Consolidated Procurement Plan (updated 6 September, 2010) : Lifeline Roads Improvement Project (Credit 4549 AM) and Additional Financing - Lifeline Roads Improvement Project (Loan 7751 AM)

Review By Expected Estimated Bank Contract Procurement Invitation Bid- Start Completion Actual Contract price in Package No. Description/ Location Cost No. of Packages (PRIOR / Award Contractor Method Date Opening Date Date* the contract currency (US$ m) Post) Date Date

A B C D E F G H I K L M

1. WORKS for rehabilitation of roads: Aghavnadzor-link to M2 Highway (section 16) lot1, CJSC RBE of 1 NCB Prior 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Contract CW-NCB-1/2009 lot 1 Yeghegnadzor 260,270,830 AMD 1.24 2 Aghavnadzor-link to M2 Highway (section 16) lot2, CJSC RBE of NCB

Public Disclosure Authorized 2 Prior 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Contract CW-NCB-1/2009 lot 2 Yeghegnadzor 204,875,616 AMD Chkalov-link to M6 Highway (section 7), Contract CW- 3 0.41 1 NCB Post 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Tumanyani RBE OJSC NCB-2/2009 154,430,544 AMD Joint Venture of Motor ----link to M1 Transport Road of 4 0.74 1 NCB Post 31-Mar-09 21-Apr-09 29-Apr-09 5-May-09 30-Nov-10 Highway (section 12) Contract CW-NCB-3/2009 Ashotck CJSC and Akhuryani CHSHSH 276,830,259 AMD Vardenut-link to M3 Highway (section 1), Contract CW- CJSC 5 0.94 1 NCB Post 2-Apr-09 23-Apr-09 19-May-09 26-May-09 30-Nov-10 Mostovik LLC NCB-4/2009 354,837,553 AMD

Aygeshat-Janfida (section 2), Contract CW-NCB-5/2009 0.6 1 NCB Post 2-Apr-09 23-Apr-09 5-May-09 19-May-09 30-Nov-10 Tshanshinvarpet CJSC 6 227,332,359 AMD Geghanist-Horom (section 9) lot1, Contract CW-NCB- 7 NCB Post 2-Apr-09 23-Apr-09 29-Apr-09 5-May-09 30-Nov-10 UnderMoscow OJSC 6/2009 lot1 467,408,989 AMD Geghanist-Horom (section 9) lot2, Contract CW-NCB- 8 3.86 3 NCB Post 2-Apr-09 23-Apr-09 8-May-09 18-May-09 30-Nov-10 Blesk LLC 6/2009 lot2 610,182,373 AMD Geghanist-Horom (section 9) lot3, Contract CW-NCB- 9 NCB Post 2-Apr-09 23-Apr-09 29-Apr-09 5-May-09 30-Nov-10 UnderMoscow OJSC 6/2009 lot3 386,200,577 AMD Lernakert-link to M1 Highway (section 3), Contract CW- 10 1.3 1 NCB Post 2-Apr-09 23-Apr-09 4-May-09 7-May-09 30-Nov-10 Khachhar LLC NCB-7/2009 493,926,092 AMD Voghji-link to M1 Highway (section 10) lot1 , Contract CHSHSH 11 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 CW-NCB-8/2009 lot1 CJSC 546,205,046 AMD Voghji-link to M1 Highway (section 10) lot2, Contract Akhuryan CHSHSH 12 4.3 3 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10

