CURRICULUM VITAE WERNER PETRICK ENVIRONMENTAL ASSESSMENT PRACTITIONER Environmental Management Planning & Approvals, Africa

QUALIFICATIONS B.Eng 1995 Civil Engineering Masters 2004 Environmental Management

z EXPERTISE Werner has over 24 years of work experience. He started out as a Civil Engineer (first 3 years) but soon became involved with environmental related projects. The following • Environmental 19 years (+) he has been working in the environmental field with experience in Management Environmental Impact Assessments (EIA’s), general environmental management and • Environmental (and implementation, Environmental Management Systems (EMS), waste management, Social) Impact environmental compliance, training, stakeholder engagement and capacity building, Assessments (EIA’s) mine closure and rehabilitation, environmental auditing and monitoring as well as due • Environmental Feasibility diligence. Studies Werner’s experience is based on work conducted as a consultant (current position) as • Stakeholder well as working for industry (i.e. implementing environmental requirements, etc.). Management • Environmental Sectors of his experience include: Exploration phase for onshore and offshore mining, Management Systems production phase of large mining projects, power generation including renewable (EMS) power initiatives and hybrid power plants, transmission lines, water supply & • Environmental Auditing sanitation, petrochemical industry, linear infrastructure including roads and rail, port related projects, chemical handling and storage, large irrigation projects and other. • Environmental Training and capacity building • Mine Closure

PROJECTS (EXCERPT)

Windhoek PEL23 B.V. & Parallel EIA processes for offshore exploration wells in PEL 82 (Walvis Basin) and PEL PEL28 B.V. 83 (Orange Basin). PEL 82 is located between 80 km and 300 km from the coastline in (Galp) - EIA for proposed water depths ranging from approximately 200 m to 1 800 m. PEL 83 is located between offshore exploration well 130 km and 250 km from the coastline in water depths ranging from approximately drilling in PEL82 and PEL 83 500 m to 2 500 m. (2019 – 2020) Werner was the Environmental Assessment Practitioner and in-country manager for the EIA process (including stakeholder engagement, PPP and report review).

Swakop Uranium Swakop Uranium proposed to develop an on-site PV power plant at their Husab Mine. Amendment – EIA for new Werner was the Lead Environmental Assessment Practitioner managing the EIA PV Power Plant (2019) process (including stakeholder engagement, PPP and report review).

. 1

CURRICULUM VITAE WERNER PETRICK

Shell Upstream BV Shell Namibia Upstream BV holds PEL 39, which is located adjacent to the – EIA for proposed offshore southernmost Namibian offshore border with South Africa. Shell is proposing to drill well drilling one or possibly two exploration wells in the northern portion of the licence area. (2017 -2018) Werner was the Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, PPP and report review).

NamParks Bridges - EIA EIA Scoping process for the the proposed construction of channel crossings. The Scoping proposed construction of 22 channel crossings in the Nkasa Rupara National Park (2018-2019) (NRNP) forms part of the Namparks IV park infrastructure developments. Werner was the Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, PPP and report review).

Gecko Cobalt Mining - Gecko Cobalt Mining (Pty) Ltd conducted reconnaissance drilling over a stretch of 24 Environmental and Social km length over the cobalt and copper mineralisation in EPL 4346, located Screening process approximately 25 km northwest of Opuwo. Depending on the outcome of further (2018) exploration activities and the feasibility study, GCM and CR are proposing to apply for a ML to ultimately mine the ore and process it on site. Gecko appointed SLR (Namibia) to conduct an Internal Environmental (and Social) Screening exercise. Lead Environmental Assessment Practitioner managing an internal Environmental and Social Screening process.

Manila Investments – Manila Investments (Pty) Ltd holds Mining Licences 73B, 16, 9 (collectively the old Kombat Copper Mine EIA Kombat Copper mine, which is currently under care and maintenance). The mine is a (2017 - 2018) past-producing copper, lead and silver mine. Manila is considering implementing the following activities upon completion of the Environmental Impact Assessment process and acquiring the relevant permits and approvals for: Open pit (surface) mining in ML 73B (also referred to as “Asis’’) and associated activities; Processing of the ore at the existing process plant, currently being refurbished, and associated activities; and Dewatering the “Asis Far West” (AFW) Shaft and conducting further underground exploration activities in ML 16. Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, PPP and report review).

Swakop Uranium Waste Swakop Uranium owns and operates the Husab Mine in the Erongo Region of Namibia; Rock Dump Amendment they propose amendment to their Waste Rock dump and also to implement a new on- and Incinerator - EIA site waste incinerator – for improved waste management on site. amendment (2017 - Lead Environmental Assessment Practitioner managing the EIA process (including 2018) stakeholder engagement, PPP and report review).

EIB and NamPower European Investment Bank and NamPower: Environmental Impact Assessment (EIA) Encroacher Bush Biomass for the proposed Encroacher Bush Biomass Power Project in Namibia. Power Project – EIA Lea d Environmental Assessment Practitioner managing the EIA process (including (2017 – 2020) stakeholder engagement, managing specialists, etc.) and compiling reports.

. . 2

CURRICULUM VITAE WERNER PETRICK

Igneous Mining (Pty) Ltd – Igneous Mining (PTY) LTD Environmental is seeking a Clearance Certificate (ECC) Application for Renewal for small scale mining activities on ML 135 in Sarusus Area, Skeleton Coast Environmental Clearance Park. (2016) Lead Environmental Assessment Practitioner managing the ECC Renewal Process.

City of Windhoek The Gammams Waste Water Treatment Plant (GWWTP) located in the Wanaheda suburb of Windhoek, is the City of Windhoek’s (CoW) largest wastewater treatment Gammams Waste Water plant. The CoW appointed SLR to develop an environmental Scoping Report (including Treatment Works Upgrade Impact Assessment) for the planned GWWTP upgrade. EIA Lead Environmental Assessment Practitioner managing the completion of the EIA (2017) process, report compilation / review.

NAMPARKS Environmental Scoping Report for Infrastructure Development: NAMPARKS Facility Amendment for the proposed addition of an Entrance Gate, Tourist Reception and Amendments at Mudumu Staff Housing at Mudumu National Park. NP – EIA amendment (2016 - 2018) Lead Environmental Assessment Practitioner for the EIA amendment process required for infrastructure development. Report review.

NamParks IV - Environmental Evaluation Memorandum and Management Plan for the proposed Environmental Evaluation development of Park Management Infrastructure (Park Signage Walls, Memorandum and Concessionaire’s Gates and Park Entrance Gates) in the Tsau //Khaeb National Park in Management Plan for the the /Karas Region. proposed development of Lead Environmental Assessment Practitioner. Park Management Infrastructure (in the Tsau //Khaeb National Park in the /Karas Region (2017)

Swakop Uranium’s Husab Coordination of the Planning and Development Phase of the Husab Mine’s waste Mine Waste Management management strategy Develop the Swakop Uranium Husab Mine. Strategy Environmental Assessment Practitioner, SLR Project Manager. (2016)

Gecko Salt (Pty) Ltd Environmental Impact Assessment for the proposed Cape Cross Gecko Salt (Pty) Ltd Cape Salt Project. Cross Salt Project - EIA (2016 - 2018) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and review reports.

Namibia Rare Earths – NRE holds the EPL at Lofdal located west of Khorixas, exploring for rare earth. They Proposed Lofdal Mine and wish to apply for a mining license in 2016, for which an EIA would is required. linear infrastructure – EIA Lead Environmental Assessment Practitioner managing the EIA process (including (2015 - 2016) stakeholder engagement, managing specialists, etc.) and compiling reports.

Rössing Uranium – Impacts Impacts of the TSF at Rössing Uranium and related dust dispersion on biota and desert of the TSF on biota and ecology. desert ecology – Managing the process and coordinating various specialists for input into the study (i.e. Management of study vegetation, air quality, biological soil crust, invertebrates and hyperspectral work). (2015 - 2016) Compiling consolidated report summarising all the findings.

. . 3

CURRICULUM VITAE WERNER PETRICK

Feasibility studies for a railway line between Windhoek and Katutura, as well as a study High Speed Railway Lines – for a railway line between Windhoek and . Environmental Screening Process Lead Environmental Assessment Practitioner managing the environmental Screening (2015 - 2016) process (including limited stakeholder engagement, managing specialists, etc.) and compiling reports.

