/15 262 239 394 8" cracked joint @ 199', PVC conn. @ 207', minor roots in broken joint @ 243', multiple offset joints, moderate roots in joint @ 278'/303'/313'/318'/323'/328'/338'/343'/347'/373', minor roots in joint @ 282'/288'/298'/308'/333'/352'/278'/383'/387', DS precast or rehabbed MH @ 394' Clean and reinspect. Determine source of connection at 130' to address heavy greasing issue. CIP Point Repair at 243'. Test and grout-seal joints as needed.

"High St"; clay, DS, some grease, low slow flow, evidence of 2/3 full pipe, clay conn. @ 12', roots in cracked joint @ 13', clay conn. w/moderate grease deposit in main @ 26', roots in joint @ 117 9 02/03/15 251 252 337 8" 39'/49'/53'/58'/108'/177'/186'/196'/206'/212'/217'/256'/276', offset joint @ 73'/282', clay conn. w/moderate grease @ 84', offset joint w/roots @ 222', PVC conn. @ 227', cracked pipe @ 325'/337'/393', DS precast MH @ 337'

Clean and regularly reinspect to ensure roots are removed. CIP Point Repair at 14'.

"High St & Luney Dr"; clay, US, moderate grease, low fast flow, evidence of 1/3 full pipe, many offset joints, clay conn. @ 20'/225', roots in joint @ 24'/49', offset joint w/roots @ 34'/39'/59'/79'/217', clay conn. 117 10 02/03/15 252 314 259 8" w/grease @ 57'/192', PVC conn. w/grease @ 185', clay conn. w/roots @221', offset & cracked joint w/roots @ 222', US precast MH 314 @ 259'

Clean and consider CIPP entire line to lessen offsets and resolve cracking.

"Luney Dr"; clay, US, moderate grease, low fast flow, evidence of half full pipe, multiple offset joints, offset joints w/roots @ 117 10 02/03/15 314 313 78 8" 15'/20'/39'/54'/59'/64'/69', clay conn. @ 47', US precast w/brick corbel MH 313 @ 78'

Clean line and monitor regularly to ensure roots do not cause issues.

"High St & 15th St"; clay, DS, moderate grease, low fast flow, evidence of full pipe, roots in joint @ 8'/13'/19'/24'/28'/34', moderate roots in joint 117 11 02/04/15 252 253 8" @ 38'/44'/49'/54'/58'/63'/68', heavy roots in joint @ 74', Inspection ends @ 74' due to heavy root blockage

Clean and reinspect line to ensure full line evaluation. Possible CIP Point Repairs required due to root infiltration.

Page 23 of 56 From DVD Chpt Month Year To MH LF Comments MH

"High St & 15th St"; clay, US, moderate grease, variable flow rate and depth, evidence of full pipe, multiple offset joints, broken pipe joint @ 37', clay conn. @ 43'/137'/182', roots in joint @ 49'/71'/76'/81'/86'/96'/101'/121'/130'/170'/190', moderate roots in joint 117 12 02/04/15 253 252 8" @ 54'/59'/66'/91'/126'/162', clay conn. w/heavy roots in lateral @ 60', flow backup due to debris @ 101', offset joint w/roots @ 111', clay conn. w/moderate grease buildup in lateral & pipe @ 143', Inspection ends @ 194' due to heavy root blockage

See also Disc 117 Chapter 11. Clean roots and reinspect lateral at 60' to determine if CIP Connection Repair will alleviate root intrusion.

"15th St"; clay/PVC, DS, moderate grease, variable flow rate & depth, evidence of higher flows, clay conn. w/grease @ 12', heavy roots in joint @ 25'/40', moderate roots in joint @ 35'/60'/65'/70', roots in joint @ 117 13 02/04/15 253 254 178 8" 45'/55'/75'/128', PVC conn. @ 78', PVC pipe from 104' to 107', PVC conn. w/ grease @ 106', cracked pipe @ 120'/149', cracked pipe w/roots @ 128', sag in line from 167' to 177', dirty lense preventing evaluation of DS MH 254 @ 178'

Clean line and reinspect to determine extend of root intrusion at 25' and 40'. CIP Point Repair at 150'.

"Gravel St"; clay, US, 3' pipe sections, some grease, low slow flow, 118 1 02/04/15 250 249 93 8" evidence of quarter full pipe, clay conn. @ 53', clay conn. w/moderate grease @ 73', US red brick MH 249 @ 93'

No repairs needed, just keep clean of settled solids and grease.

"16th St"; clay, US, 3' pipe sections, some grease, low slow flow, evidence of quarter full pipe, clay conn. @ 27'/48', offset joint @ 65', 118 2 02/04/15 249 ??? 8" clay conn. w/heavy roots @ 79', Inspection ended @ 79' due to root blockage

Clean line and reinspect. Probable CIP Connection Repair at 79'.

"Gravel St"; clay, DS, 3' pipe sections, moderate grease, low slow flow, evidence of full pipe, multiple offset joints, heavy roots in joint @ 55', 118 3 02/04/15 249 254 8" clay conn. w/roots and heavy grease @ 57', roots in joint @ 59', heavy grease deposit @ 74', Inspection ends at 74' due to grease blockage

Clean line and reinspect. Possible CIP Point Liner at 56' and 74'.

"By Edison Co."; clay, US, some grease, low fast flow, evidence of 2/3 118 4 02/04/15 ??? ??? 187 8" full pipe, clay conn. w/roots @ 20', US concrete masonry block MH @ 187'

No repairs needed, just keep clean of settled solids and grease.

Continued from "By Edison Co."; clay, US, moderate grease, low fast 118 4 02/04/15 ??? ??? 303 8" flow, evidence of full pipe, moderately offset joint @ 3', PVC conn. @ 60', US concrete masonry block MH @ 306'

Clean and install CIP Point Liner at 3'.

Page 24 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Business 37"; clay, US, moderate grease, low fast flow, evidence of full pipe, roots in joint @ 7', heavy roots in joint @ 12'/28', PVC pipe from 118 5 02/04/15 ??? 358 8" 17' to 20', offset joint @ 20', moderate roots in joint @ 23', clay conn. w/heavy roots into pipe @ 25', Inspection ends @ 28' due to root blockage

Clean line and reinspect to determine extent of lateral damage at 25' as well as finish inspection. Probable CIP repairs required.

"Business 37"; clay, DS, some grease, variable flow depth & rate due to sags & debris, evidence of 3/4 full pipe, debris deposit @ 9' causing backup, roots in joint @ 12', clay conn. w/minor roots @ 14', clay conn. 118 6 02/06/15 ??? 357 216 8" w/heavy grease in lateral @ 108', PVC conn. @ 149', sag from 202' to 216' with heavy debris settling, DS precast concrete w/red brick corbel MH 357 @ 216'

Clean line and determine source of grease from connection at 108'. Regulary clean an inspect to monitor setteling in sags.

"1st St"; clay, DS, 3' pipe sections, some grease, low fast flow, evidence of full pipe, roots in joint @ 56'/60', moderate roots in joint w/visible 119 1 03/19/15 226 184 8" infiltration @ 64', heavy roots in joint @ 69', Inspection ends @ 69' due to root blockage Clean and reinspect. Possible CIP Point Liner to resolve issues at 64' and 69'.

Uknown location; clay, US, some grease, low slow flow, evidence of nearly full pipe, clay conn. @ 5'/24'/67', roots in joint @ 27'/37', clay 119 2 03/19/15 ??? ??? 8" conn. w/roots from joint @ 30', offset joint w/roots @ 42', offset joint @ 52', Inpsection ends @ 70' due to root & grease blockage

Clean and reinspect.

Uknown location; clay, US, some grease, low slow flow, evidence of 119 3 03/19/15 ??? ??? 8" higher flow, video shows line being cleaned but auger is not able to clear blockage, clay conn. @ 70'

No recommendation for this video.

"Old Exeter Rd"; clay, DS, heavy grease, variable flow depth & rate due to debris & grease, evidence of full pipe, cracked pipe @ 9'/33'/155', 119 4 03/19/15 439 ??? 8" clay conn. @ 49', clay conn. w/cracked main @ 155', roots in joint @ 76', debris buildup on joint causing moderage backup @ 160'/189'/194', Inspection ends @ 194' due to blockage

Clean line and complete inspection. CIP Point Liner and Lateral Connection Repair at 155'.

"Old Exeter Rd"; clay, US, moderate grease, low fast flow, evidence of 119 5 03/19/15 439 437 162 8" full pipe, US precast MH 437 @ 162'

No repairs needed, just keep clean of settled solids and grease.

"Old Exeter Rd"; clay, US, moderate grease, variable flow depth & rate due to debris & sags, unknown blockage @ 40' causes backup & dirties camera, inspection resumes @ 60', clay conn. w/minor grease @ 119 6 03/19/15 440 ??? 369 8" 130'/291', clay conn. @ 227', cracked & moderately offset pipe @ 237', sag from 340' to 369', frequent sags throughout causing debris settling, US concrete masonry block MH @ 369

Clean line and reinspect. CIP Point Repair at 237'.

Page 25 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Old Exeter Rd"; clay, DS, moderate grease, low fast flow, evidence of half full pipe, cracked pipe @ 5', moderately cracked pipe from 40' to 119 7 03/19/15 440 442 8" 43', roots in joint @ 84'/94', cracked pipe w/heavy roots @ 104', Inspection ends @ 105' due to root blockage

Clean line and complete inspection. CIP Point Repair at 5', 41', and 104'. "Sale Barn Rd"; clay, US, some grease, variable flow & depth due to 119 8 03/19/15 487 486 331 8" sags, evidence of higher flow, sag from 65' to 72', US precast MH 486 @ 331'

No repairs needed.

"Sale Barn Rd"; clay, DS, some grease, low fast flow, evidence of 2/3 119 9 03/17/15 487 496 317 8" full pipe, offset joint @ 107'/149'/204'/282', roots in joint @ 257'/269'/293'/299', DS precast MH 496 @ 317'

No repairs needed.

"Sale Barn Rd"; clay, DS, moderate grease, low slow flow, evidence of 2/3 full pipe, minor roots in joint @ 40'/46', multiple offset joints, PVC conn. @ 183'/312', cracked pipe from joint-to-joint starting @ 246', 119 9 03/17/15 496 489 321 8" radial crack of pipe @ 284' w/crack continuing to joint @ 286', cracked pipe from 286' to 289', clay conn. w/heavy grease in main @ 316', DS precast MH 489 @ 321'

CIPP line to resolve issues.

"Fasco Rd"; clay, US, moderate grease, half full pipe preventing proper inspection, flow rates vary, evidence of full pipe, heavy roots in joint @ 119 10 03/17/15 518 ??? 256 8" 29', moderate roots in joint @ 84'/114'/179'/194'/239', cracked pipe @ 84', US precast MH @ 256'

Clean line and reinspect. Try to determine source of line backup. Possible CIP Point Repair at 30'. CIP Point Repair at 84'.

"Abbey Ln?"; clay, US, moderate grease, variable flow depth & rate due to sags & debris, evidence of full pipe, roots in joint @ 2'/24'/174', sags throughout line, heavy roots in joint @ 205'/243', gasket falling out out 119 10 03/17/15 517 ??? 8" joint @ 214', roots growing along pipe from 217' to 224', moderate roots in joint @ 238', Inspection ends @ 243' due to heavy grease & roots blockage

Clean and reinspect line. Probable CIP Point Repair at 205' and 243'.

"Fasco Rd"; clay, DS, moderate grease, variable flow depth & rate due to debris & sags, evidence of full pipe, accumulated debris on top of 119 11 03/17/15 518 519 346 8" pipe, moderate roots in joint @ 42', heavy roots in joint @ 48'/77', minor roots in joint @ 52'/112'/187'/192'/261'/346', sag @ 124', DS precast MH 519 @ 346'

Clean and CIP Point Repair at 48' and 77'.

"Farm Rd 2180"; clay, US, some grease, variable flow rate & depth, evidence of higher flow, camera turned until 20' due to high flow, limited 119 12 03/17/15 493 522 326 8" visibility due to dirty lense, flow level drops @ 80', US MH @ 326', MH notation on map does not match video

Clean line and reinspect. Try to determine source of line backup.

Page 26 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Farm Rd 2180"; clay, DS, some grease, low fast flow, evidence of full 520 pipe, clay conn. w/moderate roots @ 153', mulitiple sags, DS concrete 119 13 03/19/15 493 192 8" (521?) masonry block MH 520 @ 192', MH notation on map does not match video No immediate repairs needed. CIP Lateral Connection Repair at 153'.

"Farm Rd 2180"; clay, DS, some grease, low fast flow, evidence of full 119 13 03/19/15 520 494 196 8" line, multiple sags, DS possible precast concrete MH 494 @ 196', MH notation on map does not match video

No repairs needed, just keep clean of settled solids and grease.

"Farm Rd 2180"; clay, DS, heavy grease, variable flow depth & rate due to blockages, evidence of full pipe, heavy grease deposits throughout 120A 1 04/30/15 523 522 293 8" with debris backup, DS precast MH 522 @ 293', MH notation on map does nt match video

Clean line to remove blockage and reinspect to check bottom of pipe.

