General Design Guidelines & Schedule of Design Elements For the

Conceptual Greenway Master Plan From the Indian Valley Golf Course to Glencoe Mill Village

August 2007

Prepared for The City of Burlington Recreation and Parks Departments In partnership with The Alamance County Recreation and Parks Department

Funded by the Program

Prepared by the Council of Governments

______

General Haw River Trail Design Guidelines

The following general trail design guidelines illustrate typical trail dimensions and construction practices for the Haw River Trail (HRT) system. They are intended to be used as suggested practices for constructing the HRT system and may not apply to every situation, based on varying site conditions.

Trail Construction Guidelines Trail construction standards for the HRT are defined for both urban and rural trail cross-sections designed for use by pedestrians, hikers, bicyclists and horseback riders in some sections. The urban cross-section (see Figure 1 below) can be constructed in the more densely populated urban regions of the trail, with the rural cross-section (see Figure 2 below) applied in the more rural &/or environmentally sensitive areas. The HRT is a non-motorized trail. See Table 1 below for trail construction guidelines for both the urban and rural cross-sections.

Figure 1 – Urban Cross-Section Trail Construction Guidelines Recreational Trail Design and Construction – University of Minnesota Extension Service, 2007

______Haw River Trail Conceptual Greenway Master Plan Page 1 ______

Figure 2 – Rural Cross-Section Trail Construction Guidelines Recreational Trail Design and Construction – University of Minnesota Extension Service, 2007

______Haw River Trail Conceptual Greenway Master Plan Page 2 ______

Table 1 – Trail Construction Guidelines for Urban & Rural Cross-Sections

DESIGN ELEMENT URBAN TRAIL CROSS SECTION RURAL TRAIL CROSS SECTION Clearing Width 10 to 14 feet 7 to 9 feet Tread Width 6 to 10 feet 3 to 5 feet Tread Surface 4 inches crushed rock base Natural / native soil that has been compacted Firebreak (optional) 10 feet of fire resistant native N/A vegetation on each side of trail. Total corridor width should equal 30 feet DESIGN ELEMENT URBAN AND RURAL CROSS SECTIONS Percent Grade Grades should not exceed 10 percent because they become difficult for trail users to sustain & lead to trail erosion problems. Desired Grade: 0 to 5 percent Maximum Grade: 5-10 percent (sustained), 15 percent (shorter than 50 yards) Out-Slope Grade: 4 percent (maximum) Clearing Height 8 – 10 feet (10 - 12 feet to allow for horseback riding). Additional clearance may be needed to compensate for branches drooping with heavy rain or snow. Trail Layout Wet areas and steep slopes pose extreme difficulties to trail maintenance and should be avoided. Keep water and motorized road crossings to a minimum. Frequently occurring curves and grade changes will add interest. Turning Radius Wide, gentle curves with good forward sight distances are critical for safety, aesthetically pleasing, and easier to maintain. Avoid sharp-angled turns, turns on steep slopes, or turns at the base of a hill. Sight Distances Forward sight distances of 100 feet (50 feet minimum) are important because the trail may be shared by hikers, equestrians, and bicyclists. Although curves should be carefully designed to maintain good sight distances, turns and bends tend to help reduce travel speeds and add variety to the trail experience. Road Crossings Motorized road crossings must be carefully located, designed, and signed 100 to 200 feet in advance to insure that trail users and vehicle drivers have good sight distances in all directions.

______Haw River Trail Conceptual Greenway Master Plan Page 3 ______

Table 1 – Trail Construction Guidelines for Urban & Rural Cross (continued)

DESIGN ELEMENT URBAN AND RURAL CROSS SECTIONS Some water crossings along the HRT require bridges. Bridges should generally be used in areas of perennial and Water Crossings intermittent stream crossings. However, slow-moving water less than 24 inches deep may be forded or culverted. Bridge design should meet the following requirements: • meet the needs and weight of horse travel; • orient planking at a 45- to 90-degree angle to the direction of travel, gaps between planking oriented in the direction of travel may trap bicycle tires and endanger trail users; • make approaches straight, level, and when possible, at least 100 feet long; • must be located above ordinary high water mark; • have railings or log barriers on both sides; • have an 8-foot minimum width for horses; and • weight capacity varies depending on maintenance equipment and length of bridge. Parking area with space for trailers, picnic area, resting areas, Other Facilities overlooks, campsites, water, information board, signs, hitching post or tether line, horse corral, sanitation facilities, restrooms. • Helps with orientation and way-finding Signage • Helps with safety issues such as road crossings • Shows etiquette for all users • Gives distances

Recreational Trail Design and Construction – University of Minnesota Extension Service, 2007

Trail Accessibility Guidelines An important part of trail design is designing for accessibility that will allow everyone to enjoy a trail experience. Communities planning and constructing portions of the HRT have an opportunity to develop segments of the trail that are accessible. Accessible segments could be located anywhere along the trail, but locating them in more urban areas that are using the urban trail cross- section standards would best serve most users. Much of the following guidance on how to make the HRT accessible comes from the Americans with Disabilities Act Accessibility Guidelines (1991) and Designing Sidewalks and Trails for Access (1999). For more specific information about accessibility, reference these materials.