Swakop Uranium is developing the Husab Mine in the Erongo Region of Namibia (70 km north-east of the Walvis Bay port). The reagents and chemicals that will be used in Swakop Uranium Reagents the processing plant will be imported through the port of Walvis Bay. It will be sourced – EIA for storage at the in advance and stored in Manica warehouse facility (on a temporary basis – “phase 1 Manica facilities project”) and container yard in the industrial area of Walvis Bay. (2015) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports

The members of the Sand Miners Association have been mining sand from the , within the Municipal boundaries, for many years. The sand they Sand Miners Association of mine supplies Swakopmund, Long Beach and Walvis Bay with sand for construction Swakopmund – EIA for purposes. The Sand Miners Association has had to look for an alternate source of sand sandmining in the Swakop for construction activities in their area and EIA had to be done. River (2015) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

Swakop Uranium is developing the Husab Mine in the Erongo Region of Namibia (70 km north-east of the Walvis Bay port). The reagents and chemicals that will be used in Swakop Uranium Reagents the processing plant will be imported through the port of Walvis Bay. It will be sourced storage at a new facility in in advance and stored in a warehouse facility within the boundaries of NamPort’s the Port of Walvis Bay – harbour area (long term – “phase 2” project). EIA (2015) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

Namibia Rare Earths – NRE holds the EPL at Lofdal located west of Khorixas, exploring for rare earth. They Lofdal mine – wish to apply for a mining license in 2016, for which an EIA would be required. The Environmental baseline baseline environment needs to be described in detail to feed into such an EIA process. development Compile the environmental baseline project plan. Manage specialists and develop (2015) Baseline data/report with input from various specialists.

Swakop Uranium is developing the Husab Mine in the Erongo Region of Namibia (70 km north-east of the Walvis Bay port). The EMP needs to be implemented during construction Swakop Uranium and their contractors. It further needs to be rolled out Swakop Uranium – Husab into a management system for operations. Mine amendments - EIA (2015) Lead Environmental Assessment Practitioner managing the various EIA processes and compiling reports. Provide guidance and support to Environmental Control Officer(s), training to ECOs and contractors. Develop EMS procedures and other relevant documentation.

. . 4

CURRICULUM VITAE WERNER PETRICK

B2Gold is developing the Otjikoto (gold mine) Project, located approximately 70 km north-east of Otjiwarongo in the Otjozondjupa Region of Namibia. B2 Gold proposed B2Gold – Otjikoto Gold to develop a landfill site (waste disposal facility) on site to cater for non-hazardous Mine landfill site - EIA waste. They also proposed to construct and operate an on-site (heavy fuel oil) Power (2013 – 2014) Plant. Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

B2Gold applied for Mining Licence (ML 169) to developed the Otjikoto (gold mine) Project, located approximately 70 km north-east of Otjiwarongo in the Otjozondjupa Region of Namibia. As part of the ML application process, a detail EIA process needs to B2Gold – Otjikoto Gold be conducted. Mine development - EIA Lead Environmental Assessment Practitioner managing the EIA process (including (2012 – 2013) stakeholder engagement, managing specialists, etc.) and compiling reports. The Scoping phase was already completed by another company. SLR (in corporation with the other company) completed the EIA process – i.e. assessment phase. Develop Mine Closure Framework.

Arandis Power proposed to construct and operate a ‘hybrid’ thermal/PV plant with the Arandis Power Plant - EIA maximum output capacity of 120 MW. amendment (2014) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

Various exploration companies planning to conduct exploration activities on the EPLs EPL’s for exploration they hold. Prior the activities commencing, and EIA process needs to be conducted. activities – various EIA’s Lead Environmental Assessment Practitioner managing the EIA process (including (2013 – 2015) stakeholder engagement, managing specialists, etc.) and compiling reports. Also review of reports.

Development of the proposed Commissiekraal Coal Mine including services and Commissiekraal Coal Mine associated infrastructure in South Africa. – EIA Scoping Report (2015) Compiled EIA Scoping Report.

Various Mining and exploration companies across Namibia sought assistance. Various Mining and Exploration companies - Provided various services and support to various mining and exploration companies, various services including amongst others external audits, training, rehabilitation planning, compiling (2012 – 2015) EMS procedures and other relevant documents, compile environmental performance reports, etc.

. . 5

CURRICULUM VITAE WERNER PETRICK

Various Mining and exploration projects as well as infrastructure projects across Namibia sought assistance with EIAs, EMPs and review processes. Various Mining, Exploration and Review process and reports for various projects managed by other SLR environmental Infrastructure Projects – practitioners, including amongst others rail sidings; Nanomill which will produce various services 150,000 tons rebar’s and billets per year from scrap steel; Okorusu Fluorspar Mine (2012 – 2015) expansion; Offshore exploration drilling (Murphy); water and waste water treatment facilities EIA and EMPs; Dundee Precious Metal Tsumeb Hazardous Waste Site expansion; Walvis Bay Salt Holdings Expansion; and others.

Mining Pietersite (gemstone) on Mining License (ML) 57 in the Kunene Region, north- Pietersite Mining License – central Namibia. EIA (2013) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

TransNamib plans to transport sulphuric acid by rail from Dundee Precious Metals TransNamib – sulphuric (Tsumeb) to Rössing Uranium Mine and to Walvis Bay. acid transport – EIA (2014) Lead Environmental Assessment Practitioner managing the EIA processes and compiling reports.

It is envisaged that the Z20 uranium deposit would be mined as a satellite open pit as Rössing Uranium Z20 it contains uranium bearing alaskite rocks, utilising conventional blast, load and haul deposit – EIA methodology. An infrastructure corridor would need to be established to link the Z20 (2012 – 2014) site to the existing Rössing Uranium Mine across the Khan River. Managing the EIA processes and compiling reports in a ‘joint venture’ with Aurecon.

A new Desalination Plant (located approximately 6 km north of Swakopmund, at the Desalination Plant – premises of the existing Swakopmund Salt Works.) to supply water to the for Rössing Managing SEIA processes Uranium Mine. The plant will have a design capacity of 8,800 m³/day. (2014) Managing the SEIA processes and compiling reports in a ‘joint venture’ with Aurecon.

Environmental Screening/ fatal flaw analysis for the proposed expansion of coal Coal Storage at Walvis Bay storage at the Walvis Bay Harbour. Harbour – EIA (2012) Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

Arandis Power proposes to develop an independent power generation plant east of the town of Arandis, located in the Erongo Region, Namibia. Arandis Power is Arandis Power HFO and proposing a power station with a nominal output capacity of approximately 120MW recycled oil power plant - which utilises reciprocating engines. Arandis Power will utilise a residual fuel known as EIA (2012) heavy fuel oil (HFO) and recycled oil from a waste oil recycling plant. Lead Environmental Assessment Practitioner managing the EIA process (including stakeholder engagement, managing specialists, etc.) and compiling reports.

. . 6

CURRICULUM VITAE WERNER PETRICK

Langer Heinrich is an operational Uranium Mine in Namibia Naukluft National Park. Langer Heinrich Uranium Specialist environmental support to ensure EIAs for expansion projects are correctly Mine – expansion projects managed and implemented. Also to provide support, guidance and management in – Specialist environmental terms of environmental management implementation at the mine i.e. EMS support (2009 – 2012) development and implementation; mine closure and restoration strategy; environmental training; etc.).

Port Expansion Projects in Port expansions and development (Port Elizabeth, Coega and Richards Bay). SA – Project environmental management Project Environmental Manager - managing the EIA process (including stakeholder (2008 - 2009) engagement, managing specialists, etc.) and compiling reports.

Development of the Gautrain Rapid Rail Link.

Gautrain Rapid Rail Link - Appointed (on contract basis) to provide specialist input into the very challenging EIA EIA (2006 - 2007) processes and EMP development for the project. Also appointed as the Environmental Manager for the Bombela Turnkey Contractor, the managing contractor, for the Gautrain Rapid Rail Link Project.

MEMBERSHIPS

EAPAN Certified as a Lead Environmental Practitioner and a Reviewer under the Environmental Professionals of Namibia (Membership No. 114) PUBLICATIONS Paper on the integration of the EIA process with the project execution model through the University of Pretoria.

