STANDARD TEMPLATE, FORM-1, FORM-1A & CONCEPTUAL PLAN & EMP

FOR THE PROPOSED RESIDENTIAL APARTMENTS PROJECT OF SRI. ANUHAR HOMES PVT LTD SURVEY.NO: 324/E & 325, NARSINGI VILLAGE, MANDAL, RANGAREDDY DISTRICT, STATE

Category – 8 (a)

SUBMITTED BY SRI. Y. HARSHAVARDAN REDDY, C/O. M/S. ANUHAR HOMES PVT LTD, H.NO.8-2-293/82/225/A, 3RD FLOOR, ROAD NO 18, , – 500033

PREPARED BY: M/s. SPACE ENVIRO SOLUTIONS (QCI/NABET ACCREDITATION NO: NABET/EIA/1922/IA0043) H. NO: 1-4-69/7, STREET NO:8 , HYDERABAD. TELANGANA – 500007 STANDARD TEMPLATE FOR EVALUATION OF ALL PROJECTS/ ACTIVITIES: -

S.No. Information required Information to be furnished by the proponents 1 Name of the project or activity M/s. Anuhar Homes Pvt Ltd & Others Construction of Residential Apartments. 2 Name of the organization/ owner. Sri. Y. Harshavardhan Reddy 3 Address for communication Sri. Y. Harshavardan Reddy, Authorized Signatory, C/o. M/s. Anuhar Homes Pvt Ltd, H.No.8-2-293/82/225/A, 3rd Floor, Road No 18, Jubilee Hills, Hyderabad – 500033. 4 Telephone numbers 9676314744 5 Email ID of the organization or [email protected] contact person 6 Location of the Proposed project or Sy. No:324/E & 325, activity Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. 7 Appraisal Category (B2 or B1) B (B2) 8 Nearest habitation and distance from Neknampur - 0.8 km (ENE) the project or activity 9 Installed capacity / Production Apartments Area – 73,222.19 Sqm Capacities Amenities Area – 2,262.30 Sqm Parking Area – 27,505.65 Sqm Total Built-up Area – 1,02,990.14 Sqm 10 Specify the Fuel (Coal / CNG / Not Applicable biomass/Others) and quantity required 11 Details of Land use/Land Cover The proposed project activity is construction of Residential Apartments. The site area is falling in HMDA area. The present land is waste land and is not used for any productive purpose. 12 Occupancy, ownership of the land in Private Land which the activity is proposed: (Government land / Private land / Forest land /Revenue land /Temple land /leased land/ land belongs to other Department) 13 If it is a Forest land, the following None details shall be furnished: (Whether it is a Reserved forest / Protected forest / Demarcated forest / National Parks/ Sanctuaries / any land in possession of Forest Department.) (The village map with Sy. No. indicating nearest forest boundary line from the site shall be enclosed) 14 Total investment of the 112.0 Crores project/activity. a. Funds allocated for EMP (capital Capital Cost – 125.0 Lakhs cost and recurring cost per annum) Recurring Cost – 22.0 Lakhs 15 Brief description of the project with Domestic waste water is treated in sewage treatment special reference to specific pollution plant and the treated water will be used for gardening, and its control measures. flushing and washing. Adequate stack height is provided for effective dispersion pollutants from DG Set. 16 Compliance report on the following : i Status of compliance of the None conditions and environmental safeguards stipulated in the earlier clearance letters. ii Details of the court cases, if any, None pending in any Court of Law against the project as well as any directions passed by the Court relating to the project directly or indirectly. iii Details of the notices, if any, given to None the project under Section 5 of the Environmental (Protection) Act, 1986 and Section 18 of the Air (Prevention & Control of Pollution) Act, 1981. 17. Whether the project attracts the No provisions laid under the OM dt.16.11.2010 issued by the MoE&F, GOI, w.r.t. violation of EIA Notification, 2006 and its amendments there of? (Yes / No) Present stage and status of the New Project and applied for EC Project : 18 Name of the Consultant: M/s. Space Enviro Solutions, Hyderabad.

FORM-1

I) Basic information

S.No. Item Details

1 Name of the project/s M/s. Anuhar Homes Pvt Ltd & others Construction of Residential Apartments 2 S.No. in the schedule The project is categorized under 'B-2' under item 8(a) of Schedule - Gazette Notification dated 14th September 2006 and subsequent amendments issued by MoEF&CC,

New Delhi. 3 Proposed capacity /area/ length/ tonnage Net Plot Area – 16,691.92 Sqm to be handled/command area/lease area/ Apartments Area – 73,222.19 Sqm No of the well to be drilled Amenities Area – 2,262.30 Sqm Parking Area – 27,505.65 Sqm Total Built-up Area–1,02,990.14 Sqm No.of Flats - 510 4 New/Expansion /Modernization New 5 Existing capacity/Area etc. Not Applicable 6 Category of project A or B Category B ( ‘B2’) 7 Does it attract the general condition? This project does not attract general conditions. If yes please specify 8 Does it attract the specific condition? This project does not attract specific conditions. If yes please specify 9 Location Plot/ survey /Khasra no Sy. No:324/E & 325, Alakapur Township, Village Narsingi Village, Tehsil/Mandal Gandipet Mandal, District Rangareddy District, State Telangana State. 10 Nearest Railway Station/Airport along Hitech city – 9.6 Km (NE) with the distance in km Rajiv Gandhi International Airport - 17.0 km (SE) 11 Nearest Town, City, District -1.8 km (NW) Headquarters along with distances in km. Shaikpet – 2.8 km (NE) Samshabad – 14.0 km (S) 12 Village Panchayats, Zilla Parishad, Narsingi Village Municipal Corporation, Local body Gandipet Mandal, (complete postal Address with telephone Rangareddy District no. to be given) 13 Name of the applicant Sri. Y.Harshavardan Reddy 14 Registered address Sri. Y. Harshavardan Reddy, Authorized Signatory, C/o. M/s. Anuhar Homes Pvt Ltd, H.No.8-2-293/82/225/A, 3rd Floor, Road No 18, Jubilee Hills, Hyderabad – 500033. 15 Address of the correspondence Name Sri. Y. Harshavardan Reddy, Designation /owner/partner/CEO Authorized Signatory, Address C/o. M/s. Anuhar Homes Pvt Ltd, H.No.8-2-293/82/225/A, 3rd Floor, Road No 18, Jubilee Hills, Hyderabad Pin code 500033. E-mail [email protected] Telephone no 9676314744 16 Details of Alternative Sites examined if No Alternative Sites are examined any. Location of these sites Should be shown on a Topo sheet. 17 Interlinked Projects Not Applicable 18 Whether separate application of Not Applicable interlinked projects has been submitted 19 If yes, date of submission Not Applicable 20 If no reason Not Applicable 21 Whether the proposal involves approval / clearances under: if yes, details of the same and their status to be given. No (a) The Forest (conservation) Act, 1980? (b) The Wild life (protection)Act, 1972? No (c) The C.R.Z notification, 1991? No 22 Whether there is any Government No order/policy relevant/relating to the site? 23 Forest land involved (Hectares) No 24 Whether there is any litigation pending No litigation is pending against the project in any court against the project and/or land in which of law to the best of knowledge. the project is propose to be set up? (a)Name of the court (b)Case no. (c) Orders/directions of the court, if any and its relevance with the proposed project 2 (II) Activity

1.0 Construction, operation or decommissioning of the Project involving actions, which will cause Physical Changes in the locality (topography, land use, changes in water bodies, etc.). S.No. Information / Checklist Yes/ Details thereof (with approximate confirmation No quantities /rates, wherever possible ) with sources of information data

1.1 Permanent or temporary change in land Yes The proposed project activity is Residential use, land cover or topography including Apartments project. The site area is located in increase in intensity of land use (with HMDA area. The present land is waste land respect to local land use plan) and is not used for any productive purpose. The proposed project activity shall enhance the land cover. Topography: The present topography of the site is almost flat: Due to the project the topography of the project area will change. However, the drainage pattern will remain as per the existing pattern. 1.2 Clearance of existing land, vegetation and No There is 1 Tree that exists within the site. buildings? which will be removed according to the requirement and the same will be replaced by planting 1:3 ratios as per the guidelines with permission. Buildings: There are no structures, hence not applicable. 1.3 Creation of new land uses? Yes There will be a creation of new land use, which will be as per the approval of the HMDA. 1.4 Pre-construction investigations e.g. bore Yes There will be no physical impact on the locality holes, soil testing? due to soil testing or other pre-construction investigations. 1.5 Construction Works? Yes Construction of Residential Apartments 1.6 Demolition Works? No No demolition work is involved in the site. 1.7 Temporary sites used for construction No Temporary shelters for construction workers works or housing of construction works? are not required as majority of labor will be hired from the surrounding locations. 1.8 Above ground buildings, structures or Yes The project will involve construction of earthworks including linear structures, Residential Apartments. cut and fill or excavations This will add to the change in the localized

3 physical environment. In the post construction phase, tree plantation and landscaped areas will be provided which will enhance the aesthetic beauty of the area. 1.9 Underground works including mining or No Not Applicable tunneling? 1.10 Reclamation Works? No Not Envisaged. 1.11 Dredging? No Not Applicable 1.12 Offshore structures? No Not Applicable 1.13 Production and manufacturing processes? No No manufacturing activity. Activity is Construction of Residential Apartments. 1.14 Facilities for storage of goods or Yes Temporary storage shed will be provided at materials? project site for the storage of construction materials. After the structural erection of the building the sheds will be removed permanently. 1.15 Facilities for treatment or disposal of Yes The details of solid and liquid waste generated solid waste or liquid effluents? & their disposal during the construction and post construction phase are tabulated as: Construction Phase: S.No Source Nature of Waste Treatment/ Disposal 1 Site preparation Solid waste: Excavated soil Reused within the project site activities for surface leveling. 2 Construction Solid waste: Construction waste activities Recyclable waste Sold to Authorized recyclers . Inert waste (Brick, masonry, Used for road making, & land Concrete, etc.) filling within the project site. 3 Construction Solid waste:(Total =38 kg / day) Biodegradable will be sent to Workers Municipal Waste Management facility sites. Non – biodegradable will sent to SPCB Authorized Recyclers. Domestic waste water Will be sent to temporary septic tank. Post Construction Phase: S. No Source Treatment/Disposal 1 Waste Water 319.0 KLD of waste water is Waste water is treated in generated STP of capacity 385.0 KLD. Treated water will be used 4 for Flushing, Washings & Gardening. 2 Solid Waste Garbage – 1,390.0.0 Kgs/day Biodegradable waste is S.T.P. Sludge – 32.0 Kgs/day treated in Organic waste converter. Non – biodegradable will sent to SPCB Authorized Recyclers. After proper treatment the sludge is used as manure.

1.16 Facilities for long term housing of No Manpower requirement of operational operational workers? workers is nominal and will be recruited from surroundings therefore no long term housing facilities are envisaged. 1.17 New road, rail or sea traffic during Yes During construction phase, traffic will construction or operation? increase due to inward and outward movement of raw materials. In the operation phase, there will be slight increase in the traffic levels during peak hours. 1.18 New road, rail, air waterborne or other No There is no new road, rail, air borne transport infrastructure including new or transport infrastructure required for the altered routes and stations, ports, project. airports etc? 1.19 Closure or diversion of existing No There will be no closure or diversion of transport routes or infrastructure leading existing transport routes or infrastructures to changes in traffic movements? leading to changes in traffic movements. 1.20 New or diverted transmission lines or No There will be no diversion of Transmission pipelines? and line and pipelines. 1.21 Impoundment, damming, culverting, No The proposed development will not disturb realignment or other changes to the the water courses or Aquifers. hydrology of watercourses or aquifers? Rain Water Harvesting pits are proposed to recharge the Ground Water. 1.22 Stream crossings? No There are no stream crossings in the proposed site. 1.23 Abstraction or transfers of water from Yes Water requirement of the project will be ground or surface waters? met from Public Supply & Ground Water. 1.24 Changes in water bodies or the land No The development will be carried out with surface affecting drainage or run-off? no disturbance to major water or the land surface, affecting drainage or runoff. 1.25 Transport of personnel or materials for Yes Transportation of personnel or material will construction, operation or be by trucks on road. 5 decommissioning? 1.26 Long-term dismantling or No Restoration works for the project on long decommissioning which could have an term will be an ongoing activity which will impact on the environment? not have any impact on physical environment. 1.27 Ongoing activity during decommissioning No There is no decommissioning activity. which could have an impact on the environment? 1.28 Influx of people to an area in either Yes During the construction phase, there will be temporarily or permanently? inward and outward movement of local labour in the construction site, this will be an ongoing temporary activity and will not call for permanent influx of people. However, during the post construction phase, there will be regular movement of residents, visitors, staff and related personals. 1.29 Introduction of alien species? No No alien species will be introduced. Only selected local and native plant species will be planted. 1.30 Loss of native species or genetic No None diversity? 1.31 Any other actions? No None 2.0 USE OF NATURAL RESOURCES for construction or operation of the Project (Such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): S.No. Information /Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with sources of information data 2.1 Land especially undeveloped or No Net Plot Area – 16,691.92 Sqm agricultural land (ha) 2.2 Water (expected source & competing Yes Total Water Requirement – 375.0 KLD users) Unit : KLD Fresh Water – 240.0 KLD Recycle Water from S.T.P – 135.0 KLD 2.3 Minerals (MT) Yes Marble, Granite, etc. will be used as per the requirement. 2.4 Construction material – stone, Yes Construction materials like coarse aggregates, and / soil (expected source- aggregate, fine aggregate, granite, dolhur MT) stone, marble, bricks, sand, cement, steel will be used.

