ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), PROVINCE FINAL ASSESSMENT REPORT

08 NOVEMBER 2019 FINAL

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE FINAL ASSESSMENT REPORT

ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

TYPE OF DOCUMENT (VERSION) FINAL

PROJECT NO.: 41101879 DATE: NOVEMBER 2019

WSP BUILDING C KNIGHTSBRIDGE, 33 SLOANE STREET BRYANSTON, 2191

T: +27 11 361 1392 F: +27 11 361 1381 WSP.COM

WSP Environmental (Pty) Ltd.

QUALITY MANAGEMENT

ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3

Remarks Assessment Report; Assessment Report;

Draft for Public Final for Authority Review Issue

Date September 2019 November 2019

Prepared by Alice Moropa Alice Moropa

Signature

Checked by Ashlea Strong Ashlea Strong

Signature

Checked by Anri Scheepers Anri Scheepers

Signature

Authorised by Ashlea Strong Ashlea Strong

Signature

Project number 41101879 41101879

Report number 01 02

File reference W:\000 NEW Projects\41101879 -Amandelbult Modernisation\42 ES\2-REPORTS\01- Draft AR

WSP is an ISO9001:2015, ISO14001:2015 and OHSAS18001:2007 certified company

SIGNATURES

PREPARED BY

Alice Moropa Environmental Consultant

REVIEWED BY

Ashlea Strong Principal Consultant

This Final Assessment Report (Report) has been prepared by WSP Environmental Proprietary Limited (WSP) on behalf and at the request of Anglo American Platinum Limited: Rustenburg Platinum Mines (AAP:RPM)) (Client), to provide the Client and all interested and affected parties with an understanding of the impacts associated with the proposed amendments to their Environmental Authorisation. Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other than the Client for the contents of, or any omissions from, this Report. To prepare this Report, we have reviewed only the documents and information provided to us by the Client or any third parties directed to provide information and documents to us by the Client. We have not reviewed any other documents in relation to this Report, except where otherwise indicated in the Report.

PRODUCTION TEAM

CLIENT-

Project Manager: Amandelbult Gerrit van der Linde Modernisation

Project Engineer: Vent Shafts Saligh Cader,

Project Manager: Taxi Terminal Simon Smit

Environmental Manager: Platinum Dustin van Helsdingen Process Operations; Amandelbult & Unki

Environmental Co-ordinator: Ursula Marvey Amandelbult Complex

Chief Ventilation Engineer – Angelique Trollip Amandelbult Complex

WSP

Project Manager: Vent Shafts Ashlea Strong

Project Manager: Taxi Terminal Anri Scheepers

Environmental Consultant Alice Moropa

Soil Specialist Karen King

Wetland Specialist Zakariya Nakhooda

Hydrological Specialist Hassen Khan

Hydrogeological Specialist Gareth Lottreaux

SUBCONSULTANTS

Biodiversity Impact Assessment The Biodiversity Company: Martinus Erasmus

Closure Plan The MSA Group: Roelof Letter

Social Impact Assessment Tony Barbour (Environmental and Social Assessment Consultant)

Heritage Impact Assessment Archaetnos: Professor Anton van Vollenhoven

ACRONYMS AND ABBREVIATIONS

AR Assessment Report

EIA Environmental Impact Assessment

EIAr Environmental Impact Assessment Report

DEA Department of Environmental Affairs

DWS Department of Water and Sanitation

EA Environmental Authorisation

EAP Environmental Assessment Practitioner

ECO Environmental Control Officer

EMPr Environmental Management Programme

IDP Integrated Development Plan

GNR Government Notice Regulations

HIA Heritage Impact Assessment

SIA Social Impacts Assessments

IWMP Integrated Waste Management Plan

SANS South African National Standards

SAHRIS Saouth African Heritage Resources Information System

I&APs Interested and Affected Parties

CA Competent Authority

NEMA National Environmental Management Act

NHRA National Heritage Resources Act

SAHRA South African Heritage Resources Agency

I&AP Interested and Affected Parties

LT Least Threatened

LC Least Concerning

NT Near Threatened

VU Vulnerable

PES Present Ecological State

EIS Ecological Importance and Sensitivity

REC Recommended Ecological Category

CONTENT OF THIS REPO RT

As per the Environmental Impact Assessment (EIA) Regulations 2014, as amended, Regulation 32 of Government Notice Regulation (GNR) 326 identifies the legislated requirements, which must be contained within an Assessment Report for the competent authority to consider and come to a decision on the amendment application. The Table below details where the required information is located within this Final Assessment Report (this report).

RELEVANT REGULATION REPORT 32 OF GNR 326 DESCRIPTION SECTION

1 The applicant must within 90 days of receipt by the competent authority of the The final application made in terms of regulation 31, submit to the competent authority: Amendment Report will be submitted to DMR as per requirement

(a) A report reflecting:

(i) An assessment of all impacts related to the proposed change; Section 5

(ii) Advantages and disadvantages associated with the proposed change; and Section 2.4

(iii) Measures to ensure avoidance, management and mitigation of impacts Section 6 associated with such proposed change; and

(iv) Any changes to the EMPr: Section 6

Which report:

(i) Had been subjected to a public participation process, which had been Section 7 agreed to by the competent authority, and which was appropriate to Appendix J1 – J5 bring the proposed change to the attention of potential and registered interested and affected parties, including organs of state, which have jurisdiction in respect of any aspect of the relevant activity, and the competent authority; and

(ii) Reflects the incorporation of comments received, including any Appendix J5 comments of the competent authority

(b) A notification in writing that the report will be submitted within 140 days of Not Applicable receipt of application by the competent authority, as significant changes have been made or significant new information has been added to the report, which changes or information was contained in the report consulted on during the initial public participation process contemplated in subregulation 1(a) and that the revised report will be subjected to another public participation process of at least 30 days.

2 In the event where subregulation (1)(b) applies, the report, which reflects the Not Applicable incorporation of comments received, including any comments of the competent authority, must be submitted to the competent authority within 140 days of receipt of the application by the competent authority

TABLE OF 1 INTRODUCTION ...... 1 CONTENTS 1.1 Background and Project Overview ...... 1 1.2 Purpose of the Report ...... 2 1.3 Terms of Reference ...... 2

2 LEGAL FRAMEWORK ...... 3 2.1 Legal Background ...... 3 2.2 Proposed Amendments ...... 3 2.3 Listed Activities ...... 4 2.4 Advantages and Disadvantages of Proposed Changes ...... 6

3 PROJECT DESCRIPTION ...... 8 3.1 Scope of Works: Ventilation Shafts ...... 8 3.2 Scope of Works: Bus and Taxi terminal ...... 11 3.3 Project Study Area ...... 14

4 BASELINE ENVIRONMENT ...... 17 4.1 Climate ...... 17 4.2 Topography ...... 17 4.3 Geology, Soils and Land Type ...... 17 4.4 Biodiversity ...... 18 4.5 Surface Water ...... 22 4.6 Groundwater ...... 23 4.7 Socio-Economic Status ...... 24

5 IMPACT ASSESSMENT ...... 25 5.1 Impact Assessment Methodology ...... 25 5.2 Environmental and Social Impacts: Ventilation Shafts ...... 28 5.3 Environmental and Social Impacts: Bus and Taxi Terminal ...... 36

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

6 UPDATE OF THE ENVIRONMENTAL MANAGEMENT PROGRAMME ...... 41 6.1 Ventilation Shafts Environmental Management Programme ...... 41 6.2 Bus and Taxi Terminal Environmental Management Programme ...... 41

7 STAKEHOLDER ENGAGEMENT ...... 72 7.1 Purpose of Stakeholder Engagement ...... 72 7.2 What is an Interested and Affected Party? ...... 72 7.3 Stakeholder Identification ...... 73 7.4 Stakeholder Engagement Plan ...... 74 7.5 Proof of Engagement ...... 75 7.6 Comments and Responses ...... 80

8 CONCLUSION ...... 82

BIBLIOGRAPHY ...... 83

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

TABLES TABLE 2-1: AMENDMENTS PROPOSED TO THE AMANDELBULT EMPR ...... 3 TABLE 2-2: LISTED ACTIVITIES NOT TRIGGERED BY PROPOSED AMENDMENTS ...... 4 TABLE 2-3: ADVANTAGES AND DISADVANTAGES OF PROPOSED AMENDMENTS ...... 6 TABLE 4-1: MAMMAL SPECIES OF CONSERVATION CONCERN THAT MAY OCCUR IN THE PROJECT AREA AS WELL AS THEIR GLOBAL AND REGIONAL CONSERVATION STATUSES (IUCN ; 2017, SANBI, 2016) ...... 20 TABLE 4-2: EXPECTED REPTILE SPECIES OF CONSERVATION CONCERN THAT MAY OCCUR IN THE PROJECT AREA ...... 21 TABLE 4-3: AMPHIBIAN SPECIES OF CONSERVATION CONCERN WHICH MAY OCCUR IN THE PROJECT AREA ...... 21 TABLE 4-4: RIVER STATUS OF THE A24C QUATERNARY CATCHMENT (DWS; 2014) ...... 23 TABLE 5-1: NATURE OR TYPE OF IMPACT 25 TABLE 5-2: PHYSICAL EXTENT OF IMPACT ...... 25 TABLE 5-3: DURATION OF IMPACT ...... 26 TABLE 5-4: REVERSIBILITY OF IMPACT ..... 26 TABLE 5-5: MAGNITUDE OF IMPACT...... 26 TABLE 5-6: PROBABILITY OF OCCURRENCE OF IMPACT ...... 27 TABLE 5-7: SYMBOLS REFERENCE ...... 27 TABLE 5-8: SIGNIFICANCE RATINGS ...... 28 TABLE 5-9: BIODIVERSITY IMPACT SIGNIFICANCE RATING...... 28 TABLE 5-10: WETLAND IMPACT SIGNIFICANCE RATING...... 30 TABLE 5-11: AIR QUALITY IMPACTS SIGNIFICANCE ...... 31 TABLE 5-12: NOISE IMPACTS SIGNIFICANCE ...... 31 TABLE 5-13: SOCIAL IMPACT SIGNIFICANCE RATING ...... 32 TABLE 5-14: SOIL AND LAND CAPABILITY IMPACT SIGNIFICANCE RATING ...... 33

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

TABLE 5-15: HYDROLOGY IMPACT SIGNIFICANCE ...... 34 TABLE 5-16: GROUNDWATER IMPACTS SIGNIFICANCE ...... 34 TABLE 5-17: DECOMMISSIONING AND CLOSURE IMPACTS SIGNIFICANCE ...... 35 TABLE 5-18: AIR QUALITY IMPACT FROM DUST AND PM GENERATION DURING CONSTRUCTION PHASE ...... 37 TABLE 5-19: NOISE IMPACTS DURING THE CONSTRUCTION PHASE...... 37 TABLE 5-20: SOIL EROSION AND COMPACTION IMPACTS FROM CONSTRUCTION ACTIVITIES ... 38 TABLE 5-21: VEGETATION LOSS IMPACT FROM CONSTRUCTION ACTIVITIES ...... 38 TABLE 5-22: IMPACTS ON GROUNDWATER DURING THE CONSTRUCTION PHASE ...... 39 TABLE 5-23: TRAFFIC IMPACTS DURING THE CONSTRUCTION PHASE...... 39 TABLE 5-24: CONSTRUCTION IMPACTS ON EMPLOYMENT OPPORTUNITIES ...... 39 TABLE 6-1: ENVIRONMENTAL MANAGEMENT PROGRAMME: VENTILATION SHAFTS ...... 42 TABLE 6-2: ENVIRONMENTAL MANAGEMENT PROGRAMME: BUS AND TAXI TERMINAL...... 61 TABLE 7-1: INTERESTED AND AFFECTED PARTIES TABLE ...... 73 TABLE 7-2: STAKEHOLDER ENGAGEMENT PLAN...... 74 TABLE 7-3: PROOF OF SITE NOTICE PLACEMENT ...... 76 TABLE 7-4: PROOF OF GENERAL PROJECT NOTICE PLACEMENT ...... 77 TABLE 7-5: PUBLIC REVIEW LOCATIONS OF THE DRAFT ASSESSMENT REPORT ...... 80 TABLE 7-6: COMMENT AND RESPONSES TABLE...... 81

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

FIGURES FIGURE 3-1: PROPOSED UPCAST VENTILATION SHAFT SURFACE PLAN...... 9 FIGURE 3-2: PROPOSED DOWNCAST VENTILATION SHAFT SURFACE PLAN...... 10 FIGURE 3-3: TEMPORARY BUS AND TAXI TERMINAL FACILITY ...... 12 FIGURE 3-4: LOCATION OF THE PROPOSED VENTILATION SHAFT PROJECT ...... 15 FIGURE 3-5: LOCATION OF THE BUS AND TAXI TERMINAL UPGRADE PROJECT ...... 16 FIGURE 4-1: REGIONAL GEOLOGY OF THE AREA (SOURCE : FINAL REHABILITATION, DECOMMISSIONING AND MINE CLOSURE PLAN IN SUPPORT OF ANGLO-AMERICAN PLATINUM PROPOSED VENTILATION SHAFTS AT AMANDELBULT MINE, MSA GROUP) ...... 18 FIGURE 4-2: VANTILATION SHAFTS PROJECT AREA VEGETATION TYPE (SOURCE: BIODIVERSITY BASELINE ASSESSMENT FOR THE AMUNDELBULT COMPLEX MODERNIZATION PROJECT, THE BIODIVERSITY COMPANY) ...... 19 FIGURE 4-3: BUS AND TAXI TERMINAL PROJECT AREA VEGETATION TYPE...... 19 FIGURE 4-4: VENTILATION SHAFTS PROJECT AREA HYDROLOGY ...... 22 FIGURE 4-5: BUS AND TAXI TERMINAL PROJECT AREA HYDROLOGY . 23 FIGURE 7-1: SITE AND GENERAL PROJECT NOTICE LOCATIONS ...... 76

APPENDICES A PRE-APPLICATION MEETING B BIODIVERSITY BASELINE ASSESSMENT C WETLAND IMPACT ASSESSMENT

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

D SOCIAL IMPACT ASSESMENT E HERITAGE IMPACT ASSESSMENT: LETTER OF EXEMPTION F SOILS AND LAND USE ASSESSMENT G HYDROLOGICAL IMPACT ASSESSMENT H HYDROGEOLOGICAL ASSESSMENT I DECOMISSIONING AND MINE CLOSURE PLAN J STAKEHOLDER ENGAGEMENT J-1 Advertisement J-2 Site Notice J-3 Notification Letter J-4 Stakeholder Database J-5 Comments Received K TUMELA BUS AND TAXI TERMINAL IMPACT SIGNIFICANCE RATING L TUMELA BUS AND TAXI TERMINAL LAYOUT PLAN

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

1 INTRODUCTION

1.1 BACKGROUND AND PROJECT OVERVIEW

The Amandelbult Complex consists of the Tumela and Dishaba established mines, situated on the north-western limb of the Bushveld Complex. Mining at both Tumela and Dishaba Mines occurs on the Merensky and UG2 Reef horizons, with the predominant mining layout being the conventional scattered breast mining with strike pillars. Commodities mined at the mines include the platinum group metals platinum, palladium, rhodium, iridium and ruthenium, as well as by-products gold, silver, cobalt, nickel and copper. Tumela Mine e infrastructure consists of one vertical shaft, three raisebore shafts and four decline shaft systems used to transport rock, men and material, and the mine operates at a depth of between 180 and 895 meters (m) below surface. Dishaba Mine’s infrastructure consist of one vertical shaft, one raise bore and four decline shafts and the operating depth of the underground workings is between 180 and 1 250 m below surface. Anglo American Platinum Limited: Rustenburg Platinum Mines (AAP:RPM) are proposing to establish new infrastructure on site, namely two new ventilation shafts at the Dishaba Mine, and an upgrade to the existing bus and taxi terminal at the Tumela Mine.