. . 7

CURRICULUM VITAE MATTHEW HEMMING TECHNICAL DISCIPLINE MANAGER Environmental Management Planning & Approvals, South Africa

QUALIFICATIONS MSc 2001 MSc (Conservation Biology), with distinction, from University of Cape Town BSc (Agric) 1999 BSc (Agriculture) in Wildlife Science, with Zoology major, from University of Natal (PMB) f qualification here. Delete any unused rows

z EXPERTISE Matthew is a Senior Environmental Consultant with SLR and has over 14 years’ experience as an Environmental Assessment Practitioner within the environmental • Environmental legislation consulting field. Matthew is well versed in the authorisation and compliance • Environmental Impact requirements of all South African environmental legislation. He is currently the Assessment Technical Discipline Manager for SLR’s Environmental & Social Impact Assessment • Environmental planning team in Africa. Matthew is also SLR’s Lead for the Infrastructure Sector. & licensing He has managed a wide range of licensing projects including environmental • Waste management authorisations, water use license and waste management license applications, mainly • Stakeholder engagement in the waste management, gas exploration, mining, industrial and electricity • Environmental training generation sectors. His role included project management and co-ordination; specialist and engineering team management; environmental impact assessment; and co- ordination, facilitation and undertaking of stakeholder engagement processes, including for contentious projects. In recent years Matthew has focussed on assisting clients with waste management legislation and implementing projects up the waste management hierarchy. He has also managed a number of projects in the onshore oil and gas sector. Matthew also conducts or manages feasibility assessments, compliance audits, risk assessments, performance assessments, closure cost estimates and due diligence work.

PROJECTS A sample of Matthew’s project experience, summarised by sector, is provided below.

Infrastructure

EnviroServ intend to expand their Chloorkop Landfill Site to enable ongoing disposal of EnviroServ Waste general wastes. Management - Chloorkop Landfill Site, Midrand (2019 Matthew was the Environmental Assessment Practitioner responsible for the Basic - 2020) Assessment process required to inform the application for a waste manageemnt licence made in terms of NEM:WA, and an application in terms of the NWA.

The Namibia Water Corporation Limited is undertaking a Feasibility Study for the development of a Desalination Plant and Water Carriage System, to secure water NamWater - Desalination supply to the central coastal area of Namibia and Windhoek, as well as en-route users. Plant and Water Carriage System (2019 - ongoing) Matthew provided technical support to the Environmental Assessment Practitioner team responsible for undertaking the Scoping process required to inform the application for an Environmental Clearance Certificate in terms of Namibia’s EMA.

. 1

CURRICULUM VITAE MATTHEW HEMMING

Sun International Limited proposed the establishment and operation of a waste to energy Pyrolysis plant and Ash-to-Brick plant at its Sun City resort in the North West Province. Residual general waste and certain hazardous wastes will be recovered at Sun International – the Pyrolysis plant to generate approximately 100 kW of electricity for the resort. Pyrolysis and Ash to Brick Plant (2018 to 2019) Matthew was the Environmental Assessment Practitioner responsible for the Basic Assessment process required to inform the application for a waste management licence made in terms of NEM:WA, and an atmospheric emissions licence in terms of the NEM:AQA.

RHDHV for Quidenica Quidencia Investments has proposed the development of a waste park on a property Investments – Thornridge at Cato Ridge, KwaZulu-Natal. Waste Park Conservancy Matthew provided environmental inputs into an initial desktop environmental (2018) screening of the property and subsequent Master Plan development.

As part of plans to increase the capacity of the Tsumeb Smelter, Dundee Precious Metals appointed SLR to provide a high-level overview and opinion on current waste management strategies and operational procedures at the Tsumeb Smelter, including Dundee Precious Metals - for both general and hazardous waste. Tsumeb Smelter, Namibia (2017) Matthew managed the project which included the assessment of waste management strategies relative to national and international legislation and a review of current waste management practices and impacts of managed and unmanaged wastes at the site.

EnviroServ intended to expand the facilities at their Holfontein Hazardous Waste EnviroServ Waste Disposal Facility to include a range of additional disposal, recycling, recovery and Management - Holfontein treatment activities for both general and hazardous wastes. The project was Extension: Integrated withdrawn. Waste Management Matthew was the Environmental Assessment Practitioner responsible for the Facility, Gauteng (2014 to integrated Scoping and EIA process required to inform the applications for 2017) authorisation made in terms of NEMA, NEM:WA, NWA and NEM:AQA.

EnviroServ own and operate the Shongweni Landfill Site in terms of a waste EnviroServ Waste management licence. EnviroServ made application to the Department of Water and Management - Shongweni Sanitation for a water use licence in terms of the NWA. Landfill Site, Durban (2012 Matthew was the project manager responsible for the integrated water use licence to 2017) application made in terms of the NWA.

EnviroServ Waste EnviroServ own and operate the Holfontein Hazardous Waste Disposal Site in terms of Management – Holfontein a waste management licence. EnviroServ made application to the Department of Hazardous Waste Disposal Water and Sanitation for a water use licence in terms of the NWA. Site, Gauteng (2013 to Matthew was the project manager responsible for the integrated water use licence 2016) application made in terms of the NWA.

EnviroServ proposed to introduce a range of technologies for the recycling, recovery EnviroServ Waste and treatment of wastes at the Shongweni Landfill Site, KZN. Management – Treatment technologies at Shongweni, Matthew was the Environmental Assessment Practitioner responsible for the Scoping KZN (2011 to 2012) and EIA process required to inform the application for authorisation made in terms of the NEM:WA.

. . 2

CURRICULUM VITAE MATTHEW HEMMING

EnviroServ proposed to introduce a range of technologies for the recycling, recovery EnviroServ Waste and treatment of wastes at the Holfontein Hazardous Waste Disposal Site, Gauteng. Management – Treatment technologies at Holfontein, Matthew was the Environmental Assessment Practitioner responsible for the Scoping Gauteng (2011 to 2012) and EIA process required to inform the application for authorisation made in terms of the NEM:WA.

EnviroServ proposed to introduce a range of technologies for the recycling, recovery EnviroServ Waste and treatment of wastes at the Aloes Landfill Site, Port Elizabeth. Management – Treatment technologies at Aloes, Port Matthew was the Environmental Assessment Practitioner responsible for the Scoping Elizabeth (2011 to 2012) and EIA process required to inform the application for authorisation made in terms of the NEM:WA.

Industry

SAB proposed the development of a glass bottle manufacturing plant on the farm Leeuwkuil 596 IQ in Vereeniging, Gauteng. The proposed glass bottle manufacturing plant would produce approximately 290 000 tons of green and amber coloured glass The South African bottles using two gas fired furnaces. The facility would comprise a batch plant, main Breweries – Glass Bottle manufacturing building and warehouse. Manufacturing Plant, Gauteng (2018 - 2019) Matthew was the Environmental Assessment Practitioner responsible for the integrated Scoping and EIA process required to inform the applications for authorisation made in terms of NEMA, NEM:WA and NEM:AQA. An application for general authorisation under the NWA was also made.

Clay Industry cc operates a brick manufacturing plant in Fisantekraal, Durbanville. Clay Industry cc – Brick Manufacturing Plant (2018 Matthew was the project manager responsible for undertaking a general – 2019) environmental compliance audit of the operations and managing an application for the renewal of the facilities atmospheric emissions licence in terms of the NEM:AQA.

Smart Matta made application for a Recycling and Waste Management Facility in Anderbolt, Boksburg. SmartMatta (Pty) Ltd – Anderbolt (2016 -2017) Matthew was the Environmental Assessment Practitioner responsible for management of the Basic Assessment process to inform a Waste Management Licence in terms of the NEM:WA.

Rappa operates a facility that specialises in the recovery of gold from various materials Rappa Holdings - and wastes acquired from mining and mineral processing operations. Some of the Homestead Road facilities and activities may pose risk to the water resource and thus require a water operations, South Africa use licence in terms of the NWA. (2014 to 2017) Matthew was the project manager responsible for the integrated water use licence application made in terms of the NWA.

