FORM 1A Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, , , UP.

FORM-1 A

(Only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

Name of the Project/s: Expansion of Proposed Mix Use Complex “DLF My Pad” at Plot no.– TC/G/6 Vibhuti Khand, Gomti Nagar Lucknow, U.P.

LAND ENVIRONMENT

(Panoramic View of the Project site are attached)

1.1 Will the existing landuse get significantly altered from the project that is not consistent with the Surroundings? (Proposed landuse must conform to the approved Master Plan / Development Plan of the area. Change of landuse if any and the statutory approval from the competent authority is submitted). Attach Maps of (i) site location, (ii) Surrounding features of the proposed site (within 500 meters) and (iii) The site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

The proposed Mix use project is located at, Plot no.TC/G-6 Vibhuti Khand, Gomti Nagar, Lucknow, U.P.The construction has already started as per Environment Clearance granted by SEIAA vide letter no. 770/Parya/SEAC/278/2008/AD (H), Dated 09-June-2013. It is expansion of the project complex within same plot area (for which EC was granted in 2013) due to change in project layout and drawings. The existing land use will not get altered from the project as the current land use of the project area is Mix use as per the LDA Plan 2021 and the site has been approved by Lucknow Development Authority. The proposed development will be as per the approval of the local authority and building bye-laws. It is anticipated that the construction activities of the proposed project would not have any adverse effect on the land use. The development of the green belt and other landscape would enhance the visual aesthetics of the area.

 Location of the proposed project is shown in Figure 1and 2.  Master Plan of Lucknow Development Authority, 2021 is enclosed as Annexure-III a  For Surrounding features of the proposed site (within 30 m, 500 m& 10 km) is attached as Annexure-III b, Annexure III c, Annexure III d respectively.  Site layout plan is enclosed as Annexure-IV

www.dasindia.org

Page 1 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

N

FIGURE 1: LOCATION MAP Project Site

Figure 1: Google Image Showing Location of Proposed Mix use Project

www.dasindia.org

Page 2 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Figure 2: Google Image Showing Co-ordinates of Proposed Mix Use Project

www.dasindia.org

Page 3 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

1.2 List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.

Project specific details are provided in Table-1, Comparative Area statement of the proposed project is given in Table-2 and Salient Feature of the project (Comparative) is given in Table – 3 Table 1: Site Specific Details

Particulars Details Location Proposed Mixed use complex “DLF My Pad” at Vibhuti Khand,Gomti Nagar Lucknow, U.P. Type of Industry Building & Large Construction Project Category B, Type- 8(a) Latitude & Longitude Point 1: 26°51'56.04"N, 81° 0'28.43"E (Refer Fig 3) Point 2: 26°51'54.06"N, 81° 0'27.10"E Point 3: 26°51'53.46"N, 81° 0'26.07"E Point 4: 26°51'53.47"N, 81° 0'25.51"E Point 5: 26°51'53.39"N, 81° 0'24.91"E Point 6: 26°51'52.70"N, 81° 0'23.07"E Point 7: 26°51'54.31"N, 81° 0'21.02"E Point 8: 26°51'57.77"N, 81° 0'22.75"E Elevation (m) amsl 120 m Current status of land Mixed use as per Lucknow Master Plan, 2021 Type of facilities Group Housing &Shopping complex Nearest Highway Faizabad Road NH- 28: 840 m (N) : 650 m(E)

Nearest railway station Gomti Nagar Railway Station: 5 km (SW) Charbagh Railway Station: 9 km (SW) Nearest airport Amausi International Airport: 16 km (SW) Protected areas as per Wildlife None Protection Act, 1972 (Tiger reserve, Elephant reserve, Biospheres, National parks, Wildlife sanctuaries, community reserves and conservation reserves) Reserved/Protected Forests None Rivers/Lakes Gomti River: 4 km (SW) Katautha Lake: 2.6 km (E) Archaeological important places None Seismic zone Seismic Zone III Defense installations Lucknow Cantt. Area: 7 km (SW) Air Force Station Bakshi ka Talaab: 18 km (NW)

www.dasindia.org

Page 4 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Table - 2: Comparative Area Statement

Items Proposal as per EC New Proposal 770/Parya/SEAC/278/2008/AD (H), Dated 09-June-2013 Type of Building Residential and commercial Residential and commercial Total Plot Area 19950.99 m2 (4.92 Acres) 19950.99 m2 (4.92 Acres) Permissible ground coverage 5985.30 m2 (30%) 5985.30 m2 (30%) Proposed Ground coverage 5985.29 m2 5963.33 m2 (29.89%) Total open (Plot Area- Ground 13965.7 m² 13987.66 m² coverage) area Area for roads and internal 5396.85 m² 4177.88 m² ( 20.94 % of plot circulation area) Facilities 5407.34 7296.23 m² Landscape area (Soft Green) 3161.5(15.8%) 2513.55 m² (12.6% of plot area) Permissible FAR (2) 39901.98 m2 39901.98 m2 Proposed FAR 39757.02 m2 (1.992) 39876.77 m2 (1.998) Total Basement area 32638.4 m2 26359.75 m² (I Basement +II Basement) (12924.19 m² + 13435.56 m²) Total Non- FAR(Basement/ stilt/ 38045.74 m2 33365.98 m2 Podium/ services area) Built up Area (FAR+ Non FAR) 77802.76 m2 73242.75 m2

Table – 3: Salient Feature of the project (Comparative) Items Proposal as per EC New Proposal 770/Parya/SEAC/278/2008/AD (H), Dated 09-June-2013 Area Utilization Block -A ( G +6) Tower B1 (2B+G+13 Floors) Block-B1 (G+11) Tower B2 (2B+G+13 Floors) Block-B2 (G+13) Shops Shops Total Dwelling Units 745 Units 616 Units Shops 106 Shops Estimated Population Residential: 1491 Residential: 1232 (@ 2 person per Visitors: 2950 unit) Staff/ employees: 300 Visitors: 500 Staff/ employees: 250 Parking Required- 1196.28 ECS Provided- 1198.17 ECS Power requirement& 3537 KVA 3500 KVA source Source: U.P Power Corporation Ltd. Source: U.P Power Corporation

www.dasindia.org

Page 5 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Items Proposal as per EC New Proposal 770/Parya/SEAC/278/2008/AD (H), Dated 09-June-2013 (UPPCL) Ltd. (UPPCL) Power backup (DG Backup power supply is planned for Backup power supply is planned Sets) the project through DG Set. for the project through DG Set (to 2x 1500 KVA DG Sets be placed in acoustic chamber). 2x 1000 KVA DG Sets 2 x 1500 KVA + 2 x 1010 KVA Total = 5000KVA Total =5020 KVA Water requirement & Fresh water: 141 KLD Fresh water: 90 KLD source Source: Municipal supply Source: Municipal supply Recycled treated water: 165 KLD Recycled treated water: 60 KLD Total water: 306 KLD Total water: 150 KLD Sewage Generation Amount of waste water generated Amount of waste water generated : 185 KLD 113 KLD STP Capacity: 200 KLD (20%higher STP Capacity: 150 KLD (20% capacity) higher capacity) Technology: MBBR Solid waste Domestic waste : Approx. 1.3TPD Domestic waste : Approx. 754 Horticultural waste :16 kg/day kg/day E- waste : <1 kg/day Horticultural waste: 9.3 kg/day STP Sludge: 75 kg/day E- waste : <1 kg/day STP Sludge: 4.5 kg/day