6 The raw materials will be sourced from local dealers & traders. 2.5 Forests and timber (source – MT) Yes Timber will be used for windows and doors. The required timber will be procured from local traders. 2.6 Energy including electricity and fuels Yes Power Required: 3200 KVA (source, competing users) Unit: fuel Source: Telangana State Central Power (MT), energy (MW) Distribution Company Limited (TSCPDCL). Back-up power: 4 x 500 KVA & 1 x 82.5 KVA DG set for emergency during power failures. Fuel: HSD required @500 Liters will be sourced from local traders 2.7 Any other natural resources (use No Not Applicable appropriate standard units) 3.0 Use, storage, transport, handling or production of substances or materials which could be harmful to human health or THE ENVIRONMENT or raise concerns about actual or perceived RISKS TO HUMAN HEALTH. S.No. Information /Checklist confirmation Yes/ Details thereof (with approximate No quantities /rates, wherever possible ) with sources of information data 3.1 Use of substance or materials, which are No There will be storage of HSD to the tune of hazardous (as per MSIHC rules) to 500 Liters (approx.) in the project, which will human health or the environment (flora, be stored in the inbuilt storage tanks of DG fauna, and water supplies) sets.

The significant hazard due to the same will be negligible as the exposure level will be confined within a small area in the consequence of unforeseen hazard. 3.2 Changes in occurrence of disease or No The waste water generated to the tune will be affect disease vectors (e.g. insect or treated in STP of capacity 385.0 KLD based on water borne diseases) SBR technology. Further, storm water network will be well designed to leave no stagnant water pockets, at any point of time. The storm water line will not cross wastewater line. The biodegradable as well as non- biodegradable waste will be collected at earmarked places and proper sanitization will be done to prevent any disease vector.

7 3.3 Affect the welfare or people e.g. by No The living conditions of the public of the nearby changing living conditions? areas will not be affected due to upcoming of the project.

The solid waste will be suitably treated, while the liquid effluent will be treated in the sewage treatment plant of adequate capacity. 3.4 Vulnerable groups of people who could No None be affected by the project e.g. hospital patient’s children, the elderly etc., 3.5 Any other causes No None

4.0 Production of SOLID WASTES during construction or operation or decommissioning (MT/ month) S.No. Information /Checklist confirmation Yes/ Details thereof (with approximate quantities /rates, wherever possible) No with sources of information data 4.1 Soil, overburden or mine wastes No There is no activity which may generate spoil, overburden & mine waste. 4.2 Municipal waste (domestic and or Yes Construction Phase: commercial wastes) About 38 kg/day solid waste will be generated, which will be disposed – off suitably. Operational Phase: About 1,390.0 Kgs/day solid waste will be generated; a system of segregation at source will be implemented. Colour coding of the bins will be provided for different types of wastes. 4.3 Hazardous wastes (as per Hazardous No Construction Phase: Waste Management Rules) No hazardous waste will be generated. Provisions will be made to segregate the waste at source. Waste will be sent to authorize recyclers. Yes Post Construction Phase: Used Oils from D.G. Set – 300 LPA Used Batteries – 5 no’s/year Will be sent to authorized recyclers. 4.4 Other industrial process wastes No Not Applicable

4.5 Surplus product No Not Applicable

8 4.6 Sewage sludge or other sludge from Yes About 32.0 Kg/day sludge will be generated effluent treatment from STP, which will be used as manure in landscaping after proper treatment. 4.7 Construction or demolition wastes Yes During construction some amount of construction debris may be generated which will be segregated and whatever re-saleable will be sold to supplier and rest waste will be used for filling up of low lying areas and development of internal roads and boundary walls etc. 4.8 Redundant machinery or equipment No Most of the equipment used for the construction will be hired. Surplus equipment and material will be disposed off to the appropriate agencies. 4.9 Contaminated soils or other materials No No soil contamination is anticipated as the proposed project is a construction project all the waste generated will be in the form of solid waste of reusable nature. 4.10 Agricultural wastes No There will be no agriculture waste. 4.11 Other solid wastes No There will be no other solid waste. 5.0 Release of pollutants or any hazardous, toxic or noxious substances to AIR (Kg/hr)

S.No. Information /Checklist confirmation Yes/ Details thereof (with approximate quantities /rates, wherever possible) No with sources of information data 5.1 Emissions from combustion of fossil fuels Yes The source of emissions will be from D.G. from stationary or mobile sources set of cumulative capacity of 4 x 500 KVA & 1 x 82.5 KVA will be provided in case of power cuts or failure.

CPCB certified D.G. Sets for low emission standards will be installed so as to maintain the emission within the norms etc. Further, the DG sets will be provided with a safe stack height of 5.0 m above the roof of DG room/above the building to keep the emissions within the permissible norms. Low Sulphur content fuel will be used to keep the emissions within the permissible norms.

Mobile Sources: There will be emissions from the exhausts of

9 the vehicles in the construction as well as operational phase.

The engines of the transport vehicles will be switched off while they are waiting to access the site and while loading & unloading. Idle construction equipment will be throttled down or switched off. PUC certified vehicles will be used for bringing construction materials.

In the operational phase effective green belt will help to contain the emissions within the permissible range. The residents in the post construction phase will be encouraged for carpooling & the use of mass transportation services. Further, the project is situated within the city itself, which will help to reduce the emissions in terms of commutation & associated vehicular exhausts. 5.2 Emissions from production processes No There is no production process in the project. 5.3 Emissions from materials handling Yes The fugitive emission expected from including storage or transport. construction phase will be dust arising from material handling and vehicular emission from transport vehicles. These include the emissions due to idling of the vehicles during loading and unloading activities.

Construction waste will be reutilized within the site itself to reduce the emissions during transportation. Further, idling of the vehicles will be reduced to the extent possible.

The haul road will be made moist to avoid the air borne dust & PUC certified vehicles will be used. 5.4 Emissions from construction activities Yes The fugitive dust emission sources are: including plant and equipment • Excavation • Haul road movements • Construction

10 • Material Handling • Finishing

The sources of air emissions from the above

activities are PM10, PM2.5, NOx, HC, etc.

Mitigation measures like minimizing drop heights of debris, enclosures, covered transport, use of barriers, wetting surface, plantation, avoid idling of vehicles etc. 5.5 Dust or odors from handling of materials Yes • Water spraying to prevent dust pollution including construction materials, sewage from different sources of construction. and waste. • Speed restriction of all the vehicles approaching the site and within the site. • All transportation vehicles will be suitably covered with tarpaulin & overloading of the vehicles will be avoided. • Covering of the construction site on all four sides to a considerable height to prevent dust emissions and other pollutants to the surrounding environment. • Ensuring vehicles stick to the access track to prevent mud and dirt being deposited on roads. • Covering loads to limit materials or litter blowing off and reducing smells. • Proper Sewage Treatment System and Solid Waste Management System will be provided and will be well maintained so as to avoid the problems of odor. 5.6 Emissions from incineration of waste No None 5.7 Emissions from burning of waste in open No No material waste will be burnt in open air. air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No None 6.0 Generation of Noise and Vibration, and Emissions of Light and Heat: S.No. Information /Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with sources of information data 6.1 From operation of equipment e.g. Yes Noise may be generated from the engines, ventilation plant, crushers construction equipment’s and operation of DG sets. 11 The following measures will be taken: • CPCB certified DG sets conforming to the standards for noise will be used. • Temporary noise barriers will be provided all around the project site. • Light pollution will be restricted using cut- off shield fixtures on site. • Ensuring that all lights strike a surface directly and do not point at the sky or surrounds. It will be kept minimum, consistent with safety and security. • EMF radiations at site will be reduced by ensuring that construction supply connection is adequate for the task, using line filters on the mains connecting cables, installing power factor correction equipment. • An area of about 1,774.37 Sqm will be under landscape/green belt which will help to contain the emissions within the project sites. 6.2 From industrials or similar processes No None 6.3 From construction or demolition Yes During construction drilling, crushing, concrete mixing activities will create noise and vibrations. These will be temporary in nature and will be phased out once the construction is over. There are no demolition works. Ready mix concrete will be used to reduce the noise & vibrations due to the operation of concrete mixer truck, etc. 6.4 From blasting or piling No Blasting operations are not envisaged in the proposed project.

However, noise from piling activities shall be as follows: 100 dB (A) at 50 ft from source 124 dB (A) at 3.3 ft from source Temporary noise barrier will be provided all around the project site to contain the noise within the permissible norms.

12 6.5 From construction or operational traffic. Yes During the construction phase and post construction phase, noise will be generated from movement of vehicles. The construction site will be shielded to avoid the noise propagation. In the post construction phase, the efficient green belt planning will reduce the noise propagation. Proper traffic management is an integral part of design which helps in reducing the noise & vibrations and other emissions due to traffic movements. Proper traffic management plan in line with the provisions of NBC- 2016 will be constituted. 6.6 From lighting or cooling systems No There will be change in the light pollution level of the project area. Urbanization activity leads to massive lighting in the area. In this project provisions are made to use object focused light using energy efficient lights and prominent lights will be solar powered. 6.7 From any other sources No None

7.0 Risks of Contamination of Land or Water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea : S.No. Information /Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with sources of information data 7.1 From handling, storage, use or spillage of Yes The project will handle and storage of HSD hazardous materials up to 500 Liters. Inbuilt storage facility in DG sets will be as per statuary norms. 7.2 From discharge of sewage or other No The waste water generated will be treated in effluents to water or the land (expected STP. Sewage will not be discharged into the mode and place of discharge ) open surfaces causing the contamination of ground water. 7.3 By deposition of pollutants emitted to air No During construction, there will be fugitive into the land or into water emissions generated from excavation, material transfer, construction operations, finishing operations, road construction, exhaust from vehicles, and stationary

13 sources, etc. 7.4 From any other sources No There will not be any other sources, which will contaminate land & water resources. 7.5 Is there a risk of long term build-up of No There will not be building -up of pollutants in pollutants in the environment from these the environment from this project. sources? 8.0 Risk of accidents during construction or operation of the Project, which could affect human or the environment S.No. Information /Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with sources of information data 8.1 From explosions, spillages, fires etc from Yes There will be no hazardous substance or storage, handling, use or production of chemical used in the proposed project. hazardous substances However, spent oil from DG sets and transformers will be generated which will be stored in the spent oil tank prior to disposal to actual users at earmarked places. The fuel used in the DG sets will be stored in the inbuilt storage tanks which will be designed to meet out all safety norms. Required fire fighting arrangements will be provided in the project. 8.2 From any other causes Yes The major risks involved in the project would be working at different construction heights and mishaps due to human errors, bad construction practices and associated electric hazards. All Safe construction practices & precautionary measures will be adopted and use of PPE will be mandatory. However, to meet out the minor incidences and accidents first aid measures at site will be provided. All safety measures will be in place prior to commencement of operations so as to avoid any risk of human life. 8.3 Could the project be affected by natural No The project site is located at a higher disasters causing environmental damage elevation and the seismic zone for the (e.g. floods, earthquakes, landslides, project area is Zone-II, which is considered cloudburst etc)? safe.

14 9.0 Factors which should be considered (such as consequential DEVELOPMENT) which could lead to ENVIRONMENTAL EFFECTS or the potential for cumulative impacts with other existing or planned activates in the locality S.No. Information /Checklist confirmation Yes/No Details thereof (with approximate quantities /rates, wherever possible) with sources of information data 9.1 Lead to development of supporting. Yes The proposed project is a construction of utilities, ancillary development or Residential Apartments Project. So it leads development stimulated by the project to development of supporting facilities and which could have impact on the Yes ancillary & related activities. environment e.g.:  Supporting infrastructure (roads, power supply, waste or waste Yes Existing water treatment, etc.)  Housing development No  Extractive industries No  Supply industries No  Other 9.2 Lead to after use of the site, which could No None have impact on the environment 9.3 Set a precedent for later developments No --- 9.4 Have cumulative effects due to proximity No None to other existing or planned project as with similar effects ) (III) Environment Sensitivity

S.No. Areas Name/ Aerial distances (within 15 km.) Identity Proposed project location boundary

1. Areas protected under international Yes Ecologically Sensitive Areas: conventions, national or local legislation Mrugavani National Park-2.6 km(SW) for their ecological, landscape, cultural or Kasu Brahmanandareddi National Park-6.0 km other related values (NE) Nehru Zoological Park-8.3 km(ESE) Historical Monuments: Qutubshahi Tombs-3.4 km (NE) -3.5 km (E ) Chilkur Balaji Temple- 7.7 km (SW ) 2. Areas which are important or sensitive Forests Chilkur PF-1.9 km (S) for ecological reasons – Wetlands, water Kottaguda RF-7.4 km (N) courses or other water bodies, coastal Nehru Zoological Park (RF)-8.3 km(ESE) zone, biospheres, mountains, forests

