<<

Social Housing Construction Projects

Status Report Q1 2021

May 2021 Rebuilding - Action Plan for Housing and Homelessness Quarter 1 of 2021: Social Housing Construction Status Report

Rebuilding Ireland: Social Housing Targets Under Rebuilding Ireland, the Government has committed more than €6 billion to support the accelerated delivery of over 147,000 additional social housing homes to be delivered by end 2021. This will include 91,510 HAP homes, 4,600 RAS homes and over 51,000 new homes, broken down as follows: Build: 34,210; Acquisition: 6,830; Leasing: 10,036.

It should be noted that, in the context of refocussing the social housing delivery programme to direct build, the number of newly constructed and built homes to be delivered by 2021 has increased significantly with overall delivery increasing to over 51,000. This has also resulted in the rebalancing of delivery under the construction programme from 26,000 to 34,210 with acquisition targets moving from 11,000 to 6,830.

It is positive to see in the latest Construction Status Report that 9,028 social homes are currently onsite. The delivery of these homes along with the additional 8,729 homes in the pipeline will substantially aid the continued reduction in the number of households on social housing waiting lists. The latest available data published in November 2020, shows that 61,880 households were assessed as qualified for and being in need of social housing support. This represents a decrease of 6,813 households or 9.9% on the last assessment in June 2019. Since 2016, the numbers have decreased from 91,600 to 61,880, a reduction of 32.4%. This progress has been possible due to the strong delivery under Rebuilding Ireland with over 130,000 (130,079) households supported to the end of Q1 2021 since the beginning of 2016.

Social Housing Delivery- General

Rebuilding Ireland set an ambitious target to deliver 12,750 new social homes in 2021 through a combination of Build, Acquisition and Leasing. The Covid-19 pandemic has had a significant impact on the construction sector and delivery of social housing. The closure of the construction sites for a prolonged period in 2020 and again in 2021 has led to many projects being delayed. Despite this significant challenge, 569 additional homes have been delivered under New Build activity in Q1 2021, this does not include 218 vacant local authority dwellings in various states of significant disrepair were brought back to productive use through the Voids Programme in Q1 2021.

Also in Q1 2021, 152 homes have been provided by LAs and AHBs under the various acquisition programmes with a particular focus on areas of the country where acquisition of vacant properties represents the most expedient and cost efficient mechanism of delivering new homes for families. A further 461 homes were realised via the Leasing.

Families and individuals in the private rented sector were also supported through the Housing Assistance Payment and schemes such as RAS. In Q1 2021, 3,914 were supported by HAP and 234 under RAS.

Overall, 5,330 additional housing supports have been delivered in Q1 2021.

Note: Projects marked as complete in the Construction Status Report have been returned by local authorities as having reached substantial completion during the relevant time period. Grounds completions, landscaping and other ancillary in addition to the allocations process and subsequent tenanting are a matter for individual LAs.

Tracking Progress in advancing the Construction Agenda- The Q1 2021 Construction Status Report

The Quarter 1 – 2021 Social Housing Construction Projects Status Report has now been finalised and the attached Appendices set out progress made to date in advancing the construction pipeline. Appendix 1 sets out the current status of schemes, as of the end of Q1 2021.

Appendix 2 sets out the various funding programmes delivering the 34,511 homes now in the pipeline.

PPPs are also reflected in the Construction Status Report with the addition of Bundle 1 and 2 - 999 homes, across 16 schemes and 10 Local Authorities. A further PPP bundle will be added when it reaches the appropriate approval stage.

It should be noted that the Social Housing Construction Status Report does not reflect the totality of the overall Build Programme. In addition to the homes reflected in the Report, local authority Part Vs are being delivered and these are reflected in the overall statistics provided by the Department.

An explanation of the delivery categories and Stages is provided at Appendix 3.

Part V is a very important contributor to new build social housing delivery. This delivery stream is not generally reflected in the CSR; however, some AHB Part V being delivered as part of larger schemes may be included. To end Q1 2021, 59 Part V homes have been provided. A full breakdown by LA of Part V output is available on the statistics page of the Departments website. Appendix 1

Table 1 Q4 of 2016 Q4 of 2017 Q4 of 2018 Q4 of 2019 Q4 of 2020 Q1 of 2021 Approval Status Schemes* Homes Schemes* Homes Schemes* Homes Schemes* Homes Schemes* Homes Schemes* Homes Stage 1 - Capital Appraisal 165 2,687 156 2,946 71 1,545 112 2,129 121 2,688 104 2,458 Stage 2 - Pre-planning 93 1,279 124 1,715 127 2,000 130 2,195 126 2,363 124 2,410 Stage 3 - Pre-Tender design 32 490 60 613 83 1,694 55 886 53 987 58 1,127 Stage 4 - Tender Report or Final Turnkey/CALF approval 63 1,493 93 1,912 129 2,569 175 2,603 196 3,047 194 2,734 Site Start 90 1,829 190 3,646 291 4,992 374 6,704 439 8,555 455 9,028 Site Finish 61 652 223 2,592 598 6,334 1,070 11,498 1,448 16,175 1,499 16,754 Totals 504 8,430 846 13,424 1,299 19,134 1,916 26,015 2,383 33,815 2,434 34,511

* Some schemes are being delivered in phases and this is reflected in the number in the table, when we say 2,434 schemes this includes schemes being delivered in phases. Appendix 2

Table 2 Q4 of 2016 Q4 of 2017 Q4 of 2018 Q4 of 2019 Q4 of 2020 Q1 of 2021 Funding Programme Schemes* Homes Schemes* Homes Schemes* Homes Schemes* Homes Schemes* Homes Schemes* Homes CALF Construction 28 677 59 1,431 52 1,323 55 1,549 54 1,539 56 1,539 CALF Construction Turnkey 55 1,388 147 2,774 349 5,038 594 8,210 776 12,122 780 12,226 CAS Construction 108 1,048 129 1,218 144 1,405 157 1,504 188 1,858 194 1,886 Regeneration 36 782 47 1,060 54 1,104 52 985 53 1,292 53 1,201 SHIP Construction 240 3,571 365 5,124 465 6,057 583 7,438 709 9,466 685 8,914 SHIP Construction Rapid 14 467 26 716 40 1,141 50 1,470 57 1,699 64 1,927 SHIP Construction Turnkey 23 497 73 1,101 181 2,067 411 3,860 530 4,840 586 5,819 PPP 14 999 14 999 16 999 16 999 Totals 504 8,430 846 13,424 1,299 19,134 1,916 26,015 2,383 33,815 2,434 34,511

* Some schemes are being delivered in phases and this is reflected in the number in the table, when we say 2,434 schemes this includes schemes being delivered in phases. Appendix 3- Explanatory notes

The Construction Status report is a full compendium of live LA and AHB new-build activity across the period 2016-2021. The following schemes are represented in the Construction Status Report:

• Social housing Capital Investment Programme (SHCIP) • Capital Assistance Scheme (CAS) • Capital Advance Leasing Facility (CALF) • Public Private Partnership (PPP)

Schemes which have completed in prior reporting periods are retained on the Report, so as to preserve data and provide a full overview of activity.

The Report is published every quarter in open format on the data.gov.ie website, which allows the user to filter and analyse data.

The Social Housing Capital Investment Programme (SHCIP) provides funding to local authorities for the provision of social housing by means of construction and acquisition.

The Capital Assistance Scheme provides essential funding to AHBs for the provision of accommodation for persons with specific categories of housing need such as Homeless and Older Persons, People with Disabilities, Returning Emigrants and Victims of Domestic Violence.

4-Stage Approval Process

The funding approval process for social housing projects supported by the Department under the SHCIP and CAS schemes outlined above is in line with the Government’s Capital Works Management Framework (CWMF), the same approach used for other publicly-funded Capital construction projects. While there are nine points of review within the CWMF, the Department has combined these to just four for capital-funded social housing construction projects.

The Departmental approvals themselves represent a small minority only of the time taken in advancing a build project onto site. The approach we follow means that local authorities forward design proposals and costings to the Department sequentially, as the local authorities advance the projects through their own planning work. Check lists, guidance and templates have been issued to the Local Authorities to assist them in this process.

What are the 4 stages? The four stages are as follows: - Stage 1 – Capital Appraisal to verify the business case and basic project suitability – this is a light presentation of information; no design and only indicative costs are required at this initial stage.

Stage 2 –Pre-planning outline design and cost check –following site investigations, this involves the level of designs that are required for the Part 8 planning process and a completed QS cost plan; detailed tender drawings and resulting costs are not needed at this stage until planning permission is obtained.

Stage 3 – Pre-tender costs check – the more detailed designs and cost estimates have been prepared by the local authority design team at this stage and a cost check submitted before going to tender, but if costs are consistent with the earlier stages, then this review will be swift. Unless there have been changes to the design following Part 8/planning, or conditions to be met, the design is not reviewed.

Stage 4 – Tender approval from Department – the tenders have been received and assessed by the local authority and again, if costs are consistent with the earlier stages, this review will be swift.

There is now a Target Programme for advancing social housing capital-funded projects through design, planning and approval. This overall programme sets a target of 59 weeks from stage 1 submission by the local authority, to contract award for the construction. It establishes target turnaround times for the Department to carry out the review process and for the local authority to carry out the design of the scheme, the planning process and the procurement of a builder. While the aim of the programme is to create a realistic but ambitious target programme, it is acknowledged that external factors can affect construction projects; for example, delays can arise at planning, where the views of Councillors and communities are taken into account, but these can be minimised by early engagement. Site condition difficulties should not arise if appropriate site investigations are carried out at the beginning of the process.

The single-stage approval process A revised single-stage approval process for social housing projects less than €6m has been implemented. The main change from the previous single-stage approach is that in the event that the approved budget is not maintained, a second application for a budget revision will be facilitated on receipt of tenders. This will be facilitated where certain circumstances have caused the costs to rise – for example, tender inflation - and where such an adjustment will not increase the overall budget requirement beyond the €6m level. Capital Advance Leasing Facility (CALF):

The Department offers financial support to Approved Housing Bodies (AHBs) in the form of a long term loan under the Capital Advance Leasing Facility (CALF) to assist with the financing of the construction or acquisition of homes that will be provided for social housing use. This loan facility can support up to 30% of the eligible capital cost of the project, where the homes will be provided under long- term lease arrangements to local authorities for social housing use. Funding is provided to AHBs through Local Authorities.

CALF approvals do not follow the same approval process as the SHCIP 4-Stage process. The assessment process includes a full financial evaluation which is carried out in conjunction with the Housing Agency. The funding approval may be provided at various stages of project development, including pre-planning for example, in which case the funding approval will be subject to planning. Where a project changes post-approval, a revised application is submitted and a revised approval issues following normal assessment procedures.

Public Private Partnership (PPP): €300 million was committed in Budget 2015 to providing 1,500 new social housing homes via the Public Private Partnership model. The programme is being delivered in three bundles with a capital value of approximately €100 million each. Each bundle is being developed over a number of sites, spread across different local authorities. Each individual site is to provide between 50 and 100 social housing homes.

The homes are delivered using what is termed as an ‘availability-based PPP model’. A private sector company designs, builds, finances and maintains the social housing homes. In return, it receives payments which are spread over 25 years.

As the model is ‘availability-based’, the private sector partner is responsible for ensuring that homes are available for occupation. The local authority is responsible for allocating tenants. The private sector partner provides maintenance and upkeep services for 25 years. After this time, the homes are returned to the State in good condition, subject to reasonable wear and tear.

Bundles are added to the Construction Status Report at tender stage.

Part V data on the CSR: The Construction Status Report does not contain data on Part V schemes funded under the SHCIP scheme or delivered by LAs without DHPLG funding. It does contain a number of AHB Part Vs which are advancing as part of larger schemes approved under the Capital Advance Leasing Facility. The full Part V output is published as part of the overall Social Housing Delivery Report.

Disclaimer: While every effort is made to ensure that the data in the report is accurate at the time of publication, the report now covers 34,511 homes across over 2,434 schemes/phases of schemes and is reliant on the provision and processing of scheme updates and delivery data from 31 Local Authorities. Where errors arise, these will be corrected in the next version published. The most recent published version therefore should always be referred to.

Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1 Carrigbrook, Road, Carlow 6 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 2 Carlow Carrigbrook, Tullow Road, Carlow 6 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 3 Carlow Carrigbrook, Tullow Road, Carlow 12 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 4 Carlow Carrigbrook, Tullow Road, Carlow 10 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 5 Carlow Carrigbrook, Tullow Road, Carlow 10 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 6 Carlow Carrigbrook, Tullow Road, Carlow 19 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION SINGLE 7 Carlow Father Flood Avenue, 8 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 8 Carlow St. Oliver's Crescent, 4 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE St. Mary's Court & Dereen 9 Carlow 6 *N/A Q4‐2020 STAGE Heights, Tullow

SHIP CONSTRUCTION SINGLE 10 Carlow Crowsgrove, 1 *N/A Q1‐2020 STAGE

SHIP CONSTRUCTION SINGLE 11 Carlow 6 *N/A Q1‐2020 STAGE

SHIP CONSTRUCTION SINGLE 12 Carlow Brownbog, Hackettstown 1 *N/A Q1‐2020 STAGE

SHIP CONSTRUCTION SINGLE 13 Carlow Spahill, Borris 1 *N/A Q4‐2020 STAGE

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION SINGLE 14 Carlow Rural Ballypierce, Kildavin 1 *N/A the scheme is fully STAGE approved.

24/05/2021 1/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

15 SHIP CONSTRUCTION Carlow The Laurels, Carlow Town 5 *N/A Q2‐2018

16 SHIP CONSTRUCTION Carlow Ard na Greine, Tullow 16 *N/A Q4‐2018

17 SHIP CONSTRUCTION Carlow Road, Tullow 21 *N/A Q3‐2019

18 SHIP CONSTRUCTION Carlow Bagenalstown 20 *N/A Q3‐2020

19 SHIP CONSTRUCTION Carlow 2 *N/A Q3‐2018

20 SHIP CONSTRUCTION Carlow Slate Row, 4 *N/A Q4‐2018

21 SHIP CONSTRUCTION Carlow Mount Park, Carlow 4 *N/A Q4‐2017

22 SHIP CONSTRUCTION Carlow Myshall 4 *N/A Q1‐2018

23 SHIP CONSTRUCTION Carlow Pound Lane, Borris 4 *N/A Q3‐2017

24 SHIP CONSTRUCTION Carlow Rathvilly 10 *N/A Q2‐2017

25 SHIP CONSTRUCTION Carlow Moneybeg, Bagenalstown 24 *N/A Q3‐2017

26 SHIP CONSTRUCTION Carlow Paulville, Tullow (SRD) 1 *N/A Q3‐2017

27 SHIP CONSTRUCTION Carlow Maryborough St., Carlow 5 *N/A Q1‐2018

28 SHIP CONSTRUCTION Carlow Drumin, St. Mullins (SRD) 1 *N/A Q1‐2019

24/05/2021 2/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

29 SHIP CONSTRUCTION Carlow Pound Lane, Borris 9 *N/A Q3‐2020

Stage 1 approved Q3‐2020, 30 SHIP CONSTRUCTION Carlow Barrack Street, Carlow 7 *N/A outline design and costs being prepared.

Tintean Housing 31 CAS CONSTRUCTION TURNKEY Carlow Pollerton Big, Carlow 6 Q4‐2020 Association Ltd

Stage 4 approved Q2‐2020, Gleann na Bearu, Royal Oak Road, 32 CAS CONSTRUCTION Carlow 6 Respond the scheme is fully Bagenalstown approved.

Tintean Housing 33 CAS CONSTRUCTION Carlow Ballincarrig, Wexford Road 6 Q4‐2016 Association Ltd

Carlow Voluntary Housing 34 CAS CONSTRUCTION Carlow Homefield, Blackbog Road, Carlow 3 Q4‐2020 Association

7 units, Rivercourt, Carlow (Phase Co ‐ Operative Housing 35 CALF Turnkey Carlow 3 Q3‐2019 1) Ireland Society Limited

7 units, Rivercourt, Carlow (Phase Co ‐ Operative Housing 36 CALF Turnkey Carlow 4 Q4‐2019 2) Ireland Society Limited

Ballickmoyler, Graigcullen, Carlow Co ‐ Operative Housing 37 CALF Turnkey Carlow 22 Q3‐2019 (Phase 1) Ireland Society Limited

Ballickmoyler, Graigcullen, Carlow Co ‐ Operative Housing 38 CALF Turnkey Carlow 35 Q3‐2019 (Phase 2) Ireland Society Limited

Barrett Street, Bagnalstown, Co. Tintean Housing 39 CALF Turnkey Carlow 10 Q1‐2018 Carlow (Phase 1) Association Ltd

Browneshill Rise, Browneshill 40 CALF Turnkey Carlow Road, Chapelstown, Carlow 15 Túath Housing Association Q4‐2018 (Phase 1)

Browneshill Rise, Browneshill 41 CALF Turnkey Carlow Road, Chapelstown, Carlow 12 Túath Housing Association Q2‐2019 (Phase 2)

Browneshill Rise, Browneshill 42 CALF Turnkey Carlow Road, Chapelstown, Carlow 10 Túath Housing Association Q2‐2019 (Phase 3)

24/05/2021 3/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Browneshill Rise, Browneshill 43 CALF Turnkey Carlow Road, Chapelstown, Carlow 6 Túath Housing Association Q3‐2019 (Phase 4)

Browneshill Rise, Browneshill 44 CALF Turnkey Carlow Road, Chapelstown, Carlow 16 Túath Housing Association Q4‐2019 (Phase 5)

Browneshill Wood, Browneshill 45 CALF Turnkey Carlow Road, Chapelstown, Carlow 14 Túath Housing Association Q4‐2018 (Phase 1)

Cois Dara, Tullow Road, 46 CALF Turnkey Carlow 32 Túath Housing Association Q2‐2019 Chapelstown, Carlow (Phase 1)*

Cois Dara, Tullow Road, 47 CALF Turnkey Carlow 21 Túath Housing Association Q2‐2019 Chapelstown, Carlow (Phase 2)*

Cois Dara, Tullow Road, 48 CALF Turnkey Carlow 10 Túath Housing Association Q2‐2019 Chapelstown, Carlow (Phase 3)

Greenhills, Leighlin Road, Co ‐ Operative Housing 49 CALF Turnkey Carlow 8 Q3‐2020 Graiguecullen, Carlow (Phase 1) Ireland Society Limited

Mill Race, Paupish Lane, Carlow, 50 CALF Turnkey Carlow 3 Túath Housing Association Q4‐2020 Co. Carlow (Phase 1)

Mill Race, Paupish Lane, Carlow, 51 CALF Turnkey Carlow 6 Túath Housing Association Q4‐2019 Co. Carlow (Phase 2)

Co ‐ Operative Housing 52 CALF Turnkey Carlow Rivercourt, Carlow (Phase 1) 28 Q4‐2020 Ireland Society Limited

Co ‐ Operative Housing 53 CALF Turnkey Carlow Rivercourt, Carlow (Phase 2)* 19 Q3‐2018 Ireland Society Limited

Sleaty Street, Graigcullen, Carlow 54 CALF Turnkey Carlow 26 Cluid Housing Q1‐2019 (Phase 1)

Tanner Hall, Athy Road, Carlow Co ‐ Operative Housing 55 CALF Turnkey Carlow 9 Q4‐2020 (Phase 1) Ireland Society Limited

The Millrace, Burrin, Co. Carlow Co ‐ Operative Housing 56 CALF Turnkey Carlow 22 Q1‐2020 (Phase 1)* Ireland Society Limited

24/05/2021 4/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Ashgrove, Derrylurgan, 57 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Ashgrove, Derrylurgan, 58 Cavan 4 *N/A Q3‐2020 TURNKEY Ballyjamesduff (Phase 2)

SHIP CONSTRUCTION Ashgrove, Derrylurgan, 59 Cavan 3 *N/A Q4‐2020 TURNKEY Ballyjamesduff (Phase 3)

SHIP CONSTRUCTION Ashgrove, Derrylurgan, 60 Cavan 4 *N/A Q2‐2019 TURNKEY Ballyjamesduff (Phase 4)

SHIP CONSTRUCTION Woodlands, Killyfinla, 61 Cavan 4 *N/A Q1‐2021 TURNKEY Ballyjamesduff

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION Woodsland, Killyfinla, 62 Cavan 8 *N/A the scheme is fully TURNKEY Ballyjamesduff approved.

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION Woodlands, Killyfinla, 63 Cavan 10 *N/A the scheme is fully TURNKEY Ballyjamesduff approved.

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION Woodlands, Killyfinla, 64 Cavan 10 *N/A the scheme is fully TURNKEY Ballyjamesduff approved.

SHIP CONSTRUCTION Lakeland Close, Swellan, Cavan 65 Cavan 2 *N/A Q4‐2020 TURNKEY Town

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION Mullaghduff, , Co. 66 Cavan 8 *N/A the scheme is fully TURNKEY Cavan approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION Mullaghduff, Ballyconnell, Co. 67 Cavan 12 *N/A the scheme is fully TURNKEY Cavan approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION Mullaghduff, Ballyconnell, Co. 68 Cavan 11 *N/A the scheme is fully TURNKEY Cavan approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION Mullaghduff, Ballyconnell, Co. 69 Cavan 12 *N/A the scheme is fully TURNKEY Cavan approved.

70 SHIP CONSTRUCTION Cavan Rosehill, Mullagh (Phase 6) 8 *N/A Q1‐2019

24/05/2021 5/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

71 SHIP CONSTRUCTION Cavan 4 *N/A Q1‐2018

72 SHIP CONSTRUCTION Cavan Woodlands, 8 *N/A Q4‐2018

73 SHIP CONSTRUCTION Cavan Butlersbridge (Phase 1) 2 *N/A Q2‐2017

74 SHIP CONSTRUCTION Cavan Clones Road, Butlersbridge 2 *N/A Q3‐2020

75 SHIP CONSTRUCTION Cavan Corstruce, 4 *N/A Q1‐2020

76 SHIP CONSTRUCTION Cavan Main Street, Mullagh 19 *N/A Q4‐2020

Stage 2 approved Q4‐2020, 77 SHIP CONSTRUCTION Cavan Elm Grove, Main St, Cavan Town 13 *N/A full design/tender being prepared.

Stage 4 approved Q1‐2021, 78 SHIP CONSTRUCTION Cavan Cavan Road, Ballinagh 15 *N/A the scheme is fully approved.

Stage 4 approved Q4‐2020, 79 SHIP CONSTRUCTION Cavan Main St., Butlersbridge 6 *N/A the scheme is fully approved.

80 SHIP CONSTRUCTION Cavan Cluain Dara, 3 *N/A Q1‐2021

Stage 2 approved Q4‐2020, Fairymount Close, Kingscourt, Co. 81 SHIP CONSTRUCTION Cavan 3 *N/A full design/tender being Cavan prepared.

Stage 1 approved Q4‐2019, St. Bridgets Terrace, Cavan Town 82 SHIP CONSTRUCTION Cavan 12 *N/A outline design and costs (Infill) being prepared.

Stage 1 approved Q2‐2020, Beckscourt, Eastboro, 83 SHIP CONSTRUCTION Cavan 47 *N/A outline design and costs being prepared.

Túath Housing Association 84 CAS CONSTRUCTION TURNKEY Cavan Castlemanor Village, Cavan Town 29 Q3‐2019 Ltd

24/05/2021 6/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

St. Killian's Housing St. Killian's Housing Association 85 CAS CONSTRUCTION Cavan 4 Association, Mullagh, Co. Q1‐2021 Ltd., Mullagh, Co. Cavan Cavan

16 Units, Fairgreen Park, Mullagh, Clanmil Housing 86 CALF Turnkey Cavan 16 Q1‐2020 Co. Cavan (Phase 1) Association Ireland

25 units, Drumalee Manor, 87 CALF Turnkey Cavan 12 Túath Housing Association Q1‐2019 Drumalee, Co. Cavan (Phase 1)

25 units, Drumalee Manor, 88 CALF Turnkey Cavan 13 Túath Housing Association Q1‐2019 Drumalee, Co. Cavan (Phase 2)

Cluain Dara, Kingscourt, Co Cavan 89 CALF Turnkey Cavan 16 Cluid Housing Q4‐2016 (Phase 1)

Drumalee Manor, Drumalee, 90 CALF Turnkey Cavan 4 Túath Housing Association Q2‐2018 Cavan (Phase 1)

Drumalee Manor, Drumalee, 91 CALF Turnkey Cavan 5 Túath Housing Association Q3‐2018 Cavan (Phase 2)

Drumalee Manor, Drumalee, 92 CALF Turnkey Cavan 2 Túath Housing Association Q4‐2018 Cavan (Phase 3)

Rampart View, Virginia, Co. Cavan Co ‐ Operative Housing 93 CALF Turnkey Cavan 2 Q3‐2019 (Phase 1) Ireland Society Limited

Rampart View, Virginia, Co. Cavan Co ‐ Operative Housing 94 CALF Turnkey Cavan 6 Q4‐2019 (Phase 2) Ireland Society Limited

Rampart View, Virginia, Co. Cavan Co ‐ Operative Housing 95 CALF Turnkey Cavan 6 Q1‐2019 (Phase 3) Ireland Society Limited

Rampart View, Virginia, Co. Cavan Co ‐ Operative Housing 96 CALF Turnkey Cavan 5 Q1‐2019 (Phase 4) Ireland Society Limited

The Gallops, Cavan Town, Co. 97 CALF Turnkey Cavan 12 Cluid Housing Q4‐2020 Cavan (Phase 1)

The Gallops, Cavan Town, Co. 98 CALF Turnkey Cavan 22 Cluid Housing Q4‐2019 Cavan (Phase 2)*

24/05/2021 7/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 99 Clare River View, School Road, Corofin 2 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Cloughleigh Road + Shallee Drive, 100 Clare 4 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 101 Clare Shantraud Woods, Killaloe 4 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION SINGLE 102 Clare Cappagh Lodge, Sixmilebridge 2 *N/A Q4‐2020 STAGE

SHIP CONSTRUCTION SINGLE 103 Clare St. Michaels Place, Kilmihil 2 *N/A Q4‐2020 STAGE

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION SINGLE 104 Clare Madden's Terrace, Clarecastle 2 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION SINGLE 105 Clare Dun na Mara, Doonbeg 2 *N/A the scheme is fully STAGE approved.

106 SHIP CONSTRUCTION Clare Roslevan, Ennis 8 *N/A Q2‐2020

107 SHIP CONSTRUCTION Clare Feakle 13 *N/A Q4‐2019

Glor Srutha, Knockbrack Lower, 108 SHIP CONSTRUCTION Clare 9 *N/A Q4‐2019 Clonlara

109 SHIP CONSTRUCTION Clare Seaview Park, Quilty 18 *N/A Q4‐2020

110 SHIP CONSTRUCTION Clare Ashline, Kilrush Road, Ennis 40 *N/A Q3‐2020

111 SHIP CONSTRUCTION Clare Miltown Malbay 27 *N/A Q3‐2020

112 SHIP CONSTRUCTION Clare Doonaun, Tulla 25 *N/A Q4‐2020

24/05/2021 8/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Boheraroan, Newmarket‐on‐ 113 SHIP CONSTRUCTION Clare 18 *N/A Q4‐2020 Fergus

Stage 2 approved Q1‐2021, 114 SHIP CONSTRUCTION Clare Scariff 18 *N/A full design/tender being prepared.

115 SHIP CONSTRUCTION Clare Kilkee Road, Doonbeg 8 *N/A Q1‐2020

Stage 3 approved Q1‐2021, the scheme is now 116 SHIP CONSTRUCTION Clare Tulla Road, Roslevan, Ennis 8 *N/A approved to proceed to tender.

117 SHIP CONSTRUCTION Clare St Senan's Terrace, Kilrush 3 *N/A Q4‐2019

Stage 3 approved Q1‐2021, the scheme is now 118 SHIP CONSTRUCTION Clare Drumcliffe Road, Ennis, Co. Clare 26 *N/A approved to proceed to tender.

Stage 1 approved Q1‐2021, 119 SHIP CONSTRUCTION Clare Deerpark, Ennistymon 30 *N/A outline design and costs being prepared.

Stage 2 approved Q4‐2020, 120 SHIP CONSTRUCTION Clare Ballyliddan West, Sixmilebridge 16 *N/A full design/tender being prepared.

Haggard View, Clarecastle (Phase Anvers Housing 121 CAS CONSTRUCTION TURNKEY Clare 2 Q2‐2018 2) Association Ltd

Haggard View, Clarecastle (Phase Anvers Housing 122 CAS CONSTRUCTION TURNKEY Clare 2 Q1‐2018 1) Association Ltd

123 CAS CONSTRUCTION Clare Cahercalla, Ennis (Phase 2) 15 Cuan an Chlair Ltd Q4‐2020

Society of Saint Vincent de 124 CAS CONSTRUCTION Clare Laurel Lodge, Clare Road, Ennis 3 Q4‐2016 Paul

Newgrove Housing 125 CAS CONSTRUCTION Clare Monaskeha Heights 4 Q3‐2019 Association Ltd

Thomond Housing 126 CAS CONSTRUCTION Clare Roo East 4 Q4‐2018 Association Ltd

24/05/2021 9/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

9 Elmwood, Ballycannon Heights, Thomond Housing 127 CAS CONSTRUCTION Clare 4 Q1‐2019 Meelick Association Ltd

Stage 1 approved Q2‐2019, Newgrove Housing 128 CAS CONSTRUCTION Clare Teach Rua, Edenvale Ennis 4 outline design and costs Association Ltd being prepared.

Acha Bhile, Loughville, Lahinch 129 CALF Turnkey Clare 12 Cluid Housing Q2‐2018 Road, Ennis, Co Clare (Phase 1)

Acha Bhile, Loughville, Lahinch 130 CALF Turnkey Clare 18 Cluid Housing Q4‐2018 Road, Ennis, Co Clare (Phase 2)

Cahercalla, Drumbiggle, Ennis, Co. 131 CALF Turnkey Clare 2 Cluid Housing Q4‐2020 Clare (Phase 1)*

Cahercalla, Drumbiggle, Ennis, Co. 132 CALF Turnkey Clare 2 Cluid Housing Q2‐2019 Clare (Phase 2)*

Cluain Fia, Crusheen, Co. Clare 133 CALF Turnkey Clare 2 Cluid Housing Q2‐2020 (Phase 1)*

Cluain Fia, Crusheen, Co. Clare 134 CALF Turnkey Clare 2 Cluid Housing Q4‐2020 (Phase 2)*

Cluain Ros Leamhan, Roslevan, Co ‐ Operative Housing 135 CALF Turnkey Clare Tulla Road, Ennis, Co. Clare (Phase 3 Q4‐2018 Ireland Society Limited 1)

Cluain Ros Leamhan, Roslevan, Co ‐ Operative Housing 136 CALF Turnkey Clare Tulla Road, Ennis, Co. Clare (Phase 2 Q2‐2019 Ireland Society Limited 2)

Gleann Cora, Newmarket on Co ‐ Operative Housing 137 CALF Turnkey Clare 29 Q4‐2020 Fergus, Co. Clare (Phase 1)* Ireland Society Limited

Gleann Cora, Newmarket on Co ‐ Operative Housing 138 CALF Turnkey Clare 2 Q2‐2019 Fergus, Co. Clare (Phase 2)* Ireland Society Limited

Lios Anama, Sixmilebridge, Clare Co ‐ Operative Housing 139 CALF Turnkey Clare 28 Q4‐2017 (Phase 1) Ireland Society Limited

Revised ‐ Bruachlan, Westbury, Co Co ‐ Operative Housing 140 CALF Construction Clare 22 Q2‐2016 Clare (Phase 1) Ireland Society Limited

24/05/2021 10/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Sycamore Drive, Ennis, Co. Clare 141 CALF Turnkey Clare 3 Cluid Housing Q4‐2019 (Phase 1)*

Sycamore Drive, Ennis, Co. Clare 142 CALF Turnkey Clare 2 Cluid Housing Q4‐2020 (Phase 2)*

Tullyvarraga, Shannon, Co. Clare Co ‐ Operative Housing 143 CALF Turnkey Clare 31 Q4‐2019 (Phase 1)* Ireland Society Limited

Tullyvarraga, Shannon, Co. Clare Co ‐ Operative Housing 144 CALF Turnkey Clare 16 Q4‐2019 (Phase 2) Ireland Society Limited

PUBLIC PRIVATE PARTNERSHIP 145 Clare Shannon East 51 *N/A Q4‐2019 (Bundle 2)

146 SHIP DIALOG City Arus Mhuire 30 *N/A Q4‐2018

Stage 4 approved Q1‐2018, 147 SHIP DIALOG Cork City Barrack Street 32 *N/A the scheme is fully approved.

148 SHIP DIALOG Cork City FaranFerris 5 *N/A Q4‐2019

149 SHIP DIALOG Cork City High Street 9 *N/A Q4‐2019

150 SHIP DIALOG Cork City Tramore Road 4 *N/A Q4‐2018

151 SHIP DIALOG Cork City Whites Street 43 *N/A Q4‐2019

Stage 4 approved Q1‐2018, 152 SHIP DIALOG Cork City Woods Street 16 *N/A the scheme is fully approved.

153 SHIP DIALOG Cork City Church Road, Blackrock 43 *N/A Q3‐2018

1‐5, Ard Aoibhinn, Banduff, 154 SHIP DIALOG Cork City 5 *N/A Q3‐2018 Mayfield

24/05/2021 11/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

155 SHIP DIALOG Cork City Corcorans Quay 3 *N/A Q2‐2018

156 SHIP DIALOG Cork City Street 25 *N/A Q4‐2019

157 SHIP DIALOG Cork City Ballinure Road, Cork City 5 *N/A Q4‐2020

Stage 4 approved Q3‐2018, 158 SHIP DIALOG Cork City Moss Lane, Riverway, Cork 5 *N/A the scheme is fully approved.

159 SHIP DIALOG Cork City Gerald Griffin Street, Cork 13 *N/A Q4‐2020

160 SHIP DIALOG Cork City Lower John Street, Cork 17 *N/A Q4‐2020

Stage 4 approved Q2‐2019, 161 SHIP DIALOG Cork City Skehard Road, Blackrock, Cork 16 *N/A the scheme is fully approved.

Stage 4 approved Q2‐2019, 162 SHIP DIALOG Cork City Coach Street, Cork 12 *N/A the scheme is fully approved.

Stage 4 approved Q2‐2019, 163 SHIP DIALOG Cork City Shanakiel Road, Cork 20 *N/A the scheme is fully approved.

Stage 4 approved Q2‐2019, 164 SHIP DIALOG Cork City Spring Lane, Blackpool, Cork 8 *N/A the scheme is fully approved.

Stage 4 approved Q2‐2019, 165 SHIP DIALOG Cork City Glen Ryan Road, Cork 9 *N/A the scheme is fully approved.

Stage 2 approved Q2‐2020, 166 SHIP DIALOG Cork City Pouladuff Road, Cork 11 *N/A full design/tender being prepared.

Stage 2 approved Q2‐2020, Watercourse Road, Blackpool, 167 SHIP DIALOG Cork City 37 *N/A full design/tender being Cork prepared.

Stage 4 approved Q3‐2020, Denroche's Cross, Road, 168 SHIP DIALOG Cork City 43 *N/A the scheme is fully Cork approved.

24/05/2021 12/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q1‐2021, 169 SHIP DIALOG Cork City Wolsey Court, Blackpool, Cork 49 *N/A the scheme is fully approved.

SHIP CONSTRUCTION 170 Cork City 1‐4 Marble Lane 4 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 171 Cork City Sheridan Park, Tramore Road 28 *N/A Q4‐2016 TURNKEY

SHIP CONSTRUCTION 37‐39 Dublin Street, Blackpool, 172 Cork City 5 *N/A Q2‐2018 TURNKEY Cork

SHIP CONSTRUCTION 6‐10, Ard Aoibhinn, Banduff, 173 Cork City 5 *N/A Q4‐2018 TURNKEY Mayfield

SHIP CONSTRUCTION 174 Cork City 2 Deanrock Cottages, Togher 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 175 Cork City 258 & 259 Blarney Street, Cork 2 *N/A Q1‐2018 TURNKEY

SHIP CONSTRUCTION 1 & 2 The Groves, Skehard Road, 176 Cork City 2 *N/A Q2‐2018 TURNKEY Cork

SHIP CONSTRUCTION 3B & 9B South Terrace Court, 177 Cork City 2 *N/A Q4‐2018 TURNKEY South Terrace, Cork

SHIP CONSTRUCTION Ballinlough Road / Knockrea Lawn, 178 Cork City 6 *N/A Q2‐2019 TURNKEY Ballinlough, Cork

SHIP CONSTRUCTION 179 Cork City Ard na Ri, Banduff Road, Cork 10 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Gearney's Boreen, Commons 180 Cork City 3 *N/A Q4‐2019 TURNKEY Road, Cork

SHIP CONSTRUCTION Ard na Ri, Banduff Road, Cork 181 Cork City 10 *N/A Q4‐2019 TURNKEY (Phase 2)

SHIP CONSTRUCTION 182 Cork City Eagle Valley, Sarsfield Road 1 *N/A Q4‐2019 TURNKEY

24/05/2021 13/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Knockfree Avenue, 183 Cork City 2 *N/A Q4‐2019 TURNKEY Road, Fairhill, Cork

SHIP CONSTRUCTION 3‐10 Herbert Lawn, Belmont, 184 Cork City 8 *N/A Q4‐2019 TURNKEY Rochestown, Cork

SHIP CONSTRUCTION Elton Wood & Herbert Lawn, 185 Cork City 8 *N/A Q4‐2019 TURNKEY Rochestown, Cork

SHIP CONSTRUCTION Aspen Drive, Maryborough Hill, 186 Cork City 29 *N/A Q4‐2019 TURNKEY Cork

SHIP CONSTRUCTION 5 Fairfield Heights, Upper Fairhill, 187 Cork City 3 *N/A Q4‐2020 TURNKEY Cork

SHIP CONSTRUCTION Ringcroft Avenue, Ringmahon 188 Cork City 2 *N/A Q4‐2020 TURNKEY Road, Mahon

SHIP CONSTRUCTION Cluain Ard, Waterloo Road, 189 Cork City 3 *N/A Q4‐2020 TURNKEY Blarney, Cork

Stage 2 approved Q3‐2019, 190 SHIP CONSTRUCTION Cork City Poulavone, 57 *N/A full design/tender being prepared.

191 SHIP CONSTRUCTION Cork City The Meadows, Knocknacullen 1 *N/A Q3‐2016

Stage 3 approved Q1‐2019, the scheme is now 192 SHIP CONSTRUCTION Cork City Boyces Street 51 *N/A approved to proceed to tender.

Shandon Street/John Philpott 193 SHIP CONSTRUCTION Cork City 9 *N/A Q4‐2020 Curran Street

194 SHIP CONSTRUCTION Cork City St. Johns Well 6 *N/A Q4‐2019

195 SHIP CONSTRUCTION Cork City Churchfield Place East 3 *N/A Q4‐2018

196 SHIP CONSTRUCTION Cork City Deanrock, Togher 8 *N/A Q4‐2018

24/05/2021 14/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 3 approved Q3‐2019, the scheme is now 197 SHIP CONSTRUCTION Cork City Gerald Griffin Street 43 *N/A approved to proceed to tender.

198 SHIP CONSTRUCTION Cork City Cappanoole 2 *N/A Q4‐2016

Stage 2 approved Q4‐2019, Madonna House, Ballincollig 199 SHIP CONSTRUCTION Cork City 6 *N/A full design/tender being (Phase 2) prepared.

Stage 2 approved Q3‐2019, 200 SHIP CONSTRUCTION Cork City Bramble Cottages 5 *N/A full design/tender being prepared.

Stage 2 approved Q2‐2020, Errigal Heights, The Glen, Cork 201 SHIP CONSTRUCTION Cork City 32 *N/A full design/tender being City prepared.

Stage 2 approved Q3‐2019, 202 SHIP CONSTRUCTION Cork City Lawn, Mayfield, Cork 3 *N/A full design/tender being prepared.

203 SHIP CONSTRUCTION Cork City Deanrock, Togher 7 *N/A Q1‐2019

Stage 2 approved Q4‐2019, Hollywood Estate Infill Housing, 204 SHIP CONSTRUCTION Cork City 7 *N/A full design/tender being Blarney Road, Cork prepared.

205 SHIP CONSTRUCTION Cork City Deanrock, Togher 50 *N/A Q3‐2019

Stage 1 approved Q2‐2019, Clover Hill Court, Bessboro Road, 206 SHIP CONSTRUCTION Cork City 51 *N/A outline design and costs Mahon, Cork being prepared.

Stage 1 approved Q2‐2019, 207 SHIP CONSTRUCTION Cork City Westside, Model Farm Road, Cork 32 *N/A outline design and costs being prepared.

Gerald Griffin Apartments ‐ Block Stage 1 approved Q3‐2019, 208 SHIP CONSTRUCTION Cork City 7, North Monastery Road / St. 6 *N/A outline design and costs Vincent's Road, Cork being prepared.

Stage 2 approved Q2‐2020, 209 SHIP CONSTRUCTION Cork City Sli Gartan, Mayfield, Cork 1 *N/A full design/tender being prepared.

210 REGENERATION Cork City CNWQR Knocknaheeny Phase 1B 29 *N/A Q4‐2017

24/05/2021 15/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

211 REGENERATION Cork City CNWQR Knocknaheeny Phase 2A 47 *N/A Q4‐2019

Stage 3 approved Q2‐2020, the scheme is now 212 REGENERATION Cork City CNWQR Knocknaheeny Phase 1C 41 *N/A approved to proceed to tender. Stage 3 approved Q2‐2020, the scheme is now 213 REGENERATION Cork City CNWQR Knocknaheeny Phase 2B 38 *N/A approved to proceed to tender.

214 REGENERATION Cork City CNWQR Knocknaheeney Phase 2C 24 *N/A Q4‐2020

Stage 3 approved Q1‐2020, Foyle Avenue Infill Housing the scheme is now 215 REGENERATION Cork City Development, Knocknaheeny, 3 *N/A approved to proceed to Cork tender. Stage 3 approved Q1‐2020, Ardmore Avenue, Knocknaheeny, the scheme is now 216 REGENERATION Cork City 1 *N/A Cork approved to proceed to tender.

Stage 1 approved Q2‐2019, 217 REGENERATION Cork City CNWQR Knocknaheeny Phase 3B 62 *N/A outline design and costs being prepared.

Stage 1 approved Q2‐2020, 218 REGENERATION Cork City CNWQR Knocknaheeny Phase 4A 43 *N/A outline design and costs being prepared.

Good Shepherd Services 219 CAS CONSTRUCTION Cork City Edel House, Grattan Street 37 Q4‐2020 Ltd

Stage 1 approved Q3‐2020, Saint Vincent's Convent, Vincent's 220 CAS CONSTRUCTION Cork City 20 Respond outline design and costs Ave/St. Mary's Street being prepared.

Stage 3 approved Q4‐2019, the scheme is now 221 CAS CONSTRUCTION Cork City Thomas Davis Street (Phase 1) 28 Respond approved to proceed to tender.

Cork Mental Health 222 CAS CONSTRUCTION Cork City Ceanncora Lawn, Ballinlough 1 Voluntary Housing Q3‐2018 Association Ltd

St. Joachim & Anne's, Anglesea Simon Community : Cork 223 CAS CONSTRUCTION Cork City 8 Q4‐2020 Street Simon

224 CAS CONSTRUCTION Cork City 27‐29 Dublin Street, Blackpool 10 Respond Q3‐2018

24/05/2021 16/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q1‐2021, Ard na Ri, Closes Green, Farranree Sheltered 225 CAS CONSTRUCTION Cork City 20 full design/tender being Farranree, Cork Housing Association prepared.

