Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready The first 6 phases comprise 11.48‐ Castanea Rail Station to miles, from Chestnut Park in intersection with Youngdale Castanea Township to the River Road, Youngdale Rd to Source: Clinton Co Road bridge in Pine Creek Township. Lock Haven, Castanea McKinney Rd, MicKinney Rd Comp Plan 2014; Pg. Connecting to Lycoming County. Township, Wayne to Spook Hollow Road, 101‐109 Two spurs, connecting the City of Township, McElhattan, Spook Hollow Rd to Valley Partners: Clinton and CL‐1a High X Lock Haven and the Borough of Avis, Clinton Pine Creek Township, Railroad Bridge Crossing, Planning Phase 1 and 2 completed. Trail Lycoming Counties, will become a future 7th phase. Avis, into Porter Railroad Bridge to River Rd, Wayne, Pine Creek Lycoming County will develop the Township and Jersey River Rd to DCNR and Castanea connection to the Jersey Shore Shore Lycoming County Tiadaghton Elm Site. Townships trailhead of the Pine Creek . Clinton County portion (Pine Creek Trail Connector ends at Pine Creek: steel Feasibility Study) bridge to Lycoming County.

From parking lot at Phase 2 terminus, Source: Clinton Co Design awarded to Connect Wayne Township through Wayne Bald Eagle Valley Comp Plan 2014. engineer; ROW being Community Park to the terminus of Township Park, along CL‐1b Trail, Phase High X Clinton Planning Partners: Clinton obtained; construction Phase 2 (and thereby the Castanea McKinney Road 3=Wayne Township County, Wayne funding to be sought trailhead). (shared road design) to Township. through grants. connecting to Phase 1 parking lot.

Source: Clinton Co Bald Eagle Valley Phase 5 comes off the Susquehanna Comp Plan 2014. Trail, phase 5=WE crossing and follows River Road CL‐1d High X Clinton Pine Creek Township Planning Partners: Clinton In design, survey stage. Susq River bridge to through Pine Creek Township; County, Pine Creek Pine Creek Trailhead shared road design. Township.

Source: Clinton Co Construction funding Comp Plan 2014 awarded from PennDOT Convert 860‐foot abandoned Crossing the Bald Eagle Valley Partners: Clinton TAP grant. Design grant railroad bridge for bike‐ped use, and Susquehanna between CL‐1c Trail, phase 4=bridge High X Clinton Design County, Wayne and awarded from DCNR C2P2 construct two access ramps to Wayne and Pine Creek over WB Susq River Pine Creek Townships, Grant. Scheduled bid let bridge. Townships Wayne Township 2020; construction Landfill Authority. completion 2021.

1 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Add a short length of trail and ramp Source: Clinton Co Project desgin by County Bald Eagle Valley to connect Castanea trailhead to Comp Plan 2014 staff and permits in hand; CL‐1e Trail, phase 6=Lock High X Jarrett Avenue, which leads to Clinton Castanea Township Concept Partners: Castanea construction funding Haven connector Chestnut Park and City of Lock Township sought. Haven

Restoring a historic Susquehanna riverwalk from the Flaming Foliage Source: Renovo Access to the 5th Street Access. Will Borough and PRR Renovo Riverwalk incorporate the 5th street park group; Pg. 111‐116 CL‐2 Med X Clinton Renovo Planning Peer grant study in process Restoration picnic area and boat launch Partner: Susquehanna completed 2018. (Proposed County Greenway Greenway & Multi‐Modal Trails Partnership. Network) A safe, bikeable connection between Mill Hall Borough, Bald Eagle Township (Central Mountain High School Campus) along Hogan Boulevard through Flemington Mill Hall, Bald Eagle Source: Clinton Hogan Boulevard Borough into Lock Haven City. This is Pursue a grant for a Feasibility needs to be CL‐7 Low X Clinton Township, Flemington, Concept County Planning Safe Bike Route designated as Bike feasibility study. determined. Lock Haven Department Route G but should be developed into a Class 2 Bikeway with portions that could be Class 1. Proposed in 2017 by Mill Hall residents who use this route and find it dangerous Pedestrian Crossings, Source: Lock Haven Intersection of Jay Street (SR 120) This is a priority safety area CL‐8 Jay Street @ Main High X Clinton Lock Haven Planning Walkable Com Planning in Progress and E. Main Street (SR 150). for pedestrian crossings Street Program; Pg. 9

2 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Pedestrian Crossings, Source: Lock Haven Intersection of Water Street (SR This is a priority safety area CL‐9 Water Street @ High X Clinton Lock Haven Planning Walkable Com Planning in Progress 120) and Grove Street. for pedestrian crossings Grove Street Program; Pg. 9

Pedestrian Crossings, Source: Lock Haven Intersection of Mill Street and E. This is a priority safety area CL‐10 Mill Street @ E. Main High X Clinton Lock Haven Planning Walkable Com Planning in Progress Main Street (SR 150). for pedestrian crossings Street Program; Pg. 9

Pedestrian Crossings, Source: Lock Haven Intersection of 4th Street and W. This is a priority safety area CL‐11 4th Street @ W. High X Clinton Lock Haven Planning Walkable Com Planning in Progress Church Street. for pedestrian crossings Church Street Program; Pg. 9 Pedestrian Crossings, Source: Lock Haven This is a priority safety area CL‐12 Fairview Street High X Fairview Street (SR 1024) Corridor. Clinton Lock Haven Planning Walkable Com Planning in Progress for pedestrian crossings Corridor Program; Pg. 9 Future trail project ‐ will Source: Don't know ‐ Lamar Township, connect Lycoming County not the city. Brian Bald Eagle and White On Bald Eagle and White Deer CL‐14 Low X Clinton Wayne Township, and Clinton via Mid‐State Concept Auman wants to Concept Deer Ridge Trail Ridges Crawford Township Trail and Bald Eagle Valley extend the Summit Trail. trail Develop a city wide trail/bicycle Lock Haven Citywide (bike‐ped) network in 2009/2010; no plans underway at this Source: Lock Haven CL‐15 Trail/Bicycle Med X X Develop a recreation and parks Clinton Lock Haven Concept concept time Comp Plan; Pg. 109 Network facilities management plan in 2007/2008.

This project will be done by Woodward PennDOT in conjunction Township has submitted Connect Riverview Park to the City CL‐16 Township Riverview High X Clinton Woodward Township with scheduled Shovel Ready Source: PennDOT grant request to PennDOT of Lock Haven via Jay St Bridge. Park Connector Farrandsville Road Multimodal improvements.

Source: Renovo Borough and PRR Create a safe passage for residents East/West Renovo group. Partner: CL‐17 Low X to walk between downtown Renovo Clinton Renovo Concept Walking Connector Susquehanna and the East Renovo neighborhood. Greenway Partnership.

3 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Pedestrian and wheelchair riders Source: Clinton Hogan Blvd Safety have been struck by vehicles here ‐ County Planning CL‐18 project near Bald Low X Clinton Flemington Borough Concept sidewalk widening or off‐ street trail Department; Partner: Eagle Creek Bridge is needed. High traffic area. Flemington Borough

Unpaved rd that is Source: Clinton Pave the only graveled stretch of frequently used. Pine Loganton Rd County Planning CL‐19 Low X this road. Cyclists and motorists Clinton Crawford Township Improvement would Concept Improvement Department; Partner: often request this. benefit motorists and Crawford Township bicyclists.

