Government of

ZILLA PANCHAYAT, .

Backward Region Grant Fund

Annual Action Plan for the Year 2009 – 10

Approved by the District Planning Committee held on 08-09-2009. ZILLA PANCHAYAT RAICHUR

ABSTRACT FOR THE YEAR 2009 - 10

Sl. Total Awareness Service Programme Asset Institution No. Allocation Programmes Delivery Management Creation

1 Zilla Panchayat 588.30 126.88 111.74 48.82 300.86

2 Taluk Panchayat 588.51 117.66 117.65 78.43 274.77

3 Gram Panchayat 1026.08 145.4 148.70 81.66 650.32

4 Urban Local Bodies 589.59 113.26 112.84 72.25 291.24

5 Group Fund 148.05 0 0 0 0

Total 2940.53 503.20 490.93 281.16 1517.19 ZILLA PANCHATAT RAICHUR. BRGF Action Plan for the Year 2009 - 10. ZILLA PANCHAYAT PROGRAMMES.

I. AWARENESS PROGRAMMES.

1 Computer Training ( 04 Months Duration ) a Category I ( 80 per Taluk X 05 X Rs. 5000 Per Candidate ). 20.00 b Category II ( 80 per Taluk X 05 X Rs. 5000 Per Candidate ). 14.22 c Category III ( 80 per Taluk X 05 X Rs. 5000 Per Candidate ). 14.22 2 Conducting Special Intensive Literacy Camps & Fellowups. 10.00 3 Organising Health Camps in villages including making provision for salary & honororiams for resourceful persons. 10.00 4 Skill Development / Employment Training Programmes. a Garment Tailoring & Power Machine Operator Training. ( 400 Students @ Rs. 5500 /- ). 22.00 b Pattern & Cutting Master Cources. ( 300 Students @ Rs. 6500 /- ). 19.44 c Costume Designing & Garment Marking Course. ( 200 Students @ Rs. 8500 /- ). 17.00

Total 126.88

II. SERVICE DELIVERY.

Upgradation & Improvements of Services for Public Health Centres, Community Health Centres & General Hospitals. ( 05 1 34.20 Taluks X Rs. 6.5 Lakhs ). 2 Upgradation & Improvements of Blood Banks at Taluk Level Hospitals. ( Deodurga & ). 43.32 3 Providing Ambulance for Primary Health Centres ( No.s. 08 ). 34.22

Total 111.74 III. PROGRAMME MANAGEMENT

1 Establishing Data Centre & MIS at Zilla Panchayat Office. 10.00 2 Setting up with Hardware & Software equipments at Zilla Panchayat & Taluk Panchayat. 29.21 3 Conducting of Evaluation & Social Auditing from Reputed Institutions. 4.00 4 Hiring the services of programmes conducting Computer Operator at District Level. (12 Months X Rs. 10,000 /- ). 1.20 5 Documentation 4.41

Total 48.82

ZILLA PANCHAYAT, RAICHUR. BRGF Action Plan for the Year 2009 - 10. Rs. In Lakhs I. ASSET CREATION

1 Construction of Cultural Building near Venkateshwar Temple at Dinni Village, Marchathal (GP) of Raichur Taluk. 5.60 2 Extension of Pipe Line at Ibrahim Doddi Village of Raichur Taluk. 2.80 3 Extension of Pipe Line at Sagankunta Village of Raichur Taluk. 2.80 4 Extension of Pipe Line at Old Maliyabad Village of Raichur Taluk. 2.00 5 Providing Pipe Line & Cistern at New Gonwar Village of Raichur Taluk. 2.50 6 Construction of Check Dam at Gonwar Village of Raichur Taluk. 1.10 7 Construction of Higher Primary School Compound Wall at Gonhal Village, Jagirvenkatapur (GP)of Raichur Taluk. 2.00 8 Construction of Additional Class Room for Higher Primary School at Gonhal Village, Jagirvenkatapur ( GP ) of Raichur 1.50 9 Construction of Cultural Building at Sultanpur Village, Jagirvenkatapur (GP)of Raichur Taluk. 4.00 10 Construction of Cultural Bhavan at Jalibenchi Village, Kamlapur (GP) of Raichur Taluk. 4.00 11 Construction of Ranga Mandir in Primary School at Singanodi Village of Raichur Taluk. 1.60 12 Construction of Higher Primary School Compound Wall at Village of Raichur Taluk. 3.60 13 Construction of Higher Primary School Compound Wall at Tunthapur Village of Raichur Taluk. 2.00 14 Construction of Primary School Compound Wall at Kadloor Village of Raichur Taluk. 2.48 15 Construction of Primary School Compound Wall at Kathlatkoor Village of Raichur Taluk. 2.00 16 Construction of Primary School Compound Wall at Deosugur Village of Raichur Taluk. 4.48 Construction of Cultural Bhavan near Basaveshwara Temple at Raghunathanhalli Village, Jagirvenkatapur (GP) of Raichur 17 3.00 Taluk. 18 Construction of Library Building at Village of Raichur Taluk. 3.00 19 Construction of Samudaya Bhavan at Jagirvenkatapur Village of Raichur Taluk. 2.00 20 Construction of Cultural Bhavan at SC Colony, of Raichur Taluk. 4.48 21 Construction of Library Building at Sarjapur Village of Lingasugur Taluk. 3.00 22 Construction of Check - Dam at Kuppigudda Village near Chik Nala of Lingasugur Taluk. 2.60 23 Construction of Check - Dam at Telekhan Nala of Kamandaladinni Village of Lingasugur Taluk. 2.80 24 Construction of Check - Dam near Nala of Amedihal Village of Lingasugur Taluk. 2.80 25 Construction of Check - Dam at Survery No. 207 of Chittapur Village of Lingasugur Taluk. 2.60 26 Construction of Higher Primary School Compound Wall at Village, Bayyapur (GP) of Lingasugur Taluk. 3.00 27 Construction of Aganawadi Building at Yelaghatta Village, Rodalabanda (GP) of Lingasugur Taluk. 3.00 28 Construction of Aganawadi Building at Benchaldoddi Village, Goudur (GP)of Lingasugur Taluk. 2.60 29 Construction of Check - Dam near Nala of Gujjala Hanumappa Field of Guntagol Village of Lingasugur Taluk. 2.80 30 Extension of Pipe Line with Cistern at Gonwotla Village, Guntagol (GP)of Lingasugur Taluk. 2.80 31 Construction of Mahelaya Cultural Bhavan at Naglapur Village of Lingasugur Taluk. 2.00 32 Construction of Lower Primary School Compound Wall at Kadlahal Village of Lingasugur Taluk. 1.60 33 Extension of Pipe Line at Telekan Village of Lingasugur Taluk. 2.00 34 Construction of Bus Shelter near Old Bus Stand at Village of Lingasugur Taluk. 1.50 35 Construction of Bus Shelter near Maski, Baglanur Cross at Maski Village of Lingasugur Taluk. 1.50 36 Construction of Check - Dam at Maski Village of Lingasugur Taluk. 2.60 37 Construction of Cultural Bhavan at Village of Lingasugur Taluk. 3.00 38 Construction of Primary School Compound Wall at Kuppigudda Village, Sarjapur (GP) of Lingasugur Taluk. 4.50 39 Construction of Compound Wall for Devaraj Arus High School at Anahosur Village of Lingasugur Taluk. 4.50 40 Construction of Higher School Compound Wall at Hosagudda Village, Goudur (GP) of Lingasugur Taluk. 2.48 41 Construction of Higher School Compound Wall at Bandebhavi Village, Goudur (GP) of Lingasugur Taluk. 2.00 42 Construction of Primary School Compound Wall at Gurugunta Village of Lingasugur Taluk. 4.50 43 Construction of Library Building at Kallur Village of Taluk. 5.60 44 Construction of Aganawadi Building at Pasalabandi Camp, Sagapur (GP) of Manvi Taluk. 5.60 45 Construction of Compound Wall of Sericulture Dept Building at Village, Ameenagad (GP) of Manvi Taluk. 3.00 46 Construction of Check Dam at Tupdur Village, (GP) of Manvi Taluk. 2.60 47 Construction of Samudaya Bhavan near Adveshwara Math at Kallur Village of Manvi Taluk. 5.60 48 Construction of Primary School Compound Wall near Janata Colony at Hirehanagi Village of Manvi Taluk. 5.60 49 Construction of Check - Dam at Gaddemitti Camp, Haravi of Manvi Taluk. 2.80 50 Construction of Check - Dam at Madagiri Village of Manvi Taluk. 2.80 51 Construction of Compound Wall to P.U. College at Village of Manvi Taluk. 5.60 52 Construction of Check - Dam near Nala of Kardigudda Village of Manvi Taluk. 2.80 53 Construction of Check - Dam near Bheerappa Gudda at Byagwat Village of Manvi Taluk. 2.80 54 Construction of Cultural Bhavan near Adveshwar Matha, Kallur Village of Manvi Taluk. 3.50 55 Construction of School Compound Wall at Village of Manvi Taluk. 1.12 56 Construction of Check Dam at Umalipannur Village of Manvi Taluk. 4.50 57 Construction of High School Compound Wall at Kurkunda Village, Mallat (GP) of Manvi Taluk. 4.50 58 Construction of Check - Dam at Kapgal Village of Manvi Taluk. 2.24 59 Construction of Check - Dam at Machanur Village of Manvi Taluk. 2.24 60 Renovation of Tank at Goundanabhavi Village of Taluk. 2.80 61 Renovation of Tank at Surya Reddy Camp of Sindhanur Taluk. 2.80 62 Construction of Check - Dam at Survery No. 83 off Konthanoor Village of Sindhanur Taluk. 2.80 63 Construction of Check - Dam at Village of Sindhanur Taluk. 2.80 64 Extension of Pipe Line at Hosalli E.J. Camp of Sindhanur Taluk. 5.60 Drilling of 05 Bore Wells - One Bore Well at Village, One Bore Well at Pulimeshwar Dinni Village, One Bore 65 Well near Mahalingaraya Temple of Javalgera Village, One Bore Well near Bheemanna Sangathi House & One Bore Well 2.80 at Jangarahutti of Sindhanur Taluk. 66 Construction of Cultural Bhavan at Chintamandoddi Village, Gonawara (GP) of Sindhanur Taluk. 2.80 67 Construction of Cultural Bhavan opp. Church Village, (GP) of Sindhanur Taluk. 5.60 68 Construction of Library Building at Village of Sindhanur Taluk. 5.60 69 Construction of Library Building at Village of Sindhanur Taluk. 5.60 70 Construction of Library Building at Kolbal Village of Sindhanur Taluk. 5.00 71 Construction of School Compound Wall at Kolbal Village of Sindhanur Taluk. 0.60 72 Construction of Primary School Compound Wall at Sultanpur Village, Goundanabhavi (GP)of Sindhanur Taluk. 2.00 73 Construction of Cultural Bhavan at Malingaraya Colony, Javalgera Village of SindhanurTaluk. 4.00 74 Construction of Vehicle Stand for High School at Javalgera Village of Sindhanur Taluk. 1.00 75 Installation of Diamond Mess to the Drinking Water Tank at Geetha Camp, Devargudi of Sindhanur Taluk. 3.00 76 Drinking Water facility tank of Diamond Mess at Devi Camp, Devargudi of Sindhanur Taluk. 3.00 77 Construction of Aganawadi Building Compound Wall at Suryareddy Camp of Sindhanur Taluk. 1.48