Model Quarters, Tower, Blarney, Circle Voluntary Housing 226 CALF Turnkey Cork City 3 Q2‐2019 Co Cork (Phase 1) Association Ltd

Focus Housing Association 227 CALF Turnkey Cork City Kyle Street (Phase 1) 6 Q1‐2021 CLG

5 units, Shandon Street, Cork Circle Voluntary Housing 228 CALF Turnkey Cork City 5 Q3‐2019 (Phase 1) Association Ltd

Bishops Avenue, Farrenferris, 229 CALF Turnkey Cork City 37 Túath Housing Association Q4‐2019 Fairhill, Cork (Phase 1)*

Bishops Avenue, Farrenferris, 230 CALF Turnkey Cork City 49 Túath Housing Association Q4‐2020 Fairhill, Cork (Phase 2)*

Boherboy Road, Silversprings Hill, 231 CALF Turnkey Cork City 15 Respond Q1‐2021 Cork City (Phase 1)*

Convent Gardens, Blackrock Villas, 232 CALF Turnkey Cork City 1 Túath Housing Association Q4‐2019 Blackrock, Co. Cork (Phase 1)

Crawford Gate, Bessboro, 233 CALF Turnkey Cork City 4 Túath Housing Association Q4‐2020 Blackrock, Co. Cork (Phase 1)

Crawford Gate, Bessboro, 234 CALF Turnkey Cork City 2 Túath Housing Association Q4‐2020 Blackrock, Co. Cork (Phase 2)

Croppy Boy, Fairhill, Cork (Phase 235 CALF Turnkey Cork City 7 Túath Housing Association Q3‐2020 1)

Croppy Boy, Fairhill, Cork (Phase 236 CALF Turnkey Cork City 14 Túath Housing Association Q4‐2020 2)*

Emerald View, Old Mallow Road, Focus Housing Association 237 CALF Turnkey Cork City 6 Q1‐2021 Cork City (Phase 1) CLG

Evergreen Road, Turners Cross, 238 CALF Turnkey Cork City 28 Respond Q4‐2020 Cork (Phase 1)*

24/05/2021 17/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Green Lane, Blackpool, Cork City 239 CALF Construction Cork City 112 Cluid Housing Q1‐2021 (Phase 1)

Haig Gardens, Boreenamanna 240 CALF Turnkey Cork City Road and Wallace Avenue, 27 Respond Q4‐2020 Ballintemple (Phase 1)*

Hereford Place, Ballymacthomas 241 CALF Turnkey Cork City 19 Respond Q1‐2020 Street, Cork City (Phase 1)*

Leeside Apartments, Bachelors 242 CALF Turnkey Cork City 72 Cluid Housing Q4‐2018 Quay, Cork City (Phase 1)

Leeside Apartments, Bachelors 243 CALF Turnkey Cork City 6 Cluid Housing Q3‐2019 Quay, Cork City (Phase 2)

Lios Cara, Rathpeacon, Killeens, 244 CALF Turnkey Cork City 12 Cluid Housing Q4‐2019 Cork (Phase 1)

Lower Road, Cork City 245 CALF Construction Cork City 8 Galtan Ltd Q4‐2019 (Phase 1)

Lr. Glanmire Road & 2 Braemer, 246 CALF Construction Cork City 3 Galtan Ltd Q1‐2018 Cork (Phase 1)

Lr. Glanmire Road & 2 Braemer, 247 CALF Construction Cork City 3 Galtan Ltd Q4‐2018 Cork (Phase 2)

Maryborough Ridge & Blackrock 248 CALF Turnkey Cork City Villas 57 Túath Housing Association Q4‐2019 (Phase 1)*

Miles Stream, Shanakiel, Cork 249 CALF Turnkey Cork City 6 Túath Housing Association Q4‐2020 (Phase 1)

Miles Stream, Shanakiel, Cork 250 CALF Turnkey Cork City 14 Túath Housing Association Q4‐2020 (Phase 2)

Miles Stream, Shanakiel, Cork 251 CALF Turnkey Cork City 22 Túath Housing Association Q4‐2020 (Phase 3)

252 CALF Turnkey Cork City Millerd Street, Cork (Phase 1) 25 Respond Q4‐2020

24/05/2021 18/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

North Abbey Street, Cork City 253 CALF Turnkey Cork City 6 Respond Q4‐2018 (Phase 1)

Redforge Road, Blackpool, Cork 254 CALF Turnkey Cork City 18 Respond Q4‐2020 City (Phase 1)

Redforge Road, Blackpool, Cork 255 CALF Turnkey Cork City 62 Respond Q1‐2020 City (Phase 2)*

Revised‐The Meadows, 256 CALF Turnkey Cork City Knocknacullen East, 31 Túath Housing Association Q4‐2018 Gurranabraher, Cork (Phase 1)

Revised‐The Meadows, 257 CALF Turnkey Cork City Knocknacullen East, 21 Túath Housing Association Q4‐2019 Gurranabraher, Cork (Phase 2)

Springville House, Bulls Lane, 258 CALF Turnkey Cork City 35 Túath Housing Association Q4‐2020 Blackrock Road, Cork (Phase 1)

The Meadows (Phase 2) 259 CALF Turnkey Cork City Gurranabraher, Cork City (Phase 17 Túath Housing Association Q4‐2019 1)

The Oaks, Frankfield, Douglas, 260 CALF Turnkey Cork City 2 Túath Housing Association Q4‐2019 Cork City (Phase 1)*

261 CALF Turnkey Cork City Tower Street, Cork City (Phase 1) 2 Threshold Ltd Q3‐2020

Woodside, Kerry Pike, Cork (Phase 262 CALF Turnkey Cork City 22 Cluid Housing Q4‐2020 1)*

SHIP CONSTRUCTION Church Road/Station Road, 263 Cork County 18 *N/A Q2‐2018 TURNKEY

SHIP CONSTRUCTION 264 Cork County Inis Alainn & Castleoaks, Bandon 11 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 265 Cork County Gleann Tuairigh, 3 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 266 Cork County Millview Road, 11 *N/A Q4‐2019 TURNKEY

24/05/2021 19/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 267 Cork County , 2 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 268 Cork County College Wood, 31 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 269 Cork County Castletreasure, Douglas 12 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 270 Cork County Crann Ard, Fermoy 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 271 Cork County CulAird Carraigtwohill 29 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 272 Cork County Castletreasure, Douglas 12 *N/A Q1‐2017 TURNKEY

SHIP CONSTRUCTION 273 Cork County Castletreasure, Douglas 16 *N/A Q1‐2017 TURNKEY

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION 274 Cork County Road, 5 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION St. Mary’s Road, 275 Cork County 7 *N/A Q3‐2020 TURNKEY Phase 2

SHIP CONSTRUCTION 276 Cork County , Fermoy 10 *N/A Q1‐2020 TURNKEY

SHIP CONSTRUCTION 277 Cork County Quartertown, Mallow 5 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 278 Cork County Spa Glen,Ballyviniter, Mallow 8 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 279 Cork County Beacon Point, Baltimore 6 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 280 Cork County Corrin View, Fermoy 6 *N/A Q2‐2019 TURNKEY

24/05/2021 20/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION No. 43 & No. 50 Chapel Court, 281 Cork County 2 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 282 Cork County Cul Na Smear, Bandon 14 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Glen Dara, Ard Cashel, 283 Cork County 6 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Clarendon Brooks, Carrs Hill, 284 Cork County 9 *N/A Q2‐2019 TURNKEY Douglas

SHIP CONSTRUCTION 285 Cork County Sweetfields, Youghal 15 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 286 Cork County 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 287 Cork County , Mount Rivers 3 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Clarendon Brooks, Carrs Hill, 288 Cork County 17 *N/A Q4‐2020 TURNKEY Douglas Phase 3

SHIP CONSTRUCTION 289 Cork County Seafield, , 3 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 290 Cork County Parklands, Youghal 13 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 291 Cork County Oliver Plunkett Place, 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION No.9 and No.10 Chapel Court, 292 Cork County 2 *N/A Q4‐2018 TURNKEY Skibbereen,

SHIP CONSTRUCTION 293 Cork County Tir Cluain, 8 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 294 Cork County College Mews, Cobh 6 *N/A Q4‐2018 TURNKEY

24/05/2021 21/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 295 Cork County 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 296 Cork County Fairgreen, Mallow 10 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 297 Cork County Tir Cluain, Midleton (Phase 2) 14 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION Church Road/Station Road, 298 Cork County 7 *N/A Q3‐2018 TURNKEY Carrigtwohill (2)

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 299 Cork County Canon St, Rathcormac 3 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 300 Cork County Percival St, Kanturk 2 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 301 Cork County 9 & 9a Main Street, 2 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 302 Cork County Parklands, Youghal ‐ Phase 2 6 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 303 Cork County Rathcormac Phase 2 4 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 304 Cork County Inis Fáil, Curraclough, Bandon 13 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 305 Cork County Maple Woods, Midleton 6 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 306 Cork County Crann Ard, Fermoy ‐ Phase 3 8 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION St. Mary's Road, Dunmanway 307 Cork County 6 *N/A Q3‐2020 TURNKEY Phase 3

SHIP CONSTRUCTION 308 Cork County Sweetfields, Youghal, Phase 2 20 *N/A Q1‐2019 TURNKEY

24/05/2021 22/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Mill Road, Avoncore, Bloomfield, 309 Cork County 12 *N/A Q4‐2020 TURNKEY Midleton

SHIP CONSTRUCTION Mill Road, Avoncore, Broomfield, 310 Cork County 11 *N/A Q1‐2021 TURNKEY Midleton ‐ Phase 2

Stage 4 approved Q1‐2019, SHIP CONSTRUCTION Mill Road, Avoncore, Bloomfield, 311 Cork County 17 *N/A the scheme is fully TURNKEY Midleton ‐ Phase 3 approved.

SHIP CONSTRUCTION Cluain Cairn, Station Road, 312 Cork County 2 *N/A Q3‐2019 TURNKEY Carrigtwohill

SHIP CONSTRUCTION 313 Cork County Spa Glen,Ballyviniter, Mallow 6 *N/A Q2‐2020 TURNKEY

SHIP CONSTRUCTION 314 Cork County Gleann Orga, 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 315 Cork County Lios Ard, Ballyhooly 8 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 316 Cork County Cluain Ard, Cobh 6 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 317 Cork County Baltimore, 12 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 318 Cork County Chapel Court, Skibbereen 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 319 Cork County Cluain Ard, Freemount 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 320 Cork County Glengarriff 5 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 321 Cork County The Cove, 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 322 Cork County An Tui, , Leamlara 3 *N/A Q4‐2019 TURNKEY

24/05/2021 23/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 323 Cork County Millstreet Road, 12 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Clarendon Brooks, Carrs Hill, 324 Cork County 14 *N/A Q4‐2019 TURNKEY Douglas Phase 2

SHIP CONSTRUCTION Cluain Cairn, Station Road, 325 Cork County 12 *N/A Q4‐2020 TURNKEY Carrigtwohill

SHIP CONSTRUCTION 326 Cork County Glenbeg The Beeches, Boherbue 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 327 Cork County Chapel Court, Skibbereen 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 328 Cork County Millview Road, Kanturk ‐ Phase 3 4 *N/A Q1‐2021 TURNKEY

SHIP CONSTRUCTION 329 Cork County An Tui, Lisgoold, Leamlara 1 *N/A Q2‐2020 TURNKEY

SHIP CONSTRUCTION 330 Cork County Bruhenny, Churchtown 6 *N/A Q4‐2019 TURNKEY

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 331 Cork County Ard Bhaile, 6 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 332 Cork County Cecilstown, Mallow 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 333 Cork County Ballymacmoy, Killavullen, Co. Cork 13 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 334 Cork County Meenane, Watergrasshill 25 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 335 Cork County Spa Glen,Ballyviniter, Mallow 8 *N/A Q3‐2019 TURNKEY

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 336 Cork County Gortnaclohy, Skibbereen, Co. Cork 34 *N/A the scheme is fully TURNKEY approved.

24/05/2021 24/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 337 Cork County Castle Heights, 3 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Cluain Cairn, Station Road, 338 Cork County 7 *N/A Q4‐2019 TURNKEY Carrigtwohill

SHIP CONSTRUCTION The Court, Ard Cashel, 339 Cork County 4 *N/A Q4‐2019 TURNKEY Watergrasshill

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 340 Cork County Kilmoney, Carrigaline 58 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 341 Cork County Millview Road, Kanturk ‐ Phase 2 10 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 342 Cork County Glenbeg, The Beeches, Boherbue 8 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 343 Cork County Oliver Plunkett Place, Doneraile 3 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 344 Cork County Crann Ard, Fermoy ‐ Phase 2 40 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 345 Cork County Inis Fáil, Curraclough, Bandon 17 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 346 Cork County Caherdaniel, Bantry 10 *N/A Q1‐2020 TURNKEY

SHIP CONSTRUCTION 347 Cork County St. Mary’s Road, Dunmanway 7 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Cluain Cairn, Station Road 348 Cork County 7 *N/A Q4‐2020 TURNKEY Carrigtwohill

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION An Goritin Rua, Millstreet Road, 349 Cork County 14 *N/A the scheme is fully TURNKEY Macroom approved.

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 350 Cork County King St, 2 *N/A the scheme is fully TURNKEY approved.

24/05/2021 25/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 351 Cork County Lyraneag, , 2 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 352 Cork County Cluain Reidh, 1 *N/A Q4‐2019 TURNKEY

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 353 Cork County Curragh, Upper 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 354 Cork County Glebe Manor, Whitegate 12 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 355 Cork County , 6 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 356 Cork County Kilmorna, Mallow 1 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 357 Cork County Lios Ard Ballhooly 6 *N/A Q1‐2021 TURNKEY

SHIP CONSTRUCTION 358 Cork County Lios Ard Ballhooly 6 *N/A Q1‐2021 TURNKEY

SHIP CONSTRUCTION 359 Cork County Spa Glen,Ballyviniter, Mallow 20 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 360 Cork County Spa Glen,Ballyviniter, Mallow 18 *N/A Q1‐2019 TURNKEY

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 361 Cork County Fana Na gCann, Co. Cork 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Drakes Point, Knocknagore, 362 Cork County 5 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 363 Cork County Scarteen, Newmarket, Co. Cork 11 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 364 Cork County Abbeyfort, 14 *N/A Q4‐2020 TURNKEY

24/05/2021 26/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 365 Cork County Caherdaniel, Bantry 6 *N/A Q1‐2020 TURNKEY

SHIP CONSTRUCTION 366 Cork County Caherdaniel, Bantry 18 *N/A Q1‐2020 TURNKEY

SHIP CONSTRUCTION 367 Cork County Abbeyfort, Kinsale 19 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 368 Cork County Oliver Plunkett Place, Doneraile 1 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 369 Cork County Spa Glen,Ballyviniter,Mallow 8 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION Clarendon Brooks, Carrs Hill, 370 Cork County 4 *N/A Q1‐2021 TURNKEY Douglas Phase 3

SHIP CONSTRUCTION SINGLE 371 Cork County Model Village, 6 *N/A Q4‐2020 STAGE

SHIP CONSTRUCTION SINGLE 372 Cork County Castletreasure Grove, Douglas 2 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE Seaview Cottages, Derrymihan, 373 Cork County 3 *N/A Q4‐2020 STAGE Castletownbere

SHIP CONSTRUCTION SINGLE 374 Cork County Curraleigh, Inniscarra 1 *N/A Q3‐2019 STAGE

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION SINGLE 375 Cork County Main St. Dunmanway 1 *N/A the scheme is fully STAGE approved.

SHIP CONSTRUCTION SINGLE 376 Cork County Thomas Kent Street, Cobh 1 *N/A Q4‐2020 STAGE

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION SINGLE Croke Place, Garranmacgarrett, 377 Cork County 2 *N/A the scheme is fully STAGE Kilbrin, kanturk approved.

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION SINGLE 22 Aisling Ghael, Coolacoosane, 378 Cork County 1 *N/A the scheme is fully STAGE Millview Road, Kanturk approved.

24/05/2021 27/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION SINGLE 379 Cork County Mullaghroe South, Cullen 2 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE 380 Cork County 3 Knockbrogan Park, Bandon 1 *N/A the scheme is fully STAGE approved.

381 SHIP CONSTRUCTION Cork County Downeen Cross, 7 *N/A Q4‐2019

Stage 3 approved Q3‐2020, the scheme is now 382 SHIP CONSTRUCTION Cork County Ard Na Greine, Cortmacsherry 17 *N/A approved to proceed to tender.

383 SHIP CONSTRUCTION Cork County Station Road, Blarney 18 *N/A Q4‐2020

384 SHIP CONSTRUCTION Cork County Bluepool, Kanturk 12 *N/A Q4‐2020

Tower View/Cúirt na Silíní, , 385 SHIP CONSTRUCTION Cork County 7 *N/A Q3‐2019 East Cork Phase 1

386 SHIP CONSTRUCTION Cork County Beechgrove, 57 *N/A Q3‐2019

387 SHIP CONSTRUCTION Cork County House , Bantry 1 *N/A Q3‐2020

388 SHIP CONSTRUCTION Cork County Fairfield, Masseytown, Macroom 7 *N/A Q4‐2018

389 SHIP CONSTRUCTION Cork County 12 & 14 Droum, Castletownbere 2 *N/A Q4‐2018

Stage 4 approved Q1‐2020, 390 SHIP CONSTRUCTION Cork County Kilnagleary, Carrigaline (Phase 4) 15 *N/A the scheme is fully approved.

391 SHIP CONSTRUCTION Cork County Oliver Plunkett Hill, Fermoy 10 *N/A Q2‐2017

392 SHIP CONSTRUCTION Cork County Townsend Street, Skibbereen 6 *N/A Q3‐2019

24/05/2021 28/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

393 SHIP CONSTRUCTION Cork County Forest View, Mallow 10 *N/A Q4‐2020

394 SHIP CONSTRUCTION Cork County 11/10 Harbour Hill, Cobh 1 *N/A Q2‐2018

395 SHIP CONSTRUCTION Cork County Kilnagleary Carrigaline 10 *N/A Q4‐2018

Kilnagleary Carrigaline (Phase 1A 396 SHIP CONSTRUCTION Cork County 16 *N/A Q1‐2019 & 1B (ii))

397 SHIP CONSTRUCTION Cork County Kilnagleary Carrigaline (Phase 1C) 18 *N/A Q1‐2019

398 SHIP CONSTRUCTION Cork County Kearney's field Dunmanway 5 *N/A Q3‐2020

Stage 2 approved Q1‐2020, 399 SHIP CONSTRUCTION Cork County Richmond Court, Bandon 6 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2018, 400 SHIP CONSTRUCTION Cork County Brigown Road, Mitchelstown 8 *N/A full design/tender being prepared.

Stage 4 approved Q4‐2020, 401 SHIP CONSTRUCTION Cork County Sleaveen East, Macroom 8 *N/A the scheme is fully approved.

402 SHIP CONSTRUCTION Cork County Kilnagleary, Carrigaline Phase 1B 5 *N/A Q4‐2018

403 SHIP CONSTRUCTION Cork County Tudor Grove, Ballincollig 16 *N/A Q4‐2019

Stage 4 approved Q4‐2020, 404 SHIP CONSTRUCTION Cork County Pound Lane, 7 *N/A the scheme is fully approved.

Stage 1 approved Q2‐2019, 405 SHIP CONSTRUCTION Cork County 24 Glenview Terrace Lyre Co Cork 1 *N/A outline design and costs being prepared.

Stage 2 approved Q1‐2020, Broomfield West, Avoncore, 406 SHIP CONSTRUCTION Cork County 10 *N/A full design/tender being Midelton prepared.

24/05/2021 29/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q1‐2021, 407 SHIP CONSTRUCTION Cork County Knocknagown, Rylane 1 *N/A the scheme is fully approved.

Stage 2 approved Q3‐2019, Uplands (Phase 2), College Road, 408 SHIP CONSTRUCTION Cork County 11 *N/A full design/tender being Fermoy prepared.

409 SHIP CONSTRUCTION Cork County Lissoran, 4 *N/A Q4‐2020

Tower View/Cúirt na Silíní, Cloyne, 410 SHIP CONSTRUCTION Cork County 2 *N/A Q3‐2018 East Cork ‐ Phase 2

Stage 3 approved Q1‐2021, the scheme is now 411 SHIP CONSTRUCTION Cork County Convent Road, Doneraile 17 *N/A approved to proceed to tender.

412 SHIP CONSTRUCTION Cork County Kearney's field Dunmanway 13 *N/A Q3‐2020

Stage 1 approved Q2‐2020, St. Gobnaits, Ballyvourney, Co. 413 SHIP CONSTRUCTION Cork County 20 *N/A outline design and costs Cork being prepared.

Stage 1 approved Q4‐2020, 414 SHIP CONSTRUCTION Cork County Mill Road, Kanturk, Co. Cork 9 *N/A outline design and costs being prepared.

Stage 1 approved Q4‐2020, 415 SHIP CONSTRUCTION Cork County Chapel Lane, , Co. Cork 13 *N/A outline design and costs being prepared.

Stage 1 approved Q1‐2021, 416 SHIP CONSTRUCTION Cork County Uplands (Phase 1) Fermoy 31 *N/A outline design and costs being prepared.

Stage 4 approved Q1‐2020, Túath Housing Association 417 CAS CONSTRUCTION TURNKEY Cork County Ardmanagh, 12 the scheme is fully Ltd approved.

Stage 4 approved Q1‐2020, CAS CONSTRUCTION SINGLE 418 Cork County Bayview Seskin Bantry Co. Cork 1 *N/A the scheme is fully STAGE approved.

Sisters of Mercy Church and 419 CAS CONSTRUCTION Cork County Convent at Knocknamuck, Bantry 16 Cluid Housing Association Q1‐2021 Bay

Coiste Tithe Uibh Laoire 420 CAS CONSTRUCTION Cork County Cuan Barra, Kilmore, 3 Q3‐2018 Teoranta

24/05/2021 30/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Rosscarbery Housing 421 CAS CONSTRUCTION Cork County Caim Hill, , Rosscarbery 9 Q1‐2019 Association Ltd

Bandon Geriatric & 422 CAS CONSTRUCTION Cork County Avenue House, Bandon 9 Q1‐2018 Community Council

Church View, Love Lane, Charleville Care Project 423 CAS CONSTRUCTION Cork County 4 Q4‐2019 Charleville Ltd

Tabor Lodge Addiction & 424 CAS CONSTRUCTION Cork County Fellowship House, Togher 31 Q2‐2018 Housing Services Ltd

Stage 1 approved Q1‐2019, Care Home Facility, Masseytown, Túath Housing Association 425 CAS CONSTRUCTION Cork County 1 outline design and costs Macroom Ltd being prepared.

Stage 4 approved Q2‐2020, 426 CAS CONSTRUCTION Cork County Baile Bhuire, Macroom 3 *N/A the scheme is fully approved.

Charleville, Church View, Love Charleville Care Project 427 CAS CONSTRUCTION Cork County 9 Q4‐2020 Lane, Charleville Ltd

Stage 1 approved Q3‐2019, St. Michaels, 36 Main Street, Bandon Geriatric & 428 CAS CONSTRUCTION Cork County 6 outline design and costs Bandon, Co. Cork Community Council being prepared.

Distillery Lane, Distillery Walk, 429 CAS CONSTRUCTION Cork County 7 *N/A Q1‐2021 Midleton

430 CAS CONSTRUCTION Cork County Mardyke, Skibbereen 4 *N/A Q1‐2021

Stage 1 approved Q2‐2020, Lisheen Field, Kilbarry Road, 431 CAS CONSTRUCTION Cork County 16 Cluid Housing Association outline design and costs Dunmanway, Co. Cork being prepared.

21 units, Brookhill, Carrigaline, Co ‐ Operative Housing 432 CALF Turnkey Cork County 21 Q4‐2020 Cork (Phase 1) Ireland Society Limited

3 units, Mullavale, 433 CALF Turnkey Cork County , Co. Cork (Phase 3 Respond Q2‐2019 1)

Beach Road, , Co. 434 CALF Turnkey Cork County 3 Cluid Housing Q4‐2017 Cork (Phase 1)

24/05/2021 31/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Brookhill (5 Units), Carrigaline, Co ‐ Operative Housing 435 CALF Turnkey Cork County 5 Q4‐2019 Cork (Phase 1) Ireland Society Limited

Brookhill, Carrigaline, Co. Cork Co ‐ Operative Housing 436 CALF Turnkey Cork County 4 Q3‐2020 (Phase 1) Ireland Society Limited

Brookhill, Carrigaline, Co. Cork Co ‐ Operative Housing 437 CALF Turnkey Cork County 31 Q2‐2020 (Phase 1)* Ireland Society Limited

Brookhill, Carrigaline, Co. Cork Co ‐ Operative Housing 438 CALF Turnkey Cork County 8 Q3‐2020 (Phase 2) Ireland Society Limited

Cascade Apartments, Castlelake, Co ‐ Operative Housing 439 CALF Turnkey Cork County 95 Q4‐2020 Carrigtwohill, Cork (Phase 1) Ireland Society Limited

Chapel Court, Skibbereen, Cork 440 CALF Turnkey Cork County 8 Cluid Housing Q1‐2021 (Phase 1)

Chapel Court, Skibbereen, Cork 441 CALF Turnkey Cork County 8 Cluid Housing Q1‐2021 (Phase 2)

Cluain Reidh, , Co. 442 CALF Turnkey Cork County 10 Cluid Housing Q3‐2020 Cork (Phase 1)

443 CALF Turnkey Cork County College Manor, Cobh (Phase 1) 10 Túath Housing Association Q4‐2016

Coolroe, Ballincollig, Co. Cork 444 CALF Turnkey Cork County 24 Respond Q4‐2020 (Phase 1)*

Coolroe, Ballincollig, Co. Cork 445 CALF Turnkey Cork County 20 Respond Q1‐2021 (Phase 2)

Duntahane, Fermoy, Co. Cork 446 CALF Construction Cork County 46 Respond Q4‐2020 (Phase 1)

Co ‐ Operative Housing 447 CALF Construction Cork County Firgrove Harrisons lane (Phase 1) 6 Q4‐2017 Ireland Society Limited

Market Green, Knockgriffin, 448 CALF Turnkey Cork County 20 Respond Q4‐2019 Midleton, Co. Cork (Phase 1)

24/05/2021 32/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Market Green, Knockgriffin, 449 CALF Turnkey Cork County 22 Respond Q4‐2020 Midleton, Co. Cork (Phase 2)*

Mullavale, Castletownroche, Co. 450 CALF Turnkey Cork County 6 Respond Q4‐2018 Cork (Phase 1)

Post Tender ‐ Radharc An tSaile, 451 CALF Construction Cork County Cappagh, Ballynacubby, Kinsale, 40 Cluid Housing Q3‐2020 Co Cork (Phase 1)

Radharc Na Tuaithe, , Focus Housing Association 452 CALF Turnkey Cork County 7 Q3‐2020 Cork (Phase 1)* CLG

Sunville, Church Road, Carrigaline, Focus Housing Association 453 CALF Turnkey Cork County 6 Q4‐2020 Co. Cork (Phase 1) CLG

Tanners Field, Bandon, Co Cork 454 CALF Turnkey Cork County 11 Túath Housing Association Q3‐2019 (Phase 1)

455 CALF Turnkey Cork County Ticknock, Cobh, Cork (Phase 1) 8 Respond Q4‐2018

Togher Cross, Lehenaghmore, Co. 456 CALF Turnkey Cork County 9 Cluid Housing Q4‐2019 Cork (Phase 1)

Weston, Carrigaline, Co. Cork 457 CALF Turnkey Cork County 7 Respond Q2‐2018 (Phase 1)

PUBLIC PRIVATE PARTNERSHIP 458 Cork County The Miles, Clonakilty 52 *N/A Q4‐2019 (Bundle 2)

PUBLIC PRIVATE PARTNERSHIP 459 Cork County Poundhill, Skibbereen 50 *N/A Q4‐2019 (Bundle 2)

PUBLIC PRIVATE PARTNERSHIP 460 Cork County Oakwood, Macroom 50 *N/A Q4‐2019 (Bundle 2)

SHIP CONSTRUCTION Hazelbrook, Nutgrove, 461 DLR 28 *N/A Q4‐2017 TURNKEY Churchtown

SHIP CONSTRUCTION 462 DLR Dunedin Terrace, Monkstown 14 *N/A Q4‐2018 TURNKEY

24/05/2021 33/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 463 DLR Close 22 *N/A Q1‐2021 TURNKEY

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 464 DLR Kilternan Close 33 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION George's Street Upper, Dun 465 DLR 5 *N/A Q1‐2021 TURNKEY Laoghaire

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION Rosemount View, Dundrum, 466 DLR 8 *N/A the scheme is fully TURNKEY Dublin 14 approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 16 Greygates, , Co. 467 DLR 3 *N/A the scheme is fully TURNKEY Dublin: approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION RAPID Rockville Green (Glenamuck 468 DLR 13 *N/A the scheme is fully VOLUMETRIC Cottages) approved.

SHIP CONSTRUCTION RAPID 469 DLR George's Place 12 *N/A Q2‐2018 VOLUMETRIC

Stage 3 approved Q1‐2021, SHIP CONSTRUCTION RAPID the scheme is now 470 DLR Court, Ballyogan 67 *N/A VOLUMETRIC approved to proceed to tender. Stage 3 approved Q3‐2020, Park House, 66 George's Street, the scheme is now 471 SHIP CONSTRUCTION DLR 4 *N/A Dun Laoghaire approved to proceed to tender.

472 SHIP CONSTRUCTION DLR 132 Pottery Road, Dun Laoghaire 4 *N/A Q3‐2018

473 SHIP CONSTRUCTION DLR Temple Road 3 *N/A Q2‐2018

474 SHIP CONSTRUCTION DLR Assistant Harbour Master House 2 *N/A Q3‐2017

The Brambles Park Close 475 SHIP CONSTRUCTION DLR 10 *N/A Q2‐2018

476 SHIP CONSTRUCTION DLR 49 The Mews Sallynoggin Park 4 *N/A Q4‐2017

24/05/2021 34/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

477 SHIP CONSTRUCTION DLR Shanganagh Park Lodge 1 *N/A Q2‐2016

478 SHIP CONSTRUCTION DLR Rosemount Court 44 *N/A Q4‐2018

479 SHIP CONSTRUCTION DLR Broadford Rise 21 *N/A Q3‐2017

480 SHIP CONSTRUCTION DLR Fitzgerald Park 33 *N/A Q4‐2018

481 SHIP CONSTRUCTION DLR Rochestown House (Phase 3) 14 *N/A Q3‐2018

482 SHIP CONSTRUCTION DLR St Michael's Terrace 4 *N/A Q3‐2017

483 SHIP CONSTRUCTION DLR Clontibret House 4 *N/A Q4‐2016

484 SHIP CONSTRUCTION DLR Cromlech Close 15 *N/A Q3‐2016

485 SHIP CONSTRUCTION DLR Rochestown House (Phase 2) 34 *N/A Q3‐2016

486 SHIP CONSTRUCTION DLR Ballyogan Avenue, Ballyogan 2 *N/A Q1‐2020

Stage 2 approved Q2‐2020, 487 SHIP CONSTRUCTION DLR St. Laurence’s Park, 89 *N/A full design/tender being prepared.

488 SHIP CONSTRUCTION DLR Fitzgerald Park 17 *N/A Q1‐2019

Stage 2 approved Q2‐2020, Moyola Court, Churchtown Lower, 489 SHIP CONSTRUCTION DLR 4 *N/A full design/tender being Dublin 14 prepared.

Stage 2 approved Q4‐2020, 490 SHIP CONSTRUCTION DLR Shanganagh Castle 200 *N/A full design/tender being prepared.

24/05/2021 35/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q3‐2020, Site at Roebuck Road, , 491 SHIP CONSTRUCTION DLR 3 *N/A outline design and costs Dublin 14 being prepared.

Stage 2 approved Q1‐2021, 37A Rollins Villas, Sallynoggin, Co. 492 SHIP CONSTRUCTION DLR 1 *N/A full design/tender being Dublin prepared.

Stage 1 approved Q3‐2020, Old Coastguard Cottages, Coal 493 SHIP CONSTRUCTION DLR 4 *N/A outline design and costs Harbour, Harbour Road being prepared.

Stage 4 approved Q4‐2019, St. John of God Housing 494 CAS CONSTRUCTION DLR 30 Obelisk Walk, Blackrock 4 the scheme is fully Association Ltd approved.

Abbeyview House, Monkstown, 495 CALF Construction DLR 11 Cluid Housing Q4‐2020 Dublin (Phase 1)

Ardilea Crescent, Clonskeagh, 496 CALF Turnkey DLR 8 Túath Housing Association Q4‐2018 Dublin 14 (Phase 1)*

Ballybetagh Road, Kilternan, Co Clanmil Housing 497 CALF Turnkey DLR 22 Q1‐2021 Dublin (Phase 1)* Association Ireland

Belarmine Drive, Belarmine, 498 CALF Turnkey DLR 6 Cluid Housing Q4‐2019 Stepaside, Dublin 18 (Phase 1)*

Bishops Gate, Enniskerry Rd., 499 CALF Turnkey DLR 4 Cluid Housing Q4‐2019 Dublin 18 (Phase 1)*

Bishops Gate, Kilternan, Dublin 18 500 CALF Turnkey DLR 4 Cluid Housing Q3‐2018 (Phase 1)*

Bishops Gate, Kilternan, Dublin 18 501 CALF Turnkey DLR 2 Cluid Housing Q3‐2018 (Phase 2)*

Block C, Abbey Road, Monkstown, Fold Housing Association 502 CALF Turnkey DLR 3 Q4‐2018 (Phase 1)* Ireland Ltd

Clay Farm (Block E3), Ballyogan 503 CALF Turnkey DLR Road, , Dublin 18 24 The Iveagh Trust Q4‐2019 (Phase 1)*

Clays Farm, Ballyogan Road 504 CALF Turnkey DLR 44 The Iveagh Trust Q2‐2019 (Phase 1) (Phase 1)*

24/05/2021 36/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Enniskerry Road, , 505 CALF Construction DLR 9 Respond Q3‐2019 Dublin 18 (Phase 1)

Enniskerry Road, Sandyford, 506 CALF Construction DLR 44 Respond Q3‐2019 Dublin 18 (Phase 2)

Enniskerry Road, Sandyford, 507 CALF Construction DLR 18 Túath Housing Association Q3‐2019 Dublin 19, (Phase 1)

Enniskerry Road, Sandyford, 508 CALF Construction DLR 34 Túath Housing Association Q3‐2019 Dublin 19, (Phase 2)

Eustace Court, Upper St John of God Housing 509 CALF Turnkey DLR Road, Dun Laoghaire, Rathdown, 4 Q4‐2019 Association Ltd Co. Dublin (Phase 1)

Garrison Mews, The Ramparts, Focus Housing Association 510 CALF Turnkey DLR 5 Q4‐2020 , Co. Dublin (Phase 1)* CLG

Greenbank House, Upper St John of God Housing 511 CALF Turnkey DLR Glenageary Road, Dun Laoghaire, 1 Q4‐2018 Association Ltd Co. Dublin (Phase 1)

Hyde Road, Belmont, Stepaside, 512 CALF Turnkey DLR 8 Respond Q4‐2018 Co. Dublin (Phase 1)*

Johnstown Court, Cabinteely, 513 CALF Turnkey DLR 51 Cluid Housing Q2‐2019 Dublin 18 (Phase 1)*

Johnstown Court, Cabinteely, 514 CALF Turnkey DLR 50 Cluid Housing Q2‐2019 Dublin 18 (Phase 2)*

Knockrabo, Mount Anville Road, 515 CALF Turnkey DLR 6 Oaklee Housing Q4‐2020 , Dublin 14 (Phase 1)*

Loughlinstown View(formerly Co ‐ Operative Housing 516 CALF Construction DLR Cromlech Fields) , 34 Q1‐2019 Ireland Society Limited , Dublin (Phase 1)

Marine Walk, Marine Road, Dun 517 CALF Turnkey DLR 2 Oaklee Housing Q4‐2020 Laoghaire (Phase 1)*

Mount Eagle, Kilgobbin Road, 518 CALF Turnkey DLR 14 Túath Housing Association Q1‐2021 Sandyford, Dublin 18 (Phase 1)*

24/05/2021 37/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Mount Eagle, Kilgobbin Road, 519 CALF Turnkey DLR 18 Túath Housing Association Q4‐2019 Sandyford, Dublin 18 (Phase 2)*

Our Ladys Grove, Goatstown, 520 CALF Turnkey DLR 2 Respond Q4‐2018 Dublin 14 (Phase 1)*

Rockville Hall, Glenamuck Road, Co ‐ Operative Housing 521 CALF Turnkey DLR Dunlaoghaire, Dublin 18 (Phase 12 Q3‐2020 Ireland Society Limited 1)*

Stillorgan Gate, Road 522 CALF Turnkey DLR 4 Cluid Housing Q4‐2017 Upper, Co Dublin (Phase 1)*

Stillorgan Gate, Kilmacud Road 523 CALF Turnkey DLR Upper, Stillorgan, Co. Dublin 2 Cluid Housing Q4‐2018 (Phase 1)*

The Avenue, Glenside, Fold Housing Association 524 CALF Turnkey DLR Green, Dublin 18 5 Q4‐2018 Ireland Ltd (Phase 1)*

The Glen, Glenamuck Road, 525 CALF Turnkey DLR Carrickmines, Dublin 18 (Phase 48 Respond Q1‐2021 1)*

Whinsfield, Sandyford Road, 526 CALF Turnkey DLR 59 Respond Q3‐2020 Dublin 18 (Phase 1)

Whinsfield, Sandyford Road, 527 CALF Turnkey DLR 6 Respond Q3‐2020 Dublin 18 (Phase 1)*

Woodbank, Dublin Rd, Shankill, Co 528 CALF Turnkey DLR 4 Cluid Housing Q3‐2017 Dublin (Phase 1)*

Stage 4 approved Q3‐2019, 529 SHIP DIALOG Donegal Drumrooske West 36 *N/A the scheme is fully approved.

530 SHIP DIALOG Donegal Convent Road, Carndonagh 53 *N/A Q1‐2021

531 SHIP DIALOG Donegal Convoy 24 *N/A Q4‐2020

532 SHIP DIALOG Donegal Donegal Road, Ballybofey 14 *N/A Q1‐2021

24/05/2021 38/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

533 SHIP DIALOG Donegal Admiran, Stranorlar 52 *N/A Q1‐2021

534 SHIP DIALOG Donegal Rockview, Carrickboy 5 *N/A Q1‐2021

535 SHIP DIALOG Donegal Ardaravan, Buncrana 4 *N/A Q4‐2020

Stage 2 approved Q2‐2020, 536 SHIP DIALOG Donegal Glencrow, Moville 35 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2020, 537 SHIP DIALOG Donegal Ballyraine, 25 *N/A full design/tender being prepared.

538 SHIP DIALOG Donegal Lough Fern Heights, Milford 17 *N/A Q1‐2021

SHIP CONSTRUCTION Gleann Na Greine, Mullindrait, 539 Donegal 21 *N/A Q2‐2018 TURNKEY Stranorlar

SHIP CONSTRUCTION 540 Donegal Crievesmith, Letterkenny 18 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 541 Donegal Radharc an Chuain, Ramelton 18 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION Crievesmith, Letterkenny (Phase 542 Donegal 8 *N/A Q1‐2019 TURNKEY 2)

SHIP CONSTRUCTION 543 Donegal Carnamuggagh, Letterkenny 30 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 544 Donegal Heathhill, Newtowncunningham 10 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Crievesmith, Letterkenny (Phase 545 Donegal 10 *N/A Q2‐2019 TURNKEY 3)

SHIP CONSTRUCTION 546 Donegal Brookfield, Donegal Town 34 *N/A Q4‐2020 TURNKEY

24/05/2021 39/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Stáisiún an Chúirt, Falcarragh 547 Donegal 6 *N/A Q4‐2019 TURNKEY (Phase 1)

SHIP CONSTRUCTION Staisiún An Chúirt, Falcarragh 548 Donegal 6 *N/A Q4‐2020 TURNKEY (Phase 2)

SHIP CONSTRUCTION 549 Donegal Heathhill, Newtowncunningham 7 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION SINGLE 550 Donegal Figart, Dunfanaghy 8 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 551 Donegal SRD Loughanure Annagry 1 *N/A Q1‐2021 STAGE

SHIP CONSTRUCTION SINGLE 552 Donegal SRD Meenderrynasloe, Annagry 1 *N/A Q1‐2021 STAGE

553 SHIP CONSTRUCTION Donegal Meadow Hill, Raphoe 11 *N/A Q3‐2020

Radharc na Tra Breige, Malin 554 SHIP CONSTRUCTION Donegal 8 *N/A Q4‐2019 (Phase 3)

Cois Abhainn, St Johnston (Phase 555 SHIP CONSTRUCTION Donegal 6 *N/A Q4‐2020 2)

556 SHIP CONSTRUCTION Donegal Emerald Drive, Killybegs (Phase 6) 9 *N/A Q4‐2019

557 SHIP CONSTRUCTION Donegal Long Lane, Letterkenny 29 *N/A Q3‐2019

558 SHIP CONSTRUCTION Donegal Rockytown, Buncrana (Phase 1) 21 *N/A Q4‐2019

559 SHIP CONSTRUCTION Donegal Manorcunningham (Phase 2) 8 *N/A Q4‐2018

560 SHIP CONSTRUCTION Donegal Abbots Wood, Carndonagh (Ph 2) 4 *N/A Q4‐2018

24/05/2021 40/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

561 SHIP CONSTRUCTION Donegal Pound Street, Dunfanaghy 4 *N/A Q3‐2020

562 SHIP CONSTRUCTION Donegal Ardara (Phase 3) 8 *N/A Q2‐2017

563 SHIP CONSTRUCTION Donegal Newtoncunningham 7 *N/A Q4‐2018

Railway Park, Drumrooske, 564 SHIP CONSTRUCTION Donegal 24 *N/A Q3‐2019 Donegal Town

565 SHIP CONSTRUCTION Donegal Ard Connell, Ardara (SRD) 1 *N/A Q1‐2017

566 SHIP CONSTRUCTION Donegal Manorcunningham (Phase 1) 2 *N/A Q2‐2017

Stage 2 approved Q1‐2020, Railway Park, Drumrooske, 567 SHIP CONSTRUCTION Donegal 24 *N/A full design/tender being Donegal Town prepared.

Stage 4 approved Q1‐2021, 568 SHIP CONSTRUCTION Donegal Trusk Road, Ballybofey 19 *N/A the scheme is fully approved.

Stage 2 approved Q3‐2020, 569 SHIP CONSTRUCTION Donegal Crana Crescent, Buncrana 16 *N/A full design/tender being prepared.

Stage 3 approved Q1‐2021, the scheme is now 570 SHIP CONSTRUCTION Donegal Drumacrin, Bundoran 42 *N/A approved to proceed to tender. Stage 3 approved Q4‐2020, the scheme is now 571 SHIP CONSTRUCTION Donegal Gallow's Lane, Lifford 29 *N/A approved to proceed to tender.

572 CAS CONSTRUCTION TURNKEY Donegal Ballaghderg, Letterkenny 14 Respond Q4‐2020

Glenrowan House, Drumkeen, 573 CAS CONSTRUCTION Donegal 5 Apex Housing Association Q4‐2020 Stranorlar

County Donegal Parents 574 CAS CONSTRUCTION Donegal Cois Locha, Meenmore, Dungloe 15 and Friends Housing Q3‐2020 Association Ltd

24/05/2021 41/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Railway Park, Drumrooske, 575 CAS CONSTRUCTION Donegal 10 Oaklee Housing Trust Q4‐2020 Donegal Town

Dunshenny House, Derry Road, 576 CAS CONSTRUCTION Donegal 5 Apex Housing Association Q2‐2018 Carndonagh

Stage 2 approved Q3‐2020, Habinteg Housing 577 CAS CONSTRUCTION Donegal Raphoe Road, Castlefinn 34 full design/tender being Association (Ireland) Ltd prepared.