1.1.1 VENTILATION SHAFT PROJECT

AAP:RPM has identified the need to improve mining efficiency and productivity at its operations, so as to “Make Amandelbult Investable Again”. Several initiatives have been identified and form part of the “Making Amandelbult Investable Again” programme, with emphasis on low capital, value accretive and fast payback projects. The Amandelbult Modernisation project is one such initiative and aims to ensure the future safety and sustainability of the complex. In particular, the following modernisation initiatives form part of the project: — Hydro-power drilling and cleaning; — Electro-hydraulic drilling; — Hydropower cleaning; — Alternative explosives (emulsion explosives); and — Increased infrastructure (compressed air, power, water and ventilation). It is expected that the above listed mining mechanisms will improve mining productivity, entailing that a greater reserve will be accessed more efficiently and timeously. As an operational forecast, increased ventilation will therefore be required to provide a flow of air of sufficient volume to the progressing underground workings, and regulate the temperatures therein. It is proposed that 2 ventilation shafts (upcast and downcast shafts) are constructed North East and South East of Dishaba Mine. A power transmission line will also be required to provide power to the ventilation system, as well as access roads to access the ventilation shafts. A water pipe line that takes water to the downcast ventilation shaft Bulk Air Cooler will also be developed.

1.1.2 BUS AND TAXI TERMINAL PROJECT

AAP:RPM also proposes to upgrade the existing Tumela Mine bus and taxi rank, which is an informal area used by busses, taxis and private vehicles for transferring personnel working at Tumela Mine. This area is not an adjudicated parking area and is an un-developed dirt area with no infrastructure, no access control, no ablution facilities and no lighting at night for night shift employees. The area therefore poses a risk to health and safety to the mine employees and as such, the mine aims to develop it into a functional and safe bus and taxi terminal, thereby also responding to the mine’s ‘Elimination of Fatalities priority schedule’.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 1 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

During the construction phase, the current bus and taxi services will temporarily be re-established to an area that will be designated as a temporary facility for the phased project execution approach. This will include upfront work with regards to terminal facilities, interim roads, parking and drop-off facilities, potable water, shelters, pedestrian waiting areas, Lighting, waste management and road signage.

1.2 PURPOSE OF THE REPORT

This Final Assessment Report (AR) documents the process and findings of the application for the amendment of the Environmental Management Programme (EMPR) for the Amandelbult Mine (LP 30/5/1/2/3/2/1(048)EM). This report serves the purpose of amending the approved Amandelbult EMPR to be able to assess and mitigate for the additional environmental impacts that will result from the addition of the two proposed ventilation shafts at Dishaba Mine and the upgrade of the bus and taxi terminal at Tumela Mine. Due to the fact that the amendments result in a change of scope, a Part 2 Amendment Process in terms of Regulation 31 of the Environmental Impact Assessment (EIA) Regulations of 2014 (amended in 2017) is required.

1.3 TERMS OF REFERENCE

WSP Environmental (Pty) Ltd (WSP) was appointed in the capacity as independent Environmental Assessment Practitioner (EAP) to undertake the amendment process in terms of Regulation 31 and 32 of the 2014 EIA Regulations (as amended). The amendment application process to be followed is summarised below: — A pre-application meeting was held on 2 August 2019 and attended by the Department of Mineral Resources (DMR), WSP and AAP:RPM. The Attendance Register and Presentation are included in Appendix A; — Payment of the prescribed application fee for the application for the variation of the EMPR was made on 6 September 2019; and — The application for the variation of the EMPR was submitted to the DMR on 16 September 2019. Section 32 of the 2014 EIA Regulations (as amended 2017) requires that the Draft Report be subject to a public participation process prior to submission to the DMR. WSP facilitated the following public participation process on behalf of AAP:RPM: — Provision of the Draft Report for a 30-day comment period as per the requirements of Section 32 (1) (b). — All registered stakeholders (as per the updated Amandelbult database) were notified by WSP of the availability of the Draft Report for comment. Copies were made available at nearby public spaces (for public access), as well as on WSP’s webpage (https://www.wsp.com/en-ZA/services/public-documents). The Final Report includes copies of all stakeholder engagement records to submit to the DMR for decision- making. All registered interested and affected parties (I&APs) will thereafter be notified of the DMR’s decision.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 2 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

2 LEGAL FRAMEWORK

2.1 LEGAL BACKGROUND

On the 7th April 2017 the Minister of Environmental Affairs promulgated amendment EIA Regulations [Government Notice Regulation (GNR 327)] in terms of Chapter 5 of the National Environmental Management Act (No. 107 of 1998), as Amended (NEMA). Regulations 31 and 32 of the EIA Regulations details the process for a Part 2 (Substantive) amendment of an environmental authorisation where a change of scope occurs, but a listed activity is not triggered. The proposed amendments do not trigger new activities; however, it is anticipated that there will be a potential change in impacts, which were previously authorised in the existing EMPR associated with the facility’s operations. One of the aims of this report is to provide an outline of the proposed changes.

2.2 PROPOSED AMENDMENTS

AAP:RPM propose to follow a Part 2 Amendment Process for the amendment of the Approved Amandelbult Complex EMPR (LP 30/5/1/2/3/2/1(048)EM). A variation application has been completed and the amendments proposed are outlined in Table 2-1. Table 2-1: Amendments Proposed to the Amandelbult EMPR

AMENDMENT PROPOSED DESCRIPTION

Ventilation Shafts

Two New Ventilation Shafts Two ventilation shafts will be constructed, i.e the upcast ventilation shaft and the downcast (upcast and downcast) at the ventilation shaft. The upcast shaft and downcast shafts together with the associated Dishaba Mine infrastructure will cover a total surface area of about 2 318 m2 and 1 600 m2 respectively.

Upcast Shaft Power Supply Two 2 810 m, 11 kV Powelines that run parallel to each other will be constructed to transmit power from the Elandskuiul substation to the upcast shaft, following the existing overhead line (OHL) routing at Dishaba.

Downcast Shaft Power An existing 240 m buried cable will be used to transmit power to the downcast shaft until Supply the Dishaba fence line east of the mine, from which a 540 m overhead line will be erected and further transmit power to the shaft.

Down Cast Shaft Water A 510 m long water pipeline (with a diameter of between 0.20 m and 0.45 m) that runs Pipeline parallel to the OHL to the downcast shaft, will be constructed to provide water to the Bulk Air Cooler at the downcast shaft for underground temperature regulating purposes.

Upcast and Downcast Access Two access roads will be developed to access the two shafts. Roads

Bus and Taxi Terminal

Bus and Taxi Terminal The demolition of the existing informal bus and taxi terminal infrastructure and construction Upgrade of a new terminal which includes the following infrastructure: — New road layer works. — New paving surface inclusive of curbing. — Canopy to be erected over the taxi terminal. — Pedestrian waiting areas to be erected. — New Kiosk buildings be erected.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 3 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

AMENDMENT PROPOSED DESCRIPTION — New ablution facilities be erected and assessed in terms of the infra structure in comparison with the waiting time of pedestrians to get served with transportation in accordance with the Mine Operational Logistical requirements. — Skip bin area to be constructed for total terminal waste management. — New security gate house. — Installing lighting for the area. — Traffic signage and road markings to be installed. — Storm Water control shall be designed and to comply with the Environmental Requirements and legislation. — Water requirements for fire hydrants. — Lightning Detection. — Security – Access Control and Lighting

New Car Wash Area The construction of a new car wash area which includes: — A new car wash bay to be constructed. — Sewer line with oil trap will be installed. — Relocation of existing shaded parking. — Construction of a new access road.

New Light Vehicle (LV) The construction of light vehicle (LV) drop-off area which includes: drop-off area: — Road layer works. — New paving surface with curbing and installation of traffic signs and road markings.

Expansion of the salvage yard The clearing and grubbing an area which can accommodate 70 un covered parking bays for parking area: 70 private light vehicles.

2.3 LISTED ACTIVITIES

The proposed amendments do not trigger new activities; however, it is anticipated that there will be a potential change in impacts, which were previously authorised in the existing EMPR associated with the facility’s operations. Table 2-2 outlines the potential listed activities and highlights why they are not applicable. Table 2-2: Listed Activities Not Triggered By Proposed Amendments

LISTED ACTIVITY ACTIVITY DESCRIPTION APPLICABILITY

Ventilation Shafts and Associated Infrastructure

GNR 983, Activity 9: The development of infrastructure exceeding 1000 Not Applicable metres in length for the bulk transportation of water or A 510 m long water pipeline that runs storm water- parallel to the OHL to the downcast (i) with an internal diameter of 0,36 metres or more; or shaft, will be constructed to provide (ii) with a peak throughput of 120 litres per second or water to the Bulk Air Cooler at the more; downcast shaft for underground excluding where- temperature regulating purposes. The diameter of the pipeline will be between (a) such infrastructure is for bulk transportation of 0.20 m and 0.45 m. However, the length water or storm water or storm water drainage inside a of the water pipeline does not trigger road reserve; or this activity. (b) where such development will occur within an urban area.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 4 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

LISTED ACTIVITY ACTIVITY DESCRIPTION APPLICABILITY

GNR 983, Activity 11 The development of facilities or infrastructure for the Not Applicable transmission and distribution of electricity- Two parallel 11 kV lines with a 6m (i) outside urban areas or industrial complexes with a servitude running to each shaft will be capacity of more than 33 but less than 275 kilovolts; or established (outside an urban area). (ii) inside urban areas or industrial complexes with a Since the powerlines’ capacity is not capacity of 275 kilovolts or more. more than or equal to 33 kV, this activity is not applicable.

GNR 983, Activity 24 The development of- Not Applicable (i) a road for which an environmental authorisation Two access roads will be developed to was obtained for the route determination in terms of access the two shafts. activity 5 in Government Notice 387 of 2006 or A new 1005 m long access road that activity 18 in Government Notice 545 of 2010; or runs parallel to the power line will be (ii) a road with a reserve wider than 13,5 meters, or constructed from the main dirt road (that where no reserve exists where the road is wider than 8 lies North West of Dishaba Mine) to metres; access the upcast shaft from north of but excluding- Dishaba Mine. (a) roads which are identified and included in activity Similarly, a 510 m long access road that 27 in Listing Notice 2 of 2014; or runs parallel to the OHL to access the (b) roads where the entire road falls within an urban downcast shaft from a dirt road south of area. Dishaba Mine. Both access roads will be dirt roads with a servitude of not more than 3.5 m and as such, this activity will not be triggered.

GNR 983, Activity 27 The clearance of an area of 1 hectares or more, but less Not Applicable than 20 hectares of indigenous vegetation, except The upcast shaft and downcast shafts where such clearance of indigenous vegetation is together with the associated required for- infrastructure will cover a surface area (i) the undertaking of a linear activity; or of approximately 0.231 ha and 0.1600 (ii) maintenance purposes undertaken in accordance ha respectively. Therefore, a combined with a maintenance management plan. total of approximately 0.3918 ha that will be cleared form the surface. The total surface area to be cleared of indigenous vegetation is less than 1 ha, therefore this activity will not be triggered

Bus and Taxi Terminal and Associated Infrastructure

GNR 983, Activity 9 The development of infrastructure exceeding 1000 Not Applicable metres in length for the bulk transportation of water or Storm water controls will be constructed storm water- divert storm water into current storm (i) with an internal diameter of 0,36 metres or more; or water drainage control system. Class (ii) with a peak throughput of 120 litres per second or 75D Concrete Pipe Culverts of 450 mm more; Diameter will be used. excluding where- (a) such infrastructure is for bulk transportation of water or storm water or storm water drainage inside a road reserve or railway line reserve; or (b) where such development will occur within an urban area.

GNR 983, Activity 10 The development and related operation of Not Applicable infrastructure exceeding 1000 metres in length for the A 50 m (length) x 110 mm (diameter) bulk transportation of sewage, effluent, process water, PVC sewer line will be installed at the waste water, return water, industrial discharge or proposed car wash. slimes -

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 5 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

LISTED ACTIVITY ACTIVITY DESCRIPTION APPLICABILITY (i) with an internal diameter of 0,36 metres or more; or (ii) with a peak throughput of 120 litres per second or more; excluding where- (a) such infrastructure is for the bulk transportation of sewage, effluent, process water, waste water, return water, industrial discharge or slimes inside a road reserve or railway line reserve; or (b) where such development will occur within an urban area.

GNR 983, Activity 27 The clearance of an area of 1 hectares or more, but less Not Applicable than 20 hectares of indigenous vegetation, except Seven indigenous trees (i.e. Vachellia where such clearance of indigenous vegetation is tortilis and a Searsia spp) at the existing required for- informal bus and taxi terminal will be (i) the undertaking of a linear activity; or removed, however there is no other (ii) maintenance purposes undertaken in accordance remaining vegetation. with a maintenance management plan.