______Haw River Trail Conceptual Greenway Master Plan Page 4 ______

Accessible trails should be free of debris and avoid motorized roadway crossings whenever possible. Crushed rock or a road base material with a high clay content that has been rolled and compacted may be used for wheelchair access. Trail grades should be generally flat (5 percent maximum grades for short distances) and regular rest stops provided. The cross-slope should not be greater than 2 to 6 percent. Bridges should have handrails, and their decks must be flush with the trail surface. Decking boards on bridges and boardwalks should be positioned perpendicular to the trail path with gaps between boards not exceeding .375 inches. Visually impaired persons can use natural trail treads with guide ropes or definite edges such as logs or railroad ties. An accessible trail information sign should be place at the trail entrance that describes the length and difficulty of the trail, the location of rest stops, and any potential trail hazards. Rest rooms, parking lots, and ramps should be carefully designed to ensure access.

Guidelines for Sustainable & Aesthetic Trail Construction A sustainable trail surface can be created with minimal disturbance and maximum variety and interest as the following goals are met: • Minimize soil disturbance in order to allow plants and animals the best chance for survival; aesthetic appeal will be correspondingly high. • Eliminate the potential for erosion. • Use correct and aesthetic pruning or removal of tree limbs and shrubs. • Minimize drainage problems by removing water from the trail at the first opportunity. • Do not allow water to stand on the trail. • Maintain existing drainage patterns whenever possible; do not force nature. • Outslope the trail to dispose of sheet drainage and carefully shape the trail back-slope to prevent erosion. • Coordinate excavation with vegetation and drainage considerations. • Use select borrow or retaining walls to improve in adequate trail surfaces. • Attain proper slope and compaction through a detailed analysis of on-site conditions during wet and dry periods. • Make decisions to benefit the trail users. • Remove sharp plants from close proximity to the trail. • Consider the physical and visual relationship of vegetation to the trail. • Where appropriate, narrow the clearing width by leaving brush close to the trails edge; excessive clearing allows bicycles to travel faster and leave the trail when cornering. • Retain dead standing trees (i.e. “snags”) when safety permits to provide homes and feeding locations for wildlife. • Consider erecting nest boxes or creating artificial snags in woodlands near the trail route.

______Haw River Trail Conceptual Greenway Master Plan Page 5 ______

Rural Trail Cross-Section Construction Guidelines

Step One - Stake the Route • Stake the trail route from start to finish. Stakes may be included for the center-line or both sides of the trail, and may also define clearing limits.

Step Two – Cut and Clear the Vegetation • Begin construction by removing trees, brush, and rocks from the tread. • Site characteristics will determine what tools are needed. Hand tools, such as axes, loppers, bow saws, weed whips, and chain saws will be sufficient in most cases. • The trail can be cleared much faster with motorized equipment. However, motorized equipment is not recommended for trail segments less than 4 feet wide. • Cut shrubs and small trees flush with the ground to prevent tripping and to reduce stump sprouting. Avoid cutting healthy trees larger than 7 inches in stem diameter. Some trees, such as box elder, elm, and cottonwood, may require chemical stump treatments to prevent re-sprouting. • Prune overhanging branches cleanly at the branch collar on the tree trunk or where a branch forks. To avoid rapid re-growth, it may be better to remove small trees than to cut off their tops. • Trim exposed roots flush with the soil surface. • Remove large rocks and fallen logs from the trail, unless they are to be kept as obstacles to prevent motorized use. • Scatter branches and other debris off the trail or pile for wildlife cover.

Step Three - Grade the Trail Bed • Grade the trail bed on slopes as required. • On slopes, remove leaf litter and topsoil material from the cut-and-fill areas and save for later use as necessary. • Select an angle for cut-and-fill slopes based on site soil conditions, amount of rainfall, and plant cover. Retain cut & fill slopes at less than 1:1. • Spread topsoil and organic material on large embankments susceptible to erosion to encourage vegetation regeneration. • On very steep slopes use netting material, such as jute mesh or chicken wire held in place with stakes, to hold the topsoil and mulch in place. • Round out the top of embankment shoulders to prevent soil from sliding onto the trail. • Remove boulders, logs, and other debris that may fall onto the trail. • Avoid disturbing plants at the top of the cut slopes and at the base of embankments. • Pitch the trail tread at 1.5-3.0 percent toward the outside edge to allow for drainage.