78 Construction of Aganawadi Building Compound Wall at new village of Haretnur Village, Badarli (GP) of Sindhanur Taluk. 3.30

79 Construction of School Compound Wall at R.H. Camp No. 04 of Sindhanur Taluk. 1.20 80 Construction of Primary School Compound Wall at Pagadadinni Village of Sindhanur Taluk. 3.00 81 Construction of Cultural Bhavan at Maridevara Math, Balganur Village of Sindhanur Taluk. 3.00 82 Construction of Krishi Vanda, Survey No. 03 A of Village of Deodurga Taluk. 1.80 83 Construction of Library Building near Basaveshware Temple at Village of Deodurga Taluk. 2.30 84 Construction of Cultural Bhavan at Markamdinni Village of Deodurga Taluk. 1.50 85 Construction of Check - Dam at Bommanhal Village, Hemanal (GP)of Deodurga Taluk. 1.00 86 Construction of Protection Wall to School of Bommanahalli Village, Siddapur (GP) of Deodurga Taluk. 1.60 87 Construction of Check - Dam at Jalahalli Village of Deodurga Taluk. 2.00 88 Construction of Aganawadi Building at Budinhal Village, Hire Buddur (GP) of Deodurga Taluk. 3.00 89 Construction of Sthree Shakthi Bhavan at Budinhal Village, Hire Buddur (GP) of Deodurga Taluk. 2.60 90 Construction of Cultural Bhavan at Nagaddinni Village of Deodurga Taluk. 2.80 91 Construction of Cultural Bhavan at Nagoli Village, Jagirajadaladinni (GP) of Deodurga Taluk. 2.80 92 Construction of Check - Dam at Pamarth Doddi Village of Survery No. 252 of Deodurga Taluk. 2.80 93 Construction of Check - Dam at Devara Gudda Village near Nala of Deodurga Taluk. 2.80 94 Construction of School Compound Wall at Venglapur Village, Karigudda (GP) of Deodurga Taluk. 2.00 95 Construction of Aganawadi Building at Bhojanayakana Tanda of Deodurga Taluk. 3.60 96 Construction of P.U.College Compound Wall at Arkera Village of Deodurga Taluk. 4.50 97 Extension of Pipe Line with Cistern at Yermas Village of Deodurga Taluk. 2.44 98 Extension of Pipe Line with Cistern at Thippaladinni Village of Deodurga Taluk. 2.44 99 Construction of High School Compound Wall at Village of Deodurga Taluk. 4.48 Total 296.26

GRANT TOTAL 583.70

I. GROUP FUND

1 Strengthen of NIC Office, Raichur with Construction of Additional Room & Providing necessary equipments. 15.00 2 Construction of Kalika Kendra Building at Sunkeshwar Village of Manvi Taluk. 10.00 3 Construction of Kalika Kendra Building at Embral Village of Raichur Taluk. 10.00 4 Construction of Kalika Kendra Building at Dinni Village of Raichur Taluk. 10.00 5 Construction of Cultural Building at Sikal Bapur Village of Manvi Taluk. 5.00 6 Construction of Cultural Building at Village of Manvi Taluk. 5.00 7 Construction of Cultural Building at Manchalapur Village of Raichur Taluk. 12.00 8 Construction of Government Girls High School Building at Sindhanur Village. 12.00 9 Construction of High School Compound Wall at Konapurpet Village of Manvi Taluk. 10.00 After identifing the gaps arises during the implementation of 2008 -2009 programmes the fund will be used accordingly. 10 9.05 11 Furnishing of Newly Constructed Zilla Panchayat General Body Meeting Hall. 50.00