GNR 985,Activity 12 The clearing of 300 m 2 of indigenous vegetation Not Applicable within a Critical Biodiversity Area (CBA). The bus and taxi terminal project area is classified as a CBA2 area, however the area has already been transformed by the mining infrastructure at Tumela, and contains less than 300 m2 vegetation cover

2.4 ADVANTAGES AND DISADVANTAGES OF PROPOSED CHANGES

The advantages and disadvantages for the proposed amendments are outlined in Table 2-3below. Table 2-3: Advantages and Disadvantages of Proposed Amendments

PROPOSED AMENDMENT ADVANTAGE DISADVANTAGE

Ventilation Shafts and The proposed ventilation shafts are required to Although the proposed activities will be Associated cater for the progression of underground workings undertaken within Amandelbult’s authorised Infrastructure at Dishaba Mine, by supplying ventilation for mining right area, the impact footprint will underground workers. Without the additional extend to parts of the site which are currently left proposed ventilation shafts, it would be impossible natural. This includes the removal of additional for Amendulbult to continue mining the entire natural vegetation (and thereby further disturbing authorised ore body, which would mean production the natural ecosystem around the mine) and at the mine would eventually come to a halt , impacting on the aquatic systems (wetlands) near thereby shortening the life of mine. the mine. The ventilation shafts will therefore ensure that production at the mine continues. Subsequently, the life of mine will be extended, and the mine will continue to contribute to the local and national economy, and jobs will be retained.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 6 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

PROPOSED AMENDMENT ADVANTAGE DISADVANTAGE

Bus and Taxi The existing (informal) bus and taxi terminal area The construction activities associated with the Terminal Upgrade is an un-developed dirt area with no infrastructure, upgrade will temporarily cause access control, ablution facilities or lighting at distractions/disturbance (noise, dust and night for night shift employees. As such, the area movement of large machinery) to people coming poses a health and safety risk to the mine in and working at Tumela Mine. employees. The mine aims to develop this area into a Furthermore, a few indigenous trees (i.e. functional and safe bus and taxi terminal, thereby Vachellia tortilis and a Searsia spp) will be creating a safer environment and responding to the removed from the area. mine’s ‘Elimination of Fatalities priority schedule’.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 7 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

3 PROJECT DESCRIPTION

3.1 SCOPE OF WORKS: VENTILATION SHAFTS

The proposed amendments entail the drilling and raise boring of two ventilation shafts for the Dishaba Mine, as well as the establishment of power lines, water pipe lines and access roads as supporting/ ancillary infrastructure. The scope of works for the ventilation shafts is outlined below.

3.1.1 VENTILATION SHAFTS

Two ventilation shafts will be constructed, i.e the upcast ventilation shaft and the downcast ventilation shaft. The upcast shaft and downcast shafts together with the associated infrastructure will cover a total surface area of about 2 318 m2 and 1 600 m2 respectively. Figure 3-1 and Figure 3-2 illustrate the surface plans for the upcast and downcast shafts respectively. These will be constructed by the use of the ‘raiseboring’ method which comprises of two phases; ‘Phase 1’ which is the drilling/ piloting phase and ‘Phase 2’ which is the reaming phase. Prior to the commencement with Phase 1 the intersection point is identified. The intersection point is the point where the ventilation shaft will intersect with the underground workings. In Phase 1 a pilot hole is drilled from the surface to the predetermined intersection point. During this phase the underground workings are extended or developed to the intersection point and a cubby is blasted and supported, to receive the pilot hole. In Phase 2 the reamer head is positioned in the cubby and raised to the surface by the raisebore machine. The reamer head uses a turning action to cut the rock thereby widening the pilot hole. The broken rock falls down and collects in the cubby where it is loaded onto hoppers, transported to the orepass system and hoisted to the surface. The broken rock is disposed of with the existing mine waste rock and transported to the waste rock dump.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 8 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 3-1: Proposed Upcast Ventilation Shaft Surface Plan

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 9 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 3-2: Proposed Downcast Ventilation Shaft Surface Plan

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 10 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

3.1.2 POWER LINE

UPCAST SHAFT POWER SUPPLY Two 2 810 m, parallel 11 kV Powelines will be constructed to transmit power from the Elandskuil substation to the upcast shaft, following the existing overhead line (OHL) routing at Dishaba Mine. The provision of a second line to each of the ventilation fans has been made as an alternative power supply /redundancy in case of a failure/destruction to the main line.

DOWNCAST POWER SUPPLY An existing 240 m buried cable will be used to transmit power to the downcast shaft until the Dishaba Mine fence line east of the mine, from which a 540 m overhead line will be erected and further transmit power to the Bulk Air Cooler situated at the shaft.

3.1.3 WATER PIPELINE

A 510 m long water pipeline (with a diameter of between 0.20 m and 0.45 m) that runs within the OHL servitude to the downcast shaft, will be constructed to provide water to the Bulk Air Cooler at the downcast shaft for underground temperature regulating purposes. The pipeline will run above surface, supported by plinths that will be constructed outside of any water courses located along the pipe. Excavations of not more than 10 m3 will be dug for the establishment of the plinths.

3.1.4 ACCESS ROAD

Two access roads will be developed to access the two shafts. A new 1 005 m long access road that runs parallel to the power line will be constructed from the main dirt road (that lies North West of Dishaba Mine) to access the upcast shaft from north of Dishaba Mine. Similarly, a 510 m long access road that runs parallel to the OHL to access the downcast shaft from a dirt road south of Dishaba Mine. An alternative to the construction of a new access road to the downcast shaft is the use of an existing gravel road that runs from Dishaba Mine South and through the downcast shaft proposed site. This alternative is recommended in preference to constructing a new road.

3.2 SCOPE OF WORKS: BUS AND TAXI TERMINAL

The proposed amendment entails the upgrading of the existing bus and taxi terminal and other associated infrastructure. This project has been identified as a high risk project on the current Elimination of Fatalities priority schedule at Amandelbult Mine. The current bus and taxi rank at Tumela Mine is an informal area where busses, taxis and private vehicles transferring personnel working at Tumela Mine. This area is not an adjudicated parking area for busses, taxis and private vehicles. Currently, this area is an un-developed dirt area with no infrastructure, no access control, no ablution facilities and no lighting at night for night shift employees. During the raining season, this dirt area develops into a muddy mess which is a risk to health and safety. The current parking area at the shopping centre is also an informal parking area for customers entering the shopping centre. Taxis are using this area as a temporary taxi rank transporting mine employees. The amount of pedestrian activity with no traffic control, no adjudicated parking areas, absence of road signs and no demarcated areas will lead to the increase of risks for accidents and injury The layout for the bus and taxi terminal upgrade is included in Appendix L. The scope of works for the upgrade is outlined below.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 11 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

3.2.1 PREPARATORY WORK

The current bus and taxi services will temporarily be re-established at an area that will be designated as a temporary facility for the phased project execution approach. The temporary facility will be located at a currently disturbed area in close vicinity to a local shopping store, and will be used as a Bus, Taxi and private vehicle drop-off zone (see Figure 3-3 below). Preparatory work will also include upfront work with terminal facilities, interim roads, parking and drop-off facilities, potable water, shelters, ablution facilities, pedestrian waiting areas, kiosk buildings, lighting, waste management and road signage.

Figure 3-3: Temporary Bus and Taxi Terminal Facility

3.2.2 CONSTRUCTION OF NEW BUS AND TAXI TERMINAL:

A new bus and taxi terminal will be constructed on the open area just north of the industrial change house. The terminal will have controlled access for busses and taxis. Approximately seven indigenous trees (i.e. Vachellia tortilis and a Searsia spp) will be removed from the area. The construction of the bus and taxi terminal will include the following components: — Demolition and removal of existing concrete slab and bus stop; — Excavation of the entire terminal footprint; — Backfilling and compacting as per specification;

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 12 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

— New road layer works; — New paving surface inclusive of curbing; — Erection of canopy over the tax terminal; — Erection of pedestrian waiting areas; — Erection of new Kiosk buildings; — New ablution facilities will be erected and assessed in terms of the infrastructure in comparison with the waiting time of pedestrians to get served with transportation in accordance with the Mine Operational Logistical requirements; — Construction of the Skip bin area for total terminal waste management; — Construction of new security gate house; — Installation of lighting for the area; — Installation of traffic signage and road markings; — Construction of Storm Water control to comply with the Environmental Requirements and legislation; — Water requirements for fire hydrants; — Installation of lightning detection; and — Security – Access Control and Lighting installations.

3.2.3 CONSTRUCTION OF A NEW CAR WASH AREA:

The existing tar surfaced parking area in the northern area of the existing site will be upgraded by constructing a car wash complete with wash bay, drying area and store room. Water to be used for the car wash (about 100 000 l/month) will be supplied from Tumela 1 Shaft. The construction of the car wash will include the following components — Installation of a 50 m (length) x 110 mm (diameter)PVC sewer line with oil trap; — Relocation of existing shaded parking; and — Construction of a new access road (to provide access from the main road).

3.2.4 RE-WORKING EXISTING PARKING AREA:

The existing parking area between the industrial change house and new bus & taxi terminal will be tidied up by installing paving between the existing road and the perimeter fence. The area will be ripped, levelled, compacted and paved and curbs will be installed.

3.2.5 CONSTRUCTION OF NEW LIGHT VEHICLE (LV) DROP-OFF AREA:

A (LV drop-off area (50 m x 60 m) will be constructed were the current vendor kiosksare located. Those will be removed for this purpose. It is apparent that a phased construction process will be implemented as the LV drop- off area can only be constructed once the current vendor kiosks have been relocated into the newly constructed kiosk buildings at the new bus & taxi terminal. Works in this area will involve the following: — Road layer works. — New paving surface with curbing and installation of traffic signs and road markings.

3.2.6 EXTENSION OF SALVAGE YARD PARKING AREA

The clearing and grubbing of an area which can accommodate 70 uncovered parking bays for 70 private light vehicles.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 13 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

3.3 PROJECT STUDY AREA

The Amandelbult Complex is situated approximately 17km south of , and 24km north east of Northam, in the Thabazimbi Local Municipality, Limpopo Province. The mining right area covers a total area of about 31km2. The proposed ventilation shafts are situated on portion 1 of the farm Elandskuil 378 KQ which is owned by the Amandelbult Complex and registered under Rustenburg Platinum Mines (Pty) Ltd. The bus and taxi terminal is situated on farm Elandsfontein 386 (the remainder) which is owned by Amandelbult Complex and registered under Rustenburg Platinum Mines (Pty) Ltd Figure 3-4 and Figure 3-5 overleaf depict the locations of the proposed ventilation shafts and bus and taxi terminals respectively.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 14 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 3-4: Location of the Proposed Ventilation Shaft Project

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 15 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 3-5: Location of the Bus and Taxi Terminal Upgrade Project

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 16 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

4 BASELINE ENVIRONMENT

This section provides a description of the baseline environment of the project area. The descriptions encompass the geographical, physical, biological, social, economic, heritage and cultural aspects of the project area.

4.1 CLIMATE

Amandelbult Complex falls within a summer rainfall region of South Africa with little to no precipitation recorded during the months of May, June, August and September. Maximum rainfall is experienced during November and December. The average annual rainfall is recorded as 529mm. The maximum summer temperature is experienced from November to February with an average high of 25°C and maximum temperatures of 37°C. The Mean Annual Precipitation at Amandelbult Complex is approximately 600 mm as measured at the South African Weather Service Station situated at Northam. Evaporation rates far exceed rainfall with an average rate of 1 240 mm between October and April and 880 mm between April and October. The main prevailing wind directions on the site vary from south-southwesterly (approx. 12%) to south-southeasterly (approx. 14%) with the southerly wind vector being the predominant wind prevailing approximately 21% of the time. Northerly winds prevail for <10% of the time. Calm wind conditions occur on average 10.5% of the time. (SRK IWWMP, 2019).

4.2 TOPOGRAPHY

The Amandelbult mining right area is divided in two by the main Rustenburg-Thabazimbi road (R510) and a Spoornet railway line, running parallel to the road. The general elevation gently decreases in an easterly direction in the mining area. The topography ranging from 980m above mean sea level (mamsl) in the south- western boundary of the site to 920 mamsl in the north-east. The eastern section of the mine, relates to the current project, is relatively flat. Two watercourses transect the mining area, i.e. the Bierspruit and the Crocodile River. The Bierspruit transects the mining area in the west and flows in a northerly direction where it flows into the Crocodile River to the north of the mining area. The Crocodile River flows in a north-westerly directions through the east of the mining area.

4.3 GEOLOGY, SOILS AND LAND TYPE

This geological description has been sourced from the Amandelbult operational Integrated Water and Waste Management Plan (SRK, 2018) and Geohydrological Investigation Report (Groundwater Complete, 2011). Amanadelbult Complex is underlain by rocks of the Rustenburg Layered Suite (“RLS”) of the Bushveld Complex. The Bushveld Complex is a layered igneous body with intruded sedimentary and volcanic rocks of the Transvaal Supergroup formed around 2.06 billion years ago and constitutes one of the world’s largest known layered intrusions. It is host to major deposits of Platinum Group Elements, chromite, vanadium and nickel (SRK, 2018). Land types represent areas that are uniform with respect to climate, terrain form, geology and soil. According to the Agricultural Geo-referenced Information System (AGIS, 2014), the site is situated on land type Ea70. This and the surrounding land types are associated with Gabrro and Norite of the Bushveld Complex and a narrow band of sedimentary rocks along the Crocodile River. The study area is situated in a region where erosion rates are considered as very low to low relative to other parts of the country and soils are vertic black ultramafic clays (SRK, 2018). Black turf (vertisol soil type) occurs in the area and is the result of the weathering of norite. The clay has very high swelling and shrinking characteristics between the wet and dry states. When saturated with moisture, the clays are highly impermeable to water movement, but surface cracks develop due to shrinking in the dry condition that allow for some infiltration and recharge of water before saturation is reached. Figure 4-1:

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 17 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Regional geology of the area below provides an overview of the regional geology of the study area. The proposed ventilation shafts will be located within the Magaliesberg Formation of the Pretoria Group (Transvaal Supergroup).

Figure 4-1: Regional geology of the area (Source : Final Rehabilitation, Decommissioning and Mine Closure Plan in support of Anglo-American Platinum Proposed Ventilation Shafts at Amandelbult Mine, MSA Group)

4.4 BIODIVERSITY

4.4.1 FLORA

Amandelbult Complex is situated in the Savanna biome. The Savanna vegetation of South Africa represents the southernmost extension of the most widespread biome in Africa (Mucina & Rutherford, 2006). Major macroclimatic traits that characterise the Savanna biome include: — Seasonal precipitation; and — (Sub) tropical thermal regime with no or usually low incidence of frost (Mucina & Rutherford, 2006). Most savanna vegetation communities are characterised by a herbaceous layer dominated by grasses and a discontinuous to sometimes very open tree layer (Mucina & Rutherford, 2006). The Savanna biome comprises various vegetation types. The ventilation shafts and bus and taxi terminal project areas fall within Mucina & Rutherford’s (2006) Dwaalboom thornveld (SVcb1) vegetation type (See Figure 4-2 and Figure 4-3).