"Farm Rd 2180"; clay, US, heavy grease, variable flow rate & depth due to backups, evidence of full pipe, offset joint @ 113', roots in joint @ 120A 2 04/30/15 523 ??? 297 8" 296', grease deposits caused by sags or causing backups, US precast MH @ 297' Clean line and reinspect to determine if open cut repairs are necessary to address backups.

"Farm Rd 2180"; clay, US, heavy grease, low fast flow, evidence of nearly full pipe, moderately cracked pipe w/active infiltration @ 1', PVC 120A 2 04/30/15 ??? 490 275 8" conn. w/grease @ 81', moderate roots in joint @ 222', pipe to manhole joint w/active infiltration @ 275', US precast concrete MH @ 275'

Pipe End Seal connection to both manholes. CIP Point Repair at 222'. Clean line and monitor root growth.

"Farm Rd 2180"; clay, DS, moderate grease, low fast flow, evidence of 120A 3 04/30/15 517 ??? 8" full pipe, roots in joint @ 60', large debris deposits @ 183'/215'/223', Inspection ends @ 223' due to debris blockage

Clean and reinspect.

"Maple Rdg"; clay, US, moderate grease, half full pipe with moderate 120A 4 04/30/15 ??? 517 517 8" flow rate, evidence of full pipe, grease deposits on top of pipe, PVC conn. @ 207', roots in joint @ 229', US precast MH 517

No repairs needed, just keep clean of settled solids and grease.

"Unknown location"; clay, DS, Inspection ends @ 6' due to heavy root 120A 5 04/30/15 ??? ??? 8" blockage

Clean and reinspect. Possible CIP Point Liner at 6'.

"Fasco Rd"; clay, DS, moderate greae, low flow w/variable rate, 120A 6 04/30/15 519 ??? 259 8" evidence of full pipe, moderate cracked joint w/minor roots @ 14', sag @ 235', DS precast MH w/damaged invert @ 259'

CIP Point Repair at 14'.

Page 27 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Fasco Rd"; clay, DS, moderate grease, low slow flow, evidence of full 120A 6 04/30/15 ??? 494 268 8" pipe, cracked pipe @ 56', sag @ 118', joint w/minor active infiltration @ 254', moderate roots & grease @ 263', DS precast MH @ 268'

No repairs needed, just keep clean of settled solids and grease. Monitor sources of infiltration with future inspections.

"Farm Rd 2180"; clay, DS, moderate grease, low fast flow, evidence of 120A 7 04/30/15 489 490 47 8" half full pipe, DS precast MH 490 @ 47'

No repairs needed, just keep clean of settled solids and grease.

"Farm Rd 2180"; clay, DS, moderate grease, fast flow w/low variable 120A 8 04/30/15 494 521 313 8" depth, joint w/moderate active infiltration @ 129'/168', clay conn. @ 169', minor sag @ 232', DS precast MH 521 @ 313'

CIP Point Repair at 129' and 168' to address infiltration.

"Farm Rd 2180"; clay, DS, moderate grease, low fast flow, evidence of full pipe, joint w/active infiltration, cracked joint w/active infiltration @ 120A 8 04/30/15 521 497 314 8" 103'/162'/222', joint w/active infiltration @ 177', clay conn. @ 584', DS concrete masonry block MH 297 @ 314'

Pipe End Seal at 0'. CIP Point Repair at 101', 162', 177', and 222'.

"Hwy 76"; clay, US, moderate grease, variable flow depth & rate due to sags, evidence of full pipe, multiple offset joints, moderately offset joint 120A 9 04/30/15 230 232 406 8" @ 68'/198'/277', PVC conn. @ 122'/190'/217'/280', clay conn. @ 170'/202'/272'/289', PVC line from 215' to 218' & 401' to 404', multiple sags, US concrete masonry block MH 232 @ 406'

Pressure test and grout joints.

"Hwy 76"; clay, DS, moderate grease, slow flow w/variable depth due to 120A 10 05/01/15 230 231 114 8" blockages up to 1/2 pipe, evidence of full pipe, offset joint @ 6', blockage @ 114' cuasing backups & high flows limitting line inspection

Clean and reinspect.

"Hwy 76"; clay, DS, some grease, low fast flow, evidence of half full pipe, minor cracked pipe @ 73'/83'/103', clay conn. @ 81'/157', PVC 120A 11 05/01/15 231 229 300 8" conn. @ 106', video ends before inspection completetion & continues on 102B Ch. 1-1

No repairs needed. Monitor cracks in future inspections.

"Hwy 76"; clay, DS, continued from Disc 120A Chapter 11, moderate grease, low flow level with variable rate, evidence of 2/3 full pipe, PVC 120B 1-1 03/23/15 231 229 300 8" conn. w/grease @ 206', clay conn. @ 222', PVC conn. @ 257', DS concrete masonry block MH 229 @ 300'

No repairs needed, just keep clean of settled solids and grease.

Page 28 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Hwy 76"; clay, DS, moderate grease, low fast flow, evidence of 2/3 full pipe, joint w/moderate active infiltration @ 25'/50', joint w/active 120B 1-1 03/23/15 229 ??? 258 8" infiltration @ 60', clay conn. w/roots @ 69', roots in joint @ 96'/107'/111', PVC conn. @ 180'/206', clay conn. @ 180', cracked joint @ 215', DS brick MH @ 258'

Pressure test and grout joints as needed. Pressure test and grout lateral connection at 206'.

"Hwy 76"; clay, DS, moderate grease, low fast flow, evidence of full pipe, clay conn. @ 20', roots in joint @ 120'/164'/170'/185'/190', roots in 120B 1-1 03/23/15 ??? 190 214 8" cracked pipe @ 180'/213', cracked pipe @ 195', moderate sag @ 211', DS brick MH 190 @ 214', moderate infiltration in bottom of MH 190

CIP Point Repair at 180'. Clean line and monitor root growth. Inspect manhole 190 to confirm infiltration is not a hydraulic jump.

"Hwy 76"; clay, no inspection was performed as snakes were blocking 120B 2 03/23/15 231 229 8" the line

Remove snakes and reinspect.

"Hwy 76"; clay, DS, some grease, variable flow depth & rate due to sags, evidence of full pipe, multiple sags, clay conn. @ 98', roots in 120B 3 03/23/15 296 295 8" joing @ 146'/171'/176', clay conn. w/roots in joint & moderate grease in lateral @ 188', Inspection ends @ 188' due to lateral conn. protruding into line

Cut tap and reinspect. Determine source of grease at 188'.

"Hwy 76"; clay, US, some grease, low slow flow, evidence of full pipe, 120B 4 03/23/15 ??? 296 8" roots in joint @ 18'/66', sag @ 48', Inspection ends @ 67' due to lateral protruding into line

Determine if this video is a continuation of Disc 120B Chapter 3.

"Hwy 76"; clay, moderate grease, slow flow w/variable depth, evidence of full pipe, clay conn. @ 89', moderately cracked pipe w/roots @ 179', 120B 5 03/23/15 ??? 295 327 8" heavy radial pipe crack @ 237', heavy radial pipe crack w/roots @ 292', moderate roots in joint @ 303', concrete masonry block MH 295 @ 327'

CIP Point Repair at 179', 237', 292', and 303'.

"Hwy 76"; clay, US, moderate grease, slow flow w/variable depth due to 120B 6 03/23/15 267 295 105 8" heavy line sags, evidence of full pipe, US concrete masonry block MH 295 @ 105' Clean and reinspect to determine cause of backup and possible need to replace line sections. "Hwy 76'; clay, US, heavy grease, half full pipe with slow flow, evidence 120B 7 03/23/15 267 268 8" of full pipe, Inspection ends @ 18' due to heavy grease and debris deposit

Clean and reinspect line.

"Hwy 76"; clay, US, some grease, low fast flow, evidence of 3/4 full pipe gasket falling out of joint @ 19'/96', clay conn. w/heavily offset joint @ 120B 8 03/23/15 ??? 264 218 8" 95', clay conn. w/moderately offset joint @ 109', several offset joints, US concrete masonry block MH 264 @ 218'

Clean line and install CIP Point Liner at 95' and 109'.

Page 29 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Hwy 76"; clay, some grease, low fast flow, evidence of half full pipe, joint w/moderate roots @ 2'/10', joint w/minor roots @ 120B 9 03/23/15 ??? 263 144 8" 20'/35'/45'/50'/55'/65'/70'/75', capped clay conn. w/heavy roots in lateral @ 26', offset joint @ 135', brick MH 263 @ 144' Clean and reinspect to determine if root blockage in lateral at 26' is removed and monitor roots growth.

"Hwy 76'; clay, DS, heavy grease, low fast flow, evidence of 2/3 full pipe, offset joint @ 3', clay conn. w/moderate grease or rust @ 5', roots in joint @ 32'/52'/320'/340'/345'/350', clay conn. w/moderate grease 120B 9 03/23/15 ??? 233 399 8" causing buildup in line @ 71', clay conn. @ 83'/145'/195'/229'/270'/271', PVC conn. @ 207', DS brick MH 233 @ 399'

Clean line and regularly inspect to moniter root growth. Determine source of grease from lateral at 3' and 71'.

"Hwy 76"; clay, half full pipe w/slow flow, Inspection ends @ 16' due to 120B 10 03/23/15 233 229 8" debris in line

Clean line and reinspect.

"Hwy 248"; clay, DS, no grease, no flow, evidence of 1/3 full pipe, some 121 1 03/25/15 301 344 292 8" debris deposits, clay conn. @ 37'/129', gasket falling out of joint @ 53', DS concrete masonry block MH 344 No repairs needed, just keep clean of settled solids, roots, and grease.

"Hwy 248"; clay, DS, very little grease, very low flow, evidence of 1/3 full 121 1 03/25/15 344 ??? 8" pipe, major offset joint w/cracked pipe @ 5'

Open Cut Point Repar joint offset at 5'. Reinspect to complete evaluation. "Hwy 248"; clay, US, some grese, low fat flow, evidence of 1/2 full pipe, 121 2 03/25/15 154 ??? 267 8" grease deposit caused by possible roots @ 32', offset joint @ 146', DS concrete masonry block MH @367' No repairs needed, just keep clean of settled solids, roots, and grease. "Hwy 248"; clay, DS, some grease, low fast flow, evidence of 1/2 full 121 3 03/25/15 154 ??? 135 8" pipe, some debris deposits in line, DS concrete masonry MH 153 @ 135' No repairs needed, just keep clean of settled solids, roots, and grease.

"Hwy 248"; clay, DS, some grease, variable flow rate and depth due to 121 3 03/25/15 ??? 153 8" debris deposits & line sags, evidence of full pipe, cracked pipe @ 135', offset joint @ 149', Inspection ends @ 161' due to cable snag issues

Reinspect line to complete evaluation.

"Hwy 248"; clay, US, some grease, variable flow rate & depth due to debris deposits & line sags, evidence of full pipe, PVC conn. @ 121 4 04/24/15 153 154 418 8" 76'/208', moderately cracked joint w/minor roots @ 196', cracked pipe w/roots at 205', cracked pipe @ 282', gasket falling out of joint @ 395', US concrete masonry block MH 154 @ 418'

Consider CIP Point Repair at 195', 205', and 282'. Clean line to keep clear of roots and grease.

Page 30 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Hwy 248"; clay, DS, some grease, variable flow rate & depth due to line sags, evidence of full pipe, PVC conn. causing grease in line @ 34', 121 5 04/21/15 153 297 374 8" gasket falling out of joint @ 49'/283'/311', clay conn. @ 65', PVC conn. @ 200', DS concrete masonry block MH 297 @ 274'

No repairs needed, just keep clean of settled solids, roots, and grease.

"Hwy 248"; clay, DS, some grease, variable flow rate & depth due to line sags, evidence of full pipe, cracked joint @ 50', roots in joint @ 121 5 04/21/15 297 ??? 8" 109'/189'/204', moderately cracked pipe @ 139', Inspection ends @ 230' due to cable snags CIP Point Repair at 54' and 139'. Reinspect to complete evaluation.

"Hwy 248"; clay, US, some grease, variable flow rate & depth due to line 121 6 04/22/15 298 297 395 8" sags & debris deposits, evidence of full pipe, offset joint @ 255'/345', conn. @ 365', US concrete masonry block MH 297 @ 395'

No repairs needed, just keep clean of settled solids, roots, and grease.

"Hwy 248"; clay, DS, some grease, variable flow rate & depth due to line sags & debris deposits, evidence of full pipe, clay conn. @ 125', CIP 121 7 04/22/15 398 ??? 385 8" liner @ 182'/190', PVC pipe from 192' to 198', severe pipe offset @ 226' (camera doesn't stop, unable to clearly view), PVC conn. @ 374', DS concrete masonry MH @ 385' w/active infiltration

Clean line and reinspect to determine severity of joint offset at 226', line down stream manhole to eleviate infiltration.

"Old Exeter Rd"; clay, some grease, low slow flow, evidence of half full pipe, clay conn. @ 47', joint gasket falling out @ 131', PVC line from 121 8 04/22/15 448 447 144 8" 138' to 144', PVC conn. @ 141'/143', US PVC lamp hole @ 144', Map does not match video labelling (map indicates line section is DS)

No repairs needed, just keep clean of settled solids, roots, and grease.

