MONTHLY ENVIRONMENTAL MONITORING & AUDIT REPORT

Highways Department

Route 8 Between and – Phase 2a and West Tsing Yi Viaduct: Monthly Environmental Monitoring & Audit Report (29th May – 28th June 2004)

Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Monthly EM&A Report – June 2004

TABLE OF CONTENTS

EXECUTIVE SUMMARY ...... ES1 1 INTRODUCTION...... 1 1.1 Purpose of the Report ...... 1 1.2 Structure of the Report...... 1 2 PROJECT INFORMATION...... 2 2.1 Background...... 2 2.2 Site Description...... 2 2.3 Project Organisation ...... 2 2.4 Project Work Programme ...... 2 3 ENVIRONMENTAL MONITORING REQUIREMENTS...... 3 3.1 Air Quality ...... 3 3.2 Noise Quality ...... 5 4 IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION REQUIREMENTS...... 7 5 ENVIRONMENTAL LICENCE AND PERMITTING REQUIREMENTS ...... 7 6 MONITORING RESULTS...... 8 6.1 Air Quality ...... 8 6.2 Noise ...... 9 7 AUDIT RESULTS...... 10 7.1 Air Quality ...... 10 7.2 Noise ...... 10 7.3 Water Quality...... 11 7.4 Waste Management...... 12 7.5 Site Audit / Inspection ...... 13 8 ENVIRONMENTAL NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND PROSECUTIONS...... 14 8.1 Summary of Environmental Non-Compliance ...... 14 8.2 Summary of Complaints ...... 15 8.3 Summary of Notification of Summon and Prosecution...... 15 9 FUTURE KEY ISSUES...... 15 9.1 Key Issues for the Coming Month...... 15 9.2 Monitoring Schedule for the Coming Three Months...... 16 10 RECOMMENDATIONS AND CONCLUSIONS...... 16 10.1 Conclusions...... 16 10.2 Recommendations...... 17

 L Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

LIST OF TABLES

Table 2.1 Major Site Activities undertaken during the Reporting Period (Normal Hours) Table 2.2 Major Site Activities undertaken during the Reporting Period (Restricted Hours) Table 3.1 TSP Monitoring Parameter and Frequency Table 3.2 TSP Monitoring Locations Table 3.3 Air Quality Monitoring Equipment Table 3.4 Noise Monitoring Frequency and Parameters Table 3.5 Location of the Noise Monitoring Stations Table 3.6 Noise Monitoring Equipment Table 6.1 Summary of 1-hour TSP Impact Monitoring Results Table 6.2 Summary of 24-hour TSP Impact Monitoring Results Table 6.3 Summary of Corrected Impact Noise Levels for Normal Hour Monitoring Table 6.4 Summary of Corrected Impact Noise Levels for Restricted Hour Monitoring Table 7.1 Summary of Waste Disposal during the Reporting Period Table 8.1 Summary of Non-Compliance for the Reporting Period Table 8.2 Summary of Total Complaint Received

LIST OF APPENDICES

Appendix A Site Location Plan Appendix B Project’s Environmental Organization Chart and Contact Details Appendix C Three Months Rolling Programme Appendix D1 Action/Limit Levels for Air Quality Appendix D2 Action/Limit Levels for Noise Appendix E Environmental Monitoring Schedule for the Reported Period Appendix F Locations of Monitoring Stations Appendix G1 Calibration Certificates for HVS Appendix G2 Calibration Certificate for the Weather Station Appendix G3 Calibration Certificates for High Volume Orifice Calibrator Appendix G4 Calibration Certificates for Sound Level Meter and Calibrator Appendix H1 Event/Action Plan for Air Quality Appendix H2 Event/Action Plan for Noise Appendix I Implementation Status of Environmental Protection Requirements Appendix J 1-hour and 24-hour TSP Monitoring Results Appendix K Graphical Presentation of 1-hour and 24-hour TSP Monitoring Results Appendix L Weather Condition during Impact Monitoring Appendix M1 Noise Monitoring Results for Normal Hour Appendix M2 Noise Monitoring Results for Restricted Hour Appendix N1 Graphical Presentation of Noise Monitoring Results for Normal Hour Appendix N2 Graphical Presentation of Noise Monitoring Results for Restricted Hour Appendix O1 Environmental Complaint Log Book Appendix O2 Cumulative Statistics for Environmental Complaint Appendix P Tentative Environmental Monitoring Schedule for the Next Three Months Appendix Q Photographic Records of Implemented Measures Appendix R Summary of Environmental Licensing, Notification and Permit Status

 LL Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

EXECUTIVE SUMMARY

ES 1 This is the eleventh monthly Environmental Monitoring and Audit (EM&A) Report for the Project HY/2001/16 - Route 8 Nam Wan Tunnel and West Tsing Yi Viaduct. The construction commencement of this Project was on 21st August 2003 and this report presents the results of the EM&A works conducted during the period between 29th May and 28th June 2004 in accordance with the EM&A Manual which forms part of the EIA Report (Register No. AEIAR-018/1999).

ES 2 The major construction activities carried out on site during normal hours are as follows: i. Pre-bored H-pile construction ii. Piers and decks construction iii. Retaining wall construction iv. Drainage installation v. Soil nail vi. Tunnel blasting vii. Rock Crushing Plant Operation

ES 3 The major construction activities carried out on site during evening and night time (restricted hours) are as follows: i. Rock tipping (West Portal) ii. Soil nail (East Portal)

ES 4 Monitoring of Total Suspended Particulates (TSP) and Noise were carried out in accordance with the Project’s EM&A Manual. The Environmental Team (ET) site audits were conducted on 3rd, 10th, 17th and 25th June 2004 and the joint IEC monthly audit was conducted on 25th June 2004.

Air Quality ES 5 For 1-hour TSP monitoring, a total of 72 sets of measurement were carried out during the reporting period and all were below the Action/Limit (AL) Levels. For 24-hour TSP monitoring, a total of 20 sets of measurements were carried out during the reporting period and all were below the Action/Limit (AL) Levels.

Noise Daytime Monitoring

ES 6 A total of 16 sets of Leq(30min) measurement during daytime (0700 to 1900 hours on normal weekdays) were carried out during the reporting period and one exceedance of the Limit Level was recorded and a Notification of Exceedance has subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigation was carried out and it was concluded that exceedance was not contributed by the Route 8 construction activities and therefore corrective action was not considered necessary.

Evening-time Monitoring

ES 7 A total of 16 sets of 6 x Leq(5min) measurement during evening-time (1900 to 2300 hours on normal weekdays) were carried out at all monitoring locations and several exceedances of the Limit Level were recorded and Notifications of Exceedance have subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigations were carried out and were concluded that exceedances were not contributed by the Route 8 construction activities and therefore corrective action was not considered necessary.

Night-time Monitoring

ES 8 A total of 16 sets of 4 x Leq(5min) measurement during night-time (2300 to 0700 hours next day) were

 ES1 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

carried out at all monitoring locations and several exceedances of the Limit Level were recorded and Notifications of Exceedance have subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigations were carried out and were concluded that exceedances were not contributed by the Route 8 construction activities and therefore corrective action was not considered necessary.

Public-Holiday Monitoring

ES 9 A total of 20 sets of 6 x Leq(5min) measurement during public holiday (i.e. 0700 to 1900 hours on public holiday) were carried out at all monitoring locations and several exceedances of the Limit Level were recorded and Notifications of Exceedance have subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigations were carried out and were concluded that exceedances were not contributed by the Route 8 construction activities and therefore corrective action was not considered necessary.

Water Quality ES 10 In accordance with the approved Effluent Discharge License (EP742/351/0207I) conditions, water sampling is required on a monthly basis. Two water samples were taken on 11th June 2004 (one at the East Portal Wet-Sep, one at the West Portal Wet-Sep) for Total Suspended Solid (TSS) analysis. The results showed that they have fully complied with the Specific Condition as stipulated in the approved license. On 29th April 2004, EPD has confirmed that an Effluent Discharge License is not required for P2-SA12.

Waste Management ES 11 The Waste Management Plan (WMP) was approved by EPD on 7th January 2004 and it is currently being updated by GSIJV. GSIJV will submit the revised WMP by the end of June to ER, ET and IEC for comment.

ES 12 Since 21st August 2003, all non-inert C&D material from the Contract has been disposed of at NENT and WENT Landfill. 81.22 tonnes of general refuse was delivered to WENT and 9.45 tonnes were delivered to NENT during the reporting period. In addition 39102.8 tonnes (3422 trucks) of good quality rock was delivered to Lam Tei Quarry and 49411.7 tonnes (4332 trucks) of low quality rock was delivered to P2-SA12. 219 trucks (approximately 1314m3) and 450 trucks(approximately 2700 m3) of inert C&D material were delivered to designated public filling area namely Kai Tak Barging Point and Widening Project respectively.

ES 13 During this reporting period, 800 litres of chemical waste was disposed off site. Approximately 5m3 of C&D waste was reused, recycled, returned and 0.75m3 office paper was recycled during the reporting period.

Site Audits / Inspections ES 14 ET weekly site audits were carried out on 3rd, 10th, 17th and 25th June 2004 and the major findings are presented below:

Item Findings GSIJV’s Corrective and Effectiveness of measures Preventive measures 1 Dust generated from vehicle Water spraying has been Haul road watering should be movement was observed during increased and the dust on haul increased especially during hot the site audit. GSIJV was road has been cleaned up and dry conditions. reminded to increase the regularly to avoid dust frequency of watering to emission. minimize dust impact. 2 Mud and sand was found in u- The u-channels at area P2- U-channels have been cleaned

 ES2 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

Item Findings GSIJV’s Corrective and Effectiveness of measures Preventive measures channels at area P2-SA1 (CT5) SA1 (CT5) and the East Portal up, GSIJV was reminded that and the East Portal. have been cleaned up. effective preventive measures should be provided at CT5, e.g. tarpaulin covering after maintenance. (Please refer to Appendix Q, Photo 01) 3 Insufficient temporary drainage The temporary drainage GSIJV was reminded to and provision of run-off control system at P2-SA12 is implement the whole temporary and desilting facilities at P2- currently under construction. drainage system at SA12 as SA12. GSIJV was urged to The revised drainage proposal soon as possible. (Please refer implement the temporary is under certification by ICE to Appendix Q, Photo 02) drainage system on site at P2- and will be submitted once it SA12 and submit the revised is available. proposal without delay. Rubble bund has been constructed along boundary next to CLP site, concreting will also be applied for the rubble bund to ensure no seepage of water into the CLP site. 4 Dust control should be provided Tarpaulin sheeting and Measures are effective. GSIJV for the soil nail construction at watering have been applied. was reminded that such the East Portal (zone 4). measures should be maintained properly at all times during soil nail operation. 5 Inadequate watering was The stockpiles of dusty Adequate water hose and water observed for the stockpiles at for materials at area P2-SA12 has sprinklers have been provided P2-SA12. been sprayed with water for the access road of P2-SA12. The facilities and frequency of watering should be further increased. (Please refer to Appendix Q, Photo 03) 6 Significant amount of mud and The stagnant water GSIJV was reminded that mud stagnant water accumulated next accumulated has been should be removed as soon as to the sandbag barrier at the East removed. Mud has been possible. Portal (entrance) was observed. fenced off by sandbag barrier to avoid spillage to nearby area.

ES 15 The monthly IEC audit was carried on 25th June 2004 and two findings were recorded and are presented below.

Item Findings GSIJV’s Corrective and Effectiveness of measures Preventive measures 1 Deposited silt accumulated in U-channels have been Completed and closed. the u-channel was found at the maintained weekly and after (Please refer to Appendix Q, East Portal, GSIJV was rainstorm. Photo 04) reminded to clean after the rainstorm has been subsided to ensure the facilities are functioning properly. 2 GSIJV was reminded to Please refer to ES13 Item 3. Please refer to ES13 Item 3. implement the surface runoff control system at P2-SA12. Sand bag barrier should be

 ES3 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

Item Findings GSIJV’s Corrective and Effectiveness of measures Preventive measures provided along the fencing of CLP site to prevent any surface runoff overflowing from P2- SA12.

ES 16 EPD inspection was carried on 7th June 2004 and two reminders were recorded and are presented below.

Item Findings GSIJV’s Corrective and Effectiveness of measures Preventive measures 1 For area P2-SA1 adjacent to The frequency of watering Completed and closed. (Please , EPD by water bowser has been refer to Appendix Q, Photo 05) raised their concern on the dust increased to maintain the emission generated from the haul road in moist condition vehicular movement. Water at all times. bowsers, hoses should be provided to maintain the haul road in moist condition at all times. 2 For the West Portal, sufficient Water sprinklers have been Completed and closed. (Please water sprinklers and hoses used at all times for dust refer to Appendix Q, Photo 06) should be provided for the suppression in the temporary handling of temporary stockpile rock stockpiling area. within the site area to ensure dust emission from construction activities is kept to an absolute minimum.

ES 17 EPD inspection on the Rock Crushing Plant at P2-SA12 was carried out on the 9th June 2004. Plant facilities and location of High-Volume Air Sampler were inspected and recommendations were provided by EPD to the Specified Process License (SPL) holder (sub-contractor) to further improve the facilities to comply with EPD guidelines, regulations and License conditions.

Environmental Licensing and Permitting

ES 18 Environmental permits/registration/licenses granted to the Project for the entire period of the Contract includes Environmental Permit (EP-085/2000C) and Chemical Waste Producer Registration. Other valid permits and licenses during the reporting period include 1 no. Waste Water Discharge License, 16 no. Construction Noise Permits and a Specified Process License for Rock Crusher Plant.

Complaint Log

ES 19 No environmental complaint was received during the reporting period. A total of 2 no. complaints have been received for the Project since the commencement of the construction.

Notification of Summons and Prosecutions ES 20 No notification of summons and prosecutions regarding non-compliance of environmental performance of the construction site was received during the reporting period and since the commencement of construction.

Future Key Issues

 ES4 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

ES 21 The tentative program of major site activities as well as the impact prediction and control measures for the coming three months, i.e. July 2004 to September 2004 are summarized as follows:

Construction Major Impact Control Measures Works Prediction Pier and deck Air impact (dust) i) Frequent watering of haul road and unpaved/exposed areas; constructions, ii) Frequent watering or covering stockpiles with tarpaulin or similar sub-soil means; and drainage works, iii) Watering of any earth moving activities. tunnel blasting, soil nail installation, cascade construction and Rock Crushing Water quality iv) Diversion of the collected effluent to de-silting facilities for Plant operation. impact (muddy treatment prior to discharge to public storm water drains; run-off) v) Provision of adequate de-silting facilities for treating surface run-off and other collected effluents prior to discharge; vi) Provision of perimeter protection such as sealing of hoarding footings to avoid run-off from entering the existing storm water drainage system via public road; and vii) Provision of measures to prevent discharge into the stream. Noise Impact vii) Scheduling of noisy construction activities if necessary to avoid persistent noisy operation; viii) Controlling the number of plants use on site; ix) Regular maintenance of machines; and x) Use of acoustic barriers if necessary.

 ES5 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

1 INTRODUCTION

Under the requirements of Section 4 of Environmental Permit EP085/2000/C, EM&A programme is required to be implemented as set out in the Environmental Monitoring and Audit (EM&A) Manual which forms part of the EIA Report (Register No. AEIAR-018/1999) for Route 8 Nam Wan Tunnel and West Tsing Yi Viaduct Phase 2a – (hereinafter called the “Project”).

1.1 Purpose of the Report The construction commencement date of this Project was on 21st August 2003. This is the eleventh monthly EM&A report which presents the results and findings of all EM&A works for the Project between 29th May 2004 and 28th June 2004. 1.2 Structure of the Report The structure of the report is as follows: Section 1: INTRODUCTION – details the scope and structure of the report. Section 2: PROJECT INFORMATION – summarizes the background and scope of ʳ the project, project organization, construction programme and the construction works undertaken during the reporting period. Section 3: ENVIRONMENTAL MONITORING REQUIREMENTS – summarizes ʳ the monitoring programmes, Action and Limit Levels, Event Action Plans, environmental mitigation measures as recommended in the EIA Report and relevant environmental requirements. Section 4: IMPLEMENTATION STATUS ON ENVIRONMENTAL ʳ PROTECTION REQUIREMENTS – summarizes the implementation of environmental protection measures during the reporting period. Section 5: ENVIRONMENTAL LICENCE AND PERMITTING ʳ REQUIREMENTS – summarizes the environmental licences and permits obtained or being applied during the reporting period. Section 6: MONITORING RESULTS – reports the monitoring results obtained in the reporting period. Section 7: AUDIT RESULTS – summarizes the audit findings in the reporting period. Section 8: COMPLAINTS, NOTIFICATIONS OF SUMMONS AND ʳ PROSECUTIONS DURING THE REPORTING PERIOD – summarizes the complaints, notifications of summons and prosecutions recorded during the reporting period. Section 9: FUTURE KEY ISSUES – summarizes the future key issues as reviewed from the works programme and work method statements. Section 10: RECOMMENDATIONS AND CONCLUSIONS

 1 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

2 PROJECT INFORMATION

2.1 Background

2.1.1 The Ove Arup and Partners Ltd (Arup) was awarded the Design and Construction Consultancy Assignment “Agreement No. CE72/98 R9T between Tsing Yi and Cheung Sha Wan”. 2.1.2 The construction of the Phase 2a of the Route 8 project, “HY/2001/16 – Route 8 Nam Wan Tunnel and West Tsing Yi Viaduct” comprises of the West Tsing Yi Viaduct and the Nam Wan Tunnel was awarded to Gammon Skanska International Joint Venture on 23rd April 2003 and is scheduled to be completed in 2007. 2.1.3 The Works under the contract covers a 1.2 km highway tunnel in Tsing Yi Island, with two parallel tunnel tubes, each with three lanes. It will form part of the Route 8 and provides linkage between the eastern part of the and the International Airport. The Works also include 1.4 km West Tsing Yi Viaduct linking to the existing Cheung Tsing Highway.

