Procurement Plan

I. General

1. Bank’s approval Date of the procurement Plan [Original: November 2015]: Revision Public Disclosure Authorized 1 of Updated Procurement Plan, August 2016] 2. Date of General Procurement Notice: January, 2016 3. Period covered by this procurement plan: The procurement period of project covered from December 2017 to December 2019

II. Goods and Works and non-consulting services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:

Type of procurement Substantial risk Works (including turnkey, supply & installation of plant and Public Disclosure Authorized 10.000.000USD equipment, and PPP) Goods, information technology and non-consulting services 2.000.000USD

2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines Not applicable

4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P147674 issued by PRAPS-BF Public Disclosure Authorized 5. Any Other Special Procurement Arrangements: Not applicable

6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7

Ref. Description Estimated Packages Domesti Review Comments No. Cost c by Bank US$ Preferen (Prior / million ce Post) (yes/no) Summary of the NCB 7.6 7 No Post Public Disclosure Authorized (Works) Summary of the NCB 1.6 6 No Post (Goods) Summary of the RfQ 0.2 2 No Post (Works)

January 10, 2018 Summary of the RfQ 0.5 9 No Post (Goods)

III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants:

Type of procurement Substantial risk Consultants: firms 1.000.000USD Consultants: individuals 300.000USD

2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_200,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable

4. Consultancy Assignments with Selection Methods and Time Schedule

1 2 3 4 5 6

Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.8 8 post number of contracts that will be let under QCBS, FBBS, LCBS Summary of 3 39 Post CQS, number of Individual contracts that consultant will be let under other methods

January 10, 2018 PROCUREMENT Western Africa : Regional Sahel Pastoralism Support Project PLAN General Information Country: Western Africa Banks Approval Date of the Original Procurement Plan: 2018-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-05-14 Project ID: P147674 GPN Date: Project Name: Regional Sahel Pastoralism Support Project Loan / Credit No: IDA / 56510, IDA / 56520, IDA / D0650, IDA / D0640, IDA / 56490, IDA / 56500, IDA / D0660 Executing Agency(ies):Regional Sahel Pastoralism Support Project - , Regional Sahel Pastoralism Support Project - Chad, Regional Sahel Pastoralism Support Project - Senegal, Inter-State Committee against Drought in the Sahel, Regional Sahel Pastoralism Support Project - Burkina Faso, Regional Sahel Pastoralism Support Project - Mali, Regional Sahel Pastoralism Support Project - Mauritania

WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

NE-PRAPS-NE-7788-CW-RFB / Travaux de constructions Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 bureaux DGSV & rehabilitation Envelope Implementation batiment UCP

NE-PRAPS-NE-7808-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-03-25 2017-05-20 2017-07-19 Institutional Support Quotations Envelope Implementation Dosso

NE-PRAPS-NE-7962-CW-RFQ / Project Management and Request for Single Stage - One Pending Rehabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-15 2017-06-10 2017-08-09 Institutional Support Quotations Envelope Implementation Tillaberi

NE-PRAPS-NE-7963-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-15 2017-06-10 2017-08-09 Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7964-CW-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-04-22 2017-06-17 2017-08-16 Réhabilitation bureau d'Agadez Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7966-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-22 2017-06-17 2017-08-16 Institutional Support Quotations Envelope Implementation Maradi

NE-PRAPS-NE-7968-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-17 2017-06-12 2017-08-11 Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7969-CW-RFQ / Project Management and Request for Single Stage - One Pending Réhabilitation bureau antenne IDA / 56510 Post Limited 0.00 2017-04-25 2017-06-20 2017-08-19 Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7970-CW-RFQ / Request for Single Stage - One Pending Construction de 15 postes IDA / 56510 Animal Health Improvement Post Open - National 0.00 2017-05-27 2017-07-22 2018-01-18 Quotations Envelope Implementation départementaux vétérinaires

PRAPS-SN-05-TX / Recrutement d'une entreprise pour la construction et la réhabilitation Natural Resource Management Single Stage - Two Under des forages pastoraux équipés IDA / 56520 Post Request for Bids Open - National 0.00 2017-10-02 2017-10-10 2017-10-07 2017-11-18 2017-11-23 2017-12-18 2018-03-08 2018-01-22 2018-07-21 Enhancement Envelope Implementation de château d'eau, d'abreuvoirs et de moyens d'exhaure en zone 2 (KF et TC)

TD-PRAPS-TD-9637-CW-RFB / Construction de 4 marchés à Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-07-17 2017-07-22 2017-09-02 2017-10-02 2017-11-06 2018-05-05 bétail et de 2 postes de sortie Envelope Implementation frontaliers

TD-PRAPS-TD-9638-CW-RFB / Natural Resource Management Single Stage - One Pending IDA / D0650 Post Request for Bids Open - National 0.00 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 Aménagement de 20 mares Enhancement Envelope Implementation

TD-PRAPS-TD-9641-CW-RFB / Natural Resource Management Single Stage - One Pending Aménagement de 150 kilomètres IDA / D0650 Post Request for Bids Open - National 0.00 2017-07-20 2017-07-25 2017-09-05 2017-10-05 2017-11-09 2018-05-08 Enhancement Envelope Implementation de tronçons balisés

TD-PRAPS-TD-9644-CW-RFQ / Request for Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Limited 0.00 2017-10-07 2017-12-02 2018-05-31 Forage des postes de sortie Quotations Envelope Implementation

TD-PRAPS-TD-9645-CW-RFB / Single Stage - One Pending Construction et réhabilitation des IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-05-31 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2018-03-19 Envelope Implementation postes de vaccination

TD-PRAPS-TD-9648-CW-RFB / Single Stage - One Pending Construction réhabilitation et IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-05-15 2017-05-20 2017-07-01 2017-07-31 2017-09-04 2018-03-03 Envelope Implementation équipement de 12 forages

01-T/PRAPS / réhabiliter clôture Project Management and Request for Single Stage - One IDA / 56490 Post Limited 18,108.92 Signed 2017-05-03 2017-06-05 2017-06-21 2017-08-16 2017-08-20 antenne de Fada Institutional Support Quotations Envelope

REF 8 / Construction dans la Request for Single Stage - One Pending zone agro-écologique du Mali IDA / 56500 Market Access Facilitation Post Open - National 0.00 2017-06-06 2017-08-01 2018-01-28 Quotations Envelope Implementation Nord Est

NE-PRAPS-NE-23108-CW-RFB Project Management and Single Stage - One Pending IDA / 56510 Post Request for Bids Open - National 0.00 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-14 / Construction des locaux Institutional Support Envelope Implementation

119 / Construction de 15 postes Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 départementaux vétérinaires Envelope Implementation

120 / Contruction de 10 postes Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Limited 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 communaux frontaliers Envelope Implementation

122 / Fonçage de 4puits Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pastoaraux (PAAPSSP) Enhancement Quotations Envelope Implementation

123 / Réhabilitation de 3 puits Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Dosso (PAAPSSP) Enhancement Quotations Envelope Implementation

124 / Rehabilitation batiment Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 DGPIA Enhancement Quotations Envelope Implementation

125 / Constructiondes 2 centres Request for Single Stage - One Pending IDA / 56510 Market Access Facilitation Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 de collecte de lait Quotations Envelope Implementation

126 / Construction/réhabilitation Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-13 2018-02-18 2018-04-01 2018-05-01 2018-06-05 2018-12-02 des marchés à bétail Envelope Implementation

127 / Réalisation d'une station de pompage dans la commune Natural Resource Management Single Stage - One Pending de N'Guimi dans la région de IDA / 56510 Post Request for Bids Open - National 0.00 2017-09-29 2017-10-04 2017-11-15 2017-12-15 2018-01-19 2018-07-18 Enhancement Envelope Implementation Diffa dans le cadre de programme d'urgrncr Diffa 2017

128 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tchinta

129 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

130 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bermo

131 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

132 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Ollélewa

133 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Tenhiya

134 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

135 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

136 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bandé

Page 1 137 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Bouné

138 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Alakos

139 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

140 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gouré

141 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

142 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kéllé

143 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Takaya

144 / Réhabilitation des puits Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Quotations Envelope Implementation Gudimouni

145 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Moa

146 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Kanya Wamé

147 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation deTesker

148 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gueskérou

149 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Chétimari

150 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Guigmi

151 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

152 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

153 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Guel Beyli

154 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation N'Gourti

155 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Djeladjo

156 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Fillingué

157 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation deTchintaborak

158 / Réhabilitation des puits Natural Resource Management Request for Single Stage - One Pending pastoraux dans la commune de IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Ingall

159 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Ingall

160 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Bermo

161 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Tchinta

162 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune de Abala

163 / Réhabilitation des stations Natural Resource Management Request for Single Stage - One Pending de pompage/forages pastoraux IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation dans la commune deTenhiya

164 / Réhabilitation des stations de pompage/forages pastoraux Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 dans la commune deTesker (site Enhancement Quotations Envelope Implementation de et Aborak)

REF 1 / Réhabilitation de 19 Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2017-11-22 2017-11-27 2018-01-08 2018-02-07 2018-03-14 2018-09-10 batiments Enhancement Envelope Implementation

ML-PRAPS-ML-33832-CW-RFQ / Travaux d'aménagement et de gestion des pistes et des gîtes Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-10-30 2017-12-25 2018-06-23 d'étapes dans les cercles de Enhancement Quotations Envelope Implementation

Koutiala et Yorosso (région de Sikasso)

ML-PRAPS-ML-33835-CW-RFQ Natural Resource Management Request for Single Stage - One Pending / Travaux d'aménagement de 3 IDA / 56500 Post Limited 0.00 2017-11-14 2018-01-09 2018-07-08 Enhancement Quotations Envelope Implementation périmètres pastoraux

ML-PRAPS-ML-34689-CW-RFB Single Stage - One Pending / Réhabilitation dans la zone IDA / 56500 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-03-31 2018-04-05 2018-05-17 2018-06-16 2018-07-21 2019-01-17 Envelope Implementation Delta central

ML-PRAPS-ML-34760-CW-RFQ / Construction dans la zone agro- Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2017-11-13 2018-01-08 2018-07-07 écologique du Delta central de 7 Quotations Envelope Implementation magasins

MR-PRAPS-MR -35029-CW- RFB / construction en 2 lots de 7 Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-12-28 2018-01-02 2018-02-13 2018-03-15 2018-04-19 2018-10-16 marchés a bétail dans plusieurs Envelope Implementation wilayas

MR-PRAPS-MR -35030-CW- RFQ / réalisation d un puit Natural Resource Management Request for Single Stage - One Pending pastoral dans la localité de IDA / D0660 Post Open - National 0.00 2018-01-01 2018-02-26 2018-08-25 Enhancement Quotations Envelope Implementation teguelwezza commune de Kankossa

02-T/MOD1 / Réalisation de 111 forages pastoraux solaires et Natural Resource Management Single Stage - One Under IDA / 56490 Post Request for Bids Open - National 0.00 2017-12-04 2017-10-31 2017-12-18 2018-01-17 2017-12-15 2018-02-16 2018-04-01 2018-07-30 manuels dans les 6 régions du Enhancement Envelope Implementation

PRAPS

05-T/MOD1 / Réalisation de 30 Natural Resource Management Single Stage - One Pending boulis et surcreusement de 5 IDA / 56490 Post Request for Bids Open - National 0.00 2018-09-28 2018-10-12 2018-11-11 2018-12-11 2019-01-24 2019-07-23 Enhancement Envelope Implementation mares

07-T/MOD1 / Construction de 9 Request for Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Limited 0.00 2019-02-10 2019-04-16 2019-08-14 cabinets vétérinaires Quotations Envelope Implementation

Page 2 09-T/MOD1 / Travaux de construction de 6 postes Single Stage - One Pending vétérinaires et 30 parcs de IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-12-04 2017-12-18 2018-01-17 2018-02-16 2018-04-01 2018-07-30 Envelope Implementation vaccination dans les 6 régions du PRAPS-BF

06-T/MOD1 / Single Stage - One Pending construction/réhabilitation et IDA / 56490 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-10-31 2018-11-14 2018-12-14 2019-01-13 2019-02-26 2019-07-26 Envelope Implementation équipement d'UTL et CCL

PRAPS-SN-01-TX / Réalisation Single Stage - Two des travaux de construction de IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 Canceled 2018-03-02 2018-03-07 2018-04-18 2018-05-03 2018-06-17 2018-09-15 Envelope 15 parcs a vaccination

PRAPS-SN-02-TX-2018 / Réalisation des travaux de Request for Single Stage - One Pending IDA / 56520 Animal Health Improvement Post Limited 0.00 2018-05-02 2018-06-27 2018-12-24 construction d'incinérateurs au Quotations Envelope Implementation niveau des 8 SDEL

PRAPS-SN-03-TX-2018 / Réalisation des travaux de confection et de pose de bornes Natural Resource Management Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2018-05-16 2018-07-11 2019-01-07 pour la matérialisation des Enhancement Quotations Envelope Implementation couloirs de transhumance Payar - Kahène

PRAPS-SN-04-TX-2018 / Réalisation des travaux de construction et la réhabilitation Natural Resource Management Single Stage - Two des forages pastoraux équipés IDA / 56520 Post Request for Bids Open - National 0.00 Canceled 2018-01-17 2018-01-22 2018-03-05 2018-04-04 2018-05-09 2019-01-04 Enhancement Envelope de château d'eau, d'abreuvoirs et de moyens d'exhaure en zone 1 (SL, MT, LG)

PRAPS-SN-05-TX-2018 / Réalisation des travaux Natural Resource Management Single Stage - Two Pending IDA / 56520 Post Request for Bids Open - National 0.00 2018-05-25 2018-05-30 2018-07-11 2018-08-10 2018-09-14 2019-01-12 d'aménagement de mares Enhancement Envelope Implementation pastorales

PRAPS-SN-06-TX-2018 / Réalisation des travaux de Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-05-11 2018-05-16 2018-06-27 2018-07-27 2018-08-31 2018-12-29 réhabilitation de 85 km de pistes Envelope Implementation rurales

PRAPS-SN-08-TX-2018 / Single Stage - Two Réalisation des travaux de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 Canceled 2018-01-26 2018-01-31 2018-03-14 2018-04-13 2018-05-18 2018-11-14 Envelope construction des unités laitières

T01 MR PRAPS / Construction Single Stage - One Pending et réhabilitation des locaux de la IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-03-30 2017-04-09 2017-05-11 2017-06-10 2018-01-30 2018-08-28 Envelope Implementation DSV

PRAPS-SN-09-TX-2018 / Project Management and Request for Single Stage - One Under Travaux de réaménagement des IDA / 56520 Post Limited 0.00 2018-01-22 2018-03-19 2018-04-03 Institutional Support Quotations Envelope Implementation bureaux du PRAPS

MR-PRAPS-MR -45323-CW- RFB / Construction de 73 parcs Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-04-25 2018-04-30 2018-06-11 2018-07-11 2018-08-15 2018-11-13 de vaccination dans plusieurs Envelope Implementation wilayas

MR-PRAPS-MR -45327-CW- RFB / Construction en 2 lots de Single Stage - One Pending IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-05-25 2018-05-30 2018-07-11 2018-09-14 2019-03-13 10 aires d abattage améliorées Envelope Implementation dans plusieurs wilayas

