Download Detailed Project List (Last Update 1/05/2020)

Download Detailed Project List (Last Update 1/05/2020)

List of Projects OIL AND GAS PIPELINE PROJECTS S.No. Year Project Name Client 1 On- Pipeline Laying and Terminal Works (Part-C) for India Bangladesh Friendship Pipeline Numaligarh Refinery Limited (NRL) going Project of Numaligarh Refinery Ltd (Pipeline of size 10.75 inch OD x approx. length 50.361 km from Chainage 80.000 KM to Parbatipur Receipt Terminal of Bangladesh Petroleum Corporation in Bangladesh at Chainage 130.361 KM including terminal works at Parbatipur Receipt Terminal, sectionalizing valve stations SV-4 & SV-5 cum tap off station and other associated pipeline facilities) 2 On- Construction of 67 km long 762 mm (30 inch) DN X 1100 psig high Pressure Natural Gas Gas Transmission Co. Ltd. (GTCL) going Transmission Pipeline from Dhanua-Elenga and West Bank of Bangabandhu Bridge-Nalka Gas Transmission Pipeline Project under the Loan Agreement No: Natural Gas Efficiency Project (BD-P78) 3 2020 Lot-5/Section-E: Construction of 42” OD x 1100 psig Gas Transmission Parallel Pipeline Gas Transmission Co. Ltd. (GTCL) from Banigram Valve Station to Anowara CGS (approximately 14.5 km including 48 inch x 96 Meters road crossing) under Maheshkhali-Anowara Gas Transmission Parallel Pipeline Project. 4 2020 Installation of 42” OD High Pressure Natural Gas Transmission Pipeline by Horizontal Gas Transmission Co. Ltd. (GTCL) Directional Drilling (HDD) method across one River [Sangu] and three nos. Khals (Barabakia, Napithkhali & Gabinda) on Design, Procurement ,Supply, Installation and Commissioning on Turn Key basis under Moheshkhali- Anowera Gas Transmission Parallel Pipeline Project (in JV with Gypsum-Gasmin) 1 May 2020 1 5 2019 Construction of 22 km long x 36˝ OD 1000 psig high pressure natural gas transmission Gas Transmission Co. Ltd. (GTCL) pipeline (including one mainline valve station) from Ghoshoa, Barura to Nijmohichal, Chandina, Comilla (Section-G) under Construction of Chittagong-Feni-Bakhrabad Gas Transmission Parallel Pipeline Project. 6 2018 Hydrotesting (at a pressure of 128 bar) of the 24” dia 5.5. Km Sub-sea pipeline (From FSRU GEOCEAN Entrepose point upto Platform at ‘0’ point of Moheshkhali Island) and spools. 7 2018 EPC for Gas Supply Augmentation Project (Hot tapping, RMS and CMS stations, Pipeline Abul Khair Steel Melting Company with road and river crossings) of Abul Khair Steel Melting Company (A concern of AKS Group), Sitakunda, Chittagong. 8 2018 Design, Build, Procurement & Supply, Installation, Construction, Testing and Gas Transmission Co. Ltd. (GTCL) Commissioning of 1(one) 600 mmscfd Capacity Custody Transfer Metering Station (CTMS) at Maheshkhali and 1(one) 600 mmscfd Capacity City Gate Station (CGS) at Anowara on Turn-Key (EPC) basis under Maheshkhali-Anowara Gas Transmission Pipeline Project. 9 2018 Tie-in Job of Maheshkhali-Anowara Gas Transmission Pipeline with offshore Pipeline of Gas Transmission Co. Ltd. (GTCL) Excelerate Energy Bangladesh Ltd. (EEBL) at Zero Point in Maheshkhali including fabrication of spools on the tie-in platform, erection of platform in tidal zone and hydrotesting of the tie-in portion. 