15 Water Neknampur Cheruvu-0.2km (SE) Bodies Musi River-0.6 km (S) Ibrahim Cheruvu-0.7 km (E ) Muskin Cheruvu-2.3 km (NNW) Battemma Cheruvu-1.5 km (NNW) Pedda Cheruvu-4.2 km(NNE) Musa River-4.7 km(ESE) Langar houz cheruvu- 5.0 km (E ) Himayat Sagar-5.0 km(SSW) Osman Sagar-5.3 km(W) Durgam Cheruvu-5.1 km (NNE) Mir Alam Cheruvu-7.7 km(ESE) 3. Areas and by protected, important or No None sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration 4. Inland, coastal, marine or underground No None waters 5. State, National boundaries No None 6. Routes or facilities used by the public for No None access to recreation or other tourist, pilgrim areas 7. Defense installations Yes Army Training Centers-2.8km (SE) 8. Densely populated or built-up area Yes Narsingi -0.8 km (NW) 9. Areas occupied by sensitive man-made Yes Narsingi -0.8 km (NW) land uses (hospitals, schools, places of worship, community facilities) 10. Areas containing important, high quality Forests Chilkur PF-1.9 km (S) or scarce resources (ground water Kottaguda RF-7.4 km (N) resources, surface resources, forestry, Nehru Zoological Park (RF)-8.3 km(ESE) agriculture, fisheries, tourism, minerals) Water Neknampur Cheruvu-0.2km (SE) Bodies Musi River-0.6 km (S) Ibrahim Cheruvu-0.7 km (E ) Muskin Cheruvu-2.3 km (NNW) Battemma Cheruvu-1.5 km (NNW) Pedda Cheruvu-4.2 km(NNE) Musa River-4.7 km(ESE) Langar houz cheruvu- 5.0 km (E ) Himayat Sagar-5.0 km(SSW) Osman Sagar-5.3 km(W) Durgam Cheruvu-5.1 km (NNE) Mir Alam Cheruvu-7.7 km(ESE)

16 11 Areas already subjected to pollution or No None environmental damage. (those where existing legal environmental standards are exceeded) 12. Areas susceptible to natural hazard None The area is classified as Zone II (Least- which could cause the project to present Moderate Damage Risk Zone) as per the environmental problems (earthquakes, BIS classification. subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) IV. Proposed Terms of Reference for Not Applicable EIA Studies B-2 Category Project

17

FORM-1 A (Only for construction projects listed items 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT:

S.No. ITEM DETAILS 1.1 Will the existing land use get M/s. Anuhar Homes Pvt Ltd & Others significantly altered from the Construction of Residential Apartments project that is not consistent with Sy. No:324/E & 325, Alakapur Township, the surroundings? (Proposed Narsingi Village, Gandipet Mandal, landuse must conform to the Rangareddy District, approved Master Plan / Telangana State. Development Plan of the area. Change of landuse if any and the The existing land use will not get significantly statutory approval from the altered from the project that is not in consistent competent authority be submitted). with the surroundings as the site is earmarked for Attach Maps of (i) site location, (ii) Residential Apartments Development as per surrounding features of the HMDA. proposed site (within 500 meters) Net Plot Area – 16,691.92 Sqm and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. 1.2 List out all the major project The major requirements of the project is requirements in terms of the land summarized as below: area, built up area, water 1. Net Plot 16,691.92 Sqm consumption, power requirement, area 2. Built-up connectivity, community facilities, Apartments Area – 73,222.19 Sqm area Amenities Area – 2,262.30 Sqm parking needs etc. Parking Area – 27,505.65 Sqm Total Built-up Area – 1,02,990.14 Sqm No.of Flats - 510

3. Water Total Water Requirement – 375.0 consumptio KLD n Fresh Water – 240.0 KLD Recycle Water from S.T.P – 135.0 KLD

1 4. Power 3200 KVA requirement D.G. Set – 4 x 500 KVA & 1 x 82.5 KVA 5. Connectivit The project is well connected with y facilities the following: Hitech city – 9.6 Km (NE) Rajiv Gandhi International Airport - 17.0 km (SE)

1.3 What are the likely impacts of the There will be minor impacts during construction proposed activity on the existing activity of the proposed project. facilities adjacent to the proposed Community facilities will be enhanced during site? (Such as open spaces, construction period due to influx of skilled and community facilities, details of the unskilled labor in the area. existing landuse, disturbance to the The value of waste land will be increased. As the local ecology). project does not involve the clearance of any existing structures or deforestation there will not be any effect on the surroundings or on the environment. The area allocated for greenbelt is 1,774.37 Sqm 1.4 Will there be any significant land The area is not prone to any land disturbance and disturbance resulting in erosion, no evident history of the same is available. subsidence & instability? (Details of Soil Type – Red Soil soil type, slope analysis, Slope Analysis: vulnerability to subsidence, The topography of the site is almost flat. Due to the seismicity etc may be given). project the topography of the project area will change. However, the drainage pattern will remain as per the existing pattern. Vulnerability to Subsidence: There is no subsidence reported in the area. Seismicity – Zone – II as per the GSI 1.5 Will the proposal involve alteration No, there is no change in the overall natural of natural drainage systems? (Give drainage system. However, the internal run off details on a contour map showing drainage is channelized to the well connected the natural drainage near the network of storm water drains. proposed project site) 1.6 What are the quantities of The cut and fill material in the project site is nearly earthwork involved in the at par and hence the need for movement of soil to construction activity - cutting, and from the proposed site is not anticipated. filling, reclamation etc.? (Give details of the quantities of earthwork involved, transport of

2 fill materials from outside the site etc.) 1.7 Give details regarding water supply, Water supply: waste handling etc during the The domestic water demand during construction construction period. phase will be about 50-70 KLD, which will be met from water tankers The waste water generated will be sent to septic tank followed by soak pit. Solid waste: All construction wastes generated during construction will be used within the site itself for filling the floors, roads, aggregate for mortar etc. to the extent feasible. Remaining will be sent to the agency for proper disposal. 38.0 kg/day of solid waste will be generated during construction phase and will be sent to Municipal Facility. 1.8 Will the low lying areas & wetlands There are no wetlands and low lying areas around get altered? (Provide details of how the site. low lying and wetlands are getting modified from the proposed activity) 1.9 Whether construction debris & The typical waste will compute to the 25% of the waste during construction cause inventorisation and this will consists as stated health hazard? (Give quantities of under: various types of wastes generated S.No Particulars Approx. Disposal during construction including the Qty %. construction labor and the means 1. Wood 8 Sold to vendors of disposal) 2. Metal scrap 4 Sold to vendors 3. Containers 3 Sold to vendors 4. Inert waste 6 Disposal site 5. Electronic scrap 2 Sold to vendors 6. Oils 1 Sold to vendors 7. Chemicals, 1 Disposal site adhesives, bitumen *NBC 2016.

3 2.0 WATER ENVIRONMENT: S.No ITEM DETAILS 2.1 Give the total quantity of water The daily fresh water requirement for the requirement for the proposed project proposed project will be 240.0 KLD with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. 2.2 What is the capacity (dependable flow Water will be sourced from Municipal or yield) of the proposed source of Supply/Ground Water. water? 2.3 What is the quality of water required, NA in case, the supply is not from a Water will be sourced from Municipal Water municipal source? (Provide physical, Supply. chemical, biological characteristics with class of water quality) 2.4 How much of the water requirement The project will generate 319.0 KLD of waste can be met from the recycling of water, which will be treated in STP. The reusable treated wastewater? (Give the details water available after treatment will be used for of quantities, sources and usage) flushing, gardening, washing requirements and excess water will be discharged to sewers. 2.5 Will there be diversion of water from No other users? (Please assess the Water will be sourced from Public Water impacts of the project on other Supply/Bore Well. existing uses and quantities of consumption) 2.6 What is the incremental pollution The waste water generated will be to the tune of load from wastewater generated from 319.0 KLD. The waste water generated will be the proposed activity? (Give details of treated in sewage treatment plant based on SBR the quantities and composition of technology of capacity 385.0 KLD. wastewater generated from the proposed activity) 2.7 Give details of the water Elaborate plans have been made for channelizing requirements met from water the storm water by constructing water storage harvesting? Furnish details of the tanks. After treatment the water is used for non- facilities created. potable purposes. In order to minimize the surface runoff loss, groundwater recharging through groundwater recharge pits at the project

4 site has been planned. The rainwater is proposed to be channelized for storage in reservoirs to be used for project needs after due treatment and also for groundwater recharging through the recharge pits. The rainwater is proposed to be channelized for storage in reservoirs to be used for project needs and also for groundwater recharging through the Harvesting pits. 15 no’s of Rain Water Harvesting pits are provided at four corners of the site. The pits are designed as per the specifications of CGWB. 2.8 What would be the impact of the land The project will involve construction of rooftop & use changes occurring due to the paved areas and hence, quantity of runoff will proposed project on the runoff increase due to reduced infiltration & increase in characteristics (quantitative as well as surface run off coefficient in post construction qualitative) of the area in the post phase as compared to the pre-construction phase. construction phase on a long term The overflow during abnormally heavy rains will basis? Would it aggravate the follow the run off pattern. The proposed problems of flooding or water logging rainwater structures have been designed for in any way? accommodating peak rainfall intensity, which will not aggravate the problem of flooding in the project area. The run-off from roof top, paved and landscaped areas will be used for ground water recharge. Provisions of capturing the surface runoff to the extent of 100% will be done. 2.9 What are the impacts of the proposal No Impacts will be on the ground water the on the ground water? (Will there be required water will be supplied by Municipal tapping of ground water; give the Supply and the treated water is used for gardening details of ground water table, & flushing. Rain water harvesting structures will recharging capacity, and approvals be provided in the site to tap the rain water obtained from competent authority, if which in turn recharges the ground water table. any) 2.10 What precautions/measures are taken There are effective measures adapted to reduce to prevent the run-off from the storm water run-off from the construction construction activities polluting land & site- aquifers? (Give details of quantities  Ensuring vehicles stick to the access track. and the measures taken to avoid the  Cleaning all mud and dirt deposited on roads adverse impacts) from construction-related activities.  Stabilizing a single entry/exit point to ensure sediment is not tracked off site-this also

5 increase site durability during wet weather.  Excavation work will not be carried out during monsoon season.  Constructing a fence around the site to trap sediment whilst allowing water to flow through.  Diverting up-slope water with turf and not mixing mortar in locations that will drain into storm water system.  Preventing wastewater from brick cutting activities and stockpiles entering the storm water system.  Construction material will be stored at the earmarked places and will be covered with a temporary shed ensuring that no leachate or spoilage of land occurs.  Curing water will be sprayed and, after liberal curing, all concrete structures will be painted & covered with gunny bags, then the water will be sprayed. This will help to save water. 2.11 How is the storm water from within Infrastructural facilities like provision of adequate the site managed?(State the provisions storm water drains, wastewater collection and made to avoid flooding of the area, conveyance including treatment and disposal have details of the drainage facilities been planned in the project. provided along with a site layout - Regular inspection & cleaning of storm indication contour levels) water drains. - Cover waste storage areas - Avoid application of pesticides and herbicides before wet season. - Provision of silt traps in storm water drains - Good house keeping 2.12 Will the deployment of construction The local people will be deployed during laborers particularly in the peak construction. There will be no stagnant water at period lead to unsanitary conditions site, as the run off from the relevant areas will be around the project site (Justify with systematically drained. The civil contractor will be proper explanation) held responsible for site sanitation and will be bound by the management to adhere to healthy level of sanitation.

6 2.13 What on-site facilities are provided Construction phase: for the collection, treatment & safe The waste water generated from toilets will be disposal of sewage? (Give details of diverted to septic tanks followed by soak pits. the quantities of wastewater Post construction phase: generation, treatment capacities with Sewage water @ 319.0 KLD will be collected and technology & facilities for recycling treated in SBR based 385.0 KLD STP. and disposal) Treatment efficiency: >85% Reuse and disposal: STP treated water will be used for flushing and gardening, remaining will be discharged to municipal sewer. 2.14 Give details of dual plumbing system if There will be separate pipelines for the supply of treated waste used is used for flushing the fresh water and treated water from STP. of toilets or any other use. Treated water will be used for the flushing, gardening & washing purposes.

3. VEGETATION:

S.No. ITEM DETAILS 3.1 Is there any threat of the project to There will be no threat on the biodiversity due to the biodiversity? (Give a description the proposed project. Project site is almost flat of the local ecosystem with it’s unique terrain mostly dominated/covered with common features, if any) grass and shrub species. Moreover, site doesn’t support any critical or special habitat; which can support threatened, endangered species. 3.2 Will the construction involve There is 1 Tree that exists within the site. which extensive clearing or modification of will be removed according to the requirement vegetation?(Provide a detailed account and the same will be replaced by planting 1:3 of the trees & vegetation affected by ratios as per the guidelines with permission. the project) 3.3 What are the measures proposed to Due care will be taken to protect the important be taken to minimize the likely site features: impacts on important site features  Tree plantation will be done to protect the site (Give details of proposal for tree features such as topsoil erosion, ground water plantation, landscaping, creation of attenuation and avoiding contamination by water bodies etc along with a layout leachate. plan to an appropriate scale)  The excavated soil will be stored at earmarked places protected from contamination and from polluting the existing features and will be used for surface leveling and for creation of

7 landscaped areas.  Piling will be done so as to minimize the impacts on the existing structures in the nearby areas.  Green belt will be developed in an area of 1,774.37 Sqm.