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 18 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 4-2: Vantilation Shafts Project Area Vegetation Type (Source: Biodiversity Baseline Assessment for the Amundelbult Complex Modernization Project, The Biodiversity Company)

Figure 4-3: Bus and Taxi Terminal Project Area Vegetation Type

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 19 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

The Dwaalboom Thornveld is restricted to and is distributed in Limpopo and North-West Provinces within flats north of the Dwarsberge and associated ridges mainly west of the Crocodile River in the Dwaalboom area but including a patch around Sentrum. South of the ridges it extends eastwards from the Nietverdiend area, north of the Pilanesberg to the Northam area at an altitude range of between 900 and 1,200m AMSL. Its main vegetation and landscape features include plains with a layer of scattered, low to medium high, deciduous microphyllous trees and shrubs with a few broad-leaved tree species. There is almost a continuous herbaceous layer dominated by grass species. According to Mucina & Rutherford (2006) Dwaalboom Thornveld is classified as Least Threatened (LT). Although the target for conservation is 19%, only 6% of this vegetation type is currently under statutory conservation in reserves such as the Madikwe Game Reserve (approximately 150km west of the project area). Cultivation and to a lesser extend urbanisation have resulted in the transformation of approximately 14% of Dwaalboom Thornveld and exotic invasive plants are present. Incidences of erosion are low to very low (Mucina & Rutherford, 2006). Important taxa in the Dwaalboom Thornveld vegetation type include: — Trees: Vachellia erioloba, Vachellia erubescens, Vachellia nilotica, Vachellia tortilis subsp heteracantha, Senegalia fleckii, Senegalia burkei, Searsia lancea (Mucina & Rutherford, 2006). — Shrubs: Diospyros lycioides subsp. lycioides, Grewia flava, Mystroxylon aethiopicum subsp. burkeanum, Agathisanthemum bojeri (Mucina & Rutherford, 2006). — Graminoids: Aristida bipartite, Bothriochloa insculpta, Digitaria eriantha subsp eriantha, Ischaemum afrum, Panicum maximum and Cymbopogon pospischilii (Mucina & Rutherford, 2006). Plant species of conservation concern (SCC) in the project area include: — Scrophulariaceae (Jamesbrittenia bergae Taxon); and — Apocynaceae (Stenostelma umbelluliferum Taxon).

4.4.2 FAUNA

The IUCN Red List Spatial Data (IUCN, 2017) lists 99 mammal species that could be expected to occur within the vicinity of the project areas (See Biodiversity Assessment attached as Appendix B). Of these species, 7 are medium to large conservation dependant species, such as Ceratotherium simum (Southern White Rhinoceros) and Equus quagga (Plains Zebra) that, in South Africa, are generally restricted to protected areas such as game reserves. These species are not expected to occur in the project area and are removed from the expected SCC list. Of the remaining 92 small to medium sized mammal species, thirteen (13) are listed as being of conservation concern on a regional or global basis (Table 4-1). The list of potential species includes: — Two (2) that is listed as Endangered (EN) on a regional basis; — Three (3) that are listed as Vulnerable (VU) on a regional basis; and — Eight (8) that are listed as Near Threatened (NT) on a regional scale. Table 4-1: Mammal Species Of Conservation Concern That May Occur In The Project Area As Well As Their Global and Regional Conservation Statuses (IUCN ; 2017, SANBI, 2016)

CONSERVATION STATUS LIKELIHOOD REGIONAL OF SPECIES COMMON NAME (SANBI, 2016) IUCN (2017) OCCURRENCE Aonyx capensis Cape Clawless Otter NT NT Low

Atelerix frontalis South Africa Hedgehog NT LC High

Cloeotis percivali Short-eared Trident Bat EN LC Moderate

Crocidura mariquensis Swamp Musk Shrew NT LC Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 20 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

CONSERVATION STATUS LIKELIHOOD REGIONAL OF SPECIES COMMON NAME (SANBI, 2016) IUCN (2017) OCCURRENCE Crocuta crocuta Spotted Hyaena NT LC Low

Felis nigripes Black-footed Cat VU VU Moderate

Leptailurus serval Serval NT LC High

Panthera pardus Leopard VU VU High

Parahyaena brunnea Brown Hyaena NT NT Moderate

Pelea capreolus Grey Rhebok NT LC Low

Poecilogale albinucha African Striped Weasel NT LC High

Redunca fulvorufula Mountain Reedbuck EN LC Low

Smutsia temminckii Temminck's Ground Pangolin VU VU Moderate

HERPETOFAUNA (REPTILES & AMPHIBIANS) Based on the IUCN Red List Spatial Data (IUCN, 2017) and the Reptile Map database provided by the Animal Demography Unit (ADU, 2017) 81 reptile species are expected to occur in the project areas. Three (3) reptile SCC (Listed in Table 4-2 below) are expected to be present in the project area. Table 4-2: Expected Reptile Species Of Conservation Concern That May Occur In The Project Area

CONSERVATION STATUS LIKELIHOOD Regional IUCN OF SPECIES COMMON NAME (SANBI, 2016) (2017) OCCURRENCE Crocodylus niloticus Nile Crocodile VU LC Low

Lygodactylus waterbergensis Waterberg Dwarf Gecko NT NT High

Pseudocordylus transvaalensis Northern Crag Lizard NT NT High

AMPHIBIANS Based on the IUCN Red List Spatial Data (IUCN, 2017) and the Amphibian Map database provided by the Animal Demography Unit (ADU, 2017) thirty-one (31) amphibian species are expected to occur in the project area. These are listed in the biodiversity assessment report (Appendix B) One (1) amphibian species of conservation concern could be present in the project area according to the above- mentioned sources (Table 4-3). Table 4-3: Amphibian Species Of Conservation Concern Which May Occur In The Project Area

CONSERVATION STATUS LIKELIHOOD Regional IUCN (2017) OF SPECIES COMMON NAME (SANBI, 2016) OCCURRENCE Pyxicephalus adspersus Giant Bullfrog NT LC Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 21 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

4.5 SURFACE WATER

Amandelbult Complex falls within quaternary catchments A24C which is located within the Crocodile-Marico River catchment. The Crocodile Riveris located approximately 2km to the east of the ventilation shafts project area (Figure 4-4), and the bus and taxi terminal project area is located approximately 1.2 km East of the Bierspruit River (Figure 4-5).

Figure 4-4: Ventilation Shafts Project Area Hydrology

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 22 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 4-5: Bus and Taxi Terminal Project Area Hydrology The Present Ecological Status (PES), Ecological Importance and Sensitivity (EIS) and Recommended Ecological Category (REC) for the watercourses in the quaternary catchment area from the various available sources are presented in Table 4-4 below. Table 4-4: River Status of the A24C Quaternary Catchment (DWS; 2014) CATCHMENT SOURCE PES EIS REC

A24C River classification (Kleynhans, 2000) D (largely Moderate C (fair) modified)

Intermediate Reserve Determination for D (largely Moderate D (largely Crocodile (West) Marico (DWA, 2013) modified) modified)

State of Environment Report (SOER) for C (fair) High B/C (good/fair) Amandelbult (SRK Report 444284, 2013)

4.6 GROUNDWATER

This groundwater description has been sourced from the Amandelbult operational Integrated Water and Waste Management Plan (SRK, 2018), Geohydrological Investigation Report (Groundwater Complete, 2011); Updated Amandelbult Groundwater Modelling Report (Golder, 2018) and Amandelbult modernisation project Hydrogeological Assessment (WSP, 2019). The Amandelbult Complex mining right area is located within a local groundwater divide. Local groundwater flow directions are towards the west/north-west (Bierspruit) and east/north-east (Crocodile River) at average gradients of 0.5% and 0.7%, respectively. The aquifer systems identified within the Amandelbult area are as follows:

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 23 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

— Alluvial aquifer in the coarse-grained alluvium deposited in the paleo-channels of the river systems. This forms a minor aquifer system regionally, but can be an important aquifer in the vicinity of the Complex; — Shallow, weathered zone aquifer that occurs in the transitional soil and weathered bedrock zone or sub- outcrop horizon; and — Fractured Bushveld Complex rock-type aquifer in transmissive fractures in the consolidated and mostly impervious bedrock. The aquifers in the area are typically considered to be minor aquifers, with relatively low groundwater potential. No springs are known to occur in the Amandelbult mining area but evidence of groundwater base flow discharge in the low-lying areas close to the Crocodile River and drainage canals does exist. The depth of the groundwater table in the study area has been determined by means of the available groundwater monitoring boreholes. Groundwater levels historically within the mine lease area vary between 5 and 20 meters below surface. The groundwater flow directions are predominately in a northerly direction which follows the Bierspruit towards the western side of the site and to the east it’s drained by the Crocodile River. There are currently numerous groundwater monitoring locations around the Dishaba Mine and the proposed ventilation shafts. Groundwater levels have remained more or less stable with only seasonal water level fluctuations in the monitoring boreholes evident.

4.7 SOCIO-ECONOMIC STATUS

This Socio-Economic description has been sourced from the Amandelbult Social Impact Assessment (Tony Barbour Environmental Consulting and Research, 2019) for the project and operational Integrated Water and Waste Management Plan (SRK, 2018). Thabazimbi Local Municipalit’s main economic activity is mining activities, primarily in platinum, iron-ore, andalusite and limestone. Other economic activities that also play a significant role in the municipality’s economic activity are hunting and agriculture. There is a significant potential for tourism to also contribute the local economy. The retail and manufacturing sectors contribute very little to the local economy. The official unemployment rate in 2011 was 20.6% in Thabazimbi and the youth unemployment rate was 26.9%. No data was collected as part of the 2016 Community Household Survey. These number could have significantly changed over the last couple years. There are a number of operations in the area but Amandelbult Platinum Mine remains the biggest operation and employer in the Municipality. The mining sector is thus the most significant employer in the Thabazimbi Municipality area and has contributed significantly to in-migration to the area. Access municipal services as measured in terms of flush toilets, refuse removal, piped water and electricity, deteriorated between 2011 and 2016 in the municipality. This is likely to be linked to in-migration to the area and the increase in informal households. The IDP for Thabazimbi Municipality identified numerous service delivery challenges, such as water and sanitation. Most households have access to piped water and just over three quarters of households have waterborne sanitation with many of the remaining households largely reliant on ventilated improved pit latrines. Thabazimbi Municipality intends to meet the basic service needs of communities by improving access to water and sanitation from 82.5% to 100% by 2022. In addition to the social infrastructure provided by the Thabazimbi Municipality, Amandelbult residential area with ancillary land uses including business, social and other erven at the Anglo Platinum Mine. Amandelbult is a fully functional township and totally independent from Thabazimbi Municipality regarding infrastructure services, i.e. water, sanitation, electricity, roads and stormwater.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 24 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

5 IMPACT ASSESSMENT

5.1 IMPACT ASSESSMENT METHODOLOGY

To ensure a direct comparison between various specialist studies, a standard rating scale has been defined and was used to assess and quantify the identified impacts. The impact assessment used a rating criteria as per the 2014 EIA regulations and the following rating criteria was used to determine the significance of the identified impacts. Impacts are assessed in terms of the following criteria: a) The nature, a description of what causes the effect, what will be affected and how it will be affected. Table 5-1: Nature or type of impact

NATURE OR TYPE OF IMPACT DEFINITION

Beneficial / Positive An impact that is considered to represent an improvement on the baseline or introduces a positive change.

Adverse / Negative An impact that is considered to represent an adverse change from the baseline, or introduces a new undesirable factor.

Direct Impacts that arise directly from activities that form an integral part of the Project (e.g. new infrastructure).

Indirect Impacts that arise indirectly from activities not explicitly forming part of the Project (e.g. noise changes due to changes in road or rail traffic resulting from the operation of Project).

Secondary Secondary or induced impacts caused by a change in the Project environment (e.g. employment opportunities created by the supply chain requirements).

Cumulative Impacts are those impacts arising from the combination of multiple impacts from existing projects, the Project and/or future projects.

b) The physical extent: Table 5-2: Physical extent of impact

SCORE DESCRIPTION

1 the impact will be limited to the site;

2 the impact will be limited to the local area;

3 the impact will be limited to the region;

4 the impact will be national; or

5 the impact will be international;

c) The duration, wherein it is indicated whether the lifetime of the impact will be:

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 25 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 5-3: Duration of impact

SCORE DESCRIPTION

1 of a very short duration (0 to 1 years)

2 of a short duration (2 to 5 years)

3 medium term (5–15 years)

4 long term (> 15 years)

5 permanent

d) Reversibility: An impact is either reversible or irreversible. A scale of the level of reversibility if an impact is reversible and how long before impacts on receptors cease to be evident. Table 5-4: Reversibility of impact

Score Description

1 The impact is immediately reversible.

3 The impact is reversible within 2 years after the cause or stress is removed.

5 The activity will lead to an impact that is in all practical terms permanent.

e) The magnitude of impact on ecological processes, quantified on a scale from 0-10, where a score is assigned: Table 5-5: Magnitude of impact

SCORE DESCRIPTION

0 Small and will have no effect on the environment.

2 Minor and will not result in an impact on processes.

4 Low and will cause a slight impact on processes.

6 Moderate and will result in processes continuing but in a modified way.

8 High (processes are altered to the extent that they temporarily cease).

10 Very high and results in complete destruction of patterns and permanent cessation of processes.

f) The probability of occurrence, which describes the likelihood of the impact actually occurring. Probability is estimated on a scale where:

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 26 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 5-6: Probability of occurrence of impact

SCORE DESCRIPTION

1 very improbable (probably will not happen.

2 improbable (some possibility, but low likelihood).

3 probable (distinct possibility).

4 highly probable (most likely).

5 definite (impact will occur regardless of any prevention measures).

g) The significance, which is determined through a synthesis of the characteristics described above (refer formula below) and can be assessed as low, medium or high; h) The status, which is described as either positive, negative or neutral; i) The degree to which the impact can be reversed; j) The degree to which the impact may cause irreplaceable loss of resources; and k) The degree to which the impact can be mitigated.

The significance is determined by combining the above criteria in the following formula: Significance = (Extent + Duration + Reversibility + Magnitude) x Probability [푆 = (퐸 + 퐷 + 푅 + 푀) × 푃] Where the symbols are as follows: Table 5-7: Symbols Reference

SYMBOL CRITERIA DESCRIPTION

S Significance Weighting Refer to Table 5-8

E Extent Refer to Table 5-2

D Duration Refer to Table 5-3

R Reversibility Refer to Table 5-4

M Magnitude Refer to Table 5-5

P Probability Refer to Table 5-6

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 27 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

The significance weightings for each potential impact are as follows: Table 5-8: Significance Ratings

SIGNIFICANCE SIGNIFICANCE OVERALL RATING RATING SCORE (NEGATIVE) (POSITIVE) DESCRIPTION

< 30 points Low Low where this impact would not have a direct influence on the decision to develop in the area.

