September 2020 Update

September 2020 Update

September 2020 Update Transportation Services Department FEDCo September 1, 20201 2 O-Train South Design Progress • The following submissions have been Issued-For- Construction: – Structures throughout the alignment including Rail Bridges at Airport Parkway, Uplands, Leitrim, Bowesville, Earl Armstrong and Lester; and, – Utility Relocations throughout the alignment. 3 O-Train South Design Progress • The City has received construction drawings of the following project elements: – Airport Station; – Guideway for the Airport Link; and, – Structures throughout the alignment including High Road MUP Bridge, Limebank Road Elevated Guideway, Airport Elevated Guideway, VIA Grade Separation, Rideau River Pedestrian Bridge. 4 O-Train South Design Progress • The City has received final design drawings of the following project elements: – Guideway for the South Extension to Limebank; – Guideway for the existing portion of the line; – Landscape design for the existing line and Airport Link; – Dow’s Lake Tunnel, including Tunnel Ventilation; and – Vehicle elements, including the driver’s cab, interior layout and HVAC System. 5 O-Train South Design Progress • The City has received pre-final design drawings of the following project elements: – Walkley Yard Maintenance and Storage Facility (MSF); – Operational Modelling for the Overall System and the MSF; – Signaling and Train Control System; – Greenboro, Carleton, Mooney’s Bay, Gladstone and Walkley Stations; and, – Communication Systems designs for Greenboro and Carleton Stations and interface control documents for several subsystems on the project. 6 O-Train South Construction Progress • Rock excavation started on Gladstone Station; • Walkley Maintenance and Storage Facility structure construction has commenced; • Work has commenced at Ellwood Diamond grade separation. Caisson construction is underway; • Work has begun on Carleton south MUP; and, • Commenced work at South Keys and Bowesville Stations. 7 O-Train South Construction Progress • Bridge girder installation complete at Airport Parkway, Uplands Drive, Lester Road, and Bowesville Road; • Airport guideway girder installation underway; • Guideway construction is 40% complete between South Keys Station and Limebank/Airport Link; and, • Rail welding has started. 8 Gladstone Station May 2020 August 2020 9 Ellwood Diamond Rail Bridge Sawmill Creek Transitway Bridge Rail Diamond Ellwood Diamond Rail Bridge foundation construction is underway. 10 Walkley Maintenance and Storage Facility Steel structure installation is underway at Walkley Maintenance and Storage Facility. 11 South Keys Station Crews broke ground on South Keys Station in late July. 12 Lester Road Rail Bridge Preparations for deck formwork and rebar are underway at Lester Road Rail Bridge. 13 Leitrim Road Rail Bridge Retaining wall construction is progressing at the Leitrim Road Rail Bridge. 14 Bowesville Road Rail Bridge Crews hoist girders into place at Bowesville Road. 15 Limebank Elevated Guideway Foundation and embankment work are underway at Limebank Road. 16 Airport Parkway Rail Bridge Crews install girders over the Airport Parkway in early July. 17 Uplands Drive Rail Bridge Deck panel work completed at Uplands Drive Rail Bridge in preparations for deck formwork. 18 Upcoming Work • Trench widening to continue between Gladstone Avenue and Beech Street as well as at Carling Station; • Caisson excavation to continue at Ellwood Diamond Rail Bridge (grade separation with VIA Rail); • Walkley Maintenance and Storage Facility steel structure construction to continue; • Hunt Club Rail Bridge construction to commence; and, • Construction to begin at South Keys, Bowesville, and Uplands Stations. 19 Traffic and Mobility Impacts Location Timeline Traffic & Mobility Impacts The existing Trillium Line will be closed to May 2020 to O-Train Line 2 allow upgrades to the line, existing stations August 2022 and the construction of new stations. Multi-use path (MUP) Summer 2020 to Extension of the station will require at Carleton Station Fall 2021 temporary closure of the MUP in this area. Drilling and rock excavation to widen the MUP at Gladstone Summer 2020 rail corridor at Gladstone will temporarily impact access to the MUP in this area. Minor detour to Trillium Pathway north of MUP at Carling Fall 2020 Carling Avenue 20 Traffic and Mobility Impacts (Cont'd) Location Timeline Traffic & Mobility Impacts The temporary closure of the MUP on the west MUP at Walkley Fall 2020 side of the Marriott Hotel and Warehouse Lofts will be required for Walkley Station construction. Signage in place indicating a pedestrian/cyclist Summer 2020 MUP at South Keys detour via a temporary pathway connection to to Fall 2020 the southbound Transitway platform Th existing MUP that passes under the existing Fall 2020 to Brookfield MUP rail line will be modified to allow for rail structure Fall 2021 construction at the Ellwood Diamond. 21 22 O-Train East Design Update • The City is reviewing construction drawings for the following project elements: – Trim Station Park and Ride; – Jeanne D’Arc Station; – Roadway/Drainage Works; and – Utility Expansion Works. 