Total 148.05 ZILLA PANCHAYAT RAICHUR

BRGF Action Plan for the Year 2009 - 10

Taluk Panchayat Progrogrammes

ABSTRACT

Name of the Taluk Total Awareness Service Programme Asset Sl. No. Panchayat Allocation Programmes Delivery Management Creation 1 Deodurga 100.47 20.10 20.10 13.40 46.87 2 Manvi 129.08 25.81 25.81 17.20 60.26 3 Lingasugur 125.55 25.11 25.11 16.74 58.59 4 Raichur 111.20 22.25 22.24 14.83 51.88 5 Sindhanur 122.21 24.39 24.39 16.26 57.17

Total 588.51 117.66 117.65 78.43 274.77 ZILLA PANCHAYAT RAICHUR

Raichur Taluk Panchayat of BRGF Action Plan for the Year 2009 -10

I. AWARENESS PROGRAMMES 1 Educational Tour to Taluk Panchayat Members. 4.25 2 Conducting Awareness Programs regarding use of new equipments in the Agriculture & Horticulture activities in all Hooblies. 4.50 3 Computer Training to Unemploymed Youths, Teachers & Health Workers in 6 Hooblies. 7.58 Conducting Tailoring & Embroidery for SHG Groups & Literacy Programmes for Illiterate Womens ,SSLC students coaching 4 5.92 class in all Hooblies. Total 22.25

II. SERVICE DELIVERY 1 Providing Solar Lamps & Water Heater to SC / ST & BCM Hostels. 10.47 2 Providing Drinking Water facility for SC / ST Colony. 6.77 3 Establishment of Comppypponent Therpy Unit at District Hospital. 5.00 Total 22.24

III. PROGRAMME MANAGEMENT 1 Monitoring & Evaluation of Programmes. 6.41 2 Conducting Training to Staff Regarding, RTI & Purchase of Xexox Machine. 6.42 3 Preparation of Plan. 2.00 Total 14.83 IV. ASSET CREATION 1 Construction of Aganawadi Building at Atkur Village, Poorthipli of Raichur Taluk. 3.75 2 Construction of Aganawadi Building at Udamgal Village, Poorthipli of Raichur Taluk. 3.75 3 Construction of Aganawadi Building at Talmari Village of Raichur Taluk. 3.75 4 Construction of Aganawadi Building at Jagirivenkatapur Village of Raichur Taluk. 3.75 5 Construction of Aganawadi Building at Village of Raichur Taluk. 3.75 6 Construction of Open Drama Hall at Yadlapur Village of Raichur Taluk. 1.50 7 Construction of Open Drama Hall at Bijangrea Village of Raichur Taluk. 1.50 8 Construction of Open Drama Hall at Turkundona Village, Poorthipli of Raichur Taluk. 3.22 9 Construction of Library Building at Chandrabanda Village of Raichur Taluk. 3.22 10 Construction of Sanskrit Bhavan at Sagamkunta Village of Raichur Taluk. 3.22 11 Construction of School Compound Wall at Deosugur Village of Raichur Taluk. 2.43 12 Construction of School Compound Wall at Village, Manchalapur of Raichur Taluk. 3.22 13 Construction of Samratha Soudha ( Matching Grants ). 11.00 14 Construction of toilet at Taluk Panchayat Building of Raichur Taluk. 2.82 15 Providing Drinking Water facility. 1.00 Total 51.88

Grand Total 111.20 ZILLA PANCHAYAT RAICHUR

Sindhanur Taluk Panchayat of BRGF Action Plan for the Year 2009 -10

I. AWARENESS PROGRAMMES 1 Training Programmes to the Members of SHG's regarding Tailoring, Embroadary, Food Processing & Marketing. 5.13 2 Hiring Check - Up Camps to School Children at Jalihal, Gunda, Hedginal & Balaganur. 3.00 Study Tour for Taluk Panchayat Members to the place of Kerala, Coimbtore, Salam, Vishakapatanam, Ralagau Siddi ( 3 16.26 Ahamad Nagar, Maharastra ) & Rajasthan. Total 24.39

II. SERVICE DELIVERY 1Providing Solar Water Heater & Drinking Water facility to SC / ST & BCM Hostels. 7.13 Providing OT Table, Generator & Other necessary equipments to Primary Health Centre at Gandhi Nagar Village, Jalihal 2 6.13 Gram Panchayat. Providing OT Table, Generator & Other necessary equipments to Primary Health Centre at Hedginhal Village, Badarli Gram 3 6.13 Panchayat. 4 Establishment of Component Therpy Unit at District Hospital. 5.00 Total 24.39

III. PROGRAMME MANAGEMENT 1 Monitoring & Evaluation of Works. 16.26 Total 16.26

IV. ASSET CREATION 1 Construction of Community Toilet at Gudgaldinni, Matur ( Bappur GP ) & Chiratanal ( Devaragudi GP ) @ Rs. 3.75 Lakhs 11.27 Construction of Library Building at Diddgi ( Ramathnal GP ), Jalihar, Hedginhal ( Badarli GP ), Siddrampur ( Chennalli GP ), 2 34.40 Gandhinagar, & Hampanhal ( Bappur GP ) @ Rs. 4.90 Lakhs each. 3 Construction of Aganawadi Building at & Balganur @ Rs. 3.75 Lakhs each. 7.50 4 Construction of Community Toilet at Vagranal Village of Gunda Gram Panchayat. 4.00 Total 57.17

Grand Total 122.21 ZILLA PANCHAYAT RAICHUR

Lingasugur Taluk Panchayat of BRGF Action Plan for the Year 2009 -10

I. AWARENESS PROGRAMMES 1 Conducting Awareness Programmes & Workshops for Elected Members & Public. 5.03 2 Conducting Women Literacy Programmes. 15.04 3 Conducting Study Tour for Elected Members. 5.04 Total 25.11

II. SERVICE DELIVERY 1 Organising Skill Development Programmes. 2.48 2 Appointment of Bare Foot Engineers on Contact basis. 7.53 3 Organising Computer Training class for Unemployed Youths. 10.10 4 Establishment of Component Therpy Unit at District Hospital. 5.00 Total 25.11