______Haw River Trail Conceptual Greenway Master Plan Page 6 ______

• Make the tread slightly wider in areas where sloughing of the trail edge is likely to occur. • On talus or rubble where little or no soil is present, construct the outside part of the trail with hand placed rocks, 50 percent of which are 12 inches in diameter or greater. Build the outside bench from rock other than those forming the inside bench. Fill in all voids and under the trail bed surface with rock and mineral soil deep enough to provide a firm tread.

Step Four - Finish the Trail Tread • For the rural & environmentally sensitive segments of the HRT corridor, the ideal surface is natural soil free of large stones, stumps & protruding roots. • Natural trails often become easily distinguishable and comfortable to walk on after a month of regular traffic. • Always avoid unnecessary disruptions of the ground surface. If leveling is required, use a shovel, small caterpillar (D-2 or equivalent) or Sweco 480 trail dozer to sheer off a thin layer of topsoil, level humps, and fill holes. • Gravel or other fill materials may be used to elevate the trail in wet areas.

Urban Trail Cross-Section Construction Guidelines The urban trail cross-section is most likely to be constructed using trail construction professionals and a mixture of hand and mechanized trail construction equipment. The two trail construction machines most often used are the small caterpillar (D-2 or equivalent) or the Sweco 480 trail dozer. These machines clear and grade the trail after the necessary vegetation has been removed from the staked trail corridor. Handwork includes grading the side slopes, removing vegetation, construction in trail obstacle areas, and placing or removing waste vegetation. After the trail has been graded, the crushed rock fill is placed in the tread area and compacted using the trail dozer.

Trail Signage Guidelines Once constructed, the Haw River Trail should be clearly marked using the standard HRT trail marker (see Figure 3 below) to assist users in way-finding. A 4”X4”X10’ pressure-treated post is recommended to hold HRT trail markers in the initial Indian Valley to Glencoe section. However, as the Haw River Trail expands, other options may be considered. Other regional trails utilize a plastic (“carsonite”) stake marked with a trail logo. These stakes are placed at regular intervals and at junctions along the trail. The number of signs should be kept to a minimum to avoid detracting from the user's outdoor experience and to minimize vandalism or theft. Entrance signs should be placed at all HRT trail heads. These signs should include maps, trail distances, potential hazards, places of interest, and the types of trail uses permitted. Examples of options for HRT entrance, trail signs and kiosks are provided below (see Figures 4, 5 and 6).

______Haw River Trail Conceptual Greenway Master Plan Page 7 ______

Figure 3 – Haw River Trail Logo Courtesy of Brian Baker – Haw River Coordinator

Figure 4 – Typical Haw River Trail Way-Finding Sign (Initial Mock-Up) Courtesy PTCOG

______Haw River Trail Conceptual Greenway Master Plan Page 8 ______

Figure 6 – Typical Information Sign / Kiosk Construction Option Courtesy of National Park Service – North Country Trail Handbook

Figure 5 – Glencoe Park Entrance Sign Courtesy of Alamance County Recreation and Parks Department

______Haw River Trail Conceptual Greenway Master Plan Page 9 ______

Guideline for Addressing Trail Obstacles Along the trail route obstacle may be encountered that requires special attention. Recognizing and protecting such areas during construction will help reduce later maintenance costs and potential environmental damage. Some measures are relatively simple and inexpensive while others can be quite difficult and/or expensive to employ.

Subsurface Drainage Guidelines Water tends to pool on trails that are located on low-lying, level terrain. Raising the tread-way 3 to 6 inches (or more) above the surrounding terrain will allow water to drain away, reduce maintenance costs, and help ensure comfortable trail use. Gravel, flat stones, or other fill material may also be used to elevate the trail surface (see Figure 7 below). A less expensive technique for moving water off the trail is center crowning. Fill materials can be obtained from gutters cut on both sides of the trail to facilitate drainage.

Figure 7 – Subsurface Drainage Measures Recreational Trail Design and Construction – University of Minnesota Extension Service, 2007

______Haw River Trail Conceptual Greenway Master Plan Page 10 ______

Surface Drainage Guidelines On steep slopes, poorly designed and constructed tread ways allow water to accumulate, gain downhill velocity, and erode the trail. Flowing water must be diverted off the trail. One effective method is to “out-slope” the trail surface at a 2 to 3 percent grade toward the downhill side (see Figure 8). Grade dips or water bars may also be used. Grade dips are short trail sections cut at a grade opposite that of the prevailing trail surface. Grade dips typically are established at natural drainage ways or ditches with intermittent flows (See Figure 9). Water bars are obstructions on the trail surface designed to divert water off the trail. Water bars are usually constructed with logs or stones placed at a 30-degree angle from the trail's edge. Water bars must extend well beyond both sides of the trail to prevent water or people going around them. Logs must be at least 6 to 8 inches in diameter. Rubber water bars are another option that reduces potential hazards to bicyclists (See Figure 10). The number of water bars should be increased as the trail's grade increases (see Table 2 below). Figure 8 – Bench Cut & Out Sloping Recreational Trail Design and Construction

