China: Coastal Zone Sustainable Development Project 97243

Procurement Plan

Public Disclosure Authorized The procurement plan will cover the whole period of the project implementation. The Project Implementation Agency shall update the procurement plan throughout the duration of the project at least annually by including contracts previously awarded. All procurement plans, their updates or modifications shall be subject to Bank’s prior review and no objection before implementation.

I. General

1. Project information: Country: Borrower: The People’s Republic of China Project Name: Liaoning Coastal Zone Sustainable Development Project Loan No./Project Code: P126611 Project Implementation Agency (PIA): All procurement of the Project will be carried out by Public Disclosure Authorized the Provincial Project Management Office (the PMO) and each city’s Project Implementation Unit (the PIU). Detail project implementation agencies of the PMO and each city are as follows: No. Project City Main Procurement Activities Implementation Agency 1 Donggang Road CW and equipment Donggang city Municipal procurement Administration 2 Kuandian Road CW and equipment Kuandian county Urban procurement and Rural Construction Bureau 3 Road CW and bus procurement Panjin city Public Transportation Co., LTD 4 Chaoyang Road CW and equipment Chaoyang City Western

Public Disclosure Authorized procurement Industry New District Construction Investment Co., LTD 5 Lingyuan Road CW and equipment Lingyuan city Municipal procurement Administration 6 Lingyuan CW and equipment procurement of Lingyuan Emergency Water subproject Water Supply Construction Administration 7 Suizhong CW and equipment procurement of Municipal Water subproject Administration 8 Liaoning Consulting service Liaoning Provincial PMO

2. Bank’s Approval Date of the Procurement Plan :Original: November 2012 Revision: Public Disclosure Authorized January 8, 2013. As the procurement plan was not being implemented in 2013 a few changes were made on December 30, 2013, which include: a) for Chaoyang, adjustments were made between 3 contract packages of civil works on contract scope and contract value. Project scope and overall contract value stayed the same; b) for Donggang, adjustments were made on contract

scope of goods; c) for Panjin, number of vehicles to be procured is reduced to 140 units. (changes are highlighted in red).

3. Date of General Procurement Notice:

4. Period covered by this procurement plan: May 2013 to July 2018

II. Goods and Works and Non-consulting Services.

1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement:

Contract Procurement Type Prior Review Threshold Value (US$) Method

≥3,000,000 ICB All

<3,000,000 NCB First 2 NCB goods contracts by each PIU irrespective of value and Remarks: all contracts ≥ USD 3 million. Where goods are not normally available from within China, Goods/IT Systems the method of and Non-Consulting procurement Services will be ICB even if the contract value is less than USD 3 million.

<100,000 Shopping None

NA Direct All DC contracts contracting

≥25,000,000 ICB All

<25,000,000 NCB First 2 NCB works contracts by each PIU irrespective of value and Works/ Supply & all contracts ≥ USD 15 million. Installation <200,000 Shopping None

NA Direct All DC contracts contracting

Remarks: ICB –International Competitive Bidding NCB –National Competitive Bidding DC – Direct Contracting NA – Not Applicable

2. Prequalification. Bidders for all ICB works contracts shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines.

3. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: NA.

4. Reference to (if any) Project Operational/Procurement Manual: The PMO has prepared a procurement management manual, which has been reviewed by the Bank.

5. Any Other Special Procurement Arrangements: Retroactive financing will be agreed under this project. All advance contracts are subject to Bank’s prior review. Payments will be made only for contracts procured in accordance with applicable Bank procurement procedures.

Procurement Packages with Methods and Time Schedule Note: Exchange Rate 1USD=6.25CNY 1 2 3 4 5 6 7 8 9 10 11 Ref. Contract Estimated Contract Procurement Cont No No. Contract Cost category Method Pre- Domestic Review Expected ract (Description) (USD m) qualifica Preference by Bid- Perio tion (yes/no) Bank Opening d (yes/no) (Prior / Date (Mon Post) ths) Civil Work A. Urban road A4 Chaoyang road Four secondary roads and their ancillary works of CYRC Zhongxingjie, February, 1 7.046 W NCB No No Prior 24 01 Anlingdajie, 2015 Liunanlu and Yangliulu: roads, bridges, rainwater, sewage,