BF-PRAPS-BF-45749-CW-RFB Project Management and Single Stage - One Pending / Construction du siège du IDA / 56490 Post Request for Bids Open - National 0.00 2017-06-19 2017-06-24 2017-07-24 2017-08-23 2017-09-27 2018-09-22 Institutional Support Envelope Implementation PRAPS-BF

ML-PRAPS-ML-46040-CW-RFQ / Réalisation des travaux Natural Resource Management Request for Single Stage - One Pending d'aménagement de 02 mares IDA / 56500 Post Limited 0.00 2018-03-17 2018-05-12 2018-11-08 Enhancement Quotations Envelope Implementation dans la zone d'intervention du Projet

ML-PRAPS-ML-46041-CW-RFQ / Travaux de réhabilitation des Natural Resource Management Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-03-10 2018-05-05 2018-11-01 infrastructures hydrauliques Enhancement Quotations Envelope Implementation d'accès à l'eau

ML-PRAPS-ML-46042-CW-RFB / Réhabilitation de 03 marchés à bétail, construction et équipement de 02 marchés à bétail, construction de 05 aires Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-05-07 2018-05-12 2018-06-23 2018-07-23 2018-08-27 2019-02-23 d'abattage, 03 étals de Enhancement Envelope Implementation boucherie, 10 magasins d'aliment bétail et 05 pistes d'accès aux marchés à bétail dans le Mali Nord Est

PRAPS-SN-02-TX / Recrutement d'une entreprise pour les travaux Natural Resource Management Request for Single Stage - One de construction de clôtures de IDA / 56520 Post Limited 0.00 Canceled 2018-02-12 2018-04-09 2018-05-24 Enhancement Quotations Envelope pépinières communautaires (10 pépinières de 1/4 ha)

PRAPS-SN-12-TX-2018 / Recrutement d'une entreprise pour la réalisation de clôture de Natural Resource Management Single Stage - One IDA / 56520 Post Request for Bids Open - National 0.00 Canceled 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-12-01 mise en défens sur 200 ha (Dept Enhancement Envelope

Linguère, Kanel, Bakel, Koumpentoum et Koungheul)

PRAPS-SN-11-TX-2018 / Recrutement d'une entreprise pour la réalisation des travaux de Single Stage - Two construction de Magasins de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 Canceled 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2018-10-02 Envelope Stockage et de Vente d'Aliment de Bétail (4 de 100T et 5 de 50 tonnes)

ML-PRAPS-ML-48029-CW-RFB Natural Resource Management Single Stage - One Pending / Equipements et infrastructures IDA / 56500 Post Request for Bids Open - National 0.00 2018-02-15 2018-02-20 2018-04-03 2018-06-07 2018-12-04 Enhancement Envelope Implementation d'abreuvement de forages

ML-PRAPS-ML-48031-CW-RFB Natural Resource Management Single Stage - One Pending / Travaux de 11 forages grand IDA / 56500 Post Request for Bids Open - National 0.00 2018-06-12 2018-06-17 2018-07-29 2018-10-02 2019-03-31 Enhancement Envelope Implementation débit et 14 forages simples

ML-PRAPS-ML-47899-CW-RFB / Travaux de réhabilitation de 5 Single Stage - One Pending secteurs vétérinaires, 5 SLPIA, 6 IDA / 56500 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-19 2018-02-24 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Envelope Implementation Postes frontaliers, 1 Poste de contrôle frontalier et 15 UAPIA

ML-PRAPS-ML-47901-CW-RFB Single Stage - One Pending / Travaux de construction de 31 IDA / 56500 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-03-08 2018-03-13 2018-04-24 2018-05-24 2018-06-28 2018-12-25 Envelope Implementation Parcs de vaccination

ML-PRAPS-ML-47903-CW-RFB / Réalisation du balisage de 245 km de pistes et gîtes d'étapes dans les cercles de Bankass et Natural Resource Management Single Stage - One Pending Koro (région de Mopti) et de 545 IDA / 56500 Post Request for Bids Open - National 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Enhancement Envelope Implementation km de pistes et gîtes d'étapes dans les cercles de Ténenkou et Niono (régions de Mopti et de Ségou)

ML-PRAPS-ML-47905-CW-RFB / Réalisation de 14 Systèmes Hydrauliques Pastorales (SHPA) Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-04-12 2018-04-17 2018-05-29 2018-06-28 2018-08-02 2019-01-29 dans les régions de Ségou, Enhancement Envelope Implementation

Mopti, Tombouctou, Gao et Ménaka

ML-PRAPS-ML-47907-CW-RFB / Réalisation des travaux de 11 mini Systèmes Hydraulique Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-04-17 2018-04-22 2018-06-03 2018-07-03 2018-08-07 2019-02-03 Pastorales (SHPA) dans les Enhancement Envelope Implementation gites d'étapes des régions de Sikasso, Ségou, Mopti

ML-PRAPS-ML-48014-CW-RFB / Réalisation des travaux de 23 forages dont les sites seront Natural Resource Management Single Stage - One Pending IDA / 56500 Post Request for Bids Open - National 0.00 2018-02-07 2018-02-12 2018-03-26 2018-04-25 2018-05-30 2018-11-26 déterminés à l'issu de la Enhancement Envelope Implementation validation des résultats de l'inventaire des points d'eau

ML-PRAPS-ML-48011-CW-RFQ / Réhabilitation de trois bureaux Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-02-28 2018-04-25 2018-10-22 pour les antennes régionales à Institutional Support Quotations Envelope Implementation

(Kayes, Mopti, Gao)

Page 3 BF-PRAPS-BF-49891-CW-RFB / Réhabilitation 10 postes vétérinaires et 04 marchés à Animal Health Improvement Single Stage - One Pending IDA / 56490 Post Request for Bids Open - National 0.00 2018-05-15 2018-05-29 2018-06-28 2018-07-19 2018-08-23 2018-12-21 bétail dans les régions de Market Access Facilitation Envelope Implementation l'antenne de Bobo-Dioulasso et de Fada N'Gourma

04-T/MOD1 / Construction 10 marchés à bétail et Single Stage - One Pending IDA / 56490 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-07-02 2018-07-16 2018-08-15 2018-09-14 2018-10-28 2019-03-27 construction/réhabilitation 10 Envelope Implementation aires d'abattage.

08-T/MOD2 / Sécurisation d'aires de pâture intervilageoise, Natural Resource Management Single Stage - One Pending de délimitation/balisage d'aires IDA / 56490 Post Request for Bids Open - National 0.00 2018-10-31 2018-11-14 2018-12-14 2019-01-13 2019-02-26 2019-07-26 Enhancement Envelope Implementation de repôs, d'aménagement de pistes à bétail

PRAPS-SN-10-TX-2018 / Recrutement d'une entreprise Single Stage - Two Pending pour la construction et ou la IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-12 2018-02-17 2018-03-31 2018-04-30 2018-06-04 2019-01-30 Envelope Implementation réhabilitation de mise aux normes d'aires d'abattage

PRAPS-SN-07-TX-2018 / Réalisation des travaux de Single Stage - Two Under IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-22 2018-02-20 2018-02-22 2018-03-28 2018-04-27 2018-06-01 2018-09-29 construction de huit (08) Envelope Implementation marchés à bétail

PRAPS-SN-04-TX-2018-BIS / Realisation des travaux de construction et la rehabilitation Natural Resource Management Single Stage - One Pending des forages pastoraux equipes IDA / 56520 Post Request for Bids Open - National 0.00 2018-01-04 2018-01-15 2018-04-11 2018-04-26 2018-06-16 2019-02-11 Enhancement Envelope Implementation de chateau d'eau, d'abreuvoirs et de moyens d'exhaure en zone 1 (SL, MT, LG)

03-T/MOD1 / Réhabilitation de 08 postes vétérinaires dans la région du Sahel (Arbinda, Banh, Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-05-01 2018-05-15 2018-06-14 2018-07-14 2018-08-27 2018-12-25 Baraboulé, Déou, Mansila, Envelope Implementation

Marcoye, Nansoumbou, Tankougoumadié)

BF-PRAPS-BF-51569-CW-RFB Single Stage - One Pending / Construction de 08 Postes IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-06-12 2018-06-19 2018-07-19 2018-08-02 2018-08-30 2018-12-28 Envelope Implementation vétérinaires

BF-PRAPS-BF-49952-CW-RFB / Récupération de 2 000 Ha de terre dégradée par ONG/Association spécialisées à Natural Resource Management Single Stage - One Pending travers la sensibilisation, la IDA / 56490 Post Request for Bids Open - National 0.00 2018-05-30 2018-06-13 2018-07-13 2018-08-03 2018-09-07 2019-01-05 Enhancement Envelope Implementation réalisation d'ouvrages antiérosifs par la charrue DELPHINO suivi de la végétalisation par des espèces appétées

BF-PRAPS-BF-49945-CW-RFB / Balisage aire de repos, aire de Natural Resource Management Single Stage - One Pending IDA / 56490 Post Request for Bids Open - National 0.00 2018-05-30 2018-06-13 2018-07-13 2018-08-03 2018-09-07 2019-01-05 pâture et piste à bétail dans les Enhancement Envelope Implementation régions du sahel et de l'Est

ML-PRAPS-ML-53183-CW-RFQ / Réhabilitation de trois (3) Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-04-10 2018-06-05 2018-12-02 bureaux pour les antennes Institutional Support Quotations Envelope Implementation régionales

PRAPS-MR-1T / Construction en 2 lots de 3 marchés à bétail Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-09-19 2017-09-24 2017-11-05 2017-12-05 2018-01-09 2018-07-08 et de 2 aires de repos dans Envelope Implementation plusieurs wilayas du pays

PRAPS-SN-08-TX-2018 BIS / Single Stage - One Under Realisation des travaux de IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-01-05 2018-02-02 2018-02-02 2018-03-14 2018-03-14 2018-04-13 2018-05-19 2018-11-15 Envelope Implementation construction des unites laitieres

PRAPS-SN-11-TX-2018 BIS / Realisation des travaux de cloture de mise en defens sur Natural Resource Management Single Stage - One Pending IDA / 56520 Post Request for Bids Open - National 0.00 2017-11-29 2017-12-18 2018-01-24 2018-02-14 2018-04-06 2018-10-03 200 ha (Departements Linguere, Enhancement Envelope Implementation

Kanel, Bakel, Koumpentoum et Koungheul)

PRAPS-SN-12-TX-2018-BIS / Realisation des travaux de construction de Magasins de Single Stage - One Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2017-12-04 2017-12-06 2018-01-10 2018-01-23 2018-03-20 2018-11-15 Stockage et de Vente d'Aliment Envelope Implementation de Betail (4 de 100T et 5 de 50 tonnes)

121 / Finalisation de 3 puits Natural Resource Management Request for Single Stage - One Pending pastoraux à Dosso IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation (PAAPSSP/CTB)

NE-PRAPS-NE-55019-CW-RFQ Natural Resource Management Request for Single Stage - One Pending / Réhabilitation de 5 points d'eau IDA / 56510 Post Limited 0.00 2018-05-06 2018-07-01 2018-12-28 Enhancement Quotations Envelope Implementation pastoraux

NE-PRAPS-NE-55023-CW-RFB Single Stage - One Pending / Construction de 4 centres de IDA / 56510 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-05-01 2018-05-06 2018-06-17 2018-07-17 2018-08-21 2019-02-17 Envelope Implementation collecte de lait

NE-PRAPS-NE-55031-CW-RFB Natural Resource Management Single Stage - One Pending / Construction de 8 nouveaux IDA / 56510 Post Request for Bids Open - National 0.00 2018-05-10 2018-05-15 2018-06-26 2018-07-26 2018-08-30 2019-02-26 Enhancement Envelope Implementation points d'eau pastoraux

TD-PRAPS-TD-9582-CW-RFB / Natural Resource Management Single Stage - One Pending Construction de 50 des puits IDA / D0650 Post Request for Bids Limited 0.00 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Enhancement Envelope Implementation pastoraux

ML-PRAPS-ML-57153-CW-RFB Single Stage - One Pending / Réhabilitation de 3 marchés à IDA / 56500 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-05-30 2018-06-04 2018-07-16 2018-09-04 2018-10-09 2019-04-07 Envelope Implementation bétail dans la zone Mali Nord Est

TD-PRAPS-TD-9573-CW-RFB / Single Stage - One Pending Construction de 100 parcs de IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-03-26 2018-03-31 2018-05-12 2018-07-16 2019-01-12 Envelope Implementation vaccination

TD-PRAPS-TD-9585-CW-RFB / Single Stage - One Pending Construction de 12 marchés à IDA / D0650 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-03-15 2018-03-20 2018-05-01 2018-05-31 2018-07-05 2019-01-01 Envelope Implementation bétail

TD-PRAPS-TD-9579-CW-RFQ / Natural Resource Management Request for Single Stage - One Pending Réhabilitation des tronçons de IDA / D0650 Post Limited 0.00 2017-03-15 2017-05-10 2017-11-06 Enhancement Quotations Envelope Implementation 200 km balises

TD-PRAPS-TD-57329-CW-RFB / Single Stage - One Pending Construction de 24 postes IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-04-30 2018-05-05 2018-06-16 2018-07-16 2018-08-20 2019-02-16 Envelope Implementation vétérinaires

TD-PRAPS-TD-57335-CW-RFB / Single Stage - One Pending Construction de 10 pharmacies IDA / D0650 Animal Health Improvement Post Request for Bids Limited 0.00 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Envelope Implementation vétérinaires

PRAPS T 01 / Réalisation en régie du programme d Natural Resource Management Pending hydraulique pastorale avec la IDA / D0660 Prior Direct Selection Direct 0.00 2018-04-23 2018-04-28 2018-06-02 2019-10-15 Enhancement Implementation société nationale des Forages et Puits - ('signature de protocole)

PRAPS-SN-07-TX-2018-BIS / Realisation des travaux de Single Stage - One Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-01-24 2018-02-20 2018-03-28 2018-04-27 2018-06-11 2018-12-08 construction de huit (08) Envelope Implementation marches a betail

T02 MR PRAPS 2017 / Construction et rehabilitation en Single Stage - One Pending 2 de 9 postes de santé et la IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-04-10 2017-04-14 2017-05-19 2017-06-18 2017-11-14 2018-11-30 Envelope Implementation rehabilitation de 10 autres dans 7 wilayas

GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

NE-PRAPS-NE-7631-GO-RFB / Project Management and Single Stage - One Pending IDA / 56510 Post Request for Bids Open - National 0.00 2017-02-23 2017-02-28 2017-04-11 2017-05-11 2017-06-15 2017-12-12 Acquisition matériel informatique Institutional Support Envelope Implementation

NE-PRAPS-NE-7652-GO-RFQ / Production de certificat Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-03-05 2017-04-30 2017-05-10 international de transhumance de Quotations Envelope Implementation la CEDEAO

Page 4 NE-PRAPS-NE-7653-GO-RFQ / Request for Single Stage - One Pending Fourniture et installation de IDA / 56510 Market Access Facilitation Post Limited 0.00 2017-03-10 2017-05-05 2017-07-04 Quotations Envelope Implementation Panneau Solaire pour la DGPIA

NE-PRAPS-NE-7654-GO-RFQ / Project Management and Request for Single Stage - One Pending Confection des Panneaux et IDA / 56510 Post Limited 0.00 2017-03-25 2017-05-20 2017-07-19 Institutional Support Quotations Envelope Implementation totems lumineux à

NE-PRAPS-NE-7655-GO-RFQ / Productions des outils de collecte de données sur les Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-03-10 2017-05-05 2017-06-04 statistiques d'élevage ( Institutional Support Quotations Envelope Implementation commercialisation de bétail etc ....)