Ballaghderg, Letterkenny, Co 578 CALF Turnkey Donegal 33 Respond Q1‐2021 Donegal (Phase 1)*

Cnoc Moineir, Ardarawer, 579 CALF Turnkey Donegal Letterkenny, Co. Donegal (Phase 46 Cluid Housing Q2‐2018 1)*

580 CALF Turnkey Donegal Forge Road, Donegal (Phase 1) 4 Cluid Housing Q3‐2016

Post Tender ‐ Ernedale 581 CALF Construction Donegal 11 Cluid Housing Q4‐2018 Ballyshannon (Phase 1)

SHIP CONSTRUCTION 582 Dublin City Prospect Hill 58 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 583 Dublin City Parkside, , Dublin 13 16 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 584 Dublin City Hampton Wood, 47 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 585 Dublin City Hampton Wood, Finglas 45 *N/A Q4‐2019 TURNKEY

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 586 Dublin City 88‐89 Road Dublin 12 24 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION St. Pancras, Harolds Cross, Dublin 587 Dublin City 4 *N/A the scheme is fully TURNKEY 6 approved.

Stage 2 approved Q3‐2020, SHIP CONSTRUCTION RAPID 588 Dublin City Belcamp B, Dublin 17 12 *N/A full design/tender being VOLUMETRIC prepared.

24/05/2021 42/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION RAPID 589 Dublin City Bunratty Road 78 *N/A Q4‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 590 Dublin City Bonham Street Dublin 8 57 *N/A Q4‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID Cork Street/Chamber Street 591 Dublin City 55 *N/A Q1‐2020 VOLUMETRIC Dublin 8

SHIP CONSTRUCTION RAPID 592 Dublin City Springvale Dublin 8 71 *N/A Q1‐2020 VOLUMETRIC

Stage 1 approved Q1‐2021, SHIP CONSTRUCTION RAPID Cromcastle & Woodville, , 593 Dublin City 156 *N/A outline design and costs VOLUMETRIC Dublin 5 being prepared.

Stage 1 approved Q4‐2020, SHIP CONSTRUCTION RAPID Crumlin Road ‐ Rafters Lane, 594 Dublin City 47 *N/A outline design and costs VOLUMETRIC Dublin 12 being prepared.

Stage 1 approved Q4‐2020, SHIP CONSTRUCTION RAPID 595 Dublin City St. Andrews Court, Dublin 2 37 *N/A outline design and costs VOLUMETRIC being prepared.

SHIP CONSTRUCTION RAPID 596 Dublin City Belcamp H, Dublin 17 38 *N/A Q4‐2017 VOLUMETRIC

SHIP CONSTRUCTION RAPID 597 Dublin City Cherry Orchard, 24 *N/A Q4‐2017 VOLUMETRIC

SHIP CONSTRUCTION RAPID 598 Dublin City Mourne Road, Drimnagh 29 *N/A Q4‐2017 VOLUMETRIC

SHIP CONSTRUCTION RAPID 599 Dublin City St Helena's Drive, Finglas 39 *N/A Q3‐2017 VOLUMETRIC

SHIP CONSTRUCTION RAPID 600 Dublin City , 22 *N/A Q2‐2016 VOLUMETRIC

SHIP CONSTRUCTION RAPID Rapids at Ballyfermot, Rathvilly, 601 Dublin City 53 *N/A Q4‐2018 VOLUMETRIC Woodbank Drive

SHIP CONSTRUCTION RAPID Rapids at Ballyfermot, Rathvilly, 602 Dublin City 13 *N/A Q3‐2018 VOLUMETRIC Woodbank Drive

24/05/2021 43/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION RAPID Rapids at Ballyfermot, Rathvilly, 603 Dublin City 3 *N/A Q3‐2018 VOLUMETRIC Woodbank Drive

SHIP CONSTRUCTION RAPID Rapids at Ballyfermot, Rathvilly, 604 Dublin City 19 *N/A Q4‐2019 VOLUMETRIC Woodbank Drive

605 SHIP CONSTRUCTION Dublin City Hampton Wood 25 *N/A Q4‐2016

Cornamona, Ballyfermot, Dublin 606 SHIP CONSTRUCTION Dublin City 61 *N/A Q2‐2019 12

Stage 2 approved Q2‐2019, 607 SHIP CONSTRUCTION Dublin City Infirmary Road, Dublin 7 38 *N/A full design/tender being prepared.

North King Street, ‐ Sean Foster 608 SHIP CONSTRUCTION Dublin City 30 *N/A Q2‐2019 Place, Dublin 7

Stage 2 approved Q2‐2020, St. Finbar's Court, Kilkieran Road, 609 SHIP CONSTRUCTION Dublin City 46 *N/A full design/tender being Dublin 7 prepared.

610 SHIP CONSTRUCTION Dublin City Dominick Street (East side) 72 *N/A Q1‐2018

Stage 3 approved Q3‐2019, the scheme is now 611 SHIP CONSTRUCTION Dublin City Sackville Avenue Cottages 11 *N/A approved to proceed to tender.

612 SHIP CONSTRUCTION Dublin City O'Devaney Gardens ‐ Phase 1A 56 *N/A Q3‐2018

613 REGENERATION Dublin City Maxwell Road 9 *N/A Q2‐2016

614 REGENERATION Dublin City Buttercup, 19 *N/A Q4‐2017

615 REGENERATION Dublin City Buttercup, Darndale 9 *N/A Q1‐2018

616 REGENERATION Dublin City Buttercup, Darndale 7 *N/A Q2‐2018

24/05/2021 44/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

617 SHIP CONSTRUCTION Dublin City Priory Hall 9 *N/A Q1‐2017

618 SHIP CONSTRUCTION Dublin City Priory Hall 24 *N/A Q4‐2019

Stage 2 approved Q1‐2021, 619 SHIP CONSTRUCTION Dublin City Glin Court, Coolock, Dublin 17 32 *N/A full design/tender being prepared.

Stage 1 approved Q2‐2020, 620 SHIP CONSTRUCTION Dublin City Dorset Streeet, Dublin 7 115 *N/A outline design and costs being prepared.

Stage 1 approved Q3‐2020, 621 SHIP CONSTRUCTION Dublin City Matt Talbot Court 92 *N/A outline design and costs being prepared.

Stage 1 approved Q2‐2020, 622 SHIP CONSTRUCTION Dublin City Kildonan Road 75 *N/A outline design and costs being prepared.

Stage 1 approved Q2‐2020, 623 SHIP CONSTRUCTION Dublin City Lands at Emmet Road 109 *N/A outline design and costs being prepared.

Stage 1 approved Q1‐2021, Slademore Avenue, Ayrfield, 624 SHIP CONSTRUCTION Dublin City 39 *N/A outline design and costs Dublin 13 being prepared.

625 SHIP CONSTRUCTION Dublin City Road, Dublin 1 5 *N/A Q4‐2018

St Teresa's Gardens Margaret 626 REGENERATION Dublin City 54 *N/A Q4‐2020 Kennedy Road Project

627 REGENERATION Dublin City Dolphin House, Dublin 8 100 *N/A Q3‐2018

628 REGENERATION Dublin City Charlemont 79 *N/A Q4‐2017

629 SHIP CONSTRUCTION Dublin City Ballybough Road, Dublin 1 2 *N/A Q4‐2019

630 REGENERATION Dublin City St. Bricins Park 11 *N/A Q4‐2018

24/05/2021 45/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q2‐2020, 631 REGENERATION Dublin City Constitution Hill Dublin 7 130 *N/A outline design and costs being prepared.

Stage 4 approved Q3‐2020, Block 70, The Plaza, Parkwest, Túath Housing Association 632 CAS CONSTRUCTION TURNKEY Dublin City 43 the scheme is fully Dublin 12 Ltd approved.

Apartments 1‐3, 42 633 CAS CONSTRUCTION TURNKEY Dublin City 3 Peter McVerry Trust Ltd Q4‐2020 Road, Dublin 3

Túath Housing Association 634 CAS CONSTRUCTION TURNKEY Dublin City 5A & 5B Willow Park Crescent 2 Q3‐2020 Ltd

CAS CONSTRUCTION SINGLE 61 & 63 Rathoath Avenue, Finglas, Arlington Novas Ireland 635 Dublin City 6 Q4‐2020 STAGE Dublin 11 Ltd

Stage 4 approved Q3‐2019, CAS CONSTRUCTION SINGLE 13A Casement Drive / 307A Arlington Novas Ireland 636 Dublin City 4 the scheme is fully STAGE Casement Road, Finglas, Dublin 11 Ltd approved.

Stage 4 approved Q3‐2020, CAS CONSTRUCTION SINGLE 88 Lower Drumcondra Road, 637 Dublin City 6 Peter McVerry Trust Ltd the scheme is fully STAGE Dublin 9 approved.

Royal Hospital 638 CAS CONSTRUCTION Dublin City Beech Hill 19 Donnybrook Voluntary Q4‐2018 Housing Association Ltd

Túath Housing Association 639 CAS CONSTRUCTION Dublin City Ellis Court, Dublin 22 Q3‐2019 Ltd

Martanna House, High Park, Grace 640 CAS CONSTRUCTION Dublin City 8 Respond Q4‐2018 Park Road,Dublin 9

Walkinston Housing 641 CAS CONSTRUCTION Dublin City 1 ‐ 2 Rafter's Lane, Dublin 12 11 Q4‐2019 Association Ltd (WALK)

Stage 3 approved Q4‐2018, 180‐187 Townsend Street, Dublin the scheme is now 642 CAS CONSTRUCTION Dublin City 20 Peter McVerry Trust Ltd 2 approved to proceed to tender.

Stage 1 approved Q1‐2017, Arlington Novas Ireland 643 CAS CONSTRUCTION Dublin City Old Road, Dublin 811 outline design and costs Ltd being prepared.

644 CAS CONSTRUCTION Dublin City 26 New Street South, Dublin 8 8 Peter McVerry Trust Ltd Q1‐2021

24/05/2021 46/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Broome Lodge, Dunmanus, Dublin 645 CAS CONSTRUCTION Dublin City 10 Cluid Housing Association Q4‐2017 7

St Agatha's Court, North William 646 CAS CONSTRUCTION Dublin City 11 Peter McVerry Trust Ltd Q2‐2017 Street, Dublin 1

Stage 4 approved Q4‐2020, Simon Community : Dublin 647 CAS CONSTRUCTION Dublin City 55B Arbour Hill, Dublin 714 the scheme is fully Simon approved.

Stage 3 approved Q3‐2020, St. Michael's Estate, , Circle Voluntary Housing the scheme is now 648 CAS CONSTRUCTION Dublin City 52 Dublin 8 ‐ Housing Pilot Project Association Ltd approved to proceed to tender.

Stage 2 approved Q4‐2019, 649 CAS CONSTRUCTION Dublin City Shaw Street, Dublin 2 12 Peter McVerry Trust Ltd full design/tender being prepared.

Stage 1 approved Q1‐2020, Sarsfield Road, Ballyfermot, 650 CAS CONSTRUCTION Dublin City 6 Respond outline design and costs Dublin 10 being prepared.

Stage 1 approved Q4‐2020, 53a Keeper Road, Drimnagh, 651 CAS CONSTRUCTION Dublin City 9 Respond outline design and costs Dublin 12 being prepared.

Stage 2 approved Q1‐2021, Barnamore Grove, Finglas, Dublin Arlington Novas Ireland 652 CAS CONSTRUCTION Dublin City 2 full design/tender being 11 Ltd prepared.

Stage 2 approved Q1‐2021, Arlington Novas Ireland 653 CAS CONSTRUCTION Dublin City Berryfield Drive, Finglas, Dublin 11 6 full design/tender being Ltd prepared.

3 units, Block A Jamestown Court, 654 CALF Construction Dublin City 3 ALONE Q4‐2020 Dublin 8 (Phase 1)

9 units Dorset Street, Dublin 1 Clanmil Housing 655 CALF Turnkey Dublin City 9 Q4‐2020 (Phase 1) Association Ireland

An Riasc, Finglas, Phase 1,2,3 and 656 CALF Turnkey Dublin City 14 Túath Housing Association Q4‐2016 4 (Phase 1)

An Riasc, Finglas, Phase 1,2,3 and 657 CALF Turnkey Dublin City 21 Túath Housing Association Q1‐2017 4 (Phase 2)

An Riasc, Finglas, Phase 1,2,3 and 658 CALF Turnkey Dublin City 10 Túath Housing Association Q2‐2017 4 (Phase 3)

24/05/2021 47/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

An Riasc, Finglas, Phase 1,2,3 and 659 CALF Turnkey Dublin City 3 Túath Housing Association Q3‐2017 4 (Phase 4)

An Riasc, Finglas, Phase 1,2,3 and 660 CALF Turnkey Dublin City 1 Túath Housing Association Q4‐2018 4 (Phase 5)

Annamore Court, Ballyfermot 661 CALF Construction Dublin City 70 The Iveagh Trust Q2‐2017 (Phase 1)

Aughrim Street, , Clanmil Housing 662 CALF Turnkey Dublin City 4 Q3‐2019 Dublin 7 (Phase 1) Association Ireland

Balfe Road, Crumlin, Dublin 12 663 CALF Turnkey Dublin City 16 Respond Q4‐2018 (Phase 1)*

Ballygall Road East Phase 2 Fold Housing Association 664 CALF Construction Dublin City 11 Q1‐2016 (Phase 1) Ireland Ltd

Bethany House, Gilford Road, 665 CALF Construction Dublin City 62 Cluid Housing Q2‐2018 , Dublin 4 (Phase 1)

Blackbanks View, 754 666 CALF Turnkey Dublin City 40 Cluid Housing Q1‐2021 Road, , Dublin 5 (Phase 1)*

Block A Northbank, Castleforbes, 667 CALF Turnkey Dublin City 26 Túath Housing Association Q2‐2018 Dublin 1 (Phase 1)*

Block A, Jamestown Court, Dublin 668 CALF Construction Dublin City 9 ALONE Q4‐2020 8 (Phase 1)

Bluebell Avenue, Bluebell, Dublin 669 CALF Turnkey Dublin City 52 Respond Q4‐2019 12 (Phase 1)*

Bluebell Avenue, Dublin 12 (Phase 670 CALF Turnkey Dublin City 7 Túath Housing Association Q4‐2018 1)

Broome Lodge, 671 CALF Construction Dublin City 33 Cluid Housing Q4‐2017 Dunmanus Court, Cabra (Phase 1)

Camac Park, Bluebell, Dublin 12 672 CALF Turnkey Dublin City 5 Túath Housing Association Q2‐2020 (Phase 1)

24/05/2021 48/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Canal Meadows, Bluebell, Dublin 673 CALF Turnkey Dublin City 4 Túath Housing Association Q1‐2019 12 (Phase 1)

Chanel College, Coolock Village, 674 CALF Turnkey Dublin City Road, Dublin 5 (Phase 16 Respond Q4‐2017 1)*

Chanel Manor Apartments, 675 CALF Turnkey Dublin City 65 Respond Q2‐2019 Coolock, Dublin 5. (Phase 1)*

Chanel Manor, Coolock, Dublin 5 676 CALF Turnkey Dublin City 22 Respond Q4‐2020 (Phase 1)*

677 CALF Turnkey Dublin City , Dublin 13 (Phase 1)* 84 The Iveagh Trust Q2‐2019

Connaught Street, , Focus Housing Association 678 CALF Turnkey Dublin City 20 Q3‐2020 Dublin 7 (Phase 1) CLG

Cromwellsfort Court, Cromwellsfort Road, 679 CALF Turnkey Dublin City 12 Oaklee Housing Q3‐2020 , Dublin 12 (Phase 1)*

Crumlin Village, Dublin 12 (Phase 680 CALF Turnkey Dublin City 3 Cluid Housing Q2‐2017 1)

Crumlin Village, Dublin 12 (Phase 681 CALF Turnkey Dublin City 2 Cluid Housing Q3‐2017 2)

Dolphin Park, Rialto, Dublin 8 Fold Housing Association 682 CALF Construction Dublin City 43 Q4‐2019 (Phase 1) Ireland Ltd

Donnybrook Gardens, Lands of 683 CALF Turnkey Dublin City Greenfield Park, Donnybrook, 4 RHD Housing Q1‐2018 Dublin 4 (Phase 1)*

Elanora Court, Long Mile Road, 684 CALF Turnkey Dublin City Walkinstown, Dublin 12 (Phase 153 Respond Q3‐2020 1)*

Focus Housing Association 685 CALF Construction Dublin City Harolds Cross, Dublin 6 (Phase 1) 28 Q4‐2016 CLG

Harolds Cross, Dublin 6W (Phase 686 CALF Turnkey Dublin City 12 Respond Q1‐2021 1)

24/05/2021 49/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Huband Road, Bluebell, Dublin 12 Clanmil Housing 687 CALF Turnkey Dublin City 6 Q1‐2021 (Phase 1) Association Ireland

Lough Conn Road, Ballyfermot, 688 CALF Turnkey Dublin City 1 Túath Housing Association Q4‐2019 Dublin 10 (Phase 1)

Lough Conn Road, Ballyfermot, 689 CALF Turnkey Dublin City 4 Túath Housing Association Q4‐2020 Dublin 10 (Phase 2)

Merville Court, Merville Avenue, Co ‐ Operative Housing 690 CALF Turnkey Dublin City 5 Q1‐2017 Fairview (Phase 1) Ireland Society Limited

Millrose House, Bluebell Avenue, 691 CALF Turnkey Dublin City 8 Cluid Housing Q4‐2017 Dublin 12 (Phase 1)

Mountjoy Square North, Dublin 1 692 CALF Turnkey Dublin City 31 Respond Q4‐2019 (Phase 1)

Newtown Cottages Malahide Clanmil Housing 693 CALF Turnkey Dublin City 3 Q3‐2020 Road Coolock Dublin 17 (Phase 1) Association Ireland

North King Street, Dublin 7 Co ‐ Operative Housing 694 CALF Construction Dublin City 30 Q4‐2019 (Phase 1) Ireland Society Limited

Old School House Lane, Magenta 695 CALF Turnkey Dublin City Crescent, , Dublin 9 (Phase 8 Túath Housing Association Q4‐2019 1)

Orchard Lawns, Ballyfermot Co ‐ Operative Housing 696 CALF Construction Dublin City 36 Q3‐2018 (Phase 1) Ireland Society Limited

Orchard Lawns, Ballyfermot Co ‐ Operative Housing 697 CALF Construction Dublin City 36 Q4‐2018 (Phase 2) Ireland Society Limited

Park West Campus, Kileen Road, 698 CALF Turnkey Dublin City 41 Túath Housing Association Q4‐2020 Dublin 12 (Phase 1)

Post Tender ‐ Wad River Close 699 CALF Construction Dublin City Phase 2, Ballymun, Dublin 9 9 Cluid Housing Q4‐2019 (Phase 1)

Post Tender Johns Lane West Focus Housing Association 700 CALF Construction Dublin City 31 Q4‐2018 Dublin 8 (Phase 1) CLG

24/05/2021 50/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

POST TENDER, Poplar Row, 701 CALF Construction Dublin City 29 Oaklee Housing Q4‐2019 Ballybough, Dublin 3 (Phase 1)

Ravensdale Court, , 702 CALF Turnkey Dublin City 12 Túath Housing Association Q4‐2020 Dublin 12. (Phase 1)

Revised ‐ Dominic Place, Dublin The Paddy McGrath 703 CALF Construction Dublin City 9 Q3‐2020 (Phase 1) Housing Project

Revised Post Tender ‐ Raleigh 704 CALF Construction Dublin City 33 Túath Housing Association Q4‐2019 Square, Crumlin (Phase 1)

Revised, St Mary’s Mansions, 705 CALF Construction Dublin City 80 Cluid Housing Q4‐2019 Dublin 1 (Phase 1)

Richmond Road, Dublin 9 (Phase Co ‐ Operative Housing 706 CALF Construction Dublin City 40 Q4‐2018 1) Ireland Society Limited

Royal Canal Crescent, Rathborne 707 CALF Turnkey Dublin City Park, Rathborne, Dublin15 (Phase 16 Cluid Housing Q4‐2020 1)*

Royal Canal Park, Ashtown, Dublin 708 CALF Turnkey Dublin City 46 Respond Q4‐2020 15 (Phase 1)*

St Agnes Convent, Armagh Road, Fold Housing Association 709 CALF Turnkey Dublin City 44 Q4‐2019 Crumlin, Dublin 12 (Phase 1) Ireland Ltd

St Agnes Convent, Armagh Road, Fold Housing Association 710 CALF Turnkey Dublin City 6 Q4‐2020 Crumlin, Dublin 12 (Phase 1) Ireland Ltd

St Agnes Convent, Armagh Road, Fold Housing Association 711 CALF Turnkey Dublin City 42 Q2‐2020 Crumlin, Dublin 12 (Phase 2) Ireland Ltd

St Agnes Convent, Armagh Road, Fold Housing Association 712 CALF Turnkey Dublin City 11 Q4‐2020 Crumlin, Dublin 12 (Phase 3) Ireland Ltd

Stormanstown Hall, Ballymun 713 CALF Turnkey Dublin City 42 Oaklee Housing Q3‐2018 Road, (revised) (Phase 1)

Sundrive Mews, Kimmage, Dublin 714 CALF Turnkey Dublin City 9 Cluid Housing Q4‐2019 12 (Phase 1)

24/05/2021 51/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

715 CALF Turnkey Dublin City Thornwood, Beaumont (Phase 1) 28 Túath Housing Association Q2‐2016

716 CALF Turnkey Dublin City Thornwood, Beaumont (Phase 2) 18 Túath Housing Association Q4‐2016

717 CALF Turnkey Dublin City Thornwood, Beaumont (Phase 3) 14 Túath Housing Association Q1‐2017

718 CALF Turnkey Dublin City Thornwood, Beaumont (Phase 4) 8 Túath Housing Association Q1‐2017

Tonlegee Road, Dublin 5 (Phase Fold Housing Association 719 CALF Turnkey Dublin City 47 Q4‐2018 1) Ireland Ltd

PUBLIC PRIVATE PARTNERSHIP 720 Dublin City Ayrfield, Malahide Road 150 *N/A Q1‐2019 (Bundle 1)

PUBLIC PRIVATE PARTNERSHIP 721 Dublin City Scribblestown 70 *N/A Q4‐2020 (Bundle 1)

SHIP CONSTRUCTION Blackmills Grove, Blakestown 722 10 *N/A Q2‐2017 TURNKEY Road, Mulhuddard

SHIP CONSTRUCTION Balgriffin Grove, Malahide Road, 723 Fingal 6 *N/A Q1‐2017 TURNKEY Balgriffin

SHIP CONSTRUCTION 724 Fingal Hansfield, Ongar, 36 *N/A Q3‐2017 TURNKEY

SHIP CONSTRUCTION 725 Fingal Hansfield, Ongar, Dublin 15 16 *N/A Q1‐2018 TURNKEY

SHIP CONSTRUCTION 726 Fingal Hansfield, Ongar, Dublin 15 16 *N/A Q2‐2018 TURNKEY

SHIP CONSTRUCTION 727 Fingal Ravenswood, North Road, Finglas 2 Peter McVerry Trust Ltd Q4‐2018 TURNKEY

SHIP CONSTRUCTION 728 Fingal Boroimhe, Swords 6 *N/A Q3‐2018 TURNKEY

24/05/2021 52/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 729 Fingal Cnoc Dubh, 6 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 730 Fingal Kenure Gate, Park Road, Rush 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 731 Fingal Glaslinn, 3 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Bremore Pastures Park, 732 Fingal 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Northwood Green, Santry, Dublin 733 Fingal 37 *N/A Q4‐2018 TURNKEY 9

SHIP CONSTRUCTION 734 Fingal Hollytown Cottages 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Cnoc Dubh Ballyboughal Co. 735 Fingal 5 *N/A Q3‐2019 TURNKEY Dublin

SHIP CONSTRUCTION 736 Fingal Rahillion, Donabate 1 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Bay Meadows Avenue/Square, 737 Fingal 12 *N/A Q4‐2020 TURNKEY Dublin 15

SHIP CONSTRUCTION Bay Meadows, Hollystown, Dublin 738 Fingal 10 *N/A Q3‐2020 TURNKEY 15

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE 739 Fingal Outlands, Rathbeale Road, Swords 11 *N/A the scheme is fully STAGE approved.

SHIP CONSTRUCTION RAPID 740 Fingal Avondale, , Dublin 15 42 *N/A Q4‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 741 Fingal Pinewood, Balbriggan 20 *N/A Q2‐2018 VOLUMETRIC

SHIP CONSTRUCTION RAPID 742 Fingal Wellview, Mulhuddart 20 *N/A Q4‐2017 VOLUMETRIC

24/05/2021 53/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION RAPID Church Road, Mulhuddart, Dublin 743 Fingal 22 *N/A Q4‐2019 VOLUMETRIC 15

Stage 2 approved Q4‐2020, SHIP CONSTRUCTION RAPID Church Fields, Phase 2B, 744 Fingal 51 *N/A full design/tender being VOLUMETRIC Mulhuddart, Dublin 15. prepared.

745 SHIP CONSTRUCTION Fingal Rivermeade, St. Margarets 2 *N/A Q2‐2019

746 SHIP CONSTRUCTION Fingal Rowlestown 10 *N/A Q2‐2019

747 SHIP CONSTRUCTION Fingal Racecourse Commons, Lusk 5 *N/A Q2‐2018

Castlelands, Park View, Balbriggan 748 SHIP CONSTRUCTION Fingal 24 *N/A Q1‐2019 (Phase 3)

749 SHIP CONSTRUCTION Fingal Rathbeale Road, Swords 24 *N/A Q2‐2020

750 SHIP CONSTRUCTION Fingal The Grange, Ballyboughal 2 *N/A Q3‐2017

751 SHIP CONSTRUCTION Fingal Cappaghfinn (Phase 1) 14 *N/A Q2‐2016

752 SHIP CONSTRUCTION Fingal St. Cronan's Green, Swords 14 *N/A Q2‐2016

St. Cronan's Cottages, Swords ‐ 753 SHIP CONSTRUCTION Fingal 1 *N/A Q2‐2016 Infill

754 SHIP CONSTRUCTION Fingal Racecourse Commons, Lusk 25 *N/A Q4‐2017

755 SHIP CONSTRUCTION Fingal The Grange, Ballyboughal 6 *N/A Q4‐2018

756 SHIP CONSTRUCTION Fingal Racecourse Commons, Lusk 15 *N/A Q1‐2018

24/05/2021 54/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Redevelopment of Community 757 SHIP CONSTRUCTION Fingal 2 *N/A Q3‐2019 Centre, Pinewood, Balbriggan

758 SHIP CONSTRUCTION Fingal Racecourse Commons, Lusk 4 *N/A Q3‐2018

759 SHIP CONSTRUCTION Fingal Racecourse Commons, Lusk 25 *N/A Q4‐2018

Stage 3 approved Q3‐2020, the scheme is now 760 SHIP CONSTRUCTION Fingal Tucketts Lane, Howth 8 *N/A approved to proceed to tender.

761 SHIP CONSTRUCTION Fingal Wellview 20 *N/A Q3‐2020

762 SHIP CONSTRUCTION Fingal Rowlestown 6 *N/A Q4‐2019

763 SHIP CONSTRUCTION Fingal Rowlestown 6 *N/A Q4‐2019

Stage 4 approved Q4‐2020, Cappaghfinn, Cappagh Road 764 SHIP CONSTRUCTION Fingal 69 *N/A the scheme is fully Finglas ‐ Phase 3 approved.

765 SHIP CONSTRUCTION Fingal Rowlestown 4 *N/A Q3‐2019

Stage 2 approved Q4‐2020, 766 SHIP CONSTRUCTION Fingal Leonards Garage, Lusk 10 *N/A full design/tender being prepared.

Stage 2 approved Q4‐2020, 767 SHIP CONSTRUCTION Fingal Church Road, Lusk 5 *N/A full design/tender being prepared.

Stage 2 approved Q4‐2020, Church Fields, Phase 2B, 768 SHIP CONSTRUCTION Fingal 16 *N/A full design/tender being Mulhuddart, Dublin 15. prepared.

Stage 1 approved Q1‐2017, Túath Housing Association 769 CAS CONSTRUCTION Fingal Killhedge Lane Dun Emer 48 outline design and costs Ltd being prepared.

770 CAS CONSTRUCTION Fingal Ravenswood, North Road, Finglas 6 Peter McVerry Trust Ltd Q4‐2018

24/05/2021 55/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

771 CAS CONSTRUCTION Fingal 22 College Street, 4 Cluid Housing Association Q3‐2020

North & East Housing 772 CAS CONSTRUCTION Fingal Darcystown, Ringfort, 9 Q3‐2017 Association Ltd

Society of Saint Vincent de 773 CAS CONSTRUCTION Fingal Estuary Road, Malahide 8 Q2‐2018 Paul

Stage 2 approved Q4‐2020, North & East Housing 774 CAS CONSTRUCTION Fingal 5 full design/tender being Association Ltd prepared.

4 units, Taylor Hill, Balbriggan, Co. 775 CALF Turnkey Fingal 4 Cluid Housing Q4‐2018 Dublin (Phase 1)

Allendale Square, , Dublin 776 CALF Turnkey Fingal 28 Respond Q2‐2020 15 (Phase 1)*

An Muileann, Kettles Lane, Circle Voluntary Housing 777 CALF Turnkey Fingal 24 Q4‐2019 Swords, Dublin (Phase 1) Association Ltd

Barnwell Woods, Hansfield, Dublin 778 CALF Turnkey Fingal 12 Túath Housing Association Q4‐2018 15 (Phase 1)*

Barnwell Woods, Hansfield, Dublin 779 CALF Turnkey Fingal 12 Túath Housing Association Q4‐2018 15 (Phase 2)*

Belcamp Manor, Malahide Road, 780 CALF Turnkey Fingal 18 Túath Housing Association Q4‐2019 Balgriffin, Dublin 13 (Phase 1)

Belcamp Manor, Malahide Road, 781 CALF Turnkey Fingal 15 Túath Housing Association Q4‐2019 Balgriffin, Dublin 13 (Phase 2)

Belcamp Manor, Malahide Road, 782 CALF Turnkey Fingal 16 Túath Housing Association Q4‐2019 Balgriffin, Dublin 13 (Phase 3)

Bellingsmore, Hollywoodrath, 783 CALF Turnkey Fingal 29 Túath Housing Association Q4‐2020 Dubin 15 (Phase 1)

Bellingsmore, Hollywoodrath, 784 CALF Turnkey Fingal 12 Túath Housing Association Q4‐2020 Dubin 15 (Phase 2)

24/05/2021 56/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Carrs Lane, Malahide Road, Dublin 785 CALF Turnkey Fingal 29 Respond Q4‐2019 17 (Phase 1)*

Carrs Lane, Malahide Road, Dublin 786 CALF Turnkey Fingal 30 Respond Q4‐2019 17 (Phase 2)*

Castlegrange Park (2) Clonsilla 787 CALF Turnkey Fingal 5 Túath Housing Association Q2‐2016 (Phase 1)

Castlegrange Park (2) Clonsilla 788 CALF Turnkey Fingal 7 Túath Housing Association Q3‐2016 (Phase 2)

Castlegrange Park (2) Clonsilla 789 CALF Turnkey Fingal 7 Túath Housing Association Q4‐2016 (Phase 3)

Castlegrange Park (2) Clonsilla 790 CALF Turnkey Fingal 21 Túath Housing Association Q1‐2017 (Phase 4)

Castlegrange Park (2) Clonsilla 791 CALF Turnkey Fingal 8 Túath Housing Association Q2‐2017 (Phase 5)

Charlestown Centre, Charlestown 792 CALF Turnkey Fingal Place & St., Margarets Road, 94 Respond Q3‐2019 Dublin 11 (Phase 1)*

Charlestown Centre, Charlestown 793 CALF Turnkey Fingal Place & St., Margarets Road, 44 Respond Q3‐2019 Dublin 11 (Phase 2)*

Cois Sruthan, Ballyboughal, 794 CALF Turnkey Fingal 17 Oaklee Housing Q3‐2020 Co.Dublin (Phase 1)*

Drynam Heath, Feltrim Road, 795 CALF Turnkey Fingal 11 Túath Housing Association Q4‐2019 Swords, Co. Dublin (Phase 1)

Drynam Heath, Feltrim Road, 796 CALF Turnkey Fingal 6 Túath Housing Association Q1‐2019 Swords, Co. Dublin (Phase 2)*

Dun Si, St. Marnock Bay, Station Road, , Co. Dublin 797 CALF Turnkey Fingal 10 Cluid Housing Q2‐2020 (Phase 1)* Dun Si, St. Marnock Bay, Station Road, Portmarnock, Co. Dublin 798 CALF Turnkey Fingal 5 Cluid Housing Q4‐2020 (Phase 2)*

24/05/2021 57/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

799 CALF Turnkey Fingal Dunsoghly, Dublin 11 (Phase 1)* 19 Cluid Housing Q4‐2020

Knightsgate, Rush, Co. Dublin 800 CALF Turnkey Fingal 38 Cluid Housing Q4‐2019 (Phase 1)*

Knightsgate, Rush, Co. Dublin 801 CALF Turnkey Fingal 19 Cluid Housing Q3‐2020 (phase 2) (Phase 1)

Ladyswell Road & Church Road, 802 CALF Construction Fingal 65 Cluid Housing Q4‐2018 Mulhuddart, Dublin 15 (Phase 1)

Lanesborough Close, Finglas, 803 CALF Turnkey Fingal 21 Cluid Housing Q4‐2018 Dublin 11 (Phase 1)*

Martello Place, Balbriggan, Co 804 CALF Turnkey Fingal 18 Respond Q3‐2018 Dublin (Phase 1)

Millers Glen, Oldtown, Swords, 805 CALF Turnkey Fingal 28 The Iveagh Trust Q4‐2020 Co. Dublin (Phase 1)*

Millers Glen, Phase 3, Oldtown, 806 CALF Turnkey Fingal 14 The Iveagh Trust Q4‐2019 Swords (Phase 1)*

Norseman's Court, Norseman's 807 CALF Turnkey Fingal Walk, Lusk Village, Lusk, Co. 18 Cluid Housing Q4‐2020 Dublin (Phase 1)*

Northwood Green, Santry, Dublin 808 CALF Turnkey Fingal 6 Respond Q4‐2018 9 (Phase 1)*

Northwood, Ballymun Cross, 809 CALF Turnkey Fingal 48 Respond Q4‐2019 Santry, Dublin 9 (Phase 1)

Northwood, Ballymun Cross, 810 CALF Turnkey Fingal 7 Respond Q2‐2020 Santry, Dublin 9 (Phase 2)*

Old Coolock Lane, Santry, Dublin 9 Circle Voluntary Housing 811 CALF Construction Fingal 28 Q1‐2019 (Phase 1) Association Ltd

Old Road, 812 CALF Turnkey Fingal , Dublin 15 (Phase 17 Respond Q4‐2020 1)

24/05/2021 58/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Old Corduff Road, 813 CALF Turnkey Fingal Blanchardstown, Dublin 15 (Phase 10 Respond Q4‐2018 2)*

Pappan Grove, Northwood, 814 CALF Turnkey Fingal 35 Túath Housing Association Q3‐2019 Santry, Dublin 9 (Phase 1)*

Phoenix Park Avenue, Fold Housing Association 815 CALF Turnkey Fingal 31 Q4‐2019 , Dublin 15 (Phase 1)* Ireland Ltd

Riverwood Square, Dublin 15 816 CALF Turnkey Fingal 24 Cluid Housing Q4‐2019 (Phase 1)*

Semple Woods, Donabate, Co. 817 CALF Turnkey Fingal 7 Túath Housing Association Q4‐2020 Dublin (Phase 1)*

Semple Woods, Donabate, Co. 818 CALF Turnkey Fingal 3 Túath Housing Association Q4‐2019 Dublin (Phase 2)*

Semple Woods, Donabate, North 819 CALF Turnkey Fingal 30 Túath Housing Association Q4‐2019 (Phase 1)*

St Marnock’s Bay, Portmarnock, 820 CALF Turnkey Fingal 10 Cluid Housing Q4‐2017 Co Dublin (Phase 1)*

St Werburghs Court Drynam Rd 821 CALF Turnkey Fingal 18 Túath Housing Association Q4‐2017 Swords Co Dublin (Phase 1)*

Station Manor, Station Road, Circle Voluntary Housing 822 CALF Turnkey Fingal Portmarnock, Co. Dublin (Phase 3 Q2‐2019 Association Ltd 1)*

Station Manor, Station Road, Circle Voluntary Housing 823 CALF Turnkey Fingal Portmarnock, Co. Dublin (Phase 8 Q4‐2017 Association Ltd 2)*

Taylor Hill Crescent, Balbriggan, 824 CALF Turnkey Fingal 4 Cluid Housing Q4‐2018 Co. Dublin (Phase 1)

Taylor Hill, Balbriggan, Co. Dublin 825 CALF Turnkey Fingal 21 Cluid Housing Q2‐2020 (Phase 1)

Taylor Hill, Balbriggan, Co. Dublin 826 CALF Turnkey Fingal 31 Cluid Housing Q4‐2018 (Phase 1)*

24/05/2021 59/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Taylor Hill, Balbriggan, Co. Dublin 827 CALF Turnkey Fingal 24 Cluid Housing Q4‐2019 (Phase 1)*

Taylor Hill, Balbriggan, Co. Dublin 828 CALF Turnkey Fingal 1 Cluid Housing Q4‐2020 (Phase 2)

The Forge, Lusk, Co. Dublin (Phase 829 CALF Turnkey Fingal 8 Oaklee Housing Q4‐2019 1)

The Hermitage, Balgriffin, Co 830 CALF Turnkey Fingal 54 Cluid Housing Q4‐2017 Dublin (Phase 1)*

Waterside, Malahide, Dublin 831 CALF Turnkey Fingal 5 Cluid Housing Q4‐2020 (Phase 1)

Weavers Wood, Clonsilla Road, Co ‐ Operative Housing 832 CALF Turnkey Fingal 33 Q3‐2018 Clonsilla, Dublin 15 (Phase 1)* Ireland Society Limited

Weston, Feltrim Road, Swords, 833 CALF Turnkey Fingal 24 Oaklee Housing Q4‐2019 North County Dublin (Phase 1)

Weston, Feltrim Road, Swords, 834 CALF Turnkey Fingal 10 Oaklee Housing Q3‐2020 North County Dublin (Phase 2)*

Wrens Hill, (Formerly The 835 CALF Turnkey Fingal Galleries), Donabate, Co. Dublin 43 Oaklee Housing Q4‐2019 (Phase 1)

SHIP CONSTRUCTION Radharc na Gréine, (Glasshouse 836 Galway City 6 *N/A Q3‐2019 TURNKEY Site) Monivea Road (Phase 1)

SHIP CONSTRUCTION Radharc na Gréine (Glasshouse 837 Galway City 16 *N/A Q4‐2019 TURNKEY Site), Monivea Road ‐ (Phase 2)

SHIP CONSTRUCTION Radharc na Gréine (Glasshouse 838 Galway City 7 *N/A Q4‐2019 TURNKEY Site), Monivea Road ‐ (Phase 3)

SHIP CONSTRUCTION Radharc na Gréine (Glasshouse 839 Galway City 13 *N/A Q3‐2020 TURNKEY Site), Monivea Road ‐ (Phase 4)

SHIP CONSTRUCTION Radharc na Gréine (Glasshouse 840 Galway City 8 *N/A Q4‐2020 TURNKEY Site), Monivea Road ‐ (Phase 5)

24/05/2021 60/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Garraí Caol, (Coast Road Site) 841 Galway City 27 *N/A Q1‐2020 TURNKEY Dublin Road

SHIP CONSTRUCTION Garraí Caol (Coast Road Site) 842 Galway City 26 *N/A Q1‐2020 TURNKEY Dublin Road

Ard Cré, Ballymoneen Road 843 SHIP CONSTRUCTION Galway City 78 *N/A Q4‐2020 (Phase 2)

Ard Cré, Ballymoneen Road 844 SHIP CONSTRUCTION Galway City 14 *N/A Q2‐2018 (Phase 1)

Stage 2 approved Q3‐2020, 845 SHIP CONSTRUCTION Galway City Monivea Road, Ballybaan More 15 *N/A full design/tender being prepared.

Garraí Beag, Monivea Road, 846 SHIP CONSTRUCTION Galway City 58 *N/A Q1‐2020 Ballybaan More

Stage 1 approved Q2‐2020, 847 SHIP CONSTRUCTION Galway City Keeraun, Ballymoneen Road 60 *N/A outline design and costs being prepared.

848 SHIP CONSTRUCTION Galway City Clareview Park, Ballybaan 5 *N/A Q1‐2021

Stage 1 approved Q2‐2020, 849 SHIP CONSTRUCTION Galway City Merlin Park Lands, Galway City 18 *N/A outline design and costs being prepared.

Carraig Dubh Housing 850 CAS CONSTRUCTION Galway City 97/98 Rockfield 4 Q1‐2018 Association

Peter Triest Housing 851 CAS CONSTRUCTION Galway City Cul Garrai, Rahoon 6 Q4‐2020 Association Ltd

47 Forster Street, Galway City 852 CAS CONSTRUCTION Galway City 9 Cope Galway Q4‐2019 (Domestic Violence Refuge)

Stage 1 approved Q2‐2019, 853 CAS CONSTRUCTION Galway City Doughiska, Galway City 7 Respond outline design and costs being prepared.

