Technical Specification Series 10000 Piling Works

Technical Specification Series 10000 Piling Works

TECHNICAL SPECIFICATION SERIES 10000 PILING WORKS Series 10000 –Piling Works NRAP-MoPW TECHNICAL SPECIFICATION PART 10000 - PILING TABLE OF CONTENTS Item Number Page 10000 Board Cast in Place Piles 10-4 10001 Description 10-4 10100 Materials 10-4 10101 Steel Classing 10-4 10102 Concrete 10-5 10103 Reinforcement 10-5 10104 Drilling Fluid 10-5 10200 Construction Methods 10-5 10201 General 10-5 10202 Setting out Piles 10-6 10203 Diameter of Piles 10-7 10204 Tolerance 10-7 10205 Boring 10-7 10206 Placing Reinforcement 10-9 10207 Placing Concrete 10-9 10208 Extraction of Temporary Casing 10-10 10209 Temporary Support 10-10 10210 Records 10-12 10210 Measures in Case of Rejected Casing 10-12 10212 Measurement 10-12 10213 Payment 10-12 10300 Precast Concrete Units for River Training and Retaining Structures 10-13 10301 Description 10-13 10302 Materials 10-13 10303 Construction Methods 10-13 10304 King Post & Anchor Piles 10-14 10305 Precast Planks 10-14 10306 Tolerance 10-14 10307 Measurement 10-14 10308 Payment 10-14 10400 Pile Test Loading 10-15 10401 General 10-15 10402 Definitions 10-15 10403 Supervision 10-15 10500 Safety Precautions 10-16 10501 General 10-16 10502 Kentledge 10-16 10503 Tension Piles and Ground Anchors 10-16 10504 Testing Equipment 10-16 UNOPS-Afghanistan PART 10-1 Series 10000 –Piling Works NRAP-MoPW 10600 Construction of a Pilot Pile to be Test Loaded 10-17 10601 Notice of Construction 10-17 10602 Method of Constructions 10-17 10603 Boring or Driving Record 10-17 10604 Cut-Off Level 10-17 10605 Pile Head for Compression Test 10-17 10606 Preparation of a Working Pile to be Tested 10-17 10607 Reaction Systems 10-18 10608 Compression Tests 10-18 10609 Working Piles 10-18 10610 Spacing 10-18 10610 Adequate Reaction 10-18 10612 Care of Piles 10-18 10613 Loading Arrangement 10-18 10614 Equipment for Applying Load 10-18 10615 Measurement of Load 10-18 10616 Adjustability of Loading Equipment 10-19 10700 Measuring Movement of Pile Heads 10-19 10701 General 10-19 10702 Levelling Method 10-19 10703 Independent Reference Frame 10-19 10704 Others Methods 10-20 10705 Protection from Weather 10-20 10706 Prevention of Disturbance 10-20 10707 Notice of Test 10-20 10708 Records 10-20 10800 Test Procedure 10-20 10801 Proof Test by Maintained Load Test 10-20 10802 Presentation of Results 10-20 10803 Schedule of Records Data 10-20 10804 Completion of a Test 10-21 10805 Measuring Equipment 10-21 10806 Kentledge 10-22 10807 Temporary Piles 10-22 10808 Pile Integrity Test 10-22 10809 Measurement and Payment 10-23 10900 Bitumen Slip Layer for Piles 10-23 10901 Description 10-23 10902 Materials 10-23 10903 Primer 10-23 10904 Bitumen 10-24 10905 Field Storage and Installation 10-24 10906 Measurement 10-24 10907 Payment 10-24 UNOPS-Afghanistan PART 10-2 Series 10000 –Piling Works NRAP-MoPW 10000: Bored Cast In Place Piles 10001 Description This work comprises the construction of bored cast in place piles for bridges, including the provision of all material and structures in accordance with these Specifications and in conformity with the requirements of the Drawings or other parts of the Contract Documents. Piles through water and soft upper soil layers shall be provided with a permanent steel casing if shown on the Drawings. The pile boring shall be carried out using a temporary steel casing bored to the pile toe or to a level approved by the Engineer. The temporary casing shall be withdrawn. Under certain circumstances the Contractor may be permitted to bore all or part of the pile without casing under water or using drilling fluid to stabilise the borehole as referred to in Section 10.1.2.4. The piles shall be concreted and reinforced to resist pile loads and horizontal forces on the pile caps according to the Drawings and these Specifications. 10100 Materials 10101 Steel Casing This part of the Specifications only deals with the permanent steel casing. For steel casing used during boring of the pile see Section 10.1.3, Construction Methods. When permanent steel casing is shown on the Drawings, the steel shall conform to the AASHTO Standard Specification M 183-79 (ASTM A36) or equivalent. The minimum thickness of the permanent steel casing shall be 10 mm. The minimum length shall be from 100 mm above the bottom of the pile cap to 5 metre under the river bed or into firm strata. If the permanent casing is used in the boring operation or if the handling and transport require a greater thickness to avoid deformation or buckling, the increase in thickness shall be provided by the Contractor at his own expense. The steel casing shall be furnished in appropriate lengths and the joints shall be approved by the Engineer. The casing shall be handled and stored in a manner that shall prevent buckling and other deformation as well as accumulation of dirt, oil and paint. When placed in the work it shall be free from dirt, oil, grease, paint, mill scale and loose or thick rust. The outside surface of the permanent casing of piles to river piers, for the depth indicated on the Drawings from the underside of the pile cap shall receive two coats of anti-corrosion tar type paint. The paint shall be approved by the Engineer and its application shall follow the manufacturer's instructions. 