World Bank Document

World Bank Document

The World Bank Report No: ISR6846 Implementation Status & Results Tanzania Tanzania - Backbone Transmission Investment Project (P111598) Operation Name: Tanzania - Backbone Transmission Investment Project Project Stage: Implementation Seq.No: 3 Status: ARCHIVED Archive Date: 02-Nov-2011 (P111598) Public Disclosure Authorized Country: Tanzania Approval FY: 2011 Product Line:IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Public Disclosure Copy Board Approval Date 26-Aug-2010 Original Closing Date 31-Mar-2015 Planned Mid Term Review Date 31-Mar-2013 Last Archived ISR Date 02-Nov-2011 Effectiveness Date 30-Mar-2011 Revised Closing Date 31-Mar-2015 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective is to increase availability, reliability and quality of grid based power supply to northern regions of Tanzania. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Public Disclosure Authorized Component(s) Component Name Component Cost Component 1: Construction of the transmission line 134.50 Component 2: Technical Assistance to TANESCO 10.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Public Disclosure Authorized Implementation Status Overview The Project is in its second year of implementation since Board approval and further progress has been made on the implementation of the main transmission line contract. The Pre- Qualification stage of the ongoing procurement process has been completed recently. The lenders to the Project, including IDA ,are currently reviewing the draft final Bidding Documents and it is expected that the bidding of the transmission line contracts will start in June. The Resettlement Action Plan (RAP) has been finalized at the end of last year and Public Disclosure Copy was approved and disclosed in February 2012. The compensation process has started and is expected to be completed in fall 2012, well in advance of the expected contract award of the construction contracts. Page 1 of 7 Public Disclosure Authorized The World Bank Report No: ISR6846 Locations Country First Administrative Division Location Planned Actual Tanzania Singida Region Ulyampiti Tanzania Singida Region Ulemo Tanzania Singida Region Tumuli Tanzania Singida Region Puma Tanzania Shinyanga Region Ngunga Tanzania Shinyanga Region Negezi Public Disclosure Copy Tanzania Iringa Region Nduli Tanzania Ruvuma Region Ndolela Tanzania Mbeya Region Nala Tanzania Singida Region Muhalala Tanzania Singida Region Mtipa Tanzania Dodoma Region Mtera Tanzania Tabora Region Msisi Tanzania Dodoma Region Mpwapwa District Tanzania Dodoma Region Mlowa Tanzania Singida Region Mkwese Tanzania Singida Region Mkonze Tanzania Singida Region Mgori Tanzania Tabora Region Mbutu Tanzania Singida Region Maweni Tanzania Singida Region Manyoni District Tanzania Singida Region Manyoni Tanzania Rukwa Region Manga Public Disclosure Copy Tanzania Iringa Region Makungu Page 2 of 7 The World Bank Report No: ISR6846 Country First Administrative Division Location Planned Actual Tanzania Dodoma Region Makatapora Tanzania Dodoma Region Kisima Tanzania Singida Region Kisaki Tanzania Shinyanga Region Kalitu Tanzania Iringa Region Izazi Tanzania Singida Region Issuna Public Disclosure Copy Tanzania Iringa Region Iringa Rural District Tanzania Singida Region Iramba District Tanzania Singida Region Ikungi Tanzania Tabora Region Igurubi Tanzania Tabora Region Igunga District Tanzania Singida Region Igugunu Tanzania Dodoma Region Ibihwa Tanzania Shinyanga Region Ibadakuli Tanzania Dodoma Region Dodoma Rural District Tanzania Dodoma Region Chipogolo Tanzania Dodoma Region Chikuyu Tanzania Dodoma Region Bahi Tanzania Ruvuma Region Barabarani Tanzania Dodoma Region Bahi District Tanzania Singida Region Unyambwa Tanzania Tabora Region Makomero Tanzania Shinyanga Region Kishapu District Public Disclosure Copy Results Page 3 of 7 The World Bank Report No: ISR6846 Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Reduction in the number of power outages that Number Value 30.00 30.00 10.00 are linked to malfunctions in the Subsystem (in Date 16-Jul-2010 25-May-2012 31-Mar-2015 absolute numbers) Comments This Baseline was recorded Since construction of the during negotiations in July transmission line has not yet 2010 started no improvements in this subsystem have been recorded Cumulative power outages that are linked to Days Value 7.00 7.00 3.00 malfunctions in the Subsystem Date 16-Jul-2010 25-May-2012 31-Mar-2015 Public Disclosure Copy Comments This Baseline was recorded Since construction of the during negotiations in July transmission line has not yet 2010 started no improvements