4. FAUNA: S.No. ITEM DETAILS 4.1 Is there likely to be any displacement The proposed site does not have any terrestrial of fauna- both terrestrial and aquatic and aquatic fauna, so no displacement will take or creation of barriers for their place. movement? Provide the details. 4.2 Any direct or indirect impacts on the No endangered or endemic species of birds avifauna of the area? Provide details are found in the study area, 4.3 Prescribe measures such as corridors, Not applicable fish ladders etc to mitigate adverse impacts on fauna

5. AIR ENVIRONMENT: S.No ITEM DETAILS 5.1 Will the project increase atmospheric There will be increase in intensity of land use in concentration of gases & result in heat the existing area, which may result in the islands? (Give details of background air creation of heat islands. DG sets are deployed quality levels with predicted values for the project, which will result in the increase based on dispersion models taking into in atmospheric concentration of gases. account the increased traffic generation as a result of the proposed Impact: constructions)  Urban Heat island effect due to increase in the paved areas (Roof & Non Roof).  Emissions due to traffic load  An emission due to DG sets Mitigation measures: Heat Island Effect: Roof  The roofs will be covered with solar panels which will reduce the exposed roof area.  The other exposed roof will be covered with white china mosaic tiles/green roof to reduce the heat gains inside the building.

8 Heat Island Effect: Non-roof:  Hard paving onsite has been reduced to the best possible extent.  About 10% of the area will be under greenbelt, which will mitigate heat island effect. Fugitive dust emissions: Sources:  Construction activities.  Vehicular movement.  Road construction.  Paved and unpaved area emissions. Mitigation:  Screening the construction site with the help of tarpaulin to contain the emissions within the site.  Water spraying on the haul roads.  Storage of construction material and waste at earmarked places and well covered. Impact due to traffic emissions: The impact of vehicular emissions varies with rate of movement of vehicles, atmospheric conditions and stability classes. Mitigation:  About 16,691.92 Sqm area will be under landscape.  The vehicles will be PUC certified.  Reduced vehicular speed will also avoid the air borne fugitive emission on the unpaved areas. 5.2 What are the impacts on generation of The impacts of dust and gaseous pollutants due dust, smoke, odorous fumes or other to different construction activities will be hazardous gases? Give details in localized and will not affect the surrounding relation to all the meteorological environment. All necessary measures will be parameters taken.

 Water spraying at dust generation sources  All transportation vehicles will be suitably covered to prevent dust dispersion from the

9 trucks, and overloading of the vehicles will be avoided and must be PUC certified vehicle.  Plantation is proposed to be taken up along the boundary of the project site to the extent possible.  CPCB Certified D.G. Sets will be installed to maintain the emission within the norms etc.  The D.G. sets will be provided with adequate stack height for effective dispersion of pollutants.  Low Sulphur content fuel (HSD: Sulphur content: 0.05%) will be used which will help to contain the emissions within the permissible range. 5.3 Will the proposal create shortage of Adequate provision will be kept for parking at parking space for vehicles? Furnish the proposed project. Sufficient planning is being details of the present level of transport done so that transport system is organized by infrastructure and measures proposed following the good traffic management for improvement including the traffic techniques. management at the entry & exit to the Following measures will be adopted for smooth project site. traffic movements:  Provisions of fully internalized parking including the parking facilities for the visitors.  Guided traffic ways within the project site.  Speed humps will be installed for speed restrictions inside the project area. 5.4 Provide details of the movement The movement pattern inside the project area patterns with internal roads, bicycle will be guided traffic ways. There will not be any tracks, pedestrian pathways, footpaths separate bicycle tracks or pedestrian pathways etc., with areas under each category. on the periphery (driveway). 5.5 Will there be significant increase in There is no significant increase in noise and traffic noise & vibrations? Give details vibration. The noise and vibrations level will be of the sources and the measures well within the norms. Speed of the vehicles will proposed for mitigation of the above. be limited to 15-20 Km/hr to minimize noise and vibration. The following measures will be adopted to reduce the noise:  Trees with heavy foliage will be planted at the periphery so as to restrict the noise levels

10 within the permissible norms.  Both entry and exit are manned with trained and efficient security.  Road markings, stop lines, parking lanes are painted to guide the internal road user.  Separate entry/exit is provided such that it enables the smooth movement of the vehicles. 5.6 What will be the impact of DG sets & Construction Phase: other equipment on noise levels & The noise level due to construction activity and vibration in & ambient air quality in operational phase will be localized to the around the project site? Provide source. During the construction phase, noise will details. be generated from the construction equipment’s and the operation of DG sets. Fugitive emissions generated from various construction activities will be contained by screening the site by tarpaulin. The noise level due to construction activity and in operational phase will be localized. Post Construction phase: The important source of pollution during post construction phase will be emissions from D.G. sets used in case of power cuts or failure (for complete power back up). The DG sets will be housed in an inbuilt acoustic enclosure for maximum noise attenuation. The DG sets deployed will be EPA/ CPCB certified for the permissible standards of noise & vibrations.

6. AESTHETICS:

S.No. ITEM DETAILS 6.1 Will the proposed constructions in any The proposed project will not in any way way result in the obstruction of a view, obstruct any view, scenic amenity or landscapes. scenic amenity or landscapes? Are In fact it increases aesthetics of the area due to these considerations taken into large scale green belt development. account by the proponents? 6.2 Will there be any adverse impacts No, there will be no impact on existing from new constructions on the infrastructure due to the construction activities. existing structures? What are the considerations taken into account?

11 6.3 Whether there are any local The project will strictly follow the area building considerations of urban form & urban regulation of NBC. All norms on ground design influencing the design criteria? coverage, FAR, Height, Setbacks, Fire safety They may be explicitly spelt out. requirements, structural design and other parameters will be strictly adhered to. 6.4 Are there any anthropological or None archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

7. SOCIO-ECONOMIC ASPECTS:

S.No. ITEM DETAILS 7.1 Will the proposal result in any changes No such changes envisaged to the demographic structure of local Construction phase: population? Provide the details. Since local laborers will be engaged during construction phase, alteration to the existing demographic profile of the area in not anticipated. Operation Phase: The changing demography in the area is another impact that needs attention. The project will mainly lead to spatial redistribution of local plantation and hence no considerable influx of population is envisaged owing to the proposed project. 7.2 Give details of the existing social The proposed project is conveniently located infrastructure around the proposed close to, project. Hitech city – 9.6 Km (NE) Rajiv Gandhi International Airport- 17.0 km (SE) As the activity is located in city area hence required infrastructures is located nearby the project site. Other basic infrastructural amenities like safe drinking water, electricity, market, and medical services are available around the proposed project. 7.3 Will the project cause adverse effects No, Project is not likely to have any adverse

12 on local communities, disturbance to effect on local population; rather the local sacred sites or other cultural values? population will get benefit arising due the What are the safeguards proposed? proposed project. 8. BUILDING MATERIALS

S.No. ITEM DETAILS 8.1 May involve the use of building The basic materials used will be cement, steel, materials with high-embodied energy. bricks, stones, ready mix concrete, sand, gypsum, Are the construction materials plywood, hard wood, aluminum, glass, etc. produced with energy efficient  Low energy embodied materials will be given processes? (Give details of energy preference. conservation measures in the selection  Energy efficient construction materials such as of building materials and their energy Gypsum Plaster Concrete, Sand Aggregate, Fly efficiency) Ash Cement, will be used to achieve the desired primary energy efficiency.  Ready Mix concrete will be used for construction of RCC structures. M-sand will be used as an alternative to river sand and the building blocks will be solid cement blocks that are energy efficient and work efficient compared to baked bricks.  Ensuring that the building materials and products have low energy embodied energy.  Minimizing the transport of temporary structures, scaffolding, formwork, consumables and building product to the construction site.  Minimizing overall waste and the transport of waste from site.  Use of energy efficient lighting.  Ensuring idle construction equipment is throttled down or switched off All the items to be used in the project are as per the National Building Code. 8.2 Transport and handling of materials During the construction phase, the following during construction may result in measures will be taken to prevent pollution. pollution, noise & public nuisance.  Top soil excavated during construction What measures are taken to minimize activities will be stored for use in the impacts? horticulture/landscape development within the

13 project site to the possible extent  Covering of the construction site from all four sides to a substantial height to prevent dust emissions and other pollutants into surrounding area.  Covering loads to limit materials or litter blowing off and reducing smells.  Ready mix concrete will be used for concreting. This avoids cement and aggregate handling fugitive emissions and noises.  Noise machines will be preferred after 10.00 am. Loading and unloading will be done with low height.  Unloading of construction material will not be done during night  Water spraying to prevent dust pollution from different sources of construction.  Speed restriction of all the vehicles approaching the site and within the site.  All transportation vehicles will be suitably covered with tarpaulin & overloading of the vehicles will be avoided and must be pollution checked vehicle.  Heavy earth working will be avoided during night. 8.3 Are recycled materials used in roads The excavated soil will be used for backfilling as and structures? State the extent of well as for creating landscaped areas. savings achieved? 8.4 Give details of the methods of The estimated quantity of garbage will be around collection, segregation & disposal of 1,390 Kg/day. It is proposed to collect & the garbage generated during the segregate the wastes at project site and Orgnaic operation phases of the project. waste sent to OWC, Recyclables to Authorized Recyclers and remaining will be sent to municipal solid waste management facilities.

14 9. ENERGY CONSERVATION S.No. ITEM DETAILS 9.1 Give details of the power The source of the Power is from TSPCDL. requirements, source of supply, Power requirement: 3200 KVA backup source etc. What is the energy Backup power: 4 x 500 KVA & 1 x 82.5 KVA consumption assumed per square foot DG set for emergency during power failure. of built-up area? How have you tried Energy saving measures proposed to minimize to minimize energy consumption? energy consumption is as follows. 1) Use of LED Bulbs (Light Emitting Diodes) & low voltage lighting. 2) Use of energy saving methods in lift (V3F) in place of conventional methods 3) Corridors, walkways and staircases have been provided with natural lighting to the maximum extent possible. 9.2 What type of, and capacity of, power 4 x 500 KVA & 1 x 82.5 KVA DG sets will be back-up to you plan to provide? used as backup power for emergency during power failure. APFC panel will switch the above loads onto DG supply within 10 – 12 seconds. In case of repair/ maintenance or operational difficulty with any DG set, DG sets will be manually interchangeable to cater only to the critical loads. HSD requirement will be 500 Liters. 9.3 What are the characteristics of the The type of glass proposed to be used will be glass you plan to use? Provide plain glass with have low conductance and high specifications of its characteristics insulation properties so that heat ingress into the related to both short wave and long inside of the building will be minimized. This will wave radiation? help to reduce the heat gain in the building. U-value of glass – 5.40 – 5.49 9.4 What passive solar architectural Passive solar cooling is incorporated in the features are being used in the building? building design. Buildings are suitably oriented for Illustrate the applications made in the ensuring natural ventilation and day lighting. proposed project. Building design and envelope may be optimized through selection of appropriate wall and roof construction and through adoption of solar passive measures after studying the sun path analysis to provide shading devices for windows and roof which would reduce energy demand.

15 9.5 Does the layout of streets & buildings Solar power facilities shall be used for Street maximise the potential for solar lightning. energy devices? Have you considered Paving onsite (open area surrounding building the use of street lighting, emergency premises) is reduced to the extent possible to lighting and solar hot water systems minimize the imperviousness of the site and for use in the building complex? shade will be provided on hard paved surfaces to Substantiate with details. minimize heat island effect. Passive solar cooling will be incorporated in the building design. Building will suitably orient for ensuring natural ventilation and day lighting. 9.6 Is shading effectively used to reduce Walls. cooling/heating loads? What principles East and West Elevations. have been used to maximize the Walls that face the east and west will be well shading of Walls on the East and the insulated as possible, to prevent summer heat West and the Roof? How much gain from the low morning and evening sun. energy saving has been effected? Roof: Brickbats will be placed on the flat roof to give a slope and then grouting the same with cement mortar admixed with some water proofing compounds. 9.7 Do the structures use energy-efficient  Automatic power factor compensating space conditioning, lighting and multiple capacitor units are provided for mechanical systems? Provide technical maintaining of average power factor of 0.99 to details. Provide details of the have effective savings in energy cost. All transformers and motor efficiencies, capacitors are provided with Harmonic Filters lighting intensity and air-conditioning to avoid distortion in Voltage I.e. Clean Power load assumptions? Are you using CFC is available to building. and HCFC free chillers? Provide  An APFC relay based on thyristerised specifications. switching is proposed to effect the power factor correction /improvement within a few cycles of deviation from the setting & also to reduce inrush currents.  All cables shall be derated to avoid heating during use. This also indirectly reduces losses and improves reliability. Lighting System:  The recommended illumination levels (in Lux) as per the National Building Code of will be applied.