Scaw proposed to establish a 67 MW Electrical Cogeneration Power Plant and Ash Scaw South Africa - Disposal Facility at their Union Junction facility. The Ash Disposal Facility was designed Electrical Cogeneration to cater for power plant ash and other Scaw wastes. Power Plant and Ash Matthew was the Environmental Assessment Practitioner responsible for the Disposal Facility, Union integrated Scoping and EIA process required to inform the applications for Junction (2011 to 2015) authorisation made in terms of NEMA, NEM:WA and NEM:AQA. The development was authorised.

. . 3

CURRICULUM VITAE MATTHEW HEMMING

EnviroServ proposed to introduce a range of technologies for the recycling, recovery EnviroServ Waste and treatment of wastes at the Shongweni Landfill Site, Durban. Management – Treatment technologies at Shongweni, Matthew was the Environmental Assessment Practitioner responsible for the Scoping Durban (2011 to 2012) and EIA process required to inform the application for authorisation made in terms of the NEM:WA.

Oil and Gas

Rhino Oil and Gas Rhino Oil & Gas Exploration South Africa lodged two applications with the Petroleum Exploration South Africa Agency of South Africa for Exploration Rights to explore for petroleum products across (Pty) Ltd - Onshore onshore areas in the central-eastern regions of South Africa. exploration right Matthew was the Environmental Assessment Practitioner responsible for the Scoping applications, South Africa and EIA process required to inform the application for environmental authorisation in (2018 to 2020) terms of NEMA. Matthew managed the environmental impact assessment as well as an extensive public consultation process.

De Beers Marine (Pty) Ltd – De Beers Marine proposed to undertake a short, geophysical survey in offshore West Offshore Geophysical Greenland during July/August 2020. The geophysical survey would include seven Survey in West Greenland seismic lines, undertaken between 66° and 67°N, for the purpose of testing different (2019) types of seismic equipment and obtaining high-resolution geophysical data. Matthew managed the preparation of environmental inputs to the Pre-scope application document in accordance with the requirements of the Greenland Minerals Authority.

Afro Energy (Pty) Ltd – Afro Energy lodged made application with the Petroleum Agency of South Africa to Renewal of onshore renew two onshore Exploration Rights. exploration rights, South Matthew prepared reports reflecting the extent of compliance with the requirements Africa (2018) of the environmental authorisation for the exploration work programme.

Afro Energy (Pty) Ltd - Afro Energy lodged two applications with the Petroleum Agency of South Africa for Onshore exploration right Exploration Rights to explore for petroleum products across various onshore areas. applications, South Africa Matthew was the overall project manager, responsible for ensuring that the Scoping (2016 to 2017) and EIA process meet the legislative and client requirements.

Rhino Oil and Gas Rhino Oil & Gas Exploration South Africa lodged five applications with the Petroleum Exploration South Africa Agency of South Africa for Exploration Rights to explore for petroleum products across (Pty) Ltd - Onshore various onshore areas in the eastern regions of South Africa. exploration right Matthew was the Environmental Assessment Practitioner responsible for the Scoping applications, South Africa and EIA process required to inform the application for environmental authorisation in (2015 to 2017) terms of NEMA. Matthew managed the environmental impact assessment as well as an extensive public consultation process.

Centlube (Pty) Ltd - Centlube own an oil and lubricant blending and packaging facility in Wadeville that was Blending Plant at Wadeville operating without the required environmental authorisations. (2014 to 2016) Matthew was the Environmental Assessment Practitioner responsible for the Section 24G process required to inform the rectification application for environmental authorisation in terms of both the ECA and NEMA.

. . 4

CURRICULUM VITAE MATTHEW HEMMING

Energy Oil (Pty) Ltd - Waste Energy Oil own a waste oil recycling facility in Wadeville that was operating without oil recycling plant at the required waste management licence. Wadeville (2014 to 2016) Matthew was the Environmental Assessment Practitioner responsible for the Section 24G process required to inform the rectification application for environmental authorisation in terms of NEM:WA.

Kinetiko Energy lodged three applications with the Petroleum Agency of South Africa Afro Energy (Pty) Ltd - for Exploration Rights to explore for petroleum products across various onshore areas Onshore exploration right in the eastern regions of South Africa. applications, South Africa Matthew was the Environmental Assessment Practitioner responsible for the EIA (2013 to 2014) process required to inform the application for environmental authorisation in terms of the MPRDA.

Kinetiko Energy lodged 12 applications with the Petroleum Agency of South Africa for Badimo Gas (Pty) Ltd - Exploration Rights to explore for petroleum products across various onshore areas Onshore exploration right around Volksrust and Amersfoort, South Africa. applications, South Africa Matthew was the Environmental Assessment Practitioner responsible for the EIA (2010 to 2013) process required to inform the application for environmental authorisation in terms of the MPRDA.

Mining

Tshipi É Ntle operates a manganese mine near to Kathu in the Northern Cape. Tshipi É Ntle Manganese Matthew undertook a review of reported non-compliances and corrective actions Mining (Pty) Ltd (2017) taken by Tshipi in response to previous audit findings and associated authorisation conditions. Covering the Environmental Authorisation, EMPr and Water Use Licence held by Tshipi for the period 2014 to 2017.

Gecko Salt intends to develop a new solar salt production facility at the Cape Cross Salt Pan. The proposed project involves the mining of natural rock-salt and the Gecko Salt (Pty) Ltd - Cape establishment of salt crystallization pans for salt production by solar evaporation. Cross Salt Project (2016 – 2018) Matthew was the Environmental Assessment Practitioner responsible for the compilation of the EIA Report required to inform the application for an environmental clearance certificate in terms of the Environmental Management Act, 2007.

Tronox hold prospecting rights over an area at Port Durnford and required Tronox Limited - Port investigations into the environmental features of the area to inform decision-making Durnford Prospecting on future mining right applications. Rights, KwaZulu-Natal (2015) Matthew was the environmental scientist responsible for Environmental Sensitivity Study, Risk Review and Findings report.

Tronox hold prospecting rights over an area at Port Durnford and required Tronox Limited - Port investigations into the environmental features of the area to inform decision-making Durnford Prospecting on future mining right applications. Rights, KwaZulu-Natal (2015) Matthew undertook a gap analysis of Specialist Studies previously compiled for the Port Durnford area.

. . 5

CURRICULUM VITAE MATTHEW HEMMING

As part of the Sishen Western Expansion Project, Kumba Iron Ore proposed to demolish Dingleton Town to make way for mining operations. Waste arising from the Kumba Iron Ore - Sishen demolition requires to be managed. Mine, Dingleton (2014) Matthew compiled the draft waste management strategy for the Dingleton Resettlement Project.

Sishen Iron Ore Company - The activities, infrastructure and staff supporting the mining operations at Kolomela Kolomela Mine, Mine generate significant volumes of waste. All of the wastes produced at Kolomela Postmasburg (2014) Mine require to be managed. Matthew project managed the compilation of a waste management strategy for the Kolomela Mine and the development of awareness and training material on the implementation of the waste management strategy.

MEMBERSHIPS

EAPASA Application for Registration as Environmental Assessment Practitioner submitted in October 2019.

SACNASP Registered with South African Council for Natural Scientific Professions as a Professional Natural Scientist (Pr.Sci.Nat) in Environmental Science (400155/17)

IWMSA Member of the Institute of Waste Management South Africa (20112082) Committee member on the KZN branch of the IWMSA

IAIAsa Member of the International Association of Impact Assessors (1753)

DCCI Member of the Durban Chamber of Commerce and Industry and Vice-chair of the Environmental Forum

PUBLICATIONS The EAP, EIAs and our opportunity to effect change, not climate change, Synergistics Energy. IAIA Paper, 2008 The MV Treasure oil spill and its effect on the African Penguin, Spheniscus demersus, at Robben Island, South Africa. University of Cape Town. MSc Dissertation, 2001.

. . 6

CURRICULUM VITAE MARVIN NM SANZILA ENVIRONMENTAL CONSULTANT Environmental Management Systems, Impact Assessments, Permitting and Compliance.

