Bi-annual Environmental Monitoring Report

Bi annual Report June 2018

PAK: Flood Emergency Reconstruction and Resilience Project – Haveli, and Poonch Districts

Prepared by Climate Change Center for the Asian Development Bank

The Bi-annual Environmental Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of the ADB website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgements as to the legal or other status of any territory or area.

Bi-annual Environmental Monitoring Report

Project Number: No. 3264-PAK

July-December, 2017

Flood Emergency Reconstruction and Resilience Project (FERRP)

(ADB Loan No. 3264-PAK)

Prepared by: Climate Change Center

For: Asian Development Bank (ADB)

i

CONTENTS

Title Page i Table of Content ii List of Annexure iii List of Figures iv Abbreviations v

PART I INTRODUCTION

Construction activities of the project 1 Project Organization and Environmental Management Team 1 Relationship with the Contractor and the Engineer 1

PART II ENVIRONMENTAL MONITORING

Summary 4 Noise & Vibration 4 Surface & Ground Water 4 Air Quality 4 Flora & Fauna 4 Campsites 5 Top soil erosion 5 Cultural Heritage Sites 5 Safety Provisions 5

PART III ENVIRONMENTAL MANAGEMENT

Review of Rapid Environmental Assessment (REAs) 7 Campsite guidelines 7 EMP Compliance Checklist 7 Conclusion and Recommendations 8 Challenges while making Biannual Environmental Monitoring Report 9

ii Biannual Environmental Monitoring Report

LIST OF ANNEXURE

I. Construction activities of the project II. Campsite Guidelines III. - Road- “Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level” & Pictorial view of the locations Rawlakot – Hajira Road-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level IV. Hajira – Tararkhel Road-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level V. Azad Pattan Rawlakot Road Package-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level VI. Rawlakot - Hajira Road Package -Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level VII. Hajira – Abasspur Road -Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level VIII. Tatta Pani – Hajira Road -Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level IX. Kotli – Tatta Pani Road -Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level X. Lasdana - Mahmood Gali Road-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level XI. Tarar Khel- Hajira Road-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level XII. Khaigalla - Ali Sojal- Chura Gali Road-Environment and Safety Monitoring and Safeguard Compliances -Impacts and Mitigation Measures and Risk Level XIII. Thaliar Bridge Kotli - Tatta Pani Road-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level XIV. Repair work of Kotli- Sahuratta Samror Road-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level XV. AK-CW-ll Bridges-Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level XVI. Environmental Management and Monitoring Plan

iii Biannual Environmental Monitoring Report

LIST OF FIGURES

Figure.1: Project Organogram

Figure. 2: Civil works in Progress (Azad Pattan- RWK road)

Figure. 3: Non- compliance of PPEs (Azad Pattan- RWK road)

Figure. 4: Water Sprinkling (Azad Pattan- RWK road)

Figure. 5: No extra construction waste on road side (Azad Pattan- RWK road)

Figure. 6: No covering of construction material (Asphalt Plant Hajira)

Figure. 7: Asphalt Plant (Hajira), no major non-compliance issue

Figure. 8: Meeting with Contractor (Azad Pattan- RWK Road)

Figure. 9: Supervision of G-3 ES of environmental safeguard of construction activities (Azad Pattan- RWK Road)

Figure. 10: Stones on road (Hajira- Trarkhal Road)

Figure. 11: Water sprinkling (Hajira- Trarkhal Road)

Figure. 12: Meeting with Local Community (RWK-Hajira- Road)

Figure. 13: Works in Progress (Hajira- Trarkhal Road)

Figure. 14: No endangered or economical vegetation (RWK- Hajira Road)

Figure. 15: Asphalt laying (RWK- Hajira Road)

Figure. 16: No endangered or economical vegetation (Asphalt Plant Azadpattan – RWK road)

Figure. 17: Meeting with Local Community (RWK-Hajira- Road)

Figure. 18: Meeting with local community (Asphalt Plant Azadpattan – RWK road)

iv Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

ABBREVIATIONS

ADB Asian Development Bank CCC Climate Change Center EMMP Environmental Management Monitoring Plan ES Environmental Specialist FERRP Flood Emergency Reconstruction and Resilience Project GoAJ&K Government of Azad Jammu and Kashmir HSE Health Safety and Environment IA Implementing Agency PD Project Director PIU Project Implementation Unit PMC Project Management Consultants REA Rapid Environmental Assessment

v Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Part I Introduction

1. The unprecedented flood of 2014, as a result of torrential rains of monsoon, caused significant damages to the infrastructure (roads, bridges etc.) of three districts of Azad Jammu & Kashmir (AJ&K) i.e. Haveli, Kotli and Poonch. The people had lost access to and utilization of various infrastructures, and had suffered from damages to their housing and commercial structures, loss of crops, businesses and other livelihood resources.

2. The Asian Development Bank (ADB) under Loan No. 3264-PAK with total loan package of Pak Rs. 6641.00 Million is supporting Government of Azad Jammu & Kashmir (GoAJ&K) for reconstruction and rehabilitation of damaged roads and bridges networks through Flood Emergency Reconstruction and Resilience Project (FERRP).

Construction activities of the project

3. Construction activities of the project were divided into two categories, i.e. small works and major works. Name of each Road Package, length of the road, contractor’s names and physical progress achieved during the reported period are detailed in Annex-I.

Project Organization and Environmental Management Team

4. Overall responsibility for Environmental Management and Monitoring rests with the Project Implementation Unit (PIU), the implementing agency (IA), which is headed by a Project Director (PD). The PIU is supported by Environmental Specialist from Project Management Consultants (PMC) during implementation and monitoring of the Environmental Management and Monitoring Plan (EMMP). The contractors are responsible to ensure that all Project activities are in compliance with the EMMP.

5. Under the FERRP, it is mandatory to implement the environmental and social safeguard compliances. This is an essential part of project implementation and all the stakeholders involved in project implementation must consider environmental and social safeguard compliances.

6. Detailed monitoring visits have been undertaken by the PMC team during the reporting period accompanied by senior and junior engineers, supervisory staff engineers, and contractors and their workers. The objectives of the visits were to identify the impacts due to construction works being implemented, review the implementation of Environmental Management, and oversee the monitoring of the recommended mitigation measures described in the EMMP, extent of compliances of environmental and social safeguards and to find out any glaring discrepancies in environmental and social safeguards by the contractors and supervisory staff.

7. Environmental Specialist (ES) of PMC has conducted monitoring of environment and safety safeguards compliances of the project sites of FERRP (Table 1) during the months of July-December, 2017.

8. Communication and Works Department (C&W) is the Executing Agency whereas overall planning, monitoring and implementation of reconstruction activities are the complete responsibility of Project Implementation Unit (PIU). In addition to this, Project Management Consultants (PMC) is responsible for the execution of EMMP and PIU is responsible for EMMP compliance monitoring. The organizational chart of the project is shown in Figure-1.

Relationship with the Contractor and the Engineer

9. The relationship of contractor and engineer with the community was reported

1 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Table 1: List of Project site roads visited by ES of PMC

Sr. Package # Month of Visit Names of Road Packages # Rawlakot- Hajira Road, AK-CW-6

Azad Pattan- Rawlakot Road AK-CW-7 1 July 2017 Trarkhel- Hajira Road AK-CW-8 Tattapani- Hajira Road AK-CW-1

Hajira- Road AK-CW-2

2 August- Abbaspur-Mehmood Gali Road AK-CW-3 September 2017 Mehmood Gali- kahuta Road AK-CW-4 AzadPattan- Rawlakot Road AK-CW-7 Rawlakot- Hajira Road, AK-CW-6 Trarkhel- Hajira Road AK-CW-8

Lasdana- Mehmood Gali road AK-CW-5

KhaigalaAli Sojal Chura Gali road AK-CW-9 3 October- Tattapani-Kotli Road AK-CW-10 December 2017 Thlair Bridge (Kotli) AK-CW-11 Kotli Sahuratta Samror road AK-CW-10 AK-CW-II Bridges AK-CW-II

.

2 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Figure 1

.

3 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Part II Environmental Monitoring

Summary

10. The environmental monitoring was carried out through visual observations to monitor the compliance of EMMP agreed by the contractors under the assigned contracts. During the monitoring period ES carried out the observations regarding dust emissions, disposal of spoil & solid waste material of existing packages, disposal of spoil & solid waste unused materials, loss of access for roadside residents, safety precautions for workers and community, vehicles and equipment exhaust, vegetation and wildlife loss, construction near protected areas and impact on biodiversity, blasting hard rock, drainage line clogging, sourcing fill material and disposing of excess material, disposal of construction debris, loss of agricultural area/cropped area, damage or disturbance to public utility, archeological sites and existing public and community structures. The complete detail of Environment and Safety Monitoring and Safeguard Compliances, Impacts and Mitigation Measures and Risk Level is given in the tables (Annex-III-XVI)

Noise and Vibration 11. It was reported in the monitoring reports shared by PIU that there was no serious impact to people, livestock and wildlife because all the construction activities were generally done manually by labor. No vibration was observed. The machinery was being used only for few hours of the day by the contractors. The Significance Level/risk level was reported as Low.

Surface and Ground Water

12. No contamination to surface and ground water was reported as the contractor and his labor took strict care to damage water line. The Significance Level/risk level was reported as Low

Air Quality

13. It was reported that due to rocky terrain of roads this impact was not created due to construction activities. There was no creation of dust pollution. However, the instructions were given to the contractor and his staff to take actions as per EMMP.

14. During the monitoring period the risk level for vehicle exhaust was reported as low for all road packages.

Flora and Fauna

15. It was reported that as there is no agriculture or cropped areas available along the roads and at some places a number of un-economic shrubs have been damaged during excavation. Hence, the project construction activities have no significant impact on

4 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Biodiversity of the area. It was also reported that there were some wild animals but these were not adversely impacted due to construction activities along the RoW of packages.

Campsites

16. It was reported that all the workers and supervising staff were wearing PPEs. Passing by communities were guided properly through cautions with colored tapes and ropes. Training material and orientation already done by ES of PMC.

17. The overall environment and safety measures were reported satisfactory. The PMC senior and junior staff was vigilant in monitoring the environment and safety safeguards and took appropriate measures on site. But it was reported that there was no first aid kit on sites visited during the month of July for providing any first aid to the labor, passing people along the road and the supervising staff. While on other sites there were Health Safety & Environment (HSE) measures compliance at the camp sites by the contactor and passing traffic and people. There were first-aid kits on labor camps and at the work sites through adequate pre-cautionary measures. The accumulative risk level for the reporting period was informed as low.

Top Soil Erosion

18. It was reported that at roadsides which were monitored during the month of July, the vegetation was cleared and large size stones were being removed from the sites which increased vulnerability of soil erosion but on the other hand, the sites monitored during Aug- Dec, 2017 the texture of the roadsides was observed as rocky and there was no creation of soil so no soil erosion issue was noticed at those sites.

Cultural Heritage Sites

19. It was reported that only few mosques and graveyards were seen near the villages and were located away from the alignment of construction works. As it is a project for the reconstruction of the damaged roads and mostly all the construction activities are in progress on existing roads.

Safety Provisions

20. It was reported that there were no serious adverse impacts on the biotic life but due to narrowness of Kotli-Tatta Pani road and placing of construction material along the road, sometime during the night hours traffic get jams which creates problems for the people. This is a serious social problem.

21. It was reported during the month of July that Asphalt Plant is Located at Maidan (Proposed Location 1) Azad Pattan – Rawlakot Road. Near this location there is a middle level school. During interview with the Head of school it was informed that the proposed site of Asphalt Plant is owned by the school and used as volleyball playground. The contractor plans to use this plot for dumping material, labor huts, office and other infra-structure. The extracurricular activities will be stopped for the students. Moreover, the noise and dust level will increase and pollute the atmosphere. All these activities may hamper the health and education of students. The socio-economic aspects expressed by the head of the school are serious and needs to be given a sincere and serious thought.

5 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

22. There was no other major conflict with the community reported. Amiable liaison has been maintained with local community.

.

6 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Part III Environmental Management

Review of Rapid Environmental Assessment (REAs)

23. During the reporting period, REAs screening checklists for following roads were provided to Climate Change Center; Mehmood Gali-Kahuta road, Kotli-Tattapani road, Azadpattan-Rawalakot road, Rawalakot-Hajjira road and Tararkhel-Hajira road. Based on the REA checklist information, rehabilitation works were proposed within the available RoW of the existing roads. Thus, the sub-projects have not any significant adverse impacts that are irreversible, diverse or unprecedented and therefore classified as category B sub- projects in accordance with ADB safeguard policy statement 2009.