16 9.8 What are the likely effects of the Heat emission from the project can be from the building activity in altering the micro- following sources: climates? Provide a self-assessment on  Heat absorbed and radiated from the paved the likely impacts of the proposed and concrete structures. construction on creation of heat island  Increased population for a particular stretch of & inversion effects? land. Any building activity would alter the microclimate of a site and it is inevitable that wind patterns and thermal gain patterns on a site would be changed. But the proposed building has been carefully designed to modify the microclimate so as to improve overall thermal comfort and reduce energy consumption. Shade giving trees are planted near the east and west side which affect the microclimate and provide cooling effect in summers. 9.9 What are the thermal characteristics The building has been designed in such a way of the building envelope? (a) roof; (b) that it complies with the requirement of building external walls; and (c) fenestration? envelope i.e. insulation material and their “R” Give details of the material used and values, fenestration “U” factors and Solar Heat the U-values or the R values of the Gain Coefficient (SHGC) as per ECBC individual components. guidelines. For external wall – external openings will have regular door/windows with slight-tinted glass. Regular walls will have some cladding/fixture paints. Energy efficient and other conservation methods will be followed as per norms of Energy Conservation Building Code (ECBC). 9.10 What precautions & safety measures Essential fire safety measures will be installed in are proposed against fire hazards? the building to ensure the safety of the Furnish details of emergency plans. occupants within the building in the event of fire or other emergency. The entire building will be designed as per NBC- 2016 of India pertaining to fire hazards. Safety measures: -  Proper fire exits and exit signs in case of any emergency will be made available.  Fire detectors, Fire alarm and Fire extinguishers of appropriate type will be placed on a readily accessible place and will be

17 maintained accordingly. 9.11 If you are using glass as wall material The proposed project is a Residential provides details and specifications Apartments Project and will not involve glass as including emissivity and thermal wall material. characteristics. 9.12 What is the rate of air infiltration into The project will not be centrally air conditioned the building? Provide details of how and hence there will be provision for ample you are mitigating the effects of natural ventilation. infiltration. 9.13 To what extent the non-conventional Solar energy will be variedly used as: energy technologies are utilised in the - Solar street lights overall energy consumption? Provide - Solar blinkers details of the renewable energy - Solar power packs/inverters technologies used. - Roof top SPV systems with or without grid connection - LED Bulbs will be used in buildings to minimize the energy consumption - Green area is provided along with tree plantation which will result in natural air cooling and will reduce the load on conventional energy sources.

10. ENVIRONMENT MANAGEMENT PLAN

The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

The detailed Environmental Management plan report is furnished along with the application

18 CONCEPTUAL PLAN & EMP

FOR THE PROPOSED RESIDENTIAL APARTMENTS PROJECT OF SRI. ANUHAR HOMES PVT LTD SURVEY.NO: 324/E & 325, NARSINGI VILLAGE, GANDIPET MANDAL, RANGAREDDY DISTRICT, TELANGANA STATE

Category – 8 (a)

SUBMITTED BY SRI. Y. HARSHAVARDAN REDDY, C/O. M/S. ANUHAR HOMES PVT LTD, H.NO.8-2-293/82/225/A, 3RD FLOOR, ROAD NO 18, JUBILEE HILLS, HYDERABAD – 500033

PREPARED BY: M/s. SPACE ENVIRO SOLUTIONS (QCI/NABET ACCREDITATION NO: NABET/EIA/1922/IA0043) H. NO: 1-4-69/7, STREET NO:8 HABSIGUDA, HYDERABAD. TELANGANA – 500007 M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP CHAPTER –1 1.0 INTRODUCTION

1.1 PURPOSE OF THE REPORT: M/s. Anuhar Homes Pvt Ltd & Others is proposing to Construct a Residential Apartments at Sy. No:324/E & 325 situated at Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. The Total Site area as per document is 17,199.21 Sqm and Net Plot Area is 16,691.92 Sqm. The Built up area of the project is 1,02,990.14 Sqm (4 Blocks- Sub-Cellar + Cellar + Ground+14 Upper Floors & Amenities Block – Cellar +Ground + 4 Upper Floors).

The Total Built up area for the proposed project is greater than 20,000 Sqm, as per the EIA Notification dated 14th September 2006 and its amendments there off, the proposed project activity falls under Building & Construction projects 8(a) Category B (B2), which necessities to obtain Environmental Clearance from SEIAA, Telangana State. As part of this activity the proponent has prepared Form-1, Form-1A, Conceptual Plan and Environmental Management Plan and submitted to SEIAA, Telangana for obtaining Environmental Clearance.

1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT: The proposed Construction of Residential Apartments of M/s. Anuhar Homes Pvt Ltd & Others is promoted by Sri. Y. Harshavardhan Reddy and having their office at C/o. M/s. Anuhar Homes Pvt Ltd, H.No.8-2-293/82/225/A, 3rd Floor, Road No 18, Jubilee Hills, Hyderabad – 500033. 1.3 PROJECT COST: The estimated cost for the proposed project will be 112.0 Crore.

1.4 SALIENT FEATURES OF THE PROJECT: The salient features of the project are given below:

M/s. Space Enviro Solutions, Hyderabad. 1

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

TABLE 1.1 – SALIENT FEATURES OF THE PROJECT Net Plot Area 16,691.21 Sqm Built-up Area Apartments Area – 73,222.19 Sqm Amenities Area – 2,262.30 Sqm Parking Area – 27,505.65 Sqm Total Built-up Area – 1,02,990.14 Sqm No.of Flats 510 No.of Floors Sub-Cellar + Cellar + Ground +14 Upper Floors Greenbelt Area 1,774.37 Sqm Height of the building 45.0 mts Nearest Fire station Panjagutta Fire Station – 5.3 Km (NE) Water requirement & Source Total Water Requirement – 375.0 KLD Fresh Water – 240.0 KLD Recycle Water from S.T.P – 135.0 KLD Power requirement & Source 3200 KVA, TSCPDCL Backup Power 4 x 500 KVA & 1 x 82.5 KVA D.G.Set Solid waste & Garbage – 1,390.0 kg/day mode of disposal (Segregation at Source & Disposed properly as per SWM Rules 2016) Bio-Degradable – 834.0 kg/day - (Organic Waste Convertor) Non-Bio-Degradable – 556.0 kg/day- (Authorized Recyclers/vendors) S.T.P. Sludge – 32.0 kg/day (Used as manure for greenbelt) Hazardous waste & Used batteries – 5 No’s/Year mode of disposal Waste Oil from D.G. Sets – 300 Liters/Year will be sent to TSPCB Authorized Recyclers/Re-Processors

M/s. Space Enviro Solutions, Hyderabad. 2

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP CHAPTER – 2 2.0 PROJECT DESCRIPTION 2.1 LOCATION DETAILS: M/s. Anuhar Homes Pvt Ltd & Others is proposing to Construct a Residential Apartments at Sy. No:324/E & 325 situated at Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. The Total Site area as per document is 17,199.21 Sqm and Net Plot Area is 16,691.92 Sqm. The Built up area of the project is 1,02,990.14 Sqm (4 Blocks- Sub-Cellar + Cellar + Ground+14 Upper Floors & Amenities Block – Cellar +Ground + 4 Upper Floors).

Features of the site: The area earmarked for construction of Residential Apartments Project is located at Narsingi Village. The geographical co-ordinates of the site are 17°23'4.14"N Latitude and 78°22'0.61"E Longitude. i. Accessibility & Existing Road network: The nearest road is Osman Sagar Road, which is at a distance of 0.2 km(SW) to the project site and Narsingappa Service Road is at a distance of 1.6 Km (W). ii. Topography The General topography is plain topography. Commercial and Residential flats are surrounding the site. iii. Water Bodies The water bodies surrounding the project site are Neknampur Cheruvu-0.2km (SE), Musi River-0.6 km (S), Ibrahim Cheruvu-0.7 km (E ), Muskin Cheruvu-2.3 km(NNW), Battemma Cheruvu-1.5 km (NNW), Pedda Cheruvu-4.2km(NNE),Musa River-4.7 km(ESE),Himayat Sagar-5.0 km(SSW), Langar houz cheruvu- 5.0 km (E ), Osman Sagar-5.3 km(W),Durgam Cheruvu-5.1 km (NNE),Mir Alam Cheruvu-7.7 km(ESE). The Topographical Map of the study area is provided in Figure No.2.1, Google Image showing project Location is provided in Figure 2.2, Site Photographs are Given in Figure 2.3 and Site Plan is provided at Figure 2.4.

M/s. Space Enviro Solutions, Hyderabad. 3 M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP FIGURE NO: 2.1 –TOPOGRAPHICAL MAP

M/s. Space Enviro Solutions, Hyderabad. 4 M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP FIGURE: 2.2 – GOOGLE IMAGE SHOWING PROJECT LOCATION

M/s. Space Enviro Solutions, Hyderabad. 5

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

FIGURE NO: 2.3: PROJECT SITE PHOTOGRAPHS

M/s. Space Enviro Solutions, Hyderabad. 6

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

FIGURE NO: 2.4 – PROJECT SITE LAYOUT PLAN

M/s. Space Enviro Solutions, Hyderabad. 7

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

TABLE 2.1: SALIENT FEATURES OF PROJECT SITE Village Narsingi Village, Mandal Gandipet Mandal, District Rangareddy District. Ambient Temperature Minimum 130 C Maximum 430C Humidity 55 – 65 % Rainfall 800 – 1100 mm per Annum Climate Tropical & Semi-Arid Type of soil Silty sand and morum Distance from nearest Air Port Rajiv Gandhi International Airport- 17.0 km (SE) Distance from nearest Railway Station Hitech city – 9.6 Km (NE) Forests Chilkur PF-1.9 km (S) Kottaguda RF-7.4 km (N) Nehru Zoological Park (RF)-8.3 km(ESE) Water Bodies Neknampur Cheruvu-0.2km(SE) Musi River-0.6 km(S) Ibrahim Cheruvu-0.7 km (E ) Muskin Cheruvu-2.3 km (NNW) Battemma Cheruvu-1.5 km(NNW) Pedda Cheruvu-4.2 km(NNE) Musa River-4.7 km(ESE) Langarhouz Cheruvu-5.0 km (E ) Himayat Sagar-5.0 km(SSW) Osman Sagar-5.3 km(W) Durgam Cheruvu-5.1 km(NNE) Mir Alam Cheruvu-7.7 km(ESE) Any Historical monuments within 10 Qutubshahi Tombs-3.4 km(NE) KM radius Golconda Fort-3.5 km (E ) Chilkur Balaji Temple- 7.7 km(SW ) Any Ecologically sensitive areas within Mrugavani National Park-2.6 km(SW) 10 KM radius Kasu Brahmanandareddi National Park-6.0 km (NE) Nehru Zoological Park-8.3 km(ESE) Topography Plain and land locked

M/s. Space Enviro Solutions, Hyderabad. 8

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

2.2 BUILT-UP AREA: M/s. Anuhar Homes Pvt Ltd & Others is proposing to construct a Residential Apartments and the floor wise details are provided in Table 2.2. A total 510 no. of Flats are proposed in 4 Blocks. The block wise details are provided in Table-2.2. TABLE 2.2 – NUMBER OF FLOORS AND BUILT UP AREA Block Details No. of Floors Built-Up Area (Sqm) Residential Ground+14 Floors 73,222.19 Blocks (A,B,C & D) Amenities G + 4 Floors 2,262.30 Parking Sub Cellar + Cellar+ 27,505.65 Amenities Cellar Total - 1,02,990.14

2.3 PARKING AREA: The total built up area for parking is 27,505.65 Sqm, which can accommodate 706 No’s of four wheelers and 344 No’s of two wheelers. The total parking area is being proposed in the proposed project is given below:

TABLE 2.3 – PARKING SPACE PROVISION Parking Facility Area(Sqm) Sub Cellar 13,519.42 Cellar 12,916.51 Amenities Cellar 1,069.72 Total Parking Built up Area 27,505.65

2.4 ROAD NETWORK: The nearest road is Osman Sagar Road, which is at a distance of 0.2 km(SW) to the project site and Narsingappa Service Road is at a distance of 1.6 Km (W).

2.5 WATER REQUIREMENT: The total water requirement of the project during occupational stage is 375.0 KLD, out of that the fresh water requirement is 240.0 KLD will be sourced from Municipal Supply and the recycled water is 135.0 KLD. The total sewage water generated is 319.0 KLD. It is proposed to treat the sewage in STP of capacity of 385.0 KLD. The treated waste water is

M/s. Space Enviro Solutions, Hyderabad. 9

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP used for Flushing, Washing & Gardening. The total water requirement during occupational stage is given below; TABLE 2.4 – WATER REQUIREMENT

S.No. Requirement Quantity (KLD) 1 Domestic Water 240.0 2 Flushing Water 125.0 3 Gardening 6.0 4 Washings & Others 4.0 Total 375.0

As per suggestions of NBC, Water requirement for Residents is 135 Liters /day/person, for Visitors is 15 Liters/day/person and for Staff 45 Liters/ day /person, is considered.

2.6 POWER REQUIREMENT:

The power requirement for the proposed project is estimated as 3200 KVA which will be sourced from the TSCPDCL.

2.7 BACK-UP POWER DETAILS:

Entire power, lighting, UPS power shall be on emergency supply through 4 x 500 KVA & 1 x 82.5 KVA DG set.

2.8 FUEL REQUIREMENT: The fuel requirement for 4 x 500 KVA & 1 x 82.5 KVA DG set is 500 Liters. The fuel used in DG sets is High Speed Diesel (HSD).

2.9 MAN POWER REQUIREMENT: The maximum man power required for the development of proposed project during construction phase is 150 persons.

2.10 STORM WATER DRAINS: All along the road network and the arterial roads of the proposed complex, storm water drains would be provided to collect water during rains. They would adequately size to prevent over flooding of the site.