23 O-Train East Design Update (Cont'd) • The City is reviewing final designs for the following elements: – Track and Guideway – Overall Design – Montreal Station Bridge – Existing Bridges – Traction Power System – Overhead Catenary System – Train Control & Signaling 24 O-Train East Design Update • The City has received pre-final design drawings of the following project elements: – Public artwork. 25 O-Train East Construction Progress • Rail bridge from Blair to OR174 centre caisson and pier work in the highway median continues; • Culvert, utility, lane and ramp relocation work is ongoing from Blair Road to Champlain Street to facilitate widening; • Montreal Interchange overpass bridge work: Caisson, pier work, girder installation, pre-cast panel & deck pour complete; • Sir George-Étienne Cartier Bridge wall widening has begun with realignment of eastbound highway lanes; and, • Trim Road Park & Ride parking lot construction ongoing. 26 Highway 174 Roadwork Highway 174 roadwork is progressing between Blair Road and Montreal Road. 27 Highway 174 Roadwork Highway 174 road paving of eastbound lanes, east of Blair Road. 28 Montreal Road Crews hoist girders into place at Montreal Road in late July. 29 Montreal Road Bridge work is progressing at the Highway 174 Montreal Road Interchange. 30 Montreal Road May 2020 August 2020 31 Upcoming Work • Culvert and utility work along Highway 174 to continue at Orléans Boulevard and Champlain Street; • Montreal Interchange overpass installation of barriers and paving of new bridges; • Rail bridge from Blair to OR174 centre median caisson & pier work to begin on east abutment; and, • Sir George-Étienne Cartier Bridge temporary support wall construction. 32 Traffic & Mobility Impacts Location Timeline Traffic & Mobility Impacts Highway 174 February to Continued lane and ramp closures in (Blair Road to late Fall 2020 both directions during off-peak hours. Trim Road) 33 34 O-Train West Design Progress • The following submissions have been Issued-For- Construction: – Various Bridges; – Parkway Tunnel (partial) – Bell and Rogers Utility works along Richmond Road; – Wet Utilities; and, – Sir John A Macdonald Parkway Detour. 35 O-Train West Design Update • The City has received construction drawings of the following project elements: – Parkway Tunnel – Overall Design; – Highway 417 Richmond Road Interchange; – Various Bridges/Structures; – Sir John A Macdonald Overall Design; – Baseline Station – Bus Operator Building; – Roadway/Drainage Works; and, – Utility Expansion Works. 36 O-Train West Design Update • The City has received final design drawings of the following project elements: – Baseline Station; – Lincoln Fields Station; – Track and Guideway (Overall Design); – Existing Bridges; – Utility Expansion Works; – Traction Power System; – Lincoln Fields Temporary Bus Loop; – Overhead Catenary System; and, – Train Control & Signaling. 37 O-Train West Design Update • The City has received pre-final design drawings of the following project elements: – Iris Station; – Dominion Station; – Bayshore Station; – Roadway/Drainage Works; and, – Pedestrian Bridges. 38 O-Train West Construction Progress • Culvert and utility work ongoing: – Sir John A Macdonald Parkway; – Byron Linear Park; – Lincoln Fields; – Connaught Park; – Pinecrest Creek Pond; and, – Moodie Light Maintenance and Storage Facility. • Golden Rod Bridge support of excavation underway; • Sir John A Macdonald detour roadwork has been completed with additional storm sewer work continuing; and, • Byron Linear Park has closed for tunnel site preparation work. 39 O-Train West Construction Progress (Cont'd) • Lincoln Fields bus loop excavation ongoing; • West Split Rail Bridge drill shafts are complete and crews continue to construct bridge piers; • Iris Street culvert bridge and detour roadwork ongoing; and, • Moodie Light Maintenance and Storage Facility culvert bridge caisson work is complete, abutment and drainage work continues. 40 Iris Station / Iris Road Bridge Iris Street culvert bridge and detour roadwork ongoing 41 Moodie Light Maintenance and Storage Facility Abutment and drainage work continues at Moodie LMSF. 42 Connaught Avenue Tunnel Preparatory activities are underway for Connaught Tunnel cut and cover construction. 43 West Split Rail Bridge (Lincoln Fields Flyover) Pier construction is underway at the West Split Rail Bridge (Lincoln Fields Flyover). 44 Lincoln

View Full Text

Details

  • File Type
    pdf
  • Upload Time
    -
  • Content Languages
    English
  • Upload User
    Anonymous/Not logged-in
  • File Pages
    54 Page
  • File Size
    -

Download

Channel Download Status
Express Download Enable

Copyright

We respect the copyrights and intellectual property rights of all users. All uploaded documents are either original works of the uploader or authorized works of the rightful owners.

  • Not to be reproduced or distributed without explicit permission.
  • Not used for commercial purposes outside of approved use cases.
  • Not used to infringe on the rights of the original creators.
  • If you believe any content infringes your copyright, please contact us immediately.

Support

For help with questions, suggestions, or problems, please contact us