Campsite Guidelines

24. Campsite guidelines were suggested in EMMP for management of campsites during the pre-construction and construction stages .These guidelines are mainly recommendation, mitigation measures to address all the social and environmental concerns of the campsites.

EMP Compliance Checklist

25. Though it is mentioned in the monitoring reports provided by PIU that ES prepares the checklist for collection of information about the compliances of environmental safeguards of packages of FERRP but it is not annexed with the shared reports.

7 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Conclusions and Recommendations

During the reporting period 11 major packages, 1 small package and AK-CW-II Bridges were monitored by the environmental specialist. At all the project sites there are several number of construction activities in progress. The analysis of all the activities revealed that there was no serious environmental safeguard non-compliance. No cultural heritage sites/ wetlands lie in RoW of project alignment were reported. The construction activities have no significant impact on flora and fauna. No damage to the agricultural land due to borrow pits or top soil erosion is reported. Moreover, there was no disturbance on the habitat of wild animals. The impacts during the construction phase are temporary and will end with the completion of the construction activities. However, in order to avoid impact of construction activities on environment and social aspects, proper mitigation measures have been proposed. It is advised that repeated monitoring of compliances of safeguards be carried out to make the project environment friendly and socially acceptable.

Some recommendations are as follow;

i. The work in progress at all sites should not have any significant adverse environmental impact

ii. Use of PPEs by contractor site staff was poor. Awareness Sessions regarding Health Safety & Environment (HSE) should be conducted at least on weekly basis

iii. Tool box meetings should be arranged on daily basis

iv. Emergency contact numbers should also be displayed at regular intervals in local language

v. Proper segregation and marking of materials should be done in store

vi. Traffic should be managed properly at all project sites. Contractors must take road safety a priority and should place safety signs (Safety cautions, Safety cones, Safety tapes etc) where required vii. Oil tanks should be fenced and marked properly and proper care must be taken while fuel transfer to vehicles viii. Fire safety should be ensured and fire points must be installed at all sites. In addition, trainings should be conducted regarding proper usage of fire extinguishers

ix. Housekeeping should be maintained in an environmental friendly way

x. No surface water or ground water contamination was reported due to oil spillages, solid waste dumping or asphalt laying during the reporting period. However, machinery should be maintained properly to avoid oil-spill especially at Thalair Bridge site as the construction site is National Park

xi. Any type of waste should not be dumped into Poonch River or nearby places and Fishing must be prohibited at the site xii. Any type of activity involving the exploitation of Poonch River must be avoided xiii. No noise and vibration related complaints from public or workers were registered. Construction activities situated close to populated areas should be limited to daylight hours only to minimize the impact of noise. Prayer timings and school timings should be observed close to the mosques and schools along the roads during construction activities. 8 Biannual Environmental Monitoring Report

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK

Challenges while development of biannual report

i. Checklist used as a tool for data collection by ES was not annexed with the environmental monitoring reports provided to CCC

ii. Environmental Monitoring Reports were not provided timely to Climate Change Center (CCC)

.

9 Biannual Environmental Monitoring Report

ANNEXURE

Annex-I

Flood Emergency Reconstruction and Resilience Project (FERRP), ADB Loan No. 3264-PAK Summary of Construction Contracts for Major Works December, 2017

# Contract Road Length Contractor Contract Commencement Completion Physical Last Remarks (Package#) (KM) Cost Date Date Achieved Reported (MPKR) Progress By Progress % By %

Major Works

1 AK-CW6 RWK-Hajira 22 ZKA-IKAN 647.643 5.5.2017 30.11.2018 50 50 Delayed hiring of Road (JV) design and project management consultant, rebidding due to higher rates

2 AK-CW7 Azadpattan- 20 ZKA 614.558 18.1.2017 30.11.2018 NA NA Delayed hiring of RWK road design and project management consultant, Negotiating for rate decrease

3 AK-CW8 Tararkhel-hajira 16.568 PTA 336.583 19.12.2016 January,201 58 58 Delayed hiring of road 8 design and project management consultant.

4 AK-CW2 Hajira-abbaspur 29 RA-DC (JV) 566.894 5.5.2017 30.11.2018 19 19 Delayed hiring of road design and project management consultant, rebidding due to higher rates

5 AK-CW3 Abbaspur- 16 PTA 377.324 19.12.2016 30.11.2018 37 37 Delayed hiring of mahmoodgali design and road project management consultant.

6 AK- CW 4 Mahmoodgali- NA PTA 328.88 8.12.2017 30.11.2018 NA NA Due to district kahuta road boundary issues matter is on hold

7 AK- CW 5 Lasdanna - 19.45 PTA 260.344 19.12.2016 30.11.2018 53 53 Delayed hiring of mahmoodgali design and road project management consultant

8 AK- CW 9 Khaigalla - Ali 15 PTA 158.212 19.12.2016 30.11.2018 45 45 Delayed hiring of Sojal- Chura design and Gali Road project management consultant

9 AK- CW Tattapani-kotli 26.246 PTA 192.21 19.12.2016 30.11.2018 NA NA Delayed hiring of 10 road (kotli- design and sarhota project samrore road) management consultant

10 AK- CW Thalair bridge NA ZK-IKAN 348.788 21.12.2017 30.11.2018 NA NA 11 (Kotli) (JV)

11 AK- CW 1 Tattapani- 19 PTA 349.536 19.12.2016 30.11.2018 53 53 Delayed hiring of Hajira Road design and project management consultant

Annex-II

Guidelines for Camp Site

Site Selection

. Camps will be located atleast at a distance of 500 m from the nearest local settlement.

. Cutting of trees shall be avoided and removal of vegetation shall be minimized

. Water and sanitary facilities (atleast pit latrines) shall be provided for employees. Proper sanitation facilities should be provided including soakage pits

. Adequate signage, lightening and barriers at construction and camp sites should be provided to avoid any kind of accident

. Labor must be equipped with PPEs and contractor must ensure their proper usage

. The camp areas should have adequate natural drainage in order to facilitate the flow of treated effluents

Camp Site Management

. Contractor shall provide copy of the Environmental Management and Monitoring Plan (EMMP) at the concerned sites. Copy of the EMMP should be available at camp site all the times

. Contractor will nominate and authorize the Individual to implement EMMP measures

. EMMP recommendations should be clearly understood by the concerned implementing individual(s), contractors and other staff

. Contractor shall comply with the safety precautions for constructions

. Contractor shall provide PPEs to construction workforce and monitor if they are appropriately used.

. The labor should be provided with the adequate potable water at site

. Wood shall not be used as fuel or for any other activity

. Contractor shall provide LPG cylinders for cooking and heating purposes

. Contractor shall provide first aid kit at camp site and nominate/train individual (s) to address any emergency

. Contractor shall maintain proper Environmental Monitoring Record as mentioned in the Project Administration Manual (PAM) and submit monthly progress reports to PIU

. Maintain good liaison with local communities

. Contractor shall maintain Grievances Log, where all community complaints are registered and follow up actions should be recorded.

Workers Training:

. Contractor shall provide trainings to effectively implement project specific EMMP

. Training of construction workforce on HSE and use of PPEs

. Workforce training regarding storage and handling of material and chemicals that can be hazardous and cause soil contamination and/or explosion

. Contractor shall prohibit hiring of child labor and forced labor

. Contractor shall encourage hiring of Local labor

Waste Management:

. Contractor will be responsible for treatment of wastewater from camp toilets

. Solid waste generated during construction at campsite will be properly collected at source, treated and safely disposed of only in selected waste disposal sites

. Fuel and oil storage areas should be located away from any watercourses

. Contractor will be responsible to implement proper dust and noise abatement procedures at camp site

July, 2017

ANNEX-III Azad Pattan Rawlakot Road

Table 1: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Orientation for Training material and orientation Execution - 2.1 contractors and already done by Environment - PMC workers Specialist of PMC. Monitoring-PIU This impact has not created due to construction activities. The site of structures is rocky and there is no significant dusty soil Execution - 2.2 Dust Emissions creating dust. Low PMC However, the instructions were Monitoring-PIU given to the PMC staff, contractor and his staff to take actions as per EMP. Disposal of spoil Execution - & solid waste 2.3 Complied Low PMC material of Monitoring-PIU existing road Compliance in progress Disposal of spoil Such instructions were issued to the Execution - 2.4 & solid waste contractor’s representative on site Low PMC unused materials and ARE for strict compliance of Monitoring-PIU safeguards. Complied. Loss of access for Execution - 2.5 roadside The contractors have taken care by Low PMC residents giving alternate access along Monitoring-PIU roadside to facilitate the residents. Complied.

Safety All the workers and supervising precautions staff were wearing hats, jackets, and Execution - 2.6 for workers and other safety equipments/articles. Low PMC community Monitoring-PIU safety Passing by communities were guided properly through cautions with colored tapes and ropes Vehicles and Execution - 2.7 equipment Complied Low PMC exhaust Monitoring-PIU

July, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Complied.

At places some un-economic shrubs have been damaged while excavation.

No compensatory plantation of grasses was required as they will Execution - Vegetation and 2.8 naturally re-grow after rainfall in Low PMC wildlife loss proper season. Monitoring-PIU

The monitoring team revealed that there were some wildlife species but these were not adversely impacted due to construction activities along the road of this package. Complied. On both sides of road mature trees of coniferous trees and other Construction species and scattered shrubs are near protected Execution - grown and declared as protected 2.9 areas and Low PMC areas under Forest Act. impact on Monitoring-PIU

biodiversity The project construction activities have no impact on biodiversity of the area. Complied.

Execution - Blasting hard No blasting of hard rocks was being 2.10 Moderate PMC rock done. Hence, strict mitigation Monitoring-PIU measures are being undertaken by the contractors. Partially complied.

No drainage lines were damaged due to project activities. Execution - Drainage line 2.11 Low PMC clogging For future it was warned that this Monitoring-PIU impact of clogging of the drainage lines be taken care by the contractor and monitored by the PMC staff. 2.12 Sourcing fill Complied. Low Execution -

July, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level material The excess material was being used PMC and disposing of in hand filling alongwith new fill Monitoring-PIU excess material material. It was explained to supervising staff and contractors workers to take appropriate mitigation measures in such cases Complied. Disposal of Execution - 2.13 construction The extra debris material was being Low PMC Debris used in hand filling along with soil Monitoring-PIU and properly compacted. Not applicable.

Loss of Execution - There was no need to comply as no 2.14 agricultural area/ Very low PMC agriculture or cropped areas were cropped area Monitoring-PIU available along the roads. Hence, no loss. Complied. At some places telephone, gas and water lines were observed exposed Damage or and open during digging operation Execution - 2.15 disturbance but these lines were not damaged Low PMC to public utility and created no disturbance to water Monitoring-PIU line. The contractor and his labour took strict care to damage water line. Complied Only few mosques and graveyards Execution - Archeological 2.16 were seen near the villages but Low PMC sites were located away from the Monitoring-PIU alignment of construction works. Complied.

The road being main road from Kashmir to of Punjab Existing Public Province is very busy. There are Execution - 2.17 and community small to medium market places, Low PMC structures houses, shops, small tea shops, Monitoring-PIU bridges and other community huts. Due to strict monitoring by the contractor and strict supervision of PMC staff the above community

July, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level structures were not damaged.

There were sufficient cautions on site through relevant cautions particularly at site where there were landslides. Partially complied.

The construction works were generally done by medium to heavy machinery and manually by labor. Some water tankers, tractor trollies, passing buses and wagons and mixing machines were used for which proper mitigation measure Execution - Noise and 2.18 were being made. Low PMC Vibration Due to above vehicles and Monitoring-PIU machines there was noise and vibration specially during the work hours. The machinery was being used only during day hours by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, air Execution - quality, noise, 2.19 Road safety was being Complied Low PMC road safety and Monitoring-PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution -

2.20 Others PMC Environment specialist prepared Monitoring-PIU the checklist for collection of information about the compliances of environmental safeguards of packages of FERRP.

July, 2017

Photographic Views of works in progress

Fig. 2: Civil works in Progress (Azad Pattan- Fig. 3: Non- compliance of PPEs (Azad Pattan- RWK road) RWK road)

Fig. 4: Water Sprinkling (Azad Pattan- RWK road) Fig. 5: No extra construction waste on road side (Azad Pattan- RWK road)

Fig. 7: Asphalt Plant (Hajira), no major non compliance

issue Fig. 6: No covering of construction material (Asphalt Plant Hajira)

July, 2017

Fig. 8: Meeting with Contractor (Azad Pattan- RWK

Road)

Fig. 9: Supervision of G-3 ES of environmental safeguard of construction activities (Azad Pattan- RWK Road)

.