4 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Links the Village of Rupert to the area north of Bloomsburg where the former Bloomsburg, Berwick and Sullivan Railroad intersects Iron Street. The trail is 4 +/‐ miles long and future initiatives could preliminary planning, extend the trail further both The Columbia County north and south. The trail crosses Susquehanna River trail Fishing Creek via the Rupert is EXISTING from the Abandoned railroad bed Extend Columbia Covered Bridge and provides Village of Rupert to the is privately owned. Source: Columbia Co County Susquehanna direct acces to Fort McClure Town of Bloomsburg. Town of Bloomsburg, Narrow shoulders under Comp Rec, Park, CO‐1 Trail, Iron Street to High X Boulevard a joint use public road Columbia Planning Preliminary Planning has Scott Township over‐pass. Greenways, and Open Kocher Park that is part of the Columbia been done to extend the Easements or right‐of‐ Space Plan; Pg. 4‐15 (Lightstreet village) County Susquehanna Trail. This trail north to the Village ways may be required. trail development project was of Lightstreet. The spur funded by DCNR and a federal T‐ to the Huffman Natural 21 grants. There is a possibility of area is in the Concept expansion of this trail from its phase end to Kocher Park in the village of Lightstreet, Scott Township via the abandoned railroad bed and to the Hoffman Natural Area via SR 42.

5 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

This 21 acre parcel of land was acquired by Columbia County in 2009. It is located on SR 42 in the Town of Bloomsburg at the old Magee Transportation Park and more recently owned by William and Shirely Hoffman. The site provides extensive access to Trail to link Hoffman Fishing Creek for boating and Narrow shoulders under Source: Columbia Co Hoffman Natural Area is Natural Area to fishing. The area also has an Interstate 80 over‐pass. Comp Rec, Park, Existing. The link to the CO‐2 Steve Shannon Path High X Columbia Bloomsburg Concept approximately .75‐mile trail loop. Easements or Right‐of‐ Greenways, and Open Susquehanna River Trail (Columbia Co Space Plan Susquehanna Trail) There is easy acces parking south Way may be required. is a concept. of the Green Iron Bridge along SR 42. Signage is provided. The site is also approximately .25‐miles from the intersection of the Columbia County Susquehanna River Trail and SR 42 at the Shannon Tire Company. There is opportunity to link the sites.

This 138‐acre parcel is located in Montour Township, Columbia Columbia County is County. The North Branch Canal working with the Grove‐ Trail runs directly throught the Rishel Estate and the Source: Columbia Co middle of the property providing Northcentral COMPLETED‐ Grove‐ Comp Rec, Park, CO‐3 High X access from the east and west. Columbia Montour Township Conservancy to acquire Planning Planning in Progress Rishel Natural Area Greenways, and Open The property also provides the property and fulfill Space Plan extensive access to the the late owner's wishes Susquehanna River. The Estate of providing a natural requires the property to be kept area. in it's "natural" state.

6 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Berwick Dog Park Develop a trail that loops around Committee is working the lake. Provide deciduous with Columbia County to shade trees in open areas. Allow Source: Columbia Co Briar Creek Lake build a dog park at the Comp Rec, Park, meadow grasses to grow Brian Creek CO‐4 County Park trail Med X Columbia lake. Additionally, Concept Greenways, and Open Concept adjacent to the lake to deter Township, Berwick loop/ enhancements Berwick High School Space Plan; Pg. 3‐10 geese. Develop a master plan to cross country course runs through 3‐13 illustrate how these ideas can be around the lake ‐ a incorporated into the park site. potential partnership?

Key opportunities include Source: Columbia Co providing river access, extend a Comp Rec, Park, Bloomsburg Town CO‐5 Low X trail along the river, and develop Columbia Bloomsburg Concept Greenways, and Open Concept Park enhancements trails for accessibility and Space Plan; Pg. 3‐10 recreation. through 3‐13

Source: Columbia Co Develop walkways to provide Comp Rec, Park, Millville Community CO‐6 Low X accessible routes to recreation Columbia Millville Concept Greenways, and Open Concept Park walkways facilities and activity areas. Space Plan; Pg. 3‐10 through 3‐13

Source: Columbia Co Abandoned railroad line that has Inventory Study of B&S and SB &B CO‐7 Low X the potential of becoming a rail Columbia location? Concept Potential Concept Railroads Rail Trail trail. Trail/Greenway Opp. 1999; Pg. 6

Reading and Source: Columbia Co Pennsylvania Abandoned railroad line that has Inventory Study of CO‐8 Railroads Rail Trail, Low X the potential of becoming a rail Columbia location? Concept Potential Concept in both north and trail. Trail/Greenway Opp. south directions 1999; Pg. 6

7 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready The Railroad is somewhat Source: Columbia Co Abandoned railroad line that has parallel to SR 54 Inventory Study of Lehigh Valley CO‐9 Low X the potential of becoming a rail Columbia through Centralia Concept Potential Concept Railroad Rail Trail trail. between Trail/Greenway Opp. Northumberland and 1999; Pg. 6 Schuylkill County

Source: Columbia Co There is an active Abandoned railroad line that has Inventory Study of Conrail Railroad Rail Conrail line parallel to CO‐10 Low X the potential of becoming a rail Columbia Concept Potential Concept Trail the south bank of the trail. Trail/Greenway Opp. Susquehanna River 1999; Pg. 6

Maintain and expand bicycle and Source: Bloom Comp Maintain and expand Plan/Blueprint for ped infrastructure to link Bloomsburg Bicycle Bloom, 2009, pages 4‐ CO‐11 High X residential area, the downown, Columbia Bloomsburg Under Construction In Progress and Pedestrian 7 to 4‐9, the University , the Hospital, and Infrastructure Recommendation other activey centers. P.10. Source: Bloom Comp Country Club Drive Explore options to make Country Plan/Blueprint for and Lightstreet Road Club Drive and Lightstreet Road Bloom, 2009, pages 5‐ CO‐12 High X Columbia Bloomsburg Under Construction In Progress Bicycle/Pedestrian areas of Town more accessible by 8 to 5‐10, Accessibility foot or bicycle. Recommendation L.21.

Source: Bloom Comp Interconnect neighborhood Bloomsburg Trail Plan/Blueprint for CO‐13 High X destinations with trails within Columbia Bloomsburg Concept Concept Connections Bloom, 2009, page 8‐ and beyond the Town. 1, Goal 6.

Add walking/biking paths along Source: Bloom Comp Fort McClure Fort McClure Blvd from the Plan/Blueprint for CO‐14 Boulevard Walk/Bike High X Airport to the Rupert Bridge and Columbia Bloomsburg Concept Bloom, 2009, page 8‐ Concept Paths ideally up around to the 4, Recommendation Fairgrounds. R.3.

8 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Construct a walking path from Bloomsburg between SR 11 and Source: Bloom Comp Walking path from 5th Street Hollow Rd eastward, Plan/Blueprint for CO‐15 Bloomsburg to Low X more or less following property Columbia Bloomsburg Concept Bloom, 2009, page 5‐ Concept Central Road lines, to Central Rd in the Zeisloft 9, Recommendation development, ending at the AAA L.20. office.