Public Disclosure Authorized CW-NCB-8/2009 lot2 CJSC 471,044,022 AMD Voghji-link to M1 Highway (section 10) lot3, Contract Akhuryan CHSHSH 13 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 CW-NCB-8/2009 lot3 CJSC 599,851,530 AMD Joint Venture of Voskehask-link to M7 Highway (section 4), Contract Akhuryani Koopshin Ltd 14 0.68 1 NCB Post 2-Apr-09 23-Apr-09 5-May-09 7-May-09 30-Nov-10 CW-NCB-9/2009 and Akhuryan CHSHSH CJSC 256,816,373 AMD - (section 11) lot1, Contract CW-NCB- Akhuryan CHSHSH 15 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 10/2009 lot1 CJSC 520,977,631 AMD 2.87 2 Aygabats-Gyumri (section 11) lot2, Contract CW-NCB- 16 NCB Post 2-Apr-09 23-Apr-09 4-May-09 5-May-09 30-Nov-10 UnderMoscow OJSC 10/2009 lot 2 560,020,088 AMD Karchaghbyur-link to M11 Highway (section 5), 17 0.57 1 NCB Post 7-Apr-09 28-Apr-09 5-May-09 15-May-09 30-Nov-10 Kapavor Ltd Contract CW-NCB-11/2009 214,123,507 AMD Akunk-Vardenis (section 6), Contract CW-NCB- 18 0.83 1 NCB Post 7-Apr-09 28-Apr-09 5-May-09 15-May-09 30-Nov-10 Kapavor Ltd 12/2009 315,034,280 AMD Dzoragyugh-link toM10Highway (section 8), Contract 19 0.92 1 NCB Post 7-Apr-09 28-Apr-09 5-May-09 11-May-09 30-Nov-10 OJSC RBE OF GAVAR CW-NCB-13/2009 348,803,161 AMD L.Karmiraghbyur-Berd (section 13) lot1, Contract CW- 20 NCB Post 7-Apr-09 28-Apr-09 5-May-09 15-May-09 30-Nov-10 Tavushi CJSC CHSH NCB-14/2009 lot1 317,285,121 AMD 1.39 2 L.Karmiraghbyur-Berd (section 13) lot2, Contract CW- Chambarak CHSHSH 21 NCB Post 7-Apr-09 28-Apr-09 5-May-09 14-May-09 30-Nov-10 NCB-14/2009 lot2 OJSC 205,963,495 AMD

Public Disclosure Authorized Chochkan-Pokr Ayrum (section 14) lot 1, Contract CW- 22 NCB Post 7-Apr-09 28-Apr-09 29-Apr-09 8-May-09 30-Nov-10 Sahakyanshin CJSC NCB-15/2009 lot1 332,036,746 AMD 1.97 2 Chochkan-Pokr Ayrum (section 14) lot 2, Contract CW- 23 NCB Post 7-Apr-09 28-Apr-09 29-Apr-09 14-May-09 30-Nov-10 Levon Erkrord LLC NCB-15/2009 lot2 414,151,942 AMD Kurtan-Gyulakarak (section 15) lot1, Contract CW- 24 NCB Post 7-Apr-09 28-Apr-09 4-May-09 6-May-09 30-Nov-10 Argishti1 LLC NCB-16/2009 lot1 643,467,433 AMD 3.13 2 Public Disclosure Authorized 3.13 2 Kurtan-Gyulakarak (section 15) lot2, Contract CW-NCB- 25 NCB Post 7-Apr-09 28-Apr-09 4-May-09 20-May-09 30-Nov-10 Lorii CHSHSH CJSC 16/2009 lot2 535,667,075 AMD H17-Armavir- km18+850-km22+800 lot1, 26 NCB Post 13-Jun-09 6-Jul-09 10-Jul-09 1-Aug-09 30-Nov-10 Kotayki CH SH SH LLC Contract CW-NCB-17/2009 lot1 360,480,969 AMD 1.78 2 H17-Armavir-Isahakyan km22+800-km25+956 lot 2, Motor Transport Road of 27 NCB Post 13-Jun-09 6-Jul-09 10-Jul-09 20-Jul-09 30-Nov-10 Contract CW-NCB-17/2009 lot2 Talin OJSC 313,668,905 AMD Sers-Martiros-Zaritap km0+000-km3+681 lot 1, 28 NCB Post 13-Jun-09 6-Jul-09 16-Jul-09 21-Jul-09 30-Nov-10 Vayki CHSHSH CJSC 413,807,366 AMD Contract CW-NCB-18/2009 lot1 Sers-Martiros-Zaritap km3+681-km7+788 lot 2, 29 3.15 3 NCB Post 13-Jun-09 6-Jul-09 10-Jul-09 20-Jul-09 30-Nov-10 Vayki CHSHSH CJSC Contract CW-NCB-18/2009 lot2 331,537,983 AMD Sers-Martiros-Zaritap km7+788-km11+385 lot 3, 30 NCB Post 13-Jun-09 6-Jul-09 16-Jul-09 1-Aug-09 30-Nov-10 Kapani CHSHSH LLC Contract CW-NCB-18/2009 lot3 440,096,945 AMD Joint Venture of Sisiani Sisian-Brnakot km 0+000-km2+960 lot 1, Contract CW- 31 NCB Prior 24-Jun-09 15-Jul-09 22-Jul-09 1-Aug-09 15-Dec-10 BUAT LLC and Vahagn 347,656,092 AMD NCB-AF-1/2009 lot1 ev Samvel LLC 1.68 2 Joint Venture of Megru T Sisian-Brnakot km 2+960-km4+749 lot 2, Contract CW- 32 NCB Prior 24-Jun-09 15-Jul-09 22-Jul-09 1-Aug-09 15-Dec-10 SH SH D OJSC and 295,439,064 AMD NCB-AF-1/2009 lot2 Sisiani TCHANSHIN M17-Meghri km0+000-km3+000 Contract CW-NCB- LLC 33 1.04 1 NCB Prior 25-Jun-09 14-Aug-09 3-Sept-09 10-Sept-09 15-Dec-10 Megru T SH SH D OJSC AF-2/2009 396,165,535 AMD M2-Kavchut-Geghavanq km0+000-km2+500 lot 1, 34 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 17-Sept-09 15-Dec-10 Kapani CHSHSH LLC Contract CW-NCB-AF-7/2009 lot1 410,690,678 AMD 2.49 2 M2-Kavchut-Geghavanq km2+500-km6+000 lot 2, 35 Post 1-Aug-09 24-Aug-09 3-Sept-09 17-Sept-09 15-Dec-10 Kapani CHSHSH LLC Contract CW-NCB-AF-7/2009 lot2 542,518,327 AMD M17-Alvanq km0+000-km2+597, Contract CW-NCB- 36 0.83 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 15-Dec-10 Megru T SH SH D OJSC AF-6/2009 317,099,018 AMD M2-Levaz-Vahravar-Gudemnis-Kuris-Karjevan 37 (Vahravar- Gudemnis-Kuris section) 1.69 1 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 10-Sept-09 15-Dec-10 Megru T SH SH D OJSC km0+000–km4+330, Contract CW-NCB-AF-3/2009 652,226,328 AMD