31 - 60 points Medium Medium where the impact could influence the decision to develop in the area unless it is effectively mitigated.

> 60 points High High where the impact must have an influence on the decision process to develop in the area.

5.2 ENVIRONMENTAL AND SOCIAL IMPACTS: VENTILATION SHAFTS

This section provides a summary of the additional impacts that will result from the proposed development of ventilation shafts. These impacts were identified and assessed through specialist studies that were undertaken to inform this assessment report.

5.2.1 BIODIVERSITY IMPACTS

A Biodiversity Assessment (Appendix B) was undertaken by Martinus Erasmus of The Biodiversity Company to understand the additional potential impacts that may result from the development. The proposed activities may lead to the loss and destruction of habitats, direct mortalities and displacement of fauna and flora. The removal of natural vegetation to accommodate infrastructure may reduce the habitat available for fauna species and may reduce animal populations and species compositions within the area, at least temporarily. Land clearing destroys local wildlife habitat and can lead to the loss of local breeding grounds, nesting sites and wildlife movement corridors. The potential impacts associated with the various project stages have been assessed and rated accordingly as shown in Table 5-9 below. Table 5-9: Biodiversity Impact Significance Rating

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Planning Phase

— Temporary disturbance of wildlife due to increased human Negative Medium Low presence and possible use of machinery and/or vehicles

Construction Phase

— Destruction, further loss and fragmentation of the Negative Medium Low vegetation community.

— Further disturbance of a habitat classified as poorly Negative Medium Low protected

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 28 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

— Displacement of faunal community (including potential Negative Medium Low threatened species) due to habitat loss, disturbance (noise, dust and vibration) and/or direct mortalities.

Operational Phase

— Continued disturbance and degradation of the vegetation Negative Medium Low community and encroachment by alien invasive plant species

— Potential leaks or discharges due to broken pipelines Negative Medium Low flooding the surrounding environment, causing erosion and loss of species.

— Continued displacement and fragmentation of the faunal Negative Medium Medium community (including potential threatened species) due to ongoing anthropogenic disturbances and habitat degradation (litter, road mortalities and/or poaching)

— Continued displacement and fragmentation of the faunal Negative Medium Low community due to ongoing anthropogenic disturbances (noise, traffic, dust, pollution and vibrations).

— Bird strikes with the powerlines as well as electrocution by Negative High Medium the electric wiring

Decommissioning Phase

— Faunal impacts due to decommissioning of the wind farm Negative Medium Low such as noise, and operation of heavy machinery on-site.

— Following decommissioning, disturbed areas will remain Negative Medium Low vulnerable to erosion for some time.

— Following decommissioning, the site will be highly Negative Medium Low vulnerable to alien plant invasion

5.2.2 WETLAND IMPACTS

A Wetland Impact Assessment (Appendix C) was undertaken by WSP during which all wetlands and associated water courses within the vicinity of the project area, that may be potentially impacted upon by the proposed development were identified. Two seep Hydrogeomorphic (HGM) units (wetlands) were identified within 500m of the proposed infrastructure, namely S1 and S2. Wetland system S1 is located approximately 100m from the proposed underground powerline at the nearest point. Wetland systems S2 is located approximately 70m away from the proposed downcast ventilation shaft, however, the proposed overhead powerline and access road to the downcast ventilation shaft does pass through the S2 wetland system. The wetland habitat assessment determined that the proposed construction, operation and decommissioning of the proposed infrastructure does have the potential to impact the identified wetlands, with impact ratings between Low and Medium. However with mitigative measures in places, including the application of buffer zones and the relocation of the proposed powerline and access route to the downcast ventilator shaft, the risks associated with the proposed infrastructure are Low. Potential impacts on the wetlands were assessed and rated as shown in Table 5-10 below.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 29 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 5-10: Wetland Impact Significance Rating

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

Alteration to the Natural Flow Regime Negative Medium Low — Potential for increased sediments to enter the system; and, — Potential changes to the wetland hydrology through increased surface water runoff.

Impact On Water Quality Negative Medium Low — Increased sediment input; — Effluent generated on site may enter the wetland; — Domestic waste potentially entering the system; and — Potential for increased toxic chemicals and hydrocarbons to enter the wetland.

Biodiversity Loss Negative Medium Low — Alterations to the wetland functionality; and — Loss of plant and animal species

Vegetation Clearing: Negative Medium Low — Decreased roughness; — Increased runoff (volume and velocity); and, — Soil compaction

Loss of Wetland Habitat Negative Medium Low — Potential for increased sediment loads to enter the wetland: and, — Potential infilling of the wetland.

Operational Phase

Alteration to the Natural Flow Regime Negative Medium Low — Potential for increased sediments to enter the system; and, — Potential changes to the wetland hydrology through increased surface water runoff.

Water Quality Negative Medium Low — Increased sediment input; — Effluent generated on site may enter the wetland; — Domestic waste potentially entering the system; and — Potential for increased toxic chemicals and hydrocarbons to enter the wetland.

Decommissioning Phase

Alteration to the Natural Flow Regime Negative Medium Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 30 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

— Potential for increased sediments to enter the system; and, — Potential changes to the wetland hydrology through increased surface water runoff.

Water Quality Negative Medium Low — Increased sediment input; — Effluent generated on site may enter the wetland; — Domestic waste potentially entering the system; and — Potential for increased toxic chemicals and hydrocarbons to enter the wetland.

5.2.3 AIR QUALITY IMPACTS

The construction phase of the development will generate a lot of dust emissions as a result of excavation and drilling activities, as well as the operation and movement of heavy machinery and vehicles. These impacts are temporary and can be effectively minimised through the implementation of management measures and as such, have been assigned a low impact significance. Table 5-11 below summarised the airy quality impacts. Table 5-11: Air Quality Impacts Significance

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Generation and emission of dust and particulate matter Negative Medium Low (PM)

— Emission of exhaust fumes from construction vehicles Negative Low Low

5.2.4 NOISE IMPACTS

The drilling and excavation activities during the construction phase of the ventilation shafts will result in elevated noise levels that will impact on the surrounding farm landowners as well as faunal life. This impact will however be temporary and limited to the construction phase. Table 5-12 below summarises the impact significance before and after mitigation. Table 5-12: Noise Impacts Significance

Without Impacts Identified Status Mitigation With Mitigation

Construction Phase

Generation of Noise Negative Low Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 31 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

5.2.5 SOCIAL IMPACTS

A Social Impact Assessment (Appendix D) was carried out by Tony Barbour. The assessment focused on understanding the potential negative and positive impacts associated with the proposed development on the surrounding communities. The key positive impact associated with the development includes the creation of employment and business opportunities. The development enables the modernization initiative, which will improve the efficiency and productivity on the mine for the remaining 33 years of the life of mine. This in turn will ensure the retention of jobs and the continued socio-economic benefits associated with the mine. This positive impact is of high significance given its long term and significant socio-economic contribution. Negative impacts include the destabilization of family structures and social networks associated with the influx of job seekers and construction workers, as well as the health and safety risks to the farmers and neighbouring communities. These have been rated to be of low significance. Worthy of noting is that the project is only an extension of existing mining activities which have already adjusted the social dynamics within the neighbouring local communities and as such, the intensity of the changes that will be brought about by the project are minimal. The impacts are detailed in Table 5-13 below. Table 5-13: Social Impact Significance Rating

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Creation of employment and business opportunities during Positive Medium High the construction phase

— Potential impacts on family structures and social networks Negative Low Low associated with the presence of construction workers

— Potential impacts on family structures, social networks and Negative Very Low Very Low community services associated with the influx of job seekers

— Potential risk to safety of scholars, farmers and farm Negative Low Low workers, livestock and damage to farm infrastructure associated with the presence of construction workers on site

— Potential loss of livestock, crops and houses, damage to Negative Medium Low farm infrastructure and threat to human life associated with increased incidence of grass fires

— Potential noise, dust and safety impacts associated with Negative Medium Low movement of construction related traffic to and from the site

Operational Phase

— Creation of employment and business opportunities during Positive High High the operational phase

— Potential job losses associated with AMP Negative Medium Low

Decommissioning Phase

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 32 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

The impacts associated with mine closure and decommissioning are addressed in the SLP, and as such are not addressed as part of the SIA for the AMP

5.2.6 HERITAGE IMPACTS

Archaentos was appointed to undertake a Heritage Impact Assessment (Appendix E) in the study area. Following a site visit and a brief desktop assessment, it is the opinion of the heritage specialist that the project may be exempted from conducting a Heritage Impact Assessment (HIA) based on the following factors: — The proposed development is within an area already entirely disturbed by mining activities. — There are limited natural vegetation on both sites, an indication of former disturbance. — Although vegetation cover is dense and reasonably high, it mainly consists of pioneer species and grass. — Various HIA studies have been done in the broader geographical region in the past. In certain cases no heritage sites were noted. In other cases graves and Iron Age sites have been found. These are however located outside of the mine boundary (SAHRIS database; Archaetnos database). An exemption from carrying out a HIA was therefore given by the heritage specialist, with the condition however, that should any objects or features, as well as graves and burials be uncovered during construction activities on site, work will cease immediately and an archaeologist will be contacted as a matter of urgency to assess such occurrences.

5.2.7 SOIL AND LAND CAPABILITY IMPACTS

A Soil and Land Capability study (Appendix F) was undertaken by WSP to assess the potential impacts that the proposed project may have on the receiving environment’s land capability. The following was deduced from the study: — The site is dominated by Vertic soils, whose shrink-swell clay properties pose significant limitations to agriculture. — The site is not currently being used and is predominantly covered by long grasses and shrubs. Identified potential soils impacts as a result of the proposed development include soil contamination, compaction and erosion, as well as sedimentation, change in land form and a loss of topsoil. Table 5-14 indicates the significance rating of these impacts. Table 5-14: Soil and Land Capability Impact Significance Rating

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Soil Erosion Negative Medium Low

— Soil Compaction Negative High Medium

— Sedimentation Negative Medium Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 33 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

— Soil Contamination Negative Medium Low

— Loss of Topsoil Negative Medium Low

— Change in Surface Profile Negative Low Low

5.2.8 HYRDOLOGY

A Hydrological Impact Assessment (Appendix G) was undertaken to assess the project’s potential impacts on the hydrology of the area. Primary potential impacts identified include a change in the flow regime (and therefore potential source of the crocodile river) as a result of the road alignments, and potential contamination of the rivers from the potential contamination sources. The impacts are summarised in Table 5-15. Table 5-15: Hydrology Impact Significance

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Change in flow regime caused by the alignment of the roads Negative Low Low

— Change in flow regime and a potential source of Negative Low Low contamination to the Crocodile River

— Infrastructure and machinery increases potential Negative Low Low contamination sources

5.2.9 HYDROGEOLOGY

Potential impacts on the groundwater resources identified during the Hydrogeology Assessment (Appendix H) include the percolatiton and lateral migration of contaminants into groundwater resources, as well as the drawdown of water levels in nearby local aquifers as a result of the lowering of groundwater resources as dewatering is carried out by the ventilation shafts. The impacts significance are detailed in Table 5-16. Table 5-16: Groundwater Impacts Significance

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Contamination of shallow aquifers through leaks or spills of Negative Medium Low oils, fuel, grease (from construction vehicles) and sewage from temporary on-site ablution facilities: Percolation of contaminants to groundwater:

— Contamination of shallow aquifers through leaks or spills of Negative Medium Low oils, fuel, grease (from construction vehicles) and sewage

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 34 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

from temporary on-site ablution facilities.: Lateral migration in groundwater:

— Disposal of waste rock on existing waste rock dumps during Negative High Medium construction of the vent shafts: Percolation of contaminants to groundwater

— Disposal of waste rock on existing waste rock dumps during Negative High Medium construction of the vent shafts: Drawdown of water levels in local aquifers

Operational Phase

— Removal of water from underground at the vent shafts- Negative High Medium Drawdown of water levels in local aquifers

Decommissioning Phase

— Decant of contaminated groundwater- Percolation of Negative Medium Medium contaminants to groundwater

— Decant of contaminated groundwater- Lateral migration in Negative Low Low groundwater

5.2.10 CLOSURE

A Closure Plan (Appendix I) was compiled by The MSA Group to assess the risks associated with the closure and decommissioning of the proposed new ventilation shafts (in addition to all other mining infrastructure at the end of life of mine) and associated surface infrastructure. All natural (air quality, biodiversity, surface and groundwater reserves), health and safety, socio-economic and financial risks and impacts relating to the decommissioning and closure of the ventilation shafts were assessed (and are summarised in Table 5-17) prior to and after the implementation of mitigation measures. Highly significant impacts (prior to the implementation of management measures) include the loss of income, health and safety risks associated with the possible collapse of remnant infrastructure, loss of agricultural potential due to a decreased land capability and various environmental consequences as a result of failure to implement the final rehabilitation and closure plan. Table 5-17: Decommissioning and Closure Impacts Significance

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Decommissioning Phase

— Dust generation and fugitive emissions Negative Medium Low

— Inadequate management of soil stockpiles and rehabilitation Negative Medium Low activities will lead to erosion due to environmental factors.

— Loss of Agricultural Potential and Change of Current Land Negative High Low Use

— Soil Contamination Negative Medium Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 35 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

— Groundwater - Decant. Negative Medium Medium

— Impacts on Surface water quality Negative Medium Low

— Permanent loss of biodiversity and in-affected Biodiversity Negative Medium Low reestablishment

— Possibility of failing to control alien invasive species on Negative Medium Low rehabilitated land.

— Collapse of remnant infrastructure which could lead to Negative High Low human injury or fatality.

— Loss of income and jobs Negative High Medium

— Visual intrusion of decommissioning activities associated Negative Medium Low with a ventilation shafts

— Failure to implement the final rehabilitation, Negative High Low decommissioning and closure plan for the proposed ventilation shafts (due to budget restraints and/or shortcomings)

RESIDUAL RISKS POST CLOSURE The closure risk assessment also included an assessment of the residual risk that would remain after implementation of the closure actions and management interventions during decommissioning. The assessment concluded that there are negligible residual risks associated with the ventilation shafts development only. The majority of the latent environmental risk relates to the existing operations (specifically existing and future underground mining). It was recommended that residual environmental liabilities be addressed holistically as part of the existing operational requirement in terms of the NEMA Financial Provisioning Regulations.

5.3 ENVIRONMENTAL AND SOCIAL IMPACTS: BUS AND TAXI TERMINAL

This section provides an assessment for the newly identified and anticipated impacts that will result from the construction activities to be undertaken to upgrade the bus and taxi terminal at Tumela Mine. Impacts have been rated according to the impact rating methodology detailed in Section 5.1 of this report, and a significance rating has been assigned to each impact prior to and after the implementation of suggested mitigation measures. The detailed impact assessment is included in Appendix K.