August-September, 2017

Annex-IV

Rawlakot – Hajira Road

Table 2: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Orientation for Training material and orientation Execution - 2.1 contractors and already done by Environment PMC workers Specialist of PMC. Monitoring-PIU Due to rocky terrain of road this impact is not created due to construction activities. Execution - 2.2 Dust Emissions There is no creation of dust Low PMC pollution. However, the instructions Monitoring-PIU were given to the contractor and his staff to take actions as per EMP. Disposal of spoil Execution - & solid waste 2.3 Partially Complied Low PMC material of Monitoring-PIU existing road Compliance in progress Disposal of spoil Such instructions were issued to the Execution - 2.4 & solid waste contractor’s representative on site Low PMC unused materials and ARE for strict compliance of Monitoring-PIU safeguards. Complied. Loss of access for Execution - 2.5 roadside The contractors have taken care by Low PMC residents giving alternate access along Monitoring-PIU roadside to facilitate the residents. Partially Complied.

Most of the workers and supervising Safety staff were not wearing hats, jackets, precautions Execution - and other safety equipments/articles. Inadequate 2.6 for workers and PMC Compliance community Monitoring-PIU Passing by communities were also safety not guided properly through cautions with colored tapes and ropes Vehicles and Execution - 2.7 equipment Complied Low PMC exhaust Monitoring-PIU

August-September, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Partially Complied.

At places some un-economic shrubs have been damaged while alignment and excavation of road.

No compensatory plantation of Execution - Vegetation and 2.8 grasses was planned. Moderate PMC wildlife loss Monitoring-PIU The monitoring team revealed that there were small wildlife species specially birds but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees of owned by the private people and by Construction the department and scattered shrubs Execution - near protected are grown and declared as protected 2.9 Low PMC areas and impact areas under Forest Act. Monitoring-PIU on biodiversity The project construction activities have no serious impact on biodiversity of the area. Complied.

Execution - Blasting hard No blasting of hard rocks was being 2.10 Moderate PMC rock done. Hence, strict mitigation Monitoring-PIU measures are being undertaken by the contractors. Partially complied.

No drainage lines were damaged Execution - Drainage line along of the road. 2.11 Low PMC clogging Monitoring-PIU But for future it was warned to take strict measures of clogging the drainage lines. Sourcing fill Partially Complied. Execution - material The excess material was being used 2.12 Moderate PMC and disposing of in hand filling alongwith new fill Monitoring-PIU excess material material.

August-September, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level It was explained to supervising staff and contractors workers to take appropriate mitigation measures in such cases Complied. Disposal of Execution - 2.13 construction The extra debris material was being Low PMC Debris used in hand filling along with soil Monitoring-PIU and properly compacted. Not applicable.

Loss of Execution - There was no need to comply as no 2.14 agricultural area/ Very low PMC agriculture or cropped areas were cropped area Monitoring-PIU available along the roads. Hence, no loss. Complied. At places water lines were observed exposed and open during digging Damage or Execution - operation but these lines were not 2.15 disturbance Low PMC damaged and created no disturbance to public utility Monitoring-PIU to water line. The contractor and his labour took strict care to damage water line. Complied Only few mosques and graveyards Execution - Archeological 2.16 were seen near the villages and were Low PMC sites located away from the alignment of Monitoring-PIU construction works. Partially Complied.

Houses, shops, small tea shops and Existing Public other community huts/buildings Execution - 2.17 and community such as schools, shops etc. were there Moderate PMC structures but were not damaged. Monitoring-PIU

There were no sufficient cautions on site at the work sites. Partially complied.

Execution - Noise and The construction works were 2.18 Moderate PMC Vibration generally done manually by labor. Monitoring-PIU Some water tankers, tractor trollies, passing buses and wagons and

August-September, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level mixing machines were used for which proper mitigation measure of less use was being made.

The construction machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, air Complied. Road safety measures Execution - quality, noise, 2.19 were required to be implemented as Low PMC road safety and caution to people and transport. Monitoring-PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution -

2.20 Others PMC Environment specialist prepared the Monitoring-PIU checklist for collection of information about the compliances of environmental safeguards of packages of FERRP.

August-September, 2017

Annex-V

Hajira – Tararkhel Road

Table 3: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Orientation for Training material and orientation Execution - 2.1 contractors and already done by Environment PMC workers Specialist of PMC. Monitoring-PIU This impact is not created due to construction activities. Execution - No dust was created. However, the 2.2 Dust Emissions Low PMC instructions were given to the Monitoring-PIU contractor and his staff take actions as per EMP. Disposal of spoil Execution - & solid waste 2.3 Complied Low PMC material of Monitoring-PIU existing road Compliance in progress Disposal of spoil Such instructions were issued to the Execution - 2.4 & solid waste contractor’s representative on site Moderate PMC unused materials and ARE for strict compliance of Monitoring-PIU safeguards. Complied. Loss of access for Execution - 2.5 roadside The contractors have taken care by Low PMC residents giving alternate access along Monitoring-PIU roadside to facilitate the residents. Complied.

Most of the workers and Safety supervising staff were wearing precautions Execution - hats, jackets, and other safety 2.6 for workers and Low PMC equipments/articles. community Monitoring-PIU

safety Passing by communities were guided properly through cautions with colored tapes and ropes Vehicles and Execution - 2.7 equipment Complied Low PMC exhaust Monitoring-PIU 2.8 Vegetation and Complied. Low Execution -

August-September, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level wildlife loss PMC At places some un-economic shrubs Monitoring-PIU have been damaged while excavation.

No compensatory plantation of grasses was required as they will naturally re-grow after rainfall in proper season.

The monitoring team revealed that there were some wildlife species but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees of coniferous tree species and Construction broad-leaved trees and scattered near protected Execution - shrubs are grown and declared as 2.9 areas and Low PMC protected areas under Forest Act. impact on Monitoring-PIU

biodiversity The project construction activities have no impact on biodiversity of the area. Complied.

Execution - Blasting hard No blasting of hard rocks was being 2.10 Moderate PMC rock done. Hence, strict mitigation Monitoring-PIU measures are being undertaken by the contractors. Partially complied.

Execution - Drainage line No drainage lines were damaged. 2.11 Low PMC clogging Monitoring-PIU However, for future it was warned not to clog the drainage lines. Complied. Sourcing fill The excess material was being used Execution - material 2.12 in hand filling alongwith new fill Low PMC and disposing of material. Monitoring-PIU excess material It was explained to supervising

August-September, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level staff and contractors workers to take appropriate mitigation measures in such cases Partially Complied.

Disposal of Execution - The extra debris material was not 2.13 construction Moderate PMC being disposed off but being re- Debris Monitoring-PIU used in hand filling along with soil and properly compacted. Not applicable.

Loss of Execution - There was no need to comply as no 2.14 agricultural area/ Very low PMC agriculture or cropped areas were cropped area Monitoring-PIU available along the roads. Hence, no loss. Complied. At places water lines were observed exposed and open during digging Damage or Execution - operation but these lines were not 2.15 disturbance Low PMC damaged and created no to public utility Monitoring-PIU disturbance to water line. The contractor and his labour took strict care to damage water line. Complied Only few mosques and graveyards Execution - Archeological 2.16 were seen near the villages and Low PMC sites were located away from the Monitoring-PIU alignment of construction works. Complied.

Houses, shops, small tea shops and Existing Public other community huts/buildings Execution - 2.17 and community such as schools, shops etc. were not Low PMC structures damaged. Monitoring-PIU

There were sufficient cautions on site through. Partially complied.

Execution - Noise and The construction works were 2.18 Low PMC Vibration generally done manually by labor. Monitoring-PIU Some water tankers, tractor trollies, passing buses and wagons and

August-September, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level mixing machines were used for which proper mitigation measure of less use was being made.

Although the machinery was being used only during day time for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, air Execution - quality, noise, Mostly Complied but some safety 2.19 Moderate PMC road safety and measures were lacking. Monitoring-PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution -

2.20 Others PMC Environment specialist prepared Monitoring-PIU the checklist for collection of information about the compliances of environmental safeguards of packages of FERRP.

August-September, 2017

Pictorial Views of Location It was also noticed that at places the vegetation was cleared and large size stones were being removed from the site were makes the soil loose and increase vulnerability of soil erosion.

Fig. 10:Stones on road (Hajira- Trarkhal Road) Fig. 11:Water sprinkling (Hajira- Trarkhal Road)

Fig. 13: Works in Progress (Hajira- Trarkhal Road) Fig. 12:Meeting With Local Community (RWK- Hajira- Road)

August-September, 2017

Fig. 14:No endangered or economical Fig. 15:Asphalt laying (RWK- Hajira Road) vegetation (RWK- Hajira Road)

Fig. 16:No endangered or economical Fig. 17:Meeting With Local Community (RWK-Hajira- Road vegetation (Asphalt Plant Azadpattan – RWK road)

Fig. 18:Meeting with local community

(Asphalt Plant Azadpattan – RWK road)

.

October- December, 2017

Annex-VI

Azad Pattan Rawlakot Road Package Table 4 Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Orientation for Training material and orientation Execution - 2.1 contractors and already done by Environment PMC workers Specialist of PMC. Monitoring-PIU This impact is not created due to construction activities. The site of structures is rocky and Execution - 2.2 Dust Emissions is no creation of soil which creates Low PMC no dust. However, the instructions Monitoring-PIU were given to the contractor and his staff take actions as per EMP. Disposal of spoil Execution - 2.3 & solid waste Complied Low PMC material of Monitoring-PIU existing road Disposal of Compliance in progress spoil Such instructions were issued to Execution - 2.4 & solid waste the contractor’s representative on Low PMC unused site and ARE for strict compliance Monitoring-PIU materials of safeguards. Complied. Loss of access Execution - for 2.5 The contractors have taken care by Low PMC roadside giving alternate access along Monitoring-PIU residents roadside to facilitate the residents. Complied

All the workers and supervising Safety staff were wearing hats, jackets, precautions Execution - and other safety 2.6 for workers and Low PMC equipments/articles. community Monitoring-PIU

safety Passing by communities were guided properly through cautions with colored tapes and ropes Vehicles and Execution - 2.7 equipment Complied Low PMC exhaust Monitoring-PIU Complied There are no trees along the Execution - Vegetation and alignment of road construction. 2.8 Low PMC wildlife loss Hence, there is no any damage to Monitoring-PIU trees due to construction activities. At places some un-economic

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level shrubs have been damaged while excavation.

No compensatory plantation of grasses was required as they will naturally re-grow after rainfall in proper season. There are no adverse impacts to wildlife species due to construction activities along the roads of this package. Complied. On both sides of road some trees and scattered shrubs are grown and Construction declared as protected areas. near protected Execution - The project construction activities 2.9 areas and Low PMC have no impact on biodiversity of impact on Monitoring-PIU the area. biodiversity However, strict measures have been undertaken to protect biotic life. Complied. No blasting of hard rocks was Execution - Blasting hard 2.10 being done. Hence, strict Moderate PMC rock mitigation measures are being Monitoring-PIU undertaken by the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side 2.11 Low PMC clogging of the roads. Monitoring-PIU For future it was warned not to clog the drainage lines. Complied The excess material was being used in hand filling alongwith new fill material. Sourcing fill It was explained to supervising Execution - material 2.12 staff and contractors workers to Low PMC and disposing of take appropriate mitigation Monitoring-PIU excess material measures in such cases. Proper compaction of excess material specially excess soil and excess material was being taken. Complied

The extra debris material was Disposal of Execution - being used in hand filling along 2.13 construction Low PMC with soil and properly compacted. Debris Monitoring-PIU Due care was made for proper compaction of construction material and debris.

