English Section

Listed below are the designated areas for the planned maintenance work as for January , 2019:

No. Day & Date Time Location Work Description Affected Areas for Outages

Monday 8.00am to12.00 noon. Kampong Belunu Layong A part of Kampong Belunu Layong, Kampong 1 Wayleave Clearing 14th Jan 2019 1:30 pm to 4.30pm. Mukim Layong, Tanjong Dangar and surrounding area.

Tuesday 8.00am to12.00 noon. A part of Kampong Kiudang from spg 781 to Spg 2 Wayleave Clearing 15th Jan 2019 , Tutong Jln Kiudang and surrounding area.

Spg 196 Kampong Kiudang and surrounding area Wednesday Kampong Kiudang dan Btg Mitus 3 8.00am to12.00 noon. Wayleave Clearing , Jalan Temanok Batang Mitus and surrounding 16th Jan 2019 Mukim Kiudang, Tutong area.

Thursday 8.00am to12.00 noon. Kampong Batang Mitus Spg 3 Jln Kecil Kampong Batang Mitus and 4 Wayleave Clearing 17th Jan 2019 1:30 pm to 4.30pm. Mukim Kiudang, Tutong surrounding area.

Saturday 8.00am to 5.00pm , Transfering of MV/LV distribution networks to new A part of Kampong Rambai, Jln Merimbun and 5 19th Jan 2019 , Tutong. substation. surrounding area.

Monday Kampong Kebia, 6 8.00am to12.00 noon. Wayleave Clearing A part of Kampong Kebia and surrounding area. 21th Jan 2019 Mukim Kiudang, Tutong

Tuesday 8.00am to12.00 noon. Kampong Kiudang A part of Kampong Kiudang and surrounding 7 Wayleave Clearing 22th Jan 2019 1:30 pm to 4.30pm. Mukim Kiudang, Tutong area.

Page 1 Bahasa Melayu

Tersenarai di bawah adalah kawasan yang ditetapkan untuk kerja-kerja penyelenggaraan yang dirancang untuk bulan Januari, 2019:

Kawasan Yang Terjejas Gangguan Bekalan Bil Hari & Tarikh Masa Lokasi Keterangan Kerja Elektrik

Isnin 8.00 pagi hingga 12.00 tenghari Kampong Belunu Layong Sebahagian Kampong Belunu Layong, Kampong 1 Pembersihan laluan rangkaian kawat atas 14hb Jan 2019 1:30petang hingga 4.30 petang Mukim Layong, Tutong Tanjong Dangar dan kawaasan sekitarnya.

Selasa Kampong Kiudang Dari Spg 781 hingga Spg Masuk Jalan Kiudang 2 8.00 pagi hingga 12.00 tengahari Pembersihan laluan rangkaian kawat atas 15hb Jan 2019 Mukim kiudang, Tutong dan kawasan sekitarnya.

Spg 196 Kampong Kiudang dan kawasan Rabu Kampong Kiudang dan Btg Mitus 3 8.00 pagi hingga 12.00 tengahari Pembersihan laluan rangkaian kawat atas sekitarnya dan Jalan Temanok kg Batang Mitus 16hb Jan 2019 Mukim Kiudang, Tutong dan kawasan sekitarnya

Khamis 8.00 pagi hingga 12.00 tenghari Kampong Batang Mitus Sebahagian Spg 3 Jalan Kampong Batang Mitus 4 Pembersihan laluan rangkaian kawat atas 17hb Jan 2019 1:30petang hingga 4.30 petang Mukim Kiudang, Tutong dan kawasan sekitarnya

Sabtu Kampong Rambai, Pemindahan rangkaian pembahagian MV/LV Sebahagian Kg Rambai, Jln Merimbun dan 5 8.00 pagi hingga 05.00 petang 19hb Jan 2019 Mukim Rambai, Tutong. ke substesen yang baru. kawasan sekitarnya.

Isnin Kampong Kebia, Sebahagian Kampong Kebia dan kawasan 6 8.00 pagi hingga 12.00 tengahari Pembersihan laluan rangkaian kawat atas 21hb Jan 2019 Mukim Kiudang, Tutong sekitarnya

Selasa 8.00 pagi hingga 12.00 tenghari Kampong Kiudang Sebahagian Kampong Kiudang dan kawasan 7 Pembersihan laluan rangkaian kawat atas 22hb Jan 2019 1:30petang hingga 4.30 petang Mukim Kiudang, Tutong sekitarnya.

Page 2