III. PROGRAMME MANAGEMENT 1 Preparation of Plan. 3.35 2 Monitoring & Evaluation of Works. 6.69 3 Conducting Workshops for Elected Members & Staffs. 6.70 Total 16.74 IV. ASSET CREATION 1 Construction of one Aganawadi Building at Narakaladinni Gram Panchayat. 3.26 2 Construction of one Aganawadi Building at Mavinabhavi Gram Panchayat. 3.26 3 Construction of one Aganawadi Building at Bannigola Gram Panchayat. 3.26 4 Construction of one Aganawadi Building at Gejjelagatta Gram Panchayat. 3.26 5 Construction of one Aganawadi Building at Ankusadoddi Gram Panchayat. 3.26 6 Construction of one Aganawadi Building at Anahosur Gram Panchayat. 3.26 7 Construction of one Aganawadi Building at Sajapur Gram Panchayat. 3.26 8 Construction of one Aganawadi Building at Goudur Gram Panchayat. 3.26 9 Construction of one Aganawadi Building at Kalapur Gram Panchayat. 3.26 10 Construction of one Aganawadi Building at Gram Panchayat. 3.26 11 Construction of one Aganawadi Building at Talekhan Gram Panchayat. 3.26 12 Construction of one Aganawadi Building at Kannhal Gram Panchayat. 3.26 13 Construction of one Aganawadi Building at Maraladinni Gram Panchayat. 3.26 14 Construction of one Aganawadi Building at Santhekallur Gram Panchayat. 3.26 15 Construction of one Aganawadi Building at Hatti Gram Panchayat. 3.26 16 Construction of one Aganawadi Building at Kota Gram Panchayat. 3.26 17 Construction of one Aganawadi Building at Guntagol Gram Panchayat. 3.26 18 Construction of one Aganawadi Building at Paidoddi Gram Panchayat. 3.17 Total 58.59

Grand Total 125.55 ZILLA PANCHAYAT RAICHUR

Manvi Taluk Panchayat of BRGF Action Plan for the Year 2009 -10

I. AWARENESS PROGRAMMES 1 Education Tour to Taluk Panchayat Programmes. 9.00 2 Awareness of Government Programmes to Staff & Public. 7.00 3 Electronics, Electrical & Automobiles Training to Unemployed Youths. 5.00 4 Tailoring & Embroidery Training to SHG Members. 4.81 Total 25.81

II. SERVICE DELIVERY 1 Providing Solar Lamps & Water Heater to SC / ST & BCM Hostels. 12.00 2 Providing Skill Development Training & Kits. 3.81 3 Providing Medicines & Equipments to Government Health Institutions. 5.00 4 Establishment of Component Therpy Unit at District Hospital. 5.00 Total 25.81

III. PROGRAMME MANAGEMENT 1 Monitoring & Evaluation of Works. 3.50 2 Advertisement of Government Programmes in Rural Areas through Distribution of Pomplets & Exhibition of Boards in thickly populated places. 8.00 3 Conducting Workshop to People Representative & Staff. Providing Computers. 5.70 Total 17.20

IV. ASSET CREATION 1 Construction of Aganawadi Building. ( No. 14 ). 42.00 2 Construction of Library Building. ( No. 06 ). 18.26 Total 60.26

Grand Total 129.08 ZILLA PANCHAYAT RAICHUR Deodurga Taluk Panchayat of BRGF Action Plan for the Year 2009 -10

I. AWARENESS PROGRAMMES 1 Education Tour to Taluk Panchayat Programmes. 4.00 2 Awareness of Government Programmes to Staff & Public. 4.50 3 Electronics, Electrical & Automobiles Training to Unemployed Youths. 5.60 4 Tailoring & Embroidery Training to SHG Members. 6.00 Total 20.10

II. SERVICE DELIVERY 1 Providing Solar Lamps & Water Heater to SC / ST & BCM Hostels. 4.50 2 Providing Skill Development Training & Kits. 6.00 3 Providing Medicines & Equipments to Government Health Institutions. 4.60 4 Establishment of Component Therpy Unit at District Hospital. 5.00 Total 20.10

III. PROGRAMME MANAGEMENT 1 Monitoring & Evaluation of Programmes. 2.50 2 Advertisement of Government Programmes in Rural Areas through Distribution of Pomplets & Exhibition of Boards in thickly 5.45 3 Conductingltd lWorkshop to People Representative & Staff & Meeting Administrative Expenses. 5.45 Total 13.40

IV. ASSET CREATION Construction of Aganawadi Building ( No. 09 ). At - 03, Goplapura, bhumanagunda, Gagal, K. Irabgera, 1 33.75 Chikkaladoddi, Ganadhal - 02, Yamanal, Herundi @ Rs. 3.75 Lakhs each. 2 Construction of Commercial Complex in Taluk Panchayat premises. 2.12 3 Matching Grants to construction of Samarthya Soudha at Deodurga. 11.00 Total 46.87

Grand Total 100.47 ZILLA PANCHAYAT RAICHUR

Abstract of Gram Panchayat Programmes for the Year 2009 - 10

Sl. Name of the Total Awareness Service Programme Asset No. Taluks Allocation Programmes Delivery Management Creation

1 Deodurga 175.56 28.00 36.96 5.60 105.00 2 Manvi 223.40 25.90 23.58 20.91 153.01 3 Lingasugur 221.54 40.63 39.79 26.19 114.93 4 Raichur 192.40 15.85 13.35 6.18 157.02 5 Sindhanur 213.18 35.02 35.02 22.78 120.36

Total 1026.08 145.40 148.70 81.66 650.32 ZILLA PANCHAYAT RAICHUR

Backward Region Grant Fund Action Plan 2009 - 10

Gram Panchayat Programmes

Taluk : DEODURGA

Sl. Name of the Total Programme Awareness Programme Amount Service Delivery Amount Amount Asset Creation Amount No. Gram Panchayat Allocation Management

Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 1 Alkod 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 3.75 Aganawadi Building. Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 2Arkera 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Arkera. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 3 B. Ganekal 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Peera Naidk Tanda. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 4 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 3.75 Aganawadi Building. Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 5 Dondambli 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 3.75 Aganawadi Building. Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 6 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Gabbur.

Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 7 Galag 6627.27 Elected Representatives, Staffs & 1100.00 Aganawadi Centres & Providing 1132.32 Plans, Documentation, 0020.20 Aganawadi Building at 3375.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Maligoudar Oni, Galag.

Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 8 Ganadhal 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Sunnadakal Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 9 Gugal 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. . Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 10 Hemanal 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Khanpur. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 11 Hirebudur 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Nagarhal. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 12 Hosur Siddapur 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. H. Siddapur. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 13 Jagirjadaladinni 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 3.75 Aganawadi Building. Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 14 Jalahalli 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Eqqpuipments to Govt Hosp itals. Monitoring etc. Ward No. 06 at . Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 15 Jeerabandi 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Chickabudur. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 16 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Jambaldinni. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 17 Karigudda 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Venglapur. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 18 K. Irabgera 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Sasivegera. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 19 Koppar 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Paratapur. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 20 Kottadoddi 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 EducationalEducational ToursTours to Students.Students. EquipmentsEquipments to GovtGovt Hospitals.Hospitals. MonitoringMonitoring etc.etc. Hemanoor.Hemanoor. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 21 Kyadigera 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Mukkalgudda Tanda. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 22 Maladakal 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. N. Ganekal. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 23 Masarkal 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Masarkal. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 24 Mundaragi 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Mukanhal. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 25 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Shivangi. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 26 Nagadadinni 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. N. Ganekal. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 27 Palakanamardi 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 Aganawadi Building at 3.75 Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Palakanmaradi. Awareness Training Programmes to Providing Playing Materials to Preparation of GP Construction of 28 Ramadurga 6.27 Elected Representatives, Staffs & 1.00 Aganawadi Centres & Providing 1.32 Plans, Documentation, 0.20 3.75 Aganawadi Building. Educational Tours to Students. Equipments to Govt Hospitals. Monitoring etc. Total 175.56 28.00 36.96 5.60 105.00 ZILLA PANCHAYAT RAICHUR

Backward Region Grant Fund Action Plan 2009 - 10

Gram Panchayat Programmes

Taluk : LINGASUGUR

Sl. Name of the Total Programme Awareness Programme Amount Service Delivery Amount Amount Asset Creation Amount No. Gram Panchayat Allocation Management Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 1 Anahousur 8.36 1.61 1.48 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Lights. Programmes.