2.2 Site Description 2.2.1 Four sensitive receivers have been identified in the EIA; three residential areas and one school, all located on the east side of Tsing Yi Island. Two monitoring stations are located at the Tsing Yi Hong Kong Institute of Vocational Education (IVE) in the Main Education Building and Fok Ying Tung Hall of Residence, one at Mayfair Gardens and the other at Cheung Ching Estate. The site location plan and the monitoring locations are presented in Appendix A and F respectively.

2.3 Project Organisation 2.3.1 The project organization chart and contact details are shown in Appendix B.

2.4 Project Work Programme 2.4.1 The Project’s Three Months Rolling Programme is presented in Appendix C. The major site activities undertaken during the normal hours and restricted hours in reporting period are summarized in Table 2.1 and Table 2.2 respectively. Table 2.1 Major Site Activities undertaken during the Reporting Period (Normal Hours) Area Details of Site Activities P2-SA1 Site formation, pre-bored H-pile construction and Pier construction Retaining wall and reinforced earth wall erection P2-SA1A Drainage installation P2-SA2 Drainage installation, piers construction and in-situ deck construction P2-SA3 No works were carried during this reporting period P2-SA4 Tunnel blasting for Westbound and Eastbound Tunnels P2-SA6A Soil nails installation, mini pile for check dams, boulder stabilization and rock slope trimming for tunnel portal P2-SA6E Utility trough construction, soil nail installation and cascade construction P2-SA12 Rock crushing plant operation

 2 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

Table 2.2 Major Site Activities undertaken during the Reporting Period (Restricted Hours) Area Details of Site Activities P2-SA4 Rock Tipping (evening and night time) P2-SA6A Soil Nail (evening and night time)

3 ENVIRONMENTAL MONITORING REQUIREMENTS

3.1 Air Quality 3.1.1 Monitoring Requirements In accordance with the Project’s EM&A Manual 1-hour and 24-hour Total Suspended Particulates (TSP) are required to be conducted to monitor the construction dust impact. The established Action/Limit Levels for the environmental monitoring works are presented in Appendix D1.

3.1.2 Monitoring Frequency and Schedule The monitoring parameters and frequency are summarized in Table 3.1. The monitoring schedule for the reporting period is presented in Appendix E. Table 3.1 TSP Monitoring Parameter and Frequency Parameters Duration / hour Frequency 24-hour TSP 24 Once Every Six Days 1-hour TSP 1 Three Times Every Six Days

3.1.3 Monitoring Locations In accordance with the EM&A Manual, four air quality monitoring locations were selected. The four monitoring locations are listed in Table 3.2 and are presented in Appendix F. Table 3.2 TSP Monitoring Locations Location I.D. Description HK Institute of Vocational Education-Tsing Yi ASR1 Fok Ying Tung Hall of Residence HK Institute of Vocational Education-Tsing Yi ASR2 5th Floor Block D of the Main Education Building

ASR3 Mayfair Gardens 1st Floor adjacent to Swimming Pool

ASR4 Cheung Ching Estate At Roof of Ching Yung House (25/F)

A designated permanent wind monitoring station for the Project has been setup up at the East Portal for logging wind speed and wind direction since 11th March 2004.

3.1.4 Monitoring Equipment i. Continuous 24-hour and 1-hour TSP air quality monitoring was performed using a TE- 5170 Tisch Environmental Inc. High Volume Sampler (HVS), which was installed at the monitoring stations. The sampler composed of a motor, filter holder, flow controller and a sampling inlet. Its performance specification complies with that

 3 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).

ii. Details of the monitoring equipment are given in Table 3.3. A copy of the calibration certificate for the HVS and wind data monitor are attached in Appendix G1 and Appendix G2 respectively.

Table 3.3 Air Quality Monitoring Equipment Equipment Model Qty. HVS Sampler TE-5170 Tisch Environmental Inc. 4 Calibrator TE-5028A Tisch Environmental Inc. 1

3.1.5 Monitoring Procedures and Calibration Details i. Calibration Procedures - Calibration procedures of HVS are as follows (calibration certificates are presented in Appendix G3) : a. A certified orifice transfer standard with a calibration curve was used for the calibration. b. The transfer standard was connected to the inlet of the sampler. The orifice manometer was then connected to the orifice pressure port. The manometer’s connecting tubing was inspected to make sure that there are no leaks between the orifice unit and the sampler. c. The motor was then disconnected from the flow controller and plugged directly to an AC power source. d. A weather station has been setup at the Site Office to measure and record the ambient temperature, Ta (K) and the barometer pressure Pa (mmHg) during calculation. e. The sampler was allowed to run for at least 2 minutes to re-establish the run temperature conditions. The pressure drop across the orifice and the well-type manometer reading was recorded during calibration. The variable resistance was adjusted to repeat recording for four different flow rates. f. The best fit straight line was determined by linear regression and the slope (m1), intercept (b1) and correlation coefficient (r) are then determined.

ii. Operating/Analytical Procedure a. The flow rate of the high volume sampler was set to about 1.1 m3/min - 1.7 m3/min prior to commencement of the dust sampling in accordance with the manufacturer's instruction to within the range recommended in USEPA Standard Title 40, CFR Part 50. b. The samplers was located such that: b.1 the filter was about 1.3 meters above ground. b.2 it was greater than 20 meters away from trees. b.3 it was separated from any obstacle by at least twice the height of the obstacle protruding above the sampler. b.4 it has unrestricted airflow 270° around the sampler. c. Fiberglass filters were used for TSP sampling (G810) [Note: these filters have a collection efficiency of > 99% for particles of 0.3 mm diameter. d. All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment has a temperature setting between 25°C and

 4 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

30°C and should not vary by more than ±3°C; the relative humidity was < 50% and should not vary by more than ±5%. e. A new filter was placed with stamped number upward on a supporting screen. f. The filter was properly aligned on the screen so that the gasket formed an air-tight seal on the outer edges of the filter. g. Shelter lid closed and catch secured with the aluminum strip. h. The sampler was then allowed to run for at least 5 minutes to establish run- temperature conditions. i. The flow indicator reading was recorded and the sampler flow rate was determined. j. The programmable timer was set and the starting sampling time, weather condition and the filter number was recorded. k. At the end of sampling, the filter was transferred from the filter holder of the HVS to a sealable plastic bag and sent to the laboratory for weighing. The elapsed time was also recorded. l. Before weighing, all filters were equilibrated in a desiccator for 24 hours with temperature of 25°C±3°C and the relative humidity (RH) 50%±5%, preferably 40%.

iii. Maintenance a. The high volume sampler and their accessories were maintained in good working condition, include replacing motor brushes routinely and checking electrical wiring to ensure continuous power supply. b. The high volume samplers were calibrated at bi-monthly intervals using TE-5028A Tisch Environmental Inc. Calibration Kit throughout all stages of the air quality monitoring.

3.1.6 Event/Action Plan The Event/Action Plan for Air Quality is presented in Appendix H1.

3.2 Noise Quality 3.2.1 Monitoring Requirements Noise monitoring was conducted at four monitoring stations to monitor the construction noise impact. Appendix D2 presents the established Action/Limit Levels for the environmental monitoring works. 3.2.2 Monitoring Frequency and Schedule The monitoring schedule is presented in Appendix E and the frequency and parameters of noise measurement are summarized in Table 3.4. Table 3.4 Noise Monitoring Frequency and Parameters Time Period Duration / min. Parameters Frequency Daytime 30 Leq, L90 & L10 Once per week (0700 to 1900) (6 consecutive Leq(5min) in average) *Evening 5Leq,L & L Six times per week (1900 to 2300) 90 10 *Night (2300 to 0700 5Leq,L90 & L10 Four times per week next day)

 5 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

*Holiday (0700-1900 on 5 Leq, L90 & L10 Six times per week holidays) * Restricted hour noise monitoring: to be conducted only when there is construction work under valid CNP.

3.2.3 Monitoring Locations In accordance with the EM&A Manual, four noise monitoring locations (as detailed in Table 3.5 and presented in Appendix F) were selected for noise measurement. Table 3.5 Location of the Noise Monitoring Stations Location I.D. Description Type of measurement HK Institute of Vocational Education-Tsing Yi NSR1 Free Field Fok Ying Tung Hall of Residence HK Institute of Vocational Education-Tsing Yi NSR2 Free Field 5th Floor Block D of the Main Education Building Mayfair Gardens NSR3 Free Field 1st Floor adjacent to Swimming Pool Cheung Ching Estate NSR4 Free Field At Roof of Ching Yung House (22/F)

3.2.4 Monitoring Equipment Integrating Sound Level Meters were used for noise monitoring which were Type 1 sound level meters capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Also, a portable electronic wind speed indicator capable of measuring wind speed in m/s was used to monitor the wind speed. Table 3.6 summarizes the noise monitoring equipment required. Table 3.6 Noise Monitoring Equipment Equipment Model Integrating Sound Level Meter SC-30, CESVA Calibrator CB-5, CESVA Portable Wind Speed Indicator PWM2, Dwyer

3.2.5 Monitoring Procedures and Calibration Details Field Monitoring i. The microphone of the Sound Level Meter (with weatherproof kit) was mounted on a tripod at a height of 2m above ground level. ii. For free field measurement, the meter was positioned away from any nearby reflective surfaces. iii. AC power supply was checked to ensure good functioning of the meter. iv. Parameters such as frequency weighting, the time weighting and the measurement time were set as follows: a. frequency weighting : A b. time weighting : Fast

 6 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

c. time measurement : 30 minutes / 5 minutes

v. Prior to and after each noise measurement, the meter was calibrated using the Calibrator for 94 dB at 1000 Hz. If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment. vi. The wind speed was frequently checked with the portable wind meter. vii. At the end of the monitoring period, the Leq, L90 and L10 were recorded. In addition, site conditions and noise sources were recorded on a standard record sheet. viii. Noise measurement was paused during periods of high intrusive noise if possible and observation was recorded when intrusive noise was not avoided. ix. Noise monitoring was cancelled in the presence of fog, rain, and wind with steady speed exceeding 5 m/s, or wind with gusts exceeding 10m/s.

3.2.6 Maintenance and Calibration i. The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals. ii. The meter was sent to the supplier to check and calibrate yearly. iii. Calibration certificates are presented in Appendix G4.

3.2.7 Event/Action Plan The Event/Action Plan for Noise impact is presented in Appendix H2.

4 IMPLEMENTATION STATUS ON ENVIRONMENTAL PROTECTION REQUIREMENTS

The Contractor is in the process of implementing environmental mitigation measures to fulfill requirements as stated in the EIA Report, the Environmental Permit and EM&A Manual. The implementation status during the reporting period is summarized in Appendix I.

5 ENVIRONMENTAL LICENCE AND PERMITTING REQUIREMENTS

5.1.1 The status of the permits, licenses and EPD notifications for all relevant environmental issues for this project for the reporting period is presented in Appendix R. 5.1.2 Approval for the Specified Process License (SPL) for the operation of a Rock Crushing Plant at area P2-SA12 was issued to the sub-contractor of GSIJV by EPD on 14 April 2004 and EPD has granted permission for the operation on 17th May 2004. Air monitoring station had been set up at P2-SA12 and the monitoring results will be submitted to EPD on quarterly basis in accordance with the SPL condition.

 7 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

6 MONITORING RESULTS

6.1 Air Quality 6.1.1 The 1-hour TSP monitoring was carried out at four monitoring stations during the reporting period. All monitoring data are presented in Appendix J. A summary of the measured 1- hour TSP levels is given in Table 6.1. Graphical presentations of the 1-hour TSP monitoring results for the reporting period and the trend of 1-hour TSP results since the commencement of the Project are shown in Appendix K. Meteorological data such as atmospheric pressure and temperature used for the calculation of TSP values was obtained from the Hong Kong Observatory. Table 6.1 Summary of 1-hour TSP Impact Monitoring Results Location 1-hour TSP (Pg/m3) Action Level Limit Level 3 3 I.D. Mean Range Pg/m ) Pg/m ) ASR1 116.2 (40.9 – 212.1) 365.7 500 ASR2 141.7 (56.4 – 278.9) 417.0 500 ASR3 108.3 (21.4 – 189.9) 402.2 500 ASR4 115.6 (34.7 – 364.8) 365.8 500

6.1.2 The 24-hour TSP monitoring was carried out at four monitoring stations during the reporting period. All monitoring data are presented in Appendix J. A summary of the measured results is given in Table 6.2. Graphical presentation of the results and the trend since the commencement of the Project are shown in Appendix K. Table 6.2 Summary of 24-hour TSP Impact Monitoring Results Location 24-hour TSP (Pg/m3) Action Level Limit Level I.D. Mean Range Pg/m3) Pg/m3) ASR1 67.6 (43.3 – 125.9) 174.0 260 ASR2 82.5 (48.6 – 118.7) 185.5 260 ASR3 52.1 (25.7 – 98.9) 203.4 260 ASR4 65.1 (42.5 – 107.2) 192.0 260

6.1.3 No exceedance of the Action/Limit Levels of 1-hour and 24-hour TSP was recorded during the reporting period. The wind data monitoring results recorded during the reporting period are summarized in Appendix L. 6.1.4 Observations There were several significant dust sources identified during the reporting period and they were mainly contributed by the following activities: i. excavation; ii. grouting; iii. soil nail installation; iv. other construction activities nearby; and v. on-site traffic.

 8 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

6.2 Noise 6.2.1 In accordance with the Project’s EM&A Manual all noise monitoring were carried out in the absence of fog, rain and wind with a steady speed exceeding 5m/s, or wind gust exceeding 10m/s. Furthermore, an additional 3dB(A) façade correction for free field measurements were made for all monitoring locations.

6.2.2 Normal Hour Monitoring Daytime noise monitoring was carried out at all the noise monitoring stations during the reporting period. All corrected noise levels are presented in Appendix M1. A summary of the results is given in Table 6.3. Graphical presentation of the monitoring results for the reporting period is shown in Appendix N1. 1 no. exceedance of the Limit Level of noise for normal hour monitoring was recorded during the reporting period. Table 6.3 Summary of Corrected Impact Noise Levels for Normal Hour Monitoring Daytime Corrected Noise Level, dB(A) ** Limit 0700-1900 hrs on Mean (Range) Level

normal weekdays Leq (30 mins) L10 L90 dB(A) NSR1 63.6 (62.1-64.3) 65.1 (63.5-65.8) 61.5 (60.1-62.2) 75.0 NSR2 71.1 (66.9-74.1) 71.9 (69.8-74.6) 67.3 (63.9-70.2) 75.0 NSR3 76.9 (71.0-81.7) 75.7 (71.0-79.7) 70.2 (68.1-72.0) 75.0 NSR4 67.8 (56.1-72.9) 65.2 (55.1-67.9) 58.8 (52.7-60.9) 75.0 ** Additional 3dB (A) façade correction was made to the Free-field measurements. Bold numbers indicate exceedance

6.2.3 Observations The major noise sources during the normal hour were identified as follows: i. excavation; ii. demolition / site clearance; iii. on/off site traffic noise; iv. other construction works nearby; and v. transportation of rock spoil from tunnel to rock tipping platform

6.2.4 Restricted Hour Monitoring Construction works were carried out at site areas P2-SA6 (East Portal) during restricted hours (evening time and public holiday). All corrected noise levels are presented in Appendix M2. A summary of the results is given in Table 6.4. Graphical presentation of the monitoring results for the Reporting period is shown in Appendix N2. Noise monitoring was carried out at all monitoring locations during Evening-time (1900 - 2300 hours), Public-holiday (0700 -1900) and Night-time (2300-0700 next day) when construction works were carried out. Exceedances of the Limit level were recorded in the reporting period.