Land Use Break up Land use Type Area (in m2) Ground Coverage 5963.33 m2 Green Area 2513.55 m² Road+ Internal circulation 4177.88 m² Facilities 7296.23 m² Total 19950.99 m²

www.dasindia.org

Page 6 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Land Use

Ground Facilities Coverage 36% 30%

Road+ Internal Green Area circulation 13% 21%

Development Mix

FLOORS Shops in Towers B1 B2 Ground Floor 32 18 First Floor 35 21 Total Shops 106 Shops

Apartments in Towers B1 B2 Second Floor 29 14 Third Floor 29 14 Fourth Floor 29 14 Fifth Floor 29 14 Sixth Floor 29 17 Seventh Floor 29 19 Eighth Floor 29 32 Ninth 29 32 Tenth 29 32 Eleventh 29 32 Twelfth 29 32 Thirteenth 13 32 Total Units 616 Units Total FAR 39876.77

www.dasindia.org

Page 7 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities details of the existing landuse disturbance to the local ecology).

Table 4: Infrastructure in different directions of the project Direction Facilities East Plot TC/G-7 North 30 m wide road West 30 m wide road South Village Ghulam Husain purwa

There will not be any significant impacts from the proposed activity on the existing facilities adjacent to the proposed site, as the Lucknow Development Authority is developing all the facilities such as connectivity, roads, open space, drainage, sewer and water supply etc. keeping in view the land use as per Master Plan. Anticipated Negative Impacts: All construction activities will be confined within the project area. There will be no physical changes outside the project boundary. Development and Construction of proposed project will be done as per applicable norms/byelaws. Hence, negative impacts on adjacent existing facilities would be minimal, if any. Anticipated Positive Impacts: There will be no disturbance to the local ecology as project has already been approved from MoEF (SEIAA) for Building and Construction of Mix use development with predefined land use as per Lucknow Master Plan 2021. Moreover, landscaping with local plant species in post construction phase will restore the existing ecological condition in near future. So there will be no permanent adverse impact on existing ecological conditions due to proposed project. About 2513.55 m2 area will be developed as green area and will have positive impact on the surrounding. Proposed project will require manpower during construction phase and operation phase thereby creating job opportunities and improving the socio-economic conditions of the area. No rare or endangered species of fauna are reported to exist in the area. Care will be taken to minimize the disturbance to the local ecology.

1.3 Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given). There will be some land disturbance due to the upcoming project as the project will involve grading and construction of impervious surfaces. Following mitigation measures will be used to mitigate the same: . Construction planning will be done to minimize exposed soil during times of the year when the potential for erosion is high, for example during rains. . Site will be stabilized and erosion control measures will be adopted during any pause in construction.

www.dasindia.org

Page 8 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

. Suppression measures, such as promptly watering exposed area will be taken in account when visible dust is observed. . Stockpiles will be located with the slope not greater than 2:1 (horizontal to vertical). . Size and number of stockpiles will be kept minimum and will be located away from drainage line. Soil Type:  Type of soil: Sandy Loam  There will be no land disturbance resulting in erosion, subsidence or instability. The area is fairly plain and subsoil strata are alluviums deposited by water courses, geologically the litho log sections show dominant of sand percentage.

Slope Analysis: . The topography of the site area is mostly flat with slope tending towards Gomti River which is 4 km south-west of the project site. The highest elevation at site is 120 above MSL and the lowest elevation is 116 above MSL. In post construction phase the direction of the natural drainage will be maintained. Erosion / Subsidence: . Project will provide ample green space. Therefore, it will not cause any soil erosion, subsidence or instability problems.

Seismicity: According to the Indian Standard Seismic Zoning Map, the area under study falls in Zone- III (refer Figure 3). Suitable seismic coefficients in horizontal and vertical directions will be adopted while designing the structures.

www.dasindia.org

Page 9 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

SITE

Fig.3: Map Showing Seismic Zones in , 2002

1.4 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site).

The area is fairly plain and LDA has already constructed system of drains. Contour map shows the Elevation levels of proposed site as 120 m and drainage flow is towards Gomti River, south of the project site. The project will not impact any drainage pattern in the vicinity. Therefore, there will be no alteration of natural Drainage System, except the runoff from the site will increase during rains due to increase in paved area, which will be diverted towards RHW Pits (runoff from roof top) or storm water drains (runoff from other areas).

1.5 What are the quantities of earthwork involved in the construction activity cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc).

It is estimated that approximately 80000 m3 of earth material will be excavated during initial construction phase for foundations & basement. The top soil excavated during construction will be first temporarily stored in earmarked area. Almost all the soil will be reutilized into backfilling, leveling and filling of low lying area for development of landscape.

www.dasindia.org

Page 10 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

1.6 Give details regarding water supply, waste handling etc. during the construction period.  Water Requirement (Construction Phase): ~50 KLD  Construction waste generated Table 5: Details of Construction Waste Material Generated Construction waste material Total construction waste 2930 (MT) generated @ 40 Kg/sq.m of builtup area soil, sand & Gravel 0.35 1026 bricks & Masonry 0.3 879 concrete 0.25 733 metal 0.05 147 bitumen 0.0204 60 wood 0.0204 60 other 0.01 29 Source: TIFAC  Source of water: Municipal water tankers will be the primary source of water requirement during construction phase.  Construction Debris (Bricks, Cement, Concrete and Mortar) generated will be reused in road construction, backfilling and leveling, spare debris (if any) will be disposed off as per the norms.  Ready mix concrete will be used.  The fertile top soil will be reused for horticultural purpose.  Spillage of oil from the machineries will be properly collected and disposed off.  Proper Sanitary facilities and wash area will be provided and good hygienic conditions will be maintained throughout the construction phase.  Septic tank with soak pit or mobile toilets with municipal sewer shall be provided to take care of waste water generated from site (labor camps and site office)  Domestic solid waste generated will be managed as per MSW (M & H) Rule, 2016.  Litter bins will be provided in the open area.

1.7 Will the low-lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity).

Site is fairly plain and already developed by LDA with an altitude 120 m above mean sea level. Drainage pattern and slope of proposed site is toward south of site and ultimately meets Gomti River. No wetland or low lying area within project site.

www.dasindia.org

Page 11 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

1.8 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

Wastes which will be generated during the construction phase include the following:  Excavated materials from earthworks (e.g. cuttings, basement excavation, foundation etc),  General construction waste (e.g. wood, packing material, scrap metal, concrete and empty cement bags);  Hazardous wastes generated by general site practices and paint and thinner residues, etc.  Municipal wastes generated by site workers. Most of the construction waste will be reused in road construction and surplus will be sold to recyclers.