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Not applicable Loss of Execution - agricultural There was no need to comply as no 2.14 Very low PMC area/ agriculture or cropped areas were Monitoring-PIU cropped area available along the road. Hence, no loss. Complied At places water lines were observed exposed and open during Damage or Execution - digging operation but these lines 2.15 disturbance Low PMC were not damaged and created no to public utility Monitoring-PIU disturbance to water line. The contractor and his labor took strict care to damage water line. Complied Only few mosques and graveyards were seen near the villages and were located away from the Execution - Archeological alignment of construction works. 2.16 Low PMC sites The road being busy due to traffic Monitoring-PIU flow there were some mosques and shops at the bus stops only. There was no any archeological site. Complied. Houses, shops, small tea shops and Existing Public other community huts/buildings Execution - 2.17 and community such as schools, shops etc. were Low PMC structures not damaged. Monitoring-PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some heavy trucks were used for transporting construction materials, water tankers, tractor trollies, passing buses and wagons and Execution - Noise and mixing machines were used for 2.18 Low PMC Vibration which proper mitigation measure Monitoring-PIU of less use was being made. No vibration was observed. The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. There are three land slides along There are the road due to which there are almost regular 2.19 Landslides Moderate problems of traffic jams and flow arrangements of of water creating problems for the machinery and

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level traffic and people. pre-cautionary measures etc. There were first -aid kits on labor camps and There were HSE measures at the HSE Measures at the work sites 2.20 camp sites by the contactor and Low for labor force through passing traffic and people. adequate pre- cautionary measures.

October- December, 2017

Annex-VII

Rawlakot - Hajira Road Package

Table 5: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Orientation for Training material and orientation Execution - 2.1 contractors and already done by Environment PMC workers Specialist of PMC. Monitoring-PIU This impact is not created due to construction activities. The site of structures is rocky and Execution - 2.2 Dust Emissions is no creation of soil which creates Low PMC no dust. However, the instructions Monitoring-PIU were given to the contractor and his staff take actions as per EMP. Disposal of spoil Execution - 2.3 & solid waste Complied Low PMC material of Monitoring-PIU existing road Disposal of Compliance in progress spoil Such instructions were issued to Execution - 2.4 & solid waste the contractor’s representative on Low PMC unused site and ARE for strict compliance Monitoring-PIU materials of safeguards. Complied. Loss of access Execution - for 2.5 The contractors have taken care by Low PMC roadside giving alternate access along Monitoring-PIU residents roadside to facilitate the residents. Complied.

All the workers and supervising Safety staff were wearing hats, jackets, precautions Execution - and other safety 2.6 for workers and Moderate PMC equipments/articles. community Monitoring-PIU

safety Passing by communities were guided properly through cautions with colored tapes and ropes Vehicles and Execution - 2.7 equipment Complied Low PMC exhaust Monitoring-PIU Complied.

At places some un-economic Execution - Vegetation and 2.8 shrubs have been damaged while Low PMC wildlife loss excavation. Monitoring-PIU

No compensatory plantation of

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level grasses was required as they will naturally re-grow after rainfall in proper season.

The monitoring team revealed that there were some wildlife species but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of Fir and scattered shrubs are near protected Execution - grown and declared as protected 2.9 areas and Low PMC areas under Forest Act. impact on Monitoring-PIU The project construction activities biodiversity have no impact on biodiversity of the area. Complied. No blasting of hard rocks was Execution - Blasting hard 2.10 being done. Hence, strict Moderate PMC rock mitigation measures are being Monitoring-PIU undertaken by the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side 2.11 Low PMC clogging of the roads. Monitoring-PIU For future it was warned not to clog the drainage lines. Complied. The excess material was being Sourcing fill used in hand filling alongwith new Execution - material fill material. 2.12 Low PMC and disposing of It was explained to supervising Monitoring-PIU excess material staff and contractors workers to take appropriate mitigation measures in such cases Complied. Disposal of Execution - The extra debris material was 2.13 construction Low PMC being used in hand filling along Debris Monitoring-PIU with soil and properly compacted. Not applicable. Loss of There was no need to comply as no Execution - agricultural 2.14 agriculture or cropped areas were Very low PMC area/ available along the roads. Hence, Monitoring-PIU cropped area no loss. Complied. Damage or At places water lines were Execution - 2.15 disturbance observed exposed and open during Moderate PMC to public utility digging operation but these lines Monitoring-PIU were not damaged and created no

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level disturbance to water line. The contractor and his labour took strict care to damage water line. Complied Only few mosques and graveyards were seen near the villages and were located away from the Execution - Archeological 2.16 alignment of construction works. Low PMC sites There were some schools near the Monitoring-PIU road but there were necessary actions for safety and management by the school authorities. Complied. Houses, shops, small tea shops and Existing Public other community huts/buildings Execution - 2.17 and community such as schools, shops etc. were Low PMC structures not damaged. Monitoring-PIU There were sufficient cautions on site through cautions.. Partially complied.

The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and mixing machines were used Execution - Noise and 2.18 for which proper mitigation Low PMC Vibration measure of less use was being Monitoring-PIU made. The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, air quality, Execution - 2.19 noise, Complied Low PMC road safety and Monitoring-PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution - 2.20 Others Environment specialist prepared PMC the checklist for collection of Monitoring-PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017

Annex-VIII

Hajira – Abasspur Road

Table 6: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Orientation for Training material and orientation Execution - 2.1 contractors and already done by Environment PMC workers Specialist of PMC. Monitoring-PIU This impact is not created due to construction activities. The site of structures is rocky and Execution - 2.2 Dust Emissions is no creation of soil which creates Low PMC no dust. However, the instructions Monitoring-PIU were given to the contractor and his staff take actions as per EMP. Disposal of spoil Execution - 2.3 & solid waste Complied Low PMC material of Monitoring-PIU existing road Disposal of Compliance in progress spoil Such instructions were issued to Execution - 2.4 & solid waste the contractor’s representative on Low PMC unused site and ARE for strict compliance Monitoring-PIU materials of safeguards. Complied. Loss of access Execution - for 2.5 The contractors have taken care by Low PMC roadside giving alternate access along Monitoring-PIU residents roadside to facilitate the residents. Complied.

All the workers and supervising Safety staff were wearing hats, jackets, precautions Execution - and other safety 2.6 for workers and Low PMC equipments/articles. community Monitoring-PIU

safety Passing by communities were guided properly through cautions with colored tapes and ropes Vehicles and Execution - 2.7 equipment Complied Low PMC exhaust Monitoring-PIU Complied. At places some un-economic Execution - Vegetation and 2.8 shrubs have been damaged while Low PMC wildlife loss excavation. Monitoring-PIU No compensatory plantation of

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level grasses was required as they will naturally re-grow after rainfall in proper season. The monitoring team revealed that there were some wildlife species but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of Fir and scattered shrubs are near protected Execution - grown and declared as protected 2.9 areas and Low PMC areas under Forest Act. impact on Monitoring-PIU The project construction activities biodiversity have no impact on biodiversity of the area. Complied. No blasting of hard rocks was Execution - Blasting hard 2.10 being done. Hence, strict Moderate PMC rock mitigation measures are being Monitoring-PIU undertaken by the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side 2.11 Low PMC clogging of the roads. Monitoring-PIU For future it was warned not to clog the drainage lines. Complied. The excess material was being Sourcing fill used in hand filling alongwith new Execution - material fill material. 2.12 Low PMC and disposing of It was explained to supervising Monitoring-PIU excess material staff and contractors workers to take appropriate mitigation measures in such cases Complied. Disposal of Execution - 2.13 construction The extra debris material was Low PMC Debris being used in hand filling along Monitoring-PIU with soil and properly compacted. Not applicable. Loss of Execution - agricultural There was no need to comply as no 2.14 Low PMC area/ agriculture or cropped areas were Monitoring-PIU cropped area available along the roads. Hence, no loss. Complied partially. Damage or Execution - At places water lines were 2.15 disturbance Moderate PMC observed exposed and open during to public utility Monitoring-PIU digging operation but these lines

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level were not damaged and created no disturbance to water line. The contractor and his labour took strict care to damage water line. Complied Only few mosques and graveyards Execution - Archeological 2.16 were seen near the villages and Low PMC sites were located away from the Monitoring-PIU alignment of construction works. Complied. Houses, shops, small tea shops and Existing Public other community huts/buildings Execution - 2.17 and community such as schools, shops etc. were Low PMC structures not damaged. Monitoring-PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and mixing machines were used for which proper mitigation Execution - Noise and 2.18 measure of less use was being Low PMC Vibration made. Monitoring-PIU

The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, air quality, Execution - 2.19 noise, Complied Low PMC road safety and Monitoring-PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution - 2.20 Others Environment specialist prepared PMC the checklist for collection of Monitoring-PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017

Annex-IX

Tatta Pani – Hajira Road Table 7 Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and PMC 2.2 Dust Emissions is no creation of soil which creates Low Monitoring- no dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Moderate Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Complied. Loss of access Execution -

for PMC 2.5 The contractors have taken care by Low roadside Monitoring- giving alternate access along residents PIU roadside to facilitate the residents. Complied.

Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, PMC 2.6 for workers and and other safety Low Monitoring- community equipments/articles. PIU safety Passing by communities were guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. Low but At some sires some smaller suggested to Execution - vegetative cover was damaged. At plant Vegetation and PMC 2.8 places some un-economic shrubs compensatory wildlife loss Monitoring- have been damaged while plantation of PIU excavation. shrubs at No compensatory plantation of appropriate

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level grasses was required as they will places naturally re-grow after rainfall in proper season. The monitoring team revealed that there were some wildlife species but these were not adversely impacted due to construction activities along the roads of this package.

Complied No mature trees of were cut or damaged due to construction Construction machinery. Execution - near protected Scattered shrubs are grown but PMC 2.9 areas and Low there was no serious adverse impact Monitoring- impact on on biodiversity.. PIU biodiversity The project construction activities have no impact on biodiversity of the area. Complied Mitigation measures were taken Execution - during the blasting operation. Blasting hard PMC 2.10 No blasting of hard rocks was being Moderate rock Monitoring- done. Hence, strict mitigation PIU measures are being undertaken by the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side PMC 2.11 Low clogging of the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising Monitoring- excess material staff and contractors workers to PIU take appropriate mitigation measures in such cases Complied. Execution - Disposal of The extra debris material was being PMC 2.13 construction Low used in hand filling along with soil Monitoring- Debris and properly compacted. PIU Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, cropped area PIU no loss. 2.15 Damage or Complied. Low Execution -

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level disturbance At places water lines were observed PMC to public utility exposed and open during digging Monitoring- operation but these lines were not PIU damaged and created no disturbance to water line. The contractor and his labour took strict care to damage water line. Complied Execution - Only few mosques and graveyards Archeological PMC 2.16 were seen near the villages and Low sites Monitoring- were located away from the PIU alignment of construction works. Complied.

Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU

There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - mixing machines were used for Noise and PMC 2.18 which proper mitigation measure of Moderate Vibration Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution - PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017

Annex-X

Kotli – Tatta Pani Road Table 8: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and is PMC 2.2 Dust Emissions no creation of soil which creates no Low Monitoring- dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Complied. Loss of access Execution -

for PMC 2.5 The contractors have taken care by Moderate roadside Monitoring- giving alternate access along residents PIU roadside to facilitate the residents. Complied partially. Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, and PMC 2.6 for workers and other safety equipments/articles. Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. At places some un-economic shrubs Execution - have been damaged while Vegetation and PMC 2.8 excavation. Low wildlife loss Monitoring- No compensatory plantation of PIU grasses was required as they will naturally re-grow after rainfall in

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level proper season. The monitoring team revealed that there were some wildlife species but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road some grasses Construction and small vegetation and scattered Execution - near protected shrubs are grown and needs to be PMC 2.9 areas and Low protected. Monitoring- impact on The project construction activities PIU biodiversity have no impact on biodiversity of the area. Complied. Execution - Blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising staff Monitoring- excess material and contractors workers to take PIU appropriate mitigation measures in such cases Complied. Execution - Disposal of The extra debris material was being PMC 2.13 construction Low used in hand filling along with soil Monitoring- Debris and properly compacted. PIU Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, no cropped area PIU loss. Complied partially. At places water lines were observed exposed and open during digging Execution - Damage or operation but these lines were not PMC 2.15 disturbance Low damaged and created no Monitoring- to public utility disturbance to water line. PIU The contractor and his labour took strict care to damage water line.