"Old Exeter Rd"; clay, DS, some grease, low fast flow, evidence of half full pipe, clay conn. @ 36', active infiltration @ 38', clay conn. protruding into line @ 119', cracked pipe @ 141', clay conn. w/gasket 121 9 04/22/15 448 ??? 361 8" falling out @ 217', gasket falling out @ 242', PVC conn. @ 274'/311', DS concrete masonry block MH @ 361', Map does not match video labelling (map indicates line section is US), need to clarify if this MH or next is 449

Cut Tap at 119', monitor infiltration at 38', and clean line regularly.

"Old Exeter Rd"; clay, DS, some grease, low fast flow, evidence of half full pipe, clay conn. @ 21'/154', cracked pipe @ 22'/47'/103', PVC conn. @ 188', clay conn. w/possible cracked pipe from joint @ 238', possible 121 9 04/22/15 ??? 449 392 8" conn. @ 295', clay conn. w/cracked pipe @ 304', DS concrete masonry block MH 449 @ 392', Map does not match video labelling (map indicates line section is US), need to clarify if this MH or last is 449

Clean and reinspect to determine severity of cracks and locate missed connections.

Page 31 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Rainbow Dr"; clay, US, some grease, variable flow depth & rate due to sags and debris deposits, clay conn. @ 105', clay conn. @ 198', clay 121 10 04/22/15 448 118 8" conn. w/moderate grease @ 211', heavy root intrusion @ 233', Inspection ends @ 234' due to root blockage

CIP Point Repair at 233'. Clean and reinspect.

"Old Exeter Rd"; clay, US, no grease, low fast flow, evidence of full pipe, issue with footage measuring at start of video, gasket coming out of joint 122A 1 04/22/15 456 450 8" @ 45'/55'/154'/184'/209'/214', major offset pipe joint @ 233', Inspection ends @ 234' due to severity of offset joint

Open Cut Repair pipe offset at 234'. Clean and reinspect.

"Old Exeter Rd"; clay, US, some grease, low fast flow, evidence of nearly full pipe, most joints offset, PVC conn. @ 100'/186'/289', cracked 122A 2 04/22/15 456 451 243 8" pipe @ 228', US precast walls w/brick corbel MH @ 243', need to determine if 451 is the end MH

Consider CIPP line to address joint offsets.

"Old Exeter Rd"; clay, US, some grease, PVC pipe section from 41' to 122A 2 04/22/15 451 ??? 8" 51', heavily offset joint @ 51', Inspection ends @ 51' due to severity of joint offset

Open Cut Repair pipe offset at 51'. Clean and reinspect line.

"Old Exeter Rd"; clay, DS, no grease, moderately cracked pipe @ 122A 3 04/22/15 456 451 128 8" 5'/25'/45'/70', heavily broaken pipe @ 94', clay conn. @ 100', moderately broken pipe @ 109', DS precast MH 451 @ 128'

CIP Point Repar at 94' and 109'.

"Sunset Dr"; clay, DS, no grease, some debris, no flow, difficult to see inspection due to dirty lense, cracked joint @ 21' to lateral conn. @ 22', PVC conn. @ 50'/230', roots in line @ 50', some slight sags and offset 122A 4 04/23/15 113 112 8" joints, clay conn. @ 180', conn. w/heavy deposits in lateral & some roots @ 186', clay conn. @ 197', heavy root blockage @ 275', Inspection ends @ 275' due to full line root blockage, Map does not match video labelling

Clean line, determine source of grease from connection at 186', reinspect line, CIP Later Connection Repair Liner at 186', CIP Point Repair at 275'.

"Sunset Dr"; clay, DS, some grease, low fast flow, conn. w/heavy grease build up in lateral @ 67', roots in joint @ 83'/122', conn. w/moderate grease build up @ 107', cracked pipe @ 113'/156', clay conn. @ 157', 122A 5 04/23/15 113 114 219 8" clay conn. w/gasket falling out of of joint @ 164', PVC conn. @ 214', heavily broken pipe joint @ 218', DS precast walls w/brick corbel MH 114 @ 219'

Determine source of grease at 67' and 107', Pipe End Seal repair at down stream manhole, and clean line.

Page 32 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Sunset Dr"; clay, US, variable flow rate and depth due to sags, evidence of half full pipe, clay conn. w/heavy build up in lateral @ 11', multiple offset joints & sags, PVC conn. @ 89'/91'/202', clay conn. 122A 6 04/23/15 114 115 8" w/crack in lateral & lateral protruding into main @ 182', clay conn. @ 204'/260', clay conn. w/heavy buildup @ 266'/337', roots in joint @ 278'/283'/298'/328', Inspection ends @ 338' due to lateral conn. protrusion

Determine source of line buildup from connection at 11', cut taps at 182' and 338', clean line, and reinspect. Probably CIPP line.

"Sunset Dr to Sunset Hts"; clay, DS, no grease, low fast flow, evidence of nearly full line, clay conn. w/cracked joint & protruding lateral into main @ 90', roots in joint @ 95'/99'/144'/219'/258', clay conn. w/moderate roots in joint @ 101'/122', clay conn. w/heavy build up in 122A 7 04/23/15 114 116 8" lateral and roots in joint @ 139', clay conn. w/moderate roots @ 216', conn. w/heavy build up in lateral & roots in joint, heavy roots in joint @ 230'/264'/267', moderate roots in joint @ 234'/244', Inspection ends @ 272' due to root blockage

Clean line, reinspect, cut tap at 90', and CIPP line.

"Sunset Hts to Sunset Dr"; clay, US, some grease, low fast flow, 122A 8 04/23/15 116 114 8" evidence of nearly full line, Inspection ends @ 18' due to root blockage

Clean line and reinspect.

"Sunset Hts"; clay, US, no grease, low fast flow, evidence of 3/4 full 122A 9 04/27/15 116 ??? 285 8" pipe, clay conn. @ 100', roots in joint @ 197', US concrete masonry block MH @ 285', line US of end MH restricts to 6"

No repairs needed, just keep clean of settled solids, roots, and grease.

"Sunset Hts to Wild Apple Dr"; clay, DS, no grease, low fast flow, evidence of nearly full pipe, PVC conn. @ 74', clay conn. @ 79', moderately broken pipe joint @ 106', roots in joint @ 111'/146', clay 122A 10 04/27/15 116 453 8" conn. w/roots @ 118', moderately cracked pipe joint @ 126', clay conn. w/cracked pipe & moderate roots into main @ 147', moderate roots in joint @ 152', clay conn. w/moderate roots @ 156', heavy roots @ 157', Inspection ends @ 157' due to root blockage

Clean line, reinspect, and probably CIPP entire line.

"Vista Dr"; clay, DS, no grease, low slow flow, evidence of nearly full pipe, heavy debris deposits, roots in joint @ 17'/47'/62', moderate roots 122A 11 04/27/15 446 441 8" @ 55', moderately cracked pipe w/roots @ 63', heavy roots & possible pipe crack @ 137', Inspection ends @ 137' due to root blockage

Clean line, reinspect, and probably CIPP entire line.

"Vista Dr"; clay, US, moderage grease, slow deep flow w/heavy debris diposits due to unseen sag or blockage @ start, evidence of full pipe, 122A 12 04/27/15 441 ??? 8" roots in joint @ 62', cracked pipe joint @ 77', clay conn. w/cracked lateral @ 77', PVC conn. @ 100', US concrete masonry block MH @ 181',

Clean line and reinspect.

Page 33 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Vista Dr"; clay, US, moderate grease, low slow flow, evidence of full 122A 12 04/27/15 ??? 446 8" pipe, heavy debis deposits, roots in joint @ connection to unknown MH (0'), heavy roots @ 249', Inspection ends @ 435 due to root blockage

Clean line, reinspect, reseal connection to starting manhole, and CIP Point Repair at 249'.

"Vista Dr"; clay, DS, some grease, variable flow rate & depth due to 122A 13 04/27/15 441 ??? 195 8" sags and debris, evidence of full pipe, moderate debris, heavy pipe crack @ 66', DS concrete masonry block MH @ 195'

CIP Point Repair at 66'.

"Vista Dr"; clay, DS, some grease, low fast flow, evidence of full pipe, 122A 13 04/27/25 ??? 440 197 8" gasket falling out of joint @ 30', PVC conn. @ 145', moderately cracked pipe @ 156', DS concrete masonry block drop in MH 440 @ 197'

CIP Point Repair at 156'.

"E 7th St"; clay, DS, some grease, low slow flow, evidence of nearly full 122A 14 04/27/15 155 170 358 8" pipe, multiple line sags, moderate debris & silting, clay conn. @ 350', DS concrete masonry block MH 170 @ 358'

No repairs needed, just keep clean of settled solids and grease.

"E 7th St"; clay, DS, some grease, low slow flow, evidence of full pipe, 122A 14 04/27/15 170 309 314 8" multiple line sags, some debris & silting due to line sags, PVC conn. @ 64', clay conn. @ 137', DS precast MH 309 @ 314'

No repairs needed, just keep clean of settled solids and grease.

"Old Exeter Rd"; clay, US, some grease, low fast flow, evidence of 1/3 full pipe, PVC conn. @ 37', clay conn. @ 45'/142', moderate roots in 122A 15 04/28/15 442 440 8" joint @ 146', cracked pipe w/moderate roots in joint @ 157', Inspection ends @ 157' due to root blockage

Clean line and reinspect.

"Old Exeter Rd"; clay, DS, some grease, low fast flow, Evidence of 1/3 122A 16 04/28/15 442 443 389 8" full pipe, Inspection ends @ 295'

Continues on Disc 122B Chapter 1

"Old Exeter Rd"; clay, DS, some grease, low fast flow, evidence of 1/3 122B 1 04/28/15 442 443 389 8" full pipe, PVC pipe section from 281' to 389', DS precast MH 443 @ 389'

No repairs needed, just keep clean of settled solids and grease.

"Old Exeter Rd to West Gate"; clay, DS, some grease, low fast flow, evidence of 1/3 full pipe, moderate roots in joint w/possible crack @ 66', 122B 2 04/28/15 444 ??? 419 8" moderate roots in joint @ 111'/166'/265', depth varies to 1/3 full due to sags & roots, roots in joint @ 201'/285'/295'/325', DS concrete masonry block MH @ 419'

Clean to remove roots and CCTV to determine extent of root damage

Page 34 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Old Exeter Rd to West Gate"; clay, DS, some grease, variable flow 122B 2 04/28/15 ??? ??? 8" depth & rate from low fast to 1/3 full slow due to debris & sags, Inspection ends @ 73' due to debris blockage

Clean and CCTV to complete inspection

"Wild Apple Dr to Sunset Hts"; clay, US, no grease, low fast flow, evidence of 1/3 full pipe, multiple offset joints, PVC conn. @ 41'/67', cracked pipe @ 67', roots in joint @ 142'/152'/158', moderately offset 122B 3 04/28/15 453 116 8" joint w/roots @ 147', conn. of uknown material due to buildup @ 158', moderate roots in crack @ 162', PVC conn. @ 167', heavy roots in joint @ 168', Inspection ends @ 168' due to root blockage

Clean and CCTV to complete inspection

"Wild Apple Dr to Sunset Hts"; clay, DS, very little grease, low fast flow, evidence of 1/3 full pipe, roots in joint @ 15'/25', moderate roots in joint 122B 4 04/28/15 453 452??? 8" @ 21', heavy roots in joint @ 41', Inspection ends @ 41' due to root blockage

Clean and CCTV to complete inspection

"Wild Apple Dr"; clay, US, some grease, flow rate & depth vary due to 122B 5 04/28/15 452 453??? 183 8" joint offsets, evidence of 1/2 full pipe, multiple offset joints, some debris, PVC conn. @ 123', US precast w/brick corbel MH @ 183'

Consider replacing line to eleviate offset joints.

"Wild Apple Dr to Old Exeter Rd"; clay, DS, no grease, low fast flow, evidence of 2/3 full pipe, cracked pipe @ 31'/51'/86'/126', PVC conn. @ 122B 6 04/28/15 452 451 8" 87', PVC pipe section starts @ 174', Inspection ends due to severity of offset of joint @ 174', Video labelling does not match map

Clean line and CIPP. Reinspect pipe from down stream manhole to complete inspection.

"Old Exeter Rd"; clay, US, some grease, low fast flow, evidence of 2/3 122B 7 04/29/15 458 457 8" full pipe, roots in joint @ 27', heavy roots in joint @ 32', Inspection ends @ 32' due to root blockage, Video labelling does not match map

Clean and CCTV to complete inspection

"Old Exeter Rd to 1st St"; clay, US, moderate grease, quarter full pipe 122B 8 04/29/15 458 226 8" with slow flow, evidence of full pipe, roots in joint @ 14'/19'/24', heavy roots @ 43', Inspection ends @ 43' due to root blockage

Clean and CCTV to complete inspection

"West Gate"; clay, US, some grease, fast flow w/variable depth, 122B 9 04/29/15 128 ??? 269 8" evidence of higher flow, PVC conn. @ 13', clay conn. @ 87', US concrete masonry block MH 269'

No repairs needed, just keep clean of settled solids and grease.