5.3.1 AIR QUALITY IMPACTS

GENERATION AND EMISSION OF DUST AND PARTICULATE MATTER (PM) Air quality guidelines are provided by the ambient dust concentration limits prescribed by SANS 1929:2005. Whilst these guidelines are currently not enforceable they do serve as recommendations for good practice.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 36 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

SANS 1929:2005 sets out dust deposition rates, expressed in units of mg.m-2.day-1 over a typical 30-day averaging period. During the construction phase, dust and vehicular emissions will be released as a result of demolitions (of existing bus and taxi terminal infrastructure), excavations as well as earth moving machinery and trucks transporting construction material. The emissions will, however, have short term impacts on the immediate surrounding areas which can be easily mitigated and thus the authorisation of such emissions will not be required. All construction phase air quality impacts will be minimised with the implementation of dust control measures detailed in Table 5-18 and the dust impacts will be short term in nature. EXHAUST FUMES There are no anticipated dust issues during the operational phase as the site will be paved, however, low impacts are expected with regards to fumes from the onsite vehicles on the site. The operational impacts of the terminal on air quality is indicated in Table 5-18. Table 5-18: Air Quality impact from dust and PM generation during Construction Phase

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Generation and emission of dust and particulate matter Negative Medium Low (PM)

Operational Phase

— Exhaust Fumes Emissions Negative Low Low

5.3.2 NOISE IMPACTS

Elevated noise levels are likely to be generated by the construction activities (machinery and vehicles) and the workforce. The Occupational Health and Safety Act Regulations state that no employer or self-employed person shall require or permit any person to enter any workplace under his or her control where such person will be exposed to noise at or above the 85 dBA noise-rating limit. It is important to note that noise impacts (nuisance factor) may vary in the different areas as a result of the surrounding land uses and will be temporary in nature. Due to the temporary and limited nature of the project activities, coupled with the fact that there are a limited number of noise receptors around the project area, the impacted is regarded as low. The construction impact on noise is indicated in Table 5-19Table 5-19. Table 5-19: Noise impacts during the construction phase

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Generation of Noise Negative Low Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 37 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

5.3.3 SOIL EROSION AND CONTAMINATION IMPACTS

SOIL EROSION During the construction phase, measures should be implemented to manage stormwater and water flow on site. If the stormwater and water flow is not regulated and managed onsite, it could cause significant erosion of soil on the stockpiles and/or exposed surfaces (exposed during demolitions and excavations). The construction impact on soil erosion is indicated in Table 5-20.

SOIL CONTAMINATION During construction activities, construction vehicles/trucks/machinery as well as hazardous substances stored on the site might spill and contaminate the soil and groundwater resources. The impact of the construction phase on soil pollution is indicated in Table 5-20. Table 5-20: Soil erosion and compaction impacts from construction activities

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Soil Erosion Negative Medium Low

— Soil Contamination Negative Medium Low

5.3.4 BIODIVERSITY IMPACTS

VEGETATION REMOVAL The construction phase will involve the removal of seven indigenous trees (i.e. Vachellia tortilis and a Searsia spp) that are present at the current informal terminal. This is however limited as the proposed site has already been transformed and has no vegetation cover with the exception of the few large trees. The construction impact on the removal of these trees is indicated in Table 5-21 . Table 5-21: Vegetation loss Impact from construction activities

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Vegetation removal Negative Medium Low

5.3.5 GROUNDWATER IMPACTS

DETERIORATION IN WATER QUALITY There is a potential to affect the groundwater quality in the area. This is influenced by spills and leaks, the storage of chemicals, mixes and fuel. Any contaminants that are not cleaned from the ground will seep into underground water resources. The impact of construction on change in water quality is shown in Table 5-22: Impacts on groundwater during the construction phase

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 38 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

. Table 5-22: Impacts on groundwater during the construction phase

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Deterioration In Water Quality Negative Medium Low

5.3.6 TRAFFIC IMPACTS

During the construction phase the project area will experience a slight increase in traffic due to the movement of trucks, construction vehicles and machinery. The impact of additional traffic during construction is however expected to be minimal and short term, and has therefore been assessed as a low impact (Table 5-23) Table 5-23: Traffic impacts during the construction phase

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Increased Local Traffic Negative Low Low

5.3.7 SOCIO-ECONOMIC

CONSTRUCTION AND OPERATIONAL PHASE

EMPLOYMENT OPPORTUNITIES The proposed development will create a limited number of employment opportunities for contractors and individuals in the surrounding area. The positive impact of this phase is limited as it is temporary as well. The construction impact on employment opportunities is indicated in Table 5-24: Construction impacts on employment opportunities

Table 5-24: Construction impacts on employment opportunities

WITHOUT WITH IMPACTS IDENTIFIED STATUS MITIGATION MITIGATION

Construction Phase

— Increased Local Traffic Positive Low Low

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 39 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

5.3.8 NO-GO ALTERNATIVE

The no-go alternative will mean none of the negative or positive impacts described above will come into effect. As such the potential health and safety risks associated with the current area will remain.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 40 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

6 UPDATE OF THE ENVIRONMENTAL MANAGEMENT PROGRAMME

Provisions have been made in the existing EMPR for the construction and operation of existing mining infrastructure. These provisions are made to ensure minimal environmental impact and damage occurs. Newly identified mitigation and management measures associated with the proposed developments are detailed in this section and must be adhered to as an addition to the existing EMPR. Monitoring of the application of mitigation measures should be undertaken on a continuous basis to ensure effective application of all recommendations.

6.1 VENTILATION SHAFTS ENVIRONMENTAL MANAGEMENT PROGRAMME

Table 6-1 provides all management and mitigation measures to be implemented during the construction and operational phases of the proposed additional ventilation shafts (and their associated infrastructure).

6.2 BUS AND TAXI TERMINAL ENVIRONMENTAL MANAGEMENT PROGRAMME

The EMPR presented in Table 6-2 below provides mitigation and management measures to be implemented during the construction and operational phase of the bus and taxi terminal upgrade development.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 41 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 6-1: Environmental Management Programme: Ventilation Shafts

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND

MANAGEMENT MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER BIODIVERSITY MANAGEMENT PLAN

1. Only areas considered absolutely X X X X X X X necessary for the installation of project infrastructure should be cleared of vegetation. Surrounding vegetation should be protected by erecting a form of temporary barrier (such as Red And White Striped Tape). 2. Where possible, access to the X X X surrounding areas should be prevented. Human encroachment into this area will most likely severely alter the state of this area. The existing fences should be maintained. 3. The width of the new roads must X X X X X be restricted by the demarcation of the edges of the roads. 4. A qualified environmental control X X X officer must be on site when construction begins to identify species that will be directly disturbed and to relocate fauna/flora that is found during

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 42 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER construction (including all reptiles and amphibians). 5. Rehabilitation of the disturbed X X X X areas existing in the project area must be made a priority. Topsoil must also be utilised, and any disturbed area must be re- vegetated with plant and grass species which are endemic to this vegetation type. 6. An alien invasive management and X X X erosion plan must be compiled and implemented. 7. Areas that are denuded during X X X X X construction need to be re- vegetated with indigenous vegetation to prevent erosion during flood events. This will also reduce the likelihood of encroachment by alien invasive plant species. 8. If any indigenous faunal species X X X X are recorded during construction, activities should temporarily cease, and allow the fauna to move away.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 43 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 9. Fauna species such as frogs and X X X reptiles that have not moved away should be carefully and safely removed to a suitable location beyond the extent of the development footprint by a suitably qualified ECO trained in the handling and relocation of animals. 10. No trapping, killing or poisoning X X X X X of any wildlife is to be allowed on site and within the surrounding area, including snakes, birds, lizards, frogs, insects or mammals. 11. During the construction phase X X X X X noise and vibrations must be kept to a minimum to reduce the impact of the development on the fauna residing on the site. 12. Staff should be educated about the X X X X sensitivity of faunal species and measures should be put in place to deal with any species that are encountered during the construction process. 13. For larger pylons and poles, it is X X X X X recommended to install bird

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 44 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER guard/spike structures, to prevent birds from landing on and/or nesting on the pylons and poles. This has been linked with increases in corvid populations which can impact local reptile and avifauna species (plovers in particular). WETLANDS

14. The identified wetlands must be X X X X X X X demarcated as no-go areas during construction of access roads and the plant activity areas. 15. Ensure that no equipment is X X X X X X washed in the streams and wetlands of the area, and if washing facilities are provided, that these are placed no closer than 50m from a wetland or water course and that the discharge from these are managed through adequate stormwater management. 16. A site layout plan must be X X X X X X X compiled indicating the limits of disturbance associated with the proposed infrastructure in relation to the identified sensitive areas

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 45 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER (i.e. wetlands). No-go areas and any stormwater infrastructure must be indicated on this plan together with erosion and sediment, controls and measures. 17. During the construction, X X X X X X X operational and decommissioning phases, sediment control measures must be adopted in order to prevent sediments entering the wetland. A stormwater management plan must be developed. 18. Machinery and equipment must be X X X X inspected regularly for faults and possible leaks. If required, servicing of these should occur off site. 19. Potential contaminants used and X X X X X X stored on site should be stored and prepared on bunded surfaces to contain spills and leaks. A Spill Response Plan must be available for any spills that occur during construction, operation and decommissioning. 20. The construction site camp and X X X X X X X stockpile locations must not be

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 46 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER located within wetland and buffer areas. These should be located in already disturbed areas and kept to a minimal size. Appropriate measures (stormwater management) should be taken to ensure that sediments from these stockpiles do not enter the wetlands. Rehabilitation should occur to these areas once construction has been completed. 21. No water should be abstracted X X X X X X from the surrounding wetlands or the dam located downstream of wetland S2 for construction purposes, unless this has been authorised. Ideally water required during the construction phase must be sourced from an external source (i.e. outside of the wetland contributing area). 22. Monitoring of the water table within the vicinity of the wetlands should be undertaken to establish whether the development has an effect on the region water table depth. If a change is observed, an investigation into the groundwater

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 47 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER contribution to the wetlands should be undertaken which should include ongoing monitoring of changes in depth of the piezometric surface 23. The buffer zones determined and X X X X X X as illustrated in Figure 12 of the Wetlannd Impact Assessment Report attached should be clearly demarcated as no go areas during the construction and operation phases of the project. LAND MANAGEMENT PLAN

24. The vent shaft should be clearly X X X X marked on a drawing after closure and rehabilitation.

25. If during construction any possible X X X X X archaeological finds are made, the operations must be stopped immediately, the SAHRA is to be contacted and an archaeological consultant appointed.

26. Work may only resume once X X X X clearance is given in writing by the archaeological consultant.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 48 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 27. If disturbances take place beyond X X X X X X the shaft footprint area, rehabilitation will be undertaken accordingly.

28. Prior to any construction, soil will X X X X be stripped and stockpiled from all areas to be disturbed. A minimum of 300 mm of soil will be stripped. 29. Areas of soil stockpiles and bare X X X X soil should be revegetated and adequate site drainage should be incorporated.

30. When grubbing the site, only large X X X X X trees will be removed prior to the removal of the soil, thus allowing for the remaining shrubs and bushes to contribute to the organic matter content of the soil.

31. All soil stripped will be stockpiled X X X X X X for use in rehabilitation. The chemical and physical properties of the topsoils and subsoils do not differ significantly and will therefore not need to be stored separately. As the stockpiles will be in place for several years, no special measures will be

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 49 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER introduced to preserve the organic content of the soils.

32. All disused infrastructure will be X X X X X X demolished during Mine closure and waste material will be disposed of appropriately. All disturbed areas will be reinstated to the original land use, unless different end-land uses have been identified as part of overall closure planning. Closure planning to align with the ‘overall Mine closure plan’.

33. Soil replacement will be done in X X X such a manner as to ensure that the soil is not significantly compacted or contaminated.

34. Following closure re-vegetation, X X X the site will be monitored and maintained until an acceptable, self-sustaining vegetation cover has been achieved.

35. Areas disturbed temporarily X X X X X during the construction phase, such as laydown areas, will be rehabilitated directly after the completion of construction.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 50 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER Following the removal of project infrastructure (i.e. decommissioning phase), affected areas will be revegetated directly following the cessation of operations.

36. Soil stockpile heights will be X X X X X X X limited to approximately 2-4 m or alternatively will be benched to limit slope length in an effort to reduce erosion.

37. Stockpiles will be covered with X X X X X X X vegetation cleared during the scrubbing and if not naturally vegetated within a 1-2 year timeframe will be seeded with a mix of indigenous species.

38. To prevent ingress of clean X X X X X X X X X stormwater onto site, up gradient berms will be established using spoil and topsoil material.

39. Surface water management X X X X X X X X infrastructure constructed from soil will be inspected on a monthly basis, with more frequent inspections during periods of high rainfall and after major rain events.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 51 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER If any of the inspections identify eroded areas, these will be repaired before the next inspection. 40. The use of drip trays, regular X X X X X servicing of vehicles and demarcation of working zones will help to limit the contamination.

41. Spillages of oil, grease and X X X X X X X X X X hydraulic fluids will be cleaned up by undertaking soil remediation. In the event that this is not feasible soil should be removed and disposed of at a licensed facility (hazardous). Runoff will be diverted away from areas where significant spillages have occurred using berms or similar features. WATER MANAGEMENT PLAN

42. Use water saving technologies, X X X X where practical.

43. Manage vegetation and X X X stormwater to minimise erosion.

44. Clean water will be diverted X X X X around the shaft areas.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 52 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 45. Waste rock generated by the raise X X X X X bore drilling activities will be temporarily stockpiled on the project site. Material will be removed from the temporary stockpile on a continuous basis.

46. All waste rock contained within X X X X the temporary stockpile will be transferred to the operational Mine waste rock dump (WRD).

47. Determine the adequacy of the X X X X existing Mine wide groundwater monitoring programme to monitor additional groundwater impacts as a result of the proposed ventilation shafts.

48. Oil and diesel spills should be X X X X X X X X X X cleaned up within 24 hours.

49. Should oil and diesel storage be X X X X X X X X X required on the site during both construction or operational phases, the hazardous substances will be stored within a bunded area which has the capacity to store 110% the volume of the largest tank, where more than one tank is included in a bunded area.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 53 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 50. Sufficient toilets will be provided X X X X X for the construction staff (one toilet for 15 staff members).

51. No construction of any water X X X X X management measures or the access road will be undertaken with contaminated material. 52. Adhere to the conceptual storm X X X X X X water management plan. 53. Maintaining water quality X X X X monitoring of the Crocodile River 54.