October- December, 2017

Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Complied Execution - Only few mosques and graveyards Archeological PMC 2.16 were seen near the villages and Low sites Monitoring- were located away from the PIU alignment of construction works. Complied. Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - mixing machines were used for Noise and PMC 2.18 which proper mitigation measure of Low Vibration Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution - PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017 Annex-XI

Lasdana - Mahmood Gali Road

Table 10: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. The site of structures is rocky and is Execution - no creation of soil which do not PMC 2.2 Dust Emissions Low result creating dust. However, the Monitoring- instructions were given to the PIU contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Being Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Loss of access Complied. Execution - for The contractors have taken care by PMC 2.5 Low roadside giving alternate access along Monitoring- residents roadside to facilitate the residents. PIU Complied Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, and PMC 2.6 for workers and other safety equipments/articles. Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied There are no trees along the alignment of road construction. Execution - Hence, there is no any damage to Vegetation and PMC 2.8 trees due to construction activities. Low wildlife loss Monitoring- At places some un-economic shrubs PIU have been damaged while excavation. No compensatory plantation of

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level grasses was required as they will naturally re-grow after rainfall in proper season. There are no adverse impacts to wildlife species due to construction activities along the roads of this package. Complied On both sides of road some trees Construction and scattered shrubs are grown and Execution - near protected declared as protected areas. PMC 2.9 areas and The project construction activities Low Monitoring- impact on have no impact on biodiversity of PIU biodiversity the area. However, strict measures have been undertaken to protect biotic life. Complied. Execution - No blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied The excess material is being used in hand filling along with new fill material. Sourcing fill Execution - It was explained to supervising staff material PMC 2.12 and contractors workers to take Low and disposing of Monitoring- appropriate mitigation measures in excess material PIU such cases. Proper compaction of excess material specially excess soil and excess material was being taken. Complied The extra debris material was being Execution - Disposal of used in hand filling along with soil PMC 2.13 construction and properly compacted. Low Monitoring- Debris Due care was made for proper PIU compaction of construction material and debris. Not applicable Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the road. cropped area PIU Hence, no loss. Damage or Complied Execution - 2.15 Low disturbance At places water lines were observed PMC

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level to public utility exposed and open during digging Monitoring- operation but these lines were not PIU damaged and created no disturbance to water line. The contractor and his labor took strict care to damage water line. Complied Only few mosques and graveyards were seen near the villages and were located away from the Execution - Archeological alignment of construction works. PMC 2.16 Low sites The road being busy due to traffic Monitoring- flow there were some mosques and PIU shops at the bus stops only. There was no any archeological site. Complied. Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some heavy trucks were used for transporting construction materials, water tankers, tractor trollies, passing buses and wagons and Execution - Noise and mixing machines were used for PMC 2.18 Low Vibration which proper mitigation measure of Monitoring- less use was being made. PIU No vibration was observed. The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. There are There are three land slides along the almost regular road due to which there are arrangements 2.19 Landslides problems of traffic jams and flow of Moderate of machinery water creating problems for the and pre- traffic and people. cautionary measures etc. There were first -aid kits on There were HSE measures at the HSE Measures labor camps 2.20 camp sites by the contactor and Low for labor force and at the work passing traffic and people. sites through adequate pre-

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level cautionary measures.

October- December, 2017 Annex-XII

Tarar Khel- Hajira Road Table 11: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and is PMC 2.2 Dust Emissions no creation of soil which creates no Low Monitoring- dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Loss of access Complied. Execution - for The contractors have taken care by PMC 2.5 Low roadside giving alternate access along Monitoring- residents roadside to facilitate the residents. PIU Complied. Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, and PMC 2.6 for workers and other safety equipments/articles. Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. At places some un-economic shrubs have been damaged while excavation. Execution - No compensatory plantation of Vegetation and PMC 2.8 grasses was required as they will Low wildlife loss Monitoring- naturally re-grow after rainfall in PIU proper season. The monitoring team revealed that there were some wildlife species but these were not adversely

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of different tree species and Execution - near protected scattered shrubs are grown and PMC 2.9 areas and declared as protected areas under Low Monitoring- impact on Forest Act. PIU biodiversity The project construction activities have no impact on biodiversity of the area. Complied. Execution - No blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising staff Monitoring- excess material and contractors workers to take PIU appropriate mitigation measures in such cases Complied. Execution - Disposal of The extra debris material was being PMC 2.13 construction Low used in hand filling along with soil Monitoring- Debris and properly compacted. PIU Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, no cropped area PIU loss. Complied. At places water lines were observed exposed and open during digging Execution - Damage or operation but these lines were not PMC 2.15 disturbance Low damaged and created no Monitoring- to public utility disturbance to water line. PIU The contractor and his labour took strict care to damage water line. Complied Execution - Archeological Only few mosques and graveyards PMC 2.16 Low sites were seen near the villages and Monitoring- were located away from the PIU

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level alignment of construction works.

Complied. Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - mixing machines were used for Noise and PMC 2.18 which proper mitigation measure of Low Vibration Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of Execution - environment and safety measures. PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017

Annex-XIII

Khaigalla - Ali Sojal- Chura Gali Road Table 12: Environment and Safety Monitoring and Safeguard Compliances -Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and is PMC 2.2 Dust Emissions no creation of soil which creates no Low Monitoring- dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Loss of access Complied. Execution - for The contractors have taken care by PMC 2.5 Low roadside giving alternate access along Monitoring- residents roadside to facilitate the residents. PIU Complied. Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, and PMC 2.6 for workers and other safety equipments/articles. Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. At places some un-economic shrubs have been damaged while excavation. Execution - Vegetation and No compensatory plantation of PMC 2.8 Low wildlife loss grasses was required as they will Monitoring- naturally re-grow after rainfall in PIU proper season. The monitoring team revealed that there were some wildlife species

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of coniferous trees and scattered Execution - near protected shrubs are grown and declared as PMC 2.9 areas and Low protected areas under Forest Act. Monitoring- impact on The project construction activities PIU biodiversity have no impact on biodiversity of the area. Complied. Execution - No blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising staff Monitoring- excess material and contractors workers to take PIU appropriate mitigation measures in such cases Complied. Execution - Disposal of PMC 2.13 construction The extra debris material was being Low Monitoring- Debris used in hand filling along with soil PIU and properly compacted. Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, no cropped area PIU loss. Complied. At places water lines were observed exposed and open during digging Execution - Damage or operation but these lines were not PMC 2.15 disturbance Low damaged and created no Monitoring- to public utility disturbance to water line. PIU The contractor and his labour took strict care to damage water line. Complied Execution - Archeological 2.16 Only few mosques and graveyards Low PMC sites were seen near the villages and Monitoring-

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level were located away from the PIU alignment of construction works. Complied. Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - mixing machines were used for Noise and PMC 2.18 which proper mitigation measure of Low Vibration Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of environment and safety measures. Execution - PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017 Annex-XIV

Thaliar Bridge Kotli - Tatta Pani Road Table 13: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and is PMC 2.2 Dust Emissions no creation of soil which creates no Low Monitoring- dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Loss of access Complied. Execution - for The contractors have taken care by PMC 2.5 Low roadside giving alternate access along Monitoring- residents roadside to facilitate the residents. PIU Complied. Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, and PMC 2.6 for workers and other safety equipments/articles. Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. At places some un-economic shrubs have been damaged while excavation. Execution - No compensatory plantation of Vegetation and PMC 2.8 grasses was required as they will Low wildlife loss Monitoring- naturally re-grow after rainfall in PIU proper season.

The monitoring team revealed that there were some wildlife species

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of coniferous tree species of Execution - near protected different ages and scattered shrubs PMC 2.9 areas and are grown and declared as protected Low Monitoring- impact on areas under Forest Act. PIU biodiversity The project construction activities have no impact on biodiversity of the area. Complied. Execution - No blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising staff Monitoring- excess material and contractors workers to take PIU appropriate mitigation measures in such cases Complied. Execution - Disposal of The extra debris material was being PMC 2.13 construction Low used in hand filling along with soil Monitoring- Debris and properly compacted. PIU Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, no cropped area PIU loss. Complied. At places water lines were observed exposed and open during digging Execution - Damage or operation but these lines were not PMC 2.15 disturbance Low damaged and created no Monitoring- to public utility disturbance to water line. PIU The contractor and his labour took strict care to damage water line. Complied Execution - Archeological 2.16 Only few mosques and graveyards Low PMC sites were seen near the villages and Monitoring-

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level were located away from the PIU alignment of construction works. Complied. Houses, shops, small tea shops and other community huts/buildings Execution - Existing Public such as schools, shops etc. were not PMC 2.17 and community Low damaged. Monitoring- structures PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - mixing machines were used for Noise and PMC 2.18 which proper mitigation measure of Low Vibration Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of Execution - environment and safety measures. PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017

Annex-XV

Repair work of Kotli- Sahuratta Samror Road Table 14: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and is PMC 2.2 Dust Emissions no creation of soil which creates no Low Monitoring- dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Loss of access Complied. Execution - for The contractors have taken care by PMC 2.5 Low roadside giving alternate access along Monitoring- residents roadside to facilitate the residents. PIU Complied. All the workers and supervising Safety staff were wearing hats, jackets, and Execution - precautions other safety equipments/articles. PMC 2.6 for workers and Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. At places some un-economic shrubs have been damaged while Execution - excavation. Vegetation and PMC 2.8 No compensatory plantation of Low wildlife loss Monitoring- grasses was required as they will PIU naturally re-grow after rainfall in proper season. The monitoring team revealed that

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level there were some wildlife species but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of Fir and scattered shrubs are Execution - near protected grown and declared as protected PMC 2.9 areas and Low areas under Forest Act. Monitoring- impact on The project construction activities PIU biodiversity have no impact on biodiversity of the area. Complied. Execution - No blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising staff Monitoring- excess material and contractors workers to take PIU appropriate mitigation measures in such cases Complied. Execution - Disposal of The extra debris material was being PMC 2.13 construction Low used in hand filling along with soil Monitoring- Debris and properly compacted. PIU Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, no cropped area PIU loss. Complied. At places water lines were observed exposed and open during digging Execution - Damage or operation but these lines were not PMC 2.15 disturbance Low damaged and created no Monitoring- to public utility disturbance to water line. PIU The contractor and his labour took strict care to damage water line. Complied Execution - Archeological 2.16 Only few mosques and graveyards Low PMC sites were seen near the villages and Monitoring-

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level were located away from the PIU alignment of construction works. Complied. Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU There were sufficient cautions on site through cautions.. Partially complied. The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - mixing machines were used for Noise and PMC 2.18 which proper mitigation measure of Low Vibration Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Being Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of Execution - environment and safety measures. PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

October- December, 2017 Annex-XVI

AK-CW-ll Bridges

Table 15: Environment and Safety Monitoring and Safeguard Compliances - Impacts and Mitigation Measures and Risk Level Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level Execution - Orientation for Training material and orientation PMC 2.1 contractors and already done by Environment Monitoring- workers Specialist of PMC. PIU This impact is not created due to construction activities. Execution - The site of structures is rocky and is PMC 2.2 Dust Emissions no creation of soil which creates no Low Monitoring- dust. However, the instructions PIU were given to the contractor and his staff take actions as per EMP. Disposal of Execution - spoil PMC 2.3 & solid waste Complied Low Monitoring- material of PIU existing road Disposal of Compliance in progress Execution - spoil Such instructions were issued to the PMC 2.4 & solid waste Low contractor’s representative on site Monitoring- unused and ARE for strict compliance of PIU materials safeguards. Loss of access Complied. Execution - for The contractors have taken care by PMC 2.5 Low roadside giving alternate access along Monitoring- residents roadside to facilitate the residents. PIU Complied. Safety All the workers and supervising Execution - precautions staff were wearing hats, jackets, and PMC 2.6 for workers and other safety equipments/articles. Low Monitoring- community Passing by communities were PIU safety guided properly through cautions with colored tapes and ropes Execution - Vehicles and PMC 2.7 equipment Complied Low Monitoring- exhaust PIU Complied. At places some un-economic shrubs have been damaged while excavation. Execution - Vegetation and No compensatory plantation of PMC 2.8 Low wildlife loss grasses was required as they will Monitoring- naturally re-grow after rainfall in PIU proper season. The monitoring team revealed that there were some wildlife species

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level but these were not adversely impacted due to construction activities along the roads of this package. Complied. On both sides of road mature trees Construction of conifer trees and scattered Execution - near protected shrubs are grown and declared as PMC 2.9 areas and Low protected areas under Forest Act. Monitoring- impact on The project construction activities PIU biodiversity have no impact on biodiversity of the area. Complied. Execution - No blasting of hard rocks was being Blasting hard PMC 2.10 done. Hence, strict mitigation Moderate rock Monitoring- measures are being undertaken by PIU the contractors. Partially complied. No drainage lines were damaged as Execution - Drainage line the houses were on the down side of PMC 2.11 Low clogging the roads. Monitoring- For future it was warned not to clog PIU the drainage lines. Complied. The excess material was being used Sourcing fill in hand filling alongwith new fill Execution - material material. PMC 2.12 Low and disposing of It was explained to supervising staff Monitoring- excess material and contractors workers to take PIU appropriate mitigation measures in such cases Complied. Execution - Disposal of The extra debris material was being PMC 2.13 construction Low used in hand filling along with soil Monitoring- Debris and properly compacted. PIU Not applicable. Loss of Execution - There was no need to comply as no agricultural PMC 2.14 agriculture or cropped areas were Very low area/ Monitoring- available along the roads. Hence, no cropped area PIU loss. Complied. At places water lines were observed exposed and open during digging Execution - Damage or operation but these lines were not PMC 2.15 disturbance Low damaged and created no Monitoring- to public utility disturbance to water line. PIU The contractor and his labour took strict care to damage water line. Complied Execution - Archeological Only few mosques and graveyards PMC 2.16 Low sites were seen near the villages and Monitoring- were located away from the PIU

October- December, 2017 Significance Impact as per Section Mitigation Measures Taken Level/risk Responsibilities EMP level alignment of construction works.

