Council SKDC (HEHC) Paper No. 69/15 Housing & Environmental Hygiene Committee Report on Progress of Major Projects

As at 30 April 2015 Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 191WC Replacement and 111 Secretary for 8/2011 12/2015 Works comprise replacement Works for laying and rehabilitation Cat. A Rehabilitation of Development and rehabilitation of of water mains are in progress. Water Mains, Stage WSD approximate 26 km long Approximately 83% of the works 4 (Contract No. existing water mains in Sai are completed. 10/WSD/10) Kung District (Hiram’s Highway, Po Tung Road, Hong Kin Road and some sections of roads in villages) and in Tseung Kwan O District (Tsui Lam Road, Road North, Po Lam Road South, Wan Po Road, Road, New Clear Water Bay Road, Fei Ngo Shan Road and some sections of roads in villages).

- 1 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 191WC Replacement and 41 Secretary for 4/2012 12/2015 Works comprise replacement Works for laying of water mains are Cat. A Rehabilitation of Development and rehabilitation of in progress. Approximately 85% of Water Mains, Stage WSD approximate 5 km long existing the works are completed. 4 (Contract No. water mains in Sai Kung 10/WSD/11) District ( Road from Mei Yu Street to Tai Wan, Hiram’s Highway from Pak Wai to Che Keng Tuk Road, Po Tung Road near Man Nin Street, Yan Yee Road, Anderson Road near Clear Water Bay Road & Sai Sha Road).

- 2 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 191WC Replacement and 95 Secretary for 11/2013 2/2016 Works comprise replacement of Works for laying of water mains are Rehabilitation of Development approximate 36.7km long in progress. Approximately 82% of Cat. A Water Mains, Stage WSD existing water mains in Sai the works are completed. 4 (Contract No. Kung District (Ho Chung 5/WSD/13) Village, Sam Fai Tin, Hing Keng Shek, Pak Wai, Heung Chung, Kai Ham, Tin Liu, Wang Che, Kau Tsin Uk, Tai Lam Wu, Ngau Pui Wo, Luk Mei Tsuen, Ho Chung Road, Ma Yau Tong, Tseng Lan Shue, Siu To Yuen Village, Sam Long, Sun Tei Village, Sheung Sze Wan, Tai , Leung Fai Tin, Tai Au Mun, Tai Wan Tau, Chinese Permanent Cemetery, Man Sau Sun Tsuen, Tui Min Hoi, Che Keng Tuk, Wong Mo Ying, San Tin Hang, Wu Lei Tau, Tsak Yue Wu, Pak Tam Chung, Tsam Chuk Wan, Muk Yue Tau, Pak A, San Tsuen, Pik Shui Sun Tsuen, Tai Wong Kung, Po Toi O, Tai Miu Au, Tseung Kwan O Village, Pan Long Wan, Sheung Yeung, Ng Fai Tin, Wo Tong Kong, O Mun Village, Hung Uk, Chan Uk Village, Yu Uk Village, O Pui Village, Mang Kung Uk, Heng Mei Village, Tai Chung Hau, Ma Lam Wat, Shek Hang and Tai Wan) - 3 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 336WF Integration of Ma On 272 Secretary for 1/2017 1/2022 The works are to connect the 2 Detailed design is in progress. Shan and Pak Kong fresh water supply systems of Upon completion of the detailed Cat. B Development (under (under Fresh Water Supply Ma On Shan and Pak Kong. design, WSD will consult the Systems WSD review) review) The main purpose of the works District Council. is to enhance the reliability of water supply in Sai Kung District.

Works include laying about 9 km long 600 mm diameter fresh water pipe in Sai Sha Road, Tai Mong Tsai Road and Hiram's Highway. (Approximate 5 km of the pipe is in Sai Kung District)

- 4 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 382DS Sewerage at Clear 359 Secretary for 1/2013 1/2017 The project aims to improve the Sewerage works at Tai Ping Village, Water Bay Road, Pik the hygiene environment of the Pak Kong, Tai Shui Tseng, Kap Pin Cat. A Shui Sun Tsuen and Environment rural areas and reduce Long, Sha Kok Mei, Clear Water w est of Sai Kung DSD pollution to the natural streams Bay Road and the area in the Town and receiving water bodies, in vicinity of Fei Ngo Shan Road order to safeguard the public (including Fei Ha Road, Fei Wan health. Road and Lam Ha Road) are in progress. About 28% of the works The project comprises mainly are completed. construction of sewerage works at 11 unsewered areas (including Kap Pin Long, Nam Shan, Pak Kong, San Uk, Sha Kok Mei, Tai Ping Village, Tai Shui Tseng, Wo Tong Kong, Lung Wo Tsuen, Pik Shui Sun Tsuen and the area in the vicinity of Fei Ngo Shan Road), Razor Hill Road, Clear Water Bay Road and Shun Chi Street. The sewerage works include construction of about 17.3 km of sewers and a sewage pumping station.

- 5 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 402DS Feasibility Study on 41 Secretary for 8/2014 8/2016 The feasibility study will The feasibility study commenced in Relocation of Sai the preliminarily assess the impacts end August 2014. Cat. A Kung Sewage Environment during the construction and Treatment Works to DSD operation stages of the Caverns relocation of Sai Kung Sewage Treatment Works, including relevant preliminary technical and impact assessments, preparation of outline design, and formulation of implementation strategies and programmes etc.