"West Gate"; clay, DS, some grease, fast flow with variable depth, PVC 122B 10 04/29/15 128 127 375 8" conn. @ 83'/177'/185'/286'/287'/315'/339', clay conn. @ 105', DS concrete masonry block MH 127 @ 375'

No repairs needed, just keep clean of settled solids and grease.

Page 35 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Kenney Dr"; clay, US, very little grease, low fast flow, evidence of nearly full pipe, offset joint @ 14', PVC pipe section from 14' to 20', 122B 11 04/29/15 124 131 8" moderately broken pipe from 57' to 61', clay conn. w/crack in lateral @ 62', heavy roots in joint @ 73', Inspection ends @ 73' due to root blockage

Clean and CCTV to complete inspection

"Sycamore"; clay, US, some grease, low slow flow, evidence of nearly full pipe, clay conn. @ 59', moderate pipe crack @ 100', clay conn. @ 122B 12 04/29/15 124 125 182 8" 107', moderately broken pipe from 151' to 154', moderately cracked pipe from 162' to 166', US concrete masonry block MH 125 @ 182'

CIP two broken pipe sections

"Sycamore"; clay, DS, very little grease & sediment, low fast flow, 122B 13 04/29/15 124 126 192 8" evidence of full pipe, DS concrete masonry block MH 126 @ 192', Video labelling does not match map

No repairs needed, just keep clean of settled solids and grease.

"Sycamore"; clay, US, video starts in half full pipe, grease line evidence of frequent 3/4 and 4/5 full pipe, some grease, flow and grease levels 122B 14 04/30/15 126 127 118 8' drop @ 66', normal flow is 1/4 pipe & fast, US concrete masonry block MH 127 @ 118' Determine cause of line backup and CCTV line to inspect pipe obscured by high flow levels.

"Sycamore"; clay, DS, some grease, low fast flow, evidence of nearly ful pipe, moderate roots in joint @ 20', some roots in joint @ 40', PVC conn. @ 194', PVC conn. w/heavy grease buildup in main @ 213', 122B 15 04/30/15 126 134 8" possible active infiltration @ 225', PVC conn. protruding into main @ 287', Inspection ends @ 287' due to service line protrusion, Video labelling does not match map

Verify infiltration @ 225' is not flow characteristics due to joint gap, eleviate service later protrusion, and CCTV to complete inspection

"Hwy 76"; clay, DS, some grease, variable flow depth and rate due to 122B 16 04/30/15 134 ??? 145 8" line sags, evidence of nearly full pipe, multiple offset joint, PVC conn. @ 113', DS precast MH @ 145', main line broken into to install MH

No repairs needed, just keep clean of settled solids and grease.

"Hwy 76"; clay, DS, some grease, variable flow depth & rate due to 122B 16 04/30/15 ??? 138 96 8" sags, evidence of full pipe, PVC conn. @ 4', DS precast w/brick corbel MH 138 @ 96'

No repairs needed, just keep clean of settled solids and grease.

"Hwy 76"; clay, DS, moderate grease, variable flow rate & depth, evidence of full pipe, PVC conn. @ 7'/110'/291', multiple offset joints, 122B 17 05/04/15 138 ??? 293 8" moderately offset joint @ 208', flow depth increases to half full @ 270', DS precast w/brick corbel MH @ 293'

Clean line to help eleviate flow depth and CCTV to inspect submerged section.

Page 36 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Hwy 76"; clay, DS, moderate grease, variable flow depth & rate, 122B 17 05/04/15 ??? 139 8" evidence of full pipe, clay conn. @ 55', multiple offset joints, PVC conn. @ 193', Inspection ends @ 237' due to camera line snag

Clean line to help eleviate flow depth and CCTV to inspect submerged section.

"Hwy 76"; clay, US, camera pointed at pipe wall to avoid lense fouling, 122B 18 05/04/15 139 ??? 8" Inspection ends @ 59' due to high flow depth

Resolve flow depth issue and reinspect

"Hwy 76"; clay, DS, moderate grease, variable depth to half full pipe w/rapid flow, evidence of full pipe, video resets at start due to unseen debris blockage, heavy video shaking caused by unseen debris in pipe 123 1 05/04/15 139 140 355 8" until 25', camera caught @ 214' but unable to see cause, PVC conn. @ 239', roots in joint @ 285', camera snags on unseen debris on 332', clay conn. @ 337', DS precast w/brick corbel MH 140 @ 355'

Clean line to help eleviate flow depth and CCTV to inspect submerged section.

"Hwy 76"; clay, US, some grease, thrid full pipe w/rapid flow, 123 2 05/04/15 123 140 46 8" moderately offset joint @ 37', US precast w/brick corbel MH 140 @ 47'

No repairs needed, just keep clean of settled solids and grease.

"Hwy 76"; clay, DS, some grease, quarter full pipe w/rapid flow, 123 3 05/04/15 123 ?122? 48 8" evidence of full pipe, clay conn. @7', offset joint @ 23', DS precast MH 122? @ 48'

No repairs needed, just keep clean of settled solids and grease.

"Hwy 76"; clay, DS, moderate grease, quarter full pipe/rapid flow, 123 3 05/04/15 ?122? ??? 135 8" evidence of full pipe, clay conn. @ 129', DS precast w/brick corbel MH @ 135'

No repairs needed, just keep clean of settled solids and grease.

"Hwy 76"; clay, DS, moderate grease, variable flow depth & rate, 123 3 05/04/15 ??? ??? 248 8" evidence of full pipe, clay conn. @ 244', DS MH @ 248', unable to see MH material due to unknown source of water pouring on camera

Reinspect to determine source water in end MH. No repairs needed, just keep clean of settled solids and grease.

"Hwy 76"; clay, US, moderate grease, variable depth w/rapid flow, evidence of full pipe, possible roots in joint @ 6', clay conn. @ 23', 123 4 05/04/15 ??? ??? 265 8" conn. of unknown material due to grease build up in lateral & in main @ 38', DS precast w/brick corbel MH @ 265'

Proper inspection not possible due to high flow levels and lens fouling.

"Hwy 76"; clay, DS, moderate grease, variable depth w/rapid flow, 123 5 05/04/15 ??? 182 136 8" evidence to full pipe, debris in line hindered camera @ 37'/53', roots or debris on top of pipe @ 43'/48'/53'/83', DS brick MH 182 @ 136'

No repairs needed, just keep clean of settled solids and grease.

Page 37 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Gravel St"; clay, US, some grease, low fast flow, evidence of half full pipe, clay conn. w/grease buildup in main @ 61', PVC conn. @ 123 6 05/05/15 121 120 8" 81'/196', clay conn. @ 131'/159', Inspection ends @ 215' due to blockage

Clean line to remove blockage and reinspect line.

"Gravel St"; clay, DS, some grease, variable flow depth & rate, evidence 123 7 05/05/15 121 122 239 8" of full pipe, clay conn. @ 18', heavy root intrusion @ 20', PVC conn. @ 29'/88', DS precast MH 122 @ 239'

No repairs needed, just keep clean of settled solids and grease.

"Rainbow Dr"; clay, DS, no grease, low slow flow, evidence of 3/4 full pipe, clay conn. @ 102'/139'/148'/172'/251', sediment in pipe, cracked 123 8 05/05/15 117 118 295 8" pipe @ 182', cracked pipe @ 271', PVC conn. @ 334', DS concrete masonry block MH 118' @ 295'

Review need for repairs to cracks based on basin needs.

"Mountain St"; clay, DS, no grease, low slow flow, evidence of , clay conn. @ 35'/140'/194'/254', conn. w/complete root blockage @ 41'/61', 123 9 05/05/15 221 222 316 8" root in joint @ 58'/69'/292', multiple offset joints, cracked pipe & popout @ 271', clay conn. w/heavy root blockage @ 293', PVC pipe section from 310' to 316', DS dropin MH 222 @ 316'

No immediate repairs. Clean line & try to removed root blockage from laterals. Potentially place LCR in rooted laterals. Regularly inspect line break @ 271' to insure stability.

"3rd St"; clay, US, no grease, no flow, evidence of half full pipe, heavily 123 10 05/05/15 222 111 98 8" broken pipe @ 43', US concrete masonry block MH 111 @ 98'

No immediate repairs. Regularly inspect line break @ 43' to insure stability.

"Mountain St"; clay, DS, some grease, low slow flow, evidence of third full pipe, black PVC conn. @ 11', moderate roots in joint @ 123 11 05/05/15 222 223 250 8" 25'/155'/176', clay conn. @ 84'/238', some debris deposits, multiple offset joints, possible roots in joint @ 125', clay conn. protruding into main @ 186', PVC conn. @ 190', DS precast MH 222 @ 250'

Clean roots from line and potentially cut protruding lateral.

"Mountain St"; clay, DS, some grease, low slow flow, evidence of higher 123 11 05/05/15 223 224 19 8" flow, DS brick MH @ 19'

No repairs needed, just keep clean of settled solids and grease.

"Mountain St"; clay, DS, some grease, low slow flow, evidence of full pipe, multiple offset joints, clay conn. @ 62'/146'/204', roots in joint @ 123 12 05/05/15 224 226 212 8" 91'/121', clay conn. w/moderate offset @ 209', dropin to DS brick MH 226' @ 212'

No repairs needed. Clean line of roots and perform regular checks of offset cleanout connection.

Page 38 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Mountain St"; clay, US, some grease, variable flow depth & rate due to grade changes & offsets, evidence of , multiple offset joints, possible 123 13 05/05/15 226 458 8" line crack @ 58', possible roots in joint @ 108', roots hanging from top of main in possible crack, heavy roots @ 168', Inspection ends @ 168' due to root blockage, Video labelling does not match map.

Clean line and reinspect. Map does not indicate a connection between the two labelled manholes.

"1st St"; clay, DS, some grease, low fast flow, evidence of full pipe, roots 123 14 05/07/15 226 184 8" in joint @ 11'/38'/49'/54'/57', moderate roots in joint @ 63'/81', heavy roots in joint @ 69'/75'/90', Inspection ends @ 90' due to root blockage

Clean line and reinspect. Map does not indicate a connection between the two labelled manholes. "1st St"; clay, DS, moderate grease, quarter full & fast flow, evidence of nearly full pipe, flow varies due to line grade changes & joint offsets, 123 15 05/07/15 184 183 179 8" clay conn. @ 62', possible conn. @ 83', 6" clay conn. @ 104', DS precast MH 183 @ 179'

Clean line and reinspect.

"1st St"; clay, DS, some grease, variable flow rate & depth due to sags & grading, evidence of full pipe, evidence of full pipe, multiple offset joints, clay conn. @ 90'/115', PVC pipe section from 95' to 97', PVC 123 15 05/07/15 183 181 211 8" conn. protruding into main 96', clay conn. w/heavy debris in lateral @ 100', PVC conn. @ 105'/139', cracked pipe @ 378', DS precast or rehabbed MH 181 @ 211'

Clean line and consider lining pipe to eleviate poor flow characteristics caused by joint offsets.

"1st St"; clay, DS, some grease, conn. @ 6', clay conn. @ 62'/82'/116', PVC section from 115' to 117', shaking camera from settled debris & 123 16 05/07/15 181 182 188 8" high flow level aroun 175' due to line sag, DS rehabbed or precast w/brick corbel MH 182 @ 188' Clean line and consider lining pipe to eleviate poor flow characteristics caused by joint offsets.

"Sky Ave"; clay, US, no grease, no flow, clay conn. @ 59', root in joint 124 1 05/07/15 108 107 75 8" @ 70', PVC conn @ 71', US clay lamp hole @ 75'

No repairs needed, just keep clean of settled solids and grease.

"Sky Ave"; clay, DS, some grease, no flow, evidence of half full pipe, 124 2 05/07/15 107 108 123 8" settled debris @ 51', clay conn. @ 58', DS concrete masonry block MH 108 @ 123'

No repairs needed, just keep clean of settled solids and grease.

"Sky Ave"; clay, US, some grease, low slow flow, evidence of half full 124 3 05/07/15 57 108 294 8" pipe, settled deposits due to low flow, US concrete masonry block MH 108 @ 294'

No repairs needed, just keep clean of settled solids and grease.

"Sky Ave"; clay, some grease, low slow flow, evidence of higher flow, stagnant water with heavy settled material, camera turned to avoid 124 4 05/07/15 108 ??? 205 8" fouling until 79', lens is fouled making inspection difficult, uninspected conn. @ 165', concrete masonry block MH @ 205'

Clean and CCTV to complete inspection.

Page 39 of 56 From DVD Chpt Month Year To MH LF Comments MH

"7th St"; clay, no grease, low slow flow, evidence of half full pipe, clay 124 5 05/07/15 57 58 202 8" conn. @ 32'/57'/162', cracked pipe from conn. @ 57', DS precast or rehabbed MH 58 @ 202', moderate roots in MH 58

Clean and determine condition of MH 58. No repairs needed to main, just keep clean of settled solids and grease.

"Oak St"; clay, US, no grease, low slow flow, evidence of half full pipe, 124 6 05/08/15 109 ??? 225 8" clay conn. w/roots in joint @ 48', US probable concrete masonry block MH @ 225'

No repairs needed, just keep clean of settled solids and grease.