Figure 9 – Grade Dip Recreational Trail Design and Construction

______Haw River Trail Conceptual Greenway Master Plan Page 11 ______

Figure 10 – Rubber Water Bar Recreational Trail Design and Construction

Table 2 – Recommended Water-Bar Spacing for Various Trail Slopes. PERCENT GRADE SPACING BETWEEN WATER BARS (FEET) 2% 250 Feet 5% 130 Feet 10% 80 Feet 15% 50 Feet 25%+ 40 Feet

Stream Crossing Guidelines The Haw river Trail crosses over multiple small streams and tributaries. Fords (or natural crossings) can be used to traverse very small, slow-moving streams (e.g. less than 12 inches deep). Locations with gently sloping, stable banks and gravel or sand bottoms should be favored. Most hikers can safely negotiate a ford crossing on flat stones placed at convenient intervals. Culverts are recommended to cross deeper streams or ditches (see Figure 11). Professional assistance is required for design and installation of a culvert stream crossing. Bridge designs vary depending on the length and height of the crossing, type and amount of trail use, and the size of maintenance equipment. Whenever possible, structural bridge design elements such as abutments should be located above the ordinary high water mark - the point where the predominant natural vegetation changes from aquatic to terrestrial (see Figure 12). On hiking trails, a simple split-log bridge may be used for stream crossings less than 10 feet wide (see Figure 13) and a whole-log bridge may be used for wider crossings (see Figure 14). Professional assistance should be sought to assist in designing and installing more elaborate, high-use bridge crossings (see Figure 15 & Figure 16).

______Haw River Trail Conceptual Greenway Master Plan Page 12 ______

Figure 11 – Various Culvert Designs Recreational Trail Design and Construction

Figure 12 – Normal High Water Mark Recreational Trail Design and Construction

______Haw River Trail Conceptual Greenway Master Plan Page 13 ______

Figure 13 – Simple Split Log Bridge Figure 14 – Rustic Whole-Log Bridge Recreational Trail Design and Construction Courtesy PTCOG

Figure 15 – Typical Timber Bridge Construction Guidelines Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

Figure 16 – Prefabricated Steel Span Bridges Courtesy of Surry County Greenway Master Plan – Greenways, Inc.(Note: Prefabricated span bridges are ordered directly from the manufacturer. Approximate cost is $100/foot. For examples & quotes, see www.steadfastbridge.com.

______Haw River Trail Conceptual Greenway Master Plan Page 14 ______

Boardwalk Trail Tread Boardwalks, or wood surface trails, are typically required when crossing wetlands or poorly-drained areas. While boardwalks can be considered multi-use trails, the surface tends to be slippery when wet and not best suited for wheeled users. Boardwalks intended for use by bikes, pedestrians, in-line skaters and others should be a minimum of 14 feet wide. However, boardwalk trails limited to pedestrian use can be as narrow as 8 feet (see Figure 17). If maintenance vehicles use the boardwalk for maintenance access, it should be a minimum of 14 feet. Wood surfaced trails are usually composed of sawn wooden planks or lumber that forms the top layer of a bridge, boardwalk or deck. The most commonly used woods for trail surfacing are exposure- and decay- resistant species such as pine, redwood, fir, larch, cedar, hemlock and spruce. Wood is a preferred surface type for special applications because of its strength and comparative weight, its aesthetic appeal and its versatility. Synthetic wood, manufactured from recycled plastics, is now available for use as a substitute in conventional outdoor wood construction. While these products are more expensive than wood lumber, recycled plastic lumber lasts much longer, does not splinter or warp and will not discolor.

8’-0” to 14’-0” (Width varies depending on use)

Figure 17 – Typical Boardwalk Cross Section Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

______Haw River Trail Conceptual Greenway Master Plan Page 15 ______

Fence Crossing Guidelines A self-closing gate or stile will reduce fence damage and permit safe crossing. Stile designs vary depending on the size of the livestock and the availability of building materials (see Figure 18).

Steep Slope Guidelines Grade is a measurement of trail slope generally expressed as a percentage. Percent grade is equal to vertical distance divided by horizontal distance times 100. For example, an 8 percent grade is one that goes up or down 8 feet for every 100 feet of length. Acceptable trail grades depend on the recreational activity and soil structure. A sustained grade (i.e. a grade that remains the same for more than 1,000 feet) generally should not exceed 10 percent, although Figure 18 – Fence Crossing Options this limit may be exceeded for short Recreational Trail Design and Construction distances (50 yards) up to a maximum of about 25 percent. Long, steep grades tire trail users and allow drainage water to flow down the trail creating potential erosion problems. Conversely, level grades tend to bore trail users and allow water to accumulate on the trail bed. To facilitate natural drainage and increase user interest, frequently alternate steep and level grades. As a rule of thumb, trails should be 1/3 level, 1/3 uphill, and 1/3 downhill. Switchbacks or steps may be necessary to traverse steep slopes. Switchbacks are designed to reduce trail grades by lengthening the trail (see Figure 19). Switchback turns (or landings) must be located on stable soils to reduce erosion. Flat benches or areas with the least slope should be favored. Timber steps may be used to level the landing and reduce erosion. A minimum turning radius of 4 feet is required for hiking trails; 8 feet is required for other trail users. Log, rock, or shrub barriers may need to be constructed at trail turns to keep users on the trail and to avoid the creation of shortcuts. Attractive features such as benches and vistas may be located at switchback turns. Steps may be needed on steep terrain with highly erodible soil, but have several drawbacks. They may be costly to construct, restrict trails to summer use, and prohibit access for some disabled persons. Construction materials for steps include stone slabs, railroad ties, or rough-sawn, rot-resistant timbers (see Figure 20). Steps should rise at least 5 inches, but not more than 9 inches. Stairways may be required on slopes exceeding 100 percent (45 degrees).

