No LOCATION PROJECT NO SCHEME PRIMARY OBJECTIVES SCHEME DESCRIPTION PROGRAMME / REASON CURRENT FUNDING POSITION SCHEME COST CURRENT STATUS EXPECTED DATE OF COMPLETION LEAD OFFICER

Shared use pedestrian/cycle way along the eastern footway from South Park Estate to the Manchester boundary. Links to Gately 1 Kingsway Cycle Scheme Cycle Safety Fund Funded Complete .March 2014 Mark James Station CCAG1 scheme.

Contraflow Cycle Gate which allows cyclists to gain entry to Warren Aveneue from Wilmslow Road. Links to Toucan Crossing on 2 Warren Ave Cheadle Cycle Scheme LSTF Funded Complete .March 2014 Mark James Road and avoids the busy Wilmslow Road/High Street junction.

Provides a cycle route to Queens Road Primary School, Cheadle Sixth Form Colleage and District Centre. Included 3 Moseley Rd Cheadle Cycle Scheme LSTF Funded Complete .March 2014 Mark James a 20mph speed limit on Moseley Road.

4 A6-MARR Corridor PROW improvements Various schemes to go out to consultation summer 2015, for implementation in FY2016/17 SEMMMS Study Funded DfT / TfGM £200,000 Consult 15/16 Peter Harman

Proposed puffin upgrade to Toucan Crossing on Gatley Road at Gately Station. Path upgrades to cater for cyclists between Gatley 5 Gatley Cycle Scheme Station and the South Park Estate which then links into the A34 Cycle Scheme. Footpath upgrade within Willian Scholes playing CCAG1 Funded £250,000 Construct 15/16 .September 2015 Mark James fields to link both residential areas either side of the railway line.

Traffic-free (off carriageway) link between St Mary's Way and Warren St, including one crossing upgrade and a new toucan 6 Newbridge Lane 250 Cycle Scheme CCAG1 Funded Construct 15/16 Georgina Summers crossing. Will connect with TCAP schemes to provide high level of network connectivity

Proposed schared use cycle scheme to allow cycling in both directions on this one way road. Links the Town Centre with the Trans 7 Chestergate Cycle Scheme CCAG1 Funded Under Construction .June 2015 Mark James Pennine Trail.

This scheme has provided a shared use pedestrain cycle path from Mill Lane to the Manchester boundary. The scheme links the 8 Manchester Road Cycle Scheme CCAG1 Funded Under Construction .September 2015 Mark James scheme at Warren Avenue to the Trans Pennine Trail and included a new Toucan Crossing on Manchester Road. The scheme

Enhancements of Trans Pennine Trail, providing simpler and more legible alignment. There has been a history of the over-complex 9 Mersey Valley Paths Cycle Scheme CCAG1 Funded Construct 15/16 Don Naylor nature of traffic-free links in this corridor having too many strands and discontinuities for ease of use.

A number of schemes to provide links to Cheadle Hulme District Centre. No firm proposals yet and funding just granted but should 10 Chealde Hulme Cycle Scheme provide a cycle link from Warren Avenue in Cheadle to Cheadle Hulme and a link from Green Roundabout. Also could CCAG2 Awarded £2,200,000 Consult 15/16 .March 2018 Mark James provide a 20mph zone to the residential area south of Cheadle Hulme centre.

11 A34 Kingsway South 3159 PROW improvements Physical and legal upgrades to enable cycle and equestrian use of an existing PRoW to stanley Rd For Phase 5 housing development DC funced £210,000 Construct 15/16 Kevin Brooks

Traffic calming, parking TRO, cycle routes, High quality internal connections and external connections towards station; option to connect to Errwood Rd in 12 North Heatons College site Residential / School development DC funced £160,000 Construct 15/16 Alex Bond crossings Manchester

Links within the site, and also external to it (including PRoW) will inter-connect. This will improve the wider traffic-free networks, and 13 Woodford Aerodrome Off site works & PROW works Residential development S106 £431,000 Await payment of S106 Kevin Brooks provide future residents with realistic car-free options

Cycling and walkiing infrastructure, including signing, will ensure a high level of Town Centre permeability for walkiing and cycling. 14 Town Centre 527 TCAP Walking and cycling will be seen as a key component of an increasingly liveable core, additionally enhanced by an emerging Green Regeneration FUNDED / BID £68m Construct 15/16 to 19/20 As Below Infrastructure Plan

St Mary's Way - Portwood 15 0527 101-105 Highway Capacity Improvement Enables increased localised connectivity for walking and cycling networks Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Complete 2017 Sally Laws Roundabout - A6

Higher Hillgate will be traffic calmed with raised platform junctions at Shawcross St and Elizabeth Ave. Footways will be built out to 16 Higher Hillgate / Shawcross St 0527-106 Mitigation / environmental scheme delineate parking bays and improve visibility at crossing points. Higher Barlow Row will be widened on the approach to Higher Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Complete 2017 Sally Laws Hillgate to improve access for residents and businesses.