"Oak St"; clay, DS, no grease, nearly no flow, evidence of higher flow, depositted material on top of pipe indicating infiltration @ 62', clay conn. 124 7 05/08/15 109 58 8" w/heavy roots from joint @ 88', Inspection ends @ 88' due to root blockage

Clean and CCTV to complete inspection.

"Oak St"; clay, US, heavy grease & roots @ start w/little to no grease 124 8 05/11/15 58 109 8" after 10', low slow flow, Inspection ends @ 18' due to heavy root blockage

Clean and CCTV to complete inspection.

"7th St"; clay, DS, some grease, low fast flow, evidence of half full pipe, clay conn. w/moderate roots @ 6', roots in joint @ 12'/17'/72'/99', clay 124 9 05/11/15 58 59 185 8" conn. w/roots in cracked lateral @ 73', clay conn. w/moderate grease in lateral, clay conn. @ 113', clay conn. @ 182', DS brick MH 59 @ 185'

Clean and CCTV to ensure root removal. No repairs need.

"7th St"; clay, DS, some grease, low fast flow, evidence of half full pipe, 124 9 05/11/15 59 60 191 8" PVC conn. @ 3'/15', clay conn. @ 78', roots in joint @ 120'/157', DS concrete masonry block MH 60 @ 191'

No repairs needed, just keep clean of settled solids and grease.

"8th St"; clay, DS, some grease & settled material, no flow, evidence of 124 10 05/11/15 56 55 225 8" quarter full pipe, clay conn. @ 11', PVC conn. @ 49', clay conn. w/offset lateral joint @ 75'/142', DS brick MH 55 @ 225'

No repairs needed, just keep clean of settled solids and grease.

"8th St"; clay, DS, some grease, low slow flow, evidence of 3/4 full pipe, PVC pipe section from 46' to 50', PVC conn. @ 49', moderate joint 124 10 05/11/15 55 54 161 8" offset @ 50', clay conn. w/poor lateral conn. joint @ 118', uninspected conn. @ 156', DS brick MH 161'

No repairs needed, just keep clean of settled solids and grease. Consider CCTV again to inspect connection at 156'.

"8th St"; clay, DS, no grease, low slow flow, evidence of 3/4 full pipe, roots in joint @ 87'/96'/135'/144'/147'/165'/181', moderate roots in joint 124 11 05/11/15 54 52 258 8" @ 93'/99'/102'/105', clay conn. @ 182', possible crack @ 208'/211', clay conn. @ 227', DS brick MH 258'

Clean line and reinspect to determin extent of root damage and check possible cracks.

Page 40 of 56 From DVD Chpt Month Year To MH LF Comments MH

"7th St"; clay, US, no grease, low fast flow, evidence of half full pipe, clay conn. w/heavy grease in lateral @ 6', uninspected conn. @ 38', 124 12 05/12/15 61 60 185 8" conn. w/heavy root blockage @ 103', roots in joint @ 103'/112', multiple offset joints, clay conn. @ 183', US brick MH 60 @ 185'

Clena line to remove roots and reinspect to insure removal of blockage at 103'.

"7th St"; clay, DS, no grease, low fast flow, evidence of 3/4 full pipe, clay 124 13 05/12/15 61 62 211 8" conn. @ 95'/109'/183'/204'/208', DS brick MH 63 @ 211'

No repairs needed, just keep clean of settled solids and grease.

"8th St"; clay, US, minor grease, low fast flow, evidence of half flow pipe 125 1 05/12/15 63 52 175 8" multiple offset joints, very minor root growth in some joints, PVC conn. @ 5', clay conn. @ 52'/103',

No repairs needed.

"Townsend St"; clay, 3' pipe sections, DS, minor grease, minor roots in 125 2 05/12/15 63 64 8" joint @ 18'/30'/33'/, moderate roots in joint @ 72', Inspection ends @ 72' due to root blockage Clean line and reinspect to complete inspection. Probably CIP Point Liner at 72'.

"6th St"; clay, 3' pipe sections, US, very minor grease, very low flow, evidence of quarter full pipe, clay conn. @ 6', moderate roots in joint at 125 3 05/12/15 110 220 8" 35'/41', clay conn. w/heavy roots up in lateral @ 39', moderate roots in lateral at 43', heavy roots in joint at 47', heavy roots from lateral into line @ 55', Inspection ends at 54' due to heavy root presence

Clean line and reinspect to complete evaluation. Determine need of repaires to lateral connections after roots are removed. Possible LCR at 39', 43', 47', and 55'.

"6th St"; clay, 3' pipe sections, DS, very minor grease, very low flow, evidence of quarter full pipe, frequent minor joint offsets, possible 125 4 05/12/15 110 ??? 189 8" moderate pipe crack @ 85' is skipped by video, clay conn. @ 121'/142', minor roots in joint @ 168'/174', moderate roots in joint @ 177'/180', DS brick MH @ 189'

No immediate repairs needed. Maintain routine pipe cleaning and monitoring to prevent future root growth.

"6th St"; clay, 3' pipe sections, DS, no grease, very low flow, evidence of full pipe, multiple offset joints, clay conn. @ 91'/100'/130'/139'/192', 125 4 05/12/15 ??? 189 199 8" moderately broken pipe w/possible external repair @ 180', possible moderate broken pipe @ 193', DS precast concrete MH 189 @ 199'

Confirm pipe break at 180' is fixed and inspect crack at 193'. Possible CIP Point Liner at 180' and 193'.

"Townsend St"; clay, 3' pipe sections, minor grease, very low flow level, 125 5 05/12/15 189 62 208 8" evidence of half full pipe, clay conn. @ 30'/35'/50'/126'/168', PVC conn. @ 49', uninspected conn. @ 99', DS brick MH 62 @ 208'

Though not likely to have issues, reinspect to evaluate condition of connection at 99'. No other repairs needed.

Page 41 of 56 From DVD Chpt Month Year To MH LF Comments MH

"6th St"; clay, DS, 3' pipe sections, minor grease, low flow level, evidence of nearly full pipe, clay conn. w/moderate offset @ 70'/230', 125 6 05/12/15 189 216 233 8" clay conn. @ 72', moderate crack @ 75', clay conn. w/unevaluated obstruction @ 87', PVC conn. @ 154', DS precast MH 216 @ 233', moderately broken MH 216 invert

CIP Point Liner at 72' and repair invert in manhole 216.

"6th St"; clay, DS, 3' pipe sections, minor grease, low flow level, evidence of 2/3 full pipe, multiple minor join offsets, clay conn. @ 2'/84'/90'/104'/126', flow depth & debris on camera blocking visibility 125 6 05/12/15 216 ??? 8" until 38', clay conn. w/moderately offset joint @ 115/139'', minor sag with settled debris @ 212', Inspection ends @ 231' due to debris blockage

Clean line and reinspect.

"Gravel St"; clay, DS, 3' pipe sections, minor grease, low slow flow, clay 125 7 05/13/15 188 187 8" conn. w/moderate offset @ 5', clay conn. @ 6', sag starting @ 30' is too deep and fouls lense, Inspection ends @ 62' due to flow depth

Clean line and reinspect.

"Gravel St"; clay, US, 3' pipe sections, moderate grease, low slow flow, evidence of 1/3 full pipe, clay conn. @ 9'/62'/65'/84', moderate joint offset @ 9', muliple minor joint offsets, unevaluated conn. @ 175', moderate offset joint @ 175'/187', clay conn. w/moderate debris 125 8 05/13/15 187 188 403 8" blockage @ 186', clay conn. w/major break @ 193', minor roots in minor offset joint @ 223', minor roots in joint @ 226'/244'/252'/255', moderate roots in joint @ 258', major roots in joint @ 261', Inspection ends @ 258' due to root blockage.

Clean line and reinspect. Probable Joint Pressue Testing and Grout filling needed with the lateral connection at 193' requiring Grouting as well.

"Gravel St"; clay, DS, 3' pipe sections, moderate grease, low slow flow, evidence of half full pipe, moderate debris and settled material, 125 9 05/13/15 187 214 254 8" moderate roots in joint @ 25'/40'/47'/58'/79'/85'/88', major roots in joints @ 50'/82', minor roots in joint @ 64'/67'/70', clay conn. with moderate roots @ 73', Inspection ends @ 83' due to heavy root blockage.

Clean line and reinspect. Pressure test Joints and Grout as needed. Grout repair connection at 73'. "Gravel St"; clay, US, 3' pipe sections, some grease, low slow flow, 125 10 05/13/15 214 187 254 8" minor roots in joint @ 21'/24'/27', major roots in joint @ 30', Inspection ends @ 30' due to heavy root blockage. Clean line and reinspect. Pressure test joints and grout as needed.

"Gravel St"; clay, US, 3' pipe sections, some grease, low slow flow, evidence of nearly full pipe, many offset joints, minor roots in joint @ 125 11 05/13/15 214 185 200 8" 26'/39', clay conn. @ 40'/55', clay conn. w/moderate offset @ 67', clay conn. w/minor buildup or moderat offset, clay conn. with minor offset & cracked lateral pipe @ 174', DS brick MH 185 @ 200'

Clean line and monitor future root growth. LCR at 174'.

Page 42 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Gravel St"; clay, DS, line inspected in reverse, 3' pipe sections, minor 125 12 05/13/15 185 186 20 8" grease, unevaluated conn. @ 11', Inspection ends before MH is reached.

Reinspect to complete evaluation.

"Gravel St"; clay, DS, moderate grease, low slow flow, evidence of full pipe, PVC conn. @ 11', clay conn. w/heavy offest @ 30', PVC conn. @ 125 13 05/13/15 185 184 8" 33', grease covering pipe from top to bottom in many sections, major grease build up possibly on roots @ 104', severe grease dam @ 107', Inspection ends @ 107' due to grease blockage.

Clean line and reinspect. Perform regular inspections to monitor grease buildup. Open cut repair lateral connection at 30'.

"Gravel St"; clay, DS, no grease, debris in line causing difficulty 125 14 05/13/15 185 184 8" w/inspection, low slow flow, unevaluated conn. (probable PVC) @ 12', Inspection ends @ 42' due to rock in the line

Clean and reinspect to complete evaluation.

"West St"; clay, US, 3' pipe sections, no grease, very low flow, evidence of 2/3 full pipe, multiple offset joints, unevaluated conn. w/minor to moderate pipe crack @ 19', broken pipe (possibly capped hammer-tap) 125 15 05/13/15 218 217 195 8" @ 32', clay conn. @ 32'/51'/106'/108'/166'/193', major joint offset @ 32', clay conn. w/moderate debris in lateral @ 56', clay conn. w/moderate grease in lateral @ 83', clay conn. w/moderate offset lateral joint @ 93'/178', US brick MH 217 @ 195'

Repair broken pipe and offset joint at 32' with CIP Point Liner, re- establishing lateral connection.

"West St"; clay, US, 3' pipe sections, no grease, low slow flow, evidence of 2/3 full pipe, clay conn. @ 11', major pipe break w/failed repair from 125 16 05/13/15 218 219 200 8" 14' to 19', lense fouled removing visibility from 62' to 66', unevaluated clay conn. @ 62', unevaluated PVC conn. @ 66', clay conn. @ 106'/162', DS brick MH 218 @ 200'

CIP point liners from 14' to 19'. Clean line and evaluated connections at 62' and 66' when installing liner.

"4th St"; clay, DS, 3' pipe sections, minor grease, variable flow rate & depth, evidence of full pipe, multiple offset joints, clay conn. w/major 125 17 05/14/15 219 ??? 180 8" debris in lateral @ 68'/135', clay conn. w/unevaluated damage to pipe @ 109', clay conn. w/moderate debris @ 112'/114', clay conn. @ 112', backup fouls lens @ 170', DS brick MH @ 180'

Check usage of connection at 68' and 135'. Clean line and re- evaluate with lower flow level.

Page 43 of 56 From DVD Chpt Month Year To MH LF Comments MH

"West St"; clay, US, 3' pipe sections, minor grease, variable flow rate & depth, evidence of full pipe, multiple offset joints, clay conn. @ 20'/65'/177'/228'/270', clay conn. w/moderate offset @ 26', major unevaluated joint offset @ 26', clay conn. w/heavily damaged main from hammer tap & material buildup in lateral @ 41', black PVC conn. @ 49', 125 18 05/14/15 219 180 275 8" PVC conn. @ 90', probable capped PVC conn. @ 95', lens fouled at 110' inhibitting evaluation, unevaluated clay conn. @ 118', clay conn. @ 137' (does not look used), moderately offset joint @ 167', clay conn. w/minor lateral line cracks @ 219', US precast MH 180 @ 275', Map indicates line is DS

Consider open cut repair at 41' based on feasibility of access (discuss with City) otherwise use CIP Point Liner and LCR. Determine use of connections at 95' and 137'. Update GIS map to indicate opposite flow direction.

