FAA FY 15-17 DBE Goal Approval

FAA FY 15-17 DBE Goal Approval

U.S. Department Federal Aviation Administration Civil Rights Office, ACR-4 of Transportation Western-Pacific Region Headquarters 15000 Aviation Blvd. Federal Aviation Lawndale, CA 90261 Administration Reply to: Alaskan Region MAY 04 2015 Mary Siroky, Division Director Department ofTransportation and Public Facilities Civil Rights Office P.O. Box 196900 Anchorage, Alaska 99519-6900 Dear Ms. Siroky: This letter is in reference to the Disadvantaged Business Enterprise (DBE) fiscal year (FY) 2015 thru 2017 goal that you submitted for the Alaska Department of Transportation and Public Facilities (ADOT&PF) - Central Region ofAirports, Alaska. Based on our review, we have determined that the goal meet the standards in 49 CFR Part 26, Department ofTransportation regulations. The goal is described as follows: FY 15-17 overall DBE goal: 8.3 % DBE Participation To be obtained through 8.3 % Race-Neutral and 0.0 % Race-Conscious means (Covering the period October I, 2014 through September 30, 2017) The above FY 15-17 overall DBE goal covers the attached list of ADOT&PF ' s Central Region of Airports federal funded projects to be advertised during fi scal years 2015 thru 2017. DBE Accomplishments continue to be due annually on December 1 for the previous fi scal year. Accomplishments can be submitted either through our new dbE-Connect system at at www.faa.dbeconnect.com/F AA/ login.asp or by completing the Uniform Report of DBE Awards/Commitments and Payments form and submitting via email to [email protected]. If you need a dbE-Connect user account, please contact Ricky Watson at phone (310) 725-3940. Our blank forms can be found at http://v.rww.faa.gov/about/office org/headquarters offices/acr/bus ent program/. If you have any questions or need assistance, please call Ricky Watson at (310) 725-3940 or email at ricky.watson<@ faa.gov. icky ats n, MBA Northwest Mountain & Alaskan Regions DBE/ACDBE Compliance Specialist Office ofCivil Rights & DBE/ACDBE Compliance Attachment cc: Brad A. Garland, AAL-610 Gabriel Mahns, AAL-610 Dennis Good, ADOT & PF Adam Marks, ADOT & PF 2 ADOT&PF ­ CENTRAL REGION AIRPORTS FFY2015 FFY2016 FFY2017 Project Name Project Name Project Name Akutan Airport (7AK) ­ Bethel (BET) South GA Aniak Airport (AKI) Const - Stg 7 Apron Reconstruction Improvements -- Stage 1 Bethel (BET) - South GA Bethel Airport (BET) - SRE Bethel Airport (BET) North Apron Reconstruction (C) Building Air Taxi Apron & Access Road Rehabilitation Bethel Airport (BET) - RWY Dillingham (DLG) SPB Birchwood Airport (BCV) ­ I TWY Pavement Master Plan (C) Apron & TWY Pavement Rehabilitation -- Stage 2 Rehab (C) Bethel Airport (BET) - SRE Homer Beluga Lake (5BL) Chevak Airport (V AK) ­ Building (C) Float Plane Base lmprov Runway Expansion -- Stg 1 Bethel Airport (BET) Homer Beluga Lake Float Crooked Creek Airport Commercial Apron Plane Base Planning Study (CJX) - Improvements ­ Pavement Rehabilitation ROW Acquisition Coldfoot Airport (CXF) ­ Hooper Bay Airport (HBP) ­ Crooked Creek Airport Improvements Improvements w SRE Bid ­ (CJX) - Improvements (C) Stage 3 Deadhorse (SCC) - ARFF I King Salmon (AKN) Sand Dillingham (DLG) - SPB SREB I Sand I Chemical Bay Storage Bid. Master Plan (C) Addition -- Stage 2 Emmonak (ENM) - SRE Big King Salmon Airport (AKN) King Salmon (AKN) Apt (C) Improvements--Stg 4 (Parallel Improv.-Stg 5 (Parallel TWY) (C) TWY) (C) Galena Airport Lighting Kwigillingok Airport (GGV) King Salmon Airport (AKN) (GAL) Reconstruction - Stg 1 Improvements--Stg 4 (Parallel TWY) Homer (HOM) - ARFF Talkeetna Airport (TKA) ­ Kodiak Airport (ADQ) Vehicle Improve Rehab RWY 11/29, Apron and TWYs (C) Homer Beluga Lake Float Togiak SRE Building Seward Airport (SWD) ­ Plane Base (5bl) - Planning Improvements (C) Study (C) Hooper Bay Airport (HPB) ­ Whittier Airport Master Plan ­ Improvements w SRE Bid - Stg 2 Stage 2 Hughes (HUS) - SRE Building (C) Kiana (IAN) - SRE Building (C) Kodiak Airport (ADQ) Devils Creek Culvert Replacement 3 Pilot Station Airport (OAQ) ­ Relocation Project Amendments State Aviation System Plan Update State Aviation System Plan Update Talkeetna Airport (TKA) ­ Improve (C) Togiak (TOG) - SRE Building (C) Various Airports Aeronautical Surveys Various Airports Minor Surface Improvements Various Airports Obstruction Removal Various Airports Snow Removal, Safety and ADA Equipment Whittier Airport (IEM) ­ Master Plan - Stg 2 (C) .

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    3 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us