Table 6.4 Summary of Corrected Impact Noise Levels for Restricted Hour Monitoring

 9 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

Evening-time Corrected Noise Level, dB(A) ** Limit 1900-2300 hrs Mean (Range) Level

Leq (5 mins) L10(5 mins) L90(5 mins) dB(A) NSR1 63.1 (60.3-64.5) 64.6 (61.5-66.9) 61.2 (58.9-63.1) 70.0 NSR2 78.1 (62.0-81.0) 69.3 (63.0-73.7) 65.5 (60.6-69.4) 70.0 NSR3 78.0 (70.6-81.7) 75.9 (71.0-80.1) 69.9 (63.9-72.2) 70.0 NSR4 63.5 (51.6-70.2) 63.7 (52.3-69.2) 57.7 (50.3-62.6) 70.0 Night-time Corrected Noise Level, dB(A) ** Limit 2300-0700 hrs next day Mean (Range) Level

Leq (5 mins) L10(5 mins) L90(5 mins) dB(A) NSR1 58.9 (57.0-60.7) 60.6 (58.4-62.7) 57.3 (54.4-58.9) 55.0 NSR2 74.1 (58.1-81.4) 71.4 (59.1-77.8) 64.5 (56.6-67.9) 55.0 NSR3 77.9 (69.0-81.5) 75.1 (70.0-78.2) 70.4 (66.5-72.8) 55.0 NSR4 56.6 (53.9-60.2) 57.6 (55.0-60.3) 53.4 (50.7-55.4) 55.0 Public Holiday Corrected Noise Level, dB(A) ** Limit 0700-1900 hrs next day Mean (Range) Level

Leq (5 mins) L10(5 mins) L90(5 mins) dB(A) NSR1 62.2 (60.0-65.4) 63.8 (61.5-67.6) 60.7 (58.8-64.8) 70.0 NSR2 68.8 (61.4-72.9) 69.3 (62.9-72.9) 64.9 (59.6-69.3) 70.0 NSR3 72.5 (65.9-80.4) 72.6 (68.3-76.1) 69.1 (62.3-70.9) 70.0 NSR4 62.6 (52.8-67.6) 64.8 (55.0-68.3) 57.5 (49.7-61.0) 70.0 ** Additional 3dB (A) façade correction was made to the Free-field measurements. Bold numbers indicate exceedance

6.2.5 Observations The major noise sources during the restricted hour monitoring were dominated by the traffic noise and the other construction sites nearby. The types and number of power plants in operation during the monitoring period was fully in compliance with the CNP requirements.

7 AUDIT RESULTS

7.1 Air Quality 7.1.1 For 1-hour TSP monitoring, a total of 72 sets of measurements were carried out during the reporting period and all were below the Action/ Limit (AL) Levels. 7.1.2 For 24-hour TSP monitoring, a total of 20 sets of measurements were carried out during the reporting period and all were below the Action/ Limit (AL) Levels.

7.2 Noise

7.2.1 A total of 16 sets of Leq(30min) measurement during daytime (i.e. 0700 to 1900 hours on normal weekdays) were carried out during the reporting period and one exceedance of the Limit Level was recorded at NSR3 on 23rd June 2004. Notification of Exceedance has

 10 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigation was carried out and was concluded that exceedance was not contributed by the Route 8 construction activities and did not have a direct line of sight to the NSRs. Possible exceedance was caused by CT9 activity and local traffic. It should be noted that the newly developed Rambler Crest creates a reflector / barrier effect which enhances the increase in general noise levels at the NSRs and therefore corrective action was not considered necessary.

7.2.2 A total of 16 sets of 6 x Leq(5min) measurement during evening-time (i.e. 1900 to 2300 hours) were carried out during the reporting period and exceedances of the Limit Level were recorded at NSR2 on 23rd June 2004, NSR3 on 4th,11st, 18th, 23rd June 2004. Notifications of Exceedance have subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigations indicates that the number of power plants in operation during the monitoring period fully complied with the respective CNP requirements (2 no. rock drills (hand-held), 2 no. air compressors and 1 no. generator) and did not have a direct line of sight to the NSRs. It is therefore unlikely that exceedances were not contributed by the Route 8 construction activities. Possible exceedances were caused by CT9 activity and local traffic. It should be noted that the newly developed Rambler Crest creates a reflector / barrier effect which enhances the increase in general noise levels at the NSRs and therefore corrective action was not considered necessary.

7.2.3 A total of 16 sets of 6 x Leq(5min) measurement during night-time (i.e. 2300 to 0700 hours next day) were carried out during the reporting period and exceedances of the Limit Level were recorded at all locations on 4th,11st June 2004, NSR1-3 on 18th,23rd June 2004. Notifications of Exceedance have subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigations indicates that the number of power plants in operation during the monitoring period fully complied with the respective CNP requirements (2 no. rock drills (hand-held), 2 no. air compressors and 1 no. generator) and did not have a direct line of sight to the NSRs. It is therefore unlikely that exceedances were not contributed by the Route 8 construction activities. Possible exceedances were caused by CT9 activity and local traffic. It should be noted that the newly developed Rambler Crest creates a reflector / barrier effect which enhances the increase in general noise levels at the NSRs and therefore corrective action was not considered necessary.

7.2.4 A total of 20 sets of 6 x Leq(5min) measurement during public holiday (i.e. 0700 to 1900 hours) were carried out during the reporting period and exceedances of the Limit Level were recorded at NSR2 on 27th June 2004, NSR3 on 6th, 20th, 27th June 2004. Notifications of Exceedance have subsequently been issued in accordance with Section 9.6 of the EM&A Manual. Investigations indicates that the number of power plants in operation during the monitoring period fully complied with the respective CNP requirements (2 no. rock drills (hand-held), 2 no. air compressors and 1 no. generator) and did not have a direct line of sight to the NSRs. It is therefore unlikely that exceedances were not contributed by the Route 8 construction activities. Possible exceedances were caused by CT9 activity and local traffic. It should be noted that the newly developed Rambler Crest creates a reflector / barrier effect which enhances the increase in general noise levels at the NSRs and therefore corrective action was not considered necessary.

7.3 Water Quality 7.3.1 In accordance with the approved Effluent Discharge License conditions, water sampling is required on a monthly basis. Two water samples were taken on 11th June 2004 at two discharge points (one at the East Portal Wet-Sep discharge point and one at the West Portal

 11 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

Wet-Sep discharge points) for Total Suspended Solid (TSS) analysis. The results showed that they have fully complied with the Specific Condition as stipulated in the approved license. On 29th April 2003, EPD has confirmed that no Effluent Discharge License is required for P2-SA12. 7.4 Waste Management 7.4.1 The Waste Management Plan (WMP) was approved by EPD on 7th January 2004 and it is currently being updated by GSIJV. GSIJV will submit the revised WMP by the end of June to ER, ET and IEC for comment. 7.4.2 Since August 2003, all non-inert C&D material from the Contract has been disposed of at NENT and WENT Landfill. 81.22 tonnes of general refuse was delivered to WENT and 9.45 tonnes were delivered to NENT during the reporting period. In addition 39102.8 tonnes (3422 trucks) of good quality rock was delivered to Lam Tei Quarry and 49411.7 tonnes (4332 trucks) of low quality rock was delivered to P2-SA12. 219 trucks (approximately 1314m3) and 450 trucks(approximately 2700 m3) of inert C&D material were delivered to designated public filling area namely Kai Tak Barging Point and Castle Peak Road Widening Project respectively. 7.4.3 During this reporting period, 800 litres of chemical waste was disposed off site. Approximately 5m3 of C&D waste was reused, recycled, returned and 0.75m3 office paper was recycled during the reporting period.

7.4.4 The quantities of different waste and their handling are summarized in Table 7.1.

Table 7.1 Summary of Waste Disposal during the Reporting Period Material Type Handling Method Handling Quantities in Temporary Storage the reporting period Locations On-site (if applicable) C&D Public Deliver to Public Fill 219 no. of Dump Trucks N/A material Fill (Kai Tak Barging Point) (1314 m3) Rock Deliver to Lam Tei 3422 no. trucks West Portal Quarry (39102.8 tonnes) Rock Deliver to P2-SA12 4332 no. trucks West Portal (49411.7 tonnes) Mud Deliver to Castle Peak 450 no. trucks (2700 m3) N/A Road Widening Project C&D To be recycled (paper) 0.75m3 Contractor’s Office Waste To be reused and 5 m3 N/A returned to supplier (timber and metal)

Collected by licensed 18 no. trucks N/A collector for disposal to (81.22 tonnes) WENT Collected by licensed 3 no. trucks N/A collector for disposal to (9.45 tonnes) NENT Chemical waste Collected by licensed 800 L Chemical Waste chemical waste collector Storage Area (Behind GSIJV’s site office)

 12 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

7.5 Site Audit / Inspection Photographic records provided by GSIJV for deficiencies identified on site and their corresponding mitigation measures are presented in Appendix Q.

7.5.1 Environmental Team Site Audit Weekly site inspections were conducted by the ET during the reporting period and the major findings are summarized as follows.

i. Dust generated from vehicle movement was observed during the site audit. GSIJV was reminded to increase the frequency of watering to minimize dust impact.

Corrective and Preventive Actions – Watering has been increased and the dust on haul road has been cleaned up regularly to avoid dust emission. GSIJV was reminded that haul road watering should be increased especially during hot and dry conditions.

ii. Mud and sand was found in u-channel at area P2-SA1 (CT5) and East Portal.

Corrective and Preventive Actions – U-channels have been cleaned up, GCIJV was reminded that effective preventive measures should be provided at CT5, e.g. tarpaulin covering after maintenance. (Please refer to Appendix Q, Photo 01)

iii. Insufficient temporary drainage and provision of run-off control and desilting facilities at P2-SA12. GSIJV was urged to implement the temporary drainage system on site at P2-SA12 and submit the revised proposal without delay.

Corrective and Preventive Actions – The temporary drainage system at P2-SA12 is currently under construction. The revised drainage proposal is under certification by ICE and will be submitted once it is available. Rubble bund has been constructed along boundary next to CLP site, concreting will also be applied for the rubble bund to ensure no seepage of water into the CLP site. GSIJV was reminded to implement the whole temporary drainage system as soon as possible. (Please refer to Appendix Q, Photo 02)

iv. Dust control should be provided for the soil nail construction at the East Portal (zone 4)

Corrective and Preventive Actions – Tarpaulin sheeting and watering have been applied and are effective. GSIJV was reminded that such measures should be maintained properly at all time during soil nail operation.

v. Watering and impervious sheeting should be provided at P2-SA12.

Corrective and Preventive Actions – Adequate water hose and water sprinklers have been provided for the access road of PS-SA12 but the facilities and frequency of watering should be further increased.

vii. Significant amount of mud and stagnant water accumulated next to the sandbag barrier at the East Portal (entrance) was observed.

Corrective and Preventive Actions – The stagnant water has been removed and GSIJV

 13 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

was reminded that the mud should also be removed as soon as possible.

7.5.2 Independent Environmental Checker (IEC) Site Audit The IEC monthly audit was conducted on 25th June 2004 and two findings were recorded and details are presented below. i. Deposited silt accumulated in the u-channel was found at the East Portal, GSIJV was reminded to clean after the rainstorm has been subsided to ensure the facilities are functioning properly.

Corrective and Preventive Actions – U-channels have been maintained weekly and after rainstorm. (Please refer to Appendix Q, Photo 04)

ii. GSIJV was reminded to implement the surface runoff control system at P2-SA12 and sand bag barrier should be provided along the fencing of CLP site to prevent any surface runoff overflowing from P2-SA12.

Corrective and Preventive Actions – Please refer to Section 7.5.1 Item 3.

7.5.3 Environmental Protection Department (EPD) Site Inspection

EPD inspection was carried out on 7th June 2004 and two findings were recorded and details are presented below. i. For the area P2-SA1 adjacent to Cheung Tsing Highway, EPD raised their concern on the dust emission generated from the vehicular movement. Water bowsers, hose should be provided to maintain the haul road in moist condition at all times.

Corrective and Preventive Actions – The frequency of watering by water bowser has been increased to maintain the haul road in moist condition at all times. (Please refer to Appendix Q, Photo 05)

ii. For the West Portal, sufficient water sprinklers and hoses should be provided for the handling of temporary stockpile within the site area.

Corrective and Preventive Actions – Water sprinklers have been used at all times for dust suppression in the temporary rock stockpiling area. (Please refer to Appendix Q, Photo 06)

8 ENVIRONMENTAL NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND PROSECUTIONS

8.1 Summary of Environmental Non-Compliance 8.1.1 No environmental non-compliances were recorded in this reporting period and they are summarized in Table 8.1. Table 8.1 Summary of Non-Compliance for the Reporting Period Media/ No. of Exceedance Action Taken Results of Action Remarks

 14 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

Nature Action Limit Taken Level Level Air Quality 0 0 - - - Noise 0 24 N/A N/A NoE issued.

8.2 Summary of Complaints 8.2.1 No environmental related complaint was received during the reporting period. A total of 2 complaints have been received for the Project since the commencement of the construction. The summary for all the complaints received since the commencement of the Project is presented in Table 8.2. The details of previous complaints and statistics are attached in Appendices O1 and O2 respectively. Table 8.2 Summary of Total Complaint Received Total No. of No. of complaint received No. of Active No. of Inactive/Closed Complaint Received within reporting period Complaint Complaint 2002

8.3 Summary of Notification of Summon and Prosecution 8.3.1 No notification of summons or prosecutions was received regarding the non-compliance of the environmental performance of the construction site since the commencement of works.

9 FUTURE KEY ISSUES

9.1 Key Issues for the Coming Month 9.1.1 Works to be taken for the coming monitoring period will be similar to the previous month as follows: i. Site clearance and formation ; ii. Slope stabilization; iii. Bored pile construction; iv. Soil nail; and v. Excavation

9.1.2 Potential environmental impacts arising from the above construction activities are mainly associated with dust, noise, site runoff and waste. However, with the implementation of the following mitigation measures, potential impacts to the surrounding sensitive receivers could be minimized: 9.1.3 Construction Dust i. frequently watering of haul road and unpaved areas; ii. prohibition of any open burning on site; iii. investigation of other dust sources near air sensitive receivers; iv. regularly watering or covering of open areas and stockpiles with tarpaulin; v. hydroseeding or covering the inactive sand fill area with impervious sheeting if necessary; vi. switching off vehicles and equipments while not in use; and vii. regular maintenance of onsite machinery and vehicles.

 15 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

9.1.4 Construction Noise i. Identification of noise sources arising within and outside worksite; and ii. Provision of noise barriers as when necessary.

9.1.5 Construction Runoff i. identification of sources of run-off from site; ii. provision of sandbags/bunds/channels to direct run-off to silt/sand removal facilities; iii. avoidance of direct discharge of wastewater into storm water drainage; and iv. provision of treatment of wastewater and run-off prior to discharge.

9.1.6 Construction Waste Management i. avoidance of accumulation of construction waste materials and/or general refuse on site; ii. segregation of C&D waste; iii. collection of chemical waste or oil and disposal of as chemical waste in accordance with the relevant regulations; and iv. regularly removing of waste materials on site.

9.2 Monitoring Schedule for the Coming Three Months The tentative schedules for dust and noise monitoring for the next three month are attached in Appendix P.

10 RECOMMENDATIONS AND CONCLUSIONS

10.1 Conclusions 10.1.1 This Environmental Monitoring and Audit (EM&A) report presents the EM&A works undertaken during the month from 29th May 2004 to 28th June 2004 in accordance with EM&A Manual which forms part of the EIA Report (Register No. AEIAR-018/1999). 10.1.2 For 1-hour TSP monitoring, a total of 72 sets of measurements were carried out during the reporting period and all were below the Action/Limit (AL) Levels. For 24-hour TSP monitoring, a total of 20 sets of measurements were carried out during the reporting period and all were below the Action/Limit (AL) Levels was recorded.

10.1.3 A total of 16 sets of Leq(30min) measurement during daytime (i.e. 0700 to1900 hours) were carried out during the reporting period and one exceedance of the Limit Level was recorded at NSR3 on 23rd June 2004.

10.1.4 A total of 16 sets of 6 x Leq(5min) measurement during evening-time (i.e. 1900 to 2300 hours) were carried out during the reporting period and exceedances of the Limit Level were recorded at NSR2 on 23rd June 2004, NSR3 on 4th,11st, 18th, 23rd June 2004.

10.1.5 A total of 16 sets of 6 x Leq(5min) measurement during night-time (i.e. 2300 to 0700 hours next day) were carried out during the reporting period and exceedances of the Limit Level were recorded at all locations on 4th,11st June 2004, NSR1-3 on 18th,23rd June 2004.