10 2018 Reinstatement/ Repairing of 700 feet eroded Right of Way (RoW) of the Pipeline installed Gas Transmission Co. Ltd. (GTCL) by Dipon Gas Co. Ltd. at Mujiberghona and nearby Embankment (Beribadh) damaged by Roanu & it’s after effect work. 11 2017 Design, Build and Turnkey Supply, Installation, Construction, Hot tapping, Instrumentation, Gas Transmission Co. Ltd. (GTCL) Testing, Commissioning of 3 (Three) Interface Metering Stations [Town Border Stations (TBS)] at Kutumbapur, Feni and Barabkunda. 1 May 2020 2 12 2016 Lot -1/Section-A: Construction of 30'' OD x 1100 psig Gas Transmission Pipeline from Zero Gas Transmission Co. Ltd. (GTCL) Point, Maheshkhali to CTMS adjacent to Dhalghat Para Primary School (approximately 6.865 km) under Maheshkhali - Anowara Gas Transmission Pipeline Project. 13 2015 Procurement and Supply of all Materials (Line pipes, Coatings & Wrapping, Induction Bangladesh Power Development Bends, Miscellaneous fittings, Valves, Pig Traps etc.), and Construction of 20 - inch 1000 Board psig 10 KM High Pressure Gas Transmission Pipeline from Bibiyana Gas Field End to Bibiyana Power Station-3 at Parkul, Nobiganj and Hook Up on Turnkey Basis. 14 2014 Construction of 36"OD x 1000 psig x 41.5 KM Gas Transmission Pipeline (incl mainline Gas Transmission Co. Ltd. valve station) from Bibiyana Gas field to South Bank of Kalni River (Lot-l/Sec -A) of Bibiyana- Dhanua Gas Transmission Pipeline Project at Habiganj. 15 2014 Construction work of BY JGTDSL Spur Line Chevron Bangladesh 16 2014 2 nos. 8" Flow Line Modification/ Loop Making including hydro testing works-SS Pad Chevron Bangladesh 17 2014 Support for Pigging and Purging of 20"Pipe line West Pads to South Pad Chevron Bangladesh 18 2014 Bibiyana West Pad Interconnecting Piping (ICP) Works. Chevron Bangladesh 19 2014 Bibiyana North Pad Dock Access (Aviation) Project. Chevron Bangladesh 20 2013 Bibiyana South-South Pad Interconnecting Piping (ICP) Works. Chevron Bangladesh 21 2012 Construction of 24 Km, 508mm (20" OD) x 1000 psig High Pressure Natural Gas Chevron Bangladesh Transmission Pipeline Shimulia, Kushtia (AP no. 57) to North-East Bank of Kumar River (AP no. 116) Sripur, Shoilkupa (Section-B) under Bheramara - Khulna Gas Transmission Pipeline Project at-Kushtia & Jhenaidah. 1 May 2020 3 22 2012 MB-7 Pipeline Development project at Moulovibazar. Chevron Bangladesh 23 2012 Tie-in Shutdown Services at Bibiyana Plant. Chevron Bangladesh 24 2012 Fabrication and Installation of Skid Based Piping Expansion Loops - B-3 Pipeline Tullow Bangladesh Ltd. Modification works at Bangora, Comilla. 25 2012 Tie-in Services August Shutdown for Bibiyana Expansion Project, Bibiyana. Chevron Bangladesh 26 2012 Fabrication, Painting and Insulation of Misc. Pipe Support, Structure, Platforms for Muchai Chevron Bangladesh Compressor Project at Sreemongol. 27 2012 BY-JGTDSL Tie- in Project at Bibiyana. Chevron Bangladesh 28 2011 MB-9 Pipeline Development Project at Moulavibazar. Chevron Bangladesh 29 2010 Construction of 21.2 Km long 762 mm (30 inch) OD x 1000 psig High Pressure Natural Gas Gas Transmission Co. Ltd. Transmission Pipeline from Monohordi to Bagherhat (Section -A of "Monohordi- Dhanua - Elenga-East Bank of Jamuna Bridge Gas Transmission Pipeline and Installation of Compressor Station at Ashuganj and Elenga Project") Gazipur. 30 2010 30" DN x 22 Km. 1500 psig Pipeline Work from Bibiyana to Muchai, Sylhet. Unocal Bangladesh Ltd. 31 2010 Welding Works for 42” and 48” pipeline from Fujairah to Taweelah under Dolphin Energy Story Trans Gaz (STG), UAE in UAE 32 2008 8" DN Bangora Gas Flow Line Installation at Comilla. Tullow Bangladesh Ltd. 33 2005 10" & 12" DN 15.5 Km. Gas Gathering Pipeline from Wellhead 5 to Process Plant via Unocal Bangladesh Ltd. Wellhead 4 & 6 at Moulavibazar. 