Excavated Materials from Earthworks

It is estimated that approx. 80000 m3 of earth material will be excavated during initial construction for foundations & basement etc. Maximum percentage of excavated material will be re-used within premises for different purposes. The excess earth would only be the construction wastes and will not cause any health hazards.

Municipal Waste & Other waste Municipal wastes comprise kitchen wastes, packaging and waste paper. Generation of solid waste from labour colony will vary from place to place due to habits and living condition. Approximately 0.25Kg/capita/day of municipal waste may be expected during construction phase. The domestic waste water generated from construction camps shall be disposed off through septic tank / soak pit or mobile toilets with STP/ municipal sewer. Some amount of debris, cuttings and construction materials may be observed at construction site. Details of construction waste are discussed in Table 6. However the quantity of their waste materials would be very small and limited up to the construction site only. Contamination by these wastes would be negligible and would be collected time to time during construction phase and disposed off accordingly. The Impact on soil during construction phase will be marginal and reversible in nature.

2.0 WATER ENVIRONMENT

2.1 Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement.

Water Requirement, Source and Water Balance

A provision of 86 lpcd (liters per capita per day), 45 lpcd & 15 lpcd for water requirements shall be made for residents, staff & visitors respectively. This in accordance with the MoEF’s Construction

www.dasindia.org

Page 12 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Manual & Manual of Water Supply, Central Public Health and Environmental Engineering Organization (CPHEEO), Ministry of Housing, Government of India (GOI), hence the total water requirements shall be:

Table 6: Water Calculations for the proposed residential complex S. Description unit/Area Total Rate of Total Rate of Total Total Water No. (in m2) Occupancy Fresh Fresh Flushing Flushing/ Requirement water Water water Recycled (KLD) demand (KD) demand water (lpcd) (lpcd) (KLD) 1. Residential 616 units 1232 65 80 21 26 106 2. Visitors 500 5 2.5 10 5 7.5 3. Staff 250 30 7.5 15 4 11.5 Total Domestic water 90 35 125 4. Horticulture 2513.55m2 5l/ Sqm 13 13 5. HVAC* Capacity TRx9 l x 12 12 (400TR) 12 hrs Total Water requirement 90 60 150

*Note: Requirement of HVAC cooling water as per calculation is 43 KLD. However, this is one time requirement. Make up water required for HVAC Cooling is 12 KLD (considering 4 KLD evaporation losses & 7.5 KLD blow down considering cycle of concentration (COC) equal to 6)

www.dasindia.org

Page 13 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

FRESH WATER WASTEWATER 90 KLD GENERATED @90% = 113 KLD STP =150 KLD

Domestic Water 125 KLD Considering 10% Losses

102 KLD

Secondary Treated Tertiary Treated 42 KLD Domestic RECYCLED WATER Flushing 60 KLD 35 KLD

HORTICULTURE HVAC DISCHARGE INTO 13 KLD 12KLD Municipal Sewers

Figure 4 a: Water balance (During Non - Monsoon)

FRESH WATER 90 KLD WASTEWATER GENERATED @90% = 113 KLD STP =150 KLD

Considering 10% Losses 125 KLD 102 KLD

Secondary Treated Tertiary Treated Domestic 55 KLD RECYCLED Flushing WATER 35 KLD 47KLD

HVAC 12 KLD DISCHARGE INTO Municipal Sewers

Figure 4b: Water balance (During Monsoon)

www.dasindia.org

Page 14 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

2.2 What is the capacity (dependable flow or yield) of the proposed source of water?

The proposed sources of water for the proposed project are: 1. Municipal Supply 2. Recycling of treated effluent from STP of Capacity 150 KLD (20% extra).

Water Scenario of the Lucknow City

No. of groundwater structures (Lucknow city) Jal SansthanTubewells More than 350 Handpumps (Public) >6000 Mini tube wells/Borings 300-400 Tube wells : Government /Private establishments >150 Tube wells : Private colonies/multi story buildings >400 Private domestic borings Innumerable (no inventory) Tentative withdrawals 550 MLD or even more

Ground Water: Ground water is a natural occurrence. Ground water supply is met through deep, shallow tubewells, Indiamark II Handpumps& Indira wells through Jal Sansthan as follows:  Supply through more than 350 tubewells - 185 MLD  Supply through 5000 India Mark II Handpumps - 25 MLD  Supply through 55 Indira wells - 28 MLD. Total Ground water supply - 238 MLD. Thus the total supply for entire Lucknow city at present is 480 MLD out of which surface contributes 242 MLD and Ground water contributes 238 MLD. Aquifer Group Depth range (mbgl) First Aquifer Group 00.00-150.00 Second Aquifer Group 160.00-240.00 Third Aquifer Group 260.00-370.00 Fourth Aquifer Group 380.00-480.00 Fifth Aquifer Group 483.00-680.00

Hydrogeological details of tubewells of Lucknow Depth range of specific Aquifer Discharge Draw-down aquifer group in Water Level mbgl capacity group range (lpm) range (m) mbgl (lpm/m) 1 2 3 4 5 6 I 00.00 - 150.00 20-26 1100-1700 4-10 150-325 II 160.00 - 240.00 17-27 300-600 23-31 13-19 III 260.00 - 370.00 20-22 1000-1500 25-33 40-50

www.dasindia.org

Page 15 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

IV 380.00 - 480.00 10-13 1400-1600 18-33 40-100 V 483.00 - 680.00 11-12 - - - I+II 00.00 - 250.00 15-30 1100-1600 4-10 130-320 I+II+III 00.00 - 300.00 20-35 700-1600 7-33 50-250 III+IV 300.00 - 474.00 8.00 2300 24 96

2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality). The supply is through Municipal Water.

2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage). About 40% of total water demand i.e. 60 KLD will be met from recycling of treated wastewater for Flushing, Horticulture and HVAC etc. Details of water usages are as follows:

Table 7: Water/ Waste water Details Water/ Waste water Details Fresh water 90 KLD Flushing 35 KLD HVAC 12 KLD Horticulture / Landscape 13 KLD Total water requirement 150 KLD Waste water 113 KLD Source of water - Municipal supply & Tertiary treated water STP Capacity – 150 KLD (20 % extra)

2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption).

There is no diversion of water from other users, as the fresh water supplies are provided by the Municipal Authorities.

2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity).

113 KLD will be the total waste water generated, which will be treated in the STP of 150 KLD out of which, 60 KLD tertiary treated water will be recycled for various uses including Flushing, Horticulture, HVAC and the spare secondary treated water will be disposed off in Municipal Sewers. No increase in pollution load expected.

www.dasindia.org

Page 16 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Table 8: Characteristics of Raw Sewage& Treated Sewage Parameter Raw Sewage Treated Sewage Treated Sewage (Influent) (After Secondary (After Tertiary Treatment) Treatment) pH 7.5 – 8.5 6.5- 8.5 6- 8 0 BOD3 at 27 C (mg/l) 250 - 350 < 30 < 10 COD (mg/l) 400 - 500 < 100 < 10 Suspended solids (mg/l) 250 - 450 < 100 < 5 Oil and Grease (mg/l) 30 < 10 < 1

2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Rain water harvesting pits have been proposed for augmentation of ground water. The rainwater collected from the rooftop will be conveyed into the rainwater harvesting system consisting of Desilting-cum-filter chamber and borewells for recharge into the groundwater. The rain water collected from Paved and Green area will percolate naturally in to ground. No demand will be met from the process. Analysis of the observed data on intensity duration of rainfall of past records over a period of years in the area is necessary to arrive at a fair estimate of intensity-duration for given frequencies. The longer the record available, the more dependable is the forecast. In Indian conditions, intensity of rainfall adopted in design is usually in the range of 15 mm/hr to 40 mm/hr. The intensity of precipitation for design of drainage scheme has been taken 40 mm/hr for the project.