10.1.6 A total of 20 sets of 6 x Leq(5min) measurement during public-holiday (i.e. 0700 to 1900 hours) were carried out during the reporting period and exceedances of the Limit Level were recorded at NSR2 on 27th June 2004, NSR3 on 6th, 20th, 27th June 2004. 10.1.7 No environmental related complaint was received in this reporting period.

 16 Route 8 Phase 2a – Nam Wan Tunnel and West Tsing Yi Viaduct Highways Department Monthly EM&A Report – June 2004

10.1.8 No prosecution or summons was received for this Contract since the commencement of construction works. 10.1.9 ET and IEC audits were carried out in accordance with the Project’s EM&A Manual and deficiencies identified were related to dust suppression measures and effluent treatment implementation. 10.2 Recommendations According to the environmental audits undertaken during the reporting period, the following recommendations have been made: 10.2.1 Construction Dust i. Site access road and exposed areas should be watering regularly to ensure the soil surface is moist; ii. Dusty areas should be watered frequently during hot/dry weather; iii. Open stockpiles should be covered properly by tarpaulin; and iv. Watering of any earth moving activities.

10.2.2 Construction Noise i. The numbers of plant operating should not exceed the allowable plant number for each construction activity stated in the Construction Noise Permits; ii. Regular maintenance of machinery; and iii. Noisy equipment should be located away from nearby NSRs.

10.2.3 Water Quality i. All surface runoff/wastewater should be diverted to appropriate water treatment facilities before discharge; ii. Sedimentation tanks/basins should have adequate capacity for settling surface runoff; iii. Wheel washing facilities should be installed at all vehicular exits and used by all vehicles before leaving the construction site; iv. Vehicle and plant servicing area, wheel washing bay should be connected to storm drains via a petrol interceptor; v. Site hoarding should be tightly sealed at the bottom to prevent seepage of surface runoff from the site; and vi. Accumulation of water in drip trays and at chemical/fuel storage area should be avoided.

10.2.4 Waste Management i. Contaminated soil with oil or petrol should be collected and disposed of as chemical waste; ii. All types of waste should be collected by licensed waste collectors; and iii. Good housekeeping should be implemented throughout the construction period.

 17 Appendix A

Site Location Plan

Appendix B

Project’s Environmental Organization Chart and Contact Details Appendix B: Project's Environmental Organisation Chart and Contact Details

Highways Department Environmental Protection Major Works Office Department

CRE / Engineer's Representative Environmental Team Leader Independent Environmental Arup* - Ted Tang Allen C P Chan Checker 2436 7488 / 9300 6162 2436 7423 / 9300 3070 CH2M.IDC - David Yeung 2872 2934

Contractor - GSIJV*

Contractor's Project Manager K F Tam Lines of reporting 2943 9535 Lines of communication Environmental Manager * Arup - Ove Arup & Partners Hong Kong Limited Francis Sin GSIJV - Gammon Skanska International Joint Venture 2943 9506

Environmental Engineer Alex Chan 2943 9507 Appendix C

Three-Month Rolling Programme

Appendix D1

Action/Limit Levels for Air Quality Appendix D1: Action /Limit Levels for Air Quality

ACTION AND LIMIT LEVELS FOR 24-HOUR TSP Location Action Level (Pg/m3) Limit Level (Pg/m3) ASR1 174.0 260 ASR2 185.5 260 ASR3 203.4 260 ASR4 192.0 260

ACTION AND LIMIT LEVELS FOR 1-HOUR TSP Location Action Level (Pg/m3) Limit Level (Pg/m3) ASR1 365.7 500 ASR2 417.0 500 ASR3 402.2 500 ASR4 365.8 500 Appendix D2

Action/Limit Levels for Noise Appendix D2: Action/Limit Levels for Noise

Action and Limit Levels for Construction Noise Time Period Action Limit

0700-1900 hrs on normal When one 75dB(A)* weekdays documented complaint is received 0700-2300 hrs on holidays; and When one 70 dB(A) 1900-2300 hrs on all other days documented complaint is received 2300-0700 hrs of next day When one 55 dB(A) documented complaint is received * Reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods. Appendix E

Environmental Monitoring Schedule for the Reported Period Environmental Monitoring Schedule between 29 May and 28 June 2004 Sunday Monday Tuesday Wednesday Thursday Friday Saturday 29-May 1hr-TSP

30-May 31-May 1-Jun 2-Jun 3-Jun 4-Jun 5-Jun

NoiseP.H. 24hrs-TSP 1hr-TSP 24hrs-TSP Noise

Noiseevening

Noisenight 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun 12-Jun

NoiseP.H. 1hr-TSP 24hrs-TSP Noise

Noiseevening

Noisenight 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun 19-Jun

NoiseP.H. 1hr-TSP 24hrs-TSP Noise

Noiseevening

Noisenight

20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun 26-Jun

NoiseP.H. 1hr-TSP 24hrs-TSP 1hr-TSP Noise

Noiseevening

Noisenight 27-Jun 28-Jun

NoiseP.H.

1hr-TSP 3 x 1 hour TSP monitoring at ASR1 to ASR4 during 0900~1800. 24hrs-TSP 24 hours TSP monitoring at ASR1 to ASR4 Noise Leq30 measurement at NSR1 to NSR4 during 0700~1900. NoiseEvening 6 x Leq5 will be measured at NSR1 to NSR4 during 1900~2300 (if construction activities are undertaken). NoiseNight 4 x Leq5 will be measured at NSR1 to NSR4 during 2300~0700 next day (if construction activities are undertaken). NoiseP.H. 6 x Leq5 will be measured at NSR1 to NSR4 during 0700~1900 (if construction activities are undertaken). Appendix F

Locations of Monitoring Locations

Appendix G1

Calibration Certificates for HVS

Appendix G2

Calibration Certificates for Weather Station

Appendix G3

Calibration Certificates for High Volume Orifice Calibrator

Appendix G4

Calibration Certificates for Sound Level Meter and Calibrator

Appendix H1

Event/Action Plan for Air Quality Appendix H1: Event/Action Plan for Air Quality Event Action Level ET ER CONTRACTOR Action Level Exceedance x Identify source x Notify Contractor x Rectify any unacceptable for one x Inform ER x Check mortaring data and practice sample x Repeat Measurement to Contractor’s working x Amend working methods if confirm finding methods appropriate x Increase monitoring frequency to daily Exceedance 1. Identify source 1. Confirm receipt of notification 1. Submit proposals for remedial for two or 2. Inform ER of failure in writing actions to ER within 3 working more 3. Repeat measurements to 2. Notify Contractor days of notification consecutive confirm findings 3. Check monitoring data and 2. Implement the agreed proposals samples 4. Increase monitoring Contractor’s working 3. Amend proposal if appropriate frequency to daily methods 5. Discuss with ER for remedial 4. Discuss with Environmental actions required Team and Contractor on 6. If exceedance continues potential remedial actions arrange meeting with ER 5. Ensure remedial actions 7. If exceedance stops, cease properly implemented additional monitoring Limit Level Exceedance 1. Identify source 1. Confirm receipt of notification 1. Take immediate action to avoid for one 2. Inform ER and EPD of failure in writing further exceedance sample 3. Repeat measurement to 2. Notify Contractor 2. Submit proposals for remedial confirm finding 3. Check monitoring data and actions to ER within 3 working 4. Increase monitoring Contractor’s working days of notification frequency to daily methods 3. Implements the agreed 5. Assess effectiveness of 4. Discuss with Environmental proposals Contractor’s remedial actions Team Leader and Contractor 4. Amend proposal if appropriate and keep EPD and ER potential remedial actions informed of the results 5. Ensure remedial actions properly implemented Exceedance 1. Identify source 1. Confirm receipt of notification 1. Take immediate action avoid for two or 2. Inform ER and EPD the of failure in writing further exceedance more causes & actions taken for 2. Notify Contractor 2. Submit proposals for remedial consecutive the exceedances 3. Carry out analysis of actions to ER within 3 working samples 3. Repeat measurement to Contractor’s working days of notification confirm findings procedures to determine 3. Implements the agreed proposals 4. Increase monitoring possible mitigation to be 4. Resubmit proposals if problem frequency to daily implemented still not under control 5. Investigate the causes of 4. Discuss amongst 5. Stop the relevant portion of works exceedance Environmental Team Leader as determined by the ER until the 6. Arrange meeting with EPD and the Contractor potential exceedance is abated and ER to discuss the remedial actions remedial actions to be taken 5. Review Contractor’s remedial 7. Assess effectiveness of actions whenever necessary Contractor’s remedial actions to assure their effectiveness and keep EPD and ER 6. If exceedance continues informed of the results & if consider what portion of the exceedance stops, cease work is responsible and additional monitoring instruct the Contractor to stop that portion of work until the exceedance is abated Appendix H2

Event/Action Plan for Noise Appendix H2: Event/Action Plan for Construction Noise Event Action ET Leader ER Contractor Action 1. Notify ER 1. Notify Contractor 1. Submit noise mitigation Level 2. Analyse 2. Require Contractor to proposals to Environmental investigation propose measures* for Team 3. Increase monitoring the analysed noise 2. Implement noise mitigation frequency to check problem proposals* mitigation effectiveness Limit 1. Notify ER 1. Notify Contractor 1. Implement mitigation measures Level 2. Notify EPD 2. Require contractor to 2. Prove to Environmental Team implement mitigation Leader ER effectiveness of measures* Increase measures applied monitoring frequency to check mitigation effectiveness * Mitigation Measures may include: x Relocation of noise emitting plant x Use of silenced or super-silenced equipment x Use of acoustic sheds or screens x Limit quantity of plant operating x Change working technique Appendix I

Implementation Status of Environmental Protection Requirements Appendix I: Implementation Status of Environmental Protection Requirement

Environmental Protection Measures Timing Implementation Stages* Activities 29/2/04 to 29/3/04 to 29/4/04 to 29/5/04 to 28/3/04 28/4/04 28/5/04 28/6/04 Landscape Erection, painting and maintenance of site hoardings around works and Throughout N/A N/A N/A N/A and visual storage areas. the construction Restrictions on the height of material/spoil stockpiles. ———— period Prompt hydro-seeding of disturbed areas and cut/fill slopes prior to the ———— permanent landscaping works. Avoidance of chunam or shotcreting slope treatments. ———— Conservation of topsoil where practical. N/A ——— Site litter patrols and regular site waste collection. ———— Maintenance of planting. ———— Ecological Minimise damage outside works areas ———— Impact Construction: Material Covers for dusty stockpiles Throughout ———— Storage the construction Vehicle Haul road watering, vehicle wheel wash prior to exit. Where practical, ———— period movement access roads should be protected with crushed gravel. Plant All plant shall be maintained to prevent any undue air emissions. ———— maintenance All plant Reference should be made the EM&A Manual Action Plan for ———— activity measures for consideration when Noise Limit Levels are not met.

Plant All plant shall be maintained to prevent any undue noise nuisance. ———— maintenance

* N/A = Not Applicable 9 = Implemented Ÿ = Rectified # = Not Implemented Environmental Protection Measures Timing Implementation Stages* Activities 29/2/04 to 29/3/04 to 29/4/04 to 29/5/04 to 28/3/04 28/4/04 28/5/04 28/6/04 Wheel wash All wheel wash water shall be diverted to a sediment pit. Throughout ———— the Concrete All concrete trucks shall wash out into a lined pit. ———— construction Truck Washout period Surface water All clean surface water shall be diverted around the site. ———— diversion Sediment Sediment removal facilities shall be provided and be maintained and ———P2-SA12 control excavated as necessary to prevent sedimentation of the channel. and East Perimeter channels shall be provided. Works shall be programmed for Portal the dry season where feasible. entrance (bottom of soil nail) Fuel can All fuel cans shall be placed within a bundled area. Any fuel spills shall ———— storage be mopped up as necessary. Slope covers Finished slopes and other slopes near drainage areas shall be covered ———— prior to rains to reduce sedimentation of runoff. Slopes should be hydroseeded or shotcreted as early as possible to prevent erosion. Excavation Excavation works shall avoid sensitive areas. Throughout ———— works the excavation work period Material, plant Any fuel or oil spills shall be excavated and disposed of. Throughout ———— movement & the fuel can refilling. construction period Generators All generators shall be placed within a bundled area. Any fuel spills ———— shall be mopped up as necessary.

Material All empty bags and containers shall be collected for disposal. Throughout ———— * N/A = Not Applicable 9 = Implemented Ÿ = Rectified # = Not Implemented Environmental Protection Measures Timing Implementation Stages* Activities 29/2/04 to 29/3/04 to 29/4/04 to 29/5/04 to 28/3/04 28/4/04 28/5/04 28/6/04 containers the Worker Litter receptacles shall be placed around the site. Litter shall be taken construction ———— generated litter regularly to the refuse collection points. Chemical toilets (or suitable period and Waste equivalent) should be provided for workers. Any canteens should have grease-traps. Neighbourhoo All complaints regarding construction works shall be relayed to the N/A N/A — N/A d nuisance Environmental Team. Legal Different types of waste should be segregated, stored, transported and ———— requirements disposed of in accordance with the relevant legislative requirements and guidelines On-site On-site separation of municipal solid waste and construction/demolition ———— separation wastes should be conducted as far as possible in order to minimize the amount of solid waste to be disposed to landfill. Temporary Separated wastes should be stored in different containers, skips, or ———— storage area stockpiles to enhance reuse or recycling of materials and encourage their proper disposal. Record of Records of quantities of wastes generated, recycled and disposed (with ———— wastes locations) should be properly kept. Trip-ticket To monitor the disposal of waste at landfills and control fly-tipping, a ———— system “trip-ticket” system for all solid waste transfer/disposal operations should be implemented. The system should be included as a contractual requirement, and monitored by the Environmental Team and audited by the Independent Environmental Checker.

* N/A = Not Applicable 9 = Implemented Ÿ = Rectified # = Not Implemented Appendix J

1-hour and 24-hour TSP Monitoring Results The Summary of 1-hr TSP Concentration (µg/m3) at HKIVE Fok Ying Tung Hall of Residence (ASR 1) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 29-May-04 9:00 90.00 1.11 1.11 1.11 99.64 2.7797 2.7907 110.4 29-May-04 11:42 60.00 1.11 1.11 1.11 66.43 2.7835 2.7912 115.9 29-May-04 12:56 78.00 1.11 1.11 1.11 86.35 2.9075 2.9113 44.0 4-Jun-04 9:00 108.00 1.11 1.11 1.11 119.55 2.9271 2.9423 127.1 4-Jun-04 10:33 114.00 1.11 1.11 1.11 126.19 2.9170 2.9285 91.1 4-Jun-04 13:32 102.00 1.11 1.11 1.11 112.91 2.9091 2.9243 134.6 10-Jun-04 9:00 120.00 1.11 1.11 1.11 132.98 2.8791 2.8999 156.4 10-Jun-04 11:33 60.00 1.11 1.11 1.11 66.49 2.8972 2.9113 212.1 10-Jun-04 13:05 156.00 1.11 1.11 1.11 172.88 2.9185 2.9546 108.8 16-Jun-04 9:00 84.00 1.10 1.10 1.10 92.77 2.8608 2.8683 80.8 16-Jun-04 11:17 84.00 1.10 1.10 1.10 92.77 2.8948 2.9005 61.4 16-Jun-04 12:56 120.00 1.10 1.10 1.10 132.54 2.8869 2.8935 49.8 21-Jun-04 9:00 102.00 1.10 1.10 1.10 112.36 2.8953 2.8999 40.9 21-Jun-04 10:32 96.00 1.10 1.10 1.10 105.75 2.9129 2.9282 144.7 21-Jun-04 11:42 60.00 1.10 1.10 1.10 66.10 2.9007 2.9116 164.9 26-Jun-04 9:00 102.00 1.10 1.10 1.10 112.09 2.9083 2.9212 115.1 26-Jun-04 10:17 114.00 1.10 1.10 1.10 125.28 2.8613 2.8872 206.7 26-Jun-04 12:14 60.00 1.10 1.10 1.10 65.93 2.8810 2.8894 127.4