Complied. Houses, shops, small tea shops and Execution - Existing Public other community huts/buildings PMC 2.17 and community such as schools, shops etc. were not Low Monitoring- structures damaged. PIU There were sufficient cautions on site through cautions. Partially complied.

The construction works were generally done manually by labor. Some water tankers, tractor trollies, passing buses and wagons and Execution - Noise and mixing machines were used for PMC 2.18 Low Vibration which proper mitigation measure of Monitoring- less use was being made. PIU The machinery was being used only for few hours of the day by the contractors. Hence, no serious impact to people, livestock and wildlife was found. Surface and ground water, Execution - air quality, PMC 2.19 noise, Complied Low Monitoring- road safety and PIU deterioration of vehicles The contractors, their workers and supervising staff of PMC were explained the importance of Execution - environment and safety measures. PMC 2.20 Others Environment specialist prepared the Monitoring- checklist for collection of PIU information about the compliances of environmental safeguards of packages of FERRP.

.

ANNEXURE-XVII

ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN

ENVIRONMENTAL MANAGEMENT AND MONITORING PLAN Table -1: Environmental Management Plan

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring Pre-construction / Design Phase 1 Take measures at design phase to avoid or mitigate Design Landslides 1. Provision of retaining walls, breast walls, side drains and PIU, FERRP damages due to culverts to avoid land sliding. Consultant landslides.

Take measures at design 1. Design of retaining walls, where required Design and construction phase to 2 Flood Protection 2. Store construction material above ground level Consultant PIU, FERRP avoid or mitigate damages and contractor in case of flood. 3. Slope protection by provision of stone pitching techniques

Project disclosure Ensure compliance with o Design all changes in project and disclosed to AJK EPA. Design PIU FERRP. Provincial EPAs Consultant and requirements PIU FERRP. o Ensure all changes in project are included in the revised/updated EMP. 3

Determine whether changes in project need additional environmental assessment and LAR surveys, these surveys shall be carried out, if necessary.

Environmentally Ensure environmentally o The procurement for the project must be in compliance with the Design PIU FERRP. 4 Responsible responsible procurement in ADB ERP guidelines. Consultant and

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring Procurement (ERP) line with the ADB guidelines o Require in procurement specifications that the proposed PIU FERRP. euipet’s ae to e fee fo PCB and other hazardous materials that may be injurious to environment, human health or equipment.

o Choose non-polluting or enhancing methods. Contractor to submit Method Statement and schedule of environmental mitigation measures in response to EMP with tender. Include enhancements, techniques to reduce impacts.

Contractual clauses included to tie the implementation of environmental mitigation measures to a performance bond.

Construction Phase 1. Identify location of work camps in consultation with local authorities.The location shall be subject to approval by the PIU FERRP, C&W Department. If possible, camps shall not To ensure that the be located near settlements or near drinking water supply operation of work camps intakes. does not adversely affect 2. The contractor will ensure that the mobility of the local Contractor the surrounding communities, particularly women and children, and their through PIU,FERRP 1 Construction camps environment and social livestock is not hindered by the construction activities. Environmental and PMC life of locals. Also to Specialist ensure that labour is 3. In case of same water source, contractor will note the provided with basic water collection timings by community (particularly necessities in the camps. women) and will use the off time for water collection to meet campsite requirements. It is preferable that water should be collected after sunset, by the contractor from such water sources. Similarly, contractor will obey the local norms to minimize the issues related with privacy of the

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring women.

4. Contractor will warn the staff strictly not to involve in any un-ethical activities and to respect the local norms and cultural restrictions particularly with reference to women.

5. The contractor will avoid using the village tracks for hauling the construction material. However, if it is unavoidable, the existing ones will be widened, overlaid with shingle or surface treated to accommodate local as well as contractors traffic.

6. Camps will be located at least 500 m away from the nearest local settlement.

7. Cutting of trees shall be avoided and removal of vegetation shall be minimized.

8. Water and sanitary facilities (at least pit latrines) shall be provided for employees. Proper sanitation facilities should be provided including soakage pits.

9. Screen potential crew members for HIV, hepatitis and tuberculosis.

10. Maintain emergency response system.

11. Provide adequate quantity and good quality food to the labour.

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring

12. Drinking water should meet the NEQS and WHO Guidelines.

13. Provide septic tanks for treating sewage from toilets before discharging through soakage pit.

14. Water used for construction purpose should be clearly demarcated.

15. No domestic pets, livestock and wildlife should be allowed in the camp site. Area under work and campsite should be properly cordoned to avoid any hazard to animals.

16. The Contractor will be required to maintain close liaison with the local communities to ensure that any potential conflicts related to common resource utilization for the project purposes are resolved quickly.

17. Solid waste and sewage shall be managed according to the national and local regulations. As a rule, solid waste must not be dumped, buried or burned at or near the project site, but shall be disposed of to the nearest sanitary landfill or site having complied with the necessary permission of local authority. The Contractor shall organize and maintain a waste separation, collection and transport system.

18. All liquid and solid hazardous and non-hazardous wastes are segregated before disposal.

19. Exposed areas shall be planted with suitable vegetation.

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring

20. At the conclusion of the project, all debris and waste shall be removed and properly disposed. All temporary structures, including office buildings, shelters and toilets shall be removed.

21. PIU and Supervising Engineer shall inspect and report that the camp has been vacated and restored to pre-project conditions.

22. Contractor will ensure the provision of medicines, first aid kits and ambulance at the campsite and working place.

23. Proper trainings regarding safety procedures, first aid and emergency response plan should be given to the labour.

24. Labour must be equipped with Personal Protective Equipment (PPE) including safety boots, helmets, gloves, and protective masks. Contractor must ensure their proper usage.

25. Adequate signage, lightning, barriers at construction sites and camps should be provided to avoid any kinds of accidents.

26. Timely public notification on planned construction works.

27. Provision of small filtration units/ plants for safe drinking

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring water to the workers.

28. Complaints of the people regarding construction and labour must be taken seriously by the Contractor.

1. Campsites and asphalt plants will be established on waste/barren land rather than on forested or agriculturally productive land.However, in case where such type of land is not available, it will be ensured that minimum clearing of the vegetation is carried out and minimum damage is caused to trees and undergrowth. To avoid removal of trees and any adverse impact 2. The Cotato’s staff ad laou will e stitly dieted not to damage any vegetation such as trees or bushes. They on flora due to will use the paths and roads for movement and will not be Contractor construction. In case Flora allowed to trespass through farmlands or forested areas. through PIU,FERRP 2 where cutting is Environmental and PMC inevitable, planting of 3. In case where tree cutting is unavoidable, four plants will be Specialist trees at such ratio so that planted for each tree cut. it does not affect 4. Contractor will provide gas cylinders at the camps for environment at any level. cooking purposes and cutting of trees/bushes for fuel will not be allowed.

5. Open fires should be banned in the area to avoid hazards of fire in the area.

6. Dust pollution may impact trees in AOI. Regular sprinkling will ensure the safety of trees from dust.

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring 1. Cover stock piles with plastic sheeting, prevent run-off with hay bales, or use similar measures.

2. Place fence around excavation

3. Investigate shallower excavation and no excavation alternatives Contractor Excavation, cutting, Safe conditions during 4. Ensure excavation is accompanied by well-engineered through PIU,FERRP 3 and filling construction phase drainage Environmental and PMC Specialist 5. Do not fill the flow-line of a watershed

6. Use good engineering practices: for instance, do not use soil alone, first lay a bed of rock and gravel

7. Balance the cuts and fills whenever possible to minimize earthwork movement.

1. Material shall be appropriately secured to ensure safe passage between the destinations during transportation.

2. Material from borrow site should be directly transported Contractor and deposited to the site where it has to be used. Stockpiles Material storage, Ensure safe working through PIU,FERRP 4 should be positioned and sloped to create least visual handling and use conditions impact. No foreign material generated or deposited should Environmental and PMC remain on the site after completion of the activity and the Specialist areas affected by stockpiling should be reinstated.

3. Pre-wet gravel when not available during the dry season, store gravel in a way that will keep it wet, for instance,

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring covered with plastic sheeting.

4. Piling up of loose material should be done in segregated areas to arrest washing out of soil. Debris shall not be left where it may be carried by water to downstream flood plains, dams, lagoons etc.

5. Avoid using sites for storage that drain directly into sensitive areas including water bodies and agricultural land.

6. All runoff from batching plant should be strictly controlled and cement mixed water should be collected, stored and disposed of at the designated site.

7. Materials shall not be loaded to a higher level than the side and tail boards and shall be covered with a good quality tarpaulin.

8. Collection of oil and lubes drips in containers during repairing of construction equipment vehicles.Used oil and lubricants shall be recovered and reused or removed from the site in full compliance with the national and local regulations.

9. Oily wastes must not be burned. Disposal location to be agreed with local authorities and should be a part of waste disposal plan.

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring

10. Machinery should be properly maintained to minimize oil spill during the construction.

11. Solid waste should be disposed at an approved solid waste facility, open burning is illegal and contrary to good environmental practice.

1. Well maintained equipment will be used to avoid the air and noise pollution;

2. Source-control of noise through proper maintenance of haul equipment;

3. Set protocols for vehicle maintenance and prevent fuel tank leaks by: Use and Contractor maintenance of To avoid air and noise  Monitoring and cross-checking fuel level deliveries and through PIU,FERRP 5 heavy equipment pollution use, Environmental and PMC and machineries Specialist  Maximum delivery through pipes and checking pipes and joints for leaks,

 Preventing over-filling of main storage and vehicle tanks.

4. Heavy equipment should not be parked under the tree to avoid soil compaction and damage to the roots of the trees;

Minimize disturbance of 1. Contractor shall submit temporary haul and access routes Contractor 6 Traffic management PIU,FERRP vehicular traffic and plan one month prior to start of works. Special through

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring pedestrians during consideration should be given to SRs such as schools and Environmental and PMC haulage of construction hospitals. Specialist materials, spoil

equipment and machinery, blocking 2. Contractor will mobilize the dedicated team for traffic access roads during works control at diversions. Traffic control team will regulate the damage/maintenance flow of traffic. problems for roads and 3. Efforts should be made to accommodate the traffic along bridges used by the the road as far as practically possible. haulage trucks, dust nuisance to school and 4. Providing and maintaining traffic management comprising; hospitals. diversion warning, guiding and regulatory signage, channelizes and delineators, lightening etc.

5. Maximum allowable speed for heavy machinery on the site should not exceed than 20 km/ hr.

6. Timely public notification on planned construction works.

To minimize effectively 1. All heavy equipment and machinery shall be tailored in full and avoid complaints due compliance with the national and local regulations. Contractor to the airborne emissions, (Relevant regulations are in the Motor vehicles fitness rules through PIU,FERRP 7 Air Quality especially Particulate and Highway Act). Environmental and PMC Matter released to the Specialist. 2. The NEQS applicable to gaseous emissions generated by the atmosphere. construction vehicles, equipment, and machinery will be enforced during the construction of works.

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring

3. Stockpiled soil and sand shall slightly wet before loading, particularly in windy conditions.

4. Fuel-efficient and well-maintained haulage trucks shall be employed to minimize exhaust emissions.

5. Haul-trucks carrying, earth, sand, aggregate and other materials will be kept covered with tarpaulin to avoid dust pollution.

6. Limitations to speeds of such vehicles are necessary. Transport through densely populated area should be avoided.

7. Regular sprinkling of water will control dust pollution.

8. Concrete plants to be controlled with statutory requirements should not be close to sensitive receptors.

9. The existing quarries will be preferred to borrow the aggregate materials. Where local material is used for construction purposes, crushing plant should be located far distance from settlements and ecological source on downwind direction.