Table 9: Storm Water Calculation Peak Run off Max, Rainfall Intensity 40 mm/hr Location Runoff Area m2 Rainfall Peak Run Coefficient intensity off in m3/hr (in m) Roof Area 0.8 5963.33 0.04 191 Paved area 0.6 11474.11 0.04 275 Green Area 0.2 2513.55 0.04 20 Total Runoff m3/hr 486

Runoff Potential Total Runoff = 486 m3/hr Roof top runoff= 191 m3/hr Taking 15 minutes Retention Time, Total volume of storm water = 486/4= 121 m3

www.dasindia.org

Page 17 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Particular Size Volume Desilting Chamber 2.0 m x 2.0 m x 1.5 m 6 m3 Recharge Pit 2.5 m x 2.5m x 3 m 18.75 m3 Total Effective Volume 24.75 m3

Hence No. of pits required = 121 / 24.75 = 4.8 pits or 5 pits

No. of Pits Required for Roof top rainwater harvesting: Roof top Runoff = 191 m3/hr Taking 15 minutes Retention Time, Total volume of storm water = 191/4= 47.75 m3 Hence No. of pits required = 47.75 / 24.75 = 1.92 pits or 2 pits No. of pits Provided: 3 Note: RWH will be initially done only from the roof top. Runoff from green and other open areas will be done only after permission from CGWB.

2.8 What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long-term basis? Would it aggravate the problems of flooding or water logging in any way?

Since this is a mixed use project, the paved area will increase thus the land surface will change thereby increasing the run off during rains. Maximum storm rainfall of 40 mm has been assumed, based on the past experience. No adverse impacts are envisaged due to proposed project on the run off characteristics of the area as adequate arrangements have been made to trap the rainwater and suitable storm water drainage system has been provided.

There will be change in the surface run off coefficient in the pre construction phase and post construction phase. The surface run off will be captured and used for harvesting so that the ground water level is consistent. The storm water drains will be cleaned in the pre-monsoon phase so that the water logging will be avoided. During the post-construction phase, runoff from the project shall not be allowed to stand and create water logging or enter into the road side or nearby drain. Adequate measures shall be taken to collect such run off and either shall be reused or stored in recharging pits. Suitable garlanding drain as per the existing contours of the plot will be developed. There is no landscape change planned. The project will not aggravate the problems of flooding or water logging in any way, as the topography is plain.

www.dasindia.org

Page 18 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any).

Fresh water shall be supplied through Municipal water supply. The groundwater will be augmented through proposed rainwater harvesting. The rain water collected from Roof top will be sent for ground water recharging through 3 nos. of RWH pits. 191 m3/hr of water is available for ground water recharge which will be recharged through RWH pits. A major part of the area is under green or open land which will percolate naturally and augment the ground water. Therefore, most of the rain water will be directly infiltrated through these open/green areas. Hence no adverse impacts are envisaged due to the project on the ground water quality and the level. Maximum recharging of the underground aquifer will be done.

2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts).

Effective measures will be adapted to reduce the storm water run-off from the construction site-  Ensuring vehicles stick to the access track.  Cleaning all mud and dirt deposited on roads from construction-related activities.  Excavation work will not be carried out during monsoon season.  Constructing a fence around the site to trap sediment whilst allowing water to flow through.  Diverting up-slope water with turf and not mixing mortar in locations that will drain into storm water system.  Preventing wastewater from brick cutting activities and stockpiles entering the storm water system.  Construction material will be stored in temporary shed at the earmarked place and will be covered ensuring that no leachate or spoilage of land occurs.  Curing water will be sprayed and, after liberal curing, all concrete structures will be painted with curing compound & covered with gunny bags, then the water will be sprayed.  Plantation of trees will start from construction phase.  No runoff will be disposed outside the project boundary.

2.11 How is the storm water from within the site managed? (State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels).

Since the existing topography is congenial to surface disposal, a network of storm water pipe drains has been planned adjacent to roads. All building roof water will be brought down through drain water pipes. The drain sizes and sections will be designed in such a way that they can take the load of the

www.dasindia.org

Page 19 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

peak rainfall period. Proposed storm water system consists of pipe drains, catch basins and seepage pits at regular intervals for rain water harvestings and ground water recharging. All the surface drains will be covered by gratings and proper land gradient will be provided so that water logging inside the site does not occur. Collected rain water will be recharge into ground water. The storm rainfall of 40 mm/hr. has been considered for designing the storm water drainage system. A detailed storm water management plan will be developed which considers the source of storm water. The plan incorporates the best management practices which include the following:  Regular inspection and cleaning of storm water drains.  Cover waste storage area.  Avoid excavation during monsoon season.

2.12 Will the deployment of construction labourers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation).

The workers from nearby localities and villages will be employed during construction. There will be no stagnant water at site, as the run-off from the relevant areas will be systematically drained. The civil contractor will be made responsible for site sanitation and will be bound by the management to adhere to healthy level of sanitation. Temporary septic-tank followed by soak-pit will be constructed for effluent treatment. All sanitary and hygienic measures will be provided and maintained throughout the construction phase such as: • Provision of separate toilets for the construction workers. • Temporary septic-tank followed by soak-pit will be provided for effluent treatment.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal).

During the construction phase, on-site sanitation facilities will be provided (Septic tanks and soak pits). During the operational phase, the waste water generated (i.e. 113 KLD) will be treated in the STP of 150 KLD. Out of total amount waste water, 60 KLD shall be treated up-to tertiary level and recycled for various low end uses including toilet flushing, horticulture, HVAC. Spare secondary treated wastewater (42 KLD in non monsoon and 55 KLD during monsoons) shall be discharged into municipal sewer line.

2.14 Give details of dual plumbing system, if treated waste is used for flushing of toilets or any other use.

Dual Plumbing will be provided for utilization of recycled water for flushing of toilets. Different color pipes will be used for this purpose.

www.dasindia.org

Page 20 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

3.0 VEGETATION

3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with its unique features, if any).

No, the project will not pose any threat to the biodiversity of the locality. The project site was an open agricultural land. As the project site does not contain any water body, therefore, no scope of disturbance to the aquatic flora will be involved. Moreover, quite a number of trees will be planted. The species will be predominantly native in nature so that they merge with the local ecosystem. Flora and fauna of the study area is mentioned in section 3 (Table 3.16 and Table 3.17) of conceptual plan. All the waste (liquid/solid/gases) will be managed onsite as per Rules. The impact due to proposed project will be minimal.