The Summary of 24-hrs TSP Concentration (µg/m3) at HKIVE Fok Ying Tung Hall of Residence (ASR1) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 31-May-04 0:00 1452.00 1.11 1.11 1.11 1604.56 2.8954 2.9902 59.1 5-Jun-04 0:00 1386.00 1.11 1.11 1.11 1534.64 2.8789 3.0721 125.9 11-Jun-04 0:00 1398.00 1.11 1.11 1.11 1550.52 2.9002 2.9692 44.5 17-Jun-04 0:00 1410.00 1.10 1.10 1.10 1555.31 2.9152 2.9825 43.3 23-Jun-04 0:00 1374.00 1.10 1.10 1.10 1509.39 2.8991 2.9977 65.3 The Summary of 1-hr TSP Concentration (µg/m3) at HKIVE 5th floor Block D of the Main Building (ASR 2) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 29-May-04 9:00 78.00 1.30 1.30 1.30 101.57 2.7690 2.7827 134.9 29-May-04 11:00 60.00 1.30 1.30 1.30 78.13 2.8099 2.8233 171.5 29-May-04 12:13 126.00 1.30 1.30 1.30 164.07 2.8870 2.8975 64.0 4-Jun-04 9:00 78.00 1.30 1.30 1.30 101.55 2.8981 2.9206 221.6 4-Jun-04 10:52 60.00 1.30 1.30 1.30 78.12 2.9037 2.9123 110.1 4-Jun-04 12:17 60.00 1.30 1.33 1.32 78.93 2.9262 2.9458 248.3 10-Jun-04 9:00 72.00 1.33 1.33 1.33 95.79 2.8714 2.8800 89.8 10-Jun-04 11:00 60.00 1.33 1.33 1.33 79.82 2.8940 2.9003 78.9 10-Jun-04 12:05 60.00 1.33 1.33 1.33 79.82 2.9008 2.9053 56.4 16-Jun-04 9:00 66.00 1.33 1.33 1.33 87.54 2.8871 2.8955 96.0 16-Jun-04 11:00 66.00 1.33 1.33 1.33 87.54 2.9143 2.9241 111.9 16-Jun-04 12:33 66.00 1.33 1.33 1.33 87.54 2.8951 2.9072 138.2 21-Jun-04 9:00 72.00 1.33 1.33 1.33 95.96 2.9071 2.9226 161.5 21-Jun-04 11:00 66.00 1.33 1.31 1.32 87.06 2.8857 2.9015 181.5 21-Jun-04 12:17 168.00 1.31 1.31 1.31 219.33 2.8957 2.9143 84.8 26-Jun-04 9:00 60.00 1.09 1.09 1.09 65.62 2.9268 2.9350 125.0 26-Jun-04 10:04 60.00 1.09 1.09 1.09 65.62 2.8860 2.9043 278.9 26-Jun-04 11:26 60.00 1.09 1.09 1.09 65.62 2.8662 2.8792 198.1

The Summary of 24-hr TSP Concentration (µg/m3) at HKIVE 5th floor Block D of the Main Building (ASR 2) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 31-May-04 0:00 2784.00 1.30 1.30 1.30 3619.24 2.8883 3.2256 93.2 5-Jun-04 0:00 1380.00 1.33 1.33 1.33 1834.54 2.8800 3.0978 118.7 11-Jun-04 0:00 1386.00 1.33 1.33 1.33 1845.28 2.9088 3.0080 53.8 17-Jun-04 0:00 1458.00 1.32 1.32 1.32 1931.67 2.8886 2.9824 48.6 23-Jun-04 0:00 1464.00 1.09 1.09 1.09 1600.73 2.8950 3.0521 98.1 The Summary of 1-hr TSP Concentration (µg/m3) at Mayfair Gardens 1st floor adjacent to swimming pool (ASR3) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 29-May-04 9:00 60.00 1.15 1.15 1.15 68.93 2.7585 2.7714 187.2 29-May-04 10:45 66.00 1.15 1.15 1.15 75.82 2.7710 2.7737 35.6 29-May-04 13:00 138.00 1.15 1.15 1.15 158.53 2.9074 2.9108 21.4 4-Jun-04 9:00 66.00 1.15 1.15 1.15 75.81 2.8967 2.9058 120.0 4-Jun-04 10:56 90.00 1.15 1.15 1.15 103.38 2.8908 2.9028 116.1 4-Jun-04 12:41 60.00 1.15 1.15 1.15 68.92 2.9067 2.9165 142.2 10-Jun-04 9:00 60.00 1.15 1.15 1.15 68.99 2.8625 2.8648 33.3 10-Jun-04 10:42 72.00 1.15 1.15 1.15 82.79 2.9052 2.9120 82.1 10-Jun-04 11:52 66.00 1.15 1.15 1.15 75.89 2.9083 2.9120 48.8 16-Jun-04 9:00 60.00 1.15 1.15 1.15 68.78 2.8719 2.8735 23.3 16-Jun-04 10:30 90.00 1.15 1.15 1.15 103.16 2.9030 2.9109 76.6 16-Jun-04 12:57 54.00 1.15 1.15 1.15 61.90 2.8999 2.9074 121.2 21-Jun-04 9:00 60.00 1.14 1.14 1.14 68.61 2.8858 2.8959 147.2 21-Jun-04 10:49 72.00 1.14 1.14 1.14 82.33 2.9109 2.9247 167.6 21-Jun-04 11:49 138.00 1.14 1.14 1.14 157.81 2.9028 2.9218 120.4 26-Jun-04 9:00 60.00 1.14 1.14 1.14 68.46 2.9193 2.9323 189.9 26-Jun-04 10:42 72.00 1.14 1.14 1.14 82.15 2.8786 2.8931 176.5 26-Jun-04 11:52 60.00 1.14 1.14 1.14 68.46 2.8541 2.8637 140.2

The Summary of 24-hrs TSP Concentration (µg/m3) at Mayfair Gardens 1st floor adjacent to swimming pool (ASR3) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 31-May-04 0:00 2880.00 1.15 1.15 1.15 3302.94 2.9064 2.9912 25.7 5-Jun-04 0:00 1434.00 1.15 1.15 1.15 1647.57 2.8760 3.0390 98.9 11-Jun-04 0:00 1404.00 1.15 1.15 1.15 1615.59 2.9164 2.9772 37.6 17-Jun-04 0:00 1398.00 1.14 1.14 1.14 1600.61 2.8975 2.9623 40.5 23-Jun-04 0:00 1446.00 1.14 1.14 1.14 1649.33 2.9243 3.0197 57.8 The Summary of 1-hr TSP Concentration (µg/m3) at Cheung Ching Estate at the roof of Ching Yung House (ASR4) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 29-May-04 9:00 60.00 1.10 1.10 1.10 66.07 2.7686 2.7766 121.1 29-May-04 10:33 72.00 1.10 1.10 1.10 79.28 2.8986 2.9030 55.5 29-May-04 13:17 120.00 1.10 1.10 1.10 132.14 2.9065 2.9138 55.2 4-Jun-04 9:00 60.00 1.14 1.17 1.16 69.35 2.9083 2.9336 364.8 4-Jun-04 10:12 66.00 1.17 1.14 1.16 76.28 2.8900 2.9085 242.5 4-Jun-04 11:50 60.00 1.14 1.10 1.12 67.26 2.8635 2.8702 99.6 10-Jun-04 9:00 60.00 1.10 1.10 1.10 66.27 2.8682 2.8705 34.7 10-Jun-04 10:33 60.00 1.10 1.10 1.10 66.27 2.8803 2.8878 113.2 10-Jun-04 11:47 72.00 1.10 1.10 1.10 79.52 2.9056 2.9104 60.4 16-Jun-04 9:00 66.00 1.10 1.10 1.10 72.67 2.8941 2.9019 107.3 16-Jun-04 10:11 120.00 1.10 1.10 1.10 132.13 2.9197 2.9273 57.5 16-Jun-04 12:32 60.00 1.10 1.10 1.10 66.07 2.9072 2.9125 80.2 21-Jun-04 9:00 60.00 1.10 1.10 1.10 65.91 2.9054 2.9089 53.1 21-Jun-04 10:47 66.00 1.10 1.10 1.10 72.50 2.8967 2.9082 158.6 21-Jun-04 12:42 114.00 1.10 1.10 1.10 125.23 2.8924 2.9058 107.0 26-Jun-04 9:00 60.00 1.10 1.10 1.10 65.77 2.8941 2.9021 121.6 26-Jun-04 10:29 66.00 1.10 1.10 1.10 72.34 2.8743 2.8848 145.1 26-Jun-04 12:00 60.00 1.10 1.10 1.10 65.77 2.8581 2.8649 103.4

The Summary of 24-hrs TSP Concentration (µg/m3) at Cheung Ching Estate at the roof of Ching Yung House (ASR4) Initial Standard Flow Final Standard Flow Averaged Standard Total Standard Date Sampling Time Elapsed Time Rate Rate Flow Rate Volume Initial Filter Weight Final Filter Weight TSP Concentration (min) (m3/min) (m3/min) (m3/min) (m3) (g) (g) µg/m3 31-May-04 0:00 2868.00 1.10 1.10 1.10 3152.87 2.9293 3.1620 73.8 5-Jun-04 0:00 1422.00 1.10 1.10 1.10 1569.34 2.8703 3.0385 107.2 11-Jun-04 0:00 1410.00 1.11 1.11 1.11 1558.45 2.8596 2.9259 42.5 17-Jun-04 0:00 1434.00 1.10 1.10 1.10 1577.18 2.9292 2.9991 44.3 23-Jun-04 0:00 1386.00 1.10 1.10 1.10 1518.74 2.9286 3.0163 57.7 Appendix K

Graphical Presentation of 1-hour and 24-hour TSP Monitoring Result 1 hr TSP Concentration (µg/m3) at HKIVE Fok Ying Tung Hall of Residence (ASR1)

TSP Concentration Mean of TSP concentration at same monitoring day Action Level Limit Level

600.0

450.0 ) 3

300.0 TSP Concentration (µg/m

150.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 24 hrs TSP Concentration (µg/m3) at HKIVE Fok Ying Tung Hall of Residence(ASR1)

TSP Concentration Action Level Limit Level

300.0

250.0 ) 3 200.0

150.0

100.0 TSP Concentration (µg/m

50.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 1 hr TSP Concentration (µg/m3) at HKIVE 5th floor Block D of the main Building (ASR2)

TSP Concentration Mean of TSP concentration at same monitoring day Action Level Limit Level

600.0

450.0 ) 3

300.0 TSP Concentration (µg/m

150.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 24 hrs TSP Concentration (µg/m3) at HKIVE 5th floor Block D of the Main Building(ASR2)

TSP Concentration Action Level Limit Level

300.0

250.0 ) 3 200.0

150.0

100.0 TSP Concentration (µg/m

50.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 1 hr TSP Concentration (µg/m3) at Mayfair Gardens 1st floor adjacent to swimming pool (ASR3)

TSP Concentration Mean of TSP concentration at same monitoring day Action Level Limit Level

600.0

450.0 ) 3

300.0 TSP Concentration (µg/m

150.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 24 hrs TSP Concentration (µg/m3) at Mayfair Gardens 1st floor adjacent to swimming pool (ASR3)

TSP Concentration Action Level Limit Level

300.0

250.0 ) 3 200.0

150.0

100.0 TSP Concentration (µg/m

50.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 1 hrs TSP Concentration (µg/m3) at Cheung Ching Estate at the roof of Ching Yung House(ASR4)

TSP Concentration Mean of TSP concentration at same monitoring day Action Level Limit Level

600.0

450.0 ) 3

300.0 TSP Concentration (µg/m

150.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date 24 hrs TSP Concentration (µg/m3) at Cheung Ching Estate at the roof of Ching Yung House(ASR4)

TSP Concentration Action Level Limit Level

300.0

250.0 ) 3 200.0

150.0

100.0 TSP Concentration (µg/m

50.0

0.0

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 0 0 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04-04-04-04-04 0 0 0 -04-04-04-04-04-04-04-0 -0 -0 -0 -0 -04-04-04 0 0 0 0 0 -0 -0 04 04 04 04 04 04 0 0 -04-04-04-04-04 g- g- g- p- p- p- p- p- p- v-0v-0v-0 c-0c-0 n- n- b- b- b- r r r r r r- r- r- r- r- y- y- y- y- y- y- n- n- u u u e e e e e e ct-0ct-0 e e e eb eb eb eb eb ar ar p p p p p ay ay Oct-Oct-Oct-Oct-Oct- JanJanJanJanJan MaMaMaMa A A A A A JunJunJunJunJun A A A -Sep-SepS S S S S S -O -O -No-No-No Nov-Nov-Nov-Nov-Nov--De-De Dec-Dec-Dec-Dec-Dec-Dec--Ja-Ja -F -F -F F F F F F -M -M Ma -Apr-Apr-Apr -M -M MaMaMaMaMaMa-Ju-Ju 1- 5- 9- 2 6 0- 4- 8- 2- 6- 0- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 4 8 2- 6- 0- 4- 8- 1 5 9 3- 7- 1- 5- 9- 3 7 1- 5- 9- 3- 7- 1- 4 8 2- 6- 0- 4- 8- 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 2 2 2 1 1 1 2 2 3 1 1 2 2 2 Date Appendix L

Weather Condition during Impact Monitoring Appendix L: Weather Condition during Impact Monitoring

Weather Ambient PressureAverage Ambient Temperature Relative Humidity Wind Speed m/s Date Time Condition P (mmHg) oC K % Mean Max 29-May-04 0900-1317 Sunny 756.59 27.3 300.45 83 0.87 2.28 31-May-04 0000-0000 Sunny 758.31 29.0 302.15 76 0.73 2.33 4-Jun-04 0900-1332 Sunny 757.41 27.7 300.85 77 1.73 3.62 5-Jun-04 0000-0000 Sunny 756.29 27.1 300.25 80 1.46 2.78 10-Jun-04 0900-1305 Sunny 758.24 27.4 300.55 77 2.01 3.89 11-Jun-04 0000-0000 Sunny 759.14 27.3 300.45 70 1.6 3.62 16-Jun-04 0900-1257 Sunny 755.54 28.2 301.35 82 0.75 2.58 17-Jun-04 0000-0000 Sunny 755.76 29.0 302.15 80 0.82 2.56 21-Jun-04 0900-1242 Sunny 752.91 28.6 301.75 85 0.2 1.2 23-Jun-04 0000-0000 Sunny 751.04 29.4 302.55 81 2.13 3.65 26-Jun-04 0900-1214 Sunny 752.76 29.9 303.05 78 2.34 3.3

Meteorological data such as atmospheric pressure and temperature used for the calculation of TSP values was obtained from the Hong Kong Observatory

* Not Available Appendix L: Weather Condition during Impact Monitoring

Wind Direction during Impact Monitoring - Frequency of Wind Direction at 5 minute Interval

Date Wind Direction (Degree) 0 22.5 45.0 67.5 90.0 112.5 135.0 157.5 180.0 202.5 225.0 247.5 270.0 292.5 315.0 337.5 29-May-04 00001004292000000 31-May-04 035210046081000020 4-Jun-04 00472100352000000 5-Jun-04 0 1 1 15 10 0 0 7 70 9100000 10-Jun-04 00110006391100000 11-Jun-04 0 0 8 61 60 15 0 14 70 1000000 16-Jun-04 00000000184000000 17-Jun-04 0000000214863100000 21-Jun-04 0000000371000000 23-Jun-04 0000000523941000000 26-Jun-04 00000000364000000

* Not Available Appendix M1

Noise Monitoring Results for Normal Hour The Summary of Day-time Leq30 Level at HKIVE Fok Ying Tung Hall of Residence (NSR 1) Date Monitoring Time Duration Leq L10 L90 Limit Level min dB(A) dB(A) dB(A) dB(A) 4-Jun-04 17:59 30 63.6 65.5 61.5 75.0 11-Jun-04 17:59 30 63.9 65.2 62.2 75.0 18-Jun-04 18:23 30 62.1 63.5 60.1 75.0 23-Jun-04 17:09 30 64.3 65.8 62.0 75.0

The Summary of Day-time Leq30 Level at HKIVE 5th Floor Block D of the Main Education Building (NSR 2) Date Monitoring Time Duration Leq L10 L90 Limit Level min dB(A) dB(A) dB(A) dB(A) 4-Jun-04 9:00 30 66.9 69.8 63.9 75.0 11-Jun-04 9:02 30 68.2 70.4 64.8 75.0 18-Jun-04 10:40 30 74.1 74.6 70.2 75.0 23-Jun-04 18:06 30 71.5 71.0 67.6 75.0

The Summary of Day-time Leq30 Level at Mayfair Gardens 1st floor adjacent to swimming pool (NSR 3) Date Monitoring Time Duration Leq L10 L90 Limit Level min dB(A) dB(A) dB(A) dB(A) 4-Jun-04 18:25 30 71.0 72.1 68.3 75.0 11-Jun-04 9:03 30 71.3 71.0 68.1 75.0 18-Jun-04 9:25 30 73.5 74.5 71.2 75.0 23-Jun-04 16:30 30 81.7 79.7 72.0 75.0

The Summary of Day-time Leq30 Level at Cheung Ching Estate at roof of Ching Ying House (NSR 4) Date Monitoring Time Duration Leq L10 L90 Limit Level min dB(A) dB(A) dB(A) dB(A) 4-Jun-04 14:11 30 65.4 67.9 60.9 75.0 11-Jun-04 9:25 30 72.9 67.3 60.3 75.0 18-Jun-04 9:04 30 59.6 61.4 57.3 75.0 23-Jun-04 15:50 30 56.1 55.1 52.7 75.0 Appendix M2