Belmont, Renmore, Galway City Co ‐ Operative Housing 854 CALF Turnkey Galway City 16 Q4‐2019 (Phase 1)* Ireland Society Limited

24/05/2021 61/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Block C, Sraith Fhada, Doughiska, 855 CALF Turnkey Galway City 11 Túath Housing Association Q4‐2020 Galway (Phase 1)

Block D, Sraith Fhada, Doughiska, 856 CALF Turnkey Galway City 14 Túath Housing Association Q4‐2019 Galway (Phase 1)

Boireann Beag, Ros Cam, Galway 857 CALF Turnkey Galway City 16 Cluid Housing Q4‐2016 (Phase 1)

Breacan, Letteragh Road, Galway 858 CALF Turnkey Galway City 2 Túath Housing Association Q4‐2019 City (Phase 1)*

Caireal Mor (Phase 2), Headford 859 CALF Turnkey Galway City 7 Respond Q4‐2019 Road, Castlegar, Galway (Phase 1)

Caireal Mor (Phase 2), Headford 860 CALF Turnkey Galway City Road, Castlegar, Galway (Phase 8 Respond Q3‐2020 2)*

Caireal Mor, Castlegar Road, 861 CALF Turnkey Galway City 10 Respond Q4‐2019 Galway (Phase 1)

Caireal Mor, Castlegar Road, 862 CALF Turnkey Galway City 71 Respond Q4‐2020 Galway (Phase 2)

Clybaun Road, Knocknacarra, 863 CALF Turnkey Galway City 9 Túath Housing Association Q4‐2020 Galway (Phase 1)

Cnoc na Ri, Clybaun Road, Galway 864 CALF Turnkey Galway City 2 Cluid Housing Q3‐2017 (Phase 1)*

Creig Ard, Roscam, Galway City 865 CALF Turnkey Galway City 9 Cluid Housing Q4‐2020 (Phase 1)

Creig Ard, Roscam, Galway City 866 CALF Turnkey Galway City 10 Cluid Housing Q4‐2019 (Phase 2)

Creig Ard, Roscam, Galway City, 867 CALF Turnkey Galway City 17 Cluid Housing Q4‐2019 Co. Galway (Phase 1)*

Gaelcarrig, Letteragh, Galway City 868 CALF Turnkey Galway City 43 Respond Q3‐2020 (Phase 1)

24/05/2021 62/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Gaelcarrig, Letteragh, Galway City 869 CALF Turnkey Galway City 40 Respond Q3‐2020 (Phase 2)*

Leana Theas, Cappagh Road, Co ‐ Operative Housing 870 CALF Turnkey Galway City 10 Q4‐2019 Galway City (Phase 1)* Ireland Society Limited

Letteragh Road, Rahoon, Galway 871 CALF Turnkey Galway City 23 Cluid Housing Q3‐2020 City (Phase 1)*

Letteragh Road, Rahoon, Galway 872 CALF Turnkey Galway City 16 Cluid Housing Q3‐2020 City (Phase 2)

Letteragh Road, Rahoon, Galway 873 CALF Turnkey Galway City 25 Cluid Housing Q3‐2020 City (Phase 3)*

Maigh Rua, Doughiska, Galway Co ‐ Operative Housing 874 CALF Turnkey Galway City 23 Q4‐2017 (Phase 1) Ireland Society Limited

Maoilin, Ballymoneen Road, 875 CALF Turnkey Galway City 2 Túath Housing Association Q1‐2017 Galway (Phase 1)*

Maoilin, Ballymoneen Road, 876 CALF Turnkey Galway City 4 Túath Housing Association Q4‐2017 Galway (Phase 2)*

Maoilin, Ballymoneen Road, 877 CALF Turnkey Galway City Knocknacarra, Galway CIty (Phase 3 Túath Housing Association Q3‐2018 1)*

Reilean, Roscam, Block 5 Galway 878 CALF Turnkey Galway City 12 Túath Housing Association Q2‐2017 (Phase 1)*

Reilean, Roscam,Block 4 Galway 879 CALF Turnkey Galway City 12 Túath Housing Association Q2‐2017 (Phase 1)*

Revised Murrough, Renmore, 880 CALF Turnkey Galway City 20 Cluid Housing Q1‐2019 Galway (Phase 1)*

PUBLIC PRIVATE PARTNERSHIP 881 Galway City Ballyburke 74 *N/A Q4‐2019 (Bundle 2)

SHIP CONSTRUCTION 882 Galway County Lorro Gate, Prospect, Athenry 14 *N/A Q4‐2017 TURNKEY

24/05/2021 63/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 883 Galway County Arvough, Kinvara 6 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION Castlecourt, Abbey Street, 884 Galway County 10 *N/A Q4‐2017 TURNKEY Portumna

SHIP CONSTRUCTION 885 Galway County Ashthorn Avenue, Headford 10 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 886 Galway County Cuirt na hAbhann, Claregalway 8 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Tulaigh na Gréine, Tullahill, 887 Galway County 19 *N/A Q4‐2019 TURNKEY Loughrea

SHIP CONSTRUCTION Gort na dTulach, Tullahill, 888 Galway County 17 *N/A Q4‐2019 TURNKEY Loughrea ‐ Phase 2A

SHIP CONSTRUCTION 889 Galway County Arvough, Kinvara 4 *N/A Q4‐2019 TURNKEY

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Gort an Choirce, Tubber Road, 890 Galway County 24 *N/A the scheme is fully TURNKEY Gort approved.

SHIP CONSTRUCTION Páirc an Triantáin, Tullahill, 891 Galway County 10 *N/A Q4‐2020 TURNKEY Loughrea, ‐ Phase 3

SHIP CONSTRUCTION Gort na dTulach, Tullahill, 892 Galway County 15 *N/A Q4‐2020 TURNKEY Loughrea ‐ Phase 2B

SHIP CONSTRUCTION 893 Galway County Kylebroughlan, Moycullen 8 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 894 Galway County Kylebroughlan, Moycullen 10 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 895 Galway County Kylebroughlan, Moycullen 7 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 896 Galway County Kylebroughlan, Moycullen 9 *N/A Q1‐2021 TURNKEY

24/05/2021 64/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 897 Galway County Kylebroughlan, Moycullen 10 *N/A Q1‐2021 TURNKEY

SHIP CONSTRUCTION Garraí Mhic Aodha, Tubber Road, 898 Galway County 17 *N/A Q2‐2020 TURNKEY Gort

SHIP CONSTRUCTION Páirc an Triantáin, Tullahill, 899 Galway County 9 *N/A Q3‐2018 TURNKEY Loughrea ‐ Phase 4

SHIP CONSTRUCTION Garraí Mhic Aodha, Tubber Road, 900 Galway County 14 *N/A Q2‐2020 TURNKEY Gort

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Gort an Choirce, Tubber Road, 901 Galway County 21 *N/A the scheme is fully TURNKEY Gort approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Gort an Choirce, Tubber Road, 902 Galway County 8 *N/A the scheme is fully TURNKEY Gort approved.

903 SHIP CONSTRUCTION Galway County Esker Fields, Ballinasloe 2 *N/A Q4‐2019

904 SHIP CONSTRUCTION Galway County Garbally Drive, Ballinasloe 10 *N/A Q3‐2019

905 SHIP CONSTRUCTION Galway County Na Clocha Rua, An Cheathrú Rua 4 *N/A Q4‐2019

906 SHIP CONSTRUCTION Galway County Ardrahan (SRD) 1 *N/A Q4‐2017

907 SHIP CONSTRUCTION Galway County Callowfinish, Carna (SRD) 1 *N/A Q2‐2018

908 SHIP CONSTRUCTION Galway County Waterdale, Claregalway (SRD) 1 *N/A Q4‐2018

909 SHIP CONSTRUCTION Galway County Corndulla (SRD) 1 *N/A Q1‐2019

910 SHIP CONSTRUCTION Galway County Cill Ciarán (SRD) 1 *N/A Q3‐2018

24/05/2021 65/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

911 SHIP CONSTRUCTION Galway County Kinvara (SRD) 1 *N/A Q3‐2018

912 SHIP CONSTRUCTION Galway County Cnoc na Carraige, Roundstone 8 *N/A Q4‐2020

Gort na gCloch, Hospital Road, 913 SHIP CONSTRUCTION Galway County 16 *N/A Q4‐2020 Clifden

Stage 2 approved Q2‐2019, Bridge Court, Ahascragh, 914 SHIP CONSTRUCTION Galway County 18 *N/A full design/tender being Ballinasloe prepared.

Stage 2 approved Q2‐2019, 915 SHIP CONSTRUCTION Galway County Caisleán Raithlín, Ardrahan 12 *N/A full design/tender being prepared.

916 SHIP CONSTRUCTION Galway County Barrack Street, Loughrea 5 *N/A Q2‐2020

917 SHIP CONSTRUCTION Galway County Gilmartin Road, Tuam ‐ Phase 2 24 *N/A Q3‐2019

Stage 3 approved Q1‐2021, the scheme is now 918 SHIP CONSTRUCTION Galway County Cartron, Kinvara 10 *N/A approved to proceed to tender.

Stage 2 approved Q4‐2019, 919 SHIP CONSTRUCTION Galway County Gort Uí Lochlainn, Moycullen 31 *N/A full design/tender being prepared.

920 SHIP CONSTRUCTION Galway County Gilmartin Road, Tuam 16 *N/A Q4‐2018

921 SHIP CONSTRUCTION Galway County Fána Bhuí, Tuam 18 *N/A Q4‐2020

922 SHIP CONSTRUCTION Galway County Gilmartin Road, Tuam ‐ Phase 3 19 *N/A Q4‐2019

923 SHIP CONSTRUCTION Galway County Cnoc na Carraige , Roundstone 6 *N/A Q1‐2021

Stage 2 approved Q4‐2020, 924 SHIP CONSTRUCTION Galway County , Ardrahan (SRD) 1 *N/A full design/tender being prepared.

24/05/2021 66/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q4‐2020, 925 SHIP CONSTRUCTION Galway County Woodpark, Portumna (SRD) 1 *N/A full design/tender being prepared.

Stage 2 approved Q4‐2020, Carrowmore West, Clontuskert, 926 SHIP CONSTRUCTION Galway County 1 *N/A full design/tender being Ballinasloe (SRD) prepared.

Stage 2 approved Q4‐2020, 927 SHIP CONSTRUCTION Galway County Woodfireld, Dunmore (SRD) 1 *N/A full design/tender being prepared.

Stage 2 approved Q4‐2020, Knockaloura West, Brownsgrove, 928 SHIP CONSTRUCTION Galway County 1 *N/A full design/tender being Tuam (SRD) prepared.

Stage 2 approved Q4‐2020, 929 SHIP CONSTRUCTION Galway County Creggaturlough, Craughwell (SRD) 1 *N/A full design/tender being prepared.

Gort na gCloch, Hospital Road, 930 SHIP CONSTRUCTION Galway County 10 *N/A Q4‐2020 Clifden

931 SHIP CONSTRUCTION Galway County Fána Bhuí, Tuam 13 *N/A Q4‐2020

932 SHIP CONSTRUCTION Galway County Fána Bhuí, Tuam 18 *N/A Q4‐2020

Inis Housing Association 933 CAS CONSTRUCTION TURNKEY Galway County Tubber Road, Gort 11 Q2‐2020 Ltd

934 CAS CONSTRUCTION Galway County Letterfrack (Phase 2) 11 Cluid Housing Association Q4‐2020

Stage 1 approved Q4‐2016, Rossaveal Cottages, Ros a Mhíl, 935 CAS CONSTRUCTION Galway County 8 Tearmann Eanna Teoranta outline design and costs South Connemara being prepared.

Claregalway and District 936 CAS CONSTRUCTION Galway County Cregboy, Claregalway 14 Q3‐2019 Day Care Centre

Stage 2 approved Q4‐2018, 937 CAS CONSTRUCTION Galway County Eanach Mheain, Carraroe 13 Tearmann Eanna Teoranta full design/tender being prepared.

Stage 2 approved Q4‐2019, Túath Housing Association 938 CAS CONSTRUCTION Galway County Mountbellew 5 full design/tender being Ltd prepared.

24/05/2021 67/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q2‐2017, Peter Triest Housing 939 CAS CONSTRUCTION Galway County Springfield, Parkmore, Ballinasloe 4 outline design and costs Association Ltd being prepared.

940 CAS CONSTRUCTION Galway County Letterfrack (Phase 1) 13 Cluid Housing Association Q2‐2016

941 CAS CONSTRUCTION Galway County Dunlo Hill, Ballinasloe 18 Cluid Housing Association Q3‐2020

Peter Triest Housing 942 CAS CONSTRUCTION Galway County Aggard More, Craughwell 4 Q4‐2019 Association Ltd

943 CAS CONSTRUCTION Galway County The Old Post Office, Inverin 4 Tearmann Eanna Teoranta Q4‐2020

Stage 2 approved Q1‐2021, Carraig Dubh Housing 944 CAS CONSTRUCTION Galway County Shannon Road, Portumna 4 full design/tender being Association prepared.

Cnoc na Si, Portumna, Co Galway Co ‐ Operative Housing 945 CALF Turnkey Galway County 10 Q2‐2018 (Phase 1) Ireland Society Limited

Dunloe Street, Ballinasloe, Co. Co ‐ Operative Housing 946 CALF Turnkey Galway County 9 Q4‐2020 Galway (Phase 1) Ireland Society Limited

Oranhill, Oranmore, Co. Galway 947 CALF Turnkey Galway County 22 Cluid Housing Q1‐2021 (Phase 1)*

Riveroaks, Claregalway, Co 948 CALF Turnkey Galway County 11 Cluid Housing Q4‐2020 Galway (Phase 1)

Riveroaks, Claregalway, Co 949 CALF Turnkey Galway County 12 Cluid Housing Q1‐2021 Galway (Phase 2)

Riveroaks, Claregalway, Co 950 CALF Turnkey Galway County 16 Cluid Housing Q4‐2019 Galway (Phase 3)*

Spiddal Cottages, Co Galway 951 CALF Construction Galway County 23 Cluid Housing Q3‐2017 (Phase 1)

SHIP CONSTRUCTION 952 Kerry Ard Na Si, Lispole 2 *N/A Q1‐2018 TURNKEY

24/05/2021 68/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1‐4 Steeple Meadow View, 953 Kerry 4 *N/A Q4‐2017 TURNKEY Milltown

SHIP CONSTRUCTION 954 Kerry Meadow Park, Milltown 9 *N/A Q2‐2018 TURNKEY

SHIP CONSTRUCTION 955 Kerry Ard Na Si, Lispole, Phase 2 5 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 956 Kerry Ardmoniel Heights, Killorglin 3 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 47 Woodview, Cahirdown, 957 Kerry 1 *N/A Q2‐2018 TURNKEY

SHIP CONSTRUCTION 958 Kerry Dromin Upper, Listowel 8 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 959 Kerry Ard Na Si, Lispole, Phase 3 3 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Ardmoniel Heights, Killorglin ‐ 960 Kerry 1 *N/A Q2‐2019 TURNKEY Phase 2

SHIP CONSTRUCTION 961 Kerry Ballygologue, Road, Listowel 2 *N/A Q4‐2019 TURNKEY

Stage 4 approved Q2‐2019, SHIP CONSTRUCTION 962 Kerry Marian Terrace, Ballyheigue 9 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION SINGLE 963 Kerry Pinewood Estate, 6 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE Glannagilliagh, Caragh Lake, 964 Kerry 1 *N/A Q4‐2020 STAGE Killorglin (SRD)

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE 965 Kerry Knockawinna, Brosna, Co Kerry 1 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE Carrigcannon, Lyreacrumpane 966 Kerry 1 *N/A the scheme is fully STAGE (SRD) approved.

24/05/2021 69/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

967 SHIP CONSTRUCTION Kerry Cois Gallain, Killorglin 14 *N/A Q4‐2019

968 SHIP CONSTRUCTION Kerry Rathmore/Barraduff 20 *N/A Q4‐2019

969 SHIP CONSTRUCTION Kerry Ardbhearna, 22 *N/A Q4‐2018

970 SHIP CONSTRUCTION Kerry Bill Kinnerk Road, Tralee 4 *N/A Q1‐2018

971 SHIP CONSTRUCTION Kerry Cuirt Eaglaise, Milltown 8 *N/A Q4‐2019

972 SHIP CONSTRUCTION Kerry Killeen, Tralee 21 *N/A Q3‐2019

973 SHIP CONSTRUCTION Kerry Lixnaw 4 *N/A Q4‐2017

974 SHIP CONSTRUCTION Kerry The Park, Killarney 20 *N/A Q1‐2018

975 SHIP CONSTRUCTION Kerry Courthouse Lawn, Listowel 7 *N/A Q4‐2019

976 SHIP CONSTRUCTION Kerry Dreenagh, Ballyheigue (SRD) 1 *N/A Q1‐2017

977 SHIP CONSTRUCTION Kerry Glenach, Ballybunion 20 *N/A Q1‐2021

978 SHIP CONSTRUCTION Kerry Callinafercy, Milltown 1 *N/A Q4‐2018

979 SHIP CONSTRUCTION Kerry Cahernaboshina, Ventry 1 *N/A Q4‐2018

980 SHIP CONSTRUCTION Kerry An Carrigin, Tralee 28 *N/A Q4‐2020

24/05/2021 70/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

981 SHIP CONSTRUCTION Kerry Pinewood Estate, Killarney 1 *N/A Q4‐2018

982 SHIP CONSTRUCTION Kerry Drom West, Glenbeigh 1 *N/A Q4‐2020

983 SHIP CONSTRUCTION Kerry Meanus, Killorglin 1 *N/A Q3‐2019

984 SHIP CONSTRUCTION Kerry Tullig Beg, Killorglin 1 *N/A Q3‐2019

985 SHIP CONSTRUCTION Kerry Owngarry, Killorglin 1 *N/A Q4‐2019

986 SHIP CONSTRUCTION Kerry Lohercannon, Tralee 61 *N/A Q3‐2020

987 SHIP CONSTRUCTION Kerry BallinaKilly Lower, Glenbeigh 1 *N/A Q4‐2020

988 SHIP CONSTRUCTION Kerry Ashgrove, Listowel 1 *N/A Q3‐2017

989 SHIP CONSTRUCTION Kerry Cullenagh Upper, Beaufort 1 *N/A Q1‐2021

990 SHIP CONSTRUCTION Kerry Farranwilliam, Ardfert 22 *N/A Q3‐2019

991 SHIP CONSTRUCTION Kerry Ballyrickard, Tralee 21 *N/A Q3‐2020

992 SHIP CONSTRUCTION Kerry Croogorts, Tralee 30 *N/A Q3‐2020

993 SHIP CONSTRUCTION Kerry Rock Rd., Killarney 10 *N/A Q3‐2020

994 SHIP CONSTRUCTION Kerry Gortamullin, Kenmare (Phase 4) 14 *N/A Q1‐2021

24/05/2021 71/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

995 SHIP CONSTRUCTION Kerry Baile an Gharraí, Lixnaw (Phase 2) 10 *N/A Q1‐2020

996 SHIP CONSTRUCTION Kerry Woodview Place, Tarbert 22 *N/A Q1‐2021

Stage 3 approved Q1‐2021, the scheme is now 997 SHIP CONSTRUCTION Kerry Marconi South, Ballybunion 14 *N/A approved to proceed to tender.

998 SHIP CONSTRUCTION Kerry Rahoonane ‐ New Site, Tralee 8 *N/A Q1‐2021

Stage 2 approved Q2‐2020, 999 SHIP CONSTRUCTION Kerry Rusheen, Ballylongford 7 *N/A full design/tender being prepared.

1000 SHIP CONSTRUCTION Kerry Gortamullin, Kenmare (Phase 5) 14 *N/A Q1‐2021

1001 REGENERATION Kerry Croilar Na Mistaelach, Tralee 11 *N/A Q4‐2018

1002 REGENERATION Kerry Urban Terrace, Tralee 2 *N/A Q4‐2016

1003 REGENERATION Kerry Clonmore Road, Tralee 3 *N/A Q4‐2016

1004 REGENERATION Kerry St Martin's Park, Tralee 4 *N/A Q4‐2018

1005 REGENERATION Kerry Dingle Road, Tralee 1 *N/A Q2‐2018

1006 CAS CONSTRUCTION Kerry Armagh House, Killarney 6 Cluid Housing Association Q1‐2021

Kerry Emigrant Support 1007 CAS CONSTRUCTION Kerry 22 College Road, Castleisland 4 Q4‐2018 Housing Association Ltd

Chamfers Place (Mitchels road, 1008 CAS CONSTRUCTION Kerry 18 Cluid Housing Association Q4‐2020 Tralee)

24/05/2021 72/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Caherciveen Social 1009 CAS CONSTRUCTION Kerry The Parsonage, Caherciveen 5 Q4‐2018 Services (Housing) Ltd

The Presentation Convent, Social Action Group 1010 CAS CONSTRUCTION Kerry 4 Q3‐2020 Rathmore Rathmore

Ard Na Greine, Knockavota, 1011 CALF Turnkey Kerry 54 Cluid Housing Q4‐2020 Milltown, Co. Kerry (Phase 1)*

Barraduff, Killarney, Co. Kerry Co ‐ Operative Housing 1012 CALF Turnkey Kerry 15 Q4‐2020 (Phase 1)* Ireland Society Limited

Barraduff, Killarney, Co. Kerry Co ‐ Operative Housing 1013 CALF Turnkey Kerry 14 Q4‐2020 (Phase 2)* Ireland Society Limited

Barraduff, Killarney, Co. Kerry Co ‐ Operative Housing 1014 CALF Turnkey Kerry 14 Q4‐2020 (Phase 3) Ireland Society Limited

Barraduff, Killarney, Co. Kerry Co ‐ Operative Housing 1015 CALF Turnkey Kerry 13 Q1‐2021 (Phase 4)* Ireland Society Limited

Cahirdown Wood, Listowel, Co. 1016 CALF Turnkey Kerry 12 Cluid Housing Q3‐2020 Kerry (Phase 1)*

Cahirdown Wood, Listowel, Co. 1017 CALF Turnkey Kerry 26 Cluid Housing Q3‐2020 Kerry (Phase 2)

Cathair Lakes Farrantoreen Road, 1018 CALF Turnkey Kerry 5 Cluid Housing Q2‐2016 Killorglin, Co Kerry (Phase 1)

Deerpark Avenue, Tralee, Co. Co ‐ Operative Housing 1019 CALF Turnkey Kerry 4 Q3‐2020 Kerry (Phase 1) Ireland Society Limited

Derreen, Killarney, Co Kerry 1020 CALF Turnkey Kerry 61 Cluid Housing Q3‐2020 (Phase 1)*

Doon Road, Lisloose, Tralee, Co. Co ‐ Operative Housing 1021 CALF Turnkey Kerry 14 Q3‐2020 Kerry (Phase 1)* Ireland Society Limited

Dromcairn, Tralee, Co. Kerry 1022 CALF Turnkey Kerry 12 Cluid Housing Q4‐2020 (Phase 1)

24/05/2021 73/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Dun Ard, Road, 1023 CALF Turnkey Kerry 14 Respond Q4‐2018 Ballybunnion, Co Kerry (Phase 1)

Dun Ard, Doon Road, 1024 CALF Turnkey Kerry 2 Respond Q4‐2019 Ballybunnion, Co Kerry (Phase 2)

Dun Ard, Doon Road, 1025 CALF Turnkey Kerry 5 Respond Q2‐2020 Ballybunnion, Co Kerry (Phase 3)

Dun Ard, Doon Road, 1026 CALF Turnkey Kerry 1 Respond Q3‐2018 Ballybunnion, Co Kerry (Phase 4)

Fortfield, Tralee, Co. Kerry (Phase 1027 CALF Turnkey Kerry 15 Cluid Housing Q4‐2019 1)*

Hunters Lodge, Hunters Wood, 1028 CALF Turnkey Kerry Ballyseedy, Tralee, Co. Kerry 10 Cluid Housing Q2‐2020 (Phase 1)

Killeen, Abbeydorney Road, 1029 CALF Turnkey Kerry 17 Cluid Housing Q4‐2019 Tralee, Co. Kerry (Phase 1)*

Lawlers Hill, (formerly Commons Co ‐ Operative Housing 1030 CALF Turnkey Kerry East) Ardfert, Co. Kerry (Phase 12 Q2‐2020 Ireland Society Limited 1)*

Lawlers Hill, (formerly Commons Co ‐ Operative Housing 1031 CALF Turnkey Kerry 18 Q2‐2020 East) Ardfert, Co. Kerry (Phase 2) Ireland Society Limited

Lios Ard, Lisloose, Tralee, Co. 1032 CALF Turnkey Kerry 28 Cluid Housing Q4‐2019 Kerry (Phase 1)

Moanmore, Pound Road, 1033 CALF Turnkey Kerry 14 Cluid Housing Q2‐2020 Castleisland, Co. Kerry (Phase 1)*

Oakwood, Coolegrean, Killarney, 1034 CALF Turnkey Kerry 59 Cluid Housing Q3‐2019 Co. Kerry (Phase 1)

Sruthan na Saili, Derreen, Co. 1035 CALF Turnkey Kerry 22 Cluid Housing Q4‐2020 Kerry (Phase 1)*

The Grove, Dingle, Co. Kerry 1036 CALF Turnkey Kerry 20 Cluid Housing Q3‐2020 (Phase 1)*

24/05/2021 74/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1037 Kildare Bodkin Place, Kilmeague 16 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 1038 Kildare Drogheda Street, Monasterevin 6 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 1039 Kildare Oaktree, Tully Road, Kildare Town 8 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION Moore Abbey Court, 1040 Kildare 2 *N/A Q1‐2018 TURNKEY Monasterevin

SHIP CONSTRUCTION Drogheda Street, Monasterevin 1041 Kildare 7 *N/A Q1‐2018 TURNKEY (Phase 2)

SHIP CONSTRUCTION 1042 Kildare Moss Brook, Prosperous 2 *N/A Q1‐2018 TURNKEY

SHIP CONSTRUCTION Hawthorn Manor, Brockagh, Coill 1043 Kildare 2 *N/A Q4‐2018 TURNKEY Dubh

SHIP CONSTRUCTION 1044 Kildare Whitethorn Park, Allenwood 2 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 1045 Kildare The Pike, Castledermot 6 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1046 Kildare Grove Lane, Robertstown 3 *N/A Q1‐2020 TURNKEY

SHIP CONSTRUCTION 1047 Kildare Brookes Mill, Prosperous 5 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1048 Kildare The Green, Elsmore Naas 5 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1049 Kildare Oakwood Park, Derrinturn 10 *N/A Q1‐2019 TURNKEY

SHIP CONSTRUCTION 1050 Kildare Oakwood Park, Derrinturn 16 *N/A Q3‐2020 TURNKEY

24/05/2021 75/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1051 Kildare Beech Park Wood, Leixlip 4 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 1052 Kildare Oaktree, Tully Road, Kildare Town 18 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 1053 Kildare Oakwood Park, Derrinturn 10 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION Oaktree, Tully Road, Kildare Town 1054 Kildare 20 *N/A Q3‐2019 TURNKEY (Phase 2)

SHIP CONSTRUCTION 1055 Kildare Cluain Dara, Derrinturn, Kildare 1 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION Hawthorn Manor, Brockagh, Coill 1056 Kildare 3 *N/A Q4‐2019 TURNKEY Dubh

SHIP CONSTRUCTION 1057 Kildare School Walk, Allenwood 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1058 Kildare Stoneleigh, Naas 6 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1059 Kildare The Willows, Allenwood 1 *N/A Q1‐2020 TURNKEY

SHIP CONSTRUCTION 1060 Kildare The Willows, Allenwood 1 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1061 Kildare Barrack Close, Ballymore Eustace 2 *N/A Q2‐2020 TURNKEY

SHIP CONSTRUCTION Hawthorn Manor, Brockagh, Coill 1062 Kildare 6 *N/A Q2‐2020 TURNKEY Dubh

SHIP CONSTRUCTION 1063 Kildare Brookes Mill Prosperous 1 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1064 Kildare Greenfield House, Maynooth 1 *N/A Q4‐2019 TURNKEY

24/05/2021 76/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Crockaun Way, Brownstown 1065 Kildare 10 *N/A Q4‐2020 TURNKEY Manor, The Curragh

SHIP CONSTRUCTION 1066 Kildare Railway House, Dublin Road, Naas 3 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1067 Kildare Loughminane Green, Kildare Town 2 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Crockaun Way, Brownstown 1068 Kildare 26 *N/A Q4‐2020 TURNKEY Manor, The Curragh

SHIP CONSTRUCTION Crockaun Way, Brownstown 1069 Kildare 9 *N/A Q4‐2020 TURNKEY Manor, The Curragh

SHIP CONSTRUCTION 1070 Kildare Barrack Close, Ballymore Eustace 2 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION Hawthorn Manor, Brockagh, Coill 1071 Kildare 9 *N/A Q3‐2020 TURNKEY Dubh

SHIP CONSTRUCTION 1072 Kildare Temple Mills, Rathangan 2 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1073 Kildare Longstone, Craddockstown, Naas 5 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Coolaghknock Green, Kildare 1074 Kildare 4 *N/A Q4‐2020 TURNKEY Town

SHIP CONSTRUCTION Hawthorn Manor, Brockagh, Coill 1075 Kildare 6 *N/A Q4‐2020 TURNKEY Dubh

SHIP CONSTRUCTION 1076 Kildare Oakwood Park, Derrinturm 3 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1077 Kildare The Willows, Allenwood 2 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1078 Kildare The Willows, Allenwood 2 *N/A Q4‐2019 TURNKEY

24/05/2021 77/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION Straffan Road, Greenfield, 1079 Kildare 2 *N/A the scheme is fully TURNKEY Maynooth approved.

SHIP CONSTRUCTION 1080 Kildare Main Street, Robertstown 2 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Coolaghknock Green, Kildare 1081 Kildare 2 *N/A Q1‐2021 TURNKEY Town

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 1082 Kildare Abbotsfield Clane 3 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 1083 Kildare Old Mill Race, Monasterevin 9 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1084 Kildare Kildangan 20 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Coolaghknock Green, Kildare 1085 Kildare 2 *N/A Q1‐2020 TURNKEY Town

Stage 1 approved Q4‐2017, SHIP CONSTRUCTION RAPID 1086 Kildare Old Greenfield Road, Maynooth 47 *N/A outline design and costs VOLUMETRIC being prepared.

Stage 3 approved Q1‐2021, the scheme is now 1087 SHIP CONSTRUCTION Kildare Hillview Terrace, Narraghmore 4 *N/A approved to proceed to tender. Stage 3 approved Q3‐2019, the scheme is now 1088 SHIP CONSTRUCTION Kildare Athgarvan Village 18 *N/A approved to proceed to tender.

Stage 1 approved Q1‐2016, 1089 SHIP CONSTRUCTION Kildare Rathasker Road, Naas 48 *N/A outline design and costs being prepared.

Dunmurry Rise, Bishopsland, 1090 SHIP CONSTRUCTION Kildare 32 *N/A Q3‐2019 Kildare Town

1091 SHIP CONSTRUCTION Kildare Anne Street, Prosperous 12 *N/A Q3‐2020

1092 SHIP CONSTRUCTION Kildare Beechgrove, Rathangan 18 *N/A Q4‐2019

24/05/2021 78/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1093 SHIP CONSTRUCTION Kildare Kilcock (Phase 2.1) 6 *N/A Q4‐2017

1094 SHIP CONSTRUCTION Kildare Athgarvan Road, Newbridge 13 *N/A Q3‐2018

Stage 3 approved Q1‐2021, the scheme is now 1095 SHIP CONSTRUCTION Kildare Newtown House, Leixlip 4 *N/A approved to proceed to tender. Stage 3 approved Q1‐2021, the scheme is now 1096 SHIP CONSTRUCTION Kildare Coill Dubh 10 *N/A approved to proceed to tender.

Stage 1 approved Q4‐2017, 1097 SHIP CONSTRUCTION Kildare Ardclough Road, Celbridge 36 *N/A outline design and costs being prepared.

1098 SHIP CONSTRUCTION Kildare Kilcock (Phase 2.2) 13 *N/A Q1‐2018

Stage 1 approved Q2‐2020, 1099 SHIP CONSTRUCTION Kildare Ambassador Site, Kill 33 *N/A outline design and costs being prepared.

Stage 1 approved Q2‐2020, 1100 SHIP CONSTRUCTION Kildare Carbury 5 *N/A outline design and costs being prepared.

Stage 1 approved Q2‐2020, 1101 SHIP CONSTRUCTION Kildare St. Evins Park Monasterevin 16 *N/A outline design and costs being prepared.

Stage 2 approved Q1‐2021, 1102 SHIP CONSTRUCTION Kildare Castle Park, Athy 4 *N/A full design/tender being prepared.

Stage 1 approved Q4‐2020, 1103 SHIP CONSTRUCTION Kildare Oldtown Mill, Celbridge 57 *N/A outline design and costs being prepared.

KARE Promoting Inclusion Stage 2 approved Q2‐2018, 1104 CAS CONSTRUCTION Kildare Craddockstown, Naas 3 for People with full design/tender being Intellectual Disabilities prepared.

Stage 2 approved Q4‐2017, Camphill Communities of 1105 CAS CONSTRUCTION Kildare Main St., Kilcullen 4 full design/tender being Ireland prepared.

KARE Promoting Inclusion Stage 2 approved Q4‐2020, 1106 CAS CONSTRUCTION Kildare El Kantara, Newbridge 2 for People with full design/tender being Intellectual Disabilities prepared.

24/05/2021 79/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1107 CAS CONSTRUCTION Kildare Jigginstown House, Naas 12 Homeless Care Ltd Q4‐2019

Stage 1 approved Q4‐2019, St. John's Convent, New Street, Sophia Housing 1108 CAS CONSTRUCTION Kildare 28 outline design and costs Rathangan Association Ltd being prepared.

Stage 1 approved Q3‐2020, 1109 CAS CONSTRUCTION Kildare Dominican Lands, Athy 30 Cluid Housing Association outline design and costs being prepared.

Bellingsfield, Naas, Kildare (Phase 1110 CALF Turnkey Kildare 10 Respond Q4‐2018 1)*

Carton Grove, Maynooth, Co. Clanmil Housing 1111 CALF Turnkey Kildare 5 Q4‐2018 Kildare (Phase 1)* Association Ireland

Castle Farm, Jigginstown, Naas, 1112 CALF Turnkey Kildare 8 Túath Housing Association Q4‐2019 Co. Kildare (Phase 1)

Castle Farm, Naas, Co. Kildare 1113 CALF Turnkey Kildare 8 Túath Housing Association Q2‐2019 (Phase 1)*

Castlefen, Castlesize, Sallins, Co. 1114 CALF Construction Kildare 29 Túath Housing Association Q1‐2020 Kildare (Phase 1)

Cathedral Apartments, Firecastle Cill Dara Housing 1115 CALF Turnkey Kildare Lane, Kildare Town, Co. Kildare 6 Q4‐2019 Association (Phase 1)*

Cathedral Apartments, Firecastle Cill Dara Housing 1116 CALF Turnkey Kildare Lane, Kildare Town, Co. Kildare 11 Q4‐2019 Association (Phase 2)*

Elsmore, Jigginstown and 1117 CALF Turnkey Kildare Oakpark, Craddockstown, Naas, 26 Túath Housing Association Q4‐2019 Kildare (Phase 1)*

Elsmore, Jigginstown and 1118 CALF Turnkey Kildare Oakpark, Craddockstown, Naas, 17 Túath Housing Association Q2‐2018 Kildare (Phase 2)*

Elsmore, Jigginstown, Nass, Co. 1119 CALF Turnkey Kildare 8 Túath Housing Association Q4‐2018 Kildare (Phase 1)*

Elsmore, Jigginstown, Nass, Co. 1120 CALF Turnkey Kildare 3 Túath Housing Association Q3‐2019 Kildare (Phase 2)*

24/05/2021 80/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Fenton Green, Kilcock, Co Kildare 1121 CALF Turnkey Kildare 18 Túath Housing Association Q1‐2019 (Phase 1)

Fenton Green, Kilcock, Co Kildare 1122 CALF Turnkey Kildare 6 Túath Housing Association Q1‐2019 (Phase 2)

Fenton Green, Kilcock, Co Kildare 1123 CALF Turnkey Kildare 6 Túath Housing Association Q1‐2019 (Phase 3)

Fenton Green, Kilcock, Co Kildare 1124 CALF Turnkey Kildare 6 Túath Housing Association Q2‐2019 (Phase 4)

Fenton Green, Kilcock, Co Kildare 1125 CALF Turnkey Kildare 4 Túath Housing Association Q2‐2019 (Phase 5)

Fenton Green, Kilcock, Co Kildare 1126 CALF Turnkey Kildare 5 Túath Housing Association Q3‐2019 (Phase 6)

Fenton Green, Kilcock, Co Kildare 1127 CALF Turnkey Kildare 18 Túath Housing Association Q4‐2019 (Phase 7)*

Flinters Field (Phase 2), Athy, Co. 1128 CALF Construction Kildare 35 Respond Q1‐2021 Kildare (Phase 1)

Grand Canal Wood, Allenwood, 1129 CALF Turnkey Kildare 21 Cluid Housing Q1‐2021 Co. Kildare (Phase 1)*

Grand Canal Wood, Allenwood, 1130 CALF Turnkey Kildare 19 Cluid Housing Q3‐2018 Co. Kildare (Phase 2)

Hawthorn Manor, Brockagh, Coill 1131 CALF Turnkey Kildare 5 Oaklee Housing Q4‐2019 Dubh, Co. Kildare (Phase 1)*

Kilbelin Abbey, Kildare, Phase 1 1132 CALF Turnkey Kildare 4 Cluid Housing Q1‐2021 (Phase 1)*

Kilbelin Abbey, Kildare, Phase 2 1133 CALF Turnkey Kildare 4 Cluid Housing Q2‐2019 (Phase 1)*

Ledwill Park, Kilcock, Co. Kildare 1134 CALF Turnkey Kildare 31 Cluid Housing Q4‐2019 (Phase 1)*

24/05/2021 81/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Leinster Square, Dublin Street, Clanmil Housing 1135 CALF Turnkey Kildare Kildare Town, Co Kildare (Phase 4 Q1‐2019 Association Ireland 1)*

Loughlion, Kildare Town, Kildare Co ‐ Operative Housing 1136 CALF Turnkey Kildare 14 Q4‐2020 (Phase 1) Ireland Society Limited

Loughlion, Kildare Town, Kildare Co ‐ Operative Housing 1137 CALF Turnkey Kildare 17 Q4‐2020 (Phase 2)* Ireland Society Limited

Loughlion, Kildare Town, Kildare Co ‐ Operative Housing 1138 CALF Turnkey Kildare 16 Q1‐2021 (Phase 3)* Ireland Society Limited

Loughlion, Kildare Town, Kildare Co ‐ Operative Housing 1139 CALF Turnkey Kildare 16 Q3‐2019 (Phase 4) Ireland Society Limited

Loughlion, Kildare Town, Kildare Co ‐ Operative Housing 1140 CALF Turnkey Kildare 16 Q3‐2019 (Phase 5)* Ireland Society Limited

Main Street, Prosperous, Clane, Clanmil Housing 1141 CALF Turnkey Kildare 16 Q3‐2020 Co. Kildare (Phase 1)* Association Ireland

Mariavilla and Elsmore, Kildare 1142 CALF Turnkey Kildare 15 Túath Housing Association Q4‐2019 (Phase 1)*

Millfield Manor, Newbridge, Co. 1143 CALF Turnkey Kildare 19 Cluid Housing Q3‐2018 Kildare (Phase 1)*

Morristown, Newbridge, Co 1144 CALF Turnkey Kildare 14 Cluid Housing Q1‐2018 Kildare (Phase 1)

Morristown, Newbridge, Co. 1145 CALF Turnkey Kildare 4 Cluid Housing Q2‐2018 Kildare (Phase 1)*

Oakpark, Craddockstown, Kildare 1146 CALF Turnkey Kildare 6 Túath Housing Association Q4‐2020 (Phase 1)

Oaktree, Tully Road, Kildare Town 1147 CALF Turnkey Kildare 10 Túath Housing Association Q2‐2018 (Phase 1)*

Oaktree, Tully Road, Kildare Town 1148 CALF Turnkey Kildare 7 Túath Housing Association Q3‐2018 (Phase 2)*

24/05/2021 82/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Phase 2, White Oaks, Newbridge, 1149 CALF Turnkey Kildare 36 Cluid Housing Q4‐2019 Kildare (Phase 1)

Revised Rye Abbey, Kilcock, Co 1150 CALF Turnkey Kildare Kildare (apts) 33 Cluid Housing Q2‐2017 (Phase 1)

Robertstown, Naas , Co.Kildare Co ‐ Operative Housing 1151 CALF Turnkey Kildare 5 Q2‐2020 (Phase 1) Ireland Society Limited

Roseberry Hill, Newbridge (Phase 1152 CALF Turnkey Kildare 13 Túath Housing Association Q2‐2017 1)

Roseberry Hill, Newbridge (Phase 1153 CALF Turnkey Kildare 16 Túath Housing Association Q4‐2017 2)

Roseberry Hill, Newbridge (Phase 1154 CALF Turnkey Kildare 16 Túath Housing Association Q1‐2018 3)

Rye Abbey, Kilcock ‐ revised 1155 CALF Turnkey Kildare 4 Cluid Housing Q2‐2017 (houses) (Phase 1)

The Arches, Castlefarm, Naas, Co. 1156 CALF Turnkey Kildare 4 Túath Housing Association Q4‐2020 Kildare (Phase 1)*

The Paddocks, Morristown, 1157 CALF Turnkey Kildare 5 Cluid Housing Q4‐2019 Newbridge, Kildare (Phase 1)*

The Paddocks, Morristown, 1158 CALF Turnkey Kildare 3 Cluid Housing Q4‐2020 Newbridge, Kildare (Phase 2)*

The Paddocks, Morristown, 1159 CALF Turnkey Kildare 16 Cluid Housing Q4‐2018 Newbridge, Kildare (Phase 3)*

The Paddocks, Newbridge, Co 1160 CALF Turnkey Kildare 18 Cluid Housing Q4‐2020 Kildare (Phase 1)

The Paddocks, Newbridge, Kildare 1161 CALF Turnkey Kildare 26 Cluid Housing Q2‐2020 (Phase 1)

The Paddocks, Newbridge, Kildare 1162 CALF Turnkey Kildare 33 Cluid Housing Q2‐2020 (Phase 2)

24/05/2021 83/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

The Vestry, Glebelands, Athy, Co. 1163 CALF Turnkey Kildare 18 Respond Q4‐2019 Kildare (Phase 1)

The Vestry, Glebelands, Athy, Co. 1164 CALF Turnkey Kildare 18 Respond Q3‐2019 Kildare (Phase 1)*

The Vestry, Glebelands, Athy, Co. 1165 CALF Turnkey Kildare 32 Respond Q2‐2020 Kildare (Phase 2)

White Oaks, Rickardstown, 1166 CALF Turnkey Kildare 14 Cluid Housing Q4‐2018 Newbridge, Co. Kildare (Phase 1)*

White Oaks, Rickardstown, 1167 CALF Turnkey Kildare 24 Cluid Housing Q4‐2018 Newbridge, Co. Kildare (Phase 2)

White Oaks, Rickardstown, 1168 CALF Turnkey Kildare 20 Cluid Housing Q1‐2019 Newbridge, Co. Kildare (Phase 3)

White Oaks, Rickardstown, 1169 CALF Turnkey Kildare 2 Cluid Housing Q4‐2019 Newbridge, Co. Kildare (Phase 4)

1170 CALF Turnkey Kildare Willouise, Sallins, Kildare (Phase 1) 31 Túath Housing Association Q4‐2020

PUBLIC PRIVATE PARTNERSHIP 1171 Kildare Craddockstown, Naas (Phase 1) 36 *N/A Q2‐2020 (Bundle 1)

PUBLIC PRIVATE PARTNERSHIP 1172 Kildare Craddockstown, Naas (Phase 2) 38 *N/A Q3‐2020 (Bundle 1)

PUBLIC PRIVATE PARTNERSHIP 1173 Kildare Butterstream, Clane 77 *N/A Q1‐2019 (Bundle 2)

SHIP CONSTRUCTION 1174 Togher Way, Urlingford 11 *N/A Q2‐2017 TURNKEY

SHIP CONSTRUCTION Newpark, Castlecomer Road, 1175 Kilkenny 7 *N/A Q1‐2017 TURNKEY Kilkenny

SHIP CONSTRUCTION 1176 Kilkenny Abbeygate, Ferrybank 8 *N/A Q1‐2018 TURNKEY

24/05/2021 84/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1177 Kilkenny Togher Way, Urlingford 5 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 1178 Kilkenny Abbeygate, Ferrybank (Phase 2) 1 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 1179 Kilkenny Togher Way, Urlingford (Phase 3) 18 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1180 Kilkenny New Road, Mooncoin 4 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 1181 Kilkenny Chapel Street, Mooncoin 2 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 1182 Kilkenny Ogenty, Gowran 12 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Pennefeather Court, Hebron 1183 Kilkenny 8 *N/A Q3‐2020 TURNKEY Road, Kilkenny

SHIP CONSTRUCTION Limegrove, Oakridge, Ferrybank, 1184 Kilkenny 4 *N/A Q2‐2020 TURNKEY Co. Kilkenny

SHIP CONSTRUCTION Pennefeather Green, Hebron 1185 Kilkenny 58 *N/A Q3‐2020 TURNKEY Road, Kilkenny

SHIP CONSTRUCTION 1186 Kilkenny Lower Kilmacow, Co. Kilkenny 16 *N/A Q3‐2020 TURNKEY

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Limegrove, Ferrybank, Co. 1187 Kilkenny 15 *N/A the scheme is fully TURNKEY Kilkenny approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1188 Kilkenny Piltown, Kilkenny 4 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION SINGLE Group Home Cloghabrody, 1189 Kilkenny 4 *N/A Q3‐2020 STAGE Thomastown

SHIP CONSTRUCTION SINGLE 1190 Kilkenny Inchacarron, Mullinavat 2 *N/A Q3‐2019 STAGE

24/05/2021 85/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION SINGLE 1191 Kilkenny Shanganny, Jenkinstown 2 *N/A Q4‐2019 STAGE

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION SINGLE Old Fire Station, 1192 Kilkenny 2 *N/A the scheme is fully STAGE Graiguenamanagh approved.