M/s. Space Enviro Solutions, Hyderabad. 10

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

2.11 ENVIRONMENTAL INFRASTRUCTURE: a). Waste Water Generation & Management: Total quantity of wastewater generation is likely to be 319.0 KLD. The generated waste water is collected and treated in in-house Sewage Treatment Plant of 385.0 KLD capacity. The available water after treatment is 287.0 KLD, in which 135.0 KLD will be used for Flushing, Washing & Gardening and excess water will be sent to public sewer. The water balance details are presented below. TABLE 2.5 - WATER BALANCE Input Requirement Quantity Out put Quantity Domestic 240.0 Domestic Waste Water 192.0 Flushing 125.0 Flushing waste water 125.0 Gardening 6.0 Washings & Others 2.0 Washings & Others 4.0 Evaporation and other losses 56.0 Total 375.0 Total 375.0

The waste water generated from process i.e, 319.0 KLD which will be treated in 385.0 KLD Capacity S.T.P. The available recycled water after treatment is 287.0 KLD, in which 135.0 KLD will be used for Flushing, Gardening & Washings and remaining will be sent to public sewer. It should therefore be concluded there is no significant impact on surface water quality & hydrology of the area. The proposed rainwater harvesting scheme stabilizes the groundwater table in the area. b). Sewage Treatment Plant (STP):

A sewage treatment plant of 385.0 KLD capacity based on Sequential Batch Reactor (SBR) technology is proposed to treat 319.0 KLD of sewage water generated in the proposed project. After treatment the water will be used for Flushing, Gardening & Washings. The design of the STP shall be based on the parameters given in below table.

M/s. Space Enviro Solutions, Hyderabad. 11

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

TABLE 2.6 - DESIGN PARAMETERS OF SEWAGE TREATMENTPLANT Inlet Outlet Parameter Unit Concentration Concentration pH -- 7.0 – 9.5 6.5 – 9.0 Oil & Grease Mg/l 20-30 <10 BOD Mg/l 250-350 <10 COD Mg/l 500- 600 <50 TSS Mg/l 150-300 <20 CPCB: Discharge Standards for New Sewage Treatment Plants (2015)

Sewage Treatment Process Description:

Sewage treatment plant is designed to treat 319.0 KLD of Sewage per day. The proposed scheme is depicted in the figure attached below.

Primary treatment:

The sewage is collected and discharged into the treatment plant through inlet pipe. A bar screen chamber is provided for retaining coarse matter. The screens are manual type and are to be cleaned at regular intervals. Two stages of screens are provided i.e. coarse screen followed by fine screens. The sewage is then taken to grit chamber for removal of grit. From the grit chamber, the sewage is taken to an equalization tank for reduce the variations in waste flow rate and its characteristics. It is proposed to have equalization tank with detention time of 6 hours. For mixing and to avoid solids from settling, air shall be bubbled in the equalization tank through a grid placed at the base of the tank. The equalized sewage is pumped at a uniform and constant rate for further treatment.

Secondary treatment:

The SBR is a special form of activated sludge process in which the entire treatment process takes place in the one reactor tank. The wastewater is treated in batch mode and each batch mode is sequenced through a series of treatment stages like fill, aeration, sludge settle and decant. The wastewater from the equalization tank is entering into the filling phase of SBR. Mixing and aeration can be done during filling phase of the tank to carry biological treatment. Next the wastewater which is aerated enters into react phase. In the react phase, the aeration is continuously allowed to increase the rate of organic removal. Microorganisms + Organic matter Water + Gas + Biomass

M/s. Space Enviro Solutions, Hyderabad. 12

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

Followed the react phase, the wastewater undergoes settle phase. During the settle phase, no wastewater enters the tank and no mixing and aeration takes place. The sludge is settled to the bottom of the tank and clear supernatant (liquid) is formed at the top of the tank. In the final stage, the formed clear supernatant (liquid) is decanted from the tank. It is important that no scum or surface foam should be present. It is optimal that the decant wastewater volume is equal to the wastewater in the fill phase.

Advantages:  It can be installed in a limited amount of space, as treatment takes place in a single reactor instead of more basins.  Respond to the flow and load variations  Low sludge production  Flexibility in operating and control  No odor production  Gives high treatment efficiency in a single step biological process  Capital cost savings for eliminating more reactor tanks.

Tertiary treatment: The clear liquid from SBR will be collected in chlorine contact tank for the disinfection treatment. Then it is collected in a sump and pumped to a pressure sand filter for removal of particulate matter and then taken through an activated carbon column for removal of trace organics and pollutants (chlorine, color, trace organics etc.).

Sludge Treatment: The Sludge collected from the settling tank of SBR is transferred to sludge sump tank. Filter press feed pumps are used for dewatering process by transfer the sludge from sludge sump tank to filter press. After the Dewatering process, the available solid organic mass is used as manure for crops after undergo suitable treatment and the available water from the filter press is recycled into the equalization tank.

M/s. Space Enviro Solutions, Hyderabad. 13

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

FIGURE – 2.5– PROPOSED SCHEME OF TREATMENT

c). Solid & Hazardous Waste Details: S.No Type of Quantity Collection/storage Disposal Waste 1 Garbage 1,390.0 Stored in Green and Blue Biodegradable Waste 834.0 kg Kg/day bins for recyclable and @ 60% will be treated in In- non-recyclable wastes house Organic Waste respectively. Convertor and Non- Biodegradable Waste 556.0 @ 40% will be Sent to Authorized Vendors as per SWM Rules 2016. 2 STP Sludge 32.0 Stored in HDPE bags. Used as manure and or given Kg/day to farmers. 3 E-Waste 460.0 - Sent to Authorized recyclers. Kg/Annum 4 Used 5 - Sent to Authorized recyclers Batteries No’s/ Annum or returned to seller. 5 Used 300 Stored in HDPE Carboy Sold to Authorized recyclers. Lubricant Lit/Annum *Residential Refuse : 0.50 Kg/Person/Day *Commercial/Club : 0.15 Kg/Person/Day House/Visitors Refuse **E-Waste : 0.18 Kg/Person/Annum Ref : *National Building Code Volume 2 2016 ** International Resource Group Systems South Asia Pvt. Ltd (IRGSSA), 2005.

M/s. Space Enviro Solutions, Hyderabad. 14

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP d). Storm Water Management & Rain Water Harvesting Structures Elaborate plans have been made for channelizing the storm water by constructing water drains leading to the reservoirs. In order to minimize the surface runoff loss, groundwater recharging through groundwater recharge pits at the project site has been planned. Appropriate design considerations have been taken while designing the recharge pits.

TABLE-2.7: ESTIMATE OF RAIN WATER HARVESTING Rainwater Harvesting

Peak rainfall intensity Rain water Area Coefficient during one hour of harvesting Type of Area (in m2) of run-off rainfall potential/hour (in m) (in m3)

Roof-top area 4927.11 0.9 0.044 195.1 Green Area 1774.37 0.15 0.044 11.7 Paved area 9990.4 0.8 0.044 351.7 Total storm water load on the site with per hour retention is 558.5 Considering 15 minutes retention time, total storm water load 139.6 Taking the radius as 1.2 m and effective depth as 2 m, 9.0 volume of a RWH pit ( π r2h) Hence no. of pits required in approx = Total storm water load 15.4 considering 15 minutes retention time / Volume of a RWH pit

15 No's of Rain Water Harvesting pits are being proposed for rain water recharge within the project premises.

M/s. Space Enviro Solutions, Hyderabad. 15

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

CHAPTER – 3 3.0 IMPACT ASSESSMENT & MITIGATION MEASURES 3.1 IMPACT ASSESSMENT: The potential impacts on the surrounding environment in the 10km radial distance of proposed project site along with the mitigation measures during construction and operational stages are summarized in Table 3.1 and Table 3.2.

The construction phase is for a period of 24 months. Considering this to be a relatively short period, all construction impacts can be considered to be short term and temporary.

As for the operational phase, the project proponent shall ensure that impacts are minimized and are within applicable/ specified limits by SPCB & CPCB by providing relevant pollution control equipment and/ or mitigation measures discussed in the following tables.

M/s. Space Enviro Solutions, Hyderabad. 16

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

TABLE – 3.1 - CONSTRUCTION PHASE - POTENTIAL IMPACTS AND MITIGATION MEASURES

S.No. Environmental Potential Source of impacts Mitigation measures Remarks components impacts 1. Water resources Minor negative Water requirement of Judicious use of water; Water requirement will & temporary 50 - 70 KLD for minimization of water be sourced from the bore impact on construction activities consumption by use of high- wells & water tankers. surface & pressure hoses for dust However, the bore wells ground water suppression shall not be tapped resources. beyond their yield. 2. Surface water No impact Erosion and run-off due Avoiding excavation in monsoon - quality to excavation/ season; providing appropriate construction activities, measures for erosion and especially in monsoon sediment control; providing season; adequate sanitation facilities for Discharge of waste workers at site; avoiding discharge water, construction as of untreated wastewater in the well as domestic. area. 3. Ground water No impact Construction activities Storage area for fuels, paints, - quality thinners, etc. to be such so as to avoid chances of spillage. No discharge to ground water body. 4. Air quality Temporary Construction Carrying out construction activity - negative impact equipment; operation of in temporary enclosures, where

M/s. Space Enviro Solutions, Hyderabad. 17

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S.No. Environmental Potential Source of impacts Mitigation measures Remarks components impacts DG sets for feasible; water sprinkling for dust construction power suppression; regular maintenance requirement; vehicular of construction equipment & traffic; excavation; vehicles; use of fuel of proper concreting; etc. quality; use of state-of-the-art construction equipment & methods 5. Noise Medium Various construction Use of low noise generating state- - negative & activities; material and of-the-art construction equipment temporary vehicular movement and construction techniques; providing personnel protective equipment to workers; providing temporary enclosure for DG set and other construction activities, where feasible; avoiding construction work in the night time 6. Land (i) Land use/ No impact The Net plot area is No land conversion is required as Site Premises is designated requirement 16,691.92 Sqm. land is a vacant plot and is as Construction of designated for Construction of Residential Apartments Residential Apartments.

M/s. Space Enviro Solutions, Hyderabad. 18

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S.No. Environmental Potential Source of impacts Mitigation measures Remarks components impacts (ii) Solid wastes & Temporary Construction material Maintaining proper inventory - land pollution minor negative handling; construction control for reduced waste impact wastes handling and generation; substitution of disposal hazardous raw materials by non- hazardous materials, where feasible; providing proper facility for storage and handling of fuel oils; disposal of spent oils, classified as hazardous waste by sale to authorized third party; proper handling and disposal of construction wastes. (iii) Geology & No impact Construction of the No heavy structure planned as All civil structures shall be Seismicity Residential Apartments part of the project constructed as per earthquake zone classification 7. Ecology Minor positive Construction activity There is 1 tree that exist within No ecologically sensitive impact causing impact on the project area. which will be area such as forest/ existing ecosystem on- removed according to the agricultural land will be site and top soil; cutting requirement and the same will be used for the project. of existing vegetation, if replaced by planting 1:3 ratios as 1,774.37 Sqm to be required; per the guidelines with permission. developed as greenbelt.

M/s. Space Enviro Solutions, Hyderabad. 19

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S.No. Environmental Potential Source of impacts Mitigation measures Remarks components impacts Infact green belt will be developed all along the building boundary, roadside and lane divider. Water sprinkling during dust generation activities; erosion and sediment control; noise and fugitive dust control; restricting construction activity during night time 8. Socio-economic (i) Population and Minor negative Increase in population Employing local people to the About 150 construction literacy rate and temporary due to possible maximum extent possible workers are expected to temporary settling of be employed construction workers from outside the study area for the project (ii) Employment Minor positive & Availability of Employing local people to the About 150 construction temporary construction jobs maximum extent possible workers are expected to impact be employed (ii) Amenities such as No impact Needs of construction Employing local people to the - education, workers; extent possible for construction medical, water work; making adequate provision

M/s. Space Enviro Solutions, Hyderabad. 20

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S.No. Environmental Potential Source of impacts Mitigation measures Remarks components impacts supply, sanitation, through the contractors to handle etc. water, sanitary, medical and fuel requirement of construction workers to ensure that the existing infrastructure is not strained (iv) Transportation Temporary Increased traffic load Ensuring that traffic is well - negative impact due to transportation of regulated. Use of non-peak hours construction materials for material transportation and workers

TABLE – 3.2 - OPERATIONAL PHASE – POTENTIAL IMPACTS AND MITIGATION MEASURES

S. Environmental Potential impacts Source of impacts Mitigation measures Remarks No. components 1. Water resources Minor negative impact Total water requirement Recycle water will be used The fresh water will be on surface water for the proposed project Flushing ,Washing & Gardening sourced from ground resources is 375.0 KLD water.