lighting, signs and markings, intersection canalized, garbage bin, litter bins, traffic signals, safety fence, bus stop kiosks. Roads of Wenhualu, Zhongxingjie and Anlingdajie, Liunanlu, Liugangxilu, Yangliulu and rainwater pump station CYRC and their February 2 16.243 W NCB No No Prior 24 02 ancillary 2016 works: roads, rainwater, sewage, lighting, greening, signs and markings, garbage bin, traffic signals, harbor stops. Liunanlu, Liufanglu, Liugangxilu and five branch roads and their ancillary works: roads, bridges, rainwater, CYRC February 3 sewage, 7.327 W NCB No No Post 24 03 2017 lighting, signs and markings, intersection canalized, garbage bin, little bins, traffic signals, traffic guard rails, bus stop kiosks. A1 Dongang city passenger station regional road network project Zhanqiandada DGRC December 4 o Avenue 10.67 W NCB No No Prior 14 01 2014 Road,

greening, transport facilities, drainage networks, integrated trench project: road length 1.466 km, carriageway 32,241 m2, 2 culverts, non- motorized vehicles 13,190 m2, sidewalks 14,655 m2, greening 3,658m2, rainwater pipe network 3,348m, sewer network 2,828 m, 82 street light, 5 groups of signal light, integrated pipe ditch (civil works) 1,411 m, and transportation facilities. Haiguanbeilu and Gaotiedajie, including roads, greening, transport facilities, lighting, drainage network, integrated pipe DGRC March 5 ditch projects: 14.90 W NCB No No Prior 18 02 2015 road length 2.748 km, carriageway 60,457 m2, 6 culverts, non- motor vehicle lanes 6,866 m2, sidewalk 21,984 m2, greening 3,074 m2, rainwater pipe network

5,037 m, sewer network 3,536 m, 159 street light, 5 groups of signal light, integrated pipe ditch (civil works) 2,680 m, and transportation facilities. Gaotiedajie, road, greening, transport facilities, drainage network, integrated pipe ditch projects: road length 0.981 km, carriageway 21,579 m2, non-motor vehicle lanes 6,866 m2, sidewalk 7,847 m2, 7 DGRC culverts, March 6 13.623 W NCB No No Post 16 03 greening 2,480 2016 m2, DN300- 1100mm rainwater pipe network (containing the connecting pipe) 2,051 m, DN300 mm sewer network 1,800 m, 4.31m×2.75- 3.65m integrated pipe ditch (civil works) 1952 m, and transportation facilities. A2 Kuandian road Roads and bridges and KDRC their ancillary October 7 6.88 W NCB No No Prior 24 01 works of 2014 Group road No.1, No.2,

No.3, No. 4, No.5, Beiyingerlu, Ergaozhonglu, Beiyingxilu, Xibinhedonglu , Chengxihuton g, Hekoulu, Beiyingdonglu , Buyechengyiti aojie,Xinhuaji e, Anfumenlu, Zuoziyuanjie, Gongpulu: roads, box culvert, rainwater, sewage, lighting, greening, signs and markings, intersection canalized, garbage bin, litter bin, traffic signals, safety fence, bus stop kiosks. Roads and their ancillary works of Dongbinhexilu , Yalujiangxilu, Hugouhelu, Zhanqianhuto ng, Xuefulu, Dankuanlu, KDRC Tiechanglu, 8 11.811 W NCB No No Post June 2015 24 02 Qingshangoul u: roads, rainwater, sewage, lighting, greening, signs and markings, garbage bin, traffic signals, harbour stops. A3 Lingyuan road LYRC0 Wenyi Road December 9 5.6 W NCB No No Prior 24 1 and its 2014

ancillary works: roads, bridges, rainwater, sewage, lighting, greening, signs and markings, garbage bins, traffic signals, safety fence, harbour stops. Wuliudalu Road and its ancillary works: roads, bridges, rainwater, sewage, LYRC0 10 lighting, 8.781 W NCB No No Prior June 2015 22 2 greening, signs and markings, garbage bin, traffic signals, safety fence, harbour stops. Binhedong Road and its ancillary works: roads, box culverts, rainwater, sewage, lighting, LYRC0 11 greening, 12.994 W NCB No No Post July 2016 30 3 signs and markings, garbage bin, litter bins, traffic signals, safety fence, bus stop kiosks. A5 Panjin traffic Shuangtaizi District parking project: total area of 24,000 PJRC0 December 12 m2, total 2.281 W NCB No No Prior 12 1 2014 standard berths of 106, works include: land consolidation,