- 6 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 214DS Tseung Kwan O 211 Secretary for 5/2016 10/2020 The project aims at improving Preliminary design, public Sewerage for the the hygienic conditions of consultation, investigation works, Cat. B Villages Environment village environment and various impact assessments and DSD reducing pollution to natural gazettal for sewerage scheme have streams and receiving water been completed. Detailed design is bodies in order to safeguard in progress. the public health.

The project comprises mainly construction of village sewerage for 10 villages in Tseung Kwan O areas (including Shui Bin Village, Ming Oi New Village, Mau Wu Tsai Village, Tseung Kwan O Upper Old Village, Tseung Kwan O Village, Boon Kin Village, Hang Hau Old Village, Wo Tong Kong Village, Au Tau Village and Sun Tei Village). The project mainly includes construction of village sewers and a sewage pumping station.

- 7 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 362DS Sewerage for Ma 124 Secretary for 5/2016 10/2020 The project aims at improving Preliminary design, public Yau Tong Village, the the hygienic conditions of consultation, investigation works Cat. B Tseung Kwan O Environment village environment and and various impact assessments DSD reducing pollution level at have been completed. Detailed stream courses and water design and gazettal for sewerage bodies in order to enhance scheme is in progress and is being villagers’ health. The project arranged. scope mainly includes construction of village sewer for Ma Yau Tong Village.

393DS Rehabilitation of 100 Secretary for 3/2016 7/2020 The project includes the Preliminary design, investigation Trunk Sewers in the rehabilitation of a 200 m works and various impact Cat. B Kowloon, Shatin Environment submarine sewer across Sai assessments are in progress. and Sai Kung DSD Kung Hoi between and Tui Min Hoi. The rehabilitation works are to reduce the risk of sewage leakage and to enhance the operational reliability of the sewerage.

- 8 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 272DS Port Shelter 1,312 Secretary for Q3 2015 End 2020 The project aims at improving Parts of 272DS and 273DS had Sewerage Stage 2 the (First works (First works the hygienic conditions of been upgraded to Cat. A. The Cat. B Environment package) package) village environment and works commenced in Jan 2013. DSD reducing pollution level at Please refer to 382DS for details. stream courses and water The remainders of 272DS will be bodies in order to enhance implemented under 3 works villagers’ health. packages. The project comprises mainly The first works package comprises the construction of sewerage the construction of trunk sewers works at Wong Chuk Wan, Tai along Hiram’s Highways (from Chung Hau and Pak Sha Wan Marina Cove to Nam Wai). The areas (including Ta Ho Tun works will be entrusted to HyD for Sheung Wai, Ta Ho Tun Ha implementation with Project No. Wai, Kau Sai San Tsuen etc) 703TH and Ho Chung areas (including The second works package Pak Wai, Marina Cove, Luk comprises the construction of Mei Tsuen, Ho Chung, Ho sewerage works at Wong Chuk Wan Chung New Village, Nam Pin and Ho Chung areas. DSD will Wai, Wo Mei, Heung Chung, adopt alternative scheme, to replace Mok Tse Che and Nam Wai). the planned sewage pumping stations with package treatment plants at Ho Chung and Wo Mei for treating sewage collected from local areas. The third works package comprises the construction of sewerage works at Tai Chung Hau and Pak Sha Wan areas. Since trunk sewer will be laid along Hiram’s Highways (from Marina Cove to Hong Kin Road), the design and the programme of the sewerage works are under review.

- 9 - As at 30 April 2015

Estimated Responsible Commence- Completion Project No. & Project Title Cost Bureau / ment Date Date Project Scope / Remark Progress / Status Category ($M) Department (M/Y) (M/Y) 273DS Port Shelter 643 Secretary for 4/2016 4/2021 The project aims at improving Parts of 272DS and 273DS had Sewerage Stage 3 the the hygienic conditions of been upgraded to Cat. A. The Cat. B Environment village environment and works commenced in Jan 2013. DSD reducing pollution level at Please refer to 382DS for details. stream courses and water The remainders of 273DS comprise bodies in order to enhance the construction of sewerage works villagers’ health. at Tai Po Tsai, Po Toi O and Tseng The project comprises mainly Lan Shue areas. Detailed design construction of sewerage works and gazettal process is in progress. at Tai Po Tsai, Po Toi O and Regarding the sewerage works at Tseng Lan Shue areas Po Toi O, DSD is carrying out (including Tan Shan, Tseng Lan the environmental impact Shue, Siu To Yuen Village, Sam assessment (EIA) study. As coral Long, Pak Shek Wo, Pak Shek communities and Amphioxus were Wo San Tsuen, Pik Uk Au etc). identified in the ecological surveys under the EIA study, it is necessary to review the design of the proposed submarine outfall. The works are scheduled to commence in April 2016 for completion in April 2021. 226DS Sai Kung Sewage Under Secretary for Under Under The objective of upgrading is to DSD will review the need and Treatment Works review the review review cater for extension of sewerage scope of upgrading works for Sai Cat. B Upgrading Phase II Environment networks and future Kung Sewage Treatment Works DSD developments in Sai Kung. (SKSTW) based on the feasibility The scope and programme of study on relocation of SKSTW to upgrading would be formulated caverns (the feasibility study will by taking account of the be completed in 3rd quarter of sewerage works being planned. 2016), to match with the latest development and progress of 272DS (Port Shelter Sewerage Stage 2).

- 10 -