17 Higher Hillgate 0527-108 Toucan Crossing New pedestrian and cycle crossing at Charles Street Town Centre Access Plan PHASE 2 BID £126k Consult 15/16 Georgina Summers

The existing Puffin crossing is to be upgraded to provide a Toucan crossing with associated footways / cycleways linking Royal Highway capacity & safety improvement and George St and Blackshaw Street. In this scheme Booth Street will be returned to two way working in order to reduce congestion at 18 Package 0527 201-205 Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Construct 2015 - 2017 Sally Laws sustainable access Greek Street roundabout. A cycle route will be provided to link the path to Moscow Rd East to Newton Street. Three 20mph areas will be created.

Provide a cycle gate or No Entry 'Except Cycles' at Chetergate's junction with the Underbanks area. This will allow cyclists to 19 Chestergate 0527 301 Environmental improvement Town Centre Access Plan PHASE 1 FUNDED construct 2017 2017 Mark James contraflow along Great Underbank (the Tans Pennine Trail) and access the Market and Warren Street.

20 King Street West 0527 303 Gyratory system and TPT improvements New cycle link along Chestergate from King Street West to the Interchange Town Centre Access Plan PHASE 2 BID part of wider scheme Consult 15/16 Sally Laws

At the roundabout it is proposed to introduce footway / cycleways around the roundabout with Toucan crossing facilities over King Crossings at roundabout and new access to Street West and Great Egerton Street. A footway / cycle way will be provided along the north side of Heaton Lane along with a new 21 Heaton Lane & Great Egerton St 0527 304 Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Construct 15/16 Sally Laws car park pedestrian / cycle refuge. A footway / cycleway will be provided on the south side between the refuge and the Heaton Lane roundabout.

The existing through route on Station Road will be severed and a new taxi rank, bus stop and service area provided on a loop road 22 Exchange 0527 305 Phase 2 Public Realm adjacent to Station entrance on Station Road. A cycle route will be maintained including improved cycle parking. An area of high Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Construct 2015 - 2017 Nick Whelan quality public realm will be created in front of the station bounded by new development including landscaped areas.

The scheme requires the removal of through traffic from Bridgefield Street which, along with Princes St, Woodman St and Brown St Great Egerton St, A6 Right turn, Bridgefield St will form a new pedestrianised area with only cycle and limited service vehicle access controlled by rising bollards. The existing 23 Redrock 0527 401 Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Construct 2015 - 2017 Sally Laws & Princes St puffin crossing on Great Egerton St will be upgraded to a Toucan crossing. A cycle hub is being provided to the east of little Egerton St..

24 Knightsbridge Junction 0527 402 Improved junction New pedestrian and cycle crossing to aid Trans Pennine Trail access to Howard Street. Town Centre Access Plan PHASE 2 BID part of wider scheme Consult 15/16 Georgina Summers

Improved pedestrian and cycle facilities to be provided at junctions, across Yew Street at Brinksway Bridge and on link to 25 M60 J1 Imps 0527 502 Capacity improvement Town Centre Access Plan PHASE 2 BID part of wider scheme Consult 15/16 Georgina Summers underpass.

A Toucan crossing will be proved between the new junction and Myrtle St with footway / cycleways to access it from Stockport Road 26 Gorsey Bank 0527 503/504 Access junction, spine road Town Centre Access Plan PHASE 1 FUNDED part of wider scheme Construct 2015 - 2017 Sally Laws and Brinksway.

The existing pedestrian crossing of Wood St is to be upgraded to allow cycle use to link Hardman Street across Wood Street. This 27 Wood St 0527 505 Toucan Crossing Town Centre Access Plan PHASE 1 FUNDED £102k Construct 2015 Sally Laws will improve cycle access from Edgeley to the Trans Pennine Trail route along Chestergate.

This project provides walking and cycling routes to the proposed Gorsey Bank industrial development. A new pedestrian and cycle 28 Gorsey Bank 0527 506 Pedestrian and cycle access works route is constructed along the Mersey between Gorsey Bank Road and Swythamley Road. A further link will connect to Hoylake Town Centre Access Plan PHASE 1 FUNDED £311k Sally Laws Road.