Pti&Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 2 Ankushadoddi 8.36 1.61 1.53 Implementation of 0.98 4.24 Representatives. Aganawadi Childrens. Commercial Complex. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 3 Anwari 8.36 1.61 1.48 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Protection Wall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 4 Amadihal 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Meeting Hall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 5 Bannigol 8.36 1.56 1.48 Implementation of 1.03 4.29 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 6 Bayyapur 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Commercial Complex. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 7 Devarabhupur 8.36 1.61 1.48 Implementation of 0.98 4.29 Representatives. Aganawadi Childrens. Community Toilets. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 8 Eachanal 8.36 1.61 1.53 Implementation of 0.98 4.24 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 9 Gejjalagatta 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Lights. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 10 Gorebal 8.36 1.61 1.48 Implementation of 0.98 4.29 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 11 Goudur 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 12 Guntagol 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 13 Gurugunta 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 14 Hatti 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 15 Honnalli 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 16 Hunur 8.36 1.61 1.53 Implementation of 1.03 4.19 Representatives. Aganawadi Childrens. Meeting Hall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 17 Kachapur 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens. Meeting Hall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 18 Kalapur 4.18 0.75 0.75 Implementation of 0.70 1.98 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 19 8.36 1.56 1.53 Implementation of 1.03 4.24 Representatives. Aganawadi Childrens . Meeting Hall . Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 20 Kota 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Meeting Hall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 21 Maraladinni 4.18 0.75 0.70 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 22 Medakinal 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Meeting Hall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 23 Maski 4.18 0.75 0.70 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 24 Mattur 4.18 0.75 0.70 Implementation of 0.40 2.33 Representatives. Aganawadi Childrens. Meeting Hall. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 25 Mavinabhai 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Commercial Complex. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 26 Naglapur 4.18 0.75 0.70 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 27 Nagaral 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 28 Narakaladinni 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 29 Paidoddi 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Rodalabanda ( Training to Staffs & Public Supply of Playing Materials to Installation of Solar 30 4.18 0.70 0.75 Implementation of 0.45 2.28 Taga ) Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Rodalabanda ( Training to Staffs & Public Supply of Playing Materials to Construction of 31 4.18 0.70 0.75 Implementation of 0.45 2.28 UUKP.K.P. ) Representatives. Aganawadi Childrens . Aganawadi Building . Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 32 Santhekallur 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 33 Sarjapur 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 34 Telekhan 4.18 0.75 0.70 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Ananawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 35 Upparnandihal 4.18 0.70 0.75 Implementation of 0.45 2.28 Representatives. Aganawadi Childrens. Meeting Hall. Programmes. Total 79.42 13.76 14.03 8.88 42.75 ZILLA PANCHAYAT RAICHUR

Backward Region Grant Fund Action Plan 2009 - 10

Gram Panchayat Programmes

Taluk : MANVI

Sl. Name of the Total Programme Awareness Programme Amount Service Delivery Amount Amount Asset Creation Amount No. Gram Panchayat Allocation Management

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 1 Ameengada 8.36 1.00 0.55 Implementation of 0.58 6.23 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 2 Aroli 7.31 0.70 1.70 Implementation of 1.14 3.77 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 3 Athanur 8.36 1.00 0.55 Implementation of 0.58 6.23 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 4 Bagalawad 8.36 0.75 0.50 Implementation of 0.68 6.43 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 5 Ballatagi 8.36 0.75 0.50 Implementation of 0.68 6.43 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 6 Bhogavathi 7.41 0.75 1.75 Implementation of 1.60 3.31 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 7 Byagavata 8.36 0.70 0.70 Implementation of 0.48 6.48 Representatives. Aganawadi Childrens. Cultural Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 8 Chagabhavi 8.36 0.75 0.50 Implementation of 0.68 6.43 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 9 Chikkotnekal 8.44 0.95 0.58 Implementation of 0.68 6.23 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 10 Ganadinni 8.36 0.75 0.50 Implementation of 0.68 6.43 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 11 Gorkal 7.96 1.70 1.35 Implementation of 1.09 3.82 Representatives. Aganawadi Childrens. Commercial Complex. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of Health 12 Gudadinni .K. 8.36 0.75 0.50 Implementation of 0.68 6.43 Representatives. Aganawadi Childrens. Centre Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 13 Halapur 8.36 0.70 0.95 Implementation of 0.43 6.28 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of Library 14 Haravi 8.36 0.70 0.70 Implementation of 0.58 6.38 Representatives. Aganawadi Childrens. Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 15 Heera 8.36 0.75 0.70 Implementation of 0.68 6.23 Representatives. Aganawadi Childrens. Community Toilets. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 16 Hirahanagi 8.36 0.75 0.70 Implementation of 0.68 6.23 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 17 Hirekotnekal 8.36 1.70 1.75 Implementation of 1.16 3.75 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 18 Janekal 8.36 0.75 0.50 Implementation of 0.68 6.43 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 19 Kallur 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens . Aganawadi Building . Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 20 Kapgal 4.18 0.55 0.50 Implementation of 0.45 2.68 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 21 Kavithal 4.18 0.50 0.75 Implementation of 0.20 2.73 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 22 Kurdi 4.18 0.70 0.75 Implementation of 0.40 2.33 Representatives. Aganawadi Childrens. Community Toilets. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 23 Madagiri 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 24 Madlapur 4.18 0.55 0.50 Implementation of 0.45 2.68 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 25 Mallat 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 26 Nakkundi 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 27 Navalakal 4.18 0.70 0.50 Implementation of 0.45 2.53 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 28 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 29 Pamanakallur 4.18 0.40 0.75 Implementation of 0.20 2.83 Representatives. Aganawadi Childrens. Cultural Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 30 4.18 0.50 0.50 Implementation of 0.35 2.83 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 31 Sadapur 4.18 0.50 0.50 Implementation of 0.30 2.88 Representatives. Aganawadi Childrens . Cultural Building . Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 32 Sangapur 4.18 0.70 0.75 Implementation of 0.40 2.33 Representatives. Aganawadi Childrens. Lights. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Installation of Solar 33 Sirwar 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens. Lights. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 34 Sunkeshwar 4.18 0.55 0.50 Implementation of 0.45 2.68 Representatives. Aganawadi Childrens. Cultural Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 35 Toranadinni 4.18 0.50 0.50 Implementation of 0.35 2.83 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes.

Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of Libray 36 Utakanur 4.18 0.55 0.30 Implementation of 0.45 2.88 Representatives. Aganawadi Childrens. Building. Programmes. Total 223.40 25.90 23.58 20.91 153.01 ZILLA PANCHAYAT RAICHUR

Backward Region Grant Fund Action Plan 2009 - 10

Gram Panchayat Programmes

Taluk : RAICHUR

Sl. Name of the Total Programme Awareness Programme Amount Service Delivery Amount Amount Asset Creation Amount No. Gram Panchayat Allocation Management

Construction of 3.43 Supply of Playing Materials to Preparation & Cultural Building. Training to Elected Representatives, 1 Athkoor 8.36 0.55 Aganawadi Childrens & Supply of 0.55 Implementation of 0.25 Staffs & Tours for School Childrens . Equipments to Hospitals. Programmes. Construction of G.P. 3.58 Compound Wall.