1193 SHIP CONSTRUCTION Kilkenny Blackstaff House, Callan 4 *N/A Q4‐2019

1194 SHIP CONSTRUCTION Kilkenny Barna, Freshford 1 *N/A Q2‐2018

Stage 3 approved Q1‐2020, the scheme is now 1195 SHIP CONSTRUCTION Kilkenny 10 Golf Links Road, Kilkenny 6 *N/A approved to proceed to tender.

1196 SHIP CONSTRUCTION Kilkenny Main Street, Piltown 17 *N/A Q4‐2020

1197 SHIP CONSTRUCTION Kilkenny Station Road, Ballyragget 22 *N/A Q3‐2019

1198 SHIP CONSTRUCTION Kilkenny Bolton, Callan 38 *N/A Q3‐2020

1199 SHIP CONSTRUCTION Kilkenny Donaguile, Castlecomer 33 *N/A Q1‐2019

1200 SHIP CONSTRUCTION Kilkenny Rosehill, Kells Road, Kilkenny 6 *N/A Q1‐2017

1201 SHIP CONSTRUCTION Kilkenny Gaol Road, Kilkenny 10 *N/A Q3‐2016

1202 SHIP CONSTRUCTION Kilkenny Greensbridge House 5 *N/A Q4‐2018

1203 SHIP CONSTRUCTION Kilkenny The Broguemaker, Kilkenny 18 *N/A Q2‐2020

Stage 3 approved Q1‐2021, Ladywell, Thomastown, Co. the scheme is now 1204 SHIP CONSTRUCTION Kilkenny 25 *N/A Kilkenny approved to proceed to tender.

24/05/2021 86/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q2‐2019, Crokers Hill, Kennyswell Road, 1205 SHIP CONSTRUCTION Kilkenny 88 *N/A full design/tender being Kilkenny prepared.

Stage 1 approved Q1‐2020, 1206 SHIP CONSTRUCTION Kilkenny Ayrfield 9 *N/A outline design and costs being prepared.

Stage 1 approved Q1‐2020, Canal Road, Johnstown, Co. 1207 SHIP CONSTRUCTION Kilkenny 5 *N/A outline design and costs Kilkenny Project 1 being prepared.

Stage 1 approved Q1‐2020, 1208 SHIP CONSTRUCTION Kilkenny Canal Road Johnstown Project 2 2 *N/A outline design and costs being prepared.

Stage 1 approved Q1‐2020, 1209 SHIP CONSTRUCTION Kilkenny Canal Road Johnstown Project 3 4 *N/A outline design and costs being prepared.

1210 CAS CONSTRUCTION TURNKEY Kilkenny Golf Links Road, Kilkenny 15 Respond Q3‐2019

Stage 3 approved Q4‐2020, Kingsriver Housing the scheme is now 1211 CAS CONSTRUCTION Kilkenny Kingsriver, Ennisnag 4 Association Limited approved to proceed to tender.

SOS Kilkenny Housing 1212 CAS CONSTRUCTION Kilkenny Garrin Green 6 Q4‐2018 Association Ltd

Waterford Dove Housing 1213 CAS CONSTRUCTION Kilkenny Hazelbrook, Newrath 2 Q1‐2018 Association

Good Shepherd Centre ‐ Wing The Good Shepherd 1214 CAS CONSTRUCTION Kilkenny 12 Q4‐2018 1952 Centre (Kilkenny) Ltd

Camphill Communities of 1215 CAS CONSTRUCTION Kilkenny Brooke House, Thomastown 5 Q3‐2017 Ireland

1216 CAS CONSTRUCTION Kilkenny Friary Walk, Callan 12 Cluid Housing Association Q3‐2016

Garden Cottage, The Workhouse, Camphill Communities of 1217 CAS CONSTRUCTION Kilkenny 1 Q4‐2017 Callan Ireland

Stage 2 approved Q4‐2020, Red Barn, Patrick Street, Good Shepherd Services 1218 CAS CONSTRUCTION Kilkenny 12 full design/tender being Ballyragget Ltd prepared.

24/05/2021 87/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1219 CAS CONSTRUCTION Kilkenny Smith's Road, Ballyraggett 4 Oaklee Housing Trust Q4‐2018

Stage 1 approved Q3‐2017, Camphill Communities of 1220 CAS CONSTRUCTION Kilkenny Fennelly's Lane Jerpoint 2 outline design and costs Ireland being prepared.

Stage 3 approved Q3‐2020, Good Shepherd Services the scheme is now 1221 CAS CONSTRUCTION Kilkenny 8/9 Kilkenny Street, Castlecomer 3 Ltd approved to proceed to tender. Stage 3 approved Q1‐2021, Good Shepherd Services the scheme is now 1222 CAS CONSTRUCTION Kilkenny 19/21 Blackmill Street, Kilkenny 12 Ltd approved to proceed to tender.

Stage 4 approved Q4‐2020, Brother Thomas Place, Church Good Shepherd Services 1223 CAS CONSTRUCTION Kilkenny 12 the scheme is fully Lane, Kilkenny Ltd approved.

Good Shepherd Services 1224 CAS CONSTRUCTION Kilkenny Bridge Street, Callan 6 Q4‐2019 Ltd

Camphill Communities of 1225 CAS CONSTRUCTION Kilkenny Grennan Villa, Thomastown 5 Q3‐2020 Ireland

Stage 3 approved Q4‐2020, Fiennes Court, William Street, Good Shepherd Services the scheme is now 1226 CAS CONSTRUCTION Kilkenny 7 Kilkenny Ltd approved to proceed to tender.

Stage 1 approved Q4‐2019, St. John of god Convent, College Sophia Housing 1227 CAS CONSTRUCTION Kilkenny 12 outline design and costs Road, Kilkenny Association Ltd being prepared.

Stage 2 approved Q4‐2020, The Round House, Kells, Co. SOS Kilkenny Housing 1228 CAS CONSTRUCTION Kilkenny 4 full design/tender being Kilkenny Association Ltd prepared.

Stage 1 approved Q3‐2020, Ladywell Street, Thomastown, Co. Good Shepherd Services 1229 CAS CONSTRUCTION Kilkenny 6 outline design and costs Kilkenny Ltd being prepared.

Stage 1 approved Q4‐2020, Dinan lodge,Suttonsrath, 1230 CAS CONSTRUCTION Kilkenny 1 Housing Agency outline design and costs Jenkinstown, Co. Kilkenny being prepared.

Maise Stage 1 approved Q4‐2020, Good Shepherd Services 1231 CAS CONSTRUCTION Kilkenny Belle,Seixeslough,Newpark,Kilken 1 outline design and costs Ltd ny being prepared.

Stage 1 approved Q4‐2020, Kilkenny Voluntary 1232 CAS CONSTRUCTION Kilkenny Callan Road, Kilkenny 12 outline design and costs Housing Association being prepared.

24/05/2021 88/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Co ‐ Operative Housing 1233 CALF Turnkey Kilkenny Castlehyde, Rosbercon (Phase 1) 4 Q4‐2018 Ireland Society Limited

Co ‐ Operative Housing 1234 CALF Turnkey Kilkenny Castlehyde, Rosbercon (Phase 2) 6 Q4‐2018 Ireland Society Limited

Cois Na Bearu, Graiguenemanagh, Co ‐ Operative Housing 1235 CALF Turnkey Kilkenny 14 Q1‐2021 Kilkenny (Phase 1) Ireland Society Limited

Golf Links Road, Kilkenny (Phase 1236 CALF Turnkey Kilkenny 39 Respond Q4‐2019 1)*

Logan Square, Thomastown, Co 1237 CALF Turnkey Kilkenny 16 Oaklee Housing Q2‐2017 Kilkenny (Phase 1)*

Love Lane, Castlecomer, Co. Co ‐ Operative Housing 1238 CALF Turnkey Kilkenny 4 Q3‐2019 Kilkenny (Phase 1) Ireland Society Limited

Margaret’s Field, Callan Road, 1239 CALF Turnkey Kilkenny 40 Respond Q1‐2019 Kilkenny City (Phase 1)

1240 CALF Turnkey Kilkenny Nuncio Road, Kilkenny (Phase 1) 28 Respond Q4‐2020

1241 CALF Turnkey Kilkenny Nuncio Road, Kilkenny (Phase 2)* 22 Respond Q4‐2018

O’Loughlin Court, Kilkenny (Phase 1242 CALF Turnkey Kilkenny 2 Respond Q4‐2018 1)

Orchard Close, Kilkenny (Phase 1243 CALF Turnkey Kilkenny 23 Cluid Housing Q4‐2020 1)*

Park Lane, Friary Walk, Callan, Co 1244 CALF Construction Kilkenny 16 Cluid Housing Q2‐2019 Kilkenny (Phase 1)*

Side Road, Moneenroe, 1245 CALF Turnkey Kilkenny Castlecomer, Co. Kilkenny (Phase 9 Oaklee Housing Q3‐2018 1)

1246 CALF Construction Kilkenny Walkin St Kilkenny (Phase 1) 27 Oaklee Housing Q4‐2019

24/05/2021 89/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1247 Laois Priory, Borris in Ossory 6 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1248 Laois Priory, Borris in Ossory 5 *N/A Q2‐2020 TURNKEY

SHIP CONSTRUCTION 1249 Laois Clonaslee 7 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 1250 Laois Church Ave., Stradbally 31 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION SINGLE 1251 Laois Harpurs Lane, Portlaoise 1 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1252 Laois Hillview, Portlaoise 2 *N/A Q4‐2020 STAGE

SHIP CONSTRUCTION SINGLE 1253 Laois Coolroe, Ballybrittas 1 *N/A Q4‐2020 STAGE

SHIP CONSTRUCTION SINGLE 1254 Laois The Orchard, Stradbally 6 *N/A Q1‐2020 STAGE

1255 SHIP CONSTRUCTION Laois Moore Street, Rathdowney 6 *N/A Q3‐2020

1256 SHIP CONSTRUCTION Laois Ballymorris Road, Portarlington 22 *N/A Q3‐2019

1257 SHIP CONSTRUCTION Laois Gleann na Glaise, Ballyroan 10 *N/A Q4‐2020

1258 SHIP CONSTRUCTION Laois Pattison Est. Mountmellick 10 *N/A Q4‐2020

1259 SHIP CONSTRUCTION Laois Shannon Street, Mountrath 6 *N/A Q1‐2020

Conniberry Way, Old Knockmay 1260 SHIP CONSTRUCTION Laois 33 *N/A Q2‐2018 Road, Portlaoise

24/05/2021 90/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q3‐2018, 1261 SHIP CONSTRUCTION Laois Harbour Court, Mountmellick 6 *N/A outline design and costs being prepared.

Stage 2 approved Q2‐2020, 1262 SHIP CONSTRUCTION Laois Mooreville, Rathdowney 7 *N/A full design/tender being prepared.

1263 SHIP CONSTRUCTION Laois Sean Doire, Cork Road, Durrow 22 *N/A Q4‐2020

Stage 3 approved Q3‐2020, the scheme is now 1264 SHIP CONSTRUCTION Laois St Kieran's Park, Errill 14 *N/A approved to proceed to tender.

Stage 1 approved Q3‐2019, 1265 SHIP CONSTRUCTION Laois Clonrooske, Knockmay 11 *N/A outline design and costs being prepared.

1266 SHIP CONSTRUCTION Laois Carraig Glas, Stradbally 26 *N/A Q1‐2021

Stage 1 approved Q2‐2020, 1267 SHIP CONSTRUCTION Laois Stradbally Road, Portlaoise 50 *N/A outline design and costs being prepared.

Stage 1 approved Q1‐2020, 1268 SHIP CONSTRUCTION Laois Iona 9 *N/A outline design and costs being prepared.

Stage 2 approved Q1‐2021, Presentation Convent & Lands, Sophia Housing 1269 CAS CONSTRUCTION Laois 51 full design/tender being Portlaoise, Association Ltd prepared.

Stage 1 approved Q3‐2020, 1270 CAS CONSTRUCTION Laois County Hotel, Portlaoise 10 Cluid Housing Association outline design and costs being prepared.

Ballickmoyler, Graiguecullen, Laois Co ‐ Operative Housing 1271 CALF Turnkey Laois 20 Q4‐2020 (Phase 1)* Ireland Society Limited

Ballymorris Court, Portarlington, 1272 CALF Turnkey Laois 46 Cluid Housing Q1‐2021 Co Laois (Phase 1)

Bellingham, Portlaoise 1273 CALF Turnkey Laois 4 Cluid Housing Q3‐2019 (Phase 1)

Bellingham, Portlaoise 1274 CALF Turnkey Laois 6 Cluid Housing Q4‐2019 (Phase 2)

24/05/2021 91/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Bellingham, Portlaoise 1275 CALF Turnkey Laois 5 Cluid Housing Q2‐2020 (Phase 3)

Bellingham, Portlaoise 1276 CALF Turnkey Laois 9 Cluid Housing Q1‐2021 (Phase 4)*

Bellingham, Portlaoise 1277 CALF Turnkey Laois 6 Cluid Housing Q1‐2017 (Phase 5)*

Borris Road, Portlaoise, Co. Laois 1278 CALF Turnkey Laois 9 Túath Housing Association Q3‐2020 (Phase 1)*

Borris Road, Portlaoise, Co. Laois 1279 CALF Turnkey Laois 8 Túath Housing Association Q3‐2020 (Phase 2)*

Borris Road, Portlaoise, Co. Laois 1280 CALF Turnkey Laois 10 Túath Housing Association Q4‐2020 (Phase 3)

Borris Road, Portlaoise, Co. Laois 1281 CALF Turnkey Laois 9 Túath Housing Association Q1‐2021 (Phase 4)

Clonroosk Abbey, Portlaoise, Co. 1282 CALF Turnkey Laois 14 Cluid Housing Q4‐2018 Laois (Phase 1)

Clonroosk Abbey, Portlaoise, Co. 1283 CALF Turnkey Laois 6 Cluid Housing Q4‐2018 Laois (Phase 2)*

Clonroosk Abbey, Portlaoise, Co. 1284 CALF Turnkey Laois 12 Cluid Housing Q4‐2018 Laois (Phase 3)

Corrig Glen, Station Road, 1285 CALF Turnkey Laois 17 Túath Housing Association Q3‐2018 Portarlington, Co. Laois (Phase 1)

Corrig Glen, Station Road, 1286 CALF Turnkey Laois 9 Túath Housing Association Q4‐2018 Portarlington, Co. Laois (Phase 2)

Corrig Glen, Station Road, 1287 CALF Turnkey Laois 13 Túath Housing Association Q4‐2018 Portarlington, Co. Laois (Phase 3)

Doirinn Alainn, Ballylynan, Co. North & East Housing 1288 CALF Turnkey Laois 2 Q3‐2020 Laois (Phase 1) Association Ltd

24/05/2021 92/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Doirinn Alainn, Ballylynan, Co. North & East Housing 1289 CALF Turnkey Laois 4 Q4‐2020 Laois (Phase 2) Association Ltd

Doirinn Alainn, Ballylynan, Co. North & East Housing 1290 CALF Turnkey Laois 6 Q1‐2019 Laois (Phase 3)* Association Ltd

Droimnin, Stradbally, Co Laois 1291 CALF Turnkey Laois 6 Cluid Housing Q3‐2018 (Phase 1)

Harpurs Lane, Portlaoise, Co. Laois 1292 CALF Turnkey Laois 44 Respond Q1‐2021 (Phase 1)*

Holdbrook, Portlaoise, Co. Laois 1293 CALF Turnkey Laois 10 Cluid Housing Q3‐2018 (Phase 1)

Holdbrook, Portlaoise, Co. Laois 1294 CALF Turnkey Laois 10 Cluid Housing Q3‐2018 (Phase 2)

Kirwan Park, Mountmellick, Co 1295 CALF Construction Laois 2 Cluid Housing Q2‐2018 Laois (Phase 1)

Knockmay Mews, Old Knockmay 1296 CALF Turnkey Laois Road, Portlaoise, Co. Laois (Phase 3 Túath Housing Association Q3‐2020 1)

Lake Drive, Kilminchy, Portlaoise, Co ‐ Operative Housing 1297 CALF Turnkey Laois 8 Q3‐2019 Co. Laois (Phase 1) Ireland Society Limited

Lake Drive, Kilminchy, Portlaoise, Co ‐ Operative Housing 1298 CALF Turnkey Laois 2 Q3‐2019 Co. Laois (Phase 2) Ireland Society Limited

Main Street, Stradbally, Co. Laois North & East Housing 1299 CALF Turnkey Laois 16 Q3‐2020 (Phase 1) Association Ltd

Phase 2 The Glen, Kilnacourt, Co ‐ Operative Housing 1300 CALF Turnkey Laois 18 Q2‐2020 Portarlington, Co Laois (Phase 1) Ireland Society Limited

POST TENDER ‐ Cluinin 1301 CALF Construction Laois 11 Oaklee Housing Q1‐2018 Mountrath, Co. Laois (Phase 1)

South Dublin Road, Portlaoise, Co. Co ‐ Operative Housing 1302 CALF Turnkey Laois 13 Q1‐2020 Laois (Phase 1) Ireland Society Limited

24/05/2021 93/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

South Dublin Road, Portlaoise, Co. Co ‐ Operative Housing 1303 CALF Turnkey Laois 14 Q1‐2020 Laois (Phase 2) Ireland Society Limited

South Dublin Road, Portlaoise, Co. Co ‐ Operative Housing 1304 CALF Turnkey Laois 9 Q1‐2020 Laois (Phase 3)* Ireland Society Limited

Spa Street, Droughill, 1305 CALF Turnkey Laois 26 Oaklee Housing Q4‐2020 Portarlington, Co. Laois (Phase 1)*

The Glen, Kilnacourt, Co ‐ Operative Housing 1306 CALF Turnkey Laois 18 Q2‐2020 Portarlington, Co. Laois (Phase 1) Ireland Society Limited

The Meadows, Mountrath Road, 1307 CALF Turnkey Laois 48 Cluid Housing Q1‐2021 Portlaoise, Co. Laois (Phase 1)*

Wilton Lawns, Portarlington, Co. 1308 CALF Turnkey Laois 2 Respond Q1‐2021 Laois (Phase 1)

SHIP CONSTRUCTION 1309 Leitrim Roosky 7 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1310 Leitrim Drumshanbo 9 *N/A Q3‐2019 TURNKEY

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 1311 Leitrim Church Lane, Ballinamore 9 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 1312 Leitrim Druminshingore, Newtowngore 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 1313 Leitrim Carraig Breac, Drumshanbo 5 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 1314 Leitrim Oakgrove, Kinlough 5 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1315 Leitrim Ard na Drise, Mohill 3 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1316 Leitrim Ard na Drise, Mohill 2 *N/A Q1‐2021 TURNKEY

24/05/2021 94/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 1317 Leitrim Lough Meen Estate, Drumkeerin 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1318 Leitrim Commons Lane, Manorhamilton 4 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION Cluain Oir, Liscara, Carrick on 1319 Leitrim 2 *N/A the scheme is fully TURNKEY Shannon approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 1320 Leitrim Manorhamilton & 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE St. Patricks Park Site, Carrick on 1321 Leitrim 2 *N/A the scheme is fully STAGE Shannon approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE Druminshingore Td., 1322 Leitrim 3 *N/A the scheme is fully STAGE Newtowngore approved.

Autumn View, Summerhill, Carrick 1323 SHIP CONSTRUCTION Leitrim 27 *N/A Q4‐2019 on Shannon

Taobh Tire, Manorhamilton 1324 SHIP CONSTRUCTION Leitrim 7 *N/A Q4‐2018 (Phase 2)

Stage 2 approved Q3‐2020, Taobh Tire, Manorhamilton 1325 SHIP CONSTRUCTION Leitrim 5 *N/A full design/tender being (Phase 3) prepared.

Stage 2 approved Q3‐2020, 1326 SHIP CONSTRUCTION Leitrim Townparks, Carrick on Shannon 12 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2020, 1327 SHIP CONSTRUCTION Leitrim Lahard, Ballinamore 10 *N/A full design/tender being prepared.

Society of Saint Vincent de 1328 CAS CONSTRUCTION Leitrim Ballinamore 2 Q4‐2017 Paul

Cnoc an Luir, Drumshanbo, Co. 1329 CALF Turnkey Leitrim 10 Túath Housing Association Q4‐2019 Leitrim (Phase 1)

SHIP CONSTRUCTION Woodlawn Park, Ballysimon Road, 1330 9 *N/A Q4‐2019 TURNKEY Limerick

24/05/2021 95/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Woodlawn Park (Phase 2), 1331 Limerick 1 *N/A Q4‐2019 TURNKEY Ballysimon Road,

SHIP CONSTRUCTION 1332 Limerick Carraig Desmond, Newcastle West 8 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1333 Limerick Knocklong 2 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1334 Limerick Carraig Desmond 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Redgate Close, Old Cratloe Road, 1335 Limerick 14 *N/A Q1‐2020 TURNKEY Limerick City

SHIP CONSTRUCTION The Orchard, Main Street, 1336 Limerick 8 *N/A Q1‐2020 TURNKEY Pallaskenry

SHIP CONSTRUCTION Gortboy, Charleville Road, 1337 Limerick 33 *N/A Q4‐2020 TURNKEY kIlmallock

SHIP CONSTRUCTION The Orchard, Main Street, 1338 Limerick 8 *N/A Q1‐2020 TURNKEY Pallaskenry

SHIP CONSTRUCTION 1339 Limerick Knocklong 5 *N/A Q1‐2021 TURNKEY

SHIP CONSTRUCTION RAPID 1340 Limerick Faha View, Patrickswell 16 *N/A Q4‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1341 Limerick Old Christians Site, Rathbane 43 *N/A Q2‐2020 VOLUMETRIC

1342 SHIP CONSTRUCTION Limerick Patrick’s Villas, Castleconnell 4 *N/A Q4‐2020

1343 SHIP CONSTRUCTION Limerick Ballysimon, Greenhill Road 14 *N/A Q1‐2020

Gough Place, Rosbrien Road, 1344 SHIP CONSTRUCTION Limerick 17 *N/A Q4‐2020 Limerick

24/05/2021 96/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1345 SHIP CONSTRUCTION Limerick Burke Avenue, Limerick City 12 *N/A Q4‐2019

1346 SHIP CONSTRUCTION Limerick Fannings Corner, Limerick City 3 *N/A Q4‐2019

Wallers Well, Limerick City (Phase 1347 SHIP CONSTRUCTION Limerick 13 *N/A Q4‐2020 2)

1348 SHIP CONSTRUCTION Limerick Clonmacken, Limerick City 43 *N/A Q3‐2019

Stage 4 approved Q3‐2020, 1349 SHIP CONSTRUCTION Limerick Deerpark, 30 *N/A the scheme is fully approved.

1350 SHIP CONSTRUCTION Limerick Glenview Drive, Hospital 20 *N/A Q3‐2020

Stage 3 approved Q1‐2021, the scheme is now 1351 SHIP CONSTRUCTION Limerick Clare Street, Limerick City 7 *N/A approved to proceed to tender.

1352 SHIP CONSTRUCTION Limerick Hasset Villas, Thomondgate 3 *N/A Q4‐2018

1353 SHIP CONSTRUCTION Limerick Kilmurry Court, Garryowen 7 *N/A Q4‐2019

1354 SHIP CONSTRUCTION Limerick Rathbane Road, Limerick City 2 *N/A Q1‐2019

1355 SHIP CONSTRUCTION Limerick Sycamore Avenue, Limerick City 5 *N/A Q3‐2019

1356 SHIP CONSTRUCTION Limerick Lower Carey's Road, Limerick City 11 *N/A Q1‐2021

1357 SHIP CONSTRUCTION Limerick Kileely Road, Moyross 5 *N/A Q2‐2020

1358 SHIP CONSTRUCTION Limerick Clare Street, Limerick City 2 *N/A Q4‐2017

24/05/2021 97/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1359 SHIP CONSTRUCTION Limerick Knocklong 12 *N/A Q1‐2021

Stage 2 approved Q4‐2018, 1360 SHIP CONSTRUCTION Limerick Colbert Terrace, Abbeyfeale 3 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, St. Michael's Court, Watergate 1361 SHIP CONSTRUCTION Limerick 9 *N/A full design/tender being Flats, prepared.

1362 SHIP CONSTRUCTION Limerick Ballygrennan Road, Limerick City 2 *N/A Q4‐2017

1363 SHIP CONSTRUCTION Limerick Ballysimon, Greenhills Road 3 *N/A Q2‐2020

Stage 2 approved Q1‐2021, 1364 SHIP CONSTRUCTION Limerick Clueing Dara, Broadford, Limerick 18 *N/A full design/tender being prepared.

Stage 1 approved Q4‐2020, Radharc an Ghleanna, 1365 SHIP CONSTRUCTION Limerick 4 *N/A outline design and costs Mountcollins being prepared.

Stage 1 approved Q1‐2021, O’Connor Park, Ardagh, Co. 1366 SHIP CONSTRUCTION Limerick 8 *N/A outline design and costs Limerick being prepared.

Stage 1 approved Q1‐2021, Church Glen, Ballylanders, Co. 1367 SHIP CONSTRUCTION Limerick 9 *N/A outline design and costs Limerick being prepared.

Stage 1 approved Q1‐2021, Radharc Cillin, Kilfinane, Co. 1368 SHIP CONSTRUCTION Limerick 10 *N/A outline design and costs Limerick being prepared.

Lord Edward Street, P2: Main 1369 REGENERATION Limerick 79 *N/A Q4‐2017 Contract

Lord Edward Street, P2: Main 1370 REGENERATION Limerick 2 *N/A Q1‐2017 Contract

Stage 3 approved Q1‐2021, Túath Housing Association the scheme is now 1371 REGENERATION Limerick Sheep / Athlunkards Street 8 Ltd approved to proceed to tender.

1372 REGENERATION Limerick Churchfield 19 *N/A Q1‐2018

24/05/2021 98/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 3 approved Q3‐2020, the scheme is now 1373 REGENERATION Limerick Churchfield 38 Cluid Housing Association approved to proceed to tender. Stage 3 approved Q1‐2021, the scheme is now 1374 REGENERATION Limerick Cosgrave Park 30 *N/A approved to proceed to tender. Stage 3 approved Q1‐2021, the scheme is now 1375 REGENERATION Limerick Orchard Site 26 Oaklee Housing Trust approved to proceed to tender.

1376 REGENERATION Limerick 176 & 177 Cliona Park 2 *N/A Q2‐2016

1377 REGENERATION Limerick Cliona Park (Phase 2) 10 *N/A Q2‐2017

1378 REGENERATION Limerick 8‐10 Gaol Lane 3 *N/A Q4‐2016

1379 REGENERATION Limerick 1 3 Weston Gardens 3 *N/A Q2‐2016

1380 REGENERATION Limerick 2016 Moyross Rebuild 6 *N/A Q4‐2016

1381 REGENERATION Limerick 2016 Southhill Rebuild 8 *N/A Q4‐2016

1382 REGENERATION Limerick 2016 St. Mary's Park Rebuild 9 *N/A Q4‐2016

Ballinacurra Weston Vacant 1383 REGENERATION Limerick 14 *N/A Q4‐2016 Refurbs, Lot 1 & 2**

1384 REGENERATION Limerick St. Mary's Park Infills 15 *N/A Q4‐2018

Stage 3 approved Q1‐2021, Túath Housing Association the scheme is now 1385 REGENERATION Limerick Cliona Park (Phase 3) 18 Ltd approved to proceed to tender.

1386 REGENERATION Limerick 45A‐46A Cliona Park 2 *N/A Q2‐2020

24/05/2021 99/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 3 approved Q1‐2021, the scheme is now 1387 REGENERATION Limerick Dalgaish Park 27 *N/A approved to proceed to tender.

1388 REGENERATION Limerick 2017 St Mary's Park Rebuild 1 *N/A Q4‐2017

1389 REGENERATION Limerick 2017 Ballinacurra Weston Rebuild 1 *N/A Q4‐2017

1390 REGENERATION Limerick 2017 Southill Rebuilds 13 *N/A Q4‐2017

1391 REGENERATION Limerick 2017 Moyross Rebuild 1 *N/A Q4‐2017

1392 REGENERATION Limerick Churchfield 23 *N/A Q2‐2018

1393 REGENERATION Limerick St. Mary's Park Infills 4 *N/A Q1‐2019

Infill developments at Carew Park 1394 REGENERATION Limerick 38 Peter McVerry Trust Ltd Q1‐2021 and Moyross

2019 Rebuilds (Southill, Moyross, 1395 REGENERATION Limerick St Mary's Park and Ballinacurra 8 *N/A Q4‐2019 Weston)

Carebright Community, 1396 CAS CONSTRUCTION TURNKEY Limerick 6 Carebright Ltd Q1‐2019 Ardykeohane,

Barrack Mews, Brennan's Row, Arlington Novas Ireland 1397 CAS CONSTRUCTION TURNKEY Limerick 2 Q4‐2019 Cathedral Place Ltd

Barrack Mews, Brennan's Row, Arlington Novas Ireland 1398 CAS CONSTRUCTION TURNKEY Limerick 3 Q1‐2020 Cathedral place Ltd

Barrack Mews, Brennan's Row, Arlington Novas Ireland 1399 CAS CONSTRUCTION TURNKEY Limerick 1 Q2‐2020 Cathedral place Ltd

Stage 3 approved Q1‐2021, Croom Voluntary Housing the scheme is now 1400 CAS CONSTRUCTION Limerick Towerfield Crescent, Croom 16 Association Ltd approved to proceed to tender.

24/05/2021 100/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 3 approved Q4‐2020, Cappamore Housing the scheme is now 1401 CAS CONSTRUCTION Limerick Cappamore 10 Association Ltd approved to proceed to tender.

Simon Community : 1402 CAS CONSTRUCTION Limerick Speakers Corner, Limerick City 4 Q3‐2018 Midwest Simon

1403 CAS CONSTRUCTION Limerick Cuan Mhuire, Bruree 6 Cuan Mhuire Teoranta Q3‐2018

Stage 4 approved Q1‐2021, Associated Charities Trust 1404 CAS CONSTRUCTION Limerick Mirth, Thomondgate 18 the scheme is fully Ltd approved.

1405 CAS CONSTRUCTION Limerick Cois na Feile, Abbeyfeale 12 Cluid Housing Association Q4‐2016

Stage 3 approved Q1‐2021, the scheme is now 1406 CAS CONSTRUCTION Limerick 2/3 Mallow Street 12 Peter McVerry Trust Ltd approved to proceed to tender.

Stage 2 approved Q3‐2020, Sophia Housing 1407 CAS CONSTRUCTION Limerick St. Pauls Convent, Kilfinane 9 full design/tender being Association Ltd prepared.

Stage 2 approved Q4‐2020, McGarry House, 7 Alphonsus Arlington Novas Ireland 1408 CAS CONSTRUCTION Limerick 8 full design/tender being Street Ltd prepared.

Stage 2 approved Q4‐2020, 47 & 48 Main Street, Croom, Croom Voluntary Housing 1409 CAS CONSTRUCTION Limerick 4 full design/tender being Limerick Association Ltd prepared.

Simon Community : 1410 CAS CONSTRUCTION Limerick 58 Henry Street 5 Q1‐2021 Midwest Simon

Stage 1 approved Q1‐2021, Croom Voluntary Housing 1411 CAS CONSTRUCTION Limerick 43 & 44 Main Street, Croom 4 outline design and costs Association Ltd being prepared.

Ballygrennan Close, Moyross, 1412 CALF Turnkey Limerick 2 Respond Q4‐2018 Limerick (Phase 1)

Ballygrennan Close, Moyross, 1413 CALF Turnkey Limerick 2 Respond Q4‐2018 Limerick (Phase 2)

Ballygrennan Close, Moyross, 1414 CALF Turnkey Limerick 2 Respond Q4‐2018 Limerick (Phase 3)

24/05/2021 101/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Baunacloka Heights, Mungret Co ‐ Operative Housing 1415 CALF Turnkey Limerick Gate, Mungret, Co. Limerick 46 Q4‐2020 Ireland Society Limited (Phase 1)

Baunacloka Heights, Mungret Co ‐ Operative Housing 1416 CALF Turnkey Limerick Gate, Mungret, Co. Limerick 25 Q3‐2018 Ireland Society Limited (Phase 2)*

Bloodmill Road, Singland, Limerick Co ‐ Operative Housing 1417 CALF Turnkey Limerick 25 Q2‐2020 (Phase 1)* Ireland Society Limited

Bloodmill Road, Singland, Limerick Co ‐ Operative Housing 1418 CALF Turnkey Limerick 27 Q2‐2020 (Phase 2) Ireland Society Limited

Bloodmill Road, Singland, Limerick Co ‐ Operative Housing 1419 CALF Turnkey Limerick 35 Q2‐2020 (Phase 3)* Ireland Society Limited

Bloodmill Road, Singland, Limerick Co ‐ Operative Housing 1420 CALF Turnkey Limerick 33 Q2‐2020 (Phase 4)* Ireland Society Limited

Bloodmill Road, Singland, Limerick Co ‐ Operative Housing 1421 CALF Turnkey Limerick 14 Q2‐2020 (Phase 5) Ireland Society Limited

Clonmacken, Condell Road, Co ‐ Operative Housing 1422 CALF Turnkey Limerick 24 Q3‐2020 Limerick (Phase 1)* Ireland Society Limited

Clonmacken, Condell Road, Co ‐ Operative Housing 1423 CALF Turnkey Limerick 23 Q3‐2020 Limerick (Phase 2)* Ireland Society Limited

Clonmacken, Condell Road, Co ‐ Operative Housing 1424 CALF Turnkey Limerick 21 Q3‐2020 Limerick (Phase 3)* Ireland Society Limited

Clonmacken, Condell Road, Co ‐ Operative Housing 1425 CALF Turnkey Limerick 20 Q3‐2020 Limerick (Phase 4)* Ireland Society Limited

Clonmacken, Condell Road, Co ‐ Operative Housing 1426 CALF Turnkey Limerick 22 Q3‐2020 Limerick (Phase 5)* Ireland Society Limited

Cluain Ard, , Co Limerick Co ‐ Operative Housing 1427 CALF Turnkey Limerick 2 Q1‐2018 (Phase 1) Ireland Society Limited

Cluain Ard, Fedamore, Co Limerick Co ‐ Operative Housing 1428 CALF Turnkey Limerick 2 Q3‐2018 (Phase 2) Ireland Society Limited

24/05/2021 102/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Cois Carraig, Clarina Village, 1429 CALF Turnkey Limerick 18 Cluid Housing Q4‐2020 Clarina, Co. Limerick (Phase 1)

Dromsally Woods, Cappamore, Focus Housing Association 1430 CALF Turnkey Limerick 5 Q3‐2020 Co. Limerick (Phase 1) CLG

Glendale Lawn, Bloodmill Road, 1431 CALF Turnkey Limerick 4 Cluid Housing Q3‐2020 Limerick (Phase 1)

1432 CALF Construction Limerick Hyde Road, Limerick City (Phase 1) 20 Cluid Housing Q1‐2018

Laurelville, Mill Road, Corbally, 1433 CALF Turnkey Limerick 13 Cluid Housing Q3‐2018 Limerick (Phase 1)*

Mungret Gate, Baunacloka, 1434 CALF Turnkey Limerick 8 Cluid Housing Q3‐2018 Mungret, Limerick (Phase 1)

Mungret Gate, Baunacloka, 1435 CALF Turnkey Limerick 23 Cluid Housing Q3‐2018 Mungret, Limerick (Phase 2)*

Revised ‐ Ard Aulin, Mungret, Co 1436 CALF Turnkey Limerick 7 Cluid Housing Q2‐2017 Limerick (Phase 1)

Toormore, Main Street, Bruree, 1437 CALF Turnkey Limerick 16 Cluid Housing Q3‐2020 Co. Limerick (Phase 1)

Woodfield Manor, 1438 CALF Turnkey Limerick Cloonyscrehane, Newcastle West 19 Cluid Housing Q3‐2020 (Phase 1)*

Woodfield Manor, 1439 CALF Turnkey Limerick Cloonyscrehane, Newcastle West 11 Cluid Housing Q3‐2020 (Phase 2)

SHIP CONSTRUCTION 1440 Longford Mill Race Park, Drumlish 14 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 1441 Longford Knock, Lanesborough 4 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 1442 Longford Mill Race Park, Drumlish (Phase 2) 2 *N/A Q1‐2018 TURNKEY

24/05/2021 103/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1443 Longford Ballinamuck 7 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1444 Longford Ballinamuck (Phase 2) 4 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 1445 Longford Ballinamuck (Phase 3) 6 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1446 Longford Rock View, Cloondara 5 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1447 Longford Greville Court, Granard 14 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1448 Longford Knock, Lanesborough (Phase 2) 29 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1449 Longford Mill Race Park, Drumlish 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1450 Longford Carragh, Granard 4 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 1451 Longford Church Street, Edgeworthstown 5 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1452 Longford Smithfield, Legan 18 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1453 Longford Mill Race Park, Drumlish 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1454 Longford Mill Race Park, Drumlish 4 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 1455 Longford Carragh, Granard (Phase 4) 6 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1456 Longford Carragh, Granard (Phase 2) 4 *N/A Q2‐2019 TURNKEY

24/05/2021 104/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1457 Longford Mill Race Park, Drumlish (Phase 3) 4 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 1458 Longford Abhainn Glas, Edgeworthstown 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1459 Longford Caislean Breac, Newtownforbes 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Farnagh Hill, Longford Town, 1460 Longford 4 *N/A Q1‐2020 TURNKEY Phase 1

SHIP CONSTRUCTION 1461 Longford Carragh, Granard(Phase 3) 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1462 Longford Mill Race Park, Drumlish 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Farnagh Hill, Longford Town, 1463 Longford 6 *N/A Q4‐2020 TURNKEY Phase 2

SHIP CONSTRUCTION 1464 Longford Carragh, Granard 7 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1465 Longford Slí Corglass, Legga 4 *N/A Q1‐2021 TURNKEY

SHIP CONSTRUCTION Radharc Na Muileann, Knock, 1466 Longford 2 *N/A Q4‐2019 TURNKEY Lanesborough

SHIP CONSTRUCTION 1467 Longford Pearse Drive, Longford Town 1 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1468 Longford Cartrons, Kenagh 5 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Farnagh Hill, Longford Town, 1469 Longford 4 *N/A Q3‐2020 TURNKEY Phase 3

SHIP CONSTRUCTION 1470 Longford Farnagh Hill, Longford Town 8 *N/A Q1‐2021 TURNKEY

24/05/2021 105/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1471 Longford Mill Race Park, Drumlish 1 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1472 Longford Campbell's Lane, Longford 21 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION O'Hara Site, Connaught 1473 Longford 14 *N/A Q1‐2021 TURNKEY Rd.,Longford

SHIP CONSTRUCTION 1474 Longford Farnagh Hill, Longford 2 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1475 Longford Sli Corglass, Legga 5 *N/A the scheme is fully TURNKEY approved.

1476 SHIP CONSTRUCTION Longford Rathcline Road, Lanesborough 4 *N/A Q3‐2019

Edgeworthstown Road, 1477 SHIP CONSTRUCTION Longford 4 *N/A Q1‐2018 Ballymahon

1478 SHIP CONSTRUCTION Longford Daroge, Ballymahon 1 *N/A Q4‐2019

1479 SHIP CONSTRUCTION Longford 'Rose Cottage', Ballinalee 6 *N/A Q3‐2020

Stage 2 approved Q1‐2020, 1480 SHIP CONSTRUCTION Longford St.Rita's, Park Road, Longford 14 *N/A full design/tender being prepared.

1481 SHIP CONSTRUCTION Longford Fairgreen View, Longford Town 1 *N/A Q4‐2020

Stage 3 approved Q1‐2020, the scheme is now 1482 SHIP CONSTRUCTION Longford Cranleymore, Abbeylara 3 *N/A approved to proceed to tender.

1483 SHIP CONSTRUCTION Longford Cloonahard, Edgeworthstown 1 *N/A Q3‐2020

Cartrun Breac, Lisbrack Rd, 1484 CALF Turnkey Longford 7 Cluid Housing Q1‐2017 Longford (Phase 1)

24/05/2021 106/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Colmcille Terrace, Granard, Co. 1485 CALF Construction Longford 21 Túath Housing Association Q2‐2018 Longford. (Phase 1)

SHIP CONSTRUCTION Brabazon Hall, Termonfeckin, 1486 Louth 5 *N/A Q4‐2019 TURNKEY Drogheda

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 1487 Louth Castletown Road, Dundalk 6 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION ‘Gort Bui’, Ballymakenny Road, 1488 Louth 13 *N/A Q4‐2020 TURNKEY Drogheda ‐ Phase 1

SHIP CONSTRUCTION Green Gates Manor, Haynestown, 1489 Louth 44 *N/A Q2‐2020 TURNKEY Dundalk

SHIP CONSTRUCTION Wadman Park, Haynestown, 1490 Louth 16 *N/A Q3‐2020 TURNKEY Dundalk ‐ Phase 1

SHIP CONSTRUCTION ‘Gort Bui’, Ballymakenny Road, 1491 Louth 9 *N/A Q4‐2020 TURNKEY Drogheda ‐ Phase 2

SHIP CONSTRUCTION ‘Gort Bui’, Ballymakenny Road, 1492 Louth 10 *N/A Q1‐2021 TURNKEY Drogheda ‐ Phase 3

SHIP CONSTRUCTION ‘Gort Bui’, Ballymakenny Road, 1493 Louth 9 *N/A Q4‐2019 TURNKEY Drogheda ‐ Phase 4

SHIP CONSTRUCTION ‘Gort Bui’, Ballymakenny Road, 1494 Louth 8 *N/A Q4‐2019 TURNKEY Drogheda ‐ Phase 5

SHIP CONSTRUCTION Wadman Park, Haynestown, 1495 Louth 17 *N/A Q4‐2020 TURNKEY Dundalk ‐ Phase 2

SHIP CONSTRUCTION Bridgegate Close, Bridgegate, 1496 Louth 1 *N/A Q4‐2020 TURNKEY Ardee

SHIP CONSTRUCTION 1497 Louth Termon River, Termonfeckin 2 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 1498 Louth Glyde View, 2 *N/A the scheme is fully TURNKEY approved.