______Haw River Trail Conceptual Greenway Master Plan Page 16 ______

Figure 19 – Switchback Options Recreational Trail Design and Construction

Figure 20 – Steps and Stairway Options Recreational Trail Design and Construction ______Haw River Trail Conceptual Greenway Master Plan Page 17 ______

Paddle Trail Access Guidelines Designated and improved paddle trail access sites are an extremely important component of the Haw River Trail system. Paddle access sites should be strategically located every three to five miles along the HRT corridor, to maximize recreational opportunities for canoeing, kayaking and boating (see Figure 21). Paddle trail access sites should coincide with trailheads for the land- based trail system whenever possible, to efficiently provide the necessary amenities necessary to insure a safe and enjoyable experience for trail users of all ages and abilities (e.g. parking, restrooms, orientation brochures & maps, equipment rental, etc.).

Figure 21 – Typical Small Boat Access Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

Trail User Conflict Guidelines A wide variety of user groups are encouraged to use the Haw River Trail. Hikers, walkers, joggers, cyclists, mountain bikers, horseback riders, paddlers, and a range of school & environmental education groups, may all be using the trail at various times. This broad spectrum of trail users has the potential for conflict because of their varying trail needs and styles of recreation. Signs, speed limits, and good user etiquette along the HRT corridor can help minimize conflicts between these user groups. In addition, educating users and promoting responsible behavior on the HRT can minimize user conflicts. For example, trail users should be encouraged to maintain two-way communication and make an effort to warn others of their needs and intentions. Trail etiquette standards can be publicized on trail signs and in educational materials.

______Haw River Trail Conceptual Greenway Master Plan Page 18 ______

If specific user conflicts are anticipated along certain segments of the trail a yield sign may be needed (e.g. showing bicycles yielding to joggers and hikers, and joggers yielding to hikers – see Figure 22). Trail users may be less likely to become offended at the actions of others once they understand the code of conduct. Trail users are also less likely to violate an established code of behavior if they believe these rules will be enforced. Figure 22 – Yield Sign Example Courtesy of Northern Bonneville Shoreline Trail Master Plan Damage Control Guidelines A certain amount of vandalism, as well as accidental damage, can be expected on heavily used trails that are open to the public. Damaged and vandalized items, if not promptly removed or repaired, often stimulate more damage. Therefore, regular inspection of trails with early identification of damaged areas will help reduce vandalism. Proper trail design methods can also reduce damage. Trail routes should be selected that avoid sensitive environmental areas. Brush piles, drainage ditches and vegetation can help encourage users to stay on the trail. Trail signs can also encourage appropriate use of the trail. When space permits, explain the reasons for protecting the area (e.g. "Prevent erosion - Please stay on trail".

Trail Maintenance Guidelines A maintenance program helps ensure the safety of the trail user and the preservation of the trail environment. A high maintenance standard implies quick response to trail deterioration. Programs such as “Adopt a Trail” encourage local volunteers to maintain a section of trail as a service for all the recreational users of the trail.

General Trail Maintenance Guidelines • Practice environmentally sound maintenance and use techniques appropriate for the type of trail. For example, avoid the use of chemicals to retard vegetation growth. • Prepare an annual Trail Maintenance Plan. • Assess the type and volume of use with trail register records and by counting the type and volume of vehicles at the trailhead. • Repair heavily-used segments of the trail in the spring and maintain the trail throughout the season on an as-needed basis. • Prioritize trail maintenance tasks by the following criteria: 1) correct unsafe trail conditions, 2) repair environmental damage, and 3) restore the trail to the desired conditions.