Ph: +264 81 4788279 [email protected]

• Qualifications BSc 2007 Natural Resources Cert 2014 Understanding and Auditing ISO 14001 Cert 2015 New Managers Development Programme

z • EXPERTISE Marvin Sanzila joined SLR Environmental Consulting (Pty) Ltd in March 2016 as an • Environmental Environmental Assessments Practitioner and currently serves as a board member of Assessments and Project the Environmental Assessment Professionals of Namibia (EAPAN). Prior to this Management venture, Marvin successfully implemented the Langer Heinrich Uranium’s • ISO 14001: Environmental Environmental Management System (ISO 14001) for 5 years, ensuring compliance Management Systems; across the business sector and retention of the project’s license to operate. EMPs: Implementation and Marvin has assisted various consultants for 4 years in conducting Environmental Coordination Impact Assessments (EIAs) for project appraisals with the regulating authorities. All • Environmental Auditing projects experience related to EIAs have been successfully awarded Environmental • Stakeholder Management Clearance Certificates (ECCs) by the regulating authority and are operational, • Film presenter and enhancing both local and international business sector while implementing best narrator: practice environmental and social management tools. Apart from Project Management and Environmental Assessments, Marvin has presented and narrated two films, one that emphasizes the role of the environmental Management Act no.7 of 2007 in the modern day Namibian development context and the other that looks at Namibia’s Wetlands and its potential for ecotourism. His diverse capabilities, skills and knowledge and growing passion for environmental management allows an opportunity for a dynamic Environmental Team.

• PROJECTS

Swakop Uranium PTY (LTD) Role: Environmental Impact Assessment Practitioner and Project Manager (successfully completed the EIA process and have obtained the Environmental Environmental Impact Clearance Certificate (ECC) through the regulating authority for the project’s Assessment process for the development). proposed Husab mine on-site

12 MW (Phase 1) (2019). Swakop Uranium PTY (LTD) has partnered with CGN Energy International Holdings CO. Limited (CGNEI), a sister Company of Swakop Uranium, to construct and operate a Solar Photovoltaic (PV) Power Plant with a capacity of 12 megawatt (MW) at the Husab Mine to supply power to the processing plant and associated activities.

1

CURRICULUM VITAE MARVIN NM SANZILA

Alten Renewable Energy Environmental and Social Management Support Manager. Successfully completed Group (Alten) construction phase of the project. Environmental and Social Management Support for the Successfully overseen the implementation of the Environmental and Social proposed construction and Management System during the construction and operation of a 37 MW Solar operation of the 37 MW Solar Power plant in Mariental. During the construction phase of the project, the Power Plant in Mariental, Environmental and Social Management Plans (ESMPs) required their Namibia (2018) implementation in compliance to International Finance Corporation (IFC), Equator Principles (EPS) and the Namibian Regulations.

NAMWATER Role: Environmental Impact Assessment Practitioner (Project Management Assistant) (Project On-going) Environmental and social

screening: Feasibility study for a desalination plant and The Feasibility Study is financed through the Government of the Federal Republic of water carriage system to Germany, KfW Development Bank. secure water supply to Namibia Water Corporation Ltd. (NamWater) has been assigned by the Ministry of central coast, Windhoek and Agriculture Water and Forestry (MAWF), as the Project Executing Agency, to en-route users (2019) undertake a feasibility study for the development of a Desalination Plant and Water Carriage System, to secure water supply to the central coastal area of Namibia; Windhoek; as well as en-route users (i.e. towns). SLR and the Council for Scientific and Industrial Research (CSIR) (South Africa) were jointly appointed by the Project Management Team to undertake the Environmental Screening Study as input into to the overall Feasibility Study.

GALP Role: Project assistant Environmental Practitioner.

Proposed offshore Exploration Well drilling in EIA process for the proposed offshore Exploration Well drilling in PEL 82 & 83, Orange Basin, Namibia EIA Report and Environmental & Social Management PEL 82 & 83, Orange Basin, Namibia. EIA Report and Plan (ESMP). Environmental & Social Management Plan (ESMP), (2019)

Farm Skakel Role: Environmental Impact Assessment Practitioner (successfully completed the Environmental Performance EMP compilation and an ECC has been issued by the regulating Authority for the Report And Management project. Plan For Water Abstraction Boreholes (WW10801 & Environmental Performance Report And Management Plan For Water Abstraction WW10062) On Farm Skakel Boreholes (WW10801 & WW10062) On Farm Skakel.

Farm Burnel Role: Environmental Impact Assessment Practitioner (successfully completed the EMP compilation and an ECC has been issued by the regulating Authority for the Environmental Performance project. Report and Management Plan

for Water Abstraction Boreholes (WW 200285 & Environmental Performance Report and Management Plan for Water Abstraction WW 37681) on Farm Burnel Boreholes (WW 200285 & WW 37681) on Farm Burnel.

2

CURRICULUM VITAE MARVIN NM SANZILA

Farm Finsterbergen Role: Environmental Impact Assessment Practitioner (successfully completed the EMP compilation and an ECC has been issued by the regulating Authority for the Environmental Performance project. Report and Management Plan

for Water Abstraction Boreholes on Farm Environmental Performance Report and Management Plan for Water Abstraction Finsterbergen Boreholes on Farm Finsterbergen.

Swakop Uranium PTY (LTD) Role: Environmental Impact Assessment Practitioner (successfully completed the EIA process and has obtained the Environmental Clearance Certificate (ECC) Scoping report (including through the regulating authority for the project’s development). impact assessment) for the

proposed changes to the Swakop Uranium PTY (LTD) Husab mine and linear Swakop proposes further amendments to the infrastructure (2018-2019) approved Husab Mine plan and associated activities, as follows: • Further alterations of the WRD design; and • The Implementation and operation of an on-site incinerator for the purposes of improved waste management. • Six (6) new mobile communication antenna-poles for mobile communication road coverage along the access road to the mine from the B2 turn off.

Swakop Uranium PTY (LTD) Environmental Practitioner for the Scoping (including assessment) process. (Successfully completed the EIA process and has obtained the Environmental Swakop Uranium Internal Clearance Certificate (ECC) through the regulating authority for the project’s Scoping Report for the development). proposed New Raw Water

Pond (2017). Swakop Uranium Projects and Processing Departments proposed to construct an

additional raw water pond for the storage of Raw water supplied by NamWater. The additional pond is not only required to provide the plant with the required volumes of water, but also to ensure suitable volumes of water being stored during scheduled NamWater maintenance shutdown periods.

Shell Namibia Upstream B.V. Project Assistant (Environmental Practitioner) for the Public Participatory Process EIA for proposed Deep Water (including Focus Group Meetings) of the EIA. Correspondence with Client and Exploration Well Drilling in Project Management. (Successfully assisted the EIA process and has obtained the Petroleum Exploration Environmental Clearance Certificate (ECC) through the regulating authority for the Licence 39 (blocks 2913a and project’s development). 2914b) off the coast of Southern Namibia (2017) Shell Namibia Upstream BV holds PEL 39, which is located adjacent to the southernmost Namibian offshore border with South Africa. Shell is proposed to drill one or possibly two exploration wells in the northern portion of the licence area. European Investment Bank Project Assistant and NamPower: NamPower has partnered with the European Investment Bank (EIB) proposes to Environmental Impact construct and operate a biomass power plant that will generate electricity by the Assessment (EIA) for the combustion of wood from encroacher bush, growing in the surroundings of the proposed Encroacher Bush proposed power plant area. Biomass Power Project in Namibia (2017)

3

CURRICULUM VITAE MARVIN NM SANZILA

Tschudi Copper Mine: Environmental Auditor (Continues to support the Mine through compliance audit) Environmental Audit Report- November 2017 Environmental Audit for the EMP implementation of the Tschudi Mine in Tsumeb, Namibia.

Namibian National Parks Environmental Practitioner (Project Manager) (Successfully assisted the EIA Programme Phase process and has obtained the Environmental Clearance Certificate (ECC) through IV(NamParks IV) the regulating authority for the project’s development). Environmental considerations related to development of On the 20th of June 2017, Lund Consulting Engineers cc (Lund) requested SLR park management Environmental Consulting (Namibia) (PTY) Ltd (SLR), to interpret the extent of infrastructure in the Tsau environmental legal requirements for the proposed infrastructure development of //Khaeb national park in the NamParks Phase IV in the TKNP as detailed in the Concept Design Report. Design, /Karas Region (2017) site supervision and contract administration. NamParks is supported by the Federal Republic of Germany through the Kreditanstalt für Wiederaufbau (KfW) Development Bank. The programme (NamParks) has been implemented into development phases (1 to 4). NamParks Phase 4 (NamParks IV) is currently focused on Park Management infrastructure development in the Tsau //Khaeb (Sperrgebiet) National Park (TKNP).