NE-PRAPS-NE-7658-GO-RFQ / Realisation, conception d'un Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-04-08 2017-06-03 2017-07-03 compendium sur deux ans de Institutional Support Quotations Envelope Implementation mise en RN en Suvre du PRAPS

NE-PRAPS-NE-7659-GO-RFQ / impression d'un compendium sur Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-04-22 2017-06-17 2017-07-07 deux ans de mise en RN en Institutional Support Quotations Envelope Implementation

Suvre du PRAPS

NE-PRAPS-NE-7660-GO-RFQ / Edition et diffusion des outils et Project Management and Request for Single Stage - One Pending manuels de sensibilisation sur IDA / 56510 Post Limited 0.00 2017-05-02 2017-06-27 2017-07-27 Institutional Support Quotations Envelope Implementation les maladies prioritaires et les maladies emergentes du betail

NE-PRAPS-NE-7662-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Telephone et flotte PRAPS Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7663-GO-RFQ / Project Management and Request for Single Stage - One Pending Fonctionnement véhicules et IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2017-10-18 Institutional Support Quotations Envelope Implementation motos (carburant,entretien,...)

NE-PRAPS-NE-7664-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Fourniture et produit d'entretien Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7667-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Consommable bureau, journaux Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7670-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2017-06-20 Edition journal du PRAPS Institutional Support Quotations Envelope Implementation

TD-PRAPS-TD-8494-GO-RFB / Project Management and Single Stage - One Pending Acquisition d'un groupe IDA / D0650 Prior Request for Bids Limited 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2018-04-19 Institutional Support Envelope Implementation électrogène pour l'UCP

TD-PRAPS-TD-8497-GO-RFB / Single Stage - One Pending Acquisition de 4 000 000 de IDA / D0650 Animal Health Improvement Post Request for Bids Open - National 0.00 2017-07-01 2017-07-06 2017-08-17 2017-09-16 2017-10-21 2018-04-19 Envelope Implementation doses de vaccin PPR

PRAPS-SN-01-F / Acquisition Single Stage - Two IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 Canceled 2017-03-13 2017-03-18 2017-04-29 2017-05-14 2017-06-13 2017-07-13 de Vaccins PPCB, PPR et FVR Envelope

BF-CILSS-8938-GO-RFQ / Impression de divers documents Project Management and Request for Single Stage - One Pending (notes des ETP-2, fiches IDA / D0640 Post Limited 0.00 2017-06-20 2017-08-15 2017-09-14 Institutional Support Quotations Envelope Implementation techniques, notes de plaidoyer, guide routier, plaquettes)

PRAPS-SN-02-F / Acquisition de kit de diagnostic de Single Stage - Two IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 Canceled 2017-03-06 2017-03-11 2017-04-15 2017-05-15 2017-06-19 2017-08-03 laboratoire (PPR et FVR) et de Envelope matériel d'intervention

PRAPS-SN-03-F / Recrutement d'un prestataire pour la confection de supports Animal Health Improvement Request for Single Stage - One promotionnels (agendas, polos, IDA / 56520 Project Management and Post Limited 0.00 Canceled 2017-03-11 2017-04-28 2017-05-28 Quotations Envelope pagnes, etc.) et Support de Institutional Support Communication (JML, JNE, autre com)

PRAPS-SN-04-F / Acquisition Natural Resource Management Request for Single Stage - One de 8 motos pour l'animation des IDA / 56520 Post Limited 0.00 Canceled 2017-03-18 2017-05-07 2017-06-21 Enhancement Quotations Envelope UP

PRAPS-SN-05-F / Acquisition de matériel de lutte contre les Natural Resource Management Request for Single Stage - One feux de brousse en vue de IDA / 56520 Post Limited 0.00 Canceled 2017-07-29 2017-09-17 2017-11-01 Enhancement Quotations Envelope l'équipement de 30 comités de lutte contre les feux de brousse

PRAPS-SN-06-F / Acquisition Natural Resource Management Request for Single Stage - One IDA / 56520 Post Limited 0.00 Canceled 2017-06-17 2017-08-12 2017-11-10 de motofaucheuses Enhancement Quotations Envelope

PRAPS-SN-07-F / Acquisition de fournitures de bureau, de consommables informatiques et Project Management and Request for Single Stage - One IDA / 56520 Post Limited 0.00 Canceled 2017-03-11 2017-04-30 2018-04-30 de Produits d'entretien de locaux Institutional Support Quotations Envelope administratifs et de petits matériels et outillages

PRAPS-SN-09-F / Services de Project Management and Request for Single Stage - One confection d'habillement pour le IDA / 56520 Post Limited 0.00 Canceled 2017-03-25 2017-05-14 2017-06-14 Institutional Support Quotations Envelope personnel de service

PRAPS-SN-11-F / Acquisition Project Management and Request for Single Stage - One d'équipements de IDA / 56520 Post Limited 0.00 Canceled 2017-03-11 2017-04-30 2017-06-15 Institutional Support Quotations Envelope Communication

BF-CILSS-9090-GO-RFQ / Produire des éditions de fin Project Management and Request for Single Stage - One IDA / D0640 Post Limited 7,364.49 Signed 2017-12-01 2017-10-12 2017-12-30 2017-12-01 2018-01-13 d'année (calendriers, Institutional Support Quotations Envelope plannings...)

BF-CILSS-9091-GO-RFQ / Project Management and Request for Single Stage - One Acquisition de deux IDA / D0640 Post Limited 5,197.74 Signed 2018-03-05 2018-01-25 2018-04-09 2018-02-14 2018-04-19 Institutional Support Quotations Envelope rétroprojecteurs

BF-CILSS-9092-GO-DIR / Project Management and Request for Single Stage - One Pending Acquisition de matériel de bureau IDA / D0640 Post Limited 0.00 2018-03-09 2018-04-09 2018-04-19 Institutional Support Quotations Envelope Implementation complémentaire

BF-CILSS-9093-GO-RFQ / Project Management and Request for Single Stage - One Pending Acquisition de fournitures de IDA / D0640 Post Limited 0.00 2018-04-07 2018-05-12 2018-05-22 Institutional Support Quotations Envelope Implementation bureau

PRAPS-SN-12-F / Achat de Mobilier (archivage et salon pour Project Management and Request for Single Stage - One bureau coordonnateur et bureau IDA / 56520 Post Limited 0.00 Canceled 2017-04-08 2017-05-28 2017-06-27 Institutional Support Quotations Envelope assistant sauvegarde environnemental et social)

PRAPS-SN-13-F / Acquisition Project Management and Request for Single Stage - One de Groupes Electrogènes UCP et IDA / 56520 Post Limited 0.00 Canceled 2017-03-18 2017-05-07 2017-08-05 Institutional Support Quotations Envelope antennes

PRAPS-SN-14-F / Acquisition Single Stage - One de céréales en cas de crise IDA / 56520 Pastoral Crisis Management Prior Request for Bids Open - National 0.00 Canceled 2017-11-06 2017-11-11 2017-12-23 2018-01-22 2018-02-26 2018-03-28 Envelope pastorale

TD-PRAPS-TD-9182-GO-RFQ / Equipement de la salle des Project Management and Request for Single Stage - One Pending réunions du Ministère de IDA / D0650 Post Limited 0.00 2017-04-19 2017-06-14 2017-12-11 Institutional Support Quotations Envelope Implementation l'Elevage et des Productions Animales

TD-PRAPS-TD-9999-GO-RFB / Project Management and Single Stage - One Pending Acquistion de 17 véhicules Tout IDA / D0650 Prior Request for Bids Open - International 0.00 2016-07-04 2016-07-09 2016-08-20 2016-09-19 2016-10-24 2017-04-22 Institutional Support Envelope Implementation Terrain et de 176 motocyclettes

TD-PRAPS-TD-9998-GO-RFB / Project Management and Single Stage - One Pending Acqusitions des matériels IDA / D0650 Post Request for Bids Open - National 0.00 2016-07-21 2016-07-26 2016-09-06 2016-10-06 2016-11-10 2017-05-09 Institutional Support Envelope Implementation informatiques

TD-PRAPS-TD-9990-GO-RFB / Single Stage - One Pending Acquistion de 3 000 000 de IDA / D0650 Animal Health Improvement Post Request for Bids Limited 0.00 2016-07-21 2016-07-26 2016-09-06 2016-10-06 2016-11-10 2017-05-09 Envelope Implementation doses de vaccins PPCB

03-F/PRAPS / Acquérir 3 Single Stage - One groupes électrogènes au profit IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 54,364.57 Signed 2017-04-03 2017-04-11 2017-04-08 2017-05-08 2017-05-24 2017-05-29 2017-05-24 2017-07-03 2017-10-13 2017-09-01 Envelope des antennes du PRAPS-BF

02-F/PRAPS / Duplication en Project Management and Request for Single Stage - One 1000 exemplaires la version IDA / 56490 Post Limited 2,739.84 Signed 2018-01-31 2018-01-25 2018-03-28 2018-02-28 2018-04-27 Institutional Support Quotations Envelope adaptée du guide genre

Page 5 Natural Resource Management 14-F/PRAPS / Fournitures et Enhancement Request for Single Stage - One Under consommables de bureau et IDA / 56490 Post Limited 0.00 2018-01-20 2017-12-29 2018-02-24 2018-03-26 Project Management and Quotations Envelope Implementation informatiques Institutional Support

15-F/PRAPS / Mobilier de Project Management and Request for Single Stage - One Pending IDA / 56490 Post Limited 0.00 2018-10-22 2018-12-10 2019-02-08 bureau Institutional Support Quotations Envelope Implementation

13-F/PRAPS / Dispositif de Project Management and Request for Single Stage - One Under vidéoconférence au profit de IDA / 56490 Post Limited 0.00 2018-05-30 2017-12-18 2018-07-18 2018-09-16 Institutional Support Quotations Envelope Implementation l'UCP

12-F/PRAPS / 200 kits outils Request for Single Stage - One Pending pour observatoire par les relais IDA / 56490 Pastoral Crisis Management Post Limited 0.00 2019-06-24 2019-08-19 2019-10-18 Quotations Envelope Implementation de veille

10-F/PRAPS / Support de Single Stage - One Pending communication/formation adapté IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 2019-10-30 2019-11-04 2019-12-04 2020-01-03 2020-02-07 2020-04-07 Envelope Implementation aux éleveurs

09-F/PRAPS / 1 véhicule 4x4 Project Management and Request for Single Stage - One Pending station wagon et 2 véhicules 4x4 IDA / 56490 Post Limited 0.00 2019-10-28 2019-12-23 2020-02-21 Institutional Support Quotations Envelope Implementation pick-up double cabine

05-F/PRAPS / Equiper Single Stage - One l'opérateur spécialisé (VSF-B) en IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 65,012.05 Completed 2016-01-08 2016-12-14 2016-01-22 2016-02-21 2017-01-24 2016-03-22 2017-02-13 2016-04-26 2017-06-23 2016-06-25 2017-08-25 Envelope véhicule

06-F/PRAPS / Production des Affiches et, dépliants (conception de 2 maquettes et impression de 2500 affiches et dépliants), Request for Single Stage - One IDA / 56490 Animal Health Improvement Post Limited 9,123.65 Completed 2017-05-26 2017-06-15 2017-07-21 2017-07-20 2017-08-20 2017-10-03 concevoir et produire des Quotations Envelope supports 'boites à images sur la santé animale et sur la conduite du troupeau

REF 11 / Equipements et Project Management and Request for Single Stage - One Pending mobiliers de bureau pour les IDA / 56500 Post Limited 0.00 2017-04-09 2017-06-04 2017-12-01 Institutional Support Quotations Envelope Implementation antennes régionales du Projet

REF 12 / Achat d'un véhicule Request for Single Stage - One Pending spécialement équipé pour les IDA / 56500 Animal Health Improvement Post Limited 0.00 2017-02-28 2017-04-25 2017-10-22 Quotations Envelope Implementation interventions d'urgence

REF 13 / Moquettes, rideaux et Project Management and Request for Single Stage - One Under accessoires pour l'Unité de IDA / 56500 Post Limited 0.00 2017-05-21 2017-07-16 2018-01-12 Institutional Support Quotations Envelope Implementation Coordination du Projet

REF 14 / Matériels Project Management and Request for Single Stage - One Pending informatiques pour les antennes IDA / 56500 Post Open - National 0.00 2017-04-09 2017-06-04 2017-12-01 Institutional Support Quotations Envelope Implementation régionales

REF 16 / Acquisition de 80 Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-03-22 2017-05-17 2017-11-13 smartphones Institutional Support Quotations Envelope Implementation

REF 17 / Equipements de travail Request for Single Stage - One Pending pour les enquêteurs et les IDA / 56500 Market Access Facilitation Post Limited 0.00 2017-03-14 2017-05-09 2017-11-05 Quotations Envelope Implementation contrôleurs

REF 19 / kit de semences Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2017-03-25 2017-05-20 2017-11-16 fourragères et petits équipements Quotations Envelope Implementation

Request for Single Stage - One Pending REF 22 / Trousses vétérinaires IDA / 56500 Animal Health Improvement Post Limited 0.00 2017-03-30 2017-05-25 2017-11-21 Quotations Envelope Implementation

REF 23 / 40 ordinateurs Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-04-14 2017-06-09 2017-12-06 portables et disques externes Institutional Support Quotations Envelope Implementation

REF 25 / Ordinateur portable et accessoires, imprimante Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-05-16 2017-07-11 2018-01-07 multifonction, photocopieuse et Institutional Support Quotations Envelope Implementation onduleur du PADEL-M

NE-PRAPS-NE-23100-GO-RFQ Request for Single Stage - One Pending / Equipements des 2 centres de IDA / 56510 Market Access Facilitation Post Limited 0.00 2017-10-20 2017-12-15 2018-06-13 Quotations Envelope Implementation collecte de lait

NE-PRAPS-NE-23249-GO-RFQ Request for Single Stage - One Pending / Son de blé (1100 tonnes) région IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation de Tahoua avec depot sur site

NE-PRAPS-NE-7610-GO-RFB / Project Management and Single Stage - One Pending Acquisition matériel roulant ( 26 IDA / 56510 Post Request for Bids Open - International 0.00 2017-02-27 2017-03-04 2017-04-15 2017-05-15 2017-06-19 2017-09-02 Institutional Support Envelope Implementation véhicules et 42 Moto)

NE-PRAPS-NE-7640-GO-RFQ / Request for Single Stage - One Pending Equipement Vétérinaire IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-02-28 2017-04-25 2017-06-24 Quotations Envelope Implementation (matériels froid)