"West St"; clay, US, no grease, variable flow level, evidence of nearly full pipe, clay conn. @ 5'/48'/54'/127'/217'/241'/296', PVC conn. @ 125 19 05/14/15 180 181 - 8" 41'/75'/149'/250', PVC pipe section w/heavy offset @ 144', unevaluated conn. @ 216', major pipe break w/void @ 225', heavy offset pipe section @ 245', Inspection ends @ 341' due to memory space

Inspection is completed on Disc 126 Chapter 1. See for comments. "West St"; clay, US, no grease, variable flow level, evidence of nearly 126 1 05/14/15 180 181 464 8" full pipe, Inspection begins @ 343', unevaluated conn. @ 344'/359', US precast MH 181 @ 464' w/damaged invert.

Open cut repair at 144' and 245'. CIP Point Liner @ 225'. Evaluate invert in manhole 181 to determine if invert repair is needed.

"1st St"; clay, US, nothing visible due to high flow depth, Inspection 126 2 05/14/15 144 182 237 8" ends @ 237' in brick MH 182

Reinspect when flow level is lower. Clean if necessary.

"1st St"; clay, DS, Video starts @ 155' & evaluates the line as the 126 3 05/14/15 182 144 237 8" camera is being removed, flow is fast and about 1/3+ full,

Reinspect when flow level is lower. Clean if necessary.

"Behind Carr Plaza"; clay, US, moderate grease, low slow flow, evidence of nearly full pipe, multiple offset joints, clay conn. w/minor 126 3 05/14/15 144 ??? 138 8" lateral pipe offset @ 5', moderate joint offset @ 17'/87'/92'/108', clay conn. @ 31', Inspection ends at unknown service conn. or lamphole. @ 138'

Pressure test joints and grout as needed.

"Behind Carr Plaza"; clay, DS, minor grease, third full pipe with fast flow, clay conn. @ 5', PVC conn. @ 56', camera is submerged from 63' to 92' prohibitting inspection, unclear image of unevaluated debris or 126 4 05/14/15 144 145 8" conn. on top of line @ 98', protruding clay lateral w/major debris blockage @ 119', Inspection ends @ 119' due to protruding service lateral

Cut tap at 119'. Consider reinspection when flow is lower.

Page 44 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Behind Carr Plaza"; clay, DS, moderate grease, third full pipe with fast flow, evidence of full pipe, PVC conn. @ 14'/16'/276'/350', clay conn. @ 126 5 05/15/15 145 148 8" 152'/194'/261', clay conn. completely blocked @ 248', conn. w/heavy grease in lateral @ 381', Inspection ends @ 381' due to lateral protruding into main.

Determine usage of lateral connection at 248'. Cut tap at 381' and complete inspection.

"Behind Dollar General"; clay, DS, moderate grease, third full pipe with fast flow, evidence of full pipe, debris hanging from top of pipe, clay 126 6 05/15/15 148 ??? 8" conn. @ 31'/125', unevaluated conn. @ 39', camera submerged from 125' to 171', Inspection ends @ 171' due to depth of flow.

Try to reinspect during a period of lower flow. Clean line to remove debris.

"West 4th & Main St"; clay, DS, minor grease, low slow flow, evidence of half full pipe, moderate pipe crack from 8' to 9', most joints have 126 7 05/18/15 ??? 152 280 8" minor offsets, heavily broken pipe @ 109', clay conn. w/moderate offset lateral pipe @ 121', DS brick MH 152 @ 280'

CIP Point Liner from 8' to 9' and at 109'.

"East St"; clay, US, minor grease, variable flow depth and rate, evidence of over half full pipe, camera submerged at 47' to 54', clay conn. @ 57', 126 8 05/18/15 152 151 8" camera submerged from 61' to 97' and 115' to 153', Inspection ends @ 153' due to unseen obsical blocking camera

Clean line and try to reinspect with lower flow level.

126 9 05/18/15 151 179 8" "East"; clay, DS, line not inspected, camera does not move.

Line reinspected on Disc 126 Chapter 10.

"East St"; clay, DS, 3' pipe sections, minor grease, quarter full pipe, evidence of , moderate settled debris, PVC conn. @ 98', clay conn. @ 126 10 05/18/15 179 151 8" 112'/179', clay conn. w/moderately offset & broken lateral line @ 154', high flow depth around 170' to 186' preventing inspection, Inspection ends @ 186' due to high flow depth.

LCR Liner at 154'. Clean line and try to reinspect when flow is lower.

"East Ave"; clay, DS, 3' pipe sections, minor grease, variable flow rate & depth, evidence of nearly full pipe, clay conn. w/heavy offset @ 72'/85', 126 11 05/19/15 179 178 187 8" clay conn. @ 82'/100'/139', moderately cracked pipe @ 84', PVC conn. @ 92', lens fowled @ 152' reducing visibility, high flow depth from 152' to 186', DS brick MH 178 @ 187'.

LCR Liner at 72' and 85'. CIP Liner at 84'. Clean line and try to reinspect with lower flow.

"9th St"; clay, US, 3' pipe sections, minor grease, low fast flow, evidence of half full pipe, moderate debris settling, clay conn. @ 11'/17'/72'/100', 126 12 05/19/15 215 ??? 260 8" possible unevaluated cracked pipe @ 147', PVC conn. @ 240', clay conn. @ 256', US brick MH @ 260'

Unable to determine if line is cracked at 147'. The rest of the line is in good condition.

Page 45 of 56 From DVD Chpt Month Year To MH LF Comments MH

"9th St"; clay, US, 3' pipe sections, minor grease, low flow, evidence of 126 12 05/19/15 ??? 65 143 8" half full pipe, clay conn. w/minor offset @ 11', clay conn. @ 35'/60'/115'/132'/135', US brick MH @ 143' Clean line to remove grease and any settled solids, no repairs needed.

"East Ave"; clay, DS, 3' pipe sections, minor grease, low flow, evidence of , moderate deposits in line, moderate pipe crack @ 48', clay conn. @ 126 13 05/19/15 215 177 8" 50'/77'/111'/135'/140', video skips from 92' to 94' missing a service lateral, Inspection ends @ 157' due to lens fowling and debris blocking line.

Clean line and reinspect.

"10th St"; clay, heavy deposits in line, no flow visible, line is not 126 14 05/19/15 8 6 8" inspected due to height of debris, Map does not match video label as MH 6 & 8 do no connect.

Line is completely blocked by debris, clean and re-evaluate.

"East Ave"; clay, DS, minor grease, 3' pipe sections, low fast flow, 126 15 05/19/15 169 5 120 8" evidence of third full pipe, clay conn. @ 18', PVC pipe @ 80', DS brick MH 5 @ 120'

No repairs needed.

"East Ave"; clay, US, 3' pipe sections, minor grease, heavy debris, 126 16 05/19/15 169 168 8" variable flow depth & rate, clay conn. @ 6', Inspection ends @ 10' due to debris blockage.

Clean line and reinspect.

"East Ave"; clay, DS, 3' pipe sections, minor grease, low slow flow, evidence of half full pipe, most joints have minor offsets, heavy debris deposits, clay conn. @ 6'/44'/62'/138', clay conn. w/moderate offset 126 17 05/19/15 168 169 445 8" lateral joint @ 43', PVC conn. @ 127'/344', minor roots in joint @ 218'/221'/232'/245',253', moderate roots in joint @ 257'/260', heavy roots in probable lateral conn. @ 258', clay conn. w/heavy roots in lateral joint @ 272', minor pipe crack @ 434', DS brick MH 169 @ 445'

Clean line to remove roots and debris; install CIP Point Liner at 257' and 260'; and install LCR Liner at 43', 258', and 272'. Reinspect to evaluate probable connection at 258' and cracked pipe at 434'.

"East Ave"; clay, US, 3' pipe sections, minor grease, low unrestricted flow, evidence of 1/3 full pipe, frequent minor offset joints, clay conn. @ 34'/99'/163'/240'/287'/348', moderate offset joint @ 345'/394', minor 126 18 05/19/15 168 167 8" roots in joint @ 248'/385'/397'/406'/409'/415', unevaluated conn. @ 388', clay conn. w/moderate roots from joint @ 396', Inspection ends @ 432' due to end of disc space, continues on Disc 127 Chapter 1

See Disc 127 Chapter 1 for comments.

"East Ave"; clay, US, 3' pipe sections, minor grease, flow has dropped 127 1 05/19/15 168 167 8" to zero, evidence of 1/4 full pipe, heavy debris from 247' to 460'+, Inspection ends @ 460' due to mud and debris blockage

Review possibility of open cut repairs to joint offsets at 345' and 394' (possible interferance with power utilities), otherwise consider CIP Point Liner. Clean line to remove debris and reinspect to finish evaluation.

Page 46 of 56 From DVD Chpt Month Year To MH LF Comments MH

"East Ave"; clay, DS, 3' pipe sections, moderate grease, variable flow rate & depth, evidence of full pipe, clay conn. @ 46'/148'/150'/153', 127 2 05/21/15 7 4 8" PVC conn. w/moderate lateral offset joint @ 64', PVC conn. @ 104', lens fowled and pointed to the side from 164' to 200', Inspection ends @ 200' due to flow depth & poor visibility

Inspection is continues on Disc 127 Chapter 3.

"East Ave"; clay, US, 3' pipe sections, moderate grease, variable flow rate & depth, evidence of full pipe, inspection starts w/camera 127 3 05/21/15 4 7 8" submerged & continues w/camera pointed to the side until , clay conn. @ 82'/136', PVC conn. @87'/183', conn. @ 137', heavy roots in joint @ 240', Inspection ends @ 241' due to root blockage

Possible CIP Point Liner at 240', but line needs to be cleaned and reinspected for proper evaluation.

"11th St"; clay, Inspection ends @ 94' due to high flow preventing 127 4 05/21/15 4 6 8" evaluation

Clean line to try to reduce flow level and reinspect.

"11th St"; clay, DS, heavy grease, high fast flow, evidence of full pipe, camera is submerged @ 58', camera angled away from 55' to 70', DS 127 5 05/21/15 4 15 8" precast MH 15 @ 327', inspection tries to continue to next manhole but DS line has an unseen obstical preventing entrying and causing backup

Remove debris from MH 15 or find cause of backup. Clean line and consider reinspected to evaluated missed pipe sections.

"Harold St"; clay, 3' pipe sections, minor grease, low slow flow, evidence of full pipe, PVC conn. @ 8''/16'/18'/71'/160'/162'/199'/270', moderate joint offset @ 18', clay conn. w/minor active infiltration @ 80', 128 1 05/21/15 12 8 459 8" unevaluated conn. @ 141', minor cracked pipe w/minor active infiltration @ 149', clay conn. @ 300'/308'/337'/350'/354', clay conn. w/moderate offset lateral joint @ 384', flow backup starting @ 401' preventing inspection, Inspection ends @ 448' due to flow depth & camera hangup

(↑estimat LCR Liner at 80', CIP Liner at 18' & 149', and clean & reinspect line e) to complete evaluation.

"14th St & East St"; clay, US, minor grease, 3' pipe sections, variable flow rate & depth, evidence of full pipe, moderate joint offset @ 6', high flow depth submerging camera from 12' to 17', multiple minor offset 128 2 05/26/15 167 349 322 8" joints, clay conn. @ 61', moderately cracked pipe around protruding clay conn. @ 111', clay conn. w/major offset lateral @ 171', US brick MH 349 @ 322'

Cut Tap and install CIP Point Liner at 111'. LCR Liner at 171'.

"14th St & East St"; clay, DS, moderate grease, severe pipe break & 128 3 05/26/15 167 ??? 8" offset @ 36', Inspection ends @ 36' due to pipe break.

Open cut repair pipe break at 36'. Reinspect to complete evaluation.

Page 47 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Mill St"; clay, DS, moderate grease, low slow flow, evidence of full pipe, clay conn. @ 60'/113'/261'/325'/359', minor pipe crack 63'/72', clay conn. w/minor offset lateral joints @ 79'/100', PVC conn. @ 128 4 05/26/15 66 0 465 8" 129'/203'/321', major pipe crack @ 121', unevaluated conn. @ 237', clay conn. w/moderate to major unevaluated lateral offset @ 245', minor pipe crack from conn. @ 321' to joint @ 322', moderate roots in minor offset joint @ 358', DS brick MH @ 465'

CIP Point Line at 121', open cut repair at 245', and clean line to eleviate roots.

"Mill St"; clay, DS, minor grease, low slow flow, evidence of full pipe, clay conn. @ 8'/19'/33', moderate joint offset @ 30', minor roots in 128 4 05/26/15 0 1 472 8" moderate joint offset @ 48', unevaluated conn. w/minor to moderate roots @ 51', major roots in joint @ 56', Inspection ends @ 56' due to root blockage

(↑estimat Clean line and reinspect. Possible CIP Point Liner at 48'. e)

"Mill St"; clay, DS, minor grease, low slow flow, evidence of full pipe, mutliple minor offset joints, clay conn. @ 19'/40'/99', minor roots in joint 128 5 05/27/15 2 1 175 8" @ 87'/91'/96', unevaluated conn. @ 104', major debris deposit @ 107', Inspection ends @ 107' due to debris blockage

(↑estimat Clean line and reinspect to complete evaluation. e)

"Mill St"; clay, DS, Minor grease, very low flow, evidence of half full pipe clay conn. w/moderate grease @ 138', clay conn. @ 157', broken joint 128 6 05/27/15 2 3 170 8" to drop line for MH 3 @ 166', vertical exterior drop-in for MH 3 is blocked, Inspection ends @ 166' due to drop-in line, possible further damage to line

Remove blockage from exterior verticle drop-in to Manhole 3. Reinspect line from Manhole to determine if remainder of line is cracked. If possible, CIP Point Liner broken joint at 166', should this fail, Open Cut repair to restore. Revisit repair needs after blockage is cleared and remainder of line is inspected.