10102 Concrete The concrete shall conform to Section 8 of these Specifications. Concrete class 20 with type1 cement shall be used. Concrete placed under water or drilling mud by tremie shall have a cement content of not less than 350 kg/m3. UNOPS-Afghanistan PART 10-3 Series 10000 –Piling Works NRAP-MoPW The density and consistency of the concrete shall conform to the tremie casting method and the maintenance of sufficient workability (slump) of all the concrete during the casting and casing handling period, including reasonably calculated delays, shall be secured by a design mix, (including the necessary readers and plasticizers), tested by trial mixes prior to the pile construction. All relevant concrete properties such as slump, time of setting, temperature and strength shall be measured on the trial mixes. 10103 Reinforcement The reinforcement shall conform to Section 7 of these Specifications. 10104 Drilling Fluid The following clauses shall be complied with if bentonite mud is used to stabilise the boreholes: A) Supply A certificate shall be obtained by the Contractor from the manufacturer of the bentonite powder, showing the properties of the consignment delivered to the site. This certificate shall be made available to the Engineer on request. The properties to be given by the manufacturer are the apparent viscosity range (in centipoises) and the gel strength range for solids in water. Any other material proposed by the Contractor for the drilling fluid shall be approved by the Engineer. B) Mixing Bentonite and any other material shall be mixed thoroughly with clean water to make a suspension which shall maintain the stability of the pile excavation for the period necessary to place concrete and complete construction. Where saline or chemically contaminated groundwater occurs, special precautions shall be taken to modify the bentonite in fresh water so as to render it suitable in all respects for the construction of piles. C) Tests The frequency of testing drilling fluid and the method and procedure of sampling shall be proposed by the Contractor and approved by the Engineer prior to the commencement of the work. The frequency may subsequently be varied as required, depending on the consistency of the results obtained. The control tests shall cover the determination of density, viscosity, gel strength and pH values. The Contractor shall supply all equipment and experienced operators required to carry out tests on the drilling mud. No additional payment shall be made for these tests which shall be considered as an essential part of the drilling operations. 10200 Construction Methods 10201 General The Contractor shall demonstrate to the satisfaction of the Engineer that his proposed construction methods for the piles do not result in the pile shafts being weakened by contamination of the UNOPS-Afghanistan PART 10-4 Series 10000 –Piling Works NRAP-MoPW concrete, by sectional reduction, by washing out of cement, by breaking during pulling of temporary casings or in any other way, including the construction of neighbouring piles. A) Assumed Procedure The following construction procedure has been assumed in the tender design. The final construction procedure shall be as approved by the Engineer prior to commencing piling operations. 1. Place permanent steel casing, if required, in position and embed casing toe into river bed or firm strata. If no permanent steel casing is specified a sufficient length of temporary steel casing shall be used to stabilise the upper part of the borehole. 2. Bore and excavate inside the steel casing down to casing toe level, or to a level approved, and continue excavation to final pile tip level using either temporary casing under water or using drilling mud. The fluid level inside casings shall at all times be at least 2 metres higher than outside the casings. 3. Carefully clean up all mud or sedimentation from the bottom of borehole. 4. Place reinforcement cage, inspection pipes etc. 5. Concrete continuously under water or drilling fluid by use of the tremie method. 6. Withdraw the temporary boring casing concurrently with concreting to the instructed level. 7. After hardening, break out the top section of the concrete pile to reach sound concrete.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    24 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us