Joint venture of M12-Hartashen km0+000-km5+090, Contract CW- 38 1.12 1 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 7-Sept-09 15-Dec-10 Kamurjshin CJSC NCB-AF-8/2009 Zangezurtransshin OJSC 427,567,919 AMD M2-Vardanidzor km0+000-km0+602 and Shvanidzor- 39 M17 km0+000-km1+684, Contract CW-NCB-AF- 0.62 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 15-Dec-10 Megru T SH SH D OJSC 5/2009 238,667,427 AMD

M2-Agarak km0+000-km2+175, Agarak bypass 40 km0+000-km0+970 and M2-Tkhkut 0.71 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 15-Dec-10 Megru T SH SH D OJSC km0+000–km0+420, Contract CW-NCB-AF-4/2009 272,292,871 AMD H3, Yerevan-Garni-Geghard (km 10+770-km 13+850), 41 0.92 1 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 14-Sept-09 15-Dec-10 Kotayki CH SH SH LLC Contract CW-NCB-AF-10/2009 353,907,135 AMD Tcambarak-Vahan km0+000-km3+000 lot 1, Contract 42 NCB Post 1-Aug-09 24-Aug-09 3-Sept-09 10-Sept-09 31-May-11 “Kapavor” Ltd CW-NCB-AF-9/2009 lot1 470,119,820 AMD 2.06 2 Tcambarak-Vahan 3+000-km 5+730 lot 2, Contract “Chambarak CHSHSH” 43 NCB Post 1-Aug-09 24-Aug-09 28-Aug-09 7-Sept-09 30-Aug-11 CW-NCB-AF-9/2009 lot2 OJSC 343,447,598 AMD CW-NCB-AF-1/2010 lot 1 H62, Sisian-Aghitu km 44 NCB Prior 22-May-10 22-Jun-10 11-Aug-10 11-Aug-10 30-Nov-12 Sisiani Chanshin LLC 273,394,709 AMD 0+000-km2+180 1.6 2 Joint Venture of Sisiani CW-NCB-AF-1/2010 lot 2 H62, Sisian-Aghitu km 45 NCB Prior 22-May-10 22-Jun-10 15-Jul-10 15-Jul-10 30-Nov-12 BUAT LLC and Vahagn 310,454,130 AMD 2+180-km4+680 ev Samvel LLC