24/05/2021 107/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Wadman Park, Haynestown, 1499 Louth 29 *N/A Q4‐2020 TURNKEY Dundalk ‐ Phase 3

SHIP CONSTRUCTION 1500 Louth Termon River, Termonfeckin 1 *N/A Q1‐2018 TURNKEY

SHIP CONSTRUCTION SINGLE 1501 Louth 55/57 Bothar Brugha, Drogheda 3 *N/A Q4‐2017 STAGE

SHIP CONSTRUCTION SINGLE 1502 Louth CPO Bundle 2 ‐ Phase 1 4 *N/A Q1‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1503 Louth CPO Bundle 1 7 *N/A Q4‐2016 STAGE

SHIP CONSTRUCTION SINGLE 1504 Louth CPO Bundle 1 ‐ Phase 2 5 *N/A Q2‐2017 STAGE

SHIP CONSTRUCTION SINGLE 1505 Louth CPO Bundle 1 ‐ Phase 3 3 *N/A Q3‐2017 STAGE

SHIP CONSTRUCTION SINGLE 1506 Louth CPO Bundle 1 ‐ Phase 4 7 *N/A Q4‐2017 STAGE

SHIP CONSTRUCTION SINGLE 1507 Louth CPO Bundle 1 ‐ Phase 5 1 *N/A Q3‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1508 Louth CPO Bundle 2 ‐ Phase 2 1 *N/A Q3‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1509 Louth CPO Bundle 2 ‐ Phase 6 2 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1510 Louth CPO Bundle 3 2 *N/A Q2‐2017 STAGE

SHIP CONSTRUCTION SINGLE 1511 Louth CPO Bundle 3 ‐ Phase 2 1 *N/A Q3‐2017 STAGE

SHIP CONSTRUCTION SINGLE 1512 Louth CPO Bundle 3 ‐ Phase 3 4 *N/A Q4‐2017 STAGE

24/05/2021 108/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION SINGLE 1513 Louth CPO Bundle 3 ‐ Phase 7 2 *N/A Q1‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1514 Louth CPO Bundle 4 1 *N/A Q3‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1515 Louth CPO Bundle 1 ‐ Phase 6 1 *N/A Q1‐2020 STAGE

SHIP CONSTRUCTION SINGLE 1516 Louth CPO Bundle 4 ‐ Phase 3 5 *N/A Q1‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1517 Louth CPO Bundle 3 ‐ Phase 4 1 *N/A Q2‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1518 Louth CPO Bundle 3 ‐ Phase 5 4 *N/A Q3‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1519 Louth CPO Bundle 2 ‐ Phase 3 1 *N/A Q1‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1520 Louth CPO Bundle 2 ‐ Phase 4 1 *N/A Q4‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1521 Louth CPO Bundle 4 ‐ Phase 2 4 *N/A Q4‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1522 Louth CPO Bundle 3 ‐ Phase 6 5 *N/A Q4‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1523 Louth CPO Bundle 4 ‐ Phase 4 1 *N/A Q4‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1524 Louth CPO Bundle 3 ‐ Phase 8 2 *N/A Q2‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1525 Louth CPO Bundle 5 ‐ Phase 2 2 *N/A Q2‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1526 Louth CPO Bundle 5 ‐ Phase 1 1 *N/A Q1‐2019 STAGE

24/05/2021 109/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION SINGLE 1527 Louth CPO Bundle 5 ‐ Phase 4 3 *N/A Q4‐2019 STAGE

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE 1528 Louth Moneymore, Drogheda 1 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE 1529 Louth Rathmullen, Drogheda 4 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE 1530 Louth Gort Uaine, Clogherhead 1 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION SINGLE 1531 Louth School Lane, Dunleer 1 *N/A the scheme is fully STAGE approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE 1532 Louth Doire Beag, Collon 6 *N/A the scheme is fully STAGE approved.

SHIP CONSTRUCTION SINGLE 1533 Louth CPO Bundle 6 ‐ Dromiskin 1 *N/A Q1‐2021 STAGE

SHIP CONSTRUCTION SINGLE 1534 Louth CPO Bundle 2 ‐ Phase 5 1 *N/A Q3‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1535 Louth CPO Bundle 6 ‐ Phase 1 1 *N/A Q3‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1536 Louth CPO Bundle 5 ‐ Phase 3 4 *N/A Q3‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1537 Louth CPO Bundle 6 ‐ Phase 2 2 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1538 Louth CPO Bundle 6 ‐ Dromiskin 1 *N/A Q1‐2021 STAGE

SHIP CONSTRUCTION SINGLE CPO Bundle 5 ‐ Bay Estate, 1539 Louth 1 *N/A Q1‐2020 STAGE Dundalk

SHIP CONSTRUCTION SINGLE CPO Bundle 5 ‐ Mary St. North, 1540 Louth 1 *N/A Q2‐2020 STAGE Dundalk

24/05/2021 110/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION SINGLE CPO Bundle 5 ‐ Bridge Crescent, 1541 Louth 1 *N/A Q2‐2020 STAGE Dundalk

SHIP CONSTRUCTION SINGLE 1542 Louth CPO Bundle 5 ‐ Dundalk 1 *N/A Q2‐2020 STAGE

SHIP CONSTRUCTION SINGLE 1543 Louth CPO Bundle 5 ‐ Dundalk 1 *N/A Q1‐2021 STAGE

Stage 4 approved Q2‐2019, SHIP CONSTRUCTION SINGLE CPO Bundle 5 ‐ St. Clement’s Park, 1544 Louth 1 *N/A the scheme is fully STAGE Dundalk approved.

SHIP CONSTRUCTION SINGLE 1545 Louth CPO Bundle 5 ‐ Dundalk 1 *N/A Q4‐2020 STAGE

SHIP CONSTRUCTION SINGLE CPO Bundle 6 ‐ Bolton Square, 1546 Louth 1 *N/A Q3‐2020 STAGE Drogheda

SHIP CONSTRUCTION SINGLE 1547 Louth CPO Bundle 6 ‐ Ardee 1 *N/A Q1‐2021 STAGE

1548 SHIP CONSTRUCTION Louth Woodlands, Dunleer 4 *N/A Q4‐2016

Stage 2 approved Q3‐2020, 1549 SHIP CONSTRUCTION Louth Boice Court (Phase 2), Drogheda 72 *N/A full design/tender being prepared.

1550 SHIP CONSTRUCTION Louth Father Finn Park (Phase 2) 17 *N/A Q1‐2020

Stage 2 approved Q4‐2020, 1551 SHIP CONSTRUCTION Louth Mount Avenue, Dundalk 93 *N/A full design/tender being prepared.

Stage 1 approved Q3‐2019, 1552 SHIP CONSTRUCTION Louth Muirhevnamor, Dundalk (Phase 1) 18 *N/A outline design and costs being prepared.

1553 REGENERATION Louth Cox's Demesne Phase 2a 14 *N/A Q4‐2016

1554 REGENERATION Louth Cox's Demesne Phase 2b 22 *N/A Q1‐2020

24/05/2021 111/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Túath Housing Association 1555 CAS CONSTRUCTION TURNKEY Louth Liscorrie, Bog Road, Drogheda 12 Q1‐2020 Ltd

1556 CAS CONSTRUCTION Louth Slieveroe Crescent, Dundalk 1 Cluid Housing Association Q1‐2021

Stage 2 approved Q3‐2018, Simon Community : 1557 CAS CONSTRUCTION Louth Barrack Street, Dundalk 21 full design/tender being Dundalk Simon prepared.

McArdle Green (Moneymore), North & East Housing 1558 CAS CONSTRUCTION Louth 1 Q4‐2018 Drogheda Association Ltd

Stage 3 approved Q1‐2018, the scheme is now 1559 CAS CONSTRUCTION Louth Tierney Street, Ardee 7 Oaklee Housing Trust approved to proceed to tender.

1560 CAS CONSTRUCTION Louth Tredagh View, Drogheda 1 Respond Q1‐2017

Stage 2 approved Q2‐2019, Túath Housing Association 1561 CAS CONSTRUCTION Louth Coulter Park, Dundalk 7 full design/tender being Ltd prepared.

Stage 3 approved Q3‐2020, St. John's Home, Peter's Hill, North & East Housing the scheme is now 1562 CAS CONSTRUCTION Louth 4 Drogheda Association Ltd approved to proceed to tender.

Stage 2 approved Q2‐2019, 1563 CAS CONSTRUCTION Louth Riverwell Close, Dundalk 1 Respond full design/tender being prepared.

Stage 1 approved Q2‐2020, Highfield, Newry Road, Dundalk 1564 CAS CONSTRUCTION Louth 12 *N/A outline design and costs (Domestic Violence Refuge) being prepared.

Stage 1 approved Q1‐2020, 10‐16 The Alleys, St. Peter's Place, 1565 CAS CONSTRUCTION Louth 14 Peter McVerry Trust Ltd outline design and costs Drogheda being prepared.

2 units An Rian, Termonfeckin Rd., North & East Housing 1566 CALF Turnkey Louth 2 Q2‐2019 Drogheda, Co. Louth (Phase 1) Association Ltd

Aston Village, Drogheda (Phase 1567 CALF Turnkey Louth 8 Respond Q3‐2018 1)*

Bishops Court, Dundalk, Co Louth 1568 CALF Construction Louth 2 Túath Housing Association Q3‐2020 (Phase 1)

24/05/2021 112/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Carlinn Drive, Mullaharlin Road, 1569 CALF Turnkey Louth 6 Cluid Housing Q4‐2020 Dundalk, Co. Louth (Phase 1)

Castle Court, Castlebellingham, 1570 CALF Turnkey Louth 4 Cluid Housing Q1‐2017 Louth (Phase 1)

Castle Court, Castlebellingham, 1571 CALF Turnkey Louth 10 Cluid Housing Q1‐2017 Louth (Phase 2)

Castleguard, Ardee, Co. Louth 1572 CALF Turnkey Louth 9 Túath Housing Association Q1‐2018 (Phase 1)

Castleguard, Ardee, Co. Louth 1573 CALF Turnkey Louth 20 Túath Housing Association Q1‐2018 (Phase 2)*

Castleguard, Ardee, Co. Louth 1574 CALF Turnkey Louth 8 Túath Housing Association Q3‐2018 (Phase 3)

Castleguard, Ardee, Co. Louth 1575 CALF Turnkey Louth 15 Túath Housing Association Q3‐2018 (Phase 4)

Castleguard, Ardee, Co. Louth 1576 CALF Turnkey Louth 6 Túath Housing Association Q4‐2018 (Phase 5)

Castleguard, Ardee, Co. Louth 1577 CALF Turnkey Louth 22 Túath Housing Association Q4‐2018 (Phase 6)*

Castleguard, Ardee, Co. Louth 1578 CALF Turnkey Louth 22 Túath Housing Association Q2‐2019 (Phase 7)

Cathedral View, Ramparts, 1579 CALF Turnkey Louth 16 Túath Housing Association Q1‐2021 Dundalk, Co. Louth (Phase 1)*

Cathedral View, Ramparts, 1580 CALF Turnkey Louth 10 Túath Housing Association Q1‐2020 Dundalk, Co. Louth (Phase 2)

Cathedral View, Ramparts, 1581 CALF Turnkey Louth 16 Túath Housing Association Q1‐2020 Dundalk, Co. Louth (Phase 3)

Cathedral View, Ramparts, 1582 CALF Turnkey Louth 11 Túath Housing Association Q1‐2020 Dundalk, Co. Louth (Phase 4)

24/05/2021 113/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Cathedral View, Ramparts, 1583 CALF Turnkey Louth 12 Túath Housing Association Q1‐2020 Dundalk, Co. Louth (Phase 5)

Clonmore Close, Ardee, Co. Louth 1584 CALF Turnkey Louth 12 Cluid Housing Q1‐2021 (Phase 1)

Clonmore Close, Ardee, Co. Louth 1585 CALF Turnkey Louth 15 Cluid Housing Q3‐2019 (Phase 2)*

Clonmore Close, Ardee, Co. Louth 1586 CALF Turnkey Louth 15 Cluid Housing Q3‐2019 (Phase 3)

Clonmore Close, Ardee, Co. Louth 1587 CALF Turnkey Louth 13 Cluid Housing Q3‐2019 (Phase 4)

Cois Cuain, Upper Point Road, 1588 CALF Turnkey Louth 13 Túath Housing Association Q4‐2018 Dundalk, Co. Louth (Phase 1)*

Cois Cuain, Upper Point Road, 1589 CALF Turnkey Louth 8 Túath Housing Association Q1‐2019 Dundalk, Co. Louth (Phase 2)

Cois Cuain, Upper Point Road, 1590 CALF Turnkey Louth 7 Túath Housing Association Q2‐2019 Dundalk, Co. Louth (Phase 3)

Coulter Place Armagh Road (Phase 1591 CALF Turnkey Louth 10 Cluid Housing Q1‐2017 1)

Coulter Place Armagh Road (Phase 1592 CALF Turnkey Louth 12 Cluid Housing Q3‐2017 2)

Donore Road, Drogheda, Co. 1593 CALF Turnkey Louth 66 Cluid Housing Q1‐2021 Louth (Phase 1)

Dowdallshill, Dundalk, Co. Louth North & East Housing 1594 CALF Turnkey Louth 13 Q3‐2020 (Phase 1)* Association Ltd

Dublin Road, Dundalk, Co. Louth 1595 CALF Turnkey Louth 65 Respond Q4‐2020 (Phase 1)*

Dublin Road, Dundalk, Co. 1596 CALF Turnkey Louth 14 Respond Q1‐2019 Louth(Glenview) (Phase 1)*

24/05/2021 114/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Dublin Road, Dundalk, Co. 1597 CALF Turnkey Louth 14 Respond Q4‐2019 Louth(Glenview) (Phase 2)*

Dublin Road, Dundalk, Co. 1598 CALF Turnkey Louth 3 Respond Q3‐2017 Louth(Glenview) (Phase 3)

Duiche Roden (formerly The 1599 CALF Turnkey Louth Kitchen Garden)Desmesne Road, 65 Cluid Housing Q4‐2020 Dundalk, Co. Louth (Phase 1)*

Duiche Roden (formerly The 1600 CALF Turnkey Louth Kitchen Garden)Desmesne Road, 65 Cluid Housing Q4‐2020 Dundalk, Co. Louth (Phase 2)

Dundoogan, Haynestown, 1601 CALF Turnkey Louth 11 Túath Housing Association Q2‐2019 Dundalk, Co. Louth (Phase 1)*

Dundoogan, Haynestown, 1602 CALF Turnkey Louth 14 Túath Housing Association Q2‐2019 Dundalk, Co. Louth (Phase 2)*

Dundoogan, Haynestown, 1603 CALF Turnkey Louth 15 Túath Housing Association Q2‐2019 Dundalk, Co. Louth (Phase 3)*

Dundoogan, Haynestown, 1604 CALF Turnkey Louth 47 Túath Housing Association Q3‐2019 Dundalk, Co. Louth (Phase 4)*

Dundoogan, Haynestown, 1605 CALF Turnkey Louth 24 Túath Housing Association Q4‐2019 Dundalk, Co. Louth (Phase 5)*

Dundoogan, Haynestown, 1606 CALF Turnkey Louth 1 Túath Housing Association Q4‐2020 Dundalk, Co. Louth (Phase 6)*

Fire Station Site, Scarlett St, North & East Housing 1607 CALF Construction Louth 15 Q4‐2019 Drogheda (Phase 1) Association Ltd

Halliday Mills, Quay Street, Co ‐ Operative Housing 1608 CALF Turnkey Louth 85 Q3‐2020 Dundalk, Co. Louth (Phase 1)* Ireland Society Limited

Harbour Grove, Dundalk, Co. North & East Housing 1609 CALF Turnkey Louth 8 Q2‐2020 Louth (Phase 1) Association Ltd

Harbour View, Coulter Place, 1610 CALF Turnkey Louth 24 Cluid Housing Q1‐2020 Dundalk (Phase 1)

24/05/2021 115/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Knock Shee Close, Blackrock, Co. 1611 CALF Turnkey Louth 1 Cluid Housing Q4‐2020 Louth (Phase 1)

Knock Shee, Old Golf Links Road, 1612 CALF Turnkey Louth 3 Cluid Housing Q4‐2017 Blackrock, Co Louth (Phase 1)

Knockshee Close, Blackrock, Co. 1613 CALF Turnkey Louth 3 Cluid Housing Q2‐2020 Louth (Phase 1)

Liscorrie, Bog Lane, Drogheda 1614 CALF Turnkey Louth 41 Túath Housing Association Q4‐2017 (Phase 1)

Lismullen Grove, Dundalk, Co. 1615 CALF Turnkey Louth 15 Túath Housing Association Q4‐2020 Louth (Phase 1)*

Lismullen Grove, Dundalk, Co. 1616 CALF Turnkey Louth 8 Túath Housing Association Q1‐2021 Louth (Phase 2)

Mount Hamilton, Dundalk, Co. 1617 CALF Turnkey Louth 20 Cluid Housing Q4‐2019 Louth (Phase 1)

Newfoundwell Road, Drogheda, 1618 CALF Turnkey Louth 55 Cluid Housing Q3‐2020 Co Louth (Phase 1)*

Newfoundwell Road, Drogheda, 1619 CALF Turnkey Louth 39 Cluid Housing Q3‐2020 Co Louth (Phase 2)

Newtown, Marsh Road, 1620 CALF Turnkey Louth 17 Respond Q4‐2020 Drogheda, Co. Louth (Phase 1)*

Newtown, Marsh Road, 1621 CALF Turnkey Louth 23 Respond Q4‐2020 Drogheda, Co. Louth (Phase 2)*

Newtown, Marsh Road, 1622 CALF Turnkey Louth 46 Respond Q4‐2020 Drogheda, Co. Louth (Phase 3)*

Newtown, Marsh Road, 1623 CALF Turnkey Louth 47 Respond Q4‐2020 Drogheda, Co. Louth (Phase 4)*

Oriel Heights, Collon, Co. Louth North & East Housing 1624 CALF Turnkey Louth 13 Q1‐2021 (Phase 1)* Association Ltd

24/05/2021 116/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Post Tender ‐ Clos na Manach, 1625 CALF Construction Louth 10 Túath Housing Association Q2‐2018 Carlingford, Co Louth (Phase 1)

Racecourse Meadows, Dundalk, Clanmil Housing 1626 CALF Turnkey Louth 20 Q1‐2019 Co. Louth ‐ Clanmil (Phase 1) Association Ireland

Racecourse Meadows, Dundalk, Clanmil Housing 1627 CALF Turnkey Louth 25 Q1‐2019 Co. Louth ‐ Clanmil (Phase 2)* Association Ireland

Racecourse Meadows, Dundalk, 1628 CALF Turnkey Louth 11 Túath Housing Association Q4‐2019 Co. Louth ‐ Tuath (Phase 1)

Racecourse Meadows, Dundalk, 1629 CALF Turnkey Louth 22 Túath Housing Association Q1‐2019 Co. Louth ‐ Tuath (Phase 2)*

Racecourse Meadows, Dundalk, 1630 CALF Turnkey Louth 6 Túath Housing Association Q1‐2019 Co. Louth ‐ Tuath (Phase 3)*

Racecourse Meadows, Dundalk, 1631 CALF Turnkey Louth 7 Túath Housing Association Q1‐2019 Co. Louth ‐ Tuath (Phase 4)*

Rath na Gloine, Commons Road, 1632 CALF Turnkey Louth 3 Cluid Housing Q3‐2016 Louth (Phase 1)

Rathmullen Road, Drogheda, Co. North & East Housing 1633 CALF Turnkey Louth 3 Q4‐2018 Louth (Phase 1) Association Ltd

Rathmullen Road, Drogheda, Co. North & East Housing 1634 CALF Turnkey Louth 6 Q2‐2019 Louth (Phase 2) Association Ltd

Rathmullen Road, Drogheda, Co. North & East Housing 1635 CALF Turnkey Louth 3 Q3‐2019 Louth (Phase 3) Association Ltd

Rathmullen Road, Drogheda, Co. North & East Housing 1636 CALF Turnkey Louth 14 Q3‐2019 Louth (Phase 4) Association Ltd

Rathmullen Road, Drogheda, Co. North & East Housing 1637 CALF Turnkey Louth 12 Q4‐2019 Louth (Phase 5) Association Ltd

Rathmullen Road, Drogheda, Co. North & East Housing 1638 CALF Turnkey Louth 16 Q4‐2019 Louth (Phase 6) Association Ltd

24/05/2021 117/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Rathmullen Road, Drogheda, Co. 1639 CALF Turnkey Louth 4 Túath Housing Association Q2‐2018 Louth (Tuath) (Phase 1)

Rathmullen Road, Drogheda, Co. 1640 CALF Turnkey Louth 6 Túath Housing Association Q3‐2018 Louth (Tuath) (Phase 2)

Rathmullen Road, Drogheda, Co. 1641 CALF Turnkey Louth 4 Túath Housing Association Q3‐2018 Louth (Tuath) (Phase 3)

Rathmullen Road, Drogheda, Co. 1642 CALF Turnkey Louth 15 Túath Housing Association Q4‐2018 Louth (Tuath) (Phase 4)

Rathmullen Road, Drogheda, Co. 1643 CALF Turnkey Louth 6 Túath Housing Association Q2‐2019 Louth (Tuath) (Phase 5)

Rathmullen Road, Drogheda, Co. 1644 CALF Turnkey Louth 4 Túath Housing Association Q4‐2019 Louth (Tuath) (Phase 6)

Rathmullen Road, Drogheda, Co. 1645 CALF Turnkey Louth 12 Túath Housing Association Q3‐2020 Louth (Tuath) (Phase 7)

Revised ‐ 43 Units at Mount 1646 CALF Turnkey Louth Hamilton, Dundalk, Co Louth 12 Cluid Housing Q4‐2017 (Phase 1)

Revised ‐ 43 Units at Mount 1647 CALF Turnkey Louth Hamilton, Dundalk, Co Louth 15 Cluid Housing Q3‐2019 (Phase 2)

Revised ‐ 43 Units at Mount 1648 CALF Turnkey Louth Hamilton, Dundalk, Co Louth 16 Cluid Housing Q4‐2019 (Phase 3)

Slieve Row Crescent, Dundalk 1649 CALF Construction Louth 1 Cluid Housing Q2‐2016 (Phase 1)

Termon River, Baltray Road, North & East Housing 1650 CALF Turnkey Louth 1 Q4‐2019 Termonfeckin, Co. Louth (Phase 1) Association Ltd

Termon River, Baltray Road, North & East Housing 1651 CALF Turnkey Louth Termonfeckin, Drogheda, 1 Q4‐2019 Association Ltd Co.Louth (Phase 1)*

Tullybrook, Drogheda, Co. Louth 1652 CALF Turnkey Louth 85 Cluid Housing Q1‐2021 (Phase 1)*

24/05/2021 118/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

PUBLIC PRIVATE PARTNERSHIP 1653 Louth Ravel Ardee Road, Dunleer 80 *N/A Q2‐2020 (Bundle 1)

SHIP CONSTRUCTION Carrabeg, Newport Road, 1654 Mayo 2 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1655 Mayo Cois Abhainn, Bonniconlon 2 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 1656 Mayo Chapel Street, Louisburgh 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1657 Mayo Bunree, Ballina 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1658 Mayo Heathervale, Castlebar ‐ Phase 2 9 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1659 Mayo Friars Court, Ballina 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1660 Mayo Riverside Drive, Ballina 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1661 Mayo Davitt Terrace, Castlebar 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1662 Mayo Chapel St., Louisburgh 2 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1663 Mayo Ard Rua, 7 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1664 Mayo Silver Springs, Claremorris 20 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1665 Mayo Barley Hill, 3 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 1666 Mayo Main St., Charlestown 2 *N/A the scheme is fully TURNKEY approved.

24/05/2021 119/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION SINGLE 1667 Mayo Pound Road, Castlebar 6 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1668 Mayo The Boreen, 3 *N/A Q1‐2020 STAGE

SHIP CONSTRUCTION SINGLE 1669 Mayo Deel Court, Crossmolina 3 *N/A Q1‐2020 STAGE

SHIP CONSTRUCTION SINGLE 1670 Mayo 6 *N/A Q4‐2019 STAGE

SHIP CONSTRUCTION SINGLE 1671 Mayo , Moygownagh 3 *N/A Q1‐2020 STAGE

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE 1672 Mayo Liskilleen, , 1 *N/A the scheme is fully STAGE approved.

SHIP CONSTRUCTION SINGLE 1673 Mayo Low Park, Charlestown 3 *N/A Q3‐2020 STAGE

1674 SHIP CONSTRUCTION Mayo Knocknageeha, Newport 1 *N/A Q2‐2019

1675 SHIP CONSTRUCTION Mayo Road, Knock (Phase 3) 4 *N/A Q3‐2018

1676 SHIP CONSTRUCTION Mayo (Phase 2) 4 *N/A Q3‐2018

1677 SHIP CONSTRUCTION Mayo Knockmore, Ballina 8 *N/A Q1‐2019

Radharc an tSaillin, 1678 SHIP CONSTRUCTION Mayo , (Phase 4 *N/A Q2‐2019 2)

1679 SHIP CONSTRUCTION Mayo Sliabh Rua, (Phase 3) 10 *N/A Q4‐2019

1680 SHIP CONSTRUCTION Mayo Woodlands, Balla (Phase 3) 4 *N/A Q4‐2019

24/05/2021 120/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1681 SHIP CONSTRUCTION Mayo Slinaunroe, Clogher (SRD) 1 *N/A Q2‐2017

1682 SHIP CONSTRUCTION Mayo Abbeyquarter, 18 *N/A Q4‐2020

1683 SHIP CONSTRUCTION Mayo Tonragee West, Achill (Phase 2) 5 *N/A Q4‐2019

Sli na Roba, Friarsquarter, 1684 SHIP CONSTRUCTION Mayo 16 *N/A Q4‐2020 Ballinrobe

1685 SHIP CONSTRUCTION Mayo Marian Crescent, Ballina 4 *N/A Q2‐2018

1686 SHIP CONSTRUCTION Mayo Tubberhill, Westport (Phase 3) 21 *N/A Q1‐2018

1687 SHIP CONSTRUCTION Mayo Parke, Castlebar 8 *N/A Q4‐2019

1688 SHIP CONSTRUCTION Mayo Killavally 10 *N/A Q4‐2019

Stage 3 approved Q4‐2020, Lios na Circa, Saleen, Castlebar ‐ the scheme is now 1689 SHIP CONSTRUCTION Mayo 22 *N/A Phase 2 approved to proceed to tender.

1690 SHIP CONSTRUCTION Mayo Kilkelly Road, 27 *N/A Q4‐2020

1691 SHIP CONSTRUCTION Mayo Barhauve, (SRD) 1 *N/A Q2‐2018

1692 SHIP CONSTRUCTION Mayo Glaggaun, Ballycroy (SRD) 1 *N/A Q4‐2017

1693 SHIP CONSTRUCTION Mayo , Pollatomish (SRD) 1 *N/A Q2‐2018

1694 SHIP CONSTRUCTION Mayo Gorthbrack, Inver (SRD) 1 *N/A Q1‐2018

24/05/2021 121/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q1‐2019, 1695 SHIP CONSTRUCTION Mayo Cross 15 *N/A outline design and costs being prepared.

1696 SHIP CONSTRUCTION Mayo Bonniconlon 5 *N/A Q2‐2020

Stage 2 approved Q3‐2019, 1697 SHIP CONSTRUCTION Mayo Cloonkeadagh Road, 21 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2019, 1698 SHIP CONSTRUCTION Mayo Rehins Fort, Ballina 50 *N/A full design/tender being prepared.

Stage 2 approved Q2‐2020, 1699 SHIP CONSTRUCTION Mayo Murrevagh, Mulranney 14 *N/A full design/tender being prepared.

Stage 1 approved Q1‐2020, 50 Units @ Golf Course Rd., 1700 SHIP CONSTRUCTION Mayo 50 *N/A outline design and costs Westport being prepared.

Stage 1 approved Q2‐2020, 1701 SHIP CONSTRUCTION Mayo Ballyglass, , Claremorris 6 *N/A outline design and costs being prepared.

Stage 1 approved Q2‐2020, Lios na Circe, Saleen, Castlebar ‐ 1702 SHIP CONSTRUCTION Mayo 14 *N/A outline design and costs Phase 3 being prepared.

1703 SHIP CONSTRUCTION Mayo 7 St. Patrick's Terrace, Westport 1 *N/A Q3‐2017

Stage 2 approved Q1‐2021, 1704 SHIP CONSTRUCTION Mayo Atlantic Drive ,Belmullet 4 *N/A full design/tender being prepared.

Stage 1 approved Q1‐2021, 1705 SHIP CONSTRUCTION Mayo Walsh St., Ballina 8 *N/A outline design and costs being prepared.

Admiral Browne Road, Foxford Society of Saint Vincent de 1706 CAS CONSTRUCTION Mayo 4 Q1‐2018 (Phase 2) Paul

Society of Saint Vincent de 1707 CAS CONSTRUCTION Mayo Killosheehan, Ballinrobe 6 Q4‐2018 Paul

Society of Saint Vincent de 1708 CAS CONSTRUCTION Mayo Admiral Browne Road, Foxford 8 Q3‐2016 Paul

24/05/2021 122/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Irish Wheelchair 1709 CAS CONSTRUCTION Mayo Logmore, Belmullet 7 Q2‐2017 Association Ltd

Chestnut Grove, Castlebar, Co. 1710 CALF Turnkey Mayo 4 Túath Housing Association Q3‐2020 Mayo (Phase 1)

Chestnut Grove, Castlebar, Co. 1711 CALF Turnkey Mayo 4 Túath Housing Association Q3‐2020 Mayo (Phase 2)

Glenlara, Westport, Co Mayo Co ‐ Operative Housing 1712 CALF Turnkey Mayo 10 Q4‐2019 (Phase 1) Ireland Society Limited

Humbert Way, Castlebar, Co. Co ‐ Operative Housing 1713 CALF Turnkey Mayo 20 Q2‐2020 Mayo (Phase 1) Ireland Society Limited

Monamore, Lodge Road, 1714 CALF Turnkey Mayo 2 Túath Housing Association Q4‐2019 Westport, Co. Mayo (Phase 1)*

1715 CALF Turnkey Mayo The Sycamores, Ballina (Phase 1) 11 Cluid Housing Q2‐2019

SHIP CONSTRUCTION 1716 Meath Cois Glaisin, Johnstown, Navan 19 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Cluain Adain, Clonmagadden, 1717 Meath 16 *N/A Q4‐2018 TURNKEY Navan

SHIP CONSTRUCTION 1718 Meath Dun Eimear, Bettystown 8 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 1719 Meath Bracken Hill, Kilmessan 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION Cluain Adain, Clonmagadden, 1720 Meath 4 *N/A Q3‐2019 TURNKEY Navan

SHIP CONSTRUCTION Cois Glaisin Walk, Johnstown, 1721 Meath 5 *N/A Q4‐2018 TURNKEY Navan

SHIP CONSTRUCTION Cois Glaisin Walk, Johnstown, 1722 Meath 4 *N/A Q3‐2019 TURNKEY Navan

24/05/2021 123/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1723 Meath Cois Glaisin, Johnstown, Navan 8 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 1724 Meath Cois na Mara, Bettystown 2 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 1725 Meath Dun Eimear, Bettystown 14 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1726 Meath Cherry Hill Court, Kells 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1727 Meath Broadmeadow Vale, Rathoath 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1728 Meath Cois Glaisin, Johnstown, Navan 11 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Cluain Adain, Clonmagadden, 1729 Meath 15 *N/A Q4‐2020 TURNKEY Navan

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION The Brambles, Longford rd., 1730 Meath 16 *N/A the scheme is fully TURNKEY Duleek approved.

SHIP CONSTRUCTION 1731 Meath 26 Willow Green, Dunshaughlin 1 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1732 Meath Seoid na Tra, Bettytown 2 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 1733 Meath Dun Eimear, Bettystown 1 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 1734 Meath Connaught Street, Athboy 7 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION SINGLE 1735 Meath Proudstown Road, Navan 4 *N/A Q4‐2018 STAGE

SHIP CONSTRUCTION SINGLE 1736 Meath The Belfry, Trim 3 *N/A Q4‐2019 STAGE

24/05/2021 124/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE Broville, Corballis, Laytown, Co. 1737 Meath 1 *N/A the scheme is fully STAGE Meath approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE 11 Glenidan Court, Enfield, Co. 1738 Meath 1 *N/A the scheme is fully STAGE Meath approved.

SHIP CONSTRUCTION RAPID 1739 Meath Kilmainhamwood 4 *N/A Q4‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1740 Meath Cortown 10 *N/A Q4‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1741 Meath Oldcastle 16 *N/A Q4‐2019 VOLUMETRIC

1742 SHIP CONSTRUCTION Meath Bettystown (Phase 2) 15 *N/A Q4‐2020

1743 SHIP CONSTRUCTION Meath St. Oliver's Park, Ratoath 17 *N/A Q4‐2019

1744 SHIP CONSTRUCTION Meath Riverside (Townparks), Kells 40 *N/A Q4‐2020

1745 SHIP CONSTRUCTION Meath Cherry Court, Summerhill 19 *N/A Q1‐2019

1746 SHIP CONSTRUCTION Meath Connaught Grove, Athboy 32 *N/A Q2‐2018

1747 SHIP CONSTRUCTION Meath Carlanstown 13 *N/A Q4‐2020

Stage 4 approved Q4‐2020, 1748 SHIP CONSTRUCTION Meath Donore 21 *N/A the scheme is fully approved.

1749 SHIP CONSTRUCTION Meath Dunshaughlin 26 *N/A Q1‐2020

1750 SHIP CONSTRUCTION Meath Bettystown (Phase 1) 16 *N/A Q3‐2017

24/05/2021 125/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q3‐2020, 1751 SHIP CONSTRUCTION Meath Farganstown, Navan 84 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 1752 SHIP CONSTRUCTION Meath Blackhill Crescent, Donacarney 2 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2020, 1753 SHIP CONSTRUCTION Meath Archdeaconary Glebe, Kells 20 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 1754 SHIP CONSTRUCTION Meath Nangle Court, Navan 16 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2020, Castle Street, Ashbourne ‐ Dept of 1755 SHIP CONSTRUCTION Meath 74 *N/A full design/tender being Education Site prepared.

Stage 2 approved Q1‐2021, 1756 SHIP CONSTRUCTION Meath Church View, Rathmolyon 16 *N/A full design/tender being prepared.

Stage 1 approved Q3‐2019, 1757 SHIP CONSTRUCTION Meath Church Street, Kells, Co. Meath 3 *N/A outline design and costs being prepared.

Stage 1 approved Q3‐2019, 1758 SHIP CONSTRUCTION Meath Haggard Street, Trim, Co. Meath 4 *N/A outline design and costs being prepared.

Stage 1 approved Q3‐2019, 1759 SHIP CONSTRUCTION Meath Pitcher Lane, Kells, Co. Meath 4 *N/A outline design and costs being prepared.

Stage 1 approved Q4‐2019, 1760 SHIP CONSTRUCTION Meath Swan Lane, Balreask 6 *N/A outline design and costs being prepared.

Stage 1 approved Q1‐2019, 1761 SHIP CONSTRUCTION Meath Carrick St., Kells 30 *N/A outline design and costs being prepared.

Stage 3 approved Q1‐2021, the scheme is now 1762 SHIP CONSTRUCTION Meath Lagore, Dunshaughlin 34 *N/A approved to proceed to tender.

Stage 1 approved Q2‐2020, 1763 SHIP CONSTRUCTION Meath Convent Lands, Kildalkey, Athboy 20 *N/A outline design and costs being prepared.

Stage 4 approved Q3‐2020, Bridge Street, Ashbourne, Co 1764 CAS CONSTRUCTION TURNKEY Meath 20 Peter McVerry Trust Ltd the scheme is fully Meath approved.

24/05/2021 126/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q1‐2021, Gainsfield, Common Road, Navan Túath Housing Association 1765 CAS CONSTRUCTION TURNKEY Meath 6 the scheme is fully Co. Meath Ltd approved.

Túath Housing Association 1766 CAS CONSTRUCTION Meath Blackcastle, Slane Road, Navan 17 Q4‐2018 Ltd

Stage 1 approved Q2‐2020, Women's Refuge, Tailteann Drive, Meath Women’s Housing 1767 CAS CONSTRUCTION Meath 8 outline design and costs Windtown, Navan Association CLG being prepared.

18 units Churchfields, Ashbourne, 1768 CALF Turnkey Meath 18 Túath Housing Association Q4‐2018 Co. Meath (Phase 1)

5 units Dunville, Athlumney, 1769 CALF Turnkey Meath 5 Túath Housing Association Q1‐2019 Navan, Co. Meath (Phase 1)

6 Units Seabury Lawns, 1770 CALF Turnkey Meath 6 Cluid Housing Q1‐2018 Mornington, Co Meath (Phase 1)

Applewood Court, Beaufort Place, 1771 CALF Turnkey Meath 6 Túath Housing Association Q3‐2020 Navan, Co. Meath (Phase 1)

Applewood Court, Beaufort Place, 1772 CALF Turnkey Meath 15 Túath Housing Association Q3‐2020 Navan, Co. Meath (Phase 2)*

Ardmore Rise, Bettystown, Co North & East Housing 1773 CALF Turnkey Meath 1 Q4‐2018 Meath (Phase 1) Association Ltd

Ashewood, Ashbourne, Co Meath 1774 CALF Turnkey Meath 11 Cluid Housing Q3‐2020 (Phase 1)

Athboy Road, Navan, Co. Meath 1775 CALF Turnkey Meath 63 Respond Q1‐2021 (Phase 1)*

Blackcastle, Slane Road, Navan, 1776 CALF Turnkey Meath 9 Túath Housing Association Q4‐2018 Co. Meath (Phase 1)

Broadmeadow Vale, Ratoath, 1777 CALF Turnkey Meath 1 Túath Housing Association Q2‐2019 Meath (Phase 1)*

Broadmeadow Vale, Ratoath, 1778 CALF Turnkey Meath 1 Túath Housing Association Q2‐2019 Meath (Phase 2)*

24/05/2021 127/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Broadmeadow Vale, Ratoath, 1779 CALF Turnkey Meath 10 Túath Housing Association Q4‐2019 Meath (Phase 3)*

Ceamach Close, Donacarney, Co 1780 CALF Turnkey Meath 7 Cluid Housing Q2‐2018 Meath (Phase 1)

Ceamach Close, Donacarney, Co 1781 CALF Turnkey Meath 9 Cluid Housing Q3‐2018 Meath (Phase 2)*

Cherryvalley, Rathmoylan, Co 1782 CALF Turnkey Meath 9 Cluid Housing Q4‐2017 Meath (Phase 1)

Churchfields, Ashbourne, Co 1783 CALF Turnkey Meath 8 Túath Housing Association Q2‐2017 Meath (Phase 1)*

Churchfields, Ashbourne, Meath 1784 CALF Turnkey Meath 10 Túath Housing Association Q4‐2018 (Phase 1)*

Churchfields, Ashbourne, Meath 1785 CALF Turnkey Meath 3 Túath Housing Association Q2‐2019 (Phase 2)*

Churchfields, Ashbourne, Meath 1786 CALF Turnkey Meath 12 Túath Housing Association Q4‐2019 (Phase 3)*

Commons Road, Navan, Co Meath North & East Housing 1787 CALF Turnkey Meath 12 Q4‐2019 (Phase 1) Association Ltd

Dun Eimear, Bettystown, Co. 1788 CALF Turnkey Meath 12 Cluid Housing Q4‐2019 Meath (Phase 1)*

Dun Eimear, Bettystown, Co. 1789 CALF Turnkey Meath 11 Cluid Housing Q4‐2019 Meath (Phase 2)*

Dunville, Athlumney, Co Meath 1790 CALF Turnkey Meath 10 Túath Housing Association Q1‐2018 (Phase 1)

Dunville, Athlumney, Co Meath 1791 CALF Turnkey Meath 8 Túath Housing Association Q1‐2018 (Phase 2)*

Dunville, Athlumney, Co Meath 1792 CALF Turnkey Meath 10 Túath Housing Association Q2‐2018 (Phase 3)*

24/05/2021 128/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Dunville, Athlumney, Co Meath 1793 CALF Turnkey Meath 6 Túath Housing Association Q2‐2018 (Phase 4)*

Dunville, Athlumney, Co Meath 1794 CALF Turnkey Meath 18 Túath Housing Association Q2‐2018 (Phase 5)*

Dunville, Athlumney, Co Meath 1795 CALF Turnkey Meath 12 Túath Housing Association Q3‐2018 (Phase 6)

Eastham Square, Bettystown, 1796 CALF Turnkey Meath 5 Cluid Housing Q1‐2019 Meath (Phase 1)*

Fitzherbert Wood, Slane Road, 1797 CALF Turnkey Meath 1 Túath Housing Association Q3‐2018 Navan, Co Meath (Phase 1)*

Frederick Manor, Ashbourne, Co. 1798 CALF Turnkey Meath 11 Cluid Housing Q1‐2021 Meath (Phase 1)*

Gainsfield, Commons Road, 1799 CALF Turnkey Meath 20 Túath Housing Association Q4‐2019 Navan, Co. Meath (Phase 1)

Gainsfield, Commons Road, 1800 CALF Turnkey Meath 18 Túath Housing Association Q4‐2020 Navan, Co. Meath (Phase 2)

Gainsfield, Commons Road, 1801 CALF Turnkey Meath 7 Túath Housing Association Q1‐2021 Navan, Co. Meath (Phase 3)

Gainsfield, Commons Road, 1802 CALF Turnkey Meath 9 Túath Housing Association Q3‐2018 Navan, Co. Meath (Phase 4)

Gort Fionnbarra (Gainsfield Phase 1803 CALF Turnkey Meath 2), Commons Road, Navan, Co. 20 Túath Housing Association Q4‐2020 Meath (Phase 1)

Gort Fionnbarra (Gainsfield Phase 1804 CALF Turnkey Meath 2), Commons Road, Navan, Co. 15 Túath Housing Association Q4‐2020 Meath (Phase 2)

Gort Fionnbarra (Gainsfield Phase 1805 CALF Turnkey Meath 2), Commons Road, Navan, Co. 14 Túath Housing Association Q4‐2020 Meath (Phase 3)

Grangehall, Dunshaughlin (Phase 1806 CALF Turnkey Meath 7 Túath Housing Association Q2‐2018 1)

24/05/2021 129/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Kellets Grove, Dunshauglin, Co 1807 CALF Turnkey Meath 6 Túath Housing Association Q1‐2018 Meath (Phase 1)*

Knightsbrook Close, Iffernock, 1808 CALF Turnkey Meath 5 Túath Housing Association Q3‐2020 Trim, Co. Meath (Phase 1)

Knightsbrook Close, Iffernock, 1809 CALF Turnkey Meath 5 Túath Housing Association Q3‐2020 Trim, Co. Meath (Phase 2)

Knightsbrook Close, Iffernock, 1810 CALF Turnkey Meath 6 Túath Housing Association Q3‐2020 Trim, Co. Meath (Phase 3)

Ledwidge Hall Green, Drogheda 1811 CALF Turnkey Meath 6 Oaklee Housing Q1‐2021 Road, Slane, Co. Meath (Phase 1)*

Ledwidge Hall Green, Drogheda 1812 CALF Turnkey Meath 6 Oaklee Housing Q1‐2021 Road, Slane, Co. Meath (Phase 2)

Ledwidge Hall Green, Drogheda 1813 CALF Turnkey Meath 16 Oaklee Housing Q1‐2021 Road, Slane, Co. Meath (Phase 3)*

Maudelins Brook, Duleek, 1814 CALF Turnkey Meath 20 Respond Q4‐2019 Co.Meath (Phase 1)*

Maydenhayes, Donacarney, Co. 1815 CALF Turnkey Meath 12 Cluid Housing Q1‐2020 Meath (Phase 1)*

Mill Lane, Flower Hill, Navan, Co 1816 CALF Turnkey Meath 20 Oaklee Housing Q4‐2016 Meath (Phase 1)

Millrace Court, Emmet Street, North & East Housing 1817 CALF Turnkey Meath 11 Q2‐2018 Trim, Co Meath (Phase 1) Association Ltd

Millteog, Athboy Road, Trim, Co. 1818 CALF Turnkey Meath 16 Oaklee Housing Q4‐2019 Meath (Phase 1)*

Millteog, Athboy Road, Trim, Co. 1819 CALF Turnkey Meath 9 Oaklee Housing Q2‐2020 Meath (Phase 2)*

Milltown, Ashbourne, Co Meath 1820 CALF Turnkey Meath 11 Cluid Housing Q1‐2017 (Phase 1)

24/05/2021 130/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Milltown, Ashbourne, Co Meath 1821 CALF Turnkey Meath 36 Cluid Housing Q4‐2017 (Phase 2)

Milltown, Ashbourne, Co Meath 1822 CALF Turnkey Meath 20 Cluid Housing Q4‐2017 (Phase 3)

Moydervey Manor, Longwood, 1823 CALF Turnkey Meath 13 Túath Housing Association Q4‐2020 Trim, Co. Meath (Phase 1)*