10. Asphalt plants will be located at least 500 m downwind fo populated aeas, ad Cotatos’ aps, to iiize the impact of emissions.

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring

11. Concrete and asphalt batching plant should be equipped with primary or secondary emission control system such as wet scrubbers, bag filters or cyclone separators etc.

12. Contractor will set up a system to monitor the air quality along the project corridor. The system will cover protocols for sampling and analysis, assessment of air quality at sensitive locations, reporting, and information sharing. 1. Contractor shall ensure to enforce noise standards as prescribed in the NEQS.

2. Well maintained equipment shall be used to avoid the noise pollution.

3. In case where schools and hospitals are located within AOI, construction activities will be carried out on holidays or Noise / Ground To minimize noise levels during off hours where possible. Contractor and ground vibrations through PIU,FERRP 8 Vibration during construction 4. As a rule, the operation of heavy equipment shall be Environmental and PMC conducted in daylight hours. So, in case of SRs noise operations. Specialist barriers and buffer zones shall be provided to avoid nuisance.

5. Construction equipment, which generates excessive noise, shall be enclosed or fitted with effective silencing apparatus to minimize noise.

6. Contractor must provide and ensure that the labour is wearing PPEs (ear plugs, ear muffs etc.) to avoid loss/

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring damage to hearing.

1. Schedule works in sensitive areas (e.g. rivers) for dry season

2. Identify locations of water courses crossing the road due to lack of drainage facilities.

3. Provision of temporary drainage system to avoid erosion.

4. Provide temporary drainage plan one month prior to the beginning of the construction.

5. Back-fill should be compacted properly in accordance with design standards and graded to original contours where possible. Contractor To minimize soil erosion Soil Erosion/ Surface through PIU,FERRP 9 due to the construction 6. Cut areas should be treated against flow acceleration while Run-off Environmental and PMC activities filled areas should be carefully designed to avoid improper drainage. Specialist

7. Stockpiles should not be formed within such distances behind excavated or natural slopes that would reduce the stability of the slopes.

8. Temporary drains and embankments should be made to channel the runoff appropriately.

9. Measures shall be taken to prevent pounding of surface water and scouring of slopes. Newly eroded channels shall be backfilled and restored to natural contours.

10. Contractor should arrange to adopt suitable measures to

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring minimize soil erosion during the construction period. Contractor should consult concerned authorities in the area before deciding mitigation measures.

11. Clearing of green surface cover to be minimized during site preparation for camps.

12. Planting of trees to be done before the site is vacated and handed back to C&W with appropriate trees (other vegetation cover as appropriate) to ensure interception of rainwater and the deceleration of surface run-off.

1. Waste management plan to be submitted to the Project Management Consultant (PMC) and approved by Resident Engineer one month prior to starting works.

2. Estimating the amounts and types of construction waste to be generated by the project. Contractor Minimize the impacts 3. Investigating whether the waste can be reused in the Construction Waste project or by other interested parties. through PIU,FERRP 10 from the disposal of Disposal Environmental and PMC construction waste. 4. Identifying potential safe disposal sites close to the project Specialist or those designated sites in the contract.

5. Investigating the environmental conditions of the disposal sites and recommendation of most suitable and safest sites.

6. Piling up of loose material should be done in segregated areas to arrest washing out of soil. Debris shall not be left where it may be carried by water to downstream flood

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring plains, dams, lagoons etc.

7. Used oil and lubricants shall be recovered and reused or removed from the site in full compliance with the national and local regulations.

8. Oily wastes must not be burned. Disposal location to be agreed with local authorities.

9. Machinery should be properly maintained to minimize oil spill during the construction.

10. It should be ensured that all liquid and solid hazardous and non-hazardous wastes are segregated before disposal.

11. Solid waste should be disposed at an approved solid waste facility, open burning is illegal and contrary to good environmental practice. 1. No existing spring water under the use of community will be exploited by the Contractor for campsite except after getting approval from community and considering the potential impacts on quantity of water. To ensure the protection Contractor of water resources from 2. Springs will be protected by cordoning the area while through PIU,FERRP 11 Water Resources exploitation and construction to avoid contamination of water. Temporary Environmental and PMC contamination ditches and diversions should be provided to avoid any Specialist water entering the construction site. Any other site specific measures as proposed by Resident Engineer can be taken to avoid contamination of water.

3. Existing water pipelines will be fully protected by the

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring contractor. In case, where construction activities may harm the water supply system, contractor in consultation with communities will relocate the pipelines outside the construction limit.

4. Temporary drainage management plan shall be compiled one month before commencement of works.

5. Proper installation of Temporary Drainage (TD) and Erosion Control (EC) before works within 50 m of water bodies.

6. Proper construction of TD and EC measures, maintenance and management including training of operators and other workers to avoid pollution of water bodies by the considerate construction machinery and equipment.

7. The contractor will prepare guidelines for the workers for minimizing the wastage of water during construction activities and at campsites.

8. Storage of lubricants, fuels and other hydrocarbons in self- contained dedicated enclosures >50m away from water bodies.

9. Proper disposal of solid waste from construction activities and labour camps to avoid pollution of water bodies.

10. Cover the construction material and spoil stockpiles with a suitable material to reduce material loss and sedimentation

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring and avoid stockpiling near to water bodies.

11. Topsoil stripped material shall not be stored where natural drainage will be disrupted.

12. Borrow sites (if required) should not be close to sources of drinking water.

13. The Contractor is required to maintain close liaison with local communities to ensure that any potential conflicts related to common resource utilization like potable water for project purposes are resolved quickly.

1. Hunting, poaching and harassing of wild animals will be strictly prohibited and Contractor will strictly warn his labour accordingly.

2. Camps will be located at least 500 m away from the nearest wild life area to avoid any disturbance to the habitat. Contractor To ensure the protection through PIU,FERRP 12 Fauna of animals and their 3. The camps will be properly fenced and gated to check the Environmental and PMC habitat. entry of wild animals in search of eatable goods. Similarly, wastes of the camps will be properly disposed-off to Specialist prevent the chances of eating by wild animals, which may become hazardous to them.

4. Staff working on the project should be given clear orders, not to shoot, snare or trap any bird.

13 Health & Safety Ensure the health of Contractor 1. Contractor will ensure the provision of medicines, first aid PIU,FERRP workers and local through

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring community kits, vehicle, etc. at the campsite and working place. Environmental and PMC Specialist 2. Medical staff with a provision of ambulance at labour camp.

3. PPEs will be provided to the workers operating in the vicinity of high noise generating machines.

4. Training of workers in construction safety procedures, equipping all construction workers with Personal Protective Equipment (PPE) including safety boots, helmets, gloves, and protective masks, and monitoring their proper and sustained usage.

5. Availability of safe drinking water for the workers.

6. Adequate signage, lightning devices, barriers and persons with flags during construction to manage traffic at construction sites, haulage and access roads to avoid accidents.

7. Setting up speed limits in close consultation with the local stakeholders.

8. Provision of small filtration units/ plants for safe drinking water to the workers.

9. Potential for spread of vector borne and communicable diseases from labour camps shall be avoided (worker awareness orientation and appropriate sanitation should be maintained).

10. Labour will be tested for communicable diseases such as

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring HIV, Tuberculosis and Hepatitis.

11. Contractor will make sure that water ponds or stagnant water is cleaned regularly in order to avoid vector borne diseases. Where required mosquito control sprays will be done.

12. Claims/complaints of the people on construction nuisance/damages close to ROW to be considered and responded to promptly by the Contractor.

13. The storage of all solid waste shall be practiced so as to prevent the attraction, harbourage or breeding of insects or rodents, and to eliminate conditions harmful to public health or which create safety hazards, odors, unsightliness, or public nuisances.

14. Establish all relevant safety measures as required by law and good engineering practices.

Institutional To ensure that contractor Trainings and provisions of proper monitoring facilities are PIU,FERRP 14 Strengthening and is trained to understand PMC recommended. and PMC Capacity Building and implement EMP.

Operation Phase To avoid failure of 1. Monitor and maintain drainage structures and ditches including culverts. Clean out culverts and side channels and 1 Road maintenance structure due to lack of C&W C&W run-outs when they begin to fill with sediment and lose maintenance. their effectiveness; 2. Fill pot-holes with good quality gravel

Sr, Part(ies) Part(ies) Environmental Responsible Responsible Objectives Mitigation Measures (MM) Recommended No. Concern for for Implementation Monitoring To protect natural 1. Vehicle with excessive noise should be prohibited to travel Vehicle environment and nearby C&W 2 on the road; and C&W management residents from air and 2. Public should be educated about the noise and air pollution noise pollution and how to keep the road clean.

Ensure no encroachments/ 1. Necessary signboards with limits of height clearances to be Social safety 4 construction in the project placed properly. C&W C&W Impacts area. No violation of 2. Identify and prevent any illegal encroachments in or clearances spaces. immediate surroundings of the project area

ANNEXURE-V

8. ENVIRONMENTAL MANAGEMENT PLAN & INSTITUTIONAL REQUIREMENTS

8.1. Introduction

The Environmental Management and Monitoring Plan (EMMP) is developed for the following Small Works Contract Packages (District Roads) given in Table 8.1. These district roads are to be considered for rehabilitation under FERRP Project. The aim of this EMP is to eliminate and/or mitigate the impacts envisaged at the design, construction and operation stages. Table 8.1: List of Contract Packages for Small Works Sr Contract Completion Name of Roads No. Package Time

1 Package #1 1 Mujahidabad Hornamera Thalla Road 365 Days 2 Arja Rawalakot Road

2 Package #2 3 Mong Thorar Rawalakot Road

4 RawalakotThorar Road 365 Days

5 Thorar Tain Road

3 Package #3 6 Rawalakot Singola Road 365 Days

4 Package #4 7 Kotli to Serhota Samrore Road 365 Days

5 Package #5 8 Palangi Chirikot Road 365 Days

6 Package #6 9 Abbaspur Chirikot Road 365 Days

7 Package #7 10 Hajira Sirari Road 365 Days

8 Package #8 11 Khutta Aliaabad Hajipir Khawaja Bandi Road 365 Days 12 Lasdanna Hajipir Road

9 Package #9 13 Soli Kala Mula Road

14 Chanjal Fathepur Kirni Naizapir 365 Days Road

15 Khutta Khursheedabad Hellan Road

Source: C&W AJK

The detailed EMP provided in this document as Table 8.5 ensures that all sub-projects have no detrimental effect on the surrounding environment. The Plan shall act as a guideline for incorporating environmental measures to be carried out by the contractors engaged for the different sub-projects. It shall also be used for other parties concerned for mitigating possible impacts associated with each sub-project and will form part of the Contract documents to be considered alongside the specifications. Thus, the EMP implementation will be the contractual obligation for the Contractor(s). This Plan shall act as the Environmental Monitoring Plan during the construction phase of the sub-projects, and will allow for prompt implementation of effective corrective measures. 8.2. Environmental Management Plan (EMP)

The EMP attached with this report ensures the following:

. Delivery of the prescribed environmental outcomes during all phases of each sub- project;

. Formulating a system for compliance with applicable legislative and non-legislative requirements and obligations and commitments for each sub-project;

. Ensure that project design process incorporates best practice environmental design and sustainability principles to minimize potential impacts of construction on the environment and community.

. Ensure that the construction work procedures minimize potential impacts on the environment and community.

. Develop, implement and monitor measures that minimize pollution and optimize resource use.

8.3. Objectives of EMP

The EMP provides a delivery mechanism to address potential impacts of the project activities, to enhance project benefits and to outline standardized good practice to be adopted for all project works. The EMP has been prepared with the objectives of:

. Defining the roles and responsibilities of the project proponent for the implementation of EMP and identifying areas where these roles and responsibilities can be shared with other parties involved in the execution and monitoring of the project;

. Outlining mitigation measures required for avoiding or minimizing potential negative impacts assessed by environmental study;

. Developing a monitoring mechanism and identifying requisite monitoring parameters to confirm effectiveness of the mitigation measures recommended in the study;

. Defining the requirements for communication, documentation, training, monitoring, management and implementation of the mitigation measures.

8.4. Environmental Management/Monitoring and Reporting

During the construction phase, the overall responsibility for the implementation and monitoring of the EMP rests with the Project Director (PD). The PD through the Project Management Consultant (PMC), will supervise the implementation of the proposed mitigation measures and monitor the implementation progress in the field.