Noise Monitoring Results for Restricted Hour The Summary of Evening-time Leq 5 Level at HKIVE Fok Ying Tung Hall of Residence (NSR 1) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 19:04 5 63.5 65.0 62.0 70.0 4-Jun-04 19:09 5 63.8 65.8 61.7 70.0 Generator 1 4-Jun-04 19:14 5 63.4 65.3 61.7 70.0 SA6A Air Compressor 2 4-Jun-04 19:19 5 63.0 64.2 61.4 70.0 Rock drill(hand-held) 2 4-Jun-04 19:24 5 62.3 63.2 60.7 70.0 4-Jun-04 19:29 5 63.5 64.8 61.7 70.0 11-Jun-04 20:04 5 64.5 65.5 63.1 70.0 11-Jun-04 20:09 5 63.9 65.9 62.8 70.0 Generator 1 11-Jun-04 20:14 5 63.5 65.2 61.9 70.0 SA6A Air Compressor 2 11-Jun-04 20:19 5 63.3 64.9 62.6 70.0 Rock drill(hand-held) 2 11-Jun-04 20:24 5 64.1 63.3 61.0 70.0 11-Jun-04 20:29 5 63.8 64.7 61.6 70.0 18-Jun-04 19:53 5 61.7 62.9 59.6 70.0 18-Jun-04 19:58 5 60.9 62.7 59.0 70.0 Generator 1 18-Jun-04 20:03 5 60.8 62.2 59.1 70.0 SA6A Air Compressor 2 18-Jun-04 20:08 5 60.3 61.5 58.9 70.0 Rock drill(hand-held) 2 18-Jun-04 20:13 5 61.4 62.8 60.0 70.0 18-Jun-04 20:18 5 61.8 62.8 59.6 70.0 23-Jun-04 19:04 5 62.7 64.1 60.6 70.0 23-Jun-04 19:09 5 63.4 64.7 61.8 70.0 Generator 1 23-Jun-04 19:14 5 64.1 66.0 61.6 70.0 SA6A Air Compressor 2 23-Jun-04 19:19 5 63.6 65.0 61.0 70.0 Rock drill(hand-held) 2 23-Jun-04 19:24 5 63.8 66.9 60.7 70.0 23-Jun-04 19:29 5 63.6 65.2 61.6 70.0 The Summary of Night-time Leq5 Level atHKIVE Fok Ying Tung Hall of Residence (NSR 1) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 23:09 5 58.6 59.8 57.5 55.0 Generator 1 4-Jun-04 23:14 5 58.9 60.4 57.3 55.0 SA6F Air Compressor 2 4-Jun-04 23:19 5 58.8 60.0 57.4 55.0 Rock drill(hand-held) 2 4-Jun-04 23:24 5 58.5 60.1 56.7 55.0 11-Jun-04 23:19 5 58.7 61.6 57.6 55.0 Generator 1 11-Jun-04 23:24 5 58.6 60.6 57.3 55.0 SA6F Air Compressor 2 11-Jun-04 23:29 5 58.2 60.8 57.7 55.0 Rock drill(hand-held) 2 11-Jun-04 23:34 5 58.6 60.3 56.9 55.0 18-Jun-04 23:03 5 57.8 58.4 54.9 55.0 Generator 1 18-Jun-04 23:08 5 57.0 58.6 55.1 55.0 SA6F Air Compressor 2 18-Jun-04 23:13 5 57.4 59.0 55.9 55.0 Rock drill(hand-held) 2 18-Jun-04 23:18 5 57.4 58.6 54.4 55.0 23-Jun-04 23:04 5 59.9 61.1 58.6 55.0 Generator 1 23-Jun-04 23:09 5 60.7 62.1 58.9 55.0 SA6F Air Compressor 2 23-Jun-04 23:14 5 60.6 62.7 58.4 55.0 Rock drill(hand-held) 2 23-Jun-04 23:19 5 60.4 61.9 58.6 55.0 The Summary of Public Holiday Leq5 Level at HKIVE Fok Ying Tung Hall of Residence (NSR 1) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 30-May-04 18:04 5 65.4 66.5 63.5 70.0 30-May-04 18:09 5 64.8 66.9 62.8 70.0 Generator 1 30-May-04 18:14 5 64.2 66.9 64.8 70.0 SA6A Air Compressor 2 30-May-04 19:19 5 64.9 67.6 63.1 70.0 Rock drill(hand-held) 2 30-May-04 18:24 5 64.8 66.5 63.5 70.0 30-May-04 19:29 5 64.9 66.3 63.1 70.0 6-Jun-04 9:02 5 60.5 62.0 58.8 70.0 6-Jun-04 9:07 5 60.7 61.9 59.0 70.0 Generator 1 6-Jun-04 9:12 5 60.3 61.5 59.1 70.0 SA6A Air Compressor 2 6-Jun-04 9:17 5 61.3 62.9 59.7 70.0 Rock drill(hand-held) 2 6-Jun-04 9:22 5 60.5 61.6 59.3 70.0 6-Jun-04 9:27 5 61.2 62.4 59.8 70.0 13-Jun-04 9:04 5 60.6 62.3 59.5 70.0 13-Jun-04 9:09 5 60.4 62.2 59.3 70.0 Generator 1 13-Jun-04 9:14 5 60.0 62.3 59.8 70.0 SA6A Air Compressor 2 13-Jun-04 9:19 5 60.3 62.8 59.9 70.0 Rock drill(hand-held) 2 13-Jun-04 9:24 5 61.6 62.9 59.1 70.0 13-Jun-04 9:29 5 61.2 62.6 59.5 70.0 20-Jun-04 9:04 5 61.5 62.9 60.0 70.0 20-Jun-04 9:09 5 60.7 61.8 59.3 70.0 Generator 1 20-Jun-04 9:14 5 61.3 62.8 59.5 70.0 SA6A Air Compressor 2 20-Jun-04 9:19 5 61.6 63.2 59.8 70.0 Rock drill(hand-held) 2 20-Jun-04 9:24 5 61.0 62.5 59.4 70.0 20-Jun-04 9:29 5 61.6 62.8 60.1 70.0 27-Jun-04 9:04 5 62.6 62.8 60.3 70.0 27-Jun-04 9:09 5 61.2 62.0 60.5 70.0 Generator 1 27-Jun-04 9:14 5 61.3 62.9 60.0 70.0 SA6A Air Compressor 2 27-Jun-04 9:19 5 61.6 63.1 59.9 70.0 Rock drill(hand-held) 2 27-Jun-04 9:24 5 61.2 63.0 59.4 70.0 27-Jun-04 9:29 5 62.0 63.1 60.2 70.0 The Summary of Evening-time Leq 5 Level at HKIVE 5th Floor Block D of Main Education Building (NSR 2) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 19:00 5 63.9 65.4 62.3 70.0 4-Jun-04 19:05 5 65.4 67.8 62.3 70.0 Generator 1 4-Jun-04 19:10 5 64.2 65.7 62.0 70.0 SA6A Air Compressor 2 4-Jun-04 19:15 5 64.1 65.9 61.8 70.0 Rock drill(hand-held) 2 4-Jun-04 19:20 5 64.0 65.0 62.0 70.0 4-Jun-04 19:25 5 62.0 63.0 60.8 70.0 11-Jun-04 19:02 5 64.0 65.7 61.8 70.0 11-Jun-04 19:07 5 64.3 66.5 62.1 70.0 SA6A Generator 1 11-Jun-04 19:12 5 65.0 67.4 62.1 70.0 Air Compressor 2 11-Jun-04 19:17 5 63.8 65.5 61.8 70.0 Rock drill(hand-held) 2 11-Jun-04 19:22 5 63.9 65.2 61.3 70.0 11-Jun-04 19:27 5 62.2 63.5 60.6 70.0 18-Jun-04 19:00 5 69.6 70.0 67.0 70.0 18-Jun-04 19:05 5 69.3 69.4 65.9 70.0 SA6A Generator 1 18-Jun-04 19:10 5 68.6 69.5 66.4 70.0 Air Compressor 2 18-Jun-04 19:15 5 69.6 70.7 66.7 70.0 Rock drill(hand-held) 2 18-Jun-04 19:20 5 69.9 70.5 65.9 70.0 18-Jun-04 19:25 5 69.6 69.9 66.9 70.0 23-Jun-04 19:11 5 81.0 73.7 68.8 70.0 23-Jun-04 19:16 5 71.9 70.5 67.6 70.0 Generator 1 23-Jun-04 19:21 5 69.1 70.3 67.4 70.0 SA6A Air Compressor 2 23-Jun-04 19:26 5 75.4 72.9 69.4 70.0 Rock drill(hand-held) 2 23-Jun-04 19:31 5 73.2 72.4 68.4 70.0 23-Jun-04 19:36 5 78.6 72.4 67.6 70.0 The Summary of Night-time Leq5 Level at HKIVE 5th Floor Block D of Main Education Building (NSR 2) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 23:40 5 58.9 60.0 57.3 55.0 Generator 1 4-Jun-04 23:45 5 58.2 59.4 56.9 55.0 SA6F Air Compressor 2 4-Jun-04 23:50 5 58.1 59.1 56.6 55.0 Rock drill(hand-held) 2 4-Jun-04 23:55 5 58.5 59.3 56.7 55.0 11-Jun-04 23:02 5 60.8 61.8 59.1 55.0 Generator 1 11-Jun-04 23:07 5 60.3 61.4 59.0 55.0 SA6F Air Compressor 2 11-Jun-04 23:12 5 60.9 61.8 59.3 55.0 Rock drill(hand-held) 2 11-Jun-04 23:17 5 62.9 66.2 59.9 55.0 18-Jun-04 23:00 5 68.2 69.2 66.5 55.0 Generator 1 18-Jun-04 23:05 5 71.5 70.4 66.0 55.0 SA6F Air Compressor 2 18-Jun-04 23:10 5 68.9 69.7 66.8 55.0 Rock drill(hand-held) 2 18-Jun-04 23:15 5 75.5 69.6 65.8 55.0 23-Jun-04 23:01 5 81.4 76.4 67.6 55.0 Generator 1 23-Jun-04 23:06 5 80.2 77.8 67.8 55.0 SA6F Air Compressor 2 23-Jun-04 23:11 5 74.1 72.7 67.1 55.0 Rock drill(hand-held) 2 23-Jun-04 23:16 5 78.2 76.9 67.9 55.0 The Summary of Public Holiday Leq5 Level at HKIVE 5th Floor Block D of Main Education Building (NSR 2) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 30-May-04 9:04 5 65.5 66.6 63.0 70.0 30-May-04 9:09 5 69.3 72.0 63.3 70.0 Generator 1 30-May-04 9:14 5 68.3 71.0 63.5 70.0 SA6A Air Compressor 2 30-May-04 9:19 5 68.4 67.8 63.1 70.0 Rock drill(hand-held) 2 30-May-04 9:24 5 68.6 66.5 63.1 70.0 30-May-04 9:29 5 68.3 67.2 63.3 70.0 6-Jun-04 9:00 5 63.1 64.5 60.4 70.0 6-Jun-04 9:05 5 62.5 63.6 59.9 70.0 Generator 1 6-Jun-04 9:10 5 62.2 63.4 60.6 70.0 SA6A Air Compressor 2 6-Jun-04 9:15 5 62.3 63.5 60.1 70.0 Rock drill(hand-held) 2 6-Jun-04 9:20 5 63.1 64.9 60.5 70.0 6-Jun-04 9:25 5 61.4 62.9 59.6 70.0 13-Jun-04 9:02 5 65.2 67.6 62.0 70.0 13-Jun-04 9:07 5 65.3 68.0 61.7 70.0 Generator 1 13-Jun-04 9:12 5 68.4 69.2 61.7 70.0 SA6A Air Compressor 2 13-Jun-04 9:17 5 67.7 69.3 62.3 70.0 Rock drill(hand-held) 2 13-Jun-04 9:22 5 66.4 67.8 61.8 70.0 13-Jun-04 9:27 5 66.9 68.2 61.3 70.0 20-Jun-04 9:35 5 68.7 69.3 65.0 70.0 20-Jun-04 9:40 5 66.5 68.3 64.5 70.0 Generator 1 20-Jun-04 9:45 5 66.1 67.4 64.1 70.0 SA6A Air Compressor 2 20-Jun-04 9:50 5 69.7 68.6 64.0 70.0 Rock drill(hand-held) 2 20-Jun-04 9:55 5 69.8 69.6 64.3 70.0 20-Jun-04 10:00 5 69.5 69.3 64.5 70.0 27-Jun-04 9:01 5 72.8 72.6 69.3 70.0 27-Jun-04 9:06 5 71.9 72.0 69.0 70.0 Generator 1 27-Jun-04 9:11 5 72.5 72.7 69.0 70.0 SA6A Air Compressor 2 27-Jun-04 9:16 5 72.9 72.9 68.7 70.0 Rock drill(hand-held) 2 27-Jun-04 9:21 5 72.9 72.0 68.8 70.0 27-Jun-04 9:26 5 71.6 72.2 69.2 70.0 The Summary of Evening-time Leq5 Level at Mayfair Gardens 1st floor adjacent to swimming pool (NSR 3) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 19:00 5 72.7 72.5 69.4 70.0 4-Jun-04 19:05 5 70.6 71.7 68.8 70.0 Generator 1 4-Jun-04 19:10 5 71.7 72.6 69.5 70.0 SA6A Air Compressor 2 4-Jun-04 19:15 5 70.6 71.7 68.8 70.0 Rock drill(hand-held) 2 4-Jun-04 19:20 5 72.5 72.6 69.8 70.0 4-Jun-04 19:25 5 71.7 71.9 68.8 70.0 11-Jun-04 20:28 5 79.3 74.7 68.4 70.0 11-Jun-04 20:33 5 79.8 71.0 63.9 70.0 Generator 1 11-Jun-04 20:38 5 80.9 75.2 66.7 70.0 SA6A Air Compressor 2 11-Jun-04 20:43 5 79.5 73.3 67.6 70.0 Rock drill(hand-held) 2 11-Jun-04 20:48 5 80.3 73.1 68.1 70.0 11-Jun-04 20:53 5 80.8 78.2 68.8 70.0 18-Jun-04 19:00 5 73.2 74.1 70.9 70.0 18-Jun-04 19:05 5 75.5 75.7 72.1 70.0 Generator 1 18-Jun-04 19:10 5 74.0 74.4 71.4 70.0 SA6A Air Compressor 2 18-Jun-04 19:15 5 73.5 73.6 70.1 70.0 Rock drill(hand-held) 2 18-Jun-04 19:20 5 72.4 73.4 69.9 70.0 18-Jun-04 19:25 5 73.1 74.1 70.6 70.0 23-Jun-04 19:00 5 81.3 79.7 70.7 70.0 23-Jun-04 19:05 5 81.7 78.8 71.4 70.0 Generator 1 23-Jun-04 19:10 5 80.1 78.5 72.2 70.0 SA6A Air Compressor 2 23-Jun-04 19:15 5 81.4 80.1 70.0 70.0 Rock drill(hand-held) 2 23-Jun-04 19:20 5 78.5 78.2 70.6 70.0 23-Jun-04 19:25 5 78.8 78.6 70.7 70.0 The Summary of Night-time Leq5 Level at Mayfair Gardens 1st floor adjacent to swimming pool (NSR 3) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 1:15 5 69.0 70.0 67.8 55.0 Generator 1 4-Jun-04 1:20 5 72.3 71.2 68.0 55.0 SA6F Air Compressor 2 4-Jun-04 1:25 5 72.1 72.9 69.2 55.0 Rock drill(hand-held) 2 4-Jun-04 1:30 5 72.2 72.4 69.8 55.0 11-Jun-04 1:08 5 76.5 72.0 68.3 55.0 Generator 1 11-Jun-04 1:13 5 74.5 72.9 67.9 55.0 SA6F Air Compressor 2 11-Jun-04 1:18 5 75.5 70.0 67.2 55.0 Rock drill(hand-held) 2 11-Jun-04 1:23 5 80.7 73.2 66.5 55.0 18-Jun-04 23:05 5 80.4 76.3 72.8 55.0 Generator 1 18-Jun-04 23:10 5 75.0 76.1 72.5 55.0 SA6F Air Compressor 2 18-Jun-04 23:15 5 74.5 75.7 71.8 55.0 Rock drill(hand-held) 2 18-Jun-04 23:20 5 75.6 76.0 71.4 55.0 23-Jun-04 23:30 5 81.5 78.2 72.7 55.0 Generator 1 23-Jun-04 23:35 5 81.5 78.2 72.0 55.0 SA6F Air Compressor 2 23-Jun-04 23:40 5 78.9 76.3 70.2 55.0 Rock drill(hand-held) 2 23-Jun-04 23:45 5 81.3 77.3 71.1 55.0 The Summary of Public Holiday Leq5 Level at Mayfair Gardens 1st floor adjacent to swimming pool (NSR 3) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 30-May-04 12:53 5 69.9 73.3 70.3 70.0 30-May-04 12:58 5 69.8 72.7 69.6 70.0 Generator 1 30-May-04 13:03 5 69.0 73.4 70.2 70.0 SA6A Air Compressor 2 30-May-04 13:08 5 69.6 72.7 70.0 70.0 Rock drill(hand-held) 2 30-May-04 13:13 5 69.8 73.1 70.3 70.0 30-May-04 13:18 5 69.5 72.8 69.9 70.0 6-Jun-04 9:25 5 70.3 70.3 66.3 70.0 6-Jun-04 9:30 5 72.3 72.2 68.9 70.0 Generator 1 6-Jun-04 9:35 5 69.8 70.4 67.5 70.0 SA6A Air Compressor 2 6-Jun-04 9:40 5 71.2 72.3 69.2 70.0 Rock drill(hand-held) 2 6-Jun-04 9:45 5 72.6 73.8 69.8 70.0 6-Jun-04 9:50 5 71.3 72.8 68.2 70.0 13-Jun-04 9:03 5 69.1 72.0 64.4 70.0 13-Jun-04 9:08 5 69.5 71.9 66.5 70.0 Generator 1 13-Jun-04 9:13 5 67.7 70.2 63.3 70.0 SA6A Air Compressor 2 13-Jun-04 9:18 5 67.5 70.3 63.9 70.0 Rock drill(hand-held) 2 13-Jun-04 9:23 5 65.9 68.3 62.3 70.0 13-Jun-04 9:28 5 66.4 68.9 62.7 70.0 20-Jun-04 9:00 5 80.4 76.1 70.5 70.0 20-Jun-04 9:05 5 78.1 73.4 70.9 70.0 Generator 1 20-Jun-04 9:10 5 71.1 72.2 69.6 70.0 SA6A Air Compressor 2 20-Jun-04 9:15 5 71.4 71.0 68.5 70.0 Rock drill(hand-held) 2 20-Jun-04 9:20 5 73.7 73.9 69.5 70.0 20-Jun-04 9:25 5 76.9 73.8 69.6 70.0 27-Jun-04 10:06 5 71.9 72.9 70.7 70.0 27-Jun-04 10:11 5 72.0 73.0 70.8 70.0 Generator 1 27-Jun-04 10:16 5 72.4 73.5 70.9 70.0 SA6A Air Compressor 2 27-Jun-04 10:21 5 71.6 72.7 70.2 70.0 Rock drill(hand-held) 2 27-Jun-04 10:26 5 71.2 72.3 69.9 70.0 27-Jun-04 10:31 5 71.3 72.5 69.8 70.0 The Summary of Evening-time Leq5 Level at Cheung Ching Estate at the Roof of Ching Yung House (NSR 4) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 19:01 5 64.9 67.8 60.1 70.0 4-Jun-04 19:06 5 66.8 69.2 61.1 70.0 Generator 1 4-Jun-04 19:11 5 64.7 67.3 61.2 70.0 SA6A Air Compressor 2 4-Jun-04 19:16 5 66.8 69.0 62.6 70.0 Rock drill(hand-held) 2 4-Jun-04 19:21 5 65.4 67.6 61.9 70.0 4-Jun-04 19:26 5 64.2 66.7 60.4 70.0 11-Jun-04 19:55 5 63.4 63.7 57.8 70.0 11-Jun-04 20:00 5 62.8 63.9 59.3 70.0 Generator 1 11-Jun-04 20:05 5 62.9 64.4 58.8 70.0 SA6A Air Compressor 2 11-Jun-04 20:10 5 62.1 62.8 58.5 70.0 Rock drill(hand-held) 2 11-Jun-04 20:15 5 70.0 63.6 58.8 70.0 11-Jun-04 20:20 5 62.4 63.8 58.3 70.0 18-Jun-04 19:04 5 53.2 54.3 51.9 70.0 18-Jun-04 19:09 5 53.0 54.3 51.5 70.0 Generator 1 18-Jun-04 19:14 5 53.6 55.5 51.6 70.0 SA6A Air Compressor 2 18-Jun-04 19:19 5 56.1 57.7 53.6 70.0 Rock drill(hand-held) 2 18-Jun-04 19:24 5 56.2 58.7 53.0 70.0 18-Jun-04 19:29 5 55.5 57.7 52.5 70.0 23-Jun-04 19:00 5 53.0 54.1 51.7 70.0 23-Jun-04 19:05 5 70.2 55.1 50.3 70.0 Generator 1 23-Jun-04 19:10 5 51.9 53.3 50.7 70.0 SA6A Air Compressor 2 23-Jun-04 19:15 5 51.6 52.3 50.7 70.0 Rock drill(hand-held) 2 23-Jun-04 19:20 5 52.3 53.1 51.3 70.0 23-Jun-04 19:25 5 53.0 53.9 52.1 70.0 The Summary of Night-time Leq5 Level at Cheung Ching Estate at the Roof of Ching Yung House (NSR 4) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 4-Jun-04 2:01 5 55.2 57.8 51.9 55.0 Generator 1 4-Jun-04 2:06 5 55.4 57.7 51.1 55.0 SA6F Air Compressor 2 4-Jun-04 2:11 5 55.6 59.2 50.7 55.0 Rock drill(hand-held) 2 4-Jun-04 2:16 5 56.4 59.9 52.0 55.0 11-Jun-04 1:30 5 59.5 59.7 54.9 55.0 Generator 1 11-Jun-04 1:35 5 59.4 59.2 54.9 55.0 SA6F Air Compressor 2 11-Jun-04 1:40 5 60.2 60.3 55.4 55.0 Rock drill(hand-held) 2 11-Jun-04 1:45 5 58.7 57.9 54.2 55.0 18-Jun-04 23:29 5 53.9 55.1 52.6 55.0 Generator 1 18-Jun-04 23:34 5 54.0 55.5 52.2 55.0 SA6F Air Compressor 2 18-Jun-04 23:39 5 53.9 55.3 52.1 55.0 Rock drill(hand-held) 2 18-Jun-04 23:44 5 54.4 56.2 52.3 55.0 23-Jun-04 23:00 5 54.8 55.3 54.2 55.0 Generator 1 23-Jun-04 23:05 5 54.9 55.4 54.3 55.0 SA6F Air Compressor 2 23-Jun-04 23:10 5 54.9 55.5 54.3 55.0 Rock drill(hand-held) 2 23-Jun-04 23:15 5 54.3 55.0 53.6 55.0 The Summary of Public Holiday Leq5 Level at Cheung Ching Estate at the Roof of Ching Yung House (NSR 4) Date Monitoring Time Duration Leq L10 L90 Limit Level Area PME Opreated min dB(A) dB(A) dB(A) dB(A) Description No. 30-May-04 9:00 5 62.1 65.5 56.5 70.0 30-May-04 9:05 5 61.5 64.4 56.7 70.0 Generator 1 30-May-04 9:10 5 62.5 65.9 57.1 70.0 SA6A Air Compressor 2 30-May-04 9:15 5 64.0 66.9 57.3 70.0 Rock drill(hand-held) 2 30-May-04 9:20 5 62.6 65.6 58.0 70.0 30-May-04 9:25 5 67.6 65.8 57.9 70.0 6-Jun-04 9:01 5 63.7 67.3 56.5 70.0 6-Jun-04 9:06 5 61.4 64.9 55.5 70.0 Generator 1 6-Jun-04 9:11 5 62.4 65.2 56.9 70.0 SA6A Air Compressor 2 6-Jun-04 9:16 5 62.4 66.0 56.5 70.0 Rock drill(hand-held) 2 6-Jun-04 9:21 5 62.5 66.1 56.2 70.0 6-Jun-04 9:26 5 61.4 65.3 55.5 70.0 13-Jun-04 9:00 5 65.9 66.5 61.0 70.0 13-Jun-04 9:05 5 66.0 67.2 59.8 70.0 Generator 1 13-Jun-04 9:10 5 64.9 67.4 60.9 70.0 SA6A Air Compressor 2 13-Jun-04 9:15 5 62.2 64.9 58.1 70.0 Rock drill(hand-held) 2 13-Jun-04 9:20 5 64.3 68.3 57.8 70.0 13-Jun-04 9:25 5 64.9 67.8 58.9 70.0 20-Jun-04 9:04 5 61.6 63.3 59.0 70.0 20-Jun-04 9:09 5 61.7 64.0 59.2 70.0 Generator 1 20-Jun-04 9:14 5 60.4 61.6 59.1 70.0 SA6A Air Compressor 2 20-Jun-04 9:19 5 63.5 63.0 59.3 70.0 Rock drill(hand-held) 2 20-Jun-04 9:24 5 63.3 61.7 59.0 70.0 20-Jun-04 9:29 5 62.6 61.5 58.8 70.0 27-Jun-04 9:00 5 52.8 55.0 49.7 70.0 27-Jun-04 9:05 5 53.5 55.8 50.8 70.0 Generator 1 27-Jun-04 9:10 5 53.8 56.0 50.3 70.0 SA6A Air Compressor 2 27-Jun-04 9:15 5 53.7 55.9 50.9 70.0 Rock drill(hand-held) 2 27-Jun-04 9:20 5 53.2 55.2 50.0 70.0 27-Jun-04 9:25 5 53.3 55.6 50.6 70.0 Appendix N1