55. Should the alternative of utilising X X X X X an existing access route not be considered, culverts should be placed under haul roads to allow natural drainage of the catchment. VISUAL/AESTHETICS MANAGEMENT PLAN

56. A reas used for temporary X X X X X X stockpiling of waste rock will be cleaned up and covered with topsoil to encourage natural vegetation growth, following the construction phase.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 54 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER NOISE AND VIBRATION MANAGEMENT PLAN

57. X X X X During the construction phase, noise must be kept to an absolute minimum during the evenings and at night to minimise all possible disturbances. In the event that noisy activities (such as raise boring, drilling or use of heavy machinery) are required to be undertaken at night, relevant neighbouring landowners and stakeholders must be informed prior to the activities taking place

58. Selection of construction X X X X equipment with lower sound power level specifications. 59. Installation of mufflers on X X X X exhausts of construction vehicles. 60. The use of ear protection X X X X equipment for personnel working onsite in close proximity to noise sources. 61. Enclosing of the fan mechanism X X X X (excluding the fan blades) within a sound absorbing enclosure.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 55 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 62. Erection of an acoustic barrier X X X X along the southern boundary of the operations to limit the noise propagation towards the receptors to the south of the site. 63. A second noise monitoring X X X X campaign be undertaken once the ventilation shaft is operational. Since perception to noise is highly subjective, such monitoring will aid in confirming off-site noise levels and whether any complaints that may arise will warrant the need for mitigatory interventions. AIR QUALITY MANAGEMENT PLAN

64. Review dust fallout monitoring X X X X X X plan to incorporate the new infrastructure.

65. Refrigeration equipment must be X X X enclosed in properly designed and constructed buildings with brick walls and sheet metal roofs.

66. Ammonia/R134a sensors to be X X X installed at all refrigeration plants. The sensors to be linked to an

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 56 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER alarm system to warn of ammonia/R134a leakages.

67. Should excessive dust occur as a X X X X X X result of construction activities, water carts will be used to wet the area.

68. Dust suppression of the unpaved X X X X X X gravel access road will be undertaken via wetting down, if when dust becomes an issue.

69. Speed limit of 20 km/h to be X X X X X X enforced on the access gravel road. the road will be used into the operational phase and therefore should gravelled at the onset of the construction phase as part of dust suppression.

70. A wetting system will be used to X X X suppress dust where tipping of waste rock occurs.

71. Vehicle and machinery to be X X X X X X X X maintained regularly to ensure that gas and smoke emissions are minimised. WASTE MANAGEMENT PLAN

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 57 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 72. Domestic waste will be disposed X X X X X X X X of at the Mine landfill.

73. Litter bins are to be provided at the X X X X construction site and should be emptied when full for disposal at the Mine landfill.

74. Contaminated construction waste X X X X and clean construction waste must be dealt with separately; the former should be removed to a registered hazardous waste landfill disposal site.

75. Hazardous waste will need to be X X X X X X X X separated from the general waste and separate bins should be provided for this. 76. Hazardous waste safety disposal X X X X X X X X certificates should be obtained within 30 days of the disposal date.

77. Waste will be managed in line with X X X X X X X X the Anglo Amandelbult ZW2L Strategy

78. All building rubble must be X X X X removed to a registered waste disposal facility/rubble aggregate recovery facility or used as backfill

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 58 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

Y

-

MITIGATION AND MANAGEMENT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFET SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PROJECT MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER in areas of rehabilitation. Proof of disposal should be retained.

79. No wet wastes or solvents shall be X X X X X X X X X permitted to be disposed of down sewers, drains or stormwater drains. SOCIO-ECONOMIC MANAGEMENT PLAN

80. The project will be utilising a X X X X contractor for the construction of the facility. The contractor should apply the existing Mine socio- economic requirements with regards to BBEEE and local community employment. Mine wide training/internship programs should be considered by the project team.

81. The project area should be fenced X X X X off prior to construction commencement.

82. No retrenchment issues are X X X expected as a contractor is being used for the construction of the facility. Operational labour requirements are extremely limited.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 59 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 60 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 6-2: Environmental Management Programme: Bus and Taxi Terminal

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT

MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER BIODIVERSITY MANAGEMENT PLAN

It is recommended that83. areas to X X X X X X be developed be specifically demarcated so that during the construction phase and operational phase, only the demarcated areas are impacted upon. All parking areas, ablution facilities, car wash area, kiosk and access roads must be clearly demarcated from surrounding natural areas and no persons should be allowed to enter these areas under any circumstances. 84. A fence should be erected to X X X X X separate the temporary terminal and its supporting areas (parking lots/car wash etc) and associated infrastructure from the surrounding natural areas so as to restrict any movement and activities from encroaching the natural environment. 85.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 61 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER LAND MANAGEMENT PLAN

86. Where possible, consider X X X X conducting construction activities during winter where rainfall is minimal.

87. Only the proposed demarcated X X X X terminal project area should be excavated, stripped or cleared of vegetation.

88. If possible, implement X X X X stormwater management measures that will help to reduce the speed of the water. These measures must also assist with the prevention of water pollution, erosion and siltation.

89. Erosion control measures should X X X X X be implemented during the construction phase on large exposed areas and where stormwater is temporarily channelled.

90. Any exposed earth should be X X X X rehabilitated promptly, and this could include planting suitable vegetation (vigorous indigenous

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 62 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER grasses) that mimics the surrounding environment to protect the exposed soil. 91. If excavations or foundations fill X X X X up with stormwater, these areas should immediately be drained and measures to prevent access to these areas should be implemented.

92. Landscape the area so that there X X X X X X is a free flow of water, without being erosive, thus increasing the catchment area.

93. All soil stripped will be X X X X stockpiled for use in rehabilitation.. Soil stockpile heights will be limited to approximately 2-4 m or alternatively will be benched to limit slope length in an effort to reduce erosion.

94. All construction vehicles, X X X X X machinery and equipment must be properly maintained to prevent leaks.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 63 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 95. Vehicles and machinery are to be X X X X X repaired immediately upon developing leaks.

96. Dip trays shall be supplied for all X X X X X X idle vehicles and machinery.

97. No repair work may be X X X X X undertaken on machinery onsite or campsite area; 98. Drip trays are to be inspected X X X X X X daily for leaks and effectiveness, and emptied when necessary. This is to be closely monitored during rain events to prevent overflow.

99. Keep spill kits onsite and train X X X X X X personnel to use them appropriately. 100. Fuels and chemicals must be X X X X X X X stored in adequate storage facilities that are secure, enclosed and bunded. WATER MANAGEMENT PLAN

101. During construction contractors X X X X X used for the project must have spill kits available to ensure that

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 64 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER any fuel or oil spills are cleaned- up and discarded correctly.

102. A suitable storm water X X X X X X X management plan must for formulated for the project. The plan must ensure that clean and dirty water are separated, that only clean water is diverted into the natural environment and that the discharge of water will not result in scouring and erosion of the surroundings. 103. The stormwater management X X X X X plan should incorporate “soft” engineering measures as much as possible, limiting the use of artificial materials.

104. As much material must be pre- X X X X X fabricated and then transported to site to avoid the risks of contamination associated with mixing, pouring and the storage of chemicals and compounds on site.

105. Oil and diesel spills should be X X X X X X X X cleaned up within 24 hours.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 65 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 106. Should oil and diesel storage be X X X X X X X X required on the site during both construction or operational phases, the hazardous substances will be stored within a bunded area which has the capacity to store 110% the volume of the largest tank, where more than one tank is included in a bunded area. 107. All machinery and equipment X X X X X should be inspected regularly for faults and possible leaks, these should be serviced off-site.

108. Adequate sanitary facilities and X X X X X X ablutions on the servitude must be provided for all personnel throughout the project area. Use of these facilities must be enforced (these facilities must be kept clean so that they are a desired alternative to the surrounding vegetation).

109. All contractors and employees X X X X X X X should undergo induction which is to include a component of environmental awareness. The

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 66 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER induction is to include aspects such as the need to avoid littering, the reporting and cleaning of spills and leaks and general good “housekeeping”; NOISE AND VIBRATION MANAGEMENT PLAN (SPECIALIST STUDY REPORT EXTRACT)

110. The equipment used during X X X X construction must be in good working order, within service dates, and inspected before use. 111. The use of ear protection X X X X equipment for personnel working onsite in close proximity to noise sources. 112. Erection of an acoustic barrier X X X X X along the boundary of the construction site to limit the noise propagation towards the receptors to the south of the site. 113. When possible,align working X X X times with the mine related operational times. 114. Install noise reducing fittings on X X X machinery (if required).

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 67 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER AIR QUALITY MANAGEMENT PLAN

115. Implement dust suppression X X X X X X methods during construction to minimise dust emissions from the site activities.

116. Speed limit of 20 km/h to be X X X X X X enforced on the access gravel road.

117. All stockpiles must be restricted X X X to designated areas and may not exceed a height of two (2) metres.

118. Vehicle and machinery to be X X X X X X X X maintained regularly to ensure that gas and smoke emissions are minimised. 119. All materials transported to site X X X X X must be transported in such a manner that they do not fly or fall off the vehicle. This may necessitate covering or wetting friable materials. 120. No burning of waste, such as X X X X X X plastic bags, cement bags and litter is permitted.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 68 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER 121. All issues/complaints regarding X X X X X dust must be recorded in the complaints register. WASTE MANAGEMENT PLAN

122. Domestic waste will be disposed X X X X X X X X of at the Mine landfill.

123. Litter bins are to be provided at X X X X the construction site and should be emptied when full for disposal at the Mine landfill.

124. Contaminated construction X X X X waste and clean construction waste must be dealt with separately; the former should be removed to a registered hazardous waste landfill disposal site.

125. Hazardous waste will need to be X X X X X X X X separated from the general waste and separate bins should be provided for this.

126. All building rubble must be X X X X removed to a registered waste disposal facility/rubble aggregate recovery facility or used as backfill in areas of

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 69 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

ENVIRONMENT PHASE RESPONSIBILITY

ECONOMIC

- MITIGATION AND

NO. MANAGEMENT OJECT MEASURES

GEOLOGY TOPOGRAPHY USE LAND SOIL, CAPABILITY AND AND FAUNA FLORA WATER SURFACE GROUNDWATER QUALITY AIR NOISE VISUAL ARCHAEOLOGY WASTE GENERATION AND SPILLAGES INCIDENTS AND HEALTH SAFETY SOCIO CONSTRUCTION OPERATIONAL AND CLOSURE POST CLOSURE PR MANAGER CONSTRUCTION MANAGER ENVIRONMENTAL COORDINATOR SHE MANAGER rehabilitation. Proof of disposal should be retained.

127. No wet wastes or solvents shall X X X X X X X X X be permitted to be disposed of down sewers, drains or stormwater drains. 128. Enough litter bins should be X X X placed at the terminal and near the kiosks. 129. Ensure that all litter bins are X X X emptied regularly once the terminal is operational. 130. Place signage around the X X X terminal prohibiting littering. SOCIO-ECONOMIC MANAGEMENT PLAN

131. The project is utilising a X X X contractor for the construction of the facility. The contractor should apply the existing Mine socio-economic requirements with regards to BBEEE and local community employment. Mine wide training/internship programs should be considered by the project team.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 70 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN WSP EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE November 2019 Project No. 41101879 Page 71 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

7 STAKEHOLDER ENGAGEMENT

7.1 PURPOSE OF STAKEHOLDER ENGAGEMENT

Stakeholder engagement is understood to be a series of inclusive and culturally appropriate interactions aimed at providing stakeholders with opportunities to express their views, so that these can be considered and incorporated into the decision-making process. Effective stakeholder engagement requires the prior disclosure of relevant and adequate project information to enable stakeholders to understand the risks, impacts, and opportunities of the proposed amendments. Basic reasons why we involve public in the Amendment Process: — The environment is held in public trust, therefore use of environmental resources is everyone's concern. — Stakeholder engagement is proper, fair conduct in public decision-making activities. Focus on vulnerable and disadvantaged person and offer equitable participation due to historical issues. — A way to ensure that projects meet the citizens' needs and are suitable to the affected public. — The project carries more legitimacy, and less hostility, if interested and affected parties (I&APs) are able to contribute and raise concern / support to be considered in the decision-making process. Finally, the final decision is informed when local knowledge and values are included and when expert knowledge is publicly examined.

7.1.1 OBJECTIVES

The objectives of the stakeholder engagement process can be summarised as follows: — Identify relevant individuals, organisations and communities who may be interested in or affected by the proposed amendments; — Clearly outline the scope of the proposed amendments, including the scale and nature of the existing and proposed activities; — Identify shortcomings and gaps in existing information; — Identify key concerns, raised by Stakeholders; — Highlight the potential for environmental impacts, whether positive or negative; and — To inform and provide the public with information and an understanding of the proposed amendments, issues and solutions

7.2 WHAT IS AN INTERESTED AND AFFECTED PARTY?

An I&AP is defined as any person, group of persons or organisations interested in or affected by an activity, and any organ of state that may have jurisdiction over any aspect of the activity. — The difference between an I&AP and a registered I&AP: — An I&AP can be directly or indirectly impacted on by a proposed activity. — A registered I&AP is a person whose name has been placed on the register of registered I&APs. According to the PPP Guidance document, 2017, only registered I&APs will be notified: — Of the availability of reports and other written submissions made to the Competent Authority (CA) by the Applicant; and — Of the outcome of the application, the reasons for the decision, and that an appeal may be lodged against a decision. For the purpose of this report, registered I&APs will be referred to as Stakeholders.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 72 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

7.2.1 RIGHTS, ROLES AND RESPONSIBILITIES OF THE STAKEHOLDER

In terms of Chapter 6, specifically Section 43(1) of the NEMA EIA Regulations 2014, as amended, registered stakeholders have the right to bring to the attention of the CA any issues that they believe may be of significance to the consideration of the application. The rights of stakeholder are qualified by certain obligations, namely: — Stakeholders must ensure that their comments are submitted within the timeframes that have been approved by the Department of Environmental Affairs (DEA), or within any extension of a timeframe agreed by the Proponent, Environmental Assessment Practitioner (EAP) or CA; — Disclose to the EAP any direct business, financial, personal or other interest that they might have in the approval or refusal of the application; — The roles of stakeholders in a public participation process usually include one or more of the following: — Assisting in the identification and prioritisation of issues that need to be investigated; — Making suggestions on alternatives and means of preventing, minimising and managing negative impacts and enhancing Proposed Project benefits; — Assisting in or commenting on the development of mutually acceptable criteria for the evaluation of decision options; — Contributing information on public needs, values and expectations; — Contributing local and traditional knowledge; and — Verifying that their issues have been considered. In order to participate effectively, stakeholders should: — Become involved in the process as early as possible; — Register as a stakeholder; — Advise the EAP of other stakeholders who should be consulted; — Contribute towards the design of the public participation process (including timeframes) to ensure that it is acceptable to all stakeholders; — Follow the process once it has been concluded; — Read the material provided and actively seek to understand the issues involved; — Give timeous responses to correspondence; — Be respectful and courteous towards other stakeholders; — Refrain from making subjective, unfounded or ill-informed statements; and — Recognise that the process is confined to issues that are directly relevant to the application.