CW-NCB-AF-8/2010 M4-Achajur km0+000-km3+676 1.09 1 NCB Prior 12-Jun-10 9-Jul-10 22-Jul-10 22-Jul-10 30-Nov-12 Ijevani T SH SH CJSC 46 397,078,026 AMD

CW-NCB-AF-2/2010, Lusahovit-Khashtarak-M4 1.8 1 NCB Prior 29-Jun-10 27-Jul-10 24-Aug-10 26-Aug-10 15-Dec-12 Ijevani T SH SH CJSC 47 659,019,276 AMD

Joint Venture of Tavushi CW-NCB-AF-3/2010, Movsesgyugh-Norashen-Verin 48 1.92 1 NCB Prior 29-Jun-10 27-Jul-10 25-Aug-10 31-Aug-10 15-Dec-12 Ch SH SH CJSC and 701,972,263 AMD Karmir Aghbyur Ararat Chanshin LLC

CW-NCB-AF-11/2010, H17-Armavir-Isahakyan- 49 0.99 1 NCB Post 26-Jun-10 23-Jul-10 17-Aug-10 20-Aug-10 15-Dec-12 Kotayqi CH SH SH LLC 363,922,359 AMD Gyumri km 9+425-km14+000 CW-NCB-AF-12/2010, H17-Armavir-Isahakyan- 50 0.97 1 NCB Post 26-Jun-10 23-Jul-10 17-Aug-10 20-Aug-10 15-Dec-12 Kotayqi CH SH SH LLC 354,990,720 AMD Gyumri km 14+000-km 18+842

51 M4-Gagarin-Geghamavan 1.49 1 NCB Prior 5-Jul-10 2-Aug-10 9-Sep-10 9-Sep-10 15-Dec-12 Sevani TSH SH CJSC 545,979,988 AMD

CW-NCB-AF-4/2010 H39-Karmirgyugh-Gegharquniq 52 1.51 1 NCB Prior 12-Jun-10 9-Jul-10 22-Jul-10 22-Jul-10 30-Nov-12 OJSC RBE OF GAVAR 554,097,285 AMD km9+200-km14+129 Joint Venture of Vayqi CH SH SH CJSC and 53 CW-NCB-AF-5/2010, M2-Zaritap 2.18 1 NCB Prior 29-Jun-10 27-Jul-10 25-Aug-10 25-Aug-10 15-Dec-12 798,512,220 AMD Meghru Ch SH SH TS OJSC CW-NCB-AF-7/2010, Eghegis-Hermon km 0+000- 54 1.12 1 NCB Prior 5-Jul-10 2-Aug-10 25-Aug-10 26-Aug-10 15-Dec-12 Khachar LLC 408,871,421 AMD km3+500 CW-NCB-AF-18/2010, Eghegis-Hermon km 3+500- CJSC RBE of 55 1.29 1 NCB Prior 29-Jun-10 27-Jul-10 24-Aug-10 26-Aug-10 15-Dec-12 471,283,944 AMD km7+540 Yeghegnadzor

56 CW-NCB-AF-13/2010, M12-Khdzoresk 0.477 1 NCB Post 26-Jun-10 23-Jul-10 6-Aug-10 8-Aug-10 15-Dec-12 Zangezurtransshin OJSC 174,257,728 AMD

57 CW-NCB-AF-16/2010, Akhuryan- 1.72 1 NCB Prior 5-Jul-10 2-Aug-10 23-Aug-10 23-Aug-10 15-Dec-12 UnderMoscow OJSC 630,024,205 AMD