NE-PRAPS-NE-7641-GO-RFQ / Equipements Vétérinaires Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-03-05 2017-04-30 2017-06-29 (Matériels de Prélèvement et Kits Quotations Envelope Implementation de diagnostic )

NE-PRAPS-NE-23326-GO-RFQ / Tourteaux de graine (300 Request for Single Stage - One Pending tonnes) région de Tahoua ( IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation tonnes)de coton avec depot sur site

NE-PRAPS-NE-23347-GO-RFQ / Fourniture des produits Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 vétérinaires et complexes Quotations Envelope Implementation minéraux pour la DGPIA

NE-PRAPS-NE-23327-GO-RFQ Request for Single Stage - One Pending / Son de blé région (1100 t) de IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation Zinder avec depot sur site

NE-PRAPS-NE-23328-GO-RFQ / Tourteaux de graine de coton Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 (300t) région de Zinder avec Quotations Envelope Implementation depot sur site

NE-PRAPS-NE-23330-GO-RFQ Request for Single Stage - One Pending / Son de blé région deDiffa (600) IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation avec depot sur site

NE-PRAPS-NE-23333-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Diffa ( 200 tonnes)de coton avec Quotations Envelope Implementation depot sur site

NE-PRAPS-NE-23335-GO-RFQ Request for Single Stage - One Under / Son de blé région de Maradi IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (1000 tonnes) avec depot sur site

NE-PRAPS-NE-23336-GO-RFQ / Tourteaux de graine région Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 deMaradi ( 200 tonnes)de coton Quotations Envelope Implementation avec depot sur site

NE-PRAPS-NE-23337-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Tillaberi IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (1000 tonnes) avec depot sur site

NE-PRAPS-NE-23338-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Tillaberi ( 250 tonnes)de coton Quotations Envelope Implementation avec depot sur site

NE-PRAPS-NE-23339-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Dosso IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (800 tonnes) avec depot sur site

NE-PRAPS-NE-23340-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Dosso ( 150 tonnes)de coton Quotations Envelope Implementation avec depot sur site

NE-PRAPS-NE-23341-GO-RFQ Request for Single Stage - One Pending / Son de blé région de Niamey IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Quotations Envelope Implementation (400 tonnes) avec depot sur site

NE-PRAPS-NE-23343-GO-RFQ / Tourteaux de graine région de Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 Niamey ( 250 tonnes)de coton Quotations Envelope Implementation avec depot sur site

Page 6 NE-PRAPS-NE-23344-GO-RFQ / Son de blé région de Agadez ( Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 1000 tonnes)de coton avec depot Quotations Envelope Implementation sur site

NE-PRAPS-NE-23345-GO-RFQ / Tourteau de graine de coton Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-08-06 2017-10-01 2018-03-30 région d'Agadez (300 tonnes) Quotations Envelope Implementation avec depot sur site

NE-PRAPS-NE-23045-GO-RFB Project Management and Single Stage - One Pending / Aquisition materiel informatique IDA / 56510 Post Request for Bids Open - National 0.00 2017-07-31 2017-08-05 2017-09-16 2017-10-16 2017-11-20 2018-05-19 Institutional Support Envelope Implementation et de communication

1 / Acquisition materiel roulant Project Management and Single Stage - One Pending IDA / 56510 Prior Request for Bids Open - International 0.00 2016-12-02 2016-12-07 2017-01-18 2017-02-17 2017-03-24 2017-09-20 (26véhicules et 50 Motos) Institutional Support Envelope Implementation

5 / Acquisition de vaccins et Request for Single Stage - One Pending diluants PPCB et diluants (6000 IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-11-06 2018-01-01 2018-06-30 Quotations Envelope Implementation 000 doses)

6 / Edition guide ingénierie Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 sociale Enhancement Quotations Envelope Implementation

7 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tanout Enhancement Quotations Envelope Implementation

8 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Belbedji IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Gangara

9 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Enhancement Quotations Envelope Implementation

10 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Takaya Enhancement Quotations Envelope Implementation

11 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Magaria IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Doungas

12 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Gouré Enhancement Quotations Envelope Implementation

13 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Boune Enhancement Quotations Envelope Implementation

14 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tesker Enhancement Quotations Envelope Implementation

15 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Agadez IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Aderbissanet

16 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de INGAL Enhancement Quotations Envelope Implementation

17 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tchiro- Enhancement Quotations Envelope Implementation

18 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Iférouane Enhancement Quotations Envelope Implementation

19 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Enhancement Quotations Envelope Implementation

20 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de say Enhancement Quotations Envelope Implementation

21 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Téra Enhancement Quotations Envelope Implementation

22 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Enhancement Quotations Envelope Implementation

23 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Filingué Enhancement Quotations Envelope Implementation

24 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Enhancement Quotations Envelope Implementation

25 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Guidan IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation Roumdji Madaroumfa

26 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Mayayi Enhancement Quotations Envelope Implementation

27 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Bermo Enhancement Quotations Envelope Implementation

28 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tchinta-Konni Enhancement Quotations Envelope Implementation

29 / Acquisition matériel aratoire Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Quotations Envelope Implementation

30 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Enhancement Quotations Envelope Implementation

31 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Tassara Enhancement Quotations Envelope Implementation

32 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Enhancement Quotations Envelope Implementation

33 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending pour les sites de Dogon kirya IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation

34 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de -Boboy Enhancement Quotations Envelope Implementation

35 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Diffa Enhancement Quotations Envelope Implementation

36 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 pour les sites de Mainé Enhancement Quotations Envelope Implementation

37 / Acquisition matériel aratoire Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 pour les sites de Enhancement Quotations Envelope Implementation

38 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région D'Agagez Enhancement Quotations Envelope Implementation

39 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-07 2018-03-04 2018-08-31 2 pour la région De Diffa Enhancement Quotations Envelope Implementation

40 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Dosso Enhancement Quotations Envelope Implementation

41 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Maradi Enhancement Quotations Envelope Implementation

42 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Tahoua Enhancement Quotations Envelope Implementation

43 / Achat semence espèce 1 et Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 2 pour la région De Tillaberi Enhancement Quotations Envelope Implementation

44 / Achat semence espèce 1,2 Natural Resource Management Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2018-01-04 2018-03-01 2018-08-28 et 3 pour la région De Zinder Enhancement Quotations Envelope Implementation

46 / Acquisition et installation du Natural Resource Management Request for Single Stage - One Pending système de securité ( alarme IDA / 56510 Post Limited 0.00 2017-10-04 2017-11-29 2018-05-28 Enhancement Quotations Envelope Implementation incendie et vidéo surveillance)

47 / Achat matériel de collecte Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-10-25 2017-12-20 2018-06-18 pour la DGSV Quotations Envelope Implementation

48 / Acquisition materiels Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-27 2017-12-22 2018-06-20 d'archivage electronique Institutional Support Quotations Envelope Implementation

Page 7 49 / Acquisition de logiciel pour Request for Single Stage - One Pending 5 postes ( Arc Gis logicel R et IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-10-27 2017-12-22 2018-06-20 Quotations Envelope Implementation SPSS)

50 / Acquisition matériel Natural Resource Management Request for Single Stage - One Pending informatique et mobilier de IDA / 56510 Post Limited 0.00 2017-10-27 2017-12-22 2018-06-20 Enhancement Quotations Envelope Implementation bureau pour les 5 postes OSV

NE-PRAPS-NE-30651-GO-RFQ / Réalisation de film sur la place Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-10-15 2017-12-10 2018-06-08 des femmes et des jeune dans le Institutional Support Quotations Envelope Implementation pastoralisme

REF 20 / Un ordinateur, 1 imprimante et photocopieur, 2 Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-03-24 2017-03-24 2017-03-24 bureaux, une armoire, fournitures Institutional Support Quotations Envelope Implementation de bureau

ML-PRAPS-ML-31420-GO-RFB Single Stage - One Pending / Acquisition et Transport IDA / 56500 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2017-10-10 2017-10-15 2017-11-26 2017-12-26 2018-01-30 2018-07-29 Envelope Implementation d'aliment bétail

NE-PRAPS-NE-30638-GO-DIR / Pending Acquisition de vaccins et diluants IDA / 56510 Animal Health Improvement Prior Direct Selection Direct 0.00 2017-11-09 2017-11-14 2017-12-16 2018-06-14 Implementation PPR (15 000 000 doses)

NE-PRAPS-NE-34367-GO-RFQ Request for Single Stage - One Pending / Mise en place des incinérateurs IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-12-05 2018-01-30 2018-07-29 Quotations Envelope Implementation pour la gestion des déchets

NE-PRAPS-NE-34385-GO-RFQ Request for Single Stage - One Pending / Acquisition /construction des IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-11-11 2018-01-06 2018-07-05 Quotations Envelope Implementation parcs mobiles pour bovins

01-F/MOD1 / Equipement 111 Natural Resource Management Single Stage - One Pending forages solaires et manuels dans IDA / 56490 Post Request for Bids Open - National 0.00 2018-09-28 2018-10-19 2018-11-18 2018-12-09 2019-01-22 2019-05-22 Enhancement Envelope Implementation les régions du PRAPS-BF

17-F/PRAPS / Edition des manuels par compilation des Natural Resource Management Request for Single Stage - One Pending différentes règlementations IDA / 56490 Post Limited 0.00 2018-10-01 2018-11-26 2019-01-25 Enhancement Quotations Envelope Implementation existantes dans le domaine du pastoralisme

MR-PRAPS-MR -43177-GO-DIR / Acquisition de médicaments Pending IDA / D0660 Pastoral Crisis Management Prior Direct Selection Direct 0.00 2018-01-29 2018-02-03 2018-03-10 2018-09-06 vétérinaires pour le plan Implementation d'urgence.

Animal Health Improvement 04-F/PRAPS / Acquisition de Natural Resource Management Request for Single Stage - One IDA / 56490 Post Limited 59,620.75 Completed 2017-04-07 2017-05-22 2017-06-18 2017-07-21 2017-08-02 2017-10-27 165 tablettes Enhancement Quotations Envelope

Market Access Facilitation

F03 MR PRAPS 2017 / Acquisition d'équipements et Single Stage - Two Pending matériel de laboratoire de IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-27 2018-03-04 2018-04-15 2018-06-28 2018-08-02 2019-01-29 Envelope Implementation contrôle médicaments au profit du ONARDEL

PRAPS-SN-01-F-2018 / Acquisition de matériel de froid Request for Single Stage - One Pending IDA / 56520 Animal Health Improvement Post Limited 0.00 2018-02-21 2018-04-18 2018-06-02 complémentaire pour les services Quotations Envelope Implementation vétérinaires

PRAPS-SN-02-F-2018 / Single Stage - Two Pending Acquisition de vaccins (PPCB, IDA / 56520 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-02-02 2018-02-07 2018-03-21 2018-07-08 2018-10-06 Envelope Implementation PPR et FVR)

PRAPS-SN-03-F-2018 / Recrutement d'un prestataire Animal Health Improvement Request for Single Stage - One Pending pour la confection de supports IDA / 56520 Project Management and Post Limited 0.00 2018-04-12 2018-06-07 2018-09-05 Quotations Envelope Implementation promotionnels (agendas, polos, Institutional Support etc.)

PRAPS-SN-05-F-2018 / Fourniture et Installation Single Stage - Two Pending IDA / 56520 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-24 2018-03-01 2018-04-12 2018-07-30 2018-10-28 d'équipements des centres de Envelope Implementation collectes, laiteries et fromagerie

PRAPS-SN-07-F-2018 / Acquisition de groupes Project Management and Request for Single Stage - One Under IDA / 56520 Post Limited 0.00 2018-02-14 2018-02-26 2018-04-11 2018-07-10 électrogènes pour les antennes Institutional Support Quotations Envelope Implementation du PRAPS

PRAPS-SN-08-F-2018 / Project Management and Request for Single Stage - One Pending Acquisition de mobilier IDA / 56520 Post Limited 0.00 2018-03-08 2018-05-03 2018-07-02 Institutional Support Quotations Envelope Implementation d'archivage

BF-CILSS-44411-GO-RFQ / Renouvellement de licence de la Project Management and Request for Single Stage - One IDA / D0640 Post Limited 7,492.24 Signed 2018-01-28 2018-01-23 2018-03-11 2018-02-14 2018-03-21 passerelle du système visio Institutional Support Quotations Envelope conférence

BF-CILSS-44413-GO-RFQ / Project Management and Request for Single Stage - One Under Mise à jour de l'autocommutateur IDA / D0640 Post Limited 0.00 2018-01-29 2018-01-26 2018-03-05 2018-03-15 Institutional Support Quotations Envelope Implementation du CILSS

BF-PRAPS-BF-44618-GO-RFB / Aliments de bétail pour approvisionner des magasins en stocks durgence (30 000 tonnes Single Stage - One Under IDA / 56490 Pastoral Crisis Management Prior Request for Bids Open - International 0.00 2018-02-15 2018-02-13 2018-03-01 2018-04-21 2018-04-12 2018-05-09 2018-04-26 2018-06-09 2018-08-08 aliment bétail) pour distribution Envelope Implementation

SECNSA et SP-CVEL, DGEAP pour réponse à la contingence sécheresse

BF-PRAPS-BF-44630-GO-RFB / Acquisition et transport sur sites de vivres pour distribution pour vente à prix modéré/Boutiques Single Stage - One Under témoins SP CVEL pour IDA / 56490 Pastoral Crisis Management Prior Request for Bids Limited 0.00 2018-02-15 2018-03-05 2018-02-20 2018-04-03 2018-04-17 2018-05-31 2018-07-30 Envelope Implementation assistance aux sinistrés en réponse à la contingence conflits entre exploitants /scénaris de pire cas/DGEAP

07-F/PRAPS / Equipement Animal Health Improvement informatique, ordinateurs, 31 kits Project Management and solaires, 31 refrigérateurs ,31 Institutional Support Single Stage - One congelateur ,62 glacière, IDA / 56490 Pastoral Crisis Management Post Request for Bids Open - National 370,326.86 Signed 2017-04-19 2017-07-17 2017-04-24 2017-06-05 2017-09-04 2017-07-05 2017-09-13 2017-08-09 2017-12-18 2017-11-07 Envelope 124bouteilles de gaz, 35 Natural Resource Management smatphones, 35 power Bank, 50 Enhancement copteurs, équip. communicaion Market Access Facilitation

11-F/PRAPS / 100 Kits outils Request for Single Stage - One Under pour observatoire par les relais IDA / 56490 Pastoral Crisis Management Post Limited 0.00 2017-06-20 2017-05-22 2017-08-15 2017-10-14 Quotations Envelope Implementation de veille

08-F/PRAPS / 31 kits solaires - Request for Single Stage - One acquisition, pose et installation IDA / 56490 Animal Health Improvement Post Limited 104,475.96 Signed 2017-11-15 2017-10-12 2018-01-26 2018-02-21 2018-03-12 Quotations Envelope de

MOF-REF-1 / Acquisition de 43 Request for Single Stage - One motos au profit de la DGSV et de IDA / 56490 Animal Health Improvement Post Limited 94,702.76 Completed 2017-09-10 2017-09-05 2017-11-14 2017-10-30 2017-12-29 2017-12-28 Quotations Envelope VSF-B