in this subsystem have been recorded Reduction in transmission losses in Subsystem Percentage Value 6.00 6.00 3.00 (in percent) Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded Since construction of the after negotiations in July 2010 transmission line has not yet started no improvements in this subsystem have been recorded Maximum transmission capacity in the Megawatt Value 200.00 200.00 1200.00 Subsystem (MW) Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded Since construction of the during negotiations in July transmission line has not yet 2010 started no improvements in this subsystem have been recorded Intermediate Results Indicators Public Disclosure Copy Page 4 of 7 The World Bank Report No: ISR6846 Indicator Name Core Unit of Measure Baseline Current End Target Power generation projects developed Text Value None Progress made in the Satisfactory progress in development of one new development and financing of permanent power generation generation projects plant of 100MW. Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded TANESCO is expecting the during negotiations in July commissioning of a new 2010 100MW gas fired power station in June 2012. Technical feasibility study for hydropower Text Value None Feasibility Study at Feasibility study completed Public Disclosure Copy project completed Identification Stage Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded The formerly planned FS for during negotiations in July the Rumakali hydropower 2010 project has no longer been requested by TANESCO under this project. Discussions are however ongoing between the Bank and TANESCO to support another hydropower study. Staff trained in environmental and social issues Number Value 0.00 0.00 10.00 (number) Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded Training program at during negotiations in July preparation phase 2010 Timely and satisfactory implementation support Text Value None Contract Negotiations Satisfactorily completion of provided during the construction of the preparation the transmission line transmission line Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded The TER has been cleared by during negotiations in July the Bank and TANESCO is 2010 currently finalizing the Combined evaluation report and is preparing for contract negotiations in June 2012. Substations upgraded Number Value 0.00 0.00 4.00 Date 16-Jul-2010 25-May-2012 31-Mar-2015 Public Disclosure Copy Page 5 of 7 The World Bank Report No: ISR6846 Comments This Baseline was recorded Construction not yet started. during negotiations in July Contracts are expected to be 2010 bid out in August 2012. Transmission line from Singida to Shinyanga Kilometers Value 0.00 0.00 225.00 including FOCL constructed Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded Construction not yet started. during negotiations in July 2010 Transmission line from Dodoma to Singida Kilometers Value 0.00 0.00 217.00 including FOCL constructed Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments Public Disclosure Copy This Baseline was recorded Construction not yet started. during negotiations in July 2010 Transmission line from Iringa to Dodoma Kilometers Value 0.00 0.00 225.00 including FOCL constructed Date 16-Jul-2010 25-May-2012 31-Mar-2015 Comments This Baseline was recorded Construction not yet started. during negotiations in July 2010 Data on Financial Performance (as of 22-Jul-2011) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P111598 IDA-47980 Effective 26-Aug-2010 08-Oct-2010 30-Mar-2011 31-Mar-2015 31-Mar-2015 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P111598 IDA-47980 Effective XDR 101.50 101.50 0.00 0.00 101.50 0.00 Disbursement Graph Public Disclosure Copy Page 6 of 7 The World Bank Report No: ISR6846 Public Disclosure Copy Key Decisions Regarding Implementation The current key priority for the IDA Task team lies in successfully collaborating with the other lenders providing parallel finance to the project. Current priority tasks are (i) completing the review of the draft final bid documents, and subsequently (ii) preparing the Lenders review of the first draft Bid Evaluation Report expected to be received in Q3 CY 2012. In addition, the IDA Task Team, as the Lenders consortium's safeguards supervision coordinator, will closely monitor the implementation of the Resettlement Action Plan (RAP). Restructuring History There has been no restructuring to date. Related Projects There are no related projects. Public Disclosure Copy Page 7 of 7.

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    7 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us