7.3 STAKEHOLDER IDENTIFICATION

Section 41 of the 2017 EIA Regulations states that written notices must be given to identified stakeholders as outlined in Table 7-1. The stakeholder database is included in Appendix J4. Relevant authorities (Organs of State) have been automatically registered as I&APs. In accordance with the EIA Regulations, 2014 (as amended), all other persons must request in writing to be placed on the register, submit written comments or attend meetings in order to be registered as stakeholders and included in future communication regarding the project. Table 7-1: Interested and Affected Parties Table

NEMA REQUIREMENT DISCUSSION All landowners within the project area were notified of the (i) the owner or person in control of that land if the applicant is not the owner or person in control of the amendment process via email and sms. land

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 73 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

NEMA REQUIREMENT DISCUSSION

(ii) the occupiers of the site where the activity is or is to All landowners and as well as the personnel indicated on the original be undertaken or to any alternative site where the I&AP database will be notified of the proposed amendment. activity is to be undertaken

(iii) owners and occupiers of land adjacent to the site Adjacent landowner and occupier details were collected and the where the activity is or is to be undertaken or to any landowners were notified via a project notification letter via email alternative site where the activity is to be undertaken and/or sms notification.

(iv) the municipal councillor of the ward in which the The Ward Councillor (From Ward 1 Thabazimbi Municipality) has site or alternative site is situated and any organisation been included on the stakeholder database. of ratepayers that represent the community in the area

(v) the municipality which has jurisdiction in the area The Thabazimbi Local Municipality has been included on the stakeholder database.

(vi) any organ of state having jurisdiction in respect of The Department of Mineral Resources has been consulted as the any aspect of the activity competent authority.

(vii) any other party as required by the competent All tiers of government, namely, national, provincial, local authority. government and parastatals have been included on the stakeholder database. Inclusive of: — Department of Energy — Department of Agriculture, Forestry and Fisheries — Department of Rural Development and Land Reform — Department of Water and Sanitation — Department of Mineral Resources — Limpopo Department of Public Works, Roads and Infrastructure — Department of Economic Development, Environment and Tourism Limpopo — National Energy Regulator South Africa — Eskom — Waterberg District Municipality — Thabazimbi Local Municipality — Limpopo Heritage Resources Authority

7.4 STAKEHOLDER ENGAGEMENT PLAN

The stakeholder engagement plan is outlined in Table 7-2. Table 7-2: Stakeholder Engagement Plan

CURRENT NO. ITEMS STATUS DESCRIPTION

1 A newspaper advert in Completed WSP will place adverts in The Platinum weekly Newspaper (English) and a local newspapers Die Kwêvoël (Afrikaans & English). informing the public of A copy of the advert is contained in Appendix J1. Proof of placement of the proposed the advert has been included in Appendix J1. amendments and

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 74 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

CURRENT NO. ITEMS STATUS DESCRIPTION requesting public input.

2 On-site notices placed Completed Site notices will be placed around the sites and at nearby and accessible at strategic locations. public areas A copy of the site notice is contained in Appendix J2. Proof of placement has been included in Table 7-3 and Table 7-4.

3 Notification letters Completed Notification letters were distributed to stakeholders via email and post. In will be distributed addition stakeholders were notified via sms. (emailed and faxed) to A copy of the notification letter is contained in Appendix J3. Proof of the existing area distribution has been included in Appendix J3. stakeholder database.

4 The Draft Report was Completed The reports will be distributed to the public venues for review and are delivered to the available from 13 September to 14 October 2019. Northam Public Additionally, an electronic version of the report was placed on the client’s Library & Thabazimbi website to be accessed by the public at the following link: Public Library for https://www.wsp.com/en-ZA/services/public-documents public and stakeholder review. The Draft Report was made available on the WSP website.

5 The notices described Completed Notification letters were be distributed to stakeholders (including ward above included the councillors) via email and post. In addition stakeholders will be notified Draft Report via sms. availability A copy of the notification letter is contained in Appendix J3. Proof of date/venues. distribution has been included in Appendix J3.

6 All stakeholder Completed No significant comments were received during the public review period. comments will be used Correspondence received has been included in Table 7-6 below. to update the Draft Report before DEA submission.

7 Submission and To be Completed The DEA is normally allocated 107 days to review the Final Decision-Making Environmental Authorisation Amendment Assessment Report. The DEA must therefore within this timeframe issue a decision on the application for amendment. All I&APs will be notified of the submission of the Final Report to the DEA.

9 EA Not yet applicable Notify registered I&APs of the amended decision and their right to appeal.

7.5 PROOF OF ENGAGEMENT

During the 30-day public review period, site notices and reports were put up at different locations as follows: — Site and General Notice Locations (Figure 7-1); — Proof of Site Notice Placement (Table 7-3); — Proof of General Project Notice Placement (Table 7-4); and — Public Review Locations (Table 7-5).

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 75 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Figure 7-1: Site and General Project Notice Locations

Table 7-3: Proof of Site Notice Placement

LOCATION PROOF OF PLACEMENT

Dishaba – Vent Shaft Locations 24°45'40.53"S 27°23'40.80"E

Dishaba Main Office 24°45'35.72"S 27°23'21.15"E

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 76 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

LOCATION PROOF OF PLACEMENT

Tumela - Taxi Rank 24°49'24.47"S 27°17'1.96"E

Tumela Mine Office 24°49'33.65"S 27°17'28.81"E

Table 7-4: Proof of General Project Notice Placement

LOCATION PROOF OF PLACEMENT

Amandelbult Recreation Club

Choppies Supermarket

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 77 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

LOCATION PROOF OF PLACEMENT

Northam Business Centre

Northam Public Library

Nortnam Shoprite Centre

Thabazimbi - Shoprite

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 78 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

LOCATION PROOF OF PLACEMENT

Thabazimbi - Thaba Mall

Thabazimbi Municipality library

Thabazimbi Post Office

Traditional Authority Office

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 79 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 7-5: Public Review Locations of the Draft Assessment Report

LOCATION PROOF OF PLACEMENT

Thabazimbi Municipality library

Traditional Authority Office

Dishaba Main Office

Tumela Mine Office

7.6 COMMENTS AND RESPONSES

Comments received from registered stakeholders have been captured and responded to within the comments and response table (Table 7-6). The original comments and responses are included in Appendix J5.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 80 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

Table 7-6: Comment and Responses Table

STAKEHOLDER REPORT DETAILS COMMENT RESPONSE REFERENCE

Department of Water This office acknowledges the receipt of WSP have noted the Appendix J5 and Sanitation your documents regards to the above- correspondence. mentioned on 14 October 2019 (Task Ms C Theunissen T491/2019). The office responsible for this Chief Admin Clerk area is: Ms Lethabo Ramashala and can be contacted at (012) 392-1470. Date: 14 October 2019 Comments would be forwarded in due time. Email with Letter Attachement

Limpopo Department RE: COMMENTS ON THE WSP have noted the Appendix J5 Economic CONSULTATION OF DRAFT correspondence and that here Development, ASSESSMENT REPORT FOR THE are no comments from the Environmental and PROPOSED CONSTRUCTION OF TWO Department. Tourism NEW VENTILATION SHAFTS AND ASSOCIATED INFRASTRUCTURE AS Mr MolePo M WELL AS THE UPGRADING OF AN Date: 15 October 2019 EXISTING BUS AND TAXI TERMINAL AT THE RUSTENBURG PLATINUM Email with Letter MINE (AMANDELBULT SECTION)' Attachment LTMPOPO PROVINCE

The copy of Draft Assessment Report with regard to the above mentioned received by the Department on '18 September 2019 refers. The Department does not have comments on the proposed developments at the Rustenburg Platinum Mine (Amandelbult Section). Please do not hesitate to contact this Department should have any queries in this respect.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 81 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

8 CONCLUSION

This Final Amendment Report is submitted in support of the application for amendment of the EMPR issued to Amandelbult Complex for the operation of the Dishaba and Tumela Mines in the Limpopo Province. The proposed amendments do not trigger any of the NEMA listed activities but constitute a change of scope and as such, a Part 2 Amendment Process in terms of Regulation 31 of the EIA Regulations (2014) is required. WSP was appointed to undertake the amendment process in terms of Regulation 31 and 32 of the EIA Regulations (2014), as amended. In addition, various specialists were appointed to assess the proposed amendments to the EA. This assessment report provides a description of the proposed additional developments that AAP:RPM wishes to undertake, and details the aspects associated with the construction and operation. A detailed description on the existing and receiving environment (bio-physical as well as socio-economic) is provided based on findings from the specialist surveys and existing information. Stakeholder engagement was undertaken from the onset of the project in a transparent and comprehensive manner. The public were engaged through provision of the Draft Assessment Report, so as to afford all Interested and Affected Parties an opportunity to input on the proposed development. Outcomes of all comments received from the public review period have been recorded and responded to in the final Assessment Report. Based on the environmental description, specialist surveys as well as the stakeholder engagement, a detailed impact assessment was undertaken and, where relevant, the necessary management measures have been recommended. In summary, the assessment assessed both biophysical and socio-economic environments and identified appropriate management and mitigation measures. Primary impacts on the receiving environment identified through the assessment are summarised below: — Further habitat fragmentation by the proposed ventilation shafts surface infrastructure impacting on the remaining faunal life in the project area, as well as the electrocution of vultures buy the proposed OHLs. — The removal of indigenous trees (i.e. Vachellia tortilis and a Searsia spp) from the existing informal bus and taxi terminal to accommodate the new terminal infrastructure — Impact on the identified wetlands near Dishaba Mine, by the ventilation shafts and their associated infrastructure (particularly the proposed powerline and access route to the downcast ventilator shaft). — Minor changes in the surface flow regime caused by the alignment of access roads to the ventilation shafts — Very little contamination of surface (Crocodile and Bierspruit Rivers) and groundwater resources from potential oil and hydrocarbon spills — Generation and emission of dust and noise during the construction activities of both the ventilation shafts and bus and taxi terminal Worthy of noting, is that the proposed project areas have already undergone significant transformation due to the surrounding mining, agricultural and human activities and as such, the extent and magnitude of most of the proposed activities’ impacts on the actual natural environment are minor. Furthermore, it should be noted that the majority of the impacts are associated with construction activities, which are temporary and will cease after the construction phase. If implemented effectively and timeously, the management and mitigative measures will significantly reduce and eliminate some of the identified impacts. It is important that the socio-economic impacts of the proposed projects are assessed within the context of improving efficiency and productivity at the mine for the remaining 33 years of the life of mine. These initiatives will also improve worker health and safety. The construction/establishment phase of the developments will create significant socio-economic opportunities associated with the capital expenditure of between R 1.9 and 2.6 billion and also create employment opportunities. The biophysical impact assessment revealed that there are no environmental fatal flaws and no significant negative impacts associated with the proposed project should mitigation and management measures be implemented. In addition, it should be noted that the socio-economic impacts associated with the project are positive .These proposed developments will contribute significantly to the overall productivity (and therefore future) and safety of Amandelbult.

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 82 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

BIBLIOGRAPHY

— ADU (Animal Demography Unit). (2017). Virtual Museum. (Accessed: Feb 2018). — Golder (2018). Updated Amandelbult Groundwater Modelling Report - Draft for client review - Rev 1; — Groundwater Complete (October 2011). Report on geohydrological investigation as part of the Integrated Water Use Licence Application. Riversdal; Groundwater Complete, 2011). — IUCN (2017). The IUCN Red List of Threatened Species. www.iucnredlist.org (Accessed: November 2017). — Mucina, L. and Rutherford, M.C. (Eds.). (2006). The vegetation of South Africa, Lesotho and Swaziland. Strelizia 19. South African National Biodiversity Institute, Pretoria South African. — MSA Group, Final Rehabilitation, Decommissioning and Mine Closure Plan in support of Anglo-American Platinum Proposed Ventilation Shafts at Amandelbult Mine — SRK Consulting (2018). Anglo American Platinum Amandelbult Section IWWMP Update, Report Number 52811/IWWMP_2018. — SRK (2018). Amandelbult Complex - Final Rehabilitation, Decommissioning and Mine Closure Plan – 2018; — SRK (2019). Anglo American Platinum Amandelbult Section Integrated Water & Waste Management Plan Update, 2018; — WSP (2019). Amandelbult modernization project: Hydrological Impact Assessment — WSP (2019). Amandelbult modernization project soils and land use update report. — WSP (2019).Amandelbult modernization project: Hydrogeological assessment — WSP(2019) Amandelbult modernization project: Wetland Impact Assessment

PROPOSED CONSTRUCTION OF TWO NEW VENTILATION SHAFTS AND ASSOCIATED WSP INFRASTRUCTURE AS WELL AS THE UPGRADING OF AN EXISTING BUS AND TAXI TERMINAL AT November 2019 THE RUSTENBURG PLATINUM MINE (AMANDELBULT SECTION), LIMPOPO PROVINCE Page 83 Project No. 41101879 ANGLO AMERICAN PLATINUM LIMITED: RUSTENBURG PLATINUM MINES

APPENDIX

A PRE-APPLICATION MEETING

APPENDIX

B BIODIVERSITY BASELINE ASSESSMENT

APPENDIX

C WETLAND IMPACT ASSESSMENT

APPENDIX

D SOCIAL IMPACT ASSESMENT

APPENDIX

E HERITAGE IMPACT ASSESSMENT: LETTER OF EXEMPTION

APPENDIX

F SOILS AND LAND USE ASSESSMENT

APPENDIX

G HYDROLOGICAL IMPACT ASSESSMENT

APPENDIX

H HYDROGEOLOGICAL ASSESSMENT

APPENDIX

I DECOMISSIONING AND MINE CLOSURE PLAN

APPENDIX

J STAKEHOLDER ENGAGEMENT

APPENDIX

J-1 ADVERTISEMENT

APPENDIX

J-2 SITE NOTICE

APPENDIX

J-3 NOTIFICATION LETTER

APPENDIX

J-4 STAKEHOLDER DATABASE

APPENDIX

J-5 COMMENTS RECEIVED

APPENDIX

K TUMELA BUS AND TAXI TERMINAL IMPACT SIGNIFICANCE RATING

APPENDIX

L TUMELA BUS AND TAXI TERMINAL LAYOUT PLAN