Construction of Open 3.43 Supply of Playing Materials to Preparation & Theater at Baidoddi Training to Elected Representatives, 2 Baidoddi 8.36 0.65 Aganawadi Childrens & Supply of 0.55 Implementation of 0.25 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Construction of Open 3.48 Theater at Vadavatti

Construction of Cultural Building & 3.43 Supply of Playing Materials to Preparation & Training to Elected Representatives, G.P. Compound Wall. 3 Bichali 8.36 0.65 Aganawadi Childrens & Supply of 0.50 Implementation of 0.20 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Construction of Cultural Building at SC 3.58 Area at Bichali.

Construction of 2nd 3.43 Supply of Playing Materials to Preparation & floor of G.P. Building. Training to Elected Representatives, 4 Bijangera 8836.36 0065.65 Aganawadi Childrens & Supply of 0060.60 Implementation of 0020.20 Staffs & Tours for School Childrens. Construction of H.P. Equipments to Hospitals. Programmes. School Compound 3.48 Wall.

Construction of 3.43 Community Hall. Supply of Playing Materials to Preparation & Training to Elected Representatives, 5 Chandrabanda 8.36 0.65 Aganawadi Childrens & Supply of 0.60 Implementation of 0.23 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Construction of Compound Wall to 3.45 PHC at Chandrabanda. Construction of 3.43 Supply of Playing Materials to Preparation & Additionals Floor to GP Training to Elected Representatives, 6 Chicksugur 8.36 0.65 Aganawadi Childrens & Supply of 0.60 Implementation of 0.30 Staffs & Tours for School Childrens. Construction of Equipments to Hospitals. Programmes. Aganawadi Building at 3.38 Kukkanur. Construction of 3.43 Supply of Playing Materials to Preparation & Aganawadi Building. Training to Elected Representatives, 7 Devasugur 8.36 0.65 Aganawadi Childrens & Supply of 0.65 Implementation of 0.35 Staffs & Tours for School Childrens. Construction of Equipments to Hospitals. Programmes. Cultural Building 3.28 Compound Wall at Construction of G.P. 3.43 Supply of Playing Materials to Preparation & Compound Wall. Training to Elected Representatives, 8 Ganadhal 8.36 0.65 Aganawadi Childrens & Supply of 0.60 Implementation of 0.30 Staffs & Tours for School Childrens. Construction of School Equipments to Hospitals . Programmes. Compound Wall at 3.38 Ballapur. Construction of Additional Rooms for 3.43 Supply of Playing Materials to Preparation & Training to Elected Representatives, G. Panchayat. 9 Gillesugur 8.36 0.65 Aganawadi Childrens & Supply of 0.65 Implementation of 0.35 Staffs & Tours for School Childrens. Construction of Equipments to Hospitals. Programmes. Aganawadi Buidling at 3.28 Gillesugur Camp. Construction of Library 3.43 Supply of Playing Materials to Preparation & Building. Training to Elected Representatives, 10 Gunjalli 8.36 0.75 Aganawadi Childrens & Supply of 0.65 Implementation of 0.30 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Construction of School 3.23 Compound Wall.

Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of G.P. 11 Idapanur 8.48 0.65 Aganawadi Childrens & Supply of 0.30 Implementation of 0.55 6.98 Staffs & Tours for School Childrens. Compound Wall. Equipments to Hospitals. Programmes.

Construction of 3343.43 Supply of Playing Materials to Preparation & Aganawadi Buidling. Training to Elected Representatives, 12 Jagir 8.36 0.75 Aganawadi Childrens & Supply of 0.60 Implementation of 0.30 Staffs & Tours for School Childrens. Construction of Equipments to Hospitals. Programmes. Aganawadi Building at 3.28 Pattepur. Construction of School 3.43 Supply of Playing Materials to Preparation & Compound Wall. Training to Elected Representatives, 13 Jambaladinni 8.36 0.75 Aganawadi Childrens & Supply of 0.65 Implementation of 0.30 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Construction of School 3.23 Compound Wall. Construction of 3.43 Supply of Playing Materials to Preparation & Cultural Building. Training to Elected Representatives, 14 Jegarkal 8.36 0.65 Aganawadi Childrens & Supply of 0.60 Implementation of 0.35 Staffs & Tours for School Childrens. Construction of Equipments to Hospitals. Programmes. Cultural Building at 3.33 J.Timmapur. Construction of 3.43 Supply of Playing Materials to Preparation & Cultural Hall. Training to Elected Representatives, 15 Kadloor 8.36 0.75 Aganawadi Childrens & Supply of 0.65 Implementation of 0.35 Staffs & Tours for School Childrens. Construction of Equipments to Hospitals. Programmes. Additional Rooms for 3.18 G. Panchayat. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of 16 Kalmala 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Aganawadi Building. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & TiiTraining t tEltdRo Elected Represent ttiatives, CttifConstruction of 17 Kamlapur 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Community Building. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Linganakhana Training to Elected Representatives, Construction of School 18 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Doddi Staffs & Tours for School Childrens. Compound Wall. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Construction of Training to Elected Representatives, 19 Mamdapur 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 Additionals Class 3.43 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Rooms to School. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of 20 Manchlapur 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Community Building. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of Library 21 Marchathal 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Building. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Installation of Solar 22 Matmari 4.18 0.55 Aganawadi Childrens & Supply of 0.10 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Lights. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of School 23 Mitti Malkapur 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Compound Wall. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of Open 24 Purthipli 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Theater. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of Open 25 Sagamakunta 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Theater. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of Store 26 Shakhavadi 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Room. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of Library 27 Singanodi 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Building. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of School 28 Talmari 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Compound Wall. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of 29 Yadlapur 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Aganawadi Building. Equipments to Hospitals. Programmes. Supply of Playing Materials to Preparation & Training to Elected Representatives, Construction of Open 30 Yapaladinni 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 3.43 Staffs & Tours for School Childrens. Theater. Equipments to Hospitals. Programmes. SlfPliMtiltSupply of Playing Materials to Pti&Preparation & CttifUdhConstruction of Urdhu Training to Elected Representatives, 31 4.18 0.35 Aganawadi Childrens & Supply of 0.30 Implementation of 0.10 School Compound 3.43 Staffs & Tours for School Childrens. Equipments to Hospitals. Programmes. Wall. Total 192.40 15.85 13.35 6.18 157.02 ZILLA PANCHAYAT RAICHUR