Join venture of Akhuryani Koopshin LLC 58 CW-NCB-AF-17/2010, Karnut-Musaelyan 2.09 1 NCB Prior 5-Jul-10 2-Aug-10 25-Aug-10 25-Aug-10 15-Dec-12 765,590,000 AMD and Axuryani CH SH SH OJSC Axuryani CH SH SH 59 CW-NCB-AF-15/2010, Musaelyan-Jrarat 1.66 1 NCB Prior 5-Jul-10 2-Aug-10 25-Aug-10 25-Aug-10 15-Dec-12 607,446,600 AMD OJSC CW-NCB-AF-14/2010, Metsamor-Gay-Hovtashat 60 1.52 1 NCB Prior 5-Jul-10 2-Aug-10 18-Aug-10 7-Sep-10 15-Dec-12 Berma CJSC 557,522,640 AMD km4+100 km 8+926 CW-NCB-AF-6/2010, Metsamor-Haikashen-Gay km 61 0.79 1 NCB Post 26-Jun-10 23-Jul-10 6-Aug-10 11-Aug-10 15-Dec-12 Kuarlini LLC 290,000,417 AMD 0+000-km 2+718 CW-NCB-AF-9/2010 Vardenut-Aragatc km3+470- 62 0.99 1 NCB Prior 12-Jun-10 9-Jul-10 21-Jul-10 21-Jul-10 30-Nov-12 Kapavor Ltd 359,810,000 AMD km6+530

63 M4-Tcakhakadzor 0.68 1 NCB Post 10-Sep-10 9-Oct-10 16-Oct-10 16-Oct-10 15-Dec-12

64 Roads safety improvement minor works 0.50 5 NCB Post 2-Aug-10 23-Aug-10 30-Aug-10 6-Sep-10 30-Nov-12

Total 1. for works 70.23

* including DLP

2. GOODS 1 4WD Vehicle for Supervision (PIU) 0.032 1 SH Post 15-May-09 20-May-09 20-May-09 20-May-09 21-May-09 Muran Ltd 11,711,000.00 AMD 2 4WD Vehicle for Supervision (ARD) 0.05 1 SH Post 16-Oct-09 30-Oct-09 13-Nov-09 17-Nov-09 29-Dec-09 Muran Ltd 19,225,000.00 AMD 3 Vehicle for Supervision (PIU) 0.018 1 SH Post 2-Nov-09 17-Nov-09 13-Nov-09 17-Nov-09 18-Nov-09 Muran Ltd 5,990,000.00 AMD 4 Laboratory equipment (ARD) 0.05 1 SH Post 2-Jul-10 16-Aug-10 14-Aug-10 31-Aug-10 30-Nov-10 5 Fallind Weight Deflectometer (ARD) 0.2 1 ICB Prior 2-Jul-10 16-Aug-10 14-Aug-10 31-Aug-10 30-Nov-10

6 Roads and Pavement Condition Data Collection System 0.15 1 ICB Prior 2-Aug-10 16-Sep-10 14-Aug-10 30-Sep-10 30-Jan-11

7 IT equipment for PIU 0.01 1 SH Post 16-Oct-10 30-Oct-09 13-Nov-10 17-Nov-10 29-Dec-10 Total 2. for goods 0.51

Legend: For Lifeline Roads Improvement Project

ICB = International Competitive Bidding (in accordance with section 2 of the Guidelines) For works contracts valued at or more than US$4.0 m For goods contracts valued at or more than US$0.1 m NCB = National Competitive Bidding (in accordance with section 3.3 of the Guidelines) For works contracts valued less than US$4.0 m

SH = Shopping (in accordance with section 3.5 of the Guidelines) For goods and works contracts valued at or less than US$0.1 m Prior review For Works contracts: All ICB contracts. NCB first contract.

b) Pre Qualification= Not Anticipated

Domestic Preference= will apply to works contracts only

Legend: For Additional Financing - Lifeline Roads Improvement Project

ICB = International Competitive Bidding (in accordance with section 2 of the Guidelines) For works contracts valued more than US$2.0 m For goods contracts valued more than US$0.3 m NCB = National Competitive Bidding (in accordance with section 3.3 of the Guidelines) For works contracts valued at or less than US$2.0 m NCB =

For goods contracts valued more than US$0.1 m SH = Shopping (in accordance with section 3.5 of the Guidelines) For goods and works contracts valued at or less than US$0.1 m

Prior review

For Works contracts: All ICB contracts. All NCB contracts valued at or more than US$ 1 m. b) however, streamlined procedures would apply for civil works NCB contracts to be procured till the end of 2009, hence only first two NCB contracts will be subject to prior review.