BF-PRAPS-BF-45936-GO-RFQ / 43 motos au profit des structures déconcentrées de collectes de Request for Single Stage - One Pending IDA / 56490 Pastoral Crisis Management Post Limited 0.00 2018-05-19 2018-07-23 2018-09-21 données dans le cadre de la Quotations Envelope Implementation composante 4 (gestion des crises)

BF-PRAPS-BF-45948-GO-RFB / 375 kits pour insertion socio- Single Stage - One Pending IDA / 56490 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2018-04-18 2018-04-23 2018-05-23 2018-06-13 2018-07-27 2018-09-25 professionnelle de la 1ère Envelope Implementation cohorte (C4)

BF-PRAPS-BF-45979-GO-RFQ / Request for Single Stage - One Pending IDA / 56490 Animal Health Improvement Post Limited 0.00 2018-03-26 2018-05-21 2018-07-20 Matériel de vaccination Quotations Envelope Implementation

BF-PRAPS-BF-45989-GO-RFB / Single Stage - One IDA / 56490 Animal Health Improvement Post Request for Bids Open - National 0.00 Canceled 2018-03-14 2018-04-04 2018-05-04 2018-05-25 2018-07-08 2018-09-06 Vaccins contre la PPR Envelope

BF-PRAPS-BF-46005-GO-RFQ / Project Management and Request for Single Stage - One Confection de goodies (publicité IDA / 56490 Post Limited 10,498.97 Signed 2018-02-26 2018-02-14 2018-04-02 2018-02-28 2018-05-02 Institutional Support Quotations Envelope par l'objet)

BF-PRAPS-BF-46009-GO-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56490 Post Limited 0.00 2018-06-17 2018-08-12 2019-02-08 Activité hors médias Institutional Support Quotations Envelope Implementation

Page 8 ML-PRAPS-ML-46243-GO-RFQ / Acquisition des semences, de boutures et d'éclats de souches de diverses espèces/variétés Natural Resource Management Request for Single Stage - One Under IDA / 56500 Post Limited 0.00 2018-03-30 2018-04-25 2018-05-25 2018-11-21 d'herbacées et de ligneuses pour Enhancement Quotations Envelope Implementation les travaux de restauration des pâturages exondés et des bourgoutières

ML-PRAPS-ML-46244-GO-RFQ / Acquisition de 11 Kiosques et Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2018-09-30 2018-11-25 2019-05-24 11 kits pour la transformation de Quotations Envelope Implementation la viande

ML-PRAPS-ML-46245-GO-RFQ / Acquisition de 11 tricycles Request for Single Stage - One Pending IDA / 56500 Market Access Facilitation Post Limited 0.00 2018-10-13 2018-12-08 2019-06-06 motorisés pour le transport de la Quotations Envelope Implementation viande

ML-PRAPS-ML-46327-GO-RFQ / Acquisition de 72 Smartphones Project Management and Request for Single Stage - One Pending pour la collecte et la remontée de IDA / 56500 Post Limited 0.00 2018-02-23 2018-04-20 2018-10-17 Institutional Support Quotations Envelope Implementation l'information géo référenciée pour 31 cercles et 10 régions

PRAPS-SN-04-F-2018 / Natural Resource Management Under Acquisition de 4 motos pour IDA / 56520 Post Direct Selection Direct 0.00 2018-03-03 2018-03-11 2018-03-08 2018-03-12 2018-04-12 2018-06-11 Enhancement Implementation l'animation des UP

PRAPS-SN-10-F-2018 / Acquisition de divers fournitures sous fore de contrats-cadres en Single Stage - One trois lots separes Lot 1 produits IDA / 56520 Pastoral Crisis Management Post Request for Bids Open - National 0.00 Canceled 2018-02-07 2018-02-12 2018-03-26 2018-04-25 2018-05-30 2019-05-30 Envelope veterinaires Lot 2 aliment de betail et Lot 3 betail ovins et caprins

MR-PRAPS-MR -48640-GO- Single Stage - One Pending RFB / Acquisition d'un camion IDA / D0660 Animal Health Improvement Post Request for Bids Open - National 0.00 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2018-11-03 Envelope Implementation frigorifique

MR-PRAPS-MR -48643-GO- RFB / Acquisition d'équipements Single Stage - One Pending IDA / D0660 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-05-15 2018-05-20 2018-06-19 2018-07-04 2018-08-03 2018-09-02 informatiques et bureautiques Envelope Implementation pour la composante 3

MR-PRAPS-MR -48646-GO- Request for Single Stage - One Pending RFQ / Acquisition de materiel de IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-04-21 2018-06-12 2018-07-02 Quotations Envelope Implementation prelevement

MR-PRAPS-MR -48647-GO- RFQ / Acquisition de Kits ELISA Request for Single Stage - One Pending PPR pour le monitoring et Kits IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-04-04 2018-05-30 2018-11-26 Quotations Envelope Implementation ELISA PPCB pour l'enquête de prévalence

MR-PRAPS-MR -48652-GO- Project Management and Request for Single Stage - One Pending RFQ / Acquisition du logiciel MS IDA / D0660 Post Open - National 0.00 2018-04-23 2018-06-04 2018-06-19 Institutional Support Quotations Envelope Implementation project

MR-PRAPS-MR -48657-GO- Project Management and Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-04-21 2018-05-21 2018-05-31 RFQ / Acquisition de 20 GPS Institutional Support Quotations Envelope Implementation

ML-PRAPS-ML-48894-GO-RFB / Acquisition de véhicules (4 Station wagon, 5 Pickups) Project Management and Single Stage - One Under complémentaires pour améliorer IDA / 56500 Post Request for Bids Open - National 0.00 2018-03-12 2018-03-16 2018-03-17 2018-04-28 2018-03-16 2018-05-28 2018-05-07 2018-07-02 2018-12-29 Institutional Support Envelope Implementation la mobilité des services techniques (DNSV, DNPIA) et de l'UCP

MR-PRAPS-MR -48977-GO- Request for Single Stage - One Pending RFQ / carnets à souches pour le IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-05-26 2018-07-12 2018-08-11 Quotations Envelope Implementation suivi sanitaire

TD-PRAPS-TD-49619-GO-DIR / Pending Acquisition de 15 millions de IDA / D0650 Animal Health Improvement Prior Direct Selection Direct 0.00 2018-06-10 2018-06-15 2018-07-20 2019-01-16 Implementation doses de vaccin contre la PPR

BF-PRAPS-BF-44635-GO-DIR / Achat et transport sur sites de produit vétérinaires d'intervention Pending IDA / 56490 Pastoral Crisis Management Post Direct Selection Direct 0.00 2018-02-15 2018-02-20 2018-04-07 2018-06-06 en réponse à la contingence Implementation

épizooties/scénario du pire/DGSV

TD-PRAPS-TD-50122-GO-DIR / Pending Acquisition de six millions de IDA / D0650 Animal Health Improvement Prior Direct Selection Direct 0.00 2018-06-01 2018-06-06 2018-07-11 2019-01-07 Implementation doses de vaccin contre la PPCB

TD-PRAPS-TD-50145-GO-RFQ / Acquisition des matériels et Request for Single Stage - One Pending IDA / D0650 Animal Health Improvement Post Limited 0.00 2018-04-15 2018-06-10 2018-12-07 chaine de froid et une chambre Quotations Envelope Implementation négative

TD-PRAPS-TD-50430-GO-RFQ / Acquisition des groupes Project Management and Request for Single Stage - One Pending IDA / D0640 Post Limited 0.00 2018-03-25 2018-05-20 2018-11-16 électrogènes pour les antennes Institutional Support Quotations Envelope Implementation régionales du PRAPS

TD-PRAPS-TD-50439-GO-RFQ / Acquisition des équipements Request for Single Stage - One Pending IDA / D0650 Market Access Facilitation Post Limited 0.00 2018-04-15 2018-06-10 2018-12-07 SIM Bétail (1 véhicule et 20 Quotations Envelope Implementation motos)

TD-PRAPS-TD-50445-GO-RFB / Acquisition des équipements Natural Resource Management Single Stage - One Pending IDA / D0650 Post Request for Bids Limited 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 UAF en matériels de travail et Enhancement Envelope Implementation fournitures de bureau

TD-PRAPS-TD-50451-GO-RFQ / Acquisition des matériels de Natural Resource Management Request for Single Stage - One Pending IDA / D0640 Post Limited 0.00 2018-04-04 2018-05-30 2018-11-26 travail de la Division d'Ingénierie Enhancement Quotations Envelope Implementation de Formation de

PRAPS-SN-09-F-2018 / Acquisition de matériel Project Management and Request for Single Stage - One Under informatique pour CONACILSS et IDA / 56520 Post Limited 0.00 2018-02-27 2018-04-24 2018-06-23 Institutional Support Quotations Envelope Implementation PRAPS ainsi que d'un kit de suivi environnement

TD-PRAPS-TD-50153-GO-RFQ / Acquisition de trousses Request for Single Stage - One Pending vétérinaires + kit de prélèvement IDA / D0650 Animal Health Improvement Post Limited 0.00 2018-04-21 2018-06-16 2018-12-13 Quotations Envelope Implementation et de vaccination + produits vétérinaires

ML-PRAPS-ML-53212-GO-RFB / Acquisition de vingt cinq (25) Single Stage - One Under IDA / 56500 Market Access Facilitation Post Request for Bids Open - National 0.00 2018-02-01 2017-09-27 2018-02-06 2018-03-20 2018-05-24 2018-11-20 kits de collecte et transformation Envelope Implementation de lait

F01 MR PRAPS 2017 / Acquisition de 3 000 000 doses Pending IDA / D0660 Animal Health Improvement Prior Direct Selection Direct 0.00 2017-05-15 2017-05-30 2017-07-25 2017-10-23 de vaccins pour la campagne Implementation

2017/2018

PRAPS-SN-10-F-2018-BIS / Acquisition de divers fournitures et tetes de betails en cas de Single Stage - One Under IDA / 56520 Pastoral Crisis Management Post Request for Bids Open - National 0.00 2017-10-03 2017-10-11 2017-10-11 2017-11-23 2017-11-23 2018-01-17 2018-01-17 2018-04-17 2021-04-18 declenchement de crise Envelope Implementation pastorale (aliment de betail produits veterinaires betail)

PRAPS-MR-6F / acquisition de Project Management and Single Stage - One Pending IDA / D0660 Post Request for Bids Open - National 0.00 2018-04-18 2018-04-23 2018-06-04 2018-07-04 2018-08-08 2019-02-04 2 vehicules station vagon Institutional Support Envelope Implementation

NE-PRAPS-NE-54730-GO-RFQ / Acquisition des fournitures , Project Management and Request for Single Stage - One Pending mobiliers de bureau et produits IDA / 56520 Post Limited 0.00 2018-03-28 2018-05-23 2018-11-19 Institutional Support Quotations Envelope Implementation d'entretiens pour l'UCP et Antennes Régionales du PRAPS

NE-PRAPS-NE-54873-GO-RFQ / Reproduction et diffusion des Request for Single Stage - One Pending IDA / 56510 Animal Health Improvement Post Limited 0.00 2018-07-06 2018-08-31 2019-02-27 guides et manuels sur les Quotations Envelope Implementation maladies

NE-PRAPS-NE-30649-GO-RFQ / Acquisition de matériel de Request for Single Stage - One Pending prélèvements, de labo , kits IDA / 56510 Animal Health Improvement Post Limited 0.00 2017-10-22 2017-12-17 2018-06-15 Quotations Envelope Implementation d'analyses pour les 2 campagnes sero monitoring

NE-PRAPS-NE-23097-GO-RFQ Request for Single Stage - One Pending / Equipement de 3 OSV et 15 IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2017-09-01 2018-06-02 2018-11-29 Quotations Envelope Implementation SCAP - RU

Page 9 NE-PRAPS-NE-54991-GO-RFQ Request for Single Stage - One Pending / Equipements de 4 centres de IDA / 56510 Market Access Facilitation Post Limited 0.00 2018-07-06 2018-08-31 2019-02-27 Quotations Envelope Implementation collecte de lait

NE-PRAPS-NE-55001-GO-RFQ / Acquisition/entretien de 4 Request for Single Stage - One Pending IDA / 56510 Market Access Facilitation Post Limited 0.00 2018-08-06 2018-10-01 2019-03-30 motos pour les centres de Quotations Envelope Implementation collecte de lait

NE-PRAPS-NE-55005-GO-RFQ / Equipement complémentaire Request for Single Stage - One Pending IDA / 56510 Market Access Facilitation Post Limited 0.00 2018-05-10 2018-07-05 2019-01-01 aux radios communautaires de Quotations Envelope Implementation proximité

NE-PRAPS-NE-55011-GO-RFQ Request for Single Stage - One Pending / Edition des textes sur la IDA / 56510 Market Access Facilitation Post Limited 0.00 2018-04-12 2018-06-07 2018-12-04 Quotations Envelope Implementation commercialisation du BVCP

NE-PRAPS-NE-55015-GO-RFQ Request for Single Stage - One Pending IDA / 56510 Pastoral Crisis Management Post Limited 0.00 2018-08-06 2018-10-01 2019-03-30 / Edition et vulgarisation du guide Quotations Envelope Implementation

ML-PRAPS-ML-55379-GO-RFQ / Acquisition de matériels Project Management and Request for Single Stage - One Pending informatiques (portable, scanner) IDA / 56500 Post Limited 0.00 2018-04-09 2018-06-04 2018-12-01 Institutional Support Quotations Envelope Implementation pour une utilisation pratique et efficiente de STEP

BF-CILSS-BF-52681-GO-RFQ / Confection de supports de communication (Kakémonos, Project Management and Request for Single Stage - One Pending IDA / D0640 Post Limited 0.00 2018-04-15 2018-06-03 2018-07-18 guide routier, et autres visuels de Institutional Support Quotations Envelope Implementation la C3) et Mise en État des kakemonos de 2015-2016

TD-PRAPS-TD-57338-GO-RFB / Single Stage - One Pending Acquisition de chambre négative IDA / D0650 Animal Health Improvement Post Request for Bids Limited 0.00 2018-05-10 2018-05-15 2018-06-26 2018-07-26 2018-08-30 2019-02-26 Envelope Implementation et matériels de chaine de froid

TD-PRAPS-TD-57341-GO-RFB / Single Stage - One Pending Equipement de laboratoire pour IDA / 56490 Animal Health Improvement Post Request for Bids Limited 0.00 2018-06-05 2018-06-10 2018-07-22 2018-08-21 2018-09-25 2019-03-24 Envelope Implementation l'IRED

TD-PRAPS-TD-57344-GO-RFQ / Project Management and Request for Single Stage - One Pending Acquisition de panneaux solaires IDA / D0650 Post Limited 0.00 2018-06-20 2018-08-15 2019-02-11 Institutional Support Quotations Envelope Implementation pour les antennes régionales

TD-PRAPS-TD-57348-GO-RFQ / Request for Single Stage - One Pending IDA / D0650 Animal Health Improvement Post Limited 0.00 2018-07-03 2018-08-28 2019-02-24 Acquisition des GPS Quotations Envelope Implementation

TD-PRAPS-TD-57352-GO-RFQ / Request for Single Stage - One Pending IDA / D0650 Animal Health Improvement Post Limited 0.00 2018-07-25 2018-09-19 2019-03-18 Acquisition des Smartphone Quotations Envelope Implementation