Backward Region Grant Fund Action Plan 2009 - 10

Gram Panchayat Programmes

Taluk : SINDHANUR

Sl. Name of the Total Programme Awareness Programme Amount Service Delivery Amount Amount Asset Creation Amount No. Gram Panchayat Allocation Management Preparation & Construction of Training to Staffs & Public Supply of Playing Materials to 1 Alabanur 8.36 1.38 1.38 Implementation of 0.82 Additionals Class 4.78 Representatives. Aganawadi Childrens. Programmes. Rooms to School. Preparation & Construction of Training to Staffs & Public Supply of Play ing Materials to 2 Badarli 8368.36 1381.38 1381.38 Implementation of 0820.82 Additionals Class 4784.78 Representatives. Aganawadi Childrens. Programmes. Rooms to School. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 3 Balagnur 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Commercial Complex. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of Library 4 Bappur 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 5 .K 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Protection Wall. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of School 6 Bhootaladinni 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Compound Wall. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 7 Chennalli 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Commercial Complex. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 8 Devaragudi 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Commercial Complex. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 9 Dhadesugur 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 10 Goudanabhavi 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 11 Gonawara 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of Library 12 Gorebal 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Building. Programmes. Preparation & Construction of Training to Staffs & Public Supply of Playing Materials to 13 8.36 1.38 1.38 Implementation of 0.82 Additionals Class 4.78 Representatives. Aganawadi Childrens. Programmes. Rooms to School. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 14 Gunda 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Community Toilets. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of School 15 Gunjalli 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Compound Wall. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of School 16 Hosalli .E.J. 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Compound Wall. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 17 Jalihal 8.36 1.38 1.38 Implementation of 0.82 4.78 Representatives. Aganawadi Childrens. Commercial Complex. Programmes. Preparation & Construction of Training to Staffs & Public Supply of Playing Materials to 18 Javalgera 4.18 0.68 0.68 Implementation of 0.52 Additionals Class 2.30 Representatives. Aganawadi Childrens. Programmes. Rooms to School. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 19 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Commercial Complex. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 20 Kolbal 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 21 Madasirwar 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Community Toilets. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 22 Mukkunda 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Commercial Complex. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 23 Pagadadinni 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens . Aganawadi Building . Programmes. Preparation & Construction of Training to Staffs & Public Supply of Playing Materials to 24 R.H. Colony 4.18 0.68 0.68 Implementation of 0.52 Additionals Class 2.30 Representatives. Aganawadi Childrens. Programmes. Rooms to School. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 25 Ragalaparvi 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 26 Ramathnal 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 27 Roudakunda 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Community Toilets. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 28 Salagunda 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Community Toilets. Programmes. Preparation & Construction of Training to Staffs & Public Supply of Playing Materials to 29 Somalapur 4.18 0.68 0.68 Implementation of 0.52 Meeting Hall at GP 2.30 Representatives. Aganawadi Childrens. Programmes. Building. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 30 Tidigol 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 31 Turvihal 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Community Toilets. Programmes. Preparation & Construction of Training to Staffs & Public Supply of Playing Materials to 32 Uddbal ( U ) 4.18 0.68 0.68 Implementation of 0.52 Additionals Class 2.30 Representatives. Aganawadi Childrens. Programmes. Rooms to School. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 33 Umaloti 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Community Toilets. Programmes. Preparation & Training to Staffs & Public Supply of Playing Materials to Construction of 34 Virupapur 4.18 0.68 0.68 Implementation of 0.52 2.30 Representatives. Aganawadi Childrens. Aganawadi Building. Programmes. Total 213.18 35.02 35.02 22.78 120.36 Zilla Panchayat, Raichur.

BRGF Action Plan for the Year 2009 - 10

Urban Local Bodies Programmes

ABSTRACT

Sl. Total Awareness Service Programme Asset Name of Urban Local Bodies No. Allocation Programmes Delivery Management Creation 1 City Muncipal Council - Raichur 135.88 26.74 26.75 17.82 64.57 2 City Muncipal Council - Sindhanur 118.59 23.72 23.72 15.83 55.32 3 Town Muncipal Council - Manvi 86.97 17.42 16.71 11.85 40.99 4 Town Muncipal Council - Lingasugur 87.83 17.56 17.57 11.72 40.98 5 Town Muncipal Council - Deodurga 87.75 17.55 17.55 8.77 43.88 6 Pattana Panchayat - Mudugal 72.57 10.27 10.54 6.26 45.50

Total 589.59 113.26 112.84 72.25 291.24 CITY MUNICIPAL COUNCIL, RAICHUR.

BRGF Action Plan for the Year 2009 - 10

I. AWARENESS PROGRAMME Conduct of Program to the Public for Solid Waste Management through N.G.O. including IEC Materials. ( Door to door garbage collection segregation 1 14.05 of the garbage at source level etc ). Conduct of Study tour to councilors and important section heads regarding learning of Best Practices adopted in various other local bodies on the 2 matters of Solid Waste Managements, E - Governance, UGD, Water supply and other related obligatory functions discharging in at Ahamadabad, 7.50 Vijayawad, Mysore, HDMC, Suryaptet, Managalore and Sirapur in Haharastra Muncipal Corporations. 3 Conduct of Program to PK's for collection of the garbage from door to landfill site ( Reducing the multiple handing of garbage ) by the N.G.O.'s. 1.50 4 Conduct of Awareness Programmes by N.G.O. on Water Management to the Public. 2.19 Training to the Health and Engineering staff regarding Water treatment & garbage on UGD projects by identifying the resource person through ULB 5 1.50 including study tour on batches to health and engineering executive staff of Raichur CMC.

Total 26.74

II. SERVICE DELIVERY Imparting training to the existing Civil engineers to take up the development works under BRGF and various other ongoing development schemes to be 1 9.60 implemented by the Raichur CMC through identified Resource Persons as per rules. 2 Out - Sourcing of Computer Operator and Personal Assistants through Govt. agency Keonics for Data Entry and day - to - day Computer Work. 3.00 Conducting of Ministerials training classes such as new office procedures, foundation & orientation courses on the matters of KM Act, Municipal Manual 3 etc. Conduct of Guest Lecturers to the staff through Resource Persons, identifying the retired officers such as Muncipal Tahasiladars, Municipal 3.00 Commissioners. Providing Basic Computer courses to the Municipal Staff through Keonics either in the evening or in the morning to enable Computer Education so as to 4 2.25 improve the standards of working capacity. Earmaking of funds, identification of training institutes, selection of applicants for conducting of coaching classes to the aspirants of KPSC / UPSC 5 1.50 Competitive Exam. 6 Pilot training for Unemployed brilliant youths by selecting suitable recognized training institutes. 2.40 7 Establishments of Component Thephy Unit at District Hospitals. 5.00

Total 26.75

III. PROGRAMME MANAGEMENT 1 Providing and fixing of Bio - Metric Instrument for attendance of employee and generation of pay - roll including arrear bills, leave account of municipal. 7.61 2 Providing training to the municipal staff on account matters of FBAS system. 3.00 Procurement of Office automation peripherals such as Computer, Scanners, Copier, Fax Machines, Printers and strengthening of Record's section and 3 3.00 maintenance by opening separate cell. 4 Obtaining technical know how from the prestigious institutions to upgrade the services standards of CMC, Raichur in the matters of Information. 4.21

Total 17.82 IV. ASSET CREATION

1 Construction of Community Hall and Library at Harijan Ward. 11.00 2 Construction of Library in 1st floor at Mangalwarpet. 12.00 3 Construction of Tin Shed at Ambedkar Bhavan, Jahirabad. 15.00 4 Construction of Ambedkar Samodaya Bhavan at Amba Bhavani Street. 6.57 5 Construction of Babu Jaga Jivan Ram Building & Compound Wall. 20.00

Total 64.57

Grant Total 135.88 CITY MUNICIPAL COUNCIL, SINDHANUR.