3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project).

There are no significant vegetation, except some ground cover within the site thus no extensive clearance or modification of vegetation.

3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features? (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale).

Due care will be taken to protect the important site features:  Tree plantation will be done to protect the site features such as topsoil erosion, ground water attenuation and avoiding contamination by leachate.  The excavated soil will be stored at earmarked places protected from contamination and from polluting the existing features and will be used for surface leveling and for creation of landscaped areas.

Adequate measures will be taken to minimize the likely impacts of the proposed project on the surrounding as well as the project site itself and documented in the Environmental Management Plan. General principles in greenbelt design considered for this study area:  Type of pollution likely air, noise, and water and land pollution generated from the activities at the site.  Agro-climatic zone and sub-zone where the greenbelt is located  Water quantity and quality available in the area  Soil quality in the area.

www.dasindia.org

Page 21 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Total no. of trees required: 1 Tree/80sqm of open area =13987.66 /80 =174.84 Proposed: =175 Trees

Total soft green area proposed for project is 2513.55m2 (12.60% of plot area). A combination of evergreen and ornamental flowering trees, palms, shrubs and ground covers will be planted along the sides of the roads and in open spaces & setback area within the complex. Landscaping is an important element in altering the microclimate of a place. Proper landscaping reduces direct sun from striking the buildings and heating up building Surfaces, prevents reflected light carrying heat into a building from the ground or surfaces, creates different airflow patterns and can be used to direct or divert the wind advantageously by causing a pressure difference. Shade created by trees and the effects of grass and shrubs reduce air temperature adjoining the building and provide evaporative cooling. A study shows that the ambient air under a tree is 20C to 2.50C lower than that for adjacent un-shaded areas.

Parks & Avenue Plantation Ornamental trees with spreading branches, shade giving with colorful flowers for people to relax and suitable patches of lawns, rockery with cactus and other small flowering xerophytic plants shall be planted.

The plants should exhibit the following desirable characteristic in order to be selected for plantation. a. Trees with colonial canopy with attractive flowering. b. Trees with branching at 10 feet and above. c. Trees with medium spreading branches to avoid obstruction to the traffic, fruit trees to be avoided because children may obstruct traffic and general movement of public.

The selection of plant species for the development depends on various factors such as climate, elevation and soil. The criteria are based on pollution mitigation capacity (including Particulate matter), large leaf surface area, deep root system and less litter fall. Faster growing trees with lighter canopy will be planted alternatively with relatively slow growing trees with wider canopy. Trees of will be planted at 4.5 m intervals, 2.5 m away from the road curbing as per CPCB guidelines. Trees will be planted along the periphery and roadside of the project. The list of plant species, which can be suitably planted, and having significant importance are provided in Table-9.

Table-10: List of Plant Species to be planted in the Green Area S. No. Scientific Name Standard Time when Name flowering/Fruiting Occurs 1 Ailanthus excelsa Maharuk January- March 2 Albizia labbeck Sirish January- March

www.dasindia.org

Page 22 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

3 Alibizia procera SafedSirish January- March 4 Alstonia scholaris Chitwan January- April 5 Anthocephalus cadamba Kadamb August-October 6 Azadirachtaindica Neem June-July 7 Bauhinia variegata Kanchan May-June 8 Butea monosperma Palash February-April 9 Cassia fistula Amaltas March-June 10 Emblica officinalis Amla January 11 Erythurina indica Dadap July-August 12 Delonex Regia Gulmohar February-June 13 Mangifera indica Aam April-July 14 Nyctanthes arbortristis Harsingar Throughout the year

4.0 FAUNA

4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details.

There is no displacement of fauna or creation of barriers for their movement

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

There will be a positive impact on the avifauna of the area. Due to the provision of plantation on the project site it is expected that site will attract avian fauna, bees, butterflies etc.

4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna.

As there is no displacement of fauna, no mitigation measures are required and provided.

5. AIR ENVIRONMENT

5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions).

. Increased traffic generation due to project is not going to cause significant increase in atmospheric concentration of gases and will not result in heat island formation. The minor impacts of emissions from traffic will be neutralized by developing a thick green belt along the periphery and internal road side. . During construction phase, dust emissions will be the main pollutants associated within on- site roads, (paved and unpaved), stockpiles and material handling.

www.dasindia.org

Page 23 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

. Regular water sprinkling will be done and construction material will be transferred in trucks covered with tarpaulin. . The other major source of pollution during operational phase will be emissions from DG sets. . Adequate height of stacks will be provided to the DG sets as per guidelines of MoEF(as per the Gazette of India Part II, Section 3, Sub-section (I) No. 318, dated July 11, 2002, is given below, refer table no. 10) to facilitate the dispersion of flue gases into the atmosphere.

Table11: DG set Stack height Rule, as per MoEF

Table 12: DG set Stack height (Provided) Nos. Capacity of DG set (KVA) Stack Height Provided (m) 2 1500 KVA 6.0 m + Building Height 2 1010 KVA 6.0 m + Building Height . Low Sulphur diesel (LSD) will be used which will result in lower emissions and increased efficiency. . Detailed air quality monitoring will be discussed in conceptual plan.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

The impacts of dust and gaseous pollutants due to different construction activities will be localized. All necessary measures will be taken. I. Dust: Sources: Site preparation, excavation, construction, traffic. Type: Area Source, Line Source Extent: Localized • Water spraying at dust generation sources/area. • All transportation vehicles will be suitably covered to prevent dust from the trucks, overloading of the vehicles shall be avoided and all vehicles employed will be PUC certified.

www.dasindia.org

Page 24 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

II. Smoke: Sources: vehicular exhaust, DG Set Type: Line sources, Point Sources Extent: Localized Mitigation: • D.G. set will be provided with adequate safe stack-height above the terrace level of the building to regulate the emission within the permissible norms. • Low-sulphur-content fuel will be used which will help to contain the emissions within the permissible range.

III. Odorous fumes: Sources: Unsanitized conditions, indoor finishing Type: Gases, vapors, fumes, dusts, fibres, mists. Extent: localized Mitigation: • Avoid unsanitized conditions

• VOC free paints will be used

• Properly ventilated work space

No negative impact outside of site. Dust emissions from excavation, air emission from machinery and other construction activities. Dust reduction measures such as road watering and periodic maintenance of road, effective use of personal protective equipment. Most of the concrete to be used at site, will be ready mix concrete available from nearby factories.

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

The project complex will have a bell mouth traffic entry/exit through 30 m wide road on north and 30 m wide road on west. All internals roads are 6 m wide. The entry/exit points have been marked on the layout plan. Fire tender pathways shall be provided as per local bye laws. The project site is well connected to network of roads leading from various parts of the city. Site Plan is attached as Annexure-IV.

www.dasindia.org

Page 25 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Table 13: Parking Calculations Required Parking According to State norms: 3 ECS per 100 m2 of FAR area (39876.00 x 100) x3 1196.28 ECS Parking Provided 1st Basement Parking (11688.36/32) 365.26 ECS 2nd Basement Parking (11758.9/32) 367.46 ECS Open/ Surface parking 135 ECS Second Floor parking (Tower B2) 47 ECS Third Floor (Tower B2) 47 ECS Fourth Floor (Tower B2) 47 ECS Ground Floor Two Wheeler parking (2737.91/23) 119.04 ECS Second Floor Two Wheeler parking (181.26/28) 6.47 ECS Third Floor Two Wheeler parking(181.26/28) 6.47 ECS Fourth Floor Two Wheeler parking(181.26/28) 6.47 ECS Basement-1 Mechanized Parking 51 ECS Parking Provided 1196.28 ECS Total Required Parking 1198.17 ECS

5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

The site layout plan showing movement pattern is enclosed as Annexure IV.