venues pavement, construction and installation of the supporting repair room, office, canteen, checkpoints, railings and other ancillary facilities. parking project: total area of 50,000 m2, total standard berths of 198, works include: land consolidation, PJRC0 venues 13 3.874 W NCB No No Prior April 2015 12 2 pavement, construction and installation of the supporting repair room, office, canteen, checkpoints, railings and other ancillary facilities. B.Urban drainage and water reuse project B1 Lingyuan recycled water project Civil works of urban sewage main pipe, recycled water delivery pipeline and first-level, second-level LYWC pump station: November 14 13.44 W NCB No No Prior 30 01 urban sewage 2014 main pipeline of west bank of East Daling River (from Beidaqiao to Lingrexian highway bridge), east

bank of East Daling River (from Beidaqiao to the south-west of the industrial park), west bank of rain river of Daling River (from Nandaqiao to the wastewater treatment plant); recycled water delivery pipeline ( from the WWTP recycled water first-level pump station to the second- level pump station in the industrial park); civil works of the first-level and second-level pump station. Pipe network project at the industrial park: recycled LYWC water April 15 21.357 W NCB No Yes Prior 30 02 distribution 2016 pipe network, rainwater and sewage pipe network. B2 Suizhong drainage

project (cancelled)

Equipment procurement A.Urban roads A4 Chaoyang roads Maintenance equipment: Paver, excvavtor, CYRG loader, March 1 4.7986 G ICB No Yes Prior 12 01 dumper, 2015 vibroroller, roller, street light maintenance

truck, joint cutter, asphalt spreader, mark line equipment, sanitation facilities, traffic transformation facilities, signal lights and bus transformation facilities. A1 Dongang city passenger station regional road network project Road maintenance equipment: two aerial work platform, , one compression vehicle, two watering carts, two pull arm garbage trucks, two loader diggers, DGRG one tandem January 2 1.914 G ICB No Yes Prior 6 01 roller, one 2015 road repairing vehicle, one paver, one road roller, one filling and sealing machine, one traffic guardrail cleaning vehicle, one asphalt distributor. A2 Kuandian roads Traffic signal management equipment, KDRG garden and March 3 3.9672 G ICB No Yes Prior 12 01 sanitation 2015 facilities, road maintenance equipment. A3 Lingyuan roads Maintenance LYRG equipment: 1 February 4 0.6256 G NCB No No Prior 6 01 hydraulic 2017 aerial cage, 1

traxcavator, 1 roller, 1 loader-digger, 1 crane. A5 Panjin transport PJRG0 Purchase 140 December 5 16.32 G ICB No Yes Prior 6 1 LNG buses. 2014 B. Urban drainage and water reuse project B1 Lingyuan recycled water project Equipment purchase and installment of recycled water first-level and second-level pump station; LYWG technology Jan 6 0.7938 G NCB No No Prior 12 01 and power 2015 distribution equipment purchase of recycled water first-level and second-level pump station. B2 Suizhong drainage project

(cancelled)

III. Selection of Consultants

1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Expenditure Contract Value Procurement Method Bank Prior Review Category (US$) >= 300K QCBS, QBS Firms: First contract for each selection method and all contracts >=USD 300 K; < 300K QCBS, QBS, CQS Firms: All SSS contracts; Consultants N/A SSS Individual Consultant: Only in Exceptional Cases; N/A IC SSS for individual consultant: >=USD 20 K

Notes: QCBS: Quality- and Cost-Based Selection CQS: Selection Based on the Consultants’ Qualifications QBS: Quality-Based Selection SSS: Single Source Selection IC: Individual Consultant selection procedure NA: Not Applicable

2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD500, 000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.

3. Any Other Special Selection Arrangements: Retroactive financing will be agreed under this project. All advance contracts are subject to Bank’s prior review. Payments will be made only for contracts procured in accordance with applicable Bank procurement procedures.

4. Consultancy Assignments with Selection Methods and Time Schedule

1 2 3 4 5 6 7 8 Ref. No. Contract Description Estimated Selection Review Expected Contract No. of Cost Method by Bank Proposals Duration Assignment (USD 1m) (Prior / Submissio (months) Post) n Date 1.15 August 20, Project (The 2014 management 1 CS-1 contract QCBS Prior (Date of 60 consulting value Contract services is1.09) Signature) Assets December 2 CS-2 0.25 CQS Prior 12 management 2015 Traffic December 3 CS-3 0.25 CQS Post 12 management 2015