"Harold St"; clay, 3' pipe sections, minor grease, third full pipe, evidence 128 7 05/27/15 15 16 500 8" of higher flow, major roots in joint @ 12', Inspection ends due to root blockage, further roots visible beyond blockage

(↑estimat Clean line and reinspect to complete evaluation. Probable CIP e) Point Liner at 12'.

"Harold St"; clay, 3' pipe sections, moderate grease, quarter full line w/slow flow, evidence of higher flow, heavy roots @ 17', Inspection ends 128 8 05/27/15 16 14 (15?) 8" @ 17' due to root blockage, Map conflicts w/labelling and contradicts Disc 128 Chapter 10

(↑estimat Clean line an reinspect to complete evaluation. Probable CIP e) Point Liner at 17'.

"Harold St"; clay, 3' pipe sections, moderate grease, low unimpeded flow, evidence of full pipe, minor roots in joint @ 22'/25'/28'/44', 128 9 05/27/15 16 67 500 8" moderate roots in joint @ 31'/47', unevaluated conn. w/minor to moderate roots @ 43', major roots in joint @ 50', Inspection ends @ 48' due to root blockage Clean line and reinspect to complete evaluation. Probable Joint (↑estimat Pressure Testing and aplicable Grouting as well as Lateral e) Connection Grouting @ 43'.

Page 48 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Harold St"; clay, DS, 3' pipe sections, moderate grease, low slow flow, evidence of full pipe, clay conn. @ 12'/108'/283'/333', minor roots in joint @ 16', broken clay conn. w/major offset & moderate roots @ 17', major broken pipe from 55' to 56', PVC conn. w/root or worm in joint indicating poor seal, moderate offset joint 95', uninspected conn. @ 128 10 05/27/15 16 15 500 8" 114', minor roots in joint @ 132'/153'/159'/162'/449', minor roots in capped conn. @ 148'/157'/441', clay conn. w/moderate offset @ 287', clay conn. w/minor offset & broken lateral @ 426', moderate roots in joint @ 440'/477', major roots in joint @ 480', Inspection ends @ 480' due to root blockage

Clean line and reinspect to complete evaluation. Open Cut Repair (↑estimat connection at 17'. CIPP Liner from 55' to 56', 440', 447', and 480'. e) LCR Liner connection at 426'.

"Harold St"; clay, US, 3' pipe sections, minor grease, low free moving flow, evidence of full pipe, multiple minor pipe joint offsets, capped 128 11 05/28/15 14 15 202 8" conn. w/moderate roots @ 107', joint w/moderate roots @ 108', clay conn. w/moderate roots into main @ 109', major roots from unknown source @ 109', Inspection ends @ 109' due to root blockage

Clean line and reinspect to complete evaluation. CIP Point Liner (↑estimat from 107' to 109' and LCR Liner at 108', or Pressure Test and e) applicable Grouting entire line as well as Lateral Connection Grouting at 108' if necessary.

"E 11th St"; DS, 3' pipe sections, moderate grease, third to full pipe w/rapid flow, evidence of full pipe, debris in line impeding camera 128 12 05/28/15 14 ??? 8" movement, minor pipe crack @ 58', Inspection ends @ 59' due to unseen blockage and high flow depth (↑estimat Clean line and try to reinspect with lower flow level. e) "E 10th St"; DS, 3' pipe sections, minor grease, 2/3 full pipe w/rapid flow, evidence of full pipe, line is too full for inspection, Inspection ends 128 13 05/28/15 10 26 8" @ 17' due to flow depth, Both maps indicate the listed manholes are seperated by MH 8. (↑estimat Try to reinspect during a period of lower flow. e)

"Fair St"; US, 3' pipe sections, moderate grease, over half full pie w/moderate flow, evidence of full pipe, possible minor roots in joint @ 128 14 05/28/15 24 25 8" 72', clay conn. @ 142', minor roots in joint @ 145', Inspection ends @ 151' due to end of disc space, Inspection continues on Disc 129 Chapter 1

See Disc 129 Chapter 1 for comments.

"Fair St"; clay, US, 3' pipe sections, moderate grease, over half full pie w/moderate flow, evidence of full pipe, moderate infiltration in joint @ 184', minor roots in joint @ 200'/206', clay conn. @ 202'/321', clay 129 1 05/28/15 24 25 8" conn. w/minor roots deep in lateral @ 241', clay conn. w/minor broken lateral & moderate grease @ 318', PVC conn. @ 379'/387', clay conn. w/protruding tap @ 398', Inspection stops @ 398' due to protruding tap

Depth of flow preventing proper inspection. Try to reinspect with lower flow. CIP Liner at 184'. Cut Tap at 398'.

Page 49 of 56 From DVD Chpt Month Year To MH LF Comments MH

"E 10th St & Fair St"; clay, DS, 3' pipe sections, over half full pipe, evidence of full pipe, clay conn. w/protruding tap @ 67', PVC conn. @ 79', clay conn. @ 146'/148'/324', clay conn. w/moderate grease & 129 2 05/29/15 25 24 467 8" possible moderate infiltration @ 226', unevaluated conn. @ 253'/388', black PVC conn. @ 264', minor roots in joint @ 267', DS brick MH 25 @ 467', Labelling changed to TRY to match online map. No direct connection can be established.

Flow level prohibited proper inspection, try to reinspect when flow level is lower. Cut tap at 67'.

"11th & Fair St"; clay, DS, 3' pipe sections, moderate grease, over half 129 3 05/29/15 23 21 511 8" full pipe, evidence of full pipe, debris in line, moderate protruding tap @ ~10', Inspection ends @ 5' due to unseen debris blocking line

(↑estimat Clean line and try to reinspect with lower flow level. e)

"Fair St"; clay, US, inspection begins w/camera submerged, Inspection 129 4 05/29/15 17 19 177 8" ends @ 10' due to flow depth

(↑estimat Try to reinspect with lower flow level. e)

"Fair St"; clay, DS, 3' pipe sections, inspection begins w/camera 129 5 05/29/15 18 68 8" submerged, clay conn. @ 85', Inspection ends @ ' due to flow depth

(↑estimat Try to reinspect with lower flow level. e) "E 13th St"; DS, minor grease, low to half full slow flow, evidence of full 129 6 06/01/15 ??? 328 8" pipe, heavy settled solids, Inspection ends @ 88' due to debris blockage (↑estimat Clean line and reinspect. e) "E 13th St"; US, minor grease, low slow flow, evidence of over half full pipe, moderate settled debris, PVC conn. @ 187', clay conn. @ 129 7 06/01/15 331 330 352 8" 217'/345', major joint offset @ 282', minor roots in joint @ 342', US concrete masonry block MH 330 @ 352'

CIP Point Liner at 282'.

"E 13th St"; US, minor grease, low slow flow, evidence of over half full 129 7 06/01/15 330 328 244 8" pipe, PVC conn. @ 15', clay conn. @ 19', US concrete masonry block MH @ 244', US line in MH 328 has major debris blockage

No repairs needed. Keep line clear of debris.

"E 13th St"; DS, minor grease, low slow flow, evidence of 3/4 full pipe, 129 8 06/01/15 331 ??? 398 8" PVC conn. @ 44', clay conn. @ 116'/316', DS concrete masonry block MH 332 @ 398'

No repairs needed.

"E 13th St"; DS, minor grease, low slow flow, evidence of 3/4 full pipe, lense fowled from spider webs making viewing difficult, PVC conn. @ 129 8 06/01/15 ??? 332 396 8" 5'/165', unevaluated conn. @ 90', unevaluated pipe break @ 100'/104'/124'/135', moderate pipe break @ 213', DS concrete masonry block MH 332 @ 396'

Reinspect line to determine severity of pipe breaks and missed connection.

Page 50 of 56 From DVD Chpt Month Year To MH LF Comments MH

"E 13th St"; clay, DS, minor grease, low free moving flow, evidence of half full pipe, lense fowled from spider webs making viewing difficult, 129 9 06/01/15 322 333 8" clay conn. @ 43'/61', minor cracked pipe @ 71', moderate roots in joint @ 243', black material conn. w/moderate protruding tap @ 246', Inspection ends @ 246' due to tap protrusion

(↑estimat Cut tap and reinspect to complete evaluation. e)

"E 13th St"; clay, US, minor grease, low fast flow, evidence of nearly full pipe, clay conn. w/moderate infiltration @ 64', minor crack w/moderate 129 10 06/02/15 337 464 244 8" infiltration @ 76', joint w/moderate infiltration @ 91', clay conn. @ 140'/188', minor joint crack @ 189', joint w/major infiltration @ 194', US concrete masonry block MH 336 @ 244', major infiltration in MH 336

LCR Liner in connection at 64'. CIP Point Liner @ 76', 91', and 194'. Re-line manhole 245.

"E 13th St"; clay, US, minor grease, low fast flow, evidence of nearly full pipe, PVC conn. @ 43'/157', clay conn. @ 93'/185'/210', fowled lens 129 10 06/02/15 464 336 245 8" preventing proper inspection of possible infiltration in clay conn. @ 221', US concrete masonry block MH 335 @ 245'

Consider reinspecting with a clean camera lens.

"E 13th St"; clay, DS, minor grease, low fast flow, evidence of full pipe, clay conn. w/heavy infiltration @ 37', minor pipe crack @ 83', moderate 129 11 06/02/15 337 338 255 8" pipe break w/moderate to major infiltration @ 103', minor unevaluated pipe crack @ 192', DS concrete masonry block MH 338 @ 255'

LCR Liner connection at 37'. CIP Point Liner @ 103' and 192'.

"E 13th St"; clay, DS, minor grease, low fast flow, evidence of full pipe, 130 1 06/02/15 338 339 365 8" moderate pipe crack @ 145', clay conn. @ 203', minor roots in joint @ 214', DS drop-in concrete masonry block MH 339 @ 365'

Consider CIP Point Liner of joint at 145'.

"E 13th St"; clay, US, minor grease, thrid full pipe w/slow flow, evidence 130 2 06/03/15 339 325 8" of full pipe, sag @ 52'/115' submerges camera, heavy debris settling in sags, Inspection ends @ 124' due to debris blockage

(↑estimat Clean line and reinspect. e)

"13th St to Rocky Edmondson"; clay, DS, heavy grease, third full pipe w/fast flow, evidence of full pipe, minor pipe crack @ 23', frequent 130 3 06/03/15 339 340 8" grease hanging from top of pipe, camera submerged in deep flow @ 225', Inspection ends @ 286' due to zero visibility from submergence

(↑estimat Clean line an try to reinspect with lower flow level. e)

"Sapp St"; clay, DS, minor grease, low slow flow, evidence of full pipe, moderate debris settled in sags, clay conn. @ 23', clay conn. w/heavy 130 4 06/03/15 43 42 8" grease in lateral @ 52', unevaluated clay conn. @ 104', major roots in joint @ 180', Inspection ends @ 180' due to root blockage

(↑estimat Clean line and reinspect. e)

Page 51 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Sapp St"; clay, US, minor grease, low freely moving flow, evidence of full pipe, unevaluated conn. w/grease @ 42', clay conn. @ 43'/181', 130 5 06/03/15 42 44 294 8" PVC conn. @ 48'/266', PVC conn. w/heavy yellow grease in line @ 238', US precast MH 44 @ 294', Map does not match disc labelling

No repairs needed, just clean line of grease.

"Sapp St"; clay, US, minor grease, low freely moving flow, evidence of full pipe, unevaluated clay conn. @ 4', clay conn. w/heavy roots into 130 5 06/03/15 ??? ??? 8" main @ 99', severe roots from unknow source @ 118', Inspection ends @ 118' due to root blockage, Map does not match disc labelling

(↑estimat Clean line and reinspect to complete evaluation. Probable LCR e) Liner at 99' and 118'.

"Sapp St"; clay, DS, minor grease, low fast flow, evidence of full pipe, 130 6 06/03/15 41 44 153 8" PVC conn. @ 28', line suddenly sags @ 98' submerging camera, Inspection ends @ 100' due to submerged camera

Clean line and reinspect to insure backup is not caused by (↑estimat blockage. Significant line sag at 98'; line is not a major trunk line e) and cost benefit/analysis should be considered before replacing line. "Gravel & W 10th St";clay, US, low fast flow, evidence of half pipe, minmoderately full circumfrance cracked pipe from 11' to 14', clay conn @ 27', clay conn w/moderate roots in joint @ 62', moderate joint offset 130 7 06/04/15 51 ??? 200 8" @ 126', clay conn. w/moderate break in lateral @ 164', US concrete masonry block MH @ 200', Changed MH labelling to match online map

CIP Point Liner from 11' to 14'. LCR Liner at 62'.

"W 10th St to Townsend St"; clay, DS, minor grease, low freely moving 130 8 06/04/15 51 50 198 8" flow, evidence of over half full pipe, DS concrete masonry block MH 50 @ 198', Changed MH labelling to match online map

No repairs needed.