5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above.

During the construction phase, some noise will be generated through the operation of construction machines, excavators, construction vehicles, DG set etc. Following measures should be taken into consideration to mitigate the noise at construction site:  Efforts shall be made to the extent feasible not to use such excavation/ construction machines, which generate noise levels much more than 85 dB (A),  Silencers shall be fitted on construction machines  Earmuff and other protecting, devices shall be provided to labour working in high noise generation machines.

During post construction phase, not much noise is anticipated, on account of project being a residential cum commercial complex. However, noise generated due to vehicular movement, operation and maintenance will be mitigated by adopting following measures.

www.dasindia.org

Page 26 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

 DG set will be silent type with anti vibration pads.  Administrative control by display of slogans and sinages  Green belt/plantation along the internal roads will also work as noise barriers.

5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

Impacts on Air Quality due to DG Sets and construction equipments:  Noise will be emitted during construction due to operation of construction machinery like batching plant, concrete pumps, tower cranes, DG set, Air compressors etc.  Impact on onsite workers are expected to be highest. One of the major sources of noise during operational phase will also be the diesel based generator.  Impacts on ambient air during operation phase would be due to emissions from the stacks attached to stand by DG sets.

Mitigation Measures  Workers shall be provided with PPE such as ear muffs, helmets, anti-vibration boots etc.  DG sets will comply with the applicable emission norm.  Adequate stack height for DG sets will be provided as per norms.  Acoustic enclosures DG set with anti-vibration pad shall be used  Back up DG sets will be used only during power failure.  Monitoring of emissions from DG sets and ambient air quality will be carried out as per norm.

6. AESTHETICS

6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

The proposed construction will not result in the obstruction of a view, scenic amenity or landscapes, which has already been considered during planning. The architecture of the proposed project will be of highest standards, keeping in view suitable designs and material, to ensure sustainable development. The project will have world-class ambience and state of art infrastructures. The planning has been done in a way to present the best aesthetic view of the area with due consideration that the project does not cause any obstruction of the natural beauty of the area.

www.dasindia.org

Page 27 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

There will be no impact on the existing structures in the vicinity. The development in the project- influenced area is as per the development plan. Hence, no adverse impacts are anticipated from new constructions on the existing structures in this area.

6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.

The architectural design of the project is in accordance with the guidelines of local development authority i.e. LDA and National Building Code of India.

6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

There is no anthropological or archaeological site within 5 km of the site. Few anthropological or archaeological sites or artifacts nearby. (as per ASI):

Dilkusha Garden: 6 km (SW) La Martiniere College: 5.5 km (SW) Residency: 8.5 km (W) Bada Imambara: 9.5 km (W) : 11 km (W)

7.0 SOCIO-ECONOMIC ASPECTS

7.1 Will the proposal result in any changes to the demographic structure of local population? Provide the details.

As most of the workers/staff in construction as well as operation stages will be from the nearby localities, villages and township, no significant change in the local demographic structure is envisaged from the project. The complex decongests the adjoining cities to some extent and redistributes the existing population of the city. Escalation in land price and increased job opportunities will result in socio economic development of the area.

7.2 Give details of the existing social infrastructure around the proposed project.

The area is earmarked for Mixed use Development. Infrastructure Services in the Region Educational Facilities: Approx. Distance & Direction SKD Academy 1.2 km (NE) IIM Lucknow 13.5 km (NW)

www.dasindia.org

Page 28 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Lucknow University 7 km (W) Integral University 10 km (N) Jaipuria Institute of Management 1.5 km (SE) 3.5 km (SW) Kendriya Vidyalaya, Gomti Nagar 2 km (SW) Medical Facilities: Approx. Distance & Direction Divine Hospital 1.8 km (SE) RML Hospital 800 m (W) Chandra Mother& Eye Care Pvt. Ltd 62m (NW) KGMU 9 km (W) Balrampur Hospital 8 km (W) Mayo Hospital 2 km (NE) Villages: Approx. Distance & Direction Gwari 2.5 km (SW) Shahpur: 4.4 km (NE) Khargapur 3 km (SE) NijampurMalhaur: 4.5 km (SE) Recreational Areas: Approx. Distance & Direction Dr. Ambedkar Park 4 km (SW) Lohiya Park 3 km (SW) 4 km (SW) Lucknow Zoo 6 km (SW) Waves Mall 1 km (NW) Patrakarpuram Market 1.5 km (SW)

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?

The project will provide employment to people from all walks of life: Construction, Construction related materials, Engineering, Medicine, Landscapists, Animal Husbandry, Facility Management, Education, Information Technology, Administration etc. Better job opportunity for men and women, better utilization of land, preservation of environment, and infrastructure development. All the sacred sites or cultural values will not be affected by any means during or after construction but it will enhance the values of sacred places. The project will not have any adverse effect on the local communities. Since the project related activities are confined within the premises no adverse impacts on the surrounding features are envisaged. Detailed project benefits are mentioned in Section 6 of conceptual plan. Safeguards The social management plan has been designed to take proactive steps and adopt best practices, which are sensitive to the socio-cultural setting of the region.

8. BUILDING MATERIALS

www.dasindia.org

Page 29 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

8.1 May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency). The major materials required for construction of the proposed project will be steel, cement, bricks, metal, flooring tiles/stones, sanitary and hardware items, electrical fittings, water, etc. . Conventional construction material will be used outsourced from authorized vendors/sellers. . All items to be used in the proposed project will be as per the National Building Code specification. If the building materials with high-embodied energy are locally available, it will be used in construction. . Low embodied energy material like ready mix concrete, fly ash bricks will be used in construction.

8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

Mitigation Measures for Air Pollution (Construction Stage) To minimize the adverse impact due to air pollution during construction following measures will be taken.  Transportation of construction material will be provided with suitable covering like tarpaulin cover.  Water sprinkling shall be done at the location where dust generation is anticipated.  Raw material handling yard will be enclosed from all sides.  To minimize the occupational health hazard, proper personal protective gears i.e. mask shall be provided to the workers who are engaged in dust generation activity.  The trucks used for transport will be thoroughly checked for emission parameters and properly maintained.  The raw materials transport will be avoided during the peak hours to reduce traffic load. Mitigation measures for Noise Pollution (Construction Stage)  Administrative as well as engineering control of noise will be implemented. To prevent occupational hazard earmuffs / earplugs shall be given to the workers working around the operating plant and machinery emitting high noise levels.  Use of such plant or machinery shall not be allowed during night hours.  Careful planning of machinery operations and scheduling of operations shall be done to minimize such impacts.

www.dasindia.org

Page 30 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?