Graphical Presentation of Noise Monitoring Results for Normal Hour Day-time Leq30 Level at HKIVE Fok Ying Tung Hall of Residence (NSR1)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04 -04 -04 -04 0 -04 -04 -04 -04 -04 -0 -0 -0 -0 -04 0 0 0 0 -0 04 04 04 04 0 -04 -04 -04 g- p- p- p- v-0 v-0 c-0 c-0 n- n- b- r r r r r- r- r- r- y- y- y- y- n- u e e e ct-0 ct-0 e eb eb eb ar ar p p p p ay Oct- Oct- Oct- Jan Jan Jan Jan F F F Ma Ma Ma Ma A A A A Jun Jun Jun A -Sep -Sep S S S -O -O -No -No Nov- Nov- Nov--De -De Dec- Dec- Dec--Ja -Ja -F -M -M -Apr -M Ma Ma Ma Ma -Ju 8- 3 9 5- 1- 7- 3 9 5- 1- 7- 2 8 4- 0- 6- 2 8 4- 0- 6- 1 7 3- 9- 5- 1- 6 2- 8- 4- 1 7 3- 9- 5- 1- 6 2- 8- 4- 0- 6 2- 8- 4- 0- 5 1- 7- 3- 2 1 2 2 1 2 2 1 2 2 1 2 2 1 1 2 3 1 1 2 1 1 2 3 1 1 2 3 1 1 2 3 1 1 2 Date Day-time Leq30 Level at HKIVE 5th Floor Block D of the Main Education Building (NSR2)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04 -04 -04 -04 0 -04 -04 -04 -04 -04 -0 -0 -0 -0 -04 0 0 0 0 -0 04 04 04 04 0 -04 -04 -04 g- p- p- p- v-0 v-0 c-0 c-0 n- n- b- r r r r r- r- r- r- y- y- y- y- n- u e e e ct-0 ct-0 e eb eb eb ar ar p p p p ay Oct- Oct- Oct- Jan Jan Jan Jan F F F Ma Ma Ma Ma A A A A Jun Jun Jun A -Sep -Sep S S S -O -O -No -No Nov- Nov- Nov--De -De Dec- Dec- Dec--Ja -Ja -F -M -M -Apr -M Ma Ma Ma Ma -Ju 8- 3 9 5- 1- 7- 3 9 5- 1- 7- 2 8 4- 0- 6- 2 8 4- 0- 6- 1 7 3- 9- 5- 1- 6 2- 8- 4- 1 7 3- 9- 5- 1- 6 2- 8- 4- 0- 6 2- 8- 4- 0- 5 1- 7- 3- 2 1 2 2 1 2 2 1 2 2 1 2 2 1 1 2 3 1 1 2 1 1 2 3 1 1 2 3 1 1 2 3 1 1 2 Date Day-time Leq30 Level at Mayfair Gardens 1st floor adjacent to swimming pool (NSR3)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04 -04 -04 -04 0 -04 -04 -04 -04 -04 -0 -0 -0 -0 -04 0 0 0 0 -0 04 04 04 04 0 -04 -04 -04 g- p- p- p- v-0 v-0 c-0 c-0 n- n- b- r r r r r- r- r- r- y- y- y- y- n- u e e e ct-0 ct-0 e eb eb eb ar ar p p p p ay Oct- Oct- Oct- Jan Jan Jan Jan F F F Ma Ma Ma Ma A A A A Jun Jun Jun A -Sep -Sep S S S -O -O -No -No Nov- Nov- Nov--De -De Dec- Dec- Dec--Ja -Ja -F -M -M -Apr -M Ma Ma Ma Ma -Ju 8- 3 9 5- 1- 7- 3 9 5- 1- 7- 2 8 4- 0- 6- 2 8 4- 0- 6- 1 7 3- 9- 5- 1- 6 2- 8- 4- 1 7 3- 9- 5- 1- 6 2- 8- 4- 0- 6 2- 8- 4- 0- 5 1- 7- 3- 2 1 2 2 1 2 2 1 2 2 1 2 2 1 1 2 3 1 1 2 1 1 2 3 1 1 2 3 1 1 2 3 1 1 2 Date Day-time Leq30 Level at Cheung Ching Estate at the Roof of Ching Yung House (NSR4)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 4 4 0 -0 -0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 -04 -04 -04 -04 0 -04 -04 -04 -04 -04 -0 -0 -0 -0 -04 0 0 0 0 -0 04 04 04 04 0 -04 -04 -04 g- p- p- p- v-0 v-0 c-0 c-0 n- n- b- r r r r r- r- r- r- y- y- y- y- n- u e e e ct-0 ct-0 e eb eb eb ar ar p p p p ay Oct- Oct- Oct- Jan Jan Jan Jan F F F Ma Ma Ma Ma A A A A Jun Jun Jun A -Sep -Sep S S S -O -O -No -No Nov- Nov- Nov--De -De Dec- Dec- Dec--Ja -Ja -F -M -M -Apr -M Ma Ma Ma Ma -Ju 8- 3 9 5- 1- 7- 3 9 5- 1- 7- 2 8 4- 0- 6- 2 8 4- 0- 6- 1 7 3- 9- 5- 1- 6 2- 8- 4- 1 7 3- 9- 5- 1- 6 2- 8- 4- 0- 6 2- 8- 4- 0- 5 1- 7- 3- 2 1 2 2 1 2 2 1 2 2 1 2 2 1 1 2 3 1 1 2 1 1 2 3 1 1 2 3 1 1 2 3 1 1 2 Date Appendix N2

Graphical Presentation of Noise Monitoring Results for Restricted Hour Evening-time Leq5 Level at HKIVE Fok Ying Tung Hall of Residence (NSR1)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 0 -04 -04 -04 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- r r r r- r- r- y- y- y- n- e eb eb ar p p p ay Jan Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- Nov- -De Dec- Dec- Dec- -Ja -F -M -Apr -M Ma Ma Ma -Ju 0- 8- 6 4- 2- 0- 7 5- 3- 1- 8 6- 4- 3 1- 9- 7- 4 2- 0- 8- 6 4- 2- 0- 7 5- 3- 2 2 1 2 3 1 2 3 1 2 1 1 2 1 2 2 1 2 3 1 2 Date Night-time Leq5 Level at HKIVE Fok Ying Tung Hall of Residence (NSR1)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

4 4 4 4 4 4 4 4 4 4 4 04 04 04 0 0 0 0 04 04 04 04 0 0 04 04 04 - - r-0 r-0 r-0 r-0 - r- r- r- r- -0 y- y- y- y- - - - ar p p p p ay n- n- eb A A A A Jun Jun Jun F -M Ma Ma Ma Ma -Apr -M Ma Ma Ma Ma -Ju -Ju 8- 5 1- 7- 3- 9- 4 0- 6- 2- 8- 4 0- 6- 2- 8- 3 9 5- 1- 7- 2 1 1 2 2 1 1 2 2 1 1 2 2 1 2 2 Date Public Holiday Leq5 Level at HKIVE Fok Ying Tung Hall of Residence (NSR1)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 -04 -04 0 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- b- r r r r- r- r- y- y- y- n- e e eb eb ar p p p ay Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- -De Dec- Dec- Dec- -Ja -F -F -M -Apr -M Ma Ma Ma -Ju 9- 7 5- 3- 1- 8 6- 4- 1 9 7- 5- 4 2- 0- 8- 5 3- 1- 9- 7 5- 3- 1- 8 6- 4- 2 1 2 3 1 2 1 2 1 2 2 1 2 2 1 2 3 1 2 Date Evening-time Leq5 Level at HKIVE 5th Floor Block D of the Main Education Building (NSR2)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 0 -04 -04 -04 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- r r r r- r- r- y- y- y- n- e eb eb ar p p p ay Jan Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- Nov- -De Dec- Dec- Dec- -Ja -F -M -Apr -M Ma Ma Ma -Ju 0- 8- 6 4- 2- 0- 7 5- 3- 1- 8 6- 4- 3 1- 9- 7- 4 2- 0- 8- 6 4- 2- 0- 7 5- 3- 2 2 1 2 3 1 2 3 1 2 1 1 2 1 2 2 1 2 3 1 2 Date Night-time Leq5 Level at HKIVE 5th Floor Block D of the Main Education Building (NSR2)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