Moderate negative impact on ground

M/s. Space Enviro Solutions, Hyderabad. 21

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S. Environmental Potential impacts Source of impacts Mitigation measures Remarks No. components water resources due to consumption. Minor positive impact due to recharge by rainwater harvesting. 2. Surface water No impact Discharge of sewage and Recycle water will be used for - quality waste water from utilities Flushing, Washing & Gardening 3. Ground water No impact Discharge of sewage and No discharge of wastewater to Rainwater from the quality waste water from utilities ground water body; use of rain water harvesting treated sewage water for will be used to Flushing, Washing & Gardening recharge ground water. 4. Air quality Minor negative impact Fuel combustion in DG All emissions will be well within All emissions well

(for SO2, NOX and sets the specified emissions within the specified HC emissions) standards; limits stack height = building height + 5 mts. for safe dispersal of pollutants; HSD with 0.05% sulfur content in DG sets; periodic maintenance of DG sets for reduced emissions

M/s. Space Enviro Solutions, Hyderabad. 22

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S. Environmental Potential impacts Source of impacts Mitigation measures Remarks No. components 5. Noise Minor negative impact Noise generating rotating/ Proper equipment selection; - moving equipment mandatory acoustic enclosure for DG sets; regular maintenance of noise generating equipment; providing personnel protective equipment to persons working in noisy areas; suitable design and location of utility block; development of suitable green belt and landscaping 6. Land environment (i) Land use / No impact Requirement of land for 16,691.92 Sqm of area available Once the project is requirement the proposed project for development operational, no additional land will be required. (ii) Solid wastes & Minor negative impact Handling and disposal of Segregation of wet and dry Though no solid/ land pollution hazardous and solid garbage – disposal of dry hazardous waste will wastes garbage through off-site be disposed off on recycling or to municipal waste land, chances of collection system and wet waste inadvertent occasional to composting at site; disposal spillage on land cannot

M/s. Space Enviro Solutions, Hyderabad. 23

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S. Environmental Potential impacts Source of impacts Mitigation measures Remarks No. components of waste lube oils by sale to be ruled out. authorized third party; buy-back arrangement for waste lead acid batteries (iii) Geology & No impact Improper building design Regular maintenance of the - Seismicity not adhering to specified structures to withstand natural codes; improper building phenomena; carrying out the maintenance structural integrity testing 9. Ecology No impact Emissions and discharges All emissions and discharges - from project operations; including noise will be within noise generation; specified standards; all solid/ improper disposal of hazardous waste will be wastes disposed off in environmentally sound manner . 10. Socio-economic factors (i) Population and No impact Increase in population due Employing personnel from Approximately 150 literacy rate to settlement of within the study area to the persons Direct personnel and their extent possible, subject to employment and families from outside the availability of skilled manpower indirect employment study area for the requisite to the job requirement are expected to be proposed project employed for the project

M/s. Space Enviro Solutions, Hyderabad. 24

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

S. Environmental Potential impacts Source of impacts Mitigation measures Remarks No. components (ii) Employment Medium positive Direct employment of Employing personnel from Approximately 150 impact personnel for proposed within the study area to the persons Direct project. extent possible, subject to employment and availability of skilled manpower indirect employment requisite to the job requirement are expected to be employed for the project. (ii) Amenities such as No impact Requirement of various Employing personnel from Various amenities in education, facilities for the children within the study area to the the study area are medical, water of personnel employed extent possible, subject to adequate. supply, sanitation, from outside the study availability of skilled manpower etc. area requisite to the job requirement. (iv) Transportation Medium negative Burden on the existing Ensuring that vehicular - impact road infrastructure due to movement is controlled during the increased traffic from peak traffic hours; providing bus the proposed project services from the office to the nearest railway station; encouraging car-pools for office employees.

M/s. Space Enviro Solutions, Hyderabad. 25

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

CHAPTER – 4 4.0 ENVIRONMENTAL MANAGEMENT PLAN 4.1 INTRODUCTION:

The Environmental Management Plan (EMP) is a site specific plan developed to ensure that the project is implemented in an environmental sustainable manner where all contractors and subcontractors, including consultants, understand the potential environmental risks arising from the proposed project and take appropriate actions to properly manage that risk. EMP also ensures the project implementation is carried out in accordance with the design by taking appropriate mitigative actions to reduce adverse environmental impacts during its life cycle.

The plan outlines existing and potential problems that may adversely impact the environment and recommends corrective measures where required. Also, the plan outlines roles and responsibility of the key personnel and contractors who are charged with the responsibility to manage the site.

The EMP is generally:

 Prepared in accordance with rules and requirements of the MOEF&CC, CPCB& SPCB;  To ensure that the component of facility is operated in accordance with the design;  Process that confirms proper operation through supervision and monitoring;  System that addresses public inconvenience during construction and operation of the facility; and  Plan that ensure remedial measures are implemented immediately.

The key benefits of the EMP are that it provides the organization with means of managing its environmental performance thereby allowing it to contribute to improved environmental quality. The other benefits include cost control as improved relations to the stakeholders.

M/s. Space Enviro Solutions, Hyderabad. 26

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

EMP includes four major elements;  Commitment & Policy: Project proponents will strive to provide and implement the EMP that incorporates all issues related to air, land and water for the project.  Planning: This includes identification of environmental impacts, legal requirements and setting environmental objectives.  Implementation: This comprises of resources available to the developers, accountability of contractors, training of operational staff associated with environmental control facilities and documentation of measures to be taken.  Measurement & Evaluation: This includes monitoring, corrective actions, and record keeping.

It is suggested that as part of the EMP, a Monitoring Team should be formed by the project proponent comprising of the site in-charge, project planning group representative and project implementation team representative. This committee’s role would be to ensure proper, operation and management of the EMP including the regulatory compliance.

4.2 ENVIRONMENTAL MANAGEMENT PLAN

An Environmental Management Plan (EMP) will be required to mitigate the adverse environmental impacts during construction and operation phase of the project and these are as below:

4.2.1 EMP FOR AIR ENVIRONMENT

A) CONSTRUCTION PHASE

To mitigate the impact of PM (dust) during the construction phase of the proposed project, the following measures are recommended for implementation:  a dust control plan; and  procedural changes to construction activities.

M/s. Space Enviro Solutions, Hyderabad. 27

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

TABLE 4.1: DUST CONTROL PLAN S.No Fugitive Dust Dust Control Actions Source Category

1. Earth-moving - For any earth moving which is more than 30m from all property lines, conduct watering as necessary to prevent visible dust emissions from exceeding 100m in length in any direction. 2. Disturbed surface areas - Apply dust suppression in a sufficient quantity (except completed grading and frequency to maintain a stabilized surface; areas) - Areas, which cannot be stabilized, as evidenced by wind driven dust, must have an application of water at least twice per day to at least 80 percent of the unstabilized area. Disturbed surface areas - Apply water to at least 80 percent of all inactive (completed grading areas) accessible disturbed surface areas on a daily basis when there is evidence of wind driven fugitive dust. 3. Inactive disturbed surface areas - Apply dust suppressants in sufficient quantity and frequency to maintain a stabilized surface. 4. Unpaved roads -Water all roads used for any vehicular traffic at least twice per day of active operations; OR - Water all roads used for any vehicular traffic once daily and restrict vehicle speed to 30 kmph. 5. Open storage piles - Apply water to at least 80 percent of the surface areas of all open storage piles on a daily basis when there is evidence of wind driven fugitive dust. 6. Track-out control -Downwash of trucks (especially tyres) prior to departure from site.

M/s. Space Enviro Solutions, Hyderabad. 28

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

The most cost-effective dust suppressant is water, because a source of water tends to be readily available on a construction site. Water can be applied using water trucks, handheld sprays and automatic sprinkler systems. Furthermore, incoming loads could be covered to avoid loss of material in transport, especially if material is transported off-site.

Procedural Changes to Construction Activities

Material Production - The transport of materials such as concrete and asphalt to construction sites generate significant amounts of road dust, especially for sites that are relatively far from material manufacturers. Setting up temporary portable concrete plants and/or asphalt plants at construction sites can eliminate haulage of materials.

Emission Control for Equipment- Control equipment such as particle filters can be used to reduce diesel particulate matter emissions.

Idling Time Reduction - Construction equipment is commonly left idling while the operators are on break or waiting for the completion of another task. Emissions from idling equipment tend to be high, since catalytic converters cool down, thus reducing the efficiency of hydrocarbon and carbon monoxide oxidation. Existing idling control technologies, which automatically shut the engine off after a preset time can reduce emissions, without intervention from the operators.

Improved Maintenance - Recognizing that significant emission reductions can be achieved through regular equipment maintenance, contractors will be asked to provide maintenance records for their fleet as part of the contract bid and at regular intervals throughout the life of the contract. A monetary incentive/disincentive provision will be established to encourage contractors to comply with regular maintenance requirements.

Reduction of On-site Construction Time - Rapid on-site construction would reduce the duration of traffic interference and therefore, reduce emissions from traffic delay. Off- site fabrication of structural components can also enhance the quality of work, as the production takes place in controlled settings and external factors such as weather and traffic do not interfere.

M/s. Space Enviro Solutions, Hyderabad. 29

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

B) OPERATION PHASE

To mitigate the impact of pollutants from diesel generator sets during the operational phase of the site the following measures are recommended for implementation:  Diesel generator set emission control measures; and  Greenbelt development.

Diesel Generator Set Emission Control Measures

The most important pollutant requiring further control is NOx, as the impact of SO2 emission is minimal because of the use of low (~0.05%) Sulphur in diesel as fuel. The following mitigation measures are proposed for NOx reduction:  add-on emission control technologies; and  NOx retarder

Among the above-mentioned options, inherent low NOx emissions technologies (i.e. a temperature retarder) and better dilution through higher stack are preferred cost effective mitigation measures. The add-on emission control technologies are not considered as it leads to pollution transfer to another media and shall require further mitigative measures.

Greenbelt Development Increasing vegetation in the form of greenbelt is one of the preferred methods to mitigate air pollution. Plants serve as a sink for pollutants, reduce the flow of dust and reduce noise pollution.

4.2.2 EMP FOR NOISE ENVIRONMENT

A) CONSTRUCTION PHASE

To mitigate the impact of noise from construction equipment during the construction phase of the site the following measures are recommended for implementation: Noise Shields - Construction equipment producing the most amount of noise should be fitted with noise shields. This shield is a physical barrier (composed of brick and mud, with a non reflective internal plastering), approximately 3 meters in height, which will provide adequate noise attenuation.

M/s. Space Enviro Solutions, Hyderabad. 30

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

Time of Operation - Noisy construction equipment should not be permitted during night hours.

Job Rotation and Hearing Protection - Workers employed in high noise areas will be rotated. Earplugs/muffs, or other hearing protective wear will be provided to those working very close to the noise generating machinery.

B) OPERATION PHASE To mitigate the impact of noise from diesel generator sets during the operational phase the following measures are recommended for implementation:  Noise emissions control technologies; and  Greenbelt development.

Noise Emissions Control Technologies: All the diesel generators will be housed in a suitable acoustic enclosure so that noise levels at a distance of one meter do not exceed 75 dB(A) at 75% load (as per CPCB norms). The diesel generator set housing will be equipped with walls and ceilings lined with glass wool to acoustically treat the noise levels. This acoustic insulation shall be designed to meet the mandatory standards based on a 25 dB(A) insertion loss.

4.2.3 EMP FOR WATER ENVIRONMENT A) CONSTRUCTION PHASE To prevent degradation and maintain the quality of the water source, adequate control measures have been proposed to check the surface run-off, as well as uncontrolled flow of water into any water body. Following management measures are suggested to protect the water quality during the construction phase.  Avoid excavation during monsoon season.  No discharge of treated wastewater to soil and ground water body.  Waste water channels from the site would be connected to septic tank during construction to prevent wastewater from entering the water bodies.  To prevent surface and ground water contamination by oil/grease, leak proof containers should be used for storage and transportation of oil/grease. The floors of

M/s. Space Enviro Solutions, Hyderabad. 31

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

oil/grease handling area should be kept effectively impervious. Any wash off from the oil/grease handling area or workshop shall be drained through impervious drains, Clarifiers or oil/water separators shall be constructed and effluent should be treated appropriately before releasing it.  Construction activities generate disturbed soil, concrete fines, fertilizer, oils and other wastes. On-site collection and settling of storm water, prohibition of equipment wash downs, and prevention of soil loss and toxic releases from the construction site are necessary to minimize water pollution.  All stacking and loading areas should be provided with proper garland drains equipped with baffles to prevent run off from the site to enter any water body.

B) OPERATION PHASE In the operation phase of the project, water conservation and development measures need to be taken including all possible potential for conservation of water, reuse, rainwater collection in reservoirs, and recycling of waste water. These could be in the form of the following:

 Water source Development  Minimizing water consumption  Promoting reuse of water after treatment and development of closed loop systems for different water streams.

4.2.4 EMP FOR LAND ENVIRONMENT A) CONSTRUCTION PHASE Waste generated from construction activity includes construction debris, biomass from land clearing activities (if any), waste from the labour camp, and. other waste. The following section discusses management of each type of waste. Besides management of topsoil is an important area for which management measures are required.

Construction Debris Construction debris is bulky and heavy and re-utilization and recycling is an important strategy for management of such waste. As concrete and masonry constitute the majority of

M/s. Space Enviro Solutions, Hyderabad. 32

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP waste generated, recycling of this waste by conversion to aggregate can offer benefits of reduced landfill space and reduced extraction of raw material for new construction activity. This is particularly applicable to Residential project as the construction is to be completed in a phased manner.

Recycled aggregate will be used for filler application, and as a sub-base for internal road construction. Mixed debris with high gypsum, plaster, shall not be used as fill, as they are highly susceptible to contamination, and will be given to recyclers. Construction contractors shall remove metal scrap from structural steel, piping, concrete reinforcement and sheet metal work from the site. A significant portion of wood scrap can be reused on site. Recyclable wastes such as plastics, glass fiber insulation, roofing etc shall be sold to recyclers.