______Haw River Trail Conceptual Greenway Master Plan Page 19 ______

Annual Spring and Early Summer Trail Maintenance Tasks • Clear windfalls and dangerous trees from the trail bed for safety and to prevent detouring. • Remove loose rocks and debris from the tread surface. • Repair trail wash-outs. • Remove new plant growth on the trail annually. Clear in the spring and early summer when the new growth is soft. • Level the trail tread as necessary and restore the tread grade to the original slopes. Use local material to fill ruts, holes, low spots, or muddy areas. • Repair erosion-damaged facilities promptly to prevent further damage. Check for erosion effects after spring runoff. • Check and repair water bars, drainage ditches, culverts, and drainage dips. • Construct additional drainage structures as needed. • Check and repair all structures after spring runoff and after severe summer storms. • Check, repair, or replace signs and trail markers prior to the major use season.

Weekly or Monthly Trail Maintenance Tasks (As Trail Use Warrants) • Maintain trailhead facilities such as toilets or waste containers. • Re-supply trailhead information kiosks with route or safety brochures & maps.

General Trail Corridor Planting Guidelines • Seek to eliminate non-native invasive species (e.g. Ligustrum sinense). • Replant native over-story & under-story trees & shrubs where vegetation is removed or harmed due to construction of trails. • Do not remove fallen trees unless they obstruct trails or present some danger. • Use evergreens, conifers (pines) and deciduous trees proportionally. • Use trees & shrubs with berries whenever possible to provide food for wildlife. • Use flowering trees & shrubs to draw attention to important features. • Use evergreen shade trees near seating areas and picnic tables. • Use evergreen shrubs (e.g. wax myrtle) to screen private residences.

______Haw River Trail Conceptual Greenway Master Plan Page 20 ______

Tree Planting Guidelines Trees are important to greenways and trails for both aesthetic and environmental reasons. Not only do they contribute to the appearance of a trail, their shade cools the environment for trail users and provides habitat for birds and wildlife. Trees also help keep streams healthy by providing shade (which regulates the temperature), filtering pollutants in storm runoff and adding leaf litter to feed small insects and fish. When choosing trees and shrubs for greenway corridors, it is recommended that indigenous and well- adapted species be used. This will reduce the need for chemical and water applications as a part of long term maintenance. The following graphics (see Figure 23 & Figure 24) represent common installation practices used for several different types of plant material. Figure 23 – Ball and Burlap Tree Planting Detail Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

Figure 24 – Bare Root Tree Planting Detail Courtesy of Surry County Greenway Master Plan – Greenways, Inc. ______Haw River Trail Conceptual Greenway Master Plan Page 21 ______

Shrub Planting Guidelines The amount of planting needed will vary depending on the project. While some projects will require little or no planting, other projects may require it for vegetative screening, habitat restoration, erosion control or aesthetics. The graphics below illustrate planting techniques for two types of shrub material (ball & burlap and bare root) which can be used (see Figure 25 & Figure 26).

Figure 25 – Ball and Burlap Shrub Planting Detail Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

Figure 26 – Bare Root Shrub Planting Detail Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

______Haw River Trail Conceptual Greenway Master Plan Page 22 ______

General Trailhead Guidelines Trail heads should be installed throughout the Haw River Trail system to give the public access. A “trail head” is a point of formal public entry into the greenway system that may provide certain related public facilities such as parking, restrooms, drinking fountains and trail signage (see Figure 27). Major trail heads should be located in significant areas. An exhibition building or an interpretive exhibit may be incorporated, along with restrooms, water fountains, picnic tables, parking, signage. Minor trail heads can be used to connect a smaller number of people to surrounding trails, open space and parks.

Figure 27 – Typical Trailhead Plan View Courtesy of Surry County Greenway Master Plan – Greenways, Inc.

______Haw River Trail Conceptual Greenway Master Plan Page 23 ______

Schedule of Design Elements – SIGNS Indian Valley Golf Course Sub-Section POST NUMBER SIGN NUMBER LOGOS & WORDING FACE DIRECTION NOTES and TYPE Sign Post #1 Sign #1A HRT LOGO (Top Center) Up-River VW - Vehicular Hiking (right arrow) → Way-Finding Paddling (right arrow) →

Sign Post #2 Sign #2A HRT Logo (Top Center) Down-River VW - Vehicular ← (left arrow) Hiking Way-Finding ← (left arrow) Paddling

Sign Post # 3 Sign #3A ↑ (up arrow) Away from River TW – Trail Way- HRT Logo (Top Center) Finding Glencoe Park Trail Head (2 Miles)

Sign Post #4 Sign #4A HRT LOGO (Top Center) Away from River PA – Paddling PADDLING LOGO (Center) Access Site Glencoe Dam Portage (1.0 Mile) ← (left arrow)

Sign #5A ↑ (up arrow) Up- River TW - Trail Way- HRT LOGO (Center) Sign Post #5 Finding Sign #5B ↑ (up arrow) Down- River TW - Trail Way- HRT LOGO (Center) Finding Sign Post #6 Sign #6A ↑ (up arrow) Away from River TW - Trail Way- BINOCS LOGO (Center) Finding