Earthmaps CC Environmental Practitioner (Project Manager) for the EIA process of the proposed project activity. (Successfully assisted the EIA process and has obtained the Scoping Report and EMP for Environmental Clearance Certificate (ECC) through the regulating authority for the Earthmaps Consulting CC’s project’s development). Exploration Activities on EPLs

6339 and 6340, North-West of Tsumeb in the Oshikoto Earthmaps Consulting CC (Earthmaps) founded in 2004, is a local consulting service Region (2017) based in Swakopmund, Erongo Region with vast experience in minerals’ exploration and mining in Namibia and across Africa. Earthmaps holds the Exclusive Prospecting Licenses (EPLs) 6339 and 6340, located north-west (NW) of Tsumeb in the Oshikoto Region. Earthmaps required an environmental clearance certificate (ECC) from the Ministry of Environment and Tourism (MET): Department of Environmental Affairs (DEA) to conduct exploration activities in these EPLs.

Votorantim Metals Namibia Environmental Practitioner (Project Manager) for the EIA process of the proposed (PTY) LTD project activity. (Successfully assisted the EIA process and has obtained the Environmental Clearance Certificate (ECC) through the regulating authority for the Scoping Report (including project’s development). assessment) and EMP for Votorantim Metals Namibia (PTY) LTD’s Exploration Votorantim Metals Namibia (Pty) Ltd (Votorantim) is a wholly owned subsidiary of Activities on EPL 6521, North- Votorantim Metais Zinco, a Brazilian mining company, specialising in zinc, lead and West of Otavi in the copper. Votorantim has successfully obtained an Exclusive Prospecting Licence (EPL) Otjozondjupa Region (2017) 6521 in the North-western side of Otavi in the Otjozondjupa Region. Votorantim require an environmental clearance certificate (ECC) from the Ministry of Environment and Tourism (MET): Department of Environmental Affairs (DEA) to conduct exploration activities on EPL 6521.

4

CURRICULUM VITAE MARVIN NM SANZILA

Namibian National Parks Environmental Practitioner for the EIA process of the proposed project activity. Programme Phase (Successfully assisted the EIA process and has obtained the Environmental NAMPARKS Phase II Clearance Certificate (ECC) through the regulating authority for the project’s Scoping Report for development). Infrastructure Development: An environmental Scoping Report and Environmental Management Plan (EMP) for Amendment for the proposed the infrastructure development in the North-Eastern Parks was completed in March Addition of Entrance Gate, 2008 and the Environmental Clearance Certificate (ECC) subsequently issued in Tourist Reception, Staff 2008, following the submission to the MET: Department of Environmental Affairs Housing at Mudumu. (2016) (DEA). Infrastructure provisions for the Mudumu South in the approved Scoping Report only included a Park Entrance gate. It has come to terms that additional infrastructure is required at the Mudumu South. SLR was consulted to undertake the EIA process for the proposed additional park infrastructure.

ErongoRed Environmental Practitioner (for the EIA process, including EIA write up, Public EIA for a new 44 kV Participatory process, review of specialist report and project management). powerline between EIA for the proposed upgrading of the 22 kV to 44 kV powerline. A new overhead Swakopmund reservoir and powerline to be constructed. the Swakop River Plots (2016). (Successfully assisted the EIA process and has obtained the Environmental Clearance Certificate (ECC) through the regulating authority for the project’s development).

Ministry of Agriculture, Environmental Practitioner (EIA write up, process, review of specialist report and Water & Forestry (MAWF) project management) EIA process for the Zone The Ministry of Agriculture, Water & Forestry (MAWF) through the Division of Irrigation Project , North west Agricultural Engineering (DAE) intends to develop an Irrigation Project as part of the of Nkurenkuru, Kavango Government’s Green Scheme in the Zone Area located about 30 km northwest of Region Nkurenkuru in the Western region of Kavango. An EIA process is required for the (2016, 2018) project to obtain an ECC.

Namibia Construction PTY Environmental Practitioner (Successfully assisted the EIA process and has obtained Ltd. the Environmental Clearance Certificate (ECC) through the regulating authority for the project’s development). Scoping (Including Assessment) Report and EMP for Sand Mining project- Namibia Construction (Pty) Ltd is mining sand in the upper reaches of the Swakop 20km South West of River on Farm Osona 65, 20 km south-west of Okahandja town and 6 km East of Okahandja (2016) Gross Barmen. Namibia Construction has been mining sand from this location in the Swakop River between 2011 to 2014 and resumed in 2015 after the river flow reinstated the river sand in the mined out areas. An EIA process was required as per EIA regulations and EMA

Tschudi Copper Mine Environmental Auditor Environmental Audit Report- Environmental Audit for the EMP implementation of the Tschudi Mine in Tsumeb, November 2016 Namibia

5

CURRICULUM VITAE MARVIN NM SANZILA

Swakop Uranium PTY LTD Environmental Practitioner (for the entire EIA process, including EIA write up, Public Scoping Report (including Participatory process, review of specialist report and project management. impact assessment) for the (Successfully assisted the EIA process and has obtained the Environmental proposed amendment to the Clearance Certificate (ECC) through the regulating authority for the project’s Husab Mine Linear development). Infrastructure - 33kV Swakop Uranium proposes to erect a 33 kV overhead power line (±1.25 km in Overhead Powerline at the length) from the existing Erongo RED 22kV powerline to their B2 Vehicle staging B2 Vehicle Staging Area area next to the B2 main road. And EIA process was required for the issue of the (2016) ECC.

Igneous Mining Environmental Practitioner for the ECC Renewal Process. (Successfully assisted the Environmental Certificate EIA process and has obtained the Environmental Clearance Certificate (ECC) Clearance (ECC) Renewal for through the regulating authority for the project’s development). small scale mining activities Igneous Mining’s environmental clearance certificate for ML 135 Small scale mining on ML 135 in Sarusus Area, activities at Sarusus Area in the Skelton Coast Park is due for renewal. It’s with this Skeleton Cost Park (2016) background that the project still intends to keep the Mining lease until such time that the lease lapses. It has come to terms that Igneous Mining needs to apply for a renewal of their ECC.

Swakop Uranium PTY LTD Environmental Practitioner (Successfully assisted the EIA process and has obtained Swakop Uranium Internal the Environmental Clearance Certificate (ECC) through the regulating authority for Environmental Scoping the project’s development). Report for the proposed Sub- Swakop Uranium proposes a minor change and/or addition to the approved Husab Economic Material Mine design plan and infrastructure specific to stockpiling of Sub Economic Material Stockpiling Area (2016) (SEM) with an average ore grade of 113 ppm. The SEM is proposed to be stockpiled on two dedicated “SEM stockpiles”, located next to the Waste Rock Dump (WRD) within the perimeters of Pit Zone 1 and Pit Zone 2. An internal screening process was required to assess the impacts associated with the project activity

Langer-Heinrich Uranium PTY Environmental Compliance Coordinator Ltd The primary purpose of this role is to coordinate the environmental compliance Environmental Compliance program at Langer Heinrich Uranium (LHU) in order to ensure LHU successfully Coordinator (2014-2016) integrate environmental compliance across the business and retains its licence to operate. • Coordinate and provide support to ensure impact /aspect and risk assessment registers are up to date • EMP implementation • Participate in environmental incident investigations • Training and awareness • Conduct assessment of company activities to ensure compliance with ISO /internal standards and facilitate or coordinate environmental audit programme • Document control • Environmental register • Co-ordination, communication & networking

6

CURRICULUM VITAE MARVIN NM SANZILA

Langer-Heinrich Uranium PTY Environmental Technician Ltd. Roles: Environmental Technician • Environmental Aspect and compliance monitoring (September 2011-2013) • Incident management and data entry • EMP Compliance • Site-Contractors compliance to Environmental procedures, Environmental Management Plan, • Compliance to EMS ISO 14001; Environmental Internal Audits and Reports • Contribution to Monthly and Bi-Annual Environmental Reports • Waste management overall mining operation • Environmental Monitoring • Maintenance and Utilization of environmental Monitoring equipment • Training; Environmental awareness, Policy, Spill and Waste management