TD-PRAPS-TD-57353-GO-RFQ / Request for Single Stage - One Pending Acquisition de mobilier et IDA / D0650 Animal Health Improvement Post Limited 0.00 2018-07-15 2018-09-09 2019-03-08 Quotations Envelope Implementation matériels informatiques

TD-PRAPS-TD-57354-GO-RFQ / Project Management and Request for Single Stage - One Pending Acquisition des matériels de IDA / D0650 Post Limited 0.00 2018-08-01 2018-09-26 2019-03-25 Institutional Support Quotations Envelope Implementation viéoconférence

PRAPS F01 / acquisition de Project Management and Request for Single Stage - One Pending pneu pour le parc s automobile IDA / D0660 Post Limited 0.00 2018-05-07 2018-07-02 2018-09-30 Institutional Support Quotations Envelope Implementation de l UCP

PRAPS CF 03 / aquisitiion de Project Management and Request for Single Stage - One Pending produit d entretien de bureau et IDA / D0660 Post Limited 0.00 2018-06-04 2018-07-30 2018-10-28 Institutional Support Quotations Envelope Implementation de vehicule du PRAPS

MR-PRAPS-MR -24F / Acquisition en 5 lots distincts Pending IDA / D0660 Pastoral Crisis Management Prior Direct Selection Direct 0.00 2018-05-08 2018-05-10 2018-05-27 2018-06-26 d'aliment de bétail pour le plan Implementation d'urgence (PAC 2018)

MR-PRAPS-MR -23F / Acquisition de 7.000.000 de Pending IDA / D0660 Animal Health Improvement Prior Direct Selection Direct 0.00 2018-07-19 2018-07-24 2018-09-17 2018-12-16 doses de vaccins PPR pour la Implementation campagne 2018-2019

PRAPS-MR-5F / acquisition d equipements pour l appui na la Project Management and Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-06-01 2018-07-27 2019-01-23 Commission des marchés du Institutional Support Quotations Envelope Implementation secteur de l Elevage

PRAPS-MR- 4F / acquisition d Project Management and Request for Single Stage - One Pending équipement pour la salle de IDA / D0660 Post Limited 0.00 2018-06-04 2018-07-30 2019-01-26 Institutional Support Quotations Envelope Implementation réunion du Praps

NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

NE-PRAPS-NE-7661-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-24 2017-04-21 2018-04-16 Internet Institutional Support Quotations Envelope Implementation

NE-PRAPS-NE-7665-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56510 Post Limited 0.00 2017-02-25 2017-04-22 2018-04-17 Assurance véhicule Institutional Support Quotations Envelope Implementation

PRAPS-SN-10-F / Acquisition Project Management and du logiciel MS Project et IDA / 56520 Prior Direct Selection Direct 0.00 Canceled 2017-03-13 2017-03-18 2017-04-22 2017-05-22 Institutional Support formation des utilisateurs

PRAPS-SN-08-F / Services d'entretiens et de maintenance Project Management and Request for Single Stage - One IDA / 56520 Post Limited 0.00 Canceled 2016-12-30 2017-01-17 2018-01-17 du matériel informatique, du site Institutional Support Quotations Envelope web du PRAPS

REF 28 / Appui à la production Natural Resource Management Request for Single Stage - One Pending des cartes des couloirs de IDA / 56500 Post Limited 0.00 2017-04-16 2017-06-11 2017-12-08 Enhancement Quotations Envelope Implementation transhumance

REF 29 / Développement dune Project Management and Request for Single Stage - One Pending page Facebook et dune page IDA / 56500 Post Limited 0.00 2017-06-17 2017-08-12 2018-02-08 Institutional Support Quotations Envelope Implementation YouTube

REF 30 / Conception et Project Management and Request for Single Stage - One Pending réalisation dun clip vidéo pour le IDA / 56500 Post Limited 0.00 2017-04-15 2017-06-10 2017-12-07 Institutional Support Quotations Envelope Implementation PRAPS

NE-PRAPS-NE-7669-NC-DIR / Project Management and Pending IDA / 56510 Post Direct Selection Direct 0.00 2017-02-19 2017-02-24 2017-03-31 2018-03-26 Location Bureaux UCP/PRAPS Institutional Support Implementation

NE-PRAPS-NE-7642-NC-DIR / Etablissement de 7 conventions Project Management and Pending IDA / 56510 Post Direct Selection Direct 0.00 2017-02-28 2017-03-05 2017-04-09 2017-10-06 avec les média locaux pour la Institutional Support Implementation vulgarisation des textes

ML-PRAPS-ML-34772-NC-RFQ / Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-11-05 2017-12-31 2018-06-29 Diffusion de messages Institutional Support Quotations Envelope Implementation

PRAPS-SN-06-F-2018 / Recrutement d'un prestataire Project Management and Request for Single Stage - One Pending IDA / 56520 Post Limited 0.00 2018-03-19 2018-05-14 2019-05-14 pour la police d'assurance santé Institutional Support Quotations Envelope Implementation des agents du PRAPS

ML-PRAPS-ML-47132-NC-RFQ / Conception, radialisation et diffusion des supports de communication sur les activités Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2018-02-24 2018-04-21 2018-10-18 et les acquis du PRAPS- ML par Institutional Support Quotations Envelope Implementation

: affichage, audio et audiovisuel, (film, sketchs, affiches, panneaux)

REF 27 / Production des Project Management and Request for Single Stage - One Pending IDA / 56500 Post Limited 0.00 2017-05-15 2017-07-10 2018-01-06 supports de vulgarisation Institutional Support Quotations Envelope Implementation

MR-PRAPS-MR -48649-NC-RFQ / Edition de 1000 brochures du Natural Resource Management Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-05-20 2018-07-11 2018-08-25 Code pastoral en arabe/Français Enhancement Quotations Envelope Implementation et en langues nationales

MR-PRAPS-MR -48650-NC-RFQ / Conception, édition et duplication de supports imprimés Natural Resource Management Request for Single Stage - One Pending IDA / D0660 Post Open - National 0.00 2018-05-20 2018-07-06 2018-07-21 et scriptovisuels de Enhancement Quotations Envelope Implementation communication pour la composante 2

Page 10 MR-PRAPS-MR -48654-NC-RFB / Acquisition de matériels de visibilité et de supports Project Management and Single Stage - One Pending IDA / D0660 Post Request for Bids Open - National 0.00 2018-04-19 2018-04-24 2018-05-09 2018-05-24 2018-06-13 2018-07-13 communication variés (imprimés Institutional Support Envelope Implementation et scriptovisuels) pour l'UC PRAPS/Partenaires

MR-PRAPS-MR -48970-NC-RFQ Project Management and Request for Single Stage - One Pending / Production d'un film IDA / D0660 Post Limited 0.00 2018-05-15 2018-06-25 2018-07-25 Institutional Support Quotations Envelope Implementation documentaire

MR-PRAPS-MR -48971-NC-RFQ / Diffusion d'Émissions, de microprogrammes radio et Project Management and Request for Single Stage - One Pending productions médiatiques écrites IDA / D0660 Post Limited 0.00 2018-05-20 2018-06-26 2018-07-26 Institutional Support Quotations Envelope Implementation de vulgarisation du code pastoral et des thématiques essentielles sur la GRN

03-S/PRAPS / Assurance Project Management and Request for Single Stage - One IDA / 56490 Post Limited 0.00 Canceled 2017-04-22 2017-06-10 2017-07-16 maladie Institutional Support Quotations Envelope

BF-PRAPS-BF-49968-NC-DIR / Project Management and Assurance maladie du personnel IDA / 56490 Post Direct Selection Direct 39,313.98 Signed 2017-06-01 2017-07-12 2017-06-08 2017-07-19 2017-07-22 2017-08-07 2018-07-22 Institutional Support du PRAPS-BF

MR-PRAPS-MR -43178-NC-RFQ / Logistique (Transport, Single Stage - One Pending manutention et entreposage de IDA / D0660 Pastoral Crisis Management Prior Request for Bids Open - National 0.00 2018-03-20 2018-03-25 2018-05-06 2018-06-05 2018-07-10 2019-01-06 Envelope Implementation l'aliment de bétail) pour le plan d'urgence.

CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual

NE-PRAPS-NE-7700-CS-CQS / Multiples Conventions avec les opérateurs privés pour l'organisation des usagers de Consultant parcours(ingénerie sociale, Project Management and Pending IDA / 56510 Prior Qualification Open - National 0.00 2017-02-20 2017-03-13 2017-04-26 2017-05-26 2017-06-30 2018-06-25 aménagements pastoraux et Institutional Support Implementation Selection hydraulique pastorale ds les 7 régions avec une vingtaine d' ONG au niveau de Vingt sept zones

NE-PRAPS-NE-7766-CS-CQS / Appui à la mise en place d'un Consultant disposititif adapté Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-03-13 2017-04-03 2017-05-17 2017-06-16 2017-07-21 2017-09-19 d'approvisionnement et de Implementation Selection distribution d'aliments bétail en cas de crise pastorale

NE-PRAPS-NE-7769-CS-CQS / Consultant Elaboration d'un document Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-03-23 2017-04-13 2017-05-27 2017-06-26 2017-07-31 2017-08-30 d'evaluation d'une activité en Implementation Selection situation de crises pastorales

PRAPS-SN-12-PI / Sélection d'un consultant individuel pour Consultant l'étude de capitalisation des IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 0.00 Canceled 2016-11-29 2017-02-09 2017-03-26 2017-04-25 2017-06-09 2017-10-07 activités de la cellule de lutte Selection contre le vol de bétail

PRAPS-SN-04-PI / Sélection d'un cabinet pour l'étude sur les Consultant initiatives en cours pour la mise Natural Resource Management Pending IDA / 56520 Post Qualification Open - National 0.00 2017-03-27 2017-04-17 2017-05-31 2017-06-30 2017-08-04 2018-01-01 en place de pares feux dans le Enhancement Implementation Selection cadre de la lutte contre les feux de brousses

PRAPS-SN-06-PI / Sélection d'un cabinet pour les études Consultant Pending techniques en vue de la IDA / 56520 Market Access Facilitation Post Qualification Open - National 0.00 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2017-12-08 Implementation réhabilitation de 50 km de pistes Selection rurales

PRAPS-SN-10-PI / Sélection Consultant Pending d'un cabinet pour les services IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-08-28 2017-09-18 2017-11-01 2017-12-01 2018-01-05 2018-05-05 Implementation d'évaluation d'impact OSB Selection

TD-PRAPS-TD-9404-CS-QBS / Recrutement d'un consultant Project Management and Quality Based Pending IDA / D0650 Post Open - National 0.00 2017-03-23 2017-04-13 2017-05-27 2017-06-24 2017-07-24 2017-08-23 2017-09-27 2018-09-27 pour les travaux de réhabilitation Institutional Support Selection Implementation des locaux de l'UCP

19-C/MODSIEGE / MOD pour la Consultant Project Management and construction du siège de l'UCP IDA / 56490 Post Qualification Open - National 120,111.82 Signed 2017-03-09 2017-02-21 2017-03-30 2017-04-27 2017-04-14 2017-05-11 2017-05-02 2017-06-08 2017-06-01 2018-09-01 Institutional Support PRAPS Selection

43-C/PRAPS / Capitalisation Consultant des connaissances endogènes Pending IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 0.00 2019-11-28 2019-12-12 2020-01-09 2020-01-23 2020-02-20 2020-03-21 sur les indicateurs de crise en Implementation Selection pastoralisme

07-C/PRAPS / Evaluation de Consultant l'intégration du pastoralisme dans Pending IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-06-23 2017-07-14 2017-08-11 2017-08-25 2017-09-22 2017-10-22 les instruments de gestion des Implementation Selection crises au Burkina Faso

37-C/PRAPS / Etude offre de formation professionnelle en lien avec le pastoralisme au profit des jeunes et capitalisation des Consultant activités connexes autour des IDA / 56490 Pastoral Crisis Management Post Qualification Open - National 22,462.51 Signed 2017-06-16 2017-05-26 2017-07-07 2017-08-04 2017-06-17 2017-08-18 2017-07-21 2017-09-22 2017-07-27 2017-09-22 infrastructures d'élevage, des Selection AGR éligibles dans le PRAPS en relation avec le genre et les technologies adapté

46-C/PRAPS / Elaboration Consultant Natural Resource Management Pending référentiel technique des IDA / 56490 Post Qualification Open - National 0.00 2019-11-29 2019-12-20 2020-01-17 2020-01-31 2020-02-28 2020-03-29 Enhancement Implementation infrastructures pastorales Selection

REF 38 / Etudes pour 15 Consultant Natural Resource Management Pending schémas d'aménagement de IDA / 56500 Post Qualification Open - National 0.00 2017-04-18 2017-05-09 2017-06-22 2017-07-22 2017-08-26 2018-02-22 Enhancement Implementation terroirs Selection

Consultant REF 39 / Contrôle -surveillance Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-03-14 2017-04-04 2017-05-18 2017-06-17 2017-07-22 2018-01-18 des travaux daménagement Implementation Selection

REF 40 / Evaluation des Natural Resource Management Quality And Cost- Pending IDA / 56500 Post Open - National 0.00 2017-05-03 2017-05-24 2017-07-07 2017-08-04 2017-09-03 2017-10-08 2017-11-12 2018-11-12 superficies de pâturages Enhancement Based Selection Implementation

Consultant REF 42 / Réalisation des études Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-10 2017-05-31 2017-07-14 2017-08-13 2017-09-17 2018-03-16 géophysiques Enhancement Implementation Selection

REF 44 / Réalisation des études Natural Resource Management Quality And Cost- Pending IDA / 56500 Post Open - National 0.00 2017-05-04 2017-05-25 2017-07-08 2017-08-05 2017-09-04 2017-10-09 2017-11-13 2018-11-13 techniques Enhancement Based Selection Implementation

REF 45 / Contrôle -surveillance Consultant Pending des travaux et équipements IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-04-25 2017-05-16 2017-06-29 2017-07-29 2017-09-02 2018-03-01 Implementation d'abreuvement Selection

Consultant REF 46 / Contrôle des travaux Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-18 2017-06-08 2017-07-22 2017-08-21 2017-09-25 2018-03-24 dans la zone mali NORD- EST Enhancement Implementation Selection

Consultant REF 63 / Mise en place dun Pending IDA / 56500 Animal Health Improvement Post Qualification Open - National 0.00 2017-05-02 2017-05-23 2017-07-06 2017-08-05 2017-09-09 2018-03-08 fonds de roulement vaccins Implementation Selection

Consultant REF 73 / Etudes d'identification Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 des travaux daménagement Enhancement Implementation Selection

Consultant REF 74 / Aménagement dans Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 la zone Centre du Mali Enhancement Implementation Selection

REF 75 / Aménagement et Consultant Natural Resource Management Pending gestion durable des IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 Enhancement Implementation bourgoutières Selection

REF 76 / Aménagement et gestion durable des Consultant Natural Resource Management Pending bourgoutières dans les régions IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 Enhancement Implementation de Tombouctou et de Gao Selection (régions du Nord-Mali)