The specific roles and responsibilities for environmental management are provided in Table 8.5 and also elaborated below. 8.5. Institutional Arrangements

The environmental management plan will require involvement of the following organizations for its implementation:

. The Project Implementation Unit (PIU), which is already established at the C&W AJK. The PD is supported by Deputy Director Environment Safeguard. This PIU will be the project proponent and owners of the EMP;

. Project Contractors as executors of the EMP;

. PMC staff (on behalf of PIU) as environmental monitor of the execution of the EMP.

8.5.1. Role of Project Director

The key responsibilities of the PD will be as follows:

. If felt necessary at any stage of implementation, the PD liaison closely with the AJK Environmental Protection Agency (AJK EPA) through his Deputy Director Environment Safeguard and all concerned Government departments e.g. Forest and Wildlife Department, Department of Archaeology and Museums, NGOs, CBOs etc.

. Ensuring the EMP is properly implemented;

. Responsible for all environmental coordination and reporting;

. Provide technical support for compliance and monitoring of EMP;

8.5.2. Role of PMC

The PMC will work on behalf of the PIU and through their environmental specialist, will be responsible for ensuring the implementation of the EMP. The PMC will also ensure the overall environmental performance during construction operations and for ensuring implementation of the EMP by the project Contractors.

8.5.3. Role of Project Contractor

The project contractor will be responsible for following items:

. Implementation of, or adherence to, all provisions of the EMP;

. Contractor’s environmental performance will rest with the person holding the highest management position within the contractor’s organization. Reporting to

their management, the contractor’s site managers will be responsible for the effective implementation of the EMP.

8.6. Monitoring Parameters

A monitoring plan for the construction phase of the project, indicating environmental parameters, frequency and applicable standards is provided below as Table 8.5 and elaborated below.  During the procurement/pre-construction period, the monitoring activities will focus on (i) checking the Contract Documents, particularly to ensure that all necessary environmental requirements have been included; and (ii) checking that the contract documents’ references to environmental mitigation measures requirements have been incorporated as part of contractor’s assignment and making sure that any advance works are carried out in good time.  During the construction period, the monitoring activities will focus on ensuring that any required environmental mitigation measures are implemented to address possible impacts.  At this stage, due to the modest scale of these new sub-projects that will be conducted, the construction impacts will be manageable. No insurmountable impacts are predicted, providing that the EMP is implemented to its full extent as required in the Contract documents. However, experience suggests that some Contractors may not be familiar with this approach or may be reluctant to carry out some measures. In order that the Contractors are fully aware of the implications of the EMP and to ensure compliance, it is recommended that environmental measures be costed separately in the tender documentation and that payment milestones are linked to environmental performance, vis a vis the carrying out of the EMP.  The effective implementation of the EMP will be audited as part of the loan conditions and the executing agency must be prepared for this. In this regard, the PMC will guide the design engineers and Contractors on the environmental aspects.

Table 8.2: Environmental Monitoring Plan for each Sub-Project No. Environmental Monitoring Tasks Implementation Implementation Schedule Responsibility

1 Procurement/Pre-construction Phase

1.1 Audit project Contract Documents to PMC Prior to issuance of bidding ensure EMP is included. documents

1.2 Monitor the performance of PMC Ongoing, prior to and during environmental training and briefings and implementation of Works environmental awareness of project staff 2 Construction Phase

2.1 Monitor thorough implementation of PMC During all phases of sub- detailed EMP projects

Table 8.3: Capacity Development and Training Programme for Contractors from each District Provided by Organized by Contents Target Audience Venue Duration

Pre-construction Phase PD/ Deputy Short seminars and courses on: PIU Office PMC offering specialized services in Director Environmental Management Plan and Contractor, PMC One day long FERRP environmental management and Environment Environmental Monitoring Plan Site Engineers and training monitoring Safeguard PIU/ PIU Staff seminar PCU Construction Phase Short seminar on Environmental risks PD/ Deputy PMC offering specialized services in associated with construction phase. Director Contractor, PMC PIU Office One day long social management and monitoring Development of Environmental Environment Site Engineers and FERRP training Performance Indicators Safeguard PIU/ PIU Staff seminar PCU Occupational Health and Safety (OHS) issues

Environmental Management Costs The cost estimates for monitoring during the construction phase is provided below in Table 8.4.

Table 8.4: Summary of Estimated Costs for EMP Implementation for each Sub-Project Item Sub-Item Estimated Estimated Total Cost Total Cost (PKR) (USD)

Mitigation Measures As prescribed under 100,000 1000 (implemented by EMP Contractor) Contingency 5% Contingency 5000 50

Total 1050

TABLE 8.5: Environmental Management & Monitoring Plan Project Activities Section Impact Mitigation Measures Recommended Responsibility Timing Execution Monitoring PIU will check that design and bid BC: during Consideration of EMP in documents are responsive to key detailed preparation of the environmental, social and safety designing of 1.1 PMC PIU detailed design and bid considerations, and that the proposed the sub- documents. method of work reflects the boundaries projects defined in the EMP.

During detailed design, the PMC staff will modify the design in order to BC Loss of Vegetation and 1.2 minimize the removal of mature trees PMC PIU Trees from roadsides Procurement/Pre- construction Considerations  Instructions for topsoil management

will be defined, including the removal and storage of all topsoil to be used in landscaping, once the road work is completed. BC  Use of soil from private land will be 1.3 Top Soil Erosion PMC PIU minimized and only after consultation with and compensation of landowners.  The mitigation measures devised in the section 5.10.1 shall be implemented by the Contractor.  The Construction vehicles hauling materials along urban roads and anywhere where there are roadside BC Materials Haul Route 1.4 residence will be limited and the PIU PMC PIU and Traffic Management will establish a route plan to minimize this disruption.  The mitigation measures devised in

the section 5.20.3 shall be implemented by the Contractor.

 Monitor the progress in light of all environmental statutory and recommended obligations

 Conduct special briefing for managers and/or on-site training for the Contractors and workers on the Orientation for environmental requirement of each 2.1 PMC PIU DC Contractor and Workers sub-project  Agreement on critical areas to be considered and necessary mitigation measures, among all parties that are involved in the project activities.  Continuous progress review and refresher sessions to be followed Construction Phase  Water will be sprinkled daily on all exposed surfaces to suppress emission of dust and batching as well as asphalt plans (if in use by Contractor).  Temporary access road shall be 2.2 Dust Emissions compacted. Contractor PMC, PIU DC  Cleaning of vegetation shall be kept minimum.

 Clearing of vegetation beyond ROW shall be prohibited.  Construction materials susceptible to dust formation will be transported in securely covered trucks to prevent

dust emissions during transportation.  Aggregate material will be delivered to batching plant in damp condition

and water sprays will be applied, if needed, to reduce dust emissions.  Minimum distance of 30 meters will be maintained between potential sources of dust such as material stockpiles and batching plants and community. Disposal of Spoil and  It may be re-used in the soft Solid Waste: shoulders or as fill for other parts of

 Asphalt layers and the new road depending on the quality of the material. It may also be 2.3 base Contractor PMC, PIU DC used as back-fill for borrow pits and materials of the then over-lain with top soil. Asphalt existing road can be pulverized, spread on access Construction Phase roads and compacted. (Continued…)  Waste to be reused in the project or by other interested parties  Identify potential safe disposal sites close to the project sites and

obtaining approval for using these sites from PIU or use of sites Disposal of Spoil and designated in the Contract Solid Waste:  Debris shall not be left where it may 2.4  Unused construction be carried by water to downstream Contractor PMC, PIU DC material (sand, crush), flood plains, dams, lagoons etc. empty drums, concrete  Used oil and lubricants will be waste recovered and reused or removed from the site in full compliance with national regulations.  Machinery will be properly maintained to minimize oil spill during the construction

 Solid waste will be disposed at an approved solid waste facility since open burning is illegal and contrary to good environmental practice.  The mitigation measures devised in the section 5.11.3 shall be implemented by the Contractor. Construction Phase Contractor shall provide safe and

(Continued…) convenient passage for vehicles and pedestrians to and from side roads and properties connecting the project Loss of access for road/area. Work that affects the use of 2.5 Contractor PMC, PIU DC roadside residents side roads and existing access shall not be undertaken without provision of adequate alternate routes; to the prior satisfaction of the PMC staff and affected persons. Safety Precautions for  Providing adequate warning signs Workers and community  Providing workers with PPE (skull safety guard or hard hat and hard toe cap shoes and masks)  Contractor shall instruct his workers in health and safety matters and require the workers to use the 2.6 provided safety equipment Contractor PMC, PIU BC, DC  Establish all relevant safety measures as required by law and good engineering practices.  In addition, the mitigation measures devised in the section 5.18.3 and 5.21.2 shall be implemented by the Contractor.

Vehicle and equipment  All vehicles, generators and other 2.7 Contractor PMC, PIU DC exhaust equipment will be properly tuned and maintained in good working condition

to minimize emission of pollutants.  Willful killing, trapping and trade of faunal species will be strictly prohibited.  Tree plantation will be undertaken at Vegetation and Wildlife project site to compensate for any 2.8 Loss vegetation lost during construction. Contractor PMC, PIU DC Tree plantation shall be conducted in the ratio of 3 tree saplings planted for 1 tree uprooted.  Burning of wood/vegetation as fuel is strictly prohibited. Construction near  Construction activity such as borrow protected areas and pits, quarrying could impinge on impacts on biodiversity natural topography and protected areas. No construction activity shall be carried out in the protected areas and where ever borrow pits/quarries 2.9 are developed shall be leveled to its Contractor PMC, PIU DC original condition.

 The mitigation measures devised in the section 5.15.2-5.15.5 shall be implemented by the Contractor. Blasting hard rock Damage to nearby buildings from blasting and noise as well as vibration is anticipated. The blasting shall be avoided 2.10 Contractor PMC, PIU DC

Drainage line clogging Establishment of stockpiles over existing drainage lines along the hill side of road shall be prohibited. Provide alternative drainage for rainwater if earthworks fill 2.11 established drainage lines during the Contractor PMC, PIU DC construction phase. After completion repair and clean the existing drainage lines.

Sourcing fill material and Landscape defacing and excess disposing of excess transporting of materials. Design to materials optimize cut and fill net balance.

2.12 Contractor PMC, PIU DC

Disposal of construction The construction debris, if recyclable, debris could be reused in fill or otherwise leftover construction materials must be disposed off by Contractor to suitable 2.13 place (to be identified by EA) before Contractor PMC, PIU DC leaving.

Loss of Agricultural Area  Loss of standing crops and damage / Cropland to the agriculture land is anticipated. Where ever; agriculture land is aligned up along the existing road, the disposal of construction debris, 2.14 storage of construction material and Contractor PMC, PIU DC parking of construction machinery must be avoided.

 The mitigation measures devised in the section 5.17.3 shall be

implemented by the Contractor. Damage or disturbance  Some water supply and drainage to public utility. pipelines as well as power supply wires were observed aligning with or crossing the existing road, are 2.15 Contractor PMC, PIU DC anticipated to be damaged during construction works. Mitigation measures are needed to protect or re-align these utilities. Archaeological sites Some graveyards were observed along the roads needs to be protected. No works shall be carried out in the areas where archaeological sites were discovered/ identified. A chance finding 2.16 procedure needs to be devised in the Contractor PMC, PIU DC EMP.

The mitigation measures devised in the section 5.14 and 5.16.2 shall be implemented by the Contractor. Existing Public and  Some of the community and Community Structures government owned structures (Hillan hydropower canal and towers etc.) were observed along the roads needs to be protected. If dismantling in unavoidable, consultation with the concerned communities or 2.17 government agencies needs to be Contractor PMC, PIU DC carried out and appropriate compensation or restoration/ reconstruction needs to be ensured.

 The mitigation measures devised in the section 5.14 and 5.16.2 shall be implemented by the Contractor.

Noise and Vibration The mitigation measures devised in the section 5.6.2 shall be implemented by the Contractor. 2.18 Contractor PMC, PIU DC

Surface Water Quality, The mitigation measures devised in the Soil Contamination and section 5.8.2 and 5.9.3 shall be Ground Water Quality implemented by the Contractor. 2.19 Contractor PMC, PIU DC

Operational Phase Surface and ground The mitigation measures devised in the water, air quality, noise, section 5.23 shall be implemented by Impacts 3.1 C&W AJK P&DD AC road safety and the Contractor. deterioration of vehicles. PMC : Project Management Consultant BC : Before Construction

DC : During Construction

AC : After Construction

PIU : Project Implementation Unit