MAMOKOBO Video& Presenter, Narrator. Filming Logistics and schedule planner Research, Ministry of Environment & Tourism. Documentary Film; Eco- tourism and Namibia’s Wetlands: supporting livelihoods. (2011)

Risk Based Solutions cc Environmental Junior consultant (Project assistant ) Scoping Report: InnoWind • Project development stages, Socio- economic (Regional and Local Positive Energy Namibia (PTY) LTD for and Negative social impacts, Assessment methodology and procedures. the proposed 10 MW Solar array Project, Walvis Bay, Erongo Region (March 2011)

Risk Based Solutions cc Environmental Junior consultant (Project assistant ) Scoping Report: On Road • Project development stages, Socio- economic (Regional and Local Positive Investment (PTY) LTD for and Negative social impacts, Assessment methodology and procedures, mining of copper, zinc and Health and Safety gold at farm Elbe 10, EPL 4232 Okahandja, Otjozondjupa Region (November 2010)

Risk Based Solutions cc Environmental Junior consultant (Project assistant ) Scoping Report: Zhonghe • Project development stages, Socio- economic (Regional and Local Positive Resources (Namibia) and Negative social impacts, Assessment methodology and procedures. Development (PTY) LTD for proposed new uranium mine, EPL3602. Arandis area, Erongo region. (October 2010)

7

CURRICULUM VITAE MARVIN NM SANZILA

Risk Based Solutions cc Environmental Junior consultant (Project assistant) Scoping Report: Logwood • Project development stages, Socio- economic (Regional and Local Positive Investment (PTY) LTD for and Negative social impacts), Assessment methodology and procedures, mining of Copper and Silver Health and Safety at Klein Aub, EPL 3663,

Rehoboth District, Hardap Region (May 2010)

Alex Speiser Environmental Environmental Junior consultant (Project assistant) Consultants CC (ASEC cc • Baseline Assessment Environmental Background • Identification of potential impacts and Environmental • Environmental Management Plan Management Plan for the development of Eros Load Centre 66/11KV Substation and upgrade of the Olympia Load Centre (March 2010)

UNDP-MET, Versacon cc Assistant Coordinator Namibia Landscape Development of Project Document for the “Namibia Landscape Conservation Area Conservation Area Initiative” Initiative” NAM-PLACE. NAM-PLACE Pre-Feasibility and Baseline Assessment of the project focal areas and verification of (Sept 2009) the proposed PLACA demonstration Sites • Project coordination and management

Versatile Environment Assistant Coordinator Consulting cc • Administrative support and coordination. Namibia National Climate Change Policy and accompanying Strategic Action Plan (Mar 2009)

Versatile Environmental Environmental Junior Consultant Consulting cc Technical environmental services to Versacon cc: • Project development, management and coordination (Feb 2009- Feb 2010) • Project and programme environmental assessment, EIA.

MAMOKOBO Video & Project Coordinator Assistant Research, Ministry of Marketing and Distribution of the Environmental Management Act no.7 of 2007 Environment &Tourism film “A Balancing Act”. (MET) – Deutsche

Gesellschaft für Technische Zusammenarbeit (GTZ) Environmental Management Act Film(Feb 2009)

8

CURRICULUM VITAE MARVIN NM SANZILA

MAMOKOBO Video & Film Presenter/ Narrator Research, Ministry of • Participate in public consultation meetings Environment &Tourism • Conduct live interviews with various stakeholders (MET) – Deutsche

Gesellschaft für Technische Zusammenarbeit (GTZ) Environmental Management Act no.7 0f 2007, supporting film ( A Balancing Act) Sept 2008- Dec 2008

Risk Based Solution cc Environmental Junior Consultant • Assessment of Environmental components (Fauna and flora Coastal EIA for Northern Namibia Settings and the Kunene River Mouth settings, likely impact and Development Company management) (NNDC) PTY LTD proposed • Review of the Legal Framework relevant to the project. mining and ongoing exploration – EPL No. 2633 May - June 2008

SAIEA- Millennium Challenge Consultant- Enumerator Account (MCA) • Baseline data collection and impact assessment of the proposed veterinary Strategic Environmental cordon fence Impact Assessment of the construction of a new veterinary cordon fence along Namibia-Angola border (April 2008)

SAIEA- Millennium Challenge Consultant- Enumerator Account (MCA) • Baseline data collection and impact assessment of the proposed veterinary Strategic Environmental cordon fence Impact Assessment of the construction of a new veterinary cordon fence along Namibia-Angola border (April 2008)

Versatile Environment Assistant Coordinator Consulting cc • Administrative support and coordination. Namibia National Climate Change Policy and accompanying Strategic Action Plan (Mar 2009)

9

CURRICULUM VITAE MARVIN NM SANZILA

Versatile Environmental Environmental Junior Consultant Consulting cc EIA for a Seismic Survey in • Review of international, regional and national agreements/ policies/ Block 1911, offshore Namibia legislation relevant to project (April 2007) • Provision of information and data about coastal and marine regarding sensitivity, ecological importance and other relevant attributes of block 1911 • Preparation and provision of information about the Kunene River mouth, key species, sensitivities and threats.

Versatile Environmental Environmental Junior Consultant Consulting cc • Review of policies, legislation and international conventions in the context EIA for proposed of the project and biodiversity conservation development of guano platforms near Sandwich Habour Walvis Bay (March 2007)

SAIEA Project Assistance Trans-boundary issues of the Orange-Senqu river basin waters May 2007

Versatile Environmental Environmental Junior Consultant Consulting cc • Compilation of quantitative data on past, present, future petroleum Data gathering and gap industry activities and techniques for drilling in a GIS compatible format. analysis for modeling of the • Identification and compilation of data on biological, physical and chemical cumulative effects of offshore elements most likely to be affected at sites of existing petroleum petroleum exploration and exploration and production activities. production activities on the • Analysis of common impacts and project specific impact from oil/gas marine environment in the exploration BCLME region. (February 2007)

National Botanical Institute Data Coordinator (NBRI), Namibia Biodiversity Database (NaBiD) Facilitation of baseline biodiversity data through the Brown Hyena Research Project for conservation planning of the Sperrgebiet National Park Facilitation of baseline biodiversity data through the Brown Hyena Research Project for conservation planning of the Sperrgebiet National Park (Feb 2006- Jan 2007)

10

CURRICULUM VITAE MARVIN NM SANZILA

Versatile Environmental Environmental Junior Consultant Consulting cc EIA for a Seismic Survey in • Review of international, regional and national agreements/ policies/ Block 1911, offshore Namibia legislation relevant to project (April 2007) • Provision of information and data about coastal and marine regarding sensitivity, ecological importance and other relevant attributes of block 1911 • Preparation and provision of information about the Kunene River mouth, key species, sensitivities and threats.

Versatile Environmental Environmental Junior Consultant Consulting cc EIA for proposed • Review of policies, legislation and international conventions in the context development of guano of the project and biodiversity conservation. platforms near Sandwich Habour Walvis Bay (March 2007)

SAIEA Trans-boundary issues Project Assistance of the Orange-Senqu river basin waters May 2007

Versatile Environmental Environmental Junior Consultant Consulting cc Data gathering and gap analysis for modeling • Compilation of quantitative data on past, present, future petroleum of the cumulative effects of industry activities and techniques for drilling in a GIS compatible format. offshore petroleum • Identification and compilation of data on biological, physical and chemical exploration and production elements most likely to be affected at sites of existing petroleum activities on the marine exploration and production activities. environment in the BCLME • Analysis of common impacts and project specific impact from oil/gas region. (February 2007) exploration

National Botanical Institute Data Coordinator (NBRI), Namibia Biodiversity Database (NaBiD)

Facilitation of baseline biodiversity data through the Brown Hyena Research Project for conservation planning of the Sperrgebiet National Park (Feb 2006- Jan 2007).