______Haw River Trail Conceptual Greenway Master Plan Page 24 ______

Schedule of Design Elements – SIGNS (continued) SIGN POST NUMBER SIGN NUMBER LOGOS & WORDING FACING DIRECTION NOTES Sign #7A ↑ (up arrow) Away from River TW - Trail Way- HRT LOGO (Center) Sign Post #7 Finding Sign #7B HRT LOGO (Center) Toward-River TW - Trail Way- → (Right arrow) Finding Sign #8A ↑ (up arrow) Away from River TW - Trail Way- HRT LOGO (Center) Sign Post #8 Finding Sign #8B HRT LOGO (Center) Toward-River TW - Trail Way- ← (Left arrow) Finding Sign #9A ↑ (up arrow) Toward-Golf Course TW - Trail Way- HRT LOGO (Center) (Away from Bridge) Finding Sign #9B → (right arrow) Away from Golf Sign Post #9 TW - Trail Way- HRT LOGO (Center) Course Finding (Toward Bridge) Sign #9C WARNING Away from Golf W - Warning Stay on Trail Course Watch for golf balls! (Toward Bridge) Sign Post #10 Sign #10A ↑ (up arrow) Up- River TW - Trail Way- HRT LOGO (Center) Finding Sign #10B ↑ (up arrow) Down- River TW - Trail Way- HRT LOGO (Center) Finding

______Haw River Trail Conceptual Greenway Master Plan Page 25 ______

Schedule of Design Elements – SIGNS (continued) SIGN POST NUMBER SIGN NUMBER LOGOS & WORDING FACING DIRECTION NOTES

Sign #11A ↑ (up arrow) Down-River TW - Trail Way- HRT LOGO (Center) Finding Sign #11B ↑ (up arrow) Up-River Sign Post #11 TW - Trail Way- HRT LOGO (Center) Finding Sign #11C WARNING Up-River W - Warning Stay on Trail Watch for golf balls! Sign #12A ↑ (up arrow) Up- River TW - Trail Way- HRT LOGO (Center) Finding Sign #12B RESTROOMS LOGO (Center) Up-River TW - Trail Way- ← (left arrow) Sign Post #12 Finding Sign #12C ↑ (up arrow) Down- River TW - Trail Way- HRT LOGO (Center) Finding Sign #12D RESTROOMS LOGO (Center) Down-River TW - Trail Way- → (Right arrow) Finding

______Haw River Trail Conceptual Greenway Master Plan Page 26 ______

Schedule of Design Elements – SIGNS (continued) Glencoe Mill Village Sub-Section SIGN POST NUMBER SIGN NUMBER LOGOS & WORDING FACING DIRECTION NOTES

Sign #13A ↑ (up arrow) Up-River TW – Trail Way- HRT LOGO (Center) Finding Glencoe Park Trail Head (0.5 Miles) Sign Post #13 Sign #13B ↑ (up arrow) Down-River TW – Trail Way- HRT LOGO (Center) Finding Indian Valley Trail Head (1.3 Miles)

Sign #14A HRT LOGO ↑ (up arrow) Up- River TW – Trail Way- Glencoe Island Trail → (right arrow) Finding PADDLING LOGO (450 Feet) → Sign Post #14 Sign #14B HRT LOGO ↑ (up arrow) Down- River TW – Trail Way- ← (left arrow) Glencoe Island Trail Finding ← PADDLING LOGO (450 Feet)

Sign Post #15 Sign #15A HRT LOGO ↑ (up arrow) Up- River – Toward TW – Trail Way- PADDLING LOGO → (right arrow) Portage Take-Out Finding Glencoe Island Put-In Sign #15B HRT LOGO ↑ (up arrow) Down- River – Toward TW – Trail Way- Island Finding Sign #15C HRT LOGO (Top Center) Away from River TW – Trail Way- Glencoe Island Trail ↑ (up & left arrow) Finding PADDLING LOGO ↑ (up & left arrow) Glencoe Island Put-In

______Haw River Trail Conceptual Greenway Master Plan Page 27 ______

Schedule of Design Elements – SIGNS (continued) SIGN POST NUMBER SIGN NUMBER LOGOS & WORDING FACING DIRECTION NOTES

Sign #16A HRT LOGO (Top Center) Away from River W – Warning WARNING – DAM AHEAD Sign Post #16 Do NOT put in here!

Sign #16B HRT LOGO (Top Center) Toward River W - Warning WARNING – DAM AHEAD (Slightly Up-River) Mandatory Portage - Take-Out Now!