4 4 4 4 4 4 4 04 04 04 0 0 04 04 04 0 04 04 04 - - r-0 r-0 r-0 - r- r- -0 y- y- y- - - - ar p p ay n- eb A A Jun Jun Jun F -M Ma Ma Ma -Apr -M Ma Ma Ma -Ju 8- 7 5- 3- 1- 8 6- 4- 2 0- 8- 6- 3 1- 9- 7- 2 1 2 3 1 2 1 1 2 1 1 2 Date Public Holiday Leq5 Level at HKIVE 5th Floor Block D of Main Education Building (NSR2)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 -04 -04 0 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- b- r r r r- r- r- y- y- y- n- e e eb eb ar p p p ay Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- -De Dec- Dec- Dec- -Ja -F -F -M -Apr -M Ma Ma Ma -Ju 9- 7 5- 3- 1- 8 6- 4- 1 9 7- 5- 4 2- 0- 8- 5 3- 1- 9- 7 5- 3- 1- 8 6- 4- 2 1 2 3 1 2 1 2 1 2 2 1 2 2 1 2 3 1 2 Date Evening-time Leq5 Level at Mayfair Gardens 1st floor adjacent to swimming pool (NSR3)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 0 -04 -04 -04 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- r r r r- r- r- y- y- y- n- e eb eb ar p p p ay Jan Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- Nov- -De Dec- Dec- Dec- -Ja -F -M -Apr -M Ma Ma Ma -Ju 0- 8- 6 4- 2- 0- 7 5- 3- 1- 8 6- 4- 3 1- 9- 7- 4 2- 0- 8- 6 4- 2- 0- 7 5- 3- 2 2 1 2 3 1 2 3 1 2 1 1 2 1 2 2 1 2 3 1 2 Date Night-time Leq5 Level at Mayfair Gardens 1st Floor adjacent to swimming pool (NSR3)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

4 4 4 4 4 4 04 04 04 04 0 0 04 04 04 0 04 04 04 - - r-0 r-0 - - r- r- -0 y- y- y- - - - ar p p ay n- eb A A Jun Jun Jun F -M Ma Ma -Apr -Apr -M Ma Ma Ma -Ju 9- 8 6- 4- 1 9 7- 5- 3 1- 9- 7- 4 2- 0- 8- 2 1 2 1 2 1 1 2 1 2 2 Date Public Holiday Leq5 Level at Mayfair Gardens 1st Floor adjacent to swimming pool (NSR3)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 -04 -04 0 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- b- r r r r- r- r- y- y- y- n- e e eb eb ar p p p ay Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- -De Dec- Dec- Dec- -Ja -F -F -M -Apr -M Ma Ma Ma -Ju 9- 7 5- 3- 1- 8 6- 4- 1 9 7- 5- 4 2- 0- 8- 5 3- 1- 9- 7 5- 3- 1- 8 6- 4- 2 1 2 3 1 2 1 2 1 2 2 1 2 2 1 2 3 1 2 Date Evening-time Leq5 Level at Cheung Ching Estate at the Roof of Ching Yung House (NSR4)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 0 -04 -04 -04 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- r r r r- r- r- y- y- y- n- e eb eb ar p p p ay Jan Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- Nov- -De Dec- Dec- Dec- -Ja -F -M -Apr -M Ma Ma Ma -Ju 0- 8- 6 4- 2- 0- 7 5- 3- 1- 8 6- 4- 3 1- 9- 7- 4 2- 0- 8- 6 4- 2- 0- 7 5- 3- 2 2 1 2 3 1 2 3 1 2 1 1 2 1 2 2 1 2 3 1 2 Date Night-time Leq5 Level at Cheung Ching Estate at roof of Ching Ying House (NSR4)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

4 4 4 4 4 4 04 04 04 04 0 0 04 04 04 0 04 04 04 - - r-0 r-0 - - r- r- -0 y- y- y- - - - ar p p ay n- eb A A Jun Jun Jun F -M Ma Ma -Apr -Apr -M Ma Ma Ma -Ju 9- 8 6- 4- 1 9 7- 5- 3 1- 9- 7- 4 2- 0- 8- 2 1 2 1 2 1 1 2 1 2 2 Date Public Holiday Leq5 Level at Cheung Ching Estate at roof of Ching Ying House (NSR4)

Leq Limit Level

100

90

80

70 Leq dB(A)

60

50

40

3 3 3 3 3 4 4 4 4 4 4 4 4 4 4 4 0 0 0 0 0 -04 -04 0 0 -04 -04 -04 -0 -0 -0 -04 0 0 0 -0 04 04 04 0 -04 -04 c-0 n- b- b- r r r r- r- r- y- y- y- n- e e eb eb ar p p p ay Jan Jan F F Ma Ma Ma A A A Jun Jun Nov- -De Dec- Dec- Dec- -Ja -F -F -M -Apr -M Ma Ma Ma -Ju 9- 7 5- 3- 1- 8 6- 4- 1 9 7- 5- 4 2- 0- 8- 5 3- 1- 9- 7 5- 3- 1- 8 6- 4- 2 1 2 3 1 2 1 2 1 2 2 1 2 2 1 2 3 1 2 Date Appendix O1

Environmental Complaint Log Book Appendix O1-Summary of Previous Complaints Details

Case No Date of Date of Complainant's Detail's of complaint Investigation Follow-up Action / Status/Remarks Received Complaint information Recommended Mitigation Measures EC01 Passed on to EPD No detail is The complainant In accordance with the EM&A Manual the ER carried EPD had already informed the Closed. the ET on received the available. The enquired about the out an investigation and confirmed that the works complainant that the works 29th April complaint on complainant is a construction noise he carried out during the early hours were governed by being carried out at the West 2004. 1600hr, 28 frequent road heard at 1:30am on valid CNP and that all equipment used complied with Portal are being done under a April 2004. user at the several nights (exact the CNP conditions. A follow-up phone call was made valid CNP and that there are Cheung Tsing dates not known) by ER to EPD on 30th April 2004 and EPD was no sensitive receivers in the Highway. coming from the West satisfied with the investigation result. A letter from ER near by area and therefore Portal area while he was subsequently sent to EPD on 3rd May 2004. No noise impact is not was travelling along further follow up action is required. anticipated. Cheung Tsing Highway. He was concerned whether construction work is allowed and nuisance to the near by residents.

EC02 Passed on to EPD No detail is The complainant A joint site investigation was carried out amongst EPD, GSIJV agreed to increase the Closed. the ET on received the available. concerned on the dust GSIJV and RSS on 10 May 2004 and it was found that frequency of water spraying by 10/5/2004 complaint on emission generated sufficient water sprinklers and hoses were provided to water bowsers and 3 no.of 5 May 2004 from both the vehicular maintain the haul roads in moist condition. Dusty water sprinklers for the movement and the material had been wetted before loading to dump stockpile at the West Portal. handling of temporary trucks in order to minimize the potential dust impact. stockpile within the site No dust emission was observed during the site adjacent to Sai Tso investigation. No further follow up action is required. Wan Road (West Portal)

1 of 1 Appendix O2

Cumulative Statistics for Environmental Complaint Appendix O2 - Cumulative Statistics of Complaints

Route 8 Nam Wan Tunnel and West Tsing Yi Viaduct

Cumulative Statistics on Complaints for All Reporting Periods

5 5 No. of Complaints Cumulative Complaints 4 4

3 3

2 2 No. of Complaints No. of Cumulative Complaints Cumulative 1 1

0 0

3 3 3 4 4 4 4 4 4 0 0 /8/0 /9/0 /2/0 /3/0 /4/0 /5/0 /6/0 8 8 /10/ 8/1/ 8 8 8 8 8 8 8/11/03 8/12/03 2 3-2 3-2 2 2 4-2 4-2 4-2 4-2 4-2 0 0 3-2 0 0 0 0 0 0 1/8/ 9/8/ 9/1/ 9/2/ 9/3/ 9/4/ 9/5/ 2 2 9/9/ 9/12/03- 2 2 2 2 2 2 9/10/03- 9/11/03- 2 2 2 Monitoring Period Appendix P

Tentative Environmental Monitoring Schedule for the Next Three Months Tentative Environmental Monitoring Schedule between 29 June and 28 July 2004 Sunday Monday Tuesday Wednesday Thursday Friday Saturday 29-Jun 30-Jun 1-Jul 2-Jul 3-Jul 24hrs-TSP Noise 1hr-TSP

Noiseevening

Noisenight

4-Jul 5-Jul 6-Jul 7-Jul 8-Jul 9-Jul 10-Jul

NoiseP.H. 24hrs-TSP Noise 1hr-TSP 24hrs-TSP

Noiseevening

Noisenight

11-Jul 12-Jul 13-Jul 14-Jul 15-Jul 16-Jul 17-Jul

NoiseP.H. 1hr-TSP Noise 24hrs-TSP

Noiseevening

Noisenight

18-Jul 19-Jul 20-Jul 21-Jul 22-Jul 23-Jul 24-Jul

NoiseP.H. 1hr-TSP 24hrs-TSP Noise

Noiseevening

Noisenight

25-Jul 26-Jul 27-Jul 28-Jul

NoiseP.H. 1hr-TSP 24hrs-TSP

1hr-TSP 3 x 1 hour TSP monitoring at ASR1 to ASR4 during 0900~1800. 24hrs-TSP 24 hours TSP monitoring at ASR1 to ASR4 Noise Leq30 measurement at NSR1 to NSR4 during 0700~1900. NoiseEvening 6 x Leq5 will be measured at NSR1 to NSR4 during 1900~2300 (if construction activities are undertaken). NoiseNight 4 x Leq5 will be measured at NSR1 to NSR4 during 2300~0700 next day (if construction activities are undertaken). NoiseP.H. 6 x Leq5 will be measured at NSR1 to NSR4 during 0700~1900 (if construction activities are undertaken). Tentative Environmental Monitoring Schedule between 29 July and 28 August 2004 Sunday Monday Tuesday Wednesday Thursday Friday Saturday 29-Jul 30-Jul 31-Jul Noise 1hr-TSP

Noiseevening

Noisenight

1-Aug 2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug

NoiseP.H. 24hrs-TSP Noise 1hr-TSP

Noiseevening

Noisenight

8-Aug 9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug

NoiseP.H. 24hrs-TSP 1hr-TSP Noise 24hrs-TSP

Noiseevening

Noisenight

15-Aug 16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug

NoiseP.H. 1hr-TSP Noise 24hrs-TSP

Noiseevening

Noisenight

22-Aug 23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug

NoiseP.H. 1hr-TSP 24hrs-TSP Noise

Noiseevening

Noisenight

1hr-TSP 3 x 1 hour TSP monitoring at ASR1 to ASR4 during 0900~1800. 24hrs-TSP 24 hours TSP monitoring at ASR1 to ASR4 Noise Leq30 measurement at NSR1 to NSR4 during 0700~1900. NoiseEvening 6 x Leq5 will be measured at NSR1 to NSR4 during 1900~2300 (if construction activities are undertaken). NoiseNight 4 x Leq5 will be measured at NSR1 to NSR4 during 2300~0700 next day(if construction activities are undertaken). NoiseP.H. 6 x Leq5 will be measured at NSR1 to NSR4 during 0700~1900 (if construction activities are undertaken). Tentative Environmental Monitoring Schedule between 29 August and 28 September 2004 Sunday Monday Tuesday Wednesday Thursday Friday Saturday 29-Aug 30-Aug 31-Aug 1-Sep 2-Sep 3-Sep 4-Sep

NoiseP.H. 1hr-TSP 24hrs-TSP Noise 1hr-TSP

Noiseevening

Noisenight

5-Sep 6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep

NoiseP.H. 24hrs-TSP Noise 1hr-TSP

Noiseevening

Noisenight

12-Sep 13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep

NoiseP.H. 24hrs-TSP 1hr-TSP Noise 24hrs-TSP

Noiseevening

Noisenight

19-Sep 20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep

NoiseP.H. 1hr-TSP Noise 24hrs-TSP

Noiseevening

Noisenight

26-Sep 27-Sep 28-Sep

NoiseP.H. 1hr-TSP

1hr-TSP 3 x 1 hour TSP monitoring at ASR1 to ASR4 during 0900~1800. 24hrs-TSP 24 hours TSP monitoring at ASR1 to ASR4 Noise Leq30 measurement at NSR1 to NSR4 during 0700~1900. NoiseEvening 6 x Leq5 will be measured at NSR1 to NSR4 during 1900~2300 (if construction activities are undertaken). NoiseNight 4 x Leq5 will be measured at NSR1 to NSR4 during 2300~0700 next day (if construction activities are undertaken). NoiseP.H. 6 x Leq5 will be measured at NSR1 to NSR4 during 0700~1900 (if construction activities are undertaken). Appendix Q

Photographic Records of Implemented Measures Appendix Q Photographical Records of Implemented Measures

Photo 01 (P2-SA1) Photo 02 (P2-SA12)

Photo 03 (P2-SA12) Photo 04 (East Portal)

Photo 05 (PS-SA1) Photo 06 (West Portal) Appendix R

Summary of Environmental Licensing, Notification and Permit Status Appendix R: Summary of Environmental Licensing, Notification and Permit Status Valid Period Description Permit No. Section Status / Remarks From To Environmental EP- 15/04/02 - Entire Valid Permit 085/2000C work site Chemical WPN – 09/07/03 - Entire Valid Waste 5213-351- constructi (for the disposal of Producer G2391-01 on site spent lubrication oil and Registration spent chemical absorbents) Waste Water EP742/351/0 27/8/03 31/8/08 Entire Valid Discharge 207I constructi (carry out sampling on License on site a monthly basis) Construction GW- 02/1/04 30/06/04 P2-SA2, Valid for General Noise Permit UW0486-03 P2-SA3 Holiday including and P2- Sundays between 0700 SA2D - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 20/1/04 14/06/04 P2-SA6E Valid for General Noise Permit UW0020-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 10/2/04 31/07/04 P2-SA2 Valid for General Noise Permit UW0038-04 Holiday including Sundays between 0700 - 0700 hours on next day and any day not being a general holiday between 1900 - 0700 hours on next day. Construction GW- 19/2/04 15/08/04 P2-SA1 Valid for General Noise Permit UW0056-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 01/3/04 31/08/04 P2-SA6F Valid for General Noise Permit UW0081-04 Holiday including Sundays between 0700 - 0700 hours on Valid Period Description Permit No. Section Status / Remarks From To next day and any day not being a general holiday between 1900 - 0700 hours on next day. Construction GW- 26/3/04 25/09/04 P2-SA6A Valid for General Noise Permit UW0130-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 30/3/04 25/09/04 P2-SA1 Valid for General Noise Permit UW0143-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 26/4/04 25/10/04 P2-SA6A Valid for General Noise Permit UW0182-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 28/4/04 24/10/04 P2-SA12 Valid for General Noise Permit UW0191-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 12/5/04 9/12/04 P2-SA6A Valid for General Noise Permit UW0221-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 27/5/04 23/11/04 P2-SA6 Valid for General Noise Permit UW0244-04 Holiday including Sundays between Valid Period Description Permit No. Section Status / Remarks From To 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 27/5/04 23/11/04 P2-SA1 Valid for any day Noise Permit UW0245-04 from 2300 - 0700 hours on next day. Construction GW- 27/5/04 23/11/04 P2-SA6 Valid for any day Noise Permit UW0246-04 from 2300 - 0700 hours on next day. Construction GW- 3/6/04 30/11/04 P2-SA1 Valid for General Noise Permit UW0256-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 3/6/04 30/11/04 P2-SA2, Valid for General Noise Permit UW0257-04 P2-SA3 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours. Construction GW- 21/6/04 20/12/04 P2-SA12 Valid for General Noise Permit UW0279-04 Holiday including Sundays between 0700 - 2300 hours and any day not being a general holiday between 1900 - 2300 hours.