For works contracts valued more than Pre Qualification= US$10.0 m will be used for ICB works contracts Domestic Preference= only

Estimated Review Adverti- Expected Selection Contract Comple- Package Cost by Bank sement Proposal Start Actual Contract price Description of Assignment/ Location Method Award tion Consultant Note No. (US$) / m Prior / for EOI Submission Date in the contract currency Date Date Post Date Date

3. CONSULTANTS' SERVICES Update of existing design and development of EF and 0.196 SSS Prior N/A 9-Jan-09 27-Jan-09 28-Jan-09 20-May-09 Dorproject Institute Ltd 73,059,948.00 AMD LRIP 1 EMP for LRIP(2009)

Technical Supervision of Civil Works for roads Joint Venture of SAFEGE 1.58 QCBS Prior 29-Dec-09 10-Apr-09 11-May-09 18-May-09 31-Dec-10 1,580,206.67 USD LRIP Rehabilitation and IRD 2

Design Author Supervision LRIP 0.125 SSS Prior N/A 27- Apr-09 26-May-09 26-May-09 30-Nov-09 Dorproject Institute Ltd 48,024,732.00 AMD LRIP 3 4 Independent Technical Audit for 2009 0.083 IC Prior 15-Apr-09 5-May-09 22-May-09 25-May-09 31-Dec-09 Mr. Janusz Sobieniak 83,253.40 USD LRIP

Joint Venture of Dorproject Design and EMP for LRIP Additional Financing 2009 0.29 CQS Prior 21-Apr-09 3-June-09 10-June-09 11-June-09 1-Sep-09 Institute Ltd and 107,159,724 AMD LRIP roads Transproject Institute CJSC 5

Joint Venture of Dorproject Design Author Supervision LRIP Additional Financing 0.105 SSS Prior N/A 20-July-09 27-July-09 3-Aug-09 30-Sep-10 Institute Ltd and 39,982,584 AMD AF LRIP for 2009 roads* Transproject Institute CJSC 6

Joint Venture of Dorproject Design & Supervision of LRIP Additional Financing 1.796 QCBS Prior 12-Jun-09 26-Oct-09 8-Feb-10 9-Feb-10 30-Dec-11 Institute Ltd and 1,795,800 USD AF LRIP 2010 roads Transproject Institute CJSC 7 8 Review of Pavement Design and Construction 0.1 IC Prior 15-Oct-09 3-Feb-10 17-Feb-10 1-Mar-10 31-Aug-10 Serji Amirkhanian 100,000 USD LRIP 9 Road Safety Audit Manual & Road Safety Audit 0.157 IC Prior 15-Aug-09 22-Feb-10 26-Mar-10 1-Apr-10 30-Oct-10 Phil Jordan 156,726.4 USD AF LRIP 10 Audit of Project accounts (2009-2011) 0.085 QCBS Prior 27-Jan-10 23-Apr-10 11-June-10 11-June-11 30-June-12 Global Audit Services lrd 85,333.33 USD AF LRIP 11 Independent Technical Audit for 2010 0.088 IC Prior 10-April-10 10-May-10 30-Jun-10 1-Jul-10 25-Dec-10 Walter Frankenberger 87,776 USD AF LRIP 12 Design and EMP for H-46 road section 0.04 CQ Prior 26-Feb-10 12-Mar-10 7-Apr-10 7-Apr-10 17-May-10 JV of Dorproject Institute ltd 15,929,004.00AMD AF LRIP 13 Training on Roads Performance Based Maintenance 0.04 SOE Prior N/A N/A N/A 15-Feb-11 15-Mar-11 and Artsakhtshan CJCS AF LRIP Total 3. For Consultancy Services 4.69

4. Operational Cost 0.6 TOTAL FOR PROJECT 76.025

Legend QCBS = Quality and Cost-based Selection (in accordance with sections 2.1 - 2.28 of the Consultant’s Guidelines) CQS = Selection based on Consultant’s Qualification (in accordance with section 3.7-3.8 of the Consultant’s Guidelines) SSS= Single source Selection (in accordance with section 3.9-13 of the Consultant’s Guidelines) IC = Individual Consultant (in accordance with section V of the Consultant’s Guidelines) Prior Review For firms: All contracts above US$100,000. All SSS contract. For individual consultants: All contracts above US$50,000.