1 May 2020 4 34 2005 16" DN 16.5 Km Long 1000 PSIG Gas Pipeline from Tengratilla to Chattak. Niko Resources Bangladesh Ltd. 35 2006 Welding and General Labor Contract for JB Gas Plant EG Conversion Project at Sylhet. Unocal Bangladesh Ltd. 36 2005 Pipe Laying Construction Work at Chattak, Sylhet. Niko Resources Bangladesh Ltd. 37 2003 Relocation/Protection of Gas Pipeline near Joydevpur Station, Jamuna Bridge Railway Link Samwhan -TSO Joint Venture Project at Tangail. 38 2003 16" DN x 140 PSIG, 0.5 Km Pipeline Construction Work from Meghnaghat Town Bordering Shahjalal Newsprint Industries Ltd. Station to the Road Crossing of Dhaka-Chittagong Highway, Comilla. 39 2003 Design, Execution, Completion and Commissioning of a 8'' DN Gas Pipeline from the Titas Anwar Cement Ltd., Bangladesh Gas T & D Co. Ltd. to the Regulating & Metering Station (RMS) of owners captive Electrical Generating Power Plant with 3 MW (Nominal) net capacity at the premises of Anwar Cement Ltd. Gazaria, Munshigonj, Dhaka, Bangladesh. 40 2003 Design, Execution, Completion and Commissioning of a 4'' DN Gas Pipeline from the Chittagong Cement Clinker Grinding Bakhrabad Gas Systems Ltd. Line to the Regulating and Metering Station of owner's Company Ltd., Bangladesh Captive Electrical Generating Power Plant with 5.8 MW net capacity at the premises of Chittagong Cement Clinker Grinding Company Ltd., Chittagong, Bangladesh. 41 2003 Construction of 16" DN Pipeline from R.M.S. at Meghna Ghat to Meghna Industries for 10 Meghna Industries M.W. Power Plant at Comilla. 42 2003 Dhaka - Sylhet Road Project, RRMP - III, Narsingdi. BDC-NCE-F.F. Joint Venture 43 2003 Construction of 4" DN, 150 PSIG Pipeline and Construction of R.M.S. for 5.6 M.W. Power Chittagong Cement Clinker Grinding Plant at Chittagong. Co. Ltd. 44 2001 Construction of 20" DN Pipeline & Valve Station at Dhaka. Titas Gas T &D Co. Ltd. 1 May 2020 5 45 2001 Gas supply under EPC contract (Engineering, Design, Drawing, Procurement & Meghna Energy Ltd. (a unit of Rolls Construction) for 16" OD PSIG pipeline including Installation of RMS at Narayangonj. Royce Overseas Ltd.) 46 1999 Installation of 28", 16", 14", 12" & 6" DN Casing Pipes on Live Gas Pipeline at Bangabandhu Titas Gas T &D Co. Ltd. Bridge Link Project Contract- 1 at different Location J/V with SAMWHAN, Korea at Tangail. 47 1999 Construction of 24" & 20" DN High Pressure Gas lines with River Crossing from Elenga to Gas Transmission Co. Ltd. Baghabari as partner -In-charge of Bangladesh Pipeliners Consortium at Sirajgonj, Pabna. 48 1999 Construction 16" DN pipeline from Tongi - Ashulia with Turag River Crossing & 2 nos. of Titas Gas T &D Co. Ltd. DRS at Ashulia & Tongi, Dhaka. 49 1998 Construction of 20" High Pressure Gas Pipeline from Offshore to Salimpur Processing Plant Brown & Roots Bangladesh Ltd. with Gasmin Co. Ltd., Sirajgonj, Pabna. 50 1998 3" to 12" DN Fabrication of various types of Welding for Cementing unit in different Titas Gas Transmission & Distribution Drilling Location. Company Ltd. 51 1997 20" DN Gas Pipeline Construction from Monohordi DRS to Narsingdi including three Valve Titas Gas Transmission & Distribution Stations, River Crossing & Road Boring.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    26 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us