Waste from construction like excavated earth, empty cement bags, paper, cartoon and iron rods etc will be reused/ recycled as far as possible. Empty plastic cement bags and other plastic waste will be used in road construction. The waste generated as brick bats, plaster cement, reinforcement steel, concrete falls, ceramic tiles, etc will be used as a construction material.

8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project.

The philosophy of solid waste management will be to encourage the four R’s of waste i.e. waste reduction, reuse, recycling, and recovery (materials & energy). Regular public awareness meetings will be conducted to involve the residents in the proper solid waste management plan, options and techniques.

Estimation of solid Waste On the basis of the solid waste being collected in different cities, the per capita rate of solid waste generation has been adopted as 0.5 kg per day per person for residents, 0.25 kg per day per person for staff and 0.15 kg per day per person for visitors, Horticulture waste @ 0.0037 kg/m2/day, and e-waste @ 0.15kg/capita/year. Thus the anticipated municipal solid waste worked out as below: Table 14: Solid waste generation S.No. Particulars Population Waste generated in kg/day 1. Residential (@0.5kg/day) 1232 616

2. staff (@0.25 kg/day) 250 62.5

3. Visitors (@0.15kg/day) 500 75 Total Solid waste generated Approx. 754 kg/day Horticulture Waste (@ .0037kg/m2/day) 9.3 Kg/Day E-Waste (0.15 kg/C/year) 0.6 Kg/Day STP sludge (dry weight) 4.5 kg/day

Segregation & Collection of waste  A door to door and floor to floor collection system through service lifts shall be provided for collection of solid waste generated.  Adequate number of colored bins (green and Blue - separate for Bio-degradable and Non Bio- degradable) are proposed to be provided  Recyclable waste will be sold to authorized agencies.  Hazardous waste (Spent Oil) & e-waste will be stored at separate place and handover to authorized dealers of CPCB.

www.dasindia.org

Page 31 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

 Litter bin will also be provided in open areas like parks & play grounds etc.

Transportation, Treatment & Disposal Generated Solid waste shall be segregated & collected on common solid waste collection center at site, and handed over to authorized recyclers for treatment and disposal. Following steps have been proposed for collection, treatment and disposal of MSW:  Step 1: Segregation of MSW at source and collection from the premises  Step 2: Transportation of MSW  Step 3: Segregation of MSW for processing  Step 4: Shredding of the compostable waste to desired particle size  Step 5: Treatment of biodegradable waste through composting.  Step 6: Disposal of non biodegradable waste through authorized dealers.

Fig 5: Waste Management Flow Diagram (Construction Phase)

www.dasindia.org

Page 32 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Hazardous waste

Fig 6: Waste Management Flow Diagram (Operational Phase)

Hazardous Waste The Project is a Building Construction Project in which no storage of hazardous chemicals (as per MSIHC rules) will be done, except HSD (low sulphur variety) required to run standby DG sets. Also, the quantity to be stored will be below the threshold limit specified in the MSIHC rules. During construction paints, solvents, thinner, oil and lubricants will be stored for use which is hazardous to health. E-Waste E-Waste (Management & Handling Rule, 2016) Electronic waste, popularly known as ‘e-waste’ can be defined as waste electrical and electronic equipments whole or in part or reject (such as CDs, floppies, keyboards, monitors, power plug, bulbs, batteries, etc.) which have become obsolete due to:  Advancement in technology  Changes in fashion, style and status  Nearing the end of their useful life. Responsibility of Consumer or Bulk Consumer According to E-Waste (Management & Handling Rule, 2016) responsibility of Consumer or Bulk Consumer is given below:

www.dasindia.org

Page 33 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

 Consumer or Bulk Consumer of electrical and electronic equipment shall ensure that e-waste generated by them is channelized to authorized collection centers or registered dismantlers or recyclers or is return back to the pick-up or take back services provided by the producers.  Bulk consumers shall maintain records of e-waste generated by them in Form-2 and make records available to UPPCB. The e-waste generated from the proposed project would be suitably managed through assistance from e-waste handling agency. The mantra of "Reduce, Reuse, and Recycle" applies here also.  Reduce generation of e-waste through smart procurement and good maintenance.  Reuse still functioning electronic equipment by donating or selling it to someone who can still use it. Recycle those components that cannot be repaired. To identify organizations who reuse or recycle electronics.

9. ENERGY CONSERVATION

9.1 Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption? The details of power requirement, source, and backup power arrangements are given below:

Table 15: Power Requirement, Source and Backup Arrangement Power Requirement 3500 KVA Source UPPCL Backup power supply arrangement DG Sets 2 x 1500 KVA =3000 KVA 2 x 1010 KVA =2020 KVA Total: 5020 KVA Power Source during construction DG Sets 320 KVA + 62 KVA Stack Height 6.0 m above highest building

Energy Conservation Measures & Management Plan: In the Operational Phase, appropriate energy conservation measures & management plan will be adopted in order to minimize the consumptions of non-renewable energy. The following practices will be adopted: Sl. Energy Efficient Features 1. Maximum utilization of natural light 2. CFL and LED in the common areas 3. Use of solar lights in open areas and landscaped area with 50% dual lighting system.

www.dasindia.org

Page 34 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

4. All openings are shaded to reduce heat loss 6. U-values of roof, external wall and fenestration will meet requirements as specified in the Energy Conservation Building Code (ECBC) 7. The water supply pumping system will be provided with variable speed drive to conserve energy at part load. 8. Compliance for Window glazing U-values if window to wall ratio is more than 30% 9. Application of Day light sensor, motion sensor and timers. 10. Use of BEE 4-star rated or equivalent appliances 11. Orientation of building towards north, appropriately designed windows, and double light roof so that maximum day lightening to all spaces is achieved 12. Minimum glazing factor in regularly occupied spaces Permissible U-values (W/m2°C) as per ECBC: Roof: 0.409, External wall: 0.44, Fenestration: 3.3

9.2 What type of and capacity of power back up to you plan to provide?

Backup power supply arrangement DG Sets 2 x 1500 KVA =3000 KVA 2 x 1010 KVA =2020 KVA Total: 5020 KVA

Backup power units will be provided for the following emergency power back-up requirement:  Staircase, common area lighting and elevators of individual building.  Receiving station and substation lighting.  Sewage treatment plant.  Firefighting equipment.  Telltale lights in common amenity building.

9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation?

This is a Mix use project where the use of glass would be very less, i.e. for windows etc. Plain glass will be used for fenestration purposes only. Characteristics are as under*: Parameters 5 mm clear 8 mm clear Light transmission 90% 88% Light reflectance 8% 8% Solar factor 85% 81% Shading coefficient 0.97 0.94 Solar energy:

www.dasindia.org

Page 35 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Transmission 82% 77% Reflectance 8% 7% Absorption 10% 16% U –value 5.8 W/m2K 5.7 W/m2K *Source: www.sunguardglass.com

9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project.