Page 11 Consultant REF 78 / Réalisation des pare- Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-06-22 2017-07-13 2017-08-26 2017-09-25 2017-10-30 2018-04-28 feu de sécurisation Enhancement Implementation Selection

Consultant REF 80 / Mise en place dun Pending IDA / 56500 Animal Health Improvement Post Qualification Open - National 0.00 2017-04-17 2017-05-08 2017-06-21 2017-07-21 2017-08-25 2018-02-21 fonds de roulement vaccins Implementation Selection

NE-PRAPS-NE-7774-CS-CQS / Recrutement d'un bureau d'étude Consultant pour étude, conception et suivi Pending IDA / 56510 Animal Health Improvement Post Qualification Open - National 0.00 2017-03-22 2017-04-12 2017-05-26 2017-06-25 2017-07-30 2019-01-21 de travaux de construction de la Implementation Selection DGSV et Réhabilitation bureau UCP

NE-PRAPS-NE-7779-CS-CQS / Recrutement d'un bureau Consultant d'études pour etude,conception Pending IDA / 56510 Animal Health Improvement Post Qualification Open - National 0.00 2017-02-21 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2018-12-23 et contrôle des 15 postes Implementation Selection départementaux et des 10 postes communauxfrontaliers*

NE-PRAPS-NE-7702-CS-CQS / Consultant Convention de prestation avec un Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 0.00 2017-04-02 2017-04-23 2017-06-06 2017-07-06 2017-08-10 2018-08-05 Bureau pour organisation des Enhancement Implementation Selection usagers de parcours

53 / Recrutemnt d'un bureau Consultant d'étude pour Appui aux initiatives Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 communautaires à travers les Enhancement Implementation Selection CEP

58 / Identification, accords sociaux, géo référence et Consultant Project Management and Pending préparation des DAO pour les IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Institutional Support Implementation travaux de balisage en 2018 des Selection couloirs de passage

65 / Convention de prestation Consultant Project Management and Pending avec un bureau pour organisation IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Institutional Support Implementation des usagers de parcours Selection

66 / Multiples Conventions avec les opérateurs privés pour l'organisation des usagers de parcours(ingénerie sociale, Consultant Pending aménagements pastoraux et IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation hydraulique pastorale ds les 7 Selection régions avec une vingtaine d' ONG au niveau de Vingt sept zones

68 / Recrutement d'un consultant firme pour Consultant Pending l'Elaboration d'un document IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation d'evaluation d'une activité en Selection situation de crises pastorales

80 / Recrutement d'un bureau Consultant d'étude pour étude, conception et Project Management and Under IDA / 56510 Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 suivi et contôle de batiment du Institutional Support Implementation Selection Projet

84 / Recrutement des ONG/OPEL pour le démarrage Consultant Pending du processus des accords partis IDA / 56510 Market Access Facilitation Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation pour la construction/réhabilitation Selection des marchés

85 / Recrutement d'un bureau d'études pour etude,conception Consultant Pending et contrôle des 15 postes IDA / 56510 Animal Health Improvement Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation départementaux et des 10 Selection postes communauxfrontaliers*

Consultant 86 / Etude sur l'institution de Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 SVPP Implementation Selection

91 / Recrutement dun bureau detude pour Etudes de Consultant Pending faisabilité, préparation DAO, suivi IDA / 56520 Market Access Facilitation Post Qualification Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Implementation et contrôle des quatorze centres Selection de collecte de lait

97 / recrutement dun bureau d'études pour la réalisation des etudes techniques et elaboration Quality And Cost- Pending IDA / 56510 Market Access Facilitation Post Open - National 0.00 2017-09-29 2017-10-20 2017-12-03 2017-12-31 2018-01-30 2018-03-06 2018-04-10 2019-04-10 des DAO relatifs a la Based Selection Implementation construction/rehabilitation des 29 marchés à bétail

NE-PRAPS-NE-30657-CS-LCS / Recrutement d'un bureau d'étude pour etudes,suivi et contrôle des Project Management and Pending travaux de Réhabilitation du IDA / 56510 Post Least Cost Selection Open - National 0.00 2017-09-30 2017-10-21 2017-12-04 2018-01-01 2018-01-31 2018-03-07 2018-04-11 2018-10-08 Institutional Support Implementation batiment de la DGPIA et les locaux devant abriter les antennes régionales du PRAPS

REF 47 / Recrutement de consultant chargé des études Consultant Pending techniques pour la réalisation IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-05-19 2017-06-09 2017-07-23 2017-08-22 2017-09-26 2018-03-25 Implementation des Travaux dans la zone DELTA Selection CENTRAL

ML-PRAPS-ML-31460-CS-CQS / RECRUTEMENT D'UNE ONG POUR LA CONDUITE DES Consultant Project Management and Pending ACTIVITÉS DE SAUVEGARDES IDA / 56500 Post Qualification Open - National 0.00 2017-10-25 2017-11-15 2017-12-29 2018-01-28 2018-03-04 2018-08-31 Institutional Support Implementation SOCIALES AUTOUR DES Selection INFRASTRUCTURES DU PRAPS

ML-PRAPS-ML-33294-CS-CQS Consultant / Recrutement de consultant pour Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2017-05-28 2017-06-18 2017-08-01 2017-08-31 2017-10-05 2018-04-03 la réalisation des Travaux de Enhancement Implementation Selection sécurisation

18-C/PRAPS / Recrutement d'un opérateur en alphabétisation Consultant pour la formation des membres IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 Canceled 2017-11-13 2017-10-02 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 des OP de la région de la Boucle Selection du Mouhoun

17-C/PRAPS / Recrutement d'un Consultant opérateur en alphabétisation Under IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2017-11-13 2017-10-02 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 pour la formation des membres Implementation Selection des OP de la région de l'Est

16-C/PRAPS / Recrutement d'un Consultant opérateur en alphabétisation Pending IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2017-11-13 2017-11-27 2017-12-25 2018-01-08 2018-02-21 2018-03-23 pour la formation des membres Implementation Selection des OP de la région du Nord

03-C/MOD1 / Suivi-contrôle des travaux de construction de 5 Consultant Under postes vétérinaires et 30 parcs IDA / 56490 Animal Health Improvement Post Qualification Open - National 0.00 2017-12-02 2018-01-15 2017-12-16 2018-01-20 2018-02-10 2018-03-17 2018-08-14 Implementation de vaccination dans les 6 régions Selection du PRAPS-BF

04-C/MOD1 / Maîtrise d'Suvre travaux de réalisation de 111 Consultant Natural Resource Management Under forages pastoraux solaires et IDA / 56490 Post Qualification Open - National 0.00 2017-12-29 2018-01-15 2018-01-19 2018-03-04 2018-04-03 2018-05-08 2018-10-05 Enhancement Implementation manuels dans les 6 régions du Selection PRAPS

06-C/MOD1 / Etude/suivi 15 Pending marchés et 10 aires d'abattage à IDA / 56490 Market Access Facilitation Post Least Cost Selection Open - National 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-01 2018-08-31 2018-10-05 2018-11-09 2019-04-08 Implementation construire et à réhabiliter

Consultant 02-C/MOD1 / Etude/suivi 30 Natural Resource Management Under IDA / 56490 Post Qualification Open - National 0.00 2018-09-21 2017-12-27 2018-10-12 2018-01-30 2018-11-25 2018-12-25 2019-01-29 2019-07-28 boulis et5 mares Enhancement Implementation Selection

08-C/MOD1 / Etude/suivi Quality And Cost- Under UTL/CCL à construire et IDA / 56490 Market Access Facilitation Post Open - National 0.00 2018-08-21 2017-05-29 2018-09-11 2018-10-25 2018-11-22 2017-10-06 2018-12-22 2017-10-06 2019-01-26 2017-10-06 2019-03-02 2019-07-30 Based Selection Implementation réhabiliter

10-C/MOD1 / Etudes environnementales et sociales Quality And Cost- Pending IDA / 56490 Animal Health Improvement Post Open - National 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-22 2018-12-22 2019-01-26 2019-03-02 2019-06-30 UTL/CCL à construire et à Based Selection Implementation réhabiliter

01-C/MOD1 / Etude Consultant Natural Resource Management Pending environnemental et sociale 30 IDA / 56490 Post Qualification Open - National 0.00 2018-08-21 2018-09-11 2018-10-25 2018-11-24 2018-12-29 2019-05-28 Enhancement Implementation boulis et 5 mares Selection

Page 12 41-C/MOD1 / Etudes environnementales et sociales 15 Consultant marchés à bétail et 10 aires Pending IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-03-20 d'abattage à construire et Implementation Selection réhabiliter dans les régions d'intervention du PRAPS-BF

42-C/MOD1 / Etude environnementales et sociales 9 Quality And Cost- Pending cabinets vétérinaires privés à IDA / 56490 Animal Health Improvement Post Open - National 0.00 2018-07-17 2018-08-07 2018-09-20 2018-10-18 2018-11-17 2018-12-22 2019-01-26 2019-07-25 Based Selection Implementation construire dans les régions d'intervention du PRAPS-BF

43-C/MOD1 / Etudes/suivi 9 cabinets vétérinaires privés à Quality And Cost- Pending IDA / 56490 Animal Health Improvement Post Open - National 0.00 2018-05-14 2018-05-28 2018-07-02 2018-07-16 2018-07-30 2018-08-18 2018-09-22 2019-03-21 construire dans les régions Based Selection Implementation d'intervention du PRAPS-BF

PRAPS-SN-09-PI / Sélection de consultant pour le développement Consultant de modules sur les crises IDA / 56520 Pastoral Crisis Management Post Qualification Open - National 0.00 Canceled 2016-12-07 2016-12-07 2017-02-04 2017-03-10 2017-04-10 2017-03-30 2017-05-31 2017-08-29 pastorales (SIGEL) et formation Selection des utilisateurs

C11 MR PRAPS 2017 / Recrutement d'un prestataire de Consultant service (3) pour l'animation Natural Resource Management Pending IDA / D0660 Post Qualification Open - National 0.00 2017-04-15 2017-04-25 2017-05-25 2017-06-04 2017-06-19 2017-09-17 pastorale des UEP 5 & 6 partie Enhancement Implementation Selection Gorgol, Tagant, partie Brakna, Trarza, et Inchiri).

PRAPS-SN-02-PI-2018 / Sélection d'un consultant responsable du processus de Natural Resource Management Fixed Budget suivi évaluation participatif de la IDA / 56520 Post Open - National 0.00 Under Review 2018-03-06 2018-04-26 2018-03-27 2018-05-10 2018-06-07 2018-07-07 2018-08-11 2018-09-15 2019-09-15 Enhancement Selection mise en Suvre des plans de gestion et organisation des ateliers d'évaluation

21-C/PRAPS / Evaluation des Consultant performances du PRAPS et de la Project Management and IDA / 56490 Post Qualification Open - National 115,350.27 Signed 2017-01-27 2017-01-30 2017-02-17 2017-04-02 2017-03-27 2017-05-02 2017-04-19 2017-06-22 2017-06-01 2017-08-03 responsable de la formulation du Institutional Support Selection PADEL-B

Project Management and Quality And Cost- Pending 35-C/PRAPS / Auditeur externe IDA / 56490 Post Open - National 0.00 2019-04-15 2019-05-06 2019-06-10 2019-06-24 2019-07-15 2019-08-19 2019-10-02 2022-10-01 Institutional Support Based Selection Implementation

Consultant MOF-REF-2 / Réalisation film Project Management and IDA / 56490 Post Qualification Open - National 16,304.33 Signed 2016-06-09 2016-09-28 2016-06-30 2016-08-13 2017-02-28 2016-09-12 2017-02-28 2016-10-17 2017-03-13 2017-04-15 documentaire et spots Institutional Support Selection

MR-PRAPS-MR -45322-CS- QCBS / Suivi des travaux de Quality And Cost- Pending construction de 73 parcs de IDA / D0660 Animal Health Improvement Post Open - National 0.00 2018-02-15 2018-03-08 2018-04-21 2018-05-19 2018-06-18 2018-07-23 2018-08-27 2018-11-25 Based Selection Implementation vaccination dans plusieurs localités du pays

MR-PRAPS-MR -45329-CS- QCBS / Suivi des travaux de Quality And Cost- Pending construction de 10 aires d IDA / D0660 Market Access Facilitation Post Open - National 0.00 2018-06-15 2018-07-06 2018-08-19 2018-09-16 2018-10-16 2018-11-20 2018-12-25 2019-06-23 Based Selection Implementation abattage améliorées dans plusieurs wilayas

MR-PRAPS-MR -45331-CS- QCBS / Suivi des travaux de Quality And Cost- Pending IDA / D0660 Market Access Facilitation Post Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-16 2018-09-15 2018-10-20 2018-11-24 2019-07-22 construction de 7 marchés dans Based Selection Implementation plusieurs wilayas

BF-PRAPS-BF-45594-CS-CQS / Opérateur en alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP dans la Selection région des Cascades

BF-PRAPS-BF-45599-CS-CQS / Opérateur en alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP de la Selection région des Hauts Bassins

BF-PRAPS-BF-45604-CS-CQS / Opérateur en Alphabétisation Consultant Pending (Association/ONG) pour la IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-06-11 2018-07-16 2018-09-14 Implementation formation des OP et IP de la Selection région du Sahel

MOF-REF-11 / Animal Health Improvement ONG/Association pour réaliser Pastoral Crisis Management Consultant l'ingénierie sociale du PRAPS IDA / 56490 Natural Resource Management Post Qualification Open - National 90,058.24 Signed 2016-08-02 2016-07-28 2016-08-23 2016-10-06 2016-11-30 2016-11-05 2017-03-14 2017-01-03 2017-04-14 2017-07-02 dans l'antenne de Fada Enhancement Selection N'Gourma (Région de l'Est) Market Access Facilitation

MOF-REF-12 / Animal Health Improvement ONG/Association pour réaliser Pastoral Crisis Management Consultant l'ingénierie sociale du PRAPS IDA / 56490 Natural Resource Management Post Qualification Open - National 108,397.02 Signed 2016-08-02 2016-09-15 2016-08-23 2016-10-06 2016-11-30 2016-11-05 2017-03-10 2017-01-03 2017-04-12 2017-07-02 dans l'antenne de Dori (régions Enhancement Selection du Sahel et du Nord) Market Access Facilitation

MOF-REF-13 / ONG/association Animal Health Improvement pour l'ingénierie sociale du Pastoral Crisis Management Consultant PRAPS-BF dans l'antenne de IDA / 56490 Natural Resource Management Post Qualification Open - National 137,316.37 Signed 2016-08-02 2016-08-01 2016-08-23 2016-10-06 2016-11-30 2016-11-05 2017-03-15 2017-01-03 2017-04-11 2017-07-02 Bobo-Dioulasso (régions des Enhancement Selection Hauts-Bassins, de la Boucle du Market Access Facilitation Mouhoun et des Cascades)

32-C/MOD1 / Etudes Quality And Cost- environnementales et sociales 9 IDA / 56490 Animal Health Improvement Post Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-08-24 Based Selection cabinets vétérinaires