Footway / Cycleway on north side of Newbridge Lane from St Mary's Way to New Zealand Road and upgrading of crossing facilities 29 Newbridge Lane 057-602 Cycle improvement Town Centre Access Plan PHASE 1 FUNDED Construct 2017 2017 Nick Whelan to Toucan standard at Newbridge Lane / New Zealand Road.

Proposed upgrade of crossing to allow pedestrian and cycle use including footway widening to allow provision of off road cycle Stockport Rd W, Hall St & route between Osborne Street and Elm Tree Road. Modified junction to allow provision of pedestrian and cycle crossings at 30 0527 603/604/609 Junction and crossing improvements Town Centre Access Plan PHASE 2 BID part of wider scheme Consult 15/16 Georgina Summers Hempshaw Lane Turncroft Lane and new pedestrian crossing at Banks Lane. New pedestrian and cycle crossing with links to Lowndes Lane and Marsland Terrace.

New pedestrian and cycle path proposed to link Vernon Park to Stockport Road West and the off road route proposed along New 31 Goyt Valley 0527 605-608 Cycle improvement Bridge Lane. New path proposed in Woodbank Park along . New pedestrian/cycle river crossing (bridge ) over River Town Centre Access Plan PHASE 2 BID £1.9m Consult 15/16 Georgina Summers Goyt. Surface improvements to route between Dark Lane and Clapgate in Bredbury.

New linkl road includes for a segregated footway/cycleway. New junciton on the A6 Wellington road North includes traffic signals New link Road, junctions and Georges Road 32 A6-Travis Brow 0527 800 and Toucan crossing facilities. Two way segregated cycleway and improved footway / cyclway on George's Road. Improved Town Centre Access Plan PHASE 2 BID Consult 15/16 Naz Huda cycle route cycleway/footway on Travis Brow and Toucan crossing on new link road near to its jucntion with Travis Brow.

Improved pedestrian/cycle path through Park to footbridge over M60. Includes higher protective barrier on bridge (parapet) and weather protection on M60 bridge and improved surfacing /lighting on paths through Heaton Norris Park. Widen 33 Town Centre / M60 0527-901/902 Improved ped / cycle crossings of M60 Town Centre Access Plan PHASE 2 BID £940k Consult 15/16 Georgina Summers existing Trans Pennine Trail route between Penny Lane and the Tame Bridge. Improve protective barriers on bridge (parapets) and lighting on Tame Bridge. Refurbish the subway to Howard Street under the M60. Improved signage and public realm.

A new Toucan pedestrian and cycle crossing will be provided near the junction with Wharf Street and linking footway / cycleways provided on the east side of Lancashire Hill. Improvements will be provided to the subways at Lancashire Hill roundabout including Toucan crossings, junction imprivements and 34 Lancashire Hill / Belmont Way 0527 903/904/905 provision of CCTV. The scheme will provide a new Toucan pedestrian and cycle crossing near the junction with Belmont Street. Town Centre Access Plan PHASE 1 FUNDED part of wider scheme construct 15/16 Georgina Summers CCTV at roundabout Connecting footway / cycleways will link the crossing with Belmont Street. Crossing facilities at the A6 junction will be improved with Toucan facilities added.

This project entails a full study and re-design of directional signage in the Town Centre. This will include tourist signage, cycle 35 Town Centre 0527 Wayfinding Town Centre Access Plan PHASE 1 FUNDED Construct 2015-2020 Andy Varey signage and pedestrian finger post signage (in progress).

Continuation of river valley links to the east of Stockport Town Centre. Upgrading of routes through greenspace and river crossing(s) 36 Goyt Valley Footpath works LSTF Funded £600,000 consult 2016 Don Naylor will providde extensive traffic-free links to communities that will function to both support growth, and provide for leisure

37 Otterspool Road Cycletrack Proposal for off-road uphill cycle link - cyclists are currently travelling slowly within restricted carriageway space LSTF Funded £200,000 consult 2015 Georgina Summers

Rutters Lane Footpath / Woodsmoor Primary purpose will be to provide a car-free connection between the new development and Woodsmoor station. End-points of the 38 3157 Upgrade surfacing and lighting Developer contribution In S106 Await payment of S106 Kevin Brooks Station Path / Newby Rd lighting scheme connect with already-existing cycle networks, ensuring that the scheme also delivers more strategically