Building design and envelope may be optimized through selection of appropriate wall and roof construction and through adoption of solar passive measures after studying the sun path analysis to provide shading devices for windows and roof which would reduce energy demand. Components of the solar architectural features in the proposed building: • Adequate natural cross-ventilation. • Sufficient day-lighting with direct heat gains • Adequate shading devices • Natural cross ventilation: There will be adequate open able windows and doors in the living spaces, kitchens & bathrooms. • Window: The major expanse of windows in a passive solar energy structure will be south facing solar windows. Whole design planning includes following considerations: the impact of heat gain in the summer; views; natural lighting; and privacy requirements in determining the placement and size of windows in the structure. For the most part, window areas on East and West facing walls will be kept as small and as minimal as will be consistent with interior requirements.

 Shading: South facing glass can be a source of overheating during summer months. The potential for overheating will be controlled by roof over carefully designed to shade the glass during the summer (sun higher in the sky) but not block sunlight during the winter (lower in the sky). The duplexes are aligned in a way that acts as shading devices.

9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

Yes, the layout of streets & buildings has been designed to maximize the potential for solar energy. Solar energy will be used for street lighting. 50% of street lights will be powered by solar lighting. Also automatic light sensors will be installed to facilitate automatic off-on action resulting in significant amount of energy saving. Projections, shades, façade elements will reduce the summer heating of the building. Green areas and open spaces will achieve a reduction in heating in summer.

www.dasindia.org

Page 36 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

Shading options wherever feasible will be used for energy saving. Roofs will be painted with reflective paints or china mosaic tiles with solar reflectance ranging from 0.3-0.6. This will result in less absorption of sunlight causing 40% back reflection and less heating of building structures during summer season. This will effectively reduce the heat load of the building envelope. Projections, shades and façade elements will reduce the summer heating of the building. Green areas will provide cooling in summer.

9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

Suitable energy optimization will be adopted during the calculation of energy load of the proposed project. Compact fluorescent lamps (CFL) and LED lamps will be used in place of incandescent and halogen lamps in all common areas and basement parking.

Energy Efficient Features:  Maximum utilization of natural light.  T-5 lighting fixtures in the common areas and Truelite fluorescent lamps in basements.  Use of solar lights partly in open areas and landscaped area.  Appropriate thermal insulation in walls and roofs to reduce heat gain and loss.  Glazing glass: to keep the U value as per ECBC.  External glazing will be below 40% of the total vertical Surface as per ECBC.

9.8 What are the likely effects of the building activity in altering the microclimates? Provide a self- assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

Heat emission from the proposed project can be from the following sources: • Heat absorbed and radiated from the paved and concrete structures. • Increased population for a particular stretch of land. Any building activity would alter the microclimate of a site and it is inevitable that wind patterns and thermal gain patterns on a site would be changed. But the proposed building has been carefully designed to modify the microclimate so as to improve overall thermal comfort and reduce energy

www.dasindia.org

Page 37 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

consumption. Hard paving onsite has been reduced to the extent possible to reduce the heat island effects (surface). The project will have good tree plantation which will further help to reduce the heat island effect. To reduce the heat load reflective insulated glass shall be used in fenestrations to cut on heat loads and subsequently capital and operating cost of air conditioning. Shade giving trees will be planted near the east and west side windows which will affect the microclimate and will provide cooling effect in summers. The building will use energy efficient and environmental friendly designs that will control formulation of heat island effect. There will also be sufficient green cover at the site to reduce formation of heat island.

9.9 What are the thermal characteristics of the building envelope? (a) Roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R-values of the individual components.

The U-values of the roof, external wall and fenestration of the building will meet the requirements as specified in the Energy

Table 16: Conservation Building Code (ECBC) S.No. Component Material Used Permissible U-Value as per ECBC (W/m2-0C) 1 Roof Concrete 0.409 2 External wall Brick 0.44 3 Fenestration Glass Facade 3.3

Heat transfer co-efficient (in Btu/hr. sq.ft.Deg F) are as under:

• Exposed brick wall: 0.07 • Shaded slab (non insulated): 0.40 • Insulated shaded slab: 0.12 • Ceiling (non insulated): 0.48 • Ceiling (insulated): 0.12 • Floor (insulated): 0.12 • Floor (non insulated): 0.48

9.10What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans. Adequate fire protection facilities will be installed including fire detectors, fire alarm and fire fighting system to guard the building against fires. All fire protection facilities are designed as per the latest National Building Code. The approvals in this regard shall be obtained.

www.dasindia.org

Page 38 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

Fire Fighting System The basic system for Fire Fighting shall be designed as per the provisions of the National Building Code . Overhead water storage tank will be proposed to be made. Water from these reserve tanks will be drawn by electrically driven fire pump of capacity 900 LPM and supplied into hydrant ring main and wet riser system. The system will be kept pressurized at all times in order to ensure instant availability of water at all points.

Fire Safety The building materials shall be of appropriate fire resistance standard. Further, design of building will be as per NBC, 2005, which include following provisions: . The electrical systems shall be provided with automatic circuit breakers activated by the rise of current as well as activated by over current. . Fire detection systems . Manual operated Fire Alarm systems at appropriate places . Double door and Double stairs in building will be provided . Bell Mouth traffic entry/exit through service road . Access for fireman . Provision of Mechanical ventilation for air conditioned room will be made. . Adequate fire fighting requirement shall be taken into account while designing the electrical distribution system Sprinkler system . The Basements will be equipped with sprinkler system of fire fighting and the sprinkler heads shall be distributed as per the National Building Code. The sprinkler pump will be suitable for automatic operation when there is a drop of pressure in the system. Sprinklers shall be provided throughout the basement area with separate sprinkler risers as required. All the risers shall be provided with installation control valves and a hydraulic alarm. An electrical sensor flow switch will be provided on each floor and connected to the fire control panel in the security room, to identify the affected floor immediately. . The building will conform to the provisions of National Building Code as well as the provisions of State Fire Safety by Laws and will be provided with adequate arrangement to overcome fuel hazards to the satisfaction of authority.

9.11If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics.

Glass will not be used as wall material except in windows as it is a mixed use project.

www.dasindia.org

Page 39 Expansion of Proposed Mix Use Project “DLF My Pad” at plot no.TC/G-6 FORM-1 A Vibhuti Khand, Gomti Nagar, Lucknow, UP.

9.12What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.

The project will not be centrally air-conditioned, except for the commercial shops. Air infiltration will not cause any energy loss as adequate provisions will be made to mitigate the effects of air infiltration.

Infiltration will be minimized through the use of EPDM gaskets in structural glazing and weather seals in the case of windows.

9.13To what extent the non-conventional energy technologies are utilized in the overall energy consumption? Provide details of the renewable energy technologies used.

Solar Energy will be used for external lighting as far as possible and economical viable. No other technologies are viable in the case. Solar Water Heating Systems may be used, if possible. There is no wind energy available nearby. As regards to biogas, it is financial not viable for as the organic waste generated isn’t too high.

10. Environment Management Plan

The Environment Management Plan would consist of all mitigation measures for each item- wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire. Environment Management Plan is discussed in Conceptual Plan.

www.dasindia.org

Page 40