Narrow Ways, Bettystown, Co. 1824 CALF Turnkey Meath 6 Túath Housing Association Q3‐2020 Meath (Phase 1)

Narrow Ways, Bettystown, Co. 1825 CALF Turnkey Meath 6 Túath Housing Association Q3‐2020 Meath (Phase 2)

Oldbridge Manor, Drogheda, Co. 1826 CALF Turnkey Meath 29 Túath Housing Association Q4‐2020 Meath (Phase 1)*

Revised ‐ Fitzherbert Wood, Slane 1827 CALF Turnkey Meath 3 Túath Housing Association Q4‐2018 Road, Navan, Co Meath (Phase 1)

Revised ‐ Fitzherbert Wood, Slane 1828 CALF Turnkey Meath Road, Navan, Co Meath (Phase 5 Túath Housing Association Q4‐2020 10)

Revised ‐ Fitzherbert Wood, Slane 1829 CALF Turnkey Meath 6 Túath Housing Association Q2‐2019 Road, Navan, Co Meath (Phase 2)

Revised ‐ Fitzherbert Wood, Slane 1830 CALF Turnkey Meath 2 Túath Housing Association Q3‐2019 Road, Navan, Co Meath (Phase 3)

Revised ‐ Fitzherbert Wood, Slane 1831 CALF Turnkey Meath 5 Túath Housing Association Q3‐2019 Road, Navan, Co Meath (Phase 4)

Revised ‐ Fitzherbert Wood, Slane 1832 CALF Turnkey Meath 4 Túath Housing Association Q4‐2019 Road, Navan, Co Meath (Phase 5)

Revised ‐ Fitzherbert Wood, Slane 1833 CALF Turnkey Meath 6 Túath Housing Association Q1‐2020 Road, Navan, Co Meath (Phase 6)

Revised ‐ Fitzherbert Wood, Slane 1834 CALF Turnkey Meath 3 Túath Housing Association Q1‐2020 Road, Navan, Co Meath (Phase 7)

24/05/2021 131/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Revised ‐ Fitzherbert Wood, Slane 1835 CALF Turnkey Meath 4 Túath Housing Association Q3‐2020 Road, Navan, Co Meath (Phase 8)

Revised ‐ Fitzherbert Wood, Slane 1836 CALF Turnkey Meath 6 Túath Housing Association Q3‐2020 Road, Navan, Co Meath (Phase 9)

Royal Oaks, Enfield, Co Meath 1837 CALF Turnkey Meath 4 Cluid Housing Q2‐2017 (Phase 1)*

Royal Oaks, Enfield, Co. Meath 1838 CALF Turnkey Meath 4 Cluid Housing Q4‐2020 (Phase 2) (Phase 1)*

Royal Oaks, Enfield, Co. Meath 1839 CALF Turnkey Meath 14 Cluid Housing Q4‐2019 (Phase 2) (Phase 2)*

Royal Oaks, Enfield, Co. Meath 1840 CALF Turnkey Meath 16 Cluid Housing Q4‐2019 (Phase 2) (Phase 3)

Seabury Lawns, Mornington, Co. 1841 CALF Turnkey Meath 25 Cluid Housing Q3‐2017 Meath (Phase 1)

Station Road, Dunboyne, Co. 1842 CALF Turnkey Meath 24 Respond Q4‐2018 Meath (Phase 1)

The Bungalows, Dunshauglin, Co. Circle Voluntary Housing 1843 CALF Turnkey Meath 8 Q4‐2020 Meath (Phase 1)* Association Ltd

The Maudelins (Phase 2), Main 1844 CALF Turnkey Meath Street, Duleek, Co. Meath (Phase 30 Respond Q4‐2020 1)*

The Maudlins, Trim, Co. Meath 1845 CALF Turnkey Meath 9 Cluid Housing Q1‐2021 (Phase 1)

The Way, Broadmeadow Vale, 1846 CALF Turnkey Meath 2 Túath Housing Association Q4‐2019 Ratoath, Co. Meath (Phase 1)

The Willows, Dunshaughlin, Co. 1847 CALF Turnkey Meath 96 Cluid Housing Q1‐2021 Meath (Phase 1)*

Tubberclaire, Navan, Co Meath 1848 CALF Turnkey Meath 8 Cluid Housing Q2‐2016 (Phase 1)

24/05/2021 132/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Tubberclaire, Navan, Co Meath 1849 CALF Turnkey Meath 7 Cluid Housing Q3‐2016 (Phase 2)

Tubberclaire, Navan, Co Meath 1850 CALF Turnkey Meath 8 Cluid Housing Q4‐2016 (Phase 3)

Whitefield Hall, Bettystown, Co. 1851 CALF Turnkey Meath 14 Túath Housing Association Q2‐2020 Meath (Phase 1)

Whitefield Hall, Bettystown, Co. 1852 CALF Turnkey Meath 13 Túath Housing Association Q3‐2020 Meath (Phase 2)

Whitefield Hall, Bettystown, Co. 1853 CALF Turnkey Meath 2 Túath Housing Association Q2‐2019 Meath (Phase 3)

SHIP CONSTRUCTION Drumbear Wood, Monaghan 1854 Monaghan 12 *N/A Q4‐2017 TURNKEY Town

SHIP CONSTRUCTION 1855 Monaghan Knockroe Glen, Monaghan Town 6 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION Knockroe Glen, Monaghan Town 1856 Monaghan 8 *N/A Q2‐2017 TURNKEY (Phase 2)

SHIP CONSTRUCTION Knockroe Glen, Monaghan Town 1857 Monaghan 8 *N/A Q2‐2017 TURNKEY (Phase 1)

SHIP CONSTRUCTION 1858 Monaghan Killycard, Bree, Castleblaney 4 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 1859 Monaghan The Meadows, Smithborough 5 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 1860 Monaghan Maple Grove, Smithborough 11 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Plás an Bhrí, Rosevale, Bree, 1861 Monaghan 26 *N/A Q4‐2020 TURNKEY Castleblayney

SHIP CONSTRUCTION Ard na Radhairc, Carrickmacross, 1862 Monaghan 41 *N/A Q3‐2019 TURNKEY Co. Monaghan

24/05/2021 133/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1863 Monaghan Coill an Ri, Carrickmacross 6 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 1864 Monaghan The Meadows, Smithborough 5 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION Drummond Radhairc, 1865 Monaghan 1 *N/A Q3‐2019 TURNKEY Carrickmacross

SHIP CONSTRUCTION 1866 Monaghan Cnoc na Greine, Tydavnet 6 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 1867 Monaghan Coill Darach, Bree, Castleblayney 30 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q2‐2019, SHIP CONSTRUCTION 1868 Monaghan Coill an Ri, Carrickmacross 2 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION SINGLE 1869 Monaghan Folly Court, Ballybay 6 *N/A the scheme is fully STAGE approved.

1870 SHIP CONSTRUCTION Monaghan Bree, Castleblayney 8 *N/A Q2‐2019

1871 SHIP CONSTRUCTION Monaghan Latlorcan, Monaghan Town 43 *N/A Q4‐2019

1872 SHIP CONSTRUCTION Monaghan Fermanagh St., Clones 3 *N/A Q4‐2020

1873 SHIP CONSTRUCTION Monaghan Fermanagh St., Clones 3 *N/A Q4‐2020

1874 SHIP CONSTRUCTION Monaghan Fermanagh St., Clones 3 *N/A Q3‐2019

1875 SHIP CONSTRUCTION Monaghan Fermanagh St., Clones 6 *N/A Q3‐2019

1876 SHIP CONSTRUCTION Monaghan 2a & 3 Analore St., Clones 2 *N/A Q3‐2019

24/05/2021 134/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Abbey Gatehouse, Analore St., 1877 SHIP CONSTRUCTION Monaghan 4 *N/A Q3‐2019 Clones

1878 SHIP CONSTRUCTION Monaghan Lui Na Greine, Scotstown 6 *N/A Q2‐2020

1879 SHIP CONSTRUCTION Monaghan Latlorcan, Monaghan 16 *N/A Q4‐2018

Stage 4 approved Q1‐2021, 1880 SHIP CONSTRUCTION Monaghan 12 Church St., Ballybay 2 *N/A the scheme is fully approved.

1881 SHIP CONSTRUCTION Monaghan Fermanagh St., Clones 3 *N/A Q1‐2020

Stage 4 approved Q1‐2021, 1882 SHIP CONSTRUCTION Monaghan Church Hill, Clones 2 *N/A the scheme is fully approved.

1883 SHIP CONSTRUCTION Monaghan 13 McCurtain Street, Clones 1 *N/A Q1‐2021

Stage 4 approved Q1‐2020, 1884 SHIP CONSTRUCTION Monaghan Lui na Greine, Scotstown 26 *N/A the scheme is fully approved.

Drumillard, Castleblayney (Phase Castleblayney Care 1885 CAS CONSTRUCTION Monaghan 2 Q1‐2021 2) Housing Association Ltd

1886 CAS CONSTRUCTION Monaghan Liseggerton, Clones 19 Oaklee Housing Trust Q1‐2020

1887 CAS CONSTRUCTION Monaghan Convent Lands, Carrickmacross 7 Respond Q2‐2017

Stage 3 approved Q1‐2021, Birch Court Apts., 34 Main Street, North & East Housing the scheme is now 1888 CAS CONSTRUCTION Monaghan 4 Ballybay Association Ltd approved to proceed to tender.

Bree, Castleblayney, Co. 1889 CALF Turnkey Monaghan 11 Túath Housing Association Q4‐2020 Monaghan (Phase 1)

Bree, Castleblayney, Co. 1890 CALF Turnkey Monaghan 6 Túath Housing Association Q2‐2019 Monaghan (Phase 2)

24/05/2021 135/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Bree, Castleblayney, Co. 1891 CALF Turnkey Monaghan 8 Túath Housing Association Q2‐2019 Monaghan (Phase 3)

Bree, Castleblayney, Co. 1892 CALF Turnkey Monaghan 13 Túath Housing Association Q2‐2019 Monaghan (Phase 4)

Kingscourt Road, Carrickmacross, 1893 CALF Turnkey Monaghan 50 Respond Q4‐2019 Co Monaghan (Phase 1)

Lakeview Apartments, Drummond North & East Housing 1894 CALF Turnkey Monaghan Radhairc, Carrickmacross, Co 12 Q3‐2019 Association Ltd Monaghan (Phase 1)*

Macartan View, Latlorcan, Dublin 1895 CALF Turnkey Monaghan 20 Túath Housing Association Q4‐2020 Road, Monaghan (Phase 1)*

Macartan View, Latlorcan, Dublin 1896 CALF Turnkey Monaghan 21 Túath Housing Association Q4‐2020 Road, Monaghan (Phase 2)*

Magheross, Carrickmacross, Co 1897 CALF Turnkey Monaghan 7 Túath Housing Association Q3‐2019 Monaghan (Phase 1)

Magheross, Carrickmacross, Co 1898 CALF Turnkey Monaghan 6 Túath Housing Association Q3‐2019 Monaghan (Phase 2)

Magheross, Carrickmacross, Co 1899 CALF Turnkey Monaghan 6 Túath Housing Association Q3‐2019 Monaghan (Phase 3)

Magheross, Carrickmacross, Co 1900 CALF Turnkey Monaghan 14 Túath Housing Association Q3‐2019 Monaghan (Phase 4)

Post Tender ‐ Liseggerton Road, 1901 CALF Construction Monaghan 6 Oaklee Housing Q4‐2018 Clones (Phase 1)

SHIP CONSTRUCTION 1902 Offaly Mill Race, Ferbane 5 *N/A Q4‐2017 TURNKEY

SHIP CONSTRUCTION 1903 Offaly Cluain na Spideoga, Cloghan 6 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 1904 Offaly Frankford, Kilcormac 12 *N/A Q4‐2018 TURNKEY

24/05/2021 136/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 1905 Offaly McGregol, Birr (Phase 1) 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1906 Offaly Cluain na Greine, Cloneygowan 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1907 Offaly Main Street, Daingean 8 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1908 Offaly McCauley Drive, Birr 34 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1909 Offaly Riverside, Tullamore 5 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1910 Offaly Cluain na Greine, Clonygowan 3 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1911 Offaly Coolgarry, Walsh Island 4 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1912 Offaly Mucklagh, Tullamore 8 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 1913 Offaly Bog Road, Portarlington 28 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 1914 Offaly MacRegol Pairc, Birr 4 *N/A Q1‐2019 TURNKEY

SHIP CONSTRUCTION RAPID 1915 Offaly McGregol, Birr (Phase 2.1) 2 *N/A Q3‐2020 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1916 Offaly McGregol, Birr (Phase 2.2) 2 *N/A Q1‐2021 VOLUMETRIC

1917 SHIP CONSTRUCTION Offaly Chancery Lane, Tullamore 14 *N/A Q3‐2020

Stage 3 approved Q1‐2021, the scheme is now 1918 SHIP CONSTRUCTION Offaly Circular Road, Daingean 9 *N/A approved to proceed to tender.

24/05/2021 137/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 3 approved Q2‐2020, the scheme is now 1919 SHIP CONSTRUCTION Offaly Kylebeg, Banagher (Phase 2) 18 *N/A approved to proceed to tender.

1920 SHIP CONSTRUCTION Offaly Blundell Wood, Edenderry 33 *N/A Q4‐2019

Stage 2 approved Q3‐2020, 1921 SHIP CONSTRUCTION Offaly Beechgrove, Belmont 7 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2020, 1922 SHIP CONSTRUCTION Offaly Raheen ,Clara 38 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2020, 1923 SHIP CONSTRUCTION Offaly Elderberry Drive, Moneygall 4 *N/A full design/tender being prepared.

Stage 2 approved Q3‐2020, 1924 SHIP CONSTRUCTION Offaly Sr. Senan Avenue, Edenderry 4 *N/A full design/tender being prepared.

Stage 1 approved Q1‐2020, Chancery Lane, Tullamore (Phase 1925 SHIP CONSTRUCTION Offaly 20 *N/A outline design and costs 2) being prepared.

Stage 2 approved Q4‐2020, 1926 SHIP CONSTRUCTION Offaly 1 Newbridge St., Birr 1 *N/A full design/tender being prepared.

Mid Offaly Housing 1927 CAS CONSTRUCTION Offaly Mountbolus 4 Q4‐2019 Association Ltd

Túath Housing Association 1928 CAS CONSTRUCTION Offaly Killane Court, Edenderry 2 Q3‐2019 Ltd

Scurragh, Birr (AKA Camcor 1929 CAS CONSTRUCTION Offaly 6 Cluid Housing Association Q4‐2019 Green)

1930 CAS CONSTRUCTION Offaly Clonminch, Tullamore 19 Oaklee Housing Trust Q1‐2021

Stage 2 approved Q1‐2021, Presentation Convent, Sophia Housing 1931 CAS CONSTRUCTION Offaly 39 full design/tender being Portarlington Association Ltd prepared.

Stage 1 approved Q2‐2020, Sophia Housing 1932 CAS CONSTRUCTION Offaly Clonamore Hotel, Tullamore 17 outline design and costs Association Ltd being prepared.

24/05/2021 138/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

3 units, An , Crinkle, Birr, Co ‐ Operative Housing 1933 CALF Turnkey Offaly 3 Q1‐2021 Co. Offaly (Phase 1) Ireland Society Limited

Kearney’s Field, Tullamore, Co. 1934 CALF Construction Offaly 41 Oaklee Housing Q1‐2021 Offaly (Phase 1)

Killane Drive, Edenderry, Co Offaly 1935 CALF Construction Offaly 25 Túath Housing Association Q3‐2019 (Phase 1)

Rahan Road, Tullamore, Co. Offaly 1936 CALF Turnkey Offaly 26 Cluid Housing Q4‐2020 (Phase 1)*

SHIP CONSTRUCTION 1937 Roscommon Monksland, Athlone 10 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 1938 Roscommon Station Road, Termon, Boyle 10 *N/A Q1‐2019 TURNKEY

SHIP CONSTRUCTION 1939 Roscommon Lisroyne Court, Strokestown 10 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 1940 Roscommon Warren Grove, Boyle 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 1941 Roscommon Monksfield, Monksland 2 *N/A Q4‐2020 TURNKEY

1942 SHIP CONSTRUCTION Roscommon Cloonfad 3 *N/A Q4‐2019

Greenfields, Blackstick Road, 1943 SHIP CONSTRUCTION Roscommon 6 *N/A Q3‐2017 Roscommon Town

1944 SHIP CONSTRUCTION Roscommon River Oaks, Ballaghaderreen 10 *N/A Q4‐2017

1945 SHIP CONSTRUCTION Roscommon Silveroe Meadows, Boyle 12 *N/A Q4‐2020

1946 SHIP CONSTRUCTION Roscommon Cluain Fraoigh, Cloonbeirne 7 *N/A Q1‐2021

24/05/2021 139/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Old Tuam Road, Monksland, 1947 SHIP CONSTRUCTION Roscommon 2 *N/A Q4‐2020 Athlone

Meadowbrook, Ballyclare Td., 1948 SHIP CONSTRUCTION Roscommon 16 *N/A Q3‐2020 Ballyleague, Co. Roscommon

1949 SHIP CONSTRUCTION Roscommon Lisroyne Td., Strokestown 10 *N/A Q4‐2020

Stage 1 approved Q4‐2020, Windmill Road, Elphin, Co. 1950 SHIP CONSTRUCTION Roscommon 6 *N/A outline design and costs Roscommon being prepared.

Stage 1 approved Q1‐2021, Lakeview Heights, Ballspark Td., 1951 SHIP CONSTRUCTION Roscommon 4 *N/A outline design and costs Boyle being prepared.

Stage 1 approved Q1‐2021, Lisnamult, Ardnanagh Td., 1952 SHIP CONSTRUCTION Roscommon 8 *N/A outline design and costs Roscommon Town being prepared.

Castle View Apartments, Block B, Co ‐ Operative Housing 1953 CALF Turnkey Roscommon 10 Q4‐2019 Roscommon Town (Phase 1) Ireland Society Limited

Monksland, Athlone, Co. 1954 CALF Turnkey Roscommon 35 Túath Housing Association Q4‐2019 Roscommon (Phase 1)*

Revised ‐ Monksfield Park, 1955 CALF Turnkey Roscommon 13 Cluid Housing Q3‐2018 Bealnamulla, Athlone (Phase 1)

River Oaks, Kilcolman, 1956 CALF Turnkey Roscommon Ballaghaderreen, Co. Roscommon 12 Respond Q1‐2018 (Phase 1)

PUBLIC PRIVATE PARTNERSHIP 1957 Roscommon The Walk, Roscommon Town 53 *N/A Q4‐2019 (Bundle 2)

SHIP CONSTRUCTION 1958 Fairgreen Square, Ballisodare 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION SINGLE 1959 Sligo St. Joseph's Terrace, Sligo 1 *N/A Q4‐2019 STAGE

1960 SHIP CONSTRUCTION Sligo 18 *N/A Q4‐2019

24/05/2021 140/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

1961 SHIP CONSTRUCTION Sligo Knappagh Road, Sligo 28 *N/A Q4‐2020

1962 SHIP CONSTRUCTION Sligo Caltragh, Culleens 1 *N/A Q4‐2018

1963 SHIP CONSTRUCTION Sligo Fr. Flanagan Terrace 14 *N/A Q3‐2018

1964 SHIP CONSTRUCTION Sligo Daghloonagh, Keash ‐ SRD 1 *N/A Q4‐2016

1965 SHIP CONSTRUCTION Sligo 14 *N/A Q4‐2019

1966 SHIP CONSTRUCTION Sligo Fr. Flanagan Terrace 8 *N/A Q4‐2017

1967 SHIP CONSTRUCTION Sligo Connolly Park, 10 *N/A Q3‐2020

1968 SHIP CONSTRUCTION Sligo 10 *N/A Q4‐2019

Stage 1 approved Q4‐2018, Robbers' Lane, Maugheraboy, 1969 SHIP CONSTRUCTION Sligo 62 *N/A outline design and costs Sligo being prepared.

1970 SHIP CONSTRUCTION Sligo House at Ballinode 1 *N/A Q4‐2018

1971 SHIP CONSTRUCTION Sligo SRD at Crowagh, Dromore West 1 *N/A Q4‐2020

Stage 2 approved Q4‐2020, 1972 SHIP CONSTRUCTION Sligo Gormley Park, Bunnanadden 6 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 1973 SHIP CONSTRUCTION Sligo Connolly Park, Tubbercurry 15 *N/A full design/tender being prepared.

Stage 1 approved Q4‐2020, Geldof Drive & Centre Park, 1974 REGENERATION Sligo 30 *N/A outline design and costs Cranmore, Sligo being prepared.

24/05/2021 141/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Society of Saint Vincent de 1975 CAS CONSTRUCTION Sligo Cuan Iosa, 8 Q3‐2020 Paul

Newgrove Housing 1976 CAS CONSTRUCTION Sligo Killeshin, First Sea Road, Sligo 5 Q4‐2020 Association Ltd

SHIP CONSTRUCTION 1977 South Dublin Ardsolus, Kingswood, Dublin 24 2 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION White Pines, Stocking Avenue, 1978 South Dublin 26 *N/A Q4‐2018 TURNKEY , Dublin 16

SHIP CONSTRUCTION Shackleton Park / Gandon Park, 1979 South Dublin 22 *N/A Q4‐2019 TURNKEY Adamstown

SHIP CONSTRUCTION 1980 South Dublin Gandon Park, Adamstown, Lucan 12 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION SINGLE 1981 South Dublin 37 Greenfort Gardens, 2 *N/A Q4‐2020 STAGE

SHIP CONSTRUCTION RAPID Killininny Road, (Old Mill, 1982 South Dublin 24 *N/A Q4‐2018 VOLUMETRIC Old Bawn)

SHIP CONSTRUCTION RAPID 1983 South Dublin St Cuthbert's, Clondalkin (Phase 1) 63 *N/A Q3‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1984 South Dublin St. Aidan's Brookfield, 47 *N/A Q2‐2018 VOLUMETRIC

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION RAPID 1985 South Dublin St. Marks Avenue, Clondalkin 41 *N/A the scheme is fully VOLUMETRIC approved.

SHIP CONSTRUCTION RAPID 1986 South Dublin St. Aidan's Brookfield, Tallaght 22 *N/A Q3‐2018 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1987 South Dublin St. Aidan's Brookfield, Tallaght 21 *N/A Q4‐2018 VOLUMETRIC

SHIP CONSTRUCTION RAPID 1988 South Dublin Riversdale, Clondalkin, Dublin 22 22 *N/A Q4‐2020 VOLUMETRIC

24/05/2021 142/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q1‐2019, SHIP CONSTRUCTION RAPID 1989 South Dublin Riverside Cottages, 11 *N/A full design/tender being VOLUMETRIC prepared.

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION RAPID 1990 South Dublin Riversdale, Clondalkin, Dublin 22 21 *N/A the scheme is fully VOLUMETRIC approved.

1991 SHIP CONSTRUCTION South Dublin Killinarden, Tallaght 17 *N/A Q4‐2018

1992 SHIP CONSTRUCTION South Dublin Letts Field, Neilstown, Clondalkin 37 *N/A Q4‐2018

Owendoher, , 1993 SHIP CONSTRUCTION South Dublin 40 *N/A Q1‐2019 Rathfarnham

1994 SHIP CONSTRUCTION South Dublin Dromcarra, Tallaght 14 *N/A Q4‐2018

1995 SHIP CONSTRUCTION South Dublin Fortunestown (MacUilliam) 28 *N/A Q4‐2018

1996 SHIP CONSTRUCTION South Dublin Mayfield Estate, Clondalkin 17 *N/A Q2‐2018

1997 SHIP CONSTRUCTION South Dublin St Marks Green, Clondalkin 11 *N/A Q3‐2018

Stage 2 approved Q4‐2020, Balgaddy F, Griffeen Avenue, 1998 SHIP CONSTRUCTION South Dublin 69 *N/A full design/tender being Lucan Co. Dublin prepared.

1999 SHIP CONSTRUCTION South Dublin St Finians 2 *N/A Q3‐2016

2000 SHIP CONSTRUCTION South Dublin Suncroft, Tallaght 10 *N/A Q4‐2016

2001 SHIP CONSTRUCTION South Dublin Belgard Road 3 *N/A Q1‐2016

St. Catherine’s, Knockmore 2002 SHIP CONSTRUCTION South Dublin 12 *N/A Q4‐2020 Avenue, Killinarden, Tallaght

24/05/2021 143/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

2003 SHIP CONSTRUCTION South Dublin Homeville, , Dublin 16 16 *N/A Q4‐2020

2004 SHIP CONSTRUCTION South Dublin Killinarden, Tallaght 9 *N/A Q1‐2019

Stage 3 approved Q4‐2020, Nangor Road, Clondalkin, Dublin the scheme is now 2005 SHIP CONSTRUCTION South Dublin 93 *N/A 22 approved to proceed to tender.

Túath Housing Association 2006 CAS CONSTRUCTION South Dublin Collinstown Grove, Clondalkin 4 Q1‐2020 Ltd

Simon Community : Dublin 2007 CAS CONSTRUCTION South Dublin Old Nangor Road, Clondalkin 10 Q4‐2019 Simon

2 properties Tullyhall, Lucan, 2008 CALF Turnkey South Dublin 2 Túath Housing Association Q2‐2019 County Dublin (Phase 1)*

6 units Elder Heath, Kiltipper 2009 CALF Turnkey South Dublin Road, Tallaght, Dublin 24 (Phase 6 Cluid Housing Q4‐2019 1)*

Ardsolus, Old Naas Road, Dublin 2010 CALF Turnkey South Dublin 10 Respond Q3‐2019 22 (Phase 1)

Aylmer Heath, Newcastle, Co. 2011 CALF Turnkey South Dublin 32 Respond Q4‐2020 Dublin (Phase 1)

Ballynakelly, Newcastle, Co. 2012 CALF Turnkey South Dublin 6 Túath Housing Association Q4‐2018 Dublin (Phase 1)

Ballynakelly, Newcastle, Co. 2013 CALF Turnkey South Dublin 4 Túath Housing Association Q1‐2019 Dublin (Phase 2)

Balrothery, Castletymon Road, 2014 CALF Turnkey South Dublin 13 Cluid Housing Q4‐2019 Dublin Road (Phase 1)*

Broadfield Grove, Rathcoole, Co. 2015 CALF Turnkey South Dublin 14 Oaklee Housing Q3‐2017 Dublin (Phase 1)*

Burgage Gardens, Newcastle, Co. 2016 CALF Turnkey South Dublin 4 Respond Q2‐2020 Dublin (Phase 1)*

24/05/2021 144/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Burgage, Newcastle, Co. Dublin 2017 CALF Turnkey South Dublin 10 Respond Q4‐2019 (Phase 1)

Burgage, Newcastle, Co. Dublin 2018 CALF Turnkey South Dublin 26 Respond Q2‐2020 (Phase 2)

Cloverhill Road, Raheen, 2019 CALF Turnkey South Dublin 45 Túath Housing Association Q4‐2020 Clondalkin, Dublin 22 (Phase 1)

Cloverhill Road, Raheen, 2020 CALF Turnkey South Dublin 15 Túath Housing Association Q4‐2020 Clondalkin, Dublin 22 (Phase 2)

Cloverhill Road, Raheen, 2021 CALF Turnkey South Dublin 23 Túath Housing Association Q4‐2020 Clondalkin, Dublin 22 (Phase 3)*

Cuil Duin Green, Cuil Duin, Fold Housing Association 2022 CALF Turnkey South Dublin 24 Q4‐2020 Citywest, Dublin 24 (Phase 1)* Ireland Ltd

De Selby Heights, Tallaght, Dublin 2023 CALF Turnkey South Dublin 9 Túath Housing Association Q4‐2019 24 (Phase 1)

Dodderbrook (Apartments), 2024 CALF Turnkey South Dublin Oldcourt Road, Ballycullen, Dublin 6 Cluid Housing Q1‐2018 24 (Phase 1)*

Dodderbrook (Houses), Oldcourt 2025 CALF Turnkey South Dublin Road, Ballycullen, Dublin 24 8 Cluid Housing Q1‐2018 (Phase 1)*

Dodderbrook, Old Court Rd, 2026 CALF Turnkey South Dublin 4 Cluid Housing Q4‐2019 Ballycullen, Dublin 24 (Phase 1)*

Dodderbrook, Old Court Rd, 2027 CALF Turnkey South Dublin 9 Cluid Housing Q1‐2021 Ballycullen, Dublin 24 (Phase 2)*

Dodderbrook, Oldcourt Road, 2028 CALF Turnkey South Dublin 4 Cluid Housing Q3‐2018 Ballycllen, Dublin 24 (Phase 1)*

Edenbrook, Citywest, Dublin 24 2029 CALF Turnkey South Dublin 17 Túath Housing Association Q4‐2019 (Phase 1)

Elder Heath, Kiltipper Road, 2030 CALF Turnkey South Dublin 18 Cluid Housing Q1‐2018 Tallaght, Dublin 24 (Phase 1)*

24/05/2021 145/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Elder Heath, Kiltipper Road, 2031 CALF Turnkey South Dublin 10 Cluid Housing Q2‐2018 Tallaght, Dublin 24 (Phase 2)*

Fernwood Green and Maplewood 2032 CALF Construction South Dublin Heights, Tallaght, Dublin (Phase 40 Cluid Housing Q3‐2020 1)

Finnstown, Lucan, Co. Dublin 2033 CALF Turnkey South Dublin 70 Respond Q4‐2018 (Phase 1)

Finnstown, Lucan, Co. Dublin 2034 CALF Turnkey South Dublin 24 Respond Q4‐2018 (Phase 2)*

Green Lane, Rathcoole, Co. Dublin 2035 CALF Turnkey South Dublin 12 Túath Housing Association Q4‐2020 (Phase 1)*

Green Lane, Rathcoole, Co. Dublin 2036 CALF Turnkey South Dublin 9 Túath Housing Association Q4‐2020 (Phase 2)*

Kingswood, Old Road, 2037 CALF Turnkey South Dublin 24 Respond Q4‐2018 Tallaght, Dublin 24 (Phase 1)*

Millford Manor, Clondalkin ‐ 2038 CALF Turnkey South Dublin 13 Cluid Housing Q2‐2018 Apartments (Phase 1)*

Millford Manor, Clondalkin ‐ 2039 CALF Turnkey South Dublin 12 Cluid Housing Q4‐2018 Apartments (Phase 2)

Millford Manor, Clondalkin ‐ 2040 CALF Turnkey South Dublin 25 Cluid Housing Q1‐2017 Houses (Phase 1)

Millford Manor, Clondalkin ‐ 2041 CALF Turnkey South Dublin 15 Cluid Housing Q3‐2017 Houses (Phase 2)

Millford Manor, Cloverhill Road, 2042 CALF Turnkey South Dublin 2 Cluid Housing Q4‐2018 Clondalkin, Dublin 22 (Phase 1)*

New Bancroft, Tallaght, Dublin 24 2043 CALF Turnkey South Dublin 16 Cluid Housing Q3‐2017 (Phase 1)*

Palmerstown Avenue, Dublin 20 2044 CALF Turnkey South Dublin 7 Respond Q4‐2020 (Phase 1)

24/05/2021 146/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Palmerstown Way, Clondalkin, 2045 CALF Turnkey South Dublin 6 Túath Housing Association Q3‐2018 Dublin 22 (Phase 1)*

Phase 2, Aylmer Drive, Aylmer 2046 CALF Turnkey South Dublin Heath, Newcastle, Co. Dublin 17 Respond Q4‐2019 (Phase 1)*

Raheen House, Old Nangor Road, Circle Voluntary Housing 2047 CALF Turnkey South Dublin 9 Q4‐2019 Clondalkin, Dublin 22 (Phase 1) Association Ltd

Rathmill Meadows and Green, 2048 CALF Turnkey South Dublin 11 Oaklee Housing Q4‐2019 Rathcoole, Co. Dublin (Phase 1)*

Sallypark, Clondalkin, Dublin 22 2049 CALF Turnkey South Dublin 85 Cluid Housing Q4‐2020 (Phase 1)*

Scholarstown Road, Rathfarnham, Circle Voluntary Housing 2050 CALF Turnkey South Dublin 14 Q2‐2019 Dublin 16 (Phase 1)* Association Ltd

Scholarstown Wood (Apartments), Scholarstown Road, Circle Voluntary Housing 2051 CALF Turnkey South Dublin 6 Q2‐2018 Rathfarnham, Dublin 16 (Phase Association Ltd 1)*

Scholarstown Wood (Houses), Circle Voluntary Housing 2052 CALF Turnkey South Dublin Scholarstown Road, Rathfarnham, 3 Q4‐2017 Association Ltd Dublin 16 (Phase 1)*

Scholarstown Wood (Houses), Circle Voluntary Housing 2053 CALF Turnkey South Dublin Scholarstown Road, Rathfarnham, 4 Q2‐2018 Association Ltd Dublin 16 (Phase 2)*

Scholarstown Wood (Houses), Circle Voluntary Housing 2054 CALF Turnkey South Dublin Scholarstown Road, Rathfarnham, 1 Q2‐2019 Association Ltd Dublin 16 (Phase 3)*

Shackleton Park, Lucan, Co. Dublin 2055 CALF Turnkey South Dublin 8 Cluid Housing Q2‐2019 (Phase 1)*

Somerton, Lucan, Co. Dublin 2056 CALF Turnkey South Dublin 32 Respond Q4‐2019 (Phase 1)*

St. Catherine’s, Knockmore Sophia Housing 2057 CALF Construction South Dublin Avenue, Killinarden, Tallaght, 2 Q4‐2020 Association Ltd Dublin 24 (Phase 1)

St. Johns, Firhouse, Dublin 24 2058 CALF Turnkey South Dublin 10 Respond Q4‐2019 (Phase 1)*

24/05/2021 147/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Station Road, Clondalkin, Co. 2059 CALF Turnkey South Dublin 5 Respond Q3‐2017 Dublin (Phase 1)

Stone Masons Court, 2060 CALF Turnkey South Dublin Fortunestown Lane, Citywest 12 Cluid Housing Q2‐2019 Dublin (Phase 1)*

Temple Court, Temple Woods, 2061 CALF Turnkey South Dublin Greenhills Road, Dublin 12 (Phase 6 Túath Housing Association Q4‐2018 1)*

The Mews, Citywest Village, Fold Housing Association 2062 CALF Turnkey South Dublin 22 Q4‐2020 Citywest, Dublin 24 (Phase 1)* Ireland Ltd

The Rise, Citywest Village, Fold Housing Association 2063 CALF Turnkey South Dublin 13 Q4‐2019 Citywest, Dublin 24 (Phase 1)* Ireland Ltd

The Weir, Whitestown Way, 2064 CALF Construction South Dublin 81 Cluid Housing Q1‐2021 Tallaght, Dublin 24 (Phase 1)

Tullyhall, Lucan, Co Dublin (Phase 2065 CALF Turnkey South Dublin 2 Túath Housing Association Q3‐2017 1)*

Tullyhall, Lucan, Co Dublin (Phase 2066 CALF Turnkey South Dublin 2 Túath Housing Association Q4‐2018 2)*

Westpark, Garters Lane, Saggert, 2067 CALF Turnkey South Dublin 28 Cluid Housing Q4‐2018 Co Dublin (Phase 1)

Westpark, Garters Lane, Saggert, 2068 CALF Turnkey South Dublin 28 Cluid Housing Q2‐2019 Co Dublin (Phase 2)

Westpark, Garters Lane, Saggert, 2069 CALF Turnkey South Dublin 28 Cluid Housing Q4‐2019 Co Dublin (Phase 3)

Wilkins Court, Limekiln Lane, Circle Voluntary Housing 2070 CALF Turnkey South Dublin 6 Q2‐2019 Dublin 12 (Phase 1)* Association Ltd

Wilkins View, Greenhills, Dublin Circle Voluntary Housing 2071 CALF Turnkey South Dublin 3 Q2‐2018 12 (Phase 1)* Association Ltd

Willowview, Ballyboden Road, 2072 CALF Turnkey South Dublin Rathfarnham, Dublin 14 (Phase 12 Cluid Housing Q4‐2019 1)*

24/05/2021 148/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

PUBLIC PRIVATE PARTNERSHIP Corkage Grange (part of 2073 South Dublin 109 *N/A Q4‐2020 (Bundle 1) Kilcarbery)

SHIP CONSTRUCTION 2074 Tipperary Cloneen Road, Fethard 6 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 2075 Tipperary Strylea, Fethard 3 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 2076 Tipperary Ardan, Borrisokane 9 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2077 Tipperary An Grianan, Killenaule, Thurles 4 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2078 Tipperary Ardan, Borrisokane (Phase 2) 4 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION An Grianan, Killenaule, Thurles 2079 Tipperary 5 *N/A Q4‐2019 TURNKEY (Phase 2)

SHIP CONSTRUCTION 2080 Tipperary Prior Park, Clonmel 20 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION Ma Charoin, Manna South, 2081 Tipperary 13 *N/A Q3‐2020 TURNKEY Templemore

SHIP CONSTRUCTION 2082 Tipperary Cloneen Road, Fethard (Phase 2) 5 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 2083 Tipperary Cloneen Road, Fethard (Phase 3) 6 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2084 Tipperary Glencree, Newport 3 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2085 Tipperary Cloneen Road, Fethard (Phase 4) 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION An Grianan, Killenaule, Thurles 2086 Tipperary 5 *N/A Q4‐2019 TURNKEY (Phase 3)

24/05/2021 149/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 2087 Tipperary Prior Park, Clonmel 21 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 2088 Tipperary Rosanna Close, Tipperary Town 18 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 2089 Tipperary Glenconnor Road, Clonmel 21 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q4‐2020, SHIP CONSTRUCTION 2090 Tipperary Clogheen Road, Ardfinnan 13 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 2091 Tipperary Rosanna Close, Tipperary Town 1 *N/A Q3‐2020 TURNKEY

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION 2092 Tipperary Roscrea 2 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION SINGLE Mulkear View, Newport, 2093 Tipperary 3 *N/A Q4‐2018 STAGE Tipperary

SHIP CONSTRUCTION SINGLE 2094 Tipperary Grange Road, Ballina 4 *N/A Q4‐2020 STAGE

2095 SHIP CONSTRUCTION Tipperary Ard na Greine, Clonmel 2 *N/A Q4‐2020

2096 SHIP CONSTRUCTION Tipperary Knockanrawley 14 *N/A Q1‐2021

2097 SHIP CONSTRUCTION Tipperary Mill Road, Thurles 28 *N/A Q2‐2020

2098 SHIP CONSTRUCTION Tipperary Mulkear View, Newport 11 *N/A Q4‐2020

2099 SHIP CONSTRUCTION Tipperary Treacy Park, Carrick on Suir 1 *N/A Q3‐2018

2100 SHIP CONSTRUCTION Tipperary Templetouhy 10 *N/A Q4‐2019

24/05/2021 150/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

2101 SHIP CONSTRUCTION Tipperary Abbey Street, Cahir 10 *N/A Q3‐2020

2102 SHIP CONSTRUCTION Tipperary Borrisokane 16 *N/A Q3‐2020

2103 SHIP CONSTRUCTION Tipperary Portroe, Nenagh 14 *N/A Q4‐2020

2104 SHIP CONSTRUCTION Tipperary Cloughjordan 2 *N/A Q3‐2019

2105 SHIP CONSTRUCTION Tipperary Glenconnor Road, Clonmel 26 *N/A Q3‐2020

2106 SHIP CONSTRUCTION Tipperary Gortataggart, Thurles 2 *N/A Q4‐2018

2107 SHIP CONSTRUCTION Tipperary Kilcooly Way, Gortnahoe 5 *N/A Q3‐2020

2108 SHIP CONSTRUCTION Tipperary Lacey Avenue, Templemore 3 *N/A Q3‐2016

2109 SHIP CONSTRUCTION Tipperary Mitchel St., Thurles 1 *N/A Q4‐2019

2110 SHIP CONSTRUCTION Tipperary Borrisoleigh 1 *N/A Q4‐2016

2111 SHIP CONSTRUCTION Tipperary Lower Ballingarry 1 *N/A Q2‐2016

2112 SHIP CONSTRUCTION Tipperary Poulamaleen, Faugheen 1 *N/A Q2‐2016

2113 SHIP CONSTRUCTION Tipperary Cormack Drive, Nenagh 12 *N/A Q3‐2020

2114 SHIP CONSTRUCTION Tipperary Lacey Avenue, Templemore 1 *N/A Q3‐2017

24/05/2021 151/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

2115 SHIP CONSTRUCTION Tipperary Borrisoleigh 1 *N/A Q4‐2018

Stage 3 approved Q1‐2021, the scheme is now 2116 SHIP CONSTRUCTION Tipperary Bansha 14 *N/A approved to proceed to tender. Stage 3 approved Q3‐2020, Ned Hayes Drive, Twomileborris, the scheme is now 2117 SHIP CONSTRUCTION Tipperary 22 *N/A Thurles approved to proceed to tender. Stage 3 approved Q1‐2021, the scheme is now 2118 SHIP CONSTRUCTION Tipperary Donohill, 8 *N/A approved to proceed to tender.

2119 SHIP CONSTRUCTION Tipperary Mullinahone 10 *N/A Q1‐2021

Stage 3 approved Q4‐2020, the scheme is now 2120 SHIP CONSTRUCTION Tipperary Clerihan 14 *N/A approved to proceed to tender.

Stage 4 approved Q1‐2021, 2121 SHIP CONSTRUCTION Tipperary Ard Alainn, Moyne 9 *N/A the scheme is fully approved.

Stage 4 approved Q1‐2021, 2122 SHIP CONSTRUCTION Tipperary Ardcroney 4 *N/A the scheme is fully approved.

Stage 2 approved Q1‐2021, 2123 SHIP CONSTRUCTION Tipperary Comeragh Drive, Clonmel 2 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 2124 SHIP CONSTRUCTION Tipperary Church Street, Templemore 2 *N/A full design/tender being prepared.

Stage 2 approved Q4‐2020, 2125 SHIP CONSTRUCTION Tipperary Castle Crescent, Nenagh 9 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 2126 SHIP CONSTRUCTION Tipperary Boherclough Street, Cashel 12 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 2127 SHIP CONSTRUCTION Tipperary Grove Street. Roscrea 7 *N/A full design/tender being prepared.

Stage 2 approved Q1‐2021, 2128 SHIP CONSTRUCTION Tipperary William Street, Clonmel 4 *N/A full design/tender being prepared.

24/05/2021 152/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

2129 SHIP CONSTRUCTION Tipperary Knockanrawley 14 *N/A Q4‐2019

Monastery Close, Templemore Thurles Lions Trust 2130 CAS CONSTRUCTION TURNKEY Tipperary 15 Q2‐2019 Road, Thurles Housing Assoc.

Nenagh Voluntary Housing 2131 CAS CONSTRUCTION TURNKEY Tipperary Drummin Village, Nenagh 8 Q4‐2020 Association

2132 CAS CONSTRUCTION Tipperary Glenconnor Road, Clonmel 9 Cluid Housing Association Q4‐2020

Stanwix House, Kickham Street, Thurles Lions Trust 2133 CAS CONSTRUCTION Tipperary 19 Q1‐2021 Thurles Housing Assoc.

Stage 2 approved Q4‐2020, Templemore Voluntary 2134 CAS CONSTRUCTION Tipperary Main Street, Templemore 14 full design/tender being Housing Association prepared.

Stage 4 approved Q1‐2021, SPADE – St. Patrick’s 2135 CAS CONSTRUCTION Tipperary Deerpark Road, Ashwell's Lot 2 the scheme is fully Dwellings for the Elderly approved.