Source: Bloom Comp 5th Street/Hollow Explore options to make the Plan/Blueprint for Road development at the top of 5th Bloomsburg, Scott CO‐16 Low X Columbia Concept Bloom, 2009, page 5‐ Concept Bicycle/Pedestrian Street Hollow Rd (at Central Rd) Township 9, Recommendation Accessibility accessible by foot/bike. L.22. Make the southeastern part of Source: Bloom Comp 7th Street Extension Town (7th street extension) Plan/Blueprint for Bicycle/Pedestrian friendlier to pedestrians and CO‐17 Low X Columbia Bloomsburg Concept Bloom, 2009, page 5‐ Concept Accessibility and link more clearly linked to the rest of 10, Recommendation to rest of town Town, perhaps through L.23. sidewalks.

Explore options to make the Source: Bloom Comp Iron Street Plan/Blueprint for Sunview Terrace and Arbutus CO‐18 Bicycle/Pedestrian Low X Columbia Bloomsburg Concept Bloom, 2009, page 5‐ Concept Park developments accessible by Accessibility 10, Recommendation foot or bicycle to the downtown. L.24. Install new curbs and sidewalks Source: Bloom Comp Children's Museum to provide better access for Plan/Blueprint for CO‐19 Bicycle/Pedestrian Low X pedestrians at the Children’s Columbia Bloomsburg Concept Bloom, 2009, page 7‐ Concept Accessibility Museum (front sidewalks 9, Recommendation completed). LL.15. Main Street & Main Street (SR 0011) & Source: Walkable CO‐20 Lightstreet Road High X Lightstreet Road (SR 0487) / East Columbia Bloomsburg Concept Comm Program, page Concept pedestrian safety Street (SR 0011). 9, #2 Lightstreet Road Lightstreet Road (SR 0487) Source: Walkable CO‐21 corridor pedestrian Med X Corridor between North Street & Columbia Bloomsburg Concept Comm Program, page Concept safety North Penn Street. 9, #3 East Street & Fifth Source: Walkable East Street (SR 0011) & Fifth CO‐22 Street pedestrian Med X Columbia Bloomsburg Concept Comm Program, page Concept Street. safety 9, #4 Midblock Crossing on Market Source: Walkable Market Street Mid‐ CO‐23 Low X Street between Main Street (SR Columbia Bloomsburg Concept Comm Program, page Concept block Crossing 0011) & Pine Ave. 9, #1

9 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Fort McClure Source: Bloom Town to connect Streater Park and the CO‐24 Boulevard Riverfront High X Columbia Bloomsburg Concept Park Master Site Plan Concept Town Park. Trail 2008; Pg. 37

Pedestrian Improvements/Loop Source: Bloom Town Bloomsburg Town CO‐25 Med X Trail around the perimeter of the Columbia Bloomsburg Concept Park Master Site Plan Concept Park Loop Trail entire park. 2008; Pg. 37

Source: Berwick Town Berwick River Trails; Potential Landing and An approximately five‐acre site Sponsor: CO‐26 trailhead at old RR High X where the historic Berwick Columbia Berwick Planning Planning in Progress Susquehanna station with River railroad station is located. Greenway access Partnership; Pg. 5.6 Columbia County Housing Safe Routes to School and Teen Authority (CCHS) awaiting a Center ‐ The Berwick Area High proposal for a traffic study Berwick Area Safe School, Middle SchooL and in Berwick's West End to Source: Berwick Town CO‐27 High X Columbia Berwick Concept Routes to School Nescopeck, Salem, 14th Street alleviate traffic concerns for Trails; Pg. 5.10 and Orange Street Elementary students and residents near Schools. West Berwick Elementary School

CCHC is considering Hometown Streets ‐ Elm Street applying for an Elm Street and Main Street – Streetscape planning grant with Wells X Enhancements. The network of Fargo in September to Elm Street and Main Source: Berwick Town CO‐28 High street state and local roadways in and Columbia Berwick target Mulberry Street. Concept Street Streetscapes Trails; Pg. 5.12 scape around the downtown business Front Street is a top priority district and the designated Elm for the Downtown Berwick Street neighborhood. Enhancement Committee, including traffic calming. Test Track Park and BIDA Has undergone Riverfront Property ‐ The Berwick significant cleanup and Borough‐owned Test Track Park addition of various Test Track Park and the BIDA‐owned riverfront Source: Berwick Town CO‐29 Med X Columbia Berwick amenities. Could be great Concept Playground property is approximately 100 Trails; Pg. 5.1 target for Pennsylvania acres in size, and consists of Municipal League flood plain forest and natural playground program areas.

10 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Major hurdle is SEDA Rail There is a nearly 1.5‐mile right of way below corridor of Berwick riverfront Susquehanna Avenue ‐ Railroad Riverfront Source: Berwick Town CO‐30 Med X occupied by an active railroad Columbia Berwick too narrow to meet their Concept Corridor & Riverwalk Trails; Pg. 5.4 line and steep, forested river safety requirements for banks. trail. Optional route of alley on top of bank.

Berwick Area United Way is leading a series of Nescopeck roundtable discussions, and one of Approximately 0.7 of a mile the areas of interest has Nescopeck Connect separates between Berwick and been exploring the Source: Berwick Town CO‐31 Trail and Tribute Med X Downtown Nescopeck – with Columbia Berwick creation of a "tribute" Concept Trails; Pg. 5.8 Park most of that distance on the SR park to honor the once 93 highway bridge. famous Bernesco Park, in the flood plain areas at the entrance of the bridge on the Nescopeck side

The network of neighborhood A new position is being parks that offer close‐to‐home created to target town‐ Network of recreation. Neighborhood parks wide recreation and park Source: Berwick Town CO‐32 neighborhood Med X Columbia Berwick Concept include: Arbor Street Park, Louis usage. Talk to Ginny Trails; Pg. 5.14 Berwick Parks Stevens Park, Sponsler Park, St. Crake at Berwick United Charles Park, Vine Street Park. Way for info.

What are the best places to run X in the Berwick Area? What Berwick Running identify streets and roads offer safety, Source: Berwick Town CO‐33 Med Columbia Berwick Concept Routes existing scenery and a chance to get a Trails; Pg. 5.16 routes good running workout before returning home?

11 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Ber‐Vaughn Pool has Ber‐Vaughn Park Connection ‐ been working on Approximately 0.33 of a mile summertime bus Ber‐Vaughn Park separates the existing street transportation. Anything Source: Berwick Town CO‐34 Columbia Berwick Concept Connections network of Berwick’s west end connecting to Ber‐ Trails; Pg. 5.20 neighborhood and Ber‐Vaughn Vaughn should start with Park. a conversation with them.

Hiking, Mountain Biking and Trail Running ‐ The most well know resource is the PPL Susquehanna Riverlands and Council Cup owned by Pennsylvania Power and Light (PPL). Council Cup offers a scenic overlook of the Susquehanna River and the Riverland’s Wetlands Nature Area and Recreation Area on the X The region surrounding identify east shore. Other locations are Promote Destination Berwick offers some promoti the State Game Lands (SGL) 55, Source: Berwick Town CO‐35 Trails around Med Columbia region around Berwick excellent , Concept on 58 and 260 that surround the Trails; Pg. 5.26 Berwick mountain biking and trail opportu Berwick Area located both to the running opportunities nities south of the Susquehanna River (SGL 58) and to the north of Berwick near Lee and Huntington mountains. There is also an abandoned railroad corridor located near Mainville (southeast of Bloomsburg) that offers a scenic and level trail corridor. However this is not an ‘official’ trail.

Briar Creek Approximately 1.25‐miles Briar Creek Source: Berwick Town CO‐36 Lake/Bloomsburg Low X separates Berwick’s west end Columbia Concept Township/Bloomsburg Trails; Pg. 5.21 Connection Trail and Briar Creek Lake.