Solid and Other waste Construction sites are sources of many toxic substances, such as paints, solvents, wood preservatives, pesticides, adhesives and sealants. Such wastes generated during construction phase shall be stored in sealed containers, labeled, and disposed of as required by the Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016. Some management practices to be developed are;

 Herbicides and pesticide will not be over applied (small-scale applications) and not applied prior to rain;  Paintbrushes and equipment for water and oil based paints shall be cleaned within a contained area and shall not be allowed to contaminate site soils, watercourses, or drainage systems.  Adequate storage facilities for such waste shall be provided and the waste collection containers conveniently located. A separate designation to earmark such waste will be made so that the waste storage areas are away from storm drains or watercourses.  Clearly label all such waste containers with the waste being stored and the date of generation.  Educate employees and subcontractors on waste storage and disposal procedures.

M/s. Space Enviro Solutions, Hyderabad. 33

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

B) OPERATIONAL PHASE The philosophy of solid waste management at the Residential apartment will be to encourage the four R’s of waste i.e. waste reduction, reuse, recycling, and recovery (materials & energy). This will reduce in lesser reliance on land filling. Regular public awareness meetings will be conducted to involve the occupants and the employees to ensure proper segregation, storage and collection of waste as per the Solid Waste Management Rules 2016.

The Environmental Management Plan for the solid waste focuses on the Collection, Segregation, at source and disposal as per of the solid waste management rules 2016.

Segregation and storage at source

Segregation of waste at source should be made mandatory for the activity. Segregation or sorting waste at its source should be practiced in order to encourage reuse/recycling. With segregation at source recyclables do not lose their commercial value due to cross contamination. Waste generated at the Residential Apartments should be segregated as: bio degradable, inert cum mixed waste, recyclables. The entire waste stream from the activity should be stored and collected separately.

4.2.5 EMP FOR BIOLOGICAL ENVIRONMENT

Construction activities change the natural environment. But it also creates a built environment for the surrounding. The project requires the implementation of following choices exclusively or in combination.

A) CONSTRUCTION PHASE  Restriction of construction activities to defined project areas, which are ecologically less sensitive.  Restrictions on location of labour camps and offices for project staff near the project area to avoid human induced secondary additional impacts on the flora and fauna species.

M/s. Space Enviro Solutions, Hyderabad. 34

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

 Cutting, uprooting, coppicing of trees or small trees present in and around the project site for cooking, burning or heating purposes by the laborers will be prohibited and suitable alternatives for this purpose will be found.  Along the major construction work the peripheral greenbelt should be developed, so that; it will grow to become a full-fledged green cover by the time the construction is over. B) OPERATION PHASE: Enhancement of current ecology at the proposed project site will entail the following measures:  Plantation & landscaping  Green Belt Development The section below summarizes the techniques to be applied to achieve the above objective

PLANTATION & LANDSCAPING:

Selection of the plant species will be based on their adaptability to the existing geographical conditions and the vegetation composition of the forest type of the region. During the development of the green belt within the project area, it has to be emphasized that those native plant species should be planted which are having good ornamental values and fast growing with excellent canopy cover.

TABLE 4.2: SUGGESTED TREES FOR GREEN BELT DEVELOPMENT Scientific Name Standard Name Ficus Religiosa Peepal Azadirachta indica Neem Tamarindus indica Tamarind Pongamia Pinnata Pongamia Butea Monosperma Flame of Forest

4.2.6 EMP FOR SOCIO-ECONOMIC ENVIRONMENT

The Social management plan has been designed to take proactive steps and adopt best practices, which are sensitive to the socio-cultural setting of the region. The Social Management Plan for the proposed project will focus on the following components.

M/s. Space Enviro Solutions, Hyderabad. 35

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

Income Generation Opportunity during Construction and Operation phase Proposed project would provide employment opportunity during construction and operation phase. There would also be a wider economic impact in terms of generating opportunities for secondary occupation within and around the activity. The main principles considered for employment and income generation opportunities are out lined below:

 Employment strategy would prefer employment of local people.  General recruitment procedures will be transparent, public, open to all and recruitment should be publicized in advance.  There will be no discrimination on basis of gender, caste or other factors.

4.2.7 EMP FOR ENERGY CONSERVATION Energy conservation program will be implemented through measures taken both on energy demand and supply. The Energy conservation will be one of the focuses during the planning and operation stages. The conservation efforts would consist of the following:

ENERGY SAVING PRACTICES:  Purchase of energy efficient appliances.  Constant monitoring of energy consumption and defining targets for energy conservation.  Adjusting the settings and illumination levels to ensure minimum energy used for desired comfort levels.  Installing programmable on/off timers and sensors for low occupancy areas.  Use of compact fluorescent lamps and low voltage lighting.  Sunscreen films on windows to reduce heating inside the buildings

4.3 ENVIRONMENTAL MANAGEMENT SYSTEM AND MONITORING PLAN

Apart from having an Environmental Management Plan, it is necessary to have a permanent staff charged with the task of ensuring its effective implementation of mitigation measures and to conduct environmental monitoring. The major duties and responsibilities of the person – in - charge shall be as given below:

M/s. Space Enviro Solutions, Hyderabad. 36

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

 To implement the Environmental Management Plan,  To assure regulatory compliance with all relevant rules and regulations,  To ensure regular operation and maintenance of Pollution Control Devices,  To minimize environmental impacts of operations by strict adherence to the EMP.  To initiate environmental monitoring as per approved schedule.  Review and interpretation of monitored results and corrective measures in case monitored results are above the specified limit.  Maintain documentation of good environmental practices and applicable environmental laws as ready reference.  Maintain environmental related records.  Coordination with regulatory agencies, external consultants, monitoring laboratories.  Maintain of log of public inconvenience and the action taken

4.3.1 ENVIRONMENTAL MONITORING:

The purpose of environmental monitoring is to evaluate the effectiveness of implementation of Environmental Management Plan (EMP) by periodically monitoring the important environmental parameters within the impact area, so that any adverse affects are detected and timely action can be taken. The following areas will be monitored regularly;

1) Raw water quality of Public Water Supply, bore well water and tanker water (whenever used) will be monitored regularly to ensure suitability for drinking or other domestic usage.

2) The treated water quality shall also be checked on a regular basis particularly at the points of actual use.

3) Water consumption in various areas and for different users will be measured on a regular basis. Water measurement devices will be included in the design itself so that representative water consumption data can be obtained and measures of control instituted.

M/s. Space Enviro Solutions, Hyderabad. 37

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

4) Raw and Treated Sewage will be monitored for general parameters like pH, SS, COD, BOD and Oil & Grease. Also, residual chlorine and coliforms will also be monitored for treated effluent.

5) Ambient air quality within the project area will be monitored quarterly in a year for

PM2.5, PM10, SO2, NOx & CO.

6) Stack emissions with respect to PM, SOx, and NOx level will be regularly monitored from all stacks. The DG stack emissions especially are regulated as per G.S.R- 489(E) dated July 9th, 2002 and compliance to these or TSPCB standards if any, will be ensured.

7) Noise levels will be checked at regular interval near service block with DG sets, boilers, near STP and other noise generating areas.

8) Quantity of solid waste generation will also be measured for the different types of solid waste.

9) Quantity of hazardous wastes generated (waste lube and transformer oil) shall be measured on a regular basis and records of disposal maintained as per the Hazardous and Other Waste (Management & Transboundary Movement) Rules 2016.

10) Numbers of used lead-acid batteries disposed off to authorized vendors/ dealers will be monitored and requisite records maintained.

4.3.2 AWARENESS AND TRAINING

Training and human resource development is an important link to achieve sustainable operation of the facility and environmental management. For successful functioning of the project, relevant EMP’s should be communicated to the following groups of people:

Site Staff Relevant personnel at site must be trained for the following:  Collection, Segregation and Storage of the solid and waste generated during oil change.

M/s. Space Enviro Solutions, Hyderabad. 38

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

 Operation and maintenance of Sewage Treatment Plant and reclamation system  Requirements of the Emergency Response Plan in case of an emergency.  Techniques for waste minimization, water conservation and energy conservation  Applicable environmental, health and safety regulations and compliance requirements for the same.  Functioning of the Environmental Management System including environmental monitoring, reporting and documentation needs.

4.3.3 RECORD KEEPING AND REPORTING

Records should be maintained for regulatory, monitoring and operational issues. Typical record keeping requirements for the project site is summarized in Table 4.3. Table – 4.3: RECORD KEEPING REQUIREMENTS Parameter Particulars Solid Waste Handling and Disposal Daily quantity of waste generated and sent for disposal Sewage Treatment Daily quantity of raw and treated sewage Quantity and point of usage of treated wastewater quality Regulatory Licenses (Environmental) Environmental Permits / Consents from SPCB / MOEF&CC Copy of Waste manifests as per requirement Monitoring and Survey Records of all monitoring carried out as per the finalized Monitoring protocol.

4.3.4 ENVIRONMENTAL AUDITS AND CORRECTIVE ACTION PLANS

To assess whether the implemented EMP is adequate, the project Management Committee will conduct periodic environmental audits. These audits will be followed by Corrective Action Plans (CAP) to correct various issues identified during the audits.

M/s. Space Enviro Solutions, Hyderabad. 39

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

CHAPTER–5 5.0 BUDGET FOR IMPLEMENTATION OF EMP TABLE-5.1 BUDGETARY ALLOCATION - CONSTRUCTION PERIOD

CAPITAL INVESTMENT (IN LAKHS) S.NO. PARTICULARS AMOUNT REMARKS 1 Acoustic Enclosures & Stack 5.0 D.G. Room & Stack height and attached to DG sets Monitoring Platform 2 S.T.P (Sewage Treatment 65.0 Civil Works, Plant & Machinery & Plant) Technical Consultancy charges 3 Rain Water harvesting & 10.0 Civil Works for construction of pits & Storm Water Drain network material 4 Solid waste Management 15.0 OWC, Storage Bins will be provided for Solid waste & Hazardous waste 5 Green Belt Development 10.0 Development of Pits, Sapling cost, Manure & Labour cost 6 Energy Efficient Lighting & 10.0 Solar Street Lights & LED Lighting Solar Power utilization 7 Sanitary Facilities to workers, 10.0 Temporary Toilet facilities to workers, Erosion & Sediment Control Temporary sewerage lining & measures, Safe disposal of Transportation of excavated material, excavated material & Kirby Sheets will be provided, Water construction spoils, Dust sprinkling & Air Sample analysis, Water & control/ Noise attenuation Waste Water Analysis, Soil Sample screens & Monitoring of Analysis & Noise Levels Environmental Parameters Total 125.0

M/s. Space Enviro Solutions, Hyderabad. 40

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

TABLE-5.2: BUDGETARY ALLOCATION - OPERATION PERIOD

COST INCURRED DURING OPERATION PERIOD

S.NO PARTICULARS AMOUNT REMARKS (LAKHS)

1 Monitoring of Environmental 1.0 - Air Sample analysis Parameters - Water Analysis - S.T.P Inlet & Out let sample - Soil Sample Analysis - Noise Levels & - D.G. Stack (Quarterly Monitoring will be by third party)

2 S.T.P Operation & Maintenance 10.0 Chemicals, Employs, Power Charges & Replacement of machinery

3 Greenbelt Development 2.0 Maintenance Cost

4 Solid Waste Management 7.0 Replacement of Bins, MSW Collection Charges, OWC & Labour cost

5 Rainwater harvesting & Storm 2.0 Maintenance cost water drains network & Others

Total 22.0

M/s. Space Enviro Solutions, Hyderabad. 41

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

CHAPTER–6 6.0 BENEFITS OF THE PROJECT

6.1 Employment Generation:

Construction of Residential Apartments will provide employment to a large number of local people. Skilled, Semi-skilled and unskilled man power will be utilized during construction and operation phase. This will positively impact the economic condition of the people in the surrounding area.

6.2 Landscape Development:

After implementation of the project, the green cover of the project area will be enhanced by beautifully landscaped and green cover plantation by native species. This will not only enhance the aesthetic beauty of the region but also nurture, regenerate and enhance the local ecology and biodiversity.

6.3 Economy Improvement:

After implementation of the project it will give rise to employment to the local people in form of direct and indirect employment. Construction of Residential Apartments will also promote allied businesses and facilities in the area. This will result in considerable improvement in the economic condition of the surrounding area.

6.4 Improvement in Infrastructure Facility:

New and better roads will be developed public transport facilities will improve. This will give rise to better infrastructure facilities in the proposed township project and surrounding area.

M/s. Space Enviro Solutions, Hyderabad. 42

M/s.Anuhar Homes Pvt Ltd & Others– Residential Apartments, Sy. No:324/E & 325, Alakapur Township, Narsingi Village, Gandipet Mandal, Rangareddy District, Telangana State. Conceptual Plan & EMP

CHAPTER– 7 7.0 CONCLUSION The proposed project is aimed at developing Residential Apartments. The proposed site is away from city traffic and located in serene environment which will give comfort to guests. Adequate care is taken to protect, preserve and improve the environment around the site. About 1,774.37 Sqm of the area earmarked for development of greenery. It is proposed to take water from Municipal Water Supply. Further rain water harvesting structures proposed to enhance the ground water of the area. The waste water generated is to be treated in house sewage treatment plant and reuse for Flushing, Washing and Gardening.

As the site is well connected with existing road network no additional impact will be there on existing roads. Enough parking place is proposed to be developed for vehicles within the Residential Apartments.

Thus the project is environmentally viable and sustainable.

M/s. Space Enviro Solutions, Hyderabad. 43