BRGF Action Plan for the Year 2009 - 10 I. AWARENESS PROGRAMME 1 To conduct awareness programme regarding Health, Sanitation, Agriculture and Horticulture for Public & Staff. 1.00 2 Continuation of Women Literacy Programme. 1.00 3 To conduct training programmes for different department staff on important subjects like Computer training etc. 2.00 To conduct training programmes for unemployed youths regarding Electronics, Electrical, Fabrication, Automobile, Production, Manufacturing, 4 2.00 Computer Training etc. 5 To conduct teaching & Mock Exam ( SSLC ). 1.72 6 To conduct training for Self Help Group members regarding Tailoring, Embroidary, Segregation of Food, production & Marketing. 3.00 7 Tour Programme regarding study of developments. 13.00 Total 23.72

II. SERVICE DELIVERY 1 Training for Skill Developments & Providing of Kits. 1.00 2 Appointment of Barefoot Engineers. 1.00 3 Providing Water Supply to SC / ST Colonies. 1.72 4 Providing of Water Steam Cooker, Solar Water Heater for SC / ST & BCM Hostels. 1.00 5 Providing essential equipments for Hospitals. 1.00 6 Providing Water Supply to High Schools. 1.00 7 Maintenance of Public Toilets. 12.00 8 Establishment of Component Thephy Unit at District Hospital. 5.00 Total 23.72

III. PROGRAMME MANAGEMENT 1 Conducting Workshops. 10.00 2 Preparation of Action Plans. 2.00 3 Implementating & Supervision of Programmes. 2.00 4 Monitoring & Evaluation. 1.83 Total 15.83

IV. ASSET CREATION 1 Proposed construction of High Tech Ladies Toilet at Ward No. 03 & 04. 10.00 2 Proposed construction of High Tech Ladies Toilet at Ward No. 05. 10.00 3 Proposed construction of High Tech Ladies Toilet at Ward No. 12. 10.00 4 Proposed construction of High Tech Ladies Toilet at Ward No. 15. 10.00 5 Improvements to Adishesha Ancient Temple. 5.82 6 Providing of Solar Street Lights. 9.50 Total 55.32 Grant Total 118.59 TOWN MUNICIPAL COUNCIL, LINGASUGUR.

BRGF Action Plan for the Year 2009 - 10

I. AWARENESS PROGRAMME 1 Awareness Programme about Health & Sanitation to Elected Members & Public. 6.00 2 Different training programmes to SHG Members. 5.71 3 Training to unemployed students about Electrical, Electronics, Decoration, Automobile & Computers. 5.85

Total 17.56

II. SERVICE DELIVERY 1 Appointment of Bare Foot Engineers. 3.71 2 Providing Water Supply facilities to SC / ST Colonies. 4.00 3 Solid Waste Management & Computer Training. 5.86 4 Establishment of Component Thephy at District Hospital. 4.00

Total 17.57

III. PROGRAMME MANAGEMENT 1 Conducting Workshop about General Subject to Public. 11.72

Total 11.72

IV. ASSET CREATION 1 Construction of Compound Wall to Santhe Bazaar in Lingasugur Town. 29.27 2 Development of Garden in Lingasugur Town. 11.71

Total 40.98

Grant Total 87.83 TOWN MUNICIPAL COUNCIL, DEODURGA. BRGF Action Plan for the Year 2009 - 10

I. AWARENESS PROGRAMME 1 Awareness Training Programmes for Elected Members & Study Tours. 4.55 2 Remedial Teaching & Mock Exam ( SSLC ). 3.00 3 Awareness Training Programmes for Agriculture, Horticulture & Health. 4.00 4 Computer Training Programmes for Physical Handicaps & Unemployed Youths. 3.00 5 Women Literacy Camps. 3.00

Total 17.55

II. SERVICE DELIVERY 1 Skill Development Programmes & Kits. 3.00 2 Bare Foot Engineers appointment. 2.00 3 Installation of Web - Site. 3.00 4 Water Supply facility to High Schools. 3.55 5 Supply of Equipments to Hospitals. 2.00 6 Establishment of Component Thephy Unit at District Hospital. 4.00

Total 17.55

III. PROGRAMME MANAGEMENT 1 Preparation of Plan, Monitering & Evaluation. 8.77

Total 8.77

IV. ASSET CREATION 1 Construction of Samudaya Bhavana at Choudi Katti in Tilak Street. 12.00 2 Construction of Vegetable stalls at Malegadda. 10.00 3 Construction of Hi - Tech Toilet block at Goutam Street in Ward No. 09. 10.00 4 Construction of Samudaya Bhavana at various doddis in Deodurga Town. 11.88

Total 43.88

Grand Total 87.75 TOWN MUNICIPAL COUNCIL, MANVI.

BRGF Action Plan for the Year 2009 - 10

I. AWARENESS PROGRAMME 1 Organising Literacy Camps to the Women below 50 % illiteracy area. 2.00 2 Organising Skill Development Programme to the TMC Councillors about ADB Scheme and Model Municipal Development Tour Programme for studies. 3.71 3 Awareness Programme to School children about Health, Sanitation & SWM Programme. 3.00 4 Remedial Teaching & Mock Exam. 2.00 5 Awareness Programme to Public about Government Schemes. 0.71 6 To implement Government Schemes by advertising i.e. Name Boards etc. 2.00 7 Training Programme to Unemployment Youths like Electricals, Publication, Automobile, Computer Training etc. 2.00 8 Training Programme to Senior Citizens. 2.00 Total 17.42

II. SERVICE DELIVERY 1 Supplying of Training Kits to the Trained Persons. 2.00 2 Drilling of Borewells and Fixing of Cisterns in SC / ST Area. 3.00 3 Arrangements of Drinking Water to the Primary / High Schools. 2.00 4 Purchase of Generator. 3.00 5 Construction of Aganawadi School Building in Ward No. 04 & 05 & Other Wards. 2.71 6 Establishment of Component Thephy Unit at District Hospital. 4.00 Total 16.71

III. PROGRAMME MANAGEMENT 1 Training Programme. 2.00 2 Preparation of Action Plan to Water Supply Distribution System in Manvi Town. 6.00 3 Arranging training programme & supervising. 2.00 4 Implemention of evaluation. 1.85 Total 11.85

IV. ASSET CREATION 1 Construction of RCC drains & CC roads in different wards at Manvi Town. 25.00 2 Construction of RCC drains in different wards at Manvi Town. 11.71 3 Construction of Anganawadi School Buildings in different wards at Manvi Town. 4.28 Total 40.99

Grand Total 86.97 PATTANA PANCHAYAT, MUDAGAL.

BRGF Action Plan for the Year 2009 - 10

I. AWARENESS PROGRAMME 1 Awareness Programmes for Public Health. 1.50 2 IEC Activity. 1.27 3 Study Tour for Elected Members. 4.00 4 Organising Study Tour for Elected Members. 3.50

Total 10.27

II. SERVICE DELIVERY 1 Skill Development Programmes. 2.77 2 Plantering of Trees. 1.00 3 Providing Nutritution Food to Pregant Women. 1.00 4 Maintainance of Toilets. 2.00 5 Providing Basic Infrastructure for Aganawadi Buildings. 0.77 6 Establishment of Component Thephy Unit at District Hospital. 3.00

Total 10.54

III. PROGRAMME MANAGEMENT 1 Preparation of Plan, Monitoring & Evaluation. 6.26

Total 6.26

IV. ASSET CREATION 1 Construction of CC Pavament & Sepage Cannel in front of Town Panchayat. 16.91 2 Construction of High Tech Toilets at Killa. 13.53 3 Construction of CC Pavament at Vegetable Market in Mudgal Town Panchayat. 15.06

Total 45.50

Grant Total 72.57