12 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Susquehanna Riverlands / Extend Susquehanna Warrior Trail ‐ Following the river Warrior Trail from ‐ there is approximately 6.3‐miles Source: Berwick Town CO‐37 Berwick to Low X between downtown Berwick and Columbia Berwick Concept Trails; Pg. 5.22 Susquehanna PPL Susquehanna Riverlands. The Riverlands direct distance between Berwick and Riverlands is 5.3‐miles.

Ped safety around Bloomsburg Town Town Park location in the vicinity Source: CO‐38 Park at Market Low X of Market Street & Ft. McClure Columbia Bloomsburg Concept (undocumented), Street & Fort Blvd. page 9, #5 McClure Blvd. X Identify Berwick Berwick Biking Routes CO‐39 High identify Berwick Biking Routes Columbia Berwick Concept Biking Routes ‐ Pg. 5.24 routes

On SEDA‐COG JRA ROW (southern portion only). Complete N Branch Canal Trail Extension of MARC trail. and delineate from open section Susquehanna NBCT, Catawissa to Owner of Campground in CO‐40 High X of NBCT to Bloomsburg Columbia Concept Greenway Bloomsburg litigation with JRA and Fairgrounds(same as proposed Partnership, MARC MARC, refuses to remove project) trailers from ROW. Reference M‐7 project.

NBCT, Bloomsburg Extension of N Branch on railroad Very Constructable. ROW to Berwick and access road from Bloomsburg to willing to cooperate. Susquehanna CO‐41 High X Columbia Concept Susquehanna Berwick, all the way to connect Includes Kayak river Greenway Partnership Warrior Trail to Susquehanna Warrior Trail access at train station

13 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Lead Agency ‐ Lycoming County PCD and Susquehanna Greenway Partnership/Other This project includes a 2.5 Partners‐ City of mile extension of the River Williamsport, Walk to connect to Pennsylvania College Planning in progress, at Susquehanna State Park, an of Technology, engineering stage. Funding Susquehanna River Susquehanna River Walk Extension access improvement at Lycoming College, has been obtained for L‐1 Walk Extension and High X Lycoming Williamsport area Planning and Access Improvements Basin Street, a connector Susquehanna Design only. Working to Connectors into Newberry, and a Economic secure funding for connector from Development construction in 2019. Susquehanna State park to Association, SEDA‐ South Reach Road COG Joint Rail Authority, Williamsport Sanitary Authority, USACE, PennDOT, DCNR, DCED

Lead Agency – Loyalsock Township / This is a four‐phase project Other Partners – by the Township that will Loyalsock Township connect the River Walk School District, Multi‐phase project. Phase Millers Run system to two township Diamond Pointe I and II is fully funded and L‐2 High X Millers Run Greenway Lycoming Loyalsock Township Planning Greenway parks, a senior center, Apartments, USACE, Phase 3 and 4 still need Loyalsock Township High PennDOT, PADEP, funding. School, and a high density Susquehanna residential area Greenway Partnership, Lycoming County PCD

14 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Future trail project ‐ in partnership with PA DCNR Bureau of Forestry and State Park. The Ridge Trail will be created by using existing trails and gravel roads, on state and water authority lands, to create a 50‐mile trail linking Muncy Source: Greater Armstrong Township, and Lock Haven. The Williamsport Alliance Feasability study for Washington Township, project is less of a trail Comp Plan Review project has been The Ridge Trail ‐ on Bald Eagle and Limestone Township, construction project and L‐3 Ridge Trail (AKA High X Lycoming Shovel Ready and Implement. completed by Brian White Deer Ridges [TRAIL ALSO GOES more of a marketing and Ridge Trail) Strategy 2017, SGP Auman. Funding needed INTO CLINTON rebranding program for the Visison. Sponsor: for design/construction. COUNTY] trail and recreational DCNR BOF resources that already exist. More implementable on state forest land, and paved Woodland Road. Extension to Sylvan Dell can be done. Big challenge is US 15 crossing (can be done with a bridge) Eastern part is good condition gravel.

15 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Lead Agency – Susquehanna Greenway Partnership SGP has secured partial / Other Partners – Montgomery Borough, funding for design. WBRA, Pennsylvania Clinton Township, Alignment determined, Montgomery to From Montgomery, Lycoming College of Technology, L‐4 Med X Lycoming Brady Twip, Gregg Norfolk Southern approval Planning Planning in progress Allenwood Rail Trail County to Allenwood, Union County County of Lycoming, Township [UNION is essential to proceed. County of Union, COUNTY] Candidate for G‐S Montgomery Greenway project. Borough, Clinton Township, Gregg Township

No lead sponsor identified. Possible partners ‐ Lycoming County, Hepburn Hepburn Township, Extension of Lycoming Creek Township, Lycoming Extend Lycoming Lycoming Township, L‐5 Low X Bikeway North from Hepburnville to Lycoming Future trail project Concept Township, Lewis Concept Creek Bikeway Lewis Township, Trout Run (and beyond) Township, Old McIntyre Township Lycoming Township, Loyalsock Township, Susquehanna Greenway Partnership

16 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

No lead sponsor identified. Possible partners ‐ Lycoming County, Montoursville Borough, Fairfield Montoursville Future trail project. Township, Muncy Connect Borough, Muncy Connection of Eastern Terminus of Feasibility study completed. Township, Muncy Susquehanna River Township, Muncy L‐6 Low X Susquehanna River Walk to Muncy Lycoming Candidate for Genesee Concept Creek Township, Concept Walk to Muncy Creek Township, Borough Susquehanna Greenway Muncy Borough, Borough Muncy Borough, Project. PennDOT, SEDA‐COG Fairfield Township Joint Rail Authority, Williamsport Regional Airport, Susquehanna Greenway Partnership, DCNR

No lead sponsor identified. Possible partners ‐ City of Williamsport, Lycoming County, City Woodward Township, Connect Connection of Western Terminus of of Williamsport, Feasibility study Piatt Township, Porter Susquehanna River Susquehanna River Walk and Woodward Township, completed. Candidate for Township, Jersey L‐7 High X Lycoming Planning Planning in progess Walk west to Jersey Southern Terminus of Pine Creek Piatt Township, Jersey Genesee Susquehanna Shore Borough, Shore Rail Trail in Jersey Shore Shore Borough, Porter Greenway Project. Lycoming County, Township PennDOT, DCNR, SEDA‐COG Joint Rail Authority, Lycoming County, Susquehanna Greenway Partnership

17 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Land acquisition of Sylvan Dell farm properties is top priority, and funding Lead Agency ‐ South request has been submitted Williamsport Borough, to PA DCNR, and South Williamsport Funding for land Armstrong Township, application being prepared Area School District, acquisition has been Sylvan Dell South Williamsport for NAWCA (North America Armstrong Township / L‐8a Med X Sylvan Dell Nature Park Lycoming Design secured. Acquisition of Conservation Project Borough Montoursville Wetland Conservation Act) Other partners ‐ land should take place in Borough grant through US Fish and Lycoming County 2019. Wildlife. Old Montgomery Potential Partner‐ Pike has been closed to Williamsport Area traffic and serves as trail Recreation Authority connector from neighborhood to the ridge.

Establish a trail connection Lead Agency ‐ South from Sylvan Dell Nature Williamsport Borough, Park up to Ridge Trail South Williamsport Sylvan Dell Armstrong Township, System. Old Montgomery Area School District, Conservation Ridge Establish trail connection to Ridge South Williamsport L‐8b Low X Lycoming Pike has been closed to Concept Armstrong Township / Trail Connector trail Borough Montoursville traffic and can serve as a Other partners ‐ Project Borough trail connector from the Lycoming County, Nature Park to the Bald Susquehanna Eagle Ridge Trail. Greenway Partnership

18 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

AKA Clinton County Rail Trail, Pine Creek Connector. Feasibility study completed. No lead sponsor Alignment for this identified. Possible Jersey Shore to Lock connection with the Clinton partners ‐ Jersey Haven connector Jersey Shore to Lock Haven Jersey Shore Borough County trial network via Shore Borough, Porter L‐9 trail (AKA Pine Creek High X connector trail (AKA Pine Creek Lycoming to Lock Haven (Clinton Seminary St. to Broad St. Planning Township, Clinton Planning in progress Connector, Clinton Connector, Clinton County Rail Trail) County) (or old PA Canal) to River County, Lycoming County Rail Trail) Rd. over Pine Creek steel County, Susquehanna truss in Porter Township. Greenway Candidate for Genesee Partnership, DCNR Susquehanna Greenway Project.

Bike/Pedestrian Trail to be located Montoursville on SEDA‐COG JRA ROW, consistent Borough, Muncy On SEDA‐COG JRA ROW, Montoursville to Muncy borough needs L‐10 Med X with JRA Policy and design Lycoming Township, Muncy consistent with JRA policy Muncy Trail a partner standards. Overlaps eastern portion Creek Township, and design standards. of L‐6 Muncy

Muncy to L‐11 Low X Trail linking Muncy to Montgomery Lycoming Muncy, Montgomery Concept Linkage study Montgomery Trail

Basin St. River Walk L‐12 Med X Lycoming Williamsport area Connector

19 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Implementation of the proposed Greenway System that includes linking critical natural resources via Montour County Cultural Heritage Source: Montour Co M‐1 Med X trails and corridors ‐ some progress Montour Montour County Planning planning in progress Greenway System Recommendations Comp Plan; Pg. 58 has been made, though several key connections remain to be completed. Encourage the linkage of existing linkage & trail local recreational facilities and Source: Montour Co M‐2 Med X Montour Montour County Planning planning in progress development encourage the development of new Comp Plan; Pg. 65 local trails and facilities. Master Plan, Susquehanna Susquehanna Recreation Plan Source: Montour Co M‐3 Med X Greenway Corridor and trails & Montour Danville Planning planning in progress Riverfront Park Implementation Comp Plan; Pg. 66 recreation/water access. Several other greenway corridors – X including Old Iron Ore, Reading Rail, Montour County greenw Montour Ridge, Rail with Trail, Source: Montour Co some existing; some in M‐4a Greenway System ‐ Low ay Montour Montour County Planning Scenic Bikeway, Ribbons of Green & Comp Plan; Pg. 5 planning; others concept Old Iron Ore corridor Chillisquaque Creek Corridors that s together unify County recreation.

Several other greenway corridors – including Old Iron Ore, Reading Rail, Montour County Montour Ridge, Rail with Trail, Source: Montour Co some existing; some in M‐4b Greenway System ‐ Low X Montour Montour County Planning Scenic Bikeway, Ribbons of Green & Comp Plan; Pg. 5 planning; others concept Reading Rail Chillisquaque Creek Corridors that together unify County recreation.

Several other greenway corridors – X including Old Iron Ore, Reading Rail, Montour County greenw Montour Ridge, Rail with Trail, Source: Montour Co some existing; some in M‐4c Greenway System ‐ Low ay Montour Montour County Planning Scenic Bikeway, Ribbons of Green & Comp Plan; Pg. 5 planning; others concept Montour Ridge corridor Chillisquaque Creek Corridors that s together unify County recreation.

Several other greenway corridors – including Old Iron Ore, Reading Rail, Montour County Montour Ridge, Rail with Trail, Source: Montour Co some existing; some in M‐4d Greenway System ‐ Low X Montour Montour County Planning Scenic Bikeway, Ribbons of Green & Comp Plan; Pg. 5 planning; others concept Rail with Trail Chillisquaque Creek Corridors that together unify County recreation.

20 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Several other greenway corridors – X including Old Iron Ore, Reading Rail, Montour County greenw Montour Ridge, Rail with Trail, Source: Montour Co some existing; some in M‐4e Greenway System ‐ Low ay Montour Montour County Planning Scenic Bikeway, Ribbons of Green & Comp Plan; Pg. 5 planning; others concept Chillisquaque Creek corridor Chillisquaque Creek Corridors that s together unify County recreation. Greenway corridors – Old Iron Ore, X Reading Rail, Montour Ridge, Rail greenw with Trail, Scenic Bikeway, Ribbons Recreation Plan Source: Montour Co some existing; some in M‐4f Greenway Corridors Med ay Montour Montour County Planning of Green and Chillisquaque Creek Implementation Comp Plan; Pg. 66 planning; others concept corridor Corridors ‐ some progress has been s made Develop and complete a balanced pedestrian, buggy and bicycle Countywide transportation networks, including pedestrian, buggy X hiking trails, bikeways, greenways, M‐5 and bicycle Low develop special travel lanes/signage for Montour Montour County Concept Pg. 75 Concept transportation network buggies and related areas to result network in a network that serves the Danville area and the more rural areas of the County. Local recreation parks in Limestone, Develop local Derry, West Hemlock, Liberty, Municipalities in M‐6 recreation parks in Low X Mayberry, Cooper, Danville and Montour Concept Pg. 5 Concept Montour County municipalities Washingtonville ‐ no local match exists to act upon opportunities. North Branch Canal Catawissa to Bloomsburg Connector Bloomsburg into Trail Connector, M‐7 High X with North Branch Canal Trail Montour Northumberland Planning MARC planning in progress Catawissa to (Reference CO‐40) County Bloomsburg North Branch Canal Danville into Catawissa to Danville Connector M‐8 Trail, Danville High X Montour Northumberland Planning MARC planning in progress with North Branch Canal Trail Connection County Danville Riverfront A portion exists but the Danvillle Riverfront Trail ‐ Main M‐9 Trail ‐ Main Levee High X Montour Danville Planning MARC proposed final alignment is Levee Segment Segment still a concept Danville Riverfront Danville Riverfront Trail ‐ Soccer M‐10 Trail ‐ Levee to High X Montour Danville Planning MARC planning in progress Park Segment Soccer park

21 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready A portion exists but the preferred final alignment M‐11 Monkey Drift Trail Med X Monkey Drift Trail Final Alignment Montour Danville Concept MARC runs along Mahoning Creek corridor Monkey Drift Trail to Monkey Drift Trail Hess Loop M‐12 Med X Montour Danville Concept MARC Concept Hess Loop connector connector

M‐13 River Front Trail Low X River Front Trail Montour Danville Concept MARC Portion does exist Hospital Run Levee Danville, Montour Co, M‐14 Low X Hospital Run Levee Trail Montour Concept MARC Concept Trail Geisinger

survey and subdivision River Road to North Danville‐River Rd segment work has been completed. M‐16 Branch Canal Trail High X connection to North Branch Canal Montour Danville & east Planning Lack funding to do detailed Connector Trail engineering design.

Source: North West Chillisquaque 1st bid process came in Liberty Hollow Rail walking/bike path on unopened Northumb Boroughugh‐ Point Shovel Ready. Funding is N‐1 High X Township 2x available funds, Shovel Ready Trail Washington Ave erland Township Joint Comp needed seeking solutions Plan

Acquire the 80 acre parcel owned by Northumberland County on Route 11 near the Susquehanna River; acquire an adjoining parcel in order to create safe access to the future park. Master plan the site as a Source: North Borough of Point Township 80‐ community park featuring a Northumb Boroughugh‐ Point N‐2 Med X Northumberland, Concept concept acre Recreation Park sports complex. Explore the idea erland Township Joint Comp Point Township of creating a premiere sports Plan facility here as a means of generating revenue. Involve the public in the planning process. Propose potential partners in developing, and later managing, the facility.

22 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Acquire the 20‐acre site Source: North Pineknotter Park adjoining Pineknotter Park to Northumb Borough of Boroughugh‐ Point N‐3 Med X Concept concept Expansion and Trails expand the park and establish erland Northumberland, Township Joint Comp trails and trail connections. Plan

Secure the 11‐acre parcel owned by X Northumberland County and Borough of Source: North West Chillisquaque trailhea located in West Chillisquaque for Northumberland, Boroughugh‐ Point N‐4 Trailhead and River Low d & orthumberla Concept concept use as a trailhead West Chillisquaque Township Joint Comp Access river Plan access and river access. Township

Obtain a 25‐year or longer lease Source: North for the Acorn Little League Fields Borough of Acorn Little League Borough‐ Point N‐5 Low X for continued use as a orthumberla Northumberland, Concept concept Fields Township Joint Comp community ball field. Point Township Plan

Acquire two parcels of land of 25 acres or more for use as future community park. These parcels should be located in Point Township north of Northumberland Borough and Source: North Borough of south of the forested steeply Northumb Borough‐ Point N‐6 Joint Park Landbank Low X Northumberland, Concept concept sloped northern section of the erland Township Joint Comp Point Township Township and near future Plan population centers. Landbank these parcels for future generations or until funding becomes available for their development. Secure land for a neighborhood Source: North park to Borough of Northumb Borough‐ Point N‐7 Kapp Heights Park Low X serve the Kapp Heights Northumberland, Concept concept erland Township Joint Comp neighborhood. Point Township Plan

23 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Develop a plan for the on‐road bicycle routes. Evaluate roadways for on‐road bicycle X Develop Plan for on‐ routes. Engage a traffic engineer develop Borough of road Bicycle Routes to design on‐road bicycle Northumb N‐8 Low plan for Northumberland, Concept concept in Northumberland enhancements. Apply for erland on‐road Point Township & Point Township routes transportation enhancement funding for implementation of on‐ road enhancements. Source: North Sunbury to Paxinos Trail from Sunbury to Paxinos Northumb Borough‐ Point N‐9 Low X Sunbury, Paxinos Concept concept Trail along Shamokin Creek erland Township Joint Comp Plan Source: North Point Township to Trail from Point Township to Northumb Point Township & Borough‐ Point N‐10 Montour County Low X Concept concept Montour County line erland north Township Joint Comp Trail Plan

Intersection Safety Northumb N‐11 Improvements Low X Rt 45 and Rt 405 Concept Locally Identified Project erland Involving PennDOT

Rehabilitation and further Finishing Planning, Middlecreek Nature S‐1 High X development of Middlecreek Snyder Snyder County Under Construction Source: C2P2 Construction started in Park Rehabilitation Nature Park ‐ 2016 2017

Middlecreek Township, $40,000, Rehabilitation and further development of Middlecreek Nature Park, Middlecreek Middlecreek Nature Township, Snyder County. Work this is a continuation of S‐ S‐2 Park further High X to include construction of Snyder Snyder County Concept Source: C2P2 concept 1 development pavilion, pedestrian walkway, access drive and parking area; ADA access, landscaping, project sign and other related site improvements.

24 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

…there exists five abandoned rail line segments in the county stretching from McClure Borough to Kreamer and Lake Augusta West from the Steam Electric Source: Snyder Co Shore Greenway Station at Shamokin Dam S‐3a Med X Non‐motorized Transportation Snyder Snyder County Concept Comp Plan; Pg. 5‐7 Concept Trail ‐ Steam Electric to the Snyder‐Union through 5‐8 Station to Fabridam County line. In total, these abandoned segments constitute over 15 miles of potential rail‐ trail projects... (This should be verified... )

…there exists five abandoned rail line segments in the county stretching from McClure Borough to Kreamer and from the Steam Electric Snyder County Rail Source: Snyder Co Station at Shamokin Dam S‐3b Trails ‐ Kreamer to Med X Non‐motorized Transportation Snyder Snyder County Concept Comp Plan; Pg. 5‐7 Concept to the Snyder‐Union McClure through 5‐8 County line. In total, these abandoned segments constitute over 15 miles of potential rail‐ trail projects... (This should be verified... )

25 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Acquiring land from private landowner will Lake Augusta West Shamokin Dam secure right of way Shore Greenway Linear Corridor and Boathouse Borough, Monroe necessary to build the Planning in Progress, Source: Susquehanna S‐4 Trail ‐ Shamokin Low X Site Land Acquisition, Lake Snyder Township, Union West Shore Greenway, a Planning Funding request River Sports Park Dam to Union Augusta West Shore Trail Township in Union key element in the Lake submitted County line County Augusta Plan and strategic segment of the Susquehanna Greenway

A public park with trails and river access creating Shamokin Dam Source: Susquehanna S‐5 Canal Heritage Park Low X Canal Heritage Park Snyder a link between Concept Concept Borough River Sports Park boathouse site and DCNR's Fiber Dam Park. Susquehanna River high quality rowing Sports Park, Susquehanna River Sports Park, Shamokin Dam Source: Susquehanna S‐6 Low X Snyder boathouse, docks and Concept Concept Boathouse and Boathouse and Rowing Venue Borough River Sports Park staging area. Rowing Venue Countywide A comprehensive network of on‐ comprehensive road bike lanes and shoulders Source: Union Co pedestrian and and off‐road trails safely U‐1 High X Union Union County Concept Comp Plan; Section bicycle accommodates bicycle travel 8, Part 2, Pg. 6 transportation within and between towns and network villages.

Several sidewalk Establish safe pedestrian facilities extensions have been along commercial corridors (US installed along US 15 at Source: US Route 15 Route 15 in the Lewisburg area Route 15 Corridor, Lewisburg, Penn House Commons, Corridor Plan; U‐2a High X and PA Route 45 in the Union Concept Lewisburg Area Mifflinburg Fairfield Chevrolet, Jersey Section 8, Part 2, Pg. Mifflinburg area) and provide Shore State Bank, etc. as 13‐18 connections to nearby residential part of the areas. redevelopment process

26 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Several sidewalk Establish safe pedestrian facilities extensions have been along commercial corridors (US installed along US 15 at Route 15 in the Lewisburg area Source: Union Co Route 45 Corridor, Lewisburg, Penn House Commons, U‐2b High X and PA Route 45 in the Union Concept Comp Plan; Section Mifflinburg Area Mifflinburg Fairfield Chevrolet, Jersey Mifflinburg area) and provide 8, Part 2, Pg. 13‐18 Shore State Bank, etc. as connections to nearby residential part of the areas. redevelopment process

Complete sidewalk networks Union County Source: Union Co within Union County’s towns and Union County towns U‐3 Town and Village Med X Union Concept Comp Plan; Section villages promote walking as a and villages Sidewalk Network 8, Part 2, Pg. 6 basic form of transportation.

Commercial corridors outside of Union County town and village centers have Source: Union Co U‐4 Rural Commercial Med X sidewalks, crosswalks, and Union rural Union County Concept Comp Plan; Section Corridors median refuges that provide safe 8, Part 2, Pg. 6 pedestrian access.

Countywide pedestrian and A multi‐use trail network Source: Union Co U‐5 bicycle Med X connects rural parts of the Union rural Union County Concept Comp Plan; Section transportation County to towns and villages. 8, Part 2, Pg. 6 network

Provide multi‐use trails to Provide multi‐use accommodate off‐road non‐ trails to Source: Union Co motorized travel, particularly in U‐6 accomodate off‐ Med X Union Union County Concept Comp Plan; Section areas where adequate bike lanes, road non‐ 8, Part 2, Pg. 13‐18 sidewalks, or paved shoulders motorized travel are infeasible due to constraints.

Work with the local school Source: Union Co Union County Safe districts to promote the safety of Lewisburg, Occuring in Lewisburg U‐7 Med X Union Concept Comp Plan; Section Routes to School children walking and bicycling to Mifflinburg with Walk It Bike It group 8, Part 2, Pg. 13‐18 school.

27 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready C‐3. Install 200 miles of riparian forested buffers along the Source: Union Co Union County X Susquehanna River and county Greenway and Open U‐9 Riparian Forest High riparian Union Unioin County Concept streams, particularly impaired Space Plan; Pg. 74‐ Buffers buffers reaches, to improve water 78 quality. L‐3. Permanently protect the 1.5 Source: Union Co Great Stream miles of riverfront land in Great Greenway and Open U‐10 Commons Low X Union Gregg Township Concept Stream Commons. Space Plan; Pg. 74‐ Riverfront 78 X Source: Union Co Planning in progress, plan P‐6. Implement Bull Run Lewisburg, East Greenway and Open Moving to Construction U‐11 Bull Run Greenway Med implem Union Planning Greenway Plan Buffalo Township Space Plan; Pg. 74‐ Drawings on Phase I ‐ entatio 78 Kidsburg n

Planning in progress, T‐1. Buffalo Valley Rail Trail preliminary engineering Source: Union Co Buffalo Valley Rail (BVRT) US 15 crossing as per the done, needs to move Lewisburg, East Greenway and Open U‐12 Trail (BVRT) US 15 High X US 15 corridor study. Engineering Union Planning beyond concept; waiting Buffalo Township Space Plan; Pg. 74‐ crossing design, permitting and on CSVT completion by 78 construction. PennDOT and will need funding

Source: Union Co Can move into design if Greenway and Open Allenwood Village T‐3. Engineering, design and Norfolk Southern Space Plan, Concept, currently on to Montgomery construction of Allenwood U‐13 High X Union Allenwood & north crossing issue in Concept Susquehanna hold waiting on land Borough multi‐use Village to Montgomery Borough Lycoming County is Greenway developer along corridor riverfront trail multi‐use riverfront trail. resolved. Partnership; Pg. 74‐ 78 Bucknell University Civil BVRT Western T‐4. Evaluate feasibility of Engineering students Source: Union Co Extension‐ extending BVRT west of evaluated the feasibility Greenway and Open U‐14 High X Union Mifflinburg & west Planning Planning Mifflinburg to Mifflinburg across SR 45 to of the trail extension as Space Plan; Pg. 74‐ Swengle Swengle Rd. part of a senior design 78 project

28 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready T‐7. Rehabilitate BVRT railroad bridge over the Susquehanna Source: Union Co BVRT railroad Lewisburg, River to link with proposed SR Greenway and Open U‐15 bridge over the Low X Union Northumberland Concept 405 greenway and trail in Space Plan; Pg. 74‐ Susquehanna County Northumberland County. 78

West Branch Susquehanna T‐9. Monitor potential for rail Lewisburg, East Source: Union Co Greenway, with trail or rail trail connecting Buffalo Township, Greenway and Open U‐16 Med X Union Concept Lewisburg to BVRT in Lewisburg to Winfield Union Township, Space Plan; Pg. 74‐ Winfield Village Village. Winfield 78 Trail T‐11. Evaluate feasibility of improved pedestrian access on St Source: Union Co St. Anthony Anthony St bridge as a safer link Kelly Township, Greenway and Open U‐17 St./River Road Low X Union Concept Concept to Riverwoods and soccer Lewisburg Borough Space Plan; Pg. 74‐ Bridge complex along with riverwalk 78 concept

West Branch Susquehanna Water Trail T‐15. Improve West Branch Source: Union Co Infrastructure X Susquehanna water trail Demonstration Project at Greenway and Open U‐18 Improvements High river Union currently Lewisburg Concept infrastructure throughout the St. George Street LBG Space Plan; Pg. 74‐ throughout county ‐ access county. 78 St George St demonstration project

Source: Union Co Great Stream X River accesses at Great Stream Demonstration Project at Greenway and Open U‐19 Commons River High river Union Gregg Township Concept Commons and St. George Street St. George Street LBG Space Plan; Pg. 85‐ Access access 90

29 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready Urban Stream restoratiohn and greenway X Source: Union Co (demonstration stream Urban stream restoration and Greenway and Open U‐20 High Union currently Lewisburg Demonstration Project Concept project Bull Run restora greenway development. Space Plan; Pg. 85‐ Greenway, tion 90 currently at Kidsburg) Source: Union Co X Greenway and Open establis L‐7. Establish a permanent and Space Plan, West Branch h multi‐purpose greenway along eastern Union Susquehanna U‐21 Susquehanna Med perman the West Branch Susquehanna Union Concept concept County Greenway Greenway en River. Partnership Vision greenw and Strategic Plan; ay Pg. 74‐78 Source: Union Co T‐5. Explore routes, both on‐road Extend BVRT west West End Union Greenway and Open U‐22 Med X and off‐road for connecting the Union Concept to Cherry Run County Space Plan; Pg. 74‐ BVRT to the Cherry Run Trail. 78 T‐6. Engineering, design and construction of BVRT extension Source: Union Co Extend BVRT 5th from 5th Street to the Greenway and Open U‐23 Med X Union Lewisburg Concept Street to River Susquehanna River in St. John’s Space Plan; Pg. 74‐ Street corridor. 78

Source: Union Co West Branch Greenway and Open Winfield, Susquehanna T‐8. Evaluate feasibility of Space Plan, Northumberland Greenway, creating a multi‐use trail from Susquehanna U‐24 Med X Union Borough in Concept Winfield to Winfield to Northumberland Greenway Northumberland Northumberland Borough. Partnership Vision County Trail and Strategic Plan; Pg. 74‐78 Lewisburg T‐12. Explore feasibility of Source: Union Co Kelly Township, East Highschool to connecting new Lewisburg High Greenway and Open U‐25 Med X Union Buffalo Township, Concept Concept Linntown School to Linntown, Penn House Space Plan; Pg. 74‐ Lewisburg Connection Commons, BVRT, etc. 78

30 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready P‐1. Establish a community park in Source: Union Co Allenwood Allenwood at Columbia Avenue or U‐26 Low X Union Allenwood Concept Greenway and Open Community Park south of SR 44 river bridge. Space Plan; Pg. 74‐78

P‐9. Convert former New Berlin Source: Union Co New Berlin Elementary School property into Greenway and Open U‐28 Low X Union New Berlin Concept Community Park a community park. Space Plan; Pg. 74‐ 78

P‐10. Add 110 acres of community park land in eastern Source: Union Co Union County and central Union County to eastern and central Greenway and Open U‐29 Low X Union Concept Parks reduce deficit under minimum Union County Space Plan; Pg. 74‐ national standards. 78

T‐13. Create north/south Source: Union Co Mifflinburg, eastern BVRT North/South connections to the BVRT (e.g. link Greenway and Open U‐30 Low X Union and central Union Concept Concept Connections to Koon Trail in Mifflinburg Space Plan; Pg. 74‐ County Borough. 78 X T‐14. Develop and implement a Source: Union Co Penns Creek Water water Penns Creek water trail and Greenway and Open U‐31 Low Union New Berlin and west Concept Trail & access trail & access plan. Space Plan; Pg. 74‐ access 78 T‐16. Determine feasibility with Source: Union Co East Buffalo Reopen Shamokin landowners the potential to Greenway and Open U‐32 Low X Union Township, Union Concept Mountain Trail reopen the Shamokin Mountain Space Plan; Pg. 74‐ Township Trail. 78 T‐17. Develop George Long Trail Source: Union Co along Penns Creek frontage in Develop George New Berlin, Greenway and Open U‐33 Low X New Berlin and Limestone Union Concept Long Trail Limestone Township Space Plan; Pg. 74‐ Township. 78

Reduce conflicts with turning Route 15 Corridor traffic ‐ Facilitate safe pedestrian a number of projects, Source: US 15 Smart Lewisburg, eastern U‐34 Safety High X crossing of US 15 corridor/ Union over several pages of Concept Trans Corridor concept Union County Improvements Improve pedestrian access matrix docx Improve Plan through the community network

31 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Kidsburg Park ‐ 2015 Lewisburg Borough, $250,000, Rehabilitation and further development of Kidsburg Park, Lewisburg Borough, Union County. Work to include stream restoration and public access; Planning in Progress, Kidsburg Park Land owned by U‐35 High X construction of pedestrian Union Lewisburg Planning Source: C2P2 moving to Construction Rehabilitation Lewisburg Borough pathways; installation of play Documents equipment with required safety surfacing and a nature play area; ADA access, landscaping, project sign, and other related site improvements

Bull Run Source: Lewisburg Rail‐with‐Trail extension from Planning in Progress, Greenway, Rail‐ Neighborhood U‐36 High X Market Street to Bucknell Union Lewisburg Planning moving to Construction Trail exention to Project; Pg. 100 and University Documents Bucknell 105 X Create Town – Campus Gateway Source: Lewisburg Planning in Progress, 6th Street U‐37 High streets with improved pedestrian and Union Lewisburg Planning Neighborhood moving to Construction Streetscape cape bicycle accommodations. Project; Pg. 111 Documents Source: Lewisburg Acquire 65 acres of additional East Buffalo Area Comp Rec, parkland (59 acres – community East Buffalo this is more specific U‐38 Township Med X Union Concept Park, Open Space parkland, 6 acres – neighborhood Township statement of U‐27 Community Parks and Greenway Plan; parkland). Pg. 171‐180 Source: Lewisburg Acquire three acres of Area Comp Rec, Lewisburg Borough U‐39 Low X neighborhood parkland Union Lewisburg Concept Park, Open Space Community Parks (prioritize riverfront acreage). and Greenway Plan; Pg. 171‐180 Source: Lewisburg Acquire 37 acres of parkland (30 Area Comp Rec, Kelly Township U‐40 Low X acres of community parkland, 7 Union Kelly Township Concept Park, Open Space Community Parks acres of neighborhood parkland). and Greenway Plan; Pg. 171‐180

32 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Trail from Bucknell Landing to Limestone Run (AKA Bull Run) ‐ several possibilities. From Bucknell Landing, one possibility suggests building a new trail along the waterfront north to Limestone Run. The completion of a suggested West Branch pedestrian bridge would connect Susquehanna BVRA (Formerly LARA) Source: Bucknell the trail over the creek to the Lewisburg, Kelly Greenway ‐ had negotiated a 25 year University‐ U‐41 Low X existing Lewisburg RiverWalk. Union Township, Union Concept Concept Bucknell Landing or more lease with Improving River Another option would be to County to Limestone Run Riverwoods. Access; Pg. 8 follow River Road and use (AKA Bull Run) Trail sidewalks until Mill Street, where it could connect with the Lewisburg RiverWalk. Near the same point, the railroad diverges from River Road into the heart of Lewisburg, towards Hufnagle Park. This could have rail with trail along it.

Safe Routes to Source: Lewisburg‐ Safe Routes to School Walking School Rt 1: safe routes to U‐42 Med X Rte 1: Washington and 15th Union Lewisburg Lewisburg Walk It Bike It Concept concept Washington and school Streets plus minor roads 15th Streets infrastructure plan Safe Routes to Source: Lewisburg‐ School Rt 2: 19th Safe Routes to School Rt 2: 19th safe routes to U‐43 Street, Adams Ave, Med X Street, Adams Ave, Verna Rd, Union Lewisburg Lewisburg Walk It Bike It Concept concept school Verna Rd, Jean Jean Blvd infrastructure plan Blvd Connect BVRT to U‐44 Low X Union Lewisburg Concept Locally Identified Project the Library Connection to U‐45 Low X Union Lewisburg Concept Locally Identified Project Northumberland Former south end U‐46 Low X Union Lewisburg Concept Locally Identified Project of Water St.

33 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready

Paths across the Bucknell fields‐ U‐47 Med X Union Lewisburg Concept Locally Identified Project from Linntown and along golf course

U‐48 Airport Rd Bridge Med X Union Lewisburg Concept Locally Identified Project

Connections beyond the U‐49 Borough north on Med X Union Lewisburg Concept Locally Identified Project Union County side of river

Traffic calming at U‐50 Med X Union Lewisburg Concept Locally Identified Project bridge, Rt. 45

U‐52 Stein Lane Corridor High X Union Lewisburg Concept Locally Identified Project

Safety U‐53a Low X Ped signals Union Lewisburg Concept Locally Identified Project Improvements

15 and 45 U‐54 Intersection Safety High X Union Lewisburg Concept Locally Identified Project Improvements

Rail Trail and Fairground Rd U‐55 High X Union Lewisburg Concept Locally Identified Project Intersection Safety Improvements

34 Matrix of Bicycle and Pedestrian Needs as of 05‐10‐19

Bike/ Stage ‐ Concept, Parks Source, Potential ID SC Project name Priority Ped Safety Other Project Description County Location Comments Planning, Design, Status & Rec Partner Facility Shovel/Impl. Ready 15 and St Mary Street Intersection U‐56 Med X Union Lewisburg Concept Locally Identified Project Safety Improvements Market St and Water St U‐57 Med X Union Lewisburg Concept Locally Identified Project Intersection Safety Improvements

Intersection Safety U‐58a Improvements Low X Beagle Club and 15 Union Lewisburg Concept Locally Identified Project Involving PennDOT

Intersection Safety St Mary crosswalks from Penn U‐59a Improvements not Low X Union Lewisburg Concept Locally Identified Project House Commons Involving PennDOT

Stein Lane and Jefferson U‐60 Med X Union EBT Concept Locally Identified Project Intersection Safety Improvements

Stein Lane and Monroe U‐61 Med X Union EBT Concept Locally Identified Project Intersection Safety Improvements

35