09-C/MOD1 / Etudes/suivi 9 Quality And Cost- cabinets vétérinaires à IDA / 56490 Animal Health Improvement Post Open - National 0.00 Canceled 2018-10-15 2018-11-05 2018-12-19 2019-01-16 2019-02-15 2019-03-22 2019-04-26 2019-08-24 Based Selection construction

BF-PRAPS-BF-45926-CS-CQS / Consultant Project Management and Pending Suivi-contrôle de la construction IDA / 56490 Post Qualification Open - National 0.00 2017-06-26 2017-07-17 2017-08-14 2017-08-28 2017-10-02 2018-09-27 Institutional Support Implementation du siège du PRAPS-BF Selection

BF-PRAPS-BF-46011-CS-CQS / Consultant Plan d'aménagement et de Natural Resource Management Under IDA / 56490 Post Qualification Open - National 0.00 2018-03-30 2018-04-13 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2018-10-06 gestion (PAG) de la zone Enhancement Implementation Selection pastorale de Barani (48 924 ha)

BF-PRAPS-BF-46012-CS-CQS / Plan d'aménagement et de Consultant Natural Resource Management Under gestion (PAG) de la zone IDA / 56490 Post Qualification Open - National 0.00 2018-03-30 2018-04-13 2018-04-20 2018-06-03 2018-07-03 2018-08-07 2018-10-06 Enhancement Implementation pastorale de Sondré Est (16 459 Selection ha)

ML-PRAPS-ML-46328-CS-CQS / Réalisation d'une étude pour Consultant l'évaluation des superficies et de Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2019-03-06 la qualité des pâturages dans les Implementation Selection zones du Sahel Occidental, du Delta Central et du Mali Nord-Est

ML-PRAPS-ML-46378-CS-CQS / Recrutement d'une ONG pour l'Appui au renforcement de Consultant capacité des membres des Pending IDA / 56500 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-03-20 organisations pastorales sur la Implementation Selection vie associative, l'exploitation et la maintenance des infrastructures pastorales

ML-PRAPS-ML-46542-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux Consultant Natural Resource Management Pending d'aménagement de 4110 IDA / 56500 Post Qualification Open - National 0.00 2018-08-14 2018-09-04 2018-10-18 2018-11-17 2018-12-22 2019-06-20 Enhancement Implementation hectares de bourgoutières dans Selection les Régions de Ségou, Mopti, Tombouctou et Gao

ML-PRAPS-ML-46560-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux 300 Consultant Natural Resource Management Pending km de pare- feu autour des IDA / 56500 Post Qualification Open - National 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Enhancement Implementation zones de pâturages dans les Selection cercles de Bankass, Douentza et Youwarou (région de Mopti)

ML-PRAPS-ML-46561-CS-CQS / Recrutement d'une ONG pour l'Organisation des travaux 330 Consultant km de pare- feu autour des Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 zones de pâturages dans les Enhancement Implementation Selection cercles de Gao, Ansongo (région de Gao) et Niono (région de Ségou)

Page 13 ML-PRAPS-ML-47112-CS-CQS Consultant Natural Resource Management Pending / Etude géophysique IDA / 56500 Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2019-02-27 Enhancement Implementation d'implantation de 23 forages Selection

ML-PRAPS-ML-46757-CS-CQS Consultant Natural Resource Management Pending / Etude géophysique IDA / 56500 Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2019-02-27 Enhancement Implementation d'implantation de 23 forages Selection

BF-CILSS-46764-CS-CQS / Consultant Etude sur l'utilisation de Under IDA / D0640 Pastoral Crisis Management Post Qualification Open - International 0.00 2018-03-08 2018-02-16 2018-03-29 2018-05-12 2018-05-26 2018-06-16 2018-10-14 l'approche proxy calorique avec Implementation Selection les produits de l'élevage

ML-PRAPS-ML-46972-CS-CQS Consultant / Etudes complémentaires de la Natural Resource Management Pending IDA / 56500 Post Qualification Open - National 0.00 2018-05-22 2018-06-12 2018-07-26 2018-08-25 2018-09-29 2019-03-28 Stratégie Nationale d'hydraulique Enhancement Implementation Selection Pastorale

ML-PRAPS-ML-46974-CS-CQS / Surveillance des travaux pour Consultant Pending les infrastructures marchandes et IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-29 2018-06-19 2018-08-02 2018-09-01 2018-10-06 2019-04-04 Implementation des magasins d'aliments bétail Selection dans la zone du Mali Nord Est

ML-PRAPS-ML-47095-CS-CQS Consultant / Appui à l'élaboration des plans Pending IDA / 56500 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-04-18 2018-05-09 2018-06-22 2018-07-22 2018-08-26 2019-02-22 de contingence communaux par Implementation Selection un bureau

Consultant REF 41 / Contrôle -surveillance Pending IDA / 56500 Market Access Facilitation Post Qualification Open - National 0.00 2017-03-16 2017-04-06 2017-05-20 2017-06-19 2017-07-24 2018-01-20 des travaux Implementation Selection

MR-PRAPS-MR -48817-CS- Consultant CQS / Assistance Technique Pending IDA / D0660 Animal Health Improvement Post Qualification Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-07-29 2018-08-23 2018-10-07 pour opérationnalisation du Implementation Selection dispositif de la composante 1

MR-PRAPS-MR -48818-CS- CQS / Assistance technique Consultant Pending pour la rédaction d'un manuel de IDA / D0660 Animal Health Improvement Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-27 2018-08-31 2018-10-15 Implementation procédures de la réglementation Selection existante

MR-PRAPS-MR -48825-CS- Consultant CQS / Recrutement d'un Pending IDA / D0660 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-21 2018-06-11 2018-07-25 2018-08-04 2018-08-24 2018-09-23 assistant technique pour Implementation Selection l'opérationnalisation de la FNE

MR-PRAPS-MR -48831-CS- Consultant CQS / Recrutement d'un Pending IDA / D0660 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-04-23 2018-05-14 2018-06-27 2018-07-07 2018-07-27 2018-08-26 consultant pour la finalisation et Implementation Selection la mise sur pied du SI

MR-PRAPS-MR -48840-CS- Consultant CQS / Bureau d'études pour Project Management and Pending IDA / D0660 Post Qualification Open - National 0.00 2018-05-15 2018-05-30 2018-07-13 2018-07-23 2018-08-23 2018-09-22 former le personnel du ME en Institutional Support Implementation Selection bureautique et informatique

MR-PRAPS-MR -48841-CS- CQS / Screening et Evaluation Consultant Project Management and Pending impact environnementale et IDA / D0660 Post Qualification Open - National 0.00 2018-05-15 2018-05-30 2018-07-13 2018-07-23 2018-08-12 2018-09-26 Institutional Support Implementation social pour 73 parcs de Selection vaccination. .

MR-PRAPS-MR -48842-CS- CQS / Evaluation impact Consultant Project Management and Pending environnemental pour fonçage IDA / D0660 Post Qualification Open - National 0.00 2018-04-20 2018-05-11 2018-06-24 2018-07-24 2018-08-28 2018-09-27 Institutional Support Implementation de 18 forages (TDRs et NIES) et Selection 11 puits.

MR-PRAPS-MR -48844-CS- Consultant CQS / Evaluation Project Management and Pending IDA / D0660 Post Qualification Open - National 0.00 2018-05-07 2018-05-28 2018-07-11 2018-07-26 2018-08-15 2018-09-14 environnementale de 7 marchés Institutional Support Implementation Selection à bétail et 2 aires de repos

MR-PRAPS-MR -48965-CS- Consultant CQS / Evaluation impact Project Management and Pending IDA / D0660 Post Qualification Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-07-29 2018-08-18 2018-09-17 environnementale pour fonçage Institutional Support Implementation Selection de 12 forages (TDRs et NIES)

Consultant 40-C/PRAPS / Etude sur les IDA / 56490 Animal Health Improvement Post Qualification Open - National 0.00 Canceled 2017-03-31 2017-04-14 2017-05-05 2017-05-12 2017-06-16 2017-07-16 mandats sanitaires Selection

PRAPS-SN-10-2018 / Selection Consultant Natural Resource Management Pending d'un cabinet pour les services IDA / 56520 Post Qualification Open - National 0.00 2017-08-21 2017-09-14 2017-10-23 2018-01-17 2018-02-28 2018-08-31 Enhancement Implementation d'evaluation d'impact OSB Selection

BF-CILSS-BF-52674-CS-QBS / Consultant pour l'Organisation Project Management and Quality Based IDA / D0640 Post Open - International 0.00 Canceled 2018-03-20 2018-03-15 2018-04-10 2018-05-09 2018-06-06 2018-06-21 2018-07-06 2018-08-10 2019-06-06 scientifique et technique des Institutional Support Selection

ETP-3 sur la santé animale

MR-PRAPS-MR -48969-CS- CQS / Evaluation Consultant Project Management and Pending environnementale et sociale de IDA / D0660 Post Qualification Open - National 0.00 2018-04-20 2018-05-11 2018-06-24 2018-07-04 2018-07-24 2018-08-23 Institutional Support Implementation 10 aires d'abattage et 5 mini Selection laiteries.

C13 MR PRAPS 2017 / Recrutement d'un opérateur Consultant d'Ingénierie sociale pour Pending IDA / D0660 Market Access Facilitation Post Qualification Open - National 0.00 2018-03-23 2018-04-02 2018-04-27 2018-05-07 2018-05-27 2018-08-25 l'accompagnement des 2 centres Implementation Selection de collecte de lait et des 5 mini laiteries

PRAPS-MR-1C / Suivi des travaux de construction de 3 Pending IDA / D0660 Market Access Facilitation Post Least Cost Selection Open - National 0.00 2017-08-10 2017-08-31 2017-10-14 2017-11-11 2017-12-11 2018-01-15 2018-02-19 2018-08-18 marchés à bétail et de 3 aires de Implementation repos

PRAPS-MR-2C / Suivi des travaux de construction et de Pending IDA / D0660 Animal Health Improvement Post Least Cost Selection Open - National 0.00 2017-09-15 2017-10-06 2017-11-19 2017-12-17 2018-01-16 2018-02-20 2018-03-27 2018-09-23 réhabilitation de postes de santé Implementation animale

PRAPS-MR-3C / Assistance technique internationale pour Natural Resource Management Quality And Cost- Pending IDA / D0660 Prior Open - International 0.00 2016-08-12 2016-09-02 2016-10-16 2016-11-13 2016-12-13 2017-01-17 2017-02-21 2018-02-21 appui à la mise en Suvre de la Enhancement Based Selection Implementation composante 2

PRAPS-MR-6C / Recrutement d'un prestataire de service (1) Consultant Natural Resource Management Pending pour l'animation pastorale des IDA / D0660 Post Qualification Open - National 0.00 2017-04-05 2017-04-26 2017-06-09 2017-07-09 2017-08-13 2018-02-09 Enhancement Implementation UEP 1 & 2 (partie du Hodh El Selection Gharbi, Hodh Echargui)

TD-PRAPS-TD-50597-CS-QCBS / Recrutement d'un ingénieur Quality And Cost- Pending conseil pour la supervision et IDA / D0650 Market Access Facilitation Prior Open - National 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-16 2018-08-20 2018-09-24 2019-09-24 Based Selection Implementation contrôle des infrastructures pastorales

NE-PRAPS-NE-54836-CS-CQS Consultant / Etude d'impacts Pending IDA / 56510 Pastoral Crisis Management Post Qualification Open - National 0.00 2018-04-10 2018-05-01 2018-06-14 2018-07-14 2018-08-18 2019-02-14 environnementaux et sociaux sur Implementation Selection 300 km de couloirs de passage

NE-PRAPS-NE-54840-CS-INDV Consultant / Balisage des couloirs de Natural Resource Management Pending IDA / 56510 Post Qualification Open - National 0.00 2018-04-01 2018-04-22 2018-06-05 2018-07-05 2018-08-09 2019-02-05 passage (identification, Enhancement Implementation Selection piquetage, marquage)

BF-CILSS-BF-57370-CS-CQS / Consultant Consultant organisation Pending IDA / D0640 Animal Health Improvement Post Qualification Open - International 0.00 2018-04-11 2018-05-02 2018-05-31 2018-06-15 2018-07-07 2018-08-06 scientifique et technique ETP-3 Implementation Selection sur la santé animale

TD-PRAPS-TD-58319-CS-CQS / Consultant Etude de viabilité économique Pending IDA / D0650 Animal Health Improvement Post Qualification Open - National 0.00 2018-05-25 2018-06-15 2018-07-29 2018-08-28 2018-10-02 2019-03-31 des pharmacies et services Implementation Selection privés de proximité

BF-PRAPS-BF-60079-CS-CQS / Recrutement d'un bureau pour Consultant Pending suivi-contrôle 15 marchés à IDA / 56490 Market Access Facilitation Post Qualification Open - National 0.00 2018-05-15 2018-06-05 2018-07-19 2018-08-18 2018-09-22 2019-02-19 Implementation bétail et étude + suivi-contrôle 10 Selection aires d'abattage.

05-C/MOD1 / Suivi-contrôle Consultant travaux de réhabilitation/ Pending IDA / 56490 Animal Health Improvement Post Qualification Open - National 0.00 2018-06-04 2018-06-25 2018-08-08 2018-09-07 2018-10-12 2019-03-11 construction de 18 postes Implementation Selection vétérinaires

Page 14 11-C/MOD2 / Recrutement d'un cabinet ou bureau d´études pour le contrôle des travaux de balisage de 1014 km de pistes a Natural Resource Management Quality And Cost- Pending IDA / 56490 Post Open - National 0.00 2018-08-22 2018-09-12 2018-10-26 2018-11-23 2018-12-23 2019-01-27 2019-03-03 2019-07-31 bétail, de 16 aires de pâture et Enhancement Based Selection Implementation de 6 aires de repos -régions de l'Est et du Sahel (antennes de Fada et de Dori)

PRAPS CF 01 / recrutement d un bureau d études pour les Project Management and Quality And Cost- Pending évaluation environnementales d la IDA / D0660 Post Open - National 0.00 2018-06-21 2018-07-12 2018-08-25 2018-09-22 2018-10-22 2018-11-26 2018-12-31 2019-12-31 Institutional Support Based Selection Implementation deuxième phase des infrastructures

PRAPS CF 02 / recrutement d un bureau d études pour les Project Management and Quality And Cost- Pending évaluationS sociales de la IDA / D0660 Post Open - National 0.00 2018-07-04 2018-07-25 2018-09-07 2018-10-05 2018-11-04 2018-12-09 2019-01-13 2020-01-13 Institutional Support Based Selection Implementation deuxième phase des infrastructures

PRAPS-MR-5C / Suivi des Consultant travaux de construction en 2 lots Pending IDA / D0660 Animal Health Improvement Post Qualification Open - National 0.00 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2018-01-23 2018-07-22 de 27 parcs de vaccination dans Implementation Selection plusieurs willayas du pays

BF-CILSS-BF-62401-CS-CQS / Production d'un sketch de Consultant sensibilisation des routiers, des Pending IDA / D0640 Market Access Facilitation Post Qualification Open - International 0.00 2018-05-29 2018-06-19 2018-07-17 2018-07-31 2018-08-21 2018-09-20 transporteurs et commerçants de Implementation Selection bétail sur les formalités d'exportation du bétail

INDIVIDUAL CONSULTANTS