Ministry of Fisheries and Assistant Fisheries Technician Marine Resources (Marine Mammal Section) Cape fur seal Project Jan – Feb 2004

11

CURRICULUM VITAE MARVIN NM SANZILA

1999 The Deep, Hull (1999 - A large aquarium designed by Sir Terry Farrell & Partners. Located on the River 2004) Humber the site is split into two areas the main attraction being the aquarium and the other being the business centre. Design concept for a large entrance plaza, public spaces, car park and landscape to business centre. Responsible for the landscape design of the main external spaces around the visitor centre as well as the layout for the car parks. Liaison with Sir Terry Farrell & Partners and engineers to create a high quality design / interactive visitor experience. Subsequent implementation of site works.

• MEMBERSHIPS

ENVIRONMENTAL Professional Membership ASSESSMENT PROFESSIONALS OF NAMIBIA (EAPAN)

12 CURRICULUM VITAE MAVISHA NARIANSAMY SENIOR ENVIRONMENTAL CONSULTANT EMPA, South Africa

QUALIFICATIONS GDE 2015 Graduate Diploma in Engineering – Environmental Engineering BSc Hons 2011 Bachelor of Science (Hons) - Environmental Monitoring and Modelling BSc 2009 Bachelor of Science- Biological Science z EXPERTISE Mavisha Nariansamy is a Senior Environmental Consultant with the EMPA division at SLR. Mavisha began her environmental career working at the Department of  Environmental and Social Environmental Affairs in Chief Directorate: Protected Areas Systems Management. Impact Assessment There she gained experience drafting National Norms and Standard’s for mining in  Strategic Environmental protected areas, reviewing EIAs for proposed listed activities in protected areas and Assessments updating the NPAES database. She has more than 5 years of experience in the civil  Stakeholder Engagement engineering and environmental consulting field gaining experience in the mining,  Water quality power, linear infrastructure and water sectors.  Screening Studies She has worked on projects at varying capacities in Swaziland, Democratic Republic of  Integrated Waste and Congo, Guinea, Namibia and South Africa. Her experience includes the management Water Management Plan and execution of Environmental authorisations (EIA and scoping, EMPr Amendments,  Compliance Auditing Basic Assessment), compilation of management plans, risk assessments, compliance auditing, monitoring and permitting. In addition to being well versed with the South African legislative processes, she is also experienced in working on international ESIAs involving alignment with the Equator Principles and IFC Performance Standards. PROJECTS

Norplats Plant Substation Project Manager. Basic Assessment and Environmental Management Programme Expansion (Present) Report for the Upgrade of the Plant Substation at the Zondereinde Mine.

Tshipi Borwa Mine: Project Manager. Compilation of the Rehabilitation Strategy and Implementation Plan Compilation of RSIP for the Tshipi Borwa Mine. (Present)

Projects undertaken during the employ of Knight Piesold South Africa

EMPr Update for Bakubung Project Manager. The project was concerned with the amendment process for Platinum Mine Bakubung Platinum Mine for the establishment of a new Tailings Storage Facility. The (2016 – 2019) process included specialist studies as well as Integrated Water Use License amendments.

Water Quality Monitoring: Project Manager. Logistical co-ordination and management for water quality Transnet Freight Rail (TFR) monitoring for TFR across South Africa for an 18-month period. Analysis of chemical (2018 – 2019) results and compilation of monthly monitoring reports.

. 1 CURRICULUM VITAE NAME

External EIA Audits: Project Manager and auditor. Conducted an external audit in terms of Regulation 34 Middelburg Ferrochrome of the EIA Regulations. Assessed compliance and reporting of audit findings to relevant (2019) authority.

Legal compliance audits for Project Manager. Auditing of compliance to GN 704 regulations and ECA Section 20, Middelburg Ferrochrome stipulations of site Water Use License (WUL) and compliance to Kloof Dump closure (2018) Permit. Reporting of audit conditions.

Management Plans for Project Assistance. Compilation of a rehabilitation plan for watercourses around Redstone Water Use project area. Licence – Solar Reserve LLC (2018)

Project Manager. Update of the existing EMPr for the Wessels Mine, where activities EMPr Update: Wessel included liaison with client and government officials, co-ordination of specialist Hotazel Manganese Mines studies, assessment of impact; public participation process and compilation of (2016 - 2018) Environmental Impact Assessment Report.

Water Use License – External Auditor. Auditing of compliance to GN 704 regulations and stipulations of site Middelburg Ferrochrome Water Use License (WUL) and compilation of audit reports. (2017)

ECO monitoring for Ezulwini Project Manager and External ECO Auditor. Conducted monthly ECO monitoring and Water Supply Project - ensuring compliance to construction CMP. Compilation of monthly ECO reports. Swaziland Water Services Corporation (Swaziland) (2018)

Kinsevere Primary Copper Project Assistance. Co-ordination of specialist studies, compilation of impact ESIA – MMG Kinsevere assessment for ESIA report and review of specialist studies. Copper Mine (DRC) (2017)

Water Use License (WUL) External Auditor. Auditing of compliance to stipulations of Water Use License (WUL) audits - Samancor Chrome and compilation of audit report. Ferrometals (2016 – 2018)

Aquatic Biomonitoring at Project Assistance. Undertook quarterly water quality monitoring including all Wastewater Treatment administrative, logistical duties and compilation of reports Works – Johannesburg Water (2014 – 2018)

Water Quality Site Project Manager. Compilation of the mine’s water quality reports based on Support – MMG Kinsevere interpretation of laboratory results, providing water quality recommendations for the Copper Mine (DRC) mine based on findings and trends, logistical support and procedures for water (2014 – 2018) monitoring and sampling events.

. . 2 CURRICULUM VITAE NAME

Biodiversity Site Support – Project Manager. Project management and support for specialist studies undertaken MMG Kinsevere Copper at Kinsevere Copper Mine, to determine rehabilitation success of plant translocation Mine (DRC) programme (2014 – 2018)

EIA for Oxidation Ponds - Project Assistance. Compilation of scoping report and impact assessment and Ohangwena Regional preparation of BID documents and public participation material. Council (Namibia) (2016)

Initial Environmental Project Assistance. Compilation of baseline and project description, stakeholder Evaluation: Ezulwini Water consultation and review of draft IEE report. Supply – Swaziland Water Services Corporation (Swaziland) (2016)

The City Deep Kazerne ECO Auditor. Conduct monthly ECO monitoring and ensuring compliance to freight hub roads upgrade construction CMP and compilation of monthly ECO reports. programme: ECO audit – SANRAL (2016)

Ethemba Dam Project Assistance. Assistance with compilation some chapters for the ESIA Report. Environmental Social Impact Assessment - Ministry of Natural Resources and Energy (Swaziland) (2015 – 2016)

Air Quality Site Support – Project Manager. Compilation of monthly feedback air quality reports, interpretation MMG Kinsevere Copper of laboratory data and management recommendations, logistical and administrative Mine (DRC) duties and management of sub consultants. (2014 – 2016)

Environmental Impact Project Assistance. Updating EIN for Siguiri Gold Mine by compiling and reporting of Notice for plant baseline water quality data and other environmental baseline components for EIN modification and pit update for the Combination Plant Project. expansion for Siguiri Gold Mine – AngloGold Ashanti (Guinea) (2015)

State of the Rivers – City of Project Assistance. Conducted vegetation assessment (VEGRAI), including Johannesburg identification of riverine vegetation. (2015)

. . 3 CURRICULUM VITAE NAME

Lethabo Power Station: Project Manager. Waste classification of ash and sewage sludge. Project management Waste Classification and role and co-ordination/ liaison with specialists. Lining Type Assessment – ESKOM (2015)

Update of Environmental Project Assistance. Assisted with writing the baseline chapter for the update of the Impact Study – MMG Environmental Impact Study and stakeholder material such as BID documents and Kinsevere Copper Mine information brochures. (DRC) (2014)

Water Pollution Monitoring Project Assistance. Data analysis and report compilation, data capture, trend analysis for Van Eck Power Station, and provide water quality recommendations. Ruacana Power Station and Brakwater Depot – NamPower (2014 – 2015) MEMBERSHIPS

Pr. Sci. Nat. SACNASP Professional Natural Scientist (Environmental Science) of the South African Council for (Membership Number Natural Scientific Professions (SACNASP). 115550)

. . 4