An Duiche, Tipperary Town, Co. 2136 CALF Turnkey Tipperary 41 Respond Q4‐2019 Tipperary (Phase 1)

An Duiche, Tipperary Town, Co. 2137 CALF Turnkey Tipperary 2 Respond Q4‐2019 Tipperary (Phase 2)

Ashbury, Roscrea, Co Tipperary 2138 CALF Turnkey Tipperary 12 Cluid Housing Q2‐2017 (Phase 1)

Ashgrove, Monadreen, Thurles, Co ‐ Operative Housing 2139 CALF Turnkey Tipperary 9 Q4‐2018 Co Tipperary (Phase 1) Ireland Society Limited

Ashgrove, Monadreen, Thurles, Co ‐ Operative Housing 2140 CALF Turnkey Tipperary 10 Q4‐2019 Co. Tipperary (Phase 1) Ireland Society Limited

Ashgrove, Monadreen, Thurles, Co ‐ Operative Housing 2141 CALF Turnkey Tipperary 7 Q4‐2020 Co. Tipperary (Phase 2) Ireland Society Limited

Mill Street, Carrick on Suir, Co. 2142 CALF Turnkey Tipperary 22 Túath Housing Association Q3‐2020 Tipperary (Phase 1)

24/05/2021 153/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

The Avenue, Drummin Village, Focus Housing Association 2143 CALF Turnkey Tipperary 13 Q4‐2020 Nenagh, Co. Tipperary (Phase 1) CLG

SHIP CONSTRUCTION 2144 Waterford Kilrush, 8 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 2145 Waterford Gibbethill, Gracedieu 5 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION Carrickphierish, Gracedieu, 2146 Waterford 31 *N/A Q4‐2018 TURNKEY Waterford

SHIP CONSTRUCTION 2147 Waterford Shandon, Dungarvan 5 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 2148 Waterford Airport Road, Waterford City 33 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2149 Waterford Kilrush, Dungarvan ‐ Phase 2 10 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2150 Waterford Kilrush, Dungarvan ‐ Phase 3 21 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2151 Waterford Lacken Road, Waterford 20 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 2152 Waterford Lacken Road, Waterford ‐ Phase 2 14 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2153 Waterford Lacken Road, Waterford ‐ Phase 3 6 *N/A Q2‐2020 TURNKEY

SHIP CONSTRUCTION 2154 Waterford Lacken Road, Waterford ‐ Phase 4 15 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION Estuary Heights, Shandon, 2155 Waterford 6 *N/A Q3‐2019 TURNKEY Dungarvan

SHIP CONSTRUCTION 2156 Waterford Railway Gardens, Lismore 17 *N/A Q3‐2019 TURNKEY

24/05/2021 154/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Estuary Heights, Shandon, 2157 Waterford 8 *N/A Q4‐2019 TURNKEY Dungarvan

SHIP CONSTRUCTION Estuary Heights, Shandon, 2158 Waterford 6 *N/A Q4‐2019 TURNKEY Dungarvan

SHIP CONSTRUCTION Mount Suir, Gracedieu, 2159 Waterford 18 *N/A Q4‐2019 TURNKEY Carrickphierish

SHIP CONSTRUCTION 2160 Waterford 19 & 20 Bride View Close, Tallow 2 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION Mount William, Williamstown, 2161 Waterford 19 *N/A Q4‐2020 TURNKEY Waterford City

SHIP CONSTRUCTION 7A and 8A Barnes Lane, The Glen, 2162 Waterford 2 *N/A Q4‐2019 TURNKEY Waterford

SHIP CONSTRUCTION 4 and 12 Ard Alainn, Sherlock 2163 Waterford 2 *N/A Q2‐2020 TURNKEY Walk, Gracedieu, Waterford

SHIP CONSTRUCTION Mount William, Williamstown, 2164 Waterford 13 *N/A Q1‐2021 TURNKEY Waterford City

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION Mount William, Williamstown, 2165 Waterford 33 *N/A the scheme is fully TURNKEY Waterford City approved.

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION SINGLE Apt 1 and Apt 2 Rivercourt, 2166 Waterford 2 *N/A the scheme is fully STAGE Grattan Quay, Waterford City approved.

Stage 2 approved Q3‐2019, SHIP CONSTRUCTION RAPID 2167 Waterford Ballygunner, Waterford City 49 *N/A full design/tender being VOLUMETRIC prepared.

Stage 2 approved Q2‐2020, SHIP CONSTRUCTION RAPID 2168 Waterford Ballynaneashagh, Waterford City 22 *N/A full design/tender being VOLUMETRIC prepared.

Stage 2 approved Q2‐2018, An Garran, Crobally Upper, 2169 SHIP CONSTRUCTION Waterford 50 *N/A full design/tender being Tramore prepared.

2170 SHIP CONSTRUCTION Waterford Alms Houses, Tallow 4 *N/A Q4‐2018

24/05/2021 155/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Ardmore Park/Priory Lawn, 2171 SHIP CONSTRUCTION Waterford Waterford City (also referred to as 5 *N/A Q3‐2020 Saviours Green, Ballybeg)

2172 SHIP CONSTRUCTION Waterford Ballinroad, Dungarvan 21 *N/A Q2‐2020

2173 SHIP CONSTRUCTION Waterford Barrack Street, Cappoquin 4 *N/A Q4‐2017

2174 SHIP CONSTRUCTION Waterford Coolfin Woods, Portlaw 12 *N/A Q2‐2019

2175 SHIP CONSTRUCTION Waterford Larchville, Waterford City 5 *N/A Q1‐2020

2176 SHIP CONSTRUCTION Waterford Patrick Street, Tramore 2 *N/A Q3‐2018

2177 SHIP CONSTRUCTION Waterford Doyle Street, Waterford City 4 *N/A Q2‐2020

2178 SHIP CONSTRUCTION Waterford Old Cinema Site, Dungarvan 15 *N/A Q4‐2016

Stage 2 approved Q3‐2018, 2179 SHIP CONSTRUCTION Waterford The Glen, Bridge St, Waterford 17 *N/A full design/tender being prepared.

Stage 1 approved Q1‐2018, Clarendon Court, Penrose Lane, 2180 SHIP CONSTRUCTION Waterford 24 *N/A outline design and costs Waterford being prepared.

2181 SHIP CONSTRUCTION Waterford Summerland Square, Waterford 12 *N/A Q1‐2021

2182 SHIP CONSTRUCTION Waterford Bath St, Waterford City 4 *N/A Q4‐2019

Graigueshoneen, Kilmacthomas, 2183 SHIP CONSTRUCTION Waterford 16 *N/A Q4‐2020 Co Waterford

Stage 3 approved Q1‐2021, Mount Esker, Ballytruckle Road, the scheme is now 2184 SHIP CONSTRUCTION Waterford 14 *N/A Waterford City approved to proceed to tender.

24/05/2021 156/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q3‐2020, 2185 SHIP CONSTRUCTION Waterford Newgate Street, Waterford City 36 *N/A outline design and costs being prepared.

Society of Saint Vincent de 2186 CAS CONSTRUCTION Waterford Convent Hill, Tramore 10 Q1‐2017 Paul

Stage 2 approved Q2‐2016, Powersfield, Hennessys Road, 2187 CAS CONSTRUCTION Waterford 3 Focus Ireland full design/tender being Waterford prepared.

2188 CAS CONSTRUCTION Waterford Wadding Manor, Ferrybank 10 Respond Q4‐2019

The Paddocks, Williamstown Rd. Anvers Housing 2189 CAS CONSTRUCTION Waterford 9 Q4‐2020 Waterford Association Ltd

2190 CALF Turnkey Waterford Kilbarry, Waterford (Phase 1) 69 Respond Q3‐2020

St Johns College, Waterford 2191 CALF Construction Waterford 36 Respond Q1‐2016 (Phase 1)

The Walk, Fairfield Park, Kilcohan, Circle Voluntary Housing 2192 CALF Turnkey Waterford 40 Q4‐2019 Waterford (Phase 1) Association Ltd

PUBLIC PRIVATE PARTNERSHIP 2193 Waterford Slievekeale, Waterford City 58 *N/A Q4‐2019 (Bundle 2)

2194 SHIP DIALOG Westmeath Lissywollen, Athlone 55 *N/A Q1‐2021

Lissywollen, Athlone (Phase 2A 2195 SHIP DIALOG Westmeath 55 *N/A Q1‐2021 and 2B)

2196 SHIP DIALOG Westmeath Lissywollen, Athlone (Phase 3A) 38 *N/A Q1‐2021

2197 SHIP DIALOG Westmeath Lissywollen, Athlone (Phase 3B) 22 *N/A Q1‐2021

SHIP CONSTRUCTION 2198 Westmeath Belvedere Hills, Mullingar 21 *N/A Q4‐2017 TURNKEY

24/05/2021 157/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 2199 Westmeath Cloon Lara, Mullingar 12 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 2200 Westmeath Abbeybrook, Kilbeggan 7 *N/A Q1‐2019 TURNKEY

Stage 4 approved Q2‐2019, SHIP CONSTRUCTION 2201 Westmeath Lakepoint, Mullingar 24 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 2202 Westmeath Coill Rua, Mullingar 6 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2203 Westmeath Rathgarve Green, Castlepollard 3 *N/A Q1‐2020 TURNKEY

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 2204 Westmeath Valley Cottages, Mullingar 3 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 2205 Westmeath Austin Friars Street, Mullingar 4 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 2206 Westmeath Rathgarve Green, Castlepollard 5 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION 2207 Westmeath Oakcrest, Ballinderry, Mullingar 8 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 2208 Westmeath St. Marys Place, Athlone 9 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 2209 Westmeath Rathgarve Green, Castlepollard 1 *N/A Q1‐2020 TURNKEY

Stage 1 approved Q2‐2018, SHIP CONSTRUCTION RAPID 2210 Westmeath O'Growney Green, Mullingar 26 *N/A outline design and costs VOLUMETRIC being prepared.

Stage 1 approved Q3‐2019, SHIP CONSTRUCTION RAPID 2211 Westmeath Dalton Park, Mullingar 15 *N/A outline design and costs VOLUMETRIC being prepared.

Stage 2 approved Q1‐2021, SHIP CONSTRUCTION RAPID 2212 Westmeath Water Street, Castlepollard 7 *N/A full design/tender being VOLUMETRIC prepared.

24/05/2021 158/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q1‐2021, SHIP CONSTRUCTION RAPID 2213 Westmeath Ennell Court, Mullingar (Phase 1) 15 *N/A full design/tender being VOLUMETRIC prepared.

2214 SHIP CONSTRUCTION Westmeath Bun Daire, Kinnegad (Phase 3) 12 *N/A Q3‐2019

2215 SHIP CONSTRUCTION Westmeath St. Laurence's Terrace, Mullingar 9 *N/A Q4‐2018

2216 SHIP CONSTRUCTION Westmeath Ennell Court, Mullingar 1 *N/A Q1‐2018

2217 SHIP CONSTRUCTION Westmeath Arcadia, Athlone (Phase 1.1) 21 *N/A Q2‐2020

2218 SHIP CONSTRUCTION Westmeath Ennell Court (Phase 2) 3 *N/A Q2‐2016

2219 SHIP CONSTRUCTION Westmeath Grange Crescent, Mullingar 2 *N/A Q1‐2016

2220 SHIP CONSTRUCTION Westmeath Ennell Court, Mullingar 19 *N/A Q1‐2021

Stage 3 approved Q1‐2020, the scheme is now 2221 SHIP CONSTRUCTION Westmeath Cloghanboy, Athlone 10 *N/A approved to proceed to tender.

2222 SHIP CONSTRUCTION Westmeath Bishopsgate, Mullingar 4 *N/A Q3‐2019

Stage 2 approved Q3‐2020, 2223 SHIP CONSTRUCTION Westmeath Arcadia, Athlone (Phase 2) 24 *N/A full design/tender being prepared.

Stage 2 approved Q4‐2020, 2224 SHIP CONSTRUCTION Westmeath Canal Avenue, Mullingar 32 *N/A full design/tender being prepared.

2225 SHIP CONSTRUCTION Westmeath Arcadia, Athlone (Phase 1.2) 12 *N/A Q3‐2020

2226 SHIP CONSTRUCTION Westmeath Ennell Court, Mullingar (Phase 2) 12 *N/A Q1‐2021

24/05/2021 159/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Túath Housing Association 2227 CAS CONSTRUCTION TURNKEY Westmeath Elm Row, Royal Canal, Mullingar 10 Q1‐2021 Ltd

Túath Housing Association 2228 CAS CONSTRUCTION TURNKEY Westmeath Elm Row, Royal Canal, Mullingar 17 Q4‐2019 Ltd

Túath Housing Association 2229 CAS CONSTRUCTION TURNKEY Westmeath Elm Row, Royal Canal, Mullingar 9 Q4‐2019 Ltd

Túath Housing Association 2230 CAS CONSTRUCTION Westmeath , Mullingar 4 Q4‐2019 Ltd

Athlone Road, Moate, Co. 2231 CALF Turnkey Westmeath 14 Oaklee Housing Q1‐2020 Westmeath (Phase 1)*

Cluain Mullen, Castlepollard, Co. 2232 CALF Turnkey Westmeath 8 Túath Housing Association Q4‐2020 Westmeath (Phase 1)

Cluain Mullen, Castlepollard, 2233 CALF Turnkey Westmeath 2 Túath Housing Association Q2‐2017 Westmeath (Phase 1)

Coill Rua, Mullingar, Co. 2234 CALF Turnkey Westmeath 13 Cluid Housing Q4‐2020 Westmeath (Phase 1)*

Coill Rua, Mullingar, Co. 2235 CALF Turnkey Westmeath 23 Cluid Housing Q1‐2021 Westmeath (Phase 2)*

Coill Rua, Mullingar, Co. 2236 CALF Turnkey Westmeath 8 Cluid Housing Q4‐2018 Westmeath (Phase 3)

Farran, Mullingar, Co. Westmeath 2237 CALF Construction Westmeath 10 Túath Housing Association Q4‐2019 (Phase 1)

Ghairdin Beag, Main Street, 2238 CALF Turnkey Westmeath Rathwire, Killucan, Co. 6 Túath Housing Association Q4‐2020 Westmeath (Phase 1)

Rahanine, Rochfortbridge, Co 2239 CALF Turnkey Westmeath 12 Túath Housing Association Q4‐2018 Westmeath (Phase 1)

Royal Canal, Ardmore Road, 2240 CALF Turnkey Westmeath Mullingar, Co. Westmeath (Phase 8 Túath Housing Association Q1‐2021 1)

24/05/2021 160/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

The Orchard, Athlone, Co. 2241 CALF Turnkey Westmeath 8 Túath Housing Association Q4‐2019 Westmeath (Phase 1)

The Orchard, Athlone, Co. 2242 CALF Turnkey Westmeath 14 Túath Housing Association Q2‐2020 Westmeath (Phase 2)*

The Orchard, Athlone, Co. 2243 CALF Turnkey Westmeath 10 Túath Housing Association Q2‐2020 Westmeath (Phase 3)

SHIP CONSTRUCTION 2244 Wexford Madeira Oaks, Wexford 8 *N/A Q3‐2017 TURNKEY

SHIP CONSTRUCTION Gleann an Ghairdin, Ballytegan 2245 Wexford 8 *N/A Q1‐2018 TURNKEY Road, Gorey

SHIP CONSTRUCTION 2246 Wexford Ard Uisce, Whiterock, Wexford 11 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2247 Wexford Rath an Duin, Castlebridge 3 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION Gleann an Ghairdin, Ballytegan 2248 Wexford 2 *N/A Q2‐2019 TURNKEY Road, Gorey (Phase 2a)

SHIP CONSTRUCTION Ard Uisce, Whiterock, Wexford ‐ 2249 Wexford 10 *N/A Q1‐2019 TURNKEY Phase 2

SHIP CONSTRUCTION Gleann an Ghairdin, Ballytegan 2250 Wexford 10 *N/A Q4‐2018 TURNKEY Road, Gorey (Phase 1b)

SHIP CONSTRUCTION 2251 Wexford Glen Aoibhinn, Ardamine, Gorey 5 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION Glen Aoibhinn, Ardamine, Gorey ‐ 2252 Wexford 2 *N/A Q1‐2019 TURNKEY Phase 2

SHIP CONSTRUCTION 2253 Wexford Whitewater Estuary, Ballyhack 3 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 2254 Wexford Riverchapel Lane, Gorey 4 *N/A Q4‐2019 TURNKEY

24/05/2021 161/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION Ard Uisce, Whiterock, Wexford‐ 2255 Wexford 4 *N/A Q2‐2019 TURNKEY Phase 3

SHIP CONSTRUCTION Glen Aoibhinn, Ardamine, Gorey ‐ 2256 Wexford 3 *N/A Q4‐2019 TURNKEY Phase 3

SHIP CONSTRUCTION Ard Uisce, Whiterock, Wexford 2257 Wexford 10 *N/A Q3‐2019 TURNKEY Phase 4

SHIP CONSTRUCTION St. Martin's Road, Rosslare 2258 Wexford 4 *N/A Q4‐2019 TURNKEY Harbour

SHIP CONSTRUCTION 2259 Wexford Clonattin Upper, Gorey 8 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Gleann an Ghairdin, Ballytegan 2260 Wexford 2 *N/A Q4‐2019 TURNKEY Road, Gorey (Phase 2b)

SHIP CONSTRUCTION 2261 Wexford Ard Uisce, Whiterock, Wexford 14 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION Gleann an Ghairdin, Ballytegan 2262 Wexford 1 *N/A Q3‐2019 TURNKEY Road, Gorey (Phase 2 C)

SHIP CONSTRUCTION 2263 Wexford Ballynaglough, Blackwater 16 *N/A Q4‐2019 TURNKEY

Stage 4 approved Q4‐2019, SHIP CONSTRUCTION 2264 Wexford Clonhasten, Enniscorthy 50 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION No.'s 64 & 74 Chapelwood, 2265 Wexford 2 *N/A Q1‐2020 TURNKEY Kilmuckridge

SHIP CONSTRUCTION 5 The Break Ayelsbridge, 2266 Wexford 1 *N/A Q1‐2020 TURNKEY Riverchapel

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 2267 Wexford Creagh, Gorey 39 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 2268 Wexford Ard Uisce, Whiterock, Wexford 1 *N/A Q1‐2020 TURNKEY

24/05/2021 162/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Gleann an Ghairdin, Gorey ‐ Phase 2269 Wexford 4 *N/A the scheme is fully TURNKEY 2 approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION Ard Uisce, Whiterock Hill, 2270 Wexford 5 *N/A the scheme is fully TURNKEY Wexford approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 2271 Wexford Cluain Beag, Clonard, Wexford 10 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 2272 Wexford Cluain Beag, Clonard, Wexford 10 *N/A the scheme is fully TURNKEY approved.

Stage 4 approved Q3‐2019, SHIP CONSTRUCTION 2273 Wexford Ard Uisce, Whiterock, Wexford 4 *N/A the scheme is fully TURNKEY approved.

2274 SHIP CONSTRUCTION Wexford SN Castlemoyle, New Ross 1 *N/A Q4‐2019

2275 SHIP CONSTRUCTION Wexford Cloghulatagh, Taghmon 18 *N/A Q4‐2020

2276 SHIP CONSTRUCTION Wexford Coolcotts, Clonard 7 *N/A Q4‐2019

2277 SHIP CONSTRUCTION Wexford Creagh, Gorey 10 *N/A Q1‐2019

2278 SHIP CONSTRUCTION Wexford Danescastle 10 *N/A Q1‐2019

2279 SHIP CONSTRUCTION Wexford Slippery Green, Wexford 10 *N/A Q3‐2019

2280 SHIP CONSTRUCTION Wexford Whiterock Hill, Wexford (Phase 1) 22 *N/A Q3‐2020

2281 SHIP CONSTRUCTION Wexford Cois Mara 2 *N/A Q3‐2018

2282 SHIP CONSTRUCTION Wexford Killeens, Wexford 40 *N/A Q2‐2020

24/05/2021 163/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

2283 SHIP CONSTRUCTION Wexford Oilgate, Enniscorthy 2 *N/A Q2‐2018

2284 SHIP CONSTRUCTION Wexford Cherryorchard, Enniscorthy 8 *N/A Q3‐2018

2285 SHIP CONSTRUCTION Wexford Ross Road, Enniscorthy 1 *N/A Q3‐2018

2286 SHIP CONSTRUCTION Wexford Baile Eoghain, Gorey 5 *N/A Q4‐2018

Baile an Trá, Riverchapel 2287 SHIP CONSTRUCTION Wexford 10 *N/A Q2‐2016 (Courtown Ardamine)

2288 SHIP CONSTRUCTION Wexford Shanna Court, Coolcotts 8 *N/A Q1‐2016

2289 SHIP CONSTRUCTION Wexford Francis Street, Wexford 1 *N/A Q1‐2017

2290 SHIP CONSTRUCTION Wexford Commodore Barry 1 *N/A Q2‐2016

2291 SHIP CONSTRUCTION Wexford Glentire, The Ballagh, Enniscorthy 7 *N/A Q2‐2019

Stage 4 approved Q3‐2020, 2292 SHIP CONSTRUCTION Wexford Carley's Bridge, Enniscorthy 17 *N/A the scheme is fully approved.

Stage 1 approved Q2‐2018, 2293 SHIP CONSTRUCTION Wexford Creagh (East), Gorey 4 *N/A outline design and costs being prepared.

Stage 2 approved Q3‐2020, 2294 SHIP CONSTRUCTION Wexford Rosbercon, New Ross 28 *N/A full design/tender being prepared.

2295 SHIP CONSTRUCTION Wexford Baile Eoghain, Gorey (Phase 2) 4 *N/A Q4‐2018

Stage 1 approved Q1‐2019, St. Joseph's, Wexford Street, 2296 SHIP CONSTRUCTION Wexford 20 *N/A outline design and costs Gorey being prepared.

24/05/2021 164/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q2‐2019, 2297 SHIP CONSTRUCTION Wexford Bullawn, Irishtown, New Ross 2 *N/A outline design and costs being prepared.

Stage 2 approved Q1‐2021, 2298 SHIP CONSTRUCTION Wexford Ballyhine, Barntown 7 *N/A full design/tender being prepared.

Stage 3 approved Q1‐2020, the scheme is now 2299 SHIP CONSTRUCTION Wexford Whiterock Hill, Wexford (Phase 2) 22 *N/A approved to proceed to tender.

Stage 1 approved Q2‐2018, 2300 SHIP CONSTRUCTION Wexford Creagh (West), Gorey 8 *N/A outline design and costs being prepared.

Stage 4 approved Q4‐2020, Túath Housing Association 2301 CAS CONSTRUCTION TURNKEY Wexford Clonattin, Gorey 6 the scheme is fully Ltd approved.

Stage 2 approved Q1‐2018, Grantstown Voluntary 2302 CAS CONSTRUCTION Wexford Barrystown 16 full design/tender being Housing Association Ltd prepared.

Rathangan Senior Citizens 2303 CAS CONSTRUCTION Wexford Rathangan 7 Q3‐2017 Housing Association Ltd

Stage 2 approved Q3‐2020, Wexford Women's Refuge, 2304 CAS CONSTRUCTION Wexford 12 *N/A full design/tender being Maudlintown prepared.

24 Units, Gleann an Ghairdin, 2305 CALF Turnkey Wexford 8 Túath Housing Association Q3‐2020 Gorey, Co. Wexford (Phase 1)

24 Units, Gleann an Ghairdin, 2306 CALF Turnkey Wexford 16 Túath Housing Association Q4‐2020 Gorey, Co. Wexford (Phase 2)

67 units, Coolcotts, Wexford 2307 CALF Turnkey Wexford 67 Cluid Housing Q3‐2020 (Phase 1)*

9 Units, Gleann an Ghairdin, 2308 CALF Turnkey Wexford 9 Túath Housing Association Q4‐2019 Gorey, Co. Wexford (Phase 1)

Ard Uisce, Wexford Town (Phase 2309 CALF Turnkey Wexford 5 Túath Housing Association Q4‐2017 1)

Ard Uisce, Whiterock, Wexford 2310 CALF Turnkey Wexford 1 Túath Housing Association Q1‐2018 (Phase 1)

24/05/2021 165/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Ard Uisce, Whiterock, Wexford 2311 CALF Turnkey Wexford 6 Túath Housing Association Q1‐2018 (Phase 1)

Ard Uisce, Whiterock, Wexford 2312 CALF Turnkey Wexford 6 Túath Housing Association Q1‐2017 (Phase 1)*

Ballyboggan, Castlebridge, Co Co ‐ Operative Housing 2313 CALF Turnkey Wexford 10 Q4‐2018 Wexford (Phase 1) Ireland Society Limited

Co ‐ Operative Housing 2314 CALF Turnkey Wexford Clonard, Wexford (Phase 1)* 10 Q4‐2019 Ireland Society Limited

Fearach Cnoic, Greenville, The 2315 CALF Turnkey Wexford 34 Oaklee Housing Q4‐2018 Moyne, Enniscorthy (Phase 1)

Fearach Cnoic, Greenville, The 2316 CALF Turnkey Wexford 6 Oaklee Housing Q2‐2019 Moyne, Enniscorthy (Phase 2)

Forgelands, Old Forge Road, 2317 CALF Turnkey Wexford Milehouse Road, Enniscorthy, Co. 18 Túath Housing Association Q3‐2020 Wexford (Phase 1)*

Fort Road, Ramsfort Park, Gorey, Co ‐ Operative Housing 2318 CALF Turnkey Wexford 11 Q4‐2020 Co. Wexford (Phase 1)* Ireland Society Limited

Gleann an Ghairdin, Gorey (Phase 2319 CALF Turnkey Wexford 9 Túath Housing Association Q4‐2019 1)

Gleann an Ghairdin, Gorey (Phase 2320 CALF Turnkey Wexford 9 Túath Housing Association Q1‐2020 2)

Greenville, Enniscorthy, Co. 2321 CALF Turnkey Wexford 6 Oaklee Housing Q2‐2019 Wexford (Phase 1)*

Co ‐ Operative Housing 2322 CALF Turnkey Wexford Hunters Green, Gorey (Phase 1) 7 Q2‐2016 Ireland Society Limited

Co ‐ Operative Housing 2323 CALF Turnkey Wexford Hunters Green, Gorey (Phase 2) 11 Q3‐2016 Ireland Society Limited

Co ‐ Operative Housing 2324 CALF Turnkey Wexford Hunters Green, Gorey (Phase 3) 11 Q1‐2017 Ireland Society Limited

24/05/2021 166/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Co ‐ Operative Housing 2325 CALF Turnkey Wexford Hunters Green, Gorey (Phase 4) 9 Q4‐2017 Ireland Society Limited

Kerlogue Manor, Roxborough, 2326 CALF Turnkey Wexford 14 Túath Housing Association Q4‐2020 Drinagh, Wexford (Phase 1)

Kerlogue Manor, Roxborough, 2327 CALF Turnkey Wexford 14 Túath Housing Association Q4‐2020 Drinagh, Wexford (Phase 2)

Kerlogue Manor, Roxborough, 2328 CALF Turnkey Wexford 16 Túath Housing Association Q1‐2021 Drinagh, Wexford (Phase 3)

Kerlogue Manor, Roxborough, 2329 CALF Turnkey Wexford 27 Túath Housing Association Q3‐2019 Drinagh, Wexford (Phase 4)*

Meadowfields Enniscorthy, Co. Co ‐ Operative Housing 2330 CALF Turnkey Wexford 12 Q3‐2016 Wexford (Phase 1) Ireland Society Limited

Meadowfields Phase 3, Co ‐ Operative Housing 2331 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 14 Q2‐2019 Ireland Society Limited 1)*

Meadowfields Phase 3, Co ‐ Operative Housing 2332 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 14 Q4‐2019 Ireland Society Limited 2)*

Old Forge Road, Milehouse Road, 2333 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 11 Túath Housing Association Q4‐2020 1)

Old Forge Road, Milehouse Road, 2334 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 14 Túath Housing Association Q4‐2020 2)*

Old Forge Road, Milehouse Road, 2335 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 8 Túath Housing Association Q1‐2021 3)*

Old Forge Road, Milehouse Road, 2336 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 8 Túath Housing Association Q4‐2019 4)*

Páirc na gCon, Greenville Lane, 2337 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 16 Cluid Housing Q3‐2019 1)*

Páirc na gCon, Greenville Lane, 2338 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 14 Cluid Housing Q3‐2019 2)*

24/05/2021 167/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Páirc na gCon, Greenville Lane, 2339 CALF Turnkey Wexford Enniscorthy, Co. Wexford (Phase 22 Cluid Housing Q3‐2019 3)

SHIP CONSTRUCTION 2340 Wicklow Mill Court, Tinahely 2 *N/A Q2‐2018 TURNKEY

SHIP CONSTRUCTION 2341 Wicklow No. 7 Mill Court, Tinahely 1 *N/A Q4‐2018 TURNKEY

SHIP CONSTRUCTION 2342 Wicklow Heatherside, Vale Road, Arklow 10 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 2343 Wicklow Fernhill, Arklow 1 *N/A Q3‐2018 TURNKEY

SHIP CONSTRUCTION 2344 Wicklow Mill Court, Tinahely 1 *N/A Q1‐2019 TURNKEY

SHIP CONSTRUCTION 2345 Wicklow Woodview Cottages, Rathnew 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2346 Wicklow Bollarney Woods, Wicklow Town 10 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 2347 Wicklow Mill Court, Tinahely 1 *N/A Q2‐2019 TURNKEY

SHIP CONSTRUCTION 2348 Wicklow Heatherside, Vale Road, Arklow 15 *N/A Q3‐2019 TURNKEY

SHIP CONSTRUCTION 2349 Wicklow Heatherside, Vale Road, Arklow 4 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2350 Wicklow Heatherside, Vale Road, Arklow 2 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2351 Wicklow Bollarney Woods, Wicklow Town 14 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2352 Wicklow Bollarney Woods, Wicklow Town 6 *N/A Q2‐2020 TURNKEY

24/05/2021 168/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

SHIP CONSTRUCTION 2353 Wicklow Heatherside, Vale Road, Arklow 9 *N/A Q4‐2019 TURNKEY

SHIP CONSTRUCTION 2354 Wicklow Kirvin Hill, Broomhall, Rathnew 2 *N/A Q2‐2019 TURNKEY

Stage 4 approved Q1‐2020, SHIP CONSTRUCTION Weaver Square, Baltinglass, Co. 2355 Wicklow 2 *N/A the scheme is fully TURNKEY Wicklow approved.

SHIP CONSTRUCTION 2356 Wicklow Carraig Beag, WicklowTown 5 *N/A Q3‐2020 TURNKEY

SHIP CONSTRUCTION 2357 Wicklow Bramble Hill, Lugdugff, Tinahely 2 *N/A Q4‐2020 TURNKEY

Stage 4 approved Q3‐2020, SHIP CONSTRUCTION 2358 Wicklow The Birches, Ballinaclash 2 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION 2359 Wicklow Bollarney Woods Phase 2 2 *N/A Q2‐2020 TURNKEY

SHIP CONSTRUCTION 2360 Wicklow Bollarney Woods Phase 2 1 *N/A Q4‐2020 TURNKEY

SHIP CONSTRUCTION 2361 Wicklow Bramble Hill, Lugduff, Tinahely 2 *N/A Q1‐2021 TURNKEY

Stage 4 approved Q1‐2021, SHIP CONSTRUCTION Vartry Heights, Roundwood, Co. 2362 Wicklow 3 *N/A the scheme is fully TURNKEY Wicklow approved.

Stage 4 approved Q2‐2020, SHIP CONSTRUCTION 2363 Wicklow Bramble Hill, Lugduff, Tinahely 1 *N/A the scheme is fully TURNKEY approved.

SHIP CONSTRUCTION RAPID Sli na Slainte, Whitehall, 2364 Wicklow 7 *N/A Q4‐2019 VOLUMETRIC Baltinglass

SHIP CONSTRUCTION RAPID 2365 Wicklow Merrymeeting View, Rathnew 46 *N/A Q2‐2019 VOLUMETRIC

SHIP CONSTRUCTION RAPID 2366 Wicklow Coolattin Oaks, Carnew (Phase 4) 22 *N/A Q4‐2020 VOLUMETRIC

24/05/2021 169/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 1 approved Q1‐2019, SHIP CONSTRUCTION RAPID 2367 Wicklow Shillelagh Phase 4 20 *N/A outline design and costs VOLUMETRIC being prepared.

SHIP CONSTRUCTION RAPID 2368 Wicklow Ashtown Lane, Wicklow Town 40 *N/A Q3‐2020 VOLUMETRIC

SHIP CONSTRUCTION RAPID 2369 Wicklow Ard na Greine, West Ward, Bray 31 *N/A Q2‐2020 VOLUMETRIC

SHIP CONSTRUCTION RAPID 2370 Wicklow Avondale Heights, Rathdrum 20 *N/A Q3‐2020 VOLUMETRIC

Stage 2 approved Q3‐2020, SHIP CONSTRUCTION RAPID Sheehan Court, Back Street, 2371 Wicklow 7 *N/A full design/tender being VOLUMETRIC Arklow prepared.

Mountainview, Moneycarroll, Stage 4 approved Q4‐2020, SHIP CONSTRUCTION RAPID 2372 Wicklow Newtownmountkennedy, Co. 22 *N/A the scheme is fully VOLUMETRIC Wicklow approved.

SHIP CONSTRUCTION RAPID Sli na Slainte, Whitehall, 2373 Wicklow 27 *N/A Q1‐2020 VOLUMETRIC Baltinglass ‐ Phase 2

Stage 1 approved Q4‐2019, SHIP CONSTRUCTION RAPID 2374 Wicklow Three Trouts, Greystones 40 *N/A outline design and costs VOLUMETRIC being prepared.

Stage 2 approved Q4‐2019, SHIP CONSTRUCTION RAPID 2375 Wicklow Greenhills Road, Wicklow Town 36 *N/A full design/tender being VOLUMETRIC prepared.

Stage 2 approved Q3‐2020, SHIP CONSTRUCTION RAPID 2376 Wicklow Cedar Court, Schools Road, Bray 14 *N/A full design/tender being VOLUMETRIC prepared.

SHIP CONSTRUCTION RAPID 2377 Wicklow Coolattin Oaks, Carnew (Phase 4) 8 *N/A Q1‐2021 VOLUMETRIC

Stage 2 approved Q1‐2021, SHIP CONSTRUCTION RAPID Rathnew, Merrymeeting, Co. 2378 Wicklow 21 *N/A full design/tender being VOLUMETRIC Wicklow (Phase 2) prepared.

Stage 1 approved Q1‐2021, SHIP CONSTRUCTION RAPID 2379 Wicklow Tinahely & Lugduff, Co Wicklow 20 *N/A outline design and costs VOLUMETRIC being prepared.

Delaney Park, Emoclew Road, 2380 SHIP CONSTRUCTION Wicklow 21 *N/A Q4‐2019 Arklow (Phase 3)

24/05/2021 170/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q1‐2021, 10A & 10 B Castle Villas, 2381 SHIP CONSTRUCTION Wicklow 2 *N/A full design/tender being Greystones prepared.

2382 SHIP CONSTRUCTION Wicklow Druids Brook, Kilcoole 2 *N/A Q3‐2019

Delaney Park, Emoclew Road, 2383 SHIP CONSTRUCTION Wicklow 17 *N/A Q3‐2019 Arklow

Delaney Park, Emoclew Road, 2384 SHIP CONSTRUCTION Wicklow 26 *N/A Q4‐2019 Arklow (Phase 2)

2385 SHIP CONSTRUCTION Wicklow FCA Hall, Wicklow Town 8 *N/A Q4‐2020

2386 SHIP CONSTRUCTION Wicklow Kilmantain Place, Bray 4 *N/A Q4‐2020

2387 SHIP CONSTRUCTION Wicklow O'Byrne Road, Bray 1 *N/A Q4‐2018

St Mary's Rd., Arklow (Old Library 2388 SHIP CONSTRUCTION Wicklow 7 *N/A Q4‐2018 Site)

2389 SHIP CONSTRUCTION Wicklow Jameson Heights, Kilmacanogue 20 *N/A Q4‐2020

2390 SHIP CONSTRUCTION Wicklow Avondale Heights, Rathdrum 20 *N/A Q4‐2018

Kilbride Lane, Bray (Murphy's 2391 SHIP CONSTRUCTION Wicklow 23 *N/A Q4‐2020 Lands)

2392 SHIP CONSTRUCTION Wicklow 16A Oak Drive, Blessington 1 *N/A Q3‐2019

Carrig Eden, 1 Marine Road, 2393 SHIP CONSTRUCTION Wicklow 35 *N/A Q4‐2020 Greystones

2394 SHIP CONSTRUCTION Wicklow Farrankelly, Greystones (Phase 2) 24 *N/A Q2‐2020

24/05/2021 171/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Stage 2 approved Q2‐2020, 2395 SHIP CONSTRUCTION Wicklow Blackhills, Glenealy, Co. Wicklow 2 *N/A full design/tender being prepared.

Stage 1 approved Q4‐2020, Age Friendly Apartments at Main 2396 SHIP CONSTRUCTION Wicklow 4 *N/A outline design and costs St, Kilcoole, Greystones being prepared.

Stage 2 approved Q1‐2021, 2397 SHIP CONSTRUCTION Wicklow Mill Road, Greystones 2 *N/A full design/tender being prepared.

Stage 1 approved Q4‐2020, 2398 SHIP CONSTRUCTION Wicklow Carraig Eden, Greysones Phase 3 14 *N/A outline design and costs being prepared.

Kilbride Lane, Bray (Murphy's 2399 SHIP CONSTRUCTION Wicklow 19 *N/A Q1‐2019 Lands)

Stage 1 approved Q1‐2021, 2400 SHIP CONSTRUCTION Wicklow Kockroe, Delgany, Co. Wicklow 2 *N/A outline design and costs being prepared.

2401 CAS CONSTRUCTION TURNKEY Wicklow Rathcoran Square, Baltinglass 8 Peter McVerry Trust Ltd Q1‐2021

Apt 1 & 2 Carrigbrae House, The Ark Housing Association 2402 CAS CONSTRUCTION TURNKEY Wicklow 2 Q4‐2020 Friary, Church Road, Bray Limited

Stage 4 approved Q3‐2019, CAS CONSTRUCTION SINGLE Hollybrook Park, Bray, Co. St. John of God Housing 2403 Wicklow 4 the scheme is fully STAGE Wicklow Association Ltd approved.

2404 CALF Turnkey Wicklow Abbey St, Wicklow (Phase 1) 6 Túath Housing Association Q4‐2018

Ballinahinch Woods, Ashford, Co. 2405 CALF Turnkey Wicklow 9 Cluid Housing Q4‐2019 Wicklow (Phase 1)*

Ballinahinch Woods, Ashford, Co. 2406 CALF Turnkey Wicklow 8 Cluid Housing Q3‐2020 Wicklow (Phase 2)*

Ballinahinch Woods, Ashford, Co. 2407 CALF Turnkey Wicklow 4 Cluid Housing Q4‐2020 Wicklow (Phase 3)*

Fairgreen Manor, Dunlavin, Co. Circle Voluntary Housing 2408 CALF Turnkey Wicklow 40 Q3‐2018 Wicklow (Phase 1)* Association Ltd

24/05/2021 172/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Glenheron, Greystones, Co 2409 CALF Turnkey Wicklow 5 Túath Housing Association Q2‐2018 Wicklow (Phase 1)*

Glenheron, Greystones, Co. 2410 CALF Turnkey Wicklow 8 Túath Housing Association Q4‐2018 Wicklow (Phase 1)*

Glenheron, Greystones, Co. 2411 CALF Turnkey Wicklow 7 Túath Housing Association Q2‐2019 Wicklow (Phase 2)*

Glenheron, Greystones, Co. 2412 CALF Turnkey Wicklow 4 Túath Housing Association Q4‐2019 Wicklow (Phase 3)*

Glenheron, Greystones, County 2413 CALF Turnkey Wicklow 2 Túath Housing Association Q4‐2020 Wicklow (Phase 1)

Hazelbrook Rise, Ballybeg, Co ‐ Operative Housing 2414 CALF Turnkey Wicklow 15 Q4‐2018 Rathnew, Co. Wicklow (Phase 1)* Ireland Society Limited

Hazelbrook Rise, Ballybeg, Co ‐ Operative Housing 2415 CALF Turnkey Wicklow 73 Q3‐2019 Rathnew, Co. Wicklow (Phase 2) Ireland Society Limited

Heatherside, Vale Road, Arklow, 2416 CALF Turnkey Wicklow 11 Túath Housing Association Q3‐2020 Co. Wicklow (Phase 1)

Heatherside, Vale Road, Arklow, 2417 CALF Turnkey Wicklow 14 Túath Housing Association Q3‐2020 Co. Wicklow (Phase 2)

Heatherside, Vale Road, Arklow, 2418 CALF Turnkey Wicklow 13 Túath Housing Association Q4‐2020 Co. Wicklow (Phase 3)

Lower Main Street, Arklow, Co. Clanmil Housing 2419 CALF Turnkey Wicklow 4 Q3‐2020 Wicklow (Phase 1) Association Ireland

Meadow Gate, Marlton Road, 2420 CALF Turnkey Wicklow 4 Túath Housing Association Q4‐2020 Wicklow Town (Phase 1)*

Phase 2, Hazelbrook, Rathnew, Co ‐ Operative Housing 2421 CALF Turnkey Wicklow 56 Q4‐2019 Co. Wicklow (Phase 1) Ireland Society Limited

Rathcoran House, Baltinglass, Co. 2422 CALF Turnkey Wicklow 16 Respond Q4‐2020 Wicklow (Phase 1)*

24/05/2021 173/174 Rebuilding Ireland ‐ Social Housing Construction Status Report Quarter 1 2021

Stage 4 Tender Report or No. Funding Programme LA Scheme/Project Name No. of Units Approved Housing Body Stage 1 Capital Appraisal Stage 2 Pre Planning Stage 3 Pre Tender design Final Turnkey/CALF On Site Completed approval

Rathcoran House, Baltinglass, Co. 2423 CALF Turnkey Wicklow 24 Respond Q3‐2019 Wicklow (Phase 2)*

Rathcoran House, Baltinglass, Co. 2424 CALF Turnkey Wicklow 16 Respond Q3‐2019 Wicklow (Phase 3)

Sessile Oaks, Ballyguile, Wicklow, 2425 CALF Turnkey Wicklow 14 Túath Housing Association Q1‐2017 Co. Wicklow (Phase 1)*

Sessile Oaks, Ballyguile, Wicklow, 2426 CALF Turnkey Wicklow 4 Túath Housing Association Q1‐2017 Co. Wicklow (Phase 2)

Sessile Oaks, Ballyguile, Wicklow, 2427 CALF Turnkey Wicklow 10 Túath Housing Association Q1‐2017 Co. Wicklow (Phase 3)

Ternlee, Coldross Lane, Kilcoole, 2428 CALF Turnkey Wicklow 4 Cluid Housing Q2‐2019 Co. Wicklow (Phase 1)*

Ternlee, Coldross Lane, Kilcoole, 2429 CALF Turnkey Wicklow 2 Cluid Housing Q4‐2019 Co. Wicklow (Phase 2)*

The Meadows, Ballynerrin, 2430 CALF Turnkey Wicklow 7 Túath Housing Association Q4‐2018 Wicklow Town (Phase 1)*

Viewmount, Rathdrum, County 2431 CALF Turnkey Wicklow 4 Túath Housing Association Q2‐2020 Wicklow (Phase 1)

Woodpark, Rathdrum, Co. 2432 CALF Turnkey Wicklow 4 Túath Housing Association Q3‐2019 Wicklow (Phase 1)*

PUBLIC PRIVATE PARTNERSHIP 2433 Wicklow Convent Lands (Phase 1) 23 *N/A Q2‐2020 (Bundle 1)

PUBLIC PRIVATE PARTNERSHIP 2434 Wicklow Convent Lands (Phase 2) 28 *N/A Q3‐2020 (Bundle 1)

24/05/2021 174/174