"Townsend St"; clay, US, minor grease, variable flow rate & depth, evidence of full pipe, some settled solids, iron pipe from 80' to 97', gap 130 9 06/04/15 49 50 118 8" in joint @ 97' not evaluated, moderate joint offset @ 103', line sag @ 104' submerges camera, US concrete masonry block MH 50 @ 118', Changed MH labelling to match online map

Consider reinspecting joints at 80' and 97'. No visible repairs needed.

"Townsend St"; clay, DS, minor grease, variable flow rate & depth, evidence of full pipe, clay conn. @ 20'/97, capped lateral @ 53', PVC 130 10 06/04/15 49 47 8" conn. @ moderate grease @ 54', heavy roots in joint @ 98'/113', Inspection ends @ 113' due to root blockage, Changed MH labelling to match online map

(↑estimat Clean line and reinspect to complete evaluation. e)

"Townsend St"; clay, DS, minor grease, variable flow rate & depth, evidence of full pipe, clay conn. @ 54'/119'/155', minor roots in joint @ 130 11 06/04/15 234 48 8" 80', clay conn. w/minor roots in lateral joint @ 112', PVC conn. @ 116', heavily broken pipe w/minor roots @ 117', Inspection ends @ 205' due to high flow depth

(↑estimat Clean line and try to reinspect with lower flow level. CIP Point e) Liner @ 117'.

Page 52 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Townsend St"; clay, US, minor grease, low fast flow, evidence of full 130 12 06/04/15 234 238 96 8" pipe, multiple minor offset joints, possible infiltration from joint @ 27', clay conn. @ 32', US brick MH 238 @ 96'

"Townsend St"; clay, US, minor grease, generally low free moving flow 130 12 06/04/15 238 239 8" w/minor debris causing small backups, evidence of full pipe, PVC conn. @ 56', Inspection ends @ 167' due to debris blockage

(↑estimat Inspection continues on Disc 130 Chapter 13. e)

"W 13th & Townsend St"; clay, DS, minor grease, generally low free moving flwo w/minor debris causing small backups, evidence of full 130 13 06/04/15 239 238 8" pipe, minor roots in joint @ 17', moderate roots in joint @ 23', PVC conn. w/protruding tap @ 81', Inspection ends @ 81' due to tap blockage

(↑estimat Cut tap and clean line to reinspect. e)

"13th & Townsend"; clay, US, minor grease, low fast flow, evidence of half full pipe, multiple minor offset joints, minor debris settling in line, 130 14 06/04/15 239 240 175 8" minor roots in joint @ 6', clay conn. @ 30'/120', PVC conn. @ 69'/84'/103', unevaluated heavily broken pipe @ 69', clay conn. w/minor lateral joint offset @ 106', US brick MH 240 @ 175'

CIP Point Liner at 69'.

"13th & Townsend"; clay, US, minor grease, low fast flow, evidence of half full pipe, multiple minor offset joints, PVC conn. @ 39'/40'/206', clay 130 14 06/04/15 240 241 8" conn. @ 70'/137', unevaluated clay conn. @ 128', protruding clay conn. @ 262', Inspection ends @ 262' due to tap blockage

(↑estimat Cut tap to complete inspection. e)

130 15 06/04/15 239 240 8" "Townsend"; clay, US, inspection of pipe break @ 72'

(↑estimat See Disc 130 Chapter 14 for recommendation. e)

"W 14th & Townsend St"; clay, DS, minor grease, variable flow rate & depth due to settled debris, evidence of half full pipe, PVC conn. @ 29', 130 16 06/04/15 241 240 8" clay conn. w/minor roots from lateral conn. @ 94', clay conn. w/protruding tap @ 99', Inspection ends @ 99' due to tap blockage

(↑estimat Cut tap to complete inspection. e)

"W 14th & Townsend"; clay, US, very little grease, low fast flow, evidence of half full pipe, minor roots in joint @ 56'/103', moderately broken pipe w/minor roots from 65' to 66', clay conn. @ 130 17 06/04/15 241 242 251 8" 66'/102'/208'/229', PVC conn. @ 131', PVC conn. @ 156', out of focus camera preventing inspection from 160' to 193', clay conn. @ 193', unevaluated PVC conn. @ 202', US brick MH 242 @ 251'

CIP Point Liner and LCR Liner at 66'.

Page 53 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Townsen St"; clay, DS, 3' pipe sections, minor grease, low fast flow, evidence of half full pipe, PVC pipe section w/minor offset from 25' to 28', PVC conn. @ 27'/165', clay conn. @ 74'/117', minor roots in joint @ 131 1 06/08/15 244 243 8" 84'/147', PVC conn. w/minor root in lateral joint @ 92', clay conn. w/minor roots in joint @ 124', PVC conn. w/protruding tap @ 170', Inspection ends @ 170' due to tap blockage

Cut tap to complete inspection.

"W 15th & Townsend";clay, US, 3' pipe sections, minor grease, low fast flow, evidence of full pipe, multiple minor offset joints, clay conn. 131 2 06/08/15 243 244 8" w/minor roots in lateral joint @ 98', clay conn. causing heavy debris in line @ 112', unevaluated conn. or line break @ 126', unevaluated conn. @ 145'/148'

Confirm protruding tap is the same tap as seen on Disc 131 Chapter 1.

"15th & Townsend St"; clay, DS, 3' pipe sections, minor grease, low fast flow, evidence of over half full pipse, clay conn. @ 62'/77'/138'/168', 131 3 06/08/15 243 242 178 8" PVC conn. @ 71'/111', unevalutated conn. @ 122'/155', DS brick MH 242 @ 178'

Reinspect to complete evaluation.

"Main & 15th St"; clay, US, low fast flow, evidence of over half full pipe, minor roots in joint @ 8'/13'/24'/38'/48'/53'/58', clay conn. @ 11', 131 4 06/08/15 247 248 135 8" moderate roots in joint @ 78', heavy roots in joint @ 82', Inspection ends @ 82' due to root blockage (↑estimat Clean line to finish inspection. Joint pressure test and grout as e) needed. "15th & Main St"; clay, DS, quarter full pipe w/slow flow, evidence of full 131 5 & 6 06/08/15 247 347 76 8" pipe, heavy debris settling, DS precast concrete w/brick corbel MH 347 @ 76'

Clean line to keep free of debris.

"Y HWY & Main St"; clay, DS, no grease, low free moving flow, 131 7 06/08/15 247 ??? 8" evidence of half full pipe, moderate offset joint @ 38', heavy roots in joint @ 132', Inspection ends @ 132' due to root blockage

Clean line and reinspect to complete evaluation.

"W 15th & Gravel St"; clay, DS, 3' pipe sections, minor grease, low fast flow, evidence of nearly full pipe, heavy pipe offset @ 21', clay conn. @ 22'/71'/99'/131'/210'/216', minor roots in joint @ 24'/72'/75'/350', 131 8 06/08/15 254 255 248 8" moderate roots in joint @ 54', clay conn. w/minor lateral joint offset & roots & mesh bag in lateral @ 73', clay conn. w/minor lateral joint offset @ 239', clay conn. w/minor roots in lateral joint @ 336'/337', DS brick MH 255 @ 428'

Determine usage of lateral connection at 73', open cut repair @ 21', and clean line regularly to monitor root growth.

"W 14th & High St'; clay, US, minor grease, almost no flow, evidence of half full pipe, multiple minor offset joints, moderate pipe offset @ 8', 131 9 06/08/15 256 310 247 8" conn. w/heavy grease in lateral @ 83', minor pipe crack @ 97', clay conn. @ 166', PVC conn. @ 195', US concrete w/brick corbel MH 310 @ 247'

Try to determine source of heavy grease in lateral at 83'. No repair required.

Page 54 of 56 From DVD Chpt Month Year To MH LF Comments MH

"High & W 14th St"; clay, US, minor grease, 3' pipe sections, variable flow depth & rate, evidence of full pipe, moderate debris settling, 131 10 06/09/15 256 257 23 8" multiple minor joint offsets, clay conn. w/heavy debris settling in lateral @ 20', US brick MH 257 @ 23' Try to determine source of heavy debris in lateral at 20'. No repair required.

"High & W 14th St"; clay, US, minor grease, low flow depth & rate, evidence of quarter full pipe, multiple minor offset joints, clay conn. 131 10 06/09/15 257 ??? 146 8" w/heavly broken main pipe @ 83', moderate pipe offset @ 96', PVC conn. w/minor main pipe crack @ 158', US clay Lamphole @ 146'

Locate upstream lamphole. CIP Point Liner and LCR Liner at 83'.

"14th & High St"; clay, DS, minor grease, 3' pipe sections, low flow depth & rate, evidence of nearly full pipe, multiple minor line sags, 131 11 06/09/15 256 255 318 8" unevaluated conn. @ 6'/169'/286', clay conn. @ 27'/97'/176'/186'/246'/311', PVC conn. @ 106'/212', DS brick MH 255 @ 318'

Reinspect to complete evaluation.

"14th & High St"; clay, DS, minor grease, 3' pipe sections, low flow 131 11 06/09/15 255 241 239 8" depth & rate, evidence of nearly full pipe, clay conn. @ 84'/159', unevaluated conn. @ 107', drop in to MH 255 @ 239'

Reinspect to complete evaluation.

"Behind houses on Kathy Dr"; clay, US, minor grease, low fast flow, evidence of half full pipe, minor debris settling, multiple minor sags, clay 131 12 06/09/15 404 359 276 8" conn. @ 65'/175', minor roots in joint @ 136', PVC conn. @ 161', US concrete block MH 359 @ 276' No repairs needed, clean to remove roots and regularly check to monitor root growth.

"Behind Kathy Dr"; clay, DS, minor grease, low fast flow, evidence of over half full pipe, clay conn. @ 46', unevaluated conn. w/heavy roots 131 13 06/09/15 404 405 8" into main @ 76', minor roots in joint @ 77', heavy roots from unknown source @ 102', Inspection ends @ 102' due to root blockage

Clean line and reinspect. Probable LCR Liner needed at 76' and CIP Point Liner needed at 102'.

"Behind Kathy Dr"; clay, US, minor grease, low fast flow, evidence of over half full pipe, minor broken capped lateral @ 19', PVC conn. 131 14 06/09/15 405 404 8" w/minor cracked main @ 23', clay conn. @ 90', unevaluated conn. w/heavy roots into main @ 116', clay conn. w/heavy roots @ 188', Inspection ends @ 188' due to root blockage

Clean line and reinspect. LCR Liner needed at 116' and 188'.

"Behind Kathy Dr"; clay, DS, minor grease, low fast flow, evidence of over half full pipe, clay conn. @ 40', PVC conn. w/minor cracked main & minor roots @ 60'/62', moderate main break from 60' to 62', conn. 131 15 06/09/15 405 495 343 8" w/moderate grease in lateral @ 170', minor roots in joint @ 214', unevaluated minor to moderately cracked pipe from 244' to 246', DS concrete brick drop-in MH 495 @ 343'

Reinspect to complete evaluation. CIP Point Liner from 60' to 62'. LCR Liner at 60' and 62'. Possible CIP Point Liner from 244' to 246'.

Page 55 of 56 From DVD Chpt Month Year To MH LF Comments MH

"Kathy Dr"; clay, DS, minor grease, very low flow, evidence of half full pipe, minor roots in joint @ 12'/22'/27'/37'/42'/82'/87', possibly capped 131 16 06/09/15 400 401 185 8" conn. w/heavy roots & possible crack in main @ 51', PVC conn. @ 66', moderate roots in joint @ 67', PVC conn. w/minor roots in lateral joint @ 133', DS precast concrete w/brick corbel MH 401 @ 185'

Pressure test and grout joints as needed. Pressure test and grout lateral connection at 133'. "Kathy Dr"; clay, DS, minor grease, very low flow, evidence of half full 131 16 06/09/15 401 402 144 8" pipe, PVC conn. @ 95', minor roots in joint @ 144', DS precast concrete w/brick corbel MH 402 @ 144' No repairs needed, clean to remove roots and regularly check to monitor root growth.

"Kathy Dr"; clay, DS, minor grease, very low flow, evidence of over half 131 17 06/09/15 402 403 235 8" full pipe, PVC conn. @ 92', DS precast concrete MH 403 @ 235'

No repairs needed.

"Bottom side of Kathy Dr"; clay, US, minor grease, low fast flow, evidence of full pipe, PVC conn. @ 186', moderate roots or grease 131 18 06/10/15 406 495 8" deposits @ 340', heavy roots in joint @ 370', Inspection ends @ 370' due to root blockage

Clean line to complete evaluation. CIP Point Liner at 370'.

"Hwy 112 & Hwy 248"; clay, DS, no grease, variable flow rate & depth, 132 1 07/02/15 191 242 8" evidence of full pipe, minor active infiltration from joint @ 12', minor joint crack @ 31'/133', DS brick MH 191 @ 242'

CIP point liner at 12'.

"Along Old Exeter Rd"; PVC, US, minor grease, low fast flow, evidence 132 2 07/02/15 431 433 329 8" of half full pipe, US precast concrete MH 433 @ 329'

No repairs needed.

Page 56 of 56