Sign Post #17 Sign #17A HRT LOGO (Top Center) Away from River On Island: TW – Trail Way- ← Mill Race Outlet (0.3 Miles) (Toward Trail) Use posts & ropes Finding ← PADDLING LOGO (450 Feet) to discourage Glencoe Island Put-In paddling access Please Stay on Trail down steep bank Sign Post #18 Sign #18A HRT LOGO (Top Center) Away from River On Island TW – Trail Way- PADDLING LOGO (Center) (Toward Trail) Finding Optional Paddling Information ← Glencoe Park Access (0.4 Miles) ← Carolina Mill Access (1.3 Miles) ← Goat Island Bridge (3.2 Miles)

Sign #19A ↑ (up arrow) Up-River Located at TW - Trail Way- HRT LOGO (Center) Existing Gate Sign Post #19 Finding Glencoe Park Trail Head (0.4 Miles) Along Old Road Sign #19B ↑ (up arrow) Down-River Located at TW - Trail Way- HRT LOGO (Center) Existing Gate Finding Indian Valley Trail Head (1.3 Miles) Along Old Road

______Haw River Trail Conceptual Greenway Master Plan Page 28 ______

Schedule of Design Elements – SIGNS (continued) SIGN POST NUMBER SIGN NUMBER LOGOS & WORDING FACING DIRECTION NOTES

Sign #20A HRT LOGO (Center) Up-River TW - Trail Way- PADDLING LOGO (Right arrow) → Finding ??RESTROOMS LOGO (Right arrow) → Sign Post #20 Sign #20B HRT LOGO (Center) Down- River TW - Trail Way- ← (Left Arrow) PADDLING LOGO Finding ← (Left Arrow) RESTROOMS LOGO??

Sign #21A Handicap Toward River Sign Post #21 P - Parking Wheelchair LOGO (Center) Parking

Sign #22 HRT LOGO (Top Center) Away from River Color: Brown Sign Post #22 VW - vehicular HIKING LOGO (right arrow) → Located in public way finding PADDLING LOGO (right arrow) → road right of way

Sign #23 HRT Logo (Top Center) Toward River Color: Brown Sign Post #23 VW - vehicular ← (left arrow) HIKING LOGO Located in public way finding ← (left arrow) PADDLING LOGO road right of way

Schedule of Design Elements – KIOSKS KIOSK NUMBER KIOSK TYPE LOCATION FACING DIRECTION NOTES

Kiosk #1 TP - Two Post Indian Valley Golf Course Trail Head Parallel with River Kiosk #2 TP - Two Post [FUTURE] Greenwood Drive Trail Head Parallel with River Future Kiosk #3 TP - Two Post Glencoe Park Trail Head Parallel with River

______Haw River Trail Conceptual Greenway Master Plan Page 29 ______

Schedule of Design Elements – BRIDGES / CULVERTS / BOARDWALKS ITEM NUMBER TYPE DIMENSIONS RAILING NOTES

Bridge #1 Wooden 5 to 8Feet Wide X 10 Feet Long YES

Bridge #2 Wooden 5 to 8 Feet Wide X 10 Feet Long YES

Bridge #3 Wooden 5 to 8 Feet Wide X 15 Feet Long YES

Bridge #4 Wooden or 5 to 14 Feet Wide X 25 Feet Long YES Steel Pre-Fab Boardwalk #1 Wooden 5 to 8 Feet Wide X 40 Feet Long YES

Culvert #1 PVC 12 Inch Diameter X 10 Feet Long NO

Culvert #2 PVC 12 to 18 Inch Diameter X 10 Feet Long NO

______Haw River Trail Conceptual Greenway Master Plan Page 30 ______

Schedule of Design Elements –SWITCHBACKS / STEPS ITEM NUMBER TYPE DIMENSIONS RAILING NOTES

Switchback #1 Full-Bench

Switchback #2 Full-Bench

Steps #1 Wooden Approximately 7 Feet Rise x 18 Feet Run Central (6 to 8 inch Risers X 12 to 18 inch treads) Two-Rail Boat Slide

Schedule of Design Elements – PADDLING ACCESS SITE IMPROVEMENTS PADDLING ACCESS TYPE LOCATION DIMENSIONS NOTES SITE NUMBER

Access Site #1 Beach Indian Valley Trail Head Add minimal sand or rock (At Sign Post #4) dust to existing beach area

Access Site #2 Wooden or Mandatory Portage Approximately 4 Feet Rise X (At Sign Post #16) Rock Steps Take-Out Above 8 Feet of Run Glencoe Dam Access Site #3 Beach Portage Put-In Add minimal sand or rock (At Sign Post #18) Below Glencoe Dam dust to existing beach area

Access Site #4 Wooden or Glencoe Park Trail Approximately 6 Feet of Rise Rock Steps Head X 12 Feet of Run

______Haw River Trail Conceptual Greenway Master Plan Page 31 ______

Schedule of Design Elements – BENCHES / PICNIC TABLES / TRASH RECEPTACLES? / PORTAJOHNS? ITEM NUMBER TYPE DIMENSIONS COMPANY NOTES

Bench #1 6 Feet Long

Bench #2 6 Feet Long

Picnic Table #1 8 Feet Long

Picnic Table #2 8 Feet Long

Picnic Table #3 8 Feet Long

______Haw River Trail Conceptual Greenway Master Plan Page 32