Steel Bridge News National Steel Bridge Alliance Significantly Reduced the Amount of Shoring Estero Project

Steel Bridge News National Steel Bridge Alliance Significantly Reduced the Amount of Shoring Estero Project

Steel Bridge NATIONAL STEEL BRIDGE ALLIANCE NEWS JUNE 2008 On Opposite Coasts BY CRAIG FINLEY, P.E., JERRY PFUNTNER, P.E., AND MATTHEW ADAMS, P.E. This rendering shows the MIC-MIA bridge, which will provide access to Miami International Airport’s rental car facility. Two Florida bridges—on either side of the state—will deliver multiple benefits to their owners and users, thanks to value The redesign of the Estero Parkway Flyover project replaces twin, cast-in- place concrete box girders with with a design using four steel box girders. engineering redesign. LOCATED ON OPPOSITE COASTS OF FLORIDA, TWO CUR- crete, of course. And despite what some may think, the savings aren’t RENT BRIDGE PROJECTS WILL SERVE VASTLY DIFFERENT strictly linked to the material costs of the former versus the latter. PURPOSES. Donald Deberry, P.E., public works operations manager for Lee The Estero Parkway Flyover, near Fort Myers on Florida’s west County, notes that the recent cost fluctuation for all kinds of con- coast, will ease traffic congestion on the parkway and offer travel- struction materials underscores the need for good, solid engineering ers an alternate east-west route on the Tamiami Trail and I-75. The design, because chasing material prices is a losing game. Miami Intermodal Center Terminal Access Roadway Project—nick- “It might look like you’re saving money when you evaluate price Lnamed MIC-MIA—will provide access to a rental car facility as part during development of the project or the bridge development re- of a major upgrade of Miami International Airport. port,” he says. “But later, when you actually go to buy it, you might But both projects have one thing in common (besides being in find that you would have been better off using something else be- Florida): they were both initially designed to use concrete for the cause of price fluctuations in the materials market.” superstructure. Both were redesigned in steel by Finley Engineer- On both the Estero and MIC-MIA projects, three factors other ing Group in a value engineering process. And both will now be than material price dictated that steel was the better choice: built faster and will save their respective owners approximately $2.5 Site conditions. The original design for the MIC-MIA project million combined. called for a cast-in-place concrete-on-falsework section combined with concrete U-beam superstructure to make up the 584-ft-long Out of the Comfort Zone bridge. As designed, the construction would have been excessively Tampa Steel is the steel fabricator on both the Estero and the complicated and labor-intensive. The value engineering redesign MIC-MIA projects. Robert “Bob” Clark, Jr., the company’s presi- included only one superstructure type. And by converting the su- dent, says that most bridge superstructures are designed in concrete perstructure to steel, the redesign eliminated the need for falsework, because many bridge engineers are more comfortable and experi- greatly simplifying construction and minimizing the impact on on- enced with concrete than they are with steel. “Most colleges teach going operations and construction projects at the rental car facility. concrete design in their core courses, whereas steel design is an According to one of the subcontractors working on the FDOT elective in advanced courses. So many engineers choose concrete MIC-MIA project, the original design would have required substan- because of an absence of knowledge about steel.” tially more temporary shoring towers on the site, thereby impeding Not every project benefits from a conversion to steel from con- the principal access to the site. As such, the shift to steel box girders JUNE 2008 MODERN STEEL CONSTRUCTION STEEL BRIDGE NEWS NATIONAL STEEL BRIDGE ALLIANCE significantly reduced the amount of shoring Estero project. Jovan Zepcevski, president substructure design, meaning that fewer required. of Estero contractor Zep Construction, says piles were necessary. In the Estero project, The Estero site had similar site restric- steel prices were relatively high during the the number of 24-in. precast piles dropped tions—and design solutions. The redesign initial design period, but that they eventual- from 130 to 76. On the MIC-MIA, the re- replaces twin, cast-in-place concrete box ly receded enough to make steel the clearly design increased the precast piles from 18 in. girders with a single bridge using four steel better choice during the value engineering to 24 in., but reduced the number of piles box girders. portion of the project. from 163 to 60. This eliminates a large falsework sup- The less complex construction process port system, reduces foundation design will also help the contractors meet their A New Perspective requirements, and simplifies construction. schedules. For example, in the case of the An important lesson to take away from The overall result is a shorter time frame to Estero project, Zep must finish the job in both projects is that value engineering pro- complete the bridge, an obvious benefit to less than two years. For the Miami project, vides the opportunity for a new look at a the traveling public. completing the structure quickly alleviates project by involving the contractor. That Falsework in the original design would coordination issues associated with large, new look may very well uncover a better have also more significantly affected a de- integrated construction projects. way to build the bridge—as it did in these sign-build project to widen I-75, which runs Owner requirements. Lee County will two cases. Taking the opportunity to look beneath the bridge site. It would have cre- pay a minimum of $1.85 million less for the at a project, with the engineer and contrac- ated more safety hazards for motorists, and redesigned Estero Parkway Flyover than it tor both contributing ideas on how to best the falsework erection and cast-in-place budgeted under the original design. The accomplish the project’s objectives, can add pours would have slowed traffic far more county coffers may get even more back, as better, faster, and less costly to the overall proj- often than will occur with the placement of the contractor and the county will split any ect accomplishments. By incorporating a steel girders on the superstructure. additional savings. value engineering redesign, the project team Contractor means and methods. Val- The redesigns saved money in a number is loudly and clearly stating that the client’s ue engineering redesigns are often driven of ways. On the Estero project, the conver- needs are paramount. by the preferences and experiences of the sion to steel resulted in a reduced superstruc- contractor chosen for the work. Some con- ture depth. This shortened the required ap- Craig Finley is managing principal, Jerry Pfunt- tractors are simply better with one material proach embankment height, so the project ner is a principal, and Matthew Adams is a bridge than the other. won’t need as much fill on each approach. A engineer, all with Finley Engineering Group. Contractors also prefer designs that are reduction of about 4 ft in the fill height at not overly complex and that allow them to the beginning and end of the bridge, tapered For more on the Estero Parkway Flyover proj- make money on the job. On both the MIC- over the length of the nearly 700-ft-long ap- ect, see December 2007’s Steel Bridge News, MIA and the Estero projects, elimination of proach embankments, means massive savings available online at www.modernsteel.com/ the falsework reduced the complexity and in mechanically stabilized earth (MSE) fill. archives. the amount of labor that would be required In both projects, the change to steel re- to complete the work. Particularly in a con- duced the number of piles required, and in Structural Engineer (for both projects) struction climate where qualified workers the case of the MIC-MIA project, one of Finley Engineering Group, Tallahassee, Fla. have been difficult to find, this is a welcome the piers could be eliminated. Because the Steel Fabricator (for both projects) change for the contractors. steel boxes produce a lighter superstructure, Tampa Steel, Tampa, Fla. Material cost did play some role in the the redesign resulted in a more efficient (AISC/NSBA Member) MODERN STEEL CONSTRUCTION JUNE 2008 NATIONAL STEEL BRIDGE ALLIANCE STEEL BRIDGE NEWS KC Crossing Construction is scheduled to start this The project will reconstruct/rehabilitate a chor the 40 parallel strand cable stays, cre- spring on the $245 million KCICON four-mile section of Interstate 29/35 leading ating a unified focal point for the structure (Interstate Connections 29/35) Project into downtown Kansas City. Along with high- and a gateway experience for those driving in Kansas City. This is the second of three way widening and interchange reconstruc- across it. design-build projects being undertaken by tion work, the project will replace the existing To encourage the creation of an aestheti- the Missouri Department of Transporta- Paseo Bridge over the Missouri River with cally pleasing bridge, representatives of a com- tion (MoDOT). the Christopher S. Bond Bridge, a 124-ft- munity advisory group were given 20 points Paseo Corridor Constructors, a joint wide, 1,676-ft-long cable-stay structure. with which to score the two design-build venture partnership of Clarkson Construc- The cables will stretch across a 550-ft proposals. This marked the first time a state tion, Massman Construction, and Kiewit main span and 451-ft side span, with a single transportation agency has allocated selection Construction, will lead construction efforts. composite steel plate girder span connect- points to community members. Design is being handled by Parsons Trans- ing to the structure’